TECHNICAL COMMENT SHEET Rev. BK-TNG WELLHEAD PLATFORM PROJECT Project Document No.: 1014-BKTNG-EL-RPT-0001 Rev 0 Document Title: Electrical Design Basis. B Prepared by: T.H. Toai Checked by: P.H.Viet Authorised by: L.V.Dung Sign: Sign: Sign: Date: 24/02/2014 Date: 24/02/2014 Date: 24/02/2014 Sheet No.: C-1014-BKTNG- EL-RPT-0001 CODE : 1 By Status: Status *) Comment No. Description Criticality **) Comment O/C/CI TECHNICAL COMMENTS - FEED CI T.H. Toai VSP Comment: This Electrical Design Basis, Rev.0 will be approved with minor comment as below: For Sections 6.1: Last paragraph: Please correct that fuel of GTG is gas only, not dual fuel. 1 Technip Respond: Noted. Will be corrected in next issue. *) O = Open; C = Closed; CI = Closed if implemented in document. **) NC =Non Conformance (Response required); N=Note (Response required); A=Advice (No Response Required). Code 1: Code 2: Code 3: Documents to which it has no comments, WORKS can proceed; Documents to which it has minor comments, WORKS may proceed but CONTRACTOR to revise and resubmit accordingly. Documents rejected. CONTRACTOR shall re-prepare the documents and re-submit for COMPANY approval. Page 1 of 1 FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 2 of 47 TABLE OF CONTENTS 1.0 GENERAL 4 1.1 Background 4 1.2 Purpose of document 4 1.3 Definitions and Abbreviations 5 1.4 Reference Documents 7 1.5 Units of measurements 8 1.6 Language 8 2.0 CODES, STANDARDS AND APPILCABLE DOCUMENTS 8 2.1 Applicable IEC standards 8 2.2 Other standards 11 3.0 ENVIRONMENT CONDITIONS 13 4.0 ELECTRICAL EQUIPMENT ENCLOSURE AND HAZARDOUS AREA CLASSIFICATION 13 4.1 Operational safety and reliability 13 4.2 Standardization of Equipment and Materials 13 4.3 Maintainability and Accessibility 13 4.4 Protection against Explosion and Fire Hazard 14 4.5 Certificates, Declarations and Test Reports 14 4.6 Degree of Protection 15 5.0 ELECTRICAL SYSTEM DESIGN 15 5.1 General 15 5.2 System Voltage 15 5.3 Equipment Operating Voltages 16 5.4 Voltage and Frequency Variation 17 6.0 LOAD ASSESSMENT AND ELECTRICITY CONSUMPTION 17 6.1 Main Power Generators 18 6.2 Distribution Transformers 18 6.3 Emergency Power Generator 18 6.4 Other Electrical Equipments 19 6.5 Short Circuit Ratings 19 7.0 ELECTRICAL POWER GENERATION AND DISTRIBUTION SYSTEM DESCRIPTION 19 7.1 Power Generation System Operation 19 7.2 Power Distribution 19 8.0 DESIGN AND SELECTION OF ELECTRICAL EQUIPMENT 20 8.1 Main Power Generators 20 8.2 Emergency Diesel Generator 22 FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 3 of 47 8.3 Synchronization: 23 8.4 Power Supply Monitoring and Control System (PSMCS) 23 8.5 6.0kV Switchgear 24 8.6 Distribution Transformer 24 8.7 Neutral Grounding Resistor 25 8.8 400V Switchboard/MCC 25 8.9 Integrated Motor Control Centre (IMCS) 27 8.10 Electric Motors 27 8.11 Variable Frequency Drive (VFD) 28 8.12 Uninterruptible Power Supply (UPS) 29 8.13 Bus duct 30 8.14 Electric Power and Control Cables 31 8.15 Sizing of Cables 32 8.16 Cable Installation 33 8.17 Lighting System 33 8.18 Navigational Aids 36 8.19 Socket Outlets 38 8.20 Multi Cable Transits (MCT) 38 8.21 Cable Glands (stainless steel/ nickel plated brass) 39 8.22 Electrical Heat Tracing 39 8.23 Junction Boxes 40 8.24 Cable Ladder/ Tray 40 8.25 Conduits and Accessories 41 9.0 CONTROL, PROTECTION AND MONITORING 41 9.1 Generator Feeders 41 9.2 Switchgear/ MCC Incomer Feeders 42 9.3 Motor Starters 42 9.4 Transformer Feeder 43 9.5 Feeders 43 9.6 Small Power and Lighting 43 10.0 EARTHING 43 10.1 System Earthing 43 10.2 Equipment Earthing 44 10.3 Lightning Protection 44 11.0 EQUIPMENT CLEARANCE 45 12.0 ELECTRICAL ROOM REQUIREMENT (WITH RAISED FLOOR) 45 13.0 ELECTRIC HEATERS FOR PROCESS/UTILITY APPLICATIONS 46 FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 4 of 47 1.0 GENERAL 1.1 Background Thien Ung field is located in the middle part of Block 04-3 in the Nam Con Son Basin, offshore the Socialist Republic of Vietnam, approximately 15 km of Dai Hung field, and approximately 270 km southeast of Vung Tau. The Block 04-3 covers an area of approximately 2600 km2. The Thien Ung field is including its 2 structural parts. Thien Ung structure discovery was made in 2004 with the 04-3-TU-1X well. Two subsequent appraisal wells (04.3-TU-2X and 04.3-TU-3X), drilled and tested respectively, delineated the field. Location of Thien Ung field is shown in Figure 1.1 below. Figure 1.1: Thien Ung Reservoir Location 1.2 Purpose of document The intent of this document is to provide an overview and guidelines for electrical power generation, distribution, and detail design of the electrical systems and services in Thien Ung Wellhead platform (BK-TNG). The design shall fulfill the following engineering/design requirements: Safe operation and maintenance for personnel as well as equipment Reliable electrical power generation and distribution systems under all working condition at site Efficient power distribution and utilisation Commonality & interchange ability of equipment Spare capacity for future load Ease of operation, and minimum maintenance of equipment Withstand the technical scrutiny of the third party independent verification body (appointed by COMPANY) FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 5 of 47 The scope of electrical work covers all electrical supplies, main and emergency power generation, distribution, emergency generation, power system protection, earthing, power and control cabling, AC UPS systems, small power distribution and wiring, equipment, materials, lighting and small power, local control stations, navigational aids, and any other electrical items necessary for the completion of the works within the overall scope of the project. It shall be supplemented by, and shall be read in conjunction with: The Local statutory requirements and laws of the Socialist Republic of Vietnam, as applicable. International Codes, Standards and Specifications. Other Codes, Standards and Specifications which are cross referred in the above documents shall also be considered. The minimum technical requirements are defined in this document, they are therefore subject to evolution and improvements but with the approval of COMPANY. For more detailed information relevant specifications shall be referred. 1.3 Definitions and Abbreviations 1.3.1 Definitions PROJECT FEED service for BK-TNG Wellhead Platform COMPANY The party which initiates the project and ultimately pays for its design and construction and owns the facilities. Here the COMPANY is Vietsovpetro (Referred to as VSP) The party which carries out all or part of the design, engineering, procurement, construction and commissioning of the project CONTRACTOR VENDOR 1.3.2 The party on which the order or contract for supply of the equipment / package or services is placed Abbreviations ACB Air Circuit Breaker AGRU Acid Gas Removal Unit BK-TNG Thien Ung Wellhead Platform CCU Central Control Unit CWB Copper Wire Braided (tinned) DCS Distributed Control System ELCB Earth Leakage Circuit Breaker ESD Emergency shutdown (system) FEED Front - End Engineering Design FGS Fire and Gas System FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 6 of 47 FCU Feeder Control Unit FPR Feeder Protection Relay GCP Generator Control Panel IP Ingress Protection IMCS Integrated Motor Control System HPS High Pressure Sodium LSZH Low smoke zero halogen HV High Voltage LV Low Voltage LCS Local Control Station or Remote Control Unit (RCU) MBI Metal Halide MCB Miniature Circuit Breaker MCCB Moulded Case Circuit Breaker MCT Multi Cable Transit MCU Motor Control Unit NGR Neutral Grounding Resistor or Neutral Earthing Resistor (NER) PAGA Public Address and General Alarm PSMCS Power Supply Monitoring and Control System PVE Petrovietnam Engineering Consultancy Joint Stock Corporation RCCB Residual Current Circuit Breaker SDS Shut Down System SWB Steel Wire Braided (galvanized) TPGM Technip Geoproduction (M) Sdn Bhd TPVN Technip Vietnam Company Limited UPS Uninterruptible Power Supply UCP Unit Control Panel VCB Vacuum Circuit Breaker VCU Vacuum Contactor Unit VFD Variable Frequency Drive VSP Vietsovpetro FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 7 of 47 1.4 Reference Documents 1014-BKTNG-EL-EL-0001 Electrical Load List 1014-BKTNG-EL-RPT-0002 Electrical Load Analysis and Main Equipment Sizing Calculation 1014-BKTNG-EL-SP-0001 Specification for HV Switchgear 1014-BKTNG-EL-SP-0002 Specification for LV Switchboard/ MCC 1014-BKTNG-EL-SP-0004 Specification for Distribution Transformer 1014-BKTNG-EL-SP-0005 Specification for AC UPS 1014-BKTNG-EL-SP-0007 Specification for Navigational Aids System 1014-BKTNG-EL-SP-0008 Specification for LV Motors 1014-BKTNG-EL-SP-0010 Specification for Electrical Cables 1014-BKTNG-EL-DS-0001 Datasheet for HV Switchgear 1014-BKTNG-EL-DS-0002 Datasheet for LV Switchboard/ MCC 1014-BKTNG-EL-DS-0003 Datasheet for Distribution Board 1014-BKTNG-EL-DS-0004 Datasheet Distribution Transformer 1014-BKTNG-EL-DS-0005 Datasheet for AC UPS 1014-BKTNG-EL-DS-0007 Datasheet for Navigational Aids System 1014-BKTNG-EL-DS-0008 Datasheet for LV Motors (Typical) 1014-BKTNG-EL-DS-0010 Datasheet for Gas Turbine Generator (GTG) 1014-BKTNG-EL-DS-0011 Datasheet for Emergency Diesel Generator (EDG) 1014-BKTNG-PR-RPT-0001 Process and Utility Design Basis 1014-BKTNG-ME-SP-0016 Specification for Gas Turbine Generator Package 1014-BKTNG-ME-SP-0017 Specification for Emergency Diesel Generator Package 1014-BKTNG-ME-DS-0010 Datasheet for Gas Turbine Generator Package FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 8 of 47 1.5 Units of measurements The International System of units (S.I.) shall be used in all drawings and documentation unless otherwise stated. 1.6 Language All drawings, documentation and correspondence shall be in the English Language. 2.0 CODES, STANDARDS AND APPILCABLE DOCUMENTS The electrical system design shall generally comply with the latest revision and relevant sections of the following regulations, standards and codes of practices. The applicable laws, international codes and standards are as follows: Relevant Laws of Socialist Republic of Vietnam International Electrotechnical Commission (IEC), and other standards listed in section 2.1 of this document. Note: Unless specifically designated by date, the latest edition of each publication shall be used, together with amendments, supplements or revision thereto. 2.1 Applicable IEC standards IEC 60034 Series Rotating Electrical Machines IEC 60038 IEC Standard Voltage IEC 60044-1 Instruments Transformers – Part 1: Current Transformer IEC 60044-2 Instruments Transformers – Part 2: Inductive Voltage Transformer IEC 60050 International Electro technical Vocabulary IEC 60071 Insulation Co-ordination IEC 60072 Series Dimensions and output series for rotating electrical machines IEC 60073 Basic and Safety Principles for Man-machine Interface, Marking and Identification - Coding Principles for Indicators and Actuators IEC 60076 Power transformers (all parts applicable to dry type power transformers) IEC 60079 Electrical Apparatus for Explosive Gas Atmospheres. IEC 60079-30 Electrical Apparatus for Explosive Gas Atmospheres – Electrical resistance heat tracing. IEC 60085 Thermal evaluation and classification of electrical insulation IEC 60092-350 Electrical Installations in Ships - Part 350: Shipboard power cables - General construction and test requirements FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 9 of 47 IEC 60092-351 Electrical Installations in Ships - Part 351: Insulating materials for shipboard and offshore units, power, control, instrumentation, telecommunication and data cables IEC 60092-352 Electrical Installations in Ships - Part 352: Choice and installation of electrical cables IEC 60092-353 IEC 60092-354 Electrical Installations in Ships - Part 353: Single and multi-core non-radial field power cables with extruded solid insulation for rated voltage 1 kV and 3 kV Electrical Installations in Ships - Part 354: Single -and three-core power cables with extruded solid insulation for rated voltages 6 kV (Um = 7,2kV) up to 30 kV (Um = 36 kV) IEC 60092-359 Electrical Installations in Ships - Part 359: Sheathing Materials for Shipboard Power and Telecommunication Cables IEC 60092-376 Electrical Installations in Ships - Part 376: Cables for control and instrumentation circuits 150/250 V (300 V) IEC 60099 Surge Arresters IEC 60137 Bushings for Alternating Voltages Above 1000V IEC 60146 Semiconductor converters IEC 60228 Conductors of insulated cables IEC 60255 Electrical relays (all parts relevant to Project application) IEC 60269 Low-voltage fuses IEC 60270 Partial discharge measurements IEC 60282 High-voltage fuses IEC 60287 Electric cables – Calculation of the current rating IEC 60331 Fire resisting characteristics of electric cables IEC 60332 Tests on electric cables under fire conditions IEC 60391 Marking of insulated conductors IEC 60404 Magnetic Materials (all parts relevant to Project application) IEC 60439 Low voltage switchgear and control gear assemblies IEC 60445 Basic and safety principles of man-machine interface, marking and identification - Identification of equipment terminals and conductor terminals IEC 60446 Identification of conductors by colors or numerals IEC 60470 High-voltage A.C. contactors FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 10 of 47 IEC 60502:2006 Extruded solid dielectric insulated power cables for rated voltages from 1kV to 30 kV IEC 60514 Acceptance Inspection of Class 2 Alternating Current Watthour Meters IEC 60529 Classification of Degrees of Protection Provided by Enclosures IEC 60623 Ni Cd stationary batteries IEC 60664 Insulation co-ordination for equipment within low-voltage systems IEC 60688 Electrical measuring transducer for converting A.C. electrical quantities to analogue or digital signals IEC 60754 Test on gases evolved during combustion of materials from cables (Part 1 & Part 2) IEC 60811 Common test methods for insulating and sheathing materials of electric cables IEC 60836 Specification for Silicone Liquids for Electrical Purposes IEC 60885 Electrical test methods for electric cables IEC 60896 Stationary lead-acid batteries (Part 21: Valve regulated types methods of test & Part 22: Valve regulated types requirements) IEC 60898-1 Circuit-breakers for overcurrent protection for household and similar installations IEC 60909 Short-circuit currents in three-phase a.c. systems IEC 60947 Low voltage switchgear and control gear IEC 61000 Electromagnetic compatibility (EMC) IEC 61034 Measurement of smoke density of electric cables burning under defined conditions IEC 61140 Protection against electric shock – common aspects for installation and equipment IEC 61204 Low voltage power and supply devices, DC output – Performance characteristic IEC 61515 Mineral insulated thermocouple cables and thermocouples IEC 61850 Series Communication Networks and Systems in Substations IEC 61892 Mobile and Fixed Offshore Units - Electrical Installations (all parts relevant to Project application) IEC 62040 Stabilized Power Supplies, D.C. Output FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 11 of 47 IEC 62271 2.2 High-voltage switchgear and control gear (all parts relevant to Project application) Other standards API RP 14FZ Design and Installation of Electrical Systems for Fixed and Floating Offshore Petroleum Facilities for Unclassified and Class I, Zone 0, Zone 1 and Zone 2 Locations IES Lighting Handbook IES RP-12 Recommended Practice for Marine Lighting CAP 437 Civil Aviation Authority (London) Offshore Helicopter Landing Areas : A Guide to Criteria, Recommended Minimum Standards and Best Practices NFPA 496 Standard for Purged and Pressurized Enclosures for Electrical Equipment in Hazardous (Classified) Locations NEMA MG 1 Motors and Generators NEMA MG 2 Safety standard and guide for selection, installation and use of electric motors and generators NEMA VE 1 Metal Cable Tray Systems NEMA VE 2 Cable Tray Installation Guidelines IALA International Association of Lighthouse Authorities NEK606 Cables for Offshore Installations Halogen Free, or Mud Resistant NFPA 70 National Electrical Code (2011) IEE Recommendations for the electrical and electronic equipment of Mobile and Fixed offshore Installations NFPA-780 Standard for the Installation of Lightning Protection Systems IEEE std 32 Standard Requirements, Terminology, and Test Procedures for Neutral Grounding Devices IEEE std 515 IEEE Standard for the Testing, Design, Installation, and Maintenance of Electrical Resistance Trace Heating for Industrial Applications IEEE std 844 IEEE Recommended Practice for Electrical Impedance, Induction, and Skin Effect Heating of Pipelines and Vessels IEEE std 519 IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 12 of 47 IEEE std 484 IEEE Recommended Practice for Installation Design and Installation of Vented Lead-Acid Batteries for Stationary Applications IEEE std 485 IEEE Recommended Practice for Sizing Lead-Acid Batteries for Stationary Applications IEEE std 142 IEEE Recommended Practice for Grounding of Industrial and Commercial Power Systems IEEE std 242 IEEE Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems ISO 13702 Petroleum and natural gas industries - Control and mitigation of fires and explosions on offshore production installations API 500 Recommended Practice for Classification of Locations for Electrical Installations at Petroleum Facilities Classified as Class I, Division I and Division 2 API 505 Recommended Practice for Classification of Locations for Electrical Installations at Petroleum Facilities Classified as Class I, Division I and Division 2, Third Edition SOLAS 2004 Safety Of Life At Sea DNV-OS-A101 Safety principles and Arrangements DNV-OS-D201 Electrical Installations DNV-OS-D202 Automation, Safety, and Telecommunication Systems (Oct. 2008) The design and engineering of the electrical installation shall satisfy all statutory requirements of the national and/or local authorities. The electrical installation shall be suitable for the site conditions. In the event of contradiction between the requirements of this document, IEC, ISO, NFPA, DNV, NEMA, API, the particular IEC requirement shall prevail, provided the statutory obligations of both local and national authorities of the Socialist Republic of Vietnam are satisfied. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 13 of 47 3.0 ENVIRONMENT CONDITIONS All electrical equipments installed outdoors shall be suitable for operation on offshore environment conditions. Electrical equipment installed indoors shall normally be operated in air conditioned environment; however they shall be suitable for short time duty in the outdoor environmental conditions prevailing at site, without temperature rise of any part of the electrical equipment exceeding the maximum permissible temperature rise values stipulated in the relevant IEC standards. The design environmental and climatic data are summarised below: Atmosphere : Saliferous and Marine Temperature outdoor : Maximum ambient = 390C Minimum ambient = 210C Relative humidity : Average ambient = 27.10C Maximum = 98 % Minimum = 62 % Indoor Temperature + With Air-conditioning : 240C , +/- 20C (Switchgear/MCC Room) 200C, +/- 20C (Battery Room) + Without Air-conditioning : +Δ50C compare to outdoor temperature. Design room max is 440C (ventilation only) For all the other relevant environmental data, refer to Doc. No.: 1014-BKTNG-PR-RPT-0001; Document Title: “Process and Utility Design Basis”. 4.0 ELECTRICAL EQUIPMENT ENCLOSURE AND HAZARDOUS AREA CLASSIFICATION 4.1 Operational safety and reliability The design of the electrical installation shall be based on the provision of a safe and reliable supply of electricity at all times. Safe conditions shall be ensured under all operating conditions, including those associated with start-up and shutdown of plant and equipment, and throughout the intervening shutdown periods. The design of electrical systems and equipment shall ensure that all operating and maintenance activities can be performed safely. Provisions for alternative supply sources and supply routes, spare/standby capacity and automatic restarting schemes are required. 4.2 Standardization of Equipment and Materials Equipment of similar nature, identical components and construction should be of the same manufacturer. This applies to HV switchgear, LV Switchboard, MCC, transformers, power and convenience outlets and luminaries, local control station, battery and safety switch. Standardization of materials and equipment shall be aimed for and compatible with rational design. Equipment which will become obsolete in the near future shall not be selected. 4.3 Maintainability and Accessibility Electrical facilities shall be designed, constructed and installed so that components of the facilities are accessible for maintenance and capable of being repaired and replaced. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 14 of 47 4.4 Protection against Explosion and Fire Hazard Hazardous area classification drawings and document prepared by the Process Safety Discipline. This shall be used as the basis for the proper selection of electrical equipment and installations. Electrical equipment should, as far as practical and economic, be located in the least hazardous areas. Electrical equipment installed in hazardous area shall have a type of protection suitable for the relevant zones and specified in accordance with IEC 60079. Electrical equipment installed in indoor, non-hazardous areas within process areas shall be of a standard industrial type as specified in the relevant equipment design requirements. Although many types of protection are available, the following shall be used in the final selection: - For Zone 1, LV motors and all inherently non-sparking equipment, e.g., junction boxes and luminaires, shall have type of protection ‘d’, ‘de’ or 'e'. HV motors and all inherently sparking equipment, e.g., switchgear and controlgear, shall have type of protection 'd' or ‘de’. Where such type of protection is not available, e.g., large high speed HV motors, type of protection 'p' shall be used. HV motors with type of protection 'e' shall not be used in zone 1 area. - For Zone 2, motors and inherently non-sparking equipment shall have type of protection 'n', all equipment approved for Zone 1 is also acceptable. Inherently sparking equipment shall have type of protection 'd', ‘de’ or 'p', as stated for Zone 1. For a process plant/ unit having Zone 2 hazardous area, outdoor non-hazardous area within its extent, Zone 2 equipment shall be installed to cater possibility of reclassification, interchange-ability of equipment and their spares. These criteria shall be applicable to equipment like motors, lighting fixtures, remote control units and welding and convenience sockets. Equipment installed in non-hazardous areas such as within living quarters shall be standard-industrial type/ domestic type depending upon type of installation and/ or application. For the installation of electrical equipment in hazardous areas, IEC 60079-14 shall be complied with and shall be certified by the approved authorities such as Baseefa in UK, PTB in Germany, LCIE in France, CSI in Italy, UL and FM in USA, CSA in Canada. All hazardous area equipment shall be indexed against area classification, certification, and required maintenance to maintain certification validity. Copies of all hazardous area certificates or certificate of conformity shall be provided for all electrical/ electronic hazardous area equipment, in the English language. 4.5 Certificates, Declarations and Test Reports For all major equipment, shall be obtained at least the Manufacturer’s test reports in accordance with the equipment design requirements, e.g., for generators, motors, HV and LV switchgear, UPS equipment and transformers. Further certificates or declarations relating to the application of equipment for use in hazardous areas may be required by local authorities, according to the following rules: a) For electrical apparatus in Zone 0, Zone 1 and Zone 2 areas, a certificate of conformity shall be obtained from the Manufacturer/Supplier. b) For electrical apparatus in Zone 2 areas, which has type of protection ‘n’, a declaration of compliance may be accepted instead of a certificate of conformity. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 15 of 47 4.6 Degree of Protection Unless otherwise specified in the equipment specification, the following minimum degrees of protection of the enclosure against contact with live or moving parts and against ingress of solid foreign bodies and liquid shall be selected, in accordance with IEC 60529: Indoors (with HVAC system) HV switchgear : IP32 - LV switchboard / MCC : IP41 - UPS (Indoors with HVAC system) : IP31 - Ex-battery & enclosure : IP44 : IP23 Indoors (without HVAC system) - Dry Transformer (in enclosure) Outdoors areas - Switch-rack, outdoor luminaire and JB : IP56 - Electric motors, alternators (outdoors/indoors) : IP56 IP of other equipment/devices/materials shall be according to DNV-OS-D201 5.0 ELECTRICAL SYSTEM DESIGN 5.1 General The design of the electrical installation shall be based on the fundamental principles referred to above. The designs and philosophies relating to the electrical system shall be adequately illustrated by a system design description, a key single line diagram, detailed single line diagrams, layout drawings, installation details, specifications, calculations and etc as required. System studies, protection reports and the like shall be provided in support of the design, as required by relevant codes, standards and good engineering practice. Power system studies shall be carried out using suitable and applicable software. 5.2 System Voltage The electrical system voltages for the BK-TNG shall be as follows: Generation voltages and frequency: HV generation = 6.0kV, 3-phase, 3-wire, 50Hz LV generation = 400/230V, 3-phase, 4-wire, 50Hz FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 16 of 47 Distribution/Utilization voltages and frequency: 5.3 HV System = 6.0kV, 3-phase, 3-wire, 50Hz LV System = 400/230V, 3-phase, 4-wire, 50Hz = 230V, 1-phase, 2-wire, 50Hz Equipment Operating Voltages The system details at various utilisation equipment voltages shall be as given below: Service Voltage Phase HV Main Power Generator 6.0kV 50Hz , 3-phase, 3-wire HV Power Distribution 6.0kV 50Hz , 3-phase, 3-wire Motor rated above 200kW (Note 1) 6.0kV 50Hz , 3-phase, 3-wire Motors rated 200kW and below 400V 50Hz , 3-phase, 3-wire Emergency Power Generator 400V 50Hz , 3-phase, 4-wire LV Power distribution 400V 50Hz , 3-phase, 4-wire Lighting & Small Power 230V 50Hz , 1-phase, 2-wire HV Switchgear : Motor VCU Control 230V 50Hz , 1-phase, 2-wire Uninterruptible Power Supply Voltage Phase Navigational Aids 24V DC UPS Helideck Lights, Aviation Obstruction Lights 230V AC UPS, 50Hz , 1-phase, 2-wire DCS, ESD, FGS, Public Address and Alarm (PAGA) System 230V AC UPS, 50Hz , 1-phase, 2-wire (Redundant) Turbine/ Emergency/ Gas Engine Generator Control Panel, Turbine compressor control panel and critical mechanical package control panel 230V AC UPS, 50Hz , 1-phase, 2-wire Telecommunication 230V AC UPS, 50Hz , 1-phase, 2-wire VCB & ACB tripping/closing circuit, and protective relays and signalization 230V AC UPS, 50Hz , 1-phase, 2-wire (Refer Note 2) FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 17 of 47 Uninterruptible Power Supply Turbo Machinery (back-up) DC post lube oil pump Voltage Phase 230V AC UPS, 50Hz , 1-phase, 2-wire Note 1: Approval for using 400V driver motors rated above 200kW, may be considered on a case-to-case basis by COMPANY. Note 2: Any other required operating voltage should be derived internally by Manufacturer. 5.4 Voltage and Frequency Variation The electrical system shall be designed based on the following criteria: a) Under steady state condition, the voltages at all points on the system shall be kept between +5% and –5% of the nominal voltage and the frequency shall be maintained within +/-2% of rated frequency. b) The voltage dip during large motor starting as per the following:- 15% for voltage dip at Switchgear/MCC bus - 20% at motor terminal for HV motors (DOL) - 20% at motor terminal for LV motors (DOL) Voltage transient due to load variation tolerance shall be +/-20% from nominal voltage as per IEC 61892-1. 6.0 LOAD ASSESSMENT AND ELECTRICITY CONSUMPTION A schedule of the installed electrical loads, the maximum normal running load and the peak load, expressed in kilo-watt, kilo-VAr and kilo-VA and based on the facility design capacity when operating under the site conditions specified, shall be prepared. It shall be completed and updated regularly throughout the design stage of the project and shall form the basis for provision of the necessary electricity supply and distribution system capacity. The following formulas shall be used for determining the total electrical loads: Maximum Load = The larger value of either {A + (0.3xB)} or {A + Largest Single Intermittent Load} Peak Load = The larger value of either {Maximum load + (0.1xC)} or {Maximum Load + Largest Single Standby Load} Where: A = Total sum of Continuous Loads (in Load List) B = Total sum of Intermittent Loads (in Load List) FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 18 of 47 C = Total sum of Standby Loads (in Load List) All known future loads for Continuous, intermittent and standby operation shall also be defined and included in the equipment sizing. The capacity of the electrical points of supply (generation, and associated switchgear) shall be capable of supplying continuously 120% of the peak load, assessed according to the applicable load data, without exceeding specified voltage limits, and equipment ratings. 6.1 Main Power Generators There shall be two (2) nos. of gas turbine driven main power generators (1 + 1) on BK-TNG. Each of the main power generators shall be sized to cater for 100% of the total (ultimate) load of the BK-TNG during normal operation. Hence, one of the two main power generator shall act as the duty machine, the remaining unit to act as the “cold” standby machine. The main power generation shall be capable of fulfilling at least the following specific requirements: a) Supplying maximum load and simultaneously starting the largest motor load, with the spare unit inoperative in accordance with the load list summary. b) Maintaining the stability of the electrical system in response to step changes in load or available power. c) Maintain adequate spare capacity for known future loads as shown in electrical load list and mechanical equipment list. Main power generator plant site rating should be capable of sustaining at least 120% of the calculated “peak load”. The two main power generators installed shall have gas fuel capability of using treated well gas as fuel. 6.2 Distribution Transformers Dry type cast resin distribution transformers shall be used. Two distribution transformers feeding into each main LV switchboard and shall be rated for 2 x 100% configuration – i.e. Both operating transformers shall be capable of catering to at least 100% of the entire main LV switchboard load. Transformers shall be sized to handle the tabulated peak operating load, plus 20% spare capacity. 6.3 Emergency Power Generator In the event of loss of mains power supply from all the main power generators, emergency electrical power to the BK-TNG will be supplied by an emergency power generator. The emergency power generator shall be sized to cater for all the life support loads, essential process and utility loads, essential Living Quarters (LQ) loads plus black-starting loads (i.e. those necessary to allow restarting of the first main power generator). The emergency power generator shall have battery start (primary) and hydraulic (secondary) start facilities. The emergency power generator shall have additional at least 20% spare capacity of the calculated emergency ‘peak load’ in anticipation for future load growth. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 19 of 47 6.4 Other Electrical Equipments Unless otherwise specified, other electrical not identified on the above shall be sized based on the peak load plus 20% spare capacity. 6.5 Short Circuit Ratings All equipment shall be capable of withstanding the effects of short circuit currents and consequential voltages arising in the event of equipment or circuit faults. The short circuit ratings of equipment and cables, including the short circuit making and breaking capacity of circuit switching devices, shall be based on parallel operations of all supplies which can be paralleled during normal-operations; it will also include the contribution that can be expected from the connected load. The use of current-limiting reactors, Is-limiters and similar devices intended specifically as a means of limiting the magnitude of short circuit currents shall not be used. 7.0 ELECTRICAL POWER GENERATION AND DISTRIBUTION SYSTEM DESCRIPTION 7.1 Power Generation System Operation The main generating plant shall consist of 2 x 100% gas turbine driven 6.0kV, 50 Hz, 3-phase main power generators. Emergency power shall be provided at 400/230V, 50 Hz, 3-phase, 4wire by an Emergency Power Generator. The emergency power generator shall start automatically on detection of mains failure – and if ESD permitting. It shall be capable of starting, accelerating to operating speed, and carrying load after actuation of start signal. The emergency power generator shall be capable of continuous parallel operation with main power turbine generators. The electrical power distribution system shall initially be energised by emergency power generator. The system control operator has at this point to select the main duty power generators (to be started-up) and close low voltage breakers needed to energise the selected main power generator auxiliaries and utility loads. From the selected machine control panel location a manual start shall be attempted. Upon a successful main generator start, generator feeder breaker shall be closed to energise the HV Switchgear and downstream power distribution system. During commissioning and in case of emergency power generator also fails, temporary power supply generator shall feed power to selected LV loads. Once the 400V switchboards are energized from the main power generator, the emergency power generator can be taken off-line and run-down. A trip signal originating from a generator control panel shall trip the generator circuit breaker and the excitation system and prime mover. 7.2 Power Distribution The power distribution system philosophy requires electrical systems to be designed to maximize flexibility, reliability and maintainability. The ultimate goal during distribution system design is to allow for reliable process operation concurrent with ongoing isolation and maintenance of selected parts of the electrical system. The project distribution system voltages shall be as follows: FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 20 of 47 a) 6.0 kV, 50Hz, 3-phase, 3-wire, low resistance grounded wye shall be utilised for power generation and distribution; b) 400/230V, 50Hz, 3-phase, 4-wire, solidly grounded wye shall be utilised for distribution to motor control centres; c) 400V, 50Hz, 3-phase, 3-wire, un-grounded wye shall be utilised for LV distribution (where necessary). The design of low voltage (400/230V, 50Hz, 3-phase, 4-wire) power distribution system shall be provided with both main bus sections and emergency bus sections. An auto-transfer switch system shall transfer power supply from main generator (normal) supply to emergency generator supply and vice versa (re-transfer). Both “Transfer” and “re-transfer” shall be effected by “make-before-break” principle so as to realise a no-break transition - when both sources are available. High voltage (6.0kV, 50Hz) switchgear comprising bus section ‘A’ and bus section ‘B’, normally closed bus-coupler, main generator incomers and outgoing feeders/motor starters. For 400/230V consumers, the 6.0kV supply is stepped-down to main 400/230V Switchboard/MCC through 6.0/0.420 kV distribution transformers. All electric power consumed by the LQ shall be derived from the BK-TNG power distribution system. Dual redundant feeders shall be utilised for transmitting 400/230V AC normal & emergency power, and AC UPS power from BK-TNG to LQ. 8.0 DESIGN AND SELECTION OF ELECTRICAL EQUIPMENT Design life for all facilities shall be 25 years. Equipment/materials must have at least 2 years of proven offshore field experience with good client reference. All equipment/material shall be sourced from the approved Manufacturer list which had been approved by COMPANY. Main Power Generators shall be installed in a well-ventilated Main Power House and Emergency Power Generator shall be housed in a movable Emergency Generator Room. Separate HV Switchgear room, Transformer room, LV MCC room and UPS/ Emergency MCC room, Battery room shall be provided. 8.1 Main Power Generators The 6.0kV turbine driven main power generators shall be designed and constructed in accordance with the Project Specification for Power Generators (1014-BKTNG-ME-SP-0016) and Project Datasheet Power Generators (1014-BKTNG-ME-DS-0010 & 1014-BKTNG-ELDS-0010). The main power generator skids shall be housed in a 316L stainless steel clad weather-proof / acoustic enclosures, and designed and certified suitable for operating in Zone 2 hazardous location. 8.1.1 Generator System Control The generator control system shall cater to “n + 1” configuration of 6.0kV, 3 -phase, 50Hz, 0.8 power factor, low resistance grounded turbine driven main power generators - where n=1. The main power generators shall each be furnished a package comprising an enclosed skid mounted turbine driver/generator assembly and a remotely mounted PLC based unit control panel (GCP) complete with all controls, governors, automatic voltage regulator and ancillary equipment. Generator shall be suitable for operation: a) In stand-alone operation FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 21 of 47 b) Parallel with the other main power generators c) Parallel with the emergency power generator The turbine generator control panels shall include but not limited to the following: a) Power generation system b) Control and metering c) Generator protection relays d) Interface with Power Supply Monitoring and Control System (PSMCS) The GCP for each main power generator shall consist of a turbine control section and an alternator control section. The complete unit for each machine shall be installed as to form a single row of control panels (for all machines) in the control room. All control and operation functions of the main power generators and emergency power generators shall be located on the individual generator(s) control panel which provides unit control and protection. There is no intention of remote operation of any machine, except from the PSMCS [described in 8.3]. Emergency stopping of the main generator shall be effected either by depressing the generator control panel mounted “emergency push button” for the respective main generator GCP or a similar hard wired “emergency stop” push button located adjacent to each main generator package skid. Emergency stop trip signal from ESD shall be similarly routed to the GCP. The main generators shall be provided with automatic control schemes. This shall include the facilities for auto-starting, automatic synchronising and automatic loading. Main Generation shall be controlled as follows: Isochronous and droop speed control. Isochronous and droop voltage control Voltage control equipment consisting of automatic voltage control with a manual control stand-by system. Manual control system shall follow the set point of the automatic control system to allow for automatic changeover from the automatic to the manual control system without significant voltage transients in the case of the automatic voltage control system failure. Reactive-Power sharing among sets shall be provided for the voltage control system. Each main generator shall be provided with the alarm equipment, indicating instruments and integrating meters and generator protection relay. The main generator shall be equipped with a brushless exciter consisting of a three phase synchronous initiating rectifier assembly and a permanent magnet generator (PMG) pilot exciter. The excitation system shall comprise at least the following: External excitation equipment Duplicate (Main/Standby) Automatic Voltage Regulators (AVR) Voltage adjuster (rheostat) AVR excitation failure relay (alarm) The AVR shall be of the electronic type provided with a fine voltage adjuster. It shall include frequency sensing circuitry to limit the ceiling voltage and to prevent damage to components when the generator is driven at reduced speeds, such as when starting or when the engine is at idling speed. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 22 of 47 The AVR shall be matched to the generator characteristics and should be installed in the generator control panel. Generator shall be equipped with a damper winding on the rotor for parallel operation. Both ‘isochronous’, and ‘quadrature droop compensation’ of maximum 5% at full load shall be provided. A droop current transformer and droop rheostat shall be provided. Generators shall be equipped with manual and automatic synchronising facilities including a check synchronising relay and a dead-bus override. In addition automatic synchronising and continuous load sharing with main power generation shall be provided. Mimic diagram based on the key single line diagram shall be made available in the PSMCS to display main circuit breaker status for both the HV Switchgear and the LV Switchboard/MCC. It shall also include alarm and trip indication for each breaker. Generator control panel shall have an HMI for displaying live graphics that describe the workings and condition of the respective generator units. 8.1.2 Generator System Protection, Metering and Monitoring The primary location for the metering, control, protection and monitoring of each generator shall be at their respective GCPs. Secondary metering and monitoring locations shall be the DCS. The DCS shall serve the function of repeating selected status points, analogue values and all distribution alarms and trips and displaying at the DCS console in the Central Control Room. Salient power generation data from GCP to DCS shall be transmitted by redundant RS 485 serial link with MODBUS protocol. 8.2 Emergency Diesel Generator The 400/230V emergency power generator shall be designed and constructed in accordance with the Specification for Emergency Diesel Generator Package (1014-BKTNG-ME-SP-0017) and Datasheet for Emergency Diesel Generator (1014-BKTNG-ME-DS-0011 & 1014-BKTNGEL-DS-0011). A diesel engine driven Emergency Power Generator shall be provided, rated 400/230V, 50Hz, 3-phase, 4-wire, 0.8 power factor, neutral solidly grounded. The emergency power generator package shall be furnished as a skid mounted package (consisting of prime mover, cooling system, dual starting systems, exhaust system, ventilation system and alternator) housed in a 316L stainless steel clad weather-proof / acoustic enclosure - designed and certified suitable for operating in Zone 2 hazardous location. The balance of equipment shall be housed in a GCP consisting of the controls, speed governor, automatic voltage regulator shall be installed remotely in the Emergency Electrical switchgear/MCC room. Facilities for automatic start, test, synchronize and prolonged operation in parallel with the main power generator shall be provided. The emergency diesel generator shall capable of continuous parallel operation with the main power generators for weekly on load testing and maintenance. The Emergency Power Generator itself shall have battery start system and hydraulic start system as primary and secondary starting facilities respectively. The final rating of the emergency diesel generator shall be selected to cater for the following criteria, but not limited to these items: 1. Able to support all the process and utility emergency loads 2. Able to power up all life support systems 3. Able to support the essential Living Quarters (LQ) loads FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 23 of 47 4. All Black starting loads (for starting-up one main power generator) 8.3 Synchronization: The UCPs of the GTG#1, GTG#2 and EDG shall be provided with automatic and manual synchronizing. Synchronizing schemes shall be provided for the circuit breakers associated:- 6.0kV main gas turbine generator 1 circuit; - 6.0kV main gas turbine generator 2 circuit; - 400V EDG incomer Circuit Breaker and 400V Normal Supply incomer circuit Breaker of essential LV switchboard. The scheme shall include the use of AUTO/MANUAL/OFF synchronizing selector switches provided to meet the synchronising requirement. 8.4 Power Supply Monitoring and Control System (PSMCS) PSMCS system (supplied as part of the LV switchboard/MCC package) shall be capable of performing at least the following functions and to have master control of the main power generators: - - - Generator Output Control Fixes steady state voltage and frequency to preset adjustable levels Shares active and reactive load between interconnect sets Allows sets to be selected for base load control Automatically compensates set capability according to fuel type and inlet air temperature Engine Control Automatically starts and loads sets due to operator initiation or detection of low spinning reserve Automatically offloading and stops sets due to operator initiation or high spinning reserve Load Feeder Control - Synchronising - Automatic synchronizing of multiple sets across the bus sections Communication - Initiates load sharing to avert cascade failure of the generation system in the event of one generator being overloaded. Transfer of PSMCS specific data for display on DCS through dedicated redundant RS 485 serial link with MODBUS protocol. Human Machine Interface Industrial PC based interface acting between GCP and operator during both commissioning (set-point configuration) and normal operation (control commands, status & alarm annunciation) Display on-screen, monitored events and mimic diagram of key components under the GCP sphere of influence FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 24 of 47 Power Generation & Distribution System Sequence of Event Recording, data logging and archiving Interface with the generator GCP shall be hardwired for analogue signals and for rapid initiation/execution. Serial link data communication may be deployed if speed of data transmission is not necessary. The PSMCS shall be a stand-alone system with dual redundancy for critical hardware e.g. controllers and data storage. Failure of the PSMCS shall not cripple the operation main power (plant) generators. 8.5 6.0kV Switchgear The 6.0kV Switchgear shall be designed and constructed in accordance with the Specification for HV Switchgear (1014-BKTNG-EL-SP-0001) and Datasheet for HV Switchgear (1014BKTNG-EL-DS-0001). The type tested HV Switchgear shall be totally sheet metal enclosed, free standing, floor mounted panels of single front, bottom cable entry and fully compartmentalised arrangement. Facility for future extension at both ends shall be provided. Ingress protection shall be to IP 32 (min.) per IEC 60529. Incomer /outgoing feeders shall be withdrawable VCB. All switching devices shall be of withdrawable type. Each incoming and outgoing feeders shall occupy a single bay. ESD signals and emergency stop button for motor feeder in switchboard/MCC will be required if necessary. Each main incoming feeder shall be rated with 25% spare current carrying capacity. The HV Switchgear shall be fully tested and certified for a fault and duty rating by an approved independent international testing laboratory. The Switchgear shall interface with the Power Supply Management and Control System (PSMCS), which is described in Section 8.8, by serial link. All start/stop commands, measurement/status/alarm reporting capabilities from the HV Switchgear can be realisable by the PSMCS. 8.6 Distribution Transformer Distribution transformers shall be double copper wound “cast-resin” type units and designed and constructed in accordance with the Specification for Distribution Transformer (1014BKTNG-EL-SP-0004) and Datasheet for Distribution Transformer (1014-BKTNG-EL-DS0004). Distribution transformers shall be provided with louvered factory-installed safety enclosure with minimum ingress protection of IP23. Passive protection against thermal overload shall be by winding embedded RTD’s that are wired to a local detection relay for interfacing with the primary circuit breaker feeder protection relay located at HV switchgear. The distribution transformer base-rating shall be derived from natural cooling (i.e. AN); however transformer cooling fans shall be provided and activated automatically in case of high winding temperature detected. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 25 of 47 Transformer configurations are as follows: Primary system : 6.0kV, 50 Hz, 3-phase, 3-wire Secondary system : 420V, 50 Hz, 3-phase, 4-wire Neutral wye point : Solidly grounded Winding insulation / temperature rise : Class F / Class B Method of cooling : AN (however cooling fans shall be provided for forced cooling under abnormal ambient conditions) Vector group : Dyn11 Tapping : Manual, off-circuit, 5 steps at ±2.5 % steps The distribution transformers shall be installed in a pressurized /force-ventilated transformer room and shall be suitable for continuous operation at full load (under site conditions). 8.7 Neutral Grounding Resistor Facilities shall be provided to earth 6.0kV generators via a grounding resistor designed to limit the generating system earth fault current to a maximum of 400A. The NGR shall be capable of flowing the 400A earth fault current for the period of 10 seconds without sustaining damage. The neutral of each main power generator shall be connected to their dedicated NGR. During normal operation both generators’ star-points shall be grounded through the NGR. The earthing resistor shall be the rustless-unbreakable grid type in protected enclosure with minimum ingress protection of IP 23. 8.8 400V Switchboard/MCC The 400V Switchboard and Motor Control Centre shall be designed and constructed in accordance with the Specification for LV Switchgear and MCC (1014-BKTNG-EL-SP-0002) and Datasheet for LV Switchboard/MCC (1014-BKTNG-EL-DS-0002). Low voltage type tested factory-built assemblies shall be completely metal enclosed, front access, self-supporting, with bottom cable entry and fully compartmentalised multi-cubicle assembly of heavy industrial type. It should be “fully withdrawable and modular”, and internalseparation shall be based on Form 4b or Form 3b, Type 2 construction (minimum standard. The floor or deck-plate (below the switchboard) shall not be considered as being part of the enclosure. Motor starters and outgoing feeder modules shall be ‘full-width’; space saving quarter and half compartments will not be acceptable. The low voltage assemblies shall be designed for continuous operation at full load for at least 40,000 hours without maintenance that would require the main busbars and the distribution busbars (dropper system) to be de-energized. Unless specifically stated, all LV Switchboard shall be indoor installed low voltage factory built type-tested assemblies (TTA). All main and dropper busbars shall be fully insulated. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 26 of 47 The degree of ingress protection per IEC 60529 shall be: For indoor use IP41(min.) For outdoor use IP56(min.) All structural work shall be adequately protected against corrosion. Frame and partitions may be of galvanised steel without the need for a further paint coating. Those parts/covers requiring painting shall be properly pre-treated before the final coat(s) of oil resistant finishing paint is (are) applied. Assemblies shall comprise one or more sections of busbars to which incoming and outgoing units are connected. Busbar sections shall be linked through sectionalizer units. These sectionalizer units shall fully withdraw-able and be identical in construction/make to those of the incoming feeder “Air Circuit Breaker”. The maximum continuous allowable current rating of both incomer feeders/bus couplers and main busbars shall be 5000A nominal. Forced cooling of LV switchboard is not acceptable. LV switchboard incomer units shall be ACB and managed by an intelligent feeder protection relay (FPR). All motor starter modules shall comprise MCCB/contactor/motor control unit (MCU). Nonmotor feeders rated up to 400A shall c/w MCCB, non-motor feeder rated above 400A shall c/w ACB/feeder control unit (FCU). Each main incoming feeder shall be rated with 25% spare current carrying capacity. Fully equipped spare compartments shall be provided in each switchboard. The number of spare compartments shall be 25% of each size of outgoing units subject to the minimum number being 1 for each size. Unless specifically stated otherwise, all LV induction motors shall be started-up by DOL method. LV motors rated 100kW and above shall be assisted started by electronic soft starters. All motors shall be protected with intelligent MPR. The MPR shall have LCD panel as HMI either as integrated into the MPR. Motor earth fault protection to be provided for all motors. Motors may be remotely controlled (for start/stop) from the DCS through the IMCS [see 8.8 below], and tripped from ESD (in case of exercising emergency shut-down). All package equipment motors which have Unit Control Panels (UCP), shall be remotely controlled by hard-wired start/stop command signals and status signals. Shutdown/trip originating from ESD shall only be effected through one hardwired signal from the ESD to the Unit Control Panel. Push button type local control station (LCS) with running indicating light shall be provided for all electric motor. An ammeter shall be provided on LCS for motor rated ≥ 30kW. Local Control Station (LCS) with ammeter shall be provided for submersible motors and those motors which are not visible to the operator. Depending on the application (whether control by DCS or by package UCP), LCS configuration for motor starters shall either be Off-O-On type, or H-O-A type. Electrical interlock shall be provided in the LV Switchboard/ MCC to control the automatic switching of the incoming ACBs and bus-tie ACBs during transfer supply. At anytime, parallel incoming power supplies are not allowed except during power supply transfer from incomer A to incomer B (and vice-versa) during maintenance, from emergency to normal supply and during emergency power generator weekly on load testing. During emergency power generator weekly on load testing, it will be parallel supply between main power generator and emergency power generator supply. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 27 of 47 In any case, bypass key operated switch shall be provided for platform operator to bypass parallel interlock when it is necessary. Outdoor installed factory built assemblies of motor starters and feeders shall be type-tested assemblies (TTA) in the form of weatherproof switch-racks may be implemented for remote non-process/non-production/non-critical applications (e.g. at FDP) and installed in nonhazardous area. The configuration and controls topology associated with switch-racks shall be similar to the LV switchboards installed indoors. 8.9 Integrated Motor Control Centre (IMCS) The Integrated Motor Control Centre (IMCS) shall be a system complete with microprocessor based intelligent motor/feeder protection relays, control and monitoring system for both HV and LV switchboards, and other electrical systems (e.g. UPS). The IMCS shall be part of the 400V Switchboard/ MCC package order and both equipment manufacturers must be approved by the COMPANY. Each motor circuit and outgoing feeder shall be controlled by the microprocessor based Motor Control Unit (MCU) and Feeder Control Unit (FCU). The microprocessor based interface device, Central Control Unit (CCU) shall have a serial link connection for communication with MCUs and FCUs. This connection shall be of the “daisy chain” type thus ensuring that even if the communication link is broken at a single point, all devices are still accessible from the CCU. If necessary, IMCS shall be capable of interfacing with intelligent FPR via a separately configured serial link network – so as to link the FPR to the IMCS CCU. DCS communication with the Integrated Motor Control System (IMCS) shall be via redundant RS 485 serial link with MODBUS protocol. Remote start/stop of motors from DCS shall be provided as required. DCS shall also receive status and alarm signals for each motor. The motor standby/run status and alarm shall be displayed at DCS and at IMCS Operator Work Station (OWS). Motor trip command from the ESD shall be hardwired to the 400V Switchboard/ MCC directly. The trip relays required for the ESD signals shall be available in the 400V Switchboard/ MCC. When the trip command is active, motor shall not be possible to start either from DCS or from the LCS in the field. Electrical main circuit breakers’ open/close status shall be relayed to the DCS through the IMCS. Other miscellaneous electrical system I/Os which are not available from IMCS, such as battery and charger alarms, UPS common alarms, etc. shall be hardwired to the DCS. 8.10 Electric Motors Electric motors shall be designed and constructed in accordance with the Specification for Electrical HV Motor (1014-BKTNG-EL-SP-0009) and Specification for Electrical LV Motor (1014-BKTNG-EL-SP-0008) and the relevant Datasheet for Electrical HV Motor (1014BKTNG-EL-DS-0009) and Datasheet for Electrical LV Motor (1014-BKTNG-EL-DS-0008). Electric motors shall generally be delivered as part of a mechanical equipment package, i.e. mounted on the same skid or base plate as the driven equipment. For hazardous area installation, motors shall be suitably certified. All electric motors shall be of squirrel cage, totally enclosed fan cooled (TEFC) induction type, continuously rated for duty type S1, and generally suitable for direct-on-line starting. Motor FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 28 of 47 enclosure and terminal box shall have IP56 as minimum ingress of protection, but for submerged electrical motors IP68 shall apply. Motor winding shall be made from copper and insulated to insulation class F with maximum temperature rise allowable for class B. However, winding insulation class for submersible motor shall be as per Manufacturer’s standard. Electrical motors, as a minimum, shall be provided with proper sealing of motor shaft and cable entry. In general, motors with soft starter or variable speed drivers shall be provided with thermistor PTC (or RTD) detectors, for winding temperature monitoring, wired to starter panel. VFD driven motors shall have additional nameplate stating that the motor being suitable for hazardous location duty while being driven by a matching VFD, and whatever operating conditions to be observed. Motor anti-condensation heater shall be provided for all motors ≥ 15 kW. Motor anticondensation heater shall be controlled from the motor starter main contactor auxiliary contact – to energise when motor is not running. VFD controlled motors shall have safety switch installed for local isolation of motor feeder from upstream VFD. For HV motors, a heater On/Off safety switch shall be employed wherever motor space heater is powered from a source that is external to the motor starter and shall be installed adjacent to the motor’s Local Control Station (LCS). The location of the Local Control Station (LCS) and / or safety switch shall be on the opposite side of the motor to the main terminal box. LCS enclosures located at open area exposed to direct sun ray and rain shall be made from 316L stainless or aluminium alloy (LM6). Polyester Glass Reinforced Fibre (GRP) can also be used as alternative material for LCS enclosures installed in shaded areas. 8.11 Variable Frequency Drive (VFD) Variable frequency drives shall be employed where either speed-control of motor driven equipment is necessary or to regulate the high starting current encountered for exceptionally large LV motors. For applications in hazardous locations, the VFD and driven electric motor shall be matched and the electric motor shall be designed, constructed and certified for hazardous area operation. The combination of VFD and motor shall be specified to be supplied from same Manufacturer/Supplier – in order that single-point responsibility is ensured. Depending on required motor rating and overall power system configuration, voltage levels for VFD/electric motors may either be at LV or HV. Current harmonic distortion caused by the rectifier input current of VFDs shall be controlled and mitigated in order that system voltage harmonic distortion is kept within 5% and 3% - for total harmonic distortion (THD) and any single harmonic respectively. VFDs of motors driving process equipment shall have direct communication with DCS for start/stop commands, speed raise/lower commands, common fault alarms, and stand-by status. Either hard-wire signaling or serial link data communication between DCS and VFD may be acceptable. However, tripping signal from ESD shall be hardwired to trip the upstream breaker of the VFD. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 29 of 47 8.12 Uninterruptible Power Supply (UPS) 8.12.1 AC UPS AC UPS systems shall be provided for powering up vital loads. The AC UPS system shall be designed and constructed in accordance with the Specification for AC Uninterruptible Power Supply (1014-BKTNG-EL-SP-0005) and Datasheet for AC Uninterruptible Power Supply (1014-BKTNG-EL-DS-0005). UPS system shall be provided to power vital electrical loads such as LV Switchboard/MCC control supply, helideck lights, aviation obstruction lights, generator control panel, compressor control panel, telecommunication systems, and instrument systems like ESD/FGS/DCS workstation and other vital package control panels. The selection of either 3 phase or 1 phase output AC UPS shall depend on installed kVA estimated during the course of equipment sizing. The AC UPS installation shall consist of 2 x 100% UPS units (connected in Parallel Redundant configuration each with its own charger, battery, static changeover, Inverter) with a common maintenance by-pass transformer, common maintenance bypass switch and a common AC UPS distribution panel. A static by-pass shall be provided to allow the automatic changeover of the output supply from the inverter to a stabilised supply from a bypass-transformer when both of rectifiers fail. A maintenance by-pass shall be provided via a changeover switch to allow manual changeover of the output supply from inverter to isolation of the UPS for maintenance. The AC UPS shall be suitable for operation with the following requirements: Input supply : 400V, 50 Hz, 3-phase, 3-wire Output voltage (depending on installed kVA) : Either 230V, 50 Hz, 3-phase, 3-wire, or 230V, 50 Hz, 1phase, 2-wire The AC UPS unit shall be of free standing, sheet metal, front access with floor mounted panel suitable for mounting by bolts. The enclosure degree of protection shall be IP 31 minimum. The UPS shall be installed inside the Emergency Switchgear/MCC room. Battery bank shall be installed on the steel rack mounted inside the battery room. Battery circuit breaker shall be provided inside the battery room to isolate the battery bank from the battery charger and load bus. The breaker shall be installed in explosion proof enclosure. The circuit breaker shall have tripping facility from FGS/SDS and manual/remote tripping. The battery circuit breaker shall be manually close only. 8.12.2 Batteries Battery banks installed in the battery room for AC UPS shall preferably be in single strings of “gel type” Valve Regulated Lead Acid (VRLA) cells. Battery room temperature should be maintained at 20oC, in order to maintain optimum performance and ensure full design life. Batteries shall be sized with a 25% ageing factor and a further 10% contingency shall be added. Batteries mounted in indoor battery rooms shall be as per specified on the technical data sheets. All cell containers shall have shock-absorbing, non-conductive, heat resistant containers, flame retardant and sealed covers to provide a permanent leak-proof unit. The batteries of UPS units shall be rated to energise the relevant loads for not less than: FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 30 of 47 8.13 45 min. - for switchboards, packaged equipment unit control panels, and all other systems like Metering panels, Sub-sea controls and etc 1 hours - for shutdown system, ESD. 1 hour - for Distributed Control System, DCS. 3 hours - for Fire and Gas System, FGS 3 hours - for PABX, VSAT communications equipment 3 hours - for PA/GA system and status lights 45 min. - for non-SOLAS communication equipment e.g. LAN, CCTV and etc. 24 hours - for SOLAS (Safety of Life at Sea) communications equipment 12 hours - for Aviation Obstruction Light, Illuminated Windsock, 1 hour - for helideck lighting (flood lights, perimeter lights) 96 hours - for Navigational Aids marine lanterns, and beacon Bus duct Cast resin bus ducts shall be used in place of high “ampacity” feeders requiring multiple runs of single or multi-core cables e.g. feeders between transformers and LV switchgear. The bus ducts shall be designed as a system consisting of straight lengths, bends, elbows, break-outs, and terminal (flexible connectors). 600V grade, 3-phase, 4-wire, 50Hz Bus duct assemblies shall be provided for interconnection between the LV side of each of the Power Distribution Transformers and the corresponding LV Switchgear. The connection bus ducts shall be designed and constructed to IEC 61439-2 with degree of ingress protection of IP 68 for both indoor and outdoor portion of the bus ducts. Bus ducts shall comprise of tinned annealed hard drawn copper busbars self extinguishing with homogenous cast resin insulation, rigidly supported in a totally enclosed and nonventilated metal enclosure. The bus ducts shall be flame retardant and shall consist of 3 phase and neutral busbars complete with internal earth bus. Busbars shall be insulated over their entire lengths. The temperature rise of busbars inside the bus ducts shall not exceed the permissible values stipulated in IEC 61439, while carrying the rated full load current. Neutral bus shall have continuous current ratings of 100 % of the phase bus. Busbars shall be sized, braced and supported to withstand the mechanical and thermal stresses of the rated short circuit current of the Transformers, Switchgear to which the bus ducts are terminated. Bus ducts shall have short time ratings not less than the upstream circuit breakers. Bus duct access openings shall be provided at each end of bus ducts for testing and commissioning purposes. The busduct system design shall carry type test certification from a recognized independent testing laboratory for short-circuit withstand capability FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 31 of 47 8.14 Electric Power and Control Cables Electric cables to be installed shall be designed and constructed in accordance with the Specification for Electrical Cables (1014-BKTNG-EL-SP-0010). Cables shall be stranded (Class 2), tinned annealed copper conductor according to IEC 60228. Where more flexible cable bending is required, and upon the approval from the COMPANY, Class 5 cables shall be employed where needed. For LV distribution system, maximum copper conductor sizes for multi-core cables shall be 240 mm2 and 185 mm2 for power feeders and motor feeders respectively. Maximum copper conductor size for single core cables shall be 630 mm2. For HV distribution system, maximum copper conductor size for multi-core cables shall be 185 mm2. Where single run cabling is insufficient, multiple cable of up to two runs and four runs for multi-core and single-core cabling may be employed. Minimum cable cross-section for power and lighting/control cables shall be 2.5mm2 and 1.5mm2 respectively. Cables for normal services shall be flame retardant to IEC 60332-3 Cat A while those for critical services shall be flame retardant and fire resistant to IEC 60331. Penetrations through the fire rated walls, between hazardous and non-hazardous area and also when external cables enter package enclosures, these entries shall be sealed with fire rated multi-cable transits (MCT). In general, cables shall be suitable for the design conditions, fully filled with non-hygroscopic fillers, fully sealed to avoid the ingress of water and gas, and meet the minimum bending radius without the formation of ripples on their outer cover. Unless otherwise specified, all cables shall be braid armoured. Bedding and outer sheath material of cables shall be LSZH type. Cable for vital services shall be fire resistant together with flame retardant in accordance with IEC 60331 and IEC 60332 respectively. Single core cables pertaining to 3 phase circuit shall be laid together in trefoil formation and held together by “certified short circuit withstand” cable cleats and separated from multi-core cables. Individual conductors shall be based on new colour coding based on BS 7671 Amendment No.2 and IEC 60446. All cable armouring shall be tinned copper wire braid. Single run of cable from ladder/tray shall be supported by painted steel flat bar. 8.14.1 General Application EPR/CWB/LSZH , flame retardant and with an oxygen index of not less than 30, temperature index of not less than 260oC and type tested in accordance with IEC 60332-3 Category A (reduced propagation) and acidic emission of max. 17% (by weight) in accordance with IEC 60754. Cable outersheath shall be thermoset compound, SHF2 (as per IEC 60092-359). FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 32 of 47 8.14.2 Living Quarters EPR/EMA/CWB/EMA or EPR/EVA/CWB/EVA for multicore, low smoke zero halogen (LSZH), flame retardant in accordance with IEC 60332-3 category A. EPR/EVA low smoke zero halogen (LSZH), flame retardant in accordance with IEC 60332-3 category A for cable running in conduits. 8.14.3 Critical Services Mica glass tape (MGT) primary insulation, EPR insulated, fire resistant in accordance with IEC 60331, withstand with temperature of 750oC for three hours, low smoke zero halogen (LSZH), flame retardant in accordance with IEC 60332-3 category A (reduced propagation). 8.14.4 VFD Cables VFD motor feeders shall be 3-core cables, constructed and rated for VFD applications; single core cables shall not be used for VFD application. 8.15 Sizing of Cables The sizing of cables shall take the following into consideration: The maximum continuous rms load current Derating factor due to grouping of cables Derating due to maximum ambient air temperature Voltage drop The length of cables The short circuit current withstand capability shall be consider for main incomer and HV cable sizing. The short circuit current withstand capability of cables shall be determined in accordance with: The rated short circuit breaking current of the source switchboard The fault clearance time associated with the operation of the primary protection In general, the A.C. electrical system should be designed such that the voltage drop at normal operating load conditions shall not exceed the following limits: Main Feeders 1 to 2% Motor Feeders 2 to 3% Lighting Panel Feeders 2 to 3% Lighting Branch Circuits 2 to 3% Total voltage drop from main switchgear to the furthest point shall not be more than 5% based on continuous maximum current loading and rated voltage. The voltage drop in DC cable shall be consistent with the minimum system voltage at the distribution board and the minimum equipment operating voltage but should not exceed 5% in any case. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 33 of 47 8.16 Cable Installation 8.16.1 General The whole of the cabling, i.e. cabling for the electrical, instrumentation and telecommunications systems shall be designed to form one integrated system, so as to ensure suitable cable routing and adequate segregation (for reasons of safety, circuit integrity and interference prevention) of the different cable types. Cable support system may comprise cable racks, cable trays, cable ladders and “open” rigid/flexible conduits. Individual cables may be fixed directly to the main structures, walls, ceilings or columns by means of proper fixing and supporting materials. Generally, cable splicing is not permitted, and if unavoidable - requires COMPANY's approval. MCT shall be used for cable penetration 8.16.2 Laying Pattern Within the power cable category, HV multi-core cables may be laid in one layer touching, and LV multi-core cables in up to a maximum of two layers touching and with the applicable group rating factor applied. Cables should be segregated and suitably identified in the applicable cable category, i.e. HV Power Cable LV Power and Control Cable for non-instrument control Instrument cables Individual cables emerging from floors shall be protected against mechanical damage by means of galvanised steel pipes. Single core cables emerging from floors shall be protected and sealed by the use of multicable transits (MCT). Grouped cables emerging from floors and MCT shall be protected collectively by a properly designed metal shield or duct in such a way that heat dissipation from the sustained load carrying cables is not hampered. The propagation of fire from one space to the other shall be prevented by the proper sealing of openings around cables. If cables are to be routed through restricted openings, care must be taken to ensure that fire is not intensified or readily channelled along the cable route. Cables shall be fixed to ladders or trays using Nylon sheathed stainless steel cable ties. 8.16.3 Cable Marking/ Numbering Cables shall be tagged with pre-printed cable numbers similar to the Grafoplast SI2000 system at each ends and both side of cable penetration. Cables shall also be numbered where they branch off from a main route. 8.17 Lighting System The lighting system shall consist of normal lighting fed by normal lighting distribution boards while emergency lighting will be powered by emergency lighting distribution boards. HID floodlights and well-glass lights will be used for general lighting. The maximum usage of the floodlight shall be made for open areas; glare control shall be exercised. Floodlights and wellglass lights with either Ex ‘d’ or Ex’de’ certification and IP56 (min.). The lamp wattage will depend on the area to be lit. Fluorescent luminaries will be used, where necessary, for local lighting of operating areas requiring higher illumination level which will be difficult to achieve using floodlights. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 34 of 47 Fluorescent luminaires shall be used for escape route lightings. For escape lighting, the same type of luminaires shall each be equipped with an internal self contained backup battery/charger. The location and mounting of luminaries shall take account of efficient illumination, accessibility of luminaries and convenience of servicing. Luminaries shall not be mounted above machinery having exposed moving parts. Adjacent luminaires shall, as far as practicable, be on separate circuits. Lighting circuits shall also be arranged to avoid stroboscopic effects. Lighting circuits shall be single phase and neutral or three phase and neutral, protected with maximum 20A MCBs, but not be loaded higher than 16A. Lighting distribution boards shall include minimum 15% spare outgoing circuits. General lighting luminaries shall comprise of the following types: For outdoor locations or in enclosed space without air conditioning, housings of lighting luminaries shall be of either Stainless Steel (SS316L) material or Aluminium Alloy (LM6) material; suitable for Zone 1 application. For indoor locations with air conditioning, fluorescent luminaries housings shall be made of painted / powder coated steel, Glass Reinforced Polyester (GRP) luminaires may be used in damp areas. Recessed luminaires fixed to ceiling in Living Quarters shall be certified with minimum B15 fire rating to be compatible with the ceiling installation. Light sources for outdoor lighting shall be tubular HID lamps of high pressure sodium (SON) and/or metal halide (MBI), and T8 tubular tri-phosphor fluorescent lamps. Light sources for indoor lighting shall be by the use of T8 tubular tri-phosphor fluorescent lamps, halogen lamps and LED lamps. The use of compact fluorescent (PL) lamps should be explored and should be used indoors, especially in the LQ. The platform normal lighting system shall remain switched on 24 hours. The lighting installation in control rooms shall be designed so that ceiling lighting groups can be switched off independently to suit operators’ needs. The minimum illumination levels, measured at the working plane or 0.8m above the floor level in the horizontal plane shall provide the illumination levels based on the following requirements: Location Lux (a) Normal Lighting Offices Recreation Room Bedrooms Hallways, Stairways, Interior Walkways, Stairways, Exterior Bath Galley and Mess Hall Electrical Control Rooms Storeroom Work Shops Compressor, Pump and Generator Buildings, General Entrance Door Stoops 500 300 200 100 20 100 300 300 100 700 300 50 FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 35 of 47 Open Deck and Well Head Areas Central Control Room & Instrument Control & Equipment Room Telecom Equipment Room / Radio Room Battery Room Outdoor process areas Outdoor non process areas Laboratory 50 400 400 200 150 75 400 (b) Emergency Lighting When powered by internal back-up battery: Stairways Offices Exterior Entrance Compressor and Generator Rooms Electric Control Rooms Open Deck Areas Lower Catwalks 20 10 10 50 50 10 20 The illumination levels for escape route lighting where lighting is provided by battery powered luminaires, will be 1.0 lux in accordance with NFPA 101. 8.17.1 Normal Lighting Luminaires with fluorescent and HID (HPS/MBI) lamps shall be used as the main light source for outdoor area. Luminaires with fluorescent lamps shall be used for indoor areas. HID floodlights shall be provided where illumination for large and open areas is required such as main deck, wellhead, laydown area and boat landings. Outdoor areas with limited clearance such as walkways, wellhead area, etc. may use fluorescent fittings. The lighting shall be provided by pendant, wall, ceiling or stanchion mounted type. Indoor lighting shall be controlled by individual wall mounted switches located in each area or room near the exit. Normal lighting shall be fed from normal lighting distribution board and shall cover about 70% of lighting requirements. 8.17.2 Emergency, EXIT and Escape Lightings Emergency lighting luminaries shall be installed at strategic locations including control rooms, switchgear room, instrument room, living quarters, escape routes and areas where required for safety reasons. Emergency lighting shall be backed-up by supply from emergency power generator. EXIT lights with built-in back-up battery shall be installed for marking exit doorways and long escape routes; they shall remain continuously lighted. Emergency lighting shall cover about 30% of lighting requirements. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 36 of 47 Part of the emergency lighting shall function as escape lighting and be located such as to illuminate the escape routes, ladders and walkways to allow safe movement of personnel to the muster points, lifeboats, etc. Escape lighting shall be fed and equipped in the same fashion as the rest of the emergency lighting except with internal self contained battery back-up for a 90 minutes autonomy time. The battery shall be recharged within six (6) hours. Escape luminaires shall be installed at the following locations: Every exit doorway Every sleeping cabin External escape ways (stairways and walkways) Internal escape ways (escape routes in modules or deck areas, accommodation area corridors, and galley) Embarkation areas (access to helideck and survival craft stations) Muster areas Escape luminaires installed in sleeping cabins shall only illuminate on loss of the a.c. supply to the integral battery charger. Escape type lighting shall be provided in the living quarters to provide escape lighting in a smoke situation. The minimum required level of illumination is 1 lux along the centre line of an escape route. Escape lighting and battery back-up emergency lighting shall have Ex ‘e’ or Ex ‘d’ certification. Fixed emergency floodlights shall be provided under boat landings, liferafts, life boats area, and mustering area via the emergency power supply. 8.17.3 Hand Lamps Rechargeable hand lamps will be provided for all areas where operating personnel may be present at all times the followings: Control rooms Switchgear rooms Instrument rooms Workshops Maintenance supervisor room Platform supervisor room At least one hand lamp (complete with charging station) should be installed on the inside of each exit door way. Each hand lamps shall comprise a fixed wall mounted battery charger and shall be Ex ‘e’ certification. The unit shall be kept on float when not in use and fed from emergency lighting distribution board. The battery shall be rated to energise the hand lamp for not less than 5 hour. 8.18 Navigational Aids The navigation aids system shall be supplied from a dedicated DC UPS and control system complete with 96-hour back-up battery bank. This system shall comply with Specification for FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 37 of 47 Navigational Aids System (1014-BKTNG-EL-SP-0007), and Datasheet for Navigational Aids System (1014-BKTNG-EL-DS-0007). 8.18.1 Marine Navigational Lights All equipment and all it accessories shall be suitable for areas classification (normally Zone 1). Navigational Aids System shall be provided to comply with the statutory requirements. Main white navigation lights shall be provided in accordance with the requirements of the International Association of Lighthouse Authorities (IALA). Marine lanterns shall be provided at the corners of the platform and on the link bridge. Flashing white light exhibiting Morse code 'U' signal every 15 seconds shall be provided to mark the furthest corners of the platform such that at the horizontal extremities of the platform is visible to the approaching vessel. The marine navigational aids system shall operate from the Navigational Aid Central Control Panel (NCCP). A dedicated 24V DC UPS system for the navigational aids system, comprising at least the following main components shall form part of the package: 1 x 100% Rectifier (charger) 1 x 100% Battery bank The NCCP shall be housed in an Ex‘de’ enclosure with a minimum ingress protection of IP56 (min.); battery bank shall be housed in Ex’e’ battery box. The 24V DC UPS system for navigational aids shall never be tripped even under gas conditions. Battery backup time shall be at least 96 hours or 4 days continuous. 8.18.2 Foghorns Foghorns shall be provided for deployment during periods of poor visibility. Installed locations of the foghorns shall enable the blasts to be in unison, heard from all approach directions to the CPP/FDP complex. The foghorns shall not be installed close to the LQ. Activation of the foghorns shall be automatic on detection of poor visibility at CPP/FDP complex. 8.18.3 Aviation Obstruction lights Red coloured aviation obstruction lights shall be installed on the pedestal crane and flare boom and any tall structures, near/below the flight path, which are considered as potential obstructions to aviation. The lighting luminaires shall be omni-directional with a minimum intensity of 10 candelas and powered from the platform central AC UPS system with battery backup time of 12 hours. 8.18.4 Helideck Lightings Helideck lighting shall be provided in accordance with International Civil Aviation Organisation (ICAO) or CAP 437. Helideck shall be lighted up with green lanterns along the perimeter of the landing area, together with helideck floodlights. Helideck lighting shall be designed such that glaring to the pilot and hazard to helicopter landing is avoided. Power supply to the helideck lighting shall be from the AC UPS power supply. Battery backup time shall be 12 hours. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 38 of 47 Status lights (wave-off) and illuminated windsock shall be installed at the helideck. 8.19 Socket Outlets Power and convenience socket outlets installed outdoors shall be suitable for Zone 1 areas, fitted with padlocking facilities and the distribution circuit breakers associated with these socket outlets should be trip interlocked with the fire and gas/shutdown system. In non-hazardous indoor areas, convenience socket outlets of the industrial type shall be installed where required. Domestic pattern convenience socket outlets shall only be fitted in the accommodation areas. Power and convenience socket outlets shall be mounted approximately 0.3 to 1.5 m above grade level, either on a free-standing support, on structural steelwork or on a building wall. Outgoing circuit breaker for socket outlets and small power circuits shall be equipped with earth leakage protection (current operated ELCB or RCCB) with the following sensitivity: 3 phase – 100mA; 1 phase – 30mA 8.19.1 Topsides Application Sufficient power and convenient socket outlets shall be provided to enable maintenance to be carried out. Socket outlet circuits shall be protected with earth leakage protection in the distribution board or MCC and shall have facility for FGS/SDS remote tripping Power socket : 32A (& 63A), 400/230V, 50 Hz, 3-pole + neutral + earth Convenience socket : 16A, 230V, 50 Hz, 2-pole + earth Three phase socket outlets shall be located/rated to suit anticipated fixed, portable and temporary equipment, etc. plus 1 off in the electrical workshop rated to suit all anticipated testing. At least 4 nos. of 1-phase sockets and 2 nos. 3-phase sockets shall be installed per deck layout. 8.19.2 Living Quarters Minimum of two twin convenient socket outlet shall be provided in each room and four twin socket outlets for each office. Additional socket outlets shall be provided for larger rooms and special function rooms such as electrical room, equipment control room, pantry and laundry to suit special requirements. No more than four socket outlets shall be connected to each circuit. Socket outlet shall be 16A, 230V, 2-pole + earth type, and 32A, 400/230V, 400/230V, 3-pole + neutral + earth type. All socket outlets shall be protected by ELCB circuit breakers. 8.20 Multi Cable Transits (MCT) Penetrations through the fire rated walls and between hazardous and non-hazardous areas shall be sealed with fire rated multi-cable transits (MCT). Multi cable transits shall generally be installed where cables pass through the following locations: FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 39 of 47 1. rated wall / floor / ceiling 2. Gas tight wall / floor / ceiling 3. Walls between hazard and non-hazardous areas 4. Package Enclosure Cable shall not penetrate blast and H-rated walls except at the edges. Cable transits shall not be installed in roof or top entry application. Sufficient multi cable transit frames are to be installed to allow for approximately thirty (30) % spare capacity for future cables. All open cable penetrations shall be sealed with fireproof materials. These penetrations shall meet the requirements of DNV’s Offshore Standard - DNV-OS-D301 “Fire Protection”. Minimum MCT fire rating shall be 1 hour A60 rated. If the firewall or blast wall is rated for H60 then the MCT installed shall have the same fire rating. 8.21 Cable Glands (stainless steel/ nickel plated brass) All steel braided armoured cable entries into equipment shall be made by means of suitable brass double compression cable glands with an armour-clamping feature, with inner and outer seals providing minimum ingress protection of IP66, ISO metric threads, complete with locknut and earth tags. Barrier glands shall be used if the cables are not of the effectively filled type. Cables shall be terminated, glanded (without shroud) and tested shortly after installation. Incomplete cable installation shall be properly coiled, identified, supported and capped off to prevent contamination. Cable entering equipment which may be removed or replaced for maintenance shall have its cable looped prior to entry. Cable entry to equipment shall be from the bottom or side and protected from weathers. Certified plugs shall be used to blank off all unused entries in certified Ex'e' and Ex'd' equipment and similar certified adaptors shall be used to match metric glands to non-metric entries. Entries shall only be made in certified enclosures by the Manufacturer. Cable glands shall be provided to suit the type of cable and termination box/ enclosure, and shall be of the appropriate type of protection, e.g. Ex'd', Ex'e'. Effective earth continuity shall be ensured between the cable armour/braid and the gland plate or the internal earth terminal. 8.22 Electrical Heat Tracing The electrical heat tracing shall be designed to withstand the highest possible temperature which can occur under all process condition. The electrical heat tracing shall be designed based on self regulating/self limiting heater and shall be suitable for operation in Zone 1 / Zone 2 hazardous location. The source of electric power to heat tracing circuits shall be from dedicated heat tracing “isolation transformer” installed inside the heat tracing distribution panel. Heat tracing circuits shall be individually protected by 30mA ELCB located in the distribution board. Ammeter shall be provided at each outgoing heat tracing feeders in the distribution board. A common fault alarm signal from the heat tracing panel shall be provided to DCS, if any of the outgoing heat tracing circuits trip out by fault. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 40 of 47 8.23 Junction Boxes Power and lighting junction boxes for outdoor application, shall be made from electro-polished 316L stainless steel, IP 56 (min.) and certified to EEx’e’. Indoor junction boxes may be made of high impact resistant, flame retardant glass-reinforced black polyester with internal ground continuity plate. All outdoor power junction boxes cable entry shall be from bottom except for lighting junction boxes where side and/ or bottom entries are acceptable. Intermediate junction boxes or cable splices are not permitted on power cabling unless approved in writing by COMPANY. In general, this is only permitted to connect regular power cable to motor cable e.g. submersible motor. All package skid interface junction boxes shall be at the skid edge external to any acoustic enclosure. An Ex-certified breather/drain device shall be installed in each outdoor enclosure that is higher than 8 litres in volume. 8.24 Cable Ladder/ Tray Cable support system shall generally comprise cable racks, cable trays, cable ladders. All installed rigid cable supports shall be made of Stainless Steel SS316L material. Galvanised carbon steel and GRP cable support systems shall not be used. Cable trays and ladders shall be closed with removable top covers allowing adequate ventilation in situation where: Mechanical damage to the cables is likely to occur during construction, operations and maintenance. Oil or chemical spillage can be expected Sun shielding against direct solar radiation Cables trays and ladders shall not be installed in front or over pipes, risers and equipment. Maximum unsupported span for cable trays and ladders shall be in accordance with manufacturer's instruction and in no event shall exceed 1.5m and 3 m respectively. Crossing of open areas and walkway shall be at least 3 m clear. Cable tray / ladder covers in excess of 300mm shall have supplementary fastening using two (2) stainless steel bands per length. A minimum of 15% spare rack, trays or ladders capacity shall be provided. Maximum side rail height shall be 150mm for ladders and 40mm for trays. Maximum rung spacing for ladders shall be 300mm. Vertical separation is required between parallel levels of cable ladder or tray and shall be a minimum of 300mm. Sharp bends or edges for cable racks / ladders / trays are not permitted. All cable racks / ladders / trays shall be earth bonded between sections and to welded steel structures and in no event the intervals shall exceed 25m. Cable penetrating through decks shall be protected from damage by kick plates. The top of the kick plates shall be covered or made smooth. The bending radius of cables shall not be less than that specified by the cable manufacturer. Cable shall be properly identified per service grade and segregated into groups in according to the drawings. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 41 of 47 Installed cables shall be fastened by means of Nylon sheathed stainless steel cable tie wraps in every 3 m for horizontal trays and 1 m for vertical ladders. Supports for cable ladders or trays shall be painted galvanised carbon steel. Separate cable ladder / tray shall be provided for HV, LV and DC cables. High voltage cable ladder shall be mounted as far as possible from instrumentation cable ladder system. 8.25 Conduits and Accessories Wiring in conduit shall only be used on short runs of 2 metres or less (1 joint), and on package skids where it is more practical than using armoured cables on trays. Outdoor conduit/conduit fittings including condulet boxes shall be of rigid epoxy coated galvanised feraloy. All conduit termination shall have a minimum of five threads fully engaged. Conduit shall be heavy duty type. Pipe and pipe fittings are not permitted in any conduit installation. 9.0 CONTROL, PROTECTION AND MONITORING All distribution control, protection and monitoring functions shall be located on the respective distribution panels and starters. Remote operation of power users (e.g. start/stop commands, run/stop status and trip alarm for motor starters) shall be through the distributed control system (DCS). Variable frequency drives (VFD) shall have their “running” and “stopped” status and “tripped” alarm indicated on a built-in annunciator (LCD) panel. Start/stop and ramp-up/ramp-down commands to VSD shall be hardwired from the DCS. If required, VFD shall also have the capability to relay status & alarm, load current, speed and other critical information to the DCS. The electrical system shall be equipped with automatic protection which shall provide safeguards in the event of electrical equipment failures or system mal-operation. The selection and specification of switching and protective devices, control circuits and associated auxiliary equipment shall be in accordance with international standards. Notwithstanding these requirements, automatic protective systems shall be designed to achieve selective isolation of faulted equipment with minimum delay. In any event this shall be within a time corresponding to the short circuit current withstand capability of equipment, system stability limits and the maximum fault clearance times. All incomers, transformer, and main ACB/VCU/VCB outgoing feeders are controlled and protected by intelligent Feeder Protection Relays (FPR). All protection devices related to generator/driver protection will be provided by generator packager which form part of each generator UCP. 9.1 Generator Feeders The generators incoming feeders shall have the following protective and metering devices as a minimum. The protection and metering device shall be multifunction electronic type. Differential relay (87) Reverse power relay (32) Synchronising check relay (25) Voltage restrained overcurrent relay Phase balance current relay (46) FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 42 of 47 Overvoltage relay / Undervoltage relay (59/27) Over/under frequency (81 O/U) Lockout relay (86) Overcurrent relay (50/51) Over temperature protection (49) Earth fault protection (50N/51N) Negative phase sequence relay (47) Trip coil supervision relay (TCM) Metering devices includes ammeter with selector switch, voltmeter with selector switch, kWh meter, wattmeter, frequency meter and power factor meter. Surge arrester/suppressor, diode failure, loss of excitation, and over excitation shall be provided for generator protection. 9.2 Switchgear/ MCC Incomer Feeders The switchgear/ MCC incomer shall have the following protective and metering devices as a minimum. The protection and metering device shall be multifunction electronic type microprocessor based: Thermal overload protection (49) Overcurrent relay (50/51) Earth fault (50N/51N) Undervoltage relay (27) Lockout relay (86) Synchronising check relay (25) Trip coil supervision relay (TCM) Ammeter and voltmeter with selector switch The switchgear bus-tie shall have synchronizing check relay (25). 9.3 Motor Starters Motor starters shall comply with the Specification for HV Switchgear or Specification for LV Switchgear and MCC, as applicable. All motor starter units shall each be equipped with a intelligent motor protection relay (MPR) which is capable of providing a range of motorprotection functions, monitoring and metering functions, control functions through input/output contacts, non-volatile memory (capable of storing data of up to 10 trip events), a LCD panel as HMI- either as integrated into the MPR or one LCD panel shared with a group of MPRs, and a serial interface for remote access/monitoring via an HMI. All HV motors shall have RTD winding temperature detection provided. LV motors which are controlled by variable speed drives (VFD) shall be appropriately be provided with PTC thermistor or RTD winding temperature detection. 9.3.1 LV Motor MCCB for protection against short circuit shall be provided in addition to either motor protection relay or thermal overload relay. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 43 of 47 9.4 Transformer Feeder Vacuum circuit breaker (VCB) unit with multifunction electronic type of protection relay shall be provided. Distribution transformers shall be connected in accordance with IEC standards, and shall be controlled and protected on the primary side by the following: VCB in conjunction with phase short circuit and earth fault protective relays shall be provided. Phase short circuit protection shall be by means of two-stage overcurrent relays. Stage 1 shall be IDMT and set to detect secondary side faults. Stage 2 shall be instantaneous in operation and set to detect primary side faults only. Primary side earth fault protection shall be by a residual current relay, set to achieve minimum fault clearance time. Unrestricted earth fault protection shall be provided on the (earthed) star connected windings of distribution transformers. This shall be achieved by means of a relay that shall be energised by a current transformer (CT) placed in the neutral-earth connection of the power transformer secondary winding. The primary current rating of the CT supplying this relay shall correspond to the nominal current of the transformer secondary or to the current as limited by resistance earthing. The characteristic of this relay shall be extremely inverse. The setting of the earth fault protection relay shall be the minimum practicable. 9.5 Feeders a) Non-motor feeder MCCB rated at 400A and below may be equipped with built-in electronic type thermal-magnetic type release. b) Non-motor feeder MCCB rated above 400A and ACB shall be equipped with Feeder Protection Relay (FPR) and shunt-trip release. 9.6 Small Power and Lighting Distribution board main incomer shall be provided with thermal-magnetic MCCB for protection against overload and short circuit. All small power and lighting outgoing circuits shall be protected by miniature circuit breaker (MCB) against overload and short circuit. Each outgoing circuits for socket outlets/ receptacles shall be provided with earth leakge circuit breakers. 10.0 EARTHING 10.1 System Earthing System earthing arrangement for individual systems shall be as follow: System Voltage Earthing 6.0kV Low resistance earthed at HV main power generator neutral star point 400V Solidly earthed at distribution transformer secondary star point and LV emergency power generator neutral star point. Instrument I.S. Instrument I.S. earthing system Instrument Non IS Instrument clean earthing system FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 44 of 47 The LV power generation and distribution neutral for BK-TNG, being “solidly ground” shall be designated as ‘TN-S’. Generator neutral resistor and transformer star point are connected directly to main platform steel structure beam via dedicated connections. Electrical earthing grid, instrument IS earth and instrument non IS earth are connected directly to main platform steel structure, minimum at two point per earthing system. All other earthing points shall be connected to main platform steel structure beam. 10.2 Equipment Earthing All exposed metal of electrical items, equipment and installation other than current carrying parts will be double bonded and earthed, that is earthed via a separate earthing conductor connected from the equipment frame externally to the earthing grid. All non-electrical metallic equipment and installation not welded to structural steel framework including skid mounted packages, vessel, steel structures etc. will be provided with (two diagonally opposite where possible) earthing bosses bolted to the equipment skid. Earthing conductors will then be connected to the equipment earthing from main structure beam. Earthing conductors are required to bond the main components of the generation and distribution systems (namely HV and LV generators, transformers, switchboards, motors and UPS units) to the platform steelwork/ main structure beam. The computer/printer shall have earthing system separate from other power equipments. Proper earthing to the transformer must be provided when welding of equipment to foundation, base plates and piping. Earthing cables shall never be connected to any part of rotating equipment including base plates, pedestal, drive, etc. All cable racks / ladders / trays shall be earth bonded between sections and to welded steel structures and in no event the intervals shall exceed 25m. On cabinets or panels with hinged doors, earthing integrity shall be assured by the use of flexible earth bonding straps between the fixed and moving parts of the cabinet/panel. The cross-sectional area of branch conductors connecting equipment and structures to the main earth ring shall be as follows: 10.3 To metallic enclosure of HV electrical equipment : 70 mm² To metallic enclosures of LV electrical equipment, having a supply cable cross-sectional area > 35 mm² : 70 mm² To metallic enclosures of LV electrical equipment, having a supply cable cross-sectional area < 35 mm² : 70 mm² To control panels. Etc. : 25 mm² To non-electrical equipment exposed to lightning, e.g. tanks, columns and tall structures : 70 mm² To other non-electrical equipments : 25 mm² Lightning Protection Offshore platform topside shall be of fully structural steel construction welded to the jacket and the jacket bonded to the ground. Hence conventional lightning protection system for the fixed offshore platforms not required. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 45 of 47 However, the communication tower located on the top deck shall have separate air termination rod and down conductors that will be bonded to the platform structural steel. Other tall structure such as flare tower, pedestal crane … on the platform shall be protected against lightning by effecively earthing them to the nearest platform primary steelwork thus providing a direct low impedance path for the lightning discharge to ground. Lightning Surge Arresters shall be required for sensitive field instruments such as CCTV cameras and antennas inside PCS marshalling cabinet for field bus loops. Lightning surge arrestors shall be provided if recommended by the vendors for SIS/FGS cabinets, field instruments, etc. Furthermore, where the metal frame or steel structure is not welded to platform deck or steelworks, and therefore is not continuous to earth, adequate bonding shall be provided. Lightning protection on processing platform shall be in accordance with NFPA 780. 11.0 EQUIPMENT CLEARANCE Recommended equipment clearance is as follows: Item Clearance HV Switchgear (front) 1500 mm LV Switchboard / MCC (front) 1200 mm Distribution panel, large junction box (front) 1200 mm Control panel, UPS 1200 mm Switchgear & LV Switchboard / MCC (side) 800 mm Transformer (all sides) 800 mm Battery banks 900 mm Personnel access 800 mm Between cable ladder/tray (between bottom of ladder/tray) - Horizontal parallel for outdoor installation 400 - 450 mm - Horizontal parallel for indoor installation 350 - 400 mm - Vertical parallel 300 mm Batteries - Shelves depth (not more than) 760 mm - Batteries arranged in two or more tiers, each shelf space back and front (minimum space) - Above each cell (minimum space) 12.0 60 mm 300 mm ELECTRICAL ROOM REQUIREMENT (WITH RAISED FLOOR) Electrical Safety Warning signs shall be prominently displayed on the appropriate individual sections of electrical equipment within the buildings. This shall include, but not limited to voltage level warning signages. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 46 of 47 The main Switchgear/MCC room shall be furnished safety equipment cabinet and electric shock treatment / first aid posters. The cabinet shall be arranged so that each tool or device is held in its own compartment and unobstructed from the door. The cabinet shall be heavy duty painted sheet steel with locking handle, locks, and door(s). A framed A1 size, presentation quality of the key one-line diagram shall be mounted in Switchgear/MCC room. Switchgear/MCC rooms shall be furnished with electrical safety insulating mats along the entire length of the switchboard which can be rolled-up and temporarily put away when necessary. All battery room floors shall be impervious to battery acid. A water tap, eye-wash basin, sink and drain shall be provided and installed by the main door, inside the battery room. Service and drainage lines that carry both liquids and compressed air shall not be routed inside the Switchgear/MCC rooms. 13.0 ELECTRIC HEATERS FOR PROCESS/UTILITY APPLICATIONS The heater control panel and associated heater shall be designed to provide continuous operation at rated output to suit process gas temperature conditions as per stipulated process requirements. Electric heater power shall be regulated by thyristors fired according to the zero crossover mode (with a controlled output power range down to 1 cycle) in conjunction with stepcontroller; unless approved by Company, phase angle control shall not be utilised as a solution for power regulation. Electric heaters with total load greater than 45kW shall be split into smaller discrete heater loads. These discrete heater loads should be controlled by step-controller acting on power contactors, with one remaining as “thyristor controlled”. Thyristor stack protection shall include over-current protection by means of ultra rapid fuses and voltage transient suppressors. The heater shall be located outdoors and be designed to withstand the environmental conditions as specified in this document. The heater elements shall be designed to withstand the highest possible temperature which can occur under all process conditions. Tubular heater elements shall be constructed from 80/20 NiCr (Nickel Chrome) resistance wire surrounded by compacted magnesium oxide powder, designed to minimise peak in rush current. The element shall include an overall sheath tube made from material providing corrosion/ erosion resistance suitable for the operation. 10% spare (of the total number of elements required to fulfil the operational duties of the unit) installed heater elements, but not connected, shall be provided. All spare elements shall be fitted with wires of sufficient length to connect the element to any bus-bar in the event of their use. The number of heating elements provided in the heater bundle shall be indicated. Heater elements shall be protected against over-temperature by means of at least two thermocouples. The devices shall be clamped or welded to the sheaths of elements (different phases) and located in an area of highest anticipated sheath temperature. Electrical Heater shall be provided with thermocouple control to cut-off the heater in case of high skin temperature. Temperature sensing wiring shall be brought out to separate terminal box of IP 66 rating. Terminal boxes material shall be stainless steel SS 316L. FRONT-END ENGINEERING DESIGN (FEED) SERVICE FOR BK-TNG WELLHEAD PLATFORM DOC NO. 1014-BKTNG-EL-RPT-0001 REV. NO. 1 ELECTRICAL DESIGN BASIS Page 47 of 47 Thermocouple material shall be chromel-alumel with swaged sheath mineral oxides. The thermocouple sheath shall be of the same material as the heating element sheath with a minimum wire size of 0.75mm2. Thermocouple wires extending from the sheath shall be hermetically sealed in the head. The design of the Heater Control Panel shall be provided with the facilities for remote and monitoring operation with PSMCS and DCS.