1. A D lB E I K L F J H G C 2 a. H A D I J E B C b. Critical activities – A, E, G, J, K, L c. d. 180 3a. Expected time = [OP +4(MS) + P]/6 =[ 11+4(17)+30]/6 F G K L =18.17 b. Critical activities – A, B, D, G c. SD=[ P-O/6]^2 = [30-11/6]^2 =10.03 d. Z= 20-18.18/10.03 = 0.18