TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 PURPOSE This Standard describes the requirements for gas and liquid steel pipeline design and installation employing the Horizontal Directional Drilling (HDD) method on behalf of the Company in Canada, the U.S. and Mexico. SCOPE/APPLICABILITY This Standard applies to all HDD design requirements and operations conducted during the construction of gas and liquid steel pipelines in Canada, the U.S. and Mexico. Sections 2 to 7 apply to HDD design, and sections 8 to 20 specify the requirements during HDD construction. Section 1 applies to both HDD design and construction. Within an Engineering Standards Collection (ESC) document, the following terms and definitions apply for requirements: • “Company” means the TC Energy entity for whom work, services and/or materials are being provided. • “Shall”, “Must” or similar term is used to express a requirement (meaning a provision that the user is obliged to satisfy in order to comply with the ESC document or applicable standard). • “May” is used to express an option or that which is permissible within the limits of the applicable standard. • “Should” shall in all instances be interpreted in the same manner as “Shall”, unless one of the following requirements has been met: o to the extent the Company has expressly waived in writing strict compliance with such standard in such circumstance; or o the Contractor has performed a detailed documented analysis provided to the Company in advance of taking action, which analysis justifies, on reasonable grounds, the action taken to a level consistent with the applicable standard. Wherein governmental or regulatory requirements conflict with this Standard, the more stringent requirement shall govern. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 1 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 Table of Contents 1 GLOSSARY.............................................................................................................................................................. 6 2 GEOTECHNICAL PROGRAM REQUIREMENTS FOR HDD DESIGN.................................................................... 9 2.1 General................................................................................................................................................... 9 2.2 Sampling Interval and Technique ......................................................................................................... 10 2.3 Laboratory Testing ............................................................................................................................... 11 2.4 Geotechnical Data Report Requirements ............................................................................................. 11 3 SURVEY REQUIREMENTS FOR HDD DESIGN ................................................................................................... 12 3.1 General................................................................................................................................................. 12 4 BORE PATH DESIGN REQUIREMENTS .............................................................................................................. 12 4.1 General................................................................................................................................................. 12 4.2 HDD Entry and Exit Angles .................................................................................................................. 12 4.3 Depth of Cover ..................................................................................................................................... 13 4.4 Bore Tangents ...................................................................................................................................... 13 4.5 Radius of Curvature ............................................................................................................................. 13 4.6 Horizontal and Vertical Curves ............................................................................................................. 14 4.7 Setback Distance ................................................................................................................................. 14 4.8 Installation Length ................................................................................................................................ 14 5 HDD DESIGN REQUIREMENTS ........................................................................................................................... 15 5.1 General................................................................................................................................................. 15 5.2 HDD Feasibility Report Requirements.................................................................................................. 15 5.3 Work Space and Staging Area ............................................................................................................. 16 5.4 Drill and Intersect Installation Methodology .......................................................................................... 17 5.5 Temporary Starter or Conductor Casing Pipe ...................................................................................... 17 5.6 Buoyancy Control Measures ................................................................................................................ 18 5.7 No-Drill Zone Requirements ................................................................................................................. 18 5.8 Intermediate Weld During Pullback Operations.................................................................................... 18 6 CROSSING-SPECIFIC HDD DESIGN DRAWINGS .............................................................................................. 19 6.1 General................................................................................................................................................. 19 7 ENGINEERING DESIGN CALCULATIONS ........................................................................................................... 19 7.1 General................................................................................................................................................. 19 7.2 Pipe Wall Thickness ............................................................................................................................. 20 Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 2 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 7.3 Minimum Allowable Pipe Bending Radius ............................................................................................ 21 7.4 Pipe Design Bending Radius................................................................................................................ 21 7.5 Steering Radius .................................................................................................................................... 21 7.6 In-Service Operating Stress ................................................................................................................. 21 7.7 Hydraulic Fracture Evaluation .............................................................................................................. 22 7.8 Product Pipe Installation Load and Stresses ........................................................................................ 24 7.9 Roller Spacing ...................................................................................................................................... 25 7.10 Break-Over Stress Evaluation .............................................................................................................. 25 7.11 Over-Bend Stress Evaluation ............................................................................................................... 26 7.12 Highway and Railroad Crossing Stress Evaluation .............................................................................. 26 7.13 Ground Surface Settlement Evaluation ................................................................................................ 27 7.14 Risk Characterization ........................................................................................................................... 27 8 CONSTRUCTION REQUIREMENTS..................................................................................................................... 27 8.1 Company Responsibilities .................................................................................................................... 27 8.2 Environmental Plan .............................................................................................................................. 28 8.3 Safety Plan ........................................................................................................................................... 28 8.4 Workspace and Access Requirement Drawing .................................................................................... 28 8.5 Drilling Schedule and Planning ............................................................................................................ 28 9 SITE-SPECIFIC HDD EXECUTION PLAN............................................................................................................. 28 9.1 General................................................................................................................................................. 28 9.2 Lifting and Pullback Plan ...................................................................................................................... 29 9.3 Drill Rig Anchoring Plan ....................................................................................................................... 30 9.4 Site-Specific Contingency Plan ............................................................................................................ 30 9.5 Engineered Drilling Fluid Management and Composition Plan ............................................................ 30 9.6 Drilling Equipment Specifications, Condition and Integrity ................................................................... 31 9.7 Site-Specific Disposal Plan .................................................................................................................. 32 10 CONSTRUCTION EXECUTION – GENERAL REQUIREMENTS.......................................................................... 33 10.1 Protection of Other Facilities ................................................................................................................ 33 10.2 Workspace and Access ........................................................................................................................ 33 10.3 Water Sources Used for HDD .............................................................................................................. 33 11 CONSTRUCTION EXECUTION – DRILLING OPERATION .................................................................................. 33 11.1 Equipment Standard............................................................................................................................. 33 Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 3 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 11.2 Lost or Lodged Tools............................................................................................................................ 33 11.3 Inspection of Drill Pipe and Other Tubulars .......................................................................................... 34 11.4 Electronic Drilling Recorder (EDR) ....................................................................................................... 34 11.5 Casing Requirements ........................................................................................................................... 35 11.6 Radio Communication and Access to Instruments ............................................................................... 36 11.7 Reporting of Drilling Status................................................................................................................... 36 12 CONSTRUCTION EXECUTION – DRILLING FLUID SYSTEM ............................................................................. 37 12.1 Instrumentation..................................................................................................................................... 37 12.2 Drilling Fluid Pressure and Circulation ................................................................................................. 37 12.3 Drilling Fluid Containment Management .............................................................................................. 37 13 CONSTRUCTION EXECUTION – DRILLING FLUID COMPOSITION .................................................................. 38 13.1 Drilling Fluid Properties ........................................................................................................................ 38 13.2 Reporting of Drilling Fluid Properties .................................................................................................... 38 14 CONSTRUCTION EXECUTION – DISPOSAL OF DRILLING FLUID AND CUTTINGS ........................................ 39 14.1 General................................................................................................................................................. 39 14.2 Disposal Reporting ............................................................................................................................... 39 15 CONSTRUCTION EXECUTION – DRILLING FLUID MIGRATION, PREVENTION, AND RESPONSE ................ 39 15.1 General................................................................................................................................................. 39 15.2 Minimum Pump Pressure ..................................................................................................................... 39 15.3 Safe Drilling Practices .......................................................................................................................... 40 15.4 Ground Surface Monitoring .................................................................................................................. 40 15.5 Water Quality Monitoring ...................................................................................................................... 40 15.6 Reporting of Drilling Fluid Migration ..................................................................................................... 40 15.7 Notification and Response ................................................................................................................... 41 15.8 Surface Containment and Removal ..................................................................................................... 41 15.9 In-Stream Containment and Removal .................................................................................................. 41 16 CONSTRUCTION EXECUTION – PILOT HOLE DRILLING, TRACKING, AND SURVEYING .............................. 41 16.1 General................................................................................................................................................. 41 16.2 Entry/Exit Angle, Horizontal Alignment and Depth ............................................................................... 42 16.3 Pilot Hole Drill Radius........................................................................................................................... 43 16.4 Pilot Hole Drill Corrections ................................................................................................................... 44 17 CONSTRUCTION EXECUTION – HOLE REAMING ............................................................................................. 44 Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 4 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 17.1 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 General................................................................................................................................................. 44 18 CONSTRUCTION EXECUTION – PIPE FABRICATION AND TESTING PRIOR TO PULLBACK ........................ 45 18.1 Welding ................................................................................................................................................ 45 18.2 Pipe and Coatings ................................................................................................................................ 46 18.3 Pre-Pullback Hydrostatic Testing ......................................................................................................... 46 19 CONSTRUCTION EXECUTION – PIPE PULLBACK ............................................................................................. 47 19.1 General................................................................................................................................................. 47 19.2 Acceptance of Installation .................................................................................................................... 48 19.3 Preparation of Final Tie-In .................................................................................................................... 49 19.4 Final Reporting ..................................................................................................................................... 49 20 CONSTRUCTION EXECUTION – SITE CLEAN UP AND RESTORATION .......................................................... 50 20.1 Grouting and Sealing of Abandoned Holes .......................................................................................... 50 20.2 Site Restoration .................................................................................................................................... 50 21 VARIANCES........................................................................................................................................................... 50 22 ROLES AND RESPONSIBILITIES ......................................................................................................................... 50 23 REFERENCES ....................................................................................................................................................... 51 24 DOCUMENT HISTORY.......................................................................................................................................... 54 25 DESCRIPTION OF CHANGE................................................................................................................................. 55 26 APPROVALS.......................................................................................................................................................... 56 List of Tables Table 16-1: Tolerance for the Pilot Hole Drill ............................................................................................................... 42 Table 22-1: Roles and Responsibilities ........................................................................................................................ 50 Table 23-1: Regulatory References ............................................................................................................................. 51 Table 23-2: External Industry References .................................................................................................................... 52 Table 23-3: Internal References................................................................................................................................... 53 List of Appendices APPENDIX A REQUIRED DOCUMENT LIST .......................................................................................................... 57 APPENDIX B SAMPLE DRAWINGS ........................................................................................................................ 58 Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 5 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 1 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 GLOSSARY Agreement "Agreement" refers to the contract, release order or purchase order, collectively, the body of the agreement and all attached Schedules, as each of the foregoing may be amended and supplemented from time to time. As-built A drawing showing the component’s location and other facility attachments after construction. May be referred to “as-constructed drawing.” Azimuth The angle at which the downhole probe is projecting in the horizontal plane at a particular down-hole survey point (magnetic north corresponds to zero degrees). Break over The section of the product pipe behind the pipe entry location that is lifted into the air along a designed arc using cranes and/or side booms to transition the product pipe from being staged on top of the ground surface to being installed within the completely reamed and swabbed HDD bore. Centralizing casing Casing used to centralize the drilling assemblies within larger diameter casing pipes. Circulating pressure The required drilling fluid pressure observed during circulation of drilling fluids within the bore without further advancement of the pilot bore. Competent Adequately qualified, suitably trained and with enough experience to safely perform the work as outlined, independently or with only a minimal degree of supervision. Compound curve An alignment curve that bends in both the horizontal and vertical planes simultaneously. Construction line list A list provided in the project description that provides an up-to-date list of the landowners affected by the work and the legal land description. The list may define specific requirements for the work on that property and the status of any agreements between the Company and the landowner. Such agreements are included in the work to be performed by the Contractor. Design bend radius The bend radius used to develop the bore geometry for the specific crossing. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 6 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 Drawings All drawings referenced in the Agreement or issued to the Contractor by the Company for the performance of the work; this includes all design and construction drawings, typical drawings or sketches, route maps, alignment drawings, environmental alignment drawings, and any other drawings issued to help define, clarify, or assist the work. Drill and intersect An HDD installation whereby an HDD rig is used to complete the pilot bore phase of the installation process from both sides of the alignment. Each drill rig is used to drill independent pilot bores that meet within a target intersect location. Drilling pressure The drilling fluid pressure observed during advancement of the pilot bore. HDD crossing design drawing A drawing (prepared by a professional engineer) showing the crossing in plan and profile (specifies the depth, length, minimum allowable bend radius, maximum pull load). HDD entry location The established location at the end of the installation where the HDD rig will be set up and used to complete the pilot bore drilling operation. HDD exit location The established opposite location at the end of the installation where the pilot bore exits the ground surface upon completion of drilling operations. Intermediate weld Any weld introduced to the prefabricated pipe during pullback operation. Minimum allowable pipe bend radius The elastic pipe bending radius at which the stress limits of the pipe will be reached based on stress design calculations. This value represents the actual curvature radius of the installed product pipe and not the curvature of the bore profile. Minimum allowable single or one joint steering radius The minimum radius of curvature allowed for pilot hole measured over an arc length of 10 m (30 ft). Minimum allowable single joint steering radius shall be equal to or greater than minimum allowable pipe bend radius. Minimum allowable three joint steering radius The minimum radius of curvature allowed for the pilot hole measured through three (3) points over an arc length of 30 m (100 ft). Minimum allowable three (3) joint steering radius shall be at least 10% greater than the minimum allowable single or one joint steering radius. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 7 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 No-drill zone An exclusion zone established for the specific crossing upon which the HDD installation is not allowed to encroach during all phases of the installation process. Over-bend fitting Cold bends or elbow fittings at the HDD tie-ins with the rest of the pipeline. Pipe entry location Location where the product pipe enters the ground surface drilled borehole. Pipe exit location Location where the product pipe exits the ground surface drilled borehole. Product pipe The pipe that is installed during HDD which carries the liquid or gas. S-curve An alignment curve that bends in one direction followed by a bend in the opposite direction. A tangent may or may not occur between the two opposing curves. Telescoping casing A casing strategy that involves installation of multiple casing pipes of successively smaller diameters into the ground surface. The largest diameter casing is installed first, subsequently followed by a smaller diameter casing installed within the larger diameter casing. Third party inspection An agent independent of the Contractor. The inspection shall be performed by a person with the expertise, knowledge and training to perform the inspection. Washover casing Casing used during or prior to pilot bore drilling operations that is pushed into a portion of the existing previously drilled pilot to help convey drilling fluid flow back to the HDD entry location. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 8 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 2 GEOTECHNICAL PROGRAM REQUIREMENTS FOR HDD DESIGN 2.1 General 2.1.1 A geotechnical investigation shall be completed for the proposed crossing by a professional service provider that is qualified by the Company. Geophysical scope of work, including electrical resistivity tomography (ERT) and/or seismic refraction (SR), should be considered in the overall geotechnical scope of work. 2.1.2 A professional service provider that is qualified by the Company shall develop a Field Execution Plan for all geotechnical investigations. The plan shall, at a minimum, include: • location including coordinates (e.g., confirmed with One Call, First Call, Call Before You Dig) • tree clearing requirements • type of drill rig required • access requirements • fresh water requirements • environmental constraints including mud disposal requirements • size of pads • access for geotechnical investigation • pad construction details • planned termination • depth of the boreholes 2.1.3 If ERT and SR surveys are implemented, the depth of interpretation and the longitudinal extents of the surveys should be selected such that the stratigraphy along the entire HDD alignment can be interpreted. 2.1.4 Subsurface geotechnical information shall be obtained in support of all HDD designs. If available, existing geotechnical data from previous Company projects in the area of the proposed installation should be used to develop requirements for the geotechnical investigation. 2.1.5 The number and spacing of boreholes shall be consistent with the known geotechnical information and identified crossing-specific conditions and risks for the project. The number of borings to be completed shall be discussed with the Company to determine adequacy of extent, locations, and spacing. Consideration should be given to both land and water-based borings. 2.1.6 If specified in the Agreement, the depth of boreholes shall be a minimum of 15 m (50 ft) below the anticipated pipe profile at the location of the nearest borehole to characterize the site conditions in the event a deeper alignment is required during the design. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 9 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 2.1.7 Geotechnical boreholes shall not be on the HDD alignment (path). Geotechnical borings should be located a minimum of 10 m (30 ft) and a maximum of 100 m (330 ft) perpendicularly offline of the proposed HDD centerline alignment to reduce the possibility of frac-out during drilling. 2.1.8 Geotechnical borehole spacing should range between 150 m (490 ft) and 300 m (990 ft). 2.1.9 Actual boring locations shall be surveyed so that the horizontal and vertical positions of the borings are known. 2.1.10 Boring locations shall be referenced to the same horizontal and vertical control system used in the bore path design. 2.1.11 Upon completion, each boring shall be abandoned in accordance with regulatory requirements and project-specific Environmental Protection Plan (EPP), with the exception of those borings that house instrumentation to monitor groundwater, slope stability, etc. 2.1.12 At a minimum, each boring shall be grouted with a weak strength mixture of cement grout and a bentonite product to promote expansion and sealing of the boring. 2.1.13 Cuttings may be used to backfill the upper 1.5 m (5 ft) of land borings or in accordance with project-specific EPP. 2.1.14 For installations that parallel an existing pipeline or utility installation, additional geotechnical investigations shall be completed if the depth of the proposed HDD installation is greater than 10 m (30 ft) below the depth of the previous installation or investigation, or if the geotechnical data is deemed to be insufficient. If required by the Company, the additional geotechnical investigations shall include completion of additional boreholes to the full depth of the proposed installation plus a minimum of 15 m (50 ft). 2.2 Sampling Interval and Technique 2.2.1 Sampling interval and technique shall be selected based on the anticipated subsurface material characteristics and site-specific conditions. 2.2.2 Standard penetration tests shall be performed during drilling to provide an indication of the relative density or consistency of the soil. 2.2.3 Split spoon samples shall be taken within soils at 1.5 m (5 ft) depth intervals, in accordance with ASTM D 1586: Standard Test Method for Penetration Test and Split Barrel Sampling of Soils. 2.2.4 Thin-wall tube samples may be taken in accordance with ASTM D 1587 Standard Practice for Thin-Walled Tube Sampling of Soils for Geotechnical Purposes. 2.2.5 Bedrock shall be continuously cored in accordance with ASTM D 2113 Standard Practice for Rock Core and Sampling of Rock for Site Investigation. 2.2.6 Percent recovery and rock quality designation (RQD) values shall be obtained during coring. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 10 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 2.2.7 Geotechnical soil/bedrock samples shall not be discarded until the successful completion of the crossing. 2.3 Laboratory Testing 2.3.1 Laboratory testing shall be completed on collected samples to provide data necessary for soil classification in accordance with ASTM D 2487 Standard Practice for Classification of Soils for Engineering Purposes (Modified Unified Soil Classification System). 2.3.2 Grain size distributions/sieve analyses shall be completed on collected coarsegrained soil samples (soils containing gravels and larger particles) in accordance with ASTM D 422 Standard Test Method for Particle-Size Analysis of Soils. 2.3.3 Unconfined compressive strength, direct simple shear and triaxial tests shall be considered for cohesive soil samples. 2.3.4 For installations in very soft or soft cohesive soils, unconfined compressive strength tests may be completed in accordance with ASTM D 2166 Standard Test Method for Unconfined Compressive Strength of Cohesive Soil. 2.3.5 For bedrock materials, the following laboratory tests shall be considered: • unconfined compressive strength tests • Cerchar abrasivity tests • splitting tensile strength (Brazilian tensile strength) tests • Modified Jar Slake Test (Santi, 1998) to characterize slake durability and slaking categories for argillaceous (clay/silt based) bedrock materials 2.4 Geotechnical Data Report Requirements 2.4.1 A geotechnical data report (GDR) shall be developed for each crossing. 2.4.2 The GDR shall present all of the factual subsurface information gathered for use in the design and construction of the HDD installation. 2.4.3 The GDR at a minimum shall include the following components: • general geologic review • description of the subsurface geotechnical exploration program • description of the laboratory testing program • borehole logs for all borings and/or test pits • all field and laboratory test results • long term monitoring data (groundwater data, slope inclinometer data, etc.) • recommendation for crossing feasibility Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 11 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 3 SURVEY REQUIREMENTS FOR HDD DESIGN 3.1 General 3.1.1 Survey shall be completed for the proposed crossing by a professional service provider that is qualified by the Company. 3.1.2 Surveyed alignments for the proposed bore path, in addition to the 2D (horizontal chainage) and 3D chainages (slack, contour, or grid chainage), shall include a Universal Transverse Mercator (UTM) coordinate, elevation, and the applied combined scale factor (CSF), if applicable, for each point generated. 3.1.3 The surveyor shall label each column appropriately so that the type of chainage used is clearly understood. 3.1.4 A hydrotechnical assessment should be performed for major waterbody crossings (i.e., major creeks, rivers, lakes) unless otherwise approved by the Company. 4 BORE PATH DESIGN REQUIREMENTS 4.1 General 4.1.1 The bore profile shall be designed within geotechnical soil or bedrock materials deemed favorable to an HDD installation, based on site-specific conditions. 4.1.2 The HDD designer shall be responsible for confirming the adequacy of the proposed geotechnical program (in consideration of the minimum requirements established below) and addressing any questions the Company may have prior to and during the field investigations. 4.1.3 The HDD designer must document the installation risks associated with the anticipated geotechnical materials on the comprehensive risk register established by the designer for the crossing. 4.1.4 The bore profile shall consider presence of no-drill zones or other identified environmentally sensitive areas (e.g., mangroves). 4.1.5 The bore profile and alignment shall meet all required federal, provincial/state and territorial regulations. 4.1.6 A horizontal tangent shall be incorporated into the HDD bore geometry to separate all curves of differing different orientation and/or design bend radii. 4.1.7 HDD entry and exit locations shall be selected in consideration of site constraints (i.e., topography, setback distance, required entry and exit angles, existing utilities, and other crossing-specific requirements). 4.2 HDD Entry and Exit Angles 4.2.1 The entry angle should range between 8° and 18°. 4.2.2 The exit angle should range between 6° and 12°. The exit angle should be as small as practical to minimize steering requirements, equipment for staging the product pipe, height of break-over geometry, and installation induced stresses as the product pipe transitions into the bore. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 12 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 4.2.3 The selection of entry and exit angles shall consider the anticipated geotechnical conditions, site constraints, topography, depth of cover, setback distance, and other crossing-specific requirements. 4.3 Depth of Cover 4.3.1 The HDD designer shall select required depth of cover based on: • anticipated geotechnical conditions • risks of an inadvertent drilling fluid return • recommendations from hydrotechnical analysis • site constraints (see section 4.1.7) • setback distance • installation length • crossing requirements • design bending radius • presence of existing pipelines, utilities and/or structures • no-drill zones (NDZ) – HDD designer shall determine NDZ based on hydrotechnical and geotechnical considerations • allowable tolerances for vertical deviation, as set in the construction part of this Standard (refer to Table 16-1 for details) • magnitude of acceptable ground surface settlements for existing pipelines, utilities, and/or structures accounting for potential over-excavation of the geotechnical materials and/or collapse of the annular space 4.3.2 Clearances between the proposed HDD bore and existing pipelines, utilities and other surface features shall be indicated on the HDD design drawing. 4.3.3 The minimum clearance between the HDD bore and an existing utility shall be 10 m (30 ft) to account for allowable grade tolerances and over-sizing of the pilot bore during reaming operations. Actual clearance shall consider requirements by the utility, grade tolerances for the pilot bore, diameter of the final bore, and the potential for reamers or hole openers to up-cut the bore during drilling operations. 4.4 Bore Tangents 4.4.1 An entry and exit tangent length of at least 15 m (50 ft) shall be incorporated into the bore geometry to avoid elastic rebound loads on the tie-in point to the pipeline. 4.4.2 A tangent of at least 15 m (50 ft) shall be used to separate curves in the bore geometry. 4.5 Radius of Curvature 4.5.1 The design bore radius of curvature should be at least 1,200 times the nominal product pipe diameter. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 13 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 4.5.2 An in-service operational stress evaluation shall be used to establish the minimum allowable pipe bending radius. Stress evaluations shall be in accordance with section 7 of this Standard. 4.6 Horizontal and Vertical Curves 4.6.1 Length of all curves shall be minimized to the maximum extent possible. 4.6.2 Horizontal and S-curves and/or drop curves should be avoided. Designs having a horizontal curve shall be authorized by the Company. 4.6.3 Where a compound curve is required, individual vertical and horizontal bend radii shall be increased such that the combined curve radius is equal to the design bending radius of at least 1,200 times the nominal product pipe diameter. 4.6.4 If a compound curve is incorporated into the design, the note related to the calculated single or three joint steering radius on the HDD design drawings shall be: “The minimum allowable compound curve steering radius shall be calculated based on the combined effects of steering in both the vertical and horizontal orientations. Under no circumstances shall the HDD Construction Contractor assume that minimum allowable compound curve steering radius be considered to apply individually to the vertical and horizontal curve radii.” 4.6.5 A combined radius of curvature shall be used where bore geometry includes concurrent vertical and horizontal curves. The combined radius shall be calculated using: π π ππ2 π π π»π»2 π π πΆπΆ = οΏ½ 2 π π ππ + π π π»π»2 Where: π π πΆπΆ = combined radius of curvature, metres π π ππ = vertical radius of curvature, metres π π π»π» = horizontal radius of curvature, metres 4.7 Setback Distance 4.7.1 A setback distance shall be designed between the entry location and the first crossing feature to provide the required depth of cover beneath all crossing features. Special consideration shall be given to local regulatory requirements, permitting requirements, river bank dynamics, depth of cover beneath thalweg, riparian areas, slope stability and other environmental features. 4.8 Installation Length 4.8.1 The design installation length shall be as short as possible. Site-specific conditions and/or other related issues (e.g., cover, geotechnical, land etc.) shall be considered for design installation length. 4.8.2 The proposed installation length shall be compared with previously completed HDD crossing lengths in similar geotechnical materials to evaluate achievable installation length based on project site conditions. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 14 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 4.8.3 Installation lengths in excess of the completed HDD installation experiences of the HDD industry shall be authorized by the Company. If authorization is required, the longer installation length shall be documented on the risk register developed by the HDD designer for the crossing. Refer to section 7.14 for further details. 5 HDD DESIGN REQUIREMENTS 5.1 General 5.1.1 The Company should perform a field reconnaissance to identify site-specific risks and constraints, preferred entry and exit locations, available staging area, existing exposures of surficial overburden and bedrock materials, and other crossing characteristics. 5.1.2 For proposed installations where an elevation difference of at least 10 m (30 ft) exists between the HDD entry and exit locations, the HDD designer should establish the HDD entry location on the lower elevation side of the crossing (or both sides should the drill and intersect approach be specified). 5.1.3 For proposed installation of pipe size NPS 36 and above, HDD entry and exit elevation shall be levelled unless approved by the Company. 5.1.4 The HDD designer shall document bore instability risks arising from a lack of supportive drilling fluid pressure within the portion of the HDD bore above the elevation of the lower side on the risk register for the crossing. Refer to section 7.14 for further details. 5.1.5 The HDD design should allow for utilization of one (1) rig at entry location and one (1) at exit location to aid with reaming and mud handling for HDD installation of NPS 36 and larger. 5.1.6 The HDD designer should assume the HDD installation temperature is -10°C (14°F). 5.2 HDD Feasibility Report Requirements 5.2.1 The HDD designer shall provide the HDD Feasibility Report. The HDD Feasibility Report shall be reviewed, checked, authenticated, and delivered to the Company for review and endorsement by the project. The minimum requirements for this document shall include: • general project and crossing information • short introduction including project description • alignment drawing • anticipated geotechnical conditions • soil and/or bedrock characterization • geohazard identification (terrain instability, hydrotechnical hazards) • HDD considerations • • entry and exit location details design bending radius Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 15 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 • • • • • • • Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 casing pipe requirements drill and intersect requirements workspace delineation fresh water requirements disposal requirements schedule duration design calculations and evaluations, including: • • • • • • • • • • • • pipeline properties minimum allowable pipe bending radius calculation single and three (3) joint pipe bending radius operating stress calculation hydraulic fracture calculation HDD installation load and stress calculations break-over stress calculation and design over-bend stress calculation and design, if applicable railroad or highway stress calculations, if applicable settlement calculations, if applicable scour and thalweg calculation for waterbodies crossings, when available other applicable calculations • detailed risk discussions including risk register • feasibility assessment and recommendations 5.3 Work Space and Staging Area 5.3.1 The HDD designer shall select entry and exit locations to provide the minimum staging area necessary for equipment and materials. Entry and exit locations should allow space (e.g., 80 m [260 ft] in width by 80 m [260 ft] in length) for temporary containment (e.g., sump pit/tank) of drilling fluids during drilling and pullback operations to minimize hydrovac traffic. Smaller staging area width and/or length may be sufficient depending on the diameter of pipe used on the project. 5.3.2 The HDD designer should center the HDD entry and exit location laterally within the workspace area. 5.3.3 The HDD designer should locate the HDD entry location within the staging area. 5.3.4 The HDD designer should select the HDD entry location such that approximately 25 percent of the length of the staging area occurs in front of the HDD entry location and 75 percent behind the HDD entry location. 5.3.5 The HDD designer should allow for a product pipe staging area of a minimum width of 40 m (130 ft) by the length of the fully fabricated product pipe plus an additional 60 m (200 ft) for vehicle turnaround. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 16 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 5.4 Drill and Intersect Installation Methodology 5.4.1 The HDD designer shall determine if a drill and intersect installation strategy should be used for each specific crossing. Consideration shall include: • requirement for temporary casing on each end of the proposed installation • installation length • site topography • anticipated and allowable drilling fluid pressures 5.4.2 The HDD designer should consider the use of the drill and intersect method for installation lengths over 1,250 m (4,100 ft). 5.4.3 The HDD designer should establish the intersection location in the horizontal tangent section of the bore, where steering requirements are minimal. 5.4.4 The HDD designer should allow for a target intersection window length of, at minimum, 200 m (660 ft). 5.4.5 The HDD designer shall identify the intersection location on the HDD design drawings. 5.5 Temporary Starter or Conductor Casing Pipe 5.5.1 The HDD designer shall determine the casing requirements for each HDD location and identify them on the HDD design drawings. 5.5.2 The HDD designer should keep the length of required casing pipe to a minimum. 5.5.3 The HDD designer should oversize the final casing pipe (i.e., minimum 300 mm [12 in.] larger than the final ream size) to allow free passage of tooling through the casing. 5.5.4 The minimum thickness of the casing pipe shall be at least 19 mm (0.75 in.). The HDD designer shall determine if additional wall thickness is required for projectspecific requirements. Casing material at a minimum shall meet ASTM A139 Standard Specification for Electric-Fusion (Arc)-Welded Steel Pipe (NPS 4 and Over) Grade B equivalent or better. 5.5.5 The HDD designer shall design for centralizing casing during all pilot bore and reaming operations. 5.5.6 In the event casing pipe is deemed necessary at the HDD entry and exit location, the HDD designer should set up the installation as a drill and intersect installation strategy. 5.5.7 The HDD designer should allow for telescoping for casing lengths of greater than 50 m (165 ft). 5.5.8 If casing is required, the HDD designer shall identify risks on casing installation and removal upon completion of pullback operations on the risk register established by the HDD designer for the crossing. Refer to section 7.14 for further details. 5.5.9 The Company shall authorize casing removal prior to pullback operations. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 17 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 5.6 Buoyancy Control Measures 5.6.1 The HDD designer shall implement buoyancy control measures to facilitate installation for all pipe diameters equal to or larger than NPS 24. 5.6.2 The HDD designer may implement for buoyancy control measures for smaller pipe diameters. 5.6.3 The HDD designer shall specify buoyancy control measures on the HDD design drawings. 5.6.4 The HDD designer should allow for use of a liner for pipe sizes greater than NPS 36 for continuous buoyancy control during pullback. 5.7 No-Drill Zone Requirements 5.7.1 The HDD designer shall consider the following inputs into the no-drill zone including, but not limited to: • regulatory or permitting requirements • setback distance or depth of cover concerns • geotechnical • slope stability • environmental • hydrotechnical 5.7.2 At no location shall the reamed diameter encroach into the no-drill zone. 5.7.3 Once the bore path has been determined, the HDD designer shall take the actual nodrill zone for the crossing as the design bore path plus any allowance for vertical deviations and final reamed diameter. 5.7.4 The HDD designer shall specify the no-drill zone on the HDD design drawings and HDD Feasibility Reports. 5.8 Intermediate Weld During Pullback Operations 5.8.1 Intermediate welds and coating application during pullback operations shall not be allowed, unless authorized by the Company. 5.8.2 Where intermediate welds are authorized by the Company, the HDD designer shall document the installation risks associated with prolonged stoppages necessary to complete an intermediate weld, NDE and coating application on the risk register established by the HDD designer for the crossing. Refer to section 7.14 for further details. 5.8.3 The HDD designer shall plan for completion of intermediate welds, NDE, and coating application before the pipe string enters the break-over section in the vicinity of the pipe entry location. The performance of intermediate welds during installation, and not previously planned during HDD design, shall be authorized by the Company. 5.8.4 An installation strategy minimizing the length of installed product pipe within the bore shall be followed to minimize the installation loads to re-establish pullback operations. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 18 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 5.8.5 The HDD designer shall define the number of required pipe strings that are separated by an intermediate weld during pullback on the HDD design drawings. 5.8.6 The HDD designer shall consider the increased force required to re-establish pullback operations following a prolonged stoppage in the estimated installation load and stress calculations. 6 CROSSING-SPECIFIC HDD DESIGN DRAWINGS 6.1 General 6.1.1 The HDD designer shall complete all HDD design drawings in accordance with the Company’s drawing standards referenced in section 23. 6.1.2 Drawings shall indicate the pipe design radius, the minimum allowable steering radius over a single joint (10 m or 30 ft) length, the minimum allowable steering radius over a three (3) joint (30 m or 100 ft) length and the maximum pullback load (with and without buoyancy control, as applicable) 6.1.3 The HDD designer shall prepare HDD design drawings for plan, profile, and breakover and pipe staging area. Drawings shall indicate entry and exit angles, tangent and arc lengths, clearance to the object of crossing, ERT and SR, soil profiles at borehole locations. Refer to APPENDIX B for sample HDD design drawings. 6.1.4 The HDD designer shall ensure HDD drawings contain the required labelling of all features, borehole logs, and construction notes to be used on each drawing. Refer to APPENDIX B for sample HDD design drawings. 6.1.5 The HDD designer shall add crossing-specific notes informing the HDD Construction Contractor of additional site-specific crossing requirements to the HDD design drawings. 7 ENGINEERING DESIGN CALCULATIONS 7.1 General 7.1.1 The HDD designer shall complete and submit the following design calculations to the Company for review for all HDD installations: • pipe wall thickness • minimum allowable pipe bending radius • Single and three (3) joint steering radius • in-service operating stresses • product pipe installation load and stresses including maximum pullback load • pullback loads and stresses with buoyancy control, if applicable • break-over stresses • over-bend stresses, as applicable • overburden pressure Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 19 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 7.1.2 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 • maximum allowable drilling pressure and zone of operating drilling pressure • hydraulic fracture evaluations The HDD designer shall complete the following design calculations for all HDD installations (if required): • highway and railroad crossing stresses • ground surface and critical utility settlements • scour and thalweg calculation for waterbodies, when available 7.1.3 The HDD designer shall provide all assumptions and input parameters. Copies of the installation load and stress calculations shall be provided in the HDD Feasibility Report. 7.1.4 References for this calculation include the latest editions of the following, as applicable: • TEN-ME-PWT-GL Pipe Wall Thickness Design Standard (CAN-US-MEX) (Item ID: 1009372841) • CSA Z662 Oil and Gas Pipeline Systems • PRCI Installation of Pipelines Using Horizontal Directional Drilling – An Engineering Design Guide (PR-227-144507) • ASCE Manual of Practice No. 108 Pipeline Design for Installation by Horizontal Directional Drilling • ASME B31.8 Gas Transmission Distribution and Piping Systems • ASME B31.4 Oil Transmission Distribution and Piping Systems 7.2 Pipe Wall Thickness 7.2.1 The HDD designer shall determine the initial minimum pipe wall thickness in accordance with the Company TEN-ME-PWT-GL Pipe Wall Thickness Design Standard (CAN-US-MEX) (Item ID: 1009372841) 7.2.2 The dimension ratio (outer diameter to wall thickness) shall be less than 60. The HDD designer shall give consideration to ratios below 50 for HDD installations with depth of cover greater than 30 m (100 ft). 7.2.3 The HDD designer shall complete minimum allowable wall thickness evaluation in accordance with the latest editions of the following standards as applicable: • CSA Z662 Oil and Gas Pipeline Systems • ASME B31.8 Gas Transmission Distribution and Piping Systems • ASME B31.4 Oil Transmission Distribution and Piping Systems • NOM-007-ASEA Transporte de gas natural, etano y gas asociado al carbón mineral por medio de ductos (Transmission of Natural Gas, Ethane and Coal Gas Through Pipelines) Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 20 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 • PRCI Installation of Pipelines Using Horizontal Directional Drilling – An Engineering Design Guide (PR-227-144507) • ASCE Manual of Practice No. 108 Pipeline Design for Installation by Horizontal Directional Drilling 7.2.4 The HDD designer shall consider the presence of rock, boulders, or other hard materials that could cause denting of the pipe for selection of the final wall thickness in addition to geotechnical data and the HDD designer’s experience. 7.2.5 The HDD designer shall not allow for wall thickness transitions to be installed within the HDD bore. 7.3 Minimum Allowable Pipe Bending Radius 7.3.1 The HDD designer shall calculate the minimum allowable pipe bending radius for the proposed pipe properties (e.g., pipe diameter, wall thickness, pipe grade or specified minimum yield strength [SMYS]) using the design and location factors and maximum in-service operating conditions (including pressure and thermal expansion temperature). 7.3.2 The HDD designer shall design the minimum allowable single joint steering radius to be equal to or greater than the minimum allowable pipe bending radius. 7.4 Pipe Design Bending Radius 7.4.1 The HDD designer shall design the pipe design bending radius to at least 25 percent greater than the minimum three (3) joint allowable steering radius to allow for steering corrections during the HDD installation. 7.4.2 The HDD designer shall ensure the minimum allowable pipe bending radius limits the maximum shear stress in the pipe to 45 percent of SMYS when subjected to the maximum in-service operating conditions. 7.5 Steering Radius 7.5.1 The HDD designer shall design the minimum three (3) joint allowable steering radius to be at least ten (10) percent greater than the minimum single joint allowable steering radius. 7.5.2 The minimum allowable steering radii (for single and three pipes joint length) shall consider the ease of passing the required tool through the bore without over stressing reamers or hole openers in areas of reduced bore curvature from the design radius. 7.6 In-Service Operating Stress 7.6.1 The HDD designer shall complete the in-service operating stress in accordance with PRCI design guidelines or ASCE Manual of Practice No. 108, as suggested by CSA Z662 and ASME B31.4 and B31.8 for HDD applications. 7.6.2 Calculations shall consider: • proposed pipe properties (pipe diameter, wall thickness, pipe grade or SMYS) • design and location factors • operating conditions Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 21 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 • maximum operating pressure • temperature conditions of the pipeline (lowest installed temperature and maximum operating temperature) 7.6.3 The HDD designer shall base all stress calculations on the minimum allowable pipe bend radius for the selected product pipe (as opposed to the higher design bend radius used to establish the bore path geometry). 7.6.4 The HDD designer shall calculate and document all longitudinal, hoop and combined bi-axial stress states. 7.6.5 The HDD designer shall complete and compare calculated stresses to limit values provided in the reference codes and standards found in section 7.1.4 . 7.7 Hydraulic Fracture Evaluation 7.7.1 The HDD designer shall complete hydraulic fracture or hydrofracture evaluations along the design alignment and in consideration of the allowable vertical deviation during construction. 7.7.2 The HDD designer shall complete hydraulic fracture calculations in accordance to the Delft Geotechnics approach as outlined in Appendix A of Guidelines for Installation of Utilities beneath Corps of Engineers Levees Using Horizontal Directional Drilling for all soil installations. Bedrock installations shall also be based on this method, applying appropriate soil strength parameters (degree of jointing and fracture determining strength parameters) to the bedrock materials. Following items shall be considered in the hydraulic fracture calculations: 7.7.2.1 The HDD designer shall identify all input parameters, including unit weights (saturated and unsaturated), cohesion, internal angle of friction, shear modulus, pilot bore radius, radius of plastic zone, mud properties (i.e., mud weight, yield point, plastic viscosity). 7.7.2.2 The HDD designer shall take a conservative approach for all input parameters. This conservative approach refers to the selection of strength properties for the overlying geotechnical materials. Engineering judgment is required to identify the appropriate input parameters. Reliance on high strength values (i.e., cohesion, internal angle of friction and shear modulus) shall be clearly identified and discussed with Company. Justification for input parameters shall be provided in the Feasibility Report. 7.7.2.3 The HDD designer shall base the total overburden stress calculations on the actual soil/bedrock layers along the alignment. Input parameters shall be selected based on the anticipated stratigraphy of the geotechnical materials. 7.7.2.4 The HDD designer shall base the maximum allowable radius of the plastic zone on limiting this radius to competent layers that provide sufficient strength to resist drilling fluid pressures. This radius shall be limited to a maximum of three (3) times the pilot hole diameter and shall not extend into layers containing very soft to soft cohesive soils and/or very loose to loose cohesionless soils. 7.7.2.5 The HDD designer shall take the minimum required pressure as the required pressure necessary to complete the installation, based on anticipated drilling fluid parameters (i.e., pump rate, annular velocity, and drilling fluid properties). The Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 22 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 required pressure shall consider both the hydrostatic pressure exerted by the column of drilling fluid at any given location and the dynamic pressure required for drilling fluid flow to the HDD entry location. 7.7.2.6 The HDD designer shall ensure the anticipated circulating pressure (lower limit of the required drilling fluid pressure range) is below the calculated total overburden stress along the alignment. 7.7.2.7 The HDD designer shall apply a factor of safety of 2.0 to the calculated pressure threshold to determine the depth of cover requirements. Consideration shall be given to a higher factor of safety for crossings of highly sensitive areas. 7.7.3 The HDD designer shall complete calculations at a minimum of every 10 m (30 ft) along the HDD alignment and at critical areas not captured with this frequency. 7.7.4 The HDD designer shall ensure that hydraulic fracture evaluations identify the anticipated required drilling fluid pressure range based on the geotechnical materials and their anticipated strength. 7.7.5 The HDD designer shall determine the lower limit of the required drilling fluid pressure range using anticipated drilling fluid properties and flow rate. 7.7.6 The HDD designer shall design the upper limit of the required drilling fluid pressure range to not exceed the lower limit by more than 25 percent. 7.7.7 The HDD designer shall identify the calculation method used to complete the drilling fluid pressure calculations in the Feasibility Report. All factors of safety applied to the calculations shall be clearly identified. 7.7.8 The HDD designer shall produce a drilling fluid pressure chart that is part of HDD profile drawing, and is included in the HDD Feasibility Report and HDD design report. This chart shall identify the following parameters along the HDD alignment and beneath all critical features: 7.7.9 • ground surface profile • design alignment • required drilling fluid pressure and the required drilling fluid pressure upper limit (defined as 125 percent of the required drilling fluid pressure) • zone of operation clearly identified (pressure between required drilling fluid pressure and drilling fluid pressure upper limit) • overburden resistance based on Delft approach and applied safety factor of 2.0 • total overburden stress (soil limiting overburden and rock limiting overburden) • drill path The HDD designer shall provide all calculations, assumptions and input parameters in the HDD Feasibility Report. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 23 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 7.8 Product Pipe Installation Load and Stresses 7.8.1 The HDD designer shall complete installation loads and stress calculations in accordance with PRCI design guidelines and ASCE Manual of Practice No. 108, as suggested by CSA Z662, ASME B31.4 and B31.8, and all other applicable industry standards for HDD applications as referenced in section 23. 7.8.2 The HDD designer shall complete the input of the pipe profile relative to project location and elevation, segment horizontal length, segment radius and segment inclination. 7.8.3 When elevations are not provided, the HDD designer shall establish an arbitrary reference elevation and station for recording the ground surface and bore entry and exit elevations. 7.8.4 Where possible, the HDD designer shall take pipe profiles from AutoCAD renderings. If AutoCAD files are unavailable, profile elevations shall be interpreted from hard copy renderings that have been printed to scale. 7.8.5 The HDD designer shall use all tangents and vertical and/or horizontal curves in determining the estimates of installation loads and stresses. The addition of more than two alignment curves and additional tangent segments require modification to installation load and stress calculations to include the additional curve and straight sections. Averaging or simplification of the bore alignment is not permitted. 7.8.6 The HDD designer shall use a combined radius of curvature where bore geometry includes concurrent vertical and horizontal curves. The combined radius shall be calculated as specified in section 4.6.5. 7.8.7 The HDD designer shall calculate installation loads in the direction from the pipe entry location to the exit location. 7.8.8 The HDD designer shall include tail string loads in the installation load evaluation. Loads associated with the tail string shall decrease as more of the product pipe is installed. 7.8.9 The HDD designer shall calculate tail string loads using the weight of the pipeline, the friction coefficient of the rollers and the pipe string length. 7.8.10 The HDD designer shall identify all input parameters, including pipe weight (in air), buoyant or effective pipe weight, downhole drilling fluid weight, frictional drag coefficient, fluidic drag coefficient, roller coefficients, etc. and provide them in the HDD Feasibility Report. 7.8.11 The HDD designer shall use dynamic friction coefficients to estimate moving and start-up loads. Static friction factors following prolonged stoppages for intermediate welds shall be 1.5 to 2.5 times higher to reflect the higher installation loads encountered when re-establishing pullback operations. 7.8.12 Where intermediate welds have been authorized by the Company, calculations shall consider increased installation loads associated with prolonged stoppages for completion of intermediate welds, NDE and coating application during pullback operations. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 24 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 7.8.13 Calculated stresses shall be compared to limit values in accordance with Company stress specifications referenced in section 23 and PRCI, PR-227-144507 Installation of Pipelines Using Horizontal Directional Drilling – An Engineering Design Guide. All bending stress calculations shall be based on both the design radius and the minimum allowable pipe bend radius to be used during construction. 7.8.14 The HDD designer shall ensure stress calculations include tensile stress, bending stress, external hoop stress, and combined installation stresses (combinations of tensile, bending, and external hoop stresses). 7.8.15 The HDD designer shall limit tensile stress to 60 percent of the SMYS for all pipe diameters. 7.8.16 If more than one maximum tensile stress is determined for a given pull section, the greater shall govern for calculation of pull loads. 7.8.17 The HDD designer shall provide copies of the installation load and stress calculations in the HDD Feasibility Report. 7.9 Roller Spacing 7.9.1 The HDD designer shall determine and check the maximum roller spacing for the product pipe. 7.9.2 The HDD designer shall verify that stresses from rollers spacing stress evaluation such as bending and uniform axial stresses induced in the pipe due to self-weight and other loads (e.g., pipe filled with water due to buoyancy control or pressure testing) do not exceed 80% of SMYS. 7.9.3 The HDD designer shall ensure the maximum roller spacing does not allow the product pipe to come into contact with the ground between supports. 7.10 Break-Over Stress Evaluation 7.10.1 The HDD designer shall perform the break-over stress evaluation. 7.10.2 The HDD designer shall complete break-over stress evaluations in order to determine the required sideboom and/or crane spacing and lift heights. A minimum allowable bend radius of 600 times the nominal product pipe diameter should be considered in the calculation. 7.10.3 The HDD designer shall avoid a compound radius for the break-over section. If a compound bend is required within the break-over section, the horizontal bending should be facilitated across different sidebooms and/or cranes, forward of the sidebooms and/or cranes facilitating vertical bending. 7.10.4 The HDD designer shall include a tangent at the pipe entry location that is at least 5 m (15 ft) in length and in-line with the HDD installation in the break-over geometry to avoid the product pipe from contacting the bore or casing pipe wall. 7.10.5 When a break-over profile does not have a constant bend radius which results in a complex stress profile, the HDD designer should perform calculations using structural finite element software. (e.g., AutoPIPE). Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 25 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 7.10.6 The HDD designer shall calculate contact stresses on the pipe wall from roller cradles, side booms and other lifting points to determine that loading will not damage the pipe. 7.10.7 The HDD designer shall verify that break-over installation stress from bending and uniform axial stresses induced in the pipe due to the sideboom and/or crane spacing, self-weight, bore entry and other loads shall not exceed 80% of SMYS. 7.11 Over-Bend Stress Evaluation 7.11.1 The over-bend stress evaluation may be performed by another design contractor. 7.11.2 Over-bend stress evaluations shall be completed in order to determine the stresses during in-service design conditions for the elbow or cold bend connecting the mainline pipeline to the HDD section. 7.11.3 Stress calculations shall be performed in accordance with Company pipeline stress analysis specification TES-ME-STRPI-GL Pipeline Stress Analysis Specification (CAN) (Item ID: 1005882376) and the references listed in section 23, as applicable. 7.11.4 Stress calculations shall consider the geometry and soil conditions on the adjoining pipeline for a length at least equal to the calculated virtual anchor length beyond the HDD tie-in point. 7.11.5 Calculations shall be performed using structural finite element software (e.g., AutoPIPE). The HDD designer or other design Contractor must seek authorization from the Company for proposed software prior to use for this evaluation. 7.11.6 The software calculated stresses shall be completed and compared to allowable stress limits provided in the codes and standards reference in section 7.1.4. 7.12 Highway and Railroad Crossing Stress Evaluation 7.12.1 The HDD designer shall complete railroad and highway crossing evaluations in accordance with the following, as applicable: • Transport Canada, TC E-10 • American Railway Engineering and Maintenance-of-Way Association (AREMA) Specifications Part 5 Pipeline • API Recommended Practice 1102 • specific railroad owner requirements/specifications 7.12.2 The HDD designer shall use the associated railroad or highway specification for pipeline occupancy in the evaluation. The more stringent of the specifications shall govern. 7.12.3 Where possible, the HDD designer shall take the installation details beneath railroad tracks and highways from AutoCAD renderings. If AutoCAD files are unavailable, profile elevations shall be interpreted from hard copy renderings that have been printed to scale. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 26 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 7.13 Ground Surface Settlement Evaluation 7.13.1 If required by the Company, the ground surface settlement evaluation may be performed by another contractor. 7.13.2 Estimated ground surface settlements should be evaluated for critical crossing locations including, but not limited to, highway crossings, railroad crossings and nearby surface structure crossings. 7.13.3 Settlement calculations should be completed using a normal distribution probability curve approach. If completed, calculation shall be submitted to the Company for review. 7.13.4 Settlement calculations should consider any allowances for vertical deviations along the proposed HDD alignment. 7.13.5 Ground surface settlement evaluations should be completed based on the following conditions: • full annular space collapse • partial annular space of 75 percent of the annular space • partial annular space of 50 percent of the annular space 7.13.6 The HDD designer shall document the ground surface settlement risks for each of the above considerations (including probability of occurrence) on the risk register for the crossing. Refer to section 7.14 for further details. 7.14 Risk Characterization 7.14.1 The HDD designer shall complete a formal evaluation and submit an HDD risk register to the Company. 7.14.2 The HDD risk register shall identify the risk and/or opportunity, probability of occurrence, consequence of risk and/or opportunity, and proposed mitigation for any risk. 7.14.3 The HDD designer shall revaluate identified risks as the design matures, additional information becomes available and as design changes are completed to ensure the likelihood and potential impacts are not affected. 7.14.4 The HDD risk register shall be a living document and updated through the design and construction phases of the project. 8 CONSTRUCTION REQUIREMENTS 8.1 Company Responsibilities 8.1.1 The Company shall supply the following, unless otherwise specified in the Agreement: • Environmental Protection Plan • monitoring and reporting of water quality (turbidity), if applicable • product pipe for pullback • an engineered crossing design drawing showing the crossing in plan and profile Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 27 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 • Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 geotechnical report 8.2 Environmental Plan 8.2.1 The HDD Construction Contractor shall comply with all environmental requirements contained in the contract and HDD design drawings, including the Company’s Environmental Protection Plan. 8.2.2 The HDD Construction Contractor shall implement noise control measures as mandated by legislative or permit requirements. 8.3 Safety Plan 8.3.1 The HDD Construction Contractor shall include a site-specific safety plan with its sitespecific HDD Execution Plan and shall meet or exceed all legislative and Company requirements. 8.3.2 Compressed air shall not be used to clear mud and/or liquid lines unless the system is specifically designed and inspected by a Professional Engineer. 8.4 Workspace and Access Requirement Drawing 8.4.1 The Company shall identify the workspace and access requirements to the HDD Construction Contractor. 8.5 Drilling Schedule and Planning 8.5.1 The HDD Construction Contractor shall submit a drilling schedule for Company review. 9 SITE-SPECIFIC HDD EXECUTION PLAN 9.1 General 9.1.1 The HDD Construction Contractor shall submit a site-specific HDD Execution Plan in accordance with the HDD design drawings. 9.1.2 The site-specific HDD Execution Plan shall outline the procedures to be used in the completion of drilling, including • lifting and pullback plan • drilling rig anchoring plan • drill pipe inspection plan • site-specific contingency plan • casing installation and removal plan, including equipment list, centralization method, seal check procedure, welding procedure, installation, removal methods • design drawing and detail use of a casing driving shoe (as applicable) • site-specific environmental monitoring plan • engineered drilling fluid management plan • site-specific safety plan Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 28 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 • the use of drill bit directing and tracking equipment to confirm the drill path while avoiding the no-drill zone and providing acceptable as-built information • list of competent personnel executing the HDD • plan workspace requirements for equipment at entry and exit points, and to layout pipe drag section as provided by the Company in the HDD design drawings • drilling equipment specifications, condition, and integrity • a survey cable layout sketch intersect method (if required) • pilot hole size, each reaming step size, and final hole size • swab or cleaning run assembly details • anticipated and maximum penetration rates to maintain for the subsurface formations • chronological drilling, reaming, and pullback plan describing sequence, size and cutting direction of drilling and reaming passes, expected direction of fluid flow, and fluid and cuttings handling provisions • accommodation requirements • plan for site grading and preparation including support mats (or as per the Agreement) 9.2 Lifting and Pullback Plan 9.2.1 The HDD Construction Contractor shall provide a lifting and pullback plan to the Company for review 14 days prior to the pullback operation, including: • equipment size • type • spacing • lift heights 9.2.2 The lifting equipment shall be capable of withstanding the maximum pullback forces with a safety factor of 2.0. 9.2.3 The final lifting and pullback plan shall include a list of equipment to be used, with load support capacity. 9.2.4 Lifting and pullback plan shall be in accordance with the HDD design drawings. Minimum break-over radius as defined in HDD design drawings shall be adhered to during pullback. 9.2.5 The HDD Construction Contractor shall submit any deviation from the final lifting and pullback plan to the Company for review. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 29 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 9.3 Drill Rig Anchoring Plan 9.3.1 The HDD Construction Contractor shall provide a site-specific drill rig anchoring plan, authenticated by a Professional Engineer, certifying the suitability of the proposed anchoring system, to be included in the site-specific HDD Execution Plan. 9.3.2 The drill rig anchor shall be sufficient to withstand expected pulling loads, plus a 50 percent safety factor or maximum rig pull capacity, whichever is greater. 9.4 Site-Specific Contingency Plan 9.4.1 The HDD Construction Contractor shall provide a site-specific contingency plan including a frac-out mitigation and response plan for the Company to review at least 30 days prior to commencement of the work. 9.4.2 The site-specific contingency plan shall address: • mitigation of potential detrimental effects of geological formations • loss of circulation, high and low annular pressure, and inadvertent drilling fluid migration and release • collecting and cleaning after drilling fluid releases, including detailed descriptions of all equipment and materials to be used, and an inventory of equipment and materials to be on site • all of the following events: • • • • • • • • • • a product pipe becoming stuck severe damage of coating severe product pipe damage and/or drill hole collapse during pullback casing removal difficulties equipment lost in the hole steering correction procedure and contingencies for variation from design site preparation plans, including provisions for spill prevention and containment site-specific disposal plan inventory of equipment and material on site for fluid release notification, containment, and response mechanisms 9.4.3 The HDD Construction Contractor shall update the site-specific contingency plan as necessary and submit for the Company’s review. 9.5 Engineered Drilling Fluid Management and Composition Plan 9.5.1 The HDD Construction Contractor shall provide an engineered drilling fluid management plan for the Company to review at least 30 days prior to commencement of the work. 9.5.2 The engineered drilling fluid management plan shall include: • water volume requirements, including total and maximum daily rate consumed Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 30 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 • drilling fluid system, including recycling equipment (specify capacity of fluid system and supporting equipment) • model of expected circulating and hydrostatic annular pressure • drilling fluid pressure calculations • drilling fluid composition, including additives • Safety Datasheet (SDS) for both the drilling fluid and additives • target drilling fluid properties • minimum and maximum fluid viscosities that shall be maintained in sand, silt, clay, rock, and gravel (if applicable) • minimum and maximum fluid densities that shall be maintained in sand, silt, clay, rock, and gravel (if applicable) • proposed maximum percentage of solids to be maintained during the drilling operation; describe the operation that shall be implemented if the percentage of solids exceeds the proposed maximum • total volume of mixing tank (m3) or (ft3) • total volume of cleaning tank (m3) or (ft3) • anticipated mud pump volumes (m3/min) or (ft3/min) to maintain on each reaming pass for clay, sand, silts, rock, and gravel where applicable • available volume of water storage on site (minimum 50 m3) or (1,766 ft3) • equipment (e.g., pumps, hoses) required to obtain water • estimated disposal volumes for solids and liquids • drilling fluid and hole cuttings disposal method and location as provided by the Company • sample drilling fluid daily report 9.5.3 The HDD Construction Contractor shall submit SDS for any changes to the drilling fluid composition or use of additives during construction for Company review. 9.5.4 Any additives not included in the plan will not be allowed on-site or used without prior Company review. 9.6 Drilling Equipment Specifications, Condition and Integrity 9.6.1 The HDD Construction Contractor shall provide a site-specific drilling equipment list for the Company to review at least 30 days prior to commencement of the work. 9.6.2 The drilling equipment as stated below shall meet the minimum requirements as outlined in the HDD design drawings or as prescribed by the Company: • type of drilling rig, including push and pull force and rotary torque capabilities Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 31 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 • pilot survey equipment types and specifications (including accuracy) with sketch of tracking cable layout • type of pilot hole bits (include manufacturer, model, size, and type) • type of hole opening tools (include manufacturer, model, size, and type) • type of pullback swivels • diameter, type, and grade of the drill pipe • type of mud motor (if applicable) • electronic drilling recorder (EDR) type and functions monitored • annular pressure monitoring equipment type and specifications • location of survey probe in relation to drill bit • location of down-hole annular pressure monitoring in relation to drill bit • scalping shakers – quantity and mesh size • desander/desilter cones – quantity • desander/desilter cleaning ability – m3/min or ft3/min • centrifuges – quantity • centrifuges cleaning ability – m3/min or ft3/min • mud pumps capabilities (entry side): manufacturer, liner size, maximum pressure, maximum flow rate (m3/min) or (ft3/min) and (m3/stroke) or (ft3/stroke) • mud pumps capabilities (exit side): manufacturer, liner size, maximum pressure, maximum flow rate (m3/min) or (ft3/min) and (m3/stroke) or (ft3/stroke) • spare equipment and parts inventory 9.7 Site-Specific Disposal Plan 9.7.1 The HDD Construction Contractor shall include a site-specific disposal plan for drilling fluid and cuttings for review by the Company. 9.7.2 The plan shall include: • description of Contractor’s plans for disposal of drilling fluid and cuttings • contact information (e.g., names, addresses, telephone numbers) of subcontractors performing any portion of the disposal activities • anticipated intervals of disposing of the drilling fluid (duration between loads and volume per load) • estimated quantities to be disposed • disposal equipment • disposal location as provided by the Company Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 32 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 9.7.3 The site-specific disposal plan shall be updated when necessary, and submitted to the Company prior to commencement of work for review. 10 CONSTRUCTION EXECUTION – GENERAL REQUIREMENTS 10.1 Protection of Other Facilities 10.1.1 The HDD or Mainline Construction Contractor shall, prior to commencing the drilling operation, contact the appropriate utility locating service specific to each site, confirm and positively locate and stake all existing underground facilities, and modify drilling practices and down-hole assemblies to prevent damage to underground or aboveground facilities. 10.1.2 The HDD or Mainline Construction Contractor should expose all existing underground facilities crossing the drill path. 10.1.3 The HDD or Mainline Construction Contractor shall prevent damage to adjacent structures or facilities (above or below ground) due to its HDD operation. 10.2 Workspace and Access 10.2.1 The HDD or Mainline Construction Contractor shall review the HDD design drawings and perform a site visit, as required, to confirm work can be performed in the space and location provided by the Company and confirm with the Company in writing. 10.2.2 The Company shall mark the boundaries of construction workspace and sensitive areas. 10.3 Water Sources Used for HDD 10.3.1 The Company shall identify water sources and obtain any required permits for water withdrawal. 10.3.2 The HDD or Mainline Construction Contractor shall comply with site-specific environmental plans. 11 CONSTRUCTION EXECUTION – DRILLING OPERATION 11.1 Equipment Standard 11.1.1 The HDD equipment shall meet the requirements of the HDD design drawing. 11.1.2 The HDD rig shall have the capacity of 1.5 times the calculated maximum theoretical pull force. 11.1.3 The HDD Construction Contactor shall ensure all tanks, piping, portable lines, hoses and connections are suitable and rated for the service in which they are used. 11.1.4 The HDD Construction Contactor shall ensure all pressure containing tanks, piping, portable lines, hoses and connections are free of wear or damage prior to pressurizing. 11.2 Lost or Lodged Tools 11.2.1 The HDD Construction Contractor shall report any tool or other metal object lost or lodged downhole to the Company. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 33 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 11.2.2 The HDD Construction Contactor shall fully recover objects and put aside for Company inspection prior to pipe pullback operation. Failure to recover metal objects lost or lodged downhole in a reasonable time may result in rejection of the drill hole. 11.3 Inspection of Drill Pipe and Other Tubulars 11.3.1 The HDD Construction Contactor shall use API 5D double white band, of sufficient size and grade to support the required torsional and longitudinal loads required for the HDD installation for the work. 11.3.2 For ream sizes 762 mm (30 in.) and greater, 6 5/8 in. or greater drill pipe shall be used. Consideration should be given to using 7 5/8 in. drill pipe for ream sizes 1067 mm (42 in.) and greater. 11.3.3 A third-party inspector shall inspect and certify downhole tools such as crossover subs, monels and heavy weight pipe as well as threaded connections on items such as pullback swivels and reamers after any previous use, prior to project start and again prior to each subsequent drill. The third-party inspector shall provide inspection documentation to the Company prior to project start. 11.3.4 The third-party inspector shall inspect and certify drill pipe after any previous use, prior to project start and again prior to each subsequent drill. The third-party inspector shall provide inspection documentation to the Company prior to project start. 11.3.5 The HDD Construction Contractor shall develop and implement an intermediate inspection plan (as part of the HDD Execution Plan) for drill pipe to monitor and confirm the integrity of the drill pipe being used during drilling. 11.3.6 The inspection plan shall, as a minimum, consist of visual, ultrasonic, thread, and wall thickness testing in accordance with API 5D and API RP-7G on a specified percentage of the drill pipe. The HDD Construction Contractor shall submit the results to the Company in accordance with the Company-reviewed plan 11.3.7 As a minimum, HDD Construction Contractor shall re-inspect all drill pipe, subs, and bottom hole assemblies after the completion of each 42 inch and larger ream pass during the HDD installation. 11.3.8 The third-party inspector shall inspect drill pipe and crossover subs (i.e., wobble joint) on either side of reamer 762 mm (30 in.) and greater prior to re-use. HDD Construction Contractor shall replace the wobble joints with newly inspected drill pipe. Previously used wobble joints shall only be re-used after the pipe joints are fully inspected and certified. 11.4 Electronic Drilling Recorder (EDR) 11.4.1 The HDD Construction Contractor shall supply and operate an Electronic Drilling Recorder (EDR) for rig size greater than or equal to 100,000 lbs, including modification of HDD equipment to accommodate the EDR equipment. 11.4.2 The EDR shall continuously and accurately record drill string axial and torsional loads, drill string rotations per minute, drilling fluid pump rate and discharge pressure, bit depth, stand pipe drilling fluid pressure, annular pressure, drilling fluid tank volumes, and instantaneous rate of penetration. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 34 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 11.4.3 The EDR shall record each of the above listed parameters on a one-minute basis or at least every 0.1 m or (4 in.), whichever is more frequent. 11.4.4 The HDD Construction Contractor shall supply the Company with separate access to these readings (e.g., Pason), as well as provide real-time access to data for on and off-site viewing. 11.5 Casing Requirements 11.5.1 The HDD or Mainline Construction Contractor shall be responsible for installing casing pipe (if required) to facilitate the drill. 11.5.2 If the casing length specified in the drawings cannot be installed in one section, the HDD or Mainline Construction Contractor shall telescope the casing to reach the final length by installing the required diameter casing within a larger initial casing as far as practical. 11.5.3 The HDD or Mainline Construction Contractor shall provide a welded casing procedure in accordance with CSA Z662 and/or other industry-applicable specifications for the Company’s review (NDE may be required by the Company). 11.5.4 The HDD or Mainline Construction Contractor shall ensure all welds required for casing pipe are sufficient to resist the loads necessary to install the casing prior to pilot bore drilling and full removal following completion of drilling operations. 11.5.5 The HDD or Mainline Construction Contractor shall install a centralizer casing within the specified casing to allow the pilot hole to exit the casing coaxially to the longitudinal axis of the specified casing. 11.5.6 The HDD or Mainline Construction Contractor shall install an engineered reinforcing shoe to achieve a minimum of double the casing’s wall thickness for at least the first 1 m (39 in.) of the leading edge of each casing diameter. 11.5.7 The HDD or Mainline Construction Contractor should not conduct auguring within 5 m (16 ft) of the casing’s leading end (if it is submerged in the water table) to reduce the risk of subsidence. 11.5.8 The HDD or Mainline Construction Contractor should keep the casing full of water or drilling fluid to an elevation of 1 m (39 in.) higher than the water table to balance the hydrostatic pressure and reduce the risk of subsidence. 11.5.9 After installing the casing to the final depth, the HDD or Mainline Construction Contractor shall fill the casing with water or drilling fluid, and the resulting conditions monitored to ensure a seal exists between the casing and sub-surface materials. 11.5.10 If the casing does not seal, the HDD or Mainline Construction Contractor shall hammer additional casing until the fluid level in the casing does not drop (to prevent fluid migration from the borehole). 11.5.11 The HDD Construction Contractor shall install the casing in accordance with HDD design drawings. 11.5.12 Casing material shall be steel, free of cracks and free of deformations greater than two percent of the casing diameter. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 35 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 11.5.13 Casing material shall meet ASTM A139 Grade B equivalent or better. 11.5.14 Spiral weld pipe shall not be used as a casing material. 11.5.15 The HDD Construction Contractor shall provide the procedure to follow to ensure free passage of drill bits, reamer assemblies, and pull head assembly through the casing pipe’s leading edge, where the pipe is pulled into the casing. 11.5.16 The HDD Construction Contractor shall give consideration to the upward or downward cutting of the tooling in the vicinity of the casing pipe’s leading edge to avoid snagging the leading-edge during assembly passage. 11.5.17 Upon completion of the HDD, the HDD or Mainline Construction Contractor shall completely remove the casing. 11.5.18 Any casing which fails to meet the requirements of this Standard shall be removed and replaced by a new casing that meets all requirements. 11.6 Radio Communication and Access to Instruments 11.6.1 The Company shall have access inside the drill cab, separation plant and to all instruments and their readings at all times. 11.6.2 The HDD Construction Contractor shall provide a two-way radio and the frequencies used on-site to the Company prior to commencement of drilling operation. 11.7 Reporting of Drilling Status 11.7.1 The HDD Construction Contractor shall submit daily drilling status reports (on Company-approved forms) to the Company at end of each work shift. 11.7.2 The daily reports shall include the following information: • supervisor on site, crew members on site, shifts, and time worked • description of the work, tools in use, meterage completed • daily total of drilling fluid components used, and total quantities used to date • loss of drilling fluid circulation and time of occurrence • quantity of drilling fluid lost or released and status of the clean-up, as applicable • deviations between the recorded position of the drill string and the HDD design drawings and/or radius violations shall be documented and immediately brought to the attention of the Company. • maximum torque and thrust values on each pilot or reaming joint • reasoning for any excessive torque or thrust or pullback values beyond normal operating conditions • penetration rates for each pilot or reaming joint • copy of directional survey report, data verification report and report from survey tracking, including calculated one and three joint radii (e.g., ParaTrack or equivalent system) during pilot and reaming operations Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 36 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 • calculated three-dimensional coordinates, measured depth, inclination measurement, azimuth measurement, type of survey (down-hole tool or surface tracking), and the corresponding measured drilled radius for each survey point during pilot and reaming operations. These items shall be listed by the measured distance along the drilled path at each survey point. • annular pressure recorded for each joint drilled (i.e., minimum, maximum, and average) • annular pressure in electronic format (e.g., excel chart) • volumes added to the drilling fluid system • drilling fluid system updates 11.7.3 The HDD Construction Contractor shall report data in a format suitable for independent calculation of the pilot hole profile. The Company reserves the right to request this information at any time or during any shift. 11.7.4 The HDD Construction Contractor shall provide continuous and open access to the Company for all drilling operations, plans and data. 12 CONSTRUCTION EXECUTION – DRILLING FLUID SYSTEM 12.1 Instrumentation 12.1.1 The HDD Construction Contractor shall locate the downhole annular pressure monitoring equipment as close to the drill bit as possible. 12.1.2 The Company shall have access to these instruments and their readings at all times. 12.2 Drilling Fluid Pressure and Circulation 12.2.1 The HDD Construction Contractor shall maintain annular pressure within the zone of operation in accordance with the HDD design drawings. 12.2.2 The HDD Construction Contractor shall take immediate steps to restore full circulation if annular circulation is lost. 12.3 Drilling Fluid Containment Management 12.3.1 The HDD Construction Contractor shall provide adequate containment wherever rigs are located. 12.3.2 The containment shall be of sufficient size to contain all drilling fluids resulting from the drilling operation. 12.3.3 The HDD Construction Contractor shall remove all fluid and solids upon completion, and dispose of the fluids and solids at Company-approved disposal sites. 12.3.4 All containment shall comply with project-specific EPP. 12.3.5 The HDD Construction Contractor shall not discharge water, drilling fluid or cuttings into any watercourse or area surrounding the drilling sites unless at a Companyapproved disposal location. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 37 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 13 CONSTRUCTION EXECUTION – DRILLING FLUID COMPOSITION 13.1 Drilling Fluid Properties 13.1.1 Any drilling fluid and additives not included in the site-specific HDD Execution Plan shall not be allowed on-site without prior approval from the Company. 13.1.2 The HDD Construction Contractor shall stay within the threshold limits for each additive on the approved list. Refer to project-specific EPP. 13.1.3 The HDD Construction Contractor shall use clean mud for circulation and return mud shall be maintained to a weight of no greater than 1,200 kg/m3 (74.9 lbs/ft3) and a funnel viscosity within a range of 70 to 110 s/l (seconds per litre) (66 to 104 s/qt [seconds per quart]). Each mud cleaning component shall be capable of cleaning mud to the weight and viscosity required to match the full mud pump capacity. 13.1.4 The HDD Construction Contractor shall submit, at least 72 hours in advance, a Safety Data Sheet (SDS) for any changes to the drilling fluid properties or use of additives during construction, for Company approval. 13.2 Reporting of Drilling Fluid Properties 13.2.1 The HDD Construction Contractor shall check and record drilling fluid properties in accordance with the latest edition of API RP 13B-1 Recommended Practice for Field Testing Water-based Drilling Fluids. 13.2.2 The HDD Construction Contractor shall record the test results for clean and return mud every four (4) hours (minimum) in the drilling fluid report. 13.2.3 The HDD Construction Contractor shall submit a copy of the drilling fluid report to the Company at the end of each shift. 13.2.4 The drilling fluid report should include the following: 13.2.5 • drilling fluid density or weight, at both the intake to the drilling fluid cleaning system and in the suction pit, for the drilling fluid pump • viscosity, including apparent viscosity, plastic viscosity, and yield point • funnel viscosity, using a marsh funnel • solids and sand content • chemical quality of make-up water and drilling fluid (e.g., pH, chlorides, hardness, sodium) • a detailed log of tank volumes and water make-up volumes The HDD Construction Contractor shall collect a sample (minimum of 500 g [1 lb]) of the pilot hole drill cuttings for every joint of drilled pipe for further laboratory analysis if deemed necessary by the Company. The sample shall be clearly marked with measured depth, date and time and be submitted to the Company. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 38 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 14 CONSTRUCTION EXECUTION – DISPOSAL OF DRILLING FLUID AND CUTTINGS 14.1 General 14.1.1 The Company may supply a disposal location and disposal permit for approved drilling fluid and cuttings. 14.2 Disposal Reporting 14.2.1 The HDD Construction Contractor shall submit daily disposal reports to the Company. 14.2.2 The reports should include the following: • certification of disposal equipment cleaned and un-contaminated prior to use • lab sample results in accordance with disposal permit • the quantity of drilling fluid and cuttings hauled from drill sites • a bill of lading or trip ticket for each truck load 15 CONSTRUCTION EXECUTION – DRILLING FLUID MIGRATION, PREVENTION, AND RESPONSE 15.1 General 15.1.1 The Company may designate certain facilities (e.g., highways or sensitive natural areas) for the HDD Construction Contractor to monitor full-time during drilling operation. 15.1.2 The spill containment and collection equipment shall be capable of containing and collecting a typical release of drilling fluids to the ground surface, wetlands, or water bodies. 15.1.3 The HDD Construction Contractor shall immediately cease drilling and notify the Company upon detection of reduced drilling fluid returns, drilling fluid and/or mud release to the ground surface or water body, or detection of drilling fluid and/or mud migration under pavement, foundation, utilities or other structure. Operations shall not resume without the Company’s approval. 15.1.4 The HDD Construction Contractor shall clean all areas affected by drilling fluid migration and restore to requirements of regulatory agencies having jurisdiction, and to the original condition. 15.2 Minimum Pump Pressure 15.2.1 The HDD Construction Contractor shall maintain drilling fluid pump pressure at the minimum necessary to maintain good circulation and to keep the borehole clear of cutting. 15.2.2 In the event a reduction in circulation is observed, and at the discretion of the on-site drill technician, adjustments to drilling fluid properties (e.g., density, viscosity), rate of drill head advance, and reaming diameter should be considered before pump pressure is increased. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 39 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 15.2.3 If mud circulation is lost, the HDD Construction Contractor must complete a frac-out walk, and attempt to seal the zone in question with loss circulation material. If loss circulation material (LCM) does not allow for circulation to be restored, then additional attempts to restore circulation shall be made. If these methods were not already outlined in the Contractor’s execution plan, they must be reviewed by the Company prior to implementation. 15.2.4 The HDD Construction Contractor shall not proceed with drilling without restoring full circulation. 15.3 Safe Drilling Practices 15.3.1 The HDD Construction Contractor shall maintain operations within those specified in the HDD design drawings provided by the Company and outlined in the HDD Construction Contractor’s execution plan. 15.4 Ground Surface Monitoring 15.4.1 Monitoring shall be in accordance with this Standard, crossing agreements, regulatory agencies having jurisdiction, and site-specific environmental plans. 15.4.2 The HDD Construction Contractor shall monitor the ground surface, facilities and other sensitive areas within 150 m (490 ft) on either side of the drill path for drilling fluid migration. 15.4.3 The HDD Construction Contractor shall perform an inspection every four (4) hours (as site conditions permit) or more often if fluid migration is detected. 15.4.4 The HDD Construction Contractor shall perform continuous surface inspection until the drill is completed or full drilling fluid returns are restored. 15.5 Water Quality Monitoring 15.5.1 The HDD Construction Contractor shall provide personnel to monitor for observable fluid migration conditions in water bodies as required by the Company during drilling activities. 15.5.2 If drilling fluid migration is suspected (based on fluid returns and tank volume), the HDD Construction Contractor shall perform continuous water quality monitoring. Monitoring shall continue until the location of the suspected drilling fluid migration is found, the drill is completed, or measures to remedy the drilling fluid migration are successful. 15.5.3 Company environmental inspections should occur at least once every four (4) hours while pumping, and for 24 hours after pumping is terminated, or as indicated in project-specific EPP. Monitoring on ice or in water or wetlands shall be discontinued when conditions render the activity unsafe. 15.6 Reporting of Drilling Fluid Migration 15.6.1 The HDD Construction Contractor shall submit a daily report of the quantity of drilling fluid released, location and clean up activity. 15.6.2 The daily drilling fluid migration report shall include: • time and quantity of drilling fluid migration Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 40 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published • circulating pressure • fluid mixture composition • fluid viscosity • location and depth of the drill head • rate of drill advance • location of the release • cleanup activities • photographs of release and cleanup Publish Date: 2019-Nov-01 15.7 Notification and Response 15.7.1 Upon first indication of a potential drilling fluid migration, the HDD Construction Contractor shall stop the drilling fluid pump, continue rotation of the drill string, and pullback the drill head in an attempt to stop or substantially reduce the rate of fluid loss. 15.7.2 Upon first indication of a suspected drilling fluid migration, the HDD Construction Contractor shall immediately notify the Company. 15.7.3 Once a drilling fluid migration is visually confirmed, the Company shall coordinate the notification to the appropriate regulatory agencies and the landowners. 15.8 Surface Containment and Removal 15.8.1 The HDD Construction Contractor shall determine the appropriate containment equipment and materials to use. 15.8.2 The Company shall obtain the landowner’s permission prior to accessing any sites for fluid containment and removal operations, except in an emergency where inaction would pose an imminent threat to human health, sensitive environment or property. 15.9 In-Stream Containment and Removal 15.9.1 Prior to commencing any HDD, the HDD Construction Contractor shall ensure appropriate equipment is available at each HDD location to contain and recover drilling fluid flow from the release sites. 15.9.2 No containment or recovery activities shall be allowed in water bodies or wetlands without regulatory agency approval. If this cannot be achieved, the HDD drill shall be suspended until appropriate approvals are obtained. 16 CONSTRUCTION EXECUTION – PILOT HOLE DRILLING, TRACKING, AND SURVEYING 16.1 General 16.1.1 The HDD Construction Contractor shall drill the pilot hole along the path shown on the HDD design drawings. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 41 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 16.1.2 The HDD Construction Contractor shall perform a profile survey of the proposed crossing location to verify the Company-supplied HDD design drawings. 16.1.3 The survey shall include the location of the drill entry point, the angle of the hole to be drilled and the drill exit location in accordance with the HDD design drawings. If the HDD Construction Contractor detects any discrepancies, it shall notify the Company. 16.1.4 The HDD Construction Contractor shall monitor the drill string position using downhole survey instruments and verify the position with surface location equipment (e.g., ParaTrack, TruTracker, Gyro or equivalent). 16.1.5 The HDD Construction Contractor should provide the Company with the as-built surface coil position with an accuracy of +/- 0.15 m (6 in.) and submit the coordinates. 16.1.6 The HDD Construction Contractor shall compute the position in the X, Y and Z-axis relative to ground surface from downhole survey data a minimum of once per length of each drill pipe. 16.1.7 The HDD Construction Contractor shall use surface tracking equipment wherever possible to supplement the downhole survey tools. The surface tracking equipment should be installed all along the crossing, where possible, or for at least 150 m (490 ft) on both entry and exit sides. 16.1.8 Upon exit of the pilot hole, the HDD Construction Contractor shall take the final survey at the ground elevation. 16.1.9 In the case of a pilot hole intersect drill, the HDD Construction Contractor shall survey the entire drilled hole after the intersect from one side of the crossing to the other in a continuous run using only one steering tool to calculate the final pilot hole survey and drilled radii. 16.1.10 The HDD Construction Contractor shall complete a four-point roll test of the steering tool, and calibrate the annular pressure monitoring tool in accordance with manufacturer’s recommendation on surface, prior to installing the steering tool into the bottom hole assembly. 16.1.11 Calibration data shall be provided to Company prior to start of pilot hole drilling. 16.1.12 Should the steering tool require replacement during the drill, the four-point roll test and calibration shall be performed in accordance with 16.1.9 and 16.1.11. 16.2 Entry/Exit Angle, Horizontal Alignment and Depth 16.2.1 Pilot hole drills shall follow the path shown on the HDD design drawings within the tolerances shown in Table 16-1. Table 16-1: Tolerance for the Pilot Hole Drill Item Tolerance Pilot hole entry angle Increase angle up to 1° (steeper), but no decrease in angle allowed. Pilot hole entry location As staked by Company. No changes without Company approval. Pilot hole exit angle Decrease angle up to 1° (flatter), increase angle up to 1° (steeper) in exit angle allowed. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 42 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 Item Tolerance Pilot hole exit location Up to 5 m (16 ft) longer or 3 m (10 ft) shorter than exit stake. Pilot hole depth Up to 2 m (7 ft) in pipe design depth (shallower) allowed. Up to 3 m (10 ft) increase in pipe design depth (deeper) allowed. Under no circumstances shall the HDD Construction Contractor drill within the no-drill zone established for the specific crossing as shown on the HDD design drawings. Pilot hole alignment Between 2 m left and 2 m (7 ft) right of the Company survey centerline but not within one 2 m (7 ft) of the right-of-way boundary. 16.2.2 The Company shall locate and stake preliminary entry and exit points on the ground as shown on HDD design drawings using traditional survey methods. 16.2.3 If site grading is required at entry or exit points, the Company shall locate and stake the coordinates for entry or exit points upon completing of grading. 16.2.4 The HDD Construction Contractor shall measure the three-dimensional coordinates of two known reference points in the Contractor’s local coordinate system established for tracking the crossing. 16.2.5 One reference point shall be established at each HDD entry and exit staging areas in a location that is protected from movement of equipment and the influence of drilling operations. 16.2.6 The reference points shall be chosen by the Company or a surveyor designated by the Company. 16.3 Pilot Hole Drill Radius 16.3.1 The minimum allowable single joint steering radius shall be at least equal to or greater than the minimum bending radius provided on the HDD design drawings. The specified minimum single joint steering radius refers to the resulting drilled bend radius from the combined effects of steering in both the vertical and horizontal planes. 16.3.2 Calculations of the minimum drilled single and three joint steering radii shall be completed by the HDD Construction Contractor in accordance with this Standard. 16.3.3 Where a compound curve (i.e., where steering simultaneously occurs in the vertical and horizontal planes) is drilled, the minimum drilled steering radius of each component shall be used to calculate the combined compound curve drill radius. 16.3.4 The pilot hole shall be drilled at a radius in accordance with the HDD design drawings, for consecutive one and three-joint steering radii (moving average). 16.3.5 For steering solely within either the vertical or horizontal plane, the HDD Construction Contractor shall calculate the drilled steering radius over all consecutive one (1) and three (3) joint segments using the following: RV or RH = (Ldrilled/Aavg) * (360 / 2π) Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 43 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Where: Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 RV = average drilled radius over Ldrilled in the vertical plane in meters RH = average drilled radius over Ldrilled in the horizontal plane in meters Ldrilled = length drilled over one (1) or three (3) joints of drill pipe (either 10 m (30 ft) or 30 m (100 ft) approximately) Aavg = total change in inclination (for RV) or azimuth (for RH) over Ldrilled The total change in angle (Aavg) shall be computed using the Minimum Curvature Method. 16.3.6 For steering along a compound curve, where steering occurs simultaneously (concurrently) within the vertical and horizontal planes, the HDD Construction Contractor shall calculate the combined compound curve drilled radius over any one and three joint segments using the following formula: Where: π π ππ2 π π π»π»2 π π πΆπΆ = οΏ½ 2 π π ππ + π π π»π»2 RC = combined compound curve drilled radius over Ldrilled RV = drilled vertical radius over Ldrilled as calculated above RH = drilled horizontal radius over Ldrilled as calculated above 16.3.7 For compound curve pilot bores, the minimum allowable steering radius refers to the resulting drilled compound curve drilled radius from steering inputs from each plane concurrently. The resulting compound curve drilled radius shall be equal to or higher than the minimum allowable steering radii stated on the HDD design drawings. 16.3.8 Under no circumstances shall the stated minimum allowable steering radius be used to compare individual vertical and/or horizontal drilled radii separately where a compound curve is drilled. 16.4 Pilot Hole Drill Corrections 16.4.1 The HDD Construction Contractor shall notify the Company of any pilot hole failing to meet the HDD design drawings. 16.4.2 The HDD Construction Contractor shall re-drill or pullback and correct the pilot hole and provide documentation confirming the pilot hole is in accordance with HDD design drawings. 17 CONSTRUCTION EXECUTION – HOLE REAMING 17.1 General 17.1.1 HDD installation of NPS 36 and above should use one (1) rig at entry location and one (1) rig at exit location to aid with reaming and drilling fluid handling. 17.1.2 The HDD Construction Contractor shall determine the type and size of reamers as well as the number of passes according to the formation being drilled and the limitations of the HDD Construction Contractor’s equipment. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 44 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 17.1.3 The HDD Construction Contractor shall incorporate a stabilizer into the bottom hole reaming assembly for all reaming passes equal to or greater than 1,067 mm (42 in.). The HDD Contractor’s execution plan shall include all bottom hole assembly details. 17.1.4 The HDD Construction Contractor should “trip” back to surface and clean the ream hole as follows: • every 30 joints • when drilling fluid returns slow down from full return 17.1.5 Pushing on drill pipe shall not be allowed during reaming. The HDD Construction Contractor shall minimize cyclic stresses induced in the drill string throughout the course of drilling to minimize overstressing of drill pipe and fatigue. 17.1.6 The minimum final ream size shall be 1.5 times the product pipe outside diameter for pipelines equal to or less than NPS 20 and 300 mm (12 in.) larger than the product pipe outside diameter for pipelines greater than NPS 20. 17.1.7 The HDD Construction Contractor shall not increase the reamed diameter by more than 300 mm (12 in.) increments for reamers greater than or equal to 762 mm (30 in.) or as approved by the Company. 17.1.8 Upon the completion of the last reaming pass, the HDD Construction Contractor shall make at least one (1) cleaning (wiper) pass to remove excess cuttings from the previously reamed hole to ensure a clean reamed hole. 17.1.9 The HDD Construction Contractor shall keep the reamed hole clean and in good condition for pipe installation until the pullback operation starts. 17.1.10 The HDD Construction Contractor shall meet with the Company and review reaming and cleaning pass data before product pipe pullback begins. 18 CONSTRUCTION EXECUTION – PIPE FABRICATION AND TESTING PRIOR TO PULLBACK 18.1 Welding 18.1.1 The HDD or Mainline Construction Contractor shall conduct all welding and nondestructive testing in accordance with the Company specifications: • TES-WELD-PL Welding of Pipelines and Tie-Ins Specification (CDN) (Item ID: 003670960) • TES-WL-APIWL-GL Welding of Pipelines and Facilities Specification (US-MEX) (Item ID: 1001828218) • TES-NDT-RT Radiographic Examination of Welds Specification (CDN) (Item ID: 003671368) • TES-RT-API Radiographic Examination of Welds Specification (US-MEX) (Item ID: 004472888) • TES-NDT-UT Ultrasonic Examination of Girth Welds Specification (CDN) (Item ID: 1001829033) Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 45 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 • Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 TES-UT-API Ultrasonic Examination of Girth Welds Specification (US-MEX) (Item ID: 1001828660) 18.2 Pipe and Coatings 18.2.1 External coating shall be inspected in accordance with the Company specification TES-CO-EPU-GL Field-Applied External Liquid Coating Systems for Steel Pipe Specification (CAN-US-MEX) (Item ID: 003671710) with an approved electrical holiday detector during fabrication, after field joints are coated, and immediately prior to pipe being pulled into the drill hole. 18.2.2 The HDD Construction Contractor or Mainline Construction Contractor shall comply with Company specification TES-CO-EPU-GL Field-Applied External Liquid Coating Systems for Steel Pipe Specification (CAN-US-MEX) (Item ID: 003671710) for surface preparation, applying field joint coating, and all pipe coating repairs. 18.2.3 The HDD Construction Contractor or Mainline Construction Contractor shall coat all girth welds in accordance with the Company specification TES-CO-EPU-GL FieldApplied External Liquid Coating Systems for Steel Pipe Specification (CAN-US-MEX) (Item ID: 003671710) after completing the pre-testing of the fabricated pipe. 18.3 Pre-Pullback Hydrostatic Testing 18.3.1 The HDD or Mainline Construction Contractor shall conduct a one-hour pre-test on all pipe segments used for the pullback sections. Refer to TES-PRES Pipeline and Facility Piping Pressure Testing Specification (CDN) (Item ID: 1001810638) and TEPPRES Pipeline and Facility Piping Pressure Testing Procedure (Item ID: 1001810622) for Canadian pre-testing requirements and TEN-ME-PRES-GL Pressure Testing Standard (US-MEX) (Item ID: 1003107276), TES-ME-PRES-GL Pressure Testing Specification (Item ID: 1003107294) and TEP-ME-PRES-GL Pressure Testing Procedure (US-MEX) (Item ID: 1003107361) for the U.S. and Mexico pre-testing requirements. 18.3.2 The water source and disposal location for the hydrostatic test shall be at Companyapproved locations. 18.3.3 Pipe may be hydrotested on skids or rollers, provided the HDD or Mainline Construction Contractor performs the test in accordance with the following requirements: 18.3.3.1 Girth welds shall not be coated prior to hydrostatic pretesting. 18.3.3.2 The test medium shall be water. 18.3.3.3 The minimum and maximum test pressures shall be as shown on the HDD design drawings. 18.3.3.4 The maximum support spacing shall be in accordance with criteria specified in TESME-STRPI-GL Pipeline Stress Analysis Specification (CAN) (Item ID: 1005882376), TES-ME-STRPA-GL Pipe Stress Engineering Analysis and Design of Pipeline Assemblies Specification (CAN-US-MEX) (Item ID: 007808806) and the references listed in section 23, as applicable. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 46 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 18.3.3.5 Each support shall have a weight capacity sufficient to support the water-filled pipe with an appropriate safety factor. 18.3.3.6 Supports shall be arranged so they are loaded approximately equally. 18.3.3.7 Supports located in low areas shall be raised to keep the drill section as straight as possible. 18.3.3.8 Supports shall closely conform to the shape of the pipe (e.g., rollers, chocks, notched out timber). 18.3.4 The Company shall take samples during fill and dewatering operations. 18.3.5 The HDD or Mainline Construction Contractor Construction Contractor may install pull heads and associated equipment after dewatering and prior to pressuring with air. 18.3.6 If the prefabricated pipe is ready more than six (6) weeks prior to pullback, the HDD or Mainline Construction Contractor should pressure the pullback section with 350 kPa (50 psig) of air or nitrogen and monitor this pressure daily until the section is ready for pullback. 19 CONSTRUCTION EXECUTION – PIPE PULLBACK 19.1 General 19.1.1 The HDD Construction Contractor should begin pullback operation during daylight hours. 19.1.2 During pullback the pipe shall be supported on rollers. All lifting and support equipment shall be capable of withstanding the maximum exerted forces with a safety factor of 2.0. 19.1.3 All rollers shall be in good mechanical and physical condition and shall be located in accordance with HDD design drawings and lifting and pullback plan sufficient to support the pipe. The Company shall have the right to stop work if insufficient or inadequate rollers are used. 19.1.4 Maximum pullback load on the product pipe shall be in accordance with the HDD design drawings. 19.1.5 Pulling force exerted on the product pipe during pullback shall not exceed the maximum working strength of the weakest pulling assembly component and drill pipe. 19.1.6 During pipe pullback, the HDD Construction Contractor shall circulate drilling fluid at sufficient rate to remove excess cuttings from the drilled hole. The HDD Construction Contractor shall have sufficient equipment and storage on-site to manage excess fluid displaced by the pullback section. 19.1.7 The HDD Construction Contractor shall monitor and record the minimum, maximum and average pullback forces for each joint of drill pipe pulled during the pullback operation. 19.1.8 Recorded forces shall be compared to the expected pullback forces to monitor the reamed hole condition and effectiveness of the buoyancy control (if buoyancy control has been implemented). Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 47 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 19.1.9 The HDD Construction Contractor shall use a pullback swivel assembly to connect the pull section to the drill string to minimize torsional stress imposed on the pull section. 19.1.10 The pipe pulling swivel assembly and pipe pulling head shall be rated at a working load equivalent to 1.5 times the rig pullback capacity by the manufacturer or a professional engineer. A copy of this certification and inspection reports (e.g., visual, magnetic particle, radiographic) shall be provided to the Company prior to project start. 19.1.11 The HDD Construction Contractor shall install the pipeline in one continuous string with no intermediate welds, unless otherwise indicated in the HDD design drawings. 19.1.12 The HDD Construction Contractor shall begin the pullback operation immediately (within 8 hours) after the final cleaning pass has been completed. Once the Contractor begins pullback operations, installation shall not cease until pullback operations are completed. 19.1.13 The HDD Construction Contractor shall not use any hammering or ramming device to aid in the installation of the product pipe. 19.1.14 The HDD Construction Contractor shall modify buoyancy as required and/or when conditions dictate. A buoyancy control plan shall be part of the HDD Construction Contractor’s site-specific HDD Execution Plan. 19.1.15 During the pullback operation, the HDD Construction Contractor shall monitor roller operation and shall use side booms or cranes if required to assist movement of the pipe. Situations that cause coating damage shall be corrected immediately. 19.1.16 Holiday detection shall be performed continuously during pullback operation. 19.1.17 The HDD or Mainline Construction Contractor shall repair coating damage in accordance with Company specification TES-CO-EPU-GL Field-Applied External Liquid Coating Systems for Steel Pipe Specification (CAN-US-MEX) (Item ID: 003671710) before pullback operations resume. 19.1.18 If the pipe becomes lodged in the drilled hole during pullback and cannot be recovered, the HDD Construction Contractor shall seal the pipe and existing drilled hole, as specified by the Company. This shall include grouting or cementing of the drilled hole and pipe as specified by the Company. 19.2 Acceptance of Installation 19.2.1 The HDD Construction Contractor shall pull the product pipe out of the drilled hole at the pipe exit side at least 6 m (20 ft) to allow for visual inspection of potential coating or pipe damage. 19.2.2 If damage is evident to the coating or pipe, the HDD Construction Contractor may be required to pull additional length of pipe as required by the Company to adequately assess the conditions and determine the acceptance. 19.2.3 The pipe coating shall be inspected and be in accordance with the applicable Company specifications: Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 48 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 • TES-COAT-EP External Polyethylene Coating for Steel Pipe (CDN-US-MEX) (Item ID: 003678529) • TES-COAT-HPPC High Performance Powder Coating (CDN-US-MEX) (Item ID: 003845380) • TES-CO-FBE-GL External Fusion Bond Epoxy for Steel Pipe Specification (CAN-US-MEX) (Item ID: 003670892) • TES-CO-EPU-GL Field-Applied External Liquid Coating Systems for Steel Pipe Specification (CAN-US-MEX) (Item ID: 003671710) • TEN-CP-SURVY-GL Corrosion Prevention Survey Standard (CAN-US-MEX) (Item ID: 1003456006) 19.2.4 The HDD Construction Contractor shall run a gauging pig, or equivalent tool, to ensure that the pipe has no buckles, wrinkles, gouges, dents or internal restrictions. Pipe dents and ovality shall meet the criteria as mentioned in TES-CT-GEN-L Pipeline Construction Specification (US) (Item ID: 005408266), TES-CT-GEN-GL Pipeline Construction Specification (CAN) (Item ID: 003745282), TES-CT-GEN-G Pipeline Construction Specification (US-MEX) (Item ID: 1013154643) 19.2.5 The Mainline Construction Contractor shall conduct a hydrostatic test on the HDD installed pipe together with the mainline pipe. Refer to TES-PRES Pipeline and Facility Piping Pressure Testing Specification (CDN) (Item ID: 1001810638) and TEPPRES Pipeline and Facility Piping Pressure Testing Procedure (Item ID: 1001810622) for Canadian testing requirements and TEN-ME-PRES-GL Pressure Testing Standard (US-MEX) (Item ID: 1003107276), TES-ME-PRES-GL Pressure Testing Specification (Item ID: 1003107294) and TEP-ME-PRES-GL Pressure Testing Procedure (Item ID: 1003107361) for the U.S. and Mexico testing requirements. 19.2.6 The Company shall review the drill profile survey information, hydrostatic test data, gauging pig run data, internal pipeline inspection report, coating tests and any material inspection data to determine the acceptability of installed HDD crossing. 19.3 Preparation of Final Tie-In 19.3.1 The HDD Construction Contractor should nitrogen purge and 100 kPa (15 psig) pack/fill the pipeline if the HDD crossing is installed in advance (six (6) weeks or more) of the tie-ins to the pipeline to eliminate the possibility of internal corrosion. 19.3.2 The HDD crossing pipe ends shall be installed at a depth and angle suitable for final tie-in to the proposed and/or existing pipeline. Final tie-in piping shall have appropriate support (as applicable) during construction and prior to backfill. 19.3.3 The HDD or Mainline Construction Contractor shall install weld caps or seal welded plates with vents on the crossing pipe ends if tie-ins to the pipeline are delayed. Buried pipe ends shall be marked for future tie-in by the HDD or Mainline Construction Contractor. 19.4 Final Reporting 19.4.1 The HDD Construction Contractor shall provide the Company with the complete directional survey report (e.g., ParaTrack, TruTracker or equivalent) made during the Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 49 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 drilling operation and an as-built plan and profile drawing showing the X, Y, and Z coordinates of the pipeline’s final location. 19.4.2 The maximum spacing between coordinate points shall be every joint of drill pipe (approximately 10 m [30 ft]). 19.4.3 The HDD Construction Contractor shall furnish the as-built drawing within five (5) days after the pilot hole is complete. 20 CONSTRUCTION EXECUTION – SITE CLEAN UP AND RESTORATION 20.1 Grouting and Sealing of Abandoned Holes 20.1.1 The HDD or Mainline Construction Contractor shall meet all regulatory requirements, and project- specific EPP requirements for any abandoned hole drilled or abandoned pipe. 20.1.2 The HDD or Mainline Construction Contractor shall fill and seal the abandoned hole drilled (excluding the top 2 m [7 ft]) with cemented grout. 20.1.3 The HDD Construction Contractor shall place compacted soil in the top 2 m (7 ft) of the hole. The Contractor shall comply with direction provided by the Company if the Company requires more extensive grouting up to and including grouting of entire abandoned drilled hole to prevent ground subsidence, frac-out of adjacent HDD paths. 20.1.4 The HDD Construction Contractor shall submit a grouting plan (including grouting mix) for Company review. 20.2 Site Restoration 20.2.1 The HDD or Mainline Construction Contractor shall perform final clean up and restore all work areas to the satisfaction of the Company. 21 VARIANCES Any deviation shall follow the Company Controlled Document Library Variance Procedure (Cdn-US-Mex) (EDMS: 007728702). Contractors shall contact the Company for variance approval. 22 ROLES AND RESPONSIBILITIES Table 22-1 below outlines the roles and responsibilities required for the use of this Standard. Table 22-1: Roles and Responsibilities Role Responsibilities Company TC Energy entity for whom work, services and/or materials are being provided HDD Construction Contractor Any person, firm, or corporation contracting with the Company to perform the HDD construction work as set out in the Agreement. Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 50 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 23 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 Role Responsibilities HDD Designer A qualified individual who prepares the design and is responsible for preparing engineering designs, bills of materials, specifications, reports and other engineering documents. Responsible for reviewing and accepting responsibility for use of applicable industry codes, standards and regulations, Company Design Standards and project specific requirements. Mainline/ Pipeline Construction Contractor Any person, firm, or corporation contracting with the Company to perform the construction work other than HDD as set out in the Agreement. Inspector Any person designated by the Contractor, Company, or any authority to perform inspection tasks. Third-Party Inspector An agent independent of the Contractor. The inspection shall be performed by a person with sufficient expertise, knowledge and training to competently perform the inspection. REFERENCES This document relies on a number of references to regulation, industry codes and standards, general industry guidance as well as internal references. These documents are listed in Table 23-1, Table 23-2 and Table 23-3. Use the latest document revision, unless otherwise approved by the Company. Table 23-1: Regulatory References Organization/Document No. Title 49 CFR 192 Transportation of Natural and Other Gas by Pipeline 49 CFR 195 Transportation of Hazardous Liquids by Pipeline NOM-007-ASEA-2016 Transporte de gas natural, etano y gas asociado al carbón mineral por medio de ductos (Transmission of Natural Gas, Ethane and Coal Gas Through Pipelines) SOR/99-294 National Energy Board Onshore Pipeline Regulations (NEB OPR) Fisheries and Oceans (DFO) Navigable Waters Protection Act (NWPA) Pipeline Hazardous Material Safety Administration (PMHSA) Water Quality Act Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 51 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 Table 23-2: External Industry References Organization/Document No. Title 2A-WSD API Recommended Practice API 1102 Steel Pipelines Crossing Railroads and Highways API 5D Standard for Drill Pipe API 5L Standard for Line Pipe API RP 7G Recommended Practice for Inspection and Classification of Used Drill Stem Elements API RP 13B-1 Recommended Practice for Field Testing Water-based Drilling Fluids AREMA Part 5, Pipeline ASCE Manual of Practice No. 108 Pipeline Design for Installation by Horizontal Directional Drilling ASME B31.4 Pipeline Transportation Systems for Liquids and Slurries ASME B31.8 Gas Transmission and Distribution Piping Systems ASTM A 139 Standard Specification for Electric-Fusion (Arc)-Welded Steel Pipe (NPS 4 and Over) ASTM D 422 Standard Test Method for Particle-Size Analysis of Soils ASTM D 1586 Standard Test Method for Penetration Test and Split Barrel Sampling of Soils ASTM D 1587 Standard Practice for Thin-Walled Tube Sampling of Soils for Geotechnical Purposes ASTM D 2113 Standard Practice for Rock Core and Sampling of Rock for Site Investigation ASTM D 2166 Standard Test Method for Unconfined Compressive Strength of Cohesive Soil ASTM D 2487 Standard Practice for Classification of Soils for Engineering Purposes (Modified Unified Soil Classification System) Canadian Association of Petroleum Producers (CAPP) Publication 2004-0022 Planning Horizontal Directional Drilling for Pipeline Construction CSA Z245.1 Steel Pipe CSA Z662 Oil and Gas Pipeline Systems Construction Productivity Guidelines for Installation of Utilities Beneath Corps of Engineers Levees Advancement Research Program Using Horizontal Directional Drilling. C.A. Latorre, L.D. Wakeley, and P.J. Technical Report ERDC/GSL TR- Conroy. U.S. Army Corps of Engineers, Waterways Experiment Station. 02-09 Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 52 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 Organization/Document No. Title NACE Standard Test Method of Protective Coating Electrical Conductance of Underground Pipelines PRCI, PR-227-144507 Installation of Pipelines Using Horizontal Directional Drilling – An Engineering Design Guide Transport Canada, TC E-10 Standard Respecting Pipeline Crossing Under Railways Table 23-3: Internal References Organization/Document No. Title Item ID: 007728702 Controlled Document Library Variance Procedure (CDN-US-MEX) Item ID: 1003456006 TEN-CP-SURVY-GL Corrosion Prevention Survey Standard (CAN-US-MEX) Item ID: 1003107276 TEN-ME-PRES-GL Pressure Testing Standard (US-MEX) Item ID: 1009372841 TEN-ME-PWT-GL Pipe Wall Thickness Design Standard (CAN-US-MEX) Item ID: 1001810622 TEP-PRES Pipeline and Facility Piping Pressure Testing Procedure (CDN) Item ID: 1003107361 TEP-ME-PRES-GL Pressure Testing Procedure (US-MEX) Item ID: 1013154643 TES-CT-GEN-G Pipeline Construction Specification (US-MEX) Item ID: 003745282 TES-CT-GEN-GL Pipeline Construction Specification (CAN) Item ID: 005408266 TES-CT-GEN-L Pipeline Construction Specificatin (US) Item ID: 003678529 TES-COAT-EP External Polyethylene Coating for Steel Pipe (CDN-US-MEX) Item ID: 003671710 TES-CO-EPU-GL Field-Applied External Liquid Coatings for Steel Pipeline Systems Specification (CAN-US-MEX) Item ID: 003670892 TES-CO-FBE-GL External Fusion Bond Epoxy for Steel Pipe Specification (CAN-US-MEX) Item ID: 003845380 TES-COAT-HPPC High Performance Powder Coating (CDN-US-MEX) Item ID: 1003041252 TES-DR-2DSTD-GLE 2D Drawings Specification (CAN-US-MEX) Item ID: 1001810598 TEN-PRES Pressure Testing Standard (CDN) Item ID: 1003107294 TES-ME-PRES-GL Pressure Testing Specification (US-MEX) Item ID: 007808806 TES-ME-STRPA-GL Pipe Stress Engineering Analysis and Design of Pipeline Assemblies Specification (CAN-US-MEX) Item ID: 1005882376 TES-ME-STRPI-GL Pipeline Stress Analysis Specification (CAN) Item ID: 003671368 TES-NDT-RT Radiographic Examination of Welds Specification (CDN) Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 53 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 24 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 Organization/Document No. Title Item ID: 1001829033 TES-NDT-UT Ultrasonic Examination of Girth Welds Specification (CDN) Item ID: 1001810638 TES-PRES Pipeline and Facility Piping Pressure Testing Specification (CDN) Item ID: 004472888 TES-RT-API Radiographic Examination of Welds Specification (US-MEX) Item ID: 1001828660 TES-UT-API Ultrasonic Examination of Girth Welds Specification (US-MEX) Item ID: 003670960 TES-WELD-PL Welding of Pipelines and Tie-Ins Specification (CDN) Item ID: 1001828218 TES-WL-APIWL-GL Welding of Pipelines and Facilities Specification (USMEX) DOCUMENT HISTORY Rev. 01 Description Effective Date Revision 2019-Nov-01 Rationale Statement Authenticating Engineer This document was developed/revised in order to address the following requirements: • align with new Company template • reduce ambiguity • removal of scope of work requirements • updated to align with CSA Z662 latest edition • updated to include lessons learned from completed projects • updated to include all stakeholder comments Dawood Habib Impact Assessment Summary Document Owner There will be no cost impact based on changes made to the HDD document. The document language has been improved and simplified to avoid confusion and duplication, Drivers for this update are as follows; 1)TES-ME-HDD-GL will be updated as an standard, as per definition provided by Technical Center. 2) This document has been updated as per its regular review cycle, its include lessons learnt from the past projects, comments from the reviewer. 3) Based on latest CSA Z662 there will be some wording change in the requirements but overall there will be no cost impact. 4) SOW and contractual terms removed from the document Engineering Standard Governace Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 54 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 Rev. 00 Description Effective Date New document 2017-Mar-20 Rationale Statement Authenticating Engineer This document was developed/revised in order to address the following requirements: • 25 Combine HDD design and construction requirements into one specification. Dawood Habib Impact Assessment Summary Document Owner N/A Dawood Habib DESCRIPTION OF CHANGE Section Description of Change Regulatory 8.2 Included reference to Mexican regulations Industry Standards Throughout Updated to include latest CSA Z662 requirements General 7.1 Updated to clarify HDD design drawing requirements 8.3 Updated to clarify steering tolerance requirements 8.12 Updated to clarify feasibility report requirements 11.3 Added drill pipe inspection plan requirements Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 55 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 26 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 APPROVALS APPROVALS Document Contact Dawood Habib, P. Eng. Pipeline Engineer Pipeline Engineering Discipline Checker Mustafa Yulek, P. Eng. Geotechnical Engineer Pipeline Engineering Discipline Checker Jarett McInenly, C. Tech. SME Trenchless Pipeline Engineering Document Owner Manager Robert Phernambucq, P.Eng. Manager Engineering Standards Governance Dawood Habib, P.Eng. Pipeline Engineer Gas Projects Pipeline Engineering Responsible Engineer Signature/Date APEGA Permit to Practice P7100 Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 56 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 APPENDIX A Status: Published Publish Date: 2019-Nov-01 REQUIRED DOCUMENT LIST Phase of Project Design Pre-Construction Construction Driver: Regulatory Section in Standard Requirement 2.1 Geotechnical Field Execution Plan 2.4 Geotechnical Data Report 5.2 HDD Feasibility Report 7.14 HDD Risk Register 8.2 Environmental Plan 8.3 Safety Plan 8.4 Workspace and Access Requirement Drawing 8.5 Drilling Schedule 9 Site Specific HDD Execution Plan 9.2 Preliminary Lifting/Pullback Plan 9.3 Drill Rig Anchoring Plan 9.4 Site-Specific Contingency Plan 9.5 Engineering Drilling Fluid Management and Composition Plan 9.6 Drilling Equipment List 9.7 Site-Specific Disposal Plan 11.7 Drilling Status Report 13.2 Drilling Fluid Report 14.2 Disposal Report 15.4 Ground Surface Monitoring Report 15.5 Water Quality Report 15.6 Drilling Fluid Migration and Release Report (if required) 19.4 Final Report Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 57 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 APPENDIX B Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 SAMPLE DRAWINGS Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 58 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 59 of 60 TC Energy Engineering Standard TEN-ME-HDD-GL HDD Design and Construction Standard (CAN-US-MEX) Item ID: 1003103090 Rev.: 01 Driver: Regulatory Status: Published Publish Date: 2019-Nov-01 Next Review Date: 2023-Nov-01 FOIA and CEII CONFIDENTIAL TREATMENT REQUESTED Approval Date: 2019-Oct-24 UNCONTROLLED IF PRINTED – LATEST CONTROLLED COPY IN FILENET P8 Page 60 of 60