Crews - Standard Crew No. Crew A-1 1 Building Laborer 1 Concrete Saw, Gas Manual Bare Costs Hr. Daily Hr. $47.25 $378.00 112.72 $70.35 8 L.H., Daily Totals Crew A-1A 1 Skilled Worker 1 Shot Blaster, 20⬙ $490.72 Hr. Daily Hr. $61.25 $490.00 229.79 $92.00 8 L.H., Daily Totals Crew A-1B 1 Building Laborer 1 Concrete Saw $719.79 Hr. Daily Hr. $47.25 $378.00 176.00 $70.35 8 L.H., Daily Totals Crew A-1C 1 Building Laborer 1 Chain Saw, Gas, 18⬙ $554.00 Hr. Daily Hr. $47.25 $378.00 47.58 $70.35 8 L.H., Daily Totals Crew A-1D 1 Building Laborer 1 Vibrating Plate, Gas, 18⬙ $425.58 Hr. Daily Hr. $47.25 $378.00 143.82 $70.35 8 L.H., Daily Totals Crew A-1E 1 Building Laborer 1 Vibrating Plate, Gas, 21⬙ $521.82 Hr. Daily Hr. $47.25 $378.00 146.12 $70.35 8 L.H., Daily Totals Crew A-1F 1 Building Laborer 1 Rammer/Tamper, Gas, 8⬙ $524.12 Hr. Daily Hr. $47.25 $378.00 73.84 $70.35 8 L.H., Daily Totals Crew A-1G 1 Building Laborer 1 Rammer/Tamper, Gas, 15⬙ $451.84 Hr. Daily Hr. $47.25 $378.00 88.02 $70.35 8 L.H., Daily Totals Crew A-1H 1 Building Laborer 1 Exterior Steam Cleaner Incl. Subs O&P $466.02 Hr. Daily Hr. $47.25 $378.00 84.77 $70.35 8 L.H., Daily Totals $462.77 Crew A-1J Hr. Daily Hr. 1 Building Laborer 1 Cultivator, Walk-Behind, 5 H.P. $47.25 $378.00 70.72 $70.35 8 L.H., Daily Totals $448.72 Crew A-1K Hr. Daily Hr. 1 Building Laborer 1 Cultivator, Walk-Behind, 8 H.P. $47.25 $378.00 89.64 $70.35 8 L.H., Daily Totals Crew A-1M 1 Building Laborer 1 Snow Blower, Walk-Behind 8 L.H., Daily Totals $467.64 Hr. Daily Hr. $47.25 $378.00 75.10 $70.35 $453.10 Cost Per Labor-Hour Daily Bare Costs Incl. O&P $562.80 123.99 $47.25 14.09 $70.35 15.50 $686.79 $61.34 $85.85 Daily Bare Costs Incl. O&P $736.00 252.77 $61.25 28.72 $92.00 31.60 $988.77 $89.97 $123.60 Daily Bare Costs Incl. O&P $562.80 193.60 $47.25 22.00 $70.35 24.20 $756.40 $69.25 $94.55 Daily Bare Costs Incl. O&P $562.80 52.34 $47.25 5.95 $70.35 6.54 $615.14 $53.20 $76.89 Daily Bare Costs Incl. O&P $562.80 158.20 $47.25 17.98 $70.35 19.78 $721.00 $65.23 $90.13 Daily Bare Costs Incl. O&P $562.80 160.73 $47.25 18.27 $70.35 20.09 $723.53 $65.52 $90.44 Daily Bare Costs Incl. O&P $562.80 81.22 $47.25 9.23 $70.35 10.15 $644.02 $56.48 $80.50 Daily Bare Costs Incl. O&P $562.80 96.82 $47.25 11.00 $70.35 12.10 $659.62 $58.25 $82.45 Daily Bare Costs Incl. O&P $562.80 93.25 $47.25 10.60 $70.35 11.66 $656.05 $57.85 $82.01 Daily Bare Costs Incl. O&P $562.80 77.79 $47.25 8.84 $70.35 9.72 $640.59 $56.09 $80.07 Daily Bare Costs Incl. O&P $562.80 98.60 $47.25 11.21 $70.35 12.33 $661.40 $58.45 $82.68 Daily Bare Costs Incl. O&P $562.80 82.61 $47.25 9.39 $70.35 10.33 $645.41 $56.64 $80.68 Crew No. Crew A-2 2 Laborers 1 Truck Driver (light) 1 Flatbed Truck, Gas, 1.5 Ton Bare Costs Hr. Daily Hr. $47.25 52.90 $756.00 423.20 361.95 $70.35 79.00 24 L.H., Daily Totals Crew A-2A 2 Laborers 1 Truck Driver (light) 1 Flatbed Truck, Gas, 1.5 Ton 1 Concrete Saw $1541.15 Hr. Daily Hr. $47.25 52.90 $756.00 423.20 361.95 176.00 $70.35 79.00 24 L.H., Daily Totals Crew A-2B 1 Truck Driver (light) 1 Flatbed Truck, Gas, 1.5 Ton $1717.15 Hr. Daily Hr. $52.90 $423.20 361.95 $79.00 8 L.H., Daily Totals Crew A-3A 1 Equip. Oper. (light) 1 Pickup Truck, 4x4, 3/4 Ton Incl. Subs O&P $785.15 Hr. Daily Hr. $59.70 $477.60 191.73 $88.85 8 L.H., Daily Totals Hr. Daily Hr. 1 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Dump Truck, 12 C.Y., 400 H.P. 1 F.E. Loader, W.M., 2.5 C.Y. $63.05 55.45 $504.40 443.60 791.36 658.89 $93.80 82.85 16 L.H., Daily Totals Crew A-3C 1 Equip. Oper. (light) 1 Loader, Skid Steer, 78 H.P. $2398.25 Hr. Daily Hr. $59.70 $477.60 429.91 $88.85 8 L.H., Daily Totals Crew A-3D 1 Truck Driver (light) 1 Pickup Truck, 4x4, 3/4 Ton 1 Flatbed Trailer, 25 Ton $907.51 Hr. Daily Hr. $52.90 $423.20 191.73 150.61 $79.00 8 L.H., Daily Totals Crew A-3E 1 Equip. Oper. (crane) 1 Truck Driver (heavy) 1 Pickup Truck, 4x4, 3/4 Ton $765.54 Hr. Daily Hr. $66.30 55.45 $530.40 443.60 191.73 $98.65 82.85 16 L.H., Daily Totals $1165.73 Crew A-3F Hr. Daily Hr. 1 Equip. Oper. (crane) 1 Truck Driver (heavy) 1 Pickup Truck, 4x4, 3/4 Ton 1 Truck Tractor, 6x4, 380 H.P. 1 Lowbed Trailer, 75 Ton $66.30 55.45 $530.40 443.60 191.73 545.98 283.47 $98.65 82.85 16 L.H., Daily Totals Bare Costs Incl. O&P $1125.60 632.00 398.14 $49.13 $73.23 15.08 16.59 $2155.74 $64.21 $89.82 Daily Bare Costs Incl. O&P $1125.60 632.00 398.14 193.60 $49.13 $73.23 22.41 24.66 $2349.34 $71.55 $97.89 Daily Bare Costs Incl. O&P $632.00 398.14 $52.90 45.24 $79.00 49.77 $1030.15 $98.14 $128.77 Daily Bare Costs Incl. O&P $710.80 210.90 $59.70 23.97 $88.85 26.36 $921.70 $83.67 $115.21 Daily Bare Costs Incl. O&P $750.40 662.80 870.50 724.78 $59.25 $88.33 90.64 99.70 $3008.47 $149.89 $188.03 Daily Bare Costs Incl. O&P $710.80 472.90 $59.70 53.74 $88.85 59.11 $1183.70 $113.44 $147.96 Daily Bare Costs Incl. O&P $632.00 210.90 165.67 $52.90 $79.00 42.79 47.07 $1008.57 $95.69 $126.07 Daily Bare Costs Incl. O&P $789.20 662.80 210.90 $60.88 $90.75 11.98 13.18 $1662.90 $72.86 $103.93 Daily Bare Costs Incl. O&P $789.20 662.80 210.90 600.58 311.82 $60.88 $90.75 63.82 70.21 $2575.30 $124.70 $160.96 Daily $669.33 Crew A-3B $1995.18 Cost Per Labor-Hour Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 749 Crews - Standard Crew No. Bare Costs Incl. Subs O&P Crew A-3G Hr. Daily Hr. 1 Equip. Oper. (crane) 1 Truck Driver (heavy) 1 Pickup Truck, 4x4, 3/4 Ton 1 Truck Tractor, 6x4, 450 H.P. 1 Lowbed Trailer, 75 Ton $66.30 55.45 $530.40 443.60 191.73 666.04 283.47 $98.65 82.85 16 L.H., Daily Totals Crew A-3H 1 Equip. Oper. (crane) 1 Hyd. Crane, 12 Ton (Daily) $2115.24 Hr. Daily Hr. $66.30 $530.40 2150.65 $98.65 8 L.H., Daily Totals Crew A-3I 1 Equip. Oper. (crane) 1 Hyd. Crane, 25 Ton (Daily) $2681.05 Hr. Daily Hr. $66.30 $530.40 2273.31 $98.65 8 L.H., Daily Totals Crew A-3J 1 Equip. Oper. (crane) 1 Hyd. Crane, 40 Ton (Daily) $2803.71 Hr. Daily Hr. $66.30 $530.40 2446.91 $98.65 8 L.H., Daily Totals Crew A-3K 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 55 Ton (Daily) 1 P/U Truck, 3/4 Ton (Daily) $2977.31 Hr. Daily Hr. $66.30 56.40 $530.40 451.20 2461.06 157.41 $98.65 83.90 16 L.H., Daily Totals Crew A-3L 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 80 Ton (Daily) 1 P/U Truck, 3/4 Ton (Daily) $3600.07 Hr. Daily Hr. $66.30 56.40 $530.40 451.20 2641.70 157.41 $98.65 83.90 16 L.H., Daily Totals Crew A-3M 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 100 Ton (Daily) 1 P/U Truck, 3/4 Ton (Daily) $3780.71 Hr. Daily Hr. $66.30 56.40 $530.40 451.20 2768.24 157.41 $98.65 83.90 16 L.H., Daily Totals Crew A-3N 1 Equip. Oper. (crane) 1 Tower Crane (monthly) $3907.25 Hr. Daily Hr. $66.30 $530.40 1891.47 $98.65 8 L.H., Daily Totals $2421.87 Crew A-3P Hr. Daily Hr. 1 Equip. Oper. (light) 1 A.T. Forklift, 31’ reach, 45’ lift $59.70 $477.60 673.26 $88.85 8 L.H., Daily Totals Crew A-3Q 1 Equip. Oper. (light) 1 Pickup Truck, 4x4, 3/4 Ton 1 Flatbed Trailer, 3 Ton 8 L.H., Daily Totals 750 $1150.86 Hr. Daily Hr. $59.70 $477.60 191.73 78.34 $88.85 $747.67 Cost Per Labor-Hour Bare Costs Incl. O&P $789.20 662.80 210.90 732.64 311.82 $60.88 $90.75 71.33 78.46 $2707.36 $132.20 $169.21 Daily Bare Costs Incl. O&P $789.20 2365.72 $66.30 268.83 $98.65 295.71 $3154.92 $335.13 $394.36 Daily Bare Costs Incl. O&P $789.20 2500.64 $66.30 284.16 $98.65 312.58 $3289.84 $350.46 $411.23 Daily Bare Costs Incl. O&P $789.20 2691.60 $66.30 305.86 $98.65 336.45 $3480.80 $372.16 $435.10 Daily Bare Costs Incl. O&P $789.20 671.20 2707.17 173.15 $61.35 $91.28 163.65 180.02 $4340.72 $225.00 $271.29 Daily Bare Costs Incl. O&P $789.20 671.20 2905.87 173.15 $61.35 $91.28 174.94 192.44 $4539.42 $236.29 $283.71 Daily Bare Costs Incl. O&P $789.20 671.20 3045.06 173.15 $61.35 $91.28 182.85 201.14 $4678.61 $244.20 $292.41 Daily Bare Costs Incl. O&P $789.20 2080.62 $66.30 236.43 $98.65 260.08 $2869.82 $302.73 $358.73 Daily Bare Costs Incl. O&P $710.80 740.59 $59.70 84.16 $88.85 92.57 $1451.39 $143.86 $181.42 Daily Bare Costs Incl. O&P $710.80 210.90 86.17 $59.70 $88.85 33.76 37.13 $1007.88 $93.46 $125.98 Daily Crew No. Crew A-3R Bare Costs Daily Hr. 1 Equip. Oper. (light) $59.70 1 Forklift, Smooth Floor, 8,000 Lb. $477.60 311.06 $88.85 8 L.H., Daily Totals $788.66 Crew A-4 2 Carpenters 1 Painter, Ordinary Hr. Incl. Subs O&P Hr. Daily Hr. $58.60 49.65 $937.60 397.20 $87.25 73.55 24 L.H., Daily Totals $1334.80 Crew A-5 Hr. Daily Hr. 2 Laborers .25 Truck Driver (light) .25 Flatbed Truck, Gas, 1.5 Ton $47.25 52.90 $756.00 105.80 90.49 $70.35 79.00 18 L.H., Daily Totals Crew A-6 1 Instrument Man 1 Rodman/Chainman 1 Level, Electronic $952.29 Hr. Daily Hr. $61.25 56.05 $490.00 448.40 33.60 $92.00 83.30 16 L.H., Daily Totals Crew A-7 1 Chief of Party 1 Instrument Man 1 Rodman/Chainman 1 Level, Electronic $972.00 Hr. Daily Hr. $71.80 61.25 56.05 $574.40 490.00 448.40 33.60 $107.20 92.00 83.30 24 L.H., Daily Totals Crew A-8 1 Chief of Party 1 Instrument Man 2 Rodmen/Chainmen 1 Level, Electronic $1546.40 Hr. Daily Hr. $71.80 61.25 56.05 $574.40 490.00 896.80 33.60 $107.20 92.00 83.30 32 L.H., Daily Totals Crew A-9 1 Asbestos Foreman 7 Asbestos Workers $1994.80 Hr. Daily Hr. $65.75 65.25 $526.00 3654.00 $100.60 99.80 64 L.H., Daily Totals Crew A-10A 1 Asbestos Foreman 2 Asbestos Workers $4180.00 Hr. Daily Hr. $65.75 65.25 $526.00 1044.00 $100.60 99.80 24 L.H., Daily Totals Crew A-10B 1 Asbestos Foreman 3 Asbestos Workers $1570.00 Hr. Daily Hr. $65.75 65.25 $526.00 1566.00 $100.60 99.80 32 L.H., Daily Totals Crew A-10C 3 Asbestos Workers 1 Flatbed Truck, Gas, 1.5 Ton 24 L.H., Daily Totals $2092.00 Hr. Daily Hr. $65.25 $1566.00 361.95 $99.80 $1927.95 Cost Per Labor-Hour Daily Bare Costs Incl. O&P $710.80 342.17 $59.70 38.88 $88.85 42.77 $1052.97 $98.58 $131.62 Daily Bare Costs Incl. O&P $1396.00 588.40 $55.62 $82.68 $1984.40 $55.62 $82.68 Daily Bare Costs Incl. O&P $1125.60 158.00 99.54 $47.88 $71.31 5.03 5.53 $1383.14 $52.90 $76.84 Daily Bare Costs Incl. O&P $736.00 666.40 36.96 $58.65 $87.65 2.10 2.31 $1439.36 $60.75 $89.96 Daily Bare Costs Incl. O&P $857.60 736.00 666.40 36.96 $63.03 $94.17 1.40 1.54 $2296.96 $64.43 $95.71 Daily Bare Costs Incl. O&P $857.60 736.00 1332.80 36.96 $61.29 $91.45 1.05 1.16 $2963.36 $62.34 $92.61 Daily Bare Costs Incl. O&P $804.80 5588.80 $65.31 $99.90 $6393.60 $65.31 $99.90 Daily Bare Costs Incl. O&P $804.80 1596.80 $65.42 $100.07 $2401.60 $65.42 $100.07 Daily Bare Costs Incl. O&P $804.80 2395.20 $65.38 $100.00 $3200.00 $65.38 $100.00 Daily Bare Costs Incl. O&P $2395.20 398.14 $65.25 15.08 $99.80 16.59 $2793.34 $80.33 $116.39 Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew A-10D 2 Asbestos Workers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hydraulic Crane, 33 Ton Bare Costs Incl. Subs O&P Hr. Daily Hr. $65.25 66.30 56.40 $1044.00 530.40 451.20 2429.62 $99.80 98.65 83.90 32 L.H., Daily Totals $4455.22 Crew A-11 Hr. Daily Hr. 1 Asbestos Foreman 7 Asbestos Workers 2 Chip. Hammers, 12 Lb., Elec. $65.75 65.25 $526.00 3654.00 54.32 $100.60 99.80 64 L.H., Daily Totals $4234.32 Crew A-12 Hr. Daily Hr. 1 Asbestos Foreman 7 Asbestos Workers 1 Trk-Mtd Vac, 14 CY, 1500 Gal. 1 Flatbed Truck, 20,000 GVW $65.75 65.25 $526.00 3654.00 596.69 223.10 $100.60 99.80 64 L.H., Daily Totals $4999.79 Crew A-13 Hr. Daily Hr. 1 Equip. Oper. (light) 1 Trk-Mtd Vac, 14 CY, 1500 Gal. 1 Flatbed Truck, 20,000 GVW $59.70 $477.60 596.69 223.10 $88.85 8 L.H., Daily Totals Crew B-1 1 Labor Foreman (outside) 2 Laborers $1297.39 Hr. Daily Hr. $49.25 47.25 $394.00 756.00 $73.30 70.35 24 L.H., Daily Totals Crew B-1A 1 Labor Foreman (outside) 2 Laborers 2 Cutting Torches 2 Sets of Gases $1150.00 Hr. Daily Hr. $49.25 47.25 $394.00 756.00 28.48 377.34 $73.30 70.35 24 L.H., Daily Totals Crew B-1B 1 Labor Foreman (outside) 2 Laborers 1 Equip. Oper. (crane) 2 Cutting Torches 2 Sets of Gases 1 Hyd. Crane, 12 Ton $1555.82 Hr. Daily Hr. $49.25 47.25 66.30 $394.00 756.00 530.40 28.48 377.34 2150.65 $73.30 70.35 98.65 32 L.H., Daily Totals $4236.87 Crew B-1C Hr. Daily Hr. 1 Labor Foreman (outside) 2 Laborers 1 Telescoping Boom Lift, to 60’ $49.25 47.25 $394.00 756.00 385.68 $73.30 70.35 24 L.H., Daily Totals $1535.68 Crew B-1D Hr. Daily Hr. 2 Laborers 1 Small Work Boat, Gas, 50 H.P. 1 Pressure Washer, 7 GPM $47.25 $756.00 131.82 113.42 $70.35 16 L.H., Daily Totals $1001.24 Cost Per Labor-Hour Bare Costs Incl. O&P $1596.80 789.20 671.20 2672.58 $63.30 $95.54 75.93 83.52 $5729.78 $139.23 $179.06 Daily Bare Costs Incl. O&P $804.80 5588.80 59.75 $65.31 $99.90 .85 .93 $6453.35 $66.16 $100.83 Daily Bare Costs Incl. O&P $804.80 5588.80 656.36 245.41 $65.31 $99.90 12.81 14.09 $7295.37 $78.12 $113.99 Daily Bare Costs Incl. O&P $710.80 656.36 245.41 $59.70 Daily Crew No. Crew B-1E 1 Labor Foreman (outside) 3 Laborers 1 Work Boat, Diesel, 200 H.P. 2 Pressure Washers, 7 GPM Bare Costs Incl. Subs O&P Hr. Daily Hr. $49.25 47.25 $394.00 1134.00 1574.43 226.84 $73.30 70.35 32 L.H., Daily Totals $3329.27 Crew B-1F Hr. Daily Hr. 2 Skilled Workers 1 Laborer 1 Small Work Boat, Gas, 50 H.P. 1 Pressure Washer, 7 GPM $61.25 47.25 $980.00 378.00 131.82 113.42 $92.00 70.35 24 L.H., Daily Totals $1603.24 Crew B-1G Hr. Daily Hr. 2 Laborers 1 Small Work Boat, Gas, 50 H.P. $47.25 $756.00 131.82 $70.35 16 L.H., Daily Totals $887.82 Crew B-1H Hr. Daily Hr. $88.85 2 Skilled Workers 1 Laborer 1 Small Work Boat, Gas, 50 H.P. $61.25 47.25 $980.00 378.00 131.82 $92.00 70.35 102.47 112.72 24 L.H., Daily Totals $1612.57 $162.17 $201.57 Daily Bare Costs Incl. O&P $586.40 1125.60 $47.92 $71.33 $1712.00 $47.92 $71.33 Daily Bare Costs Incl. O&P $586.40 1125.60 31.33 415.07 $47.92 $71.33 16.91 18.60 $2158.40 $64.83 $89.93 Daily Bare Costs Incl. O&P $586.40 1125.60 789.20 31.33 415.07 2365.72 $52.51 $78.16 79.89 87.88 $5313.32 $132.40 $166.04 Daily Bare Costs Incl. O&P $586.40 1125.60 424.25 $47.92 $71.33 16.07 17.68 $2136.25 $63.99 $89.01 Daily Bare Costs Incl. O&P $1125.60 145.00 124.76 $47.25 $70.35 15.33 16.86 $1395.36 $62.58 $87.21 Crew B-1J 1 Labor Foreman (inside) 1 Laborer $1489.82 Hr. Daily Hr. $47.75 47.25 $382.00 378.00 $71.10 70.35 16 L.H., Daily Totals Crew B-1K 1 Carpenter Foreman (inside) 1 Carpenter $760.00 Hr. Daily Hr. $59.10 58.60 $472.80 468.80 $88.00 87.25 16 L.H., Daily Totals Crew B-2 1 Labor Foreman (outside) 4 Laborers $941.60 Hr. Daily Hr. $49.25 47.25 $394.00 1512.00 $73.30 70.35 40 L.H., Daily Totals $1906.00 Crew B-2A Hr. Daily Hr. 1 Labor Foreman (outside) 2 Laborers 1 Telescoping Boom Lift, to 60’ $49.25 47.25 $394.00 756.00 385.68 $73.30 70.35 24 L.H., Daily Totals Crew B-3 $1535.68 Hr. 1 Labor Foreman (outside) $49.25 2 Laborers 47.25 1 Equip. Oper. (medium) 63.05 2 Truck Drivers (heavy) 55.45 1 Crawler Loader, 3 C.Y. 2 Dump Trucks, 12 C.Y., 400 H.P. 48 L.H., Daily Totals Crew B-3A 4 Laborers 1 Equip. Oper. (medium) 1 Hyd. Excavator, 1.5 C.Y. 40 L.H., Daily Totals Daily Hr. $394.00 756.00 504.40 887.20 1257.68 1582.72 $73.30 70.35 93.80 82.85 $5382.00 Hr. Daily Hr. $47.25 63.05 $1512.00 504.40 1185.24 $70.35 93.80 $3201.64 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 1688.40 1731.87 249.52 $47.75 $71.09 56.29 61.92 $4256.20 $104.04 $133.01 Daily Bare Costs Incl. O&P $1472.00 562.80 145.00 124.76 $56.58 $84.78 10.22 11.24 $2304.56 $66.80 $96.02 Daily Bare Costs Incl. O&P $1125.60 145.00 $47.25 8.24 $70.35 9.06 $1270.60 $55.49 $79.41 Daily Bare Costs Incl. O&P $1472.00 562.80 145.00 $56.58 $84.78 5.49 6.04 $2179.80 $62.08 $90.83 Daily Bare Costs Incl. O&P $568.80 562.80 $47.50 $70.72 $1131.60 $47.50 $70.72 Daily Bare Costs Incl. O&P $704.00 698.00 $58.85 $87.63 $1402.00 $58.85 $87.63 Daily Bare Costs Incl. O&P $586.40 2251.20 $47.65 $70.94 $2837.60 $47.65 $70.94 Daily Bare Costs Incl. O&P $586.40 1125.60 424.25 $47.92 $71.33 16.07 17.68 $2136.25 $63.99 $89.01 Daily Bare Costs Incl. O&P $586.40 1125.60 750.40 1325.60 1383.45 1740.99 $52.95 $78.92 59.17 65.09 $6912.44 $112.13 $144.01 Daily Bare Costs Incl. O&P $2251.20 750.40 1303.76 $50.41 $75.04 29.63 32.59 $4305.36 $80.04 $107.63 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 751 Crews - Standard Crew No. Bare Costs Incl. Subs O&P Crew B-3B Hr. Daily Hr. 2 Laborers 1 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Backhoe Loader, 80 H.P. 1 Dump Truck, 12 C.Y., 400 H.P. $47.25 63.05 55.45 $756.00 504.40 443.60 357.71 791.36 $70.35 93.80 82.85 32 L.H., Daily Totals Crew B-3C 3 Laborers 1 Equip. Oper. (medium) 1 Crawler Loader, 4 C.Y. $2853.07 Hr. $47.25 63.05 32 L.H., Daily Totals Crew B-4 1 Labor Foreman (outside) 4 Laborers 1 Truck Driver (heavy) 1 Truck Tractor, 220 H.P. 1 Flatbed Trailer, 40 Ton 1 Labor Foreman (outside) 4 Laborers 2 Equip. Oper. (medium) 1 Air Compressor, 250 cfm 2 Breakers, Pavement, 60 lb. 2 -50’ Air Hoses, 1.5⬙ 1 Crawler Loader, 3 C.Y. $1134.00 504.40 1506.11 Hr. $70.35 93.80 $3144.51 Hr. Daily Hr. $49.25 47.25 55.45 $394.00 1512.00 443.60 339.98 206.92 $73.30 70.35 82.85 48 L.H., Daily Totals Crew B-5 Daily $2896.50 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 1512.00 1008.80 196.28 68.94 47.20 1257.68 $73.30 70.35 93.80 56 L.H., Daily Totals $4484.90 Crew B-5A Hr. Daily Hr. 1 Labor Foreman (outside) 6 Laborers 2 Equip. Oper. (medium) 1 Equip. Oper. (light) 2 Truck Drivers (heavy) 1 Air Compressor, 365 cfm 2 Breakers, Pavement, 60 lb. 8 -50’ Air Hoses, 1⬙ 2 Dump Trucks, 8 C.Y., 220 H.P. $49.25 47.25 63.05 59.70 55.45 $394.00 2268.00 1008.80 477.60 887.20 389.99 68.94 74.48 834.98 $73.30 70.35 93.80 88.85 82.85 96 L.H., Daily Totals Crew B-5B $6403.99 Hr. 1 Powderman $61.25 2 Equip. Oper. (medium) 63.05 3 Truck Drivers (heavy) 55.45 1 F.E. Loader, W.M., 2.5 C.Y. 3 Dump Trucks, 12 C.Y., 400 H.P. 1 Air Compressor, 365 cfm 48 L.H., Daily Totals Daily Hr. $490.00 1008.80 1330.80 658.89 2374.08 389.99 $92.00 93.80 82.85 $6252.56 Cost Per Labor-Hour Bare Costs Incl. O&P $1125.60 750.40 662.80 393.48 870.50 $53.25 $79.34 35.91 39.50 $3802.78 $89.16 $118.84 Daily Bare Costs Incl. O&P Daily $1688.40 750.40 1656.72 $51.20 $76.21 47.07 51.77 $4095.52 $98.27 $127.99 Daily Bare Costs Incl. O&P $586.40 2251.20 662.80 373.98 227.61 $48.95 $72.92 11.39 12.53 $4101.99 $60.34 $85.46 Daily Bare Costs Incl. O&P $586.40 2251.20 1500.80 215.91 75.83 51.92 1383.45 $52.05 $77.47 28.04 30.84 $6065.51 $80.09 $108.31 Daily Bare Costs Incl. O&P $586.40 3376.80 1500.80 710.80 1325.60 428.99 75.83 81.93 918.48 $52.45 $78.13 14.25 15.68 $9005.63 $66.71 $93.81 Daily Bare Costs Incl. O&P $736.00 1500.80 1988.40 724.78 2611.49 428.99 $58.95 $88.03 71.31 78.44 $7990.46 $130.26 $166.47 Crew No. Crew B-5C Hr. Incl. Subs O&P Daily Hr. 3 Laborers $47.25 1 Equip. Oper. (medium) 63.05 2 Truck Drivers (heavy) 55.45 1 Equip. Oper. (crane) 66.30 1 Equip. Oper. (oiler) 56.40 2 Dump Trucks, 12 C.Y., 400 H.P. 1 Crawler Loader, 4 C.Y. 1 S.P. Crane, 4x4, 25 Ton $1134.00 504.40 887.20 530.40 451.20 1582.72 1506.11 927.07 $70.35 93.80 82.85 98.65 83.90 64 L.H., Daily Totals $7523.10 Crew B-5D Hr. Daily Hr. 1 Labor Foreman (outside) 4 Laborers 2 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Air Compressor, 250 cfm 2 Breakers, Pavement, 60 lb. 2 -50’ Air Hoses, 1.5⬙ 1 Crawler Loader, 3 C.Y. 1 Dump Truck, 12 C.Y., 400 H.P. $49.25 47.25 63.05 55.45 $394.00 1512.00 1008.80 443.60 196.28 68.94 47.20 1257.68 791.36 $73.30 70.35 93.80 82.85 64 L.H., Daily Totals Crew B-5E $5719.86 Hr. 1 Labor Foreman (outside) $49.25 4 Laborers 47.25 2 Equip. Oper. (medium) 63.05 1 Truck Driver (heavy) 55.45 1 Water Tank Trailer, 5000 Gal. 1 High Pressure Water Jet 40 KSI 2 -50’ Air Hoses, 1.5⬙ 1 Crawler Loader, 3 C.Y. 1 Dump Truck, 12 C.Y., 400 H.P. 64 L.H., Daily Totals Crew B-6 2 Laborers 1 Equip. Oper. (light) 1 Backhoe Loader, 48 H.P. Crew B-6A .5 Labor Foreman (outside) 1 Laborer 1 Equip. Oper. (medium) 1 Vacuum Truck, 5000 Gal. Hr. $394.00 1512.00 1008.80 443.60 169.14 902.38 47.20 1257.68 791.36 $73.30 70.35 93.80 82.85 Hr. Daily Hr. $47.25 59.70 $756.00 477.60 277.19 $70.35 88.85 $1510.79 Hr. Daily Hr. $49.25 47.25 63.05 $197.00 378.00 504.40 408.90 $73.30 70.35 93.80 20 L.H., Daily Totals Crew B-6B Daily $6526.16 24 L.H., Daily Totals $1488.30 Hr. 2 Labor Foremen (outside) $49.25 4 Laborers 47.25 1 S.P. Crane, 4x4, 5 Ton 1 Flatbed Truck, Gas, 1.5 Ton 1 Butt Fusion Mach., 4⬙-12⬙ diam. 48 L.H., Daily Totals 752 Bare Costs Daily Hr. $788.00 1512.00 385.89 361.95 332.25 $73.30 70.35 $3380.09 Cost Per Labor-Hour Bare Costs Incl. O&P $1688.40 750.40 1325.60 789.20 671.20 1740.99 1656.72 1019.78 $54.80 $81.64 62.75 69.02 $9642.29 $117.55 $150.66 Daily Bare Costs Incl. O&P $586.40 2251.20 1500.80 662.80 215.91 75.83 51.92 1383.45 870.50 $52.48 $78.14 36.90 40.59 $7598.81 $89.37 $118.73 Daily Bare Costs Incl. O&P $586.40 2251.20 1500.80 662.80 186.05 992.62 51.92 1383.45 870.50 $52.48 $78.14 49.50 54.45 $8485.74 $101.97 $132.59 Daily Bare Costs Incl. O&P $1125.60 710.80 304.91 $51.40 $76.52 11.55 12.70 $2141.31 $62.95 $89.22 Daily Bare Costs Incl. O&P $293.20 562.80 750.40 449.79 $53.97 $80.32 20.45 22.49 $2056.19 $74.42 $102.81 Daily Bare Costs Incl. O&P $1172.80 2251.20 424.48 398.14 365.48 $47.92 $71.33 22.50 24.75 $4612.10 $70.42 $96.09 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew B-6C Bare Costs Hr. 2 Labor Foremen (outside) $49.25 4 Laborers 47.25 1 S.P. Crane, 4x4, 12 Ton 1 Flatbed Truck, Gas, 3 Ton 1 Butt Fusion Mach., 8⬙-24⬙ diam. 48 L.H., Daily Totals Crew B-6D .5 Labor Foreman (outside) 1 Laborer 1 Equip. Oper. (medium) 1 Hydro Excavator, 12 C.Y. Incl. Subs O&P Daily Hr. $788.00 1512.00 637.99 391.02 787.50 $73.30 70.35 $4116.51 Hr. $49.25 47.25 63.05 20 L.H., Daily Totals Daily $197.00 378.00 504.40 1404.51 Hr. $73.30 70.35 93.80 $2483.91 Crew B-7 Hr. Daily Hr. 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (medium) 1 Brush Chipper, 12⬙, 130 H.P. 1 Crawler Loader, 3 C.Y. 2 Chain Saws, Gas, 36⬙ Long $49.25 47.25 63.05 $394.00 1512.00 504.40 518.12 1257.68 107.22 $73.30 70.35 93.80 48 L.H., Daily Totals Crew B-7A 2 Laborers 1 Equip. Oper. (light) 1 Rake w/Tractor 2 Chain Saws, Gas, 18⬙ $4293.42 Hr. $47.25 59.70 24 L.H., Daily Totals Daily $756.00 477.60 161.55 95.16 Hr. $70.35 88.85 $1490.31 Crew B-7B Hr. Daily Hr. 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Brush Chipper, 12⬙, 130 H.P. 1 Crawler Loader, 3 C.Y. 2 Chain Saws, Gas, 36⬙ Long 1 Dump Truck, 8 C.Y., 220 H.P. $49.25 47.25 63.05 55.45 $394.00 1512.00 504.40 443.60 518.12 1257.68 107.22 417.49 $73.30 70.35 93.80 82.85 56 L.H., Daily Totals $5154.51 Crew B-7C Hr. Daily Hr. 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Brush Chipper, 12⬙, 130 H.P. 1 Crawler Loader, 3 C.Y. 2 Chain Saws, Gas, 36⬙ Long 1 Dump Truck, 12 C.Y., 400 H.P. $49.25 47.25 63.05 55.45 $394.00 1512.00 504.40 443.60 518.12 1257.68 107.22 791.36 $73.30 70.35 93.80 82.85 56 L.H., Daily Totals $5528.38 Cost Per Labor-Hour Bare Costs Incl. O&P $1172.80 2251.20 701.79 430.12 866.25 $47.92 $71.33 37.84 41.63 $5422.16 $85.76 $112.96 Daily Bare Costs Incl. O&P Daily $293.20 562.80 750.40 1544.96 $53.97 $80.32 70.23 77.25 $3151.36 $124.20 $157.57 Daily Bare Costs Incl. O&P $586.40 2251.20 750.40 569.93 1383.45 117.94 $50.22 $74.75 39.23 43.15 $5659.32 $89.45 $117.90 Daily Bare Costs Incl. O&P Crew No. Crew B-8 $51.40 $76.52 10.70 11.77 $2118.78 $62.10 $88.28 Daily Bare Costs Incl. O&P $586.40 2251.20 750.40 662.80 569.93 1383.45 117.94 459.24 $50.96 $75.91 41.08 45.19 $6781.36 $92.04 $121.10 Daily Bare Costs Incl. O&P $586.40 2251.20 750.40 662.80 569.93 1383.45 117.94 870.50 $50.96 $75.91 47.76 52.53 $7192.62 $98.72 $128.44 Hr. 1 Labor Foreman (outside) $49.25 2 Laborers 47.25 2 Equip. Oper. (medium) 63.05 1 Equip. Oper. (oiler) 56.40 2 Truck Drivers (heavy) 55.45 1 Hyd. Crane, 25 Ton 1 Crawler Loader, 3 C.Y. 2 Dump Trucks, 12 C.Y., 400 H.P. 64 L.H., Daily Totals Crew B-9 $1125.60 710.80 177.71 104.68 Bare Costs 1 Labor Foreman (outside) 4 Laborers 1 Air Compressor, 250 cfm 2 Breakers, Pavement, 60 lb. 2 -50’ Air Hoses, 1.5⬙ Incl. Subs O&P Daily Hr. $394.00 756.00 1008.80 451.20 887.20 2273.31 1257.68 1582.72 $73.30 70.35 93.80 83.90 82.85 $8610.91 Hr. Daily Hr. $49.25 47.25 $394.00 1512.00 196.28 68.94 47.20 $73.30 70.35 40 L.H., Daily Totals $2218.42 Crew B-9A Hr. Daily Hr. 2 Laborers 1 Truck Driver (heavy) 1 Water Tank Trailer, 5000 Gal. 1 Truck Tractor, 220 H.P. 2 -50’ Discharge Hoses, 3⬙ $47.25 55.45 $756.00 443.60 169.14 339.98 9.76 $70.35 82.85 24 L.H., Daily Totals $1718.48 Crew B-9B Hr. Daily Hr. 2 Laborers 1 Truck Driver (heavy) 2 -50’ Discharge Hoses, 3⬙ 1 Water Tank Trailer, 5000 Gal. 1 Truck Tractor, 220 H.P. 1 Pressure Washer $47.25 55.45 $756.00 443.60 9.76 169.14 339.98 104.23 $70.35 82.85 24 L.H., Daily Totals Crew B-9D 1 Labor Foreman (outside) 4 Common Laborers 1 Air Compressor, 250 cfm 2 -50’ Air Hoses, 1.5⬙ 2 Air Powered Tampers $1822.71 Hr. Daily Hr. $49.25 47.25 $394.00 1512.00 196.28 47.20 114.04 $73.30 70.35 40 L.H., Daily Totals $2263.52 Crew B-9E Hr. Daily Hr. 1 Cement Finisher 1 Laborer 1 Chip. Hammers, 12 Lb., Elec. $55.00 47.25 $440.00 378.00 27.16 $80.45 70.35 16 L.H., Daily Totals Crew B-10 1 Equip. Oper. (medium) .5 Laborer $845.16 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 $93.80 70.35 12 L.H., Daily Totals $693.40 Crew B-10A Hr. Daily Hr. 1 Equip. Oper. (medium) .5 Laborer 1 Roller, 2-Drum, W.B., 7.5 H.P. $63.05 47.25 $504.40 189.00 157.50 $93.80 70.35 12 L.H., Daily Totals $850.90 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 1125.60 1500.80 671.20 1325.60 2500.64 1383.45 1740.99 $54.64 $81.40 79.90 87.89 $10834.68 $134.55 $169.29 Daily Bare Costs Incl. O&P $586.40 2251.20 215.91 75.83 51.92 $47.65 $70.94 7.81 8.59 $3181.26 $55.46 $79.53 Daily Bare Costs Incl. O&P $1125.60 662.80 186.05 373.98 10.74 $49.98 $74.52 21.62 23.78 $2359.17 $71.60 $98.30 Daily Bare Costs Incl. O&P $1125.60 662.80 10.74 186.05 373.98 114.65 $49.98 $74.52 25.96 28.56 $2473.82 $75.95 $103.08 Daily Bare Costs Incl. O&P $586.40 2251.20 215.91 51.92 125.44 $47.65 $70.94 8.94 9.83 $3230.87 $56.59 $80.77 Daily Bare Costs Incl. O&P $643.60 562.80 29.88 $51.13 $75.40 1.70 1.87 $1236.28 $52.82 $77.27 Daily Bare Costs Incl. O&P $750.40 281.40 $57.78 $85.98 $1031.80 $57.78 $85.98 Daily Bare Costs Incl. O&P $750.40 281.40 173.25 $57.78 $85.98 13.13 14.44 $1205.05 $70.91 $100.42 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 753 Crews - Standard Crew No. Crew B-10B 1 Equip. Oper. (medium) .5 Laborer 1 Dozer, 200 H.P. Bare Costs Incl. Subs O&P Hr. Daily Hr. $63.05 47.25 $504.40 189.00 1382.36 $93.80 70.35 12 L.H., Daily Totals $2075.76 Crew B-10C Hr. Daily Hr. 1 Equip. Oper. (medium) .5 Laborer 1 Dozer, 200 H.P. 1 Vibratory Roller, Towed, 23 Ton $63.05 47.25 $504.40 189.00 1382.36 681.59 $93.80 70.35 12 L.H., Daily Totals Crew B-10D 1 Equip. Oper. (medium) .5 Laborer 1 Dozer, 200 H.P. 1 Sheepsft. Roller, Towed $2757.35 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 1382.36 444.83 $93.80 70.35 12 L.H., Daily Totals Crew B-10E 1 Equip. Oper. (medium) .5 Laborer 1 Tandem Roller, 5 Ton $2520.59 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 287.45 $93.80 70.35 12 L.H., Daily Totals Crew B-10F 1 Equip. Oper. (medium) .5 Laborer 1 Tandem Roller, 10 Ton $980.85 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 379.22 $93.80 70.35 12 L.H., Daily Totals Crew B-10G 1 Equip. Oper. (medium) .5 Laborer 1 Sheepsfoot Roller, 240 H.P. $1072.62 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 765.47 $93.80 70.35 12 L.H., Daily Totals Crew B-10H 1 Equip. Oper. (medium) .5 Laborer 1 Diaphragm Water Pump, 2⬙ 1 -20’ Suction Hose, 2⬙ 2 -50’ Discharge Hoses, 2⬙ $1458.87 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 61.92 4.37 8.18 $93.80 70.35 12 L.H., Daily Totals Crew B-10I 1 Equip. Oper. (medium) .5 Laborer 1 Diaphragm Water Pump, 4⬙ 1 -20’ Suction Hose, 4⬙ 2 -50’ Discharge Hoses, 4⬙ $767.87 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 150.72 19.04 28.30 $93.80 70.35 12 L.H., Daily Totals Crew B-10J 1 Equip. Oper. (medium) .5 Laborer 1 Centrifugal Water Pump, 3⬙ 1 -20’ Suction Hose, 3⬙ 2 -50’ Discharge Hoses, 3⬙ 12 L.H., Daily Totals 754 $891.46 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 82.39 8.96 9.76 $93.80 70.35 $794.51 Cost Per Labor-Hour Bare Costs Incl. O&P $750.40 281.40 1520.60 $57.78 $85.98 115.20 126.72 $2552.40 $172.98 $212.70 Daily Bare Costs Incl. O&P $750.40 281.40 1520.60 749.75 $57.78 $85.98 172.00 189.20 $3302.15 $229.78 $275.18 Daily Crew B-10K 1 Equip. Oper. (medium) .5 Laborer 1 Centr. Water Pump, 6⬙ 1 -20’ Suction Hose, 6⬙ 2 -50’ Discharge Hoses, 6⬙ Incl. O&P $750.40 281.40 1520.60 489.31 $57.78 $85.98 152.27 167.49 $3041.71 $210.05 $253.48 Daily Bare Costs Incl. O&P $750.40 281.40 316.19 $57.78 $85.98 23.95 26.35 $1347.99 $81.74 $112.33 Daily Bare Costs Incl. O&P $750.40 281.40 417.14 $57.78 $85.98 31.60 34.76 $1448.94 $89.39 $120.75 Daily Bare Costs Incl. O&P $750.40 281.40 842.02 $57.78 $85.98 63.79 70.17 $1873.82 $121.57 $156.15 Daily Bare Costs Incl. O&P $750.40 281.40 68.11 4.81 9.00 $57.78 $85.98 6.21 6.83 $1113.72 $63.99 $92.81 Daily Bare Costs Incl. O&P $750.40 281.40 165.79 20.94 31.13 $57.78 $85.98 16.50 18.16 $1249.67 $74.29 $104.14 Daily Bare Costs Incl. O&P $750.40 281.40 90.63 9.86 10.74 $57.78 $85.98 8.43 9.27 $1143.02 $66.21 $95.25 Bare Costs 1 Equip. Oper. (medium) .5 Laborer 1 Dozer, 80 H.P. Daily Hr. $63.05 47.25 $504.40 189.00 386.48 28.12 39.98 $93.80 70.35 $1147.98 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 591.82 $93.80 70.35 12 L.H., Daily Totals Crew B-10M 1 Equip. Oper. (medium) .5 Laborer 1 Dozer, 300 H.P. $1285.22 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 1674.53 $93.80 70.35 12 L.H., Daily Totals Crew B-10N 1 Equip. Oper. (medium) .5 Laborer 1 F.E. Loader, T.M., 1.5 C.Y. $2367.93 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 627.38 $93.80 70.35 12 L.H., Daily Totals Crew B-10O 1 Equip. Oper. (medium) .5 Laborer 1 F.E. Loader, T.M., 2.25 C.Y. $1320.78 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 958.76 $93.80 70.35 12 L.H., Daily Totals Crew B-10P 1 Equip. Oper. (medium) .5 Laborer 1 Crawler Loader, 3 C.Y. $1652.16 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 1257.68 $93.80 70.35 12 L.H., Daily Totals Crew B-10Q 1 Equip. Oper. (medium) .5 Laborer 1 Crawler Loader, 4 C.Y. $1951.08 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 1506.11 $93.80 70.35 12 L.H., Daily Totals Crew B-10R 1 Equip. Oper. (medium) .5 Laborer 1 F.E. Loader, W.M., 1 C.Y. $2199.51 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 394.79 $93.80 70.35 12 L.H., Daily Totals Crew B-10S 1 Equip. Oper. (medium) .5 Laborer 1 F.E. Loader, W.M., 1.5 C.Y. $1088.19 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 455.32 $93.80 70.35 12 L.H., Daily Totals Crew B-10T 1 Equip. Oper. (medium) .5 Laborer 1 F.E. Loader, W.M., 2.5 C.Y. 12 L.H., Daily Totals Incl. Subs O&P Hr. 12 L.H., Daily Totals Crew B-10L Bare Costs Daily Crew No. $1148.72 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 658.89 $93.80 70.35 $1352.29 Cost Per Labor-Hour Bare Costs Incl. O&P $750.40 281.40 425.13 30.93 43.98 $57.78 $85.98 37.88 41.67 $1531.84 $95.67 $127.65 Daily Bare Costs Incl. O&P $750.40 281.40 651.00 $57.78 $85.98 49.32 54.25 $1682.80 $107.10 $140.23 Daily Bare Costs Incl. O&P $750.40 281.40 1841.98 $57.78 $85.98 139.54 153.50 $2873.78 $197.33 $239.48 Daily Bare Costs Incl. O&P $750.40 281.40 690.12 $57.78 $85.98 52.28 57.51 $1721.92 $110.07 $143.49 Daily Bare Costs Incl. O&P $750.40 281.40 1054.64 $57.78 $85.98 79.90 87.89 $2086.44 $137.68 $173.87 Daily Bare Costs Incl. O&P $750.40 281.40 1383.45 $57.78 $85.98 104.81 115.29 $2415.25 $162.59 $201.27 Daily Bare Costs Incl. O&P $750.40 281.40 1656.72 $57.78 $85.98 125.51 138.06 $2688.52 $183.29 $224.04 Daily Bare Costs Incl. O&P $750.40 281.40 434.27 $57.78 $85.98 32.90 36.19 $1466.07 $90.68 $122.17 Daily Bare Costs Incl. O&P $750.40 281.40 500.85 $57.78 $85.98 37.94 41.74 $1532.65 $95.73 $127.72 Daily Bare Costs Incl. O&P $750.40 281.40 724.78 $57.78 $85.98 54.91 60.40 $1756.58 $112.69 $146.38 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew B-10U 1 Equip. Oper. (medium) .5 Laborer 1 F.E. Loader, W.M., 5.5 C.Y. Bare Costs Hr. Daily Hr. $63.05 47.25 $504.40 189.00 1186.42 $93.80 70.35 12 L.H., Daily Totals Crew B-10V 1 Equip. Oper. (medium) .5 Laborer 1 Dozer, 700 H.P. $1879.82 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 4098.16 $93.80 70.35 12 L.H., Daily Totals Crew B-10W 1 Equip. Oper. (medium) .5 Laborer 1 Dozer, 105 H.P. $4791.56 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 702.68 $93.80 70.35 12 L.H., Daily Totals Crew B-10X 1 Equip. Oper. (medium) .5 Laborer 1 Dozer, 410 H.P. $1396.08 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 2535.96 $93.80 70.35 12 L.H., Daily Totals Crew B-10Y 1 Equip. Oper. (medium) .5 Laborer 1 Vibr. Roller, Towed, 12 Ton $3229.36 Hr. $63.05 47.25 12 L.H., Daily Totals Crew B-11A 1 Equipment Oper. (med.) 1 Laborer 1 Dozer, 200 H.P. 1 Equipment Oper. (light) 1 Laborer 1 Air Powered Tamper 1 Air Compressor, 365 cfm 2 -50’ Air Hoses, 1.5⬙ Hr. $63.05 47.25 1 Equipment Oper. (med.) 1 Laborer 1 Backhoe Loader, 48 H.P. Hr. $59.70 47.25 1 Equipment Oper. (med.) 1 Laborer 1 Grader, 30,000 Lbs. 1 Ripper, Beam & 1 Shank 16 L.H., Daily Totals $93.80 70.35 Daily $504.40 378.00 1382.36 Hr. $93.80 70.35 Daily $477.60 378.00 57.02 389.99 47.20 Hr. $88.85 70.35 $1349.81 Hr. Daily Hr. $63.05 47.25 $504.40 378.00 277.19 $93.80 70.35 16 L.H., Daily Totals Crew B-11J $504.40 189.00 346.96 Hr. $2264.76 16 L.H., Daily Totals Crew B-11C Daily $1040.36 16 L.H., Daily Totals Crew B-11B Incl. Subs O&P $1159.59 Hr. $63.05 47.25 Daily $504.40 378.00 1091.19 100.54 $2074.13 Hr. $93.80 70.35 Cost Per Labor-Hour Bare Costs Incl. O&P $750.40 281.40 1305.06 $57.78 $85.98 98.87 108.76 $2336.86 $156.65 $194.74 Daily Bare Costs Incl. O&P $750.40 281.40 4507.98 $57.78 $85.98 341.51 375.66 $5539.78 $399.30 $461.65 Daily Bare Costs Incl. O&P $750.40 281.40 772.95 $57.78 $85.98 58.56 64.41 $1804.75 $116.34 $150.40 Daily Bare Costs Incl. O&P $750.40 281.40 2789.56 $57.78 $85.98 211.33 232.46 $3821.36 $269.11 $318.45 Daily Bare Costs Incl. O&P Daily $750.40 281.40 381.66 $57.78 $85.98 28.91 31.80 $1413.46 $86.70 $117.79 Daily Bare Costs Incl. O&P $750.40 562.80 1520.60 $55.15 $82.08 86.40 95.04 $2833.80 $141.55 $177.11 Daily Bare Costs Incl. O&P $710.80 562.80 62.72 428.99 51.92 $53.48 $79.60 30.89 33.98 $1817.23 $84.36 $113.58 Daily Bare Costs Incl. O&P $750.40 562.80 304.91 $55.15 $82.08 17.32 19.06 $1618.11 $72.47 $101.13 Daily Bare Costs Incl. O&P Crew No. Crew B-11K 1 Equipment Oper. (med.) 1 Laborer 1 Trencher, Chain Type, 8’ D Crew B-11L 1 Equipment Oper. (med.) 1 Laborer 1 Grader, 30,000 Lbs. 1 Equipment Oper. (med.) 1 Laborer 1 Backhoe Loader, 80 H.P. $82.08 74.48 81.93 $2624.10 $129.63 $164.01 Hr. $63.05 47.25 $504.40 378.00 2079.03 $93.80 70.35 $2961.43 Hr. Daily Hr. $63.05 47.25 $504.40 378.00 1091.19 $93.80 70.35 $1973.59 Hr. Daily Hr. $63.05 47.25 $504.40 378.00 357.71 $93.80 70.35 16 L.H., Daily Totals $1240.11 Crew B-11N Hr. Daily Hr. 1 Labor Foreman (outside) 2 Equipment Operators (med.) 6 Truck Drivers (heavy) 1 F.E. Loader, W.M., 5.5 C.Y. 1 Dozer, 410 H.P. 6 Dump Trucks, Off Hwy., 50 Ton $49.25 63.05 55.45 $394.00 1008.80 2661.60 1186.42 2535.96 12225.60 $73.30 93.80 82.85 72 L.H., Daily Totals Crew B-11Q 1 Equipment Operator (med.) .5 Laborer 1 Dozer, 140 H.P. $20012.38 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 757.89 $93.80 70.35 12 L.H., Daily Totals Crew B-11R 1 Equipment Operator (med.) .5 Laborer 1 Dozer, 200 H.P. $1451.29 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 1382.36 $93.80 70.35 12 L.H., Daily Totals 1 Equipment Operator (med.) .5 Laborer 1 Dozer, 300 H.P. 1 Ripper, Beam & 1 Shank $2075.76 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 1674.53 100.54 $93.80 70.35 12 L.H., Daily Totals Crew B-11T $55.15 Daily 16 L.H., Daily Totals Crew B-11M Incl. Subs O&P Hr. 16 L.H., Daily Totals Crew B-11S $750.40 562.80 1200.31 110.59 Bare Costs 1 Equipment Operator (med.) .5 Laborer 1 Dozer, 410 H.P. 1 Ripper, Beam & 2 Shanks $2468.47 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 2535.96 154.19 $93.80 70.35 12 L.H., Daily Totals Crew B-11U 1 Equipment Operator (med.) .5 Laborer 1 Dozer, 520 H.P. 12 L.H., Daily Totals $3383.55 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 2569.55 $93.80 70.35 $3262.95 Cost Per Labor-Hour Bare Costs Incl. O&P $750.40 562.80 2286.93 $55.15 $82.08 129.94 142.93 $3600.13 $185.09 $225.01 Daily Bare Costs Incl. O&P $750.40 562.80 1200.31 $55.15 $82.08 68.20 75.02 $2513.51 $123.35 $157.09 Daily Bare Costs Incl. O&P $750.40 562.80 393.48 $55.15 $82.08 22.36 24.59 $1706.68 $77.51 $106.67 Daily Bare Costs Incl. O&P $586.40 1500.80 3976.80 1305.06 2789.56 13448.16 $56.45 $84.22 221.50 243.65 $23606.78 $277.95 $327.87 Daily Bare Costs Incl. O&P $750.40 281.40 833.68 $57.78 $85.98 63.16 69.47 $1865.48 $120.94 $155.46 Daily Bare Costs Incl. O&P $750.40 281.40 1520.60 $57.78 $85.98 115.20 126.72 $2552.40 $172.98 $212.70 Daily Bare Costs Incl. O&P $750.40 281.40 1841.98 110.59 $57.78 $85.98 147.92 162.71 $2984.38 $205.71 $248.70 Daily Bare Costs Incl. O&P $750.40 281.40 2789.56 169.61 $57.78 $85.98 224.18 246.60 $3990.97 $281.96 $332.58 Daily Bare Costs Incl. O&P $750.40 281.40 2826.51 $57.78 $85.98 214.13 235.54 $3858.30 $271.91 $321.53 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 755 Crews - Standard Crew No. Bare Costs Incl. Subs O&P Crew B-11V Hr. Daily Hr. 3 Laborers 1 Roller, 2-Drum, W.B., 7.5 H.P. $47.25 $1134.00 157.50 $70.35 24 L.H., Daily Totals Crew B-11W $1291.50 Hr. 1 Equipment Operator (med.) $63.05 1 Common Laborer 47.25 10 Truck Drivers (heavy) 55.45 1 Dozer, 200 H.P. 1 Vibratory Roller, Towed, 23 Ton 10 Dump Trucks, 8 C.Y., 220 H.P. 96 L.H., Daily Totals Daily Hr. $504.40 378.00 4436.00 1382.36 681.59 4174.90 $93.80 70.35 82.85 $11557.25 Crew B-11Y Hr. Daily Hr. 1 Labor Foreman (outside) 5 Common Laborers 3 Equipment Operators (med.) 1 Dozer, 80 H.P. 2 Rollers, 2-Drum, W.B., 7.5 H.P. 4 Vibrating Plates, Gas, 21⬙ $49.25 47.25 63.05 $394.00 1890.00 1513.20 591.82 315.00 584.48 $73.30 70.35 93.80 72 L.H., Daily Totals Crew B-12A 1 Equip. Oper. (crane) 1 Laborer 1 Hyd. Excavator, 1 C.Y. $5288.50 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 986.56 $98.65 70.35 16 L.H., Daily Totals Crew B-12B 1 Equip. Oper. (crane) 1 Laborer 1 Hyd. Excavator, 1.5 C.Y. $1894.96 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 1185.24 $98.65 70.35 16 L.H., Daily Totals Crew B-12C 1 Equip. Oper. (crane) 1 Laborer 1 Hyd. Excavator, 2 C.Y. $2093.64 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 1096.14 $98.65 70.35 16 L.H., Daily Totals Crew B-12D 1 Equip. Oper. (crane) 1 Laborer 1 Hyd. Excavator, 3.5 C.Y. $2004.54 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 2394.44 $98.65 70.35 16 L.H., Daily Totals Crew B-12E 1 Equip. Oper. (crane) 1 Laborer 1 Hyd. Excavator, .5 C.Y. $3302.84 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 764.88 $98.65 70.35 16 L.H., Daily Totals Crew B-12F 1 Equip. Oper. (crane) 1 Laborer 1 Hyd. Excavator, .75 C.Y. 16 L.H., Daily Totals $1673.28 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 915.34 $98.65 70.35 $1823.74 Cost Per Labor-Hour Daily Bare Costs Incl. O&P $1688.40 173.25 $47.25 6.56 $70.35 7.22 $1861.65 $53.81 $77.57 Daily Bare Costs Incl. O&P $750.40 562.80 6628.00 1520.60 749.75 4592.39 $55.40 $82.72 64.99 71.49 $14803.93 $120.39 $154.21 Daily Bare Costs Incl. O&P $586.40 2814.00 2251.20 651.00 346.50 642.93 $52.74 $78.49 20.71 22.78 $7292.03 $73.45 $101.28 Daily Bare Costs Incl. O&P $789.20 562.80 1085.22 $56.77 $84.50 61.66 67.83 $2437.22 $118.44 $152.33 Daily Bare Costs Incl. O&P $789.20 562.80 1303.76 $56.77 $84.50 74.08 81.49 $2655.76 $130.85 $165.99 Daily Bare Costs Incl. O&P $789.20 562.80 1205.75 $56.77 $84.50 68.51 75.36 $2557.75 $125.28 $159.86 Daily Bare Costs Incl. O&P $789.20 562.80 2633.88 $56.77 $84.50 149.65 164.62 $3985.88 $206.43 $249.12 Daily Bare Costs Incl. O&P $789.20 562.80 841.37 $56.77 $84.50 47.81 52.59 $2193.37 $104.58 $137.09 Crew B-12G 1 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 15 Ton 1 Clamshell Bucket, .5 C.Y. 1 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 25 Ton 1 Clamshell Bucket, 1 C.Y. Crew B-12I 1 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 20 Ton 1 Dragline Bucket, .75 C.Y. Daily Hr. $66.30 47.25 $530.40 378.00 898.84 37.28 $98.65 70.35 $1844.52 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 1274.00 46.89 $98.65 70.35 $2229.29 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 1120.87 29.54 $98.65 70.35 16 L.H., Daily Totals Crew B-12J 1 Equip. Oper. (crane) 1 Laborer 1 Gradall, 5/8 C.Y. $2058.81 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 880.91 $98.65 70.35 16 L.H., Daily Totals Crew B-12K 1 Equip. Oper. (crane) 1 Laborer 1 Gradall, 3 Ton, 1 C.Y. $1789.31 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 1520.84 $98.65 70.35 16 L.H., Daily Totals Incl. O&P $789.20 562.80 1006.87 $56.77 $84.50 57.21 62.93 $2358.87 $113.98 $147.43 Crew B-12L 1 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 15 Ton 1 F.E. Attachment, .5 C.Y. $2429.24 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 898.84 72.55 $98.65 70.35 16 L.H., Daily Totals Crew B-12M 1 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 20 Ton 1 F.E. Attachment, .75 C.Y. $1879.79 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 1120.87 78.31 $98.65 70.35 16 L.H., Daily Totals Crew B-12N 1 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 25 Ton 1 F.E. Attachment, 1 C.Y. $2107.58 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 1274.00 59.18 $98.65 70.35 16 L.H., Daily Totals Crew B-12O 1 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 40 Ton 1 F.E. Attachment, 1.5 C.Y. Incl. Subs O&P Hr. 16 L.H., Daily Totals 16 L.H., Daily Totals 756 Bare Costs 16 L.H., Daily Totals Crew B-12H Bare Costs Daily Crew No. $2241.58 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 1362.63 97.47 $98.65 70.35 $2368.50 Cost Per Labor-Hour Bare Costs Incl. O&P $789.20 562.80 988.72 41.01 $56.77 $84.50 58.51 64.36 $2381.73 $115.28 $148.86 Daily Bare Costs Incl. O&P $789.20 562.80 1401.40 51.58 $56.77 $84.50 82.56 90.81 $2804.98 $139.33 $175.31 Daily Bare Costs Incl. O&P $789.20 562.80 1232.96 32.49 $56.77 $84.50 71.90 79.09 $2617.45 $128.68 $163.59 Daily Bare Costs Incl. O&P $789.20 562.80 969.00 $56.77 $84.50 55.06 60.56 $2321.00 $111.83 $145.06 Daily Bare Costs Incl. O&P $789.20 562.80 1672.92 $56.77 $84.50 95.05 104.56 $3024.92 $151.83 $189.06 Daily Bare Costs Incl. O&P $789.20 562.80 988.72 79.81 $56.77 $84.50 60.71 66.78 $2420.53 $117.49 $151.28 Daily Bare Costs Incl. O&P $789.20 562.80 1232.96 86.14 $56.77 $84.50 74.95 82.44 $2671.10 $131.72 $166.94 Daily Bare Costs Incl. O&P $789.20 562.80 1401.40 65.10 $56.77 $84.50 83.32 91.66 $2818.50 $140.10 $176.16 Daily Bare Costs Incl. O&P $789.20 562.80 1498.89 107.22 $56.77 $84.50 91.26 100.38 $2958.11 $148.03 $184.88 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew B-12P 1 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 40 Ton 1 Dragline Bucket, 1.5 C.Y. Bare Costs Hr. Daily Hr. $66.30 47.25 $530.40 378.00 1362.63 37.32 $98.65 70.35 16 L.H., Daily Totals Crew B-12Q 1 Equip. Oper. (crane) 1 Laborer 1 Hyd. Excavator, 5/8 C.Y. $2308.35 Hr. $66.30 47.25 16 L.H., Daily Totals Crew B-12S 1 Equip. Oper. (crane) 1 Laborer 1 Hyd. Excavator, 2.5 C.Y. 1 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 75 Ton 1 F.E. Attachment, 3 C.Y. Crew B-12V 1 Equip. Oper. (crane) 2 Laborers 1 Hyd. Excavator, 3.5 C.Y. Hr. $66.30 47.25 $530.40 378.00 1683.69 $98.65 70.35 $2592.09 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 2189.46 127.10 $98.65 70.35 $3224.96 Hr. Daily Hr. $66.30 47.25 $530.40 378.00 2189.46 51.71 $98.65 70.35 $3149.57 Hr. Daily Hr. $66.30 47.25 $530.40 756.00 2394.44 $98.65 70.35 24 L.H., Daily Totals Crew B-12Z 1 Equip. Oper. (crane) 2 Laborers 1 Hyd. Excavator, 2.5 C.Y. $3680.84 Hr. Daily Hr. $66.30 47.25 $530.40 756.00 1683.69 $98.65 70.35 24 L.H., Daily Totals Crew B-13 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 25 Ton 56 L.H., Daily Totals $98.65 70.35 Daily 16 L.H., Daily Totals Crew B-12Y $530.40 378.00 813.17 Hr. Hr. 16 L.H., Daily Totals 1 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 75 Ton 1 Dragline Bucket, 3 C.Y. Daily $1721.57 16 L.H., Daily Totals Crew B-12T Incl. Subs O&P $2970.09 Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 1512.00 530.40 451.20 2273.31 $73.30 70.35 98.65 83.90 $5160.91 Cost Per Labor-Hour Bare Costs Incl. O&P $789.20 562.80 1498.89 41.05 $56.77 $84.50 87.50 96.25 $2891.95 $144.27 $180.75 Daily Bare Costs Incl. O&P Daily $789.20 562.80 894.49 $56.77 $84.50 50.82 55.91 $2246.49 $107.60 $140.41 Daily Bare Costs Incl. O&P $789.20 562.80 1852.06 $56.77 $84.50 105.23 115.75 $3204.06 $162.01 $200.25 Bare Costs Incl. O&P $789.20 562.80 2408.41 139.81 $56.77 $84.50 144.79 159.26 $3900.22 $201.56 $243.76 Daily Bare Costs Incl. O&P $789.20 562.80 2408.41 56.88 $56.77 $84.50 140.07 154.08 $3817.29 $196.85 $238.58 Daily Bare Costs Incl. O&P $789.20 1125.60 2633.88 $53.60 $79.78 99.77 109.75 $4548.68 $153.37 $189.53 Daily Bare Costs Incl. O&P $789.20 1125.60 1852.06 $53.60 $79.78 70.15 77.17 $3766.86 $123.75 $156.95 Daily Bare Costs Incl. O&P $586.40 2251.20 789.20 671.20 2500.64 $51.56 $76.75 40.59 44.65 $6798.64 $92.16 $121.40 Daily Crew No. Bare Costs Incl. Subs O&P Crew B-13A Hr. Daily Hr. 1 Labor Foreman (outside) 2 Laborers 2 Equipment Operators (med.) 2 Truck Drivers (heavy) 1 Crawler Crane, 75 Ton 1 Crawler Loader, 4 C.Y. 2 Dump Trucks, 8 C.Y., 220 H.P. $49.25 47.25 63.05 55.45 $394.00 756.00 1008.80 887.20 2189.46 1506.11 834.98 $73.30 70.35 93.80 82.85 56 L.H., Daily Totals Crew B-13B 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 55 Ton $7576.55 Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 1512.00 530.40 451.20 2461.06 $73.30 70.35 98.65 83.90 56 L.H., Daily Totals Crew B-13C 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Crawler Crane, 100 Ton $5348.66 Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 1512.00 530.40 451.20 1552.12 $73.30 70.35 98.65 83.90 56 L.H., Daily Totals Crew B-13D 1 Laborer 1 Equip. Oper. (crane) 1 Hyd. Excavator, 1 C.Y. 1 Trench Box $4439.72 Hr. Daily Hr. $47.25 66.30 $378.00 530.40 986.56 131.49 $70.35 98.65 16 L.H., Daily Totals Crew B-13E 1 Laborer 1 Equip. Oper. (crane) 1 Hyd. Excavator, 1.5 C.Y. 1 Trench Box $2026.45 Hr. Daily Hr. $47.25 66.30 $378.00 530.40 1185.24 131.49 $70.35 98.65 16 L.H., Daily Totals Crew B-13F 1 Laborer 1 Equip. Oper. (crane) 1 Hyd. Excavator, 3.5 C.Y. 1 Trench Box $2225.13 Hr. Daily Hr. $47.25 66.30 $378.00 530.40 2394.44 131.49 $70.35 98.65 16 L.H., Daily Totals Crew B-13G 1 Laborer 1 Equip. Oper. (crane) 1 Hyd. Excavator, .75 C.Y. 1 Trench Box $3434.33 Hr. Daily Hr. $47.25 66.30 $378.00 530.40 915.34 131.49 $70.35 98.65 16 L.H., Daily Totals Crew B-13H 1 Laborer 1 Equip. Oper. (crane) 1 Gradall, 5/8 C.Y. 1 Trench Box 16 L.H., Daily Totals $1955.23 Hr. Daily Hr. $47.25 66.30 $378.00 530.40 880.91 131.49 $70.35 98.65 $1920.80 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 1125.60 1500.80 1325.60 2408.41 1656.72 918.48 $54.39 $81.04 80.90 88.99 $9522.00 $135.30 $170.04 Daily Bare Costs Incl. O&P $586.40 2251.20 789.20 671.20 2707.17 $51.56 $76.75 43.95 48.34 $7005.17 $95.51 $125.09 Daily Bare Costs Incl. O&P $586.40 2251.20 789.20 671.20 1707.33 $51.56 $76.75 27.72 30.49 $6005.33 $79.28 $107.24 Daily Bare Costs Incl. O&P $562.80 789.20 1085.22 144.64 $56.77 $84.50 69.88 76.87 $2581.86 $126.65 $161.37 Daily Bare Costs Incl. O&P $562.80 789.20 1303.76 144.64 $56.77 $84.50 82.30 90.53 $2800.40 $139.07 $175.03 Daily Bare Costs Incl. O&P $562.80 789.20 2633.88 144.64 $56.77 $84.50 157.87 173.66 $4130.52 $214.65 $258.16 Daily Bare Costs Incl. O&P $562.80 789.20 1006.87 144.64 $56.77 $84.50 65.43 71.97 $2503.51 $122.20 $156.47 Daily Bare Costs Incl. O&P $562.80 789.20 969.00 144.64 $56.77 $84.50 63.27 69.60 $2465.64 $120.05 $154.10 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 757 Crews - Standard Crew No. Crew B-13I 1 Laborer 1 Equip. Oper. (crane) 1 Gradall, 3 Ton, 1 C.Y. 1 Trench Box Bare Costs Hr. Daily Hr. $47.25 66.30 $378.00 530.40 1520.84 131.49 $70.35 98.65 16 L.H., Daily Totals Crew B-13J 1 Laborer 1 Equip. Oper. (crane) 1 Hyd. Excavator, 2.5 C.Y. 1 Trench Box $2560.73 Hr. Daily Hr. $47.25 66.30 $378.00 530.40 1683.69 131.49 $70.35 98.65 16 L.H., Daily Totals Crew B-13K 2 Equip. Opers. (crane) 1 Hyd. Excavator, .75 C.Y. 1 Hyd. Hammer, 4000 ft-lb 1 Hyd. Excavator, .75 C.Y. $2723.58 Hr. Daily Hr. $66.30 $1060.80 915.34 715.03 915.34 $98.65 16 L.H., Daily Totals Crew B-13L 2 Equip. Opers. (crane) 1 Hyd. Excavator, 1.5 C.Y. 1 Hyd. Hammer, 5000 ft-lb 1 Hyd. Excavator, .75 C.Y. $3606.51 Hr. Daily Hr. $66.30 $1060.80 1185.24 776.94 915.34 $98.65 16 L.H., Daily Totals Crew B-13M 2 Equip. Opers. (crane) 1 Hyd. Excavator, 2.5 C.Y. 1 Hyd. Hammer, 8000 ft-lb 1 Hyd. Excavator, 1.5 C.Y. $3938.32 Hr. Daily Hr. $66.30 $1060.80 1683.69 1011.13 1185.24 $98.65 16 L.H., Daily Totals Crew B-13N 2 Equip. Opers. (crane) 1 Hyd. Excavator, 3.5 C.Y. 1 Hyd. Hammer, 12,000 ft-lb 1 Hyd. Excavator, 1.5 C.Y. $4940.86 Hr. Daily Hr. $66.30 $1060.80 2394.44 1162.80 1185.24 $98.65 16 L.H., Daily Totals Crew B-14 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (light) 1 Backhoe Loader, 48 H.P. $5803.28 Hr. Daily Hr. $49.25 47.25 59.70 $394.00 1512.00 477.60 277.19 $73.30 70.35 88.85 48 L.H., Daily Totals Crew B-14A 1 Equip. Oper. (crane) .5 Laborer 1 Hyd. Excavator, 4.5 C.Y. $2660.79 Hr. Daily Hr. $66.30 47.25 $530.40 189.00 3788.37 $98.65 70.35 12 L.H., Daily Totals Crew B-14B 1 Equip. Oper. (crane) .5 Laborer 1 Hyd. Excavator, 6 C.Y. 12 L.H., Daily Totals 758 Incl. Subs O&P $4507.77 Hr. Daily Hr. $66.30 47.25 $530.40 189.00 3843.97 $98.65 70.35 $4563.37 Cost Per Labor-Hour Crew No. Bare Costs Incl. Subs O&P Bare Costs Incl. O&P $562.80 789.20 1672.92 144.64 $56.77 $84.50 1 Equip. Oper. (crane) .5 Laborer 1 Hyd. Excavator, 7 C.Y. 103.27 113.60 12 L.H., Daily Totals $3169.56 $160.05 $198.10 Daily Bare Costs Incl. O&P $562.80 789.20 1852.06 144.64 $56.77 $84.50 113.45 124.79 $3348.70 $170.22 $209.29 Daily Bare Costs Incl. O&P $1578.40 1006.87 786.53 1006.87 $66.30 $98.65 159.11 175.02 $4378.68 $225.41 $273.67 Daily Bare Costs Incl. O&P $1578.40 1303.76 854.63 1006.87 $66.30 $98.65 179.85 197.83 $4743.67 $246.15 $296.48 Daily Bare Costs Incl. O&P $1578.40 1852.06 1112.24 1303.76 $66.30 $98.65 242.50 266.75 $5846.47 $308.80 $365.40 Daily Bare Costs Incl. O&P $1578.40 2633.88 1279.08 1303.76 $66.30 $98.65 296.40 326.05 $6795.13 $362.70 $424.70 Daily Bare Costs Incl. O&P $586.40 2251.20 710.80 304.91 $49.66 $73.92 5.77 6.35 $3853.31 $55.43 $80.28 Daily Bare Costs Incl. O&P $789.20 281.40 4167.21 $59.95 $89.22 315.70 347.27 $5237.81 $375.65 $436.48 Crew B-17A Hr. Daily Hr. Daily Bare Costs Incl. O&P $789.20 281.40 4228.37 $59.95 $89.22 2 Labor Foremen (outside) 6 Laborers 1 Skilled Worker Foreman (out) 1 Skilled Worker $49.25 47.25 63.25 61.25 $788.00 2268.00 506.00 490.00 $73.30 70.35 95.00 92.00 320.33 352.36 $5298.97 $380.28 $441.58 Daily Crew B-14C Crew B-14F 1 Equip. Oper. (crane) .5 Laborer 1 Hyd. Shovel, 7 C.Y. Hr. Daily Hr. $66.30 47.25 $530.40 189.00 4206.21 $98.65 70.35 $4925.61 Hr. Daily Hr. $66.30 47.25 $530.40 189.00 4549.05 $98.65 70.35 12 L.H., Daily Totals Crew B-14G 1 Equip. Oper. (crane) .5 Laborer 1 Hyd. Shovel, 12 C.Y. $5268.45 Hr. Daily Hr. $66.30 47.25 $530.40 189.00 6601.66 $98.65 70.35 12 L.H., Daily Totals Crew B-14J 1 Equip. Oper. (medium) .5 Laborer 1 F.E. Loader, 8 C.Y. $7321.06 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 1999.44 $93.80 70.35 12 L.H., Daily Totals Crew B-14K 1 Equip. Oper. (medium) .5 Laborer 1 F.E. Loader, 10 C.Y. $2692.84 Hr. Daily Hr. $63.05 47.25 $504.40 189.00 2862.71 $93.80 70.35 12 L.H., Daily Totals Crew B-15 $3556.11 Hr. 1 Equipment Oper. (med.) $63.05 .5 Laborer 47.25 2 Truck Drivers (heavy) 55.45 2 Dump Trucks, 12 C.Y., 400 H.P. 1 Dozer, 200 H.P. 28 L.H., Daily Totals Daily Hr. $504.40 189.00 887.20 1582.72 1382.36 $93.80 70.35 82.85 $4545.68 Crew B-16 Hr. Daily Hr. 1 Labor Foreman (outside) 2 Laborers 1 Truck Driver (heavy) 1 Dump Truck, 12 C.Y., 400 H.P. $49.25 47.25 55.45 $394.00 756.00 443.60 791.36 $73.30 70.35 82.85 32 L.H., Daily Totals $2384.96 Crew B-17 Hr. Daily Hr. 2 Laborers 1 Equip. Oper. (light) 1 Truck Driver (heavy) 1 Backhoe Loader, 48 H.P. 1 Dump Truck, 8 C.Y., 220 H.P. $47.25 59.70 55.45 $756.00 477.60 443.60 277.19 417.49 $70.35 88.85 82.85 32 L.H., Daily Totals 80 L.H., Daily Totals $2371.88 $4052.00 Cost Per Labor-Hour Bare Costs Incl. O&P $789.20 281.40 4626.83 $59.95 $89.22 350.52 385.57 $5697.43 $410.47 $474.79 Daily Bare Costs Incl. O&P $789.20 281.40 5003.95 $59.95 $89.22 379.09 417.00 $6074.56 $439.04 $506.21 Daily Bare Costs Incl. O&P $789.20 281.40 7261.83 $59.95 $89.22 550.14 605.15 $8332.43 $610.09 $694.37 Daily Bare Costs Incl. O&P $750.40 281.40 2199.38 $57.78 $85.98 166.62 183.28 $3231.18 $224.40 $269.27 Daily Bare Costs Incl. O&P $750.40 281.40 3148.98 $57.78 $85.98 238.56 262.42 $4180.78 $296.34 $348.40 Daily Bare Costs Incl. O&P $750.40 281.40 1325.60 1740.99 1520.60 $56.45 $84.19 105.90 116.49 $5618.99 $162.35 $200.68 Daily Bare Costs Incl. O&P $586.40 1125.60 662.80 870.50 $49.80 $74.21 24.73 27.20 $3245.30 $74.53 $101.42 Daily Bare Costs Incl. O&P $1125.60 710.80 662.80 304.91 459.24 $52.41 $78.10 21.71 23.88 $3263.35 $74.12 $101.98 Daily Bare Costs Incl. O&P $1172.80 3376.80 760.00 736.00 $50.65 $75.57 $6045.60 $50.65 $75.57 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Bare Costs Incl. Subs O&P Crew B-17B Hr. Daily Hr. 2 Laborers 1 Equip. Oper. (light) 1 Truck Driver (heavy) 1 Backhoe Loader, 48 H.P. 1 Dump Truck, 12 C.Y., 400 H.P. $47.25 59.70 55.45 $756.00 477.60 443.60 277.19 791.36 $70.35 88.85 82.85 32 L.H., Daily Totals Crew B-17C 1 Labor Foreman (outside) 3 Laborers 1 Equip. Oper. (heavy) 1 Truck Driver (heavy) 1 Hyd. Excavator, 2 C.Y. 1 Dump Truck, 12 C.Y., 400 H.P. 1 P/U, 3/4 ton, Tool Truck $2745.75 Hr. $49.25 47.25 66.30 55.45 48 L.H., Daily Totals Crew B-18 1 Labor Foreman (outside) 2 Laborers 1 Vibrating Plate, Gas, 21⬙ Daily $394.00 1134.00 530.40 443.60 1096.14 791.36 157.41 Hr. $73.30 70.35 98.65 82.85 $4546.91 Hr. Daily Hr. $49.25 47.25 $394.00 756.00 146.12 $73.30 70.35 24 L.H., Daily Totals $1296.12 Crew B-19 Hr. Daily Hr. 1 Pile Driver Foreman (outside) 4 Pile Drivers 2 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Crawler Crane, 40 Ton 1 Lead, 90’ High 1 Hammer, Diesel, 22k ft-lb $62.50 60.50 66.30 56.40 $500.00 1936.00 1060.80 451.20 1362.63 409.90 485.21 $96.70 93.60 98.65 83.90 64 L.H., Daily Totals $6205.74 Crew B-19A Hr. Daily Hr. 1 Pile Driver Foreman (outside) 4 Pile Drivers 2 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Crawler Crane, 75 Ton 1 Lead, 90’ High 1 Hammer, Diesel, 41k ft-lb $62.50 60.50 66.30 56.40 $500.00 1936.00 1060.80 451.20 2189.46 409.90 640.74 $96.70 93.60 98.65 83.90 64 L.H., Daily Totals $7188.10 Crew B-19B Hr. Daily Hr. 1 Pile Driver Foreman (outside) 4 Pile Drivers 2 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Crawler Crane, 40 Ton 1 Lead, 90’ High 1 Hammer, Diesel, 22k ft-lb 1 Barge, 400 Ton $62.50 60.50 66.30 56.40 $500.00 1936.00 1060.80 451.20 1362.63 409.90 485.21 957.33 $96.70 93.60 98.65 83.90 64 L.H., Daily Totals $7163.07 Cost Per Labor-Hour Bare Costs Incl. O&P $1125.60 710.80 662.80 304.91 870.50 $52.41 $78.10 33.39 36.73 $3674.61 $85.80 $114.83 Daily Bare Costs Incl. O&P Daily $586.40 1688.40 789.20 662.80 1205.75 870.50 173.15 $52.13 $77.64 42.60 46.86 $5976.20 $94.73 $124.50 Daily Bare Costs Incl. O&P $586.40 1125.60 160.73 $47.92 $71.33 6.09 6.70 $1872.73 $54.01 $78.03 Daily Bare Costs Incl. O&P $773.60 2995.20 1578.40 671.20 1498.89 450.89 533.73 $61.69 $94.04 35.28 38.80 $8501.91 $96.96 $132.84 Daily Bare Costs Incl. O&P $773.60 2995.20 1578.40 671.20 2408.41 450.89 704.81 $61.69 $94.04 50.63 55.69 $9582.51 $112.31 $149.73 Daily Bare Costs Incl. O&P $773.60 2995.20 1578.40 671.20 1498.89 450.89 533.73 1053.06 $61.69 $94.04 50.24 55.26 $9554.98 $111.92 $149.30 Crew No. Bare Costs Incl. Subs O&P Crew B-19C Hr. Daily Hr. 1 Pile Driver Foreman (outside) 4 Pile Drivers 2 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Crawler Crane, 75 Ton 1 Lead, 90’ High 1 Hammer, Diesel, 41k ft-lb 1 Barge, 400 Ton $62.50 60.50 66.30 56.40 $500.00 1936.00 1060.80 451.20 2189.46 409.90 640.74 957.33 $96.70 93.60 98.65 83.90 64 L.H., Daily Totals Crew B-20 1 Labor Foreman (outside) 1 Skilled Worker 1 Laborer $8145.43 Hr. Daily Hr. $49.25 61.25 47.25 $394.00 490.00 378.00 $73.30 92.00 70.35 24 L.H., Daily Totals Crew B-20A 1 Labor Foreman (outside) 1 Laborer 1 Plumber 1 Plumber Apprentice $1262.00 Hr. Daily Hr. $49.25 47.25 72.05 57.65 $394.00 378.00 576.40 461.20 $73.30 70.35 107.45 85.95 32 L.H., Daily Totals Crew B-21 1 Labor Foreman (outside) 1 Skilled Worker 1 Laborer .5 Equip. Oper. (crane) .5 S.P. Crane, 4x4, 5 Ton $1809.60 Hr. Daily Hr. $49.25 61.25 47.25 66.30 $394.00 490.00 378.00 265.20 192.94 $73.30 92.00 70.35 98.65 28 L.H., Daily Totals Crew B-21A 1 Labor Foreman (outside) 1 Laborer 1 Plumber 1 Plumber Apprentice 1 Equip. Oper. (crane) 1 S.P. Crane, 4x4, 12 Ton $1720.15 Hr. Daily Hr. $49.25 47.25 72.05 57.65 66.30 $394.00 378.00 576.40 461.20 530.40 637.99 $73.30 70.35 107.45 85.95 98.65 40 L.H., Daily Totals Crew B-21B 1 Labor Foreman (outside) 3 Laborers 1 Equip. Oper. (crane) 1 Hyd. Crane, 12 Ton $2977.99 Hr. Daily Hr. $49.25 47.25 66.30 $394.00 1134.00 530.40 2150.65 $73.30 70.35 98.65 40 L.H., Daily Totals Crew B-21C 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 2 Cutting Torches 2 Sets of Gases 1 Lattice Boom Crane, 90 Ton 56 L.H., Daily Totals $4209.05 Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 1512.00 530.40 451.20 28.48 377.34 2689.54 $73.30 70.35 98.65 83.90 $5982.96 Cost Per Labor-Hour Bare Costs Incl. O&P $773.60 2995.20 1578.40 671.20 2408.41 450.89 704.81 1053.06 $61.69 $94.04 65.58 72.14 $10635.57 $127.27 $166.18 Daily Bare Costs Incl. O&P $586.40 736.00 562.80 $52.58 $78.55 $1885.20 $52.58 $78.55 Daily Bare Costs Incl. O&P $586.40 562.80 859.60 687.60 $56.55 $84.26 $2696.40 $56.55 $84.26 Daily Bare Costs Incl. O&P $586.40 736.00 562.80 394.60 212.24 $54.54 $81.42 6.89 7.58 $2492.04 $61.43 $89.00 Daily Bare Costs Incl. O&P $586.40 562.80 859.60 687.60 789.20 701.79 $58.50 $87.14 15.95 17.54 $4187.39 $74.45 $104.68 Daily Bare Costs Incl. O&P $586.40 1688.40 789.20 2365.72 $51.46 $76.60 53.77 59.14 $5429.72 $105.23 $135.74 Daily Bare Costs Incl. O&P $586.40 2251.20 789.20 671.20 31.33 415.07 2958.49 $51.56 $76.75 55.27 60.80 $7702.90 $106.84 $137.55 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 759 Crews - Standard Crew No. Crew B-22 1 Labor Foreman (outside) 1 Skilled Worker 1 Laborer .75 Equip. Oper. (crane) .75 S.P. Crane, 4x4, 5 Ton Bare Costs Hr. Daily Hr. $49.25 61.25 47.25 66.30 $394.00 490.00 378.00 397.80 289.42 $73.30 92.00 70.35 98.65 30 L.H., Daily Totals Crew B-22A $1949.22 Hr. 1 Labor Foreman (outside) $49.25 1 Skilled Worker 61.25 2 Laborers 47.25 1 Equipment Operator, Crane 66.30 1 S.P. Crane, 4x4, 5 Ton 1 Butt Fusion Mach., 4⬙-12⬙ diam. 40 L.H., Daily Totals Crew B-22B Incl. Subs O&P Daily Hr. $394.00 490.00 756.00 530.40 385.89 332.25 $73.30 92.00 70.35 98.65 $2888.54 Hr. 1 Labor Foreman (outside) $49.25 1 Skilled Worker 61.25 2 Laborers 47.25 1 Equip. Oper. (crane) 66.30 1 S.P. Crane, 4x4, 5 Ton 1 Butt Fusion Mach., 8⬙-24⬙ diam. 40 L.H., Daily Totals Daily Hr. $394.00 490.00 756.00 530.40 385.89 787.50 $73.30 92.00 70.35 98.65 $3343.79 Crew B-22C Hr. Daily Hr. 1 Skilled Worker 1 Laborer 1 Butt Fusion Mach., 2⬙-8⬙ diam. $61.25 47.25 $490.00 378.00 280.48 $92.00 70.35 16 L.H., Daily Totals Crew B-23 1 Labor Foreman (outside) 4 Laborers 1 Drill Rig, Truck-Mounted 1 Flatbed Truck, Gas, 3 Ton $1148.48 Hr. Daily Hr. $49.25 47.25 $394.00 1512.00 856.23 391.02 $73.30 70.35 40 L.H., Daily Totals Crew B-23A 1 Labor Foreman (outside) 1 Laborer 1 Equip. Oper. (medium) 1 Drill Rig, Truck-Mounted 1 Pickup Truck, 3/4 Ton $3153.25 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 378.00 504.40 856.23 122.56 $73.30 70.35 93.80 24 L.H., Daily Totals Crew B-23B 1 Labor Foreman (outside) 1 Laborer 1 Equip. Oper. (medium) 1 Drill Rig, Truck-Mounted 1 Pickup Truck, 3/4 Ton 1 Centr. Water Pump, 6⬙ $2255.19 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 378.00 504.40 856.23 122.56 386.48 $73.30 70.35 93.80 24 L.H., Daily Totals Crew B-24 1 Cement Finisher 1 Laborer 1 Carpenter 24 L.H., Daily Totals 760 $2641.67 Hr. Daily Hr. $55.00 47.25 58.60 $440.00 378.00 468.80 $80.45 70.35 87.25 $1286.80 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 736.00 562.80 591.90 318.36 $55.33 $82.57 9.65 10.61 $2795.46 $64.97 $93.18 Daily Bare Costs Incl. O&P $586.40 736.00 1125.60 789.20 424.48 365.48 $54.26 $80.93 17.95 19.75 $4027.15 $72.21 $100.68 Daily Bare Costs Incl. O&P $586.40 736.00 1125.60 789.20 424.48 866.25 $54.26 $80.93 29.33 32.27 $4527.93 $83.59 $113.20 Daily Bare Costs Incl. O&P $736.00 562.80 308.53 $54.25 $81.17 17.53 19.28 $1607.33 $71.78 $100.46 Daily Bare Costs Incl. O&P $586.40 2251.20 941.85 430.12 $47.65 $70.94 31.18 34.30 $4209.57 $78.83 $105.24 Daily Bare Costs Incl. O&P $586.40 562.80 750.40 941.85 134.82 $53.18 $79.15 40.78 44.86 $2976.27 $93.97 $124.01 Daily Bare Costs Incl. O&P $586.40 562.80 750.40 941.85 134.82 425.13 $53.18 $79.15 56.89 62.57 $3401.40 $110.07 $141.72 Daily Bare Costs Incl. O&P $643.60 562.80 698.00 $53.62 $79.35 $1904.40 $53.62 $79.35 Daily Crew No. Crew B-25 1 Labor Foreman (outside) 7 Laborers 3 Equip. Oper. (medium) 1 Asphalt Paver, 130 H.P. 1 Tandem Roller, 10 Ton 1 Roller, Pneum. Whl., 12 Ton Bare Costs Hr. Daily Hr. $49.25 47.25 63.05 $394.00 2646.00 1513.20 2352.46 379.22 384.55 $73.30 70.35 93.80 88 L.H., Daily Totals Crew B-25B 1 Labor Foreman (outside) 7 Laborers 4 Equip. Oper. (medium) 1 Asphalt Paver, 130 H.P. 2 Tandem Rollers, 10 Ton 1 Roller, Pneum. Whl., 12 Ton $7669.43 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 2646.00 2017.60 2352.46 758.44 384.55 $73.30 70.35 93.80 96 L.H., Daily Totals Crew B-25C 1 Labor Foreman (outside) 3 Laborers 2 Equip. Oper. (medium) 1 Asphalt Paver, 130 H.P. 1 Tandem Roller, 10 Ton Incl. Subs O&P $8553.05 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 1134.00 1008.80 2352.46 379.22 $73.30 70.35 93.80 48 L.H., Daily Totals $5268.48 Crew B-25D Hr. Daily Hr. 1 Labor Foreman (outside) 3 Laborers 2.130 Equip. Oper. (medium) .13 Truck Driver (heavy) .13 Truck Tractor, 6x4, 380 H.P. .13 Dist. Tanker, 3000 Gallon 1 Asphalt Paver, 130 H.P. 1 Tandem Roller, 10 Ton $49.25 47.25 63.05 55.45 $394.00 1134.00 1074.37 57.67 70.98 47.72 2352.46 379.22 $73.30 70.35 93.80 82.85 50.08 L.H., Daily Totals $5510.42 Crew B-25E Hr. Daily Hr. 1 Labor Foreman (outside) 3 Laborers 2.250 Equip. Oper. (medium) .25 Truck Driver (heavy) .25 Truck Tractor, 6x4, 380 H.P. .25 Dist. Tanker, 3000 Gallon 1 Asphalt Paver, 130 H.P. 1 Tandem Roller, 10 Ton $49.25 47.25 63.05 55.45 $394.00 1134.00 1134.90 110.90 136.50 91.78 2352.46 379.22 $73.30 70.35 93.80 82.85 52 L.H., Daily Totals Crew B-26 1 Labor Foreman (outside) 6 Laborers 2 Equip. Oper. (medium) 1 Rodman (reinf.) 1 Cement Finisher 1 Grader, 30,000 Lbs. 1 Paving Mach. & Equip. 88 L.H., Daily Totals $5733.75 Hr. Daily Hr. $49.25 47.25 63.05 64.55 55.00 $394.00 2268.00 1008.80 516.40 440.00 1091.19 2747.64 $73.30 70.35 93.80 96.40 80.45 $8466.03 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 3939.60 2251.20 2587.71 417.14 423.01 $51.74 $77.01 35.41 38.95 $10205.05 $87.15 $115.97 Daily Bare Costs Incl. O&P $586.40 3939.60 3001.60 2587.71 834.28 423.01 $52.68 $78.41 36.41 40.05 $11372.59 $89.09 $118.46 Daily Bare Costs Incl. O&P $586.40 1688.40 1500.80 2587.71 417.14 $52.85 $78.66 56.91 62.60 $6780.45 $109.76 $141.26 Daily Bare Costs Incl. O&P $586.40 1688.40 1598.35 86.16 78.08 52.50 2587.71 417.14 $53.12 $79.06 56.92 62.61 $7094.73 $110.03 $141.67 Daily Bare Costs Incl. O&P $586.40 1688.40 1688.40 165.70 150.14 100.95 2587.71 417.14 $53.34 $79.40 56.92 62.61 $7384.85 $110.26 $142.02 Daily Bare Costs Incl. O&P $586.40 3376.80 1500.80 771.20 643.60 1200.31 3022.40 $52.58 $78.17 43.62 47.99 $11101.51 $96.20 $126.15 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew B-26A 1 Labor Foreman (outside) 6 Laborers 2 Equip. Oper. (medium) 1 Rodman (reinf.) 1 Cement Finisher 1 Grader, 30,000 Lbs. 1 Paving Mach. & Equip. 1 Concrete Saw Bare Costs Hr. Daily Hr. $49.25 47.25 63.05 64.55 55.00 $394.00 2268.00 1008.80 516.40 440.00 1091.19 2747.64 176.00 $73.30 70.35 93.80 96.40 80.45 88 L.H., Daily Totals Crew B-26B 1 Labor Foreman (outside) 6 Laborers 3 Equip. Oper. (medium) 1 Rodman (reinf.) 1 Cement Finisher 1 Grader, 30,000 Lbs. 1 Paving Mach. & Equip. 1 Concrete Pump, 110’ Boom $8642.03 Hr. Daily Hr. $49.25 47.25 63.05 64.55 55.00 $394.00 2268.00 1513.20 516.40 440.00 1091.19 2747.64 1069.53 $73.30 70.35 93.80 96.40 80.45 96 L.H., Daily Totals Crew B-26C 1 Labor Foreman (outside) 6 Laborers 1 Equip. Oper. (medium) 1 Rodman (reinf.) 1 Cement Finisher 1 Paving Mach. & Equip. 1 Concrete Saw $10039.96 Hr. Daily Hr. $49.25 47.25 63.05 64.55 55.00 $394.00 2268.00 504.40 516.40 440.00 2747.64 176.00 $73.30 70.35 93.80 96.40 80.45 80 L.H., Daily Totals Crew B-27 1 Labor Foreman (outside) 3 Laborers 1 Berm Machine $7046.44 Hr. Daily Hr. $49.25 47.25 $394.00 1134.00 897.16 $73.30 70.35 32 L.H., Daily Totals Crew B-28 2 Carpenters 1 Laborer $2425.16 Hr. Daily Hr. $58.60 47.25 $937.60 378.00 $87.25 70.35 24 L.H., Daily Totals Crew B-29 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Gradall, 5/8 C.Y. $1315.60 Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 1512.00 530.40 451.20 880.91 $73.30 70.35 98.65 83.90 56 L.H., Daily Totals Crew B-30 $3768.51 Hr. 1 Equip. Oper. (medium) $63.05 2 Truck Drivers (heavy) 55.45 1 Hyd. Excavator, 1.5 C.Y. 2 Dump Trucks, 12 C.Y., 400 H.P. 24 L.H., Daily Totals Incl. Subs O&P Daily Hr. $504.40 887.20 1185.24 1582.72 $93.80 82.85 $4159.56 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 3376.80 1500.80 771.20 643.60 1200.31 3022.40 193.60 $52.58 $78.17 45.62 50.19 $11295.11 $98.20 $128.35 Daily Bare Costs Incl. O&P $586.40 3376.80 2251.20 771.20 643.60 1200.31 3022.40 1176.48 $53.45 $79.47 51.13 56.24 $13028.40 $104.58 $135.71 Daily Bare Costs Incl. O&P $586.40 3376.80 750.40 771.20 643.60 3022.40 193.60 $51.53 $76.61 36.55 40.20 $9344.40 $88.08 $116.81 Daily Bare Costs Incl. O&P $586.40 1688.40 986.88 $47.75 $71.09 28.04 30.84 $3261.68 $75.79 $101.93 Daily Bare Costs Incl. O&P $1396.00 562.80 $54.82 $81.62 $1958.80 $54.82 $81.62 Daily Bare Costs Incl. O&P $586.40 2251.20 789.20 671.20 969.00 $51.56 $76.75 15.73 17.30 $5267.00 $67.29 $94.05 Daily Bare Costs Incl. O&P $750.40 1325.60 1303.76 1740.99 $57.98 $86.50 115.33 126.86 $5120.76 $173.32 $213.36 Daily Crew No. Crew B-31 1 Labor Foreman (outside) 3 Laborers 1 Carpenter 1 Air Compressor, 250 cfm 1 Sheeting Driver 2 -50’ Air Hoses, 1.5⬙ Bare Costs Hr. Daily Hr. $49.25 47.25 58.60 $394.00 1134.00 468.80 196.28 8.19 47.20 $73.30 70.35 87.25 40 L.H., Daily Totals Crew B-32 1 Laborer 3 Equip. Oper. (medium) 1 Grader, 30,000 Lbs. 1 Tandem Roller, 10 Ton 1 Dozer, 200 H.P. $2248.47 Hr. Daily Hr. $47.25 63.05 $378.00 1513.20 1091.19 379.22 1382.36 $70.35 93.80 32 L.H., Daily Totals Crew B-32A 1 Laborer 2 Equip. Oper. (medium) 1 Grader, 30,000 Lbs. 1 Roller, Vibratory, 25 Ton $4743.97 Hr. Daily Hr. $47.25 63.05 $378.00 1008.80 1091.19 529.68 $70.35 93.80 24 L.H., Daily Totals Crew B-32B 1 Laborer 2 Equip. Oper. (medium) 1 Dozer, 200 H.P. 1 Roller, Vibratory, 25 Ton $3007.67 Hr. Daily Hr. $47.25 63.05 $378.00 1008.80 1382.36 529.68 $70.35 93.80 24 L.H., Daily Totals Crew B-32C 1 Labor Foreman (outside) 2 Laborers 3 Equip. Oper. (medium) 1 Grader, 30,000 Lbs. 1 Tandem Roller, 10 Ton 1 Dozer, 200 H.P. $3298.84 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 756.00 1513.20 1091.19 379.22 1382.36 $73.30 70.35 93.80 48 L.H., Daily Totals Crew B-33A 1 Equip. Oper. (medium) .5 Laborer .25 Equip. Oper. (medium) 1 Scraper, Towed, 7 C.Y. 1.25 Dozers, 300 H.P. $5515.97 Hr. Daily Hr. $63.05 47.25 63.05 $504.40 189.00 126.10 141.88 2093.16 $93.80 70.35 93.80 14 L.H., Daily Totals Crew B-33B 1 Equip. Oper. (medium) .5 Laborer .25 Equip. Oper. (medium) 1 Scraper, Towed, 10 C.Y. 1.25 Dozers, 300 H.P. 14 L.H., Daily Totals Incl. Subs O&P $3054.54 Hr. Daily Hr. $63.05 47.25 63.05 $504.40 189.00 126.10 177.45 2093.16 $93.80 70.35 93.80 $3090.11 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 1688.40 698.00 215.91 9.01 51.92 $49.92 $74.32 6.29 6.92 $3249.64 $56.21 $81.24 Daily Bare Costs Incl. O&P $562.80 2251.20 1200.31 417.14 1520.60 $59.10 $87.94 89.15 98.06 $5952.05 $148.25 $186.00 Daily Bare Costs Incl. O&P $562.80 1500.80 1200.31 582.65 $57.78 $85.98 67.54 74.29 $3846.56 $125.32 $160.27 Daily Bare Costs Incl. O&P $562.80 1500.80 1520.60 582.65 $57.78 $85.98 79.67 87.64 $4166.84 $137.45 $173.62 Daily Bare Costs Incl. O&P $586.40 1125.60 2251.20 1200.31 417.14 1520.60 $55.48 $82.57 59.43 65.38 $7101.25 $114.92 $147.94 Daily Bare Costs Incl. O&P $750.40 281.40 187.60 156.07 2302.48 $58.54 $87.10 159.65 175.61 $3677.95 $218.18 $262.71 Daily Bare Costs Incl. O&P $750.40 281.40 187.60 195.19 2302.48 $58.54 $87.10 162.19 178.41 $3717.07 $220.72 $265.51 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 761 Crews - Standard Crew No. Crew B-33C 1 Equip. Oper. (medium) .5 Laborer .25 Equip. Oper. (medium) 1 Scraper, Towed, 15 C.Y. 1.25 Dozers, 300 H.P. Bare Costs Hr. Daily Hr. $63.05 47.25 63.05 $504.40 189.00 126.10 196.46 2093.16 $93.80 70.35 93.80 14 L.H., Daily Totals Crew B-33D 1 Equip. Oper. (medium) .5 Laborer .25 Equip. Oper. (medium) 1 S.P. Scraper, 14 C.Y. .25 Dozer, 300 H.P. $3109.12 Hr. Daily Hr. $63.05 47.25 63.05 $504.40 189.00 126.10 2168.71 418.63 $93.80 70.35 93.80 14 L.H., Daily Totals Crew B-33E 1 Equip. Oper. (medium) .5 Laborer .25 Equip. Oper. (medium) 1 S.P. Scraper, 21 C.Y. .25 Dozer, 300 H.P. $3406.84 Hr. Daily Hr. $63.05 47.25 63.05 $504.40 189.00 126.10 2239.60 418.63 $93.80 70.35 93.80 14 L.H., Daily Totals Crew B-33F 1 Equip. Oper. (medium) .5 Laborer .25 Equip. Oper. (medium) 1 Elev. Scraper, 11 C.Y. .25 Dozer, 300 H.P. $3477.73 Hr. Daily Hr. $63.05 47.25 63.05 $504.40 189.00 126.10 1022.46 418.63 $93.80 70.35 93.80 14 L.H., Daily Totals Crew B-33G 1 Equip. Oper. (medium) .5 Laborer .25 Equip. Oper. (medium) 1 Elev. Scraper, 22 C.Y. .25 Dozer, 300 H.P. Incl. Subs O&P $2260.59 Hr. Daily Hr. $63.05 47.25 63.05 $504.40 189.00 126.10 2005.03 418.63 $93.80 70.35 93.80 14 L.H., Daily Totals $3243.16 Crew B-33H Hr. Daily Hr. .5 Laborer 1 Equipment Operator (med.) .25 Equipment Operator (med.) 1 S.P. Scraper, 44 C.Y. .25 Dozer, 410 H.P. $47.25 63.05 63.05 $189.00 504.40 126.10 3440.19 633.99 $70.35 93.80 93.80 14 L.H., Daily Totals Crew B-33J 1 Equipment Operator (med.) 1 S.P. Scraper, 14 C.Y. $4893.68 Hr. Daily Hr. $63.05 $504.40 2168.71 $93.80 8 L.H., Daily Totals $2673.11 Crew B-33K Hr. Daily Hr. 1 Equipment Operator (med.) .25 Equipment Operator (med.) .5 Laborer 1 S.P. Scraper, 31 C.Y. .25 Dozer, 410 H.P. $63.05 63.05 47.25 $504.40 126.10 189.00 2972.09 633.99 $93.80 93.80 70.35 14 L.H., Daily Totals 762 $4425.58 Cost Per Labor-Hour Crew No. Bare Costs Incl. Subs O&P Bare Costs Incl. O&P $750.40 281.40 187.60 216.11 2302.48 $58.54 $87.10 163.54 179.90 $3737.98 $222.08 $267.00 Daily Bare Costs Incl. O&P $750.40 281.40 187.60 2385.58 460.50 $58.54 $87.10 184.81 203.29 $4065.48 $243.35 $290.39 Daily Bare Costs Incl. O&P $750.40 281.40 187.60 2463.56 460.50 $58.54 $87.10 189.87 208.86 $4143.46 $248.41 $295.96 Daily Bare Costs Incl. O&P $750.40 281.40 187.60 1124.71 460.50 $58.54 $87.10 102.94 113.23 $2804.60 $161.47 $200.33 Daily Bare Costs Incl. O&P $750.40 281.40 187.60 2205.53 460.50 $58.54 $87.10 173.12 190.43 $3885.43 $231.65 $277.53 Crew B-34H Hr. Daily Hr. Bare Costs Incl. O&P 1 Truck Driver (heavy) 1 Dump Truck, Off Hwy., 65 Ton $55.45 $443.60 2126.70 $82.85 Daily $281.40 750.40 187.60 3784.21 697.39 $58.54 $87.10 291.01 320.11 $5701.00 $349.55 $407.21 Daily Bare Costs Incl. O&P $750.40 2385.58 $63.05 271.09 $93.80 298.20 $3135.98 $334.14 $392.00 Daily Bare Costs Incl. O&P $750.40 187.60 281.40 3269.30 697.39 $58.54 $87.10 257.58 283.33 $5186.09 $316.11 $370.43 Daily Crew B-34A Hr. Daily Hr. 1 Truck Driver (heavy) 1 Dump Truck, 8 C.Y., 220 H.P. $55.45 $443.60 417.49 $82.85 8 L.H., Daily Totals $861.09 Crew B-34B Hr. Daily Hr. 1 Truck Driver (heavy) 1 Dump Truck, 12 C.Y., 400 H.P. $55.45 $443.60 791.36 $82.85 8 L.H., Daily Totals $1234.96 Crew B-34C Hr. Daily Hr. 1 Truck Driver (heavy) 1 Truck Tractor, 6x4, 380 H.P. 1 Dump Trailer, 16.5 C.Y. $55.45 $443.60 545.98 151.94 $82.85 8 L.H., Daily Totals $1141.52 Crew B-34D Hr. Daily Hr. 1 Truck Driver (heavy) 1 Truck Tractor, 6x4, 380 H.P. 1 Dump Trailer, 20 C.Y. $55.45 $443.60 545.98 168.66 $82.85 8 L.H., Daily Totals $1158.24 Crew B-34E Hr. Daily Hr. 1 Truck Driver (heavy) 1 Dump Truck, Off Hwy., 25 Ton $55.45 $443.60 1471.16 $82.85 8 L.H., Daily Totals $1914.76 Crew B-34F Hr. Daily Hr. 1 Truck Driver (heavy) 1 Dump Truck, Off Hwy., 35 Ton $55.45 $443.60 1508.36 $82.85 8 L.H., Daily Totals $1951.96 Crew B-34G Hr. Daily Hr. 1 Truck Driver (heavy) 1 Dump Truck, Off Hwy., 50 Ton $55.45 $443.60 2037.60 $82.85 8 L.H., Daily Totals $2481.20 8 L.H., Daily Totals $2570.30 Crew B-34I Hr. Daily Hr. 1 Truck Driver (heavy) 1 Dump Truck, 18 C.Y., 450 H.P. $55.45 $443.60 788.42 $82.85 8 L.H., Daily Totals Crew B-34J $1232.02 Hr. 1 Truck Driver (heavy) $55.45 1 Dump Truck, Off Hwy., 100 Ton 8 L.H., Daily Totals Daily Hr. $443.60 3040.18 $82.85 $3483.78 Crew B-34K Hr. Daily Hr. 1 Truck Driver (heavy) 1 Truck Tractor, 6x4, 450 H.P. 1 Lowbed Trailer, 75 Ton $55.45 $443.60 666.04 283.47 $82.85 8 L.H., Daily Totals $1393.11 Cost Per Labor-Hour Daily Bare Costs Incl. O&P $662.80 459.24 $55.45 52.19 $82.85 57.40 $1122.04 $107.64 $140.25 Daily Bare Costs Incl. O&P $662.80 870.50 $55.45 98.92 $82.85 108.81 $1533.30 $154.37 $191.66 Daily Bare Costs Incl. O&P $662.80 600.58 167.13 $55.45 $82.85 87.24 95.96 $1430.51 $142.69 $178.81 Daily Bare Costs Incl. O&P $662.80 600.58 185.53 $55.45 $82.85 89.33 98.26 $1448.90 $144.78 $181.11 Daily Bare Costs Incl. O&P $662.80 1618.28 $55.45 183.90 $82.85 202.28 $2281.08 $239.35 $285.13 Daily Bare Costs Incl. O&P $662.80 1659.20 $55.45 188.54 $82.85 207.40 $2322.00 $244.00 $290.25 Daily Bare Costs Incl. O&P $662.80 2241.36 $55.45 254.70 $82.85 280.17 $2904.16 $310.15 $363.02 Daily Bare Costs Incl. O&P $662.80 2339.37 $55.45 265.84 $82.85 292.42 $3002.17 $321.29 $375.27 Daily Bare Costs Incl. O&P $662.80 867.26 $55.45 98.55 $82.85 108.41 $1530.06 $154.00 $191.26 Daily Bare Costs Incl. O&P $662.80 3344.20 $55.45 380.02 $82.85 418.02 $4007.00 $435.47 $500.87 Daily Bare Costs Incl. O&P $662.80 732.64 311.82 $55.45 $82.85 118.69 130.56 $1707.26 $174.14 $213.41 Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew B-34L 1 Equip. Oper. (light) 1 Flatbed Truck, Gas, 1.5 Ton Bare Costs Hr. Daily Hr. $59.70 $477.60 361.95 $88.85 8 L.H., Daily Totals Crew B-34M 1 Equip. Oper. (light) 1 Flatbed Truck, Gas, 3 Ton Incl. Subs O&P $839.55 Hr. Daily Hr. $59.70 $477.60 391.02 $88.85 8 L.H., Daily Totals $868.62 Crew B-34N Hr. Daily Hr. 1 Truck Driver (heavy) 1 Equip. Oper. (medium) 1 Truck Tractor, 6x4, 380 H.P. 1 Flatbed Trailer, 40 Ton $55.45 63.05 $443.60 504.40 545.98 206.92 $82.85 93.80 16 L.H., Daily Totals Crew B-34P 1 Pipe Fitter 1 Truck Driver (light) 1 Equip. Oper. (medium) 1 Flatbed Truck, Gas, 3 Ton 1 Backhoe Loader, 48 H.P. $1700.90 Hr. Daily Hr. $72.55 52.90 63.05 $580.40 423.20 504.40 391.02 277.19 $108.20 79.00 93.80 24 L.H., Daily Totals $2176.21 Crew B-34Q Hr. Daily Hr. 1 Pipe Fitter 1 Truck Driver (light) 1 Equip. Oper. (crane) 1 Flatbed Trailer, 25 Ton 1 Dump Truck, 8 C.Y., 220 H.P. 1 Hyd. Crane, 25 Ton $72.55 52.90 66.30 $580.40 423.20 530.40 150.61 417.49 2273.31 $108.20 79.00 98.65 24 L.H., Daily Totals $4375.41 Crew B-34R Hr. Daily Hr. 1 Pipe Fitter 1 Truck Driver (light) 1 Equip. Oper. (crane) 1 Flatbed Trailer, 25 Ton 1 Dump Truck, 8 C.Y., 220 H.P. 1 Hyd. Crane, 25 Ton 1 Hyd. Excavator, 1 C.Y. $72.55 52.90 66.30 $580.40 423.20 530.40 150.61 417.49 2273.31 986.56 $108.20 79.00 98.65 24 L.H., Daily Totals $5361.97 Crew B-34S Hr. Daily Hr. 2 Pipe Fitters 1 Truck Driver (heavy) 1 Equip. Oper. (crane) 1 Flatbed Trailer, 40 Ton 1 Truck Tractor, 6x4, 380 H.P. 1 Hyd. Crane, 80 Ton 1 Hyd. Excavator, 2 C.Y. $72.55 55.45 66.30 $1160.80 443.60 530.40 206.92 545.98 2641.70 1096.14 $108.20 82.85 98.65 32 L.H., Daily Totals $6625.54 Crew B-34T Hr. Daily Hr. 2 Pipe Fitters 1 Truck Driver (heavy) 1 Equip. Oper. (crane) 1 Flatbed Trailer, 40 Ton 1 Truck Tractor, 6x4, 380 H.P. 1 Hyd. Crane, 80 Ton $72.55 55.45 66.30 $1160.80 443.60 530.40 206.92 545.98 2641.70 $108.20 82.85 98.65 32 L.H., Daily Totals $5529.40 Cost Per Labor-Hour Daily Bare Costs Incl. O&P $710.80 398.14 $59.70 45.24 $88.85 49.77 $1108.94 $104.94 $138.62 Daily Bare Costs Incl. O&P $710.80 430.12 $59.70 48.88 $88.85 53.77 $1140.92 $108.58 $142.62 Daily Bare Costs Incl. O&P $662.80 750.40 600.58 227.61 $59.25 $88.33 47.06 51.76 $2241.39 $106.31 $140.09 Bare Costs Incl. O&P $865.60 632.00 750.40 430.12 304.91 $62.83 $93.67 27.84 30.63 $2983.03 $90.68 $124.29 Daily Bare Costs Incl. O&P $865.60 632.00 789.20 165.67 459.24 2500.64 $63.92 $95.28 118.39 130.23 $5412.35 $182.31 $225.51 Daily Bare Costs Incl. O&P $865.60 632.00 789.20 165.67 459.24 2500.64 1085.22 $63.92 $95.28 159.50 175.45 $6497.57 $223.42 $270.73 Daily Bare Costs Incl. O&P $1731.20 662.80 789.20 227.61 600.58 2905.87 1205.75 $66.71 $99.47 140.34 154.37 $8123.01 $207.05 $253.84 Daily Bare Costs Incl. O&P $1731.20 662.80 789.20 227.61 600.58 2905.87 $66.71 $99.47 106.08 116.69 $6917.26 $172.79 $216.16 Daily Crew No. Crew B-34U 1 Truck Driver (heavy) 1 Equip. Oper. (light) 1 Truck Tractor, 220 H.P. 1 Flatbed Trailer, 25 Ton Bare Costs Incl. Subs O&P Hr. Daily Hr. $55.45 59.70 $443.60 477.60 339.98 150.61 $82.85 88.85 16 L.H., Daily Totals $1411.79 Crew B-34V Hr. Daily Hr. 1 Truck Driver (heavy) 1 Equip. Oper. (crane) 1 Equip. Oper. (light) 1 Truck Tractor, 6x4, 450 H.P. 1 Equipment Trailer, 50 Ton 1 Pickup Truck, 4x4, 3/4 Ton $55.45 66.30 59.70 $443.60 530.40 477.60 666.04 336.69 191.73 $82.85 98.65 88.85 24 L.H., Daily Totals $2646.06 Crew B-34W Hr. Daily Hr. 5 Truck Drivers (heavy) 2 Equip. Opers. (crane) 1 Equip. Oper. (mechanic) 1 Laborer 4 Truck Tractors, 6x4, 380 H.P. 2 Equipment Trailers, 50 Ton 2 Flatbed Trailers, 40 Ton 1 Pickup Truck, 4x4, 3/4 Ton 1 S.P. Crane, 4x4, 20 Ton $55.45 66.30 66.40 47.25 $2218.00 1060.80 531.20 378.00 2183.92 673.38 413.84 191.73 760.97 $82.85 98.65 98.80 70.35 72 L.H., Daily Totals Crew B-35 1 Labor Foreman (outside) 1 Skilled Worker 2 Welders 1 Laborer 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 2 Welder, Electric, 300 amp 1 Hyd. Excavator, .75 C.Y. $8411.84 Hr. Daily Hr. $49.25 61.25 72.05 47.25 66.30 56.40 $394.00 490.00 1152.80 378.00 530.40 451.20 128.34 915.34 $73.30 92.00 107.45 70.35 98.65 83.90 56 L.H., Daily Totals $4440.08 Crew B-35A Hr. Daily Hr. 1 Labor Foreman (outside) 2 Laborers 1 Skilled Worker 1 Welder (plumber) 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Welder, Gas Engine, 300 amp 1 Crawler Crane, 75 Ton $49.25 47.25 61.25 72.05 66.30 56.40 $394.00 756.00 490.00 576.40 530.40 451.20 147.09 2189.46 $73.30 70.35 92.00 107.45 98.65 83.90 56 L.H., Daily Totals Crew B-36 1 Labor Foreman (outside) 2 Laborers 2 Equip. Oper. (medium) 1 Dozer, 200 H.P. 1 Aggregate Spreader 1 Tandem Roller, 10 Ton 40 L.H., Daily Totals $5534.55 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 756.00 1008.80 1382.36 67.49 379.22 $73.30 70.35 93.80 $3987.87 Cost Per Labor-Hour Bare Costs Incl. O&P $662.80 710.80 373.98 165.67 $57.58 $85.85 30.66 33.73 $1913.25 $88.24 $119.58 Daily Bare Costs Incl. O&P $662.80 789.20 710.80 732.64 370.36 210.90 $60.48 $90.12 49.77 54.75 $3476.71 $110.25 $144.86 Daily Bare Costs Incl. O&P $3314.00 1578.40 790.40 562.80 2402.31 740.72 455.22 210.90 837.07 $58.17 $86.74 58.66 64.53 $10891.82 $116.83 $151.28 Daily Bare Costs Incl. O&P $586.40 736.00 1719.20 562.80 789.20 671.20 141.17 1006.87 $60.65 $90.44 18.64 20.50 $6212.85 $79.29 $110.94 Daily Bare Costs Incl. O&P $586.40 1125.60 736.00 859.60 789.20 671.20 161.80 2408.41 $57.11 $85.14 41.72 45.90 $7338.20 $98.83 $131.04 Daily Bare Costs Incl. O&P $586.40 1125.60 1500.80 1520.60 74.24 417.14 $53.97 $80.32 45.73 50.30 $5224.78 $99.70 $130.62 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 763 Crews - Standard Crew No. Crew B-36A 1 Labor Foreman (outside) 2 Laborers 4 Equip. Oper. (medium) 1 Dozer, 200 H.P. 1 Aggregate Spreader 1 Tandem Roller, 10 Ton 1 Roller, Pneum. Whl., 12 Ton Bare Costs Incl. Subs O&P Hr. Daily Hr. $49.25 47.25 63.05 $394.00 756.00 2017.60 1382.36 67.49 379.22 384.55 $73.30 70.35 93.80 56 L.H., Daily Totals $5381.22 Crew B-36B Hr. Daily Hr. 1 Labor Foreman (outside) 2 Laborers 4 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Grader, 30,000 Lbs. 1 F.E. Loader, Crl, 1.5 C.Y. 1 Dozer, 300 H.P. 1 Roller, Vibratory, 25 Ton 1 Truck Tractor, 6x4, 450 H.P. 1 Water Tank Trailer, 5000 Gal. $49.25 47.25 63.05 55.45 $394.00 756.00 2017.60 443.60 1091.19 733.70 1674.53 529.68 666.04 169.14 $73.30 70.35 93.80 82.85 64 L.H., Daily Totals $8475.48 Crew B-36C Hr. Daily Hr. 1 Labor Foreman (outside) 3 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Grader, 30,000 Lbs. 1 Dozer, 300 H.P. 1 Roller, Vibratory, 25 Ton 1 Truck Tractor, 6x4, 450 H.P. 1 Water Tank Trailer, 5000 Gal. $49.25 63.05 55.45 $394.00 1513.20 443.60 1091.19 1674.53 529.68 666.04 169.14 $73.30 93.80 82.85 40 L.H., Daily Totals Crew B-36D 1 Labor Foreman (outside) 3 Equip. Oper. (medium) 1 Grader, 30,000 Lbs. 1 Dozer, 300 H.P. 1 Roller, Vibratory, 25 Ton $6481.38 Hr. Daily Hr. $49.25 63.05 $394.00 1513.20 1091.19 1674.53 529.68 $73.30 93.80 32 L.H., Daily Totals Crew B-37 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (light) 1 Tandem Roller, 5 Ton $5202.60 Hr. Daily Hr. $49.25 47.25 59.70 $394.00 1512.00 477.60 287.45 $73.30 70.35 88.85 48 L.H., Daily Totals Crew B-37A 2 Laborers 1 Truck Driver (light) 1 Flatbed Truck, Gas, 1.5 Ton 1 Tar Kettle, T.M. $2671.05 Hr. Daily Hr. $47.25 52.90 $756.00 423.20 361.95 199.54 $70.35 79.00 24 L.H., Daily Totals Crew B-37B 3 Laborers 1 Truck Driver (light) 1 Flatbed Truck, Gas, 1.5 Ton 1 Tar Kettle, T.M. 32 L.H., Daily Totals 764 $1740.69 Hr. Daily Hr. $47.25 52.90 $1134.00 423.20 361.95 199.54 $70.35 79.00 $2118.69 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 1125.60 3001.60 1520.60 74.24 417.14 423.01 $56.56 $84.17 39.53 43.48 $7148.58 $96.09 $127.65 Daily Bare Costs Incl. O&P $586.40 1125.60 3001.60 662.80 1200.31 807.07 1841.98 582.65 732.64 186.05 $56.42 $84.01 76.00 83.60 $10727.11 $132.43 $167.61 Daily Bare Costs Incl. O&P $586.40 2251.20 662.80 1200.31 1841.98 582.65 732.64 186.05 $58.77 $87.51 103.26 113.59 $8044.04 $162.03 $201.10 Daily Bare Costs Incl. O&P $586.40 2251.20 1200.31 1841.98 582.65 $59.60 $88.67 102.98 113.28 $6462.54 $162.58 $201.95 Daily Bare Costs Incl. O&P $586.40 2251.20 710.80 316.19 $49.66 $73.92 5.99 6.59 $3864.59 $55.65 $80.51 Daily Bare Costs Incl. O&P $1125.60 632.00 398.14 219.49 $49.13 $73.23 23.40 25.73 $2375.24 $72.53 $98.97 Daily Bare Costs Incl. O&P $1688.40 632.00 398.14 219.49 $48.66 $72.51 17.55 19.30 $2938.04 $66.21 $91.81 Daily Crew No. Bare Costs Incl. Subs O&P Crew B-37C Hr. Daily Hr. 2 Laborers 2 Truck Drivers (light) 2 Flatbed Trucks, Gas, 1.5 Ton 1 Tar Kettle, T.M. $47.25 52.90 $756.00 846.40 723.90 199.54 $70.35 79.00 32 L.H., Daily Totals Crew B-37D 1 Laborer 1 Truck Driver (light) 1 Pickup Truck, 3/4 Ton $2525.84 Hr. Daily Hr. $47.25 52.90 $378.00 423.20 122.56 $70.35 79.00 16 L.H., Daily Totals $923.76 Crew B-37E Hr. Daily Hr. 3 Laborers 1 Equip. Oper. (light) 1 Equip. Oper. (medium) 2 Truck Drivers (light) 4 Barrels w/ Flasher 1 Concrete Saw 1 Rotary Hammer Drill 1 Hammer Drill Bit 1 Loader, Skid Steer, 30 H.P. 1 Conc. Hammer Attach. 1 Vibrating Plate, Gas, 18⬙ 2 Flatbed Trucks, Gas, 1.5 Ton $47.25 59.70 63.05 52.90 $1134.00 477.60 504.40 846.40 11.36 176.00 34.98 26.61 260.99 126.94 143.82 723.90 $70.35 88.85 93.80 79.00 56 L.H., Daily Totals Crew B-37F 3 Laborers 1 Truck Driver (light) 4 Barrels w/ Flasher 1 Concrete Mixer, 10 C.F. 1 Air Compressor, 60 cfm 1 -50’ Air Hose, 3/4⬙ 1 Spade (Chipper) 1 Flatbed Truck, Gas, 1.5 Ton $4467.00 Hr. Daily Hr. $47.25 52.90 $1134.00 423.20 11.36 149.77 173.21 8.16 9.37 361.95 $70.35 79.00 32 L.H., Daily Totals Crew B-37G 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (light) 1 Berm Machine 1 Tandem Roller, 5 Ton $2271.02 Hr. Daily Hr. $49.25 47.25 59.70 $394.00 1512.00 477.60 897.16 287.45 $73.30 70.35 88.85 48 L.H., Daily Totals Crew B-37H 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (light) 1 Tandem Roller, 5 Ton 1 Flatbed Truck, Gas, 1.5 Ton 1 Tar Kettle, T.M. 48 L.H., Daily Totals $3568.21 Hr. Daily Hr. $49.25 47.25 59.70 $394.00 1512.00 477.60 287.45 361.95 199.54 $73.30 70.35 88.85 $3232.54 Cost Per Labor-Hour Bare Costs Incl. O&P $1125.60 1264.00 796.29 219.49 $50.08 $74.67 28.86 31.74 $3405.38 $78.93 $106.42 Daily Bare Costs Incl. O&P $562.80 632.00 134.82 $50.08 $74.67 7.66 8.43 $1329.62 $57.73 $83.10 Daily Bare Costs Incl. O&P $1688.40 710.80 750.40 1264.00 12.50 193.60 38.48 29.27 287.09 139.63 158.20 796.29 $52.90 $78.81 26.87 29.55 $6068.66 $79.77 $108.37 Daily Bare Costs Incl. O&P $1688.40 632.00 12.50 164.75 190.53 8.98 10.31 398.14 $48.66 $72.51 22.31 24.54 $3105.60 $70.97 $97.05 Daily Bare Costs Incl. O&P $586.40 2251.20 710.80 986.88 316.19 $49.66 $73.92 24.68 27.15 $4851.47 $74.34 $101.07 Daily Bare Costs Incl. O&P $586.40 2251.20 710.80 316.19 398.14 219.49 $49.66 $73.92 17.69 19.45 $4482.23 $67.34 $93.38 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Bare Costs Incl. Subs O&P Crew B-37I Hr. Daily Hr. 3 Laborers 1 Equip. Oper. (light) 1 Equip. Oper. (medium) 2 Truck Drivers (light) 4 Barrels w/ Flasher 1 Concrete Saw 1 Rotary Hammer Drill 1 Hammer Drill Bit 1 Air Compressor, 60 cfm 1 -50’ Air Hose, 3/4⬙ 1 Spade (Chipper) 1 Loader, Skid Steer, 30 H.P. 1 Conc. Hammer Attach. 1 Concrete Mixer, 10 C.F. 1 Vibrating Plate, Gas, 18⬙ 2 Flatbed Trucks, Gas, 1.5 Ton $47.25 59.70 63.05 52.90 $1134.00 477.60 504.40 846.40 11.36 176.00 34.98 26.61 173.21 8.16 9.37 260.99 126.94 149.77 143.82 723.90 $70.35 88.85 93.80 79.00 56 L.H., Daily Totals $4807.51 Crew B-37J Hr. Daily Hr. 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (light) 1 Air Compressor, 60 cfm 1 -50’ Air Hose, 3/4⬙ 2 Concrete Mixers, 10 C.F. 2 Flatbed Trucks, Gas, 1.5 Ton 1 Shot Blaster, 20⬙ $49.25 47.25 59.70 $394.00 1512.00 477.60 173.21 8.16 299.54 723.90 229.79 $73.30 70.35 88.85 48 L.H., Daily Totals $3818.20 Crew B-37K Hr. Daily Hr. 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (light) 1 Air Compressor, 60 cfm 1 -50’ Air Hose, 3/4⬙ 2 Flatbed Trucks, Gas, 1.5 Ton 1 Shot Blaster, 20⬙ $49.25 47.25 59.70 $394.00 1512.00 477.60 173.21 8.16 723.90 229.79 $73.30 70.35 88.85 48 L.H., Daily Totals Crew B-38 1 Labor Foreman (outside) 2 Laborers 1 Equip. Oper. (light) 1 Equip. Oper. (medium) 1 Backhoe Loader, 48 H.P. 1 Hyd. Hammer (1200 lb.) 1 F.E. Loader, W.M., 4 C.Y. 1 Pvmt. Rem. Bucket $3518.66 Hr. Daily Hr. $49.25 47.25 59.70 63.05 $394.00 756.00 477.60 504.40 277.19 194.78 789.98 70.14 $73.30 70.35 88.85 93.80 40 L.H., Daily Totals Crew B-39 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (light) 1 Air Compressor, 250 cfm 2 Breakers, Pavement, 60 lb. 2 -50’ Air Hoses, 1.5⬙ 48 L.H., Daily Totals $3464.09 Hr. Daily Hr. $49.25 47.25 59.70 $394.00 1512.00 477.60 196.28 68.94 47.20 $73.30 70.35 88.85 $2696.02 Cost Per Labor-Hour Bare Costs Incl. O&P $1688.40 710.80 750.40 1264.00 12.50 193.60 38.48 29.27 190.53 8.98 10.31 287.09 139.63 164.75 158.20 796.29 $52.90 $78.81 32.95 36.24 $6443.22 $85.85 $115.06 Daily Bare Costs Incl. O&P $586.40 2251.20 710.80 190.53 8.98 329.49 796.29 252.77 $49.66 $73.92 29.89 32.88 $5126.46 $79.55 $106.80 Daily Bare Costs Incl. O&P $586.40 2251.20 710.80 190.53 8.98 796.29 252.77 $49.66 $73.92 23.65 26.01 $4796.97 $73.31 $99.94 Daily Bare Costs Incl. O&P $586.40 1125.60 710.80 750.40 304.91 214.26 868.98 77.15 $53.30 $79.33 33.30 36.63 $4638.50 $86.60 $115.96 Daily Bare Costs Incl. O&P $586.40 2251.20 710.80 215.91 75.83 51.92 $49.66 $73.92 6.51 7.16 $3892.06 $56.17 $81.08 Daily Crew No. Bare Costs Incl. Subs O&P Crew B-40 Hr. Daily Hr. 1 Pile Driver Foreman (outside) 4 Pile Drivers 2 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Crawler Crane, 40 Ton 1 Vibratory Hammer & Gen. $62.50 60.50 66.30 56.40 $500.00 1936.00 1060.80 451.20 1362.63 2518.21 $96.70 93.60 98.65 83.90 64 L.H., Daily Totals Crew B-40B 1 Labor Foreman (outside) 3 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Lattice Boom Crane, 40 Ton $7828.84 Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 1134.00 530.40 451.20 2371.83 $73.30 70.35 98.65 83.90 48 L.H., Daily Totals Crew B-41 1 Labor Foreman (outside) 4 Laborers .25 Equip. Oper. (crane) .25 Equip. Oper. (oiler) .25 Crawler Crane, 40 Ton $4881.43 Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 1512.00 132.60 112.80 340.66 $73.30 70.35 98.65 83.90 44 L.H., Daily Totals $2492.06 Crew B-42 Hr. Daily Hr. 1 Labor Foreman (outside) 4 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Welder 1 Hyd. Crane, 25 Ton 1 Welder, Gas Engine, 300 amp 1 Horz. Boring Csg. Mch. $49.25 47.25 66.30 56.40 64.55 $394.00 1512.00 530.40 451.20 516.40 2273.31 147.09 437.50 $73.30 70.35 98.65 83.90 99.40 64 L.H., Daily Totals Crew B-43 1 Labor Foreman (outside) 3 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Drill Rig, Truck-Mounted $6261.90 Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 1134.00 530.40 451.20 856.23 $73.30 70.35 98.65 83.90 48 L.H., Daily Totals $3365.83 Crew B-44 Hr. Daily Hr. 1 Pile Driver Foreman (outside) 4 Pile Drivers 2 Equip. Oper. (crane) 1 Laborer 1 Crawler Crane, 40 Ton 1 Lead, 60’ High 1 Hammer, Diesel, 15K ft.-lbs. $62.50 60.50 66.30 47.25 $500.00 1936.00 1060.80 378.00 1362.63 233.36 687.50 $96.70 93.60 98.65 70.35 64 L.H., Daily Totals $6158.29 Crew B-45 Hr. Daily Hr. 1 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Dist. Tanker, 3000 Gallon 1 Truck Tractor, 6x4, 380 H.P. $63.05 55.45 $504.40 443.60 367.10 545.98 $93.80 82.85 16 L.H., Daily Totals $1861.08 Cost Per Labor-Hour Bare Costs Incl. O&P $773.60 2995.20 1578.40 671.20 1498.89 2770.03 $61.69 $94.04 60.64 66.70 $10287.32 $122.33 $160.74 Daily Bare Costs Incl. O&P $586.40 1688.40 789.20 671.20 2609.01 $52.28 $77.82 49.41 54.35 $6344.21 $101.70 $132.17 Daily Bare Costs Incl. O&P $586.40 2251.20 197.30 167.80 374.72 $48.90 $72.79 7.74 8.52 $3577.42 $56.64 $81.31 Daily Bare Costs Incl. O&P $586.40 2251.20 789.20 671.20 795.20 2500.64 161.80 481.25 $53.19 $79.58 44.65 49.12 $8236.89 $97.84 $128.70 Daily Bare Costs Incl. O&P $586.40 1688.40 789.20 671.20 941.85 $52.28 $77.82 17.84 19.62 $4677.05 $70.12 $97.44 Daily Bare Costs Incl. O&P $773.60 2995.20 1578.40 562.80 1498.89 256.70 756.25 $60.54 $92.34 35.68 39.25 $8421.84 $96.22 $131.59 Daily Bare Costs Incl. O&P $750.40 662.80 403.81 600.58 $59.25 $88.33 57.07 62.77 $2417.59 $116.32 $151.10 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 765 Crews - Standard Crew No. Bare Costs Incl. Subs O&P Crew B-46 Hr. Daily Hr. 1 Pile Driver Foreman (outside) 2 Pile Drivers 3 Laborers 1 Chain Saw, Gas, 36⬙ Long $62.50 60.50 47.25 $500.00 968.00 1134.00 53.61 $96.70 93.60 70.35 48 L.H., Daily Totals Crew B-47 1 Blast Foreman (outside) 1 Driller 1 Equip. Oper. (light) 1 Air Track Drill, 4⬙ 1 Air Compressor, 600 cfm 2 -50’ Air Hoses, 3⬙ $2655.61 Hr. Daily Hr. $49.25 47.25 59.70 $394.00 378.00 477.60 1191.15 466.11 93.52 $73.30 70.35 88.85 24 L.H., Daily Totals Crew B-47A 1 Drilling Foreman (outside) 1 Equip. Oper. (heavy) 1 Equip. Oper. (oiler) 1 Air Track Drill, 5⬙ $3000.38 Hr. Daily Hr. $49.25 66.30 56.40 $394.00 530.40 451.20 1191.15 $73.30 98.65 83.90 24 L.H., Daily Totals Crew B-47C 1 Laborer 1 Equip. Oper. (light) 1 Air Compressor, 750 C.F.M. 2 -50’ Air Hoses, 3⬙ 1 Air Track Drill, 4⬙ $2566.75 Hr. Daily Hr. $47.25 59.70 $378.00 477.60 655.87 93.52 1191.15 $70.35 88.85 16 L.H., Daily Totals Crew B-47E 1 Labor Foreman (outside) 3 Laborers 1 Flatbed Truck, Gas, 3 Ton $2796.14 Hr. Daily Hr. $49.25 47.25 $394.00 1134.00 391.02 $73.30 70.35 32 L.H., Daily Totals Crew B-47G 1 Labor Foreman (outside) 2 Laborers 1 Equip. Oper. (light) 1 Air Track Drill, 4⬙ 1 Air Compressor, 600 cfm 2 -50’ Air Hoses, 3⬙ 1 Gunite Pump Rig $1919.02 Hr. Daily Hr. $49.25 47.25 59.70 $394.00 756.00 477.60 1191.15 466.11 93.52 352.58 $73.30 70.35 88.85 32 L.H., Daily Totals $3730.96 Crew B-47H Hr. Daily Hr. 1 Skilled Worker Foreman (out) 3 Skilled Workers 1 Flatbed Truck, Gas, 3 Ton $63.25 61.25 $506.00 1470.00 391.02 $95.00 92.00 32 L.H., Daily Totals $2367.02 Cost Per Labor-Hour Bare Costs Incl. O&P $773.60 1497.60 1688.40 58.97 $54.21 $82.49 1.12 1.23 $4018.57 $55.33 $83.72 Daily Bare Costs Incl. O&P $586.40 562.80 710.80 1310.27 512.72 102.87 $52.07 $77.50 72.95 80.24 $3785.86 $125.02 $157.74 Daily Bare Costs Incl. O&P $586.40 789.20 671.20 1310.27 $57.32 $85.28 49.63 54.59 $3357.07 $106.95 $139.88 Daily Bare Costs Incl. O&P $562.80 710.80 721.46 102.87 1310.27 $53.48 $79.60 121.28 133.41 $3408.19 $174.76 $213.01 Daily Bare Costs Incl. O&P $586.40 1688.40 430.12 $47.75 $71.09 12.22 13.44 $2704.92 $59.97 $84.53 Daily Bare Costs Incl. O&P $586.40 1125.60 710.80 1310.27 512.72 102.87 387.84 $50.86 $75.71 65.73 72.30 $4736.50 $116.59 $148.02 Daily Bare Costs Incl. O&P $760.00 2208.00 430.12 $61.75 $92.75 12.22 13.44 $3398.12 $73.97 $106.19 Daily Crew No. Crew B-48 1 Labor Foreman (outside) 3 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Equip. Oper. (light) 1 Centr. Water Pump, 6⬙ 1 -20’ Suction Hose, 6⬙ 1 -50’ Discharge Hose, 6⬙ 1 Drill Rig, Truck-Mounted Bare Costs Hr. Daily Hr. $49.25 47.25 66.30 56.40 59.70 $394.00 1134.00 530.40 451.20 477.60 386.48 28.12 19.99 856.23 $73.30 70.35 98.65 83.90 88.85 56 L.H., Daily Totals Crew B-49 1 Labor Foreman (outside) 3 Laborers 2 Equip. Oper. (crane) 2 Equip. Oper. (oilers) 1 Equip. Oper. (light) 2 Pile Drivers 1 Hyd. Crane, 25 Ton 1 Centr. Water Pump, 6⬙ 1 -20’ Suction Hose, 6⬙ 1 -50’ Discharge Hose, 6⬙ 1 Drill Rig, Truck-Mounted $4278.02 Hr. Daily Hr. $49.25 47.25 66.30 56.40 59.70 60.50 $394.00 1134.00 1060.80 902.40 477.60 968.00 2273.31 386.48 28.12 19.99 856.23 $73.30 70.35 98.65 83.90 88.85 93.60 88 L.H., Daily Totals $8500.93 Crew B-50 Hr. Daily Hr. 2 Pile Driver Foremen (outside) 6 Pile Drivers 2 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 3 Laborers 1 Crawler Crane, 40 Ton 1 Lead, 60’ High 1 Hammer, Diesel, 15K ft.-lbs. 1 Air Compressor, 600 cfm 2 -50’ Air Hoses, 3⬙ 1 Chain Saw, Gas, 36⬙ Long $62.50 60.50 66.30 56.40 47.25 $1000.00 2904.00 1060.80 451.20 1134.00 1362.63 233.36 687.50 466.11 93.52 53.61 $96.70 93.60 98.65 83.90 70.35 112 L.H., Daily Totals Crew B-51 1 Labor Foreman (outside) 4 Laborers 1 Truck Driver (light) 1 Flatbed Truck, Gas, 1.5 Ton $9446.73 Hr. Daily Hr. $49.25 47.25 52.90 $394.00 1512.00 423.20 361.95 $73.30 70.35 79.00 48 L.H., Daily Totals Crew B-52 1 Carpenter Foreman (outside) 1 Carpenter 3 Laborers 1 Cement Finisher .5 Rodman (reinf.) .5 Equip. Oper. (medium) .5 Crawler Loader, 3 C.Y. $2691.15 Hr. Daily Hr. $60.60 58.60 47.25 55.00 64.55 63.05 $484.80 468.80 1134.00 440.00 258.20 252.20 628.84 $90.20 87.25 70.35 80.45 96.40 93.80 56 L.H., Daily Totals Crew B-53 1 Equip. Oper. (light) 1 Trencher, Chain, 12 H.P. 8 L.H., Daily Totals 766 Incl. Subs O&P $3666.84 Hr. Daily Hr. $59.70 $477.60 202.47 $88.85 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 1688.40 789.20 671.20 710.80 425.13 30.93 21.99 941.85 $53.34 $79.39 23.05 25.36 $5865.90 $76.39 $104.75 Daily Bare Costs Incl. O&P $586.40 1688.40 1578.40 1342.40 710.80 1497.60 2500.64 425.13 30.93 21.99 941.85 $56.10 $84.14 40.50 44.55 $11324.54 $96.60 $128.69 Daily Bare Costs Incl. O&P $1547.20 4492.80 1578.40 671.20 1688.40 1498.89 256.70 756.25 512.72 102.87 58.97 $58.48 $89.09 25.86 28.45 $13164.40 $84.35 $117.54 Daily Bare Costs Incl. O&P $586.40 2251.20 632.00 398.14 $48.52 $72.28 7.54 8.29 $3867.74 $56.07 $80.58 Daily Bare Costs Incl. O&P $721.60 698.00 1688.40 643.60 385.60 375.20 691.72 $54.25 $80.58 11.23 12.35 $5204.12 $65.48 $92.93 Daily Bare Costs Incl. O&P $710.80 222.72 $59.70 25.31 $88.85 27.84 $933.52 $85.01 $116.69 Daily $680.07 Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew B-54 1 Equip. Oper. (light) 1 Trencher, Chain, 40 H.P. Bare Costs Hr. Daily Hr. $59.70 $477.60 386.50 $88.85 8 L.H., Daily Totals Crew B-54A .17 Labor Foreman (outside) 1 Equipment Operator (med.) 1 Wheel Trencher, 67 H.P. $864.10 Hr. Daily Hr. $49.25 63.05 $66.98 504.40 1248.89 $73.30 93.80 9.36 L.H., Daily Totals Crew B-54B .25 Labor Foreman (outside) 1 Equipment Operator (med.) 1 Wheel Trencher, 150 H.P. $1820.27 Hr. Daily Hr. $49.25 63.05 $98.50 504.40 1338.44 $73.30 93.80 10 L.H., Daily Totals Crew B-54C 1 Laborer 1 Equipment Operator (med.) 1 Wheel Trencher, 67 H.P. $1941.34 Hr. Daily Hr. $47.25 63.05 $378.00 504.40 1248.89 $70.35 93.80 16 L.H., Daily Totals Crew B-54D 1 Laborer 1 Equipment Operator (med.) 1 Rock Trencher, 6⬙ Width $2131.29 Hr. Daily Hr. $47.25 63.05 $378.00 504.40 992.44 $70.35 93.80 16 L.H., Daily Totals Crew B-54E 1 Laborer 1 Equipment Operator (med.) 1 Rock Trencher, 18⬙ Width $1874.84 Hr. Daily Hr. $47.25 63.05 $378.00 504.40 1079.31 $70.35 93.80 16 L.H., Daily Totals Crew B-55 2 Laborers 1 Truck Driver (light) 1 Truck-Mounted Earth Auger 1 Flatbed Truck, Gas, 3 Ton $1961.71 Hr. Daily Hr. $47.25 52.90 $756.00 423.20 446.91 391.02 $70.35 79.00 24 L.H., Daily Totals Crew B-56 1 Laborer 1 Equip. Oper. (light) 1 Air Track Drill, 4⬙ 1 Air Compressor, 600 cfm 1 -50’ Air Hose, 3⬙ 16 L.H., Daily Totals Incl. Subs O&P $2017.13 Hr. Daily Hr. $47.25 59.70 $378.00 477.60 1191.15 466.11 46.76 $70.35 88.85 $2559.62 Cost Per Labor-Hour Daily Bare Costs Incl. O&P $710.80 425.15 $59.70 48.31 $88.85 53.14 $1135.95 $108.01 $141.99 Daily Bare Costs Incl. O&P $99.69 750.40 1373.78 $61.04 $90.82 133.43 146.77 $2223.87 $194.47 $237.59 Daily Bare Costs Incl. O&P $146.60 750.40 1472.28 $60.29 $89.70 133.84 147.23 $2369.28 $194.13 $236.93 Daily Bare Costs Incl. O&P $562.80 750.40 1373.78 $55.15 $82.08 78.06 85.86 $2686.98 $133.21 $167.94 Daily Bare Costs Incl. O&P $562.80 750.40 1091.68 $55.15 $82.08 62.03 68.23 $2404.88 $117.18 $150.31 Daily Bare Costs Incl. O&P $562.80 750.40 1187.24 $55.15 $82.08 67.46 74.20 $2500.44 $122.61 $156.28 Daily Bare Costs Incl. O&P $1125.60 632.00 491.60 430.12 $49.13 $73.23 34.91 38.41 $2679.32 $84.05 $111.64 Daily Bare Costs Incl. O&P $562.80 710.80 1310.27 512.72 51.44 $53.48 $79.60 106.50 117.15 $3148.02 $159.98 $196.75 Crew No. Crew B-57 1 Labor Foreman (outside) 2 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (light) 1 Equip. Oper. (oiler) 1 Crawler Crane, 25 Ton 1 Clamshell Bucket, 1 C.Y. 1 Centr. Water Pump, 6⬙ 1 -20’ Suction Hose, 6⬙ 20 -50’ Discharge Hoses, 6⬙ Bare Costs Hr. Daily Hr. $49.25 47.25 66.30 59.70 56.40 $394.00 756.00 530.40 477.60 451.20 1274.00 46.89 386.48 28.12 399.80 $73.30 70.35 98.65 88.85 83.90 48 L.H., Daily Totals Crew B-58 2 Laborers 1 Equip. Oper. (light) 1 Backhoe Loader, 48 H.P. 1 Small Helicopter, w/ Pilot Incl. Subs O&P $4744.49 Hr. Daily Hr. $47.25 59.70 $756.00 477.60 277.19 5810.29 $70.35 88.85 24 L.H., Daily Totals $7321.08 Crew B-59 Hr. Daily Hr. 1 Truck Driver (heavy) 1 Truck Tractor, 220 H.P. 1 Water Tank Trailer, 5000 Gal. $55.45 $443.60 339.98 169.14 $82.85 8 L.H., Daily Totals $952.72 Crew B-59A Hr. Daily Hr. 2 Laborers 1 Truck Driver (heavy) 1 Water Tank Trailer, 5000 Gal. 1 Truck Tractor, 220 H.P. $47.25 55.45 $756.00 443.60 169.14 339.98 $70.35 82.85 24 L.H., Daily Totals Crew B-60 1 Labor Foreman (outside) 2 Laborers 1 Equip. Oper. (crane) 2 Equip. Oper. (light) 1 Equip. Oper. (oiler) 1 Crawler Crane, 40 Ton 1 Lead, 60’ High 1 Hammer, Diesel, 15K ft.-lbs. 1 Backhoe Loader, 48 H.P. $1708.72 Hr. Daily Hr. $49.25 47.25 66.30 59.70 56.40 $394.00 756.00 530.40 955.20 451.20 1362.63 233.36 687.50 277.19 $73.30 70.35 98.65 88.85 83.90 56 L.H., Daily Totals Crew B-61 1 Labor Foreman (outside) 3 Laborers 1 Equip. Oper. (light) 1 Cement Mixer, 2 C.Y. 1 Air Compressor, 160 cfm $5647.48 Hr. Daily Hr. $49.25 47.25 59.70 $394.00 1134.00 477.60 119.22 244.12 $73.30 70.35 88.85 40 L.H., Daily Totals Crew B-62 2 Laborers 1 Equip. Oper. (light) 1 Loader, Skid Steer, 30 H.P. 24 L.H., Daily Totals $2368.94 Hr. Daily Hr. $47.25 59.70 $756.00 477.60 260.99 $70.35 88.85 $1494.59 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 1125.60 789.20 710.80 671.20 1401.40 51.58 425.13 30.93 439.78 $54.36 $80.90 44.49 48.93 $6232.02 $98.84 $129.83 Daily Bare Costs Incl. O&P $1125.60 710.80 304.91 6391.32 $51.40 $76.52 253.65 279.01 $8532.63 $305.05 $355.53 Daily Bare Costs Incl. O&P $662.80 373.98 186.05 $55.45 $82.85 63.64 70.00 $1222.83 $119.09 $152.85 Daily Bare Costs Incl. O&P $1125.60 662.80 186.05 373.98 $49.98 $74.52 21.21 23.33 $2348.43 $71.20 $97.85 Daily Bare Costs Incl. O&P $586.40 1125.60 789.20 1421.60 671.20 1498.89 256.70 756.25 304.91 $55.12 $82.04 45.73 50.30 $7410.75 $100.85 $132.33 Daily Bare Costs Incl. O&P $586.40 1688.40 710.80 131.14 268.53 $50.14 $74.64 9.08 9.99 $3385.27 $59.22 $84.63 Daily Bare Costs Incl. O&P $1125.60 710.80 287.09 $51.40 $76.52 10.87 11.96 $2123.49 $62.27 $88.48 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 767 Crews - Standard Crew No. Crew B-62A 2 Laborers 1 Equip. Oper. (light) 1 Loader, Skid Steer, 30 H.P. 1 Trencher Attachment Bare Costs Hr. Daily Hr. $47.25 59.70 $756.00 477.60 260.99 88.83 $70.35 88.85 24 L.H., Daily Totals Crew B-63 4 Laborers 1 Equip. Oper. (light) 1 Loader, Skid Steer, 30 H.P. $1583.42 Hr. Daily Hr. $47.25 59.70 $1512.00 477.60 260.99 $70.35 88.85 40 L.H., Daily Totals Crew B-63B 1 Labor Foreman (inside) 2 Laborers 1 Equip. Oper. (light) 1 Loader, Skid Steer, 78 H.P. $2250.59 Hr. $47.75 47.25 59.70 32 L.H., Daily Totals Crew B-64 1 Laborer 1 Truck Driver (light) 1 Power Mulcher (small) 1 Flatbed Truck, Gas, 1.5 Ton 1 Laborer 1 Truck Driver (light) 1 Power Mulcher (Large) 1 Flatbed Truck, Gas, 1.5 Ton Hr. $47.25 52.90 1 Equip. Oper. (light) 1 Loader-Backhoe, 40 H.P. 1 Millwright 1 Equip. Oper. (light) 1 R.T. Forklift, 5,000 Lb., diesel 1 Millwright Foreman (inside) 1 Millwright Daily $378.00 423.20 264.41 361.95 Hr. $70.35 79.00 Daily Hr. $47.25 52.90 $378.00 423.20 633.63 361.95 $70.35 79.00 $1796.78 Hr. Daily Hr. $59.70 $477.60 222.27 $88.85 $699.87 Hr. $62.85 59.70 16 L.H., Daily Totals Crew B-67B $71.10 70.35 88.85 Hr. 8 L.H., Daily Totals Crew B-67 $382.00 756.00 477.60 429.91 Hr. $1427.56 16 L.H., Daily Totals Crew B-66 Daily $2045.51 16 L.H., Daily Totals Crew B-65 Incl. Subs O&P Daily $502.80 477.60 349.30 Hr. $90.80 88.85 $1329.70 Hr. Daily Hr. $63.35 62.85 $506.80 502.80 $91.55 90.80 16 L.H., Daily Totals $1009.60 Crew B-68 Hr. Daily Hr. 2 Millwrights 1 Equip. Oper. (light) 1 R.T. Forklift, 5,000 Lb., diesel $62.85 59.70 $1005.60 477.60 349.30 $90.80 88.85 24 L.H., Daily Totals Crew B-68A $1832.50 Hr. 1 Millwright Foreman (inside) $63.35 2 Millwrights 62.85 1 Forklift, Smooth Floor, 8,000 Lb. 24 L.H., Daily Totals 768 Daily Hr. $506.80 1005.60 311.06 $91.55 90.80 $1823.46 Cost Per Labor-Hour Bare Costs Incl. O&P $1125.60 710.80 287.09 97.71 $51.40 $76.52 14.58 16.03 $2221.20 $65.98 $92.55 Daily Bare Costs Incl. O&P $2251.20 710.80 287.09 $49.74 $74.05 6.52 7.18 $3249.09 $56.26 $81.23 Daily Bare Costs Incl. O&P Daily $568.80 1125.60 710.80 472.90 $50.49 $75.16 13.43 14.78 $2878.10 $63.92 $89.94 Daily Bare Costs Incl. O&P Crew No. Crew B-68B 1 Millwright Foreman (inside) 2 Millwrights 2 Electricians 2 Plumbers 1 R.T. Forklift, 5,000 Lb., gas Crew B-68C 1 Millwright Foreman (inside) 1 Millwright 1 Electrician 1 Plumber 1 R.T. Forklift, 5,000 Lb., gas $50.08 39.15 43.06 $1883.80 $89.22 $117.74 Daily Bare Costs Incl. O&P $562.80 632.00 696.99 398.14 $50.08 $74.67 62.22 68.45 $2289.94 $112.30 $143.12 Daily Bare Costs Incl. O&P $710.80 244.50 $59.70 27.78 $88.85 30.56 $955.30 $87.48 $119.41 Daily Bare Costs Incl. O&P $74.67 $61.27 21.83 24.01 $1821.43 $83.11 $113.84 Daily Bare Costs Incl. O&P $732.40 726.40 $63.10 $91.17 $1458.80 $63.10 $91.17 Daily Bare Costs Incl. O&P $1452.80 710.80 384.23 $61.80 $90.15 14.55 16.01 $2547.83 $76.35 $106.16 Daily Bare Costs Incl. O&P $732.40 1452.80 342.17 $63.02 $91.05 12.96 14.26 $2527.37 $75.98 $105.31 Hr. $63.35 62.85 67.35 72.05 $506.80 1005.60 1077.60 1152.80 422.09 $91.55 90.80 100.10 107.45 $4164.89 Hr. Daily Hr. $63.35 62.85 67.35 72.05 $506.80 502.80 538.80 576.40 422.09 $91.55 90.80 100.10 107.45 $2546.89 Hr. Daily Hr. $47.75 47.25 59.70 $382.00 378.00 477.60 422.09 $71.10 70.35 88.85 24 L.H., Daily Totals Crew B-68E $726.40 710.80 384.23 Daily 32 L.H., Daily Totals 1 Labor Foreman (inside) 1 Laborer 1 Equip. Oper. (light) 1 R.T. Forklift, 5,000 Lb., gas Incl. Subs O&P Hr. 56 L.H., Daily Totals Crew B-68D $562.80 632.00 290.85 398.14 Bare Costs $1659.69 Hr. 1 Struc. Steel Foreman (inside) $65.05 3 Struc. Steel Workers 64.55 1 Welder 64.55 1 Forklift, Smooth Floor, 8,000 Lb. 40 L.H., Daily Totals Daily Hr. $520.40 1549.20 516.40 311.06 $100.20 99.40 99.40 $2897.06 Crew B-68F Hr. Daily Hr. 1 Skilled Worker Foreman (out) 2 Skilled Workers 1 R.T. Forklift, 5,000 Lb., gas $63.25 61.25 $506.00 980.00 422.09 $95.00 92.00 24 L.H., Daily Totals Crew B-68G 2 Structural Steel Workers 1 R.T. Forklift, 5,000 Lb., gas $1908.09 Hr. Daily Hr. $64.55 $1032.80 422.09 $99.40 16 L.H., Daily Totals $1454.89 Bare Costs Incl. O&P $732.40 1452.80 1601.60 1719.20 464.30 $66.84 $98.32 7.54 8.29 $5970.30 $74.37 $106.61 Daily Bare Costs Incl. O&P $732.40 726.40 800.80 859.60 464.30 $66.40 $97.47 13.19 14.51 $3583.50 $79.59 $111.98 Daily Bare Costs Incl. O&P $568.80 562.80 710.80 464.30 $51.57 $76.77 17.59 19.35 $2306.70 $69.15 $96.11 Daily Bare Costs Incl. O&P $801.60 2385.60 795.20 342.17 $64.65 $99.56 7.78 8.55 $4324.57 $72.43 $108.11 Daily Bare Costs Incl. O&P $760.00 1472.00 464.30 $61.92 $93.00 17.59 19.35 $2696.30 $79.50 $112.35 Daily Bare Costs Incl. O&P $1590.40 464.30 $64.55 26.38 $99.40 29.02 $2054.70 $90.93 $128.42 Daily Bare Costs Incl. O&P $586.40 1688.40 789.20 671.20 2905.87 $52.28 $77.82 55.04 60.54 $6641.07 $107.32 $138.36 Daily Bare Costs Incl. O&P $586.40 1688.40 750.40 643.60 1181.65 $51.51 $76.43 22.38 24.62 $4850.45 $73.89 $101.05 Daily $89.83 Crew B-69 1 Labor Foreman (outside) 3 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 80 Ton Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 1134.00 530.40 451.20 2641.70 $73.30 70.35 98.65 83.90 48 L.H., Daily Totals Crew B-69A 1 Labor Foreman (outside) 3 Laborers 1 Equip. Oper. (medium) 1 Concrete Finisher 1 Curb/Gutter Paver, 2-Track 48 L.H., Daily Totals $5151.30 Hr. Daily Hr. $49.25 47.25 63.05 55.00 $394.00 1134.00 504.40 440.00 1074.23 $73.30 70.35 93.80 80.45 $3546.63 Cost Per Labor-Hour Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew B-69B 1 Labor Foreman (outside) 3 Laborers 1 Equip. Oper. (medium) 1 Cement Finisher 1 Curb/Gutter Paver, 4-Track Bare Costs Hr. Daily Hr. $49.25 47.25 63.05 55.00 $394.00 1134.00 504.40 440.00 1156.49 $73.30 70.35 93.80 80.45 48 L.H., Daily Totals Crew B-70 1 Labor Foreman (outside) 3 Laborers 3 Equip. Oper. (medium) 1 Grader, 30,000 Lbs. 1 Ripper, Beam & 1 Shank 1 Road Sweeper, S.P., 8’ wide 1 F.E. Loader, W.M., 1.5 C.Y. $3628.89 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 1134.00 1513.20 1091.19 100.54 538.01 455.32 $73.30 70.35 93.80 56 L.H., Daily Totals Crew B-70A 1 Laborer 4 Equip. Oper. (medium) 1 Grader, 40,000 Lbs. 1 F.E. Loader, W.M., 2.5 C.Y. 1 Dozer, 80 H.P. 1 Roller, Pneum. Whl., 12 Ton $5226.26 Hr. Daily Hr. $47.25 63.05 $378.00 2017.60 1254.97 658.89 591.82 384.55 $70.35 93.80 40 L.H., Daily Totals Crew B-71 1 Labor Foreman (outside) 3 Laborers 3 Equip. Oper. (medium) 1 Pvmt. Profiler, 750 H.P. 1 Road Sweeper, S.P., 8’ wide 1 F.E. Loader, W.M., 1.5 C.Y. $5285.83 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 1134.00 1513.20 3680.74 538.01 455.32 $73.30 70.35 93.80 56 L.H., Daily Totals Crew B-72 1 Labor Foreman (outside) 3 Laborers 4 Equip. Oper. (medium) 1 Pvmt. Profiler, 750 H.P. 1 Hammermill, 250 H.P. 1 Windrow Loader 1 Mix Paver, 165 H.P. 1 Roller, Pneum. Whl., 12 Ton Incl. Subs O&P $7715.27 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 1134.00 2017.60 3680.74 806.43 1473.50 1265.22 384.55 $73.30 70.35 93.80 64 L.H., Daily Totals $11156.04 Crew B-73 Hr. Daily Hr. 1 Labor Foreman (outside) 2 Laborers 5 Equip. Oper. (medium) 1 Road Mixer, 310 H.P. 1 Tandem Roller, 10 Ton 1 Hammermill, 250 H.P. 1 Grader, 30,000 Lbs. .5 F.E. Loader, W.M., 1.5 C.Y. .5 Truck Tractor, 220 H.P. .5 Water Tank Trailer, 5000 Gal. $49.25 47.25 63.05 $394.00 756.00 2522.00 2108.32 379.22 806.43 1091.19 227.66 169.99 84.57 $73.30 70.35 93.80 64 L.H., Daily Totals $8539.38 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 1688.40 750.40 643.60 1272.14 $51.51 $76.43 24.09 26.50 $4940.94 $75.60 $102.94 Daily Bare Costs Incl. O&P $586.40 1688.40 2251.20 1200.31 110.59 591.81 500.85 $54.31 $80.82 39.02 42.92 $6929.57 $93.33 $123.74 Daily Bare Costs Incl. O&P $562.80 3001.60 1380.47 724.78 651.00 423.01 $59.89 $89.11 72.26 79.48 $6743.65 $132.15 $168.59 Daily Bare Costs Incl. O&P $586.40 1688.40 2251.20 4048.81 591.81 500.85 $54.31 $80.82 83.47 91.81 $9667.48 $137.77 $172.63 Daily Bare Costs Incl. O&P $586.40 1688.40 3001.60 4048.81 887.07 1620.85 1391.74 423.01 $55.40 $82.44 118.91 130.80 $13647.88 $174.31 $213.25 Daily Bare Costs Incl. O&P $586.40 1125.60 3752.00 2319.15 417.14 887.07 1200.31 250.43 186.99 93.03 $57.38 $85.38 76.05 83.66 $10818.12 $133.43 $169.03 Daily Crew No. Bare Costs Incl. Subs O&P Crew B-74 Hr. Daily Hr. 1 Labor Foreman (outside) 1 Laborer 4 Equip. Oper. (medium) 2 Truck Drivers (heavy) 1 Grader, 30,000 Lbs. 1 Ripper, Beam & 1 Shank 2 Stabilizers, 310 H.P. 1 Flatbed Truck, Gas, 3 Ton 1 Chem. Spreader, Towed 1 Roller, Vibratory, 25 Ton 1 Water Tank Trailer, 5000 Gal. 1 Truck Tractor, 220 H.P. $49.25 47.25 63.05 55.45 $394.00 378.00 2017.60 887.20 1091.19 100.54 1713.46 391.02 87.61 529.68 169.14 339.98 $73.30 70.35 93.80 82.85 64 L.H., Daily Totals $8099.42 Crew B-75 Hr. Daily Hr. 1 Labor Foreman (outside) 1 Laborer 4 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Grader, 30,000 Lbs. 1 Ripper, Beam & 1 Shank 2 Stabilizers, 310 H.P. 1 Dist. Tanker, 3000 Gallon 1 Truck Tractor, 6x4, 380 H.P. 1 Roller, Vibratory, 25 Ton $49.25 47.25 63.05 55.45 $394.00 378.00 2017.60 443.60 1091.19 100.54 1713.46 367.10 545.98 529.68 $73.30 70.35 93.80 82.85 56 L.H., Daily Totals $7581.15 Crew B-76 Hr. Daily Hr. 1 Dock Builder Foreman (outside) 5 Dock Builders 2 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Crawler Crane, 50 Ton 1 Barge, 400 Ton 1 Hammer, Diesel, 15K ft.-lbs. 1 Lead, 60’ High 1 Air Compressor, 600 cfm 2 -50’ Air Hoses, 3⬙ $62.50 60.50 66.30 56.40 $500.00 2420.00 1060.80 451.20 1704.33 957.33 687.50 233.36 466.11 93.52 $96.70 93.60 98.65 83.90 72 L.H., Daily Totals Crew B-76A 1 Labor Foreman (outside) 5 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Crawler Crane, 50 Ton 1 Barge, 400 Ton $8574.15 Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 1890.00 530.40 451.20 1704.33 957.33 $73.30 70.35 98.65 83.90 64 L.H., Daily Totals Crew B-77 1 Labor Foreman (outside) 3 Laborers 1 Truck Driver (light) 1 Crack Cleaner, 25 H.P. 1 Crack Filler, Trailer Mtd. 1 Flatbed Truck, Gas, 3 Ton 40 L.H., Daily Totals $5927.26 Hr. Daily Hr. $49.25 47.25 52.90 $394.00 1134.00 423.20 167.33 201.26 391.02 $73.30 70.35 79.00 $2710.81 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 562.80 3001.60 1325.60 1200.31 110.59 1884.81 430.12 96.37 582.65 186.05 373.98 $57.45 $85.57 69.10 76.01 $10341.28 $126.55 $161.58 Daily Bare Costs Incl. O&P $586.40 562.80 3001.60 662.80 1200.31 110.59 1884.81 403.81 600.58 582.65 $57.74 $85.96 77.64 85.41 $9596.34 $135.38 $171.36 Daily Bare Costs Incl. O&P $773.60 3744.00 1578.40 671.20 1874.76 1053.06 756.25 256.70 512.72 102.87 $61.56 $93.99 57.53 63.28 $11323.57 $119.09 $157.27 Daily Bare Costs Incl. O&P $586.40 2814.00 789.20 671.20 1874.76 1053.06 $51.02 $75.95 41.59 45.75 $7788.63 $92.61 $121.70 Daily Bare Costs Incl. O&P $586.40 1688.40 632.00 184.06 221.39 430.12 $48.78 $72.67 18.99 20.89 $3742.37 $67.77 $93.56 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 769 Crews - Standard Crew No. Crew B-78 1 Labor Foreman (outside) 4 Laborers 1 Truck Driver (light) 1 Paint Striper, S.P., 40 Gallon 1 Flatbed Truck, Gas, 3 Ton 1 Pickup Truck, 3/4 Ton Bare Costs Hr. Daily Hr. $49.25 47.25 52.90 $394.00 1512.00 423.20 73.74 391.02 122.56 $73.30 70.35 79.00 48 L.H., Daily Totals Crew B-78A Incl. Subs O&P $2916.52 Hr. 1 Equip. Oper. (light) $59.70 1 Line Rem. (Metal Balls) 115 H.P. 8 L.H., Daily Totals Daily $477.60 1648.72 Hr. $88.85 $2126.32 Crew B-78B Hr. Daily Hr. 2 Laborers .25 Equip. Oper. (light) 1 Pickup Truck, 3/4 Ton 1 Line Rem.,11 H.P.,Walk Behind .25 Road Sweeper, S.P., 8’ wide $47.25 59.70 $756.00 119.40 122.56 214.39 134.50 $70.35 88.85 18 L.H., Daily Totals Crew B-78C 1 Labor Foreman (outside) 4 Laborers 1 Truck Driver (light) 1 Paint Striper, T.M., 120 Gal. 1 Flatbed Truck, Gas, 3 Ton 1 Pickup Truck, 3/4 Ton $1346.85 Hr. Daily Hr. $49.25 47.25 52.90 $394.00 1512.00 423.20 673.88 391.02 122.56 $73.30 70.35 79.00 48 L.H., Daily Totals Crew B-78D 2 Labor Foremen (outside) 7 Laborers 1 Truck Driver (light) 1 Paint Striper, T.M., 120 Gal. 1 Flatbed Truck, Gas, 3 Ton 3 Pickup Trucks, 3/4 Ton 1 Air Compressor, 60 cfm 1 -50’ Air Hose, 3/4⬙ 1 Breaker, Pavement, 60 lb. $3516.66 Hr. Daily Hr. $49.25 47.25 52.90 $788.00 2646.00 423.20 673.88 391.02 367.68 173.21 8.16 34.47 $73.30 70.35 79.00 80 L.H., Daily Totals Crew B-78E 2 Labor Foremen (outside) 9 Laborers 1 Truck Driver (light) 1 Paint Striper, T.M., 120 Gal. 1 Flatbed Truck, Gas, 3 Ton 4 Pickup Trucks, 3/4 Ton 2 Air Compressors, 60 cfm 2 -50’ Air Hoses, 3/4⬙ 2 Breakers, Pavement, 60 lb. 96 L.H., Daily Totals $5505.62 Hr. Daily Hr. $49.25 47.25 52.90 $788.00 3402.00 423.20 673.88 391.02 490.24 346.42 16.32 68.94 $73.30 70.35 79.00 $6600.02 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 2251.20 632.00 81.11 430.12 134.82 $48.52 $72.28 12.24 13.46 $4115.65 $60.76 $85.74 Daily Bare Costs Incl. O&P Daily $710.80 1813.59 $59.70 206.09 $88.85 226.70 $2524.39 $265.79 $315.55 Daily Bare Costs Incl. O&P $1125.60 177.70 134.82 235.83 147.95 $48.63 $72.41 26.19 28.81 $1821.90 $74.83 $101.22 Daily Bare Costs Incl. O&P $586.40 2251.20 632.00 741.27 430.12 134.82 $48.52 $72.28 24.74 27.21 $4775.81 $73.26 $99.50 Daily Bare Costs Incl. O&P $1172.80 3939.60 632.00 741.27 430.12 404.45 190.53 8.98 37.92 $48.22 $71.81 20.61 22.67 $7557.66 $68.82 $94.47 Daily Bare Costs Incl. O&P $1172.80 5065.20 632.00 741.27 430.12 539.26 381.06 17.95 75.83 $48.05 $71.56 20.70 22.77 $9055.50 $68.75 $94.33 Crew No. Crew B-78F 2 Labor Foremen (outside) 11 Laborers 1 Truck Driver (light) 1 Paint Striper, T.M., 120 Gal. 1 Flatbed Truck, Gas, 3 Ton 7 Pickup Trucks, 3/4 Ton 3 Air Compressors, 60 cfm 3 -50’ Air Hoses, 3/4⬙ 3 Breakers, Pavement, 60 lb. Crew B-79 1 Labor Foreman (outside) 3 Laborers 1 Truck Driver (light) 1 Paint Striper, T.M., 120 Gal. 1 Heating Kettle, 115 Gallon 1 Flatbed Truck, Gas, 3 Ton 2 Pickup Trucks, 3/4 Ton Daily Hr. $49.25 47.25 52.90 $788.00 4158.00 423.20 673.88 391.02 857.92 519.63 24.48 103.41 $73.30 70.35 79.00 $7939.54 Hr. Daily Hr. $49.25 47.25 52.90 $394.00 1134.00 423.20 673.88 169.64 391.02 245.12 $73.30 70.35 79.00 40 L.H., Daily Totals Crew B-79A $3430.86 Hr. 1.5 Equip. Oper. (light) $59.70 .5 Line Remov. (Grinder) 115 H.P. 1 Line Rem. (Metal Balls) 115 H.P. 12 L.H., Daily Totals Crew B-79B 1 Laborer 1 Set of Gases 1 Labor Foreman (outside) 5 Laborers 1 Truck Driver (light) 1 Paint Striper, T.M., 120 Gal. 1 Heating Kettle, 115 Gallon 1 Flatbed Truck, Gas, 3 Ton 3 Pickup Trucks, 3/4 Ton 1 Air Compressor, 60 cfm 1 -50’ Air Hose, 3/4⬙ 1 Breaker, Pavement, 60 lb. 2 Labor Foremen (outside) 5 Laborers 1 Truck Driver (light) 1 Paint Striper, T.M., 120 Gal. 1 Heating Kettle, 115 Gallon 1 Flatbed Truck, Gas, 3 Ton 4 Pickup Trucks, 3/4 Ton 1 Air Compressor, 60 cfm 1 -50’ Air Hose, 3/4⬙ 1 Breaker, Pavement, 60 lb. Hr. $716.40 843.37 1648.72 $88.85 Hr. Daily Hr. $47.25 $378.00 188.67 $70.35 Hr. Daily Hr. $49.25 47.25 52.90 $394.00 1890.00 423.20 673.88 169.64 391.02 367.68 173.21 8.16 34.47 $73.30 70.35 79.00 $4525.26 Hr. Daily Hr. $49.25 47.25 52.90 $788.00 1890.00 423.20 673.88 169.64 391.02 490.24 173.21 8.16 34.47 $73.30 70.35 79.00 $5041.82 Cost Per Labor-Hour Bare Costs Incl. O&P $1172.80 6190.80 632.00 741.27 430.12 943.71 571.59 26.93 113.75 $47.94 $71.39 22.95 25.24 $10822.97 $70.89 $96.63 Daily Bare Costs Incl. O&P $586.40 1688.40 632.00 741.27 186.60 430.12 269.63 $48.78 $72.67 36.99 40.69 $4534.43 $85.77 $113.36 Daily Bare Costs Incl. O&P $1066.20 927.71 1813.59 $59.70 $88.85 207.67 228.44 $3807.50 $267.37 $317.29 Daily Bare Costs Incl. O&P $562.80 207.54 $47.25 23.58 $70.35 25.94 $770.34 $70.83 $96.29 Daily Bare Costs Incl. O&P $586.40 2814.00 632.00 741.27 186.60 430.12 404.45 190.53 8.98 37.92 $48.34 $72.01 32.47 35.71 $6032.27 $80.81 $107.72 Daily Bare Costs Incl. O&P $1172.80 2814.00 632.00 741.27 186.60 430.12 539.26 190.53 8.98 37.92 $48.46 $72.17 30.32 33.35 $6753.48 $78.78 $105.52 Daily $566.67 56 L.H., Daily Totals Crew B-79D Daily $3208.49 8 L.H., Daily Totals Crew B-79C Incl. Subs O&P Hr. 112 L.H., Daily Totals 64 L.H., Daily Totals 770 Bare Costs Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew B-79E 2 Labor Foremen (outside) 7 Laborers 1 Truck Driver (light) 1 Paint Striper, T.M., 120 Gal. 1 Heating Kettle, 115 Gallon 1 Flatbed Truck, Gas, 3 Ton 5 Pickup Trucks, 3/4 Ton 2 Air Compressors, 60 cfm 2 -50’ Air Hoses, 3/4⬙ 2 Breakers, Pavement, 60 lb. Bare Costs Hr. Daily Hr. $49.25 47.25 52.90 $788.00 2646.00 423.20 673.88 169.64 391.02 612.80 346.42 16.32 68.94 $73.30 70.35 79.00 80 L.H., Daily Totals Crew B-80 1 Labor Foreman (outside) 1 Laborer 1 Truck Driver (light) 1 Equip. Oper. (light) 1 Flatbed Truck, Gas, 3 Ton 1 Earth Auger, Truck-Mtd. $6136.22 Hr. Daily Hr. $49.25 47.25 52.90 59.70 $394.00 378.00 423.20 477.60 391.02 153.97 $73.30 70.35 79.00 88.85 32 L.H., Daily Totals Crew B-80A 3 Laborers 1 Flatbed Truck, Gas, 3 Ton Incl. Subs O&P $2217.79 Hr. Daily Hr. $47.25 $1134.00 391.02 $70.35 24 L.H., Daily Totals $1525.02 Crew B-80B Hr. Daily Hr. 3 Laborers 1 Equip. Oper. (light) 1 Crane, Flatbed Mounted, 3 Ton $47.25 59.70 $1134.00 477.60 596.44 $70.35 88.85 32 L.H., Daily Totals $2208.04 Crew B-80C Hr. Daily Hr. 2 Laborers 1 Truck Driver (light) 1 Flatbed Truck, Gas, 1.5 Ton 1 Manual Fence Post Auger, Gas $47.25 52.90 $756.00 423.20 361.95 52.21 $70.35 79.00 24 L.H., Daily Totals $1593.36 Crew B-81 Hr. Daily Hr. 1 Laborer 1 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Hydromulcher, T.M., 3000 Gal. 1 Truck Tractor, 220 H.P. $47.25 63.05 55.45 $378.00 504.40 443.60 745.16 339.98 $70.35 93.80 82.85 24 L.H., Daily Totals $2411.14 Crew B-81A Hr. Daily Hr. 1 Laborer 1 Truck Driver (light) 1 Hydromulcher, T.M., 600 Gal. 1 Flatbed Truck, Gas, 3 Ton $47.25 52.90 $378.00 423.20 234.78 391.02 $70.35 79.00 16 L.H., Daily Totals Crew B-82 1 Laborer 1 Equip. Oper. (light) 1 Horiz. Borer, 6 H.P. 16 L.H., Daily Totals $1427.00 Hr. Daily Hr. $47.25 59.70 $378.00 477.60 114.54 $70.35 88.85 $970.14 Cost Per Labor-Hour Bare Costs Incl. O&P $1172.80 3939.60 632.00 741.27 186.60 430.12 674.08 381.06 17.95 75.83 $48.22 $71.81 28.49 31.34 $8251.32 $76.70 $103.14 Daily Bare Costs Incl. O&P $586.40 562.80 632.00 710.80 430.12 169.37 $52.27 $77.88 17.03 18.73 $3091.49 $69.31 $96.61 Daily Bare Costs Incl. O&P $1688.40 430.12 $47.25 16.29 $70.35 17.92 $2118.52 $63.54 $88.27 Daily Bare Costs Incl. O&P $1688.40 710.80 656.08 $50.36 $74.97 18.64 20.50 $3055.28 $69.00 $95.48 Daily Bare Costs Incl. O&P $1125.60 632.00 398.14 57.43 $49.13 $73.23 17.26 18.98 $2213.18 $66.39 $92.22 Daily Bare Costs Incl. O&P $562.80 750.40 662.80 819.68 373.98 $55.25 $82.33 45.21 49.74 $3169.65 $100.46 $132.07 Daily Bare Costs Incl. O&P $562.80 632.00 258.26 430.12 $50.08 $74.67 39.11 43.02 $1883.18 $89.19 $117.70 Daily Bare Costs Incl. O&P $562.80 710.80 125.99 $53.48 $79.60 7.16 7.87 $1399.59 $60.63 $87.47 Daily Crew No. Bare Costs Incl. Subs O&P Crew B-82A Hr. Daily Hr. 2 Laborers 2 Equip. Opers. (light) 2 Dump Truck, 8 C.Y., 220 H.P. 1 Flatbed Trailer, 25 Ton 1 Horiz. Dir. Drill, 20k lb. Thrust 1 Mud Trailer for HDD, 1500 Gal. 1 Pickup Truck, 4x4, 3/4 Ton 1 Flatbed Trailer, 3 Ton 1 Loader, Skid Steer, 78 H.P. $47.25 59.70 $756.00 955.20 834.98 150.61 685.30 696.17 191.73 78.34 429.91 $70.35 88.85 32 L.H., Daily Totals $4778.24 Crew B-82B Hr. Daily Hr. 2 Laborers 2 Equip. Opers. (light) 2 Dump Truck, 8 C.Y., 220 H.P. 1 Flatbed Trailer, 25 Ton 1 Horiz. Dir. Drill, 30k lb. Thrust 1 Mud Trailer for HDD, 1500 Gal. 1 Pickup Truck, 4x4, 3/4 Ton 1 Flatbed Trailer, 3 Ton 1 Loader, Skid Steer, 78 H.P. $47.25 59.70 $756.00 955.20 834.98 150.61 740.76 696.17 191.73 78.34 429.91 $70.35 88.85 32 L.H., Daily Totals $4833.70 Crew B-82C Hr. Daily Hr. 2 Laborers 2 Equip. Opers. (light) 2 Dump Truck, 8 C.Y., 220 H.P. 1 Flatbed Trailer, 25 Ton 1 Horiz. Dir. Drill, 50k lb. Thrust 1 Mud Trailer for HDD, 1500 Gal. 1 Pickup Truck, 4x4, 3/4 Ton 1 Flatbed Trailer, 3 Ton 1 Loader, Skid Steer, 78 H.P. $47.25 59.70 $756.00 955.20 834.98 150.61 869.81 696.17 191.73 78.34 429.91 $70.35 88.85 32 L.H., Daily Totals $4962.75 Crew B-82D Hr. Daily Hr. 1 Equip. Oper. (light) 1 Mud Trailer for HDD, 1500 Gal. $59.70 $477.60 696.17 $88.85 8 L.H., Daily Totals Crew B-83 1 Tugboat Captain 1 Tugboat Hand 1 Tugboat, 250 H.P. $1173.77 Hr. Daily Hr. $63.05 47.25 $504.40 378.00 793.50 $93.80 70.35 16 L.H., Daily Totals Crew B-84 1 Equip. Oper. (medium) 1 Rotary Mower/Tractor $1675.90 Hr. Daily Hr. $63.05 $504.40 238.84 $93.80 8 L.H., Daily Totals $743.24 Crew B-85 Hr. Daily Hr. 3 Laborers 1 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Telescoping Boom Lift, to 80’ 1 Brush Chipper, 12⬙, 130 H.P. 1 Pruning Saw, Rotary $47.25 63.05 55.45 $1134.00 504.40 443.60 710.06 518.12 27.37 $70.35 93.80 82.85 40 L.H., Daily Totals $3337.55 Cost Per Labor-Hour Bare Costs Incl. O&P $1125.60 1421.60 918.48 165.67 753.83 765.79 210.90 86.17 472.90 $53.48 $79.60 95.84 105.43 $5920.94 $149.32 $185.03 Daily Bare Costs Incl. O&P $1125.60 1421.60 918.48 165.67 814.84 765.79 210.90 86.17 472.90 $53.48 $79.60 97.58 107.34 $5981.95 $151.05 $186.94 Daily Bare Costs Incl. O&P $1125.60 1421.60 918.48 165.67 956.79 765.79 210.90 86.17 472.90 $53.48 $79.60 101.61 111.77 $6123.90 $155.09 $191.37 Daily Bare Costs Incl. O&P $710.80 765.79 $59.70 87.02 $88.85 95.72 $1476.59 $146.72 $184.57 Daily Bare Costs Incl. O&P $750.40 562.80 872.85 $55.15 $82.08 49.59 54.55 $2186.05 $104.74 $136.63 Daily Bare Costs Incl. O&P $750.40 262.72 $63.05 29.86 $93.80 32.84 $1013.12 $92.91 $126.64 Daily Bare Costs Incl. O&P $1688.40 750.40 662.80 781.07 569.93 30.11 $52.05 $77.54 31.39 34.53 $4482.70 $83.44 $112.07 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 771 Crews - Standard Crew No. Crew B-86 1 Equip. Oper. (medium) 1 Stump Chipper, S.P. Bare Costs Hr. Daily Hr. $63.05 $504.40 263.85 $93.80 8 L.H., Daily Totals Crew B-86A 1 Equip. Oper. (medium) 1 Grader, 30,000 Lbs. $768.25 Hr. Daily Hr. $63.05 $504.40 1091.19 $93.80 8 L.H., Daily Totals Crew B-86B 1 Equip. Oper. (medium) 1 Dozer, 200 H.P. $1595.59 Hr. Daily Hr. $63.05 $504.40 1382.36 $93.80 8 L.H., Daily Totals Crew B-87 1 Laborer 4 Equip. Oper. (medium) 2 Feller Bunchers, 100 H.P. 1 Log Chipper, 22⬙ Tree 1 Dozer, 105 H.P. 1 Chain Saw, Gas, 36⬙ Long $1886.76 Hr. Daily Hr. $47.25 63.05 $378.00 2017.60 2244.42 686.57 702.68 53.61 $70.35 93.80 40 L.H., Daily Totals Crew B-88 1 Laborer 6 Equip. Oper. (medium) 2 Feller Bunchers, 100 H.P. 1 Log Chipper, 22⬙ Tree 2 Log Skidders, 50 H.P. 1 Dozer, 105 H.P. 1 Chain Saw, Gas, 36⬙ Long $6082.88 Hr. Daily Hr. $47.25 63.05 $378.00 3026.40 2244.42 686.57 931.94 702.68 53.61 $70.35 93.80 56 L.H., Daily Totals Crew B-89 1 Equip. Oper. (light) 1 Truck Driver (light) 1 Flatbed Truck, Gas, 3 Ton 1 Concrete Saw 1 Water Tank, 65 Gal. $8023.62 Hr. Daily Hr. $59.70 52.90 $477.60 423.20 391.02 176.00 97.09 $88.85 79.00 16 L.H., Daily Totals Crew B-89A 1 Skilled Worker 1 Laborer 1 Core Drill (Large) $1564.91 Hr. Daily Hr. $61.25 47.25 $490.00 378.00 118.14 $92.00 70.35 16 L.H., Daily Totals Crew B-89B 1 Equip. Oper. (light) 1 Truck Driver (light) 1 Wall Saw, Hydraulic, 10 H.P. 1 Generator, Diesel, 100 kW 1 Water Tank, 65 Gal. 1 Flatbed Truck, Gas, 3 Ton $986.14 Hr. Daily Hr. $59.70 52.90 $477.60 423.20 111.53 568.06 97.09 391.02 $88.85 79.00 16 L.H., Daily Totals Crew B-89C 1 Cement Finisher 1 Masonry cut-off saw, gas 8 L.H., Daily Totals 772 Incl. Subs O&P $2068.50 Hr. Daily Hr. $55.00 $440.00 68.42 $80.45 $508.42 Cost Per Labor-Hour Daily Bare Costs Incl. O&P $750.40 290.24 $63.05 32.98 $93.80 36.28 $1040.64 $96.03 $130.08 Daily Bare Costs Incl. O&P $750.40 1200.31 $63.05 136.40 $93.80 150.04 $1950.71 $199.45 $243.84 Daily Bare Costs Incl. O&P $750.40 1520.60 $63.05 172.79 $93.80 190.07 $2271.00 $235.85 $283.87 Daily Bare Costs Incl. O&P $562.80 3001.60 2468.86 755.23 772.95 58.97 $59.89 $89.11 92.18 101.40 $7620.41 $152.07 $190.51 Daily Bare Costs Incl. O&P $562.80 4502.40 2468.86 755.23 1025.13 772.95 58.97 $60.79 $90.45 82.49 90.73 $10146.34 $143.28 $181.18 Daily Bare Costs Incl. O&P $710.80 632.00 430.12 193.60 106.80 $56.30 $83.92 41.51 45.66 $2073.32 $97.81 $129.58 Daily Bare Costs Incl. O&P $736.00 562.80 129.95 $54.25 $81.17 7.38 8.12 $1428.75 $61.63 $89.30 Daily Bare Costs Incl. O&P $710.80 632.00 122.68 624.87 106.80 430.12 $56.30 $83.92 72.98 80.28 $2627.27 $129.28 $164.20 Daily Bare Costs Incl. O&P $643.60 75.26 $55.00 8.55 $80.45 9.41 $718.86 $63.55 $89.86 Crew No. Crew B-90 1 Labor Foreman (outside) 3 Laborers 2 Equip. Oper. (light) 2 Truck Drivers (heavy) 1 Road Mixer, 310 H.P. 1 Dist. Truck, 2000 Gal. Bare Costs Hr. Daily Hr. $49.25 47.25 59.70 55.45 $394.00 1134.00 955.20 887.20 2108.32 333.32 $73.30 70.35 88.85 82.85 64 L.H., Daily Totals Crew B-90A 1 Labor Foreman (outside) 2 Laborers 4 Equip. Oper. (medium) 2 Graders, 30,000 Lbs. 1 Tandem Roller, 10 Ton 1 Roller, Pneum. Whl., 12 Ton $5812.04 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 756.00 2017.60 2182.38 379.22 384.55 $73.30 70.35 93.80 56 L.H., Daily Totals Crew B-90B 1 Labor Foreman (outside) 2 Laborers 3 Equip. Oper. (medium) 1 Roller, Pneum. Whl., 12 Ton 1 Road Mixer, 310 H.P. $6113.75 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 756.00 1513.20 384.55 2108.32 $73.30 70.35 93.80 48 L.H., Daily Totals Crew B-90C 1 Labor Foreman (outside) 4 Laborers 3 Equip. Oper. (medium) 3 Truck Drivers (heavy) 3 Road Mixers, 310 H.P. $5156.07 Hr. Daily Hr. $49.25 47.25 63.05 55.45 $394.00 1512.00 1513.20 1330.80 6324.96 $73.30 70.35 93.80 82.85 88 L.H., Daily Totals Crew B-90D 1 Labor Foreman (outside) 6 Laborers 3 Equip. Oper. (medium) 3 Truck Drivers (heavy) 3 Road Mixers, 310 H.P. $11074.96 Hr. Daily Hr. $49.25 47.25 63.05 55.45 $394.00 2268.00 1513.20 1330.80 6324.96 $73.30 70.35 93.80 82.85 104 L.H., Daily Totals Crew B-90E 1 Labor Foreman (outside) 4 Laborers 3 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Road Mixer, 310 H.P. Incl. Subs O&P $11830.96 Hr. Daily Hr. $49.25 47.25 63.05 55.45 $394.00 1512.00 1513.20 443.60 2108.32 $73.30 70.35 93.80 82.85 72 L.H., Daily Totals $5971.12 Crew B-91 Hr. Daily Hr. 1 Labor Foreman (outside) 2 Laborers 4 Equip. Oper. (medium) 1 Truck Driver (heavy) 1 Dist. Tanker, 3000 Gallon 1 Truck Tractor, 6x4, 380 H.P. 1 Aggreg. Spreader, S.P. 1 Roller, Pneum. Whl., 12 Ton 1 Tandem Roller, 10 Ton $49.25 47.25 63.05 55.45 $394.00 756.00 2017.60 443.60 367.10 545.98 941.36 384.55 379.22 $73.30 70.35 93.80 82.85 64 L.H., Daily Totals $6229.41 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 1688.40 1421.60 1325.60 2319.15 366.65 $52.66 $78.47 38.15 41.97 $7707.80 $90.81 $120.43 Daily Bare Costs Incl. O&P $586.40 1125.60 3001.60 2400.62 417.14 423.01 $56.56 $84.17 52.61 57.87 $7954.36 $109.17 $142.04 Daily Bare Costs Incl. O&P $586.40 1125.60 2251.20 423.01 2319.15 $55.48 $82.57 51.93 57.13 $6705.36 $107.42 $139.69 Daily Bare Costs Incl. O&P $586.40 2251.20 2251.20 1988.40 6957.46 $53.98 $80.42 71.87 79.06 $14034.66 $125.85 $159.48 Daily Bare Costs Incl. O&P $586.40 3376.80 2251.20 1988.40 6957.46 $52.94 $78.87 60.82 66.90 $15160.26 $113.76 $145.77 Daily Bare Costs Incl. O&P $586.40 2251.20 2251.20 662.80 2319.15 $53.65 $79.88 29.28 32.21 $8070.75 $82.93 $112.09 Daily Bare Costs Incl. O&P $586.40 1125.60 3001.60 662.80 403.81 600.58 1035.50 423.01 417.14 $56.42 $84.01 40.91 45.00 $8256.43 $97.33 $129.01 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew B-91B 1 Laborer 1 Equipment Oper. (med.) 1 Road Sweeper, Vac. Assist. Bare Costs Hr. Daily Hr. $47.25 63.05 $378.00 504.40 1900.22 $70.35 93.80 16 L.H., Daily Totals Crew B-91C 1 Laborer 1 Truck Driver (light) 1 Catch Basin Cleaning Truck Incl. Subs O&P $2782.62 Hr. Daily Hr. $47.25 52.90 $378.00 423.20 594.04 $70.35 79.00 16 L.H., Daily Totals $1395.24 Crew B-91D Hr. Daily Hr. 1 Labor Foreman (outside) 5 Laborers 5 Equip. Oper. (medium) 2 Truck Drivers (heavy) 1 Aggreg. Spreader, S.P. 2 Truck Tractors, 6x4, 380 H.P. 2 Dist. Tankers, 3000 Gallon 2 Pavement Brushes, Towed 2 Rollers Pneum. Whl., 12 Ton $49.25 47.25 63.05 55.45 $394.00 1890.00 2522.00 887.20 941.36 1091.96 734.20 194.16 769.10 $73.30 70.35 93.80 82.85 104 L.H., Daily Totals Crew B-92 1 Labor Foreman (outside) 3 Laborers 1 Crack Cleaner, 25 H.P. 1 Air Compressor, 60 cfm 1 Tar Kettle, T.M. 1 Flatbed Truck, Gas, 3 Ton $9423.98 Hr. Daily Hr. $49.25 47.25 $394.00 1134.00 167.33 173.21 199.54 391.02 $73.30 70.35 32 L.H., Daily Totals Crew B-93 1 Equip. Oper. (medium) 1 Feller Buncher, 100 H.P. $2459.10 Hr. Daily Hr. $63.05 $504.40 1122.21 $93.80 8 L.H., Daily Totals Crew B-94A 1 Laborer 1 Diaphragm Water Pump, 2⬙ 1 -20’ Suction Hose, 2⬙ 2 -50’ Discharge Hoses, 2⬙ $1626.61 Hr. Daily Hr. $47.25 $378.00 61.92 4.37 8.18 $70.35 8 L.H., Daily Totals Crew B-94B 1 Laborer 1 Diaphragm Water Pump, 4⬙ 1 -20’ Suction Hose, 4⬙ 2 -50’ Discharge Hoses, 4⬙ $452.47 Hr. Daily Hr. $47.25 $378.00 150.72 19.04 28.30 $70.35 8 L.H., Daily Totals Crew B-94C 1 Laborer 1 Centrifugal Water Pump, 3⬙ 1 -20’ Suction Hose, 3⬙ 2 -50’ Discharge Hoses, 3⬙ 8 L.H., Daily Totals $576.06 Hr. Daily Hr. $47.25 $378.00 82.39 8.96 9.76 $70.35 $479.11 Cost Per Labor-Hour Bare Costs Incl. O&P $562.80 750.40 2090.24 $55.15 $82.08 118.76 130.64 $3403.44 $173.91 $212.72 Daily Bare Costs Incl. O&P $562.80 632.00 653.44 $50.08 $74.67 37.13 40.84 $1848.24 $87.20 $115.52 Daily Bare Costs Incl. O&P $586.40 2814.00 3752.00 1325.60 1035.50 1201.16 807.62 213.58 846.01 $54.74 $81.52 35.87 39.46 $12581.86 $90.62 $120.98 Daily Bare Costs Incl. O&P $586.40 1688.40 184.06 190.53 219.49 430.12 $47.75 $71.09 29.10 32.01 $3299.01 $76.85 $103.09 Daily Bare Costs Incl. O&P $750.40 1234.43 $63.05 140.28 $93.80 154.30 $1984.83 $203.33 $248.10 Daily Bare Costs Incl. O&P $562.80 68.11 4.81 9.00 $47.25 $70.35 9.31 10.24 $644.72 $56.56 $80.59 Daily Bare Costs Incl. O&P $562.80 165.79 20.94 31.13 $47.25 $70.35 24.76 27.23 $780.67 $72.01 $97.58 Daily Bare Costs Incl. O&P $562.80 90.63 9.86 10.74 $47.25 $70.35 12.64 13.90 $674.02 $59.89 $84.25 Daily Crew No. Crew B-94D 1 Laborer 1 Centr. Water Pump, 6⬙ 1 -20’ Suction Hose, 6⬙ 2 -50’ Discharge Hoses, 6⬙ Bare Costs Hr. Daily Hr. $47.25 $378.00 386.48 28.12 39.98 $70.35 8 L.H., Daily Totals Crew C-1 3 Carpenters 1 Laborer $832.58 Hr. Daily Hr. $58.60 47.25 $1406.40 378.00 $87.25 70.35 32 L.H., Daily Totals Crew C-2 1 Carpenter Foreman (outside) 4 Carpenters 1 Laborer $1784.40 Hr. Daily Hr. $60.60 58.60 47.25 $484.80 1875.20 378.00 $90.20 87.25 70.35 48 L.H., Daily Totals Crew C-2A 1 Carpenter Foreman (outside) 3 Carpenters 1 Cement Finisher 1 Laborer $2738.00 Hr. Daily Hr. $60.60 58.60 55.00 47.25 $484.80 1406.40 440.00 378.00 $90.20 87.25 80.45 70.35 48 L.H., Daily Totals Crew C-3 1 Rodman Foreman (outside) 4 Rodmen (reinf.) 1 Equip. Oper. (light) 2 Laborers 3 Stressing Equipment .5 Grouting Equipment $2709.20 Hr. Daily Hr. $66.55 64.55 59.70 47.25 $532.40 2065.60 477.60 756.00 51.87 97.91 $99.40 96.40 88.85 70.35 64 L.H., Daily Totals Crew C-4 1 Rodman Foreman (outside) 3 Rodmen (reinf.) 3 Stressing Equipment $3981.38 Hr. Daily Hr. $66.55 64.55 $532.40 1549.20 51.87 $99.40 96.40 32 L.H., Daily Totals Crew C-4A 2 Rodmen (reinf.) 4 Stressing Equipment $2133.47 Hr. Daily Hr. $64.55 $1032.80 69.16 $96.40 16 L.H., Daily Totals Crew C-5 1 Rodman Foreman (outside) 4 Rodmen (reinf.) 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 25 Ton $1101.96 Hr. Daily Hr. $66.55 64.55 66.30 56.40 $532.40 2065.60 530.40 451.20 2273.31 $99.40 96.40 98.65 83.90 56 L.H., Daily Totals Crew C-6 1 Labor Foreman (outside) 4 Laborers 1 Cement Finisher 2 Gas Engine Vibrators 48 L.H., Daily Totals Incl. Subs O&P $5852.91 Hr. Daily Hr. $49.25 47.25 55.00 $394.00 1512.00 440.00 59.36 $73.30 70.35 80.45 $2405.36 Cost Per Labor-Hour Bare Costs Incl. O&P $562.80 425.13 30.93 43.98 $47.25 $70.35 56.82 62.50 $1062.84 $104.07 $132.85 Daily Bare Costs Incl. O&P $2094.00 562.80 $55.76 $83.03 $2656.80 $55.76 $83.03 Daily Bare Costs Incl. O&P $721.60 2792.00 562.80 $57.04 $84.92 $4076.40 $57.04 $84.92 Daily Bare Costs Incl. O&P $721.60 2094.00 643.60 562.80 $56.44 $83.79 $4022.00 $56.44 $83.79 Daily Bare Costs Incl. O&P $795.20 3084.80 710.80 1125.60 57.06 107.70 $59.87 $89.32 2.34 2.57 $5881.15 $62.21 $91.89 Daily Bare Costs Incl. O&P $795.20 2313.60 57.06 $65.05 $97.15 1.62 1.78 $3165.86 $66.67 $98.93 Daily Bare Costs Incl. O&P $1542.40 76.08 $64.55 4.32 $96.40 4.75 $1618.48 $68.87 $101.15 Daily Bare Costs Incl. O&P $795.20 3084.80 789.20 671.20 2500.64 $63.92 $95.36 40.59 44.65 $7841.04 $104.52 $140.02 Daily Bare Costs Incl. O&P $586.40 2251.20 643.60 65.30 $48.88 $72.53 1.24 1.36 $3546.50 $50.11 $73.89 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 773 Crews - Standard Crew No. Bare Costs Incl. Subs O&P Crew C-6A Hr. Daily Hr. 2 Cement Finishers 1 Concrete Vibrator, Elec, 2 HP $55.00 $880.00 32.92 $80.45 16 L.H., Daily Totals Crew C-7 1 Labor Foreman (outside) 5 Laborers 1 Cement Finisher 1 Equip. Oper. (medium) 1 Equip. Oper. (oiler) 2 Gas Engine Vibrators 1 Concrete Bucket, 1 C.Y. 1 Hyd. Crane, 55 Ton $912.92 Hr. Daily Hr. $49.25 47.25 55.00 63.05 56.40 $394.00 1890.00 440.00 504.40 451.20 59.36 50.97 2461.06 $73.30 70.35 80.45 93.80 83.90 72 L.H., Daily Totals Crew C-7A 1 Labor Foreman (outside) 5 Laborers 2 Truck Drivers (heavy) 2 Conc. Transit Mixers $6250.99 Hr. Daily Hr. $49.25 47.25 55.45 $394.00 1890.00 887.20 1400.52 $73.30 70.35 82.85 64 L.H., Daily Totals $4571.72 Crew C-7B Hr. Daily Hr. 1 Labor Foreman (outside) 5 Laborers 1 Equipment Operator, Crane 1 Equipment Oiler 1 Conc. Bucket, 2 C.Y. 1 Lattice Boom Crane, 165 Ton $49.25 47.25 66.30 56.40 $394.00 1890.00 530.40 451.20 76.52 2672.17 $73.30 70.35 98.65 83.90 64 L.H., Daily Totals Crew C-7C 1 Labor Foreman (outside) 5 Laborers 2 Equipment Operators (med.) 2 F.E. Loaders, W.M., 4 C.Y. $6014.29 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 1890.00 1008.80 1579.96 $73.30 70.35 93.80 64 L.H., Daily Totals Crew C-7D 1 Labor Foreman (outside) 5 Laborers 1 Equip. Oper. (medium) 1 Concrete Conveyer $4872.76 Hr. Daily Hr. $49.25 47.25 63.05 $394.00 1890.00 504.40 194.76 $73.30 70.35 93.80 56 L.H., Daily Totals Crew C-8 1 Labor Foreman (outside) 3 Laborers 2 Cement Finishers 1 Equip. Oper. (medium) 1 Concrete Pump (Small) $2983.16 Hr. Daily Hr. $49.25 47.25 55.00 63.05 $394.00 1134.00 880.00 504.40 827.49 $73.30 70.35 80.45 93.80 56 L.H., Daily Totals Crew C-8A 1 Labor Foreman (outside) 3 Laborers 2 Cement Finishers 48 L.H., Daily Totals $3739.89 Hr. Daily Hr. $49.25 47.25 55.00 $394.00 1134.00 880.00 $73.30 70.35 80.45 $2408.00 Cost Per Labor-Hour Daily Bare Costs Incl. O&P $1287.20 36.21 $55.00 2.06 $80.45 2.26 $1323.41 $57.06 $82.71 Daily Bare Costs Incl. O&P $586.40 2814.00 643.60 750.40 671.20 65.30 56.07 2707.17 $51.11 $75.91 35.71 39.29 $8294.13 $86.82 $115.20 Daily Bare Costs Incl. O&P $586.40 2814.00 1325.60 1540.57 $49.55 $73.84 21.88 24.07 $6266.57 $71.43 $97.92 Daily Bare Costs Incl. O&P $586.40 2814.00 789.20 671.20 84.17 2939.39 $51.02 $75.95 42.95 47.24 $7884.36 $93.97 $123.19 Daily Bare Costs Incl. O&P $586.40 2814.00 1500.80 1737.96 $51.45 $76.58 24.69 27.16 $6639.16 $76.14 $103.74 Daily Bare Costs Incl. O&P $586.40 2814.00 750.40 214.24 $49.79 $74.12 3.48 3.83 $4365.04 $53.27 $77.95 Daily Bare Costs Incl. O&P $586.40 1688.40 1287.20 750.40 910.24 $52.01 $77.01 14.78 16.25 $5222.64 $66.78 $93.26 Daily Bare Costs Incl. O&P $586.40 1688.40 1287.20 $50.17 $74.21 $3562.00 $50.17 $74.21 Crew No. Crew C-8B 1 Labor Foreman (outside) 3 Laborers 1 Equip. Oper. (medium) 1 Vibrating Power Screed 1 Roller, Vibratory, 25 Ton 1 Dozer, 200 H.P. Crew C-8C Daily Hr. $49.25 47.25 63.05 $394.00 1134.00 504.40 90.64 529.68 1382.36 $73.30 70.35 93.80 $4035.08 Hr. 1 Labor Foreman (outside) $49.25 3 Laborers 47.25 1 Cement Finisher 55.00 1 Equip. Oper. (medium) 63.05 1 Shotcrete Pump Rig, 12 C.Y./hr 1 Air Compressor, 160 cfm 4 -50’ Air Hoses, 1⬙ 4 -50’ Air Hoses, 2⬙ 48 L.H., Daily Totals Crew C-8D 1 Labor Foreman (outside) 1 Laborer 1 Cement Finisher 1 Equipment Oper. (light) 1 Air Compressor, 250 cfm 2 -50’ Air Hoses, 1⬙ 1 Labor Foreman (outside) 3 Laborers 1 Cement Finisher 1 Equipment Oper. (light) 1 Shotcrete Rig, 35 C.Y./hr 1 Air Compressor, 250 cfm 4 -50’ Air Hoses, 1⬙ 4 -50’ Air Hoses, 2⬙ 1 Cement Finisher 2 Laborers 1 Equipment Oper. (light) 1 Grout Pump, 50 C.F./hr. 1 Air Compressor, 160 cfm 2 -50’ Air Hoses, 1⬙ 2 -50’ Air Hoses, 2⬙ 1 Laborer 2 Cement Finishers 3 Laborers 2 Cement Finishers 1 Concrete Mixer, 10 C.F. 2 Trowels, 48⬙ Walk-Behind $73.30 70.35 80.45 93.80 Hr. $49.25 47.25 55.00 59.70 $394.00 378.00 440.00 477.60 196.28 18.62 $73.30 70.35 80.45 88.85 $1904.50 Hr. Daily Hr. $49.25 47.25 55.00 59.70 $394.00 1134.00 440.00 477.60 797.28 196.28 37.24 129.40 $73.30 70.35 80.45 88.85 $3605.80 Hr. Daily Hr. $55.00 47.25 59.70 $440.00 756.00 477.60 158.45 244.12 18.62 64.70 $80.45 70.35 88.85 $2159.49 Hr. Daily Hr. $47.25 55.00 $378.00 880.00 $70.35 80.45 24 L.H., Daily Totals Crew C-10B $394.00 1134.00 440.00 504.40 651.19 244.12 37.24 129.40 Daily 32 L.H., Daily Totals Crew C-10 Hr. Hr. 48 L.H., Daily Totals Crew C-9 Daily $3534.35 32 L.H., Daily Totals Crew C-8E Incl. Subs O&P Hr. 40 L.H., Daily Totals 40 L.H., Daily Totals 774 Bare Costs $1258.00 Hr. Daily Hr. $47.25 55.00 $1134.00 880.00 149.77 171.24 $70.35 80.45 $2335.01 Cost Per Labor-Hour Bare Costs Incl. O&P $586.40 1688.40 750.40 99.70 582.65 1520.60 $50.81 $75.63 50.07 55.07 $5228.15 $100.88 $130.70 Daily Bare Costs Incl. O&P $586.40 1688.40 643.60 750.40 716.31 268.53 40.96 142.34 $51.51 $76.43 22.12 24.34 $4836.94 $73.63 $100.77 Daily Bare Costs Incl. O&P $586.40 562.80 643.60 710.80 215.91 20.48 $52.80 $78.24 6.72 7.39 $2739.99 $59.52 $85.62 Daily Bare Costs Incl. O&P $586.40 1688.40 643.60 710.80 877.01 215.91 40.96 142.34 $50.95 $75.61 24.17 26.59 $4905.42 $75.12 $102.20 Daily Bare Costs Incl. O&P $643.60 1125.60 710.80 174.29 268.53 20.48 71.17 $52.30 $77.50 15.18 16.70 $3014.48 $67.48 $94.20 Daily Bare Costs Incl. O&P $562.80 1287.20 $52.42 $77.08 $1850.00 $52.42 $77.08 Daily Bare Costs Incl. O&P $1688.40 1287.20 164.75 188.36 $50.35 $74.39 8.03 8.83 $3328.71 $58.38 $83.22 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew C-10C 1 Laborer 2 Cement Finishers 1 Trowel, 48⬙ Walk-Behind Bare Costs Hr. Daily Hr. $47.25 55.00 $378.00 880.00 85.62 $70.35 80.45 24 L.H., Daily Totals Crew C-10D 1 Laborer 2 Cement Finishers 1 Vibrating Power Screed 1 Trowel, 48⬙ Walk-Behind $1343.62 Hr. Daily Hr. $47.25 55.00 $378.00 880.00 90.64 85.62 $70.35 80.45 24 L.H., Daily Totals Crew C-10E 1 Laborer 2 Cement Finishers 1 Vibrating Power Screed 1 Cement Trowel, 96⬙ Ride-On Incl. Subs O&P $1434.26 Hr. Daily Hr. $47.25 55.00 $378.00 880.00 90.64 225.34 $70.35 80.45 24 L.H., Daily Totals $1573.98 Crew C-10F Hr. Daily Hr. 1 Laborer 2 Cement Finishers 1 Telescoping Boom Lift, to 60’ $47.25 55.00 $378.00 880.00 385.68 $70.35 80.45 24 L.H., Daily Totals $1643.68 Crew C-11 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 6 Struc. Steel Workers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Lattice Boom Crane, 150 Ton $66.55 64.55 66.30 56.40 $532.40 3098.40 530.40 451.20 2585.11 $102.50 99.40 98.65 83.90 72 L.H., Daily Totals Crew C-12 1 Carpenter Foreman (outside) 3 Carpenters 1 Laborer 1 Equip. Oper. (crane) 1 Hyd. Crane, 12 Ton $7197.51 Hr. Daily Hr. $60.60 58.60 47.25 66.30 $484.80 1406.40 378.00 530.40 2150.65 $90.20 87.25 70.35 98.65 48 L.H., Daily Totals $4950.25 Crew C-13 Hr. Daily Hr. 1 Struc. Steel Worker 1 Welder 1 Carpenter 1 Welder, Gas Engine, 300 amp $64.55 64.55 58.60 $516.40 516.40 468.80 147.09 $99.40 99.40 87.25 24 L.H., Daily Totals Crew C-14 1 Carpenter Foreman (outside) 5 Carpenters 4 Laborers 4 Rodmen (reinf.) 2 Cement Finishers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 80 Ton 144 L.H., Daily Totals $1648.69 Hr. Daily Hr. $60.60 58.60 47.25 64.55 55.00 66.30 56.40 $484.80 2344.00 1512.00 2065.60 880.00 530.40 451.20 2641.70 $90.20 87.25 70.35 96.40 80.45 98.65 83.90 $10909.70 Cost Per Labor-Hour Bare Costs Incl. O&P $562.80 1287.20 94.18 $52.42 $77.08 3.57 3.92 $1944.18 $55.98 $81.01 Daily Bare Costs Incl. O&P $562.80 1287.20 99.70 94.18 $52.42 $77.08 7.34 8.08 $2043.89 $59.76 $85.16 Daily Bare Costs Incl. O&P $562.80 1287.20 99.70 247.87 $52.42 $77.08 13.17 14.48 $2197.58 $65.58 $91.57 Daily Bare Costs Incl. O&P $562.80 1287.20 424.25 $52.42 $77.08 16.07 17.68 $2274.25 $68.49 $94.76 Daily Bare Costs Incl. O&P $820.00 4771.20 789.20 671.20 2843.62 $64.06 $97.94 35.90 39.49 $9895.22 $99.97 $137.43 Daily Bare Costs Incl. O&P $721.60 2094.00 562.80 789.20 2365.72 $58.33 $86.83 44.81 49.29 $6533.31 $103.13 $136.11 Daily Bare Costs Incl. O&P $795.20 795.20 698.00 161.80 $62.57 $95.35 6.13 6.74 $2450.20 $68.70 $102.09 Daily Crew C-14A 1 Carpenter Foreman (outside) 16 Carpenters 4 Rodmen (reinf.) 2 Laborers 1 Cement Finisher 1 Equip. Oper. (medium) 1 Gas Engine Vibrator 1 Concrete Pump (Small) Bare Costs Crew C-14B 1 Carpenter Foreman (outside) 16 Carpenters 4 Rodmen (reinf.) 2 Laborers 2 Cement Finishers 1 Equip. Oper. (medium) 1 Gas Engine Vibrator 1 Concrete Pump (Small) Daily Hr. $60.60 58.60 64.55 47.25 55.00 63.05 $484.80 7500.80 2065.60 756.00 440.00 504.40 29.68 827.49 $90.20 87.25 96.40 70.35 80.45 93.80 $12608.77 Hr. Daily Hr. $60.60 58.60 64.55 47.25 55.00 63.05 $484.80 7500.80 2065.60 756.00 880.00 504.40 29.68 827.49 $90.20 87.25 96.40 70.35 80.45 93.80 208 L.H., Daily Totals Crew C-14C 1 Carpenter Foreman (outside) 6 Carpenters 2 Rodmen (reinf.) 4 Laborers 1 Cement Finisher 1 Gas Engine Vibrator $13048.77 Hr. Daily Hr. $60.60 58.60 64.55 47.25 55.00 $484.80 2812.80 1032.80 1512.00 440.00 29.68 $90.20 87.25 96.40 70.35 80.45 112 L.H., Daily Totals Crew C-14D Incl. O&P $721.60 3490.00 2251.20 3084.80 1287.20 789.20 671.20 2905.87 $57.42 $85.38 18.35 20.18 $15201.07 $75.76 $105.56 1 Carpenter Foreman (outside) 18 Carpenters 2 Rodmen (reinf.) 2 Laborers 1 Cement Finisher 1 Equip. Oper. (medium) 1 Gas Engine Vibrator 1 Concrete Pump (Small) $6312.08 Hr. Daily Hr. $60.60 58.60 64.55 47.25 55.00 63.05 $484.80 8438.40 1032.80 756.00 440.00 504.40 29.68 827.49 $90.20 87.25 96.40 70.35 80.45 93.80 200 L.H., Daily Totals Crew C-14E 1 Carpenter Foreman (outside) 2 Carpenters 4 Rodmen (reinf.) 3 Laborers 1 Cement Finisher 1 Gas Engine Vibrator $12513.57 Hr. Daily Hr. $60.60 58.60 64.55 47.25 55.00 $484.80 937.60 2065.60 1134.00 440.00 29.68 $90.20 87.25 96.40 70.35 80.45 88 L.H., Daily Totals Crew C-14F 1 Labor Foreman (outside) 2 Laborers 6 Cement Finishers 1 Gas Engine Vibrator 72 L.H., Daily Totals Incl. Subs O&P Hr. 200 L.H., Daily Totals Bare Costs Daily Crew No. $5091.68 Hr. Daily Hr. $49.25 47.25 55.00 $394.00 756.00 2640.00 29.68 $73.30 70.35 80.45 $3819.68 Cost Per Labor-Hour Bare Costs Incl. O&P $721.60 11168.00 3084.80 1125.60 643.60 750.40 32.65 910.24 $58.76 $87.47 4.29 4.71 $18436.89 $63.04 $92.18 Daily Bare Costs Incl. O&P $721.60 11168.00 3084.80 1125.60 1287.20 750.40 32.65 910.24 $58.61 $87.20 4.12 4.53 $19080.49 $62.73 $91.73 Daily Bare Costs Incl. O&P $721.60 4188.00 1542.40 2251.20 643.60 32.65 $56.09 $83.45 .27 .29 $9379.45 $56.36 $83.75 Daily Bare Costs Incl. O&P $721.60 12564.00 1542.40 1125.60 643.60 750.40 32.65 910.24 $58.28 $86.74 4.29 4.71 $18290.49 $62.57 $91.45 Daily Bare Costs Incl. O&P $721.60 1396.00 3084.80 1688.40 643.60 32.65 $57.52 $85.62 .34 .37 $7567.05 $57.86 $85.99 Daily Bare Costs Incl. O&P $586.40 1125.60 3861.60 32.65 $52.64 $77.41 .41 .45 $5606.25 $53.05 $77.86 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 775 Crews - Standard Crew No. Crew C-14G 1 Labor Foreman (outside) 2 Laborers 4 Cement Finishers 1 Gas Engine Vibrator Bare Costs Hr. Daily Hr. $49.25 47.25 55.00 $394.00 756.00 1760.00 29.68 $73.30 70.35 80.45 56 L.H., Daily Totals Crew C-14H 1 Carpenter Foreman (outside) 2 Carpenters 1 Rodman (reinf.) 1 Laborer 1 Cement Finisher 1 Gas Engine Vibrator $2939.68 Hr. Daily Hr. $60.60 58.60 64.55 47.25 55.00 $484.80 937.60 516.40 378.00 440.00 29.68 $90.20 87.25 96.40 70.35 80.45 48 L.H., Daily Totals Crew C-14L 1 Carpenter Foreman (outside) 6 Carpenters 4 Laborers 1 Cement Finisher 1 Gas Engine Vibrator $2786.48 Hr. Daily Hr. $60.60 58.60 47.25 55.00 $484.80 2812.80 1512.00 440.00 29.68 $90.20 87.25 70.35 80.45 96 L.H., Daily Totals Crew C-14M 1 Carpenter Foreman (outside) 2 Carpenters 1 Rodman (reinf.) 2 Laborers 1 Cement Finisher 1 Equip. Oper. (medium) 1 Gas Engine Vibrator 1 Concrete Pump (Small) $5279.28 Hr. Daily Hr. $60.60 58.60 64.55 47.25 55.00 63.05 $484.80 937.60 516.40 756.00 440.00 504.40 29.68 827.49 $90.20 87.25 96.40 70.35 80.45 93.80 64 L.H., Daily Totals Crew C-15 1 Carpenter Foreman (outside) 2 Carpenters 3 Laborers 2 Cement Finishers 1 Rodman (reinf.) $4496.37 Hr. Daily Hr. $60.60 58.60 47.25 55.00 64.55 $484.80 937.60 1134.00 880.00 516.40 $90.20 87.25 70.35 80.45 96.40 72 L.H., Daily Totals Crew C-16 1 Labor Foreman (outside) 3 Laborers 2 Cement Finishers 1 Equip. Oper. (medium) 1 Gunite Pump Rig 2 -50’ Air Hoses, 3/4⬙ 2 -50’ Air Hoses, 2⬙ Incl. Subs O&P $3952.80 Hr. Daily Hr. $49.25 47.25 55.00 63.05 $394.00 1134.00 880.00 504.40 352.58 16.32 64.70 $73.30 70.35 80.45 93.80 56 L.H., Daily Totals $3346.00 Crew C-16A Hr. Daily Hr. 1 Laborer 2 Cement Finishers 1 Equip. Oper. (medium) 1 Gunite Pump Rig 2 -50’ Air Hoses, 3/4⬙ 2 -50’ Air Hoses, 2⬙ 1 Telescoping Boom Lift, to 60’ $47.25 55.00 63.05 $378.00 880.00 504.40 352.58 16.32 64.70 385.68 $70.35 80.45 93.80 32 L.H., Daily Totals 776 $2581.68 Cost Per Labor-Hour Crew No. Bare Costs Incl. Subs O&P Bare Costs Incl. O&P $586.40 1125.60 2574.40 32.65 $51.96 $76.54 .53 .58 $4319.05 $52.49 $77.13 Crew C-17A Hr. Daily Hr. Daily Bare Costs Incl. O&P $721.60 1396.00 771.20 562.80 643.60 32.65 $57.43 $85.32 2 Skilled Worker Foremen (out) 8 Skilled Workers .13 Equip. Oper. (crane) .13 Hyd. Crane, 80 Ton $63.25 61.25 66.30 $1012.00 3920.00 68.95 343.42 $95.00 92.00 98.65 .62 .68 $4127.85 $58.05 $86.00 Daily Bare Costs Incl. O&P $721.60 4188.00 2251.20 643.60 32.65 $54.68 $81.30 .31 .34 $7837.05 $54.99 $81.64 Daily Bare Costs Incl. O&P $721.60 1396.00 771.20 1125.60 643.60 750.40 32.65 910.24 $56.86 $84.51 13.39 14.73 $6351.29 $70.26 $99.24 Daily Bare Costs Incl. O&P $721.60 1396.00 1688.40 1287.20 771.20 $54.90 $81.45 $5864.40 $54.90 $81.45 Daily Bare Costs Incl. O&P $586.40 1688.40 1287.20 750.40 387.84 17.95 71.17 $52.01 $77.01 7.74 8.52 $4789.36 $59.75 $85.52 9.04 L.H., Daily Totals Daily Bare Costs Incl. O&P Crew C-20 $562.80 1287.20 750.40 387.84 17.95 71.17 424.25 $55.08 $81.26 25.60 28.16 $3501.61 $80.68 $109.43 Daily Crew C-17 Hr. Daily Hr. 2 Skilled Worker Foremen (out) 8 Skilled Workers $63.25 61.25 $1012.00 3920.00 $95.00 92.00 80 L.H., Daily Totals $4932.00 81.04 L.H., Daily Totals $5344.37 Crew C-17B Hr. Daily Hr. 2 Skilled Worker Foremen (out) 8 Skilled Workers .25 Equip. Oper. (crane) .25 Hyd. Crane, 80 Ton .25 Trowel, 48⬙ Walk-Behind $63.25 61.25 66.30 $1012.00 3920.00 132.60 660.42 21.41 $95.00 92.00 98.65 82 L.H., Daily Totals $5746.43 Crew C-17C Hr. Daily Hr. 2 Skilled Worker Foremen (out) 8 Skilled Workers .38 Equip. Oper. (crane) .38 Hyd. Crane, 80 Ton $63.25 61.25 66.30 $1012.00 3920.00 201.55 1003.85 $95.00 92.00 98.65 83.04 L.H., Daily Totals $6137.40 Crew C-17D Hr. Daily Hr. 2 Skilled Worker Foremen (out) 8 Skilled Workers .5 Equip. Oper. (crane) .5 Hyd. Crane, 80 Ton $63.25 61.25 66.30 $1012.00 3920.00 265.20 1320.85 $95.00 92.00 98.65 84 L.H., Daily Totals $6518.05 Crew C-17E Hr. Daily Hr. 2 Skilled Worker Foremen (out) 8 Skilled Workers 1 Hyd. Jack with Rods $63.25 61.25 $1012.00 3920.00 40.57 $95.00 92.00 80 L.H., Daily Totals Crew C-18 .13 Labor Foreman (outside) 1 Laborer 1 Concrete Cart, 10 C.F. $4972.57 Hr. Daily Hr. $49.25 47.25 $51.22 378.00 149.92 $73.30 70.35 9.04 L.H., Daily Totals Crew C-19 .13 Labor Foreman (outside) 1 Laborer 1 Concrete Cart, 18 C.F. 1 Labor Foreman (outside) 5 Laborers 1 Cement Finisher 1 Equip. Oper. (medium) 2 Gas Engine Vibrators 1 Concrete Pump (Small) 64 L.H., Daily Totals Bare Costs Incl. O&P $1520.00 5888.00 $61.65 $92.60 $7408.00 $61.65 $92.60 Daily Bare Costs Incl. O&P $1520.00 5888.00 102.60 377.76 $61.71 $92.68 4.24 4.66 $7888.36 $65.95 $97.34 Daily Bare Costs Incl. O&P $1520.00 5888.00 197.30 726.47 23.55 $61.76 $92.75 8.31 9.15 $8355.31 $70.08 $101.89 Daily Bare Costs Incl. O&P $1520.00 5888.00 299.90 1104.23 $61.82 $92.82 12.09 13.30 $8812.13 $73.91 $106.12 Daily Bare Costs Incl. O&P $1520.00 5888.00 394.60 1452.93 $61.87 $92.89 15.72 17.30 $9255.53 $77.60 $110.18 Daily Bare Costs Incl. O&P $1520.00 5888.00 44.63 $61.65 $92.60 .51 .56 $7452.63 $62.16 $93.16 Daily Bare Costs Incl. O&P $76.23 562.80 164.91 $47.48 $70.69 16.58 18.24 $803.94 $64.06 $88.93 Daily Bare Costs Incl. O&P $76.23 562.80 135.00 $47.48 $70.69 13.58 14.93 $774.03 $61.06 $85.62 Daily Bare Costs Incl. O&P $586.40 2814.00 643.60 750.40 65.30 910.24 $50.44 $74.91 13.86 15.24 $5769.94 $64.30 $90.16 Daily $579.14 Hr. Daily Hr. $49.25 47.25 $51.22 378.00 122.73 $73.30 70.35 $551.95 Hr. Daily Hr. $49.25 47.25 55.00 63.05 $394.00 1890.00 440.00 504.40 59.36 827.49 $73.30 70.35 80.45 93.80 $4115.25 Cost Per Labor-Hour Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew C-21 1 Labor Foreman (outside) 5 Laborers 1 Cement Finisher 1 Equip. Oper. (medium) 2 Gas Engine Vibrators 1 Concrete Conveyer Bare Costs Hr. Daily Hr. $49.25 47.25 55.00 63.05 $394.00 1890.00 440.00 504.40 59.36 194.76 $73.30 70.35 80.45 93.80 64 L.H., Daily Totals Crew C-22 1 Rodman Foreman (outside) 4 Rodmen (reinf.) .13 Equip. Oper. (crane) .13 Equip. Oper. (oiler) .13 Hyd. Crane, 25 Ton Incl. Subs O&P $3482.52 Hr. Daily Hr. $66.55 64.55 66.30 56.40 $532.40 2065.60 68.95 58.66 295.53 $99.40 96.40 98.65 83.90 42.08 L.H., Daily Totals $3021.14 Crew C-23 Hr. Daily Hr. 2 Skilled Worker Foremen (out) 6 Skilled Workers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Lattice Boom Crane, 90 Ton $63.25 61.25 66.30 56.40 $1012.00 2940.00 530.40 451.20 2689.54 $95.00 92.00 98.65 83.90 80 L.H., Daily Totals Crew C-23A 1 Labor Foreman (outside) 2 Laborers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Crawler Crane, 100 Ton 3 Conc. Buckets, 8 C.Y. $7623.14 Hr. Daily Hr. $49.25 47.25 66.30 56.40 $394.00 756.00 530.40 451.20 1552.12 425.58 $73.30 70.35 98.65 83.90 40 L.H., Daily Totals $4109.30 Crew C-24 Hr. Daily Hr. 2 Skilled Worker Foremen (out) 6 Skilled Workers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Lattice Boom Crane, 150 Ton $63.25 61.25 66.30 56.40 $1012.00 2940.00 530.40 451.20 2585.11 $95.00 92.00 98.65 83.90 80 L.H., Daily Totals Crew C-25 2 Rodmen (reinf.) 2 Rodmen Helpers $7518.71 Hr. Daily Hr. $64.55 38.85 $1032.80 621.60 $96.40 62.95 32 L.H., Daily Totals Crew C-27 2 Cement Finishers 1 Concrete Saw $1654.40 Hr. Daily Hr. $55.00 $880.00 176.00 $80.45 16 L.H., Daily Totals $1056.00 Crew C-28 Hr. Daily Hr. 1 Cement Finisher 1 Portable Air Compressor, Gas $55.00 $440.00 34.53 $80.45 8 L.H., Daily Totals Crew C-29 1 Laborer 1 Pressure Washer 8 L.H., Daily Totals $474.53 Hr. Daily Hr. $47.25 $378.00 104.23 $70.35 $482.23 Cost Per Labor-Hour Crew No. Bare Costs Incl. O&P $586.40 2814.00 643.60 750.40 65.30 214.24 $50.44 $74.91 3.97 4.37 $5073.93 $54.41 $79.28 1 Cement Finisher 1 Grout Pump Bare Costs Incl. O&P 8 L.H., Daily Totals Daily $795.20 3084.80 102.60 87.26 325.08 $64.77 $96.72 7.02 7.73 $4394.94 $71.80 $104.44 Daily Bare Costs Incl. O&P $1520.00 4416.00 789.20 671.20 2958.49 $61.67 $92.45 33.62 36.98 $10354.89 $95.29 $129.44 Daily Bare Costs Incl. O&P $586.40 1125.60 789.20 671.20 1707.33 468.14 $53.29 $79.31 49.44 54.39 $5347.87 $102.73 $133.70 Daily Bare Costs Incl. O&P $1520.00 4416.00 789.20 671.20 2843.62 $61.67 $92.45 32.31 35.55 $10240.02 $93.98 $128.00 Daily Bare Costs Incl. O&P $1542.40 1007.20 $51.70 $79.67 $2549.60 $51.70 $79.67 Daily Bare Costs Incl. O&P $1287.20 193.60 $55.00 11.00 $80.45 12.10 3 Bricklayers 3 Bricklayer Helpers .25 Carpenter $1480.80 $66.00 $92.55 50 L.H., Daily Totals Daily Bare Costs Incl. O&P $643.60 37.98 $55.00 4.32 $80.45 4.75 1 Tile Layer 1 Tile Layer Helper $681.58 $59.32 $85.20 16 L.H., Daily Totals Daily Bare Costs Incl. O&P $562.80 114.65 $47.25 13.03 $70.35 14.33 3 Bricklayers 2 Bricklayer Helpers $677.45 $60.28 $84.68 40 L.H., Daily Totals Daily Crew C-30 1 Laborer 1 Concrete Mixer, 10 C.F. Bare Costs Hr. Daily Hr. $47.25 $378.00 149.77 $70.35 8 L.H., Daily Totals Crew C-31 Incl. Subs O&P Daily Hr. $55.00 $440.00 352.58 $80.45 $792.58 Crew C-32 Hr. Daily Hr. 1 Cement Finisher 1 Laborer 1 Crack Chaser Saw, Gas, 6 H.P. 1 Vacuum Pick-Up System $55.00 47.25 $440.00 378.00 86.61 73.53 $80.45 70.35 16 L.H., Daily Totals Crew D-1 1 Bricklayer 1 Bricklayer Helper $978.14 Hr. Daily Hr. $57.50 46.65 $460.00 373.20 $86.35 70.05 16 L.H., Daily Totals Crew D-2 3 Bricklayers 2 Bricklayer Helpers .5 Carpenter $833.20 Hr. Daily Hr. $57.50 46.65 58.60 $1380.00 746.40 234.40 $86.35 70.05 87.25 44 L.H., Daily Totals Crew D-3 3 Bricklayers 2 Bricklayer Helpers .25 Carpenter $2360.80 Hr. Daily Hr. $57.50 46.65 58.60 $1380.00 746.40 117.20 $86.35 70.05 87.25 42 L.H., Daily Totals Crew D-4 1 Bricklayer 2 Bricklayer Helpers 1 Equip. Oper. (light) 1 Grout Pump, 50 C.F./hr. $2243.60 Hr. Daily Hr. $57.50 46.65 59.70 $460.00 746.40 477.60 158.45 $86.35 70.05 88.85 32 L.H., Daily Totals Crew D-5 1 Bricklayer $1842.45 Hr. 57.50 8 L.H., Daily Totals Crew D-6 Crew D-7 Crew D-8 Daily Bare Costs Incl. O&P $562.80 164.75 $47.25 18.72 $70.35 20.59 $727.55 $65.97 $90.94 Daily Bare Costs Incl. O&P $643.60 387.84 $55.00 44.07 $80.45 48.48 $1031.44 $99.07 $128.93 Daily Bare Costs Incl. O&P $643.60 562.80 95.27 80.88 $51.13 $75.40 10.01 11.01 $1382.55 $61.13 $86.41 Daily Bare Costs Incl. O&P $690.80 560.40 $52.08 $78.20 $1251.20 $52.08 $78.20 Daily Bare Costs Incl. O&P $2072.40 1120.80 349.00 $53.65 $80.50 $3542.20 $53.65 $80.50 Daily Bare Costs Incl. O&P $2072.40 1120.80 174.50 $53.42 $80.18 $3367.70 $53.42 $80.18 Daily Bare Costs Incl. O&P $690.80 1120.80 710.80 174.29 $52.63 $78.83 4.95 5.45 $2696.70 $57.58 $84.27 Daily Bare Costs Incl. O&P $527.77 Hr. Daily Hr. 460.00 86.35 690.80 57.50 86.35 $690.80 $57.50 $86.35 Daily Bare Costs Incl. O&P $2072.40 1681.20 174.50 $52.34 $78.56 $3928.10 $52.34 $78.56 Daily Bare Costs Incl. O&P $646.40 520.00 $49.90 $72.90 $1166.40 $49.90 $72.90 Daily Bare Costs Incl. O&P $2072.40 1120.80 $53.16 $79.83 $3193.20 $53.16 $79.83 $460.00 Hr. Daily Hr. $57.50 46.65 58.60 $1380.00 1119.60 117.20 $86.35 70.05 87.25 $2616.80 Hr. Daily Hr. $55.30 44.50 $442.40 356.00 $80.80 65.00 $798.40 Hr. Daily Hr. $57.50 46.65 $1380.00 746.40 $86.35 70.05 $2126.40 Cost Per Labor-Hour Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 777 Crews - Standard Crew No. Crew D-9 3 Bricklayers 3 Bricklayer Helpers Bare Costs Hr. Daily Hr. $57.50 46.65 $1380.00 1119.60 $86.35 70.05 48 L.H., Daily Totals Crew D-10 1 Bricklayer Foreman (outside) 1 Bricklayer 1 Bricklayer Helper 1 Equip. Oper. (crane) 1 S.P. Crane, 4x4, 12 Ton $2499.60 Hr. $59.50 57.50 46.65 66.30 32 L.H., Daily Totals Crew D-11 1 Bricklayer Foreman (outside) 1 Bricklayer 1 Bricklayer Helper 1 Bricklayer Foreman (outside) 1 Bricklayer 2 Bricklayer Helpers 1 Bricklayer Foreman (outside) 1 Bricklayer 2 Bricklayer Helpers 1 Carpenter 1 Equip. Oper. (crane) 1 S.P. Crane, 4x4, 12 Ton 3 Bricklayers 1 Bricklayer Helper $89.35 86.35 70.05 98.65 Daily Hr. $59.50 57.50 46.65 $476.00 460.00 373.20 $89.35 86.35 70.05 $1309.20 Hr. Daily Hr. $59.50 57.50 46.65 $476.00 460.00 746.40 $89.35 86.35 70.05 $1682.40 Hr. Daily Hr. $59.50 57.50 46.65 58.60 66.30 $476.00 460.00 746.40 468.80 530.40 637.99 $89.35 86.35 70.05 87.25 98.65 48 L.H., Daily Totals Crew D-14 $476.00 460.00 373.20 530.40 637.99 Hr. Hr. 32 L.H., Daily Totals Crew D-13 Daily $2477.59 24 L.H., Daily Totals Crew D-12 Incl. Subs O&P $3319.59 Hr. Daily Hr. $57.50 46.65 $1380.00 373.20 $86.35 70.05 32 L.H., Daily Totals $1753.20 Crew E-1 Hr. Daily Hr. 1 Welder Foreman (outside) 1 Welder 1 Equip. Oper. (light) 1 Welder, Gas Engine, 300 amp $66.55 64.55 59.70 $532.40 516.40 477.60 147.09 $102.50 99.40 88.85 24 L.H., Daily Totals $1673.49 Crew E-2 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 4 Struc. Steel Workers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Lattice Boom Crane, 90 Ton $66.55 64.55 66.30 56.40 $532.40 2065.60 530.40 451.20 2689.54 $102.50 99.40 98.65 83.90 56 L.H., Daily Totals $6269.14 Crew E-3 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 1 Struc. Steel Worker 1 Welder 1 Welder, Gas Engine, 300 amp $66.55 64.55 64.55 $532.40 516.40 516.40 147.09 $102.50 99.40 99.40 24 L.H., Daily Totals 778 $1712.29 Cost Per Labor-Hour Bare Costs Incl. O&P $2072.40 1681.20 $52.08 $78.20 $3753.60 $52.08 $78.20 Daily Bare Costs Incl. O&P Daily $714.80 690.80 560.40 789.20 701.79 $57.49 $86.10 19.94 21.93 $3456.99 $77.42 $108.03 Bare Costs Incl. O&P $714.80 690.80 560.40 $54.55 $81.92 $1966.00 $54.55 $81.92 Daily Bare Costs Incl. O&P $714.80 690.80 1120.80 $52.58 $78.95 $2526.40 $52.58 Daily Bare Costs Incl. Subs O&P Crew E-3A Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 1 Struc. Steel Worker 1 Welder 1 Welder, Gas Engine, 300 amp 1 Telescoping Boom Lift, to 40’ $66.55 64.55 64.55 $532.40 516.40 516.40 147.09 345.57 $102.50 99.40 99.40 24 L.H., Daily Totals $2057.86 Crew E-4 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 3 Struc. Steel Workers 1 Welder, Gas Engine, 300 amp $66.55 64.55 $532.40 1549.20 147.09 $102.50 99.40 32 L.H., Daily Totals $2228.69 Crew E-5 Hr. Daily Hr. 2 Struc. Steel Foremen (outside) 5 Struc. Steel Workers 1 Equip. Oper. (crane) 1 Welder 1 Equip. Oper. (oiler) 1 Lattice Boom Crane, 90 Ton 1 Welder, Gas Engine, 300 amp $66.55 64.55 66.30 64.55 56.40 $1064.80 2582.00 530.40 516.40 451.20 2689.54 147.09 $102.50 99.40 98.65 99.40 83.90 80 L.H., Daily Totals $7981.43 Incl. O&P $714.80 690.80 1120.80 698.00 789.20 701.79 $55.87 $83.62 13.29 14.62 $4715.39 $69.16 $98.24 Daily Bare Costs Incl. O&P $2072.40 560.40 $54.79 $82.28 $2632.80 $54.79 $82.28 Daily Bare Costs Incl. O&P $820.00 795.20 710.80 161.80 $63.60 $96.92 6.13 6.74 $2487.80 $69.73 $103.66 Daily Bare Costs Incl. O&P $820.00 3180.80 789.20 671.20 2958.49 $63.92 $97.52 48.03 52.83 $8419.69 $111.95 $150.35 Daily Bare Costs Incl. O&P $820.00 795.20 795.20 161.80 $65.22 $100.43 6.13 6.74 $2572.20 $71.35 $107.17 Crew E-6 Hr. Daily Hr. 3 Struc. Steel Foremen (outside) 9 Struc. Steel Workers 1 Equip. Oper. (crane) 1 Welder 1 Equip. Oper. (oiler) 1 Equip. Oper. (light) 1 Lattice Boom Crane, 90 Ton 1 Welder, Gas Engine, 300 amp 1 Air Compressor, 160 cfm 2 Impact Wrenches $66.55 64.55 66.30 64.55 56.40 59.70 $1597.20 4647.60 530.40 516.40 451.20 477.60 2689.54 147.09 244.12 92.56 $102.50 99.40 98.65 99.40 83.90 88.85 128 L.H., Daily Totals $11393.71 Crew E-7 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 4 Struc. Steel Workers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Welder Foreman (outside) 2 Welders 1 Lattice Boom Crane, 90 Ton 2 Welder, Gas Engine, 300 amp $66.55 64.55 66.30 56.40 66.55 64.55 $532.40 2065.60 530.40 451.20 532.40 1032.80 2689.54 294.18 $102.50 99.40 98.65 83.90 102.50 99.40 80 L.H., Daily Totals $8128.52 Crew E-8 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 4 Struc. Steel Workers 1 Welder Foreman (outside) 4 Welders 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Equip. Oper. (light) 1 Lattice Boom Crane, 90 Ton 4 Welder, Gas Engine, 300 amp $66.55 64.55 66.55 64.55 66.30 56.40 59.70 $532.40 2065.60 532.40 2065.60 530.40 451.20 477.60 2689.54 588.36 $102.50 99.40 102.50 99.40 98.65 83.90 88.85 104 L.H., Daily Totals $9933.10 Cost Per Labor-Hour Bare Costs Incl. O&P $820.00 795.20 795.20 161.80 380.13 $65.22 $100.43 20.53 22.58 $2952.33 $85.74 $123.01 Daily Bare Costs Incl. O&P $820.00 2385.60 161.80 $65.05 $100.18 4.60 5.06 $3367.40 $69.65 $105.23 Daily Bare Costs Incl. O&P $1640.00 3976.00 789.20 795.20 671.20 2958.49 161.80 $64.31 $98.39 35.46 39.00 $10991.89 $99.77 $137.40 Daily Bare Costs Incl. O&P $2460.00 7156.80 789.20 795.20 671.20 710.80 2958.49 161.80 268.53 101.82 $64.22 $98.31 24.79 27.27 $16073.84 $89.01 $125.58 Daily Bare Costs Incl. O&P $820.00 3180.80 789.20 671.20 820.00 1590.40 2958.49 323.60 $64.31 $98.39 37.30 41.03 $11153.69 $101.61 $139.42 Daily Bare Costs Incl. O&P $820.00 3180.80 820.00 3180.80 789.20 671.20 710.80 2958.49 647.20 $63.99 $97.82 31.52 34.67 $13778.49 $95.51 $132.49 Daily $78.95 Bare Costs Daily Crew No. Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Bare Costs Incl. Subs O&P Crew E-9 Hr. Daily Hr. 2 Struc. Steel Foremen (outside) 5 Struc. Steel Workers 1 Welder Foreman (outside) 5 Welders 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Equip. Oper. (light) 1 Lattice Boom Crane, 90 Ton 5 Welder, Gas Engine, 300 amp $66.55 64.55 66.55 64.55 66.30 56.40 59.70 $1064.80 2582.00 532.40 2582.00 530.40 451.20 477.60 2689.54 735.45 $102.50 99.40 102.50 99.40 98.65 83.90 88.85 128 L.H., Daily Totals $11645.39 Crew E-10 Hr. Daily Hr. 1 Welder Foreman (outside) 1 Welder 1 Welder, Gas Engine, 300 amp 1 Flatbed Truck, Gas, 3 Ton $66.55 64.55 $532.40 516.40 147.09 391.02 $102.50 99.40 16 L.H., Daily Totals $1586.91 Crew E-11 Hr. Daily Hr. 2 Painters, Struc. Steel 1 Building Laborer 1 Equip. Oper. (light) 1 Air Compressor, 250 cfm 1 Sandblaster, Portable, 3 C.F. 1 Set Sand Blasting Accessories $51.20 47.25 59.70 $819.20 378.00 477.60 196.28 84.26 17.14 $81.75 70.35 88.85 32 L.H., Daily Totals $1972.48 Crew E-11A Hr. Daily Hr. 2 Painters, Struc. Steel 1 Building Laborer 1 Equip. Oper. (light) 1 Air Compressor, 250 cfm 1 Sandblaster, Portable, 3 C.F. 1 Set Sand Blasting Accessories 1 Telescoping Boom Lift, to 60’ $51.20 47.25 59.70 $819.20 378.00 477.60 196.28 84.26 17.14 385.68 $81.75 70.35 88.85 32 L.H., Daily Totals $2358.16 Crew E-11B Hr. Daily Hr. 2 Painters, Struc. Steel 1 Building Laborer 2 Paint Sprayer, 8 C.F.M. 1 Telescoping Boom Lift, to 60’ $51.20 47.25 $819.20 378.00 104.28 385.68 $81.75 70.35 24 L.H., Daily Totals $1687.16 Crew E-12 Hr. Daily Hr. 1 Welder Foreman (outside) 1 Equip. Oper. (light) 1 Welder, Gas Engine, 300 amp $66.55 59.70 $532.40 477.60 147.09 $102.50 88.85 16 L.H., Daily Totals $1157.09 Crew E-13 Hr. Daily Hr. 1 Welder Foreman (outside) .5 Equip. Oper. (light) 1 Welder, Gas Engine, 300 amp $66.55 59.70 $532.40 238.80 147.09 $102.50 88.85 12 L.H., Daily Totals $918.29 Crew E-14 Hr. Daily Hr. 1 Welder Foreman (outside) 1 Welder, Gas Engine, 300 amp $66.55 $532.40 147.09 $102.50 8 L.H., Daily Totals $679.49 Cost Per Labor-Hour Bare Costs Incl. O&P $1640.00 3976.00 820.00 3976.00 789.20 671.20 710.80 2958.49 809.00 $64.22 $98.31 26.76 29.43 $16350.69 $90.98 $127.74 Daily Bare Costs Incl. O&P $820.00 795.20 161.80 430.12 $65.55 $100.95 33.63 37.00 $2207.12 $99.18 $137.95 Daily Bare Costs Incl. O&P $1308.00 562.80 710.80 215.91 92.69 18.85 $52.34 $80.67 9.30 10.23 $2909.05 $61.64 $90.91 Daily Bare Costs Incl. O&P $1308.00 562.80 710.80 215.91 92.69 18.85 424.25 $52.34 $80.67 21.36 23.49 $3333.30 $73.69 $104.17 Daily Bare Costs Incl. O&P $1308.00 562.80 114.71 424.25 $49.88 $77.95 20.41 22.46 $2409.76 $70.30 $100.41 Daily Bare Costs Incl. O&P $820.00 710.80 161.80 $63.13 $95.67 9.19 10.11 $1692.60 $72.32 $105.79 Daily Bare Costs Incl. O&P $820.00 355.40 161.80 $64.27 $97.95 12.26 13.48 $1337.20 $76.52 $111.43 Daily Bare Costs Incl. O&P $820.00 161.80 $66.55 18.39 $102.50 20.22 $981.80 $84.94 $122.72 Daily Crew No. Bare Costs Incl. Subs O&P Crew E-16 Hr. Daily Hr. 1 Welder Foreman (outside) 1 Welder 1 Welder, Gas Engine, 300 amp $66.55 64.55 $532.40 516.40 147.09 $102.50 99.40 16 L.H., Daily Totals $1195.89 Crew E-17 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 1 Structural Steel Worker $66.55 64.55 $532.40 516.40 $102.50 99.40 16 L.H., Daily Totals $1048.80 Crew E-18 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 3 Structural Steel Workers 1 Equipment Operator (med.) 1 Lattice Boom Crane, 20 Ton $66.55 64.55 63.05 $532.40 1549.20 504.40 868.10 $102.50 99.40 93.80 40 L.H., Daily Totals $3454.10 Crew E-19 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 1 Structural Steel Worker 1 Equip. Oper. (light) 1 Lattice Boom Crane, 20 Ton $66.55 64.55 59.70 $532.40 516.40 477.60 868.10 $102.50 99.40 88.85 24 L.H., Daily Totals $2394.50 Crew E-20 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 5 Structural Steel Workers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Lattice Boom Crane, 40 Ton $66.55 64.55 66.30 56.40 $532.40 2582.00 530.40 451.20 2371.83 $102.50 99.40 98.65 83.90 64 L.H., Daily Totals $6467.83 Crew E-22 Hr. Daily Hr. 1 Skilled Worker Foreman (out) 2 Skilled Workers $63.25 61.25 $506.00 980.00 $95.00 92.00 24 L.H., Daily Totals Crew E-24 3 Structural Steel Workers 1 Equipment Operator (med.) 1 Hyd. Crane, 25 Ton $1486.00 Hr. Daily Hr. $64.55 63.05 $1549.20 504.40 2273.31 $99.40 93.80 32 L.H., Daily Totals Crew E-25 1 Welder Foreman (outside) 1 Cutting Torch $4326.91 Hr. Daily Hr. $66.55 $532.40 14.24 $102.50 8 L.H., Daily Totals Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 1 Struc. Steel Worker 1 Welder .25 Electrician .25 Plumber 1 Welder, Gas Engine, 300 amp $66.55 64.55 64.55 67.35 72.05 $532.40 516.40 516.40 134.70 144.10 147.09 $102.50 99.40 99.40 100.10 107.45 28 L.H., Daily Totals Bare Costs Incl. O&P $820.00 795.20 161.80 $65.55 $100.95 9.19 10.11 $1777.00 $74.74 $111.06 Daily Bare Costs Incl. O&P $820.00 795.20 $65.55 $100.95 $1615.20 $65.55 $100.95 Daily Bare Costs Incl. O&P $820.00 2385.60 750.40 954.91 $64.65 $98.90 21.70 23.87 $4910.91 $86.35 $122.77 Daily Bare Costs Incl. O&P $820.00 795.20 710.80 954.91 $63.60 $96.92 36.17 39.79 $3280.91 $99.77 $136.70 Daily Bare Costs Incl. O&P $820.00 3976.00 789.20 671.20 2609.01 $64.00 $97.76 37.06 40.77 $8865.41 $101.06 $138.52 Daily Bare Costs Incl. O&P $760.00 1472.00 $61.92 $93.00 $2232.00 $61.92 $93.00 Daily Bare Costs Incl. O&P $2385.60 750.40 2500.64 $64.17 $98.00 71.04 78.14 $5636.64 $135.22 $176.15 Daily Bare Costs Incl. O&P $820.00 15.66 $66.55 1.78 $102.50 1.96 $835.66 $68.33 $104.46 Daily Bare Costs Incl. O&P $820.00 795.20 795.20 200.20 214.90 161.80 $65.86 $100.91 5.25 5.78 $2987.30 $71.11 $106.69 Daily $546.64 Crew E-26 $1991.09 Cost Per Labor-Hour Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 779 Crews - Standard Crew No. Bare Costs Incl. Subs O&P Crew E-27 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 5 Struc. Steel Workers 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 12 Ton 1 Hyd. Crane, 80 Ton $66.55 64.55 66.30 56.40 $532.40 2582.00 530.40 451.20 2150.65 2641.70 $102.50 99.40 98.65 83.90 64 L.H., Daily Totals Crew F-3 4 Carpenters 1 Equip. Oper. (crane) 1 Hyd. Crane, 12 Ton $8888.35 Hr. Daily Hr. $58.60 66.30 $1875.20 530.40 2150.65 $87.25 98.65 40 L.H., Daily Totals Crew F-4 4 Carpenters 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 55 Ton $4556.25 Hr. Daily Hr. $58.60 66.30 56.40 $1875.20 530.40 451.20 2461.06 $87.25 98.65 83.90 48 L.H., Daily Totals Crew F-5 1 Carpenter Foreman (outside) 3 Carpenters $5317.86 Hr. Daily Hr. $60.60 58.60 $484.80 1406.40 $90.20 87.25 32 L.H., Daily Totals Crew F-6 2 Carpenters 2 Building Laborers 1 Equip. Oper. (crane) 1 Hyd. Crane, 12 Ton $1891.20 Hr. Daily Hr. $58.60 47.25 66.30 $937.60 756.00 530.40 2150.65 $87.25 70.35 98.65 40 L.H., Daily Totals Crew F-7 2 Carpenters 2 Building Laborers $4374.65 Hr. Daily Hr. $58.60 47.25 $937.60 756.00 $87.25 70.35 32 L.H., Daily Totals Crew G-1 1 Roofer Foreman (outside) 4 Roofers Composition 2 Roofer Helpers 1 Application Equipment 1 Tar Kettle/Pot 1 Crew Truck $1693.60 Hr. Daily Hr. $53.80 51.80 38.85 $430.40 1657.60 621.60 189.41 220.65 183.83 $87.20 83.95 62.95 56 L.H., Daily Totals Crew G-2 1 Plasterer 1 Plasterer Helper 1 Building Laborer 1 Grout Pump, 50 C.F./hr. 24 L.H., Daily Totals $3303.49 Hr. Daily Hr. $53.35 47.55 47.25 $426.80 380.40 378.00 158.45 $79.30 70.65 70.35 $1343.65 Cost Per Labor-Hour Crew No. Bare Costs Incl. O&P $820.00 3976.00 789.20 671.20 2365.72 2905.87 $64.00 $97.76 74.88 82.37 $11527.99 $138.88 $180.12 Daily Bare Costs Incl. O&P $2792.00 789.20 2365.72 $60.14 $89.53 53.77 59.14 $5946.92 $113.91 $148.67 Daily Bare Costs Incl. O&P $2792.00 789.20 671.20 2707.17 $59.52 $88.59 51.27 56.40 $6959.57 $110.79 $144.99 Daily Bare Costs Incl. O&P $721.60 2094.00 $59.10 $87.99 $2815.60 $59.10 $87.99 Daily Bare Costs Incl. O&P $1396.00 1125.60 789.20 2365.72 $55.60 $82.77 53.77 59.14 $5676.52 $109.37 $141.91 Daily Bare Costs Incl. O&P $1396.00 1125.60 $52.92 $78.80 1 Carpenter 1 Small Compressor, Electric 1 Pneumatic Nailer $2521.60 $52.92 $78.80 8 L.H., Daily Totals Daily Bare Costs Incl. O&P $697.60 2686.40 1007.20 208.35 242.72 202.21 $48.39 $78.41 10.61 11.67 $5044.48 $58.99 $90.08 2 Glaziers 1 Building Laborer Bare Costs Incl. O&P 24 L.H., Daily Totals Daily $634.40 565.20 562.80 174.29 $49.38 $73.43 6.60 7.26 $1936.69 $55.99 $80.70 Daily Crew G-2A 1 Roofer Composition 1 Roofer Helper 1 Building Laborer 1 Foam Spray Rig, Trailer-Mtd. 1 Pickup Truck, 3/4 Ton Crew G-3 2 Sheet Metal Workers 2 Building Laborers Daily Hr. $51.80 38.85 47.25 $414.40 310.80 378.00 581.75 122.56 $83.95 62.95 70.35 $1807.51 Hr. Daily Hr. $70.15 47.25 $1122.40 756.00 $105.70 70.35 32 L.H., Daily Totals Crew G-4 1 Labor Foreman (outside) 2 Building Laborers 1 Flatbed Truck, Gas, 1.5 Ton 1 Air Compressor, 160 cfm $1878.40 Hr. Daily Hr. $49.25 47.25 $394.00 756.00 361.95 244.12 $73.30 70.35 24 L.H., Daily Totals Crew G-5 1 Roofer Foreman (outside) 2 Roofers Composition 2 Roofer Helpers 1 Application Equipment $1756.07 Hr. Daily Hr. $53.80 51.80 38.85 $430.40 828.80 621.60 189.41 $87.20 83.95 62.95 40 L.H., Daily Totals Crew G-6A 2 Roofers Composition 1 Small Compressor, Electric 2 Pneumatic Nailers $2070.21 Hr. Daily Hr. $51.80 $828.80 32.29 38.40 $83.95 16 L.H., Daily Totals Crew G-7 Crew H-1 2 Glaziers 2 Struc. Steel Workers $899.49 Hr. Daily Hr. $58.60 $468.80 32.29 19.20 $87.25 Hr. Daily Hr. $56.05 64.55 $896.80 1032.80 $83.30 99.40 Crew H-3 1 Glazier 1 Helper $1929.60 Hr. Daily Hr. $56.05 47.25 $896.80 378.00 $83.30 70.35 $1274.80 Hr. Daily Hr. $56.05 44.95 $448.40 359.60 $83.30 67.95 16 L.H., Daily Totals 1 Carpenter 1 Carpenter Helper .5 Electrician 20 L.H., Daily Totals $808.00 Hr. Daily Hr. $58.60 44.95 67.35 $468.80 359.60 269.40 $87.25 67.95 100.10 $1097.80 Cost Per Labor-Hour Bare Costs Incl. O&P $671.60 503.60 562.80 639.92 134.82 $45.97 $72.42 29.35 32.28 $2512.74 $75.31 $104.70 Daily Bare Costs Incl. O&P $1691.20 1125.60 $58.70 $88.03 $2816.80 $58.70 $88.03 Daily Bare Costs Incl. O&P $586.40 1125.60 398.14 268.53 $47.92 $71.33 25.25 27.78 $2378.68 $73.17 $99.11 Daily Bare Costs Incl. O&P $697.60 1343.20 1007.20 208.35 $47.02 $76.20 4.74 5.21 $3256.35 $51.76 $81.41 Daily Bare Costs Incl. O&P $1343.20 35.52 42.24 $51.80 $83.95 4.42 4.86 $1420.96 $56.22 $88.81 Daily Bare Costs Incl. O&P $698.00 35.52 21.12 $58.60 $87.25 6.44 7.08 $754.64 $65.04 $94.33 Daily Bare Costs Incl. O&P $1332.80 1590.40 $60.30 $91.35 $2923.20 $60.30 $91.35 Daily Bare Costs Incl. O&P $1332.80 562.80 $53.12 $78.98 $1895.60 $53.12 $78.98 Daily Bare Costs Incl. O&P $666.40 543.60 $50.50 $75.63 $1210.00 $50.50 $75.63 Daily Bare Costs Incl. O&P $698.00 543.60 400.40 $54.89 $82.10 $1642.00 $54.89 $82.10 Daily $520.29 32 L.H., Daily Totals Crew H-2 Incl. Subs O&P Hr. 24 L.H., Daily Totals Crew H-4 780 Bare Costs Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew J-1 3 Plasterers 2 Plasterer Helpers 1 Mixing Machine, 6 C.F. Bare Costs Hr. Daily Hr. $53.35 47.55 $1280.40 760.80 116.18 $79.30 70.65 40 L.H., Daily Totals Crew J-2 3 Plasterers 2 Plasterer Helpers 1 Lather 1 Mixing Machine, 6 C.F. $2157.38 Hr. Daily Hr. $53.35 47.55 58.45 $1280.40 760.80 467.60 116.18 $79.30 70.65 85.30 48 L.H., Daily Totals Crew J-3 1 Terrazzo Worker 1 Terrazzo Helper 1 Floor Grinder, 22⬙ Path 1 Terrazzo Mixer $2624.98 Hr. Daily Hr. $55.25 46.80 $442.00 374.40 109.91 144.05 $80.70 68.35 16 L.H., Daily Totals Crew J-4 2 Cement Finishers 1 Laborer 1 Floor Grinder, 22⬙ Path 1 Floor Edger, 7⬙ Path 1 Vacuum Pick-Up System $1070.36 Hr. Daily Hr. $55.00 47.25 $880.00 378.00 109.91 52.63 73.53 $80.45 70.35 24 L.H., Daily Totals Crew J-4A 2 Cement Finishers 2 Laborers 1 Floor Grinder, 22⬙ Path 1 Floor Edger, 7⬙ Path 1 Vacuum Pick-Up System 1 Floor Auto Scrubber $1494.07 Hr. Daily Hr. $55.00 47.25 $880.00 756.00 109.91 52.63 73.53 195.20 $80.45 70.35 32 L.H., Daily Totals Crew J-4B 1 Laborer 1 Floor Auto Scrubber Incl. Subs O&P $2067.27 Hr. Daily Hr. $47.25 $378.00 195.20 $70.35 8 L.H., Daily Totals $573.20 Crew J-6 Hr. Daily Hr. 2 Painters 1 Building Laborer 1 Equip. Oper. (light) 1 Air Compressor, 250 cfm 1 Sandblaster, Portable, 3 C.F. 1 Set Sand Blasting Accessories $49.65 47.25 59.70 $794.40 378.00 477.60 196.28 84.26 17.14 $73.55 70.35 88.85 32 L.H., Daily Totals Crew J-7 2 Painters 1 Floor Belt Sander 1 Floor Sanding Edger 16 L.H., Daily Totals $1947.68 Hr. $49.65 Daily $794.40 49.75 26.35 $870.50 Hr. $73.55 Cost Per Labor-Hour Crew No. Bare Costs Incl. O&P $1903.20 1130.40 127.80 $51.03 $75.84 2.90 3.19 $3161.40 $53.93 $79.03 Daily Bare Costs Incl. O&P $1903.20 1130.40 682.40 127.80 $52.27 $77.42 2.42 2.66 $3843.80 $54.69 $80.08 Daily Bare Costs Incl. O&P $645.60 546.80 120.90 158.46 $51.02 $74.53 15.87 17.46 $1471.76 $66.90 $91.98 Daily Bare Costs Incl. O&P 1 Carpenter 1 Carpenter Helper $1287.20 562.80 120.90 57.89 80.88 $52.42 $77.08 16 L.H., Daily Totals 9.84 10.82 $2109.68 $62.25 $87.90 Daily Bare Costs Incl. O&P $1287.20 1125.60 120.90 57.89 80.88 214.72 $51.13 $75.40 13.48 14.82 $2887.20 $64.60 $90.22 Daily Bare Costs Incl. O&P $562.80 214.72 $47.25 24.40 $70.35 26.84 $777.52 $71.65 $97.19 Daily Bare Costs Incl. O&P $1176.80 562.80 710.80 215.91 92.69 18.85 $51.56 $76.58 9.30 10.23 $2777.85 $60.87 $86.81 Daily Bare Costs Incl. O&P Daily Crew K-1 1 Carpenter 1 Truck Driver (light) 1 Flatbed Truck, Gas, 3 Ton Bare Costs Hr. Daily Hr. $58.60 52.90 $468.80 423.20 391.02 $87.25 79.00 16 L.H., Daily Totals $1283.02 Crew K-2 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 1 Struc. Steel Worker 1 Truck Driver (light) 1 Flatbed Truck, Gas, 3 Ton $66.55 64.55 52.90 $532.40 516.40 423.20 391.02 $102.50 99.40 79.00 24 L.H., Daily Totals Crew L-1 1 Electrician 1 Plumber $1863.02 Hr. Daily Hr. $67.35 72.05 $538.80 576.40 $100.10 107.45 16 L.H., Daily Totals Crew L-2 Crew L-3 1 Carpenter .5 Electrician .5 Sheet Metal Worker $1115.20 Hr. Daily Hr. $58.60 44.95 $468.80 359.60 $87.25 67.95 $828.40 Hr. Daily Hr. $58.60 67.35 70.15 $468.80 269.40 280.60 $87.25 100.10 105.70 16 L.H., Daily Totals Crew L-3A 1 Carpenter Foreman (outside) .5 Sheet Metal Worker $1018.80 Hr. Daily Hr. $60.60 70.15 $484.80 280.60 $90.20 105.70 12 L.H., Daily Totals Crew L-4 2 Skilled Workers 1 Helper $765.40 Hr. Daily Hr. $61.25 44.95 $980.00 359.60 $92.00 67.95 24 L.H., Daily Totals $1339.60 Crew L-5 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 5 Struc. Steel Workers 1 Equip. Oper. (crane) 1 Hyd. Crane, 25 Ton $66.55 64.55 66.30 $532.40 2582.00 530.40 2273.31 $102.50 99.40 98.65 56 L.H., Daily Totals $1176.80 54.73 28.98 $49.65 $73.55 4.76 5.23 $1260.51 $54.41 $78.78 Incl. Subs O&P $5918.11 Crew L-5A Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 2 Structural Steel Workers 1 Equip. Oper. (crane) 1 S.P. Crane, 4x4, 25 Ton $66.55 64.55 66.30 $532.40 1032.80 530.40 927.07 $102.50 99.40 98.65 32 L.H., Daily Totals $3022.67 Cost Per Labor-Hour Bare Costs Incl. O&P $698.00 632.00 430.12 $55.75 $83.13 24.44 26.88 $1760.12 $80.19 $110.01 Daily Bare Costs Incl. O&P $820.00 795.20 632.00 430.12 $61.33 $93.63 16.29 17.92 $2677.32 $77.63 $111.56 Daily Bare Costs Incl. O&P $800.80 859.60 $69.70 $103.78 $1660.40 $69.70 $103.78 Daily Bare Costs Incl. O&P $698.00 543.60 $51.77 $77.60 $1241.60 $51.77 $77.60 Daily Bare Costs Incl. O&P $698.00 400.40 422.80 $63.67 $95.08 $1521.20 $63.67 $95.08 Daily Bare Costs Incl. O&P $721.60 422.80 $63.78 $95.37 $1144.40 $63.78 $95.37 Daily Bare Costs Incl. O&P $1472.00 543.60 $55.82 $83.98 $2015.60 $55.82 $83.98 Daily Bare Costs Incl. O&P $820.00 3976.00 789.20 2500.64 $65.09 $99.74 40.59 44.65 $8085.84 $105.68 $144.39 Daily Bare Costs Incl. O&P $820.00 1590.40 789.20 1019.78 $65.49 $99.99 28.97 31.87 $4219.38 $94.46 $131.86 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 781 Crews - Standard Crew No. Bare Costs Incl. Subs O&P Crew L-5B Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 2 Structural Steel Workers 2 Electricians 2 Steamfitters/Pipefitters 1 Equip. Oper. (crane) 1 Equip. Oper. (oiler) 1 Hyd. Crane, 80 Ton $66.55 64.55 67.35 72.55 66.30 56.40 $532.40 1032.80 1077.60 1160.80 530.40 451.20 2641.70 $102.50 99.40 100.10 108.20 98.65 83.90 72 L.H., Daily Totals Crew L-6 1 Plumber .5 Electrician $7426.90 Hr. Daily Hr. $72.05 67.35 $576.40 269.40 $107.45 100.10 12 L.H., Daily Totals Crew L-7 2 Carpenters 1 Building Laborer .5 Electrician $845.80 Hr. Daily Hr. $58.60 47.25 67.35 $937.60 378.00 269.40 $87.25 70.35 100.10 28 L.H., Daily Totals Crew L-8 2 Carpenters .5 Plumber $1585.00 Hr. Daily Hr. $58.60 72.05 $937.60 288.20 $87.25 107.45 20 L.H., Daily Totals Crew L-9 1 Labor Foreman (inside) 2 Building Laborers 1 Struc. Steel Worker .5 Electrician $1225.80 Hr. Daily Hr. $47.75 47.25 64.55 67.35 $382.00 756.00 516.40 269.40 $71.10 70.35 99.40 100.10 36 L.H., Daily Totals $1923.80 Crew L-10 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 1 Structural Steel Worker 1 Equip. Oper. (crane) 1 Hyd. Crane, 12 Ton $66.55 64.55 66.30 $532.40 516.40 530.40 2150.65 $102.50 99.40 98.65 24 L.H., Daily Totals Crew L-11 2 Wreckers 1 Equip. Oper. (crane) 1 Equip. Oper. (light) 1 Hyd. Excavator, 2.5 C.Y. 1 Loader, Skid Steer, 78 H.P. $3729.85 Hr. Daily Hr. $47.25 66.30 59.70 $756.00 530.40 477.60 1683.69 429.91 $71.35 98.65 88.85 32 L.H., Daily Totals Crew M-1 3 Elevator Constructors 1 Elevator Apprentice 5 Hand Tools 32 L.H., Daily Totals $3877.60 Hr. Daily Hr. $96.60 77.30 $2318.40 618.40 344.60 $143.00 114.45 $3281.40 Cost Per Labor-Hour Crew No. Bare Costs Bare Costs Incl. O&P $820.00 1590.40 1601.60 1731.20 789.20 671.20 2905.87 $66.46 $100.05 36.69 40.36 $10109.47 $103.15 $140.41 Daily Bare Costs Incl. O&P $859.60 400.40 $70.48 $105.00 $1260.00 $70.48 $105.00 Daily Bare Costs Incl. O&P $1396.00 562.80 400.40 $56.61 $84.26 $2359.20 $56.61 $84.26 Crew Q-1 Daily Bare Costs Incl. O&P 1 Plumber 1 Plumber Apprentice $1396.00 429.80 $61.29 $91.29 $1825.80 $61.29 $91.29 Crew Q-1A Hr. Daily Hr. Daily Bare Costs Incl. O&P .25 Plumber Foreman (outside) 1 Plumber $74.05 72.05 $148.10 576.40 $110.40 107.45 $568.80 1125.60 795.20 400.40 $53.44 $80.28 $2890.00 $53.44 $80.28 Daily Bare Costs Incl. O&P $820.00 795.20 789.20 2365.72 $65.80 $100.18 89.61 98.57 $4770.11 $155.41 $198.75 Daily Bare Costs Incl. O&P $1141.60 789.20 710.80 1852.06 472.90 $55.13 $82.55 66.05 72.66 $4966.56 $121.18 $155.21 Daily Bare Costs Incl. O&P $3432.00 915.60 379.06 $91.78 $135.86 10.77 11.85 $4726.66 $102.54 $147.71 Daily Crew M-3 Hr. Daily Hr. 1 Electrician Foreman (outside) 1 Common Laborer .25 Equipment Operator (med.) 1 Elevator Constructor 1 Elevator Apprentice .25 S.P. Crane, 4x4, 20 Ton $69.35 47.25 63.05 96.60 77.30 $554.80 378.00 126.10 772.80 618.40 190.24 $103.05 70.35 93.80 143.00 114.45 34 L.H., Daily Totals $2640.34 Crew M-4 Hr. Daily Hr. 1 Electrician Foreman (outside) 1 Common Laborer .25 Equipment Operator, Crane .25 Equip. Oper. (oiler) 1 Elevator Constructor 1 Elevator Apprentice .25 S.P. Crane, 4x4, 40 Ton $69.35 47.25 66.30 56.40 96.60 77.30 $554.80 378.00 132.60 112.80 772.80 618.40 284.79 $103.05 70.35 98.65 83.90 143.00 114.45 36 L.H., Daily Totals $2854.18 Hr. Daily Hr. $72.05 57.65 $576.40 461.20 $107.45 85.95 16 L.H., Daily Totals $1037.60 10 L.H., Daily Totals Crew Q-1C 1 Plumber 1 Plumber Apprentice 1 Equip. Oper. (medium) 1 Trencher, Chain Type, 8’ D $724.50 Hr. Daily Hr. $72.05 57.65 63.05 $576.40 461.20 504.40 2079.03 $107.45 85.95 93.80 24 L.H., Daily Totals Crew Q-2 2 Plumbers 1 Plumber Apprentice $3621.03 Hr. Daily Hr. $72.05 57.65 $1152.80 461.20 $107.45 85.95 24 L.H., Daily Totals Crew Q-3 1 Plumber Foreman (inside) 2 Plumbers 1 Plumber Apprentice $1614.00 Hr. Daily Hr. $72.55 72.05 57.65 $580.40 1152.80 461.20 $108.20 107.45 85.95 32 L.H., Daily Totals Crew Q-4 1 Plumber Foreman (inside) 1 Plumber 1 Welder (plumber) 1 Plumber Apprentice 1 Welder, Electric, 300 amp $2194.40 Hr. Daily Hr. $72.55 72.05 72.05 57.65 $580.40 576.40 576.40 461.20 64.17 $108.20 107.45 107.45 85.95 32 L.H., Daily Totals Crew Q-5 1 Steamfitter 1 Steamfitter Apprentice 16 L.H., Daily Totals 782 Incl. Subs O&P $2258.57 Hr. Daily Hr. $72.55 58.05 $580.40 464.40 $108.20 86.55 $1044.80 Cost Per Labor-Hour Bare Costs Incl. O&P $824.40 562.80 187.60 1144.00 915.60 209.27 $72.06 $106.89 5.60 6.15 $3843.67 $77.66 $113.05 Daily Bare Costs Incl. O&P $824.40 562.80 197.30 167.80 1144.00 915.60 313.26 $71.37 $105.89 7.91 8.70 $4125.16 $79.28 $114.59 Daily Bare Costs Incl. O&P $859.60 687.60 $64.85 $96.70 $1547.20 $64.85 $96.70 Daily Bare Costs Incl. O&P $220.80 859.60 $72.45 $108.04 $1080.40 $72.45 $108.04 Daily Bare Costs Incl. O&P $859.60 687.60 750.40 2286.93 $64.25 $95.73 86.63 95.29 $4584.53 $150.88 $191.02 Daily Bare Costs Incl. O&P $1719.20 687.60 $67.25 $100.28 $2406.80 $67.25 $100.28 Daily Bare Costs Incl. O&P $865.60 1719.20 687.60 $68.58 $102.26 $3272.40 $68.58 $102.26 Daily Bare Costs Incl. O&P $865.60 859.60 859.60 687.60 70.59 $68.58 $102.26 2.01 2.21 $3342.99 $70.58 $104.47 Daily Bare Costs Incl. O&P $865.60 692.40 $65.30 $97.38 $1558.00 $65.30 $97.38 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew Q-6 2 Steamfitters 1 Steamfitter Apprentice Bare Costs Hr. Daily Hr. $72.55 58.05 $1160.80 464.40 $108.20 86.55 24 L.H., Daily Totals Crew Q-7 1 Steamfitter Foreman (inside) 2 Steamfitters 1 Steamfitter Apprentice $1625.20 Hr. Daily Hr. $73.05 72.55 58.05 $584.40 1160.80 464.40 $108.95 108.20 86.55 32 L.H., Daily Totals Crew Q-8 1 Steamfitter Foreman (inside) 1 Steamfitter 1 Welder (steamfitter) 1 Steamfitter Apprentice 1 Welder, Electric, 300 amp $2209.60 Hr. Daily Hr. $73.05 72.55 72.55 58.05 $584.40 580.40 580.40 464.40 64.17 $108.95 108.20 108.20 86.55 32 L.H., Daily Totals Crew Q-9 1 Sheet Metal Worker 1 Sheet Metal Apprentice $2273.77 Hr. Daily Hr. $70.15 56.10 $561.20 448.80 $105.70 84.50 16 L.H., Daily Totals Crew Q-10 2 Sheet Metal Workers 1 Sheet Metal Apprentice Incl. Subs O&P $1010.00 Hr. Daily Hr. $70.15 56.10 $1122.40 448.80 $105.70 84.50 24 L.H., Daily Totals $1571.20 Crew Q-11 Hr. Daily Hr. 1 Sheet Metal Foreman (inside) 2 Sheet Metal Workers 1 Sheet Metal Apprentice $70.65 70.15 56.10 $565.20 1122.40 448.80 $106.45 105.70 84.50 32 L.H., Daily Totals Crew Q-12 1 Sprinkler Installer 1 Sprinkler Apprentice $2136.40 Hr. Daily Hr. $70.80 56.65 $566.40 453.20 $105.70 84.55 16 L.H., Daily Totals Crew Q-13 1 Sprinkler Foreman (inside) 2 Sprinkler Installers 1 Sprinkler Apprentice $1019.60 Hr. Daily Hr. $71.30 70.80 56.65 $570.40 1132.80 453.20 $106.45 105.70 84.55 32 L.H., Daily Totals Crew Q-14 1 Asbestos Worker 1 Asbestos Apprentice $2156.40 Hr. Daily Hr. $65.25 52.20 $522.00 417.60 $99.80 79.85 16 L.H., Daily Totals Crew Q-15 1 Plumber 1 Plumber Apprentice 1 Welder, Electric, 300 amp 16 L.H., Daily Totals $939.60 Hr. Daily Hr. $72.05 57.65 $576.40 461.20 64.17 $107.45 85.95 $1101.77 Cost Per Labor-Hour Bare Costs Incl. O&P $1731.20 692.40 $67.72 $100.98 $2423.60 $67.72 $100.98 Daily Bare Costs Incl. O&P $871.60 1731.20 692.40 $69.05 $102.97 $3295.20 $69.05 Daily $102.97 Bare Costs Incl. O&P $871.60 865.60 865.60 692.40 70.59 $69.05 $102.97 2.01 2.21 $3365.79 $71.06 $105.18 Daily Bare Costs Incl. O&P $845.60 676.00 $63.13 $95.10 $1521.60 $63.13 $95.10 Daily Bare Costs Incl. O&P $1691.20 676.00 $65.47 $98.63 $2367.20 $65.47 $98.63 Daily Bare Costs Incl. O&P $851.60 1691.20 676.00 $66.76 $100.59 $3218.80 $66.76 $100.59 Daily Bare Costs Incl. O&P $845.60 676.40 $63.73 $95.13 $1522.00 $63.73 $95.13 Daily Bare Costs Incl. O&P $851.60 1691.20 676.40 $67.39 $100.60 $3219.20 $67.39 $100.60 Daily Bare Costs Incl. O&P $798.40 638.80 $58.73 $89.83 $1437.20 $58.73 $89.83 Daily Crew Q-16 2 Plumbers 1 Plumber Apprentice 1 Welder, Electric, 300 amp Crew Q-17 1 Steamfitter 1 Steamfitter Apprentice 1 Welder, Electric, 300 amp Crew Q-17A 1 Steamfitter 1 Steamfitter Apprentice 1 Equip. Oper. (crane) 1 Hyd. Crane, 12 Ton 1 Welder, Electric, 300 amp $859.60 687.60 70.59 $64.85 $96.70 4.01 4.41 $1617.79 $68.86 $101.11 Daily Hr. $72.05 57.65 $1152.80 461.20 64.17 $107.45 85.95 $1678.17 Hr. Daily Hr. $72.55 58.05 $580.40 464.40 64.17 $108.20 86.55 $1108.97 Hr. Daily Hr. $72.55 58.05 66.30 $580.40 464.40 530.40 2150.65 64.17 $108.20 86.55 98.65 24 L.H., Daily Totals Crew Q-18 2 Steamfitters 1 Steamfitter Apprentice 1 Welder, Electric, 300 amp $3790.02 Hr. Daily Hr. $72.55 58.05 $1160.80 464.40 64.17 $108.20 86.55 24 L.H., Daily Totals 1 Steamfitter 1 Steamfitter Apprentice 1 Electrician $1689.37 Hr. Daily Hr. $72.55 58.05 67.35 $580.40 464.40 538.80 $108.20 86.55 100.10 24 L.H., Daily Totals 1 Sheet Metal Worker 1 Sheet Metal Apprentice .5 Electrician $1583.60 Hr. Daily Hr. $70.15 56.10 67.35 $561.20 448.80 269.40 $105.70 84.50 100.10 20 L.H., Daily Totals Crew Q-21 2 Steamfitters 1 Steamfitter Apprentice 1 Electrician $1279.40 Hr. Daily Hr. $72.55 58.05 67.35 $1160.80 464.40 538.80 $108.20 86.55 100.10 32 L.H., Daily Totals Crew Q-22 1 Plumber 1 Plumber Apprentice 1 Hyd. Crane, 12 Ton $2164.00 Hr. Daily Hr. $72.05 57.65 $576.40 461.20 2150.65 $107.45 85.95 16 L.H., Daily Totals Crew Q-22A 1 Plumber 1 Plumber Apprentice 1 Laborer 1 Equip. Oper. (crane) 1 Hyd. Crane, 12 Ton 32 L.H., Daily Totals Incl. Subs O&P Hr. 16 L.H., Daily Totals Crew Q-20 Incl. O&P Bare Costs 24 L.H., Daily Totals Crew Q-19 Bare Costs Daily Crew No. $3188.25 Hr. Daily Hr. $72.05 57.65 47.25 66.30 $576.40 461.20 378.00 530.40 2150.65 $107.45 85.95 70.35 98.65 $4096.65 Cost Per Labor-Hour Bare Costs Incl. O&P $1719.20 687.60 70.59 $67.25 $100.28 2.67 2.94 $2477.39 $69.92 $103.22 Daily Bare Costs Incl. O&P $865.60 692.40 70.59 $65.30 $97.38 4.01 4.41 $1628.59 $69.31 $101.79 Daily Bare Costs Incl. O&P $865.60 692.40 789.20 2365.72 70.59 $65.63 $97.80 92.28 101.51 $4783.50 $157.92 $199.31 Daily Bare Costs Incl. O&P $1731.20 692.40 70.59 $67.72 $100.98 2.67 2.94 $2494.19 $70.39 $103.92 Daily Bare Costs Incl. O&P $865.60 692.40 800.80 $65.98 $98.28 $2358.80 $65.98 $98.28 Daily Bare Costs Incl. O&P $845.60 676.00 400.40 $63.97 $96.10 $1922.00 $63.97 $96.10 Daily Bare Costs Incl. O&P $1731.20 692.40 800.80 $67.63 $100.76 $3224.40 $67.63 $100.76 Daily Bare Costs Incl. O&P $859.60 687.60 2365.72 $64.85 $96.70 134.42 147.86 $3912.92 $199.27 $244.56 Daily Bare Costs Incl. O&P $859.60 687.60 562.80 789.20 2365.72 $60.81 $90.60 67.21 73.93 $5264.92 $128.02 $164.53 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 783 Crews - Standard Crew No. Crew Q-23 1 Plumber Foreman (outside) 1 Plumber 1 Equip. Oper. (medium) 1 Lattice Boom Crane, 20 Ton Bare Costs Hr. Daily Hr. $74.05 72.05 63.05 $592.40 576.40 504.40 868.10 $110.40 107.45 93.80 24 L.H., Daily Totals Crew R-1 1 Electrician Foreman 3 Electricians 2 Electrician Apprentices $2541.30 Hr. Daily Hr. $67.85 67.35 53.90 $542.80 1616.40 862.40 $100.85 100.10 80.10 48 L.H., Daily Totals Crew R-1A 1 Electrician 1 Electrician Apprentice $3021.60 Hr. Daily Hr. $67.35 53.90 $538.80 431.20 $100.10 80.10 16 L.H., Daily Totals Crew R-1B 1 Electrician 2 Electrician Apprentices Incl. Subs O&P $970.00 Hr. Daily Hr. $67.35 53.90 $538.80 862.40 $100.10 80.10 24 L.H., Daily Totals $1401.20 Crew R-1C Hr. Daily Hr. 2 Electricians 2 Electrician Apprentices 1 Portable cable puller, 8000 lb. $67.35 53.90 $1077.60 862.40 118.26 $100.10 80.10 32 L.H., Daily Totals Crew R-2 1 Electrician Foreman 3 Electricians 2 Electrician Apprentices 1 Equip. Oper. (crane) 1 S.P. Crane, 4x4, 5 Ton $2058.26 Hr. Daily Hr. $67.85 67.35 53.90 66.30 $542.80 1616.40 862.40 530.40 385.89 $100.85 100.10 80.10 98.65 56 L.H., Daily Totals Crew R-3 1 Electrician Foreman 1 Electrician .5 Equip. Oper. (crane) .5 S.P. Crane, 4x4, 5 Ton $3937.89 Hr. Daily Hr. $67.85 67.35 66.30 $542.80 538.80 265.20 192.94 $100.85 100.10 98.65 20 L.H., Daily Totals $1539.74 Crew R-4 Hr. Daily Hr. 1 Struc. Steel Foreman (outside) 3 Struc. Steel Workers 1 Electrician 1 Welder, Gas Engine, 300 amp $66.55 64.55 67.35 $532.40 1549.20 538.80 147.09 $102.50 99.40 100.10 40 L.H., Daily Totals $2767.49 Cost Per Labor-Hour Bare Costs Incl. O&P $883.20 859.60 750.40 954.91 $69.72 $103.88 36.17 39.79 $3448.11 $105.89 $143.67 Daily Bare Costs Incl. O&P $806.80 2402.40 1281.60 $62.95 $93.56 $4490.80 $62.95 $93.56 Daily Bare Costs Incl. O&P $800.80 640.80 $60.63 $90.10 $1441.60 $60.63 $90.10 Daily Bare Costs Incl. O&P $800.80 1281.60 $58.38 $86.77 $2082.40 $58.38 $86.77 Daily Bare Costs Incl. O&P $1601.60 1281.60 130.09 $60.63 $90.10 3.70 4.07 $3013.29 $64.32 $94.17 Daily Bare Costs Incl. O&P $806.80 2402.40 1281.60 789.20 424.48 $63.43 $94.29 6.89 7.58 $5704.48 $70.32 $101.87 Daily Bare Costs Incl. O&P $806.80 800.80 394.60 212.24 $67.34 $100.11 9.65 10.61 $2214.44 $76.99 $110.72 Daily Bare Costs Incl. O&P $820.00 2385.60 800.80 161.80 $65.51 $100.16 3.68 4.04 $4168.20 $69.19 $104.21 Daily Crew No. Crew R-5 1 Electrician Foreman 4 Electrician Linemen 2 Electrician Operators 4 Electrician Groundmen 1 Crew Truck 1 Flatbed Truck, 20,000 GVW 1 Pickup Truck, 3/4 Ton .2 Hyd. Crane, 55 Ton .2 Hyd. Crane, 12 Ton .2 Earth Auger, Truck-Mtd. 1 Tractor w/Winch Bare Costs Hr. Daily Hr. $67.85 67.35 67.35 44.95 $542.80 2155.20 1077.60 1438.40 183.83 223.10 122.56 492.21 430.13 30.79 413.43 $100.85 100.10 100.10 67.95 88 L.H., Daily Totals Crew R-6 1 Electrician Foreman 4 Electrician Linemen 2 Electrician Operators 4 Electrician Groundmen 1 Crew Truck 1 Flatbed Truck, 20,000 GVW 1 Pickup Truck, 3/4 Ton .2 Hyd. Crane, 55 Ton .2 Hyd. Crane, 12 Ton .2 Earth Auger, Truck-Mtd. 1 Tractor w/Winch 3 Cable Trailers .5 Tensioning Rig .5 Cable Pulling Rig $7110.06 Hr. Daily Hr. $67.85 67.35 67.35 44.95 $542.80 2155.20 1077.60 1438.40 183.83 223.10 122.56 492.21 430.13 30.79 413.43 609.78 76.23 370.78 $100.85 100.10 100.10 67.95 88 L.H., Daily Totals Crew R-7 1 Electrician Foreman 5 Electrician Groundmen 1 Crew Truck $8166.85 Hr. Daily Hr. $67.85 44.95 $542.80 1798.00 183.83 $100.85 67.95 48 L.H., Daily Totals Crew R-8 1 Electrician Foreman 3 Electrician Linemen 2 Electrician Groundmen 1 Pickup Truck, 3/4 Ton 1 Crew Truck $2524.63 Hr. Daily Hr. $67.85 67.35 44.95 $542.80 1616.40 719.20 122.56 183.83 $100.85 100.10 67.95 48 L.H., Daily Totals Crew R-9 1 Electrician Foreman 1 Electrician Lineman 2 Electrician Operators 4 Electrician Groundmen 1 Pickup Truck, 3/4 Ton 1 Crew Truck $3184.79 Hr. Daily Hr. $67.85 67.35 67.35 44.95 $542.80 538.80 1077.60 1438.40 122.56 183.83 $100.85 100.10 100.10 67.95 64 L.H., Daily Totals Crew R-10 1 Electrician Foreman 4 Electrician Linemen 1 Electrician Groundman 1 Crew Truck 3 Tram Cars 48 L.H., Daily Totals 784 Incl. Subs O&P $3903.99 Hr. Daily Hr. $67.85 67.35 44.95 $542.80 2155.20 359.60 183.83 237.63 $100.85 100.10 67.95 $3479.06 Cost Per Labor-Hour Bare Costs Incl. O&P $806.80 3203.20 1601.60 2174.40 202.21 245.41 134.82 541.43 473.14 33.87 454.77 $59.25 $88.48 21.55 23.70 $9871.66 $80.80 $112.18 Daily Bare Costs Incl. O&P $806.80 3203.20 1601.60 2174.40 202.21 245.41 134.82 541.43 473.14 33.87 454.77 670.76 83.86 407.86 $59.25 $88.48 33.56 36.91 $11034.14 $92.81 $125.39 Daily Bare Costs Incl. O&P $806.80 2718.00 202.21 $48.77 $73.43 3.83 4.21 $3727.01 $52.60 $77.65 Daily Bare Costs Incl. O&P $806.80 2402.40 1087.20 134.82 202.21 $59.97 $89.51 6.38 7.02 $4633.43 $66.35 $96.53 Daily Bare Costs Incl. O&P $806.80 800.80 1601.60 2174.40 134.82 202.21 $56.21 $84.12 4.79 5.27 $5720.63 $61.00 $89.38 Daily Bare Costs Incl. O&P $806.80 3203.20 543.60 202.21 261.39 $63.70 $94.87 8.78 9.66 $5017.21 $72.48 $104.53 Daily Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. Crews - Standard Crew No. Crew R-11 1 Electrician Foreman 4 Electricians 1 Equip. Oper. (crane) 1 Common Laborer 1 Crew Truck 1 Hyd. Crane, 12 Ton Bare Costs Hr. Daily Hr. $67.85 67.35 66.30 47.25 $542.80 2155.20 530.40 378.00 183.83 2150.65 $100.85 100.10 98.65 70.35 56 L.H., Daily Totals Crew R-12 1 Carpenter Foreman (inside) 4 Carpenters 4 Common Laborers 1 Equip. Oper. (medium) 1 Steel Worker 1 Dozer, 200 H.P. 1 Pickup Truck, 3/4 Ton $5940.88 Hr. Daily Hr. $59.10 58.60 47.25 63.05 64.55 $472.80 1875.20 1512.00 504.40 516.40 1382.36 122.56 $88.00 87.25 70.35 93.80 99.40 88 L.H., Daily Totals Crew R-13 1 Electrician Foreman 3 Electricians .25 Equip. Oper. (crane) 1 Equipment Oiler .25 Hydraulic Crane, 33 Ton Incl. Subs O&P $6385.72 Hr. Daily Hr. $67.85 67.35 66.30 56.40 $542.80 1616.40 132.60 451.20 607.40 $100.85 100.10 98.65 83.90 42 L.H., Daily Totals $3350.41 Crew R-15 Hr. Daily Hr. 1 Electrician Foreman 4 Electricians 1 Equipment Oper. (light) 1 Telescoping Boom Lift, to 40’ $67.85 67.35 59.70 $542.80 2155.20 477.60 345.57 $100.85 100.10 88.85 48 L.H., Daily Totals $3521.17 Crew R-15A Hr. Daily Hr. 1 Electrician Foreman 2 Electricians 2 Common Laborers 1 Equip. Oper. (light) 1 Telescoping Boom Lift, to 40’ $67.85 67.35 47.25 59.70 $542.80 1077.60 756.00 477.60 345.57 $100.85 100.10 70.35 88.85 48 L.H., Daily Totals Crew R-18 .25 Electrician Foreman 1 Electrician 2 Electrician Apprentices $3199.57 Hr. Daily Hr. $67.85 67.35 53.90 $135.70 538.80 862.40 $100.85 100.10 80.10 26 L.H., Daily Totals Crew R-19 .5 Electrician Foreman 2 Electricians $1536.90 Hr. Daily Hr. $67.85 67.35 $271.40 1077.60 $100.85 100.10 20 L.H., Daily Totals Crew R-21 1 Electrician Foreman 3 Electricians .1 Equip. Oper. (medium) .1 S.P. Crane, 4x4, 25 Ton 32.8 L.H., Daily Totals $1349.00 Hr. Daily Hr. $67.85 67.35 63.05 $542.80 1616.40 50.44 92.71 $100.85 100.10 93.80 $2302.35 Cost Per Labor-Hour Bare Costs Incl. O&P $806.80 3203.20 789.20 562.80 202.21 2365.72 $64.40 $95.75 41.69 45.86 $7929.93 $106.09 $141.61 Daily Bare Costs Incl. O&P $704.00 2792.00 2251.20 750.40 795.20 1520.60 134.82 $55.46 $82.87 17.10 18.81 $8948.21 $72.56 $101.68 Daily Crew R-22 .66 Electrician Foreman 2 Electricians 2 Electrician Apprentices Bare Costs Daily Hr. $67.85 67.35 53.90 $358.25 1077.60 862.40 $100.85 100.10 80.10 Hr. Daily Hr. .25 Electrician Foreman (outside) 1 Electrician 2 Laborers (Semi-Skilled) $69.35 67.35 47.25 $138.70 538.80 756.00 $103.05 100.10 70.35 26 L.H., Daily Totals 1 Electrician 1 Core Drill, Electric, 2.5 H.P. $806.80 2402.40 197.30 671.20 668.15 $65.31 $97.09 14.46 15.91 $4745.85 $79.77 $113.00 Daily Bare Costs Incl. O&P $806.80 3203.20 710.80 380.13 $66.16 $98.35 7.20 7.92 $5100.93 $73.36 $106.27 Daily Bare Costs Incl. O&P $806.80 1601.60 1125.60 710.80 380.13 $59.46 $88.43 7.20 7.92 $4624.93 $66.66 $96.35 Daily Bare Costs Incl. O&P $201.70 800.80 1281.60 $59.11 $87.85 $2284.10 $59.11 $87.85 Daily Bare Costs Incl. O&P $403.40 1601.60 $67.45 $100.25 $2005.00 $67.45 $100.25 Daily Bare Costs Incl. O&P $806.80 2402.40 75.04 101.98 $67.37 $100.13 2.83 3.11 $3386.22 $70.19 $103.24 $2298.25 Crew R-30 Crew R-31 Incl. O&P Incl. Subs O&P Hr. 37.28 L.H., Daily Totals Bare Costs Daily Crew No. $1433.50 Hr. Daily Hr. $67.35 $538.80 61.41 $100.10 8 L.H., Daily Totals Crew W-41E .5 Plumber Foreman (outside) 1 Plumber 1 Laborer 20 L.H., Daily Totals Bare Costs Incl. O&P $532.49 1601.60 1281.60 $61.65 $91.62 $3415.69 $61.65 $91.62 Daily Bare Costs Incl. O&P $206.10 800.80 1125.60 $55.13 $82.02 $2132.50 $55.13 $82.02 Daily Bare Costs Incl. O&P $800.80 67.55 $67.35 7.68 $100.10 8.44 $868.35 $75.03 $108.54 Daily Bare Costs Incl. O&P $441.60 859.60 562.80 $62.53 $93.20 $1864.00 $62.53 $93.20 Daily $600.21 Hr. Daily Hr. $74.05 72.05 47.25 $296.20 576.40 378.00 $110.40 107.45 70.35 $1250.60 Cost Per Labor-Hour Copyright The Gordian Group, Inc. 2023 For customer support on your Building Construction Costs with RSMeans data, call 800.448.8182. 785