Uploaded by satiullahmaikash507

GEG DEMOLITION SCHEDULE

advertisement
DEMOLITION SCOPE HZEM WELL PAD 101 105
Activity Name
Original Duration Start
Classic Schedule Layout_PMS
Finish
2023
2024
2025
2026
05-Mar-23 17:25
2027
N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
DEM-GEG-8 DEMOLITION SCOPE HZEM WELL PAD 101 & 105
DEM-GEG-8.1 Milestone and Engineering
DEM-GEG-8.1.1 Contract Milestones
Project Start Date
Commencement of Work at Site
Subcontract Completion
DEM-GEG-8.1.3 Mobilization
Mobilization
DEM-GEG-8.1.2 Construction Milestones
Demolition and Dismantling of Well Pad 103
Demolition and Dismantling of Well Pad 102
Nitrogen Purging at Well-Pads (105,101,102) Completed
Decruding,Flushing of Well-Pad 105
Decruding,Flushing of Well-Pad 101
Decruding,Flushing of Well-Pad 102
Mothballing of RTP Line2
Mothballing of RTP Line1
Mothballing of RTP Line3
Demolition and Dismantling of Well Pad 105
Demolition and Dismantling of Well Pad 101
DEM-GEG-8.2 Decruding,Flushing of trunk lines and Well-Pad
DEM-GEG-8.2.1 Decruding,Flushing of trunk lines and Well-Pad-105
Nitrogen Purging
Equipment/Pump installation
Equipment/Pump Leakage Testing
Flushing activity with water
Products/Waste disposal
DEM-GEG-8.2.3 Decruding,Flushing of trunk lines and Well-Pad-101
Nitrogen Purging
Equipment/Pump installation
Equipment/Pump Leakage Testing
Flushing activity with water
Products/Waste disposal
DEM-GEG-8.2.4 Decruding,Flushing of trunk lines and Well-Pad-102
Nitrogen Purging
Equipment/Pump installation
Equipment/Pump Leakage Testing
Flushing activity with water
Products/Waste disposal
DEM-GEG-8.5 Removal,Truncation.Mothballing of RTP Lines
DEM-GEG-8.5.1 Segment #01 RTP Line1 105 - 101 (600m)
Exposing the RTP Line
Depressurization of RTP Line
Nitrogen Purging of RTP Line
Flushing & Decruding of RTP Line
Flaring of RTP Line
Air Drying of RTP Line
Truncation of RTP Line
Mothballing of RTP Line
Reinstatement of RTP Lines
Actual Level of Effort
Remaining Work
Milestone
Actual Work
Critical Remaining Work
summary
156d 22-Nov-22 A
22-May-23
22-May-23, DEM-GEG-8 DEMOLITION SCOPE HZEM WELL PAD 101 & 105
156d 22-Nov-22
22-May-23
22-May-23, DEM-GEG-8.1 Milestone and Engineering
156d
0d
0d
0d
11d
11d
156d
0d
0d
0d
0d
0d
0d
0d
0d
0d
0d
0d
51d
22-May-23
22-Nov-22
22-Nov-22
05-Dec-22
05-Dec-22 A
22-May-23
04-Dec-22
04-Dec-22
22-May-23
22-Nov-22
22-Nov-22
07-Dec-22
25-Jan-23
25-Jan-23
01-Feb-23
18-Feb-23
01-Mar-23
09-Mar-23
03-Apr-23
22-May-23
01-Feb-23
45d
2d
6d
1d
10d
5d
44d
2d
6d
1d
10d
5d
48d
1d
2d
1d
3d
2d
27d
05-Dec-22 A
05-Dec-22 A
01-Jan-23
08-Jan-23
09-Jan-23
21-Jan-23
06-Dec-22 A
06-Dec-22 A
01-Jan-23
08-Jan-23
09-Jan-23
21-Jan-23
08-Dec-22 A
08-Dec-22 A
26-Jan-23
28-Jan-23
28-Jan-23
31-Jan-23
07-Feb-23
25-Jan-23
06-Dec-22 A
07-Jan-23
08-Jan-23
19-Jan-23
25-Jan-23
25-Jan-23
07-Dec-22 A
07-Jan-23
08-Jan-23
19-Jan-23
25-Jan-23
01-Feb-23
08-Dec-22 A
28-Jan-23
28-Jan-23
30-Jan-23
01-Feb-23
09-Mar-23
10d
2d
2d
2d
2d
2d
2d
3d
3d
3d
19-Feb-23
19-Feb-23
20-Feb-23
21-Feb-23
22-Feb-23
23-Feb-23
25-Feb-23
26-Feb-23
27-Feb-23
27-Feb-23
01-Mar-23
20-Feb-23
21-Feb-23
22-Feb-23
23-Feb-23
25-Feb-23
26-Feb-23
28-Feb-23
01-Mar-23
01-Mar-23
22-Nov-22
22-Nov-22
22-Nov-22
22-May-23, DEM-GEG-8.1.1 Contract Milestones
Project Start Date, 22-Nov-22
Commencement of Work at Site, 05-Dec-22
Subcontract Completion,
04-Dec-22, DEM-GEG-8.1.3 Mobilization
Mobilization
22-May-23, DEM-GEG-8.1.2 Construction Milestones
Demolition and Dismantling of Well Pad 103,
Demolition and Dismantling of Well Pad 102,
Nitrogen Purging at Well-Pads (105,101,102) Completed,
Decruding,Flushing of Well-Pad 105,
Decruding,Flushing of Well-Pad 101,
Decruding,Flushing of Well-Pad 102,
Mothballing of RTP Line2,
Mothballing of RTP Line1,
Mothballing of RTP Line3,
Demolition and Dismantling of Well Pad 105,
Demolition and Dismantling of Well Pad 101,
01-Feb-23, DEM-GEG-8.2 Decruding,Flushing of trunk lines and Well-Pad
Page 1 of 4
25-Jan-23, DEM-GEG-8.2.1 Decruding,Flushing of trunk lines and Well-Pad-105
Nitrogen Purging
Equipment/Pump installation
Equipment/Pump Leakage Testing
Flushing activity with water
Products/Waste disposal
25-Jan-23, DEM-GEG-8.2.3 Decruding,Flushing of trunk lines and Well-Pad-101
Nitrogen Purging
Equipment/Pump installation
Equipment/Pump Leakage Testing
Flushing activity with water
Products/Waste disposal
01-Feb-23, DEM-GEG-8.2.4 Decruding,Flushing of trunk lines and Well-Pad-102
Nitrogen Purging
Equipment/Pump installation
Equipment/Pump Leakage Testing
Flushing activity with water
Products/Waste disposal
09-Mar-23, DEM-GEG-8.5 Removal,Truncation.Mothballing of RTP Lines
01-Mar-23, DEM-GEG-8.5.1 Segment #01 RTP Line1 105 - 101 (600m)
Exposing the RTP Line
Depressurization of RTP Line
Nitrogen Purging of RTP Line
Flushing & Decruding of RTP Line
Flaring of RTP Line
Air Drying of RTP Line
Truncation of RTP Line
Mothballing of RTP Line
Reinstatement of RTP Lines
TASK filter: All Activities
© Oracle Corporation
DEMOLITION SCOPE HZEM WELL PAD 101 105
Activity Name
Original Duration Start
Classic Schedule Layout_PMS
Finish
2023
2024
2025
2026
05-Mar-23 17:25
2027
N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
DEM-GEG-8.5.3 Segment #02 RTP Line2 105 - 101 (100m)
Exposing the RTP Line
Depressurization of RTP Line
Nitrogen Purging of RTP Line
Flushing & Decruding of RTP Line
Flaring of RTP Line
Air Drying of RTP Line
Truncation of RTP Line
Mothballing of RTP Line
Reinstatement of RTP Lines
DEM-GEG-8.5.4 Segment #03 RTP Line3 101- 103 (2900m)
Exposing the RTP Line
Depressurization of RTP Line
Nitrogen Purging of RTP Line
Flushing & Decruding of RTP Line
Flaring of RTP Line
Air Drying of RTP Line
Truncation of RTP Line
Mothballing of RTP Line
Reinstatement of RTP Lines
DEM-GEG-8.3 Demolition and Dismantling of Well Pad 101
DEM-GEG-8.3.1 Production Line
Production Line Dismantling
Cable Removal
Dismantling Cable Tray
Dismantling SS Tubling
DEM-GEG-8.3.2 Walls of Instruments
Dismantling Walls of Instruments
DEM-GEG-8.3.3 WHCP Return Line
Dismantling & removal of Well Head Control Panel Return Line
DEM-GEG-8.3.4 Lighting Pole
Dismantling & removal of Lighting Pole
DEM-GEG-8.3.5 Flame Deductor Pools
Dismantling & removal of Flame Deductor Pools
DEM-GEG-8.3.6 Inter Connecting Piping
Dismantling & removal of Inter Connecting Piping
DEM-GEG-8.3.7 Test Seperators
Dismantling & removal of Test Separator - A
Dismantling & removal of Test Separator - B
Dismantling & removal of Test Separator - C
Demolition of Foundations of Test Separators A,B & C
DEM-GEG-8.3.8 Knockout Drum
Dismantling & removal of Knockout Drum
Demolition of Foundation of Knockout Drum
DEM-GEG-8.3.9 Export Pump Skid
Dismantling & removal of Export Pump Skid
Demolition of Foundation of Export Pump Skid
DEM-GEG-8.3.10 Valve Skid
Dismantling & removal of Valve Skid
Demolition of Foundation of Valve Skid
Actual Level of Effort
Remaining Work
Milestone
Actual Work
Critical Remaining Work
summary
10d
2d
2d
2d
1d
3d
2d
3d
3d
3d
22d
6d
2d
4d
4d
3d
2d
4d
4d
4d
48d
07-Feb-23
07-Feb-23
08-Feb-23
09-Feb-23
11-Feb-23
12-Feb-23
13-Feb-23
14-Feb-23
15-Feb-23
15-Feb-23
13-Feb-23
13-Feb-23
18-Feb-23
20-Feb-23
22-Feb-23
25-Feb-23
27-Feb-23
28-Feb-23
02-Mar-23
06-Mar-23
07-Feb-23
18-Feb-23
08-Feb-23
09-Feb-23
11-Feb-23
11-Feb-23
14-Feb-23
14-Feb-23
16-Feb-23
18-Feb-23
18-Feb-23
09-Mar-23
19-Feb-23
19-Feb-23
23-Feb-23
26-Feb-23
27-Feb-23
28-Feb-23
04-Mar-23
06-Mar-23
09-Mar-23
03-Apr-23
18-Feb-23, DEM-GEG-8.5.3 Segment #02 RTP Line2 105 - 101 (100m)
Exposing the RTP Line
Depressurization of RTP Line
Nitrogen Purging of RTP Line
Flushing & Decruding of RTP Line
Flaring of RTP Line
Air Drying of RTP Line
Truncation of RTP Line
Mothballing of RTP Line
Reinstatement of RTP Lines
09-Mar-23, DEM-GEG-8.5.4 Segment #03 RTP Line3 101- 103 (2900m)
Exposing the RTP Line
Depressurization of RTP Line
Nitrogen Purging of RTP Line
Flushing & Decruding of RTP Line
Flaring of RTP Line
Air Drying of RTP Line
Truncation of RTP Line
Mothballing of RTP Line
Reinstatement of RTP Lines
03-Apr-23, DEM-GEG-8.3 Demolition and Dismantling of Well Pad 101
8d
2d
2d
2d
2d
2d
2d
2d
2d
2d
2d
2d
2d
2d
2d
4d
1d
1d
1d
2d
3d
1d
2d
3d
1d
2d
3d
1d
2d
07-Feb-23
07-Feb-23
09-Feb-23
12-Feb-23
14-Feb-23
16-Feb-23
16-Feb-23
16-Feb-23
16-Feb-23
16-Feb-23
16-Feb-23
16-Feb-23
16-Feb-23
16-Feb-23
16-Feb-23
18-Feb-23
18-Feb-23
18-Feb-23
19-Feb-23
20-Feb-23
22-Feb-23
22-Feb-23
23-Feb-23
26-Feb-23
26-Feb-23
27-Feb-23
01-Mar-23
01-Mar-23
02-Mar-23
15-Feb-23
08-Feb-23
11-Feb-23
13-Feb-23
15-Feb-23
18-Feb-23
18-Feb-23
18-Feb-23
18-Feb-23
18-Feb-23
18-Feb-23
18-Feb-23
18-Feb-23
18-Feb-23
18-Feb-23
21-Feb-23
18-Feb-23
18-Feb-23
19-Feb-23
21-Feb-23
25-Feb-23
22-Feb-23
25-Feb-23
28-Feb-23
26-Feb-23
28-Feb-23
04-Mar-23
01-Mar-23
04-Mar-23
15-Feb-23, DEM-GEG-8.3.1 Production Line
Production Line Dismantling
Cable Removal
Dismantling Cable Tray
Dismantling SS Tubling
18-Feb-23, DEM-GEG-8.3.2 Walls of Instruments
Dismantling Walls of Instruments
18-Feb-23, DEM-GEG-8.3.3 WHCP Return Line
Dismantling & removal of Well Head Control Panel Return Line
18-Feb-23, DEM-GEG-8.3.4 Lighting Pole
Dismantling & removal of Lighting Pole
18-Feb-23, DEM-GEG-8.3.5 Flame Deductor Pools
Dismantling & removal of Flame Deductor Pools
18-Feb-23, DEM-GEG-8.3.6 Inter Connecting Piping
Dismantling & removal of Inter Connecting Piping
21-Feb-23, DEM-GEG-8.3.7 Test Seperators
Dismantling & removal of Test Separator - A
Dismantling & removal of Test Separator - B
Dismantling & removal of Test Separator - C
Demolition of Foundations of Test Separators A,B & C
25-Feb-23, DEM-GEG-8.3.8 Knockout Drum
Dismantling & removal of Knockout Drum
Demolition of Foundation of Knockout Drum
28-Feb-23, DEM-GEG-8.3.9 Export Pump Skid
Dismantling & removal of Export Pump Skid
Demolition of Foundation of Export Pump Skid
04-Mar-23, DEM-GEG-8.3.10 Valve Skid
Dismantling & removal of Valve Skid
Demolition of Foundation of Valve Skid
Page 2 of 4
TASK filter: All Activities
© Oracle Corporation
DEMOLITION SCOPE HZEM WELL PAD 101 105
Activity Name
Original Duration Start
Classic Schedule Layout_PMS
Finish
2023
2024
2025
2026
05-Mar-23 17:25
2027
N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
DEM-GEG-8.3.11 Instrument Air Skid
Dismantling & removal of Instrument Air Skid
Demolition of Foundation of Instrument Air Skid
DEM-GEG-8.3.12 Well Head Control Panel (A,B,C)
Dismantling & removal of Well Head Control Panel - A
Excavation of Foundation of Well Head Control Panel - A
Lifting Foundation of Well Head Control Panel - A
Dismantling & removal of Well Head Control Panel -B
Excavation of Foundation of Well Head Control Panel - B
Lifting Foundation of Well Head Control Panel - B
Dismantling & removal of Well Head Control Panel - C
Excavation of Foundation of Well Head Control Panel - C
Lifting Foundation of Well Head Control Panel - C
DEM-GEG-8.3.13 RTU Shelter
Dismantling & removal of RTU Shelter
DEM-GEG-8.3.14 Propane Skid
Dismantling & removal of Propane Skid
Demolition of Foundation of Propane Skid
DEM-GEG-8.3.15 Diesel Generator Skid
Dismantling & removal of Diesel Generator Skid (Lifting & Removal)
Demolition of Foundation of Diesel Generator Skid
DEM-GEG-8.3.16 Flare Stack & Flare Stack Line
Dismantling & removal of Flare Stack
Manual Excavation
Lifting Foundation
Flare Stack Line Removal
Dismantling & removal of Structure for Flare Stack
DEM-GEG-8.3.17 Surge Drum
Surge Drum
DEM-GEG-8.3.18 Fencing & Fence Gate
Dismantling & Removal of Fence & Fence Gate
DEM-GEG-8.3.19 Site Office
Dismantling & Removal of Site Office
DEM-GEG-8.4 Demolition and Dismantling of Well Pad 105
DEM-GEG-8.4.1 Production Line
Production Line Dismantling
Cable Removal
Dismantling Cable Trays
Dismantling SS Tubling
DEM-GEG-8.4.2 Walls of Instruments
Dismantling Walls of Instruments
DEM-GEG-8.4.3 WHCP Return Line
Dismantling & removal of Well Head Control Panel Return Line
DEM-GEG-8.4.4 Lighting Pole
Dismantling & removal of Lighting Pole
DEM-GEG-8.4.5 Flame Deductor Pools
Dismantling & removal of Flame Deductor Pools
DEM-GEG-8.4.6 Inter Connecting Piping
Dismantling & removal of Inter Connecting Piping
DEM-GEG-8.4.7 Test Seperators
Actual Level of Effort
Remaining Work
Milestone
Actual Work
Critical Remaining Work
summary
3d
1d
2d
9d
1d
1d
1d
1d
1d
1d
1d
1d
1d
1d
1d
4d
2d
2d
2d
1d
1d
7d
1d
2d
1d
2d
2d
2d
2d
2d
2d
1d
1d
51d
05-Mar-23
05-Mar-23
06-Mar-23
07-Mar-23
07-Mar-23
08-Mar-23
09-Mar-23
11-Mar-23
12-Mar-23
13-Mar-23
14-Mar-23
15-Mar-23
16-Mar-23
16-Mar-23
16-Mar-23
18-Mar-23
18-Mar-23
20-Mar-23
22-Mar-23
22-Mar-23
23-Mar-23
23-Mar-23
23-Mar-23
25-Mar-23
27-Mar-23
28-Mar-23
29-Mar-23
01-Apr-23
01-Apr-23
01-Apr-23
01-Apr-23
03-Apr-23
03-Apr-23
25-Mar-23
07-Mar-23
05-Mar-23
07-Mar-23
16-Mar-23
07-Mar-23
08-Mar-23
09-Mar-23
11-Mar-23
12-Mar-23
13-Mar-23
14-Mar-23
15-Mar-23
16-Mar-23
16-Mar-23
16-Mar-23
21-Mar-23
19-Mar-23
21-Mar-23
23-Mar-23
22-Mar-23
23-Mar-23
30-Mar-23
23-Mar-23
26-Mar-23
27-Mar-23
29-Mar-23
30-Mar-23
02-Apr-23
02-Apr-23
02-Apr-23
02-Apr-23
03-Apr-23
03-Apr-23
22-May-23
4d
3d
3d
3d
4d
3d
3d
3d
3d
4d
4d
4d
4d
4d
4d
7d
25-Mar-23
25-Mar-23
25-Mar-23
25-Mar-23
25-Mar-23
26-Mar-23
26-Mar-23
26-Mar-23
26-Mar-23
26-Mar-23
26-Mar-23
26-Mar-23
26-Mar-23
27-Mar-23
27-Mar-23
01-Apr-23
28-Mar-23
27-Mar-23
27-Mar-23
27-Mar-23
28-Mar-23
28-Mar-23
28-Mar-23
28-Mar-23
28-Mar-23
29-Mar-23
29-Mar-23
29-Mar-23
29-Mar-23
30-Mar-23
30-Mar-23
08-Apr-23
Page 3 of 4
07-Mar-23, DEM-GEG-8.3.11 Instrument Air Skid
Dismantling & removal of Instrument Air Skid
Demolition of Foundation of Instrument Air Skid
16-Mar-23, DEM-GEG-8.3.12 Well Head Control Panel (A,B,C)
Dismantling & removal of Well Head Control Panel - A
Excavation of Foundation of Well Head Control Panel - A
Lifting Foundation of Well Head Control Panel - A
Dismantling & removal of Well Head Control Panel -B
Excavation of Foundation of Well Head Control Panel - B
Lifting Foundation of Well Head Control Panel - B
Dismantling & removal of Well Head Control Panel - C
Excavation of Foundation of Well Head Control Panel - C
Lifting Foundation of Well Head Control Panel - C
16-Mar-23, DEM-GEG-8.3.13 RTU Shelter
Dismantling & removal of RTU Shelter
21-Mar-23, DEM-GEG-8.3.14 Propane Skid
Dismantling & removal of Propane Skid
Demolition of Foundation of Propane Skid
23-Mar-23, DEM-GEG-8.3.15 Diesel Generator Skid
Dismantling & removal of Diesel Generator Skid (Lifting & Removal)
Demolition of Foundation of Diesel Generator Skid
30-Mar-23, DEM-GEG-8.3.16 Flare Stack & Flare Stack Line
Dismantling & removal of Flare Stack
Manual Excavation
Lifting Foundation
Flare Stack Line Removal
Dismantling & removal of Structure for Flare Stack
02-Apr-23, DEM-GEG-8.3.17 Surge Drum
Surge Drum
02-Apr-23, DEM-GEG-8.3.18 Fencing & Fence Gate
Dismantling & Removal of Fence & Fence Gate
03-Apr-23, DEM-GEG-8.3.19 Site Office
Dismantling & Removal of Site Office
22-May-23, DEM-GEG-8.4 Demolition and Dismantling of Well Pad 105
28-Mar-23, DEM-GEG-8.4.1 Production Line
Production Line Dismantling
Cable Removal
Dismantling Cable Trays
Dismantling SS Tubling
28-Mar-23, DEM-GEG-8.4.2 Walls of Instruments
Dismantling Walls of Instruments
28-Mar-23, DEM-GEG-8.4.3 WHCP Return Line
Dismantling & removal of Well Head Control Panel Return Line
29-Mar-23, DEM-GEG-8.4.4 Lighting Pole
Dismantling & removal of Lighting Pole
29-Mar-23, DEM-GEG-8.4.5 Flame Deductor Pools
Dismantling & removal of Flame Deductor Pools
30-Mar-23, DEM-GEG-8.4.6 Inter Connecting Piping
Dismantling & removal of Inter Connecting Piping
08-Apr-23, DEM-GEG-8.4.7 Test Seperators
TASK filter: All Activities
© Oracle Corporation
DEMOLITION SCOPE HZEM WELL PAD 101 105
Activity Name
Original Duration Start
Classic Schedule Layout_PMS
Finish
2023
2024
2025
2026
05-Mar-23 17:25
2027
N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
Dismantling & removal of Test Separator - A
Dismantling & removal of Test Separator - B
Dismantling & removal of Test Separator - C
Dismantling & removal of Test Separator - D
Demolition of Foundations of Test Separators A,B,C & D
DEM-GEG-8.4.8 Knockout Drum
Dismantling & removal of Knockout Drum
Demolition of Foundation of Knockout Drum
DEM-GEG-8.4.9 Export Pump Skid
Dismantling & removal of Export Pump Skid
Demolition of Foundation of Export Pump Skid
DEM-GEG-8.4.10 Valve Skid
Dismantling & removal of Valve Skid
Demolition of Foundation of Valve Skid
DEM-GEG-8.4.11 Instrument Air Skid
Dismantling & removal of Instrument Air Skid
Demolition of Foundation of Instrument Air Skid
DEM-GEG-8.4.12 Well Head Control Panel (A,B)
Dismantling & removal of Well Head Control Panel - A
Excavation of Foundation of Well Head Control Panel - A
Lifting Foundation of Well Head Control Panel - A
Dismantling & removal of Well Head Control Panel - B
Excavation of Foundation of Well Head Control Panel - B
Lifting Foundation of Well Head Control Panel - B
DEM-GEG-8.4.13 RTU Shelter
Dismantling & removal of RTU Shelter
DEM-GEG-8.4.14 Propane Skid
Dismantling & removal of Propane Skid
Demolition of Foundation of Propane Skid
DEM-GEG-8.4.15 Diesel Generator Skid
Dismantling & removal of Diesel Generator Skid (Lifting & Removal)
Demolition of Foundation of Diesel Generator Skid
DEM-GEG-8.4.16 Flare Stack & Flare Stack Line
Dismantling & removal of Flare Stack
Flare Stack Line Removal
Manual Excavation
Lifting Foundation
Dismantling & removal of Structure for Flare Stack
DEM-GEG-8.4.17 Surge Drum
Surge Drum
DEM-GEG-8.4.18 Fencing & Fence Gate
Dismantling & Removal of Fence & Fence Gate
DEM-GEG-8.4.19 Site Office
Dismantling & Removal of Site Office
Actual Level of Effort
Remaining Work
Milestone
Actual Work
Critical Remaining Work
summary
1d
1d
1d
1d
3d
3d
2d
1d
3d
2d
1d
4d
3d
1d
3d
2d
1d
6d
1d
1d
1d
1d
1d
1d
2d
2d
3d
2d
3d
4d
3d
1d
8d
3d
2d
1d
1d
1d
1d
1d
1d
1d
1d
1d
01-Apr-23
02-Apr-23
03-Apr-23
04-Apr-23
05-Apr-23
09-Apr-23
09-Apr-23
11-Apr-23
12-Apr-23
12-Apr-23
15-Apr-23
16-Apr-23
16-Apr-23
19-Apr-23
20-Apr-23
20-Apr-23
23-Apr-23
24-Apr-23
24-Apr-23
25-Apr-23
26-Apr-23
27-Apr-23
29-Apr-23
30-Apr-23
01-May-23
01-May-23
03-May-23
03-May-23
03-May-23
07-May-23
07-May-23
10-May-23
11-May-23
11-May-23
15-May-23
17-May-23
18-May-23
20-May-23
21-May-23
21-May-23
21-May-23
21-May-23
22-May-23
22-May-23
01-Apr-23
02-Apr-23
03-Apr-23
04-Apr-23
08-Apr-23
11-Apr-23
10-Apr-23
11-Apr-23
15-Apr-23
13-Apr-23
15-Apr-23
19-Apr-23
18-Apr-23
19-Apr-23
23-Apr-23
22-Apr-23
23-Apr-23
30-Apr-23
24-Apr-23
25-Apr-23
26-Apr-23
27-Apr-23
29-Apr-23
30-Apr-23
02-May-23
02-May-23
06-May-23
04-May-23
06-May-23
10-May-23
09-May-23
10-May-23
20-May-23
14-May-23
16-May-23
17-May-23
18-May-23
20-May-23
21-May-23
21-May-23
21-May-23
21-May-23
22-May-23
22-May-23
Page 4 of 4
Dismantling & removal of Test Separator - A
Dismantling & removal of Test Separator - B
Dismantling & removal of Test Separator - C
Dismantling & removal of Test Separator - D
Demolition of Foundations of Test Separators A,B,C & D
11-Apr-23, DEM-GEG-8.4.8 Knockout Drum
Dismantling & removal of Knockout Drum
Demolition of Foundation of Knockout Drum
15-Apr-23, DEM-GEG-8.4.9 Export Pump Skid
Dismantling & removal of Export Pump Skid
Demolition of Foundation of Export Pump Skid
19-Apr-23, DEM-GEG-8.4.10 Valve Skid
Dismantling & removal of Valve Skid
Demolition of Foundation of Valve Skid
23-Apr-23, DEM-GEG-8.4.11 Instrument Air Skid
Dismantling & removal of Instrument Air Skid
Demolition of Foundation of Instrument Air Skid
30-Apr-23, DEM-GEG-8.4.12 Well Head Control Panel (A,B)
Dismantling & removal of Well Head Control Panel - A
Excavation of Foundation of Well Head Control Panel - A
Lifting Foundation of Well Head Control Panel - A
Dismantling & removal of Well Head Control Panel - B
Excavation of Foundation of Well Head Control Panel - B
Lifting Foundation of Well Head Control Panel - B
02-May-23, DEM-GEG-8.4.13 RTU Shelter
Dismantling & removal of RTU Shelter
06-May-23, DEM-GEG-8.4.14 Propane Skid
Dismantling & removal of Propane Skid
Demolition of Foundation of Propane Skid
10-May-23, DEM-GEG-8.4.15 Diesel Generator Skid
Dismantling & removal of Diesel Generator Skid (Lifting & Removal)
Demolition of Foundation of Diesel Generator Skid
20-May-23, DEM-GEG-8.4.16 Flare Stack & Flare Stack Line
Dismantling & removal of Flare Stack
Flare Stack Line Removal
Manual Excavation
Lifting Foundation
Dismantling & removal of Structure for Flare Stack
21-May-23, DEM-GEG-8.4.17 Surge Drum
Surge Drum
21-May-23, DEM-GEG-8.4.18 Fencing & Fence Gate
Dismantling & Removal of Fence & Fence Gate
22-May-23, DEM-GEG-8.4.19 Site Office
Dismantling & Removal of Site Office
TASK filter: All Activities
© Oracle Corporation
Download