Uploaded by Mohamed Shalan

Facilities Activity

advertisement
School of Science and Engineering
Fall 2022
Meng 4448 – Facilities Planning
Line Balancing Class Activity
Submitted to: Dr. Ahmed Mohib
Submitted by:
Omar Attia 900181034,
Mark Nabih 900182589,
Fady Bassily 900172913,
Abdelrahman Ehab 900160897,
Abdelrahman Moussa 900172112 (Different Group)
4th December 2022
1
Table of Contents
Introduction ............................................................................................... 3
Calculation ................................................................................................. 3
Measurements ............................................................................................ 4
Precedence Diagram .................................................................................. 4
Conclusion ................................................................................................. 6
2
Introduction
Line Balancing is the method used to divide and assign different work elements on say a
production like to different workstations. This is done based on multiple criteria, most
importantly the takt time and the work element cycle time. Work elements must then be grouped
and divided in a way that they do not exceed the takt time required to meet the expected demand
of the product.
In this activity, we worked on assembling the components of an electric plug to reach the final
product. Each operation time was recorded and then they were grouped accordingly into different
workstations.
Calculation
The required takt time can be obtained as follows:
𝐺𝑖𝑣𝑒𝑛 π·π‘’π‘šπ‘Žπ‘›π‘‘ =
30𝑝𝑐
3𝑝𝑐 0.05𝑝𝑐
1𝑝𝑐
=
=
=
10π‘šπ‘–π‘›π‘  π‘šπ‘–π‘›
𝑠𝑒𝑐
20𝑠𝑒𝑐
Therefore, in order to create 30 electric plugs in 10 minutes, 1 plug must be created every 20
seconds. This is the takt time which is derived from the demand and it sets the limit on the time
of each workstation where every workstation should no exceed 20 seconds cycle time otherwise
the demand will not be met.
Figure 1: Electric Plug diagram
3
Measurements
Work Element
Task Description
Time (sec)
Predecessor
A
Insert and connect the Earth terminal
5.5
B
Insert and connect the Live Terminal
5.7
A
C
Insert and connect the Neutral Terminal
5.4
A
D
Insert Cable grip and fix with 1 bolt
11.5
B, C
E
Fix cable grip with second bolt
8.1
D
F
Insert Fuse
5.2
G
Install Plastic Back cover
14.8
F
H
Install Paper cover
1.3
G
Precedence Diagram
B
A
5.7
5.5
C
D
11.5
E
8.1
5.4
F
G
H
5.2
14.8
1.3
4
There were five of us in the group so we can start by dividing the tasks into five workstations,
and the maximum cycle time for each workstation is 20 seconds. Therefore, we can divide the
tasks accordingly.
𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 =
57.5
∗ 100 = 57.5%
5 ∗ 20
The efficiency is low because there is overstaff (we don’t need 5 workstations). So if we only use
4 workstations, the efficiency will improve as follows.
5
𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 =
57.5
∗ 100 = 72%
4 ∗ 20
Workstation
Time
WS1
10.7
WS2
11.1
WS3
19.6
WS4
16.1
Line Balancing
25
20
15
10
5
0
WS1
WS2
WS3
WS4
Conclusion
This time the efficiency improved to 72%, while much better than the previous attempt, it is still
not high enough, this is because as shown in the chart, WS3 is the most overloaded station as it is
very close to the 20 second cycle time limit. Usually, it would be better to take off tasks from
WS 3 and add them to other workstations, but in this case it would be difficult to do so and still
satisfy the precedence requirements. So, the workstations can function as done for now.
6
Download