Uploaded by Yong Jun Xiang

IACS PR38 Rev.3 - Procedure for calculation and verification of the Energy Efficiency Design Index (EEDI)

advertisement
No.38
No. Procedure for calculation and verification of the
38
Energy Efficiency Design Index (EEDI)
38
(May 2013)
(cont)
(Rev.1
Mar 2016)
(Rev.2
Mar 2019)
(Rev.3
Jan 2021)
Introduction
This procedure applies to all cases of Class Societies’ involvement in conducting the survey
and certification of EEDI in accordance with regulations 5, 6, 7, 8 and 9 of MARPOL Annex VI.
1
Definitions
“Industry Guidelines” means the “2020 Industry Guidelines for calculation and verification of
the Energy Efficiency Design Index (EEDI)” as submitted to MEPC 76 that may be revised in
order to remain in line with the relevant IMO Guidelines.
“Verifying Society” is a Society which conducts the survey and verification of EEDI of a ship.
“Witnessing Society” is a Society which has witnessed the towing tank test of a ship of the
same type as the ship whose EEDI is verified by the Verifying Society. “Ship of the same type”
is defined in IMO “2014 Guidelines on Survey and Certification of the Energy Efficiency Design
Index (EEDI)” as amended.
“Witnessing protocol” is a document showing evidence of the witnessing and acceptance of
the towing tank test by the Witnessing Society, with indication such as date, signature and
possible remarks of the attending surveyor.
2
Scope of the Procedure
The scope of this procedure is defined in Part I of the Industry Guidelines.
3
Calculation of EEDI
The procedure to compute the EEDI is documented in Part II of the Industry Guidelines. For
the purpose of this Procedural Requirement, calculation of the EEDI is to be performed in
accordance with IMO “2018 Guidelines on the method of calculation of the attained Energy
Efficiency Design Index (EEDI) for new ships, as amended” and Part II of the Industry
Guidelines, as amended.
Note:
1.
This Procedural Requirement applies from 1 July 2013.
2.
Rev.1 of this Procedural Requirement applies from 1 July 2016.
3.
Rev.2 of this Procedural Requirement applies from 1 July 2019.
4.
Rev.3 of this Procedural Requirement applies from 1 April 2021.
Page 1 of 2
IACS Proc Req. 2013/ Rev.3 2021
No.38
No.
38
(cont)
4
Verification of EEDI
The procedure to verify the EEDI is documented in Part III of the Industry Guidelines,
together with Appendixes 1, 3, 4 and 5. For the purpose of this Procedural Requirement,
verification of the EEDI is to be performed in accordance with IMO “2014 Guidelines on
Survey and Certification of the Energy Efficiency Design Index (EEDI)” as amended and
Part III of the Industry Guidelines, as amended.
A sample of document to be submitted to the Verifier including additional information for
verification is provided in Appendix 2 of the Industry Guidelines.
5
Acceptance of towing tank tests witnessed by another Society
Further to the agreement of the submitter of the EEDI Technical File and the Shipowner, a
Verifying Society may accept towing tank tests reports witnessed by another Society if the
towing tank tested ship is of the same type as the ship of which the EEDI is verified.
Copies of the following documents are to be provided to the Verifying Society, with due
consideration given to the protection of the Intellectual Property Rights (IPR) as indicated
under paragraph 14 of the Industry Guidelines:
-
Calculation of the reference speed of the verified ship explicitly making reference to the
speed power curves of the tank tested ship model
-
Witnessing protocol of the tank tested ship endorsed by the surveyor of the Witnessing
Society
-
Towing tank test report of the tank tested ship
On specific request of the Verifying Society, the following additional information is to be
submitted:
-
Ship lines and model particulars, loading and operating conditions of the tank tested ship
as described in 4.2.7.2 of IMO “2014 Guidelines on Survey and Certification of the
Energy Efficiency Design Index (EEDI)” as amended, showing that the verified ship and
the tank tested ship are of the same type
If some of the relevant information is held by the original Witnessing Society, the submitter
should authorize the Witnessing Society to make the information available to the Verifying
Society.
6
New ship (as per MARPOL Annex VI Regulation 2) designed before the entry into
force of the MARPOL Annex VI amendments introducing the EEDI
It is expected that the towing tank tests of a new ship performed before the entry into force of
MARPOL Annex VI amendments introducing the EEDI have not been witnessed by a Verifier.
In this case, towing tank test results provided by a tank test organization with quality control
certified according to a recognized scheme or with experience acceptable to the Verifying
Society may be accepted by the Verifying Society.
Attached:
2020 Industry Guidelines for calculation and verification of the Energy Efficiency Design Index
(EEDI)
End of
Document
Page 2 of 2
IACS Proc Req. 2013/ Rev.3 2021
2020 Industry Guidelines for calculation and verification of EEDI
2020 INDUSTRY GUIDELINES FOR CALCULATION AND VERIFICATION OF THE ENERGY
EFFICIENCY DESIGN INDEX (EEDI)
TABLE OF CONTENTS
Part I – Scope of the Industry Guidelines
1
Scope of the Guidelines… ....................................................................................... 2
Part II – Explanatory notes on calculation of EEDI
2
Introduction… .......................................................................................................... 3
3
EEDI formula… ........................................................................................................ 3
4
Fuel consumption and fuel conversion factor… ....................................................... 4
5
Capacity, power and speed… .................................................................................. 5
6
Shaft generator and shaft motor…........................................................................... 6
7
Weather factor fw ....................................................................................................13
8
Correction factor for ship specific design elements fj .............................................13
9
Capacity factor fi ....................................................................................................13
10
Cubic capacity correction factor fc and cargo gears factor fl ..................................14
11
Innovative energy efficient technologies… ............................................................14
12
Example of calculation… .......................................................................................15
Part III – Verification of EEDI
13
Verification process… ............................................................................................17
14
Documents to be submitted…................................................................................17
15
Preliminary verification at the design stage… ........................................................19
16
Final verification at sea trial… ................................................................................23
17
Verification of the EEDI in case of major conversion… .........................................25
1
Appendix 1. Review and witness points… .............................................................26
2
Appendix 2. Sample of document to be submitted to the verifier… .......................29
3
Appendix 3. Verifying the calibration of model test equipment ..............................45
4
Appendix 4. Review and witnessing of model test procedures… ..........................51
5
Appendix 5. Sample report "preliminary verification of EEDI"… ............................58
6
Appendix 6. Sample calculations of EEDI… ..........................................................59
Page 1 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Part I - Scope of the Industry Guidelines
1
Scope of the Guidelines
1.1
Objective
The objective of these Industry Guidelines for calculation and verification of the Energy
Efficiency Design Index (EEDI), hereafter designated as “the Industry Guidelines”, is to
provide details and examples of calculation of attained EEDI and to support the method and
role of the verifier in charge of conducting the survey and certification of EEDI in compliance
with latest IMO Resolutions with respect to following Guidelines:
●
●
●
●
●
2018 Guidelines on the method of calculation of the attained Energy Efficiency
Design Index (EEDI) for new ships, Res. MEPC.308(73) adopted on 26 October
2018, as amended by res. MEPC.322(74) adopted on 17 May 2019, referred to
as the "IMO Calculation Guidelines" in the present document.
2014 Guidelines on survey and certification of EEDI, Res. MEPC.254(67) adopted
on 17 October 2014, as amended (MEPC.1/Circ.855/Rev.2), referred to as the "IMO
Verification Guidelines" in the present document
2013 interim Guidelines for determining minimum propulsion power to maintain the
manoeuvrability of ships in adverse conditions, Res. MEPC.232(65) as amended
(MEPC.1/Circ.850/Rev.2)
2013 Guidance on treatment of innovative energy efficiency technologies for
calculation and verification of the attained EEDI, MEPC.1/Circ.815
2012 interim Guidelines for the calculation of the coefficient fw for decrease
in ship speed in a representative sea condition for trial use,
MEPC.1/Circ.796.
In the event that the IMO Guidelines are amended, then pending amendment of these
Industry Guidelines, calculation and verification of EEDI are to be implemented in compliance
with the amended IMO Guidelines.
1.2
Application
These Guidelines apply to new ships as defined in regulation 2.23 of MARPOL Annex VI of
400 gross tonnage and above of the ship types to which Regulation 20 of MARPOL Annex
VI is applicable and defined under regulations of MARPOL Annex VI
The calculation and verification of EEDI shall be performed for each:
1. new ship before ship delivery
2. new ship in service which has undergone a major conversion
3. new or existing ship which has undergone a major conversion that is so extensive
that the ship is regarded by the Administration as a newly constructed ship
The Industry Guidelines shall not apply to ships which have non-conventional propulsion,
such as diesel-electric propulsion, turbine propulsion or hybrid propulsion systems, with the
exception of cruise passenger ships with diesel-electric propulsion and LNG carriers having
diesel-electric or steam turbine propulsion systems.
The Industry Guidelines shall not apply to category A ships as defined in the Polar Code
Page 2 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Part II - Explanatory notes on calculation of EEDI
2
Introduction
The attained Energy Efficiency Design Index (EEDI) is a measure of a ship's energy
efficiency determined as follows:
𝐸𝐸𝐷𝐼
𝐶𝑂 𝑒𝑚𝑖𝑠𝑠𝑖𝑜𝑛
𝑇𝑟𝑎𝑛𝑠𝑝𝑜𝑟𝑡 𝑤𝑜𝑟𝑘
The CO2 emission is computed from the fuel consumption taking into account the carbon
content of the fuel. The fuel consumption is based on the power used for propulsion and
auxiliary power measured at defined design conditions.
The transport work is estimated by multiplying the ship capacity as defined in the IMO
Calculation Guidelines by the ship’s reference speed at the corresponding draft. The
reference speed is determined at 75% of the rated installed power in general and 83% of the
rated installed propulsion power for LNG carriers having diesel electric or steam turbine
propulsion systems.
3
EEDI formula
The EEDI is provided by the following formula:
With the following notes:
The global fi factor may also be written:
𝑓
𝑓
where each individual fi factor is explained under section 9 of this document.
If part of the normal maximum sea load is provided by shaft generators, the term 𝑃
𝑆𝐹𝐶 may be replaced by:
𝑃
0.75 ∗
𝑃
with the condition 0.75 ∗ ∑
∙𝐶
𝑃
∙ 𝑆𝐹𝐶
0.75 ∗
𝑃
∙𝐶
∙𝐶
∙ 𝑆𝐹𝐶
𝑃 .
Where the total propulsion power is limited by verified technical means as indicated under
∑
∙𝐶
∙ 𝑆𝐹𝐶
𝑃
∙𝐶
∙ 𝑆𝐹𝐶
is to be
section 6, the term ∑
𝑃
replaced by 75 percent of the limited total propulsion power multiplied by the average
weighted value of (SFCME.CFME) and (SFCAE.CFAE).
Due to the uncertainties in the estimation of the different parameters, the accuracy of the
calculation of the attained EEDI cannot be better than 1%.
Page 3 of 74
∙
2020 Industry Guidelines for calculation and verification of EEDI
Therefore, the values of attained and required EEDI have to be reported with no more than
three significant figures (for instance, 2.23 or 10.3) and compliance with Regulations 20,
21 of Chapter 4 of MARPOL Annex VI is to be verified in accordance with this accuracy.
4
Fuel consumption and Fuel Conversion Factor
4.1
General
The conversion factor CF and the specific fuel consumption, SFC, are determined from the
results recorded in the parent engine NOx Technical File as defined in the NOx Technical
Code 2008.
The fuel grade used during the test of the engine in the test bed measurement of SFC
determines the value of the CF conversion factor according to the table provided under
paragraph “CF ; Conversion factor between fuel consumption and CO2 emission” of the
IMO Calculation Guidelines.
SFC is the corrected specific fuel consumption, measured in g/kWh, of the engines or steam
turbines as defined under paragraph “SFC,Certfied specific fuel consumption” of the IMO
Calculation guidelines.
For main engines certified to the E2 or E3 test cycles of the NOx Technical Code 2008, the
engine Specific Fuel Consumption (SFCME(i)) is that recorded in the test report included in a
NOx Technical File for the parent engine(s) at 75% of MCR power.
For engines certified to the D2 or C1 test cycles of the NOx Technical Code 2008, the engine
Specific Fuel Consumption (SFCAE(i)) is that recorded in the test report included in a NOx
Technical File for the parent engine(s) at 50% of MCR power or torque rating.
At the design stage, in case of unavailability of test reports in the NOx Technical File, the
SFC value given by the manufacturer with the addition of the guarantee tolerance is to be
used.
4.2
Dual-fuel engines
Gas fuel may be used as primary fuel for one or more of the main and auxiliary engine(s) in
accordance with the IMO Verification Guidelines.
For these dual-fuel engines, the CF factor and the Specific Fuel Consumption for gas (LNG)
and for pilot fuel should be combined at the relevant EEDI load point as described in the
IMO Calculation Guidelines.
4.3
LNG carriers with steam turbine propulsion
The Specific Fuel Consumption of the steam turbine should be determined during the running
tests of the main boilers and steam turbines on board under load during the sea trials. For
preliminary estimate of EEDI, manufacturer’s certificate is to be used.
Page 4 of 74
2020 Industry Guidelines for calculation and verification of EEDI
5
Capacity, power and speed
5.1
Capacity
The capacity of the ship is computed as a function of the gross tonnage for passenger and
cruise passenger ships and of the deadweight for other types of ships as indicated the IMO
Calculation Guidelines.
For the computation of the deadweight according to the IMO Calculation Guidelines, the
lightweight of the ship and the displacement at the summer load draught are to be based on
the results of the inclining test or lightweight check provided in the final stability booklet. At
the design stage, the deadweight may be taken in the provisional documentation.
5.2
Power
The installed power for EEDI determination is taking into account the propulsion power and in
general a fixed part of the auxiliary power, measured at the output of the crankshaft of main
or auxiliary engine.
For LNG carriers having diesel electric propulsion system, the power PME is 83% of the rated
output of the electrical propulsion motor(s) divided by the electrical chain efficiency from the
output of the auxiliary engines to the output of the propulsion motor(s).
The total propulsion power is conventionally taken as follows:
𝑃
𝑃
∙𝜂
∙𝜂
In this formula:
●
The value of PME(i) may be limited by verified technical means (see 6 below)
●
The total propulsion power may be limited by verified technical means. In particular
an electronic engine control system may limit the total propulsion power, whatever
the number of engines in function (see 6 below)
If shaft motors are installed (PTI), then in principle 75% of the shaft motor propulsion power is
accounted for in the EEDI calculation. Detailed explanation about this is given in section 6.
The auxiliary power can be nominally defined as a specified proportion of main engine power
aiming to cover normal maximum sea load for propulsion and accommodation1. The nominal
values are 2.5% of main engine power plus 250 kW for installed main engine power equal to
or above 10 MW. 5% of main engine power will be accounted if less than 10 MW main engine
power is installed. Alternatively, as explained below, the value for auxiliary power can be
taken from the electric power table (EPT) of the ship.
1
under “PAE ; Auxiliary engine power” of the IMO Calculation Guidelines.
Page 5 of 74
2020 Industry Guidelines for calculation and verification of EEDI
For Passenger ships, Ro-Ro Passenger Ships and Cruise Passenger Ships, the PAE value
should be estimated by the consumed electric power (excluding propulsion) in conditions
when the ship is engaged in a voyage at reference speed (Vref), as given in the electric
power table (EPT), divided by the average efficiency of the generator(s) weighted by power.
As an option for other vessel types, if the difference between PAE value calculated by
paragraphs “PAE ; Auxiliary engine power” of IMO Calculation Guidelines and PAE based
on EPT, leads to a variation of the computed EEDI value exceeding 1%, the value for
auxiliary power could be taken from the EPT.
5.3
Speed Vref
The speed Vref is the ship speed, measured in knots, verified during sea trials and corrected
to be given in the following ideal conditions:
● in deep water of 15°C
● assuming the weather is calm with no wind, no current and no waves
● in the loading condition corresponding to the Capacity
● at the total propulsion power defined in 5.2 taking into account shaft generators and
shaft motors
6
Shaft generator and shaft motor
6.1
Introduction and background
As for paragraphs “PPTO(i) ; Shaft generator” and “PPTI(i) ; Shaft Motor” of IMO Calculation
Guidelines, content of this section applies to ships other than LNG carriers having dieselelectric propulsion system.
Ships need electrical power for the operation of engine auxiliary systems, other systems,
crew accommodation and for any cargo purposes. This electrical power can be generated by
diesel-generator sets (gen-sets), shaft generators, waste heat recovery systems driving a
generator and possibly by other innovative technologies, e.g. solar panels.
Diesel-generator sets and shaft generators are the most common systems. While dieselgenerator sets use a diesel engine powering a generator, a shaft generator is driven by the
main engine. It is considered that due to the better efficiency of the main engine and
efficiency of the shaft generator less CO2 is emitted compared to gen-set operation.
The EEDI formula expresses the propulsion power of a vessel as 75% of the main engine
power PME. It is also termed shaft power PS, which corresponds to the ship’s speed Vref in the
EEDI formula.
PAE - the auxiliary power - is also included in the EEDI formula. However, this power demand
is largely dependent on loading and trading patterns and it must also incorporate safety
aspects, for example, the provision of a spare generator set. As noted in section 5, the
auxiliary power can generally be taken into account as a fixed proportion of the main engine
power (i.e. nominally 2.5% plus 250kW) 2.
2
c.f.: precise instruction in IMO Calculation Guidelines.
Page 6 of 74
2020 Industry Guidelines for calculation and verification of EEDI
The use of shaft generators is a well proven and often applied technology, particularly for
high electrical power demands related to the payload e.g. reefer containers. Usually a ship
design implements a main engine to reach the envisaged speed with some provision of sea
margin. For the use of a shaft generator past practice and understanding was to install a
bigger main engine to reach the same speed compared to the design without a shaft
generator and to then have the excess power available from the main engine at any time for
generation of electrical power. As a rule of thumb, one more cylinder was added to the main
engine to cover this additional power demand.
The difficulty with this issue for calculation of the EEDI is that the excess power could be
used to move the ship faster in the case where the shaft generator is not in use which would
produce a distortion between ship designs which are otherwise the same.
The IMO Calculation Guidelines take these circumstances into account and offer options for
the use of shaft generators. These options are described in detail, below.
Further, electric shaft motors operate similarly to shaft generators; sometimes a shaft
generator can act as a shaft motor. The possible influence of shaft motors has also been
taken into account in the IMO Calculation Guidelines and is also illustrated, below.
6.2
Main engine power without shaft generators
The main engines are solely used for the ship’s propulsion. For the purpose of the EEDI, the
main engine power is 75 % of the rated installed power MCRME for each main engine:
PME (i )  0.75  MCRME (i )
6.3
Main engine power with shaft generators
Shaft generators produce electric power using power from the prime mover (main engine).
Therefore the power used for the shaft generator is not available for the propulsion. Hence
MCRME is the sum of the power needed for propulsion and the power needed for the shaft
generator. Thus at least a part of the shaft generator’s power should be deductible from the
main engine power (PME).
The power driving the shaft generator is not only deducted in the calculation. As this power is
not available for propulsion this yields a reduced reference speed. The speed is to be
determined from the power curve obtained at the sea trial as explained in the schematic
figure provided in paragraph “Option 2 of PPTO(i) ; Shaft generator” of the IMO Calculation
Guidelines.
It has been defined that 75% of the main engine power is entered in the EEDI calculation. To
induce no confusion in the calculation framework, it has therefore also been defined to take
into account 75% of the shaft power take off.
For the calculation of the effect of shaft generators, two options are available.
Page 7 of 74
2020 Industry Guidelines for calculation and verification of EEDI
6.3.1
Option 1
For this option, PPTO(i) is defined as 75% of the rated electrical output power MCRPTO of each
shaft generator. The maximum allowable deduction is limited by the auxiliary power PAE as
described in Paragraph “PAE ; Auxiliary engine power” of the IMO Calculation Guidelines.
Then the main engine power PME is:
𝑃
0.75
𝑃
𝑀𝐶𝑅
0.75
𝑀𝐶𝑅
𝑃
𝑤𝑖𝑡ℎ 0.75
𝑃
𝑃
This means, that only the maximum amount of shaft generator power that is equal to PAE is
deductible from the main engine power. In doing so, 75% of the shaft generator power to be
used in the EEDI calculation must NOT be greater than the auxiliary power calculated in
accordance to Para. “PAE ; Auxiliary engine power” of IMO Calculation Guidelines.
Higher shaft generators output than PAE will not be accounted for under option 1.
6.3.2
Option 2
The main engine power PME to be considered for the calculation of the EEDI is defined as
75% of the power to which the propulsion system is limited. This can be achieved by any
verified technical means, e.g. by electronic engine controls.
𝑃
0.75
𝑃
,
This option is to cover designs with the need for very high power requirements (e.g.,
pertaining to the cargo). With this option it is ensured that the higher main engine power
cannot be used for a higher ship speed. This can be safeguarded by the use of verified
technical devices limiting the power to the propulsor.
For example, consider a ship having a 15 MW main engine with a 3 MW shaft generator. The
shaft limit is verified to 12 MW. The EEDI is then calculated with only 75% of 12 MW as main
engine power as, in any case of operation, no more power than 12 MW can be delivered to
the propulsor, irrespective of whether a shaft generator is in use or not.
It is to be noted that the guidelines do not stipulate any limits as to the value of the shaft limit
in relation to main engine power or shaft generator power.
6.3.3
The use of specific fuel oil consumption and CF-factor
Shaft generators are driven by the main engine, therefore the specific fuel oil consumption of
the main engine is allowed to be used to the full extent if 75% of the shaft generator power is
equal to PAE.
In the case shaft generator power is less than PAE then 75% of the shaft generator power is
calculated with the main engine's specific fuel oil consumption and the remaining part of the
total PAE power is calculated with SFC of the auxiliaries (SFCAE).
The same applies to the conversion factor CF, if different fuels are used in the EEDI
calculation.
Page 8 of 74
2020 Industry Guidelines for calculation and verification of EEDI
6.4
Total shaft power with shaft motors
In the case where shaft motor(s) are installed, the same guiding principles as explained for
shaft generators, above, apply. But in contrast to shaft generators, motors do increase the
total power to the propulsor and do increase ships’ speed and therefore must be included in
the total shaft power within the EEDI calculation. The total shaft power is thus main engine(s)
power plus the additional shaft motor(s) power:
𝑃
𝑃
,
Where:
𝑃
,
0.75 ∙ 𝑃
,
∙𝜂
and ΣPME may be 0(zero) if the ship is a diesel-electric cruise passenger ship.
Similar to the shaft generators, only 75% of the rated power consumption PSM,max (i.e. rated
motor output divided by the motor efficiency) of each shaft motor divided by the weighted
average efficiency of the generator(s)  Gen is taken into account for EEDI calculation3.
𝑃
∑ 0.75 ∙ 𝑃
𝜂
,
Figure 1.1 provides the notations used for the power and efficiencies used in IMO Calculation
Guidelines and the present document.
Figure 1.1: flow of power in a generic shaft motor installation
A power limitation similar to that described above for shaft generators can also be used for
shaft motors. So if a verified technical measure is in place to limit the propulsion output, only
75% of limited power is to be used for EEDI calculation and also for that limited power Vref is
determined.
3
The efficiency of shaft generators in the previous section has consciously not been taken into account in
the denominator as inefficient generator(s) would increase the deductible power.
Page 9 of 74
2020 Industry Guidelines for calculation and verification of EEDI
A diagram is inserted to highlight where the mechanical and electrical efficiencies or the
related devices (PTI and Generator’s) are located:
Figure 1.2: Typical arrangement of propulsion and electric power system
6.5
Calculation examples
For these calculation examples the ships’ following main parameters are set as:
MCRME = 20,000 kW
Capacity = 20,000 DWT
CF,ME = 3.206
CF,AE = 3.206
SFCME = 190 g/kWh
SFCAE = 215 g/kWh
vref = 20 kn (without shaft generator/motor)
6.5.1
One main engine, no shaft generator
MCRME  20,000kW
PME  0.75  MCRME  0.75  20,000kW  15,000kW
PAE  0.025  20,000 250kW  750kW
EEDI  15,000  3.206 190 750  3.206  215/20  20,000
 24.1 g CO2 / t nm
Page 10 of 74
2020 Industry Guidelines for calculation and verification of EEDI
6.5.2
One main engine, 0.75 x PPTO<PAE, option 1
MCRPTO  500kW
PPTO  500kW  0.75  375kW
MCRME  20,000kW
PME  0.75  MCRME  PPTO   0.75  20,000kW  375kW   14,719kW
PAE  0.025  MCRME  250kW  750kW
vref  19.89kn : The speed at PME determined from the power curve
EEDI  PME  CF ,ME  SCFME   0.75 PPTO  CF ,ME  SCFME   PAE  0.75  PPTO  CF , AE  SFCAE /DWT  vref
 23.8 g CO2 / t nm
6.5.3
 1%
One main engine, 0.75 x PPTO=PAE, option 1
MCRPTO  1,333kW
PPTO  1,333kW  0.75  1,000kW
MCRME  20,000kW
PME  0.75  MCRME  PPTO   0.75  20,000kW 1,000kW   14,250kW
PAE  0.025  MCRME  250kW  750kW
vref 19.71kn : The speed at PME determined from the power curve
v 
EEDI  PME  CF ,ME  SCFME   0.75  PPTO  CF ,ME  SCFME /DWT  ref
 23.2 g CO2 / t nm
6.5.4
 4%
One main engine with shaft generator, 0.75 x PPTO> PAE, option 1
MCRPTO  2,000kW
0.75  PPTO  0.75  2,000kW  0.75  1,125kW  PAE  PPTO  PAE / 0.75  1,000kW
MCRME  20,000kW
PME  0.75  MCRME  PPTO   0.75  20,000kW 1,000kW   14,250kW
PAE  0.025  MCRME  250kW  750kW
vref  19.71kn : The speed at PME determined from the power curve
EEDI  PME  CF ,ME  SCFME   0.75  PPTO  CF , ME  SCFME /DWT  vref
 23.2 g CO2 / t nm
6.5.5
 4%
One main engine with shaft generator, 0.75 x PPTO> PAE, option 2
MCRPTO  2,000kW
MCRME  20,000kW
PShaft,limit  18,000kW
PME 0.75  PShaft,limit   0.75  18,000kW   13,500kW
PAE  0.025  MCRME  250kW  750kW
vref 19.41kn : The speed at PME determined from the power curve
EEDI  PME  CF ,ME  SFCME   PAE  CF ,ME  SFCME /DWT  vref
 22.4 g CO2 / t nm
 7%
Page 11 of 74
2020 Industry Guidelines for calculation and verification of EEDI
6.5.6
One main engine, one shaft motor
MCRME  18,000kW
PME  0.75  MCRME  0.75 18,000kW  13,500kW
𝑃
0.025
𝑀𝐶𝑅
250𝑘𝑊
0.025
𝑃
0.75
18000
1612.9
0.75
250𝑘𝑊
754𝑘𝑊
PSM,max  2,000kW
PPTI  0.75  PSM,max /Gen  1,612.9kW
PTI  0.97
Gen  0.93
PShaft  PME  PPTI ,Shaft  PME  (PPTI PTI ) Gen  13,500kW  (1612.9  0.97)  0.93  14,955kW
vref  20kn
EEDI = ((PME X CF, ME X SFC ME )+(PAE X CF, AE X SFCAE )+ (PPTI X CF, AE X SFCAE))/(DWT X Vref)
 24.6 g CO2 / t nm
  2%
Page 12 of 74
2020 Industry Guidelines for calculation and verification of EEDI
7
Weather factor fw
fw is a non-dimensional coefficient indicating the decrease of speed in representative sea
conditions of wave height, wave frequency and wind speed (e.g. Beaufort Scale 6), and is
taken as 1.0 for the calculation of attained EEDI.
When a calculated fw factor is used, the attained EEDI using calculated fw shall be presented
as "attained EEDIweather" in order to clearly distinguish it from the attained EEDI under
regulations 20 in MARPOL Annex VI.
Guidelines for the calculation of the coefficient fw for the decrease of ship speed in respective
sea conditions are provided in MEPC.1/Circ.796, as amended.
8
Correction factor for ship specific design elements fj
Except in the cases listed below, the value of the fj factor is 1.0.
For Finnish-Swedish ice class notations or equivalent notations of the Classification
Societies, the fj power correction factor is indicated in the IMO Calculation Guidelines4.
For shuttle tankers with propulsion redundancy defined as oil tankers between 80,000 and
160,000 deadweight equipped with dual-engines and twin-propellers and assigned the class
notations covering dynamic positioning and propulsion redundancy, the fj factor is 0.77.
The total shaft propulsion power of shuttle tankers with redundancy is usually not limited by
verified technical means.
For ro-ro cargo and ro-ro passenger ships, the correction factor fjRoRo is to be computed according
to the IMO calculation Guidelines.
For general cargo ships, the correction factor fj is to be computed according to the
IMO Calculation Guidelines.
fj factors for ice-class and for ship’s type can be cumulated (multiplied) for ice-classed general
cargo ships or ro-ro cargo or ro-ro passenger ships.
9
Capacity factor fi and Correction Factor fm for ice-classed ships having IA Super or IA
Except in the cases listed below, the value of the fi factor is 1.0.
For Finnish-Swedish ice class notations or equivalent notations of the Classification
Societies, the fi capacity correction factor is indicated in the IMO Calculation Guidelines.4
For a ship with voluntary structural enhancement, the fiVSE ship specific voluntary structural
enhancement factor is to be computed according to the IMO Calculation Guidelines.
For bulk carriers and oil tankers built in accordance with the Common Structural Rules and
assigned the class notation CSR, the fiCSR factor is to be computed according to the IMO
Calculation Guidelines.
fi capacity factors can be cumulated (multiplied), but the reference design for calculation of
fiVSE is to comply with the ice notation and/or Common Structural Rules as the case may be.
For ice-classed ships having IA Super or IA, the factor, fm = 1.05 should apply according to
2.2.19 of the IMO Calculation Guidelines.
Page 13 of 74
2020 Industry Guidelines for calculation and verification of EEDI
10
Cubic capacity correction factor fc and cargo gears factor fl
Except in the cases listed below, the value of the fc and fl factors is 1.0.
For chemical tankers as defined in regulation 1.16.1 of MARPOL Annex II, the fc factor is to
be computed according to the IMO Calculation Guidelines.
For gas carriers having direct diesel driven propulsion constructed or adapted and used for
the carriage in bulk of liquefied natural gas, the fc factor is to be computed according to the
IMO Calculation Guidelines. This factor is not to be applied to LNG carriers defined in
regulation 2.38 of MARPOL Annex VI.
For ro-ro passenger ships having a DWT/GT-ratio of less than 0.25, the cubic capacity
correction factor fcRoPax is to be computed according to the IMO Calculation Guidelines.
For bulk carriers having R of less than 0.55 (e.g. wood chip carriers), the cubic capacity
correction factor , fc bulk carriers designed to carry light cargoes, = R-0.15 should apply
according to the IMO Calculation Guidelines. where, R is the capacity ratio of the
deadweight of the ship (tonnes) divided by the total cubic capacity of the cargo tanks of
the ship (m3)
For general cargo ships only equipped with cranes, side loaders or ro-ro ramps, the fl
correction factor is to be computed according to the IMO Calculation Guidelines.
11
Innovative energy efficient technologies
Innovative energy efficient technologies are to be taken into account according to the 2013
Guidance on treatment of innovative energy efficiency technologies for calculation and
verification of the attained EEDI, MEPC.1/Circ.815 as amended.
4
Tables 1 and 2 in IMO Calculation Guidelines refer to Finnish/Swedish ice classed ships usually trading in
the Baltic Sea. Justified alternative values for fi and fj factors may be accepted for ice-classed ships outside
this scope of application (e.g. very large ships or POLAR CLASS)
Page 14 of 74
2020 Industry Guidelines for calculation and verification of EEDI
12
Example of calculation
12.1 List of input parameters for calculation of EEDI
The input parameters used in the calculation of the EEDI are provided in Table 1.
The values of all these parameters are to be indicated in the EEDI Technical File and the
documents listed in the “source” column are to be submitted to the verifier.
For electrical generator, the rated electrical output in kW is related to the rated apparent
power output in kVA by the following relation: MCRPTO (kW) = KVAPTO * 0.8 where 0.8 is the
conventional power factor.
Table 1: input parameters for calculation of EEDI
Symbol
Name
Usage
Source
Scope
Service
Capacity, fi, fj and
For the
notation
fc factors
ship
Class
fj for shuttle tanker, Classification file
fiCSR
notations
Ice notation
fi, fj for ice class
Lpp
Length
fi, fj for ice class,
between
fjRoRo, fj for general
perpendiculars
cargo ships
(m)
BS
Breadth (m)
fjRoRo, fj for general
cargo ships
dS
Summer load
fjRoRo, fj for general
line draught (m)
cargo ships
∇
Volumetric
fjRoRo, fj for general
displacement
cargo ships
Δ
Displacement
deadweight, fiVSE,
final stability file
@ summer
fcRoPax, fl for general
load draught (t)
cargo ships, fc for
bulk carriers
LWT
Ligthweight (t)
deadweight, fiVSE,
Sheets of Submitter
fiCSR, fcRoPax fl for
calculation for
lightweightreferencedesign
general cargo
ships
lightweight check report
GT
Gross tonnage
Capacity, fcRoPax
PAE
Auxiliary
EEDI
Note: Computed from
engine power
engines & PTIs powers
(kW)
or electric power table
Vref
Reference
EEDI, fjRoRo, fj for
Sea trial report
speed (knot)
general cargo ships
Cube
Total cubic
fc for chemical
Tonnage file
capacity of the
cargo tanks
(m3)
Vgas(or
liquid)
SWL
Reach
Tank volume for
fuels (m3)
Safe working
load of the
crane (t)
Reach of the
crane (m)
tankers and gas
carriers
fDFgas, fDFliquid
Capacity plan
availability ratios
fl for general cargo
ships
fl for general cargo
ships
Page 15 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Symbol
MCR
Name
Rated installed
power (kW)
Usage
PME
MCRlim
Limited rated
output power
after PTO in
(kW)
Rated output
of motor (kW)
PME with PTO
option 2
MPPMotor
η
Electrical
efficiency
MCRSteamTurbine Rated installed
power (kW)
Fuel grade
SFC
KVAPTO
PPTI,Shaft
ηPTI
ηGEN
PSHAFTlim
PME for LNG
carriers having
diesel electric
propulsion system
PME for LNG
carriers having
diesel electric
propulsion system
PME for LNG
carriers having
steam turbine
propulsion system
CF, SFC
EEDI
Corrected
specific fuel
consumption
(g/kWh)
Rated
electrical
apparent
output power
(kVA)
Mechanical
output power
(kW)
efficiency
efficiency
power
power
Limited shaft
propulsion
power (kW)
Limited power
where means of
limitation are fitted
Source
EIAPP certificate or
nameplate (if less than
130 kW)
Verification file
Scope
Per
engine
(nME +
nGEN)
Certificate of the product
Certificate of the product
NOX Technical File of the
parent engine
NOx Technical File of the
parent engine
PME
Nameplate of the shaft
generator
Per shaft
generator
(nPTO)
EEDI
Nameplate of the shaft
motor
Per shaft
motor
(nPTI)
Verification file
12.2 Sample calculation of EEDI
A sample of document to be submitted to the verifier is provided in Appendix 2.
In addition, Appendix 6 contains a list of sample calculations of EEDI, as follows:
● Appendix 6.1: Cruise passenger ship with diesel-electric propulsion
● Appendix 6.2: LNG carrier with diesel-electric propulsion
● Appendix 6.3: Diesel-driven LNG carrier with re-liquefaction system
● Appendix 6.4: LNG carrier with steam turbine propulsion
Page 16 of 74
Per
generator
(nGEN)
Per
shaftline
(nSHAFT)
2020 Industry Guidelines for calculation and verification of EEDI
Part III - Verification of EEDI
13
Verification process
Attained EEDI is to be computed in accordance with the IMO Calculation Guidelines and Part
II of the present Industry Guidelines. Survey and certification of the EEDI are to be conducted
according to the IMO verification Guidelines. on two stages:
1. preliminary verification at the design stage
2. final verification at the sea trial
The flow of the survey and certification process is presented in Figure 2.
Figure 2: Flow of survey and certification process by verifier
14
Documents to be submitted
A sample of documents to be submitted to the verifier including additional information for
verification is provided in Appendix 2.
The following information/documents are to be submitted by the submitter to the verifier
at the design stage. Reference is to be made also to Appendix 1, Appendix 3 and
Appendix 4
Page 17 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Table 2: documents to be submitted at the design stage
EEDI Technical File
EEDI Technical File as defined in the IMO Verification
Guidelines. See example of the EEDI Technical File in
Appendix 1 of IMO Verification Guidelines.
NOx Technical File
Copy of the NOx Technical File and documented summary of
the SFC correction for each type of main and auxiliary engine
with copy of EIAPP certificate.
Electric Power Table
Ship lines and model
particulars
Verification file of power
limitation technical
arrangement
Power curves
Description of the towing
tank test facility and towing
tank test organisation quality
manual
Gas fuel oil general
arrangement plan
Towing Tank Tests Plan
Towing Tank Tests Report
Ship reference speed Vref
Note: if the NOx Technical File has not been approved at the
time of the preliminary verification, the SFC value with the
addition of the guarantee tolerance is to be provided by
Manufacturer. In this case, the NOx Technical File is to be
submitted at the final verification stage.
If PAE is significantly different from the values computed using
the formula in the IMO Calculation Guidelines
- Lines of ship
- Report including the particulars of the ship model and
propeller model
If the propulsion power is voluntarily limited by verified
technical means
Power-speed curves predicted at full scale in sea trial
condition and EEDI condition
If the verifier has no recent experience with the towing tank
test facility and the towing tank test organization quality
system is not ISO 9001 certified.
- Quality management system of the towing tank test
including process control, justifications concerning
repeatability and quality management processes
- Records of measuring equipment calibration as described in
Appendix 3
- Standard model-ship extrapolation and correlation method
(applied method and tests description)
If gas fuel is used as the primary fuel of the ship fitted with
dual fuel engines. Gas fuel storage tanks (with capacities)
and bunkering facilities are to be described.
Plan explaining the different steps of the towing tank tests
and the scheduled inspections allowing the verifier to check
compliance with the items listed in Appendix 1 concerning
tank tests
- Report of the results of the towing tank tests at sea trial and
EEDI condition as required in Appendix 4
- Values of the experience-based parameters defined in the
standard model-ship correlation method used by the towing
tank test organization/shipyard
- Reasons for exempting a towing tank test, only if applicable
- Numerical calculations report and validation file of these
calculations, only if calculations are used to derive power
curves
Detailed calculation process of the ship speed, which is to
include the estimation basis of experience-based
parameters such as roughness coefficient, wake scaling
coefficient
Page 18 of 74
2020 Industry Guidelines for calculation and verification of EEDI
The following information is to be submitted by the submitter to the verifier at the final
verification stage (and before the sea trials for the programme of sea trials):
Table 3: documents to be submitted at the final verification stage
Programme of sea trials
Description of the test procedure to be used for the speed
trial, with number of speed points to be measured and
indication of PTO/PTI to be in operation, if any.
Sea trials report
Report of sea trials with detailed computation of the
corrections allowing determination of the reference speed Vref
Final stability file
Final stability file including lightweight of the ship and
displacement table based on the results of the inclining test or
the lightweight check
Final power curves
Final power curve in the EEDI condition showing the speed
adjustment methodology
Revised EEDI Technical File Including identification of the parameters differing from the
calculation performed at the initial verification stage
Ship lines
Lines of actual ship
Concerning confidential information of submitters that may be contained in the above
mentioned documents, reference is to be made to IMO Verification Guidelines,
15
Preliminary verification at the design stage
15.1 Scope of the verifier work
For the preliminary verification of the EEDI at the design stage, the verifier:
●
●
●
●
●
Review the EEDI Technical File, check that all the input parameters (see 12.1
above) are documented and justified and check that the possible omission of a
towing tank test has been properly justified
Check that the ITTC procedures and quality system are implemented by the
organization conducting the towing tank tests. The verifier should possibly audit the
quality management system of the towing tank if previous experience is insufficiently
demonstrated
Witness the towing tank tests according to a test plan initially agreed between the
submitter and the verifier
Check that the work done by the towing tank test organisation is consistent with the
present Guidelines. In particular, the verifier will check that the power curves at full
scale are determined in a consistent way between sea trials and EEDI loading
conditions, applying the same calculation process of the power curves and
considering justifiable differences of experience based parameters between the two
conditions
Issue a pre-verification report
15.2 Definitions
Experience-based parameters means parameters used in the determination of the scale
effects coefficients of correlation between the towing tank model scale results and the full
scale predictions of power curves.
This may include:
1. Hull roughness correction
2. Wake correction factor
3. Air resistance correction factor (due to superstructures and deck load)
4. Appendages correction factor (for appendages not present at model scale)
Page 19 of 74
2020 Industry Guidelines for calculation and verification of EEDI
5.
6.
7.
8.
Propeller cavitation correction factor
Propeller open-water characteristics correction
CP and CN (see below)
∆CFC and ∆wC (see below)
Ship of the same type means a ship of which hull form (expressed in the lines such as sheer
plan and body plan) excluding additional hull features such as fins and of which principal
particulars are identical to that of the base ship.
Definition of survey methods directly involving the verifier: Review and Witness.
Review means the act of examining documents in order to determine identification and
traceability and to confirm that requested information are present and that EEDI calculation
process conforms to relevant requirements.
Witness means the attendance at scheduled key steps of the towing tank tests in accordance
with the agreed Test Plan to the extent necessary to check compliance with the survey and
certification requirements.
15.3 Towing tank tests and numerical calculations
There are two loading conditions to be taken into account for EEDI: EEDI loading condition
and sea trial condition.
The speed power curves for these two loading conditions are to be based on towing tank test
measurements. Towing tank test means model towing tests, model self-propulsion tests and
model propeller open water tests.
Numerical calculations may be accepted as equivalent to model propeller open water tests.
Possible omission of towing tank tests is addressed in the IMO Verification Guidelines
Numerical calculations may be submitted to justify derivation of speed power curves, where
only one parent hull form have been verified with towing tank tests, in order to evaluate the
effect of additional hull features such as fore bulb variations, fins and hydrodynamic energy
saving devices.
These numerical tests may include CFD calculation of propulsive efficiency at reference
speed Vref as well as hull resistance variations and propeller open water efficiency.
In order to be accepted, these numerical tests are to be carried out in accordance with
defined quality and technical standards (ITTC 7.5-03-01-04 at its latest revision or
equivalent). The comparison of the CFD-computed values of the unmodified parent hull form
with the results of the towing tank tests must be submitted for review.
15.4 Qualification of verifier personnel
Surveyors of the verifier are to confirm through review and witness as defined in 15.2 that the
calculation of EEDI is performed according to the relevant requirements listed in 1.1. The
surveyors are to be qualified to be able to carry out these tasks and procedures are to be in
place to ensure that their activities are monitored.
15.5 Review of the towing tank test organisation quality system
Page 20 of 74
2020 Industry Guidelines for calculation and verification of EEDI
The verifier is to familiarize with the towing tank test organization test facilities, measuring
equipment, standard model-ship extrapolation and correlation method (applied method and
tests description) and quality system for consideration of complying with the requirements of
15.6 prior to the test attendance when the verifier has no recent experience of the towing
tank test facilities.
When in addition the towing tank test organization quality control system is not certified
according to a recognized scheme (ISO 9001 or equivalent) the following additional
information relative to the towing tank test organization is to be submitted to the verifier:
1. descriptions of the towing tank test facility; this includes the name of the facility, the
particulars of towing tanks and towing equipment, and the records of calibration of
each monitoring equipment as described in Appendix 3
2. quality manual containing at least the information listed in the ITTC Sample quality
manual (2002 issue) Records of measuring equipment calibration as described in
Appendix 3
15.6 Review and Witness
The verifier is to review the EEDI Technical File, using also the other documents listed in
table 2 and submitted for information in order to verify the calculation of EEDI at design stage.
This review activity is described in Appendix 1. Since detailed process of the towing tank
tests depends on the practice of each submitter, sufficient information is to be included in the
document submitted to the verifier to show that the principal scheme of the towing tank test
process meets the requirements of the reference documents listed in Appendix 1 and
Appendix 4.
Prior to the start of the towing tank tests, the submitter is to submit a test plan to the verifier.
The verifier reviews the test plan and agrees with the submitter which scheduled inspections
will be performed with the verifier surveyor in attendance in order to perform the verifications
listed in Appendix 1 concerning the towing tank tests.
Following the indications of the agreed test plan, the submitter will notify the verifier for the
agreed tests to be witnessed. The submitter will advise the verifier of any changes to the
activities agreed in the Test Plan and provide the submitter with the towing tank test report
and results of trial speed prediction.
15.7 Model-ship correlation
Model-ship correlation method followed by the towing tank test organization or shipyard is to
be properly documented with reference to the 1978 ITTC Trial prediction method given in
ITTC Recommended Procedure 7.5-02-03-1.4 rev.02 of 2011 or subsequent revision,
mentioning the differences between the followed method and the 1978 ITTC trial prediction
method and their global equivalence.
Considering the formula giving the total full scale resistance coefficient of the ship with bilge
keels and other appendages:
𝑆
𝑆
𝐶
∙ 1 𝑘 ∙𝐶
Δ𝐶
𝐶
𝐶
𝐶
𝐶
𝑆
The way of calculating the form factor k, the roughness allowance ∆CF, the correlation
allowance CA, the air resistance coefficient CAAS and the appendages coefficient CAppS are to
Page 21 of 74
2020 Industry Guidelines for calculation and verification of EEDI
be documented (if they are taken as 0, this has to be indicated also), as indicated in Appendix
4.
The correlation method used is to be based on thrust identity and the correlation factors is to
be according to method 1 (CP – CN) or method 2 (∆CFC - ∆wC) of the 1978 ITTC Trial
prediction method. If the standard method used by the towing tank test organization doesn’t
fulfil these conditions, an additional analysis based on thrust identity is to be submitted to the
verifier.
The verifier will check that the power-speed curves obtained for the EEDI condition and sea
trial condition are obtained using the same calculation process and properly documented as
requested in Appendix 4 “Witnessing of model test procedures”. In particular, the verifier will
compare the differences between experience based coefficients Cp and ∆CFC between the
EEDI condition (full) and sea trial condition if different from EEDI condition () with the
indications given in Figures 3.1 and 3.2 extracted from a SAJ-ITTC study on a large number
of oil tankers. If the difference is significantly higher than the values reported in the Figures, a
proper justification of the values is to be submitted to the verifier.
NB: The trends in Figures 3.1 and 3.2 are based on limited data and may be revised in the
future. The displayed trends depend on the method used to analyze the model tests behind
the data including the form factor and other correlation factor relations. Other values may be
accepted if based on sufficient number of data.
Figure 3.1: Variation of CP- CPFull as a function of the displacement ratio
Page 22 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Figure 3.2: Variation of ∆CFC as a function of the displacement ratio
15.8 Pre-verification report
The verifier issues the report on the "Preliminary Verification of EEDI" after it has verified the
attained EEDI at the design stage in accordance with paragraphs 4.1 and 4.2 of the IMO
Verification Guidelines.
A sample of the report on the “Preliminary Verification of EEDI” is provided in Appendix 5.
16
Final verification at sea trial
16.1 Sea trial procedure
For the verification of the EEDI at sea trial stage, the verifier shall:
● Examine the programme of the sea trial to check that the test procedure and in
particular that the number of speed measurement points comply with the
requirements of the IMO Verification Guidelines (see note below).
● Perform a survey to ascertain the machinery characteristics of some important
electric load consumers and producers included in the EPT, if the power PAE is
directly computed from the EPT data’s.
● Attend the sea trial and notes the main parameters to be used for the final
calculation of the EEDI, as given under 4.3.3 of the IMO Verification Guidelines
Page 23 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Review the sea trial report provided by the submitter and check that the measured
power and speed have been corrected accordingly (see note below).
● Check that the power curve estimated for EEDI condition further to sea trial is
obtained by power adjustment.
● Review the revised EEDI Technical File.
● Issue or endorse the International Energy Efficiency Certificate.
●
Note: For application of the present Guidelines, sea conditions and ship speed should be
measured in accordance with ITTC Recommended Procedure 7.5-04-01-01.1 Speed and
Power Trials 2017 or ISO 15016:2015.
Table 4 lists data which are to be measured and recorded during sea trials:
Table 4: Measured data during sea trials
Symbol Name
Measurement
Time and duration of sea
trial
Draft marks readings
Air and sea temperature
Main engine setting
Machinery log
Ψ0
Course direction (rad)
Compass
VG
Speed over ground (m/s)
GPS
n
Propeller rpm (rpm)
Tachometer
PS
Power measured (kW)
Torsion meter or strain gauges (for
torque measurement) or any alternative
method that offer an equivalent level of
precision and accuracy of power
measurement
VWR
Relative wind velocity (m/s) Wind indicator
ΨWR
Relative wind direction (rad) See above
Tm
Mean wave period (seas
Visual observation by multiple
and swell) (s)
observers supplemented by hindcast
data or wave measuring devices (wave
buoy, wave radar, etc.)
H1/3
Significant wave height
See above
(seas and swell) (m)
χ
Incident angle of waves (
See above
seas and swell) (rad)
δR
Rudder angle (rad)
Rudder
β
Drift angle (rad)
GPS
Remark
Prior to the sea trial, the programme of the sea trials and , if available, additional documents
listed in table 3 are to be submitted to the verifier in order for the verifier to check the
procedure and to attend the sea trial and perform the verifications included in Appendix 1
concerning the sea trial.
The ship speed is to be measured at sea trial for at least three power settings of which range
includes the total propulsion power defined in 5.2 according to the requirements of the IMO
Verification Guidelines 4.3.6. This requirement applies individually to each ship, even if the
ship is a sister ship of a parent vessel.
If it is physically impossible to meet the conditions in the ISO15016:2015 or ITTC
Recommended Procedure 7.5-04-01-01, a practical treatment shall be allowed based on the
documented mutual agreement among the owner, the verifier and the shipbuilder.
Page 24 of 74
2020 Industry Guidelines for calculation and verification of EEDI
16.2 Estimation of the EEDI reference speed VRef
The adjustment procedure is applicable to the most complex case where sea trials cannot be
conducted in EEDI loading condition. It is expected that this will be usually the case for cargo
ships like bulk carriers for instance.
Ship speed should be measured in accordance with ISO 15016:2015 or ITTC Recommended
Procedure 7.5-04-01-01.1, including the accuracy objectives under introduction section of
ISO 15016:2015. In particular, if the shaft torque measurement device cannot be installed
near the output flange of main engine, then the efficiency from the measured shaft power to
brake horse power should be taken into account.
Using the speed-power curve obtained from the sea trials in the trial condition, the conversion
of ship’s speed from the trial condition to the EEDI condition shall be carried out by power
adjustment as defined in Annex I of ISO 15016:2015.
The reference speed Vref should be determined based on sea trials which have been carried
out and evaluated in accordance with ISO 15016:2015 or equivalent (see note in 16.1).
Reference is made to paragraph 3 of Appendix 2 (Figure 3.1) where an example is provided.
16.3 Revision of EEDI Technical File
Reference is to be made to para 4.3.13 and para 4.3.14 of the IMO Verification Guidelines.
17
Verification of the EEDI in case of major conversion
In this section, a major conversion is defined as in MARPOL Annex VI regulation 2.24 and
interpretations in MEPC.1/Circ.795/ Rev4 subject to the approval of the Administration.
For verification of the attained EEDI after a major conversion, no speed trials are necessary if
the conversion or modifications don’t involve a variation in reference speed.
In case of conversion, the verifier will review the modified EEDI Technical File. If the review
leads to the conclusion that the modifications couldn’t cause the ship to exceed the applicable
required EEDI, the verifier will not request speed trials.
If such conclusion cannot be reached, like in the case of a lengthening of the ship, or
increase of propulsion power of 10% or more, speed trials will be required.
If an Owner voluntarily requests re-certification of EEDI with IEE Certificate reissuance on the
basis of an improvement to the ship efficiency, the verifier may request speed trials in order to
validate the attained EEDI value improvement.
If speed trials are performed after conversion or modifications changing the attained EEDI
value, tank tests verification is to be requested if the speed trials conditions differ from the
EEDI condition. In this case, numerical calculations performed in accordance with defined
quality and technical standards (ITTC 7.5-03-01-04 at its latest revision or equivalent)
replacing tank tests may be accepted by the verifier to quantify influence of the hull
modifications.
In case of major conversion of a ship without prior EEDI, EEDI computation is not required,
except if the Administration considers that due to the extensive character of the conversion,
the ship is to be considered as a new one.
Page 25 of 74
2020 Industry Guidelines for calculation and verification of EEDI
APPENDIX 1
Review and witness points
Ref.
Function
01
EEDI Technical File
Survey
method
Review
02
Limitation of power
Review
03
Electric Power Table
Review
04
Calibration of towing tank
test measuring
equipment
Model tests – ship model
Review
&
witness
Review
&
witness
Review
&
witness
Review
&
witness
05
06
Model tests – propeller
model
07
Model tests – Resistance
test, Propulsion test,
Propeller open water test
Reference document
IMO Verification
Guidelines
This document
IMO Calculation
Guidelines
Appendix 2 to IMO
Calculation Guidelines
Appendix 2 to IMO
Verification Guidelines
Appendix 3
Appendix 4
Appendix 4
Appendix 4
Documentation
available to verifier
Documents in table 2
Remarks
Verification file of
limitation technical
means
EPT
EPT-EEDI form
Only If means of limitation are fitted
Calibration reports
Check at random that measuring devices
are well identified and that calibration
reports are currently valid
Checks described in Appendix 4.1
Ship lines plan &
offsets table
Ship model report
Propeller model report
Towing tank tests
report
Page 26 of 74
As described under paragraph 5.2 of
this industry guideline.
Checks described in Appendix 4.2
Checks described in Appendix 4.3
Note: propeller open water test is not
needed if a stock propeller is used. In this
case, the open water characteristics of the
stock propeller are to be annexed to the
towing tank tests report.
2020 Industry Guidelines for calculation and verification of EEDI
Ref.
Function
08
Model-ship extrapolation
and correlation
Survey
method
Review
Reference document
ITTC 7.5-02-03-01.4 1978
ITTC performance
prediction method (rev.04
of 2017 or subsequent
revision)
Documentation
available to verifier
Documents in table 2
Appendix 4
This document 15.7
09
Review
ITTC 7.5-03-01-04 (latest
revision) or equivalent
Witness
11
Numerical calculations
replacing towing tank
tests
Electrical machinery
survey prior to sea trials
Programme of sea trials
Appendix 2 to IMO
Verification Guidelines
IMO Verification
Guidelines
12
Sea trials
Witness
10
Review
ISO 15016:2015 or ITTC
7.5-04-01-01.1 (latest
revision)
Report of calculations
Remarks
Check that the ship-model correlation is
based on thrust identity with correlation
factor according to method 1 ( CP – CN) or
method 2 (∆CFC - ∆wC)
Check that the power-speed curves
obtained for the EEDI condition and sea trial
condition are obtained using the same
calculation process with justified values of
experience-based parameters
For justification of calculations replacing
model tests refer to 15.3.
Only if PAE is computed from EPT
Programme of sea trials Check minimum number of measurement
points (3)
Check the EEDI condition in EPT (if PAE is
computed from EPT)
Check:
• Propulsion power, particulars of the
engines
•
Draught and trim
• Sea conditions
•
Ship speed
•
Shaft power & rpm
Check operation of means of limitations of
engines or shaft power (if fitted)
Check the power consumption of selected
consumers included in sea trials condition
EPT (if PAE is computed from EPT)
Page 27 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Ref.
Function
13
Sea trials – corrections
calculation
14
Sea trials – adjustment
from trial condition to
EEDI condition
EEDI Technical File –
revised after sea trials
15
Survey
method
Review
Reference document
ISO 15016:2015 or ITTC
Recommended Procedure
7.5-04-01-01.1( latest
revision)
Documentation
available to verifier
Sea trials report
Review
This document 16.2
Power curves after sea
trial
Review
IMO Verification
Guidelines
Revised EEDI
Technical File
Page 28 of 74
Remarks
Check that the displacement and trim of the
ship in sea trial condition has been obtained
with sufficient accuracy
Check compliance with ISO 15016:2015 or
ITTC Recommended Procedure 7.5-04-0101.1( latest revision)
Check that the power curve estimated for
EEDI condition is obtained by power
adjustment
Check that the file has been updated
according to sea trials results
2020 Industry Guidelines for calculation and verification of EEDI
APPENDIX 2
Sample of document to be submitted to the verifier including
additional information for verification
Caution
Protection of Intellectual Property Rights
This document contains confidential information (defined as additional information) of
submitters. Additional information should be treated as strictly confidential by the verifier and
failure to do so may lead to penalties. The verifier should note following requirements of IMO
Verification Guidelines:
“4.1.2 The information used in the verification process may contain confidential information of
submitters, which requires Intellectual Property Rights (IPR) protection. In the case where
the submitter want a non-disclosure agreement with the verifier, the additional information
should be provided to the verifier upon mutually agreed terms and conditions.”
Revision list
B
01/05/2014
A
01/01/2013
REV. ISSUE
DATE
Final stage: sections 1 to 16
Design stage: sections 1 to 13
DESCRIPTION
Page 29 of 74
XYZ
YYY
ZZZ
XXX
YYY
ZZZ
DRAWN CHECKED APPROVED
2020 Industry Guidelines for calculation and verification of EEDI
1
General
This calculation of the Energy Efficiency Design Index (EEDI) is based on :
 All adopted MEPC resolutions regarding amendments to Chapter 4 of MARPOL Annex VI
prior to the date of revision of this guideline
 Resolution MEPC.308(73) 2018 Guidelines on the method of calculation of the attained
Energy Efficiency Design Index (EEDI) for new ships, as amended.
Calculations are being dealt with according to the Industry Guidelines on calculation and
verification of EEDI, 2020 issue.
2
2.1
Data
Main parameters
Parameter
Owner
Builder
Hull No.
IMO No.
Ship’s type
Ship classification notations
Value
OWNER
YARD
12346
94111XX
Bulk carrier
I HULL, MACH, Bulk
Carrier CSR
BC-A (holds 2 and 4 may
be empty) ESP
GRAB[20]
Unrestricted Navigation
AUT-UMS, GREEN
PASSPORT,
INWATERSURVEY,
MON-SHAFT
HULL PARTICULARS
Length overall
Length between perpendiculars
Breadth, moulded
Depth, moulded
Summer load line draught, moulded
Deadweight at summer load line draught
Lightweight
Owner’s voluntary structural enhancements
MAIN ENGINE
Type & manufacturer
Specified Maximum Continuous Rating
(SMCR)
SFC at 75% SMCR
Number of set
Fuel type
Reference
191.0 m
185.0 m
32.25 m
17.9 m
12.70 m
55000 DWT
11590 tons
No
BUILDER 6SRT60ME
9200 kW x 105 rpm
171 g/kWh
1
Diesel/Gas oil
AUXILIARY ENGINES
Page 30 of 74
See paragraph
10.1
2020 Industry Guidelines for calculation and verification of EEDI
Parameter
Type & manufacturer
Specified Maximum Continuous Rating
(SMCR)
SFC at 50% SMCR
Value
BUILDER 5X28
650 kW x 700 rpm
Reference
205 g/kWh
SFC at 75% SMCR (In case PAE is
estimated by the electric power table
(EPT) for the reason that PAE
computed using the formula in the
IMO Calculation Guidelines is
significantly different from the total
power used at normal seagoing)
Number of set
Fuel type
199 g/kWh
See paragraph
10.2
See paragraph
10.2
3
Diesel/Gas oil
OVERVIEW OF PROPULSION SYSTEM
AND ELECTRICITY SUPPLY SYSTEM
SHAFT GENERATORS
Type & manufacturer
Rated electrical output power
Number of set
See section 4
None
0
SHAFT MOTORS
Type & manufacturer
Rated power consumption
Efficiency
Number of set
0
MAIN GENERATORS
Type & manufacturer
Rated output
Efficiency
Number of set
BUILDER AC120
605 kWe
0.93
3
PROPULSION SHAFT
Propeller diameter
Propeller number of blades
Voluntarily limited shaft propulsion power
Number of set
5.9 m
4
No
1
None
ENERGY SAVING EQUIPMENT
Description of energy saving equipment
Power reduction or power output
2.2
See section 9
Propeller boss cap fins
None
Preliminary verification of attained EEDI
Parameter
TOWING TANK TEST ORGANIZATION
Identification of organization
ISO Certification or previous experience?
Value
Reference
TEST corp.
Previous
experience
See section 6.
TOWING TANK TESTS
Page 31 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Exemption of towing tank tests
Process and methodology of estimation of
the power curves
Ship model information
Propeller model information
EEDI & sea trial loading conditions
No
See section 7
See subparagraph 7.2.1
See subparagraph 7.2.2
EEDI:
mean draft: 12.7 m
Trim 0
Sea trial ( ballast ):
mean draft: 5.8 m
Trim 2.6 m by
stern
Propeller open water diagram (model, ship)
Experience based parameters
Power curves at full scale
Ship Reference speed
See paragraph 7.4
See paragraph 7.3
See section 3
14.25 knots
ELECTRIC POWER TABLE
(as necessary, as defined in IMO
Calculation Guidelines)
As
described
under
paragraph
5.2 of this
industry
guideline.
See section 5
CALCULATION OF ATTAINED EEDI
5.06
See section 11
CALCULATION OF REQUIRED EEDI
5.27
See section 12
CALCULATION OF ATTAINED EEDIweather
Not calculated
See section 13
2.3
Final verification of attained EEDI
Parameter
SEA TRIAL LOADING CONDITION
POWER CURVES
Sea trial report with corrections
Ship Reference speed
Value
See section 3
See section 15
14.65 knots
FINAL DEADWEIGHT
Displacement
Lightweight
Deadweight
66171 tons
11621 tons
54550 DWT
FINAL ATTAINED EEDI
4.96
3
Reference
See section 14
See section 16
Power curves
The power curves estimated at the design stage and modified after the sea trials are given in
Figure 3.1.
Page 32 of 74
2020 Industry Guidelines for calculation and verification of EEDI
75% of MCR
Figure 3.1: Power curves
4
Overview of propulsion system and electric power system
Figure 4.1 shows the connections within the propulsion and electric power supply systems.
The characteristics of the main engines, auxiliary engines, electrical generators and
propulsion electrical motors are given in table 2.1.
Page 33 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Figure 4.1 scheme of the propulsion and power generation systems
5
Electric power table
The electric power for the calculation of EEDI is provided in table 5.1.
Table 5.1: Electric power table for calculation of PAE
Id
Grou
p
Description
Mech.
Power
"Pm"
El.
Motor
output
Efficie
n. "e"
Rated
el.
Power
"Pr"
load
facto
r "kl"
duty
facto
r
"kd"
time
facto
r "kt"
use
facto
r
"ku"
Necessa
ry power
"Pload"
1 A
STEERING GEAR
N.A.
N.A.
N.A.
45,0
0,9
1
0,3
0,27
12.2
2 A
HULL CATHODIC PROTECTION
N.A.
N.A.
N.A.
10
1
1
1
1,00
10,0
3 A
CRANE
N.A.
N.A.
N.A.
10,00
0,2
1
1
0,20
2,0
4 A
COMPASS
N.A.
N.A.
N.A.
0,5
1
1
1
1,00
0,5
5 A
RADAR NO.1
N.A.
N.A.
N.A.
1,3
1
0,5
1
0,50
0,7
6 A
RADAR NO.2
N.A.
N.A.
N.A.
1,3
1
0,5
1
0,50
0,7
7 A
NAVIGATION EQUIPMENT
N.A.
N.A.
N.A.
5,0
1
1
1
1,00
5,0
8 A
INTERNAL COMM. EQUIPMENT
N.A.
N.A.
N.A.
2,5
1
1
0,1
0,10
0,2
9 A
RADIO EQUIPMENT
N.A.
N.A.
N.A.
3,5
1
1
0,1
0,10
0,4
N.A.
N.A.
N.A.
7,0
1
1
0,1
0,10
0,7
13 B
MOORING EQ.
MAIN COOLING SEA WATER
PUMP NO.1
MAIN COOLING SEA WATER
PUMP NO.2
MAIN COOLING SEA WATER
PUMP NO.3
14 B
15 B
16 B
10 A
11 B
12 B
28,0
30
0,925
30,3
0,9
0,66
1
0,59
18,0
28,0
30
0,925
30,3
0,9
0,66
1
0,59
18,0
28,0
30
0,925
30,3
0,9
0,66
1
0,59
18,0
LT COOLING FW PUMP NO.1
28,0
30
0,925
30,3
0,9
0,66
1
0,59
18,0
LT COOLING FW PUMP NO.2
28,0
30
0,925
30,3
0,9
0,66
1
0,59
18,0
LT COOLING FW PUMP NO.3
28,0
30
0,925
30,3
0,9
0,66
1
0,59
18,0
Page 34 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Id
Grou
p
Description
Mech.
Power
"Pm"
El.
Motor
output
Efficie
n. "e"
Rated
el.
Power
"Pr"
load
facto
r "kl"
duty
facto
r
"kd"
time
facto
r "kt"
use
facto
r
"ku"
Necessa
ry power
"Pload"
17 B
M/E COOLING WATER PUMP NO.1
13,0
15
0,9
14,4
1
0,5
1
0,50
7,2
18 B
M/E COOLING WATER PUMP NO.2
13,0
15
0,9
14,4
1
0,5
1
0,50
7,2
19 C
MAIN LUB. OIL PUMP NO.1
55,0
90
0,94
58,5
0,9
0,5
1
0,45
26,3
20 C
MAIN LUB. OIL PUMP NO.2
55,0
90
0,94
58,5
0,9
0,5
1
0,45
26,3
21 C
H.F.O. TRANSFER PUMP
6,0
7,5
0,88
6,8
1
1
0,1
0,10
0,7
22 C
D.O. TRANSFER PUMP
6,0
7,5
0,88
6,8
1
1
0,1
0,10
0,7
23 C
1,4
2,5
0,8
1,8
1
1
0,1
0,10
0,2
2,5
3,5
0,85
2,9
1
0,5
0,1
0,05
0,1
25 C
L.O. TRANSFER PUMP
TECHNICAL FRESH WATER PUMP
NO.1
TECHNICAL FRESH WATER PUMP
NO.2
2,5
3,5
0,85
2,9
1
0,5
0,1
0,05
0,1
26 C
E/R SUPPLY FAN NO.1
14,0
20
0,9
15,5
0,9
1
1
0,90
14,0
27 C
E/R SUPPLY FAN NO.2
14,0
20
0,9
15,5
0,9
1
1
0,90
14,0
28 C
E/R SUPPLY FAN NO.3
14,0
20
0,9
15,5
0,9
1
1
0,90
14,0
29 C
14,0
20
0,9
15,5
0,9
1
1
0,90
14,0
30 C
E/R SUPPLY FAN NO.4
PURIFIER ROOM
EXH.VENTILATOR
2,5
3
0,82
3,0
0,9
1
1
0,90
2,7
31 C
PUMP HFO SUPPLY UNIT NO.1
2,1
3
0,8
2,6
0,9
0,5
1
0,45
1,2
32 C
2,1
3
0,8
2,6
0,9
0,5
1
0,45
1,2
2,8
3,5
0,84
3,3
0,9
0,5
1
0,45
1,5
34 C
PUMP HFO SUPPLY UNIT NO.2
CIRC. PUMP FOR HFO SUPPLY
UNIT NO.1
CIRC. PUMP FOR HFO SUPPLY
UNIT NO.2
0,84
3,3
0,9
0,5
1
0,45
1,5
35 C
H.F.O. SEPARATOR NO.1
N.A.
N.A.
N.A.
6,5
0,9
0,5
0,9
0,41
2,6
36 C
H.F.O. SEPARATOR NO.2
N.A.
N.A.
N.A.
6,5
0,9
0,5
0,9
0,41
2,6
37 C
MAIN AIR COMPRESSER NO.1
N.A.
N.A.
N.A.
43,0
1
0,5
0,1
0,05
2,2
38 C
MAIN AIR COMPRESSER NO.2
N.A.
N.A.
N.A.
43,0
1
0,5
0,1
0,05
2,2
39 C
SERVICE AIR COMPRESSER
N.A.
N.A.
N.A.
22,0
1
1
0,1
0,10
2,2
40 C
VENT. AIR SUPPLY
N.A.
N.A.
N.A.
1,0
1
1
0,5
0,50
0,1
41 C
BILGE WATER SEPARATOR
N.A.
N.A.
N.A.
1,5
1
1
0,1
0,10
0,2
42 C
M/E L.O. SEPARATOR
N.A.
N.A.
N.A.
6,5
0,9
1
0,2
0,18
1,2
43 C
G/E L.O. SEPARATOR
N.A.
N.A.
N.A.
6,5
0,9
1
0,2
0,18
1,2
44 D
HYDROPHORE PUMP NO.1
2,8
4
0,84
3,3
1
0,5
0,1
0,05
0,2
45 D
HYDROPHORE PUMP NO.2
HOT WATER CIRCULATING PUMP
NO.1
HOT WATER CIRCULATING PUMP
NO.2
E/R WORKSHOP WELDING SPACE
EXH.
2,8
4
0,84
3,3
1
0,5
0,1
0,05
0,2
0,5
1,0
0,8
0,8
1
0,5
0,2
0,10
0,1
0,5
1,0
0,8
0,8
1
0,5
0,2
0,10
0,1
0,5
0,8
0,8
0,6
0,9
1
1
0,90
0,6
24 C
33 C
46 D
47 D
48 E
49 F
50 F
51 F
52 F
53 F
54 F
ECR COOLER UNIT
FAN FOR AIR CONDITIONING
PLANT
COMP. AIR CONDITIONING PLANT
NO.1
COMP. AIR CONDITIONING PLANT
NO.2
COMP. AIR CONDITIONING PLANT
NO.3
COMP. AIR CONDITIONING PLANT
NO.4
2,8
3,5
N.A.
N.A.
N.A.
4,2
1
1
0,5
0,50
2,1
N.A.
N.A.
N.A.
8,0
0,9
1
0,5
0,45
3,6
N.A.
N.A.
N.A.
10,0
0,9
1
0,5
0,45
4,5
N.A.
N.A.
N.A.
10,0
0,9
1
0,5
0,45
4,5
N.A.
N.A.
N.A.
10,0
0,9
1
0,5
0,45
4,5
N.A.
N.A.
N.A.
10,0
0,9
1
0,5
0,45
4,5
Page 35 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Id
Grou
p
Description
Mech.
Power
"Pm"
El.
Motor
output
Efficie
n. "e"
N.A.
N.A.
N.A.
1,5
0,9
1
0,5
0,45
0,7
N.A.
N.A.
N.A.
3,5
0,9
1
0,5
0,45
1,6
Rated
el.
Power
"Pr"
load
facto
r "kl"
duty
facto
r
"kd"
time
facto
r "kt"
use
facto
r
"ku"
Necessa
ry power
"Pload"
56 G
FAN FOR GALLEY AIR COND.
PLANT
COMP. FOR GALLEY AIR COND.
PLANT
57 G
REF. COMPRESSOR NO.1
N.A.
N.A.
N.A.
4,0
1
0,5
0,1
0,05
0,2
58 G
REF. COMPRESSOR NO.2
N.A.
N.A.
N.A.
4,0
1
0,5
0,1
0,05
0,2
59 G
GALLEY EQUIPMENT
N.A.
N.A.
N.A.
80,0
0,5
1
0,1
0,05
4,0
60 H
VAC. COLLECTION SYSTEM
2,4
3,0
0,8
3,0
1
1
1
1,00
3,0
61 H
GALLEY EXH.
1,2
1,5
0,8
1,5
1
1
1
1,00
1,5
62 H
LAUNDRY EXH.
0,8
0,1
1
1
1
1,00
0,1
63 H
SEWAGE TREATMENT
4,5
1
1
0,1
0,10
0,5
64 H
SEWAGE DISCHARGE
3,4
0,9
1
0,1
0,09
0,3
65 I
ACCOMMODATION LIGHTING
1
0,5
0,5
8,0
55 G
0,1
N.A.
0,15
N.A.
3
N.A.
7,5
0,88
N.A.
N.A.
N.A.
16,0
1
66 I
E/R LIGHTING
N.A.
N.A.
N.A.
18,0
1
1
1
1,00
18,0
67 I
NAVIGATION LIGHTING
N.A.
N.A.
N.A.
0,9
1
0,5
1
0,50
0,4
68 I
BACK. NAV. LIGHTING
N.A.
N.A.
N.A.
0,9
1
0,5
1 0,50
TOTAL POWER
0,4
354,0
PAE = Total Power / (average efficiency of generators) = 354/0.93 = 381 kW
6
Towing Tank test organization quality system
Towing tank tests will be performed in TEST corp.
The quality control system of the towing tank test organization TEST corp. has been
documented previously (see report 100 for the ship hull No. 12345) and the quality manual
and calibration records are available to the verifier.
The measuring equipment has not been modified since the issue of report 100 and is listed in
table 6.1.
Table 6.1: List of measuring equipment
Propeller
dynamometer
…
7
Manufacturer Model
Series
Lab. Id.
status
B&N
300
125-2
Calibrated
01/01/2011
6001
Estimation process of power curves at design stage
7.1 Test procedure
The tests and their analysis are conducted by TEST corp. applying their standard correlation
method (document is given in annex 1).
The method is based on thrust identity and references ITTC Recommended Procedure 7.5 02 - 03 -1.4 ITTC 1978 Trial Prediction Method (in its latest reviewed version of 2017), with
prediction of the full scale rpm and delivered power by use of the CP – CN correction factors.
The results are based on a Resistance Test, a Propulsion Test and use the Open Water
Characteristics of the model propeller used during the tests and the Propeller Open Water
Characteristics of the final propeller given in 7.4.
Page 36 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Results of the resistance tests and propulsion tests of the ship model are given in the report
of TEST corp. given in annex 2.
7.2 Speed prediction
The ship delivered power PD and rate of revolutions nS are determined from the following
equations:
𝑃
𝐶 ∙𝑃
𝑛
𝐶 ∙𝑛
Where CN and CP are experience-based factors and PDS (resp. nS) are the delivered power
(resp. rpm) obtained from the analysis of the towing tank tests.
The ship total resistance coefficient CTS is given by:
𝑆
𝑆
𝐶
∙ 1 𝑘 ∙𝐶
∆𝐶
𝐶
𝐶
𝐶
𝑆
Where:
SS:
ship hull wetted surface, here 9886 m2
SBK:
wetted surface of bilge keels
k:
form factor. Here 1+k = 1.38 over the speed range, determined according to ITTC
standard procedure 7.5-02-02-01
CFS:
ship frictional resistance coefficient (computed according to ITTC 1957 formula)
∆CF:
roughness allowance, computed according to Bowden-Davison formula. Here ∆CF =
0.000339
CR:
residual resistance coefficient
CAAS:
air resistance coefficient
CAppS: ship appendages (propeller boss cap fins) resistance coefficient, computed as
provided in annex 2.
The air resistance coefficient is computed according to the following formula:
𝜌 ∙𝐴
𝐶 ∙
𝐶
𝜌 ∙𝑆
Where:
CDA is the air drag coefficient, here 0.8
ρA and ρS are the air density and water density, respectively
AVS is the projected wind area, here 820 m2
CAAS = 7.9.10-5
The delivered power PD results of the towing tank tests are summarized in table 7.1 for the
EEDI condition (scantling draft) and in table 7.2 for the sea trial condition (light ballast draft).
Table 7.1: results of trial prediction in EEDI condition
Model reference: SX100 - model scale: 40
Loading condition: EEDI loading condition (12.70 m draft)
Resistance test:
Propulsion test: P001
Model propeller:
R001
Prop01
Ship
Propeller
Wake
Propeller
rpm on
Delivered
speed V factor
thrust TS
torque QS
ship nS
Power PD
w
-w
(kNm)
(kW)
TM
TS
(knot)
(kN)
12
0.098
522
467
78
3781
12.5
0.093
578
514
82
4362
Page 37 of 74
2020 Industry Guidelines for calculation and verification of EEDI
13
0.089
638
13.5
0.081
701
14
0.079
768
14.5
0.086
838
15
0.091
912
15.5
0.099
990
Experience-based factor CP: 1.01
Experience based factor CN: 1.02
563
615
669
727
786
849
86
90
93
97
101
105
5004
5710
6486
7333
8257
9261
Table 7.2: results of trial prediction in sea trial condition
Model reference: SX100 - model scale: 40
Loading condition: Sea trial condition (5.80 m draft)
Resistance test:
Model propeller:
Propulsion test: POO2
R002
Prop01
Ship
Wake
speed V factor
(knot)
wTM-wTS
Propeller
thrust TS
(kN)
Propeller
torque QS
(kNm)
12
0,079
406
12,5
0,081
451
13
0,083
500
13,5
0,085
551
14
0,087
606
14,5
0,088
664
15
0,091
725
15,5
0,089
790
Experience-based factor CP: 1.05
Experience based factor CN: 1.03
Delivered
Power PD
(kW)
rpm on
ship nS
379
418
459
503
549
597
648
701
72
76
79
83
87
90
94
98
2974
3445
3968
4545
5181
5878
6641
7474
The predicted results are represented on the speed curves given in Figure 3.1. The EEDI
condition results are indexed (Full, p), the sea trial condition results (Ballast, p).
7.3
Ship and propeller models
The ship model is at scale λ = 40. The characteristics are given in table 7.3.
Table 7.3: characteristics of the ship model
Identification (model number or similar)
SX 100
Material of construction
Wood
Principal dimensions
Length between perpendiculars (LPP)
4.625 m
Length of waterline (LWL)
4.700 m
Breadth (B)
0.806 m
Draught (T)
0.317 m
Design displacement (Δ) (kg, fresh water)
1008.7 kg
Wetted surface area
6.25 m2
Details of turbulence stimulation
Sand strips
Details of appendages
rudder
Tolerances of manufacture
+/- 2.5 mm on length
+/- 1 mm on breadth
Page 38 of 74
2020 Industry Guidelines for calculation and verification of EEDI
The propeller model used during the tests is a stock model with the following characteristics:
Table 7.4: characteristics of the stock propeller used during the tests
Identification (model number or similar)
Prop01
Materials of construction
aluminium
Blade number
4
Principal dimensions
Diameter
147.5 mm
Pitch-Diameter Ratio (P/D)
0.68
Expanded blade Area Ratio (AE/A0)
0.60
Thickness Ratio (t/D)
0.036
Hub/Boss Diameter (dh)
25 mm
Tolerances of manufacture
Diameter (D):
± 0.10 mm
Thickness ( t ):
± 0.10 mm
Blade width (c):
± 0.20 mm
Mean pitch at each radius (P/D):
………..± 0.5% of design value.
7.4
Open water characteristics of propeller
The open water characteristics of the stock model propeller are given in annex 2. The open
water characteristics of the ship propeller are given in Figure 7.1.
Figure 7.1: open water characteristics of ship propeller
Page 39 of 74
2020 Industry Guidelines for calculation and verification of EEDI
8
Lines and offsets of the ship
The ships lines and offsets table are given in Annex 3.
9
Description of energy saving equipment
9.1
Energy saving equipment of which effects are expressed as PAEeff(i) and/or Peff(i) in
the EEDI calculation formula
None here.
9.2
Other energy saving equipment
The propeller boss cap fins are described in annex 4.
10
Justification of SFC (documents attached to NOx technical file of the parent
engine)
10.1 Main engine
The shop test report for the parent main engine is provided in annex 5.1. The SFOC has
been corrected to ISO conditions.
10.2 Auxiliary engine
The technical file of the EIAPP certificate of the auxiliary engines is provided in annex 5.2.
The SFOC has been corrected to ISO conditions.
11
Calculation of attained EEDI at design stage
11.1 Input parameters and definitions
The EEDI quantities and intermediate calculations are listed in table 11.1:
EEDI
quantity
CFME
PME
Table 11.1: Parameters in attained EEDI calculation
Value
Remarks
3.206
6900 kW
SFCME
171 g/kWh
CFAE
PPTI
PAE
3.206
0
381 kW
Marine Diesel oil is used for shop test of the main engine
No shaft generator installed ( PPTO = 0)
MCR is 9200 kW PME = 0.75x9200 = 6 900 kW
According to parent engine shop test report in ISO conditions (see
10.1)
Marine diesel oil is used for shop test of the auxiliary engine
No shaft motor installed
MCR of the engine is 9200 kW, less than 10000kW
𝑃
0.05 ∙
𝑀𝐶𝑅
∑
𝑃
0.75
PAE = 0.05*9200 = 460 kW
According to electric power table included in table 5.1, ∑Pload(i) =
354 kW
The weighted average efficiency of generators = 0.93
(KWelec/kWmech)
PAE = ∑Pload(i) / 0.93 = 381 kW
The difference (460 – 381) KW is expected to vary EEDI by slightly
Page 40 of 74
2020 Industry Guidelines for calculation and verification of EEDI
SFCAE
(at 75%
MCR)
199 g/kWh
Peff
0
PAEeff
`feff
fj
fi
0
fm
1.0
fw
1.0
fc
Capacity
Vref
1.0
55000
14.25
knots
1.0
1.017
more than 1%, so 381 kW is considered.
According to technical file of EIAPP certificate in ISO conditions
(see 10.2). According to the IMO Calculation Guidelines, the
SFCAE at 75% MCR should be used when PAE is estimated by the
electric power table (EPT) for the reason that PAE computed using
the formula in the IMO Calculation Guidelines is significantly
different from the total power used at normal seagoing
No mechanical energy efficient devices
The propeller boss cap fins act by reducing ship resistance
No auxiliary power reduction
Not relevant here (see above)
The ship is a bulk carrier without ice notations. fj = 1.0
No ice notation fiICE = 1.0
No voluntary structural enhancement for this ship fiVSE = 1.0
The ship has the notation Bulk carrier CSR:
fiCSR = 1 + 0.08*LWTCSR / DWTCSR = 1+0.08*11590/55000 = 1.017
fi = fiICE x fiVSE x fiCSR = 1.017
No ice notation
For attained EEDI calculation under regulation 20 and 21 of
MARPOL Annex VI, fw is 1.0
The ship is a bulk carrier not designed to carry light cargoes, fc = 1.0
For a bulk carrier, Capacity is deadweight = 55 000 tons
At design stage, reference speed is obtained from the towing tank
test report and delivered power in scantling draft (EEDI) condition
is given in table 7.1
In table 7.1 PD = 1.0 x PME = 6900 kW
The reference speed is read on the speed curve corresponding to
table 7.1 at intersection between curve Full, p and 6900 kW
Vref = 14.25 knots
11.2 Result
For this vessel, Attained EEDI is:
Attained EEDI = (6900*3.206*171+381*3.206*199) / (1.017*55000*14.25) = 5.05 g/t.nm
12
Required EEDI
According to MARPOL Annex VI, Chapter 4, Regulation 21, the required EEDI is:
(1-x/100) x reference line value
The reference line value = a*b-c where a, b, c are given for a bulk carrier as:
a= 961.79 b = deadweight of the ship c = 0.477
So reference line value = 5.27 g/t.nm
Page 41 of 74
2020 Industry Guidelines for calculation and verification of EEDI
In Phase 0 (between 1 Jan 2013 and 31 Dec 2014) above 20000 DWT, x = 0
So Required EEDI = 5.27 g/t.nm
Figure 12.1 provides the relative position of attained EEDI with reference to required value.
As a conclusion, for this vessel:
●
attained EEDI = 5.05 g/t.nm
●
required EEDI = 5.27 g/t.nm
●
Regulation criteria is satisfied with 4.2% margin
Figure 12.1: Required EEDI value
13
Calculation of attained EEDIweather
Not calculated.
14
Lightweight check report
The lightweight check report is provided in annex 6. The final characteristics of the ship are:
Displacement
Lightweight
Deadweight
15
66171 tons
11621 tons
54550 DWT
Sea trial report with corrections
The sea trial report is provided in annex 7. The results of the sea trial follow the
assessment guideline of ISO 15016:2015 are given on curve Ballast,s on Figure 3.1.
Page 42 of 74
2020 Industry Guidelines for calculation and verification of EEDI
16
Calculation of attained EEDI at final stage
16.1 Recalculated values of parameters
The EEDI quantities and intermediate calculations are listed in table 16.1. Parameters which
have not been modified from the preliminary verification stage are marked “no change”.
Table 16.1: Parameters in attained EEDI calculation (final stage)
EEDI
quantity
CFME
PME
SFCME
CFAE
PPTI
PAE
Value
Remarks
3.206
6900 kW
171 g/kWh
3.206
0
381 kW
SFCAE at
75% MCR
Peff
PAEeff
feff
fj
fi
199 g/kWh
No change
No change
No change
No change
No change
The electric power table has been validated and endorsed (see
the electric power table form in annex 8)
No change
fc
fm
Capacity
1.0
1.0
54550 DWT
Vref
14.65 knots
0
0
1.0
1.017
No change
No change
No change
No change
Deadweight and lightweight are computed from lightweight check:
fiCSR = 1 + 0.08*LWTCSR / DWTCSR = 1+0.08*11621/54550 = 1.017
fi = fiICE x fiVSE x fiCSR = 1.017 (unchanged)
No change
No change
Deadweight has been computed from the lightweight check. See
14.
The reference speed in EEDI condition has been adjusted
according to the delivered power adjustment methodology defined
in Industry Guidelines.
The reference speed is read on the speed curves diagram in
Figure 3.1
Vref = 14.65 knots
16.2 Final result
Attained EEDI = (6900*3.206*171+381*3.206*199) / (1.017*54550*14.65) = 4.95 g/t.nm
Required EEDI in Phase 0: 961.79*54550-0.477 = 5.29 g/t.nm
Regulation criteria is satisfied with 6.4% margin
Page 43 of 74
2020 Industry Guidelines for calculation and verification of EEDI
List of annexes to the Document
Annex 1
Standard model-ship extrapolation and correlation method
Annex 2
Towing tank tests report
Annex 3
Ship lines and offsets table
Annex 4
Description of energy saving equipment
Annex 5
5.1 NOx Technical File of main engine(s)
5.2 NOx Technical File of auxiliary engines
Annex 6
Lightweight check report
Annex 7
Sea trials report
Annex 8
EPT-EEDI form
Page 44 of 74
2020 Industry Guidelines for calculation and verification of EEDI
APPENDIX 3
Verifying the calibration of model test equipment
Quality Control System
The existence of a Quality Control System is not sufficient to guarantee the correctness of the
test procedures; QS, including ISO 9000, only give documentary evidence what is to be and
has been done. Quality Control Systems do not evaluate the procedures as such.
The Test institute should have a quality control system (QS). If the QS is not certified ISO
9000 a documentation of the QS should be shown. A Calibration Procedure is given in ITTC
Recommended Procedures 7.6-01-01.
1.
Measuring Equipment
An important aspect of the efficient operation of Quality System according to measuring
equipment is a full identification of devices used for the tests.
Measuring equipment instruments shall have their individual records in which the following
data shall be placed:
- name of equipment
- manufacturer
- model
- series
- laboratory identification number ( optionally)
- status ( verified, calibration, indication )
Moreover the information about the date of last and next calibration or verification shall be
placed on this record. All the data shall be signed by authorised officer.
2.
Measuring Standards
Measuring standards used in laboratory for calibration purposes shall be confirmed (verified)
by Weights and Measures Office at appropriate intervals (defined by the Weights and
Measures Office).
All measuring standards used in laboratory for the confirmation purposes shall be supported
by certificates, reports or data sheets for the equipment confirming the source, uncertainty
and conditions under which the results were obtained.
3.
Calibration
The calibration methods may differ from institution to institution, depending on the particular
measurement equipment. The calibration shall comprise the whole measuring chain (gauge,
amplifier, data acquisition system etc.).
The laboratory shall ensure that the calibration tests are carried out using certified measuring
standards having a known valid relationship to international or nationally recognised
standards.
a)
Calibration Report
“Calibration reports” shall include:
Page 45 of 74
2020 Industry Guidelines for calculation and verification of EEDI
b)
identification of certificate for measuring standards
description of environmental conditions
calibration factor or calibration curve
uncertainty of measurement
minimum and maximum capacity” for which the error of measuring instrument is
within specified (acceptable) limits.
Intervals of Confirmation
The measuring equipment (including measuring standards) shall be confirmed at appropriate
(usually periodical) intervals, established on the basis of their stability, purpose and wear. The
intervals shall be such that confirmation is carried out again prior to any probable change in
the equipment accuracy, which is important for the equipment reliability. Depending on the
results of preceding calibrations, the confirmation period may be shortened, if necessary, to
ensure the continuous accuracy of the measuring equipment.
The laboratory shall have specific objective criteria for decisions concerning the choice of
intervals of confirmation.
c)
Non - Conforming Equipment
Any item of measuring equipment
-
that has suffered damage,
that has been overloaded or mishandled,
that shows any malfunction,
whose proper functioning is subject to doubt,
that has exceeded its designated confirmation interval, or
the integrity of whose seal has been violated, shall be removed from service by
segregation, clear labelling or cancelling.
Such equipment shall not be returned to service until the reasons for its nonconformity have
been eliminated and it is confirmed again.
If the results of calibration prior to any adjustment or repair were such as to indicate a risk of
significant errors in any of the measurements made with the equipment before the calibration,
the laboratory shall take the necessary corrective action.
4.
Instrumentation
Especially the documentation on the calibration of the following Instrumentation should be
shown.
a)
Carriage Speed
The carriage speed is to be calibrated as a distance against time. Period between the
calibrations is to be in accordance with the internal procedure of the towing tank test
organisation.
b)
Water Temperature
Measured by calibrated thermometer with certificate (accuracy 0.1°C).
c)
Trim Measurement
Calibrated against a length standard. Period between the calibrations is to be in accordance
with the internal procedure of the towing tank test organisation.
d)
Resistance Test
Page 46 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Resistance Test is a force measurement. It is to be calibrated against a standard weight.
Calibration normally before each test series.
e)
Propulsion Test
During Self Propulsion Test torque, thrust and rate of revolutions are measured. Thrust and
Torque are calibrated against a standard weight. Rate of revolution is normally measured by
a pulse tachometer and an electronic counter which can be calibrated e.g. by an oscillograph.
Period between the calibrations is to be in accordance with the internal procedure of the
towing tank test organisation.
f)
Propeller Open Water Test
During Propeller Open Water Test torque, thrust and rate of revolutions are measured. Thrust
and Torque are calibrated against a standard weight. Rate of revolution is normally measured
by a pulse tachometer and an electronic counter which can be calibrated e.g. by an
oscillograph.
Period between the calibrations is to be in accordance with the internal procedure of the
towing tank test organisation.
Examples of documentation sheets are given in the Annexes 1 and 2:
Page 47 of 74
2020 Industry Guidelines for calculation and verification of EEDI
ANNEX 1: SAMPLE OF MEASURING EQUIPMENT CARD
QM
4.10.5.1
Measurement Equipment Card
Equipment
Manufacturer
Serial No.
Laboratory
Identification
Number
Model
Date of Purchase
Basic range
Status
Calibrated
Indication
Verified
Work Instructions
Calibration Instructions
Verified at
Date of
Check
Certificate.
No.
Period
Date of Next
Check
Page 48 of 74
Responsible
Department
Approval
2020 Industry Guidelines for calculation and verification of EEDI
ANNEX 2: SAMPLE OF CALIBRATION CERTIFICATE.
QM
4.10.6.2
NO.
CALIBRATION CERTIFICATE
for
LIN
PROPELLER
Calibration Instructions
Calibrated by :
Date of calibration
Checked by :
Measurement combination
DYNAMOMETER
Manufacturer
Model
Serial No
Date of purchased
Work instruction
Last calibration
AMPLIFIER
Manufacturer
Model
LIN
Serial No
Date of purchased
Work instruction
Type of transducer
Excitation
Frequency of excit.
Amp. gain
Zero not load
LIN
Cable
Thrust :
Torque :
Amp. gain
Zero not load
Cable
A/C TRANSDUCER
LIN
MEASUREMENT
STANDARDS
Manufacturer
Model
Serial No
Date of purchased
Work instruction
Certificate No
Mass
Certificate No
Length arm of force
Certificate No
Voltmeter
Certificate No
Page 49 of 74
2020 Industry Guidelines for calculation and verification of EEDI
QM
4.10.6.2
CALIBRATION RESULTS
Environmental condition
Place of test :
Temperature :
initial
final
Dampness :
initial
final
Computation results of calibrations test
Executed program
procedure
certificate NO.
Thrust
Torque
Drift :
Non Linearity errors :
Hysteresis :
Precision errors :
Total uncertainty :
Calibration factor :
Calibration requests :
Specified limits of
Thrust
Torque
errors :
Maximum capacity :
Minimum capacity :
Note : tests and computations results are included in report
Prepared by : ....................... Approved by : ....................... Date : ...................
Page 50 of 74
2020 Industry Guidelines for calculation and verification of EEDI
APPENDIX 4
Review and witnessing of model test procedures
The Model Tests are to be witnessed by the verifier. Special attention is to be given to
the following items:
1.
Ship Model
Hydrodynamic Criteria
a)
Model Size: The model should generally be as large as possible for the size of the
towing tank taking into consideration wall, blockage and finite depth effects, as well as
model mass and the maximum speed of the towing carriage (ITTC Recommended
Procedure 7.5-02-02-01 Resistance Test).
b)
Reynolds Number: The Reynolds Number is to be, if possible, above 2.5x 105.
c)
Turbulence Stimulator: In order to ensure turbulent flow, turbulence stimulators have to
be applied.
Manufacture Accuracy
With regard to accuracy the ship model is to comply with the criteria given in ITTC
Recommended Procedure 7.5-01-01-01, Ship Models.
The following points are to be checked:
a)
Main dimensions: LPP, B.
b)
Surface finish: Model is to be smooth. Particular care is to be taken when finishing the
model to ensure that geometric features such as knuckles, spray rails, and boundaries
of transom sterns remain well-defined.
c)
Stations and Waterlines: The spacing and numbering of displacement stations and
waterlines are to be properly defined and accurately marked on the model.
d)
Displacement: The model is to be run at the correct calculated displacement. The
model weight is to be correct to within 0.2% of the correct calculated weight
displacement. In case the marked draught is not met when the calculated displacement
has been established the calculation of the displacement and the geometry of the
model compared to the ship has to be revised. (Checking the Offsets).
Documentation in the report
Identification (model number or similar)
Materials of construction
Principal dimensions
Length between perpendiculars (LPP)
Length of waterline (LWL)
Breadth (B)
Draught (T)
For multihull vessels, longitudinal and transverse hull spacing
Design displacement (Δ) (kg, fresh water)
Page 51 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Hydrostatics, including water plane area and wetted surface area
Details of turbulence stimulation
Details of appendages
Tolerances of manufacture
2.
Propeller Model
The Manufacturing Tolerances of Propellers for Propulsion Tests are given IN ITTC
Recommended Procedures 7.5-01-01-01, Ship Models Chapter 3.1.2. Attention: Procedure
7.5 – 01-02-02 Propeller Model Accuracy is asking for higher standards which are applicable
for cavitation tests and not required for self-propulsion tests.
Propeller Model Accuracy
Stock Propellers
During the “stock-propeller” testing phase, the geometrical particulars of the final design
propeller are normally not known. Therefore, the stock propeller pitch (in case of CPP) is
recommended to be adjusted to the anticipated propeller shaft power and design propeller
revolutions. (ITTC Recommended Procedure 7.5-02-03-01.1 Propulsion/Bollard Pull Test).
Adjustable Pitch Propellers
Before the Tests the pitch adjustment is to be controlled.
Final Propellers
Propellers having diameter (D) typically from 150 mm to 300 mm is to be finished to the
following tolerances:
Diameter (D) ± 0.10 mm
Thickness (t) ± 0.10 mm
Blade width (c) ± 0.20 mm
Mean pitch at each radius (P/D): ± 0.5% of de-sign value.
Special attention is to be paid to the shaping accuracy near the leading and trailing edges of
the blade section and to the thickness distributions. The propeller will normally be completed
to a polished finish.
Documentation in the report
Identification (model number or similar)
Materials of construction
Principal dimensions
Diameter
Pitch-Diameter Ratio (P/D)
Expanded blade Area Ratio (AE/A0)
Thickness Ratio (t/D)
Hub/Boss Diameter (dh)
Tolerances of manufacture
3.
Model Tests
a)
Resistance Test
The Resistance Test is to be performed acc. to ITTC Recommended Procedure 7.5-02-02-01
Resistance Test.
Documentation in the report
Model Hull Specification:
Page 52 of 74
2020 Industry Guidelines for calculation and verification of EEDI
-
Identification (model number or similar)
Loading condition
Turbulence stimulation method
Model scale
Main dimensions and hydrostatics (see ITTC Recommended Procedure 7.5-01-0101 Ship Models and chapter 2 of this paper).
Particulars of the towing tank, including length, breadth and water depth
Test date
Parametric data for the test:
- Water temperature
- Water density
- Kinematic viscosity of the water
- Form factor (even if (1+k) =1.0 is applicable, this is to be stated)
- ΔCF or CA
For each speed, the following measured and extrapolated data is to be given as a minimum:
- Model speed
- Resistance of the model
- Sinkage fore and aft, or sinkage and trim
b)
Propulsion Test
The Propulsion Test is to be performed acc. to ITTC Recommended Procedure 7.5-02-0301.1 Propulsion Test/Bollard Pull.
Documentation in the report
Model Hull Specification:
- Identification (model number or similar)
- Loading condition
- Turbulence stimulation method
- Model scale
- Main dimensions and hydrostatics (see ITTC Recommended Procedure 7.5-01-0101 Ship Models and chapter 2 of this paper).
Model Propeller Specification:
- Identification (model number or similar)
- Model Scale
- Main dimensions and particulars (see ITTC Recommended Procedure 7.5-01-01-01
Ship Models and chapter 3 of this paper)
Particulars of the towing tank, including length, breadth and water depth
Test date
Parametric data for the test:
- Water temperature
- Water density
- Kinematic viscosity of the water
- Form factor (even if (1+k) = 1.0 is applicable, this is to be stated)
- ΔCF or CA
- Appendage drag scale effect correction factor (even if a factor for scale effect
correction is not applied, this is to be stated).
For each speed the following measured data and extrapolated data is to be given as a
minimum:
- Model speed
- External tow force
- Propeller thrust,
- Propeller torque
Page 53 of 74
2020 Industry Guidelines for calculation and verification of EEDI
- Rate of revolutions.
- Sinkage fore and aft, or sinkage and trim
- The extrapolated values are also to contain the resulting delivered power PD.
c)
Propeller Open Water Test
In many cases the Propeller Open Water Characteristics of a stock propeller will be available
and the Propeller Open Water Test need not be repeated for the particular project. A
documentation of the Open Water Characteristics (Open Water Diagram) will suffice.
In case of a final propeller or where the Propeller Open Water Characteristics is not available
the Propeller Open Water Test is to be performed acc. to ITTC Recommended Procedure
7.5-02-03-02.1 Open Water Test.
Documentation in the report
Model Propeller Specification:
- Identification (model number or similar)
- Model scale
- Main dimensions and particulars (see recommendations of ITTC Recommended
Procedure 7.5-01-01-01 Ship Models and chapter 3 of this paper)
- Immersion of centreline of propeller shaft in the case of towing tank
Particulars of the towing tank or cavitation tunnel, including length, breadth and water depth
or test section length, breadth and height.
Test date
Parametric data for the test:
- Water temperature
- Water density
- Kinematic viscosity of the water
- Reynolds Number (based on propeller blade chord at 0.7R)
For each speed the following data is to be given as a minimum:
- Speed
- Thrust of the propeller
- Torque of the propeller
- Rate of revolution
- Force of nozzle in the direction of the propeller shaft (in case of ducted propeller)
Propeller Open Water Diagram
Page 54 of 74
2020 Industry Guidelines for calculation and verification of EEDI
4.
Speed Trial Prediction
The principal steps of the Speed Trial Prediction Calculation are given in ITTC
Recommended Procedure 7.5 - 02 - 03 -1.4 ITTC 1978 Trial Prediction Method (in its latest
reviewed version of 2017). The main issue of a speed trial prediction is to get the loading of
the propeller correct and also to assume the correct full scale wake. The right loading of the
propeller can be achieved by increasing the friction deduction by the added resistance (e.g.
wind resistance etc.) and run the self-propulsion test already at the right load or it can be
achieved by calculation as given in Procedure 7.5-02-03-1.4.
A wake correction is always necessary for single screw ships. For twin screw ships it can be
neglected unless the stern shape is of twin hull type or other special shape.
The following scheme indicates the main components of a speed trial prediction. It is to be
based on a Resistance Test, a Propulsion Test and an Open Water Characteristics of the
used model propeller during the tests and the Propeller Open Water Characteristics of the
final propeller.
Documentation
Model Hull Specification:
- Identification (model number or similar)
- Loading condition
- Turbulence stimulation method
- Model scale
- Main dimensions and hydrostatics (see ITTC Recommended Procedure 7.5-01-0101 Ship Models and chapter 2 of this paper).
Model Propeller Specification:
- Main dimensions and particulars (see ITTC Recommended Procedure 7.5-01-01-01
Ship Models and chapter 3 of this paper)
Particulars of the towing tank, including length, breadth and water depth
Resistance Test Identification (Test No. or similar)
Propulsion Test Identification (Test No. or similar)
Open Water Characteristics of the model propeller
Open Water Characteristics of ship propeller
Ship Specification:
- Projected wind area
- Wind resistance coefficient
- Assumed BF
- CP and Cn
Page 55 of 74
2020 Industry Guidelines for calculation and verification of EEDI
For each speed the following calculated data is to be given as a minimum:
- Ship speed
- Model wake coefficient
- Ship wake coefficient
- Propeller thrust on ship
- Propeller torque on ship
- Rate of revolutions on ship
- Predicted power on ship (delivered power on Propeller(s) PD)
- Sinkage fore and aft, or sinkage and trim
Page 56 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Scheme for review and witnessing Model Tests
Page 57 of 74
2020 Industry Guidelines for calculation and verification of EEDI
APPENDIX 5
Sample report “Preliminary Verification of EEDI”
ATTESTATION
PRELIMINARY VERIFICATION OF ENERGY EFFICIENCY DESIGN INDEX (EEDI)
by VERIFIER
Statement N° EEDI/YYYY/XXX
Ship particulars:
Ship Owner:
Shipyard:
Ship's Name:
IMO Number:
Hull number:
Building contract date:
Type of ship:
Port of registry:
Deadweight:
Summary results of EEDI
Reference speed
Attained EEDI
Required EEDI
VV.V knots
X.XX g/t.nm
Y.YY g/t.nm
Supporting documents
Title
EEDI Technical File
ID and/or remarks
RRRR dated DD/MM/YYYY
This is to certify:
1 That the attained EEDI of the ship has been calculated according to the 2018
Guidelines on the method of calculation of the attained Energy Efficiency Design
Index (EEDI) for new ships, IMO resolution MEPC.308(73) as amended.
2 That the preliminary verification of the EEDI shows that the ship complies with the
applicable requirements in regulation 20 and regulation 21 of MARPOL Annex VI
as amended.
Completion date of preliminary verification of EEDI: xx/xx/xxxx
Issued at:
on:
Signature of the Verifier
Page 58 of 74
2020 Industry Guidelines for calculation and verification of EEDI
APPENDIX 6
Sample calculations of EEDI
Content
Appendix 6.1: Cruise passenger ship with diesel-electric propulsion
Appendix 6.2: LNG carrier with diesel-electric propulsion
Appendix 6.3: Diesel-driven LNG carrier with re-liquefaction system
Appendix 6.4: LNG carrier with steam turbine propulsion
Page 59 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Appendix 6.1
Sample calculation for diesel-electric cruise passenger ship
1.
Preliminary calculation of attained EEDI at design stage
Attained EEDI for cruise passenger ship having diesel electric propulsion system is calculated
as follows at design stage.
For a diesel-electric cruise passenger ship:
PME = 0, PPTI ≠0, PPTO = 0
1)
Input
The table below lists the input information needed at the design stage and verified at the final
stage:
Symbol
MPP
ηPTI
ηGEN
HLOADMax
SFCAE
GT
Name
Rated output of
electric propulsion
motors
Efficiency of
transformer +
converter +
propulsion motor at
75% of rated motor
output
Power-weighted
average efficiency
of generators
Consumed electric
power excluding
propulsion in cruise
most demanding
conditions
Power-weighted
average of specific
oil consumption
among all engines
at 75% of the MCR
power
Gross Tonnage
Value
2 x 20000
kW
Source
From EEDI technical file
0.945
From electric power table
0.974
15 779 kW
Calculation from individual generator
efficiencies given in electric power table:
0.975*19000+0.972*14000/(14000+19000)
From electric power table for the most
demanding cruise contractual conditions
(here extreme summer conditions 28°C
during 80% of the time)
185 g/kWh
From NOx technical file
160000
ums
From EEDI technical file
MCR of auxiliary diesel engines
19,000 kW x 2 + 14,000 kW x 2
MPP
20,000 kW x 2
SFCAE recorded in the test report annexed to the NOx technical file at 75% of MCR power
and corrected to the ISO standard reference conditions.
185 g/kWh for both types of engines (19,000 kW and 14,000 kW)
2)
Calculation of ∑PPTI
The input is the rated output of the electric propulsion motors, MPP, which can be identified
with the quantity noted PPTI,Shaft in 2.2.5.3 of the “2018 guidelines on the method of calculation
of the attained energy efficiency design index (EEDI) for new ships”.
The term PPTI is then computed as follows:
Page 60 of 74
2020 Industry Guidelines for calculation and verification of EEDI
∑ 0.75 𝑀𝑃𝑃 𝑖
𝜂
𝜂
2 0.75 20,000
0.945 0.974
𝑃
𝑃
𝑃
32,593𝑘𝑊
Where ηPTI is the chain efficiency of the transformer, frequency converter and electric motor,
as given by the manufacturer at 75% of the rated motor output and ηGen is the weighted
average efficiency of the generators.
3)
Value of PAE
PAE is estimated by the consumed electric power, excluding propulsion, in most demanding
(i.e. maximum electricity consumption) cruise conditions as given in the electric power table
provided by the submitter, divided by the average efficiency of the generators.
The most demanding conditions maximise the design electrical load and correspond to
contractual ambient conditions leading to the maximum consumption off heating ventilation
and air conditioning systems, in accordance with Note 3 of the “2018 guidelines on the
method of calculation of the attained energy efficiency design index (EEDI) for new ships”.
In this example, the most demanding condition corresponds to extreme summer conditions,
where the external air temperature is 28°C during 80% of the time.
𝐻𝐿𝑂𝐴𝐷
𝜂
15,779𝑘𝑊
0.974
16,200𝑘𝑊
𝑃
4)
Vref at EEDI condition
Vref is obtained by the preliminary speed-power curves as the model tank test results at EEDI
condition at design stage. Suppose that Vref of 22.5 kn is obtained at 75% of MPP, in this
example calculation at design stage.
5)
Calculation of the attained EEDI at design stage
EEDI is calculated in accordance with paragraph 2 of the “2018 guidelines on the method of
calculation of the attained energy efficiency design index (EEDI) for new ships”. The primary
fuel is marine Gas Oil in this example.
EEDI 

( PAE   PPTI (i ))  C FAE  SFC AE 
i
Capacity  Vref
(16200  32593)  185  3.206
 8.04
160,000(UMS )  22.5(kn)
2.
Final calculation of attained EEDI at sea trial
Attained EEDI at sea trial of cruise passenger ship having diesel electric propulsion system is
calculated as follows.
Page 61 of 74
2020 Industry Guidelines for calculation and verification of EEDI
1)
Typical configuration and example of measurement points at sea trial
2)
Specifications
Chain efficiency of the electric motor ηPTI and generator efficiency ηGen can be confirmed
during the sea trials at EEDI conditions (i.e. 75% of the rated motor output) taking into
account the power factor cosφ of the electric consumers.
SFCAE is computed form the NOx technical file if this file was not available at the preliminary
stage.
Gross tonnage is confirmed at 160,000 ums.
Prior to sea trials, an on-board survey is performed to ensure that data read on the
nameplates of the main electrical pieces of equipment comply with those recorded in the
submitted electric power table.
3)
Vref at EEDI condition
Vref is obtained by the speed-power curves as a result of the sea trial in accordance with the
paragraph 4.3.9 of “2014 guidelines on survey and certification of the energy efficiency
design index (EEDI)” as amended. Suppose that Vref of 18.7kn is obtained at 75% of MPP, in
this example calculation at sea trial.
During the sea trials, the shaft power transferred to the propellers PPTI,Shaft must be obtained. It
could be measured by a torsiometer fitted on the propeller shaft, or obtained from the
computation of the power consumption of the motor PSM through the following relation:
𝑃 ,
𝑃
𝜂
4)
Calculation of the attained EEDI at sea trial
EEDI is calculated in accordance with paragraph 2 of the “2018 guidelines on the method of
calculation of the attained energy efficiency design index (EEDI) for new ships”. The primary
fuel is marine Gas Oil in this example.
Page 62 of 74
2020 Industry Guidelines for calculation and verification of EEDI
EEDI 

( PAE   PPTI (i ))  CFAE  SFC AE 
i
Capacity  Vref
(16200  32593)  185  3.206
 7.97
160,000(UMS )  22.7(kn)
Page 63 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Appendix 6.2
Sample calculation for LNG carrier having diesel electric propulsion system
1.
Preliminary calculation of attained EEDI at design stage
Attained EEDI for LNG carrier having diesel electric propulsion system at design stage is
calculated as follows.
1)
Specifications
MCR of main engines
10,000 (kW) x 3 + 6,400 (kW) x 1
MPPMotor
24,000 (kW)
SFCME(i)_electric, gas mode at 75% of MCR
162.0 (g/kWh) (for 10,000 (kW)-Engines) (SFC with the addition of
the guarantee tolerance)
162.6 (g/kWh) (for 6,400 (kW)-Engine) (Ditto)
SFCME(i)_Pilotfuel
6.0 (g/kWh) (for 10,000 (kW)-Engines), 6.1 (g/kWh) (for 6,400
(kW)-Engine)
Deadweight
75,000 (ton)
2)
ηelectrical at design stage
ηelectrical is set as 0.913 in accordance with paragraph 2.2.5.1 of the “2018 guidelines on
the method of calculation of the attained energy efficiency design index (EEDI) for new
ships”.
3)
Calculation of PME
PME is calculated in accordance with paragraph 2.2.5.1 of the “2018 guidelines on the
method of calculation of the attained energy efficiency design index (EEDI) for new ships”.
𝑀𝑃𝑃
0.83
𝑃
𝜂
24,000
0.83
21,818 𝑘𝑊
0.913
4)
Calculation of PAE
PAE is calculated in accordance with paragraph 2.2.5.6.1 and 2.2.5.6.3 of the “2018 guidelines
on the method of calculation of the attained energy efficiency design index (EEDI) for new
ships”.
𝑃
0.025
𝑀𝐶𝑅
𝑃
𝐶𝑎𝑟𝑔𝑜𝑇𝑎𝑛𝑘𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦
0.33
0.02
𝑆𝐹𝐶
0.75
𝐵𝑂𝑅
𝐶𝑂𝑃
𝑅
𝑃
1000
,
1 𝑎𝑛𝑑 ⁄𝑜𝑟, 𝑁𝑜𝑡 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑙𝑒
2 𝑎𝑛𝑑 ⁄𝑜𝑟 , 𝑁𝑜𝑡 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑙𝑒
3
𝑃𝑀𝐸
0.025 24,000
1,286 𝑘𝑊
𝑎𝑛𝑑 ⁄𝑜𝑟 ,
250
250
0
0
0.02
21,818
Page 64 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Note:
*1: The value of MPPMotor is used instead of MCRME in accordance with paragraph 2.2.5.6.3.3.
5)
Vref at EEDI condition
Vref is obtained by the preliminary speed-power curves as the model tank test results at EEDI
condition at design stage. Suppose that Vref of 18.4kn is obtained at 83% of MPPMotor, in this
example calculation at design stage.
6)
Calculation of the attained EEDI at design stage
EEDI is calculated in accordance with paragraph 2 of the “2018 guidelines on the method of
calculation of the attained energy efficiency design index (EEDI) for new ships”. The primary
fuel is LNG in this example calculation. In this case, SFCAE(i)_electric, gas mode at 75% of MCR is equalto
SFCME(i)_electric, gas mode at 75% of MCR, and SFCAE(i)_Pilotfuel is equal to SFCME(i)_Pilotfuel.
EEDI 

PME  C FME _ Gas  SFC ME _ Gas  C FME _ Pilotfuel  SFC ME _ Pilotfuel   PAE  C FAE _ Gas  SFC AE _ Gas  C FAE _ Pilotfuel  SFC AE _ Pilotfuel
Capacity  Vref
21,818  2.750  162 .1  3.206  6 .0 +1,286  2.750  162 .1  3.206  6.0 
 7 .79
75 ,000 (DWT)  18 .4(kn)
Note:
*1: The average weighed value of SFCME(i)_electric, gas mode at 75% of MCR and SFCAE(i)_electric, gas mode
at 75% of MCR is used;
162.010,000(kW)3162.66,400(kW)
10,000(kW)36,400(kW)
*2:
 162.1(g/kWh)
The average weighed value of SFCME(i)_Pilotfuel and SFCAE(i)_Pilotfuel is used;.
6.010, 000(kW)3 6.16, 400(kW)
 6.0(g/kWh)
10, 000(kW)3 6, 400(kW)
2.
Final calculation of attained EEDI at sea trial
Attained EEDI for LNG carrier having diesel electric propulsion system at sea trial is
calculated as follows.
1)
Typical configuration and example of measurement points at sea trial
Page 65 of 74

2020 Industry Guidelines for calculation and verification of EEDI
2)
Specifications
MCR of main engines
10,000 (kW) x 3 + 6,400 (kW) x 1
24,000 (kW)
MPPMotor
SFCME(i)_electric, gas mode at 75% of MCR
161.6 (g/kWh) (for 10,000 (kW)-Engines) (SFC of the test report in
the NOx technical file)
162.2 (g/kWh) (for 6,400 (kW)-Engine) (Ditto)
SFCME(i)_Pilotfuel
6.0 (g/kWh) (for 10,000 (kW)-Engines), 6.1 (g/kWh) (for 6,400
(kW)-Engine)
Deadweight
75,500 (ton)
3)
ηelectrical at sea trial
ηelectrical is set as 0.913 in accordance with paragraph 2.2.5.1 of the “2018 guidelines on
the method of calculation of the attained energy efficiency design index (EEDI) for new
ships”.
4)
Calculation of PME
PME is calculated in accordance with paragraph 2.2.5.1 of the “2018 guidelines on the
method of calculation of the attained energy efficiency design index (EEDI) for new ships”.
𝑀𝑃𝑃
𝑃
0.83
𝜂
24,000
21,818 𝑘𝑊
0.83
0.913
5)
Calculation of PAE
PAE is calculated in accordance with paragraph 2.2.5.6.1 and 2.2.5.6.3 of the “2018 guidelines
on the method of calculation of the attained energy efficiency design index (EEDI) for new
ships”.
𝑃
0.025
𝑀𝐶𝑅
𝑃𝑇𝐼 𝑖
𝐶𝑎𝑟𝑔𝑜𝑇𝑎𝑛𝑘𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦
0.33
𝑆𝐹𝐶
0.02
𝑃
0.025
24,000
𝐵𝑂𝑅
0.75
𝐶𝑂𝑃
250
𝑅
𝑃
1000
,
𝑎𝑛𝑑 ⁄𝑜𝑟;
… 1 𝑎𝑛𝑑 ⁄𝑜𝑟; 𝑁𝑜𝑡 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑙𝑒
… 2 𝑎𝑛𝑑 ⁄𝑜𝑟; 𝑁𝑜𝑡 𝐴𝑝𝑝𝑙𝑖𝑐𝑎𝑏𝑙𝑒
… 3
250
0
0
0.02
21,818
1,286 𝑘𝑊
Note:
*1: The value of MPPMotor is used instead of MCRME in accordance with paragraph 2.2.5.6.3.4
6)
Vref at EEDI condition
Vref is obtained by the speed-power curves as a result of the sea trial in accordance with
paragraph 4.3.9 of the “2014 guidelines on survey and certification of the energy efficiency
design index (EEDI)” as amended. Suppose that Vref of 18.5kn is obtained at 83% of
MPPMotor, in this example calculation at sea trial.
Page 66 of 74
2020 Industry Guidelines for calculation and verification of EEDI
7)
Calculation of the attained EEDI at sea trial
EEDI is calculated in accordance with paragraph 2 of the “2018 guidelines on the method of
calculation of the attained energy efficiency design index (EEDI) for new ships”. The primary
fuel is LNG in this example calculation. In this case, SFCAE(i)_electric, gas mode at 75% of MCR is equal to
SFCME(i)_electric, gas mode at 75% of MCR, and SFCAE(i)_Pilotfuel is equal to SFCME(i)_Pilotfuel.
EEDI 

PME  C FME _ Gas  SFCME _ Gas  C FME _ Pilotfuel  SFCME _ Pilotfuel   PAE  C FAE _ Gas  SFC AE _ Gas  C FAE _ Pilotfuel  SFC AE _ Pilotfuel 
Capacity  Vref
21,818  2.750  161.7  3.206  6.0+1,286  2.750  161.7  3.206  6.0
 7.67
75,500(DWT)  18.5(kn)
Note:
*1: The average weighed value of SFCME(i)_electric, gas mode at 75% of MCR and SFCAE(i)_electric, gas mode
at 75% of MCR is used;.
161.610,000(kW)3162.26,400(kW)
10,000(kW)36,400(kW)
 161.7(g/kWh)
*2: The average weighed value of SFCME(i)_Pilotfuel and SFCAE(i)_Pilotfuel is used;
6.010, 000(kW)36.16, 400(kW)
 6.0(g/kWh)
10, 000(kW)36, 400(kW)
Page 67 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Appendix 6.3
Sample calculation for LNG carrier having diesel driven with re-liquefaction system
1.
Preliminary calculation of attained EEDI at design stage
Attained EEDI for LNG carrier having diesel driven with re-liquefaction system at design stage
is calculated as follows.
1)
Specifications
MCR ME(i)
18,660 x 2 (kW) = 37,320 (kW)
SFCME(i)_at 75% of MCR
165.0 (g/kWh)
SFCAE(i)_at 50% of MCR
198.0 (g/kWh)
211,900 (m3)
CargoTankCapacityLNG
BOR
0.15 (%/day)
COPcooling
0.166
15.142
COPreliquefy
425 𝑘𝑔⁄𝑚
511 𝑘𝐽⁄𝑘𝑔
15.142
𝐶𝑂𝑃
24 ℎ
3600 𝑠𝑒𝑐
𝐶𝑂𝑃
Rreliquefy
Deadweight
2)
1
109,000 (ton)
Calculation of PME
PME is calculated in accordance with paragraph 2.2.5.1 of the “2018 guidelines on the
method of calculation of the attained energy efficiency design index (EEDI) for new ships”.
PME (i)  0.75  MCRME (i )
 0.75  18,660  18,660  27,990(kW)
3)
Calculation of PAE
PAE is calculated in accordance with paragraph 2.2.5.6.1 and 2.2.5.6.3 of the “2018 guidelines
on the method of calculation of the attained energy efficiency design index (EEDI) for new
ships”.
PAE = 0.025 x Σ0.0ME(i) + 250
+ CargoTankCaipacityLNG x BOR x COPreliquefy x Rreliquefy
= 0.025 x 37,320 +250
+ 211,900 x 0.15/100 x 15.142 x 1
= 5,996 (kW)
4)
Vref at EEDI condition
Vref is obtained by the preliminary speed-power curves as the model tank test results at EEDI
condition at design stage.
Suppose that Vref of 19.7kn is obtained at 75% of MCRME(i), in this example calculation at
design stage.
5)
Calculation of the attained EEDI on design stage
EEDI is calculated in accordance with paragraph 2 of the “2018 guidelines on the method of
calculation of the attained energy efficiency design index (EEDI) for new ships”.
Page 68 of 74
2020 Industry Guidelines for calculation and verification of EEDI
EEDI 
PME  CFME  SFCME  PAE  CFAE  SFC AE
Capacity Vref
27,990  3.206 165.0+5,996  3.206 198.0

 8.668
109,000(DWT) 19.7(kn)
2.
Final calculation of attained EEDI at sea trial
Attained EEDI for LNG carrier having diesel driven with re-liquefaction system at sea trial is
calculated as follows.
1)
Specifications
MCR ME(i)
SFCME(i)_at 75% of MCR
SFCAE(i)_at 50% of MCR
CargoTankCapacityLNG
BOR
COPcooling
COPreliquefy
COPreliquefy 
18,660 x 2 (kW) = 37,320 (kW)
165.5 (g/kWh)
198.5 (g/kWh)
211,900 (m3)
0.15 (%/day)
0.166
15.142
425 (kg / m3 )  511 (kJ / kg )
 15.142
24 (h)  3600 (sec)  COPcooling
Rreliquefy
Deadweight
1
109,255 (ton)
SFCME(i)_at 75% of MCR and SFCAE(i)_at 50% of MCR are in accordance with paragraph 2.2.7.1 of the
“2018 guidelines on the method of calculation of the attained energy efficiency design index
(EEDI) for new ships”.
Deadweight is in accordance with paragraph 4.3.10 of the “2014 guidelines on survey and
certification of the energy efficiency design index (EEDI)” as amended.
2)
Measured values at sea trial
Relation between SHPseatrial and Ship’s speed shall be measured and verified at sea trial.
3)
Calculation of PME
PME is calculated in accordance with paragraph 2.2.5.1 of the “2018 guidelines on the
method of calculation of the attained energy efficiency design index (EEDI) for new ships”.
PME (i)  0.75  MCRME (i )
 0.75  18,660  18,660  27,990(kW)
4)
Calculation of PAE
PAE is calculated in accordance with paragraph 2.2.5.6.3.1 of the “2018 guidelines on the
method of calculation of the attained energy efficiency design index (EEDI) for new ships”.
PAE = 0.025 x Σ0.0ME(i) + 250
+ CargoTankCaipacityLNG x BOR x COPreliquefy x Rreliquefy
= 0.025 x 37,320 +250
+ 211,900 x 0.15/100 x 15.142 x 1
= 5,996 (kW)
Page 69 of 74
2020 Industry Guidelines for calculation and verification of EEDI
5)
Vref at EEDI condition
Vref is obtained by the speed-power curves as a result of the sea trial in accordance with
paragraph 4.3.9 of the“2014 guidelines on survey and certification of the energy efficiency
design index (EEDI)” as amended.
Suppose that Vref of 19.8kn is obtained at 75% of MCRME(i), in this example calculation at sea
trial.
6)
Calculation of the attained EEDI at sea trial
EEDI is calculated in accordance with paragraph 2 of the “2018 guidelines on the method of
calculation of the attained energy efficiency design index (EEDI) for new ships”.
EEDI 
PME  CFME  SFCME  PAE  CFAE  SFC AE
Capacity Vref
27,990  3.206 165.5+5,996  3.206 198.5

 8.629
109,255(DWT) 19.8(kn)
Page 70 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Appendix 6.4
Sample calculation for LNG carrier having steam turbine propulsion system
1.
Preliminary calculation of attained EEDI at design stage
Attained EEDI for LNG carrier having steam turbine propulsion system at design stage is
calculated as follows.
1)
Specifications
MCRSteam turbine
SFCSteam turbine
Deadweight
2)
25,000 (kW)
241.0 (g/kWh)
75,000 (ton)
Calculation of PME
PME is calculated in accordance with paragraph 2.2.5.1 of the“2018 guidelines on the method of
calculation of the attained energy efficiency design index (EEDI) for new ships”.
PME  0.83  MCRSteamTurbine
 0.83  25,000  20,750(kW)
3)
Calculation of PAE
PAE is treated as 0(zero) because electric load (Pgenerator_seatrial) is supposed to be included in
SFCSteamTurbine, in accordance with paragraph 2.2.5.6.5 and 2.2.7.2.1 of the “2018 guidelines
on the method of calculation of the attained energy efficiency design index (EEDI) for new
ships”.
PAE = 0
4)
Vref at EEDI condition
Vref is obtained by the preliminary speed-power curves as the model tank test results at EEDI
condition at design stage.
Suppose that Vref of 18.7kn is obtained at 83% of MCRSteamTurbine, in this example calculation
at design stage.
5)
Calculation of the attained EEDI on design stage
EEDI is calculated in accordance with paragraph 2 of the “2018 guidelines on the method of
calculation of the attained energy efficiency design index (EEDI) for new ships”.
The primary fuel is LNG in this example calculation.
EEDI 
PME  CFME  SFCME  PAE  CFAE  SFC AE
Capacity Vref
20,750  2.750  241.0+0

 9.81
75,000(DWT) 18.7(kn)
2.
Final calculation of attained EEDI at sea trial
Attained EEDI for LNG carrier having steam turbine propulsion system at sea trial is
calculated as follows.
Page 71 of 74
2020 Industry Guidelines for calculation and verification of EEDI
1)
Typical configuration and example of measurement points at sea trial
In addition to the above, in order to correct measured Fuel Consumption to the design
conditions corresponding to the SNAME condition, inlet air temperature, sea water
temperature, steam temperature, steam pressure, etc. are measured, as appropriate.
PAE is treated as 0(zero) because electric load (Pgenerator_seatrial) is supposed to be included in
SFCSteamTurbine, in accordance with paragraph 2.2.5.6.5 and 2.2.7.2.1 of the “ 2018 guidelines
on the method of calculation of the attained energy efficiency design index (EEDI) for new
ships”.
2)
Specifications
MCRSteam turbine
SFCSteam turbine
Deadweight
3)
25,000 (kW)
241.0 (g/kWh)
75,000 (ton)
Measured values at sea trial
P generator_seatrial
980 (kW)
SHPseatrial
21,520 (kW)
Fuel Consumption_seatrial 5.95 x 106 (g/hour)
Each Fuel Consumption(j)_seatrial should be corrected in accordance with paragraph 2.2.7.2 of
the “2018 guidelines on the method of calculation of the attained energy efficiency design
index (EEDI) for new ships”.
Coefficient of flow meter
Steam temperature
Steam pressure
1.0010
500 degree Celsius
5.85 (MPaG)
Page 72 of 74
2020 Industry Guidelines for calculation and verification of EEDI
Condenser vacuum
725 (mmHg)
Dist. water production
28.5 (t/day)
Inlet air temperature of FAN
45 degree Celsius
Lower calorific value of fuel used at sea trial 42,030 (kJ/kg)
4)
Calculation of SFCSteamTurbine at sea trial
SFCSteamTurbine is calculated in accordance with paragraph 2.2.7.2 of the “2018 guidelines on the
method of calculation of the attained energy efficiency design index (EEDI) for new ships”.
SFC SteamTurbi ne _ seatrial (i ) 
FuelConsum ption _ Seatrial
SHPseatrial

*1
5.95  106 
 C 1  C 2  C 3  C 4  C 5  C 6  C 7
21,520


5.95  106 
 0.9871 0.8756  1.0010  1.0001  1.0035
21,520
 0.9999  1.0028
 240.7 (g/kW/h)
Note:
*1: SFC should be corrected to the value corresponding to SNAME and EEDI conditions, in
accordance with paragraph 2.2.7.2 .2 and .3 of the “2018 guidelines on the method of
calculation of the attained energy efficiency design index (EEDI) for new ships”.
Coefficients from C1 to C7 represent as follows.
C1: Coefficient of electric power to the electric load equivalent to
PAE = 0.025 x MCRSteam turbine + 250 = 875 (kW)
C2: Coefficient of LCV to the standard LCV of 48,000 kJ/kg for LNG fuel
C3: Coefficient of flow meter
C4: Coefficient of steam temperature and steam pressure
C5: Coefficient of condenser vacuum for steam turbine
C6: Coefficient of water feed of condenser
C7: Coefficient of inlet air temperature
SFCSteamTurbine is calculated as the value to include all losses of machinery and, gears
necessary for main propulsion system and the specified electric load of PAE.
Minimum two SFCSteamTurbine at around the EEDI power are obtained at the sea trial. However
in this example calculation, all SFCSteamTurbine (i) are supposed to the same value of 240.7
g/kWh.
5)
Calculation of PME
PME is calculated in accordance with paragraph 2.2.5.1 of the “2018 guidelines on the
method of calculation of the attained energy efficiency design index (EEDI) for new ships”.
PME  0.83  MCRSteamTurbine
 0.83  25,000  20,750(kW)
Page 73 of 74
2020 Industry Guidelines for calculation and verification of EEDI
6)
Calculation of PAE
PAE is treated as 0(zero) because electric load (Pgenerator_seatrial) is supposed to be included in
SFCSteamTurbine, in accordance with paragraph 2.2.5.6.5 and 2.2.7.2.1 of the “2018 guidelines
on the method of calculation of the attained energy efficiency design index (EEDI) for new
ships”.
PAE = 0
7)
Vref at EEDI condition
Vref is obtained by the speed-power curves as a result of the sea trial in accordance with
paragraph 4.3.9 of the “2014 guidelines on survey and certification of the energy efficiency
design index (EEDI)” as amended.
Suppose that Vref of 18.8kn is obtained at 83% of MCRSteamTurbine, in this example calculation
at sea trial.
8)
Calculation of the attained EEDI at sea trial
EEDI is calculated in accordance with paragraph 2 of the “2018 guidelines on the method of
calculation of the attained energy efficiency design index (EEDI) for new ships”.
The primary fuel is LNG in this example calculation.
EEDI 
PME  CFME  SFCME  PAE  CFAE  SFC AE
Capacity Vref
20,750  2.750  240.7+0

 9.74
75,000(DWT) 18.8(kn)
End of
Document
Page 74 of 74
Download