Lifting Plan Transformer

advertisement
Description of lift: Lifting of Container
Location:- T S F 2 t o T S F 1
Generic Lift plan No. : SSB/BFI/23/0013
Permit to work Number:Risk assessment No.
1. CRANE DATA
Hiab Crane Reg. No.
Inspection Date
Next due date
BAW1925
03-08-2023
02-08-2025
Safe Working Load
7900
Ton
Max boom length
16.3
Mtrs
Max working radius
16.3
Mtrs
The crane capacity charts must be consulted for operation
restrictions i.e. over the rear only, outriggers fully extended
2. LOAD DATA
Transformer
Object to be lifted
Weight of Load
Container/Vessel - Empty
Awkward Shape
COG Known
Certified lifting points
Special Rigging required
Special rigging Techniques required
3500
YES √
YES
YES √
YES
YES
YES
Kgs
NO
NO √
NO
NO √
NO √
NO √
Other
3. RIGGING REQUIRED
SWL
4000
4000
Description
Webbing Sling
Shackles
4. RIGGING WEIGHT
Description
Headache Ball & Hook
Rigging i.e. sling shackles
Weigt
30
12
Units
kgs
kgs
kgs
Spreader bar
Other rigging attached
Weight (Kgs)
8
4
Total Weight (Kgs)
5. RIGGING CALCULATION
Description
Weight
Object weight
3000
Contingency %
-10%
kgs
kgs
kgs
% safety margin
kgs
42
Weight / Unit (Kgs)
4
1
Rigging weight
Total Weight
Actual Planned Radius (Max)
Lift height
Boom length
Capacity chart rating at radius &
boom length
kgs
Total
Quantity
2
4
300
12
Units
kgs
kgs
42
3342
5.8
2
6
kgs
kgs
M
M
M
5800
kgs
57
%
6 CATEGORY OF LIFT Tick which ever is applicable
Routine
Lift plans shall be written by rigging foreman or crane operator and approved by person
in charge (PIC) o.f the lifting operation.
Simple
√
Lift plans shall be written by and rigging supervisor and approved by person in charge
(PIC) of the Lifting operation.
Complicated
Complicated lift plans shall be written by an approved lift planner and approved by T.A.
7. HAZARDS CRANE SET-UP/OPERATING AREA
7.1 Under ground Hazards no
7.2 Ground level Hazards
Utilities - Gas, Water etc
no
Members of the public
Storm Drain
no
Workers
Sewer
Recent excavations
Other describe
no
no
no
no
no
no
Vehicles/machinery
Buildings
Ground conditions
Other - describe
Access road: Concrete/Bitumen/Gravel/soft/Other
Crane Set-Up Area; Concrete/bitumen/Grave/Soft/ Slope/Other
The lifting activity requires the following to be considered, note this
Cultural, communication and language difficulties
Weight, size, shape and centre of gravity of load
√
Availability of approved lifting points on load
√
Method of slinging/attaching/detaching the load
√
Overturning/load integrity/need for tag lines
√
Initial and final load position and swing direction
√
Lifting over live equipment
No
Number and duration of lift(s)
2
8. PERSONNEL
Personnel
HAIB Truck
Banksman
Rigger
Rigger
9. APPROVALS
Required lift Approvals
Lift plan prepared by
Lift plan reviewed by
Lift plan approved by
Name
Mohammad Zeya
Mohammad Afzal
Abdurrahem
Mohammad Kyamuddin
Name
Mohd Uroj
Sukhbir Singh
Taufiq
no
no
good
no
7.3 Above ground Hazards
Electrical cables
Telephone cables
no
no
Lampposts
Other cranes
Trees
Conflicting tasks in area
Other - describe
no
no
no
no
Concrete/Bitumen
Gravel/Other
list is not exhaustive
Environmental conditions (weather and permissible limits)
Illumination in the pick-up and lay-down areas
Proximity of hazards, obstructions in the path of load
Contingency plan in case the task changes
Access and emergency escape routes
Experience, competence and training of personnel
Number of personnel required for task
Pre-Use Inspection of equipment by Operator
Tool Box Talk, including Safety and Stopping the job
Signature
√
√
√
√
√
√
4
As required
As required
Date
4/10/2023
4/10/2023
4/10/2023
4/10/2023
Signature
Date
4/10/2023
4/10/2023
4/10/2023
Lifting details (step by step)
1) Hold a Pre job meeting (TBT) with all parties involved.
2) Verify load weight.
3) Ensure barriers are in place and the load travel path and lay down area is clear of obstruction.
4) Carry out pre-start for the HAIB crane.
5) Carry out pre-use inspection for the lifting accessories.
6) Attach the tag line to the load.
7) Attach the sling to the load and ensure the load is secured.
8) Attach the slings on to the crane main hook.
9) Banksman to give hand signal to the crane operator once the sling is hooked.
10) HIAB Truck operator picks up the load and follows banksman signals to hoist & slew the load from Ground to Trailer and vice versa
11) Upon confirmation from client the position of the load is acceptable, remove all lifting tackles.
12) Ensure the area is safe and finish the lifting operation.
13) Housekeeping.