Uploaded by Jaycee Pagador

420707109-Jha-Tree-Cutting-Felling-Balling-v-2

advertisement
Job Hazard Analysis
Job Description:
TREE CUTTING, FELLING & BALLING
Start Date:
Finish Date:
Task to be accomplished (Mga dapat gawin)
Steps To Take To
Complete Task
(Mga Hakbang
upang
makumpleto ang
gawain)
MOBILIZATION OF
EQUIPMENT &
MATERIALS
Hazards
(Mga Panganib)
-Falling
(Materials fall down)
and Tossing of Objects &/or
Debris
-Ground full of debris
RESULTS:
People: sprain, strain, laceration
Adjacent Properties / Job
Process:
- Disruption, Disturbed quality living
of adjacent properties/neighborhood/
business
'- Slip & trips
- fall into the ground
- being trapped
HAULING JOBS
(MANUAL
HANDLING)
RESULTS:
People: sprain, strain, laceration
Adjacent Properties / Job
Process:
Disruption, Disturbed quality living
of adjacent properties/neighborhood/
business
Cracks, loose soils
Prolonged work execution
Required Actions To Eliminate Or
Control The Hazard
(Mga aksyon upang maalis o makontrol ang
panganib)
-
Provision of enough signages to guide the
workers about the hazards & control to be
made including the correct access
locations
-
Ensure assigned safety man to focus on
Safety Control only
-
Barricade possible extent of working and
affected area
-
Ensure back up of housekeeping team to
help during activity execution - maintain
extent of affected area to prevent
additional hazards to others
-
Assess initially the path needed to take
before handling a material
-
Eliminate and control any possible
obstruction before and during the activity
-
Provide a guide / spotter if necessary
If obstructions are structures, ensure to be
familiar to the path to eliminate additional
risk
Train the workers for proper manual
hauling technique
Identify the weight of the materials to be
hauled do tandem lift if necessary
-
Page: 1 of 7
Job Hazard Analysis
HEAVY
EQUIPMENT and
OTHER
EQUIPMENT
OPERATIONS
- Hit by/hit against
- Struck by/struck against
- Contact with Machinery
- Caught into
- Run over by
RESULTS: Body Injury, Death
PEOPLE: contusion, fracture,
laceration, avulsion, death
- Fall
- Hit against
- Struck into
ELEVATED JOBS
-
Ensure a good equipment condition to
minimize the produced by products
-
Exposure of personnel should be
minimized
-
Presence of available spare parts and
servicing personnel
-
Ensure that all workers have reflectorized
vest especially the Rigger and to give
proper signaling,
-
Ensure that the Rigger are trained and
knowledgeable
-
Don't go under the boom when the crane is
operating wait for the signal of Rigger and
Spotter
-
Set up guidelines for elevated works
applicable to the actual condition
-
Availability of materials for fall prevention
control
-
Trained individual to be involved in the job
-
Do not store Equipment on working
platforms. Area below must clear from
personnel. Working platform must have
handrails and edge protection
-
Set up exclusion zone, barricade the area,
put enough signage and observed 100 % tie
off
RESULTS:
contusion, fracture, avulsion, death
MATERIAL/ADJACENT
PROPERTIES: rupture, vent,
cracks, scratches
Page: 2 of 7
Job Hazard Analysis
'- Electrocution
- Physical Injuries
- Electrical Shock
- Trip, Slip, Fall
- Cut
RESULTS:
People: sprain, strain, laceration,
Fatality
Adjacent Properties / Job Process:
- Disruption, Disturbed quality living
of adjacent properties/neighborhood/
business
- Prolonged work execution
REMOVAL OF
CABLES AND
WIRES/
CONTACT WITH
DOWNED LINES
AND LIVE
ELECTRICAL
EQUIPMENT AND
OTHER UTILITIES
(E.G., GAS,
WATER)
- De-Energized and Lock Out/Tag out
Electrical Circuit/parts you will be working on
- Have an area outline with all the facilities
determined with location - All personnel
involved must have electrical safety/LOTOTO
Training
- Assess initially the path needed to take before
handling a material
Follow permit to work system procedures
- All temporary power supply must be
remove/installed by a competent person
- Personnel shall ensure that suitable PPE's is
worn at all times when handling sharp or
otherwise potentially hazardous materials
- Ensure that a safe system of work is
implemented so as to reduce the possibilities of
accidents/incidents caused by a lack of
communication.
- Ensure that tree trimming operations to clear
electrical lines are performed only by qualified
line-clearance tree trimmers. A qualified lineclearance tree trimmer is knowledgeable in the
construction and operation of electric power
generation, transmission, or distribution
equipment involved, along with the associated
hazards
- Closely inspect trees for electrical conductors
passing through or within reaching distance of
workers before beginning tree work
- Consider all electrical power conductors to be
energized and not to be directly or indirectly
(e.g., through tools, branches, or other
equipment) touched
- Assume that electrical lines are energized
until proven otherwise. Lines and other
conductors may become re-energized without
warning as utilities are evaluated and restored
after a disaster
- Inspect the work area for downed conductors
and do not go near, drive over, or otherwise
come in contact with them
Page: 3 of 7
Job Hazard Analysis
- Downed electrical conductors can energize
other objects, including fences, water pipes,
bushes, trees, and telephone/CATV/fiber optic
cables
- Unless deenergized and visibly grounded,
maintain proper distance from overhead
electrical power lines (at least 10 feet) and/or
provide insulating barriers
- Do not approach any gas leaks; if a gas leak
is detected, secure spark-producing devices
(e.g., engines, tools, electronic, and
communications equipment) and evacuate the
area until the leak is secured
- Contact utility company to assist in locating,
marking, and shutting off/purging utility lines
that may pose a hazard or may be impacted;
ensure that lines have been purged as needed
before beginning work
PREPARATION
FOR TREE
CUTTING/FELLING
/BALLING
-Ground full of debris
- Slips and trips
- Fall (same level of the ground)
- Struck into
RESULTS:
sprain, wounds, bruises,
contusion, abrasion, puncture, stab
wounds
- Provision of enough signages to guide the
workers about the hazards & control to be
made including the correct access locations
- Ensure assigned safety man to focus on
Safety Control only
- Barricade possible extent of working and
affected area
- Ensure back up of housekeeping team to help
during activity execution - maintain extent of
affected area to prevent additional hazards to
others
Page: 4 of 7
Job Hazard Analysis
- Falling into
- Soil Disruption
- Collapse
- Flooding/water penetration
TREE BALLING
EXCAVATION
(MANUAL
EXCAVATION)
RESULTS:
People: soft tissue and bone injuries,
suffocation, death
Material/Adjacent Properties:
mislay foundation
Environment
Unstable ground
- Entasked a competent person to monitor
adjacent area general condition
- Install suitable supports to brace affected
areas, should be designed also by a competent
person
- Advise relative authority regarding possible
extent and phase of the activity
- Install signages informing public about the
activity
- Barricade area/zone of influence
- If necessary, provide walk zone for general
public 1 meter away from the zone of
influence
- Schedule and ensure proper removal of
excavated materials
Page: 5 of 7
Job Hazard Analysis
- Fence the work location to control
the hazards noted; ensure that the
fence compensates with the impact
of the hazard
- Methods of proper demolition
should be ready for discussion during
morning meeting to limit the listed
hazards
- Provision of signages, strategically at the
highly potential areas.
- Install enough fences and provide additional
protection for adjacent properties if necessary
- Issue complete Personal Protective
Equipment for personnel involved and to those
to do inspection from time to time.
- Off-set the highly critical areas from workers
- The fence should be designed to
minimize the environmental impact
affecting near-by structure
-Start saw on ground with foot on rear handle,
left hand firmly gripping saw grip, right hand
pulling starter cord. Maintain secure footing.
- Wear gloves, hard hat, chaps, sturdy work
boots. Saws weighing less than 15 pounds may
be drop started. Make sure, co-workers are
clear of saw.
TREE CUTTING
-Maintain awareness of work areas; check
barricades; do not approach operators; shout
warnings to co-workers and bystanders.
- Control a quality condition of
heavy equipment to use to minimize
the impact
- Properly control the working hours
- Improve process to control both
waste and dust
- Barricade possible entry that is too close to
work condition
- Position signage strategically that it can also
provide proper information to project
personnel and others that may be affected.
- Gather information from general affected
personnel for any schedule that construction
team needs to offset due to the environmental
impact
- Ensure availability of materials & equipment
to haul generated solid waste
- Avoid stock up of generated solid waste
- Use all necessary PPE's against the hazard
Page: 6 of 7
Job Hazard Analysis
-
Personal Injury:
Crushing
Being hit by falling object
Hit by moving vehicle
Slips, trips, falls
Death
-
Prepare tree for felling (cut off low
branches).
-
Ensure no persons in fall area.
-
Use agreed communication (eg: radio, hand
signals and/or whistles).
-
During trimming, keep non-essential
response and recovery workers at least 20
feet beyond expected drop zones during
trimming
-
During felling, designate work area so that
trees cannot fall into an adjacent occupied
work area. Adjacent occupied work areas
should be at least two treelengths from the
tree being felled (allow more if it is
reasonably foreseeable that the tree might roll
or slide)
-
Always plan a clear path of retreat before
cutting
-
Determine the felling direction and how to
deal with forward, back, and/or side lean
-
Determine the proper hinge size to safely
guide the tree in its fall-◾If tree is broken
and under pressure, make sure you know
which way the pressure is going. If not sure,
make small cuts to release some of the
pressure before cutting up the section
-
- Be careful of young trees that other trees
have fallen against; they act like spring poles
and can propel back
-
- If you have to cut a dead tree, be careful:
the top could break off
-
- If possible, avoid felling trees into other
trees or objects; branches and objects may
get thrown back toward the tree cutter
TREE FELLING
Page: 7 of 7
Job Hazard Analysis
- Hit by/Struck by a material
- Caught into/trapped
(from falling debris and/or
something collapsing)
TREE FELLING
RESULTS:
People: contusion, abrasion,
avulsion, laceration, fracture
Materials/Adjacent properties:
cracks, scratches, tear off and breaks,
total wreckage
-
Once back cut taken up and tree begins to
fall: use agreed communication to signal fall
remove saw and switch to off (this allows
operator to hear) move to planned escape
route
-
watch for falling debris
-
watch for kickback/bounce.
-
For much larger trees – use quarter cutting
techniques:
-
cut scarf as normal
-
plan cut (mark felling cuts on map or tree)
-
select side of tree for first cut (if rot or lean
-
If not, do not approach tree in direction of
fall
-
Hung-up:
-
Use machine
-
Do not approach in direction of fall
-
If manually – use can’t hook or levering
device to dislodge.
-
Note: Do not leave trees in cut-up or hung-up
position
unless barricading and clearly signing the
area to prevent persons entering.
'- drop off material
DISPOSAL OF
MATERIALS
- forceful lifting
- Struck by
- Hit by
RESULTS:
People: contusion, abrasion, avulsion,
laceration, fracture
- Identify the weight of the materials to be
hauled
-Ensure equipment use for transferring
materials are in good condition
-Be aware of overhead obstructions & your
surrounding at all times
- Ensure Proper handling of materials
- Keep visual or audio contact with rigger
(pick up & landing points) at all times
Page: 8 of 7
Job Hazard Analysis
(Environmental Impact)
- Dust
- Debris/solid Waste
- Cut tree
DISPOSAL OF
MATERIALS
- Transfer the cut trees at accredited area
endorsed by DENR for proper disposal
- Proper segregation of materials/waste
materials
- Dumped hauled treed on the area approved
by Municipal Government
''- Barricade possible entry that is too close to
work condition
- Position signage strategically that it can also
provide proper information to project
personnel and others that may be affected.
- Gather information from general affected
personnel for any schedule that construction
team needs to offset due to the environmental
impact
- Ensure availability of materials & equipment
to haul waste
- Avoid stock up of waste
- Use all necessary PPE's against the hazard
Post Work
-
Poor materials arrangement slips
and trip. Hand injury &
ergonomic injuries
-
Good housekeeping shall perform before,
during and after. Ensure workers must have
complete Protective equipment.
Page: 9 of 7
Job Hazard Analysis
This JHA must be reviewed with all workers involved prior to starting any work.
(Bago umpisahan ang anumang trabaho, ang JHA na ito ay dapat masuri kasama ang lahat ng
manggagawa
Work Supervisor: ALFRED PATI-AN/ROEFI COLIMA/ABAD
MIRHAN/JOANNABLE SALALILA
Workers:
JOEY CARANES
MARK JOHN DELA CRUZ
ERSON RIVAS
ESON MINGOY
_
MAR BENHUR SAULOG
Page: 10 of
7
Download