Uploaded by luke schafer

BrarJ.4007A A3.pdf-1

advertisement
CPCCBC4007A - Assessment 3 Answer
sheet
Please type your answers in black font. (Calibri 12 point)
STUDENT DETAILS
Student Name: Jaspreet Singh Brar
TAFE ID: 880850451
UNIT AND ASSESSMENT DETAILS
Unit Number: CPCCBC4007A
Assessment No: 3
LA Number: LA023684
DECLARATION
I hold a copy of this assessment
I have completed all parts of the assessment.
I hereby certify that no part of this assessment or product has been copied
from any other student’s work or from any other source except where due
acknowledgement is made in the assessment.
Student’s signature: _________________________________________
(Electronic Signature is accepted)
Note: OTEN has the right to reject your assessment if the above declaration has not been
completed.
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Edition number 5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW), Version 1, August 2018
1
What you have to do
Refer to Project 3 to answer the following questions.
Please type your answers in black font. (Calibri 12 point)
Questions
1. Prepare a site establishment plan for the site documented in Project 3. Your
plan can be ruled or sketched but must be to a suitable scale. The
components shown on the plan must include:






Security
Access
Signage
Environmental considerations
Site accommodation – assume a maximum of 30 people on site on any given
day
Services
Note: there is a contour plan of the site at the end of this assignment which you
will need for the preparation of your site establishment plan.
Ans:
2
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Ed5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW – WSI), Version 1, August 2018
2. Your building organisation is a small to medium sized company specialising in
commercial projects in the range $2 million to $5 million. The company
typically has 6 projects underway at any time and is made up of the following
personnel:
 Construction manager
 Construction supervisors (2)
 Site managers (6)
 Estimator (1)
 Cadet estimator (1)
 Contracts/material supply officer
 Office manager
Prepare an organisational chart for your company.
Ans:
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Ed5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW – WSI), Version 1, August 2018
3
3. Your building company is the successful tenderer on Project 3. You have been
advised to expect to sign contracts in the near future and to advise a
commencement date for construction. Given the design of the project and
the early need for precast concrete panels on the site and the fact that you
are unable to let a sub-contract until the Head Contract is in place, you are
hesitant to advise a date without some careful consideration and planning.
The process for securing the panels on site for erection is:
Supply order
↓
Workshop plans (3 weeks) [Preparation]
↓
Approval of plans (1 week) (Review)
↓
Manufacture (6 weeks)
↓
Inspection of Panels prior to delivery (1 week)
↓
Delivery
↓
Erection of precast Panels
The onsite activities while the steel is being prepared are:
Site establishment (1 week)
↓
Bulk excavation (1 week) [The critical path period, but ongoing]
↓
Bore and pour piers (1 week) [The critical path period, but ongoing]
↓
Trench excavation and pour ground beams (1 week) [The critical path period,
but ongoing]
Nominal activity durations have been shown, which may be part only of the
activity duration which lies on the critical path. I.e. the activity may be on the
critical path.
Calculate the commencement date for the project in days, from the signing of
the Head Contract. Provide a justification for the delay to be provided to the
client
4
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Ed5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW – WSI), Version 1, August 2018
Ans:
Tasks
Duration
Sign sub contracts
5 days
Supply Order
1 day
Workshop plans
Pre task
Start date
Finish date
22/03/2021
26/03/2021
1
29/03/2021
29/03/2021
15 days
2
30/03/2021
19/04/2021
Approval of plans
5 days
3
20/04/2021
26/04/2021
Manufacture
30 days
4
27/04/2021
07/06/2021
Inspection of panels
prior to delivery
5 days
5
08/06/2021
14/06/2021
Delivery
1 day
6
15/06/2021
15/06/2021
Erection of pre cast
panels
1 day
7,11
16/06/2021
16/06/2021
Site establishment
5 days
1
29/03/2021
02/04/2021
Bulk excavation
5 days
9
05/04/2021
09/04/2021
Bore and pour piers
5 days
10
12/04/2021
16/04/2021
Trench excavation
and pour ground
beam
5 days
11
19/04/2021
23/04/2021
According to the critical task analysis, we need 40 working days to commence to
erect precast panels. And because we need 11 weeks to manufacture panels
before erection and we only need 4 weeks to prepare the site before erection of
panels, so we need to wait 7 weeks until the panels are delivered.
4. For the factory unit development detailed in Project 3, you are required to
produce a construction schedule/plan in the following formats:
a. A critical path analysis
A Gantt chart (bar chart) for the entire project
Ans:
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Ed5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW – WSI), Version 1, August 2018
5
Tasks
Pre
task
Supply precast wall
panel order
Start date
Finish date
1 day
28/06/2021
29/06/2021
Workshop plans
1
15 days
29/06/2021
20/07/2021
Approval of plans
2
5 days
20/07/2021
27/07/2021
Manufacture
3
30 days
27/07/2021
07/09/2021
Inspection of panels 4
prior to delivery
5 days
07/09/2021
14/09/2021
Delivery
panels
1 day
14/09/2021
15/09/2021
Erection of precast 10,11 3 days
panels
15/09/2021
20/09/2021
Fix reinforcement
5 days
20/09/2021
27/09/2021
1 day
27/09/2021
28/09/2021
30 days
28/09/2021
09/11/2021
Erect ground floor 15
wall panels
4 days
09/11/2021
15/11/2021
Formwork of first 16
floor concrete and
stairs
2 days
15/11/2021
17/11/2021
Concrete pour and 17
cure
35 days
17/11/2021
05/01/2022
Erect first wall panels 18
5 days
05/01/2022
12/01/2022
Erect roof trusses
19
3 days
05/01/2022
17/01/2022
Roof
plumbing 20
(gutter
and
downpipe)
2 days
12/01/2022
19/01/2022
of
Place and
concrete slab
wall 5
12
finish 13
Cure slab
6
Duration
14
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Ed5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW – WSI), Version 1, August 2018
Install roof insulation 21
and attach roof
5 days
17/01/2022
26/01/2022
Install windows and 22
external doors
5 days
19/01/2022
02/02/2022
Plumbing rough-in
23
5 days
26/01/2022
09/02/2022
Electrical rough-in
24
5 days
02/02/2022
16/02/2022
area 25
2 days
09/02/2022
18/02/2022
Wet
waterproofing
Fix internal innings
26
5 days
02/02/2022
25/02/2022
Joinery and fit-out
27
5 days
16/02/2022
04/03/2022
Wall and floor tiling
28
5 days
18/02/2022
11/03/2022
Painting
29
7 days
25/02/2022
22/03/2022
Plumber final fit-out
30
5 days
22/03/2022
29/03/2022
Electrician final fit- 30
out
5 days
22/03/2022
29/03/2022
Install carpet
30
5 days
04/03/2022
29/03/2022
Final painting
33
2 days
11/03/2022
31/03/2022
Driveway crossover 34
and
outdoor
concrete work
15 days
22/03/2022
21/04/2022
Complete
landscaping
erect fences
4 days
29/03/2022
27/04/2022
35
and
b. A critical path analysis and programme nominating the shortest
construction duration in weeks
Your initial planning must include the following:



List of tasks to complete the project
Duration of each task/activity
Start and end dates of each task/activity
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Ed5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW – WSI), Version 1, August 2018
7
Note. The critical path maybe shown superimposed on the Gant Chart
Programme.
Ans: The shortest construction duration is 44 weeks.
5. Following the pouring of the footing beams, concrete testing reveals the
concrete falls short of the design strength by 5MPa. Work on the site is
suspended until core samples are taken from the footings and further testing
confirms compliance with the specified strength.
Unfortunately though, you have lost 4 weeks progress from the construction
plan, and you are unable to claim an extension of time for this under the
contract terms.
Revise the construction plan to reflect the 4 weeks on construction time lost
and make adjustments to the plan outlining how you intend to increase
production to meet the contracted date of practical completion.
8
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Ed5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW – WSI), Version 1, August 2018
Ans: I have divided the piling work for both buildings and the ground-floor
construction into two separate teams in order to make up again for 4-week
delays to the program's critical route. These tasks, which are on the project's
critical path, can be completed concurrently by two teams working on two
buildings at the same time. This is a considerably better conclusion than the prior
scheme, when work on one structure was planned to begin after the second
structure had been finished.
One team of employees can still be assigned to tasks that aren't on the project's
critical path, such as Level 1 construction, roof work, and fit out tasks, because
their durations are not crucial to the actual completion deadline.
Due to the increase of resources, which will speed up the last phase of work
before practical completion, the time of external works including stormwater,
parking lot, and landscaping have been shortened.
The tasks that have been adjusted are:






Columns – steel reinforcement & formwork
Slab on ground - steel reinforcement & formwork
First Floor (Mezzanine) - steel reinforcement & formwork
Roof – Framing & sheeting
Carpentry – Internal framing
External Works – Formwork, steel & landscaping
NOTE: This is a competency-based assessment. You will receive a result of Satisfactory
or Unsatisfactory. This means that you must satisfactorily complete each question (or
part thereof) to meet the competency requirements set out in the training package. If you
do not meet the competency requirements, you will need to resubmit your assessment
until competency is achieved.
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Ed5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW – WSI), Version 1, August 2018
9
Checklist
I have:

named my file appropriately.

surname_Your first initial.Unit number_Assessment number (e.g.
Smith S.4018A_A3)

completed the Assessment cover sheet

submitted my assessment report as a single combined PDF file.

answered all questions in the manner described

clearly identified my answers

saved a copy of the assessment on my computer

checked spelling, grammar and punctuation

presented my own work, used only my own words, except where
cited, and

followed the presentation guidelines found on the OLS
If you require clarification, please contact your teacher at OTEN to discuss
10
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Ed5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW – WSI), Version 1, August 2018
LA023684, Answer sheet, Assessment 3, CPCCBC4007A, Edition number 5
© New South Wales Technical and Further Education Commission, 2018 (TAFE NSW), Version 1, August 2018
11
Download