ADAMA SCIENCE AND TECHNOLOGY UNIVERSTY School Of Civil Engineering and Architecture Department Of Civil Engineering MSc Program In Construction Engineering and Management System Analysis and Management Techniques ( CEM 7203) Adama Town Water Supply and Sanitation Improvement Project (ATWSSIP) G+5 Office Building in Adama Town Final Report Submitted to: Getachew Tegegne (Ph.D.) Adama, Ethiopia July, 2023 Group members No. Name ID/No. 1 Girma Fekadu PGE/24873/14 2 Mesfin Arega PGE/24916/14 3 Yared Getachew PGE/24922/14 4 Kassahun Terefe PGE/24937/14 5 Heran Boru PGE/24911/14 6 Sifen Tilahun PGE/25111/14 7 Elias Ketsela PGE/24879/14 ii | P a g e Contents Chapter 1 .................................................................................................................................................................. 1 Introduction and Detail of the Proposed Project ........................................................................................................ 1 Chapter 2 .................................................................................................................................................................. 3 Risk related issues of the proposed project ................................................................................................................ 3 Chapter 3 .................................................................................................................................................................. 8 Environmental, Social, Health and Safety (ESHS) Issues of the proposed project ..................................................... 8 3.1 Objective of ESHS ......................................................................................................................................... 8 3.2 Scope of ESHS report ..................................................................................................................................... 8 3.3 Methodology implemented by the Contractor ................................................................................................. 8 3.4 List of plans by the contractor regarding ESHS............................................................................................... 9 3.5 Findings of key project ESHS issues with the Consultant side .................................................................... 10 3.6 Implementation of the ESHS from 5 star construction P.L.C point of view ................................................... 10 Chapter 4 ................................................................................................................................................................ 12 Quality Control and Quality Assurance Plan of AWSSIP ........................................................................................ 12 Chapter 5 ................................................................................................................................................................ 15 Land Acquisition Strategy and Material Management Plan of the project ............................................................... 15 Chapter 6 ................................................................................................................................................................ 18 Project schedule Management Plan ......................................................................................................................... 18 Chapter 7 ................................................................................................................................................................ 21 Cost estimation analysis for material and work ....................................................................................................... 21 7.1 Cost analysis by 5 Star Construction P.L.C ................................................................................................... 38 7.2 Current Price Quotation for material and works ............................................................................................ 39 7.3 Detail Project Drawing ................................................................................................................................. 39 7.4 AWSSIP G+5 Office Building Construction Photos ..................................................................................... 40 7.4 Expected view of the AWSSIP G+5 Office Building when completed .......................................................... 43 Chapter 8 ................................................................................................................................................................ 44 Conclusion ............................................................................................................................................................. 44 Annex part A .............................................................................................................................................................. Annex part B ......................................................................................................................................... …………….. List of Figures Figure 1 AWSSIP Project Detail................................................................................................................. 2 Figure 2 ESHS training for site workers ..................................................................................................... 9 Figure 3 several Quality controlling and assurance tests conducted on site and laboratory ...................... 14 Figure 4 Land Acquisition Strategies ........................................................................................................ 15 Figure 5 Material Management plan ......................................................................................................... 17 Figure 6 AWSSIP G+5 Project Schedule .................................................................................................. 19 Figure 7 Current Project Cost estimation by 5 star.................................................................................... 38 Figure 8 after site clearance of building and marking for excavation layout ............................................. 40 Figure 9 Current status of the Project........................................................................................................ 42 Figure 10 Expected image when AWSSIP G+5 is completed ................................................................... 43 System Analysis and Management Techniques (CEM 7203) Page ii Chapter 1 Introduction and Detail of the Proposed Project Team Name: - 5 Star Construction P.L.C Logo:- Project Cost Descriptions Project Cost Estimated by Client = 100,000,000 Birr Total Cost Estimated by Contractor = 115,549,474.31 Birr Project Cost Estimated by 5 Star Construction P.L.C = 231,601,556.43 Birr Project Starting Date: - 19/ 03/2023 Project Name: - Adama Town Water Supply and Sanitation Improvement Project (AWSSIP) G+5 Office Building Contact Person: - Fantaye Aworaris (+251-911-045914) Project Status: - Ongoing Project (Footing column concrete casted and Backfill compaction) Project Scope Overview: The project will be aimed to develop new water sources (boreholes), collector pipes, transmission pipelines, distribution lines, construction of collector and service reservoirs, guard houses, generator houses, and guard house with EEU switch boards provide for the proper water supply system operation. Project Objective: - System Analysis and Management Techniques (CEM 7203) Page 1 The implementation of this project will be expected to alleviate the prevailing potable water supply shortage and improve the living conditions of inhabitants by appraising existing systems and redesigning additional new water supply system, as well as providing capacity building for town‟s water supply services and provision of one center controlling unit which is G+5 Office Building allocated on Adama town as one part of the project. List of Stakeholders: - The main parties/stakeholders those are involved on the project are Africa Development Bank The government of Federal Democratic Republic of Ethiopia The government of Regional state of Oromiya Adama Town Water Supply Sewerage Service Enterprise MS Consultancy P.L.C C.G.C.O.C Co.LTD Figure 1 AWSSIP Project Detail System Analysis and Management Techniques (CEM 7203) Page 2 Chapter 2 Risk related issues of the proposed project Before discussing about risk management it would be better to understand what the terminology „risk‟ means. Risk is associated with every aspect of our daily life, i.e. risk is involved in every step we take. According to the Oxford English Dictionary (2009), risk is a situation involving exposure to danger or the possibility that something unpleasant will happen. Different literatures, professionals and standards define risk in their own way. But most of them confirm that the view towards risk is most of the time negative. 2.1 Areas of Risk Main areas of risk in construction contracts are briefly discussed below; Contractual risk: is risk which result from not clearly defining the responsibilities and duties of the contracting parties. Performance risk: is a risk due to clearly undefined scope and nature of work. The contractor is expected to perform the work with some standard including safety. Financial/Economical risk: are risks that are a result of not understanding the terms of payment, performance bond, bank guarantee etc. The payment terms should reflect the progress of the work and the parties should have the required financial backing from a reliable source. Technical risk: this risk arises from lack of understanding of the system and the technology that would be utilized at the time of bid and during construction. Geographical risk: arise as a result of the location of the site. The location of the site is very important and should be selected very carefully because it can lead to additional risks like political risk. The stability, material supply interruptions, mobility and access should all be considered during bid and contract agreement. Operator risk: are due to the operators influence on the bid, contract, supervision, and approval etc…the operator should have the required insurance coverage which should be clearly stated in the contract document, for example, so that claims would lead to payment instead of dispute. Underperformance of the operator should not affect the work of the contractor; therefore there should be clear statements in the contract specifying the operator‟s obligations and the consequences to the contractor. Based on previously mentioned types of risks our team got the chance to observe some the risks on the proposed site of construction, namely each of them are listed and manipulated as below System Analysis and Management Techniques (CEM 7203) Page 3 1. Design risks Design errors and omissions and still there is modification on the design The design process takes longer than anticipated Stakeholders request late changes Failure to carry out the works in accordance with the contract 2. Environmental risks Environmental analysis incomplete New alternatives required to avoid, mitigate or minimize environmental impact 3. Organizational risks Delayed deliveries Lack of protection on a construction site 4. Project management risks Failure to comply with contractual quality requirements Scheduling errors, contractor delays 2.2 Risk management systems Management is a means of integrating resources in order to achieve organizational objectives efficiently and effectively. Risk management is used to identify, prevent, contain and mitigate risks in order to achieve project objectives. Risk management is also as ongoing process throughout the project containing the following five steps. (i) Risk identification- The process of identifying all the risks relevant to the project; (ii) Risk assessment- Determining the likelihood of identified risks materializing and the magnitude of their consequences if they do materialize; (iii) Risk allocation- Allocating responsibility for dealing with the consequences of each risk to one of the parties to the contract, or agreeing to deal with the risk through a specified mechanism which may involve sharing the risk (iv)Risk mitigation- Attempting to reduce the likelihood of the risk occurring and the degree of its consequences for the risk-taker; and System Analysis and Management Techniques (CEM 7203) Page 4 (v) Monitoring and review- Monitoring and reviewing identified risks and assessing, allocating, mitigating and monitoring new risks as the project develops and its environment changes. This process continues during the life of the contract. 2.3 Risk management in Ethiopian building construction contracts Most standard construction contracts contain some clauses that deal with common risks like none or under performance of the parties and war. But the specific risks that might hinder the project from achieving its objectives are not thoroughly identified and managed using clearly placed contractual clauses. The fact that most building construction projects are not completed on time, within budget and to the required quality standards shows that these contracts need some improvements and additional clauses that deal with managing risks. Unidentified and undefined risks have big effects on project objectives; therefore, the contract should contain clearly identified and defined risks and suggest ways of managing them to minimize their effect on project objectives. Some of the risks which are discussed in the civil code of Ethiopia and in the standard conditions of contract are briefly discussed below. According to the civil code of Ethiopia, (1960), Article 1790 (1) states “Apart from or in addition to the enforcement or cancellation of the contract, a party may require that the damage caused to him by the other party, failing to perform his obligation be made good”. This means the party that failed to perform his task should face the consequence of his actions and fix the damages. According to this article, any performance risks can be managed by checking the contractual clauses that deal with obligation and the consequences of not performing them. The contract, hence, should clearly contain the obligations and rights of the parties as well as the penalties of nonperformance of the duties specified in the contract. Article 1791(1) further states that “the party who fails to perform his obligation shall be liable to pay damages notwithstanding that he is not at fault”. This implies that a party that did not perform his duties according to the contract should pay for any damages that are found to be his fault i.e. the result of his nonperformance. Article 1795 states “A party may not claim damages on the ground of non- performance of the contract by the other party, unless he can show that the other party is in default”. This means if a party cannot prove the nonperformance of another party, in relation to the contract, he cannot claim the damages that resulted from the nonperformance. This statement shows the power of the contract, if the System Analysis and Management Techniques (CEM 7203) Page 5 obligation of the parties is clear and unambiguous in the contract then it can easily be proven if there is any nonperformance. Article 1924 (1) of the civil code states “a guarantee may not exceed the amount owned by the debtor, nor be constructed on more burdensome terms”. This means the amount of the insurance should cover the damage. As mentioned earlier insurance is one way of dealing with risk but the amount of damage the risk may cause to the project should be assessed and the exact amount known to have an equivalent insurance cover. In simple terms the insurance should cover every cost that arises because of the manifestation of the risk and its consequences. The general conditions of contract, 2006, prepared by the Public Procurement Agency (PPA) of Ethiopia also have different clauses that deal with the general risks common to most projects. Clause 20: states that “the consultant should have an insurance coverage against risks specified in the special conditions of contract”. This implies that the risks which are believed to have an effect on the execution of the project should be clearly identified and dealt with in the specific conditions of the contract by providing enough insurance coverage. The article further discusses that a consultant needs to have professional indemnity insurance before award of any contract. This is one way of dealing with risk by making sure the consultant is covered for any fault that might occur during the design and supervision of the project. The general conditions of contract by the ministry of works and urban development (MoWUD), identifies some special risks which the contractor is not liable for. Some of these special risks are war hostilities, invasion, act of foreign enemies; contamination by radio-active components, pressure wave caused by aircraft or other aerial devices; riot, commotion, or disorder, unless solely restricted to employees of the contractor or his sub-contractor and arising from the conduct of the works; rebellions, revolution, military or usurped power, or civil war. This general condition of contract further states in the following statement that the contractor should be provided with payment to rectify any damage or destruction caused by the special risk and to replace any material or property needed to complete the project. As mentioned above, the standard contract documents used in Ethiopian building construction industries deal with some risks which are common in all building construction projects. And in most cases, only the risks which are included in these standard documents are included in the contracts. But in addition to that, it is recommended that risks that are unique and specific to any particular project be System Analysis and Management Techniques (CEM 7203) Page 6 identified and included in the particular conditions of the contract so that they can easily be managed if and when they occur. System Analysis and Management Techniques (CEM 7203) Page 7 Chapter 3 Environmental, Social, Health and Safety (ESHS) Issues of the proposed project ESHS means standards, measures or actions, as appropriate and includes on a social side labor standards, as well as all social impacts on individuals, communities and workers, and the way, in which their working conditions, socio- economic status, cultural identify, human rights or health may be affected. 3.1 Objective of ESHS The objectives of ESHS implementation performance report is to make sure that environmental, social, health, and safety risks and impacts associated with the AWSSIP project/program activities implemented by the client and ensure that the transaction does not carry any environmental, social, health, and safety risks and impacts to the nearby biophysical and social environment. 3.2 Scope of ESHS report ESHS Expert drafts a Site Safety Precaution Instruction, identifying all potential risks to employee‟s health and safety, providing clear instructions on how to handle these risks, and making clear requirements on employee behavior and activities. The Site Safety Precaution Instruction should be publicized in clear and simple language, in the form of big notification board, and be erected at the entrance of work site, so that employees may have easy access to the information. The Site Safety Precaution Instruction will be revised and publicized when necessary. Besides written form of Safety Precaution Instruction, Construction manager, engineers of different professions and foremen give oral instructions to his own employees before they enter to work site. Labor protection measures, such as helmet, gloves, shoes, special cloths, glasses will be allocated to workers; the requirements of how to apply these labor protection measures will be clearly stated on the safety notification boards on site. 3.3 Methodology implemented by the Contractor The Contractor CGCOC Group Co., Ltd has established his own Environmental, Social, Health and Safety (ESHS) Management Strategies and Implementation Plan to manage all ESHS related issues, risks and hazards. ESHS Management Strategy shall be introduced to all Company staff, subcontractors, beneficiaries and related parties, and will carefully be implemented and monitored to achieve ESHS System Analysis and Management Techniques (CEM 7203) Page 8 management goals and targets, and fulfill the Company‟s commitments to eliminate ESHS related issues according to contract requirements. The Company has also developed an Implementation Plan to guarantee the unconditional implementation of ESHS Management Strategy. On Project management level, an ESHS management team will be established during the contract period, which will be directed by the Project Manager, and formed by Chief Engineer, Site Engineer, ESHS Expert, Community Relationship Expert and other managerial personnel on site. The organization guarantees the Company‟s ESHS Management Strategy and policies be implemented during daily construction work, thus on-site ESHS issues can be monitored and managed. 3.4 List of plans by the contractor regarding ESHS The company‟s plan under the safety department is: To prevent accidents, respond to emergencies, and to reinforce the effectiveness of the company‟s safety programs. To identify safety hazards and investigate them thoroughly and controls them before someone gets hurt. Create a safe environment by making sure that the employees have the necessary safety equipment Organize employees with their work load so that no harm will come to them during their work activities Assess and document hazards, risks and controls in a manner consistent with established procedures and practices. Supervise the operation of any potential hazards in the work place Ensure that health ,safety and environmental policies are followed Investigate workplace accidents and injuries and refer them to the proper authorities. Figure 2 ESHS training for site workers System Analysis and Management Techniques (CEM 7203) Page 9 3.5 Findings of key project ESHS issues with the Consultant side The Company‟s ESHS management goals are simply stated: - To manage an injury free project. - To conduct our work in the spirit of „respect for people. - To provide equal employment opportunities regardless of color, race, nationality, ethnic or national origin, sex or disability. Policy statements for social, health, safety and environment, corporate social responsibility and equal opportunities are included within this document. 3.6 Implementation of the ESHS from 5 star construction P.L.C point of view A. Right of way issues Joint effort being in unity with the contractor, the client, consultant and all the concerned governmental bodies‟ right of way issues can be managed to solve the hindrances by consultations. B. Air quality pollution The construction activities mostly the excavation and transportation of construction materials are likely to generate a significant amount of dust as well as emitting smoke and fumes from engines and oil spills that will lead to pollution of air. Therefore, to mitigate this problem we ensure that all vehicles transporting raw materials especially soil should be covered or avoid overloading to reduce dust emissions, employees should be provided with safety equipment‟s, the movement and speed of the construction machineries and vehicles should be controlled and water has to be sprinkled on dusty roads and soil heaps to keep down the dust produced. C. Occupational Health Hazards Occupational health hazards must be put under consideration and check. To mitigate this problem so far the contractor have given protective safety equipment‟s, conducted safety awareness or sensitizations programs, during inspections there is oral and formal warnings for site workers if they are working without safety equipment‟s. System Analysis and Management Techniques (CEM 7203) Page 10 D. Environmental and Social Assessment Mostly social safety issues are related to right of way issues. The Employer considers health and safety of workers as foremost priority and the Contractor is expected to reflect this in Healthy, Safety and Environment plan of the Works. The Contractor complies with all statutory and other regulations concerning the safety of Contractor‟s Personnel, Employer‟s Personnel, the Employer‟s Representative, visitors to Site and members of the public, at all times throughout the execution of the Works. The contractor obtains copies of all regulations and shall make them available on Site for inspection by the Employer‟s Representative. The Contractor is responsible throughout the contract period to ensure that all work practices comply with the occupational health and safety requirements outlined in Labor Proclamation No. 1156/2019 and all other Ethiopian statutory requirements, and these requirements are reflected in the HSE plan to ensure the health and safety of employees during the design, construction, operation and maintenance stages of the project. E. Other specific issues This section will elaborate on unplanned measures including the identification/treatment of residual impact. Example would cover the following questions, as applicable: Where the Contractor enters into private agreements with landowners for use of land outside the Site boundary or agreed way leaves, The Contractor shall provide a copy of the agreement to the Employer‟s Representative for information. F. Engagement of Personnel The Contractor‟s Representative may manage by himself, or sometimes delegate to Construction Manager, Engineers, Specialists and/or other management personnel to oversee and manage different levels of stakeholder relationships. The delegated personnel directly report to Contractor‟s Representative for critical and urgent issues; however, he/she will also be granted authority to certain extent, so that routine stakeholder related issues could be solved as quickly as possible to obtain permit for accessing the required tasks. System Analysis and Management Techniques (CEM 7203) Page 11 Chapter 4 Quality Control and Quality Assurance Plan of AWSSIP Quality assurance (QA) and quality control (QC) are critical components of any construction project. QA/QC plans help ensure that the finished product meets all requirements and that any defects are identified and corrected before they cause serious problems. Numerous studies have illustrated the benefits of a construction quality control plan. A construction quality control plan can save time and money by helping to prevent potential problems before they occur. Indeed, when it comes to construction, there is simply no substitute for a comprehensive quality control plan, especially when dealing with specialty trades or complex technical work. 4.1 Key Benefits of a QA/QC Plan A well-crafted quality control plan is essential for ensuring that a project meets all applicable standards and regulations. By extension, a quality assurance/quality control (QA/QC) plan helps to ensure that the project is delivered on time, on budget, and with no surprises. Here are some of the critical benefits of quality assurance/quality control plans: A good control plan extends the quality program deeper into specialty trade compliance, technical work, or project startup and commissioning. Having a single control plan that outlines all control methods, quality planning, and orchestrates all engineering inspections, performance tests, and checklists helps to streamline production processes and makes it easier to track progress and identify potential areas of improvement. Finally, a quality assurance/quality control plan helps to create a culture of quality within the organization that can be applied to future projects. By instilling a commitment to quality at all levels of the organization, QA/QC plans help to ensure that projects are delivered according to the highest standards. 4.2 Elements of a QA/QC Plan for the proposed Project A. Quality policy and objectives The quality policy is a statement from management that defines the quality objectives for the project. The quality objectives should be specific, measurable, achievable, relevant, and time-bound (SMART). System Analysis and Management Techniques (CEM 7203) Page 12 B. Documented Standards and Specifications All quality standards and specifications for the project should be documented in the QA/QC plan. These may include international standards such as ISO 9000 or national standards such as Safety Schemes in Procurement (SSIP). On AWSSIP Project for G+5 Office building the specification clearly states that each and every material should be examined before it is used for the project based on the standards, works and personnel should be as per the required standard for the allocated tasks. C. Formal Qualifications of Employees, Subcontractors, and Suppliers The QA/QC plan should include a list of all employees, subcontractors, and suppliers who will be involved in the project. For each individual, the plan should specify their qualifications and experience. The QA/QC plan should include how employees, subcontractors, and suppliers are qualified to work on the project. This may mean soliciting specific certifications or degrees, or demonstrating that they have a certain amount of experience in the field. D. Quality Control and Assurance Procedures The QA/QC plan should describe the procedures used to detect quality issues and control quality throughout the project. These procedures may include quality audits, inspections, listing all performance tests conducted, and reviews. E. Inspection and Test Plan The inspection and test plan is a continuous process throughout the project life time. On AWSSIP G+5 Office Building the following inspections are observed during construction Compaction test with authorized laboratories Rebar tensile strength and elongation test on AAiT laboratory Aggregate quality tests Proper mix design preparation Water quality test for concrete works Survey related works by the contractor and checked by the consultant F. Control and Prevention of Non-conformances The QA/QC plan should also include procedures or process flow diagram for preventing and correcting quality problems. These may consist of rework, repair, or replacement of defective work. The plan should also define how nonconformance will be documented and tracked. During the report period our team got System Analysis and Management Techniques (CEM 7203) Page 13 the chance to observe several quality controlling mechanisms and several tests, some of them are listed below as shown in the figure Figure 3 several Quality controlling and assurance tests conducted on site and laboratory System Analysis and Management Techniques (CEM 7203) Page 14 Chapter 5 Land Acquisition Strategy and Material Management Plan of the project 5.1 Land Acquisition Strategy The client (AWSSE) gets a total of 2000m2 land for the construction of the proposed G+5 office building near to Medihanyalem Church on the road side towards Adama Science and Technology University with suitable topographic arrangement. All right of way and compensation related issues are handled and guaranteed from the Adama Town Administration office. During pre-feasibility study period all necessary documents had been compiled and the ground condition is examined by proper authorized laboratories to decide which type of structure should be constructed to assure safety of the Building. The ground condition is almost in flat terrain therefore the proposed location saves several advantages for the consultant as well as the contractor which didn‟t require further provision of retaining wall and unsuitable cut and fill earth work. Figure 4 Land Acquisition Strategies 5.2 Material Management Plan Adama Town Water Supply and Sanitation Improvement Project (AWSSIP) G+5 Office Building all materials which is planned to use for the execution of the project had the following several properties System Analysis and Management Techniques (CEM 7203) Page 15 A. Delayed supply of material to the site Most of the construction materials are imported from other countries as per the project agreement between Client and Contractor which leads to delay on the progress of the project and affect the entire schedule. The materials include reinforcement bar, finishing materials, and such like materials to process procure and transport may take several times. B. Outlaying Materials If materials are distant from a job site, contractors will have to leave the work-space to find them resulting in time lost in the retrieval process. For example the aggregates are taken from the approved location on the East of Adama location which had more than 5km distance from the project site. C. Stolen Materials Depending site diaries and letters the contractor had been robbed and lost many materials and such activities create disturbance and wrong image creation to the future planned projects. Also to process and recover the material there will be some time gap which can be available for the construction therefore it had adverse effect on the schedule of the project. D. Projects Plan Incomplete When project plans remain pending, this causes logical challenges. If you can't depict which additional items you might need to complete a job. E. Access to the market The client is supporting the contractor by providing several support letters for different cement factories to purchase by factory price which will help the contractor to survive the current market fluctuation and price escalation. Currently the client provide support letter for Mugher cement factory and Dangote cement factory by communicating with concerned higher officials such as Ministry of Water and Energy and Ministry of Trade. F. Test on Materials 5 star Construction P.L.C during the report period had observed the following draw backs on the test of materials procedure System Analysis and Management Techniques (CEM 7203) Page 16 most of the tests are conducted on the authorized laboratories those exist outside of Adama such as Addis Ababa Institute of Technology (AAiT), Ethiopian Construction Works Design and Supervision (ECWDS), Oromiya Construction Corporation (OCC) to conduct the required tests on those laboratories it may take several time, high cost to the client, sample disturbance till the material arrive to the specified laboratory. It is preferable to rearrange one laboratory on nearby location to the project site. Test on material should be conducted on fixed interval of time instead of performing on the commencing stage because there might be change on the nature of the materials throughout the time. Sampling specimen problems may lead to incorrect result or may not represents the correct or actual executed work. Figure 5 Material Management plan System Analysis and Management Techniques (CEM 7203) Page 17 Chapter 6 Project schedule Management Plan According to previously stated chapters and articles the project (AWSSIP) passes through different challenges and risk related issues those are the cause for modification and adjustment for the schedule of the project execution as well as completion period. Also current working trend and market situation of the country the contractor (C.G.C.O.C Co.LTD) is forced to revise the project schedule several times. On the period of study from 5 Star construction P.L.C get the last revised schedule from the contractor side but still they are behind the schedule as shown below to finalize the project on 474 working days, and our team revises the schedule to complete the entire project within 201 days by applying several methods as per the attachment on the conclusion. System Analysis and Management Techniques (CEM 7203) Page 18 Figure 6 AWSSIP G+5 Project Schedule System Analysis and Management Techniques (CEM 7203) Page 19 Based on the proposed project schedule our team finds out and suggest the following points Cause for schedule revision is due to design modification from the consulting side therefore instead of modifying the design one by one it is preferable to assign or delegate expert on the company to summarize and deliver the final drawing without changing the scope of the entire project. From the Contractor side we observe that on coming rainy season they fully estimated that the weather will interrupt the progress of the project and they are ready to raise cause of delay instead it should adjusted based on the weather condition the contractor should prepare adaptable workman ship which is applicable for rainy season. There are simultaneous work which can be performed on different location for example bar scheduling for the remaining floors, material stocking on stores, preparation of shop drawing etc. therefore if those works are completed on same phases they will save time and prevent occurrence of delay on the progress of the project. Finally based on actual workmanship on site and current status of the project by including several constraints and relation between each task our team had prepared the project master schedule by using applicable software as it attached on the conclusion part. System Analysis and Management Techniques (CEM 7203) Page 20 Chapter 7 Cost estimation analysis for material and work AWSSIP G+5 Office Building project is Admeasurement type of contract agreement between the client and the contractor to execute the entire project. During biding time the contractor (C.G.C.O.C co., LTD) had won the project of G+5 Building with total project cost of 115,549,474.31(one Hundred Fifteen Million Five Hundred forty nine Thousand four Hundred seventy four and 31/100) Ethiopian Birr. There is increment on quantity of work when actual work is done since the rate for each item is clearly stated on the Bill of Quantities of the project calculation of each works is easy to adopt. The original BOQ of the project is attached here for further analysis. System Analysis and Management Techniques (CEM 7203) Page 21 System Analysis and Management Techniques (CEM 7203) Page 22 System Analysis and Management Techniques (CEM 7203) Page 23 System Analysis and Management Techniques (CEM 7203) Page 24 System Analysis and Management Techniques (CEM 7203) Page 25 System Analysis and Management Techniques (CEM 7203) Page 26 System Analysis and Management Techniques (CEM 7203) Page 27 System Analysis and Management Techniques (CEM 7203) Page 28 System Analysis and Management Techniques (CEM 7203) Page 29 System Analysis and Management Techniques (CEM 7203) Page 30 System Analysis and Management Techniques (CEM 7203) Page 31 System Analysis and Management Techniques (CEM 7203) Page 32 System Analysis and Management Techniques (CEM 7203) Page 33 System Analysis and Management Techniques (CEM 7203) Page 34 System Analysis and Management Techniques (CEM 7203) Page 35 System Analysis and Management Techniques (CEM 7203) Page 36 System Analysis and Management Techniques (CEM 7203) Page 37 7.1 Cost analysis by 5 Star Construction P.L.C As it is clearly mentioned on the previous articles our team calculated the total cost of the project by referring the current price estimation from different offices especially from City Government of Addis Ababa Design and Construction Works Bureau and total cost becomes 231,601,556.43 (Two hundred Thirty One million Six hundred One thousand Five hundred Fifty Six and 43/100) Ethiopian Birr. It had great variation with the contractor price due to market fluctuation and unstable price escalation of material. Figure 7 Current Project Cost estimation by 5 star System Analysis and Management Techniques (CEM 7203) Page 38 7.2 Current Price Quotation for material and works In order to estimate the current total project cost it is mandatory to arrange the price break down for each work items and further analysis is required for entertaining market fluctuation and economical risks on current construction industry. According to City government of Addis Ababa Design and Construction Works Bureau they provide the current market and direct cost of each resource on quarterly interval of each year, based on this document our team conducts the current rate for each item and current total project cost of the proposed building as follows Direct cost from the reference of City government of Addis Ababa Design and Construction Works Bureau Overhead cost of 10 % Profit margin of 7 % and other necessary assumption is made for the calculation. The referred document from City government of Addis Ababa Design and Construction Works Bureau and some samples of cost break down analysis document is attached on Annex A part for detail analysis. 7.3 Detail Project Drawing As it is clearly discussed on risk related issues of chapter 2 the project is highly exposed to several design changes for long time and it is causing trouble on the progress as well as on the total picture of the project by retarding the process in addition to that our team propose and shows direction for this problem which is assigning expert on the design aspect to finish the total design related issues for last time is the perfect way to handle such risk. During the analysis the project last modified drawing is attached on Annex B part for detail analysis. System Analysis and Management Techniques (CEM 7203) Page 39 7.4 AWSSIP G+5 Office Building Construction Photos Figure 8 after site clearance of building and marking for excavation layout System Analysis and Management Techniques (CEM 7203) Page 40 System Analysis and Management Techniques (CEM 7203) Page 41 Figure 9 Current status of the Project System Analysis and Management Techniques (CEM 7203) Page 42 7.4 Expected view of the AWSSIP G+5 Office Building when completed Figure 10 Expected image when AWSSIP G+5 is completed System Analysis and Management Techniques (CEM 7203) Page 43 Chapter 8 Conclusion Systems analysis is "the process of studying a procedure or business to identify its goal and purposes and create systems and procedures that will efficiently achieve them". Another view sees system analysis as a problem-solving technique that breaks down a system into its component pieces, and how well those parts work and interact to accomplish their purpose. The principal objective of the systems analysis phase is the specification of what the system needs to do to meet the requirements of end users. In the systems design phase, such specifications are converted to a hierarchy of charts that define the data required and the processes to be carried out on the data so they can be expressed as instructions of a computer program. Based on the detail analysis formulated on the discussion part our team analyzed and confirmed several constraints on the project that had adverse effect on the progress of the project, namely Design related risks Market fluctuation risks Safety and health related risks Plan vs. actual work status gap Cost of works increment Quality control and Quality assurance risks Schedule related risk etc. On cost aspect the analysis follows the following calculating perceptions Current material cost is adopted from City government of Addis Ababa Design and construction works bureau. The overhead and profit margin are 10 % and 7 % respectively. The summary of cost analysis tabulated as shown for better comparison System Analysis and Management Techniques (CEM 7203) Page 44 Table 1 Cost comparison Cost estimation by Cost Item Cost of project estimation Cost estimation client/consultant(A) by Contractor(B) by 5 star(C) 100,000,000.00 115,549,474.31 231,601,556.43 Variation between Variation between client and 5 star(C- contractor and 5 A) Star(C-B) 131,601,556.40 116,052,082.10 On schedule aspect the contractor had submitted a draft for the schedule which lasts on 474 days to complete the entire project and it is fully discussed on previous chapters, However 5 Star construction P.L.C analyzed and estimates the completion date to be 201 days by applying several mitigation measures those are described as constraints from the contractor side such as By changing Saturday and Sunday as working days By method of fast tracking on those critical activities by adding more resources to each tasks By preparing simultaneous work which can be performed in parallel Preparing several tasks for the rainy season instead of waiting until it pass By increasing the working hours of the day. System Analysis and Management Techniques (CEM 7203) Page 45 ID Task Mode 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Task Name Duration Start Finish March 3/5 5 star construction P.L..C 1 Design modification 1.1 signining agreement withmodification new design team 1.2 and correction of defect to 2 Sub Structure 201 days 15 days 1 day 15 days 41 days 2.1 Site Clearance 1 day 2.2 Bulk Excavation in 5 days ordinary soil 2.3 Bulk Excavation in Hard 2 days rock 2.4 Pit and Trench Excavation 5 days 2.5 Fill around footings 4 days and foundation to the 2.6 Back fill under hard core3 days 2.7 Cartaway surplus 2 days materrial 2.8 Hardcore fill 3 days 2.9 Concrete work 14 days 2.9.1 Lean concrete 2 days underLean footing pad for 2 days 2.9.2 concrete Grade beam 2.9.3 Form work to 3 days footing pad and column 2.9.4 Form work to 3 days Grade beam 2.9.5 Reinforcement Bar 3 days for footing pad and Bar 3 days 2.9.6 Reinforcement for Grade 2.9.7 C-25beam concrete on 3 days footing pad and column 2.9.8 C-25 concrete on 3 days GradeC-25 beam 2.9.9 Concrete on 3 days Ground floor slab Project: 5 star construction P.L.. Date: 7/5/2023 3/12 3/19 3/19/2023 8/26/2023 3/19/2023 3/19/2023 3/19/2023 3/19/2023 4/1/2023 4/5/2023 4/7/2023 4/7/2023 4/7/2023 4/1/2023 4/7/2023 4/9/2023 4/9/2023 4/9/2023 4/12/2023 4/9/2023 4/16/2023 4/12/2023 4/18/2023 4/16/2023 4/9/2023 3/19/2023 3/31/2023 4/20/2023 3/21/2023 4/5/2023 4/7/2023 4/11/2023 4/10/2023 4/9/2023 4/3/2023 4/9/2023 4/20/2023 4/11/2023 4/11/2023 4/15/2023 4/11/2023 4/18/2023 4/15/2023 4/20/2023 4/19/2023 4/11/2023 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 1 3/26 April 4/2 4/9 4/16 4/23 ID Task Mode 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 Task Name Duration Start Finish March 3/5 2.10 Masonary Work 7 days 2.10.1 Stone masonary 7 days below ground level 3 Super Structure 171 days 3.1 Concrete work 138 days 3.1.1 Reinforcemnet bar 3 days for ground 3.1.2 Form column work for 2 days ground floor column 3.1.3 C-25 concrete for 2 days ground floor column bar 3 days 3.1.4 Reinforcemnet for bracing beamfor 3.1.5 Form work 3 days Bracing beam 3.1.6 C-25 concrete for 2 days bracing beam 3.1.7 Reinforcemnet bar 3 days for first floor slab 3.1.8 Form work for first 3 days floor slab 3.1.9 C-25 concrete for 2 days first floor slab 3.1.10 Reinforcemnet 3 days bar forForm first floor 3.1.11 workbeam for 2 days first floor beam 3.1.12 C-25 concrete for 2 days first floor beam 3.1.13 Reinforcemnet 3 days bar forForm first floor 3.1.14 work for 3 days first floor column 3.1.15 C-25 concrete for 2 days first floor column 3.1.16 Reinforcemnet 3 days bar for second floor slab 3.1.17 Form work for 3 days second floor slab 3.1.18 C-25 concrete for 2 days secondReinforcemnet floor slab 3.1.19 3 days bar for second floor Project: 5 star construction P.L.. Date: 7/5/2023 4/9/2023 4/9/2023 4/12/2023 4/12/2023 4/12/2023 4/16/2023 4/16/2023 4/26/2023 4/28/2023 4/28/2023 4/28/2023 4/28/2023 5/1/2023 5/10/2023 5/10/2023 5/10/2023 5/21/2023 5/21/2023 5/23/2023 5/23/2023 5/23/2023 5/26/2023 6/3/2023 3/12 3/19 4/15/2023 4/15/2023 8/26/2023 7/31/2023 4/14/2023 4/17/2023 4/17/2023 4/28/2023 5/1/2023 4/30/2023 5/1/2023 5/1/2023 5/2/2023 5/13/2023 5/12/2023 5/12/2023 5/23/2023 5/23/2023 5/25/2023 5/25/2023 5/25/2023 5/27/2023 6/5/2023 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 2 3/26 April 4/2 4/9 4/16 4/23 ID Task Mode Task Name 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 Project: 5 star construction P.L.. Date: 7/5/2023 Duration Start Finish March 3/5 3.1.20 Form work for second floorconcrete beam for 3.1.21 C-25 secondReinforcemnet floor beam 3.1.22 bar forForm second floor 3.1.23 work for secondC-25 floorconcrete column for 3.1.24 secondReinforcemnet floor column 3.1.25 bar for third floor slab 3.1.26 Form work for third floor slab 3.1.27 C-25 concrete for third slab 3.1.28floor Reinforcemnet bar forForm third work floor beam 3.1.29 for third floor beam 3.1.30 C-25 concrete for third beam 3.1.31floor Reinforcemnet bar forForm third work floor for 3.1.32 third floor 3.1.33 C-25column concrete for third floor column 3.1.34 Reinforcemnet bar forForm fourthwork floorfor slab 3.1.35 fourth floor slab 3.1.36 C-25 concrete for fourth floor slab 3.1.37 Reinforcemnet bar forForm fourthwork floorfor 3.1.38 fourth floor concrete beam for 3.1.39 C-25 fourth floor beam 3.1.40 Reinforcemnet bar forForm fourthwork floorfor 3.1.41 fourth C-25 floor concrete column for 3.1.42 fourth floor column 2 days 2 days 3 days 3 days 2 days 3 days 3 days 2 days 3 days 2 days 2 days 3 days 3 days 2 days 3 days 3 days 2 days 3 days 2 days 2 days 3 days 3 days 2 days 6/3/2023 6/3/2023 6/11/2023 6/11/2023 6/13/2023 6/13/2023 6/13/2023 6/15/2023 6/19/2023 6/23/2023 6/25/2023 6/27/2023 6/27/2023 6/27/2023 6/29/2023 6/29/2023 7/1/2023 7/5/2023 7/9/2023 7/11/2023 7/13/2023 7/13/2023 7/13/2023 3/12 3/19 6/4/2023 6/4/2023 6/13/2023 6/13/2023 6/14/2023 6/15/2023 6/15/2023 6/17/2023 6/22/2023 6/25/2023 6/26/2023 6/29/2023 6/29/2023 6/28/2023 7/1/2023 7/1/2023 7/3/2023 7/8/2023 7/11/2023 7/12/2023 7/15/2023 7/15/2023 7/14/2023 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 3 3/26 April 4/2 4/9 4/16 4/23 ID Task Mode 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 Task Name Duration Start Finish March 3/5 3.1.43 Reinforcemnet bar forForm fifth floor 3.1.44 workslab for fifth floor slab 3.1.45 C-25 concrete for fifth floor slab 3.1.46 Reinforcemnet bar forForm fifth floor 3.1.47 workbeam for fourth C-25 fifth beam 3.1.48 concrete for fifth floor beam 3.1.49 Reinforcemnet bar forForm fifth floor 3.1.50 work for fifth floor column 3.1.51 C-25 concrete for column 3.2fifth HCBfloor works 3 days 3 days 2 days 3 days 2 days 2 days 3 days 3 days 2 days 131 days 3.2.1 Ground floor HCB 10 days wall andHCB wall 10 days 3.2.2internal First floor internal and external 3.2.3 Second floor HCB 10 days wall internal andHCB 3.2.4 Third floor 10 days wall internal and HCB 10 days 3.2.5 Fourth floor wall internal andHCB 3.2.6 Fifth floor 10 days wall internal and 3.3 Roof Work 7 days 3.3.1 Fixing Roof cover 7 days finishingand on roof 3.4and carpentary joinary 20 days 3.4.1 Fixing Gypsum 20 days ceiling board and 3.5 Metal work 20 days 3.5.1 Doors and 20 days 3.6windows Finishingmade Workof 30 days Project: 5 star construction P.L.. Date: 7/5/2023 7/17/2023 7/19/2023 7/21/2023 7/23/2023 7/25/2023 7/27/2023 7/29/2023 7/29/2023 7/29/2023 4/17/2023 4/17/2023 5/2/2023 5/27/2023 6/17/2023 7/23/2023 7/23/2023 7/30/2023 7/30/2023 7/21/2023 7/21/2023 7/21/2023 7/21/2023 7/21/2023 3/12 3/19 7/19/2023 7/21/2023 7/23/2023 7/25/2023 7/27/2023 7/28/2023 7/31/2023 7/31/2023 7/30/2023 7/31/2023 4/25/2023 5/10/2023 6/4/2023 6/25/2023 7/31/2023 7/31/2023 8/5/2023 8/5/2023 8/6/2023 8/6/2023 8/6/2023 8/6/2023 8/14/2023 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 4 3/26 April 4/2 4/9 4/16 4/23 ID Task Mode 92 93 94 95 96 97 98 99 100 101 102 103 Task Name Duration Start Finish March 3/5 3.6.1 Apply three coats 30 days plaster with cement 30 days 3.7ofGlazing 3.7.1 4mm thick Tinted 30 days glazed toCladding windows 20 days 3.8Glass Painting and 3.8.1 Apply three coats 20 days approvedinstallation type plastic 25 days 3.9ofElectrical 3.9.1 SUPLLY AND 25 days INSTALL 3.10 Sanitary installation 30 days work 3.10.1 supply and install 30 days all Correction sanitary equipments 3.11 works and 15 days checking of defects and 10 days 3.11.1 checking proper installation all over 5 days 3.11.2 Final of hand Project: 5 star construction P.L.. Date: 7/5/2023 7/21/2023 7/21/2023 7/21/2023 7/21/2023 7/21/2023 7/21/2023 7/21/2023 7/21/2023 7/21/2023 8/14/2023 8/14/2023 8/22/2023 3/12 3/19 8/14/2023 8/14/2023 8/14/2023 8/6/2023 8/6/2023 8/10/2023 8/10/2023 8/14/2023 8/14/2023 8/26/2023 8/22/2023 8/26/2023 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 5 3/26 April 4/2 4/9 4/16 4/23 4/23 May 4/30 5/7 5/14 Project: 5 star construction P.L.. Date: 7/5/2023 5/21 June 5/28 July 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 August 7/30 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 6 8/6 8/13 8/20 8/27 September 9/3 4/23 May 4/30 5/7 5/14 Project: 5 star construction P.L.. Date: 7/5/2023 5/21 June 5/28 July 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 August 7/30 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 7 8/6 8/13 8/20 8/27 September 9/3 4/23 May 4/30 5/7 5/14 Project: 5 star construction P.L.. Date: 7/5/2023 5/21 June 5/28 July 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 August 7/30 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 8 8/6 8/13 8/20 8/27 September 9/3 4/23 May 4/30 5/7 5/14 Project: 5 star construction P.L.. Date: 7/5/2023 5/21 June 5/28 July 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 August 7/30 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 9 8/6 8/13 8/20 8/27 September 9/3 4/23 May 4/30 5/7 5/14 Project: 5 star construction P.L.. Date: 7/5/2023 5/21 June 5/28 July 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 August 7/30 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 10 8/6 8/13 8/20 8/27 September 9/3 Annex part A Direct cost and cost break down from City government of Addis Ababa Design and Construction Works Bureau Cost Break down Analyis B+G+4 Oiffce Buliding FIVE STAR GROUP 1.EXCAVATION AND EARTH WORK. ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS PROJECT: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: WORK ITEM: ( 1.2 ) TOTAL QANTITY OF WORK ITEM: 20cm. Clearing on wet & black soil. EQUIPEMENT: Tool RESULT: 58.48 m2 1 Labour Cost (1:02) Material Cost (1:01) Type of Material Unit Qty * Rate Total (1:-01) Birr/m Cost per Unit 0 0 0 0 0 0 0 0 0 0 Labour by Grade DL G.Chief Foreman No. 2 1 1 UF 1.00 0.10 0.10 B= Manpower Unit Cost 47.58 Total of (1:02) Hourly Output: Direct Cost of Work Item = A+B+C = Over head cost : Profit Cost: Total Unit Cost : Remark _____________________________________________________________________________ UF: UTILIZATION FACTOR *: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC. **: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT. A= Materials Unit Cost 7/3/2023 0 1 m2/hr. Birr/m2 Equipment Cost (1:03) ** Indexed Hourly Cost 25.00 50.00 43.75 Hourly Cost 50.00 5.10 4.38 0.00 0.00 0.00 0.00 59.48 Total (1:02) 2 1.25 Birr/m 2 Type of Equipment Tools Hourly Rental 3.00 Hourly Cost 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.00 Total (1:03) C= Equipment Unit Cost 10% 7% No. 1.00 2.40 Total of (1:03) Hourly output: _______________ Birr/m2 49.98 5.00 " 3.50 " Birr/m2 58.48 Birr/m2 Cost Break down Analyis B+G+4 Oiffce Buliding FIVE STAR GROUP ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS PROJECT: WORK ITEM: ( 1.12) TOTAL QANTITY OF WORK ITEM: EXCAVATION AND EARTH WORK. LABOUR HOURLY OUTPUT: Pit& Trench Excavation in hard rock Over 1.5m,not exceeding 3m EQUIPEMENT: Tool RESULT: 229.10 1 m3 Material Cost (1:01) Type of Material Qty * Total (1:-01) Rate Cost per Unit Labour by Grade DL Forman G.Chief 0 No. 2 1 1 UF 1.00 0.22 0.10 7/3/2023 0 ** Indexed Hourly Cost 25.00 43.75 50.00 Total (1:02) Birr/m3 B= Manpower Unit Cost 184.384821 Total of (1:02) Hourly Output: Direct Cost of Work Item = A+B+C = Over head cost : Profit Cost: Total Unit Cost : Remark _____________________________________________________________________________ UF: UTILIZATION FACTOR *: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC. **: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT. A= Materials Unit Cost 2 m3/hr. Birr/m3 Equipment Cost (1:03) Labour Cost (1:02) Unit 0.35 Birr/m3 Hourly Cost 50.00 9.57 4.96 0.00 Type of Equipment Tools sledge hammer 64.53 Total (1:03) Hourly Rental 1.00 2.00 Hourly Cost 2.00 2.00 0.00 0.00 4.00 Birr/m3 11.43 Total of (1:03) Hourly output: _______________ Birr/m3 195.81 19.58 " 13.71 " Birr/m3 229.10 C= Equipment Unit Cost 10% 7% No. 2.00 1.00 Cost Break down Analyis B+G+4 Oiffce Buliding FIVE STAR GROUP 2. CONCRETE WORK ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS PROJECT: CONCRETE WORK WORK ITEM: ( 3.1 ) C-5 Lean Concrete (Hand mix) (C-5) TOTAL QUANTITY OF WORK ITEM: m2 1 0.05 Material Cost (1:01) Labour (1:02) Type of Material Cement (ppc) Sand Gravel (02) Water Unit Qnt. m3 m3 m3 Qty * 1.58 0.50 0.76 0.30 Rate 1033.00 1416.71 1424.38 105.00 Total (1:-01) LABOUR HOURLY OUTPUT: EQUIPEMENT: RESULT: 360.17 m. thick Cost per Unit 1626.98 714.02 1076.83 31.50 Labour by Trade Forman Mason DL G.CHIEF 3449.33 Total (1:02) 7/3/2023 172.47 Br./m2 3 m2/hr. Birr/m2 Equipment Cost (1:03) No. 1.00 1.00 6.00 1.00 UF 0.50 1.00 1.00 1.00 B=Manpower Unit Cost 109.71 Total of (1:02) Hourly Output Direct Cost of work item= A+B+C= Overhead Cost: Profit Cost: Total Unit Cost : Remark ________________________________________________________ UF: UTILIZATION FACTOR *: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC. **: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT. A= Materials Unit Cost 2.82 ** Indexed Hourly Cost 43.75 87.50 25.00 50.00 Hourly Cost 21.88 87.50 150.00 50.00 Type of Equipment Tools mixer 309.38 Total (1:03) Br./m2 No. 5.00 1.00 Hourly Cost 15.00 57.37 72.37 2 25.66 Br./m Total of (1:03) Hourly output: __________________ Birr/m2 307.84 30.78 " 21.55 " Birr/m2 360.17 C=Equipment Unit Cost 10% 7% Hourly Rental 3.00 57.37 FIVE STAR GROUP 1.Labur Cost No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 25 25 26 27 28 28 29 Laborer by Trade Bar bender Ass. Bar bender Carpenter Ass. Carpenter Chisler DL Electrician helper Electrician Forman Gang chief Glazer Mason Ass. Mason Mixer operter Painter Assistance Painter Plasterer Ass. Plasterer Plumber helper Plumber Tiller Ass. Tiller Time Keeper Truck Driver Equpment operator I Equpment operator II Equpment operatorIII vibrator operator L. Vehicle Driver I Surveyer Welder Welder Ass. 200.00 300.00 180-220 350.00 280.00 200.00 200-250 350-400 350.00 400.00 320-350 260.00 500.00 280.00 250.00 350.00 200-260 500.00 260.00 300.00 280.00 450-500 120.00 333.33 220.00 220.00 220.00 250.00 166.67 403.85 375.00 225.00 Hourly Rental (In birr) 35.00 52.50 35.00 61.25 49.00 25.00 39.38 65.63 43.75 50.00 58.63 45.50 87.50 49.00 43.75 61.25 40.25 87.50 45.50 52.50 49.00 83.13 21.00 58.33 38.50 38.50 38.50 43.75 29.17 70.67 65.63 39.38 B+G+G Office Building FIVE STAR GROUP B+G+G Office Building 2.Equipment Cost RENTAL COST/ day & hr 1 2 3 4 5 6 C. Mashinery cost Truck Truck compactor Dumper Mixer Truck Mixer 7 8 9 Vibrator Grinder scafolding 1,500.00 6.00 50.00 10 sledge hammer 11 Tools 12 Crane 3.Over head and profit cost(%) 13 OVER HAED COST 14 PROFIT 15 Labour out put index 10.00 3.00 3,000.00 CAPACITY(m3 ) 14 7 5 -tone 200.00 140.00 600.00 2,000.00 312.50 7,000.00 FUEL CONSUMSION 30.00 1.00 21.00 1.00 5.00 8.00 5.00 1.00 8.96 8.00 30.00 8.00 4.80 20.00 690.50 483.35 85.22 2,081.75 57.37 936.31 8.00 1.00 1.00 198.76 6.00 50.00 1.00 1.00 1.00 10.00 3.00 3,327.00 10% 7% 1.00 FIVE STAR GROUP B+G+4 Office Building 1.LOCAL MATERIALLIST NO Type of Materials Unit Source Place Material cost at Source Sand wash cost per m3 Distance from site (Round Trip) Speed /KM Rental Cost Fuel Consumtion Transportation Cost From source to site (Birr Per Unit) Total cost 1 2 3 4 5 6 LOCAL MATERIALS Sand Gravel (02) Stone (Basaltic) Stone (Trachitec) Selected Material Water m3 m3 m3 m3 m3 m3 1,409.57 1,360.87 478.26 369.57 191.30 105.00 0 40 80 80 30 0 35.00 35.00 35.00 35.00 35.00 35.00 100.00 328.57 390.00 390.00 190.00 0.00 560.57 784.80 784.80 294.30 0.00 7.14 63.51 167.83 167.83 69.19 0.00 1,416.71 1,424.38 646.09 537.39 260.49 105.00 7 8 9 10 Red Ash Eucalyptys Dia.12cm Eucalyptys Dia.10cm Eucalyptys Dia.8cm m3 pcs pcs pcs 468.75 150.00 150.00 125.00 30 40 40 40 35.00 35.00 35.00 35.00 190.00 230.00 230.00 230.00 420.43 560.57 560.57 560.57 43.60 1.98 1.98 1.98 512.35 37.99 25.33 21.16 11 Strut 0.60 mm pcs 90.00 40 35.00 230.00 560.57 1.98 15.33 12 13 Diesel Benzin(Regular) Lit. Lit. A.A. A.A. 16.35 18.77 FIVE STAR GROUP 1.MATERIAL LIST 1 Project site 2 Distance from Addis in km 3 Distance from cement factory km 4 Number of trips for cement 5 Number of trips for construction matrials NO Type of Materials B+G+4 Office Building ADAMA 105.00 145.00 1.00 1.00 1.1 Unit Source Place Lit. A.A. Material cost at Source Distance from site (Round Trip) Loading /Unloading costs Unit Weight Transportation Cost Transportati From source to site on Cost (Birr Per Unit) Total cost MATERIALS 1 Diesel 16.35 2 Benzin(Regular) Lit. A.A. 18.77 3 Cement (PPC Mugar) Qts Gindabert 980.00 250 3.00 1.00 0.20 4 Cement (OPC Mugar) Qts Gindabert 1,020.00 250 3.00 1.00 0.20 5 Rein.Bar dia.6-10mm kg Addis Ababa 40.87 105 0.03 1.00 0.0025 6 Rein.Bar dia 12-32mm kg Addis Ababa 39.13 105 0.03 1.00 0.0025 0.2625 39.42 7 1.5mm black wire (For rebar) kg Addis Ababa 40.00 105 0.03 1.00 0.0025 0.2625 40.29 8 2.5 mm black wire (For Carpentry) kg Addis Ababa 56.52 105 0.03 1.00 0.0025 0.2625 56.81 9 Steel panel sub structure (Rental Cost) m2 Addis Ababa 33.00 105 0.03 6.54 0.0025 0.2625 34.91 10 Steel panel Super structure (Rental Cost) m2 Addis Ababa 33.00 105 0.03 6.54 0.0025 0.2625 39.86 50 1,033.00 50 1,073.00 0.2625 41.16 Size /m2 Annex part B Detail project Drawing 1750 2Ø16 L=3150 1900 1250 1900 3Ø16 L=9950 Ø8/100 Ø8/150 4 3 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 5 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 5700 6 450 450 SW12 4Ø16 L=10100 4Ø16 L=6150 Ø8/100 Ø8/150 450 450 450 2Ø16 L=3150 1900 2Ø16 L=3150 1900 1250 1900 2Ø16 L=3750 2400 1350 4 Ø8/150 10 Ø8/100 2Ø16 L=3600 2400 1200 Ø8/100 2Ø16 L=2750 2300 3Ø16 L=10100 8550 11450 4Ø16 L=5850 4Ø16 L=7700 4Ø16 L=7700 7700 4Ø16 L=10650 7700 7700 Ø8/100 2Ø16 L=3250 1200 2050 3Ø16 L=11450 10000 Ø8/150 10200 5 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 SW12 6 Ø8/100 Ø8/150 3' 8 2Ø16 L=2450 1100 Ø8/100 Ø8/150 9 2Ø16 L=3500 1100 2400 Ø8/100 Ø8/150 10 Ø8/100 2Ø16 L=3600 2400 1200 Ø8/100 9 Ø8/100 2Ø16 L=2750 2300 3Ø16 L=10100 8550 4Ø16 L=10650 7700 7700 Ø8/150 2Ø16 L=3250 1200 2050 4Ø16 L=7700 4Ø16 L=7700 GB-6 8 Ø8/100 11450 7700 Ø8/100 Ø8/100 10200 10 2Ø16 L=3400 1250 1500 450 Ø8/100 Ø8/150 Ø8/100 2Ø16 L=2850 2150 2400 3Ø16 L=11430 450 4Ø16 L=8300 Ø8/100 2Ø16 L=1950 450 7400 Ø8/150 450 450 4Ø16 L=6800 6900 7400 10530 4Ø16 L=11430 10530 6350 GB-5 GB-2 Ø8/100 3Ø16 L=11450 4Ø16 L=5850 450 4Ø16 L=7350 450 5300 Ø8/150 (250X500) Ø8/150 450 1350 3Ø16 L=5750 8250 1350 Ø8/100 10000 4Ø16 L=8300 2Ø16 L=1800 1250 3Ø16 L=8700 Ø8/100 3Ø16 L=10000 8 Ø8/100 Ø8/100 450 2150 Ø8/150 450 2Ø16 L=5800 2400 2Ø16 L=2850 2400 Ø8/100 Ø8/150 2Ø16 L=3750 1350 2400 9500 GB-4 7 Ø8/100 Ø8/100 3Ø16 L=7100 (250X500) Ø8/100 Ø8/100 2Ø16 L=3150 1900 450 450 450 2' Ø8/150 7 6' (250X500) 9650 (250X500) 450 2Ø16 L=3500 1100 2400 Ø8/100 429 429 Ø8/100 4Ø16 L=10100 450 9 Ø8/100 429 Ø8/100 450 450 Ø8/150 GB-3 450 2Ø16 L=2450 1100 Ø8/150 3Ø16 L=10000 9500 5850 4 8 Ø8/100 450 3 Ø8/100 5700 Ø8/100 Ø8/100 450 2 Ø8/100 4Ø16 L=6150 1 Ø8/150 2Ø16 L=1800 1350 2Ø16 L=3050 1250 1800 (250X500) Ø8/150 1350 Ø8/100 450 GB-2 Ø8/100 Ø8/100 3Ø16 L=9950 9450 1 Ø8/150 450 450 450 1750 3Ø16 L=9900 Ø8/100 450 2Ø16 L=3650 2000 Ø8/100 3Ø16 L=7100 5850 2Ø16 L=2450 GB-2 7 6' (250X500) 9650 429 2 (250X500) 429 GB-1 429 9450 1 2Ø16 L=1800 1350 2Ø16 L=3050 1250 1800 3Ø16 L=9900 450 450 450 2000 450 2Ø16 L=3650 2Ø16 L=2450 5 7 6 8 9 10 (250X500) A Ø8/100 Ø8/100 Ø8/100 Ø8/100 2Ø16 L=2850 Ø8/150 Ø8/100 2650 Ø8/100 CLIENT NOTES 2Ø16 L=1750 1300 4Ø16 L=11900 11000 11000 Ø8/100 GB-11 4Ø16 L=11900 Ø8/150 Ø8/100 5048 4Ø16 L=7350 4Ø16 L=6800 450 K Ø8/100 Ø8/150 Ø8/100 L Ø8/100 Ø8/150 Ø8/100 G Ø8/100 Ø8/150 2286 Ø8/100 2048 2095 3Ø16 L=8550 3Ø16 L=7850 7714 7048 4Ø16 L=7350 4Ø16 L=9050 6571 450 3Ø16 L=9550 D F 450 1400 5870 4Ø16 L=8850 7750 E' 2Ø16 L=1850 1 Ø8/100 J K L Ø8/100 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 G Ø8/100 Ø8/100 Ø8/150 Ø8/150 Ø8/100 2286 Ø8/100 Ø8/100 Ø8/100 2Ø16 L=6143 2286 2Ø16 L=2850 7570 2048 450 4Ø16 L=8850 7610 8050 D E' F 1500 6170 4Ø16 L=7750 4Ø16 L=8050 7650 GB-14 2Ø16 L=1950 7057 4Ø16 L=9060 Ø8/100 K L G Ø8/150 2Ø16 L=2400 1200 1200 Ø8/100 Ø8/100 Ø8/150 Ø8/100 2Ø16 L=2650 1200 1450 3Ø16 L=7865 1700 6700 I 7440 2Ø20 L=2286 1143 1143 H G I 1095 Ø8/100 1524 No. 2Ø16 L=2250 1714 DATE. 3Ø16 L=7500 6714 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 2Ø20 L=2286 1143 1143 CGCOC GROUP CO., LTD I Ø8/100 Ø8/150 PROJECT: Adama Town water Supply & Sanitation Improvement Project Ø8/100 2Ø20 L=2762 1143 1619 2Ø16 L=2400 1857 3Ø16 L=8005 8048 7195 4Ø16 L=6950 INITIAL. REVISION.No CONTRACTOR: 8286 H G 3Ø16 L=8900 E 4Ø16 L=9655 DRAWING TITLE: OFFICE BUILDING 8767 F H G Scale: Designed: I (250X500) GB-6 @LEVEL +0.00 &1.62 (250X500) 2Ø16 L=2050 Ø8/100 4Ø16 L=9150 2Ø20 L=2000 1143 857 429 F Ø8/150 2Ø20 L=2619 1143 1476 6190 GB-5 @LEVEL +0.00 & 1.62 Ø8/100 7724 Ø8/100 Ø8/100 2Ø16 L=1600 8400 E Ø8/100 (250X500) 429 429 4Ø16 L=8850 Ø8/150 9581 3Ø16 L=7150 7865 4Ø16 L=7440 Ø8/100 4Ø16 L=8560 GB-7 @LEVEL +0.00 &+1.62 F 2Ø16 L=2150 Ø8/100 2Ø20 L=2429 1286 1143 429 Ø8/100 Ø8/150 Ø8/100 Ø8/100 2Ø20 L=2429 1143 1286 3Ø16 L=10510 9581 4Ø16 L=8560 7724 Ø8/150 Ø8/100 Ø8/100 2Ø20 L=2286 1143 1143 Ø8/150 Ø8/100 Ø8/100 Ø8/150 2Ø20 L=2714 1143 1571 Ø8/100 Ø8/100 2Ø16 L=2350 1810 2Ø16 L=2050 429 8045 Ø8/100 2Ø16 L=2350 1150 1200 8680 4Ø16 L=8045 Ø8/150 3Ø16 L=7865 7062 4Ø16 L=9515 8633 429 429 Ø8/100 429 450 450 Ø8/100 3Ø16 L=8680 9100 7655 Ø8/150 429 2Ø16 L=2800 1650 1150 1250 3Ø16 L=9550 4Ø16 L=8105 Ø8/100 429 2Ø16 L=6275 2625 Ø8/100 Ø8/150 3Ø16 L=10510 450 2400 Ø8/150 H G Ø8/100 Ø8/100 1524 450 2650 Ø8/100 450 450 2Ø16 L=3100 Ø8/100 429 429 Ø8/100 Ø8/150 2Ø16 L=2050 7870 J 429 Ø8/150 8200 F (250X500) (250X500) Ø8/100 GB-4 @LEVEL +0.00 &+1.62 2095 3Ø16 L=7860 4Ø16 L=7360 E Ø8/100 3Ø16 L=7150 7950 8800 4Ø16 L=8100 A 3Ø16 L=7950 3Ø16 L=8800 9100 2Ø16 L=2450 1200 1250 429 429 450 3Ø16 L=9550 2Ø16 L=2400 1200 1200 450 1250 2Ø16 L=2450 1250 1200 450 2400 2Ø16 L=2900 1650 1250 450 450 2650 2Ø16 L=6280 2630 Ø8/150 1809 7724 6581 2Ø16 L=3100 NOTES: 2Ø16 L=2650 3Ø16 L=8560 429 Ø8/150 4 3' (250X500) (250X500) Ø8/100 2' APRD BY REVIEWED BY 8190 GB-3 @LEVEL +0.00 &+1.62 3Ø16 L=7150 4Ø16 L=7750 8050 GB-13 2Ø16 L=2350 1200 1150 8020 8690 4Ø16 L=8050 7650 2Ø16 L=2400 1200 1200 3Ø16 L=8020 3Ø16 L=8690 9100 4Ø16 L=8100 A 2Ø16 L=2450 1250 1200 429 429 2Ø16 L=2900 1650 1250 1250 450 2400 450 450 2650 450 2Ø16 L=6280 2630 2Ø16 L=3100 MS CONSULTANCY 2Ø16 L=2650 1809 429 Ø8/100 2Ø16 L=6143 2286 2Ø16 L=2850 J Ø8/150 CONSULTANT APPROVAL Ø8/100 429 450 7625 Ø8/100 Ø8/100 Ø8/150 429 Ø8/150 Ø8/100 Ø8/100 429 Ø8/100 Ø8/100 429 4Ø16 L=8525 F Ø8/100 Ø8/150 429 Ø8/100 4 3' 429 E' Ø8/100 429 Ø8/150 2' (250X500) (250X500) Ø8/100 6048 GB-2 @LEVEL +0.00 &+1.62 429 D 1 450 7625 8050 GB-12 A 450 4Ø16 L=8500 7650 2650 3Ø16 L=8525 429 429 4Ø16 L=8100 2Ø16 L=3100 2650 450 450 6900 2Ø16 L=3100 450 3Ø16 L=7350 9100 450 450 3Ø16 L=9550 450 450 1550 NOTES: 429 Ø8/100 Ø8/100 2Ø16 L=1800 1250 450 2Ø16 L=6280 2630 2400 1286 3Ø16 L=5750 7857 429 Ø8/150 2Ø16 L=1800 1190 3Ø16 L=8700 6571 2650 Ø8/100 429 Ø8/100 2048 Ø8/150 429 Ø8/100 2286 Ø8/100 2Ø16 L=5524 2286 2Ø16 L=2850 D 429 Ø8/100 Ø8/100 1524 Ø8/150 Ø8/100 Ø8/100 2Ø20 L=2429 1143 1286 3Ø16 L=10510 9581 4Ø16 L=8560 7724 Ø8/150 Ø8/100 Ø8/100 2Ø20 L=2286 1143 1143 Ø8/150 Ø8/100 Ø8/100 Ø8/150 2Ø20 L=2762 1143 1619 Drawn: Ø8/100 2Ø16 L=2400 1857 429 A Ø8/100 3Ø16 L=8005 7195 4Ø16 L=9655 8767 429 F Ø8/150 429 E' (250X500) 2Ø16 L=3100 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 3' 3Ø16 L=11900 (250X500) Ø8/150 2' (250X500) 429 D GB-1 @LEVEL +0.00 &+1.62 1 11000 GB-10 Ø8/100 Ø8/150 2Ø16 L=3600 2400 1200 2Ø16 L=3100 10565 A E Ø8/100 429 4Ø16 L=11465 D Ø8/100 11000 450 10565 2400 4Ø16 L=11050 GB-9 Ø8/100 450 450 450 3Ø16 L=11465 450 450 Ø8/150 4Ø16 L=11900 2400 450 450 2150 Ø8/100 450 2Ø16 L=3400 1250 1500 Ø8/150 2Ø16 L=2800 8950 (250X500) 450 Ø8/100 Ø8/100 3Ø16 L=9400 450 450 Ø8/100 2Ø16 L=3350 1200 2150 7700 E Ø8/150 429 450 Ø8/150 Ø8/100 4Ø16 L=7700 D C (250X500) 2Ø16 L=1950 450 B Ø8/100 2Ø16 L=3600 2400 1200 7700 GB-8 A 10 Ø8/150 6200 4Ø16 L=7700 9 Ø8/100 3Ø16 L=6200 8000 7700 5850 Ø8/100 3Ø16 L=8000 4Ø16 L=7700 4Ø16 L=6300 Ø8/150 2Ø16 L=4800 2400 2400 8000 (250X500) Ø8/100 Ø8/100 3Ø16 L=8000 9650 GB-7 Ø8/100 2Ø16 L=4800 2400 2400 3Ø16 L=10100 8 Ø8/150 429 429 2150 Ø8/100 450 450 Ø8/100 450 Ø8/150 2Ø16 L=4200 1800 2400 2Ø16 L=2450 450 450 Ø8/100 450 Ø8/100 450 Ø8/150 450 Ø8/100 Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × FFB-1 @LEVEL ±5.22 2 4 3 5 6 FFB-1 @LEVEL ±5.22 7 6' Ø8/100 Ø8/100 Ø8/100 3Ø20 L=3649 2000 1749 Ø8/100 Ø8/150 3Ø20 L=3149 1899 1250 1899 Ø8/100 Ø8/150 Ø8/100 3Ø20 L=3049 1250 1799 2Ø20 L=10100 Ø8/100 9 Ø8/100 3Ø20 L=3499 2399 1100 Ø8/100 Ø8/150 10 Ø8/100 3Ø20 L=3599 2399 1200 Ø8/100 6 3Ø20 L=2750 2299 2Ø20 L=10100 8546 5Ø20 L=7700 4Ø20 L=10650 7697 10196 7 6' Ø8/100 3Ø20 L=3249 1200 2049 11446 7697 Ø8/150 Ø8/100 3Ø20 L=3649 1749 Ø8/100 Ø8/150 3Ø20 L=3149 1899 1250 1899 Ø8/100 Ø8/150 Ø8/100 3Ø20 L=3049 1250 1799 2Ø20 L=10100 Ø8/100 2' 3' 8 450 4Ø20 L=6800 6897 Ø8/100 450 7397 4Ø20 L=8300 7397 450 450 450 5298 4Ø20 L=7350 Ø8/100 9 Ø8/150 Ø8/100 Ø8/150 10 Ø8/100 3Ø20 L=3599 2399 1200 Ø8/100 Ø8/150 Ø8/100 3Ø20 L=3299 1200 2099 3Ø20 L=2800 2349 8746 4Ø20 L=10850 2Ø20 L=9200 5Ø20 L=7700 7697 9 10396 10 Ø8/100 Ø8/100 3Ø20 L=3399 1250 1499 Ø8/150 Ø8/100 3Ø20 L=2850 2399 2149 2Ø20 L=11430 10526 4Ø20 L=11430 10526 6348 FFB-5 @LEVEL ±5.22 Ø8/100 3Ø20 L=3499 1100 2399 7697 3Ø20 L=1950 450 1350 2Ø20 L=5750 8247 Ø8/150 (250X500) Ø8/150 4Ø20 L=8300 3Ø20 L=1800 1250 2Ø20 L=8700 3Ø20 L=2449 1100 Ø8/100 4Ø20 L=7700 FFB-6 @LEVEL ±5.22 8 8 Ø8/100 Ø8/100 Ø8/100 11446 7697 450 2149 Ø8/150 450 3Ø20 L=5798 2399 3Ø20 L=2850 2399 Ø8/100 Ø8/150 2Ø20 L=11450 5Ø20 L=7700 FFB-4 @LEVEL ±5.22 7 Ø8/100 450 Ø8/100 450 Ø8/150 1350 Ø8/100 9996 (250X500) Ø8/100 Ø8/100 2Ø20 L=10000 5848 (250X500) Ø8/150 3Ø20 L=3749 2399 1350 4Ø20 L=5850 9796 FFB-3 @LEVEL ±5.22 Ø8/100 7097 4Ø20 L=9800 5698 Ø8/100 2Ø20 L=7100 9946 4Ø20 L=6150 Ø8/150 3Ø20 L=4198 1799 2399 2Ø20 L=9950 8672 450 Ø8/100 450 450 Ø8/150 450 Ø8/100 450 Ø8/100 2000 450 450 Ø8/150 450 Ø8/150 3Ø20 L=2450 450 3Ø20 L=2449 1100 Ø8/100 (250X500) Ø8/100 4 Ø8/100 4Ø20 L=7700 FFB-2 @LEVEL ±5.47 5 Ø8/150 2Ø20 L=11450 7697 (250X500) 1 1350 Ø8/100 9996 5Ø20 L=7700 4 3 Ø8/100 2Ø20 L=10000 5848 2 Ø8/150 3Ø20 L=3749 2399 1350 4Ø20 L=5850 9796 FFB-2 @LEVEL ±5.22 Ø8/100 7097 4Ø20 L=9800 5698 Ø8/100 2Ø20 L=7100 9946 4Ø20 L=6150 Ø8/150 3Ø20 L=4198 2399 1799 2Ø20 L=9950 8672 450 Ø8/100 450 450 450 450 Ø8/150 450 450 Ø8/150 3Ø20 L=2450 1 8 (250X500) Ø8/100 450 (250X500) 450 1 5 7 6 8 9 10 (250X500) A Ø8/100 Ø8/100 3Ø20 L=2850 Ø8/150 4Ø20 L=11465 D Ø8/100 Ø8/150 Ø8/100 2649 4Ø20 L=11900 Ø8/100 3Ø20 L=1750 1300 10996 10996 4Ø20 L=11900 10996 D E' F A (250X500) FFB-11 @LEVEL ±5.22 D (250X500) 7647 2Ø20 L=8525 7622 4Ø20 L=8525 D E' F J Ø8/100 L G 3Ø20 L=6278 2629 3Ø20 L=3100 2399 2649 Ø8/150 Ø8/100 Ø8/100 Ø8/150 3Ø20 L=2899 1649 1250 1250 2Ø20 L=9550 Ø8/100 Ø8/100 3Ø20 L=2449 1250 1200 Ø8/100 Ø8/100 Ø8/150 3Ø20 L=2399 1200 1200 Ø8/100 Ø8/100 Ø8/100 Ø8/100 Ø8/100 3Ø20 L=1850 1400 2Ø16 L=6316 2613 Ø8/150 Ø8/100 2Ø16 L=1800 1470 1361 3Ø16 L=8700 8984 3Ø16 L=5750 5771 4Ø16 L=7350 7514 4Ø16 L=6800 6915 CONSULTANT APPROVAL MS CONSULTANCY 2Ø20 L=7150 8017 8687 Ø8/150 3Ø20 L=2349 1200 1150 2Ø20 L=8020 2Ø20 L=8690 9097 Ø8/150 490 Ø8/100 Ø8/100 2341 490 Ø8/100 Ø8/150 2Ø16 L=2850 2613 450 Ø8/100 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 3' NOTES: K 5868 450 Ø8/150 2' (250X500) (250X500) Ø8/100 FFB-1' 7622 8047 A FFB-12 @LEVEL ±5.22 1 490 6897 4Ø20 L=8500 2650 490 9097 4Ø20 L=8100 3Ø20 L=3100 450 1550 2Ø20 L=7350 CLIENT NOTES Ø8/100 2650 450 1250 2Ø20 L=9550 Ø8/150 3Ø20 L=3100 450 Ø8/100 Ø8/100 3Ø20 L=1800 450 441 441 Ø8/150 450 2399 2649 Ø8/100 450 Ø8/100 3Ø20 L=6278 2629 450 Ø8/100 450 Ø8/150 450 Ø8/100 3Ø20 L=3100 441 441 Ø8/150 2Ø20 L=11900 10561 A FFB-10 @LEVEL ±5.22 E Ø8/100 3Ø20 L=3599 2399 1200 3Ø20 L=3100 10996 450 10561 4Ø20 L=11050 FFB-9 @LEVEL ±5.22 Ø8/100 450 450 450 450 450 2Ø20 L=11465 441 Ø8/100 4Ø20 L=11900 2399 2149 441 441 441 1499 2399 8947 (250X500) Ø8/100 Ø8/100 450 3Ø20 L=3399 1250 3Ø20 L=1950 Ø8/150 450 Ø8/100 3Ø20 L=2800 2Ø20 L=9400 450 450 Ø8/100 Ø8/100 3Ø20 L=3349 1200 2149 7697 E Ø8/150 490 450 Ø8/150 Ø8/100 5Ø20 L=7700 D C @LEVEL ±5.22 (250X500) Ø8/100 3Ø20 L=3599 2399 1200 7697 B Ø8/150 6198 5Ø20 L=7700 A FFB-8(250X500) 10 Ø8/100 2Ø20 L=6200 7997 7697 9 Ø8/100 2Ø20 L=8000 5Ø20 L=7700 5848 Ø8/150 3Ø20 L=4798 2399 2399 7997 4Ø20 L=6300 Ø8/100 Ø8/100 2Ø20 L=8000 9646 FFB-7 @LEVEL ±5.22 Ø8/100 3Ø20 L=4798 2399 2399 2Ø20 L=10100 8 Ø8/150 450 450 2149 Ø8/100 450 Ø8/100 450 Ø8/150 3Ø20 L=4198 2399 1799 3Ø20 L=2450 450 450 Ø8/100 450 Ø8/100 450 Ø8/150 490 Ø8/100 1 FFB-2' 2' 4 3' 4Ø20 L=8850 E' F Ø8/100 7567 J K L Ø8/100 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 3Ø20 L=2449 1250 1200 E' F 1500 6168 4Ø20 L=8850 7607 8047 D K Ø8/100 L FFB-3' 3Ø16 L=7860 8069 4Ø16 L=9060 9376 F NOTES: H G APRD BY REVIEWED BY 2Ø16 L=2650 2396 2069 4Ø16 L=7360 7525 E I (250X500) 7867 J Ø8/150 3Ø20 L=1950 2Ø20 L=7150 4Ø20 L=7750 4Ø20 L=8050 7647 A FBB-14 @LEVEL ±5.22 3Ø20 L=2449 1200 1250 7947 8797 4Ø20 L=8100 3Ø20 L=2399 1200 1200 2Ø20 L=7950 2Ø20 L=8800 2Ø16 L=7024 2613 2341 490 3Ø20 L=2899 1649 1250 1250 450 3Ø20 L=6278 2629 9097 Ø8/100 Ø8/100 3Ø16 L=8560 8831 450 2399 2Ø20 L=9550 450 2649 441 441 441 3Ø20 L=3100 Ø8/100 2Ø16 L=2850 2613 490 Ø8/150 490 Ø8/100 Ø8/150 G 490 7747 8047 D (250X500) 490 4Ø20 L=8050 7647 A FFB-13 @LEVEL ±5.22 490 4Ø20 L=7750 450 441 (250X500) 4Ø20 L=8100 G Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 (250X500) Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 Ø8/100 Ø8/150 Ø8/100 4Ø20 L=8045 8042 4Ø20 L=7440 7437 490 490 6698 4Ø20 L=8850 2Ø16 L=2050 1742 1470 2Ø20 L=2777 1307 2Ø20 L=2613 1307 1307 2Ø16 L=2250 1960 2Ø20 L=2995 1307 1688 3Ø16 L=10510 10955 3Ø16 L=7500 7677 4Ø16 L=8560 8831 FFB-4' 8397 4Ø16 L=9150 9474 F DATE. Ø8/100 2Ø16 L=1600 1252 INITIAL. REVISION.No CONTRACTOR: H G No. I (250X500) 490 7652 2Ø20 L=7150 7862 8677 1699 490 4Ø20 L=8105 2Ø20 L=7865 2Ø20 L=8680 9097 3Ø20 L=2150 490 450 450 2Ø20 L=9550 3Ø20 L=2649 1200 1450 450 1250 3Ø20 L=2399 1200 1200 450 2399 3Ø20 L=2349 1150 1200 450 450 2649 3Ø20 L=2799 1649 1150 490 Ø8/100 490 Ø8/150 490 Ø8/100 CGCOC GROUP CO., LTD Ø8/100 2Ø20 L=2287 980 1307 3Ø16 L=8900 9201 4Ø16 L=6950 7078 Ø8/150 Ø8/100 Ø8/100 2Ø20 L=2613 1307 1307 Ø8/150 Ø8/100 Ø8/100 2Ø20 L=3158 1307 1851 3Ø16 L=8005 8227 4Ø16 L=9655 10024 Ø8/150 Ø8/100 2Ø16 L=2400 2124 490 Ø8/100 3Ø20 L=6273 2624 490 Ø8/100 490 Ø8/150 490 Ø8/100 3Ø20 L=3100 PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × GB-6 GB-6 GB-6 GB-5 F CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE NOTES: E CONSULTANT APPROVAL MS CONSULTANCY GB-2 D APRD BY REVIEWED BY GB-14 GB-13 GB-12 GB-10 GB-11 NOTES: No. DATE. CONTRACTOR: CGCOC GROUP CO., LTD GB-1 A 5 6 INITIAL. REVISION.No 8 9 10 PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING BRACING BEAM LAYOUT @ LEVEL +3.60 Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 I L H K G J F F CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE E E' NOTES: CONSULTANT APPROVAL D D MS CONSULTANCY C APRD BY REVIEWED BY NOTES: B A A 1 2 2' 3' 3 4 5 6 6' 7 8 9 10 No. DATE. SECOND FLOOR FLAT SLAB BOTTOM REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm INITIAL. REVISION.No CONTRACTOR: Sc. 1:50 LEVEL +8.82 CGCOC GROUP CO., LTD PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 I L H K G J CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE NOTES: F F CONSULTANT APPROVAL MS CONSULTANCY APRD BY REVIEWED BY E E' NOTES: D D C No. DATE. INITIAL. REVISION.No CONTRACTOR: CGCOC GROUP CO., LTD B A A PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING 1 2 2' 3' 3 4 5 6 6' 7 8 9 10 Scale: Designed: THIRD FLOOR FLAT SLAB BOTTOM REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm Sc. 1:50 LEVEL +12.42 Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 1507 1258 892 1200 1200 1200 I 2205 L 1684 1497 2400 2400 2400 1487 1487 1487 1200 1200 1200 H 2709 2709 K 2709 2400 2400 2400 1200 1200 1200 1200 1200 1200 G 2400 2400 J 2400 2400 2400 2400 1200 1200 1200 1200 1200 1200 973 1050 1350 CLIENT NOTES 1164 F 2550 F 2550 1500 1500 1600 1600 1650 1650 1600 1600 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 2325 1125 1310 NOTES: 4750 1535 4600 1535 1350 E 2500 965 1200 1200 1120 1120 E' CONSULTANT APPROVAL MS CONSULTANCY 2404 2405 6680 6680 6680 D 5180 6680 D 5180 APRD BY REVIEWED BY 3508 3508 NOTES: 2550 2400 C 2325 2325 2325 2325 2325 2325 2325 2325 2250 2250 2250 2250 2250 2250 2250 2250 B 2333 A A No. DATE. INITIAL. REVISION.No CONTRACTOR: 1 2 2' THIRD FLOOR FLAT SLAB TOP REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm X-DIRECTION Sc. 1:50 3' 3 4 5 6 6' 7 8 9 10 CGCOC GROUP CO., LTD PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 1051 1162 3400 2116 2000 I 1051 1162 3400 2116 2000 2000 2100 6450 1900 1750 2000 2100 6450 1900 1750 L 1051 1162 3400 2116 2000 H K 2000 2100 6450 1900 1750 1051 1162 3400 2116 2000 G J 2000 2100 6450 1650 2000 F CLIENT NOTES F 1950 1750 4200 2400 4800 2400 2250 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 1800 1050 E 2000 2100 6450 1200 2987 1907 NOTES: 2528 1650 E' 1750 1750 4200 2400 4800 2400 CONSULTANT APPROVAL 2250 MS CONSULTANCY 2200 1650 D D APRD BY REVIEWED BY 7500 1050 1200 1907 NOTES: 2358 2987 3350 1800 1749 1800 1800 1749 1800 1550 C B 1650 1750 4200 2400 4800 2400 4800 2400 3600 1200 2990 1904 2253 A A No. DATE. INITIAL. REVISION.No CONTRACTOR: 1 2 2' FOURTH FLOOR FLAT SLAB TOP REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm Y-DIRECTION Sc. 1:50 3' 3 4 5 6 6' 7 8 9 10 CGCOC GROUP CO., LTD PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 I L H K G J F F CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE E E' NOTES: CONSULTANT APPROVAL D D MS CONSULTANCY C APRD BY REVIEWED BY NOTES: B A A 1 2 2' 3' 3 4 5 6 6' 7 8 9 10 No. DATE. FIVTH FLOOR FLAT SLAB BOTTOM REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm INITIAL. REVISION.No CONTRACTOR: Sc. 1:50 LEVEL +19.62 CGCOC GROUP CO., LTD PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 1507 1258 892 1200 1200 1200 I 2205 L 1684 1497 2400 2400 2400 1487 1487 1487 1200 1200 1200 H 2709 2709 K 2709 2400 2400 2400 1200 1200 1200 1200 1200 1200 G 2400 2400 J 2400 2400 2400 2400 1200 1200 1200 1200 1200 1200 1164 1050 1350 973 F 2550 F 2550 1500 1500 1600 1600 1650 1650 1600 1600 CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 2325 1125 1310 4750 4600 NOTES: 1535 1535 1350 E 2500 965 1200 1200 1120 1120 E' CONSULTANT APPROVAL MS CONSULTANCY 2404 2405 6680 1050 6680 6680 6680 1050 D 5180 D 5180 APRD BY REVIEWED BY 2550 2400 2459 NOTES: C 2325 2325 2325 2325 2325 2325 2325 2325 2250 2250 2250 2250 2250 2250 2250 2250 2033 B 3033 A A No. DATE. INITIAL. REVISION.No CONTRACTOR: 1 2 2' FIVTH FLOOR FLAT SLAB TOP REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm X-DIRECTION Sc. 1:50 3' 3 4 5 6 6' 7 8 9 10 CGCOC GROUP CO., LTD PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × RTB-7 2' 4 3' 5 6 7 6' 3Ø20 L=2950 800 3Ø20 L=2050 800 1250 450 Ø8/150 Ø8/100 Ø8/100 4Ø20 L=9800 RTB-1 8 Ø8/100 Ø8/150 4 Ø8/100 3Ø20 L=3650 2000 1750 Ø8/100 Ø8/150 3Ø20 L=3500 1100 2400 2' Ø8/100 9 Ø8/100 3Ø20 L=3600 2400 1200 4Ø20 L=7700 7700 7700 RTB-6 1 3Ø20 L=3150 1900 1250 1900 2Ø20 L=10100 Ø8/100 3Ø20 L=2850 1350 2400 7000 4Ø20 L=10100 4Ø20 L=6150 Ø8/150 3Ø20 L=1800 2Ø20 L=7450 8675 6150 Ø8/100 450 Ø8/100 450 450 4Ø20 L=8525 Ø8/150 Ø8/100 10 Ø8/100 3Ø20 L=3250 1200 2050 Ø8/150 Ø8/100 3Ø20 L=2750 2300 8950 4Ø20 L=11050 2Ø20 L=9400 10600 3' 5 6 Ø8/100 Ø8/100 Ø8/100 3Ø20 L=5800 2400 2150 Ø8/100 1250 1350 2Ø20 L=5750 8250 5300 4Ø20 L=7350 4Ø20 L=6800 6900 6350 7 6' Ø8/150 3Ø20 L=1800 2Ø20 L=8700 9650 5700 RTB-2 Ø8/150 4Ø20 L=7700 450 450 450 6150 450 2150 2Ø20 L=8525 Ø8/150 3Ø20 L=2450 450 450 2150 450 3Ø20 L=2600 3Ø20 L=2450 1100 Ø8/100 (250X500) Ø8/100 450 3Ø20 L=2600 Ø8/100 11450 7700 3 Ø8/150 2Ø20 L=11450 4Ø20 L=7700 5850 2 1350 Ø8/100 10000 450 Ø8/100 450 Ø8/150 Ø8/100 2Ø20 L=10000 (250X500) Ø8/100 Ø8/150 3Ø20 L=3750 1350 2400 4Ø20 L=5850 RTB-3 1 2' (250X500) Ø8/100 7100 8600 6900 Ø8/100 2Ø20 L=7100 9950 4Ø20 L=6150 Ø8/150 3Ø20 L=4200 1800 2400 2Ø20 L=9950 8675 450 Ø8/100 3Ø20 L=3050 1250 1800 2Ø20 L=10100 4 Ø8/100 450 450 2150 Ø8/150 450 450 450 2400 Ø8/100 Ø8/100 450 Ø8/100 450 Ø8/150 3Ø20 L=2850 1' RTB-7 (250X500) Ø8/100 450 (250X500) 450 1 8 9 10 (250X500) 2050 Ø8/100 1350 Ø8/100 Ø8/150 3Ø20 L=2450 1100 Ø8/100 Ø8/150 7 Ø8/100 Ø8/100 2350 8750 9650 Ø8/150 Ø8/100 Ø8/100 4Ø20 L=8300 3Ø20 L=2800 2Ø20 L=9200 2Ø20 L=10100 450 Ø8/150 7400 4Ø20 L=8300 450 450 2' 1 2400 NOTES: 4Ø20 L=11430 4 3' 450 4Ø20 L=9050 450 7400 3Ø20 L=6450 2400 2150 RTB-12 CONSULTANT APPROVAL MS CONSULTANCY Ø8/100 3Ø20 L=2650 2200 2Ø20 L=7860 8110 7410 4Ø20 L=7360 E Ø8/150 1900 4Ø20 L=9060 6910 D 10 Ø8/100 Ø8/100 450 2400 8600 9 Ø8/100 2Ø20 L=8560 2Ø20 L=7850 4Ø20 L=7350 Ø8/150 3Ø20 L=2850 450 450 450 2200 APRD BY REVIEWED BY 8610 F H G NOTES: I (250X500) Ø8/150 Ø8/100 Ø8/100 3Ø20 L=2850 2150 2400 3Ø20 L=1900 1450 Ø8/150 Ø8/100 Ø8/100 2Ø20 L=2550 1200 1350 10565 450 450 4Ø20 L=11465 Ø8/100 Ø8/100 2Ø20 L=2550 1350 1200 Ø8/150 Ø8/100 Ø8/100 2Ø20 L=2400 1200 1200 2Ø20 L=10510 450 10565 450 2Ø20 L=11465 Ø8/150 8030 Ø8/100 Ø8/100 Ø8/150 2Ø20 L=2750 1200 1550 Ø8/100 3Ø20 L=2250 1800 2Ø20 L=7500 13580 4Ø20 L=8480 Ø8/150 450 3Ø20 L=3400 1250 Ø8/100 450 Ø8/100 450 Ø8/150 7050 4Ø20 L=7700 7700 4Ø20 L=5550 450 (250X500) 450 2' Ø8/100 3Ø20 L=2650 8100 RTB-11 Ø8/100 1900 6900 450 450 Ø8/100 450 3Ø20 L=6450 2400 2Ø20 L=8550 1500 10530 450 2150 Ø8/150 450 450 2400 Ø8/100 Ø8/100 450 Ø8/100 450 Ø8/150 3Ø20 L=2850 3Ø20 L=1950 Ø8/150 3Ø20 L=2850 2150 (250X500) Ø8/100 Ø8/100 Ø8/100 10530 4 3' RTB-10 (250X500) 8 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 450 1 Ø8/100 3Ø20 L=3400 1250 1500 10400 7700 RTB-8 CLIENT NOTES 10 2Ø20 L=11430 7400 4Ø20 L=10850 4Ø20 L=8150 Ø8/150 3Ø20 L=1950 450 Ø8/100 3Ø20 L=3300 1200 2100 450 Ø8/100 9 (250X500) 450 Ø8/150 2300 10200 RTB-9 8 8 450 450 Ø8/100 3Ø20 L=3600 2400 1200 3Ø20 L=2750 4Ø20 L=10650 RTB-5 450 Ø8/100 450 450 Ø8/150 Ø8/100 8550 7700 10 Ø8/150 3Ø20 L=3250 1200 2050 4Ø20 L=7700 7700 450 Ø8/100 Ø8/100 2Ø20 L=10100 (250X500) 2250 Ø8/100 3Ø20 L=3600 2400 1200 4Ø20 L=7700 9 (250X500) 3Ø20 L=2600 Ø8/150 11450 7700 8 Ø8/100 2Ø20 L=11450 4Ø20 L=7700 5850 RTB-4 Ø8/100 3Ø20 L=3500 1100 2400 10000 4Ø20 L=6300 450 Ø8/100 2Ø20 L=10000 9650 450 Ø8/100 3Ø20 L=3750 2400 1350 2Ø20 L=10100 7 Ø8/150 450 450 Ø8/100 450 Ø8/150 3Ø20 L=4200 1800 2400 3Ø20 L=2500 450 450 Ø8/100 450 Ø8/100 450 Ø8/150 450 Ø8/100 5100 No. DATE. INITIAL. REVISION.No CONTRACTOR: CGCOC GROUP CO., LTD PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × LIFTSHAFT 2 REINFORCEMENT SC. 1:25 SIDE -5 SIDE -1 SIDE -4 LIFTSHAFT 1 REINFORCEMENT SC. 1:25 SIDE -2 1 1 SIDE -4 SIDE -1 1 1 2 SIDE -3 2 SIDE -6 +29.84 +29.84 SIDE -6 SIDE -5 +29.84 +29.84 +29.84 3 3 Ø12/150 L= Ø12/150 L= Ø12/150 L= 3 3 3 1 Ø12/150 L= Ø12/150 L= 3 2 Ø10c/c150 - 950 3 3 2 SIDE -4 +29.84 1 Ø12/150 L= SIDE -3 SIDE -2 2 Ø10c/c150 - 950 2 SIDE -1 +29.84 1 +8.82 2Ø10c/c150 -19600 1 +5.22 +5.22 Ø10c/c150 - 1150 1 2 Ø12/150 L= 2 Ø10c/c150 - 1150 1 Ø12/150 L= Ø14/150 L= 5 +5.22 +5.22 2 1 Ø14/150 L= Ø10c/c150 - 850 3281 5 Ø14/150 L= +0.00 +0.00 2 Ø16c/c120 - 3375 6 1 3 2 1 1 Ø14/150 L=4050 1 3 OFFICE BUILDING +0.00 3 3 3 2 DRAWING TITLE: 2625 Ø14/150 L= 1 Ø14/150 L=4050 2 CONTRACTOR: PROJECT: Adama Town water Supply & Sanitation Improvement Project 3 3 +0.00 3 3 6 4 1 INITIAL. REVISION.No CGCOC GROUP CO., LTD 36 2 +1.62 DATE. 1 Ø14/150 L= Ø14/150 L= 1 5 1 No. 3 6 3 6 6 1 Ø14/150 L= 36 2 Ø16c/c120 - 3375 Ø14/150 L= 3 3 2625 3 3125 APRD BY 1 2 4 +5.22 2 1 3 2750 5 Ø14/150 L= Ø14/150 L= 3 5 4 +1.62 3 MS CONSULTANCY 1 1 3 2 Ø10c/c150 -850 3 6 6 4 3 6 REVIEWED BY 2750 +1.62 2 +8.82 3 3125 6 1 Ø14/150 L= 3 2 Ø10c/c150 - 5030 Ø14/150 L= Ø14/150 L=7130 3 CONSULTANT APPROVAL 1 +8.82 3281 +5.22 +12.42 3 2625 +8.82 2750 +5.22 NOTES: NOTES: Ø14/150 L= 3125 +8.82 Ø14/150 L= 3 Ø14/150 L= 3 5 3 1 2 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 6 6 Ø10c/c150 - 850 Ø14/150 L= Ø14/150 L= +8.82 CLIENT NOTES 1 2 3 3281 1 1 4 2750 +8.82 3 +12.42 3 1 5 4 +16.02 3 2 Ø10c/c150 - 850 +12.42 1 2 Ø14/150 L= Ø14/150 L= +12.42 Ø14/150 L= 6 3 5 2625 3 2 6 4 +12.42 3 6 1 2 1 1 5 +12.42 3125 3 3281 1 3 2 Ø12/150 L= 3 Ø12/150 L= 6 4 3 +16.02 1 2 2750 +12.42 +19.62 3 2625 +16.02 Ø12/150 L= Ø10c/c150 - 1900 +16.06 3 1 5 4 4 +16.02 3 2 Ø12/150 L= Ø12/150 L= 3 3125 3 Ø12/150 L= Ø12/150 L= 5 6 3 +19.62 3281 +16.02 6 6 3 2750 +16.02 1 2 6 4 3125 +19.62 1 2 1 2 Ø12/150 L= Ø12/150 L= 3 +19.62 3 6 3 1 2625 Ø12/150 L= Ø10c/c150 - 1900 +19.62 3 Ø12/150 L= 1 5 3 3281 +19.62 3 6 3 4 +23.22 3 Ø10c/c150 - 1150 6 2750 +19.62 +23.22 1 3125 1 2 2 Ø12/150 L= Ø12/150 L= 3 2625 +23.22 Ø12/150 L= 1 6 3 +23.22 3 Ø12/150 L= Ø10c/c150 - 1150 +23.22 3 5 Ø12/150 L= 3281 +23.22 6 4 2750 +23.22 1 2 6 5 4 3125 1 6 1 2 6 1 1 Scale: Designed: Drawn: 5 3 3 3 6 2 5 Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × TYPE-III FROM GROUND FLOOR TO FIRST FLOOR (+162 TO +522) SC. 1:50 5 2' 3 1 5 2 4 3 7 6 GROUND - FIRST +1.98 STAIRCASE REINFORCEMENT 2 4 6 6 3 7 1 7 Sc. 1:50 5 4 SECTION 1-1 5 sc 1:25 10 E 2 1 12 1 3 2 STB-B 11 11 6 2 7 2 1 4 SECTION 10-10 3 D 5 6 STB-A 1 sc 1:25 3 2 7 5 1 4 5 2 7 6 2 4 6 5 1 3 7 2 4 10 1 12 4 2 1 6 7 SECTION 2-2 sc 1:25 3 SECTION 11-11 sc 1:25 CLIENT NOTES 6 1 7 FIRST - ROOF TERRACE STAIRCASE REINFORCEMENT 6 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 7 6 2 3 NOTES: 7 Sc. 1:50 5 4 3 7 6 1 1 3 13 CONSULTANT APPROVAL 6 STB-B 14 5 MS CONSULTANCY SECTION 12-12 7 14 sc 1:25 2 2 4 1 3 SECTION 13-13 STB-B sc 1:25 (250X500) APRD BY REVIEWED BY NOTES: Ø8/150 C 0 450 ST-1 1 3 5 2 1460 5 613 L= 20 2795 4Ø 4 450 6 1865 7 500 2 4Ø20 L=3465 4 1 675 5 613 L= 5 20 279 4Ø 4Ø20 L=3060 1080 2565 500 450 Sc.. 1:25 6 15 450 Ø8/150 SECTION OF STAIRCASE BEAMS 5 7 13 450 /15 Ø8 450 E 2 15 2160 No. DATE. CONTRACTOR: SECTION 14-14 3 INITIAL. REVISION.No CGCOC GROUP CO., LTD sc 1:25 PROJECT: Adama Town water Supply & Sanitation Improvement Project 7 DRAWING TITLE: 6 2 1 OFFICE BUILDING 2 6 7 Scale: Designed: 3 Drawn: 1 SECTION 15-15 2 Checked: Date: Approved: APRIL,2023 sc 1:25 Drawing No. Sheet No. × · · · · SW2 CF-1 GB-4 I 3' CF-2 4 SW3 Ø8/200 2 I CF-1 CF-1 SW2 Ø8/200 Y SW10 Ø8/200 C12 C12 Ø8/200 Y SW8 GB-3` SW9 2' 1 CF-8 CF-7 L GB-3 F8 Ø8/200 C12 @LEVEL 0.00 F1 Ø8/200 Ø8/200 F2 1.62 1.62 F3 C3' H F1 GB-4 F3 F1 C12 C3' GB-8 GB-8 GB-8 GB-8 Y 1.62 C3 F F1 CF-3 C6 SW4 C6 Y C12 C12 F1 Ø8/200 J GB-3 Ø8/200 F4 CF-6 GB-4 Y C12 F1 Ø8/200 Ø8/200 F2 @LEVEL 0.00 C6 Ø8/200 Ø8/200 Y C3 C6 F2 F1 Ø8/200 F1 F1 GB-4 F2 Ø8/200 Ø8/200 C3 K GB-3 C6 C6 Ø8/200 G C12 C12 C7 C7 GB-5 F3 C11 CF-5 C11 F2 F GB-1 Ø8/200 F3 Ø8/200 Ø8/200 +1.62 F1 F1 Ø8/200 1.62 SW5 C4 F1 GB-1 C8 C10 C10 C9 SW11 Ø8/200 C10 F6 F7 F6 Ø8/200 +1.62 +0.00 F3 Ø8/200 Ø8/200 +0.00 Ø8/200 0.00 F3 F3 CF-4 C7 2 Ø8/200 2' 3' 3 4 5 Ø8/200 F7 Ø8/200 F3 F3 6 CONSULTANT APPROVAL Y MS CONSULTANCY 6' 7 Sc. 1:25 GB-1' C7 8 9 APRD BY REVIEWED BY F2 C7 C7 C9 TYPICAL SECTION OF BASEMENT FLOOR SLAB GROUND FLOOR SLAB, BEAM, COLUMN & FOOTING LAYOUT & REINFORCEMENT Y @LEVEL 0.00 1 C7 A NOTES: 2 10 SECTION OF BASEMENT FLOOR BEAMS Sc. 1:25 SLAB THICKNESS=100mm Ø8/200 NOTES: F1 C7 D F3 +0.00 C4 CF-4 GB-1' C10 Ø8/200 F1 Ø8/200 F1 GB-1 1 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE GB-6 F2 GB-10 GB-8 F1 F1 CLIENT NOTES Ø8/200 GB-6 F6 Ø8/200 C1 E' C11 GB-5 C5' C4 F1 Ø8/200 C8 F2 1.62 GB-4 C11 GB-10 C5 C5 F1 C8 F1 Ø8/200 1.62 GB-2 Ø8/200 A F2 1.62 F2 C2 B Ø8/200 Ø8/200 +0.00 C11 C8 GB-11 1.62 CF-1 C1' @LEVEL 0.00 @LEVEL 0.00 Ø8/200 Ø8/200 D C +0.00 C6 GB-10 GB-8 Ø8/200 SW1 +0.00 Ø8/200 F5 C6 SW5 F1 Ø8/200 +0.00 C11 @LEVEL 0.00 Ø8/200 F1 GB-2 GB-9 C3 E Ø8/200 SW7 Ø8/200 F2 SW7 Ø8/200 SW6 F1 100mm expansion joint FLAT SLAB EDGE BEAMS SECTION Sc.. 1:25 Sc. 1:50 LEVEL +0.00 & +1.62 10cm thick RC slab 25cm hard core 50cm Selected fill Well Compacted earth 3Ø20 ST-1 No. ST-2 DATE. INITIAL. REVISION.No TYPICAL SECTION OF RC GUTTER 3Ø20 Sc. 1:25 2 CONTRACTOR: 1 SECTION (PERIPHERAL BEAM) sc1:25 1CM STYRAFORM JOINT ST-1 SECTION (MASONRY COPPING BEAM) 100mm expansion sc 1:25 joint 8Ø12 ST-2 CGCOC GROUP CO., LTD TYPICAL SECTION OF FIRST - ROOF TERRACE FLOORS BEAMS 1 Ø10/150 L=2550 Sc.. 1:25 NGL NGL ST-2 1 2 2' 3' 2 Ø10/150 L=1050 3 PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: 5cm thick C7 lean concrete 5cm thick C7 lean concrete TYPICAL SECTION OF ROOF BEAMS OFFICE BUILDING Sc.. 1:25 ST-3 Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × +19.62 +19.62 +19.62 +19.62 21 20 +19.62 20 24 +19.62 24 +19.62 +19.62 8 20 +19.62 20 22 +19.62 22 3575 3575 3575 3575 8 10Ø20 L=4400 21 +23.22 12Ø16 L=4400 20 +23.22 12Ø20 L=4400 20 +23.22 16Ø20 L=4400 6 +23.22 12Ø16 L=3725 3575 6 +23.22 14Ø20 L=3725 3575 23 +23.22 12Ø16 L=3725 3575 23 +23.22 12Ø20 L=3725 3575 19 +23.22 12Ø24 L=3725 3575 19 +23.22 12Ø20 L=3725 3575 +23.22 +19.62 19 22 6 6 20 20 21 21 20 20 24 24 25 25 8 8 20 20 22 Ø10/100 10Ø20 L=4400 4400 12Ø16 L=4400 4400 12Ø20 L=4400 4400 16Ø16 L=3725 3575 16Ø20 L=4400 4400 12Ø16 L=4400 4400 14Ø20 L=4400 4400 12Ø16 L=4400 4400 12Ø20 L=4400 4400 22 22 Ø10/150 19 10Ø20 L=4400 4400 12Ø20 L=4400 4400 COLUMN STIRRUP SPACING DETAIL +16.02 +16.02 +16.02 +16.02 +16.02 +16.02 +16.02 +16.02 +16.02 +16.02 +8.82 +8.82 +8.82 +8.82 +8.82 19 +8.82 19 +12.42 24 +8.82 24 +12.42 14 +8.82 14 8 20 +12.42 14 +8.82 14 20 22 +12.42 19 +8.82 19 10Ø20 L=4400 4400 8 12Ø16 L=4400 4400 25 12Ø20 L=4400 4400 16Ø16 L=4400 4400 16Ø20 L=4400 4400 12Ø20 L=4400 4400 25 22 +12.42 22 +8.82 10Ø20 L=4400 4400 21 +12.42 24 12Ø20 L=4400 4400 21 24 16Ø20 L=4400 4400 20 +12.42 19 16Ø20 L=4400 4400 20 19 16Ø20 L=4400 4400 +12.42 21 12Ø20 L=4400 4400 6 21 14Ø20 L=4400 4400 20 +12.42 6 12Ø16 L=4400 4400 20 14Ø20 L=4400 4400 22 6 12Ø16 L=4400 4400 22 12Ø20 L=4400 4400 10Ø20 L=4400 4400 6 12Ø20 L=4400 4400 19 22 +12.42 12Ø20 L=4400 4400 19 +8.82 22 +12.42 10Ø16 L=3725 3575 +12.42 19 10Ø20 L=4400 4400 19 12Ø20 L=4400 4400 Ø10/100 +16.02 22 +8.82 1 1 1 7 7 11 5 +1.62 5 7 12Ø20 L=4400 4400 9 +3.60 16 8 +3.60 8 NOTES: ±5.22 18 +3.60 18 10Ø20 L=4400 4400 16 10Ø20 L=4400 4400 12Ø20 L=4400 4400 16Ø20 L=4400 4400 +3.60 8 ±5.22 22 CONSULTANT APPROVAL MS CONSULTANCY +3.60 APRD BY REVIEWED BY 8 14 14 14 14 8 8 16 16 8 8 18 18 2420 8 8 22 10Ø20 L=2420 10 +1.62 7 +3.60 14 ±5.22 19 2420 10 12Ø20 L=3650 3250 +1.62 11 14Ø20 L=4400 4400 8 14 ±5.22 19 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE NOTES: +1.62 12Ø20 L=3650 3250 8 12Ø20 L=3650 3250 +1.62 6 14Ø20 L=3650 3250 6 12Ø20 L=4400 4400 12Ø20 L=4400 4400 10Ø20 L=4400 4400 12Ø20 L=4400 4400 12 ±5.22 16 9 7 7 +0.00 +0.00 13 +0.00 13 13 +0.00 13 7 +0.00 7 15 15 +0.00 7 7 10Ø20 L=3650 3250 1 12 +1.62 10Ø16 L=3650 3250 +1.62 8 16 12Ø20 L=3650 3250 3 8 ±0.00 14 14 16Ø20 L=3650 3250 3 2 10Ø16 L=3650 3250 +1.62 12Ø16 L=3650 3250 +1.62 2 10Ø20 L=3650 3250 2 12Ø20 L=3650 3250 2 10Ø16 L=4400 4400 10Ø16 L=4400 4400 12Ø16 L=4400 4400 4 14 ±5.22 14 4 14 12Ø20 L=4400 4400 ±5.22 16Ø20 L=4400 4400 16Ø20 L=4400 4400 14 12Ø20 L=2420 ±5.22 8 16Ø20 L=4400 4400 8 2420 ±5.22 10 16Ø20 L=2420 ±5.22 10 16Ø20 L=3650 3250 8 12Ø20 L=4400 4400 14Ø20 L=4400 4400 12Ø20 L=4400 4400 8 2420 ±5.22 6 12Ø20 L=2420 6 12Ø20 L=3650 3250 12 16Ø20 L=4400 4400 ±5.22 12Ø20 L=4400 4400 10Ø20 L=4400 4400 12 2420 ±5.22 8 16Ø20 L=2420 8 16Ø20 L=3650 3250 ±5.22 2 16Ø20 L=4400 4400 ±5.22 2 2420 2 16Ø20 L=2420 2 12Ø20 L=4400 4400 10Ø16 L=3725 3575 10Ø16 L=4400 4400 CLIENT NOTES 17 17 No. DATE. INITIAL. REVISION.No CONTRACTOR: CGCOC GROUP CO., LTD PROJECT: Adama Town water Supply & Sanitation Improvement Project SECTIONS OF COLUMNS Sc. 1:25 ST-2 ST-2' ST-2'' ST-1 ST-2 ST-3 ST-1 ST-2 ST-1 ST-1 ST-3 ST-4 ST-1 ST-1 ST-2 ST-2 ST-2 ST-2 ST-1 ST-3' ST-3'' ST-4' ST-3 ST-4'' ST-3 ST-3 ST-2 ST-2 ST-1 ST-1 ST-1 ST-1 ST-2 ST-2 ST-3 ST-3 ST-1 ST-1 ST-2 ST-2 ST-3 ST-3 ST-2 ST-2 ST-1 ST-1 ST-1 ST-1 ST-1 ST-2 ST-3 ST-2 ST-2 ST-1 ST-1 ST-1 ST-2 ST-2 ST-2 ST-1 ST-2 DRAWING TITLE: ST-3 SEC.2-2 SEC.3-3 SEC.4-4 SEC.5-5 SEC.6-6 SEC. 7-7 SEC. 8-8 SEC. 9-9 SEC. 10-10 SEC. 11-11 SEC. 12-12 SEC. 13-13 SEC. 14-14 SEC. 15-15 SEC. 16-16 SEC. 17-17 SEC. 18-18 SEC. 19-19 SEC. 20-20 SEC. 21-21 SEC. 22-22 SEC. 23-23 SEC. 24-24 OFFICE BUILDING SEC. 25-25 Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 FFB-3' I I 3' 4 FFB-7 FFB-2' FFB-6 L H K FFB-6 FFB-6 J FFB-4' G CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE FFB-5 F F NOTES: CONSULTANT APPROVAL FFB-3 E MS CONSULTANCY FFB-1' E' FFB-4 APRD BY REVIEWED BY NOTES: D D FFB-2 1 DATE. INITIAL. REVISION.No CONTRACTOR: CGCOC GROUP CO., LTD FFB-1 A No. FFB-14 FFB-13 FFB-12 FFB-11 FFB-10 FFB-10 FFB-9 FFB-8 C1 FFB-8 B FFB-10 C A 2 2' 3' FIRST FLOOR SLAB & BEAM LAYOUT & REINFORCEMENT 3 4 5 6 6' 7 8 9 10 PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: @ LEVEL ±5.22 SLAB THICKNESS=180mm OFFICE BUILDING Sc. 1:50 Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 1051 1162 3400 2116 2000 I 1051 1162 3400 2116 2000 2000 6450 2100 2000 L 1750 1900 2100 6450 1900 1750 1051 1162 3400 2116 2000 H K 2000 2100 6450 1900 1750 1051 1162 3400 2116 2000 G J 2000 2100 6450 1650 2000 CLIENT NOTES F F 1950 1750 4200 2400 4800 2400 2250 1050 1200 1907 NOTES: 2528 2987 E 2000 2100 6450 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 1800 1650 CONSULTANT APPROVAL E' 1750 1750 4200 2400 4800 2400 MS CONSULTANCY 2250 2200 1650 D 1600 1700 D 1900 1050 1800 1749 1800 1800 1749 1800 APRD BY REVIEWED BY NOTES: 7500 1200 2987 1907 2358 C B 1650 1750 4200 2400 4800 2400 4800 2400 3600 1200 2990 1904 2253 No. DATE. A A 1 2 2' SECOND FLOOR FLAT SLAB TOP REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm Y-DIRECTION Sc. 1:50 3' 3 4 5 6 6' 7 8 9 INITIAL. REVISION.No CONTRACTOR: CGCOC GROUP CO., LTD 10 PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 1051 1162 3400 2116 2000 I 1051 1162 3400 2116 2000 L 1750 2000 2100 6450 1900 2000 2100 6450 1900 1750 1051 1162 3400 2116 2000 H K 2000 2100 6450 1900 1750 1051 1162 3400 2116 2000 G J 2000 2100 6450 1650 2000 CLIENT NOTES F F 1950 1750 4200 2400 4800 2400 2250 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 1800 NOTES: 1050 1200 1907 2528 2987 E 2000 2100 6450 1650 CONSULTANT APPROVAL E' 1750 1750 4200 2400 4800 2400 MS CONSULTANCY 2250 2200 1650 D D 1050 1800 1749 1800 1800 1749 1800 APRD BY REVIEWED BY NOTES: 7500 1200 2987 1907 2358 4900 C B 1650 1750 4200 2400 4800 2400 4800 2400 3600 1200 2990 1904 2253 No. DATE. A A 1 2 2' THIRD FLOOR FLAT SLAB TOP REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm Y-DIRECTION 3' 3 4 5 6 6' 7 8 9 INITIAL. REVISION.No CONTRACTOR: CGCOC GROUP CO., LTD 10 PROJECT: Adama Town water Supply & Sanitation Improvement Project Sc. 1:50 DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 I L H K G J F F CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE NOTES: E E' CONSULTANT APPROVAL MS CONSULTANCY D D APRD BY REVIEWED BY C NOTES: B A A No. 1 2 2' 3' 3 4 5 6 6' 7 8 9 DATE. 10 INITIAL. REVISION.No CONTRACTOR: FOURTH FLOOR FLAT SLAB BOTTOM REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm CGCOC GROUP CO., LTD Sc. 1:50 LEVEL +16.06 PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 1507 1258 892 1200 1200 1200 I 2205 L 1684 1497 2400 2400 2400 1487 1487 1487 1200 1200 1200 H 2709 2709 K 2709 2400 2400 2400 1200 1200 1200 1200 1200 1200 G 2400 2400 J 2400 2400 2400 2400 1200 1200 1200 1200 1200 1200 1164 1050 1350 973 F 2550 F 2550 1500 1500 1600 1600 1650 1650 1600 1600 CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 2325 1125 1310 4750 4600 NOTES: 1535 1535 1350 E 2500 965 1200 1200 1120 1120 E' CONSULTANT APPROVAL MS CONSULTANCY 2404 2405 6680 1050 6680 6680 6680 1050 D 5180 D 5180 APRD BY REVIEWED BY 2550 2400 2459 NOTES: C 2325 2325 2325 2325 2325 2325 2325 2325 2250 2250 2250 2250 2250 2250 2250 2250 2033 B 2333 A A No. DATE. INITIAL. REVISION.No CONTRACTOR: 1 2 2' FOURTH FLOOR FLAT SLAB TOP REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm X-DIRECTION Sc. 1:50 3' 3 4 5 6 6' 7 8 9 10 CGCOC GROUP CO., LTD PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 1148 1270 3714 2311 2185 1148 1270 3714 2311 2185 L 1912 2185 2294 7047 2076 2185 2294 7047 2076 I 1148 1270 3714 2311 2185 1912 H K 2185 2294 7047 2076 1912 1148 1270 3714 2311 2185 G J CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 2185 2294 7047 1803 2185 NOTES: F F 2130 1912 4589 2622 5244 2622 2458 1967 CONSULTANT APPROVAL 1147 E 2185 2294 7047 1311 3263 2084 MS CONSULTANCY 2762 APRD BY REVIEWED BY 1803 E' 1912 1912 4589 2622 5244 2622 2458 NOTES: 2404 1803 1803 D D 8194 1147 1311 2084 2576 3263 1967 1857 1911 1967 1694 C No. DATE. INITIAL. REVISION.No CONTRACTOR: CGCOC GROUP CO., LTD B 1803 1967 1911 1912 4589 2622 5244 2622 5244 2622 3933 1311 3267 2080 PROJECT: Adama Town water Supply & Sanitation Improvement Project 2462 1967 A A DRAWING TITLE: OFFICE BUILDING 1 2 2' FIVTH FLOOR FLAT SLAB TOP REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm Y-DIRECTION 3' 3 4 5 6 6' 7 8 9 10 Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Sc. 1:50 Drawing No. Sheet No. × 2' I 3' 4 RTB-11 RTB-12 1 RTB-9 I H G RTB-17 RTB-10 RTB-8 K RTB-9 J RTB-9 F RTB-14 RTB-15 RTB-8 F L CLIENT NOTES RTB-7 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE NOTES: CONSULTANT APPROVAL E RTB-6 MS CONSULTANCY E' RTB-5 APRD BY REVIEWED BY RTB-4 RTB-3 D RTB-18 D NOTES: 2 2' 3' ROOF TERRACE FLOOR SLAB REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=160mm Sc. 1:50 LEVEL +23.22 CGCOC GROUP CO., LTD 3 4 5 6 6' 7 A 8 9 RTB-21 1 INITIAL. REVISION.No CONTRACTOR: RTB-2 RTB-1 A DATE. RTB-20 No. RTB-19 B RTB-16 RTB-13 C 10 PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × RTB-18 D E' F E 3Ø20 L=6282 2631 2401 Ø8/100 3Ø20 L=1800 450 450 4Ø20 L=8500 7652 F Ø8/100 Ø8/100 Ø8/150 Ø8/100 2Ø20 L=2401 1200 1200 Ø8/100 (250X500) RTB-13 4Ø20 L=9515 9068 B D C E 2Ø20 L=2551 1350 1200 Ø8/100 Ø8/150 Ø8/100 2Ø20 L=2401 1200 1200 Ø8/100 Ø8/100 1951 7557 4Ø20 L=8560 4Ø20 L=9655 8113 Ø8/100 Ø8/100 Ø8/150 Ø8/100 4Ø20 L=11900 2Ø20 L=8005 10063 Ø8/100 3Ø20 L=2400 450 450 Ø8/100 2Ø20 L=2901 1200 1701 2Ø20 L=10510 11004 4Ø20 L=11900 11004 9208 RTB-17 D E F H G I RTB-16 A (250X500) Ø8/100 Ø8/150 2Ø20 L=2551 1350 1200 450 Ø8/100 Ø8/150 2Ø20 L=2551 1350 1200 2Ø20 L=10000 Ø8/100 Ø8/100 Ø8/150 2Ø20 L=2401 1200 1200 Ø8/100 Ø8/100 Ø8/100 3Ø20 L=2250 1801 4Ø20 L=11710 4Ø20 L=5550 11714 11154 E' Ø8/150 J Ø8/100 3Ø20 L=3601 2401 1200 3Ø20 L=3100 2651 11004 D E 4Ø20 L=11900 Ø8/150 Ø8/100 3Ø20 L=1750 1300 11004 5102 F Ø8/100 2Ø20 L=11900 7052 12004 D Ø8/100 2Ø20 L=7500 4Ø20 L=8480 RTB-12 Ø8/150 2Ø20 L=2751 1200 1550 2Ø20 L=12000 9553 450 Ø8/100 450 2401 Ø8/100 450 2Ø20 L=3751 1350 3Ø20 L=3100 2651 Ø8/150 450 Ø8/100 450 Ø8/100 450 450 Ø8/150 450 Ø8/100 450 (250X500) 450 450 Ø8/150 450 Ø8/100 450 Ø8/150 450 450 Ø8/100 Ø8/100 450 Ø8/150 1601 450 1901 (250X500) 3Ø20 L=2050 A 3Ø20 L=2350 7417 8113 A Ø8/100 2Ø20 L=7865 4Ø20 L=8560 I Ø8/150 2Ø20 L=2851 1200 1650 10063 H G Ø8/150 2Ø20 L=2551 1350 1200 1601 8053 RTB-15 Ø8/100 Ø8/100 2Ø20 L=10510 6902 4Ø20 L=8100 Ø8/150 3Ø20 L=2050 1551 450 450 Ø8/100 2Ø20 L=7350 9103 450 Ø8/150 1250 2Ø20 L=9550 450 I 450 Ø8/100 450 450 2651 A H G 450 Ø8/100 450 Ø8/100 450 Ø8/150 3Ø20 L=3100 Ø8/100 F (250X500) Ø8/100 E RTB-14 450 (250X500) 450 A K L G (250X500) Ø8/100 3Ø20 L=6282 2631 3Ø20 L=3100 450 2651 2401 Ø8/100 Ø8/150 1250 450 Ø8/100 Ø8/100 7652 Ø8/150 3Ø20 L=2401 1200 1200 Ø8/100 Ø8/100 F Ø8/100 CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 3Ø20 L=1850 1401 2Ø20 L=7150 5872 4Ø20 L=8850 7752 E' Ø8/150 3Ø20 L=2351 1200 1150 4Ø20 L=7750 8053 D Ø8/100 8023 4Ø20 L=8050 RTB-13 Ø8/100 2Ø20 L=8020 8693 4Ø20 L=8100 Ø8/150 3Ø20 L=2451 1250 1200 2Ø20 L=8690 9103 450 Ø8/150 3Ø20 L=2901 1651 1250 2Ø20 L=9550 A Ø8/100 Ø8/100 450 Ø8/100 450 Ø8/150 NOTES: 450 Ø8/100 7572 J K L G (250X500) CONSULTANT APPROVAL Ø8/100 3Ø20 L=3100 450 2651 2401 3Ø20 L=6282 2631 Ø8/100 450 Ø8/150 Ø8/100 Ø8/100 D Ø8/150 3Ø20 L=2401 1200 1200 Ø8/100 Ø8/100 F MS CONSULTANCY Ø8/100 3Ø20 L=1950 1501 APRD BY REVIEWED BY 2Ø20 L=7150 6172 4Ø20 L=8850 7612 E' Ø8/150 3Ø20 L=2451 1200 1250 4Ø20 L=7750 8053 RTB-14 Ø8/100 7953 4Ø20 L=8050 7652 Ø8/100 2Ø20 L=7950 8803 4Ø20 L=8100 Ø8/150 3Ø20 L=2451 1250 1200 2Ø20 L=8800 9103 450 Ø8/100 Ø8/100 3Ø20 L=2901 1651 1250 1250 2Ø20 L=9550 A Ø8/150 450 Ø8/100 450 Ø8/150 NOTES: 450 Ø8/100 7873 J K L G (250X500) 450 3Ø20 L=3100 2651 2401 Ø8/100 3Ø20 L=6277 2626 Ø8/100 450 450 Ø8/100 Ø8/150 Ø8/100 Ø8/100 8048 Ø8/100 Ø8/100 3Ø20 L=2401 1200 1200 Ø8/150 Ø8/100 Ø8/100 7442 Ø8/100 3Ø20 L=2150 1701 2Ø20 L=7150 7868 4Ø20 L=7440 Ø8/150 3Ø20 L=2651 1200 1450 2Ø20 L=7865 8683 4Ø20 L=8045 Ø8/150 3Ø20 L=2351 1150 1200 2Ø20 L=8680 9103 7657 Ø8/100 3Ø20 L=2801 1651 1150 1250 2Ø20 L=9550 4Ø20 L=8105 Ø8/150 450 Ø8/100 6702 4Ø20 L=8850 No. DATE. INITIAL. REVISION.No 450 Ø8/150 CONTRACTOR: 450 Ø8/100 CGCOC GROUP CO., LTD 8403 PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 9 +23.22 +23.22 +23.22 +23.22 100Ø12 L= +29.84 9 +23.22 +23.22 +23.22 +23.22 +23.22 1 1 +19.62 2 2 +19.62 +19.62 +19.62 +19.62 9 +19.62 8 +19.62 8 10 10 10 +19.62 +19.62 10 34Ø14 L= 9 34Ø14 L= 5 48Ø14 L= 5 100Ø12 L= 3 44Ø14 L= 3 42Ø16 L= 3 34Ø14 L= 1 28Ø14 L= 1 28Ø14 L= 3 42Ø16 L= +23.22 +19.62 +15.00 10 10 10 10 34Ø14 L= 48Ø14 L= 34Ø14 L= 34Ø14 L= 8 10 +16.02 34Ø14 L= 8 10 +16.02 48Ø14 L= 44Ø14 L= 42Ø16 L= 100Ø14 L= 100Ø14 L= 8 +4.20 +4.20 +8.82 +8.82 3 3 5 3 8 8 +8.82 3 5 8 +8.82 5 8 7 10 6 10 +8.82 +8.82 7 10 10 6 10 34Ø14 L= 5 +12.42 34Ø14 L= 3 +12.42 +12.42 48Ø14 L= 3 +12.42 +8.82 10 10 CLIENT NOTES 10 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 1 +5.22 +5.22 1 +5.22 2 2 3 3 3 28Ø14 L= +5.22 +5.22 +5.22 3 5 5 7 7 6 +3.60 10 6 +5.22 10 10 +3.60 +3.60 10 NOTES: +3.60 +0.00 +0.00 +0.00 34Ø14 L= 34Ø14 L= +1.62 +1.62 CONSULTANT APPROVAL +0.00 MS CONSULTANCY 7 7 +0.00 10 10 +0.00 10 10 34Ø14 L= +0.00 +1.62 44Ø14 L= +0.00 +1.62 34Ø14 L= 1 +1.62 48Ø14 L= 2 +1.62 100Ø20 L= 2 +1.62 42Ø16 L= +1.62 42Ø16 L= 28Ø14 L= 1 1 34Ø14 L= +1.62 1 28Ø14 L= +1.62 48Ø14 L= 100Ø20 L= 1 44Ø14 L= 1 +5.22 42Ø16 L= 1 +5.22 34Ø14 L= 28Ø14 L= +5.22 42Ø16 L= 1 +16.02 10 34Ø14 L= 2 8 10 34Ø14 L= 2 5 +12.42 +12.42 42Ø16 L= 1 +8.82 28Ø14 L= 1 3 34Ø14 L= 2 +8.82 28Ø14 L= +8.82 2 5 8 48Ø14 L= +12.42 34Ø14 L= 1 28Ø14 L= 1 28Ø14 L= 1 3 8 +16.02 100Ø14 L= +12.42 3 1 3 8 100Ø20 L= +12.42 3 8 +16.02 44Ø14 L= 2 5 44Ø14 L= +12.42 2 +16.02 42Ø16 L= 1 5 34Ø14 L= 1 28Ø14 L= 1 28Ø14 L= 3 1 42Ø16 L= +16.02 3 44Ø14 L= +16.02 3 42Ø16 L= +16.02 3 42Ø16 L= 2 42Ø16 L= +16.02 2 42Ø16 L= 1 28Ø14 L= 1 28Ø14 L= 1 34Ø14 L= 3 1 APRD BY REVIEWED BY 28Ø14 ST-1 NOTES: SECTION 1-1 SCALE 1:25 34Ø14 ST-2 SECTION 2-2 SCALE 1:25 42Ø16 ST-2 SECTION 3-3 SCALE 1:25 42Ø14 ST-3 +1.62 SECTION 4-4 SCALE 1:25 44Ø14 34Ø14 L= ST-4 SECTION 5-5 SCALE 1:25 48Ø14 ST-5 +0.00 No. SECTION 6-6 DATE. INITIAL. REVISION.No SCALE 1:25 100Ø20 ST-6 SCALE 1:25 11 CONTRACTOR: 34Ø14 L= 11 SECTION 7-7 100Ø14 ST-6 CGCOC GROUP CO., LTD 100Ø12 SECTION 8-8 100Ø12 ST-6 SCALE 1:25 ST-6 SECTION 9-9 34Ø14 SCALE 1:25 ST-7 SECTION 10-10 SCALE 1:25 SECTION 11-11 SCALE 1:25 PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × CLIENT NOTES ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE NOTES: 50Ø14 Ø10@150 CONSULTANT APPROVAL MS CONSULTANCY APRD BY REVIEWED BY NOTES: 50Ø14 Ø10@150 No. DATE. INITIAL. REVISION.No CONTRACTOR: CGCOC GROUP CO., LTD PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. × 2' 1 I 3' 4 1507 1258 892 1200 1200 1200 I L 1704 1684 1497 2400 2400 2400 1487 1487 1487 1200 1200 1200 H 2709 2709 K 2709 2400 2400 2400 1200 1200 1200 1200 1200 1200 G 2400 2400 J 2400 2400 2400 2400 CLIENT NOTES 1200 1200 1200 1200 1200 1200 ADAMA TOWN WATER SUPPLY AND SEWERAGE SERVICE ENTERPRISE 973 1050 1164 1350 F 2550 F 2550 1500 1500 1600 1600 1650 1650 1600 1600 NOTES: 2325 1125 1310 4750 1535 4600 CONSULTANT APPROVAL 1535 1350 E MS CONSULTANCY 2500 965 1200 1200 1120 1120 E' 2404 2405 6680 6680 6680 D 5180 APRD BY REVIEWED BY 2625 6680 D 5180 NOTES: 2550 2400 5841 5842 C 2325 2325 2325 2325 2325 2325 2325 2325 2250 2250 2250 2250 2250 2250 2250 2250 B No. DATE. CONTRACTOR: CGCOC GROUP CO., LTD A A 1 2 2' SECOND FLOOR FLAT SLAB TOP REINFORCEMENT & BEAMS LAYOUT SLAB THICKNESS=220mm 3' 3 4 5 6 6' 7 8 9 INITIAL. REVISION.No 10 PROJECT: Adama Town water Supply & Sanitation Improvement Project DRAWING TITLE: OFFICE BUILDING X-DIRECTION Sc. 1:50 Scale: Designed: Drawn: Checked: Date: Approved: APRIL,2023 Drawing No. Sheet No. ×