PRESENT GAS FLOW CONDITIONS Meghnaghat TBS Gozaria TBS A-B 1 B-S (30” OD, 60.4 Km) Pipeline (GTCL) Siddhirganj Flow: 200-230 mmcfd Haripur Meghnaghat MPL 450 MWPP From Narsingdi Location Demra Bkb-D (20” OD, 68.72 Km) Pipeline (GTCL) GOADNAIL C-F-B Haripur TBS Flow : 100-120 mmcfd Bakhrabad Hub A-B 2 Sonargaon TBS Summit 335 MWPP Flow: 110-130 mmcfd Meghnaghat EGCB 335 MWPP HPL 360 MWPP EGCB 412 MWPP EGCB 2x120 MWPP Siddhirganj Nh-S (20” OD) Pipeline (TGTDCL) Haripur Siddhirganj Power Plant MPL 450 MW Summit 335 MW HPL 360 MW EGCB 412 MW EGCB 335 MW EGCB 2x120 MW Present Flow 25 ‐ 50 60 50 ‐ Source PL B‐S B‐S B‐S B‐S B‐S B‐S Total (MMSCF) 185 Remarks Present Situation (as on 11‐10‐22) GAS FLOW CONDITIONS DURING ILI Gozaria TBS Sonargaon TBS Meghnaghat TBS Haripur TBS A-B 1 Bakhrabad Hub Flow : 180-200 mmcfd C-F-B B-S (30” OD, 60.4 Km) Pipeline (GTCL) Haripur Meghnaghat MPL 450 MWPP From Narsingdi Location Siddhirganj Flow: 50 mmcfd GOADNAIL A-B 2 Demra Bkb-D (20” OD, 68.72 Km) Pipeline (GTCL) Summit 335 MWPP Flow: 160-180 mmcfd Meghnaghat EGCB 335 MWPP HPL 360 MWPP EGCB 412 MWPP EGCB 2x120 MWPP Siddhirganj Nh-S (20” OD) Pipeline (TGTDCL) Haripur Siddhirganj Power Plant MPL 450 MW Summit 335 MW HPL 360 MW EGCB 412 MW EGCB 335 MW EGCB 2x120 MW Present Flow 25 ‐ 50 60 50 ‐ Source PL B‐S B‐S B‐S B‐S B‐S B‐S Flow 50 ‐ 50 ‐ ‐ ‐ Source PL Bkb‐D ‐ Nh‐S ‐ ‐ ‐ Total (MMSCF) 185 Remarks Present Situation (as on 11‐10‐22) 100 During Pigging