MAFIPRO CENTRAL FISH PROCESSING PLANT (CFPP) Lot 103, Jalan Perusahaan Tiga Kamunting, Industrial Estate, Perak, 34600 Kamunting, Malaysia Activity ID Activity Name Original Start Duration MAFIPRO CENTRAL FISH PROCESSING PLANT (CFPP) r1 Project Milestone MAF1000 Project Start MAF1100 Project Finish Finish 2023 Mar 219 09-May-23 21-Dec-23 219 09-May-23 21-Dec-23 Apr 0 219 09-May-23 Jun Jul Aug Sep Oct Nov Dec 2024 Jan 21-Dec-23, MAFIPRO CENTRAL FISH PROCESSIN G P 21-Dec-23, Project Milestone Project Start 0 09-May-23 Construction Milestone Dates May Project Finish 21-Dec-23 21-Dec-23, Construction Milestone Dates 21-Dec-23 Start of Mobilisation and Site Set-up MAF0018 Start of Mobilisation and Site Set-up 0 09-May-23 MAF0019 Completion foundations processing area 0 17-Jul-23 MAF0020 Completion mezzanine RC Slab 0 30-Aug-23 MAF0021 Completion Floor Finishing (PU coatings) 0 10-Nov-23 Completion Floor Finishing (PU coatings) MAF0022 Completion installation of MEP systems 0 10-Nov-23 Completion installation of MEP systems MAF0023 Building ready for equipment installation 0 07-Dec-23 MAF0024 Start Project Close-out 0 08-Dec-23 MAF0025 Signing Taking-over Certificate 0 21-Dec-23 General & Preliminaries 125 09-May-23 14-Sep-23 Completion foundations processing area Completion mezzanine RC Slab Building ready for equipment installation Start Project Close-out Signing Taking-over Certificate 14-Sep-23, General & Preliminaries 17-May-23, Contractual Requirements 9 09-May-23 17-May-23 MAF0010 Permit and Fees 7 09-May-23 15-May-23 MAF0011 Bonds, Guarantees , Securities and Insurances 7 10-May-23 16-May-23 MAF007 Construction Industry Development Board (CIDB) Requirements 7 11-May-23 17-May-23 MAF008 Contractual Requirements 9 09-May-23 17-May-23 MAF009 Certification and guarantees 7 09-May-23 15-May-23 125 09-May-23 14-Sep-23 Temporary Access 20 09-May-23 5 09-May-23 28-May-23 13-May-23 MAF0014 Temporary Buildings (Office for Consultant/Client including, Furniture and Stationary) 14 11-May-23 24-May-23 MAF0015 Temporary Structures 14 13-May-23 26-May-23 MAF0016 Contractor's Storage Sheds,Site Office and other Site Facilities 14 15-May-23 28-May-23 Administration & Quality 120 14-May-23 120 14-May-23 14-Sep-23 14-Sep-23 Safety, Health and Welfare of Work People 120 14-May-23 14-Sep-23 134 09-May-23 24-Sep-23 24-Sep-23, Pre Construction Works 134 09-May-23 24-Sep-23 24-Sep-23, Structure Works 14 09-May-23 22-May-23 120 23-May-23 24-Sep-23 28 09-May-23 06-Jun-23 14 09-May-23 22-May-23 Contractual Requirements Contractor Preliminaries Temporary Works MAF0013 Recurring Works MAF2670 MAF2680 Pre Construction Works Structure Works MAF0058 Preparation of Material Submission and Shop Drawing MAF0088 Rebar Fabrication (Cut and Bend) Architecture Works MAF1210 Preparation of Material Submission and Shop Drawing MAF1220 Approval of Material Submission and Shop Drawing MEP Works 14 23-May-23 06-Jun-23 113 09-May-23 02-Sep-23 MAF2230 Preparation of Material Submission and Shop Drawing 14 09-May-23 22-May-23 MAF2240 Approval of Material Submission and Shop Drawing 14 23-May-23 06-Jun-23 Water C ooled Chille rs 85 07-Jun-23 60 07-Jun-23 02-Sep-23 07-Aug-23 MAF3040 Water Pumps 45 27-Jun-23 12-Aug-23 MAF3050 Air Handling Units 60 17-Jun-23 17-Aug-23 MAF3060 Fan coils 45 08-Jul-23 22-Aug-23 MAF3070 Cooling Tower 45 13-Jul-23 27-Aug-23 MAF3080 Exhaust Fan 60 27-Jun-23 27-Aug-23 MAF3090 Cleanroom Wall Panel 45 13-Jul-23 27-Aug-23 MAF3100 Control Panel 45 13-Jul-23 27-Aug-23 MAF3110 Ice Flake Maker 45 13-Jul-23 27-Aug-23 MAF3120 Heat Exchanger 60 27-Jun-23 27-Aug-23 MAF3130 Roller Shutter 60 27-Jun-23 27-Aug-23 MAF3140 Fire rated door 60 27-Jun-23 27-Aug-23 MAF3150 Stainless Steel Tank 60 27-Jun-23 27-Aug-23 MAF3160 Air Compressor 30 29-Jul-23 27-Aug-23 MAF3170 Water Tank 60 03-Jul-23 02-Sep-23 MAF3180 Genset 30 07-Jun-23 07-Jul-23 MAF3190 Doors and Windows 30 17-Jun-23 17-Jul-23 MAF3200 Piping 30 27-Jun-23 28-Jul-23 Construction Works 217 11-May-23 21-Dec-23 Production Building 178 11-May-23 10-Nov-23 18 16-May-23 7 16-May-23 02-Jun-23 22-May-23 Long Lead Items MAF3030 Demolition works MAF2690 Existing ramp MAF2700 Existing perimeter drain 4 18-May-23 21-May-23 MAF2710 Existing apron slab 7 18-May-23 24-May-23 MAF2720 Existing floor slab, incl. thawing area, FFA room and ante room 3 12 18-May-23 29-May-23 MAF2730 Chipping away the existing Epoxy floor in Cold room 4 21-May-23 24-May-23 MAF2740 Repair the existing floor and ceiling to lay new finishing coat 4 30-May-23 02-Jun-23 151 11-May-23 45 11-May-23 12 14-May-23 14-Oct-23 25-Jun-23 25-May-23 Structure Works Sub- Structure MAF3240 Excavation MAF3250 Pilling Works 20 11-May-23 30-May-23 MAF3260 Pilling cutting and Pile Head works 10 26-May-23 04-Jun-23 MAF3270 Pile Caps 20 06-Jun-23 25-Jun-23 Ground beam 108 03-Jun-23 53 03-Jun-23 30 03-Jun-23 23-Sep-23 28-Jul-23 04-Jul-23 MAF2760 Ground Slab 30 17-Jun-23 17-Jul-23 MAF2800 Column Ground to Level 1 20 08-Jul-23 28-Jul-23 Reinforced concrete Works Ground Level MAF2750 Actual Work Milestone Remaining Work Summary Critical Remaining Work 14-Sep-23, Contractor Preliminaries 28-May-23, Temporary Works 14-Sep-23, Recurring Works 06-Jun-23, Architecture Works 02-Sep-23, MEP Works 02-Sep-23, Long Lead Items 21-Dec-23, Construction Works 10-Nov-23, Production Building 02-Jun-23, Demolition works 14-Oct-23, Structure Works 25-Jun-23, Sub- Structure 23-Sep-23, Reinforced concrete Works 28-Jul-23, Ground Level Tender Programme Final Submission (19 April 2023) Page 1 of 2 MAFIPRO CENTRAL FISH PROCESSING PLANT (CFPP) Lot 103, Jalan Perusahaan Tiga Kamunting, Industrial Estate, Perak, 34600 Kamunting, Malaysia Activity ID Activity Name 1st Level MAF2770 Original Start Duration Finish 1st Level beam 45 24-Jul-23 25 24-Jul-23 07-Sep-23 17-Aug-23 MAF2780 1st Level Slab 25 03-Aug-23 27-Aug-23 MAF2790 Column Level 1 to Roof 20 18-Aug-23 07-Sep-23 Roof Slab 15 08-Sep-23 15 08-Sep-23 23-Sep-23 23-Sep-23 Metal Work MAF2820 Main steel structure 30 13-Sep-23 30 13-Sep-23 14-Oct-23 14-Oct-23 Staircase & Ramp MAF2830 Staircase & Ramp 45 18-Aug-23 45 18-Aug-23 04-Oct-23 04-Oct-23 Roof Level MAF2810 Architecture Works MAF2840 Masonry works 85 08-Aug-23 40 08-Aug-23 03-Nov-23 18-Sep-23 MAF2850 Door,gla zing, windows and louvers 30 23-Aug-23 23-Sep-23 MAF2860 Floor Finishing 35 28-Aug-23 04-Oct-23 MAF2870 Wall Finishing 45 28-Aug-23 14-Oct-23 MAF2880 Sanitary Ware 45 08-Sep-23 24-Oct-23 MAF2890 Ceiling 50 13-Sep-23 03-Nov-23 Electrical Works 95 05-Aug-23 60 05-Aug-23 10-Nov-23 06-Oct-23 MAF2910 Plumbing & Sanitary Pipings 55 20-Aug-23 16-Oct-23 MAF2920 Building Chiller Water System 60 20-Aug-23 21-Oct-23 MAF2930 Waste Water Pipeline & City Water Supply 60 25-Aug-23 26-Oct-23 MAF2940 Compressor Air Piping 45 15-Sep-23 31-Oct-23 MAF2950 Fire Fighting 55 15-Sep-23 10-Nov-23 Mechanical Systems - Efrigeration equipment, Compressors, Condensers, and Evaporators 50 15-Aug-23 30 15-Aug-23 06-Oct-23 14-Sep-23 MAF3220 Electrical Systems - The power distribution systems 25 30-Aug-23 25-Sep-23 MAF3230 Plumbing Systems- drainage and water supply systems 25 10-Sep-23 06-Oct-23 50 18-Aug-23 09-Oct-23 MEP Works MAF2900 Cold Room MAF3210 Infrastructure works MAF2960 RC Manhole 20 18-Aug-23 07-Sep-23 MAF2970 Premeter drain & Cover 25 23-Aug-23 18-Sep-23 MAF2980 RC wall sump 25 03-Sep-23 29-Sep-23 MAF2990 Septic, Oil/ grease trap & retaining tanks 45 23-Aug-23 09-Oct-23 Testing & Commissioning and as-Built Drawings MAF3000 As-Built Drawing MAF3010 Testing & Commissioning Signing Taking-over Certificate & Handover MAF3020 Signing Taking-over Certificate & Handover Actual Work Milestone Remaining Work Summary Critical Remaining Work 2023 Mar 135 21-Jul-23 07-Dec-23 120 21-Jul-23 22-Nov-23 25 11-Nov-23 07-Dec-23 14 08-Dec-23 21-Dec-23 14 08-Dec-23 21-Dec-23 Apr May Jun Jul Aug Sep 07-Sep-23, 1st Level Oct Nov Dec 2024 Jan 23-Sep-23, Roof Level 14-Oct-23, Metal Work 04-Oct-23, Staircase & Ramp 03-Nov-23,Architecture Works 10-Nov-23, MEP Works 06-Oct-23, Cold Room 09-Oct-23, Infrastructure works 07-Dec-23, Testing & Commissioning and as-Built Drawings 21-Dec-23, Signing Taking-over Certificate & Handover Tender Programme Final Submission (19 April 2023) Page 2 of 2