CONSTRUCTION OF REINFORCED CONCRETE RING WALL FOUNDATIONS FOR TWO(2) UNITS VERTICAL STORAGE TANKS (T-1 & T-2) CAIP Cocochem Compound, San Pascual, Batangas ACCOMPLISHMENT REPORT Completed Tank T-1 (May 31,2021) 1|Page Earth and Demolition Works for T-2 (June 1 to 5, 2021) 2|Page Form and Rebar Works Accomplishment for T-2 (June 6 to 15, 2021) 3|Page Form and Rebar Works Accomplishment for T-2 (June 16 to 23, 2021) 4|Page T-2 Ready for Concrete Pouring (Since June 25, 2021) Prepared By : 5|Page