EPC for North Field Production Sustainability Offshore & Pipelines Project COMPANY Contract No.: LTC/C/NFP/4382/19 CONTRACTOR Project No.: 033727 SCOPE OF WORK FOR PRE-FABRICATION OF : TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) Document Title COMPANY Document No. : EPCOL-SPM-PI-SOW-00001 Saipem Document No. : 033727-E-D-12-SPM-YP-W-10001 Discipline : FABRICATION Document Type : SCOPE OF WORK Document Class : 1 B 19-JUL-2021 Issued f or Review A 30-JUN-2021 Issued f or Review REV. DATE DESCRIPTION OF REVISION Muhasin Thaikandy Muhasin Thaikandy Alessandro Mannai Alessandro Mannai PREPARED BY VERIFIED BY Andrea Giovannini Andrea Giovannini APPROVED BY Saipem S.p.A. EPCOL-SPM-PI-SOW-00001_Rev.B 1 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) REVISION HISTORY Revision Date of Revision Revision Description A1 15-JUN-2021 Issued f or IDC A 30-JUN-2021 Issued f or Review B 19-JUL-2021 Section 7.13 updated HOLDS LIST Hold No Hold Description EPCOL-SPM-PI-SOW-00001_Rev.B 2 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) TABLE OF CONTENTS 1. INTRODUCTION................................................................................................ 5 1.1. PROJECT OBJECTIVE........................................................................... 5 1.2. PROJECT SCOPE.................................................................................. 5 2. OBJECTIVE OF THE DOCUMENT .................................................................... 6 3. DEFINITIONS, ABBREVIATIONS, ACRONYMS................................................ 7 4. 3.1. DEFINITIONS......................................................................................... 7 3.2. ABBREVIATIONS ................................................................................... 7 REFERENCE RULES, CODES AND STANDARDS ........................................... 8 4.1. INTERNATIONAL CODES AND STANDARDS ........................................ 8 4.2. COMPANY STANDARDS ....................................................................... 9 4.3. CONTRACTOR PROJECT DOCUMENTS............................................... 9 5. SCOPE OF SERVICE ...................................................................................... 10 6. OVERVIEW ..................................................................................................... 11 7. DETAILED SCOPE OF WORK ........................................................................ 13 7.1. PROJECT MANAGEMENT ................................................................... 13 7.2. PROJECT CONTROL AND ADMINISTRATION..................................... 13 7.3. MOBILIZATION AND DEMOBILIZATION............................................... 15 7.4. SERVICES AND FACILITIES TO COMPANY & CONTRACTOR’S PERSONNEL ....................................................................................... 15 7.5. YARD FACILITIES ................................................................................ 15 7.6. YARD ENGINEERING .......................................................................... 16 7.7. SUBCONTRACTOR SUPPLIED MATERIAL.......................................... 16 7.8. CONTRACTOR SUPPLIED MATERIAL (FIM)........................................ 17 7.9. ACCEPTANCE OF FIM FROM CONTRACTOR..................................... 17 7.10. MATERIAL MANAGEMENT .................................................................. 18 7.10.1. MATERIAL MANAGEMENT PROCEDURES ........................................................19 7.10.2. MATERIAL TRACEABILITY AND CONTROL PLAN .............................................20 7.10.3. SURPLUS AND SCRAP MATERIAL ......................................................................21 7.11. SUBCONTRACTS ................................................................................ 22 7.12. PROJECT LANGUAGE......................................................................... 22 7.13. PRE-FABRICATION ............................................................................. 22 7.14. WELDING AND NDT REQUIREMENTS ................................................ 24 7.15. DUMMY PIG GAUGING........................................................................ 25 EPCOL-SPM-PI-SOW-00001_Rev.B 3 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 7.16. COATING (OPTION)............................................................................... 25 7.17. STORAGE , HANDLING AND TRANSPORTATION ............................... 26 7.18. MINIMUM DOCUMENTATION TO BE PROVIDED ................................ 26 7.18.1. WITHIN 2 WEEKS ONWARDS FROM CONTRACT AWARD ..............................26 7.18.2. UPON COMPLETION OF THE SCOPE .................................................................27 8. QUALITY ASSURANCE/QUALITY CONTROL ................................................ 28 9. HEALTH, SAFETY AND ENVIRONMENT........................................................ 28 10. RESPONSIBILITY MATRIX ............................................................................. 29 11. ANNEXURES .................................................................................................. 32 EPCOL-SPM-PI-SOW-00001_Rev.B 4 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 1. INTRODUCTION The reservoir pressure in Qatar’s North Field has been declining as COMPANY and other operators have been drawing gas continuously since early 1990s. The overall North Field Production Sustainability (NFPS) Project objective is to sustain the Qatargas (QG) North Field Production Plateau via an integrated investment in surface facilities expansion (Drilling, Pipeline Looping, and Compression). Compression facilities additions are expected further in the future and are not part of this project scope. The Engineering, Procurement, Construction for the North Field Sustainability (NFPS) Offshore and Pipelines Project (EPCOL) covers integrated investment for drilling and looping elements of the NFPS portfolio. The project encompasses surface facility expansion to the multiple existing ventures (i.e. RL1, RGE, QG1, QG2, etc.) within Qatargas, with a wide footprint i.e. offshore fixed facilities, subsea cables, subsea pipelines, onshore pipelines and tie-in to the existing slug catchers located in Ras Laffan Industrial City (RLIC). 1.1. PROJECT OBJECTIVE The objective of the EPCOL project includes: • • • • • 1.2. Achieve standards of global excellence in Safety, Health, Environment, Security and Quality performance. Sustain the Qatargas North Field Production Plateau via integrated investment in surface facilities expansion (Drilling/Production Platforms, Riser Platforms, Pipeline Looping, Subsea Composition Cables, and associated Brownfield modifications). Facility development shall be safe, high quality, reliable, maintainable, accessible, operable, and efficient throughout their required life. Achieve the scheduled RSFU for the FACILITIES in their entirety. Complete integration of the FACILITIES to the existing Qatargas assets. PROJECT SCOPE The project scope of work includes Engineering, Procurement, Fabrication, Construction, Installation, Hook-up and System Completion for the following facilities. Additionally, provide startup assistance for the facilities if requested in accordance to project requirement. • • • • • • • Four (4) Wellhead Platform (WHP) Topsides (Jackets by others); Six (6) Riser Platforms (RP), including Topsides and Jackets. Six (6) Bridges (BR) connection RPs to existing WHPs. Six (6) Corrosion Resistant Alloy (CRA)-Clad Carbon Steel (CS) Intra-field Pipelines. One (1) pipeline Decommissioning. Four (4) Subsea Composite (Power and Fiber Optic (FO)) Cables. Significant Offshore brownfield modifications and upgrade at existing Offshore facilities. EPCOL-SPM-PI-SOW-00001_Rev.B 5 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) • • • • • Equipment upgrade at North Field Bravo (NFB) complex to accommodate revised flow conditions. 1x ~98km, 32” CS dry, sour gas export pipeline, PL1L, beach valve and pig receiving facilities, and tie-in to the existing QGS slug catcher-1 located in RLIC and associated onshore brownfield modification. 1x ~103km, 38” CS wet, sour gas export pipeline, PL610L, beach valve and pig receiving facilities, and tie-in to the existing QGS slug catcher-3 located in RLIC and associated onshore brownfield modification. 1x ~81km, 32” CS dry, sour gas export pipeline, PL1N, beach valve and pig receiving facilities, and tie-in to the existing QGN slug catcher-1 located in RLIC and associated onshore brownfield modification. Option scope for PL811 diversion includes two (2) Riser Platforms (RP), two (2) intrafield pipelines, and associated brownfield modifications. Figure 1: Schematic for the North Field Sustainability Offshore and Pipelines Project (EPCOL) 2. OBJECTIVE OF THE DOCUMENT This document defines the Scope of Work for pre-fabrication, inspection and NDT of CRA cladded spools of topside greenfield facilities of NFPS project. EPCOL-SPM-PI-SOW-00001_Rev.B 6 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 3. DEFINITIONS, ABBREVIATIONS, ACRONYMS 3.1. DEFINITIONS Abbreviation Definition COMPANY Qatargas Operating Company Limited CONTRACTOR Saipem S.p.A. DELIVERABLES FACILITIES MILESTONE SUBCONTRACTOR SUBCONTRACT All products (drawings, equipment, services) which must be submitted by CONTRACTOR to COMPANY at times specified in the contract. All machinery, apparatus, materials, articles, components, systems and items of all kinds to be designed, engineered, procured, manufactured, constructed, supplied, fabricated, tested and permanently installed by CONTRACTOR at SITE in connection with the NFPS – EPCO & EPCL Projects as further described in Exhibit 6. A reference event splitting a PROJECT activity for progress measurement purpose Any organization selected and awarded by CONTRACTOR to supply a certain Project materials or equipment or whom a part of the WORK has been Subcontracted. Contract signed by SUBCONTRACTOR and CONTRACTOR for the performance of a certain portion of the WORK within the Project. PROJECT NFPS - EPCOL WORK PACKAGE The lowest manageable and convenient level in each WBS subdivision 3.2. ABBREVIATIONS Code Definition API American Petroleum Institute ASME American Society of Mechanical Engineers AWS American Welding Society CWC Concrete Weight Coating DNV Det Norske Veritas FIM Free Issued Material FJC Field Joint coating HSE Health, Safety and Environment EPCOL-SPM-PI-SOW-00001_Rev.B 7 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) MDR Master Document Register MRR Material Receiving Report MTO Material Take Off NDT Non-Destructive Testing PQR Procedure Qualification Record QA/QC Quality Assurance/Quality Control RT Radiographic Testing SOW Scope of Work UT Ultrasonic Test WPQT Welding procedure Qualification Test WPS Welding Procedure Specification WT Wall Thickness 4. REFERENCE RULES, CODES AND STANDARDS 4.1. INTERNATIONAL CODES AND STANDARDS Ref Document Number Title /1/ ASME B31.8 Gas Transmission and Distribution Piping Systems /2/ ASME B31.3 Process Piping /3/ DNV-ST-F101 DNV Submarine Pipeline Systems Standard /4/ API 1104 Welding of Pipelines and Related Facilities /5/ ASME Sect. IX Qualification Standard for Welding /6/ ISO 9001:2015 Quality Management System - Requirements ISO/TS 29001:2010 Petroleum, petrochemical and natural gas industries Sector-specific quality management systems Requirements for product and service supply organizations /7/ EPCOL-SPM-PI-SOW-00001_Rev.B 8 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 4.2. COMPANY STANDARDS Ref Document Number Title Specifications /8/ 200-20-CE-SPC-0001 CRA Weld Overlay for Piping Materials Specification /9/ 200-20-PI-SPC-0011 Piping general welding requirement & inspection /10/ 200-20-PI-SPC-0012 Piping Specification for Fabrication and Erection /11/ Exhibit 5, Clause 8 Project Instructions – Quality Assurance & Control /12/ 200-20-QM-SPC-0002 Quality Assurance Requirements for Suppliers /13/ 200-20-QM-SPC-0003 Quality Control Requirements for Suppliers /14/ 200-20-MO-SPC-0005 Specification for Fabrication and Load out /15/ 200-20-MO-SPC-0009 Specification for Stockpiling and Handling Materials /16/ 200-20-PE-SPC-0022 Specification for Material Traceability and Documentation Requirements /17/ 200-20-PI-SPC-0009 Material & Corrosion Requirements for Sour Service /18/ 200-20-PI-SPC-0017 Specification for Fittings /19/ 200-20-PI-SPC-0023 Specification for Pipes /20/ 200-20-PI-SPC-0027 Specification for Positive Material Identification /21/ Exhibit 5 Project Instructions /22/ Exhibit 6 Project Scope of Work /23/ Exhibit 8 Health, Safety, Environment and Security 4.3. CONTRACTOR PROJECT DOCUMENTS Ref Document Number Title /24/ 033727-A-Z-SPM-EM-P00002 Document Numbering Procedure /25/ 033727-Z-Z-00-SPMPC-P-10003 Document Control Procedure /26/ 033727-A-Z-SPM-EM-P00005 Management Of Technical Change /27/ 033727-Z-Z-00-SPMQA-P-10004 Lessons Learned Management Procedure /28/ 033727-Z-Z-00-SPMHS-P-10006 Emergency Preparedness And Response Plan EPCOL-SPM-PI-SOW-00001_Rev.B 9 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 5. /29/ 033727-Z-Z-00-SPMHS-P-10009 Environmental Management Plan /30/ 033727-Z-Z-00-SPMHS-P-10001 Project HSES Plan /31/ 033727-Z-Z-00-SPMHS-P-10002 Incident Investigation & Reporting Procedure /32/ 033727-Z-Z-00-SPMQA-P-10003 Non-Conformance and Corrective Action Management Procedure /33/ 033727-A-D-12-SPMMA-S-00055 Piping General Welding Requirement & Inspection /34/ 033727-A-D-12-SPMMA-S-00013 Protective Coating Specification for Offshore /35/ 033727-Z-Z-00-SPMHS-P-10024 Project Heat Stress Management Procedure /36/ 033727-Z-Z-00-SPMQA-P-10007 Project Quality Plan /37/ 033727-Z-Z-00-SPMQA-P-10002 Quality Audit Procedure /38/ 033727-A-W-60-SPMEM-P-00015 Redlining Procedure /39/ 033727-Z-Z-00-SPM-EY- Site Management and Control of Construction Aids and P-10001 Temporary Fabrications /40/ 033727-Z-Z-00-SPMHS-P-10003 /41/ 033727-A-D-SPM-EM-PTechnical Query Procedure 00009 Subcontractors HSE Management and Evaluation Plan SCOPE OF SERVICE The scope of this subcontract is prefabrication, inspection and NDT of CRA cladded spools. CONTRACTOR will issue bevelled cut to length CRA cladded pipes and fittings as FIM. All the works shall be performed in accordance with codes, standards, specifications cited in references as well as per this SOW. Included here are the minimum requirements to be followed to ensure that the work tasked to the Subcontractor for the fabrication of each item is completed to a satisfactory standard and will meet the requirements of the designated utility. Detailed scope will be in following sections. EPCOL-SPM-PI-SOW-00001_Rev.B 10 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 6. OVERVIEW As a minimum, the SUBCONTRACOR’s SOW will include, but not limited to: • • • • • • • • • • • • • • • • • • • • • • • • Yard mobilization and preparatory works Supervision, Inspection and Management of all construction works in Production Offloading of CONTRACTOR’s FIM at Delivery Location (SUBCONTRACTOR’s Fabrication Yard). Assurance of material traceability. Provision of all necessary management, engineering, supervision and labor including preparation of MRR in accordance with COMPANY requirements. Definition and implementation of a Quality Management System in accordance with project requirements. Provision of fabrication plan and all required tools and equipment to meet CONTRACTOR’s milestone dates. Implementation of Lessons learned retrieval and capture process and participation in the Lesson Learned Workshop. Supply of materials and consumables required to complete the work. Preparation and qualification of WPQR / WPS required for this SOW. Receive and store all CONTRACTOR’s FIM, ensuring that no damage or degradation of materials shall occur at any time within SUBCONTRACTOR’s premises. CONTRACTOR shall bear no responsibility on FIM damage after MRR is issued and material is accepted by SUBCONTRACTOR. Qualification of Welders and Welding Procedures. Provision of NDT tools, equipment rental and personnel, include its qualification and/or validation as per NDT project requirement. Preparation of fabrication engineering deliverables for CONTRACTOR review and approval. Piping prefabrication involving but not limited to handling, cutting, bevelling, edge preparation, fit-up, intermediate NDT as per requirement and final weld completion. Piping weld joints connection may comprise of pipe to pipe, pipe to fitting and fitting to fitting connection. Standard and special supports which are directly weld to the pipe (e.g. wear pads, trunnions, corrosion bar, etc.) shall be installed at shop prior to painting. It shall be under SUBCONTRACTOR’s responsibility to check any other applicable specification or requirement not mentioned in this document. Preparation of a detailed schedule. Welds which are defective shall be repaired or cut out by SUBCONTRACTOR at no expense to CONTRACTOR. PWHT performance wherever necessary; requirements shall be based on the NDT table provided by Contractor. NDT as per project specifications. Dimensional control. Dummy pig Gauging. Coating of fabricated spools (OPTIONAL scope) EPCOL-SPM-PI-SOW-00001_Rev.B 11 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) • • Spools shall be preserved (with end caps) after prefabrication. Marking of the spools as mentioned in drawings and specifications. Dimensional Control Report of the finished items to be also included in the final As-Built Dossier. Inspection and operation of cranes including load test shall be in accordance with COMPANY requirements as provided in Contract. Design, procurement & fabrication of all temporary construction items necessary for the execution of the SOW. Exotic materials including CRA cladded materials shall be well segregated from CS materials, preserved and protected from any contamination in accordance COMPANY specifications. Final release of fabricated items from COMPANY appointed inspector. Reconciliation of FIM shall be submitted to Contractor upon complete of scope. Secure storage in readiness for transportation of finished items and also with proper end caps for both pipe ends and flanges. Packing, preservation and fastening for transportation, including pipe ends/flanges protection during load-out. Subcontractor shall agree with the Contractor Final Dossier Index. Delivery as per agreed terms and conditions. • Obtaining all necessary approvals required by Statutory Authorities (if applicable) • Compliance with certification requirements according to referenced Specifications, Work Instructions or any other CONTRACTOR/COMPANY requirement. • Provision of all the required documentation (including certificates and reports) prior, during and upon completion of the activities. • Subcontractor team together with CONTRACTOR shall conduct a monthly site management walkthrough with COMPANY during the fabrication period. • • • • • • • • • • It shall be under SUBCONTRACTOR’s responsibility to execute the SOW defined herein according to all listed Codes, Standards, COMPANY and CONTRACTOR’s Documents, and any other applicable documentation in a timely and professional manner. Furthermore, it shall be the responsibility of the SUBCONTRACTOR to verify upon receipt all the documents and drawings from CONTRACTOR for any discrepancies or contradictions, which should be reported immediately in writing to the CONTRACTOR. After fabrication completion, SUBCONTRACTOR shall be responsible to ensure all residual material has been returned to CONTRACTOR. EPCOL-SPM-PI-SOW-00001_Rev.B 12 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 7. DETAILED SCOPE OF WORK 7.1. PROJECT MANAGEMENT SUBCONTRACTOR will perform all necessary Project Management functions to execute and control the work. Project Management includes the management and supervision of all the subcontractors / Vendors and ancillary or temporary services that are necessary for the timely completion of the WORK in accordance with the CONTRACT. Project Management includes coordination with CONTRACTOR and third parties as required. SUBCONTRACTOR shall develop a Document Deliverable Register for CONTRACTOR review and approval. SUBCONTRACTOR shall submit the deliverables as per the Document Deliverable Register in timely manner for COMPANY & CONTRACTOR approval. SUBCONTRACTOR Project Management Team shall be composed by qualified and experienced personnel being members of SUBCONTRACTOR’s permanent staff. The appointed SUBCONTRACTOR’s Representative, HSE, Quality and Key Personnel shall not be replaced without approval from the COMPANY and CONTRACTOR for the duration of the Project. All key positions shall be approved by CONTRACTOR. As a minimum, the following key personnel shall be assigned FULL TIME to the project: 1. Fabrication Project Manager 2. HSE Manager 3. QA/QC Manager 4. Project Control Manager 5. Engineering Manager 6. Construction Manager 7. Superintendent. 8. Materials Manager 9. Welding Coordinator/Engineer 7.2. PROJECT CONTROL AND ADMINISTRATION SUBCONTRACTOR shall comply with the requirements of Project Control and other requirements of the Subcontract. SUBCONTRACTOR shall perform all project control activities required for managing the WORK, including but not limited to the following: EPCOL-SPM-PI-SOW-00001_Rev.B 13 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) • • Planning, scheduling, progress measurement, reporting, invoicing, costing and change control. Development of detailed project control procedures applicable to engineering, procurement, construction and completion works, covering all the aspects of planning, scheduling, progress reporting and validation, estimating, accounting and administration. • 90 Days Look-ahead Schedule to be added to SOW to be submitted 1 week from Effective Date. • Implementation of an effective system for planning, scheduling, quantitative measurement, and reporting of progress • Preparation and obtain the approval 2 months prior to start the work of the Planning Package, including but not limited to: - The overall detailed WORK schedule incorporating all phases of the WORK based on CONTRACTOR guidelines and agreed WBS, from Subcontract award to completion of loadout and acceptance certificate. The schedule of the works shall be presented to Contractor within the first 7 days after the contract effective starting date and shall be concurrent with Contractor schedule of delivery dates in regard to priorities and required partial / final delivery dates. - Manpower Histogram by discipline and mobilization Plan trade wise - Equipment Histograms - Schedule basis detailing all the assumption and basis considered during the schedule preparation covering but not limited to man-hours estimation norms, briefing on construction methodology, commodities details, schedule calendar, Schedule WBS - All the Native files word, excel… to be submitted with the planning package - Progress Measurement system (PMS) based on MH estimation & Weight Factor Based on Contractor Guidance • If SUBCONTRACTOR’s progress is falling behind schedule in the execution of its scope a Recovery Plan shall be submitted by SUBCONTRACTOR within 10 calendar days for approval by CONTRACTOR and then by COMPANY. Such Recovery Plan shall then be the basis for the balance work to be carried out by SUBCONTRACTOR. • Implementation of a proper Management of Changes process. Change process shall be as per project document 033727-A-Z-SPM-EM-P-00005 (Management Of Technical Change) • Implementation of a systematic Risk Management process. • Procurement tracking report for Procured Items by Subcontractor. • MDR for Documents & Deliverables under Subcontractor SOW. EPCOL-SPM-PI-SOW-00001_Rev.B 14 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) Documents, drawings and technical queries shall be transferred through proper transmittals as per approved document control procedure. 7.3. MOBILIZATION AND DEMOBILIZATION SUBCONTRACTOR shall be responsible for all the timely mobilization and demobilization of its resources suitable to perform the assigned SOW and subject to appropriate CONTRACTOR approvals for Key Personnel. SUBCONTRACTOR shall perform all the activities related to mobilization and demobilization of resources, including but not limited to: • • Personnel suitably qualified to perform the required scope of work, in line with COMPANY and CONTRACTOR requirements. Construction Equipment in compliance with COMPANY and CONTRACTOR requirements. SUBCONTRACTOR shall submit for CONTRACTOR & COMPANY approval an Organization and Staffing Plan that includes detailed organization charts, job descriptions, mobilization and demobilization timing of KEY PERSONNEL and all other positions within SUBCONTRACTOR organization. 7.4. SERVICES AND FACILITIES TO COMPANY & CONTRACTOR’S PERSONNEL Services and facilities for COMPANY and CONTRACTOR’s personnel mobilized at SUBCONTRACTOR’s Yard to be provided during the Execution of the SOW. COMPANY & CONTRACTOR FACILITIES and shall in any case conform to the requirements of the CONTRACT, COMPANY and CONTRACTOR’s requirements. Services and Facilities to COMPANY to be accordance with EXHIBIT 5 Appendix K. 7.5. YARD FACILITIES SUBCONTRACTOR shall have all infrastructures for fabrication such as workshops, and its utilities, equipment, machines, cranes, tools, scaffolding, compressed air, water, power and any other supply necessary to perform the work as per project requirement. All tools, equipment and materials shall be in good condition with valid certificates and comply with the relevant standards acceptable to the project. SUBCONTRACTOR shall provide the following, as minimum: • Prefabrication Workshops, workshop separated dedicated to prefabrication of exotic material. EPCOL-SPM-PI-SOW-00001_Rev.B 15 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) • • • • • • • • • • • • Proper area for NDE and radiographic testing. Suitable equipment for the operation in the Yard, such us cranes, forklifts, trailers, man lift’s, etc. Calibration laboratory (as alternative an external certified laboratory). Temporary water-tight enclosures as necessary to protect the work and equipment from weather, dirt and dust. All necessary temporary lifting, slinging and rigging equipment required. All such equipment shall be tested and certified by TPA and color coded to COMPANY standards. Auditable Rigging / Lifting Equipment register to be in place. Adequate storage open areas covered and environment-controlled areas where necessary. Air-conditioned and lockable warehouse storage facility to store equipment, consumables and material that requires humidity control and a dust-free environment. Sufficient lighting for execution and inspection of the work. Access to the working sites for COMPANY & CONTRACTOR personnel at all times. Dust control measures, if necessary Potable water, sanitation and first aid facilities at ground level in close proximity to the site, for all personnel use. Wastage area adequate with local legislation All temporary and permanent site offices, equipment and amenities/facilities for COMPANY, CONTRACTOR and PMC representatives and office personnel in accordance with COMPANY and CONTRACTOR’s requirements. 7.6. YARD ENGINEERING The yard engineering to be performed by SUBCONTRACTOR shall include, but not limited to: • • • Perform all the related multi-discipline detail fabrication engineering, including fabrication procedure, construction sequence and method statements. Engineering of all temporary facilities for fabrication if required. Finalize and handover “red marked-up” documents to CONTRACTOR. 7.7. SUBCONTRACTOR SUPPLIED MATERIAL SUBCONTRACTOR shall supply all materials required for completion of the SOW in addition to FIM provided by CONTRACTOR. This shall include, but not be limited to: • All fabrication materials except FIM. • Temporary structural material/ fabrication aids. • Welding equipment and consumables with valid certificates. • Test Coupon for WPS/PQR and Welder qualifications EPCOL-SPM-PI-SOW-00001_Rev.B 16 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) • NDT and inspection equipment and consumables with valid certificates. • Materials for dummy pig gauge fabrication. • Lifting & handling equipment with valid certificates. • Materials for loading and lashing of fabricated items. • All yard utilities to support activities. Engineering and procurement done by SUBCONTRACTOR shall be subject to CONTRACTOR’s approval. All material, consumables and equipment certificates shall be submitted to CONTRACTOR for review and acceptance before commencement of the fabrication. SUBCONTRACTOR shall provide certificates with test reports confirming compliance with the requirements of the respective specifications. 7.8. CONTRACTOR SUPPLIED MATERIAL (FIM) CONTRACTOR free issued material list is as per below: 1. All project permanent materials (CRA cladded cut to length pipes, flanges, fittings etc). FIM will be delivered to SUBCONTRACTOR’s Fabrication Yard, who shall be responsible to maintain ongoing record of supplied FIM quantities, material utilization in fabrication and quantities of unused material. Such records shall be submitted to CONTRACTOR at request any time during fabrication works. After the work completion and/or as per CONTRACTOR’s request, SUB-CONTRACTOR shall be responsible to return all residual material. 7.9. ACCEPTANCE OF FIM FROM CONTRACTOR Upon receipt of CONTRACTOR FIM, SUB-CONTRACTOR is required to inspect all the materials and verify correct dimensions and markings, as specified within delivery documentation, together with general condition of the same. In the event that any defects in the materials are identified, prior to completion of material handover to SUBCONTRACTOR, the extent of the defects and any remedial action to be taken by SUBCONTRACTOR shall be agreed by CONTRACTOR. Any materials that are found to be damaged or defective after handover and change of custody to SUBCONTRACTOR, shall be repaired or replaced by the same, as per CONTRACTOR’s instructions and with no additional cost impact. EPCOL-SPM-PI-SOW-00001_Rev.B 17 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 7.10. MATERIAL MANAGEMENT SUBCONTRACTOR shall be responsible for all material reception including controls for the completeness and integrity, either for his own procured material or for FIM. All items delivered to work site shall be customs-cleared, unloaded, unpacked, inspected, checked and stored, under SUBCONTRACTOR’s responsibility, complying with appropriate and agreed procedures. The material received in the yard shall be protected against atmospheric degeneration for the duration of the construction in compliance with Manufacturer’s instructions. The SUBCONTRACTOR shall provide adequate warehouses with racks, tarpaulins, etc. for storing equipment and materials as per specifications and vendor recommendation. SUBCONTRACTOR is required to separate the storage of paint, chemical and other flammable or toxic materials away from technical ends shall be suitably capped or plugged during storage. SUBCONTRACTOR shall have a fit for purpose procedures for the recording of the incoming /outgoing of materials from the site warehouse. Such procedures shall detail all relevant steps for the receipt and subsequent filing of all material documentation such as steel certificates, test certificates, etc. The material control procedures will be subject to prior approvals of CONTRACTOR and/or certifying authority as applicable. SUBCONTRACTOR shall adhere to the requirements of the CONTRACT with respect to Scrap Material and Surplus processing. SUBCONTRACTOR shall receive, handle, store, protect and issue all items, equipment and materials required for the satisfactory completion of the work. All items shall be always provided with protective caps. All piping material shall be stored in such a way to prevent rusting, ingress of sand, dirt and dust. All CRA cladded/Inconel items shall be separated from carbon steel and stored in a protected and controlled area. The SUBCONTRACTOR shall ensure a quality assurance and control system applied to all the Project Materials, moreover in case of materials purchased directly by SUBCONTRACTOR, that system shall cover the entire supply chain. Fabricated spools shall be similarly tagged, capped or plugged when stored prior to installation. Sub-Contractor shall be responsible for maintaining traceability of material, with suitable identification methods, until entire assembly is completed and final coated. CONTRACTOR site representative shall have the right to inspect the store, facilities and records at any time without prior notice. Such inspection will not relieve the SUBCONTRACTOR of any responsibility for the accountability and safe keeping of Materials. Within two days after receiving of the FIM in the yard and/or Custom clearing, SUBCONTRACTOR shall carry out an inspection of the material received to verify the integrity, the status of conservation and to check that there are no missing items from the Bill of Material / Bill of Loading. Such inspection shall involve SUBCONTRACTOR providing CONTRACTOR with FIM lists detailing relevant material shortages, overages and damages identified upon receipt and their affect upon EPCOL-SPM-PI-SOW-00001_Rev.B 18 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) the WORK. Any failure to report within the timeframe shown after SUBCONTRACTOR inspection will be wholly SUBCONTRACTOR responsibility, CONTRACTOR will not pay any construction delay costs, excluding cost of material, resulting from shortages of FIM material not properly reported by SUBCONTRACTOR. Transportation documentation will be provided by CONTRACTOR in due time. Full report of the inspection shall be submitted to the CONTRACTOR as per ITP. Any remedial work shall be agreed with CONTRACTOR prior to initiation any rework, as for ITP. After the receiving inspection the Free Issued Material shall be stored in a convenient area as per specifications/ vendor recommendation. Procedure for preservation and routine maintenance in all phases of Free Issued Material shall be issued by SUBCONTRACTOR. SUBCONTRACTOR shall maintain an ongoing reconciliation of the quantity of CONTRACTOR furnished Free Issued Material as utilized in the work and shall submit details of such reconciliation to CONTRACTOR on monthly basis. After the work is completed and as directed by CONTRACTOR, SUBCONTRACTOR shall prepare all surpluses Free Issued Material. CONTRACTOR may decide to deliver all project material, or part of, as FIM to SUBCONTRACTOR. Preservation and protection activity shall be initiated at the arrival of bulk material at the yard and maintained through the Fabrication and testing phases. 7.10.1. MATERIAL MANAGEMENT PROCEDURES SUBCONTRACTOR shall prepare, as part of the overall Project Procedures Manual a rigorous Materials Management procedure (including Traceability and Identification) for controlling the receipt, final inspection, preservation, warehousing, storage, security, distribution, surplus material handling and handover procedure for surplus material for the CONTRACTOR’s free issue material of all equipment and materials received by SUBCONTRACTOR for execution of the Scope of WORK. These procedures shall consider, as a minimum: • Implementation and use of integrated (automated) materials management systems. This system shall be made accessible to CONTRACTOR’s designated personnel. The SUBCONTRACTOR shall facilitate in providing minimum data but not limited, in the required format, so as to align with CONTRACTOR’s material management system. • CONTRACTOR & SUBCONTRACTOR shall jointly develop a system to exchange the database before the receipt of material which include material receipt, allocation issue, weld data, test pack status etc. • Performing materials availability planning. • Issuing of Materials Receiving Reports (MRR) & Over, Short, Damaged and Rejected (OSDR) report. The OSDR report shall be issued by SUBCONTRACTOR within five (5) EPCOL-SPM-PI-SOW-00001_Rev.B 19 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) calendar days from the date of receipt after which the material as per packing list is deemed to be received and confirmed by SUBCONTRACTOR • Receipt, identification, checking for quality, damage and quantity of materials (On Shop & Delivered items) and documentation at SUBCONTRACTOR‟s fabrication yard • Initiating claims for defective and damaged items and shortages of equipment, materials and spares and the handling of such items • Stock control • Warehousing management and controls • Allocation of dedicated area for storage of free issue material issued by CONTRACTOR • Storing and protecting materials both internally and externally, as well as in environmentally controlled areas, all in accordance with manufacturer’s storage, protection and preservation recommendations • Maintaining computerized records of issue of materials for fabrication and installation to be used for current information on stock and traceability and which shall be accessible to CONTRACTOR representative on shop(s)/ yard(s) • Material handling • Materials reconciliation, handling and hand over of surplus materials for CONTRACTOR free issue material; periodically and on completion of the Scope of Work. The reconciliation of free issue material shall be carried by Subcontractor on quarterly basis. However, SUBCONTRACTOR shall provide reconciliation of any particular material item at any point of time, if requested by CONTRACTOR The dedicated area allocated for the Subcontract scope of work in the yard(s)/ shop(s) shall be ready to receive the free issue material from CONTRCATOR and Subcontractor scope of supply well in advance compared to the fabrication start date; so that management of material is well streamlined before the fabrication start up in the yards(s). SUBCONTRACTOR shall make necessary arrangement to unload the free issue material issued by CONTRACTOR within agreed time to avoid any demurrage from the Logistics vendor. 7.10.2. MATERIAL TRACEABILITY AND CONTROL PLAN SUBCONTRACTOR shall provide a material traceability and control plan that describes the material traceability and controls implemented throughout fabrication including material receipt, storage, handling, marking, cutting, and integration. The plan shall address welding consumables, weld numbering, welder traceability down to zones of a weld , and NDT results. The plan shall consider and reference as appropriate contamination, special handling, suspected contamination and cleaning requirements, as well as damage associated with CRA materials. EPCOL-SPM-PI-SOW-00001_Rev.B 20 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) The storage and handling of welding consumables shall be in accordance with manufacturer's recommendations. The storage and handling procedure shall be submitted to CONTRACTOR/COMPANY for review and acceptance. Welding consumables are to be fully traceable by batch and used sequentially with new batches being opened only after consumption of the preceding batch. Different batches of consumables shall be individually identified and separated. The marking shall be carried out by paint stenciling using suitable paint and No marking shall be done on the CRA. 7.10.3. SURPLUS AND SCRAP MATERIAL SUBCONTRACTOR shall: • Prepare a scrap/surplus material report periodically and at the end of the project. The report shall: - Identify all scrap/surplus materials - Nominate the method of disposing of scarp and redundant materials - Handing over details of Surplus material for the CONTRACTOR FIM - Address key environmental protection measures required for disposing of environmentally damaging materials Scrap materials from free issue materials supplied by CONTRACTOR to be disposed of as directed by CONTRACTOR. SUBCONTRACTOR to provide costs for disposal and or resale for CONTRACTORS review and advice. Surplus materials resulted from free issue materials supplied by CONTRACTOR shall be returned CONTRACTOR periodically and at the end of the project. Reconciliation of materials free issued to SUBCONTRACTOR: SUBCONTRACTOR shall prepare cutting & nesting plan for the free issue material and submit for CONTRACTOR approval. Also, SUBCONTRACTOR shall optimize the nesting plan for effective utilization and reduce the wastage of material. The wastage & scrap allowance for the free issue material provided by CONTRACTOR shall be as follows. The table shall be used as guidelines only. DESCRIPTION OF MATERIAL % OF WASTE & SCRAP ALLOWANCE Pipes with size 3” but less than 12” 1.5% Pipes with size 12” and above 1% Pipe Fittings and Flange Not allowed EPCOL-SPM-PI-SOW-00001_Rev.B 21 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) The mechanism for demarcating scrap material and surplus material shall be as follows. This is applicable for the free issue material provided by CONTRACTOR. DESCRIPTION OF MATERIAL UNIT SCRAP SURPLUS Pipe Cladded with all sizes m Less than 0.3 Mtr Long More than 0.3 Mtr long Pipe Fittings and Flange for all category and size Nos. Not allowed All Surplus 7.11. SUBCONTRACTS SUBCONTRACTOR may issue subcontracts to other parties for the performance of some part of this scope, if deemed necessary. Subcontract of any services including pre-qualification of proposed subcontractors shall be approved by CONTRACTOR & COMPANY in accordance with the Contract. The complete list of tier-subcontractors and tier-vendors shall be issued to CONTRACTOR within 2 weeks from PO award. 7.12. PROJECT LANGUAGE All correspondence and project documents shall be in the English language. All Key Personnel shall be fluent in the English language. 7.13. PRE-FABRICATION SUBCONTRACTOR shall be responsible to fabricate various types of CRA Cladded pipe spools as per latest approved drawings, project specifications and standards. Drawings will issue to subcontractor once detail engineering is finalized. It is under SUBCONTRACTOR’s responsibility to confirm possession of latest approved drawing revision before starting a fabrication. This scope includes topside spools under code DNV-ST-F101, ASME B31.8 and B31.3. Subcontractor shall provide temporary materials, consumables and required utilities to complete the scope. CONTRACTOR will issue bevelled cut to length CRA cladded pipes, flanges and fittings such as elbow, tees, reducers , sweepolets etc as FIM. Cutting discs will only be considered for cutting provided there is safe ID access and protection from iron contamination is implemented with prior COMPANY approval. Cutting processes that use heat for cutting shall not be used on CRA materials. Notches, burrs, swarf, and damage on the bevel shall be removed by COMPANY approved tools that are suitable for use on CRA materials and do not carry the risk of contamination. When performing fit-up for girth welding, precautions shall be taken in order to minimize the internal hi-lo and fulfil the hi-lo requirement specified in project specification. EPCOL-SPM-PI-SOW-00001_Rev.B 22 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) Dimensional control at all stages. Any resulting final dimension out of agreed tolerance shall be submitted to CONTRACTOR for approval and release before any re-fabrication activity starts. Concession Request shall be raised to CONTRACTOR in such occurrences. As-built drawings shall be issued once fabrication has been completed together with Dimensional Control Certificate. Welding & NDT shall be as per below sections of this SOW. All welded end spools shall be bevelled as per standard and properly capped before load-out. All the prefabricated spools shall be properly marked as per standard as well as CONTRACTOR instruction. Table 1: Size Range 6" 8" - 12" 14" - 24" 26" - 36" Tot no.of joints (Appx) 192 1,402 188 1,020 Tot. Dia Inches (Appx) 1134 16,069 4,178 28,849 > 36" 97 4331 Painting Area/System (Sqm) 9802 / Type A Total 2,899 54,561 Note :For thickness refer attached MTO in Annex 1 9,802 Table 2: Sweepolets to be Integrated on Pipes No. Of Size Sweepolets < 2” 440 2” 316 3” 7 4” 24 6” 10 8” 17 10” 18 14” 4 Total 836 Note: 1. For thickness and header size refer attached MTO in Annex 1 2. Below 6” are Solid Inconel and 6” & above are CRA cladded(Refer MTO) 3. Quantities are not considered in Table 1 Dia inches. EPCOL-SPM-PI-SOW-00001_Rev.B 23 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 7.14. WELDING AND NDT REQUIREMENTS In addition to the applicable international codes, standards, engineering design drawings, contract, scope of work, and approved fabrication and quality related procedures, the welding and inspection shall be carried out with reference to the following main COMPANY specifications but not limited to: 200-20-PI-SPC-0011 Piping general welding requirement & inspection 200-20-PI-SPC-0012 Piping Specification for Fabrication and Erection 200-24-PL-SPC-0009 RT and other NDT Requirements 200-20-CE-SPC-0001 CRA Weld Overlay for Piping Materials Specification 200-20-PI-SPC-0009 Material & Corrosion Requirements for Sour Service 200-20-PI-SPC-0027 Positive materials identification (PMI) 200-20-PI-SPC-0023 Specification for Pipes 200-20-PI-SPC-0017 Specification for Fittings 200-24-PL-SPC-0010 CRA Welding Specification 200-20-MO-SPC-0005 Specification for Fabrication and Load out The latest revision of above documents as well as the latest approved issued for EPCI shall apply. SUBCONTRACTOR shall mobilize qualified and experienced welding engineers at the fabrication yard, welding supervisors, and welding inspectors to prepare, execute, and complete the welding qualification campaign. Special task force shall be mobilized and dedicated to accomplishing all required qualifications and deliverables and procedures in due time. SUBCONTRACTOR organization chart along with CVs to undertake the qualification shall be proposed and submitted to CONTRACTOR for review and approval. It is subcontractor responsibility to provide the welding engineering team in a proper size to meet company & contractor requirements and workload as per project schedule. SUBCONTRACTOR shall thoroughly evaluate the technical requirements and ensure all will be considered in the schedule development and fabrication execution. SUBCONTRACTOR shall develop the welding qualification matrix compliance with the scope of work and technical requirements. The matrix shall be subjected to the CONTRACTOR and COMPANY approval. SUBCONTRACTOR shall develop and submit all required WPS/PQR for CONTRACTOR and COMPANY approval. SUBCONTRACTOR shall utilize as much as possible the existing qualified PQRs. However, the approval is solely subjected to CONTRACTOR and COMPANY approval. SUBCONTRACTOR shall develop any fabrication-welding procedures related for quality control implementation and subjected to CONTRACTOR and COMPANY approval. SUBCONTRACTOR shall qualify the welders/welding operators in the witness of CONTRACTOR and COMPANY Inspection Representative. The approval to the existing welders/welding operator qualifications is subjected to the CONTRACTOR and COMPANY review and approval. SUBCONTRACTOR shall supply all required welding consumables, electrodes, gas, wires, fluxes. The supply shall comply with technical requirements of above specifications. EPCOL-SPM-PI-SOW-00001_Rev.B 24 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) SUBCONTRACTOR shall implement all required inspections and NDT technique/methods specified in the above specifications. SUBCONTRACTOR shall develop the procedures for inspection and NDT. The personnel performed the inspection shall comply with required certifications and subject to CONTRACTOR and COMPANY approval. SUBCONTRACTOR shall assign only the approved NDT Company(s). For CRA piping, SUBCONTRACTOR shall assign the IVT with camera and laser Inspection COMPANY. SUBCONTRACTOR shall ensure that the equipment, calibration, qualification, personnel, acceptance criteria, and procedures meet the above-mentioned specifications. 7.15. DUMMY PIG GAUGING Spools under pipeline specification require to be gauged in fabrication yard prior being subject to hydrostatic testing and a report shall be prepared. - For cladded spools dummy pull-through pig with non-metallic or alternatively dummy pullthrough pig with fully PU coated aluminum gauging plates shall be used. OD of gauging plate shall be 95% of min. ID excluding any tolerances or 97% of min. ID including fabrication tolerances as per DNV-ST-F101. Final dimensions of gauging plates must be issued to Contractor for approval. For the activity subcontractor shall prepare a dedicated procedure. Material procurement and fabrication of dummy pig gauges are under subcontractor scope. 7.16. COATING (OPTION) SUBCONTRACTOR shall coat fabricated spools in accordance with COMPANY Standards, Construction Procedures, Construction Drawings, and this Scope of Work. All the coating on weld joints shall be done after hydrostatic test. Surface Preparation and coating application shall be performed in accordance with approved procedure and standards. Also, blasters, applicators, and coating crew supervisor shall be approved in accordance with Company requirements. SUBCONTRACTOR shall supply anticorrosive material & the required consumables and shall be followed below requirements. i. All the anti-corrosive materials for each coating system shall be supplied by the same manufacturer. Only proprietary thinner from the same manufacturer shall be used. ii. Anti-corrosive and abrasive materials shall be supplied only from Approved vendors/manufacturers, the selected materials list shall be submitted to contractor for approval. iii. Materials shall be handled in order to avoid damage and stored in accordance with the applicable safety regulations and with material MANUFACTURER’s recommendations. EPCOL-SPM-PI-SOW-00001_Rev.B 25 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) Storage temperatures and environmental parameters for coating materials shall be as specified by the material MANUFACTURER. iv. Materials shall be used before their expiry date. 7.17. STORAGE , HANDLING AND TRANSPORTATION The prefabricated items shall be treated in a manner such that no damage is causing during handling. All shop-fabricated piping spools shall be thoroughly cleaned inside and out of all dirt, loose mill scale, cutting chips, weld spatter, and other debris. All openings shall be protected after completion of inspection. All spools shall be prepared for shipment as follows: • Bevelled ends and flange gasket surfaces shall be protected from mechanical damage over their entire surface by firmly attached end caps. Threaded-end or socket-welding-end connections shall be fitted with metal, wood, or plastic plugs or caps. Packing material and associated securing requirement for transportation are under SUBCONTRACTOR’s responsibility. Care shall be taken to ensure that no damage is caused during rigging, loading, fastening and offloading activities related to transportation of each item. SUBCONTARCTOR shall provide temporary free storage place(minimum 90 Days) for prefabricated spools if requested by CONTRACTOR. SUBCONTRACTOR shall consider required equipment and manpower to load fabricated items on truck provided by CONTRACTOR. 7.18. MINIMUM DOCUMENTATION TO BE PROVIDED As a minimum below list of documents shall be submitted upon contract award: 7.18.1. WITHIN 2 WEEKS ONWARDS FROM CONTRACT AWARD • Master Document Register • Project Organization Chart • QA/QC Organization Chart clearly showing the names of the key functions, with particular care to Quality-related ones, along with relevant reporting and communication lines. • Yard Layout • Project Schedule and Yard equipment utilization schedule • Project Planning and Progress Management Procedure • Procurement plan EPCOL-SPM-PI-SOW-00001_Rev.B 26 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) • Project Quality Plan • Project Quality Audit Procedure • Project Quality Audit Schedule • Calibration procedures • Procedure For Document Control • Fabrication Procedures • Dimensional control procedures • NDT procedures • PWHT Procedure • Preheat and Preheat Monitoring Procedure • Non-Conformance & Corrective Action Procedure • Welding plans, procedures, and qualifications. • Procedure For Control, Storage And Distribution Of Welding Consumables • Storage & Preservation procedures. • Lifting and handling procedures. • Inspection and Test plans (ITPs) • Personnel Qualification Documentation / Certificates /CV s • HSE plans • Project Emergency Plan • Yard HSE procedures • HSE Training & Campaign Plan 7.18.2. UPON COMPLETION OF THE SCOPE The following documents shall be included in the final documentation dossier, to be submitted upon completion of the fabrication and testing: • QA/QC documentation, • WPS’s and PQR’s including respective repair procedures, • Welders’ certificates, • Welding, NDT, Coating and Hydrotest procedures. • Fully dimensional as-built drawings, including a complete list of materials, • General consumable material certificates, • Mill test certificates of materials, EPCOL-SPM-PI-SOW-00001_Rev.B 27 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) • Certificates of welding consumables, • Weld history records, • Welding, NDT, coating, QC personnel log, • Material records, • Welding, NDT, coating and Hydrotest reports, • Repair reports, • Dimensional inspection reports, • Material certificates, • Certificate of Conformity • Certificate of Origin • Packing lists • List of deviations, concessions, non-compliances, non-conformities • In addition to the above SUB-CONTRACTOR shall provide any other information as requested by CONTRACTOR documents. The As-built package / Delivery dossier shall be ready within two (2) weeks from works completion. All drawings produced by SUBCONTRACTOR shall be provided to CONTRACTOR also in the native form. 8. QUALITY ASSURANCE/QUALITY CONTROL Shall be as per Project Quality Plan. 9. HEALTH, SAFETY AND ENVIRONMENT Shall be as per Project HSE Plan. 10. FABRICATION MILESTONE Prefabricated and coated spools shall be delivered as per below schedule. 1 2 3 4 5 Facility WHP14S WHP12N RP7S RP4S WHP13S Ready By 19-Apr-22 28-Apr-22 10-May-22 21-May-22 25-May-22 EPCOL-SPM-PI-SOW-00001_Rev.B 28 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 6 7 8 9 10 11 12 RP4N RP8S RT2 RP6S RP11S RP10S WHP12S 31-May-22 21-Jun-22 23-Jun-22 29-Jun-22 26-Jul-22 05-Aug-22 24-Aug-22 11. RESPONSIBILITY MATRIX All works shall be done in accordance with the Responsibility Matrix between Contractor and Subcontractor as detailed hereinafter: DESCRIPTION 1 1.1 GENERAL General Main contract administration, organization and interf ace with COMPANY Project coordination procedure Compliance with COMPANY directives throughout duration of Subcontract, as applicable. Strict adherence to COMPANY's Procedures, Rules and Regulations for perf orming Subcontract Works Provide f ree access to COMPANY / CONTRACTOR / its Appointed agents etc. at all stage of Subcontract works Of f ice Facilities for CONTRACTOR and COMPANY Planning scheduling and progress monitoring Project execution plan for subcontract part Daily and weekly progress reports Daily submission of daily activity sheet and manpower allocation for progress monitoring Detailed project execution schedule (for the subcontract part) Manpower histogram and man hours tracking HSE HSE policy / coordination / permit to work HSE management HSE supervision 1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6 1.2 1.2.1 1.2.2 1.2.3 1.2.4 1.2.5 1.3 1.3.1 1.3.2 1.3.3 EPCOL-SPM-PI-SOW-00001_Rev.B SUBCONTRACTO R No CONTRACTOR Legend - R (Responsible); NOTES R R R R R R R R R R R R R R 29 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project DESCRIPTION 1.3.4 1.3.5 1.3.6 1.4 1.4.1 1.4.2 1.4.3 1.4.4 1.4.5 1.4.6 1.4.7 1.4.8 1.4.9 1.4.10 1.4.11 1.4.12 1.4.13 2 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.10 3 3.1 Barricades, Sign boards, etc. Worker’s PPE Saf ety Audits Quality Quality policy / coordination with COMPANY. Quality management with COMPANY. Quality control plan execution with Quality Personnel QC construction activities and supervision Filling and signature of forms. Supply of qualified QC personal Yard Quality Management NDT Reports Welding & Welders qualification, WPS, PQR Action Closeout (NCR's) Final Dossier Project Specification Quality procedures ENGINEERING Project specifications and procedures Engineering and Fabrication Isometric Drawings Approval of the change requests Material Take off MTO endorsement Fabrication Procedures and method statements Red marked up As built drawings for final dossier Approval of the change requests Welding Book PROCUREMENT Raw Materials f or fabrication 3.2 Paints and other consumables required for painting 3.3 Welding and NDT consumables EPCOL-SPM-PI-SOW-00001_Rev.B SUBCONTRACTO R No CONTRACTOR SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) NOTES R R R R R R R R R R R R R R R R R R R R R R R R R R R To be quoted as Optional. R 30 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SUBCONTRACTO R CONTRACTOR SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) No DESCRIPTION 3.4 Test coupons for WPS / PQR R 3.5 3.6 3.7 3.8 4 Test Coupons for Welders Qualifications All Fabrication aids Utilities for Fabrication Material f or Dummy PIG Gauge fabrication OPERATIONS Mobilization, maintenance and demobilization of skilled & unskilled Manpower. Equipment insurance, certification & calibration R R 4.6 Material receiving, handling, preservation, inspection, storage, etc. Pref abrication (handling, cutting, edge preparation, beveling, drilling, preservation, etc.). Fit up, pre-heating (wherever required); welding, PWHT (wherever required); intermediate and final NDT. Positive Material Identification (PMI) 4.7 Spool marking R 4.8 Blasting and Painting R 4.9 Handling Equipment for Subcontractor activities (as per this SOW) R 4.10 Dimensional control R 4.11 4.12 4.13 4.14 4.15 4.16 4.17 Dummy PIG Gauging Final preservation (Spool preservation with end caps) Raw materials shipment to Subcontractor yard Unloading of raw materials at Subcontractor yard Delivery of prefabricated items at Contractor’s premises Delivery of surplus / scrap materials at Contractor’s premises Material reconciliation R R 4.1 4.2 4.3 4.4 4.5 EPCOL-SPM-PI-SOW-00001_Rev.B NOTES R R R R R R R R To be quoted as Optional. R R R R R 31 of 32 EPC for North Field Production Sustainability Offshore & Pipelines Project SCOPE OF WORK FOR PRE-FABRICATION OF TOPSIDE CRA CLADDED SPOOLS (GREEN FIELD) 12. ANNEXURES Annex 1 – Project Documents Annex 2 – Technical and Commercial Proposal Requirements Annex 3 – Price list EPCOL-SPM-PI-SOW-00001_Rev.B 32 of 32