CERT. الشركة الوطنية لنقل الكهرباء 1 2 3 NO. DESCRIPTION CHK’D APP’D NATIONAL GRID SA REVISIONS DEPT.: E&DD SCOPE OF WORK & TECHNICAL SPECIFICATIONS PREP. BY: NAME SAMI DATE: FOR 11 / 02 / 2021 <<Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah>> APPROVED (110KV UNDERGROUND CABLES PORTION) BY: APP DATE: 22 / 02 / 2021 PTS – 20WC1033 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 1 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA TABLE OF CONTENTS DESCRIPTION SECTION I Page INTRODUCTION GENERAL PROJECT DESCRIPTION PROJECT SUMMARY ABBREVIATIONS 5 5 5 6 1 2 3 NO. 1.01 1.02 1.03 1.04 REVISIONS II DEPT.: E&DD PROJECT INTERFACE 2.01 GENERAL INTERFACE 2.02 INTERFACE WORK 7 8 PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 III 3.01 3.02 3.03 3.04 3.05 3.06 3.07 APPROVED BY: 3.08 APP DATE: 22 / 02 / 2021 3.09 3.10 3.11 CERTIFIED BY: 3.12 3.13 3.14 3.15 3.16 3.17 3.18 CER DATE 00 / 00 / 0000 3.19 3.20 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. BASIC REQUIREMENTS AND GUIDELINES GENERAL CONDITIONS KICK-OFF MEETING BASE DESIGN PHASE BASE DESIGN REVIEW PROJECT DRAWINGS PROGRESS REPORTING QUALITY ASSURANCE/QUALITY CONTROL REQUIREMENTS COMMISSIONING, OPERATION AND MAINTENANCE MANUALS TECHNICAL DATA MANUALS TEST RECORD BOOK PLANT TAGGING OF EQUIPMENT AND INDEPENDENT COMPONENTS CONTRACTOR/COMPANY'S CONSTRUCTION SITE OFFICE AND FACILITY LOSS PREVENTION AND SAFETY REQUIREMENTS SHUTDOWN/OUTAGE COORDINATION WORKING HOURS TRAVELING REQUIREMENTS INSTRUCTIONS FOR TECHNICAL PROPOSAL LIST OF TECHNICALLY ACCEPTABLE MANUFACTURERS AND MANUFACTURING PLANTS TRANSPORTATION ( as per requirement ) Oracle Primavera Portfolio Management SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 9 10 10 11 11 18 19 30 31 31 31 32 34 37 37 38 38 38 39 40 PAGE NO. 2 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D TABLE OF CONTENTS DESCRIPTION SECTION 1 2 3 NO. IV REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: V Page SCOPE OF WORK 4.01 4.02 4.03 4.04 4.05 GENERAL ELECTRICAL WORK GASSING & DEGASSING CIVIL WORK COMMUNICATION WORK 44 44 48 48 48 4.06 PROJECT DESIGN DOCUMENTS, CALCULATIONS AND DRAWINGS 49 ENGINEERING DESIGN CRITERIA AND REQUIREMENTS 11 / 02 / 2021 5.01 5.02 5.03 5.04 5.05 APPROVED BY: VI DATE: 22 / 02 / 2021 VII CERTIFIED BY: 7.01 7.02 7.03 7.04 7.05 7.06 00 / 00 / 0000 7.07 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. VIII GENERAL EQUIPMENT/MATERIALS SPECIFICATIONS APPROVAL CONDITIONS OF THE ROW AND MATERIAL SPECIFICATIONS 64 64 65 GENERAL CABLE TRENCHES AND DIRECTIONAL DRILLING REQUIREMENTS CABLE DUCT BANKS POWER CABLE INSTALLATION OPTICAL FIBER CABLES INSTALLATION CABLE ROUTING INSIDE SUBSTATION BASEMENT/CABLE ENTRY ROOM OTHER INSTALLATION REQUIREMENTS 67 67 68 68 71 71 72 COMMISSIONING TESTS 8.01 8.02 GENERAL REQUIREMENTS TESTING OF UNDERGROUND POWER CABLES SYSTEM SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> 54 55 55 58 INSTALLATION REQUIREMENTS AND GUIDELINES CER DATE 52 EQUIPMENT/MATERIALS AND TECHNICAL SPECIFICATIONS 6.01 6.02 6.03 APP GUIDELINES FOR PREPARATION OF DESIGN CALCULATIONS ENVIRONMENTAL CONDITIONS ELECTRICAL CHARACTERISTICS DESIGN REQUIREMENTS STANDARDS, CODES AND SPECIFICATIONS SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 73 74 PAGE NO. 3 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D TABLE OF CONTENTS DESCRIPTION SECTION Page 1 2 3 NO. APPENDICES REVISIONS DEPT.: APPENDIX I DRAWING CONTROL SHEETS APPENDIX II MATERIAL DATA SCHEDULES APPENDIX III TECHNICAL DATA MANUALS APPENDIX IV RIGHT OF WAY (ROW) APPROVALS AND CORRESPONDENCES E&DD APPENDIX V EXHIBIT I - SCHEDULE OF ASSET IDENTIFICATION PREP. BY: NAME SAMI APPENDIX VI COMMUNICATION SYSTEM REQUIREMENTS DATE: APPENDIX VII CIVIL AND STRUCTURAL SCOPE OF WORK DESIGN 11 / 02 / 2021 CRITERIA, TECHNICAL REQUIREMENTS AND MATERIAL SPECIFICATION APPENDIX VIII PROJECT DESIGN DOCUMENTS, CALCULATIONS AND DRAWINGS APPENDIX IX APPROVED this project) APPENDIX BY: TRAINING OF COMPANY PERSONAL (Not required in X INSTRUCTIONS FOR TECHNICAL PROPOSAL APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 4 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D SECTION I - INTRODUCTION 1.01 GENERAL DESCRIPTION This Scope of WORK and Technical Specifications <<PTS-20WC1033>> and the associated PROJECT Conceptual Drawings describe the specific Scope of Work that the CONTRACTOR is required to carry out on Lump Sum Turnkey (LSTK) basis until the successful commissioning and integration of proposed “<< ISTP 110/13.8KV SS>>” by National Grid SA (hereafter referred to as COMPANY or NG). 1 2 3 NO. 1.02 PROJECT DESCRIPTION REVISIONS DEPT.: E&DD This PROJECT is to supply power to << Madinah ISTP 110/13.8KV >> substation in <<MADINA>> area, by installing (Underground Cables) as described in section IV of this PTS. All necessary equipment, material, accessories, terminal equipment and civil work under this Scope shall be provided and installed to make the connection feasible. PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 1.03 PROJECT SUMMARY The summary of the Scope of Work of this PROJECT, to be carried out by the CONTRACTOR includes the following: APPROVED BY: APP DATE: A. Design, Supply, Installation, commissioning and Testing of new 110KV Underground cable circuits, consisting of << 31C1200mm2>>, Cu conductor, super clean-XLPE, << Copper wire + Copper tape metallic sheath, HDPE jacket >>, single cable per phase complete with all other accessories, along the proposed route and as described in section IV of this PTS. Total Approximate route length under this is <<8.8 km for first circuit and 12.9 km for second circuit >> as shown in drawing no. <<WT-925382>>. 22 / 02 / 2021 B. Design, Supply, Installation, commissioning and Testing of underground Fiber Optic cables along the new 110KV Power Cables route (refer to appendix VI). CERTIFIED BY: CER DATE 00 / 00 / 0000 C. Protection scope of work is covered in PTS-20WN1032 of <<New Madinah ISTP Substation>> D. Design, supply and installation of all necessary cable supports/structures, terminations, splices, grounding link boxes, and other accessories as required for the 110KV XLPE cables. E. Preparation of cable trenches for direct buried cable installation along the proposed route. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. F. Construction of concrete encased ductbanks and sand ductbanks as required along the proposed route. G. Perform directional drilling as required along the proposed route. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 5 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA 1.04 ABBREVIATIONS DESCRIPTION Terms, abbreviations and/or expressions frequently used herein and after shall have the following meaning: 1 2 3 NO. Terms / Abbreviations / Expressions COMPANY or NG SEC PROJECT REVISIONS CONTRACTOR DEPT.: E&DD WORK PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE Source Substations New Substations JOB SITE/WORK SITE U/G BSP S/S F/O or FOC NFOC FOTE GIS LSTK STC MOT ASTM AEIC TCS TES TSD TMSS XLPE LMDPE LLDPE SVL HDD HDPE PVC SOW/TS or PTS ROW IEC 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. Meaning National Grid SA (Subsidiary of Saudi Electricity Company) Saudi Electricity Company << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> (110KV Underground Cables Portion). Contractor, responsible for the execution of the 110KV Underground Cables WORK (<<PTS-20WC1033>>). The execution of all activities to build the 110KV Underground Cables to Supply Power to << Madinah ISTP110/13.8KV >> substationas per this PTS. All substations / BSPs mentioned in this PTS except New Substations <<New Madinah ISTP 110/13.8KV Substation>> <<MADINA >> Underground Bulk Supply Point Substation Fiber Optic Cable Non-Metallic Fiber Optic Cable Fiber Optic Terminal Equipment Gas Insulated Switchgear Lump Sum Turnkey Saudi Telecom Company Ministry of Transportation American Society for Testing and Materials Association of Edison Illumination Companies Company Transmission Construction Standards Company Transmission Engineering Standards Company Transmission Standard Drawings Company Transmission Materials Standard Specifications Cross-Linked Polyethylene Linear Medium Density Polyethylene Linear Low Density Polyethylene Sheath Voltage Limiter Horizontal Directional Drilling High Density Polyethylene Polyvinyl Chloride Scope of WORK and Technical Specifications Right-Of-Way International Electrotechnical Commission SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 6 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA *** END OF SECTION *** SECTION II -PROJECT INTERFACE DESCRIPTION 2.01 GENERAL INTER FACE This section describes the responsibilities and the works to be carried out by various contractors at interface points. WORK to be done by Substation Contractor (PTS-20WN1032): a. Provide and install new GIS bays with cable connection enclosures at <<<<NEW SUBSTATION>>>>. 1 2 3 NO. A. REVISIONS DEPT.: b. Provide and install, cable trays, cable support structures, clamps, grounding materials (for cable support structures and cable tray) at the HV Switchgear of the New Substations. E&DD c. Coordinate all WORK and construction interface activities with all other CONTRACTOR/Agencies and COMPANY as necessary for successful completion of all interface activities by other agencies. PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 d. Provide direct buried PVC conduits for the HV & MV outgoing feeder cables up to 1500mm outside the new substation boundary wall. Each duct shall contain pull wire rope and both ends shall be capped or plugged with duct sealing units. e. Provide/construct direct buried PVC conduits for communication cable from communication/NG room up to a point outside <<<<NEW SUBSTATION>>>> boundary wall without passing through substation basement with necessary handhole system for the proposed U/G NMFOC. APPROVED BY: APP DATE: 22 / 02 / 2021 B. WORK to be done by UGTL CONTRACTOR (PTS-20WC1033): a. Survey the route of all utilities and other obstacles inside new and source substations for construction purpose. Upon completion of route survey, the CONTRACTOR shall submit 110KV and fiber optic cable routing arrangement details (plan and sections) inside the new and source substations for COMPANY review. b. Testing and commissioning of 110KV XLPE cables. c. Provide and install non-metallic fiber optic cables in PVC ducts/sub ducts from the handholes outside the source and new substations boundary up to the location of the communication equipment in the communication rooms. Provide an extra 25 meter length of cable at end securely looped inside communication rooms. Provide and install 32mm diameter flexible sub ducts inside handhole and inside communication room for the installation of U/G NFOC. d. Provide impedance CONTRACTOR. CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. measurements SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 to the COMPANY/Substation INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 7 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D e. f. DESCRIPTION g. Coordinate all WORK and construction interface activities with all other CONTRACTOR/Agencies and COMPANY as necessary for successful completion of all interface activities by other agencies. Provide, install, splice, terminate and test all new HV cables. Provide and install, cable trays, cable support structures, clamps, grounding materials (for cable support structures and cable tray) at the HV Switchgear of the Source Substations. 1 2 3 NO. 2.02 INTERFACE WORK The successful CONTRACTOR shall be expected to exchange the necessary engineering details at all points of interface with other parties and provide the interface components. REVISIONS DEPT.: E&DD *** END OF SECTION *** PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED SECTION III - BASIC REQUIREMENTS AND GUIDELINES JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 8 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 3.01 GENERAL CONDITIONS 1 2 3 NO. DESCRIPTION A. All components and accessories required for the completion and successful operation of the WORK covered under the scope of this PROJECT, either specified in detail or not, shall be supplied and installed by the CONTRACTOR as necessary. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 B. The engineering design and specification of equipment/materials supplied under this PROJECT shall be in accordance with this Scope of work and Technical Specifications and COMPANY Standards. If the equipment either does not conform to specifications or is not acceptable to COMPANY based on past operating experience / any other reason, the CONTRACTOR shall propose alternative equipment for review and acceptance by COMPANY. However, in case of a conflict in the requirements, the CONTRACTOR shall bring this to the attention of the COMPANY and shall obtain such applicable requirements for this PROJECT in writing from the COMPANY. The CONTRACTOR shall have no right to decide on his own the requirements in case of such a conflict, and in case of such an eventuality, he will be doing so at his own risk and cost as the COMPANY reserves the right to reject any or the complete part of such work arising out of the CONTRACTOR'S own decision. C. The engineering and design WORKS under this CONTRACT shall be carried out by an engineering and design firm that has registration to carryout engineering and design WORK in the Kingdom of Saudi Arabia. The proposed engineering and design firm shall also be from COMPANY’s acceptable list of Engineering and design firms or shall get pre-qualified before the CONTRACT Award for carrying out any engineering and design WORK for this PROJECT. The CONTRACTOR shall submit to the COMPANY the proposed engineering and design consultant for review and approval. APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. C. The drawings enclosed with this Scope of work and Technical Specifications are conceptual and for the information of the CONTRACTOR only. The CONTRACTOR should read these drawings in conjunction with this Scope of work and Technical Specifications. The successful CONTRACTOR shall develop detailed design drawings for construction purposes. D. Copies of existing drawings, design calculations, technical reports and other information as deemed appropriate by the COMPANY may be provided to the CONTRACTOR upon request, if available. However, if such information is not available, then the CONTRACTOR should be responsible for the independent development of the information required to complete the PROJECT specified. E. The specification of equipment and materials specified herein are to be considered as the minimum requirements, and the CONTRACTOR shall carry out his own basic and detailed design necessary for his proposed specifications. The base design shall be finalized at base design review meeting based on the guideline drawings issued hereof, manufacturer's drawings, calculations and data sheets, and detailed design shall be finalized based on the base design review and other required information. All documents, drawings, data and instruction books to be submitted by the CONTRACTOR shall be written in English language and Metric Unit system. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 9 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA F. The submission of final detail drawings shall be progressive and phased out to give sufficient review time to COMPANY. 1 2 3 NO. DESCRIPTION G. COMPANY'S acceptance or approval of the CONTRACTOR'S design and material does not relieve him of any part of his obligations to meet all the requirements of the CONTRACT nor the responsibility for the correctness of the design and construction drawings of the PROJECT. H. All WORK, including services for the test and inspections required by the COMPANY and demonstrations at site, if any, for familiarization of operation, maintenance & commissioning of new type of switchgear, relays, meters, etc. to the COMPANY personnel by the manufacturer’s representative shall be arranged/done by the CONTRACTOR. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: The CONTRACTOR shall submit for COMPANY review and approval, the demonstration package proposed by him giving the detail/list of equipment and devices that will be demonstrated. I. The CONTRACTOR’S organizational chart shall be prepared as specified in Instruction to Bidders for Technical Proposal. J. The CONTRACTOR shall obtain COMPANY approval for all equipment/materials prior to supply/fabrication/installation. 11 / 02 / 2021 APPROVED K. All necessary tests on spare parts for protection system equipment shall be done at PROJECT WORK SITE in the presence of COMPANY'S REPRESENTATIVES. Also, operational spare parts supplied by the CONTRACTOR for protection system equipment shall be ensured that they are identical to those installed under this PROJECT prior to delivery to COMPANY'S warehouses. 3.02 KICK-OFF MEETING BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE A. A Kick-Off Meeting will be held in COMPANY Headquarters shortly after award of the CONTRACT. This meeting will cover PROJECT implementation, the Scope of work, and Schedule and will give the CONTRACTOR an opportunity to discuss all matters related to carrying out his responsibilities. B. A separate design Kick-Off Meeting will be held in COMPANY Headquarter between the COMPANY and the CONTRACTOR along with his approved engineering and design staff to stream line the design- related activities, expedite the design approval and hence, help commence the project site activities in a timely manner. 00 / 00 / 0000 3.03 BASE DESIGN PHASE THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. A. The base design phase of the PROJECT is a 10-12 week period of preliminary engineering following the kick-off meeting. The purpose of the base design phase is to completely define the PROJECT in enough details to ensure the COMPANY that all requirements are being met. Information developed during the base design shall be used as a guide throughout the PROJECT and shall be considered binding on both parties, unless operational difficulties or design flaws observed during detailed design review are noted and mandate change. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 10 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA DESCRIPTION Coordination meetings will be conducted with the CONTRACTOR's Design team on regular basis until the design is complete. Base design shall include drawings required to define the project. Additional drawings if provided will not be reviewed during the base design phase. B. The CONTRACTOR shall submit minimum eight (8) sets of the base design document at least four (4) weeks ahead of the base design review meeting which shall include, but not limited to the following: Major Materials Purchase Requisitions (Preliminary) Design Calculations, Design Drawings and other documents per Tables 3.01 & 3.02 of Section 3.05. 1 2 3 NO. 1. 2. REVISIONS DEPT.: The base design submittal shall be submitted fully complete, containing all discipline drawings and calculations as stated. Partial submittals or packages are unacceptable and will be rejected. Base design shall include drawings required to define the project. Additional drawings if provided will not be reviewed during the base design phase. E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 3.04 BASE DESIGN REVIEW After completing the Base Design, the CONTRACTOR shall present the Base Design Package for technical review along with the Drawing Control Sheet. CONTRACTOR's Project Manager, Project Engineer and the Design/Construction Engineer in each field of specification shall attend the presentation meeting. During this meeting, the COMPANY's comments on the base design package will be reviewed and discussed in detail to finalize the base design for the PROJECT. Minutes of the meeting shall be prepared by the CONTRACTOR and concurred by the COMPANY REPRESENTATIVE. APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 3.05 PROJECT DRAWINGS A. General 1. The CONTRACTOR shall provide all drawings required for this PROJECT covering all the substations involved in accordance with the requirements of the COMPANY Engineering Drawing Preparation Standards (SEEDS-II revision-01). The drawings shall be assigned with drawing numbers and indexed as outlined in the above procedure. A block of drawing numbers shall be provided by the COMPANY for all new drawings/documents. 2. Drawings shall be of uniform size in each discipline as much as possible and ISO scales hall be 1:10, 1:50, 1:100. 1:1200 etc. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. 3. The existing system drawings of the source substation are generally available with the COMPANY in digital or tiff format except in certain cases where it is in the form of hard copies. Copies of existing available drawings shall be provided on CONTRACTOR'S written request. However, if any related information is not available, the CONTRACTOR shall be responsible to develop all the required drawings in micro-station to satisfy the PROJECT requirements. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 11 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA 4. Contractor shall be responsible for development of relevant documents (design calculations, design drawings etc.) for all discipline (design/as-built) for the source substation and all remote end substations. 6. The drawing to be submitted by the CONTRACTOR shall be of the following standard sizes in accordance with SEEDS-II revision-01. 1 2 3 NO. DESCRIPTION 5. The drawings involving modification/expansion of the existing system in source substation shall cover the details of the existing system and interface. The drawings in general shall be computer drafted and compatible with Micro Station V8i or above version software computer-aided-design (CAD) system. However, in case of drawings involving modifications to existing drawings, which are not available in digital or tiff format CONTRACTOR shall be responsible to develop all the required drawings in micro-station. REVISIONS DEPT.: A-Size sheet, 711x1016mm or (28x40 in.) B-Size sheet, 508x711 mm or (20x28 in.) C-Size sheet, 356x508 mm or (14x20 in.) D-Size sheet, 279x432 mm or (11x17 in.) E-Size sheet, 211x297 mm or (8.27x11.69 in.) Customized-A3 size sheet, 432 x 279 mm or (17.28 x 10.98 in.) E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 B. Revision of Existing Drawings/Drawing Control Sheets 1. All existing drawings including common drawings affected by this PROJECT shall be revised and submitted for COMPANY review as part of CONTRACTOR'S design submittals. The drawings in general shall be computer drafted Micro Station V8i or above version software in accordance with SEEDS-II revision-01. APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. 2. For modification WORKS of existing substation, the existing drawings only shall be revised as far as possible. If revising the existing drawings are not feasible or not practical and new drawings need to be developed, then preferably the same number with additional/different sheet number shall be allotted. New drawings having new drawing numbers shall be created only if drawings of existing system are not available. 3. The drawing involving modification/expansion of the existing system in substation shall cover the details of the existing system and interface. Drawings giving only the isolated views/information of expansion/modification work without details of existing system/interface are not acceptable. If new drawings, developed for modification work of existing system do not cover the complete details of existing system, then the corresponding existing system drawings shall also be modified to show the interface/integration with the new drawings developed, and submitted for COMPANY review as part of CONTRACTOR'S design submittal. 4. The existing drawings are listed in the drawing control sheet(s) for the substation and covered in more than one (1) drawing control sheet for each of the affected existing substations. The CONTRACTOR shall review/study these various by drawing control sheets and drawing, identify the superseded/latest drawings and if necessary carry out field verification to ascertain the correctness of the existing drawings. Only the appropriate/ correct drawings shall be used for developing the drawings for modification WORKS, While modifying any existing drawing sheet, SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 12 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D the sheet will be submitted in duplicate, one marked as existing and the other marked as ' modified'. 1 2 3 NO. DESCRIPTION All the existing drawing control sheets shall be revised to reflect the new revision numbers of existing drawings revised and to identify the superseded drawings. Also a prominent note shall be put on the revised existing drawing control sheet (s) to indicate the new drawing control sheet number, if a new drawing control sheet was developed. (e.g. "See drawing control sheet * E-xxxxxx for list of drawings developed for C. N. # xxxxxxxxx for ………). REVISIONS 5. Contractor shall not change/modify the drawing sheets of existing drawings. If additional sheet(s) are required to be added, the same shall be done using an alphabet. For example, a new sheet is to be added after sheet 5 of a drawing number EA-467898 with 20 sheets, then, its sheet # shall be sheet 5A of 20. [Select/Modify as applicable] 6. SCADA Drawing Requirements DEPT.: E&DD a. The CONTRACTOR is responsible for obtaining all necessary SCADA information (such as existing SCADA drawing packages and Handover Book Sheets) from the COMPANY. b. The CONTRACTOR shall produce new and/or revise the COMPANY standard size (28 x 20) SCADA drawings and Handover Book Sheets (8½” x 11”) and submit to the COMPANY for review and approval, prior to field installation of the RTU: PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 i. APPROVED BY: • APP DATE: SCADA Function Diagram This is a simplified one-line diagram for the station showing each piece of equipment connected to the SCADA system. Details of this drawing include the following: 22 / 02 / 2021 • • CERTIFIED • BY: CER DATE • • • 00 / 00 / 0000 COMPANY assigned tags/labels to transmission lines, breakers, and transformers. CT and VT ratios, transducer specifications and wiring configuration. Information supplied should be complete to enable calculation of scale factors. SCADA functions at each device defined by COMPANY standard symbols. Transformer data such as rated capacity and number of tap positions. Transmission line parameters such as impedance, length, etc. SCADA point list table. Legend of COMPANY standard symbol used. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 13 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D ii. Handover Book Sheets 1. Input and Output Points List DESCRIPTION This list shall consist of all SCADA points that are grouped according to type (i.e. Analog, Status, Control, etc.). Typical fields are Absolute Point Number, Relative Point Number, Point Description, Scale Factor, Closed Contact State Description, and IFC Point Marking. This sheet is a summary of the number, type, and address of configured input/output controllers, RTU address, point group address, communication and loopback setting information. 1 2 3 NO. 2. RTU Configuration of RTU Map Sheet REVISIONS DEPT.: PREP. BY: NAME SAMI DATE: APPROVED APP DATE: 22 / 02 / 2021 CERTIFIED BY: Sample drawings and Handover Book Sheets are available from the COMPANY upon request. d. The CONTRACTOR shall submit copies of the Handover Book Sheets in Microsoft Excel format stored in CDs and USBs. e. The CONTRACTOR shall provide complete sets of Vendor drawings and documentation of the RTU and all of its associated equipment, consisting of, but not limited to Operation and Maintenance Manuals, and Schematic Diagrams. 11 / 02 / 2021 C. BY: c. E&DD Vendor Drawings 1. Vendor drawings are manufacturers' drawings, data schedules, specification sheets installation and operating instructions and any other data required for material or equipment requirements of such information are an integral part of the purchase order and shall be specified by the CONTRACTOR. 2. Preparation and assignment of vendor drawing numbers shall be in accordance with COMPANY Engineering Drawing Preparation Standard (SEEDS-II revision01). 3. All vendor drawings shall be subject to review and approval by the COMPANY at various stages (bid/base design/detail design/construction) of the CONTRACT. CER DATE 00 / 00 / 0000 Note: All vendor drawings shall be consistent with main drawings in all respects and the vendor drawings shall clearly indicate all inter references with main drawings and all other vendor drawings as applicable. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 14 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D D. Base Design Drawings The CONTRACTOR shall submit base design drawings to the COMPANY with his Base Design Package per Section 3.05. DESCRIPTION The CONTRACTOR shall submit typical samples for design drawings and each equipment vendor drawings in CD or USB flash drives along with based design package for COMPANY review and check of drawings' conformance to the requirements of SEEDS-II.01. 1 2 3 NO. E. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 Final Detail Design/Construction Drawings The CONTRACTOR shall submit point wise compliance statement to COMPANY’s comments and shall obtain approval for all final detail design drawings after incorporating COMPANY comments. After receiving the approval, the CONTRACTOR shall submit to the COMPANY eight (8) complete sets of all interconnected drawings issued for construction in one (1) submittal. Soft copy of approved IFC drawings shall also be provided on CD (4 nos.) in PDF format, in addition to the required number of hard copies or USB flash drives. These drawings shall be submitted to the COMPANY to be stamped as “Noted By” before they are stamped and issued to the CONTRACTOR's construction team as “Issued for Construction”, but in no case less than fourteen (14) days prior to the start of construction or testing and commissioning activity. No WORK shall be started at site unless all interconnected drawings for a particular WORK has been fully reviewed and agreed upon by the COMPANY and final construction drawings are available at WORK SITE and with the COMPANY. APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: A composite list of drawings the CONTRACTOR shall provide as a minimum for this PROJECT is given in Section 3.05. Final detailed design drawings shall be submitted fully complete, by discipline representing fully the part of the PROJECT to be constructed and all the related drawings. Partial submittals are not acceptable and will be rejected. CONTRACTOR shall prepare and submit separate drawing control sheets and separate drawings (different numbers from other substations) for all the substations involved in the project. CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 15 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D F. As-Built Drawings 1 2 3 NO. DESCRIPTION 1. As the PROJECT nears completion, "As-Built" drawings shall be prepared by the CONTRACTOR in sufficient details to present an accurate record for COMPANY. All existing drawings affected by this PROJECT shall be revised and corresponding existing drawing control sheets shall be updated by the CONTRACTOR. The existing drawing control sheet shall be updated and automated in XLS format. If the existing substation drawings do not have drawing control sheet, then the CONTRACTOR shall prepare new Drawing Control Sheet, which shall include the new and existing drawings. CONTRACTOR shall coordinate with COMPANY for the list of the existing drawings. All Drawing Control Sheets, listing all proposed and existing drawings shall also be submitted in the Base Design submittal. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 2. All revisions shall reflect field modifications to engineering flow diagrams, electrical one line diagrams, electrical schematic connection and interconnection wiring diagram; instrument hook-ups wiring diagrams, terminal connections, dimensioned equipment layouts, all underground installations and other WORK and facilities not normally visible. The CONTRACTOR shall provide "As-Built" drawings showing all field modifications to drawing and diagrams prepared by the Vendors and SUB-CONTRACTORS. If the CONTRACTOR was given hard copy or tiff image file to existing as-built drawings, then it is the responsibility of the CONTRACTOR to request the COMPANY at least two (2) months before the Technical completion for the existing "as-built" drawings & redraw them in Micro-station V8i or above version software in accordance with SEEDS-II.01. Updating of existing "as-built" drawings will not be accepted. APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. 3. As part of " As-Built " drawings submission, the CONTRACTOR shall also provide the COMPANY three (3) sets of field marked up drawings reflecting the " As-Built " condition of the particular segment of WORK completed by the CONTRACTOR and distributed, as given below, prior to energization. -One (1) set shall be retained by the COMPANY at the substation. -One (1) set shall be submitted to the COMPANY. -One (1) set shall be used for "as-built" by CONTRACTOR'S Engineering and Design Consultants, which shall be included in the final submittal. 4. One (1) sample of original (digital Microstation *. DGN format and five (5) check prints from different "As-built" engineering drawings shall be submitted to the COMPANY to verify the quality of digital Micro-station *.DGN format and whether the correct drafting procedure is adopted, one (1) month before initial submission of "As-Built" drawings. Before submitting the final as-built drawings, one sample drawing shall be submitted and got approved. 5. The CONTRACTOR shall submit all design documents, calculations, studies and drawings at As-Built Stage of the Project as per SOW/TS Table 3.02 as applicable, as a minimum. As-built package not complying with this requirement shall be liable for REJECTION. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 16 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 6. The CONTRACTOR is responsible to fill-in the entire Engineering Drawings/Documents Data as per SEEDS-II.01 guidelines and returns to ESD/Transmission Documents Division for necessary documentation. 1 2 3 NO. DESCRIPTION Five (5) copies of the as-built drawings/documents shall be submitted to the COMPANY for review as to adequacy, completeness, legibility and conforming to drafting standards. If returned, the CONTRACTOR shall make corrections, provide additional data and improve the quality as instructed prior to re-submittal and COMPANY acceptance. The revised "As-Built" drawings shall be resubmitted within four (4) weeks after commissioning. Five (5) sets of final "As-built" drawings, one (1) set of As-built Digital Micro Station" DGN format drawings in CD or USB flash drives shall be submitted to the COMPANY for records. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 G. GEOGRAPHIC INFORMATION SYSTEM (GIS) PROJECTS DRAWINGS PORTION REQUIREMENTS 1. General The CONTRACTOR shall provide all drawings required for the Geographic Information System portion of this PROJECT covering all the Transmission and associated facilities involved in accordance with the requirements of the COMPANY Engineering Drawing Preparation Standards (SEEDS-III Rev.00). The existing Geographic Information System drawings of the source substation are generally available with the COMPANY in digital format. Copies of existing available Geographic Information System drawings shall be provided on CONTRACTOR’S written request form (Appendix-GIS004). APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 The Geographic Information System drawings involving modification/expansion of the existing system in source substation shall cover the details of the existing system and interface. All Geographic Information System drawings shall be prepared in ArcGIS (V10 or latest version with appropriate UTM coordinate system, datum WGS1984) ONLY. For more information, contact National Grid SA, Engineering Services Department/Geographical Information System Division. 2. Vendor Drawings and Documents (GIS Portion) Vendor drawings are manufacturer’s drawings, data schedules, specification sheets, installation and operating instructions and any other data required for material or equipment requirements of such information shall be submitted by the CONTRACTOR as per SEEDS-III revision-00. All vendor drawings shall be consistent with main drawings in all respects and the vendor drawings shall clearly indicate all inter references with main drawings and all other vendor drawings as applicable. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 17 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 3. As-Built Drawings (GIS Portion) As the PROJECT nears completion, As-built drawings for the Geographic System portion shall be prepared by the CONTRACTOR. As-built drawings for the Geographic Information System portion shall be submitted to the COMPANY for review as to adequacy, legibility and conforming to SEEDS-III revision-00. If returned, the CONTRACTOR shall make corrections, provide additional data and improve the quality as instructed prior to re-submittal and COMPANY acceptance. 1 2 3 NO. DESCRIPTION The CONTRACTOR is responsible to fill-in the required attributes of the Transmission features used in the Geographic Information System portion of the PROJECT as per SEEDS-III revision-00. REVISIONS DEPT.: The revised As-built drawings for the Geographic Information System portion shall be resubmitted within four (4) weeks after commissioning. Digital format shall be submitted to the COMPANY for records. E&DD PREP. BY: NAME SAMI 3.06 PROGRESS REPORTING DATE: 11 / 02 / 2021 APPROVED BY: A. The CONTRACTOR shall submit Bi-Weekly PROJECT Progress Reports, in COMPANY-approved formats (soft and hard copy) for the PROJECT to the responsible COMPANY REPRESENTATIVE. Soft copy of progress reports shall be submitted along with hard copy. For this purpose, the total WORK shall be divided into: 1. Engineering and Design. 2. Procurement/Manufacture/Fabrication Inspection and Delivery of Materials/ Equipment. 3. Construction and Installation. 4. Testing and Commissioning. APP DATE: 22 / 02 / 2021 B. The following information shall be included in the Progress Reports: 1. CERTIFIED BY: CER DATE 2. 3. 4. 5. 00 / 00 / 0000 6. Percent of WORK completed as compared to the weighted schedule used to assess WORK progress. Statement of items worked on and/or completed during the period. Statement of items to be worked on and/or completed during the following period. Problem areas which can have an adverse effect on the schedule. Safety statistics, safety evaluation report and minutes of construction safety meeting and progress meeting. Manpower and equipment availability against the schedule requirement. C. The CONTRACTOR shall carry out PROJECT planning/scheduling by using MS PROJECT computer software or other COMPANY approved software. All PROJECT schedules shall be submitted hard copies and soft copies in CD-ROM and USB. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 18 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA DESCRIPTION CHK’D D. Bi-Weekly Progress Meeting shall be conducted between the COMPANY and the CONTRACTOR during the entire CONTRACT duration of the PROJECT. Other coordination and interface meetings will be conducted, as required. The CONTRACTOR shall prepare the minutes of all meetings. The initial draft shall be submitted by the CONTRACTOR to the COMPANY REPRESENTATIVE for review and concurrence. The CONTRACTOR shall then incorporate the required corrections and submit to the COMPANY one (1) original and two (2) copies after they are duly signed by the authorized representative of the CONTRACTOR. The COMPANY shall sign one (1) copy in acceptance and furnish it to the CONTRACTOR and retain the original. 1 2 3 NO. In addition, a Weekly Construction Safety Meeting shall be conducted by the CONTRACTOR's Safety Supervisor or PROJECT Engineer. REVISIONS 3.07 QUALITY ASSURANCE/QUALITY CONTROL REQUIREMENTS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED A. Quality Management CONTRACTOR shall implement an effective quality management which addresses all direct and indirect activities related to the PROJECT to ensure that all contractual conditions are met. Quality planning, quality control, quality assurance and quality improvement shall be part of CONTRACTOR's quality management. To effectively manage the PROJECT quality, CONTRACTOR shall develop a clearly defined PROJECT Quality Plan/Quality Program. The PROJECT Quality Plan/Quality Program shall be implemented from PROJECT start until completion and communicated at different levels of the PROJECT organization. In addition, CONTRACTOR shall also require manufacturers/suppliers to develop and implement Quality Control Plan/ Inspection and Test Plan for each material/equipment per section 2.07.C. B. PROJECT Quality Plan/Quality Program BY: APP DATE: 22 / 02 / 2021 1. The PROJECT Quality Plan/Quality Program shall set out the specific quality procedures and practices, resources, and all activities (in sequence) relevant to this PROJECT. The PROJECT Quality Plan/Quality Program shall address QA/QC activities during design, procurement, manufacturing/ fabrication, delivery, storage, construction, installation, testing and commissioning of all items of WORK and materials/equipment per Scope of WORK and Technical Specification. 2. The PROJECT Quality Plan/Quality Program shall be submitted to the COMPANY as part of the base design package for review and approval. 3. The PROJECT Quality Plan/Quality Program shall clearly define and address the following: CERTIFIED BY: CER DATE 00 / 00 / 0000 a. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. The quality objectives to be attained and CONTRACTOR’s commitment to achieve the objectives in the form of a signed policy statement. The policy statement shall be signed by CONTRACTOR’s management personnel not lower than the person who signed this CONTRACT. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 19 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D b. CONTRACTOR shall include in the PROJECT organizational chart QA/QC engineers and inspectors dedicated to quality assurance and quality control (QA/QC). The QA/QC engineers and inspectors shall report directly to one level higher than the PROJECT Manager. The QA/QC engineers and inspectors shall have adequate experience in their area of responsibility and shall be responsible for ensuring that all phases of the PROJECT are built, tested and commissioned in accordance with the requirements of the PROJECT Scope of WORK and Technical Specifications. The CONTRACTOR’s Chief QA/QC engineer shall interface directly with the COMPANY REPRESENTATIVE. 1 3 2 DESCRIPTION NO. Detailed PROJECT organizational chart and specific allocations of responsibilities and authorities during the different phases of the PROJECT. REVISIONS DEPT.: CONTRACTOR shall use QA/QC personnel other than those performing or directly supervising the WORK. The QA/QC personnel shall not report directly to immediate supervisors responsible for producing the WORK being inspected. CONTRACTOR’s QA/QC personnel shall be kept free from the pressures of cost, schedule and production and shall be given the necessary authority and independence to perform their roles effectively. E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 c. CONTRACTOR’s PROJECT QA/QC engineers shall review all products and services prior to procurement to ensure conformance to specified requirements. Procurement control shall include source evaluation and selection, source inspection and evaluation of objective evidence of quality furnished by a supplier against the PROJECT specification. APPROVED BY: These products shall cover major materials/equipment and other items including but not necessarily limited to testing services, fill materials, Portland cement concrete and additives, asphalt concrete, water proofing, steel structures, Protective Coatings, HVAC materials and equipment, electrical materials, plumbing materials, architectural and finishing materials and formwork materials. APP DATE: 22 / 02 / 2021 CERTIFIED BY: d. 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. Quality Audit CONTRACTOR shall conduct its own internal quality surveillance at appropriate stages (e.g. design, procurement, construction, installation and commissioning stage) of the PROJECT to determine compliance to and the effectiveness of the PROJECT Quality Plan/Quality Program. Each element of the PROJECT Quality Plan/Quality Program shall be assessed at least once during the life of the PROJECT. The schedule and frequency should be adjusted if one or more of the following conditions exist: i. Result of previous surveillance indicates a need to perform them more frequently. ii. Significant changes are made in the PROJECT Quality Plan/Quality Program. CER DATE Procurement Control SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 20 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D iii. iv. Safety, performance or reliability of an item is questionable due to non-conformance. Verification of corrective action implementation. DESCRIPTION Personnel conducting the quality surveillance shall be independent of those having direct responsibility for the specific activities or areas being evaluated or assessed. REVISIONS DEPT.: CONTRACTOR’s QA/QC engineer/inspector shall re-inspect repaired and reworked non-conforming items. CONTRACTOR shall not use any repaired item or product unless approved by the COMPANY. E&DD PREP. BY: NAME SAMI DATE: Under this clause, the following definitions apply: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED f. BY: Non-Conformance Control CONTRACTOR shall ensure that items and services which do not conform to specified requirement are controlled in accordance with documented procedures to prevent unintended use. CONTRACTOR shall identify, document, segregate, evaluate and dispose non-conforming items and services after proper notification of concerned personnel within the CONTRACTOR’s organization. 1 2 3 NO. e. i. Repair - Action taken on a non-conforming product so that it will fulfill the intended usage requirements although it may not conform to the original specified requirements (ISO 9000:2015). ii. Rework - Action taken on a non-conforming product so that it will fulfill the specified requirement (ISO 9000:2015). CONTRACTOR shall develop non-conformance report (NCR) form and submit it to the COMPANY for review and comment. CONTRACTOR’s QA/QC engineers/inspectors shall have the freedom to issue NCRs, verify implementation of corrective actions and prevent use of nonconforming items until the deficiency has been satisfactorily resolved. CONTRACTOR’s Chief QA/QC engineer shall submit bi-weekly site QA/QC reports to COMPANY REPRESENTATIVE about noncompliances. Corrective Action CER DATE CONTRACTOR shall develop, document and implement a system for determining the root cause of non-conformities and identifying the required corrective actions. New procedures or changes to existing procedures resulting from identification of the root cause and potential root cause of non-conformances shall be documented and implemented. Follow-up action shall be taken to verify effective implementation of corrective action. The identified cause and corrective action should be included in the bi-weekly site QA/QC reports that are required to be submitted to the COMPANY REPRESENTATIVE. 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 21 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D g. Quality Records DESCRIPTION CONTRACTOR shall develop and maintain a system for preparation, maintenance, protection and preservation of quality records. Documents such as inspection reports, field inspection checklist, factory test reports, laboratory test reports, witnessed test reports, inspection logbooks, equipment calibration records/certificates, construction drawings and specifications, approved submittals and non-conformance reports are part of these records. All quality records shall be available at WORKSITE for use and/or reference by CONTRACTOR and COMPANY REPRESENTATIVE. All measuring and testing equipment and devices which can affect the quality of construction shall be controlled and maintained. CONTRACTOR shall develop and implement a documented calibration control program indicating equipment calibration schedule and identifying those who are responsible for control of the equipment. CONTRACTOR shall ensure that only properly identified and calibrated measuring and testing equipment are used in the PROJECT. Equipment calibration certificates shall be presented to COMPANY REPRESENTATIVE, prior to commencement of related jobs. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 i. APP DATE: 22 / 02 / 2021 CERTIFIED BY: j. 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. Material/Equipment Handling, Storage, Identification and Control CONTRACTOR shall verify that material/equipment meet prescribed contractual requirements and are properly handled, identifiable, traceable, cleaned, preserved and stored. CER DATE Document Control CONTRACTOR shall develop and maintain a documented control program for the review, approval, revision and distribution of documents for the activities affecting quality. Responsible personnel for revision, issuance and approval of documents shall be identified. Control shall ensure that all pertinent and current issues of appropriate documents are available at locations where they are essential and obsolete or superseded documents are promptly removed. CONTRACTOR shall list all the documents that have to be controlled and shall include PROJECT Quality Plan/Quality Program, Quality Control Plan/Inspection and Test Plan, construction and design drawings, calculations, correspondence, inspection and test reports, field inspection checklist, etc. APPROVED BY: Control of Inspection, Measuring and Testing Equipment 1 2 3 NO. h. k. Control of interface and interaction between the COMPANY and CONTRACTOR and between the CONTRACTOR and its SUBCONTRACTORS, manufacturers/suppliers, QA/QC Services CONTRACTOR(s) [Independent Inspection Agency(ies)] and Independent Testing Laboratories. l. Any other applicable QA/QC activity(ies) for the PROJECT. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 22 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA Design Control a. CONTRACTOR shall describe the design control program that will be applied on this PROJECT whether the design activity is to be done by the CONTRACTOR’s own personnel or by design consultants. All design input and output shall be reviewed prior to release to the next stage. Hold points shall be shown or indicated in the PROJECT Quality Plan. In addition to design review, design verification shall be conducted to ensure that the design stage output meets the design stage input requirements. b. CONTRACTOR shall ensure that all design computations, design drawings and other design documents are properly controlled and checked prior to submission to the COMPANY. Design documents shall be signed by the person(s) who prepared and checked them. COMPANY reserves the right to return design documents without the proper signature of the responsible person(s). 1 2 3 NO. DESCRIPTION CHK’D 4. REVISIONS DEPT.: E&DD 5. CONTRACTOR shall establish and document all procedures and WORK instructions to ensure that the construction and installation processes are performed in a controlled manner. The necessary qualification of personnel and procedure for activities such as welding, non-destructive examination, heat treatment, civil/concrete WORKS, etc. shall be defined. WORK instructions and procedures shall be adhered to by the CONTRACTOR’s personnel. PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 CONTRACTOR shall conduct inspection and testing activities at all phases and quality audit at appropriate stages of the PROJECT construction/installation. CONTRACTOR’s QA/QC engineers/inspectors shall develop and use field inspection checklist to facilitate checking of a process, activity, material or equipment. The field inspection checklist shall state the characteristic to be verified, inspection method, acceptance criteria and clause reference of the applicable standard or specification. The checklist shall have provision for writing the result of inspection, date of inspection and name and signature of the QA/QC engineer/inspector. Such activities where inspection checklists are required shall include but not necessarily limited to all pre-commissioning and commissioning checks and tests, material/equipment receiving inspection, concrete pre-pour inspection, asphalting, hydrostatic testing, pressure testing of equipment and lines and air balancing and leak testing of HVAC system. All inspection and testing results shall be reviewed, safely stored and maintained by the CONTRACTOR. Typical checklist shall be provided to the COMPANY for review and comment. APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE Field Testing/Inspection and Construction/Installation Control 00 / 00 / 0000 CONTRACTOR shall develop and implement the use of inspection logbook for use by the CONTRACTOR’s QA/QC engineers/inspectors in recording their comments and observations as a result of their inspection. CONTRACTOR’s personnel responsible for rectifying any observed deficiency or nonconformance shall also write their reply in the logbook stating the actions taken to correct the deficiency. CONTRACTOR’s QA/QC engineers/inspectors shall ensure that all unsatisfactory observations on an item are cleared before any activity proceeds to the succeeding stage of that item. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 23 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D C. Quality Control Plan/Inspection and Test Plan REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. The CONTRACTOR shall submit to the COMPANY the Quality Control Plan/Inspection and Test Plan for each major equipment/material covered under the scope of this PROJECT only; based on the following Transmission Equipment/Materials, which requires factory inspection witnessed by Third Party Inspectors and/or SEC/National Grid SA: Switches (Air Break Disconnect Switch, Grounding Switches, Circuit Switcher) LV Panels (LV Relay & Control Panel, Main AC & DC Distributions Boards) Switchgears (MV Air/SF6 Metal-clad Switchgears, HV & EHV GIS, Ring Main Units) Circuit Breakers (SF6, Vacuum, Dead Tank & Live Tank) Supervising Equipment (Remote Terminal Unit, TFR, SOE, PSE, Annunciator Systems, CCVTs 69kV thru 380kV) Series & Shunt Capacitor Banks Batteries/Battery Chargers/Un-interrupted Power Supplies (all types) Free-standing Current & Potential Transformers (all voltage levels) Grounding Transformers (all sizes and voltage levels) Neutral Grounding Resistors Pad-Mounted Station Service Transformers (all sizes and voltage levels) Power Transformers (all sizes and voltage levels) Oil-Immersed Shunt Reactors (all sizes and voltage levels) Air-Core Series Reactors (all sizes and voltage levels) Air-Conditioning Equipment and HVAC Control Panel HV Bushings (Indoor/Outdoor type) Fire Alarm Control Panel, Fire Suppression System Control Panel Overhead Line Conductors (all types) Overhead Ground Wires (includes OPGW also) Transmission Line Structures (includes Substation Gantries, Wood Poles, Substation Steel Structures, Tubular Tapered Pole, Lattice Steel Structures) Insulators all types used in COMPANY system (includes Station Post also) Line Hardware and Fittings (includes Suspension Clamps, Vibration Dampers and Spacer Dampers also) Conductor Accessories (includes Compression Joints, Repair Sleeves, Compression Dead-end and Jumper Terminals also) LV, MV and HV Power Cables (all voltages and types) Control & Instrumentation Cables (all types) Splice and Termination Kits for all MV and HV Power Cables Grounding Conductor Grounding Rods NMFOC, Pilot Cables and Termination Equipment FOC Terminal Equipment Link Boxes for Sheath Grounding of U/G Power Cable Surge Arresters Sheath Voltage Limiter (SVL) Spherical Markers and Warning Lights SAS equipment 1 2 3 NO. DESCRIPTION 1. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 24 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA DESCRIPTION CHK’D The quality activities including but not necessarily limited to, inspection and testing, for the material/equipment shall be planned and documented in the form of a Quality Control Plan/Inspection and Test Plan. The Quality Control Plan/Inspection and Test Plan shall be submitted to the COMPANY together with the PROJECT Quality Plan/Quality Program. The Quality Control Plan/Inspection and Test Plan shall follow exactly the General Instructions written in the Inspection and Test Plan. 1 2 3 NO. 2. The essential features of the required Quality Control Plan/Inspection and Test Plan are as follows: a. It is specifically identified to a particular material/equipment. b. It has provision for revisions to be made and is assigned a unique document number. c. It lists all the inspection and testing activities sequentially. d. It states the location at which the activity is to be carried out. e. It identifies the applicable standard, test procedure to be followed and the acceptance criteria for the inspection or test activity. f. It identifies the extent of inspection, sampling frequency and sample size, or extent of check. g. It identifies the hold point, witness point and surveillance point. h. It identifies the record document to be generated, reviewed and retained. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED 3. BY: The Quality Control Plan/Inspection and Test Plan shall indicate the scheduled dates of testing and inspection at the designated location. APP DATE: 4. Factory inspection & testing of major equipment/materials (i.e. XXXKV Power Cables) involved in the PROJECT, the CONTRACTOR shall arrange traveling requirements for four (4) COMPANY Personnel for witnessing the field or laboratory testing, per the requirements of section 3.16. The CONTRACTOR shall submit a schedule for factory inspection of major equipment/materials along with base design package for COMPANY review. 22 / 02 / 2021 CERTIFIED BY: 5. Standards Inspection and Test Plan available for FAT in the COMPANY webpage shall be followed after COMPANY Approval for all applicable equipment inspection and testing as specified below: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. Manufacturer’s compliance shall be indicated in front of each test. Approved Data Schedule & final drawings for the equipment / Material shall be attached. Test Procedure & Day-to-day activity schedule shall be attached for approval. The ITP must be duly signed and stamped by manufacturer's authorized personnel. This document is valid for testing after COMPANY concerned department approval. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 25 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA 1 2 3 NO. DESCRIPTION CHK’D D. Manufacturers/Suppliers 1. CONTRACTOR shall procure all major equipment/material items for the PROJECT from COMPANY qualified and approved sources. 2. CONTRACTOR shall ensure that purchase orders to manufacturers/ suppliers contain all the applicable industry and COMPANY developed standards and specifications. 3. CONTRACTOR shall ensure that Purchase Order(s) to approved manufacturers/ suppliers are not re-assigned or sub-contracted to other manufacturers/suppliers without COMPANY’s written consent. 4. CONTRACTOR shall furnish copies of all un-priced purchase orders for COMPANY’s reference & records. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: E. Quality Assurance and Quality Control Services CONTRACTOR(s) [Independent Inspection Agency] 1. CONTRACTOR shall contract COMPANY approved Quality Assurance and Quality Control Services CONTRACTOR(s) to provide quality control/quality assurance monitoring of all quality activities related to procurement of materials and equipment to be used in this PROJECT. 2. CONTRACTOR shall instruct the contracted Quality Assurance and Quality Control Services CONTRACTOR(s) to provide directly to COMPANY REPRESENTATIVE, by express mail or fax, four (4) copies of material status, quality surveillance reports, inspection and test reports within seven (7) days after the inspection. Soft copy of these singed reports in CD and USB shall also be furnished and submitted for COMPANY records. All pages of the inspection and test reports shall be reviewed, signed and stamped by the approved inspector from the Quality Assurance and Quality Control Services CONTRACTOR. 3. CONTRACTOR’s Quality Assurance and Quality Control Services CONTRACTOR shall not re-assign or sublet portion of their contracted quality control/quality assurance monitoring WORK. 4. CONTRACTOR shall provide the COMPANY a copy of the Scope of WORK issued to the Quality Assurance and Quality Control Services CONTRACTOR. 5. CONTRACTOR shall instruct the Quality Assurance and Quality Control Services CONTRACTOR to verify and check each material/equipment for conformance against the PROJECT Scope of WORK and Technical Specification and each clause of the applicable COMPANY Material Standard Specification (TMSS) and report all deviations that are not included in the COMPANY issued clarifications. The report of the Quality Assurance and Quality Control Services CONTRACTOR shall include the following: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. a. PROJECT title, CONTRACT number. b. Complete description of the inspected material/equipment. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 26 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء c. Report number and date. d. Place and date of inspection, scope of inspection. e. Documents used during inspection. f. Manufacturer and plant location where the equipment was manufactured. g. Detailed description of the inspection and testing activities and their results, deviations to specification, manufacturer’s explanation to the deviations, visual inspection result, packing and marking inspection result, conclusion and copy of the outline drawing of the inspected material/equipment. Witnessed tests and reviewed test data shall be clearly identified in the inspection reports. h. Name and signature of the inspector(s). 1 2 3 NO. DESCRIPTION CHK’D APP’D NATIONAL GRID SA REVISIONS DEPT.: E&DD 6. PREP. BY: NAME SAMI DATE: BY: DATE: 11 / 02 / 2021 a. Purchase Order placed to the manufacturer/supplier. b. Relevant section of PROJECT Scope of WORK and Technical Specification. c. Applicable COMPANY developed standard and specification. APPROVED d. Manufacturer’s Technical Specifications and COMPANY approved design drawings. APP e. COMPANY’s approval of material/equipment and applicable clarifications issued by the COMPANY. f. COMPANY approved test program, manufacturing quality control plan or inspection and test plan. 22 / 02 / 2021 CERTIFIED BY: 7. CONTRACTOR shall send to the COMPANY, copy(ies) of all technical correspondence exchanged between CONTRACTOR and “Quality Assurance and Quality Control Services CONTRACTOR”. 8. CONTRACTOR shall obtain approval from COMPANY before allowing any personnel of the Quality Assurance and Quality Control Services CONTRACTOR to perform quality assurance and quality control monitoring activities related to procurement of materials to be used in this PROJECT. The specific material/equipment to be inspected, manufacturer and location of manufacturing plant shall be identified for each proposed inspector of the Quality Assurance and Quality Control Services CONTRACTOR. Third Party Inspectors who are approved to attend Inspection Activities during FAT can be found through COMPANY webpage. CER DATE CONTRACTOR shall furnish copies of the following document to the Quality Assurance and Quality Control Services CONTRACTOR(s) contracted to perform quality assurance and quality control monitoring of each material and equipment before surveillance: 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 27 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 9. Release for Shipment Certificate 1. Release for Shipment Certificate is a certificate issued by the CONTRACTOR to the supplier/manufacturer to release the described material for shipment after recommendation by the Quality Assurance and Quality Control Services CONTRACTOR and approval by the COMPANY. 2. CONTRACTOR shall ensure that all material requiring inspection and/or quality surveillance at the supplier/manufacturer’s facility are not shipped to the WORK SITE without a “Release for Shipment Certificate.” 3. CONTRACTOR acknowledges that material shipped without approved “Release for Shipment Certificate” is subject to rejection and return at the CONTRACTOR’s expense 4. CONTRACTOR shall ensure that all inspection and surveillance reports and any other requirements are satisfactorily completed before requesting the COMPANY to approve the “Release for Shipment Certificate.” 3. CONTRACTOR shall ensure that the independent third party inspection agency shall attach the Original Release for Shipment certificate with the inspection reports delivered to COMPANY. 1 2 3 NO. DESCRIPTION F. Employment by CONTRACTOR of a Quality Assurance and Quality Control Services CONTRACTOR shall in no way relieve the CONTRACTOR of any obligation set forth in this CONTRACT. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 G. Receipt Inspection APPROVED BY: 1. CONTRACTOR shall conduct receipt inspection of major material and equipment after delivery at the WORKSITE and shall submit a copy of the report to the COMPANY. 2. CONTRACTOR shall promptly report to the COMPANY any shipment and transportation damage. APP DATE: 22 / 02 / 2021 H. Independent Testing Laboratory CERTIFIED BY: 1. CONTRACTOR shall contract COMPANY approved Independent Testing Laboratory for material and field-testing services. 2. CONTRACTOR shall instruct the contracted Independent Testing Laboratory to provide four (4) copies of the test results and reports & a soft copy on CD and USB directly to COMPANY REPRESENTATIVE within three (3) days of the test completion. Test reports shall indicate the tested characteristics, test methods, acceptance criteria and applicable standard. The PROJECT Contract Number shall be used as reference on all reports. 3. CONTRACTOR shall ensure that contracted Independent Testing Laboratory does not re-assign or sublet any portion of their contracted testing WORK. 4. CONTRACTOR shall provide the COMPANY a copy of the Scope of WORK issued to and finalized with the Independent Testing Laboratory. CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 28 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء DESCRIPTION CHK’D APP’D NATIONAL GRID SA CONTRACTOR shall make reasonable effort to obtain timely access by the COMPANY REPRESENTATIVE to the Independent Testing Laboratory’s facility, should the COMPANY REPRESENTATIVE exercise the option to witness any or all the tests and verify the calibration status of the testing equipment. 6. Employment by CONTRACTOR of an Independent Testing Laboratory shall in no way relieve CONTRACTOR of any obligation set forth in this CONTRACT. Inspection by COMPANY REPRESENTATIVE 1. COMPANY REPRESENTATIVE will conduct routine and/or periodic inspection of the WORK. CONTRACTOR shall provide facilities and access to COMPANY REPRESENTATIVE to inspect the WORK and witness the tests. 2. CONTRACTOR shall advise the COMPANY REPRESENTATIVE in writing the schedule of any field or laboratory testing to be conducted for this PROJECT showing the dates and location of testing. 3. CONTRACTOR shall attach a copy of the completed inspection checklist or final/in-process inspection report by the CONTRACTOR’s QA/QC engineer/inspector on every inspection request submitted to the COMPANY. CONTRACTOR’s QA/QC engineer/inspector shall ensure that the items for inspection covered by the CONTRACTOR’s “Inspection Request” are ready and in accordance with the CONTRACT requirements prior to inspection by COMPANY REPRESENTATIVE. 1 2 3 NO. I. 5. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 Inspection and witnessing of testing at site by COMPANY REPRESENTATIVE shall be within the regular working hours of the COMPANY. CONTRACTOR’s schedule for inspection and witnessing of testing at site by COMPANY REPRESENTATIVE outside of the regular COMPANY working hours shall have prior approval from the COMPANY REPRESENTATIVE. APPROVED BY: APP DATE: 22 / 02 / 2021 J. COMPANY’s Quality Assessment (Audit) Right 1. CERTIFIED BY: CONTRACTOR shall provide all access and assistance in a timely manner to COMPANY personnel who will perform the quality assessment (audit). CER DATE COMPANY reserves the right to conduct scheduled and/or unscheduled quality assessment of CONTRACTOR’s Quality System, PROJECT Operation, and PROJECT Quality Plan implementation. The results of such assessments (audits) shall be confidential between CONTRACTOR and COMPANY. 00 / 00 / 0000 The CONTRACTOR shall implement corrective actions on all deficient areas discovered during the quality assessment (audit) within a mutually agreeable time frame. All costs (except cost of wages, transportation and lodging of COMPANY Quality Assessors) incurred during the quality assessment (audit) shall be borne by the CONTRACTOR. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 29 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA 1 2 3 NO. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 3.08 COMMISSIONING, OPERATION AND MAINTENANCE MANUALS A. The CONTRACTOR shall submit to the COMPANY Commissioning, Operation and Maintenance Manuals, along with Pre-commissioning and Procedures Manuals, consisting of, as a minimum, the following documents: 1. Detailed manufacturer's instruction manuals applicable to each equipment installed. These manuals shall contain all information (including any special design and/or construction or operation feature) which may be required by the COMPANY for safe operation and maintenance of the new facilities and shall describe fully erection, commissioning, operation and maintenance procedures including mechanical/ electrical tolerances for maintenance/repair purposes (soft copy as well as hard copy). 2. Manufacturer's instruction manuals applicable to each particular test apparatus (soft copy as well as hard copy). 3. Complete sets of exploded view drawings with comprehensive parts identification for each device to enable the COMPANY to catalogue and order. 4. Interconnection and Schematic Diagrams. 5. Setting and Calibration Procedures and Instructions. APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CONTRACTOR shall include the following conditions on purchase order placed with the manufacturers/suppliers: “COMPANY reserves the right to perform plant survey, quality assessment (audit), and quality surveillance activities and to inspect material at the suppliers/ manufacturer’s facility to verify compliance with the terms and conditions of the purchase order and its related documents. COMPANY reserves the right to witness any and all tests specified and to perform such visual examination (inspection) at the suppliers/manufacturer’s facility. COMPANY reserves the right to require certificates and data from the supplier/manufacturer on any pertinent aspect of the manufacturing process, including but not limited to, mill test reports, heat treatment certificates, welders and welding procedure qualification records, non-destructive examination records, test records and quality control manual that will form part of the nonmaterial requirement that shall be shipped to COMPANY as a document package”. DESCRIPTION CHK’D 2. CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED B. The submission schedule for commissioning, operation and maintenance manuals as detailed in (A) above, shall be as given below: 1. Six (6) sets for preliminary review by COMPANY as to adequacy, completeness, and legibility at least eight (8) weeks before commencing commissioning tests. 2. Four (4) complete sets of fully revised manuals original (original hard copy and original soft copy in CD and USB format and no photocopies) incorporating the COMPANY's comments to the full satisfaction of the COMPANY before technical completion of the PROJECT. For Communication equipment requirements, refer to Appendix - VI. 3. JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 30 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 3.09 TECHNICAL DATA MANUALS DESCRIPTION A. The CONTRACTOR shall provide technical data manuals for the substation equipment, protection relays and underground cable system installed under the scope of this PROJECT only as indicated in the attached Appendix - III. The manuals binders shall have COMPANY logo, binder number and PROJECT title, and CONTRACT Number on the front cover. B. For Communication equipment requirements, refer to Appendix - VI. 1 2 3 NO. 3.10 TEST RECORD BOOK REVISIONS DEPT.: E&DD A. The CONTRACTOR shall provide a "Test Record Book" which shall include the following: 1. Factory test report of each particular equipment installed. 2. Field test report, which shall include the following: a. Description of Equipment Tested and Manufacturer's Nameplate Data b. Description of Test c. List of Apparatus with Calibration Data d. Test Results e. Conclusions and Recommendations f. Appendix, including test forms PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 B. Each test form where applicable shall include a column quoting the acceptable maximum and minimum limits of the test in terms of voltage, current, frequency, time, etc. and include “As Found” and “As Left” values. APPROVED C. Four (4) copies of the "Test Record Book" are to be submitted within thirty (30) days after completion of the site testing and commissioning activities. BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. 3.11 PLANT TAGGING OF EQUIPMENT AND INDEPENDENT COMPONENTS A. The CONTRACTOR shall affix Plant Tag to each and every individual equipment including independent components to be installed under this CONTRACT which have a material value of Five Thousand Saudi Riyals (SR 5,000), or more. The CONTRACTOR shall install Plant Tags adjacent to the Manufacturer's Data Plate or at any other place approved by the COMPANY REPRESENTATIVE. The CONTRACTOR shall affix Plant Tags by bolts and nuts, or rivets or welds, or adhesives, as instructed in writing by the COMPANY REPRESENTATIVE, depending on the type of equipment to be tagged. The CONTRACTOR shall complete Plant Tagging before Technical completion. B. At least sixty (60) days before completion of the installation of all equipment covered under this CONTRACT, CONTRACTOR shall submit to COMPANY a list of all equipment and independent components to be tagged, using the format of COMPANY Form No. 16511 (2/10) Exhibit I to the PROJECT's SOW/TS. Based on this list, COMPANY shall assign Plant Tag Number to each item and CONTRACTOR shall install the Plant Tags in accordance with this list. COMPANY will, within one (1) month from the date of receipt of the list, issue to CONTRACTOR the Plant Tags together with the list showing assigned Plant Tag Numbers. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 31 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D C. The CONTRACTOR shall, if required, assist the COMPANY REPRESENTATIVE in locating all equipment identified by Plant Tag Numbers in accordance with the list provided by the CONTRACTOR. DESCRIPTION 3.12 CONTRACTOR/COMPANY’S CONSTRUCTION SITE OFFICE AND FACILITY 1 2 3 NO. A. REVISIONS DEPT.: E&DD The CONTRACTOR shall install a temporary site office, for exclusive use of COMPANY, as specified out in clause 2.1.2.a of TCS-P-105 and details of which included in the consolidated requirements listed below, prior to mobilization of any construction activity pertaining to the PROJECT. Proposal with layout sketch of the site office shall be submitted to COMPANY for approval. If the facilities located outside the COMPANY property/premises a written permission of the owner of the land/premises shall be obtained by the CONTRACTOR and copy furnished to the COMPANY for records. The site office is the property of the CONTRACTOR and shall be demobilized at the end of the PROJECT in accordance with Section 2.12.I. The temporary site office and facility shall be secured by chain link fence with drive gate, personnel gate and guard house. PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 The CONTRACTOR shall supply and maintain the temporary site offices for COMPANY use including sanitary facilities, such as toilet and wash room. The said site offices shall be of very good condition and with approx. floor area of not less than 120 sq. m and shall consist of the following: 1. 2. 3. APPROVED BY: 4. 5. Three (3) no. office rooms (dedicated to COMPANY personnel) One (1) no. conference room and one (1) no. drawing/record room Two (2) no. toilets, one eastern and the other western (dedicated to COMPANY personnel) One (1) kitchen. Lobby and sitting area. APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. The site office shall also have the following additional provisions: 1. Mosque. 2. Parking shelter for five (5) COMPANY vehicles. Telephone, furniture, fire protection equipment, office equipment and supplies including, but not limited to the following, shall be available at the site Office: 1. Three (3) computers of the latest configuration (dedicated to COMPANY offices) 2. One (1) separate telephone line 3 Telephone set for each office room including the conference room. 4. One (1) Fax Machine with separate telephone line 5. One (1) copying machine with printer sharing to above COMPANY offices. 6. Three (3) filing cabinets 7. Three (3) desks. 8. Three (3) drawing holders 9. Three (3) swivel Chairs. 10. Six (6) guest chairs. 11. One (1) conference Table and chairs for 12 persons 12. Furniture for sitting area. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 32 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA DESCRIPTION CHK’D 13. 14. 15. 16. 17. 18. 19. 20. REVISIONS DEPT.: E&DD The temporary electrical wiring and installation for the site office is to be performed in accordance with the requirements of the latest revision of the National Electrical Code (NEC) or the National Fire Protection Association (NFPA). PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 C. The CONTRACTOR will be allowed to use the telephone only for making local calls. APP DATE: 22 / 02 / 2021 D. Water Supply Connection For site office requirement and construction purpose, the CONTRACTOR shall arrange adequate water supply from Municipality. If no Municipal water supply extension is available, a water tank of adequate capacity shall be installed for site requirement during construction stage. CERTIFIED BY: Telephone Connection The CONTRACTOR shall avail a temporary telecommunication facility at the site office. The COMPANY may, at its discretion, allow the CONTRACTOR to have temporary extension of telephone connection, if possible, from the existing telecommunication facility on remittance of telephone rental charges as per COMPANY regulations. Telephone sets and associated cabling shall be installed by the CONTRACTOR. APPROVED BY: Electricity Connection/Electrical Wiring The CONTRACTOR shall provide his own generators to meet construction, testing and commissioning power requirements. However, if power supply point is available near the PROJECT site, then a temporary metered electricity connection on chargeable basis will be provided by the COMPANY to the site office by Operating Area at the request of the CONTRACTOR. 1 2 3 NO. B. One (1) presentation board. Log books and office stationary. Portable fire extinguishers (of required quantity) First-aid box. Kitchen cabinets. One refrigerator Adequate number of Battery Operated Type Smoke Detectors Provide Bottled Drinking Water daily for Company Employees/Representative throughout the duration of the project. CER DATE 00 / 00 / 0000 E. Drainage Connection A temporary drainage connection from existing system shall be provided to the site office. Alternate arrangement as per standards shall be provided if drainage facility does not exist. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. F. Quality of Temporary WORK Temporary WORK shall conform to applicable COMPANY Standards and/or the requirement of concerned outside agencies and shall be removed from the premises upon completion of the WORK, unless specifically mentioned otherwise. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 33 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D G. 5-Star Safety and Health Management System DESCRIPTION The CONTRACTOR shall adhere to all applicable provisions of the COMPANY 5-Star Safety and Health Management System Standard/Element no. 1.1, 1.2, 1.3, 1.4, 1.6, 1.7, 1.8, 1.9, 1.10, 2.1, 2.2, 2.3, 2.24, 3.1, 3.2, 3.5, 3.7, 3.8, 5.6, 5.9, 5.18 & 5.23. H. Housekeeping and Cleanliness All rubbish and waste shall be removed at regular intervals from the site on daily basis. During construction, all nearby equipment shall be secured by CONTRACTOR to prevent the intrusion of the dust into these equipment. 1 2 3 NO. The CONTRACTOR shall have special attention in housekeeping and cleanliness as per applicable provisions of the COMPANY 5-Star Safety and Health Management System Standard/Element no. 1.4, 1.8 & 1.9. REVISIONS DEPT.: E&DD I. After obtaining the CONTRACTOR shall clearance certificates PROJECT or fifteen whichever is later. PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 J. APP DATE: 22 / 02 / 2021 demobilization approval from the COMPANY, the arrange to remove all temporary facilities and submit from the concerned authorities on completion of the (15) days after removal of the temporary facilities Site Office Ownership Site office and facility is the property of the CONTRACTOR and after PROJECT completion the CONTRACTOR will take back all the materials and accordingly all the materials will be returned to the CONTRACTOR. APPROVED BY: Demobilization 3.13 LOSS PREVENTION AND SAFETY REQUIREMENTS The CONTRACTOR and/or CONTRACTOR’S SUBCONTRACTOR(s) shall strictly comply with the Loss Prevention and safety requirements, in addition to the stipulations in Schedule A - General Terms and Conditions of CONTRACT: CERTIFIED A. BY: CER DATE General Requirements 1. Adherence to all applicable provisions of the COMPANY 5-Star Safety and Health Management System Standard/Element no. 2.2, 2.4, 2.5, 2.6, 2.9, 2.10, 2.13, 2.15, 2.16, 2.17, 2.18, 2.19, 2.21, 2.22, 2.23, 3.1, 3.2, 3.3, 3.4, 4.1, 4.2, 4.3, 4.4, 4.5, 4.7, 5.2, 5.6, 5.7, 5.16, 5.18, 5.18.3, 5.18.4, 5.19, 5.20, 5.21, 5.21.1, 5.22 & 5.23. 2. Compliance with the provisions of the COMPANY 5-Star Safety and Health Management System for the Instructions on WORK Permits (Standard/Element no. 2.2, 5.21 & 5.21.1). The CONTRACTOR shall have an authorized employee with certificate to receive WORK Permit. If the CONTRACTOR has no authorized employee, or has an employee with expired certificate, he shall be responsible to coordinate with the COMPANY REPRESENTATIVE for scheduling of WORK Permit training course. All 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 34 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA REVISIONS DEPT.: 3. Immediately upon the execution of the CONTRACT, CONTRACTOR shall prepare and submit its safety and loss prevention program to COMPANY, for COMPANY's approval. CONTRACTOR shall ensure full implementation of the program in accordance with the SOW/TS. CONTRACTOR shall appoint a safety supervisor to coordinate the program. 4. Prior to approval of the program by COMPANY, the Contractor’s Safety Engineer is required to conduct a safety presentation of the program to COMPANY representatives. The presence of the Contractor’s Project Manager is required during the safety presentation. 5. The CONTRACTOR shall provide necessary personal protective clothing (i.e. head, eye, face, hand, and foot protection) and respiratory protective equipment including personal protective equipment for fall protection such as safety belts and lifelines, and implement wearing them. The CONTRACTOR shall provide and use adequate and suitable safety/ warning signs, cordon tapes, portable barricades, warning lights and personnel protective equipment at the JOBSITE to protect the safety of COMPANY and CONTRACTOR personnel and the public, and to prevent damage to property. 1 2 3 NO. DESCRIPTION CHK’D activities of the CONTRACTOR near or inside the substation shall be allowed only after securing WORK Permit. E&DD 6. PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 7. The CONTRACTOR shall provide first aid facilities and must have a certified employee to administer first aid and Cardio-Pulmonary Resuscitation (CPR). 8. The CONTRACTOR shall refrain from using mechanized excavation equipment within restricted areas unless cleared and permitted to do so. 9. The CONTRACTOR shall request in advance a clearance for de-energizing the interfacing points and observe grounding procedures. APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: 10. The CONTRACTOR shall obtain from the COMPANY, ID cards for his employees and stickers for his vehicles/equipment prior to mobilization to site. 11. In order to prevent theft/loss of materials/equipment, the CONTRACTOR shall take the necessary measures and precautions including but not limited to the following: CER DATE a. All materials provided or used in this CONTRACT shall be stored by the CONTRACTOR in safe and secured locations even if stored for short period of time. b. If the equipment/materials are to be stored in the substation area for a prolonged period, the CONTRACTOR shall ensure that they are kept in locked containers or any other appropriate method of storage such that the materials/equipment are not easily noticeable by people with intention of theft or pilferage. Moreover, such containers shall be placed at a distance from the fence/boundary wall. 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 35 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D c. CONTRACTOR shall also consider other factors (i.e. temperature, humidity, etc.) affecting the storage of materials/equipment being stored in containers, to avoid any damage during such storage period. DESCRIPTION 12. The CONTRACTOR shall depute COMPANY approved safety supervisor on full time basis during entire PROJECT implementation period at site; to monitor, coordinate, administer and ensure full implementation of the program. Safety supervisor shall report directly to one level higher than the PROJECT Manager. PROJECT Involving Elevated WORKS 1. All cranes, lifting and bucket truck to be used by CONTRACTOR for the project shall have a valid Load Test Certificate and Sticker issued by an accredited Independent Testing Agency. 2. The CONTRACTOR’s ladders shall conform to OSHA (Occupational Safety and Health Administration) standard. Safety practices shall be followed in positioning ladders. Scaffolds shall be designed, built and inspected by a competent engineer prior to its use. 1 2 3 NO. B. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: C. D. 22 / 02 / 2021 CERTIFIED BY: 1. The CONTRACTOR shall provide suitable fire extinguishers to be used in case of fire emergencies. 2. The CONTRACTOR shall provide the welding gas cylinders with suitable rack that is equipped with security chain(s). PROJECT Near Energized Lines or Equipment Observe working clearances when working near or about energized line or equipment as per COMPANY’s Accident Prevention Manual. APP DATE: PROJECT Involving Welding and Cutting Operations E. PROJECT Requiring the Use of Chemical(s) Submit material safety data sheets (MSDS) of chemicals required or which are to be used in the execution of the PROJECT. CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 36 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 3.14 SHUTDOWN / OUTAGE COORDINATION DESCRIPTION Planned outages of existing equipment which are required for CONTRACTOR’s installation of new equipment or movement/relocation of existing equipment shall be minimized by CONTRACTOR during his PROJECT execution. 1 2 3 NO. Where outages of existing equipment cannot be avoided, CONTRACTOR shall coordinate all details of planned outages through the COMPANY REPRESENTATIVE with initial coordination occurring during the base design stage of the PROJECT. Overall detailed outage schedule indicating individual equipment and duration should be submitted in detail design stage of the PROJECT REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 As part of the CONTRACTOR’s coordination activity (for the planned outage), CONTRACTOR shall provide reasons, plans and detailed schedule for the planned outages that will be subjected to COMPANY’s review and approval. Prior to erection/installation of equipment and structures or any work which requires shutdown of transmission/distribution feeders or substation, CONTRACTOR shall closely coordinate with COMPANY. All outages shall be scheduled at least four (4) weeks in advance. COMPANY’s approval of planned outages shall be based solely on COMPANY’s operational considerations. CONTRACTOR shall note that, as a minimum requirement, COMPANY will consider approval of CONTRACTOR’s proposed planned outages during low load periods (beginning of November to start of April), and when CONTRACTOR provides enough manpower and equipment at the outage site(s) to minimize the planned outage time. APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED Any modification or erection of equipment/structures shall be planned with minimum downtime as much as possible. No unplanned outages/disruptions of COMPANY’s equipment or systems shall be allowed to support the CONTRACTOR’s installation of any new equipment, or CONTRACTOR’s movement/relocation of existing equipment at any site. For Communication equipment outage and outage coordination requirements, refer to Appendix - VI. 3.15 WORKING HOURS BY: CER DATE 00 / 00 / 0000 During the construction phase of the PROJECT, the CONTRACTOR shall work during the normal working hours of the COMPANY, i.e. 7:00 AM to 3:00 PM unless otherwise instructed by the COMPANY. However, for the WORK requiring outages, the CONTRACTOR shall be prepared to work during low load season on weekends or at nights, when outages are feasible. The CONTRACTOR shall coordinate with the COMPANY to get work permit before commencing the job. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 37 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 3.16 TRAVELING REQUIREMENTS DESCRIPTION The CONTRACTOR shall provide round trip transportation/airfare, accommodations and food for the selected COMPANY personnel, that will participate in the different activities as indicated on the relevant sections of this SOW/TS, based on the following minimum requirements: 1 2 3 NO. 1. For the airfare transportation requirements, CONTRACTOR shall provide IATA (International Air Transport Association) standard business class round-trip airfare tickets from international Airport in Saudi Arabia to the activities locations. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 2. For the ground transportation requirements, to/from activities locations to hotels/airports/restaurants which participants will be utilizing as well as for ground transportation from participants homes locations to Airports, the CONTRACTOR shall provide ground transportation through use of established and reputable taxi/limousine services for these COMPANY personnel. 3. For accommodations portion, CONTRACTOR shall provide accommodations for the COMPANY selected participants in either five star, or four star hotels near the activities locations. Also, each COMPANY participant shall be provided with both breakfast and dinner (“buffet” style) for the entire duration of the hotel stay. For food requirements at the activities locations, CONTRACTOR shall provide a “buffet” style lunch either at activities locations/facilities, or at a hotel/restaurant near the activities locations for each of the COMPANY participants. Also, international phone calls (within 20 minutes/day), laundry services, water & juices shall be provided for COMPANY Personnel. 4. APPROVED BY: Additionally, the CONTRACTOR shall be responsible for obtaining the necessary entrance VISA to the country (or countries) of the activities, locations and the CONTRACTOR shall pay the required entrance VISA and VISA application fees for each COMPANY participant. APP DATE: 22 / 02 / 2021 3.17 INSTRUCTIONS FOR TECHNICAL PROPOSAL The CONTRACTOR/BIDDER shall prepare and submit Technical Proposal as per “Instructions to Bidders for Technical Proposal” ITB. CERTIFIED BY: CER DATE 3.18 TECHNICALLY ACCEPTABLE MANUFACTURERS AND MANUFACTURING PLANTS 00 / 00 / 0000 The CONTRACTOR/BIDDER shall propose only equipment/materials from the SEC/National Grid SA "List of Technically Acceptable Manufacturers and Manufacturer Plants". THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 38 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 3.19 TRANSPORTATION ( as per requirement ) 1 2 3 NO. DESCRIPTION CONTRACTOR shall supply One (1) unit of brand new (Zero meter) vehicle for the exclusive use of COMPANY engineers within two (2) weeks from CONTRACT signing date. The cost of O&M of this vehicle shall be borne by the CONTRACTOR at no additional cost to COMPANY for a period that shall start from the date of handing over to and acceptance by COMPANY of the vehicle up to the issuance of Final Acceptance of the CONTRACT. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 O&M cost of the vehicles shall include but not limited to; The registration cost Comprehensive insurance Periodic and annual maintenance cost Accidental repairs The fuel & running charges During the absence of vehicle for any reason, the CONTRACTOR shall provide substitute vehicle for that period with same specifications. The vehicle to be supplied shall be returned to the CONTRACTOR after successful completion of Bid Package CONTRACT/s. The minimum specifications of vehicle shall be: Sr. # 1 Item Model Year APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 2 Engine 3 4 5 6 7 8 9 10 Transmission Color Seats Air Conditioner Steering Audio System Air Bags Brake System 11 Tires 12 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. 13 14 15 16 Ground Clearance Miscellaneous Safety Tools Wheel base: Window Specifications Latest Year Model 6-Cylinder, Minimum 3.5L, Fuel Injection; 4x4WD, 5 Door, Gasoline vehicles (Jeeps) of compact size either from Japanese or American Manufacturers only Automatic Submit Available Colors for Company Approval 5 Passengers Including Driver Hot & Cold Power Radio Driver & Front Passenger W/ ABS On/Off or All-Terrain, Temperature Rated “A” & Full Size Spare Tire & Rim Minimum 210MM Manufacturer Standard Towing Hooks Fire Extinguisher & Safety Triangle 97.6 in Window glasses shall be insulated (Shading) SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 39 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA 3.20 Oracle Primavera Portfolio Management Solution Implementation DESCRIPTION The COMPANY has launched the process of digital transformation by implementing Oracle Primavera Portfolio Management (OPPM) solution. This solution will be used for process interface between the COMPANY and CONTRACTOR for about 30 business process. In order to implement this solution, the following minimum software and hardware requirements shall be available at CONTRACTOR side for accessing Primavera applications for optimal performance: 1 2 3 NO. Software Requirement Oracle Primavera Unifier Release v17.7 (17.7) Tested Configurations Client and Browser Information This document covers the tested configurations for Primavera Unifier REVISIONS DEPT.: E&DD Version Supported Client OS / Email Clients Client OS 32/64 bit Supported Browsers JRE Vendor Version Exceptions and Additional Information Unifier 17.7.0.0 PREP. BY: NAME SAMI DATE: APPROVED BY: APP DATE: 17.7 Windows 10 64 bit Internet Explorer 11.x Firefox 52.1.x (ESR) + Chrome 58.x + Microsoft Edge 20+ Oracle JRE: 1.8.0_131 JRE is used for Markups 17.7 Windows 8.1 Windows 7 (SP1) 64 bit Internet Explorer 11.x Firefox 52.1.x (ESR) + Chrome 58.x + Oracle JRE: 1.8.0_131 JRE is used for Markups 17.7 Windows 10 (Windows Surface Pro) 64 bit Internet Explorer 11.x Firefox 52.1.x (ESR) + Chrome 58.x + Microsoft Edge 20+ Oracle JRE: 1.8.0_131 JRE is used for Markups 17.7 Windows 8.1 (Windows Surface Pro) 64 bit Internet Explorer 11.x Firefox 52.1.x (ESR) + Chrome 58.x + Oracle JRE: 1.8.0_131 JRE is used for Markups 17.7 Windows 10 32 bit Internet Explorer 11.x Firefox 52.1.x (ESR) + Chrome 58.x + Microsoft Edge 20+ Oracle JRE: 1.8.0_131 JRE is used for Markups 17.7 Windows 8.1 Windows 7 (SP1) 32 bit Internet Explorer 11.x Firefox 52.1.x (ESR) + Chrome 58.x + Oracle JRE: 1.8.0_131 JRE is used for Markups 17.7 Mac OS X 10.12 (Sierra) 64 bit Safari 10.0.x + Firefox 52.1.x (ESR) + Chrome 58.x + Oracle JRE: 1.8.0_131 JRE is used for Markups 17.7 iOS 9.x (iPad and iPhone) iOS 10.x (iPad and iPhone) n/a n/a n/a n/a n/a n/a 1. Supported for only Unifier Mobile Native iOS App 1. Supported for only Unifier Mobile Native iOS App 11 / 02 / 2021 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 17.7 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 40 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D Oracle Primavera Portfolio Management Release 16.1.2.0 Tested Configurations - Client and Browser Information This document covers the tested configurations for Oracle Primavera Portfolio Management. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: Client OS Client OS 32/64 bit Supported Browsers OPPM 16.1.2.0 Windows 7 (SP1+) 64 bit Chrome 57.x Internet Explorer 11.x OPPM 16.1.2.0 Windows 7 (SP1+) 32 bit Chrome 57.x Internet Explorer 11.x OPPM 16.1.2.0 Windows 8.1 64 bit Chrome 57.x Internet Explorer 11.x OPPM 16.1.2.0 Windows 8.1 32 bit Chrome 57.x Internet Explorer 11.x OPPM 16.1.2.0 Windows 10 64 bit Chrome 57.x Internet Explorer 11.x Microsoft Edge OPPM 16.1.2.0 Windows 10 32 bit Chrome 57.x Internet Explorer 11.x Microsoft Edge OPPM 16.1.2.0 Mac OS X 10.11 (El Capitan) 64 bit Safari 10.0.x Chrome 57.x OPPM 16.1.2.0 Windows Surface 64 bit Exceptions and Additional Information Minimum client • Pentium 4, 1GHz or higher • 1 GB RAM or higher as required by client OS 1 2 3 NO. DESCRIPTION Client and Browser Support Version Supported 11 / 02 / 2021 - Internet Explorer 11.x Microsoft Edge Chrome 57.x - Oracle Fusion Middleware 12c (12.2.1.2.0+) Certification Matrix BROWSER APPROVED BY: Product Offering Release Browser Vendor Browser Version ALL FMW 12.2.1.2. 0+ Microsoft Edge 25.x APP DATE: 22 / 02 / 2021 CERTIFIED BY: JREVEND OR Applicable to Oracle Forms, WebCenter Content Product Line and EDQ Oracle JRE JREVERSI ON Applicable to Oracle Forms and EDQ JREVERSION Applicable to WebCenter Content Product Line Exceptions and Additional Information 1.7.0_99+ 1.8.0_101+ 1.8.0_101+ 1. Oracle Forms can only be used with Microsoft Edge when using Java Web Start. CER DATE 00 / 00 / 0000 ALL FMW 12.2.1.2. 0+ Microsoft Internet Explorer 11.* Oracle JRE 1.7.0_99+ 1.8.0_101+ 1.8.0_101+ THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 2. Oracle BI Publisher not Supported. Browser support is no longer based on Operating Systems but strictly tied to the browser themselves, no matter which Operating Systems they are installed on. INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 41 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA FMW 12.2.1.2. 0+ Google Chrome 53+ Oracle JRE 1.7.0_99+ 1.8.0_101+ 1.8.0_101+ REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: ALL FMW 12.2.1.2. 0+ Mozilla Firefox 45+ Oracle JRE 1.7.0_99+ 1.8.0_101+ 1.8.0_101+ ALL FMW 12.2.1.2. 0+ Apple Safari 8.* Oracle JRE 1.7.0_99+ 1.8.0_101+ 1.8.0_101+ 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. 3. Oracle Forms can only be used with Chrome when using Java Web Start. Browser support is no longer based on Operating Systems but strictly tied to the browser themselves, no matter which Operating Systems they are installed on. 1. Browser support is no longer based on Operating Systems but strictly tied to the browser themselves, no matter which Operating Systems they are installed on. 2. For SOA support on Safari 8.*, refer to 'Safari Browser Links tab missing and Decision Properties Overlaps with Actions' and '[SAFARI] 2ND RIGHT CLICK OPTION IS NOT WORKING IN LHN' in the 'Known Issues for Oracle SOA Products and Oracle BPM Products for 12c Release 1 (12.2.1.0.0)' documentation -> http://www.oracle.c om/technetwork/mi ddleware/soasuite/ documentation/soa known2644661.html CERTIFIED BY: 1. Browser support is no longer based on Operating Systems but strictly tied to the browser themselves, no matter which Operating Systems they are installed on. 2. When using Chrome with Java plug-in for Oracle Forms, WebCenter Content Product Line and EDQ, refer to http://java.com/en/ download/faq/chro me.xml 1 2 3 NO. DESCRIPTION CHK’D ALL SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 42 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء ALL FMW 12.2.1.2. 0+ Apple Safari 9.* Oracle JRE 1.7.0_99+ 1.8.0_101+ 1.8.0_101+ ALL FMW 12.2.1.2. 0+ Apple Safari 10.* Oracle JRE 1.8.0_131+ 1.8.0_131+ 1 2 3 NO. DESCRIPTION CHK’D APP’D NATIONAL GRID SA Browser support is no longer based on Operating Systems but strictly tied to the browser themselves, no matter which Operating Systems they are installed on. Browser support is no longer based on Operating Systems but strictly tied to the browser themselves, no matter which Operating Systems they are installed on. REVISIONS Hardware Requirements DEPT.: E&DD PC/Laptop with i4/i5 processor. RAM 4/8 GB is the minimum requirement for accessing Primavera applications. PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 **** END OF SECTION **** APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 43 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D SECTION IV - SCOPE OF WORK 4.01 GENERAL 1 2 3 NO. DESCRIPTION A. The CONTRACTOR shall execute this PROJECT on a Lump Sum Turnkey (LSTK) basis consisting of the major equipment/systems indicated in this section. All components and accessories required for the satisfactory operation of the new facilities of the PROJECT, whether specifically mentioned/specified in detail or not shall be supplied and installed as necessary. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 B. The CONTRACTOR shall perform on LSTK basis, the design, engineering, material procurement, quality management, factory inspection/testing, transport and delivery to site, construction, site inspection, testing and commissioning, and all associated work and services, including relocation/reinstatement of existing utilities and services disturbed during construction, until final handing over of this PROJECT in a satisfactorily working and operating condition to the COMPANY as specified in this Scope of WORK and Technical Specifications. C. The CONTRACTOR / BIDDER shall visit the sites and make himself aware of the details of the existing system/facilities. The modification work if required to be performed by the Contractor at the associated substations, cable boxes or anywhere shall be compatible with the existing system. 4.02 ELECTRICAL WORK I. General Items: APPROVED BY: A. Supply, manufacture, deliver, install, test and commission all necessary cable splices along with link boxes, SVLs, Joint boxes, terminations, cable supports and clamps, and other accessories (link box barricades etc) and grounding them as required for installation of 110KV XLPE Cables as per Company Standards. B. Testing and commissioning of proposed underground cables as per COMPANY standard TCS-P-105 end-to-end and documentation of the results. C. All the WORK mentioned under this PTS shall establish the complete 110KV circuits link between Substations. APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 D. Complete survey and investigation for the whole routes of the proposed 110KV underground cable circuits. All utilities found, existing roads and future roads shall be surveyed with complete details and reflected in design drawings. For the proposed 110KV underground cables route, refer to drawing no. <<WT925382>>. E. Perform soil electrical & thermal resistivity measurements along the whole cable routes as per Section 5.02. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. F. Design and installation of horizontal directional drilling, thrust boring, concrete encased ductbanks and sand ductbanks as required at road crossings. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 44 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D G. All the new equipment to be installed under this PROJECT shall be provided with grounding conductors and connected to the involved grounding grid. DESCRIPTION H. All the cables in the substations basements shall be fire proofed as per TES-P104.05. I. All outdoor Insulators, cable sealing ends, outdoor surge arresters and other outdoor terminations shall be either coated with RTV (silicon rubber hydrophobic paint) coating or silicon rubber composite type to avoid insulator washing as per latest Standards (TCS-P-122.22, 15-TMSS-07, TES-P-122-01). 1 2 3 NO. J. Material tests and documentation of the results. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: K. All dismantled items under this PROJECT shall be handed over and transported to COMPANY designated warehouse, including loading and unloading, or as directed by the COMPANY REPRESENTATIVE during the execution of the PROJECT. L. 11 / 02 / 2021 Provide the required high voltage test bushings at Source Substation and << NEW>> Substations for cable HV test. The high voltage test bushings are the property of the CONTRACTOR. M. All required WORK, materials and accessories in this PROJECT shall be provided and performed by the CONTRACTOR. N. Creepage distance for outdoor bushings/housings, follow 01-TMSS-01 and correction factor shall be used for equipment installed above 1000 meters from sea level. APPROVED O. Modification/replacement of GIS cable box (if applicable) to accommodate bigger cross section/diameter of cable as part of contract. BY: APP P. DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 For all new/ loop in-and-out circuits, Contractor shall propose New numbering/naming (from Source to destination substation). New Circuit name plates at Source and Destination substations shall also be provided by the Contractor. Q. In case of loop in and out (LILO) of existing Cable circuits contractor have to establish bonding system scheme to maintain the sheath withstanding voltage , circulating current and all parameters according to the latest Company standards. All the material required but not limited to link boxes, grounding conductor and dummy joints for new as well as for existing circuits to be supplied and installed by contractor for complete newly established circuit (end to end). R. If there is any conflict /contradiction between PTS clause and NG standards then Bidder/Contractor, have to bring to the notice of NG and get approval in writing from concerned quarters and their decision will be final. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 45 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D II. Power Supply: A. New 110KV U/G XLPE Cable Circuit/s between S/S <<NAKHEEL Substation >> and << Madinah ISTP Substation>> CONTRACTOR shall design, supply and install << one (1) >> new 110KV underground cable circuits, single cable/phase, consisting of 3×1C×1200mm2, XLPE, copper conductor with metallic shield copper wire and copper tape, to be laid between the << New Substation >>and SOURCE SUBSTATION˃˃, to form the new circuit << NAKHEEL Substation ˃˃ - << Madinah ISTP Substation >>, complete with necessary duct banks, HDD, hand holes and manhole & trenches for power cables as well as for Non-metallic Fiber Optical Cables, with required link boxes, SVLs, insulated joints, earthing, other accessories and terminations in accordance to latest COMPANY Standards and as shown in cable route drawing # WT- 925382 and CONNECTION diagram WT-925380. proposed bay (E08) will be available at NAKHEEL S/S to use for connection with Madinah ISTP project. B. New 110KV U/G XLPE Cable Circuits between new S/S <<ISUNI-2 Substation >> and <<New Madinah ISTP Substation>> CONTRACTOR shall design, supply and install << one (1) >> new 110KV underground cable circuits, single cable/phase, consisting of 3×1C×1200mm2, XLPE, copper conductor with metallic shield copper wire and copper tape, to be laid between the << New Substation >>and SOURCE SUBSTATION˃˃, to form the new circuit << ISUNI-2 Substation ˃˃ - << Madinah ISTP Substation >>, complete with necessary duct banks, HDD, hand holes and manhole & trenches for power cables as well as for Non-metallic Fiber Optical Cables, with required link boxes, SVLs, insulated joints, earthing, other accessories and terminations in accordance to latest COMPANY Standards and as shown in cable route drawing # WT- 925382 and CONNECTION diagram WT-925380. proposed Spare Bay (AD12) is already available at ISUNI-2 S/S to use for 1 2 3 NO. DESCRIPTION The Scope of WORK of this PROJECT, to be carried out by the CONTRACTOR shall include but not limited to the following: REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 Connection with Madinah ISTP project. CERTIFIED BY: CER DATE 4.03 Gassing & Degassing 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. 1. Perform gassing & degassing for concerned GIS cable compartments at Source S/S (110KV/380kV) and New Substations (110KV) for the above mentioned WORK. Gassing & degassing WORK, including electrical tests is the Transmission Line CONTRACTOR’S responsibility but it should be carried out under supervision of a Specialist Qualified & Authorized representative of GIS Manufacturer or as approved by COMPANY. 2. All parts or links if necessary to modify the old GIS interface to match the new sealing ends shall be as per IEC standards. 3. Local Manufacturer of any part for the GIS shall not be acceptable unless those SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 46 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA DESCRIPTION CHK’D are as per manufacturer's drawings and material and approved by COMPANY concerned Department. 4. Modification (addition/connection) on existing or new GIS must be done by certified specialist only under supervision of GIS Manufacturer. 5. Hiring responsibility of the GIS Manufacturer’s Supervisor for cable terminations is in the scope of Cable CONTRACTOR. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: CIVIL WORK 1 2 3 NO. 4.04 1. Earthworks (including cutting, excavation, backfilling, etc.) and road re-asphalting shall be in accordance with the requirements and specifications of Ministry of Municipal and Rural Affairs (area Municipality) or other concerned agencies (government/nongovernment). In addition, the excavation, backfilling and road reasphalting shall be performed through one of the Municipality’s/concerned agencies’ approved contractors. The CONTRACTOR shall appoint the Municipality/concerned agency approved contractor as sub-contractor. 11 / 02 / 2021 2. Re-asphalting requirements for affected roads shall be as per the right of way approval conditions given in ROW Appendix (Municipality/concerned agencies) or provided by concerned agencies. Further, Municipality (or concerned agencies) shall decide & determine the roads width to be re-asphalted. 3. For other civil work requirements, refer to Appendix – VII. APPROVED 4.05 COMMUNICATION WORK Refer to Appendix-VI, Communication Scope of Work and Technical Specifications. BY: APP DATE: 22 / 02 / 2021 4.06 PROJECT DESIGN DOCUMENTS, CALCULATIONS AND DRAWINGS The CONTRACTOR shall submit all design documents, calculations, studies and drawings at various stages of the PROJECT as per Table 4.01 & 4.02 & APPENDIXVIII, as a minimum. CERTIFIED BY: Table 4.01 CER DATE 00 / 00 / 0000 A THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DOCUMENT DESCRIPTION INDEX BID STAGE EQUIPMENT / MATERIALS Power Cables Power Cable Indoor and/or Outdoor Termination Kits Power Cable Splice Kits surge arresters ( as per requirement ) Link Box along with its accessories Non Metallic Fiber Optic Cable (NFOC) X X X X X X X - Indicates requirement for submission. Notes to the above Table (Table 4.01): JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 47 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA The following shall be provided for each indicated item in the table: - Completely filled-in Data Schedules duly signed, stamped and dated by the respective equipment/material Manufacturer and the CONTRACTOR. Equipment catalogues makes, type and technical parameters duly highlighted. Certified Type (Design) Test report. Compliance statement for each applicable TMSS and for 01-TMSS-01 separately, duly signed, stamped and dated by the Equipment/Materials Manufacturer and CONTRACTOR. Compliance statement for the scope of WORK as outlined in this PTS. List of deviations, if any. DESCRIPTION - REVISIONS DEPT.: Table 4.02 1 2 3 NO. - E&DD A PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 A/P/T/ M/Q/R APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED A BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. BASE DESIGN STAGE DOCUMENT DESCRIPTION INDEX EQUIPMENT / MATERIALS Non Metallic Fiber Optic Cable (NFOC) NFOC Accessories Fiber Optic Cable Joint Boxes Communication PullBox HDPE/Corrugated subducts DESIGN DRAWINGS SITE Layout Relaying and Metering - System One Line Diagram Fiber Optic Cables Routing Plan and profile, Sections and Details Fiber Optic Cable Interconnection Diagram Key Plan - Fiber Optic Cable Fiber Optic Cable Route/Layout Inside Both Substation Fiber Optic Cable Pulling Plan and Calculations Details Mandrel Test Plan Details Communication Handhole Plan Communication Handhole fold outs and details Overall FOC cable layout U/G NFOC Route plan Fiber Optic Cable Splicing details OPGW and OGW fixing clamp details on latticed steel/steel monopole structures OPGW/OGW fitting and hardware assembly details TEST PLAN, SCHEDULE, PROCEDURES ETC. PROJECT PERT/CPM Schedule for Monitoring and Control Activities CONTRACTOR’S Loss Prevention Program Site Security Plan QA/QC Plan Inspection, Test Plan and Factory Test Procedure for Materials Site Pre-commissioning & Commissioning Plan Site Work Test Procedure Preliminary Outage Schedule and Plan Final Outage Schedule and Plan DETAIL DESIGN & CONSTRUCTION STAGE AS-BUILT STAGE X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X - Indicates requirement for submission. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 48 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D Notes to the above Table 4.02: 1. Base Design Stage The following shall be provided for each indicated item in the table: a. Design calculations b. Original manufacturer’s drawings and literatures. c. Design drawings d. Final data schedules duly signed, stamped and dated by both equipment Manufacturers and CONTRACTOR. e. Final compliance statement for each applicable TMSS and for 01-TMSS01 separately, duly signed, stamped and dated by the Equipment/Material Manufacturer and CONTRACTOR. f. Vendor drawings g. Certified Type (design) Test Reports 1 2 3 NO. DESCRIPTION Final approval of major equipment (indicated under bid stage, Table 3.01), after all deviations have been resolved, shall be obtained. REVISIONS DEPT.: E&DD 2. Final Design Stage PREP. BY: NAME SAMI DATE: - 11 / 02 / 2021 3. APPROVED BY: DATE: DETAIL DESIGN & CONSTRUCTION STAGE (Issued for Construction Drawings - IFC/Noted By) - APP Final design drawings shall be provided for each indicated item in the table. Final design calculations for the PROJECT and additional calculations, if required. Vendor drawings Final Issued for Construction drawings shall be provided for each indicated item in the table. Revised final Issued for Construction drawings shall be provided, if required. 22 / 02 / 2021 4. As-Built Stage a. As-built drawings shall be provided for each indicated item in the table. b. The As-built drawings for Power and Fiber Optic Cable Routes shall include UTM, Ain EL Abd – Saudi Arabia Coordinates of all Cable and Joints locations on following scales: CERTIFIED BY: CER DATE 00 / 00 / 0000 5. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. Key Plan: 1:10000/1:20000 depending on the Route-Length or as directed by the COMPANY. Detailed Drawings: 1:300/1:1000 depending on the Route-Length or as directed by the COMPANY. Along with all design submittals, Base design package, Final detail design package and As-Built drawings package, the CONTRACTOR shall submit the following in Adobe Portable Document Format (PDF) files: a. Design Drawings b. Design Calculations c. Material Data Schedules d. Equipment Technical Data SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 49 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA DESCRIPTION Each discipline documents shall be arranged in a separate folder designated by discipline's name. Contractor shall submit three (3) sets of each submittal in compact discs (CDs) and (USBs). Each CD or USB shall be labeled with project identification information and CD or USB table of contents. All PDF files shall have no security protection. 1 2 3 NO. The revision numbers and notes reflecting the changes made throughout the design submittals shall be retained in the submitted final detail design drawings. 6. For additional documentation requirements for Communication systems, refer to Appendix - VI. 7. All calculations, studies, reports, drawings/sheets, Manufacturer/Vendor drawings/sheets shall be given standard COMPANY drawing numbers and format in accordance with SEEDS-II-01 and the same shall be included in the drawing control sheet as part of Project drawings/calculations. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: *** END OF SECTION *** 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 50 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D SECTION V - ENGINEERING DESIGN CRITERIA AND REQUIREMENTS The CONTRACTOR shall adopt the following design criteria and requirements for the PROJECT as a minimum: DESCRIPTION 5.01 GUIDELINES FOR PREPARATION OF DESIGN CALCULATIONS A. Scope 1 2 3 NO. This Section covers mandatory the requirements governing the preparation of underground power cables design, design calculations and all associated and required WORKS. REVISIONS DEPT.: E&DD The criteria and general design outlined below shall be adopted as applicable to the basic design of the PROJECT, and shall also serve as the basis in the development of detailed design by the CONTRACTOR subject to necessary adjustments and implementation particularly in consideration of geologic conditions of SITE. B. General Presentation PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 The calculation presentations shall be in accordance with the following procedures and requirements. 1. The heading shall provide the following information: a. b. c. BY: DATE: APPROVED 2. Calculation packages shall include a Table of Contents and a listing of all codes and referenced used. APP 3. All calculations shall be checked, initialed as checked before being sent to COMPANY. 4. Sufficient explanation shall be given so that the calculation methods are easily comprehensible. For this reason, simple clear sketches should be liberally used. The COMPANY will not accept calculations whose approach is not adequately described. 5. Calculations are to be in the English language throughout. 6. The cover sheet of each calculations package shall be assigned a COMPANY drawing number to identify the calculations for a particular Job Order, and for inclusion in COMPANY permanent records. Individual calculations sheets following the cover sheet shall be consecutively numbered (1, 2, 3, etc.). 7. All calculations shall be done using SI metric units, except when calculations are made in compliance with a code, or using a computer program, which has not yet been in metric, the conventional calculations shall be converted to metric units. 22 / 02 / 2021 CERTIFIED BY: CER DATE Name of the originator of the calculations and the name of the checker. The title, which shall clearly describe the contents of the calculations. The date the calculations were made. 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 51 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 8. Purpose of calculations: a. DESCRIPTION b. c. 9. Symbols shall conform to the corresponding International Codes and Standards that are referenced in the applicable COMPANY Standard. The connotation of all symbols, in general, used throughout the calculations shall be started at the beginning of the calculations. The connotations of symbols used only locally shall be stated immediately before or after the equations in which they are used. 10. Parameters or design data shall be justified either by quoting a source, or by brief reasoning or reference to a standard or code. 1 2 3 NO. d. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 To enable the designer to arrive at designs which are safe, feasible and economical. To provide a record for possible future reference. To satisfy code and/or COMPANY requirements as to the adequacy of the design. To facilitate determination of the effects of possible future modifications. C. Assumptions Assumptions on which calculations are based shall be listed in an orderly manner. CONTRACTOR shall clearly spell out the analysis/design methodology/philosophy adopted in the design for this PROJECT. The decision to adopt a particular analysis/design method shall solely be on the discretion of the COMPANY. D. Computer Calculations APPROVED BY: Computer calculations shall be in accordance with the following guidelines: 1. All computer models shall be accompanied by the corresponding input. Data provided, as computer program shall be clearly distinguished from those computed in the program. The engineer responsible for the design shall sign the first sheet of each computer run. A program description (user’s guide) and the computer programs shall be available upon request and contain the information necessary to determine the nature and extent of the analysis, verify the input data, interpret the results, and determined whether the computations comply with these recommendations. 2. A computer diskette/Compact Disc containing a copy of the input and output files shall be furnished to COMPANY for all computer models to aid in the review at all design stages. 3. Contractor shall use only recognized and renowned international computer software. However, other commercial and propriety software may be acceptable provided that the suitability and reliability of the results have been verified and that this verification is furnished upon request. It is solely up to the COMPANY to accept such programs. 4. A summary of analysis results should be provided that are extracted from the computer output. This summary should clearly state the result achieved. APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 52 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 5.02 ENVIRONMENTAL CONDITIONS DESCRIPTION All equipment and materials, and their specified ratings furnished under this PROJECT shall be suitable for operation under the service conditions outlined in the COMPANY Material Standard Specification 01-TMSS-01, General Requirements for All Equipment/Materials. In case of a conflict between the service conditions requirements specified in Material Standard Specifications 01-TMSS-01 and other TMSS, the requirements specified in 01-TMSS-01 shall prevail. 1 2 3 NO. Soil Thermal Resistivity REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 The soil thermal resistivity is largely dependent on density and water content of the relevant type of soil. Therefore, the actual thermal resistivity of the soil along the whole power cable route shall be measured prior to the design and all test results shall be included in the base design package. and the tested value shall be used in the current rating calculations The following shall be considered during soil thermal resistivity measurements: APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: Samples for soil thermal resistivity measurements shall be taken at every 500m along the cable route. Samples for soil thermal resistivity measurements shall be taken at or near each Horizontal Directional Drilling or Thrust Boring locations (if applicable). The location of these samples along the route shall be subject to COMPANY review and approval. The soil thermal resistivity shall be determined for (1.0% - 2.0%) moisture content on the samples. In all cases, the value of 1.20 k.m/W shall be used in the calculations whenever the measured values are less than 1.20 k.m/W. Soil thermal resistivity analysis and measurements report shall be submitted along with calculations. The back fill material should not have soil thermal resistance of more than 1.2 Km/W. as mentioned in COMPANY Standard # TCS-P-104.06. CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 53 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 5.03 ELECTRICAL CHARACTERISTICS The UGTL design parameters shall be in accordance with the following table :Table 5.01 1 2 3 NO. DESCRIPTION Serial No. REVISIONS DEPT.: E&DD REQUIREMENT 1. 2. General Sheath Sizing Calculations 3. 4. Non-Linear Resistor (Resistance) Grounding Cable/Conductor 5. Cable Pulling Tension and Sidewall Pressure Calculations Cables Transposition 6. COMPANY Standards/ Other Standards 01-TMSS-01 IEC-60949, 11-TMSS-02 & TES-P-104-03 12-TMSS-10 11-TMSS-12, TES-P-104.08, ICEA P-45-482 & IEC 60949 TES-P-104.05 & TCS-P-104.06 TES-P-104.08 5.04 DESIGN REQUIREMENTS The following design requirements shall be considered by the CONTRACTOR. PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 A. Cable Ampacity Calculations APPROVED BY: APP DATE: 1. The Cable Ampacity (continuous) calculations shall be as per IEC 60287 1-1, 1-2 &1-3. These calculations shall assure the availability of the required Ampacity for actual cables' installations and at SITE conditions, particularly at worst points. 2. The CONTRACTOR shall confirm that each of the << 3×1C×1200mm2>> Cu. XLPE cable energized circuits can carry a minimum of <<180 MVA>> continuously under all operating conditions. 3. Loading factor for cables shall be assumed 100%. 4. Type of Sheath/Screen Bonding is = Cross Bonding. 5. The ambient ground temperature shall be considered 40 oC as per company standard 01-TMSS-01. 6. Cable Ampacity calculations shall be carried out based on actual soil thermal resistivity measurements. 7. For cables installed in Direct Buried, the following shall be considered in the calculations: Minimum soil thermal resistivity = 1.2 k.m/W. (However, higher values to be considered if actual soil thermal resistivity measured values are higher). Depth of laying. Clearances between circuits and between phases. 8. For cables installed in Concrete Ductbanks, the following shall be considered in the calculations: Concrete Thermal Resistivity (min. = 1.0 k.m/W). 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 54 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 9. For cables installed in Sand Ductbanks, the following shall be considered in the calculations: Minimum soil thermal resistivity = 1.2 k.m/W. (However, higher values to be considered if actual soil thermal resistivity measured values are higher). Cables are laid in PVC ducts embedded in the existing soil. The thermal resistance of air space between cable surface and PVC internal surface shall be considered. Thermal resistivity of PVC ducts. Depth of laying. Clearances between circuits and between phases. 10. For cables installed in Horizontal Directional Drilling (HDD), the following shall be considered in the calculations: Minimum soil thermal resistivity = 1.2 k.m/W. (However, higher values to be considered if actual soil thermal resistivity measured values are higher). Cables are laid in HDPE ducts embedded in the existing soil. The thermal resistance of air space between cable surface and HDPE internal surface shall be considered. Thermal resistivity of HDPE ducts. Depth of laying. Clearances between circuits and between phases. 11. For cables installed in Thrust Boring, the following shall be considered in the calculations: Minimum soil thermal resistivity = 1.2 k.m/W. (However, higher values to be considered if actual soil thermal resistivity measured values are higher). Cables are laid in PVC or HDPE ducts embedded in the existing soil by steel pipes. The thermal resistance of air space between cable surface and PVC or HDPE internal surface shall be considered. Thermal resistivity of PVC or HDPE ducts. Depth of laying. Clearances between circuits and between phases. 12. In case the required cable Ampacity is not achieved due to any reason, the CONTRACTOR shall perform the required study/calculations to propose the necessary mitigations/solutions to achieve the required Ampacity. Some mitigations/solutions are: increasing/varying the clearances between circuits, increasing/varying the clearances between phases (for flat configuration), reducing cables depth of burial, improving the soil thermal resistivity, etc. 1 2 3 NO. DESCRIPTION REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. Minimum soil thermal resistivity = 1.2 k.m/W. (However, higher values to be considered if actual soil thermal resistivity measured values are higher). Cables are laid in PVC ducts embedded in concrete ductbank. The thermal resistance of air space between cable surface and PVC internal surface shall be considered. Thermal resistivity of PVC ducts. Depth of laying. Clearances between circuits and between phases. 13. The CONTRACTOR shall provide enough number of actual cable layout crosssections along the cable route with Ampacity calculations. The cross-sections shall be for expected worst conditions in terms of cable spacing, depth, etc. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 55 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 14. The CONTRACTOR shall clarify all parameters/assumptions for which the calculations are based. DESCRIPTION C. Metallic Sheath Grounding The grounding system of the power cable shall be designed to limit the induced voltage on the cable sheath at safe level and to eliminate the sheath losses. 1. The CONTRACTOR shall use cross-bonding scheme and shall submit his design / detailed calculations to comply with all requirements per IEEE 575, Electra (28), Electra (47), Electra (128) and CIGRE Brochure (283) for COMPANY review / approval. 2. The power frequency sheath voltage induced under through fault conditions (3-phase, phase to phase and single phase to ground faults) shall be calculated by the applicable methods and formulas as recommended in IEEE 575, Electra (28), Electra (47), Electra (128) and CIGRE Brochure (283) for cross bonding systems. 3. Cable sheath voltage limiters shall be installed at location as recommended in IEEE 575, Electra (28), Electra (47), Electra (128) and CIGRE Brochure (283). 4. The sheath normal/ induced (standing) voltage shall not exceed 200 volts, when cable is carrying the specified full load current. Also, the metallic sheath shall be directly grounded at both end terminations through a link box. 5. The cable sheath induced voltage under short circuit conditions shall not exceed 5000 volts to ground. 6. The induced shield voltage should be calculated at the worst case and assuming a short circuit current of 40 kA for 1 second. 7. The CONTRACTOR shall sectionalize the total cable length in such a way to satisfy above criteria. 8. The CONTRACTOR shall clarify all parameters/assumptions for which the calculations are based. 1 2 3 NO. For metallic sheath grounding, TES-P-104.08 shall be applied considering the following: REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 D. Cable Sections Lengths Cable sections lengths (section cutting lengths) depend mainly on the type of grounding/bonding system scheme (approved Metallic Sheath Grounding calculations & drawings). THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. Metallic Sheath Grounding calculations & drawings shall be provided as per Section 5.04.C & 4.06, Table 4.02. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 56 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D E. Arrangement/Grouping of Cables in the Ground DESCRIPTION 1. Cables grouped in a common cable trench or installed with insufficient spacing from one to another, result in mutual heating. Thus, load capacity of cables is subsequently reduced. Therefore, spacing in flat formation of single core cables, recommended by COMPANY Standards shall be maintained. The same shall be considered to overcome the effect of existing Power cables. If the right-of-way limits the cable spacing and calculated cable Ampacity is reduced, a necessary mitigation shall be provided to achieve the required Ampacity. 1 2 3 NO. 2. The cables shall not be placed in a close proximity to external heat sources. F. Interference of Power Cables with Telecommunication Cables REVISIONS DEPT.: E&DD Power cables that are in parallel with telecommunication cables of other utilities, shall maintain sufficient clearances as per Saudi Telecom Company (STC) requirement. In case the required clearance can not be achieved, a study shall be performed and necessary mitigation shall be provided. PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 5.05 STANDARDS, CODES AND SPECIFICATIONS All WORK equipment and materials covered by this document shall conform to the latest edition of the COMPANY’S Material Standard Specifications supplemented with latest applicable Standards, Codes and Specifications. The latest edition of each Standard and Specifications shall mean the latest edition specified hereunder. The CONTRACTOR shall strictly comply with the following Standards, Codes and Specifications, and no deviation shall be accepted unless otherwise supported by a written waiver from the COMPANY. The CONTRACTOR may propose “equivalent” Standards and Specifications if such Standards and Specifications are in fact equal or better than those specified herein, and shall be subject to prior approval of the COMPANY. NOTES: CERTIFIED BY: COMPANY is in the process of updating/revising their standards (TMSS, TES, TCS, and standard drawings). Hence, the new revised standards/drawings shall replace and supersede the old standards/drawings. List of applicable COMPANY standards/drawings are given below. Index of approved transmission standard and specifications (new) is attached in Appendix II. CER DATE 00 / 00 / 0000 All COMPANY standards and specifications shall be the latest revision THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. # A. Std/Sepc. No. Saudi Arabian Standards SASO/SSA-2 Steel Bars for Reinforcement of Concrete SASO/SSA-39 Mechanical Test of Welded Joints SASO/SSA-53 Graphic Symbols SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> Title/Description SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 57 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D # SASO/SSA-55 C. COMPANY Material Standard Specifications 01-TMSS-01 General Requirements for All Equipment/Materials 1 2 3 NO. DESCRIPTION International Standards and Codes ACI MCP American Concrete Institute – Manual of Concrete Practice AEIC CS9 Association of Edison Illuminating Companies Specification for Extruded Insulation Power Cables and Their Accessories Rated Above 46kV Through 345kV ANSI C2 National Electric Safety Code IEEE 575-2014 IEEE Guide for Bonding Shields and Sheaths of Single-Conductor Power Cables Rated 5 kV through 500 kV Electra (28) The Design of Specially Bonded Cable Systems (Part (1973) I) CIGRE Study Committee no. 21, Working Group 7 Electra (47) The Design of Specially Bonded Cable Systems (Part (1976) II) CIGRE Study Committee no. 21, Working Group 7 Electra (128) Guide to the Protection of Specially Bonded Cable (1990) Systems against Over Sheath Voltages CIGRE Study Committee no. 21, Working Group 7 Electra (151) Earthing of GIS - An Application Guide 1993 CIGRE Working Group 23.10 CIGRE Brochure Special bonding of high voltage power cables (283 - 2005) 2005, Working Group B1.18 ICEA P-45-482 Short Circuit Performance of Metallic Shields and (2007) Sheaths of Insulated Cable (2nd Edition) IEC 60287-1-1, Electric Cables-Calculation of the Current Ratings 1-2 &1-3 IEEE 80 Guide for Safety in AC Substation Grounding ISO/R-31 Unit of Measure NFPA 70 National Electric Code (2008 edition) NFPA 72C Installation, Maintenance and Use of Remote Station Protective Signaling Systems E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: PVC Insulated Cables B. REVISIONS DEPT.: Title/Description Std/Sepc. No. CER 10-TMSS-05 DATE 00 / 00 / 0000 11-TMSS-02 11-TMSS-12 12-TMSS-10 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. Bare, Copper-Clad Steel Grounding Conductor and Ground Rod Power Cables, XLPE Insulated, Copper conductor, Single Core,110kV, 115KV, XXXKV, 230kV & 380kV rating Coaxial Bonding and Earthing Cables for Link Boxes 12-TMSS-11 Splice and Termination Kits for Power Cable 69kV, 110kV, 115KV, XXXKV, 230kV and 380kV Link Boxes for Power Cables 23-TMSS-01 PVC Conduits & Fittings for Underground Cables SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 58 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA DESCRIPTION CHK’D # 23-TMSS-02 Duct Sealing Units 23-TMSS-04 Cable Clamps for Power Cables 48-TMSS-02 Non Metallic Fiber Optic Cables 70-TMSS-03 Normal Weight Ready-Mixed Concrete Cable Trench Materials 1 2 3 NO. 70-TMSS-04 E&DD D. PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: 22 / 02 / 2021 Sizing and Selection TES-P-104-04 Engineering Requirements for Splices & Termination for Power Cables Cable Installations, Engineering Requirements TES-P-119.01 thru. 42 TES-P-122.01 thru. 12 TES-T-111.02 thru.19 TES-W-109.01 CER DATE TES-P-104.03 TES-P-104.08 CERTIFIED BY: Cement COMPANY Engineering Standards TES-H-107.01, Painting TES-H-107.02, Paint Color Codes and Standards TES-P-104.01 General Engineering Requirements for Underground Cables TES-P-104.02 Power Cable Construction TES-P-104.05 APP DATE: Portland Note: All blanks on the Data Schedules, Inquiry Information (for TMSS) shall be properly filled-up by the CONTRACTOR (as required) without omission and shall be submitted as part of the CONTRACTOR’s Technical Proposal. REVISIONS DEPT.: Title/Description Std/Sepc. No. Bonding and Grounding of Insulated Metallic Sheath of Power Cable System (69kV to 380kV) Substation Design Standards Transmission Line Design Standards Communications General Welding Criteria 00 / 00 / 0000 E. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. COMPANY Transmission Standard Drawings TA-800062 Typical Duct Bank Sections, Concrete Duct Bank 69kV to 380kV TA-800063 Highway Crossings for 69kV to 380kV Cables TA-800068 Highway Under Crossing for 110kV to 380kV U/G Power Cables by Directional Drilling TA-800140 Water Proofing for Duct banks, Manhole/Handhole and Alternate Roof Drainage Details TA-800141 Installation Detail for Link Boxes above Ground TA-800142 Installation Detail for Link Boxes Below Ground SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 59 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D # TB-800067 DESCRIPTION TB-800069 TB-800076 SB-036365 SB-036367 1 2 3 NO. TB-800077 REVISIONS DEPT.: TB-800079 TB-800090 E&DD TB-800091 PREP. BY: NAME SAMI DATE: SB-036371 11 / 02 / 2021 SE-1040521 SE-1040522 F. APPROVED BY: DATE: 22 / 02 / 2021 TCS-P-105 TCS-P-122.01 thru. 23 TCS-Q-113.01 TCS-Q-113.02 TCS-Q-113.03 TCS-Q-113.04 TCS-T-111.01 thru. 12 CERTIFIED BY: CER DATE 00 / 00 / 0000 G. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. 110kV, 115KV, 132KV, 230kV & 380kV Direct Buried Cable Trench Details in Rocky Area (Communications) Standard Trench detail Joint Communication & Power Cables Standard Precast Handhole for Communication in Non Traffic Areas (1.20m x 1.20m x 1.20m) Standard Precast Hand-Hole for Communication in Traffic Areas (1.20m x 1.20m x 1.20m) Marker post for buried communication cables Standard Drawing Details Standard Conduit Formation (Communications Cables) PVC Conduit Installation Concrete Encased, (Vital Communications) PVC Conduit Installation Concrete Encased, (NonVital Communications) Concrete Encased Duct detail for Rocky Areas (Vital Communications) Concrete Encased Duct Details for Rock Area (NonVital Communications Installation) Streets Underground Utility Plan 69 kV to 380 kV U/G & F/O Cable Installation Streets Underground Utility Sections 69 kV to 380 kV U/G & F/O Cable Installation COMPANY Transmission Construction Specification TCS-P-104.01 General Requirements TCS-P-104.02 TCS-P-104.03 TCS-P-104.06 TCS-P-104.08 APP Title/Description Std/Sepc. No. Cable Reels Handling and Storage Trenches and Ducts Cable Installation, Field Handling Procedures Field Testing of Power Cables Rated 110kV, 115KV, 132KV, 230kV or 380kV Pre-Commissioning Tests/Procedures for SEC Transmission Electrical Installations Transmission Line Construction Standards Asphalt Concrete Paving Earthworks Cast In Place Concrete Precast Concrete works Communications/Underground Communications (Telephone/ Optical Fiber/ Pilot) Cable Installation 5-Star Safety and Health Management System Standards 1 - Premises and Housekeeping 1.1 Buildings and Floors 1.2 Lighting: Natural and Artificial 1.3 Ventilation 1.4 Workplace Hygiene Facilities SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 60 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D # REVISIONS E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: 3 - Fire Protection and Prevention Protection 3.1 Fire Extinguishing Equipment/System Assessment. 3.2 Locations Marked, Floor Clear 3.3 Maintenance of Fire Equipment 3.4 Storage of Flammable and Explosive Material 3.5 Alarm System 3.7 Security Roles For Safety 3.8 Emergency Planning APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 Risk 4 - Accident Recording and Investigation 4.1 Occupation Injury, Disease and Properties Damage Records 4.2 Internal Accident Reporting and Investigation (Occupational Injury and Near Miss Incident) 4.3 Occupational Injury/ Disease Statistics 4.4 Internal Accident Reporting and Investigation (Property Damage and Business Interruption) 4.5 Accident Statistics Kept 4.7 Accident / Near Miss Recall THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. Aisles and Storage Demarcated Stacking and Storage Housekeeping Scrap and Refuse Bins Color Coding: Plant and Pipelines 2 - Mechanical, Electrical and Personal Safeguarding 2.1 Machine Guarding 2.2 Lock out, Tag out and Try out 2.3 Labeling of Switches, isolators and Valves 2.4 Ladders (Registers), Stairs, Walkways and Scaffolding 2.5 Lifting Gear and Records 2.6 Compressed Gas Cylinders: Pressure Vessels and Records 2.9 Motorized Equipment: Checklist, Licensing 2.10 Portable Electrical Equipment 2.13 Hand Tools 2.15 Head Protectors 2.16 Eye and Face Protection 2.17 Footwear 2.18 Protective Clothing 2.19 Respiratory Equipment 2.21 Safety Harness 2.22 Hand Protection 2.23 Control of Usage, Issue Maintenance and Record of Personal Protective Equipment 2.24 Notices and Signs: Electrical, Mechanical, Protective Equipment, Symbolic Safety Signs 1 2 3 NO. DESCRIPTION 1.6 1.7 1.8 1.9 1.10 DEPT.: Title/Description Std/Sepc. No. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 61 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA 1 2 3 NO. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: Title/Description Std/Sepc. No. 5 - Safety Organization 5.2 Safety and/or Occupational Hygiene Coordination 5.6 First-aid/Responder and Facilities 5.7 First-aid Training 5.9 The 5-Star Safety System Board 5.16 Workplace Inspections 5.18 Safety Specifications: Purchasing and Engineering Control, New Plant, and Contractors 5.18.3 Contractor's Rulebook 5.18.4 Contractor Pre-Bid Document 5.19 Written Safe Work Procedures 5.20 Planned Job Observations 5.21 Mechanical Work Permits 5.21.1 Electrical Work Permits 5.22 Off-The-Job Safety 5.23 SEC Safety and Health Policy DESCRIPTION CHK’D # H. 11 / 02 / 2021 Other Standards SEEDS-II Saudi Electricity Company Engineering Drawings (Rev. 1) Standard (SEEDS) for Preparing, Processing and Managing Transmission Drawings/Documents SEEDS-III Standard Guidelines for Geographic Information (Latest Rev) System (GIS) ISD Special Safety Signs and Warning Devices Manual No. 65110 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 *** END OF SECTION *** SECTION VI - EQUIPMENT/MATERIALS AND TECHNICAL SPECIFICATIONS 6.01 GENERAL This Section outlines broadly the technical specifications of the major equipment/ materials required for the complete installation of the PROJECT. The specifications outlined herein shall be read in conjunction with the attached PROJECT drawings, the COMPANY Material Standard Specifications and the associated International Standards and Codes. The ratings and specific requirements of the various electrical equipment shall be as indicated in Data Schedule of COMPANY Material Standard Specifications, and the CONTRACTOR shall ensure full conformity with the same. 6.02 EQUIPMENT/MATERIALS SPECIFICATIONS All equipment/materials shall conform to the related COMPANY standards and other standards in accordance with the tabulation hereunder (with notes below): THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. All COMPANY standards and specifications shall be the latest revision Table 6.01 SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 62 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA 1 2 3 NO. DESCRIPTION CHK’D Serial No. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: COMPANY Standards/ Other Standards 11-TMSS-02 12-TMSS-10 12-TMSS-11 12-TMSS-11 & TES-P-104.08 12-TMSS-11, 10-TMSS-05 & TES-P-104.08 11-TMSS-12 TCS-P-104.03 & 70-TMSS-04 TCS-P-104.03 & 70-TMSS-04 TCS-P-104.03 & 70-TMSS-04 TES-P-104.05 & SB-036365 23-TMSS-01 TCS-T-111.08 23-TMSS-02 48-TMSS-02 (Refer to ATTACHMENT – VI) TCS-T-111.06 (Refer to ATTACHMENT – VI) Refer to ATTACHMENT – VI 23-TMSS-04 EQUIPMENT/MATERIAL 1. 2. 3. 4. 5. Power Cables Power Cable Terminations and Splice Kits Link Box along with its accessories Sheath Voltage Limiter (SVL) Grounding Cable & Grounding Rod for Link Box 6. 7. 8. 9. 10. 11. 12. 13. 14. Coaxial Bonding and Earthing Cables for Link Box Cable Protective Tiles Cable Warning Tapes Steel Wire Mesh Warning Post PVC Conduits & Fittings HDPE Subducts Duct Sealing Units Non-Metallic Underground Fiber Optic Cables 15. Optical Cable Joint Boxes 16. 17. Pullbox Cable Clamps for Power Cables Notes 1 2 3 11 / 02 / 2021 NOTES TO TABLE 6.01: 1. For proper installation and mechanical interface, termination of XLPE cables to GIS shall be as per IEC 62271-209, class 1 of IEEE 48 and IEEE 1300. 2. All link boxes shall be of underground type as per 12-TMSS-11. Unless practical difficulties or due to SITE conditions which makes installing underground link box type difficult or impossible, then, above ground link box type shall be proposed. 3. Fiber Optic Cable APPROVED BY: APP DATE: 22 / 02 / 2021 Refer to Appendix-VI, Specifications. CERTIFIED BY: Scope of Work and Technical A. PVC conduits and fittings shall be provided in all underground concrete ductbanks. The PVC conduits and fittings shall be designed, manufactured and tested in accordance with the COMPANY’S Materials Standard Specification 23-TMSS-01. B. Subduct on handhole and inside the building shall be corrugated, flexible and fire retardant (2 Hours UL rating) with 25mm outside diameter. Subduct installation shall be in accordance with TCS-T-111.08. C. Subduct on the underground duct banks and direct buried conduit in trenches shall be rigid with 32mm outside diameter and made from HDPE piping compound, its inner wall must be smooth and black in color. It must comply with STC specification MAT 2301 and pulling length must not exceed 450 meters. D. For direct buried cable trenches, PVC conduits shall be of class-4 type. CER DATE Communication 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 63 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA DESCRIPTION CHK’D Nylon pull ropes ¼ inches in diameter (of different colors) shall be provided and installed in all vacant/spare ducts and subducts. E. The duct sealing units for conduit fittings shall be in accordance with COMPANY’S Materials Standard Specification 23-TMSS-02. F. Unless otherwise indicated, the size of the PVC Conduit for fiber optic cable and 110KV cable shall be 100 mm inner diameter and 200 mm inner diameter respectively. 1 2 3 NO. 6.03 APPROVAL CONDITIONS OF THE ROW AND MATERIAL SPECIFICATIONS REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: A. All materials to be used within the jurisdiction of the Municipality shall conform to their specific requirements. It is the responsibility of the CONTRACTOR to coordinate with Government/Municipality Departments regarding all the required approvals. The following specific requirements shall be complied with, however not limited to the following: 11 / 02 / 2021 1. The CONTRACTOR shall try as much as possible not to have crossings over the existing utilities. In case of such crossing, a clearance of 1 meter (minimum) shall be maintained. Also, in these crossing cases, sand duct banks shall be used instead of concrete duct banks. 2. APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE The CONTRACTOR must take maximum care and attention when working near exiting pipelines and must completely adhere to concern agency conditions. The CONTRACTOR shall have the complete responsibility for any damage caused to the existing pipelines underground power cables during WORK execution. All final drawings shall be approved by the concerned Government Agencies in writing prior to commencement of WORK. Any changes or deviations from the above mentioned conditions shall be specifically approved by the respective agencies. B. The CONTRACTOR shall ensure strict compliance to the approval conditions of the various government agencies as given in the copy of letters enclosed in Appendix IV. C. The CONTRACTOR shall coordinate all the WORK with the concerned local authority and obtain all permits required to perform the WORK. 00 / 00 / 0000 *** END OF SECTION V *** THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 64 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D SECTION VII - INSTALLATION REQUIREMENTS AND GUIDELINES 7.01 GENERAL DESCRIPTION A. The subsequent sections will present the requirements and practices which shall be the basis for the installation of 110KV underground cables and Fiber Optic cables for the system of SEC. 1 2 3 NO. B. The installation practices that will be presented are consistent with the current industry standards with special consideration being given to the working environment found in Saudi Arabia. REVISIONS DEPT.: C. The CONTRACTOR must strictly adhere to the requirements of COMPANY Engineering Standard TES-P-104.05, Construction Standard TCS-P-104, Reel storage and handling Standard TCS-P-104.02 attached Conceptual Design Drawings, and the Practices and Procedures mentioned in the subsequent sections. E&DD 7.02 CABLE TRENCHES AND DIRECTIONAL DRILLING REQUIREMENTS PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 A. General Requirements The 110KV underground cable circuits shall be in direct buried in a trench, sand ductbanks and in concrete encased ductbanks. The physical requirements of the trenches and concrete encased ductbank shall be in accordance with the COMPANY’S Engineering Standard TES-P-104.05, TCS-P-104.06 and TA-800062, respectively. The COMPANY Construction Standard TCS-P-104.03 for the construction of cable trench shall be followed. APPROVED BY: B. Safety The CONTRACTOR shall take all necessary precautions to ensure the safety of personnel working in the trenches and the general public. In addition, the CONTRACTOR shall adhere to the following guidelines: APP DATE: 22 / 02 / 2021 1. The CONTRACTOR is responsible for conforming to the rules and regulations pertaining to safety established by the ministries, municipalities, traffic and COMPANY Loss Prevention Division. 2. The CONTRACTOR shall provide cable trenching signboards on every trench/road crossing and 200 meters on straight run. CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. C. Other Underground Utilities Prior to excavation, the CONTRACTOR shall gather all necessary information regarding other existing underground services such as oil, gas, water, telephone, sewage, other electric cables (110/132 KV & distribution cables), building structures and shall use all precautions in excavating to avoid any damage to any underground utilities. The CONTRACTOR shall be fully liable for any damage caused to any service during cable installation by his personnel. Other utilities found during underground utilities’ survey shall be plotted in the construction drawing “AS-Built” drawing. D. Other Trenching Requirements SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 65 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء 1. The CONTRACTOR shall open only the width of trench as specified in the CONTRACT. The COMPANY shall not reimburse the CONTRACTOR for trenching or reinstatement in excess of the contractual widths or depths. 2. Generally, Municipality or other authorities do not permit excavation of trench lengths greater than five hundred meters at a time. After a given five hundred meters of trench is completely reinstated, the Municipality will then grant a WORK Permit for an additional five hundred meters of excavation. 3. Municipalities may grant only a limited time for complete reinstatement of a trench section. 4. After completing the reinstatement WORK, the CONTRACTOR will be required to submit an acceptance certificate to the COMPANY from the concerned agencies, otherwise, such WORK will not be accepted by the COMPANY. 5. The CONTRACTOR shall be responsible for reinstatement/restoration of any disturbed or damaged facility which are incidental to PROJECT performance. 1 2 3 NO. DESCRIPTION CHK’D APP’D NATIONAL GRID SA REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 E. Horizontal Directional Drilling CONTRACTOR shall submit his proposal for the directional drilling method in accordance to COMPANY standard drawing no. TA-800068 & TES-P-104.05. For further horizontal directional drilling installation guidelines, refer to Appendix –VII. APPROVED BY: 7.03 CABLE DUCTBANKS All cable ducts installation shall follow the requirements of the COMPANY’s Construction Standard TCS-P-104.03. APP DATE: 22 / 02 / 2021 For further cable ductbanks installation, refer to Appendix – VII. 7.04 POWER CABLE INSTALLATION CERTIFIED A. Cable Pulling Tension and Sidewall Pressure Calculations BY: The same shall be in accordance to section 4.04.E. CER DATE 00 / 00 / 0000 B. Preparation of Trench The same shall be in accordance to TCS-P-104.06. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED C. Running Out of Cables JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 66 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء 1. Before running out of cables, the capped ends shall be examined by the cable manufacturer’s engineer for water tightness. The factory installed pulling eye shall be inspected for correct installation. 2. The cable drum can be positioned directly on the flat-bed trailer as long as obstacles in the trench do not prohibit such an action. The cable drum must be equipped with a braking mechanism and aligned at the proper position for cable pulling. 3. A pulling eye hook affixed to the cable pulling eye shall be connected to the wire rope through a properly sized swivel and shackle. 4. After the facilities and the equipment are properly set, portable telephone shall be located on the drum side, leading end of the cable and the winch side. They are utilized to control pulling speed and other communications. 5. Cable pulling shall be started gradually. A watchman who walks along the cable as it is being pulled, shall observe the leading end of the cable. The rotating speed of the drum shall correspond to the pulling speed. If necessary, the drum rotating speed shall be controlled with a simple wooden brake. The pulling speed must be kept stable. 6. Watchmen are to be maintained at each duct entrance / exit along the route so that when the cable leading end arrives, it can be directed into the duct without dragging the duct walls. 7. The cable shall be pulled continuously from the upper side of the drum in the direction indicated on the cable drum. 8. The COMPANY shall inspect and approve any pulling eye which is installed in the field. 1 2 3 NO. DESCRIPTION CHK’D APP’D NATIONAL GRID SA REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: APP DATE: 9. During the cable pull, the tension reading from the tension meter shall be recorded at several intervals. A special tabulation sheet for this record shall be provided by the CONTRACTOR. The tension values at each record interval shall be witnessed by the COMPANY REPRESENTATIVE. The CONTRACTOR and the cable manufacturer will affix their signatures to the record sheet at the termination of the cable pull. A copy of the recorded sheet will be submitted to the COMPANY REPRESENTATIVE on the same day. 10. Near joints, cable ducts, cable bending and at all other points where cables are brought above ground and into buildings, at least 150 mm of cable slack per cable shall be left on each side to allow for ground settlement and for future repairs. As a rule, the cable shall be laid slack in the trenches. At splicing points, cables shall overlap to guarantee proper mounting of the joint. 11. After laying, the cable shall be aligned in flat formation and bound at every 5 meters on straight lengths and at every 15 cm on bends to maintain the flat formation. The COMPANY shall approve the method of binding and the binding materials. Care shall be taken to ensure that the required spacing is maintained between power cable circuits in a common trench. 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 67 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء DESCRIPTION CHK’D APP’D NATIONAL GRID SA 12. Plastic ducts shall be placed around the cables for protection at points where the cables cross in close proximity to other underground utilities & ductbanks. 13. The sheath of power cables must be connected to the Substation grounding system at both ends. All jointing and terminating materials shall be provided by the CONTRACTOR. 14. After the cables have been laid in the trench, all duct openings along the proposed route, and new manholes shall be sealed off against ingress of moisture, sand and insects by use of COMPANY Standard duct sealing units in accordance with 23-TMSS-02. 1 2 3 NO. D. Cable Splicing and Terminations REVISIONS DEPT.: 1. APP 22 / 02 / 2021 3. a. Splicing and terminations shall be in accordance with COMPANY’S Standards 12-TMSS-10 & TES-P-104.04. Cable Snaking/Sagging Certification of Splicing Personnel CER DATE The types of splices may be straight through, isolating, or a combination of both. Depending upon the particular circuit design, these splices can be ungrounded, grounded or cross grounded. To ensure that the 110KV cable splices and terminations are installed in a professional and workmanship manner, the CONTRACTOR shall strictly adhere to the following: CERTIFIED BY: b. Extra length of cables shall be provided at both ends of each cable joint bays (3 meters from both ends) in shape of vertical snaking/sagging for future rejointing. Details of snaking/sagging of cables shall be provided as per Section 4.05, Table 4.02. APPROVED DATE: For cable splicing and terminating, it is mandatory that the CONTRACTOR install the splices and terminations in strict accordance with the cable Manufacturer’s instructions/recommendations. 11 / 02 / 2021 2. BY: a. E&DD PREP. BY: NAME SAMI DATE: General Requirements 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. All cable splicing and terminating personnel (Terminator/Jointer) shall be Manufacturer certified Terminator/Jointer or they shall obtain a certification from the COMPANY before they can commence the WORK. The COMPANY approval for Terminator/Jointer, may include previous cable manufacturer’s training, or certification at COMPANY splicing and terminating school. The COMPANY shall be the sole judge of certification. All cable terminations and joints WORK shall be performed under strict supervision of termination and joint Manufacturer(s), if it is not performed by Manufacturer certified Terminator/Jointer. For GIS terminations/links & other accessories installation and connecting to cable compartment, the CONTRACTOR will require to arrange GIS SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 68 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D Manufacturer's trained and/or certified representative(s) to perform the WORK. Also, GIS Manufacturer's trained and/or certified representative(s) will be required to be approved by COMPANY before they can commence the WORK. DESCRIPTION 4. Cable Tagging 1 2 3 NO. All cables shall be clearly identified with durable non-corroding markers securely fastened at each splice and at each termination point. Appropriate information shall include the phase and source/destination addresses, feeder number and voltage level. REVISIONS DEPT.: APP DATE: CER DATE 2. All electrical connections outside the link box shall be cad-welded and properly insulated to preclude corrosion. 3. The CONTRACTOR shall provide the detailed grounding arrangement at each link Box location. The location of grounding rods shall be such that the top connections are accessible for testing and inspection at inspection pit. Other grounding requirements as per COMPANY Standard TES-P-104.08 shall be followed. 4. All bonding leads from buried power cable joints up to the link Boxes shall be through coaxial cables capable of carrying the system short circuit currents in accordance with COMPANY’S Standards 12-TMSS-11 & TES-P-104.08. 5. For above ground link box types, they shall be provided with minimum of four (4), or suitable number as per SITE conditions, protective (crash) barriers using (6 inch diameter) steel pipes. The horizontal separation between any two crash barriers should be 600mm or less. 22 / 02 / 2021 CERTIFIED BY: At predetermined location along the cable route, foundations shall be provided for the above ground link box type. For underground link box type, concrete pit shall be provided and installed and the elevation of the removable cover of the pit shall be flush with the finish/existing grade. 11 / 02 / 2021 APPROVED BY: 1. E&DD PREP. BY: NAME SAMI DATE: E. Installation of Link Box 7.05 OPTICAL FIBER CABLES INSTALLATION Refer to Appendix-VI, Communication Scope of Work and Technical Specifications. 00 / 00 / 0000 7.06 CABLE ROUTING INSIDE SUBSTATION BASEMENT/CABLE ENTRY ROOM The same shall be in accordance to TCS-P-104.06. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 69 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 7.07 OTHER INSTALLATION REQUIREMENTS A. Responsibility During Installation DESCRIPTION The CONTRACTOR shall be responsible for all materials and component parts during installation. 1 2 3 NO. Failure of any cable and/or component during installation or testing shall cause the faulty cable and/or component to be unacceptable until all test results are reviewed and corrective action taken. To minimize failures at final testing, the CONTRACTOR should physically check and test the cable in segments during installation preferably before backfilling the cable trench. B. Access to Public and Private Properties REVISIONS DEPT.: During excavation in built-up city areas, access shall be provided to public and private properties by providing suitable bridges for both pedestrian and vehicular traffic. The COMPANY is not responsible for any result of accident due to construction of this access. E&DD PREP. BY: NAME SAMI C. Traffic Diversions DATE: 11 / 02 / 2021 The CONTRACTOR shall make and maintain all traffic diversions required for the safe completion of the PROJECT, including all necessary barricades, warning lights and signs as governed by the Traffic Police, when road cutting is warranted. *** END OF SECTION *** SECTION VIII – COMMISSIONING TESTS APPROVED 8.01 GENERAL REQUIREMENTS BY: APP DATE: A. A list, giving the details of the commissioning and site tests shall be prepared by the CONTRACTOR and submitted to the COMPANY for review and approval not less than six (6) months before the schedule date of tests. B. The CONTRACTOR shall be responsible for providing all the appropriate tools, test equipment and temporary AC and DC power supplies needed to perform the commissioning and site tests. All tests shall be performed in accordance with the applicable IEC and ANSI Standards and established practices and procedures. C. The CONTRACTOR shall furnish a schedule of proposed commissioning tests at least two (2) months prior to scheduled date of tests with a list of test and commissioning equipment to be used for the PROJECT. The list shall indicate whether each equipment is owned or to be rented. D. At least 15 days before starting of the testing & commissioning, contractor shall arrange a joint site inspection by all concerned representatives of COMPANY to satisfy and prove that testing equipments are ready to be used, all pre-requisites are complete and necessary arrangements/ preparations are done to carryout testing and commissioning activities. E. The CONTRACTOR shall be responsible for conducting additional tests if recommended by the equipment manufacturers or by the COMPANY. 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 70 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA F. The CONTRACTOR shall be responsible for commissioning the existing protection scheme involved with the scope of the subject PROJECT. 1 2 3 NO. DESCRIPTION G. Testing of high voltage cable system and fiber optic cable shall be carried out to ensure that the necessary design and operation specifications are achieved prior to placing the cable system into service. H. The CONTRACTOR shall be responsible to carry out all tests in a safe manner and with pre-determined safe working procedure submitted to the COMPANY. I. The mechanical check and visual inspection, as required in COMPANY Standard TCS-P-105 shall be carried out prior to any electrical test. J. All sites testing and commissioning will be done under COMPANY witness. Witnessing of testing/commissioning by COMPANY does not mean acceptance of test results. Test results will be reviewed and approved by COMPANY separately after CONTRACTOR submits the same for review and approval. K. Field tests and commissioning results shall be submitted to the COMPANY not later than two (2) days after completion of tests for review prior to the final energization. L. For test equipment requirements for communication equipments, refer to Appendix VI. REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 8.02 TESTING OF UNDERGROUND POWER CABLES SYSTEM APPROVED A. BY: CONTRCTOR shall submit for COMPANY review at least eight (8) weeks in advance, field testing and commissioning procedures and equipment to be used for 110KV cables and link boxes and get approval. At least two (2) weeks before starting the tests he shall arrange joint inspection with COMPANY REPRESENTATIVE to ensure that all pre requisites are complete and cables/link boxes are ready for safe testing and commissioning. Following are minimum tests required in accordance with TCS-P-105 and TCS-P-104.08. CONTRACTOR shall perform additional tests, if required by COMPANY or cable manufacturer. APP DATE: 22 / 02 / 2021 CERTIFIED BY: The CONTRACTOR shall provide cable data (i.e. size, type, configuration, length, Method of grounding, etc.) along with the Impedances (calculated and measured values) for COMPANY review and approval during construction stage of the PROJECT as per the below table. CER DATE 00 / 00 / 0000 Table 8.01: Applicable Company standards for major equipment Testing THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. Serial No. 1. 2. 3. 4. COMPANY Standards/ Other Standards 11-TMSS-02 & TCS-P-104.08 12-TMSS-11 & TCS-P-105 Refer to Appendix-VI 35-TMSS.01 & TCS-P-105. EQUIPMENT/MATERIAL Cable Test TESTING OF LINK BOX TESTING OF FIBER OPTIC CABLES TESTING OF SURGE ARRESTORS SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 71 OF 74 REV. 0 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA 1 2 3 NO. DESCRIPTION CHK’D ** END OF SECTION VIII & SOW/TS *** REVISIONS DEPT.: E&DD PREP. BY: NAME SAMI DATE: 11 / 02 / 2021 APPROVED BY: APP DATE: 22 / 02 / 2021 CERTIFIED BY: CER DATE 00 / 00 / 0000 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED JOB ORDER NO. SOW/TS FOR << Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah >> << Madinah >> SAUDI ARABIA PLANT NO. NG1168 INDEX DOCUMENT NO. A PTS20WC1033 PAGE NO. 72 OF 74 REV. 0 APPENDICES ATTACHED TO SCOPE OF WORK & TECHNICAL SPECIFICATIONS FOR <<Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah>> PTS – 20WC1033 ENGINEERING & DESIGN DIVISION-CENTRAL ENGINEERING & DESIGN DEPARTMENT ENGINEERING & PROJECTS MANAGEMENT NATIONAL GRID SA TABLE OF CONTENTS APPENDICES APPENDIX I DRAWING CONTROL SHEETS APPENDIX II MATERIAL DATA SCHEDULES APPENDIX III TECHNICAL DATA MANUALS APPENDIX IV RIGHT OF WAY (ROW) APPROVALS AND CORRESPONDENCES APPENDIX V EXHIBIT I - SCHEDULE OF ASSET IDENTIFICATION APPENDIX VI COMMUNICATION SYSTEM REQUIREMENTS APPENDIX VII CIVIL AND STRUCTURAL SCOPE OF WORK DESIGN CRITERIA, TECHNICAL REQUIREMENTS AND MATERIAL SPECIFICATION APPENDIX VIII PROJECT DESIGN DOCUMENTS, CALCULATIONS AND DRAWINGS APPENDIX IX TRAINING OF COMPANY PERSONAL APPENDIX X INSTRUCTIONS FOR TECHNICAL PROPOSAL APPENDIX - I DRAWING CONTROL SHEETS نقل الكهرباء National Grid SA DRAWING CONTROL SHEET PROJECT TITLE PROJECT MANAGER / ENGINEER CONTRACT NO. JOB ORDER NO. DRAFTING OFFICE CONNECTION OF 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah EDD/D&DCD/CADU DRAWING NO. SHEET NO. INITIAL REV. NO. FURTHER REV. DRAWING TITLE NO. REMARKS DATE INDEX-A 1 TO 0 SCOPE OF WORK AND TECHNICAL SPECIFICATIONS WT-925382 1 OF 1 3 PROPOSED 110KV U/G CABLE ROUTES WT-925380 1 OF 1 0 PROPOSED CONNECTION DIAGRAM FOR NEW Madinah ISTP S/S WT-925363 1 OF 1 1 PROPOSED SINGLE LINE DIAGRAM OF NEW Madinah ISTP S/S WT-925364 1 OF 1 1 PROPOSED SITE MAP LAYOUT PLAN OF NEW Madinah ISTP S/S WA-58897 1 OF 1 0 SINGLE LINE DIAGRAM OF EXISTIN NAKHEEL S/S WA-458898 1 OF 1 0 LAYOUT DIAGRAM OF EXISTIN NAKHEEL S/S ET-920924 1 OF 1 0 PROJECT SIGN BORD WITH ELECTRONIC COUNTER FOR 110/132 KV UNDERGROUND CABLE CIRCUITS WT-925379 1 OF 1 0 DRAWING CONTROL SHEET PTS-20WC1033 INDEX-P INDEX-X AS BUILT BY PROJECT COMPLETION DATE PLANT NO. NG1168 INDEX DRAWING NO. X WT-925379 SHEET NO. 1 THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF NATIONAL GRID SA. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER. OF REV. NO. 1 0 Rd TERRA TAPE WARNING (FOR POWER CABLE) Aff an TERRA TAPE WARNING (FOR F/O CABLE) GRADE LEVEL 250 ASPHALT (150MM THICK) Ut hm an 300 1200 Ibn 300 SELECTED BACKFILL (BASE COURSE MATERIALS) SELECTED BACKFILL (SUB-BASE COURSE MATERIALS) PROPOSED HDD-2 APPROXIMATE LENGTH= 32.64m E P EXI ST ING (1 800 U m NDE m RG DI RO AM U ND ET ER W A 12 TER m PI DEE P EL P) IN ERT CULV CULVERT R O P O S E PROPOSED 110/13.8kV M-SWPC S/S D 15 m R O A D CU LV ER T 450 1x200mmO PVC DUCTS WITH / HV POWER CABLES 150 CU LV ER T PROPOSED CDB-2 APPROXIMATE LENGTH= 15.16m CULVERT CONCRETE SEE ENLARGEMENT NO. 1 110mmO PVC DUCT WITH / 700 700 250 300 300 700 700 5 SUBDUCTS AND F/O COMMUNICATION CABLE 250 3900 PROPOSED HDD-2 APPROXIMATE LENGTH= 66.20m LP GREENLAND GREENLAND GREENLAND STREET LIGHTING MH MH LIGHTING STREET ELECTRICAL BOX LP STREET LIGHTING MH U/G ELECTRICAL CABLE MARKER (110KV) (E) NOTE: DIMENSIONS ARE IN MILLIMETERS. PROPOSED CDB-2 APPROXIMATE LENGTH= 68.41m 110kV TYPICAL DETAIL CDB-2 (WITHOUT SPARE DUCTS) 110kV U/G POWER & F/O CABLES TRENCH CROSS SECTION IN CONCRETE DUCTBANK WITHOUT SPARE DUCTS (2-CIRCUITS) CULVERT PROPOSED CDB-2 APPROXIMATE LENGTH= 14.39m ULVERT C T LVER U C CULVERT NOT TO SCALE 110mm O HDPE DUCT WITH / 4-SUBDUCTS AND FIBER OPTIC CABLE 1X200mmO HDPE DUCTS / WITH 115kV XLPE CABLES GRADE LEVEL EXISTING SOIL VARIOUS NOTE: DIMENSIONS ARE IN MILLIMETERS. 1500MIN (DEPENDENT ON THE CABLE DEPTH) CABLE PHASE CLEARANCE VARIOUS (REFER TO TABLES) NATIVE SOIL THERMAL RESISTIVITY VALUE VARIOUS (AS PER SOIL REPORT) TYPICAL DETAIL HDD-2 (WITHOUT SPARE DUCTS) PROPOSED CDB-2 APPROXIMATE LENGTH= 26.06m CULVERT CULVERT CU LVER T HV U/G POWER & F/O CABLES TRENCH CROSS SECTION IN HORIZONTAL DIRECTIONAL DRILLING WITHOUT SPARE DUCTS (2-CIRCUITS) CULVERT NOT TO SCALE SUBSTATION LOCATION SUBSTATION NAME TERRA TAPE WARNING (FOR POWER CABLE) Ab du laz iz TERRA TAPE WARNING (FOR F/O CABLE) GRADE LEVEL 400 SELECTED BACKFILL (BASE COURSE MATERIALS) 600 300 250 ASPHALT (150MM THICK) STEEL WIRE MESH PVC COATED 300 GREEN CONCRETE TILES M-SWPC S/S 2715379.526 560469.706 AL NAKHEEL S/S 2709395.972 556884.160 ISUNI-2 S/S 2707742.252 555977.002 Pr in ce SELECTED BACKFILL (SUB-BASE COURSE MATERIALS) 110mmO PVC DUCT WITH / 5 SUBDUCTS AND F/O COMMUNICATION CABLE 200 EASTINGS Na if ibn 1200 RED CONCRETE TILES NORTHINGS ENLARGEMENT No.1 THERMAL SAND 500 500 200 ME DI AN ELECTRICAL BOX CA R GATE POST PA RK IN G GATE POST LP MH W ATER 3000 WATER WELL AS PH AL T WATER TAP SI DE W WATER SANITARY MH SH ED ME DI AN MH W ELL LP MH(S) TAP AL K CONC FO UN RET DA E TI ON MH MH MH MH RO AD ME DI AN 300 LP CO NC RE TE LP MH FE NCE MH NOTE: DIMENSIONS ARE IN MILLIMETERS. LP ME DI AN 300 LP GA TE 500 PROPOSED HDD-2 APPROXIMATE LENGTH= 48.74m SIDE WA LK 500 200 BU ILD ING NOT TO SCALE HV POWER CABLES WATER TAP MH MH LP LP PROPOSED HDD-2 APPROXIMATE LENGTH= 32.64m WATER O P PI P E R O S SANITARY MH(S) E D MH I m R D W A Y A A 7. 10 W m 6 D AL K AL K SI DE W SI DE W E S O 58 58 6. 17 LV ER T CU PROPOSED 110/13.8kV MADINAH ISTP SUBSTATION BU PROPOSED 110kV UG CABLE FROM EXISTING AL NAKHEEL S/S TO PROPOSED M-ISTP S/S IL DI NG L U K LP O C E MH MH 5 F E N SID EW ALK MH SANITARY MH(S) MH MH 1 Ut hm an AL K an LP th m LV ER T CU NOT TO SCALE Ib n PROPOSED CDB-2 APPROXIMATE LENGTH= 15.16m Af fa n SI DE W 110kV U/G POWER & F/O CABLES TRENCH CROSS SECTION IN DIRECT BURIED (2-CIRCUITS) BM-1 Rd 110kV TYPICAL DETAIL DB-2 bn SID EW Aff AL EX K an IS TI N (1 G 80 U 0m ND E m RG DI RO AM U N ET D ER W A 12 TE R m P DE IP EP EL ) INE BU IL DI NG Rd TAP P P R O P LP LP FENCE WALLFENCE SI DEWALK 110mm O HDPE DUCT WITH / 4-SUBDUCTS AND FIBER OPTIC CABLE CULVERT MH ASPHALT ROAD CONCRETE BARRIERS CONCRETE BARRIERS CULVERT CULVERT CONCRETE BARRIERS MH(S) SANITARY MH(S) MH BM-2 CULVERT MEDI AN PROPOSED HDD-2 APPROXIMATE LENGTH= 48.74m 1X200mmO HDPE DUCTS / WITH 115kV XLPE CABLES SANITARY WV LP MEDI AN ASPHALT ROAD MH(T) TELEPHONE MH SI DEWALK SI DEWALK GRADE LEVEL BUI LDI NG CU BUI LDI NG SI D EW A LK LP LV ER T LP EXISTING SOIL PROPOSED 110kV UG CABLE FROM EXISTING ISUNI-2 S/S TO PROPOSED M-ISTP S/S K 500 VARIOUS PROPOSED 110kV UG CABLE FROM EXISTING AL NAKHEEL S/S TO PROPOSED M-ISTP S/S h a li d ib n A l NOTE: DIMENSIONS ARE IN MILLIMETERS. LOCATION OF COMMUNICATION DUCT CAN BE IN EITHER SIDE OF THE TRENCH, DEPENDING ON SITE W ENLARGEMENT No.2 EXISTING 110/13.8kV AL NAKHEEL SUBSTATION a li d NOT TO SCALE R d. 1500MIN (DEPENDENT ON THE CABLE DEPTH) CABLE PHASE CLEARANCE VARIOUS (REFER TO TABLES) A L EX N IS A TI K H NG E E L 110 S /1 U 3 B .8 S T kV A T IO N NATIVE SOIL THERMAL RESISTIVITY VALUE VARIOUS (AS PER SOIL REPORT) TYPICAL DETAIL HDD-1 (WITHOUT SPARE DUCTS) HV U/G POWER & F/O CABLES TRENCH CROSS SECTION IN HORIZONTAL DIRECTIONAL DRILLING WITHOUT SPARE DUCTS (1-CIRCUIT) K NOT TO SCALE SEE ENLARGEMENT NO. 2 K h a li d ib n h a li d A l W ib n A l W a li d R d. a li d R d. TERRA TAPE WARNING (FOR POWER CABLE) TERRA TAPE WARNING (FOR F/O CABLE) GRADE LEVEL PROPOSED HDD-1 APPROXIMATE LENGTH= 90.00m Pri nce Nai f ib n A bdu lazi z 400 600 300 250 ASPHALT (150MM THICK) SELECTED BACKFILL (BASE COURSE MATERIALS) STEEL WIRE MESH PVC COATED 1200 RED CONCRETE TILES 300 GREEN CONCRETE TILES SELECTED BACKFILL (SUB-BASE COURSE MATERIALS) 110mmO PVC DUCT WITH / 200 5 SUBDUCTS AND F/O COMMUNICATION CABLE THERMAL SAND HV POWER CABLES 300 300 200 300 200 1300 K PROPOSED 110kV UG CABLE FROM EXISTING AL NAKHEEL S/S TO PROPOSED M-ISTP S/S h a li d ib n A l PROPOSED 110kV UG CABLE FROM EXISTING ISUNI-2 S/S TO PROPOSED M-ISTP S/S W a li d R d. EXISTING 110/13.8kV ISUNI-2 SUBSTATION ENLARGEMENT No.3 NOTE: NOT TO SCALE DIMENSIONS ARE IN MILLIMETERS. LOCATION OF COMMUNICATION DUCT CAN BE IN EITHER SIDE OF THE TRENCH, DEPENDING ON SITE q ddi lSi r A k a B Abo SEE ENLARGEMENT NO. 3 Pri nce Nai f ib n A bdu lazi z NOT TO SCALE LEGEND Sekk ah A l hade ed q qi -A Al di Wa KEY MAP EXI STI NG 1 1 0/1 3. 8kV I SUN I 2 S/ S EXI STI 110 NG / ISU 13. 8 NI- kV 1S /S EXISTING 110/13.8kV ISUNI-1 SUBSTATION Pri nce Nai f ib n A bdu lazi Pri z nce Nai f ib n A bdu lazi z TYPICAL DETAIL DB-1 HV U/G POWER & F/O CABLES TRENCH CROSS SECTION IN DIRECT BURIED (1-CIRCUIT) PROPOSED 110kV UG CABLE FROM EXISTING ISUNI-2 S/S TO PROPOSED M-ISTP S/S NOTES 03 2021/03/01 RTA ADD TYPICAL POWER CABLE TRENCHES AMG 2021/03/01 02 2021/02/14 RTA ADD SURVEY DETAILS AND SITE UPDATE KMS 2021/02/14 01 2021/01/10 RTA ADD SURVEY DETAILS AND SITE UPDATE KMS 2021/01/10 REV. No. DATE BY DESCRIPTION CHK'D BY DATE 1. ALL VALUES ARE IN METERS. PROPOSED SUBSTATION BOUNDARY LINE TURAIF REP. OF IRAQ AL QURAYYAT JORDAN EXISTING SUBSTATION BOUNDARY LINE AR'AR SAKAKA BRIDGE 3. USERS NOTING ERRORS OR OMISSIONS ON THIS MAP ARE REQUESTED TO MARK HEREON AND RETURN TO SENIOR CARTOGRAPHER. OPEN MEDIAN 4. THIS MAP IS FOR STUDYING ONLY, NOT FOR BIDDING. PROPOSED UNDERGROUND CABLE 5. APPROXIMATE ROUTE LENGTH OF PROPOSED 110kV U/G CABLE ASPHALT ROAD KUWAIT IRAN A R TABUK A HAFAR AL BATIN B A I HAIL N SCALE 1 : 12,000 G NARIYA U 110UG L The Site F JUBAIL BAHRAIN BURAYDAH PROPOSED HDD/CDB DAMMAM QATAR CULVERT MADINAH 0 120 6. APPROXIMATE ROUTE LENGTH OF PROPOSED 110kV U/G CABLE RIYADH HOFUF FROM EXISTING AL NAKHEEL S/S TO PROPOSED M-SWPC S/S IS 8,797.31m. (ADDITIONAL 100M ALLOWANCE) U.A.E. 240 360 480 600 1,200m. METERS FROM EXISTING ISUNI-2 S/S TO PROPOSED M-SWPC S/S KINGDOM OF SAUDI ARABIA IS 12,878.17m. (ADDITIONAL 100M ALLOWANCE) TAIF BASE MAP OF CHECKED BY: JEDDAH MAKKAH -- -- PROJECT ENGINEER DATE R E D BAHA S ءﺍﺏﺭﻩﻙﻝﺍ ﻝﻕﻥ E A OMAN ABHA CONCURRED BY: National Grid SA JIZAN E AFRICA A -- -- MANAGER, E&DD - WEST DATE WESTERN AREA SHOWING ROUTE MAO FOR PROPOSED (2) 110kV UG CABLE FROM M-SWPC S/S TO AL NAKHEEL S/S N C O YEMEN A I D N I AND ISUNI-2 S/S N DRAWN BY: REFERENCE DRAWINGS DRAWING TITLE DRAWING CONTROL SHEET DRAWING NO. FERAS.A.ALZAHRANI 2020/12/08 CARTOGRAPHER DATE THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE RESTRICTED. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED WITHOUT THE CONSENT OF SURVEY & ROW DIV. - WEST JOB ORDER NO. 20WC1033 WT- 925379 FIELD VERIFICATION BY: __- ______ PLANT NO. INDEX WT-925382 NG1168 X MAP NUMBER SHEET REV. No. CERTIFIED BY: CONTROL No. ________________________________________________ DRAWING NO. UPUL SAMANTHA ----/--/-- SURVEY DATE ABDU BIN ABDULLA HOBANY MANAGER, SURVEY & ROW DIV. - WEST 2020/12/08 DATE 0000000 SB-0000 1 OF 1 03 ----- NOTES P JOB ORDER NO. INDEX NG1168 WT-925380 PLANT NO. DRAWING NUMBER 1 of 1 SHEET NO. 00 REV. NO. LEGEND: EXISTING SUBSTATION EXISTING CABLE EXISTING OHTL PROPOSED SUBSTATION PROPOSED CABLE PROPOSED OHTL PROPOSED UNDER OTHER PROJECT GANTRY 110 kV BUS MADINAH ISTP ISUNI-2 110KV UGC CIRCUITS USING DOUBLE CIRCUIT 2 1x1200mm Cu XLPE 110KV UGC CIRCUITS USING SINGLE CIRCUIT NAKEEL 2 1x1200mm Cu XLPE REFERENCE DRAWINGS DRAWING TITLE 110KV UGC CIRCUITS USING SINGLE CIRCUIT 2 1x1200mm Cu XLPE DRAWING NO. DRAWING CONTROL SHEET WT-925379 20WC1033 P.T.S-N0 110KV UGC CIRCUITS USING SINGLE CIRCUIT AS-BUILT DATE BY 2 1x1200mm Cu XLPE __ _____ ___ ______________________ __ __ ___ _____ ___ ______________________ __ __ ___ _____ ___ ________________________ __ ___ CERT. APPD. NO REPRODUCTI ON I N FULL OR I N PART SHALL BE OBTAI NED FROM THI S DOCUM ENT W I THOUT THE W RI TTEN CONSENT OF I TS OW NER. SALAM BSP __ 2 1x1200mm Cu XLPE __ __ _____ REV. NO. DATE ___ ________________________ BY __ DESCRIPTION ___ CHKD. SAUDI ELECTRI CI TY CO. 110KV UGC CIRCUITS USING SINGLE CIRCUIT S.ZUBAIR DRAWN BY DATE STARTED CHECKED BY 24-JAN-2021 CONCEPTUAL DRAWING OPRG. DEPT. FOR TENDERING PURPOSE ONLY SAMI SCALE NTS 24-JAN-2021 DATE COMPLETED ENG. DEPT. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIAL UNTIL CERTIFIED AND DATED BY DATE CONNECTION DIAGRAM INSTALLATION OF 110KV UNDER GROUND CABLES FOR ISTP 110/13.8 KV SUBSTATION MADINAH JOB ORDER NO. ---- INDEX P SAUDI ARABIA PLANT NO. DRAWING NUMBER SHEET NO. NG1168 WT-925380 1 of 1 REV. NO. 00 THI S DRAW I NG AND THE I NFORM ATI ON CONTAI NED HEREI N ARE THE SOLE PROPERTY OF CERTIFIED SEC-D (2004/10) ___ VECTOR SECD00 1 NOTES NG1167 P ----- 1- NUMBER OF CT s & PT s CORES SHALL BE AS PER APPENDI X-9 R WT-925363 of 01 1 JOB ORDER NO. INDEX PLANT NO. DRAWING NUMBER SHEET NO. REV. NO. 2- FOR CT s & PT s SPECI FI CAT I ON REFER T O APPENDI X-9. 3- 13. 8 KV SI DE OF T /F : RAT I NG OF BAYS 25 AND 40 SAME AS BAY 9. 4- ALL 13. 8 KV CABLE FEEDERS RAT I NG SAME AS BAY 5 AND BUS SECT I ON BAY 17 RAT I NG SAME AS BAY 32 B E07 E03 E05 Y E01 E04 E02 E06 E08 E10 5- CONT RACT OR SHALL FOLLOW NEW DESI GNAT I ON SCHEME FOR 110KV SWI T CHGEAR AS FAR AS POSSI BLE I N CASE OF ANY PHASE ROTATION TO TO NAKHEEL ISUNI-2 101 VT-L5 193 593 M 103 P1 220 2000A 230 2000A P2 P2 P2 P2 P2 P2 P1 P1 P1 P1 P1 P1 405 1600A M 3 160OA 131A M 141A 136 2000A 160OA 221B M M 261A M M 1600A 221A 131B 231A M 134 2000A M M 224B 2000A 224A 2000A 121A 2 4 2000A, 40kA 1Sec 306 301Z 304 1600A M 296A 301Y VT-2A 5 M 194A M 234 2000A 261B 141B M 805 1600A M 1600A 8 1600A P2 801Z 806 801Y 804 M M 10 160OA 1600A 2000A, 40kA 1Sec M 160OA P2 P1 6 M 7 M 296B 126B 2000A 126A 2000A M VT-2B VT-1A 194B 9 M 12 11 BUSBAR-1B(LOWER BUS) 206 201Z VT-1B 204 201Y 606 601Z 1600A 1600A 1600A P1 P1 305 1600A P2 205 1600A P2 605 P2 VT-L2 M VT-L6 M 293 693 GIS BUSDUCT (TYP.) GIS BUSDUCT (TYP.) GIS BUSDUCT (TYP.) SF6 / AIR BUSHING (TYP.) SF6 / AIR BUSHING (TYP.) REFERENCE DRAWINGS OIL TO AIR BUSHING OIL TO AIR BUSHING 50/67 MVA 110/13. 8k V X=22% at50MVA OLTC(+12.5,-20)% ONAN/ONAF T2 10KJ ,20KA,96KV OIL TO AIR BUSHING SAME AS T-1 T3 DRAWING TITLE SAME AS T-1 DRAWING CONTROL SHEET 1 x 1C x 630 mm² - XLPE 1500 A 10 Sec. PROJECT SCOPE OF WORK AND TECHNICAL SPECIFICATION 5 RESISTOR RESISTOR 3600A 3600A 13.8 KV BUS-2 3600A, 25kA FOR 3Sec 1 3 2 4 5 6 7 8 3600 A 10 11 12 13 14 15 16 18 19 20 21 22 23 26 24 27 28 29 30 31 3600A, 25kA FOR 3Sec 32 25 34 35 36 37 38 33 39 41 42 43 44 45 46 47 48 630 A 1 x 1C x 630 mm² 1 x 1C x 630 mm² XLPE/ PHASE XLPE/ PHASE 7.0 MVAR _____ ___ ______________________ __ __ ___ __ _____ ___ ______________________ __ __ ___ __ _____ ___ ______________________ __ __ ___ 01 03-03-2021 M.M AS PER COMMENTS M.M M.M M.M CHKD. CERT. APPD. 40 1250 A 17 __ 13.8 KV BUS-3 3600A, 25kA FOR 3Sec 9 1250 A 3600 A DATE BY NO CO. 13.8 KV BUS-I 20WN1032 5 AS-BUILT 3600A WT-925359 I N 5 RESISTOR 6x 1C x 630mm² -XLPE / PHASE DRAWING NO. REPRODUCTI ON 10KJ ,20KA,96KV REV. NO. DATE BY DESCRIPTION 7.0 MVAR Y Y Y Y Y Y S.ZUBAIR DRAWN BY CABLE FEEDER CABLE FEEDER CABLE 13.8/.4 KV CABLE FEEDER FEEDER 13.8/.4 KV CABLE CABLE FEEDER FEEDER DATE STARTED CHECKED BY 24-JAN-2020 SCALE NTS 03-03-2021 DATE COMPLETED OPRG. DEPT. AUX-1 ENG. MOSTAFA ENG. DEPT. AUX-2 THIS DRAWING IS NOT TO BE USED FOR CERTIFIED CONSTRUCTION OR FOR ORDERING TABLE-2 MATERIAL UNTIL CERTIFIED AND DATED TRANSFORMERS T1-T2-T3 DELIVERED POWER 50 /67MVA NOMINAL VOLTAGE 110 /13.8KV DATE SINGLE LINE DIAGRAM AND CONCEPTUAL DRAWING BY CONSTRUCTION OF ISTP 110/13.8KV SUBSTATION OLTC TYPE VECTOR GROUP ONAN/ONAF YNyn0 (d1) FOR TENDERING PURPOSE ONLY PHASE DESIGNATION MADINAH +12.5-20% @ 1.25% UVW JOB ORDER NO. ------- INDEX PLANT NO. SAUDI ARABIA DRAWING NUMBER OF SAUDI ELECTRI CI TY 10KJ ,20KA,96KV THE I NFORMATI ON CONTAI NED HEREI N ARE THE SOLE PROPERTY T1 SHEET NO. THI S DRAW I NG SF6 / AIR BUSHING (TYP.) 1 x 795 KCMIL (ACSR/AW) / PHASE PART OUTDOOR I N OUTDOOR FULL OR OUTDOOR SHALL BE OBTAI NED FROM THI S 393 2000A, 40kA 1Sec 604 601Y 1600A P1 VT-L3 M 801X P1 401Z 406 401Y 404 M 1600A 1600A 803 121B P1 P2 BUSBAR-1A(LOWER BUS) 401X BUSBAR-2B (UPPER BUS) 231B 236 2000A HIGH SPEED EARTHING SWITCH M P2 101Z 106 101Y 104 M 1600A 893 P1 P2 501Z 506 501Y 504 1 403 FUTURE FEEDER 801 VT-L8 OF I TS P2 2000A, 40kA 1Sec 130 2000A 101X 105 1600A M 401 VT-L8 493 BUS COUPLER-B M P1 505 BUS SECTION M 503 501X BUSBAR-2A (UPPER BUS) BUS COUPLER-A SCOPE OF WORK CONSENT 501 E230 THE W RI TTEN VT-L5 E220 OW NER. E130 LEGEND WI THOUT SPARE DI SPUT ET HAT WI LL BE FI NALI ZED AT DESI GN ST AGE. FUTURE SPARE DOCUMENT FUTURE REV. NO. 1 P NG1167 WT-925363 of 1 01 SEC-D (2004/10) DMS VECTOR SECD00 ALL DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE NOTED. 588.65 588.50 588. 23 588. 44 588.56 588. 63 PLANT NO. DRAWING NUMBER 1 of SHEET NO. 588.43 .21 588. 57 588 588. 38 588 588. 61 588. 38 588. 43 .4 9 .56 588. 53 .58 .36 5 88 58 8 .19 588 . 42 58 LP 51 8. 58 8. 4 1 5 88 BU ILD ING 588. 66 588.47 58 8 58 8 .4 8 5 88 . 50 51 588. 58 8. 56 .4 0 588 58 8.1 7 5 88 1 58 8. 59 8.5 7 .36 8.4 .55 58 5 88 58 ME DI AN 8 .6 9 8 588.63 588.18 5 8 8 8 5 TAP .4 8 8.5 7 .6 8 8 8 8 5 588.61 5 8 .50 58 8.3 8.4 6 5 588.76 58 8 58 8. 38 588.38 58 588.46 8.6 9 58 58 8.5 6 588. 20 8.4 9 8.5 6 58 8. 4 6 58 588.50 8.3 5 58 58 4 8.5 FE NC E 588.55 588.43 58 8. 61 26 00 40 00 FE NC E WI TH 15 00 40 00 EF -2 SI DE WA LK 40 00 ) Y A C E K L F E N A W CA M V DU CT m D P O CH AN NE L O DR AI N DU CT M V CA P 20 0 WI mm T TH IN H 8 K. SU 0 CM ( U EX LAT mm WA TE I TH LL RN ON K. ( AL TY WA P. ) LL S) BA BL E NK R SI DE WA LK Cor.#6 FE NC E W I TH AS PH AL T Cor.#8 587.81 58 8.2 5 BO UN DA RY Cor.#1 .1 3 5 8.0 58 BA BL E NK Y CA M V A DU CT W K 2715368.25 560517.21 2715303.03 560474.23 2715303.31 560467.22 2715304.99 560424.21 REV. NO. L D Cor.#3 NORTHINGS EASTINGS 2715304.99 560424.21 2715309.68 560416.73 2715314.81 560413.69 2715385.26 560453.44 2715358.51 560503.61 2715303.31 560467.22 2715304.99 560424.21 REMARKS Cor.#4 WALLFENCE 43.04m 587. 90 587. 94 587.96 98 587. 04 588. 5 0 . 8 8 5 00 588. 08 588. 587. 64 06 88. 06 5 588. 58 7. 66 MEDI AN 58 7. 98 07 8. 58 7 .9 7 8 5 8 .9 9 .1 2 THIS DRAWING IS NOT TO BE USED FOR MATERIAL UNTIL CERTIFIED AND DATED BM NO. NORTHINGS BM-1 2715381.50 560401.99 BM-2 2715292.00 560415.00 5 .9 6 7 7 8 8 587.63 5 587.39 587.66 LV ER T 8 5 .9 1 7 8 BUI LDI NG ISTP SUBSTATION BUI LDI NG CU .9 6 7 8 5 7 .9 6 58 7. 96 58 8. 1 0 587 . 91 5 587.55 5 .0 0 8 9 7 . 7 8 5 A LK SI DEWALK 587.66 MADINAH .8 7 587.45 SAUDI ARABIA 587.50 CONTRACT NO. JOB ORDER NO. INDEX PLANT NO. DRAWING NUMBER SHEET NO. REV. NO. 5 8 .0 7 5 5 8 7 .0 6 8 587.51 8 .1 5 8 .8 CONSTRUCTION OF 110/13.8kV 8 8 SI D EW .63 587 5 1 588. .9 7 587.66 08 588. 8 5 .7 7 8 5 5 587. 59 587. 63 587. 66 587. 88 68 587. 8 SI DEWALK 5 8 8 DATE 587. 70 587.71 7 .8 7 8 5 587.80 587.73 7. 97 Mohammed O Al-ansari SITE MAP LAYOUT PLAN MH .65 58 BY EASTINGS 8 7 CERTIFIED 5 5 LP ENG. & DESIGN ENG. DEPT. 587 587.60 5 8 .1 9 LP 07-MARCH-2021 DATE COMPLETED OPRG. DEPT. TELEPHONE 587.59 588 .10 97 . 587 24-JAN-2021 587. 66 99 7. 58 5 9 . 7 8 5 -------- CONSTRUCTION OR FOR ORDERING 587.48 587.67 8 MH(T) 94 587. APPD. CHECKED BY M.MUSTAFA-T.MOAZ SCALE 66.12m MH 587.62 CERT. 56.86m Cor.#9 Cor.#8 LP CHKD. ------- 587. 63 MEDI AN DESCRIPTION S.ZUBAIR DWN/PRP BY DATE STARTED BENCH MARK LOCATION 587. 70 BY 80.89m 587. 80 BM-2 DATE DRAWING COMPLETION CERTIFICATE (DCC): 5.96m 588.14 587.48 587.56 M.M 8.83m Cor.#2 E 560460.82 M.M A 6 m W TO M SE UN CI WE I PA R SY LI TO ST TY EM M WA UN CI TE I PA R SY LI T ST Y EM DISTANCE Cor.#1 S O P O R 2715398.33 M.M PROPERTY CORNER COORDINATES 587.67 5 560453.44 ASPER COMMENTS ISTP SUBSTATION WITHOUT ROAD 587 . 92 5 8 8 .0 9 2715385.26 M.M ------- SANITARY 587.59 587. 85 560413.69 07-MARCH-2021 PROPOSED 110/13.8kV MADINAH MH(S) MH(S) 587.55 587. 75 58 8. 08 8 8 ASPHALT ROAD 587.68 2715314.81 01 43.04m Cor.#1 587.81 560416.73 7.02m CORNER 7 587.53 2715309.68 78.11m Cor.#7 588.39 588.21 4 3 0 4 6 58 7. 97 8 Cor.#3 FE NC E W I TH BO UN DA RY T3 02 P 3 7.7 58 587.87 58 7. 90 MH 587.52 560424.21 63.91m 587.83 8 2715304.99 REMARKS 5.96m S W I TH E ST EE L TA NK SE PT I C 4. 0M BA BL E NK PI T SE EP AG E RO AD EF -3 WI DE LS CD O& EW S 37 76 6 SI DE WA LK 18 63 44 08 HVA C2 SE WE R PI PE T F MA RUC OR K NH FI LL OL I NG E (S MH ) ( 2. TO 50 IL 0m ET X2 . 50 0m ) 25 00 LA V SL OP E 1% MH -3 W FE NC E W I TH TE SE MP. NS OR CO MM U (R NI C AI SE ATI D ON (7 00 FL RO 0x OO O 55 00 R) M FR ON T DP -2 ) X8 70 0m MV DU CAB LE CT BA NK UF 1 6RA 1 UF 3 18 00 DP -1 DP -3 15 00 I SE D RO OM L POD UF 2 FR ON T DCD B WA LL BC2 DP -2 BC1 BM P DP -2 X3 66 0) 73 55 L P2 WA LL INS UL AT ED WO RK SH ( 73 OP 55 IN SU LA TE D DP -2 DP -2 FL OO R) 6RB AVC 16 3 L P1 RA2 AVC 2 6RB AVC 2 PP2 1 6RA (4 ACS 94 3 E3 6RB 00 FR ACS x6 3 ON SAS 17 E2 6RA PP1 T 0) ACS 4 S I F A 3 S 6RB E16 T 46 I 3B1 F D 2 SAS C RA5 P8 6T 3A1 I F 6RB 1 A 3 D 6T 02 CP7 MI 5 2B1 2 6RA 45 AM 6 T 6 2A1 I 1 DCP 6RB RM 6 6T 63 1 7 B1 CB3 DCP RM 6T 6 1 5 3CB A1 RM 2 6BS 5 DCP 3CB RM 4 6BC 1 HVA 4 2 RM PD CDCP 6 BC1 1 3 3 3BB RM 6BB 6 C 3BB B 2 DCP CH B1 B/ RM A& 2 B 1 2B 6BB1 A/ DCP F F 2A SA CPS 1 S F COM SAS M F F 1 COM ACP M2 SAS F COM C SA ON M3C SAS S4 O S T M SA M4 AS RO S3 COM L SA M5 SAS S2 COM RO SA M6 SAS OM S1 HVA F OD1 SAS (3 C(R 02 3 F OD2 45 A SW I TC HG EA R DP -2 25 X2 ROO 28 M 0) RE CO RD ( 41 28 0) WA LL IN SUL AT ED WI N 30 00 D (B ASE CA ME TC NT HE VE R NT ( I LA 30 TI 00 ON X2 ) 13 . 8k V SE T1 BA TT ER Y 0X RO 56 00 OM ) BO UN DA RY RO OM GI S (3 00 00 x1 20 00 ) kV 20 00 SE T1 BA TT ER ( 74 Y 0 SI DE WA LK AS PH AL T WA LK WA Y WI DE 1. 0M 24 00 0 13 2 1. 0M 74 00 BA TT ER Y 20 40 ( TY P) 127 OU /2 TL 20V ET DP -1 INS UL AT ED DP -4 WAL L Y R GT -0 2 WA LK WA Y WI DE GT -0 1 10 00 T3 01 5 MH -2 FU TU RE GT -0 3 ST EE L 10 20 0 40 00 FU TU RE 89 83 FU TU RE CM H# (T 03 YP E1) 588.36 8 8.2 58 15 87. .1 588 8 588.25 58 8. 19 8. 21 58 58 8. 19 SANITARY 587.67 587.94 58 8. 16 39 00 GR AS AT I NG PH AL T WI TH 30 00 20 40 ( TY P) WI TH CH AN NE L AS PH AL T DR AI N BO UN DA RY 588.41 588.26 EN ST D C UB AP OU T 8. 07 58 8. 06 58 8. 04 58 GR AT I NG BO UN DA RY CH AN NE L 30 0 30 00 10 20 0 30 00 30 0 30 00 GR AT I NG ST EE L 588.34 8.1 1 58 8.0 9 58 8. 11 58 8. 11 58 8. 11 58 8. 08 58 SI DEWALK 587.73 587.62 5 8 8 .0 4 P IP E RO CO AD MA NNE SHA CT LL I N RO ED BE GA AD TO TE # 2 DR AI N 00 0 30 00 HV DU C CT ABL BA E NK 80 89 4 FE NC E 0 8.5 58 RO CO AD MA NNE SHA CT LL I N RO ED BE GA AD TO TE # 2 8.1 1 58 5 8.3 58 1 8.3 58 8. 31 58 .2 8 58 8 8. 28 58 8. 25 58 8. 22 58 8. 25 8. 00 85 7. 58 58 66 11 2 8.5 58 58 E 588.49 588. 5 HV DU C CT ABL BA E NK 3 8 .3 3 5 8 588.51 WI TH 58 8. 32 58 6. 22 58 8.1 3 LV ER T 58 7. 10 58 6. 17 CU AL K SI DE W DP -2 4 8.3 8 58 8.4 9 .3 6 5 8 8 588.33 EX 5 8 8 IS .5 2 TI N (1 G 80 U 0m ND ER m G DI RO AM U N ET D ER W BO UN A DA RY 12 TE WI TH R m FE NC P E DE IP EP EL ) IN SID EW AL K 588.33 5 8 8 .5 4 3 8.3 58 10 20 0 Ibn 5 8 8 .2 3 Ut hm an 588.24 8.1 6 58 58 9 1 588. 58 7 .7 7 8 5 587.77 BOUNDARY WI TH FENCE 587.87 587.91 58 8. 03 588. 05 587.91 58 7. 67 588.05 587.85 587.87 5 8 8 .0 3 5 Cor.#2 Cor.#5 588.24 587.64 588.02 B 1 8.4 58 Aff an 588.27 588.51 8 5 8 8 .4 588.48 SID EW AL K 6 5 8 8 .2 3 5 8 8 .4 Rd .2 9 5 8 8 .5 1 5 8 8 588 .08 Rd Af fa n Ib n 58 8.7 5 26 8. 58 .32 588 5 8 8 .0 7 58 8. 30 AL K SI DE W 8. 12 58 58 an th m 1 8. 07 .2 8 8 5 58 8. 06 7. 91 58 AL K SI DE W 588.57 588.06 588.14 EASTINGS 15.01m 58 7. 71 LV ER T U 5 8 8 .1 7 1 BOUNDARY WI TH FENCE FENCE 5 8 7 . 5 2 CU 588 . 39 5 .0 8 15 00 NORTHINGS 8.83m Cor.#4 588.15 587. 60 8. 29 6 .4 8 8 5 8 BA NK RM U1 DISTANCE Cor.#1 587.66 5 15 00 1% SL OP E 26 00 0 DU CT CORNER 80.89m 5 8 8 .0 RM U2 587.87 .9 6 8 .2 CA BL E 26 00 12 10 29 00 MV 588.45 588.21 25 00 BA NK -1 AR EA 26 00 16 50 15 00 30 45 80 0 DP -1 588.21 588.23 587.92 588.32 26 00 18 00 12 10 12 20 15 00 PROPERTY CORNER COORDINATES 588.49 37 76 1% SL OP E 32 00 .9 5 2 588.56 10 00 22 00 SB 16 00 15 00 EW S OW S OW -2 S1 40 00 10 00 1% SL OP E SI DE WA LK 61 70 AR EA 588.05 5 8 7 1 8.0 .1 6 87 00 UG / WT WT PC DP -1 7 .9 58 8 DP -1 46 40 0 8. 15 588.42 LC LM 70 00 RO OM -1 0x 87 00 ) 10 00 DP -1 58 7 SI DE WA LK 80 0 12 78 M CA DF BI NE T ISTP SUBSTATION WITH ROAD 588.13 SB 80 0 CE C NT B ER 7 3 .0 8 FOI P/ MC P 90 0 FOI P/ 70 MC 0 P M 90 DFO TE 0 80 F 0 80 0 80 0 DC PD B1 PROPOSED 110/13.8kV MADINAH 9 119 0 F 80 0 D 80 CA ATA BI 0 NE FO T CA CMR BI NE T LAN/ CA WA BI NE N T 24 00 80 0 60 06 00 10 00 19 80 80 0 F 48 V SW REC I TC T. MO HDE DC P 12 DB-2 5V DC CE C NT B ER 8 8 15 588. 5 DP -1 587.97 DN CE C NT B ER CE C NT B ER .9 1 6 588.14 DP -2 DP -2 F F F 15 00 CEN C B TE R 18 00 BA NK -2 CA PA CI TO R 588.13 6 588.47 CE C NT B ER CE C NT B ER 7 15 00 DP -1 F F AC DB DP -1 ST A FO IRC AS R EA RE 2 FE RCH I. R DE DW TA G. IL UA S -3 07 52 5 FE NC E 119 0 F EQ UI PM EN (7 T 00 CE C NT B ER 17 25 WI TH 588.39 588.23 588.00 10 00 39 00 8 ST AI RC FO AS R EAR 1 CH RE DET I AI . FE LS UA R D -3 WG 07 . 52 5 DP -1 EF -1 45 0 10 00 58 1% SL OP E RO AD F CR A AC NE C LA ESS D FO DER R DE AR 2 T C RE AIL HI. S F UA ER -3 DW 07 G. 31 7 CE C NT B ER DN 588.01 588 . 25 WI DE BO UN DA RY CE C NT B ER UP 5 8 8 .5 588.57 FI RE CE C NT B ER DP -2 5 588.51 588.10 87 00 30 00 DATE BY 587.90 588.50 18 00 12 00 0 R DP -2 41 25 IL DI NG D 21 30 CE C NTE B DP -2 EW 22 80 AS-BUILT 588.44 4. 0M 36 60 22 80 0 0 15 BU A 588.22 588.38 12 00 S GA RT CA CE I RV SE MH 587.91 587.96 9 .0 8 8 5 8 .0 0 O 588.78 50 0 R 5 7 8 8 588.57 R ASPHALT ROAD 98 . 587 3 .1 8 8 5 58 8. 1 0 58 8. 05 m 80 0 6 SF 588.24 MH 56 85 0 00 39 00 13 C .8k A V B O LE C P A E B N S LE IN H A G FT TU A N T N B E A L S E M E N T WA LL WA LL MC CB 02 8. 58 .2 5 5 HV DU C CT ABL BA E NK 30 5 589.07 MH 588.20 588.79 1 LC LM 1 587. 88 5 8 .9 7 8 5 SANITARY MH(S) 588.40 O588.87 S E D BA NK 39 00 58 8. 00 58 8. 23 588.63 P 40 00 SU MP PI T SU MP PI T 13 00 13 588. 8 588. 1 5 90 587. O 588.53 588.13 88 27 R FE NC E 49 23 17 25 48 32 588.20 8 2 .2 8 8 5 WV DU CT WI TH LC LM 3 68 00 44 75 MV 588.19 7 8.1 5 5 8 8 .2 3 CA BL E 588.17 58 5 8 8 .2 8 WV P 587.48 588.78 588.88 BO UN DA RY 20WN1032 588.13 588.79 RO AD PROJECT TECHNICAL SPECIFICATIONS (PTS) NO 588.49 586.85 588.75 1% SL OP E WI DE 588.26 587.26 587.45 13 . 8k CA V BL CA E BL OP SH E EN AF TU I NG T NN EL AT BA SE ME NT 4. 0M 588.77 588.67 588.66 SI DE WA LK GR AV EL 17 588. 58 8. 30 WT-925359 588.27 588.29 588.84 588.03 588.05 5 8 8 . 3 1 5 8 8 .2 9 58 8. 1 2 DRAWING CONTROL SHEET 588.45 588.30 588.34 4 FI RE 2 588.51 588.54 588.63 588.77 10 00 GR AV EL 588.13 65 59 5 .2 8 8 5 5 8 8 . 2 8 70 00 588.60 588.84 SU MP PI T 15 00 CA PA CI TO R 588.43 588.52 589.10 588.93 58 8 .7 5 8 .2 3 3 88 .3 3 3 TAP 588.58 588.73 588.94 587.53 5 8 8 . 16 7 2 . 8 8 5 0 .5 8 8 5 588.50 BU IL DI NG 8 2 . 8 8 5 2 .5 8 8 5 588.53 588.28 26 588. 5 8 .4 8 8 5 8. 17 5 8 24 00 LP 588.44 WATER 588.68 588.59 15 00 MV 588.30 588.46 588.34 588.62 588.59 11 07 1 58 8 . 43 588.43 588.73 588.88 48 7. 58 58 8. 04 8.1 2 588.54 10 00 Fe nc e Ty pe (Typ -I . V ) 588.59 58 7. 60 58 7. 95 58 7. 96 58 588.99 MH -4 TE LE CU CO ST M OM AR ER EA EX TE RN AL 588.44 0 .3 8 8 5 1 .1 5 8 8. 75 8 588.65 BA NK -3 58 8. 19 58 5 8 8 .3 4 8. 56 588.53 8 58 8.2 0 58 5 8 .1 0 31 588.50 588.91 70 00 588. 588.31 588.40 588.76 588.80 588.48 CA PA CI TO R DRAWING NO. 8 1 588. 588.18 588.94 56 00 MV DRAWING TITLE 588.38 588.45 588.93 588.78 MV 13 . 8k CA V BL CA E BL OP SH E EN AF TU I NG T NN EL AT BA SE ME NT 588.17 588.43 588.68 4 FI RE 5 8 8 .4 3 588.47 589.00 588.75 588.64 588.42 588.53 5 5 20 00 588.36 588.70 588.96 588.96 588.14 58 8. 588.12 1 2 588.30 589.05 588.52 58 8. 25 588.38 588.54 588.41 EQ UI PM EN RO OM T TAP 588.46 588.08 58 8 . 31 588.31 588.61 588.94 588.36 588.49 588.49 588.15 58 588.46 WATER 589.13 588.50 63 60 BA TT RO ERY OM 588 . 5 589.08 588.37 588.42 588.56 588.32 588.50 LP 588. 09 58 8. 1 2 58 8.3 6 8 5 588.38 588.15 588.50 588.75 588.88 588.80 588.53 588.49 588.66 588.33588.54 LP 5 8 8 .1 7 8. 46 58 8.2 588.85 589.05 REFERENCE DRAWINGS 588.36 588.82 589.01 588.54 588.33 LP 588.34 588.14 588.77 588.83 588.68 588.04 58 8 . 20 588.20 588.46 589.01 7 .1 8 8 5 5 8 8 . 3 2 588.11 588.80 589.00 588.12 588.08 58 8. 44 588.44 588.77 588.63 MH MH 588.17 588.40 588.74 588.61 588.70 588.41 MH 588.07 5 .2 8 8 5 58 8.3 2 MH 588.27 588.57 588.90 588.51 SANITARY LP588.10 588.76 588.33 CO NC RE TE 588.07 588.55 588.07 588.06 588.91 58 8. 28 588.26 588.05 5 8 8 .3 588.32 2 588.70 588.33 LP 588.07 5 8 8 .1 588.18 8 588.96 LP MH(S) RO AD 588.77 MH LP MH MH M H LC LM -4 58 8. 29 TAP 588.77 588.14 02 588. WATER AL K 588.35 588.43 5 8 8 . 0 2 MH 588.10 588.37 588.71 MH 58 7. 87 BM-1 588. 27 58 8. 29 5 8 8 . 7 5 MH(S) MH 8.7 58 589.13 SANITARY 58 6 3 . 8 8 5 8.3 5 588.69 1 7 . 8 8 5 588.71 588.46 58 7. 80 5 8 8 . 0 7 . 22 588.22 588.48 589.02 MH 588.14 1 588 8.1 6 588.49 588.66 .4 8 8 5 58 75 8. 8 5 588.78 588.48 58 8. 25 SI DE W .4 588.40 0 WATER 58 6 588.50 CO FO NCR ET UN DA E TI ON AS PH AL T 58 8. 22 588.22 588.58 5 8 8.3 8 .4 588.56 588.66 MH ME DI AN 0 5 8.3 8 5 8 .5 2 8.5 58 58 588.49 588.69 58 05 8. 9 .5 8 8 5 588.65 ME DI AN M H 58 8 . 4 588.41 1 588.59 58 8. 07 58 8.3 4 .3 8 58 GA TE LP .5 8 8 5 58 58 8 71 587. GA TE 8.3 6 588 58 8.2 1 8.6 0 58 9 58 8.3 .36 .52 588 58 588.33 58 7. 73 LP SH ED . 37 588.86 587. 71 588.24 58 8 . 44 588.44 58 588.45 8 PO ST 03 8. 58 587. 95 588.60 9 4 . 8 588.49 8 5 7 .4 8 8 5 1 1 8. 58 587 . 89 588.59 6 588.53 4 . 588 PA RK IN G ME DI AN 8.3 8 58 SID EW AL K 588.40 5 8 8 . 3 1 8 PO ST 588.57 58 8. 1 5 8.5 58 8. 1 7 58 .37 588 .54 588 58 8.4 4 GA TE 588.49 587. 83 CA R 588.49 588.47 National Grid SA INDEX 1 N P NG1167 WT 925364 1 of 1 01 THIS DRAW ING AND THE INFORM ATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF JOB ORDER NO. WT 925364 NG1167 2. THE ORIENTATION AND NUMBER OF DUCT BANKS WILL BE FINALIZED AT DESIGN STAGE. THIS DOCUM ENT W ITHOUT THE W RITTEN CONSENT OF ITS OW NER. CONTRACT NO. 1. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM P NOTES NG-D (2012/01) VECTOR NGD00 01 REV. NO. 1500 1655 1N FAN.12 1600 FAN.5 985 FAN.6 FAN.7 EL=+0.00 T.O.F FAN.8 1V 1U 1W Q E2 FAN.11 E2 1N FAN.5 FAN.6 FAN.7 E2 1N 3W' 3U MV SIDE FAN.1 FAN.9 X0 FAN.4 FAN.14 FAN.13 X1 X2 X3 FAN.2 FAN.3 FAN.10 EL=-0.60 FAN.1 FAN.9 MV SIDE 9270 (4X1) 225 MM { PVC SLEEVES FOR 110KV INCOMER FEEDERS CABLES & 1X110MM { PVC SLEEVE FOR FIPER OPTIC CABLES 3000 3000 EL(-)1.50_ SLOPE 14% CAUTION 2650 WATER TANK STORM WATER CHANNEL COVERED WITH STEEL GRATING EL(-)1.60_ UGWT SLOPE 3% ON CHANNEL EL(-)1.60_ LM-2 7670 0 4 4 4 D1 2709405.601 E 556820.716 EL(-)3.074 EL(-)3.053 REMOVABLE PRECAST BOUNDARY WALL 2000 N 2000 DISCHARGE PIPE OUTSIDE THE SUBSTATION AREA 63723 EL(-)3.00_ REMOVABLE PRECAST BOUNDARY WALL DISCHARGE PIPE OUTSIDE THE SUBSTATION AREA EL(- )0. 077 SLOPE 7% EL(-)3.013 PROPOSED 6M SUBSTATI ON AREA EL(- )1. 488 EL(- )1. 018 ROAD 60342 TOA __ ___ __ _____ ___ ______________________ __ __ ___ __ - ___ - - __ ___ CHKD. CERT. APPD. DATE BY DESCRIPTION S.ZUBAIR CHECKED BY M.MUSTAFA-T.MOAZ SCALE 24-JAN-2021 A3=1:600 24-JAN-2021 DATE COMPLETED ENG. & DESIGN ENG. DEPT. CERTIFIED THIS DRAWING IS NOT TO BE USED FOR BY ---------- DATE HIGHLITED NEW SCOPE OF WORK 6MTR. WIDE SLIDING GATE CORD-4 6000 N EL(-)3.00_ CONSTRUCTION OF 110/13.8kV 2709363.158 E 556876.033 REF. POINT BM = +612.538(TOPOGRAPHY LEVEL) = -3.00(RELATIVE LEVEL) RELATIVE LEVEL = TOPOGRAPHY LEVEL = 615.538 SLOPE 7% EL(- )0. 548 EL(- )1. 895 EL = - 0. 54 EL(- )0. 75 6000 C SH5 EL(-)3.017 EL(-)3.005 CORD-5 EL(-)3.019 BM __ MATERIAL UNTIL CERTIFIED AND DATED EL(-)3.005 CORD-6 ______________________ EL(- )3. 005 EL(-)1.60_ C 3600 SLOPE 1% SLOPE 1% EL(-)1.60_ ___ CONSTRUCTION OR FOR ORDERING SLOPE 14% ON CHANNEL EL(-)1.60_ P RETAI NI NG W ALL SLOPE 3% ASPHALT AREA EL(-)1.56_ 2650 E 556820.209 SLOPE 1% N 2709410.011 W A LL D1 R E T A IN IN G CORD-7 EL(-)1.56_ _____ OPRG. DEPT. EL(-)2.56_ RETAINING WALL EL(-)1.56_ __ DATE STARTED 7200 EL(-)1.56_ ___ THIS DOCUM ENT W ITHOUT THE W RITTEN CONSENT OF ITS OW NER. EL(+ )0. 393 EL = - 0. 55 EL = - 0. 55 ON CHANNEL EL = - 0. 54 EL = - 0. 54 ASPHALT ROAD 4M 3000 10200 RETAINING WALL __ DWN/PRP BY 6M CONCRETE ROAD EL(-)1.56_ __ NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM 3% SLOPE 3% SLOPE CABLES FOR M V 13. 8KV O/G { PVC SLEEVES I N DUCT BANK EL = - 0. 50 1500 760 PI T SOAK EL(-)2.50_ 9270 SLOPE 1% EL(-)1.50_ SLOPE 1% EL(- )1. 50_ RETAINING WALL EL(- )1. 50_ 3000 SLOPE 1% 3000 OIL PIT FAN.13 EL(- )2. 663 FAN.2 PRECAST BOUNDARY WALL T03 X3 OIL PIT 9270 6000 FAN.10 EL=-0.60 OIL PIT SLOPE 14% X2 6000 FAN.14 FAN.13 X1 FAN.3 EL(- )2. 50_ FAN.9 FAN.4 1000 656 MV SIDE X0 FAN.1 SLOPE 1% RETAINING WALL T02 X3 FAN.2 FAN.10 FAN.14 X2 6000 EL=-0.60 X1 FAN.3 6000 X0 FAN.4 350 1300 1300 T01 1W Q E2 ______________________ 7915 EL=+0.00 T.O.F FAN.8 1V 1U ___ DRAWING COMPLETION CERTIFICATE (DCC): FAN.16 R S 656 3W' 3U FAN.12 HV SIDE 1380 _____ REV. NO. SA FAN.15 R S EL=-0.50 FAN.16 HV SIDE 350 NGR -3 __ 1500 CSE EL=-0.50 FAN.11 SLOPE 1% DATE BY National Grid SA 1500 EL(-)1.00_ AS-BUILT ------- EL(-)2.999 N 2709366.811 E 556871.272 EXISTING AL NAKEEL SUBSTATION MADINAH CONTRACT NO. JOB ORDER NO. INDEX P SAUDI ARABIA PLANT NO. DRAWING NUMBER SHEET NO. ----- WT 458898 1 of 1 REV. NO. 0 THIS DRAW ING AND THE INFORM ATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF E2 3W' 3U 1000 FOR 13.8KV INCOMER CABLES OF TRANSFORMERS (2&3) FFL=+0.00 SSL=-0.05 1700 OUTSI DE THE 2900 1W Q E2 1800 (3X2) 225MM { PVC SLEEVES SA EL=+0.00 T.O.F R S E.F --------- EL(- )1. 958 1V 1U NGR -2 FAN.15 LM-1 MANHOLE CSE FAN.16 FAN.8 E.F 1720 DRAWING CONTROL SHEET EL(- )2. 193 FAN.7 4000 FFL=+0.00 - DRAWING NO. PROJECT TECHNICAL SPECIFICATIONS (PTS) NO SLOPE 7% FAN.6 EL(+)0.00 FFL 2900 FM-200 CABLE CORRIDOR 1500 EL=-0.50 SA FAN.12 E10 LCC 2740 1500 FAN.11 FM-200 127(TYP.) 740 DI SCHARGE PI PE E08 LCC E06 LCC (3X2) 225MM { PVC SLEEVES FOR 13.8KV INCOMER CABLES OF 49800 TRANSFORMERS (1) RC FI RE W ALL NGR -1 1600 STORE SEPTI C TANK 1600 D3 3545 E04 LCC E02 LCC 1115 D3 2000 10700 1600 FM-200 OFFICE/ RECORD ROOM 740 1700 E230 LCC E220 LCC E130 LCC E01 LCC 2200 100 100 1600 1500 SLOPE 1% E03 LCC 2200 100 1600 1500 D1 SLOPE 14% 1600 100 2200 TOILET 4800 PLATFORM FM-200 D1 FFL=+0.00 - 1700 3400 EL= + 0. 00 - 362 1008 REFERENCE DRAWINGS 700 1700 BATTERY ROOM 1600 E05 LCC 75 1500 5650 D2 PANEL RETAI NI NG W ALL 1634 SH6 1500 1634 H CHEMICAL DRY PIT SLOPE 5% STAIR-2 FM-200 6290 1634 SH6 1500 850 1000 1634 1000 EL = - 0. 50 6400 FUT. 2260 EL(-)0.50_ 2110 0 0 E.W. 15 R 4000 1600 PLATFORM 2260 FUT. AH51 AH50 CP- 03 AH49 AH48 AH47 AH46 AH45 AH44 1500 2390 125V DC BATTERY (92x2=184) CELLS) 4000 2455 (9X4) 200 M M M FACP EL= + 0. 00 - D 0 2 + R 2 R 1 D 0 8 + F U T U R E A V C A V C D 0 6 + A V C D 0 6 + I /C. 3 AH43 AH39 AH42 AH41 1500 362 D1 2000 1705 EL = - 0. 50 C MI MI PRINTER D 0 U 0 H W 1 2 R 1 D 0 6 + R 2 R 1 D 0 0 + D 0 0 + D 0 0 + D 0 4 + D 0 4 + R 2 3 R 1 H 0 0 R 1 R 1 D 0 2 + R 2 1 R 2 D 0 2 + R 3 H 0 0 AH38 AH37 AUX. 02 AH36 B/R AH35 B/S- 2 AH34 AH40 1860 250 3200 S2 FFL=+0.00 D1 4000 1100 D1 ON CHANNEL EL = - 0. 50 PRI NTER D U 00 H + W 2 U H K 0 1 U H K 0 2 U H K 0 3 U H K 10 U H K 3 0 U H K 2 0 A U H K 4 0 R 1 D 2 3 0 + 1 D 2 2 0 + R 1 U V LS + R 2 U V LS + U F LS + R 2 U F LS + D 13 0 + D 0 1+ D 0 1 R 2 R 1 R 2 D 0 3 + R 1 -3 P BB BB S1 700TYP. 9000 FFL=+0.00 SSL=-0.004 3200 (LOWER BUS) EL(+ )0. 863 SLOPE 7% 5000 SLOPE 1% F U T U R E F U T U R E S E R 1 F U T U R E F U T U R E 1000 1 A H 0 3 + D 0 S 0+ C A 1 1 A H 2 0 + D S 00 C + A 2 A H 4 9 + 1 E M - A C C S = = = E M - E M - 3 2 1 A M I- 2 = A M I = E M - R 1 CORRIDOOR 1500 1600 1600 1500 D 0 3 (UPPER BUS) EL(+ )0. 00 FFL 1600 FAN.5 6290 R 3 AH33 AH32 D1 D2 D SLOPE 1% D1 4086 BUSBAR-2B 4000 640 4500 100 1 P - 6300 250TYP. 1600 HV SIDE 1000 1000 127 SCOPE OF W ORK FFL=+0.00 SSL=-0.004 KI TCHEN 140 FAN.15 SLOPE 1% 2X160MM { PVC SLEEVES FOR 125V BATTERY 9000 CABLES 1000 1860 FM200 ROOM-1 SLOPE 1% 100 E07 LCC CP-02 EL(- )2. 93_ 2500 1X160MM { PVC PIPES FOR 125V BATTERY CABLES FRONT RC FI RE W ALL 1100 (1X3){110mm PVC PIPE FOR OUTDOOR LIGHTING 1000 CABLES @ -0.7 M B.O.S RETAI NI NG W ALL U F LS -4 P ISUN-2 GRID-T03 EQUIPPED FOR SPARE S/S EL(+)1.104 DRAWING TITLE 250 1634 SLOPE 1% SLOPE 14% 4 5 E M = D 0 5 + R 2 1 E10 1296 NEW 100 1600 3500 1500 1000 SLOPE 7% 10200 EL(- )3. 00_ AH31 AH30 AH29 P - E08 4378 1634 3000 6000 G12 8X800=6400 4500 COUPLER-B 100(TYP) SUBSTATI ON AREA G11 MAIN DCDB 6X800=48001000 1250 SECTION EL(-)2.93_ 6M TR. W I DE SLI DI NG GATE R D2 5750 COUPLER-A GRID-T02 E06 CSE SLOPE 1% R DCP-1 5750 BUS E04 2500 BUS E02 (TYP. ) BUS E230 6609 1634 1500 EL(- )2. 997 F U T U R E D 0 5 + F U T U R E M AI N ACDB AH28 I /C. 2 AH27 2 E220 4100 SHUTTER ROLLI NG 4M 908 7850 6560 EL(- )2. 957 F U T U R E F U T U R E 6 E M = 11100 N01 N02 3300 AH26 AH25 AH23 AH22 AH21 CP- 02 AH20 127(TYP. ) E130 SLOPE 1% BUSBAR-1B STAIR-1 EL=-0.60 + FFL=+0.00 SSL=-1.10 1000 (UPPER BUS) EL=-0.50 + DCP-2 FFL=+0.00 SSL=-0.05 FM-200 CENTER SLOPE 1% + 13.8KV SWGR ROOM CB EL(-)1.115_ R + 3X1000=3000 5870 BUSBAR-2A (LOWER BUS) 1500 47350 34000 DN R H 0 0 PANEL FM-200 AC SDB- A PANEL FM - 200 F O IP W ALL M OUNTED FFL= + 0. 00 SSL= - 1. 10 10006X800=4800 FFL=+0.00 SSL=-0.05 BUSBAR-1A + + SAS DC ELP 110KV GIS ROOM 1500 C 19500 D4 SLOPE 7% ASPHALT ROAD GRID-T01 AS SALAM BSP + 12650 EQUIPPED FOR SPARE 2500 EL(-)1.50_ PRECAST BOUNDARY WALL OUTSI DE THE DI SCHARGE PI PE H R 3164 FUTURE E01 R 3813 2541 6000 ON CHANNEL 3% SLOPE CABLES PVC SLEEVE FOR FI PER OPTI C { 1X110M M EL(- )3. 064 FEEDERS CABLES & { PVC SLEEVES FOR HV 110KV I NCOM ER (4X1) 225 M M EL(- )3. 116 SH6 = R FCPS CONTROL ROOM SSL=-0.004 362(TYP.) E03 - HVAC CP-1 HVAC CP-2 OLP 127(TYP. ) 1322 500 362 1700 7500 + DDF DVM #1 DVM #2 TELECOM FM200 ROOM-2 FFL=+0.00 7X800=5600 B/R AH19 B/S- 1 AH18 M ET AH17 AH15 AUX. 01 AH16 3X1000=3000 D1 E05 SLOPE 1% 1600 + PSE#1 + PSE#2 + SDH + LAN ROOM /W AN F U T U R E F U T U R E F U T U R E E.F 1500 EL. = - 0. 50 1500 DC-DC CONV-1 23914 2000(TYP) ILP (3X1)160MM { PVC SLEEVES FOR 13.8KV CABLES OF CAPACITOR BANKS AH14 AH13 AH12 AH11 AH10 I /C. 1 AH09 127 AC SDB-B D1 ON CHANNEL 3% SLOPE 53963 EL(- )2. 817 EL(- )3. 019 SH5 362(TYP.) 5500 EL(-)0.50_ A D1 EL(+)1.36_ =0. 57 5 EL(-)0.50_ 500 DC-DC CONV-2 FRONT E07 CP-01 D2 7X800=5600 AH08 AH07 AH06 F U T U R E 5500 SLOPE 1% 5500 5500 SLOPE 1% F U T U R E F U T U R E SUNSHADE F U T U R E 1000 1000 EL = - 0. 50 SLOPE 1% CP- 01 AH03 FUT. 1880 2260 3200 FENCE WITH D1 1000 8X800=6400 AH05 3000 1600 1600 1540 EL.=-0.60 1x160MM { PVC SLEEVES FOR CAPACITOR BANK CONTROL CABLES 2450 STAI R- 3 PLATFORM EL= + 0. 00 - EL = - 0. 50 RC FIRE WALL EL. = - 0. 50 LV SIDE SUNSHADE 1500 C L EL. = - 0. 50 RC FIRE WALL 1W 1V 1U SUNSHADE AH04 LV SIDE MVCLSIDE AH02 1140 C L AUX- 02 1720 4000 3600 EL = - 0. 50 1W 1V 1U FUT. AH01 1140 SLOPE 14% MVCLSIDE EL =-0.50 CAP.3 EL.=-0.60 FENCE WITH 5500 750 888 EL=+0.00 WALKWAY E.F D1 3220 1000 1000 5800 EL = - 0. 50 FOR 13. 8KV O/G CABLES { PVC SLEEVES I N DUCT BANK (7X5) 200 M M EL = - 0. 68 EL = - 0. 54 EL =-0.50 2680 1000 750 750 CAP.2 EL.=-0.60 FENCE WITH 1000 EL(-)0.50_ 4720 3220 CAP.1 5550 EL = - 0. 54 750 750 5M ASPHALT ROAD SH6 4720 3220 (4X1) 160MM { PVC SLEEVES FOR LV & CONTROL F CABLES OF AUX.TRANSFORMERS SH6 & (3X1) 160MM { PVC SLEEVES FOR 13.8KV LM-3 POWER CABLES OF AUX. TRANSFORMERS EL.=-0.50 SLOPE 1% 4680 4680 D1 (2X3) 110MM PVC SLEEVES FOR FIBER OPTIC CABLES E SLOPE 1% SLOPE 1% 1500 750 2680 1000 EL(+)1.597 556911.900 E LM-4 EL ON CHANNEL 1600 4720 1200 SLOPE 3% EL(-)0.55_ EL(-)0.55_STORM WATER CHANNEL COVERED WITH STEEL GRATING ON CHANNEL (2X3) 110MM PVC SLEEVES FOR FIBER OPTIC CABLES DRY PIT 1000 EL(-)0.50_ EL(+)1.79_ PRECAST BOUNDARY WAL L D 0 8 + 1500 127 2000 FM-200 SLOPE 1% EL(+)1.952 D 0 3 + 1950 CHEMICAL 1500 SLOPE 1% ON CHANNEL 3% SLOPE 3% EL(-)0.675 EL(-)0.60_ SLOPE 1% SLOPE EL(-)0.675 HH1 EL(- )0. 60_ 5000 EL = - 0. 68 SLOPE 3% FUT. + M DF 5200 EL(- )0. 68_ PRECAST BOUNDARY WALL EL(- )1. 999 EL(+ )1. 80_ (W 4 ) 2 15 8 4 2 17 15 0 8 EL(- )0. 131 EL(- )1. 435 1200 7300 2500 EL(+)2.067 ON CHANNEL PRECAST BOUNDARY WAL L 2260 REV. NO. EL(- )0. 841 COMM. ROOM 362 SLOPE 3% EL(+)2.127 EL(+)2.164 AH24 SHEET NO. BATT. ROOM AUX- 01 0 1 1600 EL(+)2.144 ON CHANNEL RETAINING WALL D2 EL(- )2. 456 SLOPE 3% EL(+)2.079 ON CHANNEL EL(-)0.62_ 4000 2000(TYP) EL(+)1.936 D1 1836 SH5 N 2709411.695 SLOPE 7% DRAWING NUMBER 5000 2000 FM-200 B N 2709415.340 EL(+ )0. 217 PLANT NO. EL(-)0.60_ D1 800 2000 INDEX of HH2 JOB ORDER NO. 1 D1 1600 CONTRACT NO. WT 458898 EL(+)1.777 D2 UP 556853.163 CORD-3 6000 ALL DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE NOTED. 2. THE ORIENTATION AND OF DUCT BANKS WILL BE FINALIZED AT DESIGN STAGE. CORD-2 62567 DISCHARGE PIPE OUTSIDE THE SUBSTATION AREA ON CHANNEL SLOPE 1% N 2709452.743 1200 ----- SLOPE 3% EL(+)1.54_ EL(+)1.303 E 556857.436 E P N 2709453.349 CORD-8 1. E 556907.134 EL(+)0.998 CORD-1 NOTES NG-D (2012/01) ___ VECTOR NGD00 NEW SCOPE OF WORK APPENDX –II MATERIAL DATA SCHEDULES Page 1 of 1 The following COMPANY Materials Standard Specifications Data schedules are attached. CONTRACTOR shall fill out the Data schedules indicating the technical particulars of the equipment offered by him. 1 10-TMSS-05 Bare, Copper-Clad Steel Grounding Conductor and Ground Rod and Grounding Clamps/Connectors power cable, XLPE Insulated, copper conductor, single core, 110Kv, 115Kv, 132Kv, 230Kv & 380Kv Rating Coaxial Bonding & Earthing Cables for Link Boxes. 2 11-TMSS-02 3 11-TMSS-12 4 12-TMSS-10 5 12-TMSS-11 Splice & Termination kits for power cables 69kv, 115kv, 132kv , 230kv and 380kV Link boxes for Power Cables 6 23-TMSS-01 PVC conduits and fittings for Underground Cables 7 23-TMSS-02 Duct Sealing Units. 8 23-TMSS-04 Cable clamps for Power Cables. 9 35-TMSS-01 Surge Arrester 11kv through 380kv Nominal 10 48-TMSS-02 Non Metallic Fiber Optic Cables 11 48-TMSS-06 Medium Density Fiber Optic System 12 48-TMSS-12 13 70-TMSS-03 Fiber Optic Interconnecting Devices & Passive Components. Normal Weight Ready Mixed Portland Cement Concrete All blanks on the data schedules Inquiry information for (TMSS) shall be properly filled – up by the CONTRACTOR (as required) without omission and shall be submitted as part of the CONTRACTOR’S Technical Proposal. Any exception or non-conformance items which the CONTRACTOR wishes to propose shall be clearly stated in the bid proposals and in Data Schedules, together with reason(s) of justification(s), and the paragraphs of the specifications to which the exceptions or non-conformance items apply. TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 10-TMSS-05, Rev.02 DATA SCHEDULE BARE, COPPER-CLAD STEEL GROUNDING CONDUCTOR, GROUND ROD AND GROUNDING CLAMPS/CONNECTORS Enquiry No. Date: Purchase Order No. or Contract No. Date: PTS No./Project Title with J.O. No. REFERENCE SECTION NO. 3.0 DESCRIPTION 'A' 'B' 'C' APPLICABLE CODES AND STANDARDS ASTM B910/B910M * 4.0 DESIGN AND CONSTRUCTION REQUIREMENTS 4.2.2 Copper-Clad Steel Grounding Conductor AWG Size Nominal Cross-Section (mm²) Overall Diameter (mm) Minimum Tensile Strength (kN) * D.C. Resistance at 20°C (Ω/km) * 'A'- NATIONAL GRID SAUDI ARABIA SPECIFIED DATA/PARAMETERS 'B'- BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS 'C'- REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B' (*)- DATA/PARAMETERS TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B' 10TMSS05R02/SSA Date of Approval: October 30, 2017 PAGE 9 OF 11 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 10-TMSS-05, Rev.02 DATA SCHEDULE BARE, COPPER-CLAD STEEL GROUNDING CONDUCTOR, GROUND ROD AND GROUNDING CLAMPS/CONNECTORS REFERENCE SECTION NO. 4.2.3 DESCRIPTION 'A' 'B' 'C' Copper-Clad Steel Ground Rod Nominal Diameter (mm) 16 Actual Diameter (mm) 14.3 Minimum Length (mm) 3,000 4.3 Conductivity of Annealed CopperClad Steel Wire (% IACS) 4.4 Direction of Lay 4.5 Minimum Copper Thickness for: 40 left hand Copper-Clad Steel Wire (mm) Ground Rod (mm) 4.6 0.25 Length of Grounding Conductor Total Required Length (m) * Maximum Length per Reel (m) 2,000 Tolerance in Length per Reel ±5% Type of Reel 10TMSS05R02/SSA wooden Date of Approval: October 30, 2017 PAGE 10 OF 11 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 10-TMSS-05, Rev.02 DATA SCHEDULE BARE, COPPER-CLAD STEEL GROUNDING CONDUCTOR, GROUND ROD AND GROUNDING CLAMPS/CONNECTORS A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY NATIONAL GRID SAUDI ARABIA: B. ADDITIONAL SUPPLEMENTARY DATA OR BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: Actual Manufacturer of Equipment/Material FEATURES PROPOSED BY Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of Authorized representative and date Official Seal/Stamp of the Company & Date 10TMSS05R02/SSA Date of Approval: October 30, 2017 PAGE 11 OF 11 TRANSMISSION MATERIALS STANDARD SPECIFICATION 11-TMSS-02, Rev.02 7.0 DATA SCHEDULE 7.1 110kV/115kV/132kV, XLPE POWER CABLE (1200,2000,2500 mm²) National Grid SA Enquiry No. Date: National Grid SA Purchase Order No. or Contract No. Date: National Grid SA PTS No./Project Title with J.O. No. REFERENCE SECTION NO. 3.0 DESCRIPTION 'B' 'C' APPLICABLE CODES AND STANDARDS AEIC CS9/IEC 60840 Reference Manufacturing Standard 4.0 DESIGN AND CONSTRUCTION REQUIREMENTS 4.1 Design Criteria/Rating 4.2 4.3 4.3.1 'A' 'B' 'C' (*) 'A' a. Cable Nominal Voltage, kV b. System Short Circuit Current, kA c. Maximum conductor short circuit current temperature, °C d. Normal Continuous Loading Maximum permissible continuous conductor temperature, °C Permissible Load in Amps, A e. Emergency Loading Maximum emergency conductor loading temp,°C Permissible Load in Amps, A Allowable loading duration; hrs 110/115/132 40 i) During any 12 months ii) During the life of the cable 72 2160 Material Details : Conductor : Material - 250 90 * 105 * Copper NATIONAL GRID SA SPECIFIED DATA/PARAMETERS BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B' DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR / CONTRACTOR IN COLUMN 'B' 11TMSS02R02/HKG Date of Approval: January 02, 2018 PAGE NO. 19 OF 42 TRANSMISSION MATERIALS STANDARD SPECIFICATION 11-TMSS-02, Rev.02 7.0 DATA SCHEDULE 7.1 110kV/115kV/132kV, XLPE POWER CABLE (1200,2000,2500 mm²) REFERENCE SECTION NO. DESCRIPTION 'A' Conductor for stranding (Segmental) * No. of strands * Dia. of strand prior to compaction, mm * 'B' 'C' Cross-sectional area, mm² (1200, 2000 or 2500) Maximum Diameter, mm 1200 mm²: 45.0 2000 mm²: 56.0 2500 mm²: 62.0 Resistance at 25°C, /km * Conductor AC resistance at 20°C * Conductor DC resistance at 20°C * Temp. coefficient at 20°C/°C * Skin effect loss factor (ks) * Proximity effect loss factor (k) * DC resistance at 90°C, /km * Short circuit capability of conductor in kA for 1 second starting with 90°C conductor temperature up to max. short circuit current temperature 40 Water blocking material between strands * Conductor Moisture Impervious layer Material 4.3.2 Conductor shield: Material Average thickness, mm 1200, 2000, 2500 mm² Minimum thickness, mm 1200, 2000, 2500 mm² Dia. over conductor shield, mm Thermal resistivity, K.m/W 11TMSS02R02/HKG Semi-Conducting Tape SEMICON 1.50 1.35 * * Date of Approval: January 02, 2018 PAGE NO. 20 OF 42 TRANSMISSION MATERIALS STANDARD SPECIFICATION 11-TMSS-02, Rev.02 7.0 DATA SCHEDULE 7.1 REFERENCE SECTION NO. 4.3.3 110kV/115kV/132kV, XLPE POWER CABLE (1200,2000,2500 mm²) DESCRIPTION 'A' SUPER CLEAN XLPE 18.0 16.2 * * Nominal thickness , mm Minimum thickness, mm Diameter over insulation, mm Thermal resistivity, K.m/W Relative permittivity or dielectric constant () Loss factor ( ) Specific Resistance, M-km (Actual Test Value) 4.3.5 'C' Insulation: Material 4.3.4 'B' * * * Insulation shield: Material Average thickness, mm Minimumn thickness, mm Diameter over insulation shield, mm Thermal resistivity, K.m/W SEMICON 1.50 1.35 * * Copper wire + Copper tape Lead Sheath Combination of Copper wire + Copper tape and Lead Sheath. Smooth Aluminum Sheath Metallic shield: Material Total effective cross-sectional area mm² Copper wire + Copper tape: 261 mm² (CUW only) Lead Sheath, Combination of Copper wire + Copper tape and Lead Sheath & Smooth Aluminum Sheath: based on short circuit calculations Diameter over metallic shield, mm Temp. coefficient at 20°C,/°C DC resistance at 20°C, /km AC resistance at 20°C /km Self inductance, mH/km AC resistance at 90°C DC resistance at 90°C Resistivity at 20°C Short circuit capability in kA for 1 second of the metallic shield starting with 90°C conductor temperature: 11TMSS02R02/HKG * * * * * 40 Date of Approval: January 02, 2018 PAGE NO. 21 OF 42 TRANSMISSION MATERIALS STANDARD SPECIFICATION 11-TMSS-02, Rev.02 7.0 DATA SCHEDULE 7.1 REFERENCE SECTION NO. 4.3.6 110kV/115kV/132kV, XLPE POWER CABLE (1200,2000,2500 mm²) DESCRIPTION Moisture impervious layer (first layer): Material Thickness, mm Diameter over the layer, mm Thickness, mm Diameter over the layer, mm 4.3.8 SEMI-CONDUCTIVE SWELLING TAPE 0.25 * Yes/No Jacket: Material Nominal thickness, mm Minimum thickness, mm Overall cable diameter, mm HDPE 4.50 4.05 * Conductive layer : Material Thickness, mm * * 5.4 Special Thermal Short Circuit Test Special By-Product of XLPE Special Test for Smooth Aluminum Sheath 6.0 PACKING c. d. e. f. g. h. i. j. Total quantity required, m Are matched sets of cable reel length required? If "YES", how many reels are required per set? Tolerance in cable length of matched reel sets Conductor weight, kg/km Cable weight, kg/km Reel and cable weight, kg Cable length per reel, m Cable reel diameter, mm Cable reel width, mm 11TMSS02R02/HKG 'C' SEMI-CONDUCTIVE SWELLING TAPE Third Moisture impervious layer a. b. 'B' 0.25 * Moisture impervious layer (second layer): Material 4.3.7 'A' Yes Yes Yes/No * * * * * * Date of Approval: January 02, 2018 PAGE NO. 22 OF 42 TRANSMISSION MATERIALS STANDARD SPECIFICATION 11-TMSS-02, Rev.02 7.0 DATA SCHEDULE 7.1 REFERENCE SECTION NO. 110kV/115kV/132kV, XLPE POWER CABLE (1200,2000,2500 mm²) DESCRIPTION 'A' 'B' 'C' I1-hour/ I2-hours/ I3-hours I1-hour/ I2-hours/ I3-hours OTHER REQUIRED INFORMATION a. Life expectancy of cable, years Over 30 b. 3-phase inductance in trefoil/ flat formation, mH/km * c. 3phase capacitance in trefoil/ flat formation F/km * d. Maximum permissible overload in % of 3 cables in underground cable duct trefoil/ flat formation, at 40°C soil temperature, for 1/2/3(I1-hour/I2-hours/I3-hours) hours starting with a prior loading of * 50% 75% 100% e. Maximum pulling Tension (kN) * f. Maximum sidewall pressure, kN/m * g. Minimum bending radius, mm * 11TMSS02R02/HKG Date of Approval: January 02, 2018 / / / / PAGE NO. 23 OF 42 TRANSMISSION MATERIALS STANDARD SPECIFICATION 7.0 7.1 11-TMSS-02, Rev.02 DATA SCHEDULE 110kV/115kV/132kV, XLPE POWER CABLE (1200,2000,2500 mm²) A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY NATIONAL GRID SA: B. ADDITIONAL SUPPLEMENTARY DATA BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: OR FEATURES Actual Manufacturer of Equipment/Material PROPOSED BY Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of authorized representative and date Official Seal/Stamp of the Company & Date 11TMSS02R02/HKG Date of Approval: January 02, 2018 PAGE NO. 24 OF 42 TRANSMISSION MATERIALS STANDARD SPECIFICATION 8.0 11-TMSS-12, Rev. 01 DATA SCHEDULE BONDING AND EARTHING CABLES National Grid Saudi Arabia Enquiry No. Date: National Grid Saudi Arabia Purchase Order No. or Contract No. Date: National Grid Saudi Arabia PTS No./Project Title with J.O. No. REFERENCE SECTION NO. 3.0 DESCRIPTION 'A' 'B' 'C' APPLICABLE CODES AND STANDARDS AEIC CS9 IEC 60502-1 & IEC 60228 Applicable industry standard. 4.0 DESIGN AND CONSTRUCTION REQUIREMENTS 4.1 General Earthing/ Bonding Cable application Cable installation (conduit, duct, direct burial, etc.) 4.2 Voltage rating (kV) 1.8/3 Fault current duration (sec.) * Ground fault current (kA) * 'A'- NATIONAL GRID SA SPECIFIED DATA/PARAMETER. 'B'- BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS. 'C'- REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B'. (*)- DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B'. 11TMSS12R01/YM Date of Approval: May 31, 2018 PAGE 10 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 8.0 11-TMSS-12, Rev. 01 DATA SCHEDULE BONDING AND EARTHING CABLES REFERENCE SECTION NO. 4.0 DESCRIPTION 'B' 'C' DESIGN AND CONSTRUCTION REQUIREMENTS (Continued) Maximum permissible continuous conductor temperature (°C) 4.3.1 'A' 90 Conductor Material Copper Conductor cross sectional area, mm² (95, 120, 150, 240, 280, 300 or 500) Conductor AC resistance at 20°C (Ω/km) * Maximum DC resistance at 20°C (Ω/km) 95 mm2 120 mm2 150 mm2 240 mm2 280 mm2 300 mm2 500 mm2 0.193 0.153 0.124 0.0754 0.062 0.0601 0.0366 Minimum No. / Diameter of strands (Number/mm) 95 mm2 120 mm2 150 mm2 240 mm2 280 mm2 300 mm2 500 mm2 11TMSS12R01/YM 19/* 37/* 37/* 37/* 61/* 61/* 61/* Date of Approval: May 31, 2018 PAGE 11 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 8.0 11-TMSS-12, Rev. 01 DATA SCHEDULE BONDING AND EARTHING CABLES REFERENCE SECTION NO. 4.0 DESCRIPTION 'C' Yes / No Insulation Material XLPE Minimum Average Thickness of insulation (mm) 4.3.3 'B' DESIGN AND CONSTRUCTION REQUIREMENTS (Continued) Is conductor tinning required? 4.3.2 'A' 4.6 Outer Sheath/Jacket Material PVC Type ST2 Color Black Average Thickness of outer sheath (mm) Nominal Thickness of outer sheath/jacket (mm) 95 mm2 120 mm2 150 mm2 240 mm2 280 mm2 300 mm2 500 mm2 11TMSS12R01/YM 3.3 * * * * * * * Date of Approval: May 31, 2018 PAGE 12 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 8.0 11-TMSS-12, Rev. 01 DATA SCHEDULE BONDING AND EARTHING CABLES REFERENCE SECTION NO. DESCRIPTION Cable Overall Diameter (mm) 6.0 'A' 'B' 'C' * PACKING AND SHIPPING Non Returnable Reel/Drum a. Voltage (kV) / Conductor size (mm2) b. Conductor Material. c. Total quantity required (m). e. Cable Weight (kg/km). f. Maximum pulling tension (kN). Yes */* Copper * * * OTHER REQUIRED INFORMATION a. Life expectancy of cable, years Over 30 b. Minimum bending radius, mm During Laying * At Fixed Installation * 11TMSS12R01/YM Date of Approval: May 31, 2018 PAGE 13 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 8.0 11-TMSS-12, Rev. 01 DATA SCHEDULE BONDING AND EARTHING CABLES A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY National Grid Saudi Arabia: B. ADDITIONAL SUPPLEMENTARY DATA OR BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: Actual Manufacturer of Equipment/Material FEATURES PROPOSED BY Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of authorized representative and date Official Seal/Stamp of the Company & Date 11TMSS12R01/YM Date of Approval: May 31, 2018 PAGE 14 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 7.0 12-TMSS-10, Rev. 01 DATA SCHEDULE SPLICE AND TERMINATION KITS FOR POWER CABLES RATED 69, 110, 115, 132, 230 OR 380kV National Grid SA Enquiry No. Date: National Grid SA Purchase Order No. or Contract No. Date: National Grid SA PTS No./Project Title with J.O. No. REFERENCE SECTION NO. 3.0 DESCRIPTION 'A' 'B' 'C' APPLICABLE CODES AND STANDARDS * 4.0 DESIGN AND CONSTRUCTION REQUIREMENTS Catalog number (If applicable) * Type number of equipment (If applicable) * TYPE OF CABLE (XLPE OR LPOF) Nominal Voltage Rating, (kV) Conductor Size, (mm²) Conductor Material Diameter Over Conductor, (mm) Conductor Shield Thickness, (mm) Insulation Thickness, (mm) Diameter Over Insulation, (mm) Insulation Shield Thickness, (mm) 'A'- National Grid SA SPECIFIED DATA/PARAMETER. 'B'- BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS. 'C'- REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B'. (*)- DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B'. 12TMSS10R01/WAM Date of Approval: May 26, 2015 PAGE 13 OF 20 TRANSMISSION MATERIALS STANDARD SPECIFICATION 7.0 12-TMSS-10, Rev. 01 DATA SCHEDULE SPLICE AND TERMINATION KITS FOR POWER CABLES RATED 69, 110, 115, 132, 230 OR 380kV REFERENCE SECTION NO. DESCRIPTION 'A' Metallic Shield Thickness, (mm) Metallic Shield Size, (mm²) and number Outer Jacket Material Outer Jacket Thickness, (mm) Outer Jacket Color Outer Jacket Conductive Layer Overall Cable Diameter, (mm) 1.0 'B' 'C' Black DETAILS FOR XLPE CABLE : Moisture Impervious Conductor (if any) Layer for Semi conducting compatible with the conductor and the insulation. Super clean XLPE Semi conducting compatible with the XLPE insulation. Conductor Shield Material Insulation Material Insulation Shield Material Moisture Impervious Layer-1 Thickness, mm Metallic Shield Material Moisture Impervious Layer-2 Thickness, mm Moisture Impervious Layer-3 Thickness, mm (if any) 12TMSS10R01/WAM Date of Approval: May 26, 2015 PAGE 14 OF 20 TRANSMISSION MATERIALS STANDARD SPECIFICATION 7.0 12-TMSS-10, Rev. 01 DATA SCHEDULE SPLICE AND TERMINATION KITS FOR POWER CABLES RATED 69, 110, 115, 132, 230 OR 380kV REFERENCE SECTION NO. 2.0 DESCRIPTION 'A' 'B' 'C' DETAILS FOR LPOF CABLE : Oil Channel external diameter, (mm) Helix Material Conductor material Conductor Shield Material Insulation Material Insulation Shield Material Metallic Sheath Material Steel Copper Metallized paper tape or semiconducting paper tape Laminated Paper Metallized paper tape or semiconducting paper tape Extruded Lead alloy or seamless tube of corrugated aluminum Metallic Sheath Binder Tape Material Metallic Sheath Binder Tape Thickness, (mm) Reinforcing Layer (for lead alloy sheathed cable only) Material 12TMSS10R01/WAM Date of Approval: May 26, 2015 PAGE 15 OF 20 TRANSMISSION MATERIALS STANDARD SPECIFICATION 7.0 12-TMSS-10, Rev. 01 DATA SCHEDULE SPLICE AND TERMINATION KITS FOR POWER CABLES RATED 69, 110, 115, 132, 230 OR 380kV REFERENCE SECTION NO. DESCRIPTION 'A' 'B' 'C' Reinforcing Layer Thickness (mm) Sealing compound Material Cable Oil Type 3.0 Reference Manufacturing Standard for splice or termination * 4.0 Manufacturer's Designation * Type of kit (Splice or Termination) Sheath sectionalizer/shield break Insulation provided Non-linear resistance/surge arrester ratings (kV, Kj/kV) * 4.1.3 Terminations Conventional/Plug-in/Fluid Filled/Dry Type 4.2.1 Ratings a. Insulation or Voltage Class, (69,110, 115, 132, 230 or 380 kV) Yes/No b. Maximum Design Voltage to Ground, (kV) For 69 kV For 110 kV For 115 kV For 132 kV For 230 kV For 380 kV c. Continuous capability, (A) 12TMSS10R01/WAM Current 44 71 73 84 146 241 Carrying Date of Approval: May 26, 2015 PAGE 16 OF 20 TRANSMISSION MATERIALS STANDARD SPECIFICATION 7.0 12-TMSS-10, Rev. 01 DATA SCHEDULE SPLICE AND TERMINATION KITS FOR POWER CABLES RATED 69, 110, 115, 132, 230 OR 380kV REFERENCE SECTION NO. DESCRIPTION d. Temperature Rating, (°C) For XLPE Cable For LPOF Cable e. 'C' Emergency Temperature Rating, (°C) 105 Basic Lightning Impulse Insulation Level (BIL), (kV) For 69 kV For 110 kV For 115 kV For 132 kV For 230 kV For 380 kV g. 'B' 90 85 For XLPE Cable For LPOF Cable f. 'A' * * * * * * Basic Switching Impulse Insulation Level (BSL), (kV) for 380 kV only * h. Rated LPOF Internal Pressure, (kPa) (if applicable) i. System Short Circuit Current, (kArms) 12TMSS10R01/WAM (kPa) (if applicable) Current, (kArms) Date of Approval: May 26, 2015 PAGE 17 OF 20 TRANSMISSION MATERIALS STANDARD SPECIFICATION 12-TMSS-10, Rev. 01 7.0 DATA SCHEDULE SPLICE AND TERMINATION KITS FOR POWER CABLES RATED 69, 110, 115, 132, 230 OR 380kV REFERENCE SECTION NO. DESCRIPTION 'A' j. Short Circuit Current Rating for 1 second, (kArms) k. Maximum Short Circuit Conductor Temperature, (°C) For XLPE Cable For LPOF Cable 'B' 'C' for 1 second, (kArms) 250 200 l. Maximum Permissible Continuous Conductor Temperature, (°C) For XLPE Cable For LPOF Cable 90 85 m. Maximum Permissible Emergency Conductor Temperature, (°C) For XLPE For LPOF n. Termination Class Leakage Distance in mm for 40/50mm/kV Outdoor For 69 kV For 110 kV For 115 kV For 132 kV For 230 kV For 380 kV 12TMSS10R01/WAM 105 1 2760/3450 4400/5500 4600/5750 5280/6600 9200/11500 15200/19000 Date of Approval: May 26, 2015 PAGE 18 OF 20 TRANSMISSION MATERIALS STANDARD SPECIFICATION 12-TMSS-10, Rev. 01 7.0 DATA SCHEDULE SPLICE AND TERMINATION KITS FOR POWER CABLES RATED 69, 110, 115, 132, 230 OR 380kV REFERENCE SECTION NO. DESCRIPTION 'A' Indoor For 69kV 'C' 1725 4.2.11 External High Sensitivity PD Measuring Sensor on termination 4.2.20 Sealing Method Minimum Dielectric fluid termination Seal Life Expectancy, (Y’rs.) 4.5 'B' Yes/No Double inside 30 Kit Contents (Provide Part Name, Quantity) * * * * * * 5.1 5.3 Type Tests Type Test on Accessory Special Tests (humidity and required?) Yes/No condensation Yes/No required?) Net weight of each splice or termination kit, (kg) Packing Dimension, (mm) Separate Supply, List for same material, including year of supply 12TMSS10R01/WAM tests * * Yes/No Date of Approval: May 26, 2015 PAGE 19 OF 20 TRANSMISSION MATERIALS STANDARD SPECIFICATION 12-TMSS-10, Rev. 01 7.0 DATA SCHEDULE SPLICE AND TERMINATION KITS FOR POWER CABLES RATED 69, 110, 115, 132, 230 OR 380kV A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY NATIONAL GRID SA: B. ADDITIONAL SUPPLEMENTARY DATA OR BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: Actual Manufacturer of Equipment/Material FEATURES PROPOSED BY Vendor/Supplier/ Contractor Name of the Company & Factory Factory Location and address Name and Signature of Authorized Representative and Date Official Seal/Stamp of the Company & Date 12TMSS10R01/WAM Date of Approval: May 26, 2015 PAGE 20 OF 20 TRANSMISSION MATERIALS STANDARD SPECIFICATION 12-TMSS-11, Rev.02 LINK BOXES FOR POWER CABLES National Grid SA Enquiry No. Date: National Grid SA Purchase Order No. or Contract No. Date: National Grid SA PTS No./Project Title with J.O. No. REFERENCE SECTION NO. DESCRIPTION 'A' Nominal System Voltage (kV) (13.8, 33, 69,110,115,132 230, 380) System Short Circuit Current at rated system voltage (kA sym.) 3-phase Phase-to-phase 1-phase-to-ground 3.0 'B' 'C' * * * * * APPLICABLE CODES AND STANDARDS Reference Manufacturing Standard * 4.0 DESIGN AND CONSTRUCTION REQUIREMENTS 4.1 General Quantity of Link Boxes required * Model Designation of Link Box * Single point/ Cross Sheath bonding method * 'A'- NATIONAL GRID SAUDI ARABIA SPECIFIED DATA/PARAMETER 'B'- BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS. 'C'- REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B'. (*)- DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B'. 6.0 12TMSS11R02/YM DATA SCHEDULE Date of Approval: April 08, 2019 PAGE 23 OF 29 TRANSMISSION MATERIALS STANDARD SPECIFICATION 12-TMSS-11, Rev.02 LINK BOXES FOR POWER CABLES REFERENCE SECTION NO. 4.3 DESCRIPTION 'A' 'B' 'C' Ratings Magnitude of fault current (kA) to be carried by links and busbars * * Duration of fault current(sec.) Maximum induced voltage in the sheath due to load currents(V) 4.3.4 * Maximum induced voltage in the sheath due to system through fault currents(kV) 3-phase * Phase-to-phase * 1-phase-to-ground * Sheath Voltage Limiter (if required): Continuous Service Voltage (kVrms) * Rated Voltage(kVrms) * Temporary Over Voltage Capability (kVrms) at 60°C without prior energy/ with 100kA, 4/10µs prior energy 1 sec 10 sec * * Rated discharge current with 8/20µs waveform (kA peak) * High current Impulse (4/10µs)withstand (kA peak) * Long duration wave withstand current (A) duration (µs) 12TMSS11R02/YM * * Date of Approval: April 08, 2019 PAGE 24 OF 29 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 12-TMSS-11, Rev.02 DATA SCHEDULE LINK BOXES FOR POWER CABLES REFERENCE SECTION NO. DESCRIPTION 'A' 'B' 'C' 4.3.4 (Continued) Leakage current through SVL at MOCV (mA) * Maximum Residual Voltages (kVpeak) at 8/20µs lightning impulse discharge current of: 2.5kA 5kA 10kA * * * Maximum Residual Voltages (kVpeak) at long duration 2000µs discharge current of 0.25kA 0.5kA 1kA * * * Maximum Residual Voltages (kVpeak) at 1/>2µs steep impulse discharge current of: 5kA 10kA * * Energy absorption capability in kJ/kV of MOCV at 100kA, 4/10µs two Impulse 0.5kA, 2000µs multiple long duration Line Discharge Class * Non-linear Resistor Material * Insulation resistance at 2500Vdc (MΩ.) * Arrester Housing material * Cantilever strength (Nm) * Creepage length(mm) * 12TMSS11R02/YM Date of Approval: April 08, 2019 * PAGE 25 OF 29 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 12-TMSS-11, Rev.02 DATA SCHEDULE LINK BOXES FOR POWER CABLES REFERENCE SECTION NO. DESCRIPTION 'A' 'B' 'C' 4.3.4 (Continued.) Weight(Kg) * Manufacturer * Link Box Location Type of mounting of link box 4.4 * Materials Connecting Links Material Finish Size (mm2) * * * Contact resistance of connections (µohm) * Bolts and Washers Material * Cable Lug Material Finish Size (mm2) * * * Busbar Material Finish Thickness of tin plating (µm) Size (mm2) * * * * Ground Terminal Material Finish Size (mm2) * * * 12TMSS11R02/YM Date of Approval: April 08, 2019 PAGE 26 OF 29 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 12-TMSS-11, Rev.02 DATA SCHEDULE LINK BOXES FOR POWER CABLES REFERENCE SECTION NO. DESCRIPTION 'A' 'B' 'C' 4.4 (Continued) Enclosure Height (mm) Width (mm) Depth (mm) * * * Sheet Material (Fiber Glass/ Brass/ Stainless Steel) Stainless Steel Grade Sheet Thickness (mm) Net Weight (kg) Gross Weight (kg) Painting System Color of Interior Color of Exterior 4.6 304L * * * * * Cable Gland Plate: Number of holes Hole diameter (mm) Material * * * Insulating Material Type Size Voltage rating (kV) * * * Insulation resistance between links (MΩ.) links to ground (MΩ.) * * Marking Phase Identification Label Provided? * Provision for fixing danger sign plate and National Grid Saudi Arabia monogram provided? * Nameplate Provided? * 12TMSS11R02/YM Date of Approval: April 08, 2019 PAGE 27 OF 29 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 12-TMSS-11, Rev.02 DATA SCHEDULE LINK BOXES FOR POWER CABLES REFERENCE SECTION NO. 5.1 DESCRIPTION 'A' 'C' Type Tests Impulse Voltage Withstand: Between Links (kVpeak) Between Link and Ground (kVpeak) Short Circuit Current Withstand for 1 sec. Busbar (kA) Bonding Links (kA) 5.2 'B' * * * 304L Routine Tests Power Frequency / VLF Withstand Voltage for 1minute: Between Links(kVrms) Between Link and Ground (kVrms) 12TMSS11R02/YM Date of Approval: April 08, 2019 * * PAGE 28 OF 29 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 12-TMSS-11, Rev.02 DATA SCHEDULE LINK BOXES FOR POWER CABLES A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY NATIONAL GRID SAUDI ARABIA: B. ADDITIONAL SUPPLEMENTARY DATA OR BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: Actual Manufacturer of Equipment/Material FEATURES PROPOSED BY Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of authorized representative and date Official Seal/Stamp of the Company & Date 12TMSS11R02/YM Date of Approval: April 08, 2019 PAGE 29 OF 29 TRANSMISSION MATERIALS STANDARD SPECIFICATION 7.0 23-TMSS-01, Rev.01 DATA SCHEDULE PVC CONDUITS & FITTINGS FOR UNDERGROUND CABLES National Grid SA Enquiry No. Date: National Grid SA Purchase Order No. or Contract No. Date: National Grid SA PTS No./ Project Title with J.O. No. REFERENCE SECTION NO. 3.0 DESCRIPTION 'A' 'C' APPLICABLE CODES AND STANDARDS Applicable Industry Standards 4.1 'B' * DESIGN AND CONSTRUCTION REQUIREMENTS 4.2 Type of PVC conduit (Type DB, EB, EPC- 40-PVC, PVC corrugated flexible tubing) 4.3.2 Continuous operating temperature (oC) 90 * 4.3.3 Maximum emergency conductor overloading temperature (oC) 105 * 4.4.1 PVC conduit compound cell classification 12154 * PVC >80.1 21.0 to 27.5 * * * a. b. c. d. Kind of resin in compound Impact resistance, (J/m) of notch Tensile strength, (MPa) Modulus of elasticity in tension (MPa) e. Deflection temperature under load of 1.82 MPa, (°C) * 3585 to 4275 100 to 110 * * * 'A''B''C'(*)- National Grid Saudi Arabia SPECIFIED DATA/PARAMETER. BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS. REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B'. DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B'. 23TMSS01R01/DBA Date of Approval: May 26, 2015 PAGE 22 OF 24 TRANSMISSION MATERIALS STANDARD SPECIFICATION 7.0 23-TMSS-01, Rev.01 DATA SCHEDULE PVC CONDUITS & FITTINGS FOR UNDERGROUND CABLES REFERENCE SECTION NO. 4.4.2 DESCRIPTION PVC fitting compound cell classification b. b. c. e. 4.5.2 4.5.3 4.6.1 'A' Kind of resin in compound Impact resistance, (J/m) of notch Tensile strength, (MPa) Modulus of elasticity in tension (MPa) e. Deflection temperature under load of 1.82 MPa, (°C) Overall length of conduit (m) Have belled-end conduits? Conduit Size Outside diameter (mm) Min. wall thickness (mm) 23TMSS01R01/DBA 'B' 11232 * PVC >40 27.5 to 34.4 * * * 2620 to 3171 * 70 to 80 * 6.10m ± 0.03m * Yes/No * * * * * Date of Approval: May 26, 2015 'C' PAGE 23 OF 24 TRANSMISSION MATERIALS STANDARD SPECIFICATION 7.0 23-TMSS-01, Rev.01 DATA SCHEDULE PVC CONDUITS & FITTINGS FOR UNDERGROUND CABLES A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY NATIONAL GRID SAUDI ARABIA: B. ADDITIONAL SUPPLEMENTARY DATA OR BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: Actual Manufacturer of Equipment/Material FEATURES PROPOSED BY Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of Authorized Representative & date Official Seal/Stamp of the Company & Date 23TMSS01R01/DBA Date of Approval: May 26, 2015 PAGE 24 OF 24 TRANSMISSION MATERIALS STANDARD SPECIFICATION 23-TMSS-02, Rev. 0 6.0 DATA SCHEDULE DUCT SEALING UNITS SEC Enquiry No. Date: SEC Purchase Order No. or Contract No. Date: SEC PTS No./Project Title with J.O. No. REFERENCE SECTION NO. 3.0 DESCRIPTION 'A' 'B' 'C' APPLICABLE CODES AND STANDARDS * 4.0 DESIGN AND CONSTRUCTION REQUIREMENTS 4.12 Type (empty or cable) Location to be installed (underground, cable vault, etc.) * Inside diameter or dimensions of duct (mm) Provision of dimensional sketch for noncircular cross section Yes/No Precise outside diameter of cable (mm) Precise outside diameter of neutral wire (mm) 4.4.1 4.4.3 Material: Sealing * Compression Plate Bolt(s) * * 'A' - SEC SPECIFIED DATA/PARAMETERS 'B' - BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/ PARAMETERS 'C' - REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B' (*) - DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B' 23TMSS02R0/AAG Date of Approval: August 5, 2006 G PAGE NO. 11 OF 13 TRANSMISSION MATERIALS STANDARD SPECIFICATION 23-TMSS-02, Rev. 0 6.0 DATA SCHEDULE DUCT SEALING UNITS REFERENCE SECTION NO. DESCRIPTION Washers 'A' 'B' 'C' * Nuts 4.3.1 Maximum Operating Temperature of the Duct Sealing Unit (°C) * 4.3.2 Maximum Operating Pressure of the Duct Sealing Unit (kPa) * 4.6.5 Recommended nut torque for 69 kPa (10 psi) pressure (Joule or Nm) * Maximum Nut Torque (Joule or Nm) 23TMSS02R0/AAG Date of Approval: August 5, 2006 G PAGE NO. 12 OF 13 TRANSMISSION MATERIALS STANDARD SPECIFICATION 23-TMSS-02, Rev. 0 6.0 DATA SCHEDULE DUCT SEALING UNITS A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY SEC: B. ADDITIONAL SUPPLEMENTARY DATA OR BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: Actual Manufacturer of Equipment/Material FEATURES PROPOSED BY Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of authorized epresentative and date Official Seal/Stamp of the Company & Date 23TMSS02R0/AAG Date of Approval: August 5, 2006 G PAGE NO. 13 OF 13 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 23-TMSS-04, Rev. 0 DATA SCHEDULE CABLE CLAMPS FOR POWER CABLES SEC Enquiry No. Date: SEC Purchase Order No. or Contract No. Date: SEC PTS No./Project Title with J.O. No. REFERENCE SECTION NO. 3.0 DESCRIPTION 'A' 'B' 'C' APPLICABLE CODES AND STANDARDS Applicable Industry Standards 4.0 DESIGN AND CONSTRUCTION REQUIREMENTS 4.1 Type of Cable Clamp Aluminum (If not specified) Dimension (Diameter & Length) of Cable Clamp, mm Cable diameter to be accommodated, mm Type of material used in the clamp Aluminum/ Aluminum Alloy (If not specified) Weight of the unit, g Thickness of Zinc coating (Where applicable) 4.2 Mechanical Load which the clamp is expected to withstand, kN 'A'- SEC SPECIFIED DATA/PARAMETERS 'B'- BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS 'C'- REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B'. (*)- DATA/PARAMETERS TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B' 23TMSS04R0/YM Date of Approval: April 02, 2011 PAGE NO. 9 OF 12 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 23-TMSS-04, Rev. 0 DATA SCHEDULE CABLE CLAMPS FOR POWER CABLES REFERENCE SECTION NO. DESCRIPTION 4.3 Ratings 4.3.1 Short Circuit withstand rating, kA/sec 4.3.2 Temperature rating (max. operating temperature of cable clamp), oC 4.4 Materials 4.4.1 Material of gasket 'B' 'C' Rubber Material of stud/nut/washer/spring etc. 5.0 TESTS 5.1 Test for resistance to electromechanical forces/short circuit 23TMSS04R0/YM 'A' Galvanized Steel / Stainless Steel Yes Date of Approval: April 02, 2011 PAGE NO. 10 OF 12 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 23-TMSS-04, Rev. 0 DATA SCHEDULE CABLE CLAMPS FOR POWER CABLES A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY SEC: B. ADDITIONAL SUPPLEMENTARY DATA OR BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED-UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: Actual Manufacturer of Equipment/Material FEATURES PROPOSED BY Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of authorized representative and date Official Seal/Stamp of the Company & Date 23TMSS04R0/YM Date of Approval: April 02, 2011 PAGE NO. 11 OF 12 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 35-TMSS-01, Rev. 01 DATA SCHEDULE SURGE ARRESTER FROM 11kV THROUGH 380kV NOMINAL National Grid SA Enquiry No. Date: National Grid SA Purchase Order No.or Contract No Date: National Grid SA PTS No./Project Title with J.O. No. REFERENCE SECTION NO. DESCRIPTION 'A' 'B' 'C' SYSTEM DATA Nominal System Voltage(kV) (11kV, 13.8kV, 33Kv, 34.5kV, 69kV, 110kV, 115kV, 132kV, 230kV or 380kV) * System Fault Current Level at Rated System Voltage (kA) * Maximum Duration of Ground Fault (ms) * System Neutral Grounding at Arrester Point Of Installation (Effectively, Non-Effectively Grounded) 'A'- NATIONAL GRID SA SPECIFIED DATA/PARAMETER. 'B'- BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS. 'C'- REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B'. (*)- DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B'. 35TMSS01R01/KSB Date of Approval: December 25, 2016 PAGE 9 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 35-TMSS-01, Rev. 01 DATA SCHEDULE SURGE ARRESTER FROM 11kV THROUGH 380kV NOMINAL REFERENCE SECTION NO. DESCRIPTION 'A' 'B' 'C' System Component(s) to be protected Transmission Line Surge Impedance (ohms) Length (kM) * * Underground Cable Capacitance (µF/kM) Length (kM) * * Capacitor Banks Capacitance (MVAR) Others (Power Transformers, Reactors, GIS etc., attach details) * 3.0 APPLICABLE INDUSTRY STANDARDS * 4.0 DESIGN AND CONSTRUCTION REQUIREMENTS 4.1 General Type Model Designation Location (Indoor/Outdoor) 4.2 * * Performance Characteristics and Ratings Rated Voltage Arrester Class * Dielectric Withstand for Housing Lightning impulse sithstand voltage, with 1.2/50µs waveform (kVpeak) * Power frequency withstand voltage(Wet for outdoor/ Dry for indoor) * 35TMSS01R01/KSB Date of Approval: December 25, 2016 PAGE 10 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 35-TMSS-01, Rev. 01 DATA SCHEDULE SURGE ARRESTER FROM 11kV THROUGH 380kV NOMINAL REFERENCE SECTION NO. DESCRIPTION Switching impulse withstand voltage With 250/2500µs waveform (for arrester with rated voltage 200kV and above (kVpeak) 'A' 'B' 'C' * Nominal Discharge Current (Lightning Impulse Classyifying Current) with 8/20 µs waveform (kV) * High Current impulse Capability with 4/10µs Waveform (kApeak) * Maximum Lightning Impulse Residual Voltage With 8/20 µs waveform (kVpeak) at a Discharge classifying) current of : - 5kA - 10kA - 20kA - 40kA * * * * Maximum Switching Surge Residual Voltage (kVpeak) at Discharge Current of - 0.5kA - 1kA - 2kA * * * Maximum Steep Current /Front-of-Wave Residual Voltage Based on 1/ 2 or 0.5 µs Waveform as Applicable (kVpeak) - 10kA * - * 20kA Temporary over voltage capability (kVrms) (manufacturer shall submit curve for TOV for the Following duration with and without Prior duty) - 0.1second - 1 second - 10 second 100second * * * * Maximum R.I.V (µv) * 35TMSS01R01/KSB Date of Approval: December 25, 2016 PAGE 11 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 35-TMSS-01, Rev. 01 DATA SCHEDULE SURGE ARRESTER FROM 11kV THROUGH 380kV NOMINAL REFERENCE SECTION NO. DESCRIPTION 'A' Maximum External Insulation Levels Power Frequency Dry Withstand Voltage (kVrms) * 4.3 Power frequency wet withstand voltage (kVrms) * Lightning impulse withstand voltage (kVpeak) * Switching impulse withstand voltage (kVpeak) * Leakage current through Arrester at MCOV (mA) * Maximum Energy Absorption Capability i) kj/kV of arrester rating ii) kj/kv of MCOV * * Repetitive Charge Transfer rating (Qrs(C)) * Maximum resistive current acceptable * 'B' 'C' Construction Pressure Relief Capability (rms symmetrical) High Current Short duration Low current, long duration (A) 600 Porcelain Housing Color Creepage Distance (mm) Bending Failing Load (kN) Cantilever Strength min (kN) Torsional Strength (kN) Compression Strength (kNm) No. of Stacks in each unit Height (mm) * * * * * * * * 35TMSS01R01/KSB Date of Approval: December 25, 2016 PAGE 12 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 35-TMSS-01, Rev. 01 DATA SCHEDULE SURGE ARRESTER FROM 11kV THROUGH 380kV NOMINAL REFERENCE SECTION NO. DESCRIPTION Internal Pressure Required to Operate Pressure relief device as a Percent of Pressure required to Burst Porcelain (%) 'A' 'B' 'C' * Mounting arrangement Mode of mounting (self-supporting/bracket Bracket supporting) Bolt circle diameter (mm) No. of holes Size of Bolts (mm) * * * * Accessories Scale range of leakage ammeter(mA) * Diameter of the grading ring if applicable (mm) * Material of grading ring if applicable * Terminals Type Size (mm) Material (Al or CU) Pad * * Grounding Size (mm) Material * * MISCELLANEOUS Minimum clearance between live parts and earth parts (mm) * Minimum Permissible Center to Center Distance between Arresters (mm) * Overall Height of arrester (mm) * Weight of arrester (kg) * 35TMSS01R01/KSB Date of Approval: December 25, 2016 PAGE 13 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 35-TMSS-01, Rev. 01 DATA SCHEDULE SURGE ARRESTER FROM 11kV THROUGH 380kV NOMINAL A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY NATIONAL GRID,SA: B. ADDITIONAL SUPPLEMENTARY DATA OR BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: FEATURES Actual Manufacturer of Equipment/Material PROPOSED BY Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of authorized representative and date Official Seal/Stamp of the Company & Date 35TMSS01R01/KSB Date of Approval: December 25, 2016 PAGE 14 OF 14 TRANSMISSION MATERIALS STANDARD SPECIFICATION 9.0 48-TMSS-02, Rev.02 DATA SCHEDULE NON-METALLIC FIBER OPTIC CABLES National Grid SA Enquiry No. Date: National Grid SA Purchase Order No. or Contract No. Date: National Grid SA PTS No./Project Title with J.O. No. REFERENCE SECTION NO. 3.0 DESCRIPTION 'A' 'B' 'C' APPLICABLE CODES AND STANDARDS Standards to which material shall conform * 4.0 DESIGN AND CONSTRUCTION REQUIREMENTS 4.4 Optical Fiber Type Optical Fiber Core Material Cladding Material Diameter of Cladding, Nominal (m) * Primary Coating Material * Diameter of Primary Coating (m) * Non-circularity of cladding, single mode optic fiber, maximum (%) 2% Non-circularity of cladding, non-zero dispersion-shifted single mode optical fiber, maximum (%) 1% 'A'- NATIONAL GRID SA SPECIFIED DATA/PARAMETER. 'B'- BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS. 'C'- REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B'. (*)- DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B'. 48TMSS02R02/BAB Date of Approval: December 25, 2016 PAGE 20 OF 28 TRANSMISSION MATERIALS STANDARD SPECIFICATION 9.0 48-TMSS-02, Rev.02 DATA SCHEDULE NON-METALLIC FIBER OPTIC CABLES REFERENCE SECTION NO. 4.0 DESCRIPTION 'A' 'B' 'C' DESIGN AND CONSTRUCTION REQUIREMENTS (Continued) Secondary Coating Material Coating shall be easily removed without damage to the fibers Yes Diameter of Secondary Coating (m) Total Number of Optical Fibers Optical Fiber Material (Silica/Doped Silica) Optical Fiber Characteristics: Attenuation Loss: at 1310 nm (dB/km) for G.652D at 1383 nm (dB/km) for G.652D at 1550 nm (dB/km) for G.652D * * * Maximum Chromatic Dispersion: at 1285 - 1330 nm (ps/nm/km) * at 1550 - 1565 nm (ps/nm/km) * G.655 Optical Fiber Operational Wavelength nm 1550 / 1625 Maximum Optical Attenuation at : 1550 nm Wavelength (dB/km) 1625 nm Wavelength (dB/km) * * Maximum Chromatic Dispersion : 1550 nm (ps/nm/km) for G.655 1625 nm (ps/ nm/km) for G.655 * * Cut-off Wavelength (nm) * Polarization Mode Dispersion Coefficient (ps/√km) 48TMSS02R02/BAB ≤ 0.2 Date of Approval: December 25, 2016 PAGE 21 OF 28 TRANSMISSION MATERIALS STANDARD SPECIFICATION 9.0 48-TMSS-02, Rev.02 DATA SCHEDULE NON-METALLIC FIBER OPTIC CABLES REFERENCE SECTION NO. 4.0 4.5 DESCRIPTION 'A' 'B' 'C' DESIGN AND CONSTRUCTION REQUIREMENTS (Continued) Mode Field Diameter (m) * Mode Field Concentricity Error * Cladding Non-Circularity * Maximum Continuous operating temperature without optical degradation C * Maximum optical loss variation at temperature range of 0°C to + 80°C (dB/km) Color Coding: Color Coding of each Fiber for a group of twelve (12) fibers [additional group of twelve (12) fibers has the same sequence] * Blue Yellow Green Red Violet White Orange Brown Gray Black Pink Aqua Color Coding group identification Group #1 Group #2 Group #3 Group #4 Group #5 Group #6 Group #7 Group #8 48TMSS02R02/BAB Blue Yellow Green Red Violet White Orange Brown Date of Approval: December 25, 2016 PAGE 22 OF 28 TRANSMISSION MATERIALS STANDARD SPECIFICATION 9.0 48-TMSS-02, Rev.02 DATA SCHEDULE NON-METALLIC FIBER OPTIC CABLES REFERENCE SECTION NO. 6.1 DESCRIPTION 'A' 'B' 'C' Non-metallic Self-Supporting Fiber Optic Cables, Type A (Overhead) Manufacturer’s type/designation Messenger Support Diameter (mm) * Messenger Sheath Material Messenger Sheath Thickness (mm) Connection Material * * Connection Size (mm) * Central Strength Member Diameter (mm) * Tube or Core Material Tube or Core Diameter (mm) * * Filling compound * Wrapping Tape * Inner Sheath Material Inner Sheath Thickness (mm) Inner Sheath Diameter (mm) * * * Cable Weight (kg/km) * Tensile Strength (kN) * Compression (mm) * Minimum Bending Radius during : * Installation (mm) * Operation (mm) * Temperature during: (Storage & Transport.) °C Operation °C 48TMSS02R02/BAB * * Date of Approval: December 25, 2016 PAGE 23 OF 28 TRANSMISSION MATERIALS STANDARD SPECIFICATION 9.0 48-TMSS-02, Rev.02 DATA SCHEDULE NON-METALLIC FIBER OPTIC CABLES REFERENCE SECTION NO. 6.1 6.2 DESCRIPTION 'A' 'B' 'C' Non-metallic Self-Supporting Fiber Optic Cables, Type A (Overhead) (Continued) Maximum Span Length (m) * Maximum Allowable Pulling Tension (kN) * Non-Metallic Self-Supporting Fiber Optic Cables, Type B (Overhead) Manufacturer’s type/designation Strength Member (Material) (Kevlar) * Strength Member (FRP) & Kevlar (mm) * Yarn Reinforcing Diameter (mm) * Tube or Core Material Filling Compound Material * Cable Sheath - Material * Cable Sheath - Thickness (mm) * Cable Overall Diameter (mm) * Cable Weight (kg/km) * Minimum Bending Radius : Under no Tension (mm) * Under Tension (mm) * Maximum Span Length (m) * Maximum Allowable Pulling Tension (kN) * 48TMSS02R02/BAB Date of Approval: December 25, 2016 PAGE 24 OF 28 TRANSMISSION MATERIALS STANDARD SPECIFICATION 9.0 48-TMSS-02, Rev.02 DATA SCHEDULE NON-METALLIC FIBER OPTIC CABLES REFERENCE SECTION NO. 6.3 DESCRIPTION 'A' 'B' 'C' Non-Metallic Direct Buried Fiber Optic Cable: Manufacturer’s type/designation Central Strength Member Diameter (mm) * Tube or Core Material Tube or Core Diameter (mm) * Filling Compound * Wrapping Tape * Tube or Core Material Filling Compound Material * Inner Sheath Material * Inner Sheath Thickness (mm) * Inner Sheath Diameter (mm) * Outer Sheath Material * Outer Sheath Diameter (mm) * Cable Weight (Kg/km) * Tensile Strength (N) * Compression (mm) * Minimum Bending Radius (mm) * Temperature during: Trans. & Storage (°C) * Operation (°C) * 48TMSS02R02/BAB Date of Approval: December 25, 2016 PAGE 25 OF 28 TRANSMISSION MATERIALS STANDARD SPECIFICATION 9.0 48-TMSS-02, Rev.02 DATA SCHEDULE NON-METALLIC FIBER OPTIC CABLES REFERENCE SECTION NO. 6.4 DESCRIPTION 'A' 'B' 'C' Non-Metallic Duct Type Fiber Optic Cable: Manufacturer’s type/designation Central Strength Member Diameter (mm) * Tube or Core Material Tube or Core Diameter (mm) * Filling Compound * Wrapping Tape * Inner Sheath Material * Inner Sheath Thickness (mm) * Inner Sheath Diameter (mm) * Outer Sheath Material * Outer Sheath Diameter (mm) * Cable Weight (Kg/km) * Tensile Strength (N) * Minimum Bending Radius (mm) * Temperature during: Trans. & Storage (°C) * Operation (°C) * 48TMSS02R02/BAB Date of Approval: December 25, 2016 PAGE 26 OF 28 TRANSMISSION MATERIALS STANDARD SPECIFICATION 9.0 48-TMSS-02, Rev.02 DATA SCHEDULE NON-METALLIC FIBER OPTIC CABLES REFERENCE SECTION NO. 6.5 DESCRIPTION 'A' 'B' 'C' Non-Metallic Indoor Fiber Optic Cable:: Manufacturer’s type/designation Central Strength Member Material * Tube or Core Material Tube or Core Diameter (mm) * Wrapping Tape * Sheath Material * Sheath Diameter (mm) * Cable Weight (Kg/km) * Tensile Strength (N) * Compression (N/mm) * Minimum Bending Radius (mm) * Operating Temperature (°C) * 48TMSS02R02/BAB Date of Approval: December 25, 2016 PAGE 27 OF 28 TRANSMISSION MATERIALS STANDARD SPECIFICATION 9.0 48-TMSS-02, Rev.02 DATA SCHEDULE NON-METALLIC FIBER OPTIC CABLES A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY NATIONAL GRID SA: B. ADDITIONAL SUPPLEMENTARY DATA BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: OR Actual Manufacturer of Equipment/Material FEATURES PROPOSED Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of authorized representative and date Official Seal/Stamp of the Company & Date 48TMSS02R02/BAB Date of Approval: December 25, 2016 PAGE 28 OF 28 BY TRANSMISSION MATERIALS STANDARD SPECIFICATION 11.0 48-TMSS-06, Rev.01 DATA SCHEDULE MEDIUM DENSITY FIBER OPTIC SYSTEM National Grid SA Enquiry No. Date: National Grid SA Purchase Order No. or Contract No. Date: National Grid SA PTS No./Project Title with J.O. No. REFERENCE SECTION NO. 3.0 DESCRIPTION 'A' 'B' 'C' APPLICABLE CODES AND STANDARDS Reference Manufacturing Standard 4.0 DESIGN AND CONSTRUCTION REQUIREMENTS 4.1 General Type/Model/Brand * * Detailed Specifications attached for MDFOS * 4.2.1 Minimum environmental conditions for operation * 4.4.2 Optical input/output wavelength * Type of optical transmitter * 4.4.10 Type of alarm unit used to transmit alarms * 'A' – NATIONAL GRID SA SPECIFIED DATA/PARAMETERS 'B' - BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS 'C' - REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B' (*) - DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B' 48TMSS06R01/BAB Date of Approval: May 28, 2015 PAGE 52 OF 55 TRANSMISSION MATERIALS STANDARD SPECIFICATION 48-TMSS-06, Rev.01 11.0 DATA SCHEDULE MEDIUM DENSITY FIBER OPTIC SYSTEM REFERENCE SECTION No. DESCRIPTION Type of Power Supply Modules: Centralized/Decentralized External DC to DC Converters required If External DC to DC Converter is used , name & country of Manufacture 2 Mbps Tributary Interface required STM-1/STM-4 Tributary Interfaces required to interface with higher level SDH (STM-16) Digital Protection Interface type (Version 1) or (Version 3) (Detail shall be attached) 48TMSS06R01/BAB ‘A’ ‘B’ * * * * * * 2/4 Wire E&M Interface Module required * Subscriber Interface Module (FXO/FXS) required * Order Wire Interface Module required * Low Speed Data Interface Module required * Ethernet (10/100/1000 Mbps) Interface Module required * V.35 Interface Module required * 64 Kbps G.703 Interface module required * Date of Approval: May 28, 2015 ‘C’ PAGE 53 OF 55 TRANSMISSION MATERIALS STANDARD SPECIFICATION 48-TMSS-06, Rev.01 11.0 DATA SCHEDULE MEDIUM DENSITY FIBER OPTIC SYSTEM REFERENCE SECTION No. DESCRIPTION Local Craft Terminal required to program/configure equipment. If required, name of manufacturer and model of Personal Computer Equipment used for Local Craft Terminal (and provide brochures) Vendor Specific Network Management Terminal. (Details shall be attached) 48TMSS06R01/BAB Date of Approval: May 28, 2015 ‘A’ ‘B’ ‘C’ * * * PAGE 54 OF 55 TRANSMISSION MATERIALS STANDARD SPECIFICATION 48-TMSS-06, Rev.01 11.0 DATA SCHEDULE MEDIUM DENSITY FIBER OPTIC SYSTEM A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY NATIONAL GRID SA: B. ADDITIONAL SUPPLEMENTARY DATA BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS CONTRACTOR: TO BE OR FILLED-UP FEATURES BY Actual Manufacturer of Equipment/Material PROPOSED BY BIDDER/VENDOR/SUPPLIER/ Vendor/Supplier/ Contractor Name of the Company Location and Address Name and Signature of Authorized Representative and Date Official Seal/Stamp of the Company and Date 48TMSS06R01/BAB Date of Approval: May 28, 2015 PAGE 55 OF 55 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 48-TMSS-12, Rev. 01 DATA SCHEDULE FIBER OPTIC INTERCONNECTING DEVICES & PASSIVE COMPONENTS National Grid SA Enquiry No. Date: National Grid SA Purchase Order No. or Contract No. Date: National Grid SA PTS No./Project Title with J.O. No. REFERENCE SECTION NO. 3.0 DESCRIPTION 'A' 'B' 'C' APPLICABLE CODES AND STANDARDS Standards to which material shall conform 4.0 DESIGN REQUIREMENTS Fiber Optic Pig-tails, Patch cords Break-out Cable, Fan-out Cable, Drop Cable. Type of fiber Attenuation @ 1310/1383nm Attenuation @ 1550nm Total insertion loss Total return loss Operating Wavelength Version Single Mode G.652/G.657 < 0.37dB/km (without connectors) < 0.25dB/km (without connectors) < 0.45dB (with connectors) > 50dB (PC), 55dB (UPC), 60dB (APC) (with connectors) * * * * * 1260~1650nm * Simplex/ Duplex * Outer Jacket Material/Color * 'A'- NATIONAL GRID SA SPECIFIED DATA/PARAMETER. 'B'- BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS. 'C'- REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B'. (*)- DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B'. 48TMSS12R01/BAB Date of Approval: May 31, 2018 PAGE 20 OF 24 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 48-TMSS-12, Rev. 01 DATA SCHEDULE FIBER OPTIC INTERCONNECTING DEVICES & PASSIVE COMPONENTS REFERENCE SECTION NO. 4.0 DESCRIPTION 'A' 'B' 'C' DESIGN REQUIREMENTS (Continued) Fiber Optic Connectors Type of connector Connector Housing type Ferrule Material/Type Optical Fiber type Connector Intermateable Polished & Tinned Attenuation/Insertion loss Return Loss Metal/Plastic Yes/No Yes/No * * * * * * * * Fiber Optic Adapters Material * Metal/Plastic or Both Simplex/ Duplex Housing Material Version * * Attenuation/Insertion loss Return Loss Mounting type * * * Fiber Optic Attenuators Material Polarization dependent Loss (max) Housing Material Attenuation/Insertion loss Return Loss * * * * * 0.1dB Plastic/Metal Optical Fiber Management Rack (OFMR) Type Dimensions Main Frame Material Doors (Front & Back) material Doors (Front & Back) thickness * * * * * Solid/ Ventilated Front & Back Doors type Top & Bottom Cover Plate Material Top & Bottom Cover Plate thickness Shelves Material 48TMSS12R01/BAB Date of Approval: May 31, 2018 * * * * PAGE 21 OF 24 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 48-TMSS-12, Rev. 01 DATA SCHEDULE FIBER OPTIC INTERCONNECTING DEVICES & PASSIVE COMPONENTS REFERENCE SECTION NO. 4.0 DESCRIPTION 'A' 'B' Top/Bottom Yes/No Yes/No * * * 'C' DESIGN REQUIREMENTS (Continued) Cable Inlets Security Locking System Provided Earthing Bars, Point/Links Provided Minimum No. of Fiber Optic Cables that can be terminated Fiber Optic Patch Panel Frame Material Dimension Mounting Type Fiber Bend radii Water/Dust Proof Fiber Optic Splitter Box Frame Material Dimension Mounting Type Fiber Bend radii Water/Dust Proof Cable Inlet Lockable Optical Distribution Box Frame Material Dimension Mounting Type Fiber Bend radii Water/Dust Proof Easily Mountable inside racks/cabinets Cable Inlet Optical Distribution Frame Frame Material Dimension Mounting Type Fiber Bend radii Water/Dust Proof Easily Mountable inside racks/cabinets Cable Inlet 48TMSS12R01/BAB * IP41/IP54 * * * * * IP41/IP54 Top/Bottom Yes/No * * * * * * * IP41/IP54 Yes/No Top/Bottom * * * * * * * Yes/No Yes/No Top/Bottom * * * * * * * Date of Approval: May 31, 2018 PAGE 22 OF 24 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 48-TMSS-12, Rev. 01 DATA SCHEDULE FIBER OPTIC INTERCONNECTING DEVICES & PASSIVE COMPONENTS REFERENCE SECTION NO. 4.0 DESCRIPTION 'A' 'B' 'C' DESIGN REQUIREMENTS (Continued) Optical Splitter Frame Frame Material Dimension Mounting Type Fiber Bend radii Water/Dust Proof Easily Mountable inside racks/cabinets Front & Back Operation Fiber Optic Splice & Termination Panel (FSTP) Frame Material Dimension Mounting Type Fiber Bend radii Water/Dust Proof Easily Mountable inside racks/cabinets Cable Inlet Lockable * * Yes/No Yes/No Yes/No * * * IP41/IP54 Yes/No Top/Bottom Yes/No * * * * * * * * Fiber Optic Joint Closures (Aerial/Underground Use) Aerial/UG Al. Alloy, Galv. Steel, Stainless Steel, Fiber Glass, Polypropylene Type Housing Material Size & Dimensions Water/Dust Proof Splice Tray or Splice Cassette Material Cable Entries Closure gasket/seal material Grounding Provisions Security Locking Mechanism 48TMSS12R01/BAB IP67/IP68 Polycarbonate Top/Bottom or Both Chloroprene/ Neoprene Common, Isolated & External Grounding Yes/No Date of Approval: May 31, 2018 * * * * * * * * * PAGE 23 OF 24 TRANSMISSION MATERIALS STANDARD SPECIFICATION 6.0 48-TMSS-12, Rev. 01 DATA SCHEDULE FIBER OPTIC INTERCONNECTING DEVICES & PASSIVE COMPONENTS A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY NATIONAL GRID SAUDI ARABIA: B. ADDITIONAL SUPPLEMENTARY DATA OR BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: Actual Manufacturer of Equipment/Material FEATURES PROPOSED BY Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of Authorized representative And date Official Seal/Stamp of the Company & Date 48TMSS12R01/BAB Date of Approval: May 31, 2018 PAGE 24 OF 24 TRANSMISSION MATERIALS STANDARD SPECIFICATION 12.0 70-TMSS-03, Rev.02 DATA SCHEDULE NORMAL WEIGHT READY-MIXED PORTLAND CEMENT CONCRETE Enquiry No. Date: Purchase Order No. or Contract No. Date: PTS No./Project Title with J.O. No. REFERENCE SECTION NO. 4.0 DESCRIPTION 'A' 'B' 'C' APPLICABLE CODES AND STANDARDS DESIGN AND CONSTRUCTION REQUIREMENTS 8.5 a) Exposure Requirements b) Type of Cement c) Min. Cement Content (kg/m3) d) Pozzolanic Material Content (kg/m3) Name/Brand e) Req’d Min. Cylindrical Compressive Strength @ 28 Day Strength(MPa)* f) Max.water/ cementitious materials ratio g) Max. Slump w/o admixture (mm) h) Mass of fine aggregates (kg/m3) 'A' - SPECIFIED DATA/PARAMETER 'B' - BIDDER/SUPPLIER/VENDOR/CONTRACTOR PROPOSED DATA/PARAMETERS 'C' - REMARKS SUPPORTING THE PROPOSED DEVIATION IN COLUMN 'B' (*) - DATA/PARAMETER TO BE PROVIDED/PROPOSED BY THE BIDDER/SUPPLIER/ VENDOR/CONTRACTOR IN COLUMN 'B' 70TMSS03R02/SZA Date of Approval: November 15, 2018 PAGE NO. 36 OF 38 TRANSMISSION MATERIALS STANDARD SPECIFICATION 12.0 70-TMSS-03, Rev.02 DATA SCHEDULE NORMAL WEIGHT READY-MIXED PORTLAND CEMENT CONCRETE REFERENCE SECTION NO. DESCRIPTION 'A' 'B' 'C' DESIGN AND CONSTRUCTION REQUIREMENTS i) Coarse Aggregates Type Mass (kg/m3) Nominal Size (mm) j) Admixture: Type Brand Dosage (l/m³) 10.0 TESTS 10.2.2 Frequency of Sampling for Compressive Strength/m³ 10.2.4 Rapid Chloride Permeability Test (ASTM C1202) Frequency of Permeability Test/m³ Chloride Permeability Test (ASTM C1543) 70TMSS03R02/SZA Yes/No Yes/No Date of Approval: November 15, 2018 PAGE NO. 37 OF 38 TRANSMISSION MATERIALS STANDARD SPECIFICATION 12.0 70-TMSS-03, Rev.02 DATA SCHEDULE NORMAL WEIGHT READY-MIXED PORTLAND CEMENT CONCRETE A. ADDITIONAL TECHNICAL INFORMATION OR FEATURES TO BE FURNISHED BY NATIONAL GRID SA: B. ADDITIONAL SUPPLEMENTARY DATA BIDDER/VENDOR/SUPPLIER/CONTRACTOR: C. OTHER PARTICULARS TO BE FILLED UP BY BIDDER/VENDOR/SUPPLIER/ CONTRACTOR: OR Actual Manufacturer of Equipment/Material FEATURES PROPOSED BY Vendor/Supplier/ Contractor Name of the Company Location and address Name and Signature of authorized Representative and date Official Seal/Stamp of the Company & Date 70TMSS03R02/SZA Date of Approval: November 15, 2018 PAGE NO. 38 OF 38 INDICES OF APPROVED TRANSMISSION STANDARDS AND SPECIFICATIONS Standard No. Title Rev. No. Rev. Approved Date TRANSMISSION MATERIAL STANDARDS AND SPECIFICATION (TMSS) General Requirements 01-TMSS-01 GENERAL REQUIREMENTS FOR ALL EQUIPMENT/MATERIALS 3 Jan. 07, 2018 Total =1 Conductors, Bare 10-TMSS-01 [AMMENDMENT] Bare Conductors 2 Dec. 23, 2019 10-TMSS-02 Guy Wire Strand, Galvanized 0 Mar. 13, 2006 10-TMSS-03 Overhead Ground Wire (OGW) 0 Mar. 13, 2006 10-TMSS-04 [AMMENDMENT] OPTICAL FIBER GROUND WIRE (OPGW) 2 Dec. 23, 2019 10-TMSS-05 BARE, COPPER-CLAD STEEL GROUNDING CONDUCTOR, GROUND ROD AND GROUNDING CLAMPS/CONNECTORS Heat-Resistant Aluminum Alloy Bare Conductors For Overhead Line 2 Oct. 30, 2017 1 Jan. 21, 2013 10-TMSS-06 Total =6 Conductor, Insulated 11-TMSS-01 Power Cable , XLPE, Cu or Al, 1-Core, 69 kV 0 May. 30, 2006 11-TMSS-02 2 Jan. 02, 2018 11-TMSS-03 POWER CABLE, XLPE INSULATED, COPPER CONDUCTOR, SINGLE CORE, 110 kV, 115 kV, 132 kV, 230 & 380 kV RATING POWER CABLE, LPOF, CU, 1-CORE, 115kV, 132 kV, 230kV or 380kV 0 May. 30, 2006 11-TMSS-04 11 kV, 13.8 kV, 33 kV & 34.5 kV MEDIUM VOLTAGE POWER CABLES 1 Jun. 27, 2016 11-TMSS-06 Distributed Temperature Sensing (DTS) System For U/G Power Cable 0 Jul. 18, 2013 11-TMSS-10 2 May. 22, 2017 11-TMSS-11 POWER AND/OR CONTROL CABLES COPPER OR ALUMINUM CONDUCTOR 600/1000V RATING Instrumentation Cables, Shielded 0 Sep. 07, 2010 11-TMSS-12 COAXIAL BONDING AND EARTHING CABLES FOR LINK BOXES 1 May. 31, 2018 Total =8 Conductor Fittings 12-TMSS-01 LINE HARDWARE 3 Nov. 15, 2018 12-TMSS-02 Compression Type Connectors for Overhead Transmission Lines 1 Jan. 31, 2012 12-TMSS-03 Obstruction Markers And Warning lights 1 Dec. 17, 2014 12-TMSS-04 SPLICE & TERMINATIONS FOR MV POWER CABLES 1 May. 22, 2017 12-TMSS-10 Splice & Termination Kits for Power Cable 69 kV, 110 kV, 115 kV, 132 kV, 230 kV and 380kV LINK BOXES FOR POWER CABLES 1 May. 26, 2015 2 Apr. 08, 2019 12-TMSS-11 Total =6 Insulators 15-TMSS-01 Insulators, Station Post Type, Porcelain, Indoor/Outdoor 69kv Through 380Kv 1 Dec. 01, 2020 15-TMSS-02 [AMENDMENT] SUSPENSION TYPE INSULATORS, PORCELAIN OR GLASS 2 Sep. 30, 2019 15-TMSS-03 Insulators, Porcelain Horizontal Line Post Type 0 Apr. 09, 2006 09-Feb-2021 Page 1 of 15 Standard No. Title Rev. No. Rev. Approved Date 15-TMSS-04 [AMMENDMENT] INSULATORS, PORCELAIN LONG ROD TYPE 2 Mar. 15, 2020 15-TMSS-05 2 Oct. 30, 2017 15-TMSS-06 INSULATORS, COMPOSITE, HORIZONTAL LINE POST, SUSPENSION AND TENSION TYPE Composite Station Post Insulators, 69 kV through 230 kV 0 Feb. 14, 2007 15-TMSS-07 RTV SILICONE RUBBER INSULATOR COATING 1 May. 22, 2017 Total =7 Poles, Towers, Structures and Line Supports 20-TMSS-01 Transmission Line and Substation Latticed Steel Structures 1 Jan. 31, 2012 20-TMSS-02 Poles, Steel, Tapered, Tubular, for Transmission Lines 1 Dec. 17, 2014 20-TMSS-03 Wood Equivalent Steel Poles, Direct Embedded for Overhead Transmission Lines. 0 Sep. 01, 2009 Total =3 Conduits, Fittings & Accesssories 23-TMSS-01 PVC Conduits & Fittings for Underground Cables 1 May. 26, 2015 23-TMSS-02 Duct Sealing Units 0 Aug. 05, 2006 23-TMSS-04 Cable Clamps for Power Cables 0 Apr. 02, 2011 Total =3 Wire ways, Cable Trays, Boxes and Enclosures 24-TMSS-01 Metallic Cable Tray Systems 1 Jun. 19, 2012 Total =1 Line Switches and Disconnecting Devices 30-TMSS-01 AIR BREAK DISCONNECT SWITCHES AND EARTHING SWTCHES 33KV & ABOVE 1 Nov. 15, 2018 Total =1 Substation Panels 31-TMSS-01 Relay and Control Panels 1 Dec. 16, 2015 31-TMSS-02 AUXILIARY AC/DC PANELS 2 Nov. 15, 2018 31-TMSS-06 Terminal Blocks 1 Mar. 17, 2020 Total =3 Switchgear 32-TMSS-01 Metal-Enclosed Switchgear 11kV through 34.5kV 3 Dec. 01, 2020 32-TMSS-02 2 Dec. 17, 2014 0 Dec. 24, 2008 32-TMSS-04 SF6 Gas Insulated Switchgear & Hybrid SF6 Gas Insulated Switchgear, 110kV And Above Metal Clad Gas Insulated Medium Voltage Switchgear (11kV,13.8kV.33kV or 34.5kV) Hybrid SF6 Gas Insulated Switchgear Rated 69kV and Above 0 Apr. 02, 2011 32-TMSS-05 Rigid Gas-Insulated Transmission Lines (GIL) For Rated Voltage 110 kV And Above 1 Dec. 16, 2015 32-TMSS-07 SF6 Non-Extensible Ring Main Unit 11 kV through 34.5 kV 1 Dec. 16, 2015 32-TMSS-03 Total =6 Lightning & Surge Protection Devices 35-TMSS-01 09-Feb-2021 Surge Arrester11kv through 380kv Nominal 1 Dec. 25, 2016 Page 2 of 15 Standard No. Title Rev. No. Rev. Approved Date Total =1 Circuit Breakers 37-TMSS-01 Circuit Breaker, SF6, Dead Tank, 69 kV Through 380 kV 1 Jan. 21, 2013 37-TMSS-02 Circuit Breaker, SF6, Live Tank, 69 kV Through 380 kV 1 Jan. 21, 2013 37-TMSS-03 LV Circuit Breakers 0 Mar. 31, 2010 Total =3 Power Line Carrier, Supervisory Control 38-TMSS-01 Line Trap 0 Feb. 14, 2007 38-TMSS-02 Line Tuner 0 Oct. 10, 2007 38-TMSS-03 Remote Terminal Unit 1 Aug. 31, 2009 38-TMSS-04 Sequence of Events Recorder System 0 Mar. 25, 2007 38-TMSS-05 Annunciator Systems 0 Aug. 06, 2006 38-TMSS-06 DYNAMIC SYSTEM MONITOR 0 Dec. 24, 2008 38-TMSS-07 On-Line Partial Discharge Monitoring System 1 Dec. 01, 2020 38-TMSS-08 Coupling Capacitor Voltage Transformer for 69kV Thru 380kV System Voltage 0 Dec. 15, 2007 38-TMSS-09 Phasor Measurement Unit 1 Mar. 17, 2020 Total =9 Meters 40-TMSS-02 Metering Devices 0 Mar. 25, 2007 40-TMSS-03 Advanced Metering Infrastructure (AMI) 1 Jul. 18, 2013 Total =2 Protective Relays 41-TMSS-01 PROTECTIVE RELAYS 1 Oct. 30, 2017 41-TMSS-02 Digital Fault Recorder 0 Dec. 16, 2015 Total =2 Capacitor 43-TMSS-01 Shunt Capacitor Bank, 13.8kV through 380kV 1 Jan. 31, 2012 Total =1 Batteries and Power Supplies 46-TMSS-01 Vented Lead Acid Stationary Battery 1 Dec. 01, 2020 46-TMSS-02 Battery Chargers 2 Mar. 17, 2020 46-TMSS-03 UPS 5 kVA thru 100 kVA 0 Dec. 16, 2006 46-TMSS-04 Valve Regulated Lead Acid (VRLA) Stationary Battery Bank 0 Jan. 07, 2007 46-TMSS-05 48 Volt Communication Battery Chargers 2 Dec. 01, 2020 46-TMSS-06 Vented Nickel Cadmium Stationary Battery 1 Dec. 01, 2020 46-TMSS-07 DC-DC CONVERTORS 0 Apr. 29, 2009 09-Feb-2021 Page 3 of 15 Standard No. Title Rev. No. Rev. Approved Date Total =7 Ethernet Switch 47-TMSS-01 Ruggedized Industrial Ethernet Switch For Substation Automation System 0 Dec. 17, 2014 47-TMSS-02 Industrial Ethernet Switch For Advanced Metering Infrastructure 0 Dec. 04, 2014 Total =2 Substation Industrial LAN Devices/Equipments 47-TMSS-03 Industrial Computer For Substation Automation System 0 Dec. 16, 2015 Total =1 Communications & Fiber Optic Equipment 48-TMSS-01 Pilot Wire Cables 0 Aug. 21, 2006 48-TMSS-02 Non-Metallic Fiber Optic Cables 2 Dec. 25, 2016 48-TMSS-03 Pilot Cable Termination Box 0 Sep. 27, 2006 48-TMSS-04 Pilot Cable Termination Equipment 0 Aug. 21, 2006 48-TMSS-05 Pilot Cable Termination Equipment With Cabinet 0 Aug. 21, 2006 48-TMSS-06 Medium Density Fiber Optic System 1 May. 28, 2015 48-TMSS-07 SHELTERS FOR TELECOMMUNICATION FACILITIES 2 Oct. 14, 2019 48-TMSS-08 1 Jun. 27, 2016 48-TMSS-09 OPTICAL TRANSPORT NETWORK (OTN)-DENSE WAVELENGTH DIVISION MULTIPLEXING EQUIPMENT(DWDM) FOR BACKBONE NETWORK Synchronous Digital Hierarchy (SDH) Equipment 0 Jan. 02, 2014 48-TMSS-10 Ethernet Switch 0 Jul. 18, 2013 48-TMSS-11 Communication Services Router 0 Jul. 18, 2013 48-TMSS-12 FIBER OPTIC INTERCONNECTING DEVICES AND PASSIVE COMPONENTS 1 May. 31, 2018 48-TMSS-13 Telecom Cabinets & Racks 0 Dec. 17, 2014 48-TMSS-14 Remote Fiber Testing System 0 Dec. 17, 2014 48-TMSS-15 Digital Distribution Frame (DDF) 0 Dec. 16, 2015 48-TMSS-16 Digital Private Automatic Branch Exchange (DPABX) Equipment 0 Dec. 16, 2015 48-TMSS-17 Protection Signalling Equipment (PSE) 0 Dec. 16, 2015 48-TMSS-18 0 Jan. 02, 2018 48-TMSS-19 CLOSED CIRCUIT TELEVISION (CCTV) SURVEILLANCE AND SECURITY ACCESS CONTROL (SAC) SYSTEM Very Small Aperture Terminal (VSAT) 0 Dec. 25, 2016 48-TMSS-20 OPTICAL FIBER AMPLIFIER (OFA) DEVICES, SUBSYSTEMS OR COMPONENTS 0 May. 22, 2017 48-TMSS-21 PACKET TRANSPORT SYSTEM BASED ON MPLS-TP 1 Apr. 08, 2019 48-TMSS-22 IDENTITY AND ACCESS MANAGEMENT (IAS) 0 Apr. 08, 2019 48-TMSS-23 DIGITAL TRUNKED RADIO SYSTEM (DTRS) 0 Apr. 08, 2019 48-TMSS-24 SERVER HARDWARE SPECIFICATIONS (OT) 0 Apr. 08, 2019 48-TMSS-25 ACTIVE TELECOM SHELTER (FOR DAWIYAT USE) 0 Apr. 08, 2019 Total =25 Transformers, Current and Potential 09-Feb-2021 Page 4 of 15 Standard No. Title Rev. No. Rev. Approved Date 50-TMSS-01 Conventional and Low Power Current Transformers 11kV through 380kV 2 Dec. 01, 2020 50-TMSS-02 CAPACITOR VOLTAGE TRANSFORMER (CVT) 110kV THROUGH 380 kV 1 Jun. 27, 2016 50-TMSS-03 POTENTIAL TRANSFORMER 11kV THROUGH 380kV 1 Apr. 08, 2019 Total =3 Pad Mounted Station Service Transformer up to 2.5 MVA 51-TMSS-01 PAD- Mounted Station Service Transformer Up to 2.5 MVA 2 Mar. 17, 2020 Total =1 Transformer, Specialty 52-TMSS-01 Grounding Transformer, 13.8kV, 33kV or 34.5kV 0 May. 30, 2006 52-TMSS-02 Air Core Neutral grounding reactor 1 Dec. 25, 2016 Total =2 Power Transformer, Rated Above 2MVA 53-TMSS-01 Power Transformers, Rated Above 2.5 MVA 2 Dec. 25, 2016 53-TMSS-02 Power Transformers, Rated Above 100 MVA 1 Apr. 02, 2011 53-TMSS-03 Online Gas Analyzer 0 Aug. 31, 2009 Total =3 Electrical Insulating oil 54-TMSS-01 Uninhibited Insulating Mineral Oil 2 Dec. 16, 2015 54-TMSS-02 Inhibited Insulating Mineral Oil 0 Dec. 16, 2015 Total =2 Resistor 57-TMSS-01 Neutral Grounding Resistor, 11 kV through 34.5 kV 0 Jan. 08, 2007 57-TMSS-02 HARMONIC FILTER RESISTOR and DAMPING RESISTOR 0 Oct. 30, 2017 Total =2 Reactor 58-TMSS-01 Oil Immersed Reactor, 33 KV Through 380 KV 1 Jul. 18, 2013 58-TMSS-02 Air Core Series Reactor, 13.8KV Through 380KV 1 Jul. 18, 2013 Total =2 Static VAR Compensator “SVC” 59-TMSS-01 THYRISTOR VALVES FOR DYNAMIC REACTIVE POWER COMPENSATOR (DRPC) 0 Oct. 30, 2017 59-TMSS-02 VALVES COOLING SYSTEM FOR DYNAMIC REACTIVE POWER COMPENSATOR (DRPC) Voltage sourced converter (VSC) valves for static synchronous compensator (STATCOM) 0 Oct. 30, 2017 0 Apr. 08, 2019 59-TMSS-03 Total =3 CONSTRUCTION MATERIALS AND SUPPLIES 70-TMSS-01 Shop Applied Internal Cement Mortar Lining Of Steel Pipes 0 Oct. 10, 2007 70-TMSS-02 Chainlink Fence 1 Mar. 03, 2020 09-Feb-2021 Page 5 of 15 Standard No. Title Rev. No. Rev. Approved Date 70-TMSS-03 Normal Weight Ready-Mixed Portland Cement Concrete 2 Nov. 15, 2018 70-TMSS-04 CABLE TRENCH MATERIALS 1 Jun. 27, 2016 Total =4 CONSTRUCTION MATERIAL II 71-TMSS-02 Prefabricated portable bldg 0 Dec. 16, 2007 71-TMSS-03 Pre-Engineered Steel Building 1 Dec. 01, 2020 Total =2 AIR CONDITIONING EQUIPMENT 73-TMSS-01 Air Conditioning Units, Packaged 1 Jan. 21, 2013 73-TMSS-02 Packaged Air Cooled Water Chiller with Screw-Type Compressor 1 Apr. 13, 2014 73-TMSS-03 AIR HANDLING UNITS, CHILLED WATER TYPE 1 May. 22, 2017 73-TMSS-04 HVAC Pumps 1 Dec. 04, 2014 73-TMSS-05 Centrifugal Exhaust Fans 0 Jul. 17, 2007 Total =5 PIPES, HOSES, TUBINGS AND FITTINGS 75-TMSS-01 Plastic piping for plumbing systems 0 Dec. 03, 2008 75-TMSS-02 Vitreous China Plumbing Fixtures 0 Apr. 02, 2011 75-TMSS-03 Enameled Cast Iron Plumbing Fixtures 0 Jul. 17, 2007 Total =3 BOLTS; NUTS; WASHERS 76-TMSS-02 Irrigation Controllers And Valves 0 Jul. 15, 2007 Total =1 ABRASIVES; PAINT; PROTECTIVE COATING, OTHER 78-TMSS-01 Catalytically Cured Epoxy Phenolic Coating For Atmospheric Service 0 Oct. 10, 2007 78-TMSS-02 Catalytically Cured Epoxies & Epoxy Phenolics For Immersion And Damp Services 0 Oct. 10, 2007 78-TMSS-03 Primer: Zinc Phosphate 1 Jan. 21, 2013 78-TMSS-04 Paints: Enamel, Emulsion, Varnish And Laquers 0 Jun. 23, 2008 78-TMSS-05 Paints: Chlorinated Rubber Systems 0 Jun. 23, 2008 78-TMSS-06 Paints: Aluminum And Steel 0 Jun. 23, 2008 78-TMSS-07 Non-Skid Deck Paint 0 Jun. 23, 2008 78-TMSS-08 Miscellaneous Materials for Paints, Concrete Repairs and Plastering Accessories 1 Dec. 01, 2020 78-TMSS-09 Primers-Others 0 Dec. 03, 2008 78-TMSS-10 Paints for Interiors 0 Dec. 03, 2008 78-TMSS-11 Coating and Water Proofing 0 Dec. 03, 2008 78-TMSS-12 Floor Systems For Substations 0 Mar. 11, 2009 78-TMSS-13 Corrosion Protective Paint For Hot Dip Galvanized Steel Structures 0 Jan. 02, 2014 09-Feb-2021 Page 6 of 15 Standard No. Title Rev. No. Rev. Approved Date Total =13 WATER TREATMENT & STORAGE EQUIPMENT 80-TMSS-01 Shop Assembled Storage Tank 0 Jul. 15, 2007 Total =1 GENERATOR; PORTABLE; PUMPS; ENGINES; MOTOR 83-TMSS-01 Submersible Sump Pumps 0 Oct. 10, 2007 Total =1 SAFETY AND SECURITY EQUIPMENT 90-TMSS-01 Fire Protective Signaling Panel 0 Mar. 25, 2007 90-TMSS-02 Fire Water Pumps 1 Dec. 04, 2014 90-TMSS-03 Portable Fire Extinguishers 0 Jun. 24, 2008 90-TMSS-04 Carbon Steel Pipes For Fire Protection Systems 0 Dec. 03, 2008 90-TMSS-05 Aqueous Film Forming Foam (AFFF) & Fluoroprotein Foam Concentrates 0 Dec. 12, 2011 90-TMSS-07 Butt-Welding and Threaded Fittings for Fire Protection Systems 0 Dec. 12, 2011 90-TMSS-08 Emergency shower and eye (and face) wash equipment. 0 Apr. 29, 2009 90-TMSS-09 Valve Inspection And Testing Requirements 0 Jun. 23, 2008 90-TMSS-10 Fire Water Sprinklers 0 Dec. 16, 2007 Total =9 FURNISHINGS, MISCELLANEOUS APPLIANCES 94-TMSS-01 Automatic Electric Water Heaters 0 Jun. 23, 2008 94-TMSS-02 Drinking Water Coolers 0 Jun. 23, 2008 Total =2 TRANSMISSION ENGINEERING SPECIFICATION (TES) FIRE PROTECTION SYSTEM TES-B-106.01 Fire Detection And Alarm Systems 0 Dec. 17, 2007 TES-B-106.03 CO2 Total Flooding System 0 Dec. 03, 2008 TES-B-106.04 Deluge System 0 Apr. 29, 2009 TES-B-106.05 HFC-227ea Clean-Agent Extinguishing System 1 Dec. 16, 2015 TES-B-106.06 FK 5-1-12 Fixed Installation Total Flooding Clean-Agent Fire Extinguishing System 1 Dec. 16, 2015 Total =5 PAINT AND COATINGS TES-H-107.01 Painting 1 Apr. 13, 2014 TES-H-107.02 Paint Color Codes and Standards 1 Jul. 18, 2013 Total =2 AIR CONDITIONING , HEATING TES-K-100.01 09-Feb-2021 Heating, Ventilation and Air Conditioning Systems Design 2 Mar. 17, 2020 Page 7 of 15 Standard No. Title Rev. No. Rev. Approved Date Total =1 BATTERIES AND UPS STANDARDS TES-P-103.01 Introduction to Batteries and UPS Standards 1 Dec. 01, 2020 TES-P-103.02 Storage Battery Selection and Capacity Determination 1 Mar. 17, 2020 TES-P-103.03 Battery Charger Sizing 1 Mar. 17, 2020 TES-P-103.04 Storage Battery Installation 1 Mar. 17, 2020 TES-P-103.05 Uninterruptible Power System 0 Jul. 15, 2007 TES-P-103.06 Communication DC Power Systems 0 Oct. 09, 2007 Total =6 UNDERGROUND CABLE ENGINEERING STANDARDS TES-P-104.01 General Engineering Requirements for Underground Cables 1 Jun. 19, 2012 TES-P-104.02 Power Cable Construction 1 Jun. 19, 2012 TES-P-104.03 Sizing and Selection 1 Jun. 19, 2012 TES-P-104.04 Engineering Requirements for Splices & Terminations for Power Cables 1 Jun. 19, 2012 TES-P-104.05 Cable Installations, Engineering Requirements 3 Mar. 17, 2020 TES-P-104.08 BONDING AND GROUNDING OF METALLIC SHEATH OF INSULATED POWER CABLE SYSTEM (69 kV TO 380 kV) 2 May. 31, 2018 Total =6 Substation Automation System TES-P-107.01 Substation Automation System 0 Feb. 26, 2013 TES-P-107.02 SCADA SYSTEM FOR TRANSMISSION SUBSTATIONS WITH SUBSTATION AUTOMATION SYSTEM (SAS) SUBSTATION AUTOMATION SYSTEM HUMAN MACHINE INTERFACE GENERAL VIEW Cyber Security System Requirements for Substation Automation System 2 Nov. 15, 2018 1 Jan. 02, 2018 0 Dec. 25, 2016 Fiber Optic Cable Installation Engineering Requirements For Substation Automation System 0 Mar. 17, 2020 TES-P-107.04 TES-P-107.05 TES-P-107.06 Total =5 Protection System TES-P-108.02 2 Oct. 14, 2019 TES-P-108.03 PROTECTION REQUIREMENTS FOR 110kV THROUGH 380kV OVERHEAD TRANSMISSION LINES UG Cable Protection System 110kV Through 380kV 0 Feb. 26, 2013 TES-P-108.04 TELE-PROTECTION SYSTEMS 1 Oct. 14, 2019 TES-P-108.07 Shunt Reactor Protection System 33KV Through 380 kV 0 Jul. 18, 2013 TES-P-108.08 Shunt Capacitor Protection System 13.8KV Through 380KV 0 Jul. 18, 2013 TES-P-108.09 TRANSFORMER PROTECTION SYSTEM 1 Nov. 15, 2018 TES-P-108.10 BUS BAR AND CIRCUIT BREAKER FAILURE PROTECTION SYSTEM 0 Jun. 27, 2016 TES-P-108.11 PROTECTION SYSTEM FOR 11 KV and 13.8 KV FEEDERS 1 Nov. 15, 2018 TES-P-108.12 PROTECTION SYSTEM FOR 33 KV AND 34.5 KV FEEDERS 1 Nov. 15, 2018 TES-P-108.13 Bus Section and Bus Coupler Protection System 0 Dec. 25, 2016 TES-P-108.15 PROTECTIONS FOR VAR COMPENSATION SYSTEMS 0 May. 31, 2018 09-Feb-2021 Page 8 of 15 Standard No. Title Rev. No. Rev. Approved Date TES-P-108.16 UNDER VOLTAGE AND UNDER FREQUENCY LOAD SHEDDING SCHEME 0 Oct. 14, 2019 TES-P-108.17 HIGH-VOLTAGE DIRECT-CURRENT PROTECTIONSYSTEM 0 Nov. 15, 2018 TES-P-108.20 SAS EVENTS LIST FOR TRANSMISSION SUBSTATION WITH SUBSTATION AUTOMATION SYSTEM (SAS) 1 Oct. 30, 2017 Total =14 Substation Design Standards TES-P-119.01 Introduction to Substation Design Standards 0 Jan. 30, 2007 TES-P-119.02 [AMMENDMENT] Basic Design Aspects 1 Aug. 17, 2020 TES-P-119.05 Insulation Coordination 0 Oct. 17, 2006 TES-P-119.06 Surge Protection 0 Oct. 16, 2006 TES-P-119.07 Shielding 0 Oct. 16, 2006 TES-P-119.08 Substation Clearances 1 Dec. 16, 2015 TES-P-119.09 Busbars and Supporting Structures 1 Nov. 29, 2010 TES-P-119.10 Substation Grounding 1 Dec. 25, 2016 TES-P-119.11 Substation Insulators 0 Jan. 30, 2007 TES-P-119.12 Application Criteria for Electrical Equipment 0 Feb. 19, 2007 TES-P-119.18 Outdoor Equipment Foundation 1 Apr. 13, 2014 TES-P-119.19 SUBSTATION BUILDING AND SITE DEVELOPMENT 3 Nov. 15, 2018 TES-P-119.20 LV Cable Raceways & Cable Installation Practices 0 Dec. 16, 2006 TES-P-119.21 Fire & Loss Prevention and Security Requirements 1 Apr. 29, 2015 TES-P-119.25 LIGHTING AND RECEPTACLES FOR SUBSTATION YARD & BUILDING 2 May. 31, 2018 TES-P-119.26 Control Schemes for Substation Equipments 1 Nov. 29, 2010 TES-P-119.27 Supervisory Control and Data Acquisition (SCADA) 1 Jun. 30, 2010 TES-P-119.28 Protection and Metering Instrument Transformers CT & PT Sizing Calculation 0 Sep. 08, 2010 TES-P-119.29 LV Cable Selection and Sizing (600 V & Below) 0 Oct. 09, 2007 TES-P-119.30 AUXILIARY POWER SYSTEM AC/DC 2 Nov. 15, 2018 TES-P-119.31 Metering 0 Dec. 16, 2006 TES-P-119.33 Substation Electrical Diagrams 0 Dec. 16, 2006 TES-P-119.34 Application Of System Grounding 0 Dec. 15, 2007 TES-P-119.35 Station Auxiliary Transformer Sizing 0 Mar. 30, 2011 TES-P-119.36 Power Transformer Vector Group Matching 0 Jul. 06, 2011 TES-P-119.37 Short Circuit Calculation for Substation Equipment 0 Jul. 06, 2011 TES-P-119.38 Transformer Regulation and On Load Tap Changer Selection 0 Mar. 30, 2011 TES-P-119.39 Transformer Overloading & Life Span 0 Jun. 19, 2012 TES-P-119.40 Transformer X/R Ratio Calculation 0 Jul. 06, 2011 TES-P-119.41 Non-Linear Resistor Application in GIS 0 Mar. 30, 2011 TES-P-119.42 STATIC VAR COMPENSATOR (SVC) 1 Apr. 08, 2019 09-Feb-2021 Page 9 of 15 Standard No. Title Rev. No. Rev. Approved Date Total =31 TRANSMISSION LINE DESIGN STANDARDS TES-P-122.01 [AMENDMENT] BASIC DESIGN REQUIREMENTS FOR OVERHEAD TRANSMISSION LINES CONDUCTORS AND OVERHEAD GROUND WIRES 2 Nov. 22, 2020 1 Jan. 02, 2018 3 Nov. 15, 2018 TES-P-122.05-PI LINE HARDWARE & FITTINGS FOR CONDUCTORS AND OVERHEAD GROUND WIRES Transmission Line Structures Part I: Latticed Steel Towers 1 Jan. 31, 2012 TES-P-122.05-PII Transmission Line Structures Part II: Steel Poles 1 Jan. 21, 2013 TES-P-122.06 Transmission Structure Foundations 0 Sep. 08, 2008 TES-P-122.07 Transmission Structure Spotting 1 Dec. 13, 2011 TES-P-122.08 Survey Guidelines 1 Dec. 13, 2011 TES-P-122.09 Clearances And Right Of Way Requirements 2 Mar. 17, 2020 TES-P-122.10 Transmission Line Grounding 0 Feb. 18, 2007 TES-P-122.11 Access Road And Structure Pad 1 Jan. 21, 2013 TES-P-122.12 Upgrading Of Overhead Transmission Lines 0 Jun. 25, 2008 TES-P-122.03 TES-P-122.04 Total =12 CIVIL WORKS TES-Q-113.01 Design Criteria for Precast and Prestressed Concrete Structures 0 Jan. 31, 2012 Total =1 SAFETY AND SECURITY TES-S-101.01 Safety and Security - Introduction 0 Dec. 15, 2007 TES-S-101.02 Safety & Security - Security Fence 0 Dec. 15, 2007 TES-S-101.03 Safety & Security - Category II Fence 0 Dec. 15, 2007 TES-S-101.04 Safety & Security - Catergory III Fence 0 Dec. 15, 2007 TES-S-101.05 Safety & Security - Category III Fence (Alternative) 0 Dec. 15, 2007 TES-S-101.06 Safety & Security - Gates in Perimeter Fences 0 Dec. 15, 2007 TES-S-101.07 Safety & Security - Gates in Woven Wire Fabric Fences 0 Dec. 15, 2007 TES-S-101.08 Safety & Security - Barbed "S" Wire Concertina 0 Dec. 15, 2007 TES-S-101.09 Safety & Security - Security and Emergency Exit Doors 0 Dec. 15, 2007 TES-S-101.10 0 Dec. 15, 2007 TES-S-101.11 Safety & Security - Locks Used on Security Doors, Perimeter Fences and Emergency Exits Safety & Security - Building Housing Vital Equipment 0 Dec. 15, 2007 TES-S-101.12 Safety & Security - Protection Of Vital Equipments 0 Dec. 15, 2007 TES-S-101.13 Safety & Security - Power Supplies 0 Dec. 15, 2007 TES-S-101.14 Safety & Security - Communications 0 Dec. 15, 2007 TES-S-101.15 Safety & Security - Security Lighting Systems 0 Dec. 15, 2007 TES-S-101.16 Safety & Security - Check Point Lighting 0 Dec. 15, 2007 TES-S-101.17 Safety & Security - Intruder Detection Systems 0 Dec. 15, 2007 09-Feb-2021 Page 10 of 15 Standard No. Title Rev. No. Rev. Approved Date TES-S-101.18 Safety & Security - Automatic Control of Entry 0 Dec. 15, 2007 TES-S-101.19 Safety & Security - Gate House and Vehicle Lock 0 Dec. 15, 2007 TES-S-101.20 Safety & Security - Fire Fighting Equipments 0 Dec. 15, 2007 TES-S-101.21 Safety & Security - Work Permit Procedures 0 Dec. 15, 2007 TES-S-101.22 Safety & Security - Expanded Metal Mesh 0 Dec. 15, 2007 TES-S-101.23 Safety & Security - Protection of Diesel Engines 0 Dec. 15, 2007 TES-S-101.24 Safety & Security - Gasoline Filling Stations 0 Dec. 15, 2007 TES-S-101.25 Safety & Security - Automatic Control of Entry 0 Dec. 15, 2007 TES-S-101.26 Safety & Security - Turn Isles for Entry Control 0 Dec. 15, 2007 TES-S-101.27 Safety & Security - Internal Tank Cleaning 0 Dec. 15, 2007 TES-S-101.28 Safety & Security - Blast Resistant Control Building 0 Dec. 15, 2007 TES-S-101.29 Safety & Security - Tank Spacing-Dikes And Drainage 0 Dec. 15, 2007 TES-S-101.30 Safety & Security - The safe design, Construction, Operation and MTCC of On-Shore Pipelines for the Conveyance of Petrol General Procedures / Safety Standards For Blasting Near SEC Facilities. 0 Dec. 15, 2007 0 Dec. 15, 2007 TES-S-101.31 Total =31 CYBER SECURITY TES-S-102.01 CYBER SECURITY SYSTEM REQUIREMENTS 0 Jun. 27, 2016 Total =1 COMMUNICATIONS TES-T-111.02 Communication Facility Grounding 0 Mar. 29, 2008 TES-T-111.03 Communications Facility Lightning and Electrical Protection 0 Mar. 31, 2010 TES-T-111.05 General And VF Level Circuit Performance 0 Feb. 14, 2007 TES-T-111.06 Fiber Optic and PCM Circuit Performance 0 Dec. 03, 2008 TES-T-111.07 PLC/SSB Circuit Performance 0 Dec. 03, 2008 TES-T-111.08 ACC/FDM Circuit Performance 0 Dec. 03, 2008 TES-T-111.10 Communications Feeder Cables 0 Dec. 03, 2008 TES-T-111.12 Outside Plant (Communications) Standards and Practices for Facility Area Plan Design and Remote Distribution Area Plan Design Fire Protection Of Communication Facilities 0 Nov. 11, 2009 0 Jun. 25, 2008 0 Jan. 30, 2007 TES-T-111.19 Environmental Considerations For Communications Sites And Remote Communications Terminals Design Criteria For Communication Tower 0 Jul. 15, 2007 TES-T-111.20 Design Criteria of Communication Towers (For Dawiyat Use) 0 Jan. 20, 2021 TES-T-111.17 TES-T-111.18 Total =12 WELDING TES-W-109.01 General Welding Criteria 0 Mar. 30, 2011 Total =1 TRANSMISSION CONSTRUCTION SPECIFICATION (TCS) 09-Feb-2021 Page 11 of 15 Standard No. Title Rev. No. Rev. Approved Date AIR CONDITIONING, HEATING TCS-K-100.01 HVAC Systems and Equipment Installation 1 Apr. 13, 2014 Total =1 BUILDING CODE TCS-M-112.01 General Purpose Fencing 0 Dec. 03, 2008 Total =1 UNDERGROUND CABLE CONSTRUCTION STANDARDS TCS-P-104.01 General Requirments 0 Aug. 04, 2007 TCS-P-104.02 Cable Reels Handling & Storage 0 Oct. 09, 2007 TCS-P-104.03 Trenches and Ducts 0 Jun. 25, 2008 TCS-P-104.06 CABLE INSTALLATION, FIELD HANDLING PROCEDURES 1 May. 22, 2017 TCS-P-104.08 Field Testing of Power Cables Rated 110kV, 115kV, 132kV, 230kV or 380kV 0 Dec. 16, 2007 Total =5 COMMISSIONING TESTS AND CHECKS OF POWER TRANSMISSION NETWORK EQUIPMENT TCS-P-105 PRE-COMMISSIONING TESTS/PROCEDURES FOR TRANSMISSION ELECTRICAL 3 May. 18, 2020 Total =1 Substation Automation System TCS-P-107.01 PREPARATION OF SAS POINTS LIST FOR VERIFICATION 1 May. 31, 2018 TCS-P-107.03 Factory Acceptance Testing For Substation Automation Systems 0 Dec. 17, 2014 Total =2 PROTECTION SYSTEM CONSTRUCTION STANDARDS TCS-P-108.03 FAT for Relay and Control Panel 0 Dec. 25, 2016 TCS-P-108.05 RTDS TESTING FOR PROTECTIVE INTELLIGENT ELECTRONIC DEVICES 0 Nov. 15, 2018 Total =2 TRANSMISSION SUBSTATIONS CONSTRUCTION STANDARDS TCS-P-119.02 Terminal Compound Arrangement 0 Dec. 13, 2011 Total =1 TRANSMISSION LINE CONSTRUCTION STANDARDS TCS-P-122.01 Safety in Construction of Transmission Lines 0 Oct. 10, 2007 TCS-P-122.02 Material Handling 0 Oct. 17, 2006 TCS-P-122.03 Structure Staking 0 Jun. 23, 2008 TCS-P-122.05 Installation Of Steel Structure Foundations 0 Dec. 16, 2006 TCS-P-122.06 Steel Structure Assembly And Erection 1 Dec. 17, 2014 TCS-P-122.07 Installation of Overhead Line Conductors and Ground Wires 1 Jan. 31, 2012 TCS-P-122.08 Installation of Optical Fiber Ground Wire (OPGW) 1 Jul. 18, 2013 09-Feb-2021 Page 12 of 15 Standard No. Title Rev. No. Rev. Approved Date TCS-P-122.09 Storage, Handling & Installation of Composite Insulators 0 Aug. 04, 2007 TCS-P-122.21 Transmission Line Structure Details for 69kV to 380kV. 0 Aug. 18, 2009 TCS-P-122.22 APPLICATION OF RTV SILICONE RUBBER COATING ON OUTDOOR CERAMIC INSULATOTS Application Of Corrosion Protective Paint On Hot Dip Galvanized Steel Structures 1 May. 22, 2017 0 Jan. 02, 2014 TCS-P122.23 Total =11 CONCRETE FOUNDATIONS TCS-Q-113.01 Asphalt Concrete Paving 1 Jan. 02, 2014 TCS-Q-113.02 Earthworks 1 Jan. 21, 2013 TCS-Q-113.03 Cast in Place Concrete 1 Jan. 31, 2012 TCS-Q-113.04 Precast Concrete works 0 Dec. 17, 2007 TCS-Q-113.05 Reinforced Concrete Masonry 0 Dec. 13, 2011 TCS-Q-113.06 Concrete Rehabilitation 0 Jun. 19, 2012 Total =6 COMMUNICATIONS/UNDERGROUND COMMUNICATION (TELEPHONE/OPTICAL FIBER/PILOT) CABLE INSTALLATION TCS-T-111.01 1 May. 31, 2018 TCS-T-111.02 INSPECTION/ TESTING, ACCEPTANCE AND COMMISSIONING OF COMMUNICATIONS NETWORK EQUIPMENT Conduit Sealing For Underground Communication Cable 0 Dec. 03, 2008 TCS-T-111.03 Communication Cable Splicing 0 Nov. 29, 2010 TCS-T-111.04 Underground Telephone Cable Installation 0 Mar. 31, 2010 TCS-T-111.05 Long Pulls And Reel Length Limitations Of Underground Telephone Cables 0 Mar. 29, 2008 TCS-T-111.06 Optical Fiber Cables Splicing 1 Mar. 17, 2020 TCS-T-111.08 Installation of Underground Non-Metallic Fiber Optic Cables 1 Dec. 01, 2020 TCS-T-111.10 Underground Installation, Splicing and Testing / Acceptance of Pilot Cables 0 Dec. 03, 2008 TCS-T-111.11 Design And Installation Of Underground Communications Conduit And Manhole System Mini-Trenching 0 Mar. 29, 2008 0 Dec. 13, 2011 TCS-T-111.12 Total =10 TRANSMISSION DEVELOPMENT SPECIFICATION (TSD) TRANSMISSION STANDARD DRAWINGS TA-800001 110 /115 KV High/Low Bus Support & Disconnect Switch Structures 0 Mar. 25, 2007 TA-800002 Plan, Elevation, Section And Details Of Standard Switch Operating Platform 0 Mar. 25, 2007 TA-800003 110/115/132kv Typical Gantry Structure Drawing 0 Dec. 25, 2016 TA-800004 Lighting/Lightning Steel Monopoles 0 Mar. 25, 2007 TA-800005 110 kV to 115 kV "A" Frame Take Off Structure 0 Oct. 09, 2007 TA-800006 110/115 kV Take Off Structure – Lattice Gantry Structure 0 Jul. 15, 2007 TA-800009 Steel Doors, Frames and Hardware for SSD/7 Security Requirements 0 Dec. 13, 2011 TA-800012 Precast Concrete Boundary Wall (Plan, Elevation & Details) 0 Apr. 29, 2009 09-Feb-2021 Page 13 of 15 Standard No. Title Rev. No. Rev. Approved Date TA-800013 Boundary Wall for Substation Location in Urban Areas 0 Aug. 31, 2009 TA-800022 Gate in Woven Wire Fabric Fence (SAG SSD/5A:TES-S-101.07) 0 Oct. 12, 2009 TA-800023 Door Schedule & Details 0 Apr. 29, 2009 TA-800024 Finish Schedule / Miscellaneous Details 0 Apr. 29, 2009 TA-800039 Plans, Elevations & Sections for Gatehouse 0 Jun. 30, 2010 TA-800040 Foundation, Roof Plan & Details for Gatehouse 0 Jun. 30, 2010 TA-800041 Miscellaneous Details for Gatehouse 0 Jun. 30, 2010 TA-800042 Miscellaneous Details, Security Mesh & Bar Bending Schedule for Gatehouse 0 Jun. 30, 2010 TA-800049 Access Cage Ladder 0 Feb. 27, 2013 TA-800062 Typical Duct Bank Sections, Concrete Duct Bank 69kV to 380kV 0 Mar. 11, 2009 TA-800063 Highway Crossings for 69kV to 380kV Cables 0 Mar. 11, 2009 TA-800068 0 Nov. 23, 2009 0 Nov. 11, 2009 TA-800092 Highway Under Crossing for 110kV to 380kV U/G Power Cables by Directional Drilling Typical Detail of Conduit Mounting on the Gantry Structure for Non-Metallic Fiber Optic Cables Details Of Standard Anchor Bolts 0 Dec. 04, 2014 TA-800094 Typical Duct Splaying Layout For Manhole Entry 0 Dec. 17, 2014 TA-800096 Service Manhole Type-1 (1.20m x 1.5m x 1.85m) Details and Reinforcement 0 Mar. 30, 2011 TA-800097 Service Manhole Type-2 (1.50m x 2.75m x 2.00m) Details and Reinforcement 0 Mar. 30, 2011 TA-800098 Manhole/Handhole Accessories for Communications 0 Nov. 29, 2010 TA-800099 380kV Typical Gantry Structure 0 Dec. 16, 2015 TA-800100 132 kV Steel Take Off Structure and Details 0 Jun. 23, 2008 TA-800101 132kV "A” Frame Take-Off Structure 0 Nov. 23, 2009 TA-800102 132 kV High/Low Bus Support & Disconnect Switch Structures. 0 Jun. 23, 2008 TA-800106 Fire Protection System, Miscellaneous Details 0 Mar. 29, 2008 TA-800111 Substation Signboard at Gate House 0 Mar. 29, 2008 TA-800112 Decorative Steel Fence 0 Apr. 29, 2009 TA-800113 Chain Link Boundary Fence 0 Apr. 29, 2009 TA-800133 Removable Crash Barrier, Location Plan and Detail in Substation 0 Sep. 08, 2010 TA-800134 Septic Tank Installation Details for Non-Traffic Area 0 Sep. 08, 2010 TA-800135 Disposal System Layout & Seepage Pit Installation Details 0 Sep. 08, 2010 TA-800136 Miscellaneous Field Installation Details for Sanitary Works 0 Sep. 08, 2010 TA-800137 Sanitary Sewer Manhole Precast Concrete Plan, Section & Details 0 Sep. 08, 2010 TA-800138 Drainage Sump, Drainage Channel and Sewer Manhole Cover Details 0 Sep. 08, 2010 TA-800139 Counter Weight for Vehicle Entry Gate 0 Nov. 29, 2010 TA-800140 Water Proofing for Duct Banks, Manhole/Handhole and Alternate Roof Drainage Details Installation Detail for Link Boxes above Ground 0 Nov. 29, 2010 0 Jan. 31, 2012 Installation Detail for Link Boxes Below Ground 110 kV, 115 kV, 132 kV, 230 kV And 380 kV 0 Jan. 21, 2013 TA-800078 TA-800141 TA-800142 09-Feb-2021 Page 14 of 15 Standard No. Title Rev. No. Rev. Approved Date TA-800143 Concrete Masonry Unit (CMU) In Typical Substation, Plan, Sections And Details 0 Jun. 19, 2012 TA-800144 0 Jun. 19, 2012 TA-800151 Precast Boundary Wall Type-II (Typical Layout Plan, Elevation, Sections and Details) Heating, Ventilation and Air Conditioning (HVAC) Construction Details 0 Feb. 27, 2013 TA-800152 Heating, Ventilation and Air Conditioning (HVAC) Construction Details 0 Apr. 13, 2014 TB-800014 Pipe Line Crossing for SEC Access Roads 0 Sep. 08, 2010 TB-800067 Direct Buried Cable Trench Details in Rocky Area (Communications). 0 Aug. 31, 2009 TB-800069 Standard Trench detail Joint Communication & Power Cables 0 Aug. 31, 2009 TB-800076 1 Dec. 25, 2016 1 Dec. 25, 2016 TB-800079 Standard Precast Hand-Hole for Communication in Non Traffic Areas (1.20m x 1.20m x 1.20m) Standard Precast Hand-Hole for Communication in Traffic Areas (1.20m x 1.20m x 1.20m) PVC Conduit Installation Concrete Encased (Vital Communications) 0 Sep. 08, 2010 TB-800090 PVC Conduit Installation Concrete Encased (Non-Vital Communications) 0 Sep. 08, 2010 TB-800091 Concrete Encased Duct Detail for Rocky Areas (Vital Communications) 0 Nov. 11, 2009 TB-800095 CRASH BARRIER 0 Oct. 30, 2017 TC-800003 Signboard on Substation Building 1 May. 16, 2012 TC-800115 Transformer-Medium Voltage Switchgear Connection: Cable Arrangement 0 Jun. 30, 2010 TD-800007 Standard Sign Danger High Voltage Keep Away 0 Oct. 09, 2007 TD-800008 Standard Sign Danger High Voltage-Bone Skull 0 Jul. 15, 2007 TD-800061 Typical Tower Structure Configuration 380kV, 230kV, 132kV, 115kV & 110kV 0 Aug. 19, 2009 TE-800110 SEC Monogram for equipment Mounting 0 Dec. 03, 2008 TB-800077 Total =63 SAUDI ELECTRICITY COMPANY ENGINEERING DRAWINGS STANDARD(SEEDS) ENGINEERING DRAWINGS STANDARD SEEDS-I 0 PREPARING, PROCESSING & MANAGING TRANSMISSION DRAWINGS/DOCUMENTS Apr. 29, 2009 Total =1 ENGINEERING DRAWINGS STANDARD FOR CONTRACTORS SEEDS-II 1 Saudi Electricity Company Engineering Drawings Standard (SEEDS) for Preparing, Processing & Managing Transmission Drawings/Documents Jul. 09, 2011 Total =1 STANDARD GUIDELINES FOR GEOGRAPHIC INFORMATION SYSTEM (GIS) SEED-III STANDARD GUIDELINES FOR GEOGRAPHIC INFORMATION SYSTEM (GIS) 0 Jul. 13, 2014 Total =1 TMSS 09-Feb-2021 157 TES 128 TCS 40 TSD 63 SEEDS 3 TOTAL 391 Page 15 of 15 APPENDIX - III Page TECHNICAL DATA MANUALS 1. 1 of 1 Technical Data Manuals The CONTRACTOR shall provide Technical Data Manuals as applicable for underground cable systems installed under the PROJECT. The CONTRACTOR shall submit at least two (2) sets of manuals for review and approval by the COMPANY at least two (2) months prior to the mechanical completion date of the PROJECT. After COMPANY’S approval, the CONTRACTOR shall submit three (3) sets of final approved manuals two (2) weeks before mechanical completion date of the PROJECT. 2. Underground Cables The CONTRACTOR shall provide the technical data as applicable for XLPE cables, splices and terminations, as per details of updated Data Schedules of the relevant Material Standard Specifications (TMSS) stamped by the manufacturer. In addition to the above mentioned TMSS Data Schedules, the CONTRACTOR shall provide additional circuit information in the attached Form No. PTD-UG TECHNICAL DATA FOR UNDERGROUND CABLES Form No: PTD-UGC DS6 Project Title: TITLE Prepared by: Substation : ITEM # NAME OF CIRCUIT KV CABLE TYPE XLPE MANUFA CTURER CONDUCTOR SIZE CABLE PER PHASE Date: STRAIGHT JOINTS INSULATED JOINT STOP JOINTS APPENDIX - IV RIGHT OF WAY (ROW) APPROVAL AND CORRESPONDENCE Page 1 of 1 The Right -of- Way approval correspondences/conditions for the route shown in the ROW drawing is attached. The CONTRACTOR shall be responsible to implement all of these conditions and shall fully comply with the requirements stipulated in the approval letters from various agencies. The CONTRACTOR shall ensure strict compliance to all approval conditions of the various government and / or private agencies. APPENDIX V EXHIBIT I Contractor: _________________ Contract No.: _________________ S C H E D U L E O F A S S E T Work Description: ____________________________________ Work Location: ____________________________________ E Q U I P M E N T / C O M P O N E N T FOR SEC USE ONLY P. O. NO. OR INV. NO. B I N o.: ___________________ J O N o.: ___________________ J O T i t l e: ___________________ D a t e: ___________________ I D E N T I F I C A T I O N DESCRIPTION RATING etc. CAP. D E T A I L S MANUFACTURER MODEL NUMBER SERIAL NUMBER AMOUNT (SR) EXPECTED INSTALLATION DATE Contractor’s Representative: N a m e & S i g n a t u re Date APPENDIX VI COMMUNICATION SYSTEM REQUIREMENTS الشركة الوطنية لنقل الكهرباء National Grid SA DESCRIPTION CHK’D الكهرباء TELECOM ENGINEERING AND SUBSTATION AUTOMATION DEPARTMENT 1 2 3 NO. TELECOM ENGINEERING AND SUBSTATION AUTOMATION DIVISION - WOA REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED TESAD-WOA ATTACHMENT OF PTS-20WC1033 SCOPE OF WORK AND TECHNICAL SPECIFICATIONS FOR FIBER OPTIC CABLE AND LINK REQUIREMENTS FOR COMMUNICATION SYSTEM CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 1 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء TABLE OF CONTENTS DESCRIPTION SECTION REVISIONS DRAWN BY II 22/02/2021 CHK’D BY AMF 1.01 COMMUNICATIONS WORKS 1.02 STANDARDS, CODES AND SPECIFICATIONS MATERIALS 2.01 OPTICAL FIBER CABLE (NMFOC, OPGW,ADSS) RAAFAT DATE SCOPE OF WORK 1 2 3 NO. I 2.02 FIBER OPTIC JOINT BOXES 2.03 FIBER MANAGEMENT RACK APPROVED TESAD-WOA III IV TECHNICAL SPECIFICATIONS 3.01 FIBER OPTIC CABLE INSTALLATIONS 3.02 INSTALLATION OF FIBER OPTIC CABLE JOINT BOXES TESTING AND COMMISSIONING 4.01 TESTING OF FIBER OPTIC CABLES CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 2 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء SECTION I- SCOPE OF WORK 1. COMMUNICATION WORKS DESCRIPTION 1.01 CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S 1 2 3 NO. A) REVISIONS DRAWN BY UG-NMFOC from Madinah ISTP 110KV S/S To NAKHEEL 110KV S/S. a- Provide and install one (1) No of U/G-NMFOC having approximately 9 Km long, 96 cores single mode cable ITU-T G652D, from the New Optical Fiber Management Rack (OFMR) inside Madinah ISTP 110KV S/S communication room to the New Optical Fiber Management Rack (OFMR) inside NAKHEEL 110KV S/S. The U/G-NMFOC shall be routed through the communication ductbank. CONTRACTOR shall provide and install ductbank, PVC/HDPE subducts for routing U/G-NMFOC. RAAFAT DATE 22/02/2021 CHK’D BY AMF Design and construction of communication ductbank and handholes for routing the U/GNMFOC inside the switchyard up to the communication room at switchgear and control building including the installation PVC coated RSGC and cable trays at the communication room shall be done by the contractor. APPROVED The CONTRACTOR is fully responsible to provide all associated accessories (FSTP, Pigtail, Patch Cord, Connectors, etc.) at Madinah ISTP 110KV S/S and NAKHEEL 110KV S/S in order to patch/terminate the proposed fiber optic cables under this project. TESAD-WOA Perform splicing of Eall fibers cores at all required locations along the fiber optic cable route to form a complete Fiber Optics Cable Link for all cores between the following locations: Madinah ISTP 110KV S/S to NAKHEEL 110KV S/S: 1x96 cores. The CONTRACTOR shall provide, install, test and commission Dispersion Unshifted Single- Mode (ITU-T G.652D) underground non-metallic fiber optic cable (U/G-NMFOC) type. CERTIFIED BY: MRR DATE: 22-Feb-21 b- Provide and install Optical Fiber Management Rack (OFMR) with FSTPs in the communication room as follows: Madinah ISTP 110KV S/S 1FMR+2FSTP - B) THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED NAKHEEL 110KV S/S UG-NMFOC From Madinah ISTP 110KV S/S To ISUNI-2 110KV S/S. a- Provide and install one (1) No of U/G-NMFOC having approximately 13 Km long, 96 cores single mode cable ITU-T G652D, from the New Optical Fiber Management Rack (OFMR) inside Madinah ISTP 110KV S/S communication room to the New Optical Fiber Management Rack (OFMR) inside ISUNI-2 110KV S/S. The U/G-NMFOC shall be routed through the communication ductbank. CONTRACTOR shall provide and install ATTACHMENT JOB ORDER NO. 1FMR+1FSTP PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 3 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء ductbank, PVC/HDPE subducts for routing U/G-NMFOC. DESCRIPTION Design and construction of communication ductbank and handholes for routing the U/GNMFOC inside the switchyard up to the communication room at switchgear and control building including the installation PVC coated RSGC and cable trays at the communication room shall be done by the contractor. Perform splicing of Eall fibers cores at all required locations along the fiber optic cable route to form a complete Fiber Optics Cable Link for all cores between the following locations: Madinah ISTP 110KV S/S to ISUNI-2 110KV S/S: 1x96 cores. 1 2 3 NO. The CONTRACTOR is fully responsible to provide all associated accessories (FSTP, Pigtail, Patch Cord, Connectors, etc.) at Madinah ISTP 110KV S/S and ISUNI-2 110KV S/S in order to patch/terminate the proposed fiber optic cables under this project. REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED The CONTRACTOR shall provide, install, test and commission Dispersion Unshifted Single- Mode (ITU-T G.652D) underground non-metallic fiber optic cable (U/G-NMFOC) type. b- TESAD-WOA F) Provide and install Optical Fiber Management Rack (OFMR) with FSTPs in the communication room as follows: ISUNI-2 110KV S/S 1FMR+1FSTP SPLICING/TERMINATION AND COMPLETING THE LINKS For all links mentioned above, the CONTRACTOR shall perform splicing/termination of all fibers cores at all required locations joint boxes to form complete Fiber Optic link. All Connectors at all joint locations in these links shall be LC/APC type. CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 4 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء 1.02 STANDARDS, CODES AND SPECIFICATIONS A. COMPANY Material Standard Specifications DESCRIPTION TMSS # 10-TMSS-04 Rev.02 48-TMSS-02 Rev.02 Description AMMENDMENT-01 - Optical Fiber Ground Wire (OPGW) Non-Metallic Fiber Optic Cable (NMFOC) 1 2 3 NO. B. COMPANY Construction Standards REVISIONS DRAWN BY TCS # TCS-T-111.06 Rev.01 TCS-T-111.08 Rev.01 Description Optical Fiber Cables Splicing Underground Installation of Optical Fiber Cables RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED B. COMPANY Standards Drawings TSD # TB-800079 Rev.00 TA-800098 Rev.00 TESAD-WOA TB-800076 Rev.01 TB-800077 Rev.01 TA-800078 Rev.00 Description PVC Conduit Installation Concrete Encasement Communication Manhole/Handhole Accessories for Communications Standard Precast Handhole for Communication in NonTraffic Areas (1.20mx1.20mx1.20m) Standard Pre-cast Handhole for Communication in Traffic Areas (1.20mx1.20mx1.20m) Typical Detail of Conduit Mounting on the Gantry structure for Non-metallic Fiber Optic Cables **** END OF SECTION I **** CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 5 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء SECTION II-MATERIALS 2.01 OPTICAL FIBER CABLES DESCRIPTION A. COMPOSITE OPTICAL GROUNDWIRE (OPGW) 1 2 3 NO. The composite Optical Groundwire Cable (OPGW) shall meet all the requirements of COMPANY Material Standard Specification 10-TMSS-4. For standard specifications, if another standard is to be used for the fiber optics cable contained in the OPGW cable (e.g. in the case of non-zero dispersion shifted fiber optics cable), please revise the previous paragraph as necessary, and make the required additions/deletions as required. REVISIONS B. UNDERGROUND NON-METALLIC FIBER OPTIC CABLE (NMFOC) DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED TESAD-WOA The Non-Metallic Underground Optical Fiber Cable shall meet all the requirements of COMPANY Material Standard Specifications 48-TMSS-02, For standard specifications, if another standard is to be used for the fiber optics cable contained in the OPGW cable (e.g. in the case of non-zero dispersion shifted fiber optics cable), please revise the previous paragraph as necessary, and make the required additions/deletions as required. C. SELF SUPPORTING NON-METALLIC FIBER OPTIC CABLE (SS NMFOC) The Self-supporting Non-Metallic Fiber Optic Cable shall meet all the requirements of the COMPANY Material Standard Specification 48-TMSS-02, CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED For standard specifications, if another standard is to be used for the fiber optics cable contained in the OPGW cable (e.g. in the case of non-zero dispersion shifted fiber optics cable), please revise the previous paragraph as necessary, and make the required additions/deletions as required. D. CONTRACTOR shall submit his proposal along with Technical Specification and representative sample of the cable to the COMPANY for review and approval prior to manufacturing the cable. All types of the Optical Fiber Cables shall be compatible with each other. The CONTRACTOR and the cable manufacturer shall guarantee that the Fibers of each Cable Drum supplied to the COMPANY have matching parameters to enable good optical splices within COMPANY specified maximum allowable optical splice loss limit. ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 6 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء 2.02 FIBER OPTICS JOINT BOXES A. TAKE-OFF STRUCTURE TYPE 4-WAY JOINT BOX (OPGW - U/G NMFOC) 1 2 3 NO. DESCRIPTION This type of Joint Box will be used in locations known as take-off structures where the incoming OPGW cable (at the substation end) will terminate with the underground fiber optics cable at the site. Cable Glands (minimum of four each) shall be supplied for this type of joint box, with two cable glands provided for the incoming underground fiber optics cable (which will enter at the bottom of the joint box, and the cable glands fitted with a reduction adapter to mate with the incoming underground flexible conduit to provide a watertight connection to the underground conduit), and two cable glands provided for the incoming OPGW cable (with the cable glands located on the side of the take-off structure Type Joint Box, providing a watertight connection and fitting snug with the incoming OPGW cable). All splice cassettes/cable trays shall be supplied and installed inside this type of joint box, as well as all other accessories for splicing the fiber optics cables. The take-off structure Type Joint Box shall have a grounding connection for tying the box to an external ground. REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF B. TAKE-OFF STRUCTURE TYPE 4-WAY JOINT BOX (SS NMFOC - U/G-NMFOC) This type of Joint Box will be used in locations known as take-off structures where the incoming Self-supporting Non-Metallic Fiber Optic Cable (SS NFOC) (at the substation end) will terminate with the underground fiber optics cable at the site. Cable Glands (minimum of four each) shall be supplied for this type of joint box, with two cable glands provided for the incoming underground fiber optics cable (which will enter at the bottom of the joint box, and the cable glands fitted with a reduction adapter to mate with the incoming underground flexible conduit to provide a watertight connection to the underground conduit), and two cable glands provided for the incoming SS NFOC (with the cable glands located on the side of the take-off structure Type Joint Box, providing a watertight connection and fitting snug with the incoming SS NFOC). All splice cassettes/cable trays shall be supplied and installed inside this type of joint box, as well as all other accessories for splicing the fiber optics cables. The take-off structure Type Joint Box shall have a grounding connection for tying the box to an external ground. APPROVED TESAD-WOA CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED C. MID SPAN TYPE 4-WAY JOINT BOX (OPGW - OPGW) This type of Joint Box will be used in locations known as Mid-Span Structures where incoming OPGW cable will terminate with another OPGW cable at the site. Cable Glands (minimum of four each) shall be supplied for this type of joint box, with two cable glands entering at the bottom of the joint box, and two cable glands entering on the side of the joint box. (with the cable glands located on the side of the take-off structure Type Joint Box, providing a watertight connection and fitting snug with the incoming OPGW cable). All splice cassettes/cable trays shall be supplied and installed inside this type of joint box, as well as other accessories for splicing the fiber optics cables. The Mid Span Type Joint Box shall have a grounding connection for tying the box to an external ground. ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 7 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء D. MID SPAN TYPE 4-WAY JOINT BOX (SS NMFOC – SS NMFOC) 1 2 3 NO. DESCRIPTION This type of Joint Box will be used in locations known as Mid-Span Structures where incoming SS NFOC will terminate with another SS NFOC at the site. Cable Glands (minimum of four each) shall be supplied for this type of joint box, with two cable glands entering at the bottom of the joint box, and two cable glands entering on the side of the joint box. (with the cable glands located on the side of the take-off structure Type Joint Box, providing a watertight connection and fitting snug with the incoming SS NFOC cable). All splice cassettes/cable trays shall be supplied and installed inside this type of joint box, as well as other accessories for splicing the fiber optics cables. The Mid Span Type Joint Box shall have a grounding connection for tying the box to an external ground. REVISIONS E. UNDERGROUND TYPE 4-WAY JOINT BOX (U/G NMFOC – U/G NMFOC) DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED TESAD-WOA This type of Joint Box will be used in locations such as Underground Handholes/Manholes (where CONTRACTOR will route underground cable) where two underground fiber optics cables will be joined. All splice cassettes/cable trays shall be supplied and installed inside this type of joint box, as well as other accessories for splicing the fiber optics cables. The Underground Type Joint Box shall have a grounding connection for tying the box to an external ground. Notes applicable to all Joint Boxes – Tagging/Labeling During the installation of all Joint Boxes – Tags/labels shall be provided for each joint box, which shall contain the following information. CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED Contract Number of the Cable Installation: CONTRACTOR Name: Route of the Fiber Optic Cable (Source/Destination) Number of Fiber Cores: Type of Fiber Optic Cable: Structure Number of the installation (Outdoor Type Fiber Joint Boxes Only): Handhole/Manhole Number (Underground Type Fiber Joint Boxes Only): For outdoor type Joint Boxes, the tagging/labeling shall be provided and installed on a permanently affixed stainless steel tag whose size, lettering, and location shall be easily readable from personnel on the ground, and shall use embossed letters to allow for ease of reading. For underground type joint boxes (where used), the tagging/labeling shall be provided and installed on a permanently affixed stainless steel tag, or plastic tag whose size, lettering, and location shall be easily readable from personnel on the ground, and shall use embossed letters to allow for ease of reading. For all joint box tags, a sample of each tag shall be submitted for COMPANY review ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 8 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء and comment before manufacture of each tag. Notes applicable to all Joint Boxes-Other 1 2 3 NO. DESCRIPTION As a part of submittals provided by the CONTRACTOR, type test data and materials brochures shall be supplied by clearly identifying the type of fiber optics joint boxes, which are to be supplied. This data shall include (but not be limited to the following): REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED a. b. c. d. e. f. g. Crush Resistance, static load Impact Resistance, chemical resistance test Dimensions and mounting details of the Joint Box Inside dimensions, and details for mounting of all accessories Watertighthness and temperature cycling test of the Joint Box Grounding Details of the Joint Box Accessories list, including details of splice cassettes, and trays, mounting hardware and accommodate looping of excess fiber optics cable Each Fiber Optics Joint Box which is to be supplied shall be able to loop an additional 10 meters of fiber optic cores inside the joint box, other than the fiber optics cores which are to be contained inside the Splice Cassette tray. The box shall be designed with retainers to allow for looping of these excess fiber optics cores. TESAD-WOA 2.03. OPTICAL FIBER MANAGEMENT RACK:O.F.M.R Specifications: A. The Fiber Optics Cable Management rack shall be designed to utilize a standard EIA (Electronic Industries Association) 19 Inch or 23 Inch rack which will be suitable for mounting splice cassette/splice organizer modules, as well as modules which will be terminate fiber optics pigtail and fiber optics patch cable. Each standard EIA 19 inch or 23 inch rack shall be of a height which is consistent with the overall equipment installation at the site (either 2.0 meters high, or 2.2 meters high, depending on the installation. CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED B. As part of the design of the Fiber Optic Cable management Rack, enclosures will be provided for the housing of splice organizer/splice cassette trays, used to splice incoming fiber optics cable (indoor cable, or underground fiber optics cable) with fiber optics pigtail cables. The enclosure used for this purpose may be either a “pull-out” type design (where a technician will pull out the associated tray of the enclosure from the front access, exposing the inner fiber optics joints), or may be a “swing frame” design (with a left-hand hinge, and a handle on the right side) to allow the access for the splice organizer/splice cassette tray, by “swinging out” the enclosure from the right side handle. Splice organizer trays used in this enclosure shall be sized to accommodate a minimum of forty-eight (96) fusion splices. Also, the enclosure used to hold the splice organizer/splice cassette tray shall be designed with sufficient space, and lopping supports to provide storage of a minimum of five (5) meters of excess fiber optics pigtail cable (96 pigtails). ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 9 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA 1 2 3 NO. DESCRIPTION CHK’D الكهرباء REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED TESAD-WOA C. As part of the design of the Fiber Optic Cable Management Rack/Panel, enclosures will be provided for the housing of fiber optics termination connections (FC/PC barrel, or bulkhead connectors) used to interconnect fiber optics pigtail cords with Fiber Optic Patch Cable.. The enclosure used for this purpose may be either a “pull-out” type design (where a technician will pull out the associated tray of the enclosure from the front access, exposing the connections between the fiber optics pigtail cables with the fiber optics patch cables), or may be a “swing frame” design (with a left-hand hinge, and a handle on the right side) to allow the access to the interconnection between the fiber optics pigtail cable, and fiber optics patch cable, by “swinging out” the enclosure from the right side handle. also, the enclosure used to hold the splice organizer/splice cassette tray shall be designed with sufficient space, and looping supports to provide storage of a minimum of five (5) meters of excess fiber optics pigtail cable (for 96 cores fiber termination connection enclosure is used)) and a minimum of five meters of excess fiber optics patch cable. FC/PC Fiber Optic Barrel, or Bulkhead connectors used shall allow for no greater than a 0.5dB/per connection loss, when the connection is used, and shall be designed for use with Single Mode Fiber Optics Cable. D. Also, as part of the design/construction of the Fiber Optics Cable Management Rack, all accessories required to orderly route incoming underground fiber optic cable, indoor fiber optics cable, as well as fiber optics pigtail cable, and fiber optics patch cable shall be provided. These may include items such as “D” channels, incoming flexible sub duct, mounting supports (for incoming fiber optics cable), buffer tubes for fiber optics cores (in the enclosure used for splicing), brackets/guides to route fiber optics pigtail/patch cable between portions of the Fiber Optics Cable Management Rack, and other accessories which are required as part of the equipment manufacture’s design/construction of the Fiber Optics Cable Management Rack. E. If the Fiber Optics Cable Management Rack is exclusively used for patching and termination of fiber optics pigtail cable, and fiber optics patch cable, the Fiber Optics Cable Management Rack shall allow for the termination of a minimum of 96 fibers (or 2 each 24-cores Fiber Optics Cables). CERTIFIED BY: MRR DATE: 22-Feb-21 F. Also the Fiber Optics Cable Management Rack shall be provided with required dust proof covers (to prevent fiber optics splices form dust entry) and identification Tags/Labels to identify all incoming fiber optics cables to the cable Management Rack. G. Prior to the Contractor's supply of the Fiber Optics Cable Management Rack/Panel to the COMPANY, the CONTRACTOR shall provide full colored brochures, and equipment specifications for COMPANY review and approval. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED **** END OF SECTION II **** ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 10 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء SECTION III- TECHNICAL SPECIFICATIONS 3.01 FIBER OPTIC CABLE INSTALLATIONS DESCRIPTION CONTRACTOR shall prepare the details and procedures in the installation, including cable splicing shall be submitted to the COMPANY for review and acceptance. 1 2 3 NO. A. Optical Fiber Cables (OPGW) REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF The OPGW cable shall be installed as per COMPANY Construction Standard TCS-P122.8. The OPGW shall be tested as per COMPANY Construction Standard. A minimum two (2) loop of the cable shall be securely left inside each intermediate Handhole for future use. A minimum 15 meters additional length of the cable shall be securely left inside start and end Handhole. APPROVED B. Optical Fiber Cables (SS NMFOC) TESAD-WOA The SS NFOC shall be installed in full compliance with the installation instructions of the SS NMFOC manufacturer. As part of the installation requirements, all SS NFOC manufacturer’s recommended tools and installation machinery shall be used during the installation process by the CONTRACTOR. The Optical Fiber Cable shall be tested as per COMPANY Construction Standard. As part of the installation requirements all the Fiber Optics Cable Manufacturer’s recommended tools and installation machinery/materials shall be used. CERTIFIED BY: MRR DATE: 22-Feb-21 A minimum of two (2) loop of the cable shall be securely left inside each intermediate Handhole for future use. A minimum 15 meters additional length of the cable shall be securely left inside start and end Handhole. C. U/G Non-metallic Optical Fiber Cables THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED Underground Optical Fiber Cables in PVC subducts shall be installed from the Overhead/Underground Transition Structure at each site (list each source substation and each destination substation here) up to the Communications Equipment location inside each site (list each source substation and each destination substation here). PVC subducts, and conduits are to be provided inside the boundaries at both the source substation(s) (list all source substations here), and the destination substation(s) (list all source substations here), by others (under the substation contract). Inside each ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 11 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء DESCRIPTION substation, CONTRACTOR shall provide and install required two (2) hour fire rated subduct (as per NFPA-70 (U S National Electric Code) requirements) from the building entrance to the location of the communications equipment, as well as all additional civil work needed (cable trays/extensions, cable ladders, conduit raceways, etc.) if required to allow for the extension of the cable to the location of the communications equipment. 1 2 3 NO. Additionally, for all the underground cable installations inside the substation, fiber optics cables contained in conduit shall be tagged at 5-meter intervals, with the following information contained on each cable tag: Contract Number of Installation: Line Route: Cable Length: REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED TESAD-WOA Type of Fiber Optics Cable, and COMPANY Fiber Optics Cable Specifications: (E.G. Single Mode, 48-TMSS-02, etc.) Cable tags shall be either an embossed plastic, or metal firmly secured to the subduct of the incoming fiber optics cable. The underground non-metallic fiber optic cables shall be installed inside rigid conduits in duct banks from the (OPGW-U/G) joint boxes on the gantry structures up to the terminal splice boxes inside the communications room. The underground non-metallic fiber optic cables installed between stations shall be terminated in the terminal joint boxes inside the communications rooms at both ends of the links in accordance with COMPANY Construction Standard TCS-T-111.08 Rev.01 Sufficient extra length (at least 15 meters) of the underground non-metallic fiber optic cable shall be securely looped inside the start and end handholes for future splice requirements. At the intermediate handholes, at least two (2) loops (with a minimum length of 5 meters) of non-metallic fiber optic cable shall be provided for any future requirement. CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 12 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء 3.02 INSTALLATION OF FIBER OPTIC CABLE JOINT BOXES A. Optical Fiber Cable Joint Boxes DESCRIPTION 1. OPGW-OPGW (4 way) Optical fiber cable joint boxes shall be installed on the transmission line structures, as required, at a height of 5 meters above the ground level outside the substation area. The joint boxes shall be grounded as per COMPANY Standards. 1 2 3 NO. 2. At the substation Gantry structure, the joint boxes shall be installed at a height of 3 meters above ground level. A liquid tight PVC coated flexible metal conduit (25mm Ø) shall be installed between the joint box cable entry and the 50mm Ø PVC coated steel conduit. The conduit shall be sealed at both ends. REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF OPGW-U/G NMFOC (4 way) Use “weather tight connectors” connecting the flexible metal conduit with the optical fiber joint box and with the galvanized steel pipe (GSP). Refer to drawing number KT-810949 for details of conduit mounting details at steel monopoles. Refer to drawing number KT-810952 for details of conduit mounting details at latticed steel take-off structure APPROVED TESAD-WOA 3. OPGW-SS NMFOC (4 way) Optical fiber cable joint boxes shall be installed on the transmission line structures, as required, at a height of 5 meters above the ground level outside the substation area. The joint boxes shall be grounded as per COMPANY Standards. CERTIFIED BY: MRR DATE: 22-Feb-21 4. SS NFOC – U/G NMFOC (4 way) At the substation Gantry structure, the joint boxes shall be installed at a height of 3 meters above ground level. A liquid tight PVC coated flexible metal conduit (25mm Ø) shall be installed between the joint box cable entry and the 50mm Ø PVC coated steel conduit. The conduit shall be sealed at both ends. Use “weather tight connectors” connecting the flexible metal conduit with the optical fiber joint box and with the galvanized steel pipe (GSP). THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED 5. SS NFOC – SS NFOC (4 way) Optical fiber cable joint boxes shall be installed on the transmission line structures, as required, at a height of 5 meters above the ground level outside the substation area. The joint boxes shall be grounded as per COMPANY Standards. ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 13 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء B. Fiber Optics Splicing Requirements DESCRIPTION All splicing shall be of fusion type using splicing machine with built-in estimated splice loss measurement and recording (hard copy print) capabilities. All splicing shall be done by qualified and experienced Optical Fiber Cable Splicers. The qualification and experience certificates of the Optical Cable Splicers shall be submitted to the COMPANY for review and approval. 1 2 3 NO. Optical attenuation of the Fiber splices, estimated by the Fusion Splicing Machine, shall not exceed 0.05dB per splice. REVISIONS DRAWN BY The splice loss shall be measured by OTDR from both ends. Optical Splice Loss measured from any one direction shall not exceed 0.15dB per splice. Average Splice loss shall be within 0.05dB per splice. RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED TESAD-WOA All splicing activities shall be witnessed by COMPANY REPRESENTATIVE. Where COMPANY REPRESENTATIVE are not available to directly witness CONTRACTOR’s splicing activity, CONTRTACTOR shall record the video output of the optical Fiber fusion splicing machine onto VHS videotape in a video format suitable for playback on COMPANY videotape equipment, and then submit the Videotape, along with the Video Viewing Guide to the COMPANY inspector responsible for witnessing the Optical Fiber Cable splicing. **** END OF SECTION III **** CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 14 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء 4.01 SECTION IV- TESTING OF FIBER OPTIC CABLES A. Factory Test of Fiber Optic Cables REVISIONS DRAWN BY 1. COMPANY or its designated REPRESENTATIVES may witness any or all factory test performed. 2. A minimum of one (1) month notice shall be given to the COMPANY, by the CONTRACTOR, indicating their readiness to start the factory tests. 3. CONTRACTOR shall include, as a minimum, all the tests as specified in the COMPANY Materials Standard Specifications 10-TMSS-04 and 48-TMSS-02. 4. All fiber optic cables are required to be subjected to factory tests as per following procedure: 1 2 3 NO. DESCRIPTION All optical fiber cables are required to be subjected to factory tests as per the following procedure: RAAFAT DATE 22/02/2021 CHK’D BY AMF a. All materials satisfy the requirements of this specification and all further requirements to guarantee a complete working system. b. All materials meet the performance requirements under the local ambient conditions given in this specification. APPROVED TESAD-WOA 5. All test results shall be recorded and signed by the CONTRACTOR’s Test and Quality Assurance personnel. Any deficiency shall be corrected by the CONTRACTOR, and the complete set of tests shall be repeated. 6. All test reports for Routine Factory Tests performed by the CONTARCTOR’s Test and Quality Assurance Personnel shall be reviewed by an Independent (Third Party) Inspection Agency. Also, as a minimum, the following routine tests for completed Optical Fiber Cable shall be witnessed by the Independent Inspection Agency Inspector (approved by the COMPANY): CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED 7. a. Optical Attenuation Test (at 1310nm and 1550nm) – 100 percent of cable length supplied. b. Fiber Point Defects Test (at 1310nm and 1550nm) – 100 percent of cable length supplied. c. Chromatic Dispersion Test – 10 percent of cable length supplied (cable length chosen at random by Independent (Third Party) Inspection Agency Inspector). On the routine test sheets, which have been reviewed and/or witnessed by the Independent Inspection Agency, the following information shall be included on each test sheet: ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 15 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA Name of Independent Inspection Agency reviewing/witnessing routine tests. b. Name and Official Stamp of the Independent (Third Party) Inspection Agency. c. Name and signature of the inspector reviewing/witnessing the routine test results. d. Date of the witnessing/reviewing of the Routine Tests. e. For tests witnessed by the Independent (Third Party) Inspector, the words “Witnessed By (Name of Inspector)” for each test witnessed. For Tests Results/Data reviewed by the Independent (Third Party) Inspector, the words “Reviewed By (Name of Inspector)” for each test results reviewed. 1 2 3 NO. DESCRIPTION CHK’D الكهرباء a. REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED 7. Upon successful completion of all tests, and COMPANY review and acceptance of the test results, the CONTRACTOR shall export pack all the cable for shipment. 8. Four (4) copies of the complete test results with all the test data sheets shall be submitted to the COMPANY. All test data shall be retained by the CONTRACTOR throughout the warranty period. TESAD-WOA B. Field Test and Acceptance Test of Fiber Optic Cables 1. The CONTRACTOR shall perform the optical tests using 1300nm/1550nm Optical Time Domain Reflectometer (OTDR) and Optical Light Source and Power Meter to measure and document the optical attenuation at 1300nm and 1550nm wavelengths. All tests shall be witnessed by the COMPANY REPRESENTATIVES. 2. The Test shall confirm that all materials meet the performance requirements under the local ambient conditions given in this specification. 3. Calibration certificates for all test equipment shall be submitted to the COMPANY for review and acceptance. 4. Optical attenuation testing shall be performed on all fibers of all cable lengths at three (3) stages of installation and in accordance with COMPANY Construction Standard . CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED a. With the cable on the drums on-site prior to installation (Pre-Installation Test). b. With each cable length in its final condition with all clamps and other accessories attached (Post-Installation Test). ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 16 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء After completion of all optical splicing and mounting of all joint housings in their final positions (Optical Section End-to- End Test). If during any of the three (3) test stages, the test results for any fiber do not comply with the COMPANY requirements or the approved factory and field test results, the CONTRACTOR shall replace the relevant drum of the cable at no additional cost to the COMPANY and without affecting the WORK schedule. DESCRIPTION c. The CONTRACTOR shall complete all mechanical WORKS, preelectrical/communication test and pre-final documentation consisting of marked-up construction drawings, pre-commissioning test results, system and equipment manuals before inviting COMPANY REPRESENTATIVES for commissioning tests and inspection. 1 2 3 NO. C. Preparation for Acceptance Test and Inspection REVISIONS D. Scheduling Commissioning Tests and Inspection DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED 1. All testing and commissioning activities shall be coordinated with and witnessed by the COMPANY REPRESENTATIVE. 2. CONTRACTOR's invitation to the COMPANY to witness commissioning tests and inspection shall be made fourteen (14) days in advance accompanied by: TESAD-WOA a. b. c. Marked-up Construction Drawings Pre-Commissioning Test Results System/equipment Manuals E. Test and Inspection Checklist CONTRACTOR shall obtain from the COMPANY a communication checklist of acceptance tests and inspection covering documentation, mechanical, and inventory and tests requirements for PROJECT acceptance. (For Fiber Optic Cable, the COMPANY's "Fiber Optic Cable Acceptance Test and Inspection Checklist, FOC-TIC-001" form shall be used). CERTIFIED BY: MRR DATE: 22-Feb-21 F. Calibration of Test Equipment All test equipment to be used in the acceptance tests shall be calibrated to standards traceable to the National Bureau of Standards. Calibration certificates shall be submitted to the COMPANY for review and acceptance. G. Correction of Discrepancies THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED A re-inspection and re-test to be witnessed by the COMPANY REPRESENTATIVE is required to clear the CONTRACTOR of any discrepancy found during the commissioning test and inspection. A re-test and re-inspection of related parameters shall also be conducted to ensure that these are not affected by aforementioned discrepancy. ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 17 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء H. Order of Acceptance Test and Inspection Related Activities REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF 2. Validation of marked-up construction drawing (done throughout the test and inspection process). 3. Inventory and mechanical inspection of installed equipment. 4. Verification of validity of test equipment to be used in the test. 5. Performance and/or functional tests after stage 4 is complied with and any service affecting discrepancy found in stage 3 above is corrected. Unavailability of documents essential in the safe energization, operation and trouble shooting of the installation is considered service-affecting discrepancy. 6. Signing of Mechanical Completion Certificates (MCC) after all stated stages are complied with and accepted. 7. Trial period of one (1) month after clearing all outstanding discrepancies and acceptance of the final test results. 8. Signing of Performance Acceptance Certificates (PAC) after successful completion of the trial period. 1 2 3 NO. DESCRIPTION Various stages of acceptance test and inspection shall be performed according to the following order: 1. Scheduling of test and inspection by the CONTRACTOR, the date to be agreed upon by both COMPANY and CONTRACTOR and submission by the CONTRACTOR and approval by the COMPANY of documents mentioned above. APPROVED TESAD-WOA AS-Built Drawing: A. As the Project nears completion, the CONTRACTOR in sufficient details recording all CERTIFIED BY: MRR DATE: 22-Feb-21 Changes/Modifications shall prepare “As-Built” drawings and locations of underground substructure or any sub-surface utilities and cut mark identified and located in the field during construction of the Project to present an accurate record for COMPANY. B. All existing drawings affected by this Project shall be revised and corresponding existing drawing control sheets shall be updated by the CONTRACTOR. The existing drawing control sheet shall be updated and automated in XLS format. If the existing substation drawings do not have drawing control sheet, then the CONTRACTOR shall THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED prepare new Drawing Control Sheet, which shall include the new and existing drawings. The CONTRACTOR shall coordinate with COMPANY for the list of the ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 18 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء existing drawings. All Drawing Control Sheets, listing all proposed and existing drawings shall also be submitted in the Base Design submittal. C. All revisions shall reflect field modifications to engineering flow diagrams, electrical DESCRIPTION one line diagrams, electrical schematic connection and interconnection wiring diagram; instrument hook-ups wiring diagrams, terminal connections, dimensioned equipment layouts, all underground installations and other WORK and facilities not normally visible. The CONTRACTOR shall provide "As-Built" drawings showing all CONTRACTOR. If the CONTRACTOR was given hard copy or tiff image file to 1 2 3 NO. field modifications to drawing and diagrams prepared by the Vendors and SubREVISIONS DRAWN BY existing "as-built drawings, then it is the responsibility of the CONTRACTOR to request COMPANY at least two (2) months before the Technical completion for the RAAFAT DATE 22/02/2021 existing "As-Built"drawings and redraw them in Microstation V8 or above version CHK’D BY AMF software in accordance with SEEDS-I, Rev.01. The Updating of existing "as-built" drawings will not be accepted. APPROVED TESAD-WOA D. As part of " As-Built " drawings submission, the CONTRACTOR shall also provide COMPANY three (3) sets of field marked–up drawings reflecting the "As-Built" condition of the particular segment of WORK completed by the COTNRACTOR and distributed, as given below, prior to energization: One (1) set shall be retained by COMPANY at the substation. One (1) set shall be submitted to COMPANY. One (1) set shall be used for "as-built" by the CONTRACTOR'S Engineering and Design Consultants, which shall be included in the final submittal. CERTIFIED BY: MRR DATE: 22-Feb-21 E. One (1) sample of original (digital Microstation *.DGN format and Mylar) and five (5) check prints from different "As-Built" engineering drawings shall be submitted to COMPANY to verify the quality of digital Microstation *.DGN format and Mylar and whether the correct drafting procedure is adopted, one (1) month before initial submission of "As-Built" drawings. Before submitting the final as-built drawings, one sample drawing shall be submitted and got approved. F. Five (5) copies of the as-built documents shall be submitted to COMPANY for THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED reviewas to adequacy, completeness, legibility and conforming to drafting standards. If returned, the CONTRACTOR shall make corrections, provide additional data and improve the quality as instructed prior to re-submittal and COMPANY acceptance. The ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 19 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء revised "As-Built" drawings shall be re-submitted within four (4) weeks after commissioning. Five (5) sets of final "As-Built" drawings, one (1) set of good quality "As-Built Mylar's and one (1) set of as-built digital Microstation *.DGN format drawings DESCRIPTION in CD shall be submitted to COMPANY for records. G. In addition to the "As-Built” drawings, the CONTRACTOR shall submit all documents related to th Project, Such as but not be limited to the following: 1. Base design manuals 3. Cable splicing details 1 2 3 NO. 2. As-built installation manuals REVISIONS DRAWN BY 4. Test/commissioning data 5. Material test results RAAFAT DATE 22/02/2021 CHK’D BY AMF H. Each drawing should be provided and protected by a plastic pouch including the drawing control sheet/index. All drawings will be properly photocopied to ensure readability of all pages. All drawings will be submitted in Binder’s with specifically APPROVED marked as e.g. Volume I and Volume II on both the folder cover and its spine. TESAD-WOA I. Showing all Road Name, Street Name & Landmark for the FOC route. J. Showing coordinates in UTM WGS 84 format of all proposed and existing Communication Handhole/Manhole, HDD/Micro Trench and Joint Box installed inbetween and inside substations along the FOC route, MH/HH elevation to be considered. K. In addition to the " Colored As-Built” drawings, the CONTRACTOR shall submit approved FOC duct bank layout for both the linked substations CERTIFIED BY: MRR DATE: 22-Feb-21 L. Showing fiber Color Code, Circuit details, Fiber Type, Circuit No. In the case of joining existing fiber with a new one which has different color coding, different number of cores, different ITUT-T types, and/or different manufacturer, this information shall be highlighted and indicated clearly in the left and right side of joint box/ joint closure drawing. M. Showing Manhole/Handhole cross section and fold-out details with used and spare ducts & subducts number assignments. THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED N. FOC route length table to be updated in As-built with Section length between Manhole/Handhole, loop inside the HH & Accumulative length using STN: 0km+0m notation based on segment length of duct bank/trench ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 20 OF 21 REV. 01 الشركة الوطنية لنقل الكهرباء National Grid SA CHK’D الكهرباء O. Clearly indicated HDD/Micro Trench with a particular color & the exact length. P. Joint closure to be marked and numbered on the route as well per the FOC route length Table. If the route drawing is combining more than one fiber link, clearly DESCRIPTION indicate which link the joint closure belong to. Q. Cross section of trench (Direct-buried, HDD/Micro Trench) should be updated in the As-built with used and spare ducts & subducts number assignments. 1 2 3 NO. R. As built to be provided for the complete route, including the existing route "if there is". *** END OF SECTION VI & SOW/TS *** REVISIONS DRAWN BY RAAFAT DATE 22/02/2021 CHK’D BY AMF APPROVED TESAD-WOA CERTIFIED BY: MRR DATE: 22-Feb-21 THIS DRAWING IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED MATERIALS UNTIL CERTIFIED AND DATED ATTACHMENT JOB ORDER NO. PLANT NO. INDEX DOCUMENT NO. CONSTRUCTION OF Madinah ISTP 110/13.8KV S/S NG1168 A PTS-20WC1033 PAGE NO. 21 OF 21 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء DESCRIPTION CHK’D APP’D NATIONAL GRID SA 1 2 3 NO. APPENDIX - XXX REVISIONS DEPT.: E&DD PREP. BY MS / MA CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS AND MATERIALS SPECIFICATIONS DATE: FOR APPROVED UNDERGROUND CABLES BY: JAH DATE: CERTIFIED ( CIVIL APPENDIX ) BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 1 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA TABLE OF CONTENTS DESCRIPTION SECTION I Page 1 2 3 NO. 1.1 1.2 II REVISIONS DEPT.: 4-6 INTRODUCTION 4 GENERAL DEFINITION OF TERMS 4 SCOPE OF WORK 2.1 7-8 7 CIVIL WORK E&DD III PREP. BY MS / MA BASIC REQUIREMENTS & GUIDELINES 9-12 9 3.1 GENERAL 3.2 PREPARATION OF CIVIL AND STRUCTURAL DESIGN CALCULATIONS DATE: IV 9 13-22 TECHNICAL REQUIREMENTS 4.1 GENERAL 13 4.2 CONCRETE ENCASED DUCTBANKS 13 4.3 DIRECT BURIED CABLES 13 4.4 DIRECT BURIED CABLE DUCTS/CONDUITS 13 4.5 GEOTECHNICAL INVESTIGATION REPORT & SOIL RESISTIVITY MEASUREMENTS O/H – U/G TRANSITION AREA (IF REQUIRED) 13 APPROVED BY: JAH DATE: 4.6 BY: 14 CERTIFIED 4.7 COMPANY PROVIDED DESIGN OF TRANSITION/TAKEOFF STRUCTURE (IF REQUIRED) 15 AAS 4.8 16 4.9 NEW DESIGN OF TRANSITION/TAKE-OFF STRUCTURE (IF REQUIRED) FOUNDATIONS FOR STEEL STRUCTURES 4.10 CAST IN PLACE CONCRETE 16 4.11 PRECAST CONCRETE 16 4.12 CONCRETE PROTECTION FOR REINFORCEMENT 16 4.13 EXCAVATION AND BACKFILL 17 4.14 SLOPE PROTECTION 17 DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 4.15 4.16 ASPHALT ACCESS ROAD TO O/H –U/G TRANSITION AREA (IF REQUIRED) GROUNDING OF CONCRETE REINFORCEMENT PLANT NO. JOB ORDER NO. 16 CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS 17 17 PAGE NO. 2 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D TABLE OF CONTENTS SECTION Page 4.18 REMOVAL OF SAND DUNES & SAND STABILIZATION (IF REQUIRED) COMMUNICATION HANDHOLE 4.19 ABOVE GRADE LINK BOX 18 4.20 BELOW GRADE LINK BOX 18 4.21 TEMPORARY SUPPORT 18 4.22 DEMOLITION WORK 19 4.23 TRENCH REINSTATEMENT TO SUB-BASE 20 4.24 REINSTATEMENT OF PAVEMENT SUB-BASE AND BASE COURSE ASPHALT REINSTATEMENT 20 21 4.27 CABLE TRENCHES INSIDE SUBSTATION/TRANSITION AREA FENCE AND GATE 4.28 PRECAST CONCRETE BOUNDARY WALL & GATE 22 4.29 PROTECTIVE CRASH BARRIERS WITH CHAIN LINK 22 1 2 3 NO. DESCRIPTION 4.17 REVISIONS DEPT.: E&DD 4.25 PREP. BY MS / MA 4.26 DATE: V APPROVED BY: JAH DATE: 17 18 21 MATERIALS SPECIFICATIONS 21 23-27 5.1 CONCRETE 23 5.2 CONCRETE BONDING AGENT 23 5.3 REPAIR MORTARS 23 5.4 CONCRETE FORMWORK 24 5.5 TIES AND ANCHORS 24 5.6 CONCRETE INSPECTION AND TESTING 24 5.7 CURING OF CONCRETE 25 5.8 ASPHALT CONCRETE PAVING 25 5.9 REINFORCING STEEL 25 5.10 EARTHWORKS 25 5.11 CABLE TRENCH 25 5.12 STRUCTURAL STEEL 26 5.13 CEMENT AND SAND SCREED 26 5.14 WATERPROOFING MEMBRANE 26 5.15 COAL TAR EPOXY 27 5.16 WATERSTOP 27 5.17 PVC CONDUITS/FITTINGS, SUB-DUCTS AND RSGC 27 CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 3 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D TABLE OF CONTENTS SECTION Page CABLE TRAYS 27 1 2 3 NO. DESCRIPTION 5.18 REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 4 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D SECTION I - INTRODUCTION 1.1 GENERAL DESCRIPTION This Appendix describes the Civil and Structural Scope of Work, Design Criteria, Technical Requirements and Materials Specifications pertaining to civil and structural works for underground cables. 1 2 3 NO. All requirements of this Appendix shall be integrated with that of the Main SOW/TS so as to consider this document as an integral part of the Main SOW/TS and read in conjunction with it. A. Items neither specifically covered herein nor in the COMPANY standards shall conform to the latest editions of referred Industry Codes and Standards. B. It shall be the CONTRACTOR's/Manufacturer's/Vendor's responsibility to be and become knowledgeable of the requirements of the latest Industry Codes and Standards listed herein and bring to the COMPANY any latest revisions/amendments of the referred Industry Codes and Standards which have an impact on the technical requirements. C. The technical requirements & materials specifications shall fully conform to or exceed the minimum requirements/specifications stipulated herein. D. The specific requirements of project under consideration are covered in the base map drawings (U/G cables route, sections and details), drawings and rightof-way approval conditions/correspondences. The CIVIL APPENDIX sections which are technically applicable for the project under consideration shall be considered by the CONTRACTOR. E. The COMPANY’s interpretation of the project’s specific requirements and this Appendix shall be final and binding to the CONTRACTOR/Manufacturer/Vendor. REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: APPROVED BY: JAH DATE: 1.2 DEFINITION OF TERMS CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Terms, abbreviations and/or expressions frequently used, herein and after, shall have the following meaning/definition: Term/Abbreviation or Expression COMPANY or NG SEC CONTRACT Bid (or Bid Proposal) Meaning / Definition National Grid SA (Subsidiary of Saudi Electricity Company) Saudi Electricity Company Documentation of the terms and conditions that the parties mutually understand and intend to use to govern their respective rights, duties and obligations for performance of the work Commercial Proposal & Technical Proposal, if any, of a bidder for a particular contract, change order or contract amendment PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 5 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA 1 2 3 NO. DESCRIPTION Term/Abbreviation or Expression CONTRACTOR REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED HV MV LV LV DC or LVDC COMPANY REPRESENTATIVE DCS U/G O/H O/H T/L T/L, T/Line S/S F/O or FOC NFOC FOTE GIS CAD SOW/TS or PTS BSP LSTK OPGW OGW ROW VT CVT / CCVT CT IFC IEC IEEE sq.mm 3Ø / 1Ø ASTM AEIC SASO TCS TES TSD TMSS SDMS SF6 UTS XLPE SVL HDPE PVC Meaning / Definition Contractor, responsible for the execution of the WORK as described in this PTS. 110 / 115 / 132 kV (145kV Voltage Class) 33kV or 34.5kV or 13.8kV 400/230V 125VDC Personnel Authorized by COMPANY Drawing Control Sheet Underground Overhead Overhead Transmission Line Transmission Line Substation Fiber Optic Cable Non-Metallic Fiber Optic Cable Fiber Optic Terminal Equipment Gas Insulated Switchgear Computer Aided Design Scope of WORK and Technical Specifications Bulk Supply Point Lump Sum Turnkey Composite Overhead Optical Fiber Ground Wire Conventional Overhead Ground Wire Right-Of-Way Voltage Transformer Capacitive Voltage Transformer/Coupling Capacitor Voltage Transformer Current Transformer Issued for Construction International Electrotechnical Commission Institute of Electrical and Electronics Engineers Square millimeters or Square mm or mm2 Three phases / One phase American Society for Testing and Materials Association of Edison Illumination Companies Saudi Arabian Standards Organization COMPANY Transmission Construction Standards COMPANY Transmission Engineering Standards COMPANY Transmission Standard Drawings COMPANY Transmission Materials Standard Specifications SEC Distribution Materials Specifications Sulfur Hexafluoride Ultimate Tensile Strength Cross-Linked Polyethylene Sheath Voltage Limiter High Density Polyethylene Polyvinyl Chloride PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 6 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA DESCRIPTION Term/Abbreviation or Expression ACI AISC AASHTO American Concrete Institute American Institute of Steel Construction American Association of State Highway &Transportation Officials American Society of Civil Engineers Rigid Steel Galvanized Conduits Ministry of Transportation Saudi Telecommunication Company 1 2 3 NO. ASCE RSGC MOT STC Meaning / Definition REVISIONS DEPT.: E&DD PREP. BY MS / MA *** END OF SECTION I *** DATE: APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 7 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D SECTION II - SCOPE OF WORK DESCRIPTION 2.1. CIVIL WORK The civil WORK involved in this PROJECT shall include, but not necessarily limited to the following: Construction of cable trenches for direct buried cable installation including but not limited to excavation, laying of ducts & cables, backfilling, compaction and reinstatement of surfaces (unpaved and asphalt paved). Re-asphalting the roads shall be as per the requirements of the right of way approval conditions given in ROW Appendix or provided by concerned agencies. As a minimum requirement, the CONTRACTOR shall reconstruct all asphalt layers (including base and sub-base) 3.5 meters wide by using mechanical asphalting machine. C. Contractor shall clear and remove debries/dumped material from the approved right-of-way site before laying down the cables. The removed material shall be disposed to approved dumping site. D. Construct concrete encased ductbanks at crossings as shown in the base map drawing(s). CONTRACTOR shall reinstate the existing surfaces (unpaved and asphalt paved) and utilities to their original condition or better as affected by the above WORK. Ductbanks shall be provided with wing walls at the end of the run. Spare conduits shall also be provided as shown in the base map drawing(s). E. Provide all required communication civil WORK along the proposed route(s). Communication civil WORK shall include, but not limited to, the provision and installation of Handholes and Handhole accessories, as well as concrete encased ductbanks, conduits/ducts and sub-ducts required for the installation of underground Fiber Optic cables. CERTIFIED F. Design and installation of horizontal directional drilling, as required at locations shown in the base map drawing(s). AAS G. Design and installation of thrust boring, as required at locations shown in the base map drawing(s). H. All excavations shall be restored to original condition. Pavement, plantation, trees, sidewalk, existing street lighting poles, signboard, billboard, traffic lights, curbs removed or damaged during the construction, underground utilities etc. shall be restored with respect to the technical requirements and material & specifications of their owner as well as to the satisfaction of COMPANY REPRESENTATIVE. I. Perform geotechnical investigations including borehole tests, soil electrical and thermal resistivity tests and CBR tests along the U/G cables route. 3 1 B. 2 Complete survey and investigation for the whole route(s) of the proposed underground cable circuit(s). All utilities found, existing and future roads shall be surveyed with complete details and reflected on the design drawings. For the proposed underground cables route, refer to the attached base map drawing(s). NO. A. REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: APPROVED BY: JAH DATE: BY: DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 8 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء J. Design and construction of O/H - U/G transition area (including take-off structure, steel support structures, ductbanks, trenches, boundary wall/fence, asphalt access road etc.) as required in the base map drawing(s). K. Design, fabrication and installation of cable trays and other steel support structures, as required in the base map drawing(s). L. CONTRACTOR shall co-ordinate with the authorities for the latest planning of roads and utilities along the proposed cable route(s) and the same shall be reflected on the design drawings during the design and/or execution of the PROJECT. M. ROW approvals correspondences shall be obtained from COMPANY proponent for reference and use before starting any construction activity. WORK within the jurisdiction of Municipality shall be carried out under the supervision of Municipality & COMPANY REPRESENTATIVES. CONTRACTOR shall satisfy all conditions listed in the ROW approvals and all WORK shall be coordinated with Municipality for their full satisfaction. N. CONTRACTOR shall install the signboard (Project Signboard with Electronic Counter) within thirty days (30) from the project start date near Source Substation. The Electronic Counter shall show the number of days remaining for the project completion. Refer to the attached drawing for details. After the completion of the project, signboard with foundation shall be removed. O. WORKS at Source/Destination Substation: 1. Provide openings in the walls of the cable basement/cable entry room wall for sleeves/ducts for routing power cables. The openings shall be sealed properly to avoid penetration of water through these wall openings. 2. The damaged existing floor shall be coated with epoxy floor hardener. 3. Fabrication of steel support structures for any additional panels. 4. Provide cable trays for routing power, & LV/control cables. 5. Design and construct cable trenches covered with precast concrete covers to route power cables with all conduits and its support, pipe sleeves, cable trays, and all necessary accessories. 6. Design and construct direct buried PVC conduits with manholes (if required) to route the 110 / 115 / 132 kV cables with all necessary accessories from 110 / 115 / 132 kV GIS to 1.5m outside the boundary wall with reinforced concrete wing walls. Each duct shall contain pull wire rope and both ends shall be capped or plugged with duct sealing units. 7. Design and construction of reinforced concrete duct banks to route LV & control cables with all accessories. 8. All affected items due to the installation of new equipment shall be restored/reinstated to the satisfaction of COMPANY. 1 2 3 NO. DESCRIPTION CHK’D APP’D NATIONAL GRID SA REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED *** END OF SECTION II *** PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 9 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D SECTION III – BASIC REQUIREMENTS & GUIDELINES 3.1 GENERAL DESCRIPTION This section covers mandatory requirements governing the preparation of civil and structural calculations for the design of all steel and concrete structures. 3.2 REVISIONS DEPT.: E&DD PREP. BY MS / MA Scope The criteria and general design guidelines outlined below shall be adopted as applicable to the basic design of the structures, and shall also serve as the basis in the development of detailed design by the CONTRACTOR subject to necessary adjustments and implementation particularly in consideration to geological conditions of the site. 1 2 3 NO. A. PREPARATION OF CIVIL AND STRUCTURAL DESIGN CALCULATIONS B. DATE: Conflicts and Deviations Any conflict between this SOW and other applicable COMPANY Engineering Standards, Material Specifications, Standard Drawings or Industry Standards, codes and norms shall be resolved in writing by the COMPANY. C. Purpose of Calculations The purpose of calculations is as follows: APPROVED BY: 1. To enable the designer to arrive at designs which are safe, feasible and economical. JAH 2. To provide a record for future reference. DATE: 3. To satisfy code and/or COMPANY requirements as to the adequacy of design. 4. To facilitate determination of the effects of possible future modifications. CERTIFIED D. BY: Units AAS All calculations shall be done using SI units. DATE: E. Symbols Symbols used for steel and concrete structures design shall have the connotation as in the AISC Manual of Steel Constructions and ACI Manual of Concrete Practice respectively. Other symbols shall conform to the corresponding International Codes and Standards that are referenced in the applicable COMPANY Standard. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED The connotation of all symbols, in general, used throughout the calculations shall be stated at the beginning of calculations. The connotations of symbols used only locally shall be stated immediately before or after the equations in which they are used. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 10 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA F. Equations All equations, graphs, nomograms etc. used in the calculations shall be: DESCRIPTION 1. Derived in the calculations, or 2. Referred to in the relevant standard, giving clause number, or 3. If taken from a text book, accompanied by a copy of the pertinent page(s). 1 2 3 NO. 4. Commonly used and easily recognized equations such as (PL), (WL2)/8, etc. need not be derived or have references provided. REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: G. Assumptions Assumptions on which calculations are based shall be listed in an orderly manner. CONTRACTOR shall clearly spell out the analysis/design methodology/philosophy adopted in the design of structures. The decision to adopt a particular analysis/design method shall solely be at the discretion of COMPANY. H. Parameters The values of all parameters shall be stated at the beginning of calculations. Justification need not be given for commonly accepted values e.g. Young's modulus, Poisson's ratios, coefficients of expansion, etc. However, all other parameters shall be justified either by quoting a source (e.g. soil report or study), or by brief reasoning or reference to a standard or code. This in particular applies to the following: 1. Temperature differentials. 2. Allowable ground bearing pressures, settlements and differential settlements. 3. Wind pressure calculation based on the appropriate basic wind speed, exposure factor, height, shape, gust and importance factor. APPROVED BY: JAH DATE: I. CERTIFIED BY: AAS DATE: General Presentation The presentation of calculations shall be in accordance with the following procedures and requirements. 1. The heading shall provide the following information: a. Name of the originator of the calculations and the name of the checker. b. The title which shall clearly describe the contents of the calculations. c. The date these calculations were made. 2. Table of Contents and list of all codes and references used. 3. All calculations shall be initialed as checked, before being sent to the COMPANY. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 4. Calculations shall have sufficient number of sub-headings to indicate clearly what is being calculated or designed. Both sub-headings and final results shall be underlined for easy locations. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 11 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 5. Sufficient explanation shall be given so that calculation methods are easily comprehensible. For this reason, simple clear sketches shall be liberally used. Calculations not adequately described will not be accepted by the COMPANY. DESCRIPTION 6. Load calculations and load diagrams that tally with design parameters shall be included in design calculation documents. 7. Calculations shall be in English language throughout. 1 2 3 NO. 8. The cover sheet of each calculation package shall be assigned a COMPANY drawing number to identify the calculations for a particular Job Order, and for inclusion in COMPANY permanent records. Individual calculation sheets following the cover sheet shall be consecutively numbered (1, 2, 3, etc.). 9. Calculation packages shall be limited to pertinent information. Voided calculation sheets shall be removed if these sheets do not contain useful information. REVISIONS DEPT.: E&DD PREP. BY MS / MA 10. All calculations must be given a standard numbers and format as per SEEDS-II and the same shall be included in the drawing control sheet for future reference. 11. Design calculations shall also be submitted in Abode Portable Document Format (PDF). These shall be submitted in a CD during the definitive design stage to aid in the review. DATE: J. Computer Calculations Computer calculations shall be in accordance with the following guidelines: APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 1. All computer models shall be accompanied by the corresponding input and output files/data showing the structural shape, integrity of structure, loads applied and the joints/members layout etc. Data provided as computer input shall be clearly distinguished from those computed in the program. The first sheet of each computer run shall be signed by the engineer responsible for the structural design. A program description (user's guide) shall be available upon request and contain the information necessary to determine the nature and extent of the analysis, verify the input data, interpret the results with the recommendations, COMPANY minimum requirements and determined whether the computations comply with these recommendations. 2. A computer diskette (CD) containing a copy of the input and output files shall be furnished to COMPANY for all computer models to aid in the review. 3. Computer programs such as STAAD.Pro, SAP2000, Structure Point Packages, MathCAD, PLS-TOWER and PLS-POLE are recognized as acceptable programs. Use of any other software/computer program would require prior permission from NG. CONTRACTOR shall use only recognized, reputed and renowned international computer programs. However, other commercial and propriety software may be acceptable provided that the suitability and reliability of the results have been verified and that this verification is furnished upon request. It is solely up to the COMPANY REPRESENTATIVE to accept such programs. MS Excel Spreadsheets specially designed for specific design calculations shall also be submitted. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 12 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA DESCRIPTION CHK’D 4. A summary of analysis results shall be provided that are extracted from the computer output. This summary should clearly state the achieved results (maximum interaction ratios, deflection ratios, justification of the output with requirements etc.). 1 2 3 NO. *** END OF SECTION III *** REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 13 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D SECTION IV - TECHNICAL REQUIREMENTS 4.1 GENERAL DESCRIPTION This section broadly outlines the technical requirements for the satisfactory and complete design & construction of the PROJECT. The technical requirements outlined herein shall be read in conjunction with the attached PROJECT drawings, COMPANY standard drawings, COMPANY Engineering Standards, COMPANY Construction Standards and COMPANY Material Standards & the associated international Standards and Codes. REVISIONS DEPT.: E&DD PREP. BY MS / MA A. Concrete encased ductbanks shall be constructed in accordance with base map drawing(s) and COMPANY Standard Drawing TA-800062 (except that the clearance between ducts shall be minimum 500mm) and drawings included in this SOW/TS at road crossings, factory and business entrances, and other areas where vehicles cross traffic are heavy. Also, where car wash and/or gasoline stations exist near the cables route, concrete encased ductbanks shall be constructed by the CONTRACTOR along the cables route corresponding to such stations.. All cable duct installations shall follow the requirements of COMPANY Construction Standard TCS-P-104.03. B. Design and construction of concrete encased duct banks shall be in accordance to ACI 318-(latest revision). Duct banks shall be designed against AASHTO HS20 loadings. C. Bell ends shall be provided at the exit and at entrance of each duct. The bell end shall be an extension of the plastic duct, therefore, bell end inserts which have a smaller internal diameter than the plastic duct, shall not be used. DATE: APPROVED BY: CONCRETE ENCASED DUCTBANKS 1 2 3 NO. 4.2 JAH 4.3 DATE: Direct buried cables shall be installed according to COMPANY Standards TCS-P104.03 and TES-P-104.05. CERTIFIED BY: AAS 4.4 DIRECT BURIED CABLE DUCTS/CONDUITS Cables ducts/conduits shall be installed according to COMPANY Standards TCS-P104.03 and TES-P-104.05. DATE: 4.5 THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DIRECT BURIED CABLES GEOTECHNICAL MEASUREMENTS INVESTIGATION REPORT SOIL RESISTIVITY A. Prior to any design WORK, the CONTRACTOR shall hire a COMPANY approved Geotechnical Consultant, who shall undertake the geotechnical investigations. B. The Geotechnical Consultant shall carryout borehole and soil thermal resistivity tests along the route(s) of the proposed cables. PLANT NO. JOB ORDER NO. & CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 14 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء REVISIONS DEPT.: C. Sufficient number of soil borings shall be taken so that a soil profile can be drawn with reasonable accuracy to determine the plan and profile of the proposed cables. In case of transition areas, at least one borehole shall be made at the foundation of transition structure. D. Minimum depth of borehole shall be 2B, where B is the width of the cable trench/ductbank, and in no case shall be less than 5.0 meters. For transition structure, depth of borehole shall be at least 10.0m. E. When sabkhah soils are encountered at the site or in case the ground water table is very high, CONTRACTOR shall propose a berm/embankment type ductbank so as to keep cable elevation above the water table. In case, the elevated water table is localized to a smaller portion of the cable route, dewatering can also be proposed. F. For berm/embankment type ductbank, Geotechnical consultant shall also propose protective layers for erosion protection (rip-rap, loosely bound gravel etc.) Stable slopes shall also be proposed on both sides of the berm as per TCS-Q-113.02. 1 2 3 NO. DESCRIPTION CHK’D APP’D NATIONAL GRID SA E&DD PREP. BY MS / MA DATE: G. Samples for soil thermal resistivity measurements shall at least be taken at every 500m along the cable route (Refer to Main SOW). Samples shall also be taken at or near each Horizontal Directional Drilling or Thrust Boring locations (if applicable). The location of these samples along the route shall be subject to COMPANY review and approval. H. Soil thermal resistivity shall be determined for (1.0% - 2.0%) moisture content on the samples. I. For transition areas (if required), soil electrical resistivity tests shall also be carried out for the design of grounding of electrical equipment. The four-point Wenner method shall be used for electrical resistivity test. A minimum of three test locations, in the shape of a triangle, shall be selected for accuracy. APPROVED BY: JAH 4.6 DATE: O/H – U/G TRANSITION AREA (IF REQUIRED) CONTRACTOR shall design and construct the O/H - U/G transition area based on, but not limited to, the following scope of work: CERTIFIED BY: AAS A. Site Clearing, Rough Grading, Excavation, Backfilling and final grading. B. Asphalt paving of the transition area: The asphalt crown of transition area shall be 1.00 meter higher than the closest asphalt road. Extend the asphalt paving up to 1.0 meter outside from the proposed fence of the transition area. C. Installation of type (I) fence and one (1) - 3.0 meter wide drive gate. Refer to COMPANY Standards 70-TMSS-02 and TA-800113. Gate and perimeter fence shall be grounded as per the COMPANY Standard TES-P-119.10. DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED OR Design and construction of precast concrete boundary wall around transition including retaining wall and foundations, as per COMPANY standard drawing TA-800012 & TD800007. Fabrication and erection of one - (1) drive gate 3.0m wide. Height of the gates shall be kept equal to the height of boundary wall. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 15 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA Danger High Voltage Keep Away and Danger High Voltage Bone and Skull Standard Signs shall be as per drawings TD-800007 and TD-800008. REVISIONS DEPT.: E&DD PREP. BY MS / MA E. Design, fabrication and erection of hot-dip galvanized steel supporting structures for outdoor electrical equipment such as surge arrester, cable sealing ends etc. F. Design and construction of reinforced concrete foundations for take-off structure and the outdoor electrical equipment as per COMPANY Standard TES-P-119.18. Concrete shall be per the requirements of 70-TMSS-03. 1 2 3 NO. DESCRIPTION D. Design, fabrication and erection of steel monopole/gantry take-off structure as required in the Main PTS. DATE: G. Design and construct dedicated reinforced concrete ductbank and handhole for the underground non-metallic fiber optic cable. H. Provide and install two (2)-50 mm diameter rigid steel galvanized conduits from the fiber optic cable joint box on the steel gantry structure up to the communication handhole. The elevation of communication handhole shall be 100 mm above the surrounding asphalt finished grade elevation to preclude the entry of water. All handholes within the transition yard shall be traffic type. I. Design and installation of grounding grid. Grounding grid shall be designed in accordance with the requirement of TES-P-119.10. J. Design and construction of surface water drainage system to drain the surface water away from the proposed Transition Area. Surface water shall be drained outside the boundary wall/fence. 4.7 COMPANY PROVIDED DESIGN OF TRANSITION/TAKE-OFF STRUCTURE (IF REQUIRED) APPROVED BY: JAH Following types of steel take-off transition structures shall be fabricated and constructed in the transition areas as proposed by the COMPANY. DATE: A. Latticed Steel Gantry Structure CERTIFIED 1. The latticed steel gantry structures shall be as per the requirements of Drawing Nos. XT-XXXXXX, XT-XXXXXX and COMPANY Material Standard 20-TMSS-01. BY: AAS 2. CONTRACTOR shall modify the attached outline and fabrication drawings to fulfill the PROJECT requirements. Any such modification shall be submitted to COMPANY for review and approval. DATE: B. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Steel Poles Structure 1. Steel poles take-off structure shall be as per the requirements of XT-XXXXXX & 20-TMSS-01. 2. CONTRACTOR shall modify the attached outline and fabrication drawings to fulfill the project requirements. Any such modification shall be submitted to COMPANY for review and approval. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 16 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA 4.8 NEW DESIGN OF TRANSITION/TAKE-OFF STRUCTURE (IF REQUIRED) DESCRIPTION Following types of steel take-off transition structures shall be designed, fabricated and constructed in the transition areas as proposed by the COMPANY. A. Latticed Steel Gantry Structure 1 2 3 NO. 1. The latticed steel gantry structures shall be designed and fabricated as per the requirements of ASCE 10-97. Reference shall also be made to COMPANY Standard TES-P-122.05-P-I and 20-TMSS-01. The latticed steel gantry structures shall be designed and detailed such that they can be extended on both sides. 2. CONTRACTOR shall provide design calculations, outline configuration and fabrication/assembly drawings for COMPANY review and approval. REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: B. Steel Poles Structure 1. Steel poles take-off structure shall be designed and fabricated as per the requirements of ASCE 48-11. Reference shall also be made to COMPANY Standards TES-P-122.05-P-II and 20-TMSS-02. 2. CONTRACTOR shall provide design calculations, outline configuration and fabrication/assembly drawings for COMPANY review and approval. 4.9 FOUNDATIONS FOR STEEL STRUCTURES APPROVED BY: JAH DATE: Reinforced concrete foundations for cable sealing end, surge arrester and takeoff/transition structure etc. shall be designed and constructed as per COMPANY Standards TES-P-119.18, TES-P-122.06 and TCS-P-122.05. 4.10 CAST IN PLACE CONCRETE The cast-in-place concrete shall conform to TCS-Q-113.03. 4.11 PRECAST CONCRETE CERTIFIED The precast concrete shall conform to TCS-Q-113.04. BY: AAS DATE: 4.12 CONCRETE PROTECTION FOR REINFORCEMENT Concrete cover for all reinforcements at and below ground level shall be 85 ± 10mm. All other concrete cover requirements shall be as per the latest edition of ACI 318, “Building Code Requirements for Structural Concrete.” 4.13 EXCAVATION AND BACKFILL THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Excavation and Backfilling shall conform to the COMPANY Construction Specifications for Earthwork, TCS-Q-113.02. No backfilling shall be performed before the structure has been approved by the COMPANY representative. 4.14 SLOPE PROTECTION PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 17 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA 1 2 3 NO. DESCRIPTION Slope protection shall be as recommended in TCS-Q-113.02. 4.15 ASPHALT ACCESS ROAD TO O/H – U/G TRANSITION AREA (IF REQUIRED) REVISIONS DEPT.: E&DD PREP. BY MS / MA A. CONTRACTOR shall design and construct proposed asphalt access road to the proposed transition area drive gate from the existing asphalt road. B. Design and construction of access road shall conform to TES-P-122.11 and TES-P119.19. C. CONTRACTOR shall provide all necessary road traffic warning signs such as stop, speed limit, caution; slow down, direction etc., speed humps and other informative signs at the intersection of proposed asphalt access road and the existing asphalt road. Speed humps shall be provided at 10 meters from transition area gate and existing asphalt road. D. The access road shall be 4.0m wide with 1.0m wide shoulder on each side. The slope of embankment shall be protected with 50mm thick asphalt. E. Asphalt Concrete pavement works, base and sub-base shall be as per the requirements of TCS-Q- 113.01, TCS-Q-113.02. F. Access road crossing pipeline shall conform to TB-800014. DATE: G. Accelerating/Decelerating roads shall be provided when the asphalt access road is connected to Road/Highway as per the requirement of concerned agency. 4.16 GROUNDING OF CONCRETE REINFORCEMENT APPROVED Reinforcement bars in concrete foundations shall be grounded as per TES-P-119.10. BY: JAH 4.17 REMOVAL OF SAND DUNES AND SAND STABILIZATION (IF REQUIRED) DATE: CERTIFIED BY: Sand dunes and shifting sand within the radius of 20m from the proposed fence/boundary wall around the transition area shall be removed and graded. The area shall be stabilized by spraying oil or emulsified asphalt material as recommended in TCS-Q-113.01, TCS-Q-113.02 and TES-P-122.11. AAS 4.18 COMMUNICATION HANDHOLE DATE: Handhole shall conform to the COMPANY Standard drawings TB-800076 & TB800077. Communication hand hole shall be provided at every change in direction, crossing, start and end of ductbank system and at every 300 m of continuous cable run. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED CONTRACTOR shall construct and install Communication Handholes, as reference to COMPANY Standards drawing numbers TA-800096 (for manhole type-1), TB800076 (for non-traffic areas), TB-800077 (for traffic areas) and TB-800098 for accessories. Handholes/manhole shall be provided with all necessary clamps and fixing hardware to enable coiling the extra length of fiber optic cable. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 18 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D Manhole/Handholes located shall be waterproofed as per COMPANY Standard drawing number TB-800082. DESCRIPTION All interior surfaces of concrete manhole/handholes shall be coated with two (2) coats of elastomeric cementitious impermeable membrane after thirty-five days of concrete placement. The second coat shall be applied within the time interval (between successive coating application) specified by the manufacturer. The total wet film thickness shall not be less than 1 mm (minimum). Above grade link boxes shall be installed as per COMPANY Standard drawing TA800141. Foundation shall be designed and constructed as per the requirements of TES-P-119.18. Top of concrete foundations shall be at the same elevation, within the range of 150mm (minimum) to 450mm (maximum). 1 2 3 NO. 4.19 ABOVE GRADE LINK BOX REVISIONS DEPT.: E&DD 4.20 BELOW GRADE LINK BOX PREP. BY MS / MA For underground link box type, a reinforced concrete pit shall be designed for heavy traffic load, water tight and shall be easily accessible. The top of pit cover of box shall be kept flush with finish/existing ground level. Underground link boxes shall be preferably be provided away from asphalt road for easy maintenance. Refer to COMPANY Standard drawing No. TA-800142 for installation details of underground link boxes. DATE: 4.21 TEMPORARY SUPPORT APPROVED BY: The CONTRACTOR shall install temporary supports to hold the structures and equipment in place while performing repair WORK. The temporary supports shall be installed only after the section to be repaired is de-energized. JAH DATE: The temporary supports shall be removed when compressive strength of the grouting material and concrete is 27.6 MPa (4000 psi) or more, and in no case, shall the temporary supports be removed sooner than seven (7) days after concrete pouring. However, curing shall continue for twenty-one (21) days as outlined in the repair procedure. Placement of grouting material shall not be done until concrete compressive strength is 21 MPa (3000 psi) or more. CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 4.22 DEMOLITION WORK A. Procedure for the accomplishment of any demolition and removal work shall be submitted to the COMPANY for approval before any work is started. The procedure shall include a detailed description of the methods and equipment to be used for each operation and sequence of operations. B. CONTRACTOR shall construct temporary wall panels to separate the existing energized equipment from the ongoing construction. Care shall be taken to ensure that no damage is caused to the existing utilities while demolition is taking place. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 19 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء 1 2 3 NO. DESCRIPTION CHK’D APP’D NATIONAL GRID SA C. CONTRACTOR shall provide all necessary protection to ensure that damage or malfunction of the equipment due to vibration, dust and debris does not occur. D. CONTRACTOR shall protect, support and relocate (if necessary) all utilities, which may be uncovered or otherwise, are affected by the WORK. CONTRACTOR shall exercise caution, familiarize himself, and investigate the WORK SITE thoroughly prior to the actual commencement of WORK. No claims based on the lack of any such knowledge shall be entertained. E. If any utility is encountered unexpectedly, the COMPANY REPRESENTATIVE shall be notified immediately. Emergency rectification work as deemed necessary shall be put in hand without delay and without prejudice to the indemnity of the COMPANY. F. CONTRACTOR shall protect the existing utilities and shall be responsible for repairing any damage to the existing facilities at no cost to the COMPANY if such damage is caused during the course of execution by the CONTRACTOR or his SubContractors. Special care shall be taken in operating machinery close to power line, fences and other vital equipment. REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: G. CONTRACTOR shall transport all removed materials to the designated COMPANY Warehouse. Due to demolition WORK of a proposed structural element, if the stability of the nearby structure is in danger, CONTRACTOR shall reinforce the same. H. CONTRACTOR shall submit the detailed design calculations and construction procedure to COMPANY for review and approval before any loads to be applied or modification to be done. I. CONTRACTOR shall provide the entire temporary supporting structure system. J. All WORKS shall be performed in a manner least likely to interfere with the operation of the existing facilities. K. For demolition/construction work, CONTRACTOR shall use only that equipment that produces minimum vibration, and their use shall not have detrimental effects on the functioning of the existing energized equipment. The equipment used for demolition and construction shall be proposed for approval of COMPANY before the start of WORK. L. As far as feasible, CONTRACTOR shall use those modern techniques for demolition/construction work that requires least time, manpower, and shall not produce any detrimental effect or malfunctioning of the existing energized equipment. APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: M. CONTRACTOR shall identify those existing facilities (lighting poles, pipelines, cables etc.), which may come in the way of demolition/construction work, and the same shall be informed to COMPANY REPRESENTATIVE in writing. All such facilities shall be relocated to a suitable location along with their associated cables. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED N. CONTRACTOR shall identify all the existing underground facilities (cables, pipes, etc.), and the same shall be shown on the drawings at the base design stage. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 20 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA DESCRIPTION 4.23 TRENCH REINSTATEMENT TO SUB-BASE A. Sand or Special Backfill Refer to Company Construction Standard requirements of thermal sand backfill. 1 2 3 NO. B. REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: TCS-P-104.03 for construction Cable Protection After applying 500 mm layer of fine, granular, uncontaminated sand above the power cable, the following cable protection and warning devices shall be placed in the trench: 1. Concrete Tiles 2. PVC Coated Steel Wire Mesh 3. Warning Tape Refer to COMPANY Materials Standard 70-TMSS-04 for technical requirements of these materials. 4. APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Warning Post: Warning posts shall be provided in all open area throughout the cable routes except on road crossings and conflict. The installation of the warning post shall be in accordance with COMPANY Engineering Standard TES-P-104.05. 4.24 REINSTATEMENT OF PAVEMENT SUB-BASE AND BASE COURSE Since the cable trenches will be routed in/around public roads, CONTRACTOR must work in conjunction with the Municipality & COMPANY Representatives for approvals of the asphalt sub-base and base course application and testing. The reinstatement shall be in accordance with latest approved Municipality/COMPANY specifications and/or the following sections as applicable. The most stringent requirements shall govern. CONTRACTOR shall submit to the COMPANY a list of test procedures and schedule of testing. CONTRACTOR shall engage the services of an independent testing agency acceptable to the COMPANY, to conduct verification tests of in-place density at an average interval of 400 meters along trenches, if requested by the COMPANY and as dictated by Municipality authorities. This testing shall be conducted by the COMPANY approved testing agency as dictated by Municipality authorities. 4.25 ASPHALT REINSTATEMENT Asphalt Concrete mix design, preparation, placement, compaction, testing and quality control shall be as per COMPANY Construction Standard TCS-Q-113.01. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 21 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA DESCRIPTION 4.26 CABLE TRENCHES INSIDE SUBSTATION/TRANSITION AREA Cable trenches shall conform to TES-P-119.19. Design and construction of reinforced concrete trenches with removable pre-cast concrete cover to route power cables, control cables and mechanical pipes. These trenches shall be traffic type. 1 2 3 NO. CONTRACTOR shall determine the exact layout of these trenches and shall size them adequately taking into consideration the following aspects: REVISIONS DEPT.: 1. Cable bending radius 2. Cable splicing (future) 3. Maintenance and operations space 4. Control and power cables to be installed in this PROJECT plus future cables 5. Spare capacity (20% minimum) E&DD PREP. BY MS / MA DATE: CONTRACTOR shall provide all cable trays, galvanized steel supports for the cable trays & necessary accessories. Concrete cable trench shall be provided with seepage pit for water drainage. The precast concrete cover shall be provided with lifting arrangement. The edge of the trenches shall be protected with galvanized steel section. The design of trench and trench cover shall be such that entry of surface water shall be prevented; the top of trench shall be kept 100mm higher than the surrounding asphalt level to prevent the entry of surface storm water, dust, debris and sand. Bottom slab of these trenches shall be sloped towards a sump pit. Sufficient number of sump pits shall be provided at suitable locations. APPROVED BY: JAH DATE: Access to trenches shall be through climbing rungs. Climbing rungs shall be galvanized steel coated with polyethylene red in color on 300mm spacing. The diameter of the rod shall be 25mm, the wall distance shall be 180mm and bore distance shall be 330mm. CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 4.27 FENCE AND GATE A. Fence and gate shall be constructed as specified in COMPANY Standard drawing TA-800113. B. The asphalt level near the gates shall be maintained at the same elevation (preferably flat) for a distance at least equal to width of the gate leaf to facilitate opening of gates and maintaining 50mm gap between the asphalt and the gates. C. A suitable opening shall be provided in the drive and personnel gate at padlock location, so that the lock can be opened/closed from both faces of the gate, details of which shall be furnished to the COMPANY for review and approval. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 22 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA REVISIONS DEPT.: A. Pre-cast concrete boundary wall and gate shall be constructed as per TA-800012 and TA-800144 except the height of panels shall be 4.0m. B. A suitable opening shall be provided in the drive and personnel gate at padlock location, so that the lock can be opened/closed from both faces of the gate, details of which shall be furnished to the COMPANY for review and approval. 1 2 3 NO. DESCRIPTION 4.28 PRECAST CONCRETE BOUNDARY WALL AND GATE C. The asphalt level near the gates shall be maintained at the same elevation (preferably flat) for a distance at least equal to width of the gate leaf to facilitate opening of gates and maintaining 50mm gap between the asphalt and the gates. E&DD PREP. BY MS / MA D. Reinforced concrete wall shall be provided when the depth of fill or the difference in elevation between the finished grade asphalt level and the adjacent property around the transition area is more than 1000mm. DATE: 4.29 PROTECTIVE CRASH BARRIERS WITH CHAIN LINK For above ground link box type, protective crash barriers shall be installed as per COMPANY Standard drawing TA-800133. APPROVED BY: JAH *** END OF SECTION IV *** DATE: CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 23 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D SECTION V - MATERIALS SPECIFICATIONS All materials required for concrete shall conform to COMPANY Materials Standard Specification 70-TMSS-03. B. Concrete for shall be as per 70-TMSS-03. C. Provide two (2) layers of 150 microns polyethylene film as protection to the bottom surfaces of concrete. Polyethylene membranes shall be laid, lapped and sealed in accordance with manufacturer’s instructions and as approved by COMPANY REPRESENTATIVE. Waterproofing membrane shall be installed by the membrane manufacturer, or on his behalf, by a professional waterproofing contractor approved by the manufacturer, acceptable to the COMPANY. D. All concrete directly in contact and exposed to the ground as well as concrete surface for manhole/handhole shall be applied with the protective coatings as per COMPANY Construction Standard TCS-P-122.05. REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: 5.2 APPROVED BY: Material: The bonding agent shall be solvent-free epoxy resin, two components, containing pigments and fine fillers. It is used for structural bonding of new concrete to existing concrete. The bonding agent shall be able to provide a bond of far greater strength than the tensile strength of the concrete itself. Refer to TCS-Q-113.06 for the properties of bonding agent. B. Surface Preparation: Clean all surfaces and remove any dust, unsound material, plaster, oil, paint, grease, corrosion deposits or algae. Roughen the surfaces, remove any laitance and expose aggregate by light scrabbling or grit blasting. Oil and grease deposits shall be removed by steam cleaning, detergent scrubbing or the use of a proprietary degreaser. C. Application: After mixing apply directly to the prepared substrate by brush, roller or spray. On damp surfaces, ensure that it is well brushed in. Pour new concrete within specified open time, as long as material is still tacky. DATE: CERTIFIED AAS DATE: CONCRETE BONDING AGENT A. JAH BY: CONCRETE A. 1 2 3 NO. DESCRIPTION 5.1 5.3 A. REPAIR MORTARS Patch Repairs High performance, free flowing, non-metallic, non-shrink, cementitious micro concrete as per TCS-Q-113.06. B. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Concrete Surfacer A single component polymer modified cementitious fairing coat, to infill honeycombing and voids up to 3mm deep, and as a blow hole filler up to 10mm deep as per TCS-Q-113.06. C. Crack Injection PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 24 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA Epoxy resin based, low viscosity, non-shrinking bonding material as per TCS-Q113.06. DESCRIPTION 5.4 CONCRETE FORMWORK 1 2 3 NO. Formwork shall be designed and constructed in accordance with ACI-347. All forms shall be unyielding and sufficiently tight to prevent leakage of mortar, and properly braced or tied together to maintain position and shape that produces result in a final structure conforming to size, shape and dimensions of the member as required or shown on the drawings. Form surfaces shall be clean, smooth and sufficiently hard to produce smooth, hard and uniform texture on the concrete. REVISIONS DEPT.: E&DD PREP. BY MS / MA 5.5 TIES AND ANCHORS All ties, braces, anchors and other miscellaneous metal or plastic accessories shall be securely and properly placed and tied, so that they will not be dislodged during the pouring operation and will be embedded at the depths and positions specified. Gage of the wire shall be a minimum of no. 16 USS. DATE: 5.6 APPROVED BY: CONTRACTOR shall not place any concrete until the excavations and/or forms and embedded items are inspected by the COMPANY REPRESENTATIVE. This inspection will not relieve the CONTRACTOR of the responsibility of keeping the holes in acceptable condition until placement of concrete is completed nor for the accurate placement of embedded items. The placing of concrete shall be accomplished in such a manner so as to prevent any segregation. JAH Test on concrete, aggregates and mixing water shall be as per COMPANY Material Standard 70-TMSS-03. All test results shall be submitted to the COMPANY for review and approval as the tests are completed. CERTIFIED The results of these tests shall be systematically filed with descriptions of where the batch was used. Copies of all test results shall be handed over to the COMPANY REPRESENTATIVE for review and comments. When the construction WORK is completed, this shall be turned over to the COMPANY REPRESENTATIVE for incorporation into the COMPANY’S permanent records. DATE: BY: CONCRETE INSPECTION AND TESTING AAS DATE: In the event that concrete fails to meet strength requirements, in-place testing for concrete strength shall be conducted by the CONTRACTOR under supervision of the COMPANY REPRESENTATIVE at no additional cost to the COMPANY. In-place testing shall be conducted by one (1) or a combination of the following methods: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED 1. ASTM C42, “Method of Obtaining and Testing Drilled Cores and Sawed Beams of Concrete”. 2. ASTM C803, “Standard Test Method for Penetration Resistance of Hardened Concrete” PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 25 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء APP’D NATIONAL GRID SA CHK’D 3. ASTM C805, “Standard Test Method for Rebound Number of Hardened Concrete”. DESCRIPTION Concrete in the area represented by in-place test shall be considered structurally adequate provided such results conform to the provision of ACI-318. COMPANY REPRESENTATIVE reserves the right to require additional cylinders be taken whenever there is just cause, such as a change in batching procedures, a change in concrete materials, breaking of batching, delay in transport or placement, code violation and the like at no additional cost to the COMPANY. 1 2 3 NO. Concrete subject to severe exposure condition shall be tested for chloride permeability test. REVISIONS 5.7 DEPT.: E&DD PREP. BY MS / MA CURING OF CONCRETE All concrete shall be cured with concrete mix quality water (potable) in accordance with recommendations of ACI 305 and ACI 308. Refer COMPANY Standard 70TMSS-03 and TCS-Q-113.03 for methods and details of curing. DATE: 5.8 ASPHALT CONCRETE PAVING Asphalt Concrete Paving shall conform to TCS-Q-113.01. 5.9 Reinforcing steel shall be deformed steel bars conforming to SASO SSA-2 and ASTM A615M.with a yield stress of 420 MPa. APPROVED BY: REINFORCING STEEL JAH 5.10 EARTHWORKS DATE: A. All earthwork including excavation and backfilling and all other necessary materials within the COMPANY facilities shall conform to the requirements specified in the COMPANY Standards TCS-Q-113.02 and TCS-P-104.03. B. All backfill materials shall be furnished from a source accepted by the COMPANY REPRESENTATIVE. Acceptance of a backfill source shall not mean automatic acceptance of all material obtained from the source, and the COMPANY REPRESENTATIVE may withdraw approval of the source at any time if materials produced by the source are not suitable for backfill. If suitable, excavated material can also be used for backfill. CERTIFIED BY: AAS DATE: 5.11 CABLE TRENCH THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED For cable trench materials including warning tapes, wire mesh, concrete tiles and plastic spacers, Company Material Standard 70-TMSS-04 shall be followed. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 26 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA A. Structural steel shall conform to the latest revision of ASTM A36. B. Bolts, nuts and washers shall conform to the latest revision of ASTM A394, ASTM A563M and ASTM F436. C. Structural steel shall be hot-dip galvanized after fabrication in accordance with the requirements of 01-TMSS-01. Bolts, nuts, washers and palnuts shall be galvanized in accordance with the requirements of 01-TMSS-01. D. Welding shall conform to COMPANY Engineering Standards for "General Welding Criteria" TES-W-109.01. E. Anchor bolts shall conform to ASTM F1554 and AISC requirements. Full length of anchor bolts shall be hot-dip galvanized in accordance with 01-TMSS-01. F. Design, fabrication and erection of the steel structures shall be in accordance with latest revision of AISC Manual of Steel Construction. 1 2 3 NO. DESCRIPTION 5.12 STRUCTURAL STEEL REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: G. CONTRACTOR shall submit all fabrication and erection drawings for COMPANY review and approval. No fabrication shall commence until all fabrication drawings are approved and marked "Issued for Construction". H. APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: CONTRACTOR shall submit assembly and fabrication drawings for COMPANY review and approval in coordination with the steel fabricator. Assembly and fabrication drawings shall be signed and stamped by CONTRACTOR as well as steel fabricator. Fabrication shall not commence until all fabrication drawings are approved and marked "Issued for Construction". 5.13 CEMENT AND SAND SCREED Screed shall conform to TCS-Q-113.03. A cement & sand (1:3) screed with water cement ratio as low as possible compatible with workability. The surface of the structural concrete shall be thoroughly cleaned from all rubbish, concrete and mortar droppings. Oil and grease patches shall be cleaned with approved agents. The surface of the floor shall be roughened with wire brush and thoroughly cleaned with clean water. Surplus water shall be brushed off and 1:1 cement/sand slurry brushed over the surface immediately before laying the screed. The finished surface shall be laid in panels and trowelled smooth to produce hard, dense and flat surface. Continuous curing shall be performed for at least 7 days. 5.14 WATERPROOFING MEMBRANE THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED All waterproofing membranes (Modified Bituminous, PVC, Polyurethane etc.) shall conform to COMPANY Materials Standard 78-TMSS-11. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 27 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA 5.15 COAL TAR EPOXY DESCRIPTION The material shall be procured and applied as per the requirements specified in 70TMSS-01 and TES-H-107.01. 5.16 WATERSTOP 1 2 3 NO. Waterstop (Rubber or PVC) shall conform to TCS-Q-113.03. 5.17 PVC CONDUITS/FITTINGS, SUB-DUCTS AND RSGC REVISIONS A. DEPT.: E&DD B. PREP. BY MS / MA DATE: PVC conduits and fittings shall conform to 23-TMSS-01. Subducts shall be corrugated, flexible and fire retardant (2 Hours UL rating) with 25mm outside diameter. Subduct installation shall be in accordance with TCS-T-111.08. Subduct on the underground ductbanks and direct buried conduit in trenches shall be rigid with 32mm outside diameter and made from HDPE piping compound, its inner wall must be smooth and black in color. It must comply with STC specification MAT 2301 and pulling length must not exceed 450 meters. C. For direct buried cable trenches, PVC conduits shall be of class-4 type. Nylon pull ropes 0.25 inches in diameter (of different colors) shall be provided and installed in all vacant/spare ducts and subducts. D. The duct sealing units for conduit fittings shall be in accordance with COMPANY'S Materials Standard 23-TMSS-02. E. Unless otherwise indicated, the size of the PVC conduit for fiber optic cable and cables shall be 100 mm inner diameter and 200 mm inner diameter respectively. F. PVC Coated Rigid Steel Galvanized Conduits (RSGC): Rigid conduits shall be hotdip galvanized with PVC coating, fittings shall be threaded and hot-dip galvanized. APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: 5.18 CABLE TRAYS Power cables, communication cables and control cable trays shall be designed and installed as per the requirements of TES-P-119.19. Cable trays (roof or wall supported) are required in basement/cable entry room, communication room, trenches, etc. for supporting power & control cables and communication cables. Design, fabrication and installation of hot-dip galvanized steel bridges over power cables at the basement/cable entry room. The steel bridges shall be covered with hot-dip galvanized steel grating. THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Design, fabrication and installation of hot-dip galvanized steel uni-strut supports, clamps and necessary accessories for routing outgoing feeder cables in the cable basement/cable entry room. PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 28 OF 27 REV. 01 CERT. الشركة الوطنية لنقل الكهرباء CHK’D APP’D NATIONAL GRID SA 1 2 3 NO. DESCRIPTION *** END OF SECTION V & APPENDIX *** REVISIONS DEPT.: E&DD PREP. BY MS / MA DATE: APPROVED BY: JAH DATE: CERTIFIED BY: AAS DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED PLANT NO. JOB ORDER NO. CIVIL AND STRUCTURAL SCOPE OF WORK, DESIGN CRITERIA, TECHNICAL REQUIREMENTS REFER AND MATERIALS SPECIFICATIONS FOR TO MAIN UNDERGROUND CABLES SOW/TS INDEX DOCUMENT NO. A CIVIL APPENDIX TO MAIN SOW/TS PAGE NO. 29 OF 27 REV. 01 APPENDIX VIII PROJECT DESIGN DOCUMENTS, CALCULATIONS AND DRAWINGS CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء APP’D NATIONAL GRID SA CHK’D TABLE OF CONTENTS PAGE REVISIONS DEPT.: I INTRODUCTION 3 II LIST OF UNIFIED DESIGN SUBMITTALS 4 III SUBMITTAL CODE 12 IV STATUS CODES OF DESIGN SUBMITTALS 13 V CHECK LISTS 14 1 2 3 NO. DESCRIPTION SECTION E&DD PREP. BY: DATE: APPROVED BY: DATE: CERTIFIED BY: DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 2 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء APP’D NATIONAL GRID SA CHK’D SECTION I - INTRODUCTION 1 2 3 NO. DESCRIPTION This document is a guide for Unification of design submittals, which shall be followed in National Grid HV underground cable (Transition Area if required) Projects. The purpose of this document is to provide guidance to CONTRACTOR in submitting design submittals for HV underground cable (Transition Area if required) Projects with the objective of completion of design phase in an effective and efficient manner. REVISIONS DEPT.: E&DD PREP. BY: The CONTRACTOR shall submit the design documents, calculations, studies and drawings at various stages of the PROJECT design phase as per the stated guidelines and Table .1 & 2 of this Appendix. The CONTRACTOR shall, however, submit any additional calculations and drawings in support of the design work, which may be necessary for completeness of the subject design, using a new code other than the codes mentioned in the table. Partial submittal of calculations/drawings without supporting documents will not be accepted. The titles of the Document Transmittal Sheets shall be as listed in the following table (Table.1 & 2). The CONTRACTOR shall provide all drawings required for this PROJECT, covering all the submittal involved in completing design of HV underground cable (Transition Area if required), in accordance with the requirements of the COMPANY Engineering Drawing Preparation Standards (SEEDS-II, latest revision). DATE: The drawings shall be assigned with drawing numbers and indexed as outlined in the above procedure. A block of drawing numbers shall be provided by the COMPANY for all new drawings/documents. APPROVED **** END OF SECTION I **** BY: DATE: CERTIFIED BY: DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 3 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء APP’D NATIONAL GRID SA CHK’D SECTION II – LIST OF UNIFIED DESIGN SUBMITTALS Contractor should follow the submittal list as mentioned below in document submission to Engineering & Design Department (E&DD) for review. The Title & description of each submitted document should match with the submittals as mentioned in unified submittal list. DESCRIPTION Table. 1:- HV UNDERGROUND CABLE Sr. No. PRE SUBMITT AL DTS Title 1 2 3 NO. CATAGOREY - 1 GENERAL DOCUMENTS Document Control 1 Sheet E&DD PREP. BY: Technical Data / Calculation / Drawing / All / Others Document Document 2 Document Transmittal Sheet Document Document 3 Document Title Block Document Document 4 Drawing Title Block Drawing Document REVISIONS DEPT.: Document's Category 5 Single Line Diagram 6 Existing As-build drawing (If Required) Drawing Cover Page of the document bearing the Project title, document description, doc. No. & details of the Personnel's involved in the project. Cover page bearing the details of the document. Cover page bearing the details of the drawing. Drawing Drawing showing the start and End point of the proposed power cable circuit and information regarding the power cable size and tentative route length. Drawing Existing Schematic drawings and route of the existing Power cable circuits (For loop in and out of the existing Power cable circuits). Drawing/Technical Data Technical specifications as per 11TMSS-02, and drawings supported with Standard Compliance & Manufacturer's Responsibility Statements. DATE: Drawing DTS Description CATAGOREY - 2 (EQUIPMENT AND MATERIALS ELECTRICAL) APPROVED 7 HV Power Cables 44 Material BY: DATE: CERTIFIED 8 Power Cable Termination Kits (CSE) 9 Power Kits 10 7 & 12 Material Drawing/Technical Data 7 Material Drawing/Technical Data Bare copper conductor and Grounding Rods 45 Material Drawing/Technical Data 11 Bonding Cable 45 Material Drawing/Technical Data 12 Non-Linear Resistance for GIS termination 46 Material Drawing/Technical Data Cable Splice BY: DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET & Earthing APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX Power Cable Termination (Indoor/Outdoor) Technical specifications as per 12-TMSS-10 and drawings supported with Standard Compliance & Manufacturer's Responsibility Statements. Power Cable Splice Technical specifications as per 12-TMSS-10 and drawings supported with Standard Compliance & Manufacturer's Responsibility Statements. Bare copper conductor and Grounding Rods Technical specification as per 12-TMSS-11, 10-TMSS-05 & TES-P-104.08 and drawings supported with Standard Compliance & Manufacturer's Responsibility Statements. Bonding & Earthing Cable Technical specifications as per 11TMSS-12 and drawings supported with Standard Compliance & Manufacturer's Responsibility Statements. Non-Linear Resistance Technical specifications as per TES-P-119.41 and drawings supported with Manufacturer's Responsibility Statements. DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 4 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء DESCRIPTION CHK’D APP’D NATIONAL GRID SA 13 Link Box along with accessories 14 Power Cable Clamps Cable Warning Tapes Material Drawing/Technical Data 7, 20 Material Drawing/Technical Data 53, 25 Material Drawing/Technical Data 1 2 3 NO. 15 7,8,9,10, 11 REVISIONS 16 Cable Protective Tiles 53, 25 Material Drawing/Technical Data E&DD 17 Steel Wire Mesh 53, 25 Material Drawing/Technical Data 18 Cable warning post 25, 61 Material Drawing/Technical Data DEPT.: PREP. BY: DATE: Duct Sealing Units specifications as per 23-TMSS-02 and drawings supported with Standard Compliance Statements & Manufacturer's Responsibility. Complete Technical Specifications & data schedule. Approval of loading calculation and cable and trays/raceways layout are required. Latest revision of 24-TMSS-01 would be used as a reference. Complete Technical Specifications of Cable support as per TES-P104.05 supported with Standard Compliance & Manufacturer's Responsibility Statements. PVC Conduits and Fittings Technical specifications as per 23TMSS-01 and drawings supported with Standard Compliance Statements & Manufacturer's Responsibility. Exhaust and supply air fans of smoke purge fan standard, motorized fan and smoke dampers are required HV Cable Trays (Cable Support) 50 Material Drawing/Technical Data 21 PVC Conduits Fittings 7 Material Drawing/Technical Data 22 Ventilation system for power cable to be laid in Tunnel 31, 42,49, 59 Material Drawing/Technical Data 23 Temperature monitoring system of Tunnel (If Required) 32 Material Drawing/Technical Data High temperature required 24 Plumbing system tunnel (If Required) Material Drawing/Technical Data Submersible pumps and its allied piping and fittings are required. Latest revision ofTMSS-83-Tmss01,TES-P-119.19 will be used as reference 20 DATE: DRAWING CONTROL SHEET Plan, section and details of warning post Drawing/Technical Data and CERTIFIED THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED Cable Tiles Technical specifications as per 70-TMSS-04 & TCS-P-104-03 and manufacturer's Responsibility Statements & drawings Steel Wire Mesh Technical specifications as per 70-TMSS-04 & TCS-P-104-03 and manufacturer's Responsibility Statements & drawings Material Duct Sealing Units DATE: BY: Cable Warning Tapes Technical specifications as per 70-TMSS-04 & TCS-P-104-03 and manufacturer's Responsibility Statements & drawings 53, 27, 30 19 APPROVED BY: Link Box Technical specifications as per 12-TMSS-11 and drawings supported with Standard Compliance & Manufacturer's Responsibility Statements. (with SVL & without SVL) Cable Clamps Technical specifications as per 23-TMSS-04 and drawings supported with Standard Compliance & Manufacturer's Responsibility Statements. of 51, 33 ,59 sensors are CATAGOREY - 3 (PROJECT DESIGN DOCUMENTS / DRAWINGS) 25 Key plan of cables Route Power 5 Design APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A Drawings PLANT NO. INDEX Drawing showing route of the propose line, existing utilities / highways & roads crossing (within the R.O.W of the proposed cable route), start & end points and intersection points. DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 5 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء 26 Plan & profile details 25 Design Drawings 27 Cable Entry Plan 25 Design Drawings 28 Test Pit Location identification on the key plan 25 Design Drawings 29 Test Pit/Radar scanning details results 30 Horizontal Directional Drilling (HDD) 25 31 Ventilation system for power cable to be laid in Tunnel 32 Design Drawings Drawing Showing location and depth of HDD as per approved key plan of power cable route and cross sectional drawing along with Method Statement for HDD. 42,59 Design Drawings Layout and sections of tunnels showing fans and its location as per approved calculations and equipment schedule Temperature monitoring system of Tunnel (If Required) 59 Design Drawings Schematic diagram for sensors 33 Plumbing system tunnel (If Required) 59 Design Drawings Pumps and piping plan view, sections drawings, plumbing details and equipment schedule will be submitted 34 Power Cables Termination Arrangement, Termination Plan, Sections/Details 60 Design Drawings Termination arrangement with necessary sections and details 35 Cable Sagging/Snaking & Joint Bay Details 36 Remote-End Modification required) Design E&DD PREP. BY: DATE: APPROVED of BY: DATE: Power cable entry arrangement at substations showing arrangement of cable and GIS termination in basement or outdoor termination. Identifying the location of test pits on the proposed power cable route to determine the existing utilities/power cables. Drawings 28 REVISIONS DEPT.: Profile of cables circuits with necessary sections, Elevations and Details, crossings, utilities, spacing (splicing) points, and location of link Boxes for cable sheath. Test pit result shall show the location of proposed power cable & indicate clearance of all existing utilities from the proposed power cable as per NGrid SA standard. 1 2 3 NO. DESCRIPTION CHK’D APP’D NATIONAL GRID SA 60 (If Design Drawings Design Drawings Report (Electrical) Document CERTIFIED Detail layout drawing of cable sagging/snaking, link box, and joints and grounding arrangement at joint bay. Modification at Remote End substation showing all work to be done including, adding/utilizing CBs (including JIB if applicable), adding/modifying control/protection/communication etc. CATAGOREY - 4 (REPORTS) BY: 37 Soil Thermal Resistivity Measurements Report along cables route 38 Civil Design Philosophy, Standards, Codes, Design Basis and Design Data 39 Concrete Mix Design 40 41 DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET 28 Soil Thermal Resistivity Measurements measurement report along the cable route. Document providing description of project, design philosophy design parameters , Standards and Codes etc. Report providing Concrete Mix design for all Structural Concrete Works based upon NG Standards & applicable recommendations of soil investigation report. - Report (Civil) Document 41 Report (Civil) Document Asphalt mix design - Report (Civil) Document Report providing details of asphalt mix design procedure and test results of the constituents materials Geotechnical Investigation Report 62, 25 Report (Civil) Document Report providing details of soil investigation and recommendations for foundation Design. APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 6 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء APP’D NATIONAL GRID SA Calculations Detailed Design Current rating calculations as per IEC-60287 or CymCap to performed on the offered power cable to ascertain the requirement of desired power cable rating as per SOW of projects Design Calculations Calculations Design calculation for Sheath induced voltage at normal & Fault conditions along with selection of minor section length and selection of Sheath Voltage Limiters (SVL) Design Calculations Calculations Calculation for Ground and bonding Cable/Conductor Sizing Design Calculations Calculations 46 Calculations for NonLinear Resistance for GIS terminations Design Calculations Calculations 47 Circulating calculations 60,43 Design Calculations Calculations 48 Cable pulling tension and sidewall pressure calculations 7, 25 Design Calculations Calculations 42, 59 Drawing/Design Calculations Design/Drawing Mechanical Drawing/Design Calculations Design/Drawing Mechanical 59 Drawing/Design Calculations Design/Drawing Mechanical 42 Detailed Cable Ampacity Calculations 7, 28,30, 37, 53, 57, 59, Design Calculations 43 Calculations for sheath standing voltage, sheath voltage rise and the Selection of Sheath Voltage Limiters (SVL). 30, 42, 53,57 ,59 44 Calculations for Cable Metallic Sheath Sizing and Fault current withstand capability 7 45 1 2 3 NO. DESCRIPTION CHK’D CATAGOREY - 5 (PROJECT DESIGN CALCULATIONS) REVISIONS DEPT.: E&DD PREP. BY: DATE: APPROVED 49 BY: DATE: 50 CERTIFIED THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET Ventilation system design & calculation for power cable to be laid in Tunnel Calculation for cable tray (cable support) (Loading calculation for cable trays & Support) 51 Plumbing system tunnel (If Required) 52 Design Calculations and Drawings for Link Box Foundation 39,41, 13 Design All Design calculations for link box foundation and drawing of Plan, sections & reinforcement details. 53 Design Calculations and Drawings for duct banks in traffic areas and road crossings 39,41, 25 Design All Design Calculation, Sections, layout, reinforcement & structural details of Duct Bank & wing walls. 54 Design Calculations and Drawings for handhole/manholes All Design Calculation, Sections, layout, reinforcement details of Electrical and Communication Manholes & Hand hole. 55 Design Calculation and Drawings for CSE Steel Supporting Structure. 39,41, 8 Design All Design calculations, Layout, levels, section along with construction Notes and other fixing detail drawings for “CSE” Steel Support Structure. 56 Design Calculations and Drawings for CSE foundation 39,41, 55 Design All Design Calculation, Sections, layout, and reinforcement details for CSE Support Structure Foundation. BY: DATE: current of Design Calculation for Cable Metallic Sheath Sizing based on short circuit current of 40 kA for 1 second Ground Cable & Bonding CABLE /Conductor cross-section Sizing Calculation for ultimate fault current (40kA for 1 second) as per TES-P104.08, ICEA P-45-482 & IEC 60949. Calculations performed to ascertain the requirement of Non-Linear Resistor as per TES-P-119.41 to account GIS transient over voltages. For unequal section length in cross bonded system. The cable tension and sidewall pressure depend upon the material and cross-sectional area of the conductors. Allowable pulling tension and sidewall pressure are determined by calculations as per TES-P-104.05 on actual route. Calculation for air volume flow rate by heat balance and number of air changes method for fan exhaust and supply air fan selection Loading calculation required to confirm load bearing capacities, filling capacities and deflection as per SEC standard TES-P-104.05 Calculation for total dynamic head and number of pumps required will be submitted 39,41, 25 Design APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 7 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء DESCRIPTION CHK’D APP’D NATIONAL GRID SA 57 Design Calculations and Drawings of Cable Trench and Precast Concrete Cover. 58 Crash Barrier 59 Design Calculation and Drawings for Cable Tunnel. 39,41, 25 Design All - Drawing All 37,40, 41, 48,53,50 Design All Design Calculation, Sections, layout, reinforcement details for Cable trench & Precast Cover. Drawings showing the details of the crash barriers to be installed at road intersections for Access Roads Design Calculation, Sections, layout, and reinforcement details for cable tunnel. 1 2 3 NO. CATAGOREY - 6 (PROJECT DESIGN DOCUMENTS / DRAWINGS) 60 Schematic Drawing & Bonding 43 Design Drawings 61 Link Box Locations Plan, Section and Details 35, 60 Design Drawings 25 Drawings Drawings - Drawings Drawings REVISIONS DEPT.: E&DD PREP. BY: 62 DATE: 63 Bore Hole Location Plan and Method Statement for Soil Investigation General Civil/Structural Notes (Specifications of Concrete, Steel Reinforcements, Formwork, Earthwork etc.) Schematic drawing showing the transposition of power cable & bonding/grounding arrangement of power cable sheath, details of minor and major sections of the cross bonded or single point bonded scheme. Details of the induced voltage for every major and minor section during steady state & transient condition. Complete route showing locations of link boxes with necessary sections and details of installing the link box underground/above ground Drawing Showing location and depth of boreholes as per approved plan and Profile along with Method Statement for soil investigation Drawing showing Specifications of Concrete, Steel Reinforcements, Formwork and Earthwork etc. APPROVED BY: DATE: CERTIFIED BY: DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 8 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء APP’D NATIONAL GRID SA CHK’D Table. 2 :- (Transition Area) Sr. No. Submittal Title PRE SUBMITTAL Document's Category Technical Data / Calculation / Drawing / All / Others Submittal Description 1 2 3 NO. DESCRIPTION CATAGOREY – 1 (EQUIPMENT AND MATERIALS) 1 Technical Submittal for Conductor - Material Technical Data / drawing 2 Technical Submittal for take-off/gantry Material 14 Material Technical Data / drawing 3 Technical Submittal for Insulators - Material (Electrical) Technical Data / Drawing REVISIONS DEPT.: E&DD PREP. BY: DATE: 4 Technical Submittal for Insulator String Fittings, Vibration Dampers and Hardware Assembly Details 5 Technical Submittal for OPGW Fittings ,Vibration Dampers & Hardware Assembly Details 1&3 Material (Electrical) Technical Data / Drawing Technical specification material for insulator String Fittings, Vibration Dampers and Hardware as per 12TMSS-01 shall be provided by manufacturer supported with Standard Compliance & Manufacturer's Responsibility Statements and original catalogues. Technical Data / Drawing Technical specification material for OPGW Fittings, Vibration Dampers and Hardware assembly details as per 12-TMSS-01 & 12-TMSS-02 shall be provided by manufacturer supported with Standard Compliance & Manufacturer's Responsibility Statements and original catalogues. Technical Data / Drawing Technical specification material for Connectors as per 12-TMSS-02 shall be provided by manufacturer supported with Standard Compliance & Manufacturer's Responsibility Statements and original catalogues. APPROVED BY: DATE: 6 Technical Submittal for Connectors 7 Material (Electrical) 1&7 Material (Electrical) Technical Data / Drawing CERTIFIED BY: 7 Technical Submittal for OPGW - Material (Electrical & Telecom) 8 Technical Submittal for Grounding Materials (including Grounding Conductor & Grounding Rod) 13 Material Technical Data / drawing 9 Technical submittal for Surge arrestor - Material Technical Data / drawing DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A Technical specification material for Conductor (ACSR, ACSR-AW, AAAC, ACAR, and AAC etc.) as per 10TMSS-01 is provided by manufacturer supported with Standard Compliance & Manufacturer's Responsibility Statements and original catalogues. Technical specification material for take-off/gantry (lattice / Monopoles) as per 20-TMSS-01 & 20-TMSS-02 is provided by manufacturer supported with Standard Compliance & Manufacturer's Responsibility Statements. Technical specification material for Insulators (Porcelain long rod, Composite, Disc Type etc.) As per 15TMSS-01-07 shall be provided by manufacturer supported with Standard Compliance & Manufacturer's Responsibility Statements and original catalogues. PLANT NO. INDEX Technical specification material for OPGW as per 10-TMSS-04 shall be provided by manufacturer supported with Standard Compliance & Manufacturer's Responsibility Statements. Technical specification material for Grounding Materials (including Grounding Conductor & Grounding Rod) as per 12-TMSS-11, 10-TMSS05 & TES-P-104.08 and drawings supported with Standard Compliance & Manufacturer's Responsibility Statements. Technical specification material for Surge arrestor as per 35-TMSS01 is provided by manufacturer supported with Standard Compliance & Manufacturer's Responsibility Statements. DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 9 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء 1 2 3 NO. DESCRIPTION CHK’D APP’D NATIONAL GRID SA REVISIONS DEPT.: E&DD 10 Capacitor Transformer 11 12 Voltage Technical specification material for Capacitor Voltage Transformer as per 50-TMSS-02, Rev.01 shall be provided by manufacturer, supported with Standard Compliance & Manufacturer's Responsibility Statements. Technical specification material for Free Standing Current Transformer as per 50-TMSS-01, Rev.01 shall be provided by manufacturer, supported with Standard Compliance & Manufacturer's Responsibility Statements. Report providing Technical Specifications of backfill material as per standard TCS-Q-113-02. - Material Technical Data / drawing Free Standing Current Transformer - Material Technical Data / drawing Backfill Materials - Material Technical Data / drawing Calculations and drawings performed to ascertain the achievement of desired grounding resistance within the terminal compound area. CATAGOREY – 2 (DESIGN CALCULATIONS) 13 Terminal Compound grounding calculations 34 Design Calculations / Drawings 14 Design Calculations and Design Drawings/Outline Drawing for Take-off Gantry Structure at Transition Area - Design Calculations / Drawings Gantry/take-off (lattice/monopole) structure design calculations 15 Design Calculation of foundation of Takeoff/gantry structure 14,33 Design Calculations / Drawings Take-off/gantry (lattice/monopole) Foundations Design Calculations, sections & reinforcement details 16 Design calculation of retaining wall for precast boundary wall if required 31,33 Design Calculations / Drawings Design calculations for Present Boundary wall foundation (i.e. retaining wall), sections & reinforcement details in addition to precast boundary wall details. 17 Design calculation for precast boundary wall if required 16,33 Design Calculations / Drawings Panel height, Logo, Grooves, Pattern , Removable column fixing 18 Design Calculations and Drawings for handhole/manholes inside transition area 31,33 Design Calculations / Drawings Design Calculation, Sections, layout, reinforcement details of Electrical and Communication Manholes & Hand hole. 9 Design Calculations / Drawings Design calculations, Layout, levels, section along with construction Notes and other fixing detail drawings for CSE & SA Steel Support Structure 31, 33 Design Calculations / Drawings Design Calculation, Sections, layout, reinforcement details for Cable trench & Precast Cover. PREP. BY: DATE: APPROVED BY: DATE: 19 CERTIFIED 20 BY: DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET Design Calculation and Drawings for CSE & SA Steel Supporting Structure. Design Calculations and Drawings of Cable Trench and Precast Concrete Cover. 21 Design Calculations and Drawings for CSE & SA foundation 19,33 Design Calculations / Drawings Design Calculation, Sections, layout, and reinforcement details for CSE & SA Support Structure Foundation. 22 Steel support structure design calculations and detail drawings for Current Transformer (CT) 14 Design Calculations / Drawings Design calculations and drawings to show the details of steel support structure of Current Transformer (CT) 23 Design calculations and detail drawings of Current Transformer (CT) foundation 22,33 Design Calculations / Drawings Design calculations and drawings to show the details of steel support structure foundation of Current Transformer (CT) 24 Steel support structure design calculations and detail drawings for Voltage Transformer (VT) 10 Design Calculations / Drawings Design calculations and drawings to show the details of steel support structure of Voltage Transformer (VT) APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 10 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء CHK’D APP’D NATIONAL GRID SA 25 Design calculations and detail drawings of Voltage Transformer (VT) foundation 26 Design Supports of Cable 24,33 Design Calculations / Drawings Design calculations and drawings to show the details of steel support structure foundation of Voltage Transformer (VT) - Design Calculations / Drawings Design calculations for cable supports with detail drawings - Design Drawings Drawings prepared to ascertain the achievement of desired grounding resistance at the line crossing gantry location. 27 Transition Grounding Drawings 28 Layout, plan, section and Details of fence - Design Drawings The layout & details of fencing provided around all transition area. 29 Drive/personnel Gate Plan, Section and connection details. - Design Drawings Plan, section and details of Entry Gates of Fence. 1 2 3 NO. DESCRIPTION CATAGOREY - 3 (Design Documents / Drawings) Area Layout REVISIONS DEPT.: 30 Site Grading Paving Plan Transition Area and for 31 Transition Area Layout 32 Bore Hole Location Plan and Method Statement for Soil Investigation 31 Design Drawings Topographic survey including contour line, levels and elevations for the proposed transition area and the surrounding roads and area. In addition to this provide proposed inside / outside levels, slopes and storm drainage. - Design Drawings Layout drawing for the Transition area showing Equipment Arrangement including details & Sections E&DD PREP. BY: DATE: 31 Drawings Drawings Drawing Showing location and depth of boreholes as per approved plan and Profile along with Method Statement for soil investigation 32 Report Document Report providing details of soil investigation and recommendations for foundation Design. - Report (Electrical) Document Electrical soil resistivity test report for all proposed structure locations - Report Document Soil Thermal Resistivity Measurements report for various points readings for the Transition Area CATAGOREY - 4 (REPORTS) 33 Geotechnical Investigation Report 34 Geotechnical Resistivity Report 35 Soil Thermal Resistivity Measurements Report APPROVED BY: DATE: Soil **** END OF SECTION II **** CERTIFIED BY: DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 11 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء CHK’D APP’D NATIONAL GRID SA SECTION III – SUBMITTAL CODE The submittal code is a unique numbering system for each design submittal that shall be followed as mentioned below: DESCRIPTION XX XN XXX – X - XXX Submittal’s Number PTS Prepared Year Submittal’s Type E: Electrical M: Mechanical C: Civil PTS Prepared Operation 1 2 3 NO. PTS Number REVISIONS Example: 19 EN123E001 DEPT.: E&DD **** END OF SECTION III **** PREP. BY: DATE: APPROVED BY: DATE: CERTIFIED BY: DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 12 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء APP’D NATIONAL GRID SA CHK’D SECTION IV – STATUS CODES OF SUBMITTAL 1 2 3 NO. DESCRIPTION Approval status codes which will be assigned on National Grid comment sheet are as under: STATUS CODE DEFINITION A Acceptable B REVISIONS C DEPT.: E&DD PREP. BY: DATE: D DESCRIPTION Acceptable by E&DD and no further comments. Acceptable by E&DD with minor Acceptable with minor comments/notes/remarks (do not affect project's comments/notes/remarks design) and Project Dept. shall verify compliance of these comments accordingly. Major comments that affect project's design and Comments shall resubmit. Return without review and shall resubmit with same revision number due to: • Violation of Company Standard and Specifications. Rejected • Not listed in LOTAM. • Missing important documents or drawings. • No compliance to previous comments. APPROVED BY: DATE: **** END OF SECTION IV **** CERTIFIED BY: DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 13 OF 14 REV. 0 CERT. اﻟﺷرﻛﺔ اﻟوطﻧﯾﺔ ﻟﻧﻘل اﻟﻛﮭرﺑﺎء APP’D NATIONAL GRID SA CHK’D SECTION V – CHECK LISTS 1 2 3 NO. DESCRIPTION Check Lists indicate details of the pre-requisite and the documents required to review the subject document. REVISIONS DEPT.: E&DD PREP. BY: DATE: APPROVED BY: DATE: CERTIFIED BY: DATE: THIS DOCUMENT IS NOT TO BE USED FOR CONSTRUCTION OR FOR ORDERING MATERIALS UNTIL CERTIFIED AND DATED DRAWING CONTROL SHEET APPENDIX-XX FOR <<XYZ>> HV UNDERGROUND CABLE PROJECT, S AU D I A R A B I A PLANT NO. INDEX DOCUMENT NO. JOB ORDER NO. PTS-19XNXXX PAGE NO. 14 OF 14 REV. 0 HV UNDERGROUND CABLE CHECK LIST TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 1 –Document Control Sheet Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. 1 2 3 4 5 CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents: Document Control Sheet Documents which are required to be considered: PTS of project Pre-bid clarifications of project Post-bid clarifications of project Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 6 SEED-II (SEC Engineering Drawings Standard) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 2 –Document Transmittal Sheet Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. 1 2 3 4 5 CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents: Document Transmittal Sheet Documents which are required to be considered: PTS of project Pre-bid clarifications of project Post-bid clarifications of project Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 6 SEED-II (SEC Engineering Drawings Standard) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 3 –Document Title Block Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. 1 2 3 4 5 CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents: Document Title Block Documents which are required to be considered: PTS of project Pre-bid clarifications of project Post-bid clarifications of project Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 6 SEED-II (SEC Engineering Drawings Standard) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 4 – Drawing Title Block Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. 1 2 3 4 5 CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents: Drawing Title Block Documents which are required to be considered: PTS of project Pre-bid clarifications of project Post-bid clarifications of project Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 6 SEED-II (SEC Engineering Drawings Standard) 7 01-TMSS-01, latest Revision. (General Requirements of Material) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 5 – Single Line Diagram Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. 1 2 3 4 5 6 CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents: Single Line Diagram Documents which are required to be considered: PTS of project Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 7 SEED-II (SEC Engineering Drawings Standard) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 6 – Existing As-build drawing (If Required) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Detailed Route Plan for UG cable circuit 1 2 3 4 5 General Route Plan approved & stamped by survey & ROW Division. Approval of location of Terminal compound (if any) Approved/ As-built HV duct bank layout for the terminal substations Schematic drawing for UG cable circuit 7 8 Approval of Detailed route plan & Major materials As-built schematic drawing for existing circuit (if any) stamped by maintenance div. Documents which are required to be considered PTS of project Pre-bid clarifications of project 9 Post-bid clarifications of project 6 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 7 – HV Power Cables Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following Documents 6 Cross section view drawing of HV power cable stamped by the contractor as well as the manufacturer. Responsibility statement duly singed & stamped by the contractor as well as manufacturer Compliance statement as per National Grid SA standard & specification 01-TMSS-01, Rev.03 stamped by the contractor as well as the manufacturer. Compliance statement as per National Grid SA standard & specification 11-TMSS-02, Rev.02 stamped by the contractor as well as the manufacturer. Technical data schedule as per National Grid SA standard & specification 11-TMSS-02, Rev.02 stamped by the contractor as well as the manufacturer. Current rating calculation as per IEC 60287. 7 Manufacturer catalog of offer material 8 9 Documents which are required to be considered PTS of project. Post-bid clarifications of project 1 2 3 4 5 Standards which are required to be considered but not limited to mentioned below 10 11 01-TMSS-01, Rev.03 11-TMSS-02, Rev.02 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 8 – Power Cable Termination Kits (CSE) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main Documents 6 Detail A0 size drawings stamped by the contractor & manufacturer. Responsibility statement duly singed & stamped by the contractor as well as manufacturer Compliance statement as per National Grid SA standard & specification 01-TMSS-01, Rev.03 stamped by the contractor as well as the manufacturer. Compliance statement as per National Grid SA standard & specification 12-TMSS-10, Rev.02 stamped by the contractor as well as the manufacturer. Technical data schedule as per National Grid SA standard & specification 12-TMSS-10, Rev.02 stamped by the contractor as well as the manufacturer. Manufacturer catalog of offer material 7 8 9 10 Documents which are required to be considered PTS of project Post-bid clarifications of project The approved technical data schedule of HV power cable Approved Non-Linear Resistance for GIS termination 1 2 3 4 5 Standards which are required to be considered but not limited to mentioned below 11 12 01-TMSS-01, Rev.03 12-TMSS-10, Rev.02 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 9 – Power Cable Splice Kits Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main Documents 6 Detail A0 size drawings stamped by the contractor & manufacturer. Responsibility statement duly singed & stamped by the contractor as well as manufacturer Compliance statement as per National Grid SA standard & specification 01-TMSS-01, Rev.03 stamped by the contractor as well as the manufacturer. Compliance statement as per National Grid SA standard & specification 12-TMSS-10, Rev.02 stamped by the contractor as well as the manufacturer. Technical data schedule as per National Grid SA standard & specification 12-TMSS-10, Rev.02 stamped by the contractor as well as the manufacturer. Manufacturer catalog of offer material 7 8 9 Documents which are required to be considered PTS of project Post-bid clarifications of project The approved technical data schedule of HV power cable 1 2 3 4 5 Standards which are required to be considered but not limited to mentioned below 10 11 01-TMSS-01, Rev.03 12-TMSS-10, Rev.02 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 10 – Bare copper conductor and Grounding Rods Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents Cross-section Drawings for Bare copper conductor and Grounding Rods Responsibility statement duly singed & stamped by the contractor as well as manufacturer Compliance statement as per National Grid SA standard & specification 01-TMSS-01, Rev.03 stamped by the contractor as well as the manufacturer. Compliance statement as per National Grid SA standard & specification 10-TMSS-05, Rev.02 stamped by the contractor as well as the manufacturer. Technical data schedule as per National Grid SA standard & specification 10-TMSS-05, Rev.02 stamped by the contractor as well as the manufacturer. Manufacturer catalog of offer material Documents which are required to be considered PTS of project Calculation for Ground and bonding Cable/Conductor Sizing 1 2 3 4 5 6 7 8 Standards which are required to be considered but not limited to mentioned below 9 10 11 01-TMSS-01, Rev.03 10-TMSS-05, Rev.02 TES-P-104.08, Rev.02 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 11 – Bonding & Earthing Cable Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following document 7 8 Cross section view drawing of Bonding & Earthing Cable stamped by the contractor as well as the manufacturer. Responsibility statement duly singed & stamped by the contractor as well as manufacturer Compliance statement as per National Grid SA standard & specification 01-TMSS-01, Rev.03 stamped by the contractor as well as the manufacturer. Compliance statement as per National Grid SA standard & specification 11-TMSS-12, Rev.01 stamped by the contractor as well as the manufacturer. Technical data schedule as per National Grid SA standard & specification 11-TMSS-12, Rev.01 stamped by the contractor as well as the manufacturer. Manufacturer catalog of offer material Documents which are required to be considered PTS of project Post-bid clarifications of project 9 Calculation for Ground and bonding Cable/Conductor Sizing 1 2 3 4 5 6 Standards which are required to be considered but not limited to mentioned below 10 11 01-TMSS-01, Rev.03 11-TMSS-12, Rev.01 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 12 – Non-Linear Resistance for GIS termination Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following documents 5 6 Responsibility statement duly singed & stamped by the contractor as well as manufacturer Compliance statement as per National Grid SA standard & specification 01-TMSS-01, Rev.03 stamped by the contractor as well as the manufacturer. Approved calculation for Non-Linear Resistance for GIS terminations Manufacturer catalog of offer material Documents which are required to be considered PTS of project Calculations for Non-Linear Resistance for GIS terminations 7 Manufacturer’s recommendations 1 2 3 4 Standards which are required to be considered but not limited to mentioned below 8 9 01-TMSS-01, Rev.03 TES-P-119.41, Rev.00 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 13 – Link Box along with accessories Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents 7 Responsibility statement duly singed & stamped by the contractor as well as manufacturer Compliance statement as per National Grid SA standard & specification 01-TMSS-01, Rev.03 stamped by the contractor as well as the manufacturer. Compliance statement as per National Grid SA standard & specification 12-TMSS-11, Rev.01 stamped by the contractor as well as the manufacturer. Technical data schedule as per National Grid SA standard & specification 12-TMSS-11, Rev.01 stamped by the contractor as well as the manufacturer Dalit drawings for each type of Link Box stamped by the contractor as well as the manufacturer Manufacturer catalog of offer material Documents which are required to be considered PTS of project 8 Post-bid clarifications of project 1 2 3 4 5 6 Standards which are required to be considered but not limited to mentioned below 9 10 01-TMSS-01, Rev.03 12-TMSS-11, Rev.01 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 14 – Power Cable Clamps Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents 6 Responsibility statement duly singed & stamped by the contractor as well as manufacturer Compliance statement as per National Grid SA standard & specification 01-TMSS-01, Rev.03 stamped by the contractor as well as the manufacturer. Compliance statement as per National Grid SA standard & specification 23-TMSS-04, Rev.00 stamped by the contractor as well as the manufacturer. Technical data schedule as per National Grid SA standard & specification 23-TMSS-04, Rev.00 stamped by the contractor as well as the manufacturer Datil drawings for cable clamps stamped by the contractor as well as the manufacturer Manufacturer catalog for the proposed cable clamps 7 8 Documents which are required to be considered PTS of project Technical data of Power Cables 1 2 3 4 5 Standards which are required to be considered but not limited to mentioned below 9 10 01-TMSS-01, Rev.03 23-TMSS-04, Rev.00 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 15 – Cable Warning Tapes Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents/drawing sheets 1 Manufacture Catalogue 2 Drawing 3 4 Documents which are required to be considered PTS of project Pre-bid clarifications of project 5 Post-bid clarifications of project Standards which are required to be considered but not limited to mentioned below 6 7 8 TCS-P-104.03, Rev.0 TES-P-104.05, Rev.02 70-TMSS-04-R0 Cable Trench Materials BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 16 – Cable Protective Tiles Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents/drawing sheets 1 Manufacturer Catalogue 2 Drawing 3 4 Documents which are required to be considered PTS of project Pre-bid clarifications of project 5 Post-bid clarifications of project Standards which are required to be considered but not limited to mentioned below 6 7 8 TCS-P-104.03, Rev.0 TES-P-104.05, Rev.02 70-TMSS-04-R0 Cable Trench Materials BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 17 – Steel Wire Mesh Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents/drawing sheets 1 Manufacturer Catalogue 2 Drawing Documents which are required to be considered 3 4 PTS of project Pre-bid clarifications of project 5 Post-bid clarifications of project Standards which are required to be considered but not limited to mentioned below 6 7 8 TCS-P-104-03, Rev.0 TES-P-104.05, Rev.02 70-TMSS-04-R0 Cable Trench Materials BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 18 -Cable warning post Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents/drawing sheets 1 Plan, section and details of warning post 2 Manufacturer catalog of offer material 3 4 Documents which are required to be considered PTS of project Pre-bid clarifications of project 5 Post-bid clarifications of project Standards which are required to be considered but not limited to mentioned below 6 01-TMSS-01 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 19 – Duct Sealing Units Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents/drawing sheets 1 Filled Data Schedule of Duct Sealing Units as per 23-TMSS-02 2 3 4 5 Compliance Statements 6 7 Manufacturer's Responsibility supported drawings Approved PVC Conduits and Fittings Documents which are required to be considered PTS of project Pre-bid clarifications of project 8 Post-bid clarifications of project Standards which are required to be considered but not limited to mentioned below 9 10 01-TMSS-01 23-TMSS-02 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 20 – Technical submittal for HV Cable Trays (Cable Supports) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main calculation sheets 1 2 Filled data schedule of 24-TMSS-01 from the manufacturer HV cable Raceway layout drawing with plan and detailed sections 3 Copy of approved HV cable sleeves & Duct bank layout 4 5 Documents which are required to be considered PTS of project Pre-bid clarifications of project 6 Post-bid clarifications of project 7 Tender drawings requirements of project 8 Approved Calculation for cable tray (cable support) 9 Manufacturer’s Catalogues for support and accessories Drawings of the cable raceways supports and accessories from the manufacturer with proper model number Clause by clause compliance to specification 24-TMSS-01 10 11 Standards which are required to be considered but not limited to mentioned below 12 13 24-TMSS-01 TES-P-104.05 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 21 – PVC Conduits and Fittings Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main documents/drawing sheets PVC Conduits and Fittings Technical specifications as per 23TMSS-01 Compliance Statements 1 2 3 4 5 6 Manufacturer's Responsibility supported drawings Documents which are required to be considered PTS of project Pre-bid clarifications of project 7 Post-bid clarifications of project 8 HV Power Cables Technical data Standards which are required to be considered but not limited to mentioned below 9 10 01-TMSS-01 23-TMSS-01 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 22 – Ventilation System for Power Cables to be Laid in Tunnel Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following items 1 Introduction 2 Codes & Standards 3 Environmental Design Criteria 4 Sequence of Operation for the ventilation system 5 Approved civil/architectural drawings 6 Cable heat dissipation based on the actual number cables 7 Tunnel light heat dissipation based on the actual lighting fixtures 8 Ventilation calculations for fans based on air changed method and heat dissipation method 9 Duct sizing, air outlet sizing and external static pressure calculations 10 Ventilation General Notes and Legends drawing 11 Ventilation Duct and Equipment Layout – Basement 12 Ventilation Duct and Equipment Layout – Ground Floor 13 Ventilation Duct and Equipment Layout- Sectional Details 14 Ventilation control and schematic Layout 15 Equipment Schedule 16 Miscellaneous, Installation Details and Schedules 17 Selection of fans using catalog/software from the fans manufacturer 18 Selection of air outlets and other materials by properly highlighting the model number in the manufacturer’s Catalogues 19 20 Documents which are required to be considered PTS of project Pre-bid clarifications of project 21 Post-bid clarifications of project 22 Tender drawings requirements of project Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Standards which are required to be considered but not limited to mentioned below 23 24 TES-K-100.01 73-TMSS-05 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 23 – Temperature monitoring system of Tunnel (If Required) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following items 1 2 3 Tunnel diagram showing quantity and location of temperature monitoring devices Control and Schematic Diagram for the operation of ventilation system in response to the temperature sensed by the temperature monitoring devices. 5 6 Approved civil/architectural drawings Selection of temperature monitoring devices by properly highlighting the model number in the manufacturer’s Catalogues Documents which are required to be considered PTS of project Pre-bid clarifications of project 7 Post-bid clarifications of project 8 Tender drawings requirements of project 4 Standards which are required to be considered but not limited to mentioned below 9 TES-K-100.01 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 24 – Plumbing system of tunnel (If Required) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following items 1 Introduction 2 Codes & Standards 3 Design Parameters 4 Total dynamic Head calculation of pump 5 References 6 Approved civil/architectural Drawings 7 Plumbing General Notes and Legends Drawing 8 Pumps and Piping Layout including isometric 9 Plumbing Equipment Schedule 10 Plumbing Miscellaneous and installation Details 11 Selection of pumps provided by the pump manufacturer 12 Sequence of operation and control panel for the pump Documents which are required to be considered 13 PTS of project 14 Pre-bid clarifications of project 15 Post-bid clarifications of project 16 Tender drawings requirements of project Standards which are required to be considered but not limited to mentioned below 17 TES-P-119.19 18 83-TMSS-01 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 25 - KEY PLAN OF POWER CABLES ROUTE Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Single Line Diagram 2 Google Earth files to verify GPS coordinates of cable route 3 Test Pit Location identification on the key plan (approval) 4 Test Pit/Radar scanning details results 5 Existing As-build drawing (If Required) (approval) Submittal will contain following main Documents 6 No Objection certificates from all concerned authorities 7 HV Power Cables (approval) 8 Key plan of power cables route (Drawing showing route of the propose line, existing utilities / highways & roads crossing (within the R.O.W of the proposed cable route), start & end points and intersection points.) Documents which are required to consider for cable route: 9 PTS of project 10 Pre-bid clarifications of project 11 Post-bid clarifications of project 12 Tender drawings requirements of project 13 Additional Requirements (if any) Standards which are required to consider in general but not limited to mentioned below 14 SEED-II (SEC Engineering Drawings Standard) 15 TES-P-122-08-R1 (Survey Guidelines) Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 26 - PLAN & PROFILE DETAILS Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Single Line Diagram 2 Key plan of power cables route (approval) 3 Google Earth files to verify GPS coordinates of cable route 4 Test Pit/Radar scanning details results 5 Existing As-build drawing (If Required) (approval) Submittal will contain following main Documents 6 7 HV Power Cables (approval) Plan & profile details (Profile of cables circuits with necessary sections, Elevations and Details, crossings, utilities, spacing (splicing) points, location of link Boxes for cable sheath.) Documents which are required to consider for plan & profile: 8 PTS of project 9 Additional Requirements (if any) Standards which are required to consider in general but not limited to mentioned below 10 SEED-II (SEC Engineering Drawings Standard) 11 TES-P-122-08-R1 (Survey Guidelines) BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 27 - CABLE ENTRY PLAN Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Approved Substation Layout Drawing for reference 2 Approved overall Building plan view drawing with detail of MV & HV cable Raceway system for reference. 3 Approved Key plan of power cables route for reference 4 Approved Plan & profile details for reference 5 6 Approved Power Cables Termination Arrangement, Termination Plan, Sections/Details. Approved calculation for cable tray (cable support) (Loading calculation for cable trays & Support) Submittal will contain following main Documents 7 Cable Entry Plan (Power cable entry arrangement at substations showing arrangement of cable and GIS termination in basement or outdoor termination.) 8 Approved HV Power Cables 9 Approved HV Cable Trays (Cable Support) 10 Approved Power Cable Clamps 11 Approved Power Cable Termination Kits (CSE) 12 Approved Duct Sealing Units 13 Approved Fire Proofing Material to Protect the Cable in Cable entry room or Basement Documents which are required to consider for cable Entry Plan: 14 PTS of project 15 Pre-bid clarifications of project 16 Post-bid clarifications of project 17 Tender drawings requirements of project 18 Additional Requirements (if any) Standards which are required to consider in general but not limited to mentioned below 19 SEED-11 (SEC Engineering Drawings Standard) Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 28 - TEST PIT LOCATION IDENTIFICATION ON THE KEY PLAN Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Single Line Diagram 2 Key Plan Of Power Cables Route 3 Test Pit Location identification on the key plan (Identifying the location of test pits on the proposed power cable route to determine the existing utilities/power cables.) Documents which are required to consider for Test Pit Location: 4 PTS of project 5 Pre-bid clarifications of project 6 Post-bid clarifications of project 7 Additional Requirements (if any) Standards which are required to consider in general but not limited to mentioned below 8 SEED-11 (SEC Engineering Drawings Standard) 9 TES-P-122-08-R1 (Survey Guidelines) BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 29 - TEST PIT/RADAR SCANNING DETAILS RESULTS Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Single Line Diagram 2 Approved Test pit location identification on the key plan 3 Test Pit/Radar scanning details results (Test pit result shall show the location of proposed power cable & indicate clearance of all existing utilities from the proposed power cable as per NGrid SA standard.) Standards which are required to consider in general but not limited to mentioned below 4 SEED-11 (SEC Engineering Drawings Standard) 5 TES-P-122-08-R1 (Survey Guidelines) 6 TES-P-104-05-R2 (Cable Installations, Engineering Requirements) BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 30 - HORIZONTAL DIRECTIONAL DRILLING (HDD) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Approved Key Plan Of Power Cables Route Submittal will contain following main Documents 3 Horizontal Directional Drilling (HDD) (Drawing Showing location and depth of HDD as per approved key plan of power cable route and cross sectional drawing along with Method Statement for HDD.) HV Power Cables 4 PVC Conduits and Fittings 5 Duct Sealing Units 2 Standards which are required to consider in general but not limited to mentioned below 6 SEED-11 (SEC Engineering Drawings Standard) 7 TES-P-104-05-R2 (Cable Installations, Engineering Requirements) 8 TA800068-R0 (Highway Under Crossing for 110kV to 380kV U-G Power Cables by Directional Drilling) 9 TES-P-122-08-R1 Survey Guidelines BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 31 – Ventilation System for Power Cables to be Laid in Tunnel (Drawings) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 HVAC Duct Layout 2 3 Supply and Exhaust Fan Layout Equipment Schedule 4 Notes & Legends Drawing 5 Installation Details drawing 6 Sectional details drawings 7 8 Documents which are required to be considered PTS of project Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Manufacturer’s Catalogues Standards which are required to be considered but not limited to mentioned below 12 13 14 TES-K-100.01 73-TMSS-05 TCS-K-100 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 32 – Temperature Monitoring System of Tunnel (If required) “Drawings” Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 3 Control and Schematic Diagram Tunnel diagram showing location of temperature monitoring devices Documents which are required to be considered PTS of project 4 Pre-bid clarifications of project 5 Post-bid clarifications of project 6 Tender drawings requirements of project 7 Manufacturer’s Catalogues 2 Standards which are required to be considered but not limited to mentioned below 8 TES-K-100.01 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 33 – Plumbing System of Tunnel (If Required) “Drawings” Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 Pumps and Piping Layout 2 Equipment Schedule 3 Plumbing Details 4 Notes & Legends Drawing 5 Installation Details Drawing 6 7 8 Sectional Details Drawings Documents which are required to be considered PTS of project Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Manufacturer’s Catalogues Standards which are required to be considered but not limited to mentioned below 12 TES-P-119.19 13 83-TMSS-01 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 34 -POWER CABLES TERMINATION ARRANGEMENT, TERMINATION PLAN, SECTIONS DETAILS Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Approved Substation Layout Drawing for reference 2 Approved Cable Entry Plan Submittal will contain following main Documents 3 4 5 6 Power Cables Termination Arrangement, Termination Plan, Sections/Details (Termination arrangement with necessary sections and details) HV Power Cables Approved Power Cable Clamps Approved Power Cable Termination Kits (CSE) Approved Documents which are required to consider for cable Termination Arrangement: 7 Additional Requirements (if any) Standards which are required to consider in general but not limited to mentioned below 8 SEED-11 (SEC Engineering Drawings Standard) BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cables Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 35 - CABLE SAGGING/SNAKING & JOINT BAY DETAILS Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Single Line Diagram 2 Approved Test Pit/Radar scanning details results (approval) 3 Approved Key Plan Of Power Cables Route 4 Approved Schematic Drawing & Bonding Submittal will contain following main Documents 5 Cable Sagging/Snaking & Joint Bay Details (Detail layout drawing of cable sagging/snaking, link box, joints and grounding arrangement at joint bay.) 6 Approved HV Power Cables 7 Approved Bonding & Earthing Cable 8 Approved Bare copper conductor and Grounding Rods 9 Approved Link Box along with accessories 10 Approved Power Cable Splice Kits Standards which are required to consider in general but not limited to mentioned below 11 SEED-II (SEC Engineering Drawings Standard) 12 TES-P-122-08-R1 (Survey Guidelines) 13 TA800142 R0 (Installation Detail for Link Boxes Below Ground 110 kV, 115 kV, 132 kV, 230 kV And 380 kV) 14 TA800141 R0 (Installation Detail for Link Boxes above Ground) Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 36 -Remote-End Modification (If required) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 2 Approved Key Plan Of Power Cables Route Modification at Remote End substation showing all work to be done including, adding/utilizing CBs (including JIB if applicable),adding/modifying control/protection/communication etc. Documents which are required to consider for cable Entry Plan: 3 PTS of project 4 Pre-bid clarifications of project 5 Post-bid clarifications of project 6 Tender drawings requirements of project 7 Additional Requirements (if any) BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 37 - SOIL THERMAL RESISTIVITY MEASUREMENTS REPORT ALONG CABLES ROUTE Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Approved Key Plan Of Power Cables Route 2 Approved Test Pit Location identification on the key plan 3 Approved Test Pit/Radar scanning details results 4 Soil Thermal Resistivity Measurements Report along cables route (Soil Thermal Resistivity Measurements measurement report along the cable route.) Standards which are required to consider in general but not limited to mentioned below 5 SEED-II (SEC Engineering Drawings Standard) 6 TES-P-122-08-R1 (Survey Guidelines) BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 38 – CIVIL DESIGN PHILOSOPHY, STANDARDS, CODES, DESIGN BASIS AND DESIGN DATA Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following Drawing sheets and Calculations. Document providing description of project, design philosophy design parameters , Standards and Codes etc. 1 Documents which are required to be considered. 2 3 4 5 6 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Manufacturer / Supplier’s recommendations Standards which are required to be considered but not limited to mentioned below. 7 8 9 10 11 12 13 01-TMSS-01 70-TMSS-03 TES-P-122.06 TES-P-119.18 TES-P-119.19 TCS-P-122.05 TCS-Q-113.02 BY SIGNING BELOW: 1. Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 39 – CONCRETE MIX DESIGN Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Report providing Concrete Mix design for all Structural Concrete Works e.g. (Mix design of each mix type/strength, gradation, aggregate test report, water analysis report, cement mill certificates, admixture data, Batching plant calibration report, Compressive strength test report (7 & 28 days) for final approval for each type concrete trail mix etc.) 2 Geotechnical Investigation Report approval copy. Documents which are required to be considered. 3 4 5 6 7 8 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Manufacturer / Supplier’s recommendations Geotechnical Investigation Report. Standards which are required to be considered but not limited to mentioned below. 9 10 01-TMSS-01 70-TMSS-03 BY SIGNING BELOW: 1. Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 40 – ASPHALT MIX DESIGN Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Report providing details of asphalt mix design procedure and test results of the constituents materials. 2 Key plan of Power cables Route approval copy. Documents which are required to be considered. 3 4 5 6 7 8 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Manufacturer / Supplier’s recommendations Key plan of Power cables Route. Standards which are required to be considered but not limited to mentioned below. 9 10 11 01-TMSS-01 TCS-Q-113.01 TCS-Q-113.02 BY SIGNING BELOW: 1. Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 41 – GEOTECHNICAL INVESTIGATION REPORT Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following Drawing sheets and Calculations. Report providing details of soil investigation, soil properties and recommendations for foundation Design Bore Hole Location Plan and Method Statement for Soil Investigation approval copy 1 2 3 Key plan of Power cables Route approval copy. Documents which are required to be considered. PTS of Project. 4 5 6 7 8 Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Key plan of Power cables Route Bore Hole Location Plan and Method Statement for Soil Investigation. 9 Standards which are required to be considered but not limited to mentioned below. TES-P-122.06 TCS-Q-113.02 70-TMSS-03 TES-P-122.11 10 11 12 13 BY SIGNING BELOW: 1. Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 42 – DETAILED CABLE AMPACITY CALCULATIONS Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal shall contain the following 7 8 Cable Ampacity calculations meeting project requirements as per SOW/TS under all types of cable installations (direct buried, concrete duct bank, Horizontal directional drilling) Cross Sections for all types of cable installations (direct buried, CDB, HDD) & crossings with existing utilities for complete Cable route (Test Pit Results) Soil Thermal Resistivity Measurements Report along with measurement locations drawing Approved Technical Data Schedule for Power Cable specifications Parameters/assumptions considered in the Ampacity calculations Mitigations/solutions for portions where minimum ampacity requirements could not be achieved. Documents which are required to be considered PTS of project Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Manufacturer’s recommendations 1 2 3 4 5 6 Standards which are required to be considered but not limited to mentioned below 12 IEC-60287 BY SIGNING BELOW: 1. Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 43 – Calculations for sheath standing voltage, sheath voltage rise and the Selection of Sheath Voltage Limiters (SVL). Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal shall contain the following 1 2 3 Approved Cable Ampacity calculations Induced Sheath Voltage calculations based on sheath/screen bonding scheme indicated in SOW/TS under normal & fault conditions Phase to Phase & Phase to Ground (sectionalized cross bonding & single point bonding system) for all types of cable installations (Direct buried, CDB & HDD) 7 8 Calculation for minor section length selection Reference Catalogue for selected SVL Signed, dated, and stamped Compliance statement (01-TMSS-01) with no deviations for selected SVL Signed, dated, and stamped Manufacturer’s responsibility statements for selected SVL Documents which are required to be considered PTS of project Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Manufacturer’s recommendations 4 5 6 Standards which are required to be considered but not limited to mentioned below 12 13 14 15 16 IEEE 575 Electra (28) Electra (47) Electra (128) CIGRE Brochure (283) Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 44 – CABLE METTALIC SHEATH SIZING & FAULT CURRENT WITHSTAND CAPABILTY Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal shall contain the following Design Calculation for Cable Metallic Sheath Sizing based on short circuit current of 40 kA for 1 second Formula/References considered in the calculation 1 2 3 4 5 Parameters/assumptions considered in the calculation Documents which are required to be considered PTS of project Pre-bid clarifications of project 6 Post-bid clarifications of project 7 Tender drawings requirements of project 8 Manufacturer’s recommendations Standards which are required to be considered but not limited to mentioned below 9 10 11 11-TMSS-02 ICEA P-45-482 IEC-60949 (Calculation of thermally permissible short-circuit) BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 45 – GROUNDING/BONDING CABLE SIZING CALCULATION Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal shall contain the following Grounding/Bonding Cable cross-section Sizing Calculation for ultimate fault current (40kA for 1 second) Formula/References considered in the calculation 1 2 3 4 5 Parameters/assumptions considered in the calculation Documents which are required to be considered PTS of project Pre-bid clarifications of project 6 Post-bid clarifications of project 7 Tender drawings requirements of project 8 Manufacturer’s recommendations Standards which are required to be considered but not limited to mentioned below 9 10 11 12 11-TMSS-12 TES-P-104.08 ICEA P-45-482 IEC 60949 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 46 – CALCULATION FOR NON-LINEAR RESISTANCE FOR GIS TERMINATION Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal shall contain the following 1 Non-linear resistance sizing calculations 2 Formula/References considered in the calculation 3 4 7 8 Parameters/assumptions considered in the calculation Reference Catalogue for selected Non-linear Resistor Signed, dated, and stamped Compliance statement (01-TMSS-01) with no deviations for selected Non-linear Resistor Signed, dated, and stamped Manufacturer’s responsibility statements for selected Non-linear Resistor Documents which are required to be considered PTS of project Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Manufacturer’s recommendations 5 6 Standards which are required to be considered but not limited to mentioned below 12 13 14 TES-P-119.41 12-TMSS-10 12-TMSS-11 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 47 – CIRCULATING CURRENT CALCULATION Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal shall contain the following 1 Approved Technical Data Schedule for Power Cable specifications 2 Approved Cable Ampacity calculations 3 Approved Induced voltage calculation 4 5 6 Circulating current calculations Documents which are required to be considered PTS of project Pre-bid clarifications of project 7 Post-bid clarifications of project 8 Tender drawings requirements of project 9 Manufacturer’s recommendations Standards which are required to be considered but not limited to mentioned below 10 11 TES-P-104.08 IEC-60287 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 48 – CABLE PULLING TENSION & SIDEWALL PRESSURE CALCULATION Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal shall contain the following Cable Pulling Tensions and Sidewall Pressure Calculations with consideration of pulling from whichever direction that minimize the pulling tensions and sidewall pressures Approved Technical Submittal for HV Cables 1 2 5 6 Approved proposed Cable Route Drawing for Each Minor Section with shown cable’s length and bending angles Documents which are required to be considered PTS of project Pre-bid clarifications of project 7 Post-bid clarifications of project 8 Tender drawings requirements of project 9 Manufacturer’s recommendations 3 4 Standards which are required to be considered but not limited to mentioned below 10 11 TES-P-104.05 TCS-P-104.06 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 49 – Ventilation System Design & Calculation for Power Cable to be laid in Tunnel (Calculations) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main calculation sheets 1 Calculation for Air Volume Flow Rate by Number Air Changes Method (ACH) and by Heat Balance Method 2 Design Basis 3 Design Parameters 4 External Static Pressure Calculation (If Required) 5 6 7 References Documents which are required to be considered PTS of project Pre-bid clarifications of project 8 Post-bid clarifications of project 9 Tender drawings requirements of project 10 Manufacturer’s Catalogues Standards which are required to be considered but not limited to mentioned below 11 TES-K-100.01 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 50 – Calculation for Cable Tray (Cable Support) (Loading Calculation for Cable Trays & Support) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main calculation sheets 1 Calculation of weight/load of cables on the cable trays/supports to justify load bearing capability 2 Calculation of filling capacities if required 3 4 5 Calculation of deflection of cable Trays/supports Documents which are required to be considered PTS of project Pre-bid clarifications of project 6 Post-bid clarifications of project 7 Tender drawings requirements of project 8 Approved cable tray/support layout 9 Manufacturer’s Catalogues Standards which are required to be considered but not limited to mentioned below 10 11 24-TMSS-01 TES-P-104.05 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 51 – Plumbing System of Tunnel (If Required) (Calculations) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main calculation sheets 1 Pipe sizing calculation 2 Total Dynamic Head Calculation for submersible pump selection 3 References 4 5 6 Plumbing Drawings ( Including isometric & Sectional Details) Documents which are required to be considered PTS of project Pre-bid clarifications of project 7 Post-bid clarifications of project 8 Tender drawings requirements of project 9 Manufacturer’s Catalogues Standards which are required to be considered but not limited to mentioned below 10 TES-P-119.19 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 52 – DESIGN CALCULATIONS AND DRAWINGS FOR LINK BOX FOUNDATION Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 Approved Soil Investigation Report. 2 3 4 Approved Technical Submittal for link box Design Analysis & Calculation of link box foundation Structural drawings & Fixing connection details 5 6 Documents which are required to be considered PTS of project Pre-bid clarifications of project 7 Post-bid clarifications of project 8 Tender drawings requirements of project 9 10 11 Manufacturer’s recommendations Soil Investigation Report Technical Submittal for link box Standards which are required to be considered but not limited to mentioned below 12 13 14 TES-P-119.19 TA-800141 TA-800142 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 53 – DESIGN CALCULATIONS AND DRAWINGS FOR DUCT BANKS IN TRAFFIC AREAS AND ROAD CROSSINGS Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Approved Soil Investigation Report. 2 Approved Key plan of Power cables Route 3 Approved Plan & profile details 4 Design Analysis & Calculation 5 Structural drawings with reinforcement details Documents which are required to be considered 6 PTS of project 7 Pre-bid clarifications of project 8 Post-bid clarifications of project 9 Tender drawings requirements of project 10 Soil Investigation Report 11 Key plan of Power cables Route 12 Plan & profile details 13 Manufacturer’s recommendations Standards which are required to be considered but not limited to mentioned below 14 TES-P-119.19 15 TA-800062 16 TA-800140 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 54 – DESIGN CALCULATIONS AND DRAWINGS FOR HANDHOLES/MANHOLES Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 Approved Soil Investigation Report. 2 Approved Key plan of Power cables Route 3 4 5 Approved Plan & profile details Design Calculation for hand holes/manholes Drawings for plan, sections & reinforcement details 6 7 Documents which are required to be considered PTS of project Pre-bid clarifications of project 8 Post-bid clarifications of project 9 Soil Investigation Report 10 Key plan for Power Cable Route Standards which are required to be considered but not limited to mentioned below 11 12 13 14 15 16 TES-P-119.19 TA-800096 TA-800097 TA-800098 TA-800140 TB-800077 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 55 – DESIGN CALCULATION AND DRAWINGS FOR CSE STEEL SUPPORTING STRUCTURE Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 Approved Equipment- Cable Sealing End (CSE) 2 Approved Key plan of Power cables Route 3 4 5 6 Approved Plan & profile details Approved transition Area layout Design Calculations of Steel support Structure Structural drawings for steel support structure 7 8 Documents which are required to be considered PTS of project Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Manufacturer's Recommendation 11 Key plan of Power cables Route 12 Plan & profile drawing and details 13 Transition Area layout Standards which are required to be considered but not limited to mentioned below 14 15 16 TES-P-119.09 TES-P-119.19 TES-P-122.05 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 56 – DESIGN CALCULATIONS AND DRAWINGS FOR CSE FOUNDATION Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Approved Equipment- Cable Sealing End (CSE) 2 Approved Key plan of Power cables Route 3 Approved Plan & profile details 4 Approved transition Area layout 6 Approved Design Calculations of Steel support Structure for CSE & drawings Approved Soil Investigation Report 7 Design Calculations for foundation for CSE 8 Foundation drawings with reinforcement details 9 Site Grading and Paving Plan for Transition area approval Copy 5 Documents which are required to be considered 10 PTS of project 11 Pre-bid clarifications of project 12 Post-bid clarifications of project 13 Key Plan for Power Cable Route 14 Plan and Profile Drawings and Details 15 Transition Area Layout 16 Design Calculations for CSE support structure 17 Design calculations and drawings of foundations of any other relevant out door structure in transition area. 18 Site Grading and Paving Plan for Transition area. 19 Soil Investigation Report Standards which are required to be considered but not limited to mentioned below 20 21 TES-P-119.18 TES-P-122.06 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 57 – DESIGN CALCULATIONS AND DRAWINGS OF CABLE TRENCH AND PRECAST CONCRETE COVER Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Approved Key plan of Power cables Route 2 Approved Plan & profile details 3 Approved transition Area layout 4 Approved Soil Investigation Report 5 Design Calculations for cable trench and precast cover 6 7 Drawings for cable trench and precast cover with reinforcement details Site Grading and Paving Plan for Transition area approval Copy. Documents which are required to be considered 8 PTS of project 9 Pre-bid clarifications of project 10 Post-bid clarifications of project 11 Key Plan for Power Cable Route 12 Transition Area Layout 13 Site Grading and Paving Plan for Transition area. 14 Soil Investigation Report Standards which are required to be considered but not limited to mentioned below 15 TES-P-119.19 16 TCS-P-104.03 17 TA-800140 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 58 – CRASH BARRIER Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 Approved Key plan of Power cables Route 2 5 6 Approved Plan & profile details Drawings showing the details (pipe detail, foundation detail for steel pipe crash barrier, paint detail) of the crash barriers. Approved Drawings/list showing location and type of crash barriers along the transmission line route. Documents which are required to be considered PTS of project Pre-bid clarifications of project 7 Post-bid clarifications of project 8 Key Plan for Power Cable Route Drawings / list showing location and type of crash barriers along the transmission line route. 3 4 9 Standards which are required to be considered but not limited to mentioned below 10 11 TA-800133 TES-H-107.01 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 59 – DESIGN CALCULATION AND DRAWINGS FOR CABLE TUNNEL Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 Approved Key plan of Power cables Route 2 Approved Plan & profile details 3 6 7 8 Approved Layout for transition Area Design Calculations for Cable Tunnel Drawings for cable tunnel Plan, sections & details of reinforcement Soil Investigation Report Approval Copy Key Plan and Electrical Layout of the Cable Tunnel Approval Copy. Mechanical and Plumbing Design of Cable Tunnel Approval Copy. 9 10 Documents which are required to be considered PTS of project Pre-bid clarifications of project 11 Post-bid clarifications of project 12 Key Plan for Power Cable Route 13 Soil Investigation Report 4 5 Standards which are required to be considered but not limited to mentioned below 14 15 TES-P-119.19 TCS-Q-113.02 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 60 – SCHEME DRAWING & BONDING Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal shall contain the following 2 3-Phase Schematic drawing showing the transposition of power cable & bonding/grounding arrangement of power cable sheath, details of minor and major sections of the cross bonded/single point bonded scheme. Details of the induced voltage for every major and minor section during steady state & transient condition. Approved Induced Sheath Voltage calculations 3 4 Approved Calculation for minor section length selection Approved Key plan of Power cables Route 5 6 Documents which are required to be considered PTS of project Manufacturer’s recommendations 1 Standards which are required to be considered but not limited to mentioned below 7 8 9 10 11 TES-P-104.08 IEEE 575 Electra (28) & Electra (47) Electra (128) CIGRE Brochure (283) BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cables Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 61 – LINKBOX LOCATIONS PLAN, SECTIONS AND DETAILS Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal shall contain the following 2 Complete route drawing showing locations of link boxes with necessary sections and details of installing the link box underground/above ground Approved Cable Sagging/Snaking & Joint Bay Details 3 4 Approved Cable Sheath Bonding Scheme Approved Key plan of Power cables Route 1 Documents which are required to be considered 5 6 PTS of project Pre-bid clarifications of project 7 Post-bid clarifications of project 8 Manufacturer’s recommendations Standards which are required to be considered but not limited to mentioned below 9 TES-P-104.08 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cables Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 62 – BORE HOLE LOCATION PLAN AND METHOD STATEMENT FOR SOIL INVESTIGATION Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 Approved Key plan of Power cables Route 2 4 5 Approved Plan & profile details Bore hole location Drawings and Method Statement for soil investigation Documents which are required to be considered PTS of project Pre-bid clarifications of project 6 Post-bid clarifications of project 3 Standards which are required to be considered but not limited to mentioned below 7 8 TES-P-119.19 TCS-Q-113.02 BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS 63 – GENERAL CIVIL/STRUCTURAL NOTES (SPECIFICATIONS OF CONCRETE, STEEL REINFORCEMENTS, FORMWORK, EARTHWORK ETC.) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 General Civil/Structural Notes (Specification of Concrete, Steel Reinforcement, Formwork, Earthwork etc.) 2 Civil Design Philosophy approval copy. 3 Concrete Mix Design approval copy 4 Soil Investigation Report Approval Copy Documents which are required to be considered 5 PTS of project 6 Civil Design Philosophy. 7 Concrete Mix Design. 8 Soil Investigation Report. Standards which are required to be considered but not limited to mentioned below 9 TES-P-119.19 10 TCS-Q-113.02 11 TCS-Q-113.03 12 70-TMSS-03 13 01-TMSS-01 14 TES-P-119.18 15 TCS-P-122.05 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV UNDERGROUND CABLE PROJECTS BY SIGNING BELOW: 1-Contractor grantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Underground Cable Projects, Rev. 00 E&DD © 2019 Page 2 of 2 HV TRANSITION AREA CHECK LIST TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 1 –Technical Submittal for Conductor Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets: 1 Cross Sectional drawing of Conductor 2 Drawing of the drum 3 4 Submittal will contain following main documents: Technical Data schedule Manufacturer responsibility Statement 5 Material Compliance statements for the applicable standards 6 Type test report/Certificate. 7 8 9 10 11 Documents which are required to be considered: PTS of project Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 12 01-TMSS-01, latest Revision. (General Requirements of Material) 13 10-TMSS-01, latest Revision. (Bare Conductors) 10-TMSS-06, latest Revision. ( Heat Resistant Aluminum Alloy Conductors) 14 BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 2-Technical Submittal for Take-off/gantry Material Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets: 1 Approved gantry design / outline drawings 2 Shop and Erection drawings of gantry structure 6 7 Submittal will contain following main documents: Technical Data schedule Manufacturer responsibility statement Material compliance statements for the applicable standards Documents which are required to be considered: PTS of project Pre-bid clarifications of project 8 Post-bid clarifications of project 9 Tender drawings requirements of project 10 Additional Requirements (if any) 3 4 5 Standards which are required to be considered but not limited to mentioned below: 11 12 13 14 15 01-TMSS-01, latest Revision. (General Requirements of Material) 20-TMSS-01, latest Revision. ( Steel Structures) TES-P-122.05 (part I &II), latest revision. (Transmission Line Structures) TES-P-119.08 latest revision, (Clearances) TES-P-119.09 latest revision, (Bus bars & Support Structures) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 3 –Technical Submittal for Insulators Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets: 1 Technical drawings of Insulator Submittal will contain following main documents: 2 Technical Data schedule 3 4 5 Manufacturer responsibility statement Material compliance statements for the applicable standards Type test report/Certificate. Documents which are required to be considered: 6 PTS of project 7 8 9 10 Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 11 12 13 14 15 16 17 01-TMSS-01, latest Revision. (General Requirements of Material) 15-TMSS-01, latest Revision. (Post Insulator) 15-TMSS-02, latest Revision. (Suspension Insulator) 15-TMSS-03, latest Revision. ( Horizontal Post Insulator) 15-TMSS-04, latest Revision. (Porcelain Long Rod Insulator) 15-TMSS-05, latest Revision. (Composite Insulator) 15-TMSS-06, latest Revision. (Composite Station Post Insulator) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <Contractor’s Name> <NG Project Representative> <Project Manager’s Name> <Project Manager’s Name> Signature & Stamp Signature Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 4 –Technical Submittal for Insulator String Fittings, Vibration Dampers and Hardware Assembly Details Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following main drawing sheets: 1 Detail Hardware Assembly drawings for insulator strings. 2 Detail drawings of all fittings and its parts. Submittal will contain following main documents: 3 Technical Data schedule 4 Manufacturer responsibility statement 5 Material compliance statement for the applicable standards 6 Type test report/Certificate. Documents which are required to be considered: 7 PTS of project 8 Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below 12 01-TMSS-01, latest Revision. (General Requirements of Material) 13 12-TMSS-01, latest Revision. (Line Hardware) 12-TMSS-02, latest Revision. (Compression Type Connectors for OHTL) TES-P-122.04, latest Revision. (Line Hardware and fittings for Conductor & OPGW) 14 15 16 17 TCS-P-122.07, latest Revision. (Conductor & OGW Installation). TCS-P-122.21, latest Revision. (Transmission Line Structure Details). Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature & Stamp Signature Rev No. Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 5 – Technical Submittal for OPGW Fittings ,Vibration Dampers & Hardware Assembly Details Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following main drawing sheets: 1 Detail Hardware Assembly drawings for insulator strings. 2 Detail drawings of all fittings and its parts. Submittal will contain following main documents: 3 Technical Data schedule 4 Manufacturer responsibility statement 5 Material compliance statement for the applicable standards 6 Type test report/Certificate. Documents which are required to be considered: 7 PTS of project 8 Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 12 13 14 15 16 17 01-TMSS-01, latest Revision. (General Requirements of Material) 12-TMSS-01, latest Revision. (Line Hardware) 12-TMSS-02, latest Revision. (Compression Type Connectors for OHTL) TES-P-122.04, latest Revision. (Line Hardware and fittings for Conductor & OPGW) TCS-P-122.08, latest Revision. (OPGW Installation). TCS-P-122.21, latest Revision. (Transmission Line Structure Details). Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 6 – Technical Submittal for Connectors Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets: 1 Detail drawings of Connectors. Submittal will contain following main documents: 2 3 4 5 Technical Data schedule Manufacturer responsibility statement Material compliance statement for the applicable standards Type test report/Certificate. 6 7 8 9 10 Documents which are required to be considered: PTS of project Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 11 12 13 14 01-TMSS-01, latest Revision. (General Requirements of Material) 12-TMSS-02, latest Revision. (Compression Type Connectors for OHTL) TES-P-122.04, latest Revision. (Line Hardware and fittings for Conductor & OPGW) TCS-P-122.21, latest Revision. (Transmission Line Structure Details). BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 7 –Technical Submittal for OPGW Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets: 1 Cross Sectional drawing of OPGW 2 Drawing of the drum Submittal will contain following main documents: 3 4 5 6 Technical Data schedule Manufacturer responsibility Statement Material Compliance statements for the applicable standards Type test report/Certificate. 7 8 Documents which are required to be considered: PTS of project Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 12 13 01-TMSS-01, latest Revision. (General Requirements of Material) 10-TMSS-04, latest Revision. (Optical Power Ground Wire) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 8 –Technical Submittal for Grounding Materials (including Grounding Conductor & Grounding Rod) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets: 1 Cross Sectional drawing of Conductor 2 Drawing of the drum 3 Detailed drawing of grounding rod Submittal will contain following main documents: 4 5 6 7 Technical Data schedule Manufacturer responsibility Material compliance statement for the applicable standards Type test report/Certificate. 8 9 10 11 12 Documents which are required to be considered: PTS of project Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 13 14 15 01-TMSS-01, latest Revision. (General Requirements of Material) 10-TMSS-05, latest Revision. (Grounding conductor & Rod) TES-P-122.04, latest revision. (Line Hardware) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 9 –Technical submittal for Surge arrestor Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets: 1 Detailed drawing of Surge Arrestor Submittal will contain following main documents: 2 3 4 5 Technical Data schedule Manufacturer responsibility Material compliance statement for the applicable standards Type test report/Certificate. 6 7 8 9 10 Documents which are required to be considered: PTS of project Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 11 12 13 01-TMSS-01, latest Revision. (General Requirements of Material) 35-TMSS-01, latest Revision. (Surge Protection Device) TES-P-122-01-R1 (Basic Design Requirements). BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 10 –Capacitor Voltage Transformer Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. INCLUDED S.N. DESCRIPTION REMARKS YES N/A NO Submittal will contain following main drawing sheets: 1 Sectional views along with dimensions 2 Core Details, Rating Plates, Terminal Box, Terminal Drawing 3 Grounding Terminal Drawing 4 PT secondary terminal box Submittal will contain following main documents: 5 Technical Data schedule 6 Manufacturer responsibility statement 7 Manufacturer’s Technical Catalogue 8 PT sizing calculations 9 Material compliance statements for the applicable standards 10 Type test report/Certificate. Documents which are required to be considered: 11 PTS of project 12 Pre-bid clarifications of project 13 Post-bid clarifications of project 14 Tender drawings requirements of project 15 Additional Requirements (if any) Standards which are required to be considered in general but not limited to mentioned below: 16 17 01-TMSS-01, latest Revision. (General Requirements of Material) 50-TMSS-02 latest revision (Capacitor Voltage Transformer) Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 11 –Free Standing Current Transformer Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. INCLUDED S.N. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets: 1 Sectional views along with dimensions 2 Core Details, Rating Plates, Terminal Box, Terminal Drawing 3 Grounding Terminal & pad Drawing 4 CT secondary terminal box Submittal will contain following main documents: 5 Technical Data schedule 6 Manufacturer responsibility statement 7 Manufacturer’s Technical Catalogue 8 CT sizing calculations 9 Material compliance statements for the applicable standards 10 Type test report/Certificate. Documents which are required to consider: 11 PTS of project 12 Pre-bid clarifications of project 13 Post-bid clarifications of project 14 Tender drawings requirements of project 15 Additional Requirements (if any) Standards which are required to consider in general but not limited to mentioned below: 16 17 01-TMSS-01, latest Revision. (General Requirements of Material) 50-TMSS-02 latest revision (Current Transformer) Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 12 – BACKFILL MATERIALS Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 2 3 4 Approved Soil Investigation Report Approved Transition Area Layout Approved Site Grading and Paving Plan Backfill Material Details including test reports 5 6 Documents which are required to be considered PTS of project Pre-bid clarifications of project 7 Post-bid clarifications of project 8 Tender drawings requirements of project 9 Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below 10 TCS-Q-113.02 BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 13 – TERMINAL COMPOUND GROUNDING CALCULATIONS Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets: 1 2 3 Approved Electrical Layout, plan, section drawing of Equipment Arrangement and Details of fence. Approved Terminal Compound Grounding Area Layout Approved Layout and Details of Access Road, structure Pads and Access Road warning signs Submittal will contain following main Documents: 4 Approved Bare copper conductor and Grounding Rods 5 Approved Geotechnical Soil Resistivity Report 6 Terminal Compound Grounding Calculations Documents which are required to consider for terminal compound grounding calculations: 7 PTS of project 8 Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Additional Requirements (if any) Standards which are required to consider in general but not limited to mentioned below: 12 SEED-II (SEC Engineering Drawings Standard) 13 01-TMSS-01-R3 (general Requirements of Material) 14 10-TMSS-05-R1 (Bare, Copper-clad Steel Grounding Conductor and Ground Rod) 15 TCS-P-119-02-R0 (Terminal Compound Arrangement) 16 TES-P-119-10-R0 (Grounding) 17 IEEE-80 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 14- Design Calculations and Design Drawings/Outline Drawing for Take-off Gantry Structure at Transition Area Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following main drawing sheets: 1 Design Drawings / Outline Drawings 2 Clearance Drawings Submittal will contain following main documents: 3 Approved material of Conductor, OPGW, Spacer & Stock Bridge Dampers, Line Hardware, Warning system etc. 4 Approved Sag & Tension Calculations 5 Shielding Calculations 6 Mid Span clearance calculations 7 Outage rate calculations 8 Hardware assembly clearance calculations 9 Load Calculations on different load conditions with overload factors 10 Load Cases 11 Loading Trees 12 Software output results of all the loading cases Documents which are required to be considered: 13 PTS of project 14 Pre-bid clarifications of project 15 Post-bid clarifications of project 16 Tender drawings requirements of project 17 Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below 18 SEED-II (SEC Engineering Drawings Standard) 19 01-TMSS-01-R3 (General Requirements of Material) 20 20-TMSS-01&2-R1 (Steel Towers, Steel Poles, Tapered, Tubular for Transmission Lines). Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS S.N. 21 INCLUDED YES N/A NO DESCRIPTION REMARKS TES-P-122-01-R1 (Basic Design Requirements). 22 TES-P-122-05 Part-I&II-R1 (Transmission line structure Part-I&II, Steel Towers & Steel Poles) 23 TES-P-122.09 latest revision, (Clearances & R.O.W Requirements) 24 TES-P-119.08-R0, (Clearances) 25 TES-P-119.09-R1, (Bus bars & Support Structures) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 15 – DESIGN CALCULATION OF FOUNDATION OF TAKE-OFF GANTRY STRUCTURE Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following Drawing sheets and Calculations. 1 2 3 Design Calculations of foundations of Take-off/gantry structures. Drawings showing details of foundations of Take-off/ Gantry Structures. Design Calculation of Take-off/gantry structure at transition Area approval copy. 4 Transition Area Layout approval copy. 5 Transmission Line Route Plan approval copy. 6 Plan and Profile with Spotted Structures approval copy. 7 Site Grading and Paving Plan for Transition area approval copy. 8 Geotechnical Investigation Report approval copy. Documents which are required to be considered. 9 10 11 12 13 14 15 16 17 18 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Transmission Line Route Plan Plan and Profile with Spotted Structures Transition Area Layout Site Grading and Paving Plan for Transition area. Geotechnical Investigation Report Design Calculations and Drawings For Take-off/gantry structure. . Standards which are required to be considered but not limited to mentioned below. 19 20 21 22 TES-P-119.09 TES-P-122.05 TES-P-122.06 TCS-P-122.05 Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 16 – DESIGN CALCULATIONS AND DRAWINGS OF RETAINING WALL FOR PRECAST BOUNDARY WALL (IF REQUIRED) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of Retaining Wall and its foundation. 2 Drawings showing details of Retaining Wall and its foundation. 3 4 5 Design calculations and drawings of foundations of Takeoff/gantry structures approval copy. Design calculations and drawings for CSE & SA foundations or any other relevant outdoor structure approval copy. Design calculation and drawings for precast boundary wall approval copy. 6 Transition Area Layout approval copy. 7 Site Grading and Paving Plan for Transition area approval copy. 8 Geotechnical Investigation Report approval copy. Documents which are required to be considered. 9 10 11 12 13 14 15 16 17 18 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Design calculation and drawings for precast boundary wall Transition Area Layout Site Grading and Paving Plan for Transition area. Geotechnical Investigation Report Design calculations and drawings of foundations of Takeoff/gantry structures Design calculations and drawings for CSE & SA foundations or any other relevant outdoor structure. . Standards which are required to be considered but not limited to mentioned below. 19 20 TES-P-119.18 TES-P-119.19 Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 17 – DESIGN CALCULATIONS AND DRAWINGS FOR PRECAST BOUNDARY WALL (IF REQUIRED) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of Pre-cast Boundary Wall. 2 Drawings showing details of Pre-cast Boundary Wall (Layout, Panel Arrangement, Fixing Details, Sections and Elevations) 3 Site Grading and Paving Plan for Transition Area approval copy. 4 Transition Area Layout approval copy. Documents which are required to be considered. 5 PTS of Project. 6 Pre-bid clarifications of project 7 Post-bid clarifications of project 8 Site Grading and Paving Plan for Transition Area. 9 Transition Area Layout . Standards which are required to be considered but not limited to mentioned below. 10 TES-P-119.18 11 TES-P-119.19 12 TES-Q-113.01 13 TA-800012 14 TD-800007 15 TD-800008 Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 18 – DESIGN CALCULATIONS AND DRAWINGS FOR HANDHOLES/MANHOLES INSIDE TRANSITION AREA Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of Hand holes and Manholes (if required) 2 Drawings showing details of Hand holes and Manholes. 3 Transition Area Layout approval copy. 4 Geotechnical Investigation Report approval copy. Documents which are required to be considered. 5 PTS of Project. 6 7 8 9 Pre-bid clarifications of project. Post-bid clarifications of project. Transition Area Layout. Geotechnical Investigation Report. . Standards which are required to be considered but not limited to mentioned below. 10 11 12 13 14 15 16 17 TES-P-119.18 TES-P-119.19 TA-800096 TA-800097 TA-800098 TA-800140 TB-800076 TB-800077 BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 19 – DESIGN CALCULATIONS AND DRAWINGS FOR CSE & SA STEEL SUPPORTING STRUCTURE Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of CSE & SA Steel Supporting Structures 2 Drawings showing details of CSE & SA Steel Supporting Structures 3 Technical Submittals for CSE & SA approval copies. 4 Transition Area Layout approval copy. Documents which are required to be considered. 5 6 7 8 9 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Technical Submittals for CSE & SA. Transition Area Layout. . Standards which are required to be considered but not limited to mentioned below. 10 11 12 TES-P-119.09 TES-P-119.19 TES-P-122.05 BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 20– Design Calculations and Drawings of Cable Trench and Precast Concrete Cover Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of Cable Trench and Precast Concrete Cover. 2 Drawings showing details of Cable Trench and Precast Concrete Cover. 3 Transition Area Layout approval copy. 4 Design Calculations and Drawings for hand holes manholes inside transition area approval copy. 5 Site Grading and Paving Plan for Transition area approval copy. 6 Geotechnical Investigation Report approval copy. Documents which are required to be considered. 7 PTS of Project. 8 9 Pre-bid clarifications of project. Post-bid clarifications of project. 10 Transition Area Layout. Design Calculations and Drawings for hand holes manholes inside transition area. Geotechnical Investigation Report. 11 12 . Standards which are required to be considered but not limited to mentioned below. 13 14 15 16 17 18 19 20 TES-P-119.18 TES-P-119.19 TA-800096 TA-800097 TA-800098 TA-800140 TB-800076 TB-800077 Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 21 – DESIGN CALCULATIONS AND DRAWINGS FOR CSE & SA FOUNDATIONS Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of CSE & SA Foundations. 2 Drawings showing details of CSE & SA Foundations. 3 Design Calculation and Drawings for CSE & SA Steel Supporting Structure approval copies. 4 Transition Area Layout approval copy. 5 6 7 Design Calculation and Drawings of foundations of Take-off/ gantry structure approval copy. Design calculations and drawings of retaining wall for precast boundary wall (if it exists) approval copy. Design calculations and drawings of foundations of any other relevant out door structure in transition area approval copy. 8 Site Grading and Paving Plan for Transition area approval copy. 9 Geotechnical Investigation Report approval copy. Documents which are required to be considered. 10 11 12 13 14 15 16 17 18 19 20 21 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Design Calculations and Drawings of CSE & SA Steel Supporting Structures. Transition Area Layout Design Calculation and Drawings of foundations of Take-off/ gantry structure. Design calculations and drawings of retaining wall for precast boundary wall (if it exists). Design calculations and drawings of foundations of any other relevant out door structure in transition area. Transition Area Layout Site Grading and Paving Plan for Transition area. Geotechnical Investigation Report. . Standards which are required to be considered but not limited to mentioned below. 22 23 TES-P-122.06 TES-P-119.18 Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 22 – STEEL SUPPORT STRUCTURE DESIGN CALCULATIONS AND DETAIL DRAWINGS FOR CURRENT TRANSFORMER (CT) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of CT Steel Support Structure 2 Drawings showing details of CT Steel Support Structure 3 Technical Submittal for CT approval copy. 4 Transition Area Layout approval copy. Documents which are required to be considered. 5 6 7 8 9 10 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Transition Area Layout Technical Submittal for CT. . Standards which are required to be considered but not limited to mentioned below. 11 12 TES-P-119.09 TES-P-122.05 BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 23 – DESIGN CALCULATIONS AND DETAIL DRAWINGS OF CURRENT TRANSFORMER (CT) FOUNDATION Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of CT Foundation. 2 Drawings showing details of CT Foundation. 3 Design Calculation and Drawings for CT Steel Support Structure approval copy. 4 Transition Area Layout approval copy. 5 6 7 Design Calculation and Drawings of foundations of Take-off/ gantry structure approval copy. Design calculations and drawings of retaining wall for precast boundary wall (if it exists) approval copy. Design calculations and drawings of foundations of CSE & SA or any other relevant out door structure in transition area approval copy. 8 Site Grading and Paving Plan for Transition area approval copy. 9 Geotechnical Investigation Report approval copy. Documents which are required to be considered. 10 11 12 13 14 15 16 17 18 19 20 21 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Design Calculations and Drawings of CT Steel Support Structure. Transition Area Layout Design Calculation and Drawings of foundations of Take-off/ gantry structure. Design calculations and drawings of retaining wall for precast boundary wall (if it exists). Design calculations and drawings of foundations of CSE & SA or any other relevant out door structure in transition area. Transition Area Layout Site Grading and Paving Plan for Transition area. Geotechnical Investigation Report. . Standards which are required to be considered but not limited to mentioned below. 22 23 TES-P-119.09 TES-P-119.18 Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS S.N. 24 25 INCLUDED YES N/A NO DESCRIPTION REMARKS TES-P-122.05 TES-P-122.06 BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this check list, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 24 – STEEL SUPPORT STRUCTURE DESIGN CALCULATIONS AND DETAIL DRAWINGS FOR VOLTAGE TRANSFORMER (VT) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of VT Steel Support Structure 2 Drawings showing details of VT Steel Support Structure 3 Technical Submittal for VT approval copy. 4 Transition Area Layout approval copy. Documents which are required to be considered. 5 6 7 8 9 10 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Transition Area Layout Technical Submittal for VT. . Standards which are required to be considered but not limited to mentioned below. 11 12 TES-P-119.09 TES-P-122.05 BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 25 – DESIGN CALCULATIONS AND DETAIL DRAWINGS OF VOLTAGE TRANSFORMER (VT) FOUNDATION Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of VT Foundation. 2 Drawings showing details of VT Foundation. 3 Design Calculation and Drawings for VT Steel Support Structure approval copy. 4 Transition Area Layout approval copy. 5 6 7 Design Calculation and Drawings of foundations of Take-off/ gantry structure approval copy. Design calculations and drawings of retaining wall for precast boundary wall (if it exists) approval copy. Design calculations and drawings of foundations of CSE & SA or any other relevant out door structure in transition area approval copy. 8 Site Grading and Paving Plan for Transition area approval copy. 9 Geotechnical Investigation Report approval copy. Documents which are required to be considered. 10 11 12 13 14 15 16 17 18 19 20 21 PTS of Project. Pre-bid clarifications of project Post-bid clarifications of project Tender drawings requirements of project Design Calculations and Drawings of VT Steel Support Structure. Transition Area Layout Design Calculation and Drawings of foundations of Take-off/ gantry structure. Design calculations and drawings of retaining wall for precast boundary wall (if it exists). Design calculations and drawings of foundations of CSE & SA or any other relevant out door structure in transition area. Transition Area Layout Site Grading and Paving Plan for Transition area. Geotechnical Investigation Report. . Standards which are required to be considered but not limited to mentioned below. 22 23 TES-P-119.09 TES-P-119.18 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS S.N. 24 25 INCLUDED YES N/A NO DESCRIPTION REMARKS TES-P-122.05 TES-P-122.06 BY SIGNING BELOW: 1. Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 26 – Design of Cable Supports Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following Drawing sheets and Calculations. 1 Design Calculations of Cable Supports. 2 Drawings showing details of Cable Supports. 3 Technical Submittal for Cables approval copies. 3 Plan and Profile of Cables approval copy. 4 Transition Area Layout approval copy. Documents which are required to be considered. 5 PTS of Project. 6 Pre-bid clarifications of project 7 Post-bid clarifications of project 8 Tender drawings requirements of project 9 Transition Area Layout 10 Technical Submittal for Cables 11 Plan and Profile of Cables . Standards which are required to be considered but not limited to mentioned below. 12 23-TMSS-01 13 23-TMSS-04 14 24-TMSS-01 15 TES-P-104.05 16 TES-P-119.20 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1. Contractor grantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2. Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3. Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. Rev No. 0 1 2 <NG Project Representative> <Project Manager’s Name> <Contractor’s Name> <Project Manager’s Name> Signature Signature & Stamp Submission Date Releasing Date Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 27 –Terminal Compound Grounding Layout Drawings Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. INCLUDED S.N. DESCRIPTION REMARKS YES N/A NO Submittal will contain following main drawing sheets: 1 Approved Transmission Line overall route plan 2 Approved Plan & Profile 3 Approved Foundation design 4 Submission of grounding Layout Drawings of Terminal Compound. Submittal will contain following main documents: 5 Approved Technical Material for grounding 6 Approved Terminal grounding calculations Documents which are required to be considered: 7 PTS of project 8 Pre-bid clarifications of project 8 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below: 12 SEED-II (SEC Engineering Drawings Standard) 13 01-TMSS-01, latest Revision. (General Requirements of Material) 14 10-TMSS-05 latest revision, (Grounding Conductor & rod) 15 TES-P-122.10 latest revision, (TL Grounding) 16 TES-P-119.10 latest revision, (Grounding) Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 28 – Layout, Plan, Section and Details of Fence (Transition Area) Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 2 3 4 Approved Transition area layout drawings Approved site grading and paving plan Drawings of transition area Hard copy & soft copy of transition area fence design calculations (crash barrier/ chain-link/ etc.) Hard copy & soft copy of transition area fence layout plan, sectional details elevation and rebar detail drawing. Documents which are required to be considered 5 Transition Area Layout 6 Site grading and paving plan Drawings of transition area Standards which are required to be considered but not limited to mentioned below 7 8 9 10 TA-800113 chain-link boundary fence Scope of work and technical specification 70-TMSS-02 TES-S-101.1-12 BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV TRANSITION AREA Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 29 – Drive/Personnel Gate Plan, Section and Connection Details of Fence Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 Approved Transition area layout drawings 2 Approved transition area fence layout plan, elevation. Hard copy and soft copy of drive & personnel gates plan, section, elevation, details of gate parts and rebar detail of connection columns drawings Design calculation and drawings for precast boundary wall (if required) Documents which are required to be considered Approved site grading and paving plan Drawings of transition area Approved Layout, Plan, Section and Details of Fence Approved Design calculation and drawings for precast boundary wall (if required) 3 4 5 6 7 Standards which are required to be considered but not limited to mentioned below 8 9 10 11 Scope of work and technical specification TES-S-101-06/07 safety and security of gates TA-800113 chain-link boundary fence 70-TMSS-02 BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV TRANSITION AREA Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 30 – Site Grading and Paving Plan for Transition Area Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. 1 2 3 4 5 CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets Approved Transition area layout drawings Hard and soft copy of topographic survey including contour line, levels and elevations for the proposed transition area and the surrounding roads and area. Hard and soft copy of drawing with layout plan showing inside finished grade and outside ground levels, road levels of surroundings, slopes, paving details, sections, equipment area sections, fence and storm drainage. Proposed FFL. Documents which are required to be considered PTS of project Transition Area Layout Standards which are required to be considered but not limited to mentioned below 6 7 Scope of work and technical specification TCS-P-119.02 BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV TRANSITION AREA Projects, Rev. 00 E&DD © 2019 Page 1 of 1 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 31-Transition Area Layout Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. INCLUDED S.N. DESCRIPTION REMARKS YES N/A NO Submittal will contain following main drawing sheets: 1 Approved Route Plan 2 Approved Plan and Profile 3 Approved Takeoff / Gantry Structure Design / Outline drawings 4 Approved structure drawings for Cable Sealing End and Surge Arrestor Submittal will contain following main documents; 5 6 Approved grounding Calculations Approved Material (Conductor, OPGW, Grounding Material, Hardware and fittings, etc.) Documents which are required to be considered: 7 PTS of project 8 Pre-bid clarifications of project 9 Post-bid clarifications of project 10 Tender drawings requirements of project 11 Additional Requirements (if any) Standards which are required to be considered but not limited to mentioned below 12 SEED-II (SEC Engineering Drawings Standard) 13 01-TMSS-01, latest Revision. (General Requirements of Material) 14 70-TMSS-02, Latest Revision (Chain Link Fence) 15 TCS-P-119.02, latest Revision( 16 TES-S-101-112, latest Revision ( Safety & Security Standards) 17 TES-P-119.10 latest revision, (Grounding) Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 32 - Bore hole location plan & Method statement for Soil Investigation Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. INCLUDED S.N. DESCRIPTION REMARKS YES N/A NO Submittal will contain following main drawing sheets 1 Approved Transition area layout drawings Hard and soft copy of topographic survey including contour line, 2 levels and elevations for the proposed transition area and the surrounding roads and area. 3 Proposed Borehole location plan including trail pits, soil electrical & thermal resistivity measurement points (If any). Hard and soft copy of soil investigation (Method statement) guidelines (Mobilization and demobilization, schedule and order of work for geotechnical exploration and for field load tests, exploration – (drilling and sampling methods, open excavation 4 and sampling methods, cone penetration test methods (If any), geophysical methods (If any)), standards for in-situ field testing and instrumentation, field records, laboratory testing, standards for laboratory testing, laboratory test records, final bore logs, density of soils, consistency of soils, cemented overburden materials, rocks, field notes and records) Documents which are required to be considered 4 PTS of project for geotechnical investigation work & recommendations for design 5 Approved plan and profile drawings. 6 Transition Area Layout Standards which are required to be considered but not limited to mentioned below 7 Scope of work and technical specification 8 TES-P-122.06 Technical Submittal’s Checklist For HV TRANSITION AREA Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS INCLUDED S.N. DESCRIPTION REMARKS YES 9 N/A NO TCS-Q-113.02 BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV TRANSITION AREA Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 33 - Geotechnical Investigation Report Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. DESCRIPTION INCLUDED YES N/A NO REMARKS Submittal will contain following main drawing sheets 1 Approval of geotechnical investigation agency/consultant. 2 Preliminary Geotechnical Investigation proposal & approval. 3 4 5 6 7 8 9 Hard and soft copy of Scope of work of Geotechnical Investigation Hard and soft copy of soil investigation report (general introduction, scope, summary, scope of work, project description, site conditions, field investigations, laboratory tests, subsurface conditions, engineering analysis, recommendations, and certification.) Project location map, plan of exploration, logs of explorations, test data and resulting charts, site geology map, top of rock contour map, geologic structure map, soils and/or rock crosssections. Photographs of all rock core recovered as well as site photos. Recommendations including 1) Bearing capacities for various types of shallow foundations, e.g. spread footings, mat, thickened edge slab, etc. Recommend type best suited for site. 2) Deep foundation capacities; including drilled piers, caissons, driven piles, etc. Discuss tension, compression and lateral capacity of foundation system. 3) Estimated foundation settlements or swell. 4) Lateral earth pressures (active, passive, at-rest, etc.). 5) Slope stability, soil and rock. 6) Site development including site preparation and filling. 7) Foundation and subsurface construction excavation. 8) Ground water considerations. 9) Special foundation treatments, e.g. surcharging, unsuitable material replacement, grouting, etc. if any 10) Recommended elevation/depth for foundations. 11) Recommendations for type of cement in concrete using chemical analysis tests and company standards. Documents which are required to be considered Hardcopy and softcopy of approval of Borehole location plan including trail pits, soil electrical & thermal resistivity measurement points (If any). Approved plan and profile drawings for Transition area Technical Submittal’s Checklist For HV TRANSITION AREA Projects, Rev. 00 E&DD © 2019 Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS S.N. INCLUDED YES N/A NO DESCRIPTION REMARKS Standards which are required to be considered but not limited to mentioned below 10 11 12 13 14 Scope of work and technical specification TES-P-122.06 TCS-Q-113.02 70-TMSS-03 TES-P-122.11 BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV TRANSITION AREA Projects, Rev. 00 E&DD © 2019 Page 2 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 34 – GETECHNICAL SOIL RESISTIVITY REPORT Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE CONTRACT NO. S.N. DESCRIPTION YES N/A NO REMARKS Submittal will contain following main drawing sheets: 1 Approved Key Plan Of OHTL Route 2 Approved Plan & Profile 3 Approved Borehole Locations Submittal will contain following main Documents: 4 Soil Thermal Resistivity Measurements Report along OHTL route. 5 Geotechnical Soil Resistivity Report Documents which are required to consider for terminal compound grounding calculations: 6 PTS of project 7 Pre-bid clarifications of project 8 Post-bid clarifications of project 9 Tender drawings requirements of project 10 Additional Requirements (if any) Standards which are required to consider in general but not limited to mentioned below: 11 SEED-II (SEC Engineering Drawings Standard) 12 TES-P-122-08-R1 (Survey Guidelines) 13 TES-P-122.10-R0 (Transmission Line Grounding) BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. 0 1 2 Submission Date Signature & Stamp Releasing Date Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Days taken to Reply by Contractor Page 1 of 2 TECHNICAL SUBMITTAL’S CHECKLIST FOR HV TRANSITION AREA PROJECTS 35 – Soil Thermal Resistivity Measurements Report Filling Date: / / . PROJECT TILE PTS NO. SUBMITTAL CODE S.N. CONTRACT NO. INCLUDED YES N/A NO DESCRIPTION REMARKS Submittal will contain following main drawing sheets 1 Soil thermal resistivity test report signed and stamped by prequalified independent testing agency. 2 3 Documents which are required to be considered PTS Approved cable route plan. 4 Approved thermal resistivity test location plan Standards which are required to be considered but not limited to mentioned below BY SIGNING BELOW: 1-Contractor guarantees that all submitted documents are as per this checklist, otherwise, Contractor is responsible to do all required modifications without changing submittal’s revision number. 2-Contractor confirms that complete package of document submittal is stamped and signed by Contractor/Manufacturer. 3-Contractor should clarify and explain in the Remarks column if a particular document submittal is not applicable. <NG Project Representative> <Contractor’s Name> <Project Manager’s Name> <Project Manager’s Name> Signature Rev No. Submission Date Signature & Stamp Releasing Date Days taken to Reply by Contractor 0 1 2 Technical Submittal’s Checklist For HV Transition Area Projects, Rev. 00 E&DD © 2019 Page 1 of 1 **** END OF SECTION V **** APPENDIX IX TRAINING OF COMPANY PERSONAL (Not required in this project) APPENDIX X INSTRUCTIONS TO BIDDERS FOR TECHNICAL PROPOSAL TENDER XX – XXXXX RFX No. 40000XXXXX Project Title Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah BIDDER GENERAL INFORMATION (Bidder to fill-in the following information and submit along with his Technical Proposal) Name of the Bidder: Local Address: a. P.O. Box: b. City: c. Telephone No.: d. Fax No.: Foreign Address (if any): a. Street Name: b. P.O. Box: c. City: d. Country: e. Telephone No.: f. Fax No.: Name of Contact Individual(s): Page 1 of 8 Instructions to Bidders for Technical Proposal TABLE OF CONTENTS SECTION PAGE 1.0 PREPARATION OF THE TECHNICAL PROPOSAL 3 2.0 CONTENTS OF TECHNICAL PROPOSAL 4 2.1 2.2 FOLDER I: PROJECT MANAGEMENT FOLDER II: QUALITY ASSURANCE/QUALITY CONTROL (QA/QC) PLAN 4 2.3 2.4 FOLDER III: MAJOR EQUIPMENT/MATERIALS FOLDER IV: PROTECTION REQUIREMENTS 5 6 2.5 2.6 FOLDER V: TELECOMMUNICATION EQUIPMENT/MATERIALS FOLDER VI: SUBSTATION AUTOMATION SYSTEMS EQUIPMENT [Not Applicable] 6 FOLDER VII: 7 2.7 TENDER DOCUMENTS (TECHANICAL) 5 6 3.0 CONDITION FOR “MAIN” & “ALTERNATE” EQUIPMENT/MATERIALS 7 4.0 PRE-BID CLARIFICATION. 8 5.0 PURCHASE OF COMPANY STANDARD DOCUMENTS 8 ATTACHMENTS ANNEXURE I - CONTRACTOR'S KEY PERSONNEL ANNEXURE II - PROPOSED MATERIAL PROCUREMENT AND DELIVERY SCHEDULE ANNEXURE III - PROPOSED SUBCONTRACTING PLAN ANNEXURE IV - PURCHASE ORDER COMPLIANCE ANNEXURE V - GENERAL COMPLIANCE STATEMENT ANNEXURE VI - SUMMARY OF EQUIPMENT/MATERIAL SUBMITTALS ANNEXURE VII - SOW/TS OR TMSS/COMPLIANCE STATEMENT ANNEXURE VIII - MANUFACTURER'S RESPONSIBILITY STATEMENT ANNEXURE IX - POWER TRANSFORMER NO-LOAD AND FULL LOAD LOSS TABLE [Not Applicable] ANNEXURE X - SUMMARY OF PROPOSED PROTECTIVE RELAYS. [Not Applicable] ANNEXURE XI - SUMMARY OF PROPOSED SUBSTATION AUTOMATION SYSTEMS EQUIPMENT. [Not Applicable] ANNEXURE XII - COMPLIANCE STATEMENT FOR ATTENDANCE OF MANUFACTURER REPRESENTATIVES Page 2 of 8 Instructions to Bidders for Technical Proposal ANNEXURE XIII - LIST OF MANUFACTURERS 1.0 PREPARATION OF THE TECHNICAL PROPOSAL 1.1 The Bidder shall prepare the Technical Proposal separate from Commercial Proposal. No pricing information shall be included in the Technical Proposal. 1.2 Commercial Proposal deviations (if any) shall be part of Commercial Proposal only (not Technical Proposal) since this project shall be tendered for one stage bidding. 1.3 Soft copy of the Technical Proposal: The Soft copy of the Technical Proposal shall be submitted electronically, into the COMPANY Contracting Website (as defined in Paragraph 5.1 of Instructions to Bidders for Commercial Proposal), consisting of Seven (7) folders, marked as Folder I, II, III, IV, V, VI and VII . Each folder shall consist of all the documents mentioned in Sections 2.0 of this document shall be submitted and arranged in seven (7) Folders as per details given below: S/N Folder Title Folder Number 1 Folder I PROJECT MANAGEMENT 2 Folder II QA/QC PLAN 3 Folder III MAJOR EQUIPMENT/MATERIALS 4 Folder IV PROTECTION REQUIREMENTS [Not Applicable] 5 Folder V TELECOMMUNICATION EQUIPMENT/ MATERIALS 6 Folder VI SUBSTATION AUTOMATION SYSTEMS EQUIPMENT [Not Applicable] 7 Folder VII TENDER DOCUMENTS (SOW/TS, Pre-bid Clarifications. etc.) 1.4 Technical Proposal shall be in strict compliance with the Proforma Contract, Scope of Work and Technical Specifications (SOW/TS), Instructions to Bidders for Commercial and Technical Proposals and any other instructions to Bidders. No deviation from SOW/TS or Technical Specifications of Equipment shall be entertained, if any, shall be furnished in the Compliance Statement for SOW/TS and each TMSS for NG SA review [any other deviations referred to elsewhere in the documents will not be considered]. 1.5 Each page of every document submitted by the Bidder shall bear his signature, date and stamp. 1.6 No deviation from SOW/TS or Technical Specifications of Equipment shall be entertained 1.7 Incompleteness, non-compliance to Instructions to Bidders and/or deviations from the Scope of Work and Technical Specifications can be used as grounds for rejection of the Bid Proposal completely. 1.8 Bidder shall indicate “N/A” against table requirements of Paragraph 1.3, for items not applicable for the Project. Page 3 of 8 Instructions to Bidders for Technical Proposal 2.0 CONTENTS OF TECHNICAL PROPOSAL 2.1 FOLDER I: PROJECT MANAGEMENT Bidder shall provide the following documents in Folder I for complete implementation of the Project. The documents shall be prepared specific to this project and arranged in the same sequence with a Table of Contents: 2.1.1 Overall Organization Chart: i. Bidder shall put his signature/stamp & date for compliance the Overall Organization Chart as per Annexure I. ii. For the complete management of the Project, indicating the names of all key personnel. Bidders shall propose, as minimum, the personnel indicated in Annexure - I (Contractor’s Key Personnel). It shall be submitted to Project Management Department after Contract Award for approval. a. Project Management Team Bidder shall provide in his technical proposal the minimum Project Management Team composed of highly educated and professional staff, as indicated in Annexure I, to manage and complete the project as per schedule. b. Construction Staff CONTRACTOR shall provide a complete Construction Staff as per SITE Requirements of this CONTRACT. 2.1.2 Time Scaled Bar Chart Schedule (Gantt Chart): a. Bidder shall provide compliance statement for Gantt Chart at bidding stage. b. For the complete implementation of the project. Each major activity coming under Engineering, Equipment/Material Procurement, Installation/ Construction and Testing & Commissioning shall be segregated and shall be shown separately. All Milestone Events shall be indicated and shown separately in the Bar Chart Schedule, it shall be submitted to project Management Department after Contract Award for approval. 2.1.3 Materials Procurement and Delivery Schedule: i. Bidder shall provide compliance statement for Procurement and Delivery Schedule as per Annexure II at bidding stage. ii. For listing all major Equipment /Material that will be necessary for the project. Schedule times in weeks shall be indicated for the following (Please use the format given in Annexure II): It shall be submitted to project Management Department after Contract Award for approval. a. Purchase Orders (Placed) b. Expected time of arrival at construction site. Page 4 of 8 Instructions to Bidders for Technical Proposal c. Date required for construction/installation. 2.1.4 Sub-contracting Plan: indicating proposed sub-contractor(s) for Contract of work to be sub-contracted, it shall be submitted to project Management after Contract Award. (Please use the format given in Annexure III). 2.1.5 Purchase Order Compliance: that the bidder shall include all the relevant terms and conditions specified in Schedule "A", Special Terms and Conditions of the Contract, in his purchase order(s) to the equipment manufacturers / suppliers. (Please use the format given in Annexure IV). 2.1.6 Compliance Statement: stating that the bidder shall comply with Scope of Work and Technical Specifications and adhere to all Terms and Conditions of the Contract. (Please use the format given in Annexure V) 2.2 FOLDER II: QUALITY ASSURANCE/QUALITY CONTROL (QA/QC) PLAN 2.2.1 Bidder shall provide compliance statement for (QA/QC) PLAN at bidding stage. 2.2.2 Bidder shall also provide Quality Assurance/Quality Control (QA/QC) Plan for the complete project indicating all phases of Engineering Design, Equipment Manufacturing, Factory Testing, Equipment/Material Procurement, Installation / Construction and Testing & Commissioning in Folder II, after Contract Award as per project Management requirements. 2.3 FOLDER III: MAJOR EQUIPMENT/MATERIALS 2.3.1 Bidder shall propose ONLY equipment/materials from the List of NG Technically Acceptable/Prequalified Manufacturers. 2.3.2 Documents for the proposed equipment/material shall be provided in Folder III and shall consist as follows: FOLDER III: All applicable Equipment/Material pertaining to PTS listed in Annexure VI of this document. Bidder shall provide the following documents: a. Schedule (Table) of Equipment/Materials Manufacturers: giving all details of proposed manufacturers for all major equipment/material using the format given in Annexure VI. b. Table of Contents: for the proposed equipment/materials arranged in the same sequence as Annexure VI of this document. c. Documents for each major Equipment/Material proposed [arranged in the same sequence as listed below]: 1. Completely filled-in Data Schedules: given in the SOW/TS, duly filled-in [re-typed PTS documents is not acceptable], signed, stamped & dated by the respective Equipment/Material Manufacturer and the Bidder. 2. Compliance Statement: for each applicable TMSS and for 01-TMSS-01 separately, duly signed, stamped & dated by the Equipment/Material Manufacturer and the Bidder (Please use the format given in Annexure VII). 3. Compliance Statement: for attendance of manufacture representative for each Major equipment separately, duly signed, Page 5 of 8 Instructions to Bidders for Technical Proposal stamped & dated by the Equipment Manufacturer and the Bidder (Please use the format given in Annexure XII). 2.4 4. Certified Type (Design) Test Reports. The summary of the Test Reports for the Type and Special Tests that have been conducted on the equipment/material shall be submitted at Design stage for review and acceptance. 5. Manufacturer’s Responsibility Statements: (Please use the format of Annexure VIII). 6. The documents shall be arranged in the same sequence as listed above. 7. No deviation from SOW/TS Equipment shall be entertained. or Technical Specifications of d. Compliance Statement for the Scope of WORK and the list of deviations, if any, duly signed, stamped & dated by the Manufacturer and the Bidder (Please use the format given in Annexure VII). e. Summary of Equipment/Materials Submittals: for major equipment / material (Please use the format given in Annexure VI of this document). FOLDER IV: PROTECTION REQUIREMENTS Bidder shall provide the following documents in Folder IV for the Protection System. The documents shall be arranged in the same sequence with a table of contents: 2.4.1 Bidder shall provide compliance statement bidding stage. for Protection Requirement at 2.4.2 Compliance Statement: for attendance of manufacture representative duly signed, stamped & dated by the Equipment Manufacturer and the Bidder (Please use the format given in Annexure XII). 2.5 FOLDER V: TELECOMMUNICATION EQUIPMENT/MATERIALS Bidder shall provide the following documents in Folder V for the telecommunication equipment/materials. The documents shall be arranged in the same sequence with a table of contents: 2.5.1 Bidder shall provide compliance statement to Telecommunication Requirement at bidding stage. 2.5.2 Documents for telecommunication equipment proposed shall be arranged in the same sequence as per item 2.3.2.c above. 2.5.3 Compliance Statement: for Telecommunication Requirements (Appendix- VI) , duly signed, stamped & dated by the Equipment/Material Manufacturer and the Bidder (Please use the format given in Annexure VII). 2.5.4 Compliance Statement: for attendance of manufacture representative duly signed, stamped & dated by the Equipment Manufacturer and the Bidder (Please use the format given in Annexure XII). Page 6 of 8 Instructions to Bidders for Technical Proposal 2.5.5 The Bidder shall submit filled, signed and stamped copy of Appendix 01 “Technical Offers Clarification for Telecommunication” separately for each PTS. 2.6 FOLDER VI: SUBSTATION AUTOMATION SYSTEMS EQUIPMENT [Not Applicable] Bidder shall provide the following documents in Folder VI for the Substation Automation Systems (SAS) System. The documents shall be arranged in the same sequence with a table of contents: 2.6.1 Bidder shall provide compliance statement for Substation Automation System at bidding stage. 2.6.2 Following documents for each SAS equipment/materials proposed, with a Table of Contents, arranged in the same sequence as item 2.3.2.c above: a. Manufacturers Catalogues with adequate cross-reference to above, highlighting the specific model/type proposed. b. Vendor drawings. 2.6.3 Compliance Statement: for Substation Automation System (Annexure XIII), duly signed, stamped & dated by the Equipment/Material Manufacturer and the Bidder (Please use the format given in Annexure VII). 2.6.4 Compliance Statement: for attendance of manufacture representative duly signed, stamped & dated by the Equipment Manufacturer and the Bidder (Please use the format given in Annexure XII). 2.6.5 The Bidder shall submit filled, signed and stamped copy of Appendix 01 “Technical Offers Clarification for SAS” separately for each PTS. 2.7 FOLDER VII – TENDER DOUCUMENTS Bidder shall provide duly signed and stamped softcopy of the complete tender documents [Scope of Work and Technical Specifications and TMSS including Appendices, Pre bid Clarification (if any), Schedule B and Technical Instructions to Bidders ] in Folder VII. 2.8 TECHNICAL PROPOSAL CHECKLIST Bidder shall submit the Technical Checklist for equipment /materials mentioned as per Clause no.2 “Contents of Technical Proposal” of the ITB for Technical Proposal. This checklist shall be submitted and properly marked. Non submittal of the Technical Checklist may be used as ground for the rejection of the bid proposal completely. (Please use the format given in Annexure XIII - Technical Proposal Checklist). 3.0 CONDITION FOR “MAIN” & “ALTERNATE” EQUIPMENT/MATERIALS The Bidder shall follow the following, in case more than one make and/or model is proposed for any equipment/materials: 3.1 Documents of equipment , for the “Main” proposal shall be attached first, followed by documents for “Alternative” proposal. 3.2 All documents mentioned above as item 2.3, 2.4, 2.5 & 2.6 shall be submitted in the same sequence for Equipment /Materials make and/or model proposed highlighting as “Main” & "Alternative". Page 7 of 8 Instructions to Bidders for Technical Proposal 4.0 3.3 A comparison table comparing the salient features of the "Main" and "Alternative" make and/or model proposed. 3.4 Bidder shall not propose more than one alternative make and/or model for a given Equipment/Materials. Main and ONLY One (1) Alternate Offer, as per Annexure XIII, will be considered during technical evaluation of the Project by COMPANY and Bidder is not allowed to change the already technical evaluated offers. 3.5 The quoted lump sum Contract Price indicated in Bidder’s Commercial Proposal (Bid Form) shall remain same for providing the “Main” or "Alternative" make and/or model of Equipment/Materials, whichever is accepted by COMPANY. 3.6 Within six weeks from Contract Award, the CONTRACTOR may change from Main to Alternative offer. As explained above, this change will be considered by the Company only if the CONTRACTOR successfully informs the Company officially before the end of the six weeks from the Contract Award. This is valid for all equipment/ materials to be submitted in technical bid package. 3.7 AFTER six weeks from issuance of Notice of Award, Alternative offer will not be considered for acceptance. Within the following two weeks, list of “Main” and “Alternative” make and/or model of equipment/ materials and committed delivery dates for the same shall be submitted by CONTRACTOR. 3.8 In case the localization strategy applied, the General Terms & Conditions “Schedule-A” penalty clause No. 44.7, shall be applied to the change from local to foreign manufacture. PRE-BID CLARIFICATION The bidder is allowed to raise consolidated pre-bid clarifications one time only before the expiry of last date for queries by the bidder. No successive number of pre-bid queries will be accepted by the COMPANY. 5.0 PURCHASE OF COMPANY STANDARD DOCUMENTS Bidders who do not have access to NG standard documents are advised to purchase a one-year web-based access to NG standard documents by contacting the Standards and Specifications Department through the following contact information: Division Manager, Protection and Substation Automation Specifications Tel # +966 11 8077378 Fax # +966 11 8077497 Email: AliMMashhour@ngrid.sa National Grid SA Tower A, Floor 1. SEC HQ New Building P.O. Box# 22955, Riyadh 11416 Kingdom of Saudi Arabia *** END OF INSTRUCTIONS TO BIDDERS FOR TECHNICAL PROPOSAL *** Page 8 of 8 TECHNICAL PROPOSAL ANNEXURE - I RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah CONTRACT Number CN # Project Management Team project Manager Construction Staff at each Site Manager 1 BS degree in Eng'g. with 20 Years relevant experience. 1 BS degree in Electrical Eng'g. with 15 years relevant experience Planning & Scheduling Engineer 1 BS degree in Eng'g. with 10 years relevant experience Design Engineering Coordinator 1 BS degree in Electrical Eng'g. with 10 years relevant experience Material Coordinator 1 BS degree in Eng'g. or equivalent with 10 years relevant experience Protection Engineer 1 BS degree in Electrical Eng'g with 10 years relevant experience Site Electrical Engineer 1 BS degree in Electrical Eng'g. with 10 years relevant experience Site Civil Engineer 1 BS degree in Civil Eng'g. with 10 years relevant experience Site Mechanical Engineer BS degree in Mechanical Eng'g. with 10 years relevant experience 1 QA/QC Electrical Engineer BS degree in Electrical Eng'g. with 10 years relevant experience 1 QA/QC Civil Engineer BS degree in Civil Eng'g. with 10 years relevant experience 1 Safety Officer BS degree in Eng'g. with relevant experience 1 Testing & Commissioning Engineer BS degree in Electrical Eng'g. with 10 years relevant experience 1 Note : 1.CONTRACTOR shall propose, as minimum, the personnel indicated above and as per Project Management Department requirements. 2.The above personnel shall be from the CONTRACTOR's own work force and shall be assigned on full time basis. 3.CONTRACTOR shall submit the Saudi Engineering Council ID number for all Engineers during project contract. Bidder's Stamp ITB - Annexure II - 1 TECHNICAL PROPOSAL ANNEXURE - II RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah PROPOSED MATERIAL PROCUREMENT AND DELIVERY SCHEDULE Item No. Material/Equipment Description Purchase Order Expected Time of Arrival at Site Time Required at Site (In Weeks) (In Weeks) (In Weeks) Bidder's Stamp Name of Bidder: Signature: Name: Date: ITB - Annexure II - 2 TECHNICAL PROPOSAL ANNEXURE - III RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah PROPOSED SUBCONTRACTING PLAN Item No. Description of Work Proposed to be Subcontracted Commercial Registration Number Name & Address of Proposed Subcontractor Bidder's Stamp Name of Bidder: Signature: Name: Date: ITB - Annexure III - 3 TECHNICAL PROPOSAL ANNEXURE - IV RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah PURCHASE ORDER COMPLIANCE We hereby confirm that all the relevant terms and conditions specified in Schedule "A", General, Special Terms and Conditions of the Proforma Contract, and all the relevant clauses specified in the Scope of Work and Technical Specifications, SOW/TS shall be included in corresponding Purchase Order(s) to be issued to the Equipment Manufacturer(s) or Supplier(s). Bidder's Stamp Name of Bidder: Signature: Name: Date: ITB - Annexure IV - 4 TECHNICAL PROPOSAL ANNEXURE - V RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah GENERAL COMPLIANCE STATEMENT This Technical Proposal includes all the work and services required to complete the Project. Having been properly represented during the Job Explanation Meeting and having investigated the WORK SITE, and examined in their entirety the Scope of Work and Technical Specifications, the Proforma Contract and all the documents referred to therein, and all the instructions to bidders, the undersigned offers to design, engineer, procure and deliver all equipment and materials to the WORK SITE, construct, install, test and commission the above project in accordance with the above documents and agree to adhere to all terms and conditions of the Proforma Contract. The undersigned also undertake to maintain confidentiality of all correspondence with COMPANY, both in pre-award and post-award phases of the contract, and no correspondence of any kind will be relayed to a third party without the express permission of the COMPANY in writing. Bidder's Stamp Name of Bidder: Signature: Name: Date: ITB - Annexure V - 5 TECHNICAL PROPOSAL ANNEXURE - VI RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah SUMMARY OF EQUIPMENT/MATERIAL SUBMITTALS Description of Equipment and Materials Item No. A U/G POWER CABLES 1 XXXkV XLPE XXXXmm² U/G Cable 2 XXXkV, Cable Termination (Indoor/Outdoor sealing ends) 3 Joints for XXXKV power cable (Insulated, Straight) 4 SVL (SHEATH VOLTAGE LIMITER) 5 EARTH BONDING CABLES 6 Link Box (Solid Earthing & Cross Bonding ) for Underground Cables B TELECOMMUNICATION MATERIALS/EQUIPMENT FOR O/H LINE & U/G CABLE PROJECTS 1 TMSS Compliance Statement Data Schedules Single Mode OPTICAL GROUND WIRE (OPGW) 2 Single Mode U/G Non Metallic Fiber Optic Cable (UGNFOC) 3 FO Joint Box 4 FO Terminations (OFMR & FSTP) 5 FO Accessories (Fiber Pigtail & Patch cord) Notes: Name of Manufacturer, 01-TMSS-01 Type/Model Compliance & Country of Statement Origin 1. Use additional sheets as necessary. Follow the same format. 2. Strike-off items which are not applicable to this project. 3. In case different make/type/model are proposed, the same shall be listed. Name of Bidder: Bidder's Stamp Signature: Name: Date: ITB - Annexure VI - 6 Deviations (YES/NO) Type Test Reports Manufacturer's Responsibility Statement Tech. Info. In Folder/ Section # TECHNICAL PROPOSAL ANNEXURE - VII RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah SOW/TS OR TMSS COMPLIANCE STATEMENT SOW/TS, PTS No. Equipment /Material: TMSS No.: SOW/TS OR TMSS COMPLIANCE STATEMENT Item No. Clause No. Justification Deviation Having been properly read and understood, we, the undersigned certify that the equipment/material offered is strictly in compliance with the SOW/TS and applicable COMPANY Material Standard Specifications, except for the deviations mentioned in the table above. Name of Manufacturer: Signature: Name of Bidder: Signature: Name: Name: Date: Date: Manufacturer's Stamp Bidder's Stamp ITB - Annexure VII - 7 TECHNICAL PROPOSAL ANNEXURE - VIII RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah MANUFACTURER'S RESPONSIBILITY STATEMENT We hereby convey our interest to associate with the above project and supply the following Equipment: Equipment Name/Description: In the event of placement of purchase order on us we will comply with the COMPANY Term & Condition of "Manufacture's Responsibility" specified in Schedule "A" of the Performa Contract. Name of Manufacturer: Name of Bidder: Signature: Signature: Name : Name : Date : Date : Bidder's Stamp Manufacturer's Stamp ITB - Annexure VIII - 8 TECHNICAL PROPOSAL ANNEXURE - IX RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah POWER TRANSFORMER NO-LOAD AND FULL LOAD LOSS TABLE (N/A) LOSS GUARANTEED BY MANUFACTURER Name of Transformer Manufacturer Transformer Capacity in MVA Number of Transformers No Load [Core] Loss Per Transformer [*] Full Load [Copper] Loss Per Transformer [*] Note: [*] – The guaranteed No Load Loss and Full Load Loss per Transformer indicated here, shall be inclusive of Tolerance as per IEC or IEEE. Name of Manufacturer: Name of Bidder: Signature: Signature: Name : Name : Date : Date: Manufacturer's Stamp Bidder's Stamp ITB - Annexure IX - 1 Total Loss Per Transformer TECHNICAL PROPOSAL ANNEXURE - X RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah SUMMARY OF PROPOSED PROTECTIVE RELAYS (NA) Bidders compliance statement attached ITB - Annexure X - 2 TECHNICAL PROPOSAL ANNEXURE - XI RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah SUMMARY OF PROPOSED SUBSTATION AUTOMATION SYSTEMS EQUIPMENT (NA) Item No. 1 Description of Equipment and Materials Name of Manufacturer Country of Origin Type/ Model Tech. Information in Section # SUBSTATION AUTOMATION SYSTEMS EQUIPMENT (As per Notes below) Notes : 1. Bidder to specify and list the SUBSTATION AUTOMATION SYSTEMS EQUIPMENT and Devices taking into consideration the COMPANY Technical Specifications and as per the Scope of Work and Technical Specifications. 2. Use additional sheets as necessary. Follow the same format. 3. In case different make/type/model of same kind of SAS Equipment are proposed for different applications list them all. Bidder's Stamp Name of Bidder: Signature: Name: Date: ITB - Annexure X - 3 TECHNICAL PROPOSAL ANNEXURE -XII RFxN 40000xxxxx: PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah COMPLIANCE STATEMENT FOR ATTENDANCE OF MANUFACTURER REPRESENTATIVES We hereby confirm that we will take all necessary action, ahead of time, to obtain the required Visa and relevant travel documents for the representatives of the equipment manufacturer to ensure their presence/attendance in the Bid Clarification meetings, as requested by COMPANY, conducted during the Technical bid evaluation period in order to resolve any outstanding Technical issues. CONTRACTOR's failure to comply with the aforementioned statement entitles COMPANY to reject CONTRACTOR's bid proposal. Bidder's Stamp Name of Bidder: Signature: Name: Date: ITB - Annexure X - 4 TECHNICAL PROPOSAL - CHECKLIST ANNEXURE -XIII RFxN 40000xxxxx PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah LIST OF MANUFACTURERS (U/G) Item Nos. as per Bid Form Pricing Attachement (Bidder to indicate) Sr. # Equipment / Details Proposal Main Vendor/ Alternate Vendor Manufacturer Name Origin/Location Main 1 XXXKV XLPE XXXXmm² U/G Cable 2 XXXKV Cable Termination Main (Indoor/Outdoor sealing ends) Alternate 3 Joints for XXXKV power cable (Insulated, Straight) 4 SVL (Sheath Voltage Limiter) Alternate Main Alternate Main Alternate Main 5 Earth Bonding Cables Link Box (Solid Earthing & Cross Bonding ) for Underground Cables Single Mode U/G Non Metallic Fiber Optic Cable (UGNFOC) 6 7 Alternate Main Alternate Main Alternate Main 8 FO Joint Box 9 FO Terminations (OFMR & FSTP) Main 10 FO Accessories (Fiber Pigtail & Patch cord) Main Alternate Alternate Alternate Notes: 1. Only applicable Manufacturers to this project (Major Equipment) shall be filled-in. All Equipment which are not included in the above list, shall be provided from Company pre-qualified manufacturers and as per SOW/PTS. * The Protection & Control Panels shall be from NG SA approved list. 2. Bidder's Stamp Bidder's Stamp Name of Bidder Repersentative: Signature: Signature: Date: Date: TECHNICAL PROPOSAL - CHECKLIST RFxN 40000xxxxx PROJECT TITLE Installation of 110kV UGC for Madinah ISTP 110/13.8KV Substation in Madinah COMPLIANCE STATEMENT FOR QUALITY ASSURANCE/ QUALITY CONTROL REQUIRMENTS We hereby confirm to fully comply with all requirments of Quality Assurance/Quality Control (QA/QC) for the complete project as specified in all the instructions to bidders, all the relevant clauses specified in the Proforma Contract, and all the relevant clauses specified in the Scope of Work and Technical Specifications, SOW/TS. Bidder's Stamp Name of Bidder: Signature: Name: Date: ANNEXURE -XIV