CERTIFICATE OF COMPLETION
12th January, 2022
CLIENT INFORMATION
CONTRACTOR INFORMATIOM
Md. Shahinul Islam
Dibos Kanti Das
Commanding Officer
Managing Director
3 ENGINEER BATTALION
GAURON ENGINEERING & CONSTRUCTION
Jashore Cantonment, Bangladesh
House#05, Road#19, Nikunjo-2, Dhaka,
Bangladesh
PROJECT NAME
PROJECT DESCRIPTION
MULTI PURPOSE SHED
Supply of 20 Ton, 0.8mm Thickness
Jashore Cantonment
GP Steel Sheet for Multipurpose Shed
Project
Work Order Issued Date: 5th November, 2021
Completion Date: 12th January, 2022
CERTIFICATION
I hereby affirm, to the best of my knowledge and belief, based on inspections, observations,
testing of the supplied materials and upon reports submitted by responsible construction
personnel, that this supplied materials for Multipurpose Shed Project by GAURON ENGINEERING
& CONSTRUCTION is substantially complete and operable. The supply of required materials was
completed in accordance with the department’s issued supply work order.