Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 To: Johnny Bennett From: Kathryn Marley Subject: Brief 6: Flashy Flashers Date: February 14, 2014 Flashy Flashers Flashy Flashers is a medium sized firm ran by President Johnny Bennett. The firm employees a total of 1,025 people and produces a line of automotive electrical components. “Love Thy Customers as Thyself,” is Johnny Bennett’s commitment to his customers is also his company motto. Flashy Flashers has been successful through hard work, consistent product quality, and good customer service. Last year, Kathryn Marley, Vice President of Operations and Supply Chain Management, approved the installation of a new MRP system, which was the first step towards execution of a full-fledged ERP system. Recently, she has reached out to the production and inventory control manager, shop supervisor, and the purchasing manager to get feedback on the current MRP system. After conversations with the select employees, Kathryn became aware of a few issues with the current MRP system, and is working to provide continuous improvement. Kathryn has discovered she needs to find solutions to the issues of incorrect due dates production, incorrect lead times in the purchasing department, unlevel loading in production, and put the confidence back in the inventory levels for planning to accurately release and plan orders according to capacity. Taking the details provided by the managers and supervisor, Kathryn needs to consider how each of these issues will impact the company and how quickly they need to be addressed. The due dates being incorrect in production is a significant problem causing the production scheduled to be chaotic, which also increases labor costs with the amount of overtime employees must work to complete the work in the busy weeks. The purchasing group is struggling with having to expedite items with MRP not taking the vendor lead times into consideration. If this problem remains constant, the vendors will become irritated with constant expedited orders, or they also may not be able to fill the orders in time. If the vendors cannot expedite the orders, then backorders will increase; along with the lead time it takes to get the completed product to the customer. The planning department is unsure of the orders they release due to the incorrect due dates and also the inventory numbers that are in MRP. Orders are released regardless of inventory or capacity with the current MRP system. Although the MRP system does have positive benefits it brings to the company, the issues they are currently experiencing need to be addressed to ensure customer service levels are not interrupted. I recommend that Kathryn Marley presents the idea of moving forward with the fullblown ERP system to President Johnny Bennett. Having a full-blown ERP system will be costly to the company in the short term; however it will be capable of addressing and correcting all of the current issues Flashy Flashers is experiencing if implemented correctly. A new ERP system will allow production to actively update due dates, which in turn will give planning more confidence in releasing orders and inventory levels. The ERP system will also help purchasing with their struggling lead time issues. Ordering off lead times will help build vendor relationships, and also allow materials to arrive on time for production to be level loaded. The updated ERP system will allow Flashy Flashers to improve its overall process while decreasing the amount of lead time it takes to provide product to customers, and also decrease labor hours once production is level loaded. Overall, the current planning process can be improved with the full-fledged ERP system. Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 References Krajewski. Ritzman. Malhotra, (2013). Operations Management Process and Supply Chains. 2nd ed. United States of America: Pearson. Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 Appendix A Item: C206P Description: SCREWS Date Gross Requirements Scheduled Receipts Projected On Hand: 270 Planned Receipts 1 2 3 200 4 720 5 700 6 670 270 270 70 1850 2500 1150 480 Planned Order Release 2,500 Item: C310P Description: BACK RUBBER GASKET Date 1 2 3 4 Gross Requirements 100 120 Scheduled Receipts 180 Projected On Hand: 40 220 220 120 0 Planned Receipts Planned Order Release 180 Item: HL211A Description: Head Frame Subassembly Date 1 2 3 4 Gross Requirements 120 Scheduled Receipts Projected On Hand 0 0 0 0 0 Planned Receipts 120 Planned Order Release 120 90 75 Item: HL212P Description: HEAD LENS Date Gross Requirements Scheduled Receipts Projected On Hand: 15 Planned Receipts Planned Order Release 5 170 6 185 10 180 180 5 180 DO NOTHING Lot Size: FOQ 180 units Lead Time: 1 1 Weeks 1 7 8 9 0 1 12 DELAY 5 90 6 75 0 90 0 75 Lot Size: L4L units Lead Time: 1 3 Weeks 1 7 8 9 0 1 12 RELEASE 1 2 3 4 120 5 90 6 75 15 15 15 245 350 155 80 350 Lot Size: FOQ 2,500 units Lead Time: 1 1Weeks 1 1 7 8 9 0 1 2 Lot Size: FOQ 350 units Lead Time: 1 2 Weeks 1 7 8 9 0 1 12 DO NOTHING Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 Item: HL222P Description: HEADLAMP MODULE Date 1 2 Gross Requirements Scheduled Receipts 285 Projected On Hand: 10 295 295 Planned Receipts Planned Order Release Item: HL223F Description: HEAD FRAME Date 1 2 Gross Requirements Scheduled Receipts 120 Projected On Hand: 0 120 120 Planned Receipts Planned Order Release 90 75 Item: SL111P Description: Side Lens Date 1 2 Gross Requirements Scheduled Receipts Projected On Hand: 0 15 15 Planned Receipts Planned Order Release 350 Item: SL112A Description: SIDE FRAME ASSEMBLY Date 1 2 Gross Requirements Scheduled Receipts 80 Projected On Hand: 20 20 100 Planned Receipts Planned Order Release 80 3 4 120 5 90 6 75 295 175 85 10 Lot Size: POQ P=4 Lead Time: 1 3 7 8 9 0 WEEKS Weeks 1 1 12 3 4 120 5 90 DELAY Lot Size: POQ P=4 WEEKS Lead Time: 1 1 Weeks 1 6 7 8 9 0 1 12 75 120 0 0 90 0 75 RELEASE 3 140 4 5 80 6 145 225 350 225 145 0 Lot Size: 350 units Lead Time: 1 2 Weeks 1 7 8 9 0 1 12 RELEASE 3 100 4 5 80 6 110 0 0 0 80 0 110 110 Lot Size: L4L units Lead Time: 1 3 Weeks 1 7 8 9 0 1 12 DELAY Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 Item: SL113P Description: SIDE LENS RUBBER GASKET Date 1 2 3 Gross Requirements 100 Scheduled Receipts Projected On Hand: 20 20 20 20 Planned Receipts 100 Planned Order Release 100 4 5 80 6 110 20 20 100 10 100 100 100 Item: SL121F Description: SIDE FRAME Date 1 2 3 4 Gross Requirements 100 Scheduled Receipts 80 Projected On Hand: 0 0 80 0 0 Planned Receipts 20 Planned Order Release 20 80 110 Item: SL122A Description: SIDE BULB SUBASSEMBLY Date 1 2 3 4 Gross Requirements 100 Scheduled Receipts 80 Projected On Hand: 0 0 80 0 0 Planned Receipts 20 Planned Order Release 20 80 110 Item: SL123A Description: FLASHER BULB SUBASSEMBLY Date 1 2 3 4 Gross Requirements 100 Scheduled Receipts Projected On Hand: 0 0 0 100 100 Planned Receipts 200 Planned Order Release 200 200 Lot Size: FOQ 100 units Lead Time: 1 1 Weeks 1 7 8 9 0 1 12 DO NOTHING 5 80 6 110 0 80 0 110 Lot Size: L4L units Lead Time: 1 2 Weeks 1 7 8 9 0 1 12 RELEASE Lot Size: L4L units Lead Time: 1 2 Weeks 1 7 8 9 0 1 12 5 80 6 110 0 80 0 110 5 80 RELEASE Lot Size: FOQ=200 units Lead Time: 1 2 Weeks 1 6 7 8 9 0 1 12 110 20 110 200 RELEASE Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 Item: SL131F Description: SIDE CABLE GROMMET & RECEPTABLE Date 1 2 3 4 Gross Requirements 100 Scheduled Receipts 110 Projected On Hand: 0 110 110 10 10 Planned Receipts 5 80 6 110 0 70 0 110 Planned Order Release 70 110 Item: SL132P Description: SIDE BULB Date 1 2 3 4 5 Gross Requirements 100 80 Scheduled Receipts 100 Projected On Hand: 35 135 135 35 35 55 Planned Receipts 100 Planned Order Release 100 100 Item: SL133F Description: FLASHER CABLE GROMMET & RECEPTABLE Date 1 2 3 4 5 Gross Requirements 100 80 Scheduled Receipts Projected On Hand: 0 0 0 150 150 70 Planned Receipts 250 Planned Order Release 250 250 6 110 Lot Size: POQ=2 Lead Time: 1 2 7 8 9 0 WEEKS Weeks 1 1 12 DO NOTHI NG Lot Size: FOQ=100 units Lead Time: 1 1 Weeks 1 7 8 9 0 1 12 45 100 DELAY Lot Size: FOQ=250 units Lead Time: 1 2 Weeks 1 6 7 8 9 0 1 12 110 210 250 RELEASE Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 Item: SL134P Description: FLASHER BULB Date 1 Gross Requirements Scheduled Receipts Projected On Hand: 100 100 Planned Receipts 2 3 100 4 5 80 6 110 100 0 0 320 400 210 Planned Order Release Lot Size: FOQ=400 units Lead Time: 1 1 Weeks 1 7 8 9 0 1 12 DO NOTHING 400 WEEK ITEM DESCRIPTION AND PART NUMBER SCREWS (C206P) BACK RUBBER GASKET (C310P) HEAD FRAME ASSEMBLY (HL211A) HEAD LENS (HL212P HEADLAMP MODULE (HL222P) HEAD FRAME (HL223F) SIDE LENS (SL111P) SIDE FRAME ASSEMBLY (SL112A) SIDE LENS GASKET (SL113P) SIDE FRAME (SL121F) SIDE BULB SUBASSEMBLY (SL122A) FLASHER BULB SUBASSEMBLY (SL123A) SIDE CABLE GROM & RECEPT (SL131F) SIDE BULB (SL132P) FLASHER CABLE GROM & RECEPT (SL133F) FLASHER BULB (SL134P) 1 2 120 90 350 90 350 75 80 100 20 20 200 3 2,500 5 180 180 100 110 110 200 110 100 100 75 110 80 80 70 250 4 250 400 100 6 Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 Appendix B 5-Step Critical Thinking Decision-Making Process Matrix Step 1: Identify the problem(s) and uncertainties. What exactly is the problem… After Kathryn Marley spoke with the production and inventory control manager, the shop supervisor, and the purchasing manager to discuss how well the MRP system is working, she received feedback on a couple issues. The production and inventory control manager told her the due dates on the orders are wrong and do not get updated. This causes production jobs to be scheduled incorrectly. The current system also does not consider capacity issues when releasing new orders. The shop supervisor would like the job loads to be level and the overrides on the scheduled receipts information difficult to rely on. The purchasing department is too busy fixing errors that they do not have time to improve their department spending. MRP currently does not work properly with lead times and not giving the proper amount of time to order even though the item is set up correctly in the system. The problem is this … Kathryn Marley has discovered that her MRP system has a few glitches that need to be addressed. The due dates are not correct nor updated, causing production jobs to be scheduled incorrectly. Jobs are released regardless of capacity, the load of jobs each week is not level, planning has trouble relying on inventory due to overrides, and purchasing has issues with the lead times the MRP system provides. This is an important problem because… If the MRP issues can not be addressed, then Flashy Flashers may start to decrease its customer service with long lead times and back orders. This may also result in customers going to competitors for faster business and better service. The key question(s) that needs to be answered to solve this problem is… How does Flashy Flashers implement a process of updating due dates, level loading production, eliminating overrides, and ordering items off the correct lead times in MRP. Step 2: Obtain information. The following information is needed to answer this question… In the short term, Flashy Flashers can manually update due dates and stop the overrides that are affecting planning. The purchasing group will have to be aware of the lead time issues when ordering, and planners will have to do their best to level load production. In the long term, Kathryn needs to look into upgrading the MRP system to one that will help correct the issues Flashy Flashers is currently facing. The upgraded MRP system may be costly; however it will improve production efficiency, and decrease backorders and lead times. My biggest question is “do the due dates in production affect the lead times in MRP that purchasing is struggling with?” If the due dates are updated, will purchasing lead times be correct? Some important assumptions I am using in my thinking are… I am assuming that production currently does not change any due dates and they could manually update them if desired. I am also assuming purchasing has double checked the set up of all items Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 correctly in their system and are not able to figure out why the lead times are not showing up correctly when MRP runs. The points of view relevant to this problem belong to… The president of Flashy Flashers, Kathryn Marley, the purchasing team, production team, and planning team; along with all customers and suppliers who are connected to Flashy Flashers. Step 3: Make predictions about the future. If this problem gets solved, some important implications are… Kathryn Marley needs to review her options, along with the issues from the current MRP system to decide which issues need to be fixed and which ones can be managed for the time being. The disadvantage of not finding another MRP system can significantly impact customer satisfaction and also vendor relationships (which purchasing constantly requesting expedited orders). The advantage of moving to a full blown MRP system may have a large cost associated with it, but it will also help solve the current issues that Flashy Flasher’s is facing. If this problem does not get solved, some important implications are… If the problem remains unsolved, the vendors are going to be upset with the purchasing department constantly trying to expedite orders. The labor costs will continue to be high with unlevel work weeks. Customers may be upset with long lead times to get their items due to purchasing and planning issues and eventually look for other places to give their business. Capacity also may be reached once too many orders are released with incorrect due dates. The potential alternative solutions to solve the problem are… There may be multiple conflicting points of view between the production, planning, and purchasing team; however the recommendation will come from Kathryn Marley and will be presented to the president Johnny Bennett. Step 4: Make decisions by choosing among alternatives. What is the best solution and why… I recommend Kathryn Marley presents to Johnny Bennett that an upgraded full blown MRP system is necessary to ensure all items are orders, manufactured, and shipped to the customer within a timely manner. The new MRP system will also improve operations allowing the production team to level load, planning to release orders correctly, and purchasing to order the correct items with corresponding lead times. Step 5: Implement the decision, evaluate performance, and learn. In business, the fifth step in the decision making process is implementation. In the MBA program, most times you will end with Step 4 since you will not have the opportunity to implement. You may be asked to develop an implementation plan and recommend how you will evaluate performance in some assignments. Appendix C Brief 6 Rubric Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 Total 75 points Criteria Develops an opening paragraph that introduces the case. Unacceptable Acceptable Vaguely develops an opening paragraph that introduces the case or does not have an opening paragraph. Develops an opening paragraph that introduces the case and, for the most part, fulfills assignment requirements. Develops an opening paragraph that introduces the case and demonstrates solid ability to accomplish the assignment. (4 points) Analyzes the data derived from Step 2 and, for the most part, fulfills assignment requirements. (5 points) Analyzes the data derived from Step 2 and demonstrates solid ability to accomplish the assignment. (0-3 points) Analyzes the data derived from Step 2. Vaguely analyzes the data derived from Step 2 or completely off the topic. (0-7 points) Discusses the good and bad points of the MRP implementation at the company. Vaguely discusses the good and bad points of the MRP implementation at the company or completely off the topic. (8 points) Discusses the good and bad points of the MRP implementation at the company and, for the most part, fulfills assignment requirements. (0-7 points) Recommends how to improve the resource planning process at the company. Vaguely recommends how to improve the resource planning process at the company (8 points) Recommends how to the resource planning process at the company and, for the most Proficient (9-10 points) Discusses the good and bad points of the MRP implementation at the company and demonstrates solid ability to accomplish the assignment. (9-10 points) Recommends how to improve the resource planning process at the company and Student Score and Comments Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 or completely off the topic. part, fulfills assignment requirements. (0-11 points) demonstrates solid ability to accomplish the assignment. (14-15 points) (12-13 points) Integrates established operation management principles into the discussion. Synthesizes relevant information and materials to provide evidence of critical thought. Develops ideas with clarity and logic. Uses supporting documentation that has been properly Rarely integrates established operation management principles into the discussion. For the most part, does a good job of integrating established operation management principles into the discussion. Consistently does a good job of integrating established operation management principles into the discussion. (0-7 points) Synthesizes information at a minimal level. (8 points) For the most part, effectively synthesizes information, which supports main ideas. (9-10 points) Consistently and effectively synthesizes information, which provides strong support to main ideas. (0-3 points) (4 points) (5 points) Demonstrates little clarity and logic. Readers have difficulty following the line of reasoning. Develops ideas with clarity and logic. Readers can generally follow the line of reasoning. Develops ideas with clarity and logic. Ideas flow smoothly from one to another and are clearly linked to each other. (0-3 points) (4 points) Inadequate or minimal use of supporting documentation or not properly For the most part, uses supporting documentation that is properly (5 points) Consistently uses supporting documentation that is properly referenced and Rachel Byer, Brief 6: Flashy Flashers, MBA 731, Professor Bouchane February 14, 2014 references and cited. referenced or cited. referenced and cited. (0-3 points) Considered holistically, demonstrates the ability to write at the graduate level. Considered holistically, the student demonstrates an inadequate ability to write at the graduate level. cited. (5 points) (4 points) Considered holistically, the student demonstrates an acceptable ability to write at the graduate level. Considered holistically, the student demonstrates a proficient ability to write at the graduate level. (8 points) (9-10 points) (0-7 points) SubTotal Points Turnitin.com Did not turn paper into Turnitin.com ---- ---- ---- ---- --- --- Minus 10 points Revisions based on the originality Report Did not revise paper based on the originality report Minus 10 points Grammarly Did not revise paper based on Grammarly. Minus 10 points Total Points =