Uploaded by Tafadzwa Chagwiza

Preliminary Project Implementation Programme 06-03-2023 (002)

advertisement
THE PROPOSED BONGOLAND FLATS REFURBISHMENT
PRELIMINARY PROJECT IMPLEMENTATION PROGRAMME
06th March 2023
Date
24/03/2023
• Submission by Architect of Municipal Approval Drawings including
Proforma Invoice for Plan Inspection Fees to NRZCPF for actioning
16/05 – 20/05/2023
• Submission of Drawings to Victoria Falls City Council for Building Plan
Approval by MIPF
01/06/2023
• Issue of Tender Documents and Drawings to Bidders through NRZCPF
09/06/2023
• Compulsory Site Visit (Bidders)
29/06/2023
• Tender Return to NRZCPF
04/07 – 14/07/2023
• Adjudication and Preparation of Adjudication Report by Quantity
Surveyor
17/07 – 24/07/2023
• Submission by Quantity Surveyor of Adjudication Report to NRZCPF
for consideration
24/07/2023
• Appointment of Contractor and Subcontractors
• Site Establishment and Mobilisation
31/07/2023
• Commencement of Construction
30/05/2024
• Completion / Handover of Project
Download