SECTION: 07 14 00 PROJECT: G+3P+28 FLOORS RESIDENTIAL AND COMMERCIAL BUILDING ON PLOT NO. 346 - 0568 AT BUSINESSBAY, DUBAI CLIENT: H.E DHAHI KHALFAN DHAHI BIN TAMIM AL MEHAIRI FLUID APPLIED POLYURETHANE RUBBER WATER PROOFING Page 1 of 5 AUGUST 2022 REVISION: 0 MAIN WORK TENDER SECTION 07 14 00 FLUID APPLIED WATERPROOFING FOR WET AREA WATERPROOFING, INTERNAL SURFACES OF LIFT PITS ETC... GENERAL 1.1 SECTION INCLUDES (i) (ii) (iii) 1.2 Compliance with Section of General requirements. Preparation of substrates to accept waterproofing materials Fabrication, supply and installation of waterproofing membrane to floors of coffee shop, washrooms and janitor and other locations as shown on the drawings. RELATED WORK Supply and insulation and Fluid Applied Waterproofing as an air barrier/salt protection membrane to exterior walls, of reinforced concrete and rendered concrete block masonry of cladding system. Thermal insulation Sheet Membrane Waterproofing – Below grade (WP – 1) Cementitution Waterproofing (WP – 5) Membrane Roofing (WP – 2) 1.3 QUALITY ASSURANCE Applicator: Having not less than five years of proven experience in work of this Section and approved by the manufacturer of the waterproofing. 1.4 INSPECTION AND TESTING An Inspection and Testing Company will be appointed by the contractor to make inspections and tests of the waterproofing as the Engineer may determine. Cost of Waterproofing and Testing Section 07 14 00 07 14 00/1 SECTION: 07 14 00 PROJECT: G+3P+28 FLOORS RESIDENTIAL AND COMMERCIAL BUILDING ON PLOT NO. 346 - 0568 AT BUSINESSBAY, DUBAI CLIENT: H.E DHAHI KHALFAN DHAHI BIN TAMIM AL MEHAIRI FLUID APPLIED POLYURETHANE RUBBER WATER PROOFING Page 2 of 5 AUGUST 2022 REVISION: 0 MAIN WORK TENDER shall be paid by the Contractor Prior to concealing of the waterproofing, the Contractor shall give the Engineer written notice that the installation of the waterproofing has been inspected ad approved by the waterproofing subcontractor and by himself. Subsequent work will not be permitted until the above inspection and testes have been carried out by the inspection and testing Company, to the Engineer’s approval. 1.5 SUBMITTALS Comply with requirements of Section - Submittals. Product Data: Submit manufacture’s specifications, installation instructions, and recommendations for waterproofing material related components. Include data substantiating that materials comply with specified requirements. Samples: Submit cured film samples of waterproofing applied to concrete substrate. 1.6 PRODUCT HANDLING Deliver materials to site undamaged in original sealed containers. Store materials in dry area out of direct sunlight, at temperatures within \ manufacture have recommenced temperature range. 1.7 EXTENDED WARRANTY Provide and extended warranty for a period of ten years from date of the Defects liability Certificate, against faulty workmanship and materials. Upon written notification from the Engineer that the membrane waterproofing is defective work. 1.8 JOB CONDITIONS Substrate: Proceed with work of this Section after substrate construction and penetrations work is completed. Ensure substrate is sufficiently dry to prevent pin holing of membrane of membrane and to prevent to substrate. Protect work of others from damage due to work this Section. Section 07 14 00 07 14 00/2 SECTION: 07 14 00 PROJECT: G+3P+28 FLOORS RESIDENTIAL AND COMMERCIAL BUILDING ON PLOT NO. 346 - 0568 AT BUSINESSBAY, DUBAI CLIENT: H.E DHAHI KHALFAN DHAHI BIN TAMIM AL MEHAIRI FLUID APPLIED POLYURETHANE RUBBER WATER PROOFING Page 3 of 5 AUGUST 2022 REVISION: 0 MAIN WORK TENDER PRODUCT 1.9 MATERIALS (i) Waterproofing / Air Barrier / Salt Protection Membrane: Pitch modified elastomer type Nitoproof 600 by Fosroc, Sonneborn. HLM.5000 by Master Builders Technologies Permaquik 6800 or equal as per Engineers approval. WATERPROOFING OF ALL WET AREAS, WASHROOMS, PANTRIES, JANITOR, ROOF PUMP ROOMS, CONCRETE PLATFORMS FOR EQUIPMENT BASES, KITCHEN, LAUNDRY, TOILETS, BATHROOMS, OPEN TERRACES AND BALCONIES WATER PROOFING TYPE (WP-3) – REFER DRAWINGS FOR APPLICABLE LOCATIONS (i) The Product Cold-applied elastomeric single components polyurethane rubber having over 90% solids to form a complete system. (ii) The cured waterproofing system shall meet the following requirements. SNo. 1. 2. 3. 4. 5. 6. 7. 8. 9. PHYSICAL PROPERTY Tensile strength (20 deg. C56% RH) Elongation (20 deg. C65% RH) Modulus at 100% Hardness shore A Tear Resistance Dye C Adhesion to concrete Brittleness temperature Flash Point Resistance to water for 335 hours at 23 deg C. a. Change in Weight b. Volume increase c. Change in tensile strength d. Change in elongation e. Change in tear Dye C Resistance to water for 72 hours at 70 deg C a. Change in weight b. Volume increase 10. Section 07 14 00 07 14 00/3 PERFORMANCE REQUIREMENTS 1.05 N/mm2 600% 5.25 kg/sq.cm 40 +/-5 7.20 kg/cm 1.80 kg/cm 50 deg. C 200 min. above 93 deg C +0.7% 1% 0% -10% -10% +2.2% 2.5% SECTION: 07 14 00 PROJECT: G+3P+28 FLOORS RESIDENTIAL AND COMMERCIAL BUILDING ON PLOT NO. 346 - 0568 AT BUSINESSBAY, DUBAI CLIENT: H.E DHAHI KHALFAN DHAHI BIN TAMIM AL MEHAIRI c. Change in tensile strength d. Change in elongation e. Change in tear Dye C Water permeability Heat ageing for 168 hours a. Change in height b. Change in tensile strength c. Change in elongation 11. 12. Warrantee: iii) FLUID APPLIED POLYURETHANE RUBBER WATER PROOFING Page 4 of 5 AUGUST 2022 REVISION: 0 MAIN WORK TENDER 0% 0% 0% 0.25 Persm -3.1% -10% -12% 15 Years from the date of taking over Approved Product • • NITOPROOF 600 – HLM5000 – Or similar from • SIPLAST • EMI - HENKAL Or similar to approval FOSROC Master Builder Execution PREPARATION • • • • • • • • Prepare concrete surface by mechanical scrubber Apply 20mm thick self leveling waterproof screed to engineer’s approval. Ensure substrate is completely dry to approval of watering manufacturer. Make sure substrates free of latience, from oils, cure and seal compounds and other substances detrimental to bond. Any ridges and concrete irregularities shall be ground smooth. Rout out cracks greater than 1.6 mm wide. Apply primal to substrate, full coverage at the rate to manufacturer’s printed instructions. Fill cracks with sealant PQ 6800 non-sag material or as, recommended by waterproofing manufacturer, after priming of substrate where primer is required by the membrane manufacturer as part of the waterproofing system. Apply surface conditioner to all metals to be covered with waterproofing. Section 07 14 00 07 14 00/4 SECTION: 07 14 00 PROJECT: G+3P+28 FLOORS RESIDENTIAL AND COMMERCIAL BUILDING ON PLOT NO. 346 - 0568 AT BUSINESSBAY, DUBAI CLIENT: H.E DHAHI KHALFAN DHAHI BIN TAMIM AL MEHAIRI FLUID APPLIED POLYURETHANE RUBBER WATER PROOFING Page 5 of 5 AUGUST 2022 REVISION: 0 MAIN WORK TENDER INSTALLATION ON WALL AND SOFFITS • • • • • • • • Install work of this Section in accordance with manufacturer’s instructions. Apply the liquid polyurethane waterproofing (Thixotropic grade) under manufacturer’s representative supervision using spray or brush/roller when spraying is not possible due to job conditions. Prime surfaces if required by manufacture. Apply waterproofing/air barrier/salt protection membrane to minimum thickness of 0.75mm. Allow 24 hours curing time between coats. Apply final coat to full coverage at right angles to the first to provide a total coating thickness of minimum 1.5 mm. Extend waterproofing p vertical surfaces min. 150 mm and extend over curbs and up stands. At underside of slabs extend membrane on slab edge and return minimum 150 mm on top floors. Make good any work at penetrates membrane by recoating and re-drying with compatible materials to prevent water penetrating the substrate. This applies particularly to such things as brackets. INSTALLATION ON FLOORS • • • • • • Ensure that concrete substrate is clean, smooth and dry. Apply 20 mm self leveling water proof screed prior to applying water proofing. Ensure that prior top application of fluid waterproofing all the piping, conduit, drains, etc., which are penetrating the concrete slab in place. Apply the bitumen gelified emulsion with a brush or a roller at a rate of minimum 1.5 kg/m on horizontal surfaces and extend at least 100 mm high on vertical surfaces or as indicated on drawings. Allow the fluid waterproofing to cure for at least 24 hours and apply second coat at right angles to first coat. After proper curing and before installation of mortar and ceramic tile installer. Co-ordinate floor waterproofing work with the ceramic tile installer. Provide a minimum 24 hours flood test for all waterproofed floor areas and coordinate inspection and testing company. Section 07 14 00 07 14 00/5