Uploaded by 862136909

Road & Bridges Specifications

advertisement
GOVERNMENT OF THE FEDERAL REPUBLIC OF NIGERIA
GENERAL SPECIFICATIONS
(ROADS AND BRIDGES)
VOLUME II
REVISED 1997
THE DIRECTOR OF FEDERAL HIGHWAYS
FEDERAL MINISTRY OF WORKS & HOUSING
HEADQUARTERS
ABUJA, NIGERIA
INDEX TO SPECIFICATION
Pages
Clauses: Index .................................................................................................. (i) – (xxxiii)
SPECIFICATIONS:-
SECTION
I
GENERAL .............................................................................................
SECTION
II
CONCRETE: MASS AND REINFORCED ..........................................
SECTION
III
PRESTRESSED CONCRETE ...............................................................
SECTION
IV
PILING ...................................................................................................
SECTION
V
BRIDGEWORKS ...................................................................................
SECTION
VI
ROADWORKS ......................................................................................
SECTION I – GENERAL
CLAUSES
2
Page
PART (A) - ADMINISTRATION
1001
1002
1003
PRELIMINARY ........................................................................................................
DEFINITIONS ...........................................................................................................
DESCRIPTION OF WORKS AND SCOPE OF CONTRACT ................................
1004
LIAISON WITH ADJACENT WORKS ...................................................................
1005
AVOIDANCE OF DAMAGE TO WORKS .............................................................
1006
1007
DATUM .....................................................................................................................
SURVEYS AND LEVELS TO BE AS AGREED AS BASIS FOR
MEASUREMENT .....................................................................................................
1008
DIMENSIONS AND LEVELS .................................................................................
1009
PARTICULARS OF EXISTING WORKS ...............................................................
1010
WORKING DRAWINGS ..........................................................................................
1011
ALTERNATIONS OF DRAWING ...........................................................................
1012
DRAWINGS OF TEMPORARY WORKS TO BE SUBMITTED ...........................
1013
1014
SETTING OUT ..........................................................................................................
NOTICE OF OPERATIONS .....................................................................................
1015
EXISTING SERVICES .............................................................................................
1016
DAMAGE TO SERVICES ........................................................................................
1017
FILLING HOLES AND TRENCHES .......................................................................
1018
JOINT MEASUREMENT OF EXTRAS ..................................................................
1019
PROTECTION FROM WEATHER ..........................................................................
1020
WORKS TO BE KEPT FREE FROM WATER
1021
STAFF ETC. ACCOMMODATION .........................................................................
3
1022
SUPPLY OF WATER AND ELECTRICITY ...........................................................
1023
RETURNS OF LABOUR ..........................................................................................
1024
PHOTOGRAPHS .......................................................................................................
1025
REPORTS OF ACCIDENTS OR UNUSUAL OCCURRENCE ..............................
1026
MAINTENANCE OF WORKS .................................................................................
1027
AS-MADE DRAWINGS ...........................................................................................
1028
TRAFFIC ROUTES TO BE MAINTAINED AND WORKS
TRAFFIC CONTROLLED ........................................................................................
1029
BARRICADES, WARNING AND DEVIATION SIGNS ........................................
1030
WEATHER CONDITIONS .......................................................................................
1031
OTHER WORKS AND SERVICES .........................................................................
CLAUSES 1032 – 1039 NOT USED ........................................................................
PART (B) - MATERIALS AND TESTING
1040
MATERIALS TESTING LABORATORIES AND STAFF .....................................
1041
TESTING OF MATERIALS .....................................................................................
1042
INDEPENDENT TESTS ...........................................................................................
1043
INSPECTION ENGINEER .......................................................................................
1044
MATERIALS SPECIFIED TO B.S.S. .......................................................................
1045
APPARATUS REQUIRED FOR TESTING .............................................................
1046
NOTICE OF TESTS ..................................................................................................
1047
SAMPLING ...............................................................................................................
4
1048
SAMPLING OF MATERIALS FROM BORROW PITS .........................................
1049
SAMPLING OF MATERIALS FROM STOCKPILES ............................................
1050
TESTS
TO
BE
CARRIED
OUT
................................................................................
1051
UNSATISFACTORY TEST RESULTS ...................................................................
1052
TRIAL SECTIONS OF ROAD .................................................................................
1953 HANDLING AND STORAGE OF MATERIALS ...................................................
CLAUSES 1054 – 1059 NOT USED ........................................................................
PART (C) - MISCELLANEOUS
1060
ASSISTANCE FOR ENGINEER’S REPRESENTATIVE .......................................
1061
OFFICE ACCOMMODATION ................................................................................
1062
FENCING ..................................................................................................................
1063
COMPLIANCE WITH REGULATIONS OF THE NIGERIAN
RAILWAY CORPORATION AND GOVERNMENT INSPECTOR
OF RAILWAYS ........................................................................................................
1064
COMPLIANCE WITH THE REGULATIONS OF THE
NIGERIAN PORTS AUTHORITY ...........................................................................
1065
TAKING OVER OF SITE BY CONTRACTORS ....................................................
CLAUSES 1069 – 1099 NOT USED ........................................................................
SECTION II
CONCRETE: MASS AND REINFORCED
CLAUSES
2000
Page
GENERAL .................................................................................................................
5
PART (A) – MATERIALS
2001
CEMENT ...................................................................................................................
2002
WATER .....................................................................................................................
2003
AGGREGATES .........................................................................................................
2004
FINE AGGREGATES ...............................................................................................
2005
COARSE AGGREGATES ........................................................................................
2006
STEEL REINFORCEMENT .....................................................................................
2007
WATERPROOF BUILDING PAPER .......................................................................
2008
JOINT SEALING COMPOUND AND PRIMER .....................................................
PART (B) - WORKMANSHIP
2009
PROPORTIONS OF CONCRETE MIXES ...............................................................
2010
CONCRETE MIX DESIGN ......................................................................................
2011
TRIAL MIXES ..........................................................................................................
2012
MIXING OF CONCRETE .........................................................................................
2013
QUALITY CONTROL OF CONCRETE ..................................................................
2014
TRANSPORTATION OF CONCRETE ....................................................................
2015
PLACING AND COMPACTION OF CONCRETE .................................................
2016
CONCRETE PLACED UNDER WATER ................................................................
2017
PROTECTION AGAINST CHEMICAL ACTION ..................................................
2018
ATTENDANCE
OF
JOINER
AND
STEEL
FIXER
.................................................
6
2019
CONSTRUCTION JOINTS ......................................................................................
2020
JOINTS TO PREVENT BONDING OF ADJACENT SURFACES .........................
2021
SURFACE FINISHES ...............................................................................................
2022
CURING OF CONCRETE ........................................................................................
2023
2024
FORMWORK ............................................................................................................
REINFORCEMENT SCHEDULES ..........................................................................
2025
BENDING AND FIXING OF REINFORCEMENT .................................................
PART (C) - PRECAST CONCRETE UNITS
2026
PRECAST CONCRETE UNITS ...............................................................................
PART (D) - CEMENT MORTARS AND GROUTS
2027
CEMENT MORTARS AND GROUTS
2028
BUILDING IN OF FOUNDATION BOLTS, FITTINGS, KERBS, ETC. ...............
2029
EMPLOYMENT OF CONCRETE, MORTARS AND GROUT ..............................
2030
CEMENT ...................................................................................................................
2031
AGGREGATES .........................................................................................................
2032
GRANOLITHIC TOPPING ......................................................................................
2033
THE SUB-FLOOR .....................................................................................................
2034
LAYING ....................................................................................................................
2035
CURING ....................................................................................................................
2036
RETARDATION OF DUSTING ...............................................................................
7
2037
CARBORUNDUM FINISH ......................................................................................
2038
GRANOLITHIC MONOLITHIC TOPPING ............................................................
2039
DAMP
PROOFING
...................................................................................................
(CLAUSES 2040 – 2999 INCLUSIVE NOT USED) ...............................................
8
SECTION III
PRE-STRESSED CONCRETE SPECIFICATION
CLAUSES
3000
Pages
GENERAL
PART (A) - MATERIALS
3001
3002
CEMENT ...................................................................................................................
AGGREGATES .........................................................................................................
3003
WATER .....................................................................................................................
3004
UNTENSIONED REINFORCEMENT .....................................................................
3005
PRESTRESSING STEEL ..........................................................................................
3006
SHEATHING .............................................................................................................
PART (B) - WORKMANSHIP
3007
CONCRETE PROPORTIONS ..................................................................................
3008
3009
FIELD TESTS ............................................................................................................
BATCHING AND MIXING .....................................................................................
3010
PLACING OF CONCRETE ......................................................................................
3011
CURING ....................................................................................................................
3012
3013
FORMWORK ............................................................................................................
SURFACE FINISH ....................................................................................................
3014
TOLERANCE ............................................................................................................
3015
PRE-STRESSING ......................................................................................................
9
3016
ADDITIONAL REQUIREMENTS ...........................................................................
3017
LIFTING AND HANDLING ....................................................................................
3018
QUANTITY
AND
PAYMENT
.................................................................................
(CLAUSES 3019 – 3999 INCLUSIVE NOT USED)
10
SECTION IV
PILING
CLAUSES
Pages
4000
GENERAL .................................................................................................................
PART (A) - GENERAL
4001
4002
TYPES OF PILES ......................................................................................................
APPROVAL OF TYPE OF PILES ............................................................................
4003
CONTRACTOR TO DRIVE OR BORE PILES .......................................................
4004
SUB-CONTRACTOR TO DRIVE OR BORE PILES ..............................................
4005
MANUFACTURE OF REINFORCED AND PRESTRESSED ...............................
4006
CEMENT ...................................................................................................................
4007
SETTING OUT OF PILES ........................................................................................
4008
ALIGNMENT ............................................................................................................
4009
DRIVING WITH DROP HAMMERS OR SINGLE ACTING
STEAM HAMMERS .................................................................................................
4010
DRIVING WITH DOUBLE ACTION STEAM HAMMERS ..................................
4011
PROTECTION OF PILE BUTTS ..............................................................................
4012
LEADS AND FRAMES ............................................................................................
4013
DRIVING TO BE CONTINUOUS TO FINAL SET OR LEVEL ............................
4014
JETTING ....................................................................................................................
4015
DRIVING TO FINAL SET AND RECORD OF DRIVING .....................................
11
4016
RE-DRIVING HEAVED PILES ...............................................................................
4017
DAMAGED AND MIS-DRIVEN PILES .................................................................
4018
OBSTRUCTIONS .....................................................................................................
4019
CUTTING
OFF
PILES
HEADS
ETC.
......................................................................
4020
BORED PILES OR CASINGS ..................................................................................
4021
PAYMENT ................................................................................................................
(CLAUSES 4022 – 4029 INCLUSIVE NOT USED) ...............................................
PART (B) - TEST DRIVING AND TEST LOADING OF PILES
4030
4031
GENERAL .................................................................................................................
RECORDING OF TEST RESULTS .........................................................................
4032
PROCEDURE FOR TESTING PILES OF TYRES A, B, C AND D .......................
4033
PROCEDURE FOR TESTING PILES OF TYPES “E” AND “F” ...........................
4034
LATERAL DISPLACEMENT TESTS .....................................................................
4035
ASSESSMENT OF RESULTS OF PILE LOADING AND
RIVING TESTS .........................................................................................................
4036
PAYMENT FOR TEST PILES AND LOAD TESTS ...............................................
(CLAUSES 4037 – 4049 INCLUSIVE NOT USED .................................................
PART (C) - PRECAST REINFORCED CONCRETE BEARING AND
SHEET PILES – TYPE “A”
4050
4051
GENERAL .................................................................................................................
MOULDS AND CONCRETING ..............................................................................
4052
STRIPPING AND HANDLING ................................................................................
12
4053
LENGTHENING OF PILES .....................................................................................
4054
STRIPPING HEADS OF PILES ...............................................................................
4055
PAYMENT FOR PRECAST REINFORCED CONCRETE
BEARING AND SHEET PILES ...............................................................................
(CLAUSES 4056 – 4059 INCLUSIVE NOT USED .................................................
PART (D) - CAST-IN-PLACE REINFORCED CONCRETE PILES
TYPES “B” AND “C”
4060
CAST-IN-PLACE REINFORCED CONCRETE PILES TYPE “B” ........................
4061
CAST-IN-PLACE REINFORCED CONCRETE PILES TYPE “C” ........................
4062
4063
EQUIPMENT .............................................................................................................
CONTROL OF INTERVAL PRESSURES ...............................................................
4064
CONCRETE ...............................................................................................................
4065
STEEL REINFORCEMENT .....................................................................................
4066
PAYMENT FOR CAST-IN-PLACE REINFORCED CONCRETE
PILES TYPES “B” AND “C” ....................................................................................
(CLAUSES 4067 – 4069 INCLUSIVE NOT USED .................................................
PART (E) - CAST-IN-PLACE REINFORCED CONCRETE PILES TYPE
“D”
4070
4071
GENERAL .................................................................................................................
DETAILED METHOD OF CONSTRUCTION ........................................................
4072
PAYMENT FOR CAST-IN-PLACE REINFORCED CONCRETE
PILES OF TYPE “D” ................................................................................................
(CLAUSES 4073 – 4079 INCLUSIVE NOT USED) ...............................................
13
PART (F) - PRESTRESSED CONCRETE CYLINDER PILES TYPE “E”
4080
4081
GENERAL .................................................................................................................
MANUFACTURE .....................................................................................................
4082
HANDLING ...............................................................................................................
4083
4084
EQUIPMENT .............................................................................................................
REINFORCING STEEL ............................................................................................
4085
CONCRETE ...............................................................................................................
4086
CASTING
..................................................................................................................
4087
CURING
....................................................................................................................
4088
METHOD OF HANDLING ......................................................................................
4089
ASSEMBLY OF SECTIONS ....................................................................................
4090
STRESSING OF PILES .............................................................................................
4091
GROUTING OF CABLES ........................................................................................
4092
DRIVING RESISTANCE ..........................................................................................
4093
TENSION FORCES DURING DRIVING ................................................................
4094
CONTROL OF INTERNAL PRESSURES ...............................................................
4095
PRE-EXCAVATION .................................................................................................
4096
TOLERANCE ............................................................................................................
4097
CUT-OFF ...................................................................................................................
4098
PILE SPLICES OF BUILD UPS ...............................................................................
4099
DEFECTIVE PILES ..................................................................................................
4100
PAYMENT ................................................................................................................
14
(CLAUSES 4100 – 4109 INCLUSIVE NOT USED .................................................
PART (G) - PRESTRESSED CONCRETE PILES OF TYPE “E”
4110
4111
GENERAL .................................................................................................................
METHOD OF MANUFACTURE ETC. ...................................................................
4112
PAYMENT ................................................................................................................
(CLAUSES 4113 – 4119 INCLUSIVE NOT USED .................................................
PART (H) - STEEL SHEET PILES
4120
STEEL SHEET PILES ...............................................................................................
4121
WELDING ELECTRODES ......................................................................................
4122
PROTECTIVE
PAINTING
.......................................................................................
4123
DRIVING ETC. .........................................................................................................
4124
THE RODS AND ROPES .........................................................................................
4125
PAYMENT ................................................................................................................
(CLAUSES 4126 – 4999 INCLUSIVE NOT USED) ...............................................
15
SECTION V
BRIDGEWORKS
CLAUSES
5000
Pages
GENERAL .................................................................................................................
PART (A) - PRELIMINARIES, EXCAVATIONS,
FOUNDATIONS, DEMOLITIONS, TEST LOAD ETC.
5001
5002
GENERAL .................................................................................................................
TRAFFIC DIVERSIONS ..........................................................................................
5003
CLEARING OF SITE ................................................................................................
5004
WATER TRAINING AND PROTECTION WORKS ..............................................
5005
EXCAVATION AND BACKFILLING ....................................................................
5006
PAYMENT FOR EXCAVATIONS FOR FOUNDATIONS ....................................
5007
EXCAVATION FOR FOUNDATION BELOW WATER LEVEL .........................
5008
PREPARATION FOR FOUNDATIONS: NORMAL ..............................................
5009
REMOVAL OF EXISTING STRUCTURES: GENERAL .......................................
5010
EXPLOSIVES ............................................................................................................
5011
REMOVAL OF EXISTING SUPERSTRUCTURES AND
SUBSTRUCTURES: STEEL AND CONCRETE ....................................................
5012
REMOVAL OF EXISTING SUPERSTRUCTURE AND
SUBSTRUCTURE: TIMBER ...................................................................................
5013
TOTAL DEMOLITION OF EXISTING ABUTMENTS, PILERS
AND LANDINGS ......................................................................................................
5014
PARTIAL DEMOLITION OF EXISTING ABUTMENTS,
16
PIERS AND LANDINGS ..........................................................................................
5015
DISPOSAL AND RE-USE OF RUBBLE RESULTING
FROM DEMOLITION ..............................................................................................
PREPARATION OF SURFACES OF EXISTING ABUTMENTS,
PIERS, ETC., PRIOR TO PLACING CONCRETE IN CONTRACT ......................
5016
5017
PREPARATION OF SURFACES OF EXISTING ABUTMENTS,
PIERS, ETC., PRIOR TO CONSTRUCTION OF NON-BONDING
JOINT .........................................................................................................................
5018
TESTS ON COMPLETED STRUCTURES ..............................................................
5019
LOADING OF STRUCTURES: CONSTRUCTIONS,
BACKFILLING, TRAFFIC, ETC. ............................................................................
5020
AS-MADE DRAWINGS ...........................................................................................
5021
SETTLEMENT OF BRIDGE AND APPROACHES ...............................................
5022
5023
BEARINGS ................................................................................................................
ELASTOMERIC BEARING PADS ..........................................................................
(CLAUSES 5024 – 5029 INCLUSIVE NOT USED .................................................
PART (B) - STRUCTURAL STEELWORK
5030
GENERAL: MATERIALS AND WORKMANSHIP ...............................................
5031
WORKING DRAWINGS ..........................................................................................
5032
SCHEDULE OF PARTS ...........................................................................................
5033
MILD STEEL FOR STRUCTURAL MEMBERS ETC. ..........................................
5034
ROLLED STEEL PINS, KNUCKLE PINS, ROLLERS ...........................................
5035
STEEL CASTINGS FOR BEARINGS .....................................................................
5036
PATTERNS OF CASTINGS .....................................................................................
17
5037
GUNMETAL FOR BEARINGS ...............................................................................
5038
5039
5040
5041
FORGINGS ................................................................................................................
RIVETS ......................................................................................................................
BOLTS .......................................................................................................................
HAND RAILING AND GUARD RAILING ............................................................
5042
HIGH
TENSILE
STEEL
FOR
WELDING
...............................................................
5043
HIGH TENSILE STEEL NOT TO BE WELDED ....................................................
5044
HIGH TENSILE STEEL MARKING .......................................................................
5045
5046
5047
5048
CAST STEEL ............................................................................................................
CAST IRON ...............................................................................................................
ELECTRODES ..........................................................................................................
GREASE FOR BEARINGS ......................................................................................
5049
PAINT AND PAINTING ..........................................................................................
5050
INTERCHANGEABILITY .......................................................................................
5051
PREPARATION EDGES AND ENDS .....................................................................
5052
HOLES FOR BOLTS AND RIVETS ........................................................................
5053
RIVETS AND RIVETING ........................................................................................
5054
5055
5056
5057
WASHERS .................................................................................................................
WELDING .................................................................................................................
JOINTS ......................................................................................................................
NOTCHING OF FLANGES AND WEBS ................................................................
5058
BENDING AND PRESSING ....................................................................................
5059
SHOP ASSEMBLY ...................................................................................................
5060
MACHINING ............................................................................................................
5061
ERECTION AT MANUFACTURERS WORKS AND MARKING
18
UP FOR RE-ERECTION ...........................................................................................
5062
SHOP PAINTING AND PROTECTIVE COATINGS .............................................
5063
GALVANIZING ........................................................................................................
5064
DRIFTS, SPANNERS ETC. ......................................................................................
5065
NUMBERS OF SITE RIVETS, BOLTS, NUTS, SERVICE
BOLTS, ETC. ............................................................................................................
5066
MEASUREMENT FOR PAYMENT OF STEELWORK .........................................
5067
PACKING AND MARKING FOR SHIPMENT ......................................................
5068
ERECTION AT SITE ................................................................................................
5069
SITE PLANNING ......................................................................................................
5070
ADDITIONAL STEELWORK INVOLVED IN THE
STRENGTHENING OF EXISTING BRIDGES .......................................................
5071
RE-USE OF GIRDERS, JOINTS, ETC., OBTAINED FROM
DISMANTLED STRUCTURES ...............................................................................
5072
GROUTING BASE PLATES, ETC., OF BEARING ...............................................
5073
EXPANSION JOINTS ...............................................................................................
(CLAUSES 5074 – 5099 INCLUSIVE NOT USED) ...............................................
19
SECTION VI
ROADWORKS
CLAUSES
6000
Pages
GENERAL .................................................................................................................
PART (A) - DESIGN AND CONSTRUCTION STANDARDS
6001
HORIZONTAL ALIGNMENT .................................................................................
6002
VERTICAL ALIGNMENT .......................................................................................
6003
6004
ROLL-OVER .............................................................................................................
CONTRACTOR TO CALCULATE LEVELS ..........................................................
6005
CONSTRUCTION STANDARDS ............................................................................
(CLAUSES 6006 – 6099 INCLUSIVE NOT USED)
PART (B) - EARTHWORKS, DRAINAGE, ETC.
(1) MATERIAL
6100
6101
GENERAL .................................................................................................................
UNSUITABLE MATERIAL .....................................................................................
6102
FILLING MATERIAL ..............................................................................................
6103
SELECTED LATERITIC MATERIAL FOR SOFT SHOULDERS ........................
6104
GRASS OR GRASS SEED .......................................................................................
6105
RUBBLE AND PITCHING STONES ......................................................................
(CLAUSES 6106 – 6119 INCLUSIVE NOT USED) ...............................................
(II) WORKMANSHIP
20
6120
SITE CLEARANCE ..................................................................................................
6121
SCARIFYING EXISTING SURFACE .....................................................................
6122
EARTHWORKS ........................................................................................................
6123
PAYMENT
FOR
EARTHWORKS
...........................................................................
6124
SELECTION OF SOIL FOR FILL ............................................................................
6125
COMPACTION .........................................................................................................
6126
6127
6128
BORROW PITS .........................................................................................................
SAND FILL ...............................................................................................................
EXCAVATION TO BE KEPT FREE FROM WATER ............................................
6129
SLIPS .........................................................................................................................
6130
SUITABLE MATERIAL BELOW FORMATION LEVEL .....................................
6131
SWAMP AREAS .......................................................................................................
6132
FORMATION OF LEVEL ........................................................................................
6133
PREPARATION OF FORMATION .........................................................................
6134
TRIMMING OF SLOPES .........................................................................................
6135
EXCAVATION IN ROCK ........................................................................................
6136
BACKFILLING OF EXISTING BORROW PITS ....................................................
6137
EMBANKMENT IN BAD ROUND .........................................................................
6138
6139
BACKFILLING .........................................................................................................
GRASSING OF EMBANKMENTS, CUTTINGS, VERGES, ETC. ........................
6140
ROADSIDE DRAINAGE DITCHING .....................................................................
6141
CONCRETE DRAINS ...............................................................................................
6142
SUB-SOIL DRAINS ..................................................................................................
21
6143
CUT-OFF DITCHING ...............................................................................................
6144
EXCAVATION FOR CULVERS .............................................................................
6145
DEMOLITION OF EXISTING CULVERTS ...........................................................
6146
NEW PIPE CULVERTS ............................................................................................
6147
EXTENSION
OF
EXISTING
PIPE
CULVERS
.......................................................
6148
ACCESS CULVERTS ...............................................................................................
6149
BOX CULVERTS ......................................................................................................
6150
EXTENSIONS TO EXISTING BOX CULVERTS ..................................................
6151
CORRUGATED METAL OR “ARMCO” CULVERTS ..........................................
6152
INLETS AND OUTLETS OF CULVERTS ..............................................................
6153
CLEARING DRAINS AND CULVERTS ................................................................
6154
PITCHING .................................................................................................................
6155
APPROVAL OF METHOD ......................................................................................
6156
PREVENTION OF DAMAGE TO COMPLETED PAVEMENT ............................
6157
WATER FOR CONSTRUCTION .............................................................................
6158
ROLLERS ..................................................................................................................
6159
VIBRATORY COMPACTORS ................................................................................
6160
TRENCH EXCAVATION FOR WIDENING OF EXISTING
PAVEMENT ..............................................................................................................
6161
PREPARATION OF SUB-GRADE ..........................................................................
6162
COMPLETION AND SHAPING OF SUB-GRADE ................................................
22
6163
COMPLETION OF VERGES AND MEDIANS ......................................................
6164
STRIPPING TOPSOIL ..............................................................................................
6165
CATCHPITS AND CASCADES ..............................................................................
(CLAUSES 6146 – 6179 INCLUSIVE NOT USED) ...............................................
(III) TESTS
6180
TESTS FOR THE SELECTION OF FILLING MATERIAL ...................................
6181
TESTS FOR THE CLASSIFICATION AND CONTROL OF
COMPACTED SUB-GRADE AND FILLING .........................................................
TRIAL SECTIONS TO DETERMINE TECHNIQUE .............................................
6182
(CLAUSES 6183 – 6199 INCLUSIVE NOT USED) ...............................................
PART (C) - SUB-BASE, BASE COURSE, ETC.
(I) LATERITE
6200
GENERAL .................................................................................................................
MATERIALS
6201
MATERIALS FOR COMPACTED SUB-BASE COURSE
AND BASE COURSE ...............................................................................................
6202
ROCK LATERITE FOR SUB-BASE COURSE AND
BASE COURSE .........................................................................................................
(CLAUSES 6203 – 6204 INCLUSIVE NOT USED) ...............................................
WORKMANSHIP
6205
SEQUENCE OF OPERATIONS ...............................................................................
6206
BORROW PITS FOR SUB-BASE, BASE COURSE AND
HARD-SHOULDER MATERIALS ..........................................................................
23
6207
COMPLETION OF SUB-BASE COURSE ...............................................................
6208
COMPLETION OF BASE COURSE ........................................................................
6209
ROCK LATERITE FOR BASE COURSE ................................................................
6210
SURFACING OF BASE COURSE ...........................................................................
6211
PREPARATION OF BASE COURSE TO RECEIVE BITUMEN
PRIME COAT ............................................................................................................
(CLAUSES 6212 – 6214 INCLUSIVE NOT USED) ...............................................
TESTS
6215
TESTS FOR THE SELECTION OF LATERITE SUB-BASE
COURSE AND BASE COURSE MATERIALS ......................................................
6216
TESTS FOR CLASSIFICATION AND CONTROL OF
COMPACTED LATERITIC SUB-BASE COURSE AND
BASE COURSE .........................................................................................................
6217
TRIAL SECTIONS OF LATERITE SUB-BASE COURSE
AND BASE COURSE ...............................................................................................
(CLAUSES 6218 – 6219 INCLUSIVE NOT USED) ...............................................
(II) SOIL CEMENT SPECIFICATION
6220
DESCRIPTION ..........................................................................................................
6221
MATERIALS FOR SOIL CEMENT STABILIZATION .........................................
6222
APPROVAL ...............................................................................................................
6223
SAMPLING OF MATERIALS: GENERAL ............................................................
6224
SAMPLING OF MATERIALS TO BE STABILIZED
24
BORROW PITS .........................................................................................................
SAMPLING OF MATERIALS – STOCKPILES .....................................................
6225
6226
SAMPLING OF MATERIALS – EXISTING MATERIAL
ALREADY IN PLACE ..............................................................................................
6227
TETS FOR THE SELECTION ON SOIL TO BE STABILISED .............................
6228
DESIGN CRITERIA ..................................................................................................
6229
PROCEDURE FOR ESTIMATION OF CEMENT CONTENT ..............................
6230
CONSTRUCTION .....................................................................................................
6231
MULTIPASS – MIX-IN-PLACE METHOD ............................................................
6232
TRAVELLING MIXING MACHINE METHOD .....................................................
6233
COMPACTION .........................................................................................................
6234
GENERAL REQUIREMENT FOR PLANT MIX PROCESS..................................
6235
BATCH MIXING ......................................................................................................
6236
WEIGHT PROPORTIONING ...................................................................................
6237
VOLUMETRIC PROPORTIONING ........................................................................
6238
CONTINUOUS
MIXING
..........................................................................................
6239
6240
SPREADING .............................................................................................................
COMPACTION .........................................................................................................
6241
FINISHINGS .............................................................................................................
6242
CONSTRUCTION JOINTS ......................................................................................
6243
CURING ....................................................................................................................
6244
FIELD CONTROL TESTS ........................................................................................
25
6245
TEST RECORDS .......................................................................................................
6246
ADDITIONAL CONSTRUCTION RECORDS .......................................................
6247
SUPERVISION ..........................................................................................................
(CLAUSES 6248 – 6249 INCLUSIVE NOT USED)
(III) CRUSHED STONE
6250
6251
6252
GENERAL .................................................................................................................
MATERIALS .............................................................................................................
GRADING OF CRUSHED STONE ..........................................................................
6253
PREPARATION OF SUB-GRADE ..........................................................................
6254
FORMS ......................................................................................................................
6255
CRUSHED STONE TO BE LAID AND COMPACTED IN LAYERS ...................
6256
LAYING AND COMPACTING CRUSHED STONE-DRY PROCESS ..................
6257
CRUSHED STONE BASE COURSE LAID BY THE WET PROCESS .................
6258
PREPARATION OF CRUSHED STONE BASE COURSE TO
RECEIVE BITUMINOUS SURFACING .................................................................
6259
COMPACTION .........................................................................................................
(IV) CONCRETE CARRIAGEWAY CONSTRUCTION
6260
GENERAL .................................................................................................................
MATERIALS
6261
CEMENT ...................................................................................................................
6262
6263
AGGREGATE ...........................................................................................................
REINFORCING STEEL ............................................................................................
6264
DOWEL BARS AND THE BARS ............................................................................
26
6265
6266
SIDE FORMS ............................................................................................................
RAILS FOR MACHINE FINISHED CONCRETE CARRIAGEWAY ...................
6267
PREFORMED JOINT FILLER .................................................................................
6268
JOINT PRIMER .........................................................................................................
6269
JOINT SEALING COMPOUND ...............................................................................
WORKMANSHIP
6270
6271
GENERAL .................................................................................................................
THICKNESS OF SLABS ..........................................................................................
6272
CONCRETE DISTRIBUTOR ...................................................................................
6273
COMPACTING AND FINISHING MACHINE .......................................................
6274
WATERPROOF UNDERLAY ..................................................................................
6275
SETTING, CHECKING AND STRIKING OF SIDE FORMS ................................
6276
SETTING CHECKING AND STRIKING OF RAILS FOR
MACHINE-LAID CONCRETE ................................................................................
6277
QUANTITY AND DISTRIBUTION OF STEEL REINFORCEMENTS ................
6278
PLACING OF STEEL REINFORCEMENT FOR CARRIAGEWAY .....................
6279
TREATMENT AT MANHOLES ..............................................................................
6280
JOINTS IN CONCRETE CARRIAGEWAYS GENERAL
REQUIREMENTS .....................................................................................................
6281
TRANSVERSE JOINTS ............................................................................................
6282
LONGITUDINAL JOINTS .......................................................................................
6283
SAWING AT JOINTS ...............................................................................................
6284
SEALING OF JOINTS ..............................................................................................
27
6285
COMPRESSIVE STRENGTH OF CONCRETE ......................................................
6286
TRIAL MIXES AND TRIAL SLABS .......................................................................
6287
PLACING CONCRETE ............................................................................................
6288
SPREADING AND COMPACTION WITH A FINISHING
MACHINE OF REINFORCED CONCRETE ROAD SLABS .................................
6289
SPREADING AND COMPACTION WITH A VIBRATING
SCREED OF REINFORCED CONCRETE ROAD SLABS ....................................
6290
SPREADING AND COMPACTION WITH A FINISHING
MACHINE OR VIBRATING SCREED ON CONCRETE SLABS
OR HAUNCHES USED AS ROAD BASES ............................................................
6291
CURING CONCRETE ..............................................................................................
6292
ACCURACY OF CONCRETE SURFACE USING FINISHING OR
VIBRATING SCREED .............................................................................................
6293
TRAFFIC OVER FINISHED WORK .......................................................................
TESTS
6294
SELECTION AND CONTROL TESTS ....................................................................
6295
TRIAL SECTIONS
(CLAUSES 6296 – 6299 INCLUSIVE NOT USED) ...............................................
PART (D): SURFACING
(I) TWO COAT BITUMINOUS SURFACE DRESSING
6300
GENERAL .................................................................................................................
....................................................................................................................................
28
MATERIALS
6301
MATERIALS FOR SURFACE DRESSING ............................................................
6302
BITUMINOUS EMULSION .....................................................................................
(CLAUSES 6303 – 6309 INCLUSIVE NOT USED) ...............................................
WORKMANSHIP
6310
HEATING OF CUT-BACK BITUMEN ...................................................................
6311
CUT-BACK BITUMEN PRIME COAT ...................................................................
6312
SPRAYING OF CUT-BACK BITUMEN PRIME COAT ........................................
6313
FIRST COAT SURFACE DRESSING .....................................................................
6314
FINAL SURFACE OF CARRIAGEWAY ................................................................
6315
WET WEATHER ......................................................................................................
6316
REGULATION OF TRAFFIC OVER SURFACE DRESSING ...............................
(CLAUSES 6317 – 6319 INCLUSIVE NOT USED) ...............................................
TESTS
6320
TESTS FOR BITUMEN ............................................................................................
6321
TESTS FOR AGGREGATES, ROADSTONE AND CHIPPINGS ..........................
6322
TESTS FOR BINDER DISTRIBUTORS..................................................................
6323
TESTS FOR RATE OF APPLICATION ..................................................................
(CLAUSES 6324 – 6329 INCLUSIVE NOT USED) ...............................................
BITUMINOUS MACADAM SURFACINGS
6330
(II)
GENERAL .................................................................................................................
29
MATERIALS
6331
BITUMEN MACADAM GENERAL .......................................................................
6332
BITUMEN MACADAM MATERIALS ...................................................................
6333
BITUMEN MACADAM APPROVAL OF MATERIALS .......................................
6334
BITUMEN MACADAM COMPOSITION OF MIXES ...........................................
(CLAUSES 6335 – 6339 INCLUSIVE NOT USED) ...............................................
WORKMANSHIP
6340
MACADAM MIXING PLANT .................................................................................
6341
BITUMEN MACADAM MIXING ...........................................................................
6342
BITUMEN MACADAM TRANSPORTING MIXED MATERIAL ........................
6343
BITUMEN MACADAM PREPARATION OF SURFACE PRIOR
TO LAYING ..............................................................................................................
6344
BITUMEN MACADAM LAYING ...........................................................................
6345
BITUMEN MACADAM SPREADER OR FINISHER ............................................
6346
HAND SPREADING NOT ALLOWED ...................................................................
6347
BITUMEN MACADAM ROLLING .........................................................................
6348
FIELD DENSITY OF COMPACTED BITUMEN MACADAM .............................
6349
TRIAL AREAS ..........................................................................................................
6350
BITUMEN MACADAM FINISHED LEVELS ........................................................
6351
BITUMEN MACADAM JOINTS .............................................................................
6352
BITUMEN MACADAM DAMAGED WORK ........................................................
30
(CLAUSES 6353 – 6359 INCLUSIVE NOT USED) ...............................................
TESTS
6360
BITUMEN MACADAM TESTS ..............................................................................
6361
FREQUENCY OF TESTS: BITUMEN MACADAM ..............................................
6362
INDEPENDENT TESTS: BITUMEN MACADAM ................................................
6363
MANUFACTURER’S CERTIFICATE FOR BITUMEN ........................................
6364
CONTRACTOR TO TEST MATERIALS: BITUMEN MACADAM .....................
6365
NOTICE OF TESTS: BITUMEN MACADAM .......................................................
6366
SAMPLES TO BE IN DUPLICATE .........................................................................
6367
COST OF TESTS BITUMEN MACADAM .............................................................
(CLAUSES 6368 – 6369 INCLUSIVE NOT USED) ...............................................
(III) ASPHALTIC CONCRETE
6370
6371
GENERAL .................................................................................................................
MATERIAL ...............................................................................................................
6372
APPROVAL OF MATERIAL ...................................................................................
6373
6374
SAMPLING ...............................................................................................................
COMPOSITION OF MIXES .....................................................................................
6375
PREPARATION ........................................................................................................
6376
TRANSPORTING MIXED MATERIALS ...............................................................
6377
PREPARATION OF AREA TO BE PAVED ...........................................................
6378
TRIAL AREAS ..........................................................................................................
6379
COMPACTION .........................................................................................................
31
6380
6381
JOINTS ......................................................................................................................
FIELD DENSITY OF ROLLED ASPHALT ............................................................
6382
FINISHED LEVELS ..................................................................................................
6383
ASPHALTIC
CONCRETE
MIXING
PLANT
..........................................................
6384
ASPHALTIC CONCRETE PAVERS .......................................................................
6385
INSPECTION AND CONTROL OF ASPHALT MIXING PLANT ........................
(CLAUSES 6386 – 6999 INCLUSIVE NOT USED) ...............................................
PART (E): MISCELLANEOUS
6400
6401
MILE POSTS .............................................................................................................
CULVERT BEACONS ..............................................................................................
6402
ROAD WARNING SIGNS .......................................................................................
6403
ADVANCE DIRECTION SIGNS .............................................................................
6404
CARRIAGEWAY MARKINGS ...............................................................................
6405
PRECAST CONCRETE KERBS ..............................................................................
6406
PRECAST CONCRETE EDGING BLOCKS ...........................................................
6407
PRECAST CONCRETE PAVING SLABS ..............................................................
6408
GULLEY KERBS ......................................................................................................
6409
6410
GULLEY PIPES ........................................................................................................
PRECAST CONCRETE CHANNELS ......................................................................
6411
6412
CAT’S EYES .............................................................................................................
STREET LIGHTING .................................................................................................
6413
TRAFFIC LIGHTS ....................................................................................................
32
6414
ILLUMINATED GUARD POSTS ............................................................................
6415
6416
GUARD RAILS .........................................................................................................
DELINEATORS ........................................................................................................
6417
TELEPHONE POLES ...............................................................................................
(CLAUSES 6418 – 6499 INCLUSIVE NOT USED) ...............................................
ANNEXURE TO THE GENERAL SPECIFICATION
(Road and Bridges)
PENETRATION (GROUTED) MACADAM
CLAUSE
Page
6500
6501
6502
GENERAL .................................................................................................................
MATERIALS .............................................................................................................
WORKMANSHIP .....................................................................................................
6503
TRIAL SECTIONS ....................................................................................................
6504
TESTS ........................................................................................................................
33
SPECIFICATION
SECTION I
GENERAL
SECTION 1 – GENERAL
PART (A): ADMINISTRATION ETC.
PRELIMINARY
1001.
The conditions of contract and the drawings shall be
read in conjunction with this specification and
matters referred to, shown or described in any one of
them are not necessarily repeated in the other; two.
The drawings and specifications are intended to
complement and supplement each other. Any work
required by either of them and not by the other shall
be performed as if denoted by each. Should any work
be required which is not denoted in the specifications
or on the drawing because of an inadvertent obvious
omission, but which is nevertheless necessary for the
proper performance of the project, such work shall be
performed as if it were described and delineated
subject to the approval of the Engineer. The
Contractor shall call the attention of the Engineer’s
Representative, to any perceived errors or omissions
that occur on the drawings and/or specifications.
DEFINITIONS
1002.
On the drawings, figured dimensions shall govern in
case of discrepancy between scaled and figured
dimensions. If any discrepancy be found between the
drawings and specifications, in so far as dimensions
are concerned, the requirements of the drawing shall
govern if there be a discrepancy between the General
Specifications and the Supplementary specifications,
the requirements of the latter shall govern. The
Engineer shall have the right to correct apparent
errors and omissions in the drawings and
specifications and to make such interpretation as he
deemed necessary for the proper implementation of
the intent and purpose of the drawings and
specifications.
The term “Approved”, “Directed” and “Required”
shall mean to the approval, direction or requirement
of the Engineer or his duly authorised representative.
The letters B.S refer to the latest British Standards
published by The British Standards Institution. The
British Standard mentioned in the specification are
particularly described in schedule VII of Volume III
of these Specifications bound together by the Bills
of Quantities.
Where no particular direction is given, the letters
B.S refer to the latest British Standards including
any amendments in force at the tune of the
tendering.
Materials specified to be in accordance with the
British Standards are to be branded or a certificate
provided where and as described in the particular
Standard.
Where applicable the abbreviations used in the
Specification and Bill of Quantities arc in
accordance with the recommendations contained in
B.S. 1991, parts 1 and 4, are as follows:
“A.A.S.H.T.O.” or “A.A.S.I.T.O..” refer to the
Specifications used by the American Association of
State Highway & Transportation Officials, current
edition.
“A.S.T.M.” refer to the American Society of Testing
Materials.
“C.P.” or “B.S.C.P.” refer to the latest (unless
otherwise stated) British Standard Code of Practice,
including any amendments.
“DOE” refer to Department of Environment, United
Kingdom
“F.M.W.” refer to The Federal Ministry of Works of
the Government of the Federal Republic of Nigeria.
“NIS” refer to the Nigerian Industrial Standards
“SON” refer to the Standard Organization of Nigeria
“W.AS.C.” refer to the West African Standard
Compaction.
DESCRIPTION
1003. The works comprised in this Contract are
OF WORKS described in Schedule V of Volume III of these
specifications bound together with the Bills of
Quantities.
The drawing showing the dimensions and layouts of
the works are listed in Schedule IV appended to
Volume III of these specifications bound together
with the Bills of Quantities.
The scope of the contract covers the supply of
materials, plant, equipment, labour and supervision
necessary for the complete works all as specified
together with all temporary works and traffic
diversions required during the construction of the
works.
Where called for, the contract also includes the
maintenance of a diversion for traffic during
construction, and the maintenance of the works in
terms of Clause 49 of the conditions of contract for a
period after completion as stated in the appendix to
Tender.
LIAISON WITH
ADJACENT
WORKS
1004.
AVOIDANCE OF
DAMAGE OF
WORK
1005.
DATUM
1006.
SURVEYS AND
1007.
LEVELS TO BE
AGREED AS BASIS
FOR MESUREMENT
In the event of other works being in progress concurrently with and adjacent to the work specified in
the contract, liaison shall be maintained with such
other works to ensure that the several works been
undertaken shall not cause any mutual interference
with progress and shall culminate in the integrated
improvement as a whole. If so required by the
Engineer, the Contractor shall vary his programme
of works in accordance with clauses 14 and 90 of the
Conditions of Contract, to coordinate the works with
any other works on or adjacent to the site of the
works, whether being carried out by contract or by
direct labour of the Ministry.
The Contractor shall arrange his programme of
works and control of traffic in such a way as to avoid
damage to the works at any stage of their
construction.
The datum to which the various level have been
reduced for the purpose of the contract are as stated
on the respective drawings. Where these datum are
likely to be covered by the new works, the
Contractor shall transfer the level to such fixed
points or beacons, to be provided by the Contractor
at his own cost, as shall be required and specified by
the Engineer’s Representative. The positions of such
transferred datum shall be accurately surveyed and
shown on the working and as-made drawings
Before the works or any part thereof are begun
the Contractor and the Engineer’s Representative
shall together survey and take levels of the site of
the works and agree all particulars on which
measurements of works are to be based. Such survey
shall be recorded and signed as agreed by the
Engineer’s Representative and the Contractor and
shall form basis of the measurements for the
Engineers Certificates. Failing such surveys and
agreement being signed by the Contractor the
surveys of the Engineer’s Representative shall be
final and binding on the Contractor.
1008.
The dimension and levels shown on the drawings are
believed
to be correct but the Contractor must verify the
same on the ground, as well as all other particular of
the contract and he will be held responsible for the
consequences of any error therein or omission there
from. Levels on existing roads will depend on the
amount of wear and maintenance which has taken
place between the time of survey and the time of
construction and similarly the levels of the river
beds and banks will be affected by the amount of
erosion and repair which has taken place in the same
interval. Should any discrepancy be discovered
between the levels shown on the drawings and those
found on the site, which may affect the levels and
dimensions of any part of the works, the Contractor
shall notify the Engineer’s Representative in
sufficient time to enable the Engineer to prepare
drawings showing the amended levels and
dimensions. The attention of the Contractor in this
respect is particularly directed to the extent of wing
walls (also see Clause 1010).
PARTICULARS OF 1009.
EXISTING WORK
Such information as may be given on the drawings or
in the specification or in the Bill of Quantities as to
the present condition, character, position and size of
existing structures, roadways, rivers, pipes, cables
and other services are given without guarantee of
accuracy or completeness, and neither the employer
nor the Engineer will be liable for the consequences
of any discrepancy therein or omission there from.
Where existing works are required to be removed
completely or in part or otherwise modified, it will
be the responsibility of the Contractor to satisfy
himself absolutely in all respects in all matters
pertaining to the carrying out and completion of the
works and the rates given in the priced Bill of
Quantities for the carrying out and completion of the
work shall be deemed to be fully inclusive and no
extras will be allowed to the Contractor on the said
rates.
Before any part of the works is put in hand the
Contractor must prepare and submit for the approval
of the Engineer’s Representative copies in duplicate
(in the first instance) of any further detailed working
drawings which may be required for that part of the
DIMENSIONS
AND LEVELS
WORKING
DRAWINGS
1010.
work and at the same time call the attention of the
Engineer’s Representative to any differences
between these and the contract drawings. The
Engineer’s Representative will, after the Contractor
has made any alterations which he may require,
record on the copies, as amended, his approval and
will return one copy to the Contractor who shall
carry out the work in accordance there-with. The
Contractor shall forward to the Engineer’s
Representative four additional copies of the working
drawings as approved. In addition, working
drawings are also to be submitted (the same
procedure being followed as above described) in
respect of any work proposed to be executed by
Sub-Contractors, the distribution of drawings being
as directed by the Engineer’s Representative. The
approval by the Engineer’s Representative of all or
any of the drawings shill not relieve the Contractor
of his responsibility.
ALTERATIONS
OF DRAWINGS
1011.
In all cases where drawings are specified or required
to be supplied by the Contractor for the approval of
the Engineer any alteration to such drawings, which
the Engineer may require shall be made by the
Contractor without extra charge.
DRAWINGS OF
TEMPORARY
WORKS
1012.
The Contractor shall submit to the Engineer’s
Representative for his approval, complete drawings
of all temporary works, stagings, required for
TO BE SUBMITTED
carrying out the work, together with the calculations
relating
to
their
strength
and anticipated
deflections. The drawings shall show the method
proposed for the erection of the various parts of the
temporary works and their application to the carrying
out of the permanent works. All temporary works
shall be properly designed and substantially
constructed to carry the loads to which they will be
subjected and all drawings and calculations
pertaining thereto shall be forwarded to the
Engineer’s Representative sufficiently in advance of
the intention to proceed as will allow for their proper
study and the incorporation of any modification
which the Engineer’s Representative may require
notwithstanding the approval or modification by the
Engineer’s Representative of any submitted design
for any of the temporary works, stagings, etc., the
Contractor shall remain wholly and entirely
responsible until the removal of such works for their
efficiency security and maintenance and for all
obligations and risks in regard to such works
specified or implied in the contract and he shall
reinstate the same at his own entire cost should any
mishap or accident occur causing damage or injury
thereto subject however to such provisions of the
conditions of contract as may be applicable in the
case of such damage or injury.
Two copies of each drawing shall be submitted to
the Engineer’s Representative in the first instance
and he will record on these copies, amended and
modified as required, his approval and will return
one copy to the Contractor who may then proceed in
accordance therewith. The Contractor shall forward
to the Engineer’s Representative four additional
copies of the drawings as approved.
The cost of complying with all the requirements of
this clause shall be borne by the Contractor.
SETTING-OUT
1013.
The attention of the Contractor is directed to Clause
17 of the Conditions of Contract. The Contractor
shall give the Engineer’ Representative not less than
24 hours notice of his intention to set out or give
levels for any part of the work in order that
arrangements may be made for checking.
To enable the Engineers Representative to check the
accuracy of the Contractor’s setting-out, the
Contractor shall provide for the use of the Engineer’s
Representative approved theodolites, levels, staves,
bands, pegs, labour and all things necessary as may
be particularly specified in the respective clause.
Any approval or collaboration in respect of settingout by the Engineer’s Representative shall not in any
way affect the Contractor’s sole responsibility for
the accuracy of the setting-out and the consequent
construction.
NOTICE OF
OPERATION
1014.
EXISTING
SERVICES
1015.
No important operation and, in particular, no
blocking or cutting of any road, water pipe or other
service shall be carried out without the consent in
writing of the Engineer’s Representative nor without
full and complete notice being given to him also in
writing sufficiently in advance of the time of the
operation and will enable him to make such
arrangements as may be deemed necessary for its
inspection and the provision of all relevant safety
precautions.
The Contractor shall satisfy himself entirely as
to the location of all existing drains, pipes, cables
and similar services whether above or below ground
level. Drains, pipes, cables and similar services
encountered in the course of the works shall be
guarded from injury by the Contractor at his own
cost so that they may continue in full and
uninterrupted use to the satisfaction of the owners
thereof and the Contractor shall not store materials
or otherwise occupy any part of the site in a manner
likely to hinder the operations of such owners. If the
interests of the work shall in the opinion of the
Engineer so require, the Contractor shall on his
direction arrange for the construction by the
respective departments, bodies, corporations or
authorities of permanent protective works or
permanent or temporary diversions of the said drains
etc., (afterwards reinstating if temporary) and the
cost of such works or diversions including
reinstatement shall be charged against the
appropriate provisional sum provided in the Bill of
Quantities. The
Contractor shall be at liberty subject to the approval
of the owners and the requirements of Clause 90 of
the Conditions of Contract to make any further
diversions he may consider necessary. The cost of
these additional diversions including the cost of
reinstatement shall be borne by the Contractor. No
services may be tampered with by the Contractor
and all works in connection with any services shall
be carried out by their respective owners.
DAMAGE TO
SERVICES
1016.
FILLING IN
HOLES AND
TRENCHES
1017.
The Contractor shall be held liable for damage
and, interference to mains and pipes, to electric
cables or services of any kind. The Contractor will
be deemed to have provided for these contingencies
in fixing the rates, etc, inserted in kind either above
or below ground caused by him or his SubContractors in the execution of the works. Should
any damage be done to mains, pipes, wires,
telecommunications or electrical apparatus or any
other service, whether shown on the drawings or not,
the Contractor must make good the same without
delay and do any further work considered necessary
by the Engineer or the owners all at his own cost or
pay the costs to the owner in so doing. The
Contractor will be deemed to have provided for these
contingencies in fixing the rates, etc inserted in the
Bill of Quantities.
The Contractor shall take all precautions and
provide any temporary fences necessary to protect
the public from accidents, which may be caused by
the presence of any excavations, mounds, heaps or
earth or any other materials or stores connected with
the works. The Contractor shall, at his own expense,
and immediately upon completion of any part of the
work, fill up all holes and trenches and level all
mounds and heaps of earth, which have been
excavated or made in connection with the works.
The Contractor shall bear and pay all costs, charges,
damages and expenses incurred or sustained on
account of or in consequence of any accident which
may happen by reason of holes and trenches being
dug and left unprotected, or materials being left or
placed in unprotected or improper situations.
JOINT
MEASUREMENT
OF EXTRAS
1018.
1019.
PROTECION
FROM WEATHER
In the event of the Contractor having to execute any
work or provide any material in regard to which he
may propose to claim extras, he shall first obtain a
written order from the Engineer’s Representative and
shall at once make arrangements to take the
measurements of the said work or materials with the
Engineer’s Representative. If these measurements
are not taken jointly and booked and agreed at the
time the work is being executed the Contractor’s
measurements will not afterwards be recognized by
the Engineer. The fact of such joint measurements
having being made will in no way commit the
Engineer to a recognition of the claim if he considers
such a claim without foundation. The Engineer’s
Representative shall at all time, have full access to
the Contractor’s time book and may daily check the
time of any extra works with the Contractor’s timekeeper or otherwise, but the fact of his agreeing upon
any time shall in no way bind the Engineer to value
the work other than by measurement if he thinks fit
so to do.
All materials shall be stored on the site in a
manner approved by the Engineer and the Contractor
shall carefully protect from weather all work and
materials which may be affected thereby.
1020.
All those parts of the works required to be carried
out in the dry, whether within any part specified to
the enclosed or not, shall be kept free at all times
from water from whatever source it may come to the
satisfaction of the Engineer’s Representative. The
costs of complying with the provisions of this clause
shall be borne by the Contractor.
STAFF
1021.
ACCOMODATION
ETC
The Contractor shall, at his own expense,
provide for himself suitable offices and housing
for his staff and labour. If required by the Engineer,
the Contractor shall supply, erect and maintain
suitable furnished offices and Residential quarters
for the Engineer’s Representative and his assistants,
inspectors and staff on a site or sites to be selected,
together with all proper lighting, heating. water,
sanitary arrangements and attendance.
SUPPLY OF
WATER AND
The Contractor shall make his own arrangements
for the provision of water and electricity, whether
WORKS TO BE
KEPT FREE
FROM WATER
1022.
ELECTRICITY
RETURNS OF
LABOUR
1023.
PHOTOGRAPHS
1024.
for
use in the execution and construction of
permanent works or otherwise. In the event of the
source of water being from any existing piped
supply, the Contractor shall comply with any
regulation laid down by the water authority and shall
pay for such supply, standpipes, connections, metre
rent and all other charges as required all at his own
expense. The some conditions apply for the
temporary supply of electrical power.
Every working day, the Contractor shall supply
the Engineers Representative with a return of the men
employed the previous day and of the work on which
they were engaged, specifying also the number
employed in each trade. He shall also supply any
other returns, which may be required from time to
time, as to the number of men and plant employed
and the nature, quality and quantity of the work
done.
The Contractor, shall, if required, supply to the
Engineer monthly, or at such other periods as he may
direct, well executed and mounted photographs
showing the progress of the works and also such
particular sections of the works, site, plant,
machinery or materials as the Engineer may direct.
The cost of such photographs will be charged against
the appropriate provisional sum.
The copyright of the photographs shall be held by
the Employers. The Contractor shall provide the
Engineer’s Representative (within 5 days of the
photographs having been taken) with the negative
and three prints of each photograph, which shall be
ISO. standard size A4 or a minimum of 200mm x
300mm. On the reverse side of each print the
following information shall be shown:
1 Date photograph was taken.
2 A brief description of the location illustrated or
the name of the structure.
3 The negative number of the photograph.
4 The name and address of the photographer.
The prints of each approved photograph shall be
signed and dated by the Contractor and the
Engineer’s Representative.
REPORTS OF
ACCIDENTS OR
1025.
Notwithstanding the submission of the normal and
regular monthly progress reports the Contractor
shall report to the Engineer’s Representative
promptly and in writing the particulars of any
accident or unusual or unforeseen occurrence on the
site whether likely to affect the progress of the work
or not-stating also the steps he has taken or is
arranging to take in the matter.
UNUSUAL
OCCURRENCE
During the period of maintenance as defined in
Clause 48 and 49 of the Conditions of Contract, the
Contractor shall maintain the works, or such part of
the works as are involved, for the period named in
the tender to the entire satisfaction of the Engineer.
Such maintenance shall include repairs to the
superstructures and sub-structures of the bridges;
defects in the sub-grade, base-course and bituminous
surfacing of the roadways; landslips and failures of
culverts, but shall not include grass cutting brushing
or the cleaning of drains.
Contractor
will
be
responsible
(B) The
for
the maintenance other than grass
cutting, of all verges, margins, and side-slopes,
including stone pitching, for the period of
maintenance and shall make good all erosions during
such period whether attributable to defects in
workmanship or not.
(C) Before the commencement of the period of
maintenance the Contractor shall remove all his
buildings and plant from the whole of the site and
shall clear and regrade the areas to the satisfaction of
the Engineer.
MAINTENANCE 1026. (A)
OF WORKS
AS-MADE
DRAWINGS
1027.
TRAFFIC
1028.
ROUTES TO BE
MAINTAINED AND
WORKS TRAFFIC
On completion of the works the Contractor shall
prepare as-made drawings giving complete details
of the entire works as constructed, including all work
carried out by Sub-Contractors. The as-made
drawings shall be prepared in accordance with the
requirements of the respective clauses in the
specifications and all costs arising out of their
preparation, supply and distribution etc., shall be
deemed to be included in the tendered rates for the
work to which they refer.
There shall be no unnecessary obstruction of
roads, railways, footpaths, waterways, electrical
installations, etc. during the course of the work, and
in no circumstances shall closure, in whole or in
part, of these or any other ‘Right of Way’ be
permitted except with the prior permission of the
Engineer in writing. Before granting such
permission the Engineer shall consult with the
authorities, government departments and/or persons
concerned and when desirable shall publish due
notice of the proposed action in the government
gazette. The Contractor shall maintain adequate
through safe traffic routes for vehicles and
pedestrians throughout the whole length of the
public highways within and adjacent to the site of
the works, including such diversion of highways as
may be required, and make arrangements for
watching, signalling and control of traffic by day
and by night and for adequate lighting all to the
satisfaction of the Engineer. The Contractor shall
without extra charge if instructed to do so by the
Engineer install, make use of, adequately maintain
automatic “Stop and Go” signals, traffic lights or
other special method or methods of traffic control
and direction as the Engineer may consider
necessary, and the Contractor shall carry out all such
instructions to the satisfaction of the Engineer.
Where directed by the Engineer, temporary single or
double tracks shall be constructed and maintained in
a safe and satisfactory condition for the use of all
traffic during the construction of the works. The
temporary tracks shall be removed and all
reinstatement made to the satisfaction of the
Engineer when no longer required.
The Contractor shall, at his own expense, and during
the period of this Contract, maintain in a safe
condition and adequately protect any work executed
by him, which is exposed to traffic. The Contractor
shall supply adequate advance warning signs of
reflecting type with letters not less than 150mm high
and such warning signs shall be placed in, positions
approved by the Engineer and shall be left in such
positions as long as traffic is still utilizing any such
temporary running surface.
The Contractor shall make arrangements and
cooperate with all other contractors working in the
area for directing, routing, marshalling, controlling
and circulating the traffic connected with the works
under this contract in accordance with the
Engineer’s Requirements, in order that the flow of
all traffic may be facilitated, that all obstruction,
inconvenience and delay may be minimized, and
that the interests of all concerned, including the
general public, may be protected.
The Contractor shall allow in his tender for
complying with the requirements of this clause and
for any directions in connection therewith which the
Engineer may issue, from time to time. The
Contractor will be deemed to have allowed for
additional expense he may incur on account of extra
running or kilometre covered by his vehicle or
labour or material involved in compliance with these
requirements.
The Contractor shall be responsible for ensuring that
the highways in the vicinity of the works are kept
clean of mud and other debris falling from vehicles
connected with the works or spreading on to the
highways as a result of the works in any way.
BARRICADES,
WARNING AND
1029.
DEVIATION
SIGNS
The Contractor will at all times during the contract,
provide, erect and maintain such barricades,
warning
lights, dangers signals, reflectors, signs and watchmen as may be necessary to the satisfaction of the
Engineer’s Representative. Any such warning signs
etc., shall be left in position as long as traffic is
utilizing any temporary running surface and/or until
such time as their removal is sanctioned by the
Engineer’s Representative.
Barricades and signs shall be constructed and used in
accordance with the requirements of the Engineer’s
Representative. All barricades, obstructions and such
other conveniences as are necessary to protect the
travelling public, or as required by the Engineer’s
Representative shall be illuminated at night by
reflectors or red lanterns.
The cost of barricades, danger, warning and deviation
signs and providing watchmen, shall be deemed to
be included in the tendered rates and prices.
WEATHER
CONDITIONS
1030.
The Contractors shall be deemed to have taken all
possible weather conditions into account when pre-
paring their tender and they shall not be entitled to
extra payment by reason of the occurrence or effect
of high winds, tornadoes, excessive rainfall,
temperature or humidity or any other meteorological
phenomena.
OTHER WORKS
AND SERVICES
1031.
During the continuance of the contract the employer may cause other works such as the installation
of services to be carried out on, through or adjacent
to the site.
The Contractor shall at all times comply with the
requirements of the general conditions of contract in
respect of these and any other works not included in
the Contract and shall allow reasonable access as
approved by the Engineer on and through the site of
the works to any other Contractors or workmen who
may be working on or near the site.
The Contractor shall make adequate arrangements to the satisfaction of the Engineer’s
Representative for the disposal of all sewage,
rubbish and all other waste materials arising from or
connected with the execution of the works.
The Contractor shall make his own arrangements for and shall provide any service
(including telephone and radio communications),
which he may require in addition to the foregoing.
In the programme and particulars required under
Clause 14 of the Conditions of Contract the
Contractor shall:
(i) provide details of the sequence he proposes for
carrying out the works,
(ii) state and allow a reasonable margin of time for
contingencies and
(iii)state his intentions regarding shift work.
The Contractor’s programme shall make due
allowance for requirements specified in all clauses
of the Specification.
The Contractor shall report monthly progress to the
Engineer on charts submitted in triplicate and
showing actual work done superimposed upon
copies of the programme. He shall furnish an
explanation of any deviation from the programme
and shall state proposals for improving progress
should this be lacking in any respect.
(CLAUSES 1032 - 1039 INCLUSIVE NOT USED)
PART (B): MATERIALS AND TESTING
MATERIAL
TESTING
LABORATORIES
AND STAFFF
1040.
The Contractor shall provide and maintain
materials laboratories, equipment and staff as
directed by Engineer and more particularly described
in Schedule No. VI of the Bills of Quantities.
The Contractor shall provide, maintain and staff
laboratories at his own expense throughout the
Contract. The said laboratories shall be:in a
waterproof building or, rooms designated and used
exclusively for the purpose and shall be maintained
in a clean and tidy fashion to the satisfaction of the
Engineers Representative. The laboratories shall
have an adequate water and electricity supply. The
laboratories shall be staffed with Engineers well
experienced in material testing and approved by the
Engineer.
The laboratories shall be located within 50 km. of all
works in the field requiring sampling and testing.
Work will not be permitted to begin until
laboratories and staff have been provided within this
distance.
The Contractor shall provide all the testing
equipment, tools etc, and shall carry out test on
materials as directed and shall supply the Engineer’s
Representative with two copies of the results of each
test on approved printed forms. A third copy of the
results shall be retained in the laboratories.
Without limiting the Contractor’s responsibility as
stipulated above, the facilities of the laboratories
shall be available for the use of the Engineer’s
Representative and his assistants to perform control
tests on workmanship and materials as provided for
in the Specification.
Notwithstanding the results of tests carried out by
the Contractor approval of workmanship and
materials shall be based on the results of these
control tests.
It is the responsibility of the Contractor to notify the
Engineer’s Representative when any items of the
works scheduled below are completed and ready for
approval and the Contractor shall give sufficient
notice to allow control tests to be performed.
Generally the time required to perform control tests
by the Engineer’s Representative after the receipt of
the Contractor’s notification shall be as follows:
All filling and subgrade
3 days
Unstabilized sub-base and base course
3 days
Crushed stone base
3 days
Surfacing materials
7 days
Structural concrete
30 days
Asphalt concrete
10 days
Note: Where construction is carried out in arid
region where moisture of finished fill, sub base or
stone base can dry out from the surface rapidly, the
time of notification may be reduced at the request of
the Contractor making representation to the
Engineer’s Representative on same.
Unless otherwise specified, the cost of carrying out
all tests shall be deemed to be included in the
tendered rates and prices and the Contractor shall be
deemed to have allowed for the costs of providing
all facilities necessary. No claim for delay of any
kind shall he entertained by the Engineer in this
respect if the stipulations of the foregoing have not
been observed.
All samples and records shall be preserved as long
as the Engineer’s Representative may direct and
they shall be kept and labelled in an orderly fashion.
The laboratories equipment, all records and samples
shall be open to inspection and use by the Engineer
or his Representative during all normal work hours.
The laboratory building shall be in accordance with
the standards specified for the office of the
Engineer’s Representative. Concrete floors shall be
provided throughout. The Contractor also shall
provide air conditioning throughout the laboratory
and shall service, clean and light the building to the
standards specified for the Office of the Engineer’s
Representative.
As specified elsewhere in the Contract documents,
the Contractor shall supply suitable vehicles
equipped and reserved exclusively for the use at all
times of the laboratory staff to permit the carrying
out of control tests in the field.
Where directed by the Engineer the Contractor shall
remove and dispose of the building and
unserviceable vehicles make good any damage to
the site and leave it clean and neat.
The facilities of the testing laboratory shall be made
available for use by the Engineer’s Representative at
all times for the purpose of the works.
TESTING OF 1041. The Contractor shall arrange for the testing of all
MATERIALS
materials used throughout the contract, to
ensure that they are up to the standards specified.
The Contractor shall carry out such laboratory and field tests
(including tests to check the accuracy of testing
equipment and methods but excluding tests specified
to be carried out in an independent testing
laboratory) as specified and as may be necessary to
ensure and satisfy the Engineer that the requirements
of the Specifications are met. The type and
frequency of testing shall be in accordance with the
relevant Nigerian Industrial Standards or British
Standards except as otherwise specified herein or
directed by the Engineer.
The frequency of testing specified in the relevant clauses are intended to
represent only a general guide. The Engineer’s
Representative shall be empowered to vary the
frequencies at which tests are conducted should he
deem this necessary for the proper control of the
quality of the Works. Should the Engineer’s
Representative vary the frequencies, stated in the
relevant clauses of the Specification, the Contractor
will not be entitled to extra payment.
Unless otherwise agreed or directed by the Engineer,
methods of sampling and test procedures shall be in
accordance with the relevant Nigerian Industrial
Standards/ British Standards, British Standard Codes
of Practice, Standard Methods of the Institute of
Petroleum and the American Society for Testing
Materials, the Asphalt Institute, Building
ResearchStation
Digests
and
published
recommendations of the Transport and Road
Research Laboratory. Samples will be selected by
the Engineer’s Representative.
Where tests are specified or directed by the
Engineer’s Representative to be carried out in an
independent testing laboratory, the Contractor shall
supply and deliver the sample and shall arrange for
the relevant tests to be carried out. The independent
testing laboratory shall be nominated by the
Contractor and shall be acceptable to the Engineer’s
Representative. Unless otherwise specified the
Contractor shall arrange for one copy of the
independent testing laboratory’s certificates to be
delivered to the Engineer’s Representative not less
than 7 working days before the materials covered by
the relevant test certificate are incorporated in the
Works. Each test certificate shall be relatable to the
materials from which the sample was taken.
When any material or article is required to comply
with a British Standard or any other Standard
specified herein such material or article or its
container shall bear the stamp of the registered
certificate trade mark of the British Standards
Institution or the certification of the applicable
standard. Alternatively, the Contractor shall submit
to the Engineer certified test certificates furnished
by the supplier or manufacturer of the material or
article indicating compliance with the relevant
British Standards or a copy of the manufacturer’s or
supplier’s test certificate showing that the material
has been tested and found to comply in all respects
with the relevant standard. Notwithstanding the
above, the Engineer’s Representative may require
additional tests to be carried out by an approved
local testing establishment and the material shall be
supplied by the Contractor. In such cases a copy of
the test result shall be submitted to the Engineer’s
Representative in
lieu
of
the
Manufacturer’s/Supplier’s certificate. All testing
carried out by the Contractor shall be undertaken by
approved qualified staff who shall be nominated by
the Contractor and sufficient notice of the intention
to carry out such tests shall be given to the
Engineer’s Representative to enable him to be
present during the tests should he so desire.
The Contractor shall arrange and the Engineer shall
have power to send inspectors to the premises of the
manufacturers and suppliers to inspect the
manufacture and testing of the materials intended
for use in the works. Materials tested before leaving
the manufacturer’s or supplier’s premises may be
tested again after delivery at the site, at the
discretion of the Engineer’s Representative.
Notwithstanding the results of the tests at the
supplier’s or manufacturer’s premises, the
production of a test certificate or the results of any
tests carried out by an approved testing
establishment, or by the Contractor, the Engineer’s
Representative shall have power to reject after
delivery at the site any materials found to be not in
accordance with the requirements of this
specification.
The Contractor shall be deemed to have included in
his tendered rates and prices all costs arising out of
compliance with the requirements of this clause.
INDEPENDENT
TESTS
1042.
INSPECTION
1043.
Notwithstanding successful test results being
submitted for any material, and in addition to the
tests required under other clauses of this
specification, the Engineer may order further tests of
any material to be carried out by his own central
laboratory or by an independent tester at such places
as he may determine. The Contractor shall provide
the samples for such tests free of charge, but
payment for the tests shall be the employer’s
responsibility and charged against the appropriate
provisional sum except as detailed in Clause 36 (4)
of the Conditions of Contract.
For the purpose of this contract and in accord-
ENGINEER
ance with Clause 36 of the Conditions of Contract,
the Engineer may appoint one or more Inspection
Engineers for all imported materials to be used in
connection with the contract.
If any Inspection Engineer is to be appointed for the
inspection of imported materials the Engineer shall
select the Inspection Engineer and inform the
Contractor accordingly.
For all materials of Nigerian origin the Inspection
Engineer shall be the Engineer’s duly Authorized
Representative in Nigeria.
Where an Inspection Engineer has been appointed
for imported materials the Contractor shall before he
enters into any arrangement for the supply or
manufacture of materials, submit for the approval of
the Inspection Engineer, the names of the
manufacturers or merchants he proposes to employ.
Should the Inspection Engineer at any time be
dissatisfied with any of the materials or operations
carried out at the manufacturer’s works or place of
business, he shall be empowered to cancel his
previous consent for materials to be obtained from
such manufacturer’s or merchant. Should the
Contractor fail to submit for the approval of the
Inspection Engineer samples of material of
satisfactory quality or workmanship, the Inspection
Engineer shall have the power to specify any
particular Manufacturer or merchant for the supply
of the materials and the Contractor shall obtain such
materials from the said manufacturer or merchants
without additional charge.
The Inspection Engineer shall examine and test and
if necessary analyse all materials and test the
fabrication of any structures or structural
components to be used in the permanent works. The
Inspection Engineer and his representatives shall
have free access at all reasonable times to the
manufacturer’s or merchant’s premises and shall be
afforded every facility for making inspections and
for taking of samples for testing and analyses.
The manufacturer’s or merchant’s shall provide free
of charge and to the satisfaction of the Inspection
Engineer all appliances required for the testing of
the materials at the manufacturer’s or merchant
premises and they shall supply samples and meet the
costs of transport thereof to enable tests and analyses
to be made at a laboratory if and when directed by
the Inspection Engineer.
All materials to be provided by the Contractor shall
be submitted for the approval of the Inspection
Engineer before removal from the place of
manufacture and under no circumstances shall
materials be shipped without the approval certificate
issued by the Inspection Engineer. The Contractor
shall give twenty-one days’ notice in writing to the
Inspection Engineer of his intention to remove
materials from the place of manufacture or
fabrication.
If in the opinion of the Inspection Engineer the
despatch of any materials or things have been
unduly delayed after they have been inspected and
approval certificates issued the Inspection Engineer
may issue an order in writing that the materials or
things shall be reinspected.
Invoices or shipping lists in triplicate showing in
detail the net weights and quantities of all materials
for the permanent work despatched to the site shall
be forwarded to the Inspection Engineer directly
when the materials are despatched. In the case of
steel and iron work such invoices or shipping lists
shall show separately the net weight of articles under
each item in the schedule of prices included in the
invoice or shipping lists.
All material and any iron or steel articles supplied by
the Contractor for use in the permanent works or any
materials for fabricating permanent steel or iron
structures and other articles shall be subjected from
time to time before the issue of the approval
certificate to such tests and Inspection Engineer.
All the tests shall be carried out in the presence of
the Inspection Engineer or his Representative and
shall be performed in such a manner and by such
processes at such premises and at such times as he
may consider desirable.
Notwithstanding any examination or tests that the
Inspection Engineer may wish to be carried out on
any perishable materials prior to their despatch to
the site, the Engineer shall be at liberty to carry out
any further tests that he may consider desirable after
delivery of such perishable materials at the site and
to reject such materials which fail to comply with
the required quality or conditions, notwithstanding
any provisional approval before despatch to the site.
The Engineer shall arrange for the inspection on site
of all materials and fabricated components to
ascertain whether these materials and fabricated
components have in any way become damaged in
transit to site.
The Engineer and the Inspection Engineer shall be
kept properly informed as to the progress of any
work in hand or materials being prepared and
supplied by the Contractor in order that they shall be
able to make such arrangements for examination,
testing and analysis as they may desire.
The Contractor shall weigh without any extra charge
any materials, articles or things supplied for the
execution of the permanent work that the Engineer
or the Inspection Engineer may require and such
weighing shall be carried out in their presence or in
the presence of their representatives.
When the Inspection Engineer is satisfied in all
respects with the inspection, regarding samples and
test results of materials and fabrication of structures,
he shall issue to the Contractor an approval
certificate thereof.
Where the Contractor/Manufacturer could not agree
with the Inspection Engineer the Contractor may
request with the permission of the Engineer that
such materials be tested by an independent testing
body as may be agreed by both parties in dispute and
cost of such test shall be borne by the Contractor.
MATERIALS
SPECIFIED TO
1044.
As provided in Clause 36 of the General Condition of Contract and in accordance with the
Standard
Organization of Nigeria or British
Standard Specifications quoted for any materials
used on the works of this Contract, tests may be
called for by the Engineer to be carried out at the
place of manufacture, fabrication, on the site, or at
any of such places.
B.S.
The Contractor shall arrange for the testing of all
materials used throughout the contract to ensure that
they are up to the standard specified, i.e. aggregates,
sand, cement, water, reinforcement, concrete,
blinding materials as specified or decided by the
Engineer.
The tests to be carried out on any material except as
detailed hereafter, shall be those specified, implied
or intended in the appropriate N.I.S. or B.S.
APPARATUS
REQUIRED FOR
TESTING
1045.
Notwithstanding that any test, piece of equipment or apparatus is not specifically mentioned
or described in the various pages hereof, nevertheless
if directed by the Engineer the Contractor is to
supply at his own expense all apparatus and
equipment of whatever kind necessary to carry out
any test mentioned in or required by the provisions
of the various clauses in this specification and the
British Standard Specifications incorporated in this
Specification.
The Engineer shall be the final arbitrator on which
tests are necessary for the proper execution of the
works.
NOTICE OF
TESTS
1046.
SAMPLING
1047.
Where the Contractor is responsible for the carrying
out of any control test, he shall first give notice of his
intention to carry out such a test to the Engineer’s
Representative to enable him to be present during the
test. Where the Engineer or his Representative
conducts any control test, he shall give the
Contractor sufficient notice to enable him, should he
so wish, to be present during the test. Should the
Contractor not wish to witness any control tests
conducted by the Engineer or his Representative, the
Contractor shall be deemed to accept the validity of
the results of such tests.
All samples of materials to be tested shall be selected
according to the method laid down in the appropriate
Nigerian Industrial Standards or British Standard
Specification or where there is no such standard it
shall be by the method to be mutually agreed
between the Engineer’s Representative and the
Contractor in so far as the selection has not been
prescribed below.
SAMPLING OF
1048.
MATERIALS FROM
BORROW PIT
SAMPLING OF
1049.
MATERIALS FROM
BORROW PIT
TEST TO BE 1050.
CARRIED OUT
Trial pits in proposed borrow pit areas shall be
dug from original ground level. Trial pits shall be at
least one metre by one metre in size, dug to such a
depth that the full extent of the material intended for
incorporation in the works is exposed.
Materials for testing shall not be taken from the spoil
of the trial pit but shall be made up of increments
taken from each face of the pit, each increment to be
a representative sample of the entire depth of a
horizon. The four increments shall be mixed three
times and quartered or riffled down to the size
required for testing. Visual examination will be made
to ensure that sampling more than one horizon in any
sample is avoided.
The surface material of a stock pile shall be removed before sampling. At least twelve samples
shall be taken from different parts of a stockpile,
avoiding segregated material, and thoroughly mixed
by hand before quartering down to required size.
In addition to the specific requirement of the various
clauses of this specification, the Engineer may direct
that any or all of the following procedures and tests
be carried out.
(A)
The following tests and procedures as
described in B.S.1377 (1975)
“Methods of Tests for Soils for
Civil Engineering Purposes”:Item 1.5
Preparation of disturbed soil
samples for testing.
Test 1 (A) Item 2.1.1
Determination of
moisture
content (Standard Method)
Test 2 (A) Item 2.2.1
Determination of Liquid Limit
(CONE Penetrometre method)
Test 2 (B) Item 2.2.2
Casagrande apparatus method
Item 2.3 Test 3
Determination of Plastic Limit,
using
the
following
modifications.
(1)
(2)
(3)
(4)
Materials for testing shall be moisturized,
mixed for 15 minutes and sealed in an
approved air-tight container for a minimum
period or 24 hours before testing.
After the above period of curing, the material
shall be removed from the container and
remixed with 10mm spatula for an exact
period of fifteen minutes.
For the method of determining the liquid limit
as laid down in B.S. 1377 at least five points
in the range 10-60 blows, evenly distributed
when plotted on a logarithm scale, shall be
made. Consecutive tests with respect to
moisture content shall form a wetting and not
a drying curve.
Alternatively
the
one
point
method
of determining the liquid
limit may be used.
LL = W N tanß LL = W N x 0.10
25
25
Where W is the moisture content %, N
number of blows and tan ß = 0.10 this is the
slope of the calculated flow line. The value of
N shall lie in range 20-30. The liquid limit
shall be taken as the mean of at least two
such tests.
(5)
The plastic limit of material shall be taken as
the mean of at least three tests.
2.6.1 Test 6 (A)
Determination of the
specific gravity of soil
particles suitable for
fine,
medium
and coarse grained
soils.
2.6.2 Test 6 (B)
Suitable
for
fine grained soils
2.7.1 Test 7 (A) Determination of
particle
size
distribution in soils,
using the wet method
with
following
modifications.
WET SIEVE ANALYSIS
All materials passing 5mm sieve shall be sampled
for moisture to determine the natural moisture
content of the sample for wet sieving. For different
sizes of material the weight of soil sample to be used
is as listed in Table 1-1.
TABLE 1-1 WEIGHT OF SAMPLE FOR WET SIEVING
Maximum Size of Particle present
in substantial proportion (more
tham10%) retained on Standard
Test Sieves mm
Minimum weight of Sample to be
taken for testing
63
50
50
35
37.5
15
28
5
20
2
14
1
10
0.5
6.3
0.2
Passing 2 mm to 63 µm
0.1
kg
(A)
(B)
(C)
(D)
All material passing the 5mm sieve shall be
sampled for moisture content, weighted, wet
sieved through the No.75 µm sieve oven
dried, and sieved through the full nest of
sieves. The portion retained on each sieve
shall be weighed. The weight of the original
sample shall be adjusted for moisture content.
Material retained on the 5mm sieve if it is
porous or tends to retain fine particles on the
surface shall be wet sieved as described in the
paragraph above full allowance being made
for the air dry moisture content.
If the material retained on the 5mm sieve is
clean of clay and contains no pores or
adhesions, the coarse fraction may be dry
sieved.
Pre-treatment and the analysis of the fraction
passing 75µm sieve may be omitted.
Item 4.1
12:
Determination of
Density/ Moisture
Content relation of Soil
(B.S. Compaction Test)
Item 4.4.1, 4.4.2,
Sand
Field Density by
4.4.3: 15.A,B &C
Method.
Replacement
&
Item 15D
(B)
Determination of Dry
Density by Core-Cutter
Method (for
finegrained soils).
THE WEST AFRICAN COMPACTION TEST:This test is identical with Test 13 in B.S. 1377,
(1975) except as follows:
(I)
(II)
The size of the mould shall be, 150mm
internal diameter, and 125 mm internal
effective height and a volume of 2210 cm3.
The weight of the metal rammer shall be 4,5
kg instead of 2.5kg (the diameter of bottom
face remaining at 50mm.
(III)
(IV)
(V)
(VI)
(C)
The drop of the rammer shall be 450mm
instead of 300mm.
The moist soil shall be compacted in the
mould in five equal layers each layer being
given twenty-five blows.
The
percentage
moisture
content corresponding to the
maximum density on the moisture content
dry soil density curve shall be reported as the
optimum moisture content for West African
Compaction.
Separate materials shall be used for each
compaction point, i.e. materials only air dried
previously and not oven dried, mixed with
water and allowed to moisturize for 12 hours
before compaction.
THE MODIFIED A.A.S.H.O. (AMERICAN
ASSOCIATION OF STATE HIGHWAY
OFFICIALS) COMPACTION TEST.
This test is identical with Test 13 in B.S. 1377,
except as follows:
(I) The size of the mould shall be 150mm internal
diameter, and 125mm internal effective
height and a volume of 2210 cm2.
(II)
The weight of the metal rammer shall be 4,5
kg instead of 2.5 kg (the diameter of bottom
face remaining at 50 mm).
(III) The drop of the rammer shall be 450mm
instead of 300 mm.
(IV) The moist soil shall be compacted in the
mould in 5 equal layers, each layer being
given 61 blows from the rammer dropped
from a height of 450mm above the soil.
The
percentage
moisture
content
(V)
corresponding to the maximum density on the
moisture content dry soil density curve shall
be reported as the “Optimum Moisture
Content for Modified A.A.S.H.O.
Compaction.
(VI) Separate materials shall be used for each
compaction point, i.e. materials only air dried
previously and not oven dried, mixed with
water and allowed to moisturize for 12 hours
before compaction.
(D) LABORATORY C.B.R. TEST
To be carried out in accordance with the method laid
down by “The Materials Testing Conference,
February 1961”as follows:
(I)
Different samples of materials shall be used
for each point in the compaction for C.B.R.
Test.
(II)
The materials for testing shall be moisturized
and sealed in an airtight container for a
minimum period of 12 hours before testing.
(III) The standards Compaction used for C.B.R.
Tests shall be as follows:
(a)
(b)
(c)
(E)
Sub Grade Materials and all Filings –
The British Standard Compaction.
Sub Base Course Material: The West
African Standard Compaction.
Base Course Material: The West
African Standard or Mod. A.A.S.H.O.
Standard as directed by the Engineer
may be used for laterite, stone or
Mechanically Stabilized Base Course
and the B.S. Compaction for Cement
Stabilized Base Course. For other
type of Base-Course Compaction
shall be decided by the Engineer.
SAMPLING AND TESTNG
OF
MINERAL
AGGREGATES
The following procedures and tests shall be as
described in B.S. 812 “ Sampling and Testing of
Mineral Aggregates, Sands and Fillers”.
Section One: Sampling and submission of
Samples.
Section Three:
Determination of Particle Size
and Shape.
Section Four: Determination of Specific Gravity,
Density,
Voids
and
Absorption.
Section Five:
Organic Impurities.
(F)
METHOD OF TESTING CONCRETE
The following procedures and tests as described in B.S.
1881. “Method of Testing Concrete.
Part 1. Sampling Fresh Concrete in the Field.
Part 2. Slump Test.
Part. 3. Compacting Factor Test
Part. 6. Making and Curing of Compression Test Cubes
in the Laboratory.
Part 7. Making and Curing of Compression Test Cubes
in the Field.
UNSATISFACTORY
TEST RESULTS
1051.
Should in the opinion of the Engineer’s Representative any of the results of the specified tests on materials be unsatisfactory, the Engineer’s Representative
may order the work to be stopped pending his further
instruction. Executed work for which test results are
unsatisfactory shall be liable to be rejected, and, if so
directed by the Engineer, the work represented by
the tests shall be cut out and re-executed at
Contractor’s Expense.
The cost of all such cutting, preparation of
specimens, testing, and of making good the portions
of the works affected shall be borne by the
Contractor.
TRIAL SECTIONS 1052.
One or more trial stretches
as directed by the
Engineer’s Representative shall be constructed with
the proposed materials prior to the start of the main
construction to determine the most efficient
compaction technique, the suitability of the proposed
materials and of the plant. Each of these trial
sections shall be at least 30 metres in length, at a site
and in the alignment as directed by the Engineer’s
Representative. The results obtained from these trial
rolling stretches shall be used as guide and
complement with laboratory test results for
subsequent construction and control.
OF ROAD
It is likely that these stretches will be incorporated in
the works. Should one or all of these stretches or a
part thereof be rejected the Contractor will be
reimbursed for the rejected work in accordance with
the rates at which the relevant items have been
priced in the Bill of Quantities.
ROLLING TEST
1052. A
1052. B
DEFINITION
Rolling Test shall be used to establish the optimum
moisture and maximum dry density of the proposed
plant for a particular type of soil material. In addition
it shall be used to determine the economic number of
passes of the plant that may be required to achieve
the maximum dry density at a known moisture. This
test is a corollary to laboratory tests already carried
out using CBR mould and specified compactive
effort.
TEST PROCEDURE
(a)
Prepare a formation of a reasonable length
(about 48m) adequately compacted to serve
as a good platform for the rolling test.
(b)
Spread the loose material on the prepared
platform to a desired loose depth. (Between
200mm to 300mm for laterite)
(c)
Divide the test section into at least five bays
(each bay not less than 8m) and leaving a gap
of two metres between bays to avoid
intermixing of materials from adjacent bays.
Determine the moisture of the material in
each bay. This may be done by using the
speedy method and sampling in various
points, taking the mean result of four as the
moisture content.
(d)
Adjust the moisture content in each bay with
a view to straddling the optimum moisture
content. This could be achieved by
progressively increasing the passes of the
water tank in different bays as shown in the
Table 1.2.
TABLE 1-2: SHOWING THE NUMBER OF
PASSES OF WATER TANK
Bay 1 Bay 2
Bay 3
Bay 4 Bay 5
4
6
8
10
12
passes passes passes passes
passes
______________________________________
(e)
(f)
(g)
(h)
1052. C
Mix the loose soil and water to ensure
through moisturization using either hand,
pulvimixer or rotovator. (To ensure uniform
moisturization the watered material could be
left over night before mixing).
Compact to refusal the loose material whose
OMC and MDD is required with the
available plant. For practical purposes fifteen
to twenty passes of a 10-15 tonnes of a
three-wheel roller or ten or fifteen passes of a
vibrating roller will be adequate for a lateritic
material. For the three-wheel roller the rear
wheel is the compacting wheel while the
front is the compacting wheel for the
vibrating roller.
Determine the insitu dry density and moisture
content of each bay based on the mean of
four tests. Concentrating the measurement of
the wheel path of the rear or front wheel as
the case may be.
Plot results of the dry density and moisture
content and determine the optimum moisture
content and dry density appropriate to the
plant.
DETERMINATION OF ECONOMIC PASSES
(a)
Prepare another test section as in clause
1052B and bring the moisture content to the
optimum
moisture
content
earlier
determined.
Divide the section into bays and vary the
number of passes of the roller on each bay as
shown in Table 1.3
(b)
TABLE 1-3 NUMBER OF PASSES OF
THE ROLLER
Bay 1
Bay 2
4
passes
6
8
10
passes passes passes
(c)
(d)
Bay 3
Bay 4 Bay 5
12
passes
After rolling determine the dry density of
each bay (based on mean of four tests).
Plot the dry density and number of passes
relationship to determine the minimum
number of passes that will achieve the
maximum density.
TABLE 1-4 RELATIONSHIP BETWEEN COMPACTION PLANT AND
LABORATORY TEST: MDD AND OMC
SOIL TYPE
COMPACTION
Heavy Clay
Silty Clay
Sandy Clay
Sand
Gravelly
Sandy Clay
MDD OMC MDD OMC MDD OMC MDD OMC MDD OMC
B.S. 2.5 Kg
1554
26
1666 21
1842 14
1938 11
2067 9
B.S. (heavy)
4.5 Kg
1810
17
1922 14
2051 11
2083 9
2211 7
2800 kg
S.W.Roller
1522
21
1762 17
1826 16
2034 10
2147 8
8000 kg
S.W. Roller
1666
20
1778 16
1858 14
2115 8
2211 7
Pneumatic
Tyred Roller
1570
25
1666 20
1730 19
2034 11
2018 7
Sheepsfoot
1714
(tapper-foot) Roller
15
1842 14
1927 12
2051 5
HANDLING AND 1053 All materials to be used in the works shall be handled
STORAGE OF
with due care and whenever not in immediate
use
MATERIALS shall be adequately stored and protected having particular regard in all
cases and throughout to the nature of the material
and its susceptibility to
damage, breakage, deterioration, attack by weather
or any act of abuse.
(CLAUSES 1054 – 1059 NOT USED)
PART (C) MISCELLANEOUS:
ASSISTANCE FOR 1060.
ENGINEER’S
REPRESENTATIVE
The Contractor shall provide at all times during
the
during the continuance of the contract all equipment
and instruments for the exclusive use of the
Engineer’s Representative on the scale as set out in
detail in Schedule No. VI. The Contractor shall be
solely responsible for all such instruments and shall
ensure that they are at all times in good repair and
adjustment.
The Contractor also shall supply such workmen as
may be deemed necessary by the Engineer’s
Representative, from time to time during the
continuance of the contract, to assist the Engineer’s
Representative in carrying out his duties. These
workmen shall be selected for their intelligence and
knowledge of the English language, and where
possible the same men shall be provided throughout
the period of the Contract.
Payment for furnishing workmen and instruments,
etc. to assist the Engineer’s Representative shall be
charged against provisional sum item “ Payment of
Wages to Engineer’s Daily Paid Staff”. All
instruments and equipment so furnished become the
property of the Federal Ministry of Works on the
completion of the Works.
OFFICE
1061.
ACCOMMODATION
The Contractor shall provide air-conditioned office
accommodation and equipment for the sole use of
the Engineer’s Representative and his assistants. The
extent of the office accommodation and equipment
to be provided as set down below unless specified in
Schedule No. VI.
The offices shall be 28.95 metres long by 5.55
metres wide with 2.45 metres headroom all
measured internally complete with ceiling and
smooth concrete or wooden floor, and a 2.02 metres
wide covered veranda on all sides. The office shall
be divided into three rooms each 3.6 metres long.
The rooms shall be adequately ventilated and lighted
and through ventilation shall be provided in the roof
space. The walls must be constructed of either
prefabricated timber sections or sand-cement blocks.
All doors and windows shall be arranged so that
they can be securely fastened on the inside. All
doors shall be provided with cylinder locks with two
keys.
The following furnishings shall be supplied for each
site office:
6
Desks 1.5 metres x 0.75 metres with 2 chests of
drawers
6
Chairs with arms
1
Table 1.5 metres x 0.75 metres with two
drawers and chairs
1
Typist’s table with one chest of drawers and
chair
1
Typewriter, standard
office size
3
Draughtsman’s tables and stools
3
Sets of Normal Equipment for a Draughtsman
1
Six-drawer steel filing cabinet
3
Four-drawer steel filing cabinets
2
Cupboards 2.0 x 1.0 x 0.5 metres with 4
shelves
2
Clerk’s tables 1.2 m x 0.75 m with 12 chairs
2
Pairs of set squares 60° and 45°
2
Planimetres
3
Sets of Engineer’s scales, metric
1
Set of shelves and hooks as required
2
Stainless steel straight edges - 1 metre long
1
Refrigerator
1
Conference Table with 8 chair
3
Small Table with 8 chairs
1
Set of Applicable British Standards, Current
Edition
1
Copy of AASHTO Standard Specifications for
Highway Materials and Method of Sampling
and Testing Volumes I & II, Current Edition.
1
Civil Engineer’s Radius Guide
1
Set of transparent plastic railroad curves
1
Electronic calculator
1
Electric adding machine
1
Electric erasing machine
1 Photocopy
machine
with accessories
and supplies.
Adjacent to the two ends of the building the
Contractor shall erect a board 750mm x 600mm
bearing the following inscriptions
Principal Resident’s Engineer’s Office
(Project Designation)
Section No. or Description
In addition each door of the building shall be lettered
in accordance with the instructions of the Engineer’s
Representative. These building(s) shall be erected at
locations as directed by the Engineer’s
Representative.
The Offices shall be separate from those of the
Contractor and shall be fenced off and provided with
separate entrance.
The Contractor shall provide two water closets and
two wash hand basins with mirrors in rooms
attached to the use of the Engineer’s Representative.
The Contractor shall keep clean and maintain this
lavatory accommodation.
He shall also provide soap, towels and all necessary
fittings and cleaning materials.
The Contractor shall arrange for the offices to be
connected to a water and electricity supply.
The Contractor shall provide a roofed shelter for six
cars, which shall be built adjoining the offices.
The cost of providing the offices, water, electricity
supply and maintenance during the whole period of
the contract shall be deemed to be included in the
price inserted under the appropriate item in the Bill
of Quantities. The buildings and equipment shall be
for the sole use of the Engineer’s Representative
during the period of the Contract and shall remain
the property of the Employer after the completion of
the Contract.
FENCING
1062.
The Contractor shall provide and erect
fencing or walls complete with access gates along
the land acquisition
boundaries
during the
period of construction as and where directed by
the Engineer’s Representative.
Payment for fencing and walling will be made from
the appropriate item in the Bill of Quantities.
No payment will be made for fencing or walls
erected by the Contractor for the purpose of making
secure his own working areas, yards, stores, as this
will be deemed included in this pricing.
COMPLIANCE
1063.
WITH THE
REGULATIONS OF
THE NIGERIA
RAILWAY CORP.
AND GOVERNMENT
INSPECTOR OF
RAILWAYS
COMPLIANCE WITH 1064.
THE REGULATIONS
OF THE NIGERIAN
PORTS AUTHORITY
TAKING OVER
OF SITE BY
CONTRACTOR
1065.
Where the works abut, enter into or pass over
property or properties belonging to the Nigerian,
Railway Corporation the Contractor shall comply
with all the regulations laid down and give all
notices
required by the Nigerian Railway Corporation and
the Government Inspector of Rail ways
.
Where the works are sited in, or operations connected
with the works in any way whatsoever pass
through, waters controlled by the Nigerian Ports
Authority the Contractor shall abide by all the
regulations laid down, and give all notices required, by
the Nigerian Ports Authority.
The site shall be handed over to the Contractor in
minimum lengths of sixteen kilometres. The date
on which each portion is taken over shall be recorded
and certified in writing by both the Engineer’s
Representative and the Contractor’s Agent and from
the date on which each portion is taken over the
Contractor shall be responsible for maintaining that
portion of road in good condition and for repairing
damage of any kind to the road culverts or bridges
arising from whatever cause save and except the
excepted risks as defined in Clause 20 of the “Standard
Conditions of Contract”.
(CLAUSE 1006-1099 INCLUSIVE NON USED)
SPECIFICATION
SECTION II
CONCRETE: MASS AND REINFORCED
SECTION II
MASS AND REINFORCED CONCRETE
GENERAL
2000.
In addition to any other relevant clause of this
specifications the following shall be deemed to apply
in particular to mass and reinforced concrete work
and shall be read in conjunction with all other
relevant clauses of the conditions of contract and this
specification
PART A - MATERIALS
CEMENT
2001. (1)
(2)
GENERAL
The cement shall be ordinary or rapid hardening
Portland cement and shall conform to the
requirements of B.S.S. 12 Portland cement (ordinary
and rapid hardening) and shall be supplied by
manufacturers of good repute to be approved by the
Engineer.
SULPHATE RESISTING CEMENT
Where the use of a sulphate resisting cement is
indicated as specified or in the bills it shall be a
sulphate resisting Portland cement of approved type
and manufacture complying with B.S.S. 12.
(3)
COLOURED CEMENT
White or coloured cement shall be of approved
quality and chemical composition and shall comply
with the physical requirements of B.S.S. 12.
(4)
BLENDING
There shall be no blending or mixing of cements and
the use of any air-entraining, wetting agents or
accelerators such as calcium chloride will only be
permitted if called for by the Engineer.
(5)
EXTRA PAYMENT
The Contractor shall not receive extra payment for
using rapid hardening Portland cement unless they
do so under the specific instructions of the
Engineer.
(6)
TEST CERTIFICATE FOR CEMENT
Each consignment of cement intended for use in the
works shall be accompanied by a manufacturer’s test
certificate showing that the cement offered has been
tested and analysed, the date and results of such tests
and analyses and that the cement conforms in all
respects with NIS 11 or B.S.12.
Where such a certificate is not available due to
exceptional circumstances which, in the opinion of
the Engineer are acceptable, then the Contractor shall
arrange for each consignment of cement to be tested
and analysed strictly in accordance with NI 11 or
B.S.12 by a tester to be selected by the Engineer and
the tester shall supply a certificate satisfying all the
requirements laid down for the manufacturer’s test
certificate. Irrespective of the results of these tests,
the Contractor shall bear all costs in connection with
or arising out of them.
(7)
INDEPENDENT TESTS ON CEMENT
In addition to any tests mentioned elsewhere in this
specification, the Engineer’s Representative may
require cement to be sampled at the manufacturer’s
works and subsequently tested by an independent
tester. No cement shall be despatched until the
results of such tests and analyses are known and have
been approved in writing by the Engineer’s
Representative. Payment for these tests shall be the
employer’s responsibility and charged against the
appropriate provisional sum, except as detailed in
Clause 36 (4) of the Conditions of Contract.
(8)
PACKING AND MARKING OF BAGS FOR
CEMENT
After each consignment of cement has been tested
and approved as complying with B.S. No. 12 and
unless approval is given by the Engineer’s
Representative for the handling of cement in bulk,
all cement shall be packed into bags of an approved
type. The bags of each consignment shall be given
a distinctive mark, to be agreed between the
Contractor and the Engineer’s Representative, also
a consignment number, so that each consignment
can be easily identified on being delivered to the
site and when being used subsequently in the
works.
(9)
NOTICE OF DESPATCH AND DELIVERY OF
CEMENT
Before ordering the despatch from the manufacturer
a consignment of cement for use in the works, the
Contractor shall give notice in writing to the
Engineer’s Representative the number of the
consignment, the name of the manufacturer and the
number of tonnes in the consignment.
When each consignment is delivered to the site, the
Contractor shall issue to the Engineer’s
Representative a written statement showing the
number of the consignment, the name of the
manufacturer, the number of tonnes in the
consignment, the number of bags and enclosing the
respective test certificates.
The statement shall also show where the
consignment is stored. Cement may be shipped in
bulk or in 50 kg bags subject to approval of the
Engineer and subject to such requirements as he may
deem necessary. Railroad cars or trucks in which
cement is shipped shall be loaded under the
supervision of and sealed by the Engineer. Cars or
trucks with broken seals may be unloaded, but the
cement shall not be used until retested and approved.
(10) STORAGE OF CEMENT ON SITE
On delivery at the Site, the cement shall be stored in
suitable, thoroughly dry and well-ventilated lock-up
sheds to be erected by the Contractor and approved
by the Engineer’s Representative. Great care must be
taken to provide a perfectly dry floor of timber or
concrete for each shed so as to prevent damp rising
to the cement. Small quantities left at the site shall be
stored on suitable platforms and protected with
waterproof covering to the satisfaction of the
Engineer.
Each consignment, brand and type of cement shall
be kept separate in the sheds and suitable labels are
to be provided for each consignment, brand and
type, on which shall be entered the consignment
number, date of despatch, date of delivery a the
site, the number of bags, the date when using
commenced and the date when using finished. All
these labels shall be handed to the Engineer’s
Representative when the cement has been used and
will be retained by him.
No cement shall be used without the permission of
the
Engineer’s Representative
and each
consignment must be used singly and in order of
delivery at the site, or as may be directed by the
Engineer’s Representative.
(11) STOCK OF CEMENT AND MONTHLY
RETURNS
The Contractor shall at all times maintain at the site
such a stock of cement as will ensure due and proper
progress of the works.
Each month, on the date corresponding to the interim
certificate date, the Contractor shall forward to the
Engineer’s Representative, a return of the various
consignments in store, giving the total tonnage at
site, the quantity received during the month, from
whom it was obtained and in what sheds it has been
deposited.
Also the quantity issued during the month, from what
consignment and sheds it was issued and in what
portion of the works it was used.
(12) TESTS ON CEMENT AFTER DELIVERY
After delivery on the site the Engineer’s
Representative may require each consignment of
cement to be subjected to any or all of the tests and
analysed required by B.S.12.
Payment for these tests shall be the Contractor’s
responsibility and deemed to be included in the
tendered rates and prices.
(13) REJUNCTION OF CEMENT
Notwithstanding the production of test certificates
whether from manufacturer tester or independent
tester, the Engineer’s Representative shall reject
any cement found not to comply with this
specification, at any time. He shall also reject any
cement which has been damaged or which has
deteriorated owing to inadequate protection during
storage or transport or any other cause. Cement
containing lumps of hardened cement or which has
been stored for more than 6 months shall not be
used.
The Contractor shall remove all rejected cement
from the site without delay and at his own expense.
(14)
ADMIXTURES
Admixtures for accelerating or retarding the setting
of the cement, etc., shall not be used in any
circumstances except with the written permission of
the Engineer. When such permission is sought, the
Contractor must supply full details of the admixture
he wishes to use.
WATER
2002.
Water used for mixing and curing concrete shall be
clean, fresh water from an approved source and it
shall be free from injurious oils, chemicals, vegetable
matter, organic and other impurities and shall comply
with the requirements of B.S. 3148.
The Contractor shall ensure that all pipes, tanks and
other receptacles for the storage of water intended for
use in the makings of concrete are kept in a clean
condition.
AGGREGATES
2003. (1)
GENERAL
The aggregate (fine, coarse and all-in) for all grades
of concrete and mortar shall comply in all respects
with B.S. 882 (1973) and the Contractor shall test all
samples as described therein and in B.S. 812 (1967)
as often as Engineer’s Representative may require, to
ensure that they are continuously up to these
standards. All aggregates shall be hard , strong,
durable, perfectly clean and free from organic matter
and deleterious coating such as clay.
They shall contain no harmful material in such
quantities as to affect adversely the strength or
durability of the concrete, or attack the reinforcement
as ascertained by tests on concrete cubes as described
hereafter and by tests as described in B.S. 882
(1973).
(2)
THE SOURCES OF ALL AGGREGATES
SHALL BE APPROVED BY THE ENGINEER’S
REPRESENTATIVE
All aggregates whether fine or coarse if considered
unsuitable by the Engineer’s Representative shall be
removed from the site by the Contractor at his own
expense.
(3)
TESTING
As soon as possible after receiving the Engineer’s
Authority to commence the works (and before
commencing any concreting) the Contractor shall
have delivered upon the site sample loads of
aggregate representative, of those proposed for the
works and shall forward samples prepared in
accordance with the method laid down in B.S. 812.
The moisture content of aggregate shall be
determined using the siphon – can procedure
notwithstanding the foregoing, Speedy Moisture
Content Apparatus may be used for measuring the
water content of fine aggregates. Each sample shall
consist of not less than 45 kg weight of fine
aggregate and 90 kg of coarse aggregate in
accordance with the specification. No aggregate
shall be used in the works until results of these tests
shall have been submitted to the Engineer’s
Representative and his approval in writing
obtained.
The minimum frequency of testing at each concrete
mixing plant shall not be less that the following:
(I)
TEST OF COARSE AGGREGATES
(i)
(ii)
Sieve analysis
7 weeks
Determination of clay, fine
silt and
fine dust (Method
B – Determination
of amount
of aggregate passing a
75 microns
3 days
(iii) Determination of flakiness
index 2 weeks
(iv)
Moisture Content immediately prior
to
commenceme nt of mixing of
concrete
for each cast and hereafter every half hour
during which concrete is being mixed
(iv)
Determination of
“ten per cent fine value”
2 weeks
(II)
(i)
(ii)
TEST OF FINE AGGREGATES
Sieve analysis
2 weeks
Determination of fine silt
and
fine
dust (Method C –
Field setting test
3 days
(iii) Estimation of organic
impurities
3 days
(iv)
Moisture content immediately
prior to
commenceme
nt of mixing
concrete for
each cast
thereafter
every
half
hour during
which
concrete is
being mixed
(III)
(i)
TESTING DRYING SHRINKAGE
Drying shrinkage
8 weeks
Notwithstanding
the
foregoing additional tests
shall be carried out as and
when directed by the
Engineer’s Representative
(4)
WASHING
Washing of aggregate may only be carried out
using clean fresh water obtained from an approved
source. The Contractor is to provide adequate
storage facilities and arrange to obtain this water at
times chosen so as to cause the minimum of
inconvenience to other consumers.
(5)
STORAGE OF AGGREGATES
The Contractor shall provide proper means of
storing the aggregates at each point where concrete
is made and in such a manner that there is no
possibility of the various aggregates mixing one
with the other. Effective precautions shall be taken
to prevent the aggregates segregating in the storage
heaps and from being contaminated by the ground
and other foreign matter.
Storage heaps shall be capable of draining freely.
Wet aggregates shall not be used until, in the
Engineer’s Representative opinion, they have
completely drained. Where aggregates are damp,
the Contractor must measure the moisture contents
of the aggregates continuously and adjust the
amounts of aggregates and added water in each
batch of concrete mixed to allow for the water
contained in the aggregates. If necessary, to meet
the requirements of this Clause, the Contractor
shall protect the heaps of aggregates from
inclement weather.
(6)
METHOD
OF
CALIBRATING
SPEEDY MOISTURE TESTER
(a)
Procedure
Sufficient fine aggregate passing sieve 1.25
mm and retained on pan shall be prepared and
dried to constant weight. Weight kg to make
20 separate number of specimen.
(b)
Air-tight moisture content tins shall be
weighed empty and to each shall be placed
200 g of the dried soil and weighed again.
(c)
Varying quantity of water as indicated in the
table below shall be added to each pair of
container and allowed self moisturization for
24 hours and weighed hereafter before placing
in the oven or for speedy tester method.
TABLE II – 1 OVEN METHOD
Tin Number
a
b
c
d
e
No. of
specimen
2
2
2
2
2
200
200
200
200
200
20
24
28
32
40
Weight of
dry
soil, g
Volume of
water cc
Note: after weighing, place all oven method tins
into a standard oven with temperature not greater
than 105°C and dry the specimen to constant
weight and thereafter determine the moisture
contents.
TABLE II – 1A SPEEDY TESTER METHOD
Tin Number
a
b
c
d
e
No. of
specimen
2
2
2
2
2
200
200
200
200
200
Weight of
dry
soil, g
Volume of
water
20
24
28
32
40
Note: for the speedy tester, use the apparatus to
determine the moisture content of each pair of
specimen to constant moisture reading. The
average reading of each pair shall be the moisture
of the specimen. Same holds for the oven method.
(d)
FINE
AGGREGATES
2004. (1)
Calibration
Plot a straight line graph of oven moisture
against speedy tester results. By using the
plotted graph, speedy test results can be
converted to oven method results.
GENERAL
Fine aggregates shall either comprise natural quartz
sand or be obtained by crushing clean granite or shall
consist of naturally occurring sand obtained from
fresh water river deposits or a combination thereof
and shall comply with Grading Zone 1 or Grading
Zone 2 of B.S.882 or such other grading as may be
approved by the Engineer (see Table II-2).
(2)
FINE DUST
The total quantity of fine dust passing through a 75
µm mesh sieve in fine aggregate derive by crushing
rock shall be determined by the method described in
B.S. 812 and shall not exceed 8% by weight.
(3)
QUANTITY OF CLAY AND SILT
The total quantity of clay and silt in natural sand
shall not exceed 4% by weight when determined by
the field settling test decantation method described
in B.S. 812. The quantity of organic impurities
present in natural sand shall not be such as to
produce a reaction as dark as the standard solution
when the organic impurities are determined by the
method described in B.S.812 (1975).
TABLE II – 2
FINE AGGREGATE GRADING ENVELOPES
BS 410
P
ercentage by weight passing B.S.
es
siev
Test sieve
Grading
ZONE 1
Grading
ZONE 2
Grading
ZONE 3
Grading
ZONE 4
10.00mm
100
100
100
100
5.00mm
90 – 100
90 – 100
90 – 100
95 – 100
2.36mm
60 – 95
75 – 100
85 – 100
95 – 100
1.18mm
30 – 70
55 – 90
75 – 100
90 – 100
600µm
15 – 34
35 – 59
60 – 79
80 – 100
300µm
5 – 20
8 – 30
12 – 40
15 – 50
150µm
0 – 10
0 - 10
0 – 10
0 - 15
For crushed stone sands, the permissible limit is
increased to 20% because of its non clay nature of
the fine materials. The 5% tolerance permitted may
be applied to the percentages. In the last three sets
of sieves, it can be applied as follows: 1% on the
first of the three sieves and 2% on the others or 4%
on one sieve and 1% on others. The application of
tolerances will depend upon the shape of the
grading graph.
COARSE
2005. (1)
AGGREGATE
GENERAL
Coarse Aggregate shall comprise natural gravel or
crushed granite obtained by crushing sound hard
granite taken from a source approved by the
Engineer’s Representative and shall contain no
harmful material in sufficient quantity to adversely
affect the strength or durability of the concrete or in
the case of reinforced concrete to attack the
reinforcement. All coarse aggregate shall be
washed after crushing if necessary to comply with
the specification. The flakiness index when
determined by the method described in B.S. 812
(1975) shall not exceed 30 per cent. The individual
pieces shall be roughly cubical or spherical in
shape and have neither glassy nor powdery
surfaces..
(2)
CRUSHING VALUE
The aggregate crushing value of coarse aggregate
shall not exceed 45 per cent when determined by the
method described in B.S. 812.
(3)
THE GRADING
The grading of coarse aggregate particles is required
to satisfy strictly the percentage stated for 20 mm to
5 mm nominal sizes stated in the B.S. 882 with a
content not exceeding 1% passing the B.S. 2.4mm
sieve size. The percentage passing through 75µm
sieve shall be determined by the method described in
B.S. 812. Sieve shall comply to the requirements of
B.S.410.
STEEL
2006. (1)
REINFORCEMENT
GENERAL
The reinforcement shall be one of the following:
(I) Rolled steel bars or hard drawn steel wire
complying with the requirements of B.S. 78
“Rolled steel bars and hard drawn steel wire for
concrete reinforcement” and B.S. 4449 (1969).
Hot-rolled steel bars for the reinforcement of
Concrete.
(II) Cold twisted steel bars complying with the
requirement of B.S. 114 “Cold twisted steel bar
for concrete reinforcement and B.S. 4461
(1969). Cold works steel bars for the
reinforcement concrete.
(2)
(III) Such other reinforcement as may be suitable
having regard to the yield stress, ductility
tension strength and other essential properties.
DIAMETER OF BAR
The diameter of any Bar for the purpose of this
code should be taken as that of a circle having an
area equal to the cross-section area of the bar.
At the option of the Contractor, the reinforcing bars
can be purchased from the manufacturer using
metric units provided that the area of required steel
will not be rounded downwards.
When the diameters of the reinforcing bars are
given in one system on the contract drawings and
they do not have exact equivalent of the bar in
another system, the basic dimension must be
converted to the nearest higher cross section area.
The cost arising from additional weight of the
reinforcing steel shall be borne by the Contractor.
(3)
TEST CERTIFICATES
For each consignment of steel reinforcement used
in the works, the Contractor shall supply a
certificate giving the ultimate strength, yield stress,
elongation and result of the cold bend test
described in B.S. 4449 and B.S. 4461. The
Engineer’s Representative shall have power to
select pieces of steel for testing if no test data are
supplied by the Contractor and the costs arising out
of such tests shall be borne by the Contractor.
Reinforcement obtained from re-rolling scrap metal
shall not be used.
(4)
DELIVERY
When each consignment is delivered to the site, the
Contractor shall issue to the Engineer’s
Representative a written statement showing the
number of the consignment, the name of the
manufacturer, the number of tonnes in the
consignment.
(5)
STORAGE
Reinforcement shall be stored on site in racks off
the ground and shall be protected from rusting,
damage, oil or other deleterious matter and shall be
clean and free from all such matter before concrete
is placed.
(6)
MEASUREMENT AND PRICES FOR STEEL
REINFORCMENT
The prices inserted in the Bill of Quantities for steel
reinforcement shall include for supplying,
handling, bending, wiring, placing, cutting,
cleaning, supporting and every other expenses
necessary to complete the works as shown on the
drawings or as may be directed by the Engineer.
The Contractor shall be paid for the net calculated
weight of reinforcement, excluding binding wire
used in the work, in accordance with the drawings
or as may be directed by the Engineer’s
Representative and no allowance will be made for
margins or otherwise.
WATERPROOF
BUILDING
PAPER
2007.
Waterproof Building Paper used as an underlay
to concrete to prevent the loss of cement or as a
means of providing a non-bonding joint between two
parts of any structure shall comply with the
requirements of B.S. 1521 (1949) with the extra
provision that the material shall not become sticky in
the roll under any of the climatic conditions
encountered in Nigeria.
JOINT SEALING
COMPOUND
AND PRIMER
2008. (1)
JOINT COMPOUND
The joint sealing compound shall be hot poured
material approved by the Engineer. The material
shall adhere readily to the concrete and to the primer.
It shall be ductile, not excessively soft or tacky at a
temperature of 82°C nor brittle at a temperature of
2°C.
(2)
PRIMING PAINT
A priming paint suitable for the joint scaling
compound used, shall be applied to the concrete
surfaces prior to the pouring of the sealing compound
with the object of improving the adhesion.
PART B – WORKMANSHIP
PROPORTIONS
OF CONCRETE
MIXES
2009. Concrete to be used in the works shall be a mixture
of cement, fine aggregate, coarse aggregate and
water
and the various grades of concrete to be used shall be
in accordance with Table II – 3.
CONCRETE
MIX DESIGN
2010. At the commencement of the works, the Contractor
shall indicate the type of compaction which he
intends to use in the various parts of the works and
obtain the approval of the Engineer’s representative.
thereto. The Contractor shall then design mixes for
as
concrete of grade as required, each design
fulfilling
the following requirements:
(A) The cement, the aggregates and the water shall
all comply with the appropriate clauses of
this specifications.
(B)
The cement shall not be less than that shown
in Table II – 3 of this specification
The water content for each mix shall be in
accordance with Clause 2013 (2) of this
specification and shall be such as to give the
required compacting factor and/or slump:
where different methods of compaction are to
be employed for the same grade of concrete,
involving different compacting factors and/or
slump, then a separate design mix shall be
prepared for each case to satisfy the
requirements of the appropriate clause of this
specification.
Following the Engineer’s Representative’s approval
of the mix designs, the Contractor shall prepare, in
the presence of the Engineer’s Representative, a trial
mix of each design grade of concrete. The mixes
shall be prepared as follows.
(C)
TRIAL MIXES
2011.
Before mixing, a sieve analysis of the aggregate
shall be made by the method described in B.S. 812
/1975) and the weight and volume of the cement,
fine aggregate, coarse aggregate and water
comprising the mix carefully determined. Each trial
mix shall be not less than half a cubic meter in bulk
before mixing and shall be mixed as specified in
Clause 2012 of this specification in a mechanical
mixer of the type approved for use in the works.
The compacting factor and slump of each trial mix
shall be determined immediately after mixing as
directed in NIS 12 B.S. 1881 (1970) and shall not
exceed the maximum value obtained in the mix
design.
Each trial mix shall be handled and compacted by
the methods which the Contractor proposes to use
for that mix in the works, and the mixes shall show
no tendency of inadequate compaction by the
methods proposed.
Six cubes of 150 mm compression test cubes shall
be made from each trial mix. The cubes shall be
made, cured, stored and tested in accordance with
the requirements of B.S. 1881 (1971).
Table II – 3 REQUIREMENTS FOR CONCRETE FOR STRUCTURES AND GENERAL CONSTRUCTION
1
2
3
4
MINIMUM
CEMENT
CONTENT
PER M3 OF
FINISHED
CONCRETE
GRADE OF
CONCRETE
MAXIMUM
SIZE OF
AGGREGATE
N/mm2
mm
Kg
PRESTRESSED
CONCRETE
50
20
500
45
20
-do-
40
-do-
PURPOSE
5
6
7
WATER
CEMENT
RATIO
WORKS TEST MINIMUM
COMPRESSIVE STRENGTH
IN N/mm2
CEMENT
7 Days
28 Days
0.35-0.45
40
50
Rapid
450
0.35-0.45
35
45
Hardening
20
425
0.35-0.45
30
40
Portland
cement
35
20
400
0.45-0.55
25
35
REINFORCED
CONCRETE
30
20
350
0.45-0.55
20
30
-do-
25
20
295
0.45-0.55
15
25
-do-
20
20
235
0.45-0.55
12
20
-do-
15
20
205
0.55-0.65
10
15
MASS
CONCRETE
12
40
175
0.55-0.65
7
10
Ordinary
Portland
cement
10
BLINDING
CONCRETE
40
150
0.65-0.75
7
10
Three cubes shall be tested 7 days after manufacture and
three 28 days after manufacture. The strength requirements
of the cubes at each age shall be considered to be satisfied
if non of the strengths of the three cubes tested each age
falls below the appropriate design strength or if the average
strength of the three cubes is not less than the strength and
the difference between the greatest and least strengths is
not more than 20 per cent of that average.
Failing this, the Contractor shall re-design the mix and
make such further trial mixes and test such further cubes as
the Engineer’s Representative may direct until the
requirements of this specification are satisfied.
The design mixes which fulfil the requirements of this
specification for a particular grade of concrete shall be
called the approved mixes for that grade of concrete and
the Contractor shall only use the approved mixes where
that grade of concrete is specified and shall not depart
therefrom with out the written permission of the Engineer’s
Representative. The Engineer’s Representative may require
further trial mixes and further cube tests to be made before
such permission is given.
The Contractor shall allow ample time in his programme
for designing and making trial tests mixes and for the
preparation and testing of compression test cubes obtained
therefrom. Should any design mix fail to satisfy the
requirements of this specification and should the Engineer
consider that it is essential to commence the production of
that grade of concrete before the results of the cube tests of
a further design mix are available, he will consult with the
Contractor and decide on an interim mix for use until such
time as the results of the cube tests have become known,
any extra cost involved being borne by the Contractor.
The Contractor shall be deemed to have satisfied himself
that the materials on which he has quoted will produce a
concrete which, with the specified nominal proportions and
subsequent adjustments as indicated by trial mixes, will
develop the cube strengths specified and at same time have
the desired workability in the work itself.
The cost of all trial mixes, test cubes and their testing shall
be deemed to be included in the tendered rates for concrete.
MIXING OF
CONCRETE
2012. (1)
GENERAL
Concrete shall be mixed in mechanical mixers of the
weigh-batch type as stated in the Contractor’s mix design
proposal, complying with the requirements of B.S. 1305
(1967) and fitted with an approved weight measuring
device. No hand-mixing will be permitted. Mixing shall
continue until there is a through distribution of the
materials and the mass is of uniform colour and
consistency. The period of mixing, judged from the time
that all materials including the water are in mixer, shall be
not less than that or should not be more than 2 minutes per
m3 or as recommended by the manufacturer. The concrete
mixer shall revolve at the speed recommended by the
manufacturer, or as ordered by the Engineer’s
Representative. The entire contents of the drum shall be
discharged before materials for the next batch are fed in.
Should there, for any reason, be a stoppage greater than 30
minutes duration, the drum of the mixer shall be
thoroughly washed out with clean fresh water before
mixing is resumed. Stationary mixers shall be equipped
with an acceptable timing device that will not permit the
batch to be discharged until the specified mixing time has
elapsed.
(2)
RE-MIXING OF CONCRETE
No partly set concrete shall be placed in the works.
Concrete which has commenced to set shall not be remixed
either with or without additional water and in no case shall
such concrete be used in the works.
QUALITY
OF CONCRETE
2013. (1)
APPROVAL OF MATERIALS ETC.
Before their use in the works, the Contractor shall show, to
the satisfaction of the Engineer’s Representative that all
materials and methods of storage and mixing to be
employed in the production of concrete, conform in every
way with the requirements of this specification.
Such deliveries of materials to the site as the Engineer’s
representative may designate shall be tested and analysed
to ensure that they do so comply and the tests shall be
carried out sufficiently in advance of their intended use in
the works to allow the results to be studied and the
materials approved, modified or rejected by the engineer’s
Representative as the case may be. The Contractor shall
remove all rejected materials from the site without delay
and at his own cost. Permission to use any material shall
not be construed as an approval of its source nor any
acceptance as continued acceptance.
(2)
COMPACTING FACTOR
Workability of concrete shall be measured by compacting
factor. The Contractor shall provide a compacting factor
apparatus conveniently accessible to each concrete mixer
and shall measure the compacting factor by the method
described in B.S. 1881 at frequent intervals or as
frequently as the Engineer’s Representative may direct, but
in any case, tests shall be carried out at least once every
half-anhour during which concrete is being mixed.
Whenever the compacting factor varies from that of the
approved mix the quantity of water added to the mix shall
be immediately adjusted to counteract the variation. The
successive values of the compacting factor and the quality
control chart, which shall be kept near the mixer and
submitted to the Engineer’s Representative for his
inspection as he may direct. Notwithstanding the
foregoing, the “V-B” consistometer test may be used in
place of the compacting factor test and in such cases tests
shall be carried out in accordance with the
recommendations of the manufacturer of the “V-B”
Consistometer, see B.S. 882 part 19.
The Contractor shall ensure that all their concrete mixer
operators are aware of the importance of maintaining
uniform controlled quality of the concrete and that they are
experienced in detecting variations in concrete quality and
workability and in rapidly correcting the same.
(4)
TESTS ON AGGREGATES
In addition to the tests mentioned above, as frequently as
the Engineer’s Representative may decide and at least once
each day when concreting is in progress, the Contractor
shall sample and test the aggregates due shortly for
incorporation into the works as follows: the tests being
carried out in accordance with B.S. 812 (1975).
(I)
SIEVE ANALYSIS OF BOTH COARSE AND
FINE AGGREGATE
The gradings of all aggregates must be within the
respective limited specified in Clause 2004; failing
which the Engineer or his Representative shall
instruct the Contractor to make such modifications
to the proportions of aggregate in the mix as will
allow for such difference and the Contractor shall
immediately do so.
(II)
DETERMINATION OF CLAY, FINE SILT AND
FINE DUST IN THE FINE AGGREGATE –
FIELD SETTLING TEST
Should the amount of clay, fine silt and fine dust
exceed 4% by volume, then the Contractor shall
refrain from using the aggregate until he satisfies
the Engineer’s Representative of its suitability for
making concrete of the quality required.
(IV) DETERMINATION OF ORGANIC IMPURITIES
Should the colour produced by the test be as dark as
the standard solution, the aggregate shall not be
used until further comparative compression tests
specified in B.S. 882 (1973) have been carried out
and given satisfactory results.
(5)
PROTECTION OF CEMENT
During windy weather, effective precautions shall be taken
to prevent the cement from being blown away during the
process of apportioning and mixing. One method of
checking this is by use of wide planks as wind breakers in
the directions of the wind. During wet weather both cement
and concrete shall be adequately protected either by
covering with polythene or tarpaulin.
(6)
PRELIMINARY CUBE STRENGTH TESTS
(I)
Prior to the commencement of any concreting work
and subsequently whenever a change is intended in
the materials or the proportions of the materials to
be used, preliminary cube strength tests shall be
made in accordance with B.S. 1881, “Methods of
Testing Concrete”, to establish that the mean
strength of the mix conforms with the design
requirement. Reliance shall not be placed on the
strength obtained from only one set of three test
specimens, but separate samples of the material to e
used, taken on three occasions at intervals of not
less than one day, shall be forwarded to the testing
authority for preliminary cube strength tests. From
each sample of material, six cubes shall be made,
three for test at seven days and three for test at
twenty-eight days.
(II)
WORKS CUBE STRENGTH TESTS
Works Cubes, whether required for the normal
method or for the special method of quality control
described respectively hereunder shall be made and
cured in manner described in B.S. 1881. Where the
concrete is vibrated, the cubes shall be compacted
by similar means in such a way that full
compaction of the concrete with neither segregation
nor excessive latex is obtained. Samples of concrete
from which works test cubes shall be made shall be
taken in accordance with B.S. 1881 and in
particular at the time and place of deposition of the
concrete and at such other times and places as the
Engineer’s Representative will direct.
(III)
The frequency of sampling for each concrete
mixing plant used for the Contract shall be as
follows:
(1) when each mix is first made for use in the
works, batches shall be sampled at the rate of
8 batches per day for the first 5 days of using
that mix or at such other times as directed by
the Engineer’s Representative until a total of
40 batches have been sampled, with a
minimum requirement that:
(i)
one batch shall be sampled each day
particularly when any concrete of a
particular mix is made
(ii)
one batch shall be sampled for each
cast of concrete to be post tensioned.
(2) thereafter one sample shall be taken on each day
any grade of concrete is made.
Notwithstanding the foregoing, additional samples
shall be taken by the Contractor as and when
directed by the Engineer’s Representative.
From each sample of concrete and at the place
where the sample was taken six test cubes shall be
made; 3 shall be tested at an age of 7 days and 3 at
an age of 28 days. The test cubes shall be made
cured and tested in accordance with B.S. 1881. If
cured at a mid-point temperature of 27° C, then the
20° C strengths will be assumed to be 0.80 times
the 27° C strength.
For the strength of concrete to be acceptable to the
Engineer, the following shall be achieved:
(1) each test cube shall have compressive strength
of not less than that specified on the drawings
(2) notwithstanding the provision of sub-clause (1)
above, should the 20° compressive strength of a
test cube or cubes tested at an age of 7 days be
below the minimum specified strength, then if
the other test cubes of the set tested at 28 days
comply with the Specification, the concrete
shall be deemed to have passed the tests.
(3) Notwithstanding the foregoing provisions of the
Clause, the quality control exercised at each
mixing plant and for each mix shall be such that
the overall average 20°C compressive strength
achieved (measured in N/mm2) minus 1.64
multiplied by the standard deviation achieved
(measured in N/mm2) shall be more that or
equal to the specified minimum 28 days 20°c
compressive strength.
Overall average compressive strength and standard
deviation shall be calculated from the results
obtained from the latest forty consecutive sets of 3
test cubes of any one mix and from any one mixing
plant.
∑
S=
x 2
(x - ∑ )
N
N-1
∑ ( x)
S=
2
-
(∑ x)
2
N
N −1
where N = Number of cubes tested x = 28 day
compressive strength
of 150 mm cube in
N/MM2
S=
Standard deviation in N/MM2
Notwithstanding the foregoing, the standard
deviation shall not be calculated for a mix until
there are at least 40 sets of 3 test cube results
available.
Test reports shall include the following information:
(1)
(2)
(3)
reference number of test cubes
class of concrete
location of concrete in works from which the
sample was taken
(4) time and date test cubes were taken
(5) age of test cubes at test and curing conditions
(6) workability
(7) cement/fine aggregate/coarse aggregate ratio
by weight
(8) water/cement ratio by weight
(9) individual and average compression strengths
of the 3 test cubes and assumed 20°C values if
different
(10) individual and average densities of the 3 test
cubes
(11) average compressive strength and standard
deviation for which the mix has been
designed
(12) overall average 20°C compressive strength
and standard deviation achieved using the
results obtained from the latest forty
consecutive sets of 3 test cubes made from the
same mix and the same mixing plant.
(13) overall average compressive strength from
(12) minus 1.64 multiplied by deviation from
(12)
If results of the cube tests do not comply with the
Specification and/or if the figure from item (13) of
the test report is less that the specified minimum 28
day compressive strength, then either the quality
control at the relevant mixing plant shall be
improved to the satisfaction of the Engineer’s
Representative or the mix shall be redesigned to the
satisfaction of the Engineer’s Representative. If
directed by the Engineer, redesign of the mix shall
include carrying out further preliminary laboratory
tests in accordance with the Specification with the
redesigned mix.
(IV)
INDEPENDENT CUBES
The Contractor shall arrange for the Engineer’s
representative to be present during the sampling of
the concrete and the manufacture, storing and
curing of the cubes to ensure that there is complete
agreement between himself and the Engineer’s
Representative that the said cubes are entirely
acceptable as test cubes. Should the Contractor fail
to arrange for the Engineer’s Representative to be
present when required or decline to do so, the cubes
so manufactured will not be accepted as test cubes.
Should the Contractor wish to make independent
test cubes he may do so at his own expense, but the
results will not be valid unless the cubes are
manufactured in the presence of the Engineer’s
Representative and tested by an approved Agency,
all in accordance with B.S. 1881. The approved
form, giving the reference number of the cube, its
size and weight, the grade of concrete from which it
was made, the compaction factor, the date on which
it was made, the date on which it was tested, the
total load in kN at which it failed, the stress in
N/mm2 and the location of structure at which the
sample of concrete was taken. Two copies of each
test certificate, containing all the information
mentioned above, shall be forwarded to the
Engineer’s Representative for his retention and a
third copy retained in the Contractor’s laboratory.
(V)
FAILURE OF TEST CUBES FOR STRENGTH
REQUIREMENT
Should either the test cubes crushed at 7 days or
those crushed at 28 days or both, fail to satisfy to
specified requirements, the Contractor shall, on the
Engineer’s Representative instructions, take one or
more of the following steps:
(A)
(B)
(C)
(7)
he shall alter the design of the mix to
increase its average compressive strength
he shall alter the method of making the
concrete and controlling its quality to reduce
the variability of the concrete
he shall cut out and replace concrete placed
in the works on any day in which a cube was
made and failed it, in the opinion of the
Engineer’s Representative, such concrete is
likely to be incapable of fulfilling its
purpose. The Engineer may require the
Contractor to cut out defective concrete from
the works even though test cubes made from
that concrete have not failed. This may arise
if the concrete failed to meet other salient
features and quality standard like the
following:
(i)
honey combing
(ii)
cold joint
CORRELATION OF TESTS
Tests on concrete materials and concrete shall be made as
often as directed by the Engineer’s Representative and at
instances such that the test results can be directly
correlated to the works tests cubes for a particular batch of
concrete.
(8)
COST OF TESTS
The Contractor shall bear the cost of carrying out and
supplying all labour, materials and equipment for the sieve,
silt, organic impurities, bulking, compacting factor and
slump tests mentioned above and any other tests required
by the Engineer or the Engineer’s Representative to ensure
proper quality control of the concrete. He shall also bear
the cost of supplying all labour, materials and equipment
necessary for the preparation of the compression test cubes
and their subsequent storing, curing, packing,
transportation and testing. All costs arising out of
modification to the concrete mixes, cutting out and
replacing of defective concrete and all other work carried
out in accordance with this Clause shall be borne by the
Contractor.
TRANSPORTATION 2014.
OF CONCRETE
Concrete shall be taken from the place of mixing to the
place of deposition by methods which will prevent the
drying out and consolidation of the concrete, the
segregation and loss of the ingredients, and which are
sufficiently rapid to ensure that the concrete does not
commence to set before it is finally compacted in position.
During transportation, the concrete shall be protected from
all adverse effects of sun, wind and rain. The concrete shall
be deposited by means of chutes through a depth exceeding
3 meters. All mixers, barrows, spades and other mixing and
distributing equipment will be thoroughly clean before
commencing each period of use and shall be kept free of
partly set concrete which shall not be used in the works. No
concrete shall be transported over or near to new work that
has insufficiently hardened, in order to prevent harmful
vibration of the new work and no planks or ways for skips,
etc. shall be supported on either formwork or reinforcement
for the same reason.
PLACING AND
COMPACTION
No concrete shall be placed in any part of the works
until written permission to do so has been obtained from
the Engineer’s Representative. Well in advance of the
intention to place concrete, the Contractor shall forward to
the Engineer’s Representative for his approval full
information about the order in which he proposes to place
concrete in the various parts of the works, the height of
each lift of concrete, details of the shuttering which he
proposes to employ with relevant calculations and positions
of all construction joints.
All construction joints shall be formed as specified in
Clause 2019 and there shall be no stoppage of the placing
of concrete except at such proper construction joints.
2015.
The Contractor will be required to furnish the Engineer’s
Representative with satisfactory evidence that all
preparation, precautions and provisions have been made to
ensure that the concrete shall be placed and compacted in
accordance with this specification before the Engineer’s
Representative will give his permission for concreting to
proceed.
For members involving “vertical” placing of the concrete
(e.g. piers) each lift shall be deposited in layers extending
for the full width between shuttering and of such depth that
each layer can be easily and effectively incorporated wit
the layer below by the means of compaction being
employed. The layers shall be placed horizontally, sloping
beds not being permitted unless particularly so specified.
For members involving “horizontal” placing of the
concrete (e.g. deck slabs), the concrete shall be placed
along the line of the starting point, in such quantities as
will allow the member to cast to its full depth along the full
width between side shutter and then gradually brought
towards the finishing point along entire front, parallel to
the starting line, the tampers for giving required surface
and compaction following as closely behind practicable.
All members shall be concreted at such a rate as eliminate
any possibility of fresh batches of concrete be deposited
immediately adjacent to batches which have been
commenced to set and all members shall be poured in one
continue operation until completed, no interval being
allowed to lapse with the work is in hand.
Care shall be taken to ensure that the process of placing
concrete does not cause any harmful vibration to adjacent
work that has insufficiently hardened.
Should any unforeseen occurrence result in a stoppage of
concreting for such a time as might allow the concrete
already placed to begin to set before the next batches can
be compacted into place, the Contractor shall immediately
insert, at his own cost, a proper end-shutter to form a
proper tongue and groove construction joint as specified in
Clause 2019 normal to the work at that point which will
ensure that the section already cast is formed complete in
accordance with this specification. Any additional
reinforcement required as a result of the joint shall be
provided by the Contractor at his own expense.
No concrete for work which will present a large exposed
surface (e.g. deck slab) shall be placed in the direct rays of
the sun and the Contractor shall erect shades to protect
such work therefrom.
Compaction of the concrete shall be effected by either hand
or mechanical means and all compacting tools must be
approved by the Engineer’s Representative before being
used in the works. The concrete shall be worked well up
against whatever surface it adjoins and compacted to such
a degree that it reaches its maximum density as a
homogeneous mass, free from air and water holes, and
penetrates to all corners of the moulds and shuttering and
completely surrounds the reinforcement. Care shall be
taken to ensure that neither hand pounders nor mechanical
vibrators come into contact with the formwork,
reinforcement or any embedded fittings and to prevent the
operation of compaction from transmitting any harmful
vibration or shocks to concrete which has not yet hardened
sufficiently.
Compliance with the conditions of this clause may require
working longer than usual and the Contractor must allow
for this in his schemes for concreting and in the rates for
the work inserted by him in the Bill of Quantities.
CONCRETE
PLACED UNDER
WATER
2016.
Concrete shall be placed under water only where
particularly so specified and approved by the Engineer’s
Representative. The quantity of cement in any concrete
placed under water shall be increased by at least 25 per
cent above the cement content of the appropriate approved
mix. Concrete shall be placed in still water only and every
precautions shall be taken to prevent the cement and fine
materials from being washed out of the concrete. Concrete
shall be placed either with a tremie or a bottom opening
box of a type approved by the Engineer’s Representative.
Bottom opening boxes shall not be opened until they are
resting on the work and the lower ends of tremie pipes
shall always be kept below the surface of the wet concrete
already deposited. No concrete shall be allowed to fall
through water at any time. Concrete shall be place evenly
over the whole area enclosed by the shuttering and must
not be raked over, only the minimum of screeding being
allowed once the concrete has been replaced.
Concrete under water shall be placed in accordance with
the provisions of the British Standards Code of Practice
2004 (8.2.2.3.3 or 8.2.2.3.4).
PROTECTION
2017.
AGAINST
CHEMICAL ACTION
In cases where concrete is to be deposited against ground
known or suspected to contain sulphate salts or other
deleterious chemical agents, sulphate resisting Portland
cement shall be used instead of ordinary Portland cement.
The sulphate resisting Portland cement shall be of
approved manufacture and in accordance with B.S. 12
(1958) and in such situations where its use is required,
particular care shall be taken to keep the ground water
level below the level of concrete being placed until that
ATTENDANCE
OF JOINER AND
STEEL FIXER
2018.
CONSTRUCTION
JOINTS
2019.
concrete has hardened and has been cured as specified in
Clause 2022.
During all concreting operations, the Contractor that a
competent joiner and a competent shall ensure steel fixer
(in the case of reinforced work most especially in work in
which fittings are embedded) are in attendance on each
concreting operation. It shall be their duty to ensure that
the formwork is maintained in accordance with the
specification, temporary construction joints inserted as
necessary, and reinforcement and fittings maintained in
place as the work proceeds.
All construction joints in all classes of work shall be
formed by inserting stopping off boards normal to the
work to form a tongue and groove joint as detailed on the
drawings and against which the concrete can be properly
compacted. They shall be formed in the position shown on
the drawings or as directed and approved by the Engineer’s
Representative. There shall be no construction joints in
precast members nor in the reinforced concrete deck slabs
of minor spans. In the case of tee beams the rib and slab
shall be cast together in one continuous operation. In other
work, construction joints shall be located at points where
shear stresses or tensile concrete stresses are a minimum
and at place where they will least effect the appearance
and properties of the finished works, but no construction
joint may be inserted without the written approval of the
Engineer’s Representative. All reinforcement required by
the Engineer’s Representative as a consequence of the
position selected for any proposed construction joint shall
be provided by the Contractor at his own cost, unless, in
the opinion of the Engineer’s Representative, the joint is
absolutely necessary and there is no alternative position for
such joint.
When work is resumed against a horizontal surface which
has hardened or recently set, the surface of the concrete
shall be roughened by hacking and all laitance, loose and
porous material and poorly compacted concrete shall be
removed from it. When reinforcement or fittings project
from the older concrete, these shall be carefully cleaned,
utmost care being taken not to break the bond and freed
from all adherent coatings of concrete and other matter
likely to reduce the bond between the steel and the
concrete about to be poured. The surface of the concrete
(and steel if applicable) shall then be swept clean, brushed
with a steel wire brush to remove all loose material,
saturated with water, thoroughly cleaned and all surplus
water removed. A 12mm layer of stiff, freshly mixed
mortar containing the same proportions of cement and fine
aggregates as the grade of concrete immediately before
concreting commences and the fresh concrete carefully
pounded into it without delay.
When work is to be resumed against a vertical face which
has hardened or recently set, the surface of the concrete
(and projecting steel and fittings if any) shall be treated
exactly as described above for horizontal surfaces, but the
application of the 12mm layer or mortar shall be omitted
and the fresh concrete shall be thoroughly compacted
against the damp vertical surfaces after the final saturation
with water and the final through cleaning.
All costs incurred in complying with the requirements of
this clause shall be deemed to be included in the tendered
rates for concrete.
JOINTS TO
PREVENT
BONDING OF
ADJACENT
SURFACES
2020.
SURFACE
FINISHES
2021.
Where it is specified on the drawings that a joint is to
inserted to prevent bonding between two adjacent parts of
the structure, the Contractor shall insert two layers of
approved building paper between those parts as specified.
The paper shall be tailored to fit the surfaces of the
structure in the positions accurately without any folding or
wrinkling and cut overlapping edges shall be covered with
adhesive tape to prevent any turning or movement during
concreting operations. Throughout the area of the joint,
there must be not less than two thicknesses of approved
waterproof building paper. Concreting operations and
pounding etc. shall be carried out carefully to ensure that
no damage shall be done to the paper.
All concrete surfaces not requiring shuttering shall be
smooth finished with approval floats to give a dense
surface with a minimum of cement and fine materials
being brought to the surface. The top surface of deck slabs
shall be tamped to a smooth finish, aided by floats if
necessary, to the levels, falls and cambers shown on the
drawings or as instructed. The tamping shall not be done to
the extent of bringing an excess of fine materials to the
surface.
Shuttered surfaces of work in mass concrete which will
always be in contact with the ground and more than 0.5
meters below finished ground level on the external surfaces
of abutments and piers may be cast against sawn timber
shuttering. All other surfaces, including all reinforced work
and all precast and prestressed, shall be cast against steel or
planed timber formwork. Any surfaces, irrespective of the
shuttering employed, which show honeycombing or voids
shell be made good by cutting back the concrete to behind
the reinforcement in the case of reinforced work or to such
depth as the Engineer’s Representative may specify in the
case of mass work, and in either case to sufficient depth to
remove all defective concrete, but no repair work shall be
started until after the defective surfaces have been
inspected by the Engineer’s Representative. The cut shall
be slightly belled to ensure that the new surface will be
keyed to the sound concrete and the new surface will be
cast in accordance with the requirements of this
specification and against shuttering which has been
carefully aligned with the sound concrete in either side and
tightly secured in position by wedging etc.
All exposed concrete surfaces shall be fair finished t othe
entire satisfaction of the Engineer’s Representative.
All concrete surfaces shall be protected from damage and
disfigurement due to the subsequent pouring of concrete or
the carrying out of other work in the vicinity or any cause
whatsoever, and the Contractor shall remove all blemishes
and repair all such damage to the satisfaction of the
Engineer’s Representative.
All costs for making good honeycombed and defective
concrete and repairing damages surfaces shall be deemed
to be included in the rates for concrete and shuttering
inserted in the Bill of Quantities.
CURING
OF CONCRETE
2022. (1)
GENERAL
During curing of the concrete, all precautions shall be
taken to ensure a slow heat evolution and the absence of
cracks. The temperature of the hot concrete surfaces
should not be subjected to sudden changes by spraying of
cold water and the concrete must be protected from
sunshine and wind. Freshly placed concrete must be
protected from rain.
If low heat Portland cement is preferred, the cement shall
conform to the requirements of B.S. 1370.
(2)
WATER CURING
Very great importance is attached to the proper curing of
the freshly placed concrete and the Contractor must ensure
that is effectively done. All newly placed concrete shall be
protected from the effects of rain, drying winds and the
sun by suitable screens of damp hessian or damp sand after
the concrete has hardened sufficiently to support them
directly without marking. The ends and sides of the screens
shall be held down at the edges to prevent draughts from
getting underneath. As soon as the concrete has hardened
sufficiently to support the coverings without marking, it
shall be covered with clean sacks, Hessians or a 50mm
thick layer of clean sand or other approved material which
shall be kept continuously in a wet condition by frequent
spraying with fresh clean water. Where the concrete to be
cured is enclosed by shuttering, the shuttering shall be
covered with clean sacks or hessian which must be kept
continuously in a wet condition. When the shuttering is
removed, the damp hessian or sacks shall be hung directly
around the concrete member and kept continuously wet by
spraying with clean fresh water. Providing that the
shuttering has been covered with approved mould oil
which will prevent the timber from absorbing water from
the concrete, the time that the concrete remains in
formwork under the conditions herein specified shall count
a s part of the curing period. Curing of all concrete shall
continue for at least 7 days or as directed by the Engineer’s
Representative or as otherwise specified. On no account
must the surrounding sacks, hessian, etc. be allowed to dry
out during the curing period. The cost of curing shall be
deemed to be included in he tendered rates for concrete.
(3)
RESINOUS CURING
As an alternative method of curing, the surface may be
protected,
where approved
by
the
Engineer’s Representative by treating with an
approved resinous curing compound, mechanically
sprayed on the surface of the finished concrete at a rate
approved by the Engineer’s Representative as soon as it is
possible to produce a membrane of uniform thickness.
Unless otherwise directed by the Engineer’s
Representative, the compound shall be applied
immediately after completion of the laying and finishing
of the concrete. Any groove over a joint shall be
protected from the entry of curing liquid.
FORMWORK
2023. (1)
GENERAL
All formwork shall be adapted in every respect to the
structure and to the required surface finish for the concrete.
It shall be fixed in perfect alignment and securely propped
and braced so as to withstand without displacement,
distortion or movement of any kind the weight of
construction and the movement of persons, materials and
plant.
It shall be sufficiently watertight to prevent any loss of
liquid from the concrete and shall be capable of being
removed without shock, vibration or damage to the
concrete.
Where wrot shuttering is specified, the faces to be in
contact with the concrete shall be planed perfectly smooth
and true, to form in all the surface, curves or shapes
specified and joints shall be planed and perfectly
watertight.
Where rough shuttering is specified the faces to be in
contact with concrete shall be planed smooth and true to
form. All joints must be true and perfectly tight.
All formwork for new lifts of concrete shall be tightly and
accurately fitted against the concrete already cast to ensure
that the surface of the new work will be quite flush and in
line with that of the old.
Wedges and clamps shall be used wherever practicable
instead of nails and where it is proposed to employ
mechanical vibration the formwork shall be strengthened
accordingly by increasing the number of bracing and
props, nailing wedges in position and using screws instead
of nails where necessary. Particular care shall be taken to
ensure that joints remain tight during the process of
vibration.
All forms for beams and kindred members shall be
designed and constructed so that the sides may be removed
without disturbing the bottom boards or supports thereto.
The bottom of each form shall be set with a camber of
1/300th of the span or as otherwise specified or required
according to the dimensions of the beams. The supporting
struts shall be adjusted and securely fixed in position by
approved means.
Formwork for encasing steel joints shall be suspended from
the joints to relieve the concrete of dead-load stresses.
Unless otherwise specified, fillet strips shall be fixed in the
shuttering to form a chamber 12mm by 12mm on all
external corners of the finished work.
Should the Contractor wish to erect the formwork by
passing ties through the work or embedding bolts therein,
he must first obtain the approval of the Engineer’s
Representative and when seeking such approval, shall
forward full details of the type of fitting proposed for use
and show how it will be employed in the work. No type of
fitting will be permitted which cannot be removed easily
after use or which does not allow easy and effective
making good of the concrete surface. The use of wires, etc.
requiring subsequent cutting into, and plastering over, of
the concrete will not be permitted.
Where steel shuttering is to be used, it shall be of approved
manufacture and panels shall fit tightly and accurately to
form a true surface and joints which will not allow the
escape of liquid from the concrete. All rivet and bolt heads
must be countersunk on the inside face and finished flush
so as to leave no mark on the resulting concrete surface.
The provisions for timber shuttering specified above shall
also apply to steel shuttering as applicable.
If metal forms are used, the metal shall conform to
provisions of the B.S. 4360. For prestressed units
additional 10KN/M2 shall be added to the weight of
wet concrete in the design of horizontal areas of
formwork.
the
the
the
the
All side forms for the prestressed units shall be eased as
early as possible and the soffit forms shall permit
deformation of the member when the prestressed is
applied.
The formwork should be designed to withstand the
additional forces due to the vibrations during concrete
placing. The soffit shutter should be adequately supported
to prevent any settlement which might cause cracking of
the concrete. On the soffit shutter, provision should be
made for the elastic shortening of the concrete under
prestressed.
An upward camber shall be given to ensure that the girders
do not sag under working loads. The Contractor shall make
measurement before and after concreting each section, and
submit the results to the Engineer.
The Contractor shall notify the Engineer in advance of the
time he proposes any adjustments to the forms prior to
concreting next section, should any adjustments be needed.
All surfaces of the formwork which will come into contact
with the wet concrete shall be painted with an approved
non-staining mould oil, to prevent adhesion between
concrete and formwork. The mould oil shall be insoluble in
water, unharmful to the concrete, non-flaking and shall not
be removable by rain or wash-water. The Contractor shall
ensure that the oil shall be kept from contact with the
reinforcement or embedded fittings.
Before placing any concrete, all shavings, loose binding
wires, soil, rubbish and all foreign matter shall be removed
from the formwork and the formwork shall be carefully
and thoroughly washed with water. Loose planks shall be
incorporated in the bottom of panels of shuttering to
facilitate the removal of rubbish from the section to be
concreting, as necessary.
No concrete shall be placed until the Engineer’s
Representative has inspected the formwork and props and
given his approval to do so.
(2)
STRIPPING
No formwork shall be removed without the prior approval
of the Engineer’s Representative and in no case shall any
shuttering or props be removed before the periods
mentioned in Table II – 4 have elapsed after placing the
concrete.
TABLE II – 4 FORMWORK MINIMUM
STRIPPING TIME
TYPE OF WORK PART OF WORK
SLABS
SOFFIT
BOARDS
PROPS
ORDINARY PORTLAND
CEMENT CONCRETE
5 DAYS
14 DAYS
BEAMS
SIDE BOARD
3 DAYS
BOTTOM BOARDS 14 DAYS
PROPS
28 DAYS
COLUMNS
WALLS,
PIERS AND
ABUTMENTS
7 DAYS
MASS CONCRETE 3 DAYS
REINFORCED
7 DAYS
CONCRETE
While props are to be left in position under slabs and
beams the formwork shall have been made in such a
fashion that it can be removed without disturbing the props
in any way, otherwise it must be left in position for the full
period that the props are left in position.
The formwork shall be removed by gradual easing without
jarring and only under competent supervision. Before
removal of the shuttering, the concrete shall be examined
and removal shall only be proceeded with if the concrete
has attained sufficient strength or sustain all the loads to
which it will be subjected. The Contractor shall be
responsible for any injury or damage to the work caused by
or arising out of the removal of formwork and props and
any advice permission or approval given by the Engineer’s
Representative, relative to the removal of formwork and
props shall not relieve the Contractor of this responsibility.
(3)
MEASUREMENT AND PRICES FOR FORMWORK
All timber or metal moulds inclusive of all necessary
supports and stagings (unless billed separately), bolts, nuts,
straps, clamps, wedges and other fixings also all cutting
and waste and cost of all labour and materials in making,
erecting and removing the formwork and for any other
work required to construct the forms to shapes and
dimensions shown on the drawings or as directed by the
Engineer, shall be included in the rate for formwork.
Formwork shall be measured as the net area in contact with
the finished concrete surface. No measurement will be
allowed for formwork for temporary construction or
daywork joints.
REINFORCEMENT 2024.
Schedules of steel reinforcement giving the location,
SCHEDULES
bending, diameter, length and number of the various bars
may be incorporated in the drawings or prepared on
separate sheets. These schedules have been prepared for
the convenience of the Contractor, but their accuracy is not
guaranteed. It will be the Contractor’s responsibility to
check all the schedules against the drawings and to satisfy
himself as to errors, omissions and all other things
regarding their suitability for the work before such work is
put into operation. All discrepancies shall be brought to the
notice of the Engineer’s Representative immediately and
well in advance of placing the reinforcement in the works.
Where new schedules are required or existing ones require
to be amended, the Contractor shall prepare such new or
amended schedules in accordance with B.S. 4466 (1969)
and forward three copies of each to the Engineer’s
Representative well in advance of placing reinforcement in
the work. The Contractor shall be responsible for his own
ordering sheets.
The cost of checking all new and amended schedules as
specified above shall be deemed to be included in the
tendered rates for reinforcement.
BENDING
AND2025. (1)
FIXING OF
REINFORCEMENT
GENERAL
All reinforcing bars shall be carefully bent with an even
and gradual motion to the correct dimensions by
experienced steel benders and in a manner which will not
injure the material. In particular, no reinforcement shall be
heated before bending. Unless stated to be otherwise in the
schedules, all bends and bending shall be in accordance
with B.S. 4466.
Unless otherwise directed or authorized by the Engineer,
the number, size, form and disposition of all reinforcing
bars shall be strictly in accordance with the drawings. Bars
generally must be of the required lengths and lapping and
welding of main bars will not be permitted unless so
indicated on the drawings.
All reinforcements shall be rigidly in position. To prevent
displacement before and during concreting the bars shall be
bound together at all intersections with annealed soft black
iron wire of 1.5 mm diameter and the ends of the wire shall
be turned inwards, away from the surface of the member.
Where necessary, upper layers of reinforcement shall be
maintained in position by “chairs” made from bars of
suitable size and supported on the lower layers of
reinforcement. The chairs shall be securely tied to both
upper and lower layers of reinforcement and shall be of
such shape as will produce a frame of sufficient stiffness.
Details of the chairs showing their size, bending and
disposition in the work shall be forwarded to the
Engineer’s Representative for his approval before
incorporation into the work. The use of temporary supports
will not be permitted.
Any parts of metal supports that are left in place within
50mm of an exposed surface of the concrete shall be
nonrusting metal or coated with non-rusting metal.
Galvanized of such parts will be acceptable provided the
weight of the zinc coating per 1000cm2 of actual surface
shall average not less than 56 grams and no individual
specimen shall show less than 50 grams.
Splicing of reinforcement steel, except where shown on the
drawings or approved by the Engineer, will not be
permitted. Splices shall have a length sufficient to develop
the full strength in bond of the bar, and shall not be made
at points where the section is insufficient to provide at least
50 mm between the splices and the nearest adjacent bar or
the surface of the concrete. At splices, the bars shall be
rigidly clamped or wired together in a manner acceptable
to the Engineer. Where practicable, reinforcement shall be
assembled as rigid cases before placing in the formwork.
Concrete blocks shall be used to maintain the correct
distance between the reinforcement and the formwork i.e.
to maintain the correct concrete cover to the reinforcement.
Such blocks shall not exceed 50 mm in width nor 50 mm in
length and their thickness shall be exactly that required to
give the cover specified on the drawings. Binding wires
shall be securely embedded into each block to permit
adequate fastening to the reinforcing bars. The number and
location of the blocks used in the work shall be to the
satisfaction of the Engineer’s Representative.
All reinforcement shall be perfectly clean and free from
loose scale, rust, oil, grease and any other matter which
might reduce the bond between the steel and the concrete.
Loose pieces of binding wire and other foreign matter shall
be removed.
The Contractor shall provide adequate scaffolding, boards,
runways etc. to ensure that the reinforcement is not
displaced during concreting by being walked upon. No
runways, etc. shall be supported on the reinforcement. The
ends of bars which will project beyond the limits of the
section being concreted shall be adequately supported and
protected to prevent them from being damaged or removed
by collision, wind or any other cause which might result in
a reduction of the bond between the steel and concrete or
any movement of those portions of the bars lying within
the freshly poured concrete.
No concrete shall be poured until the Engineer’s
Representative has inspected and approved the
reinforcement and the arrangements for placing the
concrete and the Contractor has ensured that competent
steel-fixers and carpenters are in attendance,. See Clause
2015.
(2)
ELECTRIC ARC WELDING
Electric Arc Welding may be permitted for joining bars,
provided the approval of the Engineer has been obtained
and for work of this type the use of electrodes of the
covered alloy or shielded arc type will be permitted,
provided that they conform to the requirements for Class A
electrodes, as described in B.S. 639 “C” Covered
Electrodes for Metal Arc Welding Wrought Iron and Mild
Steel”. Workmanship shall conform to the general
requirements of B.S. 693 (1960), 1856 (1964) and 2642
(1965) as applied to the general building construction. All
such connections shall be butt-welded with standard
Double V or Double U welds.
PRECAST
CONCRETE
UNITS
PART C – PRECAST CONCRETE UNITS
(NOT TO BE PRESTRESSED)
GENERAL
2026.
The requirements of the foregoing clauses for concrete will
apply to all precast work where applicable and in addition
the following special clauses are to be observed. Rapid
hardening Portland cement shall conform to the
requirements of B.S. 12 and may only be used with the
approval of the Engineer or his Representative.
(1)
FORMWORK
All formworks are to be such as to ensure true arris and
sound surfaces and metal lining formwork will generally
be required by the Engineer.
(2)
DIMENSIONS
Units are to be formed to the dimensions and tolerances
shown on the drawings.
(3)
MOULDS
Units are to be made in strongly constructed moulds which
are closely jointed, perfectly smooth and true in alignment.
The moulds must be constructed so that no bulging or
distortion can occur during consolidation of the concrete
and should be fitted with suitable fastenings to facilitate
easy removal without injury to the units.
(4)
MANUFACTURE
The Contractor shall provide facility for the Engineer or his
Representative to carry out any tests or inspection during
all stages of manufacture as may be required to ensure the
quality and soundness of the units. The proposed method
of manufacture is to be approved by the Engineer before
production of the units commences. All units shall have
impressed upon them in some convenient position the date
of manufacture and such distinguishing letters as the
Engineer may direct.
(5)
CURING
The moulds will be struck at such a time so that the units
are not subject to risk or damage or distortion. All concrete
shall be kept damp for seven days and protected from the
direct rays of the sun for a further of 14 days. This can be
achieved by covering roof or tent.
(6)
CURING AND LIFTING OFF MOULDS
(7)
Concrete surfaces and moulds shall be protected during
casting and for 14 days thereafter form the effects of sun,
wind and rain etc. and the concrete shall be cured for a
period of 7 days after casting all to the satisfaction of the
Engineer’s Representative. The striking of moulds shall be
without damage to or distortion of the concrete surfaces.
REJECTED UNITS
Units which show signs of honeycombing or are badly
pitted on any of the faces or are otherwise defective will be
rejected and must be immediately broken up.
(8)
STACKING
Units are to be stacked to the approval of the Engineer’s
Representative and arranged so that they are available for
use in order of age.
(9)
TRANSPORT AND DELIVERY
The methods of transporting and delivery of the units to
site must be such that the units are protected from severe
shock and any damage whatsoever. The proposed methods
of loading, transporting and off loading must be approved
by the Engineer or his Representative before delivery
commences.
(10)
STANDARD FOR PRECAST CONCRETE WORK
Precast concrete goods, whether they have been purchased
for use in the works, or manufactured by the Contractor
shall be in accordance with the requirements of the
following British Standards, as applicable:
B.S. 340 Precast Concrete Kerbs, Channels, Edging and
Quadrants
(11)
B.S. 368
Precast Concrete Flags
B.S. 556
Concrete Cylindrical Pipes and Fittings
B.S. 1194
Concrete Porous Pipes
B.S. 2028
Precast Concrete Blocks
RECONSTRUCTION OF FAULTY WORK
Should any portion of the work give evidence, in the
opinion of the Engineer or his Representative that the
concrete is of inferior quality, insufficiently compacted,
segregated or improperly deposited and rammed in the
forms or that any of the reinforcement or fittings has been
omitted, incorrectly placed or subsequently displaced or
that is suffers from any defects, omission or injury form
any cause whatsoever which may adversely affect the
strength or durability of the construction, the Contractor
shall, on the written instructions of the Engineer, remove
and reconstruct that portion of the work in such manner as
the Engineer shall direct or approve to ensure that the
requirements of this specification are fulfilled.
No repairs shall be made to any faulty work until it has
been inspected by the Engineer’s Representative and his
permission to proceed obtained. All costs involved in the
reconstruction of faulty work shall be borne by the
Contractor.
PART D – CEMET MORTARS AND GROUTS
CEMENT
MORTARS
AND GROUTS
2027.
Mortar and Grouts shall be composed of Portland cement,
sand and water satisfying the requirements of this
specification and mixed together in the proportions
indicated in Tables 11-5 and 11-6. The cement and sand
shall be measured by volume in gauge boxes of approved
size. The common size is 0.03m3. The gauge boxes shall
be filled with the respective materials without compaction
and struck level, proper allowance being made for any
bulking of the sand due to moisture content. Mixing shall
be done in an approved mechanical mixer, the amount of
water added being just insufficient to give the consistency
and workability desired by the Engineer’s Representative
for the use to which the mortar is to be put. Mixing shall
be carried out as specified for concrete.
Hand-mixing of mortar will only be permitted where very
small quantities are required and the approval of the
Engineer’s Representative has been obtained. In such
cases, the dry sand and cement shall first be mixed together
by turning over with a clean shovel or trowel on a clean
steel platform or other approved surface until a mixture of
uniform colour has been obtained.
Water shall then be added, a little at a time, the mixture
being turned over after each addition, until a homogeneous
paste has been obtained. This process shall be repeated
until the required consistency has been obtained. Only
perfectly clean implements and surfaces shall be used in
hand-mixing and care shall be exercised to ensure that no
cement is washed away during the addition of the mixing
water.
All mortar must be in its final position in the works within
30 minutes of the initial mixing together of the sand,
cement and water.
TABLE II – 5 MORTAR – CEMENTS AND MIXING
PROPORTIONS
MORTAR
QUALITY
NOMINAL
MIX
PROPORTIONS
BY VOLUME
PORTLAND
CEMENT
SAND
M1
1:1
1
1
M2
1:2
1
2
M3
1:3
1
3
M4
1:4
1
4
Note: Allowance should be made for moisture content of sand
BUILDING 2028.
IN FOUNDATION
BOLTS, FITTINGS
All foundations, bolts, fittings, kerbs, etc., are to be built
into the work as concreting proceeds by supporting them
either form the formwork in their correct position or
grouted into recesses cast in the work as specified or
directed by the Engineer or his Representative. Recesses to
accommodate such item shall be cast against properly
constructed formwork and in no circumstances shall they
be formed by cutting out green concrete. Similarly, no
fittings shall be positioned in the works by inserting into
concrete which has commenced to set.
KERBS. ETC.
The Contractor shall set the metal work which is to be
embedded into position before concreting. All items shall
be carefully cleaned, placed and firmly secured to ensure
that it will not be displaced during concreting operations.
Anchor bolts shall be placed by means of templates
supplied by the Contractor. All threads shall be carefully
greased after the bolts are firmly in position, but prior to
concreting. The position of all embedded items shall be
carefully observed during and at the completion of
concreting operations to ensure they are in the proper
position upon completion of the work.
EMPLOYMENT
OF CONCRETE,
MORTAR AND
GROUT
2029.
The grade of concrete, mortar or g rout to be used in the
various parts of the work shall be as specified on the
drawings. Where no specification is given on the drawings
as to the grade of concrete, mortar or grout to be used, it
shall then be as given in the following Table II – 6 below.
TABLE II – 6 MORTAR FOR GROUTING MIX
PROPORTIONS
GRADE
MIX
USE
M1
1:1
GROUTING IN HOLDING
DOWN BOLTS, BEDDING
GIRDER
BEARINGS, PACKING
BETWEEN
STEEL JOISTS AND
EXISTING
DECKS, MAKING GOOD
CONCRETE SURFACES,
PIPE JOINTING ETC.
M3
1:3
BEDDING & JOINTING
PRECAST
KERBS
M4
1:4
STONE PITCHING
The materials shall be mixed to a
consistency suitable for the
purpose intended. All mortar shall
be used within 30 minutes after the
mixing water has been added.
Admixtures of hydrated lime, fire
clay, diatomaceous earth or other
approved inert material may be
used in the mortar to facilitate
workability if the Contractor elects.
The amount of admixture to be
added shall be of the quantity
permitted by the Engineer.
PART E – GRANOLITHIC
CONCRETE FLOOR
FINISHED
CEMENT
2030.
All cement used in the works shall
be from an approved source, and
shall comply with the latest
appropriate Nigerian Industrial
Standards or British Standards.
The type of cement to be used in
Portland high alumina cement is to
comply with the latest revision of
B.S. 915.
The provisions of foregoing
clauses relating to ordinary
Portland cement shall apply to high
alumina cement where applicable.
Concrete shall be made with
specially selected aggregates of a
hardness surface texture and
particle shape suitable for use as a
wearing finish to floors, all to be to
the latest B.S. 1201.
All aggregates fine and coarse shall comply with the
requirements for aggregates for concrete work and shall be
subject to the approval of the Engineer’s Representative.
AGGREGATES 2013.
GRANOLITHIC
TOPPING
2032.
Granolithic Topping shall be composed of Portland high
alumina cement, fine aggregate as specified and granite
chippings as specified. The water/cement ratio shall not
exceed 0.45 and shall be kept as low as possible
compatible with workability.
Typical mixes are:
2 parts of Portland high alumina cement to 5 parts of fine
granite chippings by volume, graded as to B.S. 1201
(1954) or
1 part of Portland high alumina cement to 1 part of sand, to
2 parts of fine aggregate, the aggregate passing a 150
microns (100 mesh) sieve but free from dust.
THE SUB-FLOOR
2033.
The Granolithic Topping shall be laid and floated on a new
concrete sub-floor within 12 hours of laying the latter.
Where the sub-floor consists of an existing concrete
surfaces, this shall be hacked, thoroughly cleaned, wetted
and brushed over with cement grout prior to laying
granolithic topping.
LAYING
2034.
The Contractor shall ensure that successive trowellings are
applied at appropriate times by skilled workmen.
The topping shall be rendered with a wood float and struck
off with a steel trowel after the set has commenced. The
topping shall be laid to a thickness of 25mm to 40mm.
Slightly increased thicknesses are necessary when the
topping is laid on matured concrete sub-floors.
The toppings shall be divided into bays not larger than
about 3.5m x 3.5m laid alternatively or as directed.
CURING
2035.
Granolithic topping shall be cured for a period of seven
days after laying all as for normal concrete.
RETARDING
OF DUSTING
2036.
A solution of calcium chloride added integrally or a
solution of sodium silicate or other surface hardener as
approved by the Engineer’s Representative shall be used to
retard dusting. The amount of solution added shall be as
specified by the respective manufactures or as directed by
the Engineer’s Representative.
CARBORUNDUN
FINISH
2037.
For non-slip finish to treads of stairs and to landing
surfaces, carborundum thickly sprinkled in the proportion
of 1.50 kg per square metre of paving shall be used, being
well trowelled in before the granolithic sets.
GRANOLITHIC
MONOLITHIC
TOPPING
2038.
Where granolithic monolithic topping is ordered, it shall be
applied in the following matters:
Concrete shall be laid to finished level and while it is still
wet and soft shall be sprinkled with a mixture of 1 part of
chippings to 1 part of high alumina Portland cement mixed
together in a dry state and applied at a rate of spread of
8kg/m2 of surface.
The chippings shall consist of a suitably graded material
6mm to dust with not more than 20% content of fine
material.
This mixture shall be tamped-in with a wooden float and
twice trowelled with a steel trowel to a smooth and fine
finish. After the topping is dry it shall be treated with one
application of 10% solution of silicate of soda.
DAMP PROOFING 2039.
MISCELLANEOUS
The surface to be damp proofed shall be primed and then
thoroughly mopped with waterproofing asphalt.
The mastic asphalt shall be laid in two courses in the
manner described in British Standard Code of Practice CP
144 Part 2. Joints shall be staggered at least 150 mm
between courses.
When the first mopping of asphalt has set sufficiently, the
entire surface shall then be mopped with a second coating
of hot asphalt. Special care shall be taken to see that there
are no skips in the coatings and that all surfaces are
thoroughly covered. The two sides of all joints shall be
intimately bonded. The surfaces of any gullies and other
features with which the waterproofing will be in contact
shall be clean and painted with bitumen.
The cost of all materials, labour, tools, equipment and
incidentals and for doing all the work involved in applying
the damp proofing, complete in place as shown on the
drawings or as directly by the Engineer, shall be deemed to
be included in the tendered rates for concrete.
SPECIFICATION
SECTION III
PRESTRESSED CONCRETE
SECTION III
PRESTRESSED CONCRETE
GENERAL 3000. In addition to any other relevant clause of this
Specification, the following shall be deemed to apply in
particular to prestressed concrete work, and shall be read
in conjunction with all other relevant clauses (especially
those referring to mass and reinforced concrete) of the
conditions of Contract and this Specification.
This work shall consist of pre-stressing pre-cast concrete by furnishing, placing and
tensioning of pre-stressing steel in accordance with details
shown on the drawings and as specified in the
specifications.
This work shall include the furnishing and installation of any appurtenant items necessary for
the particular prestressing system to be used, including
but not limited to sheaths, anchorage assemblies and grout
used for pressure grouting sheaths.
The Contractor shall submit to the Engineer for his approval plans and working drawings.
The working drawings, of the pre-stressing system shall
contain details and substantiating calculations of method
and materials the Contractor proposes to use, in the prestressing operations including any additions or
rearrangement of reinforcing steel from that shown on the
drawings. Such details shall outline the method and
sequence of stressing and shall include complete
specifications and details of pre-stressing steel and
anchoring devices, working stresses, anchoring stresses,
type of sheaths and all other data pertaining to the prestressing operation, including the proposed arrangement
of the pre-stressing steel in the member.
Working drawings shall not exceed 594 mm x 841 mm in size and each drawing and
calculation sheet shall include the job site, name of the
structure as shown on the contact drawings.
Working drawings shall be submitted sufficiently in advance of the start of the affected work
to allow time for review by the Engineer’s Representative
and correction by the Contractor of the drawings without
delaying the work. In no case shall such time be less than
six weeks.
Throughout the pre-stressing work the Contractor shall
employ on the works at least one suitably qualified
engineer who shall be experienced in the systems of
prestressing being used. His duties shall be as follows:
1) Supervision of the storage and fixing of pre-stressing
components
2) Calibration of pre-stressing equipment
3) Compilation of tensioning operations
4) Supervision of grouting operations
5) Compilation of tensioning records
6) Such other duties as the Engineer’s Representative may
direct
All personnel operating the stressing equipment shall
have been properly trained in its use. In addition to the
normal precautions against accident which should be
taken at all times for the whole of the Works, special
precautions shall be taken when working with the tendons
which have been tensioned or are in the process of being
tensioned.
The personnel should not stand in line with the tendons,
their anchorages or jacking equipment. Simple protective
measure such as stout timber shields sheathed with steel
should be placed in line with tendons and behind the
jacks to protect personnel passing in the usual course of
their duties, if applicable.
PART A – MATERIALS
CEMENT
3001. The Cement shall be rapid-hardening Portland
cement in accordance with the latest B.S. 12 with all latest
amendments or
Portland
blast furnace
cement conforming to the requirements of B.S. 146 with all
latest amendments. The use of high alumina cement will
not be permitted.
The cement is to be packed in waterproof bags or steel drums and delivered to the site in first
class condition. Each consignment is to be clearly
marked with the date of manufacture and the date of
arrival. The drums of cement are to be lifted and handled
with care so as to avoid damage; and stored in a damp
free location ready for use. The consignment is to be
used in the order of arrival to the site.
Cement is to be stored on site under cover from the
weather and is to be protected from deterioration. Each
drum is to be fully used once opened and no cement is to
be stored in drums, which have previously been opened.
AGGREGATES
3002.
All concrete aggregates to be used for prestressed
concrete work shall be properly cleaned and graded
strictly to the requirements of the latest B.S. No. 882 to
which end the Contractor shall provide washing and
grading equipment on the site.
Materials, which are rejected from the grading process,
may be used up in 10 N/mm2 grade concrete in other parts
of the works at the discretion of the Engineer’s
Representative. Any rejected material is to be removed
forthwith from the site by the Contractor at his own
expense.
(1)
FINE AGGREGATE
Fine Aggregates shall consist of naturally occurring sand
obtained from fresh water river deposits approved by the
Engineer’s Representative. The grading of sand particles
shall satisfy the percentages stated for Zones 1 or 2 in
B.S. 882, and as given in Table III-I.
(2)
COARSE AGGREGATE
Coarse Aggregate shall consist of natural gravel or
crushed granite rock obtained from a source to be
approved by the Engineer or his Representative. The
grading of coarse aggregate particles shall strictly satisfy
the percentages for 19.0mm – 4.76mm nominal size
stated in B.S. 882 as given in Table III-1 with a content
not exceeding 1% passing the 2.36mm sieve size.
TABLE III-I GRADING OF FINE AND COARSE AGGREGATES
PERCENTAGE PASSING
AGGREGATE
SIEVE SIZES
150
µm
300
µm
600
µm
1.2
mm
2.4
mm
4.76
mm
9.5 mm
19.0
mm
38.1 mm
FINE
AGGREGATE
ZONE 1
0-10
5-20
15-34
30-70
60-95
90-100
100
-
-
0-10
8-30
35-59
55-90
75-100
90-100
100
-
-
-
-
-
-
0-1
0-10
25-55
95-100
100
FINE
AGGREGATE
ZONE 2
COARSE
AGGREGATE
(3)
WATER
3003.
UNTENSIONED
3004.
REINFORCEMENT
TESTS
Samples of the chosen aggregates shall be delivered to
site and prepared by the Contractor at his own expense.
Methods of testing shall be in accordance with Clause
203 (3) of these specifications. Samples of each
aggregate are to be submitted by the Contractor to a
testing authority approved by the Engineer or his
Representative. The Contractor shall obtain from the
Engineer or his Representative written approval of the
tests and types of aggregate chosen, together with the
proposed arrangement for use on the works.
The Water to be used for concrete manufacture shall be
clean water free from chemical or organic impurities and
dissolved salt solutions, which may have a harmful effect
on the concrete. The Ph value shall range from 6.8 to 7.5.
Periodic test on water used for concrete should be carried
out on site in accordance with B.S. 3148.
Such reinforcement is to be of mild steel or high yield
steel, as specified in the drawings. Mild steel
reinforcement shall be rolled mild steel bars as reinforced
concrete works and shall comply in all respect with the
latest B.S. 4449.
Un-tensioned high-tensile steel reinforcement shall be
hard drawn pre-stressing wires as specified hereunder,
hot rolled high yield deformed bars complying with B.S.
4449 or cold worked deformed bars complying with B.S.
4461.
PRE-STRESSING
STEEL
For the purpose of this specification the term “PreStressing Tendon” or “Tendons” shall mean a single wire,
bar or strand or a number of wires or strands or a number
of wires or strands grouped into a cable or a group of
bars.
3005.
(1)
The pre-stressing steel should be one of the following:
(I)
Plain hard-drawn steel wire complying with the
requirements of B.S. 2691 “Steel for prestressed
concrete, Part 1 Plain hard-drawn steel wire”.
(II)
Indented or crimped hard-drawn steel wire
complying with the requirements of B.S. 2691 in
all respects except that for the bend test.
(III)
High tensile steel bars of open hearth steel with
sulphur and phosphorus contents each below 0.05
per cent.
(IV)
Bars whether plain or deformed should have a
tensile strength of not less than 926 N/mm2 with a
0.2 per cent proof stress of not less than 75 per
cent or more than 92 per cent of the actual
ultimate strength. For methods of testing see B.S.
18, “Tensile testing of metals”.
Such other wires, strand, or bars having properties
not inferior to those laid down in B.S.
2691 or sub-Clause (III) above respectively.
Seven wire steel strand for prestressed concrete shall
comply with B.S. 3617.
Notwithstanding the foregoing stand shall comply with the
following:
(2)
(1)
It shall contain no welds
It shall be at least low relaxation strands complying
with Section 3 or B.S. 3617
TABLE III-2 PHYSICAL PROPERTIES OF PRE-STRESSING STEEL
NOMINAL
BREAKING LOAD
PRESTRESSED
DIAMETER
STEEL
KN (1000 kgf)
mm
Wire
7
5
Strands
Bars
65 6.63) to 69 (7.038)
35 (3.57) to 38 (3.876)
MINIMUM
ELONGATION
TO FRACTURE
IN GAUGE
LENGTH
6%
6%
4
25
(2.55)
6%
8
10
13
22
25
28
67
94
160
480
650
800
(6.834)
(9.588)
(16.320)
(48.960)
(66.30)
(81.60)
10%
10%
10%
10
12%
12%
REMARKS
Tensile Testing is
to be carried out
as per
BS 5896
Mechanical
Testing of Steel
Wires
Additional
Mechanical
Properties which
are not specified in
this Table shall be
subject to the
approval of the
Engineer
All bars in any individual member shall be of the same
grade. When bars are to be extended by use of couplers,
the assembled units shall have a tensile strength, of not
less than manufacturer’s minimum guaranteed ultimate
tensile strength, when tested in accordance with Test
Method No. California 641, or equal. Failure of any
sample to meet this requirement will cause for rejection
of the heap of bars and lot of couplers. The location of
couplers in the member shall be subject to approval by
the Engineer.
(2)
(V) The Engineer may permit the use of pre-stressing
steel manufactured to standards equivalent to
those mentioned above provided that minimum
strength requirements are complied with as
indicated in this specification.
CERTIFICATE
Copies of Manufacturer’s Test Certificate and
stress/strain diagrams shall be furnished by the Contractor
and given to the Engineer or his Representative for each
consignment of pre-stressing steel reinforcement. These
Certificates must be submitted to and approved by the
Engineer or his Representative before the pre-stressing
steel reinforcement is used in the works.
(3)
DELIVERY
All pre-stressing steel shall be protected against physical
damage and rust or other exposure that will result to
corrosion at all times from manufacture, to grouting or
encasing in concrete. Pre-stressing steel that has sustained
physical damage at any time shall be rejected. The
development of visible rust or other results of corrosion
shall be cause for rejection, when ordered by the
Engineer.
Pre-stressing steel shall be packaged in containers or
shipping forms for the protection of the steel against
physical damage and corrosion during shipping and
storage. A corrosion inhibitor which prevents rust or
other results of corrosion shall be placed in the package or
form, or shall be incorporated in a corrosion inhibitor,
carrier packaging, material type, or when permitted by the
Engineer, may be applied directly to the steel. The
corrosion inhibitor shall have no deleterious effect on the
steel or concrete or bond strength of steel to concrete.
Packaging or forms damaged from any cause shall be
immediately replaced or restored to original condition.
The shipping packaging and the form shall be clearly
marked with a statement that “PACKAGE CONTAINS
HIGH-STRENGTH PRE-STRESSING STEEL, PLEASE
HANDLE WITH CARE”. The type, kind and amount of
corrosion inhibitor used, including the date when placed,
safety orders and instructions for use shall be indicated.
(4)
STORAGE
Coils and bundles of pre-stressing steel shall be stored flat
on a floor raised off the ground and under full cover from
the weather. They shall be protected from damage, oil,
corrosion or any deleterious matter, and shall not be
opened until required. Before being manufactured into
pre-stressing cables, the wire shall be cleaned free from
loose rust and any deleterious matter, and inspected by
the Engineer’s Representative for approval. Prestressing
steel reinforcement which shows signs of pitting or has
any surface defects such as splits, roughness or necking is
not be used, and any lengths of wire or strand so affected
are to be cut out of the coil and rejected.
(5)
TESTS
Tests on pre-stressing steel in addition to those of the
manufacturer may be required by the Engineer and the
Contractor is to make all arrangement to supply samples
for testing to a nominated testing authority.
SHEATHING
3006.
Sheathing to pre-stressing tendons is to be of corrugated
type such as “hydrarigid” or similar, approved by the
Engineer. Sheathing enclosures for pre-stressing steel
shall be mortar-tight and accurately placed at the
locations shown on the drawings or approved by the
Engineer. All sheathings or anchorage assemblies shall
be provided with pipes or other suitable connections for
the injection of grout after pre-stressing, sheathings for
pre-stressing steel shall be securely fastened in place to
prevent movement.
After installation of the forms, the ends of sheathings
shall at all times be covered as necessary to prevent the
entry of water or debris.
The Contractor shall demonstrate to the satisfaction of the
Engineer that the sheathings are free of water and debris
immediately prior to installation of the steel.
All sheathing for continuous structures shall be vented
over each intermediate support, and at additional
locations as shown on the drawings. Vents shall be
12.5mm minimum diameter standard pipe. Connections
to sheathings shall be made with metallic structural
fasteners. The vents shall be mortar-tight, taped as
necessary and shall provide means for injection of grout
throughout the vents and for sealing the vents. Ends of
vents shall be removed 25 mm below the roadway surface
after grouting has been completed. Grout vents shall be
provided at crests and valleys in the duct profile and at
intervals of not more than 15 metres in straight ducts.
All sheathing for continuous structures, except sheathings
in bent or pier caps, shall consist of rigid galvanized
ferrous metal. Transition couplings connecting the rigid
sheathings to anchoring devices need not be galvanized.
At the Contractor’s option, such rigid sheathings may be
used in simple spans prestressed members.
Rigid
sheathings may be fabricated with either welded or
interlocked seams. Galvanizing of the welded seam will
not be required.
Rigid sheathings shall have sufficient strength to maintain
their correct alignment during placing of concrete. Joints
between sections of rigid sheathings shall be positive
metallic connections, which do not result in angle
changes at the joints. Waterproof tape shall be used at the
connections.
Corrugated sheathing is to be delivered to the site coiled
on to large diameter wooden drums, securely fastened and
protected from damage, or stored straight in containers.
Corrugated sheathing is to be stored on site under cover
from the weather and shall be protected from rusting
damage, oil or any other deleterious matter and shall be
clean and free from all such matter before being used in
the works.
PART B – WORKMANSHIP
CONCRETE
PROPORTIONS
3007. (1)
PRELIMINARY TESTS
Preliminary Tests to determine the grade 50 N/mm2, 45
N/m mm2 concrete mix proportions for prestressed work
shall be undertaken as soon as the sources and qualities of
cement, water and aggregate have been chosen.
(2)
PROPORTIONS
The Contractor shall deliver, to a testing authority to be
approved by the Engineer, sufficient quantity of cement
and prepared aggregates to enable concrete cubes to be
made.
Such cubes shall be manufactured under
laboratory conditions, using dry aggregates and
proportions calculated to give the desired workability and
10% more than the average 28 days works cube strength
given in Table II-3 Clause 2009. At the same time the
contractor shall arrange to make two concrete mixes on
site using the same proportions of cement, water and
aggregates as used in laboratory tests, with the methods to
be adopted for the whole of the works. Six cubes shall be
made from the second batch of concrete out of the mixer
and subsequently tested by the approved testing authority.
The amount of water used for mixing under site
conditions shall take into account the weight of water
contained in the wet aggregates stored at the mixer and
the weights of aggregates used shall be adjusted
accordingly.
(3)
PROCEDURE
The results of these preliminary tests shall give cube
strengths of not less than 10% more than those stated in
Table II-3 Clause 2009 in the case of cubes made under
laboratory and at least the values stated in Table II-3
Clause 2009 in the case of cubes made under site
conditions.
All cubes shall be 150mm x 150mm x 150mm and made
in standard steel moulds according to the procedures
described in B.S. 1881 and shall be vibrated. As a result
of these tests, the mix proportions for the prestressed
concrete work shall be chosen and approved by the
Engineer. Thereafter these proportions shall be adhered
to throughout the works and may be varied only on
instructions given by the Engineer’s Representative.
(4)
WATER CEMENT RATIO
The Water-Cement Ratio shall be chosen from the
laboratory tests, and shall be taken as the total weight of
water added to the mix using completely dry aggregates,
divided by the total weight of cement. The amount of
water to be added to each batch of concrete under site
conditions, shall be calculated from the results of
moisture tests on the aggregates and the weight of cement
used for each batch, using the same total watercement
ratio as used in the laboratory tests. No deviation from
this water cement ratio shall be made except with written
approval of the Engineer’s Representative.
Strict
adherence to established water cement ratio can be
maintained during the manufacture and placing of
concrete by using slump value established during mix
design exercise.
FIELD TESTS
3008.
The Contractor is to provide the following apparatus on
site for the testing of aggregates and concrete mixes
which, where applicable, shall comply with the
requirements of B.S. 1881 and 812.
1.
Sampling pans for aggregate moisture tests.
2.
Electric ovens for drying out samples of wet
aggregates.
3.
Accurate compensating balance weighing up to 10
kilograms with weights.
4.
12 No. steel moulds for 150mm cubes, with base
plates.
5.
Kango hammer vibrator for making cubes
6.
2 No. slump cones with base plates and tamping
rods.
7.
1 compacting factor apparatus.
8.
Water tank for curing concrete cubes
9.
Concrete cube testing apparatus
10.
Check weights for mixer weigh batchers.
11.
Copper sampling tube for extracting cement
samples.
12.
Apparatus for testing contents of silt, clay, organic
impurities in fine aggregates.
13.
Airtight tins or jars for dispatch of cement
samples.
14.
Two sets of B.S. 410 test sieve listed below.
Size
25
12.5
10
5
µm
2.8µm
1.25µm
600µm
300µm
150µm
BATCHING
AND MIXING
3009.
mm
15.
Complete apparatus for gamma-ray inspection of
grout in ducts for pre-stressing tendons.
16.
Cover-meter for inspection of concrete cover to
reinforcement pre-stressing steel or ducts.
17.
Load cell for directly reading tension
prestressing tendons during stressing.
in
All the equipment listed as above shall be supplied and
maintained in perfect condition by the Contractor at his
own expense for the duration of the works. After
completion of the works all equipment shall remain the
property of the Contractor.
All materials used for concrete manufacture shall be
batched by weight.
Before the casting of each prestressed beam the quantity
of aggregates to be used shall be separated from the
stockpiles at the mixer and thoroughly turned over by
hand, to produce uniformly moist aggregate. Samples
shall then be taken of each aggregate and moisture
contents tests carried out to determine the percentage of
water content of each aggregate by dry weight method.
From these results the weights of wet aggregates and
water to be used in mixing shall be calculated for the
chosen quantity of cement to be used for each mix, using
the dry weights proportions determined from the
preliminary concrete mix design.
During the casting of each beam strict control shall be
maintained at the mixer to ensure that the correct weights
of materials are consistently used for each mix of
concrete. The workability of the concrete shall be
frequently checked using the compacting factor test so
that the consistency of the concrete is kept uniform.
Mixes, which show large variation from the workability
aimed at, due to varying aggregate conditions or errors in
batching, will be rejected and the necessary corrections
are to be made to the mix immediately after this is
observed. Stockpiles of aggregates at the mixer must
always be maintained so that no fresh aggregates are fed
in while casting of the beam is taking place. The mixer
and adjacent aggregate stockpiles shall be placed under
temporary roofing so as to be fully protected from the
direct rays of the sun and rain. Where compacting factor
test apparatus is not available, slump test may be used to
control the consistency of the concrete being produced
and placed.
PLACE OF
CONCRETE
Casting of prestressed beams shall be carried out on
specially prepared casting beds, which are to be
constructed under a temporary roofing so as to be fully
protected especially from the direct rays of the sun and
rain.
3010.
(1)
VIBRATION
Te methods of vibration to be used shall be carefully
designed to ensure full compaction of the concrete, thus
producing first class appearance without subsequent
patching of concrete faces.
Full details of the
Contractor’s proposed methods of manufacturing the
beams shall be submitted to the Engineer’s
Representative for approval.
(2)
PRELIMINARY TESTS
When a design mix has been approved by the Engineer’s
Representative, the Contractor is to allow for a
preliminary casting of a short length of beam complete
with pre-stressing cables and reinforcement, using the
proposed methods of vibration for the whole works.
(3)
CASTING
Each prestressed component shall be cast in one
continuous operation and no construction joints will be
allowed.
CURING
3011.
Curing of the prestressed components shall ensure a slow
heat evolution in the concrete so that shrinkage cracks
may be avoided.
Prestressed components shall be completely covered
with hessian, which shall be kept continuously wet for a
period of seven days. If tensioning of the pre-stressing
tendons takes place before this time, the hessian shall be
retained in position until the period of seven days has
expired.
The prestressed components shall then be cured in air for
a further period of seven days or enough time to achieve
the necessary strength before being erected into position
on the bridge.
FORMWORK
3012.
Formwork shall be of purpose made steel moulds or
plywood panels, and shall be rigidly fastened together so
that no displacement can take place during casting.
Formwork shall be designed so that it can be removed
without shock or damage to concrete, and must be braced
and held in position so as to avoid any holes or fastenings
through the prestressed component.
Moulds shall be of such a nature as not to allow the
concrete member to deform when the pre-stress is
applied. The bottom portions of the moulds shall be
prevented from adhering to the concrete.
Subject to the approval of the Engineer’s Representative,
stripping of side formwork may take place 24 hours after
casting or as soon as is convenient after the concrete has
reached its final set. Stripping of bottom formwork shall
not be carried out until after transfer of pre-stress to the
prestressed component.
SURFACE
3013.
Prestressed concrete work
shall, unless
otherwise
specified have a smooth finish on all surfaces exposed in
the completed work. Surfaces which will be in contact
with concrete cat in place to form a composite
construction shall be purposely left very rough, in order
to provide an adequate key. The valleys and ridges of
any roughening system shall be transverse to the
direction of stressing.
FINISH
TOLERANCE
3014.
The Contactor shall provide continuous, experienced
supervision during all mould-assembly and concreting
operations, in order to ensure that the tolerance in
longitudinal dimensions for all concrete work shall
remain within the following limits:
(1)
For Component about 9m Long ± 6mm
(2)
For Component about 18m Long ± 10 mm
(3)
For Component about 36m Long ± 13mm
The tolerance for lack of straightness on plan or variation in
camber shall also be of the same order as shown above for
the respective lengths of the components.
The dimensional tolerances on web steel shall be of the
order of 3mm.
PRE-STRESSING
3015. (1)
GENERAL
Wires shall be straightened if necessary to produce equal
stress in all wires or wire groups or parallel lay cables that
are to be stressed simultaneously or when necessary to
insure proper positioning in the sheathings.
When wires are to be button-headed, the buttons shall be
cold formed symmetrically about the axes of the wires.
The buttons shall develop the minimum guaranteed
ultimate tensile strength of the wire. No cold forming
process shall be used that causes indentations in the wire.
At transfer of the pre-stress the concrete shall have a
minimum cube-strength of 30 N/mm2.
In order that any applied force may be maintained after
the tensioned tendons have been anchored, an allowance
must be made in assessing the value of the applied force
for loss of stress due to the yield in the anchorages and
for slip when the tendon is wedged after tensioning. At
transfer of the re-stress, the concrete shall have the cube
strengths as shown on the drawings, or as specified.
These requirements shall be ascertained from works tests
on three cubes manufactured and cured under the same
conditions as the concrete member.
Sufficient cubes shall be made so that if the stipulated
strength is not achieved, further cubes will be available
for such additional testing as may be required.
At transfer of pre-stress, the measured deflection of the
beam shall not exceed the limits given on the drawings, or
as specified.
(1)
POST TENSIONING
(I)
The system of pre-stressing and the magnitude of
the post tension in a structural component shall be
as shown on the drawings.
(II)
MANUFACTURE OF CABLES
Pre-stressing cables shall be pre-assembled in the
factory or manufactured on site from coils of
wires or strands. The cable consisting of a
number of high tensile steel wires or strands shall
be formed in the manner as directed by the
Engineer or his Representative. In estimating the
length of all cables, extra allowance must be made
for attaching either one or two tensioning jacks as
instructed by the Engineer. The method of
measurement for the purpose of payment shall be
the length of the finished cable placed, positioned,
tensioned, anchored, cut and grouted complete as
in the finished structure.
(III)
(IV)
SHEATHING
Sheathing shall be carefully examined prior to use
and any damaged lengths shall be cut away and
rejected. Joints in corrugated sheathing shall be
formed by the use of couplers and/or by wrapping
the joints with tape. They shall be so designed as
to prevent the ingress of cement, concrete or other
material during casting. All joints in sheathing
shall be approved by the Engineer’s
Representative.
PLACING OF PRESTRESSING TENDONS
AND SHEATHING
Tendons shall be carefully handled so as to avoid
sudden bends or kinks, and threaded into the
flexible sheathing before being placed into the
beam formwork.
The sheathing and the
prestressing tendon shall be rigidly supported in
the exact positions as shown on the drawings so
that no movement can take place during casting of
the beams.
(V)
PLACING OF ANCHORAGES
The anchorages shall be placed accurately in
accordance with the drawings and firmly fixed to
resist displacement during vibration of the
concrete. The anchorages shall be fixed so as to
be perfectly collinear with the axis of the tendons
and to remain so throughout the casting of the
component.
(VI)
SYSTEM OF POST TENSIONING
All post-tensioned prestressing steel shall be
secured at the ends by means of approved
permanent type anchoring devices.
All anchorage devices for post-tensioning shall
hold the prestressing steel at a load producing a
stress of not less than 95 percent of the guarantee
minimum tensile strength of the pre-stressing
steel, when tested in accordance with Test Method
No. California 641 or equal.
When headed wires are used, the outside edge of
any hole for prestressing wire through a stressing
washer or through an unthreaded bearing ring or
plate shall not be less than 5mm from the roof of
the thread of the washer or from the edge of the
ring or plate.
The load from the anchoring device shall be
distributed to the concrete be means of approved
devices that will effectively distribute the load to
the concrete.
Such approved devices shall conform to the
following requirement:
(a)
Bending stresses in the plates or
assemblies induced by the pull of the
prestressing steel shall not exceed the yield
point of the material or cause visible
distortion in the anchorage plate when 100
percent of the ultimate load is applied as
determined by the Engineer.
(b)
Materials and workmanship shall conform
to the requirements in Section V –
Bridgeworks, Part (B)
Structural
Steelworks.
(VII)
JOINTS
Joints in the spaces between a series of precast
elements, which are to be prestressed together,
shall be made precisely in accordance with the
requirements shown on the drawings.
Suitable extensions or connections of the ducts
though the gaps shall be provided and steps taken
to ensure that the jointing material does not enter
the duct or press against the prestressing steel.
The holes for the prestressing steel shall be
accurately made and meet one another in true
alignment at the ends and shall permit
unobstructed passage of the grout.
The stressing operation shall not take place until
the filling material in the joint has attained a
strength equal to at least 1½ times the stress at
transfer of prestress. The time lag is to be
established during design process.
(VIII) TENSIONING
(1)
(2)
No post-tensioning of prestressing tendons
shall take place until the concrete has
attained the specified stress as ascertained
from tests on cubes cured and hardened
under the same conditions as the concrete
of the member. Before the stressing, single
wires or strands, the wires or strands in
each cable shall be of equal length in
tension.
Tensioning shall be carried out with the
approved type of jacks.
(3)
Before tensioning the anchorages shall be
carefully cleaned on all surfaces, removing
heavy dirt.
(4)
The amount of tension given to the
tendons shall conform to a schedule of
tendon tensions, to be supplied by the
Engineer, and will be based on the test data
for prestressing steel.
(5)
Measurement of the force shall be by an
accurate gauge indicating the force on the
hydraulic jack and also by the elongation of
the steel after allowing for any initial slip in
the wedges or jaws of the grips. The
Engineer may also specify the use of a load
cell to determine the tendon tension
directly.
(6)
Approval shall be obtained from the
Engineer’s Representative before each
tendon is anchored. The contractor shall
provide printed sheets and supply the
Engineer’s Representative with a record of
all extension and pressure readings for
each tendon in every prestressed structural
component.
(7)
No tensioning of tendons can commence
until permission is obtained to do so from
the Engineer’s Representative.
(8)
The order and sequence of tensioning shall
be as specified on the drawings or as
instructed by the Engineer’s
Representative.
(9)
The prestressing force should be applied
from one or both ends as specified on the
drawings.
(10)
Each wire, pair of wires, cables, strand, or
bar shall be attached in such a manner as to
ensure that the elongation is uniform
throughout its length.
Should any
tensioned steel or anchorage break or be
damaged, it should be replaced if so
ordered.
Throughout all tensioning
operations a spare jack capable of
maintaining the designated load should be
available.
(11)
All tensioning shall be carried out I the
order specified or approved.
After
tensioning, the wires, strands or bars shall be
secured in position and cut off as directed.
(12)
Immediately before tensioning, the
Contractor shall prove that all tendons are
free to move between jacking points and
that members are free to accommodate the
horizontal and vertical movements due to
the application of prestress.
(13)
The Contractor shall establish the datum
point for measuring extension and jack
pressure to the satisfaction of the Engineer.
(14)
The tendons shall be stressed at a gradual
and steady rate until they attain the force
described in the Contract.
(15)
The Contractor shall keep full records of
all measured tensioning operations,
including the extensions, pressure gauge or
load cell readings and the amount of pull-in
at each anchorage. Copies of records shall
be supplied to the Engineer within 24 hours
of each tensioning operation.
(IX)
GROUTING
(1)
After tendons have been tensioned and
anchored they shall be grouted up solid
throughout. Suitable outlet with plugs
being provided to prevent air locks unless
otherwise specified. Grouting trials shall
be undertaken when required by the
Engineer.
The method of mixing and injecting the
grout shall be approved by the Engineer
before grouting is commenced.
The
pressure at which the grout is to e pumped
into the duct shall be approved by the
Engineer and shall not normally exceed
552 kN/m2.
(2)
Grout shall be either a neat cement grout
with a water cement ratio not exceeding
0.4 or cement mortar (1:1 by weight). An
expanding plasticizing admixture should be
used.
All ducts and holes shall be
thoroughly washed out with water,
immediately before grouting and after the
stressing operation has been completed.
Grouting is to be carried out continuously,
the discharge from consecutive air holes
being observed throughout. The mixer
shall be thoroughly cleaned before grouting
is commended. A complete spare grouting
plant for immediate use in case of
emergency or breakdown on the equipment
operation shall be available.
(3)
Care shall be taken to avoid lumps in the
cement, and sieving shall be carried out
before mixing the grout. It is essential to
mix up a quantity of grout sufficient for a
particular duct immediately prior to its
injection and to use only this batch on the
duct.
(4)
During the grouting operation grout shall
be continuously added to the bucket from
which the grout is being pumped and the
bucket shall not be changed otherwise air
may enter the sheathing with the grout.
(5)
Before the commencement of grouting and
after the completion of it, reports shall be
made to the Engineer’s Representative in
writing. The duct shall be plugged when
grout is issued freely from the outlet end,
and once plugged the pressure shall be
gradually reduced to prevent blow backs or
air pockets. The Contractor shall keep full
records of grouting including the date each
duct was grouted, the proportion of the
gout and any admixtures used, the
pressure, details of any interruption and
tapping up required. Copies of these
records shall be supplied to the Engineer
within 3 days of grouting.
Where required by the Engineer, the Contractor
shall provide facilities and attendance for the
radio- graphic testing of ducts.
(6)
(7)
(8)
(X)
The grout mixer shall produce a grout of
colloidal consistency. The grout injection
shall be capable of continuous operation
with sensibly constant pressure up to 690
kN/m2 and shall include a system of
circulating or agitating the grout whilst
actual grouting is not in process. All
baffles to the pump shall be fitted with
sieve strainers size 1.2mm.
The equipment shall be capable of
maintaining pressure on completely
grouted ducts. It shall be fitted with a
nozzle, which can be locked off without
loss of pressure in the duct.
The pressure gauges shall be calibrated
before they are first used in the works and
thereafter as required by the Engineer. All
equipment shall be thoroughly washed with
clean water at least every 3 hours during
the grouting operations and at the end of
use for each day.
FINISHING OFF TENDONS
After grouting, the ends of the anchorages and any
protecting ends of cut-off tendons shall be covered
over by a 1:1 mix mortar packed hard into the
recesses on the beam.
(2)
PRETENSIONING
(I)
In long line beds for pre-tensioning, due
consideration shall be given to the friction caused
by the varying shape and number of diaphragms
which will affect the magnitude of the applied
prestressing force.
(II)
In order to obtain concrete of uniform strength,
where members are cast in a long line bed, the
difference in strength at transfer between
components of the same type cast in the same line
shall not exceed 15 per cent. The Contractor shall
satisfy the Engineer’s Representative by
tests on special cubes cured under the same
conditions, as the members that this condition is
complied with.
(III)
(3)
With pre-tensioning, the specified force shall be
maintained by the use of approved fixing devices,
at the ends of the tensioned steel during
concreting and curing, until the concrete has
attained the strength specified. The tensioned steel
shall then be released gradually and uniformly.
TRANSVERSE PRESTRESSING
(I)
GENERAL
Transverse pre-stress shall be as specified and
shown on the drawings.
(II)
JOINTING
Joints between precast concrete u nits are to be
made in accordance with the drawings or
instructions from the Engineer’s Representative.
They shall consist of dry or wet joints. In the case
of dry joints they shall be filled with dry concrete
quality 50 N/mm2 that shall be mechanically
rammed into position and in the case of wet joints
they shall be filled with wet concrete quality 50 N/
mm2 and fully vibrated into position. In both
cases joints shall be finished flush with, the precast concrete faces. During jointing, protection
and continuation shall be given to the transverse
cable holes, using a method to be approved by the
Engineer’s
Representative.
(III)
TRANSVERSE CABLES
Transverse pre-stressing tendons, shall be as
indicated on the respective drawings and threaded
through the transverse holes after the structural
components are in position. Tensioning will be
carried out to a schedule of tendon tensions, to be
supplied by the Engineer, and must be
commenced at the centre working towards the
ends symmetrically. The tendons are to be
grouted in the same way as for the longitudinal
pre-stressing.
Permission shall be obtained from Engineer’s
Representative prior to the commencement of
stressing and grouting and the completion of
stressing and grouting shall be reported to the
Engineer’s Representative all as for the
longitudinal pre-stressing.
ADDITIONAL
3016.
The Following additional requirements shall be complied
with:
No cracks will be permitted due to:
(1) Shrinkage, settlement of formwork, or damage in
handling before application of pre-stress.
(2) Local weakness of concrete at or immediately
following pre-stressing or
(3) Improper handling and transporting application of prestress.
Where grooves are provided in which tendons have been
placed, they shall be cleaned before the mortar is inserted:
Mortar shall consist of one part by weight of cement three
parts of sand with a water-cement ratio not exceeding 0.4
and shall be thoroughly compacted in the grooves,
preferably by the use of vibrators, and subsequently
cured.
Alternatively, mortar comprising one part of cement to
one part by weight of sand together with an approved
expanding plasticizing agent and less water may be used.
External cables shall be embedded in mortar of these
proportions, an upper cover being placed over the cables
after vibration is completed to ensure that expansion
occurs uniformly within the original profile.
Any tension and retensioning procedure when allowed
for offsetting losses shall be strictly in accordance with the
instructions of the Engineer’s Representative.
The procedure to be adopted for all operations, using
large diameter single strands used as prestressing tendon
shall be specially approved by the Engineer.
LIFTING AND
HANDLING
3017.
The Contractor
shall
furnish
the Engineer’s
Representative with full details of the proposed method of
transporting and erecting, prestressed beam for his
approval, before commencing this work. Should any
cracking or other damage to components during transport
or erection render the components unfit for use the
Contractor shall replace the same at his own expense.
The method of lifting and handling prestressed beams is to
ensure that the design dead weight bending moment is not
exceeded at any point in the beam throughout the whole
operation. Lifting from casting beds shall not take place
until grouting is completed and at least 24 hours old.
Erection of the beams on to the bridge spans shall not take
place until the concrete has attained a cube strength as
specified on the respective drawings. The lifting of the
beams shall be made using temporary lifting devices
provided by the Contractor to the Engineer’s
Representative’s approval. Initial lifting from casting
beds and final lowering on to bearings shall be carried out
using hand operated chain blocks so as to avoid sudden
shock in the beam.
(2)
STORAGE
Beams shall only be stored on specially prepared
temporary bearings, which must be such that the
design dead weight bending moment is not
exceeded at any point. Beams shall only be stored
singly and not on tip of each other.
(3)
TRANSPORTING OF BEAMS
Transporting of beams from place of storage to
point of erection shall be carried out using a
purpose-made conveyance, which will ensure that
the design dead weight, bending moment is not
exceeded at any point over the length of the beam.
This can be done by in-built pad into the vehicle,
which actually come into contact with and support
the structural units. Frame may be introduced into
the vehicles to support particular structural units.
All units must be coupled directly to the frame to
eliminate movement of units in transit and shall be
designed so as to avoid winching or dragging the
beams in a horizontal direction over rough
ground. The transporting of other structural
components shall be as approved by the Engineer.
QUANTITY AND
PAYMENT
3018.
No separate payment will be made for prestressing
precast concrete members. Payment for prestressing
precast members shall be considered as included in the
contract price for furnishing precast members.
The contract lump sum price paid for prestressing precast
members shall include full compensation for furnishing
all labour, materials, tools, equipment and incidentals and
for placing and tensioning the prestressing steel in precast
concrete structures, complete in place, as shown on the
drawings, as specified in these and the special provisions
and as directed by the Engineer.
Full compensation for furnishing and placing additional
deformed bar reinforcing steel required by the particular
system used, ducts, anchoring devices, distribution plates
or assemblies and incidental parts, for furnishing samples
for testing, working drawings and microfilms and for
pressure grouting ducts shall be considered as included in
the Contract Lump Sum Price paid for in prestressing
cast-in-place concrete or in the contract price for
furnishing precast members and no additional
compensation will be allowed therefore.
(CLAUSES 3019 – 3999 INCLUSIVE NOT USED)
SPECIFICATION
SECTION IV
PILING
SECTION IV
PILING
GENERAL
4000.
In addition to any other relevant clause of this
Specification, the following shall be deemed to apply in
particular to prestressed piling works, and shall be read in
conjunction with all other relevant Clauses of the
Conditions of Contract and this Specification.
PART A - GENERAL
TYPES OF PILES
4001.
Piles used in the works shall be one of the following
types:
(I) Type “A”: Precast reinforced concrete bearing
and sheet piles.
(II)
Type “B” Cast-in-place reinforced concrete
bearing piles formed by driving a steel
shell, which is filled with concrete and
left in place.
(III) Type “C”
Cast-in-place reinforced concrete
bearing piles formed by driving a steel
pipe casing, inserting a permanent steel
shell, filling it with concrete and then
withdrawing the driving casing.
(IV) Type “D”
Cast-in-place reinforced concrete
bearing piles formed by driving a
heavy steel pipe casing, filling the
casing with concrete and withdrawing
the casing during or after concreting.
(V)
APPROVAL OF
TYPE
4002.
Type “E” Prestressed concrete cylinder bearing
piles driven in.
(VI) Type “F”
Prestressed concrete cylinder bearing
piles bored in.
(VII) Type “G”
Steel sheet piles.
The Contractor shall submit to the Engineer for his
approval details of all the types of piles intended for use
in the works. These details shall comprise complete
detailed drawings and specifications, a comprehensive list
of the equipment to be used and a full description of the
methods to the employed
The Contractor’s attention is drawing to the fact that no
equipment or material intended for use in the construction
or driving and/or boring of piles shall be imported on to
the site until the Engineer’s approval has been obtained.
CONTRACTOR
TO DRIVE OR
BORE HOLES
4003.
Should the Contractor elect to carry out the pile drive or
boring from his own resources he will be required to
satisfy the Engineer that the personnel he intends to
employ in the operation have had sufficient experience in
similar installations under like sub-surface conditions.
SUB-CONTRACTOR
4004.
Should the Contractor elect to employ a Sub-Contractor
for the piling, he shall satisfy the Engineer that the
SubContractor is sufficiently experienced in similar
operations under like sub-surface conditions.
MANUFACTURE
4005.
OF REINFORCED
AND PRE-STRESSED
CONCRETE PILES
In addition to the particular requirements of this part of
the specification, all t he relevant clauses of the
specification shall apply to the manufacture of reinforced
or pre-stressed concrete piles.
CEMENT
The cement used in the manufacture of all reinforced or
prestressed concrete piles shall be sulphate resisting
Portland cement in accordance with B.S. 4027 unless
otherwise shown on the drawings.
4006.
SETTING OUT
OF PILES
4007.
The Contractor shall be responsible for the correct
location of all piles and the establishment of all lines and
levels.
ALIGNMENT
4008.
Piles shall be driven or bored as accurately as possible to
the vertical or to the specified batter. Any pile deviating
from its proper alignment to such an extent that its load
carrying capacity cannot, in the opinion of the Engineer,
be corrected by the strengthening of the foundations, pilecap or pile ties, shall be replaced or supplemented by an
additional pile at the Contactor’s expense. In general the
allowable tolerances will be in the case of piles type “A”
– “D” within 75mm of the position shown on the
drawings and within 1½° of the inclination shown on the
drawings and in the case of piles type “E” and “F” within
150mm of the position shown on the drawings. No
wedging or drawing into line of piles that have wandered
will be allowed.
DRIVING WITH 4009.
DROP HAMMERS
OR SINGLE ACTING
Piles shall be driven with a drop hammer or with a
single acting steam hammer. The weight of the hammer
and the drop to be used shall be subject to the approval of
the Engineer and shall conform to the recommendations
of CP 2004 and will depend on the type of pile to be used.
In general the energy per blow will be of the order as
follows:
STEAM HAMMERS
(I)
(II)
For piles types “A”, “B”, “C” and “D” – at least
26,500 Joules or 35,000 Joules depending upon
cross-sectional dimensions of the piles, the lighter
hammer being used up to 300 mm diameter piles
and the heavier from 300mm diameter to 400mm
diameter.
For piles of type “E” at least 54,300 Joules with a
ram weight of not less than 6,800 Kg.
DRIVING WITH 4010.
DOUBLE ACTION
STEAM HAMMERS
Double-Acting steam hammers may be used when
driving piles to refusal but shall not be used for other
piles except with specific permission of the Engineer.
PROTECTION OF
PILE BUTTS
4011.
Suitable anvils or cushions, depending on the type of the
pile, shall be used to prevent damage to the pile butts.
LEADS AND
FRAMES
4012.
Unless otherwise specified or directed driving shall be
done using fixed leads which will hold the pile firmly in
position in axial alignment with the hammer.
Raking piles shall be held in position during driving right
down to the level at which the piles enter reasonably solid
ground and to the satisfaction of the Engineer’s
Representative.
Piles shall be driven from an approved type frame.
DRIVING TO BE
4013.
CONTINUOUS TO
FINAL SET OR
LEVEL
When the driving of any pile commences it shall be
continued without cessation for any avoidable cause until
the pile has been driven to the required set or level as
directed by the Engineer’s Representative. Where levels
or sets are indicated on the drawings, these may be varied at the Engineer’s discretion, in accordance with
the results of test piles driven in representative areas.
JETTING
4014.
DRIVING TO
FINAL SET AND
RECORD OF
DRIVING
4015.
RE-DRIVING
HEAVED PILES
4016.
Where water or air jetting is contemplated to assist the
driving of the piles, the permission of the Engineer must
be obtained. The jetting shall be carried out in a manner
to the satisfaction of the Engineer’s Representative and
must be discontinued when the toe of the pile is 3 metres
short of the estimated final depth of penetration. Driving
shall be completed by hammer only, without jetting, to
the required set or as indicated by the Engineer’s
Representative. Where it is intended to employ water or
air jetting to assist the driving of a number of piles in a
group, the jetting of piles in the group must be completed
before the driving of any pile to its final penetration is
commenced.
All piles shall be driven to the specified final set in
the presence of Engineer’s Representative
A record of the driving of each pile shall be kept in the
form of the “Daily Pile-Driving Record”, as set out in the
British Standard Code of Practice No. 8004. Four copies
of each of these records shall be forwarded to the
Engineer’s Representative for his retention.
Observations and measurements shall be made in the
field during the process of driving piles, by any suitable
method satisfactory to both the Contractor and the
Engineer to determine whether a driven pile has been
lifted from its original seat during the operation of driving
adjacent piles.
The Contractor shall provide the
necessary tools such as tell-tale pipes and instruments, to
make these measurements. Such measurements shall be
properly corrected for any temperature variations that
might exist in the case of the pile shell or instrumentation.
Where such observations or measurements indicated that
a pile has been unseated, it shall be driven to the
resistance specified.
DAMAGED AND
4017.
MIS-DRIVEN PILES
Broken or shattered piles will not be accepted.
Should any pile be damaged by over-driving or not
conform to the tolerances of the specification, an extra
pile or piles shall be driven in its place, at the
Contractor’s expense unless in the opinion of the
Engineer the pile is out of place or plumb as the result of
an underground obstruction.
Piles rejected after driving may remain in the ground at
the discretion of the Engineer, in case of shell piles the
shell shall be filled with concrete, and be cut off as
directed. When rejected piling is withdrawn, the space, if
another pile is not driven into it, shall be filled solid with
gravel or broken stone without payment thereof.
OBSTRUCTIONS
4018.
Where boulders or other obstructions make it impossible
to driving certain piles in the location shown and to the
proper bearing strata, the Contractor shall resort to all
usual methods to install the pile or steel pipes as required,
including spudding, jetting, or other feasible means. If, in
the judgement of the Engineer, the Contractor is unable to
complete the pile driving properly by resorting to such
methods, the Engineer may order an additional pile or
piles driven for which the Contractor will be paid in
accordance with the tendered rates.
Piles abandoned because of obstructions encountered
before reaching the accepted bearing strata shall be left in
position or shells filled with concrete and be paid for as a
complete pile for the length driven.
Where directed by the Engineer, excavation operations
shall be carried out to remove obstructions and the
Contractor shall be reimbursed for such operations at
rates and prices to be agreed between the Contactor and
the Engineer.
CUTTING OFF
4019.
PILE HEADS ETC.
The tops of piles shall be cut off true and level at the
elevations indicated on the drawings, all to be satisfaction
of the Engineer’s Representative. All portions, which are
battered, split, wrapped or buckled, or damaged or
imperfect in any way shall be removed.
Shells and casing shall have sufficient excess length to
allow the complete removal of working tops.
BORED PILES
OR CASINGS
4020.
The method of boring steel casing or pipes into the
ground shall be subject to the approval of the Engineer.
PAYMENT
4021.
Payment for piling shall be made as detailed hereunder in
the parts of this section of the specification dealing with
the particular types of piles.
(CLAUSES 4022 – 4029 INCLUSIVE NOT USED.)
PART (B) – TEST DRIVING AND TEST LOADING
OF PILES
GENERAL
4030.
(i)
(ii)
(iii)
(iv)
RECORDING OF
TEST RESULTS
4031.
PROCEDURE FOR 4032.
TESTING PILES OF
TYPES A,B,C AND D
Test piles shall be driven or bored as appropriate
and loaded in the manner detailed hereunder in
the number and locations indicated on the
drawings and/or in the contract documents and/or
as directed by the Engineer.
Unless otherwise directed, the test piles shall
remain as working piles under the completed
foundations.
Test piles shall be driven or bored using the
equipment and methods approved by the
Engineer for the remaining working piles.
Before any load test is made, the proposed
apparatus, structure and method to be used, in
making the load test, shall be approved by the
Engineer. All load tests shall be made under the
supervision of the Engineer’s Representative.
The results of all piles loading tests shall be set out in a
report, the form of which shall be as directed by the
Engineer. This report shall include a description of the
pile and its driving record; type and size of hammer used,
a tabulation of the load time, settlement and rebound
data; and remarks concerning unusual circumstances
during the driving or boring or loading of the pile and any
other information which the Engineer or his
Representative may require.
The following procedure shall be adopted for the testing
of piles referred to above as types “A”, “B” “C” and “D”
Piles shall be load tested to twice the design load with
the test load applied in seven increments equal to 0.5,
0.75, 1.0, 1.25, 1.5, 1.75 and 2.0 times the design load
with a minimum of two hours between the addition of
PROCEDURES
FOR TESTING
PILES OF TYPES
“E” AND “F”
4033.
load increments. Increments shall not be added until the
rate of settlement is less than .25mm per hour, or if each
increment thereafter for the test load shall remain in place
until there is no settlement in a 2-hr period.
(i) If the full test load can be applied without failure of
the pile, this load shall remain on the pile for 48
hours, after which the test load shall be removed
in four equal decrements with a minimum of one
hour between decrements.
(ii)
Readings of settlements and rebounds shall be
made with a minimum of two dial gauges mounted
on an independent framework and positioned on
opposite corners of the test plate. Readings shall
be recorded to the nearest 250µm and shall be
made every 30 minutes during the loading cycle
and every hour during the application of the full
test load. Readings of rebound shall be made
before and after each decrement and 24 hours after
the entire load has been removed.
(iii) The load test shall be considered satisfactory
provided that the net settlement (after rebound)
does not exceed 10% of the pile diameter.
(iv)
Piles to be load tested will be contract piles driven
in their proper location. During the load testing of
piles, the driving of contract piles may be
continued at the Contractor’s option provided the
testing process is not affected by the pile driving.
Should the results of the load test indicate that
longer piles are necessary, the Contractor will be
required to further drive piles driven during the
load testing operation without additional cost to
the owner except for the added pile length. Piles
driven during the testing operation shall not be
filled with concrete until the required length
and/or resistance has been determined by load
test.
The following procedure shall be adopted for the piles
referred to above as types “E” and “F”.
Pile driving or sinking requirements as to depth of
embedment and/or requested final driving resistance shall
be determined in each area of similar soil conditions by
load testing at least two piles selected by the Engineer.
The total applied load shall equal 150% of the design dead
load, plus 200% of the design live load. The test load
shall be applied in six increments equal to 25, 40, 55, 70,
85 and 100% of the total test load. Time interval between
increments shall not be less than two hours and
increments of load shall not be added until the rate of
settlement has dropped below .25mm per hour. The full
load shall remain on the pile for 48 hours, after which a
test load shall be removed in four equal decrements
allowing one hour between decrements. Readings on
settlements and rebound shall be taken before and after
each increment or decrement, every two hours during the
48 hours the full load is on the pile and 24 hours after the
full load is removed from the pile. The test shall be
considered satisfactory if the net settlement (after
deduction of rebound) does not exceed 10% of the pile
diameter.
LATERAL
DISPLACEMENT
TEST
4034.
The Engineer may order, if he so desires, that lateral
displacement tests be carried out by jacking between
adjacent piles to a given lateral displacement. The
method of carrying out lateral displacement tests shall be
as directed by the Engineer.
ASSESSMENT OF
RESULTS OF
PILE LOADING
AND DRIVING
TEST
4035.
The information obtained from the driving of the test
piles shall be applied to a suitable dynamic pile formula
or formulae. The formula or formulae to be employed
shall be as selected by the Engineer. The results of this
application or these applications shall be considered in
conjunction with the results obtained from the loading
test and lengths of the remaining piles in a particular area
or group shall then be agreed between the Contractor and
the Engineer.
PAYMENT FOR
TEST PILES AND
4036.
Payment for the fabrication and driving or boring of the
test piles shall be made at the tendered rates and prices
for working piles of the same type entered in the bills of
quantities..
LOAD TESTS
Payment for the pile load tests shall be made at the unit
price quoted for load test on the particular type of pile in
the bills of quantities, except where the Contractor should
have made any kind of guarantee as to safe bearing
capacity of any particular type of pile in any location,
payment for load tests shall only be made for tests which
are, in the opinion of the Engineer, successful.
The price by the Contractor for the carrying out of the
load test shall be deemed to be inclusive of all the costs
involved in the carrying out of the load test and also of
the cost of obtaining the stipulated information during the
driving of the test pile.
(CLAUSES 4037 – 4049 INCLUSIVE NOT USED)
PART ( C) PRECAST REINFORCED CONCRETE
BEARING AND SHEET PILES – TYPE
“A”
GENERAL
4050.
MOULDS AND
4051.
In addition to any other requirements of other parts of this
section
of
the
specification, the
following requirements shall be complied with in
respect of precast reinforced concrete bearing and sheet
piles.
The piles shall be manufactured at the site of the work in
which they are to be used and in an area entirely free
from the harmful effects of shock and vibration. They
shall be cast in lengths as determined by test.
The moulds shall be so supported that the pile is not
distorted during or after casting and shall be such as to
ensure that the resulting pile is straight and true on each
face. The sides of the moulds shall be capable of being
removed without shock or jarring of the pile. Shoes,
reinforcement, links, toggle-hole tubes and all other
fittings shall be fixed accurately in the positions shown on
the drawings. Shoes shall be of the type shown on the
drawings and of approved manufacture. They shall weigh
not less than as shown on the drawing and shall have
chilled-hardened cast iron bases and mild steel straps cast
in, i.e. the straps shall run continuously through the cast
iron bases. All castings shall be of clean, grey, tough
metal, free from sand, honeycombing, porous places, air
holes or other defects and shall be delivered to the site
without being painted, stopped or plugged in any part,
otherwise they will be rejected. Shoes shall be fixed
accurately to the piles with the points truly on the
longitudinal axis and the lower ends of the reinforcing
bards shall bear on the top of the shoe. Forks for retaining
the longitudinal reinforcing bars in position shall be of
cast iron on pressed steel and of approved shape and
length.
Each pile shall be poured in one continuous operation.
During concreting and subsequently, the pile shall be
protected from the effects of sun, wind and rain by
covering with screens of clean, damp sacks or hessian,
care being taken to prevent contact with the wet concrete
until it has hardened sufficiently to prevent marking.
When so hardened, the concrete and moulds shall be
intimately and completely covered with the damp sacks or
hessian and these shall be kept in a continuously wet
condition for a period of not less than 10 days after
casting.
CONCRETING
STRIPPING AND
4052.
The sides of the moulds shall not be removed before
HANDLING
two days after casting and the piles shall not be disturbed
on the bottom boards for at least 10 days after casting.
The piles shall be removed from the bottom boards only
by canting sideways and shall be rolled carefully to the
stacking ground for final curing. The runners and other
supporters upon which the piles are canted and rolled shall
not be more than 2 metres apart and shall be perfectly
level one with the other so that during the operations of
canting and rolling each pile shall be fully supported at
each interval of 2 metres along its length. Each pile shall
have the date of manufacture painted on one side and this
date shall determine the sequence in which the piles are
driven. The piles must on no account be lifted at this
stage and, until ready for driving, must be adequately
supported at each 2 metres interval throughout their
length.
The Contractor shall keep the piles in
continuously wet conditions until a period of at least 14
days has elapsed since manufacture.
Otherwise than as aforesaid, the piles shall not be
handled, lifted, slung, pitched or driven before 6 weeks
after manufacture and then shall be slung only from the
toggle-holes provided in the positions shown on the
drawings or as approved by the Engineers
Representative.
Should the Contractor wish to use rapid hardening cement
he shall first obtain the approval of the Engineer’s
Representative. Where approval has been given, and rapid
hardening cement used in the manufacture of the piles,
the sides of the moulds shall not be removed earlier than
2 days after casting, and the piles shall not be disturbed
on the bottom boards for at least 4 days after casting.
Curing shall continue for the full period of 14 days and
the piles shall not be driven before three weeks after
manufacture.
Notwithstanding the foregoing requirements, the
Contractor shall be responsible for any damage done to
the piles due to the sides of the moulds being removed
too soon or the piles being moved from the bottom boards
too soon or from any other cause and all piles damaged
during manufacture, handling, driving or at any other
time shall be replaced at the Contractor’s expense.
LENGTHENING
OF PILES
4053.
STRIPPING
HEADS OF PILES
4054.
PAYMENT FOR
PRECAST
REINFORCED
CONCRETE
4055.
In every case where it is found to be necessary to
increase the length of a pile after it has been driven, the
head of the pile shall be cut off to expose the
reinforcement for a length not less than 1.2 metres below
the top of the steel reinforcement. The joint shall be
made by butting the lengthening bars to the pile bars with
the addition of a supplementary bar to every pile bar and
of equal area. These supplementary bars shall extend at
least 1.2 metres on each side of the joint and shall be
secured to both pile and lengthening bars by No. 16
S.W.G. wire, links being provided as directed. The
extension shall be carried out vertically so as to form a
true continuation of the pile.
Butt welding of
reinforcement may be allowed by the Engineer’s
Representative and where so allowed shall be carried out
in strict compliance with the instructions of the
Engineer’s Representative.
After the piles have been driven, the concrete shall be cut
away from those portions of the piles extending above a
level of 75mm minimum above the bottom of the pile
cap, without damaging the reinforcement and leaving
exposed a minimum length of 0.90m of the main bars.
The binders, links, forks and toggle-hole tubes within this
portion shall be removed and the main bar reinforcement
shall be bent into the base of the foundation as shown on
the drawings.
Payment for precast reinforced concrete bearing and
sheet piles shall be made on the basis of the length of
the pile per linear metre, measured from the tip to the
cut-off elevation at the tendered rates and prices entered
in the bills of quantities for the sheet piles particular type
and dimensions of pile.
The tendered rates and prices shall be deemed to include
for all materials, equipment, labour and supervision
involved in the completed pile driven and in place. No
payment shall be made for withdrawn or ejected piles.
(CLAUSES 4056 – 4059 INCLUSIVE NOT USED)
PART D – CAST-IN-PLACE REINFORCED
CONCRETE PILES, TYPES “B” AND “C”
In addition to any other requirements of any other parts of
this section of the specification the following
requirements shall be complied with in respect of castinplace reinforced concrete piles of types “B” and “C”.
CAST-IN-PLACE 4060.
REINFORCED
CONCRETE PILES
TYPE “B”
These piles shall be formed by driving a shell to the
required bearing, leaving the shell permanently in
place, and filling it with concrete. Shells shall have
sufficient strength and rigidity to permit their being driven
and not to be distorted by soil pressure or the driving of
adjacent piles; they shall be sufficiently watertight to
exclude water during placing of concrete. No concrete is
to be placed until all piles in a cluster have been driven
and approved.
CAST-IN-PLACE 4061.
REINFORCED
CONCRETE PILES
TYPE “C”
These piles shall be placed by driving a heavy steel pipe
casing with an interior core or point to the required
depth, removing the core and inserting a permanent steel
shell, filing it concrete and then withdrawing the driving
casing. Shells shall have sufficient strength and rigidity
not to be distorted by soil pressure or the driving of
adjacent piles and they shall be sufficiently watertight to
exclude water during placing of concrete. Shells shall be
cylindrical with a minimum diameter of 315mm. No
driving casing shall be withdrawn until all piles within 3
metres centre to centre, have been driven. Pile shells may
be step tapered, cylindrical or a combination of such
shapes and may be plain or corrugated. Plain cylindrical
shells and shells driven without an internal mandrel shall
have a minimum top diameter of 255mm and a minimum
butt diameter of 355mm. For the step taper portion of
any pile, the maximum distance between changes of
diameter shall be 3.6 metres for shells driven with an
internal mandrel, the Contractor shall assume
responsibility for providing shells of sufficient strength
and thickness to withstand proper driving without injury,
to obtain proper penetration and to resist harmful
distortion and/or buckling due to soil pressure.
The lower end of each pile shell shall be closed by a butt
steel plate or shoe firmly welded to the shell.
EQUIPMENT
4062.
CONTROL OF
INTERNAL
PRESSURES
4063.
CONCRETE
4064.
Pile driver leaders shall be of the rigid or fixed type to
ensure accurate alignment of the pile and hammer during
driving. The use of swinging leads will not be permitted.
The cushion block used shall be a one-piece hardwood
block with grain parallel to the pile axis and enclosed in a
close fitting steel housing, except that subject to the
approval of the Engineer, a cap-block of other materials
may be used provided the hammer energy transmission
characteristics of the proposed capblock are equal to or
greater than the wood capblock specified herein. The use
of wood chips, small wood blocks, rope or other material
which permits excessive loss of hammer energy shall not
be permitted. The introduction of fresh capblock material
just before or during the final driving of the pile shall not
be permitted.
Observation shall be made during driving to determine
whether or not the soil and/or water is rising inside
the pile. If this occurs to such an extent that soil and/or
water is trapped in the pile under the follower, provision
shall be made for the escape or removal of such soil
and/or water before driving is continued.
No concrete shall be placed in any pile shell until the
shell has been inspected and found to be free of water,
debris or other foreign matter.
Concrete for cast-in-situ piles shall have an ultimate
compressive strength of not less than 20N/mm2 at the end
of 28 days and shall be composed of approved Portland
sulphate resisting cement, clean sharp sand and gravel or
crushed stone of maximum 25mm diameter. Care shall be
taken to ensure that the concrete is thoroughly compacted
and that the minimum cover of 38mm to the main
reinforcing bars is maintained throughout.
After driven shells have been inspected and found
satisfactory, approximately 0.03 cu.m. of 1:2 cement
grout shall be deposited in each pile followed by concrete
of 100 to 125mm slump deposited in the pile in a
continuous operation through a funnel hopper having a
discharge opening not greater than 200mm in diameter.
Concrete strength shall be determined from Standard
Cube Test made from each day’s pour as specified for
reinforced concrete.
STEEL REINFORCEMENT
4065.
PAYMENT FOR
4066.
CAST-IN-PLACE
REINFORCED
CONCRETE PILES
TYPES “B” AND “C”
All Steel Reinforcement shall be in accordance with
the drawing prepared by the Contractor or the Engineer
whichever is applicable. It shall comply with the latest
issue B.S. 785, B.S. 4449 or B.S. 4461, depending on the
type specified. All bars bending to be in accordance with
B.S. 1468. Reinforcement shall not be welded except
where indicated on the drawings.
Payment for Cast-in-Place Reinforced Concrete Piles of
Types “B” and “C” shall be made on the basis of the
length of the pile per linear metre, from the tip to the
cut – off elevation at the tendered rates and prices
entered in the Bill of Quantities for the particular type and
dimension of pile.
The tendered rates and prices shall be deemed to include
for all materials, equipment, labour and supervision
involved in the complete pile driven and in place.
No payment shall be made for withdrawn or rejected piles.
(CLAUSES 4067 – 4069 INCLUSIVE NOT USED)
PART (E) – CAST-IN-PLACE REINFORCED
CONCRETE PILES TYPE “D”
In addition to the requirements of any other parts of this
section of the specification the following requirements
shall be complied with in respect of cast-in-place
reinforced concrete piles of type “D”.
GENERAL
4070.
DETAILED
METHOD OF
CONSTRUCTION
4071.
PAYMENT FOR
4072.
CAST-IN-PLACE
REINFORCED
CONCRETE PILES
OF TYPE “D”
Cast-in-place reinforced concrete piles of type “D” are
formed by the driving of a heavy steel pipe casing closed
at the lower end by a cast steel pointed shoe firmly fitted
to the casing so as to provide a watertight joint.
Reinforcement steel is then placed within the casing and
concrete poured, the casing may be removed whilst the
concrete is being poured. Alternatively the casing may be
filled with the concrete aggregate mix and cementsand
grout injected after the casing has been removed.
Where this type of piling is pro posed for the
works, the Contractor shall submit, in detail, his
proposed method of carrying out the piling, to the
Engineer for his approval, and shall carry out the work
strictly in accordance with the method as approved by the
Engineer.
Payment for cast – in – place reinforced concrete pile of
type “D” shall be made on the same basis as for piles of
types “B” and “C” at the tendered rates and prices
(CLAUSES 4073 – 4079 INCLUSIVE NOT USED)
PART (F) – PRESTRESSED CONCRETE
CYLINDER PILES TYPE “E”
In addition to any other requirements of any other parts of
this section of the specification, the following
requirements shall be complied with in respect of
prestressed concrete cylinder piles of types “E” and “F”.
GENERAL
4080.
Prestressed concrete cylinder piles of type “E” shall have
outside diameter and minimum dimensions as indicated on
the drawings or as approved by the Engineer. Prestressing
cables of the composition, number and type as indicated
on the drawings or approved by the Engineer, shall be
uniformly placed in the wall of the piles.
MANUFACTURE
4081. (I)
(II)
All materials shall be as stated in the relevant parts of the
specification.
Metal forms shall be used and they must be well braced
and stiffened against deformations under pressure of the
wet concrete. They shall have smooth joints and inside
surfaces accessible for adequate cleaning. The portions
of the form which form the end surfaces of the pile (or
sections) must be a true plane and perpendicular to the
axis of the pile with the following tolerances: Maximum
allowable deviation for abutting end surfaces 3mm, for
head ed surfaces, 13mm and for the point end 76mm.
Forming tubes for the longitudinal holes for the
prestressing cables shall be 35mm nominal diameter and
shall be positioned so that there will be a minimum cover
of 38mm to the outside finished surface of the pile, shall
be inside the spiral steel reinforcement and shall be
uniformly spaced around the pile circumference.
HANDLING
4082.
Piles shall not be handled or moved in any manner that
would result in cracking or permanent damage to the
concrete or to the grout surrounding the wires.
EQUIPMENT
4083.
Piles shall be driven with an approved hammer which
shall develop a rated energy per blow of not less than
54,300 Joules and which shall have a ram weight of not
less than 6,800 Kg. A solid hardwood cushion block, at
least 150mm thick, shall be used in the base of the
hammer between the hammer ram and the follower. A
laminated ring-shaped cushion block at least 150mm
thick made up of 25mm hardwood boards and cut to fit
the head of the pile, shall be used between the follower
and the top of the pile. Both cushion blocks shall be
inspected periodically during driving and blocks that have
been unduly worn and compacted with use shall be
replaced before driving is continued.
Piles may be driven without guides or leaders except that
the hammer shall be kept in accurate alignment with the
axis of the pile.
Each pile of pile section shall have a cage of
nonprestressed reinforcing steel of the size, dimension
and arrangement shown on the contract drawings or as
approved by the Engineer. This reinforcing cage shall be
securely held in position during the casting and spinning
of the concrete. The spiral steel reinforcement shall have
a minimum concrete cover of 25mm to the outside
surface of the finished pile.
Concrete used shall be not leaner than Grade 35N/mm2 or
as indicated on the Contract drawings. The concrete mix
shall be such as to give the most uniform possible
distribution of the aggregates across the wall of the pile.
The fine and coarse aggregates shall be as nearly as
possible of the same specific gravity.
REINFORCING
4084.
CONCRETE
4085.
CASTING
4086.
Piles shall be centrifugally cast and shall be cast in
convenient sections as approved by the Engineer.
CURING
4087.
Piles or pile sections may initially be steam cured. After
removal of forms, membrane curing may be applied to all
surfaces except abutting end surfaces and core holes.
METHOD OF
HANDLING
4088.
The Method of Handling piles or pile sections shall
be such that no permanent damage to the concrete will
occur. If piles are made up of sections, any section that
has more than 10% of the end surfaces spalled to a depth of
more than 3mm shall be rejected.
ASSEMBLY OF
4089.
In making up the full length pile, the abutting surface
SECTIONS
STRESSING OF
CABLES
4090.
GROUTING OF
CABLES
4091.
of each section shall be covered by a sealing material of
sufficient thickness to fill all voids (except at the cable
holes) when the sections are brought together under
compression as later specified. This sealing material must
attain a minimum ultimate strength of at least equal to or
greater than that of the concrete and must be as resistant to
exposure and weathering as is the concrete. After the
sealing material is applied, the pile sections shall be
brought into contact and held together by a force
equivalent to not less than 0.79 N/mm2 on the gross
concrete area while the sealing material sets. The
individual sections shall be lined up so that the maximum
deviation in the alignment of the outside surfaces of two
adjacent sections at the joint will not exceed 6mm and the
maximum deviation in the alignment of the prestressing
cable holes at the joint will not exceed 6mm.
Piles shall not be stressed until the compressive strength
of the concrete is at least 30.0 N/mm2 after the
prestressing cables have been threaded through the cable
holes to make up cables of the required number of wires;
the cables shall be tensioned to an average cable unit
stress as indicated on the drawings or approved by the
Engineer.
This tension shall be measured by the
elongation of the wires and checked by the jack pressure.
The tension in the wire shall be transferred to mechanical
end-locks or anchors. Aggregate stress losses through
transfer of the stressing force from the jack to temporary
anchorage shall not exceed an average of 10% on one
cable or an average of 5% on all cables in any one pile.
All cable holes shall be grouted with a mixture of
cement and water in such a manner that the interstices
are completely filled with the grout material. The cable
tension shall be maintained by the mechanical anchors
while the holes are grouted and until the grout attains
sufficient strength to hold permanently the tension in the
cables. During this period, the piles shall not be moved
or handled in any manner that would result in permanent
damage to the grout. The grout curing period must be
sufficient to permit the removal of the temporary anchors
without slippage of the wires in the grout except that the
stress loss through transfer shall not exceed an average of
10% on one cable or an average of 5% on all cables in
any one pile. During removal of end anchors, if the wires
do not part under stress with a “Cup and Cone” fracture,
but can be burned completely through with a cutting
torch, no slippage is considered to have occurred.
DRIVING
RESISTANCE
4092.
Piles shall not be driven until the concrete has
attained the minimum strength as specified on the
drawings.
The piles shall be driven to a resistance or tip elevation as
determined by load test to be satisfactory for the required
design load, but the final resistance shall not exceed 10
blows per 25mm with the approved hammer. In no case
shall the stroke of the hammer exceed 1200mm.
TENSION
FORCES
DURING
DRIVING
4093.
When the point of the pile is passing through soft soil
so that there is little or no resistance to penetration at
the botton of the pile, the stroke of the hammer shall be
reduced to approximately 600mm.
CONTROL OF
EXTERNAL
PRESSURES
4094.
Observation shall be made during driving to determine
whether or not the soil and/or water is rising inside the
pile casing. If this occurs to such an extent that soil and/or
water is trapped in the pile under the follower, provision
shall be made for the escape or removal of such soil and
or water before driving is continued.
PRE-EXCAVATION 4095.
The Contractor may use any combination of driving and
drilling approved by the Engineer to obtain the required
pile embedment. Jetting or pre-excavation shall be done
below the pile tip elevation and the final seating of the
pile shall be done by driving only for the last 3 metres.
TOLERANCE
Piles may be driven with the use of template or other
method approved by the Engineer. The top of each pile
shall not vary ore than 150mm from the required plan
location.
CUT-OFF
4096.
Where piles are required to be cut-off, cuttings may be
performed with pneumatic tools, sawing, or other method
approved by the Engineer. In no case shall explosives be
used fur cutting off piles.
4097.
PILE SPLICES
4098.
If pile tops are driven below the established cut-off
OR BUILD-UPS
elevation or if pile tops are damaged below the cut-off
elevation, the pile shall be built up to the required elevation
using a cast-in-place concrete extension of the cylinder or
by use of an acceptable length of cylinder pile section. The
pile splice shall consist of a poured plug or reinforced
concrete extending at least 1.4 metres into the original pile
and, where possible, the same length into the added section
as detailed on the drawings. This concrete plug may be an
extension of the plug connecting the pile to the cap.
DEFECTIVE PILES 4099.
Piles damaged by improper driving or manipulation to
force them into proper position shall be repaired at the
Contractor’s expense to the satisfaction of the Engineer.
Any pile damaged by handling or in transit shall be
repaired to the satisfaction of the Engineer or shall be
replaced all at the Contractor’s expense.
Payment for prestressed concrete cylinder piles of type
“E” shall be made on the same basis as for piles of types
“D” or “C” at the tendered rates and prices.
PAYMENT
4100.
(CLAUSES 4100 – 4109 INCLUSIVE NOT USED)
PART “G” – PRESTRESSED CONCRETE PILES
OF TYPE “F”
In additional to any other requirements of any other parts
of this section of the specification the following
requirements shall be complied with in respect of
prestressed concrete cylinder piles of the types “F”.
GENERAL
4110.
METHOD OF
MANUFACTURE
4111.
Prestressed concrete cylinder piles of type “F” are formed
by the forcing into the ground of heavy steel casing and
the removal of the earth from its inside. After the casing
has been installed to the required depth a precast
prestressed concrete cylinder pile is inserted into the
casing either in sections and stressed in situ or as a
complete unit. The space between the steel casing and
the prestressed concrete shall be grouted with sandcement
grout as directed and approved by the Engineer.
Where prestressed concrete cylinder piles of Type
“F” are proposed for use in the works, the method of
manufacture and construction shall be as approved by the
Engineer and the Contractor shall comply strictly with
this approved method.
PAYMENT
4112.
The payment for prestressed concrete cylinder piles shall
be made on the same basis as for piles of type “E”.
(CLAUSES 4113 – 4119 INCLUSIVE NOT USED)
PART “H” – STEEL SHEET PILES
STEEL SHEET
PILES
4120.
All steel sheet piles shall be of an inter-locking
section as shown on the drawing and shall be a type and
manufacture approved by the Engineer.
Steel sheet piles, tie rods, rivets and bolts shall conform
to the minimum requirements of B.S. 4360, Parts 1 & 2
and B.S. 449. If cofferdams for foundation construction
are used, the steel sheet piling for the cofferdams shall be
carried well below the bottom of the footings and shall be
well braced and as watertight as practicable.
The interior dimensions of cofferdams shall provide
sufficient clearance inside the walls for constructing
forms and driving pile and to permit pumping outside the
forms.
For purpose of constructing the cofferdam, any
enlargement in excess of 50mm outside the dimensions of
the footing as shown on the drawings shall be considered
as being for the sole purpose of expediting the work of
the contractor as is of no value to the F.M.W.H. and
quantities of such excavation and backfill will not be
included in the quantities to be paid for.
In tidal waters or in streams at a time of probable flood,
cofferdam walls shall be vented at low water elevation to
ensure equal hydrostatic head both inside and outside of
the cofferdam during the period of placing and setting of
seals.
No shoring will be permitted in cofferdams, which will
induce stress, shock, or vibration in the permanent
structure.
When permitted by the Engineer, cross struts or bracing
may extend through foundation concrete. Such struts or
bracing below low water will be permitted to remain in
place, or when specified in the special provisions or
shown on the drawings, to be removed. Struts or bracing
above low water shall be removed and the resulting space
filled with concrete of the same mix as that specified for
the surrounding concrete.
The Contractor shall submit to the Engineer, for
approval, drawings showing his proposed method of
cofferdam construction and other details left open to his
choice or not fully shown on the drawings. The drawings
shall be submitted at least two weeks in advance of the time
the Contractor begins construction of the cofferdams.
After completion of the sub-structure, the cofferdams
with all sheeting and bracing shall be removed at least to
1 metre below the level of the stream bed, by the
contractor at his own expense, and such removal shall be
performed in a manner that will not disturb or mar the
finished concrete or masonry.
WELDING
ELECTRODES
4121.
Electrodes used for welding shall comply with B.S. 639
or B.S. 693 depending on the type employed.
PROTECTIVE
PAINTING
4122.
Where directed on the drawings or in the
specifications, steel sheet piles shall be coated before
driving with two coats of an approved bituminous paint,
in a manner as directed by the Engineers Representative.
DRIVING ETC.
4123.
The piling shall be driven either singly or in pairs
vertically and to true lines and even planes in the position
shown on the drawings and to the levels indicated
thereon. Should there be any defect in the horizontal or
vertical alignment of the piling or should a break, through
any cause whatsoever, occur in the continuity of the
piling, the Contractor shall withdraw such defective pile
or piles and drive such further piles as may be necessary
to remedy the defect. Should any distortion, fanning or
creep occur in the alignment of the piling the contractor
shall immediately take steps to rectify the defect and
shall, where necessary, supply and drive suitable tapered
piles to the satisfaction of the Engineer’s Representative.
All costs incurred by the Contractor in carrying out the
necessary remedial measures shall be at his own expense.
Should any tapered piling have to be manufactured
locally they shall have along the joint 22mm diameter
rivets at 150mm pitch except for a length of 600mm,
150mm at each end the pitch shall be 75mm.
All necessary holes for the tie-rods shall be neatly drilled
and for drains they shall be neatly burnt out, all in the
positions shown on the drawings.
THE RODS
AND ROPES
4124.
The steel sheet piling shall be connected to the anchor
piles by mild steel tie-rods or ropes as approved by the
Engineer. They shall be in lengths as indicated and
coupled together with forged steel coupling boxes or
turnbuckles. Each end of each rod shall be threaded for a
distance of 230mm with standard whitworth right and
left-handed threads as the case may be. Mild steel
bearing plates and washers of approved sizes shall be
provided for the outer-end of the tie-rods, the washers
being tapered.
PAYMENT
4125.
The tie-rods and ropes coupling boxes or turn-buckles and
other fittings shall be cleaned with wire brush or other
approved means to remove all millscale, rust, etc., and
shall then be given one coat of the bituminous solution
and the tie-rods and ropes shall, after fixing in position, be
wrapped in approved hessian and, with all fittings, be
given a second coat of the approved solution. Where
possible the coupling boxes or turnbuckles shall also be
wrapped in hessian.
The quantity of sheet piling to be paid for under this item
in this section except for cofferdams, will be the number
of square metres of sheet piling placed in its final
position. The unit price bid for this item shall include the
cost of furnishing all labour, materials and equipment
necessary to complete the work, including the cost of
furnishing and placing, if necessary removing, all wales
and braces. No separate payment will be made for
providing cofferdams unless it is called for on the
drawings.
When Cofferdams are called for on the drawings they
shall be paid for at the contract lump sum price bid for the
item COFFERDAM in the proposal.
This price shall constitute full compensation for
constructing cofferdams, controlling, removing water
from excavation, all labour, materials, tools, equipment
and incidentals.
SPECIFICATION
SECTION V
BRIDGEWORKS
SECTION V
BRIDGEWORKS
GENERAL
5000.
In addition to any other relevant clause of this
Specification, the following shall be deemed to apply in
particular to bridge works, and shall be read in
conjunction with all other relevant Clauses of the
Conditions of Contract and this Specification.
PART (A) – PRELIMINARIES, EXCAVATIONS,
FOUNDATION, DEMOLITIONS, TEST LOADS,
ETC.
GENERAL
5001.
TRAFFIC
5002.
The Contractor shall himself obtain full and accurate
information in connection with the existing structures,
traffic, periods of flow and non-flow in the waterways,
normal water levels, whether above or below ground
level, flows and frequencies, floods, nature and condition
of soils and sub-soils, etc., and generally acquaint himself
with all factors influencing the construction and
maintenance of the works as shown on the drawings and
specified herein, and shall be deemed to have allowed for
all such conditions in the rates inserted by him in the bill
of quantities.
Before commencing any operation of construction,
the Contractor shall forward to the Engineer’s
Representative, and obtain his approval of, his proposals
for avoiding interference with the existing traffic-way,
rail road and water, and for providing, and maintaining
alternative ways for all such traffic. All diversions shall
be of dimension, capacity and standard at least equal to
those of the traffic-ways, which they replace when such
traffic-ways are maintained in a good condition and they
shall be maintained continuously to this standard during
the period they are in use.
Where the use of temporary bridge spans is involved, the
Contractor shall submit complete and detailed drawings
and calculations for the scheme to the Engineer’s
Representative. The Engineer’s decision on whether such
methods may be adopted or not shall b absolutely final.
DIVERSION
Notwithstanding the approval or modification by the
Engineer’s Representative of any schemes, drawings or
calculations, the Contractor shall remain wholly and
entirely responsible for the sufficiency of all traffic
diversions and temporary works and for all obligations
and risks in regard to such works specified or implied in
the contract and he shall reinstate the same at his own
cost should any mishap or accident occur causing damage
or injury thereto subject to such provisions of the
conditions of contract as may be applicable.
Payment for all such diversions including for temporary
bridging or converting as necessary shall be deemed to be
included in the tendered rates and prices unless elsewhere
expressly allowed for.
CLEARING OF
THE SITE
5003.
WATER TRAINING 5004.
AND PROTECTION
The site of the works shall be cleared completely to the
satisfaction of the Engineer’s Representative. Generally,
the waterway shall be cleared of all obstructions to the
flow of water. All fallen trees, bushes and accumulations
of debris shall be removed and deposited as directed.
Trees, which are to be retained, shall be indicated by the
Engineer’s Representative.
Such details of training works and protective works
to the banks and protection beds of waterways as may
be shown on the contract drawings are schematic only.
Exact details of the training and protective works shall be
supplied by the Engineer’s Representative after
consideration of the final disposition of the works, local
site conditions, etc.
WORKS
EXCAVATION
AND BACK
FILLING
5005. (A)
GENERAL
Excavations shall be of the widths and lengths necessary
for the construction of the works and shall be taken down
to the depths shown on the drawings, or as otherwise
specified hereafter or to such other depths as the
Engineer’s Representative may require. When the final
level of the excavation has been reached, the Contractor
shall so inform the Engineer’s Representative, and
together they shall inspect, measure and agree in writing
all particulars on which measurements of the works are to
be based. No back filling or construction shall be
undertaken until after the final levels and dimensions of
the excavation have been surveyed and agreed. Failing
such surveys and agreements being signed by the
Contractor, the surveys of the Engineer’s Representative,
shall be final and binding on the Contractor.
Any obstacle encountered in the course of excavations shall be reported to the Engineer’s
Representative and dealt with as directed by him.
Excavations shall, where necessary, be properly shored
and supported, and the Contractor shall provide pumps,
cofferdams, sheet piling etc., as necessary to ensure that
all construction is carried out in the dry. Should any slips
or falls result from the omission by the Contractor of any
precaution, all loose and disturbed material shall be
completely removed and the ground made up at the
Contractor’s own expense with approved material which
shall include concrete grade 10N/mm2 should the
Engineer’s Representative so require. Should the material
forming the bottom of any excavation, whilst acceptable
at the time of excavation, become puddle, soft or loose
during the progress of the works, the Contractor shall
remove such damaged, softened or loosened materials and
replace them with concrete grade 10 N/mm2 or as
directed by the Engineer’s Representative, at the
Contractor’s own expense. Sumps dug in the bottom of
excavations shall be cleaned out, all soft and puddle
material removed, and the hole made up with approved
material as described above. Should excavations be taken
to a depth greater than that required by the Engineer’s
Representative such extra depth shall be made up at the
contractor’s expense with concrete grade 10 N/mm2 or as
directed by the Engineer’s Representative.
The Contractor shall not leave any item or temporary
works in position in the excavations after back-filling,
without the permission of the Engineer’s Representative.
Permission will only be given in cases where the
Engineer’s Representative is satisfied that no adverse
effect will result to the finished works. No payment shall
be made to the Contractor for any item of temporary
works so left in position, unless such item was left in on
the explicit instructions of the Engineer’s Representative.
Excavations shall be backfilled with approved materials
in layers not exceeding 150mm compacted thickness, and
shall be thoroughly compacted by approved methods.
Where such material lies below a roadway or will form
part of an embankment it shall be selected and compacted
entirely in accordance with the requirements of all
relevant clauses of this specification. Back-filling of
excavations for reinforced concrete culverts, open drains
and any other structure shall be brought up equally on
either side of the structures to eliminate unbalanced earth
pressures.
Earth and other material taken from excavation shall be set aside for selection for re-use as
filling materials, and materials unsuitable for this purpose
shall be disposed of by the Contactor at his own expense,
as directed by the Engineer’s Representative.
Selected materials shall be free draining material. The material shall have Plasticity Index
(PI) of not more than 5, and shall meet the following
gradation requirements when tested in accordance with
B.S. 410:Sieve Size
Total Per cent Passing
(by weight)
50mm
100
25mm
60 – 100
1.1mm
20 – 100
10 – 70
500µm
8 – 40
255µm
5 - 10
74µm
When tested for bearing capacity, selected material shall have a California Bearing Ratio
(CBR) of not less than 20% when compacted to 95% of
maximum density, using BS compactive effort up to a
depth not more than 600mm to formation level; there after
compaction shall be 100% MDD of the material using BS
effort.
Free draining shall be defined as a material having coefficient of permeability of not less than 1
x 102
mm/sec.
Before driving piles, the common embankment material
shall be placed and compacted to the top elevation of the
prism of selective material.
No payment for placing of selective material will be made, but the cost thereof shall be
included in the price bid for the item “Excavation and
Backfill” scheduled in the proposal.
(B)
PAYMENT FOR
EXCAVATIONS
5006.
ROCK
The term “solid rock” shall mean rock found in ledges or
masses in its original position, which would normally be
removed by blasting and pneumatic tools or by wedges
and sledge hammers if removed by hand, and all solid
boulders or detached pieces of rock exceeding 0.2 Cubic
metres in size trenches and 0.3 Cubic metres in size in
general excavations, to the classification of which the
Engineer’s Representative is satisfied.
Should any
difference of opinion arise between the contractor and the
Engineer’s Representative as to whether any material is
rock, the Engineer’s decision shall be final and shall be
made before the material is disposed of or covered up.
Should the Contractor wish to use explosives for the
excavation of rock, he must obtain the permission of the
Engineer’s Representative. When permission is granted
the Contractor shall proceed as directed in, and satisfy all
the requirements of, clause 99 of the conditions of contract
and clause 5010 of this specification.
Excavations for foundations shall be paid for on the
actual quantities measured on site by multiplying the
FOR FOUNDATIONS
EXCAVATIONS
5007.
FOR FOUNDATIONS
BELOW WATER
LEVEL
horizontal area of the base of the foundations by the mean
depth from surface level, and at the appropriate rates for
excavation inserted in the bill of quantities. The rate shall
include for all shoring, pumping, backfilling and
compactions and for all pumping, digging, backfilling of
sumps and for all other things necessary to allow the
proper placing of the foundations. No payment shall be
made to the contractor for any item of temporary works
left in position unless it has been left on the instruction of
the Engineer’s Representative. No item of temporary
works shall be left in position without the approval of the
Engineer’s Representative.
Where excavations have to be made and foundations
formed below water level, suitable arrangements shall
be made to exclude the water from the site, and the Contractor shall, when tendering, submit a full and clear
description, supported by drawing and sketches, of the
methods he proposed to use in respect of each foundation
where these conditions will be encountered. The methods
proposed shall be directed in all cases to permit the
execution of the whole of the work in the dry unless this
is shown in the method statement to be entirely
impracticable or uneconomical. The Contractor must
satisfy himself absolutely as to what water levels may be
experienced at and during the period of construction,
whether such water levels be above ground level or below
and as to what flows and water levels will be attained
during flood and high tide periods and as to the conditions
of soils and sub-soils and all other matters pertaining to
the adequacy of the temporary works and the efficient and
proper construction of the works themselves. The
Contractor shall take all precautions to prevent flooding
of the works and shall make good any loss or damage to
the temporary works and the works themselves caused
thereby at his own cost and to the satisfaction of the
Engineer’s Representative.
If Contractor chooses to use steel cofferdams for the
below water level foundation excavations, the materials
shall conform to SECTION IV, clause 4120 “STEEL
SHEET PILES”.
No separate payment for cofferdams will be made, but the
payment shall conform to the applicable portion of the
SECTION IV, Clause 4125 “PAYMENT”.
PREPARATION
FOR
FOUNDATIONS:
NORMAL
5008.
The depths to which foundations are to be taken, and
their dimensions as shown on the drawings are an indication only of the anticipated requirements. The actual
depths and consequently the dimensions are to be finally
determined on site by excavating through the various
strata until a material is reached, which is capable, in the
opinion of the Engineer’s Representative, of safely
sustaining the pressure exerted and of providing complete
security against the effects of scour. All excavations shall
be taken out as nearly as possible to exact dimensions to
minimize back-filling and in accordance with clause 5005
of this specification.
No concrete shall be placed in any foundation until the
Engineer’s Representative has inspected and approved the
excavation and the arrangements for transporting and
depositing the concrete, and given permission in writing
to proceed. The sides of the excavation shall be such as
to eliminate any possibility of loose material falling into
the work as concreting proceeds. The bottom of the
excavation shall be clean and levelled off and free from
all loose material. Contractor shall draw the attention of
the Engineer’s Representative to any soft spots which
may occur and these shall be cut out as directed,
measured in conjunction with
the Engineer’s
Representative, and afterwards filled with concrete grade
10 N/mm2. No payment shall be made for cutting out and
filling soft spots, which have not been measured in
conjunction with the Engineer’s Representative. When
foundations are to rest on rock, all adherent clay, etc.,
drummy, soft and loose rock, shall be cut away until the
hard solid rock is exposed and the base left approximately
horizontal or to a slight fall or stepped, as may be directed
by the Engineer’s Representative. Immediately before
concreting is commenced, the surface of the rock shall be
thoroughly cleaned and wetted and the concrete shall be
poured directly on to the rock and against shaped sideshuttering. The filling of the hollows with rubble, broken
rock etc., will not be permitted.
It is the intention that all concrete shall be placed in the
dry, and the Contractor shall direct all his efforts towards
this end.
REMOVAL OF
EXISTING
STRUCTURE
5009.
Before any part of any existing structure is removed
removed, the Contractor shall forward to the Engineer’s
Representative for approval, full details of the method by
which he proposes to GENERAL dismantle the structure
and provide an alternative way for traffic during the
subsequent works.
(See also clauses 90 of the conditions of contract and
5002 of this specification). Such details shall be
accompanied by drawings and calculations as required by
the Engineer’s Representative showing that no part of the
structure which may be required for re-use in another part
of the works or by the Engineer elsewhere under another
contract, shall be over stressed or damaged in any way
during the operation. Such details shall be submitted to
the Engineer’s Representative sufficiently in advance of
the intention to commence the work as this will allow the
proper study of the proposals and the incorporation of any
amendments that the Engineer may require.
Notwithstanding the incorporation of any such
amendments or any approval given by the Engineer’s
Representative to any method proposed, the Contractor
shall remain wholly and entirely responsible for the safety
of the work and for all obligation and risk specified or
implied in the contract and shall make good at his cost
any damage resulting from any mishap or accident arising
from the operation, subject to such provisions of the
conditions of contract as may be applicable. The
demolitions and dismantling shall be carried out in a
workmanlike manner and the contractor shall observe all
rules, regulations and orders which may have been made
or may be made by the government or any other
responsible authority with regard to the safety of all
persons, whether employed by him or not during such
operations.
EXPLOSIVES
5010.
Before removing any superstructure or sub-structure, the
Contractor shall bring to the notice of the Engineer’s
Representative any existing damage to the structure and
point out any missing parts and the Engineer’s
Representative and the Contractor shall together agree in
writing that such damage did exist and that such parts
were missing before the commencement of operations by
the Contractor. Should the Engineer then require the
Contractor to repair such damage or to replace such
missing parts, the Contractor shall do so as directed and
he shall be paid for the work at rates to be mutually
agreed between him and the Engineer. Should the
Contractor fail to bring such damage or missing parts to
the notice of the Engineer’s Representative, it will be
deemed for the purpose of subsequent payment that the
Contractor accepts that the structure is complete and
entirely free from damage before the commencement of
dismantling operations. After dismantling, the Contractor
shall spread out all the components and advise the
Engineer’s Representative that they are ready for
inspection. Any damage or loss discovered in addition to
that previously agreed shall be made good at the
Contractor’s own cost and to the satisfaction of the
Engineer’s Representative. Parts which have been lost
shall be replaced by entirely new material and members
which have been damaged shall be repaired or completely
replaced as required by the Engineer, who shall consider
the degree of damage in relation to the importance of the
member, and the Engineer’s decision in these matters
shall be final.
Should the Contractor wish to demolish any part of the
existing structure by using explosives, he must first
satisfy the Engineer’s Representative that this is the most
economical and satisfactory way of performing the work
and obtain his permission to proceed. The Contractor
shall provide proper buildings or magazines unsuitable
positions for the storage of the explosives in a manner and
in quantities to be approved. He shall also be responsible
for the prevention of any un-authorized issue or improper
use of any explosive brought on to the works, and shall
employ experienced and responsible men by whom only
shall explosives for the purpose of the works be handled,
all to the satisfaction of the Engineer’s Representative and
in conformity with the statutory regulations. During
blasting, the greatest care shall be taken by the Contractor
that no injury be done to persons or property or to any
finished work or any work which is to remain untouched.
The shots shall be properly loaded and covered and only
moderate charges shall be used, and where directed by the
Engineer’s Representative, the Contractor shall provide
heavy mesh blasting nets. Blasting shall be restricted to
whatever hours the Engineer’s Representative shall
prescribe.
If, in the opinion of the Engineer’s
Representative, blasting would be dangerous to persons or
adjacent structures, or is being carried on in a reckless
manner he may prohibit it, and order that the demolition
be carried out by other means. See also clause 99 of the
Conditions of Contract.
REMOVAL OF
5011.
EXISTING SUPER
STRUCTURES AND
SUB-STRUCTURES
STEEL AND
CONCRETE
Existing concrete deck, where required to be removed
shall be demolished in a manner which will ensure
that no damage whatever shall be caused to the
supporting steel troughing joists, trusses, bracing, or
any other member of part of the structure. The use of
explosive is forbidden.
Before dismantling any part of any structure which is to
be re-used either wholly or in part, either by the
Contractor in another part of the works or by the
Engineer elsewhere under another contract, the Contractor
shall mark each part of the structure with a distinguishing
mark which shall be assigned to it in a parking plan to be
prepared by him, in figures or letters not less than 50 mm.
high and in such a manner that the pieces may be readily
identified and put together again in their proper positions
when required. The figures and letters shall be painted
on, in at least two places on each member, and on a
surface which has first been thoroughly cleaned and freed
from all rust, loose paint, grease, dirt and other
deleterious coatings and given one coat of protective
paint. The colour of the paint to be used for the letters
and figures shall be such as to make them readily visible
against the background of protective paint. Where more
than one bridge is to be marked in any contract, the
Contractor shall ensure that no combination of figures and
letters employed in the marking of one bridge is repeated
in the marking of another. All markings shall be to the
approval of the Engineer’s Representative and
dismantling of the structure shall not be proceeded with
until the Engineer’s Representative has checked and
approved the marking on the structure and compared
them with those on the marking drawings and given his
permission to proceed. The drawings showing the
markings shall conform to the requirements of Clause
5020 hereinafter.
The Contractor shall forward to the Engineer’s
Representative one set of hand-made negatives on best
quality linen, one set of velograph negatives on best
quality linen and one set of prints on linen showing black
lines on a white ground, f the marking drawings and the
cost of producing and supplying all these negatives and
prints shall be deemed to be included in the rates for
dismantling.
Troughing, joists, trusses, trestle, piers, cylinders, etc.,
shall be dismantled with great care, temporary supports,
horses, jacks, wedges, stiffening, bracing, etc., being
provided to ensure that there will be no overstraining or
buckling of any member or connection during the
operation. Bolts and other fastenings shall be removed
without causing damage to or elongation of the holes
from which they are withdrawn.
Where required for re-use by the Engineer under another
contract the Contractor shall, after dismantling and
satisfying the requirements of clause 5009, scrape, clean
and free all parts of the dismantled structure from all
loose paint, grease and other deleterious coatings. Areas
of rust should be cleaned down to the bare metal and all
thick edges, fins, blistering etc., due to previous coats of
paint removed. The surfaces, when thoroughly dry, shall
be given one coat of protective paint, particular attention
being given to surfaces which have been in contract or
inaccessible whilst the structure was erected. Care shall
be taken to ensure that the distinguishing marks are not
obliterated during this operation. Surfaces which have
been galvanized shall be examined by the Engineer’s
Representative who shall direct whether the whole is to be
cleaned thoroughly, freed from all deleterious matter and
given one coat of protective paint or whether only the bad
spots are to be touched up with an approved proprietary
galvanizing commodity (aluminium paint is not to be
used for this purpose). All bright and machined surfaces
shall be cleaned and well coated with a mixture of white
lead and tallow free from acid, or with other approved
coating which will not readily melt when exposed to the
sun in the tropics. Exposed machined surfaces shall be
further protected by timber casings or other approved
means. Free ends of members shall be stiffened to
prevent distortion during transit, and the ends of members
with turned bolts connections suitably protected. A full
set of new bolts, nuts and washers, rivets and all other
fastenings should be supplied together with spares in
accordance with clause 5066 of this specification, and in
addition a complete set of erection tools (drifts spanner,
screw-drivers, etc., but not riveting apparatus) in
accordance with clause 5065 of this specification. Turned
bolts, nuts and washers shall be covered with a mixture of
white lead and tallow free from acid and black bolts, nuts
and washers, and field rivets shall be thoroughly cleaned,
heated to about the melting temperature of lead and whilst
hot dipped into boiled linseed oil.
Straight bars and plates shall be bundled and temporarily
bolted together. If this is not possible they shall be found
in at least three places with annealed steel wire of not less
than 6mm diameter which must be tightly fastened. All
rivets, bolts, nuts, washers, screws, small plates and small
articles generally shall be packed in bags. A separate bag
being used for each diameter and length of rivet, bolt etc.,
and each bag having a metal label wired on indicating its
contents. The bags shall be packed into strong wooden
cases or casks whose gross weight shall not exceed 300
kilograms. Each case, cask etc., shall be clearly marked
with its weight and an indication of its contents. Bundles
shall have a metal label, stamped with similar
information, attached to each end, the label being secured
at each of the ends by a separate wire so that it lies flat
with the bundles. All marking and labelling shall be to
the satisfaction of the Engineer’s Representative. All
parts of the structure protected, marked and packed as
above specified shall then be stacked in a position
indicated by the Engineer’s Representative to await
collection by him and transport to his store, and all
operations mentioned in this clause up to and including
this final stacking shall be deemed to e included in the
rates for dismantling the structure. Should the Engineer
require the Contractor to transport the structure to his
store, the Contractor shall do so without delay and
payment shall be made in accordance with the rates in the
day work schedule referred to in the bill of quantities or
as mutually agreed before transporting.
Where the structure is to be incorporated elsewhere into
the works, either wholly or in part, the Contractor shall
proceed as follows. On the marking drawings specified
above, he shall indicate
(i)
Those parts of the structure which are not required
for incorporation into the works and which will be
stacked in readiness for transport to the Engineer’s
store, and
(ii)
Those parts of the structure, which will be
required for incorporation elsewhere into the
works.
Those parts covered by (i) shall be treated entirely as
specified above for structure required for incorporation
elsewhere into the works.
Those parts covered by (ii) shall be treated entirely as
specified above for structures required by the Engineer for
re-use under another contract, with the following
amendments. After dismantling, the required items shall
be spread out and the Contractor shall inform the
Engineer’s Representative that they are ready for
inspection. The Engineer’s Representative shall then
examine the items with respect to length, quality weight
and condition and shall pronounce upon their suitability
for incorporation into the works and shall advise the
Contractor as to what cuts etc., should be made to permit
their proper fitting, and they shall together agree as to
where such work shall be carried out. The items shall
then be transported to that part of the works unto which
they are to be incorporated and the Contractor shall then
proceed as directed in clause 5071 of this specification.
The cost of all operations involved in complying with
these requirements shall be deemed to be included in the
rates for dismantling and re-erection.
All paint and painting shall be in accordance with clause
5049 of this specification.
REMOVAL OF
5012.
EXISTING SUPERSTRUCTURE AND
SUBSTRUCTURE:
ALL TIMBER
Existing decks, trestles, mud sills, piles, etc., in timber
shall be removed as carefully as possible. The use of
explosives is forbidden. Timber piles shall be withdrawn
completely, or sawn off, as directed by the Engineer.
All timber, fastenings, etc., shall be cleaned and stacked
neatly as directed in a place to be indicated by the
Engineer’s Representative.
Unless particularly so
mentioned in the drawings no distinguishing marks,
making plans, painting or protective coatings will be
required.
TOTAL
DEMOLITION OF
EXISTING ABUTMENTS, PIERS
AND LANDINGS
5013.
PARTIAL
DEMOLITION OF
EXISTING ABUTMENTS, PIERS
AND LANDINGS
5014.
DISPOSAL AND
5015.
The demolition of existing abutments, piers and landing
will be permitted only after the superstructure has been
removed to the satisfaction of the Engineer’s Representative, the demolition shall be carefully carried out and
the use of explosives will be subject to the approval of the
Engineer’s Representative. Generally, abutments and
piers which are specified in the drawings to be completely
removed, shall be completely removed above the lowest
level of the ground in contact with the abutments or piers
as approximately indicated in the drawings and in the bill
of quantities, or as directed by the Engineer’s
Representative, below this level only so much will be
removed as is required for the proper construction of the
new abutments and piers. Reinforced concrete piles shall
be completely withdrawn or cut away above the levels
stated in the drawings or as directed by the Engineer’s
Representative.
Abutments, piers and landings, which are required to
be only partially demolished shall be done in a manner
which will ensure that no damage whatsoever will be
caused to that portion or the structure that will remain.
The use of explosives for this work will not be permitted.
The demolitions shall be carried out to the lines and levels
shown on the drawings or to such lines and levels as the
Engineer’s Representative may determine after
examination of the material exposed. The surfaces
remaining after demolition shall be freed from all loose
stones, rubble, mortar or other material and left in a
perfectly sound conditions, to the satisfaction of the
Engineer’s Representative. Under no circumstances shall
any new work be constructed upon or against any part of
the structure that remains until the Engineer’s
Representative has inspected it and given his permission
to proceed.
All concrete and masonry rubble and all other such
RE-USE OF
RUBBLE RESULTING
FROM DEMOLITION
PREPARATION
5016.
OF SURFACES OF
EXISTING ABUTMENTS, PIERS, ETC.
PRIOR TO PLACING
OF CONCRETE IN
CONTACT
PREPARATION
5017.
OF SURFACES OF
EXISTING ABUTMENTS, PIERS,
ETC., PRIOR TO
CONSTRUCTION OF
NON-BONDING JOINT
material resulting from demolition shall be tipped as
directed. No debris shall be allowed to block, interfere with or hinder the flow of water under the new
structure, or along any part of the watercourse or through
any drain, gully or watercourse, in the vicinity of the
work, nor shall any debris be allowed to obstruct the
passage of traffic or cattle or other animals along
recognized paths. The rubble may be re-used as plums in
the construction of the new abutments and piers should
these be of mass concrete, at the discretion of the
Engineer’s Representative.
After demolition operations have been completed the
surfaces of the remaining portions of the substructures
which are to receive new concrete shall be thoroughly
hacked and freed from all loose plaster, mortar and
other materials and random stones shall be removed in
removed in the case of masonry wall as directed by the
Engineer’s Representative to provide an efficient key
between the new work and the old. Immediately before
concreting begins, the surfaces shall be thoroughly
washed with clean fresh water to remove all deleterious
matter, all surplus water being then removed. The wet
horizontal surfaces shall be covered with a 12mm layer of
stiff, freshly mixed mortar class M1 that shall be poured
and carefully pounded into it without delay. The fresh
concrete shall be carefully worked into all corners,
crevices and interstices in the wet vertical surfaces to
ensure complete bonding with the old structure.
Where the drawings require a non-bonding joint or a gap
to be left between the surfaces of the remaining portions
of the existing sub-structure and those of the new work,
the relevant surfaces of the existing structure shall be
thoroughly cleaned and freed from all loose
material.
Irregularities in the surfaces shall be filled in with conGrade 10 N/mm2 or the whole rendered with a minimum
12 mm thickness of plaster of a grade to be approved by
the Engineer’s Representative, to give a smooth surface
over the whole area of the joint. The non-bonding joint
shall then be constructed as directed by the Engineer’s
Representative or a gap left as directed in the drawings.
TEST ON
5018. (A)
COMPLETED
STRUCTURES
CONCRETE STRUCTURES
The Engineer may instruct that a loading test be made on
the works or any part thereof it, in his opinion, such a test
is deemed necessary for one or more of the following
reasons:(a) The site made concrete tests cubes failing to reach the
specified strength,
(b) The shuttering being prematurely removed,
(c) Overloading during construction of the works or part
thereof,
(d) Concrete improperly cured.
(e) Any other circumstances attributable to alleged
negligence on the part of the Contractor which, in the
opinion of the Engineer may result in the works or part
thereof being of less than the expected strength.
(f) Any reason other than the foregoing.
If the loading rest be instructed to be made solely or in
part for the reason (a) the test shall be made at the
Contractor’s own cost. If the test be instructed to be
made for one or more of the reasons (b) to (e) inclusive,
the contractor shall be reimbursed for the cost of the test
if the result thereof is satisfactory. If the test be instructed
to be made for the reason (f) the Contractor shall make
the test and shall be reimbursed for all costs relating
thereto unless the result of the test is unsatisfactory in the
opinion of the Engineer.
The test load shall not be applied within eighty-four days
of the completion of placing of the concrete in the part of
the structure to be tested, and the latter shall not be
supported during the test by the shuttering or other
nonpermanent support. Means shall however be taken to
ensure that in the event of failure under the test,
temporary support of the loaded members shall be
immediately available. The test shall proceed strictly as
directed by the Engineer.
If the result of the loading test is not satisfactory in the
opinion of the Engineer, the Engineer shall instruct that
part of the works be taken down or cut out and
reconstructed to comply with this specification, or that
other remedial measures be taken to make the work
secure.
All remedial measures shall be carried out expeditiously by
the Contractor at his own expense.
The test load to be applied shall be a series of tractors,
lorries, or road rollers equivalent to the 1.10 times the
design load of the particular structure, disposed of in one
or more arrangements so that the maximum bending
moments, thrusts, tensions and shear forces due to the test
load are produced at the critical sections. During the test,
record of the sequence of all cracks and deflections at
mid-span will be kept together with any other
observations which the Engineer may elect to record. The
residual deflection if any shall be recorded and if required
by the Engineer, the test will be repeated. The period of
loading shall be one hour in any particular case or as
otherwise directed by the Engineer.
(B)
STEEL STRUCTURES
If, through any negligence or bad workmanship or
carelessness or default on the part of the Contractor or
any Sub-Contractor or for any other reason whatsoever,
the Engineer shall deem the strength of any steel span or
any part thereof to be adversely affected, the Engineer
shall order such tests to be carried out as shall indicate the
real strength of the structure. The test may follow that
specified above for reinforced concrete structures or any
other form that the Engineer may consider desirable.
If in the opinion of the Engineer, the result of the test is
not satisfactory the Engineer shall order such remedial
measures to be carried out as may be necessary in his
opinion, and the contractor shall carry out such remedial
measure without delay and at his own expense.
LOADING OF
STRUCTURES;
CONSTRUCTION,
BACKFILLING,
TRAFFIC, ETC.
5019.
Under no circumstances shall any part of any structure included in the works be loaded in any way until permission to do so has been obtained in writing from the
Engineer’s Representative. .
The Contractor shall arrange his programme of
construction so that the loads of subsequent construction
shall not be imposed upon work already completed until,
in the opinion of the Engineer’s Representative, that work
has developed sufficient strength to withstand safely the
resulting stresses.
No backfilling of earth against or on top of any part of
any structure shall be commenced until the Contractor has
sought and obtained the written permission of the
Engineer’s Representative so to do. This will be given
after the Engineer’s Representative has inspected and
measured the work to be covered and the Contractor has
carried out all repairs, and all other work that the
Engineer’s Representative may require to ensure that the
work complies with this specification. Additionally, no
backfilling shall be undertaken until the requirements of
the preceding paragraph of this clause are satisfied and
the following conditions fulfilled:(i)
No earth shall be backfilled against or on top of a
mass concrete structure until at least 14 days have
elapsed since the pouring of the last concrete,
without the approval of the Engineer’s
Representative.
(ii)
No earth shall be backfilled against or on top of a
reinforced concrete structure until at least 28 days
have elapsed since the pouring of the last concrete
and the results of the 28 days compression cube
tests have been studied and proved acceptable.
(iii)
No earth shall be backfilled against the walls, nor
placed on top of the roof slab, of a reinforced
concrete culvert until at least 28 days have elapsed
since the pouring of the last concrete in the
complete structure, including wing-walls should
these be monolithic with the barrel, and the results
of the 28 days compression cub tests have been
studied and proved acceptable. No earth shall be
placed on to the roof slab unless this is so
specified on the drawings, and then strictly within
the limits shown thereon.
(iv)
Backfilling of all excavations for abutments,
piers, culverts, etc., shall be brought up equally
and simultaneously on all sides to eliminate
unbalanced earth pressures, filling to open-type
abutments shall likewise be brought up equally
and simultaneously around supporting columns,
walls, etc., to eliminate unbalances earth
pressures. All backfill shall be done in layers not
exceeding 150mm compacted thickness, and in
accordance with the requirements of all relevant
clauses of this specification. During backfilling
operations, the Contractor shall take every care to
ensure that no undue loads shall be imposed upon
the structure and he shall furnish the Engineer’s
Representative in advance with full details of his
proposed method of performing the task, showing
that the structure will not be overstressed in any
way.
In no case shall any structure be used for the passage of
constructional traffic, storage of materials, etc., without
the written permission of the Engineer’s Representative,
whose decision in these matters shall be final.
AS-MADE
DRAWINGS
5020.
On completion of the work, and after it has been
approved by the Engineer’s Representative, the Contractor
shall prepare as-made drawings of each bridge, showing
complete, fully dimensioned details of the foundations,
the material on which they are founded, ground levels,
road levels, protection works, superstructure and all other
work carried out under the Contract. The drawings shall
be originals prepared from records taken as the work
progresses and agreed with the Engineer’s Representative,
and shall not be merely amended prints of the contract
drawings.
Draughtsmanship shall be of a high standard, to the
satisfaction of the Engineer’s Representative.
The
drawings shall be by CAD (Computer Aided Design) or
handmade drawing ink, on best quality tracing linen and
shall be 594mm b 841mm overall including a margin of
50mm on the left hand side, and a margin of 10mm on the
other three sides and the title box shall follow the form
shown on the contract drawings. These original tracings
together with one black and white print of each on linen
shall be forwarded to the Engineer for his permanent
retention.
The cost of preparing and supplying all these negatives,
velographs, prints, etc., shall be deemed to be included in
the rates for carrying out the works to which they refer.
SETTLEMENT OF 5021.
BRIDGE AND
APPROACHES
The Contract shall include:
(a) The return to site and carrying out of a survey of
settlement of bridge and approaches at a time just
prior to the completion of the maintenance period
and the submission of a report of the results of
this survey to the Engineer. The cost of this
survey shall be deemed to be included in the
tendered rates and prices.
(b) The carrying out of any jacking operation or
other remedial works deemed necessary by the
Engineer as a result of this settlement to
reestablish the bridge and approaches to the
proper levels. The cost of any such operation
shall be deemed to be included in the tendered
rates and prices.
BEARINGS
5022.
Bearing devices expansion or fixed, shall be constructed
in accordance with the details shown on the drawings and
approved by the Engineer.
Metal bearing shall comply in all respects with the
requirements of B.S. 5400 and as specified on the
drawings.
The masonry plates shall be set level. The expansion
devices shall be set to conform to the temperature at the
time of erection or to the setting specified.
ELASTOMERIC
5023.
When masonry plates are shown on the drawings to be
placed (not embedded) directly on concrete, the concrete
bearing area shall be constructed slightly above grade and
shall be finished by grinding or other approved means to
a true level plane which shall not vary perceptibly from
straight edge placed in any direction across the area. The
finished plane shall not vary more than 3mm from the
elevation shown on the plan.
Elastomeric bearing pads shall conform to the require-
BEARING PADS
ments of B.S. 1154 and the special provisions.
Where elastomeric bearing pads are shown on drawings,
the concrete surfaces on which pads or packing are to be
placed shall be wood float finished to a level plane which
shall not vary more than 1.5mm from a straight edge
placed in any direction across the area and the finished
plane shown on the drawings.
Pads 12mm and less I n thickness may be either laminated
or all elastomer.
Pads over 12mm in thickness shall be laminated.
Laminated pads shall consist of alternate laminations of
elastomers and metal or elastomer and fabric bonded
together.
The outside laminations shall be metal or fabric. The
outside and edges of metal laminations shall be coated
with elastomer not more than 3mm in thickness.
Laminations of elastomer shall be 12mm ±3mm in
thickness. Variation in thickness of an individual
elastomer lamination shall not exceed 3mm within the
width or length of a pad and the variation in thickness of
all elastomer laminations within a pad shall be such that
each metal or fabric lamination will not vary by more
than 3mm from a plane parallel to the top or bottom
surface of the pad.
The total out to out thickness of pad shall not be less than the thickness shown on the
drawings nor more than 6mm greater than that thickness.
Variation of total thickness within an individual pad shall
not exceed 3mm.
The length and width of a pad shall not vary more than
3mm from the dimensions shown on the drawings.
Pads containing metal laminations shall be fully moulded. Pads of all elastomer or with
fabric laminations may be cut from large sheets. Cutting
shall be performed in such a manner as to avoid heating
of the material and to produce a smooth edge with no
tears or other jagged areas and to cause as little damage to
the matter as possible.
Corners and edges of moulded pads may be rounded at
the option of the Contractor. Radius at corners shall not
exceed 9mm and radius of edges shall not exceed 3mm.
The bond between elastomer and metal or fabric shall be such that, when a sample is tested
for separation, failure shall occur within the elastomer and
not between the elastomer and metal or fabric.
Metal laminations shall be rolled mild steel sheets not
less than 1.0mm thick.
Fabric laminations shall be either (1) a long chain synthetic polymer containing at least 85
percent of polyester from ethylene glycol and terephthalic
acid or (2) a long chain synthetic polymeric amide from
hexamethylene diamine and adipic acid. Each play of
fabric shall have a breaking strength of not less than 12.5
N/mm2. Fabric laminations shall be single ply at top and
bottom surfaces of the pad and either double ply or
double strength within the pad.
The sole polymer in the elastomeric compound shall be
neoprene and shall be not less than 60 percent by volume of
the total compound.
The Contractor shall furnish to the Engineer a
certification by the manufacturer that the elastomer, and
fabric (if used) in the elastomeric bearing pads to be
furnished conforms to all of the requirements specified in
the British Standard. The certification shall be supported
by a certified copy of the results of tests performed by the
manufacturer upon samples of the elastomer and fabric to
be used in the pads.
Where elastomeric bearing pads over 12mm in thickness
are shown on the drawings, such pads may be
manufactured as a moulded laminated pad, or at the option
of the Contractor, may be made up by stacking individual
laminated pads. Individual laminated pads used for
stacking shall be normally 12mm in thickness. When
laminated parts are stacked, their contact surfaces shall be
cleaned prior to stacking and a positive method shall be
used to hold the individual parts in the stack in proper
alignment.
The quantity of Elastomeric Bearing pads for which
payment will be made, will be the number of pads
actually constructed and installed as prescribed.
Payment for the Elastomeric Bearings pads shall be made
for the quantities as above determined, at the unit price
shown in the Bill of Quantities, which price shall include
the cost of bearing pads, dowels, hardware, setting, all
material, equipment, labour and all else necessary thereof
and incidental thereto.
(CLAUSES 5024 – 5029 INCLUSIVE NOT USED)
PART (B) – STRUCTURAL STEELWORK
GENERAL:
5030.
MATERIALS AND
WORKMANSHIP
WORKING
DRAWING
All materials and workmanship involved in the fabrication of steelwork shall comply with the requirements
of B.S. 5400together with the additional requirements
and modifications specified hereinafter. All materials and
fittings shall be the best of their respective kinds and free
from defects. Accurate workmanship is essential and all
work shall be neatly finished.
Before any part of the work is put in hand, the Contractor
shall prepare working drawings in accordance with
clause 1010 of this specification.
5031.
The working drawings shall be submitted as mechanically
reproduced prints on medium weight paper showing
either black lines on a white background, or white lines
on a blue background and all costs involved in supplying
them shall be deemed to be included in the rates for
steelwork.
5032.
As soon as possible after the signing of the contract,
the Contractor shall prepare schedules of all parts which
go to make up the work, including bought-out material,
and shall forward a copy, to the Engineer’s
Representative, the duly authorized inspector for
guidance during inspection.
MILD STEEL FOR 5033.
STRUCTURAL
Unless otherwise specified in the contract, structural
steelwork shall comply with the provisions of B.S. 4360
SCHEDULE OF
PARTS
(1990) “Weldable Structural Steels” and shall be of the
grade indicated on the drawings. All sections shall
conform to British Standard dimensions.
MEMBERS, ETC.
ROLLED STEEL
PINS, KNUCKLE
PINS, ROLLERS
5034.
Steel for rolled steel pins, knuckle pins, roller, etc., shall
be of the minimum tensile strength as specified on the
drawings and finished as indicated. (Not rivet steel)
STEEL CASTINGS 5035.
FOR BEARING
Steel casting for bearings shall comply with the requirements for B.S. 3100: and shall be Grade A steel except
where noted on the drawings.
PATTERNS OF
CASTINGS
Patterns of all castings are to be
submitted to the
Inspection Engineer, and shall be approved before
moulding is commenced and the casting are run. Where
this cannot be done on account of their large size the
pattern shall be kept available at the manufacturer’s
works for approval by the Inspection Engineer.
5036.
Each casting shall be legibly marked with a number or
identification mark by which it can be traced to the cast
from which it was made. All castings shall be subject to
tensile and bend tests and wherever possible the test
samples shall be attached to the castings. No casting shall
be repaired or welded without the previous sanction of the
Engineer’s Representative. If permission be given to
effect repair by welding, the Engineer’s Representative
shall decide whether further heat treatment is necessary
and such treatment shall be carried out to his satisfaction.
All surfaces to be machined shall have adequate
allowance left on to enable the castings to be machined to
the plan dimensions but in no case shall the allowances be
less than 3mm. Unless otherwise specified or shown on
the drawings all holes in castings shall be boldly filiated
and free of all faults affecting their strength and value for
the service intended.
GUNMETAL FOR
BEARING
5037.
Gunmetal for girder bearing strips, etc., shall be made
of the following mixture:
Copper 88 per cent, tin 10 per cent, zinc 2 per cent, and
shall show a tensile strength of not less than 215 N/mm2
with 7.5% elongation on 50mm.
FORGINGS
5038.
Forgings shall comply with B.S. 29 and the steel shall
have a minimum tensile strength of 430 N/mm2 or as
indicated on the drawings.
RIVETS
5039.
Steel for high tensile steel rivets shall comply with the
requirements of B.S. 548 “High Tensile Structural Steel
for Bridges, etc., and General Building Construction”,
Amendments CE 52, May 1936; CE 6854 February 1938:
CG 715 June 1942 and current amendments.
Steel for mild steel rivets shall comply with the
requirements of B.S. 15 1948 “Structural Steel”,
Amendment PD 3346, April 1959 or latest edition.
BOLTS
5040.
All bolts must comply with the requirements of B.S. 1083:
1965 (Precision Hexagon Bolts, Screws, Nuts and
Plain Washers), and of B.S. 1969: 1963 (Unified
Precision Hexagon Bolts, Screws, Nuts (Unc and Unf
Threads) and Plain Washers Normal Series), Amendment
PD 5706 November 1968 and PD 6623 or latest edition.
High strength bolts and nuts washers for high strength
bolts shall comply with B.S. 3139 and B.S. 3294, part 1.
All galvanized bolts shall conform with requirements of
B.S. 729, Part 1. Minimum zinc coating shall be 90µm.
HAND-RAILING
AND GUARD
RAILING
5041.
Hand – Railing and Guard -Railing shall be as shown on
the drawings or as directed by the Engineer.
HIGH TENSILE
STEEL FOR
WELDING
5042.
High Tensile Steel to be used for plates and rolled
sections that are specified to be welded must comply
with the requirements of B.S. 4360 with the following
additional requirements.
(A)
The chemical composition shall be as specified in
tables 6, 8, 11, 13 and 16 of B.S. 4360 and upon
request, the supplier shall supply details of the
ladle analysis to the Engineer.
HIGH TENSILE
STEEL: NOT TO
BE WELDED
5043.
(B)
The steel to be used for plates shall be delivered in
a normalized condition.
(C)
The high tensile steel (welded quality) for plates
shall be subjected to the V-Notch Charpy 2
millimetre impact energy test. The average of
three test specimens and the average impact
energy at 0°C shall not be less than 35 joules.
(D)
As a result of the V-Notch Charpy test the
crystalline area in the fractures of the high tensile
steel (welded quality) test pieces shall be
measured. In general the average crystalline area
in the fractures of the test pieces shall not be
greater than 80 per cent of the original area of the
test piece below the notch.
(E)
The high tensile steel (welded quality) for plates
shall be subjected to the Vicker’s test for
hardness. For the hardness control test of the
steel, a single welded bead shall be deposited on
the outer surface on the plate with 4mm diameter
welded electrode, and a cross section of the bead
and the plate shall be cut and etched. The
hardness in the heat-affected zone shall be
measured by the Vickers method and shall not
exceed 350 Vickers.
(F)
The frequency of the tests described in (C), (D)
and (E) above shall be the same as those for tests
for the control of tensile strength, yield point and
elongation as specified in B.S. 4360.
(G)
Should the results of the tests described in (C),
(D) and (E) above not reach the requirements
specified then the steel may be re-normalized and
re-submitted for inspection.
The cost of
renormalizing the steel shall be borne by the
manufacturer.
High Tensile Steel to be used for plates and rolled
sections and welding will not be permitted except where
shown on the drawings.
HIGH TENSILE
STEEL:
MARKING
5044.
All High Tensile Steel shall be marked strictly in
accordance with the requirements of B.S. 4360. All steel
not correctly marked and identified may be rejected by
the Inspection Engineer.
CAST STEEL
5045.
Steel castings are to be true and clean and shall comply as
regards quality and tests with the requirements of B.S.
3100 FOR steel Castings for General Engineering
Purposes, 1967. The casting shall be thoroughly annealed
and stress relieved and tested as per the above for cracks.
They are to be well fettled and dressed where necessary
to remove roughness or inequalities. All holes for bolts
shall be drilled on the drawings to be cored.
CAST IRON
5046.
Cast Iron shall comply with the requirements of B.S.
1452: (1961) for Grey Iron Castings. All holes in cast
iron for bolts shall be drilled unless shown to be cored.
ELECTRODES
5047.
The electrodes to be used for welding steel must be of the
best heavily coated type and of such make as the
Inspection Engineer may approve. They shall be kept in a
dry store in unbroken packets and shall be accompanied
by the Maker’s Certificate of date of manufacture and
guarantee that they fulfil in all respects the requirements
of B.S. 639, B.S. 1856 and B.S. 2642 depending upon the
grade of steel employed in the Contract.
1. Electrodes shall not be used in a damp condition. The
Inspection Engineer shall have access at all times to
inspect the store at the works and may reject
electrodes which he considers unsuitable.
2. The Contractor shall submit to the Inspection Engineer
the name(s), and all relevant particulars of the
electrodes he proposes to use.
3. The Quality and type of the electrodes to be used for
the submerged arc welding of high tensile steel must
be approved by the Inspection Engineer and will
depend on the submerged arc welding process that
will be used.
GREASE FOR
5048.
Grease for bearings shall be such as will ensure adequate
lubrication of the bearings under tropical conditions.
BEARINGS
The following is the approximate analysis of a suitable
grease:high-class viscous mineral oil
78.0 Per cent
pure soap (dry)
5.0 Per cent
best flake graphite
17.0 Per cent
The melting point of the grease shall be not less than
138°C.
The grease shall be packed for shipment in strong airtight
metal drums.
PAINT AND
PAINTING
5049.
All paint used in the works, whether applied in the ship
or in the site shall be the best of its kind and all
ingredients used in its manufacture shall comply with the
appropriate British standards. In any paint system (viz:
primer, undercoats and finishing coats) each coat of paint
shall be compatible one with the other, and to ensure this,
all paint shall be obtained from the same approved
manufacturer with a guarantee of compatibility. The
paints shall be used as specified for the various parts of
the work.
PRIMING PAINT: All priming paint shall be in
accordance with B.S. 2523
UNDERCOAT: Exterior quality aluminium paint tinted
with sufficient blue pigment to
distinguish if from the finishing
coat.
FINISHING COAT: Exterior quality aluminium paint.
PROTECTIVE Where steel is specified to be given one
PAINT: coat of protective paint, such paint
shall be of priming paint, as
specified by the Engineer’s
Representative. Where the paint
has to be applied to a surface
already painted with a bituminous
paint, the protective coat shall be of
bituminous paint of best approved
quality and colour.
The aluminium content of the paint used for undercoat and finishing coat shall comply with B.S. 388 and
shall constitute not less than 20 per cent by weight of the
total paint. The approved volatile matter of the paint shall
not exceed 45 per cent. The paint shall be of the type in
which the aluminium past is mixed with the vehicle
immediately prior to application and the date of the
manufacture shall be marked on each container. Mixing
of the paint and its application to the work shall be strictly
in accordance with the manufacturer’s instructions and
this specification. During painting, the paint shall be
stirred as necessary to keep the pigment in suspension.
Prior to shop painting all surfaces of steelwork shall be
cleaned and de-sealed to bare metal by steel grit or sand
blasting.
Before the application of any paint, the surfaces to be treated shall be thoroughly cleaned and
freed from all scale, loose paint, grease, rust and other
deleterious coatings. Surfaces shall be protected in
accordance with CP 2008. The paint shall not be applied
to any surface which is not thoroughly dry and shall be
applied entirely by hand brush and thoroughly worked
into all crevices, corners and splices and around all bolt
heads, nuts, rivets, etc. Successive coats of paint shall
differ in colour and each coat shall be thoroughly dry
before the next is applied. All paintings shall be carried
out in accordance with the standards laid down in British
Standard Code of Practice C.P. 231 and all testing, where
directed by the Engineer shall comply with B.S. 3900.
Before the application of any paint, the surfaces to be
treated shall be thoroughly cleaned and freed from coatings.
The paint shall not be applied to any surface which is not thoroughly dry and shall be applied
entirely by hand brush and thoroughly worked into all
crevices, corners and splices and around all bolt heads,
nuts, rivets, etc. Successive coats of paint shall differ in
colour and each coat shall be thoroughly dry before the
next is applied. All painting shall be carried out in
accordance with the standards laid down in British
Standard Code of Practice C.P. 231 (1952)
INTERCHANGE - 5050.
Corresponding parts of each unit should be Interchange-
ABILITY OF PARTS
able as far as economic manufacturing conditions permit.
PREPARATION OF 5051.
EDGES AND ENDS
When single universal plates are used with their edges
flush with heels of angles or channels, as in box
girders, end posts, etc., the edges shall be planed. The
edges of universal plates shall also be planed when used
as web plates of riveted plates girders and there are flange
plates. Where two or more universal plates or flats of the
same nominal width are used in tier (excluding covers to
a single plate) the edges shall be machined to make them
straight and flush.
All holes for rivets and black bolts shall be 1.5mm larger
than the nominal diameter of the cold rivet or bolt as
Manufacture and all holes shall be drilled, or drilled small
and reamed. Punching and sub-punching and reaming
shall be permitted only for floor plates and troughing and
only when these do not exceed 12 millimetre in thickness.
HOLES FOR
5052.
BOLTS AND RIVETS
Holes for turned bolts shall first be drilled at least 3.0mm
small in diameter and afterwards when the structure is
assembled, they shall be reamed or drilled to the correct
size through all thicknesses in one operation.
Subpunching will not be permitted.
RIVETS AND
RIVETING
5053.
Rivet heads shall be of standard shape, unless otherwise
specified, and of uniform size for the same diameter of
rivet.
They shall be full, neatly made, concentric with rivet
holes, and in full contract with the surface of the member.
Rivets shall be heated uniformly to “light cherry red
colour” and shall be driven while hot. Any rivet whose
point is heated more than the remainder shall not be
driven. When a rivet is ready for driving, it shall be free
from slag, scale, and other adhering matter. Any rivet,
which is scaled excessively, will be rejected.
All rivets that are loose, burned, badly formed or
otherwise defective shall be removed and replaced with
satisfactory rivets. Any rivet whose head is defective, in
size or whose head is driven off centre will be considered
defective and shall be removed. Where required, rivets
shall be cut for examination by the Engineer’s
Representative and afterwards replaced free of charge.
Stitch rivets that are loosened by driving of adjacent rivets
shall be removed and replaced with satisfactory rivets.
Caulking, re-cupping, or double gunning of rivet heads
will not be permitted.
WASHERS
5054.
WELDING
5055.
All bolts shall be provided with washers, those for turned
bolts being bright finished. Round washers shall not be
less than 6mm thick for turned bolts and not less than
3mm thick for black bolts. Tapered washers of the
correct angle shall be provided under all heads and nuts
bearing on bevelled surfaces and where tapered washers
are required for turned bolts, round washers shall also be
supplied. Tapered washers shall be not less than 5mm
mean thickness. All washers shall comply with the
requirement of B.S. 3410.
No welding of any description will be permitted except
where shown on the drawings.
Unless otherwise described in the Contract, metal-arc
welding shall comply with B.S. 1856 and B.S. 2642 as
appropriate except for tack welds and temporary
attachments for which the procedures laid down in B.S.
2642 shall be followed.
The temperature of steels welded in accordance with B.S.
2642 shall be not less than 10°C when welding is
commenced.
Electrodes and fluxes shall be used in accordance with
the manufacturer’s instructions. The use of welding
processes other than those covered by B.S. 1856 and B.S.
2642 shall be subject to the approval of the Engineer.
The general welding programme for shop and site welds,
including particulars of preparation of fusion faces, the
method of pre-heating where required, the methods of
making the welds and the types of electrodes shall be
submitted to the Engineer for his approval before the
work is put in hand. No departure from the agreed
welding programme or from the details shown on the
drawings shall be made without the agreement of the
Engineer. Electrodes and fluxes shall be so chosen that
the properties of the deposited metal are not inferior to
those of the parent metal.
The position of welds required for temporary attachments
shall be agreed by the Engineer before the work
commences.
Where automatic or semi-automatic processes are used
back gouging of the deposited weld will not b required
where the Engineer is satisfied that the root is free from
imperfection.
The cost of furnishing materials, labour, equipment and
all else necessary thereof and incidental thereto shall be
deemed to be included in the rates for steel work.
JOINTS
5056.
Joints shall not be made in any plate or section or in any
part of the bridgeworks, except where shown on the
drawings. Abutting joint in compression members and
girder flanges and where shown on the plans shall be
faced and brought to an even bearing.
NOTCHING OF
FLANGES AND
WEBS
5057.
When the flanges or webs of any member have to be
cut or notched to enable the section to be trimmed
into another member, a hole of suitable diameter shall
first be drilled through the flange or web so as to leave a
fillet at the intersection of the cut lines.
BENDING AND
PRESSING
5058.
Toughing up to 8mm thick may be pressed cold. Over 8
millimetres and up to 12mm thick cold pressing shall be
subject to the approval of the engineer’s Representative.
SHOP ASSEMBLY 5059.
Members shall not be riveted up until the parts have been
thoroughly scraped, cleaned and freed from all scale and
other deleterious matter. Thereafter, surfaces which will
be in permanent contract after shop assembly shall be
given one coat of priming paint on each face and the parts
drawn firmly together with bolts whilst the paint is still
wet. All rivet holes shall be thoroughly brushed out and
all burrs and exuded paint removed before rivets inserted
and riveting commenced. Surfaces not in contact but
which will be inaccessible after shop assembly shall
receive the full protective painting treatment before
assembly viz one coat of priming paint, one undercoat
and assembly viz: one coat of priming paint, one
undercoat and one finishing coat. All paint and painting
shall be in accordance with requirements of clause 5049
of this specification. All reamering of holes shall be
carried out in the manufacturer’s works and the edges of
all holes on the outside faces of members shall be slightly
arrised.
MACHINING
5060.
ERECTION AT
5061.
MANUFACTURER’S
WORKS AND
MARKING UP FOR
RE-ERECTION
SHOP PAINTING
PROTECTIVE
5062.
The bearing surfaces of bearing plates, etc., shall be
planed level, the cut being made in the direction of
expansion of the girder.
Surfaces, which require
machining, shall be indicated on the drawings.
Before being despatched, all bridge spans shall be temporarily erected complete in the manufacturer’s works
so that the Inspection Engineer can be satisfied as to
both the alignment and fit of all connections.
After the work has been passed by the Inspection
Engineer and before it is dismantled, each part shall be
stamped with the distinguishing mark assigned to it on
the marking drawings, in figures not less than 16mm
high, in such a manner that the pieces may be readily
identified on arrival at site and put together in their
proper positions. The marking shall also be stencilled on
each part in one or more places after it has received the
coat of paint mentioned in Clause 5062 and a circle of
white paint shall be placed round each stamped erection
mark. No marking other than that specified shall be put
on the steelwork.
The drawings showing the markings shall be as set forth
in Clause 5020. The Manufacturer shall forward to the
Engineer one set of hand made tracings on best quality
polyester or tracing linen, one set of mechanical copies
on tracing linen (e.g. velograph) and one set of prints
showing black lines on white background of the marking
drawings. The cost of producing and supplying all these
tracings and prints shall be deemed to be included in the
rates for steel work.
After approval by the Inspection Engineer AND not
before, the whole of the work shall be thoroughly wire
brushed, scraped, cleaned and freed from all scales,
grease and coatings. Areas of rust shall be cleaned down
to the bare metal. The surfaces shall be thoroughly dried
and given one coat of priming paint. All paint and
painting shall be in accordance with requirements of
clause 5049 of this specification. See also clause 5059
for the treatment of surfaces that will be in permanent
contact or inaccessible after shop assembly.
All machined surfaces, turned bolts, nuts and washers,
and all bright surfaces shall be well coated with other
approved coating which will not readily melt when exposed
to the sun in the tropics. Exposed machined surfaces shall
be further protected by timer casings or other approved
means.
COATINGS
Field rivets, black bolts, nuts and washers shall be
thoroughly cleaned, heated to about melting temperature
of lead, and whilst hot, dipped in boiled linseed oil.
GALVANIZING
5063.
Items which are shown on the drawings to be galvanized
shall first be cleaned by pickling and then galvanized by
the hot process. The smelter used in the process shall
comply with B.S. 222 and the manufacturer shall produce
evidence to the satisfaction of the Engineer’s
Representative that this is so, and at his own cost. In
addition, samples of metal from the batch may be taken
by the Inspection Engineer for independent analysis and
if found to contain less than 98.5 percent of pure zinc, the
galvanized parts represented will be rejected. The cost of
this independent analysis will be borne according to
clause 36 (4) of the conditions of contract.
The galvanized surfaces shall be evenly covered, clean
and free from drops or spelter, spots and blemishes of
every kind. After coating, all traces of flux shall be
removed. The coating shall weigh not less than 34 grams
per square metre of surface treated.
All cutting, holding, threading, etc., shall be carried out
before galvanizing. Cutting, holding, threading etc., after
galvanizing will only be permitted where the written
approval of the Inspection Engineer has been first
obtained. Where such permission has been given, the cut
edges shall be protected by an approved proprietary
galvanizing commodity, aluminium paint must not be
used for this purpose.
All materials shall be stored for a period of 7 days after
galvanizing in such a manner that air comes freely in
contact with the surfaces. At the end of this period each
article will be examined by the Inspection Engineer and
those showing signs of acid spot, cracks, blisters or other
defects will be rejected.
At the discretion of the Inspection Engineer the quality
of the galvanizing may be tested by the copper sulphate
test as described in B.S. 729: 1961 and the ductility and
adhesion of the zinc coating tested by bending or
otherwise. For the purpose of these tests more than 1 per
cent of the articles will be selected for testing and the cost
of the tests and replacement of the articles thus destroyed
shall be borne by the Contractor.
DRIFT, SPANNERS 5064.
ETC.
NUMBERS OF SITE 5065.
RIVETS, BOLTS,
NUTS, SERVICE
BOLT, ETC.
Drifts for rivets and bolts shall be supplied to the
extent of one per cent (with a minimum of six for each
size) of the net number of rivets or turned bolts used in
the work. Drifts for use with turned bolts shall be turned
to suit the holes. Spanner, the handles of which shall be
made in the form of a podger and joggled, shall be
supplied in the proportion of 1 in every 500 or less for
each size of bolt and nut. Where necessary, brace
spanners, screw drivers etc., shall also be supplied. The
Contractor shall ensure that an adequate number of all
tools necessary for the proper and efficient erection of the
work at site are provided; the above requirements are
regarded as a minimum.
The full number of rivets, bolts, nuts, washer etc.,
required to complete the work shall be supplied and in
the following spares shall be provided for each span:-
Black bolts, nuts
10 percent of the full
and washers
number of each size required
Turned bolts, nuts
and washers
10 per cent of the full
number of each size required
Foundation bolts
5 per cent of the full number with a
minimum of 2% of each size
required
Rivets
15 per cent of the full number of
each size when the number is 250
or less plus 10 per cent of the
number of each size in excess of
250
Service bolts complete with nuts and washers shall also
be supplied equal to 25 per cent of the net number of site
rivets for all girder work and 10 per cent of the net
number of site rivets for trough and plated floors.
There shall be no reduction in any of the above number
in the case of multiple spans.
The bolt lists including all lengths of rivets to be provided
shall be submitted on acceptable reproduced prints, and
all costs involved in supplying them shall be deemed to
be included in the rates for steelwork.
MEASUREMENT
FOR PAYMENT
OF STEELWORK
5066.
Payment for steelwork shall normally be made on the
computed weight of the structure as determined from
the dimensions given on the drawings, on the basis given
in B.S. 5400. If however the weight of any materials falls
short of the calculated weight by more than 2½ per cent,
but nevertheless be accepted, the actual weight of such
material only shall be paid for. If there is any difficulty in
obtaining the B.S. section specified or shown on the
drawings, the nearest B.S. section may be submitted for
approval. Should the weight of the substituted section
differ from that of the specified section, the weight to be
taken for the purpose of payment shall be the lighter of
the two.
PACKING AND
MARKING FOR
SHIPMENT
5067.
For the purposes of payment and unless otherwise shown
on the drawings, castings, forgings, special alloy steel
wrought iron and all structural shapes and plates for
expansion joints, pier protection, access manholes, steel
deck drains and other miscellaneous steel members, shall
be considered as structural steelwork, except that when
specific items of the above are called for in the Bill of
materials, the weight or unit of measurement of each
selected item as specified therein, will be paid at the
respective contract unit price as named in the bid
schedule.
All works shall be protected from damage in transit,
allowances being made for handling under difficult. conditions Particular care shall be taken to stiffen free ends
and to prevent distortion and to adequately protect all
machine surfaces, the ends of members with turned-bolt
connections etc.
Straight bars and plates, when bundled, shall be
temporarily bolted together. If this is not possible they
shall be bound in at least three places with annealed steel
wire of not less than 6 millimetre diameter which must be
tightly fastened. All rivets, bolts, nuts, washers, screws,
plates and small articles generally shall be packed in bags,
a separate bag being used for each diameter and length of
rivet, bolt, etc., and each bag having a metal label wired
on indicating its contents. The bags shall be packed into
strong wooden cases or casks, whose gross weight shall
not exceed 300 kilograms.
Each case, cask or drum, shall be clearly marked with the
shipping marks and indication of its contents and its
weight. Bundles shall have a metal label, stamped with
similar information, attached to each end, the label being
secure at each of its ends by a separate wire so that the
label lies flat with the bundles.
All marking and labelling shall be carried out to the
satisfaction of the Engineer’s Representative:-.
ERECTION AT
SITE
5068.
The steelwork shall be erected at site in accordance with
B.S.153: with the following amendments and additional
requirements.
All lines and levels shall be as shown on the drawings or
as specified by the Engineer’s Representative. The
Contractor shall be responsible for all setting out and
shall give all necessary assistance and facilities for
checking by the Engineer’s Representative (see clause
1013). Any stakes or marks set out by the Engineer’s
Representative on site shall be carefully preserved.
SITE PAINTING
5069.
In addition to the requirements given under clause 7 of
B.S. 153, the Contractor shall comply with the
requirement of clause 1012 of this specification relating
to drawings and calculations for temporary works and
stagings etc. The Contractor shall obtain the prior
approval from the Engineer for the method of erection
and he shall forward to the Engineer’s Representative
complete details, drawings and calculations for the
proposed method of erection at the time of seeking such
prior approval.
Surfaces which will be in permanent contact after site
assembly or erection shall be thoroughly clean and freed
from all scale, loose paint, grease and other deleterious
coatings. Areas of rust shall be cleaned down to the bare
metal. The surfaces shall be thoroughly dried and one
coat of priming paint applied to each face. The parts
shall then be drawn firmly together whilst the paint is still
wet. All rivet holes shall be brushed out and exuded
paint removed before the rivets are inserted. Similarly
for bolts and bolt holes.
Surfaces which will be inaccessible after site assembly or
erection shall be thoroughly cleaned and freed from all
scale, loose paint, grease and other deleterious coatings.
Areas of rust shall be cleaned down to bare metal. The
surfaces shall be thoroughly dried and then given one
priming coat, one undercoat and one finishing coat of
paint.
Care shall be taken to ensure that no paint shall be
applied to or allowed to foul any reinforcement or other
steelwork which is to be embedded in concrete. In the
case of steel joists which will be so embedded and steel
troughing which will be concrete filled, and all other such
surfaces, those surfaces which will be in contact with the
concrete shall be thoroughly cleaned and freed from all
rust, scale, loose paint, grease and other deleterious
coatings before the concrete is poured against them.
Where concreting or any other operation likely to foul the
steelwork has to be carried out (e.g. pouring of concrete
deck slabs supported on R.S.Is), preparation and painting
of surfaces shall not be undertaken until such time as the
cause of likely fouling or damage no longer exists.
All paint and painting shall be in accordance with clause
5049 of this specification.
ADDITIONAL
5070.
STEELWORK IN
THE
STRENGTHENING
OF EXISTING BRIDGES
Before embanking on the strengthening of the bridge,
the Contractor shall forward to the Engineer’s Representative for approval full details of the method he proposes to employ to carry out the work.
Such details shall be accompanied by drawings and
calculations showing that no part of the existing structure
shall be overstressed or likely to suffer any damage
during the strengthening operations and to ensure that this
will be so, the Contractor shall provide temporary
supports, bracing, struts, etc., as necessary. In no case
shall any part of an existing bridge be removed to
facilitate strengthening until a temporary substitute has
been fixed in place to the complete satisfaction of the
Engineer’s Representative. The Contractor shall amend
his proposals for undertaking the strengthening of the
bridge as required by the Engineer’s Representative and
shall not commence the work until the Engineer’s
Representative has given his approval to the scheme and
his permission to proceed.
Before ordering the additional steelwork the Contractor shall completely satisfy himself in all
respect as to the dimension and positions of all fastenings
and members of the existing structure and shall be
responsible for ensuring that all new plates, joists, etc.,
required for the strengthening shall avoid or accurately
pick up all such existing fastenings and members as the
case may require. The Contractor shall also check
existing spans as indicated on the drawings to ensure that
the lengths of new joists etc., are adequate for the work
proposed and before ordering any such material shall
inform the Engineer’s Representative of the dimensions,
weights, etc., which he proposes to obtain and obtain his
approval therefore. Any indications of the sizes or
positions of any part of any existing structure as are
shown on the drawings are of a general nature only and
the Contractor must on no account regard such
indications as accurate. The Contractor shall be deemed
to have inspected each and every structure and to have
taken all necessary information and measurements
required for the proper carrying out of the work, and to
have allowed for such in his rates.
The additional steelwork shall be manufactured, fabricated, protected, transported, fixed in
position and be in all respects in accordance with
requirements of this specification and the drawings. All
fabrication which can be done in the shop shall be done
there and only the absolutely necessary minimum, as
approved by the Engineer, shall be done at the site, where
the additional steelwork comes into permanent contact
with the existing steelwork, the contact surfaces of both
shall be thoroughly scraped and cleaned and freed from
all loose paint, scale, grease and other deleterious
coatings. Areas of rust shall be cleaned down to the bare
metal. The contact surfaces shall then be given one coat
of priming paint and brought together and fastened whilst
the paint is still wet. Surfaces of both existing and
additional steelwork which will be inaccessible after
strengthening measures are complete shall be prepared as
described above and given the full protective paint
treatment viz:- one priming coat, one undercoat and one
finishing coat, before assembly is begun. Where site
welding is to be employed, paint and other coatings shall
be removed from the areas to be welded for a suitable
extra distance to ensure that the quality of the welds will
not be impaired. When strengthening is complete, the
surfaces of all added steelwork, and those of the existing
steelwork that have been damages during the operation
shall be prepared as above and given one coat of priming
paint, one undercoat and one finishing coat. All paint and
painting shall be in accordance with the requirements of
clause 5049 of this specification.
The cost of fulfilling all the requirement of this clause
shall be deemed to be covered by the rates for supplying,
fixing and painting additional steelwork.
RE-USE OF 5071.
GIRDERS, JOIST
ETC. OBTAINED
FROM DISMANTLED
STRUCTURES
Girders, joists, etc., from a dismantled structure which
are to bere-used in the strengthening or reconstruction
of another structure are thus indicated on the drawings.
The Contractor shall check the dimensions of such
girders, joists, etc., has been completed , and before they
are incorporated into the structure, they shall be
submitted to the Engineer’s Representative for approval
and when this has been obtained and not before, the
Contractor shall forthwith incorporate them into the
works as directed on the drawings.
The Contractor shall ensure that during fabrication,
assembly and subsequent incorporation into the works,
the girders, joists, etc., are given the paint treatment
specified in clause 5069.
GROUTING OF
BASE PLATES,
ETC., OF
BEARINGS
5072.
The base plate etc. shall first be located accurately with
respect to both line and level, by careful tapping,
levering, wedging, etc., as approved by the Engineer’s
Representative. Care shall be taken to ensure that the
damage is done to any item, especially machined
surfaces. Immediately before the operation of grouting
in, the entire area covered by the bearing, including
pockets for holding down bolts, and a sufficient extra area
around to prevent contamination, shall be thoroughly
cleaned by washing with water from hose pipes,
compressed air, etc., and all dust, loose and deleterious
matter shall be removed. All surplus matter shall then be
dried off by mopping and the use of compressed air and
the surfaces left damp. Freshly mixed mortar, as directed
and of suitable consistency shall then be introduced to fill
the pockets for the holding down bolts, and the space
beneath the bearing plates. The mortar shall be well
pounded into the space, working from one side with
suitable pounders until the mortar appears on the opposite
side and every care should be taken to ensure that the
mortar appears on the opposite side and every care shall
be taken to ensure that the entire void is filled, giving
complete support to the bearing over the entire area,
without air holes, etc. To ensure this, wooden screed
shall be introduced around the edges of the grouting space
to contain the mortar during the pounding operations.
Any mortar that may foul the threads of bolts, nuts or
affect their bearing on washers and plates shall be
carefully removed without disturbing the mortar already
placed, and on completion of the operation, the edges of
the mortar shall be trimmed as shown on the drawings.
The whole shall then be covered with wet sacks or
hessian which shall be kept continuously damp for a
period of not less than 7 days, after which they shall be
removed and all loose, adherent or projecting mortar
liable to reduce the efficiency of the bearings carefully
removed. After 28 days all holding down and other bolts
shall be tightened as directed.
EXPANSION
JOINT
5073.
Expansion joints shall be provided where shown on
the drawings and be of the type specified.
Detailed working drawings shall be submitted to the
Engineer for approval.
The drawings shall be supplement by the materials
specifications not covered in the GENERAL
SPECIFICATION OF THE FEDERAL MINISTRY OF
WORKS or specified on the drawings.
Expansion joint scalant as shown on the drawings shall be
produced from neoprene compound and conform with the
requirements of ASTM Specifications D2628-67T, (SEE
clause 6269). Expansion joint sealant shall be placed in
correct position. When nosing type construction will be
used, the expandite expoform or equal epoxy resin special
mortar shall be used for forming the joint nosing for joint
sealant. The epoxy shall comply with DOE requirements
for nosing materials contained in Technical
Memorandum (Bridges) BE3/72. The expansion joint
sealant, shall conform to the following:
Density:
1350 kg/m3
Hardness:
50 to 60, Shore A
Tensile strength:
13.8 N/mm2 (minimum)
Elongation at break: 250% (minimum)
The size of the gap shall be compatible with the mean bridge temperature at the time of
installation. This temperature shall be determined in
accordance with arrangements agreed with the Engineers.
The position of all bolts cast into concrete and holes
drilled in plates shall be accurately determined from
templates.
The mixing, application and curing of all proprietary
materials
shall comply
manufacturers requirements.
with
the
During the placing and hardening of concrete or mortar under expansion joint components,
relative movement shall be prevented between them and
the supports to which they are being fixed.
When one half of the joint is being set, the other half shall be completely free from
longitudinal restraint. In particular where strongbacks or
templates are used to locate the two sides of a joint, they
shall not be fixed simultaneously to both sides.
Screw threads shall be kept clean and free from rust.
Ramps shall be provided and maintained to protect all
expansion joints from vehicular loading. Vehicles shall
cross the joints only by means of the ramps until the
Engineer permits their removal.
(CLAUSES 5074 – 5099 INCLUSIVE NOT USED)
.
SPECIFICATION
SECTION VI
ROADWORKS
SECTION VI
ROADWORKS
GENERAL
6000.
In addition to any other relevant clause of this
Specification, the following shall be deemed to apply in
particular to road works, and shall be read in conjunction
with all other relevant Clauses of the Conditions of
Contract and this Specification.
PART A - DESIGN AND CONSTRUCTION
STANDARDS
HORIZONTAL
6001.
For new road, the horizontal alignment must be carefully
ALIGNMENT
chosen, as this is cost related.
A good alignment shall
provide good drainage, minimum
and
balanced
earthworks and must provide good drainage, minimum
and balanced earthworks and must avoid swampy and
high water table areas, where this is possible. A good
horizontal alignment allows straight portions of the road
on the horizontal plane to be connected with horizontal
curves, which may be circular or transitional.
For the rehabilitation of roads in general, the proposed
new alignment shall follow closely on that of the existing
road, except where necessary to effect realignment to
conform with the current standards of the Federal
Ministry of Works and Housing or to effect the most
economical sitting of new bridges. It shall consist of a
series of straights joined by circular curves.
All
gradients, vertical and horizontal curves, sight and
passing distances, rate of super-elevations, etc., shall
conform with the accepted standards of the Ministry for
the particular terrain and adopted design speed as
follows:
TERRAIN
LEVEL
ROLLING
HILLY
80
60
ADOPTED
DESIGN
SPEED, KM/H 100
HORIZONTAL
ELEVATION
CURVES
AND SUPER-
Radii of horizontal curves and super-elevation rates shall
comply with the following formula:E = V2/2.25R
Where V = design speed in km/h
R = radius of circular curve in metre
E = super-elevation, this is normally limited to an
absolute maximum of 8%
DEFINITIONS:(I)
TANGENT RUN-OFF
That distance in which the level of the outer edge
of the pavement is brought to the level of the
crown of the road section.
(II)
SUPER-ELEVATION RUN-OFF
That distance in which the super-elevation is
brought from zero to its maximum value.
Super-elevation shall be achieved by rotating the
pavement about the profile of the inside edge of the
pavement in flat terrain where the drainage of the inside
edge of the curve is likely to present a problem.
In cases where the inside edge of the curve may be easily
drained, then the super-elevation shall be achieved by the
rotation of the pavement about the centre-line profile.
The sequence of operations is as follows:(a)
The outer half of the pavement width is brought to
the same horizontal plane with the crown of the
cross section. This is done within the distance
called the tangent run-off.
(b)
The outer half of the pavement is then brought to
the same inclined plane as the inner halæ of the
pavement.
(c)
(i) For rotation about the inner edge, the
pavementshall then be finally rotated about its
inner edge to the required full super-elevation.
No cut is involved along the inner edge in this
operation.
(ii) For the rotation about the centre-line, the
pavement shall be rotated about its
centreline to the required full superelevation. This operation involves “cut”
along the inner edge of the pavement.
TABLE VI – DESIGN SPEED WITH
CORRESPONDING SUPER-ELEVATION AND
MINIMUM LENGTH SUPER-ELEVATION RUNOFF
DESIGN SPEED KM/II
MAXIMUM GRADIENT
OF SUPER-ELEVATION
RUN
OFF RELATIVE TO
CENTRE-LINE OF
ROAD (PERCENT)
MINIMUM LENGTH OF
SUPER-ELEVATION
RUN-OFF (METRE)
MAXIMUM RATE OF
CHANGE OF
SUPERELEVATION
RUN-OFF
LENGTH OF SUPERELEVATION RUN-OFF
WITHIN THE CURVE
(CIRCULAR)
100
80
60
0.45
0.5
0.57
55
45
40
0.05 m/m PER
30 METRE
20%
The proposed Road shall
be
constructed
in
accordance with the
horizontal
alignment,
formations and levels
and other details as in the
DRAWINGS
or
as
directed
by
the
Engineer’s
Representative.
VERTICAL
6002. The straight portions on
the vertical plane that are
connected by vertical curves
ALIGNMENT
are
called
gradients.
Two
cases of vertical curves occur with gradients either
meeting at summits or meeting at sags. The choice of
gradient will affect construction costs, vehicle operation
cost, road capacity and passenger’s comfort. With these
considerations, the vertical alignment shall conform with
adopted standards of the Ministry. The finished work
shall be to even gradients joined by vertical curves. The
lengths of vertical curves shall be calculated using the
formula:L = K (G1-G2) = KA
Where L = length of vertical curve in metre, recommended
minimum value of 100m for all speeds.
A = (G1-G2) = change in gradient (algebraic difference)
percent. The ultimate sign of A should be ignored, i.e. A
is always positive.
K = constant for any particular speed
TABLE VI-2 - DESIGN SPEED FOR VERTICAL
SUMMIT OF CURVES WITH CORRESPONDING
K VALUES
DESIGN
SPEED
KM/H
K
SUMMIT
VERTICAL
CURVE
SAG VERTICAL
CURVE
100
80
60
100
80
60
50
26
12
35
23
13
The level of any point along the vertical curve shall be
equal to the level at the tangent point plus
G1X/100 + AX2/200L
where
X
G1
= distance of the point from the tangent point in
metres
= gradient of the road section (per cent)
A
= change in gradient (algebraic difference)
i.e. (G1-G2) per cent.
L
= length of the vertical curve in metres
AX 2
should be positive for a sag vertical curve and
200L negative for a summit vertical curve.
ROLL-OVER
6003.
Roll-over is the algebraic difference in cross-falls of two
adjacent lanes of pavement area. The Roll-Over shall be
in accordance with the details as shown on the
DRAWINGS or as directed by the Engineer’s
Representative.
CONTRACTOR
TO CALCULATE
LEVELS
6004.
The Contractor will be responsible for working out all
levels of the pavement, shoulders, ditches, etc., that are
necessary for the setting out of the works and will, if
required to do so, furnish the Engineer’s Representative
with lists of these levels for his approval prior to
settingout. The Contractor shall locate and preserve
where directed all concrete land markers, beacons,
benchmarks, etc.
CONSTRUCTION
STANDARD
6005.
The roads shall be constructed to the following
standards(I)
WIDTH
The formation width between drains comprising a
carriageway, hard-shoulders and soft shoulders shall be
constructed to the dimensions shown on the drawings or
as ordered by the Engineer.
(II)
BASE-COURSE
(III)
The base course of the carriageway, which may be
continued over the hard shoulders or extended a minimum
of 300mm at either side of the surfaced width as shown on
the drawings or as directed by the Engineer shall be
constructed of approved material having a finished
compacted thickness of not less than 150mm and
complying in all respects with this specification. The base
course to the hard shoulders if different from that of the
carriageway, shall be constructed of such other approved
material as directed by the Engineer’s Representative, but
also having a finished compacted thickness of not less
than 150mm.
SUB-BASE COURSE
The Sub-base Course of the carriageway, which may be
continuous over the hard shoulders as shown on the
drawings or as directed by the Engineer’s
Representative, shall be constructed of approved material
having a finished compacted thickness as shown on the
drawings, or as directed by the Engineer depending on the
C.B.R. value of the sub-base in question.
(IV)
GEOMETRY
(V)
The horizontal and vertical alignments, super-elevations
and cambers of the road shall be constructed in
accordance with the DRAWINGS or as directed by the
Engineer.
BITUMINOUS SURFACING
The surfacing of the roadway shall be two-coat
bituminous surface dressing or asphaltic concrete
pavement as shown on the DRAWINGS or as directed by
the Engineer.
(VI)
SIDE SLOPES TO EMBANKMENTS
Side slopes to embankments and cuttings shall be
constructed in accordance with the drawings or directed
by the Engineer’s Representative. The co-efficient of
resistance of the material shall be the determinant factor
for the embankment slope.
(VII) SIDE DRAINS
Unless shown otherwise on the drawings, the invert of the
side drains shall be not less than 900mm below the
finished level of the crown of the road. All side drains
shall, where shown, be excavated to the profile and
dimensions shown on the drawings, but the Engineer’s
Representative may direct that the side drains be
constructed to such lesser profiles consistent with
drainage capacity as he may think fit due to the existence
of rock or other obstruction. Where the height of the
embankment exceeds 900mm above the existing ground
and the natural gradient of the surrounding area is
towards the roadway, then catch-water drains shall be
constructed as shown on the drawings or as directed by
the Engineer’s Representative.
(VIII) CULVERTS
Generally, culverts shall consist of pre-cast concrete pipes
laid either as single or multiple culverts, and where
shown shall be bedded and haunched with a minimum of
150mm of concrete. In cases where sufficient cover is
not available the Engineer’s Representative may direct
that culverts be surrounded with a minimum of 150mm of
concrete.
(IX)
JUNCTION WITH ROADS
(X)
A.
Minor Roads
At all junctions with minor roads where shown on
the DRAWINGS or directed by the Engineer’s
Representative, bell mouth shall be constructed
carrying the construction and drainage to a
minimum of 15.0 metres from the edge of the
proposed roadway along the minor road as shown
in details on the DRAWINGS or as directed by the
Engineer’s Representative.
B.
Major Roads
At junctions with major road culverts shall be
constructed as shown on the DRAWINGS or as
ordered by the Engineer’s Representative.
WIDENING OF ROADWAY THROUGH VILLAGES
AND AT RECOGNIZED LORRY HALTS
Where the roadway passes through villages and at
recognized lorry halts, the base course and the asphalt
concrete pavement shall be widened. Concrete side
drains shall be constructed, all as shown on the
DRAWINGS or as directed by the Engineer’s
Representative.
(XI)
HARD SHOULDERS
Surface dressed hard shoulders shall be constructed on
both sides of the roadway as shown on the DRAWINGS
or as directed by the Engineer’s Representative.
(XII) SOFT SHOULDERS AND EMBANKMENT SLOPES
Soft shoulders and embankment slopes shall be
constructed so as to have the top 75mm consisting of
topsoil and shall be grassed throughout unless otherwise
directed.
At the discretion of the Engineer’s
Representative, the top 75mm may consist of a
compacted layer of approved lateritic material in lieu of
top soil.
(XIII) SUB-GRADE
A.
Cuts
The sub-grade of the road shall be shaped to the
dimensions, formations and levels as shown on
the drawing or as directed by the Engineer’s
Representative and the top 150mm sub-grade
shall be watered and compacted to 100% B.S.
standard compaction at optimum moisture
content (OMC)
B.
Embankments
The sub-grade of the road shall be shaped to the
dimensions, formations and levels as shown on the
DRAWINGS or as directed by the Engineer’s
Representative.
(CLAUSES 6006 – 6009 INCLUSIVE NOT USED)
PART (B) – EARTHWORKS, DRAINAGE ETC.
(1)
MATERIAL
GENERAL 6100. The materials used in the works shall be new and/or of the qualities and
kinds specified, and no materials will be used in the
works unless approved. Materials delivered to the works
shall be equal to the approved samples. Deliveries shall
be made sufficiently in advance of constructional
requirements to enable samples to be selected by the
Engineer’s Representative for testing before using the
materials in the works.
Materials failing to comply with the specification shall be immediately removed from the
works at the
Contractor’s expense.
These specifications on materials shall be read in conjunction with latest amended report of
the “the Lagos materials testing conference”, a copy of
which will be made available to the Contractor on
request.
No material shall be used until it has been approved by the Engineer or his Representative.
Permission to use any material shall not be construed as
an approval of its source nor any acceptance as continued
acceptance.
UNSUITABLE
MATERIAL
6101.
In no case will material, which contains organic matter or
other deleterious substance be used.
FILLING
6102.
Material for filling in the embankment shall be obtained
from sources approved by the Engineer’s Representative
and no slurry, mud, soft or otherwise unsuitable materials
shall on no account or under any circumstances be placed
in embankments. Large pieces of rock, or other materials
shall be properly broken up and beaten down and no
accumulation at the foot of side slopes of embankments
of boulders or lumps having no cohesion will under any
circumstances be permitted. The Engineer’s decision
regarding the suitability of any material shall be final and
any material of which more than 35% passes the No
75µm sieve may be rejected depending on the plasticity
characteristics of this material, provided good quality fill
materials are available, otherwise such material may be
modified for use.
The material to be used for the forming of embankments
shall generally be obtained from cuttings, which may be
widened as agreed with the Engineer’s Representative.
The material shall be spread evenly over the area of
embankment and compacted in uniform layers to the
specified density and moisture using B.S. compactive
effort. Each compacted layer shall not be greater tan
150mm.
SELECTED
6013.
LATERITIC
MATERIAL FOR
SOFT SHOULDERS
Where directed by the Engineer’s Representative under
the provisions of clause 6163 the material selected for
the upper 75mm of the soft shoulder shall or preferably
be a well graded lateritic soil with a Plasticity Index of not
less than 10 and not more than 20.
GRASS OR 6104.
GRASS SEED
The seed, or the grass used for sowing or planting
on the verges, the slopes of embankments and cuttings
shall be daub grass (cynoon dactylion) or bahama grass.
Tall, quick-growing or tussock grasses shall not be used
without the consent of the Engineer. The Contractor must
anticipate the requirements for the supply of suitable
grass.
RUBBLE AND
6105.
Stones for tilling behind retaining walls or walls of
culverts
shall be angular and graded from 12mm to 75mm with a
fine content below 12mm not exceeding 20% stones, for
pitching the inverts and sides of ditches embankment
sloes and culvert inlets, and outlets, shall be of durable
natural broken rock of approximate cubical shape 225mm
x 225mm x 225mm or 150mm x 150mm x
150mm as appropriate.
PITCHING STONES
(CLAUSES 6106 – 6119 INCLUSIVE NOT USED)
(II)
SITE CLEARANCE 6120.
WORKMANSHIP
The Contractor shall fell, grub-out roots and clear from
the site all trees occurring within the boundary of the
works as directed. In additional bushes, ant hills, ants’
nests, grass, stumps and other vegetation shall be cleared
from the site and roots, grubbed up, holes made in
grubbing up, removing the ant hills, roots, stumps and the
like shall be backfilled and compacted to a density at lest
equal to that of the surrounding ground except that all
holes, cavities, and wells within the road width shall be
backfilled with approved soil which shall be thoroughly
compacted throughout by power rammer to a density not
less than the dry density of the surrounding ground.
Outside the above limits, on the inside of bends, bushes
and trees shall be felled and their roots grubbed up as
directed to give an unobstructed sight distance of 150
metres. For purposes of measurement, the girths of the
trees shall be taken 900mm above ground level except
that where a tree has a buttress the girth shall be taken
immediately above the buttresses.
No economic trees or crops shall be removed prior to
their enumeration and valuation for compensation
purposes.
The Contractor shall remove gates, gateposts, manhole
covers, kerbs, signs, water mains and other items to the
extent directed by the Engineer’s Representative.
Foundations shall be broken up and removed to a depth of
900mm below natural sub-grade level or finished grade
level, whichever is lower.
Structures to be demolished shall be broken up and
removed. Prior to demolition the Contractor shall ensure
that services have been disconnected to the satisfaction of
the appropriate authorities and/or owners. Foundations
shall be broken up and removed to a depth of 900mm below
Natural Sub-grade Level or finished grade level, whichever
is lower.
Pits, tanks, underground chambers and the like shall be demolished to a depth of 900mm
below Natural Subgrade Level or finished grade level,
whichever is lower and the remainder shall be properly
cleaned out.
Clearing limits for this Contract shall be the entire length
of the project within widths as herein below defined.
I.
Buildings, walls and other man-made items
Clear everything within the Right-of-Way limits
II.
Compound walls - reconstruction
Any and all existing compound walls located
within the Right-of-Way limits shall be cleared
and removed as part of the appropriate item in the
Bill of Quantities. Also included as part of this
item shall be the reconstruction of all such walls,
equal to the removed wall, along the Right-ofWay
line connecting to the points at the start and end of
the removed section.
The cost of such
reconstruction shall be considered included in this
item. Reconstruction of compound walls may be
required anywhere along the alignment.
Wells
Working wells outside the limit of grading shall
be maintained in a condition equal to their present
condition.
III.
Working wells within the limits of grading shall
be filled as hereinabove required. Replacement
wells equal to the existing wells shall be
constructed outside the limits of grading.
The cost of all replacement wells shall be
considered as included in Item “Clear Site as
specified… etc.”
Non-working wells within the Right-of-Way lines
shall be filled as hereinbefore required.
IV. Trees and All Other Erosion Resisting Vegetation All
trees shall be cleared within a strip fifty (50)
metres wide, (25 metres to each side of the centre
line). To ensure that future falling trees do not
clog road side drains, all trees outside this 50
metre strip whose height is such that, if they fell
would reach to the nearest roadside drain, shall be
cleared.
All other erosion resisting vegetation shall be
cleared only within the limits of grading.
Outside the above limits and within the RightofWay lines all vegetation shall be selectively
thinned and/or trimmed.
A. Selective thinning shall include the removal of
live and dead trees both standing and fallen,
shrubs, and other vegetation and debris in the
areas shown on the Drawings and designated
for removal by the Engineer.
The trees, shrubs and other vegetation to be
removed will be so designated by the
Engineer’s Representative. Trees shall be
carefully felled to prevent damage to adjacent
vegetation, structures and property. Trees,
stumps and all debris shall be removed in a
manner that will not compact or disturb the
soil adjacent to trees and shrubs to remain.
B. Trimming existing trees shall include the
complete removal of all defective or
undesirable limbs and the repair of all injuries
or wounds on existing trees as directed by the
Engineer’s Representative.
All diseased, broken and seriously injured
branches shall be removed. Healthy low
branches shall not be removed except as
otherwise directed by the Engineer’s
Representative.
All wounds over 25mm
diameter shall be painted with tree paint. The
bark around all wounds and other injuries
shall be traced and treated in accordance with
approved arboricultural practice and shall be
subject to the approval of the Engineer.
All trees to remain within the area designated
for selective thinning shall be trimmed to
remove all dead and undesirable limbs up to a
height of 5m above ground. The Engineer
will determine which live limbs are
undesirable.
Materials designed for incorporation in the Works shall
be removed, marked where necessary for future
identification and stored for re-use.
The Contractor shall load, transport, unload and stock
materials designated for delivery to the owner’s thereof.
Other materials resulting from clearing operations shall
become the property of the Contractor as soon as he takes
possession of the land for the Works. The Contractor
shall remove and dispose of such materials.
Clear material shall be burnt or disposed of as directed by
the Engineer’s Representative. Trees to be cut down shall
have all light branches trimmed off and burned and useful
trimmer shall be cut in suitable lengths and stacked at the
roadside ready for removal as directed by the Engineer’s
Representative.
Payment will be made under this for the net areas cleared
and shall include for the satisfactory removal of anthills
and ants’ nests and for any backfilling and compacting
required and for disposal of material, but shall not include
any areas of grass on the road vergers or otherwise, which
is subjected to periodic cutting and maintenance.
SCARIFYING
EXISTING
SURFACE
6121.
Unless otherwise directed by the Engineer’s Representative, the existing road shall be scarified, shaped to required formation level, and compacted as specified,
where the average difference between the proposed
formation levels and the existing ground levels does not
exceed 75mm. Payment shall be made once only under
the appropriate item in the Bills of Quantities and shall
include for all operations required to bring the existing
road to the required formation levels.
Where
ordered
in
writing
by
the
Engineer’s
Representative, existing bituminous surfaces shall be
scarified, re-shaped and compacted, as specified and all
surplus material shall be disposed of as directed by the
Engineer’s Representative. Payment shall be made under
the appropriate item, in the Bill of Quantities and shall
include for all operations as required herein.
Except as provided above, the removal of existing
bituminous surfacing by scarifying and roughening of
existing unsealed roads and vergers, etc., shall be deemed
to be included in the tendered rtes and prices for
earthworks.
EARTHWORKS
6122.
In the Contract the following words and expressions shall
have the meanings hereby assigned to them, except where
the context otherwise requires:(1) “Existing Ground Level” means the ground level
shown on the drawings as existing at the start of the
Works.
(2) “Finished Ground Level” means the ground level after
the completion of the Works.
(3) “Natural Sub-grade Level” means the level at the
completion of excavation for road works.
(4) “Formation Level” means the level at the completion
of earthworks for road works prior to topsoiling.
(5) “Stripped Ground Levels” means the ground levels
after the completion of clearing operations.
(6) “Specified Finished Excavation Levels” means the
levels of the completed excavation after trimming,
compacting and preparation of the surface of the
excavation as calculated from the levels shown on the
Drawings, or the levels directed by the Engineer’s
Representative.
(7) “Specified Finished Fill” means the levels of fills
after trimming, compacting and preparation of the
surface of the fill (excluding top soiling) placed in
accordance with the Drawings or as directed by the
Engineer’s Representative.
Excavated material shall be classified by the Engineer’s
Representative as suitable material, or unsuitable
material.
Unsuitable material shall include the following:(1) Material from swamps, marshes and bogs.
(2) Peat, logs, stumps, roots and other perishable or
combustible material
(3) Topsoil and highly organic clay and silt.
(4) Clay having a liquid limit exceeding 80% or plasticity
index exceeding 55.
(5) Highly micaceous materials.
Suitable material shall exclude the foregoing unsuitable
materials and shall comprise all other natural material
acceptable for use in the Works, whether obtained from
within or without the Site.
Topsoil shall mean soil which can be seen to have been
broken down by agricultural cultivation and/or is seen to
be capable of supporting vegetable growth. It shall
include turf.
Solid rock shall mean rock found in ledges or masses in
its original position, which can only be loosened by
blasting or by pneumatic tools, or excavated by hand by
using wedges and sledgehammers. Rock, which is in a
shattered condition and/or is capable of being loosened by
rippers or earthmoving plant, is excluded from the
definition of solid rock. Boulders or detached pieces of
rock each exceeding 2 cubic meter sizes in trenches or 6
cubic meter size in general excavation, shall be regarded
as solid rock.
Where embankments are to be constructed on steeply
sloping ground, including the side slopes of existing
embankments, existing sloping surfaces shall be
excavated to form benching as shown on the Drawings or
as directed by the Engineer’s Representative.
Materials for filling shall comprise the following;(1) General Fill
General fill shall consist of suitable material as defined
herein. Subject to the requirements regarding the
forming of embankments isolated boulders not
exceeding 3 cubic metres in size may be included in
general fill.
(2) Rock Fill
Rock fill shall consist of sound igneous rock or other
sound rock acceptable to the Engineer’s
Representative or such strength that when compacted
an excess of fines will not be produced. It shall be
free draining and reasonably well graded and shall
have a maximum size of 3 cubic metres. The
percentage of material by weight passing a 5mm sieve
shall not exceed 30%. It shall be free from silt, clay
and organic material. Such material may be deposited
below water without the associated use of compaction
plant.
(3) Granular Fill
Granular fill shall consist of an approved granular
material of maximum size not greater than 38mm,
which is inert in water and which on analysis by
sieving, complies with the following requirements.
Sieve Size
10mm
Percentage by Weight Passing
up to
100
5 mm
not more than
85
600µm
not more than
45
75µm
not more than
5
(4) Special Granular Fill
Special granular fill shall be hard and durable and
shall consist of broken rock or gravel. It shall be well
graded with a maximum size of 38mm. The
percentage of material by weight passing 75µm sieve
shall not exceed 10. It shall be free from silt, clay and
organic material.
(5) Granular Bedding
Granular bedding shall consist of crushed rock or
gravel having a smooth grading curve within the
limits specified for 19mm nominal size all in
aggregate to Table 3 of B.S. 882. The fraction
passing the 425µm sieve shall be non-plastic when
tested in accordance with B.S. 1377 (1975) Sections
2, 3 and 4 unless such fraction constitutes less than 2
per cent of the whole by weight.
Earthworks shall be measured by super-imposing the
specified finished formation levels on initial cross
sections taken by the Contractor at 30 meter intervals or
closer if necessary along the centre line. The levels of
such cross sections shall be agreed by the Engineer’s
Representative.
PAYMENT FOR
EARTHWORKS
6123.
A maximum quantity of material excavated from cuttings
shall be placed to fill and the utmost advantage shall be
taken to the natural moisture content of the soil in placing
such fill provided the materials meet the qualities for use
as such see clause 6102. Fill shall be placed and
compacted in layers of a compacted thickness 150mm or
such thickness that may be found necessary to achieve the
required density over the full width of the formation. The
Contractor shall route his earth-moving equipment in such
a manner over the full width of the filling as to achieve a
uniform compaction over the entire width by this method.
All fill including sub-grade and vergers shall then be
compacted to 100 per cent of the maximum dry density
obtained in the British Standard Compaction Test. In the
case of extension to existing embankments benching will
be required as indicated on the drawings or as directed by
the Engineer’s Representative and such bending shall be
deemed to be included in the tendered rates for
earthworks.
Payment for earthworks shall be made once on the basis
of the total quantity of measured fill by the Contractors
together with the quantity of unsuitable material and/or
of excess cut placed to spoil, all as determined from the
cross sections referred to in clause 6122. The depth of
unsuitable material, if any, to be placed to spoil shall be
agreed between the Contractor’s Agent and the
Engineer’s Representative. Payment for this material will
be on the net volume as measured in situ.
The quantity of suitable excess cut placed to spoil shall be
determined as follows:(i) The net volume of suitable material excavated from
cuttings or side drains shall be determined by
deducting the quantity of unsuitable material
placed to spoil from the total quantity of cut as
determined from the cross-sections.
(ii)
The total volume of filling placed in embankment
shall be found from the cross-sections.
(iii)
The volume of suitable excess cut placed to spoil
shall be taken as the volume found in (i) above
less the volume found in (ii) above with an
adjustment made to the latter to allow for
compaction.
The adjustment which shall be made for compaction shall
be based on the ratio of the maximum dry density of the
filling at 100% B.S. compaction to the in situ dry density
of the material in the cutting or side drain.
Haulage rates will be assessed on the basis of the use of
the nearest acceptable road making materials to the
section of work under construction.
Stripping of topsoil will not be measured as roadway
excavation. The quantity of stripping topsoil for which
payment will be made will be the area stripped in
accordance with the Drawings or as directed by the
Engineer, measured in units as specified in the bill of
quantities.
SELECTION OF
SOIL FOR FILL
6124.
Soils shall be obtained from areas of cut including
ditching or from approved borrow pits.
All grass and
vegetation shall be removed from the surface of the areas
of cut or borrow pits before excavation of the fill material
is commenced and no such grass or vegetation shall be
included in the fill. In borrow pits the topsoil shall be
carefully removed and stockpiled.
Topsoil shall not be removed from any area until
excavations or filling operations are about to start in that
area. Topsoil on the sites of cuttings and embankments
shall be excavated to the average depth directed by the
Engineer’s Representative or as specified hereinafter.
The Contractor shall, at his own expense and to suit his
own convenience, make arrangements for and provide
such temporary storage sites as may be required for heaps
of topsoil.
If any materials suitable for sub-base, base or aggregates
as specified herein are encountered in material removed
as roadway excavation, and the Contractor elects to use
such material for constructing items, payment for the
various items shall be as follows:
If the contractor elects to use materials removed from
cuttings for constructing items of sub-base, base or
aggregates, payment will be made for such material
excavated under the appropriate roadway excavation item
and for such material so placed under the appropriate item
of sub-base or base, provided that the Contractor
furnishes and places borrow excavation material, in
embankment without cost, in an amount equal to the
value of the material used in the base, subbase or as
aggregate in place prior to excavation.
The Contractor shall at his own expense, make
arrangements for a provide such spoil dumps as may be
required for the disposal of excavated materials which are
not to be incorporated in the Works.
The spoil dumps shall be located and shaped in
accordance with the Contractor’s proposals as and shall
be finished with neatly trimmed slopes, adequately
surface soiled, all to the satisfaction of the Engineer’s
Representative.
During the course of the excavation from an area of cut or
borrow pit or other approved source of fill material, the
Contractor shall provide adequate supervision to ensure
that only soil of a type approved by the Engineer’s
Representative is excavated. Care shall be taken during
such excavations to avoid any pockets of heavy clay,
vegetation or other unsuitable material and if any such
unsuitable material or soil of an unapproved type is
included in the fill it shall be dug out and made good with
approved material where directed by the Engineer’s
Representative and at the Contractor’s own expense.
Where a sandy soil is encountered in the excavation of a
cut or borrow pit, the Engineer’s Representative shall
have the power to instruct the Contractors to place this
sandy soil to the top layer of fill.
Any material, which in the opinion of the Engineer’s
Representative is not suitable for fill, shall be tipped to
spoil as and where directed.
After removal of fill material from borrow pits, etc., the
area shall be levelled and topsoil replaced all to the
satisfaction of the Engineer’s Representative.
The Contractors shall arrange and pay for any
compensations and other payments whatsoever required
for their access to and occupation and use of the borrow
areas for fill material.
Payment for all arrangements, compensations and other
costs, clearance, removal and replacement of topsoil,
excavations and disposal of unsuitable materials and all
other operations and requirements of this clause shall be
deemed to be included in the tendered rates and prices for
earthworks.
COMPACTION
6125.
Compaction shall be measured by expressing the dry
density of the sample as a percentage of the maximum
dry density at optimum moisture content.
Compaction of all material shall be carried out at a
moisture content optimum for the compaction effort of
the plant used. The Engineer’s Representative may,
however, direct that the moisture content at compaction
be further controlled in order to reduce as far as possible
any subsequent consolidation or swelling.
Where it is necessary to add water to the material to
achieve the dry density specified, the cost of obtaining,
transporting or pumping, spraying and mixing sufficient
water must be allowed in the Contractor’s prices for
compaction. Water shall be added as and where
necessary by a water carrier fitted with an approved
sprinkler and the uniform wetting of the layer to be
compacted shall be achieved. Under no circumstances
will compaction solely by construction or other traffic be
adopted.
Fill materials shall be placed, spread and levelled in
layers of loose depth not exceeding 230mm of general
fill, 460mm of rock fill, 230mm of special and granular
fill. Notwithstanding the foregoing, where rock fill or
granular fill is placed below water level there shall be no
restriction on the depth of layers.
The material of each layer, of whatever type, shall be uniform throughout the layer. Except
as otherwise necessary to conform to the zoning of the
various types of materials, each layer of material shall
extend over the full width of the filling. No layer of fill
material shall be placed until the Engineer’s
Representative is satisfied that the underlying layer is
properly compacted.
Rock fill (including solid rock ……………. cuttings) shall be placed, spread and levelled by
a track-laying tractor and large voids shall be filled with
broken fragments before compaction.
Isolated boulders and isolated large fragments of solid rock forming part of general fill shall
be evenly distributed throughout each layer, but no stone
exceeding 150mm in size shall be placed within 300mm
of formation level.
During the construction of embankments the Contractor shall control and direct construction
traffic uniformly over the full width. Unless permitted by
the Engineer’s Representative, fill materials shall not be
stockpiled on embankments.
Embankments shall be constructed in such a manner that the completed formation is not
damaged by construction traffic. The Contractor may
elect to construct embankments to such higher levels as
may be necessary to protect the formation and in such
cases shall delay removal of the surplus material until
preparation of the formation can immediately proceed.
The provision, placing, compaction and subsequent
removal and disposal of such material shall be at the
Contractor’s expense.
All road materials shall be incorporated in the works by an approved sequence of operations
namely the dumping of materials, spreading by grader,
watering and mixing as specified above and compacting
by approved means. The Contractor shall keep the delays
between consecutive operations to a minimum.
All compaction equipment must operate over the whole area to ensure uniform compaction
by it. All filling including the sub-base course and base
course shall be compacted in layers of a compacted
thickness of 150mm or such other thickness as may be
found necessary to
achieve the required density. Longitudinal and transverse
joints in any two successive layers shall be staggered to a
minimum distance of 3 metres.
At the beginning of the Works and from time to time as may be necessary in the opinion of
the Engineer’s Representative, the Contractor shall carry
out, to the satisfaction of the Engineer’s Representative,
field trials, supplemented by any necessary laboratory
investigations to determine types of compaction
equipment, suitable layer thickness and moisture contents
all within the requirements of the specification for the
placing and compaction of the various materials to be
used in the earthworks. The sites of trials shall be agreed
between
the
Contractor
and
the
Engineer’s
Representative. If compaction trial fill is placed as part of
the permanent work, such fill shall conform to the
requirements of the specification and if it does not it shall
be removed or reworked until it does conform. Extra
work required either to rework or remove the trial section
shall be at the Contractor’s expense.
The Contractor shall submit to the Engineer’s
Representative his proposals, based on the rolling test
result’s for the compaction of each variety of material to
be used in the earthworks, including proposals in relation
to types of plant, numbers of passes and loose depth of
layers. Work (other than rolling test) shall not start on
any particular variety of material until the Engineer’s
Representative has signified in writing his agreement to
the Contractor’s proposals for that material.
The Contractor shall not modify the agreed methods
without the consent of the Engineer’s Representative.
Work in compaction of fill materials shall be carried out only when the moisture content is
within the range shown by the field or by laboratory tests
whichever is appropriate on that material to be suitable
for the attainment of the densities specified below.
(i)
(ii)
For material which is within 600mm Formation
Level or in the filling adjacent to structures
(including backfilling), not less than 100 percent
of the maximum dry density for the material
obtainable by B.S. standard compaction.
For all other material, not less than 95 percent of
the maximum dry density for the material
obtainable by B.S. standard compaction.
The foregoing compaction requirements shall also apply
to the sub-grade material, which is within 600mm of
formation level in cuttings.
The Contractor and the Engineer’s Representative shall
from time to time agree upon field compaction methods
and relevant plant for the various materials such that by
correlation using the relative density and ISO CBR
control tests, the need for the extensive tests on the
finished road section may be reduced.
The Contractor and the Engineer’s Representative shall
also agree on procedures for determining the areas of fill
to which particular sets of test results should be deemed
to be applicable. Such areas shall include clay or peat
deposit where consolidation test may be necessary.
All sections of the works shall be protected from damage
by plants, rainstorms or other cause. All such damage
should it occur, shall be made good by the Contractor at
his own expense.
In particular the exposed surface of each lift of fill or subbase course or base course material, after compaction,
shall be protected by a cambered surface from excessive
moisture content changes due to rainstorms until the next
lift is placed. If such changes in moisture content do take
place and the surface of the compacted layer softens, the
contractor shall, if required by the Engineer’s
Representative, remove and replace the material affected
at his own expense. Should the material used for subbase or base course be prone to drying from the surface
the Contractor shall from time to time keep the finished
surface slightly dampened. This process will continue
until another layer is placed.
Should there be patches of unsound ground, excessive
sand or clay, which are, in the opinion of the Engineer’s
Representative unsatisfactory, then such areas shall be
rectified by admixture of suitable materials or by cutting
out and replacement to ensure a uniformly compacted
formation.
Tests for the control of compaction shall be carried out at
regular intervals as directed by the Engineer’s
Representative. If any test result from a particular area
falls below the minimum specified, then the Contractor
shall at his own expense scarify, water and re-compact
that area to the satisfaction of the Engineer’s
Representative, provided the constituency of the material
will not be adversely affected as double compaction may
increase percentage passing 75µm sieve to more than
35% thus reducing the strength of the material.
The Contractor shall allow in his construction programme
time for such tests and for the results to be made known,
before the next stage of the works.
BORROW PITS
6126.
The Contractor shall at his own expense clear bush,
topsoil and other inferior materials from the site of borrow
pits.
The Contractor shall also bear the cost of
compensation for borrow pits outside the area of the site.
Borrow pits for road materials shall be excavated only
where the natural slope of the ground is away from the
road, except that where he considers it essential for the
proper execution of the works the Engineer’s
Representative may approve the excavation of borrow pits
in ground above road level.
Generally in rural areas the nearest edge of the pit shall be
not less than 15 metres from the centre-line of the road.
The Contractor shall so plan his method of execution of
the works that the haul of road materials from borrow pits
is reduced to a minimum. The Contractor may be
allowed to form “side-borrowtrenches” for fill material
wherever it is required providing such trenches are self
draining, having a minimum fall along the line of the road
of 1 in 120. All other pits shall be properly drained to the
satisfaction of the Engineer’s Representative by the
construction of turnouts or other approved methods.
In built-up areas, the Contractor shall submit to the
Engineer, his proposals for obtaining fill materials and
shall furnish details regarding the locations, sizes and
owner of all borrow areas, together with his proposed
method of working and all measures proposed to
eliminate damage or nuisance to persons or property. He
shall be required to submit his proposed method for the
reinstating such borrow areas at the same time. The
Contractor shall obtain the Engineer’s written approval
for the above before commencing work on any borrow
area. In addition the Contractor shall comply with all
other relevant clauses of the conditions of contract and
this specification.
No borrow pit shall be abandoned until the area has been levelled, top soil replaced and the
sides battered to a slope of 1 in 1½ so that no animals
may be trapped, all to the satisfaction of the Engineer’s
Representative. The cost of all operations detailed under
this clause shall be deemed to be included in the tendered
rate for earthworks.
Regulations under the mineral ordinance must be
observed by the Contractor.
SAND FILL 6127. Where sand fill, either hydraulic or otherwise, is specified, it shall be
obtained from a source or sources approved by the
Engineer. Where such sources occur in waters or areas
under the jurisdiction of the Nigerian ports Authority or
the inland waterway department of the Federal Ministry
of Transport or other appropriate authority, then the
Contractor shall first obtain written permission to remove
material from the authority concerned and shall comply,
in all respects with all regulations laid down by such an
authority.
The quality of the material intended for use as sand fill shall be subject to the approval of the
Engineer. For hydraulic sand fill, the grading of the
material shall be such that not more than 15% passes the
75µm sieve, and in no case will isolated pockets or layers
of silt, clay or other organic impurities be accepted.
The relative density of hydraulics sand fill placed in
embankment shall be as follows:
(A)
Top 600mm
90%
(B)
Next 600 mm
(C)
Below the Top 1200 mm
80%
70%
Sand fill placed by any method other than the hydraulic shall be compacted in layers by a
method approved by the Engineer’s Representative to a
density of not less than 100% of the maximum dry
density obtained in the
British Standard Compaction Test. Vibrative system of
compaction is recommended.
In the case of hydraulic sand fill the Contractor shall construct all drains, ditches, spillways,
marginal bunds necessary for the proper protection of the
works. Such drains, marginal bunds, etc., shall be
constructed sufficiently in advance of the deposit of the
sand fill, so as to effectively drain and retain the sand fill
and to prevent any of the material from flowing into any
harbours, creeks, canals, drains, etc., or from causing any
damage or nuisance to persons or property. The
Contractor shall be responsible for any slip or settlements
that may occur during the construction of the sand fill or
the bunds, drains, etc., and shall also be responsible for
same during the maintenance period. The Contractor
shall make good such slips and settlements to the
satisfaction of the Engineer’s Representative.
The
Contractor shall be responsible for the full and efficient
drainage of water resulting from the hydraulic sand fill
operation and shall construct such open drains as may be
necessary to drain all surface and rainwater, so as to avoid
all ponding. The Contractor shall make due allowance
for settlement and drying-out of the sand-fill and for the
making good of same.
Before any hydraulic sand fill is commenced, the
Contractor shall, in conjunction with the Engineer’s
Representative, survey the site and mutually agree the
surface levels, and such agreement shall be recorded in
writing by both parties. The levels shall be taken on a
grid with points at not exceeding 15 metre centres and the
Contractor shall construct concrete pilot-pillars to the
Satisfaction of the Engineer’s Representative to enable
the grid lines to be located during the filling operations.
The Contactor shall construct sufficient telltales,
consisting of 50mm x 50mmx10mm angle of adequate
length with a flange of 900mm in diameter fixed at one
end, all in non-corrosive metal, to the satisfaction of the
Engineer’s Representative, to enable any subsidence of
the original ground level to be measured. The method of
measurement of hydraulic sand fill shall be on the basis
of the volume of material placed as determined from the
area filled and the depth of fill to the finished level from
the original ground level or the subsided original ground
level, as applicable. Should any dispute arise as to the
subsided original ground level, as indicated by the
telltales, then the same shall be determined by the taking
of borings or by the digging of trial-pits. Payment for
trial pits shall be from the appropriate item, in the bills of
quantities. Where no such item is included, payment will
be from appropriate provisional sum. If option of trial pit
is chosen shutting shall be provided to check the collapse
tendencies of sand fill.
Hydraulic sand fill shall be deposited in layers as directed
by the Engineer, but in any case the thickness of such
layers shall not exceed the limits stipulated as follows:(A)
First Layer – not exceeding 450mm in thickness
(B)
Second Layer – not exceeding 750mm in thickness
(C)
All subsequent Layers – not exceeding 900mm in
thickness
The finished level shall be as shown on the drawings or as
directed by the Engineer, and shall be agreed as the result
of a joint survey carried out by the Contractor and the
Engineer’s Representative. A tolerance of 75mm above
or below the finished level may be permitted during
pumping operations, but the same shall be made good by
subsequent grading or dozing to the satisfaction of the
Engineer’s Representative and to the tolerances stipulated
for the sub-grade. Without limiting his commitments
under the terms of the contract, the Contractor shall not
be required to make good any normal expected settlement
of the original ground levels after completion of the sand
fill. The Contractor shall be deemed to have allowed for
all the foregoing provisions in his rates and prices for
sand filling. Should the Engineer so desire the Contractor
shall place stockpiles of material in quantities and areas
as directed. Payment for these stockpiles shall be made at
the tendered rates and prices for hydraulic sand fill.
EXCAVATION TO 6128.
BE KEPT FREE
FROM WATER
The Contractors shall keep all excavations free from
water and shall at their own expense construct such
temporary grips and ditches and provide and maintain
pumps as may be found necessary for this purpose.
Excavation free from water may be possible if
underground design formation level is not close to the
water level.
SLIPS
During the carrying out of excavations, the Contractors
shall limit vertical and other temporary faces to such
heights as are suitable to the nature of the soil exposed If
in the course of the works, any slips, slides, or subsidence
occur and such slips, slides or subsidence extend beyond
the lines and slopes and below the levels shown on the
drawings, the excess excavation will not be paid for and
the Contractors shall at their own expenses carry away
such materials and make good in a manner satisfactory to
the Engineer’s Representative and without extra charge.
6129.
UNSUITABLE
6130.
MATERIAL
BELOW FORMATION
LEVEL
Where unsuitable ground or other unsuitable material is
found below formation level or below the slope of cuttings under areas of fill, this shall be excavated and disposed of as directed by the Engineer’s Representative,
and the space left void shall be backfilled with selected
fill and compacted to at least 100% of the M.D.D.
achieved in the British Standard compaction test.
Payment shall be made under this clause for any material
removed as unsuitable soil only on the written direction
of the Engineer’s Representative provided such
unsuitable material could not have been discovered
during the tendering period.
Measurement for this item shall be on the compacted
backfill only and payment for this work will be at the
rates entered in the bill of quantities for earthworks.
SWAMP AREAS
6131.
Certain existing swampy areas on the proposed line of
reconstruction may have been delineated on the drawings.
The attention of the Contractor is particularly drawn to
the fact that, under the provisions of this specification, he
is responsible for the safe passing of traffic in such areas
and that the cost of any diversions which may be required
for this purpose are deemed to be included in the tendered
rates and prices.
The Contractor shall programme and execute his
earthmoving operations such as to complete the
embankments in swamp areas prior to initiating work or
other embankments and to allow minimum settlement
periods as specified in volume III, or as agreed by the
first, raising the embankments to the specified finished
surface level in the area or such other level as may be
required and the start of the construction of any part of
the pavements, drainage or other permanent works in the
area.
Prior to, during and subsequent to the settlement periods specified above the Engineer’s
Representative will carry out investigations in filled
sections of swamp areas to collect information on which
to base predictions of the magnitude and rate of
settlement which will occur after completion of the
works. Such investigations will be undertaken, to
ascertain, inter alia, the strength, compressibility of
ground beneath embankment, ground water levels and
vertical settlements and they will be made by means of
various measuring devices. The results of such tests shall
be used by the Engineer’s Representative to predict the
equitable surcharge to facilitate early maximum
settlement.
The measuring devices shall be supplied and installed by
the Contractor using methods approved by the Engineer.
They shall be read by the Engineer’s Representative. The
Contractor shall supply such skilled and unskilled
assistance as the Engineer may direct.
The Contractor shall take all practicable precautions to prevent damage or disturbance to
measuring devices. Should any damage or disturbance
occur the Contractor shall make good same at his own
expense to the satisfaction of the Engineer.
The Contractor shall be deemed to have allowed for any reduction in the efficiency of his
operation and for any delays or stoppages caused thereto
by the installation, testing and reading of the various
measuring devices and the avoidance of damage or
disturbance thereto.
As a result of the investigations described above, the
Engineer may direct the Contractor to take measures to
reduce or to compensate for settlements that will occur in
filled sections of swamp areas after completion of the
Works. Such measures shall consist of:
(i)
(ii)
the surcharging of filled areas so as to accelerate
the consolidation of foundation materials and/or
providing settlement allowances in the finished
levels of the pavements, drainage and other
permanent works constructed in the filled sections
of swamp areas.
If so ordered by the Engineer, the Contractor shall
construct surcharge loads of fill in such locations and to
such dimensions and levels as the Engineer directs. The
Contractor shall re-schedule his filling operations in other
parts of the Site to compensate for the fill materials so
diverted and to provide for the incorporation in the works
of fill material made available on subsequent removal of
the surcharge loads.
Except as provided hereunder, surcharge loads shall
remain in position for such periods as the Engineer
directs, after which the Contractor shall remove the
surcharge loads, incorporate the fill material in the works
and make good to the satisfaction of the Engineer’s
Representative the area on which the surcharge load was
formed; provided that in no case will the Engineer direct
that surcharge load in any area should be left in position
for a period extending beyond the end of the settlement
allowed for that area in accordance with Volume III.
The Contractor shall incorporate such settlement
allowances as the Engineer considers necessary in the
finished levels of the pavement, drainage works and other
permanent works in filled sections of swamp areas.
Settlement allowances shall be provided by the addition
or removal of fill material and not by varying the
dimensions of pavements, drainage works or other
permanent works.
The Contractor shall be deemed to have allowed for any
reduction in the efficiency of his operations and for any
delays, stoppages or inconveniences caused thereto
(directly or indirectly) by the operation of this Clause.
The Contractor will be required to lay a satisfactory
running surface of gravel or other approved material on
the completed earthworks. Further construction shall not
be permitted until all settlement has effectively ceased to
the satisfaction of the Engineer.
Before further
construction continues the road formation shall be made
up to the specified levels. The extent of such areas shall
be defined by the Engineer’s Representative before
construction starts, and the measurement of earthworks
within the area declared by the Engineer’s
Representative to be a settlement area shall be the net
cubic contents of the voids formed by the removal of the
material excavated in accordance with the specification
and drawings, no allowance being made for bulking. The
rates entered in the Bill of Quantities under the various
items for excavation shall include for the excavation of
material and the loading, transport, deposition and
compaction as specified, as shown on the drawings or as
directed by the Engineer’s Representative.
6132.
The Formation level shall be the level of the embankment or cutting in its final shape, after completion of the
Earthworks and before the superimposition of the subbase
course, base course, or hard shoulder and before the
surface material is applied.
PREPARATION OF 6133.
FORMATION
All earthworks shall be graded to provide the required
formation profile. The Contractor may elect to leave
sufficient material above formation level to protect the
formation and to delay the excavation of this material until
preparation of the formation can follow immediately. The
subsequent removal and disposal of such material shall be
at the Contractor’s expense. Cuttings other than those in
rock shall not be excavated to formation level in wet
weather. If suitable material below formation level is
damaged by any cause such material shall be removed and
replaced by properly compacted general fill and such
operations shall be at the expense of the Contractor.
FORMATION
LEVEL
Not less than 150 metres of completed sub-grade shall be
maintained in advance of the paving operations at all
times. Failure to comply with the provisions of this
paragraph will be deemed sufficient cause for stopping
the paving operations until this provision is met.
During the preparation of the formation, suitable motor
graders shall be used and shall be operated by highly
experienced operators. Payment for work done under this
clause will be deemed to be included in the tendered rates
for earthworks.
TRIMMING OF
SLOPES
6134.
All slopes of cuttings and embankments shall be trimmed
to the batters specified by the Engineer’s Representative
with a permissible tolerance of plus or minus 50mm
measured at right angles to the batter. Payment shall be
deemed to be included in the tendered rates for earthwork.
EXCAVATION
IN ROCK
6135.
When solid rock is encountered in excavations, the Contractor shall excavate and dispose of such material as
directed by the Engineer’s Representative. The Contractor
shall not use explosives for excavations in rock without
the prior written approval of the Engineer. Where such
approval is given, the Contractor shall provide proper
magazines in suitable positions for the storage of
explosives and take all necessary precautions to prevent
any unauthorized issue or improper use of any explosives,
to the satisfaction of the Engineer’s Representative. The
Contractor shall comply with any regulations regarding
the times for blasting, sizes of blasts, loading of shots,
provision of blasting nets, etc., that the Engineer’s
Representative may prescribe.
Blasting may be prohibited if, in the opinion of the
Engineer’s Representative, it will be dangerous to persons
or property or to any finished or existing work.
“Solid Rock” shall mean any material having a volume
greater than 0.30 cubic metres that, in the opinion of the
Engineer’s Representative, can only be removed by the
use of sledgehammers and wedges (if removed by hand)
or explosives and pneumatic tools (if removed
mechanically). Soft or decomposed material or boulders
in excess of 0.30 cubic metres which can be removed by
dozing, pushing, rooting, ripping, scarifying or by the use
of other normal earth-moving plant shall not be classified
as “Solid Rock”.
Payment will be per cubic metre of “Solid Rock”
excavated and disposed of as directed by the Engineer’s
Representative. Should any difference of opinion arise
between
the
Contractor
and
the
Engineer’s Representative the matter shall be
referred to the Engineer, whose decision shall be final and
shall be obtained before the material is disposed of or
covered up. If the Contractor is still not satisfied, the
matter may be referred to an Arbitrator.
Any material having a volume of less than 0.30 cubic
metres or material which, in the opinion of the Engineer’s
Representative, can be removed by dozing, pushing,
rooting, ripping, scarifying or by the use of other normal
earthmoving plan shall be classified as earthworks, and
the cost of such operations shall be deemed to be included
in the tendered rates and prices for earthworks.
BACKFILLING
OF EXISTING
PITS
6136.
Existing borrow pits adjacent to the roadway shall be
backfilled as and where directed by the Engineer’s Representative.
Such areas shall be backfilled with approved soil which
shall be thoroughly compacted throughout by power
rammers or other approved methods, to a density not
greater than in situ density of the soil to promote
vegetation growth as obtained in the British Standard
Compaction Test.
Measurement for this item shall be on the compacted
backfill only, based on initial and final levels, and
payment under the relevant items of the bill of quantities,
shall include for benching and providing, placing,
watering and compacting the material to the required
density as specified herein.
EMBANKMENT
6137.
The Contractor shall bring to the notice of the Engineer’s
IN BAD GROUND
BACKFILLING
6138.
Representative cases where embankments are required to
be sited over swamp or unstable ground. Where such
conditions exist the Engineer’s Representative may direct
that the first lift of fill material before compaction can be
increased to 450 mm in order to establish firm ground for
the compacting plant. This may not be done without the
written approval of the Engineer’s Representative and
even if such approval is given, the Contractor is not
relieved of his responsibility to provide a well compacted
stable embankment of the same standard as the rest of the
works.
No backfilling shall be carried out until the Engineer’s
Representative has inspected and passed the culverts and
other structures, which will be covered up.
The excavation containing culverts will be backfilled in
layers not exceeding 150mm thickness with materials
approved by the Engineer’s Representative.
When existing pipes and conduits have insufficient earth
cover during embankment construction, the Contractor
shall protect them against damage by his equipment and
operations. The embankment above and for a distance of
not less than 600mm each side of such facilities shall be
compacted by such means as the contractor may choose
so as to prevent damage to such facilities. The Contractor
shall repair or make good any damage to such facilities
that may be caused by his operations.
Embankments constructed in the vicinity of bridges and
culverts prior to the completion of abutments and wing
walls shall terminate temporarily on slopes 5:1 or flatter
which shall be located so as to allow ample space for
construction of the structure and for placing and
compacting the backfill and remaining embankment
adjacent hereto. Embankment around and adjacent to
abutments,
culverts
and
piers shall be
placed simultaneously on both sides thereof to
approximately the same elevation.
GRASSING OF
EMBANKMENTS
CUTTINGS,
VERGES, ETC.
6139.
Any space over the culverts and between the sides of the
culvert and the walls of the excavations shall be filled
with selected material in a damp state approximating to
its optimum moisture content. The material shall be
thoroughly compacted by hand or power rammers to not
less than the dry density specified in Clause 6125. The
cost of all backfilling as specified herein shall be deemed
to be included in the tendered rates and prices.
On completion of the verges, margins, embankments,
etc., or at such other times as may be approved for the
purpose of planting, all areas specified to be grassed
shall be sown with broad-cast seed or individual planting
at 225mm.
The Contractor shall be responsible for watering and
maintenance and for ensuring that the grass takes root,
spreads and forms a thick mat.
Except where otherwise directed, the Contractor shall
keep grassed areas mowed or cut until the
commencement of the period of maintenance. The grass
shall be cut three times during the growing season, or as
often as it may be necessary.
The condition of grassed areas will be assessed by the
Engineer’s Representative immediately after the third
cutting. Areas, which have not become established to his
satisfaction for any reason whatsoever shall be made
good to the satisfaction of the Engineer’s Representative.
ROADSIDE
DRAINAGE
DITCHING
6140.
Roadside drainage ditches shall be constructed to the
lines, grades and levels shown on the drawings or as
directed by the Engineer’s Representative. Where
ditches collect surface water along their length and if he
considers it necessary, the side at which the water enters
the ditch shall be protected by constructing a bund and by
allowing the water to enter the ditch only at specific
points through the bund.
Where the gradient of the road is flatter than 1 in 120 the
ditch shall be deepened to provide an adequate drainage
slope. All ditches with a gradient steeper than 1 in 120
shall be paved in the invert with small stones embedded
in the bottom of the ditch and for a height of 150mm up
the sides. Pitching with small stones if ordered by the
Engineer’s Representative shall be paid for separately.
Payment for roadside drainage ditches is covered under
earthworks and shall include for all timing, shaping and
bunding required.
Spoil excavated from drains shall, where suitable, be
incorporated in the filling, and the quantity so used shall
be deducted from the quantity of fill. No spoil shall be
placed within 2 metres of the drain.
Use shall be made of suitable roadside ditches at the
discretion of the Engineer’s Representative.
CONCRETE
DRAINS
6141.
SUB-SOIL DRAINS 6142.
Concrete drains shall be constructed to the lines and
levels shown on the drawings, or as directed by the
Engineer’s Representative and shall comply in all
respects with the requirements stipulated for mass and
reinforced concrete. The grade of concrete and quantity
and size of reinforcement to be used shall be as shown on
the drawings or as directed by the Engineer. The invert
of drains shall be trowelled to a smooth finish and the
inside face of walls shall be left with a fair finish as
obtained from wrot shuttering.
Where possible, spoil excavated for the construction of
the drains, if suitable, shall be incorporated in the filling
and payment will be made, once only, under the
appropriate item for earthworks in the Bill of Quantities.
Otherwise, the material excavated shall be disposed of as
directed by the Engineer’s Representative, and paid for
under the appropriate item in the Bill of Quantities.
All water appearing on the formation as surface water
held in depressions and potholes and sub-soil water which
in any way affects the stability of the formation or
pavement shall be carried to the side drains in rubble or
stone filled drains, to the approval of the Engineer’s
Representative.
Graded stone filling shall be hard and durable and shall
consist of broken rock or gravel. It shall be well graded
with a maximum size of 75mm and the percentage
passing a 38mm sieve shall not exceed 5%. Graded stone
filling shall be placed inlayers not exceeding 225mm
loose depth and shall be well rammed as filling proceeds.
Stone filled drains on side slopes shall be constructed
prior to any surface soiling and grassing.
Pipes for sub-soil drains shall be mainly slotted flexible
PVC pipes or perforated concrete pipes with ogee joints
or perforated corrugated metal pipes. They shall be laid
with dry joints. The pipe trenches shall be filled with
graded stone filling which shall be carefully placed and
packed in layers not exceeding 225mm in loose depth.
Stone filled pipe drains on side slopes and margins shall
be constructed prior to any surface soiling and grassing.
Payment for work done under this clause shall be at the
rate entered in the Bill of Quantities.
CONSTRUCTION
IN PERCHED
WATER AREA
6142A.
A sure way of avoiding drainage problems of perched or
spring water is to carry out a proper soil survey of the
area concerned and modify or re-adjust either the vertical
or horizontal alignment or (both) to make the formation
level far away as much as possible from the perched
water table or underground springs. If circumstances
make this impossible, the following procedure may be
useful:
Once the formation has been prepared water should be
pumped out of the section to allow perforated pipes to be
laid across the section in close proximity to enable water
flow into it and get channelled out of the roadway.
Thereafter the pipes are to be covered with specially
selected granular materials which will serve as weep
holes over and above the perched water level, before
approved fill is laid and compacted to not less than 95%
MDD at a xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
???
(Taper-foot) roller up to a depth of 600mm below
formation level, thereafter 100% compaction at OMC of
compactive effort will apply. Compaction depth shall not
be greater than 150mm per layer.
In the alternative waterproof material of uniform
thickness (gauge) polythene sheets may be used to wrap
the fill placed after the application of the weep pipes and
selected fill to prevent ingress of water into the pavement.
This method may be necessary particularly if the crown
of the road is within one metre from the level of the
perched water table.
CUT-OFF
DITCHING
6143.
Cut-off ditching, metre drains turn-outs and culvert, outfalls including bunding as and where required by the
Engineer’s Representative shall be constructed where
shown on the drawings or as directed by the Engineer’s
Representative and will be paid for under the appropriate
items of the bill of quantities. Payment shall include for
all trimming, shaping and bunding.
EXCAVATION
FOR CULVERTS
6144.
Excavation for drainage works shall be carried out to the
lines, levels and depths shown on the drawings or as
directed by the Engineer’s Representative and in such a
manner that the stability of the sides and bottom of the
excavation is ensured. Excavation shall be kept from
water until, in the opinion of the Engineer’s
Representative, concrete or other works therein are
sufficiently set and any filling has been completed.
Trenches shall be excavated through natural ground, or,
where pipe culvert structures are to be placed under
embankment, the Contractor shall, unless otherwise
directed, complete the construction of the embankment to
a minimum elevation of 300mm above the elevation of
the top of pipe. The pipe trench shall then be excavated
and the pipe placed in the trench. The width of trenches
at any point below the top of the pipe shall not be greater
than the outside diameter of the pipe at the bell or bank
plus 900mm to permit satisfactory jointing and thorough
tamping of the bedding material under the pipe. Sheeting
and bracing, where required, shall be placed within the
trench width as specified. Care shall be taken not to over
excavate. Where trench widths are exceeded, redesign
with a resultant increase in cost of stronger pipe or special
installation procedures will be necessary. Cost of this
redesign and increased cost of pipe or installation shall be
borne by the Contractor.
The width of trench for structural concrete pipe culverts shall not exceed the widths shown
on the Drawings or as specified above, and these widths
shall be maintained to a height of at least 300mm above
the top of the barrels of the pipes.
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
?????
to a height of at least 300mm above the top of the barrels
of the pipes.
Where directed by the Engineer’s Representative soft material below the required levels of
excavation shall be removed and filled to the required
level with compacted granular bedding material or
concrete grade 15N/mm2.
Where excavation is taken out to a greater depth than is necessary or there is over-excavation
at the sides of the trench, the Contractor shall fill in the
excess excavation at his own expense with 10N/mm2
concrete or with compacted granular bedding as directed
by the Engineer’s Representative.
Rock encountered in trenches for pipes shall be excavated to the depths shown on the
Drawings. Where no depths are shown it shall be
excavated to a depth 150mm below the intended level of
the bottom of the pipes and replaced with granular
bedding or concrete grade 10N/mm2 as directed by the
Engineer’s
Representative.
For measurement purposes, depths shall be measured from formation level in the case of
cuttings and from the original ground level where the new
carriageway is on embankments.
The rate for excavation shall include for any extra width over the net width, which the
Contractor may consider to be necessary. The rte for
excavation shall also include for any timbering, shoring,
strutting, or pumping if required, backfilling and
compaction and for the disposal of surplus material as
directed by the Engineer’s Representative to a distance
not exceeding 1.6 kilometres. Soft yielding material shall
be dug out and replaced with approved selected material
compacted to 100% of its maximum dry density obtained
in the West African Compaction Test. All backfilling
shall be
compacted to 100% of its maximum dry density obtained in
the West African Compaction Test.
DEMOLITION OF
EXISTING
6145.
The Contractor will be required to excavate and demolish existing culverts as and where directed by the
Engineer’s
Representative.
Materials from the
demolition will be disposed of as directed by the
Engineer’s Representative. Where the culvert has been
demolished, the area will be backfilled with suitable
material as specified in the relevant clause of the
specification.
CULVERTS
Payment will be made under the appropriate items in the
Bill of Quantities, and shall include for excavation,
demolition and disposal of materials and backfilling, all
as specified herein.
NEW PIPE
CULVERTS
6146.
Where specified on the drawings, all pipe culverts will be
bedded on and haunched with a minimum of 150mm
thickness of Grade 15 N/mm2 Quality concrete.
(a)
Unreinforced concrete pipes shall comply with
B.S. 556. They shall be unreinforced standard
pipes and the following shall apply:
(1)
Joints shall be ogee type
(2)
High alumina or sulphate resisting cement
will not be required
(3)
Samples of aggregate will not be required
(4)
Tests other than the manufacturer’s
quality control tests will not be required
(5)
No variation will be allowed in the time of
maturing
(6)
Certificates in accordance with Clause 8 of
Appendix A will be required.
Admixtures will be prohibited.
(7)
Un-reinforced concrete pipes shall be surrounded
with concrete and the pipe trenches shall be filled
to natural subgrade level with special granular fill.
No concrete shall be placed around any length of
pipe until the Engineer’s Representative has
approved the laying and jointing of same.
Special granular fill shall be placed and
thoroughly compacted in layers not exceeding
250mm loose depth.
(b) Structural concrete pipes shall comply with B.S.
556. They shall be reinforced extra strength pipes
of the Class specified on the Drawings and the
following shall apply:(1)
Joints shall be flexible spigot and socket
type with rubber gaskets and performance
data will not be required.
(2)
High alumina or sulphate resisting cement
will not be required.
(3)
Samples
not
(4)
Tests other than the manufacturer’s
xxxxxx control tests will not be required.
of
aggregate
be required.
will
(5) Certificates in accordance with Clause
xx8 Appendix A will be required.
(6)
Admixtures shall be prohibited.
Pipes shall be laid true to line and level and each pipe shall be separately boned between
sight rails. Immediately prior to laying, pipes shall be
examined for defects and no defective materials shall be
incorporated in the Works. Where non-standard lengths
of unreinforced concrete pipe are required at catch pits,
headwalls, outfalls and the like, the pipes shall be cut and
the ends made good. Where it is necessary to cut
structural concrete pipes, they shall be sawn and the cut
end shall be cast into the manhole catch pit headwall etc.,
so that at least 75mm concrete cover is provided.
Ogee joints shall be thoroughly cleaned before laying and 1:2 cement sand mortar shall be
evenly applied to the ends so as to completely fill the
joint. The pipes shall then be properly drawn together,
the outside of the joint
shall be neatly pointed and any surplus mortar on the inside
of the joint shall be removed.
Structural concrete pipes shall be laid and joined in accordance with the manufacturer’s
recommendations and the methods recommended for
flexible jointed pipes in National Building Studies Special
Report 35 “Pipe Laying Principles”.
Care shall be taken to ensure that excess cement mortar and earth or other material is
thoroughly cleaned out of the pipes. Cleaning shall be
carried out during the laying of the pipes by drawing a
timer badger through the pipes at a distance of 2 pipes
lengths from the last made joint or by other means
acceptable to the Engineer’s Representative. The timber
badges shall be not less than 450mm long and shall have a
diameter 12mm less than the internal diameter of the pipe.
The badger shall only be removed from the pipe in the
presence of the Engineer’s Representative.
If for any reason, the invert level of a pipe culvert is such that the depth of cover at the edge
of the pavement is less than 600mm or the diameter of the
pipe, then, on the instruction of the Engineer’s
Representative the culvert shall be given a complete
surround 150mm thickness, of Grade 15 N/mm2 quality
concrete in place of a concrete haunch, and payment shall
be made for same at the appropriate rates in the Bills of
Quantities.
The outlets of pipe culverts shall be pitched with stone to a minimum length of 2 metres from
the face of the culvert or as directed, and the level of the
pitching shall be at lest 75mm below the culvert invert.
The width of pitching shall be decided on site by the
Engineer’s Representative. The inlets of culverts shall be
pitched only where directed by the Engineer’s
Representative. In cases where pitching is unobtainable
the Engineer’s Representative may order a 150mm thick
apron of Grade 15 N/mm2 concrete to be constructed.
Where directed catch-pits of the required internal dimensions shall be constructed at the
inlets of culverts. The inverts and walls shall be of Grade
15 N/mm2 quality concrete, reinforced if directed.
The backfilling shall be of approved material, compacted
as specified in the relevant clauses of this specification.
a. Backfilling trenches: After the bedding has been
prepared and the pipe installed, selected material from
excavation or borrow pit, at a moisture content that
will facilitate compaction, shall be placed along both
sides of the pipe in layers not exceeding 150mm in
compacted depth. The backfill shall be brought up
evenly on both sides of the pipe for its full length.
Care shall be taken to ensure thorough compaction of
the fill under the haunches of the pipe. Each layer
shall be thoroughly compacted with mechanical
tampers or rammers. This method of filling and
compacting shall continue until the fill has reached an
elevation of at least 300mm above the top of the pipe.
The remainder of the trench shall be backfilled and
compacted by spreading and rolling, or compacted by
mechanical rammers or tempers in compacted layers
not exceeding 150mm. Tests for density will be made
as necessary and directed by the Engineer, at no
expense to the Contractor.
b. Backfilling pipe in fill sections: The fill material shall
be uniformly spread in layers longitudinally on both
sides of the pipe, not exceeding 150mm in compacted
layer and shall be compacted by rolling parallel with
pipe or by mechanical temping or ramming. Prior to
commencing normal filling operations, the crown
width of the fill at a height of 300mm above the top of
the pipe shall extend a distance of not less than twice
the outside diameter on each side of the pipe, or 4m
whichever is less. After the backfill has reached at
least 300mm above the top of the pipe, the remainder
of the fill shall be placed and thoroughly compacted in
layers not exceeding 150mm.
c. Construction machinery: In compacting by rolling or
operating heavy equipment parallel with the pipe,
displacement of or injury to the pipe shall be avoided.
Movement of construction machinery over a culvert
or a storm drain at any stage of the construction shall
be at the Contractor’s risk. Any pipe damaged
thereby shall be repaired or replaced at the option of
the Engineer’s Representative and at the expense of
the Contractor.
EXTENSION OF
6147.
Existing pipe culverts shall be extended to the lengths
shown on the drawings or as directed by the Engineer’s
Representative. The extension shall be of a similar
diameter to the existing culvert, and constructed in a like
manner. Where existing headwalls occur within the
carriageway width they shall be removed to a minimum
depth of 300mm below new road level and the new road
constructed to the profile shown on the drawings.
The existing culvert and the new extensions shall be
cleaned out and flushed as necessary on completion to
clear all dirt, cement mortar and other obstruction to
allow the free passage of water through its full internal
area.
EXISTING PIPE
CULVERTS
If so directed by the Engineer, the existing culverts which
are to be retained and do not already have a complete
surround or haunch of concrete as required, shall be dug
out and the surround or haunch completed by 150mm of
concrete as specified for new culverts.
ACCESS
CULVERTS
6148.
BOX CULVERTS
6149.
Access culverts shall, if sufficient cover is not available
for pipe culverts, be constructed in the form of a small
slab or box culverts to the grade, sizes and dimensions
shown on the drawings or as directed by the Engineer’s
Representative. The roof and floor slabs shall consist of
grade 25 N/mmm2 concrete reinforced as shown on the
drawings. The walls shall consist of grade 10 N/mm2
mass concrete. Construction shall comply with all
relevant clauses of the specification or such modifications
as the Engineer may decide. The headwalls shall be
constructed of pre-cast concrete blocks with a 6:1 sand
cement mix.
Box culverts shall be constructed to the grades, sizes and
dimensions shown on the drawings, or as directed by the
Engineer’s Representative, and the finished surface shall
be smooth and regular free from flaws, air holes and
excrescences and with a constant grade.
The grades of concrete and quantity and size of
reinforcement to be used shall be as shown on the
drawings and shall comply in all respects with the
requirements stipulated for mass and reinforced concrete.
Culvert construction shall comply in all respects with the
EXTENSIONS TO
EXISTING BOX
CULVERTS
6150.
requirements of this specification or such modification
thereof as the Engineer may decide.
The Engineer shall provide the Contractor with additional drawings for the construction of the extensions to
the existing small section box culverts. Measurement of
the works incorporated in these extensions shall be as for
new reinforced concrete box culverts.
The existing culvert and the new extensions, shall be
cleaned out and flushed as necessary on completion to
clear all dirt, cement mortar and other obstructions to
allow the free passage of water through its full internal
area.
CORRUGATED
METAL OR
“ARMCO”
CULVERTS
6151.
Where corrugated metal culverts are specified, they shall
be of galvanized corrugated metal pipes or pipe arches
of the “Armco” or other approved type, complying with
the cross-section and gauge specified. The pipes or pipe
arches shall be assembled in convenient lengths in
accordance with the manufacturer’s instructions or as
directed by the Engineer’s Representative. Before laying,
care must be taken to ensure that the bottom of the trench
or if laid under embankments, the prepared bed, is
accurately graded and compacted to provide a solid
uniform bearing for the pipes or pipe arches and to ensure
this the Engineer’s Representative may direct that a
300mm thick compacted layer of approved material be
constructed. The width of the trench shall be such that a
minimum of 300mm is left between the pipe or pipe arch
and the side of the trench. Back filling shall be of
approved material laid in uniform layers of 150mm in
depth and compacted to 100% of its maximum dry
density achieved in the West African Standard
Compaction Test.
For multiple structures, the minimum clearance between
each pipe or pipe arch shall be not less than half of the
maximum cross- sectional width of the pipe or pipe arch.
The minimum depth of compacted cover (excluding the
base course) over any pipe or pipe arch shall be at lest
300mm. The maximum depth of fill over any pipe or pipe
arch shall not exceed the manufacturer’s recommendation
for the particular gauge of culvert used.
Corrugated metal pipes culverts and channels shall
comply with the materials section Standard Specification
for Corrugated Metal Culvert Pipe, Designation M36-60
of the American Association of State Highway and
Transportation Officials except that:(i)
The pipes, culverts and channels shall be
manufactured from steel complying with B.S.
1449: Part A1, or Pat 1B with copper content
when required at 0.2 per cent minimum.
(ii)
The pipes culverts and channels shall be coated
with spelter complying with B.S. 729; Part 1,
alternatively the pipes may be manufactured from
steel sheet complying with B.S. 2989.
(iii)
The pipes and culverts shall be bitumen coated in
the course of manufacture as specified herein
below.
Where available, all culverts shall be factory coated with
a double layer of protective bitumen. Where the culverts
are not factory coated, i.e. in the case of the large
diameter or multiple culverts, the Contractor shall apply
two coats of approved bitumen, as a protective measure,
to the satisfaction of the Engineer’s Representative, and
the Contractor shall be deemed to have allowed for this in
his tendered rates and prices. If for any reason, such as
the acidity of the sub-soil water, the Engineer considers
any further protective measures to be necessary, the
Contractor shall carry out same as directed and shall be
paid at rates to be mutually agreed between the Engineer
and the Contractor.
(1) Bitumen – Bitumen for coating shall have the following
properties as in Table VI-3 below:
TABLE VI-3 QUALITY OF BITUMEN COATING
TEST TYPE
Bitumen soluble in cold
carbon tetrachloride, not
less than
Loss in
weight on
LIMIT
PERCENT
99.5
TEST
METHOD
AASHTO
T45
heating to 163°C, not
more than
Penetration of residue after
heating compared with
penetration of same sample
before testing for
loss on heating, not less
than
INLETS AND
OUTLETS OF
CULVERTS
6152.
1
85
AASHTO
T47
AASHTO
T49
The positions, lengths, dimensions and levels of all culverts including aprons shall be as shown on the drawings
or as directed by the Engineer’s Representative. The
culvert shall be cleaned out and flushed as necessary on
completion to clear all dirt, and other obstructions to
allow the free flow of water through its full internal crosssectional area.
The outlets of all culverts shall be protected from erosion
by stone pitching or concrete to a minimum length of 2
metres from its face. The width of the pitching or
concrete
shall be
decided
by
the
Engineer’s Representative and a toe-wall 450mm
deep shall be constructed at the edge of such pitching or
concrete. The inlets to culvert shall be similarly
protected, only where directed by the Engineer.
Where the gradient of the roadside drainage ditch would
be excessive if the ditch were graded to the invert level of
culverts, catchpits or balancing ponds shall be constructed
as and where directed by the Engineer’s Representative.
The catchpits shall be constructed of mass concrete to
such dimensions as required by the Engineer’s
Representative.
CLEARING
DRAINS AND
CULVERTS
6153.
Before any drain or culvert is brought into use the Contractor shall ensure to the satisfaction of the Engineer’s
Representative that it is free from all extraneous material,
all such material being completely removed from the site.
During the period of maintenance the Contractor shall
ensure that the drains and culverts shall be kept clear of
all obstructions and before the maintenance certificate is
granted all drains and culverts must be cleaned out to the
satisfaction of the Engineer. All costs incurred shall be
deemed to be included in the tendered rates and prices.
PITCHING
6154.
Pitching will be provided where shown on the drawings
or as directed by the Engineer’s Representative. The
stone used for pitching shall comply in all respects with
the requirements of this specification.
The pitching shall be either 150mm or 225mm thick as
appropriate and if directed or shown on the drawings shall
be set in mortar comprising 1 part of cement to 4 parts of
sand. The ground on which the pitching is to be placed
shall be shaped and compacted to the satisfaction of the
Engineer’s Representative before the pitching is laid. At
the extremities of the pitching, toe-walls shall be formed in
the same construction and they shall be carried down to a
depth of 450mm, or to such greater depth as may be
specified on the drawings or by the Engineer.
APPROVAL OF
METHOD
6155.
Pitching shall be measured per square metre of complete
pitching and payment will include for the supply of all
materials, labour, etc., and the construction of the
completed pitching shall be as specified in this Clause.
Catchpits where required may also be constructed in
pitching stone laid in cement mortar as directed on site by
the Engineer’s Representative and measurement shall be
per square metre of wall. Payment for toe walls shall be
based on the length of wall constructed and shall include
for excavation and backfilling.
The Contractor shall not commence work on the subgrade, sub-base course, base course or surfacing until he
has obtained the Engineer’s Representative’s approval of
the plant, materials and methods that he proposes for
clearance, excavation, mixing, transporting, heating,
spreading, grading and compacting the same as
appropriate compaction tests will be required before such
approval is granted.
The foregoing provisions shall not prevent the Engineer
from requiring the Contractor to vary his plant, material
or methods at any time during the execution of the works,
should he consider this essential for carrying out the
contract. The contractor shall not vary plant, material or
methods which have been approved by the Engineer’s
Representative without previously obtaining his approval
of such variation.
The Engineer or his Representative’s approval of any of
the Contractor’s plants, material or methods shall not at
any time imply responsibility for the execution of the
work involved and the Contractor shall at all times be
solely responsible for constructing the sub-grade,
subbase, base and pavement surfacing in accordance with
the specification and drawings.
PREVENTION OF
DAMAGE TO
COMPLETED
PAVEMENT
6156.
The Contractor shall ensure that the passage of any
vehicle or plant over the over the partially completed
pavement or over the sub-grade, sub-base or base does
not occasion any rutting or other damage or disturbance
to the partially completed works, and should such rutting
or other damage or disturbance occur, the Contractor shall
make the same good as directed by the Engineer’s
Representative at his own expense.
Vehicles and plant passing repeatedly over the partially
completed pavement or over the sub-grade, sub-base or
base shall not be allowed to travel in a single track, but
such traffic shall be spread out over as great a width as
practicable. There shall be no storage or stockpiling of
materials on top of partially completed pavements or on
the base, sub-base or sub-grade.
WATER FOR
CONSTRUCTION
6157.
The Contractor shall provide all water necessary for
the construction of the sub-grade, sub-base, base and
pavement surface. Such water shall be clean and free
from organic matters, waste matter or other harmful or
deleterious substances, and shall be obtained from an
approved source.
ROLLERS
6158.
The Contractor shall provide all plant necessary for
conveying and distributing water. Where it is necessary
to increase the moisture content of materials comprising
the sub-grade, sub-base or base, the water shall be evenly
sprinkled on the surface of the soil by spraying machine
of a type or types to be approved by the Engineer’s
Representative such machines being capable of uniformly
distributing the water at a known predetermined and
constant rate.
Smooth-wheeled, sheepsfoot and pneumatic-tyred rollers
where employed for compacting soils and pavement
materials as detailed in subsequent clauses, shall be of a
type and compacting effort approved by the Engineer’s
Representative and shall be capable of achieving the
specified degree of compaction. The compactive effort
shall be designated as the weight per centimetre width of
rolling wheel, for the smooth wheeled and pneumatic type
rollers. The compactive effort of the sheepsfoot roller
shall be expressed dividing the total load of the roller by
the foot area (square centimetre) in contact on hard
ground.
The distribution of wheels on any roller shall be such that
the whole of the ground surface within the width of the
roller is loaded during each pass of the roller.
VIBRATORY
COMPACTORS
6159.
Where vibratory compactors or power rammers are used
on the works they shall be of the type approved by the
Engineer’s Representative and shall be capable of
obtaining the specified degree of compaction approved.
TRENCH
EXCAVATION
FOR WIDENING
OF EXISTING
PAVEMENT
6160.
Where the existing carriageway is to be widened on its
existing alignment, the Contractor shall excavate a trench
with neat and vertical sides to each side of it to contain
the additional pavement construction required for the
new carriageway width.
Each edge of the existing surfacing shall be cut-back as
directed by the Engineer’s Representative on site, but
such cut-back will be kept to the minimum compatible
with the provision of a straight and clean sharp edge to
the surfacing on the inside edge of the trench. Payment
for the excavation of the trenches including for the
trimming back of the existing surfacing and the disposal
of all excavated material shall be made per cubic metre of
material excavated under the appropriate item for
earthworks in the Bills of Quantities.
Measurement shall be based on sections taken before and
after excavation of the trenches but payment shall not be
made for excavation in excess of that specified and
required to receive the specified pavement.
The maximum amount of trench excavation shall be
placed to fill and payment shall be made once only as
decided above.
PREPARATION
OF SUB-GRADE
6161.
The sub-grade, whether in trench excavation or construction shall be graded and compacted to such level as
will permit the works to be constructed to the required
thickness and specified finished levels and tolerances.
Before it is compacted, the Engineer’s Representative
will inspect the sub-grade and the Contractor shall notify
the Engineer’s Representative when each area of
subgrade is ready for inspection and shall allow
reasonable time for the inspection to be made. Wherever
ordered by the Engineer’s Representative, the Contractor
shall excavate any unsuitable material from below the
subgrade and shall deposit the same as and where directed
by the Engineer’s Representative. The Contractor shall
replace the void with fill material approved by the
Engineer’s Representative. Payment will be made in
accordance with the relevant clause of this specification,
excepting where the unsuitable material has been
imported by the Contractors.
All loose pieces of stone or other material exceeding
75mm in size in any dimension shall be removed from the
surface of the sub-grade before compaction s commenced
and disposed of as directed by the
Engineer’s Representative.
The Contractor shall then compact the whole of the
Subgrade by the use of approved smooth wheeled,
sheepsfoot or pneumatic tyred rollers, static or vibratory
type as approved by the Engineer’s Representative.
Final compaction shall be by smooth wheeled roller. The
density required shall be 100 per cent of the maximum
dry density obtained in the British Standard Compaction
Test.
Payment for compaction of sub-grade will be made once
only either through earthworks items, or other appropriate
items in the Bills of Quantities.
COMPLETION
AND SHAPING
OF SUB-GRADE
6162.
Immediately before the construction of the sub-base
course, the upper surface of the sub-grade shall be
tested for smoothness and accuracy of formation and if
any areas are found to lack the required smoothness or
accuracy, such areas shall be scarified, reshaped,
recompacted as specified, or otherwise treated as the
Engineer’s Representative may require until the required
smoothness and accuracy is obtained.
The finished surface of the sub-grade shall be left as
smooth as possible and the accuracy of finish in the
longitudinal direction shall not vary at any point by more
than 12mm from a 5-0 metre straight edge, placed in any
position on the finished surface parallel to the centre line.
The transverse profile shall conform to the same accuracy
using a correctly shaped template instead of the straight
edge. The level of any point on the aforesaid surface
shall not vary by more than 12mm from the finished level
of the pavement less the specified thickness of the
pavement construction. Payment for all of the work
required by this clause shall be deemed to be included in
the tendered rates and prices.
The requirements of this clause shall not be held to apply
to the existing bituminous surfacing scarified, shaped and
re-compacted on lengths of strengthening of the existing
alignment. Payment for all of the operations required
under this clause shall be deemed to be included in the
tendered rates and prices.
COMPLETION
OF VERGES AND
6163.
On completion of the carriageway and hard shoulders,
the verges and medians shall be brought to finished
level, shaped to the cross-falls as shown on the drawings
and compacted so that the upper 150mm has a dry density
of not less than 100% of the maximum dry density as
determined by the West African Standard Compaction
Test.
MEDIANS
Where the material forming the verges or medians is of
such a nature that it is liable to erosion, the Engineer may
direct that the top 75mm of the verges or medians be
formed of cohesive lateritic soil, or other approved
material, and the 75mm of filling material below it shall
be compacted in one operation to 100% of the maximum
dry density as determined by the West African
compaction Test. The selected lateritic soil for the verges
or medians shall preferably a well-graded lateritic soil
with a plasticity index of not less than 10 and not more
than 20. Payment for this selected compacted 75mm of
topping to the verges and medians shall be made under
the appropriate item in the Bill of Quantities.
The verges or medians shall be cleared of any windrows
or heaps of material and shall be graded evenly as
directed, so that water drains in the required manner. The
verges and medians shall be grassed, sealed or paved
where directed by the Engineer.
STRIPPING
TOPSOIL
6164.
Stripping topsoil shall apply only to those sections of the
roadway to be realigned; that is, where the proposed roadworks will not fall within the limits of the existing roadworks. Only those areas of the new construction outside
the existing road-works will be stripped of topsoil.
Before grading work is commenced, the vegetation and
underlying topsoil within excavation and embankment
areas shall be stripped off to a depth of not less than
100mm and not more than 150mm below the existing
ground surface. Stripped material, which is or may be
made suitable for topsoiling, shall be stored and used
thereafter if needed. Stripped topsoil in excess of the
quantity required for the Project top-soiling shall be stored
at locations specified for future use of the Engineer.
Topsoil shall not be stored in areas where it will interfere
with surface drainage or with the conservation of trees,
shrubs and other vegetation that are to remain.
CATCHPITS
AND CASCADES
6165.
Catchpits and cascades shall be constructed of in-situ
concrete Grade 15N/mm2 as shown on the drawings. Unshuttered exposed concrete surfaces shall be finished with
a wooden float. The ends of pipes shall be properly built
into the catchpits and un-reinforced concrete pipes shall be
cut off flush with the inner surface of catchpits.
Excavation not occupied by the catchpit cascade or by
adjacent pipe drains shall be backfilled with the excavated
material, which shall be placed and compacted in layers
not exceeding 225mm loose depth to a dry density
equivalent to that of the surrounding ground. Should the
excavated material become unsuitable for backfilling due
to any cause, the Contractor shall provide other suitable
material for filling at his own expense.
(CLAUSES 6166 – 6179 INCLUSIVE NOT USED)
TESTS
TESTS FOR THE
SELECTION OF
FILLING
MATERIAL
6180.
The following tests shall be carried out on all material
propos-ed for use as fill:(I)
PLASTICITY TESTS
(II)
GRADING TESTS
(III)
DENSITY/MOISTURE CONTENT
COMPACTION TESTS
(IV)
LABORATORY C.B.R. TESTS
Unless otherwise stated to the contrary, these tests shall
be carried out as described in section 1 of this
specification.
TESTS FOR THE 6181.
CLASSIFICATION
OF COMPACTED
The tests listed below will normally be required to be
carried out for each 2 kilometres of sub-grade or each.
layer of fill. The numbers and types of tests listed how-
ever, are given only as a guide to the Contractor for
number and type of tests which will be carried out during
the construction of the works will be determined entirely
at the discretion of the Engineer.
SUB-GRADE AND
FILLING
(I)
CLASSIFICATION TESTS
2
NO. LIQUID LIMIT TESTS
2
NO. PLASTIC LIMIT TESTS
2
NO. SIEVE ANALYSIS TESTS
4 NO. BRITISH STANDARD
COMPACTION TESTS
2
(II)
NO. LABORATORY C.B.R. TESTS AT
THE SPECIFIED DENSITY
AND
MOISTURE CONTENT.
CONTROL TESTS
20
NO. IN-SITU DRY DENSITY TESTS
Except where otherwise stated to the contrary, these tests
shall be carried out as described in section 1 of this
specification, or where no such descriptions given in
accordance with the appropriate British Standard
AASHTO and ASTM Standards.
The sieve analysis shall be carried out in accordance with
the standards laid down in the latest amended report of
the “Lagos materials testing Conference”, a copy of
which shall be made available to the Contractor on
request, or as per the latest B.S. 1377,
TRIAL SECTIONS 6182.
TO DETERMINE
TECHNIQUE
The Contractor’s attention is particularly drawn to the
necessity for carrying out trial sections with each type of
proposed filling material prior to the start of the main
construction for the particular type of material, to
determine the most efficient technique, the most suitable
compacted thickness of each layer and the suitability of
the proposed materials and plant, all as described in the
Clause 1052 of this specification.
(CLAUSES 6183 – 6199 INCLUSIVE NOT USED)
PART (C) SUB-BASE COURSE, BASE COURSE
ETC.
(1)
LATERITE
GENERAL 6200. In addition to any other clause of this specification, the following shall be
deemed to apply in particular to laterite sub-base course
and base course work, and shall be read in conjunction
with all other relevant clauses of the conditions of
contract and this specification.
MATERIALS
MATERIALS FOR 6201.
COMPACTED
SUB-BASE COURSE
AND BASE COURSE
All materials for the sub-base course, base course and
hard shoulders shall be selected by the Contractor.
Where a preliminary soil survey has been carried out by
the Engineer, a copy of the report on the soil survey
shall be made available to the Contractor. Where no such
soil survey has been carried out the Contractor shall make
his own arrangement for the location of borrow pits and
sources of materials, and the cost of any survey shall be
deemed to be included in the tendered rates and prices.
The soil survey report of the Engineer, when available,
shall be used for guidance only, and shall not relieve the
Contractor of his responsibility for executing the works in
accordance with the Conditions of Contract and this
Specification. All selected material shall be free of roots,
vegetable matter, and other deleterious material and shall
be approved by the Engineer’s Representative before its
incorporation into the works.
Normally the minimum strength of such base course material shall not be less than 80%
C.B.R. value being determined at maximum dry density
and optimum moisture content un-soaked with either East
African or Modified A.A.S.H.T.O. compaction.
However, where the Engineer’s Representative considers
it necessary on account of perched water-table or any
other reasons, he may specify that a C.B.R. value of 80%
be obtained after at least 24 hours soaking. For
construction on perched water area see clauses 6142 and
6142A.
Base Course
The requirements below in Clauses 6250, 6251 and 6252
shall apply herein.
Sub-Base Course - Type 1
The sub-base material shall consist of pit-run laterite, sand, or screening, and soil of other
similar binding or filler material and shall be obtained
from approved sources. The maximum dimensions of any
particle shall not be greater than two-thirds of the
compacted thickness of the layer in which it is to be
placed. Oversize material shall be removed by screens,
grizzlies or by hand picking. The gradation and soil
constants shall comply to the requirements specified
herein. The material shall be free from vegetable matter
and excessive amount of lumps of clay and other
objectionable or foreign substances.
Table VI-4 Gradation of Sub-base Material:
Sieve Percent Passing by Weight
75mm
600µm
425µm
75µm
100
25-60
10-40
5-20
The percent by weight passing the No-75µm sieve shall be less than but not greater than
35%. The material passing the 425µm sieve shall have a
liquid limit of not more than 35% and a plasticity index of
not more than 12, as determined by American society for
Testing Materials methods, serial designation D 432-39
and 42439 respectively or as determined by test No 2 or
2A and test Nos. 3 of B.S. 1377 (1975). Prior to approval
of the sub-base material a test section shall be constructed
to the thickness shown on the typical pavement section
and compacted to 100 percent of maximum density.
When the test section is compacted to 100 percent
maximum density at optimum moisture content, the subbase material shall be of such quality that it shall have the
minimum CBR of 30% after at least 24 hours soaking.
Once established that the sub-base meets the CBR quality
requirement at 100 percent maximum density it shall be
placed and compacted in the field to that density.
Sub-Base Course - Type 2
The minimum strength of material for Sub-base Course Type 2 shall not be less than 20%
C.B.R. after at least 24 hours of soaking, for light traffic.
The C.B.R. values shall be assessed in the same manner as for base course, at the optimum
moisture content and maximum dry density of the West
African Compaction Test.
At the Engineer’s Representative’s discretion material
with a liquid limit greater than 35%, and a plasticity index
greater than 12 may be disallowed for use as subbase
course or base course.
Sub-Base Course - Type 3
The use of Sub-standard Material for Sub-base
If the Engineer’s Representative is satisfied that good materials for base or sub-base course
are not available, sub-standard materials may be used
adopting the following guidelines:
Class A Materials
These are materials rejected either due to too much fine,
silt, or clay content but slightly fall short of strength
specified.
(i)
The material may be used by compacting it to a
dry density slightly less than maximum at
moisture content slightly grater than OMC, to
contain the tendency for such material to swell or
shrink due to cycle of weather. To make up for
strength deficiency, a ratio of strength proportion
of the material to what is specified shall be
worked out and the depth of the sub-base/base
course adequately increased to account for the
deficiency.
(ii)
On the other hand, where sand is available at
economical rate, mechanical stabilization shall be
used to reduce the fines content thus increasing the
strength of the material.
It will be necessary to determine economic percentage of
the sand required before the method is put into use.
Sub-Base Course - All Types
The gravels as excavated from the pits may contain
oversize material and such material must be broken down
so that all material used in base course shall pass a 25mm
sieve; and that used in sub-base shall ass a 50mm sieve.
The work of breaking down or disposal of such oversize
material shall be deemed to be included in the tendered
rates and prices.
ROCK LATERITE 6202.
FOR SUB-BASE
COURSE AND
AND BASE COURSE
Rock Laterite for base course shall be hard and durable
and shall be from a source approved by the Engineer’s
Representative. Samples of the stone shall be submitted
to the Engineer’s Representative for his approval and
shall be tested by soaking the specimen in water for 96
hours to ensure they do not disintegrate. The stone shall
not be less that 225mm deep, and shall be not less than
230 sq.cm base area, where the thickness of the course is
225mm. The percentage of wear shall not exceed 50% as
determined by ASTM C131-51 procedure.
Rock Laterite for blinding shall be clean crushed laterite
aggregate graded from 5mm to dust from the same source
as material for pitching, free from excessive clay or silt.
(CLAUSES 6203 - 204 INCLUSIVE NOT USED)
WORKMANSHIP
SEQUENCE OF
OPERATIONS
6205.
The pavement construction for the roadway shall consist
of the following as specified herein and shown on the
drawings:(A)
The scarifying of the sub-grade where no filling is
applied
(B)
The compacting of the sub-grade
(C)
The laying and compacting of the sub-base course
and base course
(D)
The providing of prime and first coat bituminous
surface dressing to the base course of the
carriageway if applicable.
BORROW PITS
FOR SUB-BASE,
BASE COURSE
AND HARD
SHOULDER
MATERIALS
6206.
The Contractor shall arrange and pay for any compensations or other payments whatsoever required for access
to and occupation and use of the borrow pits for course
and selected shoulder materials. The Contractor shall
clear sub-base, base the areas and remove and stockpile
overburden to such depths as may be required by the
Engineer’s Representative. Under no circumstances will
payment be made for removal of overburden. Materials
used which may include the incorporation of suitable
overburden as directed shall be taken only from such
areas and to such depths and in such a manner as the
Engineer’s Representative shall direct. The Contractor
shall at his own expense remove and dispose of all
unsuitable materials; the removal of materials may
require prior rooting and scarification and the Contractor
shall be deemed to have allowed for this in the tendered
rates and prices. The material as excavated may not fall
within the required limits of grading for the completed
pavement and the Contractor shall be deemed to have
included in the tendered rates and prices for any
additional work which may be required to bring the
material within the specified limits when laid and
compacted in the road bed.
Borrow pits shall be worked and drained so as to obtain
the maximum quantities of available suitable materials
and shall be finally drained, levelled and topsoil replaced
all as specified and to the satisfaction of the Engineer’s
Representative.
Payment for all arrangements, compensation, operations
and other requirements of this clause shall be deemed to
be included in the tendered rates and prices.
The width of the sub-base course and base course shall be
as shown on the drawings or as directed by the Engineer.
The compacted thickness of the sub-base course and base
course is dependent on the C.B.R. values of the Subgrade and that of the material used, and shall be as shown
on the drawings or as otherwise directed by the
Engineer’s Representative in accordance with the
following provisions:The specified combined thickness for the sub-base course
and the base curse has been derived from the pavement
design diagram, curve E(RRL.RN/2503) based on an
anticipated minimum C.B.R. value (after at least 48 hours
soaking) for the compacted Sub-grade. Where a C.B.R.
value in excess of the anticipated value is achieved, then
compacted thickness of the Sub-base course may be
reduced at the discretion of the Engineer’s Representative
and in accordance with curve E/RRL.RN/2803). Under
no circumstances shall the combined compacted thickness
of the pavement be reduced to less than 150mm.
Before compaction, the sub-base course and base course
material shall be brought to the optimum moisture content
for the compaction effort of the plant to achieve the
density specified. Where the existing moisture content of
the material is higher than this, the soil shall be allowed
to dry out by aeration; where it is lower sufficient water
shall be added to the soil such that uniform wetting of the
material to op6timum moisture content is achieved.
Compaction of the sub-base course and the base course
shall be carried out separately and shall begin
immediately the soil has been brought to the required
moisture content and shall be carried out rapidly until
completion. The compaction of the sub-base course and
base course shall be carried out to a dry density not less
than 100% of that achieved in the West African Standard
Compaction Test at optimum moisture content, but the
compaction of the base course may be carried out to a dry
density of not less than 100% of that achieved in the
Modified A.A.S.H.O. Compaction Test at optimum
moisture content, if so directed by the Engineer.
The base course shall be finished to camber or cross-fall
as shown on the drawings or as otherwise directed by the
Engineer’s Representative.
COMPLETION
OF SUB-BASE
COURSE
6207.
Immediately before the construction of the base course
the sub-base course shall be tested for thickness, surface finish, and accuracy, and if any areas are found to
lack the required thickness, surface finish, or accuracy or
specified density, such areas shall be scarified,
recompacted to the specified density or otherwise treated
as the Engineer’s Representative may require until the
required thickness, smoothness, accuracy or density is
obtained.
The finished surface of the Sub-base course shall be left
as smooth as possible and the accuracy of finish in the
longitudinal direction shall not vary at any point by more
than 12mm for a 5 metre straight edge, placed in any
position on the finished surface parallel to the centre line.
The transverse profile shall conform to the same accuracy
using a correctly shaped template instead of straight edge.
The level of any point on the aforesaid surface shall not
vary by more than 12mm from the finished level of the
pavement less the specified thickness of the base
construction.
The thickness of the Sub-base course at any point shall
not be less than the specified thickness by more than
12mm. The Contractor shall include in his rates the
digging of trial holes and making good same, to the
satisfaction of the Engineer’s Representative.
COMPLETION OF 6208.
BASE COURSE
Immediately before the application of the surfacing the
base course shall be tested for thickness, smoothness and
accuracy as specified below and if any areas are found to
lack the required thickness, smoothness and accuracy or
the specified density, such areas shall be scarified,
reshaped and re-compacted with additional approved
material added where necessary or otherwise treated as
the Engineer’s Representative may require, until the
required thickness, smoothness, accuracy or density is
obtained.
The finished surface of the base shall be left as smooth as
possible and the accuracy of finish in the longitudinal
direction shall not vary at any point by more than 5mm
from a 3.0 metre straight edge, placed in any position on
the finished surface parallel to the centre line. The
transverse profile shall conform to the same accuracy
using a correctly shaped template instead of the straight
edge. The level of any point on the aforesaid surface
shall not vary by more than 5mm from the finished level
of the pavement. The thickness of the base course at any
point shall not be less than the specified thickness by
more than 12mm and the average thickness over a length
of 0.4 kilometres shall be equal to, or in excess of the
specified thickness. The Contractor shall include in his
rates for digging necessary trial holes and making good
same, to the satisfaction of the Engineer’s
Representative.
In the process of completing the base course it may be
necessary to place material to a greater thickness than that
specified and to grade it to the specified finish. In so doing
excess material will be wasted. Payment for this and for all
other operations required to obtain the specified finish shall
be deemed to be included in the tendered rates and prices.
ROCK LATERITE 6209.
FOR BASE COURSE
The base course for the carriageway shall consist of
approved rock laterite as specified, laid to the required
total thickness after compaction. The lumps of rock
laterite shall be tightly wedged across the prepared
formation and interstices shall be filled with approved
spalls from the same source as the rock laterite before
thoroughly rolling. Rolling shall be carried out with a
roller weighing not less than 58 kilograms per centimetre
width of roll and any depression or surface irregularity
which occurs during rolling shall be corrected with
approved crushed quarry fines as specified, watered and
again rolled with a roller weighing not less than 58
kilograms per centimetre width of roll. No blinding shall
be done until the rock laterite bottoming has been
inspected and approved by the Engineer’s
Representative. When completed the surface of the base
course shall be smooth and even, free from irregularities
or loose material and true to cross section, line and level
as shown on the drawings.
If any clay or mud appears to the surface of the
foundation, the Contractor shall without additional charge
dig out the affected areas of such depth as directed and
make good the foundation and finish in conformity with
the adjacent surface.
6210.
The base course of the carriageway shall, where applicable, be provided with a prime coat and other surfacing as
specified in the relevant clauses of this specification. The
surfacing shall be laid as soon as possible after the
construction of the base course.
PREPARATION
6211.
OF BASE COURSE
TO RECEIVE
BITUMEN PRIME
COAT
Immediately before spraying of the prime coat, the surface of the base course shall be swept clean, and all
loose dust, dirt and the like removed. The Engineer’s
representative may also direct that any very smooth surface, to which the surfacing is unlikely to adhere, be
roughened with wire brushes or other approved means.
SURFACING OF
BASE COURSE
If any weak areas are found they shall be cut out and re-
filled with base course material and rolled to correct crosssection and gradient.
The surface shall be slightly damped before the
application of the prime coat surface.
(CLAUSE 6112 – 6214 INCLUSIVE NOT USED)
TESTS
TESTS FOR THE
SELECTION OF
LATERITE SUBBASE COURSE
AND BASE
COURSE
MATERIALS
6215.
The following tests shall be carried out on all material
proposed for use as sub-base course and base course:1.
Plasticity Test
2.
Grading Test
3.
Density/Moisture Content Compaction Test
4.
Laboratory C.B.R. Test
These tests shall be carried out as described in Section I
of this specification.
TEST FOR
6216.
CLASSIFICATION
AND CONTROL OF
COMPACTED
LATERITIC SUBBASE COURSE AND
BASE COURSE
The tests listed below will normally require to be carried
out for each 2 kilometres of sub-base course and base
course. The numbers and types of tests listed are,
however, given only as a guide to the Contractor for
tender purposes and the actual number and type of tests
which will be carried out during the construction of the
works will be entirely at the discretion of the Engineer’s
Representative.
(CLAUSES 6212 – 6214 INCLUSIVE NOT USED)
CLASSIFICATION TESTS
2
No. Liquid limit tests
2
No. Plastic limit tests
2
No. Sieve Analysis Test
3
No. West African Standard compaction tests, or
4
No. MOD A.A.S.H.T.O. compaction.
CONTROL TESTS
4 No. Laboratory C.B.R. Tests at specified conditions
20 No. In-situ dry density tests per 2 km in an alternative
manner, i.e. Right, Centre, Left, Centre, Right, etc.
Except where otherwise stated to the contrary, these tests
shall be carried out as described in Section I of this
specification, or where no such description is given in
accordance with the appropriate B.S.
The sieve analysis shall be carried out in accordance with
the standards laid down in the report of the “Material
Testing Conference, February 1963”, a copy of which
shall be made available to the Contractor on request.
INTRODUCTION OF ISO CBR
6216A.
ISO CBR is introduced because of the known factors that
our pavement elements i.e. sub-grade, sub-base and base
courses are usually compacted at a higher moisture
content than the plant optimum moisture content (OMC).
The word ISO means equal.
The procedure for
establishing the control data with the working system is as
follows:
1.
BORROW PIT FOR FILL
When borrow pit is approved for fill after passing all
necessary tests, as carried out in the laboratory, three sets
of moisture/density CBR tests shall be performed on the
specimen using the following levels of compactive
efforts:
(a) Sub-B.S., (b) B.S. and (c) West African Standard.
Each set of tests will have a minimum of five specimens.
All specimen shall be soaked ideally for 48 hours,
however the following soaking periods are recommended:
for the southern part of the country 96 hours soaking
whilst for the north 48 hours to 24 hours soaking.
NOTE: For Sub-B.S. compaction, the following shall
apply: Use CBR mould, number of layers shall be
three using 2.5 kg rammer. Height of fall =
300mm. Number of blows per layer shall be 25.
After determination of the dry density, moisture and CBR
of each set of tests, relevant graph of density/moisture of
each shall be plotted. Thereafter the values of CBR for
compacted specimen so obtained shall be plotted as
indivdual points on the compaction curve of each set of
specimen using corresponding dry density points.
Typical method of plotting ISO graph is shown in Fig.
VI-1 while the completed specimen of an ISO-CBR graph
is shown in Fig. VI.1A.
2.
SUB-BASE AND BASE COURSE
The above test will be performed on the materials
approved for use as either sub-base or base course using
the following compactive efforts. .B.S., WAS and
Modified A.A.S.H.O. The results will be treated as above
and relevant graphs with ISO CBR plotted.
3.
USE OF ISO CBR FOR CONTROL
In our present day control system, we have no method of
checking whether the compacted layer meets the specified
CBR criteria, we are only concerned with 100% relative
density and moisture content relative to the laboratory
design moisture and invariably the laboratory determined
OMC do not often tally with the
plant OMC. We are aware that maximum CBR can only
be obtained around OMC if this moisture is not achieved
on site the strength of the pavement will be les than
specified, if plant OMC is less than laboratory OMC:
meaning that the section is compacted to a moisture over
and above the plant OMC, thus producing a compacted
pavement with weak strength. When the density and
moisture of compacted layer is determined, same is
plotted on the control graph and the field CBR is read
from the ISO CBR line, this being the CBR value of the
pavement. This is a surer way of ascertaining that both
the density, moisture and required CBR are obtained on
site.
The Contractor shall carry out trial sections with the OF
proposed materials prior to the start of the main construction to determine the most efficient compaction,
technique, layer thickness and suitability of the proposed
materials and plants as described in the relevant clause of
this specification. See clause 1052A for a rolling test
method.
TRIAL SECTIONS 6217.
LATERITE SUBBASE COURSE
AND BASE COURSE
(CLAUSES 6218 – 6219 INCLUSIVE NOT USED)
(II)
DESCRIPTION
6220.
SOIL CEMENT SPECIFICATION
Soil cement shall consist of a course or courses composed
of soil stabilized with Portland cement. It shall be
constructed on prepared and accepted sub-grade, sub-base
or existing pavement in accordance with these
specifications and in conformity with the lines, grades
and typical cross sections as shown on the drawings and
compacted to a specified finished thickness to the
satisfaction of the Engineer.
INSERIRE GRAFICO
MATERIALS FOR
SOIL CEMENT
STABILIZATION
6221.
The materials used for soil- cement stabilization shall
comply with the following specifications:(A)
CEMENT The cement used shall be ordinary
Portland cement and shall comply with B.S.12 or
with the latest British Standard specification for
the cement specified, or NIS 11 of 1974 or NIS 15
1980.
(B)
WATER The water shall be clean and free from
harmful amounts of alkalis, acids or organic
matter. No water shall be used for stabilization
without the approval of the Engineer’s
Representative. The Contractor may be required
to collect samples of water in an approved manner
and to arrange for an analysis of the water by an
approved testing agency.
SOIL The soil shall be free from roots,
vegetable matter or other deleterious substances.
It shall be the nearest available approved material
which when stabilized with 3% - 7% cement shall
meet the design criteria specified in clause 6228 of
this specification.
(C)
APPROVAL
6222.
GENERAL
METHOD OF
SAMPLING
6223.
Representative samples of all materials proposed for use
in the soil-cement shall be submitted to the Engineer by
the Contractor at the Contractor’s expense. The Engineer
will test the proposed materials and inform the Contractor
if the tests indicate compliance with the specifications.
No material shall be used until it has been approved by
the Engineer. Permission to use any material shall not be
construed as approval of its source nor any acceptance as
continued acceptance.
All materials to be tested shall be selected according
to the method laid down in the appropriate British
Standard Specification and “Amended Decisions of
Material Testing Conference” or where there is no such
standard by a method to be mutually agreed between the
Engineer and the Contractor.
MATERIALS
SAMPLING OF
MATERIALS TO
BE STABILIZED
FROM BORROW
PITS
6224.
Trial pits in a proposed borrow pit area shall be dug from
original ground level and not from the bottom of any
existing borrow pits. Trial pits shall be at least 1.2 x 1.2
metres in size and dug to such a depth that the full extent
of the material intended for incorporation in the works is
exposed.
Materials for testing shall not be taken from the spoil of
the trial pit, but shall be made up of increments taken
from each face of the pit after the overburden soil has
been removed. The four increments shall be mixed three
times and quartered or riffled down to the size required
for testing.
SAMPLING OF
6235.
MATERIALS FROM
STOCKPILES
The surface material of a stockpile shall be removed
before sampling. At least twelve samples shall be
taken from different parts of the stockpile and the
resulting large sample shall be thoroughly mixed by hand
before being quartered for testing.
SAMPLES OF
6226.
MATERIALS EXISTING MATERIAL
ALREADY IN PLACE
Soil samples shall be taken by digging trenches across
the full width of the proposed pavement to the depth of
processing so that soil sampled shall be the soil that will
be actually used in soil-cement constructions.
TESTS FOR THE
SELECTION OF
SOIL TO BE
STABILIZED
The following tests shall be carried out on all materials
proposed for soil-cement stabilization:-
6227.
(i)
(ii)
(iii)
(iv)
(iv)
(v)
Liquid Limit Test
Plasticity Test
Grading Test
Density/Moisture Content Compaction Test
Laboratory C.B.R. Test
Unconfined Compression Test
The tests are to be performed in accordance with the
relevant B.S. as modified by the latest “amended
decisions of Materials Testing Conference”.
DESIGN
CRITERIA
The stabilized soil shall meet the following specification
for C.B.R. test results. The specimens shall be cured
with a wax cover for 6 days and soaked for 24 hours
before testing, after allowing the specimen to drain for 15
minutes.
6228.
TABLE VI-5 DESIGN CBR VALUES FOR SOIL CEMENT
MIX-IN-PLACE OR PLANT MIX
METHOD OF CONSTRUCTION
MIX IN PLACE
PLANT MIX
DESCRIPTION OF TEST
LABORATORY TEST ON MATERIAL
MIXED IN THE LABORATORY
LABORATORY CONTROL TEST ON
MATERIAL MIXED EACH DAY IN
THE FIELD OR ON CORED
SPECIMENS FROM COMPLETE SOILCEMENT PAVEMENT (AVERAGE)
LABORATORY CONTROL TEST ON
MATERIAL MIXED IN THE FIELD OR
ON CORED SPECIMENS FROM
COMPLETED SOIL-CEMENT PAVEMENT (MINIMUM)
PROCEDURE FOR 6229. (A)
ESTIMATION OF
CEMENT CONTENT
(B)
180%
160%
100%
100%
80%
80%
Classify the soil according to U.S. public road
Administration
system
The estimated range of cement content is determined
using the A.A.S.H.O. soil group (shown in table VI-6
below)
(C)
Material requiring high cement content should be rejected
as unsuitable.
(D)
Perform B.S. compaction on the material to establish
M.D.D. and O.M.C. using the middle cement content e.g.
(4.5)% cement for A.2 as shown in table VI-6 etc.. The
C.B.R. and U.C.S. specimens shall be moulded to this
density and moisture content.
(E)
Establish the relationship between cement content vs.
C.B.R. and U.C.S. (unconfined compression shear
strength) for soaked and un-soaked specimens.
(i) Moulding 3 C.B.R. specimens and 6 U.C.S. at each
cement content, with a minimum of three
contents.
e.g. for A-2 3%, 4.5% and 6%
(ii)
Wax and cure all specimens for 6 days (Except 3
U.C.S. specimens at each cement content which
should be cured for 7 days and tested without
soaking).
(iii)
Testing all C.B.R. Specimen and the 3 U.C.S.
specimens at each cement content after 24 hours
soaking by complete immersion in water and
allowed to drain for 15 minutes.
(iv)
Plot graphs of Cement contents vs. C.B.R.
(soaked).
Cement contents vs. U.C.S. (soaked and
unsoaked).
Established the required cement content at 180%
C.B.R. for site mix or 160% for plant mix and the
corresponding U.C.S. values soaked and unsoaked
for quality control in the field.
TABLE VI-6 MODIFIED CEMENT CONTENT
REQUIREMENTS OF A.A.S.H.O. SOIL GROUPS
AASHO
SOIL
GROUP
ESTIMATED
PERCENT OF
USUAL RANGE
AMENDED
IN CEMENT
CEMENT USED
CEMENT
REQUIREMENT
IN MOISTURE
CONTENT BY
PERCENT
DENSITY
WEIGHT OF
BY WEIGHT
DETERMINATION
DRY SOIL
OF SOIL
BY WEIGHT OF
DRY SOIL
PERCENTAGE
CEMENT
CONTENT BY
WEIGHT OF
DRY SOIL
FOR
MOULDED
SPECIMEN
A-1-4
4-6
2-4
3.0
2-3-4
A-1-B
4-7
2-5
3.5
2-3.5-5
A-2
5-8
3-6
4.5
2-4.5-6
A-3
6-9
4-7
5.5
4-5-6
A-4
7-11
5-9
7.0
5-7-9
A-5
8-12
6-10
8.0
6-8-10
A-6
9-13
7-11
9.0
6-9-12
A-7
10-14
8-12
10.0
8-10-12
Note: Heavy clay soils ranging from a-5 to A-7 should be
avoided where practicable.
CONSTRUCTION
6230.
The Contractor shall submit to the Engineer for approval
his method of stabilization, which may be based on either
the mix-in place or plant mix principle.
Whichever method of mixing is used the maximum
period between mixing of cement and final roll off of
stabilized material shall be 2 hours. The lengths of the
treated sections shall be regulated to ensure that the 2
hours time limit is not exceeded.
MULTIPASSMIX-IN-PLACE
6231. (A)
Level pegs shall be set at 30 metre intervals and the
base course material to be stabilized imported from
METHOD
(B)
(C)
borrow pits, spread and shaped to the required
crosssection and longitudinal gradient.
It may be
necessary to compact the base course material to obtain a
fair estimate to correct grade and cross-section. If the
material of the existing roadbed is to be used, the surface
shall be graded to required cross-section and longitudinal
gradient. The cross-section and grade shall be checked
by the Engineer’s Representative before construction
starts.
The material to be treated shall be scarified to the required
depth and thoroughly pulverized (including prewetting the
soil if necessary to aid pulverization). Precaution shall be
taken to obtain a uniform condition of the material for the
full depth and width to be treated. A pulverization of 80%
(i.e. ratio of the weight of soil mixture passing the 5mm
sieve to the weight of the total representative sample taken
exclusive of the gravel retained on the 5mm sieve shall be
achieved before the cement is spread.
Cement shall be spread uniformly over the pulverized
soil. Cement may be supplied in bags or in bulk. If bags
of cement are used, the bags shall be placed at calculated
intervals along the verge, the bags opened and the cement
spread evenly on the pulverized soil by shovels and rakes.
If the cement is supplied in bulk, it shall be spread by an
approved mechanical cement spreader and each batch in
the spreading equipment shall be weighed so that the
average rate of spread can be determined by the Engineer.
The rate of spread per linear metre shall not vary more
than 10% from the approved rate.
(D)
Wet Mixing is preferred to avoid
(i) Loss of cement due to formation of clouds of cement
dust during dry mixing.
(ii) Loss of time in excessive adjustment of moisture
content due to rapid evaporation
(iii) Variation in cement content due to segregation
caused by prolonged mixing.
The road mixing plant shall have provision for
introducing water at the time of mixing, through a
metering device or by other approved method.
The water shall be applied by means of controls that will
supply the correct quantity of water to produce a
complete mixture with a uniform moisture content.
Leakage of water from equipment will not be permitted
and care shall be exercised to avoid the addition of an
excessive amount of water.
TRAVELLING
6232.
MIXING MACHINE
METHOD
COMPACTION
6233.
GENERAL 6234.
REQUIREMENT
FOR PLANT
MIX PROCESS
The procedure for construction with either windrout
type or flat-type travelling mixing plant shall be as
directed by the Engineer.
Compaction shall commence as soon as an intimate
mixture has been obtained and the specified degree of
pulverization has been achieved. It is essential that the
moisture content at the time of rolling shall be at the
optimum of the compaction plant in use.
The mixing equipment shall be batch type mixing plant,
using revolving blade, or rotating drum mixers or continuous type at the option of the Contractor.
The soil,
water and cement may be proportioned either by weight
or by volume.
In all plants cement shall be added in such a manner that
it is uniformly distributed throughout the soil during the
mixing operation; the charge in a batch mixer, or the rate
of feed to a continuous mixer, shall not exceed that which
will permit complete mixing of the material. Dead areas
in the mixer, in which the material does not move or is
not sufficiently agitated shall be corrected either by a
reduction in the volume of material or by other
adjustments.
BATCH MIXING
6235.
WEIGHT
6236.
PROPORTIONING
VOLUMETRIC
6237.
PROPORTIONING
The weights or rates of feeds of soil and water shall be
within 5% of the amount specified by the Engineer and
the weights or rates of feed of cement shall be such that
the cement content in samples taken from any part of a
mixed batch or from different batches or from time to
time from the product of continuous mixers or from
mixtures spread on the roadbed, shall not vary more than
0.4% above or below the designed cement content by
weight of dry soil,
The mixer shall be equipped with a sufficient number of
paddles of a type and arrangement to produce a uniformly
mixed batch. The mixer platform shall be of ample size
to provide safe and convenient access to the mixer and
other equipment. Mixer and batch box housing shall be
provided with hinged gates of ample size to permit ready
sampling from each of the plant bins and of the mixture
from each end of the mixer. The mixer shall be equipped
with a timing device, which will indicate by a definite
audible or visual signal the expiration of the mixing
period. The device shall be accurate to within 2 seconds.
The plant shall be equipped with a suitable automatic
device for counting the number of batches. The time of
mixing a batch shall begin after all ingredients are in the
mixer and shall end when the mixer is half emptied.
Mixing shall continue until a homogeneous mixture of
uniformly distributed cement is produced. In general, the
time of mixing shall not e less than 30 seconds, except
that the time may be reduced when tests indicate that the
requirement for the variation of cement content (±.4%) is
being consistently compiled with.
When weight proportioning is used the discharge gate
on the weight box shall be so arranged as to blend the
different sizes of the soil as they enter the mixer. Cement
shall be weighed on scales, separate and distinct from the
soil batching scales.
Where volumetric proportioning is used for batch mixing, the volumetric proportioning device for the soil
shall be equipped with separate bins, adjustable in size,
for the various sizes of soil. Each bin shall have an
accurately controlled gate or other device so designed that
each bin shall be completely filled and accurately struckoff in measuring the volume of soil to be used in the mix.
Means shall be provided for accurately calibrating the
amount of material in each measuring bin.
CONTINUOUS
MIXING
6238.
In addition to the General requirements, as provided in
section 15, continuous mixing of the material shall
conform to the following requirements. The correct
proportions of each soil size introduced into the mixer
shall be drawn in from storage bins by a continuous
feeder, which will supply the correct amount of aggregate
in proportion to the cement, and so arranged that the
proportion of each soil size can be separately adjusted.
The bins shall be equipped with a vibrating unit, which
will effectively vibrate the sidewalls of the bins to prevent
any “HANG UP” of material while the plant is operating.
A positive signal system shall be provided to indicate the
level of the material in each bin and as the level of the
material in any one bin approaches the strike-off capacity
of the feed gate, the device will automatically close down
the plan instantly. The plant shall not be permitted to
operate unless this automatic signal system is in good
working order.
The drive shaft on the soil feeder shall be equipped with a
revolution counter reading to 1/100 of a revolution and of
sufficient capacity to register the total number of
revolutions in a day’s run. The continuous feeder for the
soil may be mechanically or electrically driven. The
continuous mixing plant shall be equipped with a hopper
of at least 0.6 cubic metre capacity which is divided into
as many compartments as there are sizes of soil being
proportioned. The hopper shall be suspended under the
soil feeders on a scale frame in such a manner that the
discharge from each soil feeder may be diverted into
separate compartments in the hopper when the feeders are
in full operation. The weight of a loaded hopper shall be
indicated on a springless dial scale of 2,278 kilograms
maximum capacity with 2 kilogram graduations. Each
compartment of the hopper shall be equipped with a gate
so that each size may be withdrawn separately on a
conveyor below the hopper in order that the total weight
of each size of soil may be determined and representative
samples obtained. The material so over withdrawn may
be returned to storage.
SPREADING
6239.
Side forms shall be set to the lines and grade as shown on
the drawings. Forms shall be of steel or stout timber and
shall be of sufficient strength to resist springing out of
shape during placing of soil cement.
The mixed material shall be protected by covers against moisture loss while being
transported to the spreading site and each layer shall be
spread in one operation without segregation (not more
than 30 minutes shall elapse between mixing and
spreading).
Immediately prior to spreading, the area to be covered
shall be moistened and kept moist, but not excessively wet.
The mixture shall be simultaneously deposited and
spread with a self-propelled mechanical spreader ready for
compaction without further shaping.
The spreader shall be provided with a screed that strikesoff and distributes the material to be required width and
thickness within 5% of the pre-determined rate. The
screed shall be adjustable to the required cross section.
Screed action includes any cutting, crowding, or other
practical motion that produces a finished texture of
uniform appearance. If the spreader leaves ridges,
indentations or other objectionable marks in the surface
that cannot be eliminated by rolling, or prevented by
adjustments in operation, its use shall be discontinued.
The use of motor grader, except for final trimming after
compaction, will not be permitted.
The mixed material shall be spread for the full planned width, either by one spreader or by
several spreaders operating in a staggered pattern across
the sub-grade or sub-base course, unless otherwise
permitted by the Engineer or if traffic conditions require
part width construction. Should permission be granted or
part width construction be required for the use of one
spreader operating alternately on continuous lanes, not
more than 30 minutes shall elapse between the time of
placing material in adjacent lanes at any location. If
longitudinal construction joints are necessary they shall
fall on lane lines.
Where the required compacted thickness is 150mm or less, the soil cement may be spread
and compacted in one layer. Where the compacted
thickness is more than 150mm the soil cement shall be
spread and compacted in
2 layers of approximately equal thickness and the
maximum compacted thickness of any one layer shall not
exceed 150mm or as directed.
Work on each layer shall be performed in a similar
manner and the surface of the compacted material shall be
kept moist or prevented from drying out by a method
approved by the Engineer until covered with the next
layer, either by using damp sand or sacks.
Soil cement base course placed in inaccessible areas may
be spread by approved methods in one course. After
spreading the material shall be thoroughly compacted to
the required lines and grades by means of pneumatic
tampers or with other compacting equipment, which
consistently obtains equal or better compaction than that,
specified. Soil-cement shall not be mixed or placed
during rain.
COMPACTION
6240. (A)
All rolling equipment shall be self-propelled and
reversible and shall produce the required compaction
within the operation time, e.g. from mixing, wetting,
spreading and compaction.
(B)
Initial rolling may be performed with smooth wheel steeltyred rollers weighing not less than 10,886 kilograms
with a compression on the rear wheels of not less than 58
kilograms of the tyre width, or with other compacting
equipment which consistently obtain equal or better
compaction that that specified. Pneumatic tyred rollers
shall be the oscillating type and having a width of not less
than 1.2 metres and equipped with pneumatic tyres of
equal size and diameter. Wobble wheel rollers will not be
permitted. The tyres shall be inflated to 6.3 kg per sq.cm.
or such lower pressure as the Engineer may direct and
maintained so that the air pressure will not vary more
than 0.35 kg per sq. cm. from the designated pressure.
Pneumatic-tyred rollers shall be so constructed that the
total weight of the roller can be varied to produce an
operating weight per tyre of not less than 907 kilograms.
The total operation weight of the roller shall be varied as
directed by the Engineer.
Rolling tests shall be carried out to establish the plant
maximum dry density (MDD) its optimum moisture
content (OMC) and the number of economic passes to
achieve the MDD. See Table I-4 for guidance on
performance of different plants relating to MDD and
OMC of different types of soil.
(C)
(D)
Rolling shall be performed in such a manner that bumps
and irregularities are eliminated and the finished surface
shall be true to the required grade and cross section
within the tolerances specified.
Rolling shall commence from the outer edge of the verge
to the centre of the roadway except on super-elevated
curves where rolling shall begin on the low side and
progress to the high side.
(E)
Areas inaccessible to rollers shall be compacted to the
specified density by other means, approved by the
Engineer.
(F)
All compaction planes shall be removed. The finished
surface shall be smooth, dense and free of ridges or
cracks. The surface shall be kept moist at all times until
the curing seal is applied.
FINISHINGS
6241
The finished surface shall not deviate at any point in a
longitudinal direction by more than 5mm from 3 metre
straight edge laid in any position on the finished surface
parallel to the centre line. The transverse profile shall
conform to the same accuracy when tested using a
correctly shaped template. The thickness shall not vary
more than ±12mm from the design thickness of base at
any point.
If the finished surface exceeds the above tolerance, the
excess material shall be trimmed with the least possible
disturbance of the material to remain in place. The excess
material shall be removed and disposed of immediately
after trimming and no loose material shall be left on the
base and the area shall be rolled again. Filling low spots
in the cement treated base will not be permitted.
CONSTRUCTION
JOINTS
6242. (A)
TRANSVERSE JOINTS
At the end of each day’s work or first thing in the
morning, a transverse vertical construction joint shall be
formed by cutting back 600mm into the compacted
soilcement and disposing of the material. Additional
mixture shall not be placed until the construction joint is
placed. When starting the work the 900mm section
adjacent to the joint shall be thoroughly hand mixed.
(B)
Longitudinal joints shall be constructed by cutting back
vertically into the existing stabilized material for
approximately 75mm and the material cut away may be
disposed of in the adjacent lane to be constructed. The
face of the cut joints shall be moistened in advance of
constructing the adjacent section.
CURING
The completed soil-cement shall be cured by either damp
sand cover or bituminous curing seal as directed by the
Engineer.
6243.
(A)
DAMP SAND
Immediately after compaction the soil cement shall be
cured for a period of 7 days by a 50mm layer of damp
sand spread evenly over the surface. The Contractor shall
keep the sand damp and shall close the stabilized soil to
all traffic during the curing period.
(B)
FIELD CONTROL
TESTS
BITUMINOUS CURING SEAL
The curing seal shall consist of liquid bitumen MC-O, or
MC-I unless otherwise specified. The curing seal shall
be applied at a rate between 0.68 – 1.13 litres per square
metre of surface and shall provide a continuous
membrane over the soil-cement pavement. The curing
seal shall be applied as soon as possible, but not later than
8 hours after the completion of final rolling. The surface
shall be kept moist until the seal is applied. No traffic or
equipment shall be permitted on the sealed base during
the first 6 days after the application of the curing seal,
unless otherwise permitted by the Engineer.
In order to ensure adequate cement content, proper
moisture content, adequate compaction, adequate
pulverization, intimate mixing and adequate strength, the
following field quality control tests shall be carried out
during construction.
6244.
(I)
MOISTURE CONTROL TEST
In each stretch, the moisture content shall be checked and
adjusted to optimum moisture content of the plant in use
before compaction commences. “Speedy” moisture tester
of any type may be approved by the engineer for use; the
speedy tester should be calibrated first before being put
into use (for calibrating procedure see clause 2003(6) ).
(II)
TEST FOR ADEQUATE PULVERIZATION
Before the addition of cement 80% pulverization shall be
achieved and this shall be checked for each stretch. For
procedure see Clause 6231 (B).
(III)
TEST FOR INTIMATE MIXING
Intimate mixing shall be checked by examining the colour
of exposed material from a series of holes to the full depth
of mixed soil-cement made at regular intervals. Uniform
colour of the exposed material indicates thorough mixing.
(IV)
STRENGTH
Samples of mixed soil-cement shall be taken in the field
prior to compaction. The samples shall be compacted
into CBR and/or UCS mould to B.S. or field density and
sealed with wax. In particular UCS specimens shall be
statically compacted, to the same densities as those of
field compacted CBR specimens. The specimens shall be
cured in the laboratory and tested after 7 days (6 days
curing and 24 hours soaking).
The frequency of these tests shall be one test for every
400 square metres and part thereof of material laid in
each layer.
(V)
IN SITU DRY DENSITY TESTS
(VI)
These tests shall be carried out immediately upon the
completion of compaction of each section. At least one
dry density test shall be carried out for each 350 square
metres of material laid in each layer, using the sand bottle
or other in-situ density testing equipment or the nuclear
gauge testing equipment approved by the Engineer.
These tests may be located where samples for CBR
and/or UCS have been taken.
THICKNESS OF PROCESSED LAYER
The thickness of the Soil-cement layer shall be measured
using the in-situ dry density holes, the thickness of cored
specimens from hardened soil-cement and any additional
holes at the discretion of the Engineer.
(VII) DETERMINATION OF CEMENT CONTENT
The Contractor shall provide the necessary equipment and reagents to enable cement
extraction tests to be carried out by the Engineer. For
procedure refer to B.S. 1924 (1975) test No. 6.
(VIII) CBR & UCS TESTS ON CORED SPECIMENS
CBR AND UCS tests shall be carried out on cored
specimens taken from hardened soil-cement.
The
frequency of these tests shall be at least one test for each
400 square metres and part thereof of material laid in
each layer. Sampling shall be in staggered pattern.
TEST RECORDS
6245.
The results of all the tests mentioned in this section of the
specification shall be carefully recorded in a manner
approved by the Engineer. The test results shall be
recorded in triplicate, one copy to be retained by the
Contractor and the other two copies to be handed to the
Engineer’s Representative.
ADDITIONAL
CONSTRUCTION
RECORDS
6246.
In addition to these records required under the provision
of clause 6245 above, the Contractor shall keep a record
for each individual section of soil-cement construction
giving the following details:(I)
Location, length and width of the section
(II)
In situ moisture content on scarification
(III) Moisture content prior to addition of cement
(IV) No. of bags of cement used
(V)
Time the cement was spread
(VI) Complete mixing time
(VII) Moisture content prior to compaction
(VIII) Compaction and Grading time
(IX)
Total operation time from cement spreading to
completion of compaction.
(X)
Location of borrow pit used.
This record shall be prepared in triplicate, one copy to be
retained by the Contractor and two copies to be handed to
the Engineer’s Representative.
SUPERVISION
The attention of the Contractor is drawn to the fact that he
must provide adequate experienced supervisory staff
during all the stages of soil-cement construction.
6247
(CLAUSE 6248 – 6249 INCLUSIVE NOT USED)
(III) CRUSHED STONE
GENERAL
6250.
In addition to any other clause of this specification the
following shall be deemed to apply in particular to
crushed stone base course, and shall be read in
conjunction with all other relevant clauses of the
Conditions of Contract and this specification.
MATERIALS
6251.
MATERIALS FOR CRUSHED STONE BASE
COURSE
Base course aggregate shall consist of crushed Stone.
(A)
PHYSICAL PROPERTIES OF AGGREGATE
Materials for use as Stone base shall be classified under
two categories i.e. Coarse aggregate and Fine aggregate.
1.
COARSE AGGREGATE
Coarse aggregate shall be granite crushed stone
sourced from approved Quarry by the Engineer’s
Representative and shall have sizes ranging from
50mm and retained on 5mm sieve. The aggregate
shall be free from clay or silty materials, and
when subjected to 10% fine test or aggregate
crushing value, the value of the results shall range
from 7.5% to 12.5% for 10% fine and not more
than 35% for aggregate crushing value.
It shall also comply with other requirements
under clause 2005 (1) and (2).
2.
FINE AGGREGATE
Fine aggregate known as binder materials shall be
materials passing sieve 5mm and retained on
75µm sieve. It may be sourced from river bed at
location approved by the Engineer’s
Representative or be fines from crushed stone. It
shall be free from vegetation or other
objectionable matter. Fine aggregate shall be
clean without any clay content, strong and sharp.
It shall be of such grading characteristic that when
combined with coarse aggregate, the composite
material shall conform to the gradation and other
requirements specified in clause 2004 (1-3).
3.
4.
Liquid limit and Plasticity Index requirements
stated herein shall apply to any aggregate
component that is blended to meet the required
gradation and also to the aggregate in the
compacted base course. The portion of fine
aggregate passing the 75µm sieve shall be either
non-plastic or shall have a liquid Limit not greater
than 30% and Plasticity Index not greater than 6.
This index test will only be applicable to materials
for wet laying.
COMBINATION PROCEDURE
It is easier to handle gradation size by use of two
categories of materials:- Firstly, grade the coarse
aggregate and plot on the stone base design
envelope, next, grade the fine aggregate and plot
in the design envelope. By simple proportion and
physical examination of the two graphs, guided by
experience, two to three combination trials may
produce the required satisfactory grading that will
fall into the envelope, otherwise simple
calculation may be used to achieve the required
combination proportion.
NOTE: Once an acceptable combination is
produced frequent grading checks on both
specimens must be carried out to ensure that
deviation in gradation is not allowed to occur.
The results of such grading test will enable
adjustment to be made on the combination
proportion.
5.
6.
COMBINATION OF DIFFERENT SIZES OF
AGGREGATE
Coarse aggregate of different sizes and the fine
aggregate shall be placed in different Bins. Each
aggregate size and the fines shall be sieved and
plotted on appropriate log chart. Simple arithmetic
calculation may be used to determine the
combination proportion. Alternatively, careful
study of the graphs, coupled with experience will
enable user to guess the proportion by trial and
error.
Once a suitable mix proportion is
established, the grading of each size of aggregate
shall be checked from time to time, to ensure that
there is no deviation or variation.
ESTABLISHING MIX CONTROL
CRITERIA
When a mix proportion has been established,
representative sample of each material shall be
combined and quartered to make six number of
CBR mould specimens, moisturized to 5% of dry
weight of sample and kept in air tight* container
for 18 hours. Before the samples are compacted,
the moisture shall be checked using calibrated
SPEEDY TESTER. If the moisture is lower than
5% more water to attain this moisture shall be
added. When the material is mixed thoroughly it
shall be compacted using Modified AASHO
compactive effort or using a vibrating kango
hammer. Whichever compactive effort is used
(not B.S.), it shall be in five layers and the
thickness of compacted specimen shall not be less
than 125mm or more than 130mm, otherwise it
shall be discarded. The loose material on the
specimen after compaction shall be removed
carefully, and with a straight edge placed across
the mould, in a minimum of two directions, the
depth of the compacted specimen surface from the
top shall be determined in three places along each
direction of the straight edge. The mean of six
readings shall be used to determine the depth of
the specimen and thereafter its volume.
Unless directed to the contrary the six specimens
will be tested for Dry Density only. Alternatively 3
specimens may be soaked for 24 hours (complete
immersion in water with 25mm water head above
the specimen) tested for CBR after the specimen is
allowed to drain for 15 minutes. The remaining
specimens shall be tested for CBR (strength)
unsoaked. The average of two close result shall be
the CBR or dry Density of the specimen. If CBR of
over 100% is obtained the dry density established
with corresponding moisture content shall be the
design criteria and control for the works.
The grading of crushed stone for use in crushed stone
base course shall be as follows:-
GRADING OF
6252.
CRUSHED STONE
(I)
DRY PROCESS
(A) 75mm to 12mm or 50mm – 12mm hereinafter
referred to as coarse stone.
(B)
(II)
12mm to dust hereinafter referred to as screening
WET PROCESS
Gradation: The composite mixture of coarse aggregate
and binder material, processed as hereinafter specified,
shall conform to one of the applicable gradations shown
in Table VI-7 and shall not vary from the low limit on
one sieve to the high limit on adjacent sieve or vice versa,
but shall be uniformly graded from coarse to fine.
Gradation requirement specified herein shall apply to the
completed base course after undergoing the mixing,
placing, compacting and other operations. The portion of
the aggregate passing No 75µm sieve shall not be greater
than one-third of the portion passing the No. 425 µm
sieve. The aggregates shall continuously be well graded
within the limits of Gradation A, B, C, D or E, as
specified below. The methods of test used will be ASTM
Standards C117, C127, C128, C136 and D422.
Sieves shall conform to ASTM Standard E.11 or B.S. sieve.
TABLE VI-7 GRADING ENVELOPE FOR
STONE BASE COURSE WET METHOD
PERCENTAGE BY WEIGHT PASSING SQUARE MESH SIEVE
SIEVE
DESIGNATION GRADING GRADING GRADING GRADING GRADING GRADING
A
B
C
D
E
F
75mm
100
100
100
100
50mm
100
50mm
85 - 100
85 - 100
90 - 100
90 - 100
37.5mm
95 - 100
25mm
60 - 95
65 - 95
75 - 100
80 - 100
10mm
60 - 80
10mm
30 - 65
40 - 75
50 - 85
60 - 100
10mm
40 - 60
5mm
25 - 55
30 - 60
35 - 65
50 - 85
5mm
25 - 40
2mm
15 - 40
20 - 45
25 - 50
40 - 70
2.36mm
15 - 30
425µm
8 - 20
13 - 30
15 - 30
25 - 45
600µm
8 - 22
75µm
2-8
5 - 10
5 - 10
5 - 15
75µm
6 - 12
Note:- The table is based on aggregate of uniform
specific gravity, and the percentages passing the various
sieves may require appropriate correction by the Engineer
when aggregates of varying specific gravities are used.
WORKMANSHIP
PREPARATION
OF SUB-GRADE
6253.
The sub-grade shall be prepared and compacted in
accordance with terms as contained in Section VI Clause
6161 of this specification.
Note:- No sub-grade shall be considered as a working
platform for the stone base as this will promote the early
collapse of the pavement. This is due to the fact that the
elastic property of the sub-grade (of which strain is a
part) will not be able to sustain the wheel load from the
crushed stone base to the sub-grade without any
intermediate superior layer.
Where the sub-grade or sub-base is formed of material
liable to be forced up into the crushed stone during
compacting operations, the Engineer’s Representative
may direct that a 50mm thick blanket layer of approved
material shall be superimposed upon the sub-grade prior
to the laying of crushed stone. See clause 6133.
6254.
Where kerb or concrete haunches are not specified, the
Contractor shall ensure that the edges of crushed stone
base course, laid by either the wet or dry process, are true
to line and level and properly compacted to the same
standard as the test of the Base course by the use of
forms, hunching stones or other methods approved by the
Engineer’s Representative.
CRUSHED STONE 6255.
TO BE LAID AND
COMPACTED IN
LAYERS
Crushed stone Base course laid by either the wet or dry
method shall be laid in layers of not less than 150mm
compacted thickness to the satisfaction of the Engineer’s.
Representative
LAYING AND
COMPACTING
When crushed stone Base course is to be laid by the
dry process the method of laying and compacting shall
FORMS
6256
CRUSHED STONE
DRY PROCESS
be as follows:
(I) The coarse stone 75mm to 12mm or 50mm to 12mm
shall be spread in a manner approved by the
Engineer’s Representative to an even depth
which, after compaction will produce the
specified thickness of layer.
(II)
The coarse stone shall then be regulated and
compacted by not less than three passes of an
approved roller.
(III)
Successive uniform layers of screening 12mm to
dust shall then be applied over the surface and
shall be vibrated into the interstices of the coarse
stone by means of an approved vibrating plate
compactor or other approved means. Screenings
may be spread by hand shovel using a sweeping
motion or by approved tailboard spreaders
attached to lorries. In no case shall screenings be
dumped on the surface in piles and spread there
from. Great care shall be taken to ensure that
screenings are not applied either so quickly or so
thickly as to “CAKE” or bridge on the surface in a
manner which prevents the filling of the interstices
or causes the vibrating or compacting equipment
from bearing directly on the coarse stone. The
addition of screenings and vibrating into the
interstices of the coarse stone shall continue until
all the voids are filled in.
(IV)
The surface of the crushed stone shall then be
checked transversely and longitudinally for level
and camber and any indicated variations adjusted.
The surface shall then be sprinkled with water
from a water bowser and rolled with a smooth
wheel roller having a weight of roll of not less
than 58 kilograms per centimetre. Voids in the
Base-course, which occur during this process,
shall be filled by sweeping screenings into them.
The sprinkling, sweeping and rolling shall
continue until all voids are filled with grout to the
satisfaction of the Engineer’s Representative.
(V)
CRUSHED STONE 6257.
BASE COURSE
LAID BY THE
WET PROCESS
The final surface shall be smooth and even, free
from irregularities or loose material and true to
line and level having regard to the tolerances for
base course finish specified elsewhere herein.
When crushed stone Base course is to be laid by the dry
or wet process, the method of laying and compaction
shall be as follows:(I)
The approved crushed stone, graded as specified
shall be mixed with between 3% and 5% of water
as directed in a mixer of a type approved by the
Engineer’s Representative.
(II)
The mixed material shall be protected from the
rays of the sun during transit from the mixer to the
site in order to prevent loss of moisture due to
evaporation and shall be laid by a self-propelled
asphalt finisher or other approved plant in layers
of not less than 75mm or more than 150mm
thickness after compaction.
During this
operation, care shall be taken to avoid
segregation.
Water can only be added to any wet laid stone
base if it was discovered that evaporation had
taken place during rolling. The finished rolled
stone base shall not have moisture less than 3% or
more than 5% by weight of dry aggregate.
(III)
Should any patchiness appear during compaction,
areas deficient in fines shall be blinded with
screenings, watered and rolled and areas showing
an excess of fines shall be removed and
reconstructed with graded material to the
satisfaction of the Engineer’s Representative.
(IV) The final surface shall be smooth and even, free
from irregularities or loose material, and true to
line and level, having regard to the tolerances for
Base-course finish specified elsewhere herein.
PREPARATION OF 6258.
CRUSHED STONE
BASE COURSE TO
Crushed stone Base-course, laid by either the dry or wet
process shall be prepared for the addition of bituminous
surfacing as specified under the relevant parts of this sec-
RECEIVE BITUMINOUS SURFACING
tion of the specification.
COMPACTION
Compaction of crushed stone Base-course shall be to the
satisfaction of the Engineer
6259.
(IV) CONCRETE CARRIAGEWAY CONSTRUCTION
GENERAL
6260.
In addition to any other clauses of this specification, the
following shall be deemed to apply in particular to
concrete carriageway construction. And shall be read in
conjunction with all other relevant clauses of the
conditions of contract and this specification.
MATERIALS
CEMENT
6261.
In addition to any other clauses of this specification the
following shall be deemed to apply in particular to
concrete carriageway construction. And shall be read in
conjunction with all other relevant clauses of the
conditions of contract and this specification.
AGGREGATE
6262.
Fine and coarse aggregate for use in the manufacture of
concrete for construction of concrete carriageways shall
comply with the requirements of all relevant clauses of
this specification regarding aggregates for use in concrete
work.
REINFORCING
STEEL
6263.
Steel reinforcement for use in the construction of
concrete carriageways shall, where used, comply with
the requirement of all relevant clauses of this specification
regarding M.S. reinforced concrete work.
DOWEL BARS
AND TIE BARS
6264.
Dowel bars and tie bar shall consist of mild steel complying with the requirements of British Standard 15, free
from oil, paint, dirt and loose rust.
Dowel bars for transverse joints shall be straight, free
from burred edges or other irregularities and shall have
their sliding ends sawn, not sheered, unless otherwise
approved by the Engineer.
The length and diameter of dowel bars and tie bars shall
be as shown on the drawings or directed by the Engineer.
SIDE FORMS
6265.
RAILS FOR
6266.
MACHINE
FINISHED CONCRETE
CARRIAGEWAYS
Side Forms shall be of steel and of a design to be
approved by the Engineer. Curved forms of appropriate
radius shall be used for all curves of 30metres radius or
less. The width of the form shall be not less than the
pavement thickness, up to a maximum of 250mm and
flange branches shall extend outward on the base not less
than two-thirds the height of the form. All forms shall be
free from warp, twists and kinks, and where the top
surface of the forms determines the finished level of the
concrete; it shall be accurate in manufacture to within a
tolerance of ± 2mm in 3 metres measured in a vertical
plane. Repaired forms shall not be used until inspected
and approved by the Engineer’s Representative.
Forms to support rails on which the machine is to run
shall be sufficiently robust to support the weight of all
plant running on them without deformation.
Rails shall be of steel and of approved design enabling
them to be properly supported on the side forms or on
other approved mountings.
All rails shall be sufficiently robust to support the weight
of all plant running on them without deformation. They
shall be free from warp, twists and kinks and accurate in
manufacture to within a tolerance of ± 2mm in 3 metres
measured in a vertical plane.
PREFORMED
JOINT
FILLER
6267.
Preformed joint filler shall be of the thickness shown on
the drawings or directed by the Engineer within a tolerance of ±2mm. It shall be 25mm less in depth than the
thickness of the slab, within a tolerance of ± 3mm and of
the full width between road forms.
Holes to
accommodate dowel bars shall be accurately bored or
punched out.
The material comprising joint filler shall be of approved
quality, such that the filler can be satisfactorily installed
in position at the joint.
JOINT PRIMER
6268.
Joint priming compound shall consist of a suitable
bitumen based compound approved by the Engineer.
JOINT SEALING
COMPOUND
6269.
Poured joint sealing material shall consist of an approved rubber-bitumen compound, complying with the
requirements of British Standard 2499; test to assess the
properties of hot applied joint sealing compounds for
concrete pavements, and shall be grade-1. Class B or C.
The joint sealing compound shall have the following
qualities:
(a)
Capable of adhering to concrete under all weather
conditions.
(b) It should be ductile particularly in fairly cold weather
as to cover the widening of joint without
cracking, and be able to withstand the continuous
cycle of expansion and contraction for a long time
without a break up or disintegration.
(c)
It must be durable, etc.
WORKMANSHIP
GENERAL
6270.
Concrete carriageways shall be constructed in one or more
slab widths as indicated in the drawings.
Where a concrete carriageway is constructed more than
one slab wide, the first slab or alternate slabs shall be
constructed between two forms and the adjacent or
intermediate slabs shall be constructed by replacing the
flanged wheels on one or both sides of the machine with
flangeless wheels, which can travel on the surface of the
concrete already completed, or on rails fixed to
longitudinal timber laid on the completed concrete to
support the flanged wheels. Concrete slabs shall be at
least ten das old before they are subjected to the weight of
the finishing machine, but, in suitable weather, the
Engineer’s Representative may permit a shorter period
provided that adequate provisions made for protecting the
surface of the slab on which the wheels of the finishing
machine run and provided that the wheels do not run
nearer to the edge of the slab than 150mm and provided
further that the contractor gives an undertaking in writing
to be fully responsible for any damage that may occur and
to repair same at his own expense to the satisfaction of
the Engineer’s Representative.
THICKNESS OF
SLAB
6271.
The thickness at any point shall be not more than 6mm
thinner nor more than 12mm thicker than that shown on
the drawings.
CONCRETE
DISTRIBUTOR
6272.
Unless hand spreading has been sanctioned in writing by
the Engineer’ Representative, all concrete to be compacted by finishing machines shall be distributed with a
hopper type spreader of approved design.
Where
vibratory screeds instead of finishing machines are used
for compaction, the arrangements for placing concrete
shall be to the approval of the Engineer. Spreaders shall
be capable of striking off concrete at the correct level for
the placing of reinforcement and for producing a uniform
surface.
To minimize pre-compaction, hand spreading will be
permitted only where the concrete is deposited in loads
each not exceeding one cubic metre size, and from height
not exceeding 750mm.
COMPACTING
AND FINISHING
MACHINE
6273.
Compacting and finishing machines shall be approved by
the Engineer and shall compact and finish the concrete
either by the action of vibration or by mechanical
tamping.
The machine shall be addition have a strike-off blade or
paddle-roller to control the surcharge and a rear transverse
oscillating screed.
WATERPROOF
UNDERLAY
6274.
Where shown on the drawings or directed by the
Engineer’s Representative, waterproof paper as specified
or other approved underlay, shall be used and where more
than one sheet is used for the construction of any one
slab, the overlaps shall be at least 150mm. The
waterproof underlay must not be torn or damaged and
water shall not be allowed to collect upon it before the
concrete is laid.
SETTING,
CHECKING AND
STRIKING OF
SIDE FORMS
6275.
ALL SIDE FORMS SHALL:(I)
Be so supported that they remain rigid at all
times.
They shall be set in position at leas 20 hours
before concrete is placed between them unless the
Engineer’s Representative agrees to a shorter
period. Forms shall be cleaned and oiled each
time before they are used.
(II)
Be bedded on a layer, about 50mm thick and for
only the width of the form base, of cement mortar
or concrete of the same grade as the slab on a firm
foundation so as to ensure the necessary complete
rigidity and stability. The base on the line of the
forms shall be thoroughly compacted before the
forms are set.
(III)
Be as specified in Clause 6265 set to line and level
and secured by using not less than three pins for
each 3 metre section, one pin being placed at each
side of every joint or as otherwise approved by the
Engineer’s Representative. Form sections shall be
tightly joined together by a locked joint free from
play or movement in any direction, so as to
prevent the extrusion of concrete.
For machine laid concrete the form joints shall be made
without any discontinuity in the top surface of the forms
and the levels at the joints between the forms shall, where
form and rail are not integral, be set within a tolerance of
± 3mm of the levels shown on the drawings.
The wheels of finishing machines shall not be run directly
on the top surface of the side forms, but on rails as
indicated in clause 6266 or on the finished concrete as
provided in clause 6270.
For concrete to be compacted by vibrating screeds the
setting of the forms shall be such as to provide the
accuracy of finish specified in the relevant clauses of this
specification.
If corrections are necessary as a result of checking for
conformity with the alignments and levels shown on the
drawings, such correction shall be made before any
concrete is placed between them. Where any form has
been disturbed it shall be reset and rechecked. Side forms
shall be removed not less than 12 hours after completion
of the construction of the concrete road slabs. Care shall
be taken that the concrete and any projecting rods are not
damaged in any way during the removal of the forms.
The concrete or mortar bed used at the longitudinal joint
in partial-width construction shall be removed at the same
time if applicable and the sub-grade and sub-base made
good to the satisfaction of the Engineer’s Representative.
SETTING
CHECKING AND
STRIKING OF
RAILS FOR
MACHINE LAID
CONCRETE
6276.
The Engineer’s Representative may require any or all
concreting operations to cease if at any time, the forms or
rails are not set in position sufficiently far in advance of
the concreting to enable him to be satisfied as to their
compliance with the relevant requirements of this specification.
ALL RAILS SHALL:(A)
(B)
Be integral with the forms so that they remain
rigidly fixed at all times, or where independent, be
mounted so that they remain rigidly fixed to the
approved mounting during the passage of the
spreading and finishing machines. The surface of
rails shall be kept clean at all times.
Be firmly supported along the length in such a
manner that the finishing machine can travel
along the line of the carriageway at the correct
level.
(C)
(D)
(E)
Where the width of slab is continuously varying,
it shall be firmly supported throughout its length
on cement mortar or concrete as specified each
about 50mm thick so as to ensure the necessary
rigidity and accuracy of levels. The sub-grade or
sub-base or base course beneath the rail shall be
thoroughly compacted before any concrete or
mortar is laid.
Be so set as to ensure accuracy of level of the
surface of the concrete within a tolerance of
±3mm in 3 metres.
Be so set that the screed of the finishing machine
operates in relation to the rail, not the form.
Where on checking it is found that any rail or the form on
which it rests has been disturbed or is incorrectly set, the
rail shall be reset, and rechecked before placing of the
concrete between the forms is begun.
Rails may be removed in advance of removal of the forms
on which they rest provided that the latter are not
disturbed by so doing.
QUANTITY AND 6277.
DISTRIBUTION
OF STEEL
REINFORCEMENT
PLACING OF
STEEL REINFORCEMENT
FOR
CARRIAGEWAYS
6278.
TREATMENT
6279.
The quantity and distribution of reinforcement shall
be as shown on the drawings, with such modification
as may be necessary and approved by the Engineer’s
Representative to suit manholes and surface boxes,
junctions or slabs of different width or length; or as are
directed by the Engineer’s Representative. No loose rods
or small pieces of fabric other than as provided for in the
specification shall be permitted in any portion of the
work.
Steel fabric reinforcement for carriageways shall be as
specified in B.S. 1221. All reinforcement shall be so
placed that after compaction of the concrete it is in the
position shown on the drawings and shall terminate 40
mm from the edges of all joints in the concrete unless
otherwise specified.
Manholes shall be housed in separate small slabs,
which shall be the size of the exterior of the shaft and
shall be formed by casting the main slab against boxes of
this size, made from formwork and accurately placed
vertically above the exterior of the shaft. This formwork
shall be removed at the same time as the remainder of the
formwork for the slab. Expansion joint filler 10mm wide
shall be placed against the exposed edges of the slab, and
reinforcing bars if shown on the drawings or specified
shall be placed accurately in position so as to give the
required final cover, concrete being placed by hand in the
space intervening between the slab and the manhole
frame. This concrete shall then be compacted to the same
density as that of the adjoining slab.
A sealing groove shall be formed and filled at the top of
the joints with the surrounding slab: in accordance with
Clause 6283, the top arrises of both slabs being rounded
to a radius of 6 mm.
AT MANHOLES
JOINTS IN
CONCRETE
CARRIAGEWAYS
GENERAL
REQUIREMENTS
6280.
All joints shall be constructed by methods to be approved by the Engineer, and with vertical faces. Grooves
in the surface of the concrete over joints shall be sawn,
except that alternative methods of forming the grooves
may be submitted and may be considered by the Engineer
in lieu of sawn groves, provided that the contractor
demonstrates to the Engineer’s satisfaction that the
surface finish so obtainable is within the appropriate
tolerance permitted.
TRANSVERSE
JOINTS
6281.
Expansion joints shall comprise an approved preformed
joint as specified and dowel bars. The joint filler, together
with the sawn groove, shall provide complete separation
of adjacent slabs. The dowel bars as specified shall be
provided at mid depth of the slab, parallel to the finished
surface and to the centre line of the road within a tolerance
of ± 2mm in 300mm. Provision shall be made for
ensuring that the dowel bars and joint filler are held
securely
in
position
during
spreading
and compacting of the concrete.
Dowel bars shall be provided at one end with a closely
fitting sleeve 100mm long, consisting of cardboard or
other approved material. A loose plug equal in thickness
to the width of the expansion joint, and consisting of
cotton waste or a disc of expansion joint filler, shall be
inserted within the sleeve at the end of the dowel bar. The
free half of each dowel shall be greased or painted with
joint priming compound as specified or directed. The
method of assembling and securing joints shall be
approved by the Engineer.
Where contraction joints are required, these shall be
formed by a groove sawn in the surface of the hardened
concrete and a timber fillet cast into the base of the slab,
all as shown on the drawings. The sawn groove shall be
located vertically above the timber fillet to within a
tolerance of ± 12mm. Dowel bars shall be provided as for
expansion joints. Construction joints shall be installed
only under the conditions detailed in Clause 6287. They
shall be formed by means of a drilled and split cross-form
which shall allow tie bars to be inserted and which shall
permit the reinforcement to project through the joint for a
distance of at least 400mm. On recommencing work, the
cross-form shall be removed and the vertical face of the
concrete roughened. The next reinforcing mat shall
completely overlap the projecting reinforcement.
Joints shall be formed in a straight line at right angles to
the longitudinal axis of the carriageway, except where
this cannot be achieved, as at road junctions and
roundabouts and corresponding joints on either side of a
longitudinal joint shall be in line with each other. Where
possible, all transverse joints shall be staggered.
LONGITUDINAL
JOINTS
6282.
When slabs are constructed to multi-lane widths, the
additional reinforcement as shown on the drawings shall
be bars or provided as specified in clause 6264. The
longitudinal joints shall be placed symmetrically about
the middle of the slab in the form of a dummy joint, as
shown on the drawings, or as directed.
For slabs of single lane width, tie bars shall be provided
as above and as shown on the drawings. Provision shall
be made for maintaining the tie bars accurately in position
during spreading and compacting of the concrete. When
the adjoining slab is constructed, a groove shall be sawn
or formed by other approved means to the requirements
of clause 6283.
SAWING AT
JOINTS
6283.
Except when an alternative method is approved by the
Engineer, a groove shall be sawn in the concrete
immediately over the position of the joint. Sawing shall
take place by a method to be approved by the Engineer as
soon as possible but not before the concrete has hardened
sufficiently to ensure clean faces to the groove. In
considerating the type of construction joints to be adopted,
causes precipitating the joint must be considered and the
instruments available. In addition to the above, these
other methods may be found useful:
(a)
Stepping method (vertical)
(b)
Tongue method
(c)
Grooving method
The depth of grooves shall be 40mm. Groove over
expansion joints shall be 6mm wider than the width of the
preformed joint filler and shall be accurately located over
the joint filler.
Grooves forming longitudinal or
contraction joints shall be of the width shown on the
drawings, or as directed by the Engineer.
SEALING OF
JOINTS
6284.
All dust or grit shall be removed from the grooves, which
shall first be dried, if necessary, for this purpose. Unless
an alternative method of sealing is approved by the
Engineer, the dried joints shall then be coated with
priming compound, complying with clause 6268 and an
approved sealing compound heated to a temperature not
exceeding 180°C, shall be poured in so as to fill the
grooves completely. When filling grooves in expansion
joints, allowance shall be made for normal variations of
ground temperature in the locality, so as to avoid the
extrusion of the sealing compound with an expected
increase in ground temperature.
COMPRESSIVE
STRENGTH OF
CONCRETE
6285.
During the whole progress of concreting, test cubes
shall be made in the manner described for concrete
work. Not more than 1 per cent of cubes tested at 28 days
shall show a strength of less than specified.
If rapid-hardening cement is used, reference in this clause
to 28 days, which is the period for ordinary Portland
cement, shall be the period between concreting and
opening to traffic.
Cubes shall be made each day in sets at interval and
locations as decided by the Engineer’s Representative. At
the start of the work, and until such time as the Engineer’s
Representative may order a reduction in the number of
cubes required, six sets shall be made during each day’s
work, half of each set for testing at 28 days for
determination of the minimum permissible crushing
strength and the other half for testing at seven days for the
information of the Engineer’s Representative as to quality
of the mix. When the results of the first thirty sets are
available and for so long as the Engineer’s Representative
is satisfied with the quality of the mix, he may reduce the
number of cubes required to two sets per day.
If the minimum specified crushing strength is not so
attained the Contractor may without expense to the
Employer, cut cores from locations selected by the
Engineer’s Representative. Where this is done, the
strength of cores when tested in accordance with British
Standard 1881 methods of testing concrete will be
accepted as taking precedence over the cubes strengths in
determining the strength of the concrete and a core
strength of not less than 75 per cent of the specified
crushing strength at 28 days (tested vertically) will be
accepted for a core having a height/diameter ratio of 2.
The method which shall be adopted for correcting the
strength of cubes and cores for age shall be as directed by
the Engineer. In order to check the depth of concrete laid,
the state of compaction and the position of the
reinforcement, the Engineer’s Representative may order
cores to be cut, and the Contractor shall carry out same,
and repair all holes so formed at his own expense and to
the satisfaction of the Engineer’s Representative.
The unit prices to be inserted by the Contractor in the bill
of quantities shall include for preparing, cutting, packing,
and transporting and testing cubes and cores required by
the Engineer or his Representative. In addition, for cores
the price shall include for all costs incurred in connection
with drilling and making good to the satisfaction of the
Engineer’s Representative.
TRIAL MIXES
6286.
AND TRIAL SLABS
PLACING
CONCRETE
6287.
The Contractor shall make trial mixes using the aggregates proposed for the work to ensure that the concrete
mix is sufficiently workable and that segregation of the
mix during transportation and placing does not occur. The
composition of the trial mixes shall comply with the
requirements of the specification in all respects.
The Contractor shall construct a trial slab of the same
thickness as that to be laid in the work, to the full width of
the finishing machine, and at least 30 metres long. The
slab shall be constructed with the approved mix to be used
in the work and in a position as shown on the drawings or
directed by the Engineer’s Representative. Construction
of the trial slab shall be commenced sufficiently in
advance of the main construction to enable cores to be cut
from the trial slab. Six cores shall be cut there from and
shall be tested at 7 days, to ensure that the mix as designed
and the equipment proposed to be used are both suitable to
achieve a sully compacted concrete of the specified
strength, workability and surface finish.
When concreting of a slab has commenced no cessation
of the work will be allowed until concreting of the slab is
completed. In the event of mechanical break down or
adverse weather, however, the Engineer’s Representative
may permit the use of a construction joint and the
Contractor shall carry out any additional precautionary
measures stipulated at his own expense. Any of the
following joints may be considered by the Contractor:
(i)
(iii)
(iv)
(v)
SPREADING AND 6288.
COMPACTION
WITH A FINISHING
MACHINE OF REINFORCED CONCRETE ROAD SLABS
Construction joint
Expansion joint
Warping joint
Contraction joint
The placing, compacting and finishing of the concrete
shall be carried out as rapidly as possible and operations
shall be so arranged that in any vertical section, the
concrete shall be fully compacted throughout the whole
depth and finished within 1 hour from the time of the
completion of the mixing of the first batch of concrete in
that section.
For concrete slabs of 200mm thickness or less the
concrete may either:(a)
be spread and compacted in one layer, or
(b) be spread in two layers which shall be compacted
as one
When the concrete is spread in one layer a travelling jig
or a type approved by the Engineer’s Representative shall
be used to hold the reinforcement in position while the
concrete is being placed so after compaction the top cover
to the reinforcement is as specified. When the concrete is
spread in two layers the first layer shall be spread to such
a level that after subsequent compaction, it will support
the reinforcement at a level which will ensure the
specified top cover. The layer of reinforcement shall then
be placed in position and covered with concrete.
Whichever method of spreading is adopted, the concrete
shall be struck off at the appropriate surcharge and
compacted true to line and level by one or more traverses
of the machine to give the slab the final thickness
required. The compaction and surface finish shall be to
the satisfaction of the Engineer’s Representative.
For concrete slabs exceeding 200mm in thickness, the
concrete may either:
(a)
(b)
be compacted in two layers, or
be compacted in one layer, if it can be shown to
the satisfaction of the Engineer’s Representative
that, with the plant and methods to be used, full
compaction can be achieved through out the full
depth of the slab.
If the concrete is to be compacted in two layers, a layer of
concrete shall be spread, struck off at the appropriate
surcharge and compacted to a level that will ensure the
specified top cover to the reinforcement. The layer of
reinforcement shall then be placed in position and
covered with concrete, which shall be struck off at the
appropriate surcharge and compacted true to line and
level by one or more traverses of the machine to give the
slab the final thickness required. The compaction and
surface finish shall be to the satisfaction of the Engineer’s
Representative. If the concrete is to be compacted in one
layer, the concrete shall be spread and the reinforcement
placed in position by one of the methods specified for
slabs of 200mm thickness or less.
SPREADING AND 6289.
COMPACTION
WITH A VIBRATING
SCREED OF
REINFORCED CONCRETE ROAD SLABS
A layer of concrete shall be spread, struck off at the
appropriate surcharge and compacted to a level that will
ensure the specified top cover to the reinforcement. The
layer of reinforcement shall then be placed in position by
hand, or by mechanical means approved by the
Engineer’s Representative and shall be covered with
concrete, which shall be struck off at the appropriate
surcharge and compacted true to line and level by means
of a vibrating steel or hardwood screed. The compaction
and surface finish shall be to the satisfaction of the
Engineer’s Representative.
SPREADING AND 6290.
COMPACTION WITH
A FINISHING
MACHINE OR
VIBRATING SCREED
CONCRETE SLABS
OR HAUNCHES USED
AS ROAD BASES
In exceptional circumstances where reinforced concrete
slabs or haunches are used as road bases, the concrete
shall be spread, struck off at the appropriate surcharge
and compacted in a single layer by machine or by
a vibratory steel or hardwood screed and finished true
to line and level to the required thickness. The
compaction and surface finish shall be to the satisfaction
of the Engineer’s Representative.
CURING
6291.
CONCRETE
Immediately after completion of the finishing process,
all exposed surfaces of the concrete shall be protected
from the sun an drying winds by frames covered by
canvas or other approved material until the concrete is
sufficiently hard to bear the weight of other protective
material without the surface becoming marked. The sides
and ends of the frames shall be covered to exclude drying
currents of air.
Thereafter all exposed surfaces of the concrete shall be protected and kept damp by covering
with suitable matting, sand or other approved material; if
sand is to be laid a minimum depth of 50mm, will be
required. The curing material shall be kept wet for a
period of at least seven days or longer as directed by the
Engineer’s Representative. Alternatively, waterproof
paper in accordance with the relevant clause of this
specification, or other approved sheeting may be used,
and this shall be laid dry and kept in contact with the
surface of the concrete for at least seven days. The sheets
shall be lapped by at least 230mm and shall be weighted
down and well fastened along the edges to prevent the
wind blowing beneath.
As an alternative method of curing the surfaces may be protected, where approved by the
Engineer by treating with an approved resinous curing
compound, mechanically sprayed on to the surface of the
finished concrete at a rate of 4,5 – 6 litres/sq. m as soon as
it is possible to produce a membrane of uniform
thickness. Unless otherwise directed by the Engineer, the
compound shall be applied as soon as practicable after
completion of the laying and finishing of the concrete.
Any groove over a point shall be protected from the entry
of curing liquid.
ACCURACY OF 6292. The concrete surface shall not show a departure from the
CONCRETE true surface greater than 3mm when tested with a 3- SURFACE USING
meter straightedge or template in the manner described FINISHING OR for checking Base
course finish.
VIBRATING
SCREED If at any point tested the tolerance is outside these limits, the Contractor may make
not more than two additional passes of the vibrating beam
of the finishing machine and one further pass of the
oscillating screed. The surface shall again be tested in
the specified manner whereupon if the irregularity so
measured still exceeds 3mm in 3 metres, the Engineer’s
Representative shall direct that the concrete be removed
to the level of the top surface of the reinforcement or for
un-reinforced concrete to a depth of 50mm.
The area to be removed shall be that represented by the length of the straight edge in the
position of measurement across the full width of the
screed. The concrete so removed, shall not be reused.
Where the point of measurement in default is less than 5
metres
from a transverse expansion joint, the whole area up to the
joint shall be removed to the required depth.
Fresh concrete of specified quality shall be placed to the
appropriate surcharge. It shall then be compacted and
finished in the normal manner and shall again be subject
to test for accuracy of finish.
Although the concrete may be removed immediately
following measurement of the irregularity and while it is
still wet, this shall not absolve the Contractor from
complying with the requirements of this clause if for any
reason the concrete to be removed has hardened.
The removal of concrete under this clause and its
replacement shall be carried out as directed by the
Engineer’s Representative to his approval and without
extra charge. The accuracy of surface required by this
clause shall apply also to the surface across any joint
whether formed initially or as a result of replacement of
concrete arising out of the requirements of this clause.
In exceptional circumstances, where concrete road slabs
are to be surfaced with asphalt, coated macadam or dense
tar surfacing, the requirements as to the finished surface
of the concrete shall be those in this clause except that the
specified tolerance shall be 6mm in 3 metres instead of
3mm in 3 metres.
TRAFFIC OVER
FINISHED WORK
6293.
No vehicular traffic shall be allowed on the finished
surface within 20 days of its completion where ordinary
Portland cement is used or 10 days where rapidhardening
cement is used and until the joints have been sealed
unless otherwise authorized by the Engineer.
TESTS
SELECTION AND
CONTROL TESTS
6294.
The selection and control tests to be carried out under
this section of this Specification shall be those specified
to be carried out for concrete and reinforced concrete
work and shall be conducted in the manner stipulated in
all relevant clauses of this specification. In addition to
the making, curing and testing of concrete test cubes as
control tests on concrete carriageways, the Engineer’s
Representative may order cores to be cut from the
finished work so as to check the state of compaction, the
thickness of the concrete and the position of the
reinforcement. These cores shall be drilled and tested in
accordance with the provisions of B.S. 1881, or any
amendment thereto as directed by the Engineer.
TRIAL SECTIONS
The contractor’s attention is particularly drawn to the
necessity for carrying out trial sections with the proposed
materials and plant prior to the start of the main
construction to determine the most efficient construction
technique and the suitability of the proposed materials
and plant, as described by the relevant clause of this
specification.
6295.
(CLAUSES 6296 – 62299 INCLUSIVE NOT USED)
PART (D) – SURFACING
(I)
GENERAL
6300.
TWO COAT BITUMINOUS SURFACE DRESSING
In addition to all other relevant clauses of the conditions
of contract and this specification, the following shall be
deemed to refer more particularly to two coat bituminous
surface dressing work, and shall be read in conjunction
with same.
MATERIALS
MATERIALS FOR
6301.
Materials used in surface dressing are to be:
(i)
CUT-BACK BITUMEN FOR PRIME COAT:Either a cut-back bitumen known as M.C-O,
having a viscosity of 75/150 seconds at 25°C as
measured by the furol visosimeter, or a cut-back
bitumen known as M.C-1 having a viscosity of
75/100 seconds at 50°C as measured by the furol
viscosimeter.
(ii)
CUT-BACK BITUMEN FOR WEARING
COAT:-
(For first wearing coat: Either a cut-back bitumen
having a viscosity of 100/150 seconds at 40°C as
measured by the standard tar viscometer, or a
cutback bitumen having a viscosity of 300/400
seconds viscosity at 40°C as measured by the
standard tar viscometer.
(iii)
STRAIGHT RUN BITUMEN FOR WEARING
COAT:Straight run bitumen for first wearing Coat shall
have a penetration grade of 80/100 at 25°C and a
flash point (open) of 107°C (Minimum).
(iv)
BLINDING MATERIALS:-
(v)
Sand for blinding prime coat surface shall consist
of clean sharp sand of 6mm maximum size with
not more than 20% passing 600 µm sieve and
shall be approved by the Engineer’s
Representative. Alternatively grit arising from the
crushing of the rock may be used provided it is
approved by the Engineer’s Representative and
the grading complies with the specification for
sand earlier discussed.
MATERIALS FOR SURFACE DRESSING:Material for blinding the first wearing coat surface
dressing on the carriageway, shall consist of clean
crushed rock or clean crushed or uncrushed gravel
from an approved source, as specified, graded into
single sizes as defined in B.S. 63 latest edition or
any amendment thereto; “Single Size Road Stone
and Chippings”, or in
B.S. 1984 latest edition – “Single Size Gravel
Aggregate for Roads” as appropriate. Two single
sizes 19mm and 12mm shall be used for blinding
on the carriageways, while 10mm single size
material may be allowed for non-trafficked
surfaces (like verges) but only with the written
approval of the Engineer’s Representative.
The grading of the material shall be carried out by
means of an approved mechanically operated
screening plant, fitted with screens having square
perforations corresponding to the B.S. sieve size
of the material it is intended to produce. Screens
with circular perforations will be permitted,
provided the diameter of the perforations is
increased so as to be equivalent to the
corresponding B.S. sieve size.
The different sizes of materials shall be stored in
separate stockpiles and shall not be mixed. If the
Engineer’s Representative considers it necessary
the blinding material shall be washed before use.
The aim of the Contractor shall be to obtain the
maximum production of 19mm and 12mm single
sized material from the plant and either size may
be used in blinding a continuous section of surface
dressing of not less than 2 kilometres in length.
The crushing aggregate value of all material used
for surface dressing shall not exceed 30% and its
abrasion test result not more than 25%. All
samples shall be tested as described in B.S. 882.
Sample of all blinding materials to be used in the
works shall be submitted to the Engineer’s
Representative for approval prior to being used.
Prior to the commencement of surface treatment
works the Contractor will carry out tests under the
direction of the Engineer for the purpose of
assessing the adhesive qualities of the materials,
which are to be used in the works. As a result of
these tests the Engineer may decide that it is
necessary to use an additive to the bitumen for the
prevention of strippings of the stone surfacing,
and the Contractor shall comply with the
directions of the Engineer in this respect. Strip
test is recommended.
BITUMINOUS
6302.
Bitumen emulsion shall contain 30% of bitumen and
shall comply in all other respects with B.S. 434 (latest
edition and amendment thereto) except that the basic
bitumen used in the manufacture may have a penetration
of 80/100. Bitumen emulsion containing 30% of bitumen
may be made by mixing thoroughly together in the
correct proportions emulsion complying with B.S. 434
(amendment thereto) with clean soft water.
EMULSION
(CLAUSES 6303 – 6309 INCLUSIVE NOT USED)
WORKMANSHIP
HEATING OF
CUT BACK
BITUMEN
6310.
The cut-back bitumen shall be heated in a bitumen heater
or complying with B.S. 167, which shall have a capacity
commensurate with the output required. The heater shall
be so operated that the temperature of the bitumen applied
to the road shall be within the specified range. Accurate
thermometers shall be incorporated in the heater to give a
clear indication of the bitumen temperature. Should the
temperature be in excess of that specified, the Engineer’s
Representative may direct that this overheated bitumen be
disposed of at the Contractor’s expense.
CUT-BACK
PRIME COAT
BITUMEN
6311.
The prime coat shall be of a medium curing cut-back
bitumen of either M.C.O.Grade or M.C.1 Grade as specified. The actual grade to be used shall be determined
by the Engineer after carrying out site tests to determine
the penetration of each grade.
The bitumen shall be applied strictly in accordance with
the provisions of the relevant clauses of this specification
on an approved Base course free from all dust and loose
material and slightly damped prior to applying the
bitumen.
After spraying the surface shall be left for a minimum of
three hours before blinding is applied, or longer if
considered necessary by the Engineer’s Representative to
effect the maximum penetration. Blinding consisting of
sand or grit complying with the provisions of the relevant
clauses of this specification shall be applied so that a
uniform covering of sufficient thickness is obtained to
ensure that no bare or fat patches of bitumen are showing.
The blinding shall then be rolled in with not more than
two passes of a roller.
SPRAYING OF
CUT-BACK
BITUMEN
PRIME COAT
6312.
The prime coat as specified shall be evenly applied to the
prepared Base course by means of an approved pressure
feed mobile distributor and complying with the requirements of B.S. 1707: “Binder Distributors”.
In addition to the special requirements detailed in
section three of B.S. 1707. This test shall be carried out
prior to using the spraying plant for the first time on the
contract, and subsequently at the discretion of the
Engineer’s Representative. In the event of the quantity of
bitumen in any trough or troughs being found to lie
outside the prescribed tolerance from the average, the
faulty jet shall be located and cleaned or replaced.
The bitumen shall be applied at a temperature in
accordance with the Table given below, and at a rate of
spray of between 0.8 and 1.2 litres per square metre
depending on the texture of the surface. From the
calibration charts and tests made on the distributor, the
spraying speed shall be determined to give the required
rate of spray.
OR
Alternatively rate of spray may be checked as follows:
Check the initial and final quantity of cut back and
record. The difference between initial and final readings
divided by the area sprayed can be used to check
compliance with approved rate of spraying.
Note: Initial and final reading shall take place at same
position.
TABLE VI-8 SEALING COATS
TEMPERATURE OF APPLICATION
BITUMEN
GRADE
TEMPERATURE OF
APPLICATION
MIN
MAX
M.C.O.
38°C
66°C
M.C.I
54°C
79°C
The Contractor shall carry out trial sections, as directed
by the Engineer’s Representative to determine the most
suitable grade and rate of application of bitumen.
Immediately before any spraying run is begun, the spray
bar shall be tested by allowing all the jet to discharge
simultaneously for about half a minute with a slotted
metal tray placed beneath the spray bar whilst a visual
inspection is made. Any jet which is seen not delivering
a uniform spray cone shall be cleaned or replaced. After
testing the spray bar, the distributor shall proceed with the
spraying run without delay. No spraying shall be carried
out when rain appears imminent, during rain, or after rain,
until the surface has dried. The contractor shall ensure
that joints between spraying strips are straight and
without excess or deficiency of bitumen, which would
cause either fattening up or scabbing along the joint.
The Contractor will be required to re-spray at his own
expense any section which shows deficiency of binder, or
to burn off and re-spray at his own expense any sections
which show an excess of binder and which subsequently
fat up.
FIRST COAT
6313.
The wearing course of the surface dressing shall not be
laid until at least 10 days after the application of the
prime coat. During this period additional blinding
sand shall be added if directed and brushed over the
surface to prevent damage. After such period all
damaged or weak spots shall be cut out, refilled, recompacted flush with the existing surface, sealed and
blinded as specified and re-rolled to the satisfaction of
the Engineer’s Representative. After all repair work has
been allowed sufficient time to harden, the surface shall
be swept clean of all loose material immediately prior to
the application of the wearing coat. Before spraying is
begun the surface shall be dry.
SURFACE
DRESSING
Bitumen for the wearing coat of the surface dressing
shall be an approved cutback bitumen or straight run
bitumen, as specified in the relevant clauses of this
specification. The bitumen as specified shall be evenly
sprayed on the surface by means of an approved
mechanical spraying machine as specified.
The
temperature of the bitumen at the time of spraying shall
be in accordance with the table given below. The grade
of bitumen to be used shall be determined by the
Engineer.
TABLE VI-9: BITUMEN VISCOSITY AND
TEMPERATURE OF APPLICATION
BITUMEN
VISCOSITY
TEMPERATURE OF
APPLICATION
STV at 40°C
MIN
MAX
100/150 SECS.
132°C
160°C
300/400 SECS
149°C
177°C
The rate of spray of the bitumen shall be determined
according to the type of base, type and size of chippings
which are to be used as detailed in the table given below,
and the Contractor shall carry out trial sections, as
directed by the Engineer’s Representative to determine
the most appropriate rate of application of bitumen.
TABLE VI-10: SIZE OF CHIPPING AND RATE
OF SPRAY OF BITUMEN
NOMINAL
SIZE OF
CHIPPINGS
RATE OF SPRAY OF
BITUMEN LITRE/SQ.M
10mm
0.60 - 0.90
12mm.
0.75 - 1.20
20mm
1.20 - 1.50
Immediately after spraying the surface shall be blinded
with approved single size chippings as specified. The
chippings shall be distributed on the sprayed surface by
means of mechanical spreaders or tailboard gritters so that
a single layer of closely packed chippings is obtained.
Any bare or lean areas shall be made good by a follow-on
gang using hand blinding.
Rolling shall be carried out immediately after the
chippings have been spread with an approved roller
weighing not less than 3,629 kilograms or more than
5,443 kilograms. The minimum number of passes of the
roller shall be used to press the chippings into the film of
bitumen. Two passes of the roller should generally be
sufficient. Pneumatic tyred rollers are preferable to
smooth wheeled rollers.
Prior to the commencement of spraying a section of the
road for the first coat, a 2 metres wide paper strip shall be
laid over the end of the previous section. The bitumen
sprayer shall then commence its run from over this paper
strip.
FINAL SURFACE
OF
CARRIAGEWAY
6314.
The finished surface of the carriageway shall be left as
smooth as possible and the accuracy of finish in the
longitudinal direction shall not vary at any point by more
than 6mm from a 3-metre straight edge, placed in any
position on the finished surface parallel to the centre line.
The transverse profile shall conform to the same
accuracy, using a correctly shaped template instead of the
straight edge.
The surface shall be evenly textured and show no lean or
fat areas and shall not have any low or flat spots where
water will collect.
WET WEATHER
6315.
REGULATION OF 6316.
TRAFFIC OVER
PRIME COAT AND
SURFACE DRESSING
No surfacing work shall be done in wet weather or when
rain is imminent. Only dry chippings shall be used.
After laying the prime coat surfacing, barriers shall be
erected to keep the area surfaced free from traffic. It
shall remain free from traffic for such a period as the
Engineer’s Representative may direct after which it shall
be opened to traffic for not less than 3 days and for not
more than 7 days. During this period additional blinding
material shall be added and all damage by traffic made
good. After the application of the first coat surfacing, the
area surfaced shall be kept free from traffic for at least 24
hours.
The section shall then be opened to traffic and suitable
traffic notices and barriers shall be erected for a period of
one week restricting traffic speeds to 25 KPH. During
this period empty bitumen drums or other obstacles,
which shall be well lighted, or alternatively removed
during the hours of darkness, shall be placed on the newly
surfaced areas for the purpose of limiting the speed of
traffic, and shall be moved to different positions from day
to day in such a way that the whole width of the surface
receives equal wear and compaction from the wheels of
vehicles.
(CLAUSES 6317 – 6319 INCLUSIVE NOT USED)
TESTS
TESTS FOR
BITUMEN
6320.
The Contractor shall produce manufacturer’s test
certificate if requested, otherwise the Engineer may require the Contractor to carry out the following tests as
described in “standard methods for testing petroleum and
its products” published by the Institute of Petroleum, 26
Portland Place, London W.1.
Penetration of bitumen IP.49/56
Soluble bitumen content: bitumen and asphalt IP.47/55
Flash-point by means of the Cleveland apparatus
IP.36/55
Specific gravity IP.59/57. Method C.
Specific gravity of liquids or solids – pycnometer method
Specific gravity of liquids or solids – Method F.
The determination of viscosity by the standard tar
viscosimeter or the furol viscosimeter may also be
required by the Engineer.
The cost of carrying out these tests if required by the
Engineer shall be deemed to be included in the tendered
rates and prices.
TESTS FOR
AGGREGATES
ROADSTONE
AND CHIPPINGS
6321.
In determining the suitability of aggregates for use as
road surfacing material the Engineer may require the
Contractor to carry out any of the test specified in B.S.
812 – Mineral aggre- gates sand and fillers; B.S.882,
201 – Concrete aggregates from natural sources; B.S.
1881 – Methods of testing concrete; B.S. 1200 – Building
sands from natural sources; B.S. 63 – Singlesized
roadstones and chippings. The cost of carrying out these
tests if required by the Engineer shall be deemed to be
included in the tendered rates and prices.
TESTS FOR
BINDER
DISTRIBUTORS
6322.
The Contractor shall provide a set of 50mm wide trough
as described in Appendix A of B.S. 1707 and shall carry
out depot tray test A in the presence of the Engineer’s
Representative to demonstrate that the lateral distribution
is in accordance with B.S. 1707.
TESTS FOR RATE 6323.
OF APPLICATION
This test shall be carried out prior to using the spraying
plant for the first time on the contract and subsequently at
the discretion of the Engineer’s Representative. In the
event of the quantity of bitumen in any trough or troughs
being found to lie outside the prescribed tolerance from
the average, the faulty jet shall be located, cleaned or
replaced and a further test carried out if required by the
Engineer’s Representative.
The Contractor shall test the rate of application of bitumen at regular intervals, as directed by the Engineer’s
Representative by means of the “tray test” as described in
Road Note No. 11: “Binder distributors for surface
dressing”, issued by the Road Research Laboratory,
England.
(CLAUSES 6324 – 6329 INCLUSIVE NOT USED)
(II)
GENERAL
BITUMINOUS MACADAM SURFACINGS
In addition to all other relevant clauses of the conditions
of contract and this specification, the following shall be
deemed to refer more particularly to bituminous
macadam surfacing work and shall be read in conjunction
with same.
6330.
MATERIALS
BITUMEN
MACADAM
GENERAL
6331.
The manufacture an grading of the bitumen macadam
shall be in accordance with B.S. 1621 “bitumen
Macadam with crushed rock or slag aggregate except
where stated otherwise in these specifications.
BITUMEN
MACADAM
MATERIALS
6332. (A)
AGGREGATE
Coarse aggregate shall be hard clean and durable crushed
igneous rock from a source to be approved by the
Engineer and in accordance with B.S.812.
Fine aggregate shall be quarry fines produced from the
crushing of igneous rock in a secondary plant. They are
to consist of hard non-absorbent moderately sharp
particles and to be free from clay, loam, and other foreign
matter.
If filler is used it shall consist of finely ground particles
of hydrated lime, Portland cement or crushed rock and at
least 75% of the filler shall pass 75µm sieve.
(B)
BITUMEN
6333.
BINDER
The binder shall be a straight-run bitumen with a
penetration ranging from 40/50, 60/70, 80/100 at 25°C.
Representative samples of all materials proposed for use
under these specifications shall be submitted to the
Engineer by the Contractor at the Contractor’s expense
for test and for preparation of trial mixes to determine
job-mix formula. The Engineer shall make tests of the
proposed materials and inform the Contractor if the tests
indicate compliance with the specification.
MACADAM
APPROVAL OF
MATERIALS
BITUMEN
MACADAM
COMPOSITION
OF MIXES
6334.
The grading of the combined aggregate to be used in the
respective mix for each course shall be within the limits
stated below and when plotted graphically with the particle size to a logarithmic scale shall lie on a smooth
curve within the envelope of these limits.
TABLE VI-11: GRADING ENVELOPE FOR
BITUMINOUS BINDER COURSE
55MM BINDER COURSE
% PASSING SIEVE
SIZE
38mm 100
25mm 50 - 100
12.5mm
26 - 50
6mm 18 - 30
2.8mm 12 - 22
1.25mm
8 - 17
600µm 7 - 14
300µm 4 - 11
150µm 2 - 8
75µm 0 - 5
BITUMEN 4 – 5.5% BY WT. OF
AGGREGATE OR AS
PER DESIGN
TABLE VI-12: GRADING ENVELOPE FOR
BITUMINOUS WEARING COURSE
40MM WEARING COURSE
SIZE
25mm 100
19mm
12.5mm
9.5mm
% PASSING SIEVE
95 - 100
70 - 90
55 - 75
6.4mm
3.2mm
1.25mm
600µm
300µm
150µm
75µm
BITUMEN
40 - 60
25 - 40
15 - 30
12 - 24
8 - 18
5 - 12
3-6
4 – 7% BY WT. OF
AGGREGATE OR AS
PER DESIGN
The exact job-mix formulae will depend on the nature and
grading of the aggregate and the type of bitumen. The
exact job-mix formulae for the respective courses will be
determined by the Engineer.
(CLAUSES 6335 - 6339 INCLUSIVE NOT USED)
WORKMANSHIP
BITUMEN
MACADAM
MIXING PLANT
6340.
The materials shall be mixed in an approved mixer of
batch or continuous type from which mixed materials
can be delivered and laid hot.
The mixing plant shall be maintained in good working
condition and shall be subject to inspection by the
Engineer’s Representative. The weighing, measuring and
recording apparatus shall be checked at frequent intervals
and maintained in perfect adjustment throughout the
contract.
BITUMEN
MACADAM
MIXING
6341.
The aggregate and binder shall be heated separately,
aggregate to a temperature range of 121°C – 149°C and
the binder to 135°C – 163°C.
The respective temperatures of the aggregate and the binder are to be within
14°C on each other at the time of mixing.
Prolonged and excessive heating of the materials is to be
avoided and particular care is to be taken with binders. A
dry mixing period of at least 10 seconds – shall precede
the addition of bitumen to the mix. Wet mixing shall only
continue as long as is necessary to obtain a thorough
blend.
BITUMEN
6342.
MACADAM
MIXED MATERIAL
TRANSPORTING
Aggregates, including fillers, if any shall be thoroughly
dry immediately before mixing. When moisture is
detected in the mixed materials all aggregates in the hot
bins are to be removed and replaced in their respective
stock piles.
The mixed materials shall be transported from mixing
plant to site in clean metal lined vehicles. Every
precaution is to be taken to avoid segregation of mixed
materials and to ensure that they do not become contaminated with dust or foreign matter.
Should any load be wetted excessively by rain, they will
be rejected by the Engineer’s Representative.
Before the macadam is laid on the newly constructed
base course, the surface will be inspected by the
Engineer’s Representative and testing using an
Engineer’s level 3 metre straight edge or any other
means to ensure that the surface conforms with the requirements of this specification. Any irregularities in the
surface shall be corrected to the satisfaction of the
Engineer’s Representative before surfacing work will be
allowed to proceed.
BITUMEN 6343.
MACADAM
PREPARATION OF
SURFACE PRIOR
TO LAYING
BITUMEN
MACADAM
LAYING
6344.
After mixing the material must not be reheated other
than by the means provided in or on the spreading
machine.
Material must not be laid when the surface on which it is
to be placed is wet or when rain appears imminent.
Immediately prior to laying the bitumen macadam, the
surface of the Base course shall be swept clean of all
loose and caked dirt. The macadam as specified shall be
laid by approved means to be compacted thickness of
50mm binder course and 65mm wearing course, subject
to design.
BITUMEN
MACADAM
SPREADER OR
FINISHER
6345.
HAND
SPREADING
NOT ALLOWED
6346.
It is essential that the material be laid at a temperature not
less than 107°C and not more than 149°C. The
Contractor is to provide at each spreader and finisher a
suitable thermometer for testing the temperature of the
material as it is being spread and is to take such
temperature reading continually and record them hourly
throughout each day’s laying. This record shall be
available for inspection by the Engineer or his
Representative who will himself make such additional
temperature checks, as he considers desirable.
The materials shall be laid by approved mechanical
spreaders and finishers. The spreader and finisher
shall be in good mechanical condition and shall be
capable of laying to the required width and profile
without causing segregation, dragging, burning,
irregularities or other surface defects and it shall be
capable of being operated at a speed consistent with the
character of the mixture and the thickness of the course
being laid, so as to produce a surface having a uniform
density and surface texture. When not operated-on side
forms the spreader will employ equalizing runner evener
arams or other automatic compensating devices to adjust
the profile and confine the edges of the course to true
lines.
The mixer capacity and the operating speed of the
spreader shall be so adjusted as to ensure continuous
laying and to avoid intermittent stopping of the spread as
far as is practicable.
Hand spreading will not be permitted for general
work, but will only be allowed for filling localized
depressions, or as directed by the Engineer or his
Representative.
Where hand spreading and tamping is permitted the
mixed material is to be dumped on delivery upon an
existing hard clean surface or on approved metal sheets
outside the area where it is to be spread and shall be
distributed in to place immediately by hot shovels. It
shall be spread with hot rakes in a uniformly loose layer
to the full depth required.
BITUMEN
MACADAM
ROLLING
6347.
As soon after laying as conditions permit and when the
material is still at a temperature of not less than 95°C,
the materials will be uniformly compacted with 3
wheeled smooth rollers by rolling in a longitudinal
direction, progressing gradually from side to centre of
work and so lapping the rolling as to obliterate all roller
marks on completion. A sufficient number of rollers
shall be employed to ensure that the entire surfacing as
laid is compacted at the correct temperature.
At least two rollers are to be provided, one is to be
threewheeled and is to have a weight per centrimetre
width of rear wheel of between 44 and 63 kilograms. The
second roller shall preferably be a pneumatic-tyred roller
and shall be of multiple-axle, multiple-wheel type with
smooth-tread pneumatic tyres of equal size staggered on
the axles at such spacings and overlaps as will provide
uniform compactive pressure for the full compacting
width of the roller when operating. Oscillation of the
wheels, if provided, shall be in vertical plane only. The
pneumatic tyre roller shall be capable (A) of being
ballasted sufficiently to bring its loaded weight to at least
2½ times its own weight. Gross weight to be preferably
18 - 21 Tonne and
(B) of exerting compactive ground pressures of at least
5.6 kilograms per square centimetre (5.6 – 8.4 Kg/sq.cm).
For the pneumatic rollers compaction should be done
within 65°C – 80°C range.
All roller wheels are to be kept slightly moist by the use
of water tanks and spray bars attached to the machines to
prevent the material being picked up or disturbed.
Rollers must not be left standing on the new surface
while there is any risk of it being damaged thereby.
The sequence of rolling operation shall be:
(a)
breakdown rolling with the 3-wheeled smooth
roller;
(b) intermediate rolling with the high pressure tyred
pneumatic roller; and
(c)
the final rolling with a steel wheeled tandem roller.
Rolling will continue until the specified density is
obtained. This can be checked by using non-destructive
method i.e. Nuclear gauge apparatus.
FIELD DENSITY
OF COMPACTED
BITUMEN
MACADAM
6348.
Density tests of the bitumen macadam surfacing after
compaction shall be taken from the trial area and
later at intervals throughout the course of the work and
compared with the density of control specimens taken
from the same material before laying, all in accordance
with the following procedure:
(A)
A sample of mixed material will be taken from a
lorry before the material is delivered to the
spreader, and three control specimens shall be
made and their density measured by the
Engineer’s Representative by the marshall
method.
The average of two close results from the
specimens taken as the control density of that
particular batch.
(B)
The pavement will be marked with the batch
numbers to show where the lorry load of material
(from which the sample was taken) is laid, so that
field density samples can be taken for comparison
with the control specimens.
(C)
After completion of rolling, two samples are to be
cut from each area so marked in positions
indicated by the Engineer’s Representative.
(D)
The samples shall be taken in accordance with
part 1 section 3 of B.S. 598 and the density
calculated by weighing in air and weighing in
water in accordance with part 6 of B.S. 598. The
average of two close results will be taken as the
density of the compacted material in that area.
(E) The field density will not be less than 100% of the
control density determined as above.
TRIAL AREAS
6349.
When an approved rolling procedure has been
established, each course will be sampled in accordance
with the above at the rate of one sample area for each
1670 sq.m or one sample area every four hours
(whichever is the more frequent). Material which does
not achieve the required density will either be cut out and
replaced or be further compacted until the required
density is obtained.
The first 30 metres of the approved bituminous macadam,
which is laid by the spreader, shall be regarded as a trial
area in order to establish a rolling procedure, which will
produce the required field density.
At least four samples of the material after rolling will be
taken in accordance with part 1 section 3 of B.S. 598
(1958), when the work is at least 12 hours old in order to
determine the degree of compaction.
If the required specified density determined in accordance
with the foregoing clause is not obtained, the field rolling
procedure will be changed so as to achieve the desired
field density and the trial area will be cut out and replaced
to the satisfaction of the Engineer or his Representative.
BITUMEN
6350. (A)
MACADAM
FINISHED LEVELS
The surfacing will be finished to the required levels
shown on the drawings. The finished surface shall be
of such smoothness that when tested with a 3 metre
straight edge placed anywhere in a longitudinal direction
on the surface, there shall not be a gap greater than 5mm
between the bottom of the straight edge and the surface of
the pavement anywhere along the pavement. Any
deviation exceeding 5mm will be corrected at the
Contractor’s expense by scarifying, cutting out and
removing all loosened materials, adding new materials as
required, re-shaping and rolling. No materials loosened
by scarifying and cutting out will be left in position or
otherwise re-used. The surface shall be similarly tested
and corrected if necessary in a transverse direction using
a correctly shaped template instead of a straight edge.
(B) It is essential that the surface of the road is free from waves, any depression which retain
water on the surface are immediately to be corrected as
described above to the satisfaction of the Engineer’s
Representative.
BITUMEN 6351. All joints shall be vertical, properly formed to the
MACADAM correct line and level; if necessary, they shall be cut JOINTS back to
achieve this. The exposed edges of the bitumen macadam already laid shall be coated thinly
with bitumen emulsion containing 30% to 50% bitumen before laying adjoining work. All
joints on completion shall present the same texture, density and smoothness as other sections of
the surface.
Surfaces and projections which the new paving will abut shall be thoroughly cleaned and
coated with bitumen emulsion containing 30% - 50%
bitumen. The new paving shall then be tamped around
and against the projection to such a depth that, on
completion of compaction the finished surface of the
wearing course is level with the top of the projection.
BITUMEN 6352. Should the new bitumen macadam be dragged,
MACADAM churned up,
become soft, show signs of segregation, DAMAGED
WORK show that stripping of the binder from the aggregate has occurred, or suffer other
damage during or after being laid, the Contractor will remove the damaged or faulty work at
his own expense and replace with fresh material, laid and compacted to the correct level to the
approval of the Engineer’s Representative.
(CLAUSES 6353 – 6359 INCLUSIVE NOT USED)
TESTS
BITUMEN 6360. The Contractor shall provide equipment, labour and such
MACADAM TESTS trained staff as may be required by the Engineer’s
Representative for carrying out the following tests on
materials to be used in the manufacture of bitumen
macadam in accordance with the following standards:
(A)
Grading tests on aggregates in accordance with B.S. 812: “sampling and testing of
mineral – aggregates and fillers”.
(B)
Determination of binder content of mixed materials in accordance with hot extraction
method BT 1 described in B.S. 598: - “Sampling
and Examination of Bituminous Road Mixtures”.
The Contractor is required to comply to the
requirements of B.S. 598.
FREQUENCY OF 6361.
TESTS: BITUMEN
MACADAM
INDEPENDENT
TESTS BITUMEN
MACADAM
6362.
Aggregates shall be sampled and tested at source, on
delivery to the mixing plant and after each extraction test
and the result of each test shall be submitted to the
Engineer’s Representative within 24 hours of the sample
being taken. The number of such tests shall be adequate
for proper control of the materials and shall not be limited
to those made on specific instructions of the Engineer’s
Representative. Samples of mixed materials shall be
taken and tested during the first day’s mixing and
throughout the work to confirm that the grading and
binder contents are as specified.
Such samples shall be taken either at the place and time
of mixing or at the place of laying both may be necessary
as the results will complement one another as directed by
the Engineer’s Representative. Samples for testing shall
also be cut from the surfacing as laid when directed by
the Engineer’s Representative.
The frequency of sampling mixed materials shall be at
least once per day or once for each 90 tonne of material
mixed which ever is the more frequent. The result of
each test on mixed materials shall be submitted to the
Engineer’s Representative within 24 hours of the
sampling and any adjustments shown to be necessary
shall be made immediately. Until such adjustments have
been made and until a certificate to the effect has been
forwarded to the Engineer’s Representative no further
batches of mixed material shall be made.
Independent sampling and testing may be carried out
by the Engineer’s Representative throughout the contract period and for this purpose the Contractor shall grant
free access to the mixing plant and storage depots, supply
materials and provide every facility for the Engineer’s
Representative to take samples whenever required.
In particular, throughout the contract, the Engineer’s
Representative will carry out control tests on the plant mix
as he requires.
The Engineer’s Representative shall be supplied with all
necessary equipment, labour and materials to perform any
additional tests he may wish to carry out.
MANUFAC- 6363.
TURER’S
CERTIFICATE
FOR BITUMEN
A certificate is to be obtained from the suppliers
with each consignment of bitumen delivered, stating the
grade of material being supplied, and these certificates
are to be handed to the Engineer’s Representative.
CONTRACTOR
6364.
TO TEST
MATERIALS:
BITUMEN MACADAM
Notwithstanding the production of any manufacturer’s
test certificates if the Engineer so requires, the ConContractor shall arrange for the testing in an approved
manner of all materials used throughout the contract to
ensure that they are up to the standard specified, i.e.
Aggregates, bitumen and such other materials as specified
or decided by the Engineer. The Contractor shall arrange
for the testing of materials incorporated in the works to
ensure that they have been manufactured or supplied as
specified, or as ordered by the Engineer.
Whenever the Contractor intends to carry out any of the
above tests, he shall give the Engineer’s Representative
sufficient notice to enable him, should he so wish, to be
present during the test. The Engineer’s Representative
shall be given the results in writing of all tests, as soon as
they are available, and in any case not later than 24 hours
after samples have been taken.
NOTICE OF
6365.
TESTS: BITUMEN
MACADAM
SAMPLES TO BE
IN DUPLICATE
6366.
Whenever the Contractor takes samples for testing, and
where so directed he is to take duplicate samples and
hand them to the Engineer’s Representative. Such
samples are to be properly packed and labelled as
directed.
COST OF TESTS
BITUMEN
MACADAM
6367.
The cost of these tests including the provision of samples
will be deemed to have been included in the unit price
for bitumen macadam.
(CLAUSES 6368 - 6369 INCLUSIVE NOT USED)
(III) ASPHALTIC CONCRETE
GENERAL
6370.
This item consists of hot mixed, hot laid asphaltic
concrete composed of mineral aggregate and asphalt
cement thoroughly mixed in an approved plant until all
aggregate particles are uniformly coated with asphalt.
The asphaltic concrete shall be laid in two courses – surface and binder courses, with or
without wedge or levelling course or any combination of
these as shown on the drawings. Unless specified in
volume III or on the drawings, the compacted thickness of
each course shall not be less than 60mm for the binder
and 40mm for the surface course. the compacted
thickness of any single constructed course shall not
exceed 75mm for binder or levelling course or 60mm for
surface course.
Priming of untreated base and application of tack coat to
existing paved surfaces shall be done as follows:
For Priming Base: MC-O or MC-1 shall be used at
the rate of 1.0 – 2.0 Litres/sq.m
For Applying Bitumen emulsion,
Tack Coat: quick breaking type applied at the
rate of 0.25 – 0.70 Litres/sq.m
Tack coat shall be applied in all areas to take the binder course if warranted by surface
conditions and directed by the
Engineer’s Representative.
All materials and method of preparation and construction shall conform with the
requirements of these specifications.
The finished
pavement shall conform in all respects with the lines,
grades, dimensions and cross sections shown on the
drawings or as may be otherwise specified or directed by
the Engineer.
MATERIAL 6371. The materials used shall be those prescribed for the several parts which
constitute the finished work and shall conform with all
the requirements for such materials as set out herein.
(A)
AGGREGATE
(I) Coarse aggregate shall be the portion of the aggregate
retained on the No. 5mm opening sieve and shall
be hard, clean and durable crushed igneous rock
from a source to be approved by the Engineer.
The crushed stone shall be free from dirt or other
objectionable matter.
The coarse aggregate when tested by the methods
described in B.S. 812 shall have properties not
exceeding the following values on Table VI-13.
TABLE VI-13: AGGREGATE SPECIFICATION
FOR DENSE BITUMEN MACADAM, ASPHALTIC
BASE AND WEARING COURSES
Pavement
Course
Dense Bitumen
Macadam Base
Dense Bitumen
Macadam
WearingCourse
Asphaltic
Concrete BaseCourse
Asphaltic
Concrete
Wearing
Course
Aggregate
Crushing
Value
Flakiness
Index
Absorption
Factor
30
35
1.5
30
35
0.5
30
35
0.5
30
35
0.5
(II) Fine aggregate shall be the portion of the aggregate passing the No. 5mm opening sieve
and shall be quarry fines produced from the sieve
and shall be quarry fines produced from the
crushing of igneous rock.
They shall be
composed of clean, tough, rough surfaced and
angular particles, free from lumps, or ball of clay,
loam and other deleterious substances.
(II) Mineral filler shall consist of finely ground
particles of hydrated lime, Portland cement
or other non-plastic mineral matter
approved by the Engineer. It shall be free
from foreign or other objectionable
material, and shall meet the following
grading requirements.
TABLE VI-14: SPECIFICATION FOR
MINERAL FILLER
SIEVE
% BY WEIGHT PASSING
300µm
200µm
75 µm
(B)
100
95 - 100
85 - 100
BITUMINOUS MATERIAL
TABLE VI-15: QUALITY OF ASPHALTIC
CEMENT
PROPERTY
ASPHALT CEMENT
80 – 100
PEN
60 – 70
PEN
Softening point R and B (°C)
45 - 52
1.01 –
1.06
48 - 56
Penetration @ 25°C---0.1mm
80 - 100
60 - 70
100
100
0.5
0.2
99
99
Specific gravity @ 25°C
Ductility @ 25°C---cm
minimum
Minimum loss on heating for 5
hours at 163°C % by weight-max
Solubility in CS2 % by
wt…min
1.00 – 1.05
APPROVAL OF
6372.
Drop in penetration after
heating % original ---max.
Flash point (open cut) °C min
20
20
225
250
Ash. % by wt. max
0.5
0.5
(III)
Bitumen emulsion for track coat shall be emulsion
– quick breaking type containing 30% - 50%
bitumen.
(IV)
Cutback bitumen for priming shall be MC-O or
MC-1.
Representative samples of all materials proposed for use
under these specifications shall be submitted to the
Engineering by the Contractor at the Contractor’s
expense for test and for the preparation of trial mixes to
determine the job mix formula. The Engineer shall make
tests of the proposed materials and inform the Contractor
if the tests indicate compliance with the specifications.
MATERIALS
Suitable sizes of aggregate shall be stored in bins at each
point where bituminous materials are mixed. The bins
shall be in such numbers and of such capacities as to
ensure that an uninterrupted supply of all the necessary
sizes of aggregates is available at the mixer.
If aggregates are stockpiled prior to their transference to
the bins, the stockpiles shall be formed on concrete floors
laid to falls sufficient to permit drainage at the base of the
stockpiles. Aggregates shall be handled to and from the
stockpiles in a manner such that they are not contaminated
by the ground or by extraneous matter and also in a
manner such that segregation is prevented. In as much as
possible the bins shall be covered to prevent dampness of
aggregate by rain.
Coarse and fine aggregates and aggregates from different
sources shall be stockpiled separately and if aggregates of
different grading or from different sources are stockpiled
in close proximity, the stockpiles shall be separated by
partitioning.
All aggregates produced or handled by hydraulic methods
and all washed aggregates shall be stockpiled under cover
for draining for at lest 24 hours before use.
Material used as filler shall be stored in dry conditions to
the satisfaction of the Engineer’s Representative.
SAMPLING
6373. (1)
No material shall be used until it has been approved by
the Engineer. Permission to use material shall not be
construed as an approval of its source nor any acceptance
as continued acceptance.
The Contractor shall provide equipment, labour and such
trained staff as may be required by the Engineer for
carrying out the following tests on material to be used in
the manufacture of hot asphaltic concrete in accordance
with the following standards:
(A)
Grading tests on aggregates in accordance with
the latest B.S. 812 – “Sampling and testing of
mineral aggregate and fillers”
(B)
Determination of binder content of mixed
materials in accordance with either
(I)
Hot extraction method BT1 described in
B.S.598 (1974) – “Sampling and
examination of bituminous road mixtures”.
The Contractor is to comply with the
requirements of B.S. 598 and to the need
of providing results in duplicate.
OR
(II)
By reflux extractor method
(2) Aggregates shall be sampled and tested on delivery to the mixing plant and after each
extraction test and the result of each test shall be
submitted to the Engineer or his Representative within 24
hours of the sample being taken.
The number of such tests shall be adequate for proper
control of the materials and shall not be limited to those
made on specific instructions of the Engineer or his
Representative. Samples of mixed materials shall be
taken and tested during the first day’s mixing and
throughout the work to confirm that the gradings and
binder contents are as specified. Such samples shall be
taken either at the place and time of mixing or at the place
of laying as directed by the Engineer or his
Representative. Samples for testing shall also be cut from
the surfacing as laid when directed by the Engineer or his
Representative.
The frequency of sampling mixed materials shall be at
least once per day or once for each 90 tonne of material
mixed whichever is the more frequent. The result of each
test on mixed materials shall be submitted to the Engineer
or his Representative within 24 hours of the sampling and
any adjustments shown to be necessary shall be made
immediately. Until such adjustments have been made and
until a certificate to the effect has been forwarded to the
Engineer or his Representative no further batches or
mixed material shall be made.
(3)
Independent sampling and testing may be carried out by
the Engineer throughout the contract period and for this
purpose the Contractor shall grant free access to the
mixing plant and storage depots, supply materials and
provide very facility for the Engineer or his
Representative to take samples whenever required.
In particular, throughout the contract, the Engineer will
carry out control tests on the plant mix material using the
marshall test apparatus.
(4)
A certificate is to be obtained from the suppliers with
each consignment of bitumen delivered, stating the grade
of material being supplied, and these certificates are to be
handed to the Engineer’s Representative.
(5)
If the Engineer so requires, the Contractor shall arrange
for the testing in an approved manner of all materials used
throughout the contract to ensure that they are up to the
standard specified, i.e. Aggregates, bitumen and such
other materials as specified or decided by the Engineer.
The Contractor shall arrange for the testing of materials
incorporated in the works to ensure that they have been
manufactured as specified, or as ordered by the Engineer.
Whenever the Contractor intends to carry out any of the
above tests, he shall give the Engineer’s Representative
sufficient notice to enable him, should he so wish, to be
present during the test.
(6)
(7)
Whenever the Contractor takes samples for testing, and
where so directed, he is to take duplicate samples and
hand them to the Engineer’s Representative. Such
samples are to be properly packed and labelled as
directed.
(8)
The Engineer’s Representative shall be given the results
in writing of all tests, as soon as they are available, and in
any case not later than 24 hours after samples have been
taken.
(9)
The Engineer shall be supplied with all necessary
equipment, material and labour to perform any additional
tests he may wish to carry out himself.
(10)
COMPOSITION
OF MIXES
6374.
The cost of these tests including the provision of
samples, will be deemed to have been included in the bill of
quantities under the appropriate item.
Asphaltic concrete prepared under these specifications
shall be composed of graded aggregates and asphalt
cement within the limits set forth below. When plotted
graphically, the aggregate grading shall lie on a smooth
curve within the envelope.
TABLE VI-16: GRADING ENVELOPE FOR
BINDER AND WEARING COURSES
% BY WEIGHT PASSING
SIEVE SIZE
40mm – 65mm
40mm – 65mm
BINDER-COURSE WEARINGCOURSE
31.8mm
100
100
25mm
90 - 100
100
19.0mm
70 - 90
100
12.5mm
55 - 80
85 - 100
9.5mm
47 - 70
75 - 92
6.4mm
40 - 60
65 - 82
2.8mm
27 - 45
50 - 65
1.25mm
20 - 34
36 - 51
600µm
14 - 27
26 - 40
300µm
8 - 20
18 - 30
150µm
5 - 15
13 - 24
75µm
2-7
7 - 14
Bitumen
Content % by
4.5 – 6.5
5 – 8.0
weight of
aggregate
Asphaltic concrete mixes designed by the Contractor prior to the selection of Job-Mixes (see below)
shall have combined aggregate gradings approximating as
closely as possible to the plotted averages of the
respective limits of grading specified above and shall
comply with the following requirements.
TABLE VI-17: PROPERTIES OF
COMPACTED ASHPALTIC CONCRETE
Property
Base-course
Wearing-course
Optimum
Bitumen Content
4.5% - 6.5%
5.0& - 8.0%
Stability, not less
than
3.5KN
3.5KN
Flow
2mm – 6mm
2mm – 4mm
Voids in total
mixture
3%-8%
3% - 5%
Voids filled with
bitumen
65% - 72%
75% - 82%
The exact job-mix formula will depend on the nature and grading of the aggregate and the
grade of bitumen and will be determined by the Engineer
using the marshall method of mix design. For this
purpose the Contractor shall supply to the Engineer
without charge adequate samples (in separate containers)
of coarse and fine aggregates and bitumen, which he
intends to use. The Engineer will, after testing, furnish
the Contractor with the exact job-mix formula, which will
be within the specified limits.
Before any asphaltic concrete is laid, the Contractor shall produce sufficient dry mixes in the
plant and carry out sieve analysis to ensure that the
correct grading is being obtained. In addition he shall
produce a number of trial mixes to which the specified
quality of bitumen has been added. He will then carry out
extraction tests on this material and further sieve analysis
on the aggregate in accordance with clause 6373 of the
specification. The results of these tests on both the dry
and wet mixes shall be approved by the Engineer before
any surfacing is laid in the permanent works.
JOB MIX FORMULA DEFINED:
The job-mix formula is the single definite percentage of aggregate passing each required
sieve size, a single definite bitumen content to be added to
the aggregate, a single definite temperature at which the
mixture is to be emptied from the mixer and a single
definite temperature at which the mixture is to be
delivered on the road.
Unless specifically changed in writing by the Engineer,
the maximum permissible variation from the job-mix
formula shall be as follows:
TABLE VI-18: PERMISSIBLE VARIATION
PERCENT BY WEIGHT OF TOTAL MIX
PERMISSIBLE
VARIATION %
BY WEIGHT OF
TOTAL MIX
± 5%
± 4%
± 3%
± 0.1%
± 0.3%
Passing sieve 9.5mm and layer
Passing sieve 9.5mm - 600µm
Passing sieve 600µm - 150µm
Passing sieve 150µm - 75µm
Bitumen content
Notes:
Temperature of Mixture when
emptied from mixer
Temperature of Mixture
on delivery on the road
145°C ± 5°C
130°C ± 5°C
The job-mix formula is liable to alteration by the Engineer throughout the progress of the
work but at all times it will be within the specified limits.
PREPARATION
6375. (1)
PREPARATION OF AGGREGATES
The coarse and fine aggregate shall be separately fed by feeders to the cold elevator or
elevators in their proper proportions and at a rate to
permit correct and uniform temperature control of the
heating and drying operation.
The aggregate shall be heated before entering the mixer to a temperature range of 120°C –
149°C. All aggregates in the bins of a temperature that
will produce a mix outside the limits stated above or that
contain moisture or expanding gases to cause “Foaming”
in the mixture, shall be removed and replaced in their
respective stock piles. All aggregates that have been
overheated shall be cooled before being deposited in the
feeder. All unsuitable aggregates that may be in the
weigh box or that become combined in the process of
“Pulling” the bins shall be discarded.
The screening efficiency shall be maintained within the
limits set forth in Clause 6383. When these limits are
exceeded, the material shall be discarded and the cause
for such condition shall be corrected.
(2)
PREPARATION OF ASPHALT CEMENT
The asphalt cement shall be delivered to the asphalt
bucket at a temperature between 135°C and 163°C. All
asphalt cement heated beyond 177°C at the plant before
mixing or heated beyond 163°C during the mixing shall
be rejected. No asphalt shall be used while “foaming”.
(3)
PREPARATION OF MIXTURES
The exact proportions within the limits specified for each
mix shall be regulated so as to produce a satisfactory
mixture with all particles uniformly coated with bitumen.
When batch mixing is used, the aggregate at the
temperature specified, shall be mixed dry for a minimum
of 15 seconds; the asphalt cement shall then be added in
an evenly spread sheet over the full length of the mixer.
The mixing shall be continued for a minimum of 30 to 45
seconds for all mixtures.
The “initial time of mixing” shall be the interval of time
between the opening of the weigh box and the opening of
the mixer gate. The number of batches produced in one
hour from the mixer shall not exceed 60.
When continuous mixing is used the dry aggregates shall
be thoroughly mixed before the addition of the asphalt
cement. The asphalt cement shall then be added in an
evenly spread sheet over the full width of the mixer by
means of spray bars. The mixing shall b continued for a
period of not less than 30 seconds. The “total time for
mixing” shall be the ratio of the “dead load” in the mixer
to the kilograms per minute delivered. The kilograms per
minute delivered shall be determined by timing and
weighing a load of mixed material. The “dead load” shall
be determined by weighing the “mixer-full” of material.
The dry mixing shall be the product of the ratio of dry
mixer length to the total mixer length and total mixing
time. The Engineer may vary the length of the dry and
wet mixing periods, but under no circumstances shall the
total mixing time be less than 45 seconds.
The mixture shall be loaded into trucks in such a manner
that segregation will not occur.
The temperature of the mixture on arrival at the project
site shall be as determined by the Engineer in keeping
with the temperature range set for the mix design and heat
losses in transit.
TRANSPORTING
MIXED
MATERIALS
6376.
The mixed materials shall be transported from mixing
plant to site in clean metal lined vehicles. Every precaution is to be taken to avoid segregation of mixed
materials and to ensure that they do not become
contaminated with dust or foreign matter. Covers such as
waterproof canvas and other insulation shall be provided
when directed.
PREPARATION
OF AREA TO BE
PAVED
6377.
The area to be paved shall be true to line and grade,
having a dry and properly prepared surface prior to the
start of paving operations. The area to be paved shall be
free from all screenings, and other loose or foreign
material.
Where a base is rough or uneven, a levelling course shall
be placed by use of a motor grader or spreader and shall
be properly compacted before the placing of subsequent
paving courses.
When a levelling course is not required, all depressions
and other irregularities shall be patched or corrected in a
manner satisfactory to the Engineer. All fatty and
unsuitable patches, excess crack or joint filler and all
surplus bituminous material shall be removed from the
area to be paved. Blotting of excessive deposits of
asphalt with sand or stone shall not be permitted.
Where the area to be paved is an untreated soil or
aggregate, it shall be primed. The prime coat shall
consist of an application of the asphaltic material
indicated, and at the rate specified in clause 6370. The
prime coat shall be allowed to cure properly before any
further operations are permitted on the primed area.
A tack coat shall be applied when the surface to be paved
is an existing Portland Cement concrete, or dry asphalt
pavement. When a tack coat is required, it shall consist
of an application of the asphaltic material indicated, and
at the rate specified in clause 6370.
In all cases, the emulsion shall be allowed to break before
laying. Prior to application of the tack coat, all loose or
objectionable material will be removed from the surface
by brooming or other approved method. After cleaning,
the surface shall be inspected by the Engineer before the
tack coat is applied. The tack coat will be applied evenly
and by mechanical sprayer of approved type which is to
comply with B.S. 1707.
Where the time between the completion of one surface
course and the laying of the subsequent surface course
exceed 72 hours, a tack coat shall be applied to the
preceding course as above, but at a rate of spread of 4 –
4.5 square metres per litre. Such tack coat shall be at the
Contractor’s expense unless compliance with the 72 hours
limit was impracticable.
Tack coats shall be applied 24 hours in advance of
bituminous surfacing work, or such longer period as is
necessary to ensure complete breaking of the bitumen
emulsion before bituminous surfacing are laid thereon.
Traffic shall not be allowed on the tack coat before
surfacing work begins.
Concrete kerbs, channels and similar objects shall be
adequately masked and protected during the application
of tack coats.
The surface of curbs, gutters, vertical faces of existing
pavements and all structure in actual contact with asphalt
mixes shall be painted with a thin uniform coating of
asphalt material to provide a closely bonded water-tight
joint.
TRIAL AREAS
6378.
The first 30 metres of the approved bituminous mixture,
which is laid by each spreader shall be regarded as a trial
area in order to establish a rolling procedure which will
produce the required field density.
At least four samples of the material after rolling will be
taken in accordance with part 1 section 3 of B.S. 598:
when the work is at least 12 hours old in order to
determine the degree of compaction.
If the required density determined in accordance with
clause 6381 is not obtained, the field rolling procedure will
be changed so as to achieve the desired field density and the
trial area will be cut out and replaced to the satisfaction of
the Engineer.
After mixing, the material must not be reheated other
than by the means provided in or on the spreading machine.
Materials must not be laid when the surface on which it
is to be placed is wet or when rain appears imminent.
It is essential that the material be laid at a temperature not less than 121°C and not more than
163°C. The Contractor is to provide at each spreader and
finisher a suitable thermometer for testing the temperature
of the material as it is being spread and is to take such
temperature readings continually and record them hourly
throughout each day’s laying. This record shall be
available for inspection by the Engineer who will himself
make such additional temperature checks, as he considers
desirable.
The materials shall be laid by approved mechanical paver in accordance with clause 6384.
The spreader paver shall be in good mechanical condition
and shall be capable of laying to the required width and
profile without causing segregation, dragging, burning,
irregularities or other surface defects. When not operated
on side forms, the paver will employ equalizing runners,
evener arams or other automatic compensating devices to
adjust the profile and confine the edges of the course to
true lines.
As soon as the first load of material has been spread, the texture of the unrolled surface shall
be checked to determine its uniformity. The adjustment
of the screed, tamping bars, feed screws, hopper feed,
etc., shall be checked frequently to ensure uniform
spreading of the mix to proper line and grade and
adequate initial compaction. Segregation of materials
shall not be permitted. If segregation occurs, the
spreading operation shall be immediately suspended until
the cause is determined and corrected.
Any irregularities in alignment left by the paver shall be corrected by trimming directly
behind the machine. Immediately after trimming, the
edges of the course shall be thoroughly compacted by
tamping. Distortion of the pavement during this operation
shall be avoided.
Edges against which additional pavement is to be placed shall be vertically formed to true
line. A rake shall be used immediately behind the
finisher, when required, to obtain a true line and vertical
edge. Any irregularities in the surface of the pavement
course shall be corrected directly behind the paver.
Excess material forming high spots shall be removed by a
shovel. Indented areas shall be filled with hot mix and
smoothed with the back of a shovel being pulled over the
surface. Fanning of materials over such areas shall not be
permitted.
The mixer capacity and the operating speed of the spreader shall be so adjusted as to ensure
continuous laying and to avoid intermittent stopping of
the spreader as far as is practicable.
Hand spreading will not be permitted for general work,
but will only be allowed for filling localized depressions, or
as directed by the Engineer.
Hand laying of any bituminous material will only be
permitted in the following circumstances:
(i)
for laying regulating courses of irregular shape
and varying thickness
(ii)
in confined spaces where it is impracticable for a
paver to operate.
(iii)
for footways
(iv)
at the approaches to expansion joints at bridges or
viaducts
When a paver laying base material approaches an
expansion joint at a bridge or viaduct it shall be taken out
of use as soon as there is a danger of the material being
laid fouling the joint. In laying the remainder of the
pavement up to the joint and the corresponding area
beyond it by hand, the joint or joint cavity shall not be
fouled with surface material.
Hand-raking of wearing course material which has been
laid by a paver and the addition of such material by handspreading to the paved area for adjustment of level will
only be permitted at the edges of the layers of materials or
where otherwise directed by the Engineer.
Where hand spreading and tamping is permitted, the
mixed material is to be dumped on delivery upon existing
hard clean surface or on approved metal sheets outside
the area where it is to be spread and shall be distributed in
to place immediately by means of hot shovels. It shall be
spread with hot rakes in a uniformly loose layer to the
depth required.
Materials are to be laid to the depths necessary to give the
required thickness after compaction and they are to be
finished true to profile.
The Contractor shall break out and remove at his own
expense any asphaltic concrete laid in trial areas if such
asphaltic concrete fails to meet the specified requirements
for asphaltic concrete surfacing.
If for any reason the quality, grading or supply source of
aggregates or the quality or source of bitumen is changed,
or at any time the cause of variations outside the
permissible limits cannot be corrected for reasons beyond
the contractor’s control, the engineer may require the
contractor to carry out additional laboratory tests and/or
the construction of additional trial areas depending on the
extent of the change or variation.
COMPACTION
6379.
After spreading, the mix shall be thoroughly and uniformly compacted by rolling
The initial “breakdown” rolling shall be done with three
wheel smooth roller, followed by intermediate rolling
with high-pressure tyred pneumatic roller. The final
rolling shall be with a tandem roller. During rolling, the
roller wheels shall be kept moist with only sufficient
water to avoid picking up material.
Heavy equipment or rollers shall not be permitted to stand
on finished surface until it has thoroughly cooled. In the
initial rolling the three-wheel smooth roller shall proceed
on to the fresh material with the rear or driven wheels
leading. The rolling shall start as soon after laying as
conditions permit and when the material is still at a
temperature of not less than 99°C. The weight per unit
width of the rear wheel shall be between 45 – 65 Kg per
centimetre width.
After the longitudinal joints and edges have been
compacted, rolling shall start longitudinally at the sides
and gradually progress towards the centre of the
pavement, except on super-elevated curves where rolling
shall begin on the low side and progress to the high side.
Each pass of the roller shall overlap the preceding one by
about one half width of the rear wheel. The roller should
move at a slow but uniform speed not exceeding 8
kilometres per hour. The roller shall be in good
condition, and capable of being reversed without
backlash, and the line of rolling shall not be suddenly
changed or the direction of rolling suddenly reversed,
thereby displacing the mix.
If rolling causes
displacement of the material, the affected areas shall be
loosened at once with shovels or rakes and restored to the
original grade of loose material before being re-rolled.
The intermediate rolling shall be done with a pneumatic roller exerting compactive ground
pressures between 5-6 – 8.4 kilograms per sq.cm. The
Contractor shall furnish to the Engineer charts or
tabulations showing the contact areas and contract
pressures for the full range of tyre inflation pressures and
for the full range of tyre loadings for each type and size
compactor tyre furnished. The intermediate rolling shall
follow the breakdown rolling as closely as possible and
while the mix is still at a temperature of 70°C – 85°C.
Rolling shall be continuous until the mix is thoroughly
compacted and the density specified in Clause 6381 is
achieved. Turning of pneumatic rollers on the hot mix,
which causes undue displacement, shall not be permitted.
The final rolling shall be accomplished with two-wheel
tandem roller while the material is still warm enough for
the removal of roller marks.
JOINTS 6380. All joints shall be vertical, properly formed to the correct line and level; if
necessary they shall be cut back to achieve this. A
template made to the shape of the true line and width may
be placed at each end of the construction joint line and
width may be placed at each end of the construction joint
to create vertical straight finish. Joints in the surface
course should be staggered with those in the binder course
and must be kept straight, when the abutting lane is not
placed the same day or if the edge of the first strip has
been distorted by traffic, the joint shall be cut back to an
even line and then be coated with bitumen before laying
the adjoining strip. All joints on completion are to
present the same texture, density and smoothness as other
sections of the course.
FIELD DENSITY 6381.
ROLLED ASPHALT
Density tests of the asphalt surfacing after compaction
shall be taken from the trial area and later at intervals
throughout the course of the work and compared with the
density of control specimens taken from the same
material before laying, all in accordance with the
following procedure:
(a)
A sample of mixed material will be taken from a
lorry before the material is delivered to the
spreader, and three specimens shall be made and
their density measured by the Engineer by the
immersion method.
The average of the two close specimens will be
taken as the control density of that particular
batch.
(b)
The pavement will be marked to show where the
lorry load of material (from which the sample was
taken) is laid, so that field density samples can be
taken for comparison with the control specimen.
(c)
After completion of rolling, three samples are to
be cut from each area so marked in positions
indicated by the Engineer.
(d)
The samples shall be taken in accordance with
part 1 section 3 of B.S. 598 (1974) and the density
calculated by weighing in air and weighing in
water in accordance with part 6 of B.S. 598
(1974). The average of two close results of the
samples will be taken as the density of the
compacted material in that area.
(e)
This density will not be less than 100% of the
control density determined as above.
When
approved
rolling procedure
has
been
established, each course will be sampled in accordance
with the above at the rate of one sample area for each 84
square metres placed or one sample area every 2 hours
(whichever is more frequent). Material which does not
achieve the required density will either be cut out and
replaced or be further compacted until the required
density is obtained.
FINISHED
6382.
an
The surfacing will be finished to the required levels
shown on the drawings. Any deviation exceeding 5 mm
from these levels will be corrected at the Contractor’s
expense by scarifying, cutting out and removing all
loosened materials, adding new materials, as required,
reshaping and rolling. No materials loosened by
scarifying or cutting out, will be left in position or
otherwise reused.
LEVELS
Except across the crown of a camber, the finished surface
shall be of such smoothness that when tested with a 3
metre straight edge placed anywhere and in any direction
on the surface, there shall not be a gap greater than 3mm
between the bottom of the straight edge and the surface
of the pavement anywhere along the straight edge.
Should the new asphalt surface be dragged, churned up,
become soft, show signs of segregation, show that
stripping of the binder from the aggregate has occurred or
suffer other damage during or after being laid, the
Contractor will remove the damaged or faulty work at his
own expense and replace with fresh material, laid and
compacted to the correct level and density to the approval
of the Engineer.
ASPHALTIC
MIXING PLANT
6383. (1)
(2)
GENERAL EQUIPMENT REQUIREMENT
All equipment furnished by the Contractor shall be of
approved design and shall be maintained in its best
mechanical condition. Equipment shall be serviced and
lubricated away from the paving site; units that drip fuel,
oil and grease shall be removed from the project until
such leakage is corrected to the satisfaction of the
Engineer. This is necessary because fuel leakage can be
injurious to newly laid asphaltic concrete.
ASPHALTIC PLANT SITE
The plant site shall have sufficient storage space for
separate stock piles; bins or stalls for each size of
aggregate, and the different aggregate sizes shall be kept
separately until they have been delivered by the feeder or
feeders to the boot of the cold elevator or elevators in
meat and orderly condition and the separate stock pile
shall be readily accessible for sampling. Samples from
each bin shall be graded from time to time for conformity
to design size otherwise adjustment may be necessary.
(3)
THE ASPHALTIC CONCRETE PLANT
The plant shall be either the batch mixing type or the
continuous mixing type meeting the following
requirements.
(A)
REQUIREMENTS FOR ALL PLANTS
(I)
UNIFORMITY: The plants shall be so
designed, co-ordinated and operated to
produce a mix uniformly within the jobmix
tolerances as specified in Clause 6374,
Table VI-18 Paragraph 5.
(II)
EQUIPMENT FOR PREPARATION OF
ASPHALT
Tanks for storage of asphalt shall be
provided with a device for controlled
heating of the material to temperature
requirements set forth in the specification.
Heating shall be accomplished by steam or
oil coils, electricity or other means such
that no flame shall come in contact with
the heating tank. All lines shall be checked
periodically under full pressure for
leakage. All line valves shall have clear
and permanent markings to indicate all
openable and closable positions. A
circulating system for the asphalt of
adequate size to ensure proper and
continuous circulation between storage
tank and mixer during the entire operating
period shall be provided. All pipe lines and
fittings shall be properly insulated and
heated. The discharge end of the
circulating pipeline shall be maintained
below the surface of the asphalt in the tank
while the pump is in operation. Storage
tank capacity shall be sufficient for at least
one day’s run.
(III)
COLD AGGREGATE FEEDER
The plant shall be provided with an
accurate mechanical means for uniformly
feeding the mineral aggregate into the drier
to secure a uniform production and a
uniform temperature. The feeder or feeders
shall be capable of delivering the
maximum weight of aggregate sizes
required in their proper proportion. The
feeder shall provide for adjustment of total
and proportional feed and be capable of
being locked in any position. When more
than one cold elevator is used each shall be
fed as a separate unit and the individual
controls shall be integrated with a total
master control.
(IV)
DRIER
The plant shall include a rotary drum drier
that will continuously agitate the mineral
aggregates during the heating and drying
process. It shall be capable of heating and
drying all aggregates specified in the
necessary quantities to supply the mixing
unit continuously at its operating capacity
and at the temperature and maximum
bitumen content specified.
(V)
SCREENS
The plant shall have screens of the shaker
or vibrating type and be capable of
screening all aggregates to the sizes
required for proportioning. The screens
shall have normal capacity slightly in
excess of the full capacity of the mixer or
the drier. The plant screens shall have an
efficiency such that when measured by
weight there will be not more than 5% of
oversize material in bin n. 1 (fine
aggregate), not more than 15% undersize
and/or 10% oversize in bin n. 2 and not
more than 20% undersize and/or 5%
oversize in bin n. 3, and not more than 20%
undersize and/or 0% oversize in bin n. 4.
The Contractor shall expose the screens for
inspection at the request of the Engineer.
These screen tolerances are for general
guidance and shall not invalidate the
specific job-mix tolerances.
(VI)
BINS
Bins shall be divided into at least three
compartments for any mix composition
other than a base (binder) composition, and
at least four comportments for a wearing
course. They shall be arranged to ensure
separate storage of the appropriate
fractions of aggregate. The bin sizes shall
be adequate for continuous operation of the
plant at rated capacity. Adequate additional
dry storage shall be provided for mineral
filler when required and provision made for
proportioning it into the mix.
Each compartment shall be provided with
an overflow pipe that shall be of such size
and location as to prevent any backing up
of material into other compartments or bins
or against the screens. The overflow
material shall be wasted.
(VII) ASPHALT CONTROL UNIT
Satisfactory means, either by weighing,
metering or volumetric measurements,
shall be provided to obtain the required
amount of asphalt in the mix within the
tolerances specified. Where the quantity of
asphalt is controlled by metering, provision
shall be made whereby the amount of
asphalt delivered though the meter may be
readily checked by weight. Suitable steam
jacketing or other insulation for
maintaining the specified temperature of
asphalt in pipe lines, metres, weigh
buckets, spray bars, flow lines or other
containers shall be provided.
(VIII) THERMOMETRIC EQUIPMENT
An armoured thermometer reading from
90°C to 205°C shall be fixed in the asphalt
feed line at a suitable location near the
discharge valve at the mixer unit. The plant
shall be further equipped with an approved
dial-scale, mercury-actuated thermometer,
a recording electric pyrometer or other
approved thermometric instrument having
an accuracy of ± 2°C and a sensitivity
which will provide an indication of
temperature change at the rate of not less
than 5°C per minute. It shall be so placed at
the discharge chute of the drier to register
automatically or indicate the temperature
of the heated aggregate. The Engineer shall
have the right to test the efficiency of
thermometric instruments for better control
of asphalt, aggregate and mix temperatures.
The Engineer shall direct the immediate
repair or replacement of any instrument
yielding inaccurate
or
inconsistent
readings.
(IX)
DUST COLLECTOR
The plant shall be provided with a dust
collector, designed to waste, or return
uniformly to the hot elevator, all or part of
the material collected as directed by the
Engineer. Prior to permitting the return of
such collected dust, the Engineer shall
examine its characteristics in relation to the
mix requirements and shall designate the
quantity to be returned. When dust is
permitted to be returned to the hot elevator,
it shall be accomplished by mechanical
means in a constant and uniform flow. All
plants shall have mixer covers and such
additional housing as may be necessary to
ensure the proper collection of dust.
(X)
SAFETY REQUIREMENTS
Adequate and safe stairways to the mixer
platform and guarded ladders to other plant
units shall be provided. All gears, pulleys,
chains, sprockets and other dangerous
moving parts shall be well guarded and
protected. Ample and unobstructed space
shall be provided on the mixing platform.
A clear and unobstructed passage shall be
maintained at all times in and around the
track loading space. This space shall be
free from dripping from the mixing
platforms. A ladder, or platform, shall be
so located at the truck loading space to
permit easy and safe inspection or
sampling of the mix as it is delivered into
the truck. Adequate overhead protection
should be provided where necessary. It is
the Contractor’s responsibility to ensure
the plant or the plant site shall be free from
fire hazard.
(XI)
MIXING TIME
All plants shall be equipped with a positive
means to govern the time of mixing.
(B) SPECIAL REQUIREMENTS FOR BATCH
TYPE PLANTS
(I)
PLANT SCALE
Scales for any weigh-box or hopper may be
of either the beam or springless dial type
and shall be of a standard make and design,
accurate to 0.005 of the indicated load.
When scales are of the beam type, there
shall be tare beam for balancing the hopper
and a separate beam shall be provided
which shall be capable of functioning when
the load being applied is within 45
kilograms of the weight desired. Each
beam shall have a locking device designed
and so located that the beam can easily be
suspended or thrown into action.
Dial scales shall be springless and of a
standard make. They shall be designed,
constructed and installed in such a manner
as to be free from vibration. They shall also
be of such size that the numerical figures
on the dial can be read at a distance of 3
metres. All dials shall be so located as to be
plainly visible to the operator at all times.
The end of the pointer shall be set close to
the face of the dial and shall be free from
excessive parallax. The scale shall be
provided with adjustable pointers for
marking the weight of each material to be
weighted into the batch, which shall
automatically cut off feeder system when
the required weight is attained.
Scales for the weighing of asphalt shall
conform to the requirements for aggregate
scales, except that beam scales shall consist
of a full capacity beam and a tare beam.
The minimum graduation shall not be
greater than 1 kilogram and there shall be
attached a tell-tale device which will start
to function when the load being applied is
within 10 kilograms of the weight desired.
Dial scales for weighing the asphalt shall
read to the nearest 450 gr. All scales for
weighing the asphalt shall have a capacity
of not more than 15% of the normal
capacity of the mixer.
Scales shall be satisfactory to the Engineer
and shall be tested and sealed as often as
the Engineer may deem it necessary to
ensure their accuracy. All weighing
equipment
shall
be
substantially
constructed and of a design which will
permit easy realignment and adjustment.
Weighing equipment that easily gets out of
adjustment shall be replaced when so
ordered. The Contractor shall provide and
have at hand at least ten 25 kilogram
standard weights for frequent testing of all
scales. For each scale, a suitable cradle, or
platform, shall be provided for applying the
test load so that the load is uniformly
distributed. The test weights shall be kept
clean and stored near the scales.
Volumetric proportioning of heated and
screened aggregates shall be permissible
provided the volumetric system is standard
equipment furnished with the plant when
first sold by the manufacturer. Convenient
and accurate scales and facilities shall be
provided for checking the measuring
devices by weight.
(II)
BINS
In addition to the requirements stated in
clause 6383 (3A) each compartment shall be
provided with its individual outlet gate,
designed and constructed so that when closed
there shall be no leakage into the weigh box.
The gates shall be cut off quickly, completely
and easily and prevent excessive overdrawn.
(III)
WEIGH BOX OR HOPPER
Equipment shall include a means for
accurately weighing each bin size of
aggregate in a weigh box or hopper
suspended on scales ample in size to hold a
full batch without hand raking or running
over. The weigh box or hopper shall be
supported on a fulcrum with knife edges
and shall be so constructed that they will
not easily be thrown out of alignment.
Gates on hopper shall be so constructed as
to prevent leakage when they are closed.
Proportioning of aggregates and charging
of mixer shall be performed so as to blend
the aggregates thoroughly and prevent
segregation in the mixer.
(IV)
ASPHALT MEASURING EQUIPMENT
Asphalt measuring equipment provided on
the plant shall be capable of accurately
measuring into each batch the required
amount of asphalt within a tolerance of
±0.3%.
When an asphalt bucket is used, it shall be
a non-tilting type provided with a loose
sheet-metal cover. The capacity of the
asphalt bucket shall be at least 10% in
excess of the weight of asphalt required for
a one-batch mix. The plant shall have a
steam-jacketed quick-closing, nondripping, charging valve. The length of the
discharge opening or spray bar shall not be
less than three-fourths of the length of the
mixer and it shall discharge directly into
the mixer. The discharge system shall be
designed and arranged to deliver the
asphalt the full length of the mixer in a
thin, uniform sheet or in multiple streams
or sprays except in the case of a rotary
mixer where the asphalt is sprayed.
When a volumetric meter is used, the meter
shall be designed and constructed so that it
will automatically meter the asphalt into
each batch. The dial to indicate the amount
of asphalt shall have a capacity of at least
10% in excess of the weight of asphalt
required in one batch. The meter shall be
constructed so that it may be locket at any
dial setting and will automatically reset to
this reading after the addition of asphalt to
each batch. The dial shall be in full view of
the mixer operator. The flow of asphalt
shall be automatically controlled so that it
shall begin when the dry mixing period is
over and all of the asphalt required for one
batch shall be discharged in not more than
15 seconds after the flow has started. The
size and spacing of the spray bar openings
shall provide a uniform application of
asphalt the full length of the mixer. The
section of the asphalt flow line between the
charging valve and the spray bar shall be
provided with a valve and outlet for
checking and testing the accuracy of the
meter.
(V)
MIXER
The plant shall have a mixer of approved
type such as standard twin pug-mill batch
type, steam-jacketed and a batch capacity
of not less than 1000 kilograms. It shall be
capable of producing a uniform mix within
the job-mix tolerances established by the
Engineer. Deviation in size of batches will
be permitted to provide for mixing batches
20% below or 15% above the rated
capacity of the mixer, provided the quality
of the mix is not impaired. The paddles
shall be set in such a manner to ensure a
completely uniform mix. If not enclosed,
the mixer box shall be equipped with a dust
hood to prevent loss of dust. The mixer
shall be so constructed as to prevent
leakage of contents until the batch is to be
discharged.
(VI)
TIME LOCK AND BATCH COUNTER
The mixer shall have an accurate time lock
to control the operation of a complete
mixing cycle by locking the weight box
gate after the charging of the mixer, until
the closing of the mixer gate at the
completion of the cycle. The time lock
shall also lock the asphalt bucket
throughout the dry mixing period and shall
lock the mixer gate throughout the dry and
wet mixing periods. The dry mixing period
is the interval of the time between the
opening of the weigh box gate and the
application of asphalt. The wet mixing
period is normally the interval of time
between the application of all asphalt and
the opening of the mixer gate for discharge.
When asphalt is applied by a spray system,
the wet mixing time shall begin with the
start of asphalt spray.
The Engineer shall, after tests of a few trial
mixes, designate the length of both dry and
wet mixing periods to ensure a uniform and
completely coated mix. Excessive wet
mixing shall be avoided. Control of the
timing shall be flexible, permitting timed
intervals of not less than five seconds
throughout cycles up to three minutes. A
mechanical batch counter, designed to
register only completely mixed batches
shall be installed.
(C)
SPECIAL
CONTINUOUS MIXING PLANTS
(I)
REQUIREMENTS FOR
BINS
In addition to the requirements stated in
clause 6383 (3A), each compartment shall
have sufficient capacity to ensure the
minimum depth of aggregate necessary for
the proper cut-off action of the bin outlet
and to compensate for normal variation in
depth due to aggregate grading. The bin
partitions shall extend close enough to the
apron or vibrating plate to prevent
crossflow of the unstrucked material.
(II)
GRADATION CONTROL UNIT
The plant shall include a means for
accurately proportioning each bin size of
aggregate either by weight or by
volumetric measurement.
When gradation control is by volume, the
unit shall include a feeder mounted under
the compartment bins. Each bin shall have
an accurately controlled individual gate to
form an orifice for volumetrically
measuring the material drawn from each
respective bin compartment. The orifice
shall be rectangle, with one dimension,
adjustable by positive mechanical adjuster
and provided with a lock. Indicators shall
be provided on each gate to show the gate
opening in millilitres. Mineral filler, if
specified, shall be proportioned separately
from a suitable hopper equipped with an
adjustable feed which may be accurately
and conveniently calibrated and which
shall be interlocked with the aggregate and
asphalt feeds. The feeder equipment for
the mineral filler shall meet the approval
of the Engineer.
(III)
CALIBRATION AND SAMPLING
The Contractor shall provide qualified
personnel to calibrate the plant so that it
will produce the specific composition of
mixture within the accuracy and
uniformity tolerances specified.
The plant shall be calibrated at the
beginning of each project and whenever
there is any change in source, size or unit
weight of aggregate. The plant shall be recalibrated whenever the actual weigh of
bituminous concrete varies from its
theoretical weight by more than the
specified limit or when the tolerance set
forth in “formula for job-mix” for the
specified item are exceeded.
The plant shall be equipped so that bin
samples weighing approximately 4.5 kg
can be conveniently obtained without
intermingling or segregation of the
aggregate.
(IV)
SYNCHRONIZATION OF
AGGREGATE AND ASPHALT FEED
Satisfactory means shall be provided to
afford positive interlocking control
between the flow of aggregate from the
bins and the flow of asphalt form the
meter or other proportioning device. This
control shall be accomplished by
interlocking mechanical means or by any
positive method approved by the
Engineer capable of being controlled by
the operator. The aggregate bins shall be
provided with automatic controls and
signal devices which will warn of low
levels and which will automatically stop
the flow of all aggregate and asphalt to the
mixer when the aggregate in any one bin
is so low that the feeder will not operate at
set capacity.
The asphalt storage system shall be
provided with automatic controls and
signal devices which will warn of low
levels of asphalt and which will
automatically stop the entire plant
operation when the asphalt storage level is
to the point of exposing the feed end of
the asphalt suction line.
(V)
MIXER
The plant shall have a steam-jacketed,
twin-pugmill, continuous type mixer of not
less than 700 kilograms per minute rated
capacity. The mixer shall be in first class
condition equipped with a sufficient
number of blades of paddles and operated
at such a speed as to produce a properly
and uniformly mixed composition within
the job-mix tolerance specified. The
paddles shall be of a type adjustable for
angular position on the shafts and
reversible by remote control to retard the
flow of the mix. The mixer shall carry a
manufacturer’s plate giving the net
volumetric contents of the mixer at the
several heights inscribed on the permanent
gauge. The mixer shall have a cut off gate
at its discharge and adequately sealed
against leakage between truck loads. The
determination of mixing time shall be by a
weigh method under the following method
unless otherwise required:
Mixing time in seconds =
Pugmill dead capacity in kilograms
Pugmill output in kilograms per second
The weights shall be determined for the job
from the tests made by the Engineer.
(VI)
ASPHALTIC
CONCRETE
PAVERS
6384.
TRUCK SCALES
The Contractor shall provide conveniently
accessible platform trucks scales at the
plant site for use in obtaining the net
weight of each load of finished mix.
Bituminous concrete pavers shall be self-powered
machines capable of spreading and finishing the
mixtures true to the line, grade and crown with or
without the use of forms or side supports. For twolane
construction, pavers shall be capable of laying to half
widths plus or minus 150 mm. The screed assembly shall
be such that it will be capable of laying courses from a
minimum of 2.5 metres in width in steps of 150 mm to a
maximum of 3.85 metres in width.
Pavers shall employ mechanical devices such as
equalizing runners, straight-edge runners, evener arms or
other compensating devices that will adjust the grade and
confine the edge of the courses to true lines.
Pavers shall be equipped with hoppers and distributing
screws of the reversing type to evenly place the mixtures
in front of the screeds.
The screed shall be a strike-off device operated by
cutting, crowding or other practical action which is
effective on the mixtures without tearing, shoving or
gouging and which produces a finished surface without
segregation. The screed shall e adjustable as to level and
shall have an indicating level attached thereto in full view
of the operator.
The pavers shall be further equipped with blending or
joint levelling devices for smoothing and adjusting all
longitudinal joints between adjacent stripes of surface
course.
The paver shall be capable of being operated at variable
forward speeds consistent with the satisfactory laying of
the mixtures.
The paver shall be equipped with an efficient steering
device and shall be capable of travelling both forward and
in reverse.
ROLLERS
Rolling equipment shall consist of steel-wheel and
pneumatic tyre rollers or a combination of both described
as follows:
(A)
STEEL-WHEEL ROLLERS May be of three types:
Three-Wheel Rollers of 10 to 12 tonne in weight
Two –Axle Tandem Rollers of 7 to 12 tonne in
weight and
Three-Axle Tandem Rollers o f12 to 16 tonne in
weight
These rollers shall be equipped with power units
of not less than four cylinders and under working
conditions shall develop a compression in the rear
wheels of 45-65 kg per centimetre of roller width.
Rollers shall be in good working condition and be
free from backlash, faulty steering mechanism or
worn parts. Rollers shall be equipped with
adjustable scrapers to keep the rolls clean and
with efficient means of keeping the wheels wet to
prevent mixes from sticking to the rolls. Rollers
shall also be free of flat areas, openings or
projections, which will mar the surface of the
pavement.
The Three-Axle Tandem Rollers shall be so
constructed that, when locked in position for all
treads to be in one plane, the roller wheels are
held with such rigidity that, if either front or
centre wheel is unsupported, the other two wheels
will not vary from the plane by more than 6mm.
(B) The pneumatic-tyre rollers shall be self propelled,
multiple-axle
multiple-wheel
type
with
smoothtread pneumatic tyres of equal size and
diameter. The tyres shall be staggered on the axles
at such spacings and overlaps as will provide
uniform compactive pressure for the full
compacting width of the roller, when operating.
Oscillation of the wheels, if provided, shall be in
vertical plane only. The pneumatic tyred roller
shall be capable of:
(I)
(II)
being ballasted sufficiently to bring its
loaded weight to at least 2½ times its own
weight
exerting compactive ground pressures at
least 5.6 kilograms per square centimetre
5.6 – 8.4 kg/cm2 preferred
Vehicles used for the transportation of hot-mix
asphalt form the plant to the site of work shall
have tight metal bottoms and shall be free from
dust, screenings, petroleum oils, volatiles or other
mineral spirits which may affect the mix being
hauled. The truck beds shall be painted or sprayed
with a lime-water or soap solution, at least once a
day or as often as required. After this operation
the truck bed shall be elevated and thoroughly
drained, no excess solution shall be permitted.
When ordered by the Engineer, trucks shall be
suitably insulated and provided with covers of
canvas or other material of sufficient size and
weight to protect the load from adverse weather
conditions. When variations in size, speed and
condition of trucks are such as to interfere with
orderly and continuous operation, the Engineer
may order suitable substitutions to be made.
INSPECTION
AND CONTROL
OF ASPHALT
MIXING PLANT
6385. (1)
GENERAL PROVISIONS
For verification of weights and measures, character and
quality of materials and determination of temperatures
used in the preparation of the paving mixes, the
Engineer or his Representative shall at all times have
access to all portions of the paving plant, aggregate plant,
storage yards and other facilities for producing and
processing the materials of construction. All sampling and
testing of processed and unprocessed material shall be
under the control and direction of the Engineer.
(2)
JOB-MIX FORMULA
(3)
The Engineer shall make frequent gradation analyses of
the hot aggregate and of the completed mix to be certain
that the materials being used and produced are within the
tolerances of the job-mix formula and the specifications of
the mix number being used. If the mix is found to be
outside of the job-mix formula tolerances, or outside of the
specification limits, correction shall be made in quantities
measured from the hot bins and suitable changes made at
the cold bin feeders.
SAMPLING AND TESTING
Stockpiles and bins shall be sampled for gradation
analysis, dust coating and for other purposes, at the option
of the Engineer. Gradation analysis of material from each
hot bin shall be performed and combined analyses
computed at least twice a day – once in the forenoon and
once in the afternoon. A combined gradation and analyses
shall be performed at least twice a day. If materials do not
run uniform, more frequent tests shall be made.
When requested by the Engineer, the Contractor shall
provide representative samples from each of the hot bins
from convenient doors in the side of each bin, or by
drawing aggregate from each bin through the mixing
chamber (without asphalt) into a trunk or other receptacle.
At least one sample shall be taken form each 250 tonne of
the mix being produced. Samples shall be used to
determine compliance with general and special
requirements.
PLANT TESTING LABORATORY
At each plant site, there shall be provided a testing
laboratory for joint use of the producer’s quality control
and acceptance testing functions, and the Engineer’s
Representative, during periods of mix production,
sampling and testing, and whenever materials subject to
the provisions of these specifications are being supplied
or tested.
The bituminous plant testing laboratory shall have a floor
area of not less than 14 square metres, with a ceiling
height of not less than 2.3 metres. The laboratory shall be
weather-tight, sufficiently heated in cold weather, air
conditioned in hot weather, to maintain temperatures, for
testing purposes of 24°C plus or minus 2.5°C degrees. It
shall be so located on the asphalt plant site as to provide
an unobstructed view form one of its windows of the
trucks, as they are located with the plant mixed materials.
The bituminous plant testing laboratory shall have:
(1)
adequate artificial lighting
(2)
electrical outlets sufficient in number and capacity
for operating the required testing equipment and for
drying samples
(3)
fire extinguishers approved by the Engineer’s
Representative
(4)
work benches for testing with dimensions not less
than 0.75 metres by 3 metres
(5)
a desk or table and at least two chairs
(6)
sanitary facilities
laboratory
convenient
to
the
testing
(7)
exhaust fan to outside air, with minimum blade
diameter of 300 mm to adequately handle laboratory
dust and fumes
(8)
telephone
(9)
(10)
4-drawer legal size file cabinet
a sink with running water and attached drainboard
and drain capable of handling elutriable
material
(11)
a metal stand to hold sieves used in washing
elutriable material
(12)
a 2-element hot plate or other comparable heating
device, with suitable dial type thermostatically
controlled to adjust the heat, for drying
aggregates
(13)
mechanical shaker and appropriate sieves
conforming to requirements of current B.S. 812 or
ASTM designation E-II for determining the
gradation of coarse and fine aggregates in
accordance with ASTM C 136 or AASHTO T27.
(14)
testing equipment meeting the requirements of
current B.S. 598 (1974 or ASTM D 2172 Method A
for the extraction of bitumen from bituminous
paving mixtures)
(15)
apparatus to perform the Marshall procedures as
specified in B.S. 812 and ASTM C 127 and C
128
(16)
an oven of suitable size to contain enough
bituminous paving mixture to prepare 3 Marshall
specimens
(17)
other necessary small hand tools required for proper
sampling and testing of materials
(18)
library containing
all
British Standards
referenced herein, ASTM Parts 10 and 11 and
AASHTO Tests, Part II.
Approval of the bituminous plant and testing laboratory
by the Engineer will require all the above facilities and
equipment in good working order. during all periods of
mix production, sampling and testing; and whenever
materials subject to the provisions of these specifications
are being supplied or tested. Failure to provide any of the
above shall be sufficient cause for disapproving the
bituminous plant operations.
(CLAUSE 6386 – 6399 INCLUSIVE NOT USED)
SECTION VI – ROADWORK
PART (E) MISCELLANEOUS
KILOMETRE
6400.
Where directed by the Engineer, new precast reinforced
concrete kilometre posts shall be provided to indicate
distance in kilometres along the road. The kilometre posts
shall conform with the accepted standards of the Federal
Ministry of works for kilometre posts on Trunk “A”
Roads, as shown on Federal Ministry of Works
Drawing No. 28016, or such modification thereof as the
Engineer may direct. Normally the new kilometre posts
shall be constructed of Grade 15 N/mm2 concrete, be
approximately 2.0 metres in length and shall have a
roughly triangular cross-section the back face being 300
mm wide with two 50mm perpendicular offsets and the
two side surfaces being 400mm wide with the apex
truncated to give a 50 mm flat surface. The kilometre
posts shall be reinforced longitudinally with three 16.0
mm diameter mild steel rods having 6mm mild steel
stirrups at 250mm centres.
The kilometre posts shall be erected with the apex facing
the road and shall be located on the right hand side of the
road (when looking towards the higher distance in
kilometres). They shall be set in a 600 mm x 750 mm x
380 mm (deep) block of grade 15 N/mm2 concrete and
shall project 900mm above the ground level. The distance
between the nearest edge of the kilometre post and the
edge of the ultimate carriageway shall not be less than 3
metres.
All kilometre posts shall be twice painted with a white
(non-reflective) paint and have the letters and numbers
stencilled on in green reflective paint. The lettering and
distance in kilometre and origin shall be approved by the
Engineer.
Where existing kilometre posts are in good condition, the
Engineer may direct that these be taken down, painted
and treated as for new kilometre posts and re-erected at
the correct chainages.
CULVERT
BEACONS
6401.
Where directed by the Engineer, culverts shall be proprovided with two precast concrete beacons located
diagonally near the ends of the culvert as directed by the
Engineer. The beacons shall be cast of grade 15N/mm2
concrete and shall be 230 mm, 150mm thick and 900mm
long and shall project 45mm above the ground level.
They shall be set at the left hand side of the road with the
broad face facing the traffic and on this face shall be
stencilled, in two coats of black oil paint figuring 20mm
high on a two coat white painting background the
appropriate mileage and culvert number as directed by the
Engineer.
The beacons shall be located in a readily visible position
from the carriageway and as near as possible to the ends
of the culverts, but in no case shall they be nearer than
3.0 metres from the edge of the ultimate carriageway. All
markings of culvert beacons shall be completed before
the issue of the completion certificate for the section of
road in question.
Where directed by the Engineer, the appropriate reference
marks may be painted on any flat easily visible and
accessible surface of the culvert, such as on the headwalls of box culverts, in lieu of culvert beacons. In such
cases the figuring shall be stencilled as described above
on a white painted rectangular background as directed by
the Engineer.
ROAD WARNING
SIGNS
6402.
Where directed by the Engineer, road warning signs
shall be provided by the Contractor at approaches to all
dangerous curves, narrow bridges, railway level crossings
etc. Warning signs shall be of approved standard design
complying with the accepted standards of the Federal
Ministry of Works for use of Trunk “A” Roads. They
shall be constructed of plain single-sided pressed
aluminium shall be suitably braced at the back and shall
be painted in the regulation manner. They shall be
mounted on 76mm diameter tabular steel posts when
supported from the ground or, where such a support may
not cause an obstruction. They may be suspended as
shown on the drawings or as may be directed by the
Engineer.
The signs shall be erected in such locations and in such
numbers as shown on the drawings or directed by the
Engineer. They shall be erected, painted and completed in
every way prior to the issue of the completion certificate
for the section of the works in question.
Payment for road warning signs shall be made under the
appropriate item in the bill of quantities or where no such
item is included from the appropriate provisional sum.
ADVANCE
6403.
The Contractor shall provide and erect advance direction
signs in such numbers and in such locations as directed
by the Engineer. The signs shall be of approved design
complying in all respect with the accepted standards of
the Federal Ministry of Works for use on trunk A roads.
Generally they shall consist of plain single-sided pressed
aluminium suitably braced at the back and painted in the
regulation manner. The Engineer shall supply to the
Contractor a more detailed specification and drawings for
all advance direction signs required, showing their
locations, sizes, structural details, type of support etc. The
signs shall be erected, painted and completed in every
way prior to the issue of the completion certificate for the
section of the works in question.
DIRECTION
SIGNS
Payment for advance direction signs shall be from the
appropriate item in the bill of quantities of where no such
item is included, form the appropriate provisional sum.
CARRIAGEWAY
MARKINGS
6404.
On completion of the surfacing of the carriageways etc.
the Contractor shall construct such carriageway markings
as are shown on the drawings or that may be directed by
the Engineer.
For smooth dense textured road surfacing the markings
shall consist of an approved ready coated self-adhering
thermoplastic material. If shall be suitably reflectorised,
be durable and long-wearing containing adequate antiskid
properties and the adhesive shall provide sufficient bond
between the markings and the road surface as to prevent
any undue movement either due to traffic action or due to
temperature variations.
For coarse-textured road surfacing such as surface
dressing, the markings shall consist of an approved quicksetting thermoplastic composition applied hot by an
approved “line laying” machine. The composition shall
be suitably reflectorised, have a setting time of not
exceeding 60 seconds, be durable, long-wearing and have
adequate anti-skid properties. When set the markings
shall be sufficiently rigid and provide sufficient bond
with the road surface as to prevent any undue distortion
or movement due to traffic action or temperature
variation.
The type and colour of markings to be used shall be
decided by the Engineer for the various kinds of usage
and road surface and all markings shall be completed
prior to the issue of the completion certificate for the
section of works in question.
Payment for carriageway markings shall be made per
linear metres of marking from the appropriate item in the
bill of quantities or, where no such item is included, from
the appropriate provisional sum.
PRECAST
CONCRETE
KERBS
6405.
All precast concrete kerbs shall be in accordance with
B.S. 340 and shall be of the sizes and dimension shown
on the drawings or directed by the Engineer. The kerbs
shall be manufactured using grade 20N/mm2 quality
concrete and shall be cast in steel moulds and adequately
vibrated or pressed. The kerbs shall pass the tests for
transverse strength and the absorption of water tests as
described in the appropriate B.S. 340.
After casting they shall be lightly rubbed over with a
carborundum stone and later to a smooth finish, but shall
not be slurried over with cement.
The kerbs shall be cured for a period of 14 days by
protection from the direct rays of the sun or from drying
winds and for the first 7 days after manufacture they shall
be thoroughly saturated with water. Kerbs shall not be
incorporated into the works until they are at least 28 days
old.
The vertical joints shall be filled in with grade M1 mortar
and flush pointed. Where expansion joints occur in the
carriageway, such jointing shall be extended in the same
plane through the kerbing and kerb base and ducking
when provided.
Kerbs for radius work shall be purposely made to the
required internal and external radii. For radii less than 6
metre, they shall be 500mm long. All kerbs for radii work
in excess of 15 metres radius may be straight kerbs and
shall be 500mm long for radii up to 30 metres.
Otherwise than above, all kerbs shall be 1000mm long.
Where shown on the drawings, or directed by the
Engineer’s Representative, precast concrete kerbs shall be
laid on a grade 15N/mm2 concrete bed and haunched at
the back as directed. All kerbs shall be bedded on a layer
of grade M3 quality mortar and shall be laid true to line
and level as shown on the drawings to the satisfaction of
the Engineer’s Representative. Payment shall be per
linear metre of kerb from the appropriate item in the bill
of quantities.
PRE-CAST
CONCRETE
EDGING
BLOCKS
6406.
Where pre-cast concrete edging blocks are specified such
as edging to footpaths, they shall be of the sizes and dimensions shown on the drawings or directed by the Engineer, shall be in accordance with B.S. 340 and generally
shall comply with the provisions of the preceding clause
for N/mm2 grade quality concrete and shall be laid as
directed true to line and level to the satisfaction of the
Engineer’s Representative. Payment shall be made per
linear metre of edging under the appropriate item in the
bill of quantities.
PRE-CAST
CONCRETE
PAVING
SLAB
6407.
Pre-cast concrete paving slab shall comply with B.S.
368 “Precast Concrete Flags”. Except where otherwise stated to the contrary, or directed by the Engineer,
the slabs shall be 50mm thick, and except where cutting
is necessary, be of a uniform width of 450mm and a
uniform length of 600mm. The paving slabs shall be
adequately vibrated or pressed and shall have a smooth
hard-wearing non-skid finish.
The paving slabs shall be laid and bedded on approved
compacted sand filling to the correct level, grade and
cross-fall, so that when tested with a 3 metre straight edge
placed in any position on the paving, the maximum
deviation shall not exceed 6mm. Joints between the
paving slabs shall be filled in with a slurry of cement
mortar grade “M1” brushed over the paving in a circular
motion until all the joint cavities are completely filled in
to the satisfaction of the Engineer’s Representative. Any
excess slurry shall be removed and as soon as the joints
have sufficiently hardened the whole of the paving shall
be washed so as to leave the completed paving in a neat
and workmanlike manner.
The price for paving shall include all cutting, whether
straight or curved, laying, bedding, jointing, etc., and
payment shall be made per square metre of completed
paving from the appropriate item in the bill of quantities.
GULLEY KERBS
6408.
As shown on the drawings, or as directed by the
Engineer, precast concrete gulley kerbs shall be inserted
at intervals in the kerbing to ensure a quick and complete
run-off of surface rainwater from the carriageway.
Gulley kerbs shall be constructed to the dimensions
shown on the drawings or as directed by the Engineer and
shall comply in all respects with the provisions of the
relevant clause for precast concrete kerbs.
The
Contractor’s attention is drawn to the necessity for
accurate gradients of the kerbs and the edge of the
carriageway, especially for flat gradients, to ensure that
no surface water ponds on the carriageway. Payment
shall be per number of gulley kerbs placed from the
appropriate item in the bill of quantities.
GULLEY PIPES
6409.
PRE-CAST
CONCRETE
CHANNELS
6410.
Gulley pipes shall be inserted into all gulley outlet kerbs
to convey the surface water to the side drain or otherwise.
The gulley pipes shall consist of approved PVC pipes or
Class B asbestos cement pipe (150mm) in diameter, but
the Engineer may direct that cast iron pipes be used where
the pipe is under an access road etc. Where the depth of
cover is less than 300mm on footpaths, or less than
900mmm on carriageways, the gulley pipe shall be
bedded on a 300mm by 150mm concrete bed and given a
76mm thick concrete surround in grade 15N/mm2
concrete. Where a concrete bed or surround is not used,
the gulley pipe shall be adequately supported and
anchored in position at the kerb and at its outlet by a bed
and surround of grade 15 N/mm2 concrete at last 300mm
long. When completed, all gulley pipes shall be flushed
with water so as to leave the full internal of the pipe free
from any mortar, concrete or other debris. Payment for
gulley pipes shall be per linear metre of pipe and shall
include all anchoring, fixing and necessary joining, but
shall not include the provisions of a concrete bed and
surround.
Where the outlet of gulley pipes is over an embankment, or where the existing ground is liable to erosion
or otherwise as directed by the Engineer’s
Representative, precast concrete half-round channels of
225mm diameter or as directed, shall be laid to form a
water course leading from the outlets of the 150mm
diameter gulley pipes.
The channels shall be cast in 600mm lengths of grade 15
N/mm2 concrete and shall be accurately laid on a
prepared bed, true to line and level and jointed with
Grade M.3 mortar to the satisfaction of the Engineer’s
Representative. Both extremities of the channel shall be
securely anchored and set in a bed of Grade 15 N/mm2
concrete approximately at least 75mm wider than the
external width of the channel and 150mm thick. Prior to
the laying of the channels, the soil bed shall be properly
shaped and compacted to provide an even bed for the
channels throughout the whole of their length.
Payment shall be per linear metre of channel laid,
including all necessary bedding, jointing and anchoring,
from the appropriate item in the bill of quantities.
CAT’S EYES
6411.
If shown on the drawings or directed by the Engineer, the
Contractor shall provide and fix in position approved
standard-type reflecting road studs known as “cat’s eyes”.
Payment shall be per number of cat’s eyes provided and
fixed. And shall include for all cutting out of the road
surface and making good as necessary to the satisfaction
of the Engineer’s Representative.
STREET
LIGHTING
6412.
Where provision for street lighting is included in the
bill of quantities forming part of the main contract, the
Engineer shall issue to the Contractor a separate street
lighting specification and drawings for each individual
project. The street lighting system shall be of the
electrical type and generally shall comply with the
relevant provision of the British standard code of
practice, “C.P. 1004 parts 1 and 2 – Street lighting”, or
such other provisions specified by the Engineer. The
types of cables, controls, lanterns and mountings to be
employed shall be specified by the Engineer and the
source and manufacturers of same, shall be approved by
the Engineer. The actual electrical installation shall be
carried out by a competent electrical sub-Contractor to be
approved by the Engineer.
Payment for street lighting shall be made from the
appropriate items in the bill of quantities, or, where no
such items are included, from the appropriate provisional
sum. The street lighting shall be completed and tested to
the satisfaction of the Engineer’s Representative prior to
the issue of the completion certificate for the section of
work in question.
TRAFFIC LIGHTS 6413.
Where provision for traffic control lights are included in
the bill of quantities forming part of the main contract, the
Engineer shall issue to the Contractor a separate traffic
light specification and drawings for each individual set
employed. The traffic control lights shall be electrically
operated and the types of cables, controls, lanterns and
mountings shall be specified by the Engineer, and their
source and manufacturers shall be approved by the
Engineer. The actual electrical installation shall be
carried out by a competent electrical sub-Contractor, to be
approved by the Engineer.
Payment for traffic lights shall be made from the
appropriate items in the bill of quantities or, where no
such items are included, from the appropriate provisional
sum. The traffic control lights shall be completed and
tested to the satisfaction of the Engineer’s Representative
prior to the issue of the completion certificate for the
section of work in question.
ILLUMINATED
GUARD POSTS
6414.
Where illuminated guard posts, such as “keep right”
signs at roundabouts, etc., are to be provide, they shall be
of the electrically operated, internally illuminated type
having a pressed steel fluted type body with a vitreous
enamel finish and rust proofed steel lantern with a stove
enamel finish. For roundabouts, etc., the guard post shall
be fitted with a single aspect lantern having one 600mm x
300mm “keep right” glass panel.
The Engineer shall issue to the Contractor a
comprehensive specification and drawings for each
individual type of guard post, indicating the types of
cables, controls, lanterns and mountings to be employed
and the source and manufacturers of same shall be subject
to his approval. The actual electrical installation shall be
carried out by an approved competent electrical subContractor.
Payment for guard posts shall be made from the
appropriate items in the bill of quantities or, where no
such items are included, from the appropriate provisional
sum. The guard posts shall be completed and tested to
the satisfaction of the Engineer’s Representative prior to
the issue of the completion certificate for the section of
work in question.
GUARD RAILS
6415. A.
Scope
The work covered by this Clause consists of the
construction of beam guard rails mounted on concrete or
steel posts as shown on the DRAWINGS or as ordered by
the Engineer’s Representative.
B.
Material
1. Steel rail elements shall conform to the
DRAWING and shall be of Armco Flex-Beam
Guardrail of 12 gauge, non-galvanized or
equivalent. The minimum tensile strength when
tested in conjunction with splices and end
connections shall be 40,000 kg/cm2, and the bolts
attaching the rail element to posts shall be 15mm
in diameter.
Splices and end connections shall be as shown on
the DRAWINGS and the minimum tensile
strength of the splice and end connection
assembly shall be 40,000 kg/cm2.
2.
Concrete posts shall conform to the design shown
on the DRAWINGS. The concrete shall be of 20
N/mm2 and shall conform to the applicable
requirements of SECTION II – CONCRETE:
MASS AND REINFORCED of the GENERAL
SPECIFICATION; “PART 8 –
WORKMANSHIP”. Reinforcing steel shall be as
shown on the DRAWINGS and shall conform to
the applicable requirements of SECTION II –
CONCRETE: MASS AND REINFORCED of the
GENERAL SPECIFICATION; PART “B” WORKMANSHIP
C.
3.
Steel posts shall conform to the design shown on
the DRAWINGS and shall conform to the
applicable requirements of SECTION II –
CONCRETE: MASS AND REINFORCED of the
GENERAL SPECIFICATION.
4.
White paint shall conform to the requirements of
the applicable British Standards and the painting
clauses set forth in Section V Clause 5049.
Method of Construction
The concrete posts shall be set in excavated holes and the backfill shall be firmly tamped in
layers not more than 150mm thick in a manner
satisfactory to the Engineer’s Representative.
All posts shall be plumb, properly spaced and to the prescribed line and grade. Post holes
shall be excavated to such depth that backfill below the
posts will be kept to the minimum and, if any such back
fill shall be thoroughly compacted before setting the
posts.
The rail elements shall be erected to the required grade
and line with the top edge in a straight line or smooth
curve, parallel to or concentric with the roadway. Where
a vertical transition is required, the top edge of rail
elements shall form the chords of a smooth vertical curve.
At each end post, a single terminal section of rail element
shall be erected and lapped in the direction of traffic.
The Contractor’s attention is directed to the details of
guardrail transition at the approach end of the guard
railing as shown on the DRAWINGS.
No punching, drilling, reaming, cutting or welding of the
rail elements or terminal sections will be permitted in the
field unless provided for on the DRAWINGS or
specifically approved by the Engineer.
All bolts and nuts attaching the rail element to the posts
shall be hot-dip galvanized in accordance with the current
ASTM Designation 153.
D.
All metal parts that are not galvanized shall be thoroughly
cleaned and shop-painted with one coat of rust-inhibitive
primer. Any metal surfaces from which the shop coat of
rust-inhibitive primer has worn off, or on which the
primer has become defective otherwise, shall be given a
brush coat of the above-specified rustinhibitive primer
before the first coat of white paint is applied. All exposed
parts of the guardrail shall be given two field coats of
white paint. Paint shall not be applied over a previous
coat, which is not thoroughly dry.
Measurement
The quantity of beam guard rail for which payment will
be made will be the sum of the overall lengths of all
sections of new beam guard rail constructed in
accordance with the DRAWINGS and Specifications or
as directed by the Engineer’s Representative, measured
along the face of the guard rail, including the terminal
sections of the rail element.
E.
Payment
Payment for beam guard rail shall be made at the unit
rate shown in the Bill of Quantities which price shall
include furnishing and erecting the guard rail complete,
including excavation, backfilling, furnishing and setting
posts, priming, painting, preservation treatment, the
furnishing of all materials, labour and equipment, and all
else necessary therefore and incidental hereto.
DELINEATORS
The Contractor shall furnish and erect delineators of
hermetically scaled acrylic plastic prismatic reflector
housed in embossed aluminium and provided with a
single grommeted mounting hole, mounted on
galvanized “U” section channel post as shown on the
DRAWINGS or as directed by the Engineer’s
Representative.
6416.
1.
Materials
a.
Prismatic Reflectors
The housing shall be 0.50mm aluminium formed
to approximately 85mm in diameter and 6mm in
depth to retain the acrylic reflector. Housing
shall be provided with embossed reinforcement
ribs.
A corrosion resistant metal grommet with 5mm
inside diameter shall be expanded within the
reflector mounting hole.
The reflector shall be acrylic plastic and the
Contractor shall specify the manufacturer of the
raw material and the identification number of the
particular moulding compound to be furnished.
Acceptable formulations:
TABLE VI-19: ACCEPTABLE FORMULATIONS
FOR TYPE OF MOULDING COMPOUND
MANUFACTURER
TRADE
NAME
E.I. DUPONT
DENEMOURS AND
LUCITE
CO. INC.
ROHM AND HAAS
CO. OR
FLEXIGLASS
EQUIVALENT
TYPE OF
MOULDING
COMPOUND
MH-140
V
The reflector shall consist of a clear and transparent plastic face with 45.0 sq.cm of
relecting area, herein referred to as the lens with a
heat resistant plastic coated back fused to the lens
under heat and pressure around the entire
perimeters of the lens and control mounting hole
to form a unit permanently sealed against dust,
water and water vapour. The reflector shall be
colourless.
The lens shall consist of a smooth front surface free from projection or indentation
other than a central mounting hole and
identification with a rear surface bearing, a
prismatic configuration, such that it will reflect
total internal reflection of light.
The
manufacturer’s trade mark shall be moulded
legibly into the face of the lens.
b.
Galvanized Steel Posts
Galvanized Steel posts for delineators shall be
“U” section channel posts as shown ON
DRAWINGS and weigh not less than 1.0 kg/m
nor more than 2.75 kg/metre as approved by the
Engineer’s Representative. The channel posts
shall be drilled or punched as shown on the
DRAWINGS. All holes shall be provided before
galvanizing. Oversize holes shall be backed up
with rectangular washers as stated hereinafter.
All steel posts shall be mild steel No. 1 quality
entirely in accordance with the requirements of
B.S. 15. All sections shall conform to British
Standard dimensions.
All steel posts shall be entirely galvanized after
fabrication, including cutting and punching or
drilling, in accordance with Clause 5063 of the
GENERAL SPECIFICATION.
c.
Hardware
Bolts for connecting centre-mounted reflectors to
the posts shall be Phillips round-headed bolts of
aluminium alloy 2024-T4 or equivalent with 8-32
or 10-24 thread, and with square or hexagon
aluminium nuts. If post mounting holes are larger
than 6mm diameter, provide rectangular
aluminium backing washers, 1.0mm thick,
minimum, with holes 5.0mm to 6.00mm diameter
and large enough to provide satisfactory area of
bearing against the post. Reflectors may also be
fastened to their respective posts by blind rivets or
bolts, provided aluminium washers are used at
oversize holes; rivets and riveting or tightening
device and technique may be used if only they are
approved by the Engineer’s Representative.
Bolts shall be of such length that in no case shall
the exposed threaded length of a bolt extend
beyond the tightened bolt more than 10mm.
2.
Methods of Construction
All delineators shall be located and erected in
conformance with the DRAWINGS or as directed by the
Engineer’s Representative and all delineator pots and
reflector mountings shall be plumb. The top of posts
shall have substantially the same cross sectional
dimensions as the body of the posts; no battered heads
will be permitted. A suitable driving cap shall b used
whenever posts are driven. If posts are set in earth, post
holes shall be backfilled with suitable material placed in
layers not more than 150mm in depth and each layer shall
be thoroughly compacted.
All posts shall be in the final position before attaching
reflectors
Topmost centre mounted reflectors shall be mounted on
posts through holes having an edge distance from the top
of post of not less than 10mm or more than 25mm.
Centre to centre spacing of delineators shall be 100mm.
All fasteners shall securely grip their respective reflectors.
Reflectors shall show no sign of damage after being
mounted. Rectangular washers described herein above
shall be used under nuts whenever mounting holes exceed
6.0mm diameter.
The Contractor, at his own expense, shall replace or
repair to the satisfaction of the Engineer’s Representative
any delineators, removed or damaged in any way prior to
the acceptance of this work.
3.
Quantity and Payment
The quantity of delineators for which payment will be
made shall be the number of delineators actually
furnished in accordance with the DRAWINGS, the
Specification, and as directed by the Engineer’s
Representative.
TELEPHONE
POLES
6417.
Payment for the delineators shall be made for the
quantities as above determined, at the unit price shown in
the Bill of Quantities, which price shall include the cost
of posts, mounting plates, plastic reflectors, hardware,
galvanizing, driving or setting of posts, all excavation and
backfilling, drilling in rock and grouting, all material,
equipment, labour, and all else necessary thereof and
incidental thereto.
The Contractor shall furnish and install telephone poles
where and as shown on the DRAWINGS or as directed
by the Engineer’s Representative.
All work under this Clause affecting the property, rightofway and facilities of the Posts and Telegraphs
Department, Ministry of Communication (hereinafter
called as Owners) shall be carried out under joint
supervision of the Engineer’s Representative and the said
Owners in a manner satisfactory to both.
The Contractor shall submit to the Engineer’s
Representative detailed working drawings and written
description of the intended construction methods and
shall obtain approval from the Engineer’s
Representative.
After approval of the working drawings and/or working
plans, the Contractor shall furnish the said owners,
through the Engineer’s Representative, with as many
numbers of prints of such drawings as required by the
said owners. No work affecting the safety, operation or
maintenance of the utilities shall be commenced or
prosecuted until written approval of the owners has been
obtained. This provision must be complied with before
the Contractor begins actual construction work.
Payment shall be made at the unit price for this item
tendered in the Bill of Quantities. Payment shall include
all costs for furnishing materials, equipment and labour,
and for all costs for coordination of all construction
activities with the owners. The installation shall be
completed and tested to the satisfaction of the Engineer’s
Representative and of the owners prior to the issue of the
completion certificate for the work in question.
(CLAUSES 6418 – 6499 INCLUSIVE NOT USED)
ANNEXURE TO THE GENERAL
SPECIFICATION
(ROAD AND BRIDGES)
PENETRATION (GROUTED) MACADAM
GENERAL
6500.
MATERIALS
6501.
(a)
Penetration macadam shall consist of a compacted
wearing course of coarse crushed rock aggregate laid
upon a prepared base and grouted with straight run
bitumen. For keying the penetration layer 19mm and
10mm crushed rock chippings shall be used. Surface
sealing shall be carried out using either a straight run or
cut back bitumen as specified and 12mm crushed rock
chippings.
The materials to be used in penetration macadam shall
comply with the following:The coarse aggregate for the wearing course shall consist
of clean crushed rock dry and free from dust. The
aggregate crushing value shall not exceed 23%. The
aggregate shall be graded as shown in the table below.
TABLE VI-20 COARSE AGGREGATE GRADING
ENVELOPES FOR PENETRATION MACADAM
Percent Passing
Sieve
80mm thick
base
50mm thick
base
63.5mm
100
-
50.8mm
90 - 100
100
38.1mm
30 - 80
80 - 100
25.4mm
0 - 15
30 - 80
19.0mm
-
0 - 15
(b)
The 19mm aggregate for keying the penetration layer of
coarse aggregate shall comply with B.S. 63 – “Single
sized Road Stone and Chippings”.
(c)
the 10mm aggregate for keying the penetration layer of
coarse aggregate shall comply with the grading shown in
the table below:
TABLE VI-21: GRADING ENVELOPE FOR
KEYING THE PENETRATION LAYER OF
PENETRATION MACADAM
Sieve
Percentage Passing
12mm
100
9.5mm
90 - 100
6.4mm
5 - 20
600µm
0 - 10
(d)
The 12mm aggregate for the seal coat shall comply with
B.S. 63 “Single sized road Stone and Chippings”.
(e)
The bitumen for grouting the penetration macadam shall
be a straight run bitumen as specified in Clause 6301
(iii).
(f)
The bitumen for the seal coat shall be either a straight
run or cut back bitumen as specified in Clause 6301 (ii)
or Clause 6301 (iii).
(g)
An approved anti-stripping additive shall be incorporated
in the bitumen when this is directed by the Engineer. The
additive shall be mixed with the bitumen by the supplier
during manufacture so as to ensure a uniform dispersion
of the additive.
(h)
The specification for the various grades of aggregate
required is devised so that the full range of crushed stone
produced will be used except for the fines passing a 5mm
screen. Aggregate in the 63.5mm to 19.0mm range will
be used in the base layer. Aggregate in the 19.0mm to
12mm and 10mm to 5mm range shall be used as
keystone. Aggregate in the 12mm to 10mm range shall
be used as chippings in the seal coat. The above will
apply provided always that the efficiency of the screening
arrangements is such that the gradings of each range of
aggregate comply with the specifications.
WORKMANSHIP
6502. (1)
(2)
(3)
The coarse aggregate shall be spread by mechanical means
on the prepared base in a uniform loose layer so that after
it is fully compacted it shall be of the specified thickness.
The layer of coarse aggregate shall be rolled to the correct
shape longitudinally and transversely by a three-wheel,
steel-tyred, roller weighing not less than 9 tonne or by a
vibratory roller of same capacity and having a minimum
weight of 54 kilograms per centimetre width of rear
wheel. Any irregularities shall be corrected by loosening
the surface and removing or adding aggregate as required
and re-compact. Rolling shall be continued until thorough
interlocking is obtained and there is no movement under
the action of the roller. Rolling shall be stopped if the
aggregate begins to crack or crush. The finished surface
shall show uniform voids and when tested with a 3 metre
straight edge placed parallel to the centre line of the road
shall not show any variation greater than 12mm. The
transverse profiles shall conform to the same accuracy
using a correctly shaped rigid fabricated metal template
instead of a straight edge. The length of this template
shall not be less than the width of the base.
Straight run bitumen shall then be sprayed as specified in
Clause 6313 on the shaped and compacted layer of coarse
aggregate at the rte of 0.71 to 0.89 litres per sq.m per
centimetre of compacted thickness. The actual rate of
application shall be determined by the Engineer’s
Representative after tests have been carried out on site, as
described in Clause 6503.
Immediately following the applications of the bitumen
and while it is still warm, the key-stone shall be spread
evenly over the surface so as to key the surface voids.
The key-stone shall be applied in successive layers. The
first layer shall be 19.0mm. Key-stone applied in just
sufficient quantity to prevent the roller wheels sticking.
As rolling continues further 19.0mm and 10mm keystone
shall be spread and lightly broomed over the surface and
rolled until all the voids in the coarse aggregate have been
filled but without having an excess of loose key stone on
the surface. Rolling shall continue until the key-stone is
thoroughly embedded and the stone layer shows no
movement under the roller. The proportions of 19.0mm
and 10mm key-stone to be used and the order in which
they shall be used shall be determined after trial sections
have been constructed as described in Clause 6503.
(4)
When the spreading and rolling of the key-stone have
been completed to the satisfaction of the Engineer’s
Representative, the road shall be opened to traffic as
specified in Clause 6316.
(5)
The seal coat shall not be applied until at least 10 days
after the completion of the wearing course. During this
period additional key-stone shall be applied if directed
and brushed into any voids, which may appear under the
action of the traffic. After such period any irregularities
or areas of failure due to workmanship shall be cut out
and made good to the satisfaction of the Engineer’s
Representative. After all remedial work has been allowed
sufficient time to harden and settle under the action of
traffic, the surface shall be swept clean of all loose
material and the seal coat shall be applied as described
for the wearing coat in Clause 6313 except that the
bitumen will be sprayed at the rate of 1.30 to 1.50 litres
per sq.m.
On completion of the seal coat the road shall be opened to
traffic and speeds shall be restricted to a maximum speed
of 25 km/h for one day following the opening.
(6)
TRIAL SECTIONS 6503.
The Contractor shall construct trial sections at least 90
metres long to determine the most efficient construction
technique and the suitability of the materials and plant to
be used. If the trial sections are satisfactory they shall be
incorporated in the finished work.
TESTS
6504. (1)
(2)
The rate of application of the bitumen shall be checked as
specified in Clause 6223. When tests are carried out on
the rate of application of the bitumen used in grouting,
the test trays shall be provided with lips of sufficient
depth to prevent loss of bitumen through overflowing.
Holes 300mm square shall be cut in the stone layer to the
full depth where directed
by
the
Engineer’s
Representative who shall determine by visual inspection
the degree of penetration of the bitumen. The Engineer’s
Representative may order such variation in the rte of
spread or application temperature of the bitumen as he
may consider necessary to obtain the most uniform
penetration of the bitumen throughout the full depth of
the stone layer.
Download