12/05/2023 Scenario 1 – Projects are Divisible and Constraints is a Single Period One Solution: Scenarios of Capital Rationing The following steps may be adopted by solving the problem under this situation: a. Calculate the profitability index for each project b. Rank the projects on basis of profitability index calculated in a above. c. Choose the optimal combination of projects. 41 43 Scenario 1 – Projects are Divisible and Constraints is a Single Period One XYX Company is considering five independent projects. Scenario 1 – Projects are Divisible and Constraints is a Single Period One Solution: Project Required Initial Investment NPV at the Appropriate Cost of Capital Project Required Initial NPV at the Appropriate Investment Cost of Capital (1) (2) (3) A P1,000,000 P20,000 Profitability Index (3/2) (4) 0.02 Rank A P1,000,000 P20,000 B 3,000,000 35,000 C 500,000 16,000 B 3,000,000 35,000 0.0117 5 D E 2,000,000 1,000,000 25,000 30,000 C 500,000 16,000 0.032 1 D 2,000,000 25,000 0.0125 4 E 1,000,000 30,000 0.03 2 The fund available is P3,000,000. Determine the optional combination of projects assuming that the projects are divisible. 42 (5) 3 44 1 12/05/2023 Scenario 1 – Projects are Divisible and Constraints is a Single Period One Solution: Rank of Investment Project Required Initial Outlay 1 C P 500,000 2 E 1,000,000 3 A 1,000,000 4 Total ¼ of D 500,000 P3,000,000 45 Scenario 2 – Projects are Indivisible and Constraints is a Single Period One Solution: Feasible Combination Aggregate of NPVs A, C P36,000 A, D 45,000 A, E 50,000 C, D 41,000 C, E 46,000 D, E 55,000 A, C, E 66,000 By a careful inspection of the feasible combinations constructed in the above table, we can conclude that the optimal project mix is A, C, and E because the aggregate of their NPVs is the maximum. 47 Scenario 2 – Projects are Indivisible and Constraints is a Single Period One Using the same data, used in previous illustration, determine the optimal project mix on the basis of the assumption that the projects are indivisible. Scenario 3 – Projects are Divisible and Constraints is Multi-period One Under this scenario, the problem of capital rationing can be solved with the help of linear programming. It is a mathematical programming approach. Solution: The following steps to be followed for solving the problem under the situation are: a. Construct a table using the visible combination of the project (whose aggregate of initial outlay does not exceed the fund available for investment). b. Choose the combination whose aggregate NPV is maximum and consider it as the optimal project mix. Harrah Corporation has considered seven independent projects, namely, A, B, C, D, E, F, and G for implementation. The company has a capital budget of P400 million. The minimum acceptable rate of return is 7%. Let us now consider the capital rationing problem. 46 48 2 12/05/2023 Scenario 3 – Projects are Divisible and Constraints is Multi-period One Ranking Based on the NPV Project Investments In millions NPV @ 7% In millions A 100 54.73 B 100 40.47 C 200 87.014 D 200 283.007 E 200 62.23 F 50 4.76 G 50 26.08 Scenario 3 – Projects are Divisible and Constraints is Multi-period One Ranking Based on the Profitability Index Project The optimum set comprise of projects D and C. by implementing them with an investment of P400 million (P200 million+P200 million), the company would earn returns whose present value is P370.021 million (P283.007+87.014 million). A B C D E F G PV of Outflows PV of Inflows Profitability In millions In millions Index 100 154.73 1.547 100 140.47 1.405 200 287.01 1.435 200 483.01 2.415 200 262.23 1.311 50 54.76 1.095 50 76.08 1.522 49 51 Scenario 3 – Projects are Divisible and Constraints is Multi-period One Ranking Based on the IRR Scenario 3 – Projects are Divisible and Constraints is Multi-period One Ranking Based on the Profitability Index Under the profitability ranking projects D, A, and G has scored the first three ranks with a total funds commitment of P350 million. Obviously, Projects C. B, and E which are next in the sequence of decreasing PI, cannot be accommodated from the balance of funds ie. P50 million (P400 million – P350 million) available for investment. Hence, Project F is selected to complete the optimum set. The sum of NPVs of Projects D, A, G, and F amounts to P368.58 million. As seem from the above illustration, the decision regarding choice of set of projects which best meets the corporate financial objective in a capital rationing situation upon checking the criterion used for selection. Project Investments In millions NPV @ 7% In millions A 100 13.6 B 100 15.1 C 200 22.1 D 200 20.7 E 200 12.0 F 50 11.9 G 50 16.7 Among the seven projects, Project C has the highest IRR of 22.1% and, hence, this project is selected as first and its commitment of funds is P200 million, the project having next best IRR is Project D with 20.7% and its commitment of funds is also P200 million. 50 52 3 12/05/2023 Effects of Inflation to Capital Budgeting Analysis Inflation Effects on Capital Budgeting Computations under the two approaches are presented below: Reconciliation of the Market-Based and Real Costs of Capital The real cost of capital The inflation factor The combined effect (12%x10%) The market-based cost of capital 12.0% 10.0 1.2 23.2% 55 Effects of Inflation to Capital Budgeting Analysis Effects of Inflation to Capital Budgeting Analysis Inflation affects the numbers that are used in the analysis but does not affect the results of the analysis if certain condition is satisfied. To illustrate, we use the following data: Marvex Corp. wants to purchase a new equipment that cost P360,00. The equipment would provide annual net cash flows from operations of P200,000 and it would have a three-year life with no salvage value. For each of the next three years, the company expects a 10% inflation rate in the cash flows associated with the new machine. If the company’s real cost of capital is 12% or market based cost of capital of 23.2%, should the equipment be purchased. 54 Solution A: Inflation Not Considered Items Initial Investment Annual cost savings NPV Years(s) Amount of Cash Flows 12% Factor PV of Cash Flows Present (P360,000) 1.000 (P360,000) 1-3 200,000 2.402 480,400 P120,400 56 4 12/05/2023 Effects of Inflation to Capital Budgeting Analysis Solution B: Inflation Considered Items Years(s) Amount of PI Cash Number Flows Initial Investment Present (P360,000) 1 2 3 Annual cost savings Price – Adjusted Cash Flows 2.3% Factor PV of Cash Flows 1.000 (P360,000) 1.000 (P360,000) 200,000 1.100 220,000 0.812 178,640 200,000 1.210 242,000 0.659 159,480 200,000 1.331 266,200 0.535 142,420 P120,540 *Computation of the price-index number, assuming a 10% inflation rate each year: (1+r)n *Discount formula is computed as 1/(1+r)n *the amount of the total might be different because of rounding off error 57 Financial Breakeven Point Effects of Inflation to Capital Budgeting Analysis Financial Breakeven Point Solution B: Inflation Considered It will be noted that the net present value obtained in solution B, where inflation is explicitly taken into account is the same within rounding error to the obtained in Solution A, where the inflation effects were not considered. This result may seem surprising but it is logical because we have adjusted both the cash flow and the discount rate so that they are consistent and these adjustments cancel each other out across the two solutions. (with and without the inflation considered) This occurs when the NPV of the project is zero. The financial BEP is thus: 58 60 Where the OCF is the level of the OCF that results in a zero NPV. A project that breaks even on a financial basis has a discounted payback equal to its life, a zero NPV, and an IRR just equal to the required return. 5 12/05/2023 Sensitivity Analysis If the NPV estimate turns out to be very sensitive to relatively small changes in the projected value of some component of project cash flows, then the forecasting risk associated with that variable is high that may require further study or market research Sensitivity Analysis 63 Sensitivity Analysis This is the determination of what happen to the Net Present Value (NPV) estimates when we ask “what if” questions or in response to a given change in an input variable other things held constant. This is useful in pinpointing the areas where forecasting risk is especially severe. In this technique, each variable is changed by several specific percentage points above and below the expected value, holding other things constant; then a new NPV is calculated for each of these values. 62 6