siemens-energy.com Siemens Energy Colombia Transformers Factory SAT Operation and maintenance manual for liquid immersed PadMounted Transformers Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Table Content Tank pressure- Tightness........................................ 20 Important safety information ................................. 4 Internal inspection ................................................. 20 Important information about this manual ............. 5 Shipping ................................................................ 21 1. 4. Pad-mounted transformers............................. 6 Oil level inspection ................................................ 20 Manipulation ................................................ 22 Generalities .............................................................. 6 Lifting of the transformer....................................... 22 Radial feed Pad-mounted .......................................... 6 Forklift .................................................................. 23 Loop feed Pad-mounted ........................................... 6 Pulling ................................................................... 23 Modified Loop Feed Pad-mounted ............................ 7 Jack ....................................................................... 23 Single-phase Pad-mounted ....................................... 7 5. 2. Technical description ...................................... 8 Long time storage.................................................. 24 Core ......................................................................... 8 Location ................................................................ 24 Windings .................................................................. 8 6. Accessories .............................................................. 8 Before energization ............................................... 25 High-voltage bushings .............................................. 8 Test on site ............................................................ 25 Low-voltage bushings............................................... 9 Points to check before energization........................ 26 Oil level indicator ................................................... 10 7. Oil temperature indicator (Optional) ....................... 10 Cold Start Procedure .............................................. 30 Load breaker .......................................................... 10 8. Expulsion fuses ...................................................... 11 Operating conditions. ............................................ 31 Current-limiting fuses ............................................. 13 Temperature.......................................................... 31 Insulation fuses ...................................................... 13 Altitude of the installation...................................... 31 Thermomagnetic circuit breaker (opcional) ............. 13 Load under no nominal conditions. ........................ 32 Tap changer ........................................................... 14 Maintenance tests ................................................. 33 Pressure relief valve................................................ 15 Description of supervision and maintenance work .. 33 Drain and oil sampling valve ................................... 15 9. Ground Pads or screws ........................................... 15 Tightening Torque ................................................. 37 Vacuum pressure gauge (optional) ......................... 15 Health, safety and environment ............................. 39 Nameplate ............................................................. 15 During the design phase ........................................ 39 Insulating liquids .................................................... 16 During the Purchasing phase.................................. 39 Tank....................................................................... 17 During the Production and Service phase ............... 39 Radiators ................................................................ 17 Final disposition of the transformer’s materials....... 39 Surface Proteccion.................................................. 17 Spare parts ............................................................ 40 Sensformer® Connectivity Device ........................... 17 Warranty ............................................................... 41 3. 10. Attachments.................................................. 42 Reception ...................................................... 19 Storage ......................................................... 24 Installation ................................................... 25 Commissioning............................................. 29 Operation ..................................................... 31 Maintenance ................................................ 36 Shock indicator / impact recorder ........................... 19 Drawings and documents ....................................... 19 External inspection ................................................. 19 Version 3 © 2021 Siemens Energy 3 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Important safety information You must read this manual carefully before proceeding with the processes of transportation, installation, storage, operation and maintenance of the equipment. Siemens Energy transformers manage dangerous voltages for the human being. Not following the instructions present on this manual could cause several injuries, death or damage to the property. The safety use of the equipment depends of the properly practices of installation, operation, transportation, storage and maintenance. The staff must not try to manipulate the equipment while this is energized, to do it, the equipment must be disconnected, and all the terminals must be properly grounded. Only qualified staff should do the processes of installation, maintenance and operation of the equipment. The qualified staff are those people who were trained to install, maintein and operate high voltage equipments and to know the appropriate use of the personal protective equipment (gloves, helmet, dielectric boots and safety glasses) in the same way, this people must have been trained to practice first aid procedures. All the general safety guidelines, the regulations and the specific legislation for the installation place must be fulfilled without exception as well as the guidelines described in this user manual for every life cycle of the transformer. This service instructions include important signs of danger, warning and precaution that must be considered by the user. This transformer has been designed exclusively for the purpose described in this user manual. It is not allowed any other use that was not planned. If the described safety guidelines are not followed, Siemens Energy Colombia will not asumme any kind of guarantee or responsibility. Incorrect operation of the tap changer High pressures Fatal voltages Dangerous atmospheres Mobile machinery Heavy components The specialized staff must have the related certifications and autorizations to realize these jobs and should get used to the manage of transformers and the safety regulations of this user manual. Warning signs Indicates an imminent risk situation which, if not avoided, will result in death, several injuries and damage to the property. Indicates a potential risk situation which, if not avoided, could result in death, several injuries and damage to the property. The transportation, installation, launch, operation, maintenance and final disposition of the transformer is only allowed for specialized staff. It is recommendable that the local energy enterprise staff supervise these procedures. During the installation, operation and maintenance of the transformer, unsafe potential situations could present such as: Version 3 Indicates a potential risk situation which, if not avoided, may result in minor or moderate injuries and damage to the property. © 2021 Siemens Energy 4 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Important information about this manual This service manual must be maintained available for those who are responsible for the activities of installation, operation and service of the transformer. The information included in this document have as main purpose be a general guide for the installation and the operation for the Siemens Energy transformers when these are use in typical applications and normal ambient conditions. Even though every effort has been made to guarantee accurate and complete information, these instructions are not directed to specific situations that could present. The information presented in this document could not be for every type of transformer. Standard or optional features can be modified without notice. Siemens Energy does not assume any responsibility for the integrity, veracity, competence, and utility of this manual. Questions about the installation, operation or maintenance process (particularly when unusual situations or specific circumstances that are not cover by this manual arise) should be directed to the Siemens Energy Transformers Division. For every necessary task during the life cycle of the transformer only specialized staff with the relevant information and enough experience in the manage of transformers and knowledge of the guidelines, prescriptions, dispositions and accident prevention regulations validated for every case should be employed. It is necessary to check means of tie (wires, chains, hooks) and of lifting (raise bridges, crossbeams) before the use. Is is only allowed to use lifting means that are approved and certificate. Before starting any work with the transformer, it is to necessary apply “The 5 rules of safety”: 1. Disconnect the power 2. Prevent a reconnection 3. Verify that is free of voltage 4. Verify that is properly grounded and short circuit 5. Cover up the components that are under charged To avoid damages in the equipment it is not allowed to tie the raise points to the transformer components, like the air terminal bushings or the tank. It is necessary to be aware of the transformer pictograms! The prescriptions and dispositions valid in the country of use of the transformer should be considered, besides all the user manuals of the used merchandise. It is indispensable to read withpout exception every security indication included in this user manual. Version 3 © 2021 Siemens Energy 5 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 1. Pad-mounted transformers Generalities The Pad-mounted transformer provides electric service to underground distribution systems, where there is circulation of people and/or where the available space does not permit the set up of a conventional substation. The transformer is designed to be mounted outdoors on a pedestal. The Pad-mounted transformer consists in a tank with compartments for the bushings of high and low voltage, the compartments are in the front side of the tank and are separated by a metal barrier or another rigid material. It has two doors mechanically locked up that just give access to the high voltage compartment when the door of the low voltage compartment is open. As main characteristics it is important to highlight that these are dead-front equipments, a complete unit and that are autoprotected. There are generally the following feed type configurations: radial Pad-mounted, Loop feed Padmounted, modified Loop feed Pad-mounted and single-phase Pad-mounted. Pad-mounted transformers design is based on IEEE Std C57.12.34 standard and the use under the “usual service conditions” described in IEEE Std C57.12.00 standard. All the other conditions are considered outside the usual service and should be avoided. Loop feed Pad-mounted In the Loop feed type configuration, the primary power terminals are six or more insulators, with a 4position switch disconnector that are arranged to allow that similar transformers or another kind of charges keep being powered by the primary supply system without interruption, even when the transformer is out of operation. Radial feed Pad-mounted In the radial feed type configuration, the high voltage circuit culminates at the powered transformer terminals. Therefore, this configuration has just three bushings on the high voltage side and 2-position switch disconnector. Version 3 © 2021 Siemens Energy 6 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Modified Loop Feed Pad-mounted The modified Loop Feed configuration is applied in elevator transformers where the output on the HV side can be carried out by any of the two rows of bushings. The two-position switch disconnector normally only isolates the active part of the transformer. In this configuration the de-energization of the HV side is carried out upstream by means of sectioning cells. The protections used are agreed between the manufacturer and the customer. The configuration of the transformer and reference of the protections must be consulted on the nameplate and general dimensions drawing. Single-phase Pad-mounted Single-phase, self-cooled, Pad-mounted, compartmental-type distribution are rated 250 kVA and smaller with high voltages of 34.500 GrdY/19.920 V and below for operation between one phase and grounded neutral and low voltage of 480/240 V and below. These transformers are generally used for stepdown purposes from an underground primary cable supply. There are two configurations, radial or loop feed, according the terminal arrangements. Version 3 © 2021 Siemens Energy 7 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 2. Technical description Every transformer has its own construction specifications, accessories and characteristics, these are detailed in the transformer outline and in the drawings listed on the transformer nameplate. Pad-mounted transformers can be equipped with a variety of optional equipments. Most of these accessories are installed at the factory and it is not necessary any kind of work on site to prepare them to operate. This manual contains a brief description of the typical components of a transformer provided by Siemens Energy Colombia, however that not indicates that every transformer has all the components described here, Siemens Energy guarantee that the components included with the transformer are the requested by the purchase order and that the offer is the optimal solution according to the user requirements. The user must identify which of the following components apply for the provided transformer. The provided transformer has the components agreed in the negotiation. NAMEPLATE: It is obligatory for the user to check the nameplate information of the provided transformer. Wounded core The sliced sheets are rolled through loops with minimun inter-irons, this piece is subjected to a heat treatment to orient the grain, it is formed by groups to facilitates the assembly. Stacked core Stacked cold rolled oriented grain silicon steel sheets with inorganic insulation in both faces. The joints between the limbs and the yokes are overlapped by packages by the step lap method, to achieve minimun no load losses and noises while the transformer is being operated. Windings For wounded type core normally are fabricated rectangular windings, and for stacked type core normally are fabricated two types of windings, oval and circular. The windings are placed in a concentric way between them, sometimes the secondary winding is places concentric over the primary windings or vice versa. If it is requested, the windings can be equipped with a shield sheet properly grounded. The winding conductors can be high purity conductive materials, round, flat or in form of foil. The conductors could be without insulation or can be insulated with enamel or paper. Accessories Accessories are an important part of the transformer because they help to prevent several accidents in case of an internal or external failure. High-voltage bushings Core It is constructed by magnetic steel sheets, which are an oriented grain cold rolled silicon alloy. There can be two manufacturing technology types. Version 3 The high-voltage bushings fulfill the requierments stablished by the IEEE Std 386 and EN50180 standards. It facilitates the connection between de active part and the transmission line. There are mainly two forms of connection: The first with a bushing well where an © 2021 Siemens Energy 8 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers insert connector enters; the second, one-piece bushing (Integral). In both cases, the connectors material is insulating epoxy. Both configurations allow the connection of the cables of the transmission lines through insulating epoxy or similar elbows connectors. One-Piece Bushing (Integral) According to the voltage level, insulation level and current required, one-piece polymeric insulators are used to be installed in the wall of the tank and arranged to receive Loadbreak elbow type connectors, “T” elbows, grounding elbow connectors, among others. Bushing Well The bushing well is a device that facilitates the connection between the transformer active part and the transmission line through the corresponding inserts. The bushing well is attached to the side part of the tank and has a compartment where the interphase bushing well insert is inserted to connect the terminal to the loadbreak elbow. Loadbreak Elbow Bushin Well Inserts These connectors are useful as the interphase to realize the connection between the bushing well and the loadbreak elbow. The Loadbreak elbow allows to connect the cable of the high voltage supply connection to the bushing insert interphase insulator connector. Low-voltage bushings The secondary voltage windings are connected in the transformer according to the defined vector group and it is guided outside of the transformer through cables to the transformer cover/tank through the bushings. They can be dry type or if it is requested by the customer, they can be epoxy, resin or polymer material. Version 3 © 2021 Siemens Energy 9 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Load breaker The cantilever load must not exceed the bushings load. Heavy loads can cause damage to the bushings. In the three-phase transformers the load breaker are submerged in oil and are in the high-voltage section. For single-phase transformers the sectionalization must be carried out by means of separable insulated elbow connectors type of operation on load. Oil level indicator Pad- mounted transformers have an oil level viewer type located in the low-voltage compartment. Optional, when it is requested by the customer, it can be installed a magnetic type liquid level indicator. The nameplate must be checked to determine if the switch disconnector is capable to operate on load. Voltage and current limits specified in the nameplate must not be exceded. Generally, the three-phase transformer load breaker are to operate on load and according to the functionality there are two types: a. Load breaker for radial operation: this switch disconnector has two positions (open/close) and can be used to energize or to de-energize the transformer. Oil temperature indicator (Optional) The temperature liquid indicator is used to indicate the highest temperature of the liquid of the transformer. The design of the temperature indicator allows to change the indicator whithout getting access to the inside of the tank and to get low the oil level. Version 3 © 2021 Siemens Energy 10 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers b. Load breaker for loop feed opeation: this switch disconnector can be of four positions or it can be composed of two load breaker with two positions each one and independent handles. This switch disconnector is used to interrupt or to cotinue the supply line, in which two or more Transformers (loop feed) are connected, it can also insulate each transfomer from the loop for failures in the same or in the power cables for maintenance or replacement. remain insulated and de-energized of the power supply. Expulsion fuses This fuse operates in case of a low internal current failure and/or in case of a low-voltage grid failure. If your transformer is not provided with a secondary switch, your equipment must be integrated with a double element fuse bay-o-net type of internal operation. If your transformer is provided with a secondary switch, then it must be integrated with a single element fuse. The bay-o-net fuse is a dead-front device which can interrupt the load and it is powered by a live-line tool (insulated switch hook stick). This type of fuse is in the high-voltage compartment over the high-voltage bushings. Before energizing the bay-o-net fuse make sure that this is correctly hooked at its place. The four-position switch disconnector can only turn around in the clockwise direction, while the twoposition switch disconnector can turn around in both directions. Loop feed operation transformers: The load breaker of this equipments have metallic plates that indicates the positions, open or close, in the “A” line and in the “B” line, apart from the direction of the operation handles. The loop feed operation trasnformers have two bushings for each high-voltage phase. For example, the three-phase transformers have three bushings in the A line indentified as H1A, H2A and H3A and three bushings in the B line indentified as H1B, H2B and H3B. In that case the transformer can have the next positions: DANGER OF ELECTRIC SHOCK, EXPLOSION OR ARC FLASH The action of a fuse may indicate a damaged transformer. Do not replace the fuse until the cause of its action has been identified and rectified. The non-compliance of this instruction may result in death, serious injuries or damage to the equipment. Postion 1: A line and B line in “close” position. This position allows the supply to the adjacent transformers in the loop. Position 2: A line in “close” position and B line in “open” position. In this position only the A line of the loop is connected to the windings of the transformer. Position 3: A line in “open” position and B line in “close” position. In this position only the B line is connected to the windings of the transformer. Position 4: A line and B line in “open” position. In this position both sides of the loop (A and B line) are connected, whereby the windings of the transformer Version 3 These fuses are formed by a protective casing and a removable cartridge where the fuse is installed. The fuse should be replaced manually once it has operated. © 2021 Siemens Energy 11 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Case Cartridge and fuse Procedure for fuse replacement: a. b. c. d. Release the air preassure which has accumulated in the tank before removing the fuse (Operate the pressure relief valve, pulling the ring, to remove the internal pressure). e. Use a slotted screwdriver or another tool to facilitate removal of the connector. f. Use a 3/4” wrench to remove the damaged fuse from the cartridge. g. Place the new fuse in the cartridge and tighten to between 50 and 70 pounds-inch. h. Perform the same procedure to replace the connector and tighten to between 50 and 70 pounds-inch. i. Reinstall the fuse. Place the cartridge within the case and slide it until it stops, then turn it 90 degrees anticlockwise direction to allow to hook the cartridge with the case. Press downwards and turn the handle 90 degrees clockwise direction. Extract the fuse 150 mm (6 inches) approximately and allow the oil to drain before completely removing it. Use a 3/4”and a 1/2” wrenches to remove the connector from the end of the removable cartridge. Version 3 © 2021 Siemens Energy 12 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers To replace the removable current-limiting fuse from the outside, it must be do it in the next way: a. Place the radial disconnector in the open position to de-energized the transformer and unlock the fuse holders. b. Release the internal pressure of the transformer pulling the ring of the pressure relief valve. c. Place the switch hook stick and hooked to the fuse holder. The fuses must operate within their nominal values. The spare fuses must be of the same voltaje and equivalent time-current characteristics to the original fuses. d. Pull until completely take out the fuse. Current-limiting fuses f. It is a fuse with high breaker capacity and it can be of complete or partial coverage according to the specified requirements. It operates in case of an internal failure of the transformer or in case of high currents in the primary side to protect the distribution system or the power supply system. The internal partial range current-limiting fuse is used in conjunction with a low current interruption device, as well as a protective fuse link or bay-o-net fuse. It is installed in the inside of the transformer and can be replaced through the handhole or through the main cover, consequently the diagnosis, device repairing and fuses replacement, should be in a specilized workshop. The partial range fuse is designed to clear low impedance (high current) failures, with the expulsion fuse clearing all the high impedance and overcharge failures. e. Replace the fuse with a new one with the same characteristics. Insert the fuse in its place again, pushing until the correct position. Insulation fuses In some transformers this fuse does not have the interrupter capacity, which always goes in series with the expulsion fuse, designed to protect the operator from re-energizing a transformer that has a fault whose current is greater than the interrupting capacity of the current-limiting fuse. When this fuse is operating, it indicates that the transformer has an internal failure (principally in the windings) and that it is necessary to repair it in a specialized workshop. Review the instructions of the manufacturer of the fuse that is being used. Thermomagnetic circuit breaker (opcional) The complete range current-limiting fuse can be installed in the inside of the transformer and in that case, it must be replaced in the same way as the partial range fuse. There is another type, that is installed in the fuse holder and can be replaced from the outside, in this case, there is a mechanism that not allow to take out the fuses unless the radial switch disconnector of the transformer is open. Version 3 This device is used to protect the transformer against the raising of the oil temperatura induced by the overload and the instant shot to protect the external shot circuit. It can be thermal or thermomagnetic, immersed in insulated liquid, and it is connected internally by the secondary side or transformer low voltage. The swtiches are operated from the outside by using a handle and they are operated by a switch hook stick. © 2021 Siemens Energy 13 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers The operation handle has three positions: open, reset and close. To open the switch, the handle must be in the open position. To close the switch when this is being operating by overload, the handle must be in the open position and then in the close position. Aditionally, it has a light that indicates the overload and a handle to control emergency overloads. The function of the indicator light is to prevent the users from an overload. The light will turn on and remain in that state even if the overcharge disappears. Before energizing or applying voltage to the transformer, turn the tap changer to the desired voltage position. The position marked correspond to the primary voltages marked on the tranformer nameplate. The unit is delivered from the factory with the tap changer in te nominal voltage position, defined in the nameplate (standard execution), the typical configuration has 5 positions marked as 1, 2, 3, 4 and 5 or A, B, C, D and E. Every position changes a percent of the transformation ratio from the primary to the secondary voltage, this change can alter the secondary voltage in this increase. The tap changer positions set at 2.5% are usual but not essential. Other percentages can be provided if it is requested. To elevate the secondary voltage, move the tap changer to the position 4 (D) or 5 (E). To reduce secondary voltage, move the tap changer to the position 1 (A) o 2 (B). Tap changer Before operating the tap changer make sure that the transformer is out of operation. It is possible to equip the windings with exits to a tap changer or commutator, to adapt the transformer to the network voltage. That tap changer modifies the voltage tranformation ratio between the primary and the secondary voltage to adjust the open circuit voltage in the secondary side. All the transformer commutation lines are subjected to verification against short circuit and are manufactured to be duly insulated under the work voltage levels. To change the voltage position, follow the steps below: a. Make sure the transformer is de-energized. b. Unscrew the fastening screw until it is no longer in contact with the hole. c. Place the operaction handle in the desired position. If the tap changer is used to adjust the voltage to a voltage higher than the nominal one, it will produce a high level of noise in the transformer, besides the increase of the losses in the core. The tap changer comes with an operating handle, a position change indicator and in some cases, with a a provision for Padlock. Version 3 d. Tighten the fastening screw again to minimize the possibility of accidental movement. e. Carry out transformation ratio tests once the work on the tap changer has been completed. Some large units are provided with a tap changer in the supply transformer which require the removal of a locking pin and the total rotation of the handle for every change position. © 2021 Siemens Energy 14 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Pressure relief valve The pressure relief valve is located at the upper part, above the liquid level. The device is screwed to the tank wall to facilitate its intallation or removal. The valve opens automaticall the gas internal pressure increases from 8 to 10 psi. Once the pressure has reduced, the device closes automatically. To manually reduce the internal pressure, put an insulated stick in the extraction ring of the valve and pull gently. This is not a protection device against sudden overpressure. Follow all the suitable guidelines to the grounded of the transformer. Make sure to do the correct ground connection. An incorrect ground connection may cause energization in the tank. Not following this instruction may cause accidents. Vacuum pressure gauge (optional) The vacuum pressure gauge located near the upper part of the transformer, above the liquid level, indicates if the air chamber in the transformer is under pressure or vacuum. This accesory is normally calibrated in PSI. The indicator readings should vary according to the change in the tranformer temperature and should indicate normally positive pressure. Do not expect that the instrument indicates exact readings near zero point. The lack of readings under any change of temperature is a sign of leakages in the transfomer seal and must be investigated. Optionally an overpressure valve can be provided with tripping contacts which in case of a major failure take out of service the transformer. The tripping contacts just can be recovered manually. Drain and oil sampling valve On the lower part of the tank it is located a Ø1” bronze drain valve with plug and with an incorporated device of 3/8” to take oil samples. Ground Pads or screws There are metallic pieces that are welded to the tank to make the physical ground connection, these must be free of paint or grease to avoid fake contacts, also they must be permanently connected to the ground system. Pressure readings between ±5 psi are considered normal as long as exist a variation in the readings of the changes of liquid level. A pressure greater than ±5 psi can be drecrease dropping the pressure relief valve. Nameplate In accordance with IEEE Std C57.12.00, a nameplate is supplied with every transformer. To know the capacities and proper connections of the transformer to the system it is necessary to check the nameplate. None of the internal conections should be do it inside of the transformer unless it is indicated in that way in the nameplate. Version 3 © 2021 Siemens Energy 15 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Insulating liquids The insulating liquid of the transformer has the functions to refrigerate the active component inside the tank, insulate the parts with different voltage and conservate out of oxidation the metallic parts inside the transformer. Basically, there are use various types of oil, like mineral oil, silicone oil and vegetable oil. The dielectric strengh of the insulating liquid must be maintained at high levels. It is recommendable to take samples of the liquid and test them after ther first days of operation. After that, it is recommendable to take samples according to the maintenance guidelines. Keep exact records of the tests and liquid replacements. Approved and recommended oils to Siemens Energy Transformers are those that fulfil the ASTM D 3487 and the IEC 60296 standards. For the manipulation and storage of the insulating oils for transformers it is necessary to check the manufacturer guides and recommendations. Mineral Oil Mineral dielectric oil are petroleum fractions that in its composition own pure low volatility hydrocarbons, of naftenic or parafenic predominant nature, free of polar compounds. Within its characteristics: not corrosive for iron transformer metallic parts – copper, low solubility for painting and varnishes found inside the transformer, chemically inactive for dielectric paper cellulose and compatible with other mineral dielectric fluids. They are available in inhibited or not inhibited form. Inhibited mineral oil are submitted to artificial aging, which allowed them to present an excellent resistance to aging. Uninhibited oils aged in a controlled and predictable manner under constant effort. Version 3 Recommended periodic maintenance tests for mineral oil include: a. Dielectric strengh according to ASTM D1816 standard. b. Fire and flash points. Measured based on ASTM D92 standard. c. Dissolved gas analysis. May be applied following ANSI/IEEE C57.104-1991 guide for detection and generated gases analysis, excluding proportion methods. d. Dissipation factor tests, neutralization number and interfacial tension provide a good indication of possible contamination or unusual degradation. According to ASTM D924 standard. Vegetal Oil (Optional) Offer an excellent environmental compatibility and are preferably used in applications with strict environment requirements. Its formulated based on vegetal oil and edible additives. Not containing petroleum, halogens, silicon or any other pollutant material for the environment. Easily degraded in soil or aquatic ambient. Compatible with constructive, conductor and insulated materials of a transformer. Within offered characteristics, is fire resistant, high flash and fire point, not toxic and biodegradable. Must avoid mixture with other mineral or silicone oil, due to negative impact in characteristics with environment, of fire security and fire point decrease. Miscible with mineral oil but not with silicone oil. Storage, transportation, sampling and filtration equipment used must be exclusively use for this oil and must remain cleaned. Can be transported with metallic drums or plastic containers with nitrogen or inert gas space. Same basic procedures for storage and oil manipulation of conventional transformer must be used with vegetal fluid. In order to help maintaining saturation percentage extremely low, in fluid fabrication moment, its recommended that air exposition time be as minimum as possible. Drums and containers storage should be in interior or exterior protected from outdoors. Maintenance periodic tests for vegetal fluids should observe same programming used for fully transformers with mineral oil of transformer. © 2021 Siemens Energy 16 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Silicone oil (optional) It is a selected fluid to reach optimum heat transference and fire-resistant properties balance. Due to viscosity inadequate and reduced environment compatibility, silicone oil is only used by customer’s expressed request. Within offered characteristics, high electric stregh, low temperature fluidity, high flash and fire point. Materials in contact with this fluid have been selected for transformers fabrication reason why should not be substituted with Siemens Energy Colombia prior authorization. Silicone oil can be treated in containers, barrels or grease free hose, oil or material that contaminated the fluid, all equipment used for storage, transportation, sampling or filtration should be used exclusively for this oil. Use kerosene or another approved solvent to remove all traces of Silicon fluid on the outside of the transformer since silicone oil can affect the adhesion of paint layers. Tank It is designed in cold rolled (CR) or hot rolled (HR) sheets for thicknesses up to 7/64” (2.5mm) or 5/16” (8mm) respectively, according to ASTYM A-36. The design has structural reinforcement to support absolute vacuum and internal pressures up to 14.7 psi. Radiators The transformers are equipped with radiators which help to transfer the heat generated by the transformer to the environment. The radiators are commonly fixed (welded) to the transformer, however they could be provided detachable. Surface Proteccion Paint schemes and surface coatings used in the Siemens Energy Colombia are according to Std. ISO 12944-2 for all kind of environments in function of the corrosion degree. Version 3 The following describes the surface protection schemes used in Siemens Energy Colombia. The customer must identify the level of protection requested in the order. Classification Siemens Energy ISO 12944-2 Type 1 C1 Type 2 C2 & C3 Type 3 C4 High (industrial and moderated salinity areas) Type 4 C5 Very high (industrial, aggressive atmosphere and high salinity areas) (Offshore) CX Very high (naval, very aggressive and high salinity atmosphere) Corrosion degree Very low Low and Medium Sensformer® Connectivity Device* The Sensformer Connectivity Device is the data acquisition unit, which collects analog and digital data from the transformer and publishes to the management software. The Sensformer Connectivity Device is not a controlling solution, the provided data shall not be the base of control-, or management decisions regarding the transformer or the power system. The device is not replacing conventional safety and security solutions. For critical operations always rely on data from multiple sources. The Sensformer Connectivity Device uses high voltage, failure to comply can result in an accident. As all of electric devices, the Sensformer Connectivity Device has a few installation requirements. The device may only be installed in accordance with these instructions. Do not mount the device under voltage. Risk of electric shock! Above and below the installed device must be get at least 50 mm free space because of the suitable © 2021 Siemens Energy 17 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers ventilation. The device does not require other ventilation. High voltage and warming devices cannot be placed closer than 50 mm for the Sensformer Connectivity Device. The device must be only used at operating temperature. Minimum temperature rating of the cables to be connected to the field wiring terminals is 80 °C. Use copper conductors only! The MAINS field-wiring leads shall not be more than two standard wire sizes smaller than the copper conductor to which they will be connected. Also the field wiring leads must not be smaller than 18 AWG (0,82mm2) The Sensformer Connectivity Device requires the PE (protected earth). Not allow to use the Sensformer Connectivity Device without PE. The using PE cable must be green - yellow. The used cables on the digital inputs and power supply must be certified, double insulated and must have UL 94 V-1 flammability classification and VW-1 flame rating. The used cables on the analog inputs, pt100 input and RS485 communication port must be certified, double insulated and must be UL 94 V-1 flammability classification and VW-1 flame rating. In case of digital inputs and power supply, the used cables must have ferrules. Do not use cables without ferrules about digital inputs and power supply. The used ferrules must be certified, 1.5 mm2 conductor area with 16-18 mm overall length and 8 mm pin length. For the other ports, the used cables must have ferrules. The ferrules must be certified, 1.5 mm2 conductor area with 14 mm overall length and 8 mm pin length. Do not used cables without ferrules about the analog inputs, pt100 input and RS485 communication port. Degree of protection: Indoor use only Type of mounting: DIN rail Dimensions: 156 mm x 85 mm x 58 mm Weight: 555 g (with antenna) Operating ambient temperature: -25 °C -70 °C Humidity: 0.95% relative, non-condensing Pollution degree Pollution degree 2 Overvoltage category: Overvoltage II Common specifications Power supply 100 – 240 VAC 50/60 Hz Power consumption < 15 VA Communication interfaces: o Ethernet (10 Mbit / 100 Mbit) o mini USB 2.0 (not used) o RS485 (ModBus) Inputs: o 3 x Analog input: 4-20mA DC (active or passive) or ±20mApp AC (passive) o 2 x Digital input o 1 x PT100 input (3-wire) Antenna connectors: o 1 mobile communication (SMA female) o 1 GPS (SMA female) Measurement resolution: 12 bit *If is Sensformer®, apply terms and conditions The following information describes the general technical parameters of the Sensformer Connectivity Device. Physical parameters Version 3 © 2021 Siemens Energy 18 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 3. Reception These instructions apply for transformers made in Siemens Energy Colombia, it is important to read the security section in this instruction book. All transformers, components and accessories are subjected to rigorous quality tests before leaving the facilities. Despite all the actions made, any damage during transport can occur. When the transformer is received, the costumer must take a general inspection and inform immediately to Siemens Energy of any type of damage that may have occurred during shipping. The customer must carry out a general inspection of the transformer at the time of reception in order to confirm the optimal external condition of the equipment or, failing that, report any obvious difficulty (impacts, scratches, oil leakage, etc.), at the moment of receiving the equipment, it is necessary, if the accessory is assembled, to verify that the Indicators or impact recorders have not acted, in case of identifying it, it is necessary to leave the observation in the transformer remissions. Shock indicator / impact recorder This accessory allows to record the magnitude of the accelerations presented during transport. If an acceleration above 2g is recorded, Siemens Energy recommends to make a detailed inspections and tests to the transformer”. The Shock indicator / impact recorder inspection is mandatory and must be done before installation and transformer stat up. Drawings and documents All the shipping documents, packing list (if applicable), general arrangement drawings, nameplates drawings, electric control cubicle drawing (if applicable) and instruction books must be review. Also, the reception of all the accessories of the transformer must be checked. Version 3 General arrangement drawing: In it the dimensions, weights and accessories of the transformer are related. Also, it can be seen the location of the nameplate and accessories and the type and function of the transformer. Nameplate: This nameplate lists the capacities of the transformer, vector group and weights of the transformer. No internal connection which is not listed on the nameplate should be made in the transformer. Control cubicle drawing: Provides detailed information on the control arrangement and connections. Do not remove or modified the nameplate from the transformer. External inspection a. The tank and radiators must be inspected searching for any kind of damage. If any dents or scratches are found, these may be corrected on site and/or by paint retouching. b. Check the transformer to make sure there are no oil leaks on the surface, welded joints, low and high voltage bushings and on the bottom of the transformer. If you find any, carry out a visual inspection to determine if there is a oil leak. Small leaks can be repaired on site. c. Check the transformer for any broken or cracked bushing and for any missing or damage component sent separated. d. Confirm the information present in the nameplate to ensure that it complies with the design requirements. The voltage, power, impedance and others design characteristics must agree with technical specification. e. With the signature of the delivery document, the costumer (or its agent) accepts that there is no damage on the transformer when it is received. © 2021 Siemens Energy 19 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Tank pressure- Tightness Internal inspection For transformers equipped with a pressure-vacuum gage, at the moment of receiving the equipment it should be checked if it is indicating positive or negative pressure values. This indicates that the transformer is perfectly hermetic, if it indicates zero or a constant reading with variable temperatures, it may be that the tank has a leak, however, the indication of a value of zero can happen by chance. In most cases, it is not necessary to perform an internal tank inspection. This is only required if there is an obvious indication of damage due to impacts during transport. The tank is sealed to avoid contamination of the oil. The accumulation of moisture decreases the properties of the insulating oil. If it is zero or constant at variable temperatures, the tank should be pressurized with dry air between 3 and 4 psig, the tank should be left under pressure for a period of one or two hours, after this period it should be examined if there are leaks or loss of hermeticity. Leaks above the liquid level can be detected with the application of a solution with soapy water in the welds, joints and pipe connections. If at the end of the test no loss of pressure is seen, the transformer must be pressurized at 1 psig (or according to the general arrengement drawing) at the installation site. If an internal inspection is required, the activity must be performed by qualified staff and in adequate facilities with a controlled environment to prevent further damage to the equipment. The internal inspection typically consists in a visual inspection documented with photographs and will be focused on the items below. Also, the internal inspection must be done with a relative humidity less than 70%. Visual status of the windings: it must be checked that there are no abnormal displacements or any dent or scratch due to any conductor loose during transport. It will be reviewed the general status of its insulation. Oil level inspection Fixing system: it consists in all the components which fix the active part to the transformer. It must be checked that there are no displacements or loose items. The transformer is shipped with the correct oil level for operation. The oil lever must be checked when the transformer is delivered. Visual inspection of the core: it must be checked that there are no displacement of the laminated core sheets and its geometry and shape must be perfect. If any equipment does not have the proper oil level, it must be reviewed looking for any leak and then refilled before commissioning. It must be only filled with the liquid specified on the general arrengement drawing. Laminated wood or pressboard supports: it must be checked their general status, there must be no bending, broken or loose component. ELECTRIC SHOCK RISK, EXPLOSION HAZARD OR ARC FLASH HAZARD Do not energize the transformer if the fluid level is low. Keep the proper fluid level when the transformer is energized. Failure to follow this instruction may result in damage to the equipment, serious injury or dead. Version 3 Conductors: The state of the insulation will be verified, which must be in perfect conditions, it will be observed that there are no folds or bends that damage the insulation and its correct location in the respective supports. The arrival of the conductors that go from the windings to the tap changer must be verified paying special attention to the points of assurance (generally bolted), verifying that there are no loose points. If any issue is found during the inspection, it must be informed to Siemens Energy. If the internal inspection is made, then the instructions included in the installation chapter must be followed, transformer opening in this instruction book. © 2021 Siemens Energy 20 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Shipping When the transformer is located on a vehicle, it must be according to its gravity center and weight, avoiding any movement by securing the transformer. Inclination above 15° degrees during transport may result in the overturning of the transformer. All the components that hang over the transformer must be protected to avoid damage during transport. The velocity of the vehicle must be controlled according to the conditions of the road in order to avoid internal damage in the transformer and acceleration above 2g must be avoided. Version 3 © 2021 Siemens Energy 21 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 4. Manipulation The use of the lifting lugs to fix the transformer during transport is mandatory. A lifting sling can be attached to these lifting lugs and a rubber protection for the paint of the lifting lugs must be use if chains are used. Lifting of the transformer All the transformers are provided with lifting lugs, that can be used with lifting slings and cranes. It is important to avoid hitting the tank or radiators with the lifting slings, as these impacts may damage the transformer paint and even deform the components or generate leaks. When it is used a single fixing point, the maximum angle between lifting slings is 60 degrees, observed from the frontal or the side view. If the lifting slings are at least as the longest dimension of the transformer, then the angle cannot exceed the maximum value. There must be a lifting plan in other to move a transformer. Lift the transformer by crane using the 4 lifting lugs provided for this purpose. Use an equipment with enough capacity for the loading, unloading and handling of the transformer. Ensure that all the staff keep a safety distance while the transformer is being moved. The transformer must be handled in its normal vertical position to avoid internal tensions in the active part and the generation of internal turbulence, which may create air bubbles in the windings. This could cause serious problems when the transformer is energized. The weight of the transformer is listed on the nameplate. There must not be inclinations during lifting above 15° degrees from the vertical axis. Version 3 © 2021 Siemens Energy 22 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Forklift The wood base on which the transformer is shipped can be used to move the transformer with a forklift. This base provided additional protection for the transformer, so it is recommended to leave the transformer on its base until it reaches the installation site. Lift the transformer with jacks using only the jacking Pads (verified if the transformer is equipped with jacking Pads, these components are not usual for low voltages.) For lifting with forklift, it must be verified the working load of the forklift. Do not allow the transformer to be directly dragged over the floor as the cabinet could suffer deformations or the paint could deteriorate resulting in corrosion. You can slide the transformer on rollers. Without any reason move the transformer using an air terminal chambers or a control cabinet as a fixing point. Only use the components designed for this purpose. Pulling Some transformers are equipped with pulling holes. Do not drag the transformer form the radiators or cabinet. Neither invent dragging points to move the transformer. Jack Some Transformers are equipped with supports for jacking Version 3 © 2021 Siemens Energy 23 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 5. Storage The transformer must be storage completely assembled (Sealed tank and closed cabinets) as if it were energized on in its permanent location. The transformer must be stored on a solid and level surface. It must be done a regularly inspection of the transformer just like a transformer in operation. Check the transformer looking for oil leaks and guarantee tightness, it is recommended to storage the transformer with an internal pressure between 2 or 3 psig. and other elements allowing a correct air flow for cooling. Long time storage It is necessary to built oil colleting pits according to the national standards where it will enter into service. If the transformer will be stored for more than 1 year, it must be storage on a solid and a lever surface, with its total amount of oil. Also, it is recommended to pressure the tank between 2 or 3 psig if the transformer is sealed tank. This will prevent moisture from entering to the transformer. It is necessary to have an easy access to the nameplate, protection equipment and to the indicators. The concrete base must be able to drain water from rain. A failure on the transformer may lead to fire or explosion as the transformer is filled with flammable liquid. This possibility must be considered when the transformer is located near public buildings or roads. Avoid locating the transformer in highly corrosive areas. If the transformer has been subjected to the recommended inspections, then the transformer will be ready for service at any time. It must be prevented the humidity in the tank replacing the aire dryer when it is fully of humidity. All the accessories which remains in its wooden protections must be protected from the environment and storage in an indoor area. Keep in mind the local and national regulation when the transformer is installed, and the handbooks of all the components used. The cabinets must have their heating resistors energized to avoid water condensation inside the cabinets. If it is requested additional information for the construction and dimensioning of the installation locations, as dimensions, distances between fixing holes, location of cables entries or losses of power, then Siemens Energy will provide it. Location If the transformer has wheels, then the wheels must have wheel breaks. The transformer must be mounted and leveled on a smooth concrete base, sufficiently large and with enough load capacity to support the weight of the transformer. The minimum clearances according standards must be fulfilled for transformers without air terminal chambers. If the transformer is not correctly level, then the fluid may have flow and cooling problems, generating overheating on the transformer and reducing its lifetime. The location where transformer will be installed must have good ventilation and easy access for inspection. The transformer must keep enough distance with walls Version 3 It must be checked any damage in the protection against corrosion (paint coat) after the transformer is installed, specifically in the lifting lugs and pulling holes. The costumer is responsible for the installation unless otherwise is specified © 2021 Siemens Energy 24 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 6. Installation Before energization Do NOT disconnect the main ground connection of the transformer. At least the following checks and tests must be done to ensure the transformer is ready to be energized. It is recommended doing the following test before connecting the transformer: 1. Every task must be done by qualified personnel with enough knowledge and experience about transformers. Also, the personnel must be familiarized with the standards, codes and laws of prevention of accidents according depending on each individual case. Insulation resistance measurement: This test measures the electrical insulator resistance between the primary windings and the secondary windings, or between the windings and ground. This test is only made to check that the components are isolated with each other. The results may be affected by different factors such as voltage of the generator, humidity, how clean are the porcelain bushings or temperature. Specialized personnel must assess the results. If there are good condition to make the measurements, a reference value could be 1 M/KV (Reference value is the service voltage of the measured terminal). This test must be done with the transformer disconnected from the electricity network. Verify that transformer is installed following the local regulations about housing or fencing to prevent access of non authorized persons. Mega-ohmmeters with voltages of 2.5 kV or 5 kV must be used as far as possible for the measurement. This test voltage (DC) must be less than 0.75 x low frequency test voltage (AC) Test on site 2. DANGER OF ELECTRIC SHOCK, EXPLOSION OR ARC FLASH. Only specialized personnel must carry out these tests. Disconnect all high voltage, low voltage and neutral connections. Disconnect auxiliary equipment, such as arresters, temperature control system, measuring equipment and any other low voltage control system connected to the windings which will be used in these tests. Version 3 Transformation ratio test: This test measures the relation between the primary and secondary transformation. This test is needed to verify that the tap changer, their connection and the coupling of the drive are still working after shipping and installation of the transformer. The transformation ratio must be comparable and fulfill the tolerances according to the standards against the factory values. In this way it is possible to verify that the voltage is constantly changing and without interruption from the maximum number of turns to the minimum in correspondence with the taps. In general, tap 1 corresponds to the maximum number of turns. © 2021 Siemens Energy 25 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 6. 3. Core grounding (if the core has an external connection through a terminal box): This test is needed to verify the insulation between the core and the clamping frames is in good condition after shipping. This test is used to prove the correct status of the internal connections of the windings. As the current in the circuit is ohm-inductive, then it is mandatory to wait until the values of voltage and current stay constant to measure the ohm component. It must be used equipment designed to measure inductive loads. Inside the terminal box, the test is made in the bushing with an insulator resistor measurement device with a constant voltage maximum of 1000 V for 1 minute. 4. Oil test: It is made to evaluate the dielectric strength, power factor and moisture content. The minimum values for dielectric strength for new oil before the transformer energizer are according to IEEE Std C57.106-2006 table 2. The following tests oil can be made to an oil sample: Flash point (°C) Moisture (ppm) Dielectric strength (kV) Power factor (%) Neutralization number (mg KOH / g) Aniline point (°C) Particles/100 ml Inhibitor content (% mass) Acidity Color Specific gravity Visual For any question about these tests contact Siemens Energy. 5. Leakage test: if the pressure-vacuum gauge indicates a zero value, then the tank must be pressurized with dry air between 3 and 4 psig during 1 or 2 hours. Then is necessary to check for any leak in the transformer. If at the end of the test no loss of pressure is seen, the transformer must be pressurized according to the general arrengement drawing. According to ASTM D 3283-98 which define the composition and characteristics of the dry air used as insulator gas, the air must have at least 20% of oxygen with less than 30ppm of humidity and dew point under < -52ºC. Version 3 Winding resistance test: this test verifies the continuity of the windings, measures the resistance of the windings must be compared with the factory results. Keep in mind that the values must have a correction according to the temperature of the oil. 7. Polarity and current transformers ratio (if applicable): keep all the test records made and the traceability of the equipment used, they will be requested for investigation in case of any inconvenient with the transformer Points to check before energization It must be made a complete inspection before the transformer energization. Verify all the components are working. Before energization keep in mind the following: Electrical connections During installation, it is recommended to make the ground connection first, then the low voltage connections and finally the high voltage connections. If the connections are made opposite from the recommendations, the transformer may put out of service. Carefully, review the nameplate to know the maximum capacities. Avoid overloading the terminals or the bushings, this can damage the contact joints, leading to oil or gas leaks. The connection of the transformer must be done by specialized and qualified personnel. Take the following point into account for the connection of the transformer: © 2021 Siemens Energy 26 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers The electrical connection to the transformer can be made through the bushings, using cooper bars or terminals. It must be used supports for all the connections. If there is not a good support for the connections, then the bushings will be loaded and may damage them. It is necessary to secure all bolted connections to prevent them from coming loose during operation. It must be tolerated the bending radios of the cable according to its manufacturer. If the transformer has installed bushings, then it is not recommended to loosen them, they will lose the factory torque. Check all the electrical connections made on site. Remove all the temporal clips on electrical devices. Check all the accessible connections and ensure they are tight. Check that all the primary and secondary connections are connected. If there are connections devices to the transformer, then make sure their status before starting up. Ensure that all ground wiring have been carried out correctly, this include the grounding of the tank, the air terminal chambers to the tank, conservator, arresters, accessories and control cabinet. Check the wiring carried out on site. Make sure it does not touch any live element and it tolerate the fault currents. Read and follow the instructions of the manufacturer to install the high voltage connectors. Check all the network and device protections were verified and they are according to protection coordination study and the standards. Version 3 Do NOT modify the transformer, tank, air terminal chambers or control cabinet. Ground connections Always connect the tank to the ground through the grounding Pads located near the bottom of the tank. It is crucial an excellent and a constant connection to the ground for provide protection to the tank and air terminal bushings and prevent damage caused by internal failures or overvoltage due to lightning. The transformers are designed to use a Y connection to the ground, that is, a system in which there is a solid connection to ground. The transformer must have all the neutral connections constantly available and rigidly connected to the main neutral system before energizing the transformer. Follow all the grounding connection instructions of the transformer. Verify to make a correct ground connection. An incorrect connection may result in the energization of the tank. Failure to follow this instruction may cause accidents. Tank Check the transformer looking for any leak. If any leak is found, this must be fixed before energizing the transformer. Also, the level of oil must be verified. Inspect the transformer looking for any dent or scratch in the paint coat, specifically in the lifting lugs and the pulling holes. Check all the bolted connection If the transformer has removable radiators, they must be purged. © 2021 Siemens Energy 27 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Tap changer It must be checked the position of the tap changer. The chosen position must match with the actual network voltage. The positions needed according to the network voltage can be found in the nameplate Cleaning Inspect all the insulator surfaces looking for dirt or moisture, including the support insulators and the primary insulation barriers. If necessary, clean the surfaces using a clean cloth Remove all the dirty and any other particles which do not belong to the bushings before energizing the transformer. Oil level Do NOT operate or apply a voltage to the transformer if the oil level indicator shows “LOW OIL”. Verify the oil level before energizing the transformer. Tools Verified to take out all the tools after finishing the work. Basic tools for installation of the transformer: Version 3 1 drive socket set. 1 metric ratchet wrenches set (624mm). 3 adjustable wrench set (6-10 -12 inch). 1 screwdriver set of 6 pieces. 1 Screwdriver Phillips set of 6 pieces. 1 diagonal cutter plier 1 nose cutter plier 1 side cutter linemans pliers 1 locking pliers 1 rubber hammer. 1 flat face hammer 1 solid frame for hacksaw 2 hacksaws 1 measuring tape 1 Pipe wrench. 14”. Heavy duty. 1 Toolbox. 1 Non-metalic ladder 1 torque wrench. 25-550 Nm 1 Current clamp meter. 1 multimeter 1 digital thermometer. Dry air devices. Fire extinguisher near the transformer. (maximum 5 meters away) Activity schedule 1. Starting meeting. 2. External inspection. 3. Cleaning and paint coat restoration of the tank and accessories used in shipping. 4. Verification of all the boxes with their gasket list. 5. Wheels assembly (if applicable). 6. Radiators assembly (if applicable). 7. Bushings assembly (if applicable). 8. Conservator and compensator assembly (if applicable). 9. Air terminal chamber assembly (if applicable). 10. Pipe assembly (if applicable). 11. Oil level revision and adjustment if necessary. 12. Oil tests. 13. Oil treatment (optional). 14. Leakage test. 15. Accessories and wiring assembly. 16. Alarm and firings test. 17. Final paint coat restoration. 18. Electric test. 19. Commissioning – Energization This transformer was designed, built and tested according to the last version of the standards ANSIAmerican National Standards Institute, Instituto colombiano de normas tecnicas” or any other standards according with the costumer. If the transformer is operated outside its power limits, the lifetime of the transformer is reduced (see IEC 60076-7). © 2021 Siemens Energy 28 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 7. Commissioning Check the primary voltage is correct and then energize the transformer. It is important to know that considerable values of current are generated when the transformer is energized, due to the core magnetization, thus, the protection response must be settled up to consider this transitory effect. If the voltage is not the appropriate, then check the primary voltage, use the tap changer to modify de voltage. Follow these instructions if the voltage is appropriate: 1. Check the oil and winding thermometer (if applicable). Record in time intervals (every hour) until stabilization. 2. Track de room temperature. 3. Make sure there is any effect of a partial discharge in the high and low voltage terminations. 4. Look the behavior of the transformer when it is energized for the first time and in the first hours 5. Make a periodic verification to the voltage to prevent the transformers works overloaded. 6. Listen the noise made by the transformer and ensure it is not above the standards. The test must be done according to the instructions of the device used or the test made. Furthermore, the companies that carry out the installation activities must show, to supervisor of Siemens Energy (If applicable), all calibration certifies of the equipment used. Also, the companies must present an inform showing all the activities done, tests made and their protocols. All these documents must be available to guarantee a good performance of the transformer. The transformer is ready for service. However, carefully observe the transformer (particularly in low environmental temperature areas in which case it is recommended to charge the transformer gradually) during the first hours after the load is applied. The following are some recommended actions: Do not operate the transformer beyond its maximum load according to the manufacturer. The transformer is an important component of the distribution system and should be evaluated the option of add protections against disturbances on the electrical system. It should be protected against instant voltage oscillations and overcurrents. To allow the correct operation of the protection devices against overrecurents that may be provided with the transformer, it is necessary a coordination study of the protections. Devices used in the electrical test for commissioning Multimeter. Version 3 Device to measure the winding resistance in transformers. Device to measure the insulator resistance in a transformer ((5 kV, > 100 G). Power factor measurement device. Transformation ratio measurement device. Current transformers measurement device. Oil Dielectric strength measurement device. Digital thermometer. Current clamp meter. Check the load, the oil temperature and the winding hot spot, recording data every hour until stabilization. Check for noise and vibration overload. Verified the gas detector (if applicable). It must be taken an oil sample before energization to made physical-chemical tests and a sample for a gas chromatography. After 24 hours it must be taken another sample for gas chromatography. For this test, please do not hesitate to contact Siemens Energy. The interpretation of the results must be according to ANSI C57.104 or IEC60599 for mineral oil or IEEE C57.155 for natural ester and considering the oil volume in the transformer. It is not needed to increase gradually the voltage using a generator. After all the inspections made, it could be connected directly. High insulaton stresses in the high voltage windings can be generated by disconnecting the transformer when it is in rush period (right after its connection). © 2021 Siemens Energy 29 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Only specialized personnel must energize the unit. Follow safety recommendations according to local regulations and network operator regulations. Keep personell at safe distance from transformer during energization maneouvers. If exist, energize transformer from control room. The cold start procedure must ensure that the transformer is heated up slowly, to avoid overheating of the windings until the cooling equipment can work effectively. Thus, during the heating up process, observe the top oil temperature till the coolers are heated up as well. At the beginning, the cold start procedure shall be at no-load or reduced load (refer to table below). During the heating up process; prevent overheating, the top oil temperature shall not exceed maximum temperature limits. The transformer can be fully loaded when the liquid circulates through the coolers (coolers get warm). Energizing of the equipment is not allowed below a minimum liquid temperature of: DANGER OF ELECTRIC SHOCK, EXPLOSION OR ARC FLASH. Only specialized personnel must energize the unit. If a trip occurs on energization or during operation of transformer, its condition must be evaluated by electrical testing. Before re-energization the cause of the initial trip must be corrected or eliminated. As it is possible that a disconnection occurs immediately after the connection, originated by an erroneous operation of a protection accessory (eg differential relay, overcurrent-time protection relay, remote protection relay, etc.) the connection must be initiated with the minimum possible induction. This means that the maximum number of turns on the highvoltage side to be connected is connected. If, in spite of this, disconnection occurs, reconnection must be attempted after the cause has been eliminated, in order to minimize the number of connections. Follow procedure stated on “IEEE C57.125 Guide for Failure Investigation, Documentation, and Analysis for Power Transformers and Shunt Reactors". Cold Start Procedure Liquid Typical pour point of liquid [°C] Mineral oil, arctic grade Mineral oil, standard Synthetic ester Natural ester Energizing: Heat up Minimum slowly below liquid [°C liquid temperatur temperature e [°C] ] -60 -50 -20 -45 -40 -20 -50 -40 -10 -20 -10 0 Additionally the switching operation of tap changer is not allowed at very low temperature due to mechanical reasons. Liquid Typical minimum temperature for tap changer switching operation [°C] Mineral oil, arctic grade -35 Mineral oil, standard -30 Synthetic ester -18 Natural ester -10 If a transformer is energized at very low temperature, special care is required mainly due to the high viscosity of the insulating liquid at low temperature. Depending on the type of insulating liquid the permissible minimum temperature for energizing varies. Version 3 © 2021 Siemens Energy 30 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 8. Operation After the energization a completed copy of the energization protocol must be sent to the factory through the corresponding Siemens Energy sales office. Operating conditions. The transfomer is suitable for operation at nominal power under the following usual operating conditions.1 Any other condition than those described herein represents an ununsual operating condition that must be consulted directly with the equipment manufacturer. The voltage waveform of the transformer power supply must be approximately sinusoidal and the phase voltages that feed a polyphase transformer must be equal in magnitude and frequency. Load current. The load current must be approximately sinusoidal, the harmonic factor must not exceed 0.05 per unit (unless this condition is established in the initial design stage in the design of the transformer). The definition of the harmonics factor is established in the IEEE Std C51.12.80-1978 standard. Operation above nominal voltage or below rated frequency. Temperature. Air temperature. The Transformers must be capable of: For cooling conditions where the cooling medium is air, the ambient temperature should not exceed 40°C, and the average temperature of the cooling air for a term of 24 hours should not exceed 30°C. a) Operate continuously above its nominal voltage or under its nominal frequency, at the maximum power in KVA for any tap, without exceeding the observable temperature rise limits, when all the following conditions prevail. 1) The secondary voltage and the volts per hertz do not exceed 105% of the nominal values. 2) The power factor is greater than or equal to 80% 3) The frequency is not less than 95% of the nominal frequency. Lower limit of the coolant. The coolant temperature should not be lower than 20°C, temperatures below this level are considered equivalent to an unusual operating condition. Altitude of the installation. In general, the installation altitude should not exceed 1000 meters above sea level, check the nameplate to verify if the design of the transformer is suitable for operating at higher altitudes, since the operation at higher altitudes means a revision of transformer isolation levels and the refrigeration conditions of the same. In general terms, operating a transformer at an altitude greater than the design altitude means that its operation must be restricted in terms of power supplied. Voltage supply. Capability. b) Operate continuously above the nominal voltage or under the nominal frequency in a tap without load, without exceeding the observable temperature limits, when neither the voltage nor the voltages per hertz exceed 110% of the nominal values. Maximum continuous operating voltage of the transformer. The maximum continuous operating voltage must not exceed the limits specified on the nameplate of the transformer. IEEE Std C57.12.00 -2000 Standard general requirements for liquid immersed Distribution and Power Transformers. 1 Version 3 © 2021 Siemens Energy 31 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Operation. Outdoor Operation. supervision of the equipment and its maintenance work. If not specified otherwise, the transformers must be suitable for outdoor operation. Operation as step down transformer. Unless otherwise specified, the transformers are designed for operation as voltage reducers. Operation as step up transformer. The transformers to operate as tension elevators, are those that were considered for this application from the initial conception of design. Check the nameplate to verify the application of the step-up transformer, and/or operation connected to a generator. Maintenance and monitoring work must be performed with the transformer de-energized and grounded. Failure to follow this instruction may result in damage to the equipment, serious injury or dead. Load under no nominal conditions To load the transformer to different conditions from nominal conditions is required to consult the international normatives of acceptable general application (ANSI / IEEE or IEC Standars), to load the transformer in any of the following conditions. a) Atmospheric temperatures higher or lower than those considered as a nominal base. b) Overloads of short duration, exceeding the power on the nameplate, for normal reduction of useful life. c) Loads that lead to reduce the life expectancy. d) Installation in enclosed spaces of transformers for outdoors use. Loadability guidelines are not standards, they provide the most suitable information for transformer loadability under several conditions, based on typical insulation systems and from the best engineering information available at the time of preparation of the guidesines. The guidelines discuss limitations in the other complementary components apart from the windings, which may limit the loadability of the transformers. When auxiliary or complementary components are specified for operation (as well as construction components like cables, bushings, tap changers, oil expansion space, etc.), they must be supplied so that they do not limit the transformer loadability. DANGER OF ELECTRIC SHOCK AND ARC FLASH EXPLOSION HAZARDS Do not re-energize the transformer if it has been damaged or has signs of being damaged. Failure to follow this instruction may result in damage to the equipment, serious injury or dead. Before beginning any work on the transformer, it is mandatory to apply the "5 safety rules": 1. De-energize. 2. Lockout to prevent reenergized. 3. Check absence of voltage. 4. Ground and shor-circuit. 5. Cover or shielding adjacents components. energized Obtaining a reliable and uninterrupted service from the transformer depends on the general and careful Version 3 © 2021 Siemens Energy 32 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers monitoring the status and condition of it. Annual verification of the correct operation of fans in case they are installed in the equipment. Before performing these procedures, review the "SECURITY" section. Before energizing the transformer, check that all static loads have been discharged by grounding the windings with appropriate groundingdevices. Failure to follow this instruction may result in damage to the equipment, serious injury or dead. If the oil of the transformer is overheated, for example, when welding works are being carried out in transformer tanks with oil, it is possible to produce oil vapor, which is explosive when mixed with air in a certain proportion. Likewise, oil gases appear when an electric arc occurs in the oil. These gases are flammable and produce an explosive mixture in contact with air. Therefore, any welding work with an open flame or involving an electric arc in filled or partially filled transformers with oil, expansion compartments, connection boxes, etc., requires special safety measures, such as Nitrogen filling or vacuum application, which requires extensive expertise. It is the responsibility of the owner to inspect and perform maintenance services to the transformer as well as to keep it in good conditions. The Siemens Energy Colombia Transformers require the following maintenance protocols, which can be performed during network disconnections or planned shutdowns. In equipment with expansion tank it is necessary to periodically check the saturation state of the dehydrating breather and make the changes of the silica gel granules on time it shows saturation color, the periods for this effect to happen depend on the load cycles and environmental conditions of installation place. Conduct annual physicochemical tests to the oil for Version 3 Review of correct operation of the indicators according to the established verification sequences or at least make a semi-annual record of their status. It is necessary to keep records of equipment maintenance activities. Check the tightening torque values of all electrical connections, including ground connections, and tighten them properly if necessary. Check the tightening torque chapter of this instruction book. Maintenance tests The following tests are recommended to determine the condition of the transformer: a. Insulation resistance test. b. Transformation ratio test. c. Leakage test. d. Continuity test. e. Oil tests. • Dielectric strengh • Power factor. • Moisture content. It is recommended to review the chapter 6 of Installation, and tests in Site, of this instruction book. Description of monitoring and maintenance work The inspection frecuency depends on the operating conditions. If the transformer operates under regular service conditions, as defined in the ANSI / IEEE © 2021 Siemens Energy 33 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers standard C57.12.00, one inspection per year may be acceptable. Nevertheless, for uncommon locations, where the air is contaminated with particles such as dust or chemical fumes, the transformer must be inspected every three months or more frequently. 1. Main tank of the place, the average life of the painting ranges from 2 years for corrosive environments (marine, desert and mining) and 5 years for non-corrosive environments, however, periodic revisions must be made (every 6 months) and touch up the paint to avoid accelerated deterioration of the coating. 1.1.Oil temperature control Read and record the oil temperature. Indicate whether the increase in oil or winding temperature is caused by prolonged overloads of the transformer or by deficient cooling. Take counteractive actions. Verify opening of Valves. 1.2.Oil level control The oil level in the expansión tank or in other oil container is established in the oil level gauges or with the oil level indicators and correspond with the temperatura marks shown on the indicator devices of the transformer. In case the oil level is lower than the proper level, the cause of oil losses must be eliminated, and the tank must be refilled with new dry oil. The filling oil data to be used is detailed in the transformer test certificate or on its nameplate. 1.3.Control of oil leakages in welded and bolted joints Check for oil leakages in all flanges, sealed joints, and welded seams. The leaks detected must be eliminated immediately by retightening screws, substitution of seals or, if necessary, welding. Welding must be done only by an experienced welder. We recommend requesting the assistance of an expert from Siemens Energy. It is expressly stated that accident prevention measures must be followed, especially the fire protection measures for work related to oil immersed transformers. Check the integrity of the gabinets (hinges, blocking provisions, corrosion, etc.) 1.4.Control of the paint and cleaning of the exterior surface Depending on the environmental conditions Version 3 Instructions: Clean the surface to be painted by passing a cloth soaked with solvent or by means of a steam jet treatment remove all dirt and traces of oil and grease. Sand old paint to remove paint residue. Clean the rusted parts by grinding or brushing until they shine. Apply on the deoxidized surfaces double layer of base paint. Old paint that is still well adhered to the base surface must be covered with finishing paint. Replace damaged or illegible tags. 1.5.Earthing control (Protection groundings). To avoid circulating currents, the transformer tank and the cooling system must be earthed by means of a conductor with a proper crosssection or grounding lock washers. The correct tightening of grounding screw must be verified and retightened if necessary. 1.6.Obtaining oil samples (oil analysis). Obtaining samples of transformer oil is required for the determination of dielectric strengh, as well as for the control of the physical and chemical qualities of the insulating liquid. Samples are obtained before commissioning the transformer, after a prolonged service or in case of damage. It is recommended to take oil samples regularly at intervals of at most 1 year. "Below" sampling valve. Samples for the other analyzes. The oil level in the tank or in other oil container is established in the oil level gauges or with the oil level indicators and correspond with the temperatura marks shown on the © 2021 Siemens Energy 34 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers indicator devices of the transformer. In case the oil level is lower than the proper level, the cause of oil losses must be eliminated, and the tank must be refilled with new dry oil. 2.2.Interlock control. The extreme positions of the tap cahnger are mechanically secured. Upon reaching the final position of the tap changer, a new position change of the tap is only possible in the opposite direction. 3. High and low voltage bushings The extraction of samples of insulating liquid should be done by personnel with the pertinent qualification and training. The extraction must be carried out considering the IEC 60475 standard for insulating liquids and the IEC 60567 standar for dissolved gases. 2. De-energized tap changer 3.1.Verification of porcelain insulating epoxy. status and Check for chipped areas, fractures or fissures, besides check for leaks in the fastening joint. 3.2.Verification of connectors. Verify that the cable attached to insulation connector is not loose. 4. Protection devices Make sure all protection devices are working satisfactorily. De-energize the transformer operating the tap changer. before The protection devices, such as oil level indicator, pressure vacuum gage, pressure relief device and filter press/drain valve with sampling device, do not need maintenance but they must be replaced when they are damaged. 2.1.Setting up all positions for cleaning the contacts of the tap changer. Over time, the copper contacts immersed in oil are covered with a foreign layer, under certain circumstances this layer can cause a rise of temperature in the contacts. Therefore, during the service interruptions of the transformer (at least once a year), it is advisable to set up the total positions range of the tap changer several times to scrape off foreign layer that has been deposited in the intermediate time. Version 3 © 2021 Siemens Energy 35 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 9. Maintenance Time intervals for supervision and manteninance work w = weekly; m = monthly; a = annually; v = variable; h = hour Work to do No. 1 Time of work Time interval. h w m a Main Tank. 1 .1 Oil temperatura control <1 1 1.2 Oil level control <1 1 1.3 Control of oil leakages in welded and bolted joint <1 1 1.4 Control of the paint and cleaning of the exterior surface 8 6 1.5 Grounding control (Protection groundings) 3 1 1.6 Obtaining oil samples (for physicochemical análisis and gas DGA content). <1 1 2 2 to 5 De-energized Tap changer 2,1 Setting up all positions for cleaning the contacts of the tap changer <1 1 2.2 Interlock control <1 1 3 Fans (if aplicable) 3.1 Fans control 2 3.2 Fans cleaning 4 1 4 6 Control Cubicle 4.1 Heating and lighting control of the control cubicle <1 1 4.2 Watertightness control <1 1 4.3 Replacement of contact of motor-protective circuitbreaker and contators 5 4 Note 1 Insulator Bushing 5.1 Verification of porcelain or epoxy status <1 5.2 Verification of conectors tightening <1 1 6 Current transformer (if aplicable) 1 6,1 Control of connections <1 1 6,2 Control of terminal grounding <1 1 7 v Protection Devices 7.1 Control of thermometers <1 1 1 7.2 Oil level indicator control <1 1 7,6 Control of the transformer pressure relief device <1 1 (Note 1) in case of defects Version 3 © 2021 Siemens Energy 36 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Tightening Torque In the next image are shown the typical executions for bolted joints in the transformers. Version 3 © 2021 Siemens Energy 37 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers The next table shows the torque tightening values. Version 3 © 2021 Siemens Energy 38 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Health, safety and environment Final disposition of the transformer’s materials During the design phase Within the responsibilities of the Design Engineer is that of selecting optimal materials in order to have an excellent quality product, including environmental issues for this (preference is given to environmentally friendly materials), where options arise as possibility of minimizing materials, reduction of process times and products. Moreover, during product design considers the life cycle assessment, and this is why Siemens Energy products are based on designs that are easy for disposal activities when it ends its life. During the Purchasing phase There is an interactive participation of shopping area and the Quality and Environment Management with the suppliers. Initially the buyer contacts the provider and receives appropriate samples with technical information, considering the parameters of approval materials. During the process of identifying environmental aspects, the Quality and Environment Management establish suppliers with high pollution commitments in their processes. During the Production and Service phase Production and projects areas represent the most critical points to consider for determine the objectives of environmental improvement. The first step in minimizing the impact environment that can produce the waste is the process of reduction at source, by which Siemens Energy uses only the raw materials needed in production, so that post-industrial wastes are minimal. Version 3 The final disposal or management of any constituent part of the transformer is the responsibility of the equipment’s owner, which has an environmental commitment to give them their proper use for minimizing environmental impact and / or consult with companies specialized in special waste management. Care should be taken into processes requiring heating elements as the tank or the active part. Siemens Energy recommends that these should be purged with dry air before to avoid any ignition hazard due to the presence of vapors from air / oil inside the tank. Insulating materials such as paper, wood, fiberglass, are not considered harmful, but as were in contact with dielectric oil (chemical composition may change during the cycle operation of the processor) Siemens Energy recommends chemical analysis of materials before they are reused or from the beginning classify them as special waste. Reference for the proper disposal of transformer’s materials: © 2021 Siemens Energy 39 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Materials Active part of the transformer (includes active parts motorfan) Final disposal at the end of it`s lifecycle The constructive parts made of iron, aluminum, copper, steel plate (depending on type of motor) are 100% recyclable (scrap). The constructive parts made of plastic, correspond to the type PP (polypropylene) are 100% recyclable. The constituent parts made of synthetic rubber can be sent to vulcanization process (recycling). The constructive active parts made of paper are recyclable. through the ground or reaches the water, it can be a danger to the environment. When eliminating the transformer or any of its components, it is necessary to consult the data sheets of the insulating liquid, as well as the rest of the components, included this document. The nameplate of the transformer specifies type of the insulating liquid used. Measures to be considered for the preservation of the environment: Care must be taken with the common animals of the workspace (snakes, bees, wasps, scorpions or other unknown animals), keep in force your vaccine shots and do not use gasoline to wash your hands. Do not dump material into the streams. Waste and garbage from the assembly process must be placed in appropriate containers. Containers that have contained a substance dangerous must be stored in cans or sealed boxes, avoiding excess waste in those containers react with other waste containers and to avoid possible spills of these dangerous substances. Magnetic foil Scrap - Foundry Copper Scrap- Crafts Insulation paper Fill Steel Scrap - Foundry Porcelain Raw Material in similar processes or construction landfill disposal. Valves Scrap - Reuse Dielectric Oil Fuel - Recovery Consult the relevant environmental legislation, considering that all aspects of environment Calibration devices Junkyard - Junk legislation is constantly updated. Rubber packaging Recycling vulcanization Plastics electrical equipment Recycling in the plastics industry Electronic Material Recovery auto parts Fiberglass Recycling Plastic Recycling The oil is part of the customer's property and is his responsibility of getting rid of old oils, contaminated or surplus following the regulations of the Ministry of the environment. If the insulating liquid used in the transformer go Version 3 Spare parts It is possible to replace the accessories in the field. Due to the wide variety of sizes, ratings, nominal values and styles used in different types of transformer, it is not possible to provide a quantity of specific accessories for a transformer. If you require a replacement accessory, request it by providing its description, serial number, nominal values and transformer size in kVA; as well as any pertinent information of the transformer. Order the parts directly from your local Siemens Energy sales representative. © 2021 Siemens Energy 40 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers To ensure proper operation, use spare parts approved by Siemens Energy, do not make repairs to damaged parts or accessories, replace them. Contact for purchase of spare parts or services of trans-formers outside warranty period. Warranty Consult the warranty terms and conditions in the contractual documentation. To have full warranty claim rights in case of anomaly or damage, it is essential to comply without exception with the safety instructions included in this instruction book. In the event of an anomaly or damage, the transformer must be disconnected immediately from the voltage supply in order to avoid consequential damage. In the event of failure or damage, please contact Siemens Energy Colombia technical service team. During the warranty period, report any problem to your local Siemens Energy sales representative. All repairs under warranty must be carried out by Siemens Energy or by a Siemens Energy Authorized Service workshop. Version 3 © 2021 Siemens Energy 41 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers 10. Attachments General dimensions drawing of the transformer. Name plate of the transformer. Test reports of the transformer. Version 3 © 2021 Siemens Energy 42 Operation and maintenance manual for liquid immersed Pad-Mounted Transformers Contact Siemens Energy Colombia Tenjo, Cundinamarca, Colombia Service Team* Tel: +57 601 4253829 + 57 320 8535227 sat_services_team.col@siemens-energy.com Sales Team Tel: +57 601 2942568 ventas.transformadores.col@siemens-energy.com siemens-energy.com * For services after the warranty period, we will direct you to the area in charge Note: Siemens Energy reserves the right to make changes to this instruction book without prior notice. For purchase orders and contracts, the agreements described in these purchase orders and contracts will prevail. Siemens Energy is a trademark licensed by Siemens AG. © Siemens Colombia 2019. All rights reserved