SWMS

advertisement
Job details
Date created:
Friday, 25 August 2023
Company name:
Apex Painters
Job site address:
Perrin, Salisbury
Job Description:
painting a roof manufactured with ACM (asbestos containing material).
Created by:
Mohammed
Name of person(s)
consulted:
Mohammed
Page 1
PPE required for this job
RISK MATRIX
Likelihood
ALMOST CERTAIN
Insignificant
Minor
Moderate
Major
Severe
Medium
High
Extreme
Extreme
Extreme
Medium
Medium
High
Extreme
Extreme
Low
Medium
High
High
Extreme
Low
Low
Medium
High
High
Low
Low
Low
Medium
Medium
This event is expected to occur in most circumstances
LIKELY
This event will probably occur in most circumstances
OCCASSIONAL
This event will occur at some time
UNLIKELY
This event could occur at some time
RARE
This event may occur only in exceptional circumstances
For emergency response call '000' or follow your site-specific emergency response procedures.
Page 2
Job steps / tasks
Asbestos disturbance
Step / Task
Pre-Start Check at Site
Risk / Hazard
Control measure
Site hazards may
Do pre-site inspection to verify conditions on site
impair works
allows works to be carried out as per the SWMS
Risk
Rating
Discuss site specific works with the Site Supervisor
Review site signage and Safety Management Plan
for site specific hazards
Ensure all employees are made aware of any site
specific hazards
If SWMS are to be changed, a copy is to be
low
provided to site supervisor
All persons on site must hold Construction Induction
(White) Card
Only licensed personnel are to remove asbestos
Operation of items of plant are to be undertaken by
certified or licensed workers
Preparation &
Exposure to asbestos
Consultation
Removal work to be assigned to a suitably qualified
asbestos removalist
Notify regulatory authority of proposed removal
works Co-ordinate with the nominated hygienist
regarding methods to be employed, inspections,
decontamination, control monitoring and clearance
inspections
low
Ensure all parties have been notified of the
commencement of works
Asbestos removal company to prepare an Asbestos
Removal Control Plan & identify asbestos containing
materials
Work in public spaces
Potential exposure to
asbestos
Restrict access from general publicIsolate asbestos
work with barriers
Isolate asbestos work with barriers extending 10m
from asbestos
Provide public with knowledge of work undertaken
and assist with any concerns
low
Erect appropriate signs and keep all access points
locked at all times
Page 3
Risk
Step / Task
Risk / Hazard
Control measure
Personal Protective
Equipment to be Used
Exposure to asbestos
During any work in the contaminated area prior to
final clearance hooded asbestos overalls are to be
Rating
worn
A P3 foleter with half face respirator to be used
low
Approved safety footwear, eyewear, ear protection,
and canvas gloves to be worn
Removal of asbestos
Exposure to asbestos
containing materials
Cleaning of work zone
following removal
Removal of asbestos to be performed in accordance
with State codes of practice
Asbestos
low
Following removal works all surfaces are to be
thoroughly cleaned using HEPA filtered vacuum and
wet wipe techniques
On completion site is to carefully checked for visible
asbestos containing materials
Any asbestos materials found are to be placed into
asbestos labeled 200mm plastic bags
low
The nominated hygienist is to issue a clearance
certificate
Removal of barriers signage, fencing, and
equipment can only be removed following the
Waste disposal
Asbestos
All waste are to be placed into asbestos labelled
drums or 200 micron plastic bags
All waste is to be removed from site and transferred
to the relevant State asbestos licensed landfill
Clearance inspection
Asbestos
An independent hygienist is to supply monitoring
and/or visual inspection to clear work areas for the
low
low
safe re-entry by unprotected personnel
Page 4
This SWMS is developed in consultation and cooperation with workers and relevant reresentatives. I have read the
above SWMS, and I understand its contents. I confirm hat I have the skills and training, including relevant certification,
to conduct the task as described. I agree to comply with safety requirements within the SWMS, including risk control
measures, safe work instructions and PPE described.
Name of Worker
Signature
Date
Page 5
Compliance and review
Person responsible for
Mohammed
ensuring compliance
with SWMS:
What measures are in
place to ensure
compliance with the
Regular compliance checks by site supervisor
SWMS ?
How will the SWMS
control measures be
Before any change is made to the way the construction work is carried out
reviewed ?
Before the place where the work is being carried out is changed
Before a new system of work is introduced
If a new hazard is identified
If new information about a hazard becomes available
If a notifiable incident occurs in relation to construction work
If a control measure does not control the risk
A request for a review is received from a health and safety representative
Select Review Date:
30 Aug
2023
Signature:
Page 6