Delay and Extension of Time Albert K H Juan Barrister-at-Law Lecturer, Department of Real Estate & Construction, The University of Hong Kong Delay Time aspect of construction projects Along with cost and quality Main Contractor’s obligations Beyond the control of parties Caused by the Employer Caused by the Main Contractor EOT – in respect of certain causes of delay Beyond the control of parties Force majeure :Nature/natural disasters – Act of God Examples: war, epidemics, earthquake, governmental requirements, exceptionally adverse weather Before commencement and during the course of works Covered by insurance Caused by the Employer Disturbance of regular progress of the works Claims for loss and expense The Employer’s personnel AIs caused :Additional work to be done Postponement Change of sequence Necessary instructions or drawings as per a specific request in writing Delay of artists, tradesmen or other people engaged by the Employer (in executing other works) Caused by the Main Contractor In violation of the obligations Mismanagement in respect of :Labour, goods/materials, plant and equipment Remedies available to the Employer LD, determination Domestic sub-contractors VS NSCs EOT - Introduction Types of valid grounds Condition precedent Grounds and procedure Meaning Date for Practical Completion – be reasonably extended Clause 23 of the Old Standard Form Concepts in relation to Time Time is “of the essence” Meaning Remedies available Circumstances in which time will be of the essence of the contract :So expressed in the contract concerned In case of delay to an unreasonable extent NB- for typical construction contracts :- Time is “at large” Meaning In the absence of an agreed date for completion Court’s approach: a question of facts Rare for standard forms of building contract When may time become at large? – NBdefault/neglect on the part of the Architect May affect the operation of the LD clause EOT - Grounds Grounds Fault of neither contractual party :Force majeure Inclement weather (rain, typhoons) Civil commotion, local combination of workmen, strike or lockout which affects any of the trades/manufacture/transportation of goods/materials NSCs Antiquities Shortages in respect of labour or goods/materials Fault of the Employer :Include: Compliance with AIs Delay in receiving instructions/drawings Delay on the part of the people engaged by the Employer EOT - Procedure Is mere occurrence of a certain relevant event sufficient? NB- “Causal” link Reasonably apparent that the progress of the works is delayed Give written notice forthwith To the Architect Cf. procedural requirements under the New Standard Form Role of the Architect What if the Main Contractor fails to act promptly? Consideration of EOT Applications Consideration by the Architect :Estimate/decide on the length of delay Complicated task at times As soon as he can reasonably decide on the matter NB- right to challenge the decision made by the Architect Consider the scenario in which the Architect, in his decision on the matter, provides detailed reasons as support :A matter which calls for an exercise of judgment Cf. duty of a judge From the perspective of the Main Contractor Duty of the Architect to grant an EOT if the application is with justifications Grounds/criteria as set out in the construction contract are the relevant considerations NB- the Architect may communicate with/inform the Employer prior to making his decision Is this to be a relevant consideration? Cf. duty to seek consent? Argyropoulos & Pappa v Chain Compania Naviera SA (1990) 7-CLD-05-01 :Facts: the employer concerned raised objections to and refused to accept the grant of an EOT in favour of the main contractor concerned What the employer was doing was to prevent the architect from granting the EOT NB- the actions of the architect References – (see Course handout/planner)