SAFETY AND HEALTH AUDIT PURPOSE Provide guidelines and tools for management and subcontractors to conduct job site safety audits. SCOPE This procedure applies in its entirety to all operations unless a variance is granted by the Safety Director. RESPONSIBILITIES The Project Manager and Superintendent have overall responsibility for establishing and ensuring compliance with this procedure. The field safety and health staff are responsible for implementing and/or monitoring activities associated with this procedure. All managers and supervisory personnel will enforce this procedure and ensure each employee follows it. GENERAL REQUIREMENTS Audit Schedule - Each construction executive, senior superintendent, superintendent, assistant superintendent, and safety manager is required to formally inspect her or his project weekly using the attached Safety and Health Audit Report format. Subcontractors – If applicable, a senior supervisor for each subcontractor should accompany the Safety Manger/Superintendent during the weekly audit of the subcontractor's work area. Project managers, senior project managers and project executives are required to do this documented audit monthly. Correcting Deficiencies - Any discovered unsafe condition or act should be corrected on the spot by the Foreperson or Superintendent responsible for the work. If the deficiency cannot be corrected on the spot and is not an imminent danger, then it must be corrected within three (3) days maximum. If an unsafe condition or act could result in an injury, the work should be stopped until the situation is resolved. All employees exposed to hazard should be removed and only those required to correct the problem allowed to remain – with appropriate protection for the circumstances. All unsafe conditions or acts discovered should be documented on the audit forms/checklists along with the corrective action taken to resolve them. The checklist is provided only as a guide. Auditing every item on the checklist every week or month is not the intention and is not required. Distribution Copies of the completed audits are to be filed with the project safety files and are submitted to [_______]. 1 TOPIC RATING DETAILS General Safety C= Compliant N=Non-Compliant N/A All required Posters, Paperwork, posted in a visible location, and up to date? Is the [COMPANY NAME] safety sign displayed? Are there any outstanding issues which have not been addressed? Have orientation forms been completed Has the Job Hazard Analysis (JHA) been updated for today? Last JHA update posted: Are Toolbox Talks being performed? Topic covered today? Employees wearing all required PPE (gloves, hiviz vests, glasses, hardhats, etc)? Signage & Barricades in place where required? Are employees wearing hearing protection when noise levels are in excess of 85 dBa? dBa Measurement during Visit: Sanitation C= Compliant N=Non-Compliant N/A Adequate supply of potable water? 1per 20 workers when fewer than 20 on site? 1 toilet and urinal per 40 workers when more than 20 on site? 1 toilet and urinal per 50 workers when more than 200 on site? Washing facilities provided? Clean-up & Housekeeping C= Compliant N=Non-Compliant N/A Re-Bar Caps in use where necessary? Are all worksites clean, sanitary, and orderly? Stairs clear and free of debris? Dumpster emptied regularly? Oily rags and combustible refuse stored in covered metal containers? Bins or Dumpsters located at suitable points around Jobsite? 2 Chemical Safety C= Compliant N=Non-Compliant N/A Have safety data sheets been updated for new products in inventory? Spot check (3): First Aid Center C= Compliant N=Non-Compliant N/A Is the eyewash station on the safety board and within the manufacturer’s expiration date? Is the first aid kit available and stocked? Fire Prevention & Protection C= Compliant N=Non-Compliant N/A Are hot work permits being filled out? Fire Extinguishers located throughout areas of work, and freely accessible? Fire Extinguishers fully charged, and recently certified? Fire Extinguishers located within reach where any hot-work is being performed and combustible storage areas? Masonry C= Compliant N=Non-Compliant N/A Is proper scaffolding provided? Are masonry saws properly equipped, and is dust protection provided? Is safe hoisting equipment used? Are limited-access zones established as required? Silica C= Compliant N=Non-Compliant N/A Silica Plan on site? Have Hazard Analyses been completed? Are OSHA Table-one controls being used? Equipment & Machinery C= Compliant N=Non-Compliant N/A Back-up Alarms working correctly? Adequate roll-over protection provided? Seatbelts installed and functional on all Equipment? Fuel stored in proper containers? 3 Power Tools C= Compliant N=Non-Compliant N/A Power Tools in good working order? Guards/Shields functional? Powder Actuated Tools in good condition Trenches, Excavations & Openings C= Compliant N=Non-Compliant N/A Trenches & Excavations are barricades as required? (Barricade 6ft from any open excavation) Controlled Access Zone when required? Protective systems in place as required (trench boxes, etc.) Air monitoring for all work areas that are considered confined spaces, or areas containing airborne contaminants? Have all openings, holes, etc been covered & marked as necessary? Adequate access/egress provided? (Within 75ft) Excavations adequately benched, with spoils away from sides? Cranes and Rigging C= Compliant N=Non-Compliant N/A Lifting Chains and Chokers Inspected, Tags Legible? Outriggers Extended, And Set On Firm Foundation Glass Intact Steel Erection C= Compliant N=Non-Compliant N/A Steel Erection? Floor Decked as required? Perimeter protection in place? Fall Protection in use where required? Welding & Cutting C= Compliant N=Non-Compliant N/A Cylinders stored properly? Hoses in good condition? Adequate shielding provided? Fire Blankets used where necessary? 4 Electrical C= Compliant N=Non-Compliant N/A Temp or Permanent Lighting adequate (meets OSHA standards, at a minimum)? Temp Lighting connections secure and covered? Electrical Cords in good condition? All tools & equipment powered via GFCI Protected circuits? All Panels, Boxes, etc secured and covered? Roofing C= Compliant N=Non-Compliant N/A Are all skylights/roof openings protected by covers or guardrails? Note: Most glass or plastic covers on skylights will not meet the structural requirements of a cover, check with manufacturer. To be safe, the installation of a proper cover or guardrail is recommended. Is there a warning line in place? Perimeter Protection in place? Is there a safety monitor in visual/verbal range of employees? Rooftop Operation Plans developed? Lifts C= Compliant N=Non-Compliant N/A Lift inspected/free of defects? Lift operated with all wheels in contact of ground? Access gate/opening closed during operation? Workers trained on use of lift? Floor of lift kept reasonably clean? Both feet on floor of lift? Stairways (Permanent or Temporary) C= Compliant N=Non-Compliant N/A Pans filled? Stairs free and clear of debris? Handrail/Guardrail in place? 5 Fall Protection C= Compliant N=Non-Compliant N/A Is perimeter protection in place where necessary? Personal fall arrest systems in use where required (all work over 6ft)? Are harnesses recently inspected? Are all lanyards, retractables, etc clearly marked with weight limits and other required info? Personal Fall Arrest anchor points adequate? Ladders C= Compliant N=Non-Compliant N/A Ladders tied-off? Extension Ladders - Ropes, pulley, etch in good condition? Frame Ladders – Free of defects? Ladders extended 3ft above all landings? All Ladders adequately rated for use? Ladders used correctly (not standing on top rung, leaning against walls, etch)? Non-conductive Ladders used for Electrical Work? Scaffolds C= Compliant N=Non-Compliant N/A Competent person? Adequate anchor points provided? Platform clean free of debris? Is a system square and level and plumb? Scaffold grade lumber being used? Platforms - Fully decked? Foundation /soil good no visible settling or wash out? Fall protection provided above 6’? Walk boards overlapping as required 6-12 inches Access provided no buck/brace climbing? Toe boards in place? Frames have plates leveling jacks 6 Action taken to correct deficiencies _____________________________________________________________________________ _____________________________________________________________________________ _____________________________________________________________________________ ____________________________________________________________________________ _____________________________________________________________________________ Injuries reported and investigated this week _____________________________________________________________________________ _____________________________________________________________________________ _____________________________________________________________________________ _____________________________________________________________________________ _____________________________________________________________________________ Special safety activities this week _____________________________________________________________________________ _____________________________________________________________________________ _____________________________________________________________________________ _____________________________________________________________________________ _____________________________________________________________________________ Signature: ___________________________________________________________________ Date: __________________ 7