Uploaded by Kristal Marie Morales

Lecture Note 4b. DPWH Standard

advertisement
Construction Materials
and
Testing
CE23
DPWH Standards in testing
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
1. Cement
MNIMUM TESTING
REQUIREMENTS
1 sample per 2000 bags
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
10 kg
10 kg
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
2. Asphaltic material
MNIMUM TESTING
REQUIREMENTS
1 sample per 40T or 200 drums
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
5L
5L
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
3. Aspahlt mix
MNIMUM TESTING
REQUIREMENTS
1 sample per 130T
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
20 kg
20 kg
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
4. Aggregates
a. coarse aggregate
b. fine aggregate
MNIMUM TESTING
REQUIREMENTS
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
1 sample per 1,500 m3
70 kg
50 kg
70 kg
50 kg
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
5. Soil aggregates
a. Classification
b. Routinary tests
c. MDR test and CBR
MNIMUM TESTING
REQUIREMENTS
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
1 sample per 1,500 m3
20 kg
50 kg
50 kg
20 kg
50 kg
50 kg
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
6. Non – Reinforced Concrete Pipes
MNIMUM TESTING
REQUIREMENTS
2 pipes min./0.5% of no. of
pipes
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
2 pipes
2 pipes
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
7. Reinforced Concrete Pipes
MNIMUM TESTING
REQUIREMENTS
1 sample per 50 pipes or 2% of
# of pipes
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
1 pipe (1 m length)
1 pipe
(1m length)
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
8.Steel pipe (galvanized)
MNIMUM TESTING
REQUIREMENTS
1 sample per 500 lengths
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
2 pcs Of 100 mm long taken from both
ends w/ thread
2 pcs
(100mm length)
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
9. Concrete hollow blocks (CHB)
a. strength
b. moisture content
MNIMUM TESTING
REQUIREMENTS
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
1 sample per 10,000 units
3 units
3 units
3 units
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
10. Steel bar
MNIMUM TESTING
REQUIREMENTS
1 sample per 10T
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
1m
1 meter
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
11. Steel sheet (galvanized)
MNIMUM TESTING
REQUIREMENTS
1 sample per 100 sheets
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
3 pcs 60mm x 60mm
3 pcs
(60mm x 60mm)
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
12. Wire strand
MNIMUM TESTING
REQUIREMENTS
1 sample per 20T
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
2m
2 meters
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
13. Gabion
MNIMUM TESTING
REQUIREMENTS
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
1m x 2m
1m x 2m
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
14. Paints
MNIMUM TESTING
REQUIREMENTS
1 sample per 100 cans
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
1 - 4L can
1 – 4liters
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
15. Concrete cylinder
MNIMUM TESTING
REQUIREMENTS
1 sample per 75 m3
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
1 set (3 cylinders)
1 set (3 cylinders)
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
16. Concrete beam
MNIMUM TESTING
REQUIREMENTS
1 sample per 75 m3 or 1
day pouring
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
1 set (3 beams)
1 set (3 beams)
DPWH MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
MATERIALS
MNIMUM TESTING
REQUIREMENTS
17. Joint – filler (pre – molded)
18. Curing compound
MINIMUM QUANTITY/VOLUME OF
MATERIALS FOR EACH SAMPLE
SUBMITTED
1 – 400mm x 400mm
1L
19. Concrete core
5 holes for every km/lane
20. Asphalt core
1 core for every 100m
DPWH COMPOSITION AND STRENGTH OF CONCRETE FOR USE IN STRUCTURE
Class of
concrete
Minimum
cement
content per
cu. m
kg (bags)
Maximum
water –
cement ratio
kg/kg
Consistency
range in
slump
mm (inch)
A
360 (9)
0.53
50 -100 (2 – 4)
B
320 (8.5)
0.58
50 -100 (2 – 4)
C
380 (9.5)
0.55
50 -100 (2 – 4)
P
440 (11)
0.49
Seal
380 (9.5)
0.58
100 max ( 4
max)
100 – 200 (4 –
8)
Minimum
Designated compressive
size of coarse strength of
aggregate
150mm x
300mm
square
concrete
opening –
cylinder @
28 days
std. mm
MN/m2 (psi)
37. 5 – 4.75 (1
20.7 (3000)
½ - No. 4)
50.0 – 4.75 (2
16.5 (2400)
- No. 4)
12. 5 – 4.75
20.7 (3000)
(½ - No. 4)
19.0 – 4.75
37. 7 (5000)
(3/4 - No. 4)
25.0 – 4.75 (1
20.7 (3000)
- No. 4)
DPWH PAYMENT ADJUSTMENT FOR PAVEMENT WITH DEFICIENCY IN
STRENGTH
Deficiency in strength of
concrete pavement
Percent (%)
Less than 5
5 to less than 10
10 to less than 15
15 to less than 20
20 to less than 25
25 or more
Percent (%) of
contract price
allowed
100
80
70
60
50
0
DPWH PAYMENT ADJUSTMENT FOR PAVEMENT WITH DEFICIENCY IN
THICKNESS
Deficiency in the
average thickness
per lot(mm)
0–5
Percent (%) of
contract price
per lot
100
6 – 10
95
11 – 15
85
16 – 20
70
21 – 25
50
more than 25
removed and replaced (no
payment)
DPWH COMMON LABORATORY TESTS
Kind of material
Type of test
Cement
Coarse aggregate
Physical and chemical
Grading
Specific gravity
Absorption
Abrasion
Unit weight
Test duration per sample (min. # of
days)
8
3
3
3
1
1
Fine aggregate
Grading
Specific gravity
Absorption
Unit weight
3
3
3
1
Soil aggregates mixture (subbase,
base and surfaces courses
Grading
3
Liquid limit
Plastic limit
Compaction
CBR
Abrasion
3
3
3
7
1
DPWH COMMON LABORATORY TESTS
Kind of material
Type of test
Asphalt
Paint
Physical
Physical and chemical
Test duration per sample (min. # of
days)
4
4
Concrete cylinder
Compressive
1
Concrete beam
Flexural
1
Concrete core
Cutting of sample
1
DPWH REMOVAL OF FORMS
Scope of work
Centering under
girders, beams,
frames or arches
Floors slabs
Walls
Columns
Sides of beams and
all other vertical
surfaces
Minimum time
Minimum % of
design strength
14 days
80%
14 days
1 day
2 days
70%
70%
70%
1 day
70%
DPWH MINIMUM LAP FOR SPLICING
GRADE 40
GRADE 60
Tension
24 times bar Ø
36 times bar Ø
Compression
20 times bar Ø
24 times bar Ø
References
DPWH Standard Specifications for Public Works and Highway (2004 edition), Volume II
Youtube Links for Testing
1. Sieve Analysis: https://www.youtube.com/watch?v=3Xqq1cxhD-s
2. Liquid and Plastic limits: https://www.youtube.com/watch?v=EcXJ961qjGA
3. Compressive Strength for the concrete: https://www.youtube.com/watch?v=6ferJ1OncnQ
4. Hydrometer Test: https://www.youtube.com/watch?v=Yi8wdl5cN9Y
Download