Project Risk Log Template Wilmont's Pharmacy Drone Project Revision: 0; Date: 2 sep 2023 Risk ID Priority 1 2 3 4 5 6 7 8 9 2 2 2 1 3 1 2 1 2 WBS 1.1.3 1.2.1 1.3.1 Analysis Responsible Person Risk Description Open Katie O'Ryan Contract with Wilmont's cannot be finalized in time for scheduled start 02-Jul-20 of Project Eileen Seymour Design is not completed in a timely manner William Holt Construction of Drones is not completed in a timely manner 1.4.1, 1.4.2, 1.4.3 Eileen Seymour Delay in DroneTech system interface to Wilmont's system 1.4.2 Eileen Seymour Customer data is not protected during regsitration process Sandeep Vasu Cost estimate is incorrect. Fund issues Gerald Hasper Drones fail to operate during testing 1.2.2 1.6.1 1.6.4 1.3.2, 1.6.4 02-Jul-20 02-Jul-20 02-Jul-20 Impact Rating 5 4 4 5 Likelihood Rating 2 3 3 3 Impact Severity 12 Add schedule contingency in plan for design to be complete. Add additional staff $4,000 Add schedule contingency in plan for construction to be complete. Add additional staff $4,000 Add schedule contingency in plan for system interface to be complete. Add additional staff $8,000 12 15 2 4 02-Jul-20 5 3 15 02-Jul-20 5 1 5 02-Jul-20 4 4 16 Gerald Christ Harsh weather affecting Drone Operations 02-Jul-20 William Colt Products delivery problem due to improper packing system Description Contingency Add schedule contingency in plan for contract negotiations to be complete. 2 2 Mitigation Strategy 10 02-Jul-20 4 Prior to After Mitigation Mitigation 8 > 4 Weeks delay <1 week delay Double check system integrity during customer registration > 4 Weeks delay <1 week delay Consider a cost contingency of 10% over budget $25,000 > 2 Weeks delay <1 week delay Alternate delivery methods to be developed and standby in case of adverse weather $10,000 Double check packing system. Trial runs at DroneTech facility before handover Status Impact Rating Scale 5 Very High 4 High 3 Moderate 2 Low 1 Very Low Likelihood Rating Scale 5 Nearly Certain 4 Likely 3 Possible 2 Unlikely 1 Rare Cost Schedule > $ 100,000 < $ 75,000 < $ 50,000 < $ 25,000 < $ 10,000 > 4 Weeks delay > 2 Weeks delay > 1 Week delay < 1 Week delay 1-2 days delay Description > 80% probability of occuring 50-80% chance of occuring 21-49% chance of occuring 1-20% chance of occuring < 1% chance of occuring Scope Quality Drone not operating Product damage Drone performance affected Compensation Required Corrections required