PROJECT TIME MANAGEMENT USING MS PROJECT Project Time Management Using MSP EMGT 5430.01 (Week 4 IA) Lokesh Reddy Patturu – 2251906 Komal Nagalla- 2148816 MS in Engineering Management, UHCL PROJECT TIME MANAGEMENT USING MS PROJECT Question 1 PERT (10 pts) The Denver Iron & Steel Company is expanding its operations to include a new drive-in weigh station. The weigh station will be a heated/air-conditioned building with a large floor and small office. The large room will have the scale, a 15-foot counter, and several display cases for its equipment. Before erection of the building, the project manager evaluated the project using PERT analysis. The activities with their corresponding times were recorded in Table 1. # Activity Optimistic Most likely Pessimistic 1 Preceding Tasks Lay Foundation 8 10 13 2 Dig hole for scale 5 6 8 1 3 Insert scale bases 13 15 21 2 4 Erect frame 10 12 14 3 5 Complete building 11 20 30 4 6 Insert scales 4 5 8 5 7 Insert display cases 2 3 4 6 8 Put in office equipment 4 6 10 7 9 Finishing touches 2 3 4 8 10 Request inspection 1 2 3 5 11 Complete inspection 2 5 10 10 1. Develop MS project Gantt chart and display the critical path. (Note that you have to convert three parameters to the expected task duration using the following formula (You may use Excel for this calculation, and this number should be given as a task duration in the MSP): Task Duration = [Optimistic + 4* Most likely + Pessimistic]/6 PROJECT TIME MANAGEMENT USING MS PROJECT Optimisti c 8 5 13 10 11 4 2 4 2 Most likely 10 6 15 12 20 5 3 6 3 Pessimisti c 13 8 21 14 30 8 4 10 4 Preceding Tasks Request inspection 1 2 3 5 Complete inspection 2 5 10 10 # Activity 1 2 3 4 5 6 7 8 9 1 0 1 1 Lay Foundation Dig hole for scale Insert scale bases Erect frame Complete building Insert scales Insert display cases Put in office equipment Finishing touches Below is Gantt chart showing the critical path for the given task. 1 2 3 4 5 6 7 8 Duration 10.17 6.17 15.67 12 20.17 5.33 3 6.3 3 2 5.3 PROJECT TIME MANAGEMENT USING MS PROJECT Question 2. (10 pts) Consider the following network for a computer training class: Note that the number inside parenthesis represents the duration of the task; Construct the Gantt chart and display the critical path. A(7) 2 B(3) E(2) 1 4 C(6) The critical path is A-B-E. 3 D(3) 5 PROJECT TIME MANAGEMENT USING MS PROJECT Question 3. Handling Dependency. Please draw the following network diagram using MSP and compute critical tasks and critical path in MSP. (10 pts) Use the following assumptions: All task durations are one day. PROJECT TIME MANAGEMENT USING MS PROJECT The Critical path is A-B-C-D-E.