DESIGN, INSTALLATION & MAINTENANCE MANUAL MARINE CARBON DIOXIDE FIRE EXTINGUISHING SYSTEM DOT CONTAINERS MARINE APPROVAL NFPA 12 STANDARD P/N C06-019 (Rev. 3 / July, 2015) TABLE OF CONTENTS Section Number 1.0 Page Number Equipment .................................................................................................................. Section 1 – 34 Pages 1.1 General Information ................................................................................................................ Page 1 1.2 Agent ...................................................................................................................................... Page 1 1.2.1 1.2.2 1.2.3 1.2.4 1.2.5 1.2.6 1.3 Storage and Pressure.......................................................................................................... 1 Temperature ........................................................................................................................ 2 Visibility ................................................................................................................................ 2 Noise.................................................................................................................................... 2 Cleanup ............................................................................................................................... 2 Static Electricity ................................................................................................................... 2 Safety...................................................................................................................................... Page 2 1.3.1 Safety Recommendations ................................................................................................... 3 1.4 Carbon Dioxide Cylinders ....................................................................................................... Page 4 1.5 Cylinder Valve Assembly ........................................................................................................ Page 5 1.5.1 1.5.2 1.6 Slave Valve Assembly ......................................................................................................... 6 Master Valve Assembly ....................................................................................................... 6 System Actuation .................................................................................................................... Page 6 1.6.1 Pneumatic Actuator Valve and Cylinder Assembly ............................................................. 7 1.6.2 Local Lever Actuator............................................................................................................ 8 1.6.3 Latch Door Cable Pull Box .................................................................................................. 9 1.6.4 Corner Pulley ..................................................................................................................... 10 1.6.5 Stainless Steel Cable ........................................................................................................ 11 1.6.6 Cable Junction Box Assembly ........................................................................................... 11 1.7 Flexible Discharge Bend w/ Check Valve ............................................................................. Page 12 1.8 Nozzles And Accessories ..................................................................................................... Page 13 1.9 1.10 1.8.1 Radial Nozzle .................................................................................................................... 13 1.8.2 Baffle Nozzle ..................................................................................................................... 14 1.8.3 Vent Nozzle ....................................................................................................................... 15 1.8.3.1 Flange Mounting Kit, Vent Nozzle ...................................................................... 15 1.8.4 “S” Type Nozzle ................................................................................................................. 16 1.8.4.1 Flange Mounting Kit, “S” Type Nozzle ................................................................ 16 Cylinder Racks...................................................................................................................... Page 17 1.9.1 Single Row Racking .......................................................................................................... 17 1.9.2 Double Row Racking ......................................................................................................... 18 Check Valve – 1/2” through 2” .............................................................................................. Page 19 1.10.1 Check Valve – 1/4” ............................................................................................................ 20 1.11 Header Vent Plug ................................................................................................................. Page 21 1.12 Header Safety Relief ............................................................................................................ Page 21 1.13 Pressure Switch .................................................................................................................... Page 22 1.14 Pressure Trip Assembly ....................................................................................................... Page 23 USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 1 of 4 Revision Date: July, 2015 TABLE OF CONTENTS 1.15 Odorizer ................................................................................................................................ Page 24 1.16 Weigh Beam Scale Assembly .............................................................................................. Page 24 1.17 Pneumatic Time Delays ........................................................................................................ Page 25 1.18 Pneumatically Operated Siren .............................................................................................. Page 26 1.19 Selector Valve....................................................................................................................... Page 27 1.20 Instructional Signs ................................................................................................................ Page 28 1.20.1 1.20.2 1.20.3 1.20.4 1.20.5 1.20.6 2.0 System Configurations ............................................................................................... Section 2 – 2 Pages 2.1 3.0 Warning – Primary Actuation ............................................................................................. 28 Warning – Secondary Actuation ........................................................................................ 29 Warning – Manual Actuation ............................................................................................. 30 Caution – Vacate Immediately / Nearby Space................................................................. 31 Warning – Vacate Immediately / Inside Room .................................................................. 32 Warning – Do Not Enter .................................................................................................... 33 Configuration No. 1 ................................................................................................................. Page 1 System Design ........................................................................................................... Section 3 – 15 Pages 3.1 3.2 Machinery Spaces .................................................................................................................. Page 1 3.1.1 System Design .......................................................................................................... Page 1 3.1.2 System Design – Spaces with Propulsion Machinery ............................................... Page 1 Electrical Equipment Spaces .................................................................................................. Page 2 3.2.1 3.3 3.4 3.5 System Design .......................................................................................................... Page 2 Additional Design Considerations. ......................................................................................... Page 2 3.3.1 Uncloseable Openings .............................................................................................. Page 3 3.3.2 Ventilation .................................................................................................................. Page 4 Nozzle Selection / Placement ................................................................................................. Page 4 3.4.1 Baffle Nozzle ............................................................................................................ Page 4 3.4.2 Vent Nozzle .............................................................................................................. Page 5 3.4.3 “S” Type Nozzle ....................................................................................................... Page 5 3.4.4 Radial Nozzle ........................................................................................................... Page 6 3.4.5 Nozzle Strainer ........................................................................................................ Page 6 3.4.6 Nozzle Orifice Data Table ........................................................................................ Page 7 Discharge Piping .................................................................................................................... Page 8 3.5.1 USCG No: 162.038/12/0 U.L. Ex4447 Pipe Size Determination ............................................................................................ Page 8 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 2 of 4 Revision Date: July, 2015 TABLE OF CONTENTS 4.0 3.6 Equivalent Length Values. ...................................................................................................... Page 9 3.7 Pipe and Nozzle Calculations for USCG Systems. .............................................................. Page 10 3.8 Sample Problem. .................................................................................................................. Page 12 System Installation .................................................................................................... Section 4 – 16 Pages 4.1 General Requirements ........................................................................................................... Page 1 4.2 Pipe and Fittings ..................................................................................................................... Page 1 4.2.1 4.2.2 4.2.3 4.3 4.4 Ferrous Pipe ........................................................................................................................ 1 Fittings ................................................................................................................................. 1 Flanged, Welded and Misc. Fittings .................................................................................... 2 Piping Distribution System ...................................................................................................... Page 2 4.3.1 Discharge Pipe, Tubing and Fittings ................................................................................... 2 4.3.2 Pneumatic Actuation Pipe and Tubing ................................................................................ 2 4.3.2.1 Pneumatic Actuation Pipe / Tubing Length Limitations ........................................ 2 4.3.3 Discharge Manifold .............................................................................................................. 3 4.3.4 Closed Pipe Sections .......................................................................................................... 3 4.3.5 Check Valves ....................................................................................................................... 4 Cylinder Assemblies ............................................................................................................... Page 4 4.4.1 Carbon Dioxide Cylinders .................................................................................................... 5 4.4.2 Local Lever Actuator ............................................................................................................ 5 4.4.3 Master Cylinder Adapter Kit................................................................................................. 6 4.4.4 Nitrogen Cylinders ............................................................................................................... 7 4.5 Pipe and Nozzle Installation ................................................................................................... Page 7 4.6 Installation of Flexible Discharge Hose to Piping ................................................................... Page 8 4.7 Pressure Switches .................................................................................................................. Page 9 4.8 Stop Valve ............................................................................................................................ Page 10 4.9 Odorizer ................................................................................................................................ Page 10 4.10 Remote Pull Cable Components .......................................................................................... Page 11 4.11 Pneumatic Time Delay ......................................................................................................... Page 12 4.12 Pneumatic Actuator Valve Station ........................................................................................ Page 13 4.13 Pneumatically Operated Siren .............................................................................................. Page 14 4.14 Pressure Trip Assembly ....................................................................................................... Page 15 4.15 Discharge Nozzles ................................................................................................................ Page 15 4.16 Pressure Testing New Installation ........................................................................................ Page 15 4.17 System Operation Requirement ........................................................................................... Page 16 4.18 Remote Pneumatic Manual Operation ................................................................................. Page 16 4.19 Emergency Manual Operation .............................................................................................. Page 16 USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 3 of 4 Revision Date: July, 2015 TABLE OF CONTENTS 5.0 Maintenance and Inspection ...................................................................................... Section 5 – 9 Pages 5.1 Preventive Maintenance ......................................................................................................... Page 1 5.1.1 Preventive Maintenance Procedures, Monthly .......................................................... Page 2 5.1.1.1 Inspect Hazard Area System Components........................................................... 2 5.1.1.2 Check Nitrogen Cylinder Pressure ....................................................................... 3 5.1.2 Preventive Maintenance Procedures, Semi-Annual .................................................. Page 4 5.1.2.1 Check Carbon Dioxide Cylinder Weight ............................................................... 4 5.1.2.2 Test Pressure Switch ............................................................................................ 4 5.1.3 Preventive Maintenance Procedures, Annual ........................................................... Page 5 5.1.3.1 Verify Operation of Alarms and Pressure Switches .............................................. 5 5.1.4 Preventive Maintenance Procedures, Two (2) Year ................................................. Page 5 5.1.4.1 Inspect Carbon Dioxide Distribution Piping .......................................................... 5 5.1.5 Preventive Maintenance Procedures, Five (5) Year ................................................. Page 6 5.1.5.1 Inspect and/or Hydrostatically Test Co2 Cylinder ................................................. 6 5.1.5.2 Inspect and/or Hydrostatically Test Nitrogen Cylinders ........................................ 6 5.1.5.3 Inspect and/or Hydrostatically Test Flexible Discharge Bends............................. 6 5.2 Cleaning.................................................................................................................................. Page 7 5.3 Nozzle Service ........................................................................................................................ Page 7 5.4 Repairs ................................................................................................................................... Page 7 5.5 Removal of Cylinders ............................................................................................................. Page 7 5.5.1 5.5.2 6.0 CO2 Cylinders ...................................................................................................................... 7 Nitrogen Cylinders ............................................................................................................... 7 5.6 Post Fire Maintenance ............................................................................................................ Page 8 5.7 CO2 Cylinder Recharge .......................................................................................................... Page 8 5.8 Nitrogen Cylinder Recharge ................................................................................................... Page 9 Parts List ...................................................................................................................... Section 6 – 4 Pages 6.1 Cylinder Assemblies ............................................................................................................... Page 1 6.2 Cylinder Accessories .............................................................................................................. Page 1 6.3 Nozzles w/ Accessories .......................................................................................................... Page 1 6.4 Accessories ............................................................................................................................ Page 1 6.5 Check Valves .......................................................................................................................... Page 1 6.6 Signs ....................................................................................................................................... Page 1 6.7 Cylinder Rack Assemblies / Single Row ................................................................................ Page 2 6.8 Add-on Rack Assemblies / Single Row .................................................................................. Page 2 6.9 Cylinder Rack Assemblies / Double Row ............................................................................... Page 2 6.10 Add-on Rack Assemblies / Double Row ................................................................................. Page 2 6.11 Cylinder Racking Accessories ................................................................................................ Page 2 6.12 Cylinder Racking Spare Parts ................................................................................................ Page 2 6.13 Spare Parts for CO2 Hardware ............................................................................................... Page 3 6.14 Stop / Selector Valves ............................................................................................................ Page 3 6.15 Cable Components and Accessories ..................................................................................... Page 3 USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 4 of 4 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.0 EQUIPMENT 1.1 GENERAL INFORMATION Carbon Dioxide is an effective agent for Class A (wood, paper, etc.), Class B (flammable liquids and gases), and Class C (electrical equipment hazards). Carbon Dioxide should only be applied after careful consideration of potential fire characteristics of the hazard itself, as well as its contents. Rapidly developing fires such as those found in engine and pump rooms must be extinguished quickly to minimize the effects of heat build-up. However, a fire in a cargo hold should be protected with a slower Carbon Dioxide discharge. In some cases, the cargo hold may have to be kept inert for a considerable amount of time to contain the fire until additional means of extinguishment are possible. A Fike Marine Carbon Dioxide system consists of a cylinder, or multiple cylinders, discharging into a system of distribution piping that terminates at specially designed Carbon Dioxide discharge nozzles. Fike Carbon Dioxide systems are custom designed to protect a specific hazard or application. The system designer determines the quantity of Carbon Dioxide and the method of application required for the protection of a specific hazard. This is based on the materials or product involved. Title 46 of the Department of Transportation Code of Federal Regulations, NVIC Circular 6-72, NFPA 12 – Standard on Carbon Dioxide Extinguishing Systems, and this manual are used as guides to determine the appropriate design parameters. Fike Marine Carbon Dioxide systems are actuated pneumatically and/or manually as described in Section 2 of this manual. Local manual operation is possible at the tanks, but is not considered part of the normal system actuation mode and should only be used as a last resort in an emergency situation. 1.2 AGENT Carbon Dioxide is an odorless, colorless, electrically non-conductive and non-deteriorating inert clean agent. Carbon Dioxide is approximately 50% heavier than air and is normally present in the atmosphere at 0.03% by volume. Carbon Dioxide is instrumental in controlling respiration and other vital responses in humans and animals. Extinguishing concentrations of Carbon Dioxide WILL NOT support human or animal life. (See Sections 3.0 and 3.1 for additional precautionary and safety recommendations). Carbon Dioxide is a standard commercial product commonly used for carbonating beverages, fast-freezing food products, purging pipes and tanks, medical purposes and a multitude of other tasks. It is also used for fire fighting purposes: e.g. hose reels, hand portable extinguishers, and engineered fixed-pipe systems. Carbon Dioxide is available in most large cities and seaports throughout the world. Carbon Dioxide extinguishes fires by reducing the oxygen content of the protected space to a point where it will not support combustion. “Class B” (flammable liquids and gases) and “Class C” (electrical equipment) fires are generally extinguished rather quickly by the use of Carbon Dioxide. “Class A” (wood, paper, cloth, etc.) fires are extinguished by the prolonged action of a high concentration of Carbon Dioxide. Retaining the agent within the protected space inhibits the fire’s ability to re-ignite. The ability of the space to retain the Carbon Dioxide is a critical factor in the extinguishment of “Class A” fires. In addition to reducing the amount of oxygen available to the fire, Carbon Dioxide also cools the surrounding atmosphere. This additional by-product has been found to be beneficial to the extinguishment process. 1.2.1 STORAGE AND PRESSURE Carbon Dioxide, when used as a fire extinguishing agent, is stored under pressure in spun steel cylinders. Standard cylinder sizes include 50, 75 and 100 lb. (22.7, 34 and 45.4 kg) capacities. These cylinders contain o o Carbon Dioxide in a liquid/vapor state at an ambient temperature of 70 F (21.1 C) and a pressure of 850 psi o o (5,861 kPa). The allowable working temperature range of the Fike Marine Carbon Dioxide System is 0 F -130 F o (-17.8-54.4 C). In this range, the pressure of Carbon Dioxide is 300-2,300 psi (2,068-15,858 kPa). The discharge of this pressurized CO2 occurs at a high velocity that can cause noise loud enough to be startling, but insufficient to cause injury. WARNING: The Carbon Dioxide gas used in these systems is stored at extremely high pressures. An accidental, uncontrolled discharge of this gas can result in the sudden violent propulsion of the cylinder(s) capable of causing severe property damage and personal injury. All the warnings and instructions stated in this manual must be followed to ensure the safe installation and performance of the CO2 system. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 1 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.2.2 TEMPERATURE o o The temperature of liquid Carbon Dioxide discharging from a nozzle is approximately –100 F (-78.8 C). Direct contact with the liquid agent being discharged from the nozzle(s) will have a freezing effect on objects within the hazard and can cause frostbite and/or freezing if contact is made with the skin. The liquid phase of the agent vaporizes quite rapidly when coming into contact with the atmosphere, thus limiting this hazard to the immediate vicinity of the nozzle(s). 1.2.3 VISIBILITY The discharge of Carbon Dioxide resembles a cloud as liquid Carbon Dioxide vaporizes. The low temperature of the agent chilling the moisture in the atmosphere causes the cloud effect, or fogging. The fine “snow” accompanying the discharged liquid is remnant particles of dry ice. 1.2.4 NOISE The high pressure / velocity discharge from the system nozzle(s) can cause noise loud enough to be startling, but is ordinarily insufficient to cause harm. 1.2.5 CLEANUP Carbon Dioxide vaporizes completely after discharge, whereas the cost of cleanup and peripheral damage associated with water, foam, and dry chemical agents can exceed the cost of the actual fire damage. Cleanup costs and associated downtime with a Carbon Dioxide System discharge are negligible. Because Carbon Dioxide is an inert gas, most materials and equipment are totally unaffected by exposure to the agent. Carbon Dioxide is stable, even at high temperatures, and does not decompose when subjected to open flame or extreme temperatures. Therefore, it does not cause metals to corrode or deteriorate. 1.2.6 STATIC ELECTRICITY Caution is required where Carbon Dioxide may be discharged into potentially explosive atmospheres. Electrostatic charging of non-grounded conductors may occur during the discharge of liquefied gases. These conductors may discharge to other objects causing an electric spark of sufficient energy to initiate an explosion. 1.3 SAFETY In hazard areas that may be occupied, suitable safeguards MUST be provided to ensure prompt evacuation from, and/or prevent entry into, the protected space(s). Warning signs, visual and audible alarms, discharge delays, and other notification devices SHALL be provided with all Carbon Dioxide systems and installation. Extinguishing concentrations of Carbon Dioxide can create a serious health hazard to any personnel in the discharge area. In addition, the fog cloud produced by a Carbon Dioxide discharge can limit visibility in the discharge area. Carbon Dioxide does not contain oxygen and WILL NOT support human life. The following reactions to Carbon Dioxide have been documented: • • • At concentrations between 3% and 4% by volume in the atmosphere, the breathing rate increases and headaches may occur. At concentrations exceeding 9% by volume, personnel can lose consciousness within minutes. This is generally preceded by disorientation, visual disturbances, ringing ears, tremors, etc. At concentrations exceeding 20% by volume, death will occur within 20 to 30 minutes. The above effects are important to note as inexperienced personnel may fail to think clearly and take proper action if suddenly exposed to even relatively low concentrations of Carbon Dioxide. Any person overcome by Carbon Dioxide should be moved immediately to a location where plenty of fresh air is available. Artificial respiration should be applied, as in the case of drowning. DO NOT use Carbon Dioxide as a stimulant. Contact a physician immediately. Persons rendered unconscious by exposure to Carbon Dioxide may possibly be revived if promptly removed from the Carbon Dioxide atmosphere. Direct contact with the liquid agent being discharged from the nozzle(s) will have a freezing effect and can cause frostbite if contact is made with the skin. The liquid phase of the agent vaporizes quite rapidly when coming into contact with the atmosphere, thus limiting the freezing hazard to the immediate vicinity surrounding the discharge nozzle(s). USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 2 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT Because Carbon Dioxide is a dense gas, it has a tendency to drift and settle in low-lying spaces in and around the discharge area. This agent migration can result in unacceptable concentrations of Carbon Dioxide in certain areas. Consideration must be given to warning area personnel of this possibility of agent migration. A means of ventilating Carbon Dioxide from enclosed, low-lying areas MUST be considered when designing a Carbon Dioxide suppression system. After a discharge, the protected hazard and all adjacent low-lying areas must be well ventilated before personnel are allowed to re-enter the space(s). After all traces of the fire have been extinguished, and the possibility of reignition eliminated, thoroughly ventilate the protected space. If there is a question as to the presence of Carbon Dioxide in a space, DO NOT ENTER THE SPACE UNTIL THE APPROPRIATE AUTHORITIES HAVE INSPECTED AND CLEARED THE AREA. 1.3.1 SAFETY RECOMMENDATIONS Safeguards must be provided to ensure the safety of personnel who may occupy areas protected by Carbon Dioxide. The following list taken from NFPA 12, Carbon Dioxide Extinguishing Systems, contains suggestions and recommendations related to the installation of all Carbon Dioxide Systems. 1) Provide aisle ways and exit routes. Keep them clear and well marked at all times. 2) Provide emergency lighting and directional signs, as necessary, to aid in quick evacuation of discharge areas. 3) Provide audible alarms inside and outside all protected areas that will operate immediately upon activation of the system. 4) Delay the discharge of Carbon Dioxide and the actuation for a sufficient period of time to allow evacuation of the protected space. 5) Provide only outward swinging, self-closing doors at all exit points from the hazard area(s). Where such doors could be latched or secured, provide “panic” hardware. 6) Provide warning and instructional signs at all entrances to, and inside of, all protected spaces. These signs should inform personnel that Carbon Dioxide is protecting the area. These signs may also contain information or instructions pertinent to the conditions of the specific hazard. 7) Provide for the prompt discovery and rescue of any personnel trapped, or rendered unconscious, in a protected space. This includes having self-contained breathing apparatus readily available, with personnel trained in its use and in rescue techniques. 8) Provide instructions and drills for all personnel in the proper procedures to follow in the event of a Carbon Dioxide discharge. This training should also include outside persons with access to protected spaces. 9) Provide a means of prompt ventilation of the protected area(s). Forced ventilation will often be necessary. Care must be taken to ensure that the Carbon Dioxide is dissipated, not merely moved to another location. 10) Carbon Dioxide is heavier than air and can collect in low-lying areas. Care must be taken when entering these areas after a discharge. 11) Provide any other safeguards that are deemed necessary to prevent injury to personnel. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 3 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.4 CARBON DIOXIDE CYLINDER ASSEMBLIES (P/N’S C70-100-N, C70-075-N, and C70-050-N) Fike Carbon Dioxide Cylinders are spun steel containers finished with a red gloss, baked enamel paint. The cylinders are available in three capacities: 50 lb. (22.7 kg), 75 lb. (34 kg), and 100 lb. (45.4 kg). Fike Carbon Dioxide Cylinders are equipped with a siphon tube to provide a complete discharge of the cylinder contents. The cylinders must be floor mounted with the discharge valve in the vertical (up) position. Horizontal mounting of the cylinders is not allowed. Each cylinder is factory filled to capacity, and partial fills are not allowed. The cylinders may be used in single or multiple cylinder applications as needed. Cylinders are shipped from the factory with a Safety/Shipping Cap installed. Filled cylinders MUST be secured during transport, and while in storage, in accordance with DOT and OSHA requirements. Upon installation, all cylinders shall be secured by cylinder straps or in a suitable racking arrangement. The Safety/Shipping Cap must only be removed after securing the cylinder(s). The caps should then be stored in a suitable, nearby area for reuse. WARNING: Never handle, move, weigh on a scale, or transport in any manner, any Carbon Dioxide cylinder, (full or empty) without the Safety/Shipping Cap firmly in place. If the cylinders are handled without this cap in place, serious injury and/or damage can result. CYLINDER DATA English Data (Metric Data) Description Cylinder Assy. P/N C70-050-N C70-075-N C70-100-N 50 lb. (22.7 kg) 8.50 in. *Dimension “A” (216 mm) 51.0 in. *Dimension “B” (1295 mm) 56.625 in. *Dimension “C” (1438 mm) 160 lbs. Avg. Shipping Weight (72.6 kg) D.O.T. Rating 3AA2015 *All dimensions are approximate 75 lb. (34 kg) 9.25 in. (235 mm) 56.0 in. (1422 mm) 61.625 in. (1565 mm) 220 lbs. (99.8 kg) 3AA2300 100 lb. (45.4 kg) 10.50 in. (267 mm) 58.0 in. (1473 mm) 63.625 in. (1616 mm) 296 lbs. (134.3 kg) 3AA2300 Cylinder Capacity R R CARBON DIOXIDE (CO )2 CYLINDER ASSEMBLY UN1013 Made in U.S.A. ASSEMBLY NO. Carbon Dioxide Extinguishing System SERIAL NO. GROSS WGT. TARE WGT. AGENT AGT. DANGER INSTALLATION Discharge of Carbon Dioxide into a confined space will lower the oxygen concentration to a point that will cause unconsciousness or death due to suffocation. Avoid exposure by evacuating and ventilating the space when Carbon Dioxide is discharged. "C" system built to withstand the forces exerted during system discharge. All discharge hoses must be connected to the manifold or piping system prior to installing any valve actuation devices. RECHARGE WARNING Contents under high pressure, (850 psi @ 70°F.) Make sure shipping cap is installed when shipping or handling an unsecured cylinder. Failure to do so may result in personal injury or property damage due to ciolent cylinder movement if valve is actuated or damaged. FIRST AID shall be recharged by authorized Fike distributors using recommended fill station equipment only. Remove all actuators and replace the shipping cap before transporting cylinders to the recharge station. MAINTENANCE "B" refilled or replaced. To be installed, inspected, maintained and tested in accordance with the National Fire Protection Association code No. 12, as well as all local or state codes that may apply. Carbon Dioxide fire suppression systems are designed to operate between 0 and 130°F. (-17 and 54°C). may result in rupture of the safety burst disc. Locate in an area with adequate ventilation. FOR INDUSTRIAL USE ONLY DO NOT REMOVE THIS LABEL "A" USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 4 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.5 CYLINDER VALVE ASSEMBLY (P/N C85-010) Fike Carbon Dioxide cylinders are equipped with a cylinder valve designed to hold the Carbon Dioxide agent in the cylinder until actuated. All Fike cylinders are shipped from the factory with the Cylinder Valve pre-assembled in a “Slave Valve” configuration. (Refer to Paragraph 1.5.1) The Cylinder Valve Assembly has a forged brass body and a stainless steel Pilot Valve Assembly. The valve o o actuation (opening) pressure is 100 – 110 psi (689 – 758 kPa) at 70 F (21.1 C). All cylinder valves are equipped with a Safety Relief device that will rupture should the pressure increase to 2,650 – 3,000 psi (18,271 – 20,684 kPa) and safely vent the cylinder contents to atmosphere. Each valve has a Pilot Port that has two specific functions: • • Fill port for charging the cylinder Actuator port for the manual / mechanical release functions USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 5 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.5.1 SLAVE VALVE ASSEMBLY All Fike Valves are shipped from the factory in a “Slave Valve” configuration. Slave Valves are actuated from the backpressure provided by a discharge of Carbon Dioxide into the piping manifold from the system’s Master Valve(s). The pressure from the discharge enters the discharge port of the Slave Valve via the flexible discharge hose, where it is then transferred to the piston chamber through an internal pressure port in the valve body. Due to the greater surface area of the piston, the pressure forces the main seal downward, thus opening the valve and discharging its entire contents. Refer to the Cylinder Valve Assembly Cross-Section in Paragraph 1.5 for a detailed view inside the valve assembly. 1/4"Tube Tee (C02-1359) Flex Hose (C02-1366) Plug Discharge Port Discharge Port Plug Slave Valve Master Valve Local Lever Actuator (C85-120) Connector (C85-1099) 1.5.2 MASTER VALVE ASSEMBLY The Slave Valve configuration is easily converted to a Master Valve configuration. Remove the two (2) plugs from the valve body: one (1) from the Pilot Port, and one (1) from the Top Pressure Port of the Cylinder Valve Assembly. The Local Lever Actuator Assembly (Refer to Paragraph 1.6.2) threads into the Pilot Port as shown above. In this configuration, the Carbon Dioxide in the cylinder passes through the stainless steel flex hose to the Top Pressure Port of the Cylinder Valve Assembly when the Local Lever Assembly is manually operated. The Carbon Dioxide pressure present in the top piston chamber causes the cylinder valve to open, thus allowing the Carbon Dioxide to discharge into the pipe manifold and, subsequently, to the remainder of the system piping network. Refer to the Cylinder Valve Assembly Cross-Section in Paragraph 1.5 for a detailed view inside the valve assembly. The release of the Carbon Dioxide may also be initiated by pressurizing the top piston chamber with Nitrogen from a Remote Pneumatic Actuator. NOTE: When two (2) Master Valves are required, use a Master Cylinder Adapter Kit (P/N C70-243) to complete the necessary connections. 1.6 VALVE ACTUATION Fike Master Valves can be actuated either mechanically or pneumatically. Manual actuation is accomplished using manual cable pull boxes and local lever actuators. Pneumatic manual release stations may also be located in the hazard area, or at a remote location. Local manual operation is also possible by physically operating the local lever actuators installed on the Master Valve(s). Local manual operation is not considered part of the normal system actuation mode and should only be used as a last resort in an emergency situation. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 6 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.6.1 PNEUMATIC ACTUATOR VALVE & CYLINDER ASSEMBLY (P/N C70-233) The Pneumatic Actuator Valve and Cylinder Assembly consists of a machined brass valve with a stainless steel lever mechanism and a spun steel container finished with a red gloss, baked enamel paint. The pneumatic Actuator Valve includes a pressure gauge to monitor the nitrogen pressure in the cylinder, and a Safety Relief Device that will rupture if the pressure increases to 2,650 – 3,000 psi (18,271 – 20,684 kPa). OPERATION: Remove the safety pin, followed by the operation of the lever at the top of the valve. This releases the Nitrogen in the container to the tubing connected to the Carbon Dioxide Master Valve(s) and Cylinder(s). This tubing is typically 1/4” (8 mm) stainless steel, 0.035” (0.9 mm) wall thickness or 1/4” NPT galvanized Schedule 40 or 80 pipe. The Carbon Dioxide is then released into the piping manifold as described in Paragraph 1.5.2. 3.5” (89 mm) Manual Override Lever Pressure Gauge 20.25” (514 mm) 5.75” (146 mm) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 7 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.6.2 LOCAL LEVER ACTUATOR (P/N C85-119) The Local Lever Actuator is also used to provide a means of manually discharging the Carbon Dioxide system at the Master Valve Cylinder location. Discharge is accomplished by removing the “ring-pin”, thus breaking the plastic seal and operating the lever 1/4 turn to the [OPEN] position. This action releases the pressure necessary to open the valve and discharge the contents of the cylinder(s). Systems with two (2) cylinders or less require one (1) Local Lever Actuator. Systems with three (3) or more cylinders require two (2) Local Lever Actuators that are tied together using a Connecting Link (P/N C70-228). (Reference: CFR Title 46, Section 95.15-10) NOTE: Local manual operation is not considered to be part of the normal system actuation mode and should only be used as a last resort in an emergency situation. 5.25" APPROX. [134mm] PULL PIN PULL PIN CABLE TIE CABLE TIE 1/4" JIC LEVER 1/8" NPT SIDE VIEW END VIEW 1/4" Tube Tee (C02-1359) Flex Hose (C02-1366) Discharge Port Master Valve Local Lever Actuator (C85-120) Connector (C85-1099) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 8 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.6.3 LATCH DOOR PULL BOX (P/N C70-242) The Latch Door Pull Box is used to provide mechanical operation of the Local Lever Manual Actuator from a remote location. The Latch Door Pull Box has a solid cast brass door that must be opened in order to access the pull handle. The pull handle is attached to a 1/16” (2 mm) diameter stainless steel actuation cable. A 3/8” NPT female opening is provided in the back of the enclosure for connection of the cable and piping system. The Pull Box is coated with a red, corrosion-resistant, polyurethane paint. A Corner Pulley may be attached directly to the back of the Pull Box if an immediate change of direction is necessary. Up to 100 ft. (30.5 m) of cable, and a maximum of fifteen (15) Corner Pulleys may be used for each cable run. NOTE: No more than four Pull Boxes may be used to operate any system. One of the Pull Boxes shall be located outside the space, at the main escape from the hazard. Do not locate a Pull Box where it will can be cut off or made inaccessible in the event of a fire. (Reference: CFR Title 46, Section 95.15-10) FOR FIRE OPEN DOOR PULL HANDLE HARD USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 9 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.6.4 CORNER PULLEY (P/N C70-241) Corner Pulleys are required on Fike Marine Carbon Dioxide systems whenever a remote pull box cable requires a o change in direction. Corner Pulleys are installed as part of the stainless steel cable system to provide 90 directional changes with minimal loss of force and elimination of induced cable kinking. The Corner Pulley is made of brass and threaded for 3/8” NPT pipe connections. Up to fifteen (15) Corner Pulleys may be used per Pull Box. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 10 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.6.5 STAINLESS STEEL CABLE (P/N C02-1344 = 50 ft.) (P/N C02-1343 = 250 ft.) The Stainless Steel Cable is used to mechanically connect the Latch Door Pull Box to the Local Lever Manual Actuator. The cable is a woven wire rope, 1/16” (2 mm) diameter, constructed of many individual wire threads woven into a 7 x 7 matrix for added strength and flexibility. The Stainless Steel Cable should be enclosed in 3/8” NPT piping. 1.6.5.1 ACCESSORIES The Stainless Steel Cable is attached to the various devices (Pull Box, Cable Junction Box, Local Lever Manual Actuator, etc.) using Oval Crimps (P/N C02-1345) that are compression fit devices which are installed using a Cable Crimp Tool (P/N C02-1348). A removable Cable Clamp (P/N C02-1347) is also available. 1.6.6 CABLE JUNCTION BOX ASSEMBLY (P/N C70-239) The Cable Junction Box Assembly allows manual activation of the Local Lever Manual Actuator from four (4) locations as allowed by CFR Title 46 Section 95.15-10. The inlet side has four 3/8” NPT connections, and the outlet side has a single 3/8” NPT connection. 20.75" (527 mm) WIRE LOOP (REQUIRES OVAL CRIMP) DIRECTION OF PULL 5.00" (127 mm) (COVER NOT SHOWN) 5.00" (127 mm) OVAL CABLE CRIMP (C02-1345) The cables from each Latch Door Pull Box are routed through the inlet of the Multiple Pull Control Box, while the outlet cable is routed to the Local Lever Manual Actuator as required. Each inlet and outlet cable is fitted with an Oval Crimp/Sleeve (P/N C02-1345), and the connection is crimped as shown above using a wire loop fed back through the Oval Crimp (Sleeve). Care must be taken to attach the inlet and outlet cables no more than five (5) inches (127 mm) from the outlet end of the Control Box. This will ensure that the cable is free to move through its full range of travel. The Multiple Pull Control Box is equipped with an easily removable cover that allows easy access to the cable assembly. The body and cover are made of carbon steel and painted with a corrosion-resistant, red polyurethane paint. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 11 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.7 FLEXIBLE DISCHARGE BEND (P/N C70-226) The Flexible Discharge Bend is used to provide the interconnection between the Carbon Dioxide cylinder and the actuation piping manifold. The Discharge Bend has a built-in check valve. When connected to a Cylinder Valve Assembly, the check valve is mechanically held open and allows the cylinder contents to be discharged. When disconnected from the cylinder, the check valve closes and prevents the flow of Carbon Dioxide from the discharge manifold if a system actuation should occur. A flow arrow is clearly stamped on the check valve to indicate the direction of flow. 20" (508 mm) CHECK VALVE FLOW 13/16"-16UNC-2A 1/2" NPT The Discharge Bend is a 5/8” I.D. (16 mm), double-wire braided hose with a 1/2” NPT connector on one end, and a 13/16”-16UNC-2A machine thread connector on the other end that threads into the discharge port of the Cylinder Valve Assembly. CAUTION: The Discharge Bend MUST be connected to the Cylinder Valve Assembly for the Carbon Dioxide System to be operational. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 12 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.8 NOZZLES AND ACCESSORIES All nozzles are supplied with orifices drilled to meet the requirements of the specific hazard. Nozzle orifice codes must be specified at the time of order. 1.8.1 RADIAL NOZZLE (P/N’S C80-041, 042, 043, 044, 045 & 046) The Radial Nozzle is used for most total flooding applications. The nozzles are primarily located around the o o perimeter of the protected space. Therefore, 180 nozzles are the most commonly used, but 360 nozzles are also available for special applications. The Radial Nozzle is made of brass and is available in 1/2”, 3/4”, and 1” NPT sizes with discharge orifice codes ranging from 3.5 to 25. Nozzle Strainers (P/N C02-1181) are required for Radial Nozzles with discharge orifice codes of (7) or smaller. Part Number: C80-041 C80-042 C80-043 C80-044 C80-045 C80-046 Size - NPT 1/2” 1/2” 3/4” 3/4” 1” 1” o o o o o o Discharge Pattern 360 180 360 180 360 180 Orifice Codes 3.5 - 13 3.5 - 13 10 - 19 10 - 17 15 - 25 15 - 25 "A" "C" "B" Radial Nozzle Dimensions USCG No: 162.038/12/0 U.L. Ex4447 1/2” NPT 3/4” NPT 1” NPT Dim. “A” 1.88” (48 mm) 2.19” (56 mm) 2.50” (64 mm) Dim. “B” 1.00” (25 mm) 1.25” (32 mm) 1.50” (38 mm) Dim. “C” 1.00” (25 mm) 1.25” (32 mm) 1.50” (38 mm) Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 13 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.8.2 BAFFLE NOZZLE (P/N C80-030) The Baffle Nozzle is used for total flooding applications. The nozzles should be located around the perimeter of o the protected space, with each nozzle providing a 180 pattern of coverage. The Baffle Nozzle is made of brass and is available in a 1/2” NPT size with discharge orifice codes ranging from 1 to 13.5. Nozzle Strainers (P/N C02-1181) are required for Baffle Nozzles with a discharge orifice code of 3 or smaller. 1/2" N.P.T. THREADS DISCHARGE ORIFICE 2-5/16" REF. (59 mm) 2-1/8" REF. (54 mm) 1.75" (45 mm) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 14 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.8.3 VENT NOZZLE (P/N C80-020) The Vent Nozzle is used for total flooding applications protecting ductwork, electrical cabinets, or any other application that requires direct mounting of the nozzle and a narrow discharge pattern. The Vent Nozzle is made of brass and is available in a 1/2” NPT size with discharge orifice codes ranging from 1 through 13.5. Nozzle Strainers (P/N C02-1181) are required on any nozzle with a discharge orifice code of 3 or smaller and must be ordered separately. 1/2" N.P.T. SUPPLY END 1/2" N.P.T. 1.688" (43 mm) 1.8.3.1 VENT NOZZLE FLANGE MOUNTING. KIT (P/N C80-1013) The Vent Nozzle Flange Mounting Kit is available as an option for mounting a Vent Nozzle directly to the exterior of an electrical cabinet, vent hood, or ductwork with an access hole that allows the Carbon Dioxide to be discharged directly into the protected hazard. A Teflon Sealing Disc is provided to prevent the discharge orifice from becoming “plugged” when the nozzle is used in a dirty environment. A new sealing disc is required after each system discharge. MOUNTING SURFACE 3/16" SHEET METAL SCREW TYP. OF 3 VENT NOZZLE BODY #8 LOCKWASHER TYP. OF 3 9/72" DIA. (7 mm) MOUNTING HOLE DISCHARGE CUTOUT 1.5" (38 mm) MINIMUM 2.0" (51 mm) MAXIMUM #8-32 X 1/4" SCREW TYP. OF 3 SEALING DISC 3.00" (76 mm) "O"-RING 2.5" (64 mm) BOLT CIRCLE MTG. FLANGE 2.188" (56 mm) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 15 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.8.4 ”S” TYPE NOZZLE (P/N C80-010) The “S” Type Nozzle is for total flooding applications that require a “soft” discharge that won’t disrupt loose materials or liquids. The “S” Type Nozzle is made of nickel-plated steel and has a brass nozzle orifice insert. The nozzle is available in 1/2” NPT size with discharge orifice codes ranging from 1 through 11. Nozzle Strainers (P/N C02-1181) are required on any nozzle with a discharge orifice code of 3 or smaller. 1.8.4.1 ”S” NOZZLE FLANGE MTG. KIT (P/N C80-1018) The “S” Nozzle Flange Mounting Kit is available as an option for mounting a “S” Nozzle directly to the exterior surface of an enclosure, hood, ductwork, etc. with an access hole that allows the Carbon Dioxide to be discharged into the protected hazard. A Teflon Sealing Disc (P/N C80-1007) is provided for the purpose of preventing the discharge orifice from becoming “plugged” when the nozzle is used in a dirty environment. A new sealing disc is required after each system discharge. 5/16" NUT, BOLT & WASHER SEALING DISC 5.125" O.D. (130 mm) 3.50" I.D. (89 mm) 3/8" DIA. (10 mm) HOLES LOCATED ON 4-3/8" (111 mm) B.C. CLAMPING FLANGE USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 16 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.9 CYLINDER RACKS All Carbon Dioxide cylinders must be secured using USCG approved cylinder strap arrangements or racking to prevent movement and/or damage to the cylinders and associated hardware. 1.9.1 SINGLE ROW RACKING Single Row Racking is one of the most commonly installed rack configurations. The Single Row Rack allows access to each cylinder in the system from the front of the rack installation. As the name implies, Single Row Racking will store the exact number of cylinders provided in the system in a single row. The racking is erected in the field using components selected for the specific rack capacity. All racking components are made from stainless steel, and all hardware supplied for assembly is stainless as well. Single Row Racks are available in 2-to-6 cylinder capacities with rack extensions of 2-to-6 cylinders each available as well. The cylinders are mounted on 12” (305 mm) centers with a maximum rack height of 86” (2184 mm). Single Row Racking Basic Rack Description Add-on Rack C70-040-20-N 2 Cylinder Rack C70-040-20A-N C70-040-30-N 3 Cylinder Rack C70-040-30A-N C70-040-40-N 4 Cylinder Rack C70-040-40A-N C70-040-50-N 5 Cylinder Rack C70-040-50A-N C70-040-60-N 6 Cylinder Rack C70-040-60A-N USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 17 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.9.2 DOUBLE ROW RACKING Double Row Racking with two (2) rows of cylinders, one row behind the other, allows for storage of a larger number of cylinders in a relatively small space. Access to the rear cylinder row requires the removal of the front cylinder row. Care must be exercised to protect removed cylinders from falling or tipping over during handling. All racking components are made from stainless steel, and all hardware supplied for assembly is stainless as well. Double Row Racks are available in 4-to-12 cylinder capacities with rack extensions of 4-to-12 cylinders available. The cylinders are mounted on 12” (305 mm) centers with a maximum rack height of 86” (2184 mm). Double Row Racking Basic Rack Description Add-on Rack C70-040-22-N 4 Cylinder Rack C70-040-22A-N C70-040-33-N 6 Cylinder Rack C70-040-33A-N C70-040-44-N 8 Cylinder Rack C70-040-44A-N C70-040-55-N 10 Cylinder Rack C70-040-55A-N C70-040-66-N 12 Cylinder Rack C70-040-66A-N USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 18 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.10 CHECK VALVE – 1/2” NPT THROUGH 2” NPT SIZES Check Valves are used to isolate the discharge manifold from other portions of the system as may be required by the specific installation. The Check Valve prevents undesired pressurization by blocking the flow of Carbon Dioxide from getting to the discharge valves into the manifold or piping sections that are intended for other purposes such as reserve supplies of agent. Check Valves are available in 1/2” NPT through 2” NPT sizes. The body is made from brass stock with female o pipe threads, and the seat material is Buna-N. The working pressure rating is 3,000 psi @ 100 F (20,685 kPa @ o o o 37.7 C), and the maximum recommended service temperature is 400 F (204 C). Check Valves – 1/2” NPT through 2” NPT Part No. Size (NPT) Dim. “A” Dim. “B” C02-1204 1/2” 2-3/4” (70 mm) 1” (25 mm) C02-1205 3/4” 3” (76 mm) 1-1/4” (32 mm) C02-1206 1” 3-5/8” (92 mm) 1-5/8” (41 mm) C02-1207 1-1/2” 4-5/16” (110 mm) 2-1/2” (64 mm) C02-1240 2” 5-13/16” (148 mm) 3” (76 mm) * All dimensions are approximate USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 19 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.10.1 CHECK VALVE – 1/4” (P/N C02-1340 and C02-1355) 1/4” Check Valves are used in the pneumatic actuation piping/tubing to prevent backpressure from a Carbon Dioxide discharge from filling and/or discharging into areas where it isn’t intended to. If multiple Remote Pneumatic Actuators are utilized, one Check Valve is required for each actuation line. The Check Valve(s) should be located downstream near the connection(s) to the Discharge Valves. o o The working pressure rating for the 1/4” Check Valve is 3,000 psi @ 100 F (20,685 kPa @ 37.7 C), and the minimum cracking pressure is 10 psi (68 kPa). P/N C02-1340 is used for pneumatic actuation lines utilizing schedule 40 or 80 piping. This valve has a brass hex body with 1/4” NPT connections of both ends. P/N C02-1355 is used for pneumatic actuation lines utilizing 1/4” stainless steel tubing. This valve has a stainless steel hex body with 1/4” tube connections on both ends. 2-3/8" (60 mm) 1/4" NPT C02-1340 2-3/8" (60 mm) 1/4" TUBE C02-1355 USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 20 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.11 HEADER VENT PLUG (P/N C02-1363) The Header Vent Plug is used to assure that no undesired pressure build-up may occur in a closed section of pipe, such as in the manifold or header piping between the Cylinder Discharge Valve(s) and a Pneumatic Time Delay or Stop Valve. The Header Vent Plug should be installed in a tee or coupling located in the piping system between the items listed above. The Header Vent Plug is a 1/2” NPT brass pipe plug with a 1/32” (0.8 mm) diameter bleed hole drilled through. An insignificant amount of CO2 leakage will occur during system discharge. BLEED HOLE 7/8" HEX (22 mm) 1.09" (28 mm) 1.12 HEADER SAFETY RELIEF (P/N C70-231) A dangerous situation may occur if CO2 becomes trapped in a closed section of discharge piping, such as before a Stop Valve or Pneumatic Time Delay. An increase in temperature may cause the pressure in the piping to rise to a dangerous level that may burst the pipe. This can cause extensive damage and potential injury to individuals in the immediate area. The Header Safety Relief is equipped with a rupture disc designed to open if the pressure in the piping increases to a level of 2,400 – 2,800 psi (16,547 – 19,305 kPa), thus safely releasing the CO2 pressure to atmosphere. The Header Safety Relief is fabricated from brass stock and is installed in a 1/2” NPT tee or coupling located in the closed piping section. 7/8" HEX (22 mm) 1-3/8" (35 mm) APPROX. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 21 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.13 PRESSURE SWITCH (P/N C70-202) The Pressure Switch is used to annunciate alarms and shutdown equipment and/or ventilation. The pressure connection is made to the system piping via a female 1/4” NPT connection. The Pressure Switch is operated pneumatically by Carbon Dioxide pressure from the discharge system piping network. The Pressure Switch is a double-pole, single-throw unit. Pushing the plunger on top of the unit downward will manually reset the switch to the “normal” position. The electrical load ratings for this switch are as follows: 15 Amps @ 125VAC, or 8 Amps @ 24VDC. 3-1/8" (79 mm) 4" (102 mm) Protection Systems Division Fike Corporation PRESSURE SWITCH D.P.S.T. TYPE ON C70-202 RAINTIGHT FACTORY MUTUAL SYSTEM 5-5/16" (135 mm) F Approved TO RESET PUSH PLUNGER IN C02-1074 1/2" (15 mm) CONDUIT HUB USCG No: 162.038/12/0 U.L. Ex4447 1/4" NPT PRESSURE CONNECTION Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) 2-13/16" (56 mm) 1/4" (6 mm) DIA. Page 22 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.14 PRESSURE TRIP ASSEMBLY (P/N C70-230) The Pressure Trip Assembly is used to provide a pneumatic release function to operate mechanical closers on doors, valves, dampers, etc. The Pressure Trip is operated pneumatically using the Carbon Dioxide pressure from the discharge piping network. The Pressure Trip Assembly may also be manually operated by pulling the manual release ring. The Pressure Trip Assembly is attached to the CO2 discharge piping via two 1/4” NPT female connections on either side of the device body. The Pressure Trip will operate properly regardless of which port is used as the inlet. The outlet port is connected to the next Pressure Trip or plugged with a 1/4” NPT pipe plug if another device is not necessary. 3-1/2" (89 mm) LOAD PIN 2" (51 mm) PULL RING 1/4" NPT PRESSURE CONNECTION USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 23 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.15 ODORIZER The odorizer (p/n 02-9868) is used to inject a small amount of wintergreen scent into the carbon dioxide agent as it flows through the piping network, discharging into the hazard area carrying a scent of wintergreen. The purpose of the wintergreen scent is to warn personnel that the area contains a concentration of carbon dioxide and precautions must be taken, either to leave the area immediately or secure proper breathing apparatus. The internal ampoule containing the oil of wintergreen must be replaced and the broken glass in the device must be cleaned out after each system discharge. This device is made of carbon steel, painted red with a 3/4” NPT male thread. NOTE: To meet the requirements of NFPA 12, all systems that are installed in Normally Occupied, Occupiable or Local Application hazards that can expose personnel to concentrations exceeding 4% for more than 1 minute must install 1 of the following: an olfactory device (wintergreen odorizer), carbon dioxide detectors or oxygen detectors or have an established and enforceable confined space entry procedure for the space being protected. 1.16 WEIGH BEAM ASSEMBLY (P/N C70-229) The Weigh Beam Assembly is used to determine the weight of Carbon Dioxide in a cylinder without the need to remove it from its secured position in a rack assembly. The Weigh Beam Assembly is a one-piece device that includes a lifting yoke, weigh beam, and a dial scale. To use the Weigh Beam Assembly, the Carbon Dioxide cylinders must be located in a cylinder rack that has a weigh bar attached, the flexible discharge bend(s) must be removed from the cylinder(s), and the cylinder clamps must be loosened or removed to allow the cylinder(s) to move freely. The Weigh Beam Assembly is readied for use by placing the eyehook over the weigh rail and installing the lifting yoke under the cylinder valve. The operator then lifts the cylinder by pulling down on the eye ring attached to the scale. When the weigh bar is in the horizontal position and the cylinder has been stabilized, the cylinder weight is obtained directly from the dial scale. Scale Range: 20 to 600 lbs. (9.1 to 272.2 kg) WEIGH BAR J-HOOK CYLINDER LIFTING YOLK 580 600 20 40 60 0 56 0 12 52 0 0 10 54 0 80 500 Protection Systems 160 480 140 Division Fike Corporation 180 460 200 440 0 42 22 0 1 Graduation = 2.5lbs. Capacity: 615lbs. x 2.5lbs. 24 0 0 40 38 0 360 SCALE FACE USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) NOT LEGAL FOR TRADE 340 320 300 0 26 280 LIFTING RING Page 24 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.17 PNEUMATIC TIME DELAY (30 SECONDS - C70-235) (60 SECONDS - C70-237) The purpose of the Pneumatic Time Delay is to delay the discharge of Carbon Dioxide for a specific period of time. This delay period is intended to allow time for: • • • Notification and evacuation of personnel from the protected space Shutdown and rundown of ventilation equipment Shutoff of fuel supply systems The delay and notification / shutdown period is accomplished by the Pneumatic Time Delay starting the countdown at the same time as the Pressure Switches and Pneumatic Sirens become activated by the CO2 discharge. Fike offers factory pre-set Pneumatic Time Delays with either a 30 or 60 second delays. The Pneumatic Time Delay is normally installed in the discharge piping manifold between the Master and Slave CO2 cylinders, but care should be taken to ensure that the manual override lever on the Time Delay is accessible from the floor. After completion of the pre-set time period, the Carbon Dioxide is allowed to continue through the discharge piping system. The Pneumatic Time Delay is equipped with a manual override lever. This lever allows for manual bypass of the time delay, thus resulting in the immediate discharge of the CO2 to the piping network. o o o o Operating Temperature Range: 0 F to +130 F (-18 C to + 54 C) NOTE: The pneumatic time delay is preset at the factory for either 30s or 60s. The delay Manual Override Lever time may vary from the rated delay time by 30% at the minimum intended use 1” NPT temperature to –15% at the maximum intended temperature. (Typical for Inlet & Outlet) If the delay time at 70°F is not within the range of +20% to – 0% of the rated delay time, the time delay shall be replaced. 3.5” (89 mm) 22.56” (573 mm) 5.75” (146 mm) Pneumatic Time Delay USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 25 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.18 PNEUMATICALLY OPERATED SIREN (P/N C02-1230) The Pneumatic Siren is used to warn personnel of an impending Carbon Dioxide System discharge. The same Carbon Dioxide pressure that starts the Pneumatic Time Delay is used to operate the siren. The siren is connected to the system piping via the 1/2” NPT connection located at the base of the siren. The Carbon Dioxide spins the turbine and sounds the siren from the beginning of the discharge throughout most of the discharge time. The siren operates at a minimum decibel level of approximately 90 dB @ 10 ft. (3.0 m). The siren is constructed of brass and stainless steel, and is finished with red finish coat. 3.875" DIA. (98 mm) 2.75" DIA. (70 mm) 13/64" DIA (5 mm) MTG. HOLE 1/2" NPT 3.563" (90 mm) 7.50" (191 mm) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 26 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.19 STOP VALVE The stop valve is used to prevent discharge of CO2 from the system discharge nozzles while the system is “locked out” for maintenance or other purposes. The stop valves are constructed of carbon steel with a stainless steel ball, Lubetal seats and a Buna-N body seal. The ¼ turn valve handle can be locked in either the “Open” or “Closed” positions. Locks and keys are not provided with the stop valves. A visual position indicator shows the current position of the valve at all times. The valves are available in nominal pipe sizes ½” through 1 ½”, and can be mounted in either the horizontal or vertical position. However, the recommended mounting configuration is in the horizontal position. See Section 4.8 for valve installation procedures. Stop / Maintenance Valve Specifications Part Number Nominal Size (NPT) Dim. “A” In. (mm) Dim. “B” In. (mm) Dim. “C” In. (mm) C02-1210 ½” 7.50 (191) 4.71 (120) 2.98 (76) C02-1211 ¾” 7.59 (193) 4.71 (120) 3.05 (77) C02-1212 1” 8.19 (208) 7.28 (185) 3.56 (90) C02-1213 1-1/2” 8.88 (226) 9.53 (242) 3.74 (95) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 27 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.20 INSTRUCTIONAL SIGNS 1.20.1 WARNING – PRIMARY ACTUATION – P/N C02-1367 The Warning – Primary Actuation Sign is 10” x 14” (254 mm x 356 mm) x .025” (0.6 mm) thick 304 stainless steel. All wording is etched black as shown below. This sign must be located next to each Pneumatic Actuator Assembly in accordance with CFR Title 46, Section 95.15-10(h). USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 28 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.20.2 WARNING – SECONDARY ACTUATION – P/N C02-1368 The Warning – Secondary Actuation Sign is 10” x 14” (254 mm x 356 mm) x .025” (0.6 mm) thick 304 stainless steel. All wording is etched black as shown below. This sign must be located next to the Latch Door Pull Box that operates the Stop Valve in accordance with CFR Title 46, Section 95.15-10(h). OPERATION OF THIS SECONDARY ACTUATION DEVICE MUST BE PRECEDED BY OPERATION OF THE PRIMARY ACTUATION DEVICE TO CAUSE CARBON DIOXIDE TO DISCHARGE. BEFORE OPERATING, BE SURE PERSONNEL ARE CLEAR OF THE DISCHARGE AREA. 1/4 DIA. HOLE TYP. 4 PLCS. C02-1368 USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 29 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.20.3 WARNING SIGN – MANUAL ACTUATION (C02-1388) The Warning – Manual Actuation Sign is 10” x 14” (254 mm x 356 mm) x .025” (0.6 mm) thick 304 stainless steel. All wording is etched black as shown below. This sign must be located next to the Local Lever Actuators, (or Pull Boxes that operate the Actuators), in accordance with CFR Title 46, Section 95.15-10(h). ACTUATION OF THIS DEVICE WILL CAUSE CARBON DIOXIDE TO DISCHARGE. BEFORE ACTUATING, BE SURE ALL PERSONNEL ARE CLEAR OF THE AREA. 1/4 DIA. HOLE TYP. 4 PLCS. C02-1388 NC USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 30 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.20.4 CAUTION – VACATE IMMEDIATELY / NEARBY SPACE (P/N C02-1390) The Caution – Vacate Immediately / Nearby Space Sign is 10” x 14” (254 mm x 356 mm) x .025” (0.6 mm) thick 304 stainless steel. All wording is etched black as shown below. This sign should be located in any nearby space where CO2 may accumulate after discharge. WHEN ALARM OPERATES VACATE AREA IMMEDIATELY. A CARBON DIOXIDE EXTINGUISHMENT DISCHARGED INTO A NEARBY SPACE MAY COLLECT HERE. 1/4 DIA. HOLE TYP. 4 PLCS. C02-1390 NC USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 31 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.20.5 WARNING – VACATE IMMEDIATELY / INSIDE ROOM (P/N C02-1391) The Warning – Vacate Immediately / Inside Room Sign is 10” x 14” (254 mm x 356 mm) x .025” (0.6 mm) thick 304 stainless steel. All wording is etched black as shown below. This sign should be located throughout the protected space in accordance with CFR Title 46, Section 95.15-10(h). USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 32 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT 1.20.6 WARNING – DO NOT ENTER (P/N C02-1392) The Warning – Do Not Enter Sign is 10” x 14” (254 mm x 356 mm) x .025” (0.6 mm) thick 304 stainless steel. All wording is etched black as shown below. This sign must be located at all entrances to the protected space in accordance with CFR Title 46, Section 95.1510(h). WHEN ALARM OPERATES DO NOT ENTER AREA UNTIL IT HAS BEEN VENTILATED. 1/4 DIA. HOLE TYP. 4 PLCS. CARBON DIOXIDE GAS MAY OCCUPY AREA. C02-1392 NC USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 33 of 34 Revision Date: July, 2015 SECTION 1 – EQUIPMENT This page intentionally left blank USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 34 of 34 Revision Date: July, 2015 SECTION 2 – SYSTEM CONFIGURATIONS 2.0 SYSTEM CONFIGURATION The following configurations depict typical Marine Carbon Dioxide System arrangements. The schematics of these configurations are intended to assist the system designer in selecting the arrangement and components best suited for a particular application. The symbol legend below defines the symbols used in the system configuration schematics for quick reference. Additionally, a description of the “sequence of operation” is also provided with each configuration to describe how each system works. 2.1 CONFIGURATION NO. 1 Configuration No. 1 depicts a system protecting a single space requiring no more than 300 lbs. (136kg) of Carbon Dioxide. The cylinders must be stored outside the protected space, and a remote mounted Pneumatic Actuator Valve and Cylinder Assembly is used to accomplish primary system actuation. An emergency, manual method of actuation is also provided at each Master cylinder via the manually operated Local Lever Actuator equipped with a pull pin to guard against accidental discharge. This system can also be equipped with a siren to warn personnel and a pressure switch to shut down ventilation and equipment. The schematic of this system configuration is shown below. NOTE: United States Coast Guard regulations mandate two separate and distinct actions for operation of any 3 system with more than 300 lbs. (136 kg.) of Carbon Dioxide. Had this configuration been larger than 6,000 ft or required more than 300 lbs. (136 kg.) of Carbon Dioxide, a Cable Operated Stop Valve would be required. Also note that the Carbon Dioxide cylinders are to be located outside the protected space. USCG No: 162.038/12/0 U.L. Ex4447 Carbon Dioxide Marine Manual P/N C06-019 (Rev 3) Page 1 of 2 Revision Date: July, 2015 SECTION 2 – SYSTEM CONFIGURATIONS This page intentionally left blank USCG No: 162.038/12/0 U.L. Ex4447 Carbon Dioxide Marine Manual P/N C06-019 (Rev 3) Page 2 of 2 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 3.0 SYSTEM DESIGN Protected spaces require total flooding Carbon Dioxide suppression systems designed in accordance with the following USCG categories: 1. Machinery Spaces 2. Electrical Equipment Spaces The Carbon Dioxide supply and flow rate requirements will vary depending upon the type of spaces being protected, and the gross volume of the space. To begin the design process, the space must first be identified and assigned into one of the categories listed above. Once this determination has been made, the required amount of CO2 can be determined as well as the required flow rates, pipe sizes, quantity of nozzles, etc. 3.1 MACHINERY SPACES Defined as a space that contains mechanical equipment for handling, pumping, or transferring flammable or combustible liquids as a fuel. Examples of Machinery Spaces include spaces that contain engines used for propulsion, oil filling stations, cargo pumps, or heating, ventilation and air conditioning machinery. Machinery Spaces generally house Class “B” (flammable liquids) combustibles. Fires in these areas tend to develop rapidly and intensify in a short amount of time. For this reason, it is important to introduce the extinguishing gas quickly to prevent the possibility of heat causing failure of bulkheads that would make it impossible to maintain the CO2 concentration after discharge. 3.1.1 SYSTEM DESIGN Machinery Spaces shall be designed for a 34% concentration based on the gross volume of the space. (Refer to the table below for the proper multipliers.) The system flow rate shall be designed to deliver 85% of this concentration within two (2) minutes from the start of the discharge. Refer to Section 3.3 for additional design considerations. 3.1.2 SYSTEM DESIGN – SPACES CONTAINING PROPULSION MACHINERY Machinery Spaces containing propulsion boilers or internal combustion propulsion machinery shall be designed for a 34% concentration based on the gross volume of the space. The gross volume shall also include the casing. If the flammable liquid (fuel) can drain or spread into an adjacent space, the sum of the compartment volumes must be used to determine the required amount of CO2, and the system shall be arranged to discharge into all of the affected compartments simultaneously. (Refer to the table below for the proper multipliers.) The system flow rate shall be designed to deliver 85% of this concentration within two (2) minutes from the start of the discharge. Refer to Section 3.3 for additional design considerations. TABLE 95.15-5(e)(4) FROM CFR TITLE 46, 95.15-5 3 3 Volume of Compartment – ft (m ) Volume Factors 3 3 Over Not Over (ft /lb. CO2) (m /kg CO2) 500 (14.15) 15 0.93 500 (14.15) 1,600 (45.28) 16 0.99 1,600 (45.28) 4,500 (127.35) 18 1.11 4,500 (127.35) 6,000 (169.90) 20 1.25 USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 1 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 3.2 ELECTRICAL EQUIPMENT SPACES Defined as a space containing electrical propulsion, power generating, and power distribution or control equipment. These spaces generally house Class “C” (electrical equipment) combustibles. Fires involving Class “C” hazards are typically deep-seated in nature. An initial discharge is usually provide to quickly suppress any surface flames, and an extended discharge is provided to maintain the CO2 concentration. The required concentration of CO2 must be maintained until the machinery can be stopped. 3.2.1 SYSTEM DESIGN The amount of CO2 required in these spaces for the initial discharge can be determined by dividing the gross volume of the space by the factors shown in the table below to provide a 50% concentration. The initial discharge must be completed within two (2) minutes. The amount of CO2 required for the extended discharge is dependant upon many factors including: the gross volume of the space, the time that it takes to stop the equipment, and the amount of air movement in the space. Sufficient CO2 must be provided to maintain a minimum 25% concentration until the equipment can be stopped. Should this be accomplished by the initial discharge, an extended discharge supply is not necessary. No specific discharge rates apply to the extended discharge. DESIGN FACTORS FOR ELECTRICAL EQUIPMENT SPACES 3 3 Volume of Compartment – ft (m ) Volume Factors (50%) 3 3 Over Not Over (ft /lb. CO2) (m /kg CO2) 2,000 (56.60) 10 0.62 2,000 (56.60) 12 0.75 3.3 ADDITIONAL DESIGN CONSIDERATIONS The design information listed previously provides a general overview of Marine CO2 Fire Suppression Systems based on USCG requirements. However, there are other factors beyond the type of combustible material being protected that may affect the design of a Marine CO2 system. This section describes the additional factors that influence system design. 3.3.1 UNCLOSEABLE OPENINGS Additional Carbon Dioxide must be added to compensate for all uncloseable openings in a protected hazard. The additional quantity must equal the total anticipated quantity of Carbon Dioxide that will be lost through the openings during the required agent hold time. Use the Leakage Compensation Chart on the next page to determine the leak rate for the area due to the uncloseable openings. Then multiply that leak rate by the total area of the opening(s) and the discharge time to determine the amount of additional CO2 required. (Reference: NFPA 12) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 2 of 15 Revision Date: July, 2015 Leakage Rate (lbs./ft2/min.) SECTION 3 – SYSTEM DESIGN Center of Opening (ft.) To determine the additional amount of Carbon Dioxide required to compensate for the leakage, proceed as follows: • Find the intersection of the vertical line representing the distance from the center of an opening to the top of the enclosure – in feet, to the diagonal line representing the design concentration of Carbon Dioxide. • Follow a horizontal line left to the “Leakage Rate” axis to determine the leakage rate value in 2 lbs./min./ft . • Determine the equivalent metric value by using the conversion formula of 1lb./min./ft = 4.89 2 kg/min./m . 2 EXCEPTION: If the opening(s) are in the side wall(s) only, the area of the wall opening can be divided by two (2). It is assumed that one-half of the opening will provide a fresh air intake while the other half allows Carbon Dioxide leakage. (Reference: NFPA 12) If the opening is in the ceiling only, no additional CO2 is required to compensate for this opening. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 3 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 3.3.2 VENTILATION It is Fike’s recommendation to shutdown and/or damper the ventilation system for any spaces protected with CO2 in accordance with CFR Title 46, Section 95.15-35. When a ventilation system cannot be shutdown, additional CO2 should be added to compensate for the loss of agent associated with the air leaving the enclosure. The volume of air leaving the enclosure is expressed in cubic feet per minute (cfm). This information is variable and will depend upon the type and capacity of the air handling system(s) present. The additional agent is supplied through the regular piping distribution system, and the amount must be determined by multiplying the volume moved (cfm) during the required holding period by the flooding factor used to determine the base quantity required. 3.4 NOZZLE SELECTION / PLACEMENT All Fike nozzle types are acceptable for the total flooding designs utilized for USCG applications. However, each nozzle has its own discharge characteristics and recommended range of flow rates. The following information will assist the system designer in determining which nozzle is the most appropriate to use for each application. USCG regulations require nozzles to be located in a manner that will give a “relatively uniform” coverage after discharge. Spacing the nozzles in a uniform pattern, (generally as a “ring” surrounding the space), reduces the time necessary for the gas to mix with the air and completely inert the space. Nozzles are generally placed at a height equal to 1/3 to 1/2 of the height of the space. Additional tiers of nozzles may be required for spaces with multiple levels and/or combustibles located at higher levels. 3.4.1 BAFFLE NOZZLE – P/N C80-030 o Baffle Nozzles provide a 180 , fan-shaped, discharge pattern that makes them acceptable for perimeter mounting around the protected hazard space. The Baffle Nozzle is brass and has a 1/2” NPT male pipe thread connection. BAFFLE NOZZLE – P/N C80-030 Flow Rates Maximum Minimum Maximum Recommended Linear Spacing 25 lbs./min. 160 lbs./min. See USCG Limits 20 ft. (11.3 kg/min.) (72.6 kg/min.) (Section 3.5.1) (6.1 m) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 4 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 3.4.2 VENT NOZZLE – P/N C80-020 Vent Nozzles are primarily installed in ductwork and small enclosures such as: shallow, covered pits, covered o trenches, and electrical cabinets. The discharge pattern is a narrow, 120 cone shape. Machined from brass stock, the Vent Nozzle has a 1/2” NPT pipe thread on each end. The 1/2” NPT male thread on the discharge end allows the Vent Nozzle to be mounted on the outside of a protected enclosure, duct, etc. This results in easier installation and access, as well as preventing contamination or blockage of the nozzle due to dirty airflows and/or atmospheres. Duct mounting is accomplished by using the Vent Nozzle Flange Mounting Kit, P/N C80-1013, complete with Mylar dirt seal. VENT NOZZLE – P/N C80-020 Flow Rates Maximum Minimum Maximum Recommended Linear Spacing 10 lbs./min. 120 lbs./min. See USCG Limits 15 to 20 ft. (4.5 kg/min.) (54.4 kg/min.) (Section 3.5.1) (4.6 to 6.1 m) 3.4.3 ”S” TYPE NOZZLE – P/N C80-010 “S” Type Nozzles can be used for all total flooding designs. They are particularly effective when specific objects within the hazard area need to be protected. The “S” Type Nozzle has a circular-shaped discharge pattern. The bell-shaped “S” Nozzle is spun from a single stock piece and provided with a 1/2” NPT female pipe thread connection. The nozzle uses a brass insert sleeve that contains 2 or 4 orifice holes, depending upon the orifice code value requested. With the orifice sleeve in position within the nozzle, an extremely “soft” CO2 discharge is realized, thus making the “S” Type Nozzle well suited for use in hazard areas were small, or loose, items could be dislodged and propelled about the protected space during a system discharge. The “S” Type Nozzle can be duct-mounted by using the “S” Type Nozzle Flange Mounting Kit, P/N C80-1018, complete with Mylar dirt seal. “S” TYPE NOZZLE – P/N C80-010 Flow Rates Maximum Minimum Maximum Recommended Linear Spacing 15 lbs./min. 130 lbs./min. See USCG Limits 30 ft. (6.8 kg/min.) (59.0 kg/min.) (Section 3.5.1) (9.1m) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 5 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 3.4.4 RADIAL NOZZLES – P/N’s C80-041, 042, 043, 044, 045 and 046 Radial Nozzles can be used for all total flooding designs. The Radial Nozzle is available in 1/2”, 3/4”, and 1” NPT o o female pipe thread sizes, and they are available in 180 and 360 discharge patterns. RADIAL NOZZLES – P/N C80-041 THRU C80-046 Nozzle Flow Rates Description C80-041 – 360 o 1/2” NPT C80-042 – 180 o 1/2” NPT C80-043 – 360 o 3/4” NPT C80-044 – 180 o 3/4” NPT C80-045 – 360 o 1” NPT C80-046 – 180 o 1” NPT Maximum Minimum Maximum Recommended Linear Spacing 15 lbs./min. 130 lbs./min. See USCG Limits 30 ft. (6.8 kg/min.) (59.0 kg/min.) (Section 3.5.1) (9.1m) 15 lbs./min. 130 lbs./min. See USCG Limits 30 ft. (6.8 kg/min.) (59.0 kg/min.) (Section 3.5.1) (9.1m) 15 lbs./min. 130 lbs./min. See USCG Limits 30 ft. (6.8 kg/min.) (59.0 kg/min.) (Section 3.5.1) (9.1m) 15 lbs./min. 130 lbs./min. See USCG Limits 30 ft. (6.8 kg/min.) (59.0 kg/min.) (Section 3.5.1) (9.1m) 15 lbs./min. 130 lbs./min. See USCG Limits 30 ft. (6.8 kg/min.) (59.0 kg/min.) (Section 3.5.1) (9.1m) 15 lbs./min. 130 lbs./min. See USCG Limits 30 ft. (6.8 kg/min.) (59.0 kg/min.) (Section 3.5.1) (9.1m) 3.4.5 NOZZLE STRAINER – P/N C02-1181 Nozzle Strainers are required on Radial Nozzles having an orifice code of seven (7) or less, and all other nozzles having an orifice code of three (3) or less. Nozzle Strainers do not come with the nozzles and must be ordered separately. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 6 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 3.4.6 NOZZLE ORIFICE DATA TABLE NOZZLE DATA Orifice Code 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 .0008 .0017 .0031 .0047 .0069 .0094 .0123 .0155 .0192 .0232 .0276 .0324 “S” Nozzle X X X X X X X X X X X X Vent Nozzle X X X X X X X X X X X X Radial Nozzle ---- ---- ---- ---- ---- X X X X X X X Baffle Nozzle X X X X X X X X X X X X 7 7.5 8 8.5 9 9.5 10 10.5 11 11.5 12 12.5 .0376 .0431 .0491 .0554 .0621 .0692 .0767 .0846 .0928 .1014 .1105 .1198 “S” Nozzle X X X X X X X X X ---- ---- ---- Vent Nozzle X X X X X X X X X X X X Radial Nozzle X X X X X X X X X X X X Baffle Nozzle X X X X X X X X X X X X 13 13.5 14 14.5 15 15.5 16 17 18 19 20 21 .1296 .1398 .1503 .1613 .1725 .1845 .1964 .2225 .2485 .2777 .3068 .3390 ---- ---- ---- ---- ---- ---- ---- ---- ---- ---- ---- ---- Vent Nozzle X X ---- ---- ---- ---- ---- ---- ---- ---- ---- ---- Radial Nozzle X X X X X X X X X X X X Baffle Nozzle X X ---- ---- ---- ---- ---- ---- ---- ---- ---- ---- 22 23 24 25 .3712 .4065 .4418 .4771 “S” Nozzle ---- ---- ---- ---- Vent Nozzle ---- ---- ---- ---- Radial Nozzle X X X X Baffle Nozzle ---- ---- ---- ---- Equiv. Single 2 Orifice Area (in ) Orifice Code Equiv. Single 2 Orifice Area (in ) Orifice Code Equiv. Single 2 Orifice Area (in ) “S” Nozzle Orifice Code Equiv. Single 2 Orifice Area (in ) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 7 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 3.5 DISCHARGE PIPING Distribution piping within the space shall be proportioned from the supply line to give proper distribution to the outlets without throttling. All piping shall also be provided in accordance with the following Title 46 CFR requirements: a) The piping, valves, and fittings shall have a burst pressure rating of not less than 6,000 psi. (40,816 kPa). b) All piping less than 3/4” NPT shall be at least Schedule 40, and all piping 3/4” or larger shall be Schedule 80. c) All piping, valves, and fittings of ferrous materials shall be protected inside and outside against corrosion unless specifically approved otherwise by the Authority Having Jurisdiction. d) A pressure relief valve set for 2,400 – 2,800 psi (16,327 – 19,048 kPa) shall be installed in the manifold to protect the piping in the event that all branch line shut-off valves are closed. e) All dead-end lines shall extend at least two (2) inches (51 mm) beyond the last nozzle drop and shall be closed with a pipe cap to form a dirt trap that will prevent clogging of nozzles. f) Pipe passing through living quarters shall not be fitted with drains or other openings within such spaces. Continuous piping runs without joints are preferred. 3.5.1 PIPE SIZE DETERMINATION The requirements for pipe sizes of branch lines are specified in the table that follows. Distribution piping within the protected spaces shall be proportioned from the supply line to give proper distribution to the outlets without throttling. SUPPLY PIPE LINE SIZES Maximum Quantity Minimum Maximum Quantity Minimum CO2 Required Pipe CO2 Required Pipe (lbs. / kg) Size (lbs. / kg) Size 100 / 45.4 1/2” NPT 2,500 / 1,134 2-1/2” NPT 225 / 102 3/4” NPT 4,450 / 2,018.5 3” NPT 300 / 136.1 1” NPT 10,450 / 4,740 4” NPT 600 / 272.2 1-1/4” 20,900 / 9,480.1 5” NPT 1,000 / 453.6 1-1/2” 33,600 / 15,240 6” NPT 2,450 / 1,111.3 2” SUPPLY PIPE LINE SIZES Pipe Internal Area 2 2 Pipe InternalArea 2 2 Size (in / mm ) Size (in / mm ) 1/2” NPT .3040 / 196 2-1/2” NPT 4.238 / 2,734 3/4” NPT .5330 / 344 3” NPT 6.605 / 4,261 1” NPT .7190 / 464 4” NPT 11.50 / 7,419 1-1/4” 1.283 / 828 5” NPT 18.194 / 11,738 1-1/2” 1.767 / 1,140 6” NPT 26.067 / 16,817 2” 2.953 / 1,905 USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 8 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 3.6 EQUIVALENT LENGTH VALUES The following are the equivalent length values for the various valves used on Marine CO2 systems. EQUIVALENT LENGTH PART NUMBER DESCRIPTION SCH. 40 SCH. 80 ft. (m) ft. (m) C02-1205 1/2” Check Valve 18 (5.5) 10 (3.1) C02-1205 3/4” Check Valve 24 (7.3) 14 (4.3) C02-1206 1” Check Valve --- 20 (6.1) C02-1207 1-1/2” Check Valve --- 33 (10.1) C02-1240 2” Check Valve --- 30 (9.1) C02-1212 1” Stop Valve --- 27 (8.2) C70-235 Pneumatic Time Delay, 30 seconds 85 (25.9) 51 (15.5) C70-237 Pneumatic Time Delay, 60 seconds 85 (25.9) 51 (15.5) CO2 Discharge Valve & Discharge Bend 25.4 (7.7) 13.5 (4.1) C85-010 & C70-226 USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 9 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 3.7 PIPE & NOZZLE CALCULATIONS FOR USCG SYSTEMS The following methods are used to calculate the pipe sizes and nozzle orifice diameters necessary to provide the CO2 to the protected space in the time constraints outlined in the previous paragraphs. • The first step is to determine the amount of CO2 required to protect the space: DETERMINE AMOUNT OF CO2 REQUIRED Hazard Type: Machinery Space (Engine Room) Dimensions = 20 ft. long x 20 ft. wide x 15 ft. high 3 Volume = 6,000 ft 3 6,000 ft ÷ 20 = 300 lbs. required = 300 lbs. supplied • Determine the Nominal Cylinder Outlet Area. This is done by multiplying the amount of CO2 supplied (in lbs.) by the constant [0.0022] in accordance with CFR Title 46, Section 95.15-5. (The minimum 2 nominal cylinder outlet area allowed is 0.110 in ) DETERMINE NOMINAL CYLINDER OUTLET AREA 2 300 lbs. Supplied x 0.0022 = 0.66 in • Determine the Internal Pipe Area for the main supply pipe. (Refer to Section 3.7.1) DETERMINE INTERNAL PIPE AREA OF MAIN SUPPLY PIPE 300 lbs. supplied = 1” NPT Pipe 2 Internal Area of 1” NPT Pipe = .7190 in • Determine the Total Nozzle Area required by multiplying the smaller value of the Nominal Cylinder Outlet Area vs. the Internal Pipe Area by 45% (0.45). NOTE: The Total Nozzle Area shall not exceed 85%, nor be less than 35% of the Nominal Cylinder Outlet Area or the Internal Pipe Area, whichever is the smaller value, in accordance with CFR Title 46, Section 95.15-5. DETERMINE TOTAL NOZZLE AREA 2 2 45% (0.45) of 0.66 in = .297 in USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 10 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN • Determine the Single Orifice Area required by dividing the Total Nozzle Area by the number of nozzles supplied. Refer to Section 3.4 for information regarding nozzle quantities, placement, etc. DETERMINE SINGLE NOZZLE ORIFICE AREA .297 in ÷ 1 Nozzle = .297 in .297 = 20 Orifice Code (Select the nozzle with the Equivalent Single Orifice Area in the Nozzle Orifice Data Table that most closely matches the area required) 2 • 2 Verify the validity of the chosen nozzle by first multiplying the Equivalent Single Orifice Area by the number of nozzles to obtain the Actual Total Nozzle Area. DETERMINE ACTUAL TOTAL NOZZLE AREA 2 .3068 (20 Orifice Diameter) x 1 Nozzle = .3068 in • Finish the calculation by verifying that the Actual Nozzle Area falls within the 35% to 85% limitation by dividing the Actual Nozzle Area by the Nominal Cylinder Area. DETERMINE ACTUAL NOZZLE AREA PERCENTAGE .3068 in ÷ .66 in = 0.46 = 46% 2 2 If the system falls within the limits stated, (Actual Nozzle Area Percentage = 35% to 85% of the Nominal Cylinder Area), the calculations are complete, and the system is deemed acceptable. If the system falls outside of these limitations, a change to the nozzles will be required. The options would be to change the number of nozzles in the system, or to take a large percentage of the Nominal Cylinder Area (perhaps 60% instead of 45%). USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 11 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 3.8 SAMPLE PROBLEM The following example is provided to give the designer an idea of the steps necessary to design a Marine CO2 system that is compliant with USCG requirements. The methods shown may or may not be applicable to the requirements of other marine approval authorities. The hazard being protected in this example is a unitized Engine Compartment and Storage Room for an offshore platform. The Engine Compartment houses a diesel generator, a couple of air compressor skids, and miscellaneous equipment that would be associated with such a hazard. The Storage Room contains flammable liquids and solvents associated with an Engine Room. The following steps describe the general design process for this example: • Determine the Hazard Type and Design Requirements. The Engine Compartment contain dieselpowered machinery, air compression equipment, and flammable liquids that generally fall within a Class “B” hazard type. A fire within this space will tend to develop quickly, and it will be important to introduce the CO2 into the protected space quickly. Therefore, this space will be designed in accordance with the requirements outlined for a Machinery Space. • Determine the Amount of Carbon Dioxide Required. This involves determining the hazard volume and the amount of gas required for both spaces. DETERMINE AMOUNT OF CO2 REQUIRED Hazard Type: Machinery Space (Engine Compartment) Dimensions (Engine Comp.) = 20’-0” long x 20’-0” wide x 15’-0” high 3 6,000 ft ÷ 20 = 300 lbs. required USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 12 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN • Determine the Nozzle Requirements. Two specific criteria should be considered when determining the nozzle requirements for a system: USCG flow limitations, and area coverage limitations. Referring to the pipe sizing chart provided in Section 3.5.1, it is determined that 1/2” NPT nozzles can flow a maximum of 100 lbs. in two minutes, and 3/4” NPT nozzles can flow a maximum of 225 lbs. in two minutes. Therefore, we know that multiple nozzles will be required for the Engine Compartment. To determine how many nozzles are required for the Engine Compartment, the area coverage must be considered. The first point to consider is that the USCG generally requires a “ring” of nozzles to be provided around the room to ensure uniform coverage and to reduce the time necessary for the gas to mix and completely inert the space. With this in mind, the area coverage limitations for the nozzles selected must be taken into account, with additional consideration given to obstructions within the protected space that would inhibit the “line-of-sight” coverage for each nozzle. Therefore, we have selected a coverage pattern involving a single 3/4” NPT Radial Nozzle for the Storage Room, and an additional seventeen (17) 1/2” NPT Radial Nozzles for the Engine Compartment (see drawings provided). From an empty volume standpoint, fewer nozzles could have been used. However, the diesel generators provide substantial obstructions within the volume that dictate the need for additional nozzles, and the uniform spacing requirement must be utilized throughout the entire volume. DETERMINE NOZZLE SUPPLY REQUIREMENTS 300 lbs. (Engine Comp.) ÷ 3 nozzles = 100 lbs. each = 1/2” NPT Nozzle • Determine the Release “Control” Requirements. Since this system requires 300 lbs. minimum, Configuration No. 1 should be applied. (See Section 2.0) Two separate and distinct functions are required to activate the system. Therefore, Pneumatic Actuator Valves or Cable Pull Boxes tied to the Local Lever Actuators on the Master CO2 Valves are required for the primary actuation. For the purpose of this example, Pneumatic Actuators have been selected. NOTE: Emergency actuation of the CO2 Cylinders can also be initiated by operating the emergency manual release (Local Lever Actuators) located on the Master CO2 Valves. • Determine the Auxiliary Device Requirements. Additional devices are required such as: Header Vents, Header Safety Reliefs, Warning Signs, etc. These devices should be provided and located in accordance with the requirements outlined previously in this section. • Determine the Tank Location and Piping Layout. This is largely dependent upon customer preferences, but for this type of system configuration, the CO2 cylinders must be located outside of the protected space, and the piping layout should accommodate the nozzle placement requirements. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 13 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN • Determine Pipe Sizes. The pipe sizes must be determined in accordance with the chart provided in Section 3.7.1 that was excerpted from CFR Title 46, Table 95.15-5 (e)(4). Refer to the Isometric Drawing provided for pictorial clarification. DETERMINE PIPE SIZES • Pipe Section CO2 Flow (lbs.) Pipe Size (NPT) 1–2 300 1” 2 – 101 100 1/2” 2–3 200 3/4” 3 – 102 100 1” 3 – 103 100 1/2” Perform USCG Hydraulic Calculations. The hydraulic calculations are completed as follows: 1. Determine the Nominal Cylinder Outlet Area. This is done by multiplying the amount of Carbon Dioxide supplied (in lbs.) by the constant [0.0022] in accordance with CFR Title 46, Section 95.15-5. (The minimum 2 nominal cylinder outlet area allowed is 0.110 in ) DETERMINE NOMINAL CYLINDER OUTLET AREA 2 300 lbs. supplied x 0.0022 = 0.66 in 2. Determine the Internal Pipe Area for the main supply pipe. (Refer to Section 3.7.1) DETERMINE INTERNAL PIPE AREA OF MAIN SUPPLY PIPE 300 lbs. supplied = 1” NPT Pipe 2 Internal Area of 1” NPT Pipe = 0.7190 in 3. Determine the Total Nozzle Area required by multiplying the smaller value of the Nominal Cylinder Outlet Area or the Internal Pipe Area by 45% (0.45). NOTE: The Total Nozzle Area shall not exceed 85%, nor be less than 35%, of the Nominal Cylinder Outlet Area or the Internal Pipe Area, whichever is smaller in accordance with CFR Title 46, Section 95.15-5. DETERMINE TOTAL NOZZLE AREA 2 2 45% of 0.7190 in = 0.3235 in 4. Determine the Single Orifice Area required by dividing the Total Nozzle Area by the number of nozzles supplied. Refer to Section 3.6.3 for information regarding nozzle quantities, placement, etc. DETERMINE SINGLE NOZZLE ORIFICE AREA 0.3235 in ÷ 3 Nozzle = 12 Orifice 2 USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 14 of 15 Revision Date: July, 2015 SECTION 3 – SYSTEM DESIGN 5. Verify the validity of the chosen nozzle by first multiplying the Equivalent Single Orifice Area by the number of nozzles to obtain the Actual Total Nozzle Area. DETERMINE ACTUAL TOTAL NOZZLE AREA 2 0.1105 (12 Orifice Code) x 3 Nozzle = 0.3315 in 6. Finish the calculation by verifying that the Actual Nozzle Area falls within the 35% to 85% limitation by dividing the Actual Nozzle Area by the Nominal Cylinder Area. DETERMINE ACTUAL TOTAL NOZZLE AREA PERCENTAGE 0.3315 in ÷ 0.66 in = 0.50 = 53% 2 2 Since this system falls within the limits state, (Actual Nozzle Area = 35% to 85% of the Nominal Cylinder Area), the calculation is complete, and the system is deemed to be acceptable. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 15 of 15 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.0 SYSTEM INSTALLATION 4.1 GENERAL REQUIREMENTS Fike Marine Carbon dioxide Fire Suppression System components are included as part of a total suppression system package. Pipe, fittings, electrical conduit and fittings, wire, hangers, brackets, and all normal mounting hardware are to be provided by the installing Fike Distributor or sub-contractor. These items are provided to suit the installation specifications and the requirements of the specific Carbon Dioxide system. All materials provided for a Carbon Dioxide Fire Suppression System installation must be new, free from all defects and imperfections, and shall of a grade and type that complies with the latest edition of NFPA 12, and this manual. The system installation shall be completed in accordance with the current issue of the following applicable codes and/or standards: • • • USCG Navigation and Vessel Inspection Circular NVIC 6-72 Department of Transportation (DOT) Code of Federal Regulations, Title 46 NFPA 12 – Carbon Dioxide Extinguishing Systems In the event of a conflict between the Code of Federal Regulations and NFPA Standard no. 12, the Code of Federal Regulations shall be the final authority. 4.2 PIPE AND FITTINGS The following paragraphs detail the specifications for materials normally used for the installation of Carbon Dioxide Fire Suppression Systems. All piping and fittings must comply with the requirements outlined in DOT Title 46 CFR, Part 56, “Piping Systems and Appurtenances”. 4.2.1 FERROUS PIPE The piping supplied for Fike Marine CO2 systems shall be galvanized or stainless steel in accordance with the following information. Black pipe is not acceptable for use. Galvanized steel pipe shall be either ASTM A-53 seamless or electric resistance welded, Grade A or B, or ASTM A-106, Grade A, B or C. Stainless steel pipe shall be 304 or 316 for threaded connections or 304, 316, 304L or 316L for welded connections. NOTE: ASTM A-53 Furnace Butt Weld Piping is not acceptable. High pressure Carbon Dioxide system piping components, 3/4” NPT and smaller, may utilize Schedule 40 piping components. 1” NPT through 4” NPT sizes must be a minimum of Schedule 80. High pressure Carbon Dioxide system piping components not specifically covered in this manual shall have a minimum burst pressure of 5,000 psi (34,470 kPa). 4.2.2 FITTINGS 1) Galvanized malleable or ductile iron fittings having a Class 300 rating shall be used through 2” NPT. Forged steel fittings must be used for all larger sizes. 2) Flanged joints upstream of any Stop Valve shall be Class 600. Flanged joints downstream of Stop Valves, or in systems without, may be Class 300. 3) Stainless steel fittings shall be type 304 or 316, wrought/forged (ASTM A-182), Class 3000, threaded or socketweld, for all sizes 1/4” through 4” NPT. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 1 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.2.3 FLANGED, WELDED AND MISCELLANEOUS FITTINGS Carbon Dioxide Fire Suppression piping systems may contain threaded, flanged, or welded joints utilizing malleable or ductile iron, and forged steel fittings. Where hex reducing bushings are used for one pipe size reduction, a 3,000 lb. forged steel fitting shall be used to maintain adequate strength. Where hex bushings are used for more than one pipe size reduction, Class 300 malleable or ductile iron fittings may be used. Suitable compression-type or flared fittings shall be used with compatible tubing. Brazed fittings may be used, o o provided the brazing alloy used has a minimum melting point of 1,700 F. (926 C). NOTE: Flush or face bushing shall not be used. 4.3 PIPING DISTRIBUTION SYSTEM Equipment installation shall be such that the components are located and arranged to facilitate inspection, test, recharge, and any other maintenance that may be necessary. Components must not be located where they will be subject to severe weather conditions, mechanical, chemical, or other damage that could render them inoperative. 4.3.1 DISCHARGE PIPING, TUBING AND FITTINGS Piping, tubing, and fittings must be installed in strict accordance with the system drawings and good commercial practices. The piping between the cylinders and the discharge nozzles must be the shortest route possible, with a minimum of fittings. The design engineer must approve any deviations to the pipe routing prior to installation. Piping must be reamed, free of burrs and ridges after cutting, welding, or threading. All threaded joints must conform to ANSI B1-20.1. Joint compound tape or thread sealant must be applied to the male threads of the joint, excluding the first two threads. All welded piping connections must be made in accordance with DOT Title 46 CFR, Part 57, “Welding and Brazing”. Each pipe section must be swabbed clean using a nonflammable cleaning solvent such as Perchlorethylene. All piping must be blown out with dry nitrogen, carbon dioxide, or compressed air prior to installing the discharge nozzles. Never use oxygen to blow out piping. Dirt traps must be installed at the end of each trunk line, nozzle branch, and feeder branch. A 2”-6” long (51-52 mm) nipple and pipe cap will provide the dirt trap configuration required. The piping system must be securely braced to account for discharge reaction forces and thermal expansion/contraction. Care must be taken to ensure the piping is not subject to vibration, mechanical, or chemical damage. Refer to ANSI B-31.1 (Power Piping Code) for additional bracing requirements. 4.3.2 PNEUMATIC ACTUATION PIPE AND TUBING The pneumatic actuation tubing must be 1/4” (6 mm) O.D. stainless steel x 0.035” (0.009 mm) thick wall tubing, or 1/4” NPT galvanized schedule 40 or 80 piping. The pipe or tubing used must be routed in the most direct manner, using a minimum of fittings. Pipe and fittings must comply with the requirements of NFPA 12, Sections 1 through 9. Tubing fittings can be flared or compression type. The pressure/temperature ratings of the manufacturer must not be exceeded. Piping and tubing must be reamed, free of burrs or ridges after cutting, threading or flaring. Upon assembly, pipe or tubing must be blown out with dry nitrogen, carbon dioxide, or compressed air. It must be securely braced and isolated from vibration, mechanical, or chemical damage. Check Valves shall be installed in the pneumatic actuation piping/tubing to prevent back-flow during a local (cylinder) actuation of the system. 4.3.2.1 PNEUMATIC ACTUATION PIPE / TUBING LENGTH LIMITATIONS 1/4” NPT Piping (Sch. 40): 1/4” NPT Piping (Sch. 80): 1/4” x 0.035” wall (6 mm x 1 mm) Tubing: USCG No: 162.038/12/0 U.L. Ex4447 300 ft. (91.5 m) Maximum 436 ft. (132.9 m) Maximum 450 ft. (137.2 m) Maximum Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 2 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.3.3 DISCHARGE MANIFOLD Securely attach the discharge manifold to the bulkhead or other structural member. The manifold must be level and the inlets aligned for connection to the cylinder valves. Manifolds larger than 2” NPT in size must be welded. 4.3.4 CLOSED PIPE SECTIONS All closed pipe section that could trap Carbon Dioxide shall be provided with a pressure relief device. This situation may occur if Stop Valves or Pneumatic Time Delays are incorporated into the Carbon Dioxide system piping. The Header Safety Relief has a 1/2” NPT threaded body and is installed in a tee or coupling located within the closed section of piping. Closed pipe sections are potentially created where Stop Valves, Pneumatic Time Delays, and Check Valves are used. The Header Vent Plug has a 1/2” NPT threaded body and is installed in a tee or coupling located at each end of the manifold. HEADER VENT TYP. OF 2 PLCS. HEADER SAFETY TYP. OF 2 PLCS. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 3 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.3.5 CHECK VALVES Install the Check and/or Stop Valves as shown on the system drawings. Apply Teflon tape or pipe compound to the male threads of the supply piping, excluding the first two threads. Valves larger than 2” NPT should be provided with flanged connections. IMPORTANT: All valves must be installed with the arrow on the valve body pointing in the direction of flow. CHECK VALVE MAIN RESERVE 4.4 CYLINDER ASSEMBLIES The CO2 cylinders must be located outside of the protected space, but as close to it as possible. If the cylinders are located adjacent to the protected space, the common bulkhead between the two spaces must be insulated and construction to A-60 class requirements. Cylinders must be located in an environment protected from the weather and where the ambient storage o o o o temperature does not exceed 130 F. (54.4 C), nor falls below 0 F. (-18 C). External heating or cooling may be required to maintain this temperature range. Position cylinders in the designated location(s) and secure in place with the mounting hardware provided. All cylinders must be supported on an elevated platform at least 2” (51 mm) above the deck. NOTE: Cylinders shall not be moved or transported without the safety/shipping cap securely installed on each cylinder. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 4 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.4.1 CARBON DIOXIDE CYLINDERS These instructions must be carefully performed, in the exact order given, when any cylinder or group of cylinders is installed. 1) Place fully charged cylinder(s) in a cylinder rack before removing the shipping cap. 2) Install the cylinder front rail and tighten bolts only enough to allow for turning of the cylinder(s) as may be required for alignment purposes. 3) Remove the cylinder shipping cap from the cylinder valve. Return all caps to the storeroom. 4) Turn the cylinder so that the valve is orientation in the proper direction, install the flexible discharge hose, and tighten the bolts on the cylinder front rail securely. 4.4.2 LOCAL LEVER ACTUATOR INSTALLATION The Local Lever (Manual) Actuator is installed as follows: 1) Remove the 1/8” NPT pipe plugs from the top port and actuation/fill port on the CO2 Valve. 2) Place Teflon tape on the 1/8” NPT pipe thread of the 1/4” JIC x 90 brass elbow (C02-1278) and install it in the top port of the Master Valve. Tighten securely and orientate the elbow with the Fike logo as shown. 3) IMPORTANT: Install Teflon tape on the Valve Connector (C85-1099) and thread into the fill/actuator port as shown. Failure to use tape on this connection can result in the threads becoming damaged or stripped. 4) Carefully align and thread the assembly in the Master Valve approximately five (5) turns until the assembly is snug. Some Carbon Dioxide (vapor) leakage will be observed. Continue tightening until the leakage stops and the assembly is oriented as shown below. 5) Install the stainless steel hose (C02-1366) between the elbows on the Local Lever Actuator and the elbow installed on top of the Master Valve. o 1/4"Tube Tee (C02-1359) Flex Hose (C02-1366) Plug Discharge Port Discharge Port Plug Slave Valve USCG No: 162.038/12/0 U.L. Ex4447 Master Valve Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Local Lever Actuator (C85-120) Connector (C85-1099) Page 5 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.4.3 MASTER CYLINDER ADAPTER KIT (C70-243) INSTALLATION Install the Master Cylinder Adapter Kit as follows: 1) Install the Local Lever Actuator as described in steps 2,3, and 4 of the previous section (4.4.2). 2) Remove the 1/8” NPT pipe plugs from the top port and actuation/fill port of the CO2 Valve. 3) Place Teflon tape on the 1/8” NPT pipe thread of two (2) 1/4 Tube to 1/8” NPT Male Adapters (C02-1357) and install in the top pressure ports of the two Master Valves. 4) Install the 1/4” SST Tube Cross to the Master Cylinder closest to the actuation line connection and tighten in accordance with the manufacturer’s instructions. 5) Install the 1/4” SST Tube Tee (C02-1359) to the remaining Master Cylinder and tighten in accordance with the manufacturer’s instructions. 6) Install the 24” long SST Hose (C02-1370) between the SST Cross and SST Tee as shown. Tighten fittings in accordance with the manufacturer’s instructions. 7) Install the loose end of the short SST hoses supplied with the Local Lever Actuator to the SST Cross and SST Tee as shown. Tighten fittings in accordance with the manufacturer’s instructions. 8) Install the actuation piping (or tubing) to the inlet of the SST Cross. An adapter will have to be supplied by the installation contractor as appropriate for the type of actuation line selected. 24" BRAIDED STEEL HOSE (C02-1370) 1/4" TUBE CROSS (C02-1358) 1/4" CHECK VALVE (TUBE OR NPT) *NOT INCLUDED 1/4" TUBE x 1/4" JIC ADAPTER (C02-1356) 1/4" TUBE TEE (C02-1359) 1/4" TUBE x 1/4" JIC ADAPTER (C02-1356) LOCAL LEVER ASSY. (C85-120) 1/4" TUBE x 1/8" NPT ADAPTER (C02-1357) 1/4" TUBE x 1/8" NPT ADAPTER (C02-1357) LOCAL LEVER ASSY. (C85-120) ACTUATION TUBING *NOT INCLUDED USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 6 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.4.4 NITROGEN CYLINDERS 1) Remove nitrogen cylinder valve protection cap. 2) Install nitrogen cylinder in position in mounting bracket. 3) Tighten sufficiently to hold cylinder in place while allowing cylinder to be manually rotated. 4) Manually rotate cylinder until cylinder valve discharge outlet is in the desired position. CAUTION: Nitrogen cylinders must be positioned so that the manual lever is readily accessible and cannot be obstructed during manual operation. 5) Securely tighten mounting bracket clamps and hardware. 6) Install manual lever assembly to cylinder valve, and tighten securely. 7) Connect pneumatic pressure piping. 4.5 PIPE AND NOZZLE INSTALLATION Carbon Dioxide system piping shall be installed according to the piping layout drawing(s) prepared by/for the Fike distributor, or the installing contractor. The drawings will show the proposed pipe routing, equipment and nozzle locations, general details, notes, and a piping isometric drawing showing pipe sizes, lengths, nozzle types, and orifice code numbers. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 7 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.6 INSTALLATION OF FLEXIBLE DISCHARGE HOSE TO PIPING Connect the Discharge Hose to the piping or manifold as shown on the system drawings. Apply Teflon tape or pipe compound to the male NPT threads; leaving the first two threads dry. The cylinders may have to be loosened to assure proper alignment. Make certain that no kinks are present in the hose. NOTE: Be certain to orientate the discharge hose correctly. The hose must be installed with the check valve end threaded into the valve body. DO NOT attempt to thread the 1/2” NPT pipe connection into the brass valve body. 13/16”-16UNC-2A 13/16"-16UNC-2A Connector CONNECTOR W/ w/ Check Valve CHECK VALVE 1/2"½”NPT NPT WARNING: Always connect the Discharge Hose to the manifold before making the connection to the Cylinder Valve Assembly. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 8 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.7 PRESSURE SWITCHES Pressure Switches must be connected to either the pilot piping or the discharge manifold, as shown on the system drawings. The preferred mounting position is upright. The electrical connections are either 1/2” (15 mm) conduit knockouts, or 1” NPT fittings. The pressure connection is provided through the 1/4” NPT pipe connection, stainless steel tubing, or flex hose connection to the discharge piping or manifold. The minimum operating pressure is 75 psi (517 kPa). 3" (76 mm) 4" (102 mm) 5-1/8" (130 mm) 1/4" NPT FEMALE, PORT `A' 1/2" (15mm) CONDUIT ENTRY OPERATED POSITION 2 MTG. HOLES 1/4" DIA. (8 mm) "NORMAL" STANDBY POSITION 1/4" (8 mm) PIPE, TUBE OR FLEX HOSE DISCHARGE PIPING USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 9 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.8 STOP VALVE The stop valve is installed in the discharge piping after the manifold, (if applicable), in a location that is accessible from the ground without being prone to accidental damage. It is also recommended that a union be installed on either side of the valve to facilitate removal if needed. After installation, the stop valve should be equipped with a suitable lock to secure the valve in the “open” or “closed” position depending upon the situation. Signage should also be provided to identify the stop valve, its purpose, and its operation requirements. Odorizer Stop Valve 4.9 ODORIZER The odorizer is installed in the distribution piping and should be located before the stop valve. This device has a 3/4” NPT male thread and is installed in the side outlet of a side/thru tee and must be installed in the upright position. After a system discharge, the ampoule and adaptor must be replaced. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 10 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.10 REMOTE PULL CABLE COMPONENTS Locate the Remote Pull Box(es) as shown on the system installation drawings. Connect the Pull Box(es) to the Cable Junction Box (if used) using 3/8” NPT, Schedule 40 piping. Do not run more than one cable in each pipe run. At each change in pipe direction, a Corner Pulley must be used. DO NOT bend the pipe. A Cable Junction Box MUST be used where more than one Pull Box is used to operate a system. Beginning at the Pull Box, remove the covers of each Corner Pulley and feed the 1/16” cable through the Pulley and into the 3/8” piping. Connect one end of the cable to the cable fastener in the Pull Box. Route the other end to the Stop Valve, taking up as much slack as possible, and reattach the Corner Pulley covers. After installation is complete, test the remote cable actuation for free travel and pull force, making certain that the cable doesn’t bind or kink, and the pull force doesn’t exceed the 40 lb. pull force limitation. PULL HANDLE COVER OVAL CABLE CRIMP BASE 1/16" SST CABLE 2 - HOLES FOR 1/4" SST MOUNTING SCREWS (NOT SUPPLIED WITH PULL BOX) 3/8" NPT FEMALE PULL BOX INSTALLATION USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 11 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.11 PNEUMATIC TIME DELAY The Pneumatic Time Delay must be installed between the Master and Slave Valves as shown on the system drawings, and as shown below. The Time Delay must be securely mounted to the bulkhead or other structural member with the mounting bracket. Make certain that the inlet and outlet ports are properly oriented. Both have 1” NPT fittings for connections to the piping network. A lever operator is provided on each Pneumatic Time Delay for the purpose of manually overriding the delay timing; allowing the system to begin discharging without further delay. Make certain that the flow arrow on the Pneumatic Time Delay Body is properly oriented in the direction of flow for the system. NOTE: The pneumatic time delay is preset at the factory for either 30s or 60s. The delay time may vary from the rated delay time by 30% at the minimum intended use temperature to –15% at the maximum intended temperature. If the delay time at 70°F is not within the range of +20% to –0% of the rated delay time, the time delay shall be replaced. MANUAL OVERRIDE LEVER TIME DELAY MASTER USCG No: 162.038/12/0 U.L. Ex4447 SLAVE Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 12 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.12 PNEUMATIC ACTUATOR CYLINDER & VALVE ASSEMBLY The Pneumatic Actuator Valve should be installed as follows: 1) Locate the mounting bracket (see below) in an area where the Pneumatic Actuator Valve will be protected from inclement weather by a suitable enclosure. Install clamps and hardware. 2) Remove the safety (shipping) cap and place the Pneumatic Actuator Valve in the mounting rack. Tighten sufficiently to hold cylinder in place while allowing cylinder to be rotated for alignment purposes. 3) Rotate the cylinder until the valve discharge outlet is in the desired position. 4) Install the Manual Lever Assembly. CAUTION: The Manual Lever Assembly MUST be installed with the piston in the “UP” position and the safety pin attached. The nitrogen cylinder must also be positioned so that the manual lever is readily accessible and cannot be obstructed during manual operation. 5) Securely tighten mounting bracket clamps and hardware. 6) Connect nitrogen pilot lines. 3/8” Dia. (9.5 mm) 3.0” Typ. 4 Places (76 mm) U-Bolt 12.25” (311 mm) 8.0” (203 mm) U-Bolt 4.0” (102 mm) USCG No: 162.038/12/0 U.L. Ex4447 1.75” (45 mm) Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) 5.75” (146 mm) Page 13 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.13 PNEUMATICALLY OPERATED SIREN Pneumatically Operated Sirens must be installed throughout the protected space, as shown on the system drawings, and they must be audible over any running machinery. Connect the siren(s) with 3/4" NPT Schedule 40 piping. A 3/4” x 1/2” reducing fitting will be required for the final connection at the Siren. A dirt trap and union should also be installed after the siren (see below). NOTE: Do Not use Teflon tape on the threaded connections directly leading to the Pneumatic Siren. Each Pneumatically Operated Siren uses 5.2 lbs. (2.4 kg) of Carbon Dioxide per minute. The quantity of CO2 provided for the system must be adjusted to compensate for the amount used by the siren(s). Because the Pneumatically Operated Siren uses CO2 taken from the Master Cylinder(s), it is important that a sufficient quantity of CO2 is provided for the operation of the remainder of the system. Therefore, no more than two (2) Pneumatically Operated Sirens may be installed per Master Cylinder. Based on flow rates and pressure drop, no more than 100 ft. (30.5 m) of 3/4” NPT pipe may be used to connect a maximum of two (2) Pneumatically Operated Sirens to a system. PNEUMATIC SIREN 0.90" (23 mm) DIRT TRAP 1/2" NPT PIPING 3/4" NPT PIPING 0.823" (21 mm) USCG No: 162.038/12/0 U.L. Ex4447 3/4" x 1/2" NPT REDUCER Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 14 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.14 PRESSURE TRIP ASSEMBLY Connect the Pressure Trip in the horizontal position as shown below. Connections to the discharge piping are made using 1/4” NPT Schedule 40 pipe or stainless steel tubing. The maximum load on the retaining ring is 100 lbs. (45.4 kg). Pressure Trips can be installed in series from a common pressure outlet fitting on the discharge piping. When using more than one (1) Pressure Trip on a common supply line, the 1/4” NPT outlet port on the last device must be plugged with a 1/4” NPT pipe plug to prevent leakage. 3.50" (89 mm) 3.625" (92 mm) 1/4" NPT PRESSURE INLET/OUTLET CONNECTION (TYP. OF 2) 9/32" DIA. (7 mm) TYP. OF 2 PLCS. 4.15 DISCHARGE NOZZLES After the piping has been blown free of debris, install the discharge nozzles in accordance with the system drawings. Make certain that the correct nozzle type, part number, and orifice size is installed at each location. 4.16 PRESSURE TESTING OF NEW INSTALLATION USCG regulations mandate pressure testing of new CO2 systems upon completion of the piping installation and before the cylinders are connected. A pressure test shall be applied as set forth below. Only CO2 or similar inert gases should be used for this test. 1) The piping from the CO2 cylinders to the Stop Valve shall be subjected to a pressure of 1,000 psi (6,803 kPa). The source of pressure shall be closed and it shall be demonstrated that the pressure in the system does not drop more than 150 psi (1,020 kPa) per minute for a two (2) minute period. 2) The individual branch lines to the various protected spaces from the Stop Valve shall be subjected to a test similar to that described above, with the exception being that the pressure used shall be 600 psi (4,082 kPa). For the purpose of this test, the distribution piping shall be capped within the space protected at the first joint ahead of the nozzles. 3) Small independent systems protecting spaces such as emergency generator rooms, lamp lockers, or etc. may be tested by blowing out the piping with air at a pressure of at least 100 psi (680 kPa). USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 15 of 16 Revision Date: July, 2015 SECTION 4 – SYSTEM INSTALLATION 4.17 SYSTEM OPERATION REQUIREMENT USCG regulations mandate two separate and distinct actions for operation of any system with more than 300 lbs. (136 kg) of CO2. Fike Marine CO2 systems with more than 300 lbs. (136 kg) of CO2 will NOT discharge into the protected space unless both the Pneumatic Actuator Valve Lever and the Stop Valve are operated. 4.18 REMOTE PNEUMATIC MANUAL OPERATION 1) Evacuate all personnel from the hazard area immediately; close all hatches, bulkheads, doors, etc. 2) Proceed to the Remote Pneumatic Actuator Valve for the appropriate hazard space. 3) Remove the Locking Pin from the Manual Lever located on top of the Pneumatic Actuator Valve. 4) Operate the Manual Lever by rotating the lever 180 . Be certain that the lever is rotated a full o 180 and is in the down-and-locked position. o NOTE: Siren(s) will start immediately upon this action. 5) Notify the appropriate personnel of emergency condition. WARNING: If the Pneumatic Time Delay fails to operate, use the manual lever located on top of the Pneumatic Time Delay to discharge the system without further delay. 4.19 EMERGENCY MANUAL OPERATION NOTE: This manual control is not part of the normal system actuation mode, and should only be used as a last resort or emergency condition. 1) Evacuate all personnel from the hazard area immediately; close all hatches, bulkheads, doors, etc. 2) Proceed to the CO2 Cylinder(s) for the specific hazard. 3) Remove the Locking Pin(s) from the Local Lever Actuator(s) located on the cylinder(s). 4) Operate the Lever Handle 1/4 turn. NOTE: Siren(s) will start immediately upon this action. 5) Notify the appropriate personnel of emergency condition. WARNING: If the Pneumatic Time Delay fails to operate, use the manual lever located on top of the Pneumatic Time Delay to discharge the system without further delay. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 16 of 16 Revision Date: July, 2015 SECTION 5 – MAINTENANCE AND INSPECTION 5.0 MAINTENANCE AND INSPECTION Fire extinguishing systems require proper care to ensure normal operation at all times. Periodic inspections must be made to determine the exact condition of the system equipment, and a regular program of systematic maintenance must be established to ensure proper operation of all Carbon Dioxide components. A periodic maintenance schedule should be followed, and an inspection log maintained for ready reference. At a minimum, the log should record: 1) 2) 3) 4) Inspection date Inspection procedure(s) performed Repair(s) performed as a result of inspection Name of inspector performing task If inspection identifies areas of rust or corrosion are present, immediately clean and repaint the area. Perform cylinder hydrostatic pressure testing in accordance with NFPA, DOT, and CGA requirements. WARNING: Carbon Dioxide and Nitrogen cylinder/valve assemblies must be handled, installed and serviced by trained personnel in accordance with the instructions contained in this manual and Compressed Gas Association (CGA) pamphlets C-1, C-6, G-6, and P-1. All persons responsible for inspection and maintenance should be familiar with the safety information provided in the Material Safety Data Sheets for Carbon Dioxide and Nitrogen prior to performing their functions. All pressurized equipment must be disabled prior to performing system maintenance. Observe all safety precautions applicable to handling Carbon Dioxide and Nitrogen pressurized equipment. Only qualified Fike Distributors or recharge facilities should recharge Fike Carbon Dioxide and Nitrogen cylinder/valve assemblies. 5.1 PREVENTIVE MAINTENANCE Perform preventive maintenance in accordance with the schedule referenced below: Preventive Maintenance Schedule Schedule Requirement Paragraph Reference Monthly Inspect hazard area system components Check Nitrogen cylinder pressure 5.1.1.1 5.1.1.2 Semi-Annually Check Carbon Dioxide cylinder weight(s) Test pressure switch(es) 5.1.2.1 5.1.2.2 Annually Verify operation of sirens and pressure switches Check Nozzle Screens for Blockage 5.1.3.1 5.1.3.2 Every 2 Years Inspect Carbon Dioxide distribution piping 5.1.4.1 Every 5 Years Inspect and/or hydrostatically test CO2 cylinders Inspect and/or hydrostatically test nitrogen cylinders Inspect and/or hydrostatically test flexible discharge bends 5.1.5.1 5.1.5.2 5.1.5.3 USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 1 of 9 Revision Date: July, 2015 SECTION 5 – MAINTENANCE AND INSPECTION 5.1.1 PREVENTIVE MAINTENANCE PROCEDURES, MONTHLY Prior to testing or maintenance of the CO2 system, all personnel must be evacuated from the protected space. 5.1.1.1 INSPECT HAZARD AREA SYSTEM COMPONENTS Inspect hazard area system components as follows: 1) Inspect all cylinders and equipment for damaged or missing parts. If equipment requires repair or replacement, refer to paragraph 5.4. 2) Ensure that access to hazard areas, remote Nitrogen or cable pull stations, discharge nozzles, and cylinders is clear and that there are no obstructions to the operation of the equipment or distribution of Carbon Dioxide. 3) Inspect 1/4” NPT fittings. Tighten loose fittings and replace all damaged components. If necessary, clean parts as directed in paragraph 5.2. 4) Inspect CO2 cylinder and valve assemblies for leakage or physical damage such as cracks, dents, distortion, or worn parts. If necessary, clean cylinder and associated parts. 5) Inspect cylinder straps, cradles and attachment hardware for loose, damaged or broken parts, corrosion, oil, grease, grime, etc. Tighten loose hardware and replace damaged parts. 6) Inspect flexible discharge hoses for loose fittings, damaged threads, cracks, rust, kinks, distortion, dirt and frayed wire braid. Tighten loose fittings and replace hoses if damaged. 7) Inspect discharge manifold for physical damage, corrosion and dirt. Inspect manifold support brackets and clamps for looseness and damage. Inspect connections to manifold for tightness. Inspect check valves, where applicable, for deformation, leakage, cracks, wear, corrosion, and dirt. Secure loose parts and replace damaged parts. 8) Inspect discharge nozzles for dirt and physical damage. Replace damaged nozzles with the same type and nozzle code. If nozzles are dirty or clogged, refer to paragraph 5.3. NOTE: Nozzles must never be painted or altered. If damaged, replace with nozzles that are the same type and manufacture, making certain that the same orifice drill code is stamped on the nozzle as the original being replaced. 9) Inspect pressure switches for deformation, cracks, dirt or other damage. Replace all damaged switches. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 2 of 9 Revision Date: July, 2015 SECTION 5 – MAINTENANCE AND INSPECTION 5.1.1.2 CHECK NITROGEN CYLINDER PRESSURE Check nitrogen cylinder for proper operating pressure. If the pressure loss exceeds 10% of the initial charge (adjusted for temperature), recharge with nitrogen to 1,800 psig at 70°F (12, 410kPa @ 21.1°C). See paragraph 5.8.2. Temperature Degrees F Degrees C 10 -12.2 12 -11.1 14 -10.0 16 -8.9 18 -7.8 20 -6.7 22 -5.6 24 -4.4 26 -3.3 28 -2.2 30 -1.1 32 0.0 34 1.1 36 2.2 38 3.3 40 4.4 42 5.6 44 6.7 46 7.8 48 8.9 50 10.0 52 11.1 54 12.2 56 13.3 58 14.4 60 15.6 62 16.7 64 17.8 66 18.9 68 20.0 70 21.1 Nitrogen Cylinder Fill Chart Pressure Temperature PSI kPa Degrees F Degrees C 1596.1 11005 72 22.2 1602.9 11052 74 23.3 1609.7 11098 76 24.4 1616.5 11145 78 25.6 1623.3 11192 80 26.7 1630.1 11239 82 27.8 1636.9 11286 84 28.9 1643.7 11333 86 30.0 1650.5 11380 88 31.1 1657.3 11427 90 32.2 1664.1 11473 92 33.3 1670.9 11520 94 34.4 1677.7 11567 96 35.6 1684.5 11614 98 36.7 1691.3 11661 100 37.8 1698.0 11708 102 38.9 1704.8 11755 104 40.0 1711.6 11801 106 41.1 1718.4 11848 108 42.2 1725.2 11895 110 43.3 1732.0 11942 112 44.4 1738.8 11989 114 45.6 1745.6 12036 116 46.7 1752.4 12083 118 47.8 1759.2 12129 120 48.9 1766.0 12176 122 50.0 1772.8 12223 124 51.1 1779.6 12270 126 52.2 1786.4 12317 128 53.3 1793.2 12364 130 54.4 1800 12411 3 3 Pressure PSI kPa 1806.8 12457 1813.6 12504 1820.4 12551 1827.2 12598 1834.0 12645 1840.8 12692 1847.6 12739 1854.4 12786 1861.2 12823 1868.0 12879 1874.8 12926 1881.6 12973 1888.4 13020 1895.2 13067 1902.0 13114 1908.7 13160 1915.5 13207 1922.3 13254 1929.1 13301 1935.9 13348 1942.7 13395 1949.5 13442 1956.3 13488 1963.1 13535 1969.9 13582 1976.7 13629 1983.5 13676 1990.3 13723 1997.1 13770 2003.9 13816 3 3 NOTE: Final density is 0.3359 lb.-moles/ft = 0.0752 SCF/in = 9.4098 lb./ft (150.73 kg/m ) USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 3 of 9 Revision Date: July, 2015 SECTION 5 – MAINTENANCE AND INSPECTION 5.1.2 PREVENTIVE MAINTENANCE PROCEDURES, SEMI-ANNUAL Prior to testing or maintenance of the CO2 system, all personnel must be evacuated from the protected space. 5.1.2.1 CHECK CARBON DIOXIDE CYLINDER WEIGHT The following is a description of the procedures necessary to verify the weight of agent in the CO2 cylinders using a Fike Weigh Beam device: 1) Disconnect flexible discharge hose from cylinder valve. 2) Loosen cylinder racking so cylinders are free to move vertically. Do not remove the front rail completely. WARNING: All Fike CO2 cylinders are equipped with pressure differential discharge valves. When actuated, the discharge valve will remain open and cannot be closed. Accidental actuation of the discharge valve on an unsecured and disconnected cylinder will result in a discharge thrust capable of propelling the cylinder to velocities that can cause severe property damage and/or bodily injury. Therefore, it is extremely important that these procedures are followed carefully. Cylinder removal or replacement must always be supervised to assure full compliance with the instructions in this manual. 3) Hook the scale on weighing rail, slip the yoke under cylinder valve and adjust lever. 4) Pull the lever downward until the cylinder is just clear of floor and the lever is horizontal. 5) Read weight directly off scale (scale is calibrated to compensate for the effects of leverage). To determine the weight of agent in the cylinder, deduct the empty weight (the empty cylinder weight is stamped on the cylinder label), and deduct 3.75 lbs. (1.7 kg) for the weight of the discharge head. The result is the amount of liquid Carbon Dioxide (charged weight) in the cylinder. 6) If the charged weight loss exceeds 10% of the required weight, forward the cylinder WITH THE SAFETY CAP INSTALLED to an authorized Fike Distributor or recharge facility. 7) After all Carbon Dioxide cylinders have been weighed, tighten clamps and reconnect flexible discharge bend(s) to cylinder valve(s). 5.1.2.2 TEST PRESSURE SWITCH Test each pressure switch as follows: 1) Contact the appropriate personnel and obtain authorization for shutdown of affected equipment or facilities. If necessary, disconnect all control wiring and test the pressure switch circuits with an ohmmeter. 2) Verify that the affected hazard area operations controlled by the pressure switch are operative. 3) Remove the cover plate and manually operate switch. Verify that the hazard area operations controlled by pressure switch operate as required. 4) Return pressure switch to “SET” position. Replace cover. 5) Re-activate all systems shutdown by pressure switch (power and ventilation systems, compressors, etc.). USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 4 of 9 Revision Date: July, 2015 SECTION 5 – MAINTENANCE AND INSPECTION 5.1.3 PREVENTIVE MAINTENANCE PROCEDURES, ANNUAL Prior to testing or maintenance of the CO2 system, all personnel must be evacuated from the protected space. 5.1.3.1 VERIFY OPERATION OF ALARMS AND PRESSURE SWITCHES Perform operational check of alarms and pressure switches as follows: WARNING: Checking of alarms and pressure switches according to this procedure will cause carbon dioxide to discharge. Before conducting this procedure, be sure all personnel are clear of the protected space. 1) Contact the appropriate personnel for authorization and notification of intentional sounding of alarm sirens and shutdown of affected equipment or facilities. 2) Check that affected hazard area operations, controlled by pressure switch(es), are operative. 3) Disconnect the main Carbon Dioxide supply from the system and use one (or more) separate cylinders (or compressed air) to pressurize the system. 4) Check that affected hazard area sirens sound properly 5) Verify that affected hazard area operations controlled by pressure switch(es) have been shutdown. 6) Return pressure switch to “SET” position. 7) Re-activate all systems shutdown by pressure switch(es) (power and ventilation systems, compressors, etc.). 5.1.3.2 INSPECT NOZZLE SCREENS Check all nozzle screens for blockage and remove any debris that may be present. 5.1.4 PREVENTIVE MAINTENANCE PROCEDURES, TWO (2) YEAR 5.1.4.1 INSPECT CARBON DIOXIDE DISTRIBUTION PIPING Blow out all distribution piping with air or CO2 to make sure that piping is not obstructed. WARNING: Do not use water or oxygen to blow out piping. 1) Remove all flexible discharge bends from CO2 cylinders. 2) Remove all caps on dirt traps to allow any foreign matter to blow clear. CAUTION: Secure and install safety rope or tape in the immediate area of discharge from these dirt traps to protect against personnel injury or equipment damage during this operation. 3) Install and discharge a test cylinder into system manifold. 4) Remove test cylinder and replace caps on dirt traps. 5) Reconnect flexible discharge bends and activate CO2 system. 6) Remove safety rope or tape protection. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 5 of 9 Revision Date: July, 2015 SECTION 5 – MAINTENANCE AND INSPECTION 5.1.5 PREVENTIVE MAINTENANCE PROCEDURES, FIVE (5) YEAR Prior to testing or maintenance of the CO2 system, all personnel must be evacuated from the protected space. 5.1.5.1 INSPECT AND/OR HYDROSTATICALLY TEST CO2 CYLINDERS Inspect and retest guidelines for CO2 cylinders: CAUTION: These guidelines do not apply to cylinders containing commodities other than CO2. All Fike CO2 cylinders are designed, fabricated, and factory tested to comply with DOT Title 49 CFR Regulations 2A-2015, 3AA-2015 or 3AA-2300, as stamped on each cylinder. All CO2 cylinders must be hydro-tested and marked in accordance with DOT Title 49 CFR requirements, as follows: 1) Any cylinder that has been discharged or removed from the vessel indicating five (5) years or more having elapsed from the date of the last hydrostatic test, as indicated by the marking on the cylinder shoulder, must be emptied, retested and remarked. 2) Any cylinder continuously in service on board a vessel, must be removed from the vessel, its contents discharged, and the cylinder retested and remarked after twelve (12) years have elapsed from the date of the previous test and marking. 3) A cylinder must be hydro-tested and remarked immediately if the cylinder shows evidence of distortion, damage, cracks, corrosion, or mechanical damage. Cylinders failing the hydrostatic test must be replaced. 5.1.5.2 INSPECT AND/OR HYDRO-TEST NITROGEN CYLINDERS Nitrogen cylinders must be hydro-tested every five (5) years in accordance with NFPA and DOT requirements. The cylinder must be hydro-tested immediately if the cylinder shows evidence of distortion, damage, cracks, corrosion, or mechanical damage. Cylinders failing the hydrostatic test must be replaced. 5.1.5.3 INSPECT AND/OR HYDRO-TEST FLEXIBLE DISCHARGE BENDS Flexible discharge bends and distribution piping must be hydro-tested every 5 years at a pressure of 2,500 psi (6,894 kPa). The pressure must be maintained for one (1) full minute. Observation shall then be made to note any distortion, or leakage. 1) If the test pressure has not dropped, and if the couplings have not moved, the pressure shall be released. The hose assembly shall then be considered to have passed the hydrostatic test if no permanent distortion has taken place. 2) Hose assemblies passing the test should be completely dried internally. If heat is used for drying, the maximum temperature shall not exceed 150°F (66°C). 3) Hose assemblies failing the above tests shall be so marked and destroyed. These hose assemblies must be replaced with new ones. 4) Hose assemblies passing the test shall be marked with the date of the test on the hose. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 6 of 9 Revision Date: July, 2015 SECTION 5 – MAINTENANCE AND INSPECTION 5.2 CLEANING Remove dirt from metallic parts using a lint-free cloth moistened with a dry cleaning solvent. Dry parts with clean, dry, lint-free cloth or air blow dry. Wipe nonmetallic parts with clean, dry, lint-free cloth. Remove corrosion with crocus cloth or any similar product. 5.3 NOZZLE SERVICE Service nozzles after use as follows: 1) Clean outside of nozzles with rag or soft brush. 2) Examine discharge orifices for damage or blockage. If nozzles appear to be blocked, remove nozzles and clean by immersing in dry cleaning solvent and drying thoroughly with lint-free cloth. Replace damaged nozzles. Nozzles must be replaced with same nozzle type and nozzle code number. 5.4 REPAIRS Replace all damaged parts found during inspection. Replacement procedures for Carbon Dioxide and nitrogen cylinders are provided below. Since replacement of other system components are simple, refer to installation drawings and component drawings for guidance. 5.5 REMOVAL OF CYLINDERS 5.5.1 CO2 CYLINDERS 1) Remove flexible discharge bends from all cylinder valves. 2) Install safety/shipping protective cap on each cylinder valve. 3) Remove cylinder racking front rail. 4) Remove cylinder(s). WARNING: Cylinder safety/shipping cap must always be in place to prevent damage to the cylinder valve during removal, handling, and transport. Damage to cylinder valve could cause cylinder to discharge resulting in possible equipment and property damage, or injury to personnel. 5.5.2 NITROGEN CYLINDERS 1) Remove manual lever assembly. 2) Carefully remove cylinder from bracket. 3) Screw safety/shipping cap onto cylinder. WARNING: When removing nitrogen cylinders, the manual lever must be in the closed position with locking pin installed. Manual lever in the open position will result in discharge of remaining contents of cylinder, resulting in inadvertent system activation, property damage, or possible bodily injury. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 7 of 9 Revision Date: July, 2015 SECTION 5 – MAINTENANCE AND INSPECTION 5.6 POST FIRE MAINTENANCE After a CO2 discharge, qualified fire suppression system maintenance personnel must perform post fire maintenance as directed in this section. Observe all warnings, especially those pertaining to the length of elapsed time before entering the hazard area. WARNING: Do not enter a space with an open flame or lighted cigarette. The possible presence of flammable vapors may cause re-ignition of vapors or an explosion. For deep-seated hazards, the space must be kept tightly closed until instructed otherwise by the responsible authorities after a system discharge. DO NOT permit anyone to enter the space until it is ventilated thoroughly. Prior to ventilating, nobody may enter without using self-contained breathing apparatus. After a discharge, the following will be required: 1) Recharge all Carbon Dioxide and nitrogen cylinders immediately after use. 2) Return all cylinders to a recognized Fike Distributor or qualified recharge facility. 3) Recharge cylinders in accordance with established recharge procedures. 4) If system was operated using a Nitrogen pilot cylinder, remove the manual lever from the nitrogen cylinder. This will vent nitrogen pressure from the actuation piping and reset the pressure operated valves on the Carbon Dioxide cylinders. Replace Nitrogen cylinder and reconnect piping. 5.7 CARBON DIOXIDE CYLINDER RECHARGE Carbon Dioxide cylinders must not be recharged without a hydro-test if more than five (5) years have elapsed since the last test. The hydro-test shall be performed in accordance with the requirements of DOT Title 49 CFR, paragraphs 173.301 through 173.308 and 173.324. After retest, cylinder must be thoroughly dried and free of water vapor. WARNING: When removing Carbon Dioxide cylinders, observe the following: 1) Each cylinder is factory equipped with a safety/shipping cap securely installed over the valve assembly. This cap protects the valve from damage during cylinder handling and transport. 2) The protective cap must be installed at all times, except when the cylinder is connected into the system piping, or being filled. 3) The safety/shipping cap must be stored in a secure space and be readily available for use. Never move or handle any cylinder without the safety/shipping cap installed. Carbon Dioxide cylinders should be recharged by a Fike authorized distributor or recharge facility in accordance with Fike Recharge Procedure C06-017. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 8 of 9 Revision Date: July, 2015 SECTION 5 – MAINTENANCE AND INSPECTION 5.8 NITROGEN CYLINDER RECHARGE Nitrogen cylinders must be recharged when the cylinder pressure gauge indicates a storage pressure below the normal charge of 1800 psig at 70°F (12,410 kPa @ 21.1°C), or immediately after discharge. Nitrogen used for charging must comply with Federal Specification BB-N-411, Grade A, Type 1. Copies of this specification may be obtained from Global Engineering Documents, 2625 S. Hickory St., Santa Ana, CA 92707. WARNING: Any area in which nitrogen is used or stored must be properly ventilated. A person working in an area where the air has become enriched with nitrogen can become unconscious without sensing the lack of oxygen. Never dispose of liquefied nitrogen in an indoor work or storage area. Recharge nitrogen cylinders as follows: Before recharging, the cylinder must be firmly secured by chains, clamps, or other devices to an immovable object such as a wall, structural I-beam or permanently mounted holding rack. 1) 2) 3) 4) 5) 6) Remove cylinder valve protection cap. Remove manual lever assembly and pressure isolation nut. Install appropriate nitrogen cylinder charging adapter to valve pilot check port. Connect nitrogen recharging supply hose to adapter. Tighten securely. Open nitrogen recharging control valve slowly until full nitrogen flow is obtained. Monitor recharging supply pressure gauge. Close recharging control valve when gauge indicates the proper cylinder pressure of 1,800 psi at 70°F (12,410 kPa @ 21.1°C). NOTE: A calibrated pressure gauge MUST be used for recharge purposes. DO NOT use the pressure gauge on the nitrogen cylinder. 7) Allow cylinder to cool to ambient temperature and recheck indicated pressure. 8) Open valve and add additional nitrogen as necessary to obtain full cylinder charge at ambient temperature (1,800 psi / 12,410 kPa). 9) Close valve and remove supply hose and charging adapter from nitrogen cylinder. 10) Reinstall pressure isolation nut, being sure to apply thread-locking adhesive to male threads. 11) Using a soap solution, thoroughly check nitrogen cylinder valve for leakage. Bubbles appearing in the solution indicate leakage that require further inspection and repair before the unit can be returned to service. 12) After completing the leak test, thoroughly clean and dry cylinder valve. 13) Ensure cylinder valve manual lever port is clean and dry. 14) Install protective cap to manual lever port and install cylinder valve protective cap. 15) Install charged cylinder as instructed previously, and reinstall manual lever assembly. USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 9 of 9 Revision Date: July, 2015 SECTION 6 – PARTS LIST 6.0 CARBON DIOXIDE SYSTEM PARTS LIST PART NUMBER DESCRIPTION 6.1 CYLINDER ASSEMBLIES C70-050-N 50 lb. (22.7 kg) Cylinder w/ Brass Valve C70-075-N 75 lb. (34.0 kg) Cylinder w/ Brass Valve C70-100-N 100 lb. (45.4 kg) Cylinder w/ Brass Valve 6.2 CYLINDER ACCESSORIES C70-233 Pneumatic Actuator Valve & Cylinder Assembly C85-120 Local Lever Actuator C70-243 Master Cylinder Adapter Kit C70-226 C70-228 Flexible Discharge Bend w/ Check Valve Connecting Link Assembly 6.3 NOZZLES WITH ACCESSORIES C80-010 "S" Nozzle C80-1018 Flange & Seal Kit for "S" type Nozzle C80-020-B Vent Nozzle (Brass) C80-020-S Vent Nozzle (Stainless Steel) C80-1013 Flange & Seal Kit for Vent type Nozzle C80-030 Baffle Nozzle (Brass) C80-041 C80-042 C80-043 C80-044 C80-045 C80-046 1/2" NPT Radial Nozzle / 360 Degree 1/2" NPT Radial Nozzle / 180 Degree 3/4" NPT Radial Nozzle / 360 Degree 3/4” NPT Radial Nozzle / 180 Degree 1" NPT Radial Nozzle / 360 Degree 1" NPT Radial Nozzle / 180 Degree 6.4 ACCESSORIES C70-227 CO2 Filling Adapter Assembly / Brass Valve C70-202 Pressure Switch Assembly / DPST C02-1231 Explosion-Proof Pressure Switch Assembly / DPST C70-230 Pressure Trip Assembly C02-1230 Pressure Operated Siren C70-235 C70-237 C02-1363 C70-231 IG71-240 Pneumatic Time Delay / 30 Seconds Pneumatic Time Delay / 60 Seconds 1/2" NPT Header Vent Plug / Low Pressure 1/2" NPT Header Safety Release / High Pressure Odorizer Assembly 6.5 CHECK VALVES C02-1204 1/2" NPT Check Valve (Brass) C02-1205 3/4" NPT Check Valve (Brass) C02-1206 1" NPT Check Valve (Brass) C02-1207 1-1/2" NPT Check Valve (Brass) C02-1240 2" NPT Check Valve (Brass) 6.6 SIGNS C02-1367 C02-1368 C02-1388 C02-1390 C02-1391 C02-1392 USCG No: 162.038/12/0 U.L. Ex4447 Warning Sign / Primary Actuation Warning Sign / Secondary Actuation Warning Sign / Manual Actuation Caution Sign / Vacate Immediately – Nearby Space Warning Sign / Vacate Immediately – Inside Space Warning Sign / Do Not Enter Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 1 of 4 Revision Date: July, 2015 SECTION 6 – PARTS LIST PART NUMBER DESCRIPTION 6.7 UNI-STRUT CYLINDER RACK ASSEMBLIES / SINGLE ROW C70-040-20-N 2 Cylinder Rack Assembly C70-040-30-N 3 Cylinder Rack Assembly C70-040-40-N 4 Cylinder Rack Assembly C70-040-50-N 5 Cylinder Rack Assembly C70-040-60-N 6 Cylinder Rack Assembly 6.8 UNI-STRUT ADD ON RACK ASSEMBLIES / SINGLE ROW C70-040-20A-N 2 Cylinder Rack Add On C70-040-30A-N 3 Cylinder Rack Add On C70-040-40A-N 4 Cylinder Rack Add On C70-040-50A-N 5 Cylinder Rack Add On C70-040-60A-N 6 Cylinder Rack Add On 6.9 UNI-STRUT CYLINDER RACK ASSEMBLIES / DOUBLE ROW C70-040-22-N 4 Cylinder Rack Assembly C70-040-33-N 6 Cylinder Rack Assembly C70-040-44-N 8 Cylinder Rack Assembly C70-040-55-N 10 Cylinder Rack Assembly C70-040-66-N 12 Cylinder Rack Assembly 6.10 UNI-STRUT ADD ON RACK ASSEMBLIES / DOUBLE ROW C70-040-22A-N 4 Cylinder Rack Add On C70-040-33A-N 6 Cylinder Rack Add On C70-040-44A-N 8 Cylinder Rack Add On C70-040-55A-N 10 Cylinder Rack Add On C70-040-66A-N 12 Cylinder Rack Add On 6.11 CYLINDER RACKING ACCESSORIES C70-229 Weigh Beam w/ Scale, Brass Valve 6.12 CYLINDER RACKING SPARE PARTS C70-1114-2 Center / Front / Weigh Rail – 2 Cylinder C70-1114-3 Center / Front / Weigh Rail – 3 Cylinder C70-1114-4 Center / Front / Weigh Rail – 4 Cylinder C70-1114-5 Center / Front / Weigh Rail – 5 Cylinder C70-1114-6 Center / Front / Weigh Rail – 6 Cylinder C70-1111 C70-1113 02-4232 02-4229 02-4233 Cylinder Saddle for 50, 75, or 100 lb. (22.7, 34, or 45.4 kg) Cylinder Vertical Post Weigh Bar Bracket Post Base, Single or Double Row Rack Tee Bracket, Center / Weigh Rail Support 02-4218 C02-1209 C02-1208 C02-1214 Nut, 1/2" UNC, Special Uni-strut Connection Nut, 1/2" UNC Rod, 1/2" x 12-1/2” lg. (15 mm x 317.5 mm) / Single Row Rod, 1/2" x 24" lg. (15 mm x 609.6 mm) / Double Row Rack USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 2 of 4 Revision Date: July, 2015 SECTION 6 – PARTS LIST PART NUMBER DESCRIPTION 02-4372 02-4373 02-4231 Lock Washer, 1/2" (15 mm) Flat Washer, 1/2" (15 mm) Nut Coupler, 1/2" X 1-3/4" (15 mm x 44.45 mm) Long 6.13 SPARE PARTS FOR CO2 HARDWARE C85-010 Brass Cylinder Valve Assembly C85-1100 Pilot Valve Assembly C85-1087 Main Valve Seal Assembly C85-1077 Main Valve Retainer C02-1273 Spring for Main Valve Seal C02-1289 Washer for Main Valve Seal Retainer C85-1094 C85-1002 C02-1015 Safety Disc Nut Safety Disc Safety Disc Washer C02-1282 C02-1276 C02-1150 C02-1175 C02-1277 O-Ring for Top Cap O-Ring for Piston (Top / Large) O-Ring for Piston (Bottom / Small) O-Ring Piston Retainer O-Ring for Pilot Valve C85-120 C02-1027 C02-1359 C02-1366 C02-1280 02-2213 Local Lever Actuator Ring Pin for Manual Actuator Lever Tube Tee, ¼” (6mm) – Stainless Steel Hose / Flexible – Stainless Steel Elbow / 1/4" (6mm) x 1/4” (6 mm) JIC – 90° Brass Security Seal C85-1099 C70-1107 C70-1108 C70-1109 Connector Fitting Siphon Tube – 50 lb. (22.7 kg) Cylinder Siphon Tube – 75 lb. (34.0 kg) Cylinder Siphon Tube – 100 lb. (45.4 kg) Cylinder C02-1181 C02-1177 C80-1011 C02-1175 C85-1002 C02-1173 Strainer / Vent or "S" Nozzle Sealing Disc / Flange & Seal Kit – "S" Nozzle Sealing Disc / Flange & Seal Kit – Vent Nozzle O-Ring / Flange & Seal Kit Rupture Disc – 1/2" (15 mm) Header Safety Release Cylinder Nameplate (Non U.L.) 6.14 STOP VALVE C02-1210 1/2" NPT Stop Valve C02-1211 3/4" NPT Stop Valve C02-1212 1" NPT Stop Valve C02-1213 1-1/2" NPT Stop Valve 6.15 CABLE COMPONENTS & ACCESSORIES C70-239 Cable Junction Box Assembly C70-242 Cable Pull Box C70-241 Corner Pulley C02-1344 Stainless Steel Cable, 1/16” (2 mm) dia. x 50 ft. (15.2 m) long C02-1343 Stainless Steel Cable, 1/16” (2 mm) dia. x 250 ft. (76.2 m) long C02-1345 Oval Crimp (Sleeve) C02-1347 Removable Crimp C02-1348 Crimping Tool C02-1349 Cable Cutter USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 3 of 4 Revision Date: July, 2015 SECTION 6 – PARTS LIST This page intentionally left blank USCG No: 162.038/12/0 U.L. Ex4447 Marine Carbon Dioxide Manual P/N C06-019 (Rev 3) Page 4 of 4 Revision Date: July, 2015