MAFIPRO CENTRAL FISH PROCESSING PLANT ( Tender Programme) r1

advertisement
MAFIPRO CENTRAL FISH PROCESSING PLANT (CFPP) Lot 103, Jalan Perusahaan Tiga Kamunting, Industrial Estate, Perak, 34600 Kamunting, Malaysia
Activity ID
Activity Name
Original Start
Duration
MAFIPRO CENTRAL FISH PROCESSING PLANT (CFPP) r1
Project Milestone
MAF1000
Project Start
MAF1100
Project Finish
Finish
2023
Mar
219 09-May-23
21-Dec-23
219 09-May-23
21-Dec-23
Apr
0
219 09-May-23
Jun
Jul
Aug
Sep
Oct
Nov
Dec
2024
Jan
21-Dec-23, MAFIPRO CENTRAL FISH PROCESSIN G P
21-Dec-23, Project Milestone
Project Start
0 09-May-23
Construction Milestone Dates
May
Project Finish
21-Dec-23
21-Dec-23, Construction Milestone Dates
21-Dec-23
Start of Mobilisation and Site Set-up
MAF0018
Start of Mobilisation and Site Set-up
0
09-May-23
MAF0019
Completion foundations processing area
0
17-Jul-23
MAF0020
Completion mezzanine RC Slab
0
30-Aug-23
MAF0021
Completion Floor Finishing (PU coatings)
0
10-Nov-23
Completion Floor Finishing (PU coatings)
MAF0022
Completion installation of MEP systems
0
10-Nov-23
Completion installation of MEP systems
MAF0023
Building ready for equipment installation
0
07-Dec-23
MAF0024
Start Project Close-out
0
08-Dec-23
MAF0025
Signing Taking-over Certificate
0
21-Dec-23
General & Preliminaries
125 09-May-23
14-Sep-23
Completion foundations processing area
Completion mezzanine RC Slab
Building ready for equipment installation
Start Project Close-out
Signing Taking-over Certificate
14-Sep-23, General & Preliminaries
17-May-23, Contractual Requirements
9 09-May-23
17-May-23
MAF0010
Permit and Fees
7 09-May-23
15-May-23
MAF0011
Bonds, Guarantees , Securities and Insurances
7 10-May-23
16-May-23
MAF007
Construction Industry Development Board (CIDB) Requirements
7 11-May-23
17-May-23
MAF008
Contractual Requirements
9 09-May-23
17-May-23
MAF009
Certification and guarantees
7 09-May-23
15-May-23
125 09-May-23
14-Sep-23
Temporary Access
20 09-May-23
5 09-May-23
28-May-23
13-May-23
MAF0014
Temporary Buildings (Office for Consultant/Client including, Furniture and Stationary)
14 11-May-23
24-May-23
MAF0015
Temporary Structures
14 13-May-23
26-May-23
MAF0016
Contractor's Storage Sheds,Site Office and other Site Facilities
14 15-May-23
28-May-23
Administration & Quality
120 14-May-23
120 14-May-23
14-Sep-23
14-Sep-23
Safety, Health and Welfare of Work People
120 14-May-23
14-Sep-23
134 09-May-23
24-Sep-23
24-Sep-23, Pre Construction Works
134 09-May-23
24-Sep-23
24-Sep-23, Structure Works
14 09-May-23
22-May-23
120 23-May-23
24-Sep-23
28 09-May-23
06-Jun-23
14 09-May-23
22-May-23
Contractual Requirements
Contractor Preliminaries
Temporary Works
MAF0013
Recurring Works
MAF2670
MAF2680
Pre Construction Works
Structure Works
MAF0058
Preparation of Material Submission and Shop Drawing
MAF0088
Rebar Fabrication (Cut and Bend)
Architecture Works
MAF1210
Preparation of Material Submission and Shop Drawing
MAF1220
Approval of Material Submission and Shop Drawing
MEP Works
14 23-May-23
06-Jun-23
113 09-May-23
02-Sep-23
MAF2230
Preparation of Material Submission and Shop Drawing
14 09-May-23
22-May-23
MAF2240
Approval of Material Submission and Shop Drawing
14 23-May-23
06-Jun-23
Water C ooled Chille rs
85 07-Jun-23
60 07-Jun-23
02-Sep-23
07-Aug-23
MAF3040
Water Pumps
45 27-Jun-23
12-Aug-23
MAF3050
Air Handling Units
60 17-Jun-23
17-Aug-23
MAF3060
Fan coils
45 08-Jul-23
22-Aug-23
MAF3070
Cooling Tower
45 13-Jul-23
27-Aug-23
MAF3080
Exhaust Fan
60 27-Jun-23
27-Aug-23
MAF3090
Cleanroom Wall Panel
45 13-Jul-23
27-Aug-23
MAF3100
Control Panel
45 13-Jul-23
27-Aug-23
MAF3110
Ice Flake Maker
45 13-Jul-23
27-Aug-23
MAF3120
Heat Exchanger
60 27-Jun-23
27-Aug-23
MAF3130
Roller Shutter
60 27-Jun-23
27-Aug-23
MAF3140
Fire rated door
60 27-Jun-23
27-Aug-23
MAF3150
Stainless Steel Tank
60 27-Jun-23
27-Aug-23
MAF3160
Air Compressor
30 29-Jul-23
27-Aug-23
MAF3170
Water Tank
60 03-Jul-23
02-Sep-23
MAF3180
Genset
30 07-Jun-23
07-Jul-23
MAF3190
Doors and Windows
30 17-Jun-23
17-Jul-23
MAF3200
Piping
30 27-Jun-23
28-Jul-23
Construction Works
217 11-May-23
21-Dec-23
Production Building
178 11-May-23
10-Nov-23
18 16-May-23
7 16-May-23
02-Jun-23
22-May-23
Long Lead Items
MAF3030
Demolition works
MAF2690
Existing ramp
MAF2700
Existing perimeter drain
4 18-May-23
21-May-23
MAF2710
Existing apron slab
7 18-May-23
24-May-23
MAF2720
Existing floor slab, incl. thawing area, FFA room and ante room 3
12 18-May-23
29-May-23
MAF2730
Chipping away the existing Epoxy floor in Cold room
4 21-May-23
24-May-23
MAF2740
Repair the existing floor and ceiling to lay new finishing coat
4 30-May-23
02-Jun-23
151 11-May-23
45 11-May-23
12 14-May-23
14-Oct-23
25-Jun-23
25-May-23
Structure Works
Sub- Structure
MAF3240
Excavation
MAF3250
Pilling Works
20 11-May-23
30-May-23
MAF3260
Pilling cutting and Pile Head works
10 26-May-23
04-Jun-23
MAF3270
Pile Caps
20 06-Jun-23
25-Jun-23
Ground beam
108 03-Jun-23
53 03-Jun-23
30 03-Jun-23
23-Sep-23
28-Jul-23
04-Jul-23
MAF2760
Ground Slab
30 17-Jun-23
17-Jul-23
MAF2800
Column Ground to Level 1
20 08-Jul-23
28-Jul-23
Reinforced concrete Works
Ground Level
MAF2750
Actual Work
Milestone
Remaining Work
Summary
Critical Remaining Work
14-Sep-23, Contractor Preliminaries
28-May-23, Temporary Works
14-Sep-23, Recurring Works
06-Jun-23, Architecture Works
02-Sep-23, MEP Works
02-Sep-23, Long Lead Items
21-Dec-23, Construction Works
10-Nov-23, Production Building
02-Jun-23, Demolition works
14-Oct-23, Structure Works
25-Jun-23, Sub- Structure
23-Sep-23, Reinforced concrete Works
28-Jul-23, Ground Level
Tender Programme Final Submission (19 April 2023)
Page 1 of 2
MAFIPRO CENTRAL FISH PROCESSING PLANT (CFPP) Lot 103, Jalan Perusahaan Tiga Kamunting, Industrial Estate, Perak, 34600 Kamunting, Malaysia
Activity ID
Activity Name
1st Level
MAF2770
Original Start
Duration
Finish
1st Level beam
45 24-Jul-23
25 24-Jul-23
07-Sep-23
17-Aug-23
MAF2780
1st Level Slab
25 03-Aug-23
27-Aug-23
MAF2790
Column Level 1 to Roof
20 18-Aug-23
07-Sep-23
Roof Slab
15 08-Sep-23
15 08-Sep-23
23-Sep-23
23-Sep-23
Metal Work
MAF2820
Main steel structure
30 13-Sep-23
30 13-Sep-23
14-Oct-23
14-Oct-23
Staircase & Ramp
MAF2830
Staircase & Ramp
45 18-Aug-23
45 18-Aug-23
04-Oct-23
04-Oct-23
Roof Level
MAF2810
Architecture Works
MAF2840
Masonry works
85 08-Aug-23
40 08-Aug-23
03-Nov-23
18-Sep-23
MAF2850
Door,gla zing, windows and louvers
30 23-Aug-23
23-Sep-23
MAF2860
Floor Finishing
35 28-Aug-23
04-Oct-23
MAF2870
Wall Finishing
45 28-Aug-23
14-Oct-23
MAF2880
Sanitary Ware
45 08-Sep-23
24-Oct-23
MAF2890
Ceiling
50 13-Sep-23
03-Nov-23
Electrical Works
95 05-Aug-23
60 05-Aug-23
10-Nov-23
06-Oct-23
MAF2910
Plumbing & Sanitary Pipings
55 20-Aug-23
16-Oct-23
MAF2920
Building Chiller Water System
60 20-Aug-23
21-Oct-23
MAF2930
Waste Water Pipeline & City Water Supply
60 25-Aug-23
26-Oct-23
MAF2940
Compressor Air Piping
45 15-Sep-23
31-Oct-23
MAF2950
Fire Fighting
55 15-Sep-23
10-Nov-23
Mechanical Systems - Efrigeration equipment, Compressors, Condensers, and Evaporators
50 15-Aug-23
30 15-Aug-23
06-Oct-23
14-Sep-23
MAF3220
Electrical Systems - The power distribution systems
25 30-Aug-23
25-Sep-23
MAF3230
Plumbing Systems- drainage and water supply systems
25 10-Sep-23
06-Oct-23
50 18-Aug-23
09-Oct-23
MEP Works
MAF2900
Cold Room
MAF3210
Infrastructure works
MAF2960
RC Manhole
20 18-Aug-23
07-Sep-23
MAF2970
Premeter drain & Cover
25 23-Aug-23
18-Sep-23
MAF2980
RC wall sump
25 03-Sep-23
29-Sep-23
MAF2990
Septic, Oil/ grease trap & retaining tanks
45 23-Aug-23
09-Oct-23
Testing & Commissioning and as-Built Drawings
MAF3000
As-Built Drawing
MAF3010
Testing & Commissioning
Signing Taking-over Certificate & Handover
MAF3020
Signing Taking-over Certificate & Handover
Actual Work
Milestone
Remaining Work
Summary
Critical Remaining Work
2023
Mar
135 21-Jul-23
07-Dec-23
120 21-Jul-23
22-Nov-23
25 11-Nov-23
07-Dec-23
14 08-Dec-23
21-Dec-23
14 08-Dec-23
21-Dec-23
Apr
May
Jun
Jul
Aug
Sep
07-Sep-23, 1st Level
Oct
Nov
Dec
2024
Jan
23-Sep-23, Roof Level
14-Oct-23, Metal Work
04-Oct-23, Staircase & Ramp
03-Nov-23,Architecture Works
10-Nov-23, MEP Works
06-Oct-23, Cold Room
09-Oct-23, Infrastructure works
07-Dec-23, Testing & Commissioning and as-Built Drawings
21-Dec-23, Signing Taking-over Certificate & Handover
Tender Programme Final Submission (19 April 2023)