Third Party Inspection Agency for Jal Jeevan Mission, Quality Control, Technical Inspection and Evaluation of Construction works in Haridwar District, Uttarakhand for various Water Supply Schemes MONTHLY PROGRESS REPORT MONTH: June -2023 (5th) Report No: TUV/ UK SWSM/DWSM /MPR/26/HARIDWAR Report Date: 10/07/2023 Implementing Agency: -UJS, Haridwar. S. No. Name of Scheme Cost Block 1. Padaratha urf Dhanpura 432.87Lacs. Bahadrabad 2. Anneiki hetanpur 430.13Lacs. Bahadrabad 3. Kota muradnagar 425.06 Lacs Bahadrabad 4. Sarai 396.78 Lacs. Bahadrabad 5. Nenhera anantpur 387.41 Lacs. 6. Daulatpur bhudwa 384.35 Lacs. 7. Nagla thaska 241.57 Lacs 8. Dada patti 236.71 Lacs Bhagwanpur 9. Suthari nehandpur 221.31 Lacs Laksar 10. Mubarakpur alipur 207.14 Lacs Laksar 11. Khedli 197.50 Lacs Bahadrabad 12. Katarpur alipur 195.50 Lacs Bahadrabad 13. Jaspur Chamaria 193.81 lacs Bahadrabad 14. Shahpur sitlakhera 193.42 Lacs Bahadrabad 15. Hasnawala 187.52 Lacs Bhagwanpur 16. Aurangabad 180.09 Lacs Bahadrabad 17. Mubarikpur alipur 178.36 Lacs 18. Sisona 175.82 lacs 19. Ibrahimpur deh 177.96 Lacs Bhagwanpur Bhagwanpur Page No. 20. Beldi salhapur 177.48 Lacs 21. Sajanpur peeli 153.53 Lacs Bahadrabad 22. Shyampur nauragabad 150.17 Lacs Bahadrabad 23. Sadhauli 24. Peetpur 142.67 Lacs Laksar 25. Rohalki dayalpur 139.41 Lacs Bhagwanpur 26. Raipur darera 134.28 Lacs Bahadrabad 27. Subhashgarh 132.15 Lacs Laksar 28. Raheempur 130.74 Lacs 29. Kanpur kasauli 116.71 Lacs 30. Lawwa 105.80 Lacs Bhagwanpur 31. Gin mohmad 104.63 Lacs Bhagwanpur 32. Hasanpur madanpur 104.63 lacs Bhagwanpur 33. Bhurni khatirpur 104.3 Lacs Laksar 34. Alipur ebrahimpur 60.71 Lacs 35. Tanda bhanera 39.02 Lacs 36. Bahadarpur jatt 29.03 Lacs Bahadrabad I. Scheme: Padartha Urf Dhanpura Water supply Scheme. Block- Laksar. General information Name of scheme/sub scheme Name of DIA Sanctioned cost(InRs.) Contract bond cost(in Rs.) Date of Start Date of completion Physical progress ( in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail NOTE:Work is stopped due to land dispute. Padartha Urf Dhanpura Pumping water supply scheme. (134 EE/JJM/2022-23) MD UJS 432.87Lacs. 408.82 Lacs. 01-07-2022 30-06-2023 40% 34% Sh. Parvej Sh. Pervez Pumping. 1st visit@ June-23 No Running. - Physical Progress S.No. Item 1 OHT 2 Pipeline work 3 FHTC Proposed Quantity as per contract bond Total quantity Executed till date Executed This month 02 01 0 26973 2118 Remarks Work is stopped Work is stopped Work is stopped Scope of work /Description of works S. No Item Details ZONE-I Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. Comment regarding quality of work Construction of Boundary wall Rmt. MS Gate Excavation in soil mixed with shingle boulders etc. MSERW pipe 100 mm D.I. Sluice/ Gate Valve 80 mm dia Following size of CI/DI DF sluice valves No. Cum. A 1 2 3 4 50 01 30 No 02 50 mm No 01 B 65 mm No 01 7 Chamber No 04 8 OHT 50kl, 18m staging Dismantling of CC pavement 6 9 10 Excavation in pipe line Not provided by DIA 16.20 Mtr. 5 Per Kl Cum Cum 11 Construction of Unreinforced, CC Cum pavement 12 Providing and laying of HDPE pipes A 63 mm Mtr. 13 Not provided by DIA Not provided by DIA 293.97 Not provided by DIA 5291.46 293.97 5037 B 75 mm Mtr. 725 C 90 mm Mtr. 401 D 110 mm Mtr. 2533 E 140 mm Mtr. 746 F 140 mm Mtr 234 G 140 mm Mtr 123 House hold connection No. 1018 ZONE-I Construction of Boundary wall Rmt. Not provided by DIA 40 Not provided by DIA MS Gate No. Excavation in soil mixed with shingle boulders etc. Cum. MSERW pipe 100 mm D.I. Sluice/ Gate Valve 150 mm dia Following size of CI/DI DF sluice valves 01 16.20 Mtr. Not provided by DIA 30 No 02 50 mm No 3 65 mm No 3 Chamber No 08 Per Kl 01 OHT 325kl, 18m staging Dismantling of CC pavement Excavation in pipe line Cum 515.22 Cum 9273.96 Construction of Unreinforced, CC Cum pavement Providing and laying of HDPE pipes 515.22 63 mm Mtr. 11150 75 mm Mtr. 2085 90 mm Mtr. 1070 110 mm Mtr. 714 140 mm Mtr. 861 140 mm Mtr 878 140 mm Mtr 416 House hold connection No. 1100 Physical Measurement checking status as per scope: Not provided by DIA S. No . 1 2. Item Unit OHT Pipeline work No. Mtr. FHTC No. As per tender/co ntract bond Qty. 02 As per actual (MB) %age complet ed Qty. Qty. 40% Remarks about quality 26973 2118 Compliance for last observations reported S. No 1. Item NIL Observations last reported NIL Compliance reported NIL Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per Report Remarks (whether tests are Availabili Conducted as per respective IS code ty approved Status Provision so not) QAP) (yes/No) No Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Not provided by DIA. 1. Design mix report 2. GI pipe (dia. wise) 3. HDPE Pipe 4. MSERW Pipe 5. DI pipe No 6. Cement No 7. Steel No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be 8. Aggregate/ Sand No 9. Bricks No 10. CC Cube No 11. Water test report No conducted as per specifications. Not provided by DIA. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register Site order book : Not provided by DIA. : Not provided by DIA. Test register/Report: Not Provided by DIA. Concrete Register : Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Seapage observed in bottom of tank. Primer not applied on MS gate. Status of OHT at VillGhossipura V. Scheme: Anneiki Hetampur Water supply Scheme. Block- Bhadrabad. General information Name of scheme/subsch0eme Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress (in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Anneiki Hetampur Pumping water supply scheme. (161/E.E/JJM/2022-23) 430.13 Lacs. 371.86 Lacs. 29-08-2022 31-03-2023 15 % 8% Sh. Vishal Yadav Sh. Akhilesh Semwal Pumping. 1stvisit@ March23 NA. Running. - Note:Work is stopped for few months. Physical Progress S.No Item 1. OHT Proposed Quantity as per contract bond Total quantity Executed till date Executed this month I. Zone-1 1.00 5% 5% II. Zone-2 1.00 5% 5% Zone-1 16530m - 2500m Zone-2 7523m - 1500m Zone-1 1117.00 - - Zone-2 491.00 - - 2. 3. Remarks RCC over Head Tank, 300kl, 18m Staging. RCC over Head Tank, 150kl, 18m Staging. Pipeline work Work in progress. Work in progress. FHTC Scope of work /Description of works Work in progress. Work in progress. S. No 1 I. II. III. IV. V VI. VII. 2. 3. 4. Item Details Providing and laying of pipes 63 mm 75 mm 90mm 110mm 140mm 160 mm 180 mm Excavation of pipe line Valves 50&65 mm House hold connection Unit Mtr. Mtr. Mtr Mtr Mtr Mtr Mtr Cubic. M As per DPR proposal Qty. Not provided by DIA As per contract bond Qty. 8975.00 2745.00 1601.00 944.00 455.00 1160.00 650.00 8926.20 Nos 2.00 Nos 1117.00 As per actual (MB) Qty. Comment regarding quality of work Work in progress. Not provided by DIA Work in progress. Work in progress. Work in progress. 5. Road cutting Cum 843.03 6. Roadreinstatement Cum. 843.03 No. 1.00 Work not starts. No. 2.00 Work not started. 7. 9. Electrification of pump house D.I. Sluice/ Gate valve 150 mm Not provided by DIA Not provided by DIA 10. RCC over Head Tank, 300kl, 18m Staging. Per Kl. 300.00 11. 12. Chamber M.S. Gate No. No. 4.00 1.00 Mtr. Mtr. Mtr Mtr Mtr 4485.00 1450.00 1100.00 320.00 168.00 OHT work done upto Raft foundation & found as per drawing & specification. Work not started Work not started Zone – 2nd 13. I. II. III. IV. V. 14. 15. 16. 17. Providing and laying of pipes 63 mm 75 mm 90 mm 110 mm 140 mm Valves 50&65 mm Excavation of pipe line House hold connection Earth work in by mechanical means/ manual means Not provided by DIA Nos Cubic. M Nos Cum. Not provided by DIA Work in progress. 2.00 4062.42 Not provided by DIA 491.00 20.56 Not provided by DIA Work in progress. Work in progress. Work in progress. As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. Comment regarding quality of work S. No Item Details Unit 18. 19. Brick work CC Flooring Construction of boundary wall Excavation in soil mixed with shingle boulders etc. MS ERW pipe 100 mm (5.6 thick) Cum. Sqm. 13.70 41.00 Work not started Work not started Rm. 22.18 Work not started Cum. 24.30 Work in progress. Mtr. 45.00 Work in progress. Road cutting Cum 383.67 Cum. 383.67 20. 21. 22. 23. 24. 25. 26. 27. 1. 31. 32. 33. 34. 35. 37. 38. 39. 40. 41. 42. Road rein statement Electrification of pump house D.I. Sluice/ Gate valve 100 mm RCC over Head Tank, 150kl, 18m Staging. Drilling of borehole 600 mm Pea Gravel Development of TW by 250 PSI/900 CFM Air compressor Development of TW by suitable size of OP unit Geological survey at site Submersible cable 1x3x16 sq.mm C class MS column pipe MSDI clamp set 150 mm Installation of pumping plants and accessories. G.I. Earth plate Chamber MS Gate No. Work in progress. Work in progress. 1.00 Work not started. 2.00 Work not started. Per Kl. 150.00 OHT work done up to Raft foundation & found as per drawing & specification. Per Mtr. 150.00 Work in progress. No. Cum. Hrs. Not provided by DIA 80.00 80.00 Hrs. 80.00 Job. 1.00 Per Mtr. Per Mtr. Not provided by DIA Work not started. Work not started Work not started 100.00 Work not started 42.00 Work not started Set. 2.00 Work not started Job 1.00 Work not started Job No. No. 1.00 2.00 1.00 Work not started Work not started Work not started Physical Measurement checking status as per scope: Unit Item As per tender/co ntract bond Qty. As per actual (MB) %age complet ed Qty. Qty. 1 OHT No. 2.00 - 5% 2. HDPE Pipeline Mtr. 24053m - 5% Remarks about quality OHT work done upto Raft foundation & found as per drawing & specification. OHT work done upto Raft foundation & found as per drawing & specification. Compliance for last observations reported S. No 1. 2. Item OHT OHT Observations last reported The back filling of soil has not been done according to the layer. The back filling of soil has not been done according to the layer. Garbage has been used in back filling the soil. Compliance reported Compliance not done Compliance not done Material testing status (Lab test/MTC) S. No Name of Material (as per scope of work) Make(as Report Per availability Approved QAP) Status (yes/No) 1. Design mix report M-25 & M-30 2. GI pipe (dia. wise) NA No 3. HDPE Pipe NA No 4. MSERW Pipe NA No Yes Remarks (whether tests are Conducted as per respective IS code Provisions or not) Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Test Reports not Submitted Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Test Reports Submitted Test Reports Submitted DI pipe NA No 6. Cement OPC 43Grade MP Birla Yes 7. Steel Sail NA 8. Aggregate/ Sand Yes No 9. Bricks NA No 10. CC Cube NA NA 11. Water test report NA NA 12. NDT test (if any) NA NA 5. Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications.Test Reports not Submitted Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications.Test Reports Submitted As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012 NA Availability of Register on site: Material register Site order book :Not provided by DIA. :Not provided by DIA. Test register/Report :Provided by DIA Concrete Register :Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Work is stopped. M-30 Design mix. Test report by Indian Testing Laboratory. M-25 Design mix. Test report by Indian Testing Laboratory. Cement OPC 43 MP Birla Grade test report from Indian Testing Laboratory. III. Scheme: Kota Muradnagar water Supply scheme. Block- Bhadarabad. General information Kota Muradnagar water supply arrangement and Appurtenant work(78/S.E./JJM/2021-22) 425.06 Lacs Sanctioned cost (InRs.) 400.00Lacs Contract bond cost ( in Rs.) Not provided by DIA Date of Start 13-04-2023 Date of completion 75% Physical progress(in%) 43.16 Financial progress(in%) Sh. Vivek Ravi Name of EE/AE/JE with Contact No. Sh. Akhilesh Semwal Name of TPI Engineer /mobile no. Pumping Type of scheme No Last reported Yes ATR provided till date. Current status of work(Running/completed) Running. Any other detail Name of scheme/ sub scheme Physical Progress S.No Item ProposedQ Totalquanti uantity tyExecutedt aspercontr illdate act bond Executed thismonth Remarks HDPE Pipeline 1. I. Zone -1 9972m II. Zone -2 1327m III. Zone -3 1902m 2. OHT 03 Nos 3. Pump House 01 No. Not provided by DIA 02 Not provided by DIA Work in progress Work in progress 02 01 No. Work in progress 01 No. Scope of work /Description of works S. No 1 Item Details Zone-1 Providing and laying of HDPE pipes Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. Not provided by DIA Comment regarding quality of work S. No I. II. III. IV. V. VI. 2 I. II. III. IV. V. 3. 4 5 6 7 8 Item Details Unit 63 mm 75 mm 90 mm 110 mm 140 mm 160 mm Sluice / Gate Valves 65 mm 80 mm 100 mm 125 mm 150 mm Drilling of borehole 600 mm MSERW fin cut plain pipe 300 mm MSERW fin cut slotted pipe 300 mm Pea Gravel CFM Air compressor Mtr. Mtr. Mtr. Mtr. Mtr. Mtr. 5134.00 1464.00 1391.00 821.00 631.00 531.00 Nos Nos. Nos Nos. Nos. Per Mtr. 1.00 1.00 3.00 2.00 2.00 Geological survey Supply of submersible 1x3x16 sq.mm 10 Supply of aluminium armored cable 35 sq.mm 3.5 core 11 MSDI housing clamp & girder set 300 mm 12 C class MS column pipe 13 MSDI clamp set 80mm 14 G.I Earth plate 15. Earth work in excavation by mechanical means / manual means 16 Brick work As per DPR proposal Qty. Not provided by DIA As per contract bond Qty. As per actual (MB) Qty. Comment regarding quality of work Work in progress Work in progress 130.00 Per m 110.00 Per m 40.00 Cum 80.00 Hrs 80.00 Job 1.00 Work in progress 9 Per m 100.00 Per m 40.00 Set 1.00 Per m 42.00 Set Job Cum Cum 2.00 Not provided by DIA 1.00 20.56 13.70 Work not started. 41.00 Work not started. 17 CC flooring Sqm S. No Item Details 18 Unit As per DPR proposal Qty. As per contract bond Qty. Electrification of pump house No Construction of Boundary wall Rm 50.00 MS gate No 1.00 As per actual (MB) Qty. 1.00 Not provided by DIA 19 20 21 22 23 24 25 26 27 28 I. II. III. IV. 29 I. II. 30 31 32 33 34 35 Excavation in soil mixed with boulders. MSERW pipe 150 mm Chamber RCC over Head Tank, 300 KL OHT staging 18 mtr. Excavation in pipe line Dismantling of CC Pavement Cement concrete Road Zone-2 Providing and laying of HDPE pipes 63 mm 75 mm 90 mm 110 mm Sluice / Gate Valves 80 mm 100 mm Drilling of borehole 600 mm MSERW fin cut plain pipe 200 mm MSERW fin cut slotted pipe 200 mm Pea Gravel CFM Air compressor Supply of submersible Cum 16.20 Mtr 30.00 No 2.00 Per Kl 300.00 Cum 5083.20 Cum 508.32 Cub 508.32 Mtr. Mtr. Mtr. Mtr. Nos. Nos Per Mtr. Per m 782.00 347.00 160.00 38.00 Not provided by DIA 2.00 2.00 150.00 Not 110.00 provided by DIA Per m 40.00 Cum 50.00 Hrs 40.00 Per m 50.00 Comment regarding quality of work Work not started. Work not started. Work not started. Work in progress Work in progress Work in progress S. No Item Details 36 37 38 39 1x3x16 sq.mm Supply of aluminum armo red cable 35 sq.mm 3.5 core C class MS column pipe MSDI clamp set 80mm Earth work in excavation by mechanical means / manual means Unit As per DPR proposal Qty. As per contract bond Qty. Per m 15.00 Per m 42.00 Set As per actual (MB) Qty. 2.00 Cum 20.56 Brick work Cum 13.70 Work in progress Work not started. CC flooring Sqm 41.00 Work not started. Construction of Boundary wall Rm 45.00 Work not started. 40 41 42 43 44 MS gate Excavation in soil mixed with boulders. No Cum 1.00 Not provided by DIA Not 13.50 provided by DIA 45 Chamber 46 47 48 49 50 51 I. II. III. IV. V. 52 Comment regarding quality of work RCC over Head Tank, 100 KL OHT staging 18 mtr. Excavation in pipe line Dismantling of CC Pavement Cement concrete Road House connection Zone-3 Providing and laying of HDPE pipes 63 mm 75 mm 90 mm 110 mm 140 mm Sluice / Gate No 2.00 Per Kl 100.00 Cum 597.15 Cum 53.08 Cub 53.08 No Mtr. Mtr. Mtr. Mtr. Mtr. Work not started. Work in progress Work in progress 150.00 Not provided by DIA Not 1033.00 provided 428.00 by DIA 155.00 200.00 86.00 Not Work in progress Work in progress S. No Item Details Unit Valves I. 80 mm Nos. II. 100 mm Nos III. 100 mm Nos 53 54 55 56 57 58 59 60 61 62 As per DPR proposal Qty. provided by DIA As per contract bond Qty. 2.00 2.00 2.00 Drilling of borehole 600 mm MSERW fin cut plain pipe 200 mm MSERW fin cut slotted pipe 200 mm Pea Gravel CFM Air compressor Supply of submersible 1x3x16 sq.mm Supply of aluminum armored cable 35 sq.mm 3.5 core C class MS column pipe MSDI clamp set 80mm G.I. Earth plate Earth work in excavation by mechanical means / manual means Per Mtr. 150.00 Per m 110.00 Per m 40.00 Cum 50.00 Hrs Per m 40.00 Not provided by DIA 50.00 Per m 15.00 Per m 42.00 Work in progress Work in progress Work in progress 2.00 Job 1.00 Cum 20.56 Brick work Cum 13.7 Work not started. CC flooring Sqm 41.00 Work not started. Construction of Boundary wall Rm 75.00 Work not started. MS gate No 1.00 Work not started. 1.00 Work not started. 64 66 67 68 Comment regarding quality of work Set 63 65 As per actual (MB) Qty. Pump House No. Chamber No Not provided by DIA 2.00 Work not started. S. No Item Details 69 70 71 72 73 Unit RCC over Head Tank, 100 KL OHT staging 18 mtr. Excavation in pipe line Dismantling of CC Pavement Cement concrete Road House connection As per DPR proposal Qty. As per contract bond Qty. Per Kl 100.00 Cum 855.90 Cum 76.08 Cub As per actual (MB) Qty. Not provided by DIA Work in progress Work in progress Work in progress Work in progress Work in progress 76.08 No Comment regarding quality of work 147.00 Physical Measurement checking status as per scope: S. No Item Unit 1 OHT work 250 KL. 18 m STAGING. HDPE pipeline 2. As per actual (MB) %age completed Qty. No. As per tender/co ntract bond Qty. 03 - Qty. 70% Mtr. 17306 - 30% Remarks about quality Work in progress Compliance for last observations reported S. No Item No 1. Observations last reported No Compliance reported No Material testing status (Lab test/MTC) Sl. No 2. Name of Make Report Remarks (whether tests are Materials (as per (As per availability conducted as per respective IS code scope of work) approved status provisions or not) QAP) (yes/No) Yes Tests to be conducted as per IS Design mix report NA (M-25 & M-30) 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications Sl. No 5. Name of Make Report Remarks (whether tests are Materials (as per (As per availability conducted as per respective IS code scope of work) approved status provisions or not) QAP) (yes/No) No Tests to be conducted as per IS 1239 (Part GI pipe (dia .wise) I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 HDPE Pipe (1995) & Frequency of tests to be conducted as per specifications.Not provided by DIA. No Not provided by DIA. MSERW Pipe 6. DI pipe NA NA 7. Cement OPC 43 CCI Grade No 8. Steel 8mm 10mm 12mm 16mm 20mm Aggregate 10 mm 20mm 3. 4. 9. Sail Yes NA Yes Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. NA No Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012NA Not provided by DIA. 10. Bricks 11. CC Cube M-25 Yes 12. Water test report No 13. Development of B/W by O.P. unit & compressor unit NDT test(if any) No 14. Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications.Not provided by DIA. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. NA Availability of Registeron site: Material register :Not maintained at site Site order book :Not available at site. Test register : Not maintained at site Concreting Register : Not maintained at site Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Railing observed damaged. I. Scheme: Sarai Water supply Scheme. Block-Bahadrabad . General information Name of DIA Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress (in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported Sarai Pumping water supply scheme. (156 EE/JJM/2022-23) MD UJS 396.78Lacs. 330.45 Lacs. 18-08-2022 31-03-2023 50% 15% Sh. Parshant kothari Sh. Pervez Pumping. 2nd visit@June-23 ATR provided till date. Current status of work(Running/completed) Any other detail No Running. - Name of scheme/sub scheme Physical Progress S.No. Item 1. Pipeline work 2. FHTC Proposed Quantity as per contract bond 23905 1771 Total quantity Executed till date Executed This month 19000 3000 1400 200 Remarks Work in progress Work in progress Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. ZONE-I 1 2 3 4 5 6 7 Construction of Boundary wall Rmt. MS Gate Excavation in soil mixed with shingle boulders etc. MSERW pipe 150 mm D.I. Sluice/ Gate Valve 150 mm dia Following Size of CI/DI DF sluice valves No. Cum. 50 mm Not provided by DIA Not provided by DIA 13.12 Mtr. No 24.3 Not provided by DIA 02 02 Comment regarding quality of work 8 65 mm 02 9 80 mm 02 10 100 mm 11 Chamber 12 OHT 75kl, 18m staging 13 Dismantling of CC pavement 14 Excavation in pipe line 02 Not provided by DIA 10 No Per Kl Cum 904.76 Cum 7867.5 15 Construction of Unreinforced, CC Cum pavement 16 Providing and laying of HDPE pipes A 63 mm Mtr. 904.76 6776 B 75 mm Mtr. 3089 C 90 mm Mtr. 2452 D 110 mm Mtr. 1458 E 140 mm Mtr. 1409 F 160 mm Mtr. 346 G 180 mm Mtr. 198 13 House hold connection No. 1180 ZONE-II Construction of Boundary wall Rmt. 2 MS Gate No. 3 Excavation in soil mixed with shingle boulders etc. Cum. 1 5 6 D.I. Sluice/ Gate Valve 100 mm dia Following Size of CI/DI DF sluice valves Not provided by DIA 20.41 4 MSERW pipe 150 mm Not provided by DIA Mtr. Not provided by DIA 37.8 No 02 7 50 mm No 02 8 65 mm No 02 Not provided by DIA No 02 10 100 mm No 02 11 Chamber No 10 9 80 mm 12 OHT 75kl, 18m staging 13 Dismantling of CC pavement 14 Excavation in pipe line Per Kl Cum 465 Cum 4043.5 15 Construction of Unreinforced, CC Cum pavement 16 Providing and laying of HDPE pipes A 63 mm Mtr. 4480 465 B 75 mm Mtr. 992 C 90 mm Mtr. 1484 D 110 mm Mtr. 524 E 140 mm Mtr. 549 F 160 mm Mtr. 148 13 House hold connection No. 591 Physical Measurement checking status as per scope: S. No . Item Unit As per tender/co ntract bond Qty. 1. Pipeline work Mtr. 23905 2. FHTC Nos 1771 As per actual (MB) %age complet ed Qty. Qty. 70% Remarks about quality 65% Compliance for last observations reported S. No 1. Item NIL Observations last reported NIL Compliance reported NIL Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per Report Availabili Remarks (whether tests are Conducted as per respective IS code ty approved Status Provision so not) QAP) (yes/No) No Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Apollo No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. Tirupati No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Not provided by DIA. 12. Design mix report 13. GI pipe (dia. wise) 14. HDPE Pipe 15. MSERW Pipe 16. DI pipe No 17. Cement No 18. Steel No 19. Aggregate/ Sand No 20. Bricks No 21. CC Cube No 22. Water test report No Availability of Register on site: Material register Site order book : Not provided by DIA. : Not provided by DIA. Test register/Report: Not Provided by DIA. Concrete Register : Not provided by DIA. Conclusion and Suggestions: Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Not provided by DIA. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Work in progress. I. Scheme:NanheraAnantpurPumping water Supply scheme, Block-Roorkee. Generalinformation NanheraAnantpurPumpingwater supply scheme. 387.41 Lacs. Sanctionedcost (InRs.) NotprovidedbyDIA. Contractbondcost (inRs.) NotprovidedbyDIA. DateofStart NotprovidedbyDIA. Dateofcompletion 80 % Physical progress(in%) 30% Financialprogress(in%) Sh.HimanshuTyagi (A.A.E.) NameofEE/AE/JEwith ContactNo. Sh.HimanshuKaushik. Nameof TPIEngineer/mobileno. Pumpingwater supplyscheme. Typeofscheme 3rdVisit Report. Lastreported Nil. ATRprovidedtilldate. currentstatusofwork(Running/completed Running. ) Nameofscheme/subscheme - Anyotherdetail PhysicalProgress S.N o 1 Proposed Totalquant Quantity ityExecute aspercont d tilldate ractbond Item OHT350KL, 18 mstaging. 01No. - Execute dthismo nth Remarks Work is inprogress up to vertical wall of OHT. Staircase work not started yet. Cubes found at site for raft foundation. Testing not done for raft foundation cubes .Cubes of vertical wall were also not submerged in water which is not as per specifications. As a result , NDT TEST is recommended for the structure. Scopeofwork/Descriptionofworks S.No ItemDetails Unit 1. Providingand layingof pipes 63mm Mtr. 2. 75mm Mtr. 90 mm Mtr. 110 mm Mtr. Excavationof Cum pipeline Asper DPR propos alQty. Asper contract bondQt y. Not provided Notpro vided Not provided Not provided Not provided Notpro vided Not provided Not provided Asper actual (MB)Qty. Comment regarding qualityof work Workin progress.. 3. Valves 80mm Nos. 100mm Nos. 4. Airvalve 25mmdia 5. OHT350KL, 18mstaging. Nos. 6. Nos. 7. 8. 9. House holdconn ection Roadcutting No. cum Road Cum reinstatement Constructiono Each f pumphouse 10. Risingmain Mtr 11. Boundarywall Nos Not provided Not provided Not provided Not provided Not provided Not provided Not provided Not provided Notpro vided Notpro vided Notpro vided Notpro vided Not provided Not provided Not provided Not provided Not provided Not provided Not provided Not provided Notpro vided Notpro vided Staircase work not started yet. Cubes found at site for raft foundation. Testing not done for raft foundation cubes .Cubes of vertical wall were also not submerged in water which is not as per specifications. As a result , NDT TEST is recommend ed for the structure Worknotstarted. Workin progress up to excavation work. Procurement pending. Worknot started. PhysicalMeasurementcheckingstatusasperscope: S. No 1. Item OHT350KL,18 metrestaging Unit No. As pertend er/contr actbond Qty. 01 As perac tual( MB) Qty. Notprov ided %ageco mpleted Remarksabo utquality Qty. 5% Qualityofworkisasp erspecifications. Complianceforlastobservationsreported S. No 1. Item NIL Observationslastreported NIL Compliancereported NIL Materialtesting status(Labtest /MTC) S. Make: Nameof Material Reportav ailability AsPerper approved QAP no Remarks(whether testsare conducted asperrespectiveIScode) 1. Designmix report Yes Yes 2. GIpipe (dia.wise) NA NA 3. HDPEPipe JOSEXIM No 4. DIpipe NA 5. Cement JK Super Yes 6. Steel TATA Yes 7. Aggregate Yes Yes 8. Bricks Yes Yes 9. CC Cube Yes No 10. Watertestreport Yes No NA Tests to be conducted as per IS10262:2009andIS456:200 0& Frequencyofteststobeconducteda sperspecifications. TeststobeconductedasperIS1239 (Part I):2004&IS:10748:2004with Amnd-5,Grade2 TestsconductedasperISCodeIS498 4(1995) &Frequencyof tests to be conductedasperspecifications. TestsconductedasperISCode IS8329 &Frequencyofteststobeconductedas perspecifications. TestsconductedasperISCodeIS 8182:2013 & Frequency of tests to beconductedas per specifications. TestsconductedasperISCodeIS 1786:2008 & Frequency of tests to beconductedas per specifications. TestsconductedasperISCodeIS 383:2016&Frequencyofteststobe conductedas per specifications. TestsconductedasperISCode 1077:1992 & Frequency of tests to beconductedas per specifications. As per IS Code IS 10086:1982 &Frequencyofteststobeconducted as perIS456:2000. TestreportnotprovidedbyDIAandt eststo beconducted asperIS 10500:2012 11. NDTtest(ifany) NA NA NA Availabilityof Registeronsite: Material register :Not provided by DIA.Siteorderbook :Not provided by DIA.Testregister provided by :Not DIA.ConcretingRegister:Not providedbyDIA, ConclusionandSuggestions: - Batch Report no. to be provided in the HDPE Pipe Available at site as per Test reportssubmitted . NDT test is recommended for the structure as post testing date cubes found at site. Staircase work not started till date. No safety taken at site. Bamboo scaffolding used at site . JOSEXIM HDPE Pipe used at site and in test report provided ,make of pipe is JOSS polymers. Backfilling should be done in layers and proper compaction should be done in mechanicalmeans. Note: All concrete mixers to be attached with Weigh Batcher machine and volumetricconcretearenot acceptable. PhotographsofInspection Comment s Site visit at OHT. OHT work done upto vertical wall. JK Super OPC 434 Grade cement used at site. 1.Backfilling work not started till date. Staircase work is in progress without any safety precautions. Coarse sand aggregate stock at site. JOSE XIM” make HDPE pipes found at site. Test report provided by DIA, Make of pipe in test report is JOSS POLYMERS. 63mm HDPE pipes 75mm HDPE pipes 90mm HDPE pipes 7dayscubetestreportfromexternallabfor OHTraft foundation. 7dayscubetestreportfromexternallabfor OHT1st lift columns. 8mmsteeltestreportfromexternal lab. 10mmsteeltestreportfromexternal lab. 12mmsteeltestreportfromexternal lab. 16mmsteeltestreportfromexternal lab. 20mmsteeltestreportfromexternal lab. Bricktestreportfromexternallab. Fineaggregatetestreport fromexternallab. Cementtestreportfrom externallab. 10mmcoarseaggregatetestreportfro mexternallab. 20mmcoarseaggregatetestreportfro mexternallab. M-25designmix. M-30designmix. I. Scheme:Daulatpur Bhudhwa Water supply Scheme. Block-Bahadrabad . General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost ( in Rs.) Date of Start Date of completion Physical progress (in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Daulatpur Bhudhwa Pumping water supply scheme. (155 EE/JJM/2022-23) MD UJS 384.35Lacs. 345.22 Lacs. 18-08-2022 31-03-2023 25% 13.5% Sh. Vivek Ravi Sh. Pervez Pumping. 2nd visit @June-23 NA. Running. - Physical Progress S.No. Item 1. Pipeline work 2. FHTC 3. OHT 4. Pump House Proposed Quantity as per contract bond 15397 1182 02 02 Total quantity Executed till date Executed This month 0 - 0 - 01 01 0 0 Remarks Work not started Work not started Work in progress Work not started Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. ZONE-I 1 Following Size of CI/DI DF sluice valves A 50 mm No B 65 mm No C 125 mm No D 150 mm No 01 2 Chamber No 08 01 Not provided by DIA 04 01 Not provided by DIA Comment regarding quality of work 3 Dismantling of CC pavement Cum 337.76 4 Excavation in pipe line Cum 2649.12 5 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes Cum 337.76 6 A 63mm Mtr. 2460 B 75mm Mtr. 149 C 90 mm Mtr. 218 D 110mm Mtr. 128 E 140mm Mtr. 2085 F 160mm Mtr. 479 7 125KL OHT Staging 18m No. 8 House hold connection No. 321 Pump House No. 01 9 01 ZONE-2 1 Following Size of CI/DI DF sluice valves A 50 mm No 07 B 65 mm No 04 C 80 mm No 01 D 100 mm No 03 E 125 mm No 01 F 150 mm No 01 2 Chamber No 16 3 Dismantling of CC pavement Cum 604.53 4 Excavation in pipe line Cum 4741.44 5 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes Cum 604.53 6 A 63mm Mtr. 6113 B 75mm Mtr. 925 C 90 mm Mtr. 743 D 110mm Mtr. 1022 E 160mm Mtr. 1075 7 75KL OHT Staging 18m No. 8 House hold connection No. 861 Pump House No. 01 9 01 Physical Measurement checking status as per scope: S. No . Item Unit As per tender/co ntract bond Qty. As per actual (MB) %age complet ed Qty. 0 - 1. Pipeline work Mtr. 15397 Qty. 0 2. FHTC Nos 1182 0 0 3 OHT Nos 02 0 30% 4 Pump House Nos 02 0 0 Remarks about quality Work in progress - Compliance for last observations reported S. No 1. Item Observations last reported Compliance reported NA NA NA Material testing status (Lab test/MTC) S. No. 23. 24. 25. 26. Name of Material Make as (as per scope of work) Per Report Remarks (whether tests are Availabili Conducted as per respective IS code ty Approved Status Provision so not) QAP) (yes/No) M-25 & M- Yes Tests to be conducted as per IS 10262:2009 Design mix report 30 and IS 456: 2000 & Frequency of tests to be conducted as per specifications.(Reports Submitted) No Tests to be conducted as per IS 1239 (Part GI pipe 15mm Dia I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 HDPE Pipe-90 mm (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. Tests to be conducted as per IS 4270:2001 MSERW Pipe-7.9mm Jindal Hissar Yes Frequency of tests to be conducted as per specifications.(Report Submitted) No 27. DI pipe 28. Cement OPCYes 43Grade(Bir la Uttam) 29. Steel 30. Aggregate/ Sand SAIL(8mm, Yes 10mm,12m m,16mm & 20mm) Course Yes sand,10mm &20mm 31. Bricks No 32. CC Cube No 33. Water test report No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications.(Report submitted) Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. (Report submitted) Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications.(Report submitted) Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register : Not Available at site. Site order book : Not Available at site. Test register/Report : Available at site. Concrete Register : Available at site. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Access not provided to reach at working spot Birla Uttam cement is being used at site. Make of steel is “SAIL”. II. Scheme: NaglaThaskaPumping water Supply scheme. Block- Narsan.Generalinformation NaglaThaskapumpingwatersupply scheme(97/E.E./JJM/2022-23) 241.57Lacs. Sanctionedcost(InRs.) 230.76Lacs. Contractbondcost(inRs.) 12-05-2022. DateofStart 11-05-2023. Dateofcompletion 80% Physical progress(in%) 80% Financialprogress(in%) Sh.HimanshuTyagi. NameofEE/AE/JEwith Contact No. Sh.HimanshuKaushik, AdityaThapliyal NameofTPIEngineer/mobileno. PumpingWaterSupplyScheme. Typeofscheme 4th visit report Lastreported Not provided till date ATRprovidedtilldate. current statusofwork(Running/completed) Running . Anyotherdetail Nameofscheme/subscheme PhysicalProgress S.No 1 2 Proposed Quantityasper contractbond Item OHT250KL,18m Staging Pumphous e Executed thismont h Totalquan tityExecut edtilldate 01No. 01No. - 01No 0 - Remarks Workisin progress. Workis in progress. Scopeofwork/Descriptionofworks S.No ItemDetails 1. 2. 3. Providingand layingof pipes 63 mm 75 mm 90 mm 110 mm 140 mm 160 mm Excavationof pipeline Valves 50 mm 65 mm Unit Mtr. Mtr. Mtr. Mtr. Mtr. Mtr. Cubic. M Nos. Nos. As perD PR propos alQty. As percontract bondQty. As peractual (MB)Qty. Commentre gardingquali tyofwork Notprovid ed byDIA. Work is inprogress. Depth found asperspecifi cations. 6389 443 249 409 1127 283 6389 443 249 409 1127 283 20.56 20.56 Workisin progress. 10 02 10 02 Worknot S.No ItemDetails 4. 5. 6. Unit 80 mm 100mm 125mm 150 mm Airvalve Nos Nos. Nos. Nos. Nos. 25mmdia Household connection Nos Roadcutting Cum As perD PR propos alQty. 01 01 02 01 As percontract bondQty. 01 01 02 01 02 02 968 96 8 702.19 702.19 702.1 9 702.1 9 01 01 7. 8. Roadreinst atement Cum. Tubewell Job 9. Pumpingplant Each 01 01 10. Servovoltage Job stabilizer Electrification 01 01 01 01 01 01 11. oftube well & Job pumphouse As peractual (MB)Qty. Commentre gardingquali tyofwork started. Worknotstarted . Workisin progress. Workisin progress. Hydrostatic testingistobe done beforesta rting reinstatement work. Workisin progress. Not Worknotstarted provided by . Worknotstarted DIA. . Worknotstarted . 12. Construction ofpumphous e 13. RCCover Head Tank,250K LOHT staging18 mtr. Each Workis in progress. OHT work is completed. Each 01 01 Mtr 30 30 Worknotstarted . Boundarywall Mtr. 60 60 Workis completed. . 14. Risingmain 15. Complianceforlastobservationsreported S. No Item Observationslastreported NIL 1. NIL Compliancereported NIL Materialtesting status(Labtest /MTC) Sl.N o Name Make(A ofMaterials (as sper perscopeofwor approve k) dQAP) Reportav ailability status( yes/No ) Yes 1. Designmixreport Yes 2. GIpipe(dia. wise) NA NA 3. HDPEPipe Tirupati Yes 4. DIpipe NA NA 5. Cement BirlaUttam Yes 6. Steel SAIL Yes 7. Aggregate Yes No 8. Bricks Yes No Remarks (whether tests areconductedasperrespectiveIS codeprovisionsor not) Tests to be conducted as per IS10262:2009andIS456:200 0& Frequencyofteststobeconducteda sperspecifications. NA Tests to be conducted as per IS 1239(Part I):2004&IS:10748:2004with Amnd-5,Grade2NA Tests conducted as per IS Code IS4984(1995)&Frequencyoftests to beconducted asperspecifications. TestsconductedasperISCodeI S8329 &Frequencyof tests tobe conductedasperspecifications.NA Tests conducted as per IS Code IS8182:2013&Frequencyofteststo be conductedasperspecifications. Tests conducted as per IS Code IS1786:2008&Frequencyofteststo be conductedasperspecifications. Tests conducted as per IS Code IS383:2016&Frequencyofteststo beconductedas perspecifications. Reportsnot provided. Testsconductedas per ISCode1077:1992 & Frequency of tests to beconductedas per specifications. Reportsnotprovided. Yes 9. CC Cube 10. Watertestreport NA Yes As per IS Code IS 10086:1982 &Frequencyofteststobeconducted asper IS 456:2000. NA Testreportnot providedbyDIAand teststobeconductedasperI S10500:2012NA 11. NDTtest(ifany) NA NA NA Availabilityof Registeronsite: Material register : Not provided by DIA.Siteorderbook :Not provided by DIA.Testregister :Not provided by DIA.ConcreteRegister:Not provided byDIA. ConclusionandSuggestions: - Itisrecommendedtomaintainalltestregistersat site. - Allmaterial test reports tobe provided byDIA. beforeanyconcretingwork. - Note: All concrete mixers to be attached with Weigh Batcher machine and volumetric concreteisnot acceptable. PhotographsofInspection Comments SitevisitatOHT. Boundary wall brickwork in progress. Balcony slab checked and found as per drawing and specification. Bottom dome reinforcement checked and found as per drawing and specification. Bottom dome reinforcement checked and found as per drawing and specification. SAIL steel used at site. Drawing for OHT. “Birla Uttam” OPC 43 Grade cement used at site. MSERW pipefactorytestreport. HDPEpipeinspectionreportfromcr ownagents. M-25Designmix fromexternallab. M-25Designmix fromexternallab. Watertestreport fromexternallab. Steel20mmdia.testreportfromexte rnallab. Steel16mmdia.testreportfromexte rnallab. Steel12mmdia.testreportfromexte rnallab. Steel10mmdia.testreportfromexte rnallab. Cementtestreportfrom externallab. M-30Designmix. CubetestreportforRaftfoundationf romexternallab. CubetestreportforOHTcolumnsf romexternallab. Specificliftofcolumnforwhichcubes arebeingtested isnot mentionedin thereport. CubetestreportforOHTcolumnsfrom externallab. Cube test report for OHT 1st brace fromexternallab. Cube test report for OHT 1st brace fromexternallab. CubetestreportforOHT2ndbracefrome xternallab. OHT container wall 28 days test report from external lab. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page8 1of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT I. Scheme:Dada Patti Water supply Scheme. Block-Bhagwanpur . General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress (in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Dada Patti Pumping water supply scheme. (85EE/JJM/2022-23) MD UJS 236.71 Lacs 222.09 Lacs. 29-04-2022 28-04-2023 10% 0% Sh.Vivek Ravi Sh. Pervez Pumping. 1st visit @June-23 NA. Running. - Note:Work is stopped Physical Progress S.No. Item 1. Pipeline work 2. FHTC Proposed Quantity as per contract bond Total quantity Executed till date Executed This month Remarks Work is stopped Work is stopped 12538 886 Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. 1 Following Size of CI/DI DF sluice valves A 50 mm No B 65 mm No C 80 mm No D 100 mm No 01 E 125 mm No 01 D 150 mm No 04 19 Not provided by DIA 01 01 As per Comment actual regarding (MB) quality of work Qty. Not provided by DIA Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page8 2of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT F 200 mm No 01 G Air valve-25mm dia No 02 2 Chamber No 30 3 Dismantling of CC pavement Cum 799.97 4 Excavation in pipe line Cum 6856.92 5 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes Cum 799.97 6 A 63mm Mtr. 9353 B 75mm Mtr. 785 C 90 mm Mtr. 757 D 110mm Mtr. 323 E 140mm Mtr. 681 F 180mm Mtr 639 8 House hold connection No. 886 9 Pump House No. 01 Physical Measurement checking status as per scope: S. No . Item Unit As per tender/co ntract bond Qty. 1. Pipeline work Mtr. 12538 2. FHTC Nos 886 As per actual (MB) %age complet ed Qty. Qty. 60% Remarks about quality - 70% Compliance for last observations reported S. No 1. Item Observations last reported Compliance reported NA NA NA Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per Report Availabili Remarks (whether tests are Conducted as per respective IS code Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page8 3of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT ty Approved Status Provision so not) QAP) (yes/No) M-25 & M- No Tests to be conducted as per IS 10262:2009 30 and IS 456: 2000 & Frequency of tests to be conducted as per specifications.(Reports Submitted) No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Tests to be conducted as per IS 4270:2001 Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. 34. Design mix report 35. GI pipe 15mm Dia 36. HDPE Pipe-90 mm 37. MSERW Pipe 38. DI pipe 39. Cement 40. Steel 41. Aggregate/ Sand No 42. Bricks No 43. CC Cube No 44. Water test report No Availability of Register on site: Material register : Not Available at site. Site order book : Not Available at site. Test register/Report : Not Available at site. Concrete Register : Not Available at site. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page8 4of77 Conclusion and Suggestions: TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page8 5of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Make of HDPE pipe is “STAR”. I. Scheme: Suthari Nehandpur pumping Water supply Scheme. Block- Laksar. General information Name of scheme/sub scheme Name of DIA Sanctioned cost(In Rs.) Contract bond cost(in Rs.) Date of Start Date of completion Sutheri Nehandpur Pumping water supply scheme. (108 EE/JJM/2022-23) MD UJS 221.3Lacs. 201.52 Lacs. 25-05-2022 24-05-2023 Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page8 6of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 30% Physical progress(in%) 19.62% Financial progress(in%) Sh. Name of EE/AE/JE with Contact No. Sh. Akhilesh Semwal Name of TPI Engineer/mobile no. Pumping. Type of scheme 1st visit @June-23 Last reported No ATR provided till date. Running. Current status of work(Running/completed) Any other detail Note:Work is stopped for few months. Physical Progress S.No. 1 2 3 4 Item Proposed Quantity as per contract bond Total quantity Executed till date Executed This month Remarks 01 OHT 150kl, 18m staging OHT 10kl, 10m staging Pipeline work FHTC 01 9938 570 Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. ZONE-I Construction of Boundary wall Rmt. MS Gate Excavation in soil mixed with shingle boulders etc. MSERW pipe 100 mm D.I. Sluice/ Gate Valve 80 mm dia Following size of CI/DI DF sluice valves No. Cum. A 50 mm No B 65 mm No D 80 mm No 01 E 100 mm No 01 F 125 mm No 01 G 150 mm No 01 1 2 3 4 5 6 Not provided by DIA 50 01 Not provided by DIA 16.2 Mtr. 30 No 01 Not provided by DIA 12 02 Not provided by DIA Comment regarding quality of work Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page8 7of77 7 Chamber 8 OHT 150kl, 18m staging Dismantling of CC pavement 9 10 Excavation in pipe line TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT No 19 Per Kl 01 Cum 395.55 Cum 4219.2 11 Construction of Unreinforced, CC Cum pavement 12 Providing and laying of HDPE pipes A 63 mm Mtr. 13 395.55 6352 B 75 mm Mtr. 811 C 90 mm Mtr. 440 D 110 mm Mtr. 1077 E 140 mm Mtr. 35 F 160 mm Mtr 75 House hold connection No. 554 ZONE-II Construction of Boundary wall Rmt. MS Gate No. Excavation in soil mixed with shingle boulders etc. Cum. MSERW pipe 100 mm D.I. Sluice/ Gate Valve 150 mm dia Following size of CI/DI DF sluice valves Not provided by DIA 50 01 16.20 Mtr. Not provided by DIA 30 No 01 50 mm No 03 Chamber No 04 Per Kl 01 OHT 10kl, 10m staging Dismantling of CC pavement Excavation in pipe line Not provided by DIA Cum 51.86 Cum 551.04 Not provided by DIA Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page8 8of77 Construction of Unreinforced, CC Cum pavement Providing and laying of HDPE pipes TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 51.66 63 mm Mtr. 1148 House hold connection No. 16 Physical Measurement checking status as per scope: S. No . Item Unit 1 2 3. OHT 150kl, 18m staging OHT 10kl, 10m staging Pipeline work No. No. Mtr. 4 FHTC No. As per tender/co ntract bond Qty. 01 01 As per actual (MB) %age complet ed Qty. Qty. Remarks about quality 9938 570 Compliance for last observations reported S. No 1. Item NIL Observations last reported NIL Compliance reported NIL Material testing status (Lab test/MTC) 45. Design mix report 46. GI pipe (dia. wise) 47. HDPE Pipe 48. MSERW Pipe Report Remarks (whether tests are Availabili Conducted as per respective IS code ty approved Status Provision so not) QAP) (yes/No) M-30 & No Tests to be conducted as per IS 10262:2009 M-25 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Yes No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. Yes No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. Yes No Not provided by DIA. 49. DI pipe Yes S. No. Name of Material Make as (as per scope of work) Per No Tests conducted as per IS Code IS 8329 & Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page8 9of77 50. Cement 51. Steel 52. Aggregate/ Sand 53. Bricks 54. CC Cube 55. Water test report TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Frequency of tests to be conducted as per specifications. OPC No Tests conducted as per IS Code IS 43Grade 8182:2013 & Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Not provided by DIA. Yes No Tests conducted as per IS Code IS (10mm&20 383:2016 & Frequency of tests to be mm) conducted as per specifications. No Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. No As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA No Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register Site order book : Not provided by DIA. : Not provided by DIA. Test register/Report: Not Provided by DIA. Concrete Register : Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page9 0of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Make of HDPE pipe is “JOSEXIM”. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page9 1of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Work is stopped. Work is stopped. I. Scheme:Mubarakpur Alipur Water supply Scheme. Block-Laksar . Generalinformation Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page9 2of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Mubarakpur Alipur Pumping water supply Name of scheme/sub scheme scheme. (85EE/JJM/2022-23) MD UJS Name of DIA 207.14 Lacs Sanctioned cost(InRs.) 150.50 Lacs. Contract bond cost(in Rs.) 25-06-2022 Date of Start 24-06-2023 Date of completion % Physical progress(in%) % Financial progress(in%) Sh. Name of EE/AE/JE with Contact No. Sh. Pervez Name of TPI Engineer/mobile no. Pumping. Type of scheme 1st visit @June-23 Last reported NA. ATR provided till date. Running. Current status of work(Running/completed) Any other detail Note:Work not started yet. Physical Progress S.No. Item 1. 2. Pipeline work FHTC Proposed Quantity as per contract bond Total quantity Executed till date Executed This month Remarks 8138 494 Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. ZONE-1 1 Following Size of CI/DI DF sluice valves A 50 mm No 01 B 65 mm No 01 C 80 mm No D 100 mm No E 125 mm No D 150 mm No 2 Chamber No 3 Dismantling of CC pavement Cum 207.83 4 Excavation in pipe line Cum 2672.1 Not provided by DIA 02 04 Not provided by DIA Comment regarding quality of work Revision: Issue 01 Rev:0 DocNo. QM17 5 6 Effective asof 05.01.2023 Page9 3of77 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Cum 207.83 A 63mm Mtr. 5070 B 75mm Mtr. 275 C 90 mm Mtr. 96 D 110mm Mtr. 94 E 140mm Mtr. 403 F 160mm Mtr 8 House hold connection No. 100 KL OHT staging 18M) No. Pump House No. 01 Boundary wall Rm 60 9 10 11 344 ZONE-II 1 Not provided by DIA A 50 mm No 01 B 65 mm No 01 C 80 mm No D 100 mm No E 125 mm No D 150 mm No 2 Chamber No 02 3 Dismantling of CC pavement Cum 77 4 Excavation in pipe line Cum 990 5 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes Cum 77 6 11 Not provided by DIA Following Size of CI/DI DF sluice valves A 63mm Mtr. 1200 B 75mm Mtr. 800 C 90 mm Mtr. 200 8 House hold connection No. 150 10 Pump House No. 01 Boundary wall Rm 30 Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page9 4of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Physical Measurement checking status as per scope: S. No . Item Unit 1. Pipeline work Mtr. 2. FHTC Nos 3. OHT Nos 4. Pump House Nos As per tender/co ntract bond Qty. As per actual (MB) %age complet ed Qty. Qty. Remarks about quality - Compliance for last observations reported S. No 1. Item Observations last reported Compliance reported NA NA NA Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per 56. Design mix report 57. GI pipe 15mm Dia 58. HDPE Pipe-90 mm 59. MSERW Pipe 60. DI pipe 61. Cement Report Remarks (whether tests are Availabili Conducted as per respective IS code ty Approved Status Provision so not) QAP) (yes/No) M-25 & M- No Tests to be conducted as per IS 10262:2009 30 and IS 456: 2000 & Frequency of tests to be conducted as per specifications.(Reports Submitted) No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Tests to be conducted as per IS 4270:2001 Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page9 5of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT conducted as per specifications. 62. Steel No Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. 63. Aggregate/ Sand No 64. Bricks No 65. CC Cube No 66. Water test report No Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register : Not Available at site. Site order book : Not Available at site. Test register/Report : Not Available at site. Concrete Register : Not Available at site. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page9 6of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. I. Scheme:Banjarewala Water supply Scheme. Block-Laksar . General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress ( in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Note:Work not started. Banjarewala Pumping water supply scheme. (135EE/JJM/2022-23) MD UJS Lacs Lacs. 25-06-2022 24-06-2023 0% 0% Sh. Sh. Pervez Pumping. 1st visit @June-23 NA. Running. - Physical Progress S.No. Item 1. 2. Pipeline work FHTC Proposed Quantity as per contract bond Total quantity Executed till date Executed This month Remarks 8138 494 Scope of work /Description of works S. No Item Details ZONE-1 Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. Comment regarding quality of work Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page9 7of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 1 Following Size of CI/DI DF sluice valves A 50 mm No B 65 mm No C 80 mm No D 100 mm No E 125 mm No D 150 mm No 2 Chamber No 3 Dismantling of CC pavement Cum 4 Excavation in pipe line Cum 5 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes 6 63mm Mtr. B 75mm Mtr. C 90 mm Mtr. D 110mm Mtr. E 140mm Mtr. F 160mm Mtr 8 House hold connection No. 100 KL OHT staging 18M) No. Pump House No. Boundary wall Rm 10 11 Not provided by DIA Cum A 9 Not provided by DIA ZONE-II 1 Not provided by DIA Following Size of CI/DI DF sluice valves A 50 mm No B 65 mm No C 80 mm No D 100 mm No E 125 mm No D 150 mm No 2 Chamber No Not provided by DIA Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page9 8of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 3 Dismantling of CC pavement Cum 4 Excavation in pipe line Cum 5 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes 6 Cum A 63mm Mtr. B 75mm Mtr. C 90 mm Mtr. 8 House hold connection No. 10 Pump House No. Boundary wall Rm 11 Physical Measurement checking status as per scope: S. No . Item Unit 1. Pipeline work Mtr. 2. FHTC Nos 3. OHT Nos 4. Pump House Nos As per tender/co ntract bond Qty. As per actual (MB) %age complet ed Qty. Qty. Remarks about quality - Compliance for last observations reported S. No 1. Item Observations last reported Compliance reported NA NA NA Material testing status (Lab test/MTC) S. No. 67. Name of Material Make as (as per scope of work) Per Design mix report Report Remarks (whether tests are Availabili Conducted as per respective IS code ty Approved Status Provision so not) QAP) (yes/No) M-25 & M- No Tests to be conducted as per IS 10262:2009 30 and IS 456: 2000 & Frequency of tests to Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page9 9of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT be conducted as per specifications.(Reports Submitted) 68. GI pipe 15mm Dia No 69. HDPE Pipe-90 mm No 70. MSERW Pipe No 71. DI pipe No 72. Cement No 73. Steel No 74. Aggregate/ Sand No 75. Bricks No 76. CC Cube No 77. Water test report No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. Tests to be conducted as per IS 4270:2001 Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register : Not Available at site. Site order book : Not Available at site. Test register/Report : Not Available at site. Concrete Register : Not Available at site. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 00of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. IV. Scheme: Khedli water Supply scheme. Block- Bhadarabad. General information Name of scheme/sub scheme Name of DIA Sanctioned cost(In Rs.) Contract bond cost(in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Khedli pumping water supplyscheme(98/E.E./JJM/2022-23) MD UJS 197.50 Lacs 164.43Lacs 12-05-2023 11-05-2023 75% 41% Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 01of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Sh. Prvez Aalm Name of EE/AE/JE with Contact No. Sh.Pervez Name of TPI Engineer/mobile no. Pumping Type of scheme Last reported No ATR provided till date. Current status of work(Running/completed) Running. Any other detail Physical Progress 1. HDPE Pipeline Proposed Quantity as per contract bond 7087Mtr. 2. OHT 1 No. 1.00 1.00 3. Pump House 1 No. - 01 S.No Item Total quantity Executed till date Executed This month 3500m 1000m Remarks Work in progress. Railing work in progress. Work in progress. Scope of work /Description of works S. No. 1. I. II. III. IV. V. VI. 2. I. II. III. IV. V. VI. 3. 4. Item Details Providing and laying of HDPE pipes 63 mm 75 mm 90 mm 110 mm 140 mm 160 mm Sluice / Gate Valves 50 mm 65 mm 80 mm 100 mm 125 mm 150 mm Drilling of borehole 600 mm MSERW fin cut plain pipe 7.9 mm thick 300 mm dia Unit Mtr. Mtr. Mtr. Mtr. Mtr. Mtr. Nos Nos Nos. Nos Nos. Nos. Per Mtr. Per m As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. 4979.00 644.00 931.00 188.00 280.00 65.00 4979.00 644.00 931.00 188.00 280.00 65.00 2.00 2.00 1.00 1.00 1.00 1.00 2.00 2.00 1.00 1.00 1.00 1.00 - 150.00 - 110.00 Not provided Comment regarding quality of work Work in progress. Work not started Work in progress. Revision: Issue 01 Rev:0 DocNo. QM17 S. No. 5. 6. Effective asof 05.01.2023 Page1 02of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Item Details Unit MSERW fin cut slotted pipe 7.9mm thick 300 mm dia Per m - 40.00 Pea Gravel Cum - 80.00 Hrs Job - 80.00 1.00 Per m - 50.00 Work not started Per m - 20.00 Work not started Per m - 42.00 Set - 2.00 Job - 1.00 Cum - 20.56 Cum - 13.70 Work not started. CC flooring Sqm - 41.00 Work not started. Electrification of pump house No - 1.00 Work not started. Construction of Boundary wall Rm - 85.00 7. 8. 9. CFM Air compressor Geological survey Supply of submersible 1x3x16 sq.mm 10. Supply of aluminum armored cable 35 sq.mm 3.5 core 11. C class MS column pipe 12. MSDI clamp set 100 mm 13. G.I Earth plate 14. Earth work in excavation by mechanical means / manual means 15. Brick work As per DPR proposal Qty. As per contract bond Qty. 16. 17. As per actual (MB) Qty. by DIA Comment regarding quality of work Work completed. Work not started Work not started Work in progress. 18. 19. MS gate 20. Excavation in soil mixed with boulders. 21. MSERW pipe 125 mm 22. Chamber 23. RCC over Head Tank, 150 KL OHT staging 18 mtr. 24. Excavation in pipe line No - 1.00 Cum - 27.00 Mtr - 50.00 No 9.00 9.00 Per Kl Cum 150.00 150.00 3577.65 3577.65 Work not started. Work not started. Work in progress. OHT railing work in progress. Work in progress. Revision: Issue 01 Rev:0 DocNo. QM17 S. No. Effective asof 05.01.2023 Page1 03of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Item Details 25. Dismantling of CC Pavement 26. Un-reinforced CC Road 27. House hold connection Unit As per DPR proposal Qty. As per contract bond Qty. Cum 303.05 303.05 Cum No. 303.05 303.05 600.00 600.00 As per actual (MB) Qty. Comment regarding quality of work Work in progress Work in progress. Physical Measurement checking status as per scope: S. No Item Unit 1 OHT work 250 KL. 18 m STAGING. No. As per tender/co ntract bond Qty. 01 2. HDPE pipeline Mtr. 17306 As per actual (MB) %age completed Qty. Qty. 85% - - Remarks about quality OHT railing work in progress. Vimal GI pipe used at site. Work in progress. Compliance for last observations reported S. No Item 1. OHT 2. OHT Observations last reported Compliance reported Honeycomb found in OHT column Compliance not done in staircase area and poor workmanship shown. The column repair is not made correctly. Honeycomb found in staircase top Compliance not done landing & Steel visible and Poor workmanship shown. Material testing status (Lab test/MTC) Sl. No Name of Make Materials (as per (As per scope of work) approved QAP) Report availability status (yes/No) Remarks (whether tests are conducted as per respective IS code provisions or not) Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 04of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Sl. No Name of Make Report Remarks (whether tests are Materials (as per (As per availability conducted as per respective IS code scope of work) approved status provisions or not) QAP) (yes/No) Yes Tests to be conducted as per IS 15. Design mix report Yes (M-25 & M-30) 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications VIMAL No Tests to be conducted as per IS 1239 16. GI pipe (dia .wise) (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 17. HDPE Pipe 4984 (1995) & Frequency of tests to be conducted as per specifications.Not provided by DIA. No Not provided by DIA. 18. MSERW Pipe 19. DI pipe NA NA 20. Cement OPC 43 CCI Grade No 21. Steel 8mm 10mm 12mm 16mm 20mm Aggregate 10 mm 20mm Sail No NA Yes Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. 22. Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications.Not provided by DIA. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. 23. Bricks NA No 24. CC Cube M-25 Yes No 25. Water test report Yes No 26. Development of Yes B/W by O.P. unit & compressor unit NDT test(if any) NA No Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012NA Not provided by DIA. NA NA 27. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 05of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Availability of Register on site: Material register :Not maintained at site. Site order book : Not maintained at site. Test register : Not maintained at site. Concreting Register : Not maintained at site. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 06of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Workers not co operate for inspection due to not availability representative at the end of contractor/DIA available at site Spacing of Stirrups is not maintained as per specification/Drawings. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 07of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Curing not done properly. I. Scheme: Katarpur Alipur pumping Water supply Scheme. Block- Haridwar. General information Name of scheme/sub scheme Name of DIA Sanctioned cost(In Rs.) Contract bond cost(in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Physical Progress Katarpur Alipur Pumping water supply scheme. (77 EE/JJM/2022-23) MD UJS 195.43Lacs. 181.76 Lacs. 13-04-2022 12-04-2023 70% 61.44% Sh. Vinod Kumar Sh. Pervez Pumping. 1st visit @June-23 No Running. - Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 08of77 S.No. Item 2 OHT 150kl, 18m staging Pipeline work 3 FHTC 4 Pump House 1 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Proposed Quantity as per contract Bond Total quantity Executed till date Executed This month 01 01 01 6000 3000 250 200 01 01 10604 663 01 Remarks Work in progress Work in progress Work in progress Work in progress Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. ZONE-I Construction of Boundary wall Rmt. MS Gate Excavation in soil mixed with shingle boulders etc. MSERW pipe 125 mm D.I. Sluice/ Gate Valve 125 mm dia Following size of CI/DI DF sluice valves No. Cum. A 1 2 3 4 Not provided by DIA 30 01 12 Mtr. 30 No 02 50 mm No 01 B 65 mm No 01 7 Chamber No 04 8 OHT 150kl, 18m staging Dismantling of CC pavement 5 6 9 10 Excavation in pipe line Not provided by DIA Per Kl Cum Cum 11 Construction of Unreinforced, CC Cum pavement 12 Providing and laying of HDPE pipes A 63 mm Mtr. Not provided by DIA 01 477.18 4771.8 477.18 7425 B 75 mm Mtr. 880 C 90 mm Mtr. 1202 Not provided by DIA Comment regarding quality of work Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 09of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT D 110 mm Mtr. E 140 mm Mtr. 949 F 160 mm Mtr. 20 House hold connection No. 663 13 128 Physical Measurement checking status as per scope: S. No . Item Unit 1 2 3. OHT 150kl, 18m staging Pipeline work FHTC No. No. Mtr. 4 Pump house No. As per tender/co ntract bond Qty. 01 As per actual (MB) %age complet ed Qty. - 10604 663 - Qty. 60% 60% 70% 01 - 80% Remarks about quality Compliance for last observations reported S. No 1. Item NIL Observations last reported NIL Compliance reported NIL Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per 78. Design mix report 79. GI pipe (dia. wise) 80. HDPE Pipe 81. MSERW Pipe 82. DI pipe Report Remarks (whether tests are Availabili Conducted as per respective IS code ty approved Status Provision so not) QAP) (yes/No) No Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Not provided by DIA. No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 10of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT specifications. 83. Cement No 84. Steel No 85. Aggregate/ Sand No 86. Bricks No 87. CC Cube No 88. Water test report No Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Not provided by DIA. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register Site order book : Not provided by DIA. : Not provided by DIA. Test register/Report: Not Provided by DIA. Concrete Register : Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 11of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Barricading not provided at site. Rock strong cement is being used at site in construction of OHT. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 12of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Access not provided to climb at working spot. I. Scheme: Jaspur Chamaria Water supply Scheme. Block- Bhadrabad. General information Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 13of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT JaspurChamaria Pumping water supply scheme. Name of scheme/subsch0eme (80/E.E/JJM/2022-23) 193.81 Lacs. Sanctioned cost(In Rs.) 182.51 Lacs. Contract bond cost(in Rs.) 29-04-2022 Date of Start 28-04-2023 Date of completion 65 % Physical progress(in%) 23% Financial progress(in%) Sh. Vinod kumar Name of EE/AE/JE with Contact No. Sh. Akhilesh Semwal Name of TPI Engineer/mobile no. Pumping. Type of scheme 1st visit@May-23 Last reported No Running. - ATR provided till date. Current status of work(Running/completed) Any other detail Physical Progress S.N o 1 2 3. Proposed Quantity as per contract bond Item OHT 100KL ,18m 01 Staging Construction of Pump 1 House Pipeline work 17306m Total quantity Executed till date Executed This month 01 01 01 10000m 3000m Remarks Work in progress Work not started. Work in progress. Scope of work /Description of works S. No 1. I. II. III. 2. 3. 4. I. II. III. 5. Item Details Providing and laying of HDPE pipes 63 mm 75 mm 90 mm Excavation of pipe line Trenches Excavation in soil mixed Valves 50 mm 80 mm 150 mm House hold connection Unit Mtr. Mtr. Mtr. Cubic. M Cubic. M Nos Nos Nos Nos As per DPR proposal Qty. As per contract bond Qty. 6376.00 7350.00 3580.00 As per actual (MB) Qty. Not provided by DIA 4480.00 Comment regarding quality of work Work in progress. Work in progress. Work in progress. 1493.40 1.00 1.00 1.00 406.00 Work in progress. Revision: Issue 01 Rev:0 DocNo. QM17 S. No 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. Effective asof 05.01.2023 Page1 14of77 Item Details Unit Road cutting (C.C. Road) Electrification of tube well & pump house RCC over Head Tank Chamber Drilling of Borehole MSERW fin cut plain pipe 300 mm MSERW fin cut slotted pipe 300 mm Pea gravel Development Tube well Geological survey Supply of submersible cable 1x3x16 sq.mm Supply of aluminium armored 35sq. mm 3.5 core C class MS column pipe MSDI clamp set. 150 mm Installation of pumping plants G.I. Earth plate Earth work in Excavation by mechanical means/ manual means Supplying and filling in plint Brick work CC flooring Plaster 12mm Excavation in Pipe line Trenches Cum TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT As per DPR proposal Qty. Nos Per Mtr. As per actual (MB) Qty. Comment regarding quality of work 255.84 Job Each As per contract bond Qty. 1.00 Not provided by DIA 1.00 4.00 100.00 Per Mtr. 40.00 Per Mtr. 60.00 Cum 85.00 Hrs. 70.00 Job. 1.00 Per Mtr. 100.00 Per Mtr. 40.00 Per Mtr. 42.00 Set 2.00 Job 1.00 Job 1.00 Cum 20.56 Cum 7.89 Cum Sqm Sqm 13.70 41.00 123.86 Cum 23.13 100Kl, 18m staging. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 15of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Physical Measurement checking status as per scope: S. No . 1 2. Item Unit OHT HDPE Pipeline No. Mtr. As per tender/co ntract bond Qty. 01 17306.00 As per actual (MB) %age complet ed Qty. Qty. 55% 60% 01 Not provided by DIA Remarks about quality Work in progress. Compliance for last observations reported S. No 1 Item Curing Tank 2 Safety Observations last reported Curing tank is not being clean properly. PPEs not provided to workers. Compliance reported Compliance not done Compliance not done Material testing status (Lab test/MTC) S. no Name of Material (as per scope of work) Make as Per Report Availability 1. approved QAP) Design mix report M25 Status (yes/No) 2. GI pipe (dia. wise) Surya 3. HDPE Pipe Ashirwad Yes 4. MSERW Pipe Jindal Yes 5. DI pipe NA NA 6. Cement Birla Uttam Yes 7. Steel NA NA Remarks (whether tests are Conducted as per respective IS code Provisions or not) Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2 Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Test Reports Submitted Test Reports Submitted Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications.Test Reports Submitted Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications.NA Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 16of77 8. Aggregate/ Sand NA 9. Bricks NA 10. CC Cube NA 11. Water test report NA 12. NDT test (if any) NA TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Yes Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications.Test Reports not Submitted Yes Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications.Test Reports Submitted NA As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012 NA NA Availability of Register on site: Material register Site order book Test register/Report : Not provided by DIA. : Not provided by DIA. : Provided by DIA. Concrete Register : Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 17of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Rusted steel is being used at site. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 18of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Quality of concrete observed poor in OHT. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 19of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT I. Scheme: Shahpura Sitlakhera Water supply Scheme. Block- Bhadrabad. Generalinformation Name of scheme/sub scheme Sanctioned cost (In Rs.) Contract bond cost(in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Shahpura Sitlakhera Pumping water supply scheme. (100E.E/JJM/2022-23) 193.42Lacs. 178.20 Lacs. 12-05-2022 11-05-2023 80 % 36.36% Sh. Vinod Kumar Sh. Pervez Pumping. 1st visit @June-23 No Running. - Remark: Work is stopped since last three months. Physical Progress S.No. 1 Item OHT 125 KL OHT Proposed Quantity as per contract bond Total quantity Executed till date 1.00 1.00 Executed This month Top dome RCC completed. staging 18 mtr. 2 3. Construction of Pump House Pipeline work Zone-1 Zone-2 Remarks 1.00 Work not started. 10525m Work in progress. 1100.00 Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. Comment regarding quality of work Revision: Issue 01 Rev:0 DocNo. QM17 1. 3. Providing and laying of HDPE pipes 63 mm 75 90 mm 110 mm 140 mm Excavation of pipe line 5408.00 1703.00 2040.00 812.00 490.00 I 50 mm II 65 mm Nos Nos. 1.00 1.00 1.00 1.00 III 80 mm Nos 1.00 1.00 IV 100 mm Nos. 1.00 1.00 Nos 5. 6. 7. 8. 9. 5408.00 1703.00 2040.00 812.00 490.00 305.00 305.00 Road cutting Cum 418.12 418.12 Tube well Job 1.00 Electrification of pump house Electrification of boundary wall No RM 1.00 50.00 1.00 50.00 Work not started. Work not started. 10. 11. MS gate No. 1.00 1.00 Rising main Cum 46.20 46.20 12. RCC over Head Tank, 125 KL OHT staging 18 mtr. Per Kl 125.00 125.00 Chamber Nos 6.00 Per Mtr. 150.00 150.00 Per Mtr. 110.00 110.00 Per Mtr. 40.00 40.00 Cum 50.00 50.00 15. 16. Not provided by DIA Work in progress 6.00 17. Pea Gravel Work in progress Work not started. 1.00 Drilling of borehole 600 mm dia MSERW fin cut plain pipe 7.9 mm thick 200 mm dia MSERW fin cut slotted pipe 7.9 mm thick 300 mm dia Work in progress Not provided by DIA 1.00 1.00 14. Work in progress 4703.85 Construction of No pump house 13. Not provided by DIA Valves and chamber House hold connection 4. TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Mtr. Mtr. Mtr. Mtr. Mtr. Cum I II III IV V 2. Effective asof 05.01.2023 Page1 20of77 Work not started. Revision: Issue 01 Rev:0 DocNo. QM17 18. 19. 20. 21. 22. 23. Effective asof 05.01.2023 Page1 21of77 CFM Air compressor Geological survey Supply of submersible 1x3x16 sq.mm Supply of aluminum armored 35sq.mm 3.5 core TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Hrs. 40.00 40.00 Job 1.00 1.00 Per Mtr. 100.00 100.00 Per Mtr. 40.00 40.00 C class MS column pipe Per Mtr. 42.00 42.00 MSDI clamp set 150 mm Set 2.00 2.00 Not provided by DIA G.I. Plate Job 1.00 1.00 Work not started. Earth work in excavation by mechanical means / manual means Cum 20.56 20.56 Work in progress Brick work Cum 13.70 13.70 Work not started. No 1.00 1.00 5.00 5.00 8.00 8.00 25.00 25.00 30.00 30.00 Work not started. 1.00 1.00 Work not started. 49.50 49.50 495.00 495.00 49.50 49.50 24. 25. 26. 27. 28. 29. 30. 31. 32. 33. 34. 35. 36. Work not started. ZONE-2nd Submersible pump 125mm Providing laying cement concrete MS door Dismantling of existing flooring CC flooring Cum Not provided by DIA Work not started. Sqm Work in progress Sqm Sqm Electrification of Pump house No Dismantling of cc pavements Trench Excavation Construction of Un-rein froced Providing HDPE Pipe 63 mm Cum Cum Cum Mtr Work in progress 1100.00 1100.00 Not provided by DIA Work in progress Work in progress Work in progress Work in progress Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 22of77 Sluice valve/ Gate valve 50 mm Chamber House hold connection 37. 38. 39. TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT No No Nos 2.00 2.00 2.00 2.00 59.00 59.00 Work in progress Physical Measurement checking status as per scope: S. No . 1 2. Item Unit OHT HDPE Pipeline No. Mtr. As per tender/co ntract bond Qty. 01 11625.00 As per actual (MB) %age complet ed Qty. Qty. 80% 65% 01 Not provided by DIA Remarks about quality Work in progress. Compliance for last observations reported S. No 1. Item OHT Observations last reported Compliance reported Joint of staircase and landing is not Compliance not done proper. Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per approved QAP) 89. Design mix report 90. GI pipe (dia .wise) 91. HDPE Pipe 92. MSERW Pipe 93. DI pipe 94. Cement Report Availabili ty Status (yes/No) Remarks (whether tests are Conducted as per respective IS code Provisions or not) Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Not provided by DIA. Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications.Not provided by DIA. Not provided by DIA. NA Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS Not provided by 8182:2013 & Frequency of tests to be conducted as per specifications.Not DIA. provided by DIA. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 23of77 95. Steel 96. Aggregate/ Sand 97. Bricks 98. CC Cube 99. Water test report TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications.NA Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications.Not provided by DIA. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications.Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register Site order book :Not provided by DIA. :Not provided by DIA. Test register/Report :Not Provided by DIA. Concrete Register :Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 24of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Work is stopped Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 25of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT I. Scheme:Hasnawala Water supply Scheme. Block-Bhagwanpur . General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Hasnawala Pumping water supply scheme. (85EE/JJM/2022-23) MD UJS 187.52 Lacs Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 26of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 164.95 Lacs. Contract bond cost (in Rs.) 18-07-2022 Date of Start 18-07-2023 Date of completion 45% Physical progress ( in%) 39.18% Financial progress (in%) Sh.Vivek Ravi Name of EE/AE/JE with Contact No. Sh. Akhilesh Semwal Name of TPI Engineer/mobile no. Pumping. Type of scheme 1st visit @June-23 Last reported NA. ATR provided till date. Running. Current status of work(Running/completed) Any other detail Physical Progress S.No. Item 1. 2. 3. 4. Pipeline work FHTC OHT Pump House Proposed Quantity as per contract bond Total quantity Executed till date Executed This month Remarks 8155 475 01 01 Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. 1 Following Size of CI/DI DF sluice valves A 50 mm No B 65 mm No C 80 mm No 03 D 100 mm No 02 E 125 mm No D 150 mm No 2 Chamber No 3 Dismantling of CC pavement Cum 499.09 4 Excavation in pipe line Cum 4403.7 5 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes Cum 499.09 6 Not provided by DIA 01 01 07 As per Comment actual regarding (MB) quality of work Qty. Not provided by DIA Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 27of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT A 63mm Mtr. B 75mm Mtr. 1487 C 90 mm Mtr. 213 D 110mm Mtr. 269 E 140mm Mtr. 1324 F 160mm Mtr 10 8 House hold connection No. 475 100 KL OHT staging 18M) No. 01 Pump House No. 01 Boundary wall Rm 50 9 10 11 4852 Physical Measurement checking status as per scope: S. No . Item Unit As per tender/co ntract bond Qty. 1. Pipeline work Mtr. 8155 2. FHTC Nos 475 3. OHT Nos 01 4. Pump House Nos 01 As per actual (MB) %age complet ed Qty. Qty. Remarks about quality - Compliance for last observations reported S. No 1. Item Observations last reported Compliance reported NA NA NA Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per 100. Design mix report Report Remarks (whether tests are Availabili Conducted as per respective IS code ty Approved Status Provision so not) QAP) (yes/No) M-25 & M- No Tests to be conducted as per IS 10262:2009 30 and IS 456: 2000 & Frequency of tests to be conducted as per specifications.(Reports Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 28of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Submitted) 101. GI pipe 15mm Dia No 102. HDPE Pipe-90 mm No 103. MSERW Pipe No 104. DI pipe No 105. Cement No 106. Steel No 107. Aggregate/ Sand No 108. Bricks No 109. CC Cube No 110. Water test report No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. Tests to be conducted as per IS 4270:2001 Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register : Not Available at site. Site order book : Not Available at site. Test register/Report : Not Available at site. Concrete Register : Not Available at site. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 29of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments CCI cement is being used at site. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 30of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 90mm Slump observed at site. Raft foundation found satisfactory and ready to cast. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 31of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT VI. Scheme: Aurangabad Water supply Scheme. Block- Bhadrabad. General information Aurangabad water supply scheme. (105/EE./JJM/2022-23) 180.09 Lacs. Sanctioned cost (In Rs.) 175.06 Lacs. Contract bond cost(in Rs.) 12-05-2022 Date of Start 11-05-2023 Date of completion 35% Physical progress(in%) 28% Financial progress(in%) Sh. Vinod Kumar Name of EE/AE/JE with Contact No. Sh. Akhilesh Semwal Name of TPI Engineer/mobile no. Pumping. Type of scheme 1st visit @June-23 Last reported No ATR provided till date. Current status of work(Running/completed) Running. Any other detail Name of scheme/subsch0eme Physical Progress S.No Item Proposed Quantity as per contract bond Total quantity Executed till date Executed this month Remarks 1. OHT 01 Nos. - - Raft Foundation RCC work completed. 2. 3. 4. Pump house 01 Nos - 9806 Mtr. - - 559.00 Nos - - Pipeline work FHTC Work is in progress Scope of work /Description of works S. No. Item Details 1. I. Uni t As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. Comment regarding quality of work 4421.00 Not provided by DIA Work is in progress Providing and laying of pipes 63 mm Mtr . Not Revision: Issue 01 Rev:0 DocNo. QM17 II. Effective asof 05.01.2023 Page1 32of77 75 mm III. 90 mm IV. 110 mm V. VI. 1400 mm 160 mm 2. I. II. III. 3. 4. 5. Mtr . Mtr . Mtr . Mtr . Mtr . TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT provided by DIA 1715.00 2054.00 804.00 484.00 328.00 D.I. Sluice/ Gate valve 50 mm 65 mm 80 mm House hold connection Drilling of Borehole 600 mm Pea gravel Development of Tube well CFM Air compressor 7. Geological Survey of site 8. Supply of submersible 1x3x16 sq.mm 9. Supply of aluminumarmo red cable 35 sq.mm 3.5 core 10. C class MS column pipe 11. MSDI clamp No No No No s Per Mtr . Cu m 2.00 2.00 1.00 Not provided by DIA 559.00 Work not started. Work not started. Work not started. Not provided by DIA Work is in progress 150.00 Drilling work completed. 80.00 Work completed. Hrs 80.00 Work not started. Job 1.00 Per Mtr 100.00 Work not started. Per Mtr 40.00 Work not started. Per Mtr 42.00 Work not started. Set 1.00 Work not started. Job Cu m 1.00 Work not started. 6. set 150 mm 12. G.I. Earth plate 13. Brick work 14. 15. Excavation in soil mixed with shingle boulders etc. Chamber 16. OHT 250kl, 18 m staging 17. Dismantling of cement concrete pavement Cu m. No s Per kl Cu m Work not started. 16.20 Work is in progress 2.00 Work not started. 250.00 Raft foundation RCC work completed. 343.21 Work is in progress Revision: Issue 01 Rev:0 DocNo. QM17 18. 19. Effective asof 05.01.2023 Page1 33of77 Excavation of Pipe line Trenches Un-reinforced cement concrete pavement TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Cu m 4412.70 Work is in progress Cu m. 341.21 Work is in progress Physical Measurement checking status as per scope: S. No. Item Unit As per tender/contract bond As per actua l (MB) %age completed Remarks about quality 1. 2. OHT No. 01 - 10% Raft Foundation RCC Work completed & found as per drawing & specification. HDPE Pipeline Mtr. 9806.00 - - Work is in progress Compliance for last observations reported S. No 1. Ite m Cover blocks Observations last reported The cover block is not placed correctly at the site and is not inserted into the curing tank. Compliance reported Compliance not done Material testing status (Lab test/MTC) S. No. Name of Material (as per scope of work) Make(as Per approved QAP) Report Availabili ty Status (yes/No) 1. 2. Design mix report Yes (M-25) Yes GI pipe (dia. wise) Yes No Remarks (whether tests are Conducted as per respective IS code Provisions or not) Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 34of77 3. HDPE Pipe 4. MSERW Pipe TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be TIRUPATI No conducted as per specifications.Not provided by DIA Yes No 5. DI pipe NA No Cement OPCGrade-43 Birla Uttam No 6. 7. 8. Steel 8 mm 10 mm 12 mm 16 mm SAIL 550D No Aggregate/ Sand Yes No Bricks NA No CC Cube Yes No Water test report NA No 9. 10. 11. Not provided by DIA Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Not provided by DIA Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications.Test Reports Submitted Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications Not provided by DIA As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000Not provided by DIA Test report not provided by DIA and tests to be conducted as per IS 10500:2012 Not provided by DIA Availability of Register on site: Material register Site order book :Not provided by DIA. :Not provided by DIA. Test register/Report :Not provided by DIA Concrete Register :Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 35of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 36of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Access not provided to reach at construction spot for inspection. Safety measures not provided at site. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 37of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT M-25 mix design. Test report by Indian Testing Laboratory. M-25 mix design. Test report by Indian Testing Laboratory. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 38of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT I. Scheme: Mubarikpur Alipur Water supply Scheme. Block- Bhadrabad. General in formation Name of scheme/subsch0eme Name of DIA Sanctioned cost(InRs.) Contract bond cost(in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Note-Work not started yet. Mubarikpur Alipur Pumping water supply scheme. MD UJS 178.36Lacs. 150.5 0% 0% Sh. Deepak bhatt. Sh. Pervez Pumping. 1st visit @June-23 NA. Running. - Physical Progress S.No. Item 1 OHT staging 18 mtr. 3. Pipeline work Proposed Quantity as per contract bond Total quantity Executed till date Executed This month Remarks Scope of work /Description of works S. No 1. 2. 3. 4. 5. 6. Item Details Unit Construction of Boundary wall Rmt. MS Gate Excavation in soil mixed with shingle boulders etc. MSERW pipe 150 mm D.I. Sluice/ Gate Valve 150 mm dia No. Cum. Chamber No As per DPR proposal Qty. Not provided by DIA As per contract bond Qty. As per actual (MB) Qty. Not provided by DIA Comment regarding quality of work Work not started. Work in progress Mtr. No Not provided by DIA Work completed. Work in progress Work in progress Revision: Issue 01 Rev:0 DocNo. QM17 7. 8. 9. Effective asof 05.01.2023 Page1 39of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT OHT 250kl, 18m staging Dismantling of CC pavement Cum Excavation in pipe line Not provided by DIA Mtr. 10. Construction of Unreinforced, CC pavement 11. Providing and laying of HDPE pipes I. 63 mm 12. Bottom dome RCC completed. Work in progress Per Kl Work in progress Work in progress Cum House hold connection Mtr. Work in progress No. Work in progress Physical Measurement checking status as per scope: S. No . Item Unit 1 OHT No. 2. HDPE Pipeline Mtr. As per tender/co ntract bond Qty. As per actual (MB) %age complet ed Qty. Qty. Remarks about quality Bottom Dome RCC work completed. Work in progress. Compliance for last observations reported S. No 1. Item NIL Observations last reported NIL Compliance reported NIL Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per 111. Design mix report 112. GI pipe (dia. wise) 113. HDPE Pipe Report Remarks (whether tests are Availabili Conducted as per respective IS code ty approved Status Provisions or not) QAP) (yes/No) No Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 40of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT (1995) & Frequency of tests to be conducted as per specifications.Not provided by DIA. No Not provided by DIA. 114. MSERW Pipe 115. DI pipe No 116. Cement No 117. Steel No 118. Aggregate/ Sand No 119. Bricks No 120. CC Cube No 121. Water test report No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications.Not provided by DIA. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications.Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register Site order book :Not provided by DIA. :Not provided by DIA. Test register/Report :Not Provided by DIA. Concrete Register :Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 41of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. I. Scheme:Sisona Water supply Scheme. Block-Bhagwanpur . General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress (in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Sisona Pumping water supply scheme. (85EE/JJM/2022-23) MD UJS 175.82 Lacs. 02-05-2022 03-05-2023 70% 54% Sh.Vivek Ravi Sh. Pervez Pumping. 1st visit @June-23 NA. Running. - Physical Progress S.No. Item 1. Pipeline work Proposed Quantity as per contract bond 7404 Total quantity Executed till date Executed This month 4500 2500 Remarks Work in progress Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 42of77 2. FHTC 3. OHT 4. Pump House 471 01 01 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 410 60 Work in progress 01 01 Work in progress 01 01 Work in progress Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. 1 Following Size of CI/DI DF sluice valves A 50 mm No 07 B 65 mm No 01 C 80 mm No 03 D 100 mm No 02 E 125 mm No 01 D 150 mm No 01 F 200 mm No 01 G Air valve-25mm dia No 02 2 Chamber No 19 3 Dismantling of CC pavement Cum 4 Excavation in pipe line Cum 5 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes 6 Not provided by DIA 380.31 3803.07 Cum 380.31 A 63mm Mtr. 4545 B 75mm Mtr. 884 C 90 mm Mtr. 681 D 110mm Mtr. 607 E 140mm Mtr. 488 F 180mm Mtr 199 7 250KL OHT Staging 18m No. 8 House hold connection No. 471 9 Pump House No. 01 10 Boundry wall Rm 50 01 As per Comment actual regarding (MB) quality of work Qty. Not provided by DIA Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 43of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Physical Measurement checking status as per scope: S. No . Item Unit As per tender/co ntract bond Qty. As per actual (MB) %age complet ed Qty. Qty. 60% Remarks about quality 1. Pipeline work Mtr. 7404 2. FHTC Nos 471 70% 3 OHT Nos 01 80% Work is stopped. 4 Pump House Nos 01 80% - - Compliance for last observations reported S. No 1. Item Observations last reported Compliance reported NA NA NA Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per 122. Design mix report 123. GI pipe 15mm Dia 124. HDPE Pipe-90 mm 125. MSERW Pipe 126. DI pipe 127. Cement Report Remarks (whether tests are Availabili Conducted as per respective IS code ty Approved Status Provision so not) QAP) (yes/No) M-25 & M- No Tests to be conducted as per IS 10262:2009 30 and IS 456: 2000 & Frequency of tests to be conducted as per specifications.(Reports Submitted) No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Tests to be conducted as per IS 4270:2001 Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 44of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT conducted as per specifications. 128. Steel No Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. 129. Aggregate/ Sand No 130. Bricks No 131. CC Cube No 132. Water test report No Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register : Not Available at site. Site order book : Not Available at site. Test register/Report : Not Available at site. Concrete Register : Not Available at site. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 45of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Railing found damaged. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 46of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Undulation observed in beam. Without rectification paint applied. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 47of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Droplet not provided in plaster of Chajja. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 48of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT OPC 43Grade Birla Uttam Cement Test report by Indian Testing Laboratory. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 49of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT M-30 Mix DesignTest report by Indian Testing Laboratory. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 50of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT M-30 Mix Design Test report by Indian Testing Laboratory. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 51of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 10 mm Aggregate Test report by Indian Testing Laboratory. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 52of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 10 mm Aggregate Test report by Indian Testing Laboratory. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 53of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 20 mm Aggregate Test report by Indian Testing Laboratory. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 54of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 20 mm Aggregate Test report by Indian Testing Laboratory. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 55of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Corse sandTest report by Indian Testing Laboratory. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 56of77 XIX. TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Fine Aggregate (Corse sand)Test report by Indian Testing Laboratory. Scheme:IbrahimpurDehPumping water Supply scheme, Block-Roorkee. Generalinformation Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 57of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT IbrahimpurDehPumpingwater supply Nameofscheme/subscheme scheme. 177.96 Lacs. Sanctionedcost (InRs.) NotprovidedbyDIA. Contractbondcost (inRs.) NotprovidedbyDIA. DateofStart NotprovidedbyDIA. Dateofcompletion 10% Physical progress(in%) 40% Financialprogress(in%) Sh.HimanshuTyagi (A.A.E.) NameofEE/AE/JEwith ContactNo. Sh.HimanshuKaushik. Nameof TPIEngineer/mobileno. Pumpingwater supplyscheme. Typeofscheme 2ndVisit Report. Lastreported Nil. ATRprovidedtilldate. currentstatusofwork(Running/completed Running. ) Anyotherdetail PhysicalProgress S.N o 1 Proposed Totalquant Quantity ityExecute aspercont d tilldate ractbond Item OHT200KL, 18 mstaging. 01No. - Execute dthismo nth Remarks Work is on hold Work is inprogress due to lack of upto column manpower. above raft foundation. Scopeofwork/Descriptionofworks S.No ItemDetails Unit 1. Providingand layingof pipes 63mm Mtr. S.No 75mm Mtr. 90 mm Mtr. 110 mm Mtr. ItemDetails Unit pipeline Asper DPR propos alQty. Asper contract bondQt y. Not provided Notpro vided Not provided Not provided As per DPRprop osal Qty. Not provided Notpro vided Not provided Not provided As percon tract bond Qty. Asper actual (MB)Qty. Comment regarding qualityof work Worknotstarted. As peractual (MB) Qty. Commentrega rdingquality of work Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 58of77 3. Valves 80mm 100mm 4. Airvalve 25mmdia 5. OHT350KL, 18mstaging. 6. 7. 8. 9. House holdconn ection Roadcutting TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Not Not provided provided Nos. Not Not provided provided Nos. Not Not provided provided Nos. Not Not provided provided No. Notpro Notpro vided vided Nos. cum Road Cum reinstatement Constructiono Each f pumphouse 10. Risingmain Mtr 11. Boundarywall Nos Notpro vided Notpro vided Not provided Not provided Not provided Not provided Not provided Not provided Not provided Not provided Notpro vided Notpro vided Qualityof workis as perspecifica tions. Worknotstarted. Worknotstarted. Procurement pending. Worknot started. PhysicalMeasurementcheckingstatusasperscope: S. No 1. Item Unit OHT200KL,18 metrestaging No. As pertend er/contr actbond Qty. 01 As perac tual( MB) Qty. %agecom pleted Remarksab outquality Qty. Notprov ided 10% Qualityofworkisa sperspecification s. Complianceforlastobservationsreported S. No 1. Item NIL Observationslastreported NIL Compliancereported NIL Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 59of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Materialtesting status(Labtest /MTC) S. Make: Nameof Material Reportav ailability AsPerper approved QAP no conducted asperrespectiveIScode) 1. Designmix report Yes Yes 2. GIpipe (dia.wise) NA NA 3. HDPEPipe NA NA 4. DIpipe NA NA 5. Cement Birla Uttam Yes 6. Steel Sail Yes 7. Aggregate Yes Yes 8. Bricks Yes Yes 9. CC Cube Yes No 10. Watertestreport Yes No 11. NDTtest(ifany) NA Remarks(whether testsare NA Tests to be conducted as per IS10262:2009andIS456:200 0& Frequencyofteststobeconducteda sperspecifications. TeststobeconductedasperIS1239 (Part I):2004&IS:10748:2004with Amnd-5,Grade2 TestsconductedasperISCodeIS498 4(1995) &Frequencyof tests to be conductedasperspecifications. TestsconductedasperISCode IS8329 &Frequencyofteststobeconductedas perspecifications. TestsconductedasperISCodeIS 8182:2013 & Frequency of tests to beconductedas per specifications. TestsconductedasperISCodeIS 1786:2008 & Frequency of tests to beconductedas per specifications. TestsconductedasperISCodeIS 383:2016&Frequencyofteststobe conductedas per specifications. TestsconductedasperISCode 1077:1992 & Frequency of tests to beconductedas per specifications. As per IS Code IS 10086:1982 &Frequencyofteststobeconducted as perIS456:2000.Test reports not provided for Raft foundation by DIA. TestreportnotprovidedbyDIAandt eststo beconducted asperIS 10500:2012 NA Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 60of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Availabilityof Registeronsite: Material register :Not provided by DIA.Siteorderbook :Not provided by DIA.Testregister provided by :Not DIA.ConcretingRegister:Not providedbyDIA, ConclusionandSuggestions: - Batch Report no. to be provided in the HDPE Pipe Available at site as per Test reportssubmitted . Work is on hold due to lack of manpower. Backfilling should be done in layers and proper compaction should be done in mechanicalmeans. Note: All concrete mixers to be attached with Weigh Batcher machine and volumetricconcretearenot acceptable. PhotographsofInspection Comm ents OHT work done upto column second lift above raft foundation. Work on hold from more than two months. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 61of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Covering not provided over the boring well pipe. SAIL Steel used at site. OHT work is on hold from 2 months due to lack of labour. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 62of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Drawing of OHT. M-25 Design mix. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 63of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Cement test report from external lab. Coarse sand test report from external lab. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 64of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 10 mm aggregate test report from external lab. 20 mm aggregate test report from external lab. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 65of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Steel 8mm dia. test report from external lab. Steel 10 mm dia. test report from external lab. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 66of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Steel 12 mm dia. test report from external lab. Steel 16 mm dia. test report from external lab. cheme: BeldiSalhapur Water supply Scheme. Block- Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 67of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Roorkee.Generalinformation Nameofscheme/subscheme Sanctioned cost(InRs.) Contractbondcost(inRs.) DateofStart Dateofcompletion Physical progress(in%) Financialprogress(in%) NameofEE/AE/JEwith Contact No. NameofTPIEngineer/mobileno. Type ofscheme Lastreported ATRprovidedtilldate. current statusofwork(Running/completed) Anyotherdetail Beldi Salhapur Pumping water supply scheme. (86/EE./JJM/2021-22) 177.48Lacs. 166.58Lacs. 02-05-2022 03-05-2023 95 % 70% Sh.HimanshuTyagi Sh.HimanshuKaushik,AdityaThapliyal Pumping. 05-01-2023 Not provided till date. Running. - PhysicalProgress S.No Proposed Quantityasper contractbond Item Totalquan tityExecut edtilldate Executed thismont h Remarks 1 OHT150KL,18m Staging 01No. 01No. - OHT Structure work completed. Paint and railing work in progress. 2 Pumphous e Boundary wall 01No 01No. - 60 m 60m - Paint work in progress. Plaster work in progress. 3. Scopeofwork/Descriptionofworks S.No 1. I. ItemDetails Unit Providingand layingof pipes 63 mm Mtr. As perD PR propos alQty. 5027 As percontract bondQty. 5027 As peractual (MB)Qty. Commentre gardingquali tyofwork Work is in progress. Revision: Issue 01 Rev:0 DocNo. QM17 S.No II. III. IV. V. VI. 2. 3. I. II. III. IV. V. 4. 5. 6. 7. Effective asof 05.01.2023 Page1 68of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT ItemDetails Unit As As As perD percontract peractual PR bondQty. (MB)Qty. propos alQty. 75 mm Mtr. 540 540 Notprovid 90 mm Mtr. 248 248 ed byDIA. 110 mm Mtr. 168 168 140 mm Mtr. 440 440 160 mm Mtr. 15 15 Excavationof Cubic. 20.56 20.56 pipeline M Valves 50 mm Nos. 09 09 65 mm Nos. 03 03 80 mm Nos 02 02 100mm Nos. 01 01 125mm Nos. 01 01 Airvalve Nos. 02 02 25mmdia Household Nos 502 502 connection Cum Roadcutting 394.0 394.0 1 1 Cum. Roadreinst atement 8. Tubewell Job 9. Pumpingplant Each 10. Servovoltage Job stabilizer Electrification of tube well Job &pumphous e 11. 12. Construction ofpumphous e 13. RCC overHea dTank, 394.0 1 394.0 1 01 01 01 01 01 01 01 01 Notprovid ed byDIA. Commentre gardingquali tyofwork Work is inprogre ss. . Workin progress. Work in progress. Workisin progress. Workisin progress. Hydrostatict esting is to bedone beforestarti ngreinstate ment work. Workisin progress. Worknotstarte d. Worknotstarte d. Worknotstarte d. Each 01 01 Paint Work is inprogre ss. Each 01 01 OHT structure work completed .Paint work in Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 69of77 150KL OHT TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT progress. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 70of77 S.No ItemDetails TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Unit As As As perD percontract peractual PR bondQty. (MB)Qty. propos alQty. Commentre gardingquali tyofwork staging18 mtr. 14. 15. Risingmain Mtr Boundarywall Mtr. 27 60 Worknotstarted Plaster work in progress. 27 60 PhysicalMeasurementcheckingstatusasperscope: S . N o. 1 2. Item Unit OHT 150KL, 18 m Staging As pertend er/contr actbond Qty. As perac tual( MB) Qty. %age compl e ted Qty. No 01 - 80% Mtr. 6438 - 70% No. 01 - 80 % 60 m - HDPEPipeline 3. PumpHouse 4. Boundary wall M Remarksaboutquality OHT paint work in progress. Hydrostatic testing to be done before reinstatement work. Quality of work is as per specifications. 70% Quality of work is as per specifications. Complianceforlastobservationsreported S. No 1. Item NIL Observationslastreported NIL Compliancereported NIL Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 71of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Materialtesting status(Labtest /MTC) S. Nameof Material no (asperscopeo fwork) 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Make(as Report Per availability Remarks(whethertestsar e conductedasperrespectiveI Scode provisionsornot) approved Status QAP) (yes/No) Yes Designmix report Yes Tests to be conducted as per IS10262:2009andIS456:200 0& Frequencyofteststobeconductedas perspecifications. No GIpipe (dia.wise) Yes Tests to be conducted as per IS 1239(Part I):2004&IS:10748:2004with Amnd-5,Grade2 APOLLO No HDPEPipe Tests conductedas perISCodeIS4984(1995)&Frequenc yofteststobe conducted as per specifications. TestReportsNot Submitted. NA No TestsconductedasperISCodeIS DIpipe 8329 & Frequency of tests to beconductedasperspecificati ons. BirlaUttam Yes Cement Tests conducted as per IS Code IS8182:2013&Frequencyofteststo be conductedasperspecifications. Yes Yes Steel Tests conducted as per IS Code IS1786:2008&Frequencyofteststo be conductedasperspecifications. Yes Aggregate/Sand Yes Tests conducted as per IS Code IS383:2016&Frequencyofteststo be conductedasperspecifications. Yes Yes Bricks Testsconductedas per ISCode1077:1992&Frequencyofte ststobe conductedasperspecifications. Yes NO CC Cube As per IS Code IS 10086:1982 &Frequencyofteststobeconducteda s per IS456:2000 Not provided of staircase ,bottom dome ,vertical wall and top dome. Yes Watertestreport Yes Testreportnotprovided byDIAandteststo beconducted asperIS 10500:2012TestReportsprovided Revision: Issue 01 Rev:0 DocNo. QM17 11. Effective asof 05.01.2023 Page1 72of77 NDTtest(ifany) TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT NA NA NA Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 73of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Availabilityof Registeronsite: Material register : Not provided by DIA.Siteorderbook :Not provided by DIA.Testregister :Not provided by DIA.ConcreteRegister:Not provided byDIA. ConclusionandSuggestions: - Testregisterstobemaintainedatsite. - Work is on hold from one month. - Backfilling should be done in layers and proper compaction should be done in mechanicalmeansforpipelineand OHT work. - Note: All concrete mixers to be attached with Weigh Batcher machine and volumetric concreteisnot acceptable. PhotographsofInspection Comment s Double coat of paint completed for the OHT structure. Work is on hold from one month. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 74of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Railing work of OHT completed. Clamps in ms-angle are missing at some places. Brickwork of chamber is not in plumb. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 75of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Pedestal platform checked and found as per standard and specification. Poor workmanship observed in brickwork of chamber. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 76of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Drawing for OHT . Backfilling work on hold from more than month. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 77of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Pump house paint work completed but requires repair on some places. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 78of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Raft foundation cube test reports for 28 days. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 79of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Column 1st lift cube test reports from external lab. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page1 80of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Brace 1st cube test reports from external lab. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 181 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT 10mmsteeltestreportfromexternal lab. 8mmsteeltestreportfromexternal lab. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 182 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT 16mmsteeltest reportfromexternallab. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 183 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT 12mm steel bartest report. Bricktestreportfromexternallab. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 184 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Sandtestreportfromexternallab. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 185 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Bricktestreportfromexternallab. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 186 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Cementtestreportfrom externallab. Aggregate 10 mm test report fromexternallab. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 187 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Aggregate 10 mm test report fromexternallab. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 188 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Soiltest reportprovided byDIA. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 189 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT DrawingsforOHTwork. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 190 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT DrawingsforOHTwork. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 191 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Drawingfor OHTwork. 5 Scheme: Sajanpur Peeli Water supply Scheme. Block- Bhadrabad. General information Name of scheme/subsch0eme Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress (in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Sajanpur Peeli Pumping water supply scheme. (82/EE./JJM/2022-23) 153.53 Lacs. 142.66 Lacs. 29-04-2022 28-04-2023 30% 21% Sh. Deepak Bhatt Sh. Akhilesh Semwal Pumping. 1st visit @June-2023 No Running. - Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 192 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Physical Progress S.No Item Proposed Quantity as per contract bond Total quantity Executed till date Executed this month 5. OHT 150Kl, 14m staging. 01 Nos. 01 01 6. Pump house 01 Nos. - - 7. 8. Pipeline work FHTC 12759m - - 440.00 Nos - - Remarks 2nd Brace rcc work completed Work not started. Work in progress Work in progress Scope of work /Description of works S. no. 1. I II III IV 2. I. 3. I. II. III. 4. 5. 6. 7. 8. 10. 11. 12. Item Details Unit As per DPR proposal Qty. Providing and laying of pipes 63 mm 75 mm 90 mm 110 mm Mtr. Mtr. Mtr. Mtr. 7871.00 3152.00 602.00 1136.00 7871.00 3152.00 602.00 1136.00 150 mm D.I. Sluice/ Gate valve 50 mm 80 mm 150 mm Mtr. 92.00 92.00 No No No 1.00 1.00 1.00 1.00 1.00 1.00 House hold connection Nos 440.00 440.00 Drilling of Borehole Per Mtr. 100.00 100.00 Per Mtr 40.00 40.00 Per Mtr 60.00 60.00 Cum 85.00 85.00 Job 1.00 1.00 Per Mtr 50.00 50.00 Per Mtr 15.00 15.00 As per contract bond Qty. As per actual (MB) Qty. Comment regarding quality of work Not provided by DIA Work is in progress D.I. Pipe S&S K-7 MSERW fin cut plain pipe 300 mm dia MSERW fin cut solotted pipe 300 mm dia Pea gravel Geological Survey of site Supply of submersible 1x3x16 sq.mm Supply of aluminum armored cable 35 Work not started. Work is in progress Drilling work completed. Work completed. Work completed. Not provided by DIA Work completed. Work not started. Work not started. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 193 of 112 S. no. 13. 15. 16. 17. 18. 19. 20. 21. 23. 24 25. 26. 27. 28. 29. Unit As per DPR proposal Qty. As per contract bond Qty. Per Mtr 42.00 42.00 G.I. Earth plate Job 1.00 1.00 Earth work in excavation by mechanical means / manual means Cum 20.56 20.56 Brick work Cum 13.70 13.70 CC Flooring Sqm 41.00 41.00 Nos 1.00 1.00 Cum 17.69 17.69 Mtr. 5.44 5.44 Work is in progress No 1.00 1.00 Work not started. No 1.00 1.00 Work not started. Chamber Nos 6.00 6.00 OHT 150kl, 14m staging Per kl 150.0 150.0 Item Details sq.mm 3.5 core C class MS column pipe Electrification of pump house Excavation of pipe line Trenches Excavation in soil mixed with shingle boulders etc. D.I. Sluice/ Gate valve Pressure 1.6 100mm dia D.I. Non Return valve Pressure 1.6 100mm dia Dismantling of flexible pavement Dismantling of cement concrete pavement Excavation of Pipe line Trenches As per actual (MB) Qty. Work not started. Work not started. Work is in progress Work not started. Work not started. Work not started. Work is in progress Not provided by DIA Cum 5.40 5.40 Cum 68.64 68.64 Cum 4552.68 4552.68 Comment regarding quality of work Work not started. 1St Brace RCC work completed. Work is in progress Work is in progress Work is in progress Physical Measurement checking status as per scope: S. No . Item Unit 1 OHT No. As per tender/co ntract bond Qty. 01 As per actual (MB) %age complet ed Remarks about quality Qty. - Qty. 30% OHT work done upto 2nd Revision:Iss ue 01 Effective as of 17.05.2023 Rev: 0 Doc No. QM 20 Page 194 of 112 2. HDPE Pipeline TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Mtr. 2825 - - brace & found as per drawing &specification. Work is in progress Compliance for last observations reported S. No Item 1. OHT 2 Concrete cube Observations last reported OHT 1st brace work in progress. Its observed that workers were not wearing Safety PPEs. Curing tank for cubes at site.Curing tank is not being cleaned. Compliance reported Compliance not done Compliance not done Material testing status (Lab test /MTC) S. No. Name of Material (as per scope of work) 12. 13. Make(as Report Remarks (whether tests are Per Availability Conducted as per respective IS code approved QAP) Status (yes/No) Provisions or not) Design mix report Yes Yes GI pipe (dia. wise) Yes No HDPE Pipe Yes No MSERW Pipe Yes No 14. 15. 16. DI pipe NA No Cement OPCGrade-43 Birla Uttam Yes 17. 18. Steel 8 mm 10 mm 12 mm TATA Yes Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications.Not provided by DIA Not provided by DIA Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Not provided by DIA Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications.Test Reports Submitted Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 195 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT 16 mm 19. Aggregate/ Sand Yes Yes Bricks NA No CC Cube Yes No Water test report NA No 20. 21. 22. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications Not provided by DIA As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000Not provided by DIA Test report not provided by DIA and tests to be conducted as per IS 10500:2012 Not provided by DIA Availability of Register on site: Material register Site order book :Not provided by DIA. :Not provided by DIA. Test register/Report :Not provided by DIA Concrete Register :Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 196 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Access not provided to reach at working spot. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 197 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Birla Uttam cement is being used at site. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 198 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Coarse Aggregate 40mm. Test report from Reliable Test House. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 199 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Coarse Aggregate 20mm. Test report from Reliable Test House. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 200 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Coarse Aggregate 10mm. Test report from Reliable Test House. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 201 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT House TMT bar 16 mm Dia. Test report from Reliable Test. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 202 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT House TMT bar 12 mm Dia. Test report from Reliable Test. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 203 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT House TMT bar 10 mm Dia. Test report from Reliable Test. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 204 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT House TMT bar 08 mm Dia. Test report from Reliable Test. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 205 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT M-25 Design mix. Test report from Reliable Test. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 206 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Sieve Analysis 10 mm Corse Aggregate. Test report from Reliable Test. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 207 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT M-25 Design mix. Test report from Reliable Test. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 208 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT I. Scheme: Shyampur Nauragabad pumping Water supply Scheme. Block- Laksar. General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress (in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Shyampur Naurangabad Pumping water supply scheme. (84 EE/JJM/2022-23) MD UJS 150.17Lacs. 140.99 Lacs. 55% 48% Sh. Badmoda Sh. Akhilesh Semwal Pumping. 1st visit @June-23 No Running. - Physical Progress S.No. 1 2 3 4 Item Proposed Quantity as per contract Bond Total quantity Executed till date Executed This month 01 01 01 OHT 150kl, 18m staging Pipeline work FHTC Pump House Remarks Work in progress 17278 559 01 Scope of work /Description of works S. No 1 2 Item Details Unit Construction of Boundary wall Rmt. MS Gate No. As per DPR proposal Qty. Not provided by DIA As per contract bond Qty. As per actual (MB) Qty. Not provided Comment regarding quality of work evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 209 of 112 Excavation in soil mixed with shingle boulders etc. MSERW pipe 125 mm D.I. Sluice/ Gate Valve 100 mm dia Following size of CI/DI DF sluice valves Cum. A 3 4 by DIA 23.13 Mtr. 35 No 02 50 mm No 01 B 80 mm No 02 C 150 mm No 02 7 Chamber No 06 8 OHT 200kl, 18m staging Dismantling of CC pavement Per Kl 01 5 6 9 Not provided by DIA Cum 10 Excavation in pipe line Cum Not provided by DIA 84.96 6332.91 11 Construction of Unreinforced, CC Cum pavement 12 Providing and laying of HDPE pipes A 63 mm Mtr. 7715 B 75 mm Mtr. 5478 C 90 mm Mtr. 1973 D 110 mm Mtr. 1832 E 125 mm Mtr. 280 House hold connection No. 559 13 Physical Measurement checking status as per scope: S. No . Item Unit 1 2 3. OHT 200kl, 18m staging Pipeline work FHTC No. No. Mtr. 4 Pump house No. As per tender/co ntract bond Qty. 01 17278 As per actual (MB) %age complet ed Qty. 559 Qty. 80% - 01 - Compliance for last observations reported Remarks about quality evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 210 of 112 S. No 1. TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Item No Observations last reported No Compliance reported No Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per 133. Design mix report 134. GI pipe (dia. wise) 135. HDPE Pipe 136. MSERW Pipe 137. DI pipe Report Remarks (whether tests are Availabili Conducted as per respective IS code ty approved Status Provision so not) QAP) (yes/No) M25 Yes Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Not provided by DIA. No 138. Cement Birla Uttam Yes 139. Steel Tata Tiscon Yes 140. Aggregate/ Sand Yes 141. Bricks No 142. CC Cube No 143. Water test report No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 211 of 112 Availability of Register on site: Material register Site order book : Not provided by DIA. : Not provided by DIA. Test register/Report: Not Provided by DIA. Concrete Register : Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 212 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Work is stopped Depth of trench observed 780mm. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 213 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Make of HDPE pipe is “Vectus”. XX. Scheme: SadhauliPumping water Supply scheme, Block-Roorkee. Generalinformation Nameofscheme/subscheme Sanctionedcost (InRs.) Contractbondcost (inRs.) DateofStart Dateofcompletion SadhauliPumpingwater supply scheme. 143.69Lacs. Not provided by DIA. NotprovidedbyDIA. NotprovidedbyDIA. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 214 of 112 10% Physical progress(in%) Financialprogress(in%) Sh.Vivek Ravi (A.A.E.) NameofEE/AE/JEwith ContactNo. Sh.HimanshuKaushik, AdityaThapliyal Nameof TPIEngineer/mobileno. Pumpingwater supplyscheme. Typeofscheme 1stVisit Report. Lastreported Nil. ATRprovidedtilldate. currentstatusofwork(Running/completed Running. ) Anyotherdetail PhysicalProgress S.N o 1 Proposed Totalquant Quantity ityExecute aspercont d tilldate ractbond Item HDPE Pipeline Not Not provided provided by DIA. by DIA. Execute dthismo nth Remarks - HDPE Pipes not stocked properly at site which may result in damage of pipes. Scopeofwork/Descriptionofworks S.No ItemDetails Unit 1. Providingand layingof pipes 63mm Mtr. S.No 75mm Mtr. 90 mm Mtr. 110 mm Mtr. ItemDetails Unit pipeline 3. Valves Asper DPR propos alQty. Asper contract bondQt y. Not provided Notpro vided Not provided Not provided As per DPRprop osal Qty. Not provided Notpro vided Not provided Not provided As percon tract bond Qty. Not provided Not provided Asper actual (MB)Qty. Comment regarding qualityof work Workstarted. As peractual (MB) Qty. Commentrega rdingquality of work evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 215 of 112 80mm Nos. 100mm Nos. 4. Airvalve 25mmdia 5. House holdconn ection 6. 7. 8. 9.. Roadcutting Nos. Nos. cum Road Cum reinstatement Constructiono Each f pumphouse Risingmain Mtr 10. Boundarywall Nos Not provided Not provided Not provided Notpro vided Not provided Not provided Not provided Notpro vided Not provided Not provided Not provided Not provided Not provided Not provided Not provided Not provided Notpro vided Notpro vided Worknotstarted. Quality of work is not as per specifications. Procurement pending. Worknot started. Complianceforlastobservationsreported S. No 1. Item NIL Observationslastreported NIL Compliancereported NIL evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 216 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Materialtesting status(Labtest /MTC) S. Make: Nameof Material Reportav ailability AsPerper approved QAP no conducted asperrespectiveIScode) 1. Designmix report No No 2. GIpipe (dia.wise) NA NA 3. HDPEPipe NarendraPl NO ast 4. DIpipe NA 5. Cement Birla Uttam No 6. Steel Not available at site. No 7. Aggregate Yes No 8. Bricks Yes Yes 9. CC Cube Yes No 10. Watertestreport Yes No 11. NDTtest(ifany) NA Remarks(whether testsare NA NA Tests to be conducted as per IS10262:2009andIS456:200 0& Frequencyofteststobeconducteda sperspecifications. TeststobeconductedasperIS1239 (Part I):2004&IS:10748:2004with Amnd-5,Grade2 TestsconductedasperISCodeIS498 4(1995) &Frequencyof tests to be conductedasperspecifications. TestsconductedasperISCode IS8329 &Frequencyofteststobeconductedas perspecifications. TestsconductedasperISCodeIS 8182:2013 & Frequency of tests to beconductedas per specifications. TestsconductedasperISCodeIS 1786:2008 & Frequency of tests to beconductedas per specifications. TestsconductedasperISCodeIS 383:2016&Frequencyofteststobe conductedas per specifications. TestsconductedasperISCode 1077:1992 & Frequency of tests to beconductedas per specifications. As per IS Code IS 10086:1982 &Frequencyofteststobeconducted as perIS456:2000. TestreportnotprovidedbyDIAandt eststo beconducted asperIS 10500:2012 NA evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 217 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Availabilityof Registeronsite: Material register :Not provided by DIA.Siteorderbook :Not provided by DIA.Testregister provided by :Not DIA.ConcretingRegister:Not providedbyDIA, ConclusionandSuggestions: - Batch Report no. to be provided in the HDPE Pipe Available at site as per Test reportssubmitted . HDPE Pipes not stacked properly at site which may result in damage of pipes. No Index plan provided by DIA. Backfilling should be done in layers and proper compaction should be done in mechanicalmeans. Note: All concrete mixers to be attached with Weigh Batcher machine and volumetricconcretearenot acceptable. PhotographsofInspection Com ment s HDPE pipe stacking at site. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 218 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT HDPE pipe make“NarendraPlast” Depth of trench checked at site and found as per standard and specification. Depth- 940mm evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 219 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Depth of HDPE pipe945mm Excavation of HDPE pipeline in progress. I. Scheme: Peetpur pumping Water supply Scheme. Block- Laksar. General information evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 220 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Name of scheme/sub scheme Name of DIA Sanctioned cost(In Rs.) Contract bond cost(in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Peetpur Pumping water supply scheme. (99 EE/JJM/2022-23) MD UJS 142.67Lacs. 134.55 Lacs. 12-05-2022 12-05-2023 88% 87.52 Sh. Vinod Kumar Sh. Pervez Pumping. 1st visit @June-23 No Running. - Note:Work is stopped due to land dispute for few months. Physical Progress S.No. Item 2 OHT 150kl, 18m staging Pipeline work 3 FHTC 1 Proposed Quantity as per contract Bond Total quantity Executed till date Executed This month 01 01 01 3200 0 500 0 5613 540 Remarks Work is stopped Work is stopped Work is stopped Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. ZONE-I 1 2 3 4 5 Construction of Boundary wall Rmt. MS Gate Excavation in soil mixed with shingle boulders etc. MSERW pipe 100 mm D.I. Sluice/ Gate Valve 125 mm dia No. Cum. Not provided by DIA 40 01 16.20 Mtr. No Not provided by DIA 30 02 Not provided by DIA Comment regarding quality of work evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 221 of 112 6 Following size of CI/DI DF sluice valves A 50 mm No 01 B 65 mm No 01 7 Chamber No 04 8 OHT 150kl, 18m staging Dismantling of CC pavement Per Kl 01 9 10 Excavation in pipe line Cum 112.26 Cum 2525.85 11 Construction of Unreinforced, CC Cum pavement 12 Providing and laying of HDPE pipes A 63 mm Mtr. 112.26 4106 B 75 mm Mtr. 521 C 90 mm Mtr. 221 D 110 mm Mtr. 179 E 140 mm Mtr. 586 House hold connection No. 540 13 Not provided by DIA Physical Measurement checking status as per scope: S. No . 1 2 3. Item Unit OHT 150kl, 18m staging Pipeline work FHTC No. No. Mtr. As per tender/co ntract bond Qty. 01 As per actual (MB) %age complet ed Qty. Qty. 70% 60% 90% 5613 540 Remarks about quality Compliance for last observations reported S. No 1. Item NIL Observations last reported NIL Material testing status (Lab test/MTC) Compliance reported NIL evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 222 of 112 147. MSERW Pipe Report Remarks (whether tests are Availabili Conducted as per respective IS code ty approved Status Provision so not) QAP) (yes/No) M-30 & No Tests to be conducted as per IS 10262:2009 M-25 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Yes No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. Yes No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. Yes No Not provided by DIA. 148. DI pipe Yes No 149. Cement OPC 43Grade No S. No. Name of Material Make as (as per scope of work) Per 144. Design mix report 145. GI pipe (dia. wise) 146. HDPE Pipe No 150. Steel 151. Aggregate/ Sand 152. Bricks Yes No (10mm&20 mm) No 153. CC Cube No 154. Water test report No Availability of Register on site: Material register Site order book : Not provided by DIA. : Not provided by DIA. Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Not provided by DIA. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 223 of 112 Test register/Report: Not Provided by DIA. Concrete Register : Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 224 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Work is stooped due to land dispute evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 225 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Taps not provided in all FHHTC. IV. Scheme: Rohalki Dayalpur Water supply Scheme. Block- Bhagwanpur. General in formation Name of scheme/subsch0eme Sanctioned cost(In Rs.) Contract bond cost(in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer / mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Physical Progress Rohalki Dayalpur Pumping water supply scheme. (91/EE./JJM/2022-23) 139.41 Lacs. 114.56 Lacs. 22-12-2021 23-12-2022 95 % 86.51% Sh. Vivek Ravi Sh. Pervez Pumping. 1st visit @June-2023 No Running. - evision:Iss 01 Effective as of 17.05.2023 ev: 0 oc No. M 20 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 226 of 112 S. No 9. Item Proposed Quantity as per contract bond Total quantity Executed till date OHT 01 Nos. 01 Nos. 01 Nos. 01 Nos. 01 Nos. 01 Nos. 5490Mtr. 5490Mtr. 481 Nos 481Nos 90Mtr 81Nos Pump house Repairing work 11. Pipeline work 12. FHTC 10. Executed this month Remarks Completed Work in progress Completed Completed Scope of work /Description of works S. No Item Details Providing and laying of pipes IV. 63 mm V. 75 mm VI. 90mm VII. 110mm VIII. 140mm Excavation of 29. pipe line 30. Valves V. 50&65 mm House hold 31. connection 32. Road cutting Road 33. reinstatement Electrification of tube well 34. & pump house Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. Comment regarding quality of work 28. 35. 36. 37. 38. 39. Repair of pump house RCC over Head Tank, 100 kl Rising main Boundary wall Chamber Mtr. Mtr. Mtr. Mtr. Mtr. Cubic. M Not provided by DIA 3993.00 870.00 350.00 151.00 125.00 2058.75 Completed Not provided by DIA Completed Nos 2.00 Nos 481 Completed Cum 185.95 Completed Cum. 185.95 Completed Job 1 Completed Each Not provided by DIA 1 Not provided by DIA Completed Each 1 Completed Mtr 30 Completed Mtr. 0 Completed Nos 2 Completed Physical Measurement checking status as per scope: evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 227 of 112 1 OHT No. As per tender/co ntract bond Qty. 01 2. HDPE Pipeline Mtr. 5490 3. FHTC No. 481 S. No. Item Unit As per actual (MB) %age complet ed Remarks about quality Qty. 100% Completed 99% Completed Qty. Completed Compliance for last observations reported S. No 1. Item Observations last reported No No Compliance reported No Material testing status (Lab test/MTC) S. no 13. Name of Material (as per scope of work) Design mix report Make(as Report Remarks (whether r tests are Per availability Conducted as per respective I S code approved QAP) Status (yes/No) Provisions or not) NA 14. G I pipe (dia .wise) Jindal Hisar NA Yes Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Test Reports Submitted 15. HDPE Pipe APOLLO Yes Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Test Reports Submitted 16. MSERW Pipe Jindal Yes Test Reports Submitted 17. DI pipe NA NA 18. Cement CCI Yes 19. Steel NA NA 20. Aggregate/ Sand NA Yes Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications.Test Reports Submitted Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications.NA Tests conducted as per IS Code IS evision:Iss 01 Effective as of 17.05.2023 ev: 0 oc No. M 20 Page 228 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT 21. Bricks NA Yes 22. CC Cube NA NA 23. Water test report NA NA 24. NDT test(if any) NA NA 383:2016 & Frequency of tests to be conducted as per specifications.Test Reports not Submitted Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications.Test Reports Submitted As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012 NA Availability of Register on site: Material register Site order book Test register/Report Concrete Register : Not provided by DIA. : Not provided by DIA. : Provided by DIA : Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 229 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Chamber not prepared yet. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 230 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Clamp fixed without applied of anticorrosive paint. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 231 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Railing observed damaged. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 232 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Leakage observed in OHT. II. Scheme: Raipur Darera Pumping water Supply scheme. Block- Bahdrabad. General information Name of scheme/sub scheme Name of DIA Sanctioned cost(In Rs.) Contract bond cost(in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Raipur Darera pumping water supply scheme(154/E.E./JJM/2022-23) MD UJS 134.28Lacs. 126.59 Lacs 52% Sh. Parshant Kothari Sh. Pervez. evision:Iss 01 Effective as of 17.05.2023 ev: 0 oc No. M 20 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 233 of 112 Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Pumping Water Supply Scheme. 1st visit @May-23 NA Running - Physical Progress Item Propose Quantity as per contract bond Total quantity Executed till date Executed this month Remarks 1. Distribution pipe line 2. OHT 01 01 01 Work in progress 3. Pump house 01 01 01 Work in progress Scope of work /Description of works S. No Item Details As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. Comment regarding quality of work 1 2 Providing and laying of HDPE pipes I. 63 mm II. 75 mm III. 90 mm IV. 110 mm V. 140 mm VI. 160 mm Excavation of pipe line Excavation in Soil mixed with boulder 3 Valves and chamber I. 50 mm II. 65mm Unit Mtr. Mtr. Mtr. Mtr. Mtr. Mtr. Cum Not provided by Not provided by DIA Work in progress Work in progress Cum Work in progress Nos Nos. Not provided by DIA Work not started. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 234 of 112 S. No 4 5 6 7 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Item Details Unit Air valve 25mm dia Nos. House hold connection Road cutting As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. Work not started. Nos Cum Comment regarding quality of work Not provided by DIA Work in progress Work in progress Tube well Job Electrification of pump house No Electrification of boundary wall RM Work in progress Construction of pump house No MS gate No. Work in progress Work not started. 8 9 10 Work not started. 11 12 13 14 15 16 17 18 19 20 21 22 23 RCC over Head Tank, 300 KL OHT staging 18 mtr. Chamber Drilling of borehole MSERW fin cut plain pipe 300 mm MSERW fin cut slotted pipe 300 mm Pea Gravel CFM Air compressor Geological survey Supply of submersible 1x3x16 sq.mm Supply of aluminum armored 35sq.mm 3.5 core MSDI clamp set 150 mm Earth work in Work not started. Per Kl Nos Per Mtr. Per Mtr. Completed Per Mtr. Completed Cum Hrs. Completed Job Per Mtr. Per Mtr. Set Cum Not provided by DIA evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 235 of 112 S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. excavation by mechanical means / manual means Comment regarding quality of work Brick work Cum Work in progress Work not started. CC flooring Sqm Work not started. 24 25 Physical Measurement checking status as per scope: S. No Item Unit 1 OHT No. As per tender/co ntract bond Qty. 01 2 3 Pipe line Pump House M No 01 01 As per actual (MB) %age completed Qty. Qty. - 60% - 80% 10% Remarks about quality Complianceforlastobservationsreported S. No Item NIL 1. Observationslastreported NIL Compliancereported NIL Material testing status (Lab test/MTC) S.No 1. Name of Make Report Remarks (whether tests are Materials (as per (As per availability conducted as per respective IS code scope of work) approved status provisions or not) QAP) (yes/No) yes Tests to be conducted as per IS Design mix report (M-25 & M-30) 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications evision:Iss 01 Effective as of 17.05.2023 ev: 0 oc No. M 20 Page 236 of 112 S.No TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT 4. Name of Make Report Remarks (whether tests are Materials (as per (As per availability conducted as per respective IS code scope of work) approved status provisions or not) QAP) (yes/No) NA No Tests to be conducted as per IS 1239 GI pipe (dia. wise) (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. JOSEIM No Tests conducted as per IS Code IS HDPE Pipe 4984 (1995) & Frequency of tests to be conducted as per specifications.Not provided by DIA. JINDAL No Not provided by DIA. MSERW Pipe 5. DI pipe NA No 6. Cement OPC 43 NA Grade No 7. Steel NA No 8. Aggregate 10 mm 20mm Yes 9. Bricks Yes 10. CC Cube M-25 11. Water test report No 12. Development of B/W by O.P. unit & compressor unit NDT test(if any) No 2. 3. 13. No No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications.Not provided by DIA. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications.NA Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012NA Not provided by DIA. NA Availability of Register on site: Material register :Work not started. Site order book :Work not started. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 237 of 112 Test register TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT :Work not started . Concreting Register : Work not started Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 238 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Photographs of Inspection Comments Access not provided to reach at working spot. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 239 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT PPEs not provided to workers. I. Scheme: Subhashgarh Water supply Scheme. Block- Laksar. General information evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 240 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Subhashgarh Pumping water supply scheme. (157 EE/JJM/2022-23) MD UJS 132.15Lacs. 115.77 Lacs. 18-08-2022 31-03-2023 40% 35% Sh. Deepak Bhatt Sh. Pervez Pumping. 1st visit @May-23 NA. Running. - Physical Progress S.No. 1 Item Proposed Quantity as per contract bond 01 OHT 50 KL OHT Total quantity Executed till date - Executed This month - staging 18 mtr. 2 Pipeline work 3 Pump House 7183 01 3000 1000 01 01 Remarks Work not started Work in progress Work in progress Scope of work /Description of works S. No 1 2 3 4 5 6 Item Details Unit Construction of Boundary wall Rmt. MS Gate Excavation in soil mixed with shingle boulders etc. MSERW pipe 100 mm D.I. Sluice/ Gate Valve 80 mm dia Following size of CI/DI DF sluice valves No. Cum. As per DPR proposal Qty. Not provided by DIA As per contract bond Qty. 60 01 16.20 Mtr. No Not provided by DIA 30 02 As per actual (MB) Qty. Not provided by DIA Comment regarding quality of work evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 241 of 112 A 50 mm No 01 B 65 mm No 01 7 Chamber No 04 8 OHT 50kl, 18m staging Dismantling of CC pavement Per Kl 01 9 10 Excavation in pipe line Cum 179.58 Cum 3232.35 11 Construction of Unreinforced, CC Cum pavement 12 Providing and laying of HDPE pipes A 63 mm Mtr. 124.58 5414 B 75 mm Mtr. 800 C 90 mm Mtr. 461 D 110 mm Mtr. 81 E 140 mm Mtr. 427 House hold connection No. 342 13 Not provided by DIA Physical Measurement checking status as per scope: S. No . 1 2. Item Unit OHT 50 KL OHT staging 18 mtr. Pipeline work No. As per tender/co ntract bond Qty. 01 As per actual (MB) %age complet ed Qty. Qty. 0% Mtr. Remarks about quality 40% 7183 3 Pump House No. 60% 01 Compliance for last observations reported S. No 1. Item NIL Observations last reported NIL Compliance reported NIL evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 242 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per 155. Design mix report 156. GI pipe (dia. wise) 157. HDPE Pipe 158. MSERW Pipe Report Remarks (whether tests are Availabili Conducted as per respective IS code ty approved Status Provision so not) QAP) (yes/No) NA Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Apollo Yes Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Not provided by DIA. 159. DI pipe No 160. Cement No 161. Steel(8mm,10mm& 12mm) SAIL Fe 500 Yes 162. Aggregate/ Sand 163. Bricks Yes Gagan Yes 164. CC Cube No 165. Water test report No Availability of Register on site: Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Not provided by DIA. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 243 of 112 Material register Site order book TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT : Not provided by DIA. : Not provided by DIA. Test register/Report: Not Provided by DIA. Concrete Register : Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 244 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT ` Photographs of Inspection Comments evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 245 of 112 XXI. Scheme: RaheempurPumping water Supply scheme, Block-Roorkee. Generalinformation RaheempurPumpingwater supply scheme. 130.74Lacs. Sanctionedcost (InRs.) 122.99 Lacs. Contractbondcost (inRs.) NotprovidedbyDIA. DateofStart NotprovidedbyDIA. Dateofcompletion 90 % Physical progress(in%) 90% Financialprogress(in%) Sh.HimanshuTyagi (A.A.E.) NameofEE/AE/JEwith ContactNo. Sh.HimanshuKaushik, AdityaThapliyal Nameof TPIEngineer/mobileno. Pumpingwater supplyscheme. Typeofscheme 3RDVisit Report. Lastreported Nil. ATRprovidedtilldate. currentstatusofwork(Running/completed Running. ) Anyotherdetail Nameofscheme/subscheme PhysicalProgress S.N o Item Proposed Totalquant Quantity ityExecute aspercont d tilldate ractbond Execute dthismo nth Remarks evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 246 of 112 1 HDPE Pipeline Not provided by DIA. - - Scopeofwork/Descriptionofworks S.No ItemDetails Unit 1. Providingand layingof pipes 63mm Mtr. S.No 75mm Mtr. 90 mm Mtr. 110 mm Mtr. ItemDetails Unit pipeline 3. Valves 80mm Nos. 100mm Nos. 4. Airvalve 25mmdia 6. House holdconn ection 7. 8. 9. Roadcutting Nos. Nos. cum Road Cum reinstatement Constructiono Each f pumphouse 10. Risingmain Mtr 11. Boundarywall Nos Asper DPR propos alQty. Asper contract bondQt y. Not provided Notpro vided Not provided Not provided As per DPRprop osal Qty. Not provided Notpro vided Not provided Not Provided As percon tract bond Qty. Not provided Not provided Not provided Not provided Notpro vided Not provided Not provided Not provided Not provided Notpro vided Not provided Not provided Not provided Not provided Not provided Not provided Not provided Not provided Notpro vided Notpro vided Asper actual (MB)Qty. Comment regarding qualityof work WorkOon hold. As peractual (MB) Qty. Commentrega rdingquality of work Worknotstarted. Worknotstarted. Procurement pending. Worknot started. evision:Iss 01 Effective as of 17.05.2023 ev: 0 oc No. M 20 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 247 of 112 PhysicalMeasurementcheckingstatusasperscope: S. No Item HDPE Pipeline 1. As pertend Unit er/contr actbond Qty. m Not provid ed by DIA. As perac tual( MB) Qty. %agecom pleted Remarksab outquality Qty. - Not provide d Quality of work is as per specifications. Complianceforlastobservationsreported S. No 1. Item NIL Observationslastreported NIL Compliancereported NIL evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 248 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Materialtesting status(Labtest /MTC) S. Make: Nameof Material Reportav ailability AsPerper approved QAP no conducted asperrespectiveIScode) 1. Designmix report NA NA 2. GIpipe (dia.wise) - - 3. HDPEPipe Apollo NO 4. DIpipe NA NA 5. Cement NA NA 6. Steel NA NA 7. Aggregate NA - 8. Bricks NA NA 9. CC Cube NA NA 10. Watertestreport Yes 11. NDTtest(ifany) NA Remarks(whether testsare No NA Tests to be conducted as per IS10262:2009andIS456:200 0& Frequencyofteststobeconducteda sperspecifications. TeststobeconductedasperIS1239 (Part I):2004&IS:10748:2004with Amnd-5,Grade2 TestsconductedasperISCodeIS498 4(1995) &Frequencyof tests to be conductedasperspecifications. TestsconductedasperISCode IS8329 &Frequencyofteststobeconductedas perspecifications. TestsconductedasperISCodeIS 8182:2013 & Frequency of tests to beconductedas per specifications. TestsconductedasperISCodeIS 1786:2008 & Frequency of tests to beconductedas per specifications. TestsconductedasperISCodeIS 383:2016&Frequencyofteststobe conductedas per specifications. TestsconductedasperISCode 1077:1992 & Frequency of tests to beconductedas per specifications. As per IS Code IS 10086:1982 &Frequencyofteststobeconducted as perIS456:2000. TestreportnotprovidedbyDIAandt eststo beconducted asperIS 10500:2012 NA evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 249 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Availabilityof Registeronsite: Material register :Not provided by DIA.Siteorderbook :Not provided by DIA.Testregister provided by :Not DIA.ConcretingRegister:Not providedbyDIA, ConclusionandSuggestions: - Batch Report no. to be provided in the HDPE Pipe Available at site as per Test reportssubmitted . Improper stacking of HDPE pipes observed at site which may damage the pipes. No work in progress from two months. No representative of contractor found at site. PhotographsofInspection Comment s “APOLLO” make HDPE pipes found at site. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 250 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Improper stacking of HDPE pipes found on site which may damage the pipes. No work in progress since two months. Boring work completed. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 251 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT No representative of contractor found during site visit. No work in progress since two months. Improper stacking of HDPE pipes found on site which may damage the pipes. No work in progress since two months. XXII. Scheme:KhanpurKasauli Pumping water Supply scheme, Block-NarsanGeneralinformation Nameofscheme/subscheme Sanctionedcost(InRs.) Contractbondcost(inRs.) DateofStart Dateofcompletion Physical progress(in%) Financialprogress(in%) KhanpurKasauliPumpingwatersupply scheme.(88/E.E./2022-23) 116.71Lacs. 108.87Lacs 05-05-2022 06-05-2023 90% 85% evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 252 of 112 Sh.HimanshuTyagi A.A.E.) Sh.HimanshuKaushik. Pumpingwatersupplyscheme. 05-01-2023 Not provided till date. Running. NameofEE/AE/JEwith Contact No. NameofTPIEngineer/mobileno. Typeofscheme Lastreported ATRprovidedtilldate. current statusofwork(Running/completed) Anyotherdetail - PhysicalProgress S.N o 1. Proposed Totalquant Quantity ityExecute aspercont dtilldate ractbond Item OHT125KL, 18m staging. 01 Structure work completed. Execute dthismo nth - Remarks Quality of work is as per specifications. Scopeofwork/Descriptionofworks S.No 1. 2. 3. ItemDetails Unit As per DPRprop osal Qty. As percon tract bond Qty. Providingand layingof pipes 63mm 75mm 90mm 110 mm 140 mm 160 mm Excavation ofpipeline Mtr. Mtr. Mtr. Mtr. Mtr. Mtr. Cum.C ubic.m 1437 217 113 223 34 98 1437 217 113 223 34 98 Not providedby DIA. 1082.22 1082.22 Not Done as per providedby specifications. DIA. Valves As peractual (MB) Qty. Commentrega rdingquality of work Quality of work is as per specifications. evision:Iss 01 Effective as of 17.05.2023 ev: 0 oc No. M 20 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 253 of 112 S.No 4. 5. ItemDetails Unit 50mm 65mm 80 mm 100 mm 125 mm 150 mm Airvalve 25mmdia Household connection 6. Nos Nos. Nos. Nos. Nos. Nos. As per DPRprop osal Qty. 02 01 01 01 01 01 As percon tract bond Qty. 02 01 01 01 01 01 Nos. 02 02 No. Nos Nos. 255 255 01 01 162.3 3 162.3 3 162.3 3 03 162.3 3 03 OHT125KL , 18mstaging. 7. Cum Roadcutting 8. Roadreinst atement 9. Chamber Cum. Nos As peractual (MB) Qty. Commentrega rdingquality of work Workis in progress. Not providedby DIA. Workis in progress. Work is in progress. Not provided Work is by DIA. inprogre ss. Qualityof workis as per drawingsandsp ecifications. Not providedby Work in progress DIA. Not providedby Workin progress. DIA. Workin progress. PhysicalMeasurementcheckingstatusasperscope: S. No 1. Item Unit OHT 125KL, 18 m staging S. No 1. Nos. Item NIL As pertend er/contr actbond Qty. 01 As perac tual( MB) Qty. - %ageco mpleted Qty. 95% Observationslastreported NIL Remarksabo utquality Quality of work is as perspecificationsand drawings. Compliancereported NIL evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 254 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Materialtesting status(Labtest /MTC) S. no 1. 2. 3. 4. 5. 6. 7. 8. 9. Make(as Report Remarks(whethertestsare Availabili conductedasperrespectiveI per ty Scode approved Status provisionsornot) QAP) (yes/No) Yes Designmix report Yes Tests to be conducted as per IS10262:2009andIS456:200 0& Frequencyofteststobeconducteda sperspecifications. NA GIpipe (dia.wise) NA TeststobeconductedasperIS1239 (Part I):2004&IS:10748:2004with Amnd-5,Grade2NA NA HDPEPipe TestsconductedasperISCodeIS498 4(1995) &Frequencyof tests to be conductedasperspecifications. NA NA TestsconductedasperISCode IS8329 DIpipe &Frequencyofteststobeconductedas perspecifications. BirlaUttam Yes Testsconductedasper ISCodeIS Cement 8182:2013 & Frequency of tests to beconductedasperspecifications. SAIL Yes Steel Tests conducted as per IS Code IS1786:2008&Frequencyofteststo be conductedasperspecifications. Yes Yes TestsconductedasperISCodeIS Aggregate 383:2016&Frequencyofteststobe conductedasperspecifications. Yes No Testsconductedasper ISCode Bricks 1077:1992 & Frequency of tests to beconductedasperspecifications. Not provided Yes Yes CC Cube As per IS Code IS 10086:1982 &Frequencyofteststobeconducted asper IS 456:2000 NameofMaterial 10. Watertestreport Yes 11. NDTtest(ifany) NA Availabilityof Registeronsite: No NA TestreportnotprovidedbyDIAandt eststo beconducted asperIS 10500:2012 NA evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 255 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Materialregister :Not provided by DIA.Siteorderbook : Not provided by DIA.Testregister : Not provided by DIA.ConcretingRegister: providedbyDIA. Not evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 256 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT ConclusionandSuggestions: - Water test report , MSERW pipe test reports , Strata chart and logbook to be provided forTubewell boringwork byDIA.(E&M Deptt.) Backfilling should be done in layers and proper compaction should be done in mechanicalmeans. Note: All concrete mixers to be attached with Weigh Batcher machine and volumetricconcretearenot acceptable. PhotographsofInspection Comment s Pumphouse paint completed at site and found as per standard and specification. Site visit at OHT. evision:Iss 01 ev: 0 oc No. M 20 Effective as of 17.05.2023 Page 257 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Boundary wall paint work completed Railing work of staircase completed. Clamps in MS-Angle are missing at some places. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 58of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Site visit at OHT. “APOLLO” HDPEpipesatsite. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 59of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT DrawingforOHT. Cementtestreportfrom externallab. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 60of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 10mmaggregatetestreportfromexternal lab. 20mmaggregatetestreportfromexternal lab. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 61of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Coarsesandtest reportfrom externallab. 8mmsteel testreportfromexternal lab. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 62of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 10mmsteel testreportfromexternal lab. 12mmsteel testreportfromexternal lab. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 63of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 16mmsteel testreportfromexternal lab. M-25designmix. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 64of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT M-30Designmix. 7dayscubetestreportfromexternallabforr aftfoundation. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 65of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 28dayscubetestreportfromexternallabforr aftfoundation. 7dayscubetest reportfor1st braceofOHT. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 66of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 28dayscubetest reportfor1st braceofOHT. 7dayscubetestreportforColumnsabove 2ndbraceof OHT. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 67of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Top dome cube test report from external lab. Bottom dome cube test report from external lab. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 68of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT I. Scheme:Lawwa Water supply Scheme. Block-Bhagwanpur . General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Lawwa Pumping water supply scheme. (145EE/JJM/2022-23) MD UJS 105.80Lacs. 98.92 Lacs. 19-07-2022 18-07-2023 20% 0% Sh.Vivek Ravi Sh. Pervez Pumping. 1st visit @June-23 NA. Running. - Physical Progress S.No. Item 1. Pipeline work 2. FHTC 3. OHT 4. Pump House Proposed Quantity as per contract bond 3288 145 01 01 Total quantity Executed till date Executed This month 500 500 0 0 01 0 0 0 Remarks Work in progress Work not started Work is stopped Work not started Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. Not provided by DIA 1 Following Size of CI/DI DF sluice valves A 50 mm No B 65 mm No C 80 mm No As per contract bond Qty. 04 02 04 As per Comment actual regarding (MB) quality of work Qty. Not provided by DIA Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 69of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT D 125 mm No G Air valve-25mm dia No 02 2 Chamber No 13 3 Dismantling of CC pavement Cum 213.06 4 Excavation in pipe line Cum 1775.52 5 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes Cum 213.06 6 01 A 63mm Mtr. 2371 B 75mm Mtr. 366 C 90 mm Mtr. 466 D 110mm Mtr. 60 E 140mm Mtr. 25 7 50KL OHT Staging 18m No. 8 House hold connection No. 145 9 Pump House No. 01 10 Boundry wall Rm 60 01 Physical Measurement checking status as per scope: S. No . Item Unit 1. Pipeline work Mtr. 2. FHTC 3 4 As per tender/co ntract bond Qty. As per actual (MB) %age complet ed Remarks about quality 3288 Qty. 0 Qty. 2% Nos 145 0 0% OHT Nos 01 0 5% Work is stopped. Pump House Nos 01 0 0% - - Compliance for last observations reported S. No 1. Item Observations last reported Compliance reported NA NA NA Material testing status (Lab test/MTC) Revision: Issue 01 Rev:0 DocNo. QM17 S. No. Effective asof 05.01.2023 Page2 70of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Name of Material Make as (as per scope of work) Per 166. Design mix report 167. GI pipe 15mm Dia 168. HDPE Pipe-90 mm 169. MSERW Pipe 170. DI pipe 171. Cement 172. Steel Report Remarks (whether tests are Availabili Conducted as per respective IS code ty Approved Status Provision so not) QAP) (yes/No) M-25 & M- No Tests to be conducted as per IS 10262:2009 30 and IS 456: 2000 & Frequency of tests to be conducted as per specifications.(Reports Submitted) No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Tests to be conducted as per IS 4270:2001 Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. 173. Aggregate/ Sand No 174. Bricks No 175. CC Cube No 176. Water test report No Availability of Register on site: Material register : Not Available at site. Site order book : Not Available at site. Test register/Report : Not Available at site. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 71of77 Concrete Register TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT : Not Available at site. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 72of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Pipe line work just start. OHT work is stopped. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 73of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Depth of trench of HDPE pipe is observed 1020mm. I. Scheme:Gin Mohmad Water supply Scheme. Block-Bahadrabad . General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress (in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Gin Mohmad Pumping water supply scheme. (104 EE/JJM/2022-23) MD UJS 104.63Lacs. 87.16 Lacs. 15-05-2022 11-03-2023 60% 50.21% Sh. Parshant Kothari Sh. Pervez Pumping. 2nd visit @June-23 NA. Running. - Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 74of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Physical Progress S.No. Item 1. Pipeline work 2. FHTC 3. OHT 4. Pump House Proposed Quantity as per contract bond 3104 192 01 01 Total quantity Executed till date Executed This month 2560 2560 192 192 0 0 0 0 Remarks Work in progress Work in progress Work not started Work not started Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. ZONE-I 1 Following Size of CI/DI DF sluice valves A 50 mm No 02 B 65 mm No 01 80 mm No 02 C 125 mm No 01 D Air valve-25mm dia No 02 2 Chamber No 07 3 Dismantling of CC pavement Cum 4 Excavation in pipe line Cum 5 6 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes Cum 201.14 Not provided by DIA 1676.16 201.14 A 63mm Mtr. 2106 B 75mm Mtr. 50 C 90 mm Mtr. 764 D 110mm Mtr. 146 E 140mm Mtr. 38 7 75KL OHT Staging 18m No. 8 House hold connection No. 01 192 Not provided by DIA Comment regarding quality of work Revision: Issue 01 Rev:0 DocNo. QM17 9 Effective asof 05.01.2023 Page2 75of77 Pump House TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT No. 01 Physical Measurement checking status as per scope: S. No . Item Unit 1. Pipeline work Mtr. 2. FHTC Nos 3 OHT Nos 4 Pump House Nos As per tender/co ntract bond Qty. 3104 As per actual (MB) %age complet ed Qty. 0 Qty. 70% 0 80% 01 0 0% 01 0 0 192 Remarks about quality Tab not provided in all FHTC - Compliance for last observations reported S. No 1. Item Observations last reported Compliance reported NA NA NA Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per 177. Design mix report 178. GI pipe 15mm Dia 179. HDPE Pipe-90 mm 180. MSERW Pipe 181. DI pipe Report Remarks (whether tests are Availabili Conducted as per respective IS code ty Approved Status Provision so not) QAP) (yes/No) M-25 & M- No Tests to be conducted as per IS 10262:2009 30 and IS 456: 2000 & Frequency of tests to be conducted as per specifications.(Reports Submitted) No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Tests to be conducted as per IS 4270:2001 Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 76of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT No Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. No Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. 182. Cement 183. Steel 184. Aggregate/ Sand No 185. Bricks No 186. CC Cube No 187. Water test report No Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register : Not Available at site. Site order book : Not Available at site. Test register/Report : Not Available at site. Concrete Register : NA Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 77of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Make of GI pipe is “Jindal” Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 78of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Taps not provided in all FHTC Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 79of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Marking for OHT is being done. I. Scheme:Hasanpur Madanpur Water supply Scheme. Block-Bhagwanpur . General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress (in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Hasanpur Madanpur Pumping water supply scheme. (95 EE/JJM/2022-23) MD UJS 104.63Lacs. 87.16 Lacs. 12-05-2022 11-05-2023 70% 66.63% Sh. Parshant Kothari Sh. Pervez Pumping. 2nd visit @June-23 NA. Running. - Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 80of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Physical Progress S.No. Item 1. Pipeline work 2. FHTC 3. OHT 4. Pump House Proposed Quantity as per contract bond 6236 650 01 01 Total quantity Executed till date Executed This month 6136 2000 640 200 01 01 0 0 Remarks Work in progress Work in progress Work in progress Work not started Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. ZONE-I 1 Following Size of CI/DI DF sluice valves A 50 mm No 13 B 65 mm No 01 C 125 mm No 01 D 100 mm No 01 E 150 mm No 01 D Air valve-25mm dia No 02 2 Chamber No 19 3 Dismantling of CC pavement Cum 4 Excavation in pipe line Cum 5 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes 6 Not provided by DIA 505.12 3180.36 Cum 505.12 A 63mm Mtr. 4919 B 75mm Mtr. 616 C 90 mm Mtr. 157 D 110mm Mtr. 224 E 140mm Mtr. 175 F 160mm Mtr. 145 Not provided by DIA Comment regarding quality of work Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 81of77 7 125KL OHT Staging 18m No. TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 8 House hold connection No. 650 9 Pump House No. 01 10 Boundry wall Rm 50 01 Physical Measurement checking status as per scope: S. No . Item Unit As per tender/co ntract bond Qty. As per actual (MB) %age complet ed Qty. 0 Qty. 70% 1. Pipeline work Mtr. 6236 2. FHTC Nos 650 0 80% 3 OHT Nos 01 0 10% 4 Pump House Nos 01 0 0 Remarks about quality Tab not provided in all FHTC - Compliance for last observations reported S. No 1. Item Observations last reported Compliance reported NA NA NA Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per 188. Design mix report 189. GI pipe 15mm Dia 190. HDPE Pipe-90 mm 191. MSERW Pipe Report Remarks (whether tests are Availabili Conducted as per respective IS code ty Approved Status Provision so not) QAP) (yes/No) M-25 & M- No Tests to be conducted as per IS 10262:2009 30 and IS 456: 2000 & Frequency of tests to be conducted as per specifications.(Reports Submitted) No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Tests to be conducted as per IS 4270:2001 Frequency of tests to be conducted as per Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 82of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT specifications. 192. DI pipe No 193. Cement No 194. Steel No 195. Aggregate/ Sand No 196. Bricks No 197. CC Cube No 198. Water test report No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register : Not Available at site. Site order book : Not Available at site. Test register/Report : Not Available at site. Concrete Register : Available at site. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 83of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Raft foundation ready to cast. Slump found 85mm. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 84of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Birla uttam cement is being done. Taps not provided in all FHTC. Make of steel is “SAIL”. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 85of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 86of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT I. Scheme: Bhurni khatirpur Water supply Scheme. Block- Bhadrabad. General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost(in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Bhurni Khatirpur Pumping water supply scheme. (79 EE/JJM/2022-23) MD UJS 104.3Lacs. 94.81 Lacs. 20-04-2022 21-04-2023 0% 0% Sh. Deepak Bhatt Sh. Pervez Pumping. 1st visit @June-23 NA. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 87of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Running. Current status of work(Running/completed) Any other detail Note:Work not started yet. Physical Progress S.No. 1 Item Proposed Quantity as per contract bond Total quantity Executed till date Executed This month 1.00 OHT 75 KL OHT Work not started Work not started staging 18 mtr. 3. Pipeline work Remarks 3183 Scope of work /Description of works S. No Item Details Unit 12. Construction of Boundary wall Rmt. 13. MS Gate 14. Excavation in soil mixed with shingle boulders etc. 15. MSERW pipe 100 mm 16. D.I. Sluice/ Gate Valve 50 mm dia 17. D.I. Sluice/ Gate Valve 65 mm dia 18. Chamber No. Cum. As per DPR proposal Qty. Not provided by DIA 22. Construction of Unreinforced, CC pavement 23. Providing and laying of HDPE pipes I. 63 mm 12. 60 01 As per actual (MB) Qty. Not provided by DIA 16.20 Mtr. 30 No 01 No 01 No 02 19. OHT 75kl, 18m staging Per Kl 20. Dismantling of CC pavement 21. Excavation in pipe line As per contract bond Qty. 01 Cum Cum Cum 111.41 Not provided by DIA 1432.35 111.41 Mtr. 2187 75 mm Mtr. 239 90 mm Mtr. 351 110 mm Mtr. 286 140 mm Mtr. 120 House hold connection No. 222 Not provided by DIA Comment regarding quality of work Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 88of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Physical Measurement checking status as per scope: S. No . 1 2. Item Unit OHT 75 KL OHT staging 18 mtr. Pipeline work No. As per tender/co ntract bond Qty. 1.00 As per actual (MB) %age complet ed Qty. Qty. 0% Mtr. Remarks about quality 0% 3183 Compliance for last observations reported S. No 1. Item NIL Observations last reported NIL Compliance reported NIL Material testing status (Lab test/MTC) S. No. Name of Material Make as (as per scope of work) Per 199. Design mix report 200. GI pipe (dia. wise) 201. HDPE Pipe 202. MSERW Pipe Report Remarks (whether tests are Availabili Conducted as per respective IS code ty approved Status Provision so not) QAP) (yes/No) No Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Not provided by DIA. 203. DI pipe No 204. Cement No 205. Steel No 206. Aggregate/ Sand No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Not provided by DIA. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 89of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT conducted as per specifications. 207. Bricks No 208. CC Cube No 209. Water test report No Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Register on site: Material register Site order book : Not provided by DIA. : Not provided by DIA. Test register/Report: Not Provided by DIA. Concrete Register : Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 90of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments I. Scheme: Alipur Ebrahimpur Water supply Scheme. Block- Bhadrabad. Generalinformation Name of scheme/subsch0eme Name of DIA Sanctioned cost (In Rs.) Contract bond cost(in Rs.) Date of Start Date of completion Physical progress(in%) Financial progress(in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Alipur Ebrahimpur Pumping water supply scheme. (89.E.E/JJM/2022-23) MD UJS 60.71Lacs. 59.02 Lacs. 06-05-2022 05-05-2023 75% 22.59% Sh. Himanshu Tyagi. Sh. Akhilesh Semwal Pumping. 1st visit @ June-23 No Running. - Physical Progress S.No. Item ProposedQuantit y aspercontract bond Totalquantity Executedtilld ate Executed thismonth Remarks Revision: Issue 01 Rev:0 DocNo. QM17 1 Effective asof 05.01.2023 Page2 91of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 1.00 1.00 1.00 Bottom dome OHT 250 KL OHT staging 18 mtr. 3. Pipeline work 850m 1022.00 450m RCC completed. Work in progress. Scope of work /Description of works S. No Item Details Unit 24. Construction of Boundary wall Rmt. 25. MS Gate 26. Excavation in soil mixed with shingle boulders etc. 27. MSERW pipe 150 mm 28. D.I. Sluice/ Gate Valve 150 mm dia 29. Chamber No. Cum. 30. OHT 250kl, 18m staging 31. Dismantling of CC pavement 32. Excavation in pipe line 33. Construction of Unreinforced, CC pavement 34. Providing and laying of HDPE pipes I. 63 mm 12. House hold connection As per DPR proposal Qty. As per contract bond Qty. Not provided by DIA 80.00 1.00 As per actual (MB) Qty. Not provided by DIA 18.00 Comment regarding quality of work Work in progress Work in progress Work completed. Mtr. 30.0 No 2.00 No 2.00 Work in progress 250.00 Work in progress Per Kl Cum Mtr. Not provided by DIA Work in progress 40.88 511.00 Work in progress Not provided by DIA Work in progress Work in progress Cum 40.88 Mtr. 1022.00 Work in progress No. 175.00 Work in progress Physical Measurement checking status as per scope: S. No . 1 2. Item OHT HDPE Pipeline Unit No. Mtr. As per tender/co ntract bond Qty. 01 1022..00 Compliance for last observations reported As per actual (MB) %age complet ed Qty. Qty. 95% 85% 01 Not provided by DIA Remarks about quality Work in progress Work in progress. Revision: Issue 01 Rev:0 DocNo. QM17 S . N o Effective asof 05.01.2023 Page2 92of77 Item 1. OHT 2. Curing Tank 3. Safety TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Observationslastreported Compliancereported Wooden cover block has been used in bottom Compliance not done dome Grass has accumulated all around the Curing tank Compliance not done and curing tank has not been clraned. Safety Net is not being used during the construction Compliance not done of OHT. Its observed that workers were not wearing Safety PPEs. High Risk observed during work at the site. Bamboo is being used for the staging work for construction of OHT instead of MS S/Pipes. Materialtestingstatus (Labtest/MTC) 1. Design mix report 2. GI pipe (dia .wise) 3. HDPE Pipe 4. MSERW Pipe Report Remarks (whethertestsare Availabili conductedasperrespectiveIScode ty approved Status provisionsornot) QAP) (yes/No) M-30 & Yes Tests to be conducted as per IS 10262:2009 M-25 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Yes No Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. Yes No Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications.Not provided by DIA. Yes No Not provided by DIA. 5. DI pipe Yes 6. Cement 7. Steel OPC Yes 43Grade Birla Uttam SAIL 550D No 8. Aggregate/ Sand 9. Bricks S. No. NameofMaterial (asperscopeof work) Makeas Per No Yes Yes (10mm&20 mm) Yes No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications.Not provided by DIA. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications.Not provided by DIA. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 93of77 10. CC Cube Yes 11. Water test report Yes TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT No As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA No Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Availability of Registeronsite: Material register Site order book :Not provided by DIA. :Not provided by DIA. Test register/Report :Not Provided by DIA. Concrete Register :Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 94of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Photographs of Inspection Comments Bricks are being used as shuttering which is not satisfactory practice. Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 95of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Spacing of stirrups is not as per drawing/specification. Status of OHT Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 96of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT .Rusted steel is being used at site. X c h e m e : T a n Stacking of material is not as per specification. d a B h a n e r a W a ter supply Scheme, Block-Narson. Generalinformation Nameof scheme/subscheme TandaBhaneraPumpingwatersupplyscheme. (2201/EE./JJM/2021-22,03-12-2021) Revision: Issue 01 Rev:0 DocNo. QM17 Effective asof 05.01.2023 Page2 97of77 TUVSUDSOUTHASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 39.02Lacs. Sanctionedcost(InRs.) 34.40Lacs. Contractbondcost(inRs.) 03-12-2021 DateofStart 03-04-2022 Dateofcompletion 25 % Physicalprogress(in%) 15% Financialprogress(in%) Sh.HimanshuTyagi NameofEE/AE/JEwith ContactNo. Sh.HimanshuKaushik. NameofTPIEngineer/mobileno. Pumping. Typeofscheme NA Lastreported N0 ATRprovidedtilldate. CurrentStatusofwork(Running/completed) Workis Stoppedsincelast67Months(Dueto LocalIssue) Anyotherdetail PhysicalProgress S.No Item Proposed Quantityas percontractbond 1 OHT 2 Pumphouse Existing 3. Boundary wall Existing Existing Totalquant ityExecute d tilldate Executedt hismonth - - - - - - Remarks Work is Stopped Work is Stopped Work is Stopped Scopeofwork/Descriptionofworks S.No ItemDetails Unit Asp erD PR proposa lQty. 1.DismantlingofWork DismantlingofCCPavement 1. sbyMechanicalmeansusing pneumatictoolsbreakingtopi ecenotexceeding.02cumvol umeandstockPillingatdesig nedlocationanddisposalofdi CU M smantleuptoaleadof1m 76.05 As percon tractb ondQt y. 76.05 As per actual(MB) Qty. Not ProvidedbyDIA Commentre gardingqual ityofwork - Revision: Issue01 Rev:0 Doc No. QM37 Effective asof 29-06-2023 Page 1of20 TUVSUDSOUTH ASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT 2.Restorationof Road Roadreinstatement Cum. Not ProvidedbyDIA 76.0 5 76.0 5 - 612 612 - 3.EarthWork 3.1 Excavationinsoilmixed withsingle,Bajari,bouldersord cum inarynormalsoil 4.ProvidingandLayingofPipeline 4.1 140mmHDPEPipe RM 300 300 - 4.2 90mmHDPEPipe RM 600 600 - 4.3 63mmHDPEPipe RM 800 800 - No. 600 600 - 01 1 - No 1 1 - No 1 1 - 5.WaterConnections 5.1 No.ofFHTC’S 6.Servovoltagestabilizer 6.1 50KVAServovolta gestabilizer Job 7.ChlorinationPump SupplyandInstallationofC hlorinationPump 8.SubmersiblePump 8.1 Supply,Installationand Commissioningof 20HPSubmersiblePump Revision: Issue01 Rev:0 Doc No. QM37 Effective asof 29-06-2023 Page 1of20 TUVSUDSOUTH ASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT PhysicalMeasurementcheckingstatusasperscope: S . N o. 1 2. Item Unit OHT150KL,18 m Staging As pertend er/contr act bond Qty. As perac tual( MB) %age compl eted Qty. Qty. No Exi sti ng - 00% Mtr. 1700 - 70% HDPEPipeline 3. PumpHouse No. Exi sti ng - 00% 4. Boundarywall M Existing - 00% Remarksaboutquality Hydrostatic testing to bedonebeforereinstate ment work. Complianceforlastobservationsreported S. No Item 1. NIL Observationslastreported NIL Compliancereported NIL Revision: Issue01 Rev:0 Doc No. QM37 Effective asof 29-06-2023 Page 1of20 TUVSUDSOUTH ASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Materialtestingstatus(Labtest/MTC) S. no 1. 2. NameofMaterial (asperscopeo fwork) Make(as Per Report availability Remarks(whethertestsare conductedasperrespective IScode provisionsornot) approved Status QAP) (yes/No) NA Designmix report NA Tests to be conducted as per IS10262:2009andIS456:200 0& Frequencyofteststobeconductedas perspecifications. No GIpipe(dia.wise) Yes TeststobeconductedasperIS1239 (Part I):2004&IS:10748:2004with Amnd-5,Grade2 3. HDPEPipe 4. DIpipe Narendra No Plast, Makedoes notmentio n in TestReport NA No 5. Cement NA Yes 6. Steel NA Yes 7. Aggregate/Sand NA Yes 8. Bricks NA Yes 9. CC Cube NA NO 10. Watertestreport NA Yes 11. NDTtest(ifany) NA NA Testsconducted asperISCodeIS4984(1995)&Frequ encyofteststobeconducted as per specifications. TestReportsNot Submitted. TestsconductedasperIS CodeIS8329 &Frequencyof tests tobe conductedasperspecifications. TestsconductedasperISCodeIS 8182:2013&Frequencyofteststobe conductedas perspecifications. TestsconductedasperISCodeIS 1786:2008&Frequencyofteststobe conductedas perspecifications. TestsconductedasperIS Code IS 383:2016&Frequencyofteststobe conductedas perspecifications. TestsconductedasperISCode 1077:1992&Frequencyofteststobe conductedas perspecifications. As per IS Code IS 10086:1982 &Frequencyofteststobeconducteda sper IS 456:2000 Not provided ofstaircase,bottomdome,verticalwal l andtopdome. Testreportnotprovided byDIAand tests to be conducted as per IS10500:2012TestReportsprovi ded NA Revision: Issue01 Rev:0 Doc No. QM37 Effective asof 29-06-2023 Page 1of20 TUVSUDSOUTH ASIA REAL ESTATE & INFRASTRUCTUREPROJECTVISIT/ MONTHLYREPORT Availabilityof Registeronsite: Material register : DIA.Site order book DIA.Testregister Not provided by : Not provided by :Not providedbyDIA.ConcreteRegister:Not provided byDIA. ConclusionandSuggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site forinspection. SafetyPPEsKitis mustatsitefortheconstructionworkers Safety Display boards & Barricades must be displayed at all workplaces near the public conveyancelocations. TPIAshould be informed beforeanymajoractivityto be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification.Excavatedsoil near theedges of thetrench should be300 mm awayfrom the trenchedges. HydrotestingofthePipeline worksand waterretainingstructures tobedoneas perspecifications. ProperprocedureforRoadrestoration workto be followed. E&MEquipmentto bepostinspected atsitetoo. FHTCConnectionworksto bedoneas perdrawingandas perspecifications. Backfillingwork tobedonein layersand properlycompacted. Allthetestreportsofthe constructionmaterialsistobeavailableat site andproperlymaintained. Testregisterstobemaintainedatsite. Backfilling should be done in layers and proper compaction should be done in mechanicalmeansforpipelineand OHT work. Note: All concrete mixers to be attached with Weigh Batcher machine and volumetric concreteis notacceptable. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 302 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT PhotographsofInspection Comment s ExtensionNipplelengthisverys mallandneedtobe rectified. Vertical pipe length for FHTC connection ismore than as specified in specification. Need toberectified. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 303 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT FHTCPipelineisnotGroutedpr operlyandneedto be rectified. FoundSatisfactoryFHTCCon nection. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 304 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT ExtensionNipplelengthisverys mallandneedtobe rectified. Verticalpipeisnotproperlyclam pedtothewalland need to berectified. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 305 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT ExtensionNipplelengthisverys mallandneedtobe rectified. FoundSatisfactoryFHTCCon nection. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 306 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT ExtensionNipplelengthisverys mallandneedtobe rectified. ExtensionNipplelengthisverys mallandneedtoberectified. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 307 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Extension Nipple length is very small and needto be rectified. Also Vertical pipe is not properlyclamped. ExtensionNipplelengthisverys mallandneedtoberectified. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 308 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Verticalpipeis notproperlyclamped. FHTCConnectioninverticalpip enotdoneasperspecification. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 309 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT FHTCConnectionisfoundtobe satisfactory. FHTCConnectionisnotdonea sspecifiedinspecification. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 310 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT NarendraPlastHDPE PipeusedatSite. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 311 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT 90MMHDPEPipeTestReport Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 312 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT 110 MMHDPEPipeTestReport Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 313 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT 63MMHDPEPipeTestReport Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 314 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT 160 MMHDPEPipeTestReport I. Scheme: Bahadarpur Jatt Water supply Scheme. Block-Bahadrabad . Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 315 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT General information Name of scheme/sub scheme Name of DIA Sanctioned cost (In Rs.) Contract bond cost (in Rs.) Date of Start Date of completion Physical progress (in%) Financial progress (in%) Name of EE/AE/JE with Contact No. Name of TPI Engineer/mobile no. Type of scheme Last reported ATR provided till date. Current status of work(Running/completed) Any other detail Bahadarpur Jatt Pumping water supply scheme. (51 EE/JJM/2022-23) MD UJS 29.03Lacs. 27.92 Lacs. 18-08-2022 31-03-2023 % 61% Sh. Vishal Yadav Sh. Pervez Pumping. 2nd visit @May-23 NA. Running. - Note: Site has been completed and final visit to be done after getting compliances of ATR. Physical Progress S.No. Item 1. 2. Pipeline work FHTC Proposed Quantity as per contract bond 700 331 Total quantity Executed till date Executed This month 680 320 - Remarks Scope of work /Description of works S. No Item Details Unit As per DPR proposal Qty. As per contract bond Qty. As per actual (MB) Qty. ZONE-I 1 Following Size of CI/DI DF sluice valves Not provided Not provided Comment regarding quality of work Revision:Iss ue 01 Effective as of 17.05.2023 Rev: 0 Doc No. QM 20 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Page 316 of 112 2 80 mm 3 100 mm 4 Chamber No 02 5 Dismantling of CC pavement Cum 33 6 Excavation in pipe line Cum 420 7 Construction of Unreinforced, CC pavement Providing and laying of HDPE pipes Cum 33 8 by DIA 01 by DIA 01 A 90 mm Mtr. 700 9 House hold connection No. 331 Physical Measurement checking status as per scope: S. No . Item Unit As per tender/co ntract bond Qty. As per actual (MB) %age complet ed Qty. 1. Pipeline work Mtr. 700 Qty. 98% 2. FHTC Nos 331 95% Remarks about quality Compliance for last observations reported S. No 1. Item Observations last reported FHTC Bib cock is not provided for the FHTC Compliance not done 2. FHTC Extension nipple is not provided for FHTC Compliance not done Material testing status (Lab test/MTC) Compliance reported Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 317 of 112 S. No. TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Name of Material Make as (as per scope of work) Per 210. Design mix report 211. GI pipe 15mm Dia 212. HDPE Pipe-90 mm 213. MSERW Pipe Report Remarks (whether tests are Availabili Conducted as per respective IS code ty Approved Status Provision so not) QAP) (yes/No) No Tests to be conducted as per IS 10262:2009 and IS 456: 2000 & Frequency of tests to be conducted as per specifications. Apollo Yes Tests to be conducted as per IS 1239 (Part I):2004 & IS: 10748:2004 with Amnd-5, Grade 2Not provided by DIA. Yes Yes Tests conducted as per IS Code IS 4984 (1995) & Frequency of tests to be conducted as per specifications. Not provided by DIA. No Not provided by DIA. 214. DI pipe No 215. Cement No 216. Steel No 217. Aggregate/ Sand No 218. Bricks No 219. CC Cube No 220. Water test report No Tests conducted as per IS Code IS 8329 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 8182:2013 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code IS 1786:2008 & Frequency of tests to be conducted as per specifications. Not provided by DIA. Tests conducted as per IS Code IS 383:2016 & Frequency of tests to be conducted as per specifications. Tests conducted as per IS Code 1077:1992 & Frequency of tests to be conducted as per specifications. Not provided by DIA. As per IS Code IS 10086:1982 & Frequency of tests to be conducted as per IS 456:2000NA Test report not provided by DIA and tests to be conducted as per IS 10500:2012Not provided by DIA. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 318 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Availability of Register on site: Material register Site order book : Not provided by DIA. : Not provided by DIA. Test register/Report: Not Provided by DIA. Concrete Register : Not provided by DIA. Conclusion and Suggestions: Site Order Book is to be available at site whenever any TPIA/ DIA/DWSM/SWSM come to site for inspection. Safety PPEs Kit is must at site for the construction workers Safety Display boards & Barricades must be displayed at all work places near the public conveyance locations. Primary Steel is to be used instead of Secondary steel. If Secondary steel is to be used then it is to be approved from the Engineer in charge and as per CPWD specifications. Proper lap length and development length to be maintained as per drawing/ IS Code: 456. Binding wire to be used is to be between 16 – 18 gauges. Mix design is to be approved by the Engineer in charge before being used at site. Volumetric Mix concrete to be avoided at site and proper placing of Weigh Batcher with the Mixer Machine is to be done. Shuttering material should be cleaned from old concrete. Old rusted shuttering plate and deformed MS Sheets shouldn’t be used and removed. Shuttering oil to be placed before placing of reinforcement. Cover Blocks to be placed properly. Curing of the structure and brick masonry to be done as per IS Code 456 TPIA should be informed before any major activity to be started. Proper depth and width to be maintained of the Trench for pipeline work as per work specification. Excavated soil near the edges of the trench should be 300 mm away from the trench edges. Hydro testing of the Pipeline works and water retaining structures to be done as per specifications. Proper procedure for Road restoration work to be followed. E&M Equipment to be post inspected at site too. FHTC Connection works to be done as per drawing and as per specifications. Backfilling work to be done in layers and properly compacted. All the test reports of the construction materials is to be available at site and properly Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 319 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT maintained. Field Tests of concrete i.e. Cube Tests and Slump Test to be done as per IS Code 456 Tests reports of Pea Gravel are to be from approved Quarry for TW work. Site Register is to be maintained for the Development of Tube Well. Photographs of Inspection Comments Height of stand post observed 500mm in connection of Ikram s/o Jameer hasan. Tap found damaged in FHTC of saleem s/o Shareef. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 320 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Many FHTC provided in open ground (House of beneficiary not available ). Make not mentioned in test report of HDPE pipe. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 321 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Make not mentioned in Test report of GI pipe. Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 322 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 323 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT Revision:Iss ue 01 Rev: 0 Doc No. QM 20 Effective as of 17.05.2023 Page 324 of 112 TUV SUD SOUTH ASIA REAL ESTATE & INFRASTRUCTURE PROJECT VISIT /MONTHLY REPORT END OF REPORT