Journal of Petroleum Science and Engineering 201 (2021) 108407 Contents lists available at ScienceDirect Journal of Petroleum Science and Engineering journal homepage: http://www.elsevier.com/locate/petrol PERT based emergency disposal technique for fracture failure of deepwater drilling riser Yuanjiang Chang a, *, Yajie Jiang a, Changshuai Zhang a, Anti Xue a, Bin Chen b, Weiguo Zhang b, Liangbin Xu c, Xiuquan Liu a, Yongguo Dai d a Centre for Offshore Engineering and Safety Technology (COEST), China University of Petroleum (East China), Qingdao, China Shenzhen Branch of China National Offshore Oil Corporation, Shenzhen, China Research Institute of China National Offshore Oil Corporation, Beijing, China d Jiangsu Shuguang Oil Tools Co.,Ltd, Taizhou, China b c A R T I C L E I N F O A B S T R A C T Keywords: Emergency disposal PERT Deepwater drilling riser Fracture failure Completion probability Deepwater drilling risers are the crucial connections of subsea wellhead and floating drilling platform, and its fracture failure would lead to disastrous consequences. However, few efforts have been devoted to studying the way to efficiently and safely conduct the operation of emergency disposal for drilling riser fracture accident rescue. In this paper, program evaluation and review technique (PERT) was employed to quantitatively design the emergency disposal operation procedure of deepwater drilling riser fracture failure. The PERT model of emergency control operation for riser fracture accident were developed respectively to reflect the sequential logical relationships of each emergency disposal operation activity. Subsequently, the time parameters of operation activity for the PERT model were calculated according to the working time of each operation activity and expected completion time of the whole operation. Finally, the critical path and total duration of the emergency control operation for riser fracture accident were determined respectively, and some relevant opti­ mization measures drawn from the results were presented to further ensure the completion of emergency disposal of riser fracture accident on schedule during drilling operations. 1. Introduction The deepwater drilling riser system is an important device for con­ necting floating drilling platform with the subsea wellhead, and the fracture failure of the drilling riser is still one of the most dangerous and costly accidents in the offshore oil industry, as shown in Fig. 1 (Holand and Skalle, 2001; Per, 2014; Xu et al., 2013; Chang et al., 2018). The primary functions of the drilling riser system include isolating seawater, circulating drilling fluid, supporting the choke and kill (C/K) lines, guiding the drilling tools, and compensating for the heave motion of the drilling platform (Liu et al., 2013). However, the drilling riser system is subjected to many complex dynamic loads, which significantly affect the safety of the drilling riser and may lead to the severe drilling riser fracture accident. On May 21, 2003, a drilling riser fracture occurred when the drillship Discoverer Enterprise started pulling the drill string from the bottom of the well hole in a BP development well in 6015 ft of water in the Gulf of Mexico, as shown in Fig. 2 (Kirton et al., 2004). The drilling riser fracture accident had an extremely serious impact on the safety of marine drilling operations, which caused the grave losses to the lives and property, and subsequent accident disposal also took a long time and caused long downtime (Chang et al., 2019a; Kofiani et al., 2011). Currently, many scholars have conducted analysis of mechanical behavior, safe operation, dynamic response of deepwater drilling risers (Khakzad et al., 2013; Mao et al., 2019; Meng et al., 2018a, 2020). Be­ sides, risk analysis regarding the deepwater drilling risers have also been performed (Nie et al., 2019). In the case of broken riser failure or in extreme weather, the riser must be quickly disconnected from below the LMRP to avoid damage to the riser or well structure (Lang et al., 2009). Emergency disposal technology is an important tool to take corre­ sponding emergency measures and develop disposal strategies to com­ plete the emergency disposal project as soon as possible (Wei et al., 2015). In recent years, many studies have contributed to emergency disposal technology (Bruce et al., 2002; Wei, 2017; Qu and Hu, 2013). Norrington et al. (2008) established Bayesian network model to solve the reliability problem of maritime emergency force dispatching and * Corresponding author. E-mail address: changyj@upc.edu.cn (Y. Chang). https://doi.org/10.1016/j.petrol.2021.108407 Received 1 December 2020; Received in revised form 11 January 2021; Accepted 12 January 2021 Available online 23 January 2021 0920-4105/© 2021 Elsevier B.V. All rights reserved. Y. Chang et al. Journal of Petroleum Science and Engineering 201 (2021) 108407 achieved good simulation results. Pang et al. (2017) analyzed the rela­ tionship between maritime emergency rescue forces and assessment indicators, and built a rescue force assessment model, which effectively improved the efficiency of maritime rescue. Meng et al. (2012) pre­ sented the principle, working process, applicable conditions, design ideas and maturity of each deep water blowout emergency technology, as well as the research focus of each emergency technology. Wang et al. (2019) established the multi-objective optimization model of actual arrival supplies and time under the conditions of insufficient supply and sufficient supply to maximize the use of time and reduce supplies. Li et al. (2019) analyzed the dispatch procedure of the emergency supplies and proposed a joint dispatch model for offshore oil spill accidents. However, studies for emergency disposal for drilling riser fracture ac­ cident rescue can be found sporadically in literatures. PERT is a widely used method for measuring and controlling activity progress in project. As a result of the attributes of PERT that it can deal with the uncertainty of the operation activity time in the process of project, some issues like project environment, the uncertain time of the activities in the process of project implementation and uncertain factors of the project itself can be solved (Fazar, 1959). Thus, PERT is gradually applied to the calculation of project completion time, offshore engi­ neering construction, marine emergency rescue (Bates and Griffis, 2012; Per, 2014). Li et al. (2019) combined with the PERT and job safety analysis, presented a risk assessment system for deepwater drilling operation. Wu et al. (2015) proposed the project duration risk evalua­ tion method based on PERT under the influence of multi-factors, and analyzed the independent impact and portfolio impact of risk factors on the project duration. Meng et al. (2019) used PERT to quantitatively design the operation procedure of capping stack in Deepwater Horizon blowout accident, ensuring that the whole operation was completed as scheduled. Meng et al. (2018b) applied PERT to study the design of the operation process and the mechanical model of working scenarios of the LMRP cap system. The risk analysis of riser failure in deepwater drilling has been published (Chang et al., 2019b), which developed a model to identify the hazards that may cause drilling riser fracture and to calculate dy­ namic failure probabilities of drilling riser fracture and failure proba­ bilities of consequences. The purpose of this paper is to make a further study on the previous content, that is, the analysis of emergency disposal after the accident. It is aimed at developing a PERT model for emergency disposal of deepwater drilling riser fracture accident, which can be used to quantitatively design the emergency disposal operation procedure and determine the crucial path and total duration for emergency disposal of drilling riser fracture accident. On this basis, optimization measures were put forward to ensure that each process is completed as soon as possible within the required time, to improve the completion probability of accident emergency disposal, and to formulate the optimal emergency plan. The rest of the paper is structured as follows: Section 2 briefly introduced PERT technique. In Section 3, the emergency disposal methodology framework for fracture accident of drilling riser is pro­ posed. The PERT model of emergency control operation for riser fracture accident and completion probability of accident emergency control operation within time limit are presented in Section 4. Finally, the present work is summarized in Section 5. Fig. 1. Deepwater drilling riser system. 2. Program evaluation and review technique 2.1. PERT modeling process The process of PERT network modeling is to decompose the project into several more detailed operation activities, and design the network according to the sequence of operation logic of each operation activity to form the PERT network diagram. Then the time parameters of relevant operation activities are calculated to determine the crucial path and total duration of the operation based on the determined PERT network Fig. 2. Drilling riser after fracture. 2 Y. Chang et al. Journal of Petroleum Science and Engineering 201 (2021) 108407 model. Finally, by coordinating the time, human power and material resources consumption of the relevant operation activities on the crucial path, the operation time is shortened as much as possible to ensure that the entire project is completed on schedule. The operation flow chart of PERT is shown in Fig. 3. 2.2. PERT model basics Fig. 4. Example of PERT network. The PERT model is a network which uses directed lines with arrows to connect the operation activities based on the sequence relationship of operation activities. Fig. 4 shows an example of the PERT network model. PERT network chart is comprised of vertices (i.e., numbered circles, also called events) and edges (i.e., solid and dotted arrows). The numbered circles represent milestones (i.e., starting/finishing of activ­ ities). The solid arrows imply activities with corresponding estimated durations. The dashed arrows indicate dummy activities. They serve as pre-conditions to pointing milestones. For example, “2” and “3” in cir­ cles stand for the starting and finishing of activity “B”. “B 3” indicates that the estimated duration of activity “B” is 3 h. The dashed arrow between the numbered circles “3” and “5” represents that the activity “F” can only start after the completion of the activities “B” and “E”. A route starting at the numbered circles “1” and ending at “8” is called path, and the path with the longest total operation time is called the crucial path of the PERT network chart, and the activities on the crucial path are called the crucial activity. { { tE (1) = 0 { } tE (j) = max tE (i) + t(i,j) (j = 2, …, n) (1) tL ((n) ) = tE (n) ( ( ) } ( ) i = n − 1, …, 1 tL i = min tL j − t(i,j) (2) Where tE(1) and tE(n) represent the earliest start time of the total start event and total finish event, respectively. tL(n) represents the latest finish time of the total finish event and t(i,j) implies the activity duration time. (2) Time parameters of activity: Each activity in the PERT network has six time parameters: 2.3. The time parameters calculation of PERT model In PERT, several characteristic variables are defined to clarify the logical relationships and estimated time of sub-activities (Frederick and Gerald, 2006; Meng et al., 2018b; Winston and Goldberg, 2004): (1) Time parameters of event: Each event in the PERT network has two time parameters: the earliest start time and the latest finish time of the event, which can be expressed as: tE(j) and tL(i). tES (i, j) = tE (i) (3) tEF (i, j) = tE (i) + t(i,j) tEF (i, j) = tES (i, j) + t(i,j) (4) tLF (i, j) = tL (j) (5) tLS (i, j) = tL (i) − t(i,j) tLS (i, j) = tLF (i, j) − t(i,j) (6) Fig. 3. The operation flow chart of PERT. 3 Y. Chang et al. Journal of Petroleum Science and Engineering 201 (2021) 108407 R(i, j) = tLS (i, j) − tES (i, j) R(i, j) = tLF (i, j) − tEF (i, j) (7) r(i, j) = tE (j) − tES (i, j) − t(i,j) r(i, j) = tE (j) − tEF (i, j) (8) where k is the last activity, Tk is the total project time, which follows the Gaussian distribution. Tc(k) is the expectation of the earliest finish time for the last activity. σ2Tc(k) is the variance of the total activity completion time. 3. Proposed emergency disposal framework for drilling riser fracture accident where tES(i,j) and tEF(i,j) stand for the earliest activity start and finish time, respectively, tLF(i,j) and tLS(i,j) represent the latest allowable ac­ tivity finish and start time, respectively, R(i,j) indicates the total activity slack, which measures the excess time available to complete a project, r (i,j) represents the activity free slack, with positive values indicating that the task is ahead of schedule, negative values implying that the activity is behind the schedule and with zero values revealing that the activity is on time. Based on the expected and variance time of activities, the probability of the project for meeting the scheduled date (i.e., the deadline) can be obtained. They are defined as (Meng et al., 2018b, 2019; Winston and Goldberg, 2004): Tij = a + 4b + c 6 (9) σ 2i,j = (c − a)2 6 (10) Since time is a key factor during the emergency rescue process, it is helpful to quantitatively design the emergency response procedure. Considering the continuity of accident evolution process of fracture failure and the necessity of emergency disposal of accident, the proposed methodology framework shown in Fig. 5 involved the following five main steps. 1) Collecting necessary information. In this step, the necessary infor­ mation of the deepwater drilling riser fracture accident is collected, including data information at all stages, empirical knowledge from research paper and the tacit knowledge from domain experts, which should have been collected first in order to provide a basis for emergency response. 2) Model development. The purpose of this stage is to develop a definitive PERT model after an accident. It includes two aspects, i.e. determination of logical relationship, and duration time. Consider the logical relationships and duration of the related activities and integrate them into a PERT network model according to the corre­ sponding rules. 3) Model analysis. Calculate the element parameters according to the above model. The total activity slack and the activity free slack are calculated by PERT model. According to the above calculation time where Tij is the expected time of the activity (i, j), a is the optimistic time, b is the most likely time, and c is the pessimistic time. It is assumed that Tij = b, that is, a + c = 2b. σ 2i,jis the variance of time. The probability of a project for meeting scheduled date Tdk is: ) ( ∫ Tdk ( ( ) ) Tdk − Tc (k) N Tc k , σ2Tc(k) dt = Φ (11) P(Tk ≤ Tdk ) = − ∞ σTc (k) Fig. 5. Methodology framework for emergency disposal of drilling riser fracture accident. 4 Y. Chang et al. Journal of Petroleum Science and Engineering 201 (2021) 108407 to determine the critical path, get the total project time. Based on the relevant time parameters, the duration and variance of a process on the critical path are calculated to obtain the total expectation and variance of the emergency response and completion operation, and finally the probability of completion of the corresponding operation process within the specified time is calculated, which provide time basis for the subsequent optimization scheme. 4) Propose the optimization to make the critical path complete on time and improve the completion probability. The calculation results and conclusions of the above steps can provide reference for the deter­ mination of the emergency plan, and on this basis, update the key route, select the optimal scheme, shorten the construction period, and improve the completion probability of accident emergency control operation within time limit to reduce the severity and con­ sequences of riser fracture failure. 4. Case study 4.1. Analysis of emergency control operation of riser fracture accident Fig. 7. Riser joint leans against the BOP adjacent to control lines. This section takes the drilling riser fracture accident of the Drilling ship Discoverer Enterprise in the Gulf of Mexico on May 21, 2003 as an example and conducts PERT emergency control operation research on riser rupture accident. The drilling riser fracture accident scenario is shown as follows: On May 21, 2003, a fracture accident of drilling riser occurred during the drilling operation of dynamic positioning drilling ship at the water depth of 1875m in the Gulf of Mexico. The riser rupture caused a powerful riser recoil on the top tension provided by the tensioner system. The riser recoil damaged the hull, equipment in the recoil path, and further fractured the drilling riser. Subsequently, the remotely operated Remotely Operated Vehicle (ROV) was deployed and it was found that the drilling riser broke at an underwater depth of 975.36 m and was suspended from the drilling ship. Then the second fracture was then found at the 1860m ROV, which was located on the upper part of the LMRP at the top of the BOP. Both the riser and drill pipe were broken. Riser-joint number 1 was resting against the BOP close to the control lines that operate the stack (Fig. 6) (Kirton et al., 2004). In addition, about 580 m of risers were still connected and scattered around the center of the well, either buried in mud or lying on the seabed and on the wellhead of the abandoned development well, and the risers also rested on the control line of the blowout preventer’s shut­ down stack, threatening wellhead safety at any time, as shown in Fig. 7 (Kirton et al., 2004). Besides, 275 m risers still stood vertically on the seabed around the broken drill pipe. Drilling fluid spilled from multiple locations and 2450 barrels of synthetic based drilling fluid was released. The primary task after the accident is to carry out the emergency control of riser fracture accident and to prevent it from developing in a more unfavorable direction. Therefore, in order to efficiently and timely complete the riser fracture accident emergency control operation target, using the PERT analysis to determine a series of emergency control operation process, through the reasonable process adjustment, resource allocation, accident emergency control in the shortest possible time to achieve, to control the development of accident control, and ensure the accident loss minimized. In view of the occurrence of the deepwater drilling riser fracture accident, the first time for emergency control should be lowered to ROV to observe the fracture of the riser, and then the salvage vessels should be mobilized to salvage the drilling riser string that may cause two damage to the wellhead. Subsequently, because the underwater BOP has been damaged, the automatic shut in function cannot be realized at this time, in order to effectively control the underwater wellhead, it is necessary to further cut the LMRP part to level the wellhead and prepare for the installation of simple BOP group. The cutting operation is shown in Figs. 8 and 9 (Kirton et al., 2004). Finally, the installation and commissioning of the simple BOP group are completed, and the well shut-in operation is completed to control the riser fracture accident within the controllable range. Therefore, the emergency control opera­ tion of riser fracture accident mainly includes three main sub tasks: Fig. 6. Top of the Lower Marine Riser Package (LMRP) after riser fracture. Fig. 8. ROV circular saw cut away the riser auxiliary line. 5 Y. Chang et al. Journal of Petroleum Science and Engineering 201 (2021) 108407 Table 1 Completion time and relations of emergency control operation. Symbol Name of the activity Preceding activities Duration/ h Time can be shortened/ h Increased costs (ten thousand dollar/h) A Lower the ROV and observe the riser fracture Pull the bent drillpipe Reposition the original drilling vessel away from the primary drill center Mobilize rescue drilling vessel Position rescue drilling vessel to drilling center Install expansion packer at the fracture of suspended riser of original drilling vessel Inject water base mud into the suspended riser Recovery of suspended riser Lower circular saw cutting tool Cut LMRP upper riser auxiliary line Lower diamond cutting tool Cut riser above LMRP Separate LMRP from original BOP Retrieve LMRP Lower the simple BOP Stack Lower the accumulator and control system Debug the simple BOP group on the seabed Install a simple BOP Stack Determine shut-in strategy Close the simple BOP Stack – 9 4.5 6.5 A 12 6.5 7 B 5 3.5 7 – 15 2 9 C, D 6 2.5 7.5 C 11 2 7 F 4 2 9.5 G 10 2 9 E 8 1.5 7.5 I 2 – – I 8 1.5 8 J, K 5 0.5 7 L 2 – – M 48 8 10 E 15 3.5 7 E 12 2 7 O, P 5 1 5 M, Q 3 – – R 6 – – S 2 – – H 10 2 B C D Fig. 9. Diamond wire saw used to cut riser. E recovery of fractured drilling riser, leveling of accident wellhead, installation and closing of simple BOP, and then based on the specific subtasks, the more detailed operation process is divided. According to the accident report and marine emergency rescue experience, combined with the emergency response situation of the accident, the operation efficiency of the operators and the relevant equipment of the existing offshore platform, the completion time and operation relationship of the emergency control operation for the riser fracture accident can be ob­ tained, as shown in Table 1. F G 4.2. PERT chart for emergency control operation of riser fracture accident H 4.2.1. PERT of emergency control operation After the relationship between the emergency control operation procedure and the operation procedure of the riser fracture accident is determined, according to the drawing rules of the above PERT diagram and the relationship between the emergency control operation proced­ ure and the operation procedure of the riser fracture accident in Table 1, the PERT diagram of the emergency control operation of the riser frac­ ture accident can be drawn as shown in Fig. 10. I J K L 4.2.2. Operation time parameters After the PERT diagram of emergency control operation of riser fracture accident is determined, the parameters of emergency control operation time of riser fracture accident can be calculated according to the planned completion time of operation procedure given in Table 1 and the relevant formulas in Section 2.3. Let tES(1,2) = tES(1,8) = 0. It is assumed that all work should be finished within 96 h, namely, tLF(7,20) = tLF(14,20) = tLF(19,20) = 96. The calculation process of the PERT network is shown in Table 2. M N O P 4.3. Emergency control operation design for fracture accident of drilling riser Q 4.3.1. Critical path of accident emergency control operations Because the total time difference of the working procedures with codes A, B, C, E, I, K, L, M and N is negative, and the route composed of them takes the most time, the critical route for emergency control of riser fracture accident is A-B-C-E-I-K-L-M-N, as shown in Fig. 11. The sum of the working time on the critical path is duration. Its duration is 103 h, which is more than the supposed 96 h, and the time of the critical path needs to be shortened. It is recommended to fulfill the emergency operation on time by mobilizing rescue drilling vessel, pulling out the bent drill pipe, shortening the time of lowering drilling riser cutting tool, and recovering LMRP. R S T U 8 (continued on next page) 6 Y. Chang et al. Journal of Petroleum Science and Engineering 201 (2021) 108407 In addition, the emergency control operation design of riser fracture accident will enter the field implementation stage after four steps: PERT diagram drawing, time parameter calculation, critical route determi­ nation and operation completion probability calculation. Due to the harsh marine operating environment and sudden accidents, emergency control on-site operations often need to be adjusted in time according to feedback. If there is a need to adjust the operation during the on-site operation, it is necessary to re-adjust the design of the emergency con­ trol operation, otherwise the whole emergency control operation will be completed in turn until the end of the accident emergency control activity. Table 1 (continued ) Symbol Name of the activity Preceding activities Duration/ h Time can be shortened/ h Increased costs (ten thousand dollar/h) Salvage the rest of the riser string scattered on the sea bed 4.3.2. Probability of completion of accident emergency control operation By using the PERT diagram to design the emergency control opera­ tion flow of the riser fracture accident, the critical path of the emergency control operation flow of the accident is obtained, and then the timely completion can be ensured by adjusting the duration of the operation process on the critical path. Therefore, determining the completion probability of emergency operations within the specified time limit is of great value for emergency planning and rescue decision-making. First of all, the expected duration Tii and variance σ 2i,j of a certain process on a critical path are calculated according to Eqs. (9) and (10). In order to simplify the calculation in the emergency control accident environment, it is assumed that t(i,j) is equal to the most probable time b, that is a+b = 2c. The expectation and variance of the completion time of critical path operation for emergency control of riser fracture accident are shown in Table 3. Then according to the total expectation and total variance of the completion time of the critical route, combined with Eq. (11), the completion probability of the emergency control operation of the riser fracture accident within the specified time limit Tdk is calculated. The earliest realization time of the whole emergency control oper­ ation (item 20) Tc (20) is the sum of the expected completion time of the critical path operation, which is equal to 103 h. When the prescribed time limit is 85–120 h respectively, the completion probability of emergency control operation of riser fracture accident in different specified periods can be obtained by Eq. (11), as shown in Table 4 and Fig. 12. With the increase of the prescribed time limit of the emergency control operation, the probability of completion of the operation in­ creases, on the contrary, it decreases, and the growth rate is the highest near the total duration of the critical path. The probability of completion of emergency control operation of riser fracture accident should be improved according to the suggestion of operation optimization, and the duration of operation process should be reduced within a certain range near the total length of critical path, which can reasonably reduce the probability of completion of emergency control operation, so as to improve the efficiency of emergency control. Table 2 Computational table of PERT for emergency control operation. Symbol Activity (i, j) t (i, j) t ES (i, j) t EF (i, j) t LS (i, j) t LF (i, j) R (i, j) F (i, j) A D B C F Dummy activity G H U E I O P J K Dummy activity L M Dummy activity N Dummy activity Q R S T (1, (1, (2, (3, (4, (4, 2) 8) 3) 4) 5) 8) 9 15 12 5 11 0 0 0 9 21 26 26 9 15 21 26 37 26 − 7 4 2 14 61 19 2 19 14 19 72 19 − 7 4 − 7 − 7 35 − 7 0 11 0 0 0 0 (5, 6) (6, 7) (7, 20) (8, 9) (9, 10) (9, 15) (9, 16) (10, 11) (10, 12) (11, 12) 4 10 10 6 8 15 12 2 8 0 37 41 51 26 32 32 32 40 40 42 41 51 61 32 40 47 44 42 48 42 72 76 86 19 25 65 68 39 33 41 76 86 96 25 33 80 80 41 41 41 35 35 35 − 7 − 7 33 36 − 1 − 7 − 1 0 0 35 0 0 0 3 0 0 6 (12, 13) (13, 14) (14, 17) 5 2 0 48 53 55 53 55 55 41 46 85 46 48 85 − 7 − 7 30 0 0 0 (14, 20) (15, 16) 48 0 55 47 103 47 48 80 96 80 − 7 33 − 7 0 (16, 17) (17, 18) (18, 19) (19, 20) 5 3 6 2 47 55 58 64 52 58 64 66 80 85 88 94 85 88 94 96 33 30 30 30 3 0 0 30 Fig. 10. PERT of emergency control operation in drilling riser fracture accident. 7 Y. Chang et al. Journal of Petroleum Science and Engineering 201 (2021) 108407 Fig. 11. Critical path of PERT for emergency control operation in drilling riser fracture accident. 4.4. Optimization of PERT network Table 3 Expectation and variance of critical path operation completion time. Symbol Activity (i, j) Estimated duration (a-b-c)/h Expected duration/h Variance A B C Dummy activity E I K L M N (1, 2) (2, 3) (3, 4) (4, 8) 6-9-12 7.5-12-16.5 3-5-7 0 9 12 5 0 1.0000 2.2500 0.4444 0 (8, 9) (9, 10) (10, 12) (12, 13) (13, 14) (14, 20) 4.5-6-7.5 5.5-8-10.5 5.5-8-10.5 3-5-7 1.5-2-2.5 35-48-61 6 8 8 5 2 48 0.2500 0.6944 0.6944 0.4444 0.0278 18.7778 4.4.1. New critical path The optimization of network plan refers to shortening the whole construction period through some measures. Usually shortening the construction period is to increase the cost, and the goal of optimization is to minimize the increase in cost. The sum of the working time on the critical path is the minimum time required to complete the whole project. Therefore, the activities on the critical path play a key role in the whole project. The critical path of emergency control operation is C – D – E − F, as is shown in Fig. 13. The activity with the minimum marginal cost is A [6.5], and the duration of the project needs to be shortened: Table 4 Completion probability of emergency control operation within time limit. Time limit Tdk/h 85 90 95 100 105 110 115 120 Completion probability P 0.0001 0.0039 0.0505 0.2709 0.6591 0.9236 0.9929 0.9997 Fig. 12. Completion probability of accident emergency control operation within time limit. 8 Y. Chang et al. Journal of Petroleum Science and Engineering 201 (2021) 108407 Fig. 13. New critical path of PERT. ⎧ ⎫ ⎧ ⎫ ⎨ the duration needs to be shortened ⎬ ⎨ 7 ⎬ Δt = min the activity can shortened at most = 4.5 ⎩ ⎭ ⎩ ⎭ the new critical path 4.5 Table 6. With the increase of the prescribed time limit of the emergency control operation, the probability of completion of the operation in­ creases, on the contrary, it decreases, and the growth rate is the highest near the total duration of the critical path. The completion probability before and after optimization is compared in Fig. 14. After the optimi­ zation of the operation process, the completion probability increases correspondingly in each specified time limit, especially near the con­ struction period, and the completion probability is greatly improved. In addition, the following measures can be taken to shorten the construction period. Check whether the time of each activity is reason­ able, and if it is too long, consider shortening it. Further subdivide the jobs on the critical path and adopt the method of multi-station or par­ allel operation. Allocate resources on non-critical paths to support op­ erations on critical paths. Redesign the workflow and change the PERT network structure diagram. Due to the harsh marine operating envi­ ronment and sudden accidents, emergency control on-site operations often need to be adjusted in time according to feedback. = 4.5h If activity time fail to meet the requirements of the construction period, the adjustment should be continued. After shortening activity A, the activity with the minimum marginal cost is B [7]. And after adjusting the network diagram, D is the critical activity on the new network diagram, as shown in Fig. 13, and the duration of the project needs to be shortened: ⎧ ⎫ ⎨ 2.5 ⎬ Δt = min 6.5 = 2.5h ⎩ ⎭ 5 The cumulative cost: 4.5 × 6.5 + 6.5 × 7 = 0.7475 million dollars. 4.4.2. Probability of completion The new critical path is obtained by adjusting the time of activities on the longest path in the PERT network. The expected duration Ti and variance σ2i,j of a certain process on the new critical path are calculated according to Eqs. (9) and (10). The expectation and variance of the completion time of new critical path operation for emergency control of riser fracture accident are shown in Table 5. Then according to the total expectation and total variance of the completion time of the critical path, combined with Eq. (11), the new completion probability of the emergency control operation of the riser fracture accident within the specified time limit Tdk’ is calculated. After path adjustment, the earliest realization time (item 20) is the sum of the expected completion time of the critical path operation, which is equal to 96 h. That is, the specified time. When the prescribed time limit is 85–120 h respectively, the new completion probability in different specified periods can be obtained by Eq. (11), as shown in 5. Summary and conclusions Based on the plan review technology, a novel PERT network is developed for emergency disposal technique for fracture failure of deepwater drilling riser. According to the logical relationship and duration of the process, the emergency disposal plan for the fracture failure of drilling riser is figured out, and the PERT network diagram is drawn to characterize the emergency disposal process of the accident. Further, calculate the probability that the emergency disposal plan will be completed within the specified time limit. It provides a reference for time optimization measures and emergency treatment of fracture failure accident of deepwater drilling riser. The present study indicates that the proposed model could be effi­ ciently applied to emergency disposal for fracture failure of drilling riser. It includes 21 sub-operation procedures, and the total duration of the key route is 103 h. The network shows that A (Lower the ROV and observe the riser fracture), B (Pull the bent drillpipe), C (Reposition the original drilling vessel away from the primary drill center), E (Position rescue drilling vessel to drilling center), I (Lower circular saw cutting tool), K (Lower diamond cutting tool), L (Cut riser above LMRP), M (Separate LMRP from original BOP) and N (Retrieve LMRP) are critical activities for the emergency disposal plan. Meanwhile, the correspond­ ing completion probability of accident emergency disposal is calculated when the construction period is 103 h and the prescribed time limit is 85–120 h, it can be found that the completion probability increases with the increase of the specified time, and the growth rate of completion probability is the largest near the total length of the critical path. According to the network diagram, combined with the activity cost, the duration of activities A, B, C is reduced, and the timescale is Table 5 Expectation and variance of new critical path operation completion time. Symbol Activity(i, j) Estimated duration (a-b-c)/h Expected duration/h Variance D Dummy activity E I K L M N (1, 8) (4, 8) 10-15-20 0 15 0 2.7778 0 (8, 9) (9, 10) (10, 12) (12, 13) (13, 14) (14, 20) 4.5-6-7.5 5.5-8-10.5 5.5-8-10.5 3-5-7 1.5-2-2.5 35-48-61 6 8 8 5 2 48 0.2500 0.6944 0.6944 0.4444 0.0278 18.7778 9 Y. Chang et al. Journal of Petroleum Science and Engineering 201 (2021) 108407 Table 6 New Completion probability of emergency control operation. Time limit Tdk’/h 85 90 95 100 105 110 115 120 Completion probability P′ 0.0119 0.1093 0.4168 0.7939 0.9678 0.9980 0.9999 0.9999 Fig. 14. Comparison of completion probability. References shortened to 96 h. Update the key roadmap to get new critical activities D (Mobilize rescue drilling vessel), E (Position rescue drilling vessel to drilling center), I (Lower circular saw cutting tool), K (Lower diamond cutting tool), L (Cut riser above LMRP), M (Separate LMRP from original BOP) and N (Retrieve LMRP). Besides, calculate the completion proba­ bility of accident emergency disposal after critical path update. Comparing the probability curve before and after time optimization, the completion probability at each time point after optimization is higher than that before, and the increase of completion probability between the total duration of the two critical paths is the most obvious. It could also be taken to shorten the excessively long duration of activities such as N (Retrieve LMRP) to improve the probability of completion of accident emergency disposal. The analysis results obtained from this study could be used to provide as the reference for emergency disposal plan after fracture failure of drilling riser. Bates, A., Griffis, F.H., 2012. Program Evaluation and Review Technique (PERT) in construction schedule risk assessment. China Urban Economy 3, 246–249. Chang, Y., Wu, X., Chen, G., et al., 2018. Comprehensive risk assessment of deepwater drilling riser using fuzzy Petri net model. Process Saf. Environ. Protect. 117, 483–497. Chang, Y., Li, J., Zhang, C., et al., 2019a. Dynamic risk assessment approach of riser recoil control failure during production test of marine natural gas hydrate. Energy Science and Engineering 7 (3), 1–15. Chang, Y., Zhang, C., Wu, X., et al., 2019b. A Bayesian Network model for risk analysis of deepwater drilling riser fracture failure. Ocean Eng. 181, 1–12. Frederick, S., Gerald, J., 2006. Introduction to Operations Research. Tsinghua University Press. Fazar, W., 1959. Program evaluation and review technique. The American Statian 13 (2), 646–669. Holand, P., Skalle, P., 2001. Deepwater kicks and BOP performance, unrestricted version. Sintef Industrial Management 17–30. Khakzad, N., Khan, F., Amyotte, P., 2013. Dynamic safety analysis of process systems by mapping bow-tie into Bayesian network. Process Saf. Environ. Protect. 91, 46–53. Kirton, B., Wulf, G., Henderson, B., 2004. Thunder horse drilling riser break-The road to recovery. In: SPE Annual Technical Conference and Exhibition. Society of Petroleum Engineers. Kofiani, K.N., Koutsolelos, E., Wierzbicki, T., 2011. Shear-generated fracture in predicting oil leak in accidents involving sinking platforms. In: International Offshore and Polar Engineering Conference. International Society of Offshore and Polar Engineers. Lang, D.W., Real, J., Lane, M., 2009. Recent developments in drilling riser disconnect and recoil analysis for deepwater applications. In: International Conference on Offshore Mechanics and Arctic Engineering. American Society of Mechanical Engineers. Liu, X., Chen, G., Chang, Y., et al., 2013. Analyses and countermeasures of deepwater drilling riser grounding accidents under typhoon conditions. Petrol. Explor. Dev. 40 (6), 791–795. Li, S., Chen, Y., Li, H., et al., 2019. Study on optimization of coordinated emergency supplies operation for large offshore oil spill accidents. Journal of Waterway and Harbor 40 (6), 735–741. Mao, L., Zeng, S., Liu, Q., 2019. Dynamic mechanical behavior analysis of deep water drilling riser under hard hang-off evacuation conditions. Ocean Eng. 183, 318–331. Meng, S., Chen, Y., Che, C., 2020. Coupling Effects of A deep-water drilling riser and the platform and the discharging fluid column in an emergency disconnect scenario. China Ocean Eng. 34 (1), 25–33. Meng, S., Song, S., Che, C., et al., 2018a. Internal flow effect on the parametric instability of deepwater drilling risers. Ocean Eng. 149, 305–312. Meng, H., Chen, G., Chang, Y., et al., 2012. Classification and discussion on the direction of emergency technology for deepwater blowout. Petroleum Drilling Techniques 40 (6), 27–32. CRediT author statement Yuanjiang Chang: Conceptualization, Methodology, Writing – review & editing; Yajie Jiang: Software, Writing – original draft; Changshuai Zhang: Visualization, Data curation; Anti Xue: Investigation, Resources; Bin Chen: Supervision, Data curation; Weiguo Zhang: Software, Vali­ dation; Liangbin Xu: Investigation, Resources; Xiuquan Liu: Project administration; Yongguo Dai: Investigation, Supervision. Declaration of competing interest The authors declare that they have no known competing financial interests or personal relationships that could have appeared to influence the work reported in this paper. Acknowledgement Authors gratefully acknowledge the financial support provided by National Natural Science Foundation of China (52071337) and Key Project of Natural Science Foundation of China (51890914). 10 Y. Chang et al. Journal of Petroleum Science and Engineering 201 (2021) 108407 Meng, H., Chen, G., Liu, X., 2019. A capping technique for emergency response in offshore blowout accidents. J. Loss Prev. Process. Ind. 62, 103925. Meng, H., Chen, G., Liu, X., et al., 2018b. An oil recovery technique for emergency response in deepwater blowout accidents. Saf. Sci. 113, 134–143. Nie, Z., Chang, Y., Liu, X., et al., 2019. A DBN-GO approach for success probability prediction of drilling riser emergency disconnect in deepwater. Ocean Eng. 180, 49–59. Norrington, L., Quigley, J., Russell, et al., 2008. Modelling the reliability of search and rescue operations with Bayesian Belief Networks. Reliab. Eng. Syst. Saf. 93, 940–949. Per, H., 2014. Reliability of Subsea BOP Systems for Deepwater Application. Phase II DW. Pang, H., Ma, Y., Mao, T., et al., 2017. Evaluation of maritime emergency rescue capability based on network analysis. IOP Conf. Ser. Earth Environ. Sci. 100, 012121. Qu, Y., Hu, W., 2013. Emergency disposal technology and method for leakage of liquefied natural gas (LNG) storage tank. Journal of Safety Science and Technology 9 (4), 99–103. Wang, Q., Liu, X., Yan, C., 2019. Emergency material scheduling at initial emergency response stage of marine oil spill accidents. J. Shanghai Marit. Univ. 40 (4), 27–32. Wei, H., Wang, R., Zhang, Y., et al., 2015. Anti-typhoon emergency technology of deepwater drilling in South China Sea. Oil Drilling & Production Technology 37 (1), 115–153. Wei, Z., 2017. Discussion on key technologies of emergency disposal of dangerous chemicals leakage accident. Guangzhou Chem. Ind. 45 (3), 173–175. Winston, W.L., Goldberg, J.B., 2004. Operations Research : Applications and Algorithms. Ernational Thomson Pub. Wu, F., Wang, X., Cheng, T., 2015. A project duration risk analysis and evaluation under multiple influencing factors based on PERT. Ind. Eng. J. 18 (6), 89–92. Xu, L., Zhou, J., Liu, Z., et al., 2013. Challenges and solutions for deepwater drilling in the South China Sea. In: Proceedings of Offshore Technology Conference. OTC, Houston, Texas, USA, p. 23964. 11