I 750-310 Revision: February 2013 VBM Fault Interrupter Instructions THREE PHASE 15kV/25kV Grounded 400A 15kV/25kV Grounded 600A ONE POLE* 38kV 400A 38kV 600A 48.5kV 200A THREE PHASE 25kV 200A 25kV 300A 25kV 400A THREE PHASE 38kV 300A ONE POLE* 48.5kV 300A 48.5kV 400A (with longer insulators) *Three poles required for a three phase installation. 8155 T&B Boulevard, Memphis, Tennessee 38125 Phone: 800.888.0211 Fax: 800.888.0690 T&B Utility: http://utility.tnb.com JHV: www.joslynhivoltage.com ONE POLE* 72.5kV 300A VBM Instruction Manual I 750-310 TABLE OF CONTENTS: I. Safety ..............................................................................................................................6 A. Hazard Statement Definitions .........................................................................................................................................6 II. General ..........................................................................................................................7 A. Description .....................................................................................................................................................................7 B. Switches Rated 1,000 Amperes and Higher....................................................................................................................8 C. Operating Mechanisms ...................................................................................................................................................8 1. Solenoid Operator .......................................................................................................................................................9 a) Description of Operation..........................................................................................................................................9 b) Manual Operation...................................................................................................................................................10 2. Motor Operator .........................................................................................................................................................10 a) Description of Operation........................................................................................................................................10 b) Manual Operation...................................................................................................................................................12 D. Optional VACSTATTM feature .....................................................................................................................................12 1. Description of Operation...........................................................................................................................................12 III. Installation..................................................................................................................14 A. B. C. D. E. F. G. Inspection and Uncrating ..............................................................................................................................................14 Mounting ......................................................................................................................................................................14 Clearance Requirements ...............................................................................................................................................15 Control Voltage ............................................................................................................................................................17 Control Wiring..............................................................................................................................................................17 High Voltage Connections............................................................................................................................................18 Vacuum Interrupter Integrity Test ................................................................................................................................18 1. High Potential Withstand ..........................................................................................................................................19 2. Vacuum Contact Resistance Test ..............................................................................................................................20 IV. Servicing ....................................................................................................................21 A. Tools Required .............................................................................................................................................................21 B. Replacement Parts ........................................................................................................................................................22 C. Servicing Housing Cover and Breather Bag .................................................................................................................23 1. Removal ....................................................................................................................................................................23 2. Installation.................................................................................................................................................................25 D. Servicing Vacuum Module Assembly...........................................................................................................................26 1. Removal.....................................................................................................................................................................27 2. Preparation.................................................................................................................................................................28 3. Mounting....................................................................................................................................................................29 E. Servicing Solenoid Switch Operator.............................................................................................................................31 1. Solenoid Assembly Replacement...............................................................................................................................31 a) Pin Gap Setting Procedure .....................................................................................................................................32 F. Servicing Motor Switch Operator .................................................................................................................................34 1. Servicing Motor Assembly - Mechanical...................................................................................................................34 a) Installation..............................................................................................................................................................34 b) Charging Springs Installation and Adjustment .......................................................................................................36 c) Tripping Setup........................................................................................................................................................38 2. Replacing Motor ........................................................................................................................................................41 3. Servicing Motor Assembly - Electrical ......................................................................................................................42 a) Removal and Installation of Relay Panel – Overview ............................................................................................42 b) Installation of Relay Panel – Detailed ....................................................................................................................43 2 VBM Instruction Manual I 750-310 G. Synchronization of Replacement Module Assembly ....................................................................................................44 1. Toggle Link Setting Procedure ..................................................................................................................................45 a) Measuring Toggle Link Setting..............................................................................................................................45 b) Setting Toggle Link Requirements.........................................................................................................................45 2. Full Travel Setting Procedure ....................................................................................................................................48 a) Measuring Full Travel Setting................................................................................................................................48 b) Setting Full Travel Requirements...........................................................................................................................50 3. Overtravel Setting Procedure.....................................................................................................................................51 a) Measuring Overtravel Setting.................................................................................................................................51 b) Setting Overtravel Requirements............................................................................................................................52 4. Auxiliary Switch Adjustment.....................................................................................................................................55 a) Auxiliary Switch Adjustment (Switches Made After 1997) ...................................................................................55 b) Auxiliary Switch Adjustment (Switches Made Prior to 1997) ...............................................................................56 H. Wiring Harness and Auxiliary Contact Replacement (Switches Made Prior to 1997)..................................................57 V. Specifications ..............................................................................................................58 Appendix A ......................................................................................................................59 Manual Revision Notes .......................................................................................................................................................59 3 VBM Instruction Manual I 750-310 TABLE OF FIGURES: Figure 1: Diagram VBM Switch............................................................................................................................................... 7 Figure 2: Cutaway of a Single Vacuum Module on 15kV Line-to-Ground Insulator ............................................................... 7 Figure 3: Solenoid Operator ..................................................................................................................................................... 8 Figure 4: Motor Operator ......................................................................................................................................................... 8 Figure 5: Solenoid Operated Mechanism Diagram................................................................................................................... 9 Figure 6: VBM Motor Operated Mechanism ......................................................................................................................... 10 Figure 7: Sequence of Motor Operations................................................................................................................................ 11 Figure 8: VBM Switch with VACSTATTM vacuum monitor.................................................................................................. 12 Figure 9: VACSTATTM Operational Information................................................................................................................... 13 Figure 10: Typical Erecting Sling........................................................................................................................................... 14 Figure 11: 32” Clearance Around Interrupters - Front View (38 kV Single Phase shown) .................................................... 15 Figure 12: 32” Clearance Around Interrupters - Side View ................................................................................................... 15 Figure 13: 15kV/25kV 3 Phase Ungrounded.......................................................................................................................... 16 Figure 14: 25kV 3 Phase ........................................................................................................................................................ 16 Figure 15: 38kV 3 Phase ........................................................................................................................................................ 16 Figure 16: 48.5kV Single Phase ............................................................................................................................................. 16 Figure 17: 69kV Single Phase ................................................................................................................................................ 16 Figure 18: Double-Stack Interrupters ..................................................................................................................................... 16 Figure 19: Terminal Pad Diagram .......................................................................................................................................... 18 Figure 20: VBM Test Equipment ........................................................................................................................................... 18 Figure 21: AC High Potential Test Set Connections .............................................................................................................. 19 Figure 22: Contact Resistance Test Connections.................................................................................................................... 20 Figure 23: 3090X0014G1 VBM Adjustment and Repair Kit................................................................................................. 21 Figure 24: Breather Bag Replacement Parts........................................................................................................................... 23 Figure 25: Breathe Bag Cover and Screws............................................................................................................................. 23 Figure 26: Removing Breather Bag Cover ............................................................................................................................. 24 Figure 27: Removing Breather Bag........................................................................................................................................ 24 Figure 28: Placing Desiccant Bag into Breather Bag ............................................................................................................. 25 Figure 29: Attaching Clamping Plate to Breather Bag ........................................................................................................... 25 Figure 30: Attaching Breather Bag to VBM Cover ................................................................................................................ 26 Figure 31: Mechanism Cover and Screws .............................................................................................................................. 27 Figure 32: Disconnecting Pull Rod......................................................................................................................................... 27 Figure 33: Temporary Bolts and Replacement Module.......................................................................................................... 28 Figure 34: Replacement Module Preparation ......................................................................................................................... 28 Figure 35: Mounting VBM Module ....................................................................................................................................... 30 Figure 36: Fastening Insulators and Modules......................................................................................................................... 30 Figure 37: Attaching Pull Rod to Clevis Link ........................................................................................................................ 31 Figure 38: Solenoid Assembly................................................................................................................................................ 31 Figure 39: Inserting Feeler Gauge .......................................................................................................................................... 32 Figure 40: Flat Brass Washer and Pin Gap Location.............................................................................................................. 33 Figure 41: Attaching Motor Mechanism to Linkage............................................................................................................... 34 Figure 42: Attaching Assembly to Actuating Bars ................................................................................................................. 35 Figure 43: Attaching Roll Pins ............................................................................................................................................... 36 Figure 44: Installing Charging Springs................................................................................................................................... 36 Figure 45: Pre-adjusting Charging Springs............................................................................................................................. 37 Figure 46: Charging Spring and Jam Nut ............................................................................................................................... 37 Figure 47: Adjusting Stop Bolts ............................................................................................................................................. 37 Figure 48: Trip Link and Jam Nut .......................................................................................................................................... 38 Figure 49: Setting Power Springs Lengths ............................................................................................................................. 38 Figure 50: Turning Motor Shaft ............................................................................................................................................. 39 Figure 51: Setting Eccentrics.................................................................................................................................................. 39 Figure 52: Setscrews on Motor Mechanism Assembly........................................................................................................... 40 Figure 53: Spring Plates Assembly......................................................................................................................................... 40 4 VBM Instruction Manual I 750-310 Figure 54: VBM Motor Operator Diagram ............................................................................................................................ 41 Figure 55: Relay Panel Assembly Diagram............................................................................................................................ 42 Figure 56: Motor Wires and Relay Panel ............................................................................................................................... 43 Figure 57: Relay Panel Assembly........................................................................................................................................... 43 Figure 58: Attaching Relay Panel Assembly .......................................................................................................................... 43 Figure 59: Tie Raped Wires and Relay Panel Assembly ........................................................................................................ 44 Figure 60: Toggle Link Adjustment ....................................................................................................................................... 45 Figure 61: Switch Indicator in Close Position ........................................................................................................................ 45 Figure 62: Location of the Close Bumper Stops..................................................................................................................... 46 Figure 63: Degree Guide Position .......................................................................................................................................... 46 Figure 64: Adjusting the Close Stop....................................................................................................................................... 47 Figure 65: Adjusting Screw.................................................................................................................................................... 47 Figure 66: Tightening the Bumper Stop ................................................................................................................................. 47 Figure 67: Position of Dial Indicator Gauge........................................................................................................................... 48 Figure 68: Actuating Rod/Arm and Dial Indicator Gauge...................................................................................................... 49 Figure 69: Switch Indicator in Open Position ........................................................................................................................ 49 Figure 70: Full Travel Value on Dial Indicator Gauge........................................................................................................... 49 Figure 71: Open Bumper Stop Assembly ............................................................................................................................... 50 Figure 72: Solenoid Operated VBM Mechanism ................................................................................................................... 51 Figure 73: VBM Mechanism with Dial Indicator................................................................................................................... 52 Figure 74: Wedge and Dial Indicator ..................................................................................................................................... 53 Figure 75: Pull Rod and Clevis............................................................................................................................................... 53 Figure 76: VBMs First-to-Last Synchronization .................................................................................................................... 54 Figure 77: VBM Module Pair Synchronization...................................................................................................................... 54 Figure 78: Shim Placement..................................................................................................................................................... 55 Figure 79: Auxiliary Switch Adjustment ................................................................................................................................ 55 Figure 80: Auxiliary Switch Adjustment (Prior to 1997) ....................................................................................................... 56 Figure 81: Wiring Harness and Auxiliary Contact Replacement............................................................................................ 57 TABLE OF TABLES: Table 1: VBM Control Voltage Options ................................................................................................................................ 17 Table 2: VBM Adjustment and Repair Kits ........................................................................................................................... 21 Table 3: VBM Tools in a Kit (3090X0014G1) ...................................................................................................................... 22 5 VBM Instruction Manual I 750-310 I. Safety A. Hazard Statement Definitions ! WARNING: Refers to hazards or unsafe practices which could result in death, severe personal injury, or significant equipment damage. ! CAUTION: Refers to hazards or unsafe practices which could result in damage to equipment or in personal injury. ! WARNING: Before installing, operating, maintaining, or testing this equipment, carefully read and understand the contents of this manual. Improper operation, handling, or maintenance can result in death, severe personal injury, or equipment damage. ! WARNING: This equipment is not intended to protect human life. Follow all locally approved procedures and safety practices when installing or operating this equipment. Failure to comply may result in death, severe personal injury and/or equipment damage. ! ! WARNING: Hazardous voltage. Do not rely on the contact position indicator to determine that the line has been de-energized. Always establish a visible disconnect and establish person grounds when performing de-energized line work. Failure to follow proper safety practices can result in contact with high voltage, which can cause death or severe personal injury. WARNING: Hazardous voltage. Contact with high voltage will cause serious personal injury or death. Follow all locally approved safety procedures when working around high voltage lines and equipment. 6 VBM Instruction Manual I 750-310 II. General A. Description The VBM switch is manufactured in voltage ratings from 15kV to 69kV with continuous current capabilities from 200 amperes. The mechanism may be operated manually, or electrically by solenoid or motor operators. BUS BAR LINE-TO-GROUND INSULATOR CONTROL CABLE CONNECTOR VACUUM MODULE PAIR ASSEMBLY SINGLE VACUUM MODULE MECHANISM HOUSING UPPER MODULE LOWER MODULE POSITION INDICATOR OPERATING HANDLE BREATHER BAG COVER MECHANISM COVER Figure 1: Diagram VBM Switch The assembly containing the vacuum interrupter is called a module (Figure 2). Each module has a vacuum interrupter contact sealed in Joslyte, a solidified foam which provides mechanical strength, high dielectric strength and complete moisture sealing. The module housings are cycloalephetic or EPR rubber bonded to a fiberglass tube. One or two modules are mounted on each insulator and connected to the mechanism by a high strength pull rod. Vacuum Contacts High Voltage Terminals Solid Dielectric Joslyte Insulation Dead Soft Copper Shunts Porcelain Insulator Insulated Fiberglass Pull Figure 2: Cutaway of a Single Vacuum Module on 15kV Line-to-Ground Insulator 7 VBM Instruction Manual I 750-310 B. Switches Rated 1,000 Amperes and Higher These switches utilize modules connected in parallel. For some ratings, more than one mechanism per pole is used. They are installed per instructions in Installation Section III and connected per Joslyn Hi-Voltage drawings and control schematic for the particular switch. All servicing and testing is performed on separate mechanisms by removing the connecting bus and referring to the appropriate section of these instructions. C. Operating Mechanisms The VBM is offered with two types of mechanisms: solenoid and motor. A solenoid mechanism has an expected maintenance-free life of 100,000 operations on AC and 15,000 operations on DC. Controls for solenoid operators are mounted in a separate enclosure. A motor operator is only used on single-mechanism three-phase Varmaster VBM switches, such as 15kV, 400 Amp and 600 Amp models and 34.5kV, 300 Amp models. All controls are located inside the VBM mechanism housing. Inspection after 10,000 operations is recommended. Figure 3: Solenoid Operator Figure 4: Motor Operator (For single mechanism switches only) The completely sealed operating mechanism housing supports line-to-ground insulators and the modules. An expansion bag in the housing prevents “breathing-in” contaminants or moisture and contains a desiccant package to maintain dry air. All electrical control connections to the mechanisms are made through a single environmental control cable connector. An “Open-Closed” position indicator is directly coupled to the mechanism. A separate operating crank enables manual operation of the switch. The entire assembly can withstand several G’s without damage. Depending upon rating there may be one or more mechanisms for a three-phase switch. 8 VBM Instruction Manual I 750-310 1. Solenoid Operator In the single solenoid operator, two solenoids, one for opening and one for closing are used to move a toggle linkage over center releasing stored spring energy to open and close the vacuum contacts. This operation is sequentially described in Description of Operation section. Some solenoid operators use a double solenoid assembly which utilizes two solenoids each for close and open operation. The operation and maintenance of the double solenoid operator is similar to that described for the single solenoid operator. VRL IMPROPER CONDITION Toggle link is past vertical away from open position “Toward OPEN” Bumpers C Toggle Link B Control Yoke Close Stop Open Stop E Actuating Bar Spacer Sleeves Actuating Pin Actuating Pin End Play “Pin Gap” A Solenoids TOGGLE LINK – Rotates around A and is fastened to actuating bar at B. CONTROL YOKE – Rotates around C. ACTUATING BAR – Moves in arc around D and E. Figure 5: Solenoid Operated Mechanism Diagram a) Description of Operation 1.) Switch is open. Spring assembly connected between toggle link and control yoke holds open stop against bumper. 2.) Control circuit energizes close solenoid. Actuating pin rotates control yoke clockwise until toggle link is over center. 3.) Spring assembly pulls toggle link and actuating arm in counterclockwise arc until close stop and bumper engage. Vertical movement of actuating bar raises pull rods and closes vacuum contacts. 4.) When open solenoid is energized, the control yoke is rotated counterclockwise until the toggle link is over center and pulled clockwise by the spring assembly. This returns the actuating bar to the original position, opening the vacuum contacts. 9 VBM Instruction Manual I 750-310 b) Manual Operation The switch may be operated manually using a switch hook. An operating crank is located on the switch housing. The crank ends are notched to receive a switch hook. To close the interrupter, place a switch hook in the notch above the words “Push to Close” and push. This moves the toggle linkage over center, releasing spring energy to close the contacts at high speed independent of speed at which the arm is pushed. To trip, or open the interrupter, place the switch hook in the notch above the words “Push to Open” and push. 2. Motor Operator A series motor drives a cam which loads a spring assembly. When the springs are fully loaded, the cam releases a linkage closing the vacuum switch using one-half the energy in the spring assembly. A low energy solenoid releases the remaining energy in the spring assembly through the same linkage to open the interrupter. Operation is sequentially described in Description of Operation section. The design inherently prevents closing the switch, unless sufficient energy to trip is stored in the spring assembly. The motor consists of a mechanical energy storage assembly and a control assembly. The control assembly is located in the base of the VBM switch. Connections to external circuitry are made through a control cable with environmental connectors. The VBM motor operator is designed to operate at 24VDC, 48VDC, 125VDC, or 120VAC depending upon application. Figure 6: VBM Motor Operated Mechanism a) Description of Operation The following Figure 7 illustrates the sequential operation of the assembly. The motor operator lever is connected to the switch actuating bar at point M. The actuating bar linkage is connected to the pull rods (not shown) of each module assembly. 10 VBM Instruction Manual I 750-310 1.) 2.) 3.) 4.) Switch is open. Toggle links P1 and P2 are in relaxed position. Spring assembly S1 is unloaded. Cam is rotated counter-clockwise by motor or manual pumping. 5.) Lever is displaced in direction R1. 6.) Spring assembly S1 is compressed storing energy in springs. 7.) Lever pulls toggle links P1 and P2 over center. 8.) Toggle spring S2 brings toggle linkage in extended position against stop. 9.) The switch is open and the mechanism is ready to close. 10.) As spring assembly S1 is fully loaded the cam releases lever and stops. 11.) Lever pivots around fulcrum T. Pin R moves in arc R2 and comes against motor assembly chassis stop using ½ total energy in spring assembly S1. 12.) M is moved in arc M1. M’s displacement moves the switch actuating bar and closes the interrupter contacts. 13.) Switch is closed. 14.) Solenoid exerts force U on lever V which pivots on fulcrum W exerting force X on toggle linkage P1 and P2. 15.) Toggle link assembly is displaced. The remaining ½ total energy S1 pulls lever which pivots on fulcrum R. 16.) M moves in arc M2 moving switch actuating bar and opening contacts. 17.) The switch is open. Figure 7: Sequence of Motor Operations 11 VBM Instruction Manual I 750-310 b) Manual Operation The switch may be operated manually using a switch hook. An operating crank is located on the switch housing. The crank ends are notched to receive the switch hook. To close the fault interrupter, place a switch hook in the notch above the words “Push to Close” and pump. After approximately 25 strokes, the switch will close. A unique rotary clutch allows strokes of any length to rotate the cam. A single swift push in the notch above the words “Push to Open” will trip the switch. Vacuum contact operating speed is independent of speed of manual activation. NOTE: Slowly pushing the handle will NOT provide enough energy to open the switch. D. Optional VACSTATTM feature The VBM is also available with a new feature, the VACSTATTM vacuum interrupter monitor. This feature will monitor the vacuum inside each interrupter assembly. If loss of vacuum is detected, a flag type indicator will rotate to indicate the loss of vacuum. In addition, a relay will be energized that will block all close and trip operations. A second relay will also be energized and close its normally open contacts. The two wire output of this dry contact status signal is available for remote signaling if a loss of vacuum occurs. The cutaway of a VBM Switch in Figure 8 shows the placement of the vacuum sensor. It is connected via fiber-optic cable to a control board located in the base of the unit. Refer to Figure 9 on the next page for a more detailed description of VACSTATTM operation. Vacuum Interrupter Vacuum Interrupter Monitor Normal Alarmed Figure 8: VBM Switch with VACSTATTM vacuum monitor 1. Description of Operation For VBM’s that have the optional VACSTAT vacuum monitor, the PC board shown in Figure 9 is added inside the VBM. This PC board will send a signal via fiber optic lines to each vacuum interrupter. If the interrupter has vacuum, the signal will be returned. In the event of a loss of vacuum on any interrupter, the signal will not be returned, indicating that a 12 VBM Instruction Manual I 750-310 loss of vacuum has occurred. The 74 Relay (located next to the PC board inside the VBM) will then energize and open the circuits to the Close and Trip solenoids. The Flag Indicator will rotate and the 74-1 Relay will close its contacts for remote indication. Note: The 74-1 Relay is not available for all configurations. There is a Test switch on the PC board that will simulate a vacuum loss to test all indicators and relay operation. The Reset switch will clear the faulted condition. There are 3 red LED’s on the board that will provide the vacuum status of each phase. A fault will cause the LED to turn on. A blinking red LED indicates an intermittent or poor fiber optic connection. On power up, the Flag indicator will rotate to show a “Faulted” condition, and then back to “Normal”. The 74 Relays will NOT change state during the initialization sequence. In the event of a power loss to the board, the Flag Indicator will remain as it was prior to the power loss. That is, if it was showing a Fault, the indication will remain. On power up, it will still go through the initialization sequence but will change back to the “Faulted” state. ! CAUTION: USE CARE WHEN WORKING AROUND THE FIBER OPTIC LINES. DO NOT BEND THEM SHARPLY TO AVOID DAMAGING GLASS FIBER. Green LED Flashing = OK Off or On Steady = Not OK Flag Indicator. Faulted condition shown. Shielded Cable Test Switch Phase A Vacuum Module 74 Relay Reset Switch Close and Trip Blocking Contactor (Located inside VBM) Fiber Optic Receive Phase B Vacuum Module *74-1 Relay Output 74-1 Relay (+) AC/DC Input (-) (Power supplied by Control or VBM) Phase C Vacuum Module PN 3187A0000 3 1 Fiber Optic Transmit Red LED’s On Steady = Loss of vacuum in interrupter. Blinking = Loose connection 3 phase or 1 phase selection jumper. Figure 9: VACSTATTM Operational Information 13 *74-1 Relay Detail N.O. Dry Contacts. Will close on loss of vacuum. Contacts rated 120 VAC, 10 A VBM Instruction Manual I 750-310 III. Installation A. Inspection and Uncrating Carefully inspect the equipment on arrival. Contact carrier and file a claim if damaged during shipment. Remove crating or carton surrounding the VBM switch. Do not unbolt switch from the wooden base to prevent accidental contact from knocking over switch. Consult the factory if VBMs with multiple interrupters (Figures 14 through 18) are being installed in a metal enclosure. An indoor RC network option can be supplied to reduce the 32” requirement to standard clearances. ! CAUTION: PERFORM A VACUUM INTERRUPTER INTEGRITY TEST DESCRIBED IN THIS SECTION, PRIOR TO PUTTING EQUIPMENT INTO SERVICE. B. Mounting Attach an erecting sling to each mechanism as shown in Figure 10. Make certain the lift is stabilized. Remove the three nuts holding VBM to wooden base. Hoist the switch to its mounting location with the manual operating handle facing the desired direction. Fasten the VBM to its mounting with three 5/8” bolts and remove the erecting sling. CAUTION: The two boards shown are for stabilization only. Be careful that the sling exerts no forces on the vacuum contacts or insulators. CAUTION: Do not lift from terminal pads. Figure 10: Typical Erecting Sling ! CAUTION: THE STRUCTURE AND VBM MECHANISM HOUSING MUST BE SOLIDLY GROUNDED. 14 VBM Instruction Manual I 750-310 C. Clearance Requirements NOTE: For switches with multiple vacuum interrupters in series, a 32 inch (81.3 mm) clearance must be maintained from all switch line parts to adjacent equipment (bus, reactors, CT’s, transformers, frames). This also includes the high voltage conductors, which must run horizontally for at least 32 inches before bending upwards. Failure to meet this clearance requirement will adversely affect the electrical voltage distribution and electromagnetic field within the interrupters during opening and closing operations. This insufficient clearance can prevent proper interruption within the vacuum switch interrupters resulting in undesirable restrikes during opening operations for some application parameters. Incorrect! Conductor within 32 inch area. 32” 32” 32” Correct. Conductor outside 32 inch area. 2 Interrupters in series (with bus bar) 32” 32” Figure 11: 32” Clearance Around Interrupters - Front View (38 kV Single Phase shown) 32” 32” 32” Figure 12: 32” Clearance Around Interrupters - Side View 15 VBM Instruction Manual I 750-310 The 32 inch requirement does NOT apply to switches with only 1 interrupter per phase, as shown in Figure 13 below. All other configurations shown must maintain a 32 inch clearance from adjacent objects, as previously stated. NO Clearance Requirement! (Only 1 interrupter per phase) 32” 32” 32” 32” Figure 13: 15kV/25kV 3 Phase Ungrounded 32” Figure 14: 25kV 3 Phase 32” 32” 32” 32” 32” 32” 32” 32” 32” 32” Figure 15: 38kV 3 Phase Figure 16: 48.5kV Single Phase 32” 32” 32” 32” 32” 32” 32” Figure 17: 69kV Single Phase 32” Figure 18: Double-Stack Interrupters 16 VBM Instruction Manual I 750-310 D. Control Voltage A variety of control voltage options are available. Refer to the table below. Control Voltage 48 VDC 125 VDC 120 VAC 250 VDC Operating Mechanism Motor1 Solenoid4 Reclosing Motor1 Solenoid Reclosing Motor1 Solenoid Reclosing Solenoid Control Current Per Switch Mechanism 3 amps 60 amps3,4 7 amps 4 amps 60 amps2 7 amps 5 amps 60 amps3,4 7 amps 60 amps Close Time Trip Time 5 sec 6 cycles 6 cycles 3 sec 6 cycles 6 cycles 3 sec 6 cycles 5 cycles 6 cycles 2 cycles 6 cycles 3 cycles 2 cycles 6 cycles 3 cycles 2 cycles 6 cycles 3 cycles 6 cycles Table 1: VBM Control Voltage Options NOTE 1: NOTE 2: NOTE 3: NOTE 4: Motor operating mechanisms are designed for single mechanism switches. Current is 60 amperes peak for one, two, or three mechanism switch systems. Current is 120 amperes for 34.5kV 300A VBM. Current for three mechanism switch systems is approximately 180 amperes. Control power must meet the requirements of the drawing supplied with the switch. Refer to the appropriate power input tables for proper requirements. Solenoid Operated Switches Direct Energy DC Operated VBM Switch Direct Energy AC Operated VBM Switch 3045A0176 3045A0169 Motor Operated Switches 5A max during operation ! CAUTION: FAILURE TO COMPLY WITH THE CONTROL POWER AND WIRING REQUIREMENTS MAY RESULT IN SWITCH MALFUNCTION OR DAMAGE. E. Control Wiring All control connections to the VBM switch are made through either of the following methods: a. Environmental cable and connector. The cable may be shortened to desired length if supplied with a connector on the switch end only. NOTE: For multiple mechanism switches, all cable lengths should be cut to the same length. Connection to the control enclosure must be in accordance with the specific wiring diagram for the system supplied. 17 VBM Instruction Manual I 750-310 b. A junction box mounted on the housing wired to the mechanism through conduit. F. High Voltage Connections The terminal pads are aluminum alloy with standard NEMA two-hole drilling. The electrical connection at the terminal pad must be treated with Alcoa No. 2 joint compound or equivalent. Remove brown paper from terminal pad before making electrical connections. Wire brushing through the compound will improve the connection. 1 ¾” [44mm] ½” [13mm] Figure 19: Terminal Pad Diagram G. Vacuum Interrupter Integrity Test Two tests, high potential withstand and contact resistance, may be performed to evaluate the vacuum contacts. They should be performed across each module separately. The following test equipment is required: 30kV AC High Potential Test Set 3070A0244P2 Micro Ohm Meter Figure 20: VBM Test Equipment 18 VBM Instruction Manual I 750-310 1. High Potential Withstand Figure 21 indicates connection points for vacuum module assemblies. ! WARNING: DISCONNECT ANY HIGH VOLTAGE CONNECTIONS TO THE SWITCH PRIOR TO HIGH POTENTIAL TESTING. 30kV AC 30kV AC AC HighPotential Test Set Test Performed with switch in OPEN position Figure 21: AC High Potential Test Set Connections NOTE: Test each module separately. Loss of vacuum results in complete breakdown across an open vacuum contact at voltages below 30kV RMS. Only AC high potential testing is meaningful. DC testing cannot be used. Apply 30kV RMS across each individual contact for 15 seconds with the switch open. To avoid possible generation of X-rays, do not apply more than 30kV RMS. During the high potential testing, self-extinguishing, momentary breakdowns lasting only a few microseconds may occur. These “barnacles” are not significant but can result in false indication of vacuum loss, if the test set utilizes a high speed overload relay or breaker. During normal operation with the switch in service, loss of vacuum or a defective switch module may be indicated by excessive radio noise with the switch open or observation of different surface temperatures of modules on the same switch. See Joslyn Engineering Memo TD 750-918. 19 VBM Instruction Manual I 750-310 2. Vacuum Contact Resistance Test MicroOhm Meter MicroOhm Meter Test Performed with switch in Closed position Figure 22: Contact Resistance Test Connections NOTE: Test each module separately. With the switch closed, the resistance across each module should be less than 200 microohms. On switches with modules connected in parallel for higher current operation, remove the connecting bus to perform this test. If higher resistance values are measured, contact Joslyn Hi-Voltage. 20 VBM Instruction Manual I 750-310 IV. Servicing A. Tools Required Servicing of VBM switches is easily accomplished by referring to the appropriate section of these instructions. One of the following VBM Adjustment and Repair Kits is required when performing maintenance/repair on appropriate switch type: KIT NUMBER 3090X0014G1 3090X0014G2 3090X0014G3 3090X0014G4 DESCRIPTRION VBM (Standard) VBM (⅜ Gap - Straight) VBM (⅜ Gap - 20 Degree Angle) VBM (ZVC) Table 2: VBM Adjustment and Repair Kits Figure 23: 3090X0014G1 VBM Adjustment and Repair Kit 21 VBM Instruction Manual I 750-310 The kit above (Figure 23) includes the following items: PART NUMBER 3090X0014P1 3090X0014P3 3090X0014P5 3090X0014P7 3090X0014P8 3090X0014P11 3090X0014P12 3090X0014P13 3090X0014P14 3090X0014P15 3090X0014P16 3090X0014P17 3090X0014P18 3090X0014P19 3090X0014P21 3090X0014P22 3090X0014P23 3090X0014P24 3090X0014P25 3090X0014P26 DESCRIPTION Snap-On Flashlight Mounting Fixture 3090B0005G2 Starrett Indicator Torque Wrench (10-200 in-lbs.) 3/8 drive Torque Wrench Preset – 50 in. lbs. 1/2-3/8” Drive 5/16” Wrench 7/16-3/8” Socket 3/8” Wrench Phillips No. 3 Screwdriver Flat Tip 1/8” Screwdriver 7/16” Wrench 9/16” Wrench 3/4” Wrench Tool Box 3/16” Allen Socket Dow Corning Torque Wrench Preset – 25 in. lbs. Adjustment Gauge 1 degree Go-No-Go Gauge 3090A0012P1 Table 3: VBM Tools in a Kit (3090X0014G1) Tool required not in the kit: Synchronization Lamps (Sync Lamps) – required for continuity test B. Replacement Parts Replacement parts are available from our factory in Hackettstown, New Jersey. Furnish complete nameplate data and the Joslyn Hi-Voltage GO order number applying to the original purchase, along with description of the part and quantity required. 22 VBM Instruction Manual I 750-310 C. Servicing Housing Cover and Breather Bag The parts necessary to replace the breather bag are as follows: Breather Bag Desiccant Bag Clamping Plate Figure 24: Breather Bag Replacement Parts 1. Removal 1.) Place the switch on a table or use a stand to access the bottom of the switch. Remove the ten (10) or twelve (12) screws that hold the mechanism cover to the switch base. 2.) Remove three (3) cover screws from breather bag cover. ¼”-20 x 5/8 plastic screw ¼” self tapping screw Screws Figure 25: Breathe Bag Cover and Screws 23 VBM Instruction Manual I 750-310 3.) Remove breather bag cover. Figure 26: Removing Breather Bag Cover 4.) To remove breather bag, turn base over and remove 7/16” nut leaving the holes exposed. Turn base back over to and remove breather bag. Figure 27: Removing Breather Bag 24 VBM Instruction Manual I 750-310 2. Installation 1.) To install new breather bag, put desiccant bag inside breather bag. Figure 28: Placing Desiccant Bag into Breather Bag 2.) Put clamping plate into breather bag with beveled side facing inside the bag. The flange of the clamping plate and breather bag MUST be aligned properly otherwise it will not seal. Figure 29: Attaching Clamping Plate to Breather Bag 25 VBM Instruction Manual I 750-310 3.) Place bolt back through the center hole and attach breather bag by screwing the 7/16” bolt. Make sure the breather bag is sealed around clamping plate. Figure 30: Attaching Breather Bag to VBM Cover 4.) Replace breather bag cover by tightening the three screws. 5.) Replace mechanism cover to the base of the switch by securing the ten or twelve cover screws. D. Servicing Vacuum Module Assembly One or two modules are mounted on each insulator depending on switch rating. Module pair assemblies should not be separated in the field because special tools are required for assembly and adjustment. Furthermore, if a switch’s breather bag ruptures, all vacuum modules on that switch must be replaced. Prior to the removal of a module assembly, disconnect all power from the VBM and remove the mechanism cover. 26 VBM Instruction Manual I 750-310 1. Removal 1.) Place the switch on a table or use a stand to access the bottom of the switch. Remove the ten (10) or twelve (12) screws that hold the mechanism cover to the switch base and remove the cover. Screws Figure 31: Mechanism Cover and Screws 2.) Disconnect pull rod from the switch mechanism by removing two bolts and washer plates. Figure 32: Disconnecting Pull Rod ! CAUTION: FOR VBM’S WITH VACSTAT, USE CARE WHEN WORKING AROUND THE FIBER OPTIC LINES. DO NOT BEND THEM SHARPLY TO AVOID DAMAGING GLASS FIBER. 27 VBM Instruction Manual I 750-310 3.) Remove four bolts on top of the insulator that connect module to insulator, and lift module assembly complete with lower terminal pad and pull rod from the insulator. Insulators may be removed by taking out four cap screws holding them to switch base. 2. Preparation 1.) Remove the bolts temporarily holding the lower terminal plate to single replacement modules. Temporary Bolts Figure 33: Temporary Bolts and Replacement Module 2.) Apply silicone grease (Dow Corning DC III or equivalent) to gasket channel and reuse rubber gasket if in good condition. Figure 34: Replacement Module Preparation ! CAUTION: WITH THE BOLTS REMOVED, EXTREME CARE MUST BE USED NOT TO PUT ANY FORCE WHATSOEVER ON THE LOOSE TERMINAL PAD SINCE THIS FORCE WOULD BE DIRECTLY TRANSMITTED TO THE DELICATE BELLOWS OF THE VACUUM MODULES. ANY TWISTING COULD RESULT IN IMMEDIATE LOSS OF VACUUM. 28 VBM Instruction Manual I 750-310 3.) Attach pullrod to the vacuum module. The double module assembly consists of two modules in series, an upper terminal plate and a lower terminal. It should not be disassembled. The single module and module pair assemblies are mounted in the same manner. An aluminum clevis link may be bolted in the mechanism end of replacement pull rods. If so, remove the aluminum clevis link and discard it. DO NOT attempt to replace the link already in the mechanism. All single replacement modules are supplied with a separate “screw-on” pull rod. It is installed by slowly screwing onto the bolt in base of the module. Stop as thread bottoms to avoid putting any stress or strain on the vacuum contact. Back the rod off a maximum of one turn as required to mate with the clevis link on mechanism. NOTE: Do not overtighten pull rod to module. Earlier modules utilized either a permanently attached pull rod or a “screw-in” design. To replace a “screw-in” pull rod, slip the 1” nylon bushing supplied over the bolt end of the rod and slowly screw into the threaded module base. Stop as thread bottoms and back rod out approximately three full turns as required for proper orientation with the mechanism. Double module assemblies of the present design utilize a pull rod which is bolted to a draw bar in the lower module. All necessary hardware is supplied with replacement double module assemblies. The former design utilized a “screw-on” pull rod system. All module assemblies are interchangeable and may be used on the same mechanism, regardless of type of pull rod, however using a present and former design double module pair assembly on the same mechanism requires special considerations. If this situation is required, contact Joslyn Hi-Voltage. ! CAUTION: BUMPING OR TWISTING ANY PULL ROD WHEN ATTACHED TO A MODULE CAN DAMAGE THE VACUUM INTERRUPTER AND REDUCE ITS LIFE. 3. Mounting In mounting insulators and vacuum switch modules, particular attention should be paid to torque values. If a bolt head or nut bears on epoxy or porcelain housing should be torqued to 25 inch-pounds, otherwise torque to 50 inch-pounds. (See Figure 36) 29 VBM Instruction Manual I 750-310 1.) Insert pull rod through insulator with module terminals in proper position. Fasten the replacement module to insulator with the ¼-20 x 2 ½” bolts, nuts, and washers from the original module. Figure 35: Mounting VBM Module 2.) Tighten the bolts evenly to the specified torque. Epoxy or Porcelain Housing Torque to 50-in-lb. Torque to 25-in-lb. VBM Base Figure 36: Fastening Insulators and Modules 30 VBM Instruction Manual I 750-310 3.) With switch mechanism closed, attach pull rod to the aluminum clevis link of the mechanism with ¼-20 x 1” stainless steel bolts, nuts, and lockwashers placed outside the pull rod side pieces. Do not tighten the nuts to facilitate adjustment/synchronization. Figure 37: Attaching Pull Rod to Clevis Link 4.) Refer to Synchronization of Replacement Module Assembly section on Page 44 to sync modules. E. Servicing Solenoid Switch Operator 1. Solenoid Assembly Replacement Refer to Servicing Housing Cover and Breather Bag section on Page 23 for instructions regarding removal of housing cover. Once the cover is removed, refer to Figure 38 below and follow the instructions on next page for removal and installation of Solenoid Assembly. Splicing Connectors Nylon Pin Bolts Torque to 70 in-lbs Figure 38: Solenoid Assembly 31 VBM Instruction Manual I 750-310 1.) Open splicing connectors on the yellow solenoid wires. Leave wires as long as possible. 2.) Remove four bolts (two visible in Figure 38) and the solenoid assembly is released. Decco Solenoids The following procedure is for Decco solenoids. Replacement solenoids are sold as an assembly. Solenoid assembly can be replaced by removing the appropriate bolts attaching the assembly to the mechanism. As the assembly is removed, the nylon actuating pins will fall out. Nemco Solenoids In case of Namco solenoids, one or both solenoids can be replaced by removing and replacing the appropriate bolts holding the assembly together, however replacements solenoids are sold as an assembly. The nylon actuating pins will fall out as the assembly is removed. 3.) To remount the solenoid assembly, insert new nylon actuating pins and position the assembly. Do not reuse old nylon pins. NOTE: To insure operating components freedom of movement necessary to achieve proper operation speed, refer to next section on setting pin gap of each actuating pin. 4.) Connect the four yellow solenoid coil leads to corresponding wires using new insulated compression splices. NOTE: Refer to wiring diagram on switch nameplate for wiring details. a) Pin Gap Setting Procedure Solenoid Pin Gap Requirements = 0.070” – 0.090” 1.) Insert the Feeler Gauge (Part # 3090A0011) between the Solenoid actuating plunger and the Nylon pin. The gauge will slide to a preset position on the device which will represent the actual gap setting. The gap must be between 0.070” and 0.090”. Feeler Gauge Feeler Gauge: 0.070” and 0.090” Figure 39: Inserting Feeler Gauge 32 VBM Instruction Manual I 750-310 2.) Manually change switch position to check opposite pins. 3.) Pin gap is adjusted by adding or removing flat washer shims (Part # 9991542) under nylon spacer sleeves. 4.) To add or remove washers the solenoid assemblies’ four (4) mounting bolts must be removed. If the gap is less than 0.070”, add brass flat washer into the assembly as needed. If the gap is greater than 0.090”, take brass flat washers out of the assembly as needed. Location to add or remove washers Nylon Pin Bolts Torque to 70 in-lbs Flat Brass Washer: .620” OD x .255” ID x .010” Figure 40: Flat Brass Washer and Pin Gap Location 5.) Tighten the bolts to 70 in-lbs. 33 VBM Instruction Manual I 750-310 F. Servicing Motor Switch Operator 1. Servicing Motor Assembly - Mechanical a) Installation NOTE: Insure Switch is in Closed position. 1.) Attach the Motor Mechanism to the Linkage. Secure the assembly with two 3/816x3¼” bolts to temporarily hold mechanism in place. 3/8-16x3¼" bolt Motor Mechanism Figure 41: Attaching Motor Mechanism to Linkage 34 VBM Instruction Manual I 750-310 2.) Attach the assembly to the actuating bars with a clevis pin. Secure the clevis pin with three large nylon washers (two nylon washers on one side and one on the other), and a cotter pin. Open the split end of the cotter pin. Pin Assembly Close the cotter pin as shown Figure 42: Attaching Assembly to Actuating Bars 35 VBM Instruction Manual I 750-310 3.) Remove the bolts and replace with Roll pins. Using a hammer, pound the Roll pins, located on Mech. Plate, down until the Roll pins is in the center of the mechanism. Roll Pin Punch Holder Figure 43: Attaching Roll Pins b) Charging Springs Installation and Adjustment 1.) Install two power springs to the motor mechanism assembly. Secure the power springs with ¼-20 jam nuts. Tighten the jam nut down until the end of the jam nut is even with the end of the thread of the power spring. ¼-20 jam nut Figure 44: Installing Charging Springs 36 VBM Instruction Manual I 750-310 2.) Loosen up the ¼-20 nut of the power spring until there are four (4) threads left between the power spring and the nut. Figure 45: Pre-adjusting Charging Springs 3.) Torque the jam nut to 80-in-lb. Torque to 80 in-lb. Figure 46: Charging Spring and Jam Nut 4.) Using a feeler gauge, adjust the gap on both of the stop bolts to 0.020” Stop Bolt Figure 47: Adjusting Stop Bolts 37 VBM Instruction Manual I 750-310 c) Tripping Setup 1.) Loosen Jam nut, located on the Trip Link, all the way. Jam Nut Trip Screw Figure 48: Trip Link and Jam Nut 2.) Turn the Trip Screw clockwise until the switch trips then back it off 2 full turns. 3.) Close the switch. Fine-tune the Trip screw exerting minimum upward pressure on the screw until the switch trips. Turn the Trip Screw 5/8 to ¾ of a turn backward. 4.) Tighten the nut until no movement is allowed. Close the switch. 5.) Using Pin gauge, reset the Stop bolts at 0.020” 6.) Open the switch. Set the length of the Power Spring between 3” to 3 1/8”. Make sure that both springs are set at the same length. Space Washer Set 3" to 3 1/8" without the thickness of the washers Torque the Jam Nut to 80 in-lb. Figure 49: Setting Power Springs Lengths 38 VBM Instruction Manual I 750-310 7.) Check Cranks for number of strokes to manually close the switch. 8.) Turn the Shaft, at the bottom of the motor; to setup one Eccentric operated at a time. Figure 50: Turning Motor Shaft 9.) Pull the crank to manually close the switch. It must be no more than 30 full manual strokes before the switch is operated. 10.) Set eccentrics by turning shaft of motor. Rotate shaft of motor to rotate eccentrics 180° using screwdriver. Reverse position and open switch. Close switch by moving handle back and forth less than 30 times and set. Cranks Eccentrics Figure 51: Setting Eccentrics 39 VBM Instruction Manual I 750-310 11.) Recheck the tightness of the setscrews on the motor mechanism assembly. Torque to 70 in-lb. Figure 52: Setscrews on Motor Mechanism Assembly 12.) Close the switch. Make sure that the Spring Plates Assembly is flat with the Actuator Bar. Spring Plates Assembly Figure 53: Spring Plates Assembly 40 VBM Instruction Manual I 750-310 2. Replacing Motor Not all motors are identical. When ordering replacement motors, the catalog number from the VBM nameplate must be supplied. New control panel may be required for obsolete motors. (G) Wiring Harness (D) Auxiliary Switches (F) Environmental Connector (E) Screws (4) Actuator Bar (C) Cable Connector (B3) Mounting Bolt (B1) Mounting Bolt Operating Lever Stops (A) Relay Panel (Control Assembly) (B2) Mounting Bolt Motor Operator Figure 54: VBM Motor Operator Diagram Refer to Figure 54 and follow steps below to replace motor assembly. 1.) Loosen bolts B1-B3. (Figure 54) 2.) Remove three set screws (if present). 3.) Disconnect push-on connectors of motor leads from relay. 4.) Unbend locking straps and remove three set screws. 5.) Remove motor. 6.) Install motor using set screw. 7.) Retighten bolts B1-B3. (Figure 54) 8.) Install locking straps and nuts and set the set screws. 9.) Bend corners of locking straps. 10.) Connect push-on connectors of motor leads to relay. 41 VBM Instruction Manual I 750-310 3. Servicing Motor Assembly - Electrical a) Removal and Installation of Relay Panel – Overview Refer to Figure 55 and follow steps below for removal and installation of Relay Panel. (G) Wiring Harness (D) Auxiliary Switches (F) Environmental Connector (E) Screws (4) (C) Cable Connector Motor Operator (B1) Mounting Bolt (A) Relay Panel (Control Assembly) Figure 55: Relay Panel Assembly Diagram 1.) Remove entire relay panel (A) by removing the mounting bolt (B1) and disconnecting cable connector (C), trip coil leads, charging motor leads, and install new relay panel. 2.) Remove wiring harness by disconnecting cable connector (C) and remove leads from terminals of auxiliary switch(es) (D). Remove four screws (E) which hold the environmental connector (F) and pull wiring harness (G) out of the housing. 3.) To install wiring harness (G), clean surfaces of casting where connector mounts. Apply a small amount of silicone grease to gasket of new connector. Install new harness (G) and rewire. NOTE: Refer to specific wiring diagram supplied with the switch. Check switch nameplate for wiring diagram number. 4.) To adjust auxiliary switch(es) (D), see the Auxiliary Switch Adjustment section on Page 55. 42 VBM Instruction Manual I 750-310 b) Installation of Relay Panel – Detailed 1.) Connect the motor wires to the Relay panel as shown in the figure below. Figure 56: Motor Wires and Relay Panel 2.) Remove the bolt from the Motor mechanism assembly as shown in the figure below. Spacer Bolt Shock Absorber Relay Panel Figure 57: Relay Panel Assembly 3.) Attach the assembly to the Motor mechanism assembly. Torque Bolt to 80 in-lb. Figure 58: Attaching Relay Panel Assembly 4.) Reinstall the bolt. Torque the bolt down to 80 in-lb. 43 VBM Instruction Manual I 750-310 5.) Tie the wire with Plastic Tie Rap as need to make it look neat in appearance. Plastic Tie Raps Figure 59: Tie Raped Wires and Relay Panel Assembly G. Synchronization of Replacement Module Assembly Operation of a replacement module assembly must be synchronized with other module assemblies on the mechanism. Module pair assemblies are synchronized using the lower contacts only. Synchronization refers to the difference in over-travel of modules (or lower contacts of module pair assemblies) on the same operating mechanism. NOTE: Do not attempt to synchronize a lower module with an upper module on a module pair assembly. ! CAUTION: FOR VBM’s WITH VACSTATTM. USE CARE WHEN WORKING AROUND THE FIBER OPTIC LINES. DO NOT BEND THEM SHARPLY TO AVOID DAMAGING GLASS FIBER. 44 VBM Instruction Manual I 750-310 1. Toggle Link Setting Procedure Toggle Link Requirements Standard Controls = 1 degree off vertical ZVC Application = 5 – 6 degrees off vertical a) Measuring Toggle Link Setting 5.) Place the VBM in the close position. 6.) Position the 1 (Standard) or 5-6 (ZVC) degree guide on linkage to confirm the guide lines up tight against the linkage. If a gap is present, adjust the toggle per steps below. 1 [5-6 for ZVC applications] Figure 60: Toggle Link Adjustment b) Setting Toggle Link Requirements 1.) Place the VBM in the close position. Figure 61: Switch Indicator in Close Position 45 VBM Instruction Manual I 750-310 2.) Loosen the close bumper stop. Close Bumper Stop Toggle Link Toggle Link Auxiliary Contact Assembly Bolts Toggle Link Support Bar Cable Connector Connecting Bolts Open Stop Close Stop Figure 62: Location of the Close Bumper Stops 3.) Position degree guide on linkage under the position indicator. Figure 63: Degree Guide Position 46 VBM Instruction Manual I 750-310 4.) Adjust the close stop to align the linkage against the degree guide. Use the ¾” wrench to help slowly move the linkage required. Figure 64: Adjusting the Close Stop 5.) Use the “adjusting screw” to hold the linkage in place after positioning the degree guide. Figure 65: Adjusting Screw 6.) Reposition the close bumper tight against the mechanism housing and tighten the bumper stop to 120 inch-lbs. Torque the Bumper Stop Bolts to 120 in-lb. Figure 66: Tightening the Bumper Stop 47 VBM Instruction Manual I 750-310 2. Full Travel Setting Procedure Full Travel Requirements (Revised December 2010) Solenoid/Motor = 0.220” – 0.230” Motor (⅜” Gap) = 0.405” – 0.425” Operating Notes: Full Travel setting was revised from 0.200” – 0.210” on December 2010. It is recommended that this new setting be used if maintenance is performed on the VBM. There is no need to make this change unless maintenance/repair is being performed. a) Measuring Full Travel Setting 1.) Place the VBM in the close position. 2.) Position the Dial Indicator gauge under the position indicator and then set the dial to the zero point. Set to the Zero Position Figure 67: Position of Dial Indicator Gauge ! CAUTION: AN OPEN OPERATION WITH THE DIAL GAUGE ATTACHED COULD DAMAGE THE GAUGE. 48 VBM Instruction Manual I 750-310 3.) Pull out and hold the actuating rod/arm on the dial indicator gauge. CAUTION: If arm is not held down during the open operation, damage to dial gauge could occur. Figure 68: Actuating Rod/Arm and Dial Indicator Gauge 4.) Manually operate the VBM to the open position. Figure 69: Switch Indicator in Open Position 5.) Release the arm dial indicator gauge when the VBM is in the open position. The dial should read a full travel value between acceptable range. If out of tolerance, refer to next section to adjust full travel. Figure 70: Full Travel Value on Dial Indicator Gauge 49 VBM Instruction Manual I 750-310 b) Setting Full Travel Requirements 1.) Place the VBM in the close position. 2.) Position the Dial Indicator gauge under the position indicator and then set the dial to the zero point. 3.) Loosen the Open Bumper stop and slide the bumper against the cast housing stop. Slide Assembly towards Housing Stop Loosen Bolts to Open Bumper Stop Note: Holes are actually slotted behind bracket to allow assembly to slide Figure 71: Open Bumper Stop Assembly 4.) Manually start to operate the VBM towards the open position with the ¾” wrench while holding the manual handle to prevent a complete open operation. Manually move the wrench towards the open position until 2 full rotations are observed on the dial. ! CAUTION: AN OPEN OPERATION WITH THE DIAL GAUGE ATTACHED COULD DAMAGE THE GAUGE. 5.) After the 2 full rotations, allow the mechanism to return back to the close position. 6.) Torque the open stop to 120 in-lbs. Be sure the auxiliary contact striker bracket is aligned before tightening. 7.) The setting can be confirmed by performing the test done previously by pull out and hold the actuating rod/arm on the dial indicator gauge. 50 VBM Instruction Manual I 750-310 ! CAUTION: IF ARM IS NOT HELD DOWN DURING THE OPEN OPERATION, DAMAGE TO THE DIAL GAUGE COULD OCCUR. 8.) Manually operate the VBM to the open position. 9.) Release the arm when the VBM is in the open position; dial should read the full travel requirement value. 3. Overtravel Setting Procedure Overtravel Requirements Solenoid/Motor = 0.038” – 0.048” ZVC Application = 0.043” – 0.048” a) Measuring Overtravel Setting 1.) Place the VBM in the close position. 2.) Position the Dial Indicator gauge under the position indicator and then set the dial to the zero point. Toggle Link Toggle Link Auxiliary Contact Assembly Dial Indicator (Secure against bolt) Toggle Link Support Bar Cable Connector Open Stop Bolts Connecting Bolts Close Stop Figure 72: Solenoid Operated VBM Mechanism 3.) Attach the sync lamps clamps to the high voltage contacts; the lamp should be illuminated. 51 VBM Instruction Manual I 750-310 4.) Using the 3/4" wrench, manually start to operate the mechanism towards the open position until the connected sync lamps turn off. An overtravel reading should be observed on the dial gauge. Figure 73: VBM Mechanism with Dial Indicator ! CAUTION: USE CAUTION TO PREVENT A COMPLETE OPERATION DUE TO POTENTIALLY DAMAGING THE DIAL GAUGE. b) Setting Overtravel Requirements 1.) Place the VBM in the close position. 2.) Position the Dial Indicator gauge under the position indicator and then set the dial to the zero point. 3.) Attach the sync lamps clamps to the high voltage contacts; the lamp should be illuminated. 4.) Using the ¾” wrench, manually start to operate the mechanism towards the open position. 5.) Observe the dial gauge reading at which the sync lamps on the other module(s) turn off. At ambient temperatures between 50ºF and 80ºF the lights should turn off when appropriate overtravel value is observed on the dial gauge. 52 VBM Instruction Manual I 750-310 6.) Insert the triangle wedge between close bumper stop and mechanism housing to hold the linkage at a position that the dial indicator reads overtravel spec value. Wedge Close Bumper Stop Figure 74: Wedge and Dial Indicator 7.) With the mechanism held in place, loosen and then re-tighten the pull rod to the clevis at 70 in-lbs. Clevis Pull Rod ¼-20x1" bolts, split lockwashers & ¼-20 nuts Torque to 70 in-lbs. Figure 75: Pull Rod and Clevis 8.) Remove the triangle wedge and close the mechanism. 9.) Slowly open the mechanism using the ¾” wrench, observe the sync lamps turn off as the mechanism travels to the open position. Note the dial readings at which the replacement and adjacent modules open. The last light must go out within 0.005” mechanism travel after the first light (see Figure 76). 53 VBM Instruction Manual I 750-310 Max sync 0.005” Max sync 0.005” L L L L Sync Lamps L One Pole 34.5kV Switch Three Phase 15kV/25kV Switch Figure 76: VBMs First-to-Last Synchronization ! CAUTION: USE CAUTION TO PREVENT A COMPLETE OPERATION DUE TO POTENTIALLY DAMAGING THE DIAL GAUGE. 10.) If desired sync requirement is not achieved, loosen pull rod varying the “set” position in appropriate direction until all single or lower contacts open within 0.005” of mechanism travel. 11.) After module pair assemblies have been synchronized using the lower contacts only, the synchronization between upper and lower contacts should be verified. The synchronization of upper and lower contacts is related to ambient temperature. At temperatures between 50ºF and 80ºF the dial gauge should measure a maximum of 0.010” travel of the actuating bar between the opening of each lower contact and its corresponding upper contact (see Figure 77). L Max contact sync on each pole 0.005” Sync Lamps Max contact sync on each pole 0.005” L L L Three Phase 34.5kV Switch Three Phase 25kV Switch Figure 77: VBM Module Pair Synchronization 54 VBM Instruction Manual I 750-310 4. Auxiliary Switch Adjustment a) Auxiliary Switch Adjustment (Switches Made After 1997) While the switch is in the open position, place a shim with 0.100” thickness up between the close bumper stop and casting. Close the switch using the manual operating handle so shim is firmly held in place. Shim (0.100” thickness) Close Bumper Stop Figure 78: Shim Placement Move auxiliary switch contact bracket so the spring is completely depressing plungers of auxiliary switch. Adjust the angle between spring and actuating bar to 88 – 90. Tighten bolts on contact bracket to 20 in-lbs. torque. Open switch with the manual operating handle and remove the shim. Auxiliary Contacts Contact Bracket Spring Torque to 20 in-lbs 88° to 90° angle Actuating Bar Figure 79: Auxiliary Switch Adjustment 55 VBM Instruction Manual I 750-310 b) Auxiliary Switch Adjustment (Switches Made Prior to 1997) With mechanism in closed position, use a C-clamp to hold the operating crank to its cover, so the crank cannot move from the closed position. Attach dial indicator and set at zero. With a wrench on toggle link move the mechanism toward the open position. The auxiliary switch should operate at or before 0.175” vertical movement is indicated. Slowly return mechanism to closed position. The auxiliary switch should operate before the mechanism has returned to within 0.025” of the fully closed position. If adjustment is not correct, release bolts and reposition bracket in appropriate direction. Retighten the bolts and recheck operation. Repeat until auxiliary switch operations occur within the allowable range. Tighten bolts to 70 inch-pounds. Switch Bracket Gasket Cable Connector Auxiliary Switch Toggle Link Torque to 70 in-lbs. Dial Indicator Figure 80: Auxiliary Switch Adjustment (Prior to 1997) 56 VBM Instruction Manual I 750-310 H. Wiring Harness and Auxiliary Contact Replacement (Switches Made Prior to 1997) The auxiliary switch (8) and cable connector (9) are integral parts of the wiring harness assembly. The entire assembly must be removed as a unit. Open splicing connectors on the four black solenoid wires. Remove the auxiliary switch bracket (10) from the support bar (11). Remove four screws (12) which hold the environmental control cable connector and pull wiring harness assembly out of housing. Figure 81: Wiring Harness and Auxiliary Contact Replacement To install wiring harness, clean surfaces of casting where connector mounts. Apply a small amount of silicone grease (Dow Corning DC III or equivalent) to gasket (13) of new connector. Install harness assembly, remount and adjust the auxiliary switch and rewire. See Auxiliary Switch Adjustment section on Page 56 to adjust properly. 57 VBM Instruction Manual I 750-310 V. Specifications Description Requirements Manual Reference Torque: Through Epoxy or Porcelain Metal to Metal Pull Rod Bolts Auxiliary Contacts (Switches Made After 1997) Auxiliary Contacts (Switches Made Prior to 1997) Solenoid Bracket - 4 Bolts Allen Head Screw (Motor Mech. Assembly) Bumper Stop Bus Bar 25 in-lb 50 in-lb 70 in-lb 20 in-lb 70 in-lb 70 in-lb 70 in-lb 120 in-lb 315 in-lb Toggle Link: Solenoid/Motor Angle 1° Angle 5-6° (ZVC Application) Page 48 Full Travel: Solenoid/Motor Motor, ⅜” Gap Page 29, 30 Page 29, 30 Page 53 Page 54 Page 55 Page 33 Page 40 Page 47, 50 n/a Page 45 0.220” – 0.230” 0.405” – 0.425” Overtravel: Solenoid 0.038” – 0.048” 0.043” – 0.048” (ZVC Application) Max sync. First-to-last ≤ 0.005” Max sync. Module Pair pole ≤ 0.005” Page 51 Page 51 Page 54 Page 54 Motor 0.038” – 0.048” Max sync. First-to-last ≤ 0.005” Max sync. Module Pair pole ≤ 0.005” Page 51 Page 54 Page 54 0.070” – 0.090” Page 32 200 µΩ Max Page 20 Pin-Gap: Solenoid Resistance: All VBMs 58 VBM Instruction Manual I 750-310 Description Torque: Handle Force Requirements 25 lb max Timing: Solenoids Open Timing 26-37 ms @ 120VAC Open Sync 2 ms max between Phases 2 ms max between Module Pair (Double Stack) Open Bounce 1 ms max Close Timing 29-37 ms @ 120VAC 25.8-37.8 ms @ 120VAC, timing repeatability must be < 0.5ms between all shots (ZVC Application) Close Bounce 2 ms max between Single Contacts 4 ms max between Module Pair (Double Stack) Motor Open Timing 50 ms max @ 24/48/125VDC, 120VAC, 220/240VAC Open Sync Time 1 ms max between Phases @ 24VDC, 120VAC/125VDC, or 220/240VAC 1 ms max between Module Pair (Double Stack) @ 24VDC, 120VAC/ 125VDC, or 220/240VAC Open Bounce 1 ms max Close Timing 4 sec max @ 125VDC/120VAC 6 sec max @ 24/48VDC Close Current 2 A max running current @ 220/240VAC 3 A max running current @ 48/125VDC 4 A max running current @ 24VDC Appendix A Manual Revision Notes Date: Scope: January xx, 2011 Added Detailed Sections for Toggle Link Setting, Full Travel Setting, Overtravel Setting, and Pin Gap Setting Added Specifications Section Revised Section Organization September 25, 2012 Changed 1 ms to 2 ms on page 59, under Open Sync February, 2013 Re-numbers index 59 VBM Instruction Manual I 750-310 Thomas & Betts Corp. 8155 T&B Blvd. Memphis, TN 38125 Phone: 800.326.5282 T&B Utility Products: http://utility.tnb.com Joslyn Hi-Voltage: www.joslynhivoltage.com 60