DOCUMENT No. A918-160-80-45-MC-T-7601 Rev.1 TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE Page 1 of 10 TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE UNIT : GASOLINE HYDROTREATMENT UNIT (160) PROJECT : GTU CLIENT : BPCL, MUMBAI JOB NO. : A918 1 01.09.2017 ISSUED FOR TENDER KK PG MK 0 30.06.2017 ISSUED FOR TENDER RS PG MK Rev. No Date Purpose Prepared by Checked by Approved by Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE DOCUMENT No. A918-160-80-45-MC-T-7601 Rev. 1 Page 2 of 10 INDEX OF CONTENTS SL. No. I 1. 2. 3. II A DOCUMENT TITLE DOCUMENT NO. TECHNICAL CHECKLIST FOR BID SUBMISSION & BQC Checklist (Technical) for Bidder reference A918-160-80-45-OD-0001 for ‘ZERO DEVIATION’ bid Technical Compliance for Fired Heater A918-160-80-45-OD-0002 Package (REFER NIT) Bidder Qualification Criteria (Technical) for Furnace Package FIRED EQUIPMENT MECHANICAL REVISION No. 0 0 0 JOB SPECIFICATIONS 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. B B1. 18. 1 19. Scope of Work Job Specification for Fired Heater Package Specification for procurement of pressure parts Specification for procurement of tube support castings Specification for Procurement of Steam Air Pre Heater Specificationforprocurementofcast& glass tube air preheater Specification for procurement of Dampers and shut off blinds Specification for external Insulation of duct for fired Heaters Specification for Procurement of Expansion Joints Basis of Structure Design Site Specific Seismic Spectra Specification for Modularization of Fired Heater Package 3D Modeling requirement forfired heater package Vendor Data Requirement A918-160-80-45-SW-0001 0 A918-160-80-45-SP-0002 0 A918-160-80-45-SP-0003 A918-160-80-45-SP-0004 A918-160-80-45-SP-0005 A918-160-80-45-SP-0006 A918-160-80-45-SP-0007 0 0 0 0 0 A918-160-80-45-SP-0008 0 A918-160-80-45-SP-0009 0 A918-160-80-45-SP-0010 A918-000-16-54-DB-0001 0 0 A918-160-80-45-SP-0011 0 A918-160-16-43-SOW-7601 A A918-160-80-45-VDR-7601 A A918-160-80-45-0100 1 A918-160-80-45-1101 B DRAWINGS: Splitter Re-boiler Heater Foundation Loading Plan for Splitter heater (160-F-0001) & 1st and 2nd Stage HDS Heaters (160-F-0002A/B) General arrangement cross section, long. Sec Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE DOCUMENT No. A918-160-80-45-MC-T-7601 Rev. 1 Page 3 of 10 1 1 SL. No. 20. General arrangement plans-1 A918-160-80-45-1102 REVISION No. B 21. General arrangement plans-2 A918-160-80-45-1103 B 22. General arrangement stack and plans A918-160-80-45-1104 B 23. APH system ducting layout plan A918-160-80-45-0105 B 24. B2. APH system ducting layout elevation A918-160-80-45-0106 B 25. Foundation loading plan A918-160-80-45-1200 A 26. General arrangement cross section A918-160-80-45-1201 B 27. General arrangement long Sec & plan A918-160-80-45-1202 B 28. 29. 30. 31. 32. 33. B3. 34. 35. 36. C. 37. General arrangement plans-1 A918-160-80-45-1203 B General arrangement plans-2 General arrangement plans-3 General arrangement stack APH system ducting layout plan APH system ducting layout elevation COMMON Tube supports castings General notes for GA drawings Equipment Layout EIL STANDARDS Convection Section Intermediate Tubesheet Support Bracket with 102x102 Bearing Surface (Light Pattern) Wall Tube Hanger (Medium Duty) for 168.3 O/D Vertical Radiant Tubes Wall tube hanger (heavy duty) for 168.3 O/D vertical radiant tubes Tube support lug for crossovers & jumpovers of vertical radiant tubes Tube support lug for vertical radiant tubes Chain link reinforcement for insulation concrete lining Anchor Spacing and Types for Castable Lining Anchor for vertical insulating concrete walls with backup insulation Insulating concrete anchors for walls and overhead surfaces (50≤ lining thickness ≤ 75mm) Insulation details at pressure relief doors for cabin or circular heaters Detail of Insulation at Tube Supports for Concrete Walls Insulation details at floor mounted burners Insulation details of floor peep holes Insulation at ends of extended surface A918-160-80-45-1204 A918-160-80-45-1205 A918-160-80-45-1206 A918-160-80-45-0208 A918-160-80-45-0209 B B B B B A918-160-80-45-1207 A918-160-80-45-4110 A918-160-16-43-00001 B A 1 7-17-0102 5 7-17-0104 1 7-17-0121 5 7-17-0139 5 7-17-0140 5 7-17-0202 5 7-17-0205 5 7-17-0208 5 38. 39. 40. 41. 42. 43. 44. 45. 46. 47. 48. 49. 50. DOCUMENT TITLE st 1 nd and 2 DOCUMENT NO. Stage HDS Heater Format No. EIL 1641-1924 Rev. 1 5 7-17-0212 7-17-0305 7-17-0306 7-17-0307 7-17-0309 7-17-0313 4 5 5 5 4 Copyright EIL – All rights reserved TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE DOCUMENT No. A918-160-80-45-MC-T-7601 Rev. 1 Page 4 of 10 SL. No. 51. 52. 53. 54. 55. 56. 57. 58. 59. 60. 61. 62. 63. 64. 65. 66. 67. 68. 69. 70. 71. 72. 73. 74. 75. 76. 77. 78. 79. DOCUMENT TITLE tubes Insulation Details at Floor Access Door in Vertical Tube Heaters Insulation details at access door Insulation details at observation doors in convection walls Insulation details at sight door Tube sealing detail Header Box with removable panels for convection section Bolts and shear plate for intermediate tube sheet support bracket (light) Hinged access door for steel stack Details of Tube Pulling doors for flat arch Floor access doors for vertical tubes heaters Fabricated pressure relief door for cabin and circular heater (510x610) observation door for convection wall Details of fabricated 4" dia self-closing floor peephole 510X 610 Fabricated Door for use in Top of Breeching Details of 610 wide x 610 or 850 high bolted access door for vertical walls Details of lifting lugs and tie rods for convection section (packaged units) Floor sleeves for spigot guides on top supported vertical tubes. Temporary shipping handling bracing for convection section (packaged units) Arrangement of painters trolley for circular stack Mounting plate for nameplate for heaters. Steel stack field splice details Shipping spiders for prefabricated stacks (for stack diameters upto 3050) Fixing Details of Wall Tube Hanger for 6 inch NB Tube and Under Fixing details for wall tube hanger 8” N.B. tube Shear plate and bolts for cast tube hangers vertical cylindrical heaters Detail of stack strakes Fabricated end tube sheets and support plates (convection) Carbon Steel Guide Angles for Intermediate Tube sheets Ladder and cage details (side step type) Format No. EIL 1641-1924 Rev. 1 DOCUMENT NO. REVISION No. 7-17-0314 6 7-17-0318 5 5 7-17-0319 7-17-0320 7-17-0322 7-17-0404 5 5 5 7-17-0407 4 7-17-0410 7-17-0411 5 4 5 7-17-0412 7-17-0414 3 7-17-0415 4 7-17-0417 5 7-17-0418 5 4 7-17-0419 7-17-0420 4 7-17-0421 4 7-17-0422 4 7-17-0423 4 7-17-0427 7-17-0428 4 4 7-17-0439 4 7-17-0440 4 7-17-0441 7-17-0443 7-17-0444 7-17-0446 7-17-0451 7-17-0454 4 4 4 4 4 4 Copyright EIL – All rights reserved TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE DOCUMENT No. A918-160-80-45-MC-T-7601 Rev. 1 Page 5 of 10 SL. No. 80. 81. 82. 83. 84. 85. 86. 87. 88. 89. 90. 91. 92. 93. 94. 95. 96. 97. 98. 99. 100. 101. 102. 103. 104. 105. 106. 107. 108. 109. 110. DOCUMENT TITLE Ladder and cage details (step through type) Stair details (for use with chequered plate or grating platforms) Details of circular platforms with open type flooring Details of rectangular platforms with open type flooring Hand rail details 230 x 130 Sight Door Mounting for Curved Surfaces Steel stack top ring & painters trolley rail Tube Pulling Bracket Fabricated sight door assembly with glass (120x220 opening) Auxiliary connection detail for heater system Instrument / auxiliary coil connection detail Misc. steel connection details Damper control cable Coil Guide Spigot for Top Supported Vertical Tubes Vertical Radiant Tubes Coil guide spigot (with coupling ) for top supported vertical tubes Name Plate List of abbreviations. Draughting symbols Detail of welded column splice (unequal parallel flange section) Welded column splice (unequal joist section) Splicing detail for rolled sections Beam to beam and beam to column connection details. Welding Symbols Typical detail of weld length for angle members Detail of moment connection for MC [ ] column to [ ] beam Typ. detail of moment connection with MB column to MB beam Welded shear connection details for parallel flange beam with parallel flange beam Details of moment connection for parallel flange beams with parallel flange columns Welded shear connection details for parallel flange beam with parallel flange column Shear connections welded type - beam to Format No. EIL 1641-1924 Rev. 1 DOCUMENT NO. 7-17-0455 7-17-0456 7-17-0459 7-17-0460 7-17-0461 7-17-0463 7-17-0465 7-17-0472 7-17-0473 7-17-0475 7-17-0476 7-17-0477 7-17-0512 7-17-0606 7-17-0611 7-17-0613 7-17-0701 7-17-0705 7-17-0707 7-68-0206 REVISION No. 4 4 4 4 4 4 4 4 0 0 0 0 4 5 5 5 4 4 4 0 7-68-0207 4 7-68-0208 5 7-68-0211 5 7-68-0251 5 7-68-0653 3 7-68-0654 3 7-68-0660 2 7-68-0686 0 7-68-0687 0 7-68-0688 0 7-68-0689 3 Copyright EIL – All rights reserved TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE DOCUMENT No. A918-160-80-45-MC-T-7601 Rev. 1 Page 6 of 10 SL. No. D. 111. 112. E. 113. 114. 115. 116. 117. 118. 119. 120. 121. 122. 123. 124. 125. 126. 127. 128. 129. 130. 131. 132. 133. 134. 135. DOCUMENT TITLE beam BPCL STANDARDS Detail of galvanized grating (Type-A, heavy duty) Technical specificationofPaint coating EIL SPECIFICATIONS Standard Specification for execution of fired Heaters and Air Preheating System Standard Specification for Steelwork of Fired Heaters and Air Preheating System. Standard Specification of Coil work for fired heaters Standard specification for studded tubes for fired heater Standard specification of finned tubes for fired heaters. Standard Specification of Tube Support Castings for Fired Heaters Standard Specification for Design and Supply of Cast Tube Air Preheater Standard specification for design and supply of dampers / shut off blinds Standard specification forDesign and supply ofGlass air preheater Standard specification for fabric type expansion joints Standard specification for quality checks for fabrication erection and execution of fired heaters Standard specification for heater system leakage testing through smoke generation Standard specification for miscellaneous refractory and auxiliary material used in fired heaters Standard specification for workmanship and quality plan for refractory work in fired heater Standard specification for hot insulation of vessels, piping and equipment Technical notes for pipes Technical Notes for valves Technical notes for flanges, spectacle blinds and drip rings Technical notes for butt welded, socket welded and screwed fittings Technical notes for gaskets (for pressure parts) Technical notes for bolts and nuts (for pressure parts) Specification for Documentation Requirements from Contractors Format for completeness of final Format No. EIL 1641-1924 Rev. 1 DOCUMENT NO. REVISION No. FS-536 - AE-S-5430 1 6-17-0001 5 6-17-0002 5 6-17-0003 4 6-17-0004 5 6-17-0005 5 6-17-0007 5 6-17-0010 1 6-17-0013 0 6-17-0014 0 6-17-0016 0 6-17-0017 0 6-17-0018 0 6-17-0020 1 6-17-0021 1 6-44-0002 5 6-44-0051 6-44-0052 6 6 6-44-0053 6 6-44-0054 6 6-44-0056 4 6-44-0057 4 6-78-0002 1 3-78-0004 1 Copyright EIL – All rights reserved TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE DOCUMENT No. A918-160-80-45-MC-T-7601 Rev. 1 Page 7 of 10 SL. No. 136. 137. 138. 139. 140. III A. 141. 142. 143. 144. 145. B. 146. 147. 148. 149. 150. 151. C. 152. 153. 154. 155. 156. 157. 158. 159. 160. 161. D 162. 163. 164. 165. 166. 167. 168. 169. 170. DOCUMENT TITLE documentation Standard Specification for Refractory Material Sampling, Inspection and Criteria for Acceptance. Standard Specification for Fire Bricks Standard Specification for C.F. Blankets Standard Specification for Castable applications Standard Specification for Insulating Castable PROCESS – THERMAL 1st Stage HDS Heater Burner datasheet Skin thermocouples datasheet (common) Flow instrument datasheet (common) Air preheater datasheet (common) SAPH datasheet DOCUMENT NO. REVISION No. 6-79-0001 1 6-79-0003 6-79-0005 1 2 6-79-0007 2 6-79-0008 2 A918-160-02-44-DS-72 A918-160-02-44-DS-70 A918-160-02-44-DS-74 A918-160-02-44-DS-75 A918-160-02-44-DS-80 A 0 0 A A A918-160-02-44-DS-82 A918-160-02-44-DS-84 A918-160-02-44-DS-85 A918-160-02-44-DS-87 A918-160-02-44-DS-88 A918-160-2-44-P&ID-1171 A 0 0 0 0 A A918-160-02-44-DS-91 A918-160-02-44-DS-92 A918-160-02-44-DS-93 A918-160-02-44-DS-96 A918-160-02-44-DS-97 A918-160-02-44-DS-98 A918-160-02-44-DS-99 A918-160-02-44-DS-78 A918-160-02-44-DS-83 A918-160-2-44-P&ID-1172 A 0 0 A A 0 0 0 0 A A918-160-02-44-SP-01 A918-160-2-44-SP-02 A918-160-02-44-OD-01 A918-160-02-44-OD-02 A918-160-02-44-OD-03 A918-160-02-44-OD-04 6-17-0008 A A A A A A 6-78-0001 0 6-78-0003 0 2nd Stage HDS Heater Burner datasheet Damper datasheet (common) Sob datasheet (common) FD fan datasheet (common) ID fan datasheet (common) Piping & Instrumentation Diagram Splitter Heater Burner datasheet Skin thermocouples datasheet Flow instrument datasheet Air preheater datasheet SAPH datasheet FD fan datasheet ID fan datasheet Damper datasheet Sob datasheet Piping & Instrumentation Diagram-Splitter Burner Specification Job Specification for burners Job Specifications for CFD Recommended Vendor List List of Sub-Vendor for Ignition System Checklist for the bidders Instructions to Bidders Standard Specification for Forced Draft Burners for Fired Heaters Specification for Quality management system requirements from Contractors Specification for documentation Format No. EIL 1641-1924 Rev. 1 4 Copyright EIL – All rights reserved TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE DOCUMENT No. A918-160-80-45-MC-T-7601 Rev. 1 Page 8 of 10 SL. No. 171. 172. IV 173. 174. 175. 176. 177. 178. 179. 180. 181. 182. 183. V DOCUMENT TITLE requirements from Suppliers Inspection & Test Plan for Burners of Fired Heaters Vendor Data Requirement- Burners ROTATING EQUIPMENT(S&ME-2) Scope of Supply / Works Special Instructions to bidders Operation and Maintenance Spares Philosophy Mandatory Spares for ID/FD fans Datasheet for Forced Draft Fan of Splitter Heater Datasheet for Forced Draft Fan of 1st and 2nd stage Reactor Heater Datasheet for Induced Draft Fan of Splitter Heater Datasheet for Induced Draft Fan of 1st and 2nd stage Reactor Heater Vendor data requirement for ID/FD Fans Experience record proforma – (ID/FD fans) ITP for pump reciprocating (plunger/piston) ELECTRICAL DOCUMENT NO. REVISION No. 6-81-0114 1 A918-160-2-44-VDR-0001 A A918-160-80-43-SOW-7601 A918-160-80-43-SI-7601 A A AES-3711 A A918-160-80-43-SL-7601 A A918-160-80-43-DS-0001 A A918-160-80-43-DS-0002 A A918-160-80-43-DS-0003 A A918-160-80-43-DS-0004 A A918-160-80-43-VDR-7601 A A918-160-80-43-ER-7601 A 6-81-0053 3 A918-160-16-50-SOW-7601 0 184. Scope of work & job specification (Electrical) for ID-FD fans 185. Data sheet for Medium Voltage S.C. Induction Motor A918-160-16-50-DS-7601 0 186. Datasheet for Variable Frequency Drive A918-160-16-50-DS-7602 0 187. Electric load data A918-160-16-50-DS-7603 0 188. Vendor Data Requirement (For ID & FD Fans Motors) A918-160-16-50-VR-7601 0 189. Specification for Flameproof Control Stations 6-51-0006 190. Specification for MV variable frequency drive system 6-51-0038 191. Speciation for Numerical Relays 6-51-0055 192. Specification for energy efficient medium voltage induction motors 6-51-0064 193. Specification for electrical equipment installation 6-51-0081 4 194. Specification for field inspection, testing and commissioning of electrical installations 6-51-0087 3 195. Specification for electrics of package equipment. 6-51-0093 4 Format No. EIL 1641-1924 Rev. 1 5 2 2 1 Copyright EIL – All rights reserved TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE DOCUMENT No. A918-160-80-45-MC-T-7601 Rev. 1 Page 9 of 10 SL. No. DOCUMENT TITLE DOCUMENT NO. REVISION No. 196. Inspection & test plan for flameproof control stations 6-81-1006 3 197. Inspection & test plan for MV variable frequency drive system 6-81-1038 2 198. Inspection & test plan for MV motors 6-81-1032 5 199. 6-81-1055 2 200. Inspection & test plan for Numerical Relay INSTRUMENTATION Job specifications-FD fan A918-160-16-51-SP-1009 A 201. FIDU -drawing A918-160-16-51-1001 A 202. Skin thermocouple heater A918-160-16-51-DS-4001 A 203. Venturi tubes Data sheet A918-160-YF-DS-0001 A 204. Thermocouple assembly head drawingsheet2 A918-160-16-51-4002/2 A 205. Job specifications-APH A918-160-16-51-SP-1010 A 206. Thermocouple assembly head drawingsheet1 A918-160-16-51-4002/1 A 207. Job specifications- burner A918-160-16-51-SP-1011 A 208. Skin thermocouples A918-160-16-51-DS-4002 209. Job specifications-heater A918-160-16-51-SP-1012 A A 210. Heater tube skin thermocouple drawing A918-160-16-51-3001 A 211. Vendor data requirements-heater A918-160-16-51-VDR-7601 A 6-52-0072 3 212. Standard specification for local control panel and accessories(electronic/pneumatic) 213. Standard specification for heater tube skin thermocouples. 6-52-0043 4 214. Instrument connections on (fired heaters) 7-52-0010 4 215. ITP for heater tube skin thermocouples 6-81-2043 4 216. Standard specification for signal cables. 6-52-0046 7 217. ITP for signal cables 6-81-2046 3 218. ITP for local control panel & accessories CONSTRUCTION Construction Supervision And Management Inspection & test plan (ITP) heater package Standard specification for PMI at construction sites Standard specification for color coding of piping material Standard specification for piping and heater (fired) coil material traceability at 6-81-2072 3 A918-00-160-19-41-0001 0 6-82-5000 0 6-82-0002 3 6-82-0003 2 6-82-0004 1 VI VII 219. 220. 221. 222. 223. Format No. EIL 1641-1924 Rev. 1 Copyright EIL – All rights reserved TECHNICAL PORTION OF TENDER FOR FIRED HEATER PACKAGE DOCUMENT No. A918-160-80-45-MC-T-7601 Rev. 1 Page 10 of 10 SL. No. 224. 225. 226. 227. 228. 229. VIII 230. 231. 232. 233. 234. 235. 236. 237. 238. IX 239. DOCUMENT TITLE construction sites Inspection & Test Plan (ITP) for incoming material checking for contractor’s supplied materials Standard specification for erection of equipment & machinery Standard specification for application of torque and hydraulic bolt tension for flange joints Standard specification for HSE management at construction site Calibration requirements of monitoring and measuring devices at construction sites Qualification and experience requirements of key personnel and penalty for their nonmobilization INSPECTION Inspection methodology for package items Standard specification for positive material identification (PMI) at vendor's work Inspection & test plan for seamless pipes Inspection & test plan for valves Inspection & test plan for forged, seamless and welded fittings Inspection & test plan for flanges, spectacle blinds & drip rings Inspection & test plan for bolting material Inspection & test plan for gaskets ITP for ID/FD Fans MISCELLANEOUS Vendor List Format No. EIL 1641-1924 Rev. 1 DOCUMENT NO. REVISION No. 6-82-1010 1 6-76-0001 3 6-76-0002 2 6-82-0001 (Refer commercial part) 7 7-82-0002 (Refer commercial part) 0 7-82-0003 (Refer commercial part) 0 A918-9-1842-1001 0 6-81-0001 3 6-81-0003 6-81-0004 5 5 6-81-0005 6 6-81-0006 4 6-81-0007 6-81-0008 6-81-0054 4 3 3 A918-160-85-41-VL-07 0 Copyright EIL – All rights reserved