RUMAILA PROJECT Document Title: METHOD STATEMENT Project Title: Scaffolding services at SIDS-201&202 – 1ST Stage Vessel 1- TRH & TRI LT Look check Project - Station / Location To Erect, Modify & Dismantle scaffold to access the SIDS-201&202 – 1ST Stage Vessel 1- TRH & TRI LT Look check. 00 Approval REV. Revision Description 14-Apr-23 Date Senthil Khaldoun Akeel Jasem Originated Reviewed Approved RAK Approved ROO Table of Contents 1. SAFETY...................................................................................................................... 3 2. OBEJECTIVE ............................................................................................................... 3 3. STANDARDS .............................................................................................................. 3 4. TOOLS & EQUIPMENTS .............................................................................................. 3 5. MANPOWER ............................................................................................................. 4 6. SCOPE OF WORK ....................................................................................................... 4 7. SCAFFOLDING ERECTING AND DISMANTLING PROCEDURE......................................... 4 8. HOUSE KEEPING ........................................................................................................ 5 2 1. SAFETY PA to raise PTW and HITRA for the scope of work to be carried out. Essential Personnel only to be permitted in the work area, area to be barricaded off & safety sign to be put in place accordingly. Existing access egress routes to be used in case of any emergency and to be clearly stated to the personals involved via TBT. Toolbox Talk to be conducted with all personnel involved in the task. Execution and HSE team to ensure that all equipment to be used for task is inspected, fit for purpose and in compliance. Task specific RA to be developed for task and communicated via TBT and signed off by all personnel. HSE officer to ensure that suitable and sufficient PPE is available and worn by all personnel. 2. OBEJECTIVE The purpose of this method statement is to Install, Modify and Dismantle Scaffold at SIDS-201&202 – 1ST Stage Vessel 1- TRH & TRI LT Look check. It is supported by guidance for scaffold installation, dismantling, inspection and maintenance, and advice for workers on managing the risks associated with scaffolds and related scaffolding work. This shall be carried out properly & safely by RAK team. 3. STANDARDS The Works shall comply with the latest editions of appropriate standards including ROO procedures and HSE requirements. 4. TOOLS & EQUIPMENTS S. NO. 1. 2. 3. 4. 5. Description Truck with crane capability (Hiab crane) - 10 ton Qty (Nos.) 1 Scaffolding Material Lump Mechanical Hand tools 2 Units Trailer 1 Mobile Scaffolding 1 3 5. MANPOWER S. NO. Description Qty (Nos.) 1. Site Engineer 1 2. PA 1 3. HSE 1 4. Rigger 1 5. Scaffolding Foreman 1 6. Scaffolding Technicians 5 6. SCOPE OF WORK Scaffolding Erection & Dismantling To execute the above said task, the following activities will be carried out very carefully and very controlled manner. 7. SCAFFOLDING ERECTING AND DISMANTLING PROCEDURE The purpose of this procedure is to ensure scaffolding is adequate for the work to be performed and properly erected and dismantled. It covers selecting, erecting, and dismantling all types of scaffolds. It applies to workers, supervisors, scaffold qualified persons, scaffold custodians, and Facilities. To Evaluate the work required, Inspect the location, Confirm the best scaffold choice and determine the scaffold’s duration. To Reviews and includes procedures required by ROO as determined by the type of scaffolding. Supervises, with assistance of and scaffold qualified person, scaffold assembly to ensure standards and regulatory requirements are met. Erects scaffold as per the instructions from the scaffold erector/dismantler supervisor, the scaffold qualified person, and training. ERECTING, ALTERING OR DISMANTLING Risk assessments and safe work method statements are the joint responsibility of the scaffolding supervisor and scaffolding technicians. They must obtain information/consult from the scaffold inspectors to the workers who undertake the erecting, altering or dismantling of the scaffolds. RAK scaffold supervisor will review the approved scaffold design and ensure that all necessary equipment is available. 4 The scaffold erectors will assemble the scaffold in accordance with the approved design, ensuring that all connections are secure. ROO scaffold supervisor/Authority will inspect the scaffold before allowing personnel to access it. The scaffold supervisor will install all necessary safety features, including toe-boards, guardrails, and safety harnesses. The scaffold supervisor will ensure that all personnel have safely evacuated the scaffold before dismantling begins. The scaffold erectors will disassemble the scaffold in the reverse order of erection. The scaffold erectors will modify the scaffold in accordance with the approved design, ensuring that all connections are secure. The scaffold supervisor will inspect the modified scaffold before allowing personnel to access it. The scaffold supervisor will install all necessary safety features, including toe-boards, guardrails, and safety harnesses. Ensures scaffold maintenance is performed if needed, Ensures the work site is left in a clean and safe condition. All scaffolding components will be lowered to the deck safely and stored in a designated area. The scaffold supervisor will review the proposed modification and ensure that all necessary equipment is available. 8. HOUSE KEEPING Area to be cleaned and barricades and warning tapes to be removed, site will be made good and control handed back to the client. Works to be inspected during and on completion of works by site engineer or competent foreman. After completion of all scrap and debris will be removed using registered waste carriers. 5