Interview Question for QA/QC Electrical and Instrumentation Inspector General Questions Q What is Q.C./Quality Control? Ans 1)-Quality control is an inspection or testing of products to uncover defects and reporting to management who make decision to allow or deny the product release. 2)-Quality control is an operational technique (inspection, testing, and examination) that are used to fulfill the quality requirements. Q What is Q.A./Quality Assurance? Ans 1)-Quality assurance attempts to improve and stabilize the production by avoiding or minimizing the issues which led to defects. 2)-Quality assurance is the system of action and planning needed to provide a service or product will satisfy the requirements of quality. Q What are the responsibilities of QA/QC inspector at site? Ans A QA/QC inspector is responsible for quality control and quality assurance of all the construction works, and all the work at site should be according to standards, approved procedures and ITP’s. When some construction activity starts, QC will do internal inspection and will do review of documents before raising the RFI. If there is some violation or non-conformance in work then QC shall raise NCR. When there is some issue/complication/irregularity regarding to construction activity then QC will consult with his QC supervisor and construction representative to resolve it. Q What is schedule Q? How many attachments it has? Ans Schedule Q is an Aramco document that describes the project quality requirements, inspection schedules and procedures, documentation requirements, contractor and subcontractor quality personnel qualification requirements and quality requirements for contractor supplied materials. It has 6 attachments: (1) Attachment-I >> Contractor and Subcontractor Quality Personnel Qualification Requirements (2) Attachment-II >> Saudi Aramco Standards and Procedures Containing Quality Requirements (3) Attachment-III >> Quality Requirements for Contractor Supplied Materials (4) Attachment-IV >> Quality Requirements for the Construction Phase (5) Attachment-V >> Summary of Quality System Deliverables (6) Attachment-VI >> Project Specific Quality Requirements Q What is the quality plan? Ans 1)-It includes procedures and documents, covering work activities and description of sequences of work. 2)-Quality Plan include inspection, testing and proper documentation. 3)-Document specifying which procedures and associated resources will be applied by whom and when to a specific project, product or process. Q What is SAES, SAEP, SAIP, SAMSS, SAER, GI, SATIP, ITP, SAIC, QMIS, RFI? Ans SAES: Saudi Aramco engineering Standards SAEP: Saudi Aramco engineering procedures SAIP: Saudi Aramco inspection procedure SAMSS: Saudi Aramco materials systems specifications SAER: Saudi Aramco engineering report GI: Saudi Aramco general instructions SATIP: Saudi Aramco typical inspection plan SATIP is a document which provides us information related to activity, activity number, SAIC number and responsibility of contractor and client QC personnel inspection level. ITP: Inspection and test plan SAIC: Saudi Aramco inspection checklist QMIS: Quality management information system RFI: Request for inspection Q Name some international standards which you follow for electrical and instrument work? Ans IEEE: Institute of electrical and electronic engineers NEC: National electrical code IEC: International electrotechnical commission NEMA: National electrical manufacturers association 2 NFPA: National fire protection association NACE: National association of corrosion engineers ANSI: American national standards institute ASTM: American society for testing and materials UL: Underwriters laboratories AEIC: Association of Edison illuminating companies ICEA: Insulated cables engineering association IS: International standards ISO: International standards organization BS: British standards institution Q How will a QC inspector raise a RFI? Ans When some activity starts, QC will do internal inspection and will do review of documents and then will raise the RFI. Q How much time before the inspection you will raise RFI? Ans 24 hours before the inspection time. Q What is the inspection, documentation, document review, standards, hold point, witness point? Ans Inspection: An activity such as measuring, examining, testing one or more characteristics of a product/equipment and comparing the results with specified requirements (standards and procedures) in order to know whether conformity is achieved or not for each characteristic. Documentation: Any record or pictorial information describing, defining the procedures or results. Document review: To collect all the documents related to an activity and to evaluate the requirements for quality of that specific activity are fulfilled or not and to identify if there is any problem or non-conformity exists. Inspection assignment package: A set of documents that include details of purchased material/equipment, needed to perform full inspection at the vendor/sub-vendor facility. Standards: A document approved by a generally recognized body. Specification: A detailed description of the design and materials used to make something. 3 Quality management system: All activities that determine the quality policy, objectives and responsibilities, and implement them by means such as quality planning, quality control, quality assurance. Quality System: Organizational structure, procedures, processes and resources needed to implement the quality arrangements and requirements. Quality audit: A systematic and independent examination to determine whether quality activities and related results comply with the planned arrangements and whether these arrangements are implemented effectively and are suitable to achieve objectives. Hold point: Inspection or test stage beyond which work/activity should not proceed without the QA/QC organization representative in attendance. Witness point: A point that provides QA/QC representative with the opportunity to attend the inspection/test at his option. Surveillance: Generally visiting the site work without RFI. Compliance: A judgment that the product or service meets the requirements of the relevant specification or standard. Non-conformity: Non-fulfillment of a specific requirement of the relevant specification or standard. Corrective action: Action taken to eliminate the defect or existing non-conformity, or other undesirable situation. Preventive action: Action taken to eliminate the causes of the existing non-conformity, defect or other undesirable situation in order to prevent recurrence. Procedure: A specified way to perform an activity. Pre-commissioning: Testing of system components for continuity, operability. Commissioning: Process by which an equipment, facility, or plant (which is completed or near completion) is tested to verify if it functions according to its design objectives or specifications. Q What is NCR, Define and explain it with example? Ans None-conformance report, we raise NCR when there occur some non-conformity/violation at the site during the construction work or when there is some non-conformity/violation occurred during material receiving. There are 4 parts of a NCR... (1) Violation occurred (2) Root cause analysis (3) Corrective action to be taken (4) Preventive action (Recommendations to avoid re-occurrence of violation). 4 Q What will you do when you see some violation/non-compliance has occurred at site? Ans I will put internal NCR at once and then after that I will ask to construction team to take action to rectify it. Q After how much time of occurrence of violation you will raise NCR? Ans Within 24 hours Q Within how much time the violation/non-conformity should be resolved? Ans As per ACD-(Agreed Completion Date). Q There are how many types of NCR? Ans: There are 2-types of NCR, and what is the difference between them? 1- Internal NCR 2- LBE Standard Violation/Client NCR 3- Company NCR Internal NCR is a NCR which is raised by the Contractor QC-Inspector and LBE/Client NCR is a NCR which is raised by PID (Client QC-Inspector) Q How many types of RFI are? Ans There are two type of RFI; (1) Internal RFI (2) QMIS RFI Q What is walk through? Ans Preparation of balanced work report (punch list items) upon completion of 80% of construction work Q What is punch list items? Ans Any balanced work report during completion of work is called punch list items. Q What is two week look ahead schedule? Ans It is the schedule of work that have to do/complete in the next two weeks. The project planner/ project scheduler will prepare two week ahead schedule. Q What is the T.Q? Ans If there is some conflict/issue occurred to execute work as per approved IFC Drawing, T.Q is raised according to site requirement and the designer/CSD/Client will approve it. Q What is red-mark/as-built drawing? 5 Ans Changed drawing according to the site requirement, for example re-routing/re-location of cable/conduit/equipment. Q To deviate from any standard and other Mandatory Saudi Aramco Engineering Requirements (MSAERs), what is the procedure? Ans As per SAEP-302, if there any conflict between Mandatory Saudi Aramco Engineering Requirements (MSAERs) or referenced industry standards shall request the Manager, Consulting Services Department (CSD) of Saudi Aramco, Dhahran to resolve the conflict. To deviate from any standard, requests shall be submitted electronically through the SAP Waiver Process in accordance with SAEP-302. Q For obtaining a Waiver of a Mandatory Saudi Aramco Engineering Requirement which standard we follow? Ans For obtaining a waiver of a Mandatory Saudi Aramco Engineering Requirement we follow SAEP-302. Q What is a waiver? Ans To get favor to deviate from any Mandatory Saudi Aramco Engineering Requirements is called waiver. Q What is FAT test? Ans The factory acceptance test procedure is a test that is performed to determine that an equipment or product meets the requirements or specifications of a client before it shipped out to its destination site. The FAT is normally performed at the manufacturer’s workshop. The manufacturer checks that the safety instrumented system works as intended according to the requirements stated in the safety requirements specification (SRS). Q What are the test activities included in FAT? Ans During the FAT the manufacturer checks: I) II) III) IV) V) VI) VII) The equipment is according to the specification. The equipment is installed according to the manufacturer’s specifications. The inputs and outputs are connected according to the drawings. The calibration of the equipment are correct. The trip points operate according to the requirements in SRS. The logic solver and associated software operate according to the requirements. The outputs and their actions behave according to the SRS. 6 VIII) IX) X) XI) XII) XIII) The reset function operate according to the SRS. The alarms operate according to the SRS. The operator functions operate according to the SRS. The bypass function operate according to the SRS. The manual shutdown function operate according to the SRS. The diagnostic alarm functions according to the SRS. Q What is SAT test? Ans SAT is site acceptance test of an equipment to ensure that it is tested in accordance to client approved test plan & specifications and to show the equipment is installed properly and interfaces with other systems and peripherals in its working environment. Q How many test are done on circuit breaker? How we do pre-commissioning of circuit breaker? Ans The following test are performed on circuit breaker 1) Contact resistance test {this involves injecting a fixed current through the contacts and measuring the voltage drop across it using Wheatstone bridge, kelvin bridge and ohm law. This test is done with special contact resistance measuring instrument name microohmmeter (200A/600A) to check the contact condition/damage} 2) Current injector test/ Trip Test {primary current injection tests are normally conducted to check the operation of circuit breaker and their protective relays and devices. The objective of the test is to identify how the system operates under various levels of current load. By injecting current into the system we can measure if the breaker will trip or fail. This test is performed with Primary Injections Tester}. 3) IR test (megger test) Q How many test are performed on motor? How we do pre-commissioning of motor? Ans 1) IR Test 2) Continuity Test 3) Low resistance test {low resistance ohmmeter – MOM milli-ohmmeter} 4) No load test / Solo run test (4 hours to check if voltage or current drop) 5) Temperature Test (With Temperature Gun, Assembly+ Bearing+ Shaft+ Non-Derive End) 6) Vibration Test (Vertically, Horizontally, Axially of Frame, Foot and Base with vibration tester) 7) Noise Test (DBA Meter-at derive end and non-derive end) 8) Full load test – Mechanical Run Test (it is performed by operation department to check the capacity of motor for designed parameters of system for voltage or current) 7 Q How many test are performed on transformer? How we do pre-commissioning of transformer? Ans 1) Low resistance test {low resistance ohmmeter – MOM (milli-ohmmeter)} 2) Winding Resistance Test (MOM-Micro ohmmeter) {the resistance can be measured by simple voltmeter ammeter method, kelvin bridge meter or winding resistance measurement kit} 3) Turn ratio test (MOM) 4) IR Test 5) Continuity Test 6) Temperature Test 7) Breakdown test (oil di-electric strength test, for oil immersed transformer apply 50KV) 8) No load test 9) Gauge calibration (Level and Temperature) Q What is low resistance test? Ans Q What is winding resistance test? Ans Q What is temperature test of motor and transformer? Ans Q What is the turn ratio test of transformer? Ans Q How we do contact resistance of busbar and cable joints? Ans We do this test with ducter test. Q What is ducter test? Ans Contact resistance test (commonly known as the ducter test) measures the resistance of electrical connections such as joints, terminations and connectors etc. This test measure the resistance at the micro or milli ohm level and is used primarily to verify that electrical 8 connections are made properly. This is particularly important for contacts that carry large amount of current e.g. switchgear busbar. ------------------------------------------------------------------------------------------------------------------------------Material Receiving Questions Q How we do material receiving, describe the general procedure? Ans We collect all the documents related to the material to be inspected and after document review we do the inspection and we check that the arrived material is according to the NMR, PO, MTO, IRC and Delivery Note and verify that Aramco standards and specifications are complied, then we raise the RFI for final inspection and acceptance. Q What documents are required for material receiving? Ans Material receiving RFI includes the following contents depending upon the type of material. (1) MR/NMR---(Material Requisition> include the approved material’s details and specifications) (NMR—If there is some conflict in MR then NMR >> non material requirement) (2) IRC---(inspection release certificate/vender inspection certificate) (3) MTC/MTR---(Material testing certificates/ material testing reports) (4) PO--- (Pay order) (5) Delivery note (6) Aramco-manufacturer vender ID // Aramco-supplier vender ID (7) MTO---(Material take off list/project complete items list) (8) Calibration certificates/ ISS-Data sheets for instruments/ Technical Drawings for electrical Equipment and instruments. (9) If equipment/instruments are for hazardous area should have certificates of flameproof/explosion proof (i.e. EEx D, IECEx). (10) If Cable material then cable schedule/meggering & continuity certificate for cables (11) Related Drawings Q What documents are required for material supplied by Aramco? Ans When material is supplied by Aramco, following document are required. (1) Out Bond TO (2) MTO (3) Related Drawings Q What type of label or certification requirements are for equipment in classified (hazardous) area? Ans IEC or EX labeled equipment meeting the requirement of IEC 60079. 9 IECEx certification is needed and shall meet shall meet NEC requirements (Article 505). Q What type of label & certifications are required for enclosures in classified (hazardous area)? Ans Enclosures shall be flameproof (explosion proof), EEx D II certification, meeting the NEC requirements (Article 505) & IP-54. Q What are the requirement for equipment used in severe corrosive environments (and offshore locations)? Ans NEMA Type 4 X, IP-66 Q Which document provide us information about the material inspection levels? Ans Inspection levels are mentioned in SAER-1972 (Saudi Aramco Materials Inspection and Testing, SA 175 Forms) Q What are the material inspection levels according to SAER-1972? Ans There are 5-levels (1) Level-0 >> required documentation only, no vendor inspection required. (2) Level-1 >> only final inspection is required prior to shipping (3) Level-2 >> include pre-inspection meetings, one or more surveillance inspections, all witness and hold points, final inspection and release for shipping (4) Level-3 >> include pre-inspection meetings, surveillance inspections on regular basis (daily, weekly or bi-weekly), all witness and hold points, final inspection and release for shipping. (5) Level-4 >> resident inspector continuously monitoring the work ----------------------------------------------------------------------------------------------------------------------------------------- Cathodic Protection (SAES-X-400, SAES-X-600) Q What is CP and how we do it? Ans Cathodic protection (CP) is a technique used to control/prevent the corrosion of metal by making it cathode of an electrochemical cell. Q Which standard we follow for the “cathodic protection of buried pipelines”? Ans SAES-X-400 Q Where we use SAES-X-600? Ans SAES-X-600 is used for “cathodic protection of plant facilities”. 10 Q How many types of CP are used? Ans There are two types of CP; 1) Galvanic Cathodic Protection 2) Impressed Current Cathodic Protection Q What are the contents of permanent CP? Ans CP Transformer rectifier, DC Cable/ Separate negative leads, High silicon cast iron anode. Q What is galvanic/temporary cathodic protection, define it with diagram. Ans In galvanic cathodic protection, a galvanic anode, a piece of a more electrochemically active metal, is attached to the required metal surface. The galvanic anode continues to corrode, consuming the anode metal until it must be replaced. Q What is impressed current cathodic protection (ICCP), explain it with diagram. Ans Impressed current cathodic protection (ICCP) systems consist of anodes connected to a DC power source, often a transformer-rectifier. An ICCP system for pipeline consist of a DC power source, often an AC powered transformer rectifier and an anode or array of anodes buried in the ground (the anode groundbed). The DC power source would typically have a DC output of up to 50 amperes and 100 volts, but this depends on several factors, such as the size of the pipeline and coating quality. The positive DC output terminal would be connected via cables(25 mm2/ #4 AWG) to anode array, while another cable would connected from the negative terminal of the rectifier to the pipeline, preferably through junction boxes to allow measurements to be taken. Anodes can be installed in a groundbed consisting of a vertical hole (50ft/15m minimum) and backfilled with conductive coke (a material that improves the performance and life of the anodes) or laid in a prepared 11 trench, surrounded by conductive coke and backfilled. The choice of groundbed type and size depends on the application, location, and soil resistivity. Q What types of anodes are used in galvanic/temporary cathodic protection and impressed current cathodic protection? Ans For galvanic cathodic protection mostly magnesium anodes are used (for dry, sandy, rocky areas 60lbs prepackaged Mg anode is used and for buried mechanical fittings 32 lbs prepackaged Mg anode is used and for wet, subka areas 100 lbs bare-not prepackaged Mg anode is used) and sometimes zinc anodes also used. For impressed current cathodic protection mostly High Silicon Cast Iron (HSCI) anodes are used and sometimes Mixed Metal Oxide (MMO) are also used (only for use in subka) Q What is the purpose of temporary cathodic protection? Ans The purpose of cathodic protection (CP) is to control the corrosion of new pipeline by making it the cathode of an electrochemical cell. Q For how much length of pipelines the permanent CP is required? Ans Production pipelines that extend more than 25km Q Within how many days need to provide a temporary/permanent CP? Ans Within 30 days of burial. Q How to know that temporary CP is working is properly? Ans Potential survey data shall be submitted monthly to verify that temporary CP is providing proper protection. Q For how long time the potential survey data should be submitted? 12 Ans Pipe-to-soil potential survey data verifying that the temporary system is providing proper protection shall be submitted to the CP proponent monthly for 6-months, and every 6-months thereafter. Q What is bond cable? Ans A cable installed between two metallic structures to provide electrical continuity between the structures for the purpose of cathodic protection. Q What is calcined petroleum coke breeze? Ans A carbonaceous backfill used as a conductive backfill media for impressed current anodes in soil. Q What does mean CP? Ans Cathodic Protection Q What is Cross Country Pipeline? Ans A pipeline between; two plant areas, another cross-country pipeline and a plant area, or between two cross-country pipelines. Q What is CSD? Ans Consulting Services Department Q What is Deep Anode Bed? Ans Anode or anodes connected to a common CP power supply installed in a vertical hole, (typically 25 cm diameter) with a depth exceeding 15 m (50 ft.). Q What is Design Agency? Ans The organization or company contracted by client for the design of a system. Q What is Drain Point? Ans The location on the cathodically protected structure where the negative cable from the rectifier or junction box is fastened. Q What are Galvanic Anodes/Sacrificial anodes? Ans Anodes fabricated from materials such as magnesium, zinc or aluminium that are connected directly to the buried structure to provide cathodic protection. Galvanic anodes are also called sacrificial anodes. Q What is Negative Cable? Ans A cable that is electrically connected (directly or indirectly) to the negative output terminal of a cathodic protection. Q What is Positive Cable? 13 Ans A cable that is electrically connected to the positive output terminal of an ICCP power supply, including impressed current anode cables. Q What is Reference Electrode? Ans An electrode used as a common reference potential for cathodic protection measurements. A copper/copper sulfate (Cu/CuSO4) reference electrode is typically used for soil applications. A silver/silver chloride (Ag/AgCl/0.6M Cl) reference electrode is typically used for aqueous applications. Q What is GOSP and WIP? Ans Gas and Oil Separation Plant, Water injection plant Q What is thermite weld/ Cad Weld? Ans An exothermic process to make electrical connections between tow piece of metals. Q What is the content of the cad weld? Ans Mold, powder, steel plate, fire gun or lighter Q With one mold how many cad welds are allowed? Ans Fifty (50) CAD Welds are allowed. Q How we will verify that CAD Weld powder is okay to use? Ans It shall be of same number as mentioned on mold, and CAD weld powder & mold shall be from same manufacturer and shall be UL listed. Q What are the dimensions for surface cleaning for CAD Welds? Ans Shall be cleaned 100 mm sq including 50 mm sq white cleaned and in case if two adjacent cad welds or failure of cad welds the distance will be 75mm apart. Q What shall be the weight of the hammer to test cad weld? Ans It shall be one pound. Q How much value is for open circuit potential for galvanic anodes? Ans Magnesium anodes have an open circuit potential of -1.7 volts. Q What is project proposal package? And what shall it provide? 14 Ans The Project Proposal package shall provide all general design considerations that can be developed without requiring measurement of field data. The Project Proposal package should include: a) A scope of work including a specific statement that clearly identifies any additional requirement to provide CP for any existing pipeline. b) Proposed locations of new cathodic protection systems on an overall CP system layout drawing, including proposed anode type(s) and estimated output ratings of the proposed cathodic protection power source. c) Information on spare cathodic protection capacity (from nearby or adjacent pipelines) along the route of the proposed pipeline. d) Information on all locations where the proposed pipeline will be mechanically connected to other facilities (plants, pipelines etc.) with clear details on whether these other facilities will be electrically isolated. Q At which locations the electrical isolation or supplemental cathodic protection is mandatory? Ans Electrical isolation or supplemental cathodic protection is mandatory at (a) (b) (c) (d) (e) Valve stations and scraper traps Metallic supports Pipelines between GOSPs, WIPs, or other production facilities Product pipeline to bulk plant transitions MOV Q What are the bonding requirements for buried pipelines? Ans Bonding shall be provided at the following locations (a) At every 10 km intervals (at all negative drain points for ICCP power supplies) between the parallel pipelines wherever pipelines are parallel within 50 meters (b) At all buried pipeline crossings (c) All the negative drain points for ICCP power supplies (d) Within 500m start and end of parallel segment *Bonding shall be completed according to Standard Drawing AA-036674. *Bonding is only required between a crossing pipeline and the outer pipelines, provided adjacent pipelines are not more than 50 meters apart. Q Which kind of anode shall install for temporary CP? Ans Install galvanic anode of Mg for temporary CP system using 3-pin test station. Q What is the size of cables used for CP bonding? Ans It is 10 mm sq. and 16 mm sq. (8-AWG & 6-AWG) 15 Q What is the minimum size for the primary positive and negative DC cables from the rectifier? Ans The minimum size for the primary positive and negative DC cables from the rectifier shall be 25 mm2 (# 4 AWG) Q What is the size of bond conductor in Aramco standard? Ans The minimum bond conductor size shall be 6 AWG (16 mm2) Q How many anodes are installed at buried mechanical fitting? Ans One 32 lbs prepackaged anode in installed Q (1) How many anodes are installed at full thrust anchors? (2) How many anodes are installed at trust bored road crossings? Ans Two 60 lbs prepackaged Mg anodes at each end, total of 4 anodes. Q At thrust anchor anode installation, how much distance is required from anodes to pipeline & thrust anchor? Ans Four anodes are installed at thrust anchor two at each side, distance from pipe to anode shall be 1000mm/1m and 600mm apart from thrust anchor and 900mm deep. Q How many anodes are installed at camel crossings? Ans One 60 lbs prepackaged anode per pipe, plus one additional 60 lbs prepackaged anode, i.e. one pipe requires 2 anodes and two pipes requires 3 anodes. Q How many anodes are installed for open road cut? Ans 2 anodes, one at each side for the open cut road. Q How many anodes shall install at thrust anchor located inside the fence or plant area? Ans 2 magnesium anode, one at each side. Q What is the mini length for the pipe line to be treated as cross country pipe line? Ans As per SAES-X-400, the minimum length for the cross country pipe line is 25-KM. if pipeline is more than 25 km it shall be call or treated as cross country pipe line. Q What is the voltage value of CP cable holiday test? Ans 18 KV - DC Q What the minimum life is of impressed current and galvanic anode system? 16 Ans As per the SAES-X-600, the minimum design life of impressed current and galvanic anodes shall be 20 years. Q What the minimum life is of temporary CP system? Ans The minimum design life of temporary CP system shall be 2 years. Q What is the capacity/rating of power source is required for ICCP? Ans 50V & 100 Amps Q At what locations test station should be provided on pipelines? Ans Provide a test station for measuring pipe-to-soil potential at (a) at kilometer marker (1-pin) (b) negative connection (3-pin) (c) thrust anchor (d) road crossings Q Within how many days of pipeline burial there should be installed 1-pin and 3-pin test stations? Ans Within 1-week of berming completed. Q What shall be the height of test station from grade level? Ans It shall be 1200mm/1.2m Q What is the purpose of test station? Ans The purpose of the test station is to take the pipe-to-soil potential measurements. Q What is the average current density of galvanic anodes for buried pipelines? Ans Average current density for bare pipelines is 20 mA/m2 Average current density for coated buried pipelines is 0.1 mA/m2 (design criteria) and 0.005 mA/m2 (temporary criteria) Q What is the maximum current density of impressed current anode? Ans For HSCI anode maximum current density is 0.7 mA/cm3 Q What is the mini currents density value for bare buried steel? Ans Minimum current density for bare steel buried is 20 mA/m2 Q What is the mini current density value for copper ground rod? Ans Minimum current density for copper ground rod is 50 mA/m2 Q What is the minimum and maximum voltage for buried pipeline? 17 Ans According to SAES-X-400 minimum voltage 1.V and maximum 3 V with the reference to a copper /copper sulfate electrode. Q What types of reference electrodes are used for taking voltage potential value from pipe-tosoil? Ans Copper-copper sulfate (Cu-CuSO4) reference for soil, and silver-chloride electrode for aqueous applications. Q How much depth require for installation of Anode for ICCP protection? and galvanic cathodic protection? Ans For ICCP anode bed, minimum depth requirement is 15 meters (50 ft.) Q How much depth require for installation galvanic Anode? Ans For galvanic anode the required depth is 900 mm/ 90 cm from the ground level and in rocky areas it should be 300 cm/ 30 cm, the clearance between pipe and anode should be 600 mm/ 60 cm. *When parallel piping runs prohibit 600 mini clearance, anodes shall be buried a mini of 600 below pipe (except 300 min. in rocky areas). Q What should be the minimum distance between two anodes installed side by side? Ans There should be 1.5 m distance between two anodes. Q What should be the clearance/ distance between pipeline and anode in CP? Ans The clearance between pipe and anode should be 600 mm/ 60 cm Q What is the minimum HSCI anode bed distance from the buried pipe line or structure? Ans SAES-X-400 says minimum distance 35 meter and maximum 225 meter. Q What are the depth requirements for direct buried CP cable Trench? Ans For sand or subka area Total 750mm is required including 150mm sand bedding and then after warning tap 450mm sand cover. For Rocky Area Total 300mm is required including 75mm sand bedding and then 125mm cement backfill. For Sand and Rock Area 18 Total 450mm is required including 75mm sand bedding and after warning tap 150mm crushed marl backfill. Over the pipeline crossing Total 600mm required including 150mm sand bedding (distance between cable and pipe) and 450mm sand cover. Q What is the width of CP cable trench? Ans It is 200mm. *Cathodic protection Junction Boxes and Bond Boxes shall be manufactured in accordance with 17-SAMSS-008. Q What is the difference between the bonding box and junction box? Ans Bonding box is used in bonding two wires, while junction box in instrumentation for connection of instrument wires. Q What is the difference between distribution board and junction box? Ans Junction box contains terminal blocks and is used for termination and joining of cables. While distribution board contains breakers for distribution of electricity to one or more power circuits. *Do not install the D.C power supply in hazards location *Do not use DC power supplies with rated output voltage greater than 100 volts *Do not install isolating devices in areas classified as hazardous locations. *Do not install isolating devices in any buried or submerged portions of a pipeline. *Install the rectifiers in non-hazardous areas where possible and use oil-immersed rectifier units inside hydrocarbon plant areas. *Conduct soil resistivity or soil conductivity measurements at 10-meter intervals over the full length of the proposed remote surface anode bed location. *The number and size requirements for the anodes shall be determined based on providing a sufficient potential gradient over the entire length of the respective pipeline to achieve the protection criteria. *If impressed current anodes are placed within 50 meters of a thrust anchor, then two additional impressed current anodes shall be installed within 15 meters of the anchor, and placed on opposite sides of the anchor. If impressed current anodes are installed, galvanic anodes are not required for the thrust anchor. 19 *Use 27.2 kgs (60 lbs) magnesium anodes for soil resistivities greater than 500 ohm-cm. Grounding (SAES-P-111) Q What is the difference between bonding, earthing and grounding? Ans Bonding: Bonding is simply a technique of joining two electrical conductors together to bring them to the same electrical potential. Bonding has to be done by connecting of all the metal parts (that are not supposed to be carrying current under normal conditions) to bring them to the same electrical potential. Bonding ensure that these two things which are bonded will be at the same electrical potential. Earthing: Earthing means connecting the dead part (which does not carry current under normal conditions) to the earth for example electrical equipment’s frames, enclosures, supports etc., to minimize the risk of receiving an electric shock if touching metal parts when a fault occurs. Grounding/Neutral: Grounding means connecting the live part to the earth, for example neutral of the power transformer, for the protection of the power system equipment and to provide an effective return path from the machine to the power source. Q What is the purpose of grounding? Ans The purposes of grounding are personal safety, equipment & distribution circuit protection, electrostatic discharge, building safety protection etc. Q What are the names of international standards which are used for grounding and ground system installation? Ans Grounding and ground system installation shall be designed in accordance with IEEE 142 and meet the requirements of NFPA 70 (NEC 250) *Measurements of earth resistivity and ground impedance shall be made in accordance with IEEE 81 Q Describe the characteristics/properties of ground Conductors? Ans Ground conductors shall have the following characteristics: (a) Should be of copper. (b) If insulated should have green jacket or a green jacket with yellow stripes. 20 (c) If larger than 35 mm² (#2 AWG) be stranded. Q Describe the requirements/characteristics of ground rods? Ans Ground rods shall have the following characteristics: (a) Shall be UL listed & meet the requirements of UL 467. (b) i) copper or ii) copper jacketed-steel or iii) galvanized-steel (c) Have a minimum length of 2.4 meters. (Jointed rods are permitted but each joint must be 2.4 meters long) (d) Copper or copper jacketed steel rods be minimum of 16 mm in diameter, Galvanized steel rods be minimum of 19 mm in diameter. Q What type of ground rod is used in areas of 70 ohm-meters resistivity areas or areas protected by cathodic protection (low resistivity areas)? Ans In areas where cathodic protection is present (lower than 70 ohms-meters resistivity), galvanized steel ground rods (minimum 19 mm dia) are used. Q What is the standard color for insulated grounding conductor? Ans The grounding conductor shall be green or green with yellow strip. Q What is the size of ground conductor is used for grid and equipment? Ans SAES-P-111 says that the cable size for grid interconnection and with ground rods shall be mini 70 mm2 and for the equipment grounding mini 25mm2 shall be used. Q What is the length of grounding rod? Ans SAES-P-111 says, ground rods have a minimum length of 2.4meter. Q What is the diameter of a copper and galvanized steel rod? Ans For copper or copper jacketed steel rod minimum diameter is 16mm. And for galvanized steel rod diameter is minimum 19mm. Q How we do grounding at pipeline valve stations? What are the grounding requirements at valve stations? Ans According to SAES-P-111, grounding at pipeline valve stations shall be done with zinc or magnesium anodes interconnected by insulated copper cable. Each ground rod shall be replaced by with a magnesium or zinc anode and a minimum of two anodes spaced a minimum of 2 meters apart. Q Which grounding rod is used when area is subject to cathodic protection? 21 Ans According to SAES-P-111, the ground rods shall be galvanized steel if area is subjected to cathodic protection. Q How much there will be distance between the ground rods installed in triangular shape for MIG ground (master instrument ground) Ans There shall be a distance of 1.83m (6ft) between them. Q What is the goal of installing more than one ground rods? Ans To achieve resistance of 25 ohms Q What is the grounding electrode? Ans The electrode which is used for grounding purpose. Q What is the resistance for ground grid/ network of electrical system? Ans It shall be 5 ohms i.e., voltage drop 5V Q What is the resistance for ground grid/ network for instrument system? Ans It shall be 0 ohms i.e., voltage drop 0V Q How we do the below ground and above ground connections to grounding grid or ground rods or between grounding conductors or ground rods? Ans (a) By thermite welding or brazing (b) By irreversible compression type connectors (c) To steel structure by compression type connectors bolted to bare steel. (d) Approved mechanical connectors, where it is necessary to disconnect ground conductors for test at ground test stations. *Underground ground conductors shall be insulated when within 3 meters of a buried metal pipeline or metal piping. *Underground ground conductors electrically connected to buried metal pipelines, buried metal vessels, or metal tanks sitting on grade shall be insulated. *The goal of a grounding rod is to achieve a resistance of 25 ohms or less between the rod/grounding conductor and the soil *Master Instrument Ground grid is made by connecting the ground rods in ground in a triangle shape each 1.83m apart. 22 Substation Grounding Q How we do the substation equipment grounding? Ans Substation equipment shall be grounded as follows: (a) For substations having equipment operating at a nominal system voltage exceeding 1,000 Volts, a ground grid meeting the requirements of IEEE 80 for step and touch potential shall be installed. (b) All electrical equipment in the substation, substation yard, and within 5 meters of the substation fence shall be connected to the grid or to a ground bus connected to the grid. (c) Substation ground grids shall be constructed of minimum 70 mm² (2/0 AWG) stranded bare copper cable. Q What is the size of substation ground grids cable? Ans Substation ground grids shall be constructed of minimum 70 mm² (2/0 AWG) stranded bare copper cable. Grounding Electrodes Q Can the reinforcing bar of building be used as a grounding electrode? Ans Reinforcing bar of buildings shall not be used as a grounding electrode. Structural steel of a building may be used as a grounding electrode in accordance with the NEC provided it is continuous and effectively grounded by connecting at least every other structural steel column on the perimeter of the building to a concrete-encased electrode or a ground ring installed per the NEC and this standard. Q If concrete-encased electrode is used, what type of conductor is should be? Ans If a concrete-encased electrode is used, the conductor must be bare copper. Q What type of ground rod is used for system grounding? Ans The ground electrode for system grounding shall consist of (1) A rod or pipe electrode OR (2) Combination of rod or pipe electrodes and a grid or loop of bare copper conductors Q How much the buried depth required for grounding conductor used to interconnect rod or pipe electrode? Ans SAES-P-111 says, the conductor shall be buried a minimum depth of 460 mm. Q Where supplementary grounding electrode shall be provided? 23 Ans Supplementary grounding electrodes (per NEC 250) shall be provided in outdoor industrial areas, process plant areas, and in substations Q What is the minimum burial depth for ground conductor or loop? Ans The grids or loops shall be buried a minimum of 460 mm. Q Supplementary electrodes are made of what? Ans Supplementary electrodes shall consist of ground rods connected by bare or covered conductors, bare ground conductors, or combinations. Q How many connections require for above ground supplementary electrode? Ans Two connection are required to supplementary electrode. System Grounding Q What is system grounding? Ans System grounding is a technique used to protect a power system and to give the return path to the current from load to the source. Q What is grounding system for three phase electrical system as per SAES-P-111? Ans As per SAES-P-111, three phase electrical system shall be grounded at neutral point of the wye connection of the transformer or generator by connecting directly as possible to grounding grid or grounding electrode. Q How we do grounding of dry type transformer? Ans Dry-type transformers in substations, in switchgear rooms, or in equipment rooms may be connected to a ground bus that is directly connected to the grid or other grounding electrode. Q What is solidly neutral grounded system? Ans In solidly grounded system, the neutral point in connected to earth directly by ground electrode. Solidly grounded systems are usually used in low voltage applications at 600 volts or less. Solidly neutral grounding slightly reduce the problem of transient over voltages, found on the undergrounded system and provide path for the ground fault current. 24 Q What is the ground resistance in solidly grounded system? Ans According to SAES-P-111, for solidly grounded system, the resistance for above 600V is 1Ω, and ground resistance for less than 600V is 5Ω. Q What is low resistance grounding? 25 Ans A grounding in which a transformer or generator is grounded by connecting a resistor between the system neutral and ground to provide the desired higher value of ground current. The impedance is selected to limit line to ground fault current normally between 100A to 1000A Q What is high resistance grounding? Ans A grounding in which a transformer or generator is grounded by connecting a resistor between the system neutral and ground to provide the desired lower value of ground current. The impedance is selected to limit line to ground fault current normally less than 10A. With an HRG system, service is maintained even during a ground fault condition. If a fault does occur, alarm indications and lights help the user quickly locate and correct the problem or allow for an orderly shutdown of the process. Equipment Grounding Q What is the equipment grounding? Ans Equipment grounding is the grounding used for protection of our using equipment and for protection of human life from electric shocks. Q How many grounding connection are provided from grounding bus to electrical panel board? Ans Ground busses (in switchgear, switchboards, and motor control centers) shall have two connections to the local ground grid or the main ground electrode. Q How many grounding connections are provided from ground grid to ground bus? Ans Two connections Q How many grounding connection are provided from grounding bus to instrument panel board? Ans 2 connections Q How many grounding connection are provided from grounding bus to instruments? Ans Two connections. Q How many grounding connection are provided from grounding bus to electrical equipments? Ans Under 1000 V panels shall be provided with one connection and above 1000V shall be provided with two connections. Frames of equipment (motors, generators and transformers and other equipments) operating at 1000 V or greater shall have two connections to the grounding electrode. Q Which two grounding systems are required for instrumentation systems? 26 Ans These two grounding systems are required for instrumentation systems: a) Safety Ground for personnel safety. b) Instrumentation DC & Shield Ground. Q What is the minimum size of equipment ground conductor? Ans The minimum size of equipment ground conductor is 25mm2/ 4 AWG. Q Metallic cable tray after how many meter need to be bond? Ans According to SAES-P-111, metallic cable trays shall be bonded at both end points a minimum of 25 meters. *Aluminum cable trays containing only circuits operated at, or below, 50 V to ground may be used as equipment grounding conductors *A cable concentric neutral, if properly sized and not used as a current carrying grounded circuit conductor (3 phase 3 wire system; no neutral loads are served), may be used as the equipment grounding conductor. *Electrical submersible pump motors in oil and water well service do not require a dedicated equipment grounding conductor, provided the motor controller has ground fault detection. *The well head must be bonded by an approved means to the ground bus at the motor controller or supply transformer. *Armored submarine cables do not require equipment grounding conductors. *Shields and armor of power cable shall be grounded at both ends. Continuity at splices shall be maintained by bonding across the splice. Q How we do grounding of shields and armor of power cables? Ans Shields and armor of power cable shall be grounded at both ends. Continuity at splices shall be maintained by bonding across the splice. Q How we do grounding of the metallic conduit? Ans Metallic conduit shall be grounded at both end points by bonding to a grounding conductor, a grounded metal enclosure, or to a grounded metal cable tray. This may be accomplished: a) With approved grounding clamps connected externally to the conduit or b) Bonding to a grounded enclosure using threaded bushings or using a conduit hub which is approved for grounding purposes or c) Bonding to a grounding conductor using an approved grounding bushing. 27 *Grounding with locknuts is not acceptable. *Isolated sections of rigid metal conduit that are buried at all points at least 0.5 meters below grade are not required to be grounded. *Conduit sleeves used to enclose power cables transitioning from above grade to below grade are required to be grounded only at the above grade end. Q Why should we need to provide the temporary grounding? Ans The temporary grounding is for easy drain or easy way to fault current. Q How is the neutral conductor identify? Ans Neutral conductor is identified by colors white or grey. Q How is an insulated ground conductor identify? Ans An Insulated ground conductor is identified by colors green or green with yellow stripes. Q How we do grounding of metallic cable trays? Ans Metallic cable trays shall be bonded to the local ground grid or ground electrode at both end points ensuring that bonding continuity is met throughout all the racks in the system. Q How many connections are required for ground bus to main ground electrode? Ans Ground busses (in switchgear, switchboards, and motor control centers) shall have two connections to the main ground electrode. Q How electrical manholes should be grounded? Ans Electrical manholes shall be grounded using two ground rods located close to diagonally opposite corners of the manhole. These rods shall be connected to each other, to a ground loop or bus accessible from inside the manhole, and, where applicable, to a minimum 120 mm² (4/0 AWG) grounding conductor that is connected to the local (within 15 m) grounding grid. Q How raised computer floors should be grounded? Ans Raised computer floors shall be grounded by bonding a minimum of two pedestals at opposite corners to the nearest ground bus or grounding electrode. Q How Structural steel supports for process equipment and piping and structural steel columns for buildings should be grounded? 28 Ans Structural steel supports for process equipment and piping and structural steel columns for buildings shall be grounded at least every 25 m (i.e., No part of the base of the structure shall be more than 25 m from a grounded support or column.) with a minimum of two connections at opposite corners of each structure or building. Q How many grounding connection require for equipment operating above 1000 V? Ans Equipment operating above 1000V (MCC, switchboard, switchgear) shall have two connection of grounding electrode. Q How motors, generators and transformers operating at 480V should be grounded? Ans Motors, transformers, and generators operating at a nominal voltage of 480 V shall have a minimum of one connection to a supplementary grounding electrode. Offshore Platform Grounding Q What is the size of copper cable or copper bar for off-shore platform grounding? Ans A copper cable or copper bar minimum size 120 mm² (4/0 AWG) Fence Grounding Q How we do the substation fence (not be PVC coated) grounding? Ans Electrical substation fences shall be grounded as following methods: (1) Substation fences shall not be PVC coated and shall be grounded in a minimum of two locations to the local ground grid or loop. (2) The grounding conductor(s) shall be connected to the substation ground grid at a minimum of four locations spaced equally around the loop. (3) The fence shall be connected to the grounding conductor(s) at intervals not exceeding 15 m. (4) Corner posts and gateposts shall be connected to the grounding conductor. Q How we do the non-substation fence grounding? Ans Non-substation fences shall be grounded as follows: (a) Fences which are within 10 m of an enclosed ground grid or ground loop that is connected to equipment operated at 1000 V or greater shall not be PVC coated and shall be grounded at intervals not exceeding 15 m to the ground grid or loop. (d) All fences within 3 meters of a ground grid or ground electrode shall be bonded at the nearest fence post to the ground grid or ground electrode. 29 (e) Fences that pass under a transmission line operating at 69 kV and above shall not be PVC coated and be grounded at intervals not exceeding 15 m on fence that is within 100 m of the power line. (f) Fences that pass under a transmission line operating at 34.5 kV and above shall not be PVC coated and be grounded at intervals not exceeding 15 m, of the fence within 100 m of the power line. (g) Fences that cross over a ground grid, or conductors that connect two ground grids, shall not be PVC coated and shall have a bond between the grid or conductors and the nearest post. If the crossing area is extensive, the bond is required every 50 m. (h) Fences constructed with concrete posts and PVC coated fencing material are not required to be grounded. Tank Grounding Q How we do grounding of shells of onshore storage tanks? Ans The shells of onshore storage tanks in hydrocarbon service shall be grounded at a minimum of two points on diagonally opposite sides of the tank. Each point shall be bonded to the area ground grid or to a minimum 16 mm x 2.4 m ground rod. Lightening Protection Q Which standards are applied for design and installation of lightening protection system? Ans Lightning protection system design and installation shall be based on NFPA 780 and UL 96A, IEEE 998 Or IEC 61662, IEC 61024-1, and IEC 61024-1-1. Q Which Facilities shall be provided with a lightning protection system? Ans The following Facilities shall be provided with a lightning protection system: a) b) c) d) e) Buildings and occupied structures over 30 m in height High Voltage outdoor substations and switchyards, if area is 3250 m² or greater. If required by NFPA 780. Schools Hospitals Q For lightening protection system components which standard is used? Ans Lightning protection components shall be UL Listed or Labeled in accordance with UL 96 for lightning protection service or have approved equivalent certification. 30 *Protection systems design for petroleum facilities shall comply with API RP 2003. Q Which standard is applied for static electricity grounding? Ans Tank trucks, tank cars, tanks, other large containers, associated filling apparatus, and other equipment which during normal operation can cause accumulation of sufficient static charge to cause an ignition of hydrocarbon vapors in the area shall be bonded and grounded in accordance with API RP 2003. Standard Drawings for Grounding 1) Library Drawing DD-950022 shows recommended details for making grounding connections. 2) Manually operated switches for overhead power lines shall have operating platforms and be grounded as shown on Standard Drawing AA-036572. 3) Grounding Arrangement for Disconnect Switch Structure AA-036572. General questions for electrical and instrumentation SAEP-302 Instructions for Obtaining a Waiver of a Mandatory Saudi Aramco Engineering Requirement IEC 60529 Degrees of Protection Provided by Enclosures NEMA ICS 6 Enclosures for Industrial Controls and Systems NEMA 250 Enclosures for Electrical Equipment NEMA VE 1 - 2002 (Design & specifications of Metal Cable Tray Systems) NEMA VE 2 - 2006 (Cable Tray Installation Guidelines) NFPA 70 - National Electrical Code (NEC) NFPA 72 - National Fire Alarm Code NEMA 250 Enclosures for Electrical Equipment (1000 Volts Maximum) NEMA FG 1 Fiberglass Cable Tray Systems NEMA ICS 6 Enclosures for Industrial Control and Systems NEMA RN 1 Polyvinyl-Chloride (PVC) Externally Coated Galvanized Rigid Steel Conduit and Intermediate Metal Conduit NEMA TC 2 Electrical Polyvinyl Chloride (PVC) Conduit NEMA TC 3 PVC Fittings for Use with Rigid PVC Conduit and Tubing NEMA TC 6 & 8 PVC Plastic Utilities Duct for Underground Installations NEMA TC 9 Fittings for PVC Plastic Utilities Duct for Underground Installation 31 SAES-B-068 Electrical Area Classification SAES-O-113 Security Lighting System ANSI C80.1 Rigid Steel Conduit - Zinc Coated ANSI C80.3 Electrical Metallic Tubing - Zinc Coated NEC 250 NEC 725 NEC 760 Q What is hazardous and non-hazardous area? Ans Hazardous locations are areas where flammable liquids, gases, vapors or combustible dusts exist in sufficient quantities to produce an explosion or fire, otherwise non-hazardous area. Q What is classified area? Ans Hazardous locations are called classified areas, where flammable liquids, gases, vapors or combustible dusts exist in sufficient quantities to produce an explosion or fire. Q What is IP code? (Ingress protection rating or International protection rating) Ans Ingress protection classifies and rates the degree of protection provided against intrusion, dust, accidental contact, and water by mechanical casing and electrical enclosures. Q How we classify the severe corrosive environment? Ans Severe corrosive environments include: a) Offshore locations b) Onshore locations within 1-Km from the shoreline of the Arabian Gulf; and within 3-Km from the shoreline of the Red Sea. Q What is a substation? Ans A substation is a part of an electrical generation, transmission, and distribution system, which transform voltage level from high to low, or the reverse. It contain transformers, and control equipment, i.e. breakers, relays, contactors, disconnecting switches etc. Q What is electrical area classification? Ans Production facilities contain, or may contain, flammable gases and vapors, combustible dust or fibers in normal operations. These can form an explosive environment that is ignitable by hot surfaces, electrical arcs, and sparks. To prevent this from happening, facilities must be classified properly, so that all electrical equipment and systems are properly selected and installed. (SAESB-068) 32 Classes: There are three categories of hazardous materials that have been designated as Class I, Class II, or Class III. The Classes define the type of explosive or ignitable substances which are present in the atmosphere such as: Class I locations are those in which flammable vapors and gases may be present. Class II locations are those in which combustible dust may be found. Class III locations are those which are hazardous because of the presence of easily ignitable fibers or flying. Each of the three Classes, discussed earlier, is further subdivided into two Divisions, Division 1 or Division 2 Divisions: The Division defines the likelihood of the hazardous material being present in a flammable concentration. Division 1: In which ignitable concentrations of hazards exists under normal operation conditions and/or where hazard is caused by frequent maintenance or repair work or frequent equipment failure. Division 2: In which ignitable concentrations of hazards are handled, processed or used, but which are normally in closed containers or closed systems from which they can only escape through accidental rupture or breakdown of such containers or systems Groups: The explosive characteristics of the air mixtures of gases, vapors, or dusts vary with the specific material involved. Materials have been placed in groups based on their ignition temperatures and explosion pressures. Combustible and flammable gases and vapors are divided into four Groups, A, B, C, D. Zone Method of Area Classification Class I, zone 0 Locations (1) In which ignitable concentrations of flammable gases or vapors are present continuously for long periods to time. Class I, zone 1 Locations (1) in which explosive or ignitable concentrations of flammable gases or vapors are likely to exist under normal operating conditions. (2) in which ignitable concentrations of flammable gases or vapors may exist frequently because of repair or maintenance operations or because of leakages. 33 (3) in which equipment is operated or processes are carried on, of such a nature that equipment breakdown or faulty operations could result in the release of ignitable concentrations of flammable gases or vapors and cause simultaneous failure of electrical equipment in a mode to cause the electrical equipment to become a source of ignition. (4) that is adjacent to a Class I, Zone 0 location, from which ignitable concentrations of gases or vapors could be communicated, unless such communication is prevented by adequate positivepressure ventilation from a source of clean air, and effective safeguards against ventilation failure are provided. Class I, zone 2 Locations (1) In which ignitable concentrations of flammable gases or vapors are not likely to occur in normal operation and if they do occur will exist only for a short period (2) In which volatile, flammable liquids, flammable gases, or flammable vapors are handled, processed, or used, but in which the liquids, gases, or vapors are confined within closed containers or a closed system from which they can escape only in case of accidental rupture or breakdown of such containers or system, or as a result of the abnormal operation of equipment with which the liquids or gases are handled, processed, or used. (3) In which ignitable concentrations of flammable gases or vapors normally are prevented by positive mechanical ventilation, but which may become hazardous because of failure or abnormal operation of the ventilation equipment. (4) Which are adjacent to a Class I, Zone 1 location from which ignitable concentrations of flammable gases or vapors could be communicated unless such communication is prevented by adequate positive-pressure ventilation from a source of clean air, and effective safeguards against ventilation failure are provided. Unclassified All areas in the facility that are not Zone 0, Zone 1, or Zone 2 are considered unclassified. Arcing electrical equipment in unclassified areas need not be explosion-proof. General-purpose enclosures are acceptable in these areas. Q What is cable? Ans A group of individually insulated conductors, twisted helically. Q What is cable gland? Ans A gland is a connector designed to attach, secure and seal the end of a power cable to equipment. Q What are types of cable glands? 34 Ans Types of glands a) Metal glands (For Armored cables & Hazardous Area Applications) b) PVC Glands ( For Non Armored and Flexible Cables) Q What is an electrical connector? Ans Electrical connectors join wires/cables to an electrical terminal. Q What are types of electrical connectors? Ans There are many types of electrical connectors a) b) c) d) e) f) crimp-on connectors twist-on (spring pressure type) connectors plug and socket connectors screw connectors blade connectors ring & spade terminals (fork or split ring terminals) Q What are terminal blocks? Ans A device that joins wires or cables to equipment, types are: a) screw type terminal blocks b) spring-clamp terminal blocks c) panel mount terminal blocks Q What is conduit? Types of conduit? Ans An electrical conduit is a tubing system used for routing & protection of electrical wiring. Types are: a) Metal conduit (rigid metal conduit, galvanized rigid metal conduit, intermediate metal conduit, electrical metallic conduit) b) Non-metal conduit (PVC conduit) c) Flexible conduit (flexible metallic conduit, liquid-tight flexible metal conduit, flexible metallic tubing) Q What are cable raceways? Ans Cable raceways are enclosed channels of metallic or plastic materials designed to hold, hide and protect cables. Q What is cable dressing? Ans Neat and clean arrangement of cables is called cable dressing. 35 Q What is cable lacing? Ans Cable lacing is a method of arranging the cables and wires. Q What are cable ties? Ans A cable tie is a type of fastener, for holding together wires or cables. Q What are the types of cable ties? Ans hose-tie, zip-tie, tie-wrap, zap-trap. Q What is fastener? Ans A fastener is a hardware device that mechanically joins or affixes two or more objects. Q What is cable termination? Ans Cable termination is the process of connecting power or control cables up to the final equipment or up-stream circuit breaker. Q What are the conduit fittings? Ans Conduit fitting are accessories used to connect, redirect, extend or terminate a pipe. Q Name some conduit fittings? Ans (a) bushing (b) hubs (c) locknuts (d) couplings (e) reducers (f) nipples (g) conduit union (h) elbows (i) conduit bodied Q What are the conduit supports and their types? Ans A conduit or pipe support is a designed element that transfer the load from the pipe to the supporting structures. There are many types of conduit supports. (1) Clamps (2) Hangers (3) Clips (4) Brackets (5) Straps Q What are the cable tray fittings? Ans Cable tray fittings are. 1) Clamps 2) Hangers 3) splice plates 4) reducer plates 5) blind ends 6) tray cover Q What are the cable tray fasteners? Ans There are many types of cable tray fasteners. 1) Nuts 2) bolts 3) washers Q What is sealing compound? 36 Ans It is a substance used to prevent the passage of gasses, vapors of flames from one portion of the electrical installation to another through conduit. Q What is conduit sealing? Ans Conduit sealing is used at the conduit ends to effectively seal the conduit. Q What is cable tray? How many types? Ans A cable tray is a system used to support insulated cables used for power distribution, control systems or communication. Types are: 1) Ladder type cable tray 2) Perforated bottom & Solid bottom type cable tray Q What is duct bank? Ans A duct bank is a group of conduits, or ducts, which is encased in concrete. Q What is splicing? Splice? Ans The joining of wires in electrical wiring is called splicing. Q What is wire ferrule? Ans A plastic sleeve used on terminated ends of cables, which is imprinted with tag number. Q What is creepage distance? Ans The shortest distance between two conductors. Q What is electrical enclosure/terminal enclosure? Ans An electrical enclosure/terminal enclosure is a cabinet for electrical or electronic equipment to mount/install switches, knobs and displays and to prevent electrical shock to equipment users and protect the contents from the environment. Q What is the junction box? Ans A box containing the connections and junctions and terminal blocks of wiring cables. Q What is distribution board? Ans A distribution board (distribution panel or power panel) is an enclosure which distributes an electrical power into subsidiary circuits, while providing protective fuse or circuit breaker for each circuit. Q What is switch board? 37 Ans An electric switchboard is an enclosure that controls electricity/electric power from one or more sources of supply to several smaller devices of usage. Q What the difference is between switch board and switch rack? Ans Switch board is installed inside and switch rack is installed outside and electrical room, and it is a package of transformer, busbar, and power control panels (DP’s). Q What is bonding box? Ans A box/electrical enclosure in which the bonding cables are terminated is called bonding box. Q What is megger and what is meggering? Ans A Megger meter (Insulation resistance tester) is designed to measure resistance. The measurement of the insulation resistance of cables is called meggering/megger testing. Meggering/Megger Testing is to check that electrical insulation of cables is intact and in good condition. Q What are inspection points for a cable tray installation? Ans Checking of material as per approved spec, size and type, tray installation as per drawings, clearance from top of the tray, proper distance from tray to tray i.e. power/control/signal/low voltage and high voltage, supports are at proper distance, and splice plates are properly installed. Cable tray is free of any debris. Q What are inspection points for field instruments with impulse tubing? Ans Checking of material as per approved material, type and size, installation as per IFC & hook up, check the route to be free of any obstruction, check tube bending and check tube support, fittings. Q What is inspection points for cable laying? Ans Material inspection as per approved material type and size, cable routing as per IFC drawing, installation as per cable schedule (tray, conduit or trench etc.), meggering, dressing and cable tags. Q What is the inspection points for junction box and marshalling cabinets (any electrical/instrument enclosures)? Ans Checking of material is as per approved material, type and size, drain & breathers, installation as per IFC & installation details drawing, hardware type, name plate, tag number and shall be easily accessible for maintenance work. Q What are the inspection points for conduit installation? Q What are the inspection points for power penal/ distribution panel installation? Q What are the inspection points for duct bank installation? Q What are the inspection points for battery enclosure installation/ solar modules/ solar system installation? Q What are the inspection points of lighting fixture/pole? 38 Ans Material inspection as per approved material, type, installation as per IFC drawing and installation details drawing, termination inside fixture, heat resistive sleeve over the cables inside fixture, if armored cable then brass glands if non-armored then pvc glands, shrouds, tag number on cables, color coding of cables, IR, continuity, termination inside fuse box/breaker compartment, degree of lighting fixture. Q What is ITP? Ans Inspection & testing plan provide us details & sequence of inspections for material receiving, installation & pre-commissioning. Q What is the maximum distance between supports for R G S conduit system? Ans Horizontal: 3 mtrs. (10 ft) Vertical: 6 mtrs. (20 ft)> Q What are the material receiving inspection points for classified area/ hazardous area electrical equipment/instruments? Ans Q What is the standard work clearance around high voltage transformers? Ans Minimum ten feet (10') - 3mtrs. As per NEC table -110.31 Q What is red line drawing? Brief its color coding. Ans In case of any change occur to the IFC drawing construction, installation or testing the relevant drawing will be redlined. Following color coding shall be used for this purpose: a) Red: If any addition required in the drawing. b) Green: If any deletion is required from the drawing (c) Blue: If any comment is added in the drawing. Q What are the difference between surveillance, witness and hold point? Ans Surveillance: Work can be executed without client's inspection and it can be inspect some part of them if it required. Witness: Work can be executed without client inspection and then it can be inspected upon the completion of work. Hold Point: Work can't be executed without client inspection. Q What is difference between Hazardous and Non Hazardous area? Ans Hazardous: A hazardous location is an area where a potential for fire or explosion exit due to the presence of flammable gases, liquid or vapors, combustible dusts or fibbers' and flying in sufficient quantities to produce an explosion or ignitable mixture . 39 Non-Hazardous: An area where no risk of presence of any kind of fire or explosion. Q What are different kinds of certification? Ans i) Weather Proof. ii) Dustproof. iii)Water Tight. iv) Explosion Proof. v) Flam Proof. vi) Intrinsic Safety Proof Instrumentation (Electrical Systems for Instrumentation SAES-J-902) Q What is instrument termination? Ans Cable is run from the marshaling cabinet, or some control system to the instrument in the field. The act of attaching the cables to the terminals of the instrument or input output terminal at the transmitting or receiving end is called termination of the instrument. Q For what purpose SAES-J-902 is used? Ans SAES-J-902 is used for electrical systems for instrumentation Q What is the scope of SAES-J-902? Ans This Standard establishes the design criteria for the installation of power and wiring systems for electrical instrumentation. Q Design and installation of power and wiring systems for instrumentation shall be in accordance with which NEC/NFPA-70 Code? Ans Design and installation of power and wiring systems for instrumentation shall be in accordance with National Electrical Code (NEC) Article 725, Article 505. Q Fireproofing of cables in hazardous areas shall be in accordance with which standard? Ans Fireproofing of cables in fire hazardous areas shall be in accordance with SAES-B-006. Q Fire alarm systems shall be installed in accordance with which standard? 40 Ans Fire Alarm systems shall be installed in accordance with NEC Article 760. Q What is Class-I Circuit, Class-II Circuit, and Class-III Circuit? Ans Class 1 Circuit: A circuit complying with National Electrical Code (NEC) Article 725, Part II. Class 2 Circuit: A circuit that complies with National Electrical Code (NEC) Article 725, Part III. Class 3 Circuit: A circuit that complies with National Electrical Code (NEC) Article 725, Part III. Q What is Data link? Ans An information channel used for connecting data processing equipment to any input, output, display device, or other data processing equipment. Q What is drain wire? Ans In a cable, the non-insulated wire in intimate contact with a shield to provide for termination of the shield to a ground point. Q What is home run cable? Ans A cable, typically multi-pair/triad, extending between the field junction boxes and marshaling cabinets in control or PIB buildings. Q Electrical and electronic equipment in hazardous area shall be according to which standard? Electrical and electronic equipment in hazardous area shall meet which requirements? Ans Electrical and electronic equipment in hazardous areas shall meet listing/certification requirements specified in NEC i.e. IECEx & EEx d Q Where the intrinsically safe systems shall use? Ans Intrinsically safe systems shall only be used in Zone 0 hazardous areas? When the vendor's standard product offering is supplied as intrinsically safe. Q What are the intrinsically safe systems? Ans Intrinsically safe systems are those equipments which are manufactured to be safe to use in hazardous area. Q What kind of cable tie shall be used in field (outdoor) for instrumentation? Ans All cable ties shall be nylon coated 316 stainless steel. Q What kind of cable tie shall be used in indoor for instrumentation? 41 Ans All cable ties shall be weather resistant nylon with a stainless steel barb. Conduit and Cable Sealing Q Conduit and cable sealing shall be installed with which standard? Ans According to NEC article 505 Q What type of cable glands shall be used on instruments and enclosures in hazardous and nonhazardous areas? Ans Certified flameproof (Type “d”) cable glands using a compound barrier seal shall be used on all instruments and enclosures located in hazardous areas. Certified Flameproof (Type “d”) cable glands shall be used on all instruments and enclosures including those located in non-hazardous areas. Enclosures Q Enclosure for instrumentation in outdoor & plant area shall be of which type? Ans For non-hazardous outdoor/plant area should be NEMA type 4, Type IP 65 (in accordance with IEC 60529, NEMA ICS 6 and NEMA 250). In severe corrosive areas shall be NEMA type 4X, Type IP 66 (in accordance with IEC 60529). Q What are the construction requirements for field junction box? What are the installation requirements for field junction box? Ans The field junction box shall be a single door NEMA Type 4X, Type IP 66 (IEC 60529). The box construction shall meet the following requirements: (1) (2) (3) (4) (5) (6) (7) (8) Type 316 stainless steel body, door and hardware. Continuously welded seams, finished smooth. Stainless steel hinge. Stainless steel captive clamps. Data pocket on inside of door. Removable door. Ground stud for terminating ground wire. External mounting brackets. Q How junction box shall be installed? Ans All field junction boxes shall be mounted vertically, i.e., the door shall open from left-toright or from right-to-left. 42 Q For what volume of instrument enclosures and junction boxes the breather and drain fittings shall be provided and of what type? Ans Instrument enclosures and junction boxes having an internal volume exceeding 2,000 cm³ shall be provided with Type 300 Series stainless steel breather and drain fittings. Conduit, Conduit Fittings and Supports Q What is the distance between the field device and a conduit outlet box (GUAT)? Ans A conduit outlet box shall be installed within 18” of the field device. Q How we attach a conduit to the instrument? Ans A flexible conduit shall be used at the instrument end of the conduit to provide isolation from vibration, protection against the thermal expansion and for ease of maintenance. Q For CLASS I ZONE 1 location which fitting shall be use? Ans For CLASS I ZONE 1, flexible fittings listed for the area shall be used. Q For CLASS I ZONE 2 which type of metal conduit shall be used at instrument end? Ans For CLASS I ZONE 2 locations and unclassified areas the flexible conduit shall be liquid tight flexible metal conduit shall have a sunlight resistant cover which resist oil and chemical breakdown and shall be rated for temperatures ≥ 90° C. Cable Trays Q According to which standard, the cable trays shall be designed and manufactured? Ans Cable tray shall be designed, manufactured, and marked in accordance with NEMA VE 1 2002. Q Installation of instrumentation cable tray shall be as per which standard? Ans Cable tray installation shall be as per NEMA VE 2-2006 Q What type of cable tray is used for homerun cables? Ans Ladder type cable tray. Q What type of cable tray is used for instrument cables from field instruments to junction boxes? Ans Channel cable tray Q What type of material is used for manufacturing of cable trays for instrument cables? Ans Cable tray material shall be copper-free aluminum. 43 Q What is the distance between the consecutive rungs of ladder cable tray? Ans The distance between the consecutive rungs of ladder cable tray shall not exceed 9”. Q What are the components of the cable tray? Ans The cable tray system components are clamps, hangers, brackets, spice plates, reducer plates, blind ends, connectors and grounding straps. Q In new grass project, how much spare space in cable trays is required for the future? Ans 20% free space. Q What type of material/material grade is used for fasteners/hardware for cable trays in indoor, outdoor and corrosive environments? Ans For indoor/outdoor areas, all fasteners/hardware shall be 304SS and for corrosive area it shall be 316SS. Q What type of cable trays should use between field instruments and junction boxes? Ans Cable tray for armored cables between field instruments and junction boxes shall be ventilated bottom, channel cable tray. Q Name the cable trays which are used in electrical system for instrumentation Ans 1) Ladder Cable Tray, 2) Channel Cable Tray, 3) Perforated Cable Tray Q What is the width and depth of the channel tray? Ans The channel cable tray width shall be 3’’, 4”, or 6” and the minimum loading depth of 1 ¼”. *The channel cable tray system shall be installed with flanged covers. *Cable tray fill shall comply with NEC Article 392. Connections at Field Instruments and Junction Boxes Q What kind of terminal blocks (T.B) shall use for field instruments? Ans Screw type terminal blocks. *Wire nut and spring type terminal blocks shall not be used. *The outer jacket of shielded twisted single pair/triad cables shall be left intact up to the point of termination. Drain wires and mylar shields on shielded cables shall be cut and insulated with heat shrink sleeve at the field instrument unless otherwise specified by the 44 instrument manufacturer. For armored cables, the "outer jacket" is the jacket covering the pair or triad; not the jacket covering the armor. *All instrument wiring shall be routed to field junction boxes. Conduit and cable entries to field junction boxes shall be through the bottom. Top entry is allowable provided a drain seal is installed on the conduit within 18" of the enclosure. Side entry (within six inches of the bottom) shall be permitted only when space limitations dictate. The number of conduit entries shall be kept to a minimum. All unused entry ports shall be fitted with approved plugs. *Conduit entries to junction boxes shall be through gasketed hubs, except in explosionproof installations where the connection shall be through threaded connections. *In severe corrosive environments, cable glands shall be protected against corrosion, either by a heat shrink sleeve, anti-corrosion tape or PVC shroud. Gasket materials shall be oil resistant. *Twisted, multi-pair/triad cables shall be cut to the appropriate length to minimize looping and flexing of the cable within the junction box. *For individually shielded twisted multi-pair/triad cables each pair/triad shall be heat shrink sleeve insulated from the cable-jacket-end up to the point-of-termination to keep the foil shielding intact and free from accidental grounds. The shield drain wire shall be insulated from foil end to terminal. Approximately, two inches of heat shrink tubing shall be applied over the jacket end. *The terminals shall be mounted on vertical DIN rails (i.e., horizontal DIN rails are not allowed). *Twenty percent (20%) unused DIN rail length shall be provided in field junction boxes. Power Supply *Where instrument-circuit power distribution panels are used, each panel shall be dedicated to a single voltage level. These panels shall not provide power to noninstrumentation circuits. Distribution panels shall be furnished with a minimum of 20% spare circuit breakers. *Redundant power supplies feeding process automation systems, emergency shutdown systems, metering systems, auxiliary systems or field instrumentation shall be fed from separate distribution panels. *Power wiring for field instruments, two-wire analog transmission loops, field switch contacts, etc., shall be individually fused and provided with a means of disconnecting the 45 power without disturbing terminated wiring. Visual indication of a blown fuse condition shall be provided. *Low level signals are defined as Millivolt, Microamp, Pulse and Frequency Signals under 1 Volt. *Where multiple online DC power supplies are connected to a single power bus, diode auctioneering shall be used to ensure bump less transfer in the event of a single power supply failure. *Where multiple DC power supplies are an integral part of a manufacturer's standard product, the manufacturer's standard method of load sharing shall apply. *UPS power and utility power shall not share the same cable or be routed in the same conduit. *UPS systems powering critical instrumentation shall consist of redundant UPS units. *Critical instrument systems are defined as systems which, upon loss of their supply power, would cause: 1) process failure in a non-failsafe mode, 2) area or plant shutdowns, 3) loss of custody transfer metering or accounting systems, or 4) other adverse facility operating scenarios. *The time during which the battery bank shall supply power to the instrumentation system shall depend on the application, but not be less than 30 minutes. *Backup power supply shall be required for instrumentation systems containing volatile memory. For all such systems, the manufacturers' recommendations shall be followed. Q What is the function of diode auctioneering? And where is it used? Ans Diode auctioneering shall be used to ensure bump less transfer in the event of a single power supply failure. Signal/Control Wiring *Splices are not permitted in wiring. When wiring must be extended, connections shall be made via terminal blocks in a junction box installed above ground. *Twist-on wire nut connectors shall not be used for making any electrical instrumentation terminations or wiring connections. Q What are the wire and cable minimum size requirements for field instrument to field junction box in instrument circuits? Ans The minimum wire size for single pair cable from field instrument to field junction box shall be 16 AWG/300V, 600V. 46 Q What are the wire and cable minimum size requirements for field junction box to marshalling cabinet in instrument circuits? Ans The minimum size for multi-pair/triad cable from field junction box to marshalling cabinet shall be 18 AWG/300V, 600V. *The minimum size for multi-pair/triad cable should be 18 AWG. The minimum wire size for single pair cable shall be 16 AWG. *Type ITC cable shall not be installed on either non-power limited circuits or powered limited circuits operating at more than 150 volts or more than 5 amperes. *Differences in the manufacturer recommended cable and these requirements shall be resolved with Instrumentation Unit/PID/P&CSD. Q How protection is provided against reverse EMF for inductive loads? Ans Protection against reverse EMF shall be provided for inductive loads such as relays, solenoids, etc. This may be accomplished by installing a diode across the coil for DC loads or a metal oxide varistor (MOV) across the coil for AC inductive loads. *If a discrete loop length exceeds 1000 feet, 120 VAC signal shall not be used due to potential capacitive or inductive coupling. In such cases, DC voltage shall be used. *Cables used in Class 1, Class 2 and Class 3 circuits shall meet the requirements of Article 725 of the National Electrical Code (NEC). Q What are the special cables? Ans 1) Thermocouple Extension Cables 2) Data links *All in plant process automation networks shall be redundant and shall be routed in separate cables. The primary cable shall follow a different route from the backup cable. Primary and backup data link cables shall preferentially enter cabinets or consoles from opposite sides. *Data link cables shall not be routed in the same conduit, duct, or tray with other instrument cables. *Fiber Optic data link Cables may be routed with other instrumentation cables – in existing trays or ducts with prior approval of the Supervisor, Instrumentation Unit/PID/Proponent & CSD. Q How we do color coding for power and signal wiring? Ans Power and signal wiring shall be color coded as follows: 47 AC Supply DC Supply Signal Pair Signal Triad Phase Neutral Ground Positive Negative Positive Negative Positive Negative Third Wire Black White Green or green with yellow tracer Red or red sleeve over any color except green Black or black sleeve over any color except green Black White Black White Red Routing Q How the instrument cable is laid above ground from the field instrument to the field junction box? Ans Single twisted pair/triad cables shall be installed in RGS or PVC Coated RGS conduits from the field instruments to the field junction boxes and armored instrumentation cable shall be routed on a cable tray. Q How an armored cable is laid above ground from the field junction box to marshaling cabinets? Ans Cables between field junction boxes and marshaling cabinets may be routed in conduits, on trays, or direct buried. Q What is the marshaling cabinet? Ans A marshalling cabinet contains main terminal strips and wire terminations. Q How we use armored cables for instrumentation homerun application? Ans The use of armored cables for homerun application is not recommended. However, if they are used, the cables shall be terminated using glands at both ends (Certified flameproof (Type ‘d’) cable glands using a compound barrier seal shall be used in hazardous areas. Certified Flameproof (Type “d”) cable glands shall use in non-hazardous areas). In addition, the armor shall be grounded at both ends. *Control room cabling/wiring must conform to NEC Articles 725. *Wiring for millivolt, microamp, pulse, and frequency signals under one Volt such as thermocouples, vibration elements, load cells, thermistor elements and transmitters with pulse outputs may be directly connected to the I/O unless. *Each cable or group of cables leaving a specific junction box and carrying similar signals shall contain a minimum of 20% spare of the used pairs or triads. 48 *Emergency shutdown system (ESD) wiring shall have dedicated cabling, junction boxes and marshaling cabinets. *For offshore platforms only, ESD system wiring may be terminated in the same junction box as general instrumentation wiring. Terminals shall be segregated and clearly labeled. *Wiring for intrinsically safe (IS) systems shall be segregated and installed in dedicated conduit or cable tray and terminated in dedicated junction boxes. Q How cables are laid above ground from the marshaling cabinets to Control Room for Instrumentation and Control Systems? Ans Cables between marshaling cabinets to Control Room Instrumentation and Control Systems may be routed in conduits, on trays, or direct buried. Q How cables are laid under ground beneath raised computer type floors in control rooms? Ans Instrumentation cables installed beneath raised computer-type floors in control rooms shall be placed in ladder cable tray or trough or solid bottom cable tray. Cable trays beneath raised floor shall be adequately identified using suitable permanent tag plates. These tag plates shall be installed at each end, tee connection and at three-meter intervals. The tag plates shall be located so that it is clearly visible. The tag plates shall contain, as a minimum, the noise susceptibility level of the circuits enclosed source, and the destination. *Multi-pair/triad cable shall not be used to route more than one signal type. In addition, junction boxes shall be segregated based on signal type (e.g., each signal type shall have its dedicated junction box). Signal Segregation, Separation and Noise Reduction Q How the signal wiring is categorized with NSLs? Ans Signal wiring (instrumentation cable) shall be categorized with noise susceptibility levels (NSL) of ‘1’ or ‘2.’ Level 1 – High to Medium Susceptibility: Analog signals of less than 50 V and discrete instrument signals of less than 30 V. Level 2 – Low Susceptibility: Analog signals greater than 50 V and Switching signals greater than 30 V, and 120-240 AC feeders less than 20 amps. Level 3 – Power: AC and DC buses of 0-1000 V with currents of 20-800 amps. 49 * Multi-pair/triad cable shall not be used to route more than one signal type. In addition, junction boxes shall be segregated based on signal type (e.g., each signal type shall have its dedicated junction box). * Cables with the same noise susceptibility level may be grouped in trays and conduit (e.g., all level-1 cables may be routed in one cable tray). *When routing instrumentation and control signal cabling (level 1 or 2) near sources of strong electromagnetic fields, such as large transformers, motors and generators, as greater than 100 kVA, a minimum spacing of 2 meters shall be maintained between the cables and the devices. *When routing Instrumentation cables (level 1 & level 2) near power cables carrying higher loads than the limits specified in level 3, the separation distances shall be 1.5 meters as a minimum. Q What is the minimum separation between power and instrumentation cables? Ans Power cables and instrumentation cables have minimum separation between given blow: 1) Conduit to Conduit Spacing, millimeters (inches) NSL * Level 1 Level 2 Level 3 Level 1 0 (0) 75 (3) 300 (12) Level 2 75 (3) 0 (0) 150 (6) Level 3 300 (12) 150 (6) 0 (0) 2) Tray to Conduit Spacing, millimeters (inches) NSL * Level 1 Level 2 Level 3 Level 1 0 (0) 100 (4) 450 (18) Level 2 100 (4) 0 (0) 150 (6) Level 3 450 (18) 150 (6) 0 (0) 3) Tray to Tray Spacing, millimeters (inches) NSL * Level 1 Level 2 Level 3 Level 1 Level 2 Level 3 0 (0) 150 (6) 650 (26) 150 (6) 0 (0) 200 (8) 650 (26) 200 (8) 0 (0) *Twisting and shielding of instrumentation wiring shall also be used as detailed below to minimize the noise impact on instrumentation signals. 50 Q Why we use shielded cables? What is the purpose? Ans Shielded cables shall be used to reduce electrostatic noise. Q How we do grounding in shielded cables? Ans The shield shall be grounded at one point only, typically at the marshaling cabinet in the control room or process interface building. *For individually shielded twisted multi-pair/triad cables each pair/triad shall be heat shrink sleeve insulated from the cable-jacket-end up to the point-of-termination to keep the foil shielding intact and free from accidental grounds. The shield drain wire shall be insulated from foil end to terminal. Approximately, two inches of heat shrink tubing shall be applied over the jacket end. *Except for coaxial cables, instrument cable shields shall never be used or considered as signal conductors. Q Why we do twisting of paired or triads of instrument cable? What is the purpose of twisted paired/triads cables? Ans Twisted pairs/triads shall be used to reduce electromagnetic noise. Termination Q What type of terminal blocks are used for termination of instrument cables? Ans Terminal blocks shall be screw type and channel (rail) mounted, strip type, with tubular box clamp connector and compression bar or yoke for wire termination. As a minimum, the thickness of the terminals shall be 5 mm or higher. Multi-deck and spring type terminal blocks are not acceptable. Q What is instrument termination? Ans When installing instrumentation, cable is run from the marshaling cabinet, or some control system to the instrument in the field. The act of attaching the cables to the actual electrical terminals of the instrument or input output terminal at the Transmitting or receiving end is called Terminating the instrument, i.e. instrument termination. Usually the instrument loop is installed in stages, where the instrument is physically mounted in the field, cable is pulled and run in cable trays or buried in trenches, and the ends of the cables are terminated. Q What type of terminal blocks are used for termination of instrumentation cables? Ans Screw-type terminals are provided on field instruments or other electrical devices, solder less crimp/compression connectors shall be used for connecting stranded copper conductors. 51 *The thickness of the terminals shall be 5 mm or higher. *Multi-deck and spring type terminal blocks are not acceptable. Connections at Field Instruments: (1) All connections at the field instrument shall be made on screw type terminal blocks. Wire nuts and spring type terminals shall not be used. Instruments with integral terminal blocks shall be connected directly to the field cable. (2) If the instrument is fitted with factory sealed fly leads then they shall be connected to a screw type terminal block installed in a GUA conduit fitting. The outer jacket of shielded twisted single pair/triad cables shall be left intact up to the point of termination. Drain wires and mylar shields on shielded cables shall be cut and insulated with heat shrink sleeve at the field instrument unless otherwise specified by the instrument manufacturer. Connections at Field Junction Boxes Conduit and cable entries to field junction boxes shall be through the bottom. Top entry is allowable provided a drain seal is installed on the conduit within 18" of the enclosure. Side entry (within six inches of the bottom) shall be permitted only when space limitations dictate. The number of conduit entries shall be kept to a minimum. All unused entry ports shall be fitted with approved plugs. In severe corrosive environments, cable glands shall be protected against corrosion, either by a heat shrink sleeve, anti-corrosion tape or PVC shroud with anti-corrosion compound. Gasket materials shall be oil resistant. Q What are the terminals/terminal blocks accessories? Ans Terminals and terminal block accessories are end brackets, DIN rail mounting brackets for electrical insulation, bus-bar support blocks, etc. Q What should be material specifications of terminal blocks accessories? Ans Shall be made of fire retardant, halogen free, high strength material such as polyamide or equivalent in accordance with UL 94, V0. Brittle materials such as melamine shall not be used. *Wires terminated on these terminal blocks shall not have the bare ends coated with or dipped in solder (“tinned”). However, termination of wiring that has individual strands of the copper conductor tinned during manufacture is acceptable. *No more than two bare wire ends shall be connected to each side of a single terminal block. Q What type of wire ducts & gutters are used and what is the purpose? 52 Ans Plastic wire ducts with removable covers shall be used in control panels and marshaling cabinets. The purpose is to provide a means of routing and organizing wiring between terminal blocks and instrument racks or panels for cable termination. Q How much distance should be between the wire duct and the terminal strips? Ans A minimum of 50 mm (two inches) shall be maintained between the duct and terminal strips to permit wire markers to be completely presented without being obscured by the duct. Identification Q What is the wire tagging method? How we do wire tagging? Ans All wiring shall be tagged at each end. Each wire tag shall have two labels. The first label (closest to the end of the wire) shall identify the terminal number to which the wire is physically connected. The other label shall be the terminal number of the connection of the opposite end of the wire. Q How we do wire tagging of instrument cables? What is the wire tagging method for instrument cables? Ans Where wires terminate on instrument or device terminals, the instrument tag number and terminal designation (+) or (-), shall be used in place of terminal strip identification. *Wire tag information shall be permanently marked in block alpha numeric or typed on tubular, heat-shrinkable, slip-on sleeves. Wrap-around, Snap-on or self-adhesive wire markers shall not be used. Handwritten wire tags are not acceptable. Q What is cable tagging in instrumentation and how it shall be done? Ans All cables shall be tagged, at each end, with a cable-tag. Homerun cables shall be tagged with the assigned “IC” cable number. Cable-tags outside junction boxes and marshalling cabinets shall be 316 SS with permanently marked alphanumeric characters. The cable-tag shall be securely attached to the cable with stainless-steel cable ties. Where cable tags are required inside junction boxes or marshalling cabinets shall be weather resistant, high quality plastic cable tags secured using cable ties. Q How terminal blocks are identified by tagging? Ans Each row of terminals shall be uniquely identified alphanumerically, e.g., TS-101, TS-102, etc. 53 The terminals in each row shall be sequentially numbered starting at number one (1). Grounding Q Which two grounding systems are required for instrumentation systems? Ans Two grounding systems are required for instrumentation systems: a) Safety Ground for personnel safety. b) Instrumentation DC & Shield Ground. *Both safety ground and instrumentation circuit ground must conform to NEC, Article 250. Q What size of cable is used for grounding systems for instrumentation? Ans Two copper conductors, 25 mm² minimum Q After how many time Instruments need to be calibrate? Ans After 6 month. Q What is loop check? Ans Loop check is a test of checking/testing the continuity of wires or cables. Q What are the contents of loop folder? What is the Loop Folder and what is the purpose of Loop folder and which documents it contains? Ans Loop folder consists of: (1) Punch list Form (2) Loop Check Cover Sheet (3) Instrument installation inspection report/form (4) Calibration Certificates (5) Data sheet (ISS) (6) Instrument Block Diagram (7) Instrument Interconnection Diagram (8) Junction Box Connection Wiring Drawing (9) ILD (instrument loop diagram) (10) P&ID (piping and instrument diagram) (11) Hook up drawing (12) Instrument Points and Line (IPL) (13) Instrument cable meggering report and continuity test report (14) Instrument loop acceptance sheet (15) Cable Conduit Schedule Q What is instrument termination? What is instrument commissioning? 54 Ans The instrument terminated, calibrated and tested to be functioning at the control system, the instrument is said to be commissioned, i.e. ready for service. That is called commissioning. Q (1) How we install an instrument like MOV, PIT, and flow meter? (2) What is the installation procedure of an instrument? (3) Which things are required for the installation of an instrument? (4) What will we do before installing an instrument? Ans (1) Data sheets and calibration sheets (2) Hook up drawing, location drawing (3) P&ID Electrical (Wiring Methods and Materials > SAES-P-104) Q SAES-P-104 is used for what purpose? Ans This Standard prescribes mandatory requirements for the design and installation of insulated power and control wiring and cable systems. Q SAES-P-104 is used for what? Ans SAES-P-104 is used for “Wiring Methods and Materials”. Q Define control wiring and instrumentation wiring? Ans Control wiring: Control wiring is wiring used to power up the electrical control devices, such as pushbuttons, electromechanical relays, meters, transducers, etc. Instrumentation/Signal wiring: Wiring connected on one or both sides to instruments, distributed control systems, etc is called instrumentation wiring. *Signal cables carry signals of 24 VDC and 4-20mA. Q Which standard code is used for the design and installation of wiring and cable systems? Ans Design and installation of wiring and cable systems shall be in accordance with Saudi Building Code, ANSI/NFPA 70, NEC 725. Wire and Cable 55 Q What type of conductor material is used for wires and cables? Ans Wires and cables shall have copper conductors. Aluminum conductors are permitted to be used in community areas for sizes 25 mm² or larger. Q What are the low voltage Jacketed wire and cable specifications, according to SAES-P-104? Which standards shall comply low voltage jacketed cables? Ans Low voltage jacketed cables shall comply with NEC or IEC 60502-1 and shall conform to UL standards. Q What are the low voltage unjacketed wire and cable specifications, according to SAES-P-104? Which standards shall comply low voltage unjacketed cables? Ans Low voltage unjacketed insulated wires shall comply with NEC, IEC 60227 or SASO 55 and shall conform to UL standards. *Low voltage unjacketed insulated wires shall not be used in cable trays, duct banks involving manholes, or direct burial applications. Q What are the medium voltage power cables specifications, according to SAES-P-104? Ans Medium voltage power cables, rated 5 kV to 35 kV, shall comply with 15-SAMSS-502, and shall be either IEC or ICEA & AEIC type cables. Q What are the high voltage power cables (rated 69 KV high voltage) specifications, according to SAES-P-104? The power cables rated 69KV and above should comply with which standard? Ans According to SAES-P-104, Power cables rated 69 kV and above, with solid dielectric insulation, shall comply with either AEIC CS6 (69 kV EPR insulated cable) or AEIC CS9 (69 kV and above XLPE insulated cable). Q The submarine power cables rated 5KV through 115 KV should comply with which standard? Ans According to SAES-P-104, Submarine power cables, 5 kV to 115 kV, shall comply with 15-SAMSS503. Q What type of cables should use in areas Class I, Division 2 and Zone 2 (hazardous) locations? Ans Power cables meeting the requirements of NEC Article 501 are allowed. *Power and control conductors shall be stranded * Stranded power, control and grounding conductors shall have stranding in accordance with ASTM B8 Class B or C, or ASTM B496, or IEC 60228 Class 2. Q How much thickness of the insulation required for power cables for high voltage? 56 Ans According to SAES-P-104, insulation thickness should be 16 mm to 20 mm. Q What is the minimum size of control conductor? Ans The minimum size of control conductor for 600V and below shall be 2.5 mm2 (14 AWG) Q What is the minimum size of power conductor? Ans The minimum size of power conductor for 600V and below shall be 4 mm2 (12 AWG) Q What is the maximum size of power conductors rated 69KV and below Ans Maximum size of conductors rated below 69 kV shall be 500 mm² or 1,000 kcmils. Q According to which standards the armored cable shall be manufactured, as per SAES-P-104? What are the standard requirements for armored cable? Ans Armored cable shall be manufactured to IEC 60502-1 or IEC 60502-2, and shall have galvanized steel wire armor or galvanized steel tape armor under the jacket. Q What kind of cables used for security lighting (perimeter and area lighting)? Ans Cables used for security lighting (perimeter and area lighting) shall be armored or metal clad. Q What is the maximum number of field splices permitted in any one circuit for new installations of cables rated above 1000 V? Ans Splicing of conductors shall be kept to a minimum. The maximum number that made necessary by the use of the standard size reels with full length cables, but in case of accidental damage of the cable during installation, one additional splice is permitted with the concurrence of the cable proponent. *For installation and application purposes, armored cable manufactured to IEC 60502-1 or IEC 60502-2 shall be considered equivalent to type MC (metal clad) cable. *Type MC Cable and armored cable shall be permitted to be installed and exposed above ground where it is not subject to damage by vehicular traffic or similar hazards. Q What type of cables are used for underground installations? Ans Type MC Cable and armored cable shall be used for underground installations. *Un-armored type cables shall be used for cable tray and conduit systems installations. *Fireproofing of cables shall be in accordance with SAES-B-006 (onshore facilities) or SAESB-009 (offshore facilities). Q What is the hazard location in area classification? 57 Ans Hazardous locations are: CLASS I, ZONE 0 & CLASS I, ZONE 1 Connections and Terminations *Compression (crimped) type connectors shall be used for splicing and terminating stranded conductors. *The use of solder lugs is prohibited. *Compression terminal connectors for 4/0 and larger conductors shall be two hole NEMA design. *All compression connectors shall be tinned copper. Q What type of connectors are used for lighting and receptacle circuits? Ans Spring pressure type twist-on connectors, and pressure set screw connectors with insulating caps are permitted for lighting and receptacle circuits in non-hazardous locations, and in nonindustrial applications. Q What type of connectors are used for control wiring? Ans Insulated ring tongue, locking fork tongue, flanged fork tongue and pin type compression terminals shall be used for control wiring. *All threaded cable fittings including terminators (glands) for metric size cables shall have tapered (NPT) threads in accordance with ANSI/ASME B1.20.1. Q What is the cable identification method for electrical cables? Ans Identification of cables shall include the cable number and destination. Individual control wires shall be identified by two labels at each end. The first label (closest to the end of the wire) shall identify the number of the terminal to which the wire is connected. The other label shall identify the terminal of the opposite end of the wire. Q What are marking methods for wires for terminations? Ans Wires at termination points shall be identified by the use of: (a) Permanently imprinted or embossed wire markers of the heat-shrinkable or slip-on type. Slip-on wire markers shall be sufficiently tight so that they will not slip unintentionally. (b) Cables may be identified by special plastic or non-corrosive metal labels held with cable ties, or similar methods. (c) Colored insulating tapes may be used for phase identification of power circuit conductors. 58 * Wrap-around, rigid Snap-on, or adhesive type markers are not permitted for wire or cable identification. Q How to identify the individual phases of power cable circuit? Ans SAES-P-104 describe that, individual phases of power circuit shall be identified by the color-coding cable (Red, Yellow, Blue). Q What is creepage distance? How much creepage distance for 13.8 KV outdoor terminations? Ans The clearance between the terminated ends of phase to the ground is called creepage distance. For 13.8 kV outdoor terminations, each phase shall have a creepage distance of 552 mm to ground minimum. Q What is the creepage distance for medium and high voltage terminations installed outdoor? Ans Medium and high voltage terminations (operating at 2.4 kV and above) installed outdoors shall have a minimum creepage distance to ground of 40 mm per kV line-to-line nominal system voltage. Q What is the creepage distance for medium and high voltage terminations installed indoor? Ans Medium and high voltage terminations installed indoors shall have a minimum creepage distance to ground of 25 mm per kV line-to-line nominal system voltage. Q What is the minimum creepage distance for MV/HV terminations? Ans For outdoors installed is 40 mm per KVL-L and indoors installed is 25 mm per KVL-L. Q According to SAES-P-104, Cable glands should be in accordance with? Ans Cable glands (for hazardous and non-hazardous locations) shall be in accordance with BS 6121 or BS 50262. Enclosures Q According to SAES-P-104, which type of terminal/ equipment enclosure shall be used in outdoor plant areas? Ans In outdoor plant areas, terminal/equipment enclosures shall be: (a) NEMA Type 4 (b) NEMA Type 3 (c) IEC 60529, Type IP54 or better. Q According to SAES-P-104, which type of terminal/equipment enclosure shall be used in outdoor plant areas in severe corrosive environment? 59 Ans In outdoor plant and other industrial areas located in severe corrosive environments, equipment and terminal enclosures shall be: (a) NEMA Type 4X (b) NEMA Type 4 or 3 (c) IEC 60529, Type IP 54 or better Q According to SAES-P-104, what type of enclosure material shall be? Ans Enclosure materials shall be a) b) c) d) Aluminum (Copper Free -0.4%) Plastic (Fiberglass) Stainless steel (Type 304 or better) Galvanized/Painted/Coated carbon steel in indoor air conditioned area. Q According to SAES-P-104, which equipment/terminal enclosure shall be used in outdoor nonindustrial area? Ans In outdoor non-industrial areas, equipment and terminal enclosures shall be: (a) NEMA Type 3R, 3 or 4 (b) IEC 60529 Type IP34 or better Q According to SAES-P-104, which type of enclosure shall be used for dry-type transformers in outdoor locations? Ans In outdoor locations, enclosures for small dry-type transformers shall be totally enclosed NEMA Type 3R. *In hazardous (classified) locations, enclosures that are required to be approved for Class I locations by NEC Article 501 or 505. Q What type of breathers and drain fitting shall have in enclosures and junction boxes? Ans Enclosures and junction boxes having an internal volume exceeding 2,000 cm³ shall be provided with Type 300 Series stainless steel breather and drain fittings. Q AS per SAES-P-104, what is the size of drain hole? Ans SAES-P-104, says thin wall enclosure and junction box may be drill by 5mm hole in the bottom. Conduit, Conduit Fittings and Supports Q What are the specifications of direct buried PVC conduit, as per SAES-P104? 60 Ans Direct buried conduit shall be PVC conduit Type DB-120 per NEMA TC 6 & 8 or Type EPC-40-PVC per NEMA TC 2. Q What are the specifications of concrete encased underground conduit as per SAES-P104? Ans Concrete encased conduit shall be PVC conduit Type EB-35 or DB-120 per NEMA TC 6 & 8 or Type EPC-40-PVC per NEMA TC 2. Q What are the specifications of direct buried conduit for corrosive area, as per SAES-P104? Ans Direct buried conduit in class I division I (Classified area) shall be PVC coated RGS conduit. Q What are the specifications of aboveground/exposed conduit, as per SAES-P104? Ans Conduit installed exposed, above ground in outdoor, industrial facilities shall be rigid steel per ANSI C80.1, and in addition it shall be galvanized. Q What are the specifications of aboveground conduit in severe corrosive environments as per SAES-P104? Ans Conduit above ground in severe corrosive environments shall be rigid steel per ANSI C80.1, and it shall be galvanized, in addition, it shall be factory PVC coated (1 mm) per NEMA RN 1. *Where flexibility is required, liquid-tight flexible metal conduit (non-hazardous and Class I, Division 2 and Zone 2 locations) or explosion-proof neoprene coated or PVC coated flexible couplings (in Class I, Division 1 and Zone 1 locations) shall be used. *EMT (electrical metallic tubing) is acceptable only for indoor non-hazardous location. EMT shall comply with the requirements of ANSI C80.3. *Intermediate metal conduit (IMC) is prohibited. Q What is the minimum size of conduit shall be, as per SAES-P-104? Ans The minimum conduit size shall be ¾ inch or equivalent. *In non-industrial areas and for instrumentation wiring the minimum size conduit shall be ½ inch. *Conduit and threaded conduit fittings shall have tapered (NPT) threads in accordance with ANSI/ASME B1.20.1. *Field cut conduit threads shall be coated with a zinc rich protective coating. Q What type of conduit fittings are used for outdoor rigid steel conduit and liquid-tight flexible metal conduit as per SAES-P-104? 61 Ans Conduit fittings for outdoor rigid steel conduit and liquid-tight flexible metal conduit shall be of steel, iron, either hot-dip galvanized, or zinc electroplated. Q What type of conduit fittings are used for aboveground rigid steel conduit and liquid-tight flexible metal conduit, as per SAES-P-104? Ans Conduit fittings for rigid steel conduit and liquid-tight flexible metal conduit used above ground in severe corrosive environments shall be steel, iron, either hot-dip galvanized, or zinc electroplated and in addition, shall be factory-coating with PVC or field coating prior to installation. *Conduit fittings for direct buried PVC coated rigid steel conduit shall be factory PVC coated. *Threads of plugs, junction boxes and other fittings shall be lightly lubricated with a rust preventive grease before assembly. *The use of conduit unions with underground conduit should be avoided. If this is not possible, conduit unions must be protected with heat-shrinkable sleeves or wrap-arounds. Q As per SAES-P-104, pvc conduit fittings shall be in accordance with which standard? Ans Fittings for NEMA TC 6 & 8 Type PVC conduit shall be in accordance with NEMA TC 9. Fittings for NEMA TC 2 Type PVC conduit shall be in accordance with NEMA TC 3. Q What type of supports are used to support conduits, cable trays, enclosures, lighting fixtures and other electrical equipment? Ans Channel erector system components used to support conduits, cable trays, enclosures, lighting fixtures and other electrical equipment shall be made of steel or iron, either hot-dip galvanized (preferably), or zinc electroplated. Q What type of supports are used to support conduits, cable trays, enclosures, lighting fixtures and other electrical equipment in severe corrosive environment? Ans Shall be made of (A) Steel or iron, either hot-dip galvanized (preferably), or zinc electro plated and in addition, shall be factory-coating with PVC or field coating prior to installation. (B) Stainless steel (C) Fiberglass Cable Trays Q What kind of material is used for the cable trays? Ans According to SAES-P-104, cable trays materials shall be 62 a) Aluminum (copper free 0.4%). b) Fiber glass. c) Stainless steel d) Galvanize carbon steel in indoor air-conditioned area. Q According to SAES-P-104, Aluminum and galvanized carbon steel cable trays are designed, manufactured, rated and tested in accordance with? Ans Aluminum and galvanized carbon steel cable tray shall be designed, manufactured, rated, and tested in accordance with NEMA VE 1. Q According to SAES-P-104, Fiberglass cable trays are designed, manufactured, rated and tested in accordance with? Ans Fiberglass cable tray shall be designed, manufactured, rated, and tested in accordance with NEMA FG 1. Q What is purpose of providing the cover of cable tray? Ans Cover provide for protection from sun light and mechanical damage. Q How much spacing require on expansion joint for aluminum cable tray? Ans Spacing between expansions joint that allowed a 25 mm movement in 20 meters Underground Cable Systems Q What are the minimum depth of burial requirements for underground installations? Ans Minimum depth of burial requirements for underground installations are as follows: Millimeters from Grade Level to the Top Surface of Cable, Conduit or Duct Bank System Voltage Direct Buried Cables Direct Buried PVC Duct Bank and Direct Buried Rigid Steel 600 V and below 610 460 460 Over 600 V to 35 kV 920 610 460 Over 35 kV 1070 760 460 63 Q What is the underground conduit installation depth requirements in rocky areas, in areas where cables being below the water table, or to avoid underground obstructions such as other cables, conduits or piping? Ans In rocky areas where digging must be minimized, in areas where cables being below the water table, or to avoid underground obstructions such as other cables, conduits or piping, cables may be installed in one of the following configurations with total cover of 300mm or 150 mm: (a) PVC coated rigid steel conduit with a total cover not less than 300 mm, which shall include a 50 mm thick (minimum) reinforced concrete slab over the conduit; or (b) PVC coated rigid steel conduit with a total cover not less than 150 mm, which shall include a 100 mm thick (minimum) reinforced concrete slab over the conduit; or (c) A reinforced concrete encased duct bank with 150 mm of total cover, measured from the top of the upper conduit, which shall include a minimum of 100 mm of concrete over the upper conduit. *The top layer of the concrete slab or the duct bank shall be mixed with red dye. (Minimum thickness of red concrete layer should be 5 mm). Q What is the mini thickness of red concrete tiles? Ans SAES-P-104, minimum thickness of red concrete tiles is 50mm/5cm and are placed 300mm above direct buried cable or direct conduit, in addition, a yellow warning tape shall be installed over the tiles. Tiles dimensions are 200x400 mm. Q What is the depth, width of trench? And what is the minimum sand bedding height? And what is the minimum height of sweet sand before the yellow warning tape? Ans For direct buried cable trench the minimum depth is 610 mm from the top surface of the cable and minimum sand bedding is 150 mm and minimum height of sweet sand over the cable is 300 mm and then put red tiles and yellow warning tape and then backfill it. Q What type of duct banks are used for underground cable systems? Ans Duct banks shall consist of PVC conduit, encased in concrete. (1) The minimum burial depth from the grade level to the top surface of duct bank is 460 mm. (2) There shall be a minimum of 75 mm of concrete from the outside surface of the duct bank to any conduit or reinforcing steel. (3) In duct banks with steel conduit, unreinforced non-structural concrete shall be used. (4) In duct banks with PVC conduit, under areas with no traffic, or occasional traffic, unreinforced non-structural concrete shall be used. (5) In duct banks with PVC conduit, under areas with frequent traffic, such as roads and parking lots inside plants or communities, reinforced concrete shall be used. 64 *There shall be a minimum of 75 mm of concrete from the outside surface of the duct bank to any conduit or reinforcing steel. *The top layer (5 mm minimum thickness) of the concrete shall be mixed with red dye. Q When is the duct banks used? Ans At cross under paved road, and railroads and when depth is restricted/minimized due to some reasons. Q What is the minimum crossing or parallel clearance between direct buried cables or conduits and underground piping? Ans The minimum crossing or parallel clearance between direct buried cables or conduits and underground piping, shall be 300 mm. Cable Testing after Installation Q Why we do hypo-test? For what purpose we do hypo-test? Ans To check the insulation condition (di-electric strength of insulation) of the cables. Q Why we do megger test/IR test? For what purpose we do megger test/IR test? Ans To check the insulation resistance of the cables. Q What is Hi-Pot Test? Ans The Hi-Pot leakage current technique is a diagnostic test which involves the measurement of leakage current when a high potential (above nominal) is applied to the cable to determine the condition of the cable, specifically the insulation. Q What is the procedure for DC Hi-Pot Testing of medium voltage cables? Ans STEP-BY-STEP PROCEDURE FOR DC FIELD TESTING • Ground all conductors, except the one to be tested. • Connect cable shield to ground; ground any adjacent equipment. • Ensure adequate clearance of the conductor/terminals to be tested from ground to prevent flash over. • Carefully wipe terminals to remove any contamination (i.e. dust, moisture, etc.) • Corona-proof conductor/terminal ends of cable by sufficiently taping them. If cable is terminated, cover termination with a polyethylene bucket or bag. 65 • Fence test cable ends to ensure personnel safety. • Preliminary step: ‘Megger’ cable to be tested. Any cable that exhibits low ‘Megger’ readings is questionable and should be cleared before the high voltage DC test is performed. • Connect output of test set to conductor/terminal to be tested and connect ground terminal of test set to ground. • Bring DC voltage up to prescribed test level in five equal steps. Raise the voltage at an even rate, so as to reach the required level in not less than 10 seconds. Hold the voltage at each step for 60 seconds. Read and record the leakage current at the end of each hold period. • Hold the full test voltage for not less than 10 minutes or more than 15 minutes. Read and record the leakage current at 15-second intervals for the first 2 minutes and then every minute for the duration of the test. • Bring the test voltage control quickly and smoothly to zero. Read and record the voltage remaining on the cable after 30 and 60 seconds. Discharge the cable to ground using a properly terminated resistor stick. When the test set voltmeter indicates zero voltage on the cable, attach a solid ground to the cable and then disconnect the test set and resistor stick. • Test each conductor/cable in the circuit in the same manner. • Record all data concerning the circuit and test results. Q How can we check the condition of the cable insulation in field? Ans 1. The insulation resistance test performed with a megger tester. 2. The DC high potential test or DC hi-pot test 3. The very low frequency high potential test (VLF hi-pot test) 4. The AC high potential test which is performed at power frequency (50 hertz or 60 hertz). Q For low voltage cable, how much megger voltage requires? Ans SAES-P-104, megger voltage shall be 1-KV (DC) for one minute. Q For medium voltage cables how much megger voltage requires? Ans SAES-P-104, for medium voltage cables (5KV to 35 KV), megger voltages shall be 5-KV (DC). Q What kind of cable testing shall be performed at medium voltage (5 kV to 35 kV) cables? Ans 5 kV megger tested before and after backfilling and then DC- high- potential testing after installation and prior to placing in service 66 Q For how long time we applied the DC high potential test for 5kv and high rating direct buried cables? Ans The DC high potential value shall be 4 kV/1 mm for one minute and not to exceed 10 kV. Q How we do megger testing of new cables spliced to existing cables? Ans New cables to be spliced to existing cables shall be 5 kV megger tested and DC high-potential tested prior to splicing. After splicing, the new and existing cable combination shall be 5 kV megger tested. In addition, if the existing cable has been in service for less than five years, the new and existing cable combination shall be high-potential tested. Q What kind of test may be applied to determine the condition of old cables? Ans Very low frequency (VLF) test. Q For what purpose we applied VLF test? Ans Very Low Frequency (VLF) test may be applied to determine the condition (dielectric strength of insulation) of old cables. Q For high voltage cable (69 KV and above) how much voltage requires for Hi-Pot test? Ans SAES-P-104, Hi-Pot test voltages shall be 192-KV (AC) Q For what purpose we use high potential test and megger test? Ans To check to integrity of the cable jacket. Q How we check the integrity of overall jacket of direct buried cables rated 5KV and higher? Ans The integrity of the overall jacket of direct buried cables rated 5 kV and higher shall be tested by conducting a 5 kV megger and DC high potential test between the cable insulation and ground. Q How we check the integrity of the overall jacket of direct buried low voltage armored or metal clad cables? Ans The integrity of the overall jacket of direct buried low voltage armored or metal clad cables shall be tested by conducting a 500 V megger test. *IEC 60229 shall be used for HV cable jacket integrity testing. Cable Separation Q What is the minimum separation b/w power and control cables? 67 Ans At (1 kV to 34.5 kV), 300 mm separation is required At (34.5 kV and above), 1 m separation is required Q What are the low voltage, medium voltage and high voltage values? Ans Less than 1000 V → Low voltage 1KV to 35 KV → Medium voltage 35KV to 69 KV → High Voltage 69KV and high voltages → Extra high Voltage *Conduit sealing fittings shall not be used. *Conduits that cross hazardous location boundaries shall terminate in the open air at both ends of the conduit. *The cables outside the building shall be direct buried for a distance of at least 2 meters Conduit and Cable Sealing Basic Power System Design Criteria (SAES-P-100) Q SAES-P-100 is used for what? Ans SAES-P-100 is used for basic power system design criteria. Q What is the scope of SAES-P-100? Ans This SAES prescribes mandatory design basis and performance criteria of electrical power systems. Q What is bus tie breaker? Ans A breaker used to connect the two busses of secondary-selective system. 68 Q What is captive transformer? Ans A transformer whose output is dedicated to a single piece of utilization equipment. Q What are the critical loads? Ans Critical Loads are loads a) Where a single possible failure could cause a loss of power which would create an immediate hazard to human life. b) Security systems. c) Which cannot be shut-down for a minimum of 5 consecutive days annually for scheduled maintenance on upstream power supply equipment. Examples of critical loads are: major computer centers, major office buildings, process units in gas plants and refineries. Q What is electrical load? Ans Electrical load is the averaged usage of electricity over a specified time period. Q What is distribution equipment? Ans The equipment used to distribute power to utilization equipment or other distribution equipment. For example switchgear, Panel boards, Switch racks, switchboards, etc. Q What are the industrial facilities? Ans Industrial Facilities includes the following: a) Facilities directly associated with production, processing, or bulk distribution of hydrocarbons. This includes, but is not limited to, facilities such as the following: I) GOSPs II) Water injection plants III) Refineries IV) Bulk distribution plants V) Pumping stations VI) Gas plants b) Hospitals. c) Office buildings, exceeding three occupied floors. 69 d) Control buildings. Q What are the non-industrial facilities? Ans Non-industrial Facilities includes commercial type building applications. This includes, but is not limited to, the following: a) Shops b) Small office buildings c) Schools d) Community buildings e) Warehouses Q What is the operated load? Ans Operating Load: a) For new facilities: One-hour demand based on plant or facility design conditions. b) For existing facilities: When data from metering equipment is available, maximum 60-minute demand measured over a minimum of one year. Q What is secondary-selective switchgear? Ans A switchgear assembly consisting of two buses connected with a single bus tie breaker. Each bus has one breaker to receive incoming power Q What is secondary-selective substation? Ans A substation fed by two independent power sources (different transmission or distribution lines) which consists of one or more sets of two transformers and associated secondaryselective switchgear. Also referred to as a “double-ended” substation. Q What is utilization device/equipment? Ans The equipment whose primary function is to convert electrical energy to another form or store electrical energy. Examples of utilization equipment would be motors, heaters, lamps, batteries, etc. Equipment directly feeding/controlling the utilization equipment is considered part of the utilization equipment (e.g., AFDs, reduced voltage starters, battery chargers, etc.). Q what are the basic design codes for electrical power systems? Ans Electrical power systems shall be designed and constructed in accordance with the SBC, NFPA 70 (National Electrical Code), NFPA 70 E (Standard for Electrical Safety in the Workplace) and ANSI C2 (National Electrical Safety Code), as supplemented or modified by the Saudi Aramco Engineering Standards. *Only secondary-selective switchgear shall be used to feed critical loads. 70 Q What types of loads are supplied by stand-by power or emergency power? Ans Loads to be supplied by standby power or emergency power include the following: a) b) c) d) e) Security system Emergency control room or disaster response room. HVAC and air handling control equipment for pressurized buildings Emergency lighting, if DC power or UPS is not sufficient for the intended purpose. Essential loads, that cannot be supplied from UPS or DC system Q What should be the sizing of the electrical system? Ans Sizing of the electrical system shall be based upon using 110% of the sum of the operating load plus all known future loads. *Electrical equipment for fire pump installations shall meet the requirements of NFPA 20 *The frequency of alternating current electrical power systems shall be 60 Hz. *The primary distribution within industrial facilities shall be 13.8 kV, three-phase, threewire. *The Secondary distribution shall be either 4.16 KV, three phase three wire and/or 480 V, three phase three wire. *Equipment suitable for Class 1, Zone 0 locations may be used in Class 1, Zone 1 locations. Both areas are hazardous. UPS and DC Systems (SAES-P-103) Mandatory Saudi Aramco Engineering Requirements (MSAERs) are Saudi Aramco Materials System Specifications (SAMSSs), Engineering Standards (SAESs) and Standard Drawings (SASDs). Q What is the scope of SAES-P-103? Ans This standard prescribes mandatory requirements for installation and application of DC power systems (stationary storage batteries and rectifiers/chargers), uninterruptible power supply (UPS) systems, and solar photovoltaic systems. Q Describe DC Power System. Ans DC Power System shall consist of, but not limited to batteries, battery circuit breaker, rectifier/charger, DC/DC stabilizer (if requested), output distribution panelboards (if requested) and management system. 71 Q Describe Uninterruptible Power Supply System. Ans Uninterruptible Power Supply (UPS) System shall consist of, but not limited to batteries, battery circuit breaker, rectifier/charger, inverter, static transfer switch, manual bypass line, bypass shielded isolation transformer, output distribution panelboards and management system. Q Describe Photovoltaic Power System. Ans Solar Photovoltaic (PV) Power System shall consist of, but not limited to batteries, photovoltaic panels, charge regulator and output distribution panelboards. If AC output is required, inverter (DC/AC converter) shall be included. Battery Selection, Sizing and Load Determination *Batteries shall comply with 17-SAMSS-511. Q What are the guidelines for the battery selection? What is the criteria for battery selection? Ans Battery selection shall be made according to the following guidelines. a) Lead-calcium or lead low antimony pasted flat plate batteries are generally the most suitable for standby float service applications in an indoor temperature controlled environment. Such applications include electrical substations and UPS systems where shallow moderate cycling is expected. Lead-calcium batteries are not capable of many charge/discharge cycles, i.e., up to 5 cycle operations per year. Nonetheless, lead calcium battery features low current during float charging, and requires equalize charging only as needed. In comparison, lead low antimony batteries are capable of many charge/discharge cycles, but require equalize charging yearly. b) Tubular plate lead-antimony batteries or lead selenium batteries are suitable for cyclic loads (frequent charge/discharge cycles) and for high current short discharge applications. Due to material retention properties of the tubular construction, such batteries can also be successfully used in locations where frequent battery discharges are anticipated. Lead selenium batteries feature low water loss. c) Nickel-cadmium batteries are suitable for the applications described in this standard including outdoor non-temperature controlled applications such as remote unattended substations and photovoltaics systems. The batteries are fairly immune to corrosion, are resistant to mechanical and electrical abuse, operate well over a wide temperature range, and can tolerate frequent shallow or deep discharges. 72 Q d) The use of valve regulated lead acid (VRLA) batteries shall be limited to applications where flooded batteries cannot be used and when installed in temperature-controlled (25°C) environment. What are the factors to be considered for selection of batteries? Ans The following factors shall be considered in selecting a battery for a particular application: a) The design life of the battery shall be at least 20 years for flooded lead acid/nickel cadmium batteries, and at least 10 years for VRLA batteries. b) The design life of the battery shall be based on 25°C. Q Describe the battery sizing criteria? Ans 1- For applications involving a combination of continuous loads, non-continuous loads and/or momentary loads (such as switchgears), lead acid batteries shall be sized in accordance with the battery sizing worksheets of IEEE 485, and nickel cadmium batteries shall be sized in accordance with the battery sizing worksheets of IEEE 1115, or the equivalent IEC standards as applicable. 2- For photovoltaic (PV) applications involving a combination of continuous loads, noncontinuous loads and/or momentary loads, lead acid and nickel cadmium batteries shall be sized in accordance with IEEE or IEC applicable standards. 3- For applications of constant current consumption loads, the battery ampere-hour capacity shall be calculated as follows: DC Loads: Battery Ah Capacity @ CBT = L x BT x TC x AF x DF (1) UPS Loads: Where: Battery Ah Capacity @ CBT = Ah capacity of battery at required backup time Battery Ah Capacity = Ah capacity of battery at C8/C10 and C5, for lead acid battery and nickel cadmium battery, respectively (consult battery manufacturer for the conversion factor to convert Ah @ CBT to Ah @ C8/C10 and C5, for lead acid battery and nickel cadmium battery, respectively) L = Continuous load current (dc amperes) 73 BT = Battery back-up time (hours) AF = Aging factor (use 1.25 for all batteries) DF = Design factor (use DF = 1.1 for all types of batteries) kVA Load = Load designed apparent power (= Actual Load Power Consumption + Future Growth) PF = Load power factor No. of Cells = Number of series connected battery cells Eff.Inverter = Efficiency of UPS inverter VoltageEndCell = Battery cell voltage at end of discharge TC = Temperature compensation factor (cell size correction factor) 4- If the calculated battery capacity exceeds a manufacturer's standard rating by more than 5%, then the next larger standard battery capacity shall be selected. 5- Paralleling up to 4 sets of battery banks of identical Ah capacity and potential shall be allowed, to achieve the required Ampere Hour capacity. 6- The minimum battery backup time shall be in accordance with Table, and shall be based on the actual load calculation. For applications where the battery backup time exceeds Table 1 requirements, Electrical Equipment Unit, Consulting Services Department shall be consulted. 7- Redundant DC system, which consists of 2 rectifiers/chargers connected in parallel, shall have separate battery banks such that each battery bank shall be sized for 50% of the required total battery backup time as specified in Table. Table – Battery Backup Times Load Location In-Plant or In-Office In-Plant or In-Office Type of Load Primary Power Source Battery Backup Time(1) AC (UPS) AC (UPS) 60 minutes 30 minutes In-Plant or In-Office In-Plant or In-Office DC DC Remote Attended Substation(3) Attended Substation(3) Unattended Substation(3) Unattended Offshore Substation AC & DC DC DC Utility Only Utility + Generator(2) Utility Only Utility + Generator(2) Solar Photovoltaic Utility + Generator(2) Utility DC Utility 8 hours DC Utility 12 hours 2 hours 30 minutes 5 days (120 hours) 2 hours 4 hours 74 8- Battery backup time (battery duration) for emergency or life-critical loads shall be as specified in NFPA 70 and NFPA 101 9- Battery backup time for all security emergency systems shall be per the requirements of SAES-O Standards. 10- No-load losses of redundant systems shall be included in the battery sizing calculations. 11- Switchgear DC system shall be dedicated for loads that are critical and require continuous operation during utility power loss. 12- In-plant DC loads shall not be connected to the battery bank which is dedicated to the UPS system. 13- Substation battery systems shall be dedicated to connected DC loads and shall not be part of a plant UPS or other DC system. 14- The minimum number of series-connected battery cells shall be in accordance with Table or as determined by the calculations. Nonetheless, battery manufacturer's recommended number of cells based on the specified battery backup time shall be followed, if available. Nevertheless, for UPS applications, the number of series connected cells (DC voltage value) shall be selected by the UPS manufacturer. Required Number of Cells Nominal Battery Voltage (VDC) 12 24 48 120/125 240/250 360 408 480 Number of cells DC Systems Lead Acid Nickel Cadmium Number of Cells Photovoltaic Systems Lead Acid Nickel Cadmium 6 12 24 60/62 120/125 180 204 240 6 12 24 60 120 NA NA NA 9 18 36 91 182 273 309 364 10 19 38 95 191 NA NA NA 15- The maximum number of series connected cells shall be calculated as follows to ensure an optimal and safe DC system voltage and battery recharge voltage: Max. Number of Cells = Max. Allowed DC System Voltage / Equalizing Volts per Cell 75 16- Based on the number of cells calculated, the end-of-discharge voltage for each cell shall be calculated as follows to ensure that the system voltage does not fall below the minimum acceptable level: Voltage Discharge -of – End = Voltage System DC Allowed Min. / Cells of Number Unless otherwise recommended by the manufacturer, the minimum allowed DC system voltage shall be 87.5% of the nominal system voltage for DC and UPS systems, and 92.5% for Photovoltaic systems. 17- The cell end-of-discharge voltages shall be per Table below: Battery Cell End of Discharge Voltage Battery Type Lead-Acid Nickel-Cadmium General Applications 1.65 VPC to 1.75 VPC 1.0 VPC to 1.14 VPC PV Applications* 1.85 VDC 1.14 VPC to 1.2 VPC VPC = Volt Per Cell Battery Installations Q What are the international standard codes for installation of batteries? Ans All batteries shall be installed in battery rooms or battery enclosures in accordance with NFPA 70 (NEC), IEEE 484 or IEC 50272-2. *Batteries shall not be installed in enclosures inside a battery room. *The minimum battery room ventilation shall be one complete air change every 3 hours, and the temperature inside this battery room is maintained, but never exceed, 25°C. *Batteries shall not be installed in Class I, Division 1 locations. *Batteries installed in Class I, Division 2, locations shall be in a building or enclosure made safe by pressurized air. Loss of pressurization shall be monitored in accordance with NFPA 496. *Working space of at least 1 meter shall be provided in front of each battery rack or enclosure. *Batteries shall be supplied with covers for all inter-cell connecters and terminals or insulated copper busbars to enhance safety. Q Battery room walls and floor shall be made of what type of material? 76 Ans Battery room walls and floor shall be made of concrete construction and finishing. *Battery room finishing shall not contain drywall (such as plasterboard, wallboard, gypsum board, sheetrock, or gyprock). *Manned workstations shall not be located in battery rooms. *Battery rooms shall be provided with enclosed and gasketed (i.e., vapor tight) corrosion resistant lighting fixtures *Battery room lighting shall be installed to provide a minimum level of illumination of 30-ft candles (300 lux). *Emergency lighting with illumination level of 10-ft candles (100 lux) shall be installed to operate in the event of loss of mains power supply. Q How shall be installed the battery room doors? Ans Battery room doors shall open outward, away from the room, to the outside of the building, and be fitted with door closers and anti-panic (quick-release, quick-opening) hardware. No hasp, padlock, or other device shall be installed which will hinder operation of the emergency door opening devices. *Doors between battery rooms and other rooms shall not be permitted. *Potable water facilities shall be provided for rinsing spilled electrolyte in the battery room. Raw water shall not be used (as it is rich of minerals and dissolved solids that may react with the electrolyte). The amount of water supply shall be determined based on a risk assessment of the extreme scenario where the largest battery or electrolyte container gets spilled. *Provisions for neutralizing the battery electrolyte (acid or alkali) and caustic spillage shall be included in the battery room design. *Floor drains shall comply with SAES-S-060. *Sealed valve-regulated batteries do not require floor drains. *Emergency eyewash facilities shall be provided as required by SAES-B-069. *Sealed valve-regulated batteries do not require eyewash facilities. Q With what type of cover the battery room floor shall be covered? Ans Battery room floor shall be covered with an electrolyte (acid or alkali) resistant, durable, antistatic and slip-resistant surface overall, to a height 100 mm on each wall. 77 Where batteries are mounted against a wall, the wall behind and at each end of the battery bank shall be coated to a distance of 500 mm around the battery with an electrolyte resistant paint or tiles. *A dry type chemical fire extinguisher shall be installed on the outside of the battery room. *Cabinets or racks shall be provided in the battery room for storing maintenance tools and safety equipment. These cabinets and racks shall be acid or alkaline resistant as applicable. *Lead acid batteries shall not be mounted in the same room together with nickel cadmium batteries, and vice versa. *Battery rooms shall be vented to the outside air by forced ventilation to prevent accumulation of hydrogen and to maintain design temperature. The ventilation system is designed such that the hydrogen concentration shall not exceed 1% of the total air volume of the battery room. *The maximum hydrogen evolution rate for all kinds of flooded batteries is 0.000457 m³/hour (0.016 ft³/hour), per charging ampere, per cell, at 25°C, at standard pressure. The worst condition (the maximum hydrogen evolution) occurs when current is forced into a fully charged battery (overcharge). *An interlock between the air-handling unit and the high-rate charging switch shall be provided, such that failure of the air-handling unit shall cause the high-rate charging of batteries to stop. *The ventilation system shall be 100% redundant. Only direct driven exhaust fans shall be used. An interlock with the ventilation system shall be provided to stop the high-rate battery charging if the exhaust fan stops. *An alternative to interlocking with either air-handling unit or exhaust fans is to interlock the high-rate battery charging system with either an air-flow or air-pressure measuring device, such that ventilation insufficient to the 1% hydrogen limit will cause the high-rate charge to stop. *Audible and visual alarm shall be installed outside the battery room entrance to annunciate a failure in ventilation for prompt repair. *The minimum ventilation shall be one complete air change every 3 hours. *A battery area that meets the above ventilation requirements and the high-rate charge interlock shall be considered non-hazardous. Therefore special electrical equipment enclosures to prevent fire or explosions shall not be required. 78 *Equipment with arcing contacts shall be located in such a manner as to avoid those areas where hydrogen pockets could form. Electrical equipment shall not be located directly above the batteries and, as a rule, shall have a minimum horizontal separation of 1.5 meters from the nearest cell. *Temperature in a room that contains batteries shall not exceed 25°C. *If battery operating temperature increases by 10°C above the 25°C reference, battery design life is reduced by: 50% for lead acid batteries, and 20% for nickel cadmium batteries. *Return air-conditioning ducts from battery rooms shall be prohibited. *Lighting fixtures shall be installed at least 300 mm below the finished ceiling. *Inlets of air-conditioning shall be no higher than the top of the battery cell and the outlets (exhaust) at the highest level in the room. Air inlets and outlets shall be located in such a manner to provide effective cross ventilation over the batteries. *Batteries installed in a sealed passively cooled shelter shall be located in a separate compartment with a dedicated entrance. All battery cell vents shall be tubed so that hydrogen gas is vented outside the battery compartment. *Battery racks shall be constructed in accordance with 17-SAMSS-511. *Battery racks installations shall meet NEC bonding and grounding requirements. Battery racks shall be bonded at both end points to a local supplementary grounding electrode per NEC 250 or EN 50178. Install lug and cable on the steel rack and tighten to ensure ohmmeter reading between each component and a common point on rack frame indicated continuity for proper grounding. *Stationary batteries shall be installed on open battery racks within a battery room to facilitate proper cooling, routine inspection, and maintenance. *Either covers for all inter-cell connecters and battery terminals or insulated copper busbars shall be supplied as part of the battery. Q How much clearance shall be for battery cell to the rack? Ans Clearance from the top of the battery cell highest point to the bottom of the rack above it shall be 350 mm, and airspace between battery cells shall be approx. 10 mm. Q What are the requirements for battery enclosures? Ans Battery enclosures shall be in accordance with the following requirements: 79 a) The enclosure design shall include a removable lid, secured by quick- release latches, type 316L stainless steel or equivalent. Hinged enclosures shall be designed to open at least 120 degrees to facilitate proper maintenance access. b) The enclosure base shall be provided with cell supports designed to raise the cells a minimum of 5 cm above the enclosure floor. c) For indoor use, the battery enclosures and cell supports shall be made of fiberglass reinforced material or steel, with provisions for anchoring to the floor and grounding. The ventilation requirements of paragraph 6.3 shall be complied with. d) Valve regulated (sealed) lead acid (VRLA) batteries shall be mounted in ventilated indoors enclosures unless installed inside a dedicated battery room, where battery racks are sufficient. VRLA batteries shall not be used for outdoors applications. e) Battery enclosures for outdoor use shall be made of fiberglass-reinforced material, and shall be completely weatherproof, dust-tight, and rain-tight. The gasket shall be onepiece, heavy-duty black neoprene or Buna nitrile rubber, mechanically attached to the enclosure lip and in continuous contact with the enclosure lid. Minimum protection Class for outdoors mounting shall be NEMA 250 Type 4 (or IEC 60529 IP 65). For offshore outdoors applications, corrosion resistance enclosure NEMA 250 Type 4X (or IEC 60529 IP 65 with corrosion protection) shall be required. f) The fiberglass material shall meet the flammability rating of UL 94 type V-0. g) Steel enclosures and grounding lugs shall be coated with an acid-resistant or alkaliresistant (as applicable), chip and scratch resistant, baked powder epoxy or propylene. h) All hardware shall be 316L stainless steel or equivalent. i) The enclosure shall have an adequate number of drain openings at the bottom and a minimum of two ventilation openings at the top. The ventilation openings shall be fitted with breather-type plugs to release hydrogen gas without allowing sand/dust to enter the enclosure. j) Clearance above each battery cell shall be 350 mm, to allow proper air circulation and to permit filling, testing, and replacement of cells. Adequate clearance shall also be maintained in between cells. Air space between battery cells, as well as between the cells and external enclosure walls shall be approx. 10 mm. k) Enclosures with front access only shall have no more than 2 rows of stepped cells. Enclosures with access from the front and back sides may have a maximum of 4 rows of stepped cells. In the stepped cell arrangement, for vented battery application, cells shall be positioned in such a way that the electrolyte levels markings (both minimum and maximum) can be easily seen. Q What are the cable requirements for battery cables? Ans Battery cables shall be sized for a total voltage drop of less than 3%. Positive and negative battery cables shall be run in the same conduit to prevent inductive heating. 80 *The positive and negative buses of batteries shall be isolated from earth ground. *Each battery-based system shall be equipped with properly sized two-pole fused disconnect switch or circuit breaker with an undervoltage release feature to prevent battery discharge beyond the battery's end-of-discharge voltage. The undervoltage device shall disconnect the battery from the load when the battery voltage drops to the end-ofdischarge voltage. *An alarm to indicate the battery circuit breaker open condition (or fused disconnect switch open or blown fuse condition) shall be provided on the charger cabinet or the UPS cabinet. This alarm shall also be annunciated to the main control room DCS or to an area where operators are present. *The battery circuit breaker open condition (or fused disconnect switch open or blown fuse condition) shall be routed via Standalone or the Supervisory Control and Data Acquisition (SCADA) system or Network Management System (NMS), to the power control center. *Another alarm to indicate the battery room high temperature shall be annunciated to the main control room. Q What is wiring color coding for batteries wiring for grounded and ungrounded systems? Ans Ungrounded Systems for Industrial Facilities Positive: Red Negative: Black Battery rack and other equipment grounding conductors: Green Grounded Systems for Special Applications a) Negative Grounded Systems Positive: Red (ungrounded) Negative: White (grounded) b) Positive Grounded Systems Positive: Black (grounded) Negative: Red (ungrounded) *Battery rack and other equipment grounding conductors: Green, or green with yellow stripes Q What are the safety equipments shall be provided near stationary batteries? Ans The following safety equipment shall be provided near stationary batteries: a. Safety face shields and goggles b. Safety aprons c. Acid resistant rubber gloves 81 d. Safety shoes e. Eye washing facilities (refer to SAES-B-069) f. Neutralizing agent: - To neutralize lead acid battery: Mix 0.1 kg bicarbonate of soda to one liter of water. - To neutralize nickel cadmium battery spillage: Mix 50 grams boric acid solution to one liter of water. - Or use other suitable neutralizing agent recommended by the manufacturer for acid electrolyte spillage or the manufacturer of alkaline electrolyte spillage, whichever applicable. Q What are the safety signs shall be posted on battery room? Ans The following safety signs shall be permanently posted on battery room entrance at a visible location in Arabic and English languages: a. Sign: “DANGER CAUSTIC/ACID” b. Sign: “DANGER CAUSTIC/ALKALINE” c. Sign: “DANGER NO SMOKING” d. Sign: “EYE PROTECTION REQUIRED IN THIS AREA” Q How the batteries shall be disposed? Ans All batteries are considered hazardous wastes and shall be disposed per Saudi Aramco Supply Chain Management Manual CU 22.03 Processing and Handling of Hazardous Material. This manual reference to: Saudi Aramco Form 112-H shall be used to dispose (return to Reclamation) or to ship hazardous materials / chemicals. Rectifiers/Chargers *Rectifiers/chargers for utility type applications shall comply with 17-SAMSS-514. *Parallel redundant rectifiers/chargers with dynamic load sharing capability shall be provided for all double-ended substations. *Each rectifier/charger shall be fed from a different source. *A single rectifier/charger shall be provided for single-ended substations unless an alternative power supply is available, in which case dual rectifiers/chargers shall be required. *For critical systems, two parallel battery chargers should be provided, so that maintenance can be performed without loss of load supply. *Critical DC load(s) that are sensitive to high DC supply voltage, that can reach up to +18% of nominal, shall be supplied through DC/DC stabilizer. During loss of mains supply and fault clearances, the DC/DC stabilizer shall be automatically isolated (bypassed) and load(s) 82 supply shall be directly from the batteries of the DC system. The DC/DC stabilizer shall secure supply voltage to sensitive critical load(s) within ±1% of nominal under all operating conditions. Voltage supply to sensitive load(s) through DC/DC stabilizer shall be performed during normal operating conditions only. Q What type of enclosure is used for outdoors mounting rectifier/charger? Ans Rectifier/charger enclosure for outdoors mounting shall be completely weather-proof, dusttight and rain-tight. Enclosure minimum protection class shall be NEMA 250 Type 4 (or IEC 60529 IP 65). Q What type of enclosure of rectifier/charger is used for marine applications? Ans For marine applications, rectifier/charger enclosure shall have corrosion protection as follows: a) Outdoors Mounting: NEMA 250 Type 4X (or IEC 60529 IP 65 with corrosion protection). b) Indoors Mounting: NEMA 250 Type 12 (or IEC 60529 IP 54) with corrosion protection. *Rectifier/charger enclosure doors shall be hinged and designed to open at least 120 degrees to facilitate maintenance access. *The Rectifier/Charger shall be monitored remotely and be equipped with, but not limited to the following: 1) Rectifier/Charger management software and hardware. 2) Web-based monitoring facility a) Card for network connection b) Software for network management c) Web/SNMP manager 3) RS 232/RS 485 ports. 4) Battery management technology. 5) Environment sensor for SNMP/Web application (to monitor temperature and humidity). Uninterruptible Power Supply (UPS) Systems *UPS rating larger than 10kVA shall comply with 17-SAMSS-516. *Industrial UPS rating less or equal to 10 kVA shall comply with UL 1778 or IEC 62040 UPS Specifications (Less or Equal to 10 kVA) UPS Technology Double Conversion True On-Line 83 Inverter Topology AC Input Input Voltage Pulse Width Modulation 230 VAC 1-Phase, or 400 VAC 3-Phase, 50/60 Hz Or as per project specified requirements Voltage Tolerance Frequency Tolerance Inverter Output ±15% ± 5% Output Voltage Voltage Regulation 230 VAC 1-Phase, or 400 VAC 3-Phase, Or as per specified requirements 50% unbalanced load 100% unbalanced load Operating Frequency Frequency Regulations When Synchronizing When Free Running Maximum Total Harmonic Distortion at 100% nonlinear loads Steady State Condition: ±1% ±2% (for 3-Phase UPS only) ±5% (for 3-Phase UPS only) 50/60Hz ±1% ±0.1% 5% THDV UPS Specifications (Less or Equal to 10 kVA) Load Crest Factor Load Power Factor Overload Capacity (Inverter) Equipped with Built-in Battery Backup Time Type Recharge Time Warranty 0.8 Lagging to 0.8 Leading 150% for 1 minute 125% for 10 minutes Maximum Voltage Transient 5% for 0 to 100% step load with recovery to ±2% of nominal within 1 mains cycle a. Bypass static transfer switch – rated for continuous operation at full load b. Manual transfer switch – for maintenance purpose c. Battery circuit breaker that has low DC voltage disconnect d. UPS management software e. Battery management technology f. Web-based monitoring facility - Card for network connection - Software for network management - Web / SNMP manager g. Environment sensor for SNMP / Web application - Monitoring of temperature and humidity h. RS232 port i. 6 outlets, fused (UPS up to 6 kVA UPS only) j. Input cable and plug k. UPS control LCD display to - Display UPS measurements and alarms - Control UPS functionality l. UPS manuals in English language (both hardcopy and softcopy) - User Manual - Maintenance, Troubleshooting and Repair Manual - Complete circuit diagram(s) Minimum 30 minutes at full load, or as per requirement/specifications. Valve Regulated Lead Acid; Long lifetime type (design life >= 10 years) Within 10 x battery backup time to 95%of battery Ah capacity At least two (3) years from UPS successful commissioning 84 *UPS enclosure doors shall be hinged and designed to open at least 120 degrees to facilitate maintenance access. Q What are the input requirements for UPS? Ans 1) UPS rating larger than 50 kVA: Normal and alternate source voltages shall be 3 phase, 3 wire + ground. 2) The normal input to the UPS rectifiers/chargers and the feed to the bypass shielded isolation transformer (alternate source) shall be from different sources. The separate sources could be separate buses of a double-ended system. If separate sources are not available, then the UPS shall be supplied from separate breakers of the same source. 3) UPS rectifier/charger shall contain a programmable walk-in ramp circuit, for which input current shall gradually increase from 0 to UPS rated power in approx. 10 seconds after the rectifier/charger input circuit breaker is closed. Q What are the output requirements for USP? Ans 1) UPS Systems Rating <= 50 kVA: 1 phase, 2 wire; or 3 phase, 4 wire, plus ground. 2) UPS Systems Rating > 50 kVA: 3 phase, 4 wire, plus ground. *The power (kVA) rating of the UPS system shall be equal to or greater than the steadystate kVA of all the downstream loads plus a future load growth factor. *The load power factor (PF) of 0.9 lagging shall be considered in sizing the batteries for the UPS system. The UPS inverter shall be sized to deliver full rated power at PF = 0.8 and PF = 0.9 lagging without derating, for Plant UPS and IT UPS, respectively. *Every UPS system shall have the following fully rated and designed for continuous operation: static bypass switch and maintenance (manual) bypass switch. *Steady-State Load Conditions: Determine the average power requirement of all downstream loads based on their operating duty cycle. *Transient Conditions: Determine the transient current peaks (inrush currents) and the time duration of such peaks which may occur during the start-up of all load devices. Analyze the UPS to determine if it can withstand the inrush current requirements of the loads based on the following overload capabilities 150% for 1 minute. *A workspace of 1 m shall be provided in front of the UPS cabinets. If rear access or side access is required for UPS maintenance, a clearance of 1 m shall be allowed. 85 *UPS system shall be located in a temperature-controlled room in which the temperature is maintained at 25°C. Redundant AC systems are preferred for continuous and reliable operation. *Cables for the primary AC input, output, and the alternate AC source shall be run in separate raceways. Q Ans AC input power to industrial UPS systems shall comply with the following: a) The initial magnetization current shall be limited to 600% of the rectifier/charger rated input current for a duration of one main cycle. b) The circuit breakers for both the primary and alternate AC sources shall be equipped with overcurrent protection, sized and coordinated with upstream and downstream protections c) When a generator and automatic transfer switch arrangement is used to extend the protection time of a UPS system, it shall be connected to deliver power to the UPS rectifier, but not directly to the critical load. d) The UPS static switch shall be arranged to transfer the entire UPS load to the alternate AC source (bypass line) in the event of a malfunction of the inverter or to clear a load fault. After fault clearance, the load shall be transferred automatically from the mains supply to the UPS output supply. e) The kVA rating of a backup generator used for supplying emergency backup power to the UPS system shall be at least 2.25 times the rated kVA of the UPS. f) The UPS system shall automatically block (inhibit) battery charging during supply of power through the emergency generator. *UPS loads shall be distributed through panelboards. Protection for the outgoing circuits shall be accomplished through circuit breakers rated for continuous operation with capability to quickly open and clear short-circuit and/or overload conditions. *Ratings of distribution panel's main feeder and branch circuits shall be coordinated with UPS and bypass ratings. The maximum current rating of the largest branch circuit breaker in the distribution panel shall be no greater than one-half the rated current output of the inverter. In the case of fuses, the largest load-side fuse shall be no greater than one-fourth the rated current output of the inverter. This is to ensure proper selectivity between the tripping of the load circuit protective devices and the inverter's internal protective devices. These requirements shall not apply when the UPS is equipped with a static bypass switch for transferring to the bypass (alternate) line. In that case, the protective devices for the outgoing loads shall be selected to achieve selective coordination with the primary breaker on the line side of the bypass transformer. 86 *Branch circuit breakers shall be coordinated with the load crest factor (in-rush current) as applicable. *A bolted fault test (three phases connected to ground) shall be conducted on the UPS distribution system to establish that proper fuse coordination has been achieved. Conduct the test by placing a bolted fault, by means of a contactor, on a typical branch circuit of the UPS distribution system. The branch circuit fuse shall clear the fault without affecting any upstream fuses and circuit breakers. Photovoltaic (Solar) Systems *Solar photovoltaic systems shall be installed in accordance with NFPA 70/NEC, Article 690 *Enclosures housing electronic equipment and batteries shall be shaded from direct sunlight regardless of the sun inclination angle. Q What type of enclosure is used for housing electronic equipment and batteries for solar system? Ans Minimum enclosure protection class for all outdoors mounting applications shall be NEMA 250 Type 4X (or IEC 60529 IP 65 with corrosion protection). *Each solar photovoltaic module shall be equipped with a Shottky blocking diode to prevent reverse flow of power into the photovoltaic module. Q How much should be the tilt/inclination angle of the solar photovoltaic array? Ans Solar photovoltaic array shall be installed at a tilt (inclination) angle equal to the latitude of the location plus 10-15 degrees. *Solar photovoltaic array shall be directed toward the geographical south (±5 degrees). *Battery shall be selected for minimum topping-up interval of 1 year, at 25°C operating temperature and float charging. Q Battery selected for photovoltaic application should be of how many cycles? Ans Battery shall be selected for photovoltaic application with a cycling life of at least 8000 cycles to a shallow cycle of 20% depth of discharge (DOD), and 1000 cycles to 80% DOD. *The charge regulator shall be designed to provide two-step (stage) charging for the batteries (float charging and equalize charging) and to provide the power requirements of the load when the photovoltaic solar array is producing power. 87 *On-off type regulators, which simply disconnect the solar array from the entire system when the battery reaches a certain terminal voltage, are not acceptable. *The charge regulators shall be of the solid-state design. *The charge regulator shall be designed to operate continuously at full rate in ambient temperatures between 0 and 55°C. *The charge regulator shall be equipped with a Shottky blocking diode to prevent reverse flow of power into a faulty regulator. *The charge regulator shall be equipped with temperature compensation feature to adjust the charging voltage with temperature. *The charge regulator shall be equipped with a low-voltage battery disconnect which shall act to disconnect the load from the battery when the battery reaches the end-of-discharge voltage (1.85 Volts per cell for lead-acid batteries and1.14 Volts per cell for nickel-cadmium batteries) to prevent severe battery discharge. Battery manufacturer's recommended cell end of discharge voltage shall be followed. *The charge regulator shall include the following instrumentation and alarms: a. b. c. d. e. f. Battery voltage Battery current (charging or discharging) Solar array current (for each array) Load current; Local indication of high and low battery voltage plus normally open and normally closed voltage free contacts for activating remote alarms All alarms shall be indicated on the charge regulator cabinet and a set of normally open and normally closed voltage free contacts shall be provided for annunciating the alarms to a central control room via Remote Terminal Units (RTUs) or similar facilities, where such facilities are available. * Surge protection shall be provided for the DC load bus. *All controls and instrumentation shall be housed in a NEMA 250 Type 4X (or IEC 60529 IP 65 with corrosion protection) enclosure. Q What are the sizing parameters for solar photovoltaic power system? Ans Solar photovoltaic power system shall be sized as follows: 1) Maximum autonomy (backup) time shall be 5 days or as per application requirement. 2) Charge regulator shall be rated for the maximum array current plus 10% design margin. 88 Solar photovoltaic array shall be sized with the following factors: 1) The solar array shall be sized to fully recharge the battery to 95% state of charge in 30 days. 2) The array shall be sized based on 5 effective sun hours for all installations in Saudi Arabia. 3) The array size shall be derated 10% for dust accumulation. 4) The array size shall be derated 10% for aging over the array expected useful life. 5) The array sizing shall include additional 10% capacity for future growth. Battery Tests and Records The initial battery capacity test and commissioning records are pertinent to the maintenance and optimum operational life of the battery. All commissioning data shall be dated, recorded, and maintained in a permanent file to facilitate required future maintenance and interpretation of the operating data. * The following data shall be maintained in a permanent record file: a) Initial battery capacity test performed in accordance with IEEE 450 (for lead acid), IEEE 1106 (for nickel cadmium), or IEEE 1188 (for VRLA) or the IEC equivalent standard, as applicable. b) The initial resistance values of the intercell connections. c) The initial individual cell voltages and specific gravity measurements. * Routine battery maintenance and testing shall be in accordance to SAEP-350. Overhead Distribution Systems (SAES-P-107) Q What are the environmental conditions on which overhead line design is based? Ans Overhead line design shall be based on the following environmental conditions: a) Minimum temperature: 0°C b) Maximum temperature: 50°C c) Wind speed (50 yr.): 160 km/h Q What is the length of distribution line span? Ans Distribution line spans should normally not exceed 90 m in length Q What type of lugs are used for overhead line connections 89 Ans Compression type lugs shall be used for overhead line connections to equipment furnished with pad type terminals. Compression lugs or splices used for connections of insulated or covered cables to overhead lines shall have a closed barrel or solid center stop to prevent ingress of water into the insulated cable. Non-current carrying metallic enclosures, brackets, and braces shall be bonded together via grounding lugs and shall be connected to a grounding electrode conductor. Pole ground conductors shall be minimum 4 AWG, stranded, soft drawn, bare copper. Q What should be the vertical clearance above grade for desert installation of conductors? Ans Vertical clearances above grade for desert installations of conductors, including service drops, messengers, and guys shall be minimum 8.5 m at final unloaded sag, no wind, and 50°C ambient temperature. Q What type of Arial-to-ground transitions should be? Ans Aerial-to-underground transitions shall be in rigid galvanized steel conduit or PVC coated galvanized rigid steel conduit Q What type of material supporting structures for overhead lines shall be? Ans Supporting structures for overhead lines shall hot dipped galvanized steel or seamless aluminum alloy poles in plants and other industrial facilities and fiberglass poles or wood poles. Q What type of wood poles for supporting structures shall be? Ans Wood poles used for supporting structures shall be Class 4 or better as defined in ANSI O5.1. Q Where wood poles shall be used? Ans Wood poles shall be permitted for use in stand-alone Water Injection Plants, Water Treatment Plants, and for supply lines located outside of industrial and plant areas (for example, Cathodic Protection supply lines in desert areas). Q On which bases the locations of supporting structures, guy, messenger and anchor shall be selected? Ans Supporting structure, guy, messenger, and anchor locations shall be selected based on accessibility, limited use of guys, minimal obstructions to pedestrian and vehicular traffic, and shall be as inconspicuous as possible. Q Supporting structures located less than 9m from a roadway shall be protected by what? 90 Ans Where required supporting structures located less than 9 m from a roadway shall be protected by barriers meeting the requirements of the Highway Design Manual, Volume 2, and Part 1. Q What is the clearance between supporting structures and curbs? Ans Supporting structure clearance from curbs shall be maintained at a minimum of 0.6 m from face of curb. Q What is the height of dating nail above grade for wood supporting structures? Ans Wood supporting structures shall have a dating nail indicating the year of installation located at approximately 2 m above grade. Q Where we use armless type construction? Ans Armless type construction shall be used for the conductor support system. Q What is the value limit for horizontal loading for line post insulators? Ans Horizontal loading for line post insulators shall not exceed 2.2 KN for initial sag at the minimum temperature, and wind loading of 430 pa. *Line conductors up to 336.4 kcmil ACSR shall be dead-ended for line angles larger than 30°. *Line conductors 336.4 kcmil and larger shall be dead-ended for line angles larger than 5°. *Lines more than 2 km long shall be double dead-ended a minimum of every 1.5 km. Q What should be the angle between the down=guy and the supporting structure? Ans The angle between a down-guy and the supporting structure shall not exceed 60°. Q What is the load limit of supporting structure for sidewalk guys? Ans The use of sidewalk guys shall be limited to supporting structure loads of less than 6.6 kN. Q What type of structure for sidewalk guy horizontal member shall consist of? Ans Sidewalk guy horizontal member shall consist of a 2 in galvanized pipe at a minimum height of 2.4 m above grade. Q What type of sidewalk guys shall be? Ans Sidewalk guys shall have reflective finished guy guards with the open side of the guard facing away from the sidewalk. Guys from supporting structures having ungrounded or resistance grounded circuits shall be insulated with strain insulators. Q What is the height of insulators from above grade shall be? 91 Ans Insulators shall be located a minimum of 2.4 m above grade and below the lowest power conductor. Q What type of guy insulators shall be used? Ans Guy insulators shall not be used with guy strands having ultimate strengths greater than 80 kN. Guy insulators shall have a rated ultimate strength greater than the rated breaking strength of the guy. Q What type of messengers shall be used? Ans Messengers shall be of the stranded steel type. Messengers shall be sized for the ultimate number of cables to be installed. Q What is the minimum insulator creepage shall be? Ans Minimum insulator creepage for components shall be 40 mm per kV line-to-line nominal system voltage. Q What types of insulators shall be used? Ans Post and suspension type insulators shall be used. *Pin type insulators shall not be used. Insulator brackets shall be metallic. Semiconducting or resistive glaze insulators shall not be used. Q What requirements shall meet the insulators used on overhead distribution systems? Ans Insulators used on overhead distribution systems shall meet the requirements of the ANSI C29 series of standards. (1) (2) (3) (4) (5) (6) Insulators shall be tested in accordance with C29.1 Suspension type insulators shall be in accordance with ANSI C29.2 Strain type insulators shall be in accordance with ANSI C29.4 Line-post type insulators shall be in accordance with ANSI/NEMA C29.7 Station-post type insulators shall be in accordance with ANSI C29.9 Preferred insulator color is chocolate brown. Q What is the load limit for insulators for overhead distribution systems? Ans Insulators shall not be loaded in excess of 40% of their rated ultimate strength. Q Where we use the Fog type porcelain suspension insulators? Ans Fog type porcelain suspension insulators shall be used to terminate overhead circuits at a substation bay or supporting strain bus. For these applications, an insulating string shall consist of a minimum of 2 units at 13.8 kV and 4 units at 34.5 kV. 92 Q What type of conductors shall be used for overhead distribution systems? Ans Conductors shall be ACSR/AW (aluminum clad steel reinforced)/AW per ASTM B549 *Phase rotation shall be x y z (a b c) counterclockwise. Q What are the normal service conditions? Ans Normal service conditions are defined as follows: 80°C conductor temperature 50°C ambient temperature 0.6 m/sec wind velocity Q What are the emergency service conditions? Ans Emergency service conditions are defined as follows: 120°C conductor temperature 50°C ambient temperature 0.6 m/sec wind velocity Q What should be the conductor tension? Ans Conductor tension shall not exceed 10% of the conductor ultimate strength. Q Sag and tension calculations shall be based on what? Ans Sag and tension calculations shall be based on maximum and minimum ambient temperatures. Q How transformer primary connections shall be made? Ans Transformer primary connections shall be made with hot line clamps connected to a bail (stirrup) compressed on the line conductor. Q What is the minimum height between any parts of a pole mounted transformer or its mounting bracket or plate form and grade? Ans Minimum height between any part of a pole mounted transformer or its mounting bracket or platform and grade shall be 4.9 m. Q What should be the minimum stress safety factor shall have supporting structures for accessories? Ans Supporting structures for accessories shall have a minimum stress safety factor of 4.0 93 Q What should be the minimum separation between underground conductors? Ans Minimum separation between ungrounded conductors shall be System Voltage (kV) 4.16 13.8 34.5 Clearance mm 230 410 710 Q What the of load break switches should be? Ans Load break switches shall be provided at sectionalizing points. Q where the surge arresters shall be installed? Ans Surge arresters shall be installed at distribution transformer installations, capacitor bank installations, recloser installations, metering installations, and aerial-to-underground cable termination points Q what type of surge arresters shall be and what are the ratings of hem? Ans Surge arresters shall be of the distribution class, metal-oxide, gapless type and shall have the ratings as follows: System Voltage (kV) 4.16 13.8 34.5 Arrester Rating (kV) 6.0 12 27 Q What type of grounding electrode for surge arrester used and of what dimensions? Ans The grounding electrode for surge arresters shall be minimum 16 mm (5/8 in) diameter by 3 m (10 ft) local copper or copper clad ground rod(s) driven along the center line of the circuit. The ground rod(s) shall also be bonded to the plant or substation ground grid if located within 15 m of the rod. Q what should be the ground resistance of surge arrester? Ans The resistance to ground of the surge arrester ground shall not exceed 25 ohms. Q what is the minimum arrester-to-arrester clearance shall be? Ans Minimum arrester-to-arrester clearance shall be 94 System Voltage (kV) 4.16 13.8 34.5 Clearance mm 230 410 710 Q from where fused cutouts shall be fed? Ans Fused cutouts shall be provided for transformers fed directly from overhead distribution lines. *Load break switches and fused cutouts shall be provided for capacitor installations on overhead distribution lines. Motors and Generators (SEAS-P-113) Power System and Equipment Protection (SAES-P-114) Q SAES-P-114 is used for what? Ans SAES-P-114 is used for power system and equipment protection Q which standard is used for power system and equipment protection? Ans SAES-P-114 Q What is the scope of SAES-P-114? Ans This Standard prescribes minimum mandatory requirements for the design and installation of protective relaying for power systems and equipment. Switchgear and control equipment (SAES-P-116) General Questions 95 Q Define switchgear/control gear/control panel? Ans In an electrical system, a switchgear/control gear/control panel is the combination of electrical disconnect switches, fuses or circuit breakers used to control, protect and isolate electrical equipment Q What is a control system? Ans A control system is a device or set of devices, that manages, commands, directs or regulates the behavior/working of other device(s) or system(s). Q what is a transfer switch? Ans A transfer switch is an electrical switch that switches a load between two sources. Q What is bus bar? Ans In electrical power distribution, a busbar is a strip or bar of copper, brass or aluminium that conducts electricity within a switchboard, distribution board, substation, battery bank, or other electrical apparatus. Q What is an automatic transfer switch (ATS)? Ans An automatic transfer switch is used to switch a load automatically between two sources. Q What is the difference between the ATS (Automatic Transfer Switch) and AMF (Auto Man Failure Panel)? Ans ATS (automatic transfer system panel) will transfer load from main power to emergency load when the power source drop below 80% or normal voltage while AMF (automatic main failure panel) this will substitute as main electricity source and reserve the generator if the main supply fail or down. Q What is PFI panel? Ans Power factor improvement panel. It controls power factor. Q What is MCC (Motor Control Center) panel? Ans MCC (Motor control center) panel is used for distributing power to electric motors. MCC is consists of an enclosure which contains the combination control units, wire ways, internal wiring and bus bars. Q What is electrical enclosure/junction box/terminal enclosure? Ans An electrical enclosure/junction box/terminal enclosure is a cabinet for electrical or electronic equipment to mount/install switches, terminal blocks, knobs and displays and to prevent electrical shock to equipment users and protect the contents from the environment. 96 Q What is the junction box? Ans A box containing the connections and junctions and terminal blocks of wiring cables. Q what is PCC panel? Ans There is no difference between PCC (power control center) and PDB (power distribution board). They have same functions i.e. controlling power feeders. Q What is distribution board? Ans A distribution board (panelboard or breaker panel) is a component of an electricity supply system which divides an electrical power feed into subsidiary circuits, while providing protective fuse or circuit breaker for each circuit, in a common enclosure. Q What is switch board? Ans An electric switchboard is a device that directs electricity/electric power from one or more sources of supply to several smaller devices of usage. Q Define DOL circuit? Ans DOL (direct on line starter) is a circuit used for the starting of the induction motors because the induction motors draw more starting current during starting. DOL consists a circuit breaker, contactor, and an overload relay for protection. Q Define working load? Ans The maximum load that a machine or other device is designed to bear. Q What is the testing and commissioning of control panel? Ans we do the: a) b) c) d) e) f) g) all wire connections are cleaned and checked for tightness megger test and continuity test (phase to phase and phase to ground) of control wiring proper clearance between the connections check insulation, insulating tapes and insulated epoxy for damage check the safety and electrical interlocks for correct operation inspect grounding to check if all the components/circuit elements are working by energizing the circuit Q How we do circuit breaker test? Pre-commissioning? Ans The tests/pre-commissioning includes: a) trip test/current injection test b) Contact resistance test 97 c) megger test/ continuity test (from phase to phase and phase to ground) Q How we do contactor test? Pre-commissioning? Ans Turn the control switch to ON status to energize the coil in the contractor. Get the volt ohmmeter and turn it on and make sure that the ohm is positioned in front of the selector switch. Proceed to testing the L-side with its corresponding T-side as L-1 to T-1, reading must be 0 ohm. Q How we do relay testing? Pre-commissioning? Ans we do following tests a) megger test, insulation resistance test b) test of tripping circuit Q What is low voltage switchgear? Ans Low voltage switchgear is that operate within low voltage range. Q What is disconnecting switch? Define it? How many types are? Ans In electrical engineering, a disconnector, disconnect switch or isolator switch is used to ensure that an electrical circuit is completely de-energized for service or maintenance. a) Center-break disconnector b) Double-side break disconnector c) Knee type disconnector Q What is a switching device? Ans Device used to make or break the current in one or more electrical circuits. Q What is the current rating of switchracks? Ans Maximum switchrack rating is 600A. The current rating of a switchrack shall be a maximum of 600A and a minimum of 125% of the switchrack maximum operating load. Q What is the current rating of switchboards? Ans Switchboards shall have a maximum rating of 2000 A. *Switchracks shall only be used in low voltage applications. Q What is the current rating of Panelboards? Ans Panelboards in industrial facilities shall be rated 400A or less. Panelboards in non-industrial facilities shall be rated 1000A or less. 98 Transformers and reactors (SAES-P-121) Q How many types of transformer testing/pre-commissioning? Ans there are many types: a) b) c) d) e) Q Oil level checking Gauge checking Verify operation of temperature alarm Perform winding insulation test Turns ratio test how many type of transformer are used in field? Ans Power Transformer, Dry-Type Power Transformer, Overhead-Type Distribution Transformer, Pad-Mounted Distribution Transformer, Instrument Transformer, Current Transformer (CT), Voltage Transformer (VT), Control Transformer, Current-Limiting Reactor Tests of Transformer Type tests of transformer includes 1. Transformer winding resistance measurement 2. Transformer ratio test. 3. Measurement of insulation resistance. 4. Temperature rise test of transformer. 5. Tests on on-load tap-changer. Lighting (SAES-P-123) *IESNA >> Illuminating Engineering Society of North America Ambient Temperature: Average temperature of air or another medium in the vicinity of the luminaire. Ambient temperature is expressed in degrees Celsius. 99 Operating Temperature Range: Ambient temperature range within which the luminaire with regard to the specification can be operated. The operating temperature range is expressed in degrees Celsius. Luminaire: Apparatus which distributes, filters or transforms the light emitted from one or more lamps and which includes all the parts necessary for fixing and protecting the lamps and, where necessary, circuit auxiliaries together with the means for connecting them to the electric supply. The words “luminaire” and “lamp system” are often assumed to be synonymous. For the purposes of this standard, the word “luminaire” is restricted to apparatus used for distributing light in general lighting, while “lamp system” implies use of lamps in other than general lighting applications. Luminaire Lifetime: Length of time during which 70% of the measured initial luminous flux value are provided, as a function of maximum operating temperature range. The luminaire lifetime of the module is expressed in hours. Lumen Maintenance: Value of the luminous flux at a given time in the life of a luminaire divided by the initial value of the luminous flux of the luminaire and expressed as a percentage x of the initial luminous flux value. The lumen maintenance of a luminaire is the effect of decrease of lumen output which is sometimes referred to as depreciation or lumen loss factor. Luminaire Efficacy: Quotient of the luminous flux emitted by the power consumed by the luminaire. The efficacy is expressed in lm/W. Lighting Requirements Q Lighting design should be according to which standard? Ans Lighting design shall be in accordance with IESNA RP-7 Q Lighting standard for parking facilities shall be in accordance with which standard? Ans Lighting design for parking facilities shall be in accordance with IESNA RP-20. Q For photometric measurements of sports which standard we follow? Ans Photometric measurements of sports lighting, when required shall be performed as per the IESNA LM-5 Q For photometric measurements of parking areas which standard we follow? Ans Photometric measurements of parking areas, when required shall be performed as per the IESNA LM-64. Q what is ambient temperature for continuous operation of photocell switches? 100 Ans Photocell switches shall be suitable for continuous operation in an ambient temperature above 40°C. *Where floodlights are installed on steel towers, the towers shall be equipped with steel service platforms located 1.5 m below the fixtures. Q What are the requirements for poles in lighting areas and street lighting? Ans Poles for area lighting and street lighting shall meet the following requirements: (1) Poles used in process areas shall be hot-dipped galvanized steel. (2) Poles outside process areas shall be hot dipped galvanized steel or seamless aluminum alloy. (3) Aluminum, steel, and fiberglass poles shall be provided with a suitable wiring compartment located at a height of not less than 150 mm nor more than 900 mm from the base. *Lighting poles installed within 5 meters from roads having a speed limit in excess of 50 km/h Q What type of lamps are used in lighting fixtures for offices, control buildings, and in industrial areas? Ans Energy-efficient fluorescent lamps type T5 or T8 and compatible energy efficient electronic ballasts having less than 10% THD (total harmonic distortion) shall be used in lighting fixtures for offices, control buildings, and in industrial areas where fluorescent lighting is required. Q What type of fixtures are used for outdoor area illumination? Ans High-pressure sodium fixtures shall be used for outdoor area illumination. Q What type of fixtures are used for high-bay or low-bay indoor industrial applications? Ans High-pressure sodium or Metal Halide fixtures shall be used for high-bay or low-bay indoorindustrial applications. Q What type of fixtures are used in workshops, repair shops and maintenance shops? Ans Metal halide fixtures shall also be permitted in workshops, repair shops and maintenance shops where a high Color Rendering Index (CRI) is essential. *The use of energy-efficient fixtures like High Pressure Sodium, Metal Halide shall be maximized. Mercury vapor fixtures shall not be used. *Battery rooms shall be provided with enclosed and gasketed (i.e., vapor-tight) corrosionresistant lighting fixtures. Q For street lighting design which standard is used? Street lighting design shall be in accordance with which standard? 101 Ans Street lighting design shall be in accordance with IESNA RP-8 Q What is the height of light fixtures positioned over stairways, platforms, elevated walkways and landing? Ans Light fixtures positioned over stairways, platforms, elevated walkways and landings shall be positioned at a height of 2.03 m. Q What is the mini time duration of normal power failure for emergency lighting? Ans Minimum duration of emergency lighting in the event of normal power failure, shall be one-andone-half hours. Q What is the minimum emergency illumination level in manned switchgear rooms and control room? Ans In manned switchgear rooms and control rooms where essential activities continue during failure of the normal lighting, a minimum emergency illumination level of 100 lux (10 fc) shall be provided at 760 mm above the floor. Q Where the normal and emergency task lighting should be provided? Ans Normal and emergency task lighting of at least 200 lux (20 fc) shall be provided for the following: A. In plant areas to illuminate equipment required for use in emergencies, such as: emergency telephones, shutdown and emergency isolation stations, fire water pump areas, central foam concentrate mixing areas, fire control panels and stand-by generators. B. B. In evacuation assembly areas and in off-shore platform escape capsule areas and boat landings Q illuminated exit sign shall be manufactured and installed in accordance with which standard? Ans Illuminated exit signs shall be manufactured and installed in accordance with NFPA 101 requirements. Q where the emergency egress lighting shall be provided? Ans Emergency egress lighting shall be provided for the following. 1) 2) 3) 4) 5) Q Control Rooms Process Areas Switchgear Rooms In-Plant Buildings Offshore Platforms What is the emergency lighting illumination minimum and maximum lux value? 102 Ans Emergency lighting facilities shall provide initial illumination that is no less than a maintained maximum of 10 lux (1 fc) and a minimum at any point of 1 lux (0.1 fc) measured along the path of egress at floor level. *A maximum to minimum illuminance uniformity ratio of 40:1 shall not be exceeded. *Fluorescent and incandescent fixtures installed in the control room shall provide shadow less illumination. Q What is the efficiency and color rendering index of fluorescent lamps? Ans The fluorescent lamps shall have 82.5 lumens per-watt efficacy and a color rendering index (CRI) of 82 at a correlated color temperature of 3,500 K or higher *General illumination for offices, computer rooms, interface rooms and general service areas shall be provided by fluorescent fixtures. Office lighting shall be done as per IESNA RP-1. *Offices containing computer visual display terminal (VDT) shall be done as per IESNA RP-24. *Fixtures for suspended ceilings shall be recessed mounted and shall be self-supporting in accordance to NFPA 70. *Incandescent spot fixtures with dimmers to provide variable illumination of up to 1,000 lux shall be used for supplementary task lighting in work areas within the control room as required. Power System Automation (SEAS-P-126) 103