SIE3012 – Integrated Work Study Programme (IWSP) Final Report Jazly Aris Bin Hashizam Aris 2001140 Page |i Sustainable Infrastructure Engineering (Land) Engineering Cluster Singapore Institute of Technology AY2022/2023 24th July 2023 DECLARATION I hereby declare that this IWSP final report has been cleared and approved by all my present and past IWSP Work Supervisor/s that the report does not contain any company’s proprietary or confidential information. Signature Jazly Aris Bin Hashizam Aris 24th July 2023 P a g e | ii Summary The student’s IWSP was with Land Transport Authority’s (LTA) Network Renewal (NWR) Light Rapid Transit (LRT) Division. NWR manages projects involving Sengkang-Punggol LRT (SPLRT) and Bukit Panjang LRT (BPLRT). He was assigned to assist in project C801B: Asset Replacement And Reliability Enhancement Works For Bukit Panjang Light Rail Transit. The project is split into three major components, Signalling, Rolling Stock and OCC. The student was assigned to the team in charge of C801B's rolling stock component, primarily working on project management-related tasks like attending meetings and taking minutes, organising work crews on-site, and showing up for site activities like site surveys, installations, and testing and commissioning affairs. Tracking all contractual submissions and the status of test reports was another responsibility assigned that was not limited to Rolling Stock. The student was given 2 primary tasks and a continuous task to focus on throughout the 12-month IWSP studentship. Firstly, to create an Excel file that would be able to automatically track the details of documents submitted into LTA’s engineering documents system (EPIC). Secondly, to produce a guidebook that can be used to introduce new hires to BPLRT. Lastly, a continuous task to create an Excel template where the test completion of each vehicle can be tracked. This template will be used for both NCX1 and NCX2. The Excel required the student to furnish the status and set of information, specified by the task giver, for every single document. This Excel would not only track the documents in EPIC that have been submitted but also the documents that were to be submitted later. The completion of this project would mean an Excel that would automate the current manual process of searching EPIC for each document. Thus, eliminating mistakes from human error and reducing work time from 2 days to 30 minutes. The second task was for the student to create a guidebook with information on the BPLRT system. This guidebook would brief new hires on what the BPLRT system is, how it functions, and what is being upgraded. It would be a guidebook consolidating the information gathered from various documents, the student, SMRT staff and LTA P a g e | iii staff. This helps speed up the familiarisation process for new hires as all the information has been gathered in the guidebook. The guidebook would be an ongoing project with new information added and old information updated or removed. For a student entering the workforce, the IWSP studentship with the LRT project team over the past 12 months has been a fascinating and crucial experience. The ability to apply concepts from school modules on Rolling Stock, Signalling and Maintenance, to a real-world system related the theoretical concepts from the textbooks to the practical world. The student learned project management skills as well, learning how to understand Gantt charts, managing works according to criticality and urgency, and how to preside over a meeting. Being tasked with real-world experiences, helped the student apply theory to practice and become a proficient professional in the railway industry. P a g e | iv Acknowledgment I would like to express my deepest gratitude to Mr Low Tian Leng (Deputy Director BPLRT Projects), Mr Teo Kim Yon (Project Manager - BPLRT Projects, IWSP Industry Reporting Officer), Mr Jayson Ang (Senior Project Engineer - BPLRT Projects Rolling Stock) and Professor Kenneth Sng (IWSP Academic Supervisor) and all the members of LTA’s BPLRT Project Team. The team as a whole has made my IWSP experience has been a fruitful one. At no time during the 12-month journey did I ever feel lost or overwhelmed. They have ensured that all the required resources for my growth in the workforce were provided and guided me through every hurdle I encountered. Page |v Contents 1. Background ......................................................................................................................................... 1 1.1 Company Background ................................................................................................................... 1 1.2 Company Structure ....................................................................................................................... 1 1.3 BPLRT Background ........................................................................................................................ 2 1.4 Contract Background .................................................................................................................... 3 2. Job Scope and Responsibilities ........................................................................................................... 5 2.1 Project Management Responsibilities ...................................................................................... 5 2.2 Technical Responsibilities ......................................................................................................... 6 3. Training and Courses Attended........................................................................................................... 7 4. Tasks and Projects Undertaken........................................................................................................... 8 4.1. Project 1 – Automated Document Tracking................................................................................. 8 4.1.1 Project 1 Background ............................................................................................................. 8 4.1.2 Project 1 Scope ...................................................................................................................... 8 4.1.3 Project 1 Methodology .......................................................................................................... 8 4.1.4 Project 1 Automation ........................................................................................................... 10 4.1.5 Project 1 Deliverable ............................................................................................................ 12 4.1.6 Project Enhancement ........................................................................................................... 12 4.2. Project Guidebook ..................................................................................................................... 13 4.2.1 Project 2 Background ........................................................................................................... 13 4.2.2 Project 2 Scope .................................................................................................................... 13 4.2.3 Project 2 Methodology ........................................................................................................ 13 4.2.4 Project 2 Deliverable ............................................................................................................ 15 4.3 Continuous Testing Task ............................................................................................................. 15 4.3.1 Task Background .................................................................................................................. 15 4.3.3 Task Methodology................................................................................................................ 16 4.3.4 Task Deliverable ................................................................................................................... 17 5. Skills Attained .................................................................................................................................... 17 5.1 Soft Skills Attained ...................................................................................................................... 17 5.1.1 Interpersonal Skills ............................................................................................................... 17 5.1.2 Meeting Etiquette ................................................................................................................ 18 5.1.3 Project/Time Management .................................................................................................. 18 5.2 Technical Skills Attained.............................................................................................................. 19 5.2.1 Meeting Minute Writing ...................................................................................................... 19 6. Self-Reflection ................................................................................................................................... 19 7. References ........................................................................................................................................ 21 P a g e | vi List of Figures Figure 1 Rail E&M Organisation Chart ....................................................................... 2 Figure 2 BPLRT System Map in 1999 [1] ................................................................... 3 Figure 3 NCX1 Vehicle Delivered for C801B [2] ......................................................... 4 Figure 4 NCX2 Lifted onto Guideway ......................................................................... 4 Figure 5 Attend Director Meeting ............................................................................... 5 Figure 6 Installation on Guideway .............................................................................. 7 Figure 7 Vehicle testing .............................................................................................. 7 Figure 8 Example of Documents to be Submitted List.............................................. 10 Figure 9 Sample of Extracted List from EPIC ........................................................... 10 Figure 10 Excel Information Template...................................................................... 11 Figure 11 VBA Script Sample ................................................................................... 11 Figure 12 Summary Tables ...................................................................................... 12 Figure 13 Example of Under Review Table .............................................................. 13 Figure 14 Guidebook Outline Example..................................................................... 14 Figure 15 Guidebook Example ................................................................................. 15 Figure 16 Test Procedure Example .......................................................................... 16 Figure 17 Tracking Example .................................................................................... 17 Figure 18 Eisenhower Matrix [3] ............................................................................... 18 List of Tables Table 1 EPIC Status ................................................................................................... 9 Table 2 Summary page Project Status ....................................................................... 9 Table 3 Required Information to be Displayed ........................................................... 9 P a g e | vii 1. Background 1.1 Company Background Singapore's land transport development is regulated by the Land Transport Authority (LTA), a statutory division of the Ministry of Transport. Established in 1995, it is responsible for managing the infrastructure and procedures for planning, designing, building, and maintaining transportation. By integrating a more environmentally friendly and accessible public transportation system, LTA hopes to increase Singapore's land transportation connectivity. LTA has been steadily enhancing Singapore's rail and bus infrastructure as the city's commuter population grows. To fulfil the daily commuter demand of seven million people, more trains and buses must be purchased. The infrastructure must also be upgraded to be able to handle these increasing demands. As there are more neighbourhoods, LTA is also attempting to improve commuter accessibility by enlarging the rail network. By incorporating modern technologies into LTA’s Master Plan, LTA hopes to enhance road linkages and point-to-point travel alternatives while boosting the dependability of the public transport system. This is in line with LTA's objective to develop a ground transport network in Singapore that links different communities and locations by having a dependable public transit system, smoothing traffic flow on the roads, and viable transport options for the differently abled. 1.2 Company Structure LTA is divided into multiple divisions that deal with the various facets of transport in Singapore. Some of the divisions include the Thomson-East Coast and Cross Island Lines, Traffic and Road Operations, Rail Asset Ops and Maintenance, Rail Infrastructure and Expansion, and Rail Electrical and Mechanical. The student carried out his 12-month IWSP in LTA’s BPLRT team. The BPLRT team is a subgroup of the Light Rail Transit group which is a part of the Rail Electrical and Mechanical division. The BPLRT team manages projects involving various systems for Bukit Panjang as shown in the table below. Page |1 Figure 1 Rail E&M Organisation Chart 1.3 BPLRT Background A significant component of the city-state's public transport system is the BPLRT system, situated in the western part of Singapore. The earliest light rail transit line in Singapore started revenue services on 06 November 1999. The 7.6-kilometre long BPLRT system is an automated guideway transport with 13 stations distributed in the region of Bukit Panjang and Choa Chu Kang and a depot situated in Junction 10, previously known as Ten Mile Junction. The BPLRT system currently has a fleet of 19 ECX vehicles in service since 1999, and 13 NCX2 vehicles in service since 2015. As of July 2020, the BPLRT system, which is run by SMRT, has a daily ridership of about 64,781 people per day. Page |2 Figure 2 BPLRT System Map in 1999 [1] 1.4 Contract Background The contract the student would be involved in is titled C801B: Asset Replacement And Reliability Enhancement Works For Bukit Panjang Light Rail Transit and will now be referred to as C801B. The contract was awarded to Bombardier Transportation (acquired by Alstom on 29 January 2022) on 07 March 2018. The contract consists of: 1) Replacing the legacy Signalling system, CityFlo 550, with CommunicationsBased Train Control (CBTC), CityFlo 650 2) Manufacturing, delivery and testing of 19 new vehicles (NCX1) 3) Retrofitting and testing of 13 existing vehicles (NCX2) Page |3 Figure 3 NCX1 Vehicle Delivered for C801B [2] The C801B site office is located beside the BPLRT depot on State Land MK1103827APT along Choa Chu Kang Road. The site office houses Alstom and LTA personnel where meetings and discussions take place daily. The site office is also the location where the NCX1 and NCX2 vehicles are lifted onto the BPLRT guideway through the use of a 250-ton crane seen in Figure 4. Figure 4 NCX2 Lifted onto Guideway Page |4 2. Job Scope and Responsibilities The student was assigned to LTA’s LRT Division BPLRT Project Team, who is undertaking project C801B: Asset Replacement And Reliability Enhancement Works For Bukit Panjang Light Rail Transit. The student was assigned to assist the team in charge of C801B's rolling stock component as a Project Engineer. This involved both Project Management and Technical Responsibilities. 2.1 Project Management Responsibilities Under Project Management, the student was involved in multiple tasks that required project management skills to complete. The tasks were: 1) Attend Meetings – The student attended meetings, shown in Figure 5, where technical and contractual matters were discussed. The student took meeting notes during the meetings and wrote meeting minutes after each meeting. Minutes for each meeting will need to be updated, vetted, finalised, and distributed within 3 days of the meeting. The minutes are used for every subsequent meeting and are updated accordingly. Figure 5 Attend Director Meeting 2) Chair Meetings – Once the student gained sufficient knowledge, he was allowed to chair meetings under guidance. This involved ensuring every meeting point in the meeting minutes were discussed and the meeting minutes were subsequently updated with the discussed points. 3) Liaising with Stakeholders – The student was in charge with liaising with Alstom US counterparts for LTA’s visit to the US factories. The student had to ensure the itinerary given by Alstom was feasible and there was enough time for recovery from jet lag. The student was tasked with searching for feasible flights Page |5 from Singapore to the US. The flights had to have the proper arrival and departure date and times, have as little layovers and shortest flight time as possible, and the price of the tickets had to be justifiable. The student was charged with finding suitable accommodation in the US that was suitable for the budget given. The accommodation had to be close to the factories LTA would be visiting and have adequate long stay facilities. 4) Upper Management Visits – The student was tasked with assisting the Managers and Engineers for all upper management visits. These visits included LTA’s Chief Executive, SMRT’s CEO and Alstom’s Upper Management Team. He assisted in the planning of site visit activities and the production of presentation slides. On the day of the visits, the student assisted in the guided tours by ensuring all presentation materials need have been prepared ahead of time. 2.2 Technical Responsibilities The student was also given responsibilities that required technical knowledge and skills. Technical responsibilities were: 1) Document Review – Technical documents are submitted to LTA detailing the vehicle’s electrical and mechanical design, vehicle operating procedures and vehicle maintenance manuals. The student was required to review each submitted document to ensure what was submitted was according to LTA’s specifications and the different international Engineering Standards. 2) Safe Work Method Statement (SWMS) Review – Ensure the installation methods detailed in the SWMS follow safety guidelines and appropriate LTA installation methods. This includes but is not limited to, the correct and appropriate use of PPE, tools to be used, number of manpower, method of entry to the work site, delivery of tools and equipment to the work site, and the method in which the work is to be carried out. 3) Site Installation – Supervision of site installations required the student to know and understand what was to be installed and how to install it correctly and safely. This required the student to know the basic safety requirements during installations. Page |6 Figure 6 Installation on Guideway 4) Vehicle Testing – The student supervises vehicle testing, seen in Figure 7, to ensure the test is carried out according to the accepted test procedures. During the tests the student, was to ensure no deviations from test procedures and if any deviations were required, they were to be noted down for review. Test results were to be taken down after every test to compare against the officially submitted test reports to ensure no mistakes or deviations from the actual test results. Figure 7 Vehicle testing 3. Training and Courses Attended The student attended the Safety Induction Course (SIC), chaired by Alstom’s Safety Manager, within the first week of IWSP. The SIC ensures all attendees know the safety requirements for each type of work that would be carried out. The use of personal protective equipment (PPE) was also elaborated on how to wear and when to wear them. Page |7 4. Tasks and Projects Undertaken The student was tasked with multiple responsibilities as elaborated on in Section 2. Job Scope and Responsibilities. In addition to the aforementioned responsibilities, the student was assigned 2 projects and a continuous. Firstly, to create an Excel file that would be able to automatically track the details of documents submitted into LTA’s engineering documents system (EPIC). Secondly, to produce a guide booklet that can be used to introduce new hires to BPLRT. The continuous task was to create an Excel template where the test completion of each vehicle can be tracked. This template will be used for both NCX1 and NCX2. 4.1. Project 1 – Automated Document Tracking 4.1.1 Project 1 Background A part of C801B’s contractually obligated deliverable is the submission of documents detailing the product design, product and installation drawings, test procedures and reports, and operating and maintenance manuals. These submissions can number in the thousands with multiple revisions of the same documents being submitted. These submitted documents will need to be uploaded into EPIC, reviewed and a status assigned within a stipulated timeframe. The status of each submitted document needs to be updated to LTA’s upper management weekly. 4.1.2 Project 1 Scope The student was tasked to create an Excel where the required information on each submitted, and to-be-submitted document is displayed. The information required as specified by the task giver were document number and title, current revision, submitted date of the current revision, acceptance status, review finish date and the number of days LTA took to review the document. A summary page was to be included to show the acceptance statuses of each project stage as defined by the task giver. 4.1.3 Project 1 Methodology Before an Excel could be created, there were a few requirements the student needed to follow and some information the student needed to find out. Firstly, the student had to define the statuses that would need to be displayed which are shown in Table 1. Page |8 Table 1 EPIC Status A Accepted AC Accepted with Comments NA Not Accepted UR Under Review NS Not Submitted Then the project stages needed to be confirmed for the summary page as seen in Table 2. Table 2 Summary page Project Status Stage Pre-Final Pre-Final (Power Rail) Final (Mixed Mode) - SIG/COMMS/PDS Code Only Final (Vehicle) - NCX1 & NCX2 Code Only Final (Full CBTC) - SIG Code Only Final (Option 1 Interim OCC) - OCC Code Only Final (Option 1 Final OCC) - OCC Code Only FCDD (Vehicle) - NCX1 Code Only FCDD (Vehicle) - NCX2 Code Only FCDD - PDS Code Only Test Procedures (Vehicle) - NCX1 Code Only Test Procedures (Vehicle) - NCX2 Code Only Test Procedures (Signalling) - SIG Code Only Test Procedures (Comms) - COM Code Only Test Procedures (Option 1 Interim OCC) - OCC Code Only Test Procedures (Option 1 Final OCC) - OCC Code Only Test Procedures (EMC) - EMC Code Only Test Procedures (Interface) - ITF Code Only Test Procedures (General) - GEN Code Only Thirdly, the required information is to be displayed on each sheet for each project stage as shown in Table 3. Table 3 Required Information to be Displayed Document Number Document Title Current Revision Current Status Document Received Date Document Closure Date Days LTA Review Page |9 Fourth, the student needed the full list of documents there were contractually obligated to be submitted throughout the project. This was supplied to the student by the Project Engineer in the form of a long list in an Excel file shown in Figure 8. Figure 8 Example of Documents to be Submitted List The last piece of information provided to the student was a way for the student to see the status of every document submitted since the start of the project in 2019. This came in the form of an Excel list that was extracted from the EPIC system containing thousands of rows of information similar to Figure 9. Figure 9 Sample of Extracted List from EPIC The method the student came up with to complete this project was to automate the Excel to look up the required information in Table 3 from the extracted list from EPIC in Figure 9 every time the document status information is required to be sent to LTA’s upper management. 4.1.4 Project 1 Automation Before the student could work on the automated process, he had to first create an Excel P a g e | 10 template for the information to be presented as seen in Figure 10. Figure 10 Excel Information Template The template served as a look up table for the document numbers that the Excel would end up using as a reference to search in the extracted EPIC list. Next, the student used Microsoft’s Visual Basic for Applications (VBA) to create a script, seen in Figure 11, that would be run every time a created button in the Excel is pressed. Figure 11 VBA Script Sample The script uses the document numbers column in every Excel sheet, seen in Figure 10, to search for its corresponding row in the extract EPIC list seen in Figure 9. For example, once the script finds the rows which contain the document number “801B/NCX1/2001” it would then search the selected rows to find the row that has the latest revision and use the information only found in that single row. The information is then printed into P a g e | 11 the cells of the Excel sheet seen in Figure 10. 4.1.5 Project 1 Deliverable The final product was an Excel that was able to automate what was done manually. Instead of an Engineer having to manually look up the status and information of every document in EPIC, they would now only need to extract the EPIC list and press a button created in the Excel. The Excel would also automatically update the summary tables in the first sheet as seen in Figure 12. This removed any mistakes that might occur from human error and reduced the time need to complete the task from 2 days to 30 minutes. Figure 12 Summary Tables 4.1.6 Project Enhancement After the project deliverable was completed and disseminated for use, the student spoke to the users on possible improvements that could be made. A popular suggestion was a way for the users to filter what documents had the “Under Review” status. Users wanted a table that showed what documents were currently “Under Review” across all project stages as shown in Figure 13. P a g e | 12 Figure 13 Example of Under Review Table This would have been a simple improvement to implement if the lists of documents were compiled into a single table. Unfortunately, the Excel consisted of multiple sheets with multiple tables in each sheet. For the student to solve problem, he turned to VBA. Through VBA coding, the rows with the documents still “Under Review” in all sheets would be compiled by the code and then displayed in a table similar to Figure 13 in the Summary sheet together with the summary table in Figure 12. User now did not have to go through each sheet in the Excel in order to know what documents were still “Under Review”. 4.2. Project Guidebook 4.2.1 Project 2 Background LTA has new hires as well as seasoned colleagues from other departments joining the BPLRT Project Team. Every time that happens, they would need to be briefed on LTA administration matters and what the BPLRT system is, how it functions, and what was being upgraded for the project. This required repetitive work which often times resulted in different information being shared or information being missed out. 4.2.2 Project 2 Scope The project aimed to create a guidebook that would detail all LTA administration matters and the different railway systems in BPLRT and how they functioned individually, interfaced with each other and how the BPLRT system works as a whole. The guidebook would be updated whenever there are changes to LTA administration or to the current project that is undergoing. Relevant information can be added, and old information updated or removed when needed. 4.2.3 Project 2 Methodology The student created a PowerPoint file with an outline of the information to be included in the guidebook. This would serve as a checklist to ensure sufficient information has P a g e | 13 been included, an example of this checklist is shown in Figure 14. The checklist can be updated to either include more items or remove obsolete ones. Figure 14 Guidebook Outline Example The completion of the checklist would allow the student to source the relevant information for each item. He would need to ascertain where the information can be found by either using the internet, LTA’s intranet or asking LTA and SMRT staff. Before starting the search for information, the student listed out the likely information source for each item in the checklist. This would assist in shortening the time of sourcing for information by collating the different checklist items by their information sources. For example, information for checklist items 1 to 3 and 9 to 11 can be found on LTA’s intranet. Instead of having to access the intranet multiple times, the student can access the intranet and know what information needs to be found there. This method is repeated for all the information sources, reducing the number of times the resource needs to be accessed. The information is then transferred into the relevant pages in the guidebook, hence turning the guidebook into a collated document of all the information from the multiple resources. An example of the information found in the guidebook is shown in Figure 15. P a g e | 14 Figure 15 Guidebook Example 4.2.4 Project 2 Deliverable The guidebook will be provided to the BPLRT team in the form of PowerPoint slides. The guidebook can be printed in PDF format for dissemination and edited in PowerPoint for clarification. The guidebook is still being worked on by the student as not all checklist items have been completed by the end of the 12-month IWSP. This is acceptable as the guidebook is a live document and would be constantly updated according to information changes. 4.3 Continuous Testing Task 4.3.1 Task Background The vehicles (NCX1 & NCX2) under C801B undergo 2 major types of testing, onshore tests that are conducted in Singapore, and offshore tests where the tests are done in Alstom’s manufacturing plant or test facility in Wuhu, China. The tests are conducted through the use of test procedures, where each test would have a specific test procedure assigned to it. A test procedure would contain multiple test cases and a single test case would have multiple test steps. An example of how the test flows can be seen in Figure 16 Test Procedure Example P a g e | 15 Figure 16 Test Procedure Example This test flow would be repeated for every single vehicle that was to be delivered under C801B. Totalling 19 test suites for NCX1 and 13 test suites for NCX2. An accurate method to track each test was needed to ensure no test was left out or had failed for each vehicle. For the purpose of tracking the test statuses, the student created an Excel. 4.3.3 Task Methodology The first step the student took before creating the Excel was to compile the list of tests that would be carried out for NCX1 and NCX2. There were 76 onshore and offshore tests for NCX1 and 31 onshore tests for NCX2. The next step was time consuming as it required the student to read each test procedure carefully. The student had to record down every test step for each of the test case for every test procedure. Certain test procedures might contain only 3 test cases while some can contain up to 12, and each test case can contain from 6 to 20 test steps. This ended up with a significant number of test steps that needed to be tracked for each vehicle. Figure 17 below shows an example of how the tracking of test 902 VATC Static would look like in the Excel. As seen, for test case 13.2 there were multiple test steps that needed to be carried out and results recorded. P a g e | 16 Figure 17 Tracking Example 4.3.4 Task Deliverable Once the student has completed the Excel, the tracking of test completion will be organised and simplified. No test step would be skipped unnoticed, every test result would be recorded, and any test status would be easily verified. 5. Skills Attained Throughout the 12-month IWSP, I was able to cultivate skills that were not taught in school. These skills can be classified into soft skills, skills that help with interpersonal communications, and technical skills that enable me to perform my practical tasks. 5.1 Soft Skills Attained 5.1.1 Interpersonal Skills I have been able to improve my interpersonal skills through constant interaction with people of different socioeconomic, cultural, racial, and religious backgrounds. A method I found useful in improving interpersonal skills would be observing how a senior Engineer is able to take control and calm a tense meeting where tempers start to rise for all parties. Another method is to actively listen when people are talking as compared to listening for the sake of answering or passively listening. I would wait to form an answer only after the other party has completed speaking rather than forming an answer while the P a g e | 17 other party is still speaking. I am also more aware of visual cues the other party might portray and the visual cues I might unintentionally be portraying. For example, crossing my arms while listening might portray a negative emotion when I do not intend to. 5.1.2 Meeting Etiquette I had the opportunity to attend and chair multiple meetings. While attending meetings I learned how to properly behave, to respect the chairperson and also to be more productive throughout the meeting. I am now aware to always be prepared for the meeting before the meeting even starts. This does not just mean being punctual for the meeting but also being aware of the meeting agenda and the meeting minutes if there are any. Respecting the chairperson means giving my full attention to them for the duration of the meeting. I do this by not having my handphone anywhere visible where the buzzing or screen lighting up might distract me or the speaker. Another meeting etiquette I found to be often overlooked would be the tendency to fidget. Fidgeting can be distracting to others in the meeting and might also portray boredom or restlessness. 5.1.3 Project/Time Management Without exception, every project has a deadline, and every task within the project has a deadline as well. I learned to set an appropriate amount of time for every task in accordance with how difficult it may be for me to complete. I learned to judge which tasks to complete first and how much time to assign to them according to their criticality and urgency. A useful tool to do this would be the Eisenhower Matrix [3] seen below in Figure 18. Figure 18 Eisenhower Matrix [3] P a g e | 18 5.2 Technical Skills Attained 5.2.1 Meeting Minute Writing I was given multiple opportunities to write meeting minutes for a multitude of meetings, which ranged from technical meetings to contractual meetings. With the meetings not being recorded, it forced me to improve my listening and writing skills to ensure no points discussed in the meetings were missed out from my minutes. I learned how to take down only the most necessary pointers for each meeting minute agenda. 6. Self-Reflection The IWSP journey has gifted me a better understanding of what it takes to keep our land transport systems moving and be a viable transport option for the residents. It allowed me to appreciate the amount of work LTA and railway operators have to go through to ensure the railway systems in Singapore are safe and reliable. I was fortuitous to have been assigned to LTA’s BPLRT team. After sharing my experiences with the students assigned to other divisions in LTA, I realised I have had the chance to experience many unique instances. I have had the opportunity to telecommunicate with people in multiple time zones and experience the different working customs of people who may work in the same company but are based in different countries. I was given the good fortune of rubbing shoulders with LTA’s CE, Alstom’s upper management and SMRT’s CEO. Being involved in their visits to BPLRT taught me how to portray a professional image to proudly represent LTA. The first few weeks of my IWSP journey were a challenging period. It took some time to familiarise myself with the technical jargon constantly used. I had to quickly learn how the systems were designed to function and how to spot if they were malfunctioning. I overcame this shortfall by always asking questions and always searching for why certain functions behaved the way they do. By always being curious I learned more and fast. I learned many soft skills that would be viable throughout my career not just in the railway sector but all work sectors. One of which would be meeting etiquette, this is a skill that transfers well into all career sectors not just railway. Through polishing my P a g e | 19 meeting skills, I improved my presentations, minute writing and listening skills. I am more eloquent in my presentations which would be a plus when I am being interviewed for positions in a company. IWSP has allowed me to explore a career path in project management to see if it would be a good fit for the mindset and skills I have. It has allowed me to develop and refine the soft and hard skills school has imparted to me. School has planted the seeds of a future engineer in me and IWSP has allowed that seed to grow and flourish. My IWSP journey has established my affinity for a career in project management. I thoroughly enjoyed the experiences and challenges I have journeyed through in my IWSP. P a g e | 20 7. References [1] “Land Transport Guru,” [Online]. Available: https://landtransportguru.net/train/bplrt/. [2] M. Loh, “A Train of Thought,” SGTrains, 19 April 2022. [Online]. Available: https://blog.sgtrains.com/2022/04/new-3rd-generation-bukit-panjang-lrt-trainarrives-in-singapore/. [Accessed 17 July 2023]. [3] V. Bansal, “Tech Tello,” [Online]. Available: https://www.techtello.com/eisenhower-productivity-matrix/. [Accessed 18 July 2023]. P a g e | 21