THE PROPOSED BONGOLAND FLATS REFURBISHMENT PRELIMINARY PROJECT IMPLEMENTATION PROGRAMME 06th March 2023 Date 24/03/2023 • Submission by Architect of Municipal Approval Drawings including Proforma Invoice for Plan Inspection Fees to NRZCPF for actioning 16/05 – 20/05/2023 • Submission of Drawings to Victoria Falls City Council for Building Plan Approval by MIPF 01/06/2023 • Issue of Tender Documents and Drawings to Bidders through NRZCPF 09/06/2023 • Compulsory Site Visit (Bidders) 29/06/2023 • Tender Return to NRZCPF 04/07 – 14/07/2023 • Adjudication and Preparation of Adjudication Report by Quantity Surveyor 17/07 – 24/07/2023 • Submission by Quantity Surveyor of Adjudication Report to NRZCPF for consideration 24/07/2023 • Appointment of Contractor and Subcontractors • Site Establishment and Mobilisation 31/07/2023 • Commencement of Construction 30/05/2024 • Completion / Handover of Project