MINUTES OF THE MEETING
IMS MEETING in preparation for EMB 1 Internal Audit CY 2023
23 June 2023 (Friday) at ORD Conference Room and via Microsoft Teams Online
Active participants:
1
Engr. Remedios A. Jimenez
28
Ms. Sariah Jane Orine-Sabado
2
Engr. Nicanor C. Esteban
29
Engr. Diana T. Flores
3
Engr. Ryanne N. Narvaez
30
Engr. Rupert Anton C. Usalla
4
Mr. Michael E. Alvear
31
Ms. Hazel R. Cariaso
5
Engr. Maria Theresa D. Flores
32
Ms. Immaecor Joy A. Amilao
6
Ms. Leny Grace L. Cajote
33
Engr. Sherwin Labilles
7
Ms. Ma. Isabel O. Perez-Mamaradlo
34
Ms. Dionalyn L. Soriano
8
Engr. Bernadeth B. Agusto
35
Mr. Roderick. F. Valdez
9
Engr. Maureen S. Malazo
36
Ms. Nerissa D. Ortiz
10
Engr. Ferdinand Marck C. Aquino
37
Ms. Kristelle Joy R. Angala
11
Engr. Magna Riola-Paramio
38
Ms. Marvilyn O. Barrantes
12
Mr. Joseph E. Cajote
39
Ms. Glaiza Mariz M. Laudencia
13
Engr. Rowell G. Lipadan
40
Engr. Marc Lester Rodriguez
Protect the environment. . . Protect Life. . .
Tel. Nos. (072)-687-8370; e-mail: r1@emb.gov.ph
1
14
Mr. Newman Diego P. Nate
41
Ms. Aloha S. Renion
15
Ms. Nimozenie I. Magleo
42
Ms. Jean A. Apilado
16
Engr. Ronald Pascua
43
Ms. Lyra L. Tadifa
17
Mr. Benedict R. Manapat
44
Engr. Lyra Erika L. Comtiag
18
Mr. Albert Sotelo Jr.
45
Ms. Rubie Honey B. Tavas
19
Mr. Maynard Sydney Cara
46
Ms. Gemmalyn M. De Guzman
20
Engr. Rogelio B. Gabuyo, Jr
47
Mr. Ezekiel B. Salinas
21
Ms. Florilyn Padua-Claro
22
Ms. Roxy Pearl B. Dumo
23
Engr. Judy Ann S. Abella
24
Engr. Vic Joseph P. Esquejo
25
Mr. Mardave Nerveza
26
Mr. Nestor C. Bambalan, Jr.
27
Ms. Jessica E. Sapasap
***Nothing follows
Total of Forty-Seven (47) participants: 20 Males and 27 Females
Highlights of the meeting:
I.
Call to Order
Protect the environment. . . Protect Life. . .
Tel. Nos. (072)-687-8370; e-mail: r1@emb.gov.ph
2
On 23 June 2023, Friday at 11:00 AM, Environmental Management Bureau Region I - IMS
Team convened for a meeting to discuss matters on organizational compliance with the
integrated management system (IMS) specifically in preparation for the conduct of Internal
Quality Audit this July CY 2023.
Forty-seven (47) members of the Environmental Management Bureau Region I - IMS
Team actively participated during the meeting presided over by IM/QM Representative,
Engr. Remedios A. Jimenez.
II.
Objectives
In the interest of the public service, the meeting has the primary objective to strengthen the
organizational capacity and sustain compliance with the ISO-integrated management
system.
Specifically, EMB I -Integrated Management Team aimed to evaluate and enhance
organizational areas pertaining to quality management, environmental management
system, occupational health & safety, and internal quality system as collectively for
compliance with integrated management system standards.
III.
Agenda
The following are the approved agenda of the meeting:
a) Review of the EMB 1 Risk Register
b) Preparation for the Internal Audit
c) Other Matters
IV.
Business Proper
Responsible
Discussion
Office / Process
Owner
Response from the
body
Remarks
In the Risk Register,
Engr. Remedios A.
Jimenez suggested
Engr. Remedios A. Jimenez
assigned Mr. Joseph E.
Cajote, Ms. Roxy Pearl B.
Dumo, and Mr. Ezekiel B.
1. Review of EMB 1 Risk Register
Engr. Remedios
A. Jimenez,
IM/QM
Representative
A revised and updated Risk
Register, bearing document
control number EMB-RISK
Protect the environment. . . Protect Life. . .
Tel. Nos. (072)-687-8370; e-mail: r1@emb.gov.ph
3
REGISTER-F001 Rev.2/ 210-2023, was presented to
the body.
lowering the risk
scores given to
Supplies
Management:
Engr. Lyra Erika L.
Probability=1,
Comtiag carefully read the
Impact=2,
context and coverage of the Exposure=2. She
EMB 1 Risk Register.
mentioned that other
cited risks especially
Engr. Remedios A. Jimenez Budget Cuts under
called the attention of the
Top management
IMS Core Team to comment should be given
on possible changes to the
appropriate
presented EMB 1 Risk
mitigation and
Register.
contingency
measures although
beyond the control of
EMB 1 as an
implementing
agency.
Salinas in the creation of one
Google Folder containing the
Risk Register, and other
controlled documents.
Relatively, she reminded Ms.
Ma. Isabel O. PerezMamaradlo to finalize the
updating of Citizen’s Charter.
Engr. Remedios A. Jimenez
set the tentative schedule for
Management Review by
August CY 2023.
Engr. Maria Theresa
D. Flores suggested
that review of Risk
Register should be
conducted per
Division especially to
be able to internalize
some
observations/findings
cited for a particular
process. She
proposed the creation
of a Risk Register
form as a shareable
Google Sheet. In that
way, everybody (IMS
Core Team) can
view/edit the Risk
Register easily.
Protect the environment. . . Protect Life. . .
Tel. Nos. (072)-687-8370; e-mail: r1@emb.gov.ph
4
Responsible
Discussion
Office / Process
Owner
Response from the
body
Remarks
Regarding Internal Audit
Procedures:
Engr. Maria Theresa D.
Flores discussed the IA
Procedures and some
important matters pertaining
to the conduct of internal
quality audit in EMB 1. She
reiterated the vital elements
of an internal audit, viz: the
classification of findings,
the internal auditors, and IA
performance evaluation.
Engr. Remedios A.
Jimenez called the
attention of the IMS
Team if there is a
need to revise the
presented Internal
Audit Procedure.
Regarding Internal Audit
Procedures:
The body agreed to retain the
existing Internal Audit
Procedure.
Regarding Internal
Auditors and Selection of
IA Deputy:
Per the conducted IA
performance evaluation,
respective scores of the
internal auditors were
presented. Top 3 internal
auditors: Engr. Rogelio B.
Gabuyo, Jr, Ms. Leny Grace
L. Cajote, and Ms. Ma.
Isabel O. Perez-Mamaradlo
all earned a perfect IA
performance score of 5.
Regarding the
Selection of IA
Deputy:
Engr. Remedios A.
Jimenez suggested
that selection of IA
Deputy should be
through votation.
2. Preparation for the Internal Audit
Engr. Maria
Theresa D.
Flores, IA Lead
Engr. Maria Theresa D.
Flores emphasized the need
for a basis in selection of
deputy IA Lead (based on
IA performance score,
length of experience as an
auditor, etc).
The body agreed that IA Lead
will be excluded from the
conduct of regular internal
auditing.
Regarding the Selection of
IA Deputy:
The body agreed in the
designation of Ms. Ma. Isabel
O. Perez-Mamaradlo as the
IA Deputy.
Engr. Rogelio B.
Gabuyo Jr declined
his nomination for IA
Deputy. He said that
he still needs deeper
experience of IA
procedures and ISOrelated matters.
Engr. Maureen S.
Malazo endorsed Ms.
Ma. Isabel O. PerezMamaradlo for the IA
Deputy Position. She
said Ms. Perez-
Protect the environment. . . Protect Life. . .
Tel. Nos. (072)-687-8370; e-mail: r1@emb.gov.ph
5
Observation from the
previous surveillance audit:
The IA Lead must be
excluded in the conduct of
internal audit of regular
processes of an
organization. Rather, the IA
Lead should only
assess/evaluate the conduct
of internal auditing by the
internal auditors.
Mamaradlo has a vast
knowledge in ISO
compliance
procedures and
moreover has been an
active member of the
EMB 1 ISO Core
Team since CY 2017.
To date, EMB 1 has a total
of 25 internal auditors.
Regarding the Internal
Audit Plan for CY 2023:
Engr. Maria Theresa D.
Flores presented the
proposed IA plan tentatively
slated for July 3-14, 2023 (2
weeks). She asked if there
are some impending office
activities that should be
considered in selection of
specific dates per process.
Regarding the
Internal Audit Plan
for CY 2023:
Engr. Remedios A.
Jimenez said that new
members of IA Team,
Engr. Sherwin
Labilles and Engr.
Vic Joseph P.
Esquejo must be
enlisted as IA
observers.
Engr. Maria Theresa
D. Flores asked the
body for any
suggestions regarding
IA assignment.
Otherwise, IA shall
adopt the previous
audit plan.
Engr. Remedios A.
Jimenez encouraged
the internal auditors
to choose their
preferred partners and
respective processes
to audit.
Regarding the Internal
Audit Plan for CY 2023:
The body agreed to have the
EMB 1 Internal Audit to be
conducted on the following
dates:
July, 4, 2023 (Tuesday)
July, 5, 2023 (Wednesday)
July, 7, 2023 (Friday)
July, 10, 2023 (Monday)
July, 11, 2023 (Tuesday)
July, 12, 2023 (Wednesday)
Assignment of internal
auditors for this year’s EMB 1
Internal Audit is hereby
tabulated in a separate page.
Protect the environment. . . Protect Life. . .
Tel. Nos. (072)-687-8370; e-mail: r1@emb.gov.ph
6
3. Other Matters
- Preparation of documents to be qualified for CSC Prime HRM Bronze Award.
Engr. Remedios
A. Jimenez,
IM/QM
Representative
Engr. Remedios A. Jimenez
shared the undertaken
preparations by the Finance
& Administrative Division
for the pillar on
Performance Management
Documents that includes the
compilation of employees’
IPCR rating to be submitted
at the end of this month at
CSC office.
Engr. Remedios A.
To compile all documents and
Jimenez tapped the
submit to CSC until 30 June
Environmental
2023 (Friday)
Monitoring and
Enforcement
Division (EMED) to
provide copy of their
drafted IPCR
showing some
corrections that it was
reviewed by the
Section and Division
Chiefs.
On the other hand, the full
completion of the Learning
& Development Plan and
Rewards and Recognition is
ongoing.
V.
Adjournment
With no further issues and matters to discuss, Engr. Jimenez adjourned the meeting at
exactly 4:18PM.
Prepared by:
Reviewed by:
Ezekiel B. Salinas
Secretariat
Engr. Remedios A. Jimenez
Integrated Management and Quality
Management Representative
Protect the environment. . . Protect Life. . .
Tel. Nos. (072)-687-8370; e-mail: r1@emb.gov.ph
7
Noted by:
Engr. Maria Dorica Naz-Hipe, CESE
Regional Director
Protect the environment. . . Protect Life. . .
Tel. Nos. (072)-687-8370; e-mail: r1@emb.gov.ph
8
PHOTO DOCUMENTATION
IMS MEETING in preparation for EMB 1 Internal Audit CY 2023
23 June 2023 (Friday) at ORD Conference Room and via Microsoft Teams Online
IMS Team / Review and Presentation of Risk Register
IMS Internal Audit Team
Protect the environment. . . Protect Life. . .
Tel. Nos. (072)-687-8370; e-mail: r1@emb.gov.ph
1
Online Participants via Microsoft Teams
Protect the environment. . . Protect Life. . .
Tel. Nos. (072)-687-8370; e-mail: r1@emb.gov.ph
2
Download