General Technical Specifications for CS & SS Pipes and Pipe Fittings 1. Quotation should clearly indicate that supply of items are confirming to specifications and typical QA plans given in this specification. 2. Supply of pipe shall be only from reputed Indian manufacturers. Original Manufacturer’s test certificate and heat treatment details (co-relatable with heat no.) shall be offered to NPCIL-QA for verification of heat no., mechanical & chemical properties and hydro-test details. A copy of same duly signed by NPCIL QA shall accompany the supply. 3. In case of non availability of original manufacturers test certificates of Indian manufactured pipes the whole lot of material shall be subjected to material testing, i.e., mechanical properties & chemical composition checking (minimum of two samples/size/heat/lot and maximum as decided by NPCIL-QA) at NPCIL Approved labs in front of NPCIL representative witnessing. In case of failure of item while Testing, the testing charges will not be given to the supplier. 4. In case Indian manufacturers are not available for that item, foreign manufactured item will be acceptable. In that case, the supplier should mention the make & origin of the material in his offer and the whole lot of material shall be subjected to material testing (one sample per each length or sample size as decided by NPCIL-QA) at NPCIL approved labs in front of NPCIL-QA witnessing. However products, those made in China, are not acceptable. 5. Hence supplier should quote the testing charges per sample basis (inclusive of cost of sample or pipe length used for testing) separately in the quotation. Payment will be made only for the supplied length or supplied quantity only. For mechanical testing; testing charges per sample shall be quoted for both mechanical and chemical testing. 6. If original manufacturer test certificate (co-relatable with heat no) is available and NPCIL-QA insist for additional tests on sample selected by QA engineer, the same shall be tested at NPCIL approved or Govt. approved lab with NPCIL-QA witnessing. The testing charges will be paid as per offer/PO clauses. Positive Material Identification (PMI) test or any spectrography test in place lab testing is not acceptable. 7. Manufacturer’s Mill Test Certificate shall indicate, wherever applicable, results of Heat treatment (solution annealed), 100% Hydrostatic pressure test along with other details. However micro-test for solution annealed and Hydrostatic pressure test are not required. 8. Supplier shall execute 100% testing as indicated in QA Plan and submit internal reports to NPCIL-QA for review and supplier is required to do the same tests for 20% of quantity in presence of NPCIL-QA engineer or witness by NPCIL-QA. In case of failure of material, during NPCIL QA witnessing the whole lot of that size item will be rejected. 9. All materials will be subjected to pre-dispatch inspection and material shall be dispatched only after inspection and issue of shipping release by NPCIL QA. 10. If supplier doesn’t agree to the above conditions, the offer will be summarily rejected without further review. 11. Material identification such as mark/stamp and heat no. /lot no shall be available on each item as per ASME standards 12. Wall thickness measurement for pipes and pipe fittings are to be done through ultrasonic thickness gauge as per ASME Boiler & Pressure vessel code Sec-V-1998SE-797. Wall thickness measurement shall be done randomly at any cross section of the fitting for 100 % of items by the supplier. The report of wall thickness measurement shall be submitted to NPCIL QA for review before 20% witnessing. 13. Procedure for testing of IGC or Ultrasonic examination (applicable only for SS pipes & pipe fittings) shall be prepared by level-II qualified operator and submitted for approval of purchaser, prior to inspection. 14. The NDT testing done only by qualified personnel only will be acceptable. 15. Necessary measuring instruments shall be given along with calibration certificate for carrying out measurements. 16. Pipe surface inside and outside should be clean and free from any dent or corrosion mark. 17. Supplier shall take care that the testing marks/indentations shall be on the least important face/ part of component, to ensure sealing faces. 18. Dimensional checks to be done as per the respective ANSI standards. 19. No rectification of damages by any means is allowed. However prior approval shall be obtained for rectification. 20. Both the ends of pipe shall be protected by PVC caps to avoid transit damage and entry of foreign material. 21. Pipe lengths shall be within 5 to 7mtrs length each. 22. +/-10% quantity tolerance is acceptable. 23. For pipe fittings; samples for testing will be taken from raw material pipe prior to fabrication; hence only offers from manufacturers are preferable. If traders quote, Acceptance certificate for the same shall be submitted. 24. GI pipes and GI pipe fittings are excluded from QA inspection. However inspection of these materials will be done at site on receipt. Hence Mill test certificates shall be furnished along with material. If advance payment involves; PDI will be incorporated. 25. The material shall be packed properly to avoid damages during transit. If items found in damaged condition on receipt at site, the material may get rejected even after QA inspection & clearance by NPCIL QA. 26. No manufacturer’s TC in Xerox will be considered as original under any circumstances 27. No manufacturer’s TC issued in the name, other than the vendor, on who order going to be placed, will be considered original. 28. In case of original correlated manufacturer’s TC, number of test samples will be as per relevant material Specification, Or else number of test samples shall be drawn by NPCIL Engineer, that will depend upon the quantity, size etc. and be sufficient to have an confidence about the property of the material ,their repeatability and consistency. 29. Performance bank guarantee is not applicable as these items are raw material in nature. 30. Mechanical testing other than hardness test is not applicable for fittings less than 2”NB. TECHNICAL SPECIFICATIONS FOR STAINLESS STEEL SEAMLESS PIPE AND PIPE FITTINGS: 1. All SS pipes shall conform to ASME SA 312 TP 304L and dimensions to ANSI B 36.19M. 2. All SS pipe fittings material shall be conform to ASME SA 182 F304L or ASME SA 403 WP 304L and dimensions to ANSI B 16.9 & 16.11. 3. All SS flanges shall confirm to ANSI B 16.5 and 16.25. 4. IGC test as per SE-262 Pr-A shall be carried out, if gets failed in practice-‘A’; Practice-‘E” shall be carried out for all pipe, pipe fittings and flanges. 5. Thickness measurement for pipe and pipe fittings shall be carried out as per SE-797 (100% by supplier and 20% witnessing by NPCIL-QA). 6. All pipes shall be tested for uniformity & flaw detection by ultrasonic examination as per SE-213. Preparation of specimen/blocks, notch cutting, verification of machined specimen/blocks, and calibration of equipment as per approved procedure are in scope of supplier. The Calibration block preparation for UT flaw measurement is under scope of supplier. Supplier shall carry out test for 100% quantity with approved qualified personnel and submit the report to NPCIL-QA. Witness by NPCIL-QA on 20% random selected samples will be done after review of report. The supplier should ensure the thorough cleaning of ID & OD of pipes after UT testing. 7. In case of ultrasonic examination is not feasible for small size pipes, Eddy current test shall be carried out as per Section- XI, Appendix - IV and Section - V Article 8 of the ASME Code - 2001. 8. The supplier shall submit all internal reports, original MTC, dimensional reports to NPCIL –QA for review. Based on review, witness inspection by NPCIL-QA will be made. 9. QAP shall be submitted for approval, however draft QAP has been attached. Separate QAP for SS pipes and SS pipe fittings shall be prepared. Quality Assurance plan for Stainless steel pipes S. Operation No. Inspection by Supplier Inspection by NPCIL- Remarks QA 1. Chemical Analysis Verification of co-relating MTC 2. Mechanical Verification of 1. Review of co-relatable MTC. 2. Sample collection and test witness, if required. 1. Review of co-relatable To be verified for each Heat .no. Analysis shall be done from NPCIL approved lab only. To be verified for each Heat .no. Analysis co-relating MTC Verification of relating MTC 4. Hydrostatic test (Verification of Material Test Certificates – Original / endorsed) Visual inspection 5. Dimensional check 6. 8. IGC Test as per ASTM-E_262 Practice –‘A’/‘E’ Ultrasonic Examination Marking 9. Packing 10. Issue of inspection Certificate & shipping Release Checking for Certificates & enclosed for shipment 3. 7. 11. MTC. 2. Sample collection and test witness, if required. Verification of co-relatable MTC Analysis shall be done from NPCIL approved lab only. 100% Visual inspection 100% Visual inspection Rust preventive oil/coating should be removed before visual inspection. No Dents/ corrosion marks are permitted. 100% Dimensional check. (OD, Wall thickness, length etc.) One sample from each heat no. 20% Dimensional check. (OD, Wall thickness, length etc.) Ultrasonic Thickness Gauge to be used for wall thickness measurement. One sample from per each heat no. As per Standard A-262; 100% as per ASTM-SE-213 100% for checking the Markings. Checking for proper packing NA 20% as per ASTM-SE213 100% for checking the Markings NA Calibration block preparation is under scope of supplier. Each pipe shall be marked as given in ASTM A106 & A530. Provision of PVC Caps at free ends of the pipes to be ensured. ------ Check for all the enclosed documents N.A co- Issue of inspection report & Shipping Release. To be verified for each Heat .no. ------- Typical QA plan for Stainless steel pipe fittings Butt weld end. S. No. Operation Inspection Supplier by 1. Chemical Analysis Verification MTC of 2. Mechanical Analysis Verification MTC of 3. Visual inspection 100% inspection 4. Dimensional check 100% Dimensional check Visual Inspection by NPCIL- Remarks QA 1. Review of co-relatable MTC. 2. sample collection and test witness, if required. 1. Review of co-relatable MTC. 2. sample collection and test witness, if required. 100% Visual inspection RANDOM Dimensional check: 20% of the offered quantity in each type of fittings. Wall thickness will be measured at any cross section of the fitting(especially at extradoss area of the Analysis shall be done from NPCIL approved lab only. To be verified for each Heat no. MTC shall be of NPCIL approved lab. To be verified for each Heat no. Rust preventive oil/coating should be removed before visual inspection. No Dents/ corrosion marks are permitted. Wall thickness measurement to be done by ultrasonic thickness gauge. In case of any deviation is found in the random inspection, entire quantity of the particular item 5. IGC Test as per ASTM-E_262 Practice –‘E’ 6. Material identification mark/ stamp One sample from each heat no/lot no. 100% for checking the Markings. 7. Packing Checking for proper packing NA 8. Issue of inspection Certificate & shipping Release 9. Checking for Certificates enclosed for shipment elbows) 100% witness will be rejected. Test witness by NPCIL-QA. 100% for checking the Markings Each fitting shall be marked as given in ASTM A 234 standard. Check for all the enclosed documents NA Issue of inspection report & Shipping Release. ------ N.A ------- TECHNICAL SPECIFICATIONS FOR CARBON STEEL SEAMLESS PIPE AND PIPE FITTINGS: 1. All CS pipes shall conform to ASME SA 106 Gr-B and dimensions to ANSI B 36.10M. 2. All CS pipe fittings material shall be conform to ASME SA 105N or ASME SA 234 Gr WPB (for BW fittings) and dimensions to ANSI B 16.9 & 16.11. 3. All CS flanges shall confirm to ANSI B 16.5 and 16.25. 4. Thickness measurement for pipe and pipe fittings shall be carried out as per SE-797. 100% by supplier and 20% witness by NPCIL-QA. 5. The supplier shall submit all internal reports, original MTC, dimensional reports to NPCIL –QA for review. Based on review, witness inspection by NPCIL-QA will be made. 6. QAP shall be submitted for approval however draft QAP has been attached. Separate QAP for SS pipes and SS pipe fittings shall be prepared. Typical Quality Assurance plan for Carbon steel pipes S. No. Operation Inspection by Supplier 1. Chemical Analysis Verification of relating MTC co- 2. Mechanical Analysis Verification of relating MTC co- 3. Hydrostatic test Verification of (Verification of relating MTC Material Test Certificates –Original /endorsed) co- Inspection by NPCIL- QA Remarks 1. Review of co-relating MTC. 2. Sample collection and test witness, if required. 1. Review of co-relating MTC. 2. Sample collection and test witness, if required. Verification of corelating MTC Analysis shall be done from NPCIL approved lab only. To be verified for each Heat no. MTC shall be of NPCIL approved lab. To be verified for each Heat no. To be verified for each Heat .no. 4. Visual inspection 100% Visual inspection 100% Visual inspection 5. Dimensional check 100% Dimensional check. (OD, Wall thickness, length etc.) 100% Dimensional check. (OD, Wall thickness, length etc.) 6. Marking 100% for checking the Markings. 100% for checking the Markings 7. Packing Checking packing NA 8. Issue of inspection Certificate & shipping Release Checking for Certificates enclosed for shipment NA Issue of inspection report & Shipping Release. Check for all the enclosed documents N.A 9. for proper Rust preventive oil/ coating should be removed before visual inspection. No Dents/ corrosion marks are permitted. Ultrasonic Thickness Gauge to be used for wall thickness measurement. (Randomly at any location of the each pipe) Each pipe shall be marked as given in ASTM A106 & A530. Provision of PVC Caps at free ends of the pipes to be ensured. ------ ------- Typical QA plan for Carbon steel pipe fittings Butt weld end. S. No. Operation Inspection by Supplier Inspection by NPCILQA Remarks 1. Review of co-relating MTC. 2. Sample collection and test witness if required. 1. Review of co-relating MTC. 2. Sample collection and test witness if required. 100% Visual inspection Analysis shall be done from NPCIL approved lab only. To be verified for each Heat no. 1. Chemical Analysis Verification of MTC 2. Mechanical Analysis Verification of MTC 3. Visual inspection 100% Visual inspection 4. Dimensional check 100% Dimensional check for the RANDOM Dimensional check: 20% of the offered quantity in each type of fittings. Wall thickness will be measured at any cross section of the fitting(especially at extradoss area of the elbows) 100% for checking the Markings 5. Material identification mark/ stamp 100% checking Markings. 6. Packing Checking for proper packing NA 7. Issue of inspection Certificate & shipping Release NA Issue of inspection report & Shipping Release. MTC shall be of NPCIL approved lab. To be verified for each Heat no. Rust preventive oil/coating should be removed before visual inspection. No Dents/ corrosion marks are permitted. Wall thickness measurement to be done by ultrasonic thickness gauge. In case of any deviation is found in the random inspection, entire quantity of the particular item will be rejected. Each fitting shall be marked as given in ASTM A 234 standard. Shall provide adequate packing to avoid transit damages to fittings. ------ 8. Checking for Certificates enclosed for shipment Check for all the enclosed documents N.A ------- Note: 1. Tenderers, who supplied similar materials with inspection to NPCIL, shall sent the POs and inspection reports along with offer. 2. The tendered shall be aware of all testing procedures, NPCIL-QA inspection processes and requirements before submitting their offer. 3. Supplier shall have original manufacturer test certificates with heat treatment details and hydro static test details. 4. The offer with ready stock or within 7 days delivery period (excluding inspection process) will be considered. 5. The below attached form for details of testing done shall be filled and sent along with material dispatch for every shipping release and DC. ********** *********** ************ (To be filled by supplier) PO No.: CMM/MAPS/ Supplier Name and address: dtd. Material Testing: PO Sl. No. Heat no. / Lot no. No. of samples tested for physical and Chemical Shipping Release No.: QA witness stamp made on lab report Y/N Y/N Y/N Y/N IGC testing (for SS pipe and pipe fittings) PO Sl. No. Heat no. / Lot No. of samples no. tested for IGC testing Whether QA witness with stamp made on lab report Y/N Y/N Y/N Ultrasonic Examination SE-213 (for SS pipes) PO Sl. No. Qty in meters No. of lengths (one length is 6 mtrs) Testing details Material testing (Chemical & Physical) IGC testing No. of samples N NPCIL-QA stamp punched on each component Y/N Y/N Y/N Y/N Remarks Whether Test report duly signed by NPCIL-QA attached Y/N Y/N Y/N Y/N Testing charges per sample/length T Amount A=N X T or lumpsum Ultrasonic Examination Total amount claimed ∑A: (Rupees………………………………………………………………………………………………only) Marking as per standards are made on each component & rounded with paint NPCIL-QA stamp punched on each component and rounded with paint Whether All Lab reports of Mechanical testing, IGC testing, Ultrasonic examination reports, Ultrasonic thickness measurement report, Dimensional report duly signed by NPCIL-QA with stamp are attached Copy of Original manufacturer’s Mill test certificates duly verified and signed by NPCIL-QA with stamp are attached in same order Po sl.no. of each item shall be indicated in its corresponding LAB reports, MTC, other reports etc (either with pencil or pen) In additional to above, whether booklet is made with copies of following documents and sent along with material dispatch. (3sets) a. Shipping release copy b. Quality Surveillance Reports c. Guarantee certificate d. Approved QAP e. DCR copies if any f. All Lab reports, MTC, etc as indicated above g. Approved procedure pertaining to above PO h. Test and calibration certificates of instruments/equipments used (duly verified and signed by NPCIL-QA) i. Ultrasonic examination SE-213 reports j. Ultrasonic thickness measurement reports and Dimensional report. Yes / No Yes / No Yes / No Yes / No Yes / No Yes / No Signature with stamp & date