Description of lift: Lifting of Container Location:- T S F 2 t o T S F 1 Generic Lift plan No. : SSB/BFI/23/0013 Permit to work Number:Risk assessment No. 1. CRANE DATA Hiab Crane Reg. No. Inspection Date Next due date BAW1925 03-08-2023 02-08-2025 Safe Working Load 7900 Ton Max boom length 16.3 Mtrs Max working radius 16.3 Mtrs The crane capacity charts must be consulted for operation restrictions i.e. over the rear only, outriggers fully extended 2. LOAD DATA Transformer Object to be lifted Weight of Load Container/Vessel - Empty Awkward Shape COG Known Certified lifting points Special Rigging required Special rigging Techniques required 3500 YES √ YES YES √ YES YES YES Kgs NO NO √ NO NO √ NO √ NO √ Other 3. RIGGING REQUIRED SWL 4000 4000 Description Webbing Sling Shackles 4. RIGGING WEIGHT Description Headache Ball & Hook Rigging i.e. sling shackles Weigt 30 12 Units kgs kgs kgs Spreader bar Other rigging attached Weight (Kgs) 8 4 Total Weight (Kgs) 5. RIGGING CALCULATION Description Weight Object weight 3000 Contingency % -10% kgs kgs kgs % safety margin kgs 42 Weight / Unit (Kgs) 4 1 Rigging weight Total Weight Actual Planned Radius (Max) Lift height Boom length Capacity chart rating at radius & boom length kgs Total Quantity 2 4 300 12 Units kgs kgs 42 3342 5.8 2 6 kgs kgs M M M 5800 kgs 57 % 6 CATEGORY OF LIFT Tick which ever is applicable Routine Lift plans shall be written by rigging foreman or crane operator and approved by person in charge (PIC) o.f the lifting operation. Simple √ Lift plans shall be written by and rigging supervisor and approved by person in charge (PIC) of the Lifting operation. Complicated Complicated lift plans shall be written by an approved lift planner and approved by T.A. 7. HAZARDS CRANE SET-UP/OPERATING AREA 7.1 Under ground Hazards no 7.2 Ground level Hazards Utilities - Gas, Water etc no Members of the public Storm Drain no Workers Sewer Recent excavations Other describe no no no no no no Vehicles/machinery Buildings Ground conditions Other - describe Access road: Concrete/Bitumen/Gravel/soft/Other Crane Set-Up Area; Concrete/bitumen/Grave/Soft/ Slope/Other The lifting activity requires the following to be considered, note this Cultural, communication and language difficulties Weight, size, shape and centre of gravity of load √ Availability of approved lifting points on load √ Method of slinging/attaching/detaching the load √ Overturning/load integrity/need for tag lines √ Initial and final load position and swing direction √ Lifting over live equipment No Number and duration of lift(s) 2 8. PERSONNEL Personnel HAIB Truck Banksman Rigger Rigger 9. APPROVALS Required lift Approvals Lift plan prepared by Lift plan reviewed by Lift plan approved by Name Mohammad Zeya Mohammad Afzal Abdurrahem Mohammad Kyamuddin Name Mohd Uroj Sukhbir Singh Taufiq no no good no 7.3 Above ground Hazards Electrical cables Telephone cables no no Lampposts Other cranes Trees Conflicting tasks in area Other - describe no no no no Concrete/Bitumen Gravel/Other list is not exhaustive Environmental conditions (weather and permissible limits) Illumination in the pick-up and lay-down areas Proximity of hazards, obstructions in the path of load Contingency plan in case the task changes Access and emergency escape routes Experience, competence and training of personnel Number of personnel required for task Pre-Use Inspection of equipment by Operator Tool Box Talk, including Safety and Stopping the job Signature √ √ √ √ √ √ 4 As required As required Date 4/10/2023 4/10/2023 4/10/2023 4/10/2023 Signature Date 4/10/2023 4/10/2023 4/10/2023 Lifting details (step by step) 1) Hold a Pre job meeting (TBT) with all parties involved. 2) Verify load weight. 3) Ensure barriers are in place and the load travel path and lay down area is clear of obstruction. 4) Carry out pre-start for the HAIB crane. 5) Carry out pre-use inspection for the lifting accessories. 6) Attach the tag line to the load. 7) Attach the sling to the load and ensure the load is secured. 8) Attach the slings on to the crane main hook. 9) Banksman to give hand signal to the crane operator once the sling is hooked. 10) HIAB Truck operator picks up the load and follows banksman signals to hoist & slew the load from Ground to Trailer and vice versa 11) Upon confirmation from client the position of the load is acceptable, remove all lifting tackles. 12) Ensure the area is safe and finish the lifting operation. 13) Housekeeping.