FACULTY OF CHEMICAL & PROCESS ENGINEERING TECHNOLOGY BACHELOR OF OIL AND GAS FACILITY MAINTENANCE TECNOLOGY WITH HONOURS BVF 2213 OIL & GAS PROJECT MANAGEMENT TOPIC: OVERHAUL EFFLUENT PUMP AT PETRONAS CHEMICAL SDN BHD STUDENT NAME & ID: AISYA SHAHIZAH BINTI ABDUL RAZAK (VA21021) MUHAMMAD WIDAD ASFA SHAFIE (VA21031) MOHAMAD AQID SYAFAAT BIN AMRAN (VA21020) NURUL KHALEEDA BINTI MOHD KAMAL BOKORI (VA21032) LECTURER: TS.DR. NURUL SA’AADAH BINTI SULAIMAN DATE SUBMISSION: 31 JANUARY 2023 1 TABLE CONTENT NO. 1. CONTENT Background of Company - 2. Organization Chart - 3. Objectives Scope of works Work Flowchart Project Management - 6. Client Background BOM Description of Project - 5. Task Description Project Ooverview - 4. Introduction Contract Risk Assessment JSA Project Plan Summary WBS - Work Schedule 7. Scheduling 8. Resource of Project 9. Conclusion 2 PAGE INTRODUCTION OF COMPANY Rusoh Accurate Maintenance Sdn. Bhd a wholly - owned subsidiary of Rusoh Accurate is a company involved in the business of installation, maintenance, and restoration. Its related services such as repairs and overhaul services. Rusoh Accurate provides installation, maintenance, and restoration to repair and maintain the equipment that are essential to mitigate corrosion, increase safety and reliability, and reduce expenses long term. Rusoh Accurate Maintenance Sdn. Bhd laboratories are in Johor and Kuantan. Today, we operate throughout Malaysia, servicing projects ranging from small to large scale in equipment maintenance in oil and gas industry, processes of preparing, maintaining, and restoring equipment before, during, and after oilfield production. Our field of experience cover all types of equipment maintenance in oil and gas industry ranging from small equipment to factories. Through the use of our services, customer can realize substantial maintenance and repair cost savings and higher system uptime and reliability Our vision is to expand the branches of business conducted and strength the reputation achievement as a professional provider of quality maintenance service for our clients. To achieve the vision, our company provided a professional who are skilled in performing tasks more productively. Our mission is striving to perform tasks better and more efficiently that provide benefits to the company to ensure high risk work are carried out safely 3 CORPORATE DETAIL Company’s Name: Rusoh Accurate Maintenance Sdn Bhd Company Reg. No.: 1320254-T Corporate Status: Private Limited Company Date of Incorporation: 1 April 2019 Paid Up Capital: RM 4,000.00 Registered Address: 5430, Tingkat 1, Jalan J9 Fasa 6, Taman Melawati, Kuala Lumpur, 53100 Wilayah Persekutuan. Company Secretary: Rodhiah Management Services Business Address: C 01-15, Jalan Pulai Perdana 11/7, Taman Sri Pulai Perdana, 81300 Skudai, Johor Tel: 607 980 1987 Fax: 603 743 7779 Email: rusohaccurate@gmail.com Bankers: MAYBANK Malaysia Berhad, Taman Universiti, Skudai, Johor 4 DIRECTOR PROFILE Director’s Name : MOHAMAD AQID SYAFAAT BIN AMRAN NRIC Number : 940410-01-0085 Date of Birth : 10 April 1994 Home Address : 290, Jalan Pulai Jaya 17, Bandar Pulai Jaya, 81300 Skudai, Johor Certificate : 2011 - Sijil Pelajaran Malaysia 2012– 2014 - Diploma in Mechanical Engineering, Politeknik Port Dickson 2015 – 2018 – Bachelor of Oil and Gas Maintenance Facility with Honour Position : Managing Director Experience : 4 Years 2018 - 2019 - Technical Executive (Hull and Deck Machinery) 2020 – 2022- Assistant Ship Repair Manager LNG (Hull and Deck Machinery, Scaffolding, Painting Blasting) 5 ORGANIZATION CHART Work descriptions Position Duties Manages and coordinates the activities of designated projects Project Manager/Director with a specific timeframe and funding amount to ensure that goals or objectives of the project are accomplished. Project Leader Supervisor Instrument Technician Helper Conduct and give a briefing in toolbox meeting, informal safety meeting held before the start of a work shift. Overseeing plant projects and ensuring that teams meet production projections. Install, repair, and maintain assorted plant control and process monitoring instrumentation. Supplying or holding materials or tools, and cleaning work area and equipment. 6 PROJECT OVERVIEW Rusoh Accurate Maintenance Sdn. Bhd a wholly - owned subsidiary of Rusoh Accurate is a company involved in the business of installation, maintenance, and restoration. Our company Project is Overhaul 1 unit of Effluent Pump. Our client is Petronas Chemical Sdn Bhd. This project is a one-day project. The supervisor, Work Leader, Instrument Tech, and Helper are assigned to do the overhaul of 1-unit effluent pump at Petronas Chemical Sdn Bhd. At the first phase, Supervisor do a planning. In the phase is consistent with an analytical and identify the product and product requirement. Cost analysis is also included in this phase. Phase 2 at the site work, Instrument Tech Start to do the overhaul. It starts from Removal of the effluent pump casing until installation all of the new parts to replace the old part. The last phase is Testing and running. After all the Installation and replacement, the effluent pump is ready to use. This project cost is RM 21,540.00. CLIENT BACKGROUND FULL NAME OF CLIENT COMPANY : Petronas Chemical Sdn Bhd. CLIENT COMPANY PERMANENT ADDRESS : Lot 3633, Kawasan Bukit Tengah KM 105, Jalan Kuantan- Kuala Terengganu 24300 Kertih, Kemaman Terengganu Darul Iman NO. TELEPHONE : + 609 830 5648 FAX : + 609 830 5618 LOCATION OF THE PROJECT Petronas Chemical Sdn Bhd Base COST OF PROJECT RM19,627.00 7 BILL OF MATERIALS Bill Description Part code 1. Gasket N/A Per unit 1 200.00 2. Washer N/A Per unit 1 200.00 3. Screw N/A Per unit 1 20.00 4. Nut N/A Per unit 1 40.00 6. Bolt N/A Per unit 1 40.00 7. Stud N/A Per unit 1 30.00 8. Key N/A Per unit 1 15.00 9. Oil Seal N/A Pe unit 1 200.00 10. Lubricant Oil N/A Per unit 1 50.00 11. Grease N/A Per unit 1 250.00 12. Impeller 211 Per unit 1 800.00 13. Bearing Sleave 529.01 Per unit 1 300.00 14. Bearing Sleeve 529.01 Per unit 1 300.00 15. Line Shaft 211 Per unit 1 200.00 16. Shaft Seal Ring 420 Per unit 1 500.00 17. Insert Sleave 932 Per unit 1 400.00 18. Oil Level Tube 641 Per unit 1 1200.00 19. Impeller ring N/A Per unit 2 100.00 20. Tube 707.01 Per unit 1 88.00 21. Impeller Nut 2 70.00 922 Total Cost Unit rate Per unit Quantity Price RM 5003.00 8 WORKERS Position Wages Total days Total Wages Work Leader RM 88.00/hour 1 days RM 704.00 Helper RM 70.00/hour 6 days RM 3360.00 Supervisor RM 150.00/hour 4 days RM 4800.00 Instrument Technician RM 120.00/hour 6 days RM 5760.00 Total Cost RM 14,624.00 PROJECT Project Overhaul Effluent Pump Project Reference P1-2710a Client Petronas Chemical Sdn Bhd Date 20/1/2023 Place Petronas Chemical Sdn Bhd Base EQUIPMENT No Name Of Equipment 1 Wrenches 2 Seat puller rods 3 Seat puller heads 4 Pony rod clamps 5 Hydraulic hoses 6 Hand pumps 7 Grease guns 8 Lifting subs 9 Foot pumps Total Estimated Project Cost: RM 19,627.00 9 DESCRIPTION OF PROJECT OBJECTIVES Rusoh Accurate Sdn Bhd hereinafter referred to as ‘PGB’ intends to enter into a contract to overhaul 1 Unit of Effluent Recycle Pump P1-2710a For Utilities Kertih, Kemaman, Terengganu Darul Iman. Our experts provide our clients with personal support in every phase of the project, from design and configuration, through to commissioning and maintenance. Our systems and product solutions set new standards in terms of technical performance, cost efficiency, security standards, and durability in all applications relating to Effluent Recycle Pump. SCOPES OF WORK 1. To mob/de-mob pump from UK to contractor workshop. 2. To produce ‘As Found Report’ after 5 working days of initial pump inspection which include but not limited to disassembly, record all findings with picture, record as found clearance, recommendation of repair & overhaul schedule. 3. To submit repair, work procedure, QAQC procedure & acceptance criteria prior execution if necessary/required. 4. To perform incoming shaft run out check. 5. To perform impeller balancing. 6. To perform cleaning of all pump parts (blasting/grinding/polishing/power brush). 7. To perform NDT (Dye Penetration) if necessary/required. 8. To perform a 5-point check. 9. To reassemble pump & record all clearances. 10. To perform 3 coat system painting (if necessary/required). 11. To supply required spare parts for overhaul activity. 12. To replace damaged pump parts. 13. To prepare all required special tools necessary to perform the work. 14. To carry out performance test if necessary/required. 15. To reinstate the pump at site. 16. To stand by for pump test run. 17. To produce detailed overhaul report (close out report) stating general findings or observations pertaining to the works. 10 WORK FLOWCHART START All tools needed were prepared. All part has been cleaned. Rusty and failure parts were checked. No Inspection approved? Have not approved Yes Material and parts have been purchased. The consumable parts were repaired and replaced. Recycle pump have been tested and ran smoothly. FINISH 11 PROJECT MANAGEMENT CONTRACT FOR PROJECT MANAGEMENT SERVICES Overhaul 1 unit of Effluent Pump This Contract is made this 20 day of JANUARY in the year 2023 between (day) (Owner) (month) (year) (street) (city) the Rusoh Accurate Maintenance Sdn.Bhd, C 01-15, Jalan Pulai Perdana 11/7, Taman Sri Pulai Perdana, 81300 Skudai, Johor (State) (Zip Code) hereinafter called Rusoh Accurate Maintenance Sdn.Bhd and Petronas Chemical Sdn Bhd (Owner’s Project Manager) Lot 3633, Kawasan Bukit Tengah,KM 105, Jalan Kuantan-Kuala Terengganu,24300 Kertih, Kemaman ,Terengganu Darul Iman(street) (city) (Zip Code) (State) The Petronas Chemical Sdn Bhd, hereinafter referred to as The Petronas Chemical Sdn Bhd, will offer the Project Management services required to execute the Basic and Extra Services outlined below at Overhaul 1 unit of Effluent Pump. Through the Project planning, Rusoh Accurate Maintenance Sdn. Bhd is permitted to provide the services required by this Contract. The Project Manager may be authorised to provide services for the Overhaul 1 unit of Effluent Pump following the Overhaul, at which point a mutually agreed upon amendment to this Contract will be executed between the client and the Project Manager. Rusoh Accurate Maintenance Sdn. Bhd. will be paid by Petronas Chemical Sdn. Bhd. for rendering the services needed by this Contract for the maintenance and troubleshooting of pumps in the oil and gas plant. IN WITNESS WHEREOF, the respective authorised officers of Petronas Chemical Sdn Bhd and Rusoh Accurate Maintenance Sdn.Bhd have caused the execution of this Contract. Rusoh Accurate Maintenance Sdn.Bhd (Manager) Petronas Chemical Sdn Bhd(Manager) Qied (Mohamad Aqid Syafaat) Bob Helmie (Bob Helmie) Date 20/01/2023 Date 20/01/2023 12 PROJECT PLAN SUMMARY Rusoh Accurate Maintenance Sdn. Bhd has gone over the work schedule that needs to be completed at the plant for a duration of 7 days in order to perform overhaul effluent pump at Petronas Chemical Sdn Bhd. The first of the three steps are depicted in the prepared table. The "Early Planning" phase will include a first meeting with the client when the usage of cash and preparation for maintenance work will be discussed. The overhauling of the effluent pump, which is the second phase in the service process, takes seven days to complete, as shown in the table. Over the next seven days, the work will be done inside the Petronas Chemical Sdn Bhd site. The effluent pump is given one more inspection and test run in the closing days of that process, which is referred to as the final phase. In this report, a table has been built up to give the business more details regarding the process of overhauling the effluent pump. The repair and troubleshooting on the pump at the Petronas Chemical Sdn Bhd will be successfully carried out by Rusoh Accurate Maintenance Sdn Bhd, who will make sure that the task is done. 13 RISK ANALYSIS LIKELIHOOD VALUE LIKELIHOOD(L) XSEVERITY(S) = RISK(R) VALUE SEVERITY RISK ASSESSMENT RESULT RANKING SEVERITY LIKELIHOOD 3 2 1 Risk Ranking What to do? High Immediate attention and action required. Shall consider whether to eliminate or modify the activity. (Stop the Score Unlikely 1 Minor 1 3 9 6 3 6–9 (H) work.) Likely 2 Moderate 2 2 6 4 2 3–4 Medium Specific monitoring procedures required; management responsibility must be specified. (M) Shall consider what can be done to eliminate the risk to prevent any. negative outcomes. Frequent 3 Catastrophic 3 1 3 2 1 1–2 Low (L) JOB SAFETY ANALYSIS 14 Manage through routine procedures. Can proceed with the activity as planned NO 1 Risk Description Preparing for every tools Impact Impact Probability Priority Description Level Level Level 1. Physical To hazard Ndt Dye Penetration test wear full Personal Protective Equipment (PPE) 1 2 Mitigation Notes 2 2 Headaches, nausea Test personnel should be or tightness or pain aware of job-related hazards in the chest. and safety precautions about 3 3 9 Prolonged breathing of penetrant vapors, emulsifier vapors or solvent remover vapors. 3 4 Cleaning the impeller 1. Hand injury 2. Eye injury 3 Removal casing, motor and capacitor, 1. Hand injury impeller, shaft. Shaft sleeve, wearing 2. Eye injury ring, all bearings and sleeve 3. Spark 4. Chemical burn 15 3 2 3 6 9 Use full Personal Protective Equipment 1. Ensure set screws are loose. 2. Ensure pump has cooled and Use full Personal Protective Equipment. 5 Noise and vibration Hearing impairment Vibration injury 3 6 7 8 9 Electric shock Pump Pressurized Installation and replacement Housekeeping 3 9 1. Body burn 2. Electrocution 3. Death Regular equipment familiarization using a stationbased training plan Personal Protective Equipment (PPE) must be always worn (ear plugs) 1. 2 2 4 3 3 9 2 3 6 1. Steam Escape with contaminants 2. Jets of Hot Liquid 1. Physical hazard 1. Slipping on greasy, wet, or dirty surfaces. 2. Physical hazard 16 1 2 2 keep your hands clean and dry when doing any electrical work. Be sure to wear full Personal Protective Equipment (PPE) and safety clothes in a dry condition. 2. Ensure electricity supply is shut off and pump driver locked out 1. Ensure pump has cooled sufficiently and pipework drained before attempting disconnection. 2. Check external casing temperatures. 3. Open bolts slowly To wear full Personal Protective Equipment (PPE) To wear full Personal Protective Equipment (PPE) WORK BREAKDOWN STRUCTURE WBS OVERHAUL 1 UNIT EFFLUENT RECYCLE PUMP 1)PLANNING 2)PREPARATION TOOLS 3)CLEANING ALL PARTS 4)INSPECTION 5)IDENTIFY AND PURCHASE MATERIAL/PARTS BLASTING/GRINDING /POLISHING 6)REPAIR/REPLACE THE CONSUMABLE PARTS 8)TESTING AND RUN 7)INSTALLATION ALL PARTS CHECK THE RUSTY AND FAILURE PART COATING AND PAINTING PARTS NDT INSPECTION (DYE PENETRATION) ALIGNMENT 17 WORK SCHEDULE Task Day PHASE 1: PLANNING Analytical and identify production 1 Identify product requirement Cost effectiveness analysis Preparation tools include special tools PHASE 2: Site Work Removal casing Removal motor & capacitor Removing the impeller Cleaning the impeller Inspect its eye, vanes, shrouds, wearing rings, passages, hub and other parts Removing the shaft 2 Remove shaft sleeve Inspection alignment NDT Dye Penetration test Inspection of crack, corrosion, rusty, and failure Removing wearing rings from casing or impeller Inspection the crack, corrosion, rusty and failure Removing all bearings Removing sleeve PHASE 3: Installation and Replacement Cleaning all parts BLASTING/GRINDING/POLISHING Replace the new motor & capacitor Installation the new shaft Install the new line shaft Alignment the shaft Replace the new impeller 3 Replace the new sleeve Install new circlip Replace the set of all bearings Coating and painting Replace the new casing Instrument Tech Instrument Tech Instrument Tech Instrument Tech, Supervisor Instrument Tech, Supervisor Instrument Tech Instrument Tech, Supervisor Instrument Tech, Helper Instrument Tech, Helper Install new: Gasket, Washer, Screw, Nut Bolt, Stud, Key Oil Seal, Lubricant Oil, Grease Instrument Tech, Helper PHASE 4: Testing and run Testing and run 1 18 Resources Supervisor Supervisor Work Leader Work Leader Instrument Tech Instrument Tech Instrument Tech Instrument Tech, Helper Instrument Tech, Helper Instrument Tech, Helper Instrument Tech, Helper Instrument Tech Instrument Tech Instrument Tech Instrument Tech, Helper Instrument Tech, Helper Instrument Tech, Helper Instrument Tech, Helper Instrument Tech, Helper Instrument Tech, Helper Instrument Tech, Helper Instrument Supervisor Tech, Helper, PROJECT SCHEDULLING 19 20 21 RESOURCE OF PROJECT I. Pumps - Restoration and Efficiency Enhancement, www.belzona.com, 20 January 2023 https://www.belzona.com/en/applications/pumps.aspx II. Pump Maintenance Tools: Oil & Gas Industry, summit, 20 January 2023 https://www.summitsalesusa.com/pump-tools III. Maintenance & repair of Pumps: Centrifugal, vacuum, multistage, Maintenance Partners, 7 August 2020, 20 January 2023 https://maintenancepartners.com/en/pumps/ IV. Maintenance, Repair, Overhaul: End market: Oil & Gas, chempoint, 20 January 2023 https://www.chempoint.com/en-emea/industries/maintenance-repair-overhaul/oil-and-gas V. Step-by-step guide for overhauling centrifugal pumps: Sintech, Sintech Pumps India, 29 May 2020, 20 January 2023 https://www.sintechpumps.com/pumps/centrifugal-pumps/overhauling-of-centrifugalpumps-step-by-step-guide/ 22 CONCLUSION Point of fact, Rusoh Accurate Maintenance Sdn. Bhd. will offer exceptional service and highquality solutions through our professional knowledge and commitment to any maintenance and troubleshooting task, which should be approached with an open mind and a sincere desire to identify and resolve the problem. Excellent observational and verbal communication skills are needed for all of these activities. 23