Uploaded by masoha9752

Pile Static Load Test Method Statement

advertisement
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
Issue Date: 06 Nov 2009
Rev No.: 0
METHOD STATEMENT
-STATIC LOAD TESTS OF PILES-
Prepared
Rev.
Date
QA/QC
Eng.
06-Nov-09
Approved
Description
No
0
Checked
First Issue
F. Ulu
T.O Mng.
HSE Mng.
M. Poojari
I. Azizov
QA/QC
S.C. Project
Project
Mng.
Mng.
Manager
J. Beckett
E. Albayrak
C. G. Lee
1/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
Issue Date: 06 Nov 2009
Rev No.: 0
TABLE OF CONTENTS
1. PURPOSE
4
2. SCOPE
4
3. APPLICATION AREAS
4
4. REFERENCES
4
5. RESPONSIBILITIES
4
5.1 Responsibility for implementation of this procedure
4
5.2 Quality Assurance & Quality Control Manager
4
5.3 Laboratory Manager
4
6. EQUÄ°PMENT
5
7. DEFINITIONS and ABBREVIATIONS
5
8. PERMANENT MATERIALS
5
9. WORK METHODOLOGY
5
9.1 General
5
9.2 Test Pile
6
9.3 Reaction Piles
6
9.4 Execution of Compressive Tests
6
9.4.1
Compression Test Load System
6
9.4.2
Test Pile Head Preparation
7
9.4.3
Test Location
7
9.4.4
Test Pile and Instrumentation
8
9.4.5
Reaction System
8
9.4.6
Loading System
9
9.4.7
Settlement Readings
9
9.5 Loading Procedure
10
10. INSPECTION and TESTING
10
10.1
Parties Involved
10
10.2
Tests and Results
10
10.3
Related Documents
10
11. ENVIRONMENT and SAFETY
10
11.1
Protective & Safety Equipment
11
11.2
Risk Assessment
11
11.3
Emergency
11
2/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
Issue Date: 06 Nov 2009
Rev No.: 0
12. RECORDS
11
13. APPENDICES
12
13.1
Conformation of Instructions to Operatives
13
13.2
Risk Assessment
14
3/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
Issue Date: 06 Nov 2009
Rev No.: 0
1. PURPOSE
The purpose of this document is to define the methods and controls employed to ensure that
all static load testing of piles undertaken by the Contractor and the Sub-Contractors engaged
by the Contractor which is designated to be AGT-ZETAS for the project are carried out in a
controlled and systematic manner that in all respects conform to the specified requirements.
2. SCOPE
The method statement refers to the static load testing of cast-in-place bored piles.
3. APPLICATION AREAS
All related departments of the project
4. REFERENCES
References for this document are:
•
•
•
•
•
Construction Specification
Construction Specification Appendix
Designer’s Drawings
Quality Control Manuel
ASTM D 1143-81
5. RESPONSIBILITIES
5.1
Responsibility for implementation of this procedure
QA/QC Manager or his Designee and person in charge for will be responsible of execution of
works.
5.2
Quality Assurance & Quality Control Manager
He is responsible for the “Project Quality Assurance Plan” and the quality control during the
execution of work in field as well as laboratory. All the tests required the Project by
specification are carried out under his supervision. He is assisted by Laboratory Chief.
5.3
Laboratory Manager
The Laboratory Chief is responsible for carrying the tests in the field and laboratory as per
applicable standards and quality assurance plan. All the tests for the quality control are
performed with the help of technicians.
4/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
Issue Date: 06 Nov 2009
Rev No.: 0
6. EQUIPMENT
The equipment/machinery involved for execution of this work consists of:
Mobile Crane
Steel Connection Beam
Welding Machine
7. DEFINITIONS and ABBREVIATIONS
PM =
Project Manager
SM =
TOM =
QM =
QT =
EPE =
Site Manager
Technical Office Manager
QA/QC Manager
QC Technician
Earthwork Engineer
RFI =
Request for Inspection
8. PERMANENT MATERIALS
N/A
9. WORK METHODOLOGY
9.1
General
No. of static load test on preliminary test pile
B20 - 14
Working load (WL)
866 kN
Ultimate test load
866 kN
Standard followed
ASTM D1143-81
Hydraulic jack acting against reaction
Loading system
piles & reaction frame
No. of reference beams
No. of dial gauges/precision
2 parallel (test pile)
2/0.01 mm
5/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
9.2
Issue Date: 06 Nov 2009
Rev No.: 0
Test Pile
Pile cons. platform level
Pile cut-off level
+106.983 m
(pile above sleeved)
Pile toe level
Pile length to cut-off
9.3
+96.983 m
10.00 m
Reaction Piles
Ultimate test load
No of reaction piles
Individual pile load (tension)
866 kN
2
866/2=433 kN
Pile cut-off level
+106.983 m
Pile toe level
+96.983 m
Pile length
9.4
10.00 m
Execution of Compressive Tests
9.4.1
Compression Test Load System
The principle system for axial compression load test is to apply a vertical load to the test pile
using hydraulic jack, getting reaction force from other bored piles which are both sides.
Bored pile axial loading test system is based on getting reaction force from the beam that will
be made installation to the reaction bored piles loading the test pile in the axial direction.
From the three bored piles of the same direction, two are called reaction piles in the edge
and pile in the middle is called test pile.
Test beam must be fixed between two reaction piles and stability of loading system shall be
ensured under maximum test load to be applied. Load will be applied by means of hydraulic
power pack unit connected to the hydraulic jacks. Pressure values corresponding to the
scheduled loads will be adjusted by means of calibrated manometers.
6/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
Issue Date: 06 Nov 2009
Rev No.: 0
Test beam will be prepared with two 800mm pipe which are put under the test beam and
inside the reaction piles. These pipes will be fixed inside the reaction pile’s steel gauge
overlaps and will be welded. Hydraulic jack will be accomodated between test beam and
steel test plate which was fixed on the test pile.
9.4.2
Test Pile Head Preparation
Before commencement of the test, this is need for the preperation head of test pile, which
shall be broken at project level. In this stage, it is necessary to reach strong concrete. Then, if
necessary the required level of test pile can be provided by casting additional concrete. All
steel gauge overlaps must be fixed stirrup re bars up to top level, before concreting.
According to additional concrete sampling result, test can be erected after 7 days.
If test pile defined before construction, steel gauge overlaps shall be fixed all length with
stirrups, and concrete casting shall be continue come to fresh concrete. After this process no
need to breaking pile head and casting new concrete.
9.4.3
Test Location
The test location shall be as illustrated in Figure-1
7/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
9.4.4
Issue Date: 06 Nov 2009
Rev No.: 0
Test Pile and Instrumentation
Test pile will be of 1000 mm diameter with toe level at 96.983 m. Its construction will be
done from the working level at 106.983 m. The shallowest base will be at the same level of
the original cut-off level of 106.983 m, so that the displacement and corresponding friction
resistance up to this depth can easily be differentiated for the accurate representation of the
performance of the original 10 m long pile from 96.983 to 106.983 m.
9.4.5
Reaction System
The following photo and the enclosed drawing illustrate the test set-up planned to be used
for the full scale loading tests.
8/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
9.4.6
Issue Date: 06 Nov 2009
Rev No.: 0
Loading System
The load shall be applied by means of hydraulic jack having a capacity of 500 kN. The jack is
connected to control unit where the hydraulic power is generated by electricity and also
where the pressure in the system (and jack) is monitored by built in manometer(s). The
picture of the loading system is presented below.
9.4.7
Settlement Readings
The settlements shall be read by two (2) micrometers connected to reference beams,
independently supported by steel rebar. Every reaction piles displacement shall be read by
one micrometer connected to reference beams. The micrometers have a range of 0-50 mm
and precision of 0.01 mm. The settlement monitoring setup is illustrated below.
9/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
9.5
Issue Date: 06 Nov 2009
Rev No.: 0
Loading Procedure
Standard Loading Procedure with two cycles shall be applied.
i.
•
First Cycle;
Load the pile 25%, 50%, 75% of the pile working load (WL) and taking four readings for half
an hour.
•
Maintain 100% of the WL for 6 (six) hour and taking 15 readings.
•
Remove the applied load in decrements equal to the loading increments, allowing 15 min.
between decrements.
•
ii.
Maintain 0% of the WL for 2 (two) hours and taking 7 readings.
Second Cycle;
•
Reapply load to 50% of WL and maintain the load for 30 min. and 4 readings.
•
Apply additional 50% of WL and maintain the load for 30 min. and 4 readings.
•
Maintain 100% of WL for 12 hours.
•
Remove the applied load in decrements equal to the loading increments, allowing 15 min.
between decrements.
•
Maintain 0% of the WL for 2 (two) hours and taking 7 readings.
10. INSPECTION AND TESTING
N/A (Already described above)
10.1
Parties Involved
Inspection and Testing will be conducted in accordance with the Contract Documents and
will include the responsible person mentioned sub-section 5; i.e. internal and external
representatives.
10.2. Tests and Results
Test results will be prepared by AGT-ZETAS and will be submitted to Engineer for review
10.3
Related Documents
•
RFI
: Request for Inspection
•
RFT
: Request for Testing
11. ENVIRONMENT and SAFETY
Project Safety Manuel ref: YKGN-UAJV-HSE-01 and risk assessment will be followed
10/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
11.1
Issue Date: 06 Nov 2009
Rev No.: 0
Protective & Safety Equipment
All workers engaged in embankment works shall wear appropriate PPE to minimize the risks.
•
•
•
•
11.2
Safety Shoes
Reflective Jackets
Gloves
Eye Protective Glasses
Risk Assessment
See Appendix 1
11.3
Emergency
In case of emergency, contact person and contact number is as listed below:
-
Ilgar Azizov : 050 255 38 89
Zaur Ganbarov: 055 209 22 47
(Safety Manager)
(Structural Engineer)
12. RECORDS
Full records of the test will be submitted to the Engineer for review.
11/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
Issue Date: 06 Nov 2009
Rev No.: 0
13. APPENDICES
APPENDICES
12/14
Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project
STATIC LOAD TEST OF PILES
Doc. No: YKGN-UAJV-MS-13
13.1
Issue Date: 06 Nov 2009
Rev No.: 0
Conformation of Instruction to Operatives
Those names listed below confirm receipt of the method statement and have had the
contents explained to them/understand it and are aware of the requirements.
Name & Surname
Job Title
Date
Sign
13/14
The Employer
The Engineer
The Contractor
AZERROADSERVICE OJSC
Project : Yevlakh-Ganja Road Section Widening to 4-Lane Project
RISK ASSESSMENT
Method Statement No: MS-13 Rev. 0
Hazard
1
2
Factors of Harm
Likelihood
Severity
Activity: STATIC LOAD TEST OF PILES
Assesed By: FATIH ULU
3
4
Risk
Rating
Enviromental
Risks
2
2
4
Traffic
Accidents
3
3
9
Hand &
Mechanical
Tools
2
3
6
Weather
Conditions
1
2
2
Chemicals in
Concrete
1
2
2
Rigging
(Lifting)
Operations
2
3
6
Welding
Works
2
2
4
Proposed Control Measures (PCM)
1) Good hosuekeeping habit must be maintained at all the time
2) Trenches/ excavation must be properly enclosed with barriers and
warning signboard.
3) Spillage of diesel and oil leakage to rivers shall be prevented by taking
necessary precautions
5) Provision of proper training for all operatives.
6) Ensure all operatives using PPE propperly
1) Mandatory/ informative / directional signs must be posted on all
strategic points.
2) Separate vehicular routes from pedestrian routes on site.
3) High reflective jackets must be worn by operatives all the time while
at work
4) Adequte warning lights shall be used during nightshift work
5) Close supervision during work in progress
6) Provision of proper training for all operatives.
7) Proper housekeeping must be carried out to avoid fire hazard.
8) Proper PPE must be used
9) Adhere to the speed limit on site
10) Equipments shall have reverse warning noise indicators
1) Provision of tool bags while working.
2) Inspecting tools for loose and deflecting parts.Reports and replace
immediately.
3) Wear appropiate PPE.
1) Drinking cold water when hot.
2) Resting in suitable shaded areas in hot weathers
3) Adequate clothing and protection from cold and rain
1) Wearing appropriate PPE (Gloves, Glasses)
2) Direct touch with concrete without PPE is forbidden
1) One supervisor as rigger must manage rigging operations
2) Slings must be tied and inspected by riggers and site supervisors
3) Passing under the lifted load is prohibited, rigger shall organize
1) Only authorized operators shall perform welding
2) Proper PPE like gloves resistant to heat, full body cover shall be warn
3) Welding mask shall always be used to protect eyes
5
6
Factors of Harm (after PCM)
7
8
Control Measures
Implemented by
Likelihood
Severity
Risk Rating
x<4
1
2
2
Engineers,Foreman &
Workers
1
2
2
Engineers, Foreman &
Workers
1
2
2
Engineers,Foreman &
Chargehand
1
1
1
Engineers,Foreman &
Workers
1
1
1
Workers
1
2
2
Engineers,Foreman &
Riggers
1
2
2
Foreman & Workers
Classification
Likelihood of harm : Likely = 3, Possible = 2, Unlikely = 1
Severity of harm : Major Injury/death = 3, Notifiable = 2, Minor = 1
Risk Rating = Likelihood x Severity
14/14
Download