Job details Date created: Friday, 25 August 2023 Company name: Apex Painters Job site address: Perrin, Salisbury Job Description: painting a roof manufactured with ACM (asbestos containing material). Created by: Mohammed Name of person(s) consulted: Mohammed Page 1 PPE required for this job RISK MATRIX Likelihood ALMOST CERTAIN Insignificant Minor Moderate Major Severe Medium High Extreme Extreme Extreme Medium Medium High Extreme Extreme Low Medium High High Extreme Low Low Medium High High Low Low Low Medium Medium This event is expected to occur in most circumstances LIKELY This event will probably occur in most circumstances OCCASSIONAL This event will occur at some time UNLIKELY This event could occur at some time RARE This event may occur only in exceptional circumstances For emergency response call '000' or follow your site-specific emergency response procedures. Page 2 Job steps / tasks Asbestos disturbance Step / Task Pre-Start Check at Site Risk / Hazard Control measure Site hazards may Do pre-site inspection to verify conditions on site impair works allows works to be carried out as per the SWMS Risk Rating Discuss site specific works with the Site Supervisor Review site signage and Safety Management Plan for site specific hazards Ensure all employees are made aware of any site specific hazards If SWMS are to be changed, a copy is to be low provided to site supervisor All persons on site must hold Construction Induction (White) Card Only licensed personnel are to remove asbestos Operation of items of plant are to be undertaken by certified or licensed workers Preparation & Exposure to asbestos Consultation Removal work to be assigned to a suitably qualified asbestos removalist Notify regulatory authority of proposed removal works Co-ordinate with the nominated hygienist regarding methods to be employed, inspections, decontamination, control monitoring and clearance inspections low Ensure all parties have been notified of the commencement of works Asbestos removal company to prepare an Asbestos Removal Control Plan & identify asbestos containing materials Work in public spaces Potential exposure to asbestos Restrict access from general publicIsolate asbestos work with barriers Isolate asbestos work with barriers extending 10m from asbestos Provide public with knowledge of work undertaken and assist with any concerns low Erect appropriate signs and keep all access points locked at all times Page 3 Risk Step / Task Risk / Hazard Control measure Personal Protective Equipment to be Used Exposure to asbestos During any work in the contaminated area prior to final clearance hooded asbestos overalls are to be Rating worn A P3 foleter with half face respirator to be used low Approved safety footwear, eyewear, ear protection, and canvas gloves to be worn Removal of asbestos Exposure to asbestos containing materials Cleaning of work zone following removal Removal of asbestos to be performed in accordance with State codes of practice Asbestos low Following removal works all surfaces are to be thoroughly cleaned using HEPA filtered vacuum and wet wipe techniques On completion site is to carefully checked for visible asbestos containing materials Any asbestos materials found are to be placed into asbestos labeled 200mm plastic bags low The nominated hygienist is to issue a clearance certificate Removal of barriers signage, fencing, and equipment can only be removed following the Waste disposal Asbestos All waste are to be placed into asbestos labelled drums or 200 micron plastic bags All waste is to be removed from site and transferred to the relevant State asbestos licensed landfill Clearance inspection Asbestos An independent hygienist is to supply monitoring and/or visual inspection to clear work areas for the low low safe re-entry by unprotected personnel Page 4 This SWMS is developed in consultation and cooperation with workers and relevant reresentatives. I have read the above SWMS, and I understand its contents. I confirm hat I have the skills and training, including relevant certification, to conduct the task as described. I agree to comply with safety requirements within the SWMS, including risk control measures, safe work instructions and PPE described. Name of Worker Signature Date Page 5 Compliance and review Person responsible for Mohammed ensuring compliance with SWMS: What measures are in place to ensure compliance with the Regular compliance checks by site supervisor SWMS ? How will the SWMS control measures be Before any change is made to the way the construction work is carried out reviewed ? Before the place where the work is being carried out is changed Before a new system of work is introduced If a new hazard is identified If new information about a hazard becomes available If a notifiable incident occurs in relation to construction work If a control measure does not control the risk A request for a review is received from a health and safety representative Select Review Date: 30 Aug 2023 Signature: Page 6