Uploaded by Darwin Kishore

package-equipment-plc-control-system-specification

advertisement
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
1/18
Client Doc. No.
Client
Project
Location
Unit
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
PACKAGE EQUIPMENT PLC CONTROL SYSTEM SPECIFICATION
Information contained in this document is the work product of one or more legal entities of the Technip Energies N. V. business unit and
embodies confidential and proprietary information of the applicable entity and/or its client. Use of this information is restricted in
accordance with conditions specified by the contract. Technip Energies N. V. and its affiliates disclaim any and all liabilities for any
changes or modifications to this document which are made by any person other than the entity that issued the document under the
applicable client contract.
THIS DOCUMENT IS UNCONTROLLED WHEN REPRODUCED
Hugo
A
REV.
11-Oct-2022
2022.10.11
14:01:04-05'00'
Swetha Thimmaiah
2022.10.11 14:07:29 06'00'
Digitally signed
by Victor Vazquez
Date: 2022.10.11
15:45:53 -05'00'
ISSUED FOR INFORMATION
H. GARCIA
S. THIMMAIAH
V. VAZQUEZ
STATUS
WRITTEN BY
(NAME & SIGN)
CHECKED BY
(NAME & SIGN)
APPROVED BY
(NAME & SIGN)
DATE
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
2/18
Client Doc. No.
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
Client
Project
Location
Unit
REVISION LOG
REV.
SECTIONS / PAGE NO.
CHANGE DESCRIPTION
HOLD STATUS
HOLD NO.
REV.
PAGE NO.
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
DESCRIPTION OF HOLD
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
3/18
Client Doc. No.
Client
Project
Location
Unit
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
TABLE OF CONTENTS
1.
GENERAL........................................................................................................................................ 4
1.1
1.2
Purpose ........................................................................................................................................... 4
Project Overview .............................................................................................................................. 4
2.
REFERENCE DOCUMENTS AND SPECIFICATIONS .................................................................... 4
3.
ACRONYMS .................................................................................................................................... 5
4.
DEFINITIONS................................................................................................................................... 6
5.
REFERENCE DOCUMENTS ........................................................................................................... 7
5.1
5.2
5.3
Codes and Standards ...................................................................................................................... 7
General Codes and Standards ..................................................................................................... 7
Exceptions and Deviations ............................................................................................................ 8
6.
GENERAL REQUIREMENTS .......................................................................................................... 8
6.1
6.2
6.3
Local Conditions .............................................................................................................................. 8
Standard Products ........................................................................................................................ 8
Proven Systems ............................................................................................................................ 9
7.
PLC SYSTEM CONFIGURATION.................................................................................................... 9
8.
PACKAGE ROTATING MACHINERY CONTROLS PHILOSOPHY............................................... 10
9.
ETHERNET SWITCH ..................................................................................................................... 12
10.
HUMAN MACHINE INTERFACE (HMI) ......................................................................................... 12
11.
COMMUNICATION REQUIREMENTS ........................................................................................... 12
12.
CYBERSECURITY ......................................................................................................................... 13
13.
ELECTRICAL REQUIREMENTS ................................................................................................... 13
14.
PROGRAMMING ........................................................................................................................... 14
15.
OPERATING MODES .................................................................................................................... 14
16.
POWER FAILURE AND RESTORATION ...................................................................................... 14
17.
TESTING........................................................................................................................................ 15
18.
COMMISSIONING, STARTUP, AND OPERATIONAL RELIABILITY ............................................ 17
19.
DOCUMENTATION........................................................................................................................ 17
20.
SHIPPING AND HANDLING .......................................................................................................... 18
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
4/18
Client Doc. No.
Client
Project
Location
Unit
1.
GENERAL
1.1
Purpose
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
This specification, along with the reference documents shown in Section 2, describe the requirements of
the PLC System for Packaged Equipment provided by Vendors for the Commonwealth LNG Project in
Cameron Parish, LA.
1.2
Project Overview
Commonwealth LNG proposes to construct a facility in Cameron Parish, Louisiana located approximately
29º46’ North and 93º21’ West on a leased property at the entrance to the Calcasieu River. The Facility
will receive domestically produced natural gas, liquefy the natural gas into LNG, temporarily store the
produced LNG, and periodically load the LNG into LNG carriers.
The basic information of Commonwealth LNG project is the following:
2.
•
Client:
Commonwealth LNG, LLC
•
Official Project Name:
Commonwealth LNG FEED
•
Plant Location:
Cameron Parish, Louisiana, USA
•
Contractor:
Technip Energies
REFERENCE DOCUMENTS AND SPECIFICATIONS
The following documents are referred to in this specification. Packaged Equipment shall follow
requirements in those documents were referred to in this document.
Technip Doc. No.
Specification Title
078051C-000-JSS-1510-0003
Control Panels Specification
078051C-000-JSS-1600-0001
Electrical Basis of Design
078051C-000-JSS-1600-0002
Equipment Specification for Electrical Requirements for
Packaged Equipment
078051C-000-JSS-1010-0001
Expander Compressors With Magnetic Bearings (API 617,
Parts 1 & 4) Specification
078051C-000-DW-1510-0001-1 to 10
ICSS Architecture Block Diagram
078051C-000-JSS-1510-0005
Integrated Control and Safety System (ICSS) Specification
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
5/18
Client Doc. No.
Client
Project
Location
Unit
3.
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
078051C-000-JSS-1010-0010
Machine Monitoring System Specification
078051C-000-JSD-0000-0501
Project Facilities Basis of Design
078051C-000-JSS-1500-0001
Packaged Equipment Instrumentation Specification
078051C-000-JSS-1510-0002
Remote Instrument Enclosure (RIE) Specification
078051C-000-JSS-1530-0001
Telecommunication Specification - Plant Security Telecom
Design
ACRONYMS
The following acronyms are used in this specification.
API
American Petroleum Institute
BPCS
Basic Process Control System
CCR
Central Control Room
FAT
Factory Acceptance Test
FGS
Fire and Gas System
ICSS
Integrated Control and Safety System
IEC
International Electrotechnical Commission
I/O
Input / Output
IP
Internet Protocol
ISA
International Society of Automation
NEMA
National Electrical Manufacturers Association
NFPA
National Fire Protection Association
OPC
Open Platform Communication
PLC
Programmable Logic Controller
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
6/18
Client Doc. No.
Client
Project
Location
Unit
4.
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
RIE
Remote Instrument Enclosure
RTU
Remote Terminal Unit
SAMA
Scientific Apparatus Makers Association
SIL
Safety Integrity Level
SIS
Safety Instrumented System
TCP/IP
Transmission Control Protocol/Internet Protocol
UL
Underwriters Laboratory
UPS
Uninterruptible Power Supply
VAC
Volts of Alternating Current
VDC
Volts of Direct Current
DEFINITIONS
Following is the list of terms and their definitions applicable in this specification
CLIENT/COMPANY:
Commonwealth LNG
CONTRACTOR:
The individual, firm or company undertaking to supply services, plant, or
equipment to which this document applies.
SHALL:
A mandatory term – No change is permitted without written approval from
the CLIENT/COMPANY.
VENDOR:
The party that carries out and/or supplies equipment, materials, goods
and/or services for the project. The wording VENDOR is a synonymous of
the term SUPPLIER.
LNG FACILITY:
All equipment on site including: the inlet feed gas receiving facilities; LNG
Plant; LNG Marine Facilities; and all other associated facilities required to
receive, treat, liquefy, store and export LNG.
LNG PLANT:
The Gas Pre-treatment and LNG liquefaction process trains (Process
Area).
GOODS:
Equipment/ Materials/ Spares, etc. to be supplied under the contract
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
7/18
Client Doc. No.
Client
Project
Location
Unit
SERVICES:
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
Engineering Design, Project Management, Coordination, Procurement,
and Quality Assurance Services.
5.
REFERENCE DOCUMENTS
5.1
Codes and Standards
All design, materials, construction and performance of the PLC Systems shall conform to the latest issue
of the relevant internationally recognized codes and standards.
In general, the following codes/ standards should be followed in the design of the facilities.
1.
National (US) and local (Louisiana) Laws, Decrees, Regulations, and Protocols
2.
International Codes and Standards
3.
Published Industry Codes and Standards
4.
Company Standards, Guidelines and Philosophies
5.
Guidelines from the international finance institutes
6.
Commonwealth Basis of Design Documents
7.
Project Job Specifications
In the event of apparent technical conflict, Contractor and Company will come to a common resolution.
Applicable codes and standards for a dedicated system, not included in the above-mentioned document,
shall be included in the dedicated system specifications.
Following is the list of Codes and Standards applicable for the design, manufacture, inspection, testing
and installation of all equipment and systems covered under this specification.
5.2
General Codes and Standards
API RP 500
Recommended Practice for Classification of Locations for Electrical
Installations at Petroleum Facilities Classified as Class I, Division I
and Division 2
API STD 617
API STD 670
Axial and Centrifugal Compressors and Expander-compressors
Machinery Protection Systems
IEC 61508
IEC ICS6
Functional Safety of Electrical / Electronic / Programmable Electronic
Safety Related System
Functional Safety - Safety Instrumented Systems for the Process
Industry Sector
Enclosures for Industrial Systems
NFPA 70
National Electric Code
IEC 61511
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
8/18
Client Doc. No.
Client
Project
Location
Unit
5.3
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
NFPA 70E
Standard for Electrical Safety in the Workplace
NFPA 496
Purged and Pressurized Enclosures for Electrical Equipment
SAMA PMC 33.1
Electromagnetic Susceptibility of Process Control Instrumentation
Exceptions and Deviations
Exceptions to and deviations from this specification shall not be implemented without written approval
from Contractor and Company.
Compliance by the Vendor with the requirements of this document does not relieve Vendor of the
responsibilities of proper mechanical, electrical and software design to ensure operability at specified
service conditions.
Where any conflict exists between the above codes, the more stringent code shall be followed.
Requirements specifically stated here-in shall take precedence over the codes.
Any omission or ambiguity shall be brought to attention and resolved to the satisfaction of the parties
involved.
In the event a conflict cannot be resolved, the Vendor shall bring the matter to the CONTRACTOR’s
attention. The Vendor shall outline the conflict, the implications of the conflict, and Vendor’s suggested
resolution to the conflict.
6.
GENERAL REQUIREMENTS
6.1
Local Conditions
The main local conditions at the Plant location are summarized in the Project Facilities Basis of Design.
Technip Document Number 078051C-000-JSD-0000-0501.
6.2
Standard Products
Package Equipment PLC shall consist of hardware, system software, and firmware that can be configured
to meet the stated requirements. Use of novel prototype equipment or software is unacceptable.
Equipment provided as part of the systems shall be the latest version or revision level currently available
for sale from the original Manufacturer at the time of the purchase order award.
Systems hardware and software shall be modular and designed with flexibility for future expansion, this
shall be achieved by straight addition, not requiring any mayor modification to existing hardware and
software configuration. Configuration software shall be implemented in a manner that requires no
modification to the system operating software. The system’s standard operating software shall not be
modified to meet the project requirements.
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
9/18
Client Doc. No.
Client
Project
Location
Unit
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
All necessary software licenses shall be provided enabling the rights to exercise the use of all relevant
and applicable software.
All system components shall have electromagnetic interference (EMI) immunity as per SAMA PMC 33.1.
6.3
Proven Systems
All hardware, software and firmware supplied with the Package Equipment PLC shall be commercially
available and field-proven prior to the Purchase Order award. Field-proven is defined as successful
operation of a standard product at a field installation of similar application for at least two (2) or more
years.
It shall be possible for Buyer to verify the field proven status of all system equipment. This requirement
does not apply to customized application software developed for this project.
All equipment supplied for the project shall have guaranteed support of all system hardware and firmware
with spare parts and service for the minimum plant design life of 25 years. All proposals shall include the
perceived operating life of the System.
7.
PLC SYSTEM CONFIGURATION
Vendor shall furnish the PLC System in accordance with this specification. Each system shall include all
components and systems for an effective control of the package equipment and to interface seamlessly
with the plant Integrated Control and Safety System (ICSS).
Allen Bradley ControlLogix or CompactLogix or equivalent shall be the PLC used in all Package
Equipment for non safety related control. For SIL 2 Applications, Vendor shall use Rockwell Automation
AAdvance PLC or equivalent with appropriate SIL rating.
The PLC shall be with redundant CPU in hot stand-by mode. In case of failure of one processor, switch
over to back-up shall be automatic and instantaneous without affecting operation of the package
equipment. There shall be separate processors for control and safety functions. PLC shall have
redundant serial and network interface capability with the Plant ICSS.
Rack Power supplies shall be sized so that no more than 60% of the available current of the power supply
is utilized. Power supply with 120VAC input shall be utilized when no specific input voltage requirements
are provided. The Programmable Logic Controller including Input/output cards shall be capable of
operating on 24 VDC. Power supply shall be redundant.
PLC Chassis shall be selected to provide a minimum of 20% spare slots available. PLC chassis mounting
and grounding in the control panel shall follow Vendor’s requirements provided with the installation
instructions.
Two (2) Ethernet cards shall be provided with every PLC system to support redundant Modbus TCP/IP
communication.
The protocol and electrical interface to be used for communications between the PLC and the ICSS is
Modbus TCP/IP over Ethernet or Modbus RTU.
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
10/18
Client Doc. No.
Client
Project
Location
Unit
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
Analog modules shall be installed in the same rack with the controller when possible. System shall accept
as a minimum 4 -20mA or 1 -5 VDC analog signals. All Analog I/O modules shall support HART Protocol.
All analog points shall be wired to terminals for field wiring, including spare points. A minimum of 20%
spare points of each type included in the panel shall be provided and available after completion of FAT.
Temperature modules if need it, shall be installed in the same rack with the controller when possible.
Wiring from temperature devices should wire directly to the card to reduce any noise or signal loss from
terminals. A minimum of 20% spare points of each type included in the panel shall be provided and
available after completion of FAT.
Digital I/O modules shall have a minimum of 16 points per module. Use of 32 point modules shall be
only with Client’s Approval. All digital points shall be wired to terminals for field wiring, including spare
points. A minimum of 20% spare wired points of each type shall be provided and available after
completion of FAT. System shall accept as a minimum dry contact digital inputs with interrogation voltage
of 24VDC. System outputs shall be, as a minimum, able to drive 100mA at 24VDC.
All spare slots shall have slot covers installed. A minimum of 20% spare slots shall be provided and
available after completion of FAT for future expansion.
When multiple chassis are needed, communications to the remote racks shall be done using redundant
communication links.
8.
PACKAGE ROTATING MACHINERY CONTROLS PHILOSOPHY
All Package Rotating Machinery control systems shall as a minimum, provide the following functionality.
For full details, refer to Machine Monitoring System Specification (078051C-000-JSS-1010-0010) and
Expander Compressors With Magnetic Bearings (API 617, Parts 1 & 4) Specification (078051C-000JSS-1010-0001).
Personnel Safety:

Vibration Monitoring (In accordance with API STD 617, Chapters 1 and 2, API STD 670)

Over speed protection (if applicable)

Safety Instrumented System (as required by API STD 670 and IEC 61511)
Protect and control the package machinery and auxiliary systems during all phases of operation including
Startup and sequential Shutdown.
Process upsets:

Anti-surge/Performance (if applicable)

Vibration Monitoring (In accordance with API STD 617, Chapters 1 and 2, API STD 670)

Over speed (if applicable)

Safety Instrumented System (API STD 670 and IEC 61511)

Machinery Emergency Shutdown
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
11/18
Client Doc. No.
Client
Project
Location
Unit
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
Optimize the machinery operation efficiency (Performance Control).
Provide a safe, controlled, reliable, automatic shutdown upon the detection of potentially dangerous or
abnormal conditions (API STD 670 and IEC 61511).
Provide Operations and Maintenance personnel with centralized indications, alarms, and controls to
startup, operate, and shutdown the machinery train from the Local Control Panel.
Allow Operations personnel to control machinery operation and performance from the ICSS Operator
Consoles located in the remote Central Control Room.
All primary machinery controls will reside in the package equipment PLC (performance, anti-surge, load
sharing, etc.). Local Control Panel with HMI to be utilized for machinery startup with hardwired motor
start/stop/run indication on panel face. The installation of local Programmable Logic Controllers (PLC),
CPUs and I/O cards in the Local Control Panel should be avoided. Preferably, these should be installed
in an Remote Instrument Enclosure (RIE) Building.
Field instruments to utilize 4-20 mA with HART protocol with explosion proof installation as required.
All package PLC’s to meet SIL rating as determined in the SIL study with SIL architecture, based on IEC
61511, the project shall adopt recommendations for one PLC for Control/Monitoring, and another Safety
Instrumented Function, independent, stand-alone PLC, which could be SIL 2 or Triple Modular
Redundant (TMR) SIL 3 including redundancy for the following PLC components:

Processor CPU

Power Supplies (rack & field instrument power)

Modbus or Ethernet TCP/IP communications

I/O cards
Each machine to have a dedicated control system, such that a failure will not trip other rotating equipment
and redundant Modbus or Ethernet TCP/IP interface with the unit BPCS.
The PLC software program to include alarm first out and provision to synchronize the internal clock of
the PLCs thru a Network GPS per API STD 670 5.4. for alarm time stamping.
The package rotating machinery Vendor to provide a SIL Assessment Summary based on IEC 61511
requirements, regarding the safety lifecycle phases of development, manufacture, commissioning, repair,
and modification. The EPC Contractor must review the Vendor’s SIL analysis and provide further direction
if required, in terms of acceptance and scope.
The package PLC will initiate all shutdown functions through hardwired signals to plant’s SIS, including
package auxiliaries.
The Process Unit SIS (by others) will directly activate machinery shutdown safety functions independent
from the package PLC (SIS I/O hardwired directly to the trip element with feedback to the package PLC).
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
12/18
Client Doc. No.
Client
Project
Location
Unit
9.
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
ETHERNET SWITCH
Managed Ethernet switches, with at least Two (2) Fiber Optic ports shall be provided. Each of these
managed Ethernet switches shall also have enough number of copper ports (including spare ports) that
will be used for plant communications.
Vendors, who are providing redundant PLC configurations, shall provide Two (2) managed Ethernet
switches, one for each communication link. Vendors, who are providing simplex PLC configurations, shall
provide One (1) managed Ethernet switch.
If required, a Fiber Optic Patch Panel shall be provided in each PLC panel. Fiber optic patch cords shall
be provided for connection of the patch panel to the switches. All control network switches and routers
shall include the capability to disable (secure) unused Ethernet ports.
10.
HUMAN MACHINE INTERFACE (HMI)
Local Human Machine Interface (HMI) shall be provided for PLC’s and configured according to ICSS
Specification (078051C-000-JSS-1510-0005). Additional HMI may be configured by the ICSS vendor for
the control room BPCS as necessary.
11.

HMI panel shall be touchscreen with proper NEMA rating for the environment installed. If HMI is
outdoors, it shall have a sunshield provided. HMI panels shall be mounted at a height no less
than 54” from ground level and no higher than 72” from ground level. Adequate cooling shall be
provided for all installations.

HMI panels shall be capable of displaying control sequence steps, color graphics, trends, loop
views, system diagnostic views and alarms. The HMI display should be visible in bright sunlight
and also at night. Details of HMI graphics shall be developed together with Company /
Contractor during detailed engineering.

HMI communication to the PLC shall be via Ethernet/IP.

HMI Software configurations shall be approved by Client before any development commences.

HMI shall have different layers of Password Protected authorization with assignable tasks. All
passwords shall be capable of being changed with proper authorization.

No calculations or logic functions shall be performed in HMI. HMI shall not generate any alarms.
It shall only display alarms.

HMI shall be rated NEMA 4X when used outdoors.
COMMUNICATION REQUIREMENTS
All data gathered by the PLC (e.g., Process parameters, HART diagnostics) shall be available to the
facility ICSS.
PLC communication with the facility ICSS shall be redundant Modbus TCP/IP for Simplex and Redundant
PLC configuration.
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
13/18
Client Doc. No.
Client
Project
Location
Unit
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
PLC communication with vibration monitoring system shall be via Modbus TCP/IP. All parameters
required to monitor the vibration monitoring system in ICSS shall be included in the Modbus mapping to
be sent to BPCS.
Package vendor to submit a Modbus mapping file as part of the vendor documentation. Note that the
Modbus mapping file excel format will be based on the main ICSS Vendor requirements. PLC data that
needs to be transmitted to BPCS (Memory Mapping) shall be placed in small number of Contiguous
Registers in PLC program. All programming and configuration of the Ethernet module shall be provided
and will be verified with a communications test during Factory Acceptance Test (FAT).
The PLC communications interface shall be used to synchronize the date and time on the PLC
periodically.
The Mechanical Package shall be capable of continuing to run in LOCAL mode upon loss of
communication with the facility BPCS (see section 15 on Operation Modes). The PLC should incorporate
a capability of sending a common hardwired alarm to BPCS in the event of loss of communications
between the package controller and the BPCS. The facility BPCS will be the Master in relation with the
PLC.
Data shall be transferred between the facility BPCS and PLC in a logical and structured manner, utilizing
a format that is the most effective using the Modbus TCP/IP protocol. This data transfer structure shall
be created such that it allows for future growth and can be easily analyzed. The structure shall be defined
by the facility BPCS vendor.
Transfer of grouped data that does not readily allow the identification of individual data points at opposite
ends of the channel shall be avoided. Tagging must be kept uniform across system boundaries.
Data that is naturally arrayed (e.g., a setpoint with high and low scale values), shall not be partitioned
such that sub-components are spread out in an unordered manner. Provisions should be made to keep
the data integral, or provide common structures, with placeholders for skipped components, for all data
subsets (e.g., all setpoints grouped, all high scales grouped, etc.).
Validation of the communications with the facility BPCS shall be done as a combined effort between the
Contractor, Package Equipment PLC Vendor and the integrated ICSS Vendor.
OPC data servers can be considered for bulk data transfer between package PLC and BPCS.
12.
CYBERSECURITY
Package PLC shall meet all cyber security requirements as per Client’s cyber security policy and local
regulations. Any interface switches or gateways shall be provided with suitable firewalls. Details of
cybersecurity requirements and implementation guidelines shall be developed during detailed
engineering.
13.
ELECTRICAL REQUIREMENTS
All electrical equipment shall be UL or FM listed and all installations shall comply with the electrical area
classification requirements.
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
14/18
Client Doc. No.
Client
Project
Location
Unit
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
PLC System electronics that will not meet the electrical area classification may be placed in a purged
enclosure Local Control Panel. Instrument air purging shall be designed in accordance with NFPA 496.
The loss-of-purge signal shall be wired to the PLC and shall be communicated to the BPCS.
Electrical wiring shall be provided to accept redundant 120 VAC UPS (by others) supply to the PLC
System. Electrical distribution to the PLC equipment shall consist of circuit breakers.
Each piece of equipment excluding outlets will require a separate circuit breaker.
One receptacle 120 VAC shall be provided in the Local Control Panel interior.
Interior lighting shall be fluorescent tube type suitable for the area classification (typically 4-foot, 2-tube
fixtures) with a switch at the door(s).
14.
PROGRAMMING
Programs shall be written so that individual processes, equipment, etc. are in separate routines. Areas
or systems shall be divided into separate programs.
Programs shall be fully annotated with descriptions to provide full documentation of the program.
All programming shall be fully documented and subject to review by the Contractor.
PLC shall have a minimum of 50% spare memory available at program 100% approval and shipment of
equipment to site.
Vendor shall provide pricing for one (1) license of software for each PLC system at the same revision
level of the provided PLC programming.
PLC shall accept and send hardwired and communications I/O to/from facility SIS and BPCS as required.
SIS inputs shall take high priority over any other logic.
The Programmable Logic Controller shall be configurable to allow modification only by authorized users.
Client shall have full access to all logic.
15.
OPERATING MODES
Package control shall be possible either from the Local Panel (Local) or from the BPCS workstation
located in the Central Control Room (Remote).
Local/Remote Mode switching function shall be performed from the Local Panel. Transfer from one mode
to the other shall be bumpless. The current position of the switch shall be indicated on the HMI at all
times.
16.
POWER FAILURE AND RESTORATION
Upon loss of power, the PLC System must shut down in an orderly manner and all I/O shall fail to their
configured failure state. Failure state shall be identified for all instrument types. Where applicable for
shutdowns, fail-safe instrumentation shall be specified.
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
15/18
Client Doc. No.
Client
Project
Location
Unit
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
During power restoration, the PLC System must come back online in a predetermined safe state that
must be transitioned into a running state as appropriate to the facility. The PLC System design must
include any required features necessary to appropriately control the system outputs following a restart.
17.
TESTING
All PLC based Local Control Panels provided by the Vendor as part of a package shall be inspected and
tested at the Vendor shop by Vendor’s technicians / engineers in the presence of Client and EPC
Contractors’ representatives.
Interface between the packaged equipment PLC and ICSS shall be tested during the Package FAT. The
facility ICSS vendor shall be present at the vendor’s facility during the Package FAT. Any ICSS test
equipment required to perform the test of 3rd party vendor packaged equipment ICSS interfaces at the
vendor's facilities shall be supplied by the ICSS vendor.
Inspection shall include a physical check and functional check for compliance with the specifications. It
also includes continuity check and loop testing of electrical and electronic wiring, the nameplate
engraving, and the proper function of instruments provided by the Vendor. Contractor reserves the right
to witness all functional tests. Waiver of inspection does not relieve the Vendor of his responsibility for
proper test, instrument installation and panel construction.
Factory Acceptance Testing (FAT):

Vendor shall notify Contractor at least ten (10) working days in advance of commencement of
testing and final inspection(s) to allow Contractor designated personnel and Client designated
personnel to witness said testing and final inspection.

Before the witness tests commence, the vendor shall have performed a complete system
Vendor functional test in accordance with the vendor's standard procedure. This internal test
reports shall be furnished to Client / Contractor before start of FAT

Vendor will provide a FAT Test Procedure, indicating the steps of the test.

The Vendor shall provide all necessary test equipment and simulation facilities required for the
witnessed tests and supply manpower in order to simulate analog and digital input signals and
display/demonstrate the resulting analog or digital output.

The vendor shall develop a redundancy switch over test procedure which clearly defines the
method of testing the switch over of redundant components and the expected results. The
procedure shall be part of the FAT Test Procedure document and as such shall be available for
review prior to the FAT.

Prior to delivery to the site, the mechanical package control system shall be subjected to a
thorough inspection and checkout to verify the correct operation of the PLC System and all
associated I/O hardware. The PLC System checkout shall be conducted by the System
Integrator (e.g., Local Panel Fabricator).

All FAT testing shall include all the interfaces between the packaged equipment PLC System
and the BPCS/SIS systems. Signals normally originating or received by the BPCS/SIS shall be
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
16/18
Client Doc. No.
Client
Project
Location
Unit
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
simulated accordingly.

Documentation of detailed test results including all AS BUILT data link mapping shall be
provided prior to shipment of equipment.

The witnessed test shall consist of a functional check of each I/O point, alarm point, digital and
regulatory control loop for proper functions and displays on the operator interface and shall
include the following tests:
Note:
FAT =
Factory acceptance test
SAT =
Site acceptance
FAT
X
SAT
X
X
X
X
X
X
X
X
X
X
X
X
X
Check of sequences and interlocks configuration
Check of correct change over to redundant unit in the event of
primary failure
Check of all types of displays
X
X
Test of alarm system
X
X
Operator interface (including keyboard, etc.) functioning
X
X
Hardware check.
X
X
Demonstration of diagnostic equipment
X
X
Simulation of power failure and restarts
Burn-in test or relevant certification, if the test has been already
carried out, for all sections of the system
Simulation of communication from/to each sub-system
X
X
X
Activity
Overall system security checkout.
Test of standard software
Demonstration of all system functions (e.g. changing Tuning
constants, check of algorithm functions etc.)
Check of loop's configuration for correct entry of ranges, limits, etc.
The system shall not be accepted until the entire system has passed an error - free test. Once a failure
or an error has been detected by internal diagnostic system, repairs may be made.
If the test is aborted, and/ or the equipment rejected, the Vendor shall rectify the problem and advise a
date for retest. A report shall be forwarded to Client and Contractor before the retest detailing why the
equipment was rejected and what actions have been taken to rectify the problem. These repeat tests
shall be at the Vendor’s cost.
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
17/18
Client Doc. No.
Client
Project
Location
Unit
18.
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
COMMISSIONING, STARTUP, AND OPERATIONAL RELIABILITY
Vendor in conjunction with the Client/Contractor shall completely inspect the installation including wiring,
physical components, electrical installations, controls and communications systems, etc. and shall
perform functional tests of the system after field installation to ensure a certifiable system. Tests shall
have already been witnessed by the Client/Contractor at the Vendor's testing site. Preliminary acceptance
of the system shall be contingent on the results of the test. Final acceptance shall occur after successful
operation of the PLC System at the plant site.
Vendor shall provide complete SAT test document at least three weeks prior to on-site testing and
acceptance of the PLC System.
Vendor shall be responsible for preparing each PLC System for operation.
Vendor shall have qualified personnel available during start-up to place the PLC System on service and
correct any difficulties which may be encountered.
In addition to commercial warranty provided by Vendor, the PLC System shall provide on-line reliable
service. Vendor shall comply with all field services agreements in place with the Client/Contractor and
ensure service and repair to maintain the operational reliability requirement.
19.
DOCUMENTATION
Vendor to generate all the deliverables (drawings & documents) as per document list (to be finalized
jointly during detail engineering). The set shall include following drawings/documents as a minimum but
not limited to:

PLC System hardware information.

PLC System Programming software used, and the program loaded.

Hardware Manuals: System Hardware manuals shall be submitted for assuring satisfactory
operation and maintenance of the system. Detailed literature for installation and maintenance of
all hardware, startup procedures shall be provided. Detail specifications & literature for all
bought out items shall be provided.

Software Manuals: Software manuals shall be supplied for system software, other programs
used as supporting software, bought out software etc. Software reference manuals,
programming manuals shall also be supplied.

System Configuration diagram

Bill of material with part numbers

System loading, power consumption & heat dissipation calculations

Hardware Design Manual

Software Design Manual

Local Control Panel GA drawings
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Project N°
Unit
Doc. Type
Code
Serial N°
Rev.
Page
078051C
000
JSS
1514
0001
A
18/18
Client Doc. No.
Client
Project
Location
Unit
20.

I/O assignment

Cause and Effect Diagrams

Modbus Mapping File

Internal wiring diagrams

Graphics, logging & report formats

Inspection & test reports
Commonwealth LNG LLC
Commonwealth LNG
Cameron Parish, Louisiana
000
SHIPPING AND HANDLING
Vendor shall submit their standard packing and shipping procedure for review.
PLC Local Control Panel shall be provided with shipping supports, to assure structural rigidity during
shipment, unless vendor proves they are not required.
Shipping crates and boxes will be provided for handling and preservation for temporary storage at site.
PLC Local Control Panel shall be fitted with lifting lugs and/or eyebolts so that the PLC Local Control
Panel can be lifted by a crane using a single point and put in its proper location. Vendor shall supply
lifting specifications, requirements, and weights to enable installer to safely place the Local Control Panel
on foundation.
Local Control Panel shall be provided with temporary additional supports. Components inside shall be
protected with plastic foams. Loose components on panels shall be secured with appropriate fasteners.
PLC Local Control Panel or any of its components shall not be shipped until Client/Contractor has
approved the operational test results and the protective provisions afforded to the Local Control Panel
and its PLC System components prior to shipment. Particular care and attention shall be given to the
preparation of all equipment for shipment in compliance with the manufacturer’s recommendations.
Confidential–Do Not Disclose Without Written Authorization
© Copyright Technip Energies USA, Inc. All Rights Reserved
Technip Energies USA, Inc.
LAPELS Firm Reg. No. 2886
Download