COP 30.104 Change Control Revision No: Effective Date and Signature: I Purpose New See Master Document list for effective date of this procedure. (Date of final approver’s electronic signature.) A. Description This procedure describes the AECOM process by which changes to an authorized Performance Measurement Baseline (PMB) are processed for contract work that uses an Earned Value (EV) management methodology. It establishes the methodology to initiate the PMB change control process, track the Program Change Notice (PCN) through approval by the Change Control Board (CCB), initiation of the Baseline Change Proposal (BCP) process per the Planning and Budgeting procedure, COP 30.101 Planning and Budgeting (Level 4) (Reference A), and incorporation of changes into the performance baseline. The purposes of this procedure are to: 1. Incorporate authorized changes in a timely manner, recording the effects of such changes in budgets and schedules. In the directed effort prior to negotiation of a change, base such revisions on the amount estimated and budgeted to the program organizations. 2. Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal re-planning in the detail needed by management for effective control. 3. Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs, EV, or budgets. Adjustments should be made only for correction of errors, routine accounting adjustments, effects of customer or management directed changes, or to improve the baseline integrity and accuracy of performance measurement data. 4. Prevent revisions to the program budget except for authorized changes. 5. Document changes to the performance measurement baseline. II Scope A. Applicability This procedure applies to AECOM team members (program, program and site operations) and subcontractors supporting AECOM work. The processes detailed in this procedure are followed when initiating and processing changes to approved scope, schedule, and/or budgets for AECOM programs. B. Change Control Logic Attachment A – Change Control Logic is the logic for change control from change identification through approval to proceed with the work, AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 1 of 11 COP 30.104 Change Control change of the PMB, and the initiation of a formal BCP. III Responsibilities A. President, AGS Approves Corporate Operating Procedures (COPs). B. Chief Operating Officer, AGS Reviews and, as appropriate, recommends approval to the President. C. Quality Director, AGS Ensures procedures are in compliance with governing policies and the Quality Management System (QMS). D. Chief Financial Officer (CFO) 1. Provides guidance to other managers for compliance with this procedure. 2. Manages internal Finance Department implementation of this procedure. E. Program Manager (PM) 1. Establishing the Program Change Control Board (PCCB), delegating authority to the PCCB, and designating a Board chair. 2. Requesting the client to establish a CCB for each task order (TO) and designating the AECOM representative to that CCB. 3. Reviewing and concurring with the Control Account Managers (CAMs) and Program Controls on the merits and impact of a proposed change. 4. Approving the use of Management Reserve (MR) for in-scope changes. F. Business Manager (BM) Implements this procedure as part of the EVMS. G. Program Control Manager (PCM) 1. Ensuring the respective work planners and schedulers, in concert with CAMs and the Directors of Costing and Procurement, assess and develop: a. Technical scope and justification for a proposed change. b. Potential schedule and critical path impact of a proposed change. c. Estimated cost and budget impact of a proposed change. d. Subcontract requirements, including the affected subcontractor AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 2 of 11 COP 30.104 Change Control estimated costs and schedule impacts. 2. Assigning PCN Control Number, establishing and maintaining the PCN Log, and tracking the PCN status throughout the process. 3. Facilitating the change process to ensure timely and consistent processing from initiation through Program Manager concurrence, submission to and approval by the PCCB, and submission of the PCN Review Package to the CCB for approval. This includes completion and issuance of the PCN Impact Assessment to the PCCB for a go/no-go decision. 4. In concert with the CAM and the Program Manager, compiling the formal PCN Review Package and submitting it via the Directorate of Contracts for CCB review and approval. 5. Assisting the CAM in updating Control Account plans for PM approved in-scope changes not requiring the use of MR. H. Contracts Manager 1. Ensuring the PCN Review Package meets program and contractual requirements prior to submission to the CCB. 2. Submitting the PCN Review Package for CCB review and approval. 3. Facilitating the CCB approval process to ensure timely approval. I. Control Account Manager (CAM) 1. Assessing the scope, schedule, and cost impacts on the CA for PCCB approval, in concert with the Directors of Costing, Program Controls, Procurement, and the program team. 2. Compiling the PCN Review Package for CCB approval in concert with Program Controls and the Program Manager. 3. Assessing the use of MR for in-scope changes, in concert with Program Manager. J. Costing Manager Estimating the cost impact for the defined technical scope. K. The Procurement Manager Assessing the impact of the proposed change on a subcontractor’s schedule and cost. L. Financial Manager In concert with Program Controls, is responsible for establishing the necessary charge codes for affected CAs to capture cost prior to and/or after CCB approval and to ensure PCN costs are tracked separately. AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 3 of 11 COP 30.104 Change Control M. Subcontractors Provide detailed supporting schedules and estimated cost impact for the proposed PCN. IV Reason for Revision New Procedure V General A. Definitions 1. Baseline Change Proposal (BCP): A proposal requesting a contractual change to a program’s budget, schedule, and/or scope. It may contain a single or multiple approved PCN. Authorization and requirements for a BCP are specified in the associated Letter of Technical Directive for each approved PCN. 2. Change Control Board (CCB): The approving authority for PCN Review Packages. 3. Letter of Technical Direction (LOTD): The document issued by the client based on a CCB-approved PCN to authorize AECOM to perform the PCN-defined work, authorize a PMB change, and establish the BCP requirements. 4. Program Change Notice (PCN): A notice issued to initiate and receive approval for a PMB change. 5. Program Change Notice Log (PCN Log): A log monitoring PCN status from initiation through BCP approval. 6. Program Change Control Board (PCCB): An AECOM internal review board for a proposed PCN. The members of the PCCB review the merits of each proposed change. Note: It will be the responsibility of each program to control its own Program Change Notices and Program Change Notice Logs. VI Procedures and Instructions The Change Control Process consists of five steps: A. Step 1: Change Identification 1. This first step identifies a potential change that may affect a program’s authorized work scope, cost, and/or schedule. The key elements of this step are: 2. AECOM personnel, subcontractors, or client representatives can identify a potential change that impacts the scope, cost, and/or schedule by completing a PCN. At a minimum, the initiator provides the following: a. PCN title, as defined by the initiator. b. The date the PCN Form is initiated and the initiator’s name, AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 4 of 11 COP 30.104 Change Control organization, and contact information. c. The name of the individual initiating the PCN. d. The WBS elements and WBS dictionaries that would be affected by the proposed change. e. The type of change: 1) External Change—A change to T.O. or contract effort, cost, funding or schedule directed by the client. 2) Internal Change—A change to scope, cost, or schedule proposed by the Program Office, program team, or subcontractor. This change may or may not require the application of MR and may or may not require a change to the approved performance measurement baseline. f. The primary affected CA and respective CAM and all other known affected CAs and/or CAMs. If not known by the initiator, this information must be completed by the primary CAM as part of the impact assessment. g. A brief description of the proposed change that is adequate enough to define the scope and assess the potential impact. h. Justification for the proposed change or the impact on the program’s performance, cost, and/or schedule if the change is not accepted. i. Note that retroactive changes to the baseline are approved only to correct errors. 2. Program Controls then assigns a PCN Control Number and initiates status tracking in the PCN Log. The format of the PCN No. is xxxx-ppp where: a. xxxx is the WBS code as specified in the WBS Dictionary that the PCN affects. b. ppp is a sequential number starting at 001 and continuing through 999, based on the TO. It is the ppp number that is appended to the respective CA that identifies a subdivision of the affected CA and where ppp = 000 is reserved for original CA scope item. B. Step 2: Change Assessment 1. The responsible CAM, in concert with other affected CAMs, Costing and Program Control’s planners and schedulers, appends to the PCN Initiation Notice a PCN impact assessment of the proposed change. This assessment is a narrative description that describes: AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 5 of 11 COP 30.104 Change Control a. Draft PCN scope and/or justification by affected CA, including WBS and WBS dictionaries. b. Basis of Estimate (BOE) for cost and schedule impacts by affected CA. c. Cost estimate by the affected CA. d. Schedule impact and critical path analysis to determine if the change will have an impact on any program milestone or affect the work sequence. Affected scheduled activity should be identified and the impact estimated. 2. The responsible CAM reviews the PCN Impact Assessment with the Program Manager for concurrence to proceed to the PCCB. C. Step 3: Internal Review 1. The Program Manager, Program Controls Manager and the CAM will discuss the proposed PCN with the client. 2. Program Controls issues the PCN Impact Assessment to the PCCB for a go/no-go decision based on the impact assessment and the merits of the proposed change. This can occur concurrently or after receiving input from the client, as described below: a. Upon a no-go decision, Program Controls, in concert with the CAM, stops all work associated with processing the PCN. b. Upon a go decision, and based on the recommendations of the PCCB, the Program Manager, in concert with Contracts, determines if the PCN is in or out of scope: 1) If “out of scope,” the procedure in Paragraph VI.2.D. of this procedure is followed. 2) If “in scope” and MR is used to fund the work the impact, then the CAM, in concert with Program Controls, Costing and Program Manager/team, initiates the planning and budgeting process (Reference A) to revise the MR log and PMB budgets. 3) If “in scope” and the change affects an existing, defined CA planning package, summary-level planning package, or the allocation of undistributed budget, then the CAM, in concert with Program Controls, Costing and the Program Manager, initiates the planning and budgeting process to revise the appropriate Control Account Plan (CAP, PMB Logs, reports, and PMB budgets. c. PCN Review Package: The PCN Review Package compiles into a single package a potential change to scope, schedule, and AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 6 of 11 COP 30.104 Change Control cost. (See the Target Timeline in Attachment B.) The key actions are: 1) Program Controls, in concert with the Program Manager/ team and the associated CAM either identifies the CA impacted or creates a new CA if needed. 2) Program Controls, in concert with Financial Management, ensures that the appropriate charge codes are established in the accounting system. 3) Program Controls completes the PCN Review Package and submits it to the Director of Contracts. 4) The Contracts Manager confirms contract compliance, submits the PCN Review Package to the CCB, and facilitates the CCB approval process in concert with the Program Manager until the change is either approved or rejected. D. Step 4: External Review Approval 1. CCB review and approval of a PCN Review Package results in the issuance of a LOTD by the client. (See Target Timeline in Attachment B.) 2. After the CCB approval of a PCN Review Package, the client issues a LOTD that specifies: a. Authorization to proceed with the PCN scope of work as approved b. Authorization of a PMB change per the spending limits as approved based on the PCN Rough Order of Magnitude (ROM) c. Authorized schedule changes d. BCP requirements and instructions 3. Any discussion of an OTB must be coordinated carefully with the client and managed consistent with the definition found in VI.G. 4. If a PCN Review Package is not approved, the rejected PCN Review Package and all supporting data/information are recorded. The PMO will determine if a claim to the client is warranted for PCN preparation cost. E. Step 5: Implementation 1. Upon receiving the LOTD from the client, Program Controls updates the PMB per the Planning and Budgeting Procedure. (Note: Upon initial acceptance of the PMB by management, Program Controls personnel will complete the PMB Change Log up to the section where the first change will be entered. The log then AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 7 of 11 COP 30.104 Change Control becomes the basis for tracking the PCN process.) 2. The CAM updates the affected CAP per Reference A. 3. Reports of program performance are modified to reflect approved changes to the baseline. F. Records PCN Impact Assessments and/or PCN Review Package and related support documents are maintained by Program Controls. G. Reprogramming OTB/OTS 1. The primary purpose of reprogramming is to establish realistic budgets, schedules, and a meaningful basis for performance measurement for the remaining work. Reprogramming decisions must be based on achievability of the remaining plan. They are preceded by a comprehensive EAC and schedule review and may result in the need for an IBR. During the life of a program, initiation of reprogramming may be required when severe performance or technical problems are realized. Only after all other corrective management actions are implemented should the program decide the baseline is inadequate for effective control. Before reprogramming, it is in the best interest of the company to maintain open communication with the appropriate stakeholders (internal or external) in the process. Approval from the customer is required before implementing a reprogram for those programs that have a CPR requirement. Customer and contractor discussions should address the program cost, schedule, technical, and funding implications resulting from implementing a reprogram. Implementation of an OTB (i.e., the CBB exceeds the original contract value) does not result in an automatic contract modification nor a change to the contract past performance. A program considering a reprogramming effort should exhibit the following characteristics: a. The overall program is between 15 and 85 percent of budgeted work complete (BCWPcum/BAC) and at least 6 months of significant effort remaining. b. The existing budget baseline cannot be executed within reasonable tolerances. 2. Below is a list of key reprogramming decisions that should be considered: a. Over-target schedule (OTS) – Defined as a schedule in excess of contractual obligations b. Customer concurrence regarding remaining scope and needed AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 8 of 11 COP 30.104 Change Control resources c. OTB – Defined as a budget in excess of contractual obligations d. Elimination of cumulative schedule variance e. Elimination of cumulative cost variance f. Establishment of new management reserve targets for future risk mitigation g. Appropriateness of management controls to focus on problem areas h. Potential recovery from the customer for under-valued scope. i. Contracting officer written approval is required before reprogramming is implemented. Contracts without an external EVMS requirement require the approval of management and finance, at least one level above the contract Program Manager. VII Office of Primary Responsibility VIII Attachments Director of Program Controls Attachment A – Change Control Logic Attachment B – Baseline Change Control Target Timeline IX Disposition of Records This procedure is valid until superseded or cancelled. X Approval Level Program Manager XI References A. COP 30.101 Planning and Budgeting (Level 4) AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 9 of 11 COP 30.104 Change Control Attachment A–Change Control Logic AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 10 of 11 COP 30.104 Change Control Attachment B–Baseline Change Control Target Timeline AGS Corporate Operating Procedures Date: 09.26.2011, New Uncontrolled when printed. Page 11 of 11