Brigada Eskwela Physical Facilities Assessment Form

advertisement
BE FORM 01
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
BRIGADA ESKWELA
PHYSICAL FACILITIES REPAIR AND MAINTENANCE NEEDS ASSESSMENT FORM
(To be accomplished by the School Physical Facilities Coordinator)
 Instruction: Conduct an ocular inspection of the school physical facilities listed below. Then provide the needed information to facilitate the improvement to be done on these identified
facilities.
(If needed, you may use separate forms for each classroom or school facility)
CONDITION
(check one)
FACILITIES
Satisfactory

Roofs/ gutters
Ceilings
Blackboards
Chairs/ desks/ tables
Water facilities/ Drainage system
Signages
School garden
Windows
Doors
Comfort rooms
School grounds
School fence
Others, please specify
Construction of Canopy for School Canteen
Unsatisfactory
REMARKS
If unsatisfactory
describe the problem
Gutter with
holes
Faded roof paint
NATURE OF
IMPROVEMENT NEEDED
( e.g.repair, repainting,
replacement etc.)
MATERIALS OR RESOURCES NEEDED
(indicate kind and quality)
Replacement
repainting
Gutter 8pcs.
4 gal. paint
Carpentry
Painter
Carpentry & Painter


MANPOWER NEEDED
(Indicate quantity and
nature of labor services
needed)

Destroyed & faded
Repair & repainting
.
7 kilos Nails & 7 gal. paint

Many weeds
weeding
.
Weeder


Many weeds
destroyed
weeding
repair
Spade 2pcs.
Weeder
Carpenter

Not available
construction





9mm- 180 pcs
10mm- 120 pcs
CHB- 1,200 pcs
Cement- 800 bags
10 pcs. Gutter
10 bags cement
15 pcs 10MM
Carpenter
10 pcs PVC pipe #1
100 pcs rebits



Prepared by:
Noted:
ANGEALA F. GERMO
School Physical Facilities Coordinator
August 5, 2023
Date of Inspection
MARLYN G. GARDOSE
TIC/ Head Teacher/ Principal
BE FORM 02
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
BRIGADA ESKWELA SCHOOL WORK PLAN
(To be accomplished by the School Head)
Instruction: List down all the specific activities that you will be undertakin in relation to the conduct of Brigada Eskwela in your school and fill in The required information. Add another sheet
if needed. Once completed , submit a copy to Adopt –A-School Program Coordinator or Brigada Eskwela Coordinator of you Division before January 31.
KRA
1.Advocacy and
Marketing
2.Resource
Mobilization
ACTIVITIES
-General PTA Meeting
-Closing program activity
-Selection & Composition of different BRIGADA COMMITTEE
-Orientation of their DUTIES & RESPONSIBILITIES.
-Display of Brigada Streamer
- Conduct an ocular inspection of the school physical facilities.
-Asking DONATIONS/ PLEDGES from parents, Brgy.Officials,
Alumni, etc
-Preparation of Solicitation Letter.
3.Implementation -Preparation/ collection of materials needed
-Checking the BE Form.4
(DAILY ATTENDANCE OF VOLUNTEERS)
-Inspecting their ACCOMPLISHMENTS
5.Reporting
-Filling out of different BE Forms
-Submission of Report
AUGUST 14, 2023
PTA Officers
AUGUST 14-18, 2023
AUGUST 19, 2023
AUGUST 18, 2023
AUGUST 19, 2023
Prepared by:
ANGEALA F. GERMO
Signature over printed Name
AUGUST 14, 2023
PERSONS RESPONSIBLE
School Head
B.E school Coordinator Teachers
PTA
Brgy. Officials
Diff. BRIGADA Committee
AUGUST 14, 2023
-Meeting with different BRIGADA COMMITTEE
-Doing/ Performing different TASKS
-Closing activity
4.Monitoring and
Evaluation
TIMELINE
AUGUST 2, 2023
MATERIALS NEEDED
BUDGET
Printing of Streamers
Printing of
SOLICITATION
LETTERS
P 500
School Head
B.E school Coordinator Teachers
PTA
Brgy. Officials
Diff. BRIGADA Committee
School Head
B.E school Coordinator
Diff. BRIGADA Committee
gutter, latex &
enamel paints,
paint brush, nails
spade , and etc.
P 15,000
Evaluation Sheet
Attendance Sheet
P 300
School Head
B.E school Coordinator
BE Forms, pictures
and etc.
P 300
Noted:
AUGUST 11, 2023
Date
P 300
______________________________
ASP Division Coordinator/ BE Coordinato
BE FORM 03
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
BRIGADA ESKWELA RESOURCE MOBILIZATION FORM
(To be accomplished by the Resource Mobilization Committee)
Instruction: Using the completed BE Form 01: Physical Facilities Needs Assessment Form as basis, summarize the resources (materials and manpower) needed and list down the potential
source or partners to be tapped. Add additional sheet if needed. The Status and Remarks columns should be updated regularly to determine progress in acquiring resources needed.
MATERIALS NEEDED
QUANTITY
KEY PERSONS/ ORGANIZATIONS
TO BE TAPPED
STRATEGIES/
PLAN OF ACTION
gutter
Paint LATEX
Paint ENAMEL
Roof Paint
Nails (assorted)
spade
CHB
cement
10mm
9mm
12 mm
plywood
Square bar
Concrete table & chairs
PVC pipe #1
rebits
lumber
8pcs,
2 pails
7gal.
4 gal
7 kilos
2pcs.
300 pcs.
120 bags
110 pcs.
32 pcs.
30 pcs
15 pcs.
15 pcs.
4 sets
10 pcs.
100 pcs.
865 b.ft.
Barangay Officials
Barangay Captain
Municipal Officials
PTA
Barangay Officials
NGO’s
Internal/External stakeholders
Benefactors and others
Benefactors and others
Benefactors and others
Benefactors and others
Internal/External stakeholders
Internal/External stakeholders
Benefactors and others
Benefactors and others
Benefactors and others
Benefactors and others
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
solicitation
PERSON RESPONSIBLE
LGU, parents, teachers
Barangay Officials
Municipal Officials
Internal stakeholders
External stakeholders
Teachers
Benefactors and others
STATUS
REMARKS
LABOR SKILLS/ VOLUNTEERS NEEDED
QUANTITY
Carpentry
Painter
Ordinary Labor
 cleaning
 gardening
 weeding
KEY PERSONS/ ORGANIZATIONS TO
BE TAPPED
STRATEGIES/
PLAN OF ACTION
PERSON RESPONSIBLE
parents
parents
parents
parents
parents
parents
Seek
for
help
Parents
Barangay Officials
Municipal Officials
Internal stakeholders
External stakeholders
Teachersand others
Prepared by:
STATUS
REMARKS
Noted:
ANGEALA F. GERMO
Signature over printed name
SCHOOL BE COORDINATOR
AUGST 11, 2023
Date Prepared
___________________________________
ASP Division Coordinator/ BE Coordinator
BE FORM 04
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
BRIGADA ESKWELA
DAILY ATTENDANCE OF VOLUNTEERS
Date: ________________________________________
Instructions: Volunteers themselves should personally fill in the details required by this form under the supervision of any of the committee members. For the last column, indicate if masonry,
carpentry, plumbing, painting, electrical, gardening/ landscaping, ordinary labor or others.
NAME
POSITION/
DESIGNATION
ADDRESS/
ORGANIZATION/
AFFILIATION
CONTACT
NUMBER
TIME
IN
SIGNATURE
OUT
TOTAL
NUMBER OF
HOURS
SERVED
Noted:
ANGEALA F. GERMO
School BrigadaEskwela Coordinator
__________________________________
Date Prepared
MARLYN G. GARDOSE
TIC/ Head Teacher/ Principal
NATURE OF
VOLUNTEER SERVICES
RENDERED
BE FORM 5
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
DAY
1
2
3
BRIGADA ESKWELA
DAILY ACCOMPLISHMENT REPORT
(Tobe accomplished by the Program Implementation Committee)
5
6
DATE:
4
Instruction; List down all the activities that needs to be undertaken for each day of the BrigadaEskwela Week. At the end of each day please mark the appropriate column
that corresponds to the status of each activity. Cite reasons for non-completion.
ACTIVITIES
COMPLETED
Replacement of gutters
Repainting of roof
Repainting of walls
Repair of damaged chairs/desks
Repainting of chairs
Weeding of the school garden
Cleaning of the classrooms and structuring
Weeding of pathways/school ground
Enhancement of School Canteen
Noted:
ANGEALA F. GERMO
School BrigadaEskwela Coordinator
STATUS
STARTED BUT NOT YET
COMPLETED
NOT DONE
REMARKS/
RECOMMENDATIONS








__________________________________
Date Prepared
MARLYN G. GARDOSE
TIC/ Head Teacher/ Principal
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
DAY
1
2
3
4
BRIGADA ESKWELA
DAILY ACCOMPLISHMENT REPORT
(Tobe accomplished by the Program Implementation Committee)
5
6
DATE:
Instruction; List down all the activities that needs to be undertaken for each day of the BrigadaEskwela Week. At the end of each day please mark the appropriate
column that corresponds to the status of each activity. Cite reasons for non-completion.
ACTIVITIES
STATUS
COMPLETED
STARTED BUT NOT YET
NOT DONE
COMPLETED
Replacement of gutters

Repainting of roof

Repainting of walls

Repair of damaged chairs/desks

Repainting of chairs

Weeding of the school garden

Replacement of unusable bulbs

Cleaning of the classrooms and structuring

Weeding of pathways/school ground

Construction of Rain Catchment for Grade-1&2


Repair of Concrete Fence
REMARKS/
RECOMMENDATIONS
Noted:
ANGEALA F. GERMO
School BrigadaEskwela Coordinator
__________________________________
Date Prepared
MARLYN G. GARDOSE
TIC/ Head Teacher/ Principal
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
BRIGADA ESKWELA
DAILY ACCOMPLISHMENT REPORT
DAY
1
2
3
4
5
(Tobe accomplished by the Program Implementation Committee)
6
DATE:
Instruction; List down all the activities that needs to be undertaken for each day of the BrigadaEskwela Week. At the end of each day please mark the appropriate
column that corresponds to the status of each activity. Cite reasons for non-completion.
ACTIVITIES
STATUS
COMPLETED
STARTED BUT NOT YET
NOT DONE
COMPLETED
Replacement of gutters

Repainting of roof

Repainting of walls

Repair of damaged chairs/desks

Repainting of chairs

Weeding of the school garden

Replacement of unusable bulbs

Cleaning of the classrooms and structuring

Weeding of pathways/school ground

Construction of Rain Catchment for Grade-1&2


Repair of Concrete Fence
REMARKS/
RECOMMENDATIONS
Noted:
ANGEALA F. GERMO
School BrigadaEskwela Coordinator
FORM 5
__________________________________
Date Prepared
MARLYN G. GARDOSE
TIC/ Head Teacher/ Principal
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
BRIGADA ESKWELA
DAY
1
2
3
4
DAILY ACCOMPLISHMENT REPORT
(Tobe accomplished by the Program Implementation Committee)
5
6
DATE:
Instruction; List down all the activities that needs to be undertaken for each day of the BrigadaEskwela Week. At the end of each day please mark the appropriate
column that corresponds to the status of each activity. Cite reasons for non-completion.
ACTIVITIES
STATUS
COMPLETED
STARTED BUT NOT YET
NOT DONE
COMPLETED
Replacement of gutters

Repainting of roof

Repainting of walls

Repair of damaged chairs/desks

Repainting of chairs

Weeding of the school garden

Replacement of unusable bulbs

Cleaning of the classrooms and structuring

Weeding of pathways/school ground

Construction of Rain Catchment for Grade-1&2


Repair of Concrete Fence
REMARKS/
RECOMMENDATIONS
Noted:
ANGEALA F. GERMO
School BrigadaEskwela Coordinator
__________________________________
Date Prepared
MARLYN G. GARDOSE
TIC/ Head Teacher/ Principal
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
DAY
1
2
3
4
BRIGADA ESKWELA
DAILY ACCOMPLISHMENT REPORT
(Tobe accomplished by the Program Implementation Committee)
5
6
DATE:
Instruction; List down all the activities that needs to be undertaken for each day of the BrigadaEskwela Week. At the end of each day please mark the appropriate
column that corresponds to the status of each activity. Cite reasons for non-completion.
ACTIVITIES
STATUS
COMPLETED
STARTED BUT NOT YET
NOT DONE
COMPLETED
Replacement of gutters

Repainting of roof

Repainting of walls

Repair of damaged chairs/desks

Repainting of chairs

Weeding of the school garden

Replacement of unusable bulbs

Cleaning of the classrooms and structuring

Weeding of pathways/school ground

Construction of Rain Catchment for Grade-1&2


Repair of Concrete Fence
REMARKS/
RECOMMENDATIONS
Noted:
ANGEALA F. GERMO
School BrigadaEskwela Coordinator
__________________________________
Date Prepared
MARLYN G. GARDOSE
TIC/ Head Teacher/ Principal
BE FORM 05
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
ITEMS OR MATERIALS
QUANTITY
Juice & Bread- 1st day
Juice & Bread- 2nd day
Juice & Bread- 3rd day
Juice & Bread- 4th day
Juice & Bread- 5th day
School Supplies
135 packs
BRIGADA ESKWELA
RECORD OF DONATIONS RECEIVED
(To be accomplished by the Documentation Committee)
DATE RECEIVED
NAME OF DONOR
ASSUMED COST OF ITEMS
PER UNIT
TOTAL
May 20, 2019
Baby Jane T. Fojas
500
May 21, 2019
Jocye Micah S. Germo
500
May 22, 2019
Angela F. Germo
500
May 23, 2019
Selebrio G. Gardose
500
May 24, 2019
Kempee F. Pio
500
May 25, 2019
Agpalali BRGY. Officials
100
13,500
TOTAL
Prepared by:
IRENE G. GALLENERO
Program Implementation Committee Chair/Member
Date Prepared
MARLYN G. GARDOSE
School Head
Enclosure No.2-A to Dep.ED Memo No. 41 s.2017
BE school form 1
BE FORM 05
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
ITEMS OR MATERIALS
QUANTITY
cement
CHB
9mm
10mm
CHB
9mm
10mm
9mm
10mm
80 bags
800 pcs
60 pcs
40 pcs
400 pcs
60 pcs
40pcs
60 pcs
40 pcs
3pcs.
3pcs.
2pcs.
2 pails
7 kilos
6pcs
2pcs
gutter
gutter
gutter
Paint LATEX
Nails (assorted)
bulbs
spade
BRIGADA ESKWELA
RECORD OF DONATIONS RECEIVED
(To be accomplished by the Documentation Committee)
DATE RECEIVED
NAME OF DONOR
ASSUMED COST OF ITEMS
PER UNIT
TOTAL
250
JESELLE gamayao HALL
P 20,000
15
SERGIO GAMAYAO JR.
P 12,000
100
DIOSDADO GAMAYAO
P 6,000
150
RAMEL GAMAYAO
P 6,000
100
BATCH 1994
P 6,000
100
BATCH 1998
P 6,000
150
CONCEPCION LINTUCO
P 6,000
100
LOVELYN TANTOCO
P 6,000
150
MARTIN GAMAYAO SR.
P 6,000
May 1, 2019
Hon. Leo Gamayao
180
540
May 3, 2019
Hon. Angeles Gole
180
540
May 3, 2019
Hon. Demetrio Lopez Jr.
180
360
May 6, 2019
Hon Sonny Gabucayan
1,800
3600
May 10, 2019
Vergie C.Onato
65
195
May 12, 2019
CRISTINA ES Teachers
80
480
May 15, 2019
Cresilda G. Gapasinao
800
1600
TOTAL
Prepared by:
IRENE G. GALLENERO
Program Implementation Committee Chair/Member
JUNE 3, 2019
Date Prepared
MARLYN G. GARDOSE
School Head
Enclosure No.2-A to Dep.ED Memo No. 41 s.2017
BE school form
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
BRIGADA ESKWELA 2019
School
_ID
School
Name
NUMBER OF VOLUNTEERS
Government Agencies/ National & Local
Community
NGO PTA
SGC
Gawad
Kalinga
etc.
Corpo
ration
Parents
Alumni
Private
Individual/
Community
Member
Religious
Organizations
(Youth &
Adult)
Congressional
Officials and
Staff
Provincial
Officials
City/
Municipal
Officials
Barangay
Officials
SK
Officials
Provincial/
City/Municipal
Employees
E.S
10
0
40
4
0
16
0
0
0
16
12
0
TOTAL
10
0
40
4
0
16
0
0
0
16
12
0
Cristina
ES
115810
Private Sector
Prepared by:
Firem
n PNP
0
AFP
PA,
Marines
Airforce
Etc.
Barangay
Workers
Other
Volunteers
Total
Number of
Volunteers
0
20
36
154
0
20
36
154
Approved by:
____________________________________________________
ASP Division Coordinator
ROEL F. BERMEJO, Ed.D. CESO V
Schools Division Superintendent
BE school form 1.1
Enclosure No.2-B to Dep.ED Memo No. 41 s.2015 Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
BRIGADA ESKWELA 2023
School
_ID
115810
School
Name
RESOURCES GENERATED
Hardware Materials for
Classroom Repair
Cristina
ES
Qty.
Item
Amount
in Peso
8 pcs.
2 pcs
3 kilos
gutter
lawanet
Nails
(assorted)
Infrastructures
Hardware Materials for
Toilet
Newly Construction/
repair
Hardware Materials for
Wash Facilities
Newly Construction/
repair
Qty
Qty.
Item
Amount
in Peso
Item
Amount
in Peso
Other Donations
Qty.
Item
Amount
in Peso
1,440
500
195
6 pcs.
2 pcs.
For 5.days
bulb
spade
Juice & bread
480
1,600
2,500
School supplies
PE Uniform
13,500
40,500
52,000
180 pcs
120 pcs.
1,200 pcs
9mm
10mm
CHB
18,000
18,000
18,000
135 packs
135 sets
8
80 bags
cement
20,000
1
Prepared by:
32 inches TV &
wall mount
43 inches TV
27,000
Approved by:
RUBY C. GERAFUSCO
Coordinator
ROEL F. BERMEJO, Ed.D.CESO V
Schools Division Superintendent
Total
Number of
Volunteers
Total
Number of
Hours
rendered
(Labor)
Volunteer
Man
Hours
(Amount
in Peso)
Total
Amount
(In Peso)
154
462
37.50
17, 325
Republic of the Philippines
Department of Education
Region VI-Western Visayas
Divison of Capiz
Agpalali Elementary School
School Year 2023-2024
BRIGADA ESKWELA SCHOOL WORK PLAN
School Year 2023-2024
Instruction: List down all the specific activities that you will be undertaken in relation to the conduct of BRIGADA ESKWELA in your school and fill in the required information.
Add another sheet if needed. Submit a copy tp Adopt-A- School Program Coordinator or BrigadaEskwela Coordinator.
KRA
1.Advocacy and
Marketing
2.Resource
Mobilization
ACTIVITIES
TIMELINE
1-General PTA Meeting
-Closing program activity
-Selection & Composition of different BRIGADA
COMMITTEE
2-Orientation of their DUTIES &
RESPONSIBILITIES.
-Display of Brigada Streamer
- Conduct an ocular inspection of the school
physical facilities.
-Asking DONATIONS/ PLEDGES from parents,
Brgy.Officials, Alumni, etc
-Preparation of Solicitation Letter.
March 30, 2019
3. Implementation
-Preparation/ collection of materials needed
-Meeting with different BRIGADA COMMITTEE
-Doing/ Performing different TASKS
-Closing activity
4. Monitoring and
Evaluation
-Checking the BE Form.4
(DAILY ATTENDANCE OF VOLUNTEERS)
-Inspecting their ACCOMPLISHMENTS
-Filling out of different BE Forms
-Submission of Report
5.Reporting
Noted:
ANGEALA F. GERMO
School BrigadaEskwela Coordinator
April 8, 2019
April 8–30, 2019
May 1-25, 2019
May 17, 2019
May 20- June 3, 2019
May 20, 2019to
June3,2019
-May 27 , 2019
-June 3, 2019
PERSONS RESPONSIBLE
MATERIALS NEEDED
BUDGET
School Head
B.E school Coordinator Teachers
PTA
Brgy. Officials
Diff. BRIGADA Committee
Printing of Streamers
P 500
Printing of SOLICITATION LETTERS
P 300
gutter, latex & enamel paints,
paint brush, nails . Shovel , spade ,
bulb and etc.
P 15,000
PTA Officers
School Head
B.E school Coordinator Teachers
PTA
Brgy. Officials
Diff. BRIGADA Committee
School Head
B.E school Coordinator
Diff. BRIGADA Committee
School Head
B.E school Coordinator
Evaluation Sheet
Attendance Sheet
P 300
BE Forms, pictures and etc.
P 300
MARLYN G. GARDOSE
TIC/ Head Teacher/ Principal