ATP Document PowerCube1000 with ACB Solution ATP Document (Roll Out 3G New Sites) Region: Site Name Site ID Address City Site Type ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 □ GF □ RT Page 1 1. Test Procedures: Power Cube 1000 with ICC300 and of ACB100/200 banks inside power cabinet. No Test Item 1.1 Installation of PowerCube system Cabinet 1.2 Power ON/OFF the AC Input 1.3 Check the status of the indicators on the PSU 1.4 Check the status of the Heat Exchanger Fan Unit connections and working 1.5 Check the Surge Protection Devices connections and specifications 1.6 Installation of ACB battery in PowerCube cabinet. 1.7 Installation of ESMU-A inside Power cabinet for ACB200AH. 1.8 Check DC Air-condition connections and working. ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Specified Value/ Requirement and Test Procedure. Power system installed securely on PAD or mounting racks as per site layout (approved / as built) No damage observe. Put ON/OFF the AC Input 3pole Circuit Breaker, all the PSU Modules should work properly. Power input indicator (top): ON Protection indicator (middle):OFF Fault indicator (bottom): OFF The internal fans of heat exchanger are working and check air circulation inside power cabinet. The Surge Protection Devices installed in Rectifier Cabinet (PowerCube) shall be in healthy state. Check Color on front of SPD shall be GREEN, In case of RED/BLACK, it is declared to be faulty The ACB batteries ICC310 cabinet; arrange each bank/battery as per guidance from manufacturer. The interconnection strips for each battery string cell to cell terminal must be tightened The ESMU-A is installed with Sub rack of each ACB battery string. The interconnection of each ESMUA port connected with communication cables for each battery in the string. DC Air-condition is working and DC power cable for powering Air-condition is connected with breaker. The compressor and internal fan units of Air-condition are in working condition. Temperature Set point is 30 degrees. Severity Test Result (OK/NOK) Major Major Major Major Major Major Major Major Page 2 2. Test Procedures: Power Parameter Settings adjustment for ACB 100 and 200Ah battery site scenario. NO Test Items 2.1 Running status 2.2 Rectifier module failure 2.3 Check AC Input voltage thresholds values Scenario: Observat ion / Meas. Value Parameters At Normal Working there should be no Major alarm. Fail the rectifier module and check its light is turned off and generate alarm. AC Under and Over Voltage system reference value 180V/280V For 100ACB (OK/NOK) Major Major Major For 200ACB SET (As per Actual) 2.4 Date and Time 2.5 Battery Capacity 100 200 Major 2.6 Charge Current limit 0.4C 0.4C Major 2.7 Float Voltage 54.0V 54.0V Major 2.8 Boost Voltage 56.4V 56.4V Major 2.9 Low Battery Voltage 51.0V 51.0V Major 2.10 LLVD 50V 50V Major 2.11 BLVD 48V 48V Major 2.12 Check the alarm LED’s on SMU 2.13 TEST SET (As per Actual) Test Result On event of alarm RED LED on SMU shall lit on to give alarm indication. Check the values at the Display of SMU output voltage (54.0V) and Load current should be according the reference value. Minor Major Major 3. Test Procedures: AC / DC and Grounding Cables. No Test Item Specified Value/ Requirement and Test Procedure. Observatio n / Meas. Value 3.1 Specifications / installation & routing of AC power cable.(cable size as per BOQ) AC power cable: Wire 4*16mm2 connected with ACDB to rectifier main breaker. Routed separately from other cables. Both end connections of AC cable are tightened with Lugs and terminals covered by sleeves. Major 3.2 Specifications / installation & routing of DC power cable.(cable size as per BOQ) DC Power Cable: 35mm2 connected with battery bank. Connect the positive and negative cables as per the polarity. Major ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Test Result (OK/NOK) Page 3 3.3 3.4 Specification / installation of GND cables. (cable lengths & size as per BOQ) Ground Cable: 25mm2 connected with positive bus-bar of power system and grounding bar of site. Major Labels / Tagging of Cables (AC / DC / ACB Batteries and Alarm cables etc) The Tags must be pasted at the both ends of every cable inside ICC310 cabinet. All installed ACB batteries are tagged with its battery cell number for each bank. Minor 4. Test Procedures: Alarm Verification. NO Test Case 1 Mains Failure 2 Rectifier Major Alarm 3 Rectifier Minor Alarm 4 Low Battery Volt Alarm 5 Fan Failure alarm 6 ESMU-A Failure Alarm 7 Rectifier Door Open Alarm 8 DC AirCon Fault Alarm 9 High Temp. Alarm (ACB battery) ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Specified Value/ Requirement and Test Procedure. Observatio n / Meas. Value Test Result (OK/NOK) Check float voltages on ECC500 screen. Turn Off the Mains power supply from ACDB Check MF Alarm red led observed at ECC500. Unplug & remove any 2 modules (PSU’s) from the rectifier. Unplug & remove one SPD unit from the rectifier. Check alarm indication observed on ECC500 Adjust low battery voltage value to 51V from ECC500 Turn 3 ESMU-A off position Check voltage rating on ECC500 if decreased to 51V or below. Open the door of rectifier cabinet and turn its fan off. Disconnect the positive power plug of any BMU Check ESMU-A is turned off. Open the Door of Rectifier cabinet. Turn Off the breaker of DC AirCon form Rectifier unit. Check Aircon fault Alarm reports to EMUA and NOC. Open the door of battery cabinet and find temperature probe inside. Apply heat or rub the temp probe or decrease temp set point value in ECC500. Page 4 5. Test Procedures: Charging and Discharging of ACB Banks. No 1 2 3 Procedure Expected result Health check of battery banks Check ACB Battery for leakage / damaged / deformed etc. Voltage measurement of batteries PTML standard battery health check template (attached) is attached with ATP documents for battery testing. The ACB batteries are not leaked. Check for any leakage observed from joints of each cell or any acid corrosion observed inside cabinet. The ACB battery is not deformed or de-shaped. Take the complete cell by cell voltage readings before commencing battery test. Shutdown the AC Input supply of Rectifier to take batteries on load. Check the batteries feeding power to load after disconnection of AC power. Take the complete bank & cell voltage readings after every 30 minutes. tested battery backup is up to/greater than designed backup. (3hrs at the time of ATP) 4 Battery heath check 5 Battery health check Result Pass Fail Pass Fail Pass Fail Pass Fail Pass Fail T05-04 Battery Test Results: BATTERY BANK TEST – CHECKLIST Time (mins) No: Banks Output Voltage Float / Discharge Cell Voltages Bank 1 Bank 2 Bank 3 Bank 4 Bank 5 Bank 6 Bank 7 Bank 8 Bank 1 Bank 2 Bank 3 Bank 4 Bank 5 Bank 6 Bank 7 Bank 8 Bank 1 Bank 2 Bank 3 Bank 4 Bank 5 Bank 6 Bank 7 Bank 8 Bank 1 Bank 2 Bank 3 Bank 4 Bank 5 Bank 6 Bank 7 Bank 8 Output Current Ambient Temp(0C) Cell 1 Before Test Cell 2 Cell 3 Cell 4 30 mins 60 mins 90 mins Cell 1 Cell 2 Cell 3 Cell 4 Cell 1 Cell 2 Cell 3 Cell 4 Cell 1 Cell 2 Cell 3 Cell 4 RESULTS Observations: Last Discharge O/P Voltage Discharge Time(Hrs) Pass Fail Not Run ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Page 5 6. Snag List ACB Power Solution ATP Snags Classification ATP Date Snag Details Snag Classification (Major/Minor) Workmanship Factor(WM) * Note: *WF: Means Snags reported due to Workmanship /Human Factor.(Technical Expertise , Skills lacking. Poor Workmanship etc) Huawei Representative PTML Representative Name:_____________________ Name:_____________________ Signature:__________________ Signature:__________________ Date:______________________ Date:______________________ ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Page 6 Contents: S # No. Test Items Tests T01 Installation of Power System T01-01 Installation of PowerCube1000 with ICC300 Cabinet and of ACB100/200 banks inside power cabinet T02 Commissioning of Power System T02-01 Commissioning of PowerCube1000 with ACB100/200Ah and ICC300 Power Cabinet. T03 AC / DC / Grounding & Alarm Cables T03-01 Installation of AC Power Cable, DC Cables and Grounding Cables/SPD 5 T04 Site Tagging and Labels 2 T05 Test Procedures T05-01 Site External Alarm Tests 9 T05-02 Charging and Discharging of ACB Battery Banks 5 T05-03 Battery Test Results 1 T06 Documentation Required 4 ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Status Pass Fail 6 8 Page 7 T02 Installation of Power System T02-01 Installation of PowerCube1000 with ICC300 and of ACB100/200 banks inside power cabinet Objective Verify that the installation of the PowerCube 1000 System with ICC300 rectifier and fixation of cabinets; ACB banks, ECC500,PSU’s connections which complies with the engineering specifications according to system manual. Result: PassFailNot Run Comment & Remark: Prerequisites The Power Cube1000 installation as per site approved design. (Refer: site layout) The rectifier modules are installed in Rectifier Cabinet. Cabinet Security and Locking mechanism for PowerCube1000. ACB battery banks are installed according to BOQ Qty. Cascaded connection of ESMU-A with ACB Battery string Procedure Expected result 1.1: The Power system is installed securely on the concrete PAD or mounting racks as per site layout (approved / as built). 1. Installation of Power Cube 1.2: No damage has been done to equipment while 1000 system Cabinet. installation and door opening of installed power system 0 can be > 90 2. Installation of Expansion bolts for Power system POWERCUBE1000. 3. Check the PSU Installation inside power cabinet POWERCUBE1000. 4. Check the POWERCUBE1000 cabinet locks / security mechanism and holes for cable entry. 5. Installation of ACB battery in PowerCube cabinet. 6. Installation of ESMU-A inside Power cabinet for ACB200AH. ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 2.1: The mounting holes for the cabinet must be carried out by drilling on concrete PAD. 2.2: The 4 expansion bolts (M12 x 60) are installed and tightened by using appropriate socket wrench.The extra holes for cable entry are properly sealed and covered by fire proof mud. 3.1: The rated output current of each PSU is 50Amps, and minimum installed quantity of PSU’s is 2 or 3 as per BOQ and all should be in working condition. 4.1: The Entrance door and locks of POWERCUBE1000 are installed and operational , door closer is operational 4.2: The POWERCUBE1000 Cabinet Door sealing is complete and no damage is observed. 5.1: The ACB batteries installed in ICC310 cabinet must be arranged along with each bank/battery as listed on top of each battery. As per guidance from manufacturer. 5.2: Check number installed of battery Banks matches the quantity as per BOQ. 5.3: The interconnection strips for each battery string cell to cell terminal must be tightened. 6.1: The ESMU-A is installed with Sub rack of each ACB battery string. 6.2: The interconnection of each ESMU-A port connected with communication cables for each battery in the string. 6.3: Every ACB battery in string is connected in sequential order with battery communication ports of Result Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Page 8 ESMU-A(max 4 cells can be connected /BMU-). 6.4: The main communication cable for cascaded ESMU is connected with ECC500 of POWERCUBE1000 system cabinet. Pass Fail Not Run Huawei Representative PTML Representative Name:_____________________ Name:_____________________ Signature:__________________ Signature:__________________ Date:______________________ Date:______________________ T03 Commissioning of Power System T03-01 Commissioning of POWERCUBE1000 with ACB100/200Ah ICC300 Power Cabinet. Objective Verify that the commissioning of the Power System connected with ECC500, PSU’s as well as ACB Battery, ESMU , DC Aircon; complies with the engineering specifications. Result: PassFailNot Run Comment & Remark Prerequisites The Power system POWERCUBE1000 commissioning. The PSU’s are in working condition. The AC / DC and signaling cables are routed and properly connected with ACB100/200Ah. The Alarm connections are extended. The ACB100/200Ah cabinet is interconnected inside POWERCUBE1000 Procedure 1. Check the POWERCUBE1000 specifications and check AC, DC and signal cable connections of Power system Cabinet. 2. Check ECC500 commissioning with system power parameters. ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Expected result Result 1.1: The Power system installed is as per BOQ. Pass Fail Not Run 1.2: No component in Rectifier cabinet is loose or damaged. Pass Fail Not Run 1.3: The power cables (AC/DC) are connected correctly, check end to end ‘O’ & ‘U’ type lugs connections properly done as per appropriate cable dia” and punched with lugs presser tool. Pass Fail Not Run 2.1: The ECC500 has been installed and in working condition and ECC500 Display shall be properly visible and each parameter appearing on ECC500 shall be viewable. Blurring & disappearance of parameters shall fall ECC500 into faulty State. Pass Fail Not Run Page 9 2.2: Set all provided parameters in ECC500 such as DC float volts, boost volts, charging current; etc shall be appearing on ECC500. For 100ACB For 200ACB Date & Time Set Set Battery Capacity 100 200 Charge Current Limit 0.4C 0.4C Float Voltage 54.0 V 54.0 V Boost Voltage 56.4 V 56.4 V Low battery Voltage 51.0V 51.0 V LLVD Voltage 50 V 50 V BLVD Voltage 48 V 48 V Check 3. Check the alarm LED’s on ECC500 4. Check the status of the Heat Exchanger Fan Unit connections and working. 5. Check the status of the indicators on the PSU. 6. Check DC cables for ACB Batteries and check interconnection of communication cables between ESMU-A and ECC500. 7. Check DC Air-condition connections and working. 8. Check alarm cables DSS and DC Air-condition of ACB. ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Pass Fail Not Run 3.1: On event of alarm RED LED on ECC500 shall lit on to give alarm indication. Pass Fail Not Run 3.2: No alarm is present on the Rectifier indicator ECC500. Both battery & load power ratings visible on ECC500 are according with the specifications. Pass Fail Not Run 4.1: The Heat Exchanger Fan Unit of power system is connected with rectifier distribution breaker units. Pass Fail Not Run 4.2: The internal fans of heat exchanger are working and check air circulation inside power cabinet. 5.1: Power input indicator (top): ON 5.2: Protection indicator (middle): OFF 5.3: Fault indicator (bottom): OFF 6.1: The DC power cables of each ACB battery string is connected 6.2: Check 15 pin communication cable of every ACB in string is connected to its respective port number of ESMU-A card (one ESMU-A connects 4 ACB’s). 6.3: Check communication cable RJ485 of each ESMU-A must be interconnected with each other and main cascaded communication cable is connected between last ESMU-A and ECC500 (COM0). 7.1: The DC Air-condition is in working condition and DC power cable for powering Air-condition is connected with POWERCUBE1000 A through LLVD breaker. Pass Fail Not Run 7.2: No leakage of cold air observed outside ICC310 cabinet, check for heat insulation sealing for door of ACB cabinet. 7.3: The compressor and internal fan units of Aircondition are in working condition (check compressor working by cooling). Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run 8.1: The alarm cable of cabinet DSS (Door Status Switch) of ACB Cabinet is connected to EMUA Pass Fail Not Run 8.2: The Alarm cable of Aircon fault alarm and battery high temp alarm is connected with EMUA. Pass Fail Not Run 8 。 3 : Check the temperature set point of ACB cabinet is set to 30℃. Pass Fail Not Run Page 10 Huawei Representative PTML Representative Name:_____________________ Name:_____________________ Signature:__________________ Signature:__________________ Date:______________________ Date:______________________ T03 AC / DC / Grounding & Alarm Cables T03-01 Installation of AC Power Cable, DC Cables and Grounding Cables/SPD Objective Verify that the AC power cable, DC Cables and PGND cables &SPD are correctly processed and installed. Result: PassFailNot Run Comment & Remark Prerequisites All internal cables (AC / DC / Alarm) are installed. Procedure 1. Check the specifications and installation & routing of AC power cable.(cable lengths & size as per BOQ) 2. Check specification and installation of DC Power cable. .(cable lengths & size as per BOQ) 3. Check the specification and installation of GND cables. (cable lengths & size as per BOQ) 4. Connection of Grounding cable to main site DC Earth plate. 5. Check the Surge Protection unit’s connections and specifications. ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Expected result Result 1.1: The AC power cable installed to power up the 2 rectifier is Wire 4*16mm (Cores: Red, Yellow, Blue, Black) connected with ACDB to rectifier main breaker. (Cable specs. as listed in Annex. A) Pass Fail Not Run 1.2: The AC Power cable must be routed separately from other cables. Both end connections of AC cable are tightened with Lugs and terminals covered by sleeves. Pass Fail Not Run 2.1: The Rating of DC cable from Rectifier to Battery must be compliance with BOQ. Pass Fail Not Run 2.2: The positive and negative terminal of the DC power cable is connected with ACB battery and POWERCUBE1000 +ve & -ve bus-bar of power system cabinet. Pass Fail Not Run 3.1: The rating of grounding cable Wire must be compliance with BOQ. Pass Fail Not Run 3.2: Lugs at both ends of the power cables and PGND cables are soldered or securely crimped. Pass Fail Not Run 4.1: Grounding Cable for Cabinet shall be properly terminated to DC Earthing Bus bar. Pass Fail Not Run 4.2: End to End connectivity of grounding cable to Bus bar to Earthing pit shall be verified. Pass Fail Not Run 5.1: The Surge Protection Devices installed in Rectifier Cabinet (POWERCUBE1000) shall be in healthy state. 5.2: The AC SPD rating installed in Built-in power system of POWERCUBE1000 Cabinet is ~30/ 60KA255Volt~. Pass Fail Not Run Pass Fail Not Run Page 11 5.3: Check Color on front of SPD shall be GREEN, In case of RED/BLACK, it is declared to be faulty. Pass Fail Not Run Huawei Representative PTML Representative Name:_____________________ Name:_____________________ Signature:__________________ Signature:__________________ Date:______________________ Date:______________________ T04 Site Tagging and Labels. Objective: Verify that the Tagging and Labels of each new installed part /spare are proper. Result: PassFailNot Run Comment & Remark Prerequisites Check Tagging and Labels of each item for newly installed system / cabinet / cables etc. Procedure Expected result Result 1.1: The Tags must be pasted at the both ends of every 1. Labels / Tagging of cable inside ICC310 cabinet. Cables (AC / DC / Pass Fail Not Run communication / Alarm etc) 2.1: All installed ACB batteries are tagged with its battery 2. Labels of ACB Pass Fail Not Run cell number for each bank. Batteries and Alarm cables 2.2: All alarm cables for each cabinet alarm must be Pass Fail Not Run pasted with proper tagging separately inside BTS. Huawei Representative PTML Representative Name:_____________________ Name:_____________________ Signature:__________________ Signature:__________________ Date:______________________ Date:______________________ ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Page 12 T05 TEST PROCEDURES T05-01 Testing of Extended Alarms of POWERCUBE1000 from NOC Num of Test Case Name of test Case Preset Conditions Test Procedures Expected Results Test Results EAS Alarm Test # 1 Mains Failure 1. MF Alarm cable is extended to EMUA and ECC500 from both ends, 2. Rectifier is commissioned, 3. ECC500 is working. 1) Check float voltages on ECC500 screen. 2) Turn Off the Mains power supply from ACDB 3) Check MF Alarm red led observed at ECC500. 4) Call to NOC for MF Alarm verification 5) Restore Wapda supply and check float voltages again. Mains Failure alarm reported to NOC. Pass / Fail Num of Test Case Name of test Case Preset Conditions EAS Alarm Test # 2 Rectifier Major Alarm 1. Major Alarm cable is extended to EMUA and ECC500 from both ends, 2. Rectifier is commissioned, 3. ECC500 is working. 4. PSU’s are working Test Procedures 1) Check float voltages on ECC500 screen and Alarm LED is OFF. 2) Unplug & remove any 2 modules (PSU’s) from the rectifier. 3) Check alarm indication observed on ECC500 4) Call to NOC for Alarm verification 5) Connect the PSU’s again with rectifier and check Alarm indication OFF. Rectifier Major alarm reported to NOC. Pass / Fail Expected Results Test Results Num of Test Case Name of test Case Preset Conditions EAS Alarm Test # 3 Rectifier Minor Alarm 1. Minor Alarm cable is extended to EMUA and ECC500 from both ends, 2. Rectifier is commissioned, 3. ECC500 is working. 4. SPD is connected with mains supply Test Procedures 1) Check float voltages on ECC500 screen and Alarm LED is OFF. 2) Unplug & remove one SPD unit from the rectifier. 3) Check alarm indication observed on ECC500 4) Call to NOC for Minor Alarm verification 5) Connect the SPD unit again with rectifier and check Alarm indication OFF. Rectifier Minor alarm reported to NOC. Pass / Fail Expected Results Test Results Num of Test Case Name of test Case Preset Conditions EAS Alarm Test # 4 Low Battery Volt Alarm 1. Alarm testing if ACB battery bank voltages are Low. 2. To be test on battery discharging condition Test Procedures 1) 2) 3) 4) 5) 6) Adjust low battery voltage value to 51V from ECC500 Turn 3 ESMU-A off position Check voltage rating on ECC500 if decreased to 51V or bellow Check low battery voltage indication on ECC500 Confirm alarm from NOC Adjust low battery voltage value back to 51.0V from ECC500 ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Page 13 Expected Results Test Results Num of Test Case Name of test Case Preset Conditions Test Procedures Expected Results Test Results Num of Test Case Name of test Case Preset Conditions Test Procedures Expected Results Test Results Num of Test Case Name of test Case Preset Conditions Test Procedures Expected Results Test Results Num of Test Case Name of test Case Preset Conditions Test Procedures 7) Turn 3 ESMU-Aon confirm alarm disappears on ECC500 and NOC Low Battery alarm reported to NOC. Pass / Fail EAS Alarm Test # 5 Fan Failure alarm Temp Alarm testing if Temperature inside POWERCUBE1000 cabinet increased. 1) Open the door of rectifier cabinet and turn its fan off. 2) Call to NOC for Fan failure alarm verification. 3) Again restore power supply of Heat Exchange Unit. Fan Failure alarm reported to NOC. Pass / Fail EAS Alarm Test # 6 ESMU-A Failure Alarm ESMU-A in working condition while testing 4) Disconnect the positive power plug of any BMU 5) Check ESMU-A is turned off. 6) Check the ESMU-A Fail Alarm is reported at ECC500 & NOC. 7) Connect the positive plug of ESMU-A again and check ESMU-A working. ESMU-A Failure Alarm reported to NOC. Pass / Fail EAS Alarm Test # 7 Rectifier Door Open Alarm Alarm testing for Door of rectifier opens 1) Open the Door of Rectifier cabinet. 2) Check Rectifier Door open Alarm signal at ECC500 card and NOC 3) Call to NOC for Alarm verification. 4) Again close the door of Rectifier cabinet and check Alarm indication OFF. Rectifier door open Alarm reported to NOC. Pass / Fail EAS Alarm Test # 8 DC AirCon Fault Alarm 1. Aircon fault Alarm cable is extended to EMUA to ACB cabinet Expected Results Test Results 1) Check DC Aircon of ACB Cabinet is in working condition. 2) Turn Off the breaker of DC AirCon form Rectifier unit. 3) Check Aircon fault Alarm reports to EMUA and NOC. 4) Call to NOC for AirCon Fault Alarm verification. 5) Again Turn-On the breaker of DC Aircon and check Alarm indication OFF. AirCon Fault Alarm reported to NOC. Pass / Fail Num of Test Case Name of test Case Preset Conditions EAS Alarm Test # 9 High Temp. Alarm (ACB battery) 1. Temperature sensor available inside ACB Battery cabinet. Test Procedures 2. Temperature set point is adjusted to 30℃ 3. Temperature Alarm cable is extended to EMUA to ACB cabinet 1) Open the door of battery cabinet and find temperature probe inside. ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Page 14 Expected Results Test Results 2) Apply heat or rub the temp probe or decrease temp set point value in ECC500. 3) Check in ECC500 the increase in High Battery Temperature value 30℃ 4) Check alarm indication at ECC500 if the ACB cabinet temp is increased 5) Verify the alarm from NOC 6) Close the cabinet door and wait till temperature value gets normal.. Battery High Temperature Alarm reported to NOC. Pass / Fail ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Page 15 T05-02 Charging and Discharging of ACB Battery Banks Objective: Verify that the Batteries can be normally charged and discharged after the mains power supply. Result: PassFailNot Run Comment & Remark: Prerequisites The Discharging Test of ACB batteries. The mains power supply for the Rectifier POWERCUBE1000 A is working normally. The BTS Load is working normally. Procedure Expected result Result 1.1: PTML standard battery health check template Pass Fail Not Run 1. Health check of battery (attached) is attached with ATP documents for banks battery testing. Pass Fail Not Run 2.1: The ACB batteries are not leaked. Check for 2. Check ACB Battery for any leakage observed from joints of each cell or any leakage / damaged / acid corrosion observed inside cabinet. deformed etc. 2.2: The ACB battery is not deformed or de-shaped. Pass Fail Not Run 3. Voltage measurement of batteries 4. Battery heath check 5. Battery health check ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 3.1: Take the complete cell by cell voltage readings before commencing battery test. 4.1: Shutdown the AC Input supply of Rectifier to take batteries on load 5.1: Check the batteries feeding power to load after disconnection of AC power. 5.2: Take the complete bank & cell voltage readings after every 30 minutes. 5.3: Is tested battery backup is up to/greater than designed backup. (3hrs at the time of ATP) Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Pass Fail Not Run Page 16 T06 Documentation Required: Objective: All SIte related documentation and BOQ provided. Available Not Available 1. BOQ 2. Site Layout (approved / as built) Available Not Available 3. Power Parameters Available Not Available 4. Cables specifications Available Not Available ATP Document ACB Power Solution Ufone/Technical/ANO/DOC/03B/01 Page 17