Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 Issue Date: 06 Nov 2009 Rev No.: 0 METHOD STATEMENT -STATIC LOAD TESTS OF PILES- Prepared Rev. Date QA/QC Eng. 06-Nov-09 Approved Description No 0 Checked First Issue F. Ulu T.O Mng. HSE Mng. M. Poojari I. Azizov QA/QC S.C. Project Project Mng. Mng. Manager J. Beckett E. Albayrak C. G. Lee 1/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 Issue Date: 06 Nov 2009 Rev No.: 0 TABLE OF CONTENTS 1. PURPOSE 4 2. SCOPE 4 3. APPLICATION AREAS 4 4. REFERENCES 4 5. RESPONSIBILITIES 4 5.1 Responsibility for implementation of this procedure 4 5.2 Quality Assurance & Quality Control Manager 4 5.3 Laboratory Manager 4 6. EQUÄ°PMENT 5 7. DEFINITIONS and ABBREVIATIONS 5 8. PERMANENT MATERIALS 5 9. WORK METHODOLOGY 5 9.1 General 5 9.2 Test Pile 6 9.3 Reaction Piles 6 9.4 Execution of Compressive Tests 6 9.4.1 Compression Test Load System 6 9.4.2 Test Pile Head Preparation 7 9.4.3 Test Location 7 9.4.4 Test Pile and Instrumentation 8 9.4.5 Reaction System 8 9.4.6 Loading System 9 9.4.7 Settlement Readings 9 9.5 Loading Procedure 10 10. INSPECTION and TESTING 10 10.1 Parties Involved 10 10.2 Tests and Results 10 10.3 Related Documents 10 11. ENVIRONMENT and SAFETY 10 11.1 Protective & Safety Equipment 11 11.2 Risk Assessment 11 11.3 Emergency 11 2/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 Issue Date: 06 Nov 2009 Rev No.: 0 12. RECORDS 11 13. APPENDICES 12 13.1 Conformation of Instructions to Operatives 13 13.2 Risk Assessment 14 3/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 Issue Date: 06 Nov 2009 Rev No.: 0 1. PURPOSE The purpose of this document is to define the methods and controls employed to ensure that all static load testing of piles undertaken by the Contractor and the Sub-Contractors engaged by the Contractor which is designated to be AGT-ZETAS for the project are carried out in a controlled and systematic manner that in all respects conform to the specified requirements. 2. SCOPE The method statement refers to the static load testing of cast-in-place bored piles. 3. APPLICATION AREAS All related departments of the project 4. REFERENCES References for this document are: • • • • • Construction Specification Construction Specification Appendix Designer’s Drawings Quality Control Manuel ASTM D 1143-81 5. RESPONSIBILITIES 5.1 Responsibility for implementation of this procedure QA/QC Manager or his Designee and person in charge for will be responsible of execution of works. 5.2 Quality Assurance & Quality Control Manager He is responsible for the “Project Quality Assurance Plan” and the quality control during the execution of work in field as well as laboratory. All the tests required the Project by specification are carried out under his supervision. He is assisted by Laboratory Chief. 5.3 Laboratory Manager The Laboratory Chief is responsible for carrying the tests in the field and laboratory as per applicable standards and quality assurance plan. All the tests for the quality control are performed with the help of technicians. 4/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 Issue Date: 06 Nov 2009 Rev No.: 0 6. EQUIPMENT The equipment/machinery involved for execution of this work consists of: Mobile Crane Steel Connection Beam Welding Machine 7. DEFINITIONS and ABBREVIATIONS PM = Project Manager SM = TOM = QM = QT = EPE = Site Manager Technical Office Manager QA/QC Manager QC Technician Earthwork Engineer RFI = Request for Inspection 8. PERMANENT MATERIALS N/A 9. WORK METHODOLOGY 9.1 General No. of static load test on preliminary test pile B20 - 14 Working load (WL) 866 kN Ultimate test load 866 kN Standard followed ASTM D1143-81 Hydraulic jack acting against reaction Loading system piles & reaction frame No. of reference beams No. of dial gauges/precision 2 parallel (test pile) 2/0.01 mm 5/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 9.2 Issue Date: 06 Nov 2009 Rev No.: 0 Test Pile Pile cons. platform level Pile cut-off level +106.983 m (pile above sleeved) Pile toe level Pile length to cut-off 9.3 +96.983 m 10.00 m Reaction Piles Ultimate test load No of reaction piles Individual pile load (tension) 866 kN 2 866/2=433 kN Pile cut-off level +106.983 m Pile toe level +96.983 m Pile length 9.4 10.00 m Execution of Compressive Tests 9.4.1 Compression Test Load System The principle system for axial compression load test is to apply a vertical load to the test pile using hydraulic jack, getting reaction force from other bored piles which are both sides. Bored pile axial loading test system is based on getting reaction force from the beam that will be made installation to the reaction bored piles loading the test pile in the axial direction. From the three bored piles of the same direction, two are called reaction piles in the edge and pile in the middle is called test pile. Test beam must be fixed between two reaction piles and stability of loading system shall be ensured under maximum test load to be applied. Load will be applied by means of hydraulic power pack unit connected to the hydraulic jacks. Pressure values corresponding to the scheduled loads will be adjusted by means of calibrated manometers. 6/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 Issue Date: 06 Nov 2009 Rev No.: 0 Test beam will be prepared with two 800mm pipe which are put under the test beam and inside the reaction piles. These pipes will be fixed inside the reaction pile’s steel gauge overlaps and will be welded. Hydraulic jack will be accomodated between test beam and steel test plate which was fixed on the test pile. 9.4.2 Test Pile Head Preparation Before commencement of the test, this is need for the preperation head of test pile, which shall be broken at project level. In this stage, it is necessary to reach strong concrete. Then, if necessary the required level of test pile can be provided by casting additional concrete. All steel gauge overlaps must be fixed stirrup re bars up to top level, before concreting. According to additional concrete sampling result, test can be erected after 7 days. If test pile defined before construction, steel gauge overlaps shall be fixed all length with stirrups, and concrete casting shall be continue come to fresh concrete. After this process no need to breaking pile head and casting new concrete. 9.4.3 Test Location The test location shall be as illustrated in Figure-1 7/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 9.4.4 Issue Date: 06 Nov 2009 Rev No.: 0 Test Pile and Instrumentation Test pile will be of 1000 mm diameter with toe level at 96.983 m. Its construction will be done from the working level at 106.983 m. The shallowest base will be at the same level of the original cut-off level of 106.983 m, so that the displacement and corresponding friction resistance up to this depth can easily be differentiated for the accurate representation of the performance of the original 10 m long pile from 96.983 to 106.983 m. 9.4.5 Reaction System The following photo and the enclosed drawing illustrate the test set-up planned to be used for the full scale loading tests. 8/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 9.4.6 Issue Date: 06 Nov 2009 Rev No.: 0 Loading System The load shall be applied by means of hydraulic jack having a capacity of 500 kN. The jack is connected to control unit where the hydraulic power is generated by electricity and also where the pressure in the system (and jack) is monitored by built in manometer(s). The picture of the loading system is presented below. 9.4.7 Settlement Readings The settlements shall be read by two (2) micrometers connected to reference beams, independently supported by steel rebar. Every reaction piles displacement shall be read by one micrometer connected to reference beams. The micrometers have a range of 0-50 mm and precision of 0.01 mm. The settlement monitoring setup is illustrated below. 9/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 9.5 Issue Date: 06 Nov 2009 Rev No.: 0 Loading Procedure Standard Loading Procedure with two cycles shall be applied. i. • First Cycle; Load the pile 25%, 50%, 75% of the pile working load (WL) and taking four readings for half an hour. • Maintain 100% of the WL for 6 (six) hour and taking 15 readings. • Remove the applied load in decrements equal to the loading increments, allowing 15 min. between decrements. • ii. Maintain 0% of the WL for 2 (two) hours and taking 7 readings. Second Cycle; • Reapply load to 50% of WL and maintain the load for 30 min. and 4 readings. • Apply additional 50% of WL and maintain the load for 30 min. and 4 readings. • Maintain 100% of WL for 12 hours. • Remove the applied load in decrements equal to the loading increments, allowing 15 min. between decrements. • Maintain 0% of the WL for 2 (two) hours and taking 7 readings. 10. INSPECTION AND TESTING N/A (Already described above) 10.1 Parties Involved Inspection and Testing will be conducted in accordance with the Contract Documents and will include the responsible person mentioned sub-section 5; i.e. internal and external representatives. 10.2. Tests and Results Test results will be prepared by AGT-ZETAS and will be submitted to Engineer for review 10.3 Related Documents • RFI : Request for Inspection • RFT : Request for Testing 11. ENVIRONMENT and SAFETY Project Safety Manuel ref: YKGN-UAJV-HSE-01 and risk assessment will be followed 10/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 11.1 Issue Date: 06 Nov 2009 Rev No.: 0 Protective & Safety Equipment All workers engaged in embankment works shall wear appropriate PPE to minimize the risks. • • • • 11.2 Safety Shoes Reflective Jackets Gloves Eye Protective Glasses Risk Assessment See Appendix 1 11.3 Emergency In case of emergency, contact person and contact number is as listed below: - Ilgar Azizov : 050 255 38 89 Zaur Ganbarov: 055 209 22 47 (Safety Manager) (Structural Engineer) 12. RECORDS Full records of the test will be submitted to the Engineer for review. 11/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 Issue Date: 06 Nov 2009 Rev No.: 0 13. APPENDICES APPENDICES 12/14 Project Title: Yevlakh - Ganja Road Section Widening to 4-Lane Project STATIC LOAD TEST OF PILES Doc. No: YKGN-UAJV-MS-13 13.1 Issue Date: 06 Nov 2009 Rev No.: 0 Conformation of Instruction to Operatives Those names listed below confirm receipt of the method statement and have had the contents explained to them/understand it and are aware of the requirements. Name & Surname Job Title Date Sign 13/14 The Employer The Engineer The Contractor AZERROADSERVICE OJSC Project : Yevlakh-Ganja Road Section Widening to 4-Lane Project RISK ASSESSMENT Method Statement No: MS-13 Rev. 0 Hazard 1 2 Factors of Harm Likelihood Severity Activity: STATIC LOAD TEST OF PILES Assesed By: FATIH ULU 3 4 Risk Rating Enviromental Risks 2 2 4 Traffic Accidents 3 3 9 Hand & Mechanical Tools 2 3 6 Weather Conditions 1 2 2 Chemicals in Concrete 1 2 2 Rigging (Lifting) Operations 2 3 6 Welding Works 2 2 4 Proposed Control Measures (PCM) 1) Good hosuekeeping habit must be maintained at all the time 2) Trenches/ excavation must be properly enclosed with barriers and warning signboard. 3) Spillage of diesel and oil leakage to rivers shall be prevented by taking necessary precautions 5) Provision of proper training for all operatives. 6) Ensure all operatives using PPE propperly 1) Mandatory/ informative / directional signs must be posted on all strategic points. 2) Separate vehicular routes from pedestrian routes on site. 3) High reflective jackets must be worn by operatives all the time while at work 4) Adequte warning lights shall be used during nightshift work 5) Close supervision during work in progress 6) Provision of proper training for all operatives. 7) Proper housekeeping must be carried out to avoid fire hazard. 8) Proper PPE must be used 9) Adhere to the speed limit on site 10) Equipments shall have reverse warning noise indicators 1) Provision of tool bags while working. 2) Inspecting tools for loose and deflecting parts.Reports and replace immediately. 3) Wear appropiate PPE. 1) Drinking cold water when hot. 2) Resting in suitable shaded areas in hot weathers 3) Adequate clothing and protection from cold and rain 1) Wearing appropriate PPE (Gloves, Glasses) 2) Direct touch with concrete without PPE is forbidden 1) One supervisor as rigger must manage rigging operations 2) Slings must be tied and inspected by riggers and site supervisors 3) Passing under the lifted load is prohibited, rigger shall organize 1) Only authorized operators shall perform welding 2) Proper PPE like gloves resistant to heat, full body cover shall be warn 3) Welding mask shall always be used to protect eyes 5 6 Factors of Harm (after PCM) 7 8 Control Measures Implemented by Likelihood Severity Risk Rating x<4 1 2 2 Engineers,Foreman & Workers 1 2 2 Engineers, Foreman & Workers 1 2 2 Engineers,Foreman & Chargehand 1 1 1 Engineers,Foreman & Workers 1 1 1 Workers 1 2 2 Engineers,Foreman & Riggers 1 2 2 Foreman & Workers Classification Likelihood of harm : Likely = 3, Possible = 2, Unlikely = 1 Severity of harm : Major Injury/death = 3, Notifiable = 2, Minor = 1 Risk Rating = Likelihood x Severity 14/14