BASEMENT CONSTRUCTION Dincel Construction System Pty Ltd Level 3, 7K Parkes Street PARRAMATTA NSW 2150 Phone: (612) 9689 1877 Fax: (612) 9689 2028 Email: construction@dincel.com.au COPYRIGHT © Dincel Construction System Pty Ltd All rights reserved. No part of the information contained in this document may be reproduced or copied in any form or by any means without written permission from Dincel Construction System Pty Ltd. DISCLAIMER The information contained in this document is intended for the use of suitably qualified and experienced architects and engineers and other building professionals. This information is not intended to replace design calculations or analysis normally associated with the design and specification of buildings and their components. Dincel Construction System Pty Ltd accepts no liability for any circumstances arising from the failure of a specifier or user of any part of Dincel Construction System to obtain appropriate professional advice about its use and installation or from failure to adhere to the requirements of appropriate Standards and Codes of Practice, and relevant Building Codes. ©Copyright Page 1 of 16 SHORING – BASEMENT CONSTRUCTION The basement excavation for buildings is required for carparking, amenities and services. The depth of the excavation, depending on the ground slopes can be single or multiple carparking/storage levels. The difficulty, hence cost of basement shoring construction depends on: y The type of material being excavated. For example, the majority of rock excavations, depending on the rock quality and fault planes may not need any shoring at all, however on the other hand sandy materials or even clayey materials require shoring systems. y The ground water conditions – it is conventionally very costly to build below the permanent water table. The majority of basement constructions in clayey types of foundation material can be excavated without shoring having adequate batters to soil if there is adequate distance from the boundaries to allow the battering. Battering to avoid excavation shoring systems may cause the following problems. h Massive quantities of earth moving for the materials along the batters. h Batters may need to be stepped and stabilised to satisfy work cover requirements. h The extent of the batters may restrict the site usage and accessibility. h The removed material needs to be back-filled behind the basement walls, usually with imported granular, free draining material which needs to be placed carefully to avoid future soil consolidation problems. All of the above procedures are timely and certainly not cost effective. There are many cases observed where excavations have been shored rather than having soil battering to avoid the above issues. The conventional method of shoring is to have discreet piles with shotcreted walls in between or over the piles for clay-shale types of ground materials. However, the irony is the entire site containing clayey material is normally shored by piles plus shotcrete walls for the full extent of the basement height for the sake of loose clayey material immediately below the natural ground level. The clay required to be shored could only be a couple of metres high over the stable shale or rock which can be excavated safely with minimal or no batter at all. It is therefore obvious to the professionals in ground engineering science that only the loose and unstable materials need to be stabilised by sheet piling or similar terminating over stable soils. The most unpredictable ground material for shoring purposes is shale type ground materials. The shale can have a fault line inclining towards the excavation. This type of material reported by geotechnical soils investigation and analysis must be retained by shoring to prevent the mass movement of shale material over the fault line irrespective of how hard the shale is. The construction sites containing sand or similar materials needs to be shored for the full extent of the bulk excavation. ©Copyright Page 2 of 16 The conventional shoring systems can be summarised as follows: 1. DISCREET PILES AND SHOTCRETE WALLS IN BETWEEN THE PILES This shoring system will be applicable to non-granular, virgin types of cohesive soil conditions. This type of shoring normally extends the full height of basement excavation irrespective of the depth of the top soil material required to be shored. The problems are usually associated with cracking and steel rusting of shotcrete walls, inadequate waterproofing and unsightly walls. 2. CONTIGUOUS PILING SYSTEMS This shoring system is normally associated with granular foundation materials or loose fill materials when there are no water table issues. The face of piles receives shotcreting to close the gaps between piles and also to provide a presentable appearance to the basement walls. Normal construction tolerance is such that frequent gaps of 75mm or more and misalignment in the exposed faces can occur. This is a costly and slow operation and certainly not the best way of waterproofing the walls. There can be risk of sand or backfilled material leaking between the gaps. Cracking and corrosion of shotcreting is again a common problem. 3. SECANT-PILE WALL SYSTEM This shoring system is normally specified if there is a ground water problem. The soft piles are placed first; the structural and reinforced piles are bored and placed within the soft piles to provide water tight walls. In most cases, the tightness of the joint between soft and hard piles cannot be effective to prevent the water egress. The use of bentonite in soft piles is a better way of making sure that the joints are watertight. This system requires structural render to bring the piles in reasonable alignment before the waterproof membrane system is placed onto it. The membrane system further receives another masonry or concrete wall to protect the membrane. The disadvantage of this system is that it is extremely costly and a slow system to build. It is normally difficult to obtain a guarantee from the piling contractor for the straightness of long piles if used for water cut-off and assist dewatering purposes. There could also be water related problems depending on how well the membrane system is applied. 4. SHEET-PILING AND SHOTCRETE WALL Steel sheet pile wall systems can be suitable for many situations but have tended to be rejected due to a number of problems including: y Noise of installation. y Possible vibration damage to nearby properties during driving. y Availability and cost of suitable sheet pile wall sections. y Risk of leakage through the clutches and holes in the sheets below the water table. y Disturbance to surrounding area during extraction of sheets. ©Copyright Page 3 of 16 This shoring system can be considered as an alternative to Item Nos: 2 and 3 above. The sheet piling’s inner face normally is reinforced with bars and/or mesh prior to concreting. This way concrete cladding to the sheet piling has various concrete depths between each rib of the sheet piling. The concrete cracks at the position where the concrete thickness varies between the ribs. Since the water tightness of the joints of the sheet piling cannot be 100% prevented, water or moisture will attack the reinforcing steel at the cracked concrete. Depending on the type of soil, water and minerals, contaminants in the environment, the life of the shotcrete concrete can even be less than the builder’s liability period. The rectification of this type of problem will prevent the already occupied building use and hence costly. On the other hand steel piling itself must have adequate extra steel thickness for corrosion problems hence sheet piling itself becomes more expensive. 5. DIAPHRAGM WALLS These are usually excavated in panels by a specialist contractor with a grab and the excavation supported by drilling mud until reinforcement is placed and the panel concreted. Panels are generally 3 – 6m long and 0.5 to 0.8m wide. Work is carried out on an alternate panel system coming back later for the infill panels. Stop ends are provided in the first set of panels to form the ends, and various other patented devices have been developed to reduce the risk of leakage through the joints between panels. It is generally normal to construct guide walls to ensure location control. The finished walls are usually smooth and of a high standard suitable for a basement. Construction of diaphragm walls is expensive and requires a specialist experienced contractor who has the appropriate equipment and expertise. ©Copyright Page 4 of 16 THE BASEMENT CONSTRUCTION WITH As it can be seen from the above conditions there is currently no available basement shoring system that is: h Considerably cheaper and faster to build. h Waterproof, maintenance free, does not rust, decay or corrode or crack. h Ready finish. h Elimination of slab edge formings and slab edge beams, more economical floor slab solutions. h Long term corrosion free reliable structural connections between wall and floor slabs. h Provisions for ready safety handrails. can be used: (i) (ii) In association with sheet piling with or without the presence of ground water. will offer the following advantages. h The use of cold formed sheet piles, i.e. cheaper sheet piles. h Sheet piling without corrosion allowance, i.e. cost effective sheets. h Cheaper sheet piling can be sacrificed, hence eliminates the costs and risks for sheet extractions. h Much quicker sheet piling erection procedure since the water tightness of the sheet joints are not prime importance, as long as dewatering is manageable. In association with site excavations consisting battered ground conditions. h Elimination of sub-soil drainage and imported backfilling behind the basement . perimeter h Elimination of conventional footings where allowable ground bearing pressures are suitable. Note: The latest studies indicate that aggregate lines behind walls contribute to bacteria problems. The basement conditions and shoring methodologies may be generalised as shown by Figures A and B below. FIGURE A represents sand, sandy soils, full height of basement shored by anchored sheet piles and permanent water table above the lowest level. FIGURE B covers the most common cases of basement excavation. The excavations are either battered or sheet piled and the lowest basement level above the permanent water table. The sheet piles in association with are treated as temporary shoring purposes as they can be either removed or left in place to rust away. The supply of sheet piling is determined by its thickness and how well the joints of the sheet piling will retain the water. The sheet piling suppliers in association with do not need to consider the additional corrosion allowances for sheet thicknesses. Their sheet thicknesses can be determined by the drivability issue rather than corrosion. However, drivability issues can be easily overcome by pre-drilling the ground where required. The joints of the sheet piling can be allowed to leak as long as the leakage is within the de-watering limits. Today’s sheet piling technology is well advanced and reasonably stiff clays, even shale can be shored with the assistance of vibrationless hydraulic rams pushing into the soil, where required ground is pre-drilled to assist the drivability. ©Copyright Page 5 of 16 eliminates the need for sheet piling to be treated as permanent structural element hence reducing its relative costings and risks. As illustrated on Figure A provides a permanent water-proofed wall to water charged ground, is reliable and liability free, and the most cost efficient rate. ©Copyright Page 6 of 16 ©Copyright Page 7 of 16 ©Copyright Page 8 of 16 ©Copyright Page 9 of 16 ©Copyright Page 10 of 16 ©Copyright Page 11 of 16 ©Copyright Page 12 of 16 ©Copyright Page 13 of 16 ©Copyright Page 14 of 16 ©Copyright Page 15 of 16 ©Copyright Page 16 of 16