Installing PBC PBC 05 Cabinet INSTALLATION INSTRUCTIONS 1/1531-LZA 701 6011 Uen K Copyright © Ericsson AB 2011-2016. All rights reserved. No part of this document may be reproduced in any form without the written permission of the copyright owner. Disclaimer The contents of this document are subject to revision without notice due to continued progress in methodology, design and manufacturing. Ericsson shall have no liability for any error or damage of any kind resulting from the use of this document. Trademark List All trademarks mentioned herein are the property of their respective owners. These are shown in the document Trademark Information. 1/1531-LZA 701 6011 Uen K | 2016-03-01 Contents Contents 1 Introduction 1 1.1 Target Group 1 2 Prerequisites 3 2.1 Documents 3 2.2 2.2.1 2.2.2 Conditions Before Going to the Site Before Starting the Installation 3 3 3 2.3 Tools 4 2.4 Space 4 3 System Overview 7 3.1 PBC 05 7 3.2 PBC 05 Solar Hybrid 10 4 Work Process for Installing 15 5 Unpacking and Checking Materials 17 6 Moving the Cabinet into Position 19 6.1 Using a Pallet Truck to Move the Cabinet 19 6.2 Using a Hand Truck to Move the Cabinet 21 6.3 Using a Lifting Device to Move the Cabinet 23 6.4 Carrying the Cabinet by Hand 24 7 Preparing the Cabinet 27 7.1 Correct Roof Panel Sealing 28 8 Installation 31 8.1 8.1.1 8.1.2 8.1.3 8.1.4 8.1.5 Installing Installing Installing Installing Installing Installing 31 32 34 38 43 43 8.2 Grounding the Cabinet 45 8.3 Installing Incoming AC Power for PBC 05 Variant 1 46 8.4 Installing Incoming AC Power for PBC 05 Variant 2 50 1/1531-LZA 701 6011 Uen K | 2016-03-01 Cabinet Cabinet on a Floor the Cabinet on a Wall the Cabinet on a Pole the Cabinet on Stacking Kit Cable Inlets Installing PBC 8.5 Installing the AC Service Outlet (Optional) for PBC 05 Variant 1 54 Installing the AC Service Outlet (Optional) for PBC 05 Variant 2 55 8.7 Installing SPD in PBC 05 Variant 2 57 8.8 8.8.1 8.8.2 8.8.3 8.8.4 8.8.5 8.8.6 58 59 66 67 70 73 8.8.11 8.8.12 8.8.13 8.8.14 8.8.15 8.8.16 8.8.17 8.8.18 Connecting Power Distribution to Site Equipment Installing Circuit Breakers and Connecting Cables Connecting DC Input on Solar Subrack Connecting the Incoming Alarm Cable (Optional) Installing External Alarms Connections Connecting Outgoing Alarm Cables Connecting DC Supply to Fans in Other BBS 05 Cabinets (Optional) Connecting 048 V DC to other Site Equipment Connecting the Battery Temperature Sensor Connecting the External Battery Temperature Sensor (Optional) Handling the Battery Temperature Sensor when no Internal Batteries in the PBC 05 Cabinet Installing the Battery String (Optional) Installing the 19-inch Equipment (Optional) Connecting the external Battery Backup Systems (Optional) Installing the Heater (Optional) Connecting the AC Heater Cable External (Optional) Installing the Rectifier Units Installing the Controller Unit Installing the Door Lock 79 81 87 88 90 91 92 93 94 8.9 Checking and concluding the installation 95 9 Power Up and Verification 97 10 Performing Concluding Routines 99 8.6 8.8.7 8.8.8 8.8.9 8.8.10 74 74 76 77 Glossary 101 Reference List 103 1/1531-LZA 701 6011 Uen K | 2016-03-01 Introduction 1 Introduction This document describes how to install and verify the functionality of the following systems: • PBC 05 system, which is a Power and Battery Cabinet (PBC) that supplies 048 V Direct Current (DC) power to outdoor Radio Base System (RBS) equipment. • PBC 05 Solar Hybrid system, which is a PBC 05 equipped with a solar subrack and connected to solar panels. PBC 05 and PBC 05 Solar Hybrid are two main cabinets described in this document. PBC 05 variant 1 and PBC 05 variant 2 are two variants for PBC 05 cabinet. PBC 05 Solar Hybrid has the same units as PBC 05 variant 01 plus a solar power system. When making reference to both variants, the document states "PBC 05". 1.1 Target Group This document is for personnel involved in the site installation engineering process and those responsible for the installation and integration of power systems on site. 1/1531-LZA 701 6011 Uen K | 2016-03-01 1 Installing PBC 2 1/1531-LZA 701 6011 Uen K | 2016-03-01 Prerequisites 2 Prerequisites This section contains information on the documentation, tools, equipment, and conditions required for the installation procedure. 2.1 Documents Make sure that the following documents have been read and understood: • Personal Health and Safety Information • System Safety Information See Reference List on page 103 for required documents. 2.2 Conditions The conditions in this section must be fulfilled before starting work. 2.2.1 Before Going to the Site Before going to the site, make sure of the following: 2.2.2 • Site access permission has been received. • Documentation stated in Section 2.1 on page 3 is available. • All tools stated in Table 1 are available. Before Starting the Installation The Customer Site Documentation describes what equipment shall be installed and how the equipment shall be installed at the site. Before starting the installation, make sure of the following: • The site is prepared in accordance with the Customer Site Documentation, which is prepared and supplied by site engineering. • Ordered hardware is available. • The site grounding system is installed and tested. • Remove all metallic bracelets, rings and watches to prevent short-circuiting during installation. 1/1531-LZA 701 6011 Uen K | 2016-03-01 3 Installing PBC 2.3 Tools The tools required for the installation of the RBS are shown in Table 1. Table 1 Required Tools Product Name Product Number Personal tool kit, light (case) LTT 601 156/1 Torque set, insulated 5–25 Nm. For battery installation LTT 601 157/1 Torque set, 20–100 Nm LTT 601 141/1 Torque set, 0.5–4 Nm LTT 601 145/1 Torque set, 5–25 Nm with 3/8 inch socket adapter LTT 601 140/1 Screwdriver bit for Secure TORX T40-TR Lifting eyes, M8, kit of four pieces. NTM- 101 1902/1 Electrostatic Discharge (ESD) wrist strap LTT 601 136/1 Ear protection LYB 921 50/1 Eye protection LYB 921 51/1 One of the following: • LTT 601 146/1 • Hammer drill 230 V AC • LTT 601 147/1 • Cordless hammer drill, with 230 V AC charger Hammer drill bit, 20 mm More information on tools can be found in Implementation Team Products Overview in the RBS Site Installation Products library. In addition to the tools mentioned above, the following material will be required: 2.4 • Electrical insulation tape • Plastic wire strappers in different dimensions and lengths • Lubrication for sealing Space Each cabinet has space requirements both for working condition and airflow. Figure 1. shows recommended dimensions. 4 1/1531-LZA 701 6011 Uen K | 2016-03-01 Prerequisites The minimum distance to nearest object above the cabinet is 500 mm. The minimum distance to nearest object beside the cabinet is 100 mm. The minimum distance to nearest object behind the cabinet is 80 mm. Note: It is recommended to have more space in front of the cabinet, for a more comfortable working condition. A B C D P022458A Figure 1 Table 2 Space Around Cabinet Installation Space Dimensions Measurement Dimension in mm A 800 B 660 C 700 D 1050 1/1531-LZA 701 6011 Uen K | 2016-03-01 5 Installing PBC 6 1/1531-LZA 701 6011 Uen K | 2016-03-01 System Overview 3 System Overview 3.1 PBC 05 The system consists of the main PBC 05 Cabinet, which provides 048 V DC power to all other RBS equipment on the outdoor site. The cabinet has the option to include one string of back-up batteries. An additional option to install up to two more battery back-up systems exists. The BBS 05 is a battery back-up system, and is designed to work with the main cabinet, but it is also possible to connect the main cabinet to other battery back up systems. Alternative battery backup cabinets may be the BBS 6301, BBS 6101 and the BBS 6102. The main connectivity from the PBC 05 Cabinet is shown in Figure 2 and can be summarized follows: • AC main power supply • 048 V DC supply to site equipment. 048 V DC to external battery backup system. • Alarm signal inputs from internal and external sources. • Alarm signal outputs. • PBC 05 BBS 05 AC/DC power B AC power input B B B B B B B B B B B B B B B B B B B –48V DC –48V DC power out Figure 2 BBS 05 P022425B PBC 05 System Connectivity Figure 3 shows the main features of the PBC 05 variant 1 cabinet and Table 3 provides a brief description. 1/1531-LZA 701 6011 Uen K | 2016-03-01 7 Installing PBC Figure 4 shows the main features of the PBC 05 variant 2 cabinet and Table 4 provides a brief description. A B C Q D P E N F G M L K H J H P022422A Figure 3 Table 3 8 PBC 05 Variant 1 Cabinet PBC 05 Variant 1 Cabinet Key Modules Position Function A Cabinet roof panel B Panel, behind which there are cable connections, fans and the fan control board C Door switch D Controller unit E Connector blocks on inside wall for Interface Board (IB2), alarms and cable shields F AC circuit breakers G Compartment for optional battery string or optional 19-inch equipment H Cable inlets with environmental sealing J Heater (optional) K Main Earthing Terminal (MET) 1/1531-LZA 701 6011 Uen K | 2016-03-01 System Overview Position Function L Filter for incoming air M Cabinet door N AC main power terminal behind panel P Rectifiers Q DC Multifunction unit with circuit breakers A B C S D R E Q F P G N M Figure 4 Table 4 L H K J H Ge4667A PBC 05 Variant 2 Cabinet PBC 05 Variant 2 Cabinet Key Modules Position Function A Cabinet roof panel B Panel, behind which there are cable connections, fans and the fan control board C Door switch D Controller unit E Connector blocks on inside wall for Interface Board (IB2), alarms, and cable shields F AC circuit breakers 1/1531-LZA 701 6011 Uen K | 2016-03-01 9 Installing PBC 3.2 Position Function G Compartment for optional battery string or optional 19-inch equipment H Cable inlets with environmental sealing J Service outlet K Heater (optional) L MET M Filter for incoming air N Cabinet door P SPDs Q AC Input Terminal R Rectifiers S DC Multifunction unit with circuit breakers PBC 05 Solar Hybrid The system consists of the main PBC 05 cabinet, which is equipped with a solar subrack and connected to solar panels. The solar subrack is a power device providing electricity for load by using solar energy. It needs to be used together with other power systems. The solar subrack contains the solar connection point and the wind connection point. The cabinet can install up to two BBS 6102, which is a battery back-up system designed to work with the main cabinet. Two BBS cabinets will secure up to two days of battery backup. The main connectivity from the PBC 05 cabinet is shown in Figure 5 and can be summarized follows: 10 • AC main power supply • 048 V DC supply to site equipment. • 048 V DC to external battery backup system. • DC input cables from solar panels. • DC input cables from wind generator. • Alarm signal inputs from internal and external sources. • Alarm signal outputs. 1/1531-LZA 701 6011 Uen K | 2016-03-01 System Overview PBC 05 AC/DC power Junction Box BBS 6102 BBS 6102 B BB B B BB B B BB B B BB B B BB B B BB B B BB B B BB B B BB B B BB B B BB B B BB B Solar Subrack ATC AC power input Diesel Generator -48V DC AC -48V DC power out RBS Ge4668A Figure 5 PBC 05 System Connectivity Figure 6 shows the main features of the cabinet and Table 3 provides a brief description. 1/1531-LZA 701 6011 Uen K | 2016-03-01 11 Installing PBC A B C M L D K E F J H G G P023392B Figure 6 Table 5 PBC 05 Solar Hybrid Cabinet PBC 05 Solar Hybrid Cabinet Key Modules Position Function A Cabinet roof panel B Panel behind which are cable connections, fans and fan control board C Door switch D Advanced Controller Unit (ACU+) Connector blocks on inside wall for Interface Board (IB2), alarms and cable shields E AC circuit breakers F Solar Converter with Solar power system and Wind generator connection points 4 U space for 19-inch equipment 2 U can be used for Ericsson Site Controller (ESC) and ESC Patch Panel (EPP) G 12 Cable inlets with environmental sealing 1/1531-LZA 701 6011 Uen K | 2016-03-01 System Overview Position Function H Filter for incoming air J Cabinet door K MET L AC main power terminal behind panel M Rectifiers DC Multifunction unit with circuit breakers 1/1531-LZA 701 6011 Uen K | 2016-03-01 13 Installing PBC 14 1/1531-LZA 701 6011 Uen K | 2016-03-01 Work Process for Installing 4 Work Process for Installing This section provides a process flowchart for installing the cabinet. Figure 7 shows the work process for installing the PBC 05. 1/1531-LZA 701 6011 Uen K | 2016-03-01 15 Installing PBC Introduction Material check and unpacking Preparing and moving cabinet Cabinet on floor Cabinet on wall Cabinet on pole Cabinet grounding Cabinet AC installation Cabinet cable installation Cabinet equipment installation Cabinet battery installation (optional) 19-inch customer equipment installation (optional) BBS cabling (optional) Installation check Installation power up Performing concluding routines P022442B Figure 7 16 Cabinet Installation flowchart 1/1531-LZA 701 6011 Uen K | 2016-03-01 Unpacking and Checking Materials 5 Unpacking and Checking Materials This section provides information for unpacking and checking the materials. The cabinet is transported in a transport package. In addition to the cabinet, several items like circuit breakers, rectifiers, controllers, cable lugs, batteries and installation frames are packed separately. Unpack and check the equipment as follows: 1. Examine the packaging for damage. If it has been damaged, make an immediate complaint to the transport company. 2. Check that the items delivered correspond to the packing list. More information can be found in Customer Site Documentation. 3. Unpack the cabinet. Note: Allow the cabinet to remain on the pallet until required for installation. 4. Dispose of the crate in accordance with local regulations. 1/1531-LZA 701 6011 Uen K | 2016-03-01 17 Installing PBC 18 1/1531-LZA 701 6011 Uen K | 2016-03-01 Moving the Cabinet into Position 6 Moving the Cabinet into Position This section provides the procedure for moving the cabinet into position for installation. The weight of the cabinet is approximative 70 kg. This weight is excluding batteries and installation kit. When the cabinet is in position a required minimum space around the cabinet is required as shown in Section 2.4 on page 4. It is recommended that the space in front of the cabinet is increased for more comfortable working conditions. Note: Cabinets must be moved and installed without batteries. The following methods are recommended depending on available equipment and the distance to the installation location: • Using a pallet truck to move the cabinet on its pallet as described in Section 6.1 on page 19. • Using a hand truck to remove the cabinet from its pallet as described in Section 6.2 on page 20. • Using a lifting device to remove the cabinet from its pallet as described in Section 6.3 on page 22. • Carrying the cabinet by hand as described in Section 6.4 on page 24. Note: 6.1 All the above alternatives require at least two people to move the cabinet and install it on either ground, wall or pole. Using a Pallet Truck to Move the Cabinet Caution! Tip risk. Unsecured equipment can tip over if not secured properly, causing injury to personnel. Secure products with a high center of gravity as soon as possible to avoid accidents. If a pallet truck or similar is available, the following procedure is recommended: 1. Move the pallet, using a pallet truck, close to the installation location. 1/1531-LZA 701 6011 Uen K | 2016-03-01 19 Installing PBC Ge1692A Figure 8 Moving the Cabinet on a Pallet Truck 2. Gently remove the cabinet from the pallet. Ge1693A Figure 9 20 Removing the Cabinet from the Pallet 1/1531-LZA 701 6011 Uen K | 2016-03-01 Moving the Cabinet into Position 6.2 Using a Hand Truck to Move the Cabinet Caution! Tip risk. Unsecured equipment can tip over if not secured properly, causing injury to personnel. Secure products with a high center of gravity as soon as possible to avoid accidents. If a hand truck is available, this following procedure is recommended: 1. Gently remove the cabinet from the pallet Ge1693A Figure 10 Removing the Cabinet from the Pallet 2. Push the cabinet onto the hand truck using a board between the hand truck and the cabinet to prevent damage 1/1531-LZA 701 6011 Uen K | 2016-03-01 21 Installing PBC Ge1694A Figure 11 Using the Hand Truck 3. Gently move the cabinet into position close to the installation location. Ge1695A Figure 12 22 Move the Cabinet into position 1/1531-LZA 701 6011 Uen K | 2016-03-01 Moving the Cabinet into Position 6.3 Using a Lifting Device to Move the Cabinet Caution! Tip risk. Unsecured equipment can tip over if not secured properly, causing injury to personnel. Secure products with a high center of gravity as soon as possible to avoid accidents. The roof panel of the cabinet is fastened with four bolts. The bolts with dimension M8, can temporarily be replaced by lifting eye bolts. The lifting eye bolts are part of the toolset in Table 1 and must be ordered separately. If a lifting device is available, the following procedure is recommended: 1. If the roof panel has not been removed previously, remove the four corner bolts of the roof panel with a secure TORX T40. 2. Insert the four M8 lifting eyes on top of the cabinet and tighten them finger-tight. The cabinet is now ready for lifting. 3. Attach lifting straps to the lifting eyes, and lift the cabinet close to the installation location. Note: The lifting device must be designed and approved for the current weight. Warning! Overloading, or other wrong use of lifting devices, can cause serious injury to anyone hit by falling equipment. Use long enough lifting straps to create an angle of minimum 60 between lifting straps and roof. A smaller angle increases the strain on the straps and can cause them to snap. Please refer to Figure 14. 4. Attach the cabinet to its ground location or on its wall or pole frame as described in Section 8.1 on page 31. 5. Remove the lifting straps and lifting eyes. Note: It is not necessary to reinstall the screws for the cabinet roof, at this stage, as it will be removed during the installation process. 1/1531-LZA 701 6011 Uen K | 2016-03-01 23 Installing PBC P022464B Figure 13 Lifting Eye Bolts Min 60° P022426A Figure 14 6.4 Lifting the Cabinet Carrying the Cabinet by Hand It is possible to carry the cabinet by hand. It is recommended to do this by at least two people. It is a difficult operation as the cabinet has no handles and there are no natural points for a good and secure grip. 24 1/1531-LZA 701 6011 Uen K | 2016-03-01 Moving the Cabinet into Position Caution! The equipment is heavy. Lifting the equipment without the aid of a lifting device can cause injury. 1/1531-LZA 701 6011 Uen K | 2016-03-01 25 Installing PBC 26 1/1531-LZA 701 6011 Uen K | 2016-03-01 Preparing the Cabinet 7 Preparing the Cabinet The cabinet comes with some factory installed items and panels. Some cover panels must be removed during the installation process. Please refer to Figure 3 showing the interior of the cabinet. It is recommended to do the following steps: • Remove the door stop at the bottom. This will make it possible to open the door to almost 180 degree. • Remove the cover plate for the fan unit to install all the DC cables. The cover plate is fastened with screws in each corner. • The cover plate for the multifunction unit is fastened with hinges at the bottom. Open the cover by unscrewing the two top corner screws, open the cover downwards and unscrew the bottom screws at the hinges halfway and remove the cover plate completely. • Remove the cover panel over the AC-main power terminal. • Remove the roof panel by removing all the screws on the topside of the cabinet. The roof is secured by two hooks at the front side and they are accessible when the door is opened, as shown in Figure 15 for PBC 05 variant 1 and in Figure 16 for PBC 05 variant 2. For lifting purpose only, the 4 corner screws are removed and replaced with lifting eye bolts. 1/1531-LZA 701 6011 Uen K | 2016-03-01 27 Installing PBC T40 Torx ×4 P022473C Figure 15 PBC 05 Variant 1 Cabinet Roof T40 Torx ×4 Ge4670B Figure 16 7.1 PBC 05 Variant 2 Cabinet Roof Correct Roof Panel Sealing When the roof panel is installed it is important it is correctly sealed. At the back of the cabinet the outlet air filter is located. On top of the filter a bar is loosely placed. This bar has on its top side a sealing which is a part of the complete 28 1/1531-LZA 701 6011 Uen K | 2016-03-01 Preparing the Cabinet roof sealing. See Figure 17 for details of how this bar is placed. To install the roof panel, do the following steps: 1. Check the sealing gasket at the top of the cabinet. 2. If the gasket is damaged, replaced it. 3. If the gasket is dry, replace it. 4. Check that the bar at the back of the cabinet is properly placed on top of the air outlet filter, with the seal upwards 5. Place the roof panel in correct position. 6. Use metal washer on top of rubber washer to form a proper environmental sealing. Note: The rubber washer is about 6 mm think. Using the correct torque will compress it to about 3 mm and end at a mechanical stop. 7. Tighten all the M8 bolts with 6 Nm torque. 8. Secure the roof with the two hooks and tighten the screws holding the hooks in the correct locking position, as shown in Figure 15. If the cabinet is installed on a wall or on a pole, two additional locking plates must be installed at the end of the of the equipment installation process, with the following procedure: 1. Before installing the M8 roof top bolts, swing the locking plate into correct position as shown in the enlarged picture in Figure 26. 2. Place the metal washer on top of the rubber washer on top of the locking plate. Tighten the M8 bolt with a torque of 6 Nm. 3. Tighten the M10 bolt for the locking plate in the frame with a torque of 37 Nm. 1/1531-LZA 701 6011 Uen K | 2016-03-01 29 Installing PBC P022493A Figure 17 30 Sealing Bar for Cabinet Roof 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation 8 Installation The cabinet can be installed on the ground, on a wall or on a pole. The Customer Site Documentation explains where to install the cabinet. This section describes how the cabinet is installed. Note: This document does NOT specify plugs and expanders to be used in the installation process. This information is site dependent and is found in the Customer Site Documentation. Some of installation instructions specify the head of bolt, the socket or bit to be used and the torque that must be applied in tightening the bolt or nut. The torque to be used for battery pole terminals is normally written on the battery. Please pay close attention to the values mentioned. If no values are given, use the table below as general guidelines. Table 6 General Torque Values Dimension Torque in Nm Note M6 9.8 For general use M8 24 For general use M10 41 For general use M12 80 For general use Removing the roof panel of the cabinet is not required for installation. However the installation is much easier if the roof is removed. Install the empty cabinet first and secure it to its foundation before installing any equipment into the cabinet. Note: Empty means that no batteries, no wires, no controllers and no rectifiers are installed. Certain factory pre installed equipment is in place, for example, fans, circuit breakers and wire connector blocks. Depending on where the cabinet is installed, certain steps can be made in a different order. Guidelines are given for each of the different installing options. 8.1 Installing Cabinet The cabinet can be installed on the floor, on the wall or on a pole. For the floor installation a foundation is installed under the cabinet and secured to the floor. For the other two options the cabinet is secured to a frame which first is installed on a wall or on a pole. 1/1531-LZA 701 6011 Uen K | 2016-03-01 31 Installing PBC 8.1.1 Installing Cabinet on a Floor To install the cabinet on the floor, perform the following procedure: 1. Place the cabinet on its back on the floor, with a protection between cabinet and floor. 2. Install the ground foundation according to Figure 18. The four M10 bolts are placed in each corner. Insert bolts with washers from below into the foundation and up into the cabinet. The cabinet has nuts fastened at the inside corner points. Use 17 mm socket and tighten with recommended torque of 37 Nm. 3. While cabinet is in this position, install the cable inlets as described in Section 8.1.5 on page 43. The unused inlets must have a plastic cover to seal the inlets. Which inlets to be used and which are unused is given later in the installation document in combination with information in the Site Installation Document. 4. Figure 19 shows the drill pattern for the foundation on the floor. 5. Drill the holes according to the Customer Site Documentation. 6. Use a vacuum cleaner to clear the drilled holes. 7. Use the bolts and expanders specified in the Customer Site Documentation. 8. Insert expanders into ground. 9. Raise the cabinet and place it in its correct location. Fasten to ground using bolts ant torque specified in the Customer Site Documentation. 32 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation ×4 ×4 P022427A Figure 18 Cabinet installing on ground 4 × Ø14 F A B Front E C D P022457C Figure 19 Note: Cabinet Drill Pattern, Foundation to floor. The hole placement between frame and foundation is similar to the drill pattern, but there is a small and clear difference to the floor drill pattern. 1/1531-LZA 701 6011 Uen K | 2016-03-01 33 Installing PBC Table 7 Drill Pattern Dimension Measurement Dimension in mm A 555 B 490 C 530 D 582 E 24 F 32.5 P009900C Figure 20 8.1.2 Drilling Installing the Cabinet on a Wall This section describes the steps and equipment needed to install the frame on a wall and how to install the cabinet on the frame. The frame is an optional equipment. It is delivered disassembled, and must be assembled during the installation process before the cabinet can be positioned on the frame. Before starting the work, check that all pieces are present according to Table 8. The frame parts are shown in Figure 21. Table 8 34 Wall Installation Frame - Part List Legend Description Quantity A Wall Bracket 2 B Locking plate 2 C Brace 2 D L-shaped bracket 2 E Pole bracket 0 Square washer plate 8 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation Legend Description Quantity Washer for M10 18 Nut, M10 14 Bolt, M10 x 25 mm 18 Bolts for wall installation , specified in the Site Installation Document 8 Diameter can be up to 12 mm Expander plugs for wall A B C D E P022701C Figure 21 Frame Assembly Details To install the frame on the wall, the dimensions shown in Figure 22 and Table 9 are important. Figure 23 shows all the parts of the frame. The frame is assembled with M10 bolts from the outside in all the joints. On the inside a washer is installed and followed by the nut. Figure 26 shows how the cabinet is placed on the assembled frame, which is identical for both wall and pole installation. An enlarged detailed drawing shows how the locking plate is positioned. Note: Pay close attention to vertical alignment of the two brackets, and that they are parallel and horizontal. 1/1531-LZA 701 6011 Uen K | 2016-03-01 35 Installing PBC C A B D E P022702A Figure 22 Table 9 Frame Dimensions, Front View Frame Dimensions Description Dimension in mm A 945.5 B 876.5 C 200 D Hole diameter, 13 mm E 500 To install the frame on the wall, perform the following steps: 1. Prepare the installation work by marking all the holes on the wall for the upper and lower wall brackets. This can be done by marking the holes according to dimensions from Figure 22 or by creating a drill pattern. Note: Pay close attention to vertical alignment of the two brackets, and that they are parallel and horizontal. 2. Drill the holes for the lower wall bracket. Use dimensions specified in the Customer Site Documentation. Clean the holes and use expander plugs 36 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation 3. Use bolts specified in the Customer Site Documentation with the square washer plates supplied in the installation kit. Tighten with the torque specified in the Customer Site Documentation. Note: The same brackets are used for pole and wall installation. A horizontal flip is the only difference between the two installations. 4. Drill the holes for the upper wall bracket. Use dimensions specified in the Customer Site Documentation. Clean the holes and use expander plugs. 5. Use bolts specified in Customer Site Documentation with the square washer plates supplied in the installation kit. Do not tighten yet. 6. Check vertical alignment, horizontal alignment and the distance according to Figure 22 before tightening with the specified torque. 7. Install L-shaped brackets on the lower wall bracket. For each side, use two M10 bolts installed from the outside as shown in Figure 23. Use washers and nuts. Tighten with 37 Nm Torque. 8. Install the brace on each side as shown in Figure 23. Use M10 bolts installed from the outside. Use washers and nuts. Check that L-shaped brackets are level before tightening with 37 Nm torque. 9. Install locking plates below the wall frame on the upper wall bracket, as shown in Figure 23. The rounded side must be towards the wall frame. Use M10 bolts installed from the outside. Use washers and nuts. Keep the nut loose enough, so the plate can swing easily. Do not tighten at this point. 10. Lift the cabinet onto the frame and push toward the rear. A lifting device can be used for this operation. Please see Section 6.3 on page 22 for details. 11. If the two rear screws for roof panel have not been removed previously, do so now and slide the cabinet backwards so that the cabinet bottom holes are aligned with the holes on the L-shaped bracket. 12. The cabinet is fastened with four M10 bolts from below. Place a washer on the bolt and insert it upwards through the upper part of the L-shaped bracket and into the bottom of the cabinet as shown in Figure 23. The cabinet has nuts already installed in its bottom plate. Compare to Figure 18. Tighten with 37 Nm torque. 13. Turn the locking plate forwards. Check alignment with roof top holes. If the installation of equipment is finished and the roof top is reinstalled, it is important to have a correct fastening and environmental sealing. Perform the following steps: 1. Install metal washer on top of rubber washer as shown in the enlarged picture in Figure 26. Tighten the M8 bolt with 6 Nm. 2. Tighten the M10 nut with 37 Nm torque to fasten the locking plate in the wall frame bracket. 1/1531-LZA 701 6011 Uen K | 2016-03-01 37 Installing PBC B C A E D P022703B Figure 23 Table 10 8.1.3 Wall Frame Assembly Details Frame Details for Wall Installation Detail Description A M10 × 25 mm bolt. Inserted from outside B Washer C Nut, tighten with 37 Nm torque D Square washer plate 50 × 50 mm E Fastening bolt. Specified in the Site Installation document Installing the Cabinet on a Pole This section describes the steps and equipment needed to install the frame on a pole and to install the cabinet on the frame. The pole installation kit is an optional equipment. It is delivered disassembled, and must be assembled during the installation process before the cabinet can be positioned on the frame. Before starting the work, check that all pieces are present according to Table 11. The frame parts are shown in Figure 21. 38 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation Table 11 Pole Installation Frame - Part List Legend Description Quantity A Wall Bracket 2 B Locking plate 2 C Brace 2 D L- shaped bracket 2 E Pole bracket 2 Bolt M12 x 400 mm 4 Washers for M12 4 Nut, M12 8 Self locking nut, M12 8 Square washer plate 8 Washer for M10 18 Nut, M10 14 Bolt, M10 x 25 mm 18 To install the frame on a pole, the dimensions shown in Figure 22 and Table 9 are important. Figure 24 shows all the parts of the frame. The frame is assembled with M10 bolts from the outside in all the joints. On the inside a washer is installed and followed by the nut. Figure 26 shows how the cabinet is placed on the assembled frame, which is identical for both wall and pole installation. An enlarged detailed drawing shows how the locking plate is positioned. Note: Pay close attention to vertical alignment of the two brackets, and that they are parallel and horizontal. To install the frame on a pole, perform the following procedure: 1. Prepare the wall brackets with the M12 bolts, washers and nuts as shown on the right hand side of Figure 25. Note: The same brackets are used for pole and wall installation. A horizontal flip is the only difference between the two installations. 2. Install the lower wall bracket to the pole as shown in Figure 24 with details shown in Figure 25 left side. Check that the bracket is horizontal. Do not tighten to full torque at this point. 3. Install the upper wall bracket to the pole as shown inFigure 24 with details shown in figure Figure 25 left side. Check that the bracket is horizontal and that the distance between brackets is as shown in Figure 22. Do not tighten to full torque at this point. 1/1531-LZA 701 6011 Uen K | 2016-03-01 39 Installing PBC 4. Install L-shaped brackets on the lower wall bracket. For each side, use two M10 bolts installed from the outside as shown in Figure 24. Use washers and nuts. Tighten with 37 Nm torque. 5. Install the brace on each side as shown in Figure 24. Use M10 bolts installed from the outside. Use washers and nuts. Check that the L-brackets are level before tightening with 37 Nm torque. 6. Install locking plates below the wall frame on the upper bar, as shown in Figure 24. The rounded side must be towards the wall frame. Use M10 bolts installed from the outside. Use washer and nut. Keep the nut loose enough, so the plate can swing easily. Do not tighten at this point. 7. Lift the cabinet onto the frame and push toward the rear. A lifting device can be used for this operation. Please see Section 6.3 on page 22 for details. 8. If the two rear screws for roof panel have not been removed previously, do so now and slide the cabinet backwards so that the cabinet bottom holes are aligned with the holes on the L-shaped bracket. 9. The cabinet is fastened with four M10 bolts from below. Place a washer on the bolt and insert it upwards through the upper part of the L-shaped bracket and into the bottom of the cabinet as shown in Figure 24. The cabinet has nuts already installed in its bottom plate. Compare to Figure 18. Tighten with 37 Nm torque. 10. Tighten all the M12 nuts with 65 Nm torque. 11. Turn the locking plate forwards. The enlarged picture in Figure 26 shows the details. Check alignment with roof top holes. If the installation of equipment is finished and the roof top is reinstalled, it is important to have a proper fastening and proper environmental sealing. Perform the following steps: 1. Install metal washer on top of rubber washer as shown in the enlarged picture in Figure 26. Tighten the M8 bolt with 6 Nm. 2. Tighten the M10 nut with 37 Nm torque to fasten the locking plate in the wall frame bracket. 40 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation A D B C P022704C Figure 24 Table 12 Pole Frame Assembly Details Frame Details for Pole Installation Detail Description A M10 × 25 mm bolt. Inserted from outside B Washer C Nut, tighten with 37 Nm torque D Square washer plate 50 × 50 mm E M12 × 400 bolt, with square plate 1/1531-LZA 701 6011 Uen K | 2016-03-01 41 Installing PBC H G F E D C B A P022705B Figure 25 Table 13 42 Pole Frame Bracket Details Pole Frame Bracket Description Legend Description A M12 bolt with square head B Wall bracket C Round metal washer D Nut E Pole bracket F Square washer plate G Self locking nut H Nut 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation P022706C Figure 26 8.1.4 Assembled Pole Installation Frame Installing the Cabinet on Stacking Kit The stacking kit is only used for installing BBS 05 at the bottom, and PBC 05 on the top. Information about installing the PBC 05 cabinet on stacking kit can be found in Installing Stacking Kit. 8.1.5 Installing Cable Inlets There are several holes with different diameters punched in the metal frame at the bottom of the cabinet. These holes are intended for cable inlets. One cable is allowed per hole. For a proper environmental sealing, cable inlets are installed in the holes. When tightened with a correctly dimensioned cable the inlet will serve both as environmental sealant and as strain relief to the cable. Please refer to Figure 28. 1/1531-LZA 701 6011 Uen K | 2016-03-01 43 Installing PBC The cable inlet is shown in Figure 27. The inlet is tightened to the cabinet with two nuts. One from above and one from below, as shown in the picture. Make sure the cable gland is installed from the outside of the cabinet. P022430A Figure 27 Note: Cable Inlet Even unused inlets must have a cable inlet installed and covered with a cover seal. 18 7 8 9 10 11 12 16 13 14 15 17 19 22 1 2 3 4 6 21 20 5 23 24 25 P022444A Figure 28 Cable Inlet Positions in Cabinet Bottom The cable inlets are dimensioned for various different cable types and dimensions. Some cables are necessary and some are optional. This is described in detail in the Site Installation document. This document also lists the lengths of the different cables. All the possible options are shown in Table 14 Table 14 Cable Inlets and Hole Pattern in Cabinet. Position in PBC 05 PG Size Cable Diameter Cable Type Cable Purpose Connection Type 1 PG 16 10 - 14 mm Green/Yellow 35 mm2 Ground Cable Cable lug 8mm - Open ended 2 PG 29 18 - 25 mm AC mains. 5 x 16 mm2 AC main power. Number of conductors can vary Open end - Open end 3 PG 16 10 - 14 mm 3 x 1.5 - 2,5 mm2 220 VAC cable to heater in BBS Open end - Open end Or 2 x 1.5 - 2,5 mm2 44 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation Table 14 Position in PBC 05 Cable Inlets and Hole Pattern in Cabinet. PG Size Cable Diameter Cable Type Cable Purpose Connection Type PG 11 5 - 10 mm 4 x 2 x 0.5 mm2 In PBC: Incoming alarm cable Open end - Open end In BBS: incoming alarm cable. Open end - Open end In PBC: outgoing alarm cable to RBS Open end - Open end In BBS: outgoing alarm cable to PBC or BBS Open end - Open end PBC to RRU Open end - Open end PBC to RBS Open end - Open end PBC to RBS Open end - Open end 4 5 6 7 - 15 PG 11 PG 16 5 - 10 mm 10 - 14 mm 4 x 2 x 0.5 mm2 2 x 6 - 16 mm2 Shielded cable 16 PG 21 13 - 18 mm 2 x 16 mm2 1 x 25 - 70 mm2 Shielded cable 17 PG 21 13 - 18 mm 2 x 16 mm2 1 x 25 - 70 mm2 Shielded cable 18 PG 11 5 - 10 mm 2 x 2.5 - 6 mm2 From PBC to BBS for DC to fan Open end - Open end 19 PG 11 5 - 10 mm 2 x 2.5 - 6 mm2 From PBC to BBS for DC to fan Open end - Open end 20 PG 9 4 - 8 mm temp sensor In PBC: Incoming temperature sensor Special Cable 21 PG 9 4 - 8 mm temp sensor In PBC: Incoming temperature sensor Special Cable In BBS: Outgoing temperature sensor 22-25 PG 29 18 - 25 mm 1 x 50 mm2 PBC to BBS. Always in Pairs. 1 x 70 mm2 Unshielded Open ended - Open ended 1 x 95 mm2 8.2 Grounding the Cabinet This section describes how to install the cabinet grounding cable. The cabinet ground cable must be a 35 mm2 green/yellow cable. It is installed through the inlet position 1 at the bottom. Refer to figures Figure 28 and Table 14. The cabinet is equipped with a Main Earthing Terminal (MET) on the left hand side in front of the battery compartment, see Figure 29. To install the grounding cable, perform the following steps: 1. Connect the cable lug on the grounding point, the lower M8 stud on the MET. 1/1531-LZA 701 6011 Uen K | 2016-03-01 45 Installing PBC 2. Connect the other end of the ground cable to site grounding terminal. 3. Use plastic strip wire to secure the ground cable to the left inside frame of the cabinet to the hole near the MET. 4. Tighten the nut around the bottom of the cable inlet to form a tight seal in the cable gland. 13 mm 24 Nm P022460A Figure 29 8.3 Ground Cable Installation on Main Earthing Terminal (MET) Installing Incoming AC Power for PBC 05 Variant 1 This section describes how the AC main power is installed. The incoming AC main power cable is installed through the inlet position 2 at the bottom. Refer to figures Figure 28 and Table 14. The AC distribution unit is "box-like" and the front and rear view is shown in the Figure 30. The AC main power terminal is shown in Figure 31, when the cover plate on the left front side is removed. The type of AC cable depends on the market, and is specified in the site installation document. Electricity delivered to the site may vary. The cabinet can be adapted to several different configurations. At the back of the AC distribution unit, are both the strapping terminal and the Surge Protecting Device (SPD). 46 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation P022432A Figure 30 AC Distribution Unit PE N L3 L2 L1 P022668A Figure 31 AC Main Power Terminal Before beginning installation, it is necessary to determine which type of supply is available and then which strapping is needed. This is done using the data in Table 15, Figure 33 and Figure 32. Position number 1 is the factory default setting. This corresponds to three phases and separate neutral and protective earth lines, with a total of five conductors. 1/1531-LZA 701 6011 Uen K | 2016-03-01 47 Installing PBC Table 15 Posit ion AC Configuration and Strapping Configuration Numb er Voltage range Nominal Voltage Installation figure V AC Phase-Neutral V AC 1 3W + N + PE 346/200 433/250 230 A 2 3W + PEN 346/200 433/250 230 A 3 1W + N+ PE 200 - 250 230 B 4 1W + PEN 200 - 250 230 B 5 3W + N + PE 208/120 220/127 120 C 6 3W + PEN 208/120 220/127 120 C 7 3W + N + PE 200/100 240/120 110 C 8 3W + PEN 200/100 240/120 110 C 9 3W + PE 200-240 10 2W + PE + N 200/100 240/120 115 E 11 2W + PEN 200/100 240/120 115 E D PE N L3 L2 L1 Ge1626B Figure 32 48 AC Main Power Input Terminal and optional Strapping 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation Do the following steps for the correct AC main power installation: 1. Identify which AC main power configuration is delivered from the local electricity company in accordance with Table 15 and Figure 33. 2. If the default setting is used, go to Step 9. 3. Remove the AC distribution unit by removing the screws on the side of this module. 4. Install the correct strapping in the main power terminal as shown in Figure 33 and in Figure 32. 5. Install the correct strapping blocks in the strapping terminal, see Figure 33. 6. Install the wires marked X1-X3 correctly in the strapping terminal, as shown in Figure 33. 7. Install the correct strapping in SPD. This is required if the PEN combination is used. See Figure 33. 8. Return the AC distribution unit in its location with a torque of 10 Nm. 9. Remove the left plate on the AC main power distribution unit. The AC main power terminal is located beneath the plate. 10. Feed the AC cable through the cable inlet position 2 at the bottom of the cabinet. Refer to figures Figure 28 and Table 14. 11. Feed the cable along the left interior of the cabinet and through the hole on the left side into the AC distribution box. 12. Strip the AC cable to 10 mm length. 13. Install the AC main power cable in the terminal in accordance with the main power configuration as shown in Figure 33. 14. Use plastic strip wire to secure the AC main power cable and the ground cable to the left inside frame of the cabinet. 15. Install the cover of the left plate on the AC distribution unit using four screws to hold in place. 1/1531-LZA 701 6011 Uen K | 2016-03-01 49 Installing PBC Mains Input Terminal Strapping Terminal SPD PE N L3 L2 L1 A X3 X2 X1 PE N L3 L2 L1 PE N L3 L2 L1 17 16 15 14 13 12 11 7 6 5 4 3 2 1 B PE N L ZHONG GUANG PE N L3 L2 L1 L1 L2 L3 N N DEHN L1 L2 L3 N C X3 X2 PE N L3 L2 L1 PE N L3 L2 L1 X1 17 16 15 14 13 12 11 7 6 5 4 3 2 1 N N N N PE If PEN connection PE If PEN connection D PE L3 L2 L1 X3 X2 X1 PE N L3 L2 L1 17 16 15 14 13 12 11 E 7 6 5 4 3 2 1 PE N Figure 33 8.4 L2 L1 P022476A Configuration for Different AC Main Power Installing Incoming AC Power for PBC 05 Variant 2 This section describes how the AC main power is installed. The incoming AC main power cable is installed through the inlet position 2 at the bottom. Refer to Figure 28 and Table 14. The AC distribution unit is "box-like", and the front view is shown in the Figure 34. The AC main power terminal is shown in Figure 35, when the cover plate on the left front side is removed. 50 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation AC input terminal Service Outlet SPD Rectifier breakers AC mains adaption Heater breaker Ge4663B Figure 34 AC Distribution Unit L1 L2 L3 N PE Ge4675A Figure 35 AC Main Power Terminal Before beginning the installation, it is necessary to determine which type of power supply is available and which strapping is needed. This is done using the data in Table 16, Figure 36 and Figure 37. Position number 1 is the factory default setting. This corresponds to three phases and separate neutral and protective earth lines, with a total of five conductors. 1/1531-LZA 701 6011 Uen K | 2016-03-01 51 Installing PBC Table 16 Posit ion AC Configuration and Strapping Configuration Numb er Voltage range Nominal Voltage Installation figure (V AC) Phase-Neutral (V AC) 1 3W + N + PE 346/200 433/250 230 A 2 3W + PEN 346/200 433/250 230 A 3 1W + N + PE 200 - 250 230 B 4 1W + PEN 200 - 250 230 B 5 3W + N + PE 208/120 220/127 120 C 6 3W + PEN 208/120 220/127 120 C 7 3W + N + PE 200/100 240/120 110 C 8 3W + PEN 200/100 240/120 110 C 9 3W + PE 200-240 - D 10 2W + PE + N 200/100 240/120 115 E 11 2W + PEN 200/100 240/120 115 E PE N L3 L2 L1 Ge1626B Figure 36 52 AC Main Power Input Terminal and Optional Strapping 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation Do the following for the correct AC main power installation: 1. Identify which AC main power configuration is delivered by the local electricity company, according to Table 16 and Figure 37. 2. If the default setting is used, go to Step 8. 3. Remove the front cover of the AC distribution unit. 4. Install the correct strapping in the mains power terminal and the strapping terminal as shown in Figure 36 and Figure 37. 5. Install the correct strapping blocks in the strapping terminal; see Figure 37. 6. Install the wires marked X1 - X3 correctly in the strapping terminal, as shown in Figure 37. 7. Install the correct strapping in SPD. This is required if the PEN combination is used. See strapping terminal in Figure 37. 8. Feed the AC cable through the cable inlet position 2 at the bottom of the cabinet. Refer to Figure 28 and Table 14. 9. Feed the cable along the left interior of the cabinet and through the hole on the left side into the AC distribution box. 10. Strip the AC cable, a length of 10 mm. 11. Install the AC main power cable in the mains input terminal according to the main power configuration as shown in Figure 37. 12. Use plastic strip wire to secure the AC main power cable and the ground cable to the left inside frame of the cabinet. 13. Install the cover of the left plate on the AC distribution unit using two screws to hold in place. 1/1531-LZA 701 6011 Uen K | 2016-03-01 53 Installing PBC Mains Input Terminal Strapping Terminal SPD L1 L2 L3 N PE Emerson Class 2 A X3 X2 X1 L1 L2 L3 PE L1 L2 L3 N PE N N 7 6 5 4 3 2 1 B ZHONG GUANG Class B+C L1 L2 L3 N PE L1 L2 L3 N N C X3 X2 X1 N N N N PE L1 L2 L3 N PE 7 6 5 4 3 2 1 D DEHN Class B+C L1 L2 L3 N X3 X2 X1 L1 L2 L3 N PE PE E 7 6 5 4 3 2 1 Ge4689A Figure 37 8.5 Configuration for Different AC Main Power Installing the AC Service Outlet (Optional) for PBC 05 Variant 1 There is space on the AC distribution unit to install an optional AC service outlet. This section describes how it is installed. The steps in this section can be done if all the incoming AC main power cable installations and configurations have been made. The AC main distributions unit must also be firmly replaced in its position, if it has been removed. The AC service outlet comes preassembled and is ready for installation. It consists of two parts: the outlet contact and the circuit breaker and they are 54 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation interconnected by a piece of cabling. Figure 38 shows the European outlet. Other outlet types can be ordered. Note: All outlets are equipped with a residual circuit breaker. To install the AC service outlet, perform the following steps: 1. The narrow middle panel of the AC distribution unit is removed by loosening the screw on the top of the panel and then lifting the panel. 2. Connect the three pin connector at the back of the circuit breaker with the connector on the cable just behind the previously removed panel. 3. Insert the panel with the circuit breaker into the bottom slot and fasten it on the top side with the screw from the removed panel. 4. The AC outlet is installed piggy-back on the large panel by sliding the two small flanges into the holes of the panel, and then securing the outlet with the screw on the top end. P022433A Figure 38 8.6 AC Service Outlet for PBC 05 Variant 1 Installing the AC Service Outlet (Optional) for PBC 05 Variant 2 There is space on the AC distribution unit to install an optional AC service outlet. This section describes how it is installed. The AC service outlet comes preassembled and is ready for installation. The AC service outlet consists of two parts: the outlet contact and the circuit breaker as shown in Figure 39. If needed, use the adpater as shown in Figure 40. 1/1531-LZA 701 6011 Uen K | 2016-03-01 55 Installing PBC Figure 39 shows the European outlet. Other outlet types can be ordered. Note: All outlets are equipped with a residual circuit breaker. To install the AC service outlet, perform the following steps: 1. Connect the three pin connector at the top of the circuit breaker with the connector on the cable. 2. Insert the service outlet into the DIN rail. 3. Plug in the adapter into the outlet contact, if needed. Ge4700C Figure 39 AC Service Outlet for PBC 05 Variant 2 Ge4706A Figure 40 56 Adapter 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation 8.7 Installing SPD in PBC 05 Variant 2 There is space on the AC distribution unit to install the SPD. This section describes how it is installed. The AC distribution unit is pre-wired for SPD installation, and the wires are connected to AC connector inputs, and are isolated, as shown in Figure 41. Ge4686A Figure 41 Pre-wired AC Distribution Unit for SPD Installation To install the SPD in PBC 05 variant 2, perform the following steps: 1. Remove the isolation and connect the wires to the SPD. ' Ge4685A 2. Connect the grounding wire from "PE" on the SPD to the MET bar in PBC. 1/1531-LZA 701 6011 Uen K | 2016-03-01 57 Installing PBC L1 L2 L3 PE N Ge4687A 3. Connect the wires to the SPD class B+C or class C. L1 L2 L3 N N N N N N PE Ge4688A 8.8 Connecting Power Distribution to Site Equipment This section describes the installations of cables, circuit breakers and other optional cabling in the system. Cables to external equipment, and internal equipment, are terminated at various terminals and boards inside the cabinet. The MET and AC connections have been described. External AC and DC connections are described in the coming sections. On the right hand side on the inside of the cabinet are several connector blocks and boards, see Figure 42. Details will be given in subsequent chapters. Alarm signals and sensors are among the cables which are terminated in this area. At the top is the connector block for incoming external digital alarms from other cabinets as shown in detail inFigure 53. One step below is the interface board for the cabinet controller unit. External temperature sensors are connected to this board. Details are shown inFigure 57 Towards the bottom is a ground connector block for cable shield connection. Refer to Figure 52. 58 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation P022465A Figure 42 8.8.1 Cabinet Right Inside Terminals Installing Circuit Breakers and Connecting Cables This section describes how to install circuit breakers in the cabinet and how DC distribution cables are connected to both the circuit breaker with 048 V and the 0 V connector blocks. Circuit breakers for AC distribution are factory installed. Figure 43, Figure 44 and Figure 45 shows the DC power shelf from different views and with panels and circuit breakers removed. A B C D ENT ESC Ge4664A Figure 43 DC Power Shelf 1/1531-LZA 701 6011 Uen K | 2016-03-01 59 Installing PBC Table 17 Power Shelf positions Position Description A Priority load for DC distributions. A Factory installed circuit breaker in the left most position at 6 A is reserved for fan supply. Eight positions towards the left are available for user configuration. B Battery circuit breakers. 12 circuit breaker positions in total. One block of 4 positions is factory installed. C Main load circuit breakers. Eight positions available for user configuration. D System controller for on-site and remote system access. The location, type and number of circuit breakers is depending on the configuration, and is described in the Customer Site Documentation. Circuit breakers are installed at the front of the power system. Figure 44 shows the DC Multifunction Unit. There is a rail for circuit breakers in the front. Behind the circuit breakers there is a 0 V connector block for the corresponding wire pair. Note: Figure 44 shows the open front cover in a forward position. Remove the cover during installation by halfway unscrewing the screws on the hinges at the bottom. The lower connector, the pegs shown in Figure 44, are feeding the circuit breakers. 60 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation B A C D E K F G J H P022737A Figure 44 Table 18 DC Multifunction Unit for PBC DC Multifunction Unit Details Positi on Function A Relays, for power switching to main load and priority load B DC Surge Protection Device C Connector block on top of Controller for battery temperature sensor connection D 0 V connector blocks E DIN rail for circuit breaker support F System Controller for on-site and remote system access G Current feeding pegs from relays to circuit breakers H Circuit breaker J Space between 0 V connector blocks and circuit breakers, in which alarm cables are located K Circuit breaker terminal for load connection (1) (1) The system controller for a PBC 05 can be either standard (SCU+) or advanced (ACU+). The system controller for a PBC 05 Solar Hybrid can only be ACU+. 1/1531-LZA 701 6011 Uen K | 2016-03-01 61 Installing PBC Circuit breakers occupy between one to four positions depending on the load current. The number and type of circuit breakers is specified in the Customer Site Documentation. Figure 46 shows how a circuit breaker is installed. P022448A Figure 45 DC Multifunction Unit, Left view A circuit breaker is installed in the following steps: 1. Verify in the Customer Site Documentation which type and which position should be used. 2. Make sure all screws in the bottom are completely loosened. 3. Slide the circuit breaker from above over the ‘‘peg’’ . 4. Move the top portion inwards as shown on the left hand side of the figure below. 5. Slightly lift the circuit breaker so its top end slides over the rail, and then let it drop downwards. 6. Tighten all the bottom end screws as shown on the right hand side of the figure. 62 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation 1 2 P022736A Figure 46 Circuit Breaker Installation Circuit Breaker Alarms The PBC 05 system controller is capable of detecting open circuit breaker and generate alarms. For that purpose the proper alarm cables need to be installed. The alarm cables are partly factory installed. The installation already done, is the connection for the digital input to the controller. The other end of the cable needs to be installed in the circuit breaker together with the 048 V cable. Two bundles with circuit breaker alarm cables can be found in the groove between the circuit breaker suspension DIN rail and the 0 V connector blocks. Please refer to Figure 44 and Figure 47. One bundle consists of several black cables. They are shrink wrapped together in the factory delivery, and they are all unmarked. In addition there are three colored cables. These are each marked with a battery fuse number, Batt1, Batt2 and Batt3. Number one is intended for the optional internal battery string. This circuit breaker with fork and alarm cable is factory installed. Number 2 and 3 are intended for the optional external battery cabinets. For each load in the multifunctional unit an alarm cable must be installed. The battery cables have their dedicated colors and corresponding alarms. All the black cables are identical, and any can be used an any circuit breaker location. For installation of an alarm cable, please see the details in Figure 48. It shows an alarm cable installed together with the fork in one circuit breaker. The same applies if no fork is used. Unused alarm cables are bundled together and wrapped in insulated tape and tucked back and secured into the groove. The fans are located at the back of the shelf above the DC power system. Towards the front is space to feed all the cables to the circuit breaker and 0 V rails, which are all installed from above. A cable can have a single terminal or a fork based terminal, depending on the current rate. Figure 48 shows a cable installed with a fork and Figure 49 without a fork. A fork can have two to four teeth connecting to the circuit breakers or 0 V rails, and the Figure 48 shows a fork with two teeth. 1/1531-LZA 701 6011 Uen K | 2016-03-01 63 Installing PBC ×20 P022492A Figure 47 64 Alarm Cables 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation P022475B Figure 48 Cable Connected to Forks To Install a cable with fork, perform the following steps: 1. Insert the fork in the terminals on the 0 V connector block at the back and tighten all the screws as shown in the figure above. 2. Insert the fork in the terminals on the circuit breaker and tighten all the screws as shown in Figure 48. 3. Strip about 15 mm of the cables. 4. Connect the plus (+) cable to the fork on the 0V connector block. Insert circuit breaker alarm cable and tighten the screw. 5. Connect the minus (0) cable to the fork on the circuit breakers and tighten the screw. Note: The fork used in the 0V connector block always has two teeth, even if circuit breaker fork has three or four teeth. 1/1531-LZA 701 6011 Uen K | 2016-03-01 65 Installing PBC P022738A Figure 49 Cable Connected Directly to 0 V Terminal and Circuit Breaker To install a cable without fork, perform the following steps: 1. Strip about 15 mm of the cables 2. Connect the plus (+) cable to the ground connector block at the back. Insert the alarm cable and tighten the screw. 3. Connect the minus (0) cable to the circuit breakers. Tighten the screw. 8.8.2 Connecting DC Input on Solar Subrack The solar subrack is a power device providing electricity for load by using solar energy. The subrack contains the solar connection point and wind connection point. The wind connection point is optional. Table 19 66 DC Solar Input Connection Point Input Voltage Range Solar 2 x (68-106 V DC, Maximum Maximum 6 kW 50 A) Output Power 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation 1+ 23+ 4- + Solar connection Ge4666A Figure 50 Cable Connection on Solar Subrack To install a DC input cable from one solar power system, perform the following steps: 1. Strip about 10 mm of the cables 2. Connect the (+) cable from the number one solar power system to the 1+ on the solar connection point see Figure 50. 3. Connect the minus (0) cable to the 2-. 4. Tighten the screws firmly. To install a DC input cable from a second solar power system, perform the following steps: 1. Strip about 10 mm of the cables 2. Connect the (+) cable from the number two solar power system to the 3+ on the solar connection point see Figure 50. 3. Connect the minus (0) cable to the 4-. 4. Tighten the screws firmly. 8.8.3 Connecting the Incoming Alarm Cable (Optional) The local controller unit in the cabinet can support both internal end external alarms through digital alarm input. This section describes how external digital alarm signals are connected. External digital alarms are connected to the alarm connector block, shown in Figure 53 . The alarm inputs are designed in a Normally Closed (NC) configuration. The Figure 53 shows the alarm connector block which is located on the right hand side of the cabinet. The figure shows, on the left hand side, the factory default delivery. Three wire straps are inserted to close the loop and to prevent the external binary alarms. The position of the alarm connector block is shown 1/1531-LZA 701 6011 Uen K | 2016-03-01 67 Installing PBC in Figure 42. The system controller software is setup assuming three types of external alarms, namely: • Fan alarm in external cabinet. • Door open in external cabinet. • Fuse open in external battery string The incoming alarm cable is of type 4x2x0,5 mm 2. It is installed through the inlet position 5 or 6 at the bottom. Refer to figures Figure 28 and Table 14. The alarm cables has one extra pair of wires that is unused. Strip the cable as shown in Figure 51. To install alarm cables, perform the following steps: 1. Install cable through the inlet at the bottom and fed it to the alarm connector block. 2. Remove strapping on positions 1-2. 3. Install open door alarm on terminals 1-2. 4. Remove strapping on positions 4-5. 5. Install External Battery fuse open alarm on position 4-5. 6. Remove strapping on position 7-8. 7. Install External Fan alarm on position 7-8. 8. Secure cable to right hand side of cabinet with plastic wire straps. 9. Twist the shield and cut to appropriate length so it can be properly fastened at the cable shield connector block. Refer to figureFigure 52. 10. Tighten the cable inlet nut. 68 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation B A C P022452A Figure 51 Alarm Cable Table 20 Cable stripping Position Length A Dismantle the cable to appropriate length. B 5 mm C Cut the shield to appropriate length to fit to cable shield terminal P022467A Figure 52 Cable Shield connector block 1/1531-LZA 701 6011 Uen K | 2016-03-01 69 Installing PBC 1 –48 V DC 12 0 V DC A B P022729A Figure 53 Alarm connector block Table 21 Alarm Terminal Positions Position 8.8.4 Function A 048 V DC to external fan B Digital alarms from external cabinet in NC loop function. Installing External Alarms Connections This section describes outgoing alarms on IB2 board for PBC 05, and PBC 05 solar hybrid. 8.8.4.1 Outgoing alarms on IB2 board in PBC 05 Figure 54 shows the outgoing alarms on IB2 board in PBC 05. 70 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation Board IB2-ROA1190872/1 J6:1 (DO1_NC) Critical alarm J6:3 (DO1_COM) J3:1 (DI1+) Relay output 1 Digital input 1 J6:5 (DO1_NO) J3:3 (DI2+) J6:2 (DO2_NC) Major alarm (Not urgent) J6:4 (DO2_COM) Digital input 2 Relay output 2 Digital input 3 J7:1 (DO3_NC) J7:3 (DO3_COM) Relay output 3 J7:5 (DO3_NO) J3:4 (DI2-) J3:5 (DI3+) J6:6 (DO2_NO) Observation alarm J3:2 (DI1-) J3:6 (DI3-) J4:1 (DI4+) Digital input 4 J4:2 (DI4-) J7:2 (DO4_NC) J4:3 (DI5+) Door open alarm J7:4 (DO4_COM) Relay output 4 Digital input 5 J4:4 (DI5-) J7:6 (DO4_NO) J4:5 (DI6+) J8:1 (DO1_NC) Fan failure alarm J8:3 (DO1_COM) Relay output 5 Digital input 6 J8:5 (DO1_NO) J5:1 (DI7+) J8:1 (DO2_NC) Battery temp alarm (High and low batt temp) J8:3 (DO2_COM) Digital input 7 Relay output 6 J8:5 (DO2_NO) Prio operation signal to RBS (follow the LVD1 contactor) Spare J9:4 (DO4_COM) Relay output 7 J9:5 (DO3_NO) J5:2 (DI7-) J5:3 (DI8+) Digital input 8 J9:1 (DO3_NC) J9:3 (DO3_COM) J4:6 (DI6-) J5:4 (DI8-) J5:5 Digital input 9 J5:6 J9:2 (DO4_NC) Relay output 8 J9:6 (DO4_NO) Ge5921A Figure 54 8.8.4.2 Outgoing alarms on IB2 board in PBC 05 Outgoing alarms on IB2 board in PBC 05 Solar Hybrid Figure 55 shows and Table 22 describes the outgoing alarms on IB2 board in PBC 05 solar hybrid. 1/1531-LZA 701 6011 Uen K | 2016-03-01 71 Installing PBC Board IB2-ROA1190872/1 J6:1 (DO1_NC) Generator alarms J6:3 (DO1_COM) J3:1 (DI1+) Digital input 1 Relay output 1 J6:5 (DO1_NO) J3:3 (DI2+) J6:2 (DO2_NC) Battery alarms J6:4 (DO2_COM) Digital input 2 Relay output 2 Digital input 3 J7:1 (DO3_NC) Rectifier alarms J3:4 (DI2-) J3:5 (DI3+) J6:6 (DO2_NO) J7:3 (DO3_COM) J3:2 (DI1-) J3:6 (DI3-) J4:1 (DI4+) Relay output 3 Digital input 4 J7:5 (DO3_NO) J4:2 (DI4-) J7:2 (DO4_NC) J4:3 (DI5+) System alarms J7:4 (DO4_COM) Relay output 4 Digital input 5 J4:4 (DI5-) J7:6 (DO4_NO) J4:5 (DI6+) J8:1 (DO1_NC) Generator run at high temp J8:3 (DO1_COM) Digital input 6 Relay output 5 J8:5 (DO1_NO) J5:1 (DI7+) J8:1 (DO2_NC) LVD control J8:3 (DO2_COM) Digital input 7 Relay output 6 Digital input 8 J9:1 (DO3_NC) DG1 in operation J5:2 (DI7-) J5:3 (DI8+) J8:5 (DO2_NO) J9:3 (DO3_COM) J4:6 (DI6-) J5:4 (DI8-) J5:5 Relay output 7 Free terminals J9:5 (DO3_NO) J5:6 J9:2 (DO4_NC) DG2 in operation J9:4 (DO4_COM) Relay output 8 J9:6 (DO4_NO) Ge5922A Figure 55 Table 22 Outgoing alarms on IB2 board in PBC 05 Solar Hybrid Outgoing alarms on IB2 board in PBC 05 Solar Hybrid Relay Alarm 1 General Alarms: No generator alarm or No AC supply (delayed 60s) 2 Battery Alarms: Under voltage 1 or Under voltage 2 or LVD 1 or LVD 2 or Battery high temp or Battery very high temp or Over voltage 1 or Over voltage 2 or Battery temp sensor fail or Battery fuse alarm or High load alarm 72 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation Relay Alarm 3 Rectifier Alarms: Multiple rectifier alarm or Rectifier fail or Rectifier fan failure or Rectifier HVSD or Rectifier AC failure or Rectifier not responding 4 System Alarms: Load fuse alarms or High ambient temperature or Ambient temp sensor fail or Smoke detected or Water detection 5 Generator Run at High Temp: Control signal to a cooling device 6 LVD Control: Prio operation signal to RBS (to follow LVD 1) 7 DG1 in Operation: Control signal to DG1 8 DG2 in Operation: Control signal to DG2 8.8.5 Connecting Outgoing Alarm Cables The local controller in the cabinet can process both internal and external sources. All alarms that are processed can be generated to an external management or signal entity. The controller has the following two different output formats: • Digital relay output. • RJ 45 connector for Local Area Network (LAN) connectivity. The RJ45 connector is inserted in the socket of the controller Digital output signals are generated in the IB2 board. 1/1531-LZA 701 6011 Uen K | 2016-03-01 73 Installing PBC 8.8.6 Connecting DC Supply to Fans in Other BBS 05 Cabinets (Optional) The cabinet can supply 048 V DC to fans in external battery cabinets. This section describes how to install the outgoing 048 V DC. DC power is provided to external fans from the alarm connector block, shown in Figure 53 The outgoing 048 V DC cable to external fan is of type 2x2,5 mm2. It is installed through the inlet position 18 or 19 at the bottom. Refer to figures Figure 28 and Table 14. 1. Install cable through the inlet at the bottom and route the cable to the alarm connector block. 2. Install the cable on position 11 for the 048 V connection. 3. Install the cable on position 12 for the 0 V connection. 4. Secure the cable to the right hand side of the cabinet with plastic wire straps. 5. Tighten the cable inlet. 8.8.7 Connecting 048 V DC to other Site Equipment The cabinet can supply 048 V DC to various other RBS site equipment. For example the Radio Remote Unit (RRU) and transmission systems can be supplied with DC power. This section describes how to install these power feeds. The type and number is site dependant and is described in detail in the Customer Site Documentation. This installations process requires cable routing through the bottom inlets, along the right hand side of the cabinet up to the top to ground connector block and circuit breakers at the top of the cabinet. Cables are installed through the inlets position 7-15,16 and 17at the bottom. Refer to figures Figure 28 and Table 14. 74 • Cable type, dimension and length are described in detail in the Customer Site Documentation. • Cable inlet, based on dimension is defined as listed in Table 14 if not specified in the Customer Site Documentation. • The number of circuit breakers and the position to be used is described in the Customer Site Documentation. • Seal unused cable inlets at the bottom of the cabinet. • Some cables will have shielding. The shield is connected to the cable shield connector block on the right hand side of the cabinet. Refer to Figure 52. 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation • All DC load cables come in pairs. One for the 048 V DC and one for 0 V. In some cases the cable has one conductor, and in some cases the cable might have two conductors. Cables may be shielded or not. Cable specification like type and length are given in the Customer Site Documentation. Note: Make sure that the -48 V DC cables (feed and return cables) are tied together all the way to the load. Bonding Signal DC DC-return Ge0411B • For each installed equipment, that is supported by a separate circuit breaker, an alarm cable must be installed. This alarm is triggered when the circuit breaker trips and disconnects power to this particular equipment. Please see Section 8.8.1 on page 59 for more information on alarm cables. Cable routing and installation in the DC multifunction unit is much easier if the roof panel is removed as described in Section 7 on page 27 and Figure 15. For each of the cable pairs, follow the procedure below: 1. Insert the cable from below through the correct inlet. 2. Route the cable to the right hand side of the cabinet. 3. Route the cable to the top of the cabinet by feeding it upwards between the cabinet and the rack frame on the right hand side. 4. If the cable is shielded, perform the following steps: • Before feeding the cable to the top, split the shield from the cable. About 60 to 70 cm should be sufficient. • Cut the shield to proper length, twist it, and terminate the shield in the cable shield connector block on the right-hand side as shown in Figure 52. 1/1531-LZA 701 6011 Uen K | 2016-03-01 75 Installing PBC 5. Connect the 0 V cable to the 0 V rail at the back from above. Section 8.8.1 on page 59 describes the options with and without a fork. 6. The 048 V cable is connected to the circuit breaker at the front. This is done from above. Please refer to Section 8.8.1 on page 59 showing the options with and without a fork. Repeat the above steps for all other cable pairs. To conclude this installation perform the following steps: 1. Tighten all the cables together with a plastic strap wire and also tie the bundle to the right side frame of the cabinet. 2. Tighten the cable inlet nut to form both a tight environmental seal as well as a strain relief. 8.8.8 Connecting the Battery Temperature Sensor This section describes the installation of the battery temperature sensor. It controls the load voltage, depending on temperature. The control unit in the DC multifunctional unit terminates the signals from all the battery temperature sensors. The cabinet can monitor the input from up to 3 temperature sensors. The controller software controls the load current to the batteries depending on the temperature. Only one of the input signals from the sensor is able to control the load current. Hence it has to be decided which of the temperature sensors has the controlling function. The other two sensors are recognized but only from alarm purpose of high or low temperature. The sensor that is selected to control the load current has to be terminated at the connector on top of the control unit. The factory installed temperature sensor, which is intended for internal optional battery string, is terminated at the controller. Please refer to Figure 44 and Figure 56 for details. The other end, the sensor element, is routed to the battery shelf. The other two optional sensors are connected to J11 and J12 on the IB2 as shown in Figure 57. The temperature sensor itself, is inserted on the side of the selected battery in a temperature sensor holder If the temperature sensor is to be installed on the side of one battery block, this is done during the process of battery installation as described in Section 8.8.11 on page 81. If the temperature sensor is to be installed on the front of a battery block it can be placed in correct position at any time. Note: 76 A PBC 05 cabinet can support up to two external battery cabinets. The system may be designed so that the battery load voltage is controlled from an external cabinet. In that case it becomes important which of the temperature sensors is connected to the different terminals. 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation P022494B Figure 56 Note: 8.8.9 Battery Temperature Sensor Termination Red cable to the left and blue cable to the right. Connecting the External Battery Temperature Sensor (Optional) The controller interface board IB2, located on the right hand in-side of the cabinet has several connectors. At the bottom side are two connectors, labeled J11 and J12, giving room for two external battery temperature sensors as shown in Figure 57. 1/1531-LZA 701 6011 Uen K | 2016-03-01 77 Installing PBC J9 J8 SW1 J7 J1 J6 J10 J5 J4 J3 J2 J11 J12 P022466A Figure 57 Interface Board 2 The battery sensor cable has on one side a temperature sensor and on the other side a three pin connector. Neither end can pass through the bottom end cable inlet. Cables are installed through the inlets position 20 and 21 at the bottom. Refer to figures Figure 28 and Table 14. To install the external temperature sensor, perform the following steps: 1. Remove the plastic housing on the connector for each of the pins. This is done by pressing the spring of the pin contact using a small flat screwdriver and pulling the wire. The metal connector comes out of the housing, still attached to the wire. Repeat this for all the three wires as shown in Figure 58 on the left side. Note: Make sure to list to which position each wire belongs. In Figure 58 the cables are in the following order, top to bottom: black, blue, red. 2. Feed the wire, with the three metal connectors from the inside of the external cabinet to the outside. 3. Feed the wire, with the three metal connectors upwards through the cable inlets in the PBC 05 from below. 4. Install the plastic housing on the metal connectors by pushing the cable connectors back into the housing. The spring will lock the connector into the housing as shown on the right side of Figure 58. 5. Connect the connector to the IB2 temperature sensor input as instructed below. 78 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation 6. Place the battery temperature sensor itself in the Battery Backup System following the installations guidelines for that specific product. Temp sensor IB2 board P022470C Figure 58 Temperature Sensor Cable The control unit in the DC multifunctional unit terminates the signals from all the battery temperature sensors. The controller software controls the load current to the batteries depending on the temperature. Only one of the input signals from the sensor is able to control the load current. Therefore it must be decided which of the temperature sensors has the controlling function. The other two sensors are recognized but only from alarm purpose of high or low temperature. The sensor that is selected to control the load current has to be terminated at the connector on top of the control unit. The other two sensors are connected to J11 and J12 on the IB2 as described above. 8.8.10 Handling the Battery Temperature Sensor when no Internal Batteries in the PBC 05 Cabinet This section describes how to handle the factory installed battery temperature sensor when the PBC 05 has no batteries. The following two scenarios exist: • No batteries at all in the system. That is, no batteries in the PBC 05 cabinet and no connected BBS cabinet. Go to Section 8.8.10.1 on page 80 for instructions on how to handle the battery temperature sensor. 1/1531-LZA 701 6011 Uen K | 2016-03-01 79 Installing PBC • Only batteries in a connected BBS. That is, no batteries in the PBC 05 cabinet but a connected BBS cabinet. Go to Section 8.8.10.2 on page 80 for instructions on how to handle the battery temperature sensor. 8.8.10.1 No batteries in the System Follow the instruction to remove the factory installed battery temperature sensor: 1. Remove the temperature sensor cables from the SCU, as shown in Figure 56. 2. Disable the temperature sensor function in the SCU as instructed in the SCU User Guide. 8.8.10.2 Only Batteries in a Connected BBS Follow the instruction to connect the battery temperature sensor from the BBS cabinet to the SCU: 1. Follow step 1 to step 3 in Section 8.8.9 on page 77. 2. Remove the factory installed temperature sensor cables from the SCU, shown in Figure 56. 3. Connect the temperature sensor cable from the BBS to the SCU, as shown in Figure 59. Note: Connect the red cable to the left and the blue cable to the right. The black cable is not used. 4. Place the battery temperature sensor itself in the Battery Backup System following the installations guidelines for that specific product. 80 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation SCU Temp sensor P022976A Figure 59 8.8.11 Temperature Sensor Cable between BBS and SCU Installing the Battery String (Optional) The PBC 05 has the space to hold one internal battery string consisting of four batteries. This section describes how the batteries are installed. The product description document explains which battery types are approved. See the reference list for proper document titles. Note: Battery blocks are heavy. A battery lift may be of assistance The battery installation is much easier to do if the optional heater has not been installed yet. However it is not a requirement to do this in this particular order. Figure 3 and Figure 61 show the battery compartment and the battery positioning in the cabinet. The cable connection to the battery string is factory installed. The terminals with cable lugs come with protective covers, and the loose terminals are found in the battery compartment. Compare Figure 61 and Figure 62, showing two different ways of installing the cables to the battery string. One battery string has the connections from above and the second battery string has the connections at the front, using adaptors. The front adaptor is used together with Enersys batteries. They are used only at the battery terminals to which the cables are connected. 1/1531-LZA 701 6011 Uen K | 2016-03-01 81 Installing PBC Note: Batteries can be secured in position by a battery strap as shown in Figure 60. This strap is an optional equipment that is only mandatory in earthquake zone 4. P022436A Figure 60 Note: Battery Strapping Before each battery block is installed in the process below, make sure the top part of the battery strap does not fall on the back of the battery, but stays on top. To install batteries, perform the following procedure: 1. Install the battery strap as shown in Figure 60. Leave the front end lock open and the strap loose enough to place the batteries. 2. Install the battery block spacer on the right side of the first battery as shown in Figure 63. 3. Place the first battery block in the middle of the shelf and push in half-way, so the battery block does not fall out. Make room enough so the battery terminals stick out in the front. 4. Connect the battery cable to the battery from above and place the cable lug over the negative (-) terminal. Insert the bolt and tighten according to battery type. 5. Push the battery inside and to the left side position No 1, as shown in Figure 61. Make sure the top portion of the battery strap is on top and does not fall behind the battery blocks. 6. Place the second battery block in the middle of the shelf and push in half-way, so the block does not fall out. Make room enough so the battery terminals stick out in the front. 82 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation 7. Connect the battery cable to the battery from above and place the cable lug over the positive (+) terminal. Insert the bolt and tighten according to battery type. 8. Push the battery inside and to the right side position No 4, as shown in Figure 61. Make sure the top portion of the battery strap is on top and does not fall behind the battery blocks. 9. Install the battery block spacer and the temperature sensor holder on the right side of the third battery as shown in Figure 64. 10. Place the third battery block into the shelf and push in and to the left to position No 2 shown in Figure 61. Make sure the top portion of the battery strap is on top and does not fall behind the battery blocks. 11. Install the battery temperature sensor by inserting the sensor in the holder on the right hand side of the battery in position No 2 as shown in Figure 65. 12. Install the inter battery block spacer on the right side of the last battery as shown in Figure 63. 13. Place the last battery block into the shelf and push in half way. 14. Push in and to the right to position No 3 as shown in Figure 61. Make sure the top portion of the battery strap is on top and does not fall behind the battery blocks. 15. Install the battery inter block connection between batteries 1 and 2. Tighten according to battery type. 16. Install the battery inter block connection between batteries 3 and 4. Tighten according to battery type. 17. Install the battery pole protection cover on batteries 1 and 4 as shown in Figure 66. Leave the two last covers to the initialization stage. Note: Leave the inter battery connection between batteries 2 and 3 uninstalled. This connector is installed during the start up process. 1/1531-LZA 701 6011 Uen K | 2016-03-01 83 Installing PBC 1 2 3 4 P022446B Figure 61 Battery Positions P021230B Figure 62 84 Battery Front End Adaptor 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation 0,5xH H Front 30 30 Units of measurement: mm Figure 63 P028071C Battery Block Spacer Pads 0,5xH 0,5xH H Front 30 Units of measurement: mm Figure 64 30 P028072C Temperature Sensor Holder 1/1531-LZA 701 6011 Uen K | 2016-03-01 85 Installing PBC P028074B Figure 65 Temperature Sensor Attachment P022727A Figure 66 Battery Pole Protection Cover When all the batteries are in position, pull the two loose ends of the battery holding strap. This will tighten the top side of the strap.Figure 60 shows how the strap must be positioned with the lock at the front.Figure 67 shows in detail how the strap is fed through the lock and how it is secured by closing the lock towards the left. 86 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation P022437A Figure 67 8.8.12 Battery Strap Locking Mechanism Installing the 19-inch Equipment (Optional) PBC 05 allows the battery compartment to be used for housing 19-inch equipment instead of, or along with, a battery. If the 19-inch compartment is to be used for equipment that require high cooling capacity, or have internal fans, the air restriction plate must be removed. To install the 19-inch equipment: 1. Locate the air restriction plate in the rear of the cabinet, shown in Figure 68 . 2. Remove the air restriction plate, shown in Figure 69. Use two screwdrivers to bend the plate down. Remove the plate downward. 3. Install the 19-inch equipment. Refer to the relevant installation instructions. 4. Fill the empty slots in the 19-inch compartment with dummy plates; otherwise the climate system may not function properly. 1/1531-LZA 701 6011 Uen K | 2016-03-01 87 Installing PBC PBC 05 Front Rear Air restriction plate P022453C Figure 68 Location of Air Restriction Plate Ge1433A Figure 69 8.8.13 Removing the air restriction plate Connecting the external Battery Backup Systems (Optional) In addition to the single battery string in the inside the cabinet, one or two additional cabinets with batteries can be installed. This section describes how the cables are connected. 88 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation Cables are installed through the inlets position 22 to 25 at the bottom as shown in Figure 28 and Table 14. The cables are routed along the right-hand side of the cabinet up to the top to the ground connector block and circuit breakers. For each installed external battery cabinet, a separate circuit breaker and alarm cable must be installed in the DC multifunctional unit. This alarm is triggered when the circuit breaker triggers and disconnects power to the external battery cabinet. Please see Section 8.8.1 on page 59 for more information on alarm cables. For each of the cable pairs, follow the procedure below: • Cable type, dimension and length will be described in detail in the Customer Site Documentation. • Cable inlet, by dimension is defined as listed in Table 14 if not specified in Customer Site Documentation. • The number of circuit breakers and the position to be used is described in the Customer Site Documentation. • Unused cable inlets at the bottom of the cabinet need to be properly sealed. • All Battery Backup System cables come in pairs. One for the -48 V DC and one for 0 V path. Cable specification like type and length are given in the Customer Site Documentation. Cable routing and installation in the DC multifunction unit is much easier if the roof panel is removed as described in Section 7 on page 27 and Figure 15. For each of the cable pairs, follow the procedure below. 1. Insert the cable from below through the correct inlet. 2. Route the cable to the right hand side of the cabinet. 3. Route the cable to the top of the cabinet by feeding it between the cabinet and the rack frame on the right-hand side. 4. Insert the 0 V cable in the 0 V rail at the back from above. Section 8.8.1 on page 59 describes the options with and without a fork. 5. Insert a fork with four teeth on top of a circuit breaker combination as described in the Customer Site Documentation. Install the battery fuse alarm cable in one of the circuit breaker terminals at the same time. 6. Insert the 048 V cable in the fork at the front from above.Section 8.8.1 on page 59 describes the options with and without a fork. Repeat the above mentioned steps for all other cable pairs. Conclude this installation by the following steps: 1/1531-LZA 701 6011 Uen K | 2016-03-01 89 Installing PBC 1. Tighten all the cables together with a plastic strap wire and also tie the bundle to the right side frame of the cabinet. 2. Tighten the cable inlet nut to form both a tight environmental seal as well as a strain relief. 8.8.14 Installing the Heater (Optional) In cold areas it may be necessary to install a heater. This section describes the process of installing the heater which is supplied by AC main power. The heater kit also includes a filter cover in the package. Note: Never install the filter cover in the PBC 05 Cabinet The heater is shown in Figure 70. It is a complete module. The heater is supplied by AC main power. A cable is factory installed from AC circuit breaker 6. The cable end for the heater should be found behind the MET. Follow the steps below for heater installation. 1. Make sure circuit breaker 6 is in ‘‘off’’ position. 2. Pull out the cable pair behind the MET that supplies the heater. 3. Remove the plastic cover over the heater terminal block. 4. Loosen the two screws on the frame, on which the heater will hang. 5. Install the heater module by sliding the heaters key holes over the loosened screws. 6. Tighten the screws to secure the heater in its position. 7. Connect the ground cable from the heater to the MET and secure by washer and nut. The ground cable is equipped with a cable lug and fits the M6 stud on the MET. 8. Connect the AC main power to the upper side of the terminal block. 9. Instal the plastic cover over the terminal block. 10. Secure the AC main power cable to the inside frame of the cabinet with a plastic wire strap. 11. Check that heater thermostat is set to 9 degrees Celsius. 90 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation P022439B Figure 70 8.8.15 Heater Connecting the AC Heater Cable External (Optional) If the cabinet is used together with external BBS 05 cabinets, it is possible to support them with a heater power cable. This section will describe how the cable to external heaters are installed. The cable is installed through the inlets position 3 or 4 at the bottom. Refer to figures Figure 28 and Table 14. Follow the procedure below: 1. Install the cable through the bottom inlet. 2. Make sure the heater circuit breaker 6 is in ‘‘off’’ position. 3. Remove the plastic cover of the Terminal Block AC. 4. Install the ground cable, which is pre installed in the heater Terminal Block AC, by connecting its cable lug to one of the 6 mm bolts in the MET. 5. Strip AC heater cable. 6. Loosen the Terminal Block AC screws on the topside. 7. Connect the AC cable on the topside in the same connector blocks as the incoming AC. 8. Tighten screws. 1/1531-LZA 701 6011 Uen K | 2016-03-01 91 Installing PBC 9. Install plastic cover on Terminal Block AC. 10. Secure AC cable to the frame inside cabinet by using plastic strap wire. 11. Tighten cable inlet at bottom of cabinet. 8.8.16 Installing the Rectifier Units The rectifier units, shown in Figure 71 for PBC 05 variant 1, and Figure 72 for PBC 05 variant 2, are not factory installed. Up to five rectifiers can be installed. The rectifiers are installed by sliding them into the designated slots. They are secured by closing the latch at the bottom and by tightening the screw in the bottom right corner. Only slight hand power is sufficient to secure them in their slots. Two different types of rectifiers are allowed in the system. The difference between them is the efficiency value. It is allowed to have both types installed in the system at the same time. Note: If not all five rectifiers are used, the empty slots must have a cover plate installed at the front. P022472A Figure 71 92 PBC 05 Variant 1 Rectifier 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation Ge4465A Figure 72 8.8.17 PBC 05 Variant 2 Rectifier Installing the Controller Unit The controller unit, SCU+ shown in Figure 73 or ACU+ shown in Figure 74, is not factory installed. The SCU+ or ACU+ is installed by sliding it into its designated slot. Controller Unit is secured by a latching arm at the bottom. When the controller unit is in place, the arm is closed to the bottom right corner and secured by a screw. Only slight hand power is sufficient to fasten the screw. ENT ESC P022441B Figure 73 SCU+ 1/1531-LZA 701 6011 Uen K | 2016-03-01 93 Installing PBC ENT ESC Ge4701A Figure 74 8.8.18 ACU+ Installing the Door Lock The cabinet has a factory installed door locking mechanism. The door has two locks. The key is a simple form of a triangular shape. Security can be improved by switching one or both locks to a proper lock with a key. Replacing the lock is done by unscrewing the nut and bolt in the door lock from the inside. The new lock is installed in the reverse operation with the nut and bolt. The process is shown in Figure 75. P022497A Figure 75 94 Installation of Door Locking Mechanism 1/1531-LZA 701 6011 Uen K | 2016-03-01 Installation 8.9 Checking and concluding the installation When the installation is completed it must be verified. Table 23 provides a checklist for the installation before power is switched on, and the start-up process is initialized. Table 23 Item Checklist Description yes no Cabinet. 1 Cabinet location as described in Customer Site Documentation. 2 Cabinet clean and undamaged. 3 Cabinet fastened as described in Customer Site Documentation. 4 Check that filters for incoming air in the door and for the outgoing air at the back, are properly in place and are clean. Main power. 5 Cabinet ground between MET and site ground. 6 Ground cable properly fastened and correctly tightened. 7 AC main power cable correctly stripped, terminated and fastened in cabinet AC main power terminal. 8 AC main power cable correctly stripped, terminated and fastened in external circuit breaker. 9 Check all bolts and nuts at the cabinet MET and cable shield terminals. Cabling 10 Check all cables to make sure no cable is damaged. 11 Check all cables terminated in the cabinet for correct stripping. 12 Check all terminal and fork screws to be properly tightened. 13 Check that all cable ends outside the cabinet are properly terminated. Unconnected cable ends need to have a proper cover or wrapped in isolation tape. 14 Check that all cables inside the cabinet are properly fastened to the inside frame, using plastic wire strapping. 15 Check that all cable glands in the bottom, with a cable, are properly tightened. 16 Check that all unused cable glands in the bottom are properly sealed. 1/1531-LZA 701 6011 Uen K | 2016-03-01 95 Installing PBC Item yes Description no Batteries. 17 Check that all batteries in the string are of the same type, and all that are installed in the same direction, facing outwards. 18 Check that the battery string has proper connection with 0 V and 048V. 19 Check that the middle inter-cell connector is not installed. 20 Check that all other inter-cell connectors are properly installed and tightened. 21 Make sure all circuit breakers are on the "off" position. 22 Check that all tools and installation material has been removed from inside the cabinet. 23 Check that all cables are marked according to Customer Site Documentation instructions. After the checklist is completed for the installation of equipment, perform the following concluding steps before power-up: 1. Replace the cover plate in front of the cables and fans at the top inside of the cabinet. This plate is installed with four screws at each corner. 2. Replace the cover plate for the multifunction unit by first installing the screws at the bottom hinges. The plate is then lifted up and secured at the top. 3. Replace the cabinet roof and secure it using washers and screws and optional locking plates as described in Section 7.1 on page 28. 4. Replace the doorstop. 5. Check that the door closes properly. 96 1/1531-LZA 701 6011 Uen K | 2016-03-01 Power Up and Verification 9 Power Up and Verification This section will provide guidelines and checklist for power up and verification of the PBC 05 system Table 24 Start-up preparation and Installation Test Item Action 1 Check that ALL circuit breakers are in ‘‘OFF ’’position. 2 Connect remaining battery interconnect strip between batteries 2 and 3. Result Comment Install the remaining pole protection covers on batteries 2 and 3. 3 Measure battery voltages and potential short circuits The voltages must correspond to values given by battery manufacturer. Nominal value for a battery string is in the range of 48 -51V. Resistance between battery pole - and cabinet chassis should high (> 50 Ohm) Resistance between battery pole + and cabinet chassis should be zero 4 Check incoming main power voltage Rectifiers are designed for nominal voltage of 200-250 V AC with 50/60 Hz. Voltage tolerances are between 85 to 300 VAC. Start up 1/1531-LZA 701 6011 Uen K | 2016-03-01 97 Installing PBC Table 24 Item Start-up preparation and Installation Test Action Result Switch on the main power supply to the cabinet The green optical indicator on the controller will start emitting light. Switch on the circuit breaker to rectifiers. The rectifier fan starts. Comment If the LVD contactors were off, they will now operate. Alarms will be issued and this will be displayed by a red optical indicator on the controllers as well as "Alarm" in the LCD window. Check the DC voltage in the Controller display Voltage must correspond to controller default setting, or programmed value. If temperature compensated charging is activated the value may differ +- 2 V from set value. 98 Switch on the circuit breaker to the battery string, and check battery voltage. The battery voltage increases and reach system voltage. This may take hours depending on battery charge level. Connect all other batteries the same way as above. The alarm Batt Fuse Alarm will cease. Switch on the distribution circuit breakers The loads get power. Push the door locking connectors, to simulate all doors are closed. All alarms cease in the controller. Check all optical indicators of the system Only green optical indicators must emit a light. The alarms cease in the controller. 1/1531-LZA 701 6011 Uen K | 2016-03-01 Performing Concluding Routines 10 Performing Concluding Routines Before leaving the site, perform the following procedure: 1. Check the parameter settings. 2. Clean the site and remove objects such as wrapping paper and cable clippings. 3. Dispose of waste in accordance with local regulations. 4. Fill in the verification checklist in the Customer Site Documentation. 5. Report any faults in accordance with local requirements. 6. Hand over the Customer Site Documentation to the person responsible for the site. 7. Lock all doors and gates to the site. Ericsson strongly recommends that installers pay particular attention to the environment when cleaning the site after RBS installation, in particular, recycle all waste that can be recycled and sort the rest so that it can be disposed in accordance with local regulations. Use the checklist in Table 25 to recycle and sort waste after the procedure in this instruction are completed. Table 25 Recycling and Sorting Waste Recycle or Sort as Item Metals Nuts bolts, washers, and screws YES N/A Pieces of cable with high metallic content Waste metal from cable ladders Paper Paper Plastics Bubble plastic Cable insulation from crimping, brazing, or welding Cable tie clippings Foam Packing chips Pieces of cable with low metallic content Polystyrene Wood 1/1531-LZA 701 6011 Uen K | 2016-03-01 Wood 99 Installing PBC Recycle or Sort as Item YES N/A Notes: 100 1/1531-LZA 701 6011 Uen K | 2016-03-01 Glossary Glossary BBS Battery Backup System DC Direct Current ESC Ericsson Site Controller EPP ESC Patch Panel ESD Electrostatic Discharge IB2 Interface Board LAN Local Area Network MET Main Earthing Terminal NC Normally Closed PBC Power and Battery Cabinet RBS Radio Base System RRU Radio Remote Unit SCU Standard Controller Unit SPD Surge Protecting Device 1/1531-LZA 701 6011 Uen K | 2016-03-01 101 Installing PBC 102 1/1531-LZA 701 6011 Uen K | 2016-03-01 Reference List Reference List The following documents are related to this product installation guideline: Safety [1] Personal Health and Safety Information, 124 46-2885 [2] System Safety Information, 124 46-2886 Site [3] Grounding Guidelines for RBS Sites, 23/1551-LZA 701 6009 [4] Customer Site Documentation [5] Battery Guidelines , 1/154 43-LZA 701 6009 [6] Installing Stackable Kit, 12/1531-LZA 701 6011 Product specific documents [7] Installing BBS, BBS 05, 3/1531-LZA 701 6009 [8] PBC Description, PBC 05, 1/1551-LZA 701 6009 1/1531-LZA 701 6011 Uen K | 2016-03-01 103