CIBSE AM12: 2013 The Chartered Institution of Building Services Engineers 222 Balham High Road, London, SW12 9BS Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Combined heat and power for buildings Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 The rights of publication or translation are reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means without the prior permission of the Institution. © Second edition January 2013; The Chartered Institution of Building Services Engineers London Registered charity number 278104 ISBN 978-1-906846-30-5 This document is based on the best knowledge available at the time of publication. However no responsibility of any kind for any injury, death, loss, damage or delay however caused resulting from the use of these recommendations can be accepted by the Chartered Institution of Building Services Engineers, the authors or others involved in its publication. In adopting these recommendations for use each adopter by doing so agrees to accept full responsibility for any personal injury, death, loss, damage or delay arising out of or in connection with their use by or on behalf of such adopter irrespective of the cause or reason therefore and agrees to defend, indemnify and hold harmless the Chartered Institution of Building Services Engineers, the authors and others involved in their publication from any and all liability arising out of or in connection with such use as aforesaid and irrespective of any negligence on the part of those indemnified. Typesetting and layout by CIBSE Publications Printed in Great Britain by The Lavenham Press, Lavenham, Suffolk CO10 9RN. Cover illustration: The Energy Centre at the 2012 London Olympic Park (architects: John McAslan and Partners). The Energy Centre includes a gas-fired combined cooling, heating and power (CCHP) plant to capture the heat generated by electricity production. It also includes biomass-fired boilers to generate heat and deliver low carbon energy. Cooling is provided through a combination of electric, ammonia-based chillers and absorption chillers, which are driven by heat recovered from plant in the Energy Centre. (Photograph by Hufton+Crow; courtesy of John McAslan and Partners.) Note from the publisher This publication is primarily intended to provide guidance to those responsible for the design, installation, commissioning, operation and maintenance of building services. It is not intended to be exhaustive or definitive and it will be necessary for users of the guidance given to exercise their own professional judgement when deciding whether to abide by or depart from it. CIBSE Applications Manual AM12: Small-scale chp for buildings was first published in 1999. With the growing concerns over global warming and the recognition of the role that chp can play in delivering low carbon buildings this revised and updated edition has been produced. A number of new sections have been added including: —— a new chapter on district heating applications —— more information on assessing environmental benefits —— more detail on tri-generation and thermal storage. Principal author Paul Woods (AECOM) AM12 Steering Group The production of this publication has been greatly assisted by the work of the AM12 Steering Group. CIBSE are indebted to the following individuals and their organisations: Phil Jones (chair) Mark Anderson (Arup) Huw Blackwell (Hoare Lea) Lars Fabricius (SAV Systems) Tony Gollogly (PB Energy Solutions) Dr Julian Packer (Cogenco Ltd) Dr Robin Wiltshire (BRE) Reviewers Detailed reviews have been carried out by the following. The CIBSE is very grateful for their valuable contribution. Dr Jonathan Williams (BRE) Peter Pearson (Dalkia plc) Huw Blackwell (Hoare Lea) Dr Gregory Zdaniuk (Cofely GDF-Suez) Acknowledgements (third edition) CIBSE would like to acknowledge the valuable contributions provided by a wide range of individuals and organisations including the following: AECOM, Cofely District Energy Ltd, Combined Heat and Power Association (CHPA), Cogenco Ltd, Corporation of London, Dalkia plc, EC Power A/S, EnerG Combined Power Ltd, David Hague (Cogen Solutions Ltd), LowC Communities Ltd., SAV Systems, UK District Energy Association, University of East Anglia, Veolia Environmental Services (UK) plc. Editor Ken Butcher CIBSE Head of Knowledge Nicholas Peake Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Foreword to the third edition Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Contents 1 Introduction 1.1 The energy challenges 1.2 What is chp? 1.3 Why chp should be considered 1.4 Scope of AM12 1.5 Purpose of AM12 1 1 1 3 4 4 Part 1: Technologies, applications and regulations 2 CHP and energy centres (fossil fuel) 2.1 Spark-ignition gas engines (50 kWe to 10 MWe) 2.2 Mini or small-scale chp (<50 kWe) 2.3 Micro gas turbine chp 2.4 Individual dwelling chp (<2 kWe) 2.5 Larger-scale chp 2.6 Fuel cells 2.7 Combined cooling, heating and power (tri-generation) 3 Renewable energy and CHP 3.1 Biomass chp using combustion of solid biomass fuel 3.2 Biogas chp using gasification of solid biomass fuel 3.3 Liquid biofuel chp 3.4 Energy from waste 3.5 Biomethane injection 3.6 Integration of chp with renewable energy sources 3.7 Integration of chp with heat pumps 8 8 9 10 10 11 11 11 4 CHP for individual buildings 4.1 Introduction 4.2 Building heating, cooling and electrical demands 4.3 Fuel and electricity tariffs 4.4 Principles of chp sizing 4.5 Design of building heating systems to benefit chp operation 4.6 Building applications most suitable for chp 4.7 chp to improve security of electricity supply 12 12 12 13 13 16 17 17 5 Application of CHP to supply district heating 5.1 Principles of district heating 5.2 Typical applications of dh and chp 5.3 Selling electricity and private wire networks 5.4 Efficient design of dh systems to benefit chp operation 5.5 Use of thermal storage 5.6 District cooling 5.7 Large-scale district heating 18 18 19 19 19 21 22 22 6 Primary energy savings and environmental impact of chp 6.1 Primary energy savings 6.2 CO2 savings and impact of emission factors 6.3 CO2 benefits from tri-generation 6.4 Other emissions to air 6.5 Noise 6.6 Other environmental impacts 22 22 24 26 26 27 27 7 Legislation and regulations and impact on CHP viability 7.1 Planning 7.2 Building Regulations 7.3 Climate Change Act 7.4 Carbon trading: CRC Energy Efficiency Scheme and the EU Emissions Trading Scheme 7.5 CHP Quality Assurance Programme 7.6 Other financial mechanisms 7.7 Parallel operation with dno system 5 5 6 6 6 7 7 8 28 28 28 28 28 28 29 29 8 Feasibility studies 8.1 Introduction 8.2 Data gathering of energy demands and system temperatures 8.3 chp performance, heat recovery options 8.4 Optimum sizing of chp 8.5 Thermal storage 8.6 Tri-generation (cchp) 8.7 Integration with other low carbon technologies 8.8 Typical capital and maintenance costs and efficiencies for gas-engine chp 8.9 Economic appraisal 8.10 Financing options 8.11 Feasibility report 30 30 30 33 33 33 34 34 34 9 39 39 39 40 41 43 43 44 44 44 45 45 46 47 47 48 49 Design 9.1 9.2 9.3 9.4 9.5 9.6 9.7 9.8 9.9 9.10 9.11 9.12 9.13 9.14 9.15 9.16 Allocation of responsibilities Health and safety aspects Energy balance for chp and heat recovery systems System design: interfaces with heating circuit System design: absorption chillers System design: electrical interface Fuel system Combustion exhaust system Combustion and ventilation air systems Control systems Maintenance facilities Control of noise and vibration Fire and gas detection and protection Regulatory compliance and approvals Specification: typical contents for chp package specification Design of district heating 34 36 38 10 Procurement Tendering 10.1 10.2 Assessment of tenders 51 51 52 11 Installation, commissioning and testing 11.1 Installation 11.2 Component testing, off-site testing 11.3 Commissioning 11.4 Client acceptance testing 53 53 53 54 55 12 Operation and maintenance 12.1 Operation 12.2 Operation and maintenance manuals 12.3 Maintenance and servicing 55 55 56 57 Part 3: Lessons learned 13 Lessons learned 13.1 Feasibility studies 13.2 Economic appraisals 13.3 Integration of chp into heating systems 13.4 District heating 13.5 Environmental impacts 13.6 Procurement 13.7 Detailed design and installation 13.8 Commissioning 13.9 Operation 13.10 Tri-generation and absorption chillers 59 59 59 60 60 60 60 61 61 61 61 References 62 Appendices Appendix A1: Conversion factors Appendix A2: Glossary of terms 64 64 64 Index 67 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 1 Combined heat and power for buildings 1 Introduction of the future low carbon energy strategies will increase the costs of energy supply. Key points: —— Three energy challenges are climate change, security of supply and competitive prices. —— CHP can assist in meeting these challenges. —— primary energy savings of 23–30% are possible. 1.1 The energy challenges The UK faces three major challenges in its supply and use of energy (see Figure 1.1). First, the risks of climate change are now accepted and the need to reduce cumulative CO2 emissions has become a fundamental part of the energy policies of all countries with the Copenhagen Accord committing us to joint action. In the UK the Climate Change Act 2008 has set a legally binding requirement for an 80% reduction in CO2 emissions from 1990 levels by 2050. Secondly, the UK has benefited from indigenous energy resources of coal, oil and natural gas for many years. We are now facing a new situation where we will be increasingly importing fossil fuels from a declining resource against a background of rising worldwide energy demand. At the same time a significant proportion of power stations need to be replaced as older coal-fired and nuclear stations need to be closed. Energy security is becoming a more important issue with concerns over the potential for gas supply interruption from unstable regimes, higher world prices for gas and the potential for power outages if investment is not forthcoming. The third challenge is to maintain competitive energy prices to enable both industry and society to thrive. Many CO2 reduction In responding to these three challenges, energy strategies also need to minimise the impact on the wider environment, whether this is related to air quality in cities, visual impact in the countryside or at sea, or the safe disposal of waste products from energy systems. Energy use in buildings is a major contributor to CO2 emissions and the supply of heat for space heating and hot water is associated with approximately 16% of total UK CO2 emissions (CCC, 2010). The role and responsibility of the building services engineer in meeting these challenges is therefore very significant. Combined heat and power (chp) has been recognised as a technology that can reduce CO2 emissions. It can also be cost-effective to implement in many applications. The greater efficiency of fuel utilisation will also help improve energy security. chp thus has the potential to help meet all of the three challenges outlined above. The energy efficiency benefits obtained with a chp system will still be needed even if the fuels used in the future are low carbon, as such fuels will be in short supply and will also have environmental impacts. Maximising the efficiency of utilisation of renewable fuel will remain an important part of the case for chp in the future. 1.2 What is CHP? Our conventional energy supply system is based on the separate production of electricity in power stations and heat from boilers. (also known as co­generation) is the name applied to energy systems that produce both useful heat and electricity in a single process. chp As a result of the second law of thermodynamics, power stations reject to atmosphere about 50% to 60% of the thermal energy used. In a chp plant a large proportion of this heat is captured for use in heating buildings or for process heat. Energy prices • Fuel poverty • Competitive economy Figure 1.1 The energy challenges Security of supply • Heat reliability • Imported gas • Power blackouts Electrical energy is also lost in the transmission and distribution of power to buildings and this energy can also be saved if the chp generates electricity more locally. Although the production of electricity by chp is less efficient than that which can be achieved from central power stations, the use of the heat that would otherwise be rejected leads to a net saving in primary energy. Combined heat and power for buildings A comparison between the separate production of heat and power and chp is shown in Figure 1.2. The primary energy saving is calculated as: —— Fuel used by chp = 100 units (35 units of electricity and 45 units of heat produced) —— Conventional electricity at 40% efficiency would require 35/0.4 units of fuel = 88 units —— Conventional heat at 80% efficiency would require 45/0.80 units of fuel = 56 units —— Total fuel required for conventional supply = 88 + 56 = 144 units So the potential saving in primary energy is about 30%. Improvements in efficiency of boilers and power stations are taking place. However, even if the boiler efficiency is assumed to be 85% and the conventional electricity supply efficiency improves to 45%, the primary energy saving would still be 23%. chp efficiencies are also improving. An important question is whether chp represents a more efficient use of natural gas. In this case it is the efficiency of gas power stations rather than the grid average that should be used; currently this efficiency is about 43% (gross calorific value basis) delivered to customers. A more detailed discussion of primary energy saving and CO2 emissions is given in section 6. Types of CHP 1.2.1 There are a number of types of chp and these are discussed in section 2 below. The most common type for building applications, where relatively low grade heat is required, is based on a sparkignition reciprocating gas engine directly driving a generator to produce electrical power. Heat is typically recovered from the engine jacket, the oil cooler and the exhaust gases and, if the heat required is at low enough temperature, from the intercooler. This type of chp was developed in the 1980s and is supplied as a fully packaged unit of which several thousand have been sold in the UK. Gross calorific value and net calorific value Efficiencies of power plant are conventionally expressed using the net calorific value (ncv) of the fuel. This is the energy in the fuel released when the combustion products are cooled but excludes energy released from the condensation of water vapour (latent heat). The gross calorific value (gcv) includes the energy released from condensation and is thus a higher value. As energy is sold on the basis of gcv it is important to convert the energy efficiencies to gcv basis before carrying out any analysis. A chp unit typically operates in parallel with the public supply with additional electricity imported as required. The heat output is commonly supplemented with boiler plant at times of peak demand. A thermal store can be included to smooth the heat demand, reduce the need for peak boiler use and maximise electricity production at times of higher elec­tricity prices. The boilers and public electricity supply connections are normally sized to meet the peak demands of the building when the chp is not operating, as the chp unit requires regular maintenance. The chp units are normally maintained by the supplier under a long-term maintenance contract with remote monitoring of the operation allowing faults to be identified and visits scheduled to maximise availability. It is important that other energy savings measures are fully considered before the viability of a chp scheme is evaluated. Failure to do so may result in the benefit of the chp scheme being undermined by the later application of other energy efficiency measures. It is usually more important to avoid oversizing chp, rather than undersizing, unlike most building services plant. When comparing district heating supplied by chp with conventional systems the energy inputs to the district heating network for both heat losses and pumping energy also need to be considered. In summary, the higher primary energy efficiency obtained with chp delivers the energy cost savings required to finance the chp installation and results in lower CO2 emissions. 1.2.2 Applications Losses 11 45 Heat demand 45 35 Power demand 35 Boiler 56 CHP 144 100 20 Power 88 station 53 Losses Figure 1.2 The energy efficiency of chp (reproduced from GPG388 (Carbon Trust, 2004) by permission of the Carbon Trust) A wide range of buildings can be suitable for chp systems. The economic return on the investment is determined partly by the operating hours, so buildings that have a yearround demand for heat will generally be the most econom­ ically attractive. These buildings include residential blocks, hospitals, hotels and swimming pools. For other buildings, chp systems will still be able to operate effectively and reduce costs and emissions but the payback period will be longer due to fewer operating hours in the year. Combining the demands of buildings with different heat demand profiles through a district heating (dh) network will improve the operating hours of the chp but will of course incur additional cost for the dh network. For large campustype sites, e.g. a university, the higher efficiencies and lower costs associated with larger-scale chp often mean that a lack of summer heat demand is less of a barrier. The chp is simply operated for 8–9 months of the year. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 2 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Introduction 1.2.3 3 Tri-generation The term tri-generation is often used to describe a chp system that also supplies heat to an absorption or adsorption chiller so that heat, electricity and cooling are produced. If the chp is efficient enough so that the heat has a low carbon content then there can be additional CO2 benefits. As discussed in section 6.1 the effective CO2 content of chp heat is very dependent on the source of the electricity that will be displaced and thus the benefit of using heat driven chillers is expected to fall over time, especially when there is no unabated coal-fired generation operating in summer. However this change might be offset by future improvements in the coefficient of performance (cop) of heat driven chillers. The additional running hours of the chp will generate additional cost savings for the site that are needed to help finance the additional cost of the absorption or adsorption chiller. 1.3 Why CHP should be considered chp is typically considered because of the following drivers: —— lower operating costs —— reduced CO2 emissions —— greater security of supply for electricity —— government policy and incentives —— replacement of boiler capacity —— efficient use of renewable fuels. These are discussed in turn below. 1.3.1 Lower operating costs Lower operating costs are achieved with a chp unit as the energy purchased for a site changes as follows: —— More gas is purchased as both electricity and heat is produced from the chp. —— Less electricity is purchased as the electricity on-site. chp generates power stations (e.g. natural gas) then a CO2 reduction of up to 30% would be obtained for the energy produced by the chp unit in accordance with Figure 1.1 above. For a given site, the chp unit will not be perfectly matched to the heat and electricity demands and boilers and the grid supply will be needed to supplement its output. The CO2 reduction for a typical site is therefore normally lower than 30%. However, there is a secondary benefit from installing gasfired chp in the UK at present, which arises from displacing coal-fired power generation that has about double the CO2 emissions of gas-fired power stations. If the chp plant uses renewable fuels then further emissions savings are possible allowing a site to achieve zero carbon in operation. The methodology for calculating CO2 reductions is discussed further in section 6.2. 1.3.3 Security of electricity supply The third reason for considering chp is to enhance the security of electricity supply at the site. It is possible to design chp systems to operate in ‘island’ mode, independent of the public supply, and in some cases this will provide an additional advantage for chp. However, chp units are not equivalent to standby power generation as typically provided by diesel generators, and they are less able to accept sudden load changes. They will require regular maintenance so will not always be available to operate and may be sized to meet the heat load rather than the electrical demand. A specific design to improve security of supply would therefore need to consider a larger number of smaller units to maximise availability, a higher total capacity or a load shedding system to enable the site load to be controlled to a level that the chp units can supply. Finally, if there are times when the chp units are scheduled to be turned off (e.g. at night) the start-up times need to be considered as gas engines will take longer to start and reach full-load than diesel-powered standby generators. The chp units can only be started when supporting systems are also in operation, e.g. ventilation and circulation pumps, heat rejection capacity and gas fuel supply. Maintenance costs for the chp unit need to be taken into account. chp suppliers offer finance schemes that can deliver savings without capital investment. 1.3.4 The efficiency of the boilers may change as a result of their operation only in peak periods and the energy prices charged for electricity and gas may also change as a result of the different demand profiles. As a recognition of the environmental benefits and energy saving potential of chp, the UK Government has encouraged chp through various mechanisms. These incentives are discussed further in section 7 but are subject to change and it will be necessary to check the latest position on the relevant website. 1.3.2 Reduced CO2 emissions systems reduce CO2 emissions as a result of their improved energy efficiency. The CO2 emissions at the site will increase as more fuel is consumed but this is more than offset by the reduced CO2 emissions at power stations as less electricity needs to be produced for the national grid supply. The net reduction in CO2 emissions is thus dependent on the CO2 emissions factors for the fuel for the chp and boilers and for the electricity displaced by the chp. If the same fuel emissions factor is assumed for chp and chp Government policy and financial incentives Local government planning policies are increasingly requiring new buildings to adopt low and zero carbon technologies beyond that required by the Building Regulations for England and Wales*. In many cases chp systems are an important component of the policy and the interconnection of buildings to form district heating networks, which then make chp systems more viable, is also a key part of energy planning policies in some cities. * Requirements may differ in Scotland and Northern Ireland. Combined heat and power for buildings Boiler replacement and district heating —— is often considered in the context of replacement of boilers. In some sites this leads to a review of whether the heating system should be centralised or decentralised, i.e. whether district heating should be retained, abandoned or introduced. chp can be supplied at a range of sizes but is generally more efficient at a larger scale, and its introduc­ tion at a time when boilers are being replaced provides an opportunity to design the plant room to incorporate chp. Part 2 (sections 8 to 12) provides guidance on each aspect of implementation of a typical chp project from feasibility study through design, specifications, procurement, commissioning and operation and maintenance. —— Part 3 (section 13) provides lessons learned from practical applications. 1.3.5 chp 1.3.6 CHP and renewable energy There are a number of ways in which renewable fuels can be used in conjunction with chp. The renewable fuels are generally derived from biomass and as such are limited by available land area. It is important therefore to maximise the availability of this limited renewable fuel by using it in the most efficient manner through chp. 1.4 Scope of AM12 1.4.1 Scale A number of Government regulations impact on chp within the UK and section 7 provides an overview of the legislation current at the time of publication. Regulations change frequently therefore it is essential that the reader checks the current status of Government regulations or seeks advice from the Combined Heat and Power Association (CHPA) (http://www.chpa.co.uk). Appendices provide conversion factors and a glossary of terms. 1.4.4 Exclusions Although district heating and cooling systems are included in section 5, this is mainly in relation to the sizing and operation of the chp system. More detailed guidance is available on district heating design in other publications. systems can range in size from 1 kW to hundreds of MW of electrical generation. AM12 is intended to provide information directed towards chp used to supply buildings and so the emphasis is on smaller packaged chp units of 1 MWe or less, typically using reciprocating engines. A section on district heating has been included, which describes some of the differences that might arise for largerscale chp systems. The scope of the manual also refers to, but excludes detail of: chp —— prediction of energy usage patterns —— building energy management systems (bems) design —— energy audits, and monitoring and targeting (m&t) methods Smaller-scale chp systems below 50 kWe tend to be preengineered as complete packages with controls and in some cases thermal stores. For these types of systems, information should be sought from suppliers as some of the information in this manual may be less relevant. —— other energy saving measures —— other means of providing heat and/or power —— uninterruptible power supplies (ups) and standby generation. 1.4.2 A number of these are covered in other CIBSE publications, see references. Applications This manual is intended to provide advice for designers of systems in both new and existing buildings of all types and scales. It is intended to assist the designer of the building services for these buildings and does not attempt to provide advice on how to design the chp unit itself. The emphasis is on how chp can best be integrated into a building’s engineered systems and how to evaluate the operating cost and environmental benefits. In some cases, the building heating system will need to be modified to maximise the chp benefits and the manual also provides information on the nature of these desirable changes. chp 1.4.3 Organisation of the manual Following this introduction, the remainder of AM12 is divided into three parts: —— Part 1 (sections 2 to 7) deals with chp technologies and their application 1.5 Purpose of AM12 This manual is intended to be read by anyone concerned with energy matters in buildings: building services engineers, energy efficiency officers, energy managers, consultants and designers. The aim of the manual is to give the reader sufficient background information and direction to promote, install and manage successful chp installations to supply both new and existing buildings. The manual aims to incorporate experience gained and to describe best practice so as to enable new installations to benefit from the lessons of the past. Some sections of the manual may also be relevant to architects, planners and energy policy makers seeking to deliver a lower carbon future. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 4 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations 5 Part 1: Technologies, applications and regulations 2 CHP and energy centres (fossil fuel) Key points: units less than 1 MWe output are normally supplied as a packaged unit within an acoustic enclosure. The enclosure requires a ventilation system to provide combustion air and to provide cooling to remove heat lost from the engine. In some cases the heat in the ventilation air can be used directly or indirectly but in most cases it is dissipated. chp —— Spark-ignition gas-engines are the predominant prime-mover technology for CHP supplying buildings. —— CHP can be classified as micro (domestic scale <2 kWe), mini or small-scale (<50 kWe) and above 50 kWe. —— Above about 200 kWe, most engines are turbocharged, which improves their electrical efficiency. —— Heat can be recovered from the engine jacket, oil cooler and exhaust gases. Additional heat can be recovered at lower temperature by a condensing exhaust heat exchanger, from the intercooler heat rejection and from the ventilation air of the acoustic enclosure. chp systems can be characterised by both capacity and type. The main characteristic of chp systems is the type of prime- mover and common systems, based on fossil fuels, are described below. Section 3 discusses chp systems that use renewable fuels. 2.1 It is normal practice for the heat recovery system to be a closed circuit as part of the chp package with a single interface to the building heating system via a plate heat exchanger. Spark-ignition gas engines (50 kWe to 10 MWe) The most common type of chp is based on spark-ignition gas engines. These are either purpose-designed for stationary applications or derived from engines used in vehicles. The size ranges from 50 kWe to around 10 MWe, with a typical life of 10–15 years. Gas engines are available in naturally aspirated and turbocharged types. Turbocharging is normally available in engines larger than 200 kWe and typically improves electrical efficiency from around 31% to 33% (gcv). The main components of a chp unit based on spark-ignition gas engine technology are: —— prime mover: an engine to drive the generator —— fuel system: providing gas at appropriate pressure —— generator: to produce electricity, which is fed into the building’s power distribution system —— heat recovery system: to recover usable heat from the engine —— cooling system: to dissipate heat rejected from the engine that cannot be used —— combustion and ventilation air systems: to supply fresh air to, and carry radiated and convected lost heat away from, the engine —— exhaust gas silencer and chimney: to safely dissipate exhaust gases without causing a nuisance —— control system: to maintain safe and efficient operation, to synchronise with the public supply and to provide a remote monitoring facility —— enclosure: to achieve physical and environmental protection for the engine and operators, and to reduce noise. The main components are shown in Figure 2.1. Engine exhaust gases In naturally aspirated engines, air is drawn into the engine at atmospheric pressure without pre-compression. The engine geometry and ambient conditions limit the air–fuel mixture and, in high ambient temperature conditions, engine performance is likely to be reduced. In turbocharged engines, air for combustion (commonly called ‘charge air’) is received via a compressor, driven by a turbine in the exhaust gas stream. The resulting increased air mass flow rate enables the engine power output to be increased for a given engine frame size. A disadvantage of this arrangement is that compression of the charge air increases its temperature, and to avoid undesirable combustion effects the air must be cooled in an intercooler or after-cooler. The heat liberated from the intercooler may be recovered to the building heating systems (if these are designed to operate at a sufficiently low temperature) or rejected to atmosphere. In conditions of high ambient temperature the plant rating may be reduced depending on the design and capacity of the intercooler cooling system. Engine exhaust Gas or oil Control panel Engine Generator Hot water supply Exhaust heat exchanger Engine heat exchanger Cool return water Figure 2.1 Principal components of a gas-engine chp unit (reproduced from GPG388 (Carbon Trust, 2004) by permission of the Carbon Trust) Combined heat and power for buildings There are two main types of generator: synchronous and asynchronous. Synchronous generators rotate at a governed fixed speed, which is usually an integer multiple of the supply system frequency, e.g. 1000, 1500 or 3000 r/min for a 50 Hz system. The generator maintains its own frequency standard and can thus continue to run at the desired frequency when isolated from the public supply. Synchronisation with the main supply requires special control and instrumentation equipment to match frequency, phase and voltage on connection. Asynchronous generators do not have the ability to maintain a frequency standard but rely on the mains supply frequency to monitor and maintain the desired generated frequency. This means that operation in isolation as a standby mode is not possible. The majority of chp schemes will use synchronous gener­ ators. Generators are typically low voltage up to 1 MWe and are normally high voltage above 3 MWe. Between 1 MWe and 3 MWe either are possible, depending on the relative costs of generator, transformer and switchgear, and maintenance costs. Figure 2.2 illustrates a typical gas engine acoustic enclosure doors open. 2.2 chp unit with Mini or small-scale CHP (<50 kWe) In recent years a new generation of small-scale chp systems (<50 kWe) have been introduced. These have been designed specifically to provide longer running hours between servicing (10 000 hours is typical) and a sophisticated control system. Much of this manual is directly applicable to this type of chp. However, as the units tend to be standardised, advice should be sought from the suppliers at an early stage of design. Typical applications will be in smaller commercial and residential buildings. Figures 2.3 and 2.4 show examples of this system type. 2.3 Micro gas turbine CHP This type of chp is based around small-scale gas turbines, which have been introduced in the last 10 years. Typically such turbines produce an electrical output of about 100 kWe. Micro-turbines differ from larger-scale gas turbines by running at high speed and a dc generator is used together with an inverter. Their main benefit is that maintenance intervals are much longer than for recipro­ cating engines, so availability is higher and maintenance costs lower. However electrical efficiency is generally lower than the equivalent sized spark-ignition gas engine chp. 2.4 Individual dwelling CHP (< 2 kWe) systems suitable for use in individual dwellings have been the subject of considerable research and development over the last 10 years. They offer the potential for obtaining the benefits of chp without the need for, or cost of, district heating and may offer a replacement for the domestic gas boiler. Most systems include an auxiliary burner to enable peak heating demands to be met. chp There are two principal types: Figure 2.2 A typical gas engine chp unit with acoustic enclosure doors open (photo courtesy of EnerG Combined Power Ltd) Figure 2.3 Mini-chp system (photo courtesy of SAV Systems and EC Power) —— Stirling engine: this is a reciprocating engine but with the heat energy provided through an external heat exchanger. Its electrical efficiency is generally much lower than the larger spark-ignition reciprocating engines, however it can be well suited to the small outputs of an individual dwelling chp system. It will typically have a 1 kWe electricity output. —— Fuel cell: these utilise a chemical reaction to generate electricity, rather than a combustion process. The fuel cell offers the potential for a higher electrical efficiency than other types of chp and hence lower CO2 emissions and cost savings. The high electrical efficiency also means that Figure 2.4 Mini-chp system (photo courtesy of Baxi-SenerTec UK) Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 6 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations operation will be viable even with only partial heat recovery, and running hours can be extended to improve operational savings. As a result of the high efficiency the power output will be typically 2 kW, sufficient to provide heating for the dwelling. The output of fuel cells can be modulated to meet variable energy demands, which is important in individual dwellings where demands are highly variable. The main challenges to development include reducing initial cost, prolonging the life of the fuel cell stack and reducing the size of the system. Fuel cells are considered in more detail in section 2.6. At present, domestic chp is still in the early stages of development and more experience is needed to establish performance and the environmental and cost benefits. The Carbon Trust has conducted early field trials of a number of different types of units (Carbon Trust, 2011). The main market is expected to be in larger detached houses, as in higher density housing district heating and larger-scale chp is likely to be preferred on efficiency or cost grounds. 2.5 2.5.1 Larger-scale CHP Gas turbines Gas turbines are available in the range 500 kWe to over 200 MWe, although the choice of models below 1000 kWe is very limited. They are most commonly used in industrial chp applications of 2.5 MWe and above, where the high grade heat in the exhaust can be utilised to generate process steam, or in conjunction with a waste heat boiler and a steam turbine to generate additional electrical power (known as a combined cycle gas turbine). The electrical efficiency of gas turbines in open cycle (i.e. without a steam turbine) is lower than reciprocating engines for gas turbines of 500 to 1500 kWe. Larger turbines have higher electrical efficiencies but still do not compare well with spark-ignition gas engines when in open cycle mode below about 5 MWe. In combined cycle applications the electrical efficiency can be over 50% but the complexity of this type of plant means that the scale required is typically over 50 MWe. Gas turbines require higher pressure gas than sparkignition gas engines, so a gas compressor is required. The electricity used for the compressor is significant and so sites with access to gas mains at higher pressure will be more effective. When considering chp, gas turbines have the advantage of producing most of the available heat as high temperature exhaust gas, which may be used to provide high temperature hot water or steam. The firing of additional fuel into the exhaust (supplementary or auxiliary firing) may be used to produce additional heat at higher combustion efficiency than conventional boilers. There are several examples of gas turbine chp systems supplying buildings, especially in hospitals or universities where a steam distribution system exists. Some of these use steam to supply absorption chillers. 7 2.5.2 Dual-fuel reciprocating engines These engines use the compression-ignition principle as used most commonly with diesel engines in vehicles. As gas has been cheaper than oil for some time engines have been developed where gas provides the main fuel but a small amount of oil is also injected so that ignition takes place when the cylinder is compressed. The advantage is a higher electrical efficiency at the expense of a small additional fuel cost and higher emissions of NOx, SOx and particulates as a result of the use of oil. An additional advantage is that it can also run on oil alone should that prove financially beneficial (e.g. if an inter­ ruptible gas contract is used). The oil used may also be derived from renewable sources. There are a few examples of this type of chp engine but mainly for larger district heating schemes (e.g. Citigen, in the City of London, and Southampton). On the continent, larger-scale spark-ignition engines are more common than dual-fuel engines. 2.6 Fuel cells A potential alternative to reciprocating engines and gas turbines is the fuel cell. This is an electrochemical device comprising an anode and a cathode separated by an electrolyte. Fuel (hydrogen) is supplied continuously to the anode and oxygen to the cathode. The chemical reaction creates a voltage difference. Each cell generates about 1 volt so a number of cells are combined to form a cell stack. As hydrogen is not readily available, a reforming stage is required (either external or internal to the fuel cell) to convert a fuel such as natural gas to provide the hydrogenrich fuel source. Fuel cells have been developed both for stationary electricity generation and also for vehicular applications. Typical sizes currently available or in development as chp units range from domestic scale 1 kWe units to 500 kWe. There are a number of different types of fuel cell, which are characterised by the electrolyte used. The most common types for chp applications are: —— Proton exchange membrane fuel cell (pemfc): This operates at a low temperature of 80 °C and requires higher grade hydrogen. Also known as solid polymer fuel cells (spfc). —— Phosphoric acid fuel cell (pafc): This type is closest to being generally commercially available. It is less sensitive to fuel quality. —— Molten carbonate fuel cell (mcfc): The electrolyte is typically a mix of lithium carbonate and potassium carbonate. This is a high temperature fuel cell operating at 650 °C, which allows internal reformation of the fuel. —— Solid oxide fuel cell (sofc): The electrolyte is a solid ceramic and the operating temperature is 1000 °C. This type has the potential for high electrical efficiencies. It is also the basis for a domestic scale fuel cell chp presently under development. —— Alkaline fuel cells (afc): Fuel cells of this type use hydrogen as a fuel and were originally developed for space exploration applications. These are Combined heat and power for buildings unlikely to be used unless a hydrogen economy is developed. —— Direct methanol fuel cells (dmfc): These have been developed for vehicular applications. Fuel cells offer the potential for higher electrical efficiencies than the equivalent sized reciprocating engines with figures of 35% to 55% (gcv basis) quoted. This would result in lower CO2 emissions. In addition, as the combustion process is avoided emissions of nitrogen oxides are much lower. Although a few demonstration projects exist in the UK, fuel cell chp has a much higher capital cost than conventional gas-engines and the life expected from the fuel stack is also limited to around 40 000 hours. Fuel cells should be considered for applications where continuous running can be expected as this will maximise the stack life. chiller utilisation is maximised and frequent start/stops are avoided. The absorption chiller is normally sized so that its heat requirement does not exceed the chp heat output as otherwise boiler heat would be used for the absorption chiller, which is less efficient than using electric chillers. If there is no other heat demand in the summer cooling period then the absorption chiller heat requirement will need to match the chp heat output closely to avoid heat rejection or part-load operation. Absorption and adsorption chillers are normally only considered for cooling loads greater than 250 kW. The environmental benefits from tri-generation are discussed in section 6.3. 3 Renewable energy and CHP Fuel cells generate dc electricity and so an inverter is normally used to produce ac for parallel operation with the grid supply. Key points: —— The temperature of heat available is typically 80 °C for pemcs but higher temperatures are available from the sofc and mcfc types. Spark-ignition gas-engines are the predominant type of CHP for buildings —— CHP is a concept that can be applied to any thermal electricity generation process. —— CHP using renewable fuels: solid biomass, liquid biofuels and biogas are feasible and there are a wide range of technologies in use and under development. —— Further information is provided in BSRIA BG 9/2003: Fuel cell technology: The scope for building services applications (BSRIA, 2003). If there is good heat utilisation over the year, CHP should result in a more efficient use of renewable biofuel which will always be a limited and valuable resource . —— Combining CHP and solar thermal is normally not appropriate. 2.7 —— CHP and photovoltaics or wind are generally compatible. —— Gas-fired CHP and a biomass boiler may be integrated but can be difficult to control automatically, especially for small-scale systems. —— CHP and heat pumps compete for the same base heat load but could be complementary in the future as marginal electricity grid emissions fall and heat pumps become more viable. Further technical developments include the use of hybrid systems combining a high temperature fuel cell (mcfc and sofc) with a micro-turbine to improve power efficiencies further. Combined cooling, heating and power (tri-generation) A chp unit can be seen as a source of low cost and low carbon heat. This heat is normally used to displace boilers but can also be used as heat source for an absorption or adsorption chiller. There are two basic types of absorption chiller: single effect and double effect. Single effect chillers can use low temperature hot water and have cops of around 0.7 and the double effect chillers use higher temperature hot water, steam or exhaust gases from the chp and cops are around 1.3. Units are also available which can use multiple heat sources. The cops of such units are much less than those of vapour compression chillers so it is important that the carbon content of the heat from the chp is low and that the cost of heat production is low. The lower cops also mean that about twice as much heat needs to be rejected from the condenser circuit. The adsorption chiller uses a silica gel as the refrigerant, which is alternately heated and cooled. This type of chiller offers lower maintenance costs and higher efficiencies when operating with lower temperature heat sources. It would normally be the case that the absorption chiller is sized to supply the base cooling load with vapour compres­ sion chillers used for peak periods so that the chp/absorption 3.1 Biomass CHP using combustion of solid biomass fuel The renewable fuel most likely to be considered for chp at present is wood chips or wood pellets. These have found a growing market for small boilers for heating. Wood pellets are compacted small wood chips and sawdust. They have a higher price than wood chips but have a lower moisture content and hence a higher calorific value. They are also denser and easier to transport and store. The twin benefits of using biomass as a fuel for chp is that the energy is produced from a renewable source and also the energy in the fuel is used in the most efficient way. This is important in the context of biomass as the amount of biomass is limited in any given area and there will always be competition for the land area needed for food production Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 8 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations or amenity space. The main drawback of biomass chp is the much higher capital cost for the chp plant compared to gasfired plant, especially at a small scale and limited operational experience. There are a number of types of chp that use conventional combustion of the fuel. These are described below. 3.1.1 Steam turbines Conventional steam turbine technology can be used for biomass chp with an electrical output of greater than 2 MWe but are most suitable for systems over 10 MWe. It offers robust, well proven technology, with a very good part-load performance. However, at a small-scale, lower electrical efficiencies (20–25%) along with high capital, operating and maintenance costs are some of the disadvantages. This option is best considered in the context of a large district heating system. The steam turbine can be designed either as an extraction condensing unit or a backpressure turbine. The former will be of benefit if there are significant times of the year when the heat demand is lower than the chp output and there are financial benefits from maintaining electrical output. 3.1.2 Air turbine Systems of this type use a micro-turbine supplied with air heated from the combustion of the biomass. Additional heat recovery is obtained from the exhaust gases rejected by the heat exchanger, which heats the air for the turbine. The benefit of this approach is that all of the components are well proven. The disadvantage is that the micro-turbine is relatively inefficient as the air temperature that can be supplied is limited. The electrical efficiency is around 20%, thermal efficiency about 50%. 3.1.3 Organic Rankine cycle (ORC) Biomass chp systems based on orc technology are now commercially available from a few manufacturers in Europe but there is limited experience in the UK. These systems use an organic working fluid with a lower boiling point than water/steam, such as freon or an organic solvent. This allows the system to work more efficiently at lower temperatures and pressures, and at smaller scales more suited to biomass fuel. Electrical outputs are typically in the range 200 kWe to 2.0 MWe, with thermal to electrical output typically around 5:1. The main drawback is the relatively high capital cost. 3.1.4 9 in a modified gas engine to produce electricity and heat. It is important to have a uniform product entering the gasifier because carry-over of tars in the syngas can be a problem. However the newer generation of gasifiers appear to have made progress in overcoming this problem. Such systems are supplied as fully integrated packaged units with the gasifier and chp system running from the same control system which can then be integrated into the building’s bms. Gasification brings higher electrical efficiencies due to gas engine technology having advantages over steam based systems. There is limited experience of wood gasifiers at a small scale but there are now a few applications in the UK of larger schemes of 1 to 5 MWe capacity. In Europe there are several wood gasifiers of less than 1 MW capacity that have been running successfully for some years, and this technology is now starting to become available in the UK. Gasifiers are most reliable in continuous operation so proper consideration should be given to sizing and the use of thermal stores to modulate the heat use in building schemes. Capital costs remain high compared to bio-liquid chp, but due to the relatively lower cost of solid biomass against bio-liquid fuel, the returns in both operation and investment can be attractive, especially where Government incentives apply. The use of solid biomass is generally seen as a more sustainable solution as woodland is often on land that is unsuitable for large-scale agriculture thus avoiding com­ petition with food production. However the sustainability of any biomass resource needs to be carefully considered in the light of competing uses and scale of demand (CCC, 2011). The UK Government is currently promoting the sustainable management of woodlands through various grant schemes, leading to more fuel sources becoming available. Gasification of biomass and use in chp can provide a more efficient use of biomass in terms of CO2 saved per unit of biomass fuel provided the heat produced is well utilised. Wood chip size and moisture content are likely to be the most important aspects of uniformity but gasifier dimensions and internal design are also critical design elements. Stirling engine The Stirling engine operates with an external heat source so the products of combustion are separated from the working fluid. Some small-scale biomass chp systems are now commercially available. The electrical efficiency is relatively low so a building with a high heat demand relative to electrical demand would be preferred. 3.2 Biogas CHP using gasification of solid biomass fuel Gasification systems turn biomass material into a fuel known as synthesis gas or syngas. This gas is then burned Figure 3.1 Biomass gasifier used for chp (courtesy of the University of East Anglia) Combined heat and power for buildings Tar problems can be minimised by operating at the appropriate temperatures, which will vary depending on the type of plant. approved by the Office of the Gas and Electricity Markets (Ofgem). The liquid fuels currently available for chp are: The production of biochar from the gasifier/pyrolysis plant is potentially beneficial to the economics and overall sustainability of the process. —— 100% biodiesel —— pure vegetable oil, e.g. rape seed oil 3.3 —— bioethanol —— generator fuel derived from waste oils from the food industry. Liquid biofuel CHP Liquid biofuels (also known as ‘bioliquids’) are likely to be well suited to chp engine applications as some may have been developed for vehicle applications. As a result, higher electrical efficiencies can be achieved compared to other renewable chp technologies. The main concerns with this technology are as follows: —— —— The land taken for the production of the feedstock for bioliquids may compete with food crops. However, in many circumstances bioliquids are produced from crops that are grown within the practice of sustainable agriculture as part of a standard crop rotation. Where there is a change of land use to grow crops for fuel the different CO2 impacts of the change of land use need to be considered. —— There may be a more beneficial application for the fuel than use in chp for buildings. —— There is limited long-term operating experience with engines operating on these fuels. —— The price of the fuel is relatively high. —— The maintenance costs are higher. —— NOx emissions are higher than for natural gas engines, but can be mitigated through using higher flue stacks. —— The energy used for processing some fuels can be high increasing the carbon content. —— There is a need to store the fuel on-site and in some cases keep its temperature above a minimum level. Set against these disadvantages is the potential to achieve higher chp electrical efficiency and also to receive financial incentives such as Renewable Obligation Certificates (ROCs). To receive ROCs the chp installation needs to be Figure 3.2 Rapeseed oil energy centre (courtesy of LowC Communities Ltd) Information on the CO2 content (and other greenhouse gases) of some bioliquids used for transport applications can be obtained from the Department for Environment, Food and Rural Affairs (DEFRA, 2011). However it is recommended that fuel-specific factors are obtained from other sources or from suppliers, as knowledge in this area is still developing. 3.4 Energy from waste 3.4.1 Large-scale combustion and steam turbines The most established waste-to-energy technology is mass combustion (incineration) to raise steam for a steam turbine generator. Typically these are large-scale plants handling over 100 000 tonnes p.a. of waste. The steam turbine can be used as a chp plant either with steam extraction or as a back-pressure turbine if there is sufficient base-load heat demand. Typically such plants supply large district heating schemes, such as those in Sheffield (see Figure 3.3) and Nottingham. 3.4.2 Landfill gas Landfill gas is produced when waste that has been landfilled releases a methane rich gas. This can be used as fuel in gas engines to produce electricity and in this form has been one of the largest contributors of renewable electricity in recent years. It would be possible to obtain heat from the gas engine in a similar way to conventional gas engines and supply a district heating network. An alternative approach would be to pipe the landfill gas to a location closer to the buildings and site the gas engine at that location. Figure 3.3 The Sheffield energy from waste plant, which supplies the city’s district heating network (courtesy of Veolia Environmental Services (UK) plc) Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 10 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations 3.4.3 Anaerobic digestion (AD) This process is used to treat organic wastes to produce a biogas that can be used directly in spark-ignition gas engines to produce electricity with some of the heat from the engine used to drive the process. There is the potential for additional heat recovery, which could be used to supply a district heating scheme. The digestate produced as a byproduct from the process can be used as a liquid fertiliser. The volumes of waste and digestate are significant, so to reduce transport costs the ad plants are normally sited in rural areas close to the source of farm wastes. In the future with food waste segregation ad plants may become more widespread thereby providing opportunities for heat recovery. 3.4.4 Advanced thermal treatment of waste 3.4.4.1 Gasification This process can be applied to general waste streams and involves heating the waste with restricted oxygen levels which breaks down the material and releases a syngas, part of which is used to provide heating for the process. The surplus heat is used for the production of steam and a steam turbine generator used for electricity production. This provides the potential for the plant to operate in chp mode to supply a district heating network. This technology is relatively new, a recent example being at Newport, Isle of Wight. 3.4.4.2 Pyrolysis The pyrolysis process involves heating the waste in the absence of oxygen and again a syngas can be produced. This type of plant can be smaller-scale and the syngas could be used with a gas engine with heat recovery for supplying a district heating system. Pyrolysis processes can also be designed to produce bio-oil. The solid byproduct biochar is of interest as a soil conditioner and for carbon sequestration. These plants can be smaller-scale and could therefore be more easily integrated with urban district heating. An example is the plant at Avonmouth, Somerset. 3.5 Biomethane injection A further option for the future use of renewable fuels is the production of biogas and conversion to biomethane of a suitable quality to inject into the national gas grid. By this means, chp can continue to use the national gas supply and operate at high efficiencies but with a progressively decreasing carbon content and an increasing renewable fuel content. A few examples of biomethane injection based on anaerobic digestion processes have been implemented in the UK and a major study for National Grid (National Grid, 2009) concluded that there was significant potential from this resource, equivalent to between 15% and 48% of the residential gas demand. 3.6 Integration of CHP with renewable energy sources A chp system is primarily designed to produce low carbon heat. The best economic case will be obtained when the chp unit operates for the maximum number of hours in the 11 year. In the summer period, the heat available from the chp is likely to be greater than the heat demand so surplus low carbon heat is available, assuming the chp is sized to supply some of the space heating demand. chp is unlikely to be sized to meet the peak heating demand so the use of boilers in peak winter conditions would be expected. The chp unit may not operate at night due to the low electricity price although correct sizing of the unit and the use of thermal stores can be used to meet any heat demand at night. The above operating characteristics mean that integration with other renewable energy sources needs to be carefully considered to maximise the opportunities of the site: —— If there is surplus heat in summer, solar thermal systems will not be appropriate with chp as currently they would offer only a small CO2 saving compared to operating the chp plant. However, in the future this could change as electricity emission factors fall and CO2 content of heat from chp rises. Using solar thermal with chp will reduce the operating hours of the chp unit, which would reduce its economic advantage. —— If there is a need for peak heat demands to be met from boilers in winter then biomass boilers could have a role; a thermal store is recommended in this case. Solar photovoltaic panels will generate most in summer when the chp output is lower and could therefore complement chp operation if the site electricity demand is relatively constant over the year. Small-scale wind would be similarly compatible with chp but is likely to generate more electricity in winter. 3.7 Integration of CHP with heat pumps Heat pumps are another form of low carbon heat with very similar characteristics to chp. Whereas a chp plant sacrifices electrical efficiency to produce heat at a useful temperature, a heat pump requires electricity to raise the temperature of the heat drawn from ambient sources. As chp and heat pumps are a higher capital cost than boilers, both will typically be sized to supply base heat load and achieve long running hours and therefore are unlikely to be compatible technologies. Heat pumps are most suited to low temperature applications such as underfloor heating and fresh air heating as the coefficient of performance is related to the temperature at which the heat is supplied. Heat pumps are also more efficient when using elevated temperature heat sources, for example heat rejection from cooling systems for buildings where there is domestic hot water heating and a cooling demand in summer. is more suited to higher temperature applications including domestic hot water heating and district heating where a higher flow temperature reduces the cost of the district heating network. chp With the current electricity emission factors, typically heat from chp has a lower carbon content than heat from heat pumps (see section 6, Figure 6.2). However in the future, when the electricity system has reduced its carbon Combined heat and power for buildings 4 CHP for individual buildings Key points: —— Use a load duration curve to study the demand profiles. —— Develop an operating model to simulate CHP energy flows over the year with the appropriate level of complexity. —— Analyse a range of CHP sizes against a number of economic and environmental parameters to establish an optimum size. —— Consider the benefits of thermal storage. 4.1 Introduction The economic and environmental benefits of a chp scheme, whether for new or existing buildings, are determined by a number of factors: —— building heat and power demand profiles —— fuel and electricity tariffs —— chp plant rating and efficiencies —— chp maintenance costs —— chp plant running hours. Although the above factors are shown as distinct items, they are all interlinked. For the successful application of any chp scheme, all the factors must be assessed together. For any application, there may be a broad range of possible solutions but only a limited number of optimum solutions. In this section, the fundamental factors and how they interact are examined. This section discusses chp for individual buildings although much of the information is also relevant for district heating schemes connecting a number of buildings together. The application of chp to district heating is discussed in more detail in section 5. For a detailed discussion of environmental benefits, see section 6. 4.2 Building heating, cooling and electrical demands The application of a chp scheme in a building depends initially upon the presence of heat and power demands and the extent to which they are compatible with, or close to, the optimum duty cycle of any prospective chp plant. In existing buildings, heat and power demands are substantially predetermined although they may be altered by changing building occupancy, improving building thermal efficiency, or adding new equipment or plant. The chp designer may have only limited scope for altering peak demands or profiles. Demand profiles for new buildings must be assumed from design data or other means. Both existing and new building heat and power demand profiles may be modified by the choice of plant. Examples include: —— hws calorifiers utilising chp heat, rather than electric heating at point of use —— absorption chilling plant utilising chp heat rather than power to produce the desired chilling. chp units will be most effective in buildings where the ratio of heat demand to power demand is steady throughout the day between 1.3:1 and 2.0:1. However, even if these conditions do not apply chp may still be viable — the main factor influencing feasibility is the operating hours of the chp plant. The operating hours may be improved by connecting together buildings with different demand patterns, e.g. a school or office and residential buildings or by the use of a correctly sized thermal store. Heat demand profiles can be visualised in a number of ways. Particularly useful is the load duration curve, which 3000 Heat demand / kW In the longer term, the marginal electricity emission factors may vary significantly by season, time of day and as a result of the output of wind farms. In this situation a hybrid system using both chp and heat pumps combined with significant heat storage could provide an optimum solution whilst also contributing to the control of the national grid. Determination of the heat and power demands will be made by studying graphically presented demand load data. Whereas conventional heating and power plant ratings are set by maximum projected demands to cover seasonal peaks, chp plant rating selection is affected by minimum demands and seasonal and diurnal profiles. Consequently, the building services engineer will need to be able to establish the instantaneous values of heat and power usage during the projected operating period of the chp plant. In practice, half-hourly or hourly data may be used. Using averaged data for a whole day or week may hide too many variations in demand level to be a safe method of assessing profiles, particularly for the final analysis and the choice of chp plant. 2500 2000 1500 1000 500 0 0 249 497 745 993 1241 1489 1737 1985 2233 2481 2729 2977 Hours Figure 4.1 Load duration curve for an office building Percentage of total heat emissions, the two technologies will become similar in performance. 120 100 80 60 40 20 0 –20 0 500 1000 1500 2000 CHP heat input rate / kW 2500 Figure 4.2 Proportion of load supplied against chp capacity 3000 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 12 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations 13 takes the demand in each hour and plots this in descending order. This enables the annual demand that can be met from a given chp capacity to be determined (see Figures 4.1 and 4.2). For this example 80% of the annual demand can be supplied with a chp unit sized at about 30% of the peak demand. —— A simpler approach would be to use a 24-hour model for a typical day in each month (or a typical weekday and weekend day in each month). However the daily profiles still need to be determined for each month. There is a loss of accuracy as the variation of demand within each month is not captured. 4.3 —— A further option is to assume a day/night split of demand and calculate averages for each month. This is clearly a simplification as the 24-hour variation in demand is not modelled. This may not be too much of a disadvantage if a thermal store is included in the scheme which is sufficiently large to result in a smoothed profile. —— Another approach is to divide the demand profile into a series of slices or ‘bins’ and calculate the chp operation for each of these slices before summing for the year. The disadvantage of this approach is that it is not easy to reflect the variations in electricity and fuel prices that are related to the time of day or month of the year. Fuel and electricity tariffs The operating cost benefit of chp, i.e. the difference between the cost of power and heat generated by chp plant and the same power and heat generated conventionally, will depend on the fuel and electricity prices. Where the electricity price is relatively high compared to fuel, chp will achieve high savings, but with low electricity prices and high fuel prices savings will reduce. The difference between electricity and gas prices is often referred to as the ‘sparkgap’ or ‘spark spread’. It is important to be aware of the sensitivity of the economic savings to the relative difference in energy prices. If both electricity and gas prices rise together then the saving from chp operation will also increase. The savings may be negative (losses) on night rate electricity, particularly if the unit is operating at part load in this period. The cost of electricity generated by a gas engine chp generator will be constant throughout the day, since gas tariffs are independent of time of day (this is the case for smaller contracts — larger schemes could obtain gas contracts with varying prices through the year). The cost of imported electricity varies through the day for many tariffs. In the seasonal time of day (stod) tariffs the variation can be very marked during winter month peak hours. 4.4 Principles of CHP sizing Once an understanding of the site’s heat and electricity demand profile has been established the designer is then faced with the task of deciding on the size of the chp. There is no straightforward way to size a chp. Some guidance recommends sizing only to meet the lowest demand that occurs — the base-load that will result in the longest running hours and the shortest payback period. However this is not necessarily the most economically advantageous approach and certainly would limit the amount of CO2 savings that could be achieved on a given site. The recommendations given below are a more rigorous approach to the problem and allow both economic and environmental benefits to be assessed. 4.4.1 Constructing an operating model It would be normal practice to use a spreadsheet model to carry out the calculations. This model can be constructed in a number of ways: —— The most accurate would be to use an hour by hour model over a whole year with heat and electricity demand profiles representing an average year. This is the recommended approach for new buildings where dynamic simulation modelling has been carried out or for existing sites with actual metered demand data. Whereas in most engineering calculations it is possible to make simplifications that result in a conservative or pessimistic answer, simplifying a chp model generally will result in a more optimistic result with respect to the chp operating hours and hence the economic return. Although developing an hour by hour model is the best approach (and, in the absence of metered data, demand profiles can be predicted or modelled assuming typical occupancy patterns and external temperatures), in some cases it may be sufficient to use a monthly model, particularly where the availability of data is limited. However the night/day split that typically is a function of both heat demand and electricity price should always be modelled as the differences in night and day operational costs and heat demand are normally significant. The operating model should be able to: —— determine whether the chp is worth operating based on the relative fuel and electricity prices in each time period considered —— determine the output of the chp to follow the heat demand or electricity demand taking account of part-load operation, and hence the chp fuel used —— establish the heat needed from the peak and standby boilers and hence the boiler fuel use —— make allowance for chp downtime for maintenance —— include any constraints on number of starts (especially for gas turbines) —— model the operation of a thermal store —— determine the net import or export of electricity and its costs/revenue —— calculate the operating costs to compare with the non-chp conventional operating costs. 4.4.2 Evaluating CHP options Once the operating model has been set up it is necessary to run a number of cases for a range of chp sizes starting with a size that just meets the lowest demand (base-load sizing) and increasing the capacity until say 90% of the annual heat Combined heat and power for buildings demand is satisfied by the chp plant. To carry out the calculations it is necessary to have the following data for each size of chp unit: —— capital cost —— efficiencies —— maintenance costs —— minimum turndown ratios —— impact of number of starts. the year. There comes a point when the additional capital cost for a larger size cannot be justified on the fewer hours of operation. Note that this economic comparator gives different results to maximising the irr, which will tend to result in a smaller chp size that is simply maximising running hours and meeting baseload demand. As the chp size increases the CO2 savings will increase. This is a result of the chp unit delivering more of the heat demand. However, without a thermal store, if the chp is too large it will have to shut down in periods of low demand or reject surplus heat. Hence there is typically an optimum size which maximises the running hours and hence the CO2 savings. —— It is also necessary to carry out a net present value (npv) calculation for each option (see section 8.9) and a CO2 emissions reduction calculation (see section 6.2). The criteria for project evaluation are typically: —— —— 500 maximise the internal rate of return (irr) (or minimise the payback period) for the project investment 450 400 maximise the npv of the project investment 350 minimise the net present cost (the negative of npv) of energy supply to the site. 300 MW·h —— In addition, clients may also wish to take into account CO2 savings for each option. A value for the CO2 saved can be included in the economic calculations if desired. Typical results from such a sizing exercise will examine a range of chp sizes as in Figures 4.3 to 4.5. Figure 4.3 represents a baseload sizing that maximises the chp plant’s operating hours and will produce the shortest payback period. Figure 4.4 shows a large chp installation that meets much of the winter demand but is oversized for the summer period when boilers have to be used. The operating hours are much reduced accordingly. Figure 4.5 shows a chp size that seeks to minimise the total costs of energy supply for the site taking account of capital and operating costs. The size is such that the summer demand can still be supplied from the chp plant. Figure 4.6 represents typical results for a chp project and shows the irr, net present cost and CO2 emissions for a range of chp sizes. 250 200 50 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Figure 4.3 chp size too small; this will produce good payback for chp but limited impact on site energy costs 500 450 400 350 300 Boiler heat produced CHP heat output for heating MW·h Total space heating and DHW demand 250 200 150 100 50 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Figure 4.4 chp size is too large; the chp cannot supply heat in summer when demand is low 500 450 400 350 300 Boiler heat produced CHP heat output for heating MW·h Total space heating and DHW demand 250 200 The results show that: 150 —— 100 As the chp size increases the npv increases to a maximum and then falls. There is therefore an optimum size that maximises npv. This optimum occurs as a larger chp unit will produce a greater saving per hour of operation but will have a higher capital cost and will operate for fewer hours over Total space heating and DHW demand 100 MW·h In general it is better to undersize chp than oversize, as heat demands are often overestimated and can reduce over time as a result of energy efficiency improvements. CHP heat output for heating MW·h 150 MW·h Selecting a chp size to provide the shortest payback period and highest irr may not be the best option in terms of minimising the total cost of energy supply for the site. This is because the highest irr will tend to result in a chp sized to meet the baseload and therefore have the longest operating hours. A baseload chp will however have least impact on the site’s energy costs as a whole, taking account of boiler fuel use. Hence for most clients, minimising the net present cost for the total site energy demands will be more appropriate. Boiler heat produced 50 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Figure 4.5 chp size that may be optimum to minimise life cycle costs of heat supply Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 14 15 The comparison can result in two optimum points based on either maximum npv or maximum CO2 savings. To resolve this issue, two approaches can be taken: —— the expected trading value through the CRC Energy Efficiency Scheme or through the European Union’s Energy Trading Scheme. —— Include a value for the CO2 saved and re-run the economic model with the CO2 saving creating an additional revenue stream. 4.4.3 —— Calculate the cost per tonne of CO2 saved for each increment of chp capacity and determine with the client what additional capacity can be justified when the chp investment is compared with other options to save CO2. If a baseload chp size is not the selected solution then consideration needs to be given as to how the chp will operate when heat demands are lower than its rated heat output. A number of options can be evaluated: The value of carbon could be derived from: —— Operation at part-load: This is the most straight­ forward. However there is a loss of efficiency and maintenance costs will increase. This is because maintenance contracts are normally written in terms of a charge per hour run, not on the basis of electricity generation. —— Use of multiple chp units: Using two or more chp units would allow better load following and two units of different sizes provide the greatest flexibility. However there will be higher capital and maintenance costs from using two units and also some loss of efficiency (see below). —— Use of a thermal store: A thermal store would enable the chp to operate at full output for fewer hours in the low demand period instead of modulating down. The surplus heat would be stored for later in the day when the chp would be turned off. —— Heat rejection: To avoid part-load operation the excess heat could be rejected to maintain chp operation at full electrical output. This may have a cost and environmental penalty (see below). 25 IRR / % 20 15 10 5 0 500 600 700 800 900 1000 CHP capacity / kW 1100 1200 500 Operation of CHP in low demand (summer) periods —— the shadow price of carbon published by the Government 30 In practice more than one of these approaches may be used. 450 Net present value / kW 400 4.4.4 350 300 250 200 150 100 50 0 500 600 700 800 900 1000 CHP capacity / kW 1100 1200 1400 1200 CO2 savings / tonnes p.a. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations 1000 800 600 400 0 500 The above discussion has focused particularly on heat. Where the chp electricity is all sold to a licensed supplier, i.e. there is no host site to take the electricity generated directly, then optimising on heat demand will be correct. Where there is the potential for export of electricity there are additional complexities. If the electricity generated is only a small part of the site demand it will be sufficient to assume that the electricity generated displaces the incoming electricity. Where the chp output is similar to the site demand it is possible that the electricity supplier will change the selling price to reflect the change in load factor for the site, which can significantly affect the npv of a potential project. Therefore the price structure that would result from the installation of chp should be carefully evaluated. Where there is significant export, the net electricity income could fall off sharply as export prices are much lower than import prices (typically 30–50% lower). This can be a limiting factor on the size of the chp that can be installed. 4.4.5 200 600 700 800 900 1000 CHP capacity / kW 1100 1200 Figure 4.6 Internal rate of return, net present value and CO2 savings versus chp size Export of electricity Multiple units In addition to sizing of a single chp it is also likely that the option of using two or more chp units will need to be evaluated. The same approach can be used. The capital costs for two chp units will be higher than one unit of the same total capacity and the maintenance costs higher and the performance slightly less efficient. However the Combined heat and power for buildings advantage is that some maintenance can be programmed to take place in periods of low demand when one engine can be kept in operation, improving the overall availability, and that periods of low demand can be supplied from one engine, improving the percentage of heat that can be supplied. It is not necessary to have two equal sized units — greater flexibility is achieved by having two different sizes. Again there is no substitute for detailed modelling of this option against the demand profiles. For small-scale chp (<50 kWe) there is unlikely to be a significant capital or maintenance penalty for multiple units and therefore their use is attractive as it offers a significant gain in flexibility. These units are supplied with a control system that provides automatic sequencing of the units to follow electricity or heat demand. 4.4.6 Heat rejection For a relatively small cost it is possible to include a heat rejection system in the design. This can be achieved by means of an air blast radiator or by a bypass damper in the chp exhaust. This results in additional flexibility in that the chp can continue to generate full electrical output even when the heat demand is low. It can be economic to operate in this manner if the electricity price is relatively high compared to the gas price. It may still be better in terms of CO2 reduction to operate with an element of heat rejection depending on the electricity emissions factor used and the relative efficiencies of chp and boilers. 4.5 Design of building heating systems to benefit CHP operation heat demands are lower than forecast by the original designers, especially if there have been subsequent fabric efficiency improvements to the building. If heat emitters are oversized it is possible to reduce the flow temperature and rebalance the heat emitters to reduce return temperatures. There is some flexibility in the design of chp systems with varying degrees of heat recovery as shown in Table 4.1. The values for individual engines may differ from these figures so discussions with the chp supplier at an early stage is advisable. Heat rejection equipment may be required if the temperatures for heat demand and heat supply from chp are not compatible; for example, the heat from the secondstage intercooler is frequently rejected as the heat demand is normally above 40 °C. Clearly any heat rejection reduces the benefits of having chp and will need to be limited. Heat rejection may also be included to provide greater flexibility in operation. In larger systems where part of the demand is required as steam and part as hot water it is possible to have a low pressure steam-raising heat exchanger in the exhaust and separate heat recovery for low temperature hot water from the engine jacket/oil cooler circuit. This is often achieved by ducting the chp exhaust to a fired shell steam boiler modified to accept this exhaust gas flow to supplement its output. Exhaust gas can also be used directly as the heat source for an absorption chiller. If the majority of the heat demand is high temperature or steam, and if the site is large enough, a gas turbine could be considered where all of the heat (typically >3 MWe) is available as high temperature exhaust gases. Many of the problems of poor chp performance are a result of inadequate attention to the integration of chp into the heating circuit design. Analysis of the design is necessary at all part-load operating conditions, not just under maximum demand. The building services heating system will assist the chp operation if it is designed with low return temperatures There are a number of key objectives for the integration of chp: Flow temperature Return temperature — <40 ºCHeat recovery from second-stage intercooler possible — <50 ºCCondensing exhaust heat exchanger possible 80 ºC (max.) As low as possible but <60 ºC 90 ºC 70–75 ºCStandard conditions suitable for most chp units — >75 ºCRisk of chp tripping out if this temperature is exceeded >100 ºC —Leaks will result in flash steam 110 ºC 70 ºCThis is feasible if the heat recovery is in two stages with the higher temperatures from the exhaust boiler (1) The chp unit should operate in preference to the boilers at all times. (2) The chp unit output remains at maximum when boilers need to be used to meet the demand. (3) The heat recovery from the chp unit is optimised. (4) The chp unit should always be able to generate heat, even at part-load. (5) The building heating system should be designed so that return temperatures do not result in the chp unit shutting down unnecessarily. Operating temperatures with spark-ignition gas engine For new buildings the designer has the opportunity to select flow and return temperatures for the heating circuits to suit the chp plant, condensing boilers and the design of the heat emitters. In retrofit situations, the existing operating temperatures will be a constraint. Often heat emitters are oversized and Table 4.1 Operating temperatures on building services systems and heat recovery opportunities Low pressure steam from exhaust; 90 ºC hot water from jacket Constraints Small-scale chp Two separate heat recovery circuits Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 16 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations 17 (e.g. below 70 °C and preferably lower) and a variable volume control system. This will reduce the risk of the chp shutting down prematurely as a result of rising return temperatures under part-load conditions. Low return temperatures also enable thermal storage to be incorporated more effectively as the amount of energy stored per unit of volume increases. Further discussion of the design of heating circuits for chp is given in section 9. 4.6 Building applications most suitable for CHP Building heat and power loads and profiles are, to a greater or lesser extent, dependent on occupancy. Hence, buildings that are suitable for chp schemes are those where occupancy and energy use regimes normally extend beyond the normal 9 to 5 weekday office hours. Buildings with high domestic hot water heating demands are attractive as they will provide the opportunity for the chp to operate in summer. 4.6.2 plant is less commonly applied in the applications shown in Table 4.3, but these are nonetheless contenders for further consideration. chp Any building that includes a swimming pool should be viewed as having the potential for a chp scheme for both domestic and pool water heating. If the heat/power profile of a building does not immediately seem appropriate, further analysis may identify alternative conditions that would improve the viability. Examples include: —— Using heat-driven absorption or adsorption chilling plant to extend the base load heat demand into the summer months. Absorption chillers may save CO2 and avoid the use of greenhouse gases as refrigerants. —— Energy linking with other nearby buildings that have a complementary heat/power profile. This is the basis on which university systems are often suc­ ces­sful where accommodation units and academic buildings exist on the same campus. The connection of buildings of different types in a mixed use scheme or through district heating will generally result in longer operating hours. It is important to estimate how the demand may vary over a typical 24-hour period as assuming a uniform average demand is likely to result in an optimistic assessment of chp. 4.6.1 Table 4.3 Less common applications for chp schemes Application Reason Offices/town hallsEspecially where normal occupancy extends into the evening; may be combined with absorption chilling MuseumsNeed to maintain stable temperature conditions, independently of opening hours Common applications of CHP Buildings that have historically proved suitable for schemes are shown in Table 4.2. Applications with potential for CHP chp Data centres Year round cooling demand Prisons 24-hour occupancy Schools Extended occupancy, particularly for: — boarding schools — schools with swimming pools — adult education centres Large retail stores and shopping centres Extended operating hours; potential benefit from an associated absorption chilling plant Table 4.2 Suitable applications for chp schemes Application Reason Swimming poolsContinuous demand for pool heating and pump power. High demand for domestic hot water Leisure centresOperate from early morning to late evening. High demand for domestic hot water Hospitals24-hour operation. Need high ambient temperatures for patient care. High demand for domestic hot water Residential homesElderly residents needing high ambient temperatures. High demand for domestic hot water HotelsLong operating hours, need to maintain customer comfort. Often include leisure facilities. High demand for domestic hot water District heatingPotential for long operating hours due to linking of buildings with differing demand profiles and economies of scale University campusOffice/teaching areas require heat during the day and for evening activities. Accommodation areas require heat early morning and evenings Military sites and 24-hour operation and occupancy. Requirement barracksfor standby generating capacity for critical operational facilities. Normally centralised domestic hot water for accommodation blocks 24-hour operation and occupancy. Requirement Police, fire and ambulance stationsfor standby generating capacity for critical operational facilities 4.7 CHP to improve security of electricity supply The presence of a chp generator could provide the security of being able to maintain an energy supply in the event of a failure in the public electricity supply. The extent to which this will apply will depend upon the way in which the electrical system is configured. Careful consideration must be given to the final arrangement to resolve the potentially conflicting requirements of chp plant (i.e. near continuous running, load limitations and maintenance requirements) and conventional standby generators (i.e. low running hours, high availability and independence of standby supply). In particular, chp should not be used for life safety systems as there will be significant downtime for chp maintenance. Separate diesel standby generators should always be used. Combined heat and power for buildings Additional electrical protection will be required to ensure that systems can safely be returned to normal operation on restoration of the public supply. Where standby operation is considered, the load connected to the generator under distribution network operator (dno) failure conditions must be within the generator’s rating. Load shedding arrangements may be required, but may be difficult and expensive to achieve. Gas engines cannot accommodate as large a step change in load as diesel engines so if a chp unit is being used for standby purposes, the load will need to be controlled to avoid step changes in load greater than about 30% of maximum output. Where standby plants can be run on peak-lopping or regional peak export duty during winter months (stor contracts) when tariff margins are greatest, the additional cost to upgrade to chp plant operation may well be worthwhile. In these circumstances, the savings on power import charges and reductions in plant operation may be recovered, even if running hours are as low as 1000 hours per year. 5 Application of CHP to supply district heating Key points: —— The difference between flow and return temperatures for district heating should be at least 30 °C. —— Heat emitters and domestic hot water heating systems should be designed to achieve low return temperatures. —— Controls should be variable volume (two-port control valves) to maintain low return temperatures at part-load and minimise pumping energy. —— Where bypasses are included the bypass flow rate should be limited and controlled so as to maintain a minimum flow temperature in the network. 5.1 Principles of district heating District heating (dh) is not an energy supply technology; it is only a means of transporting heat to a number of buildings such that a wider variety of heat sources can be used. In addition, the inclusion in the dh scheme of buildings of varied type, size, age and occupancy patterns results in a diversity of demand that tends to reduce peaks and provide more continuous demands. This can be advantageous for chp systems and other high capital cost plant where longer running hours will improve the economic case. Note: many of the principles set out below are also applicable to any large heating circuit and the distinction between district heating and building services heating design is somewhat arbitrary. A dh network consists of flow and return pipes connecting each building’s heating system to a centralised pumping arrangement. At the building connections the dh water can be used directly in the building’s heating system (direct connection) or through a heat exchanger (indirect connection). A direct connection can also be used with a mixing system where the flow temperature in the building heating system can be lower than in the dh network. An efficient dh system will have a flow/return differential temperature between 30 °C and 50 °C to reduce flow rates on the network and keep pipe sizes small. The system will also be more efficient if return temperatures do not rise under part load conditions as this would involve additional pumping energy and heat losses from the return pipe. The use of two-port control valves and variable flow systems within the building heating systems is therefore strongly recom­mended. A dh network will need to ensure that the flow temperature is maintained above a set level at all points of the network and this typically is achieved by using bypasses to maintain a minimum flow rate. The best system is where these bypasses are temperature controlled to avoid unnecessary bypass flows, which would add to pumping energy. The dh system will operate as a variable flow system and variable speed pumps should be used to minimise energy consumption using pressure differential sensors within the network to control pump speed. Often multiple pumps are used to enable the flow rate and head requirements to be followed more closely. A fundamental requirement for a dh network is that the design flow rate can be supplied to all customers during maximum demand periods. This means that the flow rate into each customer’s connection must be limited regardless of the differential pressure on the network. This is most easily achieved using a differential pressure control valve (dpcv) to limit the pressure across the heat exchanger or control valve, or across the building heating system in the case of direct connection. The dpcv is then adjusted (using a balancing valve in addition, if necessary) to set the required design flow rate. In addition to chp plant of all types and scale, dh networks can be supplied with heat from: —— fossil fuel boilers —— biomass boilers —— industrial waste heat sources with a heat pump to raise the temperature if necessary —— large-scale solar thermal systems —— large-scale heat pump systems, especially with ground or river as the heat source or in combination with district cooling —— deep geothermal heat. The efficiency of heat pumps depends strongly on the temperature at which heat is supplied as well as the tempera­ ture of the heat source. This means that the flow temperature from a dh network supplied by a heat pump will probably be below 80 °C for efficiency reasons. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 18 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations 5.2 Typical applications of DH and CHP A dh network is a significant capital investment and any scheme should be seen as a long-term strategic infrastructure suitable for sites with a long life. The advantage of dh is that, provided routes for the pipework are carefully chosen, alterations to any given building will not have a major impact on the operation of the central plant. In this respect a chp system supplying a dh scheme is more flexible than if chp were to be installed in each building in an area. Typical applications where a diversity of demand will lead to more constant heat loads and longer running hours for chp include: —— —— 5.3 New mixed use developments including housing, offices, retail and leisure: this type of scheme has the potential for reasonable summer heat demands for domestic hot water, daytime heating demands from offices and retail and evening heat demands from leisure and housing. University campus: a wide range of academic buildings often exists including laboratories where high air change rates can lead to significant heat demands. If student accommodation is provided on the campus, this will result in extended heating through the evening. Many universities, libraries and leisure facilities function with long opening hours. Student accommodation is often used in the summer for short courses and conferences. Selling electricity and private wire networks Unlike a building or campus application, a chp plant installed to supply a district heating network may not be displacing imported electricity but will have to sell electricity to a customer that may not have any connection with the heat supply. There are a number of options available: —— selling to a licensed supplier who will then sell on to their customers —— direct sale to a large electricity user using a dedicated cable connection —— sale to one or more customers using the existing distribution network operator (dno) infrastructure through paying use of system charges —— direct sales to the buildings in the area using a private wire network —— ‘netting off ’ chp generation as part of a large electricity sales contract. For a private network, terms will need to be offered for the use of the system by other electricity suppliers if competition on electricity supply is to be maintained. 19 5.4 Efficient design of DH systems to benefit CHP operation 5.4.1 New buildings or buildings with extensive refurbishment If new building services are being specified to operate in conjunction with a dh supply there is the potential to optimise the design to the benefit of the dh system. Ultimately this will lead to lower energy supply costs and lower CO2 emissions, even though the initial cost for the building services may be slightly higher. The main design principles to be followed are: —— Selection of low operating temperatures and especially low return temperatures. Typical space heating circuit temperatures of 60–70 °C flow and 40 °C return should be considered. —— Selection of hot water heating systems to deliver low return temperatures using the dh supply; typically this would involve: instantaneous plate heat exchangers to (a) meet peak hot water demands storage of hot water but with heating (b) provided by external plate heat exchangers. The domestic hot water heat exchangers should be sized to give a dh return temperature of 40 °C (preferably lower). Storage calorifiers should be avoided as the return tempera­ tures will be higher than the stored temperature except at cold start-up. Variable volume control systems should be used with twoport control valves to ensure return temperatures on the dh network do not rise at part-load. Bypass flows in the heating circuit should be avoided to prevent rising return temperatures at part-load. If bypasses are necessary to maintain flow temperatures they should be temperature controlled and only open to allow the minimum flow rate when needed. A design and control system that ensures that heat is taken from the dh network as the priority heat source and that if boilers within the building are retained for use in peak periods the heat taken from the dh network remains at its maximum level when the boilers operate. Correct commissioning is needed to ensure that the intended design return temperatures are achieved. There will always be a tendency in commissioning to have higher return tempera­tures than design and higher heating circuit flow rates as this will be seen as providing greater margin. This approach should be avoided. The location of the dh heat exchanger in the circuit is an important consideration to achieve the above objectives. Where on-site boilers are installed or retained, the heat exchanger can be in either a series or parallel arrangement with the boilers, however, if it is in parallel a common header bypass should be avoided and the dh heat exchanger and boilers should have separate shunt pumps. Combined heat and power for buildings Energy centre DH network Building connection (indirect) Building heating system Controls (D) CHP Peak boiler Thermal store (A) (E) (J) (B) M (F) (C) (A) Thermal store to minimise use of peak boiler (B) Variable speed pumps with a range of duties to suit demand pattern (C) Temperature controlled bypass at extremities of network (H) (G) Plate heat exchanger sized for close return temperatures (D) Differential pressure control valve to limit maximum flow and limit pressure across control valve (E) (E) Two-port control valve to ensure variable volume in DH network and to vary secondary temperature (F) Heat meter to encourage careful use of energy (G) (H) Two-port control valve to maintain low return temperature (J) Heat emitters sized to give low return temperature Figure 5.1 Features of an efficient district heating system 5.4.2 Existing buildings For existing buildings the dh supply may meet the peak demand of the building or supply only part of the demand with peak demands being met by boilers installed within the building. 5.4.2.1 DH supplies peak demand In this case the dh company will provide a heat exchanger that can be installed either in parallel with the boilers or in the return to the boilers. The dh company will wish to have return water at as low a temperature as possible and the contract for the supply of heat may include penalties for high return temperatures or incentive payments for lower return temperatures. The maximum supply rate into the building will be constrained by two factors: the size of the heat exchanger and the primary flow rate from the dh system. The flow rate will be determined by assumed return temperature and if the secondary (building side) return temperatures rise above this assumed value the heat delivered to the building will be lower than the agreed figure. It is therefore necessary for the building services designer to ensure that the temperatures set out in the contract can be achieved. The key issues are: —— Checking that the building circuit flow temperature does not exceed the design value at time of peak demand (this will be a set point on the dh heat exchanger control). —— Limiting any bypasses in the heating system to the minimum compatible with avoiding dead legs. It would be preferable for such bypasses to be temperature controlled. —— Ensuring that the system is balanced so that at times of peak demand the return temperature is at design condition. This may require balancing of all heat emitters and ahu coils in the building. This re-balancing will not only help the dh network but will also avoid unnecessary pumping energy on the building system. The above considerations should ensure that the peak demand situation is satisfactory. At part load conditions the dh network energy (pumping and heat loss) can be minimised by ensuring that return temperatures do not rise above (and preferably fall below) the peak design return temperature. This will not be achieved if three-port control valves are used. It would be preferable for such systems to be converted to operate as variable volume, two-port control valves and it may be worth establishing with the dh company how such a change could be financed through the heat service contract. The recommendations for new buildings above would then apply for the conversion works. These conversion works may be justified on the energy savings generated within the building, irrespective of any district heating or chp benefit. It is also possible that the operating temperatures could be lowered, which will benefit the dh system. It is likely that there will be a general oversizing of heat emitters as a result of design margins or possibly as a result of improved insulation after the services were installed. It may be possible to examine bems data to see whether control valves are fully open at times of peak demand. If they are not then this would indicate potential for reducing temperatures. A gradual reduction in flow temperature whilst monitoring internal conditions through a winter period would enable the lowest maximum required flow temperature to be established. 5.4.2.2 DH supplies part of demand In this case the dh supplies part of the demand and there will be an agreed maximum supply rate so that the dh network will only meet a proportion of the annual demand, with the building boilers being required to operate at times of peak demand. The guidance above should be followed but in addition: —— the dh heat exchanger should be used as the priority heat source in preference to the boilers Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 20 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations —— 21 when the boilers are also required to operate, the heat exchanger should continue to supply its maximum heat output. dh These requirements are most easily achieved by connecting the dh heat exchanger into the return pipe before a common header. This may require some pipework modifications to combine the returns. 5.5 Use of thermal storage The use of a thermal store in association with a chp system (and often with other low carbon heating technology) brings four potential advantages: —— It enables heat demands greater than the maximum output of the chp to be met from chp heat stored earlier thus reducing the use of boilers and increasing chp running hours. —— It enables heat demands lower than the minimum turndown of the chp to be met from chp heat stored earlier reducing the use of boilers and increasing chp running hours. —— It enables the chp unit to operate at full output rather than at part-load thus improving its efficiency. —— It allows heat demands to be supplied outside the normal economic operating regime of the chp, e.g. at night when electricity prices are low and it would not be economic to run the chp thus reducing the use of boilers. 5.5.1 Figure 5.2 Thermal store supplying a small district heating system (courtesy of Cofely District Energy Ltd.) Designing a thermal store Thermal stores consist of a cylindrical vessel of hot water. This should be installed between flow and return circuits and will remain full of water at all times. For a store located internally there will be space constraints, and costs will also be dependent on volume. So it is prefer­ able to reduce the size of the store as far as possible. This is achieved by maximising the temperature difference between flow and return on the heating circuit. As the flow tempera­ ture is normally limited to about 90 °C, in practice this means having as low a return temperature as is practicable. The other benefit to having a large temperature difference is that the depth of the mixing layer between the hotter flow water and the cooler return water is smaller. The water in this mixing layer cannot be delivered to the scheme so the useful volume of the store is reduced by this amount. The depth of the layer can be minimised as a proportion of the volume of the store by: —— having taller cylinders (i.e. large height to diameter ratio) —— by using low return temperatures, and therefore a greater difference in density between flow and return —— ensuring there is flow into the store only during filling and recovering of energy, and no flow through the store when the demand and supply is matched Figure 5.3 Thermal store at the London 2012 Olympic Park (courtesy of Cofely District Energy Ltd.) —— ensuring velocities at entry and exit are low by using large diameter pipe connections and baffle plates. A higher flow temperature can be used for the chp and store circuit than that supplied to the building by using a variable temperature mixing valve. This enables the maximum temperature difference to be achieved within the store so that more heat energy can be stored. 5.5.2 Combined heat and power for buildings Sizing of the thermal store To establish the optimum size of the store it is necessary to use an hour by hour operating model preferably for the whole year, and to carry out a series of calculations with a range of store sizes. The aim would be to optimise on the npv or CO2 emissions savings, as described in section 4.4. If it is considered that the most important aspect of the store is to meet the demand at times when the chp is not operating, then this would be a fairly straightforward calculation as the store would need to hold the heat energy required to supply all of the heat demand in this period. 5.6 District cooling Many of the principles outlined above apply equally to district cooling (except that temperatures are reversed). District cooling systems have limited temperature differ­ ences (e.g. 4 °C to 14 °C) so controlling pumping energy by avoiding low return temperatures at part-load is important. A direct connection will avoid the need for a temperature differential across a heat exchanger, which could be of benefit in reducing flow rates. The limited temperature difference available inevitably means larger pipe sizes and higher capital costs. Hence district cooling systems tend to be found only where there is high density of cooling demand with good load factors. The cooling source may be provided by absorption or adsorption chillers supplied by chp or by large efficient vapour compression chillers. An alternative approach is to install absorption chillers in the buildings, supplied from the dh network. 5.7 Large-scale district heating Large-scale district heating operates on the same principles as described above. The main difference is that the chp heat source may be a major power station and will be operated primarily to generate electricity. As a result a flexible design is often used where the steam is extracted from the steam turbine when required for heat and there is full condensing capability so that electricity generation can be maximised when there is low heat demand. This flexibility can be used to advantage when combined with large-scale heat storage as heat can be extracted from the steam turbine at night, when electricity demand is low, and stored for the following day. The other feature of large-scale district heating is the ability to use multiple heat sources and to vary their relative contribution in both the short-term and long-term to minimise operating costs and CO2 emissions. This could be an important advantage in the future, when CO2 emissions associated with grid electricity are lower, as a means of avoiding the risk of having ‘stranded’ assets that are less beneficial, which could be the case with smaller schemes where gas fired chp is the only realistic heat source. District heating networks are now installed using preinsulated pipe systems buried directly in the ground. These comprise a steel carrier pipe, rigid polyurethane pipe insulation and a high density polyethylene outer casing. A surveillance system is included to detect the ingress of moisture into the insulation that could cause corrosion. High water quality needs to be maintained using chemical and physical water treatment. Smaller pipe systems using low temperatures and pressures can use pre-insulated allplastic systems with cross-linked polyethylene (pex) or polybutylene (pb) carrier pipes. 6 Primary energy savings and environmental impact of CHP Key points: —— The equivalent heat efficiency of CHP is given by: CHP thermal efficiency CHP equivalent = ————————————— heat efficiency CHP electrical efficiency 1 – —————————— Grid efficiency ( ) This efficiency can be compared directly with a boiler efficiency. —— Equivalent heat efficiency for a heat pump is given by: Heat pump equivalent = CoP Í grid efficiency heat efficiency —— The CO2 content of a unit of heat supplied by CHP is given by: CO2 content = [Ef – (Ee Í he)] / hh where Ef is the fuel emission factor, Ee is the electricity emission factor, he and hh are the CHP electrical and thermal efficiencies respectively. 6.1 Primary energy savings The energy efficiency of heat supply can be calculated using the ‘equivalent heat efficiency’ concept and used to compare heating options. For a boiler: Heat output Equivalent heat efficiency = —————– (6.1) Fuel used For a heat pump: Heat output Equivalent heat efficiency = —————————– Primary energy input Heat output = —————————————–– (Electricity used / Grid efficiency) = cop Í he, grid (6.2) where cop is the coefficient of performance (i.e. useful heat output divided by the electricity consumption over the year) and he, grid is the grid efficiency. The grid efficiency is given by: Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 22 Delivered electricity he, grid = ————————–—— Primary fuel input (Fps) 23 (6.3) The performance of a chp system needs to be defined in terms of two factors, i.e: Thermal efficiency (hh) = ­­­­­­­­­Hchp / Fchp (6.4) where Hchp is the useful heat output and Fchp is the fuel input. Electrical efficiency (he) = Echp / Fchp (6.5) where Echp is the electricity generated and Fchp is the fuel input. Note: the chp performance can also be defined using total efficiency (i.e. heat plus electricity, divided by fuel input), or heat-to-power ratio plus one of the two efficiencies defined above; however two parameters are always needed to define chp performance. The equivalent heat efficiency for chp is given by: Heat output Equivalent heat efficiency (hh,eq) = —————– Net fuel used The net fuel used is the chp fuel (Fchp) minus the power station fuel (Fps) displaced by chp electricity generated (Echp). Therefore the equivalent heat efficiency is: hh,eq = Hchp / (Fchp – Fps) (6.6) Substituting for Fps from equation 6.3: hh,eq = Hchp / [Fchp – (Echp / he, grid)] Substituting for Echp from equation 6.5: and so the chp electrical efficiency will therefore generally be lower than the best power station efficiency. However, electricity grid losses also need to be taken into account, which reduces the effective grid electrical efficiency at the point of supply, narrowing the gap with chp. In equation 6.7, as the chp electrical efficiency tends towards the grid efficiency then the equivalent heat efficiency tends towards infinity, i.e. the heat would eventually be rejected close to ambient temperature and could be classed as ‘waste heat’. At the other extreme, if the chp electrical efficiency tends towards zero then the chp equivalent heat efficiency tends towards the chp thermal efficiency, i.e. the chp is tending to become the equivalent of a boiler. So the most efficient chp is where the electrical efficiency is as high as possible. Equation 6.7 can be plotted in various ways and Figure 6.1 shows how the equivalent heat efficiency varies with chp electrical efficiency for three different grid efficiencies (40%, 45% and 50%) and for a total chp efficiency (thermal plus electrical) constant at 80% in all cases. Figure 6.1 shows that the equivalent heat efficiency increases as the chp electrical efficiency increases. The increase is significant; for the 40% grid efficiency case the chp equivalent heat efficiency increases from 200% to 360% for an increase in electrical efficiency from 30% to 35%. Similarly, to maintain the same equivalent heat efficiency of 200% as the grid efficiency improves from 40% to 50%, the chp electrical efficiency would need to improve from 30% to 40%. All of the chp equivalent heat efficiencies are higher than those for boilers, which are typically 80% to 90%. Figure 6.1 can also be used to compare chp with heat pumps. From equation 6.2, for example, with a grid efficiency of 40%, a heat pump with a cop of 3 has an equivalent heat efficiency of 120% (i.e. 3 Í 40%) and a chp with an electrical efficiency of 20% would have the same equivalent heat efficiency. However, for a grid efficiency of 50%, a heat pump with a cop of 4 would have an equivalent heat efficiency of 200% (i.e. 4 Í 50%) and a chp would need to have an electrical efficiency of 40% to be as efficient. hh,eq = Hchp / [Fchp – (Fchp he / he, grid)] 400 Rearranging gives: hh,eq = (Hchp / Fchp) / [1 – (he / he, grid)] Substituting for (Hchp / Fchp) from equation 6.4: hh,eq = hh / [1 – (he / he, grid)] (6.7) i.e: chp thermal efficiency chp equivalent = ———————————— heat efficiency chp electrical efficiency 1 – ————————–—— Grid efficiency ( ) Equation 6.7 is fundamental to chp performance and merits further explanation. One implication of the second law of thermodynamics is that the highest electrical efficiency will be achieved when discharging heat at the lowest possible cold sink temperature, i.e. ambient temperature. For heat to be useful it will always need to be above ambient Equivalent heat efficiency / % Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations 350 300 250 200 150 100 50 0 15% 20% 25% 30% 35% CHP electrical efficiency Grid efficiency 40% Grid efficiency 50% Grid efficiency 45% Heat pump CoP 4 grid efficiency 50% 40% 45% Heat pump CoP 3·5 grid efficiiency 45% Heat pump CoP 3 grid efficiency 40% Gas boiler at 85% efficiency Figure 6.1 Equivalent heat efficiencies for chp (chp total efficiency = 80%) Combined heat and power for buildings The current grid efficiency is about 39% as calculated from Table 5.6 of the Digest of UK Energy Statistics (DECC, 2010). This excludes transmission and distribution electrical losses so the average efficiency for delivered energy is around 36%. energy efficiency gains and hence the mitigation of climate change, it does not take account of the variation in CO2 emissions that result from using different types of fuel. Typical equivalent heat efficiencies calculated from the above equations are as follows. The CO2 savings associated with chp can be established by calculating the total CO2 emissions for the building or district heating scheme both with and without chp installed; the difference is the CO2 saving. For current technology and a grid efficiency of, say, 40%: Without chp: —— Individual gas boiler: 85% —— Air source heat pump (cop = 2.5): 100% —— Gas-engine chp (35% electrical efficiency and 45% thermal efficiency): 360% For future technology and a grid efficiency of, say, 50%: —— Individual gas boiler: 85% —— Air source heat pump (cop = 2.5) = 125% —— chp —— Heat pump (cop = 4): 200% —— chp (35% electrical efficiency and 45% thermal efficiency): 150% (40% electrical efficiency and 40% thermal efficiency): 200%. Equation 6.7 shows the importance of achieving a high electrical efficiency for the chp plant in relation to the grid efficiency. As grid efficiency improves, chp electrical efficiency will also need to improve if the benefits of chp are to be maintained, for example by the use of fuel cells or, at a larger-scale, combined cycle gas turbines. It is more meaningful to consider the relative energy efficiencies of chp and conventional grid electricity when both sources are using the same fuel (i.e. natural gas). Currently gas-fired power stations are about 47% efficient or 43% efficient after taking account of grid losses, although these efficiencies are likely to improve with the new generation of combined cycle gas turbine (ccgt) plant being constructed, so the figures given above for 50% grid efficiency may be achieved for gas-fired power stations in the future. Often chp efficiencies are quoted as being 80% (referring to the total efficiency) and then compared with the grid efficiency of 40%, thus indicating a doubling of energy efficiency. As the analysis above shows, this is a false comparison, for a low chp electrical efficiency of, say, 15%, a chp total efficiency of 80% may be only slightly better than a boiler. Similarly, heat pumps are often claimed to have an efficiency of more than 100% (which is true provided that cop Í grid efficiency >100%) and that this must therefore always be better than a chp that has a practical maximum total efficiency of 80%. Again, this is an erroneous conclusion — the chp equivalent heat efficiency can be significantly better than a heat pump depending on the seasonal cop of the heat pump, the chp electrical efficiency and the electricity grid efficiency. 6.2 CO2 savings and impact of emission factors Although the primary energy approach described in section 6.1 provides some useful insights into the potential for CO2 emissions = [(H / hboiler) Í Ef,boiler] + (P Í Eelec) (6.8) where H is total heat consumption for the site (MW·h), hboiler is the boiler efficiency, Ef,boiler is the emissions factor for the boiler fuel (kg/MW·h), P is the electrical consumption for the site (MW·h) and Eelec is the emissions factor for electricity (kg/MW·h). With chp: CO2 emissions = [(H – Hchp) / hboiler Í Ef,boiler] + (Fchp Í Ef,chp) + [(P – Pchp) Í Eelec] (6.9) where Hchp is the heat supplied from chp (MW·h), Fchp is the fuel used by the chp (MW·h), Ef,chp is the emissions factor for the chp fuel (kg/MW·h) and Pchp is the electricity supplied by chp (MW·h) The boiler efficiency (hboiler) is the heat produced divided by the fuel input (based on gross calorific value (gcv)). The above equations assume that the boiler efficiency is constant whereas in some cases the boiler efficiency may be reduced by the addition of chp if the boilers operate intermittently and at lower load. This approach results in a single absolute CO2 saving for the site and does not involve assigning this saving to either heat or electricity. Net (lower) calorific value and gross (higher) calorific value Energy efficiencies are defined by the ratio of useful energy produced to the energy in the fuel that is used. There are two definitions for the calorific value of the fuel used to convert the volume or mass of a fuel to energy: —net calorific value (NCV) is the energy recovered from the combustion gases but excluding the latent heat recovered from the water vapour produced —gross calorific value (GVC) includes the energy that can be obtained by condensing the water vapour. Energy is sold using GCV and emission factors are based on GCV. It is therefore important to use GCV efficiencies in calculations of cost-effectiveness and environmental impact of CHP. There is a convention in the power industry to state efficiencies in terms of NCV and so the efficiencies used must be carefully checked and converted to GCV if necessary. The conversion from NCV to GCV depends on the fuel used. For UK natural gas, the GCV is 1.108 times the NCV, so an efficiency quoted using NCV needs to be divided by this conversion factor to provide an efficiency based on GCV. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 24 6.2.1 25 CO2 emissions due to heat supplied If it is necessary to compare chp with other options a similar approach can be used to calculate the site CO2 emissions. However it may also be useful to compare the options on the basis of the CO2 content of the heat supplied. The chp unit is installed to provide heat, not electricity and, on this basis, its CO2 emissions can be compared with, say, a biomass boiler. It will be the heat demand that is constant in each case. The method given below calculates the CO2 emissions associated with a unit of heat produced by the different technologies. For a boiler, the CO2 emissions associated with heat output are given by the fuel emission factor divided by the efficiency; for a heat pump, they are given by the electricity emission factor divided by the cop. For a chp plant, the CO2 emissions are given by: ( ) ( fuel chp-generated elec. Í – Í fuel emission factor elec. emission factor ————————–———————————— chp heat generated chp ) This can be expressed in terms of the chp thermal efficiency and chp electrical efficiency as follows: Fchp Í Ef – Echp Í Ee CO2 content of chp heat = ————————–— Hchp = (Ef / hh) – Ee (he / hh) = (Ef – Ee he ) / hh (6.10) where Echp , Hchp and Fchp are the chp energy flows for electricity generated, heat and fuel respectively, Ef is the fuel emission factor, Ee is the electricity emission factor, and he and hh are the chp electrical and thermal efficiencies respectively. Another type of chp plant is where heat is extracted in the form of low pressure steam from a power station built primarily for electricity generation, irrespective of the energy source (i.e. fossil fuel, energy from waste, biomass or nuclear). When steam is extracted from the steam turbine at a useful temperature, there will be a reduction in the electricity generated. In this case the CO2 content of heat relates to the emissions from other power stations on the system that would have to operate in order to replace this ‘lost’ electricity. The ratio of heat extracted to electricity reduction is termed the ‘z-factor’ and is typically in the range of 6 to 8. Hence: CO2 content of heat extraction = Ee / z (6.11) The above equations have been plotted graphically as Figure 6.2 for comparison, with the main variable being the electricity emission factor for the grid supply. It is assumed that gas is the fuel used for chp and a gas emission factor of 198 g/kW·h (DCLG, 2010). Figure 6.2 demonstrates that the key issue in the comparison is the emission factor assumed for the grid electricity. As the electricity supply is composed of a mix of power stations with wide variation in emissions factor (from hydro­ electricity and wind energy with near zero emissions to coal-fired power stations with around 900 g/kW·he), it is not obvious which emissions factor to use. An average emissions factor is the approach taken within Part L of the Building Regulations 2010 (DCLG, 2010) where 529 g/kW·he is to be used in assessing the benefits from displacing grid electricity. Figure 6.2 also shows the importance of electrical efficiency of the chp in achieving low CO2 emissions. Long-term decarbonisation of the electricity grid will mean that, over time, chp systems will save less CO2 as they will be competing with lower-carbon grid electricity. However, natural gas fired chp with efficiencies greater than 20% electricity and 60% thermal will still result in CO2 savings provided unabated gas fired power stations are still operating on the system. It is possible that the gas supply will also be decarbonised through the injection of biomethane, which may offset some of the reductions in CO2 savings. chp would make better use of this renewable energy. In the longer term beyond 2030, it may be necessary to move away from the small-scale natural gas fired plant that dominates the chp market at present to the use of renewable fuels or extraction of heat from major power stations, together with the greater use of district heating. District heating systems may also use low carbon heat sources other than chp, including heat pumps. The impact on chp applications will depend greatly on the rate of decarbonisation of the grid. In addition to the comparison of technologies on the basis of CO2 emissions, the flexibility of generation is likely to become important as the amount of intermittent wind energy increases. The use of local smaller generators that CO2 emissions per kW·h heat / (g / kW·h) Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations 300 250 200 150 100 50 0 –50 –150 300 350 400 450 500 550 600 650 CO2 emissions per kWh electricity / g/kWh CHP at 25% 700 Gas boiler at 85% CHP at 35% Heat pump (CoP = 2) CHP at 42% Heat pump (CoP = 3) Steam turbine extraction z=7 Figure 6.2 CO2 emissions for heat from various sources against electricity emissions factor (Note: stated chp efficiencies relate to electrical efficiency; total chp efficiency (i.e. thermal plus electrical) is kept constant at 80%. All efficiencies are on gcv basis) Combined heat and power for buildings can respond quickly could have a valuable role in helping to balance the grid. 6.3 CO2 benefits from tri-generation The CO2 benefits from tri-generation can be assessed in a similar way by first calculating the CO2 content of heat from chp and then the CO2 content of ‘coolth’ from the absorption chiller from: CO2 content of coolth is the CO2 content of the heat supplied divided by the cop of the heat-driven chiller. This can then be compared with the CO2 content of coolth from a conventional electrically driven chiller from: CO2 content of electricity CO2 content of coolth = ——————————–– cop of electric chiller (6.12) CO2 emissions per kW·h heat / (g / kW·h) Typical results for a single effect absorption chiller coupled to a gas fired chp system with a range of electrical efficiencies are plotted as Figure 6.3. It can be seen that with current electricity emission factors of around 500 g/kW·h, trigeneration offers some benefits compared to an electric chiller with a cop of 4, but if the electricity emission factor falls to around 400 g/kW·h (as is predicted) there will be no CO2 savings even for a very efficient chp. A detailed comparison of relative benefits is recommended given that cops for electrically driven chillers are improving. Account should also be taken of ancillary electricity for condenser cooling, as a single effect absorption chiller will require around twice the energy of an electrically driven chiller for its heat rejection system. 300 250 As with most fuel combustion sources, the principal means for reducing the impact is to ensure good dispersion of the combustion gases away from people who might be affected (the term ‘sensitive receptors’ is used). This can be achieved by using a sufficiently high stack to ensure dispersion by the air such that ground level concentrations are low. Care needs to be taken when there are tall buildings in the vicinity. Generally stacks should be at a height above the roof line to avoid turbulence around the building, which could cause the plume to return downwards and reach occupants of the building. Stack exit velocities should be 10–15 m/s. Using lower exhaust temperatures to maximise heat recovery may have the undesirable effect of reducing the buoyancy of the plume. Engine emissions are determined by the quality of fuel, the mixture of air and fuel, and the efficiency of the combustion process. For a given engine, maximum shaft power output will be achieved when combustion takes place under stoichiometric conditions, i.e. just the right amount of oxygen for the amount of fuel. However, this will not achieve minimum emissions. It is normal to supply engines with an excess of oxygen (air) to reduce the NOx and CO levels. Both of these pollutants are addressed in the UK Air Quality Strategy (DEFRA, 2007), which identifies that NOx in particular can have adverse effects on human health and can contribute to acidification of the environment. Most engine manufac­ turers design engines to comply with recognised emission standards. Where stringent emission conditions are demanded, emission control may be achieved by use of lean-burn engines (air flow 1.5 to 2.0 times stoichiometric conditions). Selective catalytic reduction systems can be employed and are designed to reduce NOx by 95% or more. Oxidation catalysts may be designed to reduce CO and non-methane hydrocarbons (nmhcs). Reductions of 90% in CO and 50–70% in nmhcs may be achieved. 200 150 100 50 Selection of catalytic reduction systems is an area where specialist advice should be sought. 0 -50 Catalysts will have a finite life and it is necessary to factor in the cost of their replacement over the life of the scheme. -100 -150 300 potentially have a negative impact on the local environment and will need to be assessed and controlled. 350 400 450 500 550 600 650 CO2 emissions per kW·h electricity / (g / kW·h) 700 Tri-generation at 25% Tri-generation at 42% Tri-generation at 35% Chiller (CoP = 4) 6.4.1 Particulate emissions Figure 6.3 Comparison of tri-generation with electrically driven chillers (Note: tri-generation efficiencies refer to the chp electrical efficiency; overall chp efficiency is taken as 80% in all cases) Where natural gas, or clean synthesis gas (‘syngas’) from advanced gasification, is used as the fuel, particulate emissions are not a concern. However the range of fuels for chp is expanding and particulate emissions need to be considered when using biomass or any liquid fuels. 6.4 6.4.2 Other emissions to air Although CO2 emissions are the main concern with regard to climate change, N2O is also a greenhouse gas. In addition, NOx emissions are associated with poor air quality in cities leading to public health concerns. Whilst chp units will displace electricity generated at remote power stations and provide global environmental benefits, the local emissions Relevant legislation and guidance The third edition of Chimney Heights: 1956 Clean Air Act Memorandum (DoE, 1981) was produced specifically for dealing with emissions from conventional boilers in use at the time and can continue to be used for boiler emissions unless other criteria apply to the site, e.g. under the European Directive on Integrated Pollution Prevention Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 26 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations and Control (‘the IPPC Directive’). However, it should not be used in the calculation of chimney heights for chp gas engine emissions. In some larger schemes dispersion modelling may be required to demonstrate the levels of NOx concentration at ground level as part of a planning application. In other schemes applying the guidance in HMIP Technical Guidance Note D1 (HMIP, 1993) should be followed whether using new purpose-built chimneys or re-using existing. If the site comes under the provisions of the IPPC Directive, the Environment Agency will almost certainly require dispersion modelling to be carried out using approved software, rather than a D1 calculation. 6.4.3 Flue dispersion modelling Whilst not mandatory, HMIP Technical Guidance Note D1 may be used as the benchmark for determining the appropriate stack height. However this was not originally written for gas-fired chp systems. A more appropriate method is to carry out a modelling exercise to establish the impact of the emissions on ground concentrations, and from this model determine the optimum height that balances impact on air quality with cost and visual impact. This is typically the information that would be needed for a planning application for a large installation, especially if the site is located within an Air Quality Management Area. It is advisable to discuss the project in advance with the local Environmental Health Officer to determine the information that is required to be submitted with a planning application. The Local Authority, the Environment Agency, the Scottish Environment Protection Agency (SEPA) or the Northern Ireland Environment Agency who grant approval may require particular operating parameters to be used in the calculation of chimney height. They may also require a copy of any D1 or dispersion modelling calculations, so early contact with the appropriate authority is recommended to avoid conflict or disagreement at a later date. The installation of a chimney calculated to meet D1 or using dispersion modelling is not a guarantee that the site will not cause a nuisance. The calculation is based upon the 98th percentile of meteorological conditions (Guidance Note D1, paragraph 2.6 refers) and there remains the risk of a smell being detected during engine operation under abnormal weather conditions or sudden gusts of winds carrying undiluted exhaust down to ground level. Special consideration may be necessary for occupied buildings that are close to chimneys or are relatively tall with opening windows at high level. D1 and dispersion modelling only consider ground level concentrations, so taller occupied buildings may be subjected to higher concentration levels of pollutants than are expected at ground level. 6.4.4 Air quality objectives Under the authority of the Environment Act 1995 the Secretary of State has issued The Air Quality (England) Regulations 2000 Statutory Instrument 2000 No. 928. This sets short and long term air quality objective levels 27 (measured at ground level, not at chimney discharge) for seven substances, including nitrogen dioxide, carbon monoxide and sulphur dioxide, which are relevant to chp gas engines and fired boilers. This was supplemented in 2007 by DEFRA’s Air Quality Strategy for England, Scotland, Wales and Northern Ireland (DEFRA, 2007). 6.5 Noise Reciprocating engines and their auxiliaries will generate noise that must be attenuated to acceptable levels. The degree of attenuation will depend on the target limits of noise to be achieved: —— in plant room —— in adjacent areas —— at air inlets and exhaust outlets —— at nearby buildings. suppliers should be able to provide noise data for the units which are external to the acoustic enclosure and the exhaust air terminations. Most small-scale chp units will be supplied within acoustic enclosures, which in many cases will be adequate to achieve all required noise targets. chp Additionally, noise levels from other aspects of an installation, in particular the exhaust flues and the venti­ lation and heat rejection systems, will need consider­ation at the feasibility stage. Consideration of the noise impacts of the plant relative to existing background noise levels both inside and outside the building, and within the plant room for health and safety purposes, may affect the design of the development to ensure that potentially adverse effects are minimised. The starting point is to determine the background noise levels by measurement. Acoustic mitigation is discussed in section 9.12. 6.6 Other environmental impacts engines need lubricating oil to maintain efficient operation. This needs to be regularly replaced and appropriate storage provided on-site if the chp engine is being maintained in-house rather than by external contractors. Oil spills can have an adverse effect on the environment and waterways in particular. There is a need to consider the use of bunded stores and oil interceptors with remote alarms where large volumes of oil are involved. chp There may also be a visible water vapour plume from the exhaust as a result of condensation on cold days and this may be of concern to local residents, even though such a plume indicates good heat recovery conditions. As with the combustion exhaust outlet, consideration must also be given to the ventilation air exhausted from the engine enclosure. This should be discharged to a well ventilated area that will not cause a nuisance; there is a risk of odour, even though it is only heated air. The engine crankcase breather pipe will need to be terminated at a suitable point away from ventilation air intakes. 7 Combined heat and power for buildings Legislation and regulations that impact on CHP viability Key points: reduction in greenhouse gas emissions by 2050, the first such commitment made by any nation. To support the achievement of this target, the Act empowers the Government to set 5-year carbon budgets. The Act also establishes a Committee on Climate Change to advise the Government on the emission reduction target for each carbon budget and progress towards meeting them. There are a number of Regulations that impact on CHP including important financial incentives. The first report of the Committee on Climate Change was published on 1st December 2008. Regulations are subject to change and although this section summarises the main areas of legislation that impact CHP, readers must consult relevant Government websites or the Combined Heat and Power Association (CHPA) for the latest information. This confirmed that an 80% reduction by 2050 was an appropriate target to support global efforts to avoid dangerous climate change, and that the emission reduction target should relate to all greenhouse gases and include emissions from UK aviation and shipping. Regulations associated with the generation, distribution and supply of electricity are also important for CHP systems and early liaison with the local Distribution Network Operator is recommended to establish the interface requirements 7.1 Planning The energy strategy for new buildings is often influenced by local and regional planning policies. The latest policy and draft policies and associated supplementary planning guidance or area development plans should be consulted to establish whether chp is seen as a preferred technology and whether there is the potential for a wider district heating network to be established in the area. If chp is to be incorporated there will be a number of detailed planning considerations. Planning approval will be required for the building and information will need to be provided on emissions, noise and visual impact. For biomass chp, planners will also require information on expected vehicle movements. For large installations a full Environmental Impact Assessment may be required. Planning is currently the responsibility of the Department of Communities and Local Government (DCLG). 7.2 Building Regulations For new buildings in England and Wales, Part L of the Building Regulations* will influence the design of the building fabric, its services and the heat sources used. The ways in which chp, renewable fuels and district heating are treated within the Regulations need to be carefully studied to ensure that the most up to date information is being used. In addition to the Building Regulations Approved Documents there are accompanying Compliance Guides that contain information relevant to chp and district heating. 7.3 Climate Change Act The Climate Change Act 2008 came into force on 26th November 2008. It is significant as it contains a legally binding commitment for the UK to achieve an 80% * Requirements may differ in Scotland and Northern Ireland. The main impact of this legislation is that CO2 reduction targets have considerable influence in overall policy direction. It also shows that there will need to be a progressive reduction in CO2 emissions from the electricity system against which local chp systems will be compared. This means that over time, the CO2 savings from natural gas fired chp are likely to decrease leading to pressures to either improve chp efficiency or convert to alternative renewable fuels. 7.4 Carbon trading: CRC Energy Efficiency Scheme and the EU Emissions Trading System 7.4.1 CRC Energy Efficiency Scheme The CRC Energy Efficiency Scheme (previously known as the Carbon Reduction Commitment) aims to reduce carbon emissions from large commercial and public sector bodies in the UK. ‘Large’ is defined as electricity consumption greater than 6000 MW·h per annum. 7.4.2 EU Emissions Trading Scheme The European Union Emissions Trading Scheme (EU ETS) is a form of market regulation resulting from the EU Directive 2003/87/EC (the ‘Emissions Trading Directive’). Only the larger combustion plants (with a site fuel input greater than 20 MW) are under a mandatory requirement to participate in the EU ETS. If chp is introduced, the fuel use, and hence local CO2 emissions on the site, will increase (but decrease globally) and therefore it is necessary to obtain additional ETS allowances for the site. 7.5 CHP Quality Assurance Programme Three of the fiscal incentives that have historically provided support for chp schemes (namely, exemption from the Climate Change Levy, eligibility for Enhanced Capital Allowances and free allocation of allowances under Phase 2 of the EU Emission Trading Scheme) require that the scheme be certified as ‘good quality chp’. This is a standard under the Combined Heat and Power Quality Assurance (CHPQA) programme (managed by the Department of Energy and Climate Change (DECC)), for which a detailed assessment methodology has been developed. This method­ ology is set out in CHPQA Guidance Notes (CHPQA, Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 28 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 1: Technologies, applications and regulations 2012). The CHPQA methodology was amended in January 2009. Good quality chp must be certified as such by the award of a certificate from the CHPQA (a ‘CHPQA certificate’). CHPQA requires compliant metering and annual performance monitoring. Enhanced Capital Allowances Enhanced Capital Allowances (ECAs) were introduced in 2001 as part of the UK Government’s commitment under the Kyoto Agreement to reduce UK carbon dioxide emissions. ECAs are a 100% first year allowance (fya), which can be claimed in the year the expenditure was incurred on the provision of the qualifying equipment. ECAs can only be claimed on a chp installation, if a Certificate of Energy Efficiency has been issued by the Secretary of State. This certificate can only be issued if the chp installation meets the requirements of the Combined Heat and Power Quality Assurance (CHPQA) standard and obtains quality-certification. The CHPQA Scheme provides a series of guidance notes on compliance; Guidance Note 42: Use of CHPQA to Obtain Enhanced Capital Allowances deals specifically with ECAs and can be found on the CHPQA website (CHPQA, 2012). The rules relating to the claiming of capital allowances are a complex area of the UK tax system. Professional advice should be sought at the initial stages of any chp project where capital allowances are being considered. 7.6 Other financial mechanisms 7.6.1 Renewables Obligation The Renewables Obligation is the main support mechanism of large scale renewable energy schemes in the UK. It imposes a requirement on electricity generators to source an annual percentage of the electricity they supply from renewable sources. This percentage rises annually, and will be approximately 15% by 2015. For each MW·h of renewable energy supplied, the energy supplier receives a tradable Renewables Obligation Certificate (ROC). A supplier must annually surrender sufficient ROCs to cover the required 29 number of MW·h imposed on it under the Renewables Obligation. If insufficient ROCs have been issued to the supplier, the supplier may buy further ROCs on the ROCs market, or pay a charge into the ‘buy-out’ fund. Proceeds in the buy-out fund are annually recycled back to suppliers presenting ROCs. The Government is currently proposing an alternative to ROCs using a ‘Contract for Difference’ (CfD) based incentive model. 7.6.2 Feed-in tariffs The Government has introduced legislation for feed-in tariffs for electricity generated from renewable sources below 5 MWe capacity and for gas-fired chp below 50 kWe. The technologies that currently qualify include micro-chp, defined as less than 2 kWe and biomass chp systems less than 5 MWe. Feed-in tariffs and their scope are subject to change to reflect the latest policy aspirations and the latest position should be checked prior to any economic analysis. 7.6.3 Renewable heat incentive The Government is currently introducing a Renewable Heat Incentive. This would result in additional income for heat delivered from energy sources classed as renewable, including biomass boilers and heat pumps. Gas-fired chp projects will not benefit from this scheme but the heat produced from renewables-fired chp will qualify. 7.7 Parallel operation with DNO system In order to connect the chp in parallel with the public electricity system (the ‘grid’) a Connection Agreement must be in place with the local distribution network operator (dno). The dno will need to approve the operation of the plant with tests to demonstrate that the unit will disconnect from the dno system in the event of a fault to avoid feeding power onto the dno system under fault conditions. The detailed requirements are contained in Engineering Recommendations G/59/2 (ENA, 2011a) and G/83/1 (ENA, 2011b) obtainable from the Energy Networks Association (http://2010.energynetworks.org). A generation licence is only required for exporting more than 10 MW of power. Combined heat and power for buildings Part 2: Project implementation 8 Feasibility studies 8.1 Introduction The object of the feasibility phase of a project is to determine whether or not it is worth the investment of time and resources necessary to develop the initial concept of a chp scheme into an actual engineering project. One important aim is to identify and reject unsuitable schemes at an early stage to avoid abortive costs. At this stage, chp schemes should be compared with other appropriate alternatives, e.g. installing condensing boilers, biomass boilers etc. For chp projects with potential for further development, the feasibility phase will ensure that sufficient consideration is given to acquiring adequate information upon which sound decisions may be based. The feasibility stage, carried out by technical personnel, will marshal the arguments necessary for obtaining financial approval from the relevant nontechnical decision makers. can be considered. At this stage the considerations are related to matching of heat and power demands rather than economic analysis. —— Economic options appraisal: once a technically viable option (or normally more than one option) has been identified, the financial viability may be investigated through an economic appraisal. Again, the aim is to quickly identify projects that are unsuitable and to provide sound arguments for proceeding with those that are. —— Recommendation to proceed to design and tender: the information obtained during the data gathering, initial technical evaluation and economic appraisal stages will form the basis for any recommendation to proceed to design and tender. If the project is identified as currently unsuitable for further consideration the reasons for such rejection should be recorded and other information retained for reconsideration at a later date, should circum­ stances change. Where the project is suitable for further consideration, information should be made available for framing the recommendation to decision makers for the further development of the project. Once the feasibility phase is successfully completed, the project can be developed to detailed design with confidence that the necessary information is to hand and that an economically sound project will result. The client can choose to use either a consultant or equipment supplier for the feasibility study. In either case, the client’s in-house staff will probably need to do much of the groundwork of gathering data on current energy use. schemes may be considered as a retrofit measure in an existing building or included in the plant specification for a new building. In each case, the arguments for and against a chp scheme will be formed by comparison with the appropriate conventional plant alternative. The following sections amplify aspects of these activities. 8.2 chp Figure 8.1 provides an overview of the feasibility process. The key steps involved in the feasibility stage are described briefly below: —— —— —— Project initiation: project initiation may come from many quarters but in essence someone will have made a decision to consider a chp scheme. The drivers for this decision may have been financial, environmental or regulatory. There may be no commitment of funding and only superficial support for the idea; however, the project is now underway. Data gathering: the first task for the project is to gather together the data that will be used to assess viability. For an accurate feasibility study, the scope of the required data is extensive. The higher the quality of data gathered, the greater the accuracy of any study. The process of gathering data should not be regarded as a once-only event, but as an activity that will continue throughout the project as more information becomes available. Initial technical evaluation: when sufficient infor­ mation is available, the project may proceed to a stage when the capacity of any potential chp plant Data gathering of energy demands and system temperatures The scope of data that may form part of any chp scheme investigation can be extensive, from the purely technical aspects of energy use to the financial aspects of project appraisal. Some of the data will be readily available, others may require further investigation. At this stage, approval of the project is not assured but the level of data gathered should be sufficient to progress to subsequent phases. 8.2.1 Energy consumption A minimum understanding of site energy demands is required to make any assessment of the viability of the chp scheme. Some data will be readily available (e.g. quarterly or monthly fuel bills), whereas other data (e.g. energy profiles for a week or a day) may require special data acquisition. The scope of data required should be assessed since the project should not proceed from one stage to the next without sufficient, sound data. Energy consumption will need to be understood in considerable detail for full implementation of a chp scheme. Whereas for conventional power and heating systems, the capacity of the plant installed is determined largely by the maximum demands (which consequently results in the plant operating at part load most of the time), chp schemes require high plant utilisation to achieve the necessary economic viability. Consequently, for selecting a chp scheme, the minimum energy demands in the running Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 30 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation 31 Receive client brief Gather data on energy use Obtain details of site and plantrooms Process data to produce heat and electricity demand profiles Establish energy prices to be used in model Consider physical arrangement and interfaces Construct operating model Capital cost estimates Maintenance cost estimates Optimise CHP size Optimise thermal store Update capital cost estimates for selected scheme Finalise operating model Finalise energy prices and incentives Evironmental appraisal Economic appraisal Figure 8.1 Typical feasibility study flow diagram Reporting period are as important as, and often more important than, the maximum demands. For building applications of chp there are usually significant differences between winter and summer demands. An understanding of these differences will be important in determining the capacity and expected running hours for the selected chp scheme. In the ideal case, data that identify heat and power energy demands at hourly intervals throughout the year will be obtained from monitoring of electricity, heat or gas meters. Where this is the case, it will be relatively easy to optimise the chp size based on a full hour by hour simulation over the year. Data available from monthly energy bills will give a coarser consumption profile that will identify how consumption varies with season. However, these monthly profiles will not give any guidance on how energy consumption profiles vary on a daily or hourly basis. Using monthly data to assess loads available for a chp scheme can be misleading and over-optimistic where there is significant variation in demand over 24 hours (e.g. between day and night). Using monthly average profiles will tend to overestimate the potential operating hours from chp during the shoulder months. Where the scope of data immediately available is not deemed sufficient, particularly with respect to energy consumption, specific energy surveys, temporary metering and audits may be required. If time is available, sample monitoring of meters on representative days (weekday and weekend, heat and power demand data) in each month would be beneficial; otherwise, days in late spring or early autumn should be selected as it is in the shoulder months where greatest accuracy is needed. 8.2.1.1 Electricity demand data For larger sites, electricity half-hourly demand data are normally available from the electricity supply company at the supply meter point. Judgments must be made regarding the suitability of this information; i.e. does the information from the metering point accurately represent the consump­ tion of the building under consideration and are there other buildings served from that point? 8.2.1.2 Combined heat and power for buildings Heat demand data Heat demand information is often available only for fuel supplied on a monthly, or intermittent, basis. In these circumstances, a dedicated monitoring exercise may be required. Ideally, monitoring should be at the point of use and include representative weekdays and weekends. In converting from fuel use to heat demand, a pessimistic boiler efficiency should be assumed. —— distribution layouts —— possible connection points. Future changes to demand Most chp generators in the size range being considered (<1 MWe) will generate at 415 V using step-up or stepdown transformers to achieve other voltages. For larger generators there may be a case for using an hv generator to avoid the cost and space for the transformer. The hv generators are more expensive and a detailed cost comparison will be needed. There will also be staffing implications from the need for qualified hv operators. As well as considering existing energy consumption, consideration should also be given to future changes in consumption. These may be prompted by: Approval from the distribution network operator (dno) to connect the selected chp capacity and to export if needed should be sought at the earliest opportunity. 8.2.1.3 —— implementation measures of various energy efficiency —— creating new facilities —— discontinuing old processes —— changes in operation, organisation or occupancy patterns. The impact of any projected changes must be considered very carefully to assess whether the changes would enhance or detract from the chp scheme viability, and to what extent. These aspects may be evaluated by sensitivity analysis of any calculations, i.e. by reviewing changes to calculated outputs from the selective alteration of key input parameters. 8.2.1.4 Demands in new buildings In the case of new buildings, the heat and power demand profiles must be estimated. Such estimates may be based on a combination of: System fault level information is required in relation to the incoming supply system (information from the dno) and for the building system. The existing fault levels will determine whether or not there is fault capacity to accept a new generator without requiring enhancements or upgrades to system wiring or switchgear. Where system fault levels are inadequate, the necessary alterations to switchgear and wiring may make the project uneconomic. The electrical distribution system and switchgear should be examined to identify likely points into which the generated supply may be fed and the extent of any additional switchgear required. Likely points may be spare switchgear or extendible boards. If the anticipated site loads are such that the chp will need to export electricity at certain times an export agreement and a power purchase agreement will be required. 8.2.2.2 Heat systems —— building design data —— dynamic simulation model of the building For the heat distribution systems the following should be identified: —— projected occupancy patterns —— —— benchmark data from similar buildings heating systems in use, e.g. hws, steam, warm air —— empirical data from energy models or consumption codes for different buildings by type of use, floor area, volume, etc. —— operating temperatures, especially return tempera­ tures —— users, peak loads and load profiles —— existing plant performance, age and condition. The confidence level attached to the demand profiles derived must be recognised when selecting a suitable chp plant rating. 8.2.2 Energy systems Knowledge is required not only of the raw energy consumption data, but also of how the energy is transferred around the building. 8.2.2.1 Electrical systems For electricity, the following information is required: —— supply voltage, e.g. 11 kV/415 V —— system voltages used in building, e.g. 415 V —— system fault levels —— switchgear arrangements lthw, mthw, hthw, Heat from chp is most effectively absorbed in systems with an operating temperature of 80 ºC or below, and with a near constant demand through the year. Control and instrumentation systems also need consider­ ation to identify the extent to which any new plant could or should be integrated into existing systems. At the simplest level, a chp unit would be self-monitored by its own standalone controls, while at the most sophisticated level the chp scheme will be remotely monitored by a physically distant service organisation and be fully integrated with the building’s own building energy management system (bems). The initial task is to identify the state of current control systems and to determine in broad terms what the control and operating strategies will be for the prospective new chp scheme. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 32 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation 8.2.3 33 Fuel Fuel options for most chp plant are natural gas, lpg, gas oil, biogas and liquid biofuels. For the majority of installations, natural gas will be the fuel of first choice as it can be supplied virtually on demand and requires no on-site storage facility. Exhaust gas loss 19% Heat loss from engine and generator 5% Electricity 34% generated Fuel 100% At this stage it is necessary to establish the condition of any existing gas supply arrangement, in respect of: —— pipe size, pressure, capacity —— metering capacity —— supply agreement details —— users of gas on site. availability and cost of providing supply —— where gas could be used on site (apart from plant). Figure 8.2 Energy flows in a typical gas engine chp unit (turbocharged) can be used to provide low temperature heating (see also Table 9.2). chp The likely capacity of gas supply required to support the chp plant and other users should be estimated. Where the supply pressure available is not adequate, a gas pressure booster may be required. This will impact upon energy consumption, space and cost. Contracts for the supply of gas should be investigated. Contracts may be for firm or, for the larger units, interrup­ tible supplies. Interruptible gas is cheaper than a firm gas supply but the likely chance of a gas interruption should be considered and taken into account; unless a standby fuel is available, the use of interruptible gas may result in consider­ able expenditure in importing electricity during peak tariff periods. Dual-fuel options, which will necessitate some liquid fuel storage on site, may be considered for engines over 500 kWe. These engines benefit from higher electrical efficiency but still require some pilot oil use when running on gas. They can be run only on oil to take advantage of an interruptible gas supply. 8.3 Useful heat recovery 6% Intercooler heat rejection Where gas is not immediately available, it is necessary to establish: —— 36% CHP performance, heat recovery options An early decision will be the operating temperatures and the impact on the chp design. Consideration should be given to whether heat recovery from the intercooler is feasible and the amount of heat recovery possible from the exhaust gases. Figure 8.2 shows the energy flows from a chp unit and the potential for heat recovery. 8.4 Optimum sizing of CHP Once the heat and power demands have been established the optimum chp size can be determined following the approach outlined in section 4.4. An operating model will be set up to enable the annual energy flows arising from chp operation to be determined, from which operating costs and savings can be evaluated. This operating model needs to be subjected to sensitivity runs on energy prices and also on variations in site energy demands. As it is not possible to continuously match heat and power demands, the planned operating strategy will often require one or more of the following: —— additional heat from conventional boilers or heat rejection —— power importing or exporting —— modulation of chp output. The costs for a number of different operating strategies may need to be tested prior to carrying out final optimisation runs, for example: —— Is exporting power more worthwhile than part-load operation? —— Is heat rejection more worthwhile than part-load operation? —— Is operating at night beneficial? —— What is the best way to utilise a thermal store? Particular attention should be paid to exhaust gas temperature if high grade heat is required on site, e.g. to raise steam. chp gas engines are fitted with increasingly larger turbochargers in order to maximise the chp electrical efficiency. This removes more energy from the exhaust gases and hence lowers the exhaust gas temperature. Lower temperature exhaust reduces the potential for high temperature heat generation, especially steam raising. 8.5 In some cases the surplus heat from the engine that is normally ventilated out of the chp enclosure or plant room —— Thermal storage The feasibility study should consider the benefits of thermal storage and assess the optimum size and the practical issues associated with installing the storage vessel. The size of the store will be influenced by the selection of operating temperatures. The potential benefits of a thermal store are as follows: It enables peaks in demand to be met by the chp by smoothing the demand profile. Combined heat and power for buildings —— Night-time heat demands may be met with surplus chp heat produced during the day (as the electricity value at night is normally insufficient to justify chp operation at night). —— At times of low heat demand (in summer) the chp can be operated for fewer hours but at higher output. (Without a store the demand may be below the chp unit’s acceptable turndown limit) 8.6 Tri-generation (CCHP) The use of heat driven chillers is normally a second stage of a feasibility study, once the case for a chp supplying heat has been established. It is rare for the cooling demand to determine the chp capacity so the usual approach is to assess how much surplus heat is available from the chp in summer and how well this matches the cooling demand. The cooling demand profiles also need to be estimated to enable the tri-generation system to be optimised. Absorption chillers have a relatively high capital cost so their operating hours need to be maximised, i.e. the absorption chiller needs to be sized to meet a base load cooling demand. 8.7 Integration with other low carbon technologies Capital cost / (£/kWe) Other technologies to supply heat and power may need to be considered especially for new-build projects and the interaction with the chp system should be quantified to ensure that two technologies are not competing to supply the same demand. 8.8 Capital costs for gas-engine chp will generally fall in specific terms (£/kWe) with the capacity of chp as shown in Figure 8.3. These costs include the supply and installation of the chp assuming the minimum amount of interfacing with or alteration of existing systems which will need to be assessed on a site specific basis. Costs are at 2010 price levels. Maintenance costs are provided in Figure 8.4. Although these are expressed in p/kW·h of electricity generated for comparison purposes it is more typical for maintenance contracts to be written in terms of a fixed cost per hour of operation, so operating at part load will effectively incur additional maintenance costs per unit of energy produced. Generally, specific maintenance costs reduce with the chp capacity. Costs are provided at 2010 price levels. Typical chp unit electrical efficiencies are shown in Figure 8.5. Efficiencies generally rise with the size of unit but there are significant variations for any given size. Efficiencies are given on gcv basis. 2500 8.9 Economic appraisal 2000 8.9.1 Simple payback period 1500 This is the simplest of appraisal techniques and calculates how many years will elapse before the project capital costs have been recovered by the operational cost savings. 1000 A typical economic calculation is shown in Table 8.1 for a 300 kWe plant sized to run for 5000 hours a year. The formulae that can be used in a spreadsheet are given. 500 0 0 1000 1500 2000 2500 CHP electrical capacity / kWe Figure 8.3 Typical capital costs for gas engine chp units (2010 price levels) allowing for minimum interfaces with electrical and heating systems 500 The basis of the calculation is first to compute the saving in any hour of operation from the difference between the conventional cost for producing the same amount of heat and electricity that would be produced by the chp and the chp operating cost (chp fuel + chp maintenance). When the hourly saving has been calculated the annual saving is 2·5 45 40 2·0 Electrical efficiency / % Maintenance cost / (p/kWe·h) Typical capital and maintenance costs and efficiencies for gas-engine CHP 1·5 1·0 0·5 35 30 25 20 15 10 5 0 0 500 1000 1500 2000 CHP electrical capacity / kWe 2500 Figure 8.4 Typical maintenance costs for gas-engine chp units (2010 price levels) 0 0 500 1000 1500 2000 CHP electrical capacity / kWe 2500 Figure 8.5 Typical electrical efficiencies for gas engine chp units with capacity Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 34 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation 35 Table 8.1 Example of estimation of chp savings and simple payback period using a spreadsheet Item Units reference Manual calculation Spreadsheet formula Example Average electrical output kWe A B2 300 Average heat output kWt B B3 450 Overall chp efficiency % C B4 80% kW D=(A+B)/C B5=(B2+B3)/B4 938 Average electricity price p/kW·h E B6 7 Gas/oil price p/kW·h F B7 2 Fuel input (gross cv basis) Conventional boiler efficiency % G B8 80% chp maintenance costs p/kW·h H B9 1.1 chp hours run per year hours J B10 5000 system costs: — capital and installation £ K B12 300 000 L=AÍE/100 M=B/GÍF/100 N=L+M B14=B2*B6/100 B15=(B3/B8)*B7/100 B16=B14+B15 21.00 11.25 32.25 £/h £/h £/h P=DÍF/100 Q=AÍH/100 R=P+Q B18=B5*B7/100 B19=B2*B9/100 B20=B18+B19 18.75 3.3 22.05 benefit: — operating cost savings — annual operating cost savings £/h £/year S=N–R T=SÍJ B22=B16-B20 B23=B22*B10 10.2 51 000 Simple payback period years U=K/T B24=B12/B23 5.9 chp Conventional operating costs: — electricity costs £/h — boiler fuel costs £/h — total conventional operating costs £/h operating costs: — fuel — maintenance — total chp operating costs chp chp simply obtained by multiplying by the operating hours (in this case 5000). The payback period is the capital cost divided by the annual operating saving. The electricity and gas prices used for these calculations is an average price experienced by the user for the operating period. For a more rigorous analysis, it may be necessary to differentiate between energy consumption and costs in winter and summer seasons or by month as a result of different electricity or fuel prices. This example shows a payback period of 5.9 years, which typically would make the project worth investigating further. The accuracy of the final result depends upon the reliability of input information. However, by setting up a spreadsheet model it is a straightforward process to test the sensitivity of the result to fluctuations in input parameters such as the gas or electricity price. Each organisation will have its own project evaluation criteria. It should be noted that simple payback approach assumes constant operational savings and ignores the project benefits beyond the payback period (which may be higher if energy prices rise). Where multiple investment options are being compared a simple payback period is also of limited value as the capital investments may vary significantly. For a project that could generate variable revenues over a period in excess of 10 years, or where there are many options to evaluate, a discounted cashflow analysis is more appropriate. 8.9.2 Discounted cashflow analysis An alternative to the simple payback approach is the use of discounted cashflow analysis. The underlying principle is that the value of money is time dependent. For example, the buying power of £1 today is greater than the buying power of £1 in five years’ time. This is not as a result of inflation but because the £1 today can be invested to provide additional value in the future. The reduction in future value is calculated by the use of a discount rate: Discount factor in each year = 1 / (1 + r)n where r is the discount rate (%) and n is the number of years after initial investment. For example, at a discount rate of 8%, an income of £1 in five years’ time will be worth £0.68. In comparing a range of options such as several different sizes of chp and other low carbon heat source investments there are two measures that can be used: —— net present value (npv) —— internal rate of return (irr) The npv can be seen as the total value of the project expressed in terms of a sum of money at today’s value, equivalent to a capital cost. If the npv is positive then the project is viable. The npv calculation requires the discount rate and the term of the analysis to be defined. Combined heat and power for buildings Table 8.2 Illustration of calculation of net present value (npv) and internal rate of return (irr) Item Year 0 Capital cost Operating saving Cashflow 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 300 000 — 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 –300 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 51 000 Discount rate 8% Discount factor — Discounted cashflow 0.926 0.857 0.794 0.735 0.681 0.630 0.583 0.540 0.500 0.463 0.429 0.397 0.368 0.340 0.315 –300 000 47 222 43 724 40 485 37 487 34 710 32 139 29 758 27 554 25 513 23 623 21 873 20 253 18 753 17 364 16 077 Net present value 136 533 Internal rate of return 14.9% The irr is the discount rate that would result in a zero npv and also requires the term of the analysis to be defined. Both of these functions are available within Microsoft® Excel; the ‘Help’ function will provide further guidance. Each organisation will have a view on what discount rate should be employed, depending on their cost of capital and attitude to the perceived project risks. The starting point of npv calculations is the identification of the cash inflows and outflows for each year under consideration. The npv calculations shown in Table 8.2 analyse the same 300 kWe chp plant over a projected life of 15 years. In this example, operating savings have been assumed to be constant over the period but these could be changed depending on the particular installation. For example, maintenance costs may be predicted to rise over the 15 year period as the chp ages or electricity and gas prices may be predicted to rise. The final value of npv represents the cash benefit at today’s value of implementing the chp scheme as opposed to retaining conventional arrangements. In this example, the benefit is £136 553. When a number of projects or schemes are being considered, the one with the highest npv would be preferred. The irr value for the project identifies the return that money invested elsewhere would have to earn to give a better return than the chosen project. Many companies and organisations will set a ‘hurdle’ rate of return that must be achieved for a project to receive funding. The threshold rate may vary depending on the type of project being considered. Table 8.2 also shows the results of calculating the irr, which in this case is 14.9%. 8.9.3 Sensitivity of results For any appraisal technique, care must be taken regarding the reliability of input data and the sensitivity of results to changes. When using computer based spreadsheets, the recalculation of results for various inputs is a simple matter. The aim of any sensitivity analysis is to give confidence in the project viability under variations in key project parameters including: —— heat and power demands —— gas and electricity prices —— capital expenditure. As discussed in section 7 there may be incentive schemes available that need to be included in the economic appraisal. The availability of such schemes should be checked prior to carrying out each analysis. 8.10 Financing options 8.10.1 Capital purchase Under capital purchase the user of the chp scheme finances the installation. By so doing the user gains all the financial benefits and the greatest return on investment, but also takes on all the risks. The decision on whether to pursue the capital purchase route will depend on the availability of capital or directly financed borrowing, other demands for capital, and the company view on the management and risks associated with the chp scheme. Any bid for funds for capital purchase will undoubtedly need a well presented financial case to demonstrate that the project meets the necessary internal funding criteria. There may also be a lead time between bidding and funds being made available. A risk assessment should be carried out. Some risks can be mitigated through contracts, e.g. a guaranteed fixed price construction contract, a long-term maintenance contract and longer-term gas or electricity contracts. 8.10.2 Equipment supplier finance (ESF) Under esf schemes, the equipment supplier finances the purchase and installation of the chp plant, at no initial cost to the user, and retains ownership of the plant. The user normally pays for the fuel used by the chp plant, buys electricity from the supplier, and receives the chp heat for no additional charge. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 36 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation 37 The equipment supplier recovers the cost of the chp unit by charging for the generated electricity over a fixed contract period of up to 15 years. No charge is levied for heat recovered from the chp plant. The electricity price may be at an agreed tariff, or at a set discount to imported electricity. esf contracts will normally be long term, 10 to 15 years, and so will need agreed review mechanisms to keep the benefits of the project equitable to both user and supplier. Electricity price charges may be varied based on an agreed indexing formula. chp equipment suppliers often have esf schemes under their own brand name, which include design, installation, monitoring and maintenance. The availability of a number of such schemes opens the opportunity for competitive tendering for esf. Whichever esf scheme is chosen, the following factors should be carefully considered: —— what is included: equipment, modifications, fuels —— what is excluded: equipment, modifications, fuels —— performance guarantees —— payments for non-availability from supplier —— payments for poor efficiency —— payments if the user cannot take the outputs —— monitoring and maintenance arrangements (including breakdown repairs and planned overhauls) —— length of contract (normally >10 years) —— price, including standing and unit charges —— basis of price calculation: • price review mechanism • responsibility for CHPQA returns licences, approvals, — technical and financial soundness of the supplier — termination of contract, at full term or before — ownership of plant at termination — condition of plant at termination — options to buy chp plant before contract end. The esf contract may contain some statement of guaranteed performance, i.e. guaranteed number of hours running per year and guaranteed power output, backed up by an agreed scale of charges if performance targets are not achieved, but the principle is that payments are only made for the energy supplied. Achievement of performance targets, and hence liability for non-performance, is not solely the responsibility of the esf provider. For instance, the contract may commit the user to accepting all the heat energy from the engine. If the user cannot utilise the heat, and heat rejection equipment has not been installed, the plant will shut down on overtemperature. This situation may be caused by: —— reductions in building demand following changes in usage patterns —— implementation of other energy saving measures —— facilities being taken out of use for major renovation, e.g. swimming pool repairs. In these circumstances, the liability for non-performance of the chp plant will rest with the user, not the esf provider. Some chp users have started with an esf arrangement but upon seeing the reliability and financial benefit of the chp plant have purchased the plant outright from the esf provider. In order that this option is available, the original contract should include mechanisms for making such a change. To assist this process, a schedule of plant values for each year of the contract may be included. Ultimately, an esf arrangement should represent a partnership between supplier and user wherein the supplier is able to recover the capital outlay in a reasonable period and the user achieves acceptable savings. 8.10.3 Contract energy management (CEM) Contract energy management (cem) is an extension of esf schemes to a point where the cem company takes much greater responsibility for the system, including purchase of fuels and, in many cases, operation and maintenance of the entire building energy systems, with the user buying the energy provided. cem schemes will often form part of a total energy supply service, part of which is chp. The company may not be an equipment supplier but a service company specialising in the installation and operation of energy plant. The cem company, which is funding the capital elements of the project, has to recover its investments through the term of the contract and make an appropriate profit. cem arrangements may be one of the following options: —— fixed fee: services are supplied for a fixed charge irrespective of usage —— energy supply: the user agrees to buy a certain quantity of energy at an agreed unit price —— shared savings: cem company and user share the chp savings benefits. The essence of a cem scheme is for a partnership between the cem provider and user as with esf. Normally, on termination of the cem contract, ownership of the plant transfers to the user. This may be when the plant is 10 to 15 years old. The user needs to ensure, during original contract negotiations, that at contract termination the plant will be in a fit state for continued useful life and not in immediate need of major refurbishment or replacement. 8.10.4 Energy service companies (ESCOs) An esco is a further stage in contracting out energy facilities. Under esco agreements the end user will define the energy needs in terms of delivered result, e.g: —— specified internal room temperatures —— specified levels of illumination. The esco then undertakes to provide the service in a costeffective manner. Under these arrangements the esco may undertake: Combined heat and power for buildings —— installation of energy efficient plant, which may include chp plant (h) —— operation and maintenance of energy producing plant —— maintenance of energy consuming plant —— implementation of energy efficiency measures to the building fabric, e.g. thermal insulation. The aim is to secure funding approval to proceed to full system specification, at which point, with more accurate information to hand, the economic appraisal may be re-run for confirmation of funding approval before going to contract. ‘Energy performance contracting’ is a further type of contract in which chp can be integrated. 8.10.5 Leasing Leasing arrangements will provide financing for a chp scheme, but will not confer any of the operating advantages of esf or cem. Forms of lease commonly available include: —— lease purchase, in which the client owns the plant on expiry of the lease —— operating lease, where the client is only effectively renting the chp plant with no prospect of ownership. In all cases options for leasing would need careful scrutiny by suitably qualified people. Joint ventures 8.10.6 A joint venture is where potential chp users and possibly suppliers enter a funding partnership to install a chp scheme. Such arrangements may beneficially introduce an appropriate range of expertise. Where more than one potential chp user is involved, it may bring a complementary pattern of heat and power demand that no single user could provide. A potential disadvantage is that is that they can be costly, complex and time consuming to arrange. financing options. At any stage in the foregoing process, the scheme may be determined to be unsuitable for development. In such circumstances, the evidence for rejection should be reviewed to assess whether there are other conditions which would make the scheme viable, for example: —— changes in operating profile —— inclusion or exclusion of other buildings —— reassessment of financial criteria. If the project is to be rejected, the reasons for that decision should be recorded and retained with sufficient information to allow a review after a period of time, or when other factors alter. 8.11.2 Statement of requirements The final task at the feasibility stage is to write the outline statement of requirements that will identify the key features of the proposed chp scheme, e.g: —— heat and power rating (acceptable range) —— operating hours per day —— requirement for modulation of output, following heat or power demands —— requirement for heat rejection 8.11 Feasibility report —— fuel supply 8.11.1 Recommendation —— requirement for operation on mains failure —— uses of heat —— whether heat driven chillers are included —— location of chp plant and auxiliaries —— route of exhaust, pipework and cabling systems —— provision of thermal storage —— compatibility with existing heating systems and controls or modifications required —— noise and vibration requirements —— arrangement for connection to electrical system —— outline control requirements —— outline maintenance strategy, in-house or contract —— heat or power export —— design and procurement strategies. With the benefit of the economic appraisal and with knowledge of the organisation’s requirements for consideration of funding, all necessary information should now be available to present to management a report that should outline: (a) the technical solution: • chp • operating pattern • how it will be installed • modifications needed to existing systems • how it will be maintained capacity (b) project capital costs (c) project operating savings (d) energy consumption savings (e) CO2 savings (f) other relevant issues, e.g. environmental impacts (g) economic appraisal results This statement forms the essential detail upon which the subsequent design will be based. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 38 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 39 Part 2: Project implementation 9 Design 9.1 Allocation of responsibilities The design process ultimately leads to the detailed specification of all aspects of the chp scheme, during the course of which various choices and decisions will be made. Before the specification is written, the division of responsibilities not only for the design but also for the installation, operation and maintenance of the plant needs to be decided. Only when these decisions have been made can the specification cover all aspects in a consistent manner. It is possible to keep some options open until further information on the costs of the options is available, since the selection will depend on a consideration of the benefits, as well as the risks, associated with each option. The responsibility for the design and specification may be divided among: —— client’s engineer —— consulting engineer —— main contractor —— chp supplier. The client needs to nominate at least one responsible organisation to the following activities: —— Initial design: this may be carried out by the client’s engineer or the consulting engineer. The output would be a concept design or performance specification. —— Detailed design: this may be carried out by the client’s engineer or consulting engineer if using a standard construction contract or the main contractor or chp supplier if using a ‘design and build’ type of contract. The chp supplier will design the chp package. A main contractor is more frequently used when the project involves more extended scope of work including for example a building or district heating. In some cases the consulting engineer may be novated to the main contractor to maintain design continuity. —— Tender action: this would be carried out by the client supported by the consulting engineer. Life cycle costs should be compared, including chp main­ tenance. —— Installation and construction: the main contractor or supplier would be responsible for the instal­ lation of the chp. The chp supplier would normally be appointed for commissioning even if they were not directly involved in the installation. Where there is a complex controls interface the main contractor will also need to be closely involved at the commissioning stage. chp —— Operation and maintenance: a suitable division of responsibility would need to be agreed between the client and the chp supplier (see also section 12.3.3). The choice of who undertakes each element of the project may be biased by organisational preferences and by the scale of the project. A single small chp plant (<100 kWe) in a local swimming pool may not warrant the involvement of consultants. A hotel chain considering chp schemes for several sites may benefit from a consultant’s input and from a broader choice of equipment suppliers. It is often the case that the main contractor route is followed for more complex installations and in some cases the main contractor may also be appointed as an energy services company (esco) to operate the scheme under a long-term contract. In the latter case there is clearly an advantage in placing the design responsibility with the esco. 9.2 Health and safety aspects The building services engineer, or others within the organisation, must ensure compliance with all current health and safety legislation. Items listed have particular relevance to small-scale chp installations: —— Construction (Design and Management) Regulations 2007 —— Electricity at Work Regulations 1989 —— Gas Safety (Installation and Use) Regulations 1998 —— Control of Noise at Work Regulations 2005 The following outlines some of the relevant points of each of the above regulations; the reader must consult the regulations and comply fully with them. 9.2.1 Construction (Design and Management) Regulations 2007 The ‘CDM Regulations’ require the appointment by the client of a planning co-ordinator, whose role is to ensure that health and safety risks associated with the construction, operation and demolition have been identified and mitigated initially through the design phase. Any risks that cannot be mitigated need to be documented and passed through to the contractor and ultimately to the owner and occupier. Designers will be appointed to carry out design risk assessments. The use of chp will bring some additional potential risks, especially in the area of operation, as regular specialist maintenance will be required. Storage and handling of materials and safe access will be important issues. 9.2.2 Electricity at Work Regulations 1989 There is no mandatory scheme for the registration of electrical contractors but there are several recognised bodies to which electrical contractors may belong. These include: —— National Inspection Installation —— Electrical Contractors Association —— Electrical Contractors Association (Scotland) —— National Association of Professional Inspectors and Testers. 9.2.3 Council for Electrical Gas Safety (Installation and Use) Regulations 1998 The Gas Safety (Installation and Use) Regulations 1998 require anyone installing and connecting gas fired plant in domestic and commercial premises (e.g. schools, hospitals, Combined heat and power for buildings offices) to be registered with the Gas Safe Register for the relevant equipment. Gas fired chp engines implicitly have a risk of explosion from gas leakage. This risk may be small, but it cannot be ignored. Protective measures must be included from inception and may include the following: —— —— Dilution ventilation: even where there is adequate ventilation to cool the engine, care must be taken to ensure that there are no areas with little or no air movement where gas may build up to dangerous levels. Gas leakage detection equipment: this will be linked to audible and visible alarm systems and to the engine control system. At a predetermined low level, alarms and warnings should be activated. At higher levels, the plant should shut down automatically. 9.2.4 Control of Noise at Work Regulations chp plant generates high levels of noise but, by the provision of acoustic enclosures, the noise hazard may be minimised. Chapter 5 of CIBSE Guide B (CIBSE, 2001–2) provides details on the Control of Noise at Work Regulations 2005. 9.3 Energy balance for CHP and heat recovery systems engines liberate heat as the result of the combustion of fuel. The heat that is not converted to electrical output may be recovered at various temperatures as shown in Table 9.2 (typical figures, data will vary between chp units). chp Heat recovery, normally by heat exchanger to the appropriate building services circuits, is dependent on being able to match the building services and engine parameters. The overall thermal efficiency of the chp scheme may be as high as 90% where suitable applications exist with low temperature heat demands. In many applications, however, it is not possible to utilise all the available heat, and a lower overall efficiency will be achieved. Figure 9.1 shows a typical arrangement of a heat recovery circuit from a gas engine chp unit. Figure 9.1 illustrates the following features: —— exhaust heat exchanger is in series with jacket cooler Combustion air Heat rejection Exhaust gases Turbocharger Exhaust heat exchanger Table 9.2 Typical heat energy for two gas-engines Item Percentage of input energy available for heat recovery (gcv basis) Turbocharged engine (500 kWe) Naturally aspirated engine (90 kWe) Exhaust gases (c. 450–120 °C) 21% 17% Jacket and oil cooling (80–95 °C) 15% 33% After-coolers (45 °C) 6% n/a Alternator and engine block radiation (30 °C) 5% 5% Heat remaining in flue gases (<120 °C) 19% 15% (Electrical generation 34% 30%) —— heat rejection from aftercooler is available at all times —— heat rejection from the main chp-side heat recovery circuit can be included as an option, frost protection must be considered. More complex circuits are available when it is necessary to supply heat at two different temperatures, for example low pressure steam could be supplied from the exhaust heat exchanger and low temperature hot water from the engine jacket circuit. On larger engines there may be two or three stages of turbocharging and some of the aftercooler heat can be usefully recovered. Even on smaller engines, if a sufficiently low return temperature is maintained under all demand conditions, the intercooler heat can be included in the heat recovery circuits. For exhaust gas heat recovery, a shell-and-tube heat exchanger is placed in the exhaust stream close to the engine. For jacket water heat recovery, a plate heat exchanger or similar is placed between the engine cooling circuit and the building service being heated, usually the main lthw circuit. The rating of heat rejection equipment will depend on whether it is required to reject all of the engine heat, (i.e. so the chp can run at full output in electricity only mode) or only a specified proportion of the heat is rejected (i.e. to enable some flexibility of operation). This in turn will be determined from assessments of the minimum heat loads that may be expected from the building in planned Heat rejection (optional) Gasengine jacket To building heating system Oil cooler Start-up valve Typical limit of CHP unit supply Figure 9.1 Typical heat recovery schematic for gas-engine chp Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 40 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation 41 operating periods. If the chp plant is to be used as a standby generator, full heat rejection capacity is required. As an alternative to heat rejection from an air cooler, exhaust gases can be diverted from the exhaust heat exchanger by means of a bypass stack. This is more commonly used for gas turbines where all of the heat is recovered from the exhaust gases. Boiler Heat load Boiler X 9.4 System design: interfaces with heating circuit CHP As discussed in section 4.5, there are a number of key objectives for the integration of chp into a heating system: Position A —— that the chp unit should operate in preference to the boilers (when it is economic to do so) —— that when boilers also need to be used to meet the heat demand the chp unit output remains at its maximum heat output Note: If thermal store used then a non-return valve is required at point X —— that the heat recovery from the chp unit is optimised Figure 9.2 —— that the chp unit is always able to generate useful heat even at part load —— that the heating system is designed so that return temperatures do not result in the chp unit shutting down unnecessarily —— that the efficiency of the boilers is not significantly worsened by the addition of the chp. It is important to understand how the building heating system has been designed. For example, heating systems might comprise a variable volume system using two-port control valves and variable speed pumps or a constant volume system using three-port control valves and fixed speed pumps. Either of these systems may be constant temperature or variable temperature (weather compensated). The boiler circuit may have a common primary pump or each boiler may be separately pumped. There may be a common ‘low loss header’ with multiple flows and returns. There may be a mix of systems installed on larger sites/ buildings. Part of the analysis of the heating system should involve a consideration of operating temperatures to understand how flow temperatures can be varied and, more importantly, the likely variation of return temperatures which are solely a function of the building heating systems and controls. There are two principal ways of integrating the into a heating circuit: —— in series with the boilers —— in parallel with the boilers. 9.4.1 chp unit Series arrangement In this design (see Figure 9.2), the chp unit is connected to either the common return supplying the boilers (position A) or the common return from the heating system (position B). The chp pump ensures a constant flow to the chp unit. As this connection involves minimal impact on the boiler circuit and its controls it is commonly used when retrofitting chp into an existing building. Thermal store T Hot T layer T T Cold layer T T chp CHP Position B located in series with boilers If the heating system uses variable flow control then the return temperature will be approximately constant. When the flow rate drops below that of the chp flow rate some recirculation of chp flow will occur leading to higher temperatures onto the chp and part load operation. If the heating system is a constant flow system then the return temperature will increase under part-load, unless weather compensation is used, again resulting in part load operation of the chp to match the load. The benefit of this system is that the chp unit is always used in preference to the boilers (meeting objective 1, see section 4.5). If the required flow temperature is achieved by the chp the boilers will not fire as they are controlled by the boiler thermostats. The boiler thermostat should be set a few degrees lower than the chp supply temperature. A disadvantage of this circuit is that, as the return temperature will be increased by the injection of heat from the chp, any benefit from the use of condensing boilers to meet the remaining heat demand is likely to be significantly reduced. The addition of chp in series with condensing boilers could lead to a loss of efficiency of the boilers. The chp will remain at maximum output at times of high heat demand as it will continue to receive a constant flow of water and will be unaffected by the boiler operation, thus meeting objective 2. To optimise the heat recovery from the chp unit (objective 3) the selection of operating temperatures for the heating circuit need to be considered. If heat recovery from the intercooler is to be achieved, consistently low return temperatures will be needed (typically 40 ºC to 45 ºC). Low flow and return temperatures will also enable maximum heat recovery from the exhaust gases. If the chp unit is to continue to operate with maximum heat recovery under part-load, the return temperature must not rise above the manufacturer’s set point at which part load operation commences (typically 75–80 ºC). This operating limit should be checked with the chp supplier. Although the chp unit is connected to the lowest temperature part of the heating circuit, it is still possible Combined heat and power for buildings that the chp will modulate down or turn off if the return temperature is allowed to rise under part-load (objective 4). With constant volume circuits and three-port valves this could easily occur. The result would be that the chp modulates down and ultimately turns off even though there is sufficient load to maintain it in operation. This situation should be avoided by changing at least part of the system to two-port controls to limit recirculation and to check that there are no fixed bypasses in the system. If weather compensation is used then the flow and return temperatures will be lower under part-load and the risk of the chp turning off unnecessarily is reduced. It will generally be better to install the chp in a common return before the low loss header (position B in Figure 9.2) to avoid recirculation via the header. This may involve significant changes to pipework in order to combine the returns from several circuits. Flow header CHP Boiler Boiler Heat load DPS Variable speed pumps Pumps are controlled in sequence to ensure maximum heat from CHP and to control flow from flow header to return header to near zero Figure 9.3 chp Return header DPS = differential pressure sensor connected in parallel with boilers T A thermal store can be added to this circuit as shown in Figure 9.2 with an additional pump in the circuit. The store discharge pump can then be sized to deliver more flow than the chp plant potentially meeting peak demands from the site. 9.4.2 T T CHP Boiler Objective 2 requires the chp heat output to be maintained when the boilers are operating, which is more complex to achieve with this circuit especially where the capacity of the first boiler to be enabled is similar to or greater than that of the chp. If there is a low loss header in the circuit, the chp flow rate and boiler flow rate would be maintained but the return water temperature would rise as a result of recirculation of flow water into the return via the header. As a result, the chp would modulate down and the load would be shared between the chp and the boilers. To avoid this problem and maintain the chp heat output at maximum output the flow rate through the boiler would need to be controlled, either with a modulating valve or a variable speed pump so as to prevent the recirculation flow in the header and thus maintain the return temperature onto the chp unit. A suitable control signal could be provided from the difference in temperature between the return water from the load and the return water from the header. However, this would be difficult to achieve if there are multiple zone circuits that may be designed with different return temperatures. A better solution would be to split the header into two parts (flow and return) and arrange for a bypass to be installed with a flow sensor so that the recirculation flow can be measured directly, e.g. with an orifice plate or regulating valve. The controls will also need to be set such that any minimum flow rate required through the boiler (as defined by the manufacturer) is always achieved once the boiler is enabled. This circuit is shown in Figure 9.3. The above controls issues are more easily resolved when there is a thermal store in the circuit. In this case the excess flow when the boiler operates can be accommodated by the thermal store and the boiler can be turned on and off to maintain the top of the store at a set temperature without Heat load T T Parallel arrangement In this design, the chp unit is connected between flow and return in parallel with the boilers. Objective 1 can be achieved by designating the chp unit as the lead boiler in the boiler sequencer controls. Boiler Thermal store Hot layer Cool layer T Figure 9.4 chp connected in parallel with thermal store affecting the running of the chp (see Figure 9.4). Further details on the control of a thermal store with chp are given below. Optimising the heat recovery (objective 3) can be achieved with this circuit provided the system temperatures are selected appropriately and preferably a variable volume system is used so that return temperatures are maintained at low levels. The system can incorporate condensing boilers as the chp will not raise the return temperature onto the boilers. If a common primary pump is used there will need to be motorised valves on the chp unit and boilers to control the flow to each heating unit but separate pumps for each heat source would normally be a more efficient pumping arrangement. In both of these circuits, if there is a heat rejection circuit incorporated this should be interlocked with the boiler controls to prevent boiler firing if the chp heat is not being fully utilised. 9.4.3 Operation of CHP with a thermal store A thermal store will only be successful with a variable flow building heating system that can maintain low and constant return temperatures so that the stored energy is maximised. The simplest form of a thermal store operates automatically as it is inherently self balancing. When the demand for heat is less than the heat output of the chp there will be surplus flow from the chp into the store and the store will fill with the flow water. When the demand is greater than the chp output there will be insufficient flow from the chp and some water will flow out of the store to meet the demand. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 42 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation The chp controls will be set so as to fill the store and turn the chp off when it is nearly fully charged with water at the flow temperature. The chp will turn on again when the temperature at or near the top of the store is below a set point and the store is nearly fully discharged, giving ‘room’ for the chp to generate again. There is no benefit in storing boiler heat so the boilers should be controlled to maintain the top of the store at the required flow temperature with this control set-point a few degrees below that of the chp set-point. The store is always full of water and relies on the stratification between the hotter flow layer and the cooler return layer. If there is a large difference between these temperatures the degree of mixing between the layers will be reduced. Operation of the store over a period of time will lead to a gradual increase in the depth of the mixing layer. At intervals the store will need to be ‘refreshed’ by filling it completely with water at the flow temperature. This may happen anyway as a result of a normal daily cycle, e.g. at the end of the day the store may be completely full of flow water at high temperature ready for the night period; however at other times it may be necessary to temporarily arrange for the standby boilers or chp to operate in order to completely fill the store. 43 highest temperature part of the circuit upstream of any mixing valves. —— The temperature drop across the absorption chiller on the hot water side can be small and the return temperatures at both full and part load need to be checked against the maximum chp return tempera­ ture. —— The absorption chiller needs to operate against a baseload cooling demand to maximise its running hours. The simplest way to achieve this is to use the absorption chiller to pre-cool the chilled water return to the main electric chillers. —— In analysing the economic case for an absorption chiller in a new-build scheme, a decision needs to be made as to whether the capacity of the main electric chillers will be reduced such that the additional cost for the absorption chiller is the extra-over cost compared to an electric chiller. If the capacity of the electric chillers is reduced then the availability of the chp and absorption chiller in the summer needs to be considered taking account of chp maintenance downtime. 9.6 9.4.4 Control of flow temperature off CHP unit When the chp unit is operating at full output, there will be a nearly constant rise in temperature across the connected heating circuit. The designer will need to consider if this raises issues for the other parts of the circuit. For example, if the return temperature is low under part-load the flow temperature off the chp will also be lower than the design set-point. This could lead to unnecessary boiler firing, less heat being stored in a thermal store or more pumping energy on the distribution system. Normally a fixed flow temperature is required from the chp unit and a mixing circuit should be used to control the flow temperature off the unit by injecting flow water into the return as required. A more detailed discussion of the issues of interfacing chp with boiler systems is given in the BSRIA Guide BG 2/2007 (BSRIA, 2007) and the HVCA Good Practice Guide TR37 (HVCA, 2008). chp suppliers will also be able to provide guidance. 9.4.5 Small-scale CHP systems (<50 kWe) Small-scale chp system suppliers produce a range of packages that incorporate all the necessary controls and often include a thermal store. However, the common issues outlined above still apply, i.e. the need to design heating circuits with lower return temperatures of 50 °C or below, and to avoid recirculation of flow water into the return. 9.5 System design: absorption chillers Absorption chillers can be incorporated as simply another heating demand in the main circuit; however, the following points need to be considered: —— With single effect absorption chillers the capital cost is dependent on the temperature of hot water supplied so the connection should be made to the System design: electrical interface Power from the generator (normally at 415 V, 50 Hz, 3-phase) will be connected to the building’s electrical distribution system at a convenient location. This may be at a spare breaker cubicle on an existing busbar or at a new bus-section within the associated switchgear. In all cases, the building power distribution system must be checked to ensure that system fault levels are not exceeded. If fault levels are likely to be exceeded, additional reinforce­ ment of the distribution system may be required. Where power distribution systems operate at 11 kV then 415 V generators and step-up transformers may be used as an alternative to generation at 11 kV. Low voltage generators and transformers are likely to be the preferred option below 2 MWe. In most cases the chp generator will be connected to the public electricity supply and will be operated in parallel. It is necessary to obtain a Connection Agreement with the local distribution network operator (dno). Contact should be made with the dno as early as possible. The Electricity Networks Association publishes the following guides, which show how the Connection Agreement can be obtained. These guides also refer to the other documents that may be relevant. —— Distributed Generation Connection Guide: A Guide for connecting generation that falls under G59/2 to the distribution network (ENA, 2011a) —— Distributed Generation Connection Guide: A Guide for connecting generation that falls under G83/1 (Stages 1 and 2) to the distribution network (ENA, 2011b). The G83/1 is for chp units below 11.04 kWe 3-phase and 3.68 kWe for single phase. Where a standby power facility is required, special care must be taken to ensure that loads seen by the generator under standby power conditions are within the generator’s Heat output Combined heat and power for buildings Generator protection Load protection Supply protection Synchronisation Building PES Alternator Prime mover M Generator contactor Mains switch Metering Building —— IGEM/UP/6: Application of compressors to natural gas fuel systems (IGEM, 2009b) —— IGEM/UP/9: Application of natural gas and fuel oil systems to gas turbines and supplementary and auxiliaryfired burners (IGEM, 2004) A chp unit must not be specified as a standby generator for safety critical systems as there will be periods when the chp will be on outage for maintenance. A typical connection schematic is shown in Figure 9.5 above. The chp control panel will also provide power to the chp auxiliary equipment. 9.7 Fuel system Natural gas is available in most areas of the UK and to most sites where a chp scheme is likely to be considered. The pressure of the gas may be suitable for smaller spark ignition engines but gas boosters may be required for larger higher efficiency engines. The building services engineer should ensure that the pressure and capacity of the current system are adequate to satisfy the needs of the proposed chp system and other usage on site. If long distances are involved between the gas supply and the chp installation, adequate allowances must be made for pressure drop. If the site supply pressure is marginal or low, it may be possible to negotiate for gas to be supplied at a higher supply pressure instead of installing a pressure booster at site. The capital and operating costs (i.e. electricity use) for gas compressors can be significant, especially for gas turbines where higher pressure gas is required. The minimum equipment configuration and testing necessary for the safe installation of a gas fuelled engine are described in the following publications issued by the Institution of Gas Engineers and Managers: —— IGEM/UP/1: Soundness testing and purging of industrial and commercial gas installations (IGEM, 2005a) —— IGEM/UP/2: Gas installation pipework, boosters and compressors on industrial and commercial premises (IGEM, 2005b) —— IGEM/UP/3: Gas fuelled spark ignition and dual fuel engines (IGEM, undated) —— IGEM/UP/4: Commissioning of gas fired plant on industrial and commercial premises (IGEM, 2009a) PES Figure 9.5 Typical electrical connection arrangement (pes = public electricity supply) Supply LV loads capacity. If there is a shutdown and a need for the gas engine to take on load immediately after starting, the rate at which load is imposed on the unit needs to be carefully controlled. PES supply 9.8 Combustion exhaust system The primary function of the exhaust system is to carry the products of combustion away from the engine safely. As engines are often located in basements, and exhaust outlets are typically at roof level, careful consideration must be given to exhaust duct routing and insulation to contain heat, vibration and noise. Catalytic converters may be included in the exhaust system either separately or combined with silencers. A typical system is shown in Figure 9.6. Care must be taken to ensure that exhaust gases are not re-circulated into the building or engine intake systems. Guidance on the avoidance of recirculation may be found in CIBSE TM21: Minimising pollution at air intakes (CIBSE 1999). The design of the exhaust system must consider the effects of over-pressure and vacuum which can occur during backfires. 9.9 Combustion and ventilation air systems An air supply system is required at the engine for combustion, general cooling and ventilation. The two functions, i.e. cooling air supply and combustion air supply, may be satisfied by common or separate systems. For very small installations (<100 kWe) it may be perfectly satisfactory to draw cooling and combustion air directly from the surrounding plant room without recourse to special ducting, provided the plant room is naturally ventilated. For larger engines, separate fresh air supply ducting is normally used in order to obtain sufficiently cool combustion air and to obtain a cleaner air supply. Since engine power output reduces as charge air temperature increases, care must be taken with the location of combustion air intakes to avoid recirculation. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 44 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation 45 Features of exhaust system: • Long radius bends in exhaust to minimise back pressure • Flexible connections to allow for expansion and vibration • Vibration/noise attenuation measures in pipe supports • Condensate drain traps at appropriate positions • Horizontal sections slope towards drains • All welded construction recommended Absorptive stainless steel silencer Rigid support Sliding support Reactive stainless steel silencer CHP unit Exhaust heat exchanger Condensate trap and drain Condensate trap and drain Figure 9.6 Typical exhaust system Although the majority of the available heat from the engine is recovered, a significant amount of heat radiated from the engine surfaces and rejected from an air-cooled alternator needs to be dissipated. Typically this heat is about 5% of the fuel input (see Table 9.2). This is most easily achieved by providing a once-through ventilation system to the unit enclosure or plant room. Air may be drawn from the plant room; however, this is likely to be at an elevated temperature and may have some contaminants and so an external air supply is preferable. To minimise the electricity use of the ventilation fans low pressure ducts are used and the space for this ductwork and the location of the air inlet and outlet terminations are often critical in determining the location and feasibility of the chp installation. —— modulate output when running to match the heat or power demand, or the electricity tariff —— adjust alternator excitation to achieve a desired power factor —— monitor performance of the engine and shed load or shut down if required —— revert to predetermined safe conditions on any failure or parameter excursion —— connect and disconnect the generator from the building electrical distribution system —— provide power supplies to chp auxiliary equipment. In some cases this heat rejection can be used for low grade process use such as air heating of greenhouses. It would also be possible to reduce the volumes of air, and hence fan power, by using a chiller to cool the air with heat recovery from the chiller condensers, i.e. acting as a heat pump. These functions will be achieved by the chp unit controls however the local bems may be configured to interface with the chp system so that the building owner can have visibility of the chp operation. The key interfaces with the bems are likely to include: 9.10 Control systems —— start/stop signal based on time control to suit the site and the electricity supply contract prices —— Control, instrumentation and monitoring of chp systems is concerned with: status of the chp unit (e.g. started/running/ synchronised/stopped/tripped) —— output of the chp unit (e.g. kW generated) —— ensuring that the efficiently —— —— integrating the heat produced with the building heat systems monitoring of energy meters and circuit temperatures (although these may be directly monitored rather than through an interface with the chp controls). —— synchronising, paralleling and disconnecting the generator safely An overview of the structure of a typical controls system is given in Figure 9.7 below. —— monitoring the chp plant for performance, maintenance and accounting purposes. chp engine runs safely and Systems are typically designed around microprocessor controllers communicating with remote pc-based control and monitoring stations, often at the chp plant supplier’s offices. The control system will be required to: —— stop and start the engine at predetermined times and/or match building loads or electrical tariffs 9.11 Maintenance facilities In designing the chp system provision needs to be made for any facilities required for the maintenance of the equipment. Access to the chp prime mover will be required on a regular basis with sufficient space provided to carry out the work in a safe manner. Where there are multiple chp units it is desirable to be able to maintain one unit whilst the other is in operation, which implies the use of separate acoustic enclosures. Combined heat and power for buildings Figure 9.7 Overview of control systems for chp Distribution switchboard Generator Synchronisation Mains monitoring and protection Metering Generator control, monitoring and protection Engine Engine control, monitoring and protection Fuel system monitoring and protection Fuel system Heat recovery system Heat recovering control, monitoring and protection CHP CHP controls Modem link to remote monitoring and control positions, e.g. maintenance contractor Building heat systems Plant room monitoring and control position There may be a requirement to provide storage facilities for tools and consumables and an early discussion with the chp supplier, who may also be appointed to carry out the maintenance, is recommended. The storage and handling of lubricating oil requires particular attention to minimise health and safety risks during delivery of new and removal of used oil. Larger systems will typically use on-site storage of ‘clean’ and ‘dirty’ oil. 9.12 Mains electricity supply Control of noise and vibration Prime movers used for chp will always require some form of enclosure and mounting to provide attenuation of: —— airborne noise —— structure-borne noise —— exhaust and ventilation systems noise —— vibration from engine feet and pipe systems. In all cases, it is the responsibility of the owner to specify the noise and vibration requirements for the installation. In many cases, packaged solutions that include an acoustic enclosure may be all that is required. However, in other circumstances, such as where very stringent noise limits are required or where transmitted vibration could be a cause for complaint, detailed monitoring and evaluation of the building may be required, together with special attention to use of acoustic treatment and anti-vibration mounts. This is a complex area that will often require specialist advice. BEMS Figure 9.8 opposite illustrates the following measures, which may be required to achieve appropriate noise and vibration attenuation: —— A: a concrete plinth or inertia base isolated from the plant room floor with suitable resilient material —— B: anti-vibration mounts between the plinth and module frame —— C: anti-vibration mounts between the module frame and engine/generator base plate —— D: flexible connections on all pipe systems to and from the engine and generator —— E: generous bends in electrical cables —— F: noise attenuating ducts on the ventilation supply and exhaust to plant room and module —— G: appropriate penetration details to maintain the construction’s sound insulation performance where ducts, pipes, cables, exhaust flues pass through module and plant room boundaries —— H: flexible connection(s) in exhaust flues to accommodate expansion and attenuate vibration —— I: noise/vibration attenuating pipe supports —— J: silencer(s) in exhaust system —— K: acoustic cladding of module —— L: acoustic cladding of plant room walls and ceiling —— M: acoustic cladding of doors with acoustic seals to module and plant room Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 46 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation 47 (I) (G) (N) (J) (N) Figure 9.8 Potential approaches to noise and vibration control (L) (H) (K) (G) (F) (F) (J) (F) (F) (H) (E) Engine (M) Plant room floor (M) Engine and generator bed plate Generator Module bed plate (C) (D) (N) (A) —— (E) Concrete plinth N: vibration-absorbent packing between pipes and pipe clamps. Not all the measures shown will be necessary in every installation. However, if required, a very high degree of noise and vibration attenuation may be achieved. For example a chp unit installed in an office block, directly adjacent to executive facilities, may require a very high degree of attenuation, whereas a chp unit installed in a detached boiler house may require a much lower degree of attenuation. Most small chp units, up to about 500 kWe, will normally be supplied with a dedicated acoustic enclosure. Larger machines may be installed in plant rooms without an acoustic enclosure where the plant room itself is designed for acoustic control. Alternatively a larger engine may have an acoustic enclosure installed on site around the unit. A key issue to consider the provision of a suitable environment for maintenance of the engine with sufficient space and for noise levels to be low enough for a working environment including for the case where multiple units are installed and other chp units may be in operation. Weatherproof acoustic enclosures may also be specified allowing the unit to be installed outside the building on a suitable hardstand. Exhaust noise attenuation can be achieved by the careful selection of silencers. Depending on the location and route of the exhaust, noise may need to be minimised along its route as well as at the outlet. In situations where there are buildings nearby, the problems of minimising transmitted or reflected noise must also be considered. Specialist advice may be required in this area. Flexible connections in pipe systems should be fitted in strict accordance with the manufacturer’s recommendations. The function of the flexible connection is to provide vibration isolation, not to correct for pipe misalignment. If it is used in that manner, it may fail prematurely. In addition to the main chp installation the noise impact from auxiliary equipment will need to be assessed. In particular heat rejection equipment, whether for the main (B) Noise-absorbent layer between frame and plinth heat recovery circuit or the intercooler, can often be overlooked. As the heat rejection equipment needs to be in free air it is difficult to provide further attenuation after the coils and fans have been sized. Detailed guidance on noise and vibration criteria and their control is set down in chapter 5 of CIBSE Guide B (CIBSE, 2001–2). 9.13 Fire and gas detection and protection Whilst fire and gas detection systems are not a mandatory requirement, many buildings’ insurance companies will require some form of protection/detection. At the lowest level, this will be a simple detector linked into the normal building fire alarm/warning system. At the other extreme, fire/gas detectors will be linked to the engine control and gas supply system, as well as the building alarm system. Automatic gas supply shut-off valves will be required where chp units are installed alongside conventional boilers. Where required, automatic module fire suppression systems may also be installed. The necessary level of detection, protection and suppression must be determined for each installation. 9.14 Regulatory compliance and approvals The main regulatory system at present is the Climate Change Levy exemption available for ‘good quality’ chp. To achieve this exemption, annual fuel use, useful heat produced and electricity generated need to be measured using meters that comply with an accuracy standard. Approvals in the form of a connection agreement will need to be obtained from the local district network operator (dno) to connect the chp unit and to export power if this is envisaged. The dno will need to witness the testing of the G59-compliant (ENA, 2011a) controller before permitting operation. Combined heat and power for buildings 9.15 Specification: typical contents for CHP package specification Demarcations between CHP contract and others The most fundamental part of the specification is to define the scope of supply. This is partly achieved by clearly defining demarcation points for: Space available, internal or external siting A ground floor location is recommended. Restrictions on siting the unit and requirements if it is to be installed externally. Consideration needs to be given to the space required for routine maintenance and for the subsequent removal of the chp for major overhauls/repairs. —— heating circuits Fuel supply —— electrical connections The type of fuel available and its supply pressure. —— fuel supply —— flue termination —— ventilation inlet and outlet —— whether interconnecting pipework to heat rejection equipment is included —— bems —— telephone connection for external communication —— make-up water to engine cooling circuit —— lubricating oil storage and delivery system —— drain points —— civil works —— floor finish. interfaces CHP capacity The required capacity of the chp unit(s) will need to be defined. This may be expressed in terms of its electrical or heat output, although the heat capacity is more logical as it is the heat demand that determines the chp size. However, it is important not to be too restrictive about the required capacity as a range can be specified to allow suppliers to offer standard units from which the preferred option can be selected. Voltage generated The generator voltage will need to be specified and, if low voltage is preferred, whether a transformer is to be included as part of the package Exhaust termination A complete exhaust system may be specified including the height at which the exhaust should terminate. Alternatively the limit to the exhaust system from which others will connect will be defined, together with an initial deter­ mination of the acceptable backpressure. Acoustic constraints The acoustic constraints on the design need to be provided, normally following either the planning conditions or recommendations of an acoustic report. NOx limits Allowable NOx limits should be given. Other planning conditions There may be specific planning conditions that need to be met. Fire detection/suppression and interface with main fire detection system Specific requirements for fire detection and suppression including the need for interfacing with main plant room systems. Heating circuit temperatures Controls and mode of operation The flow and return temperatures under design conditions (maximum heat output) need to be given together with the likely range of these under part load conditions. Description of how the plant is expected to be operated to meet heat or electricity demands, to modulate in output and any restrictions on time of operation; anticipated number of starts. Heat rejection requirements The requirements for heat rejection from the unit need to be defined, e.g. whether all of the heat from the unit needs to be capable of being rejected to maintain electricity output. Monitoring and BEMS interface Requirement to provide an interface to a bems for monitoring purposes, e.g. ‘run’, ‘trip’ and meter outputs. Ambient temperatures Metering The maximum and minimum ambient air temperatures at which the heat rejection equipment needs to be designed to should be specified. The meters to be installed should be specified, together with accuracy standards commensurate with CHPQA requirements. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 48 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation 49 Lubricating oil system 9.16 The requirements for handling lubricating oil during changes, and the need for clean and dirty oil storage on site if required. District heating (dh) is increasingly recognised as an important option to deliver low carbon heating supply. In many cases, chp systems are the preferred heat source for dh, although biomass boilers are also used. A full treatment of the design of district heating is not provided here and reference should be made to other guidance, in particular: Delivery Specific constraints to be provided, e.g. availability of lifting equipment, times at which delivery can be made, responsibility for off-loading and positioning. Commissioning Design of district heating —— Technical Guide to District Heating (BRE, 2012) —— Research reports and guides published by the International Energy Agency District Heating and Cooling Annex (IEA, 2011) —— Guidelines for District Heating Substations (Euroheat, 2008). Scope of commissioning activities, requirements to provide information on commissioning including commissioning procedures, any impact on site activities, recording of commissioning results, witnessing by client representative. In developing a district heating system design there are a number of key issues to be considered. Off-site testing The operating temperatures to be used Requirements for testing and acceptance criteria. Arrangement for test including notice to be given to client for witnessing of tests. Whether tests are on-load or functional. Specific requirements for documentation and format of documentation, drawings, manuals, test certificates. systems will be more cost-effective if the temperature difference between flow and return is maximised so that flow rates are reduced. The flow temperature is normally limited to a maximum of 130 °C so that a long life is achieved for the pre-insulated pipe systems. Lower flow temperatures would be more appropriate for gas engine chp systems. Return temperatures should be reduced as far as possible, although an economic balance is reached where low return temperatures would result in higher costs for larger radiators or air handling unit coils than the cost savings on the dh network. It is recommended that, for new systems, radiator circuit temperatures of 70 ºC (flow) and 40 °C (return) are used with a maximum return temperature of 25 °C from instantaneous domestic hot water heat exchangers. Lower temperatures will help ensure that dh systems are compatible with other low carbon heat sources in the future including extraction of heat from steam turbine power stations and large-scale heat pumps. Maintenance contract Whether there is hydraulic separation at the connections to buildings or dwellings On-site testing The requirements for performance tests and reliability tests to be given including acceptance criteria. Procedure to be followed if performance test does not pass and any compensation (liquidated damages payments). Documentation It is recommended that a maintenance contract is offered at the same time as the tender is submitted for the supply of the unit. Key requirements for this contract are to be given including: period of contract, guarantees on availability, principles of compensation and indexing of costs. Training Training to be provided to client’s personnel to be specified. Requirements to liaise with DNO Any requirements to liaise with the dno to arrange witness tests and provide ‘G59’-compliant equipment. Requirements to liaise with others There may be requirements to liaise with other organisations to carry out tests, e.g. Fire Officer. dh The dh system water can be used directly in the building or dwelling heating system, or indirectly by installing a plate heat exchanger. If a heat exchanger is used the dh system is protected from contamination by the building heating system and there is more flexibility in the choice of dh operating temperatures and pressures. However, the additional cost and complexity mean that direct connection is often used, especially for connecting individual dwellings. A direct connection will minimise the return temperature as there is no temperature difference required at the interface, resulting in a small improvement in dh efficiency. In addition, the dh system pressure difference will provide the circulation pressure for the dwelling avoiding the energy use of a secondary pump. The way in which domestic hot water is produced Domestic hot water can be produced using an indirect coil in a cylinder or through an instantaneous plate heat exchanger. The latter will result in much lower return temperatures, which will be of benefit to the dh system. Combined heat and power for buildings The control of design (maximum) flow rates The design of internal pipe distribution in housing An essential requirement of a dh system is to maintain balanced flows, i.e. the flow rate taken by any building or dwelling should be limited to the maximum design value. This is achieved by using differential pressure control valves at each supply point. Where there are significant lengths of distribution pipework within a block of flats care must be taken to prevent heat losses from the pipes and hydraulic interface units causing overheating in summer. Horizontal runs in long unventi­ lated corridors are to be avoided. It is often preferable to use more risers than to rely on horizontal distribution. The aim should be to minimise the lengths of distribution. If risers are located within the dwelling, provision should be made for the risers to be ventilated at high level to ensure unwanted heat can be dissipated in summer. Such ventilation paths can be shut off in winter to enable pipe heat losses to provide useful heat to the building. The use of variable flow control principles It is preferable to adopt a variable volume control system for the dh system and all of the building heating systems connected. This will ensure that pumping energy is minimised through reducing the volume of water to be pumped and the pressure drops to be met, and also reduces heat losses through ensuring that return temperatures remain low under part load conditions. The control of pumps Pumping energy will be more significant in dh systems than small-scale heating circuits and so it is important to design an efficient pumping arrangement. The energy can be minimised by selecting multiple pumps with a range of duties — both flow rate and head, to suit the requirements for the variation in heat demands on the network. Variable speed drives should be used to take full advantage of the variable flow systems. The sizing of distribution pipework Peak design flow rates will be determined from the required space heating and hot water demands. Diversity of demand for space heating will be limited unless the scheme is very large and contains a mix of types of buildings when a diversity factor of 0.7 to 0.8 can be applied. Where domestic hot water is provided by instantaneous heat exchangers a diversity factor can be used for sizing of the local distribution pipework as shown in Figure 9.9. Experience from continental schemes indicates that the BS 6700 (BSI, 2009a) factors are too conservative and Danish Standard DS 439: 2009 (Dansk Standard, 2009) diversity factors are recommended for sizing supplies to multiple dwellings. This standard contains the following equation, which was used to generate Figure 9.9: Pmax = 1.19 N + 18.8 N 0.5 + 17.6 The location of peak and standby boilers As the chp plant will require regular maintenance, it is normal practice to install peak and standby boilers. It is simplest to locate these at the central energy centre. However, if boilers are installed or retained within buildings there would be additional benefits of security of supply and lower dh network costs. The dh network need only be sized to deliver the chp heat, not the peak heat demand in this case. In these cases it may be appropriate for the dh company to offer an interruptible heat supply contract. where Pmax is the total heat rate required for dhw production for the group of dwellings (kW) and N is the number of dwellings. From this equation it can be seen that the heat rate for a single dwelling has been taken as 37.5 kW, which is typical. However, the diversity factors will be similar for larger dhw heat exchangers for dwellings. Pre-insulated pipe systems The design of a building’s heating system and controls has a significant impact on the efficiency and cost-effectiveness of the dh network. A variable volume control approach should be used so that the return temperature on the dh system remains low under part-load. This reduces pumping energy and ensures heat recovery is maximised from chp. It also means that a thermal store will be more feasible. If bypasses are required within the heating system these should be temperature controlled. With an indirect connection system, it is important to ensure that the primary (dh side) flow is also controlled otherwise unnecessary primary circulation will occur leading to higher return temperatures. —— steel carrier pipe, rigid polyurethane insulation, high density polyethylene casing (BS EN 253) (BSI, 2009b) —— cross-linked polyethylene carrier pipe, flexible insulation and outer casing There is a need to define clear demarcation points between the dh system and the building system, both for construction and operation; normally this is defined at the flange of an isolating valve. The building owner would normally own the heat exchanger substation except for the heat meter, which would be owned by the dh company. 1·0 0·9 0·8 0·7 0·6 0·5 0·4 0·3 0·2 0·1 0 1 5 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 There are a number of types of pre-insulated district heating pipework systems: Diversity factor The design of a building’s heating systems Number of dwellings Figure 9.9 Diversity factor for instantaneous domestic hot water heat exchangers Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 50 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation —— 51 polybutylene carrier pipe, flexible insulation and outer casing. —— a statement of deliverables —— guarantees The plastic carrier pipe systems have a degree of flexibility, which means that the smaller diameters can be supplied in rolls of 50 m length, thus reducing the number of joints to be used and enabling ground obstructions to be easily avoided. Generally the heat losses are likely to be higher than for the equivalent steel system. The main benefit is resistance to corrosion. —— a statement of liquidated damages —— quality and acceptance tests —— health and safety —— insurance requirements. A surveillance system is normally incorporated in the steelin-plastic system, which enables ground water ingress into the insulation to be detected and located prior to the onset of external corrosion. This is recommended as it can result in significant savings in dh repair costs. 10 Procurement 10.1 Tendering Tenders sent out to prospective bidders should contain: —— a technical performance specification —— conditions of contract. The purchase of the chp unit is frequently accompanied by the procurement of a maintenance contract. Indeed this is recommended both to ensure that the best expertise is used to maintain the plant and to pass on the risks for poor reliability to the supplier of the unit. The total cost of the maintenance of the unit over 15 years is significant and can be as much as the initial cost of the purchase. So it is important to tender the maintenance contract at the same time as for the supply and installation, and to compare tenders on both aspects of the offer as part of a single life cycle evaluation. 10.1.1 Technical performance specification The technical performance specification is developed from the preceding design stage information. To the greatest extent possible, the specification should identify the outcome or output of any particular feature, not what has to be done to achieve it. The aim of this approach is to clarify the responsibility between purchaser and supplier for the provision of supply and adequacy for purpose. If the purchaser gives a prescriptive description of how a feature is to be achieved and that subsequently fails, then the purchaser, not the supplier, may be liable for the failure. If the purchaser identifies what is required from the system and the supplied system does not meet that requirement, the supplier may be held liable for such failures. 10.1.2 Conditions of contract Conditions of contract may be adopted from any appropriate standard form in accordance with an organisation’s normal practice. MF/1: Model form of general conditions of contract (IMechE, 2010) is suitable for use with chp projects. Whatever form of contract is used the following may be included: —— model conditions 10.1.3 Selection of tenderers The procedures for selecting tenderers will vary between organisations but may involve: —— advertising for potential tenderers through trade or EU journals —— selecting tenderers from known suppliers or approved vendor lists. Certain public sector and utilities contracts must be advertised, under EU rules, normally through the Official Journal of the European Union (OJEU). This will impose time restrictions on the process. Assessment criteria for the selection of potential tenderers may include seeking evidence of: —— relevant experience —— financial status —— insurance status —— quality system accreditation —— capacity to carry out work in desired time-scale —— health and safety record. The objective is to have sufficient tenderers to achieve a realistic level of competition for the works, i.e. where the companies tendering are in genuine competition but where the purchasing organisation’s building services engineer is not overwhelmed by bids. 10.1.4 Tender assessment criteria Tender assessment criteria should be developed in parallel with the invitation to tender (itt). Criteria may include: —— compliance with the itt: • technical, including schedules of exclusions where required • commercial • presentational —— price and life cycle costs —— proposed installation programmes —— proposed payment schedule —— maintenance capability —— guarantees and after sales service. 10.1.5 Invitation to tender The itt should be sent to each potential tenderer with a clear statement of the response time, and the presentation required. Combined heat and power for buildings 10.2 Assessment of tenders —— operating benefits based on guaranteed performance efficiencies 10.2.1 Initial review of tenders —— availability based on guaranteed levels in main­ tenance contracts —— maintenance costs over life of the economic analysis. When tenders are received, they should be examined and assessed against the agreed format. Responses from manufacturers or suppliers should be considered for compliance with such items as: —— generator voltage —— gross and net power output in kW —— heat output by kWt and temperature —— dimensions —— weight —— specific fuel consumption —— on-engine monitoring and control —— performance guarantees, e.g. reliability, availability and utilisation over the proposed duty cycle —— manufacturers’ experience with similar machines in similar usage —— maintenance requirements —— capital cost —— installation cost —— maintenance cost. Records of the tender review should be maintained, particularly in formal or statutory tendering processes, when records of the assessment procedure can later be requested for inspection. Subject to the maintenance contract terms being similar and an assessment of other qualitative matters, e.g. level of back-up, experience of similar projects, financial stability etc., the tender offering the lowest npv can be recommended. A weighting system may be employed to score the qualitative criteria in a consistent manner. The review should include revisiting the operating pattern for the machines that are offered so as to optimise the returns for each proposed scheme and hence to be able to select a preferred scheme. This review should follow the same format as the earlier appraisals. It will be useful at this time to include a sensitivity analysis to assess the effect on the payback period of changes to fuel and energy prices. The building services engineer will then have a better idea of the factors affecting the future financial viability of the project. Financing 10.2.4 The result of the invitation to tender may have an influence on the means of financing the project. For instance: —— Project costs may have reached a pre-determined level that requires a different approach. —— None of the tenderers may be able to offer the required or preferred finance package. With all returned tender responses available, the building services engineer should check for completeness of technical or commercial information and ask tenderers to forward any information that is outstanding. The objective is to ensure that sufficient information is available to recommend a preferred tenderer and avoid the potential for additional costs during the contract due to unforeseen items. —— The payback period may be short enough to permit capital purchase rather than leasing. The assessment of tenders should continue to the agreed format to a point where a preferred tenderer can be selected. It is always possible that in the early stages, two tenderers may be effectively equal and further negotiations will be necessary before a decision can be made. 10.2.5 10.2.2 Rationalisation of tenders 10.2.3 Economic reviews Once tenders have been assessed and specific information is available on the cost of the project and potential savings, the building services engineer should carry out a further economic appraisal to demonstrate that the scheme still meets the management’s financial criteria. The basis for the tender appraisal should be to reassess the project economics in accordance with the client’s financial parameters for each tender, taking account of: units cost —— chp —— installation costs In any event, the building services engineer should review the means of financing the chp scheme to ensure compliance with management guidelines and to obtain best value for money, commensurate with acceptable risk. Report As a conclusion to the tender phase, the building services engineer should prepare a report formally summarising: —— the result of the invitation to tender —— a recommendation on the preferred tenderer —— the project costs associated with the preferred tenderer —— the result of the economic appraisal —— recommendation for future action: —— • proceed with project, or • stop at the present time the need for any further work before contract placement, e.g. finalise contract terms, programme etc. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 52 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 53 Part 2: Project implementation 11 Installation, commissioning and testing 11.1 Installation The installation must be installed by a competent contractor and comply with the latest legislation and in accordance with other guidance published by CIBSE, IET, IGEM etc —— Whilst the following list is not exhaustive, careful consideration should be given to the following points: —— —— —— Pre-installation and construction: fall under CDM • Who is taking responsibility once the becomes live? • Does the chp and ancillary equipment have a fire or gas system? • How is this going to be connected into the end user system? hv Testing, flushing and filling: • Has the local planning inspector accepted the installation? • Has the electrical installation been tested to IET Regulations, witnessed and signed off? • Has the mechanical installation been pressure tested and witnessed? • Have water samples been carried out on new and existing system? • Does the contract Regulations? • Who is the principal contractor? • Has flushing been carried out satisfactorily? • Who is the cdm coordinator? • Is dosing required on the water systems? • Who is responsible for informing the Health and Safety Executive? • Is pipe work exposed to external conditions, is glycol required in system? • Who is responsible for arranging ‘G59’ protection? • Has the system been commissioned and witnessed? • Is planning permission required? • Is the system ready to ‘go live’? • Is there a construction plan in place? • Has a health and safety risk assessment been carried out? • Has a detailed site survey been completed? • Has a detailed client review discussion taken place? —— Installation: • Has planning approval been obtained prior to commencing on site? • Is there a construction programme in place? • Have site inductions taken place? • Have competent contractors been engaged? • Do all personnel have the correct qualifications and Construction Skills Certificate Scheme (CSCS) cards in place? • Are Risk Assessments and Method Statements in place prior to commencing works? • Have permits been issued to allow works to commence? • Have regular site progress meetings been arranged? • Are toolbox talks in place? Final connections: • Have the tie-in points been identified? • Have the risks been identified when tying into existing system? • Is a high voltage (hv) study required prior to connecting to hv? • Have the tappings on the new former been set correctly? hv trans­ ‘Go live’ stage: • Has the installation been signed off? • Has the commissioning been completed? • Is there a permit to work in place to allow ‘go live’? • Has the ‘G59’ test been completed? • Who is taking responsibility for the system when operational? • What period is allowed and required for initial proving of the chp controls under actual site demand conditions? Specialist systems, such as tri-generation, or systems with island mode operation will require additional checks. 11.2 Component testing, off-site testing The chp unit must be CE-marked, to ensure that it conforms with the essential requirements of applicable EC directives The chp unit is made up of a number of components that are individually tested and designed to allow them to fit within the general arrangement of the chp system. A thorough test of all equipment (where possible) is conducted. However, unless a thermal and electrical load is available, the unit performance cannot be checked. This is normally done when on site and fully connected to the client’s system. Where the system has ‘island’ mode or ‘no-break’ facility, additional hardware and design is required to enable the system to support the facility. A ‘soft’ test will be carried out by the manufacturer to ensure the correct interlocks and transfer operates when required. However, it is important that a number of ‘live’ tests are carried out on the client’s Combined heat and power for buildings premises when fully commissioned and connected to the client’s system to check compatibility and correct operation. —— What is to be tested or trialled? —— How is the test or trial to be conducted? Initial works: —— Who will carry out the test? • design approved for manufacture —— • general arrangement drawing completed. Are any special approvals required e.g. dno verification of G59 compliance prior to permitting generation? —— When is the test or trial to be conducted? A typical regime for testing of a comprise: —— —— —— —— The sequence for on-site stw should be agreed in advance. The stw programme should include: chp chp unit off-site will build: • COSSH Assessment • during the day • machine risk assessment • at night • assemble chp • at week-end • complete build checklist prior to offering to test. Prior to energising: • gas test, purging and certification • IET testing and certification • system pressure tested and filled with water • system lubrication added. —— Will the test have an impact on the normal operation of the building? —— Who is to witness the test? The stages of site stw will commonly follow the pattern: —— installation checks to ensure that all equipment is fitted as required by drawings —— static testing of systems: System testing: • pressure testing of pipe systems • assign test engineer • • complete pre-commission test sheets line checks and earth resistance checks of electrical systems • energise system —— dynamic running checks of individual equipment • load software —— functional checks of all safety devices • run and tune engine —— • complete commissioning test sheets generator and switchboard performance and safety trials • collate performance data and sign off as commissioned —— operational running checks of complete systems —— • glycol added once fully satisfied and prior to dispatch (when required) proving of all normal and reversionary operating modes. • system identification added • system made safe and secure for dispatch • transport to client location. During the course of the testing programme the client is normally invited to witness the tests. 11.3 Commissioning 11.3.1 Co-ordination Commissioning a new chp plant should be a planned, progressive and sequential process of setting to work (stw). A considerable degree of test and trial may be carried out at the supplier’s factory, particularly for smaller engines or packaged units. Where factory testing is possible, the maximum advantage should be taken of this opportunity to carry out all possible tests. On completion of factory testing, testing on site will be reduced to: —— items that could not be tested in the factory —— checking that factory test results are still valid. 11.3.2 Documentation The contractor must present a full dossier with all relevant information, e.g. test methods and results, at the end of the test. Any defects identified during the stw, whether in the factory or on site, should be recorded and assessed for impact. Some may prevent further testing without rectification; others may be acknowledged for rectification later. Whatever decision is reached, it should be logged for future reference. 11.3.3 Handover Finally, stw will culminate in an acceptance trial and report which, if successful, will lead to handover. At handover all relevant parties should sign a certificate. The ‘taking-over certificate’ in MF/1* or similar form may be used. The certificate should include reference to all outstanding defects (‘snagging list’) with the agreed responsibility and action for rectification, and any agreed retention against the contract price. * MF/1 (Revision 5): Model Form of General Conditions of Contract (London: Institution of Engineering and Technology) (2010) Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 54 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation 11.4 Client acceptance testing Typically there will be three sets of acceptance testing: —— —— —— proving of the functionality of all equipment, controls, interlocks etc. 12.1 12.1.1 —— conditions of heat or power to initiate a shut-down to a standby mode —— conditions of heat or power to initiate a re-start from standby —— operation of other plant during periods when the plant is on, including plant sequencing chp performance testing to confirm that the unit is operating as the supplier’s proposals —— reliability testing: operating under normal conditions for a limited period of, say, 1 week to prove that the engine and systems are reliable. plant response to engine parameters entering warning levels, e.g. rising lubrication oil temper­ ature —— plant response to partial failure of control and monitoring system, e.g. failure of remote modem link —— plant response to failure of local electricity supply —— level of plant operation and control that is possible without the normal automatic systems —— location and authority of normal plant control: from where and by whom. Consideration needs to be given during the tender preparation stage to the availability of suitable site demands for heating, electricity and, in the case of tri-generation, cooling to enable testing and commissioning to be completed. This is particularly an issue for new buildings or when the commissioning is planned for the summer. Electrical demand is less critical if export is permitted but in some cases an electrical load bank can be provided temporarily. If full heat rejection facility is included in the scope, the chp operation can normally be fully tested. However, some aspects of the controls may need to be carried out later (such as how boilers are sequenced with the chp as the site heat demand varies). Where a thermal store is incorporated this may be sufficient to provide a heating load. It may be necessary to carry out some of the final proving at a later date, say during the heating season, and this can be allowed for within the contract. 12 55 Operation and maintenance Operation Strategy for using the CHP plant In the feasibility study, consideration was given to the way in which the chp plant might be operated. This was developed further in the tender stage in order to assess accurately the annual savings from and economic justification for the project. If an operation and maintenance agreement has been signed with a contractor, this may reference operating periods and annual energy production as key performance factors. The building services engineer will already have planned and set into the control system such features as: —— the normal start and stop time each day: determined by electricity tariff times and/or building usage —— conditions for heat and power demand before the plant can start —— number of attempts and maximum time to start, run and parallel before declaring failed start and shutting down —— protection of starter motors —— protection of circuit breakers —— conditions of heat or power to initiate a modulation of plant output Each of the items above needs to be addressed to ensure that the operator (as distinct from the building services engineer) understands what to expect or demand of the chp plant. The pattern of operation should remain within the building services engineer’s overall control. It may be set up and adjusted by the remote monitoring contractor in agreement with the building services engineer for plant that is under performance based maintenance contracts. Otherwise, alterations to the operating pattern may be made through the building bems, by adjustable timers or by other semiautomatic means within the chp plant control system. The interaction of other plant in particular requires careful consideration. It is usual that, when running, the chp unit becomes the lead boiler. However, to achieve this with other boilers, or even other chp plant, requires careful selection of the chp plant and boiler on/off set temperatures, and of the sensing positions, to ensure that the plants operate in the correct sequence. Different temperature schedules may be required when the chp plant is running and when it is shut down. If heat raising plant is not co-ordinated in this manner, the boilers may suppress the chp plant at times when all conditions would otherwise be favourable for chp operation. 12.1.2 Monitoring benefits The chp plant will be installed, in most cases, because of the financial benefit achieved by displacing the more expensive combination of imported power and boilergenerated heat. It is therefore incumbent upon the building owner’s or operator’s services engineer to maintain and monitor records to ensure that the plant delivers the benefit. As a minimum, records should show: —— running hours: from the chp plant hours-run meter —— fuel consumption: from the chp plant’s meter —— usable electrical power generated: from chp plant kW·h meter, minus any parasitic loads for each tariff period Combined heat and power for buildings —— usable heat generated: estimated, if not directly metered —— the duration and cause of any plant stoppages. Should any changes to the operation of the chp plant be contemplated? Re-running the financial appraisal, or monthly reports, should provide the answer as to whether the proposed change should proceed. These minimum records may be taken directly from the automatically monitored records provided by the o&m company or by other local means. In most instances, the building services engineer will wish to see a fuller record of performance than the bare minimum. A balance needs to be struck regarding the frequency and detail of information presented to the building services engineer to ensure that it is sufficient for purpose without being overwhelming. The building services engineer may also wish to initiate changes that improve the overall building operation and economics. Any changes to the chp plant operating pattern should take into account the cost implications for existing operation and maintenance agreements. On modern pc-based data logging systems, it is possible to retain considerable volumes of data for later analysis. Normally a hierarchy of data retention will be established, e.g.: The provision of services to operate the plant on a day-today basis and to attend to breakdowns may be the subject of a service agreement with a specialist contractor. The building services engineer will be able to forecast the operating periods and generating profiles of the chp plant to assist in negotiating the service agreement. —— last hour: all data recorded —— last day: one data set per hour plus all start/stop signals, alarms and warnings —— last three months: one data set per week, plus all start/ stop signals, alarms and warnings. Records of plant performance should be converted periodically into a costed record of benefit that will compare the actual cost of running the chp plant with the cost of providing the equivalent heat and power by conventional means, in effect validating the financial appraisal. The information required to achieve the necessary results is: —— cost of fuel for the chp plant: from gas bills —— cost of chp generated electricity: from the chp contract —— cost of chp plant maintenance: from the chp contract —— equivalent cost of importing chp generated power: from electricity bills —— equivalent cost of boiler firing: from boiler records. The data may be entered into the spreadsheet used in the feasibility study, formatted to suit the analysis required, or presented in any other suitable form. Performance records should be updated and reviewed as often as required. Many organisations keep records monthly and find them a useful way of keeping senior management informed of the chp scheme and its continuing financial benefit to the organisation. Information about plant stoppages is particularly important in relation to payments in performance based contracts. Liability for non-performance of the plant will be dependent on the reason for non-performance. 12.1.3 12.1.4 12.2 Operation and maintenance manuals 12.2.1 Manuals The provision of operation and maintenance manuals will have been specified in the contract specification. These manuals are required by the building services engineer, irrespective of whether the supplying contractor is providing maintenance services. Holding the manuals will allow, should circumstances dictate, the operation and maintenance of the plant using in-house resources or the placement of an alternative operation and maintenance contract. The manuals must be clear and comprehensive. The building services engineer should ensure that manuals are received from the supplying contractor before plant handover. The manuals should cover: —— health and safety warnings —— plant data sheets —— general and detailed descriptions of engines and all equipment —— installation guidance notes —— general arrangement drawings —— circuit and schematic diagrams —— commissioning procedures, records and test sheets —— operating instructions —— detailed maintenance instructions and schedules for all equipment —— diagnostic fault finding information —— passwords to access control system —— listing and descriptions of special tools —— recommended spares holdings and ordering infor­ mation. Changes in operation If fuel tariffs change, the monthly reports should identify the change in benefit. Such a change may be the prompt that is required to re-examine the way in which the chp plant is being operated; for example, should a new running pattern be adopted (e.g. continuous operation rather than 17 hours per day)? Provision of operating services Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 56 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 2: Project implementation 12.3 57 Maintenance and servicing plant requires maintenance as a necessity. The purchaser should understand the need for, and degree of, maintenance required and set in motion the means of delivering a suitable service. chp 12.3.1 —— daily or weekly checks: • performance monitoring checks • visual inspection of plant for leaks and unusual noises • visual check on oil level in oil make-up tank Delivery of maintenance Maintenance may be carried out by: —— in-house staff —— equipment suppliers —— specialist contractors. —— The costs and benefits, or risks, associated with each option will determine the choice of who should carry out maintenance. Many organisations choose some form of contract maintenance with equipment suppliers or specialist contractors (see section 12.3.3 below). 12.3.2 Maintenance schedules for chp plant will vary depending on the exact machine. The following schedule is an example of the items that may be included for a typical gas-engine: Schedules of maintenance Maintenance of a gas-fired spark-ignition chp installation will include activities that will be scheduled on an hoursrun basis, as well as activities that will depend on inspections or condition monitoring. Individual engine and equipment suppliers will provide detailed statements on the scope of maintenance for their equipment. These statements should be observed carefully in order to: —— ensure the enduring life of equipment —— maintain the warranties —— co-ordinate scheduling of major services. performance guarantees routine service (typically every 1000 hours): • check running records for plant performance trends • check starter battery condition. • change engine oil • change oil filter • send oil sample for analysis • check spark plugs and renew as required • check air filter and clean or change as required • check oil tank level and top up as required • check ht leads for wear and corrosion • check and reset valve clearances as required; record high recession • change rocker box gaskets • check engine coolant level; top up antifreeze as required • check battery terminals for tightness • clean out engine catchment area; wipe clean • visually inspect all engine and control panel wiring • visually inspect all water flexible connection hoses and expansion joints for deterioration • check and clean in-line water filters, if fitted • check condensate pot level • visually inspect close coupled engine/ generator connection • visually inspect anti-vibration mounts supporting engine/generator monoblock • restart engine; visually inspect for fluid leaks, unusual noises, loose fittings and The maintenance requirements of machines are now more frequently being determined by condition monitoring of the plant. Particularly where fully automatic monitoring and data logging is used, deviations in plant performance can be identified early and appropriate remedial steps taken. Not every slight deviation in condition will evoke an immediate maintenance response. Condition monitoring of bearings is a valuable tool for making an early diagnosis of incipient bearing failure. • Oil sample monitoring may also be used. Laboratory analysis of the oil would look for: check engine performance; set up using gas analyser • check and record exhaust back pressure —— water or glycol contamination: indicating leakage of engine coolant into the oil circuits • check operation/control of dry air cooler and 3-port valve —— changes in viscosity, acidity, oxidation, nitration and other conditions: indicating that the oil needs to be changed • check unit controls, metering, monitoring and communications. —— metal particulate contamination: indicating engine bearing or component wear —— non-metallic particulate contamination. Further servicing requirements will depend on the equipment selected and the feedback from condition monitoring. The requirements will be influenced by the hours run, the frequency of starts and the type of fuel. Combined heat and power for buildings It is important that full records of maintenance activities carried out are kept and that these are provided to the owner. 12.3.3 Contracted-out maintenance The level of maintenance contracted out may cover a very wide range of options. The following are examples of typical cover: —— —— Service only: The maintenance contractor will carry out a pre-set list of maintenance tasks to a predetermined time schedule only. All tasks in excess of the standard predefined tasks will be extras. Spares and consumables quoted in the stated tasks will be included in the price but all other spares will be extras. The user is responsible for calling in the maintenance contractor for any defect rectification at additional cost. Service only with remote monitoring: The same as ‘service only’ with the addition that the contractor is also monitoring the chp plant performance and should therefore identify plant failures (or the need for early attention) and can discuss with the user whether the attendance of a service engineer is required. —— Comprehensive service with remote monitoring: The maintenance contractor will carry out pre-defined maintenance tasks and will respond to defect callouts. The range of spares included in the price will be greater than for ‘service only’. —— Comprehensive service with performance guarantee: The maintenance contractor takes on almost total responsibility for ensuring that the plant achieves specified performance levels. Performance may be determined in terms of guaranteed availability of hours run and in terms of heat and power generated. The contractor carries out all planned maintenance activities and is responsible for addressing all unplanned defects. The contractor provides a near immediate call-out response to breakdowns. —— Monitoring service only: The monitoring contractor takes no responsibility for ensuring that the plant achieves any particular level of service but provides the client with reports of plant monthly perfor­ mance, operation outside of normal limits and trips, with the time and type of fault. Other services may be included such as monthly savings reports, diagnostic assistance from data analysis, prediction of service interval. This level of service provision is relatively rare and, if adopted, needs careful consideration to ensure that all parties are aware of the scope and limits of their responsibilities. The client must also select which elements of the maintenance will be contracted out. For all maintenance arrangements, it is important to establish agreed or contracted response times, and defect call-outs, since all lost running time detracts from the chp scheme’s financial benefit. It is possible for an otherwise well designed and installed chp plant to be out of action for 1000 hours in a year if faults are not promptly attended to. This may include downtime at times of highest electricity price and greatest heat demand. As a guide, planned downtime for a plant running 8000 hours per year should not exceed 400 hours, and unplanned downtime a further 400 hours in an average year without a major overhaul. The best systems should achieve a total downtime of less than 600 hours per year, most of this being for planned maintenance and therefore carried out at times of least inconvenience. For plants running only 4000 hours per year, most planned downtime could be programmed outside the duty hours. Where maintenance is scheduled at weekends, premium payments may be incurred. Where performance guarantees are involved, clear and careful agreement of the performance criteria are required. Issues to be clarified include: —— Output performance: Is power used by chp plant auxiliaries, fuel systems and heat rejection systems included or excluded? These parasitic loads may be significant but they should be excluded from any calculation of chp scheme benefit to the user, since without the chp scheme these loads would not exist. —— Hours available; hours run: how will downtime be logged and attributed to cause, e.g. planned maintenance, defect or unplanned maintenance, building heat or power demand too low etc.? On remotely monitored systems, the data logger may record the fact that a chp plant has been manually tripped locally and interpret this as the user deciding not to run the plant. Such an event would therefore not count against the maintainer, whereas the user may have been responding to a request to shut down from the maintainer. 12.3.4 In-house maintenance If the purchaser takes on any part of the operating service or maintenance of the chp plant, the division of respon­ sibility with any specialist contractor must be clearly identified. A normal chp plant requires daily observation, either locally or via a remote terminal, to check for good operation and to identify trends that may indicate future problems. Other functions may require weekly or monthly checks, with main services being needed every six months. Oil changes may be required every 6 to 8 weeks (1000 to 1500 hours running). To ensure that appropriate maintenance is carried out, the building services engineer should establish maintenance schedules following the manufacturer’s recommendations. 12.3.5 Consumable spare parts The contract specification should allow for the immediate provision on handover of an appropriate range of consumable spares recommended by the supplier. When selecting spares holdings, judgment must be exercised in relation to: —— the convenience of immediate availability —— space required for storage —— anticipated draw-off rates —— the shelf-life of spares —— the cost of cash tied up in stock Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 58 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Part 3: Lessons learned —— the likelihood of the need and the impact of nonavailability —— the ability to source spares when required. All spares should be detailed in a spares listing within the operating and maintenance manuals. This listing should 59 also include all relevant references, sources of supply and ordering information. The precise level of spares holdings may ultimately be determined by the arrangements made for maintenance and service. Part 3: Lessons learned 13 Lessons learned —— The following checklist of do’s and don’ts summarises some of the guidance provided within the body of the guide. It is divided into the following headings following the stages of a project development: Ensure that efficiencies and gas consumption rates are defined using gross calorific value and always check this with the chp supplier. —— Discuss with the local authority the local Air Quality Objectives and assess the impact of chp; this may involve dispersion modelling. —— Feasibility studies —— —— Economic appraisals —— Integration of chp into heating circuits —— District heating —— Environmental impact Consider adequacy of gas supply (noting that normally gas consumption increases significantly with the installation of chp). Gas suppliers will need to know the ‘supply hourly quantity’ (shq) (i.e. the maximum hourly gas consumption), the ‘supply offtake quantity’ (soq) (i.e. the maximum daily consumption) , and the ‘annual quantity’ (aq) of gas required. —— Procurement —— Installation —— —— Commissioning Check the gas pressure available at maximum demand and compare this with the engine requirements to assess whether gas boosters will be required. —— Operation —— —— Tri-generation and absorption chillers Establish how supplies of heat and power are maintained during chp maintenance periods. —— Confirm suitable space exists for access. —— Establish how adequate ventilation is provided to the chp enclosure and plant room. —— Consider location for heat rejection equipment taking account of potential issue of noise generation. 13.1 —— Feasibility studies Establish heat and power demands in as much detail as possible, which could involve installing temporary metering or monitoring equipment. —— Consider opportunity for connection to nearby buildings with different heat demand profiles. —— If steam or mthw is to be generated by exhaust gases then consider uses for lthw, or consider options for converting system to lthw. —— Discuss the proposed project with the distribution network operator at the earliest stage to identify any issues concerning fault level contribution and reinforcement works, and make an early application for connection using the appropriate G59/2 or G83/1 application forms. —— Consider the extent of on-site electrical infra­ structure works. —— Evaluate whether for larger schemes hv generators would be preferred to using step-up transformers —— In most cases limit the maximum size of the chp to the electrical base load to avoid significant export which attracts much lower value. Boilers can be used to meet peak heat demands. 13.2 chp with good Economic appraisals —— Define the criteria for assessment with the client and agree period of analysis and discount rates to be used. —— Ensure all maintenance and operating costs are included: routine and non-routine, consumables including lubricating oil. —— Try to establish true market levels for gas and electricity prices: simply taking current contract prices may be misleading if these are for different contract periods ending at different dates. Refer to statistics and forecasts published by the Department of Energy and Climate Change (DECC). —— Consider other economic benefits that may accrue through regulatory incentives, e.g. CRC Energy Efficiency Scheme, Climate Change Levy exemption. Combined heat and power for buildings —— Make sure that the maintenance regime and the cost implications are understood. —— Carry out sensitivity analysis on energy prices and availability, reflecting any compensation terms within the proposed maintenance contract. 13.3 Integration of CHP into heating systems —— For new-build schemes, select flow and return temperatures of heating circuits to optimise chp operation and prevent chp tripping on high return temperatures. —— Ensure chp acts as the lead heat source at all times. —— Consider whether the chp is connected to the common return to the boilers or connected in parallel and, if in parallel, the control approach to give priority to chp. —— Evaluate the benefits of thermal storage and locate the thermal store between the flow and return, maximising the temperature difference in the store. —— Avoid the use of a low loss header if this risks high return temperatures onto the chp at part-load. —— Ensure suitable access is provided for maintenance and subsequent removal and replacement of chp. 13.4 Prevention and Control (IPPC) regulations or only under the Clean Air Act 1993. —— Use HMIP Technical Guidance Note (Dispersion) D1: Guidelines on Discharge Stack Heights for Polluting Emissions (June 1993) (HMIP, 1993) for the calculation of chimney height. —— If the site comes under the IPPC Regulations carry out dispersion modelling using EA-approved software. —— Obtain accurate emissions data from the chp engine manufacturer. NO2 is 6 or 7 times more toxic than NO, so the chimney height calculation will be sensitive to their relative proportions as well as total NOx content in exhaust gas. —— If local Air Quality Objectives are to be met, background levels of common pollutants are available in Table 2 in HMIP Technical Guidance Note D1 or from the UK Air Quality Archive (http://www.airquality.co.uk/index.php). —— Check the calculation for each fuel and at part load to find the most onerous condition, taking account of emissions from both chp and fuel for all realistic operating scenarios. —— Design entire flue gas system and stack for minimum internal volume (to minimise residence time between engine and top of stack) consistent with meeting the chp engine manufacturer’s maximum backpressure limitation (allow a design margin for fouling etc). District heating —— For new schemes select low return temperatures to reduce flow rates on dh network. —— —— For existing schemes consider potential for reducing return temperatures by investigating degree of oversizing and rebalancing heat emitters. Ensure stack discharge velocity is within specified limits (typically between 10 and 15 m/s depending upon heat content). —— —— Consider benefits of investing in new heat emitters to reduce return temperatures. If using dispersion modelling, the following design guidance is suggested in the absence of other criteria set by the regulatory authorities: —— Ensure all controls operate as variable volume (2port valves) not constant volume (3-port valves). —— Limit the scope for bypasses in the network whilst maintaining minimum circuit flow temperatures. —— Use variable speed pumps to reduce electrical energy use. —— Consider the impact of particulates for some types of chp/fuels. —— Evaluate whether and where heat meters are to be installed and how these will be read. —— —— Establish where hydraulic breaks in the system are needed and select hydraulic interface units and heating substations as appropriate. Carry out background noise measurements in accordance with BS 7445: Description and measurement of environmental noise (BSI, 2003). —— Agree design basis with local authority for noise control taking account of possible restrictions in operating hours. —— 13.5 —— Check that pressure constraints for all equipment are not violated in terms of static pressure, peak pressure, minimum pressure to avoid cavitation and differential pressures. Environmental impacts Liaise with local authority or Environment Agency (EA)/ Scottish Environment Protection Agency (SEPA)/ Northern Ireland Environment Agency (EHSNI) (as appropriate) at an early stage to agree design basis and reporting standards and whether the scheme falls under the Integrated Pollution 13.6 • the maximum plant contribution should be less than 10% of the 1-hour mean target value • the annual mean of the plant emissions plus existing background concentrations should be less than the annual mean target value. Procurement —— Choose form of contract and the allocation of design responsibility. —— Define demarcation and interface points. —— Consider whether chp supplier is to be the main contractor or a sub-contractor depending on the scope of work. —— Establish how the project opportunity will be advertised. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 60 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 61 Part 3: Lessons learned —— Assess tenders on a whole life cost basis, not just on a capital cost basis. —— Electrical efficiency is probably the biggest single factor contributing to overall cost effectiveness. —— To carry out the tender analysis, produce a spread­ sheet that enables sensitivity of variables such as gas price, electricity value etc to be tested. —— —— —— 13.7 —— Negotiate maintenance contract with chp supplier at the same time as the construction contract and incorporate in the tender analysis: 13.8 Commissioning —— Agree a commissioning/proving trial scope and programme. —— Establish who pays for fuel used for commissioning and who owns the electricity generated. —— Ensure metering is calibrated and operational prior to commissioning and that it complies with CHPQA standards (CHPQA, 2009). —— Consider what load will be available for heating, cooling and electricity at the time that commission­ ing is planned and whether a load bank (for example) is needed. —— Obtain a connection agreement from the dno and negotiate an import/export agreement with an electricity supplier (if export is contemplated). Ensure a Meter Operator (mo) is appointed if exporting. • ensure availability calculation method and compensation terms is agreed • check for total limits of liability • check for exclusions, e.g. for major failures • check for provision of standard reports • check for use of subcontractors —— • check for supply of materials and removal of waste. Ensure CHPQA form F1 is completed in good time and nominate the Responsible Person. —— Complete CHPQA form F3 (forecast of performance) in good time. —— Apply to Secretary of State for Climate Change Levy (CCL) exemption certificate in good time. —— Submit CCL forms PP10/PP11 to fuel suppliers in good time prior to commissioning. —— Validate engine power and heat outputs and effi­ ciencies against supplier performance guarantees. —— Carry out a reliability run over several days. Ensure requirements of the Construction Design and Management Regulations 2007 (‘CDM Regulations’) have been considered: appointment of principal contractor, cdm co-ordinator etc. Evaluate risks and transfer operational risk to supplier as far as is practicable. chp Detailed design and installation chp Develop detailed control strategy to deliver the optimum economic and environmental perfor­ mance. 13.9 —— Is the existing bems control to be extended to control the chp or will the chp supplier provide a standalone control system? —— Agree response time to attend chp breakdowns. —— Agree how remote monitoring is carried out. —— —— Ensure local authority planning approvals are in place for all aspects of the project (if necessary write into contract). Supplier to have responsibility for all chp-integrated components. —— Agree availability guarantee covers all integrated components. —— Ensure all service input and output requirements are known and designed-in. —— Ensure chp running regime and decision factors (e.g. tariffs) are documented and understood. —— Ensure design is robust in all aspects before contract is signed. —— Track the chp performance and availability and manage the maintenance provider. —— Anticipate any site heating, dhw and steam downtimes and detail these in the installation programme. —— Submit CHPQA form F4 to CHPQA before 31st March each year to obtain CCL exemption. —— Agree all demarcation/take-over points in the design phase. 13.10 —— Supplier/installer to keep the project timing plan up-to-date throughout the project. —— If an absorption chiller is to be included check its sensitivity to input temperature. —— Allow enough time for all phases of the commission­ ing period. —— —— Ensure major items of equipment have mean time between failures (mtbf) information. Establish the additional heat rejection requirement for the absorption chiller, which is typically double the capacity required for conventional vapour compression chillers. —— Consider impact on power factor of chp generation. —— —— Ensure heat rejection circuit has frost protection. Identify and resolve any pre-existing problems with a cooling system, heat rejection system, water treatment etc before installing an absorption chiller. Operation chp- Tri-generation and absorption chillers Combined heat and power for buildings —— Design the absorption chiller system for full load operation (by the incorporation of thermal stores if necessary) as cop may drop by up to 33% at partload. —— Consider variable speed control of absorbent pump to improve the cop at low load. —— Consider access and floor-loading (a typical 2 MW double-effect steam chiller weighs 12.5 tonnes empty and 16.7 tonnes when operating). —— Ensure ambient of >5 °C in chiller room to prevent crystallisation. —— Crystallisation can be prevented if the following are considered: —— • avoid cooling water temperature colder than design by the use of mixing valves etc. • avoid sudden changes in cooling water temperature. Ensure heat supply is completely shut off when not required. Carbon Trust (2011) Micro CHP (Combined Heat and Power) Accelerator — Final report CTC788 (Carbon Trust). Available at http://www.carbontrust. com/resources/reports/technology/micro-chp-accelerator (accessed May 2012). CCC (2010) The Fourth Carbon Budget — Reducing emissions through the 2020s (London: Committee on Climate Change). Available at http://www. theccc.org.uk/reports/fourth-carbon-budget (accessed May 2012). CCC (2011) Bioenergy Review (London: Committee on Climate Change). Available at http://www.theccc.org.uk/reports/bioenergy-review (accessed May 2012). CHPQA (2009) CHPQA Standard: Quality Assurance for Combined Heat and Power Issue 3 (London: Department of Energy and Climate Change). Available at http://chpqa.decc.gov.uk/chpqa-documents (accessed May 2012). CHPQA (2012) CHPQA Guidance notes (website) (London: Department of Energy and Climate Change). http://chpqa.decc.gov.uk/guidance-notes (accessed May 2012). CIBSE (2001–2) ‘Noise and vibration control for hvca’, ch. 5 in Heating, ventilating, air conditioning and refrigeration CIBSE Guide B (London: Chartered Institution of Building Services Engineers). —— Provide a ups to run the absorbent pump for 20 minutes after a power cut. —— Over-size external heat rejection if possible as reduced heat rejection capacity will severely restrict absorption chiller output. CIBSE (1999) Minimising pollution at air intakes CIBSE TM21 (London: Chartered Institution of Building Services Engineers). —— Allow adequate time for commissioning: absorption chillers require two weeks to establish passivated internal coating after first charging with refrigerant and chemicals, and after any subsequent opening to atmosphere. Construction (Design and Management) Regulations 2007 (SI 320/2007) (London: The Stationery Office). Available at http://www.legislation.gov. uk/uksi/2007/320 (accessed May 2012). —— Remember that a suitable cooling load is needed for commissioning. —— Ensure operators are adequately trained in absorption chiller operation and in particular the conditions and transients likely to cause crystal­ lisation. References BRE (2012) Wiltshire R Technical Guide to District Heating (Garston: IHS/ BRE Press). BSI (2003) BS 7445: Description and measurement of environmental noise: Part 1: 2003: Guide to quantities and procedures; Part 2: 1991: Guide to the acquisition of data pertinent to land use; Part 3: 1991: Guide to application to noise limits (London: British Standards Institution). BSI (2009a) BS 6700: 2006+A1: 2009: Design, installation, testing and maintenance of services supplying water for domestic use within buildings and their curtilages. Specification (London: British Standards Institution). (BSI (2009b) BS EN 253: 2009: District heating pipes. Preinsulated bonded pipe systems for directly buried hot water networks. Pipe assembly of steel service pipe, polyurethane thermal insulation and outer casing of polyethylene (London: British Standards Institution). Control of Noise at Work Regulations 2005 (SI 2005/1643) (London: The Stationery Office). Available at http://www.legislation.gov.uk/uksi/2005/ 1643 (accessed May 2012). Dansk Standard (2009) DS 439: 2009: Code of Practice for domestic water supply installations (Charlottenlund, Denmark: Dansk Standard). DCLG (2010) Approved Document L: Conservation of fuel and power (4 parts) Building Regulations Part L Approved Documents (London: Department for Communities and Local Government). Available at http://www. planningportal.gov.uk/buildingregulations/approveddocuments/partl/ approved (accessed May 2010). DECC (2010) Chapter 5, Table 5.6 in Digest of UK Energy Statistics (London: Department of Energy and Climate Change). Available at http:// www.decc.gov.uk/en/content/cms/statistics/publications/dukes/dukes.aspx (accessed May 2012). DEFRA (2007) The Air Quality Strategy for England, Scotland, Wales and Northern Ireland (London: Department for Environment, Food and Rural Affairs). Available at http://www.defra.gov.uk/environment/quality/air/ air-quality/approach (accessed May 2012) DEFRA (2011) 2011 Guidelines to Defra/DECC’s GHG Conversion Factors for Company Reporting: Methodology Paper for Emission Factors (London: Department for Environment, Food and Rural Affairs). Available at http://www.defra.gov.uk/publications/2011/09/01/ghg-conversion-factorsreporting (accessed May 2012). BSRIA (2003) Galliers S Fuel Cell Technology: The scope for building services applications BSRIA BG 9/2003 (Bracknell: BSRIA). DoE (1981) Chimney Heights: 1956 Clean Air Act Memorandum (London: Her Majesty’s Stationery Office) BSRIA (2007) Teekaram A, Palmer A and Parker J CHP for existing buildings. Guidance for design and installation BSRIA BG2/2007 (Bracknell: BSRIA). Electricity at Work Regulations 1989 (SI 1989/635) (London: The Stationery Office). Available at http://www.legislation.gov.uk/ uksi/1989/635 (accessed May 2012). Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 62 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 References 63 ENA (2011a) Distributed Generation Connection Guide: A Guide for connecting generation that falls under G59/2 to the distribution network Version 3.2 June 2011 (London: Energy Network Association). Available at http://www. energynetworks.org/electricity/engineering/distributed-generation.html (accessed May 2012). ENA (2011b) Distributed Generation Connection Guide: A Guide for connecting generation that falls under G83/1 (Stages 1 and 2) to the distribution network Version 3.2 June 2011 (London: Energy Network Association). Available at http://www.energynetworks.org/electricity/engineering/distributedgeneration.html (accessed May 2012). Euroheat (2008) Guidelines for District Heating Substations (Brussels, Belgium: Euroheat & Power). Available at http://www.euroheat.org/ Technical-guidelines-28.aspx (accessed May 2012). The Gas Safety (Installation and Use) Regulations 1998 (SI 1998/2451) (London: The Stationery Office). Available at http://www.legislation.gov. uk/uksi/1998/2451 (accessed May 2012). HMIP (1993) Guidelines on Discharge Stack Heights for Polluting Emissions HMIP Technical Guidance Note (Dispersion) D1 (London: The Stationery Office). IGEM (undated) Gas fuelled spark ignition and dual fuel engines IGEM/UP/3 Edition 2 (Kegworth: Institution of Gas Engineers and Managers). IGEM (2005a) Soundness testing and purging of industrial and commercial gas installations IGEM/UP/1 Edition 2 (Kegworth: Institution of Gas Engineers and Managers). IGEM (2005b) Gas installation pipework, boosters and compressors on industrial and commercial premises IGEM/UP/2 Edition 2 (Kegworth: Institution of Gas Engineers and Managers). IGEM (2009a) Commissioning of gas fired plant on industrial and commercial premises IGEM/UP/4 Edition 3 (Kegworth: Institution of Gas Engineers and Managers). IGEM (2009b) Application of compressors to natural gas fuel systems IGEM/ UP/6 Edition 2 (Kegworth: Institution of Gas Engineers and Managers). IGEM (2004) Application of natural gas and fuel oil systems to gas turbines and supplementary and auxiliary-fired burners IGEM/UP/9 Edition 2 (Kegworth: Institution of Gas Engineers and Managers). HVCA (2008) Installation of Combined Heat and Power HVCA TR37 London: Building and Engineering Services Association). IMechE (2010) Home or overseas contracts for the supply of electrical, electronic or mechanical plant — with erection IMechE Model forms of general conditions of contract MF/1 (Revision 5) (London: Institution of Mechanical Engineers). IEA (2011) District Heating and Cooling (website) IEA Annex X (International Energy Agency). http://www.iea-dhc.org (accessed May 2012). National Grid (2009) The Potential for Renewable Gas in the UK (National Grid). Available at http://www.nationalgrid.com/uk/Media+Centre/ Documents/biogas.htm (accessed May 2012). Appendices Appendix A1: Conversion factors Table A1.1 Energy unit conversion factors Table A1.3 SI multiples To Prefix Symbol Factor From Joule Joule­1 3.6 Í 106 kW·h Therm 105.5 Í BTU 106 1.055 Í 103 kW·h Therm BTU kilo k 103 0.2778 Í 10–6 9.48 Í 10–9 0.948 Í 10–3 mega M 106 1 34.12 Í 10–3 0.2931 Í 10–3 0.293 Í 10–3 3.412 Í 103 giga G 109 10–6 1 tera T 1012 10 Í 10–6 1 peta P 1015 exa E 1018 10 Í Table A1.2 Miscellaneous conversions Multiply by to obtain ton 1.1016 tonne tonne 0.984 ton pound (lb) 0.454 kilogramme Table A1.3 Typical calorific values for fuels gallon 4.546 litre Fuel litre 0.220 gallon Gross Net cubic foot 0.028 m3 Fuel oil to BS 2869 Class D 45.0 42.2 m3 35.315 cubic foot Natural gas at 15 °C, 1013.25 mbar 38.6 34.7 Calorific value / MJ·kg–1 Combined heat and power for buildings Appendix A2: Glossary of terms The definitions given here relate specifically to the context of chp installations. Terms may have broader or alternative meanings in other contexts. Absorption refrigeration. Refrigeration plant that uses heat instead of electricity as the driving energy source, utilising, for example, lithium bromide and water as the working fluid. Adsorption refrigeration. Refrigeration caused by the evaporation of water at low pressure as it is attracted to an adsorber such as silica-gel. Alternator. A machine whose shaft is driven by an engine or turbine and converts mechanical energy into alternating current (ac) electricity. Also called a generator. Auxiliary firing. The burning of fuel (with its requisite air supply) in waste heat boilers when the generator set is not running but the site heat supply is to be maintained. Availability charge. The charge made for maintaining an agreed electrical supply capacity to a consumer’s premises. Construction (Design and Management) Regulations 2007 (CDM2007). The Construction (Design and Management ) Regulations 2007 came into force on 6th April 2007; they replace the CDM Regulations 1994 and the Construction (Health, Safety and Welfare) Regulations 1996. The key aim of CDM2007 is to integrate health and safety into the management of a project and to encourage everyone involved, to work together. The principles of cdm apply to all construction projects; however, notification applies where work: — will last more than 30 days, or —will involve more than four persons working on site at any time, or — will involve more than 500 person days. CDM Regulations identify task functions of the client, designers, the cdm coordinator, principal contractor and contractors that must be carried out by nominated bodies. Contract energy management (cem). A service providing technical, financial and management resources to implement an energy saving project. Remuneration for the service is often by retention of a proportion of the savings. The cem contractor can also bear a higher proportion of the financial risk of any investment. Building energy management system (bems). A computer-based system for remote control and monitoring of building services used for interactive energy management. Cylindrical rotor generator. A type of electricity generator. As frequency depends on the speed multiplied by the number of pole pairs, higher speeds require fewer poles and the excitor winding can be accommodated in radial slots machined into the periphery of the rotor. Calorific value (cv). The heat energy available from a fuel when it is completely burnt, expressed as heat energy units per unit of weight or volume of the fuel. The gross or higher calorific value (gcv/hcv) is the total heat energy available when all the products of combustion are cooled to standard conditions and the heat released from the condensation of water vapour is included. The net or lower calorific value (ncv/lcv) is the total heat energy released from combustion excluding the latent heat of the water vapour from condensation of the products of combustion. Demand; maximum demand; demand profile. The rate at which energy is required, expressed in kW or MW. It is usually related to a time period, typically half an hour, e.g. 1 kW·h used over half an hour is a demand rate of 2 kW. Maximum demand is the highest half-hourly rate at which electricity is required during a month or year. Peak load or peak demand are the terms usually used for heat energy. A graph of demand rate over a typical day, for example, is the demand profile. Cascade control. A system that automatically starts up or stops units in a predetermined sequence to meet variations in the energy demands being served. The sequence may be changed periodically to ensure that the running time of each unit is approximately equal. Catalytic converters. Devices used to convert undesirable components of exhaust gases into other less objectionable forms. There are two catalytic conversion processes relevant to chp plant: Selective catalytic reduction. Reduction of NOx by injecting — ammonia ahead of a vanadium or titanium catalyst to initiate a chemical reaction to convert NOx and NH3 into N2 and H2O; >95% reduction of NOx may be achieved. — Oxidation catalytic conversion. Reduction of CO and nonmethane hydrocarbons by use of an oxidation catalyst. Conversion of CH3 through CH8 is highly temperature depend­ ent, requiring temperatures above 415 °C for any significant reduction. cchp. See Tri-generation. CO, carbon monoxide; CO2, carbon dioxide. Oxides of carbon produced by fuel combustion. CO represents incomplete combus­tion and can be burnt to CO2 , which is the product of complete combustion. Coefficient of performance (cop). For a refrigeration system, the ratio of useful cooling effect to the total energy input to the system. For a heat pump system the ratio of useful heating effect to the total energy input to the system. Diesel engine. A generic term for compression ignition reciprocating engines, whatever the fuel used. Discount factor. The factor used to convert net annual cash flow to present value, depending on the interest rate and the number of years from present. Calculated by a derivation of the compound interest formula: df = 1/ (1 + r /100) n where r is the interest rate (%), n is the number of years from present. Discounted cash flow (dcf); internal rate of return (irr). The discounting rate that gives a ‘break even’ result, i.e. zero net present value. It can be compared with other investments or the cost of borrowing. Discounted cash flow (dcf), net present value (npv). The value of cash inflows less the value of cash outflows over the life of a project, with all future cash flows discounted back to present day values. Used to compare optional projects against a common index Distribution Network Operator (dno). The companies that own and operate the public electricity network under licence. Dual-fuel. The use of two fuels in a prime mover or boiler. They may be alternatives, e.g. with one as standby if the main fuel supply is interrupted, or simultaneous, e.g. gas plus a small proportion of diesel used in compression ignition engines. Co-generation. See Combined heat and power. Energy audit. A review of energy use and costs normally performed in conjunction with a site investigation. Combined heat and power (chp). Combined generation of heat and electricity. Also known as co-generation. Energy manager. A person in an organisation with responsibility for energy matters. Compression ignition. System used in reciprocating engines whereby fuel is injected after compression of the air and is ignited by the heat generated by compression. As pre-ignition is thereby eliminated, higher compression ratios than with spark ignition engines can be utilised, with corresponding higher energy conversion efficiency. Energy service companies (escos). Companies offering a total energy supply service who take responsibility for provision, financing, operation and maintenance of energy facilities. Energy services contracts may be worded to define the outcome of the service provided, temperatures and light levels, rather than how much energy is to be supplied. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 64 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Appendices 65 Energy survey, comprehensive. A detailed site investigation of specified aspects of energy use providing firm recommendations for energy saving measures. Medium temperature hot water (mthw). Pressurised hot water at 95 ºC to 120 ºC used for space heating and process. Energy survey, concise. A short site examination of specified aspects of energy use to identify potential energy saving measures. Monitoring and target setting (m&t). A method of energy management in which real energy consumption is recorded regularly and related to specific variables to allow comparison with the standard or target values calculated. Corrective action is then taken where appropriate. Excess air. Reciprocating engines and gas turbines have to operate with far more air than is needed purely for the combustion of the fuel. This excess over requirements forms the major proportion of the exhaust gases and is termed excess air. Fault level. The maximum prospective current that can flow under a 3-phase short-circuit condition. It should be noted that it may vary according to the point in the system at which the fault occurs. The magnitude of the fault level has a major influence on the choice and design of the equipment to be used. Montreal Protocol. International agreement signed at Montreal in 1990 to control the use of and ultimately reduce the release of substances into the atmosphere that contribute to depletion of the ozone layer. Substances covered by the protocol include those used as refrigerants and firesuppressants such as: — cfc: — hcfc: — hfc: hydrofluorocarbon Gas supply, interruptible. A supply of gas, which may be interrupted within specified limits at the discretion of the supply company allowing lower contract prices than a firm supply for large users. The allowable interruption period is negotiable. — btm: bromotrifluoromethane — bcf: Gas supply, firm. A supply of gas available continuously. Network. The distribution system which links energy production to energy usage. Mostly applied to electricity. Frequency. The number of times per second that alternating current changes direction. Frequency is expressed as hertz (Hz). The public electricity supply frequency in the UK is 50 Hz. Generator. An alternator or dc generator. ‘Generator set’ refers to the combination of prime mover and generator. Heat exchanger. A device in which heat is transferred from one fluid stream to another without mixing. There must obviously be a temperature difference between the streams for heat exchange to occur. They are characterised by the method of construction or operation, e.g. shell-andtube, plate, rotary. Heat-to-power ratio. The amounts of heat energy and electricity produced by a chp unit, expressed as a ratio. High temperature hot water (hthw). Pressurised hot water at 120 ºC and above used for space and/or process heating. In-duct burner. A burner sited inside the duct of the air or gas stream it is heating, and thus also adding its combustion products to the stream. A typical method of supplementary firing where direct heat recovery is employed. ippc. Integrated pollution prevention and control Load factor. The average intensity of usage of energy producing or consuming plant expressed as a percentage of its maximum rating. An annual load factor, for example, would be: Annual heat consumption Í 100 Load factor (%) = —————————————— Peak demand Í 8760 Low temperature hot water (lthw). Hot water at up to 95 ºC used for space heating and low temperature process. Maximum demand (md). Maximum power, measured in kW or kVA, supplied to a customer by a supply/distribution company, equal to twice the largest number of kW·h or kVA·h consumed during any half-hour in a specified period (usually a month). Charges for maximum demand usually vary seasonally. Measures, medium cost. Investment measures that involve a medium level of capital expenditure. Measures, good housekeeping. Actions that can be taken to save energy, requiring no capital expenditure. Measures, low cost. Energy saving measures requiring minimal capital expenditure. Measures, high cost. Measures involving major capital expenditure that may need further study and authorisation at executive level. chlorofluorocarbon hydrochlorofluorocarbon bromochlorofluoromethane Parasitic load. Electricity used within the chp plant itself and therefore reducing the amount available for beneficial use. Particulate. Particles of solid matter, usually of very small size, derived from the fuel either directly or as a result of incomplete combustion and considered deleterious emissions. Performance guarantees. Performance guarantees may be defined by reference to absolute measures such as absolute quantity of heat or power produced. However, these will depend on uncontrollable factors such as warm or cold winters. Alternative measures attempt to assess the degree to which the plant was capable of providing its specified output. These indicators are availability, reliability and utilisation and are defined below, where A is the actual hours plant was run during period (h), P is the planned operating hours in period, S is the scheduled plant downtime for maintenance and U is the unscheduled plant downtime for plant defects. Availability defines what might reasonably be expected of, or is achieved from, the plant allowing for scheduled and unscheduled downtime: P – (S + U) Availability = ­­­­————— P Reliability measures the unscheduled downtime of the plant: P – (S + U) Reliability = ­­­­————— P–S Utilisation is a measure that takes into account when the plant was actually running and so includes all occasions when the plant was prevented from operating by external factors, e.g. low heat load: Utilisation = A / P Performance indicator (pi). The value of annual energy consumption related to a building or site characteristic; most commonly kW·h per square metre of floor area under consideration. Planning co-ordinator. Function defined under the CDM Regulations. The planning co-ordinator is responsible for collating information for the health and safety file. Combined heat and power for buildings Power factor. The quantification of the time lag between the voltage wave and the current wave expressed as the cosine of the angle (f ) between true (active) power (kW) and apparent (reactive) power (kVA). cos f = [kW] / [kVA] Supply contracts usually have a direct or indirect penalty charge for poor power factor (say below 0.95), which can be avoided by installing power factor correction equipment. Premium. A general term to describe the quality of a fuel in terms of handling/storage combustion, consistency of composition, pollutants etc., e.g. natural gas high premium, heavy fuel oil low premium. Fuel price usually follows premium value. Principal contractor. A function defined under the CDM Regulations. Programmable logic control (plc). A programmable device for the control of a system accor­ding to a predetermined logic. Reciprocating engine. Machine in which the mechanical power is produced by the to-and-fro (‘reciprocating’) movement of a piston within a cylinder; such machines are so called to distinguish them from purely rotating machines such as turbines. Salient pole generator. A type of electricity generator. As frequency depends on speed multiplied by the number of pole pairs, lower speeds require more poles than can be accommodated within the rotor periphery. The excitor winding is therefore formed with copper strip or coils of wire attached to the surface of the rotor. Sankey diagram. A diagram demonstrating graphically and in true proportion the energy flows in a system, starting with the energy sources and showing losses, heat exchange loops etc. to the degree desired. Shell-type boiler. A cylindrical steam, hot water or thermal boiler, usually horizontal but possibly vertical. The shell contains water or oil that is heated by the burner flame and combustion products in a chamber and tube or annular flueways inside the shell. Sometimes called a fire tube boiler in contrast to the water tube boiler. A typical shell boiler is in fact a specialised shell-and-tube heat exchanger. Simple payback period. The time calculated to recover an investment when the capital cost of implementing a measure is divided by the net annual saving. Soft-start. A technique for starting a motor from rest which reduces the maximum current drawn during start-up. SOx. A generic term for oxides of sulphur produced by the combustion of sulphur in the fuel, and considered as deleterious emissions. Their presence in flue gases can restrict thermal efficiency, because if the flue gas temperature is reduced below specific levels, highly corrosive sulphurous and sulphuric acids are deposited on heat exchange surfaces. Spark ignition. A reciprocating engine that utilises an electrical spark to ignite the compressed air/fuel mixture in the cylinders. stw. Setting to work, taken to include testing and commissioning Supplementary firing. The firing of additional fuel in the chp heat recovery unit, utilising the hot oxygen present in the prime mover exhaust gases as excess air. Synchronism. The condition whereby generator frequency, voltage levels and phase angle match those of the public supply. When operating in parallel mode, it is obligatory to maintain these levels within closely specified limits. Total energy plant. See Combined heat and power. Transformers (voltage). A device with primary and secondary windings to convert the voltage of electricity from one value to another. Transformers may be step-up or step-down, i.e. voltage increased or reduced, and there may be more than one secondary tapping to give a choice of output voltage. Shaft efficiency. That percentage of its initial energy supply that a prime mover delivers as mechanical energy at its output shaft. Tri-generation. Combination of chp with absorption chilling to give simultaneous production of heat, power and cooling; often power and heat in winter, power and cooling in summer. Shell-and-tube heat exchanger. A unit having a bundle of tubes contained in a cylindrical shell. One fluid flows through the tubes, the other through the shell. Uninterruptible power supply (ups). Device for maintaining power to a service for a limited period following a supply failure. Used to maintain essential service supply and to allow for controlled shut-down of sensitive equipment. Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 66 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 Index Index Note: page numbers in italics refer to figures. absorption chillers 8, 34, 43, 61–62, 64 acceptance criteria 49 acceptance testing 55 acoustic enclosures 6, 47 adsorption chillers 8, 64 air quality management 26–27 air supply systems 44–45 air turbines 9 ambient temperatures 5, 48 anaerobic digestion (ad) 11 asynchronous generators 6 auxiliary firing 7, 64 availability, plant 58, 66 availability charge 64 (building energy management systems) 45, 64 biogas chp 9–10, 11 bioliquids 10 biomass chp 8–9 biomass gasifiers 9–10, 11 biomethane injection 11 building applications 2, 17 building energy management system (bems) 45, 64 building heating systems, integration with 16–17, 20–21, 32, 41–43, 50, 60 Building Regulations 28 bypass flows 19, 20 bems calorific values (cv) 24, 64 capacity see sizing capital costs 34 carbon emissions 3, 14–15, 24–25, 28, 64 Carbon Reduction Commitment (CRC) 28 carbon trading 28 cascade control 42, 64 catalytic converters 26, 44, 64 CDM Regulations (2007) 39 cem (contract energy management) 37, 65 chimneys 27 CHPA (Combined Heat and Power Association) 4 CHPQA (CHP Quality Assurance Programme) 28–29 client acceptance testing 55 Climate Change Act (2008) 28 Climate Change Levy exemption 47 CO2 emissions 3, 14–15, 24–25, 28, 64 coefficient of performance (cop) 22 combined cooling, heating and power (cchp) see tri-generation Combined Heat and Power Association (CHPA) 4 combustion air supply 44 combustion exhaust systems 44, 45 combustion gases 26–27 commissioning 49, 54, 61 component testing 53–54 compression ignition 7, 65 condition monitoring 57 Construction (Design and Management) Regulations 39 consultants 39 consumable spare parts 58–59 contract energy management (cem) 37, 65 contractors responsibilities 39 selection 51 contracts maintenance 58 67 contracts (continued) procurement 51–52 Control of Noise at Work Regulations (2005) 40 control systems 32, 45, 46 conversion factors 64 cooling air supply 44 cooling demand 12–13 cooling systems 8, 22 cost appraisal 34–36, 52, 59–60 CRC Energy Efficiency Scheme 28 cylindrical rotor generator 65 data logging 56 delivery of equipment 49 demand loads 12–13, 30–32, 65 design 39–51, 61 diesel engines 7, 65 differential pressure control valves (dpvc) 18 discounted cash flow (dcf) 35–36, 65 distribution network operators (dno) 65 grid connection 29, 32, 43, 47 district cooling 22 district heating 4, 18–22, 49, 60 diversity of demand 19, 50 dno see distribution network operators (dno) documentation 49, 54, 56 domestic chp 6–7 downtime 58 dpcv (differential pressure control valves) 18 dual-fuel options 33, 65 dual-fuel reciprocating engines 7 economic appraisal 34–36, 52, 59–60 electrical demand 12, 31 electrical efficiency 23, 34 electrical generators 6, 32, 65 micro-turbines 6 standby operation 17–18, 43–44 voltage generated 48 electrical systems 32, 43–44 Electricity at Work Regulations (1989) 39 electricity export 15, 19, 29 electricity tariffs 13 emission control 26 emission reduction targets 28 emissions trading 28 energy audits 31, 65 energy demand 12–13, 30–33 energy efficiencies 2, 22–24, 28 energy flows 33 energy from waste 10–11 energy manager 65 energy savings 2, 22–26 energy service companies (esco) 37–38, 65 energy strategy 1, 28 energy surveys 31, 65 energy tariffs 13, 56 energy units 64 Enhanced Capital Allowances (ECAs) 29 environmental impacts 26–27, 60 see also CO2 emissions equipment supplier finance (esf) 36–37 equivalent heat efficiency 22–23 escos (energy service companies) 37–38, 65 European Union Emissions Trading Scheme (EU ETS) 28 excess air 26, 65 exhaust gases air quality issues 26–27 heat recovery 5, 16, 33, 40, 45 temperature 33 exhaust noise 47 exhaust systems 44 exhaust termination 48 existing buildings 20–21 fault levels 32, 43, 65 feasibility studies 30–38, 59 feed-in tariffs 15, 29 financial appraisal 34–36, 52, 59–60 financial incentives 3, 28–29 financing options 36–38, 52 fire detection, protection and suppression 47, 48 flow control 41, 42, 50 flow rates 18, 20 flow temperature see operating temperatures flue dispersion modelling 27 flue gases see exhaust gases flushing and filling 53 fuel cells 6–7, 7–8 fuel oil, calorific value 64 fuel options 33 fuel supply 48 fuel tariffs 13, 56 gas boilers CO2 emissions 25 equivalent heat efficiency 23, 24 gas detection systems 47 gas engine chp units 5–6 gas leakage detection 40 gas safety 39–40, 44 Gas Safety (Installation and Use) Regulations (1998) 39–40 gas supply 33, 44, 65 gas turbine chp 6, 7 gas-fired power stations relative CO2 emissions 3, 25 relative efficiencies 23, 24 gasification systems 9–10, 11 generators see electrical generators government policy 3, 28–29 grid connection 29, 32, 43, 47 grid efficiency 22–24 gross calorific value (gvc) 24 handover 54 health and safety 39–40, 44 heat demand 12–13, 32 heat distribution systems 16–17, 32, 41–42, 50 heat efficiency 22–24 heat exchangers 5, 16, 40, 65 district heating 19, 49 domestic hot water 19 heat pumps 11–12, 18 CO2 emissions 25 equivalent heat efficiency 22, 23, 24 heat recovery 16, 41 exhaust gases 5, 16, 33, 40, 45 options 33 ventilation exhaust 33, 45 heat rejection 16, 40, 45, 47, 48 heating systems see building heating systems heat-to-power ratio 23, 65 high temperature hot water (hthw) 7, 65 hot water heating 19 demand 12, 16, 17 district heating 49, 50 hydrogen fuel 7 in-duct burners 65 installation 53, 61 instrumentation 32, 45 insulation, pipe systems 50–51 integrated pollution prevention and control (ippc) 26–27, 65 intercooler heat recovery 5, 33, 40, 41 internal rate of return (irr) 14, 15, 35–36, 65 investment appraisal 13–15, 34–36 invitations to tender (itt) 51 ippc (integrated pollution prevention and control) 26–27, 65 joint ventures 38 landfill gas 10 leasing arrangements 38 legislation 28–29 health and safety 39 plant emissions 26–27 liquid biofuels 10 load control 18 load factor 65 load profiles 12–13, 30–32 low temperature hot water (lthw) 16, 65 lubricating oil storage and handling 27, 46, 49 m&t (monitoring and target setting) 37, 66 maintenance 45–46, 57–59 contracts 49, 58 costs 34 manuals 56 schedules 57 maintenance costs 34 maximum demand (md) 18, 65 measures (energy efficiency) 2, 65–66 medium temperature hot water (mthw). 66 metering 31, 32, 48 micro gas turbine chp 6, 9 mini-chp 6 monitoring energy demand 31, 32 plant 45, 46, 48, 55–56, 57, 58 monitoring and target setting (m&t) 37, 66 Montreal Protocol 66 multiple chp units 15–16 multiple heat sources 22 natural gas calorific value 24, 64 efficient use of 2 supply 33 net calorific value (ncv) 24 net present value (npv) 14, 15, 35–36, 65 new buildings 19, 32 noise control 27, 46–47 NOx emissions 10, 26, 27, 48 occupancy, building 17 off-site testing 49, 53–54 oil sample monitoring 57 oil spillage 27 operating temperatures 16–17, 41 control of 43 district heating 18, 19, 20, 49 specification 48 thermal stores 21 operation of plant 55–56, 61 operating costs 3, 34 Combined heat and power for buildings operating hours 12, 15 operating manuals 56 operating models 13 operating services 56 operating strategies 33, 48, 55 organic Rankine cycle (orc) 9 package specification 48–49 parasitic loads 58, 66 particulate emissions 26, 66 part-load operation 15, 19, 20, 41, 43 peak boilers 19, 20–21, 50 peak demand 12, 13, 20–21 performance of plant 33 energy efficiencies 2, 22–24 guarantees 58, 66 monitoring 56 performance indicator (pi) 66 specification for tendering 51 targets 37 pipe systems 22, 47, 50 insulation 50–51 planning conditions 48 planning co-ordinator 39, 66 planning legislation 28 pollution control 26–27 power demand 12, 31 power distribution systems 43–44 power factor 66 power stations district heating schemes 22 relative CO2 emissions 3, 25 relative efficiencies 23, 24 pre-insulated pipework 50–51 premium (fuel quality) 66 principal contractor 66 procurement 51–52, 60–61 programmable logic control (plc) 66 pump control 50 pyrolysis 11 Quality Assurance (CHPQA) Programme 28–29 reciprocating engines 2, 6, 7, 66 refurbished buildings 19 regulatory systems 47 reliability of plant 58, 66 renewable energy and chp 8–12, 11, 25 Renewable Heat Incentive 29 Renewable Obligation Certificates (ROCs) 29 responsibilities 39 retrofit 20–21 return temperatures see operating temperatures ROCs (Renewable Obligation Certificates) 29 salient pole generators 66 Sankey diagram 66 scope of package 48 security of electricity supply 3, 17–18, 25–26 servicing of plant 57–59 setting to work (stw) 54, 66 shaft efficiency 66 shell-and-tube heat exchangers 40, 66 shell-type boilers 16, 66 simple payback period 34–35, 66 siting of plant 48 sizing chp plant 13–16, 33, 48 distribution pipework 50 small-scale chp 6–7, 9, 16, 43 soft-start 43–44, 66 solar photovoltaic 11 solar thermal 11 SOx 66 spare parts 58–59 spark-ignition gas engines 5–6, 66 specification 48–49 standby boilers 50 standby operation 18, 43–44 steam turbines 9, 10 Stirling engines 6, 9 stw (setting to work) 54, 66 sulphur oxides 66 supplementary firing 7, 66 synchronism 66 synchronous generators 6 syngas 9, 11 system testing 53–54 tariffs 13, 56 feed-in 15, 29 technical specification 48–49, 51 tenders 51–52 testing of plant 49, 53–54 thermal efficiency 22–23 thermal storage 15, 21–22 feasibility studies 33–34 operational issues 42–43 thermal treatment of waste 11 training requirements 49 transformers (voltage) 32, 43, 67 tri-generation 3, 8, 26, 34, 61–62, 67 turbocharged engines 5, 33, 40 types of chp 2 UK Building Regulations 28 UK government policy 3, 28–29 uninterruptible power supply (ups) 67 utilisation of plant 2, 17, 30–31, 66 variable flow control 41, 50 ventilation air exhaust air quality issues 27 heat recovery 33, 45 ventilation of plant 40, 44–45 vibration control 46–47 voltage generated 48 waste-to-energy technology 10–11 water quality 22 wind turbines 11 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351 68 Robert W M Gichuba, rgichuba@yahoo.com, 10:51am 23/09/2013, 1, 35351