QA/QC&I FORMAT NO. : IOCL/WORLEY/NRP-QCF-070, REV.-0 PIPING ISOMETRIC / AS-BUILT DRAWING(S) CLEARANCE REPORT (ABOVE GROUND PIPING) Contractor : NRP Projects PROJECT : Composite Works for Acrylic/ Oxo-Alcohol Project at IOCL Dumad Pvt Ltd Complex & Gujarat Refinery, Vadodara, Gujarat Sub-Contractor Owner : Indian Oil Corporation Limited Project Management Consultant : Worley India Pvt Ltd. REPORT NO : IOCL/WORLEY/NRP/IC/ PROJECT NO : 44AC9100 DATE : UNIT / LOCATION / AREA : Test pack no : Sub system no : System no : Ref. Line / Isometric No. & P&ID No. with Revision : Line/ISO no : As per attached list MOC : Line class : CHECK LIST FOR ISO CLEARANCE Sr. no. Check Point 1 Installation checked as per Isometric with respect to a) Configuration# Route, plumb, elevation, clearance for thermal expansion/insulation b) Branch# Location,angle, orientation, type, R.F. pade etc. c) Steam Trap# Direction 2 Installation checked as per GAD with respect to a) Configuration# Route, plumb, elevation, clearance for thermal expansion/ insulation 3 Installation checked as per P&ID 4 Isometrics completed for (enclosed) a) Joint numbering (Shop and Field welds) b) Spool numbering c) As-built routing and dimensions 5 Valves (Check Rating, Gaskets, Flow direction, Sheet No. Tag No., Spindle direction. CSO, LO/LC, Damage etc.) a) Gate valves b) Globe valves c) Check valves d) Control valves Tag Nos. e) Safety Valves Tag Nos. f) Any other valves 6 Strainers Check for clearance, flow direction, elements 7 Flanged joints Total Nos. Check for type of flange Check for Rating Check for Alignment, (Proper gap and parallelity) Check for correct studs and nuts – dia, length, material, uniform protrusion of studs, anti seize compound Check for correct gasket (type, size, spec., thickness, etc.) Torque values used for tightening 8 Seal welding of Screwed connections (If required) 9 Vents/ Drains as per Drawing. And provision of additional high point vents and / or low point drains, if required. 10 Reinforcement pads as per piping class 11 Orifice flanges Check for Tag. No. Tapping orientation, tap valve, jack screw, straight run length of upstream and downstream 12 Local Gauges: Check for accessibility 13 Slope (When applicable) Observation NRP WORLEY/IOCL Page : 01 of 02 QA/QC&I FORMAT NO. : IOCL/WORLEY/NRP-QCF-070, REV.-0 REPORT NO : NBA/IOCL/WORLEY/NRP/IC/ 14 Supports a) Guides, Cross Guides, Trunnion etc. i Check for correct type, material and dimension ii Check welding iii Check for vent hole on pads (if applicable) iv Check offset for thermal expansion b) Spring supports i Verify tag no. and check details as per data sheet/ spring set ii Check for locking arrangement and any damage during transit, etc. iii Check for completeness of installation as per drg. Including welding of mounting cleat/ bracket iv Check for locking during installation and pressure test c) Bracket support and inserts with Anchor fasteners i Check for members dimensions and materials ii Check for welding iii Check for bolting iv Check for appearance damage 15 Vents/ Drains As per Drg Orientation of valve handles Clearance for hose Requirement of additional vents/ drains (highest/ lowest pt.) 16 Earthings a) Check for location b) Check for dimension of lug welding 17 Checked for Removal Binding off of: a) Control, Safety and Check valves b) In-line instruments c) Rupture discs d) Equipment nozzles e) Others 18 Supports and Weld/Flanged/ Screwed connections free from insulation or other coverage 19 Checked installation of (Indicate location in Drawings) a) Temporary Blinds, Spades b) Temporary Strainers c) Temporary Dummy-spools d) Temporary Gaskets e) Others 20 Expansion Bellows a) Checks prior to installations i. Physical damage ii. Transit locks are intact iii. Dimensions as per drawings. b) Checks during installation i. Parallelity of matching flanges ii. Face to face dimensions of mating flanges iii. Concentricity of matching flanges iv. No stress on expansion bellows v. Record c) Isolation during pressure tests i. Bellow manufacturer’s recommendations on isolation of bellow during Pr. Test to be followed ii. If recommended expansion bellow to be dropped during pressure test 21 Cleanliness internally and externally 22 Rotating equipment final alignment checked with piping 23 Removal of unwanted construction supports 24 Instrument tappings provided as per Drawing 25 Physical Walk Through the Line Checked for gross irregularities including physical damages, unwanted tacks, arc strikes, spatters and space for thermal expansion Other 26 Remarks : Signature Name DATE : PROJECT NO : 44AC9100 Date Authority NRP WORLEY Page : 02 of 02