Material
Submittal
Material Approved
Material
Procurement
Material Delivery
Drawing
Submittal
Drawing Approved
From Consultant
Plumbing 1st Fix
Installation
Cutting Block Wall to Install
Pipes
Plumbing 2nd
Fix Installation
Install High level Drainage & WS
Testing Pipes
Install Water Heaters & CXN
Authority or Borehole
Plumbing Final
Fix Installation
Install Pumps
Errection of water tank & cxn
Sanitary ware installation
Water meter fixing
Water
Connection
Final
Commisionng
Commission pumps
Commission water sypply PRV's
Commissioning sanitary wares
Handover