DEMOLITION SCOPE HZEM WELL PAD 101 105 Activity Name Original Duration Start Classic Schedule Layout_PMS Finish 2023 2024 2025 2026 05-Mar-23 17:25 2027 N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J DEM-GEG-8 DEMOLITION SCOPE HZEM WELL PAD 101 & 105 DEM-GEG-8.1 Milestone and Engineering DEM-GEG-8.1.1 Contract Milestones Project Start Date Commencement of Work at Site Subcontract Completion DEM-GEG-8.1.3 Mobilization Mobilization DEM-GEG-8.1.2 Construction Milestones Demolition and Dismantling of Well Pad 103 Demolition and Dismantling of Well Pad 102 Nitrogen Purging at Well-Pads (105,101,102) Completed Decruding,Flushing of Well-Pad 105 Decruding,Flushing of Well-Pad 101 Decruding,Flushing of Well-Pad 102 Mothballing of RTP Line2 Mothballing of RTP Line1 Mothballing of RTP Line3 Demolition and Dismantling of Well Pad 105 Demolition and Dismantling of Well Pad 101 DEM-GEG-8.2 Decruding,Flushing of trunk lines and Well-Pad DEM-GEG-8.2.1 Decruding,Flushing of trunk lines and Well-Pad-105 Nitrogen Purging Equipment/Pump installation Equipment/Pump Leakage Testing Flushing activity with water Products/Waste disposal DEM-GEG-8.2.3 Decruding,Flushing of trunk lines and Well-Pad-101 Nitrogen Purging Equipment/Pump installation Equipment/Pump Leakage Testing Flushing activity with water Products/Waste disposal DEM-GEG-8.2.4 Decruding,Flushing of trunk lines and Well-Pad-102 Nitrogen Purging Equipment/Pump installation Equipment/Pump Leakage Testing Flushing activity with water Products/Waste disposal DEM-GEG-8.5 Removal,Truncation.Mothballing of RTP Lines DEM-GEG-8.5.1 Segment #01 RTP Line1 105 - 101 (600m) Exposing the RTP Line Depressurization of RTP Line Nitrogen Purging of RTP Line Flushing & Decruding of RTP Line Flaring of RTP Line Air Drying of RTP Line Truncation of RTP Line Mothballing of RTP Line Reinstatement of RTP Lines Actual Level of Effort Remaining Work Milestone Actual Work Critical Remaining Work summary 156d 22-Nov-22 A 22-May-23 22-May-23, DEM-GEG-8 DEMOLITION SCOPE HZEM WELL PAD 101 & 105 156d 22-Nov-22 22-May-23 22-May-23, DEM-GEG-8.1 Milestone and Engineering 156d 0d 0d 0d 11d 11d 156d 0d 0d 0d 0d 0d 0d 0d 0d 0d 0d 0d 51d 22-May-23 22-Nov-22 22-Nov-22 05-Dec-22 05-Dec-22 A 22-May-23 04-Dec-22 04-Dec-22 22-May-23 22-Nov-22 22-Nov-22 07-Dec-22 25-Jan-23 25-Jan-23 01-Feb-23 18-Feb-23 01-Mar-23 09-Mar-23 03-Apr-23 22-May-23 01-Feb-23 45d 2d 6d 1d 10d 5d 44d 2d 6d 1d 10d 5d 48d 1d 2d 1d 3d 2d 27d 05-Dec-22 A 05-Dec-22 A 01-Jan-23 08-Jan-23 09-Jan-23 21-Jan-23 06-Dec-22 A 06-Dec-22 A 01-Jan-23 08-Jan-23 09-Jan-23 21-Jan-23 08-Dec-22 A 08-Dec-22 A 26-Jan-23 28-Jan-23 28-Jan-23 31-Jan-23 07-Feb-23 25-Jan-23 06-Dec-22 A 07-Jan-23 08-Jan-23 19-Jan-23 25-Jan-23 25-Jan-23 07-Dec-22 A 07-Jan-23 08-Jan-23 19-Jan-23 25-Jan-23 01-Feb-23 08-Dec-22 A 28-Jan-23 28-Jan-23 30-Jan-23 01-Feb-23 09-Mar-23 10d 2d 2d 2d 2d 2d 2d 3d 3d 3d 19-Feb-23 19-Feb-23 20-Feb-23 21-Feb-23 22-Feb-23 23-Feb-23 25-Feb-23 26-Feb-23 27-Feb-23 27-Feb-23 01-Mar-23 20-Feb-23 21-Feb-23 22-Feb-23 23-Feb-23 25-Feb-23 26-Feb-23 28-Feb-23 01-Mar-23 01-Mar-23 22-Nov-22 22-Nov-22 22-Nov-22 22-May-23, DEM-GEG-8.1.1 Contract Milestones Project Start Date, 22-Nov-22 Commencement of Work at Site, 05-Dec-22 Subcontract Completion, 04-Dec-22, DEM-GEG-8.1.3 Mobilization Mobilization 22-May-23, DEM-GEG-8.1.2 Construction Milestones Demolition and Dismantling of Well Pad 103, Demolition and Dismantling of Well Pad 102, Nitrogen Purging at Well-Pads (105,101,102) Completed, Decruding,Flushing of Well-Pad 105, Decruding,Flushing of Well-Pad 101, Decruding,Flushing of Well-Pad 102, Mothballing of RTP Line2, Mothballing of RTP Line1, Mothballing of RTP Line3, Demolition and Dismantling of Well Pad 105, Demolition and Dismantling of Well Pad 101, 01-Feb-23, DEM-GEG-8.2 Decruding,Flushing of trunk lines and Well-Pad Page 1 of 4 25-Jan-23, DEM-GEG-8.2.1 Decruding,Flushing of trunk lines and Well-Pad-105 Nitrogen Purging Equipment/Pump installation Equipment/Pump Leakage Testing Flushing activity with water Products/Waste disposal 25-Jan-23, DEM-GEG-8.2.3 Decruding,Flushing of trunk lines and Well-Pad-101 Nitrogen Purging Equipment/Pump installation Equipment/Pump Leakage Testing Flushing activity with water Products/Waste disposal 01-Feb-23, DEM-GEG-8.2.4 Decruding,Flushing of trunk lines and Well-Pad-102 Nitrogen Purging Equipment/Pump installation Equipment/Pump Leakage Testing Flushing activity with water Products/Waste disposal 09-Mar-23, DEM-GEG-8.5 Removal,Truncation.Mothballing of RTP Lines 01-Mar-23, DEM-GEG-8.5.1 Segment #01 RTP Line1 105 - 101 (600m) Exposing the RTP Line Depressurization of RTP Line Nitrogen Purging of RTP Line Flushing & Decruding of RTP Line Flaring of RTP Line Air Drying of RTP Line Truncation of RTP Line Mothballing of RTP Line Reinstatement of RTP Lines TASK filter: All Activities © Oracle Corporation DEMOLITION SCOPE HZEM WELL PAD 101 105 Activity Name Original Duration Start Classic Schedule Layout_PMS Finish 2023 2024 2025 2026 05-Mar-23 17:25 2027 N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J DEM-GEG-8.5.3 Segment #02 RTP Line2 105 - 101 (100m) Exposing the RTP Line Depressurization of RTP Line Nitrogen Purging of RTP Line Flushing & Decruding of RTP Line Flaring of RTP Line Air Drying of RTP Line Truncation of RTP Line Mothballing of RTP Line Reinstatement of RTP Lines DEM-GEG-8.5.4 Segment #03 RTP Line3 101- 103 (2900m) Exposing the RTP Line Depressurization of RTP Line Nitrogen Purging of RTP Line Flushing & Decruding of RTP Line Flaring of RTP Line Air Drying of RTP Line Truncation of RTP Line Mothballing of RTP Line Reinstatement of RTP Lines DEM-GEG-8.3 Demolition and Dismantling of Well Pad 101 DEM-GEG-8.3.1 Production Line Production Line Dismantling Cable Removal Dismantling Cable Tray Dismantling SS Tubling DEM-GEG-8.3.2 Walls of Instruments Dismantling Walls of Instruments DEM-GEG-8.3.3 WHCP Return Line Dismantling & removal of Well Head Control Panel Return Line DEM-GEG-8.3.4 Lighting Pole Dismantling & removal of Lighting Pole DEM-GEG-8.3.5 Flame Deductor Pools Dismantling & removal of Flame Deductor Pools DEM-GEG-8.3.6 Inter Connecting Piping Dismantling & removal of Inter Connecting Piping DEM-GEG-8.3.7 Test Seperators Dismantling & removal of Test Separator - A Dismantling & removal of Test Separator - B Dismantling & removal of Test Separator - C Demolition of Foundations of Test Separators A,B & C DEM-GEG-8.3.8 Knockout Drum Dismantling & removal of Knockout Drum Demolition of Foundation of Knockout Drum DEM-GEG-8.3.9 Export Pump Skid Dismantling & removal of Export Pump Skid Demolition of Foundation of Export Pump Skid DEM-GEG-8.3.10 Valve Skid Dismantling & removal of Valve Skid Demolition of Foundation of Valve Skid Actual Level of Effort Remaining Work Milestone Actual Work Critical Remaining Work summary 10d 2d 2d 2d 1d 3d 2d 3d 3d 3d 22d 6d 2d 4d 4d 3d 2d 4d 4d 4d 48d 07-Feb-23 07-Feb-23 08-Feb-23 09-Feb-23 11-Feb-23 12-Feb-23 13-Feb-23 14-Feb-23 15-Feb-23 15-Feb-23 13-Feb-23 13-Feb-23 18-Feb-23 20-Feb-23 22-Feb-23 25-Feb-23 27-Feb-23 28-Feb-23 02-Mar-23 06-Mar-23 07-Feb-23 18-Feb-23 08-Feb-23 09-Feb-23 11-Feb-23 11-Feb-23 14-Feb-23 14-Feb-23 16-Feb-23 18-Feb-23 18-Feb-23 09-Mar-23 19-Feb-23 19-Feb-23 23-Feb-23 26-Feb-23 27-Feb-23 28-Feb-23 04-Mar-23 06-Mar-23 09-Mar-23 03-Apr-23 18-Feb-23, DEM-GEG-8.5.3 Segment #02 RTP Line2 105 - 101 (100m) Exposing the RTP Line Depressurization of RTP Line Nitrogen Purging of RTP Line Flushing & Decruding of RTP Line Flaring of RTP Line Air Drying of RTP Line Truncation of RTP Line Mothballing of RTP Line Reinstatement of RTP Lines 09-Mar-23, DEM-GEG-8.5.4 Segment #03 RTP Line3 101- 103 (2900m) Exposing the RTP Line Depressurization of RTP Line Nitrogen Purging of RTP Line Flushing & Decruding of RTP Line Flaring of RTP Line Air Drying of RTP Line Truncation of RTP Line Mothballing of RTP Line Reinstatement of RTP Lines 03-Apr-23, DEM-GEG-8.3 Demolition and Dismantling of Well Pad 101 8d 2d 2d 2d 2d 2d 2d 2d 2d 2d 2d 2d 2d 2d 2d 4d 1d 1d 1d 2d 3d 1d 2d 3d 1d 2d 3d 1d 2d 07-Feb-23 07-Feb-23 09-Feb-23 12-Feb-23 14-Feb-23 16-Feb-23 16-Feb-23 16-Feb-23 16-Feb-23 16-Feb-23 16-Feb-23 16-Feb-23 16-Feb-23 16-Feb-23 16-Feb-23 18-Feb-23 18-Feb-23 18-Feb-23 19-Feb-23 20-Feb-23 22-Feb-23 22-Feb-23 23-Feb-23 26-Feb-23 26-Feb-23 27-Feb-23 01-Mar-23 01-Mar-23 02-Mar-23 15-Feb-23 08-Feb-23 11-Feb-23 13-Feb-23 15-Feb-23 18-Feb-23 18-Feb-23 18-Feb-23 18-Feb-23 18-Feb-23 18-Feb-23 18-Feb-23 18-Feb-23 18-Feb-23 18-Feb-23 21-Feb-23 18-Feb-23 18-Feb-23 19-Feb-23 21-Feb-23 25-Feb-23 22-Feb-23 25-Feb-23 28-Feb-23 26-Feb-23 28-Feb-23 04-Mar-23 01-Mar-23 04-Mar-23 15-Feb-23, DEM-GEG-8.3.1 Production Line Production Line Dismantling Cable Removal Dismantling Cable Tray Dismantling SS Tubling 18-Feb-23, DEM-GEG-8.3.2 Walls of Instruments Dismantling Walls of Instruments 18-Feb-23, DEM-GEG-8.3.3 WHCP Return Line Dismantling & removal of Well Head Control Panel Return Line 18-Feb-23, DEM-GEG-8.3.4 Lighting Pole Dismantling & removal of Lighting Pole 18-Feb-23, DEM-GEG-8.3.5 Flame Deductor Pools Dismantling & removal of Flame Deductor Pools 18-Feb-23, DEM-GEG-8.3.6 Inter Connecting Piping Dismantling & removal of Inter Connecting Piping 21-Feb-23, DEM-GEG-8.3.7 Test Seperators Dismantling & removal of Test Separator - A Dismantling & removal of Test Separator - B Dismantling & removal of Test Separator - C Demolition of Foundations of Test Separators A,B & C 25-Feb-23, DEM-GEG-8.3.8 Knockout Drum Dismantling & removal of Knockout Drum Demolition of Foundation of Knockout Drum 28-Feb-23, DEM-GEG-8.3.9 Export Pump Skid Dismantling & removal of Export Pump Skid Demolition of Foundation of Export Pump Skid 04-Mar-23, DEM-GEG-8.3.10 Valve Skid Dismantling & removal of Valve Skid Demolition of Foundation of Valve Skid Page 2 of 4 TASK filter: All Activities © Oracle Corporation DEMOLITION SCOPE HZEM WELL PAD 101 105 Activity Name Original Duration Start Classic Schedule Layout_PMS Finish 2023 2024 2025 2026 05-Mar-23 17:25 2027 N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J DEM-GEG-8.3.11 Instrument Air Skid Dismantling & removal of Instrument Air Skid Demolition of Foundation of Instrument Air Skid DEM-GEG-8.3.12 Well Head Control Panel (A,B,C) Dismantling & removal of Well Head Control Panel - A Excavation of Foundation of Well Head Control Panel - A Lifting Foundation of Well Head Control Panel - A Dismantling & removal of Well Head Control Panel -B Excavation of Foundation of Well Head Control Panel - B Lifting Foundation of Well Head Control Panel - B Dismantling & removal of Well Head Control Panel - C Excavation of Foundation of Well Head Control Panel - C Lifting Foundation of Well Head Control Panel - C DEM-GEG-8.3.13 RTU Shelter Dismantling & removal of RTU Shelter DEM-GEG-8.3.14 Propane Skid Dismantling & removal of Propane Skid Demolition of Foundation of Propane Skid DEM-GEG-8.3.15 Diesel Generator Skid Dismantling & removal of Diesel Generator Skid (Lifting & Removal) Demolition of Foundation of Diesel Generator Skid DEM-GEG-8.3.16 Flare Stack & Flare Stack Line Dismantling & removal of Flare Stack Manual Excavation Lifting Foundation Flare Stack Line Removal Dismantling & removal of Structure for Flare Stack DEM-GEG-8.3.17 Surge Drum Surge Drum DEM-GEG-8.3.18 Fencing & Fence Gate Dismantling & Removal of Fence & Fence Gate DEM-GEG-8.3.19 Site Office Dismantling & Removal of Site Office DEM-GEG-8.4 Demolition and Dismantling of Well Pad 105 DEM-GEG-8.4.1 Production Line Production Line Dismantling Cable Removal Dismantling Cable Trays Dismantling SS Tubling DEM-GEG-8.4.2 Walls of Instruments Dismantling Walls of Instruments DEM-GEG-8.4.3 WHCP Return Line Dismantling & removal of Well Head Control Panel Return Line DEM-GEG-8.4.4 Lighting Pole Dismantling & removal of Lighting Pole DEM-GEG-8.4.5 Flame Deductor Pools Dismantling & removal of Flame Deductor Pools DEM-GEG-8.4.6 Inter Connecting Piping Dismantling & removal of Inter Connecting Piping DEM-GEG-8.4.7 Test Seperators Actual Level of Effort Remaining Work Milestone Actual Work Critical Remaining Work summary 3d 1d 2d 9d 1d 1d 1d 1d 1d 1d 1d 1d 1d 1d 1d 4d 2d 2d 2d 1d 1d 7d 1d 2d 1d 2d 2d 2d 2d 2d 2d 1d 1d 51d 05-Mar-23 05-Mar-23 06-Mar-23 07-Mar-23 07-Mar-23 08-Mar-23 09-Mar-23 11-Mar-23 12-Mar-23 13-Mar-23 14-Mar-23 15-Mar-23 16-Mar-23 16-Mar-23 16-Mar-23 18-Mar-23 18-Mar-23 20-Mar-23 22-Mar-23 22-Mar-23 23-Mar-23 23-Mar-23 23-Mar-23 25-Mar-23 27-Mar-23 28-Mar-23 29-Mar-23 01-Apr-23 01-Apr-23 01-Apr-23 01-Apr-23 03-Apr-23 03-Apr-23 25-Mar-23 07-Mar-23 05-Mar-23 07-Mar-23 16-Mar-23 07-Mar-23 08-Mar-23 09-Mar-23 11-Mar-23 12-Mar-23 13-Mar-23 14-Mar-23 15-Mar-23 16-Mar-23 16-Mar-23 16-Mar-23 21-Mar-23 19-Mar-23 21-Mar-23 23-Mar-23 22-Mar-23 23-Mar-23 30-Mar-23 23-Mar-23 26-Mar-23 27-Mar-23 29-Mar-23 30-Mar-23 02-Apr-23 02-Apr-23 02-Apr-23 02-Apr-23 03-Apr-23 03-Apr-23 22-May-23 4d 3d 3d 3d 4d 3d 3d 3d 3d 4d 4d 4d 4d 4d 4d 7d 25-Mar-23 25-Mar-23 25-Mar-23 25-Mar-23 25-Mar-23 26-Mar-23 26-Mar-23 26-Mar-23 26-Mar-23 26-Mar-23 26-Mar-23 26-Mar-23 26-Mar-23 27-Mar-23 27-Mar-23 01-Apr-23 28-Mar-23 27-Mar-23 27-Mar-23 27-Mar-23 28-Mar-23 28-Mar-23 28-Mar-23 28-Mar-23 28-Mar-23 29-Mar-23 29-Mar-23 29-Mar-23 29-Mar-23 30-Mar-23 30-Mar-23 08-Apr-23 Page 3 of 4 07-Mar-23, DEM-GEG-8.3.11 Instrument Air Skid Dismantling & removal of Instrument Air Skid Demolition of Foundation of Instrument Air Skid 16-Mar-23, DEM-GEG-8.3.12 Well Head Control Panel (A,B,C) Dismantling & removal of Well Head Control Panel - A Excavation of Foundation of Well Head Control Panel - A Lifting Foundation of Well Head Control Panel - A Dismantling & removal of Well Head Control Panel -B Excavation of Foundation of Well Head Control Panel - B Lifting Foundation of Well Head Control Panel - B Dismantling & removal of Well Head Control Panel - C Excavation of Foundation of Well Head Control Panel - C Lifting Foundation of Well Head Control Panel - C 16-Mar-23, DEM-GEG-8.3.13 RTU Shelter Dismantling & removal of RTU Shelter 21-Mar-23, DEM-GEG-8.3.14 Propane Skid Dismantling & removal of Propane Skid Demolition of Foundation of Propane Skid 23-Mar-23, DEM-GEG-8.3.15 Diesel Generator Skid Dismantling & removal of Diesel Generator Skid (Lifting & Removal) Demolition of Foundation of Diesel Generator Skid 30-Mar-23, DEM-GEG-8.3.16 Flare Stack & Flare Stack Line Dismantling & removal of Flare Stack Manual Excavation Lifting Foundation Flare Stack Line Removal Dismantling & removal of Structure for Flare Stack 02-Apr-23, DEM-GEG-8.3.17 Surge Drum Surge Drum 02-Apr-23, DEM-GEG-8.3.18 Fencing & Fence Gate Dismantling & Removal of Fence & Fence Gate 03-Apr-23, DEM-GEG-8.3.19 Site Office Dismantling & Removal of Site Office 22-May-23, DEM-GEG-8.4 Demolition and Dismantling of Well Pad 105 28-Mar-23, DEM-GEG-8.4.1 Production Line Production Line Dismantling Cable Removal Dismantling Cable Trays Dismantling SS Tubling 28-Mar-23, DEM-GEG-8.4.2 Walls of Instruments Dismantling Walls of Instruments 28-Mar-23, DEM-GEG-8.4.3 WHCP Return Line Dismantling & removal of Well Head Control Panel Return Line 29-Mar-23, DEM-GEG-8.4.4 Lighting Pole Dismantling & removal of Lighting Pole 29-Mar-23, DEM-GEG-8.4.5 Flame Deductor Pools Dismantling & removal of Flame Deductor Pools 30-Mar-23, DEM-GEG-8.4.6 Inter Connecting Piping Dismantling & removal of Inter Connecting Piping 08-Apr-23, DEM-GEG-8.4.7 Test Seperators TASK filter: All Activities © Oracle Corporation DEMOLITION SCOPE HZEM WELL PAD 101 105 Activity Name Original Duration Start Classic Schedule Layout_PMS Finish 2023 2024 2025 2026 05-Mar-23 17:25 2027 N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J Dismantling & removal of Test Separator - A Dismantling & removal of Test Separator - B Dismantling & removal of Test Separator - C Dismantling & removal of Test Separator - D Demolition of Foundations of Test Separators A,B,C & D DEM-GEG-8.4.8 Knockout Drum Dismantling & removal of Knockout Drum Demolition of Foundation of Knockout Drum DEM-GEG-8.4.9 Export Pump Skid Dismantling & removal of Export Pump Skid Demolition of Foundation of Export Pump Skid DEM-GEG-8.4.10 Valve Skid Dismantling & removal of Valve Skid Demolition of Foundation of Valve Skid DEM-GEG-8.4.11 Instrument Air Skid Dismantling & removal of Instrument Air Skid Demolition of Foundation of Instrument Air Skid DEM-GEG-8.4.12 Well Head Control Panel (A,B) Dismantling & removal of Well Head Control Panel - A Excavation of Foundation of Well Head Control Panel - A Lifting Foundation of Well Head Control Panel - A Dismantling & removal of Well Head Control Panel - B Excavation of Foundation of Well Head Control Panel - B Lifting Foundation of Well Head Control Panel - B DEM-GEG-8.4.13 RTU Shelter Dismantling & removal of RTU Shelter DEM-GEG-8.4.14 Propane Skid Dismantling & removal of Propane Skid Demolition of Foundation of Propane Skid DEM-GEG-8.4.15 Diesel Generator Skid Dismantling & removal of Diesel Generator Skid (Lifting & Removal) Demolition of Foundation of Diesel Generator Skid DEM-GEG-8.4.16 Flare Stack & Flare Stack Line Dismantling & removal of Flare Stack Flare Stack Line Removal Manual Excavation Lifting Foundation Dismantling & removal of Structure for Flare Stack DEM-GEG-8.4.17 Surge Drum Surge Drum DEM-GEG-8.4.18 Fencing & Fence Gate Dismantling & Removal of Fence & Fence Gate DEM-GEG-8.4.19 Site Office Dismantling & Removal of Site Office Actual Level of Effort Remaining Work Milestone Actual Work Critical Remaining Work summary 1d 1d 1d 1d 3d 3d 2d 1d 3d 2d 1d 4d 3d 1d 3d 2d 1d 6d 1d 1d 1d 1d 1d 1d 2d 2d 3d 2d 3d 4d 3d 1d 8d 3d 2d 1d 1d 1d 1d 1d 1d 1d 1d 1d 01-Apr-23 02-Apr-23 03-Apr-23 04-Apr-23 05-Apr-23 09-Apr-23 09-Apr-23 11-Apr-23 12-Apr-23 12-Apr-23 15-Apr-23 16-Apr-23 16-Apr-23 19-Apr-23 20-Apr-23 20-Apr-23 23-Apr-23 24-Apr-23 24-Apr-23 25-Apr-23 26-Apr-23 27-Apr-23 29-Apr-23 30-Apr-23 01-May-23 01-May-23 03-May-23 03-May-23 03-May-23 07-May-23 07-May-23 10-May-23 11-May-23 11-May-23 15-May-23 17-May-23 18-May-23 20-May-23 21-May-23 21-May-23 21-May-23 21-May-23 22-May-23 22-May-23 01-Apr-23 02-Apr-23 03-Apr-23 04-Apr-23 08-Apr-23 11-Apr-23 10-Apr-23 11-Apr-23 15-Apr-23 13-Apr-23 15-Apr-23 19-Apr-23 18-Apr-23 19-Apr-23 23-Apr-23 22-Apr-23 23-Apr-23 30-Apr-23 24-Apr-23 25-Apr-23 26-Apr-23 27-Apr-23 29-Apr-23 30-Apr-23 02-May-23 02-May-23 06-May-23 04-May-23 06-May-23 10-May-23 09-May-23 10-May-23 20-May-23 14-May-23 16-May-23 17-May-23 18-May-23 20-May-23 21-May-23 21-May-23 21-May-23 21-May-23 22-May-23 22-May-23 Page 4 of 4 Dismantling & removal of Test Separator - A Dismantling & removal of Test Separator - B Dismantling & removal of Test Separator - C Dismantling & removal of Test Separator - D Demolition of Foundations of Test Separators A,B,C & D 11-Apr-23, DEM-GEG-8.4.8 Knockout Drum Dismantling & removal of Knockout Drum Demolition of Foundation of Knockout Drum 15-Apr-23, DEM-GEG-8.4.9 Export Pump Skid Dismantling & removal of Export Pump Skid Demolition of Foundation of Export Pump Skid 19-Apr-23, DEM-GEG-8.4.10 Valve Skid Dismantling & removal of Valve Skid Demolition of Foundation of Valve Skid 23-Apr-23, DEM-GEG-8.4.11 Instrument Air Skid Dismantling & removal of Instrument Air Skid Demolition of Foundation of Instrument Air Skid 30-Apr-23, DEM-GEG-8.4.12 Well Head Control Panel (A,B) Dismantling & removal of Well Head Control Panel - A Excavation of Foundation of Well Head Control Panel - A Lifting Foundation of Well Head Control Panel - A Dismantling & removal of Well Head Control Panel - B Excavation of Foundation of Well Head Control Panel - B Lifting Foundation of Well Head Control Panel - B 02-May-23, DEM-GEG-8.4.13 RTU Shelter Dismantling & removal of RTU Shelter 06-May-23, DEM-GEG-8.4.14 Propane Skid Dismantling & removal of Propane Skid Demolition of Foundation of Propane Skid 10-May-23, DEM-GEG-8.4.15 Diesel Generator Skid Dismantling & removal of Diesel Generator Skid (Lifting & Removal) Demolition of Foundation of Diesel Generator Skid 20-May-23, DEM-GEG-8.4.16 Flare Stack & Flare Stack Line Dismantling & removal of Flare Stack Flare Stack Line Removal Manual Excavation Lifting Foundation Dismantling & removal of Structure for Flare Stack 21-May-23, DEM-GEG-8.4.17 Surge Drum Surge Drum 21-May-23, DEM-GEG-8.4.18 Fencing & Fence Gate Dismantling & Removal of Fence & Fence Gate 22-May-23, DEM-GEG-8.4.19 Site Office Dismantling & Removal of Site Office TASK filter: All Activities © Oracle Corporation